Title: Decommission process
CR Number Current Status
Date
Area Impacted Products Impacted

5582318 Completed
11/14/2001
Pre-Ordering Collocation
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Nelson, Steve
Director:
CR PM:

Description Of Change

Qwest has recently changed their Collocation Decommission Policy. AT&T objects to the fact that Qwest made this process change unilaterally – without the input of AT&T. Objections that AT&T has regarding the new policy are:

·1: A certified letter - stating that either no customers were ever installed in the collo or if customers were installed, AT&T has notified them their service will be disconnected or moved - and a copy of the decommission application must to be sent to the Account Team Representative. Prior to this process change, AT&T was not required to do this. We have processed approximately 10 decommission applications so far this year and have not sent a certified letter for any of them.

Resolution: AT&T wants to send the application via email only as before.

2. The decommission process reads "The completion of a decommission request and 100% payment of any outstanding financial obligation, will terminate the billing of recurring charges for the site." What this means to AT&T is that we should be current on any bills for the collocation we are decommissioning. What this means to Qwest is that if there is any outstanding bills - either non recurring or recurring - due for any collocation in Qwest territory, they will NOT process the decommission application until all bills for all sites are paid. AT&T may incur additional monthly charges for the collocation being decommissioned since the application is on hold.

Resolution: It is AT&T’s request that only the non recurring and recurring bills for the collocation being decommissioned be subject to scrutiny.

3. Since Qwest charges AT&T a flat fee to decommission a site, AT&T has inquired about the possibility of conducting a site visit to ensure that Qwest has completed the decommissioning of the site. Qwest has denied AT&T this final site visit. Although Qwest may disconnect power cables, conduct a site visit and complete database work, they do not actually tear down the actual site. Qwest is hoping to lease the space to another CLEC and will not have to rebuild the space. Qwest assures AT&T that if the space is leased within a year of the decommissioning, AT&T will reimbursed some monies for the collo space.

Resolution: AT&T would like proof that the work has been completed.


Date Action Description
6/6/2001 CR received by Donna Osborne Miller of AT&T 
6/7/2001 Status changed to New – to be evaluated  
6/25/2001 Status changed to Reviewed – Under consideration 
6/25/2001 Revised CR submitted by AT&T 
7/9/2001 Completed Draft Response 
7/12/2001 Drafted Response sent to CICMP team via email (MR) 
7/27/2001 90 day review process for Joint Planning process for Cancel ,Decom and change of Responsibility Offering letter distributed. 
8/9/2001 Proposed meetings for a collaborative re-design of the Collocation Cancellation, Decommission, and Change of Responsibility product offerings began. Meeting notice sent on July 27th with a reminder sent August 6th. 
9/12/2001 Joint planning meeting held, chaired by Steve Nelson 
9/14/2001 AT&T verbal notice received from Sharon Van Meter to not close this CR as the Decommission process is still being worked on. 
9/19/2001 CMP Meeting - Qwest provided status of CLEC meetings to develop the process. 
10/10/2001 Template agreement to be finalized with AT&T, chaired by Steve Nelson. 
10/17/2001 CMP Meeting: Steve Nelson to finalize decommission policies and procedures with CLEC community. No status change. 
10/31/2001 Qwest response submitted to database CLEC Community. 
11/14/2001 CMP Meeting - AT&T moved to "Close" CR. 

Project Meetings

New Interim Procedures to Terminate or Decommission An Existing Collocation Site

As a result of your feedback concerning Qwest’s recently issued Decommission procedures for existing Collocation sites, Qwest is adopting an interim plan for 90 days. During this interim 90-day period, Qwest will hold a series of meetings and conference calls with the industry to develop mutually acceptable procedures to follow concerning this issue. Please review the interim changes and the calendar of meetings below. We sincerely hope that you will participate.

Interim Changes Effective August 9, 2001 • Qwest will no longer issue a Quote of $3455 for each decommission before monthly recurring billing stops.

Qwest is waiving the Decommission Quote charges effective immediately with issuance of this announcement. Future pricing will be reviewed as part of the “Future Procedures Modifications Process” as described below.

• Qwest will credit past decommission quotes paid and any monthly charges paid past the date of acceptance of the valid application. CLECs can contact their Wholesale Project Manager regarding past decommissions processed or currently being processed.

• The vacating CLEC submitting the “Collocation Application for Cancel, Decommission, or Change of Responsibility” will no longer be required to be current on all billing for all collocation sites, including both monthly and non-recurring quotes before Qwest will process a decommission request.

• The interim requirement will state that a CLEC must be current on “all billing for the specific site for which the decommission application is submitted” for Qwest to decommission a site.

• Qwest will no longer require receipt of the quote charges to stop billing. Monthly billing will stop effective with the valid receipt of a decommission application.

• Applications will no longer need to be sent via certified mail for processing. “Electronic submission of requests to decommission a site can be sent to colo@qwest.com”

Future Procedures Modifications Process Qwest intends to issue future procedures that are acceptable to those parties concerned. For Qwest to implement satisfactory procedures, CLEC feedback is needed and valued. At the completion of this joint 90-day effort, the revised product procedures will be priced, and if appropriate, a template offered by Qwest for an amendment to the CLEC/Qwest

Interconnection Agreements. Please join Qwest in participating in the following calendar of meetings. These meetings will be chaired by Steve Nelson, Group Product Manager Collocation. He can be reached on 303-896-6357. Interested CLECs are encouraged to participate.

Kick-off meeting

August 9th, from 9am to 3pm, 1801 California, Executive Conference room, 23rd floor. Conference bridge: 877-542-1778, pass code 6904985.

1. Review existing product offerings and proposed changes, gather information on additional proposed changes, understand all concerns. Here is a brief outline of the discussion: 2. Agree to as many items as possible initially, table for future review those items requiring detailed response, and respond to disputed items by next meeting for resolution. 3. Capture voting record of participants on each issue, and dissenting opinion as agreed to by the team. 4. Prioritization of changes and timelines. 5. Review costing of current products. Items included in the costing model. 6. Discuss how other ILECs handle cancellation, decommission, change of responsibility or network transfer.


CenturyLink Response

"The below response does not include the attachments referenced in the response. Please see the CMP Web Site for complete response to include Cancellation and Decommissioning Procedures"

October 31, 2001 Sharon Van Meter Manager, AT&T 1875 Lawrence St., 10th floor Denver, Colorado 80202

CC: William Campbell Steve Nelson Jane Lacy

This letter is in response to CLEC Change Request Form #5582318, dated June 25, 2001. This Change Request pertains to several issues regarding the Decommission product offering. On July 9th Qwest committed to partnering with the CLEC industry to resolve the issues identified in the Change Request Form specifically referring to decommission procedures. In addition, Qwest expanded this effort to review the product offerings for Cancellation, and Change of Responsibility. Throughout the month of August, September and October representatives from Qwest and the CLEC industry met to review the procedures for administering a Cancellation and Decommission request. The Qwest/CLEC Forum meetings will continue as we work together to revamp the Change of Responsibility product offering procedures. Successful resolution was achieved for those items addressed in the Decommission Change Request Form. Your efforts were instrumental in this partnership effort.

The following is a summary of the issues identified in the Decommission Change Request Form and the resolution for each: AT&T objected to process changes unilaterally without input from AT&T. Qwest committed to participate in a joint effort to review the Cancel, Decommission, and Change of Responsibility product offerings with CLEC industry and met that commitment. AT&T objected to the requirement to submit a certified letter stating that AT&T customers were notified of the disconnect or move. Qwest agreed to modify the process and allow both the application and confirmation notice to be sent electronically to the rfsmet@qwest.com mailbox. AT&T objected to the requirement that 100% payment of any outstanding financial obligation must be met in order to terminate billing of recurring charges. Qwest modified the procedures to state that financial obligations must be met with respect to the collocation site that is being decommissioned only. We further defined the financial obligations to include all non-recurring and monthly recurring charges must not be greater than thirty (30) days past due. AT&T objected to when the monthly recurring charges would cease. Qwest agreed that the billing end date will coincide with the date of a valid Decommission Application submit date. AT&T felt that they should be entitled to some monies for reimbursable elements at the Decommission site. Qwest agreed that a CLEC would be eligible for reimbursement on the re-usable elements for up to one (1) year from the Decommission Application submit date.

The following is the implementation schedule for the revised Cancellation and Decommission procedures: 11/15/01 - CMP Notification 12/01/01 - CLEC Review Period 12/15/01 - Revised Cancellation and Decommission procedures posted on the Collocation PCAT 01/01/02 - Effective date for the revised Cancellation and Decommission procedures

In summary, Qwest believes that we have satisfied your concerns regarding the Decommission and Cancellation procedures and therefore are considering this Change Request closed.

Sincerely,

Steve Nelson Group Collocation Product Manager