Wholesale: Products & Services

All Archived Product/Process CMP's in One File

Open Product/Process CR PC013002-1 Detail

 
Title: Removing Bridge Taps from LADS circuits
CR Number Current Status
Date
Area Impacted Products Impacted

PC013002-1 Denied
3/20/2002
Resale - Private Line
Originator: Worden, Doug
Originator Company Name:
Owner: Houston, Neil
Director:
CR PM:

Description Of Change

Need to have LADS circuits designed with no bridge taps or be able to remove bridge taps.

Modification after Clarification Meeting:

Establish a process to request the removal of bridge-taps.


Status History

01/30/02 - CR Submitted byVanion Inc.

01/30/02 - CR acknowledged by P/P CMP Manager.

02/04/02 - Contacted Doug Worden at Vanion, Inc to schedule meeting time availability for Clarification Meeting.

02/06/02 - Conducted Clarification Meeting with Vanion, Inc.

02/11/02 - Issued Clarification Meeting Minutes to Vanion, Inc.

02/20/02 - CMP Meeting - CLEC Community Clarification held. It was agreed that the CR would move to Evaluation. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/13/02 - Issued Qwest's Draft Response dated March 8, 2002 to Vanion.

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 8, 2002. The participants agreed that the response was a Deny. Qwest to contact Vanion, who was not in attendance, and inform them of their options.

03/22/02 - Formal response dated March 8, 2002 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses.

03/28/02 - Telephone conversation with Doug Worden, Vanion - Qwest advised that the response was a deny and there was an escalation process he could pursue if he wanted. He indicated that he would let the response go and they were looking into other avenues.


Project Meetings

CLEC Change Request Clarification Meeting

February 6, 2002 9:00 a.m. (MT) Conference Call 877-564-8688 PC013002-1, Removing Bridge Taps from LADA Circuits

Attendees:

Ric Martin, Qwest Neil Houston, Qwest Jeff Cook, Qwest Cindy Buckmaster, Qwest (Part Time) Steve Kast, Qwest (Follow-up conference call) Doug Worden, Vanion, Inc.

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change Doug advised that on LADA Circuits, which are for low speed data, but can handle high speed they want the ability to request the removal of bridge taps is requested. Doug clarified that LADA was 2-wire dry pair cable. Qwest indicated that this was data/data non-load service. It was clarified that this was for point to point service passing through the same wire center. Doug indicated that he had no way to order repair and provided an example of where Qwest moved a pedestal and added a bridge-tap, which has disrupted a customer’s service. Doug clarified that for this service Vanion was reselling Private Line services for High-Speed data. He also indicated that Vanion was also a Facility Based CLEC. Cindy Buckmaster joined the call and explained the Line Condition that can be ordered for UBL. However, she indicated that we need to review what was offered for Resale Qwest unable to bring Freddie Pennington, Wholesale Product Manager for Resale, into the call. Qwest indicated that they would coordinate internally and may get Doug back on an additional clarification meeting. Doug indicated that it was OK to have the CR follow the normal process, but wanted Qwest to investigate his trouble ticket CD328473 which was closed and was escalated. Doug advised that Steve Kast, Vanion Service Manager, was involved. Qwest advised that if they caused the problem and were responsible to fix it, they would look into it further. Note: it was clarified further with Doug Worden, Steve Kast and Ric Martin that Qwest was not committing to correcting the problem, but would look into it further to see if there was anything else that could be done.

Confirm Areas & Products Impacted It was confirmed that the product was for Resold Private Line . Confirm Right Personnel Involved Network personnel would be involved, but it was agreed that Process person should be the Owner. Qwest will coordinate.

Identify/Confirm CLEC’s Expectation It was confirmed that Vanion was looking for a process to request the removal of a bridge tap.

Identify any Dependent Systems Change Requests None

Establish Action Plan (Resolution Time Frame) Qwest will look into the Trouble Ticket Qwest will coordinate internal reviews of the CR.


CenturyLink Response

March 8, 2002

Vanion, Inc. Doug Worden Provisioning Manager

SUBJECT: Qwest’s Change Request Response - CR #PC013002-1 Removing Bridged Taps from LADS circuits

This letter is in response to Vanion Inc.’s Change Request PC013002-1 requesting a process for CLECs to request the removal of Bridge Taps from Local Area Data Service (LADS) circuits.

Local Area Data Service (LADS) is ordered in the Colorado Tariffs. Specifically LADS is offered in “Private Line Transport, Services Tariff, COLO. P.U.C. No. 19, Section 5.2”. LADS is described in Section 5.2.4, A.:

Service is offered only for balanced transmission of data signals conforming to the signal power limitations and other parameters specified in the applicable Technical Reference. These circuits are furnished on either a two-wire or four-wire basis, over non-loaded, metallic cable facilities.

Note the facility is non-loaded, but no reference is made to Bridged Tap. Additionally Section 5.2.4, C., 4. states:

No repair will be performed to change the electrical characteristics of the circuit, if they are within the parameters specified in the Technical Publication.

The General Regulations section of COLO. P.U.C. No. 19, Section 2.1.8 states:

It is expressly declared that metallic facilities are in continually decreasing supply and the Company is not obligated to continue to provide such facilities. Due to facility rearrangements, continued use of metallic facilities may be denied to existing customers with no obligation on the Company’s part to pay customer rearrangement costs.

As referenced above, Qwest’s Technical Publication 77314, Local Area Data Service (LADS), Issue C, July 2001 supports the Colorado Tariff on LADS. In addition to qualifying the LADS technical parameters, the General Section 1. states:

The customer should also be aware that Qwest has no obligation to continue to provide this service if suitable facilities are no longer available. Non-availability of suitable facilities may be caused by the continuing need to add new central offices and to transfer areas between serving wire centers, and the increasing use of Digital Loop Carrier technology on lines between the serving wire center and customer locations.

Vanion has stated that their high-speed data has deteriorated with changes in Qwest’s Network, allegedly from the addition of bridged tap to the circuit. LADS is not designed for high-speed data transmission and is not dependent upon the absence of bridged tap. As referenced above, in the Colorado Tariff and Technical Publication 77314, facility rearrangements could impact existing service. Also, as long as the service is within its technical parameters, repair is not required and will not be performed.

Qwest offers a variety of Unbundled Loop products that should meet Vanion’s transmission requirements. These include 2/4/ Wire Non-Loaded Loop, Basic ISDN Capable Loop, DS-1 Capable Loop, and the ADSL Qualified Loop.

Qwest will provide Vanion LADS service as described in its tariffs and technical publications. However, since LADS is not a high speed data service, Qwest declines to initiate a process to remove bridged tap from LADS and respectfully denies Vanion, Inc’s change request.

Sincerely,

Neil G. Houston Staff Advocate-Policy & Law Qwest

Cc: Mary Retka Kathleen Lucero Barry Orrel Jamal Boudhaouia


Open Product/Process CR PC061302-1 Detail

 
Title: Process for ordering Megabit DSL service to connect to Mega Central hubs now installed.
CR Number Current Status
Date
Area Impacted Products Impacted

PC061302-1 Denied
8/21/2002
Pre-Ordering, Ordering, Provisioning Private Line (Megabit DSL Lines)
Originator: Worden, Doug
Originator Company Name:
Owner: Van Dusen, Janean
Director:
CR PM:

Description Of Change

Need to be able to order a new line and megabit service on the same order (LSR) and know that the circuit will be conditioned to provide the DSL service. Without having to do line sharing. Especially when the CO offers MegaBit DSL and the customer has existing lines that already qualify for DSL.


Status History

06/12/02 - CR Submitted by Vanion.

06/13/02 - CR acknowledged by P/P CMP Manager.

06/13/02 - Contacted Vanion to coordinate available times for clarification meeting.

06/18/02 - Conducted Clarification Meeting with Vanion, Inc.

06/25/02 - Issued Clarification Meeting minutes to Vanion. Inc.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status "Clarification" was not changed.

08/14/02 - Issued Qwest's Draft Response dated August 12, 2002 to Vanion.

08/21/02 - CMP Meeting - Qwest presented its Draft Response dated August 12, 2002. Vanion was not present. Qwest will confirm deny response with Vanion. Minutes on this CR to be posted to the Project Meetings section.

08/22/02 - Confirmed with Doug Worden that Qwest's response was a deny. He expressed concern that he was really looking for line conditioning on a POTS line before ordering. Ric Martin advised that the response referenced a previous CR for that request, which was denied. He understood Qwest's response.


Project Meetings

08/21/02 August CMP Monthly Meeting Minutes

Qwest advised that since Vanion was not on the call, Qwest would get with Vanion independently to go over the response. Qwest reviewed its draft response with the CLEC participants. Eschelon asked how many calls does the retail customer have to make to get DSL. Qwest advised that one call is made and Qwest follows up with the customer after POTS is in service. Eschelon stated that CLECs do not get a follow-up call and the retail customer doesn’t have to call back to get DSL. Qwest confirmed that comment. Eschelon asked if this was a deny and Qwest confirmed that it was.

07/17/02 - July CMP Meeting Minutes: Vanion had to leave the CMP meeting early and asked that their CR be rolled over to the August CMP meeting for presentation. CR status is clarification.

CLEC Change Request Clarification Meeting

June 18, 2002, 11:30 a.m. (MT) Conference Call 877-564-8688 PC061302-1, Process for ordering Megabit DSL service to connect to Mega Central Hubs now installed.

Attendees: Ric Martin, Qwest Cindy Buckmaster, Qwest Jeff Cook, Qwest Steve Kast, Qwest Doug Worden, Vanion, Inc. Becky Watson, Vanion, Inc.

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Doug reviewed Vanion’s CR. He indicated that they wanted to put in one order (LSR) for Megabit DSL service and POTS. Becky clarified that Vanion was not collocated in Qwest facilities and was not interested in the Line Sharing product. They wanted to order on the customer’s behalf. They would like to order a 1FB with DSL. They want to be able to take the customer out of dealing with Qwest. Becky indicated they currently can’t offer the DSL product because it’s a moving target on whether facilities would be available. Cindy indicated that data would not be available only if the facility can’t support it. Becky confirmed they were only interested carrying data and having Qwest as the voice provider. Cindy clarified that Vanion is looking to be able to provision the POTS circuit on copper cable versus pair gain capable to allow data service.

Confirm Areas & Products impacted It was confirmed that the area impacted was Pre-Ordering, Ordering and Provisioning. The product impacted are Resale POTS and Megabit DSL.

Confirm Right Personnel Involved Qwest indicated that they would need to include their Resale SMEs, Janean Van Dusen and Stacy Hartman.

Identify/Confirm CLEC’s Expectation Vanion’s expectation is to be able to place one LSR and be able to provision DSL on the POTS line ordered.

Identify any Dependent Systems Change Requests There are no related Systems CRs. Qwest advised that there was a similar CR issued by Eschelon, PC122701-2. Qwest requested Vanion to review the Archive Interactive Report for the CR and Qwest’s response.

Establish Action Plan (Resolution Time Frame) The CR will have the collective CLEC clarification and SME input at the July CMP meeting.


CenturyLink Response

August 12, 2002

Doug Worden Provisioning Manager Vanion, Inc.

SUBJECT: Qwest’s Change Request Response - CR #PC061302-1 Process for ordering Megabit DSL service to connect to Mega Central hubs now installed

This letter is in response to Vanion’s Change Request PC061302-1 requesting that they be allowed to place one LSR and be able to provision DSL on the POTS line ordered.

Vanion’s Change Request is similar to two (2) previously submitted Change Requests, PC122701-1, Qwest to offer line conditioning to qualify a loop for Qwest resale DSL service, and PC122701-2, Qwest to allow 1FB POTS and DSL on one LSR.

Qwest’s response to the two previous Change Requests was that basically the service was not offered to Qwest Retail customers and, therefore, was not going to be offered to Resale customers. Qwest’s responses to each CR can be reviewed in Qwest’s Product/Process CR Archive Report located at URL http://www.qwest.com/wholesale/cmp/archive.html. After additional review, Qwest’s position remains the same. It is not technically and economically feasible for Qwest Retail to offer this service at this time. Qwest does not offer pre-qualification of facilities for DSL prior to the end user’s line being in place. Current process for Retail and Resale is that two (2) orders must be issued. One (1) for the POTs and one (1) for the DSL once the POTS line is loop qualified.

At last month's CMP meeting, there was a question on the Retail process for ordering POTS and DSL. The Retail process does require 2 orders, whether it is an N (new) order or a T (transfer) order. If the end user is interested in DSL, then after the N or T order is installed, a Loop qualification is done on the N (telephone number) or the T (telephone number) and the end user is contacted to place the 2nd order, which would be a C (change) order to add the DSL service.

Sincerely,

Janean Van Dusen (801) 239-4305

Cc:


Open Product/Process CR PC062602-2 Detail

 
Title: Rejects on CLEC to CLEC Reuse of Facilities orders for no circuit IDs found
CR Number Current Status
Date
Area Impacted Products Impacted

PC062602-2 Completed
4/15/2009
Ordering, Provisioning LNP, Unbundled Loop, UNE, Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Urevig, Russell
Director:
CR PM: Thomte, Kit

Description Of Change

While there is a process in place to be able to submit CLEC to CLEC reuse of facilities orders without providing circuit ID information, 90% of the orders submitted by Allegiance since late May 2002 are being rejected for various erroneous and invalid reasons regarding the circuit ID information. While working through these rejected orders with Russ Urveig, it was discovered that the process currently in place for Qwest’s SDCs to find working circuits needs to be redesigned, job aides need to be changed, and the SDCs need more training. While Allegiance received rejects for “no working circuits at end user address”, “unable to validate address to find circuits that are working”, and “these numbers on this LSR are ported to XXX Company” – Russ was able to locate working, reusable UNE DS0 Circuits.

While some of the rejects proved out that there were no reusable UNE DS0 circuits, the reject reasons did not clearly state the true circumstances. For example one reject stated “no working circuits found”. When further researched, it was found that there were indeed working circuits there but the only working circuits for the End User were DS1s.

Allegiance would also like to collaboratively work with Qwest and other CLECs to establish clear, definitive reject reasons for CLEC to CLEC reuse of facilities orders to insure that all resources available to the SDCs have been utilized to find working circuits. When Allegiance submits CLEC to CLEC reuse of facilities orders, we already have obtained a CSR from the CLEC so we know the numbers we are porting are indeed working on some kind of circuit. These reject reasons should be clear enough to insure the CLEC that there are indeed no working UNE DS0 circuits to reuse. As stated above some of the orders rejected did indeed have available working UNE DSO circuits that could be reused. Allegiance currently does not have confidence that the SDC’s reject reasons are valid and their training is adequate to locate reusable UNE DS0 circuits. In many instances we are having to drop new loops in order to take the customer when there are reusable loops available. Installing new loops is more expensive, more time consuming for the cut over, and there is the risk the orders will be held for lack of facilities. The ability to “reuse” facilities is less expensive, the cut over process is less time consuming, and the end user has less down time.

Expected Deliverable:

Clear, definitive reject reasons that the CLECs can rely on that all resources were utilized to “find” working UNE DS0 circuits for CLEC to CLEC reuse of facilities orders.


Status History

06/26/02 - CR Submitted by Allegiance.

06/26/02 - CR acknowledged by P/P CMP Manager

06/28/02 - CR Posted to Web

07/01/02 - Clarification meeting scheduled

07/03/04 - Clarification meeting held

07/10/02 - Meeting minutes distributed to Allegiance

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status remains as "Clarification"

08/06/02 - Held additional session with Allegiance regarding comment and scenarios associated with reject reasons

08/14/02 - Sent Draft Response to Allegiance

08/21/02 - August CMP Meeting - Meeting minutes posted to this CR's Project Meetings section and the CMP Web site. The CR status changed to "CLEC Test"

09/18/02 - September CMP Meeting - Status remains as "CLEC Test" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

10/03/02 - Contacted Alex with Allegiance to inform him of action item that Allegiance had from the September Product and Process meeting.

10/16/02 -October CMP Meeting: This CR will remain in "CLEC Test" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site. Approval given to close this off line with concurrence from Lori at Allegiance.

10/18/02 - Contacted Allegiance to follow up on potential closure of this CR.

10/23/02- Received message from Allegiance that this CR could be closed based on information that Lori had received from within Allegiance.


Project Meetings

Qwest requested that Allegiance research to determine if Allegiance personnel is receiving the comments that were agreed to. Attendees agreed that this could be closed off line if Allegince (Mendoza) agreed.

09/18/02 September CMP Meeting The improved comments associated with rejects on CLEC to CLEC Reuse of Facilities were implemented on August 23. The response indicated it was implemented on August 22. Qwest will update the status history to reflect the actual date. Allegiance (Wicks) indicated they were unaware that the process was underway, Terry will check with his people to find out. Eschelon (Johnson) indicated they had encountered a couple of problems with the process, Russ worked through these issues for them. This CR will remain in “CLEC Test” until the October meeting when it is anticipated that the CR will be updated to "Completed."

- 08/21/02 - August CMP Meeting Minutes Qwest (Urevig) reviewed the three scenarios and comments that are associated with the reject reasons. Allegiance (Wicks) inquired about the second scenarios comments. Are they intended to be two separate or one comment? Qwest indicated that they are two distinct comments. This CR was moved to "CLEC Test".

"Wicks, Terry" , Kathleen Thomte/Mass/USWEST/US@USWEST cc: Cheri Hurless/GROUPWARE/USWEST/US@USWEST

Subject: CR

I wanted to get back to you with the different type of comments we are looking at placing on the rejected CLEC to CLEC migrations request, during our last meeting we determined there were 4 different types of rejects which would require different comment.

1. Wrong type of circuit being requested does not match what was requested by CLEC. 2. Multiple circuits at customer location not all circuits being migrated. 3. No circuits found for migration 4. CLEC to CLEC reuse of facility show detail of which CLEC migration is from (This is probably going to be included in the first scenario).

These are the scenarios and the comments that will reject will contain, I combined the 2 and 3

1. When Qwest finds the circuit at the requested address is NOT the same type of circuit to which the migrate has been requested, the comment remark associated with this will read: Circuits at request address do not match the type of circuit indicated on the LSR for migration. The circuits found are (ex. LX-N or AD--, HCE-, etc)

2. Multiple circuits are found at the requested address, if the number of circuits at the address do NOT match the number of migrations indicated on the LSR. It is very important that the CLEC indicate who the OLSP (old local service provider) is when requesting migration because this will aid in determining whether multiple circuits are really an issue. Qwest will provide these comment remarks for the reject: Multiple circuits have been identified at request address, circuits are currently not those of the indicated OLSP or Multiple circuit have been identified for the OSLP but do not match the number of loops requested for migration.

3. Qwest has searched all available records to identify circuits at end user address, but was NOT able to identify circuit for migration. Qwest will review all data on LSR to obtain circuits to be migrated. Additional data that is recommended to aid in the migration request are: the TN that is being ported to the NLSP’s (new local service provider) switch and the name of the OLSP. If Qwest can NOT find the circuits, the following comment remarks will be provided on the reject: Qwest has search for circuits at the requested address, using the end user name, address, OLSP, and TN provided. Qwest can not find circuits please verify data on LSR for accuracy.

If these cover additional comments or consistent comments will help the CLEC determine the reason for the reject I will place these into the Job aid for Migration then cover this with the SDC's, coaches, SME's and SDC to make sure everyone has the same understanding.

If you have any comments or concerns maybe we can talk or discuss this at the next CMP meeting.

August 12, 2002

Terry Wicks Allegiance Russ Urevig Qwest Kit Thomte Qwest

Notes from follow up meeting: PC062602-2 Rejects on CLEC to CLEC Reuse of Facilities order for no Circuit Ids found. Qwest agreed to hold follow up meeting to collaborate with Allegiance regarding comments associated with reject reasons.

The team agreed that Russ would put together proposed comments for Terry to review. The group also agreed to talk through on the call what the 3-4 scenarios are that exist that could drive the comments.

1. Wrong type of circuit being requested does not match what was requested by CLEC. 2. Multiple circuits at customer location not all circuits being migrated. 3. No circuits found for migration 4. CLEC to CLEC reuse of facility show detail of which CLEC migration is from (This is probably going to be included in the first scenario).

The team agreed that Russ would put together scenarios and new comments for Terrys review.

07/17/02 - July CMP Meeting Minutes: Allegiance (Wicks) reviewed the CR and indicated that his representatives were not using the prescribed process. When analyzed he discovered that the reject reasons did not really make sense. Through discussions with Qwest it appeared that our SDC need access to a special database. Qwest and Allegiance will review the reject reasons to help clarify them. Qwest will provide an initial response prior to the August meeting. This CR will carry a “Clarification” status

Date: July 3, 2002 Place: 1005 17th St Room 1770-C Call-In No.: 877 550-8686 PC062602-2 CR No.:PC062602-2 CLEC Change Request Clarification Meeting

Attendees Name/Company: Terry Wicks Allegiance Russ Urevig Qwest Debbie Osborne Qwest Neil Houston Qwest Kit Thomte Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees See list above

2.0 Review Requested (Description of) Change Terry Wicks reviewed the CR with the SME from Qwest. Process to find working circuits needs to be re designed and reviewed with personnel. Update reject reasons to be clearer specify scenarios that relate to the reject so the SDC can provide better information to the CLECs.

2.1 Terry believes that a collaborative process should be used to allow input from Allegiance and other CLECs in the development of the error messages. We agreed that we could discuss at the CMP meeting and determine the level of interest. 2.2 Terry presented an example that the SMEs reviewed to ensure a level of understanding for the problem. 2.3 Qwest inquired about what changed in May 2002 that seemed to impact thee errors. Allegiance clarified that was when they discovered that the process was not being used.

3.0Confirm Areas & Products impacted 3.1CLEC to CLEC migrations Qwest wanted to clarify that this was a specific issue associated with one product (UNE). And not a global issue. Allegiance indicated it was not global. Qwest inquired about what changed in May 2002 that seemed to impact thee errors. Allegiance clarified that was when they discovered that the process was not being used. 4.0Confirm Right Personnel Involved 4.1Russ Urevig will have the lead on this CR. Neil will stay involved as required.

5.0 Identify/Confirm CLEC’s Expectation 5.1Ensure that Qwest personnel understand the process and are trained. Improve the reject remarks to be more specific to scenarios thus providing the CLECs a better idea of the problem.

6.0Identify any Dependent Systems Change Requests 6.1 None apply

7.0 Establish Action Plan 7.1 No systems are impacted the time frame would be dependent on the participation of the CLEC in the meeting and the timing of updating the documentation. 7.2


CenturyLink Response

August 12, 2002

Terry Wicks, LEC Manger Allegiance Telecom, Inc

SUBJECT: Qwest’s Change Request Response - CR # PC062602-2 Rejects on CLEC to CLEC Reuse of Facilities orders for no circuit IDs found

This is in response to the request from Allegiance where as Allegiance would like to collaboratively work with Qwest to establish clear, definitive reject comment reasons for CLEC to CLEC reuse of facilities orders to insure that all resources available to the SDCs have been utilized to find working circuits.

After meeting with Terry Wicks several times to discuss the application of the comment remarks that are associated with the reject for CLEC to CLEC migration, we have clarified the comments and have modified the comments as set forth below to address the following scenarios.

1. When Qwest finds the circuit at the requested address is NOT the same type of circuit to which the migrate has been requested, the comment remark associated with this will read: Circuits at request address do not match the type of circuit indicated on the LSR for migration. The circuits found are (ex. LX-N or AD--, HCE-, etc)

2. Multiple circuits are found at the requested address, if the number of circuits at the address do NOT match the number of migrations indicated on the LSR. It is very important that the CLEC indicate who the OLSP (old local service provider) is when requesting migration because this will aid in determining whether multiple circuits are really an issue. Qwest will provide these comment remarks for the reject: Multiple circuits have been identified at request address, circuits are currently not those of the indicated OLSP or Multiple circuit have been identified for the OSLP but do not match the number of loops requested for migration.

3. Qwest has searched all available records to identify circuits at end user address, but was NOT able to identify circuit for migration. Qwest will review all data on LSR to obtain circuits to be migrated. Additional data that is recommended to aid in the migration request are: the TN that is being ported to the NLSP’s (new local service provider) switch and the name of the OLSP. If Qwest can NOT find the circuits, the following comment remarks will be provided on the reject: Qwest has search for circuits at the requested address, using the end user name, address, OLSP, and TN provided. Qwest can not find circuits please verify data on LSR for accuracy.

A review of the internal documentation for Qwest has been completed and several changes have been made to streamline the search for unbundled loop circuits. The completed changes and notification to the Wholesale Service Delivery centers will be complete by August 22. The change notifications will be distributed with an MCC, the details of the MCC are the TOPIC is Standardized Comments for CLEC to CLEC Migration Rejects, the SUBJECT is Unbundled Loop, the USER GROUPS AFFECTED are Wholesale. A joint review meeting with the Team Leads, Coaches and SMEs (subject matter experts) will also be held to review the changes and clarify the importance of this process. We have accepted the request to modify the comment remarks on the rejected migration, so that the comments are more standard for the problem encountered. If the Qwest deviates from the standard comments it will be only to provide additional information about that reject.

Sincerely,

Russell Urevig Sr Process Analyst Wholesale Service Delivery


Open Product/Process CR PC062602-3 Detail

 
Title: Cross Reference CLEC Trouble Ticket number on Qwest Trouble Ticket numbers
CR Number Current Status
Date
Area Impacted Products Impacted

PC062602-3 Withdrawn
9/18/2002
Billing, Maintenance/Repair
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Suellentrop, Craig
Director:
CR PM:

Description Of Change

When Allegiance calls the Qwest Repair Center to open a trouble ticket verbally, we want the CLEC’s internal trouble ticket number to be a required item to be provided to the Qwest representative issuing the Qwest trouble ticket. This will allow for both the Qwest trouble ticket number and the CLEC’s internal trouble ticket number to be cross referenced to each other. Allegiance also wants the CLEC’s internal trouble ticket number to appear on the CLEC’s bill from Qwest for repair and maintenance charges along with the Qwest trouble ticket number. This cross reference of both the Qwest trouble ticket number and the CLEC’s internal trouble ticket number on the bills will allow the CLECs the ability to better reconcile the repair and maintenance charges from Qwest.


Status History

06/26/02 - CR Submitted by Allegiance.

06/26/02 - CR acknowledged by P/P CMP Manager.

06/28/02 - Left voice mail message with T Wicks, Allegiance, for coordinating Clarification meeting on 7/2.

07/02/02 - Conducted Clarification Meeting with Allegiance.

07/03/02 - Issued Clarification Meeting Minutes to Allegiance.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status "Clarification" was not changed.

08/08/02 - Issued Mailout Notification to CLECs advising that the CR will be reviewed with other similar CRs. Notification CMPR.08.08.02.F.01312.Mtg_Proposal.

08/14/02 - Issued Qwest's Draft Response dated August 13, 2002 to Allegiance.

08/19/02 - Issued Mailout Notification to CLECs confirming the Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled for 8/27/02, 2:00 pm MT. Notification CMPR.08.19.02.F.01317.CMP_CR_Mtg.

08/21/02 - CMP Meeting - Qwest presented its Draft Response dated August 13, 2002. This CR to be included for discussion in the CLEC conference call scheduled for 8/27. Minutes on this CR to be posted to the Project Meetings section. Status was changed to Evaluation

8/27/02 - CR included in the Synergy Meeting for Multiple Trouble Tickets & Billing CRs. See Meeting Notes in Attach O, Sept Systems CMP Package.

08/30/02 - Conducted additional clarification call with Allegiance to discuss the manual and system aspects of their CR.

09/11/02 - Issued Qwest's revised response dated September 10, 2002 to Allegiance.

09/18/02 - CMP Meeting - Qwest presented its revised response dated September 10, 2002. Minutes on this CR to be posted to the Project Meetings section. Allegiance agreed to withdraw the CR with a Global Action Item being opened to address their request to modify the current spreadsheet they receive with trouble ticket information. Qwest agreed. The CR will be status as Withdrawn


Project Meetings

09/18/02 September CMP Monthly Meeting Minutes

Allegiance advised they would withdraw this CR which will be satisfied with the System CR’s, providing Qwest opens a Global Action Item to research if a column with their Trouble Ticket Number could be added to the current spreadsheet they receive from their Service Manager. Qwest advised that they are looking into this action item. Qwest expressed that development of the spreadsheet is a complicated process. No participating CLEC indicated that they wanted to assume sponsorship of this CR. The CR will be status Withdrawn and a Global Action Item will be opened.

--

08/30/02 Conference Call

Ric Martin and Craig Suellentrop, Qwest, held a conference call with Terry Wicks, Allegiance to discuss the manual and system aspects of their CR. Qwest advised that the system aspect of Allegiance’s CR would be covered under the resultant Systems CR from combining the various System CRs on Trouble Tickets and Repair Charges. Qwest advised that the Systems resolution would look at the “Input” aspect (CEMR and MEDIACC) of getting CLEC Trouble Tickets and the “Output” aspect (Bill) of cross-referencing trouble tickets and Circuit IDs, etc. Allegiance was in agreement with the handling of the systems aspect of their CR. Qwest explained that there might be something that could be done on the manual process aspect, but there wouldn’t be any meaningful output until the systems fix was accomplished. Qwest indicated that they would still pursue the manual aspect if Allegiance were interested in this. Allegiance indicated that they didn’t want Qwest to duplicate efforts on a manual and systems fix. Allegiance asked if Qwest would look into modifying the spreadsheet they get from their Service Manager to include their internal Ticket Number. Qwest advised that they would open a Global Action Item to look at this and asked Allegiance to send an e-mail with a copy of the spreadsheet and details on what they would like included and at the September CMP meeting we would discuss the disposition of their CR.

08/21/02 August CMP Monthly Meeting Minutes

Qwest reviewed its draft response and advised that this CR would be reviewed in conjunction with other CRs related to trouble tickets, repair charges, etc. scheduled for August 27, 2002. The CLEC participants agreed to have this CR reviewed at that meeting. Qwest clarified that a manual process could be developed to request the CLEC trouble ticket, but it would be input into the remarks field that doesn’t have any sorting capability. Allegiance indicated that they currently receive a spreadsheet with the Qwest trouble ticket identified and asked if Qwest couldn’t put Allegiance’s ticket number on the spreadsheet. Qwest confirmed that the spreadsheet is created from a Web site and maintained by Nancy Tangeman.

07/17/02 - July CMP Meeting Minutes: Allegiance introduced their Change Request. Qwest stated the need is to create a process to capture the information Allegiance has requested. CR status is evaluation.

CLEC Change Request Clarification Meeting

July 2, 2002 9:00 a.m. (MT) Conference Call 877-564-8688 PC062602-3, Cross Reference CLEC Trouble Ticket number on Qwest Trouble Ticket Numbers

Attendees: Ric Martin, Qwest Lynn Stecklein, Qwest Craig Suellentrop, Qwest Alice Matthews, Qwest Terry Wicks, Allegiance

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Terry indicated that this CR was different than the Systems CR that has to do with the CEMR update. Allegiance does not use CEMR and call in their trouble to the AMSC. Allegiance wants to be able to call tickets in, provide their internal number, have it cross referenced with Qwest’s number and to have their internal number show up on the bill. Terry indicated that they would like to see a process change that would require Qwest to get an Internal Ticket number from the CLEC before they open up a trouble ticket. Terry indicated that they intend to e-bond with MEDIACC in the future, which allows them to electronically report trouble without making a phone call. Craig confirmed that the trouble tickets called in are entered into WFA-C and Qwest would need to look into what the flow through systems are. Additionally Qwest will need to look into what is needed to have Allegiance’s ticket number appear on the bill. Terry indicated that no matter how we open up a ticket, the cross-reference to the CLEC Ticket on the bill is what matters. Terry will look into how e bonding to MEDIACC would be communicated and if there is a field currently that would allow this. He will look into whether a systems CR would be required for MEDIACC.

Confirm Areas & Products impacted It was confirmed that the area impacted was Billing and Maintenance & Repair. The product impacted is UBL.

Confirm Right Personnel Involved Qwest confirmed that Craig would remain the SME for now.

Identify/Confirm CLEC’s Expectation Terry confirmed that they were looking for: 1. A process to have the AMSC not open a trouble ticket without first getting a CLEC internal trouble ticket. 2. Determine best method to get CLEC trouble ticket number on the bill.

Identify any Dependent Systems Change Requests Systems CR SCR030702-1 has to do with CEMR update to include a field for CLEC Trouble Ticket. Systems CR SCR042902-01 has to do with getting the CLEC trouble ticket number onto the bill.

Establish Action Plan (Resolution Time Frame) The CR will have the collective CLEC clarification and SME input at the July CMP meeting.


CenturyLink Response

September 10, 2002

Terry Wicks LEC Manager Allegiance Telecom, Inc.

SUBJECT: Qwest’s Revised Change Request Response - CR PC062602-3 “Cross Reference CLEC Trouble Ticket number on Qwest Trouble Ticket numbers.”

This CR requests that “the CLECs internal trouble ticket number to be a required item to be provided to the Qwest Representative issuing the Qwest trouble ticket. This will allow for both the Qwest trouble ticket number and the CLECs internal trouble ticket number to be cross referenced to each other.” Allegiance would also like the CLEC’s trouble ticket number to appear on bills for maintenance and repair charges.

Because of the large number of Charge Requests related to Maintenance and Repair, a meeting was held on August 27, 2002 to discuss possible synergies between the various CRs. As a result of this meeting and further consultation with Allegiance on August 30, 2002, it was determined that the system CRs SCR030702-1 – CLEC Trouble Ticket Cross Reference and SCR042902-01 – Use CLEC Internal Repair Ticket number on CLEC bill to identify maintenance and repair charges would address the concerns raised by this CR relating to cross-referencing trouble ticket numbers and CLEC trouble ticket numbers appearing on the bill. Allegiance agreed that a separate manual process would not be required with the development of the system enhancements covered by these CRs.

Allegiance also raised an issue concerning a spreadsheet they receive from their Qwest Service Manager that contains all of the TOK and NTF tickets. Allegiance would like to see their trouble ticket number on this spreadsheet. Qwest and Allegiance agreed that this issue could be pursued as a Global Action Item and that Qwest will continue to investigate this issue.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Senior Process Analyst, Qwest Alice Matthews, Senior Process Analyst, Qwest Dan Busetti, Lead IT Analyst, Qwest

--

August 13, 2002

Terry Wicks LEC Manager Allegiance Telecom, Inc.

SUBJECT: Qwest’s Change Request Response - CR PC062602-3 “Cross Reference CLEC Trouble Ticket number on Qwest Trouble Ticket numbers.”

This CR requests that “the CLECs internal trouble ticket number to be a required item to be provided to the Qwest Representative issuing the Qwest trouble ticket. This will allow for both the Qwest trouble ticket number and the CLECs internal trouble ticket number to be cross referenced to each other.” Allegiance would also like the CLEC’s trouble ticket number to appear on bills for maintenance and repair charges.

The current repair process for Designed Services allows a CLEC to offer the CLEC trouble ticket number to the Qwest representative opening the Qwest trouble ticket. The CLEC trouble ticket number will be entered into a remark field. This field is not “searchable” and does not appear on CLEC bills. This option is not available for Non-Designed Services. Qwest would agree to a process change to ask all CLECs for their internal trouble ticket number, but without systems changes this would not address the majority of Allegiance’s concerns.

Open System CR’s SCR030702-1 – CLEC Trouble Ticket Cross Reference and SCR042902-01 – Use CLEC Internal Repair Ticket number on CLEC bill to identify maintenance and repair charges also would require a very similar process. A meeting will be scheduled for late August to discuss the similarities between these and some other CR’s involving maintenance and repair. Further clarification and direction for this CR will be determined after this meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Senior Process Analyst, Qwest Alice Matthews, Senior Process Analyst, Qwest


Open Product/Process CR PC062602-1 Detail

 
Title: Circuit IDs on CLEC to CLEC Reuse of Facilities orders
CR Number Current Status
Date
Area Impacted Products Impacted

PC062602-1 Completed
10/23/2002
Ordering, Provisioning Unbundled Loop, UNE Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Urevig, Russell
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Allegiance wants the capability to get CLEC circuit ID information from Qwest on UNE DS0 loops prior to submitting a CLEC to CLEC reuse of facilities order. If Qwest Retail wants to reuse facilities when porting a customer from a CLEC back to Qwest, they have the capability to “look up” circuit ID information. Qwest Retail does not have to get this information directly from the CLEC, thus the ability to access circuit ID information speeds up their process of submitting orders to Wholesale and eliminates rejects for “bad or missing” circuit IDs. Giving the CLECs a process to obtain CLEC circuit ID detail up front for reuse orders, will allow the CLECs the same parity in submitting accurate orders in a timely manner. This capability will also allow more frequent use of the CLEC to CLEC reuse of facilities process. In many instances, some CLECs that are loosing a customer will not provide circuit ID information to the winning CLEC, thus inhibiting the process of reusing the facilities. When facilities are not reused and the CLEC submits new loop orders, the results may be held orders for lack of facilities. Also installing new loops is much more expensive.

While there is a process in place to be able to submit CLEC to CLEC reuse of facilities orders without providing circuit ID information, 90% of the orders submitted by Allegiance since late May 2002 are being rejected for various erroneous or unclear reasons regarding the circuit ID information. (I will be addressing that issue in a separate change request.) Allegiance believes that having this additional capability, will greatly enhance our ability to get reuse orders successfully processed and in a more timely manner.

Expected Deliverable:

A process for CLECs to be able to request Circuit IDs up front for CLEC to CLEC reuse of facilities orders that is in parity with Retail’s capability to get such circuit IDs before placing a reuse order for UNE DS0 loops.


Status History

06/26/02 - CR Submitted by Allegiance.

06/26/02 - CR acknowledged by P/P CMP Manager.

06/28/02 - CR Posted to Web

07/02/02 - Contacted Terry Wicks and set up clarification call for July 8, at 9:00 a.m.

07/08/02 - Clarification call was held

07/10/02 - Clarification meeting minutes sent to Allegiance

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Clarification.

08/14/02 - Issued Qwest draft response to Terry Wicks at Allegiance

08/21/02 - CMP Meeting - Qwest presented its draft response dated 8/13/02. Minutes on this CR to be posted to the Project Meetings section.

09/12/02 - Issued revised Qwest draft response dated 9/10/02 to Terry Wicks at Allegiance

09/18/02 - September CMP Meeting - Qwest presented revised response. CR will stay in Development. Meeting minutes will be posted to this CR's Project Meetings section

10/10/02 - Issued revised Qwest draft response dated 10/8/02 to Alex Pantazis at Allegiance

10/16/02 - October CMP Meeting - Minutes on this CR to be posted to the Project Meetings section. CR will move to CLEC Test status.

10/23/02 - Lori Mendoza notified Qwest that CR should be moved Completed status.

10/28/02 - Issued Qwest Revised Response dated 10/8/02 to Lori Mendoza at Allegiance.


Project Meetings

10/16/02 October CMP Meeting Russ Urevig with Qwest reviewed the revised response dated 10/8/02. Lori Mendoza with Allegiance asked what they should do if unable to determine the circuit ID using the RLD Query. Russ said that the RLD Query must have a valid address and suite number. If no response from RLD Query then send in the LSR to Qwest. Qwest does accept LSRs for CLEC to CLEC migration without circuit ID information. This CR will be updated to CLEC test status and will look to close in November.

09/18/02 September CMP Meeting Qwest reviewed its draft response and summarized the September 4th conference call with Allegiance, walking through Raw Loop Data Tool. When the end user location was a single tenant address the circuit ID was produced. When the end user location was a multi-tenant address, the circuit ID was produced when the suite number was included and when the suite number was in PREMIS database. Allegiance appreciated the assistance with RLD, and, said that providing the circuit ID will get migration orders through the first time with fewer rejects. This CR will stay in development status while determining the tool for CLEC’s to obtain circuit IDs is identified. Eschelon asked if Qwest is not able to come to a systems solution, would a single point of contact be implemented for CLEC’s. Qwest responded that such a solution may be entertained but it was more likely that a mechanized process would be identified.

-- 08/21/02 - August CMP Meeting Minutes: Qwest reviewed its draft response. Allegiance would like to walk through on the phone with Qwest and use Raw Loop Data Tool. Eschelon asked how to identify which CLEC owns the circuit. Qwest stated that the RLDT will provide the circuit ids and that retail and CLECs rely on Qwest Wholesale to identify the local provider. Allegiance indicated they would like to move this CR into development.

07/17/02 - July CMP Meeting Minutes: Allegiance presented their Change Request. Qwest stated that current tools will be reviewed for their capability to look at curcuit IDs in conjunction with end user addresses, including specific addresses that have suite numbers. CR status is clarification

Time/Date: 9:00 a.m. (MDT) / Monday, July 8, 2002 Place: Conference Call Conference: TEL: 877.521.8688 Call-In No: CODE: 7901848 CR No: PC062602-1" Circuit IDs on CLEC to CLEC Reuse of Facilities orders"

Attendees: Terry Wicks, Allegiance Russ Urevig, Qwest Neil Houston, Qwest Bob Mohr, Qwest Michael Keegan, Qwest

Introduction of Attendees Attendees introduced. Review Requested (Description of) Change Description: Allegiance wants the capability to get CLEC circuit ID information from Qwest on UNE DS0 loops prior to submitting a CLEC to CLEC reuse of facilities order. If Qwest Retail wants to reuse facilities when porting a customer from a CLEC back to Qwest, they have the capability to "look up" circuit ID information. Qwest Retail does not have to get this information directly from the CLEC, thus the ability to access circuit ID information speeds up their process of submitting orders to Wholesale and eliminates rejects for "bad or missing" circuit IDs. Giving the CLECs a process to obtain CLEC circuit ID detail up front for reuse orders, will allow the CLECs the same parity in submitting accurate orders in a timely manner. This capability will also allow more frequent use of the CLEC to CLEC reuse of facilities process. In many instances, some CLECs that are loosing a customer will not provide circuit ID information to the winning CLEC, thus inhibiting the process of reusing the facilities. When facilities are not reused and the CLEC submits new loop orders, the results may be held orders for lack of facilities. Also installing new loops is much more expensive.

While there is a process in place to be able to submit CLEC to CLEC reuse of facilities orders without providing circuit ID information, 90% of the orders submitted by Allegiance since late May 2002 are being rejected for various erroneous or unclear reasons regarding the circuit ID information. (I will be addressing that issue in a separate change request.) Allegiance believes that having this additional capability, will greatly enhance our ability to get reuse orders successfully processed and in a more timely manner.

Discussion: Allegiance stated they cannot force a CLEC to provide circuit ID information. Allegiance is dependent on Qwest to provide this information. Reuse of facilities benefits both the CLEC and Qwest. Qwest stated that the current tools will be reviewed for their capability to look at circuit IDs in conjunction with end user addresses. Confirm Areas & Products Impacted Areas Impacted: Ordering, Provisioning Products Impacted: Unbundled Loop, UNE Loop Confirm Right Personnel Qwest confirmed the correct personnel were on the call.

Identify/Confirm CLEC’s Expectation A process for CLECs to be able to request Circuit IDs up front for CLEC to CLEC reuse of facilities orders that is in parity with Retail’s capability to get such circuit IDs before placing a reuse order for UNE DS0 loops. Identify any Dependent Systems Change Requests None Establish Action Plan (Resolution Time Frame) Allegiance can present this Change Request to the CLEC community at the July Product/Process CMP meeting scheduled for July 17 Qwest will issue draft response to this Change Request by Aug 14 (one week prior to the Aug 21 CMP meeting). Qwest will discuss the draft response at the Aug 21 CMP meeting.


CenturyLink Response

October 8, 2002

Lori Mendoza LEC Account Manager Allegiance Telecom

SUBJECT:Qwest’s Change Request Revised Response - CR # PC062602-1 Circuit IDs on CLEC to CLEC Reuse of Facilities orders

At the September CMP meeting, Qwest agreed to continue to research the issues, to determine the most suitable path forward in determining circuit ID information to allow the CLECs the ability to get circuit ID information on DSO type loops for CLEC to CLEC migrations.

Qwest has reviewed the current process of obtaining loop circuit ID’s using the Raw Loop Data (RLD) Query for CLEC to CLEC migrations. We find the tool meets the needs of the change request to provide CLECs a process to obtain Loop Circuit ID details for reuse orders. To clarify, the RLD Query can be used as follows: - Enter a valid address, this must be suite or unit specific if address is multi-tenant. - If address is valid, RLD will provide information on all working TN’s or circuits. - If no matches are found for a specific address, RLD will return a message indicating no information found.

When no circuit information is found, proceed with submitting the LSR and Qwest will determine the circuit and migrate the end user as requested.

The current process provides parity with migrations between Wholesale CLEC to CLEC migrations and migrating end users back to Qwest Retail. The work performed, the results and the responses are handled in the same manner between Retail and the CLECs

LSRs for CLEC to CLEC migration do not require that the Circuit ID field be populated. - Qwest will accept the requests for migration without circuit information. - Qwest will research and determine the circuit or circuits at that address. - If the Loop Circuit ID cannot be determined, Qwest will provide a standard remark associated with the reject of a migration request as follows:

1. When Qwest finds the circuit at the requested address is NOT the same type of circuit to which the migrate has been requested, the comment remark associated with this will read: Circuits at requested address do not match the type of circuit indicated on the LSR for migration. The circuits found are (ex. LX-N or AD--, HCE-, etc).

2. Multiple circuits are found at the requested address: If the quantity of circuits at the address do not match the quantity of lines migrating, as indicated on the LSR, Qwest will use the OLSP information provided by the CLEC to try to determine which services will be migrated. It is very important that the CLEC indicate who the OLSP (old local service provider) is when requesting migration because this will aid in determining whether multiple circuits are really an issue. Qwest will provide these comment remarks for the reject: Multiple circuits have been identified at request address, circuits are currently not those of the indicated OLSP or Multiple circuits have been identified for the OSLP but do not match the number of loops requested for migration.

3. Qwest has searched all available records to identify circuits at the end user address, but was not able to identify circuit for migration: Qwest will review all data on the LSR to obtain circuits to be migrated. Additional data that is recommended to aid in the migration request are: the TN that is being ported to the NLSP’s (new local service provider) switch and the name of the OLSP. If Qwest can not find the circuits, the following comment remarks will be provided on the reject: Qwest has searched for circuits at the requested address, using the end user name, address, OLSP, and TN provided. Qwest can not find circuits, please verify data on LSR for accuracy.

- The CLEC should review the reject remarks, validate any issues in question, and re-submit the LSR once the information is found and the LSR is corrected. - Qwest provides a method to escalate questions on rejects or clarification on remarks for rejects.

Sincerely,

Russ Urevig Senior Process Analyst Wholesale Service Delivery


Open Product/Process CR PC071502-1 Detail

 
Title: Include CFA Information on PTA Email Notifications of NDT
CR Number Current Status
Date
Area Impacted Products Impacted

PC071502-1 Completed
12/18/2002
Coordinated Hot Cuts and Regular Cuts LNP, Unbundled Loop, UNE Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Hendricks, Linda
Director:
CR PM: Thomte, Kit

Description Of Change

Allegiance is requesting that the CFA information be added to the current PTA notifications of NDT. During the testing of the PTA tool notification of NDT, there have been several instances of receiving a notification of NDT that were Qwest errors. When Allegiance has researched these, everything checks out fine. Our translations are correct, and when dispatching our Tech to our Collocation to check the pairs, the pairs are working fine. The issue has been that Qwest has them on the wrong pair and in some instances the service order has been incorrectly issued.

This is resulting in Allegiance spending extra time, effort and money to isolate the NDT issue to the Qwest side. What would resolve this is if the Pair Information was also on the PTA notification next to the telephone number. With this information showing what pairs Qwest is testing to, we can identify the error quicker.

Expected Deliverable:

Receiving the PTA email notifications of NDT with the CFA information provided in addition to PON, TNs and DD


Status History

07/15/02 - CR Submitted by Allegiance

07/15/02 - CR acknowledged by P/P CMP Manager.

07/17/02 - Spoke with Allegiance regarding potential times for meeting

07/22/02 - Held clarification meeting with Allegiance

08/21/02 - This CR is in "Evaluation" status and is alligned with another CR

09/10/02 - Sent Draft Response to Allegiance

09/18/02 - September CMP Meeting: CR status changed to "Development" Meeting minutes will be posted to this CR's Project Meeting section and the CMP Web site.

10/14/02 - Level one notification sent to CLEC community PROS.10.14.02.F.00598.CFA_Email_Notice

10/16/02 -October CMP Meeting: This CR will change "CLEC Test" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

11/20/02 - November CMP Meeting: This CR will reamin in "CLEC Test" October CMP Meeting: Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

12/18/02 - December CMP Meeting: This CR changed to Closed Status in the CMP Meeting. Meeting minutes posted to this CR's Project Meeting section and the CMP Web site.


Project Meetings

12/18/02 December CMP Meeting Qwest (Hendricks) reported that the QCCC is working to ensure they follow the process and Allegiance (Mendoza) reported the process is working as agreed to and it is O.K. to close the CR. This CR will change to Closed status.

11/20/02 November CMP Meeting Qwest (Thomte) indicated that she thought some problems had been identified recently through a comment from Lori Mendoza. Linda Hendricks confirmed that was true. Allegiance (Mendoza) indicated that they were getting CFA on the PTA about 50 percent of the time. Other CLECs indicated they were seeing problems as well. This CR will remain in CLEC Test.

10/16/02 October CMP Meeting Qwest initiated a Level 1 notification (PROS.10.14.02.F.00598.CFAEmailNotice) on October 14 advising the CLEC community that CFA information would be provided on PTA E-mail notifications. This CR moved to “CLEC Test”

09/18/02 September CMP Meeting This CR should be discussed in conjunction with PC050302-1. Qwest provided an updated response indicating this Change Request has been accepted, although it is dependent on the implementation of PC050302-1. Participants agreed that PC071502-1 CR can implement with a Level 1 notice after comments cycle is completed for PC050302-1. This CR will change to "Development"status with agreement to update to "CLEC Test" once Level 1 notice is sent.

08/21/02 - August CMP Meeting Minutes

This CR is dependent on CR PC050302-1. This CR status changed to "Evaluation"

Date: July 22, 200 Place: 1005 17th St Room 1770-C Call-In No.: 877 550-8686 CR No.: CLEC Change Request PC071502-1 Clarification Meeting

Attendees Name/Company: Terry Wicks Allegiance Russ Urevig Qwest Linda Hedricks Qwet Steve Hilleary Qwest Phyllis Sunnins Qwest Kit Thomte Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees See list above 2.0 Review Requested (Description of) Change Terry Wicks reviewed the CR with the SMEs from Qwest. 2.1During the trial that was held in May and June Allegiance investigated situations that resulted in NDT. *One scenario was due to the Service Order being written with information that was different than what appeared on the LSR. *Another scenario was due to the Central Office being wired incorrectly. 2.2Terry indicated that if Allegiance knows up front what CFA Qwest is testing to it allows them to resolve the issue faster. Allegiance can review based on what they passed on the LSR and what Qwest FOCd back. 2.3

3.0 Confirm Areas & Products impacted 3.1 UNE, Unbudled Loop 4.0 Confirm Right Personnel Involved 4. The team agreed that Linda Hendricks would be the respondent Steve will participate, and Phyllis and Russ would have no further action.

5.0 Identify/Confirm CLEC’s Expectation 5.1 Receive notification regarding CFA used in no dial tone situations

6.0 Identify any Dependent Systems Change Requests 6.1

7.0 Establish Action Plan (Resolution Time Frame) 7.1 No systems are impacted the time frame would be dependent on the participation of the CLEC in the meeting and the timing of updating the documentation.


CenturyLink Response

September 5, 2002

Terry Wicks Allegiance

SUBJECT: Qwest’s Change Request Response - CR #PC071502-1 Include CFA Information on PTA Email Notifications of NDT.

This is a preliminary response regarding Allegiance CR PC071502-1 (Include CFA Information on PTA E-Mail Notifications of NDT). As discussed in the August Product & Process Monthly CMP Meeting, this CR is dependent on the outcome of PC050302-1 (Email Notification of No Dial Tone at 48 Hours).

The implementation of Change Request PC050302-1 is being pursued as a CMP Level 3 change as agreed to in the July Product & Process Monthly CMP Meeting. Based upon the issuance of notice PROD.09.05.02.F.00818.AnalogLoop24Wire, Change Request PC050302-1 is currently in a comment cycle.

Upon the implementation of Change Request PC050302-1 Qwest anticipates being able to make changes as described in PC071502-1. Specifically, Qwest expects to be able to include CFA information in addition to PON, TNs and DD in PTA e-mail notifications.

Assuming the successful implementation of e-mail notifications of No Dial Tone (NDT) per Change Request PC050302-1, Qwest would propose to notify the CLEC community of the changes specified in PC071502-1 as a Level 1 change (i.e. “additional information that does not change the product or process”). Qwest will seek concurrence with this approach at the September Product & Process Monthly CMP Meeting.

Sincerely,

Linda Hendricks Lead Project Analyst Qwest


Open Product/Process CR PC072902-1 Detail

 
Title: Request for estimate of cost for extending or moving a DMARC beyond the MPOE prior to doing the work
CR Number Current Status
Date
Area Impacted Products Impacted

PC072902-1 Withdrawn
8/21/2002
Coordinated Hot Cuts and Regular Cuts Unbundled Loop, UNE Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Tallman, Shirley
Director:
CR PM:

Description Of Change

Allegiance is requesting that Qwest develop a process to give the CLEC the ability to request an estimate of cost for extending or moving a DMARC (NIU) beyond the MPOE prior to placing an order. In other ILEC territories, Allegiance can fill out a form requesting the extention or move of a DMARC beyond the MPOE, and can get an estimate of the cost prior to placing the order. This gives the CLEC an opportunity to know what costs are involved prior to submitting such an order. Currently in Qwest, we don't know what it will cost until the order is processed and the work has been completed. Allegiance is not aware of the cost until after it has been billed to us.


Status History

07/29/02 - CR Submitted by Allegiance

07/30/02 - CR acknowledged by P/P CMP Manager.

07/31/02 - CR Posted to Web

07/31/02 - Received revised CR title and description from Allegiance

07/31/02 - Coordinated Clarification meeting with Terry Wicks, Allegiance.

08/02/02 - Conducted Clarification meeting with Allegiance.

08/05/02 - Issued Clarification Meeting Minutes to Allegiance

08/05/02 - Allegiance provided response to its Action Item from the Clarification Meeting.

08/05/02 - Received comments from Allegiance on meeting minutes and incorporated them into the database.

08/21/02 - CMP Meeting - Allegiance advised that a conference call clarified the NID/Demarc relocation requirements. Allegiance advised that they were withdrawing the CR. No other CLEC opted to sponsor the CR. Minutes on this CR to be posted to the Project Meetings section.


Project Meetings

08/21/02 August CMP Monthly Meeting Minutes

Allegiance advised that they had a conference call with Qwest where it was clarified the difference between requesting an extension of a jack versus a NID/DEMARC. It is Qwest’s policy that CLECs cannot request an extension to a NID/DEMARC and only in Minnesota and Oregon is it mandated that CLECs can request and extension of a Jack. Allegiance advised that based on this clarification, they would like to withdraw their CR. Qwest asked if any other CLEC would like to sponsor the CR and no CLECs expressed an interest. It was agreed that the CR would be status as withdrawn.

-

Subject: RE: CR PC072902-1 Clarification Meeting Minutes Date: Mon, 5 Aug 2002 13:41:39 -0500 From: "Wicks, Terry" To: "'Richard Martin'"

The department that we fax a form to for Southwestern Bell , to get an estimate of cost, is called the LSC (Local Service Center). This is the department that processes our LSRs.

Terry Wicks LEC Account Manager allegiancetelecom, inc 469-259-4438 terry.wicks@algx.com

CLEC Change Request Clarification Meeting

August 2, 2002 10:00 a.m. (MT) Conference Call 877-564-8688 PC072902-1, Request for estimate of cost for extending or moving a DMARC beyond the MPOE prior to doing the work

Attendees: Ric Martin, Qwest Russ Urevig, Qwest Shirley Tallman, Qwest Bob Mohr, Qwest Linda Sanchez-Steinke, Qwest Terry Wicks, Allegiance

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the call discussed

Review Requested (Description of) Change Terry indicated that when Allegiance is taking a customer, they may want to move or extend the DMARC beyond the MPOE. They want to get an estimate of the cost before the work is performed. Currently they put their request in when they place the order and get billed for the work after the order is completed. Terry indicated that another ILEC has a form that they complete and submit to get an estimate before the order is submitted. Terry indicated that they have an 800 number and a fax number to which this form is sent. He believes they are dealing with the ILECs engineering department. Terry will confirm what department they deal with. The department is the LSC, Local Service Center at Southwestern Bell. Terry indicated that they were billed for the estimate and would be willing to pay for the estimate. He agreed that an estimate was acceptable with actual costs being billed per their agreement with Qwest. Russ asked if Allegiance was looking at a multi-tenant facility and looking more at an individual customer’s DMARC. Terry indicated that Allegiance is looking at extending the DMARC or sometimes moving the DMARC beyond the MPOE for an individual tenant of a multi-tenant building.

Confirm Areas & Products impacted Terry indicated that their product focus was UBL. Qwest may have to look at other products that would have the same need. It was agreed that the area impacted was Pre-Ordering and Ordering.

Confirm Right Personnel Involved Qwest confirmed that the Network department would be responsible.

Identify/Confirm CLEC’s Expectation Terry confirmed that they wanted a process to request and receive a written cost estimate for extending or moving a DMARC beyond the MPOE prior to submitting an order.

Identify any Dependent Systems Change Requests There are no systems changes associated with this request.

Establish Action Plan (Resolution Time Frame) The CR will have the collective CLEC clarification and SME input at the August CMP meeting.


Open Product/Process CR PC081902-1 Detail

 
Title: The 30 minute rule for Coordinated Hot Cuts.
CR Number Current Status
Date
Area Impacted Products Impacted

PC081902-1 Completed
4/15/2009
Provisioning, Coordinated Hot Cuts UBL, UNE-Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Toye, Deni
Director:
CR PM: Harlan, Cindy

Description Of Change

The 30 minute rule wording was only added to the PCAT for CHC with and without cooperative testing on 7/19/02. Prior to 7/19/02 Allegiance had asked for the rule in writing and had not received it. The application of this rule by the QCCC has not been consistent over the past year as I have discussed with Allegiance's Service Manager on several occassions. I had asked that the written rule or policy be sent to me in writing so that Allegiance could document our internal processes to follow the Qwest policy. Up until the notice was sent out on 7/18/02 that it was being added to the PCAT, it was conveyed by word of mouth between the QCCC and our operations. For example, some Testers stated that if we had not confirmed with the tester that we were ready to start the cut within 30 minutes of the start time of a cut, then they would JEP the order at 31 minutes. Other QCCC Testers stated that we have to be working the cut within this time or they would JEP it. It has had various clarifications as to what this rule is under the various Managers that have worked in the QCCC over the past year.

Qwest has been pointed out that this is not a new or even a changed process. Qwest has stated that this information has been in the SGAT for approximately 6 years. Allegiance has never opted into the SGAT language for our ICA and up until 8/02/02, Allegiance was never aware that this information was documented in the SGAT.

Here is the wording for reference:

“If you are not ready within thirty (30) minutes of the scheduled appointment time, then you must reschedule the installation by submitting a supplemental LSR. If Qwest is not ready within thirty (30) minutes of the scheduled appointment time, Qwest will waive the nonrecurring charge for the installation option. You and Qwest will attempt to set a new appointment time on the same day and, if unable to do so, Qwest will issue a jeopardy notice and a FOC with a new Due Date.”

The statement implies that “if for any reason” the CLEC is not ready, then it will be SUPd at 31 minutes. It does not take into account that if Qwest fails to notify us of a no dial tone issue, according to the current 48 hour dial tone testing requirements, then the CLEC is still held accountable for not being ready and the order will be SUPd. At the maximum, we may have 1 hour and 30 minutes from the start time of the cut to resolve a no dial tone issue if no notification was sent prior to due date. This has happened to Allegiance several times, and some QCCC testers hold fast to this policy. We have had to escalate on these instances and in some cases it has been denied and the order was JEPd. The wording needs to change to identify exceptions to the rule.

If Qwest is not ready for whatever reason according to this policy, Qwest will work with the CLEC throughout the day to get it cut. But if the CLEC is not ready, Qwest is only allowing a maximum of 1 hour and 30 minutes ( less in many instances) to "get ready" or the order will be JEPd.

Qwest is not taking it into consideration when Qwest fails to follow all steps of the 48 hour dial tone testing requirements and timely notification to the CLEC. When Qwest fails to do this, Qwest is considering that the CLEC is not ready. Allegiance believes that in this type of situation, it is Qwest that is not really ready because Qwest has not followed all steps of the process. Qwest’s consequence for not doing the cuts on due date is the potential that Qwest may have to pay penalties. The current policy is allowing Qwest to work with the CLEC to get it done on cut date to avoid such penalties. The consequence to the CLEC is we can lose that customer if we cannot get the order cut on due date as promised and we only have a limited time to “get ready” in order to complete the cut.


Status History

08/16/02 - CR Submitted by Allegiance

08/19/02 - CR acknowledged by P/P CMP Manager.

08/20/02 - Contacted customer and scheduled Clarification meeting

08/21/02 - CR Posted to Web

08/26/02 - Conducted Clarification meeting with Allegiance

08/30/02 - Clarification minutes issued to Allegiance

09/18/02 - September CMP Meeting Allegiance introduced and explained CR. It was agreed that the CR could move into Evaluation. Qwest will provide Response at the October Meeting. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product /Process CMP Meeting Distribution Package 10/16/02.

10/09/02 - Draft Response issued to Allegiance

10/16/02 - October CMP Meeting - Response accepted by CLEC community. Development of Level 3 Change will begin. This CR will move to Development status. Minutes will be posted to the Project Meeting section.

10/23/02 - Removed Draft from the Response and updated it to include comment from ATT to clarify this process does not over ride the VP Expedite Process

10/25/02 - Final Response posted to web

11/20/02 - November CMP Meeting advised process document is being updated.

12/16/02 - Level 3 Document Number: PROD.12.16.02.F.00877.AnalogLoop2_4Wire distributed. Proposed Effective Date: January 30, 2003

12/18/02 - December P/P CMP Meeting notes will be posted to the Project Meeting section. Changed status to CLEC Test.

12/19/02 - Message from CMP Comment Mail-In PROD.12.16.02.F.00877.AnalogLoop2_4Wire. Comments received on PCAT updates.

01/02/03 - Comments cycle closed for Notification PROD.12.16.02.F.00877.AnalogLoop2_4Wire. There were two CLEC comments received for this notification. The Qwest Final Release Notice and Response to the comments on this notification must be posted to the web by 1/15/03 with an effective date of 1/30/03.

01/07/03 - Changes Qwest owner and presenter to Deni Toye as Linda Hendricks is retired on Jan. 10, 2003. Cindi Dahlstedt will also support CR.

1/15/03 - Comments responded to and updates made to PCAT based on comments made.

1/1/5/03 - January P/P CMP Meeting notes will be posted to the Project Meeting section.

02/19/03 - February P/P CMP Meeting notes will be posted to the Project Meeting section.

3/19/03 - March P/P CMP Meeting notes will be posted to the Project Meeting section.


Project Meetings

03/19/03 March CMP Meeting Cindi Dahlstedt – Qwest reported she has checked to make sure we are sending the NDT notifications and all was okay. Bonnie Johnson – Eschelon asked if we do a spot or total check. Cindi replied a spot check. If any issues are found please notify Deni Toye at dtoye@qwest.com. Lori Mendoza – Allegiance reported NDT are working okay. Sometimes the CFA information is missing. Lori agreed to close this CR.

02/19/03 February CMP Meeting

Deni Toye–Qwest provided statistics regarding PTA NDT Notifications. All were sent within the 24-36 hour time frame. The QCCC has not been out of compliance so we have not executed the 30 minute rule. Lori Mendoza–Allegiance reported they have not had any problems, except they have gotten some PTA notifications without CFA information. This information has been provided to their Service Manager to investigate. Sharon Van Meter–ATT advised she will be meeting with her company to determine whether they will begin to use the PTA tool. This CR will be left in CLEC Test status until next month. At that time we will review additional feedback from the CLEC Community and determine a close date.

01/15/03 - Janaury CMP Meeting

Toye-Qwest stated that Qwest had distributed a notification on this CR and had responded to CLEC comments to the changes. Johnson-Eschelon stated that she had not yet read the Qwest response. Mendoza-Allegiance stated that Qwest has been much better, recently, on no-dial-tone notifications. This CR remains in CLEC Test.

12/18/02 - December CMP Monthly Meeting Minutes Qwest-Linda Hendricks advised the PCAT is out for CLEC comments with a planned implementation date of January 31. This CR will change to CLEC Test.

11/20/02 - November CMP Monthly Meeting Minutes Qwest (Hendricks) reported the PCAT is under development. This project will remain in Development status.

10/16/02 - October CMP Meeting Minutes Qwest reviewed the Acceptance Response to this CR and outlined when the exception will apply and when it will not apply. Eschelon clarified the following scenario: If Qwest can not reschedule the CHC for the same day the exception process will not apply. ATT expressed their concern that the exception process does not apply to VP Expedites. Qwest clarified the current VP Expedite Process does not change and this CR does not override the current VP Expedite Process. Qwest obtained agreement this CR would be handled as a Level 3 change and will follow the Level 3 process. This CR will move to Development status.

09/24/02 - September CMP Meeting Minutes Terry Wicks - Allegiance introduced and explained this CR would allow for an exception to the 30 minute rule for CHC process if CLECs do not get at least 24 - 48 hours NDT notification from Qwest. This applies to CHC only, not basic. In the case of not receiving notification QCC would work with the CLEC to reschedule the technician for sometime the same day instead of sup the LSR at 31 minutes. Jonathan-ATT said this should reduce the number of C01 misses. Linda Hendricks - Qwest explained if we are not doing the PTA email notification we won't be able to track whether the 48 hour NDT notifcation occurred. Eschelon and Allegiance expressed their support of the PTA tool. Qwest advised a response would be provided at the October meeting.

1:30 p.m. (MDT) / Monday 26th August 2002 1-877-561-8688 PC738 5723# Review CR PC081902-1 30 minute rule for Coordinated Hot Cuts

In Attendance: Terry Wicks - Allegiance Linda Hendricks - Qwest Bob Mohr – Qwest Cheri Hurless – Qwest Neil Houston – Qwest Cindy Macy – Qwest Ric Martin – Qwest Linda Sanchez-Steinke – Qwest Deb Smith – Qwest Deni Toye - Qwest

Introduction of Attendees

Review Requested (Description of) Change : Reviewed CR and confirmed business issues this CR will address. Terry requests the wording in the PCAT be changed to reflect an exception to the 30 minute rule if Qwest does not follow the 48 hour DT testing process. If Qwest notifies CLEC with 24 hours or less advance notice an exception process needs to be available. The exception process would allow Qwest and the CLEC to set a new appointment time on the same day, instead of jeopardizing the order and requiring the installation to be rescheduled by submitting a supplemental LSR. The business issue this CR is addressing is prevention of customer loss.

Confirm Areas & Products Impacted : Unbundled Loop / UNE / Loop Conversion orders existing customers PCAT – Ordering Wholesale UNE Installation Option Coordinated Installation with / with out testing

Confirm Right Personnel Involved : Linda Hendricks – confirmed as Lead SME Neil Houston – Network Regulatory Bob Mohr – Product Manager Cheri Hurless – Service Manager Cindy Macy – Change Request Project Manager

Identify/Confirm CLEC’s Expectation : Terry requests the wording in the PCAT be changed to reflect an exception to the 30 minute rule if Qwest does not follow the 48 hour DT testing process. If Qwest notifies CLEC with 24 hours or less advance notice an exception process needs to be available. The exception process would allow Qwest and the CLEC to set a new appointment time on the same day, instead of jeopardizing the order and requiring the installation to be rescheduled by submitting a supplemental LSR.

Identify any Dependent Systems Change Requests : CR PC 081902-2

Establish Action Plan (Resolution Time Frame) Document and issue meeting minutes within 5 business days (9-3-02) - Qwest Present CR at September CMP Meeting - Allegiance Present Draft Response at October CMP Meeting - Qwest


CenturyLink Response

October 16, 2002 For Review by CLEC Community and Discussion at October's CMP Meeting

Allegiance Telecom, Inc

SUBJECT: Qwest’s Change Request Response - CR #PC081902-1 The 30 minute rule for Coordinated Hot Cuts

Allegiance Telecom, Inc is requesting that Qwest change the wording and current process to allow the CLEC to work with Qwest on due date to get the cut done, when Qwest has failed to timely notify the CLEC according to the notification of NDT process, just as Qwest is allowing itself to do when Qwest is not ready. Update the PCAT with any changes resulting from this CR.

Qwest will accept the “30 Minute Exception” CR with the following guidelines:

-All CLECs must be enrolled in the NDT PTA Notification procedure in order to have accurate tracking and parity to ensure the success of the “30 minute rule” process.

-If Qwest fails to notify the CLEC within the timeframe of the NDT notification procedure, we will attempt to reschedule at a mutually agreed upon time for the same day.

-If Qwest is able to reschedule the same day it will not require a Customer Not Ready jeopardy and will not require a supp to the LSR. However the order will be in a CLEC delay status documented on the OSSCN screen in WFA/C.

- Rescheduling the Coordinated Hot Cut may not be workable on the same day. The appointment may require another date and time. This will result in a Customer Not Ready jeopardy.

- This process will be rework for Qwest in several departments and will require the CLEC to supp their LSR if another day and time is required.

The “30 Minute Exception” will not apply when:

- If Dial Tone is found at 48 hours before Due Date and noted in the OSSLOG, then at 1 hour before the due date the Dial Tone is no longer present.

- If the CLEC is not using the PTA NDT Email Notification.

- If the email systems of either Qwest or the CLEC were not working during the notification period, tracking would be invalid.

- If the CLEC has requested a VP Expedite and the interval does not allow the appropriate time for DT verification and CLEC notification (This process does not over ride the VP Expedite Process)

Qwest will issue this as a Level 3 change and seek concurrence of this approach at the October CMP Meeting.

Sincerely,

Linda Hendricks Lead Project Analyst Qwest

Cc: Mary Pat Cheshier, Diane Diebel


Open Product/Process CR PC081902-2 Detail

 
Title: The 48 Hour Dial Tone Testing Requirements
CR Number Current Status
Date
Area Impacted Products Impacted

PC081902-2 Completed
11/20/2002
Provisioning UBL, UNE-Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Hendricks, Linda
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

The following mailout was sent to CLECs on July 19, 2001 regarding Qwest's process for 48 hour dial tone testing:

*********************************************************************************************

Announcement Date: July 19, 2001

Effective Date: July 29, 2001

Document Number: PROS.07.19.01.F.00012

Notification Category: Process Update

Target Audience: CLEC

Subject: Dial Tone Test 48 Hours Before Due Date

Effective July 29, 2001, a process enhancement will be added to both the Coordinated and Basic Installation Option Processes. Qwest will verify the CLEC’s Dial Tone at the CLEC’s CFA 48 hours prior to the Due Date. This will assist CLECs in identifying dial tone concerns prior to the due date.

Central Office Technicians (COT’s) will check for CLEC Dial Tone 48 hours prior to the Due Date. The Dial Tone check will be for the Unbundled Loop Analog (Voice Grade) Product.

The COT will check for Dial Tone at the CLEC CFA. The COT will document the results from the Dial Tone test and the results will be forwarded to the Implementer/Coordinator (C/I).

If the COT does not detect Dial Tone 48 hours prior to the Due Date, then the (C/I) will contact the CLEC with the information. The CLEC should investigate and supply the dial tone by the Due Date or issue a supplement to the LSR to change the due date.

If the CLEC has requested a Coordinated Installation, the COT will check for Dial Tone one hour prior to the Coordinated Installation time. If dial tone is not detected at that time, then the COT will report this to the C/I who will in turn inform the CLEC.

This Process will be put in place to ensure that the CLEC will receive their circuit on the due date.

*********************************************************************************************

Allegiance believes that Qwest is not complying with the process as stated above. The testing for dial tone is actually being conducted on DVA date (48 hours after Application Date not 48 hours prior to Due Date). Also it is not clear as to when Qwest is notifying the CLEC of no dial tone conditions. This process implies that once the COT forwards the results to the QCCC tester at 48 hours prior to due date, then the tester will immediately notify the CLEC of No Dial Tone conditions. In actual practice, Qwest is not consistently notifying the CLEC at 48 hours prior to cut date. There are inconsistencies between the process and Qwest's actual application of the process. Qwest needs to comply with its published process. This process is not published in the PCAT. The only reference to this process that Allegiance could find was the mailout sent to CLECs on July 19, 2001.

Expected Deliverable

Qwest will comply with its published process. Qwest will update the PCAT to include this process.


Status History

08/16/02 - CR Submitted by Allegiance

08/19/02 - CR acknowledged by P/P CMP Manager.

08/21/02 - CR Posted to Web

08/22/02 - Contacted Allegiance to schedule Clarification Meeting

08/26/02 - Conducted Clarification Meeting with Allegiance.

08/30/02 - Clarification meeting minutes issued to Allegiance

09/18/02 - September CMP Meeting - Allegiance clarified this CR. Meeting minutes will be posted to this CR's Project Meetings section.

10/09/02 - Issued Qwest draft response dated 10/3/02 to Alex Pantazis at Allegiance Telecom.

10/16/02 - October CMP Meeting - Minutes on this CR to be posted to the Project Meetings section. CR status changed to CLEC test.

10/28/02 - Issued Qwest Response dated 10/3/02 to Lori Mendoza at Allegiance.

11/20/02 - November CMP Meeting - CR status changed to Completed. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

11/20/02 November CMP Meeting Qwest (Neil Houston) reviewed the status of this CR and Qwest said that final notification was sent to CLECs on 10/11/02. Neil proposed that this CR be closed. Lori Mendoza with Allegiance agreed this CR could be moved to complete status.

- 10/16/02 October CMP Meeting Linda Hendricks with Qwest reviewed the draft response to this CR dated 10/3/02. Language was updated in the 2-Wire 4-Wire PCAT Version 10 which was published on 10/11/02. There were no questions from the CMP participants and this CR will be updated to CLEC test.

- 09/18/02 September CMP Meeting Minutes Allegiance reviewed the CR submitted and explained that they would like to have the dial tone testing and notification sync up in the PCAT documentation because the process document, PROS.07.19.01.F.00012, is not clear. Allegiance and Eschelon would like the testing process and the notification process of a no dial tone condition on 5-day interval and on longer than standard interval orders clarified. If the CLECs understand when the dial tone testing is done, then, they can adjust the date their translations are complete. Qwest explained that the CLEC is notified 24 - 36 hours before the due date of a no dial tone condition. The dial tone test is performed on DVA, which on 5-day interval orders is 48 hours after application date. Qwest will clarify the process, for 5-day and longer than standard interval orders, in the PCAT. Allegiance said that clarification in the PCAT would satisfy this CR.

- CLEC Change Request Clarification Meeting 3:00 p.m. (Mountain Time) / Monday 26th August 2002

1-877-554-8688 1930099 # PC081902-2 The 48 Hour Dial Tone Testing Requirements

Attendees Terry Wicks, Allegiance Deb Smith, Qwest Linda Hendricks, Qwest Bob Mohr, Qwest Cindy Macy, Qwest Neil Houston, Qwest Linda Sanchez-Steinke, Qwest

Introduction of the participants on the Conference Call was made and the purpose of the call discussed.

Review Requested (Description of) Change Terry indicated that Qwest is not following the process in document number PROS.07.19.01.F.00012. The process is interpreted that Qwest does the dial tone test and then calls the CLEC right away. The following is extracted from the CR submitted by Allegiance: Allegiance believes that Qwest is not complying with the process as stated above. The testing for dial tone is actually being conducted on DVA date (48 hours after Application Date not 48 hours prior to Due Date). Also it is not clear as to when Qwest is notifying the CLEC of no dial tone conditions. This process implies that once the COT forwards the results to the QCCC tester at 48 hours prior to due date, then the tester will immediately notify the CLEC of No Dial Tone conditions. In actual practice, Qwest is not consistently notifying the CLEC at 48 hours prior to cut date. There are inconsistencies between the process and Qwest's actual application of the process. Qwest needs to comply with its published process. This process is not published in the PCAT. The only reference to this process that Allegiance could find was the mailout sent to CLECs on July 19, 2001.

Confirm Areas & Products Impacted Unbundled Loop 2 wire 4 wire Analog Voice Grade, Coordinated and Basic Option

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call. Identify/Confirm CLEC’s Expectation

Allegiance requests the following deliverables on this CR: - Update the PCAT with the Qwest process, and the agreed upon number of hours before due date the dial tone check is done, and, the agreed upon number of hours before the due date that the CLEC is notified of a no dial tone condition. - Provide notification of the process above - Improve on the CLEC notification process when there is a no dial tone condition. Determine the minimum number of hours before due date that the CLEC’s would like to be notified of a no dial tone condition.

Identify any Dependent Systems Change Requests PC081902-1, PC050302-1

Establish Action Plan (Resolution Time Frame) Allegiance will clarify and review this CR at the 9/18/02 CMP Meeting. Qwest will present the draft response at the 10/18/02 CMP Meeting.


CenturyLink Response

October 3, 2002

Lori Mendoza LEC Account Manager Allegiance Telecom, Inc.

SUBJECT: Qwest’s Change Request Response - CR #PC081902-2 48 Hour No Dial Tone Notification

This in response to Allegiance Telecom’s Change Request (CR) PC081902-2. This CR requests that Qwest clarify its 48 Hour No Dial Tone notification process and to document the process in the PCAT.

Qwest accepts this CR and the following language has been added to the 2-Wire or 4-Wire Analog (Voice Grade) Loop V10 PCAT.

Qwest verifies for dial tone at your CFA 48 hours after Qwest’s APP (application) date. If Qwest finds No Dial Tone (NDT), Qwest will retest 48 hours prior to due date. If dial tone is still not present, Qwest will email the NDT results to you through Qwest’s Provider Test Access (PTA) email system. You will receive the NDT PTA email notification approximately 24 to 36 hours prior to the due date. Qwest will email only when there is No Dial Tone. You will need to supply the dial tone by the due date or supplement the LSR, changing the due date.

This language is in document review and will be published to the Wholesale PCAT web site on October 11, 2002.

Sincerely,

Neil Houston Staff Advocate Policy & Law

Linda Hendricks Lead Project Analyst

cc: Mary Retka, Director, Technical Regulatory Interconnection Planning


Open Product/Process CR PC010302-1 Detail

 
Title: RSUs the inabilitiy to provision UNEs
CR Number Current Status
Date
Area Impacted Products Impacted

PC010302-1 Denied
7/17/2002
Ordering Collocation: Physical UNE: Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Mohr, Bob
Director:
CR PM:

Description Of Change

PON 928898-LP LSR#3330778 Orders D66190766, N66190767 - N66190789 The cancellation of these orders in the Dry Creek Colo states "This customer comes out of a remotely located central office and unbundled loop is not an available product."

Qwest does not allow the provisioning of an Unbundled Loop within a colocation when an End User is serviced by a Remote Switching Unit (RSU). The orders are cancelled and a reject notice is sent to the CLEC. At this time, the CLEC has absolutely no recourse to be able to switch this customer's local service over to that CLEC. The inability to switch an End User that is serviced by a RSU over to a facility based CLEC is unacceptable and anti-competitive. The End User also has no capability to choose another carrier for local service. Allegiance has spent tremendous amounts of money to co-locate in Qwest Central Offices in order to be able to swith Qwest customers over to Allegiance facilities. Allegiance is requesting that Qwest develope a means to allow the switching of End Users service by a RSU to CLEC facilities .


Status History

01/02/02 - CR submitted by Allegiance.

01/03/02 - CR acknowledged by P/P CMP Manager.

01/04/02 - Allegiance contacted to coordinate available times for clarification call.

01/11/02 - Conducted Clarification Meeting with Allegiance.

01/18/02 - Issued Clarification Meeting Minutes to Allegiance.

02/20/02 - CMP Meeting - CLEC Community Clarification held. It was agreed that the CR would move to Evaluation. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/04/02 - Conducted additional Clarification Meeting with Allegiance.

03/07/02 - Issued 3/4/02 additional Clarification Meeting minutes to Allegiance.

03/13/02 - Issued Qwest's Draft Response dated March 12, 2002 to Allegiance.

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 12, 2002. It was agreed that the CR could be moved into CLEC test. Qwest to respond to an action item where Allegiance will reevaluate the CR status. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/22/02 - Formal response dated March 12, 2002 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses.

04/15/02 - Issued E-Mail to Allegiance with EEL and Loop pricing.

04/17/02 - CMP Meeting - Allegiance disagreed that the CR should be in CLEC Test. Allegiance restated its intent of the CR. Qwest to review and provide a revised response. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. The CR status will be revised to Presented.

05/08/02 - Issued Qwest's Supplemental Response dated May 2, 2002 to Allegiance.

05/10/02 - Supplemental response dated May 2, 2002 issued to CLECs. Notification CMPR.05.10.02.F.01265.Final_CR_Response.

05/15/02 - CMP Meeting - Qwest presented its Supplemental response. Qwest to respond to action items generated at the meeting. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CLEC participants requested that the CR remain in a Presented status.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Presented.

06/28/02 - Clarified with Covad their request identified under Action Item No. 4. Issued e-mail with uderstanding.

06/28/02 - Reviewed Qwest's response to Action Item No. 5 with John Sheehan, Frontier Communications (Electric LightWave) and sent e-mail with Interactive Report link.

06/28/02 - Received e-mail confirmation from Frontier Communications that Action Item No. 5 can be closed.

07/10/02 - Sent email to Covad, Allegiance, and Eschelon containing responses to additional questions associated with open action items 2 and 4.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Denied.and remaining open action items (2 and 4) were closed.


Project Meetings

07/17/02 - July CMP Meeting Minutes: Qwest presented the latest responses to open Action Items 2 and 4 which had been sent to Eschelon, Allegiance, and Covad on July 10, 2002 for comment. CLECs agreed the Action Items could be closed. CR status changed to deny.

Subject: Re: CR Location Date: Fri, 28 Jun 2002 14:05:05 -0400 From: John Sheehan Organization: Frontier / ELI Carrier Services To: Richard Martin

Rick, Sounds fine. This can be closed.

--

Subject: CR Location Date: Fri, 28 Jun 2002 10:56:25 -0600 From: Richard Martin Organization: Qwest Communications International, Inc. To: johnsheehan@frontiercorp.com

John,

Go to URL, http://www.qwest.com/wholesale/cmp/changerequest.html

Click on, "CLEC Qwest Change Request - Product/Process Interactive Reports" to launch the interactive report. The report is in Adobe Acrobat.

When in the report, click on the blue button with CR number PC010302-1. Review Action Item No. 5.

If the response satisfies the intent of Peder's question, please advise. If further clarification is required, please let me know.

Thanks

Ric

--

Subject: Action Item 4 to CR PC010302-1 Date: Fri, 28 Jun 2002 09:28:57 -0600 From: Richard Martin Organization: Qwest Communications International, Inc. To: Mike Zulevic CC: Craig Saunders , Kelly Trachsel

Mike,

Based on our conversation regarding Action Item 4 to the subject CR, the response, which is stated below, didn't fully answer what you were looking for.

Action Item 4 Question and Answer:

Q. Covad expressed the need to have the geographical area of a RSU and the number of lines served by the RSU included in the ICONN database tool.

A. The ICONN database has not been set-up to provide the geographical area of a RSU. This is done through utilization of the DA Maps (refer to CR PC110201-1 and PC012902-1). The number of lines in a RSU will be delineated if the RSU does not share a NXX with another wire center. The number of lines associated with a Central Office NXX can be identified by performing a search on the NPA NXX under the Cetral Office Find tool located at the same URL as Action Item No. 3.

It is my understanding, from our call, that Covad would like to identify what RSUs are tied to a CO, where are the RSUs and what area do they cover.

If this is not correct, please provide further clarification.

Thanks

Ric

-- Subject: CR PC010302-1 Action Item EEL Pricing Comparison Date: Mon, 15 Apr 2002 10:38:51 -0600 From: Richard Martin Organization: Qwest Communications International, Inc. To: Terry Wicks CC: Robert Mohr , Robyn Libadia , Cindy Buckmaster

Terry,

The attached rate sheet is in response to the Action Item on your Change Request PC010302-1 requesting that Qwest provide pricing for an EEL from the Denver Dry Creek to an end-user fed from the Denver Tech Center wire center. You also requested rates for an Unbundled Loop to feed this same user from the one wire center.

The attached rates are for the EEL and UNE products for an EEL from the Drycreek office to an end-user fed from the Tech Center wire Center. As the only way to feed a customer located in the Tech Center Wire Center on an Unbundled Loop is with a collocation placed in the Tech Center Wire Center, the pricing example for the Unbundled Loop is for an Unbundled Loop feed from a collocation space located in the Tech Center Wire Center.

The rates for the EEL were taken from the Qwest templated agreement and, because Allegiance currently doesn’t have the ability to order EELs in Colorado in their contract, a request of this kind would require an amendment to the Allegiance Interconnection Agreement (ICA) before ordering could commence on this product. Rates for the loop were taken from the Allegiance ICA . Collocation would also need to be established at the Tech Center wire center for this example.

Please contact us if you require additional information on these products, or have any questions.

Sincerely,

Ric Martin - CRPM (303) 896-9823 Robyn Libadia- EEL Product Manager (253) 445-0234 Bob Mohr- Unbundled Loop Product Manager (303) 896-2160

PC010302-1 Allegiance response 4-12-02.xls

--

CLEC Change Request Clarification Meeting

March 4, 2002, 9:00 (MT) Conference Call

PC010302-1, RSUs – the inability to provision UNEs

Attendees: Ric Martin, Qwest Cheri Hurless, Qwest Bernadette Derlein, Qwest Cindy Buckmaster, Qwest Terry Wicks, Allegiance

Introduction of Attendees Introduction of the participants on the Conference Call was made. Qwest explained that they wanted to review the current situation and get feedback from Allegiance.

Review Requested (Description of) Change Cindy advised that Qwest would be providing a drawing explaining how the Dry Creek CO was configured to the Tech Center RSU. Cindy explained that the Tech Center was connected to the Dry Creek CO by a transport medium (umbilical) and the end user would have a loop to the Tech Center. Cindy explained that there were two ways a CLEC could get a loop for the end user connected to the Tech Center. The first would be for the CLEC to be physically collocated in the Tech Center. The second would be to request an EEL from the dry creek office at whatever transmission level for the end user. Terry wanted to know how to tell if a customer was serviced out of an RSU. Cindy advised that the Raw Loop Data Tool cable field designation of EX would indicate this. Terry advised that it wasn’t practical for them to obtain a certificate for all their sales folks and to check each address separtely. Cindy explained that there is a Raw Loop Data Dump for each central office that would allow for various sorts on the data in the RLDT. A sort could be made on cables with EX and then by address. Terry asked if Qwest could provide information on how the transport for an EEL works and a narrative on the Raw Loop Data Dump. Terry asked about the RSUs that were tied to Dry Creek CO, Eagan, MN and Chandler AZ. Qwest will identify those RSUs tied to those Central Offices Qwest Identified the following Action Items to address: 1. Breakdown how an EEL works that uses a MUX, riding a higher capacity transport 2. Identify how collocation would occur in the different types of RSUs. 3. Identify the Raw Loop Data Tool Training available. Terry requested Qwest to address why the CLEC cannot obtain a loop for an end user that is identified out of the Central Office of record.

CLEC Change Request Clarification Meeting

Date: January 11, 2002, 9:00 (MT) Place: Conference Call 877-564-8688 Subject: PC010302-1, RSUs – the inability to provision UNEs

Attendees: Ric Martin, Qwest Neil Houston, Qwest Laurel Neher, Qwest Bernadette Derlein, Qwest Cindy Buckmaster Terry Wicks, Allegiance

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Terry reviewed Allegiance’s CR. He explained that they had several orders they had to cancel due receiving reject notices on orders for UNEs. The problem indicated that COs customers given service by RSUs and routes to the CO where they are collocated and there is no place to cross connect. They are unable to port because they are in a RSU. He explained that they do not know they are in a RSU when processing an order. Laurel explained that the RSU would look like a CO. The switch depends on another switch for intelligence. She said that the LERG should have the CLLI. Qwest will look at the LERG to see if it has the information. Qwest thought that the NPNAXX would have the CO location. Neil advised that the Account Manager should advise which Colos have RSUs. The following COs have RSUs: Colorado – Dry Creek ? Center Park ? Denver SE ? Denver Tech Center – ISDN ? Aberdene ? Northglen Minnesota – Egan Arizona – Chandler Laurel explained that the RSU would need to the loop extended to the CO and this is done by ordering an EEL. Terry indicated that they look at customers that are serviced out of the CO where they are collocated at. Neil asked if Allegiance had any volume on the number of instances this is happening. Terry indicated that he did not. He advised that the reject notice was 10/24. Terry provided the TNs that were involved: RFG Management, Inc. 8400 E Cressent Parkway, suite 475, Greenwood Village, 80111, 303-771-0321. Banta, Hoyt, Everall 7979 Tufts Parkway, sutie 1050, Denver 80237, 303-220-8000 Terry indicated that he could go to the Raw Loop Data Tool and pull the address which provides the cable name fixed EX, but he could not identify on a CSR. Terry asked how Qwest determines a customer is in a RSU. Neil advised that it was a matter of Geography. The RSU is an electronic switch with a switch module connected by a TI to the CO. Neil advised that the customers referenced by Terry are in the Denver Tech Center. He explained that the loop is coming out of the RSC and doesn’t extend to the CO. Terry asked what is covered and what is available to view by CLEC. He does not want to have the cost of adding the EEL. He wants to be able to port from the CO where the records show the CO. His record is the CSR. Laurel indicated that the LERG should be used to determine the CO. Terry advised that another ILEC, GTE, put a card in their switch.

Identify/Confirm CLEC’s Expectation Allegiance wants to be able to port a UNE serviced out of an RSU from the CO where the records show the RSU’s CO is serviced and do not want to pay an additional cost.

Establish Action Plan (Resolution Time Frame) Qwest will identify what is contained in the LERG. The CR will have the collective CLEC clarification and SME input at the February CMP meeting.


CenturyLink Response

May 2, 2002

Terry Wicks Allegiance Telecom Inc

SUBJECT: Qwest Change Request Supplemental Response - CR PC010302-1 Remote Swiching Unit- Inability to provision UNEs

This letter is in response to the additional clarification requirements provided at the April 17, 2002 CMP Monthly Meeting on your Change Request PC010302-1 and supplements Qwest’s response dated March 12, 2002. The additional clarification requirements requested that Qwest:

1) Consider the reduction of the Non-Recurring Charge (NRC) for the EEL to allow a CLEC to order the EEL at the Loop NRC price. 2) Consider the elimination of transport rates where the transport would otherwise be billed in the EEL product. 3) Consider the identification of RSUs upon application of the CLECs for a collocation so as to ensure the CLECs make sound decisions about where to spend their collocation monies.

In response to items 1 and 2 above, Qwest’s research indicates that Qwest is in alignment with other ILECs on the handling of RSUs. As described in Qwest’s March 12, 2002 response, Qwest deploys RSUs in a number of situations. Primary among these situations is the deployment of augment switches to accommodate growth in a given geographic area. Installation efforts for EELs are more time and labor intensive than those for UBL, thus the higher NRC. In regard to transport, at times, the new RSU is either programmed to have the same NXX as the host, or has a unique NXX. Where the NXX is the same as the host, mileage is rated at $0. If the NXX is unique, mileage is calculated and the appropriate band rate applies. Reduction of the non-recurring charge or the elimination of the transport rate would tend to undermine both the embedded EEL and Collocation base. Based on our alignment with other ILECs, and the additional cost of the EEL product, Qwest is unable to reduce the NRC or eliminate the Transport charge from EELs provisioned under this arrangement.

In response to item 3, CLECs have access to several resources that indicate the structure of the Qwest network. Among these resources, the Raw Loop Data Tool indicates remotes via the ‘EX’ cable naming convention and the ICONN Database is being modified to identify remotes assigned to a given Central Office. As Qwest is not in a position to counsel CLECs on the construction of their network, Qwest would encourage CLECs to perform their own analysis and research.

Sincerely,

Cindy Buckmaster Product Manager Unbundled Loop Qwest Communications

CC: Bill Campbell – Product Director Qwest Communications Richard Martin – CMP Project Manager Qwest Communications

-

March 12, 2002

Terry Wicks Allegiance Telecom Inc

SUBJECT: Qwest Change Request Response - CR PC010302-1 Remote Swiching Unit- Inability to provision UNEs

This letter is in response to your Change Request PC010302-1 requesting that Qwest develop a process to allow the switching of end users service via an RSU to CLEC facilities.

General Information

The structure of the Qwest network occasionally results in the placement of Remote Switching Units (RSUs). These RSUs are a “spin off” of a host wire center and are created where geographic distance and/or population density requires. For the purposes of the Unbundled Loop, an RSU becomes the serving wire center for the end users it touches. As RSUs are deployed, end users served by the RSUs are terminated at the RSU. The structure between the host and the remote units becomes transport, therefore, there is no contiguous loop between the host and the end-users served by the RSU. End users of the remote are not individually identified at the host.

The underlying requirement of an Unbundled Loop is a Collocation in the serving wire center. The serving wire center for end users in the remote is the remote Central Office. Unbundled Loop can be ordered out of the remote only if the CLEC is collocated in the remote.

How to tell if an end user is in a RSU

The Raw Loop Data Tool (RLD) provides the CLEC with the information during pre-order to determine that the end user customer is served from an RSU. In the Raw Loop Data Tool the end user’s cable pair will indicate an “EX” prefix when the facility originates from an RSU (i.e., F1 ca EXA7).

There are two versions of the RLD tool. Using the IMA version a CLEC can view information specific to an end user address. With a digital certificate the CLEC can use the wire center version of the Raw Loop Data Tool. Data from this version of the RLD tool can be downloaded into an Excel spreadsheet or a database provided by the CLEC. Using the “File, Save As” commands from the browser software the CLEC can save the information to the location and in the format they prefer. Approximately 50 – 150 MB of disk space is needed per wire center. The process may be time intensive, as each wire center is checked separately.

See Loop Qualification and Raw Loop Data- CLEC Job Aid on URL http://www.qwest.com/wholesale/training/coursecatalog.html

How to serve customers in an RSU

The first option available to CLECs, to serve end users in a Remote Serving Unit (RSU), is to Collocate in the RSU.

Central Office Collocation:

For Central Office Collocation, each Central Office will be evaluated to determine if your Collocation requirements can be met (e.g., space, power, and heat dissipation).

Three types of Central Office Collocation are available:

Physical Caged Collocation – Allows the CLEC to physically collocate the CLECs own equipment in a Qwest Central Office in a space that is completely enclosed via chain link fencing. The CLEC installs, maintains and repairs their collocated equipment.

Physical Cageless Collocation - Allows the CLEC to physically collocate the CLECs own equipment in a Qwest Central Office in a space shared by Qwest and other CLECs that opt for Cageless Collocation. The CLEC installs, maintains and repairs their collocated equipment.

Virtual Collocation - Allows the placement of the CLECs equipment in a Qwest Central office, however, Qwest will install, maintain and repair the CLECs collocated equipment. In a Virtual Collocation arrangement, the CLEC does not have physical access to the virtually collocated equipment in the Qwest Central Office.

More information can be found in the Collocation Product Catalog (PCAT) at: http://www.qwest.com/wholesale/pcat/collocation.html

Enhanced Extended Loop (EEL):

The second option available to CLECs to serve end users in an RSU, is to request an Enhanced Extended Loop (EEL).

As the facility between the host Central Office and the remote Central Office is transport, the requested EEL would originate in the host office, extend through the remote Central Office and terminate at the end users premises. EEL can be ordered in two configurations; point-to-point (one transmission level from point of origination to point of termination) or Multiplexed EEL (a higher transmission level between the two central offices and a lower transmission level to the end user).

The "Multiplexed EEL" most closely resembles the network Allegiance has described. The CLEC can order a Multiplexed EEL with transport from their Collocation to another Qwest wire center. The Multiplexed EEL must be turned up before ordering EEL links (loops) to be connected to the Multiplexer. The EEL link orders must provide CFA (CKTID and slot number from the Multiplexed EEL). Each EEL, whether link or multiplexed, is ordered via an LSR. Standard intervals apply to each LSR EEL request. Intervals may be found under EEL/LMC in the Interconnection Service Interval Guide (SIG), also located on the Qwest wholesale website: http://www.qwest.com/wholesale/guides/sig/index.html

An abbreviated copy of that SIG has been attached to this document for ease of discussion (see Attached).

More information can be found in the EEL Product Catalog (PCAT) at: http://www.qwest.com/wholesale/pcat/eel.html

Billing elements are further described in the EEL PCAT and each billing element is labeled on the PCAT diagram. Billing elements for this situation are defined below.

Monthly recurring charges for a DS1 or DS3 multiplexed EEL, originating from a collocation, include: ITP, for the connection to the collocation, transport between the two Qwest wire centers, and multiplexing. Multiplexed EEL nonrecurring charges include transport and are applied to the multiplexer.

Monthly recurring charges for the DS1 or DS0 EEL links would be for the link only. EEL link nonrecurring charges include transport and are applied to the link.

Channel Performance charges may also apply (for DSO only).

A CLEC requiring EEL will need both EEL language and all applicable rate elements in their Interconnection Agreement in order to prevent rejection of the LSR. A CLEC with incomplete or no EEL information will need an amendment before EEL can be ordered. All rates and charges associated with EEL can be found in the CLEC Interconnection Agreement or the SGAT, Exhibit A.

Summary

As described above, Qwest will provide CLEC access to all end users, including those served by an RSU. As Qwest’s network complexities are vast, requests may require individual case basis (ICB) review. Qwest continues to modify its process to ensure CLEC access on a timely basis. Status will be provided in accordance with Change Management Process notification methods as updates to the process warrant.

Sincerely,

Bernadette Derelin Product Manager Unbundled Loop Qwest Communications

CC: Bill Campbell – Product Director Qwest Communications Cindy Buckmaster- Product Group Manager Unbundled Loop Qwest Communications Debra S Smith- Product Manager Unbundled Loop Qwest Communications Neil Houston – Network Qwest Communications Richard Martin – CMP Project Manager Qwest Communications


Open Product/Process CR PC050302-1 Detail

 
Title: Email Notifications of No Dial Tone at 48 Hours
CR Number Current Status
Date
Area Impacted Products Impacted

PC050302-1 Completed
4/15/2009
Other: Coordinated Hot Cuts and Regular Cuts Unbundled Loop, UNE
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Houston, Neil
Director:
CR PM: Harlan, Cindy

Description Of Change

The current process for the QCCC is to call Allegiance with notifiction of No Dial Tone at 48 hours prior to cut date. Allegiance would like to receive all notifications of NDT at 48 hours prior to cut date through email using Qwest's PTA tool in place of receiving these notifications by telephone calls or leaving voice mails.This will allow proper tracking of NDT notifications by both Qwest and the CLECs. This will also insure the CLECs have sufficient time to achieve dial tone prior to cut date. Allegiance believes that receiving email notifications will save a lot of time for both Qwest and the CLECs


Status History

05/03/02 - CR Submitted by Qwest.

05/03/02 - CR acknowledged by P/P CMP Manager

05/06/02 - CR posted to Web

05/09/02 - Schedule Clarification Meeting with Allegiance for this date.

05/09/02 - Conducted Clarification Meeting with Allegiance.

05/14/02 - Issued Clarification Meeting minutes to Allegiance.

05/15/02 - CMP Meeting - Allegiance introduced its CR. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/10/02 - Received e-mail from Allegiance providing spreadsheet on the NDT trial.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status was changed to Evaluation.

07/10/02 - Initial response sent to Allegiance and posted to the Web

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Development.

07/20/02 - Qwest issued formal response to the CLEC Community. Notification CMPR.07.29.02.F.01300.Final_CR_Responses.

08/21/02 - CMP Meeting - Qwest provided a status on issuance of the Level 3 notification. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

09/05/02 - Qwest issued Initial Notification on e-mail notification process. Notification PROD.09.05.02.F.00818.Analog_Loop_2_4_Wire.

09/18/02 - CMP Meeting - Qwest advised that the Level 3 notification was issued and the comments cycle ends 9/20/02. Minutes on this CR to be posted to the Project Meetings section. It was agreed that the CR would be status as CLEC Test.

09/26/02 - Qwest issued Final Notification on e-mail notification process. Notification PROD.09.26.02.F.00830.Analog_Loop_Final. Effective date of change is 10/11/02.

10/16/02 - CMP Meeting - Qwest explained this process was implemented 10/11/02. Minutes on this CR to be posted to the Project Meetings section. It was agreed this CR would stay in CLEC test until next month.

11/20/02 - CMP Monthly Meeting agreed to close this CR.


Project Meetings

Qwest explained this process was implemented effective October 11, 2002. No issues have been identified with the process and Qwest requested to close this CR. Lori Mendoza - Allegiance advised they are using the process and it is working without any issues. Allegiance and the other CLECs in attendance agreed to close the CR.

10/18/02 October CMP Monthly Meeting Minutes Qwest explained this process was implemented effective October 11, 2002. As of October 16, four CLECs have signed up to receive E-Mail Notification of NDT via the PTA tool. Eschelon verified that if you do not sign up for email notification via the PTA tool then you will not get any NDT notification, as the only method of NDT notification is now the PTA tool. CLECs can continue to sign up at any time. Qwest agreed to leave the CR in CLEC Test since this process was just implemented, with potential closure in November.

09/18/02 September CMP Monthly Meeting Minutes

Qwest advised that the Level 3 notification had been issued and that the comment cycle was scheduled to end this Friday, September 20th. Qwest advised that Qwest Service Managers had sent out notifications to their CLECs advising them to provide their e-mail address. The CLECs expressed concern over the 48-our language as written and intervals that were longer than the standard intervals. Qwest confirmed that the 48-hour notification was from the due date and this would be clarified in the PCAT or in writing. CLECs expressed concern over participation in the trial. It was agreed that next time Qwest does a trial, Qwest could evaluate if additional CLECs need to be involved. CLECs requested that the final notification advise the CLECs of the impact of the e-mail notification change. Qwest advised that they would add language in the final notification that advises the CLECs that if they do not provide an e-mail address they would not receive the No Dial Tone notifications.

08/21/02 August CMP Monthly Meeting Minutes

Qwest provided a status update on issuance of the Level 3 notice. Qwest indicated that they were holding off until the current 2-wire 4-wire PCAT language gets published to the Web on August 26, 2002. Allegiance expressed concern that issuance was based on the no dial tone PCAT language since they have taken exception to the language. Qwest advised that this could be addressed during the 1:00 p.m. discussion on issuance of the PCAT language. Eschelon advised that they were disappointed that they will need to wait longer for issuance of the Level 3 notice. They stated that Qwest advised last month that it would be issued by this month’s meeting and now they have to wait longer. AT&T asked if they could only have one e-mail. Qwest advised that they could only have one and it must be different than the e-mail if they are receiving test results.

-

07/17/02 - July CMP Meeting Minutes: Qwest will continue with the trial that began May 6, 2002. It is available to all CLECs. Allegiance asked if all CLECs had to request the process in order for it to proceed. Qwest responded that the answer is yes, it is all or nothing. Allegiance stated that there should be a choice and that the Qwest response does not reference the “all or nothing” position. Qwest responded that the Level 3 process will support this effort and will allow other CLEC participation.. Qwest will issue the Level 3 initial notice prior to the August CMP meeting. CR status was changed to development.

Subject: Allegiance - NDT Trial E-mail Notification Final Spreadsheet 5/6 - 5/31/02 Date: Mon, 10 Jun 2002 11:36:25 -0500 From: "Wicks, Terry" To: "'Cheri Hurless'" , "'Deni Toye'" , "'Kathie Simpson'" , "'Linda Hendricks'" , "'Mary Pat Cheshire'" CC: "Reece, Mamie" , "Best, Doreen" , "Hill, Todd"

Here is the finalized spreadsheet with the data and comments captured for May. The trial is continuing through June and I will have a separate spreadsheet for June.

<>

Terry Wicks LEC Account Manager allegiancetelecom, inc 469-259-4438 terry.wicks@algx.com

--

CLEC Change Request Clarification Meeting

May 9, 2002, 3:30 p.m. (MT) Conference Call 877-564-8688 PC050302-1, E-Mail Notification of No Dial Tone at 48 Hours

Attendees: Ric Martin, Qwest Neil Houston, Qwest Mike Raleigh, Qwest Deni Toye, Qwest Terry Wicks, Allegiance

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Terry reviewed Allegiance’s CR. He explained that the initial phone call would roll to voice mail and the issue is with the voice mail notifications falling through the crack. He would like to get an e-mail to have a record to hold Allegiance personnel accountable. Terry advised that there is currently a trial with Qwest and Allegiance on this process that started in February with the QCCC. Deni advised that the trial started May 6th and is to be concluded May 31st. Currently they are having the PTA System send the e-mail. Terry advised that the CR was submitted in addition to the trial to have this process implemented for all CLECs.

Confirm Areas & Products impacted It was confirmed that the area impacted was Provisioning for coordinated hot cuts and basic cuts. The product impacted is UBL, LX—Reuses.

Confirm Right Personnel Nvolved Qwest confirmed that Neil Houston would be the SME for response to this Change Request.

Identify/Confirm CLEC’s Expectation Allegiance would like this process implemented for all CLECs.

Identify any Dependent Systems Change Requests There are no related Systems CRs.

Establish Action Plan (Resolution Time Frame) The trial will complete May 31st. The CR will have the collective CLEC clarification and SME input at the June CMP meeting.


CenturyLink Response

.July 10, 2002

Terry Wicks LEC Manager Allegiance Telecom, Inc.

SUBJECT: Qwest’s Change Request Response - CR # PC050302-1 E-mail notifications of NDT at 48 hours through PTA tool

This is in response to Allegiance’s Change Request (CR) PC050302-1. This CR requests that all notifications of No Dial Tone (NDT) at 48 hours prior to the cut date be provided to the CLEC via e-mail using Qwest’s Plant Test Access (PTA) tool. The current trial of PTA e-mail notifications with Allegiance began on May 6, 2002. The trial with Allegiance will continue during the implementation phase for this CR.

Qwest is able to provide all NDT notifications via e-mail using the PTA tool. PTA notifications require that CLECs provide Qwest with an e-mail address separate from the e-mail address provided for test results. CLECS should send their NDT PTA e-mail location to Deni Toye, dtoye@qwest.com. Qwest will add the CLECs NDT PTA e-mail address to the notification list upon receipt. To provide an efficient and uniform notification, Qwest will provide NDT notifications via the PTA tool to all CLECs.

Based upon Qwest’s understanding of the scope of this CR, Qwest views the implementation of this CR as a Level 3 Product & Process change. Timing of the implementation of this change will be dependent upon the quantity and nature of CLEC comments.

Qwest will seek concurrence for this approach at the July Monthly Product & Process CMP Meeting.

Sincerely,

Neil Houston Staff Advocate Policy & Law

cc: Mary Retka, Director, Technical Regulatory Interconnection Planning


Open Product/Process CR 5608353 Detail

 
Title: CLEC unbundled loop to CLEC unbundled loop conversion (for re use of facilities) Revision B May 25, 2001
CR Number Current Status
Date
Area Impacted Products Impacted

5608353 Completed
8/15/2001
Ordering LNP, Unbundled Loop
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Urevig, Russell
Director:
CR PM:

Description Of Change

Allegiance has submitted orders following this published process and has yet to get an FOC. Every LSR has been rejected. The most common reason for reject is “rejecting lsr for no circuit # provided on lsr” (PON 677170-C1, opened ticket #882725 with IMA help desk. Ticket #882736 was closed. Voice mail left stating that circuit ID is required) another is “not authorized to retrieve CSR” (PON 674152-C1, EDI Help desk ticket #5582316 ), another is “cannot determine changes requested – accnt submitted as “c” – please check and resubmit w/specific changes” (PONs 678784-C2, C3, C4, C5. Did get a FOC on C1, but Susan said it was not typed correctly). On 6/22/01 for PON 684449-C3 and 684449-C4 the rejects were “on a CLEC to CLEC conversion, a circuit number must be provided, and also ACT should be V or Z, (SDC – CAW 888 796 9087). When escalating these rejects, Qwest personnel are not aware of the published process. They insist that the NLSP must provide the OLSP’s circuit ID. Qwest’s published process clearly states that if the NLSP is unable to obtain the circuit ID from the OLSP, the ECCKT field can be left blank. The Service Delivery Consultant will research and determine the circuit ID for the requested migration. This process needs to be sent to all Qwest personnel involved in order writing and training on how to get the circuit IDs within Qwest’s systems needs to take place. It also needs to be sent to the personnel in the call center, the help desk personnel and personnel handling escalations. I did not find one person who was aware of this process, thus the rejects seem valid to them. The alternative might be to give the CLECs access to Qwest’s systems to obtain the proper circuit IDs so that they can be put in the ECCKT field when the LSRs are submitted the first time. Retail doesn’t seem to be having any trouble with their orders when reusing our facilities. They reuse our facilities regularly and as far as I can tell they are not requesting the circuit ID from us prior to submitting their LSR.


Status History

6/13/01 – CR received from Terry Wicks of Allegiance 6/18/01 – Status changed to New – to be Evaluated

6/20/01 – Process implementation for enhanced Circuit ID Process to be verified and presented in interim meeting to be scheduled by Qwest prior to the July CICMP Meeting. (MR) 6/25/01 – Status changed to Reviewed – Under Consideration

7/10/01 – Interim conference call conducted to discuss CLEC to CLEC conversions – meeting minutes sent to the CICMP team on 7/12/01 (MR)

7/13/01 – Drafted response sent to the CICMP Team via email (MR)

8/07/01 – Eschelon and Allegiance confirmed that LSRs are being submitted and handled properly in relation to Qwest’s process on Circuit ID attainment. (MR)

8/09/01 – Revised CR response distributed to the CICMP team via email. (MR)

8/15/01 – CLEC CMP Meeting Product & Process CR 5608353. It was agreed that the CR was closed due to successful processing of LSRs with revised procedure for CKTIDs. Closed


Project Meetings


CenturyLink Response

August 7, 2001

This letter is in response to the following CLEC Change Request Forms #5263137, dated December 1, 2000 and #5608177 and #5608353, dated June 13, 2001. All of these Change Requests pertain to the CLEC to CLEC Migration process. The revised process was released via the Co-Provider Industry Change Management Process (CICMP) on May 25, 2001.

? Re-use of facilities for CLEC to CLEC carrier changes, improving the CLEC to CLEC reuse of facilities process and to ensure nondiscrimination.

? Response: The Qwest Release Notification Forms #5393537 (CLEC Unbundled Loop to CLEC Unbundled Loop), #5393543 (CLEC Unbundled Loop to CLEC Resale), and #5467108 (CLEC LNP with Unbundled Loop to CLEC Unbundled Loop) Revision B, released on May 25, 2001, noted changes in the Pre-Order section that the requirement to obtain the “Circuit Identification Number from the OLSP” is optional. Both Eschelon and Allegiance provided Qwest with examples of orders that were rejected by Qwest due to no Circuit Identification Number provided. After gap analysis, it was determined that additional training of Qwest Service Center personnel and updates to Service Delivery M&Ps were required. The following measures have been implemented:

? An updated Multi Channel Communicator (MCC) New or Changed Information Procedure was issued on July 9, 2001. ? Issued to target Qwest internal personnel in the Wholesale Customer Care, Customer Service, Error Group, Held Order/Escalation, Order Processing and Order Resolution organizations. ? Topic of the MCC: “CLEC to CLEC Migration of an Unbundled Loop and Unbundled Loop to other products.” ? CLEC to CLEC Migration is defined as; unbundled to unbundled, unbundled to resale, unbundled to Centrex resale. ? Emphasis placed on processing orders without circuit ids (ECCKT’s) on LSR requesting migration. ? States included in this communication are; AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NE, NM, OR, Outside 14 State Region, SD, UT, WA and WY. ? All internal job aids and on-line support documentation have been updated. ? Qwest Service Center specific training sessions are currently in progress for both center coaches and center personnel. The training will be on going to ensure process compliance.

Sincerely

Nancy J. Hoag Qwest Wholesale Product Team


Open Product/Process CR PC073101-7 Detail

 
Title: QCCC SUPs entire order NDT for partials numbers on multi line cuts
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-7 Denied
12/12/2001
Ordering Unbundled Loop, LNP
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Aesquivel III, Frederick
Director:
CR PM:

Description Of Change

It is Qwest’s current practice to SUP the entire order on a multi-line cut when there is NDT or other problems on one or more of the TNs, but not the entire list of numbers being ported. It is Allegiance’s position that the CLEC should be able to make the decision to bring the number over “broken” or not. Qwest should not be making the call to not port a number on cut date due to this scenario. The SUPing of these orders creates additional work and processing for both Qwest and the CLEC. This is also increasing the cost associated with processing the order multiple times. When these numbers are not cut on the due date, Allegiance has experienced the trend of loosing these customers. Our credibility and our ability to service the end user are jeopardized at the very start of the relationship. Allegiance feels that the current Qwest practice to SUP these orders is anti-competitive and therefore the CLEC should have the final say in bringing the Customer over “broken” then effect repair whether it be on the CLEC side or the LEC side in order to fulfill our obligation to the end user as outlined in our signed contract with them.

Granted the process of the 48 pre-testing will catch most of these ahead of cut date, things happen on cut date that cannot be prevented. Allegiance wants the decision to bring the lines over or not to be the CLEC’s call.


Status History

07/30/01 - CR submitted byTerry Wicks

07/31/01 - Status changed to New – To be Reviewed

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - Allignment meeting held with Allegiance

08/09/01 - Draft response completed.

08/20/01 - Minutes issued of Alignment Meeting held 08/09/01.

08/23/01 - Clarification Meeting held with Allegiance, minutes issued.

08/29/01 - CR escalated to Scott Simanson, VP. Scott reaffirmed Qwest's position, See attached response.

09/07/01 - Walk through Meeting Held

09/19/01 - CMP meeting - Qwest presented response. Qwest agreed to re-evaluate this request. Status changed from presented to evaluation; Qwest revisiting response.

10/09/01 - Revised Draft Response posted to Database

10/17/01 - CMP Meeting: Qwest presented revised response. Allegiance would like to have Rational and Justification as to why CR was denied.

10/31/01 - Qwest to explain policy issues as it relates to multi-line cuts and will work on cut date issues.

11/14/01 - CMP Meeting: Allegaince not in attendance. Fred Aesquivel/Qwest to provide update at December CMP Meeting.

12/12/01 - CMP Meeting: Request was denied, status changed to denied.

12/28/01 - Formal response dated 10/9/01 issued to CLECs

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

09/07/01 - Walk through Meeting Terry Wicks - Allegiance, Todd Mead, Linda Hendricks & Dave Maier - Qwest Reviewed Qwest revised response. Qwest will not hand over circuits with dial tone problems (either on Qwest or CLEC side). However Qwest will be flexible on cut date and will work with the CLEC. Allegiance wants further clarification around the definition of 'flexibility'. Allegiance want to escalate this issue - however, this CR has already been escalated internally to the Vice President level as per the existing CMP escalation procedure.

Action : Linda Hendricks will provide definition of Qwest 'flexibility' on cut date. Allegiance will submit a new CR to clarify the Qwest process when dial tone problems are on the Qwest side.

August 23rd, 2001 Clarification Meeting 1-866-289-7092 PC 741-1286 # PCCR073101-7

Terry Wicks/Allegiance Patrick Weston/Allegiance Doug Barman/Allegiance Linda Hendricks/Qwest Todd Mead/Qwest Introduction of Attendees Terry, Patrick, Doug, Linda and Todd Review Qwest Response Linda’s response to the original CR (PCCR073101-7) was discussed. Essentially Qwest will not hand over bad circuits to a CLEC. In mitigation, Qwest has implemented the 48/1 hour DT test on July 29, 2001 to resolve this issue. There is also the opportunity for the CLEC to split the order and have the bad circuits moved to another LSR. CLEC Response Allegiance accepted that when there is no DT on the Qwest side, Qwest should not hand over circuits until the problem has been resolved. Allegiance’s position is that they would still like to be able to take the circuit. If Qwest is consistently pre-testing on their side at least 48 hours prior to cut date, then the number of incidents of bad facilities on the Qwest side on cut date should be minimal. Allegiance will track and report accordingly. Allegiance will not pursue the issue at this point when the circuit is “bad” on the Qwest side. However, they will be pursuing to take the circuit when the problem is on Allegiance’s side. Allegiance agreed that the 48/1 hour DT test implemented on July 29 should substantially reduce the number of occurrences related to this issue on the Allegiance side. However, when the “no DT” is on the CLEC side, Allegiance wants to have the circuits passed over “as is”, and do not want to split the order. Allegiance has options to get the end user service on any “broken” line when the NDT is on their side. Once the TN is activated and Allegiance has the number in their switch, they can call forward the line to another line or to cell phones they supply to the end user. Allegiance has processes in place that they use daily with this type of situation when dealing with the other LECs. Allegiance would like to be able to use their processes in this situation with Qwest as well. Allegiance is prepared to escalate as needed if this cannot be resolved at this level. Confirm Right Personnel Involved Scott Simanson, VP and Fred Aesquivel Director (Qwest) need to be involved to make the final determination on Qwest’s position with respect to this issue. An internal meeting involving these people needs to take place. Todd will organize. Identify/Confirm CLEC’s Expectation Allegiance wants Qwest to hand over good circuits if the “no DT” is on the CLEC side. Allegiance stated every other ILEC they deal with (including PacBell, SW Bell, Bell North and South, Verizon and Ameritech) do this, as part of their normal business. Establish Action Plan (Resolution Time Frame) Review these minutes as an accurate account of this mornings discussion Set up a meeting with Scott, Fred and Linda to discuss Qwest’s position and draft a response. Set up a walk-through meeting with Allegiance to discuss the Qwest final response.

08/23/01 - Clarification Meeting Allegiance - Terry Wicks, Patrick Western, Doug Baram Qwest - Linda Hendricks, Todd Mead

Allegiance accepted that when there is no DT on the Qwest side, Qwest should not hand over circuits until the problem has been resolved. Allegiance agreed that the 48/1 hour DT test implemented on July 29 should substantially reduce the number of occurrences related to this issue. However, when the “no DT” is on the CLEC side, Allegiance wants to have the circuits passed over “as is”, and do not want to split the order.

08/09/01 - Alignment Meeting Terry Wicks/Allegiance Qwest - Scott Simanson, James Mackie,Dana Frenking, Linda Hendricks, John Moore, Cindy Buckmaster, Nancy Hoag, Lisa Schuzer

Turning up loops that do not meet Qwest test requirements or do not have CLEC DT on them. Their example was if they send in an LSR with 10 loops and 2 do not have CLEC DT on them or if Qwest has a facility problem, Qwest should allow Allegiance to make the decision to accept all of the orders even if problems exist. They want Qwest to close the order and open a repair ticket to provision the loops with the problems. No CLEC DT concern: Turning up loops that do not meet requirements will leave Qwest and the end user in a vulnerable position. If the CLEC decides they can't get DT working after we have closed the order and (if applicable had the translations ran), the end user customer could be out of service. Qwest wouldn't be able to work the order back, because it is closed. In order for the end user to get back to Qwest they would need to issue a WINBACK order and the CLEC would need to issue a disconnect order on the "BAD circuit/loop turned up". Qwest's facilities concern: If Qwest has the problem and our facilities are bad or maybe in some cases won't be built out at all, the following could occur if loop is turned up bad: mask facility issues on Qwest side (or perceive that is what we are doing) open the door for repair PID issues open our selves up to many issues from provisioning to repair PID measurement accuracy billing on a bad loop


CenturyLink Response

October 09, 2001

Wholesale Product Marketing

This letter is in response to the following CLEC Change Request Form PC073101-7 dated 07/30/2001. The Change Request related to Qwest’s current practice to not complete all circuits and/or orders on a given LSR, when there is known trouble either in the Qwest or CLEC network on one or more of the circuits being turned up.

In an effort to minimize the risk of the of an out of service condition during a migration, and to ensure the readiness of all parties to maximize success, Qwest has put the following process improvements in place:

48-Hour Dial Tone Check – Qwest Central Office Technician (COT) tests for Dial Tone at the CLEC CFA on the ICDF 48 hours prior to the scheduled cut. If Dial Tone is not present, the COT notifies the Qwest QCCC Coordinator, who in turn notifies the CLEC. This gives the CLEC 48 hours to correct the no dial tone condition.

1 Hour Dial Tone Check – Qwest COT tests for Dial Tone at the CLEC CFA on the ICDF 1 hour prior to the scheduled cut. If Dial Tone is not present, the COT notifies the Qwest QCCC Coordinator, who in turn notifies the CLEC. This second notification gives the CLEC an hour to correct the no dial tone condition.

Field Pre-Survey - Qwest Field Technicians Pre Survey outside plant facilities to identify any before due date. If Field Technicians determine that facilities are not available or acceptable for the service ordered, the Technician invokes an internal Qwest process to search for other facilities or place the order in a held status if suitable facilities are unavailable. The CLEC is then notified of the Held status.

Order Splitting – Qwest has offered to “split” orders on an LSR and “supp” the order with the circuit with the trouble condition at the time of the cut, allowing the CLEC the necessary time to correct the known condition.

After considerable deliberation and reconsideration, Qwest will continue to follow its practice to not turn over circuits that do not meet all defined standards at the time of the migration. CLEC’s retain the right to escalate and to petition through the Bona Fide Request (BFR) process.

Respectfully,

Frederick M Aesquivel III Director – Local Network Operations Support

CC: Scott Simanson Linda Hendricks Dana Filip


Open Product/Process CR 5548229 Detail

 
Title: Same day pair change during test and turn up (day of cut)
CR Number Current Status
Date
Area Impacted Products Impacted

5548229 Completed
8/21/2002
Ordering Unbundled Loop, LNP
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Toye, Deni
Director:
CR PM: Thomte, Kit

Description Of Change

Allegiance is requesting that a process be put in place by Qwest to allow for a same day pair change on the day of the cut, during test and turn up, when Allegiance has determined that our assigned pairs have become defective. Currently on cut date when Allegiance has determined that our pairs are bad, Qwest requires Allegiance to SUP the order with the necessary pair change information and a new due date of 5 days out is given thus delaying the cut and possibly loosing the customer. There currently is a process in place within Qwest to do a same day pair change on repair tickets. After a customer has ported to Allegiance and the pairs become defective, Allegiance can issue a change order with new pair information. Once the FOC is received, Allegiance opens an assist-type, or “AT” ticket with Qwest Repair to change the pairs. When we open the assist-type ticket the COT knows that there is a pending order and is able to work the “AT” ticket from the word document generated when the LSR change order has been submitted and FOCd. This process only takes a few hours once Allegiance has submitted the change LSR to Qwest. Allegiance is requesting that a similar process be put in place to accomplish a same day pair change on cut date to save the cut.


Status History

5/10/01 – CR received from Terry Wicks of Allegiance 5/14/01 – CR logged and status changed to New – To be Evaluated

5/16/01 – Status changed to Reviewed – Under consideration

6/15/01 - Allegiance is requesting that a process be put in place by Qwest to allow for same day pair change on the day of the cut, during test and turn up when Allegiance determined that our assigned pairs have become defective. When it is determined that Qwest pairs are faulty at test and turn up, Qwest will try and assign new pairs so that the order can be turned up on the due date. If there are not any spare pairs to assign to, then the order will go into RTT and will be worked through that process. If we are talking CFA change, and Allegiance finds out that the Allegiance CFA is bad on test and turn up, then this poses a few issues. The outside workforce and the Central Office workforces are assigned their workloads 48 hours in advance. Also, if the CFA move work is completed in the Central Office, but a LSR is never received to update the records, the CLEC would run the risk of being put out of service since our records would indicate that the CFA was actually in a different slot. This would also pose a problem if a case of trouble was reported. The actual CFA would not be what the records would show. (DT)

8/09/01 – CR response sent to the CICMP team via email and included in the August CICMP Distribution Package (MR)

8/15/01 – CLEC CMP Meeting. Terry Wicks advised that they haven’t been experiencing any problems and it would be OK to close. Jim Beers indicated that we would show the CR as accepted until procedure is working with CLEC.

08/30/01 - CR is in CLEC test, Allegiance will give update at September 19th CMP Meeting

09/19/01 - CR to remain in CLEC test. Qwest will investigate and provide feedback on issues raised by Allegiance.

10/05/01 - Clarification Meeting Held with Allegiance. Russ Uriveg and Deni Toye to respond to Allegiance issues.

10/10/01 - Revised draft response completed and posted to database.

10/17/01 - CR to remain in CLEC test. Allegiance indicated they were still not receiving FOC . Qwest will investigate and provide feedback on issues raised by Allegiance via revised Qwest response at November CMP Meeting.

10/24/01 - Qwest Response issued to CLEC Community

11/14/01 - CMP Meeting - Allegaince not in attendance. Deni Toye to discuss at December CMP Meeting.

12/12/01 - CMP Meeting, Allegaince still not receiving consistent updated FOCs. Qwest will investigate (see action # 1), CR will remain in CLEC Test.

12/13/01 - Received e-mail from Allegiance listing PONs for same day CFA changes that were processed by Qwest during December thus far.

12/13/01 - Received e-mail from Allegiance listing previous email lists of PONs Allegiance did not get updated FOCs on for the Same Day Pair Change process on test and turn up date.

12/26/01 - Response e-mail from Qwest to Allegiance with revised information on December examples

12/26/01 - E-mail reply from Qwest to Allegiance asking for LSR ID #

12/26/01 - E-mail from Allegiance with LSR ID

12/26/01 - E-mail from Qwest with order numbers

12/26/01 - Reply e-mail from Qwest

12/28/01 - E-mail from Allegiance with more examples of missing updated FOCs

12/30/01 - E-mail from Allegiance with updated PON and LSR ID

01/02/02 - E-mail from Allegiance with two more examples of missing updated FOCs

01/07/02 - Response dated 01/07/02, issued to Allegiance

01/08/02 - E-mail from Allegiance with one example out of four not receiving an updated FOC

01/11/02 - E-mail from Allegiance with early January examples of not receiving updated FOCs

01/16/02 - January CMP meeting. Qwest reiterated that they are focusing on correcting this process. Allegiance will continue to monitor on a weekly basis and hope to see an improvement. CR status will remain in "CLEC Test"

01/18/02 - E-mail from Allegiance with more January examples of not receiving updated FOCs

01/18/02 - Action # 2 opened to find out what e-mail address Qwest is using to send updated FOCs

01/25/02 - E-mail from Allegiance with more January examples of not receiving updated FOCs

02/07/02 - Action # 2 ( what e-mail address Qwest is using to send updated FOCs) changed to pending closure

02/20/02 - February CMP meeting: Allegiance reported an improvement over the past month in receiving updated FOCs. Allegiance would like to see Qwest start reporting on this metric rather than Allegiance. Action # 3 opened to create a report on this metric. CR status remains in CLEC Test. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/25/02 - E-mail from Allegiance with February examples of not receiving updated FOCs

03/04/02 - E-mail from Allegiance with February/March examples of not receiving updated FOCs

03/11/02 - E-mail from Allegiance with March examples of not receiving updated FOCs

03/13/02 - MCC titled "CFA Change and Notification" issued to ensue CLECs receive notification on CFA changes

03/14/02 - Resolution to Action Item 3 posted to database and status of action item changed to pending closure.

03/15/02 - Issued February's analysis to Allegiance.

03/20/02 - March CMP Meeting: CR to remain in CLEC Test. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be

posted on the CMP Web site

03/20/02 - E-mail from Allegiance with March 3/11 - 3/15 examples of not receiving an updated FOC

03/28/02 - E-mail from Allegiance with March 3/18 - 3/22 examples of not receiving an updated FOC

04/05/02 - E-mail from Eschelon with three examples of same day pair change where records are not correct (examples included)

04/15/02 - E-mail from Eschelon asking for updates to be made and seeking response on submitted examples

04/17/02 - April CMP Meeting: CR to remain in CLEC Test. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/29/02 - E-mail received from Allegiance with examples from 4/15 - 4/19 of not receiving an updated FOC

05/01/02 - Received email from Eschelon with examples of CFA change day of cut.....posted with wrong CFA on CSR sent to R Urevig

05/13/02 - Received email from Allegiance with examples - Same Day CFA'S FOR 4/29 THRU 5/3/02]

05/15/02 - May CMP Meeting: CR to remain in CLEC Test. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

05/17/02 - Received email from Allegiance with CFAs 05/13 - 05/17

06/05/02 - Received email from Allegiance with CFAs 05/20 - 05/31Qwest Urevig will work directly with the centers to determine problem and work with coach to identify repetative problems

06/10/02 - Received email from Allegiance with CFAs 06/03 - 06/07 Qwest Urevig to work with center personnel for responses to problems

06/19/02 - June CMP Meeting: CR to remain in CLEC Test Meeting discussions will be set forth in the Produce/Process Meeting Minutes to be posted on the CMP Web site

06/24/02 - Received email with updated spreadsheet from Allegiance with CFAs from 06/10 - 06/14 Urevig will review issues and provide feedback

06/24/02 - Received email with updated spreadsheet from Allegiance with CFAs from 06/17 - 06/21Urevig will review issue and provide feedback

06/26/02 - Sent email to Allegiance and CLEC community regarding Escalation process

07/08/02 - Allegiance - Same Day CFA Change Spreadsheet updates 6/24/02 through 7/05

07/17/02 - July CMP Meeting: CR to remain in CLEC Test , Meeting minutes posted to this CR's Project Meetings section

07/24/02 - Received email with final spreadsheet from Allegiance

08/21/02 - August CMP Meeting: CR was changed to Completed Status Meeting discussions will be set forth in the Produce/Process Meeting Minutes to be posted on the CME Web site and this CR's Project Meetings section


Project Meetings

August CMP Monthly Meeting Minutes

Allegiance (Wicks) agreed this CR could be moved to “Completed” status. Allegiance did indicate they would like to see a higher level of compliance in this area. Currently they are still not receiving updated FOC’s 30% of the time.

-

"'Russ Urveig'" cc: "'Kit Thomte'"

Subject: Allegiance - Same Day CFA Changes - No Updated FOCs Week of 7/15 - 7/19

Here is the last spreadsheet that I will send to you for updates. Beginning 7/22 we are using the new process to release busy CFAs should the situation arise.

There was only one PON that we did not get an updated FOC on last week. Please confirm the CFA change was corrected on you records for PON 1388133-LP and return the updated spreadsheet to me. Thanks.

<>

Terry Wicks LEC Account Manager allegiancetelecom, inc 469-259-4438 terry.wicks@algx.com

07/17/02 - July CMP Meeting Minutes: Qwest (Buck) provided the following status. Qwest had provided information back to Allegiance on the spreadsheet they have been tracking from. Allegiance agreed that they would begin using the escalation process on July 22. Qwest indicated that in the interim the escalation information has been provided to the CLECs to allow everyone to use the process. Worldcom inquired how someone that did not attend CMP could get the information. Qwest responded that the information was updated in the Qwest Raw Loop Data Qualification Tool Job Aid. This CR will remain in "CLEC Test" until the next CMP meeting to determine if the process is working properly and can be closed.

"Cheri Hurless" , "Wicks, Terry" cc: kthomte@qwest.com

Subject: Spreadsheets

Here is the completed spreadsheet for the CFA changes and no FOC sent, if you have any question please get with Cheri. There was only one request for CFA change where as the records were incorrect, I had a service order issue to correct the problem and it was due dated today. Just to clarify the spread sheet, in the column for NO FOC if the correct CFA was applied in TIRKS and the service order, I place an OK next you your N indicator. In the Comment section I just stated CFA verified. (See attached file: Same Day CFA Spreadsheet No FOC Master.xls)

I believe we have made great improvements on the FOC during the last several week and in all but 1 case the CFA had been correctly changed. I feel that this spread sheet should be discontinued and any concerns for CFA changes should move to the BUSY CFA activity, but only after the CFA query function had been performed on both the old CFA to make sure it is vacant and against the new CFA tom make sure it is busy. Any time we take activities out of the normal process flow and I an referring to requesting a CFA change without documentation there are extra steps we both must take to work together. Thanks for all your feed back on this matter Terry, and I look forward to closing this CR. Russ,

Here are my latest examples of not receiving updated FOCs on same day CFA changes.

5/20/02 thru 5/24/02

1268042-LP Received Updated FOC 1253525-LP Did Not receive updated FOC 1275739-LP Did Not receive updated FOC 1273724-LP Received Updated FOC 1272870-LP Received Updated FOC 1265872-LP Received Updated FOC 1277072-LP Received Updated FOC 1270017-LP Received Updated FOC 1276114-LP Received Updated FOC 1153382-LP Received Updated FOC

5/28/02 thru 5/31/02

1296008-LP 303-706-9024 Did Not receive updated FOC

1284062-L 480-237-0350 Did Not receive updated FOC 1308512-L1 480-966-8198 Did Not receive updated FOC 1295225-LP 303-781-8307 Received Updated FOC Received Updated FOC

1287395-L 303-771-0816 Received Updated FOC 1301207-LP Did Not receive updated FOC

1301991-LP Did Not receive updated FOC 303-762-9176 1278540-LP Received Updated FOC

1303185-L Received Updated FOC 1307043-L Did Not receive updated FOC 1303880-LP Received Updated FOC

1309037-LP Received Updated FOC 1309503-LP Did Not receive updated FOC 1292144-L Did Not receive updated FOC 1301212-LP Received Updated FOC

1285714-LP Received Updated FOC

Terry Wicks LEC Account Manager allegiancetelecom, inc 469-259-4438

Subject: CFA'S FOR 5/13/02 THRU 5/17/02

FOC 1242682-LP TN 720-932-8789 NEW 1263 OLD 1299

FOC 1257259-LP TN 303-755-3199 NEW 829 OLD 814

FOC 1284374-LP TN 206-323-1751 NEW 1279 OLD 1259 AND 1341 SHOWS WORKING IMA

NO FOC 1211795-LP2 TN 752-888-7554 NEW 247 OLD 276

FOC 1261532-LP TN 623-931-8086 NEW 808 OLD 768

FOC 1265023-L TN 303-991-0119 NEW 696 OLD 1183

FOC 1280325-MVL TN 763-576-6636-1 NEW 152 OLD 161

Thank you and have a good day,

Tasha Nichols/Supervisor Qwest/Verizon West 469-259-4823 fax 469-259-9051 tasha.nichols@algx.com


CenturyLink Response

June 26, 2002

Terry Wicks LEC Account Manager Allegiance Telecom

SUBJECT: Qwest’s Change Request Response - CR 5548229 Same Day Pair Change

This letter is in response to your recent request regarding the Escalation process associated with busy CFA. A subsequent request was made to include information to the CLECs regarding how they should initiate an escalation for busy CFA.

Below is the information that is necessary to initiate an Escalation for busy CFA.

Busy Connecting Facility Assignment (CFA) is defined as; When validating the CFA the slot shows that it is currently in use by a circuit in the Trunk Integrated Record Keeping System (TIRKS). The busy CFA can be the result of several different reasons: normal activity, pending service order activity, pending Inventory Availability Date (IAD) issues, and canceled service orders that have not cleared in TIRKS. Should you receive an indicator that the CFA is currently in use, however you records indicate the CFA is NOT in use, an Escalation ticket may be opened.

Information that is required for an Escalation ticket will be for BUSY CFA problems.

1. TERM Z TYPE LONG CLLI (ex.ALBONMNEHG1)

2. TERM A TYPE SHORT TYPE CLLI (e.g., ALBQNMNE)

3. CABLE TYPE (e.g., alt01)

4. UNIT NUMBER (e.g., 086)

5. Was there a disconnect request submitted to free CFA location. (EX. Yes, a disconnect request was submitted and an FOC was received. The PON number for the disconnect was AAA121211-MA)

6. Was the Slot changed during installation? If so what was the old slot and what should the current slot be? (EX. Yes, we changed the CFA during test and turn-up the previous CFA was ALT01 slot 89 TCANAZMAHG1 and slot changed to slot 91. The PON number associated to this change was AAA121211-MA)

7. Was there any migration activity on this CFA? (EX. Yes, we should that a migration to another Provider on 06/17/2002)

8. Want type of request were you attempting when you encounter the busy CFA problem? (EX. We were attempting to request a new loop and utilize this CFA, or we were attempting a change activity against circuit 99.LXFU.000111.nw.)

9. Were there any change activity against the circuit, if so PON number for activities. (EX. Our records show a change activity should have taken place on 06/17/2002 from PON AAA121211-MA to free this CFA. Or our records indicate a disconnect request on 06/17/2002 on PON AAA121211-MA which should have freed the CFA.)

If you have any questions regarding this information please feel free to contact me.

Sincerely,

Russ Urevig Senior Process Analyst

01/07/02 Response to Allegiance e-mail dated 12/28/01 January 7, 2002

Terry Wicks LEC Account Manager Allegiance Telecom

CC: Catherine Garcia

This letter is in response to your e-mail dated Friday, December 28th, 2001 – Allegiance – Same Day CFA Change – No Updated FOC Received.

Response: Since we have received examples of FOC’s not being sent to the CLEC’s when a CFA has been changed, new focus on this process has been brought forward. The QCCC have put the following procedures in place to insure that the CFA process is followed.

- All testers have been re-trained on the CFA Change Process.

- Four compliance reviews, for each tester, are completed every month focusing on compliance to the CFA Change Process.

- Performance managing is being done to insure the CFA Change Process is being complied with. If a tester fails their compliance review, there is documented discussion around the issue.

- Weekly Leadership meeting are held to discuss issues for the center. The CFA Change Process has been brought forward during these meetings to insure that the process is understood and followed.

Sincerely,

Deni Toye Network Unbundled Loop Process

October 10, 2001 Terry Wicks, Allegiance

This letter is in response to your CLEC Change Request Form CR5548229 dated August 30, 2001, Request:

Allegiance has sent Qwest examples of orders when Allegiance had problems on same day CFA changes. Allegiance was not receiving FOC’s back specifying that a CFA had been changed. Allegiance would like to know that there is a process for a CFA change on test and turn up for the same day.

Qwest Response: There was a process put into place to allow the CLEC to have a CFA change before or on the due date. On August 9, 2001 a process was put in place to allow this activity to happen. Terry Wicks sent some examples to show that the process is not working. After investigation of these orders, it was determined that a process is in place and does work, however, there are isolated cases of non-compliance issues. The orders that Terry sent to us did have the CFA changed the day of the due date, however, non-compliance to the process did not produce a call to the SDC, therefore, a FOC was not sent to the CLEC. These examples have been forwarded to the centers for process compliance verification.

Sincerely,

Deni Toye Network Unbundled Loop Process


Open Product/Process CR PC092701-1 Detail

 
Title: Develop a process for CLECs to get a FULL CSRs on DID numbers
CR Number Current Status
Date
Area Impacted Products Impacted

PC092701-1 Completed
12/12/2001
Pre-Ordering, Ordering Re-Sale
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Manning, Monica
Director:
CR PM:

Description Of Change

Allegiance is requesting that a process be developed by Qwest to allow CLECs to be able to retrieve a full and complete CSR for all DID numbers for a specific End User at a specific location. Currently Allegiance is not confident that the information received through IMA is accurate. We have had several instances of End Users going down after conversion due to DIDs not being addressed. The reason for this is that not all DIDs are showing up on the CSRs. One example is for City of Tukwila BTN 206-433-1800. The CSR we pulled in IMA only shows the block 206-433-1844 to 1851 when in actuality the range goes to 1871. Qwest also advised us the DID 206-433-1856 did not exist. This meant that there was a break in the range of 206-433-1844 to 1855 then 206-433-1857 to 1871. DID range 206-433-7140 to 7199 is totally unaccounted for on the CSR.

These DID numbers were for the local police and fire station in this city. Due to the inaccurate CSR we left a two-way trunk with Qwest which disrupted the hunting (this line had a DPA on it that the customer wanted to keep). There were two sets of DIDs that were not addressed so when the TFD trunk they were riding on was ported the DIDs went down. The only way we were able to find the additional DIDs was by call Qwest for assistance.


Status History

09/25/01 – CR received from Terry Wicks of Allegiance Telecom

09/27/01 – CR status changed to Submitted

09/27/01 – Updated CR sent to Terry Wicks of Allegiance Telecom

10/05/01 - Held Clarification Meeting with Allegiance

10/17/01 - CMP Meeting: Clarification conducted with CLEC community. "Current Status" changed to evaluation.

10/26/01 - Draft Response completed on 10/26

11/01/01 - Issued draft response dated 10/26/01 to Allegiance.

11/09/01 - Issued revised draft response dated 11/8/01 to Allegiance.

11/14/01 - CMP Meeting: It was agreed to move this CR to CLEC Test with the concurrence of Allegiance.

11/16/01 - Matt Rossi issued Final Response to the CLEC Community.

11/30/01 - Per telecon between T Wicks, Allegiance, and Ric Martin, Qwest, Allegiance was in agreement with moving the CR into CLEC Test.

12/12/01 - CMP Meeting - CLEC participants agreed that the CR could be closed.


Project Meetings

9:00 p.m. (MDT) / Friday, October 05, 2001 Conference Call 1-877-542-1728 PC7712487 # PCCR092701-1

Name/Company: Terry Wicks, terry.wicks@algx.com, Allegiance Monica Manning, mxmanni@qwest.com, Qwest Susie Wells, sdwell2@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Introduction of Attendees Terry, Monica, Susie, and Kate Review Requested (Description of) Change Develop a process for CLECs to get a “full” CSRs on DID numbers. Confirm Areas & Products Impacted Areas: Pre-Ordering / Ordering Products: Resale Confirm Right Personnel Involved Monica Manning is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Susie would like to stay informed as to response and is available for questions pertaining to her area. Terry Wicks would like to stay informed as to response. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and send information to Mike Keegan and Matt Rossi to store to database. Identify/Confirm CLEC’s Expectation Allegiance is requesting that a process be developed by Qwest to allow CLECs to be able to retrieve a full and complete CSR for all DID numbers for a specific End User at a specific location. Currently Allegiance is not confident that the information received through IMA is accurate. We have had several instances of End Users going down after conversion due to DIDs not being addressed. The reason for this is that not all DIDs are showing up on the CSRs. One example is for City of Tukwila BTN 206-433-1800. The CSR we pulled in IMA only shows the block 206-433-1844 to 1851 when in actuality the range goes to 1871. Qwest also advised us the DID 206-433-1856 did not exist. This meant that there was a break in the range of 206-433-1844 to 1855 then 206-433-1857 to 1871. DID range 206-433-7140 to 7199 is totally unaccounted for on the CSR.

These DID numbers were for the local police and fire station in this city. Due to the inaccurate CSR we left a two-way trunk with Qwest which disrupted the hunting (this line had a DPA on it that the customer wanted to keep). There were two sets of DIDs that were not addressed so when the TFD trunk they were riding on was ported the DIDs went down. The only way we were able to find the additional DIDs was by call Qwest for assistance. To clarify, two points are being addressed: ? When you pull a CSR and submit a request, the phone numbers aren’t on the CSR in the LSR. Is it then rejected? If so, why don’t they show up in the CSR if they are rejected? Terry gave the following examples: Here are the PONs where we ported these DID ranges: PON 699510-NP 206-431-3650 thru 3689 699510-NP1 206-431-3890 thru 3899 699510-NP2 206-433-1804 thru 1843

We have not completed the porting of these PONs: PON 860171-NP1 206-433-1844 thru 1855 PON 860171-NP2 206-433-1857 thru 1871 PON 860171-NP3 206-433-7140 thru 7199

The following TNs were on our CSR but we were told by Qwest there were additional TNs not showing up: 206-433-1844 thru 1851

The following TNs were not on our CSR we pulled from IMA for BTN 206-433-1800 206-433-1852 thru 1855 206-433-1857 thru 1871 206-433-7140 thru 7199

? Additional DIB ranges need to be addressed.

Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Monica will clarify process via a written formal response draft. After clarification is received regarding possible system changes. She will forward this documentation to Kate by 10/18/01. Kate will review and forward the response draft to Mike Keegan and Matt Rossi to store in the CR database by 10/19/01 for CLEC review. The web location will be noted in Matt Rossi’s email regarding the response document by 10/22/01. This information can then be reviewed and discussed by the CLEC Community at the following CMP Meeting. Terry can view this information on the CR database and this CR can then be reviewed and discussed by the CLEC Community at the following CMP Meeting. Corrections/updates can then be made at that time.


CenturyLink Response

Wholesale Product Marketing FINAL RESPONSE

November 8, 2001

Terry Wicks LEC Manager Allegiance Telecom, Inc

This letter is being sent in response to CLEC Change Request Form # PC092701-1. PC092701-1 pertains to a request for a process to get a full CSR on DID numbers.

We have reviewed the list of LSRs and associated CSR you provided to QWEST for this Change Request. While it may have appeared that a Full CSR was provided to you by IMA, the Review Full CSR Response displayed a message indicating that only 52 of 61 pages were returned. This would explain why only a portion of the DID numbers for the account appeared.

The IMA User Guide provides instructions on how to retrieve additional CSR data, when the complete CSR is not displayed. This information can be found in Chapter 1 of the User Guide, under Reviewing Customer Service Records. As long as a Full CSR request does not exceed the page number limitation (300 pages in the IMA GUI, 450 pages in IMA EDI) and the CLEC is authorized, all of the CSR pages should be returned. If the instructions in the User Guide are followed, all of the CSR pages can be retrieved.

If you should encounter this trouble again while trying to retrieve a full CSR and have followed the steps outlined in the User Guide, please contact the Wholesale Systems Help Desk at (888) 796-9102 immediately. If we receive a trouble report regarding CSR retrieval "as it is occurring", we will be able to determine the root cause and correct the problem.

Sincerely,

Monica Manning IMA Process Specialist


Open Product/Process CR PC092701-2 Detail

 
Title: Develop a process for CLECs to get a FULL CSRs on Resale Centrex lines.
CR Number Current Status
Date
Area Impacted Products Impacted

PC092701-2 Completed
2/20/2002
Pre-Ordering, Ordering Re-Sale
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Wells, Susie
Director:
CR PM:

Description Of Change

Allegiance is requesting that a process be developed by Qwest to allow CLECs to be able to request and receive from the CSR center a full CSR for all TNs for a specific End User at a specific location that has Resale Centrex lines. The CLEC would only need to submitting one WTN and the address in order to receive the full CSR that would include all WTNs and feature detail at that address for that End User. Currently the only capability to the CLECs is to pull partial CSRs by WTN. When all WTNs are not known, there is no way to ascertain that all TNs have been accounted for before submitting an order to Qwest to convert.


Status History

09/25/01 - CR received from Terry Wicks of Allegiance Telecom

09/27/01 - CR status changed to Submitted

09/27/01 - Updated CR sent to Terry Wicks of Allegiance Telecom

10/05/01 - Held Clarification Meeting with Allegiance

10/17/01 - CMP Meeting: Clarification conducted with CLEC community. "Current Status" changed to evaluation.

10/26/01 - Held additional Clarification Meeting with Allegiance.

11/01/01 - Issued draft response dated 10/26/01 to Allegiance.

11/09/01 - Sent Terry Wicks an updated version of the Draft Response dated 11/8/01.

11/14/01 - CMP Meeting: Allegiance asked Qwest SME to provide more information on the product and process at the next Dec CMP Meeting. CLEC to create a Systems CR. Qwest to advise if there was a manual process available to Qwest retail that was not available to CLECs. Qwest to advise if Qwest retail had to get all WTN numbers from new customers. Qwest to investigate the security issues.

12/05/01 - Issued Qwest's response dated 12/04/01 to Action Items to Allegiance and Eschelon.

12/12/01 - CMP Meeting - Qwest presented its response which denied the CR Request due to resource constraints. Qwest to investigate whether there is another approach which can accommodate the CR request.

12/17/01 - Received e-mail from Allegiance providing additional clarification of what he would like to receive.

01/08/02 - Qwest issued Revised Response dated January 8, 2002 to Allegiance and posted response to dBase.

01/16/02 - CMP Meeting - Qwest presented its revised response. Allegiance confirmed the response met their request and it was agreed that the CR could move into CLEC Test. Qwest will update the external documentation with its response.

01/21/02 - Issued Qwest's Response dated January 8, 2002 to CLEC Community.

02/20/02 - CMP Meeting - it was agreed that the CR could be Closed. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/20/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

Subject: Allegiance - CSRs for Centrex Resale PC 092701-2 Date: Mon, 17 Dec 2001 11:58:52 -0600 From: "Wicks, Terry" To: "'Rick Martin'"

Rick,

Per our conversation last week, here is my suggestion for the manual process for Qwest to develop so that CLECs can get full CSRs on Centrex Resale accounts:

I would like to be able to email a single point of contact at Qwest, a form that shows the following:

1. Customer Name and Service Address 2. Any WTNs that we know of 3. A box or section to be checked that we have an LOA from the End User 4. Some type of verbiage stating that we want Qwest to list all WTNs for that End User at that address 5. Qwest would then list ALL WTNs for that End User at that address and email it back to the requestor at Allegiance

All we want is to confirm all WTNs for a particular End User at a specific address. We will pull the partial CSRs for each WTN through IMA once we have confirmed with Qwest that we have all WTNs at that address.

To me, this should be a fairly simple process to get all WTNs for a Centrex Resale customer.

I don't have Monica Manning's email, so if you could forward this to her for me. Thanks

Terry Wicks LEC Account Manager allegiancetelecom, inc 469-259-4438 terry.wicks@algx.com

-

Alignment/Clarification Meeting 10:30 p.m. (MDT) / Friday, October 26, 2001 Conference Call 1-877-542-1728 PC7712487 # PCCR092701-2

Attendees: Terry Wicks, terry.wicks@algx.com, Allegiance Monica Manning, mxmanni@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

1.0 Introduction of Attendees 1.1 Terry, Monica, and Kate 2.0 Review Requested (Description of) Change 2.1 Develop a process for CLECs to get a “full” CSRs on DID numbers. 3.0 Confirm Areas & Products Impacted 3.1 3.2 Areas: Pre-Ordering / Ordering Products: Resale 4.0 Confirm Right Personnel Involved 4.1 Monica Manning is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. 4.2 Susie would like to stay informed as to response and is available for questions pertaining to her area. 4.3 Terry Wicks would like to stay informed as to response. 4.4 Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and send information to Mike Keegan and Matt Rossi to store to database. 5.0 Identify/Confirm CLEC’s Expectation 5.1 Monica learned from Jeff Thompson that what he discussed with Terry deals with retrieving CSRs in IMA by common DPA or ALI codes. She needed more clarification regarding their discussion so an additional clarifying meeting was held today. Jeff’s suggestion of using DPA or ALI codes to retrieve information would require modifying IMA screens, hence causing a systems change and would become a systems CR. Terry stated that if this is a systems change, then Allegiance would like a work-around. Monica will look into a work-around option. 6.0 Identify any Dependent Systems Change Requests 6.1 No related system CR’s were identified 7.0 Establish Action Plan (Resolution Time Frame) 7.1 Monica will look into work-around options and create a written formal response draft. She will forward this documentation to Kate by 10/26/01. 7.2 Kate will review and forward the response draft to Mike Keegan and Matt Rossi to store in the CR database. This information can then be reviewed and discussed by the CLEC Community at the following CMP Meeting. 7.3 Terry can then review and discuss the response at the next CMP meeting. Corrections/updates can then be made at that time.

Alignment/Clarification Meeting 9:00 p.m. (MDT) / Friday, October 05, 2001 Conference Call 1-877-542-1728 PC7712487 # PCCR092701-2 Terry Wicks, terry.wicks@algx.com, Allegiance Monica Manning, mxmanni@qwest.com, Qwest Susie Wells, sdwell2@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Introduction of Attendees Terry, Monica, Susie, and Kate Review Requested (Description of) Change Develop a process for CLECs to get a “full” CSRs on Resale Centrex lines. Confirm Areas & Products Impacted Areas: Pre-Ordering / Ordering Products: Resale Confirm Right Personnel Involved Monica Manning is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Susie would like to stay informed as to response and is available for questions pertaining to her area. Terry Wicks would like to stay informed as to response. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and send information to Mike Keegan and Matt Rossi to store to database. Identify/Confirm CLEC’s Expectation Allegiance is requesting that a process be developed by Qwest to allow CLECs to be able to request and receive from the CSR center a full CSR for all TNs for a specific End User at a specific location that has Resale Centrex lines. The CLEC would only need to submitting one WTN and the address in order to receive the full CSR that would include all WTNs and feature detail at that address for that End User. Currently the only capability to the CLECs is to pull partial CSRs by WTN. When all WTNs are not known, there is no way to ascertain that all TNs have been accounted for before submitting an order to Qwest to convert. (No ability to find out what 1 particular customer has at 1 particular location.) Example number is (206) 364-8495 Terry mentioned that Jeff Thompson from Qwest has been involved with this and may be a good resource to tap into. Monica will check to see if a process could be implemented to submit requests to the CSR center so that they can pull the full CSRs. Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Monica will speak with Jeff Thompson and clarify process via a written formal response draft. After clarification is received regarding possible system changes. She will forward this documentation to Kate by 10/18/01. Kate will review and forward the response draft to Mike Keegan and Matt Rossi to store in the CR database by 10/19/01 for CLEC review. The web location will be noted in Matt Rossi’s email regarding the response document by 10/22/01. This information can then be reviewed and discussed by the CLEC Community at the following CMP Meeting. Terry can view this information on the CR database and this CR can then be reviewed and discussed by the CLEC Community at the following CMP Meeting. Corrections/updates can then be made at that time.


CenturyLink Response

January 8, 2002

Terry Wicks LEC Manager Allegiance Telecom, Inc.

This letter is being issued to revise Qwest’s response dated November 8, 2001 to Change Request PC092701-2 requesting confirmation of all WTNs for a particular End User at a specific address for a Centrex Resale Customer. Qwest is prepared to implement the attached process to accommodate the CLECs request of confirming an End User WTNs.

Sincerely,

Susie Wells Sr. Process Analyst

(See Supplemental Information following detail report for Process)

December 4, 2001

Terry Wicks LEC Manager Allegiance Telecom, Inc. And, Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc.

This letter is in response to questions/concerns generated at the November CMP Meeting regarding Qwest’s response dated November 8, 2001 to Change Request PC092701-2.

Question: Is there a manual process available to Qwest retail that was not available to CLECs?

Answer: No. Qwest retail only retrieves CSRs for the WTNS provided by their customer .

Question: Does Qwest Retail have to get all WTN Numbers from new customers?

Answer: Yes. Qwest retail has to obtain all WTNs from their customer.

Sincerely,

Carolyn Brown Director Process Management

Cc: Monica Manning

--

DRAFT RESPONSE For Review By CLEC Community and Discussion at November CMP Meeting

Wholesale Product Marketing

November 8, 2001

Terry Wicks LEC Manager Allegiance Telecom, Inc

This letter is being sent in response to CLEC Change Request Form # PCR092701-2. PCR092701-2 pertains to a request for a process to get Full CSRs on Resale Centrex lines.

An IMA System Change would be required, in order to allow CLECs to request a Full CSR for all telephone numbers for a specific end user at a specific location. For the Resale Centrex account, DPA or DEPT and LOCN selection criteria might be added to the Review/Retrieve CSR functionality in IMA. However, a Systems Change Request would need to be created for these enhancements.

Until the IMA system changes can be deployed, you had requested that QWEST develop an interim process for obtaining end user specific Resale Centrex CSRs. Because a mechanized process does not exist, our service center personnel would have to gather this information manually. Unfortunately, QWEST does not have the resources to devote to these kinds of special requests. As long as a CLEC has the appropriate authorization, full CSRs can be retrieved through IMA. In lieu of the full CSR, partial CSRs by WTN can be retrieved. When a CLEC is unable to identify all WTNs associated with a request, the end user customer will have to be the provider of the information.

Sincerely,

Monica Manning IMA Process Specialist


Open Product/Process CR PC092701-3 Detail

 
Title: Develop a process for a point of contact, a process of investigating and proper training conducted when improper behavior by Qwest personnel occurs
CR Number Current Status
Date
Area Impacted Products Impacted

PC092701-3 Withdrawn
10/10/2001
Provisioning Re-Sale
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Masztaler, Joan
Director:
CR PM: Thomte, Kit

Description Of Change

Allegiance has experienced numerous instances when Qwest personnel have given false information to our customers. There have been instances of disparaging remarks against Allegiance and down right rudeness by Qwest Techs. When I have documented these occurrences and given the dates, times, names, etc. to my service manager, it has taken weeks to get any reply. The reply has not been sufficient to hold the offender accountable. In several cases, Qwest has simply replied that it did not happen or it did not happen as reported. The current process is not sufficient to handle these occurrences.

The most recent example happened today. PON 806241-HDSL1 – The FOC date to put in the circuit for this client is 09/25/01. Qwest was at the customer premises on 09/24/01 at 5:10 p.m. to do some work. The Qwest tech who went out was extremely rude to the customer. The Tech stated he has come several times, always after closing (5p.m.) and was not happy that he did not have access to the MPOE. The tech did not identify himself until the owner mentioned another company. The owner asked the tech if he worked for End 2 End Communications and the tech got upset and simply left. Several times the Qwest techs have told the customers that they would go down if they proceeded with converting to Allegiance.

Allegiance is requesting that an improved process be put in place that the CLECs can report these occurrences of anti-competitive behavior when they happen. This process should include a single point of contact , a thorough investigation with an appropriate response to the CLECs in a timely manner. The process should also include the proper training of Qwest personnel to prevent future occurrences


Status History

09/25/01 – CR received from Terry Wicks of Allegiance Telecom

09/27/01 – CR status changed to Submitted

09/27/01 – Updated CR sent to Terry Wicks of Allegiance Telecom

09/28/01 – Established clarification meeting with Terry Wicks of Allegiance Telecom for 10/10/01

10/10/01 - Spoke with Terry Wicks, he asked to have the CR withdrawn and cancelled our meeting scheduled for 10/10/01.


Project Meetings


Open Product/Process CR PC091201-1 Detail

 
Title: Please provide the standard, documented process for when orders are held on cut date, when Qwest has no facilities
CR Number Current Status
Date
Area Impacted Products Impacted

PC091201-1 Completed
10/17/2001
Ordering and Day of Cut UNE
Originator: Mendoza, Lori
Originator Company Name: Allegiance
Owner: Hendricks, Linda
Director:
CR PM:

Description Of Change

Allegiance wants clarification about the process when the problem is on Qwest’s side – Qwest should not have to SUP orders for no facilities on cut date. Allegiance provided an example of this happening (PON 824041-LP); Qwest should investigate this example and provide a documented process and reason why this happens on cut date.

Also what is the process to negate the charges for these cuts and how is this tracked to insure the CLEC is not billed?


Status History

09/12/01 - CR received by Terry Wicks of Allegiance Telecom

09/12/01 - CR status changed to Submitted

09/12/01 - Updated CR sent to Terry Wicks

09/26/01 - Clarification Meeting held with CLEC's.

09/27/01 - Draft Response issued to CLEC's.

10/17/01 - CMP Meeting: Qwest presented response. It was agreed that the CR could be closed without reissuing response.


Project Meetings

Wednesday, September 26, 2001

Introduction of Attendees Terry Wicks, terry.wicks@algx.com, Allegiance Gary Stacy, gstacy@qwest.com, Qwest W. Rob Tomlinson, wtomlin@qwest.com, Qwest Linda Hendricks, lkhendr@qwest.com, Qwest Russ Urevig, rurevig@qwest.com, Qwest Joan Wells, jmwell2@qwest.com, Qwest Deni Toye, dtoye@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest Ric Martin, rhmart2@qwest.com, Qwest

Terry, Gary, Rob, Linda, Russ, Joan, Deni, Kate, and Ric Review Requested (Description of) Change Clarify and document process for when orders are held on cut date, when Qwest has no facilities. Confirm Areas & Products Impacted Areas: Ordering and Day of Cut Products: UNE Confirm Right Personnel Involved Linda is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Russ will forward necessary SCAT documentation to Kate. After the clarification meeting, it was determined that Gary, Rob, Joan, and Deni will not need to be involved in this CR. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Identify/Confirm CLEC’s Expectation Per Allegiance, “Allegiance wants clarification about the process when the problem is on Qwest’s side – Qwest should not have to SUP orders for no facilities on cut date. Allegiance provided an example of this happening (PON 824041-LP); Qwest should investigate this example and provide a documented process and reason why this happens on cut date. Also, what is the process to negate the charges for these cuts and how is this tracked to insure the CLEC is not billed?” Per Linda, there are no non-reoccurring charges. Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Linda will clarify this process via a written formal response draft. She will forward this documentation to Kate by 9/27/01. Russ will forward the necessary SCAT documentation to Kate by 9/26/01. Kate will review and forward this information to Michael Belt and Matt Rossi to store in the CR database by 9/28/01 for CLEC review. The web location will be noted in Matt Rossi’s email regarding the response document on 9/28/01. This information can then be reviewed and discussed by the CLEC Community at the October CMP Meeting. Terry can view this information on the CR database and this CR can then be reviewed and discussed by the CLEC Community at the October CMP Meeting. Corrections/updates can then be made at that time.


CenturyLink Response

September 27, 2001

Terry Wicks LEC Manager, Allegiance Telcom Inc.

CC: Scott Simanson Fred Aesquivel

Re: DRAFT RESPONSE for PCCR 091201-1 For Review By CLEC Community and Discussion at October CMP Meeting" Topic: Provide the standard, documented process for when orders are held on cut date, when Qwest has no facilities Dated: 09/12/01

Dear Terry:

This letter is in response to the following CLEC Change Request Form PCCR 091201-1, dated 09-12-2001. The Change Request pertains to the Clarification and documented process for when orders are held on cut date, when Qwest has no facilities.

Qwest has a Pre Survey procedure in place to identify facility issues before due date. When it is discovered that facilities are not available or good an internal Qwest process looks for other facilities or place the order in a held status if no facilities can be located. The CLEC is then notified of the held status. The Cheyenne Held Order group notifies the CLEC after the order is placed in held. If the facility problem is found on test and turn up the CLEC is notified verbally at that time.

The orders that Allegiance inquired about on PON 824041-LP were held for facility problems on the due date, 8-29-01. The problem was discovered while trying to turn up the orders. The orders were all on Integrated Pair Gain and the process for handling Integrated Pair Gain orders was followed. A problem was discovered between the D4 channel and the SLC equipment in the Central Office. Qwest did not know of this problem until they tried to turn up the loops. The orders are being worked on to discover how to fix the problem and get the service provisioned. According to the WFA/C OSSLOG the CLEC has been advised of the progress.

Waiving the Non Recurring Charge does not apply to these orders because Qwest did meet the appointment time. The negating of Non Recurring Charge applies when Qwest does not meet the appointment time as specified on the CLEC’s LSR. MC The Missed Commitment should be applied only on Coordinated Orders (new and reuse) when Qwest misses the CLEC requested appointment time by 30 minutes or more. This MC=Y or MC causes a billing error to make the billing “fall-out” so the installation charges are dropped. This is placed on the OSSOI Cmnt/Rmk line in WFA/C. Systems captures and passes on to the billing CRIS system. When the billing error falls out, the SDC (service delivery coordinator) negates the nonrecurring charge on the customer's bill. This is how they receive their negated charges. The CLEC approved the start of the cut at 1007 on 8-29-01 by Scott at Allegiance.

Sincerely

Linda K. Hendricks Lead Project Analyst


Open Product/Process CR PC102517-1 Detail

 
Title: New BAN Establishment Process and Notification
CR Number Current Status
Date
Area Impacted Products Impacted

PC102517-1 Completed
2/21/2018
Billing
Originator: Isaacs, Kim
Originator Company Name: Allstream
Owner: Gfeller, Ryan
Director:
CR PM: Lorence, Susan

Description Of Change

Allstream recently experienced CenturyLink establishing a new CABS BAN that was never added to its electronic transmissions or to the CABS E-bill tool as requested on our CLEC questionnaire. As a result, Allstream was not aware of the new BAN until it received an aging from CenturyLink.

Allstream is requesting that CenturyLink automatically set up new BANs on the Bill Media requested on the CLEC questionnaire and that CenturyLink notify the CLEC when a new BAN starts billing.

Expected Deliverables:

CenturyLink will automatically set up new BANs on the Bill Media requested on the CLEC questionnaire and CenturyLink notify the CLEC when a new BAN starts billing.


Status History


Project Meetings

02-21-18 Product Process CMP Meeting Mark Coyne – CenturyLink reminded callers that this is an Allstream CR. The update to the CABS Business Procedure went in to effect on February 1, 2018 and the CR has been in CLEC Test since then. Mark recommended this CR be moved to a Completed status. There were no objections.

01-17-18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that the Level 4 initial notice was sent on December 18, 2017. No CLEC comments were received during the comment cycle. The update is to the CABS Business Procedure to advise customers that, in addition to including the new BAN on the FOC that is returned, CenturyLink will also send an email to the Customer contact as listed on their current Questionnaire to provide the newly assigned BAN. The Final notice will be sent today with an effective date of February 1, 2018. The CR will be considered for Closure in the February meeting.

12-13-17 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this Allstream CR was presented by Kim Isaacs last month and that a clarification call was conducted on November 6, 2017. A CenturyLink response was sent on December 6, 2017 to advise that the CR was accepted. Mark then reviewed the CenturyLink response that is included on pages 12 and 13 of the CMP package. He said a Level 4 notice will be sent on December 18, 2017 with an effective date now of February 1, 2018. Mark asked if there were any questions. There were none.

11-15-17 Product Process CMP Meeting Mark Coyne – CenturyLink stated that a new CR had been submitted by Allstream and asked Kim Isaacs to present.

Kim Isaacs – Allstream presented the CR stating that Allstream recently experienced CenturyLink establishing a new CABS BAN that was never added to its electronic transmissions or to the CABS E-bill tool as requested on our CLEC questionnaire. As a result, Allstream was not aware of the new BAN until it received an aging from CenturyLink. Allstream is requesting that CenturyLink automatically set up new BANs on the Bill Media requested on the CLEC questionnaire and that CenturyLink notify the CLEC when a new BAN starts billing.

Mark Coyne – CenturyLink added that a Clarification call was conducted on November 6, 2017 and the Meeting minutes are available. The new BAN process for CABS has not changed from IABS but there are a few new employees performing the tasks. There was a glitch in the current process and folks have been retrained. The process is for CenturyLink to send an email to all customers when a new BAN is established and to state that we will follow current media designations for electronic media, etc. CenturyLink will send a response that we will accept this CR. Mark asked if there were any questions. There were none. Mark asked Kim if that was acceptable.

Kim Isaacs – Allstream responded yes.

11-06-17 Clarification Call meeting minutes Attendees: Kim Isaacs – Allstream Rita Urevig – CenturyLink Sue Gilbert – CenturyLink Sue Kriebel – CenturyLink Ryan Gfeller – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink relayed the purpose of a Clarification call for the Change Request (CR) and reviewed a high level agenda.

Kim Isaacs – Allstream said the CR was due to a recent experience in conjunction with the establishment of a new BAN for Allstream. Kim said they were not aware of the new BAN until it was on an aging report. Allstream is requesting that when a new CABS BAN is established, that it be added to the Bill Media requested on their CLEC questionnaire and that CenturyLink notify the CLEC when a new BAN starts billing. Susan Lorence – CenturyLink said the SME team has done some preliminary investigation.

Sue Kriebel – CenturyLink said the “new BAN” process has not changed when we went from IABS to CABS. Sue said some new employees were trained on the process following the Access consolidation but that the select group has been retrained. Sue said she wanted to nr sure she understands the request. The CR states that Allstream wants to be notified when a new BAN starts billing but Sue said the process is to notify when the BAN is created by the service order team vs. when it starts billing. Sue asked if that made sense. She said CenturyLink used to have a process that the BAN might be established and not bill for awhile which is not the case now. Kim Isaacs – Allstream said yes that made sense to notify when the BAN is established. Sue Kriebel – CenturyLink asked who the notification would go to for Allstream so we insure that the notification is sent to the correct person.

Kim Isaacs – Allstream provided the name as listed on their current Questionnaire but said that person was out on leave and provided the backup name that would be included in the out of office message.

Susan Lorence – CenturyLink reviewed the next steps for the CR which was to have Allstream present the CR in the Product Process monthly meeting on Wednesday, November 15. We will follow-up with a CMP response to accept the CR and relay that CenturyLink believes it was a one time training situation which has been addressed. Susan said she was not sure a notice was required to the full CLEC community since it was a one off.

Mark Coyne – CenturyLink said that this resolves the problem for Allstream but asked if it addressed the problem for all customers.

Susan Lorence – CenturyLink said the process would be followed for all customers. CenturyLink is confirming that the additional training will resolve this and that no other internal process changes will be required. We will provide that as part of the CR response

Kim Isaacs – Allstream said that was fine and she will present the CR in the monthly meeting. Susan Lorence – CenturyLink asked if there were any questions. There were none.

The Clarification call ended at 1:20 PM MT.


CenturyLink Response

December 6, 2017

Kim Isaacs, Allstream

SUBJECT: Allstream Product Process Change Request PC102517-1, CenturyLink Response for Review

This letter is in response to Allstream Change Request PC102517-1, entitled “New BAN Establishment Process and Notification”

CR Description: Allstream recently experienced CenturyLink establishing a new CABS BAN that was never added to its electronic transmissions or to the CABS E-bill tool as requested on our CLEC questionnaire. As a result, Allstream was not aware of the new BAN until it received an aging from CenturyLink.

Allstream is requesting that CenturyLink automatically set up new BANs on the Bill Media requested on the CLEC questionnaire and that CenturyLink notify the CLEC when a new BAN starts billing.

History: The CR was received on October 25, 2017. A Clarification call was held on November 6, 2017 with Allstream and CenturyLink representatives present. During the Clarification call, CenturyLink relayed that the new BAN process for CABS had not changed from IABS but there were some additional employees performing the task. This small number of additional CenturyLink employees have been retrained on the current process which is for the newly established BAN to be set up to follow current media designations for electronic media, etc.

CenturyLink Response: CenturyLink is accepting this CR and is proposing that a Level 4 CMP notification be sent to communicate an additional step that CenturyLink will take to provide the new BAN to customers. An update will be made to the CABS Business Procedure to relay that in addition to including the new BAN on the FOC that is returned, CenturyLink will also send an email to the Customer contact as listed on their current Questionnaire to provide the newly assigned BAN. The proposed effective date will be in late January 2018.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager


Open Product/Process CR PC021318-1 Detail

 
Title: Include Impacted USOCs on Rate Notifications
CR Number Current Status
Date
Area Impacted Products Impacted

PC021318-1 Completed
6/20/2018
Billing
Originator: Isaacs, Kim
Originator Company Name: Allstream
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Currently, CenturyLink sends rate change notifications with a general description of the product impacted by the rate increase. To implement the rate change in its billing system(s), CenturyLink identifies the USOCs impacted.

Allstream is requesting that CenturyLink include this USOC information on the PROD:Rate notices. UPDATE: 4/18/18: Allstream is also requesting that CenturyLink included the existing rate and proposed rates along with the USOCs on rate notifications.

Expected Deliverables/Proposed Implementation Date (if applicable):

CenturyLink will include USOCs [4/18/18 Update existing rates and proposed rates] impacted by rate changes on the PROD:Rate notifications.


Status History


Project Meetings

06/20/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised that this Allstream CR is now in CLEC Test. He recapped that Allstream had revised the CR in April to also include the existing and proposed rates on the CenturyLink rate notification. CenturyLink sent the CR draft response in early May and a revised CR response in late May identifying that rate notifications will also include the existing and proposed rates when available. Mark said on June 6, 2018, a Level 1 customer notification which was effective immediately was sent to relay the CR implementation plan to all customers. CenturyLink did contact Kim Isaacs – Allstream as CR originator to see if Kim agreed to move this CR to Completed and Kim approved. Mark asked if there were any objections to moving this CR to a Completed status. There were none.

Nancy Taylor – Allstream said she agreed.

05/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised that this Allstream CR was presented by Kim Isaacs in the April meeting. He told callers that the CenturyLink draft response is included on page 15 of the package. He advised that CenturyLink accepts the original CR. CenturyLink proposes that a Level 1 notification be sent to communicate that: • The rate change notifications will include Reseller intrastate USOCs in the legacy Qwest 14-state region. • This change is temporary as long as USOCs are used in the local service request ordering and billing process. Product Codes and Price Plans associated with products and services ordered via EASE and billed in Ensemble are not considered part of this change request. • In the event the complete list of the affected USOCs may not be available at the time the rate notice is required to be distributed, CenturyLink will provide the tariff reference and location. Mark Coyne – CenturyLink stated that the Allstream revision to the CR that requested existing and proposed rates is still under review and will be reviewed and discussed in the June meeting.

Kim Isaacs – Allstream asked when the situation regarding the USOCs not being available would apply.

Mark Coyne – CenturyLink stated that he did not think it would occur often but, to his understanding, it would all revolve around the timing of the notification and perhaps the SME team would not have a complete list.

Lee Brummett – CenturyLink concurred.

Kim Isaacs – Allstream asked if, in that case, could the notice include a description of the product from the tariff.

Lee Brummett – CenturyLink stated that we would investigate to see if that could be spelled out on the notice.

Kim Isaacs – Allstream asked for confirmation that the request for rate information was still under review.

Mark Coyne – CenturyLink confirmed.

Kim Isaacs – Allstream asked if they would have to submit a new CR when the billing system migrated to the new platform.

Mark Coyne – CenturyLink said yes. He asked if there were any other questions. There were none.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised that this is a new Allstream CR. The Clarification call was held March 14, 2018. The meeting minutes are available on the calendar and in the CR. Mark asked Kim to present.

Kim Isaacs – Allstream explained the purpose of the CR and explained that she also wants rates included as a new requirement for the CR. Kim said this is similar to the information they receive from other ILECs and she believes CenturyLink has the information available. She said providing the information would save her from asking for the information from her Service Manager.

Susan Lorence – CenturyLink asked Kim to send an email and update the CR to add this new requirement.

Kim Isaacs – Allstream advised that she would.

Mark Coyne – CenturyLink stated that CenturyLink has held several meetings and that internal discussions would continue and a draft response would be sent out prior to the May CMP meeting.

03/22/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised that this is a new Allstream CR. The Clarification call was held March 14, 2018. The meeting minutes are available on the calendar and in the CR. Kim Isaacs – Allstream advised that she would like to present this CR in the April meeting.

03/14/18 Clarification Call meeting minutes

Attendees: Kim Isaacs – Allstream Rita Urevig – CenturyLink Lee Brummett – CenturyLink Robyn Crichton – CenturyLink Mark Coyne – CenturyLink Susan Lorence – CenturyLink John Hansen – CenturyLink

John Hansen – CenturyLink opened the call, announced the attendees, and explained the purpose of a Clarification call for the Change Request (CR) and reviewed a high-level agenda.

Kim Isaacs – Allstream said the CR was a request for CenturyLink to include impacted USOCs and rates whenever it sends out rate change notifications. If the USOCs are not included, she has to contact Rita Urevig to have someone internally provide them so that Allstream can update their data accordingly. She stated that other ILECs had been including this information for some time now. Kim said providing the USOCs on the notice would be more efficient and easier for both CenturyLink and customers. Mark Coyne – CenturyLink asked if she was expecting only data from the 14-state region (CenturyLink QC) or from all regions of the company.

Kim Isaacs – Allstream stated that if data was available from Legacy EQ and Legacy CenturyLink, that would be great, but definitely CenturyLink QC.

Susan Lorence – CenturyLink asked if CenturyLink could provide the first three letters of the USOC if there was an extensive list.

Kim Isaacs – Allstream stated that was acceptable and gave the example of 1RZxx indicating that the xx was the wildcard portion. Kim said if there was no specific USOC, she would like that noted also and where they would find the info in the OC&C section of the bill

John Hansen – CenturyLink reviewed the next steps for the CR and asked if Allstream was prepared to present the CR in the Product Process monthly meeting on Wednesday, March 21, 2018.

Kim Isaacs – Allstream stated that she would not be able to attend the March meeting, but would present the CR in the April meeting.

John Hansen – CenturyLink advised that the meeting minutes would be posted to the Wholesale Calendar prior to the CMP meeting and would advise via email to Allstream that they were posted.

John Hansen – CenturyLink asked if there were any questions. There were none.

The Clarification call ended at 9:41 AM MT.

02/21/18 Product/Process CMP Meeting Walk on Items (Attachment F)

Mark Coyne – CenturyLink advised callers that a new CLEC CR was received from Allstream and would be presented in the March CMP meeting. This CR is titled Include Impacted USOCs on Rate Notifications. A clarification call has been scheduled for Wednesday, March 7, 2018 at 9:00 AM MT/10:00 AM CT. The CR and information about the clarification call is posted to the Wholesale calendar and is open to the full CMP Customer community to attend.


CenturyLink Response

May 30, 2018

Kim Isaacs Allstream

SUBJECT: Allstream Product Process Change Request PC021318-1, CenturyLink Response for Review - REVISED

This letter is a revised response to Allstream Change Request PC021318-1, entitled “Include Impacted USOCs on Rate Notifications”

CR Description: Currently, CenturyLink sends rate change notifications with a general description of the product impacted by the rate increase. To implement the rate change in its billing system(s), CenturyLink identifies the USOCs impacted.

Allstream is requesting that CenturyLink include this USOC information on the PROD:Rate notices.

On April 18, 2018, Allstream updated the CR to request that CenturyLink include the existing rate and proposed rate along with the USOC on rate notifications.

History: The CR was received on February 13, 2018. A Clarification call was held on March 14, 2018 with Allstream and CenturyLink representatives present. During the Clarification call, Allstream stated that if the USOCs are not included, they have to contact their Service Manager to provide the information and that it would be more efficient if CenturyLink provided this information upfront.

On May 16, 2018, during the monthly CMP meeting, CenturyLink reviewed the draft response indicating this CR is accepted. The CenturyLink Response is being revised (in bold/caps below) to address the April 18, 2018 Allstream update to the CR.

CenturyLink Response REVISED: CenturyLink is accepting this CR and is proposing that a Level 1 CMP notification be sent to communicate the following: • The rate change notifications will include Reseller intrastate USOCs/RATES (5-30-18) in the legacy Qwest 14-state region. • This change would be temporary as long as USOCs/RATES (5-30-18) are used in the local service request ordering and billing process. Product Codes and Price Plans associated with products and services ordered via EASE and billed in Ensemble are not considered part of this change request. • In the event the complete list of the affected USOCs/RATES (5-30-18) may not be available at the time the rate notice is required to be distributed, CenturyLink will provide the tariff reference and location.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager

May 9, 2018

Kim Isaacs, Allstream

SUBJECT: Allstream Product Process Change Request PC021318-1, CenturyLink Response for Review

This letter is in response to Allstream Change Request PC021318-1, entitled “Include Impacted USOCs on Rate Notifications”

CR Description: Currently, CenturyLink sends rate change notifications with a general description of the product impacted by the rate increase. To implement the rate change in its billing system(s), CenturyLink identifies the USOCs impacted.

Allstream is requesting that CenturyLink include this USOC information on the PROD:Rate notices.

On April 18, 2018, Allstream updated the CR to request that CenturyLink include the existing rate and proposed rates along with the USOCs on rate notifications.

History: The CR was received on February 13, 2018. A Clarification call was held on March 14, 2018 with Allstream and CenturyLink representatives present. During the Clarification call, Allstream stated that if the USOCs are not included, they have to contact their Service Manager to provide the information and that it would be more efficient if CenturyLink provided this information upfront.

CenturyLink Response: CenturyLink is accepting this CR and is proposing that a Level 1 CMP notification be sent to communicate the following: • The rate change notifications will include Reseller intrastate USOCs in the legacy Qwest 14-state region. • This change would be temporary as long as USOCs are used in the local service request ordering and billing process. Product Codes and Price Plans associated with products and services ordered via EASE and billed in Ensemble are not considered part of this change request. • In the event the complete list of the affected USOCs may not be available at the time the rate notice is required to be distributed, CenturyLink will provide the tariff reference and location.

Sincerely,

John Hansen CenturyLink Wholesale CR Project Manager


Open Product/Process CR PC061002-1 Detail

 
Title: LSR put in Jeopardy when no dial tone present when Qwests installs Unbundled Loop
CR Number Current Status
Date
Area Impacted Products Impacted

PC061002-1 Completed
11/21/2002
Ordering, Maintenance/Repair, Provisioning Loop
Originator: Dowding, Byron
Originator Company Name: Alltel
Owner: Hendricks, Linda
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

When ALLTEL orders an unbundled loop with a NC Code of LX--and the CHC marked N, Qwest checks for dial tone at the end user (new loops) or at the spot pair (reuse facilities). If there is no dial tone present, Qwest contacts the CLEC gives them 30 minutes to get dial tone on the loop or the LSR is put in Jeopardy and a new LSR has to be written with a new due date. If the order contains multiple loops and one of the loops does not have dial tone, all of the loops are placed in Jeopardy. Qwest has responded to our concerns saying that this has always been their procedure but it was not being followed. Because these orders are not coordinated hot cuts, Qwest can make their cut anytime during the day. It could even happen over a lunch hour. We have also had situations where Qwest has put a loop on the wrong spot pair, had no dial tone at the customer’s premise and placed the order in Jeopardy.

Expected Deliverable:

Qwest to change this process ASAP, give the CLEC a reasonable amount of time (90 minutes) to correct a no dial tone situation on a reuse of existing facilities and give loops to the CLEC if there is continuity to the spot pair on new facilities


Status History

06/10/02 - CR Submitted by Alltel

06/10/02 - CR acknowledged by P/P CMP Manager

06/12/02 - CR posted to Web

06/14/02 - Called Alltel and scheduled clarification call to be held 06/18/02 10:30 a.m. MST

06/18/02 - Clarification call held with Alltel

06/25/02 - Clarification call meeting minutes sent to Alltel and posted in database

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section.. CR status"Clarification" was not changed.

08/14/02 - Issued Qwest draft response dated 8/13/02 to Byron Dowding at Alltel

08/21/02 - Issued updated Qwest draft response dated 8/19/02 to Byron Dowding at Alltel and posted response to http://www.qwest.com/wholesale/cmp/teammeetings.html

08/21/02 - CMP Meeting - Qwest presented its draft response dated 8/19/02. Minutes on this CR to be posted to the Project Meetings section.

08/22/02 - Posted updated Qwest draft response dated 8/19/02 to CMP database

08/21/02 - August CMP Meeting - Meeting minutes posted to this CR's Project Meetings section

08/30/02 - Posted Alltel response dated 8/27/02 to Qwest draft response dated 8/19/02

09/12/02 - Posted e-mail dated 9/12/02 to Byron Downing at Alltel

09/12/02 - Issued revised response dated 9/12/02 to Alltel

09/18/02 - September CMP Meeting - Qwest presented revised response. CR will move to Development. Meeting minutes will be posted to this CR's Project Meetings section

10/11/02 - Qwest issued Final Notification. Notification PROD.10.11.02.F.00839.Final_2 _4_Wire_Loop. Effective date of change is 10/27/02.

10/16/02 - October CMP Meeting - Minutes on this CR to be posted to the Project Meetings section.

10/28/02 - CR status changed to CLEC Test.

11/20/02 - November CMP Meeting - This CR will remain in CLEC Test Meeting minutes will be posted to this CR's Project Meetings section. Approval given to close this off line with concurrence from Byron at Altel..

11/21/02 - Contacted Alltel to follow up on potential closure of this CR.

11/21/02- Received call from Byron Dowding, Alltel that this CR can be closed.


Project Meetings

11/20/02 November CMP Meeting Qwest reviewed the status of this CR as it was moved to CLEC test last month. Linda Hendricks with Qwest said there have not been questions or concerns from the CLEC Community on implementation. Qwest will follow up with Byron Dowding at Alltel to make sure they are not experiencing any problems and ask if the CR can be closed. The CLEC Community has agreed to close this CR if Alltel agrees.

- 10/16/02 October CMP Meeting Michael Buck with Qwest said that final notification PROD.10.11.02F.00839.Final24WireLoop was sent on 10/11/02 and the implementation date is 10/27/02. The CR is currently in Development Status and Qwest would like to move it to CLEC Test on the deployment date later this month. Byron Dowding with Alltel said that it was appropriate to move to CLEC test and discuss again at the November CMP meeting.

09/18/02 September CMP meeting Minutes Qwest discussed the revised draft response and provided an update that Qwest would no longer require dial tone on new unbundled loops effective mid-October. Conversion orders will continue to require dial tone. Qwest explained that the effective date is following the PCAT update for 2-wire 4-wire, Version 11, which is effective October 21, 2002. Allegiance and Eschelon appreciate Qwest changing to the no dial tone requirement on new unbundled loops. Allegiance also noted a clarification from the August Meeting minutes regarding the conversation on this CR. At the August meeting Lyndall Nipps – Allegiance asked why doesn't Qwest check for continuity on DS0 loops like you do for DS1 and above loops by plant test date. Qwest responded that it was not in the infrastructure to test for continuity on DS0 loops. A pre-survey is done for all UBL except for LX - -. LX - - is worked on the due date. This CR was moved to Development status.

9/12/02 2:29 p.m. To: cc:

Subject: RE: Updated Draft Response to CR PC061002-1

Byron -

The following is in response to Alltel's questions in your e-mail dated 8/27/02:

1. CHC means Coordinated Hot Cut (Y or N). You can have a Hot Cut with the Basic Option. Hot Cut means we go from one service provider to another on an existing service, this option can be ordered Coordinated or Basic.

2. Qwest is preparing to only require dial tone on reuse LX-- in mid-October.

3. The polarity of the Qwest wiring and facilities, from the CFA to the NI at the end user locations, can be checked using normal Qwest test systems and sets. The polarity of the supplied CLEC service can not be tested without the CFA operationally in service. If the CLEC provides service on the CFA with reversed polarity, Qwest will not reverse their wiring or facilities to correct, as this would impair Qwest’s ability to properly maintain the circuit in service. The polarity of a loop start line is of significant importance when the facility provided is anything but a plain copper loop. Pair Gain facilities require correct polarity of supplied service to operate correctly.

4. Qwest is preparing to only require dial tone on reuse LX-- in mid-October.

Please call me if you have any questions.

Thank you

Linda Sanchez-Steinke Change Request Project Manager Qwest

-- From: Byron.Dowding@alltel.com on 08/27/2002 08:03:51 a.m. To:

Subject: RE: Updated Draft Response to CR PC061002-1 Linda This is ALLTEL's response to the Qwest response I don't have any feedback yet to verify Qwest allowing more than 30 mintutes to provide dial tone on a loop. Byron

SUBJECT: ALLTEL response to Qwest response regarding change request PC061002-1 dated 08/19/2002

ALLTEL would like to make the following points.

1. The first statement in Qwest’s response states that this CR is about Qwest’s Hot Cut process. CR PC061002-1 has nothing to do with Hot Cuts. This CR is about ordering an unbundled loop with the Basic option and no testing (CHC is N). The service being ordered is 2/4 wire analog with the NC code of LX--. Due date on the loop being turned over to the CLEC and actual customer in service date don’t have a direct relationship. 2. The CLECs have stated several times that ordering a new loop and reuse should be handled as 2 different issues. We are willing to provide dial tone in a reasonable time when we are reusing a facility. When ordering a new loop no dial tone should be provided. 3. Our techs check for polarity when shooting trouble and can reverse the jumper/drop to correct the problem. Polarity should never be an issue with loop start dial tone. I would like to know how Qwest could check for polarity on loop start dial tone when dial tone is provided. 4. For the most part providing dial tone requires CLECs to program dummy numbers in their switch and then reprogramming when the service is actually turned up. This places a costly and unneeded burden on the CLECs.

ALLTEL is planning to charge Qwest for providing joint test capabilities when ordering unbundled loops that Qwest requires dial tone on. ALLTEL is also going to work with the regulatory agencies to significantly reduce the one-time charges associated with provisioning these types of loops.

-- 08/21/02 - August CMP Meeting Minutes: Qwest provided an updated draft response dated August 19, 2002 because information was missing in the August 13, 2002 draft response. The updated draft response is available on line and was handed out to participants in the meeting. Allegiance expressed concern that the 2-wire 4 wire PCAT updated language does not distinguish between new loops and conversions and that Allegiance and other CLECS are trying to find out the technical reasons why Qwest requires dial tone on new loops when there are other ways to check for continuity. Allegiance asked if Qwest checks for continuity from demarc to the central office before plant test date. Eschelon also asked for Allegiance’s question to be answered; does Qwest dispatch for continuity. Qwest stated (Hilleary) that we are pushing for dial tone on due date and dial tone 48 hours before due date is not a requirement. Allegiance disagreed. Qwest stated (Hendricks) that dispatch for continuity is not done, and the pre-survey is done to make sure there are facilities. Qwest stated (Braegger) that on services provided on UDC there is no way to verify correct service operation without Dial Tone on the circuit. Covad said that on digital loop carrier card verified set options correctly if have dial tone. Qwest (Braegger) stated that if Dial Tone is coming in reversed to the card, the card will not operate correctly and won’t operate unless there is battery to it.

Covad asked what would prevent Qwest technician from putting dial tone on temporarily from ICDF at cosmic frame. Qwest (Retka) asked that Covad send in procedure on a CR for Qwest to use spare dial tone temporarily from the ICDF.

Allegiance indicated that Qwest was the only ILEC requiring dial tone on new loops and is a burden on all CLECs when changing from T1 to UNE loop because translations are required for two different numbers and when Qwest checks for ANI the line is not the right number. Eschelon said there is effort that they must go through internally assigning dummy numbers to CFA to provide dial tone for Qwest.

Allegiance asked how Qwest identifies a fault and what does it mean in PCAT wording, pages 5-6 under the ordering section, asked if the purpose of notification is relationship managing. Eschelon asked if they should receive a jeopardy rather than a call if there was a short. Qwest (Boudhaouia) stated Qwest will re-write the PCAT. Allegiance said that the language creates concern over PIDS managing to process and Allegiance does not want the PCAT updated on 8/26/02. Qwest (Maher) stated that for Qwest and the CLECs to follow the CMP, the PCAT would be updated on 8/26/02 because there were comments from the CLEC community on the PCAT change, and Qwest had followed CMP and responded to those comments. Qwest (Schultz) clarified that the PCAT update included documentation of processes that were currently in effect. Allegiance objected to the PCAT update on 8/26/02.

Alltel asked for status of CR. Qwest (Graham) reviewed draft response part 1 reviewing why tests are done and the technical reasons for dial tone requirement.

Qwest (Hendricks) reviewed draft response part 2 reviewing the procedure for the basic option. When the CLEC selects the basic option and is not ready on due date, the technicians go on to their other work. If the CLEC calls back later in the day, then Qwest will try to get technicians back out. Alltel (Dowding) will check with Alltel people that asked for CR because they had said at 31 minutes the order has to be supplemented. Qwest explained that the 31 minutes would be applicable on the appointment time option but is not applicable on the basic option.

Due to another scheduled meeting, which many CMP participants wished to attend, the meeting was adjourned before discussion on the final disposition of the CR was concluded. Qwest will work offline with Alltel regarding the status of the CR and bring the CR back up for discussion at the September CMP meeting.

CLEC – Qwest Change Management Process Monday, August 12, 2002 Ad-Hoc meeting to discuss CLEC comments and CR Conference Bridge: 877.521.8688, passcode 7901848#

NOTE: These DRAFT meeting minutes were developed August 19, 2002 by Qwest following a meeting on the 2Wire 4Wire CLEC Dial Tone Requirement

MEETING MINUTES

The meeting was initiated by Qwest via Change Management notice CMPR.08.06.02.F.01307.CMPMtgFinalized that was distributed to the CLECs on August 6, 2002. Qwest scheduled the meeting to discuss the following two items with members of the CLEC community:

1) CLEC comments received for Notice PROD.07.12.02.F.00784.AnalogLoop24Wire 2) CMP Change Request PC061002-1 titled, “LSR put in Jeopardy when no dial tone present when Qwest installs Unbundled Loop” from Alltel.

The meeting began with Qwest reviewing the Qwest response to CLEC comments from Allegiance, Alltel, and Eschelon on the Level 3 notification sent out by Qwest on July 12th, 2002, PROD.07.12.02.F.00784.AnalogLoop24Wire. Several CLECs asked when the comments response had been distributed and Qwest responded that the notification had gone out the evening of August 9th, 2002, via notice PROD.08.09.02.F.00807.AnalogLoop24Wire and that the Qwest response to the comments had been posted under the Qwest CMP Product/Process Archive Document Review site under PROD.07.12.02.F.00784.AnalogLoop24Wire. Qwest then reviewed the response to comments with the attendees on the call. Allegiance stated that the Qwest posted comments referred to both conversion of analog loops as well as new installations, and that Allegiance did agree that CLEC dial tone should be required on conversion orders but not on new orders. Eschelon asked why the PCAT was being updated associated with PROD.07.12.02.F.00784.AnalogLoop24Wire. Qwest responded that the PCAT was being updated to reflect the requirement that Qwest currently has in place for these types of orders, and that the requirement was for CLEC dial tone prior to order completion. Eschelon, Allegiance, and ATT requested that the PCAT update be delayed until there was final resolution of the Alltel CR. Qwest responded that this request was out of process because the PCAT update needed to take place August 26th based on the final notice PROD.08.09.02.F.00807.AnalogLoop24Wire, but Qwest would take the request to delay the PCAT update back for final determination. Eschelon stated that there was no reason for CLEC comments if Qwest did nothing with them. Qwest responded that Qwest does take CLEC comments under consideration, but there is no CMP requirement to revise product/process changes based upon CLEC comments. Allegiance then stated that Qwest was the only ILEC requiring CLEC dial tone prior to order completion on NEW orders, and that Qwest needed to reevaluate the requirement. Covad stated that the issue could be resolved by Qwest providing Qwest dial tone to test the circuits, or that there were other test alternatives Qwest could implement. Qwest responded that the requirement for CLEC dial tone was still in effect due to technical requirements outlined in the response to CLEC comments, and that Qwest would provide a response to the Alltel CR at the August 21st CMP Monthly Product/Process meeting. The CLECs requested that a specific block of time be set aside at the CMP Monthly Product Process meeting to discuss this issue so they could have their technical subject matter experts on the call. Qwest agreed to set aside a specific time on August 21, 2002 to further discuss this. The time will be 1PM MT. The call-in number is 877 572-8687 passcode 3393947. The meeting then adjourned.

-

07/17/02 - July CMP Meeting Minutes: Alltel introduced their Change Request. Alltel requested the wording in the meeting minutes for the clarification meeting held on June 18, 2002 be changed from “48 hours before the Due Date” to “48 hours after application date”. Allegiance stated that Qwest is the only ILEC requiring dial tone testing for testing continuity. Covad stated it should be the CLECs responsibility for providing dial tone. Eschelon stated all CLECs are interested in this Change Request. CR status is presented.

Clarification Call Time/Date: 11:00 qa.m. (MDT) / Tuesday, June 18, 2002 Place: Conference Call Conference: TEL: 877.521.8688 Call-In No: CODE: 7901848 CR No: PC061002-1 "LSR put in Jeopardy when no dial tone present when Qwests installs Unbundled Loop"

Attendees: Byron Dowding, Alltel Neil Houston, Qwest Linda Hendricks, Qwest Steve Hilleary, Qwest Michael Keegan, Qwest

1.0 Attendees introduced. 2.0 Description: The following is extracted from the CR submitted by Alltel: When ALLTEL orders an unbundled loop with a NC Code of LX--and the CHC marked N, Qwest checks for dial tone at the end user (new loops) or at the spot pair (reuse facilities). If there is no dial tone present, Qwest contacts the CLEC gives them 30 minutes to get dial tone on the loop or the LSR is put in Jeopardy and a new LSR has to be written with a new due date. If the order contains multiple loops and one of the loops does not have dial tone, all of the loops are placed in Jeopardy. Qwest has responded to our concerns saying that this has always been their procedure but it was not being followed. Because these orders are not coordinated hot cuts, Qwest can make their cut anytime during the day. It could even happen over a lunch hour. We have also had situations where Qwest has put a loop on the wrong spot pair, had no dial tone at the customer’s premise and placed the order in Jeopardy.

Clarification Call Discussion: Alltel indicated that this problem started recently (60 – 90 days ago) and has occurred at both Omaha and Grand Island, Nebraska

Alltel said the problem is they get a call from Qwest on the due date when no dial tone is present and the order is placed in jeopardy if the problem is not corrected in 30 minutes.

Qwest does a Dial Tone check on both Basic and Coordinated LX - - (2W/4W Analog)type orders on DVA (Design Verify Assign) which is approximately 48 hours after application Date. If there is no Dial Tone at that time Qwest contacts the CLEC to let them know there is no dial tone at this time. The notification is approximately 24-36 hours before the Due Date. I have verified a couple of orders and we have called Alltel after the Dial Tone Check to notify them that there was No Dial Tone at DVA. On Due Date Qwest does another Dial Tone check before they do the install or hot cut before Qwest starts to do the work. If Dial Tone is not present, the COT calls the QCCC (Qwest CLEC Coordination Center) Coordinator. The QCCC Coordinator calls the CLEC and lets them know that Dial Tone is not present at their CFA (Connecting Facility Assignment). The CLEC is given 30 minutes to correct the Dial Tone situation. If the CLEC is not ready in 30 mintues they are requested to send a supplement to their LSR for a new Due Date. If the LX- - has a Reverse Battery or No Signal NCI (Network Channel Interface) Qwest does not require Dial Tone to be present at the CLEC’s CFA. If the order has multiple loops the CLEC may split out the LSR and accept those that do have Dial Tone. The order without Dial Tone may be put on a separate LSR. The Coordinated Appointment Time Option allows the CLEC to choose exactly when they want the installation or hot cut to be performed. The Basic Option allows Qwest to start the installation or hot cut any time between 8AM and 5PM regional time. The COT should be doing the ANI test on the loop before and after they perform the lift and lay. The correct number should be identified. This is the process in place and should be followed to insure the accuracy of the request.

Linda Hendricks will prepare the Qwest response.

3.0 Confirmed that UNE Loop is the product impacted.

4.0 Qwest confirmed the correct personnel were on the call.

5.0 CLEC expects Qwest to change this process ASAP, give the CLEC a reasonable amount of time (90 minutes) to correct a no dial tone situation on a reuse of existing facilities and give loops to the CLEC if there is continuity to the spot pair on new facilities

6.0 No Dependent Systems Change Requests were identified,.

7.0 Action Items Alltel can present this Change Request to the CLEC community at the July Product/Process CMP meeting scheduled for July 17 Qwest will issue draft response to this Change Request by Aug 14 (one week prior to the Aug 21 CMP meeting). Qwest will discuss the draft response at the Aug 21 CMP meeting.


CenturyLink Response

September 12, 2002

Byron Dowding OSS Coordinator Alltel

SUBJECT: Qwest’s Change Request Revised Response - CR #PC061002-1 LSR put in jeopardy when no dial tone present when Qwest installs unbundled loop Alltel is requesting that Qwest change its Hot Cut process to allow for 90 minutes when no Dial Tone is present at the CFA and not to reject orders with multiple service requests when one of the requests must be rescheduled. (Part 1, No Dial Tone) Dial tone is required to provide a quality installation of the service ordered. To ensure adequate circuit level performance, installation and operational tests are performed. Dial tone must be present to perform these tests across the entire circuit: - To verify the assurance of the assignment and translation of the CFA. - To confirm the Competitive Local Exchange Carrier (CLEC) Connecting Facility Assignment (CFA) is operational and test hard wiring from the Qwest Interconnection Distribution Frame (ICDF) to the CLEC CFA. - To perform a polarity test at the termination of the Network Interface Device (NID) and to perform an overall end to end operational circuit test to ensure reliability and functionality. - When provisioning over Digital Loop Carrier (DLC), to perform ground start, loop start and polarity check tests to assure the electronic card in the DLC is operational and optioned correctly. These operational tests require dial tone to minimize trouble reports immediately following test and turn up. If the NC/NCI codes are such that the circuits do not require Dial Tone, Qwest does not require Dial Tone to be present at the CLEC’s CFA.

Qwest is preparing to no longer require the CLEC to provide Dial Tone on new Unbundled Loops (LSR ACT = N) in mid-October and will follow all appropriate CMP timelines. Prior to new Unbundled Loop Basic or Coordinated Hot Cuts, the Qwest Technician will conduct performance testing to assure the new Unbundled Loop complies with its respective NC/NCI standards.

(Part 2, 90 minutes) Perhaps the CLEC request reflects a misunderstanding. Qwest believes that the process in place more than meets the needs of the CLECs. The Basic Option allows Qwest to start the installation or hot cut any time between 8AM and 5PM regional time. Qwest actually allows more than 90 minutes when a Basic Installation is ordered.

Here is the procedure when the Basic Installation Option is ordered:

On Due Date when Qwest is finished doing the installation and core tests, we call to notify the CLEC that we are done and that the test has been completed. If the CLEC wants to do more testing on their own or they can't get something working on their end, Qwest waits 30 minutes, then calls the CLEC again. If the CLEC still isn’t ready Qwest lets the field tech and the Central Office Technician (COT) go to their next jobs.

Qwest will hold the order open and if we do not have a CLEC resolution by the end of day we will have the COT disable the circuit. If the CLEC calls back on the same day and is ready, we will try to get a tech back out (if applicable) and the COT back in the central office. If it is too late in the day, or the resources are not available, Qwest will jeopardize the order and the CLEC must supplement the LSR with a new desired due date.

If the order has multiple loops the CLEC should accept the loops that have Dial Tone and supplement the LSR to remove the loop that does not have Dial Tone. The loop without Dial Tone should be put on a separate LSR with a new desired due date.

In mid-October, on a New order the Outside Technician (OST) will check for dial tone. If the OST does not have dial tone they will: - Call the Central Office and have the COT check for dial tone. If dial tone exists, the OST needs to check the facilities and resolve. - If no dial tone exists, the COT needs to check for dial tone at the Connecting Facility Assignment (CFA). If dial tone exists at the CFA, the COT needs to check the wiring in the CO and resolve. - If dial tone does not exist, the COT will notify the OST and the COT will wire in temporary Qwest dial tone for the OST to perform core tests to complete the order. The QCCC Coordinator / Implementor will not need to notify the CLEC.

Sincerely,

Linda Hendricks Lead Project Analyst Qwest

Cc: Mary Retka, Mary Pat Cheshier, Diane Diebel


Open Product/Process CR PC102802-1 Detail

 
Title: Correction/clarification of Qwest documentation (PCAT, IMA User’s Guide, etc.) describing customer authorization requirements for retrieval of CSRs.
CR Number Current Status
Date
Area Impacted Products Impacted

PC102802-1 Completed
3/31/2003
Pre-Ordering All Products
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner: Thacker, Michelle
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest documentation contains conflicting requirements for CLECs to obtain customer authorization prior to reviewing a customer’s CSR. Qwest’s requirements are not only conflicting within the Qwest documentation, but also conflict with the requirements of applicable law. AT&T requests that Qwest correct its documentation to be clear and consistent with applicable law. The three websites that AT&T has identified with this problem (there may be more) of conflicting information are the websites for:

- Pre-ordering (http://www.qwest.com/wholesale/clecs/preordering.html),

- LOA/POA (http://www.qwest.com/wholesale/preorder/index.html), and

- the IMA User’s guide (http://www.qwest.com/wholesale/downloads/2002/020916/ugpreorder_101_091302.pdf).

The Pre-Ordering website states "Before initiating activity, obtaining a CSR and placing orders on behalf of an end-user, you are required to have a Letter of Authorization or Proof of Authorization giving you authorization to do activity on their behalf." In a separate paragraph, the website provides "While it is not necessary for the LOA to accompany your request, the indication of authorization is required when you request a CSR for an account owned by Qwest or another CLEC." The initial reference to “Letter of Authorization or Proof of Authorization” by itself is fine, but the later reference only to "LOA" suggests written approval from the customer is required for access to the CSR. This is not the case. AT&T understands that customer authorization is required, but a written authorization is not. See 47 CFR Section 64.2007(b). This section of the federal rules identifies the methods by which a carrier may obtain customer approval to access CPNI. It states that "A telecommunications carrier may obtain approval through written, oral or electronic methods." State requirements in the Qwest territory largely mirror the federal rules.

The LOA/POA document states "Prior to obtaining records or placing orders for an end-user you must obtain permission from the end-user to act on their behalf in matters pertaining to the communications services." The following paragraph states "Proof of authorization can be arranged through a Letter of Agency" -- indicating there are options for obtaining authorizations from the customer. The third option cited is "oral authorization verified by an independent third party (with third party verification as POA)." Third party verification is necessary for a transfer of service, but is not required just to view a CSR. The website further states "While the Letter of Agency need not accompany your request for records or services, the indication of agency authorization is a required field entry when you request customer service records or submit Local and Access Service Request forms." As written, this language seems to require a written letter of authorization from the customer in order to view customer records. This is not consistent with the federal and state rules referenced above.

In the IMA user’s guide, "Reviewing Customer Service Records", 10.01 page 1-18 also provides that "Proof that a CLEC has received a Letter of Authorization (LOA) is required if the CLEC attempts to retrieve a CSR for a customer account owned by Qwest or another CLEC". Once again, this language suggests that a written letter of authorization is required. It is not.

While AT&T understands it is necessary to obtain customer consent prior to reviewing CSRs, it is not necessary to obtain written consent or third party verification of oral consent. Qwest does not have the authority through its PCAT, or otherwise, to demand more of CLECs than applicable law requires. AT&T would like to believe that the Qwest language referenced in this CR is simply inadvertent and does not represent Qwest’s intent to require more of CLECs than applicable law requires. However, AT&T does find this documentation troubling and believes that it is important that Qwest clean up its documentation to reflect what is required by applicable law. Please make these corrections and clarifications as soon as possible to avoid further confusion among Qwest’s CLEC customers. Suggestions AT&T would offer include: (i) do not use LOA interchangeably with other forms of authorization that may be obtained; and (ii) simply refer to applicable law in the places where the requirement for authorization needs to be referenced.

Expected Deliverable

AT&T expects Qwest to provide uniform instructions, in accordance with applicable law, within 60 days of submission of this CR.


Status History

10/28/02 - CR Submitted by AT&T

10/29/02 - CR acknowledged by P/P CMP Manager.

11/01/02 - Contacted customer and scheduled Clarification meeting

11/01/02 - CR Posted to Web

11/05/02 - Conducted Clarification meeting with AT&T

11/08/02 - Clarification meeting minutes issued to AT&T

11/20/02 - November CMP Meeting - AT&T presented this CR. CR status changed to Presented. Meeting minutes will be posted to this CR's Project Meetings section.

12/10/02 - Issued Qwest draft response dated 12/3/02 to Carla Dickinson Pardee at AT&T

12/11/02 - Draft Response posted to the web site

12/18/02 - December CMP Meeting - Qwest presented draft response to this CR. CR status changed to Development. Meeting minutes will be posted to this CR's Project Meetings section.

01/08/03 - Issued Qwest response to Carla Dickinson Pardee at AT&T

01/15/03 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/30/03 - Qwest issued Process Notification PROS.01.30.03.F.00998,PreorderingV14, Pre-Ordering Overview V14.0 updates to PCAT, effective date 1/31/03

01/31/03 - Qwest issued Process Notification PROS.01.31.03.F.0997.POA_LOA_V2, Proof of Authorization / Letter of Agency V2.0, planned updates to PCAT, proposed effective date 2/21/03.

02/14/03 - Qwest issued Final Notice and Qwest Response to CLEC Comments on Proof of Authorization Letter of Agency V2.0, effective 2/21/03

02/19/03 - February CMP Meeting - Qwest provided update on this CR. Meeting minutes will be posted to this CR's Project Meetings section.

03/07/03 - Qwest issued PROS.03.07.03.F.01023.LSOG_Updates Pre-Ordering Overview V18.0

03/19/03 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/27/03 - Rec'd voice mail from Carla Pardee ok to close this CR.


Project Meetings

03/19/03 March CMP Meeting Michelle Thacker with Qwest provided status on this CR and said that the 12.0 IMA and LSOG documentation has been provided for review. Carla Pardee with AT&T will call Linda Sanchez-Steinke with Qwest after review of the documentation and advise if AT&T is ready to close this CR. The CLEC Community agreed that this CR could be closed if AT&T agrees.

02/19/03 February CMP Meeting This CR is in development status and Donna Osborne-Miller with AT&T said that Qwest will incorporate the PCAT changes requested, the submitted comments, and they would like to leave the CR open another month. This CR will remain in development status.

01/15/03 January CMP Meeting Michelle Thacker with Qwest gave an update on this CR. Documentation for IMA will be effective 1/21/03 with IMA release 11.01. PCAT documentation is targeted to be available in late January. LSOG documentation and Preparation Guide will be available with the 12.0 IMA release in April. This CR will stay in Development status.

12/18/02 December CMP Meeting Linda Sanchez-Steinke with Qwest presented the draft response to this CR and said that CLEC facing documentation and the IMA User’s Guide will be updated. AT&T agreed with the Qwest response and Liz Balvin with Worldcom asked if there would be updates to the Preparation Guide. Qwest will e-mail an answer to Liz Balvin’s question and include in meeting minutes. This CR will be moved to Development status.

11/20/02 November CMP Meeting Carla Pardee with AT&T presented this CR and said that three of the Qwest pre-ordering web sites have different requirements ranging from oral to written approval prior to CLECs reviewing the customer service record. AT&T Legal interpretation is that only oral approval from customers is required prior to reviewing the CSR. Qwest will present the draft response at the December CMP Meeting.

CLEC Change Request Clarification Meeting

November 5, 2002, 3:00 p.m. (MT) Conference Call 1-877-554-8688 PIN 1930099 # PC102802-1 Correction/clarification of Qwest documentation (PCAT, IMA User’s Guide, etc.) describing customer authorization requirements for retrieval of CSR’s.

Carla Pardee, AT&T Mike Johnson, Qwest Sharon King, Qwest Cap Hamilton, Qwest Beth King, Qwest Michelle Thacker, Qwest Linda Sanchez-Steinke, Qwest

Introduction of the participants on the Conference Call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of change requested in the CR was reviewed. Carla indicated that AT&T is asking that there be consistency in all Qwest documentation associated with the review of customer service records (CSRs). AT&T Legal interprets the wording in the following Qwest websites to be inaccurate according to federal rules, 47 CFR Section 64.2007(b) - Pre-ordering (http://www.qwest.com/wholesale/clecs/preordering.html), - LOA/POA (http://www.qwest.com/wholesale/preorder/index.html), and - the IMA User’s guide (http://www.qwest.com/wholesale/downloads/2002/020916/ugpreorder101091302.pdf) AT&T’s interpretation is that approval to view the customer service record (CSR) can be in written, oral or electronic format.

Confirm Areas & Products Impacted Carla indicated that all products are impacted.

Confirm Right Personnel Involved Qwest confirmed that the right personnel were involved in the conference call.

Identify/Confirm CLEC’s Expectation Carla confirmed that AT&T is not disputing oral approval from customer to review CSR. The documentation wording sounds like the CLECs have to get written permission from customers to view their CSR and AT&T is asking that Qwest documentation be revised.

Establish Action Plan (Resolution Time Frame) This CR will be presented by Carla at the November CMP Meeting.


CenturyLink Response

December 3, 2002

Carla Pardee LSAM Manager AT&T

SUBJECT:Qwest’s Change Request Response - CR # PC102802-1 (Correction/clarification of Qwest documentation (PCAT, IMA User’s Guide, etc.) describing customer authorization requirements for retrieval of CSRs.)

This is in response to AT&T’s Change Request CR PC102802-1. This CR requests that Qwest clarify and correct as needed Qwest documentation (PCAT, IMA User’s Guide, etc.) that describes customer authorization requirements for retrieval of CSRs.

Qwest accepts this CR and will review and clarify CLEC facing documents pertaining or referencing customer authorization requirements.

The IMA User Guide 11.01, is targeted for review in late December and Qwest External Documentation is targeted for review in late January.

Sincerely,

Michelle Thacker Process Specialist Qwest


Open Product/Process CR PC110702-1 Detail

 
Title: Request that rate change notifications/mailouts contain rates effected.
CR Number Current Status
Date
Area Impacted Products Impacted

PC110702-1 Completed
2/19/2003
Notifications/Mailouts All Products
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner: Cornwell, Barbara
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest notifications/mailouts advising of a rate change do not identify the effected rates. Rather, the notifications/mailouts frequently reference a Commission Order from a cost docket, or some other reference, without identifying either the rates that have been effected or the newly implemented rates. It would be extremely helpful to the CLECs if these notifications/mailouts would list the precise rates effected, rather than having to track down the reference to the rate change.

Expected Deliverable

Notifications/mailouts list the precise rates effected.


Status History

11/07/02 - CR Submitted by AT&T

11/08/02 - CR acknowledged by P/P CMP Manager

11/11/02 - CR Posted to Web

11/13/02 - Contacted customer and scheduled Clarification meeting

11/14/02 - Held Clarification Meeting

11/20/02 - Clarification meeting minutes issued to AT&T

11/20/02 - November CMP Meeting - AT&T walked on this CR. Meeting minutes will be posted to this CR's Project Meetings section.

12/10/02 - Issued Qwest draft response dated 12/3/02 to Carla Dickinson Pardee at AT&T

12/11/02 - Draft Response posted to the web site

12/18/02 - December CMP Meeting - Qwest presented draft response to this CR. CR status changed to Development. Meeting minutes will be posted to this CR's Project Meetings section.

12/26/02 - Notification sent PROS.12.26.02.F.00973.CR_RateChange

01/08/03 - Issued Qwest response to Carla Dickinson Pardee at AT&T

01/15/03 - January CMP Meeting - Qwest presented updated response. Meeting minutes will be posted to this CR's Project Meetings section.

02/07/03 - Qwest Issued PROS.02.07.03.F.01008.AZ_Struc_Rates

02/19/03 - February CMP Meeting - CR was moved to completed status. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

02/19/03 February CMP Meeting This CR is in Development status and Donna Osborne-Miller with AT&T said that they received the rate change notification with new rates attached and they would like to close this CR. This CR will be moved to Completed status.

01/15/03 January CMP Meeting Barb Cornwell with Qwest gave an update on this CR and said that a generic Exhibit A will be provided with the Arizona Phase II A cost docket. This CR will remain in Development status.

12/18/02 December CMP Meeting Barb Cornwell presented the Qwest draft response and said that starting with the next Cost Docket, Qwest will include an Exhibit A in the notification. The Exhibit A will include the rates that are changing and timeframe the rates will be changed. Individual contract rate sheets are available from Qwest service managers. Joan Matzler added that SGAT rate changes are also available on the web site. This CR will be moved to Development status. Stichter-Eschelon provided updates to the notes to include the following: Would any change in the SGAT rate because of a cost docket apply to Eschelon? And Qwest responded yes.

11/20/02 November CMP Meeting Carla Pardee with AT&T presented this CR and said that the rate change notifications that Qwest currently provides do not meet AT&T’s needs. Carla said that they would like to have the new rates included in the notifications. Mike Zulevic with Covad said this is something he requests from the Account Team. Once rates are effective, Covad wants to understand the impact prior to implementation. Bonnie Johnson said that Eschelon has asked for rate changes many times and Kathy Stitcher added that previous change requests have been denied. A CR was denied in the May timeframe, because of the number of staff hours required. Sue Burson with Qwest said that she remembered the change request. Mike Zulevic said that Qwest might want to look at the dispute resolution process for billing and determine if providing the new rates is unduly burdensome. Judy Schultz with Qwest asked if AT&T was looking for rates associated with specific USOCs applying to AT&T. Carla Pardee said that last week they received notification about Arizona and the week before on Utah. They would like to know what the elements are, and what the new rate will be. With the Colorado UNE, we never received rates and it causes confusion, and the account team doesn’t always provide what is needed. Kathy Stitcher said that Eschelon submitted CR number PC053002-2X and it was denied because it was economically not feasible. Kathy said that on Arizona they did contact their service manager and also received a spreadsheet for Utah with some items missing. It was agreed this CR would move to clarification status.

- CLEC Change Request Clarification Meeting

November 14, 2002, 2:30 p.m. (MT) Conference Call 1-877-554-8688 PIN 1930099 # PC110702-1 Request that rate change notifications/mailouts contain rates effected. Introduction of the participants on the Conference Call was made and the purpose of the call discussed. Attendees Carla Pardee, AT&T Sue Kriebel, Qwest Barb Cornwell, Qwest Laurel Neher, Qwest Cliff Dinwiddie, Qwest Cindy Pierson, Qwest Dana Nielsen, Qwest Linda Sanchez-Steinke, Qwest

1 Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the call discussed.

2. Review Requested (Description of) Change The description of change requested in the CR was reviewed. Carla indicated that AT&T receives the mailouts when there is a Commission order or Cost Docket for rate changes and they would like to review the rates in a more efficient way and would like ability to compare the old rates to the new rates. Laurel Neher with Qwest asked if this would apply to Exhibit A SGATs. Carla said that most would be applicable and the Utah Order is what prompted the CR and it would be helpful to compare the new rates that were effective and be able to distribute throughout AT&T. Cindy Pierson with Qwest said that today on the Qwest web site Utah 10/16/02 is available in Exhibit A in the SGAT. Carla asked if there is a footnote that references the commission order and Cindy said that the note section lists the dockets approved in. Barb Cornwell with Qwest said that when the notice is received that if interested in AT&T specific rate sheets, an electronic copy of the rate sheet can be sent by the Service Manager. Barb also said that a notification for Arizona would be received today by AT&T. Carla will contact her Service manager and get with the AT&T people who requested the CR to provide information on the web site information available.

3. Confirm Areas & Products Impacted Carla indicated that all products are impacted.

4. Confirm Right Personnel Involved Qwest confirmed that the right personnel were involved in the conference call.

5. Identify/Confirm CLEC’s Expectation Carla confirmed that AT&T is interested in comparing the old rates to the new rates and that they are interested in AT&T specific rates.

6. Establish Action Plan (Resolution Time Frame) This CR will be walked on by Carla at the November CMP Meeting.


CenturyLink Response

January 6, 2003

Carla Dickinson Pardee ILEC Relations Manager AT&T

SUBJECT: Qwest’s Change Request Response - CR PC110702-1 Request rate change notifications/mailouts contain rates effected.

As a follow up to the December 18, 2002 CMP Meeting, Qwest will enhance the current process to additionally provide an Exhibit "A" rate sheet customized to specifically reflect only the rates Ordered in the Docket. This document will be attached as a communication piece with the rate change notifications/mailouts for CLEC distribution and reference.

Qwest plans to have this solution coordinated and operational to coincide with the implementation of the Arizona Cost Docket Phase IIA. Notification of the Arizona rate change is expected on or about January 15, 2003. Level 1 Process Change, PROS.12.26.02.F.00973.CRRateChange, was sent on December 26, 2002.

Sincerely,

Barb Cornwell Senior Process Analyst Qwest

December 3, 2002

DRAFT RESPONSE For Review by CLEC Community and Discussion at December’s CMP Meeting

Carla Dickinson Pardee ILEC Relations Manager AT&T

SUBJECT:Qwest’s Change Request Response - CR PC110702-1 Request rate change notifications/mailouts contain rates effected.

Currently, Qwest notifications/mailouts advising of a rate change do not identify the affected rates. The purpose of the notification is to advise the CLEC of the pending implementation of a rate change as Ordered by a Public Utilities Commission. Qwest’s standard operating procedure is to ensure Interconnect Contract Agreements are updated with the Ordered rates are available to CLECs during the implementation process.

In response to this request, Qwest will enhance the current process to additionally provide an Exhibit "A" rate sheet customized to specifically reflect only the rates Ordered in the Docket. This document will be attached as a communication piece with the rate change notifications/mailouts for CLEC distribution and reference.

Qwest plans to have this solution coordinated and operational to coincide with the implementation of the New Mexico Cost Docket. Notification of the New Mexico rate change is expected on or about January 15, 2003.

Sincerely,

Barb Cornwell Senior Process Analyst Qwest


Open Product/Process CR PC030802-1 Detail

 
Title: Local Service Freeze Process to remove LEFV from Qwest residential accounts (being executed under the exception process)
CR Number Current Status
Date
Area Impacted Products Impacted

PC030802-1 Completed
6/19/2002
Pre-Ordering, Ordering, Provisioning, Billing LNP, Private Line, Unbundled Loop, UNE
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Berry, Harriett
Director:
CR PM: Thomte, Kit

Description Of Change

VALIDATE THESE FOLLOWING BULLET ITEMS AS PART OF THE PROCESS:

- Caller must be a Qwest retail customer

- Customer must call business office and say they wish to "remove the freeze off of their local service"

- Do not instruct the customer to use the word "PIC". This is used for inter and intra lata services and causes confusion which can delay removing the LEFV

- CLEC can be a third party on the call to Qwest by the local customer

- Customer can call up to 7pm in his local service area to remove the freeze

- The LEFV resides in a repository that is worked overnight which means it will be removed off the customer's account that night and the LSR can be sent the next day without rejection

- Although updates to a CSR can take up 3-5 days, the removal of the freeze is not dependent on that CSR being updated.

- Qwest does not charge $5 to remove the freeze

- A Communicator will be sent to the CLEC community when the PCAT is updated

The last 2 bullet points can be removed from the CR as per clarification call 03/18/02

Scope expanded to include business accounts as well (per CLEC request 03/20/20)


Status History

03/08/02 - CR Submitted by AT&T (03/08/02 reflects the date notification was sent advising the receipt of this CR at cmpcr@qwest.com and not the 03/05/02 submitted date shown on the CR.)

03/08/02 - CR acknowledged by P/P CMP Manager

03/08/02 - CLEC contacted (e-mail) to organize clarification meeting

03/14/02 - Clarification call cancelled by Qwest. Call rescheduled for Monday March 18th.

03/18/02 - Clarification call held with AT&T

03/19/02 - Clarification draft meeting minutes sent to AT&T by e-mail

03/19/02 - AT&T advised Qwest they would like this CR expedited (on letter dated March 18)

03/20/02 - March CMP Meeting: AT&T 'walked-on' this CR and requested the use of the exception process. CMP meeting participants agreed. AT&T also requested a call next week with Qwest SME’s and the CLEC community. CR Status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/20/02 - AT&T e-mail requesting Qwest to work with them on specific customer issues related to removing local service freeze

03/20/02 - Reply e-mail from Judy Schultz stating she would be investigating the issue

03/21/02 - Notification CMPR.03.21.02.F.01239.CR_Meeting issued to CLECs informing them of a call on 03/26/02 to discuss this issue

03/26/02 - CR scope expanded to include business accounts

03/26/02 - General clarification call held

03/27/02 - Draft general clarification meeting minutes sent to participating CLECs via e-mail

03/28/02 - E-mail from AT&T seeking clarification on the IMA 9.0 edit

03/28/02 - Letter from AT&T expressing their disappointment with the general clarification call held on 03/26/02

03/29/02 - E-mail from AT&T asking for status and description of potential systems fix

04/01/02 - Minutes from general clarification call (03/26/02) updated to reflect AT&T’s comments. Last bullet point modified to reflect AT&T’s request to lift freeze until all issues addressed.

04/01/02 - E-mail from AT&T to Qwest with an example of rejected LSR

04/01/02 - Reply e-mail from Qwest with R-Order details

04/01/02 - Notification CMPR.04.01.02.F.01248.CR_Meeting issued to CLECs informing them of a call on 04/04/02 for a follow up discussion on this issue

04/01/02 - Reply e-mail from AT&T expressing their reservation about the effectiveness of the escalation process

04/02/02 - Draft response dated 04/02/02 sent to AT&T for discussion at Thursday's (04/04/02) general call. CR Status changed to "Presented"

04/02/02 - Notification PROS.04.02.02.F.00414.Local_Service_Freeze issued informing CLECs of PCAT update

04/03/02 - Draft response dated 04/02/02 posted to the P&P Interactive report on the CMP web site at: http://qwest.com/wholesale/cmp/changerequest.html

04/04/02 - Follow-up meeting held

04/04/02 - Notification CRCMPR.04.04.02.F.01251.Draft_CR_Response informing all CLECs a draft response had been posted in the Product/Process Interactive Report for this CR

04/05/02 - Letter from AT&T expressing their disappointment with Qwest's response presented in the follow-up meeting on 04/04/02

04/05/02 - Status update from Qwest on AT&T's request to immediately lift the freeze

04/08/02 - E-mail from AT&T seeking clarification on the correct 800 number to use

04/08/02 - Draft follow-up meeting minutes sent to participating CLECs via e-mail

04/08/02 - Formal Escalation received from AT&T, status changed to "Escalated"

04/09/02 - Reply e-mail with correct 800 number - 877-719-4294 (outside of the retail/business office number 800-244-1111)

04/09/02 - Qwest response sent acknowledging receipt of Formal Escalation from AT&T (PC030802-1-E06).

04/09/02 - Escalation posted to the web: http://qwest.com/wholesale/cmp/escalations.html

04/09/02 - All CLECs notified this CR has been escalated Notification CMPR.04.09.02.F.01252.CR_Escalation

04/10/02 - Worldcom joins escalation PC030802-1-E06 as a participant

04/10/02 - AT&T comments on Qwest's draft response

04/10/02 - E-mail from AT&T asking for clarification on whether the LEFV is always on the CSR

04/10/02 - "Participate" button removed from escalation web site at 5 p.m. (MST) as per CMP guidelines

04/11/02 - Qwest binding response dated 04/11/02 sent to Worldcom and AT&T

04/11/02 - Qwest binding response dated 04/11/02 posted to the web: http://qwest.com/wholesale/cmp/escalations.html

04/11/02 - E-mail from AT&T asking whether the binding response is effective immediately

04/12/02 - Reply e-mail from Qwest confirming binding response is effective immediately

04/17/02 - April CMP Meeting: Qwest and AT&T read out their binding responses. Status remains "Escalated." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/18/02 - Received AT&T binding response and posted to the escalation web site: http://qwest.com/wholesale/cmp/escalations.html Attached binding response to CR

04/19/02 -Received AT&T letter regarding numerous issues associated with the CMP System and Product and Process meeting

04/23/02 - Received email from AT&T regarding process updates Business Procedures RN: Removal of Local Service freeze letter addressed questions with this CR as well as others

04/26/02 - Reply email from Qwest to AT&Ts response of April17th

04/26/02 - Qwest binding response dated 04/26/02 posted to the web: http://qwest.com/wholesale/cmp/escalations.html

04/29/02 - Qwest AT&T and other CLECs participated in a call to review Qwests response to AT&T questions from 04/17/02

05/06/02 - Qwest sent email containing minutes for CLEC review from meeting on 4/29/02

05-15-02 - May CMP Meeting: Status remains "Escalated." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. AT&T to issue letter outlining problems that still exist.

06/19/02 - June CMP Meeting: AT&T agreed to close this CR. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.


Project Meetings

04/19-02 This is an excerpt from a letter sent by Terry Bahner at AT&T. This is the only portion of the letter that pertained to this CR.

Documentation and disposition of AT&T CR PC 03802-1 – Local Service Freeze

As you know, I submitted this CR and requested application of the CMP “Exception Process”. I then escalated the issue based on discussions with Qwest. It’s a strange dichotomy for Qwest to state at the CMP Product and Process meeting that AT&T had five business days to respond to Qwest’s binding response to AT&T’s escalation of PC 030802-1 and then infer it was at Qwest’s own discretion whether to even document AT&T’s comments let alone where. At a minimum, the correspondence generated as part of the escalation should be included with the documentation of the CR, just as all other correspondence and minutes relating to CRs are documented. Since Qwest indicated in its binding response to AT&T’s escalation that Qwest would continue “to do problem solving working sessions with AT&T”, I don’t understand why my request to move the escalated change request to a ”Development” status was denied. AT&T understood the main purpose of escalating a change request was to ensure it received top priority based on business needs, not to house it in the dead-end file once Qwest provides its binding response. Qwest was clearly not prepared to present the binding response at the CMP meeting. No copies were provided to the CLEC community at the meeting and Sue Burson appeared unsettled by the request to present the binding response and respond to questions. While I have provided detailed written comments on Qwest’s binding response, AT&T has not rejected it. The areas addressed by Qwest’s response may satisfy most of AT&T’s needs, however, it is not clear from Qwest’s response that the problems AT&T has been experiencing have actually been resolved. AT&T expects that Qwest will work collaboratively with AT&T to resolve these issues. We are extremely disappointed that Qwest chose to then send out the local service freeze notice as a Level 1 notification (Announcement Date: April 18, 200; Document Number: PROS.04.18.02.F.00426.LocalServFreeze) . Judy, you had articulately explained the five levels of Qwest-initiated product/process changes in the morning portion of the April 17th meeting. Yet, the notice was sent on April 18th as a Level 1 instead of the Level 3 AT&T had strongly recommended in our written and oral responses on April 17th. We have repeatedly indicated to Qwest the local service freeze has had a daily negative impact on our ability to meet the end customers’ requests for a change in local service provider. For Qwest to indicate at this juncture of the change request that no comment cycle is available to the CLEC community shows a true disregard for the redesigned CMP, to the commitment made by the entire CMP re-design team since its work began in July 2001 and to Qwest’s commitment in its binding response “to do problem solving working sessions with AT&T.”

04/10/02 - AT&T comments on Qwest's draft response

1. Caller must be a Qwest retail customer This is a true statement. The Qwest Retail end user may contact their Qwest Retail business office to have their local service freeze removed. Their new CLEC may be on the phone with them at the same time (Three-way call).

AT&T - AT&T should be able to call the retail office without having the customer on line, this would eliminate the unnecessary time it takes to reach the customer. (Portland Metro Market – AT&T Broadband)

2. Customer must call business office and say they wish to "remove the freeze off of their local service" This is a true statement. When the end user customer contacts the Qwest Retail business office, they should ask to have their local service freeze removed. If the end user customer simply states that they are moving to AT&T, there may be some confusion as to whether this is a PIC change or the customer is moving their local service to AT&T.

AT&T - Does the retail office see the pending order to port to the CLEC? End users are being told their Qwest number(s) are disconnected and therefore Qwest cannot remove the LEFV. Perhaps they are confusing the "pending" disconnect. Notation on the Qwest side is very poor. Customers are given information such as their number is disconnected, but when they call back again, there is no note of the information they were given or even that they called in earlier. (Denver Metro Market - AT&T Broadband) AT&T believes the Qwest Retail business office is not the best arm of Qwest to be responsible for removing the LEFV. Sales’ organizations are based on revenue generating actions. They should not be responsible for lifting the LEFV when this clearly indicates a loss of revenue when the end customer moves to another competing CLEC for their local service. We believe this accounts for the lack of notations on the customer’s account after he has called nine times to remove the LEFV. (Terry Bahner - LSAM)

3. Do not instruct the customer to use the word "PIC". This is used for inter and intraLATA services and causes confusion which can delay removing the LEFV This is true. It is helpful in guiding the end user customer through the process since they may have a PIC, LPIC, and Local Service Freeze. The Sales Consultants have been provided training and job aids to help determine the customer’s need.

AT&T - Again, Qwest’s notation is very poor. The notes need to indicate what "type" of freeze the customer wishes to remove. The customer will use the word "LOCAL" and the Qwest notes will indicate "PIC". This is still a training issue on the Qwest side. The "R" order number should be noted so both sides of Qwest’s offices have access to this information. (Denver Metro Market - AT&T Broadband) AT&T believes the lack of notation or the wrong notation on the customer’s account and the multiple times the end customer has to call Qwest to lift the LEFV is indicative of a failed process and a serious training deficit. (Terry Bahner - LSAM)

4. CLEC can be a third party on the call to Qwest by the local customer See question #1

AT&T - AT&T believes Qwest needs to send out additional internal memos to drive home this statement. (Terry Bahner - LSAM)

5. Customer can call up to 7pm in his local service area to remove the freeze Qwest has customers across three different time zones. The Residence end user customer may call their Qwest Retail business office until the close of business in the Pacific time zone. - Central time zone until 9:00 PM (they will be routed to a center in the Mountain or Pacific time zones after 7:00 PM local time) - Mountain time zone until 8:00 PM (they will be routed to a center in the Pacific time zone after 7:00 PM local time) - Pacific time zone until 7:00 PM The hours for the Business, Federal Government, Education, Public Access Lines business offices are listed in the April 3, 2002 update to the PCAT.

AT&T - The window of opportunity to reach the retail office should be extended to include Saturdays. (Portland Metro Market - AT&T Broadband) Prime selling hours are until 9pm. The 7pm time could prevent us from closing the sale if the customer has a freeze on. It is not enough to rationalize that the customer can always call back later to remove the freeze. Sales organizations know that any obstacle thrown in the way of completing the sale at the time of offering the sale diminishes the chances of completing the sale. This places Qwest at an unfair competitive advantage. (Salt Lake Metro Market - AT&T Broadband) AT&T requests expanded hours to include Saturdays. (Denver Metro Market - AT&T Broadband) AT&T believes that Qwest for the time being should at least match their hours of removing the LEFV to the Monday-Saturday schedule already in existence. A second option would be for the CSIE to field the calls and note the customer’s account. (Terry Bahner - LSAM)

6. The LEFV resides in a repository that is worked overnight which means it will be removed off the customer service record. Qwest has a Local Freeze Repository where all frozen phone numbers are stored. That repository is updated on a daily basis as orders are issued to add or remove local freeze. When an order is issued to remove the freeze, the telephone number is removed from the Repository that night. The LEFV will not be removed from the CSR for 3-5 days. See further explanation in response to question 7.

AT&T - If the "R" order number is supplied in the remarks field...why cannot this be done manually and resubmitted the same day? See # 7’s explanation that SDC’s are already checking for system notations and if there is a notation, they will process the LSR. If Qwest does include Saturday hours but not same day supps, what day would the number update in the repository? (Denver Metro Market - AT&T Broadband)

7. Although updates to a CSR can take up 3-5 days, the removal of the freeze is not dependent on the CSR being updated. The Customer Service Record does not update for 3-5 days after the R order is issued to add or remove the Local Service Freeze. When a LSR is issued and there is LEFV on the CSR, the Wholesale Service Delivery Coordinators are checking system notations to determine if an order has been issued to remove the local service freeze. If there is a notation, they will process the LSR. In addition, if the LSR contains the R order number (of the freeze removal) the SDC will allow the order to be processed.

AT&T - The centers should be able to send the LSR immediately after calling the retail office to remove the freeze. Waiting 24hrs to submit is unacceptable unless Qwest is willing to reduce the 3-business day port rule. (This point was made my Jonathan Wolf on last week’s call. (Portland Metro Market - AT&T Broadband) However, the LSR will be rejected if submitted the same day as the LEFV removal request. This adds an additional day to the installation process. This may also require AT&T to contact the customer again to reschedule the originally promised installation date. This, in turn, could cause the original install to be missed if the customer cannot be contacted again in enough time to meet the due date. (Salt Lake Metro Market - AT&T Broadband)

The following questions were submitted by AT&T in a letter to Qwest dated 03/19/02

8. Customer required to call Qwest multiple times to remove LEFV The customer should be able to accomplish removal of the local service freeze in one call to Qwest.

AT&T - Simply remove the freeze with one call. (Portland Metro Market - AT&T Broadband) Should be able to and can are two different things. (Salt Lake Metro Market - AT&T Broadband) AT&T has provided examples where this demonstrates that it does not occur. As stated in earlier meetings with Qwest, this is one of the three process requirements that must be addressed to move the CR towards a workable process. (Terry Bahner - LSAM)

9. No established process to remove the LEFV at the Qwest retail offices Qwest has had established processes in place for local service freeze removal since March 10, 2001 when Local Service Freeze was first implemented.

AT&T - There are no established process by Qwest, until a workable process is in place a all frozen accounts should be lifted per Mike Mason’s request on the last two calls. (Portland Metro Market - AT&T Broadband) It’s apparent these "established processes" are broken. (Denver Metro Market - AT&T Broadband) AT&T has repeatedly indicated the process is not consistent. This has been demonstrated to Qwest by examples that range from Qwest refusing to help the end customer when AT&T Broadband is on the call to actually adding the LEFV and issuing a "D" order to disconnect the customers service instead of the "R" order. (Terry Bahner - LSAM)

10. No consistent confirmation number provided by the Qwest retail offices to note customer account Qwest Sales Consultants are currently providing the R order number to any end user customer or CLEC (on 3-way call) who requests it. We have determined that a specific work group has been providing "confirmation numbers" instead of the R order numbers. That situation has been corrected by the issuance of internal memo (MCC) and managing the performances of the involved individuals. Do not hesitate to request the R order that is being issued to remove the freeze.

AT&T - AT&T believes Qwest needs to continue to monitor how the LEFV is noted on the customer’s account by the Qwest representative. Although AT&T acknowledges and appreciates Qwest identifying a specific work group who was incorrectly providing a "good" confirmation number, a problem still surfaced after the MCC was sent. Once again we reference when Qwest issued either a "D" order or a "C" order for removing the LEFV. (Terry Bahner - LSAM)

11. Inconsistent information between the account team and the PCAT pertaining to submission of the LSR The PCAT is the Qwest official source for CLEC information.

AT&T - AT&T believes Qwest subject matter experts did provide inconsistent information to the service managers. It placed them in a precarious position by having to always "go to the SPOC" for every issue concerning the LEFV. This caused delays in developing a working process and delays in the status of the examples provided. It created a unnecessary extra layer in resolving outstanding LEFV issues. (Terry Bahner - LSAM)

12. Inconsistent Quality Check process at the Sierra Vista Center Calls and orders are monitored on a regular basis to ensure quality.

AT&T - Improved communication between the retail office and Sierra Vista (Portland Metro Market - AT&T Broadband) Inconsistencies still exist. (Denver Metro Market - AT&T Broadband) If this is true, why is Qwest saying they can cancel an LSR related to an LEFV issue? If this is true, why are some orders rejected and others are issued a jeopardy condition after the FOC? (Terry Bahner - LSAM)

13. Inconsistent escalation process at the Denver CSIE once confirmation has been received There are several determining factors as to how the escalation is handled. Each escalation is reacted to on an individual case basis.

AT&T - A single point of contact for escalations. (Portland Metro Market - AT&T Broadband) AT&T believes this does not meet our business requirements. Our third standing request is for Qwest to provide an escalation process that addresses LEFV issues that occur out of process. AT&T should not be penalized and lose their requested due date when Qwest fails to remove the LEFV. Our customer should never be placed in jeopardy when he wishes to have another CLECS’ local service because a Qwest system or agent failed to respond properly to a LSR issue regarding LEFV. (Terry Bahner - LSAM)

14. IMA 9.0 edit pulled and no notice sent to the CLEC Qwest did not remove any IMA 9.0 edits; therefore, notification to the CLECs was not necessary. There was a non-IMA edit in place that was checking the CSRs for LEFV which was relaxed so LSRs could flow through and allow the Service Order Processors to check the Freeze Repository and edit for a freeze at that point in the process.

AT&T - Qwest has stated on numerous occasions that back end systems are not considered CLEC impacting. Therefore, these back end system edits are neither subject to a CLEC review nor a CLEC upgrade notification. AT&T believes these edits did affect our orders. We believe they changed whether a LSR was rejected up front or issued a jeopardy condition after the FOC. This alters how a CLEC responds to an LSR. AT&T has repeatedly asked how these non-IMA edits affect our orders. Qwest has not provided an answer. AT&T has reconfirmed the information provided on March 15th by the Qwest service managers that an edit did occur on March 14th, 2002. If we cannot question Qwest’s backend systems, then we will refer to it as an IMA change when we believe our orders have been impacted. (Terry Bahner - LSAM)

15. IMA 9.0 edit to be implemented at a future date without CLEC notice All planned CLEC Impacting changes to IMA are currently being presented to the CLECs for prioritization. There are no plans to implement a 9.0 edit pertaining to Local Service Freeze.

AT&T - AT&T wants Qwest to not implement any edits in any systems (IMA, non-IMA) until a workable process to remove the LEFV has been agreed upon by AT&T and the CLEC community. (Terry Bahner - LSAM)

16. Jeopardy condition codes issued after the FOC affecting CLEC due date Qwest has listened to the concerns raised by AT&T on this issue and has taken steps to fortify existing processes to alleviate this problem.

AT&T - However, since we have to wait to supp the Pon AFTER the freeze is removed, this still results in a due date push out/reschedule for the customer. (Denver Metro Market - AT&T Broadband) AT&T wants to know what these steps are. The action of issuing a jeopardy condition after the FOC drastically affects our due date. If this jeopardy condition is a result of Qwest’s inability to successfully lift the LEFV, we believe we should not lose our due date under any circumstances. (Terry Bahner - LSAM)

17. Inconsistent Qwest retail process where CLEC can be a third party on the call with end customer See question #1

18. Inconsistent process between removing the LEFV and the updating of the CSR See question #6

19. Confusing reject /jeopardy condition message issued by Qwest The reject/jeopardy message currently being used is the only existing message that fits the local service freeze situation. Requests for new reject messages go through the CMP CR process. LSRs received to change lines/accounts with a local service freeze are rejected with the error message "Features on account are not compatible with requested features". In the Customer Comments section of the Reject Notice Qwest will include the following: "Please have end user contact current local service provider to have local service freeze removed."

AT&T - According to an earlier Qwest communication, Qwest stated the error message would read "Change activity not allowed, CLEC does not own account". Is this the message if the reject is caught up front (fatal reject) as opposed to the message for a jeopardy reject after the FOC? Or has this been changed altogether? (Denver Metro Market - AT&T Broadband) AT&T believes Qwest has not adequately addressed this issue. AT&T has requested LEFV be listed as a reason for a reject/jeopardy message in the PCAT. The jeopardy matrix needs to address LEFV. (Terry Bahner - LSAM)

20. AT&T reiterated they would like all of the above bullet points validated by Qwest and the process clearly documented in the PCAT The PCAT will be updated April 3, 2002.

AT&T - Under the current circumstances, Qwest needs to provide a collaborative atmosphere in resolving LEFV issues before any future PCAT documentation takes place. (Terry Bahner - LSAM)

21. What kind of questions does Qwest ask a Retail end user customer before adding a local service freeze? Upon initial contact with the end user customer, the Qwest Sales Consultant informs the customer of the availability of the freeze as follows: "We offer free protection to ensure that your provider of local service, long distance service, and local long distance service cannot be changed unless you contact us directly. You may remove this protection from your account at any time by contacting Qwest directly with a verbal, written, or electronically signed authorization. Would you be interested in setting that up now?" If the end user customer indicates they would like a freeze established, they are transferred to a Third Party Verifier (TPV) who asks the customer for the Billing Name on the account, Billing Address, the last four digits of their Social Security Number, and their date of birth. In addition, they ask if the caller is over 18 years old and is responsible for the account, and if they have permission to place the local service freeze on each specific line of the account.

AT&T - AT&T believes Qwest needs to go beyond the statement provided. It’s apparent the end customer is unaware of the cumbersome process to remove the LEFV when he wishes to obtain local service from a different company. (Terry Bahner - LSAM)

22. What changes have been made in the Local Service Freeze Removal process since 02/18/02? The process was working well before that date. Qwest has had established processes in place for local service freeze since March 10, 2001 when Local Service Freeze was first implemented. The only changes made to the process have been made within the past two weeks as a result of this CR.

AT&T - It is very clear to AT&T that Qwest did not have a working process in place on March 10, 2001. If Qwest had a good process in place that didn’t harm both the end customer and the CLEC, this CR would have never been submitted. (Terry Bahner - LSAM)

As a general proposition, Qwest has responded in the theoretical realm to many of the questions versus saying what the actual situation is (like in #8 above, but there are many other examples in their responses). It's easy to set up a theoretical process, but that is meaningless if the practical implementation is not being accomplished effectively. (Salt Lake Metro Market - AT&T Broadband)

-

04/08/02 - Draft follow-up meeting minutes sent to participating CLECs via e-mail

CLEC Change Request Follow-up Meeting 11:30 a.m. (MDT) / Thursday 4th April 2002 1-877-564-8688 ID 626-5401 # PC030802-1 Local Service Freeze - Process to remove LEFV from Qwest residential accounts

Attendees: Terry Bahner / AT&T Sharon Van Meter / AT&T Lindel Watkis / AT&T Mike Mason / AT&T Cynthia Linenberger / AT&T Rick Wolters / AT&T Johnthon Wolf / AT&T Joan Russell / AT&T Mitchell Menezes / AT&T Bonnie Johnson / Eschelon Karen Clauson / Eschelon Terry Wicks / Allegiance Leilani Hines / Worldcom Susan Travis / Worldcom Monica Avila / VarTec Telecom, Inc. Judy Schultz / Qwest Todd Mead / Qwest Harriett Berry / Qwest Pam DeLaittre / Qwest Scott Riley / Qwest Pete Budner / Qwest Carylon Brown / Qwest Sue Burson / Qwest

Introduction: - Qwest presented a brief history of the CR, (submitted 03/08/02, clarification call 03/18/02, AT&T expedite letter 03/19/02, AT&T walked-on @ CMP 03/20/02, general clarification call 03/26/02, Qwest draft response issued 04/02/02). The purpose of this call is to review Qwest’s draft response dated 04/02/02 - Note: Notification CMPR.04.01.02.F.01248.CRMeeting issued to CLECs on the 1st of April, informing them of a call on 04/04/02 for a follow up discussion on this issue. Standard P&P Redline guidelines of 5 business days for notifications to CLECs not followed due to expedited status of this CR.

Review Qwest Draft Response - Harriett Berry reviewed Qwest’s draft response dated April 2, 2002 - AT&T commented that using Aegis is currently their only option, as when they call the Qwest Business Offices they be on hold for long periods and the staff do not appear to be familiar with this process. AT&T asked that the 866-311-0222 number remain in effect. Qwest agreed that the Aegis number will remain in effect until this issue is resolved. - AT&T stated that the Qwest web site states the Local Service Freeze can be removed immediately, which has not been their experience. Qwest reiterated that it is effective the same day, but the LSR has to be submitted the next day. AT&T then asked Qwest to reduce the process time by one business day. Qwest took an action to reply to this. - AT&T stated that their desire is for Qwest to lift the Local Service Freeze so the LSR can be submitted the same day - see 2.10 - Eschelon asked if the LSR can be submitted using the R-Order number in the PON field? Qwest believed this would work. Qwest will investigate and report back. - AT&T reiterated they believe something changed on February 18th. They believe this process is broken and asked Qwest to lift the Freeze to before February 18th conditions - see 2.10 - Eschelon stated that Qwest could go to the State Commissions and seek a waiver on the Local Service Freeze. Eschelon also asked about a written process to remove the Freeze. Besides the presence of a form, Eschelon wanted to know whether there was a back end process in place to deal with this and what had been communicated to the CLECs? Qwest took an action to respond to this. - AT&T reiterated they are seeking: 1. To only have to make one call 2. To send in their LSR without rejection 3. A clear and concise escalation process 4. Have the AGIS number available on Saturday’s - AT&T also stated they continue to see large numbers of customers with the Freeze implemented, who believe they have never asked for it on their account. Qwest replied that they are continuing to investigate the AT&T examples and have already found most of the TPV’s for the AT&T examples. AT&T replied they have heard this before but have yet to receive any validation from Qwest. AT&T stated the implementation of a freeze is not clear as too many customers are not aware of this action on their account. Qwest will provide validation to Terry Bahner (AT&T) - AT&T stated they were going to escalate this CR as they expected resolution today, but believed this call had failed in its intent. AT&T want the freeze lifted and want an official response on this from Qwest in 24 hours. AT&T also offered to support an application by Qwest to the commission to get a waiver on Local Service Freeze until this issue is resolved. - AT&T also stated they believe the interim exception process has not worked for them as they had expected a response to this CR immediately.

Establish Action Plan - Qwest will respond to the above actions as soon as possible. - Qwest will either respond or provide a status update on lifting the freeze within 24 hours

-

04/05/02 - Status update from Qwest on AT&T's request to immediately lift the freeze

Status Update: Per action from April 4th CLEC Meeting

All, Qwest continues to review and analyze AT&T's request made yesterday to lift the Local Service Freeze. Qwest has not arrived at its final position at this time, however executive management is deeply engaged. We will follow up with another status update prior to close of business Monday April 8th 2002.

CR details can be found in the Product & Process Interactive report. The Product & Process Interactive report can be found at: http://qwest.com/wholesale/cmp/changerequest.html

Thanks Todd Mead

-

04/05/02 - Letter from AT&T expressing their disappointment with Qwest's response presented in the follow-up meeting on 04/04/02

1875 Lawrence St. Denver, CO 80202-1847

April 5, 2002

Todd Mead CMP Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Change Request PC 030802-1

Dear Todd:

This reconfirms AT&T’s repeated request that Qwest suspend the local service freeze until a collaborative Qwest-CLEC process can ensure an effective, efficient and prompt way to remove the LEFV with no impact to the end customer. AT&T does not believe Qwest’s draft response presented at the April 4th conference call meets our company’s immediate needs.

AT&T is disappointed that Qwest cannot recognize the impact the LEFV has on our daily LNP operations. It is very disturbing when Qwest continues to fail to bring to the table a workable solution. It is discouraging when Qwest continues to ignore our requests to engage the appropriate Qwest subject matter experts to participate in discussions with AT&T to help resolve this issue quickly. Had the appropriate operational SMEs from Qwest participated on the call yesterday, we might have made progress resolving these issues. Unfortunately, once again such individuals were absent.

AT&T’s expectations of the LEFV process is really quite simple. The end customer should be able to remove the LEFV with one call. AT&T Broadband should then be able to submit the LSR to port the customer immediately after the customer has taken the appropriate step to remove the LEFV without fear of an order rejection or a jeopardy condition being issued after the FOC. And last, if the process fails, there is a working escalation process to effectively handle the issue quickly.

Up to this point, Qwest has made minimal effort to work with AT&T to hammer out a workable solution. We view this as a dismal Qwest failure. First, it demonstrates Qwest’s inability to perform a normal function adequately. Second, it clearly shows Qwest does not acknowledge nor recognize the urgency related to the CMP exception process. Third, it demonstrates Qwest’s inability to effectively manage changes to its processes when they adversely impact CLECs.

AT&T will send to Qwest written comments embedded in Qwest’s April 2, 2002, rough draft response to change request PC 030802-1. It will also include AT&T’s proposed resolutions. In the meantime, AT&T will continue to direct the end customer to call AEGIS directly to remove the LEFV from his account. We are expecting at least a verbal response from Sue Burson by close of business today regarding AT&T’s request to suspend LEFV until a workable process can be implemented. AT&T would expect Sue to then send a written response to AT&T. Please insure the minutes from the April 4th conference call reflect AT&T has officially escalated this to Sue Burson.

Sincerely,

Terry Bahner Supervisor AT&T Local Services Access Management Western Region 303-298-6149

Cc: Tim Boykin Sharon Van Meter Donna Osborne-Miller Judy Schultz Mike Mason

-

04/02/02 - Notification PROS.04.02.02.F.00414.LocalServiceFreeze issued informing CLECs of PCAT update

Announcement Date: April 2, 2002 Effective Date: April 3, 2002 Document Number: PROS.04.02.02.F.00414.LocalServiceFreeze Notification Category: Process Notification Target Audience: CLECs, Resellers Subject: Options to Remove Local Service Freeze

Beginning April 4, 2002, Qwest will issue updates to its Wholesale Product Catalog that includes new/revised documentation for Local Service Freeze.

The Local Service Freeze PCAT will be updated to outline the options of requesting the removal of the Local Service Freeze. The PCAT also lists the information the retail end-user needs to provide to have the Local Service Freeze removed.

You will find a summary of these updates on the attached Web Change Notification Form. Actual updates are found on the Qwest Wholesale Web site at this URL: http://www.qwest.com/wholesale/clecs/lsfreeze.html

You are encouraged to provide feedback to this notice through our web site. We provide an easy to use feedback form at http://www.qwest.com/wholesale/feedback.html. A Qwest representative will contact you shortly to discuss your suggestion.

-

03/28/02 - Letter from AT&T expressing their disappointment with the general clarification call held on 03/26/02

1875 Lawrence St. Denver, CO 80202-1847

March 28, 2002

Todd Mead CMP Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Change Request PC 030802-1

Dear Todd:

AT&T is greatly disappointed with the conference call Qwest facilitated March 26, 2002 to discuss the expedited CR PC 030802-1. Qwest stated at the March 20, 2002 Product and Process CMP monthly meeting they understood the urgency of this change request regarding the local service freeze (LEFV). There was no need for a second clarification call. A clarification call had already been held on March 18, 2002.

We believed Qwest was willing to resolve the issue expediently, Todd, when you indicated you would have your subject matter experts available on the March 26th call. I then indicated to you that I was expecting my AT&T Broadband subject matter experts to also be available to help resolve the issue in the e-mail I sent March 22, 2002 (RE: CR # 5582295 - Updated Matrix). I suggested, in order getting to immediate resolution, that you include operational subject matter experts. I was very clear about AT&T’s expectations for the March 26th conference call.

AT&T also believes Qwest implied a resolution would be forthcoming by indicating the temporary 800 telephone number was directly dependent on the outcome of the March 26th meeting. If Qwest was not ready to problem solve the issue then there should never have been a question about keeping the 800 number available. While AT&T appreciates Qwest extending the use of the 800 telephone to help ease the burden of this issue, we should not have had to explain why we needed the extended use of it.

AT&T once again reminds Qwest of the negative impact the LEFV has imposed on our ability to port a customer. It continues to affect our daily ability to port a customer who wants our local service. This truly is unacceptable to us. AT&T has identified and shared with Qwest some of the most basic obstacles in a letter sent March 18, 2002 (RE: Change Request PC 030802-1).

Since Qwest has indicated a formal response will be issued to the CLEC community on April 3rd without a collaborative effort between Qwest and the CLEC community, AT&T clearly expects Qwest to be open to additional suggestions on the follow up conference call scheduled April 4th. AT&T expects that conference call to resolve outstanding issues and the appropriate decision-making individuals from Qwest will attend.

We believe going forward explicit timelines should be provided and adhered to by Qwest for an expedited CR. It should mirror the expedited CR Qwest presented as a walk on at the same March 20 meeting. Qwest clearly defined the timeframe and expectations of the CLEC community during that presentation. It should not be any different for an expedited CLEC CR.

AT&T looks forward to partnering with Qwest and the CLEC community to enhance the Interim Exceptions Process for OSS interfaces, Product and Process Changes (RE: Qwest Re-Design Web site) in future re-design CMP sessions. We believe use of the process, as it now stands for this specific change request, clearly indicates its’ lack of substance.

Sincerely,

Terry Bahner Supervisor AT&T Local Services Access Management Western Region 303-298-6149

Cc: Tim Boykin Sharon Van Meter Donna Osborne-Miller Judy Schultz Mike Mason

-

03/27/02 - Draft general clarification meeting minutes sent to participating CLECs via e-mail

General Clarification Meeting

3:00 p.m. (MDT) / Tuesday 26th March 2002

1-877-564-8688 ID 626-5401 # PC030802-1 Local Service Freeze - Process to remove LEFV from Qwest residential accounts

Attendees: Terry Bahner / AT&T Carla Dickinson-Pardee / AT&T Sharon Van Meter / AT&T Lindel Watkis / AT&T Mike Mason / AT&T Cynthia Linenberger / AT&T Noriko Wilson / AT&T Anthony Robert / AT&T Leilani Hines / Worldcom Susan Travis / Worldcom Monica Avila / VarTec Telecom, Inc. Judy Schultz / Qwest Todd Mead / Qwest Harriett Berry / Qwest Pam DeLaittre / Qwest Gay Abrahamson / Qwest Joan Smith / Qwest Connie Winston / Qwest

Introduction: Qwest presented a brief history of the CR, (submitted 03/08/02, clarification call 03/18/02, AT&T expedite letter 03/19/02, AT&T walked-on @ CMP 03/20/02 and general notification to all CLECs advising them of this meeting 03/21/02) Note: Notification CMPR.03.21.02.F.01239.CRMeeting issued on 03/21/02 to CLECs informing them of a call on 03/26/02 to discuss this issue. Standard P&P Redline guidelines of 5 business days for notifications to CLECs not followed due to expedited status of this CR.

Review Description of Change: Terry Bahner read out the following from Change Request PC030802-1: VALIDATE THESE FOLLOWING BULLET ITEMS AS PART OF THE PROCESS: - Caller must be a Qwest retail customer - Customer must call business office and say they wish to "remove the freeze off of their local service" - Do not instruct the customer to use the word "PIC". This is used for inter and intra lata services and causes confusion which can delay removing the LEFV - CLEC can be a third party on the call to Qwest by the local customer - Customer can call up to 7pm in his local service area to remove the freeze - The LEFV resides in a repository that is worked overnight which means it will be removed off the customer's account that night and the LSR can be sent the next day without rejection - Although updates to a CSR can take up 3-5 days, the removal of the freeze is not dependent on that CSR being updated. - Qwest does not charge $5 to remove the freeze * - A Communicator will be sent to the CLEC community when the PCAT is updated * *Removed as per clarification meeting 03/18/02 Terry also read out additional scope as per AT&T’s expedite request (AT&T letter dated 3/19/02) - Customer required to call Qwest multiple times to remove LEFV - No established process to remove the LEFV at the Qwest retail offices - No consistent confirmation number provided by the Qwest retail offices to note customer account - Inconsistent information between the account team and the PCAT pertaining to submission of the LSR - Inconsistent Quality Check process at the Sierra Vista Center - Inconsistent escalation process at the Denver CSIE once confirmation has been received - Qwest retail office confusing end customers by referring to the LEFV as a PIC freeze (Repeated above 3rd bullet) - IMA 9.0 edit pulled and no notice sent to the CLEC - IMA 9.0 edit to be implemented at a future date without CLEC notice - Jeopardy condition codes issued after the FOC affecting CLEC due date - Inconsistent Qwest retail process where CLEC can be a third party on the call with end customer - Inconsistent process between removing the LEFV and the updating of the CSR - Confusing reject /jeopardy condition message issued by Qwest

- AT&T reiterated they would like all of the above bullet points validated by Qwest and the process clearly documented in the PCAT - AT&T confirmed they would like the CR scope expanded to include Business Accounts as per CLEC request at the March CMP meeting. Todd will adjust CR documentation. - AT&T stated that 68% of all orders for removing LEFV in the Portland region had to be rescheduled last month. AT&T are seeking clarification on what exactly is the process for removing LEFV. AT&T also asked for an extension on the 800 number until the LEFV process is clarified and documented. - Qwest reiterated that they are working as expeditiously as possible to resolve this issue, and they aim to present a written draft response to the CLECs next week. - AT&T said they are willing to wait for the written response next week but need immediate ‘relief’ now. Immediate ‘relief’ was defined by AT&T as: - Keeping the 800 number live until next week (and include Saturday availability) - Someone in CSIE to take the lead on this issue and be nominated as the Single Point of Contact (SPOC) - Qwest would confirm later in the day on the status of this request. - AT&T also stated that they believe 100% of customers they talk too, insist they never asked for the freeze to be installed. AT&T would like to know what type of validation/questions Qwest ask to believe the customer has requested this product. - AT&T also asked for clarification on the R-Number and whether the order number is sufficient as some LSRs are currently being rejected with this information. - Worldcom and VarTec Telecom expressed their continued interest in this issue. - Qwest restated that they are currently not aware of anything that was ‘backed out’ of IMA 9.0 and also reiterated that the only work currently pending for IMA is in the prioritization list for all CLECs to vote on. - AT&T stated that since February 18th 2002, this process has not been working. They requested that in light of Qwest’s inability to support the process and the fact that the freeze placed on accounts were questionable as far as customer approval to begin with. That the best and quickest way to fix this matter was to lift the freeze and go back to the way we were prior to February 18th and not go back until all the issues were properly addressed and good process was actually in place. Qwest stated that a number of States were ‘turned-up’ on Feb 18th so this may be a volume issue. AT&T believe their volume did not change on Feb 18th and asked for the freeze to be lifted until a working process is put in place by Qwest. Qwest replied they understood AT&T’s concern and reiterated they are working as fast as possible on getting an accurate and workable solution for all CLECs.

Establish Action Plan: Next Meeting: Thursday 4th April @ 11:30 am (MDT) - same bridge number as this call. Qwest will present written response. Qwest will investigate and report back to AT&T this afternoon on providing ongoing ‘relief’

-

03/21/02 - Notification CMPR.03.21.02.F.01239.CRMeeting issued to CLECs informing them of a call on 03/26/02 to discuss this issue

Qwest will host a general clarification meeting on CLEC Change Request (CR) PC030802-1 (Process to remove LEFV from Qwest residential accounts) on Tuesday March 26, 2002.

Date: Tuesday, March 26, 2002 Time: 3:00 p.m. MST Conference Line: 1-877-564-8688 Passcode 626-5401 #

Details of the CR can be found in the Product/Process Interactive report at: http://qwest.com/wholesale/cmp/changerequest.html Sincerely,

Todd Mead

-

03/19/02 AT&T advised Qwest they would like this CR expedited

1875 Lawrence St. Denver, CO 80202-1847

March 18, 2002

Todd Mead CMP Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Change Request PC 030802-1

Dear Todd:

AT&T is requesting Qwest to officially expedite PC 030802-1. The local service freeze (LEFV) is critically affecting AT&T Broadband’s ability to port customers. This LEFV has presented multiple obstacles. We are requesting to have an immediate discussion between Qwest and AT&T Broadband subject matter experts to discuss the many problems associated with LEFV. What have been identified to date are the following:

- Customer required to call Qwest multiple times to remove LEFV - No established process to remove the LEFV at the Qwest retail offices - No consistent confirmation number provided by the Qwest retail offices to note customer account - Inconsistent information between the account team and the PCAT pertaining to submission of the LSR - Inconsistent Quality Check process at the Sierra Vista Center - Inconsistent escalation process at the Denver CSIE once confirmation has been received - Qwest retail office confusing end customers by referring to the LEFV as a PIC freeze - IMA 9.0 edit pulled and no notice sent to the CLEC - IMA 9.0 edit to be implemented at a future date without CLEC notice - Jeopardy condition codes issued after the FOC affecting CLEC due date - Inconsistent Qwest retail process where CLEC can be a third party on the call with end customer - Inconsistent process between removing the LEFV and the updating of the CSR - Confusing reject /jeopardy condition message issued by Qwest

It is critical Qwest establish a team to address the customer impact and at the same time improve the processes. As I have indicated both in e-mail and on the clarification call to Qwest, this is now a high profile issue between both companies. Mike Mason, Vice-President AT&T Broadband, has escalated this to Scott Shipper, Vice-President Qwest.

AT&T’s account team has declined to work directly with AT&T to resolve this issue and has instructed AT&T to move all discussion to CMP. In addition Todd, you stated on the clarification call held March 18, 2002, Qwest would not provide a resolution to this CR until the monthly CMP forum in May. This is unacceptable to AT&T.

AT&T requests Qwest to expedite PC 030802-1 immediately. AT&T will present this CR as a "walk on". Please inform Jim Beers. Under the Interim Exception Process for OSS Interfaces, Product and Process Changes (RE: Qwest Re-Design Web site) this can be addressed at Wednesday’s monthly CMP meeting and voted on as an expedited issue by the CLEC community.

Sincerely,

Terry Bahner Supervisor AT&T Local Services Access Management Western Region 303-298-6149

Cc: Tim Boykin Sharon Van Meter Donna Osborne-Miller Judy Schultz

-

Clarification Meeting

11:00 a.m. (MDT) / Monday 18th March 2002 1-877-564-8688 ID 626-5401 # PC030802-1 Local Service Freeze – Process to remove LEFV from Qwest residential accounts

Attendees: Terry Bahner / AT&T Donna Osborne-Miller / AT&T Cynthia Linenberger / AT&T Lindel Watkis / AT&T Mike Harggert / AT&T Harriett Berry / Qwest Chris Quinn-Struck / Qwest Pete Budner / Qwest Todd Mead / Qwest

Review Requested (Description of) Change: Terry read out the change request: VALIDATE THESE FOLLOWING BULLET ITEMS AS PART OF THE PROCESS: * Caller must be a Qwest retail customer * Customer must call business office and say they wish to "remove the freeze off of their local service" * Do not instruct the customer to use the word "PIC". This is used for inter and intra lata services and causes confusion which can delay removing the LEFV * CLEC can be a third party on the call to Qwest by the local customer * Customer can call up to 7pm in his local service area to remove the freeze * The LEFV resides in a repository that is worked overnight which means it will be removed off the customer's account that night and the LSR can be sent the next day without rejection * Although updates to a CSR can take up 3-5 days, the removal of the freeze is not dependent on that CSR being updated. * Qwest does not charge $5 to remove the freeze * A Communicator will be sent to the CLEC community when the PCAT is updated

- AT&T asked for more clarification around the 6th Bullet as the updated PCAT indicated the LSR can be submitted immediately after the LEFV is removed (not the next business day). - The last two bullet points can be removed from the original CR. Todd will adjust the CR documentation. - AT&T asked for clarification around the edit that is going into IMA - AT&T asked for Qwest to explain the role and also train the duty pager on the Local Service Freeze process. AT&T have experienced significant problems with issues they have escalated to the duty pager - AT&T also asked Qwest to provide clarification on what remarks to expect in the remarks section of the jep notification re: Joan Wells

Confirm Areas & Products Impacted: Products: LNP, Private Line, Unbundled Loop & UNE Areas: Pre-ordering, Ordering & Provisioning - Billing was added

Confirm Right Personnel Involved: Harriett confirmed she is the correct person to be the Qwest SME in relation to this CR.

Identify/Confirm CLEC’s Expectation: AT&T want to see a clear and concise process around removing the Local Service Freeze, verified and documented in PCAT.

Establish Action Plan (Resolution Time Frame): General clarification – April CMP meeting. Qwest’s initial response presented at May CMP meeting. AT&T will send Change Management a letter this afternoon requesting Qwest expedite this CR. AT&T will ‘walk-on’ this CR at Wednesday’s CMP meeting.


CenturyLink Response

Draft Response for Discussion on General Clarification Call to be held April 4th

April 2, 2002

Terry Bahner Supervisor AT&T Local Services Access Management 1875 Lawrence St. Denver, CO 80202-1847

SUBJECT: Qwest’s Change Request Response - CR # PC 030802-1 "Local Service Freeze Removal for Residence and Business Customers"

Following are responses to your list of issues and questions from CR #PC030802-1, your additional list of issues dated March 19, as well as questions from our March 26, 2002 conference call.

1. Caller must be a Qwest retail customer This is a true statement. The Qwest Retail end user may contact their Qwest Retail business office to have their local service freeze removed. Their new CLEC may be on the phone with them at the same time (Three-way call).

2. Customer must call business office and say they wish to "remove the freeze off of their local service" This is a true statement. When the end user customer contacts the Qwest Retail business office, they should ask to have their local service freeze removed. If the end user customer simply states that they are moving to AT&T, there may be some confusion as to whether this is a PIC change or the customer is moving their local service to AT&T.

3. Do not instruct the customer to use the word "PIC". This is used for inter and intraLATA services and causes confusion which can delay removing the LEFV This is true. It is helpful in guiding the end user customer through the process since they may have a PIC, LPIC, and Local Service Freeze. The Sales Consultants have been provided training and job aids to help determine the customer’s need.

4. CLEC can be a third party on the call to Qwest by the local customer See question #1

5. Customer can call up to 7pm in his local service area to remove the freeze Qwest has customers across three different time zones.

The Residence end user customer may call their Qwest Retail business office until the close of business in the Pacific time zone.

- Central time zone until 9:00 PM (they will be routed to a center in the Mountain or Pacific time zones after 7:00 PM local time) - Mountain time zone until 8:00 PM (they will be routed to a center in the Pacific time zone after 7:00 PM local time) - Pacific time zone until 7:00 PM

The hours for the Business, Federal Government, Education, Public Access Lines business offices are listed in the April 3, 2002 update to the PCAT.

6. The LEFV resides in a repository that is worked overnight which means it will be removed off the customer service record. Qwest has a Local Freeze Repository where all frozen phone numbers are stored. That repository is updated on a daily basis as orders are issued to add or remove local freeze. When an order is issued to remove the freeze, the telephone number is removed from the Repository that night. The LEFV will not be removed from the CSR for 3-5 days.

See further explanation in response to question 7.

7. Although updates to a CSR can take up 3-5 days, the removal of the freeze is not dependent on the CSR being updated. The Customer Service Record does not update for 3-5 days after the R order is issued to add or remove the Local Service Freeze.

When a LSR is issued and there is LEFV on the CSR, the Wholesale Service Delivery Coordinators are checking system notations to determine if an order has been issued to remove the local service freeze. If there is a notation, they will process the LSR. In addition, if the LSR contains the R order number (of the freeze removal) the SDC will allow the order to be processed.

The following questions were submitted by AT&T in a letter to Qwest dated 03/19/02

8. Customer required to call Qwest multiple times to remove LEFV The customer should be able to accomplish removal of the local service freeze in one call to Qwest.

9. No established process to remove the LEFV at the Qwest retail offices Qwest has had established processes in place for local service freeze removal since March 10, 2001 when Local Service Freeze was first implemented.

10. No consistent confirmation number provided by the Qwest retail offices to note customer account Qwest Sales Consultants are currently providing the R order number to any end user customer or CLEC (on 3-way call) who requests it. We have determined that a specific work group has been providing 'confirmation numbers' instead of the R order numbers. That situation has been corrected by the issuance of internal memo (MCC) and managing the performances of the involved individuals. Do not hesitate to request the R order that is being issued to remove the freeze. 11. Inconsistent information between the account team and the PCAT pertaining to submission of the LSR The PCAT is the Qwest official source for CLEC information.

12. Inconsistent Quality Check process at the Sierra Vista Center Calls and orders are monitored on a regular basis to ensure quality.

13. Inconsistent escalation process at the Denver CSIE once confirmation has been received There are several determining factors as to how the escalation is handled. Each escalation is reacted to on an individual case basis.

14. IMA 9.0 edit pulled and no notice sent to the CLEC Qwest did not remove any IMA 9.0 edits; therefore, notification to the CLECs was not necessary. There was a non-IMA edit in place that was checking the CSRs for LEFV which was relaxed so LSRs could flow through and allow the Service Order Processors to check the Freeze Repository and edit for a freeze at that point in the process.

15. IMA 9.0 edit to be implemented at a future date without CLEC notice All planned CLEC Impacting changes to IMA are currently being presented to the CLECs for prioritization. There are no plans to implement a 9.0 edit pertaining to Local Service Freeze.

16. Jeopardy condition codes issued after the FOC affecting CLEC due date Qwest has listened to the concerns raised by AT&T on this issue and has taken steps to fortify existing processes to alleviate this problem.

17. Inconsistent Qwest retail process where CLEC can be a third party on the call with end customer See question #1

18. Inconsistent process between removing the LEFV and the updating of the CSR See question #6

19. Confusing reject /jeopardy condition message issued by Qwest The reject/jeopardy message currently being used is the only existing message that fits the local service freeze situation. Requests for new reject messages go through the CMP CR process.

LSRs received to change lines/accounts with a local service freeze are rejected with the error message "Features on account are not compatible with requested features." In the Customer Comments section of the Reject Notice Qwest will include the following: "Please have end user contact current local service provider to have local service freeze removed."

20. AT&T reiterated they would like all of the above bullet points validated by Qwest and the process clearly documented in the PCAT. The PCAT will be updated April 3, 2002. 21. What kind of questions does Qwest ask a Retail end user customer before adding a local service freeze? Upon initial contact with the end user customer, the Qwest Sales Consultant informs the customer of the availability of the freeze as follows: "We offer free protection to ensure that your provider of local service, long distance service, and local long distance service cannot be changed unless you contact us directly. You may remove this protection from your account at any time by contacting Qwest directly with a verbal, written, or electronically signed authorization. Would you be interested in setting that up now?"

If the end user customer indicates they would like a freeze established, they are transferred to a Third Party Verifier (TPV) who asks the customer for the Billing Name on the account, Billing Address, the last four digits of their Social Security Number, and their date of birth. In addition, they ask if the caller is over 18 years old and is responsible for the account, and if they have permission to place the local service freeze on each specific line of the account.

22. What changes have been made in the Local Service Freeze Removal process since 02/18/02? The process was working well before that date. Qwest has had established processes in place for local service freeze since March 10, 2001 when Local Service Freeze was first implemented. The only changes made to the process have been made within the past two weeks as a result of this CR.

Sincerely,

Harriett Berry Senior Process Analyst Qwest

Cc: Sue Burson, Director Process Management, Qwest


Open Product/Process CR PC040501-1 Detail

 
Title: Legacy CR USOC Differentiation of Business and Residence
CR Number Current Status
Date
Area Impacted Products Impacted

PC040501-1 Withdrawn
5/16/2001
Billing Unbundled Loop
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner:
Director:
CR PM:

Description Of Change

This change request asks Qwest to create a list of business USOCs separate from residence USOCs to alleviate OCN problems for CLECs. In order to ensure that the appropriate billing unit, residence or business, receives the correct DUF files for billing purposes, two OCNs for each state are having to be used for each product. If there were separate business USOCs from residence USOCs, it would only be necessary to have one OCN for each state for each product.


Status History

04/03/01 - CR submitted by Carla Dickinson

04/05/01 - Status changed to New - To be Industry Evaluated and sent to Carla Dickinson

04/06/01 - Status changed to New - To be Clarified and questions sent to Carla Dickinson

04/06/01 - Updated CR sent to Carla Dickinson

05/16/01 - Status changed to Canceled - Qwest and Co-Provider as per May CICMP Meeting

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR PC120301-6 Detail

 
Title: Two Six Code Inventory For Local Interconnection Trunk Groups Ordered By Qwest
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-6 Completed
12/18/2002
Provisioning Local Interconnection Service (LIS)
Originator: Stryczek, Kathy
Originator Company Name: AT&T
Owner: Olsen, Linda
Director:
CR PM: Thomte, Kit

Description Of Change

When Qwest orders a local interconnection trunk group, AT&T assigns the two-six code and returns it to Qwest on the FOC. Qwest should be inventorying the two-six code that AT&T assigns for Qwest-initiated ASRs. However, Qwest is not inventorying the AT&T two-six code. Qwest is assigning their own two-six code. This presents a major problem in a number of areas including maintenance. One of the first pieces of information asked by Qwest when AT&T reports a trouble is to provide the two-six code. AT&T provides the AT&T-assigned two-six code, but Qwest didn't inventory it so the Qwest maintenance group can't find the trunk group AT&T is reporting.

Here is the industry documentation from the ASOG for two-six code assignment:

53 TSC - Two Six Code

Identifies a code assigned to a trunk group or a CCS link

Set.

NOTE 1: The code set is unique to each established

trunk group or CCS Link Set and is provided to the

customer on the Firm Order Confirmation or Design and

Order Confirmation. The TSC entry may then be

populated by the customer when ordering changes,

additions or deletions to an existing trunk group or CCS

Link Set.

Clearly Qwest is not in compliance with inventorying the two-six code, as the ASOG specifically states the two-six code is provided to the customer on the FOC. In the case where Qwest initiates ASRs, Qwest is the customer and AT&T is the supplier. Consequently, Qwest should be inventorying the two-six code provided by AT&T to Qwest on the FOC.

Expected Deliverables:

AT&T expects that Qwest will comply with industry guidelines and change process to begin to inventory the two-six code that AT&T assigns to Qwest-initiated ASRs.


Status History

12/03/01 - CR Submitted by AT&T and acknowledged by Qwest

12/07/01 - Clarification call arranged for 12/10/01, rescheduled for 12/11/01 at AT&T's request

12/11/01 - Clarification call held with AT&T

12/12/01 - CMP Meeting, AT&T introduced their CR, status changed to Clarification

12/14/01 - Draft clarification meeting minutes issued to AT&T

01/16/02 - January CMP meeting. The CR was clarified with the CLEC community. Qwest presented various potential manual and system options. Qwest received feedback on potential solutions and will continue to evaluate scenarios for presentation at the February CMP meeting. Status changed to "Evaluation"

02/12/02 - Draft response sent to AT&T and entered into CMP Database

02/19/02 - E-mail from AT&T with some questions about Qwest's response

02/20/02 - February CMP meeting: Qwest response dated 02/12/02 presented to CLECs. Qwest will present expected time frame for system implementation at the March CMP meeting. CR Status changed to "Development" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/22/02 - Formal response dated 02/12/02 issued to CLECs - Document Number: CMPR.02.22.02.F.01229.CR_Responses

03/20/02 - March CMP Meeting: Status update provided to CLECs, CR status to remain in "Development." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/12/02 - Revised response dated 04/10/02 sent to AT&T

04/12/02 - Revised response dated 04/10/02 posted to the web

04/17/02 - April CMP Meeting: Qwest presented revised response dated 04/10/02. Qwest agreed to open a related systems CR. Status of this CR to be advised after discussions with Judy Schultz. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/24/02 - Issued Systems CR to cmpcr@qwest.com on behalf of AT&T

05/15/02 - May CMP Meeting: CLEC participants agreed that the CR could be closed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/14/02 - Held status session with AT&T

06/25/02 - Held status session with AT&T

06/27/02 - Held status session with AT&T

07/11/02 - Held status session with AT&T

07/18/02 - This CR was reopened under Product and Process as agreed to in the monthly Systems CMP meeting.

07/25/02 - Held status session with AT&T

08/21/02 - August CMP Meeting: This CR will remain in "Development" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

09/11/02 - Sent Revised Response to AT&T

09/18/02 - September CMP Meeting: This CR will remain in "Development" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

09/26/02 - Contacted AT&T to establish status session.

10/07/02 - Held status Meeting with AT&T

10/16/02 - October CMP Meeting: This CR will remain in "Development" Status Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

11/20/02 - November CMP Meeting: This CR was changed to "CLEC Test" Status, Meeting minutes posted to this CR's Project Meeting section and the CMP Web site.

12/18/02 - December CMP Meeting: This CR Changed to Completed status. Meeting Minutes posted to this CR's Project Meeting sectiona dn the CMP Web site.


Project Meetings

12/18/02 - December CMP Meeting Qwest (Thomte) reported that the process is working as agreed to AT&T advised it is O.K. to close this CR. This CR will change to Completed status.

11/20/02 November CMP Meeting Qwest (Thomte) indicated that the trial orders that were established to convert the embedded base trunk groups in Wyoming were successful. The result is that both new trunks and embedded trunk groups appear to process through the systems using the AT&T Two Six code of CC. Qwest recommended that this CR move to CLEC Test and potentially be completed in December.

10/16/02 October CMP Meeting Qwest (Thomte) indicated that the trial was continuing and that two trial groups that are due to complete in early November. This CR to remain in “Develoment”.

08/21/02 - August CMP Meeting Qwest (Thomte) indicated progress had been made on this CR. Back end systems and reporting capability should be capable of accepting non Qwest two six code during September. Qwest and AT&T anticipate having a status meeting in late August. AT&T (Van Meter) concurred with the read out. This CR will remain in "Development" status

02/19/02 E-mail from AT&T with some questions about Qwest's response

Subject: RE: Qwest Response to Change Request PC120301-6 "Two-Six Code Inv entory for Local Interconnection Trunk Groups Ordered by Qwest" Date: Tue, 19 Feb 2002 17:20:24 -0600 From: "Stryczek, Kathleen K (Kathy), BNSVC" To: Michael Keegan CC: "Olsen, Linda Kae" , "Martin, Richard" , "Mead, Todd" , "Adkisson, Ann B, NCAM" , "Feinstein, Philip G (Phil), NNCER" , "Scherer, Esther A, NCAM" Michael, Thank you for your response to request PC120301-6 for Qwest to inventory the two-six code provided by AT&T on local interconnection trunk groups ordered by Qwest. If Qwest used the two-six code as the PON, would AT&T be able to report trouble tickets using the AT&T assigned two-six code? Also, would the Qwest maintenance group be able to locate a trunk group by searching for a PON which would have the two-six code embedded? If Qwest uses the AT&T two-six code only in the PON, but not in other systems, then I am concerned that Qwest may not be able to find the two-six code and associated trunk group when AT&T is reporting a trouble involving trunk groups ordered by Qwest. Kathy Stryczek AT&T 602-277-4527

Clarification Call, December 11, 2001, 11:00 am (MDT)

Attendees: Todd Mead, Qwest Linda Kae Olsen, Qwest Peggy Kilgus, Qwest Ann Adkinisson, AT&T Kathy Stryczek, AT&T Ester Shearer, AT&T

Reviewed description of Change Request.

Products impacted: Local Interconnection Service (LIS) Qwest need to have someone from the repair group who is involved in the management and use of the TIRKS system, involved in preparing the response to this CR. AT&T's expectation: AT&T would like Qwest to use the two-six code provided by AT&T when Qwest places an order for a local trunk group.

Action Plan: - Qwest will evaluate various options. This CR will be clarified with the CLEC Community at the January CMP Meeting. Qwest will provide a draft response for discussion at the February 2002 CMP meeting. - AT&T will provide Qwest with a contact in Ameritech to discuss ordering process and use of two-six codes. - Qwest to identify and involve the appropriate repair/TIRKS person to assist Linda in developing the draft response. An internal meeting will be held by next Wednesday (12/19/01)


CenturyLink Response

REVISED RESPONSE

September 6, 2002

Kathy Stryczek AT&T

Subject: PC120301-6 Two-Six Code Inventory for Local Interconnection Trunk Groups Ordered By Qwest

This is a revised Qwest response to AT&T’s request, that Qwest comply with industry guidelines and change process to begin to inventory the two-six code that AT&T assigns to Qwest-initiated ASRs.

Qwest accepts AT&T’s request regarding complying with industry guidelines and inventory the two six code that is provided to Qwest on the FOC.

Qwest has worked in conjunction with AT&T to provide a trial request that will flow through the various systems and reporting processes. Qwest is currently making the appropriate modifications to support the request for AT&T.

Currently Qwest has one order that is in a trial process. AT&T has advised that they have additional orders expected in the near future. Qwest expects to address AT&T’s additional orders with the revised process.

Sincerely, Qwest

REVISED RESPONSE

September 6, 2002

Kathy Stryczek AT&T

Subject: PC120301-6 Two-Six Code Inventory for Local Interconnection Trunk Groups Ordered By Qwest

This is a revised Qwest response to AT&T’s request, that Qwest comply with industry guidelines and change process to begin to inventory the two-six code that AT&T assigns to Qwest-initiated ASRs.

Qwest accepts AT&T’s request regarding complying with industry guidelines and inventory the two six code that is provided to Qwest on the FOC.

Qwest has worked in conjunction with AT&T to provide a trial request that will flow through the various systems and reporting processes. Qwest is currently making the appropriate modifications to support the request for AT&T.

Currently Qwest has one order that is in a trial process. AT&T has advised that they have additional orders expected in the near future. Qwest expects to address AT&T’s additional orders with the revised process.

Sincerely, Qwest

REVISED RESPONSE

April 10, 2002

Ms. Kathy Stryczek Manager AT&T

SUBJECT: Qwest’s Change Request Response - CR # PC120301-6 Two-Six Code Inventory for Local Interconnection Trunk Groups Ordered by Qwest

This letter is a follow-up response to AT&T Change Request PC120301-6, requesting Qwest inventory the two-six code that AT&T assigns for Qwest initiated ASRs.

Qwest’s written response dated February 12, 2002 informed the CLEC community that Qwest was willing to perform a detailed economic and technical investigation to evaluate the feasibility of implementing the system changes required to meet the intent of this CR.

Qwest has completed its evaluation and has concluded the cost of changing the myriad of downstream-related systems needed to effect this change is prohibitive. Qwest suggests deferral of this CR until the 2003 fiscal year funding review, planned for later this year.

Therefore Qwest regretfully informs AT&T that this CR cannot be processed this year.

Sincerely,

Susan Bliss Director Process Management Qwest

FORMAL RESPONSE

February 12, 2002

AT&T Ms. Kathy Stryczek Manager

SUBJECT: Qwest’s Change Request Response - CR PC120301-6 Two-Six Code Inventory for Local Interconnection Trunk Groups Ordered by Qwest

This letter is in response to AT&T Change Request PC120301-6, Two-Six Code Inventory For Local Interconnection Trunk Groups Ordered By Qwest. AT&T has requested that Qwest inventory the two-six code that AT&T assigns for Qwest initiated ASRs.

During the CLEC Community clarification meeting held January 16, 2002, AT&T confirmed their desire for Qwest to inventory the TSC provided on the FOC for the order. AT&T agreed that this TSC, along with the TCICs and ACTL information provided today, could be provided during the up-front planning meeting for new markets. Qwest could then use this code as the PON number as well as possibly make program modifications that would allow it to be used as the TSC (TGAC) in the processing and inventory systems used by Qwest (EXACT, IABS, TIRKS, WFA, TRDB, etc.)

Qwest is willing to pursue internal system changes to evaluate the feasibility (technical and economical) of implementing such changes. Qwest can not determine all of the systems that would be impacted, nor what the downstream effects on the process would be until the systems evaluations are performed.

If this approach is acceptable to AT&T, Qwest will initiate the required internal system changes and provide a status update at the March CMP meeting.

Sincerely,

Linda Kae Olsen Process Specialist - LIS Qwest


Open Product/Process CR PC012302-1 Detail

 
Title: Qwest to provide more detail in embargoed central office notifications
CR Number Current Status
Date
Area Impacted Products Impacted

PC012302-1 Completed
3/20/2002
Other: Notifications LNP
Originator: Bahner, Terry
Originator Company Name: AT&T
Owner: Suellentrop, Craig
Director:
CR PM:

Description Of Change

AT&T would like to see more detail included in Qwest’s embargoed central office notifications. Specifically, AT&T seek great clarification about the cut-over process and the planned timing of cut-overs. AT&T also seek clarification on the product implications of this process.


Status History

01/22/02 - CR Submitted by AT&T.

01/23/02 - CR acknowledged by P/P CMP Manager.

01/29/02 - AT&T contacted to schedule clarification meeting for 01/30/02.

01/30/02 - Clarification Meeting conducted with AT&T.

02/06/02 - Clarification Meeting minutes transmitted to AT&T.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/12/02 - Draft response dated 03/01/02 issued to AT&T. CR Status changed to "Presented"

03/13/02 - Received e-mail from AT&T seeking clarification concerning LNP supplemental orders to cancel or reschedule a port out

03/20/02 - March CMP Meeting: CLECs agreed to close CR. CR Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/21/02 - Formal response dated 03/01/02 posted to CMP database

03/22/02 - Formal response dated 03/01/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

1:30 p.m. (MDT) / Wednesday 30th January 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC012302-1 "Qwest to provide more detail in embargoed central office notifications"

Attendees: Terry Bahner, AT&T Esther Scherer, AT&T Sharon Van Meter, AT&T Jonathan Spangler, AT&T Laurel Burke, Qwest Craig Suellentrop, Qwest Joan Wells, Qwest Peter Wirth, Qwest

Introduction of Attendees: Attendees introduced.

Review Requested (Description of) Change: AT&T would like to see more detail included in Qwest’s embargoed central office notifications. Specifically, AT&T seek great clarification about the cut-over process and the planned timing of cut-overs. AT&T also seek clarification on the product implications of this process.

Terry Bahner, AT&T reviewed the CR and added the following points that need to be addressed: 1) AT&T would like additional information on notices for both “switch embargoes” and “frame conversions” including the specific URL in the Qwest Wholesale web page identifying the schedule dates for embargoes/conversions in Qwest CO facilities. Joan Wells, Qwest identified the URL [http://www.qwest.com/cgi- bin/iconn/iconnembargoreport.pl?function=14]. Information was also requested regarding the Qwest contact for notice issuance, and the frequency and time interval for notices transmitted via e-mail to potentially affected CLECs. 2) AT&T indicated that current Qwest notices are incomplete in that “ordering embargo implications” are not addressed. AT&T expressed a need for written language in the notice directing the CLEC to the applicable Qwest procedures for product ordering during the associated “quiet time” and “embargo” periods. This would assist AT&T in planning orders, thus minimizing potential rejected orders during the actual embargo timeframes. Craig Suellentrop, Qwest indicated that current Qwest notices provide information on the physical cut-over process only and not overall product ordering during the entire embargo timeframe. Joan Wells, Qwest will investigate the location of Qwest procedures within the SGAT and PCAT. An example notification was submitted to Qwest via e-mail. This notification was transmitted to the Qwest participants prior to the clarification meeting. 3) AT&T raised questions regarding IMA 9.0. Terry Bahner, AT&T asked “what the different product embargo intervals are in regards to an LSR being rejected because of the IMA 9.0 edit?” Jonathan Spangler, AT&T indicated that the IMA edit was generated under a Qwest internal UR sometime in the November 2002 time frame. Qwest will investigate this IMA edit and determine the impact to product orders during the embargo time frame.

Confirm Areas & Products Impacted: LNP product added to CR.

Confirm Right Personnel Involved: Qwest & AT&T confirmed appropriate personnel were in attendance. Qwest will engage any other additional personnel, as required, to address the IMA 9.0 edit.

Identify/Confirm CLEC’s Expectation: Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR; or provide an expedited response to the CR.


CenturyLink Response

March 1, 2002

Terry L. Bahner Supervisor AT&T 1875 Lawrence St Denver, CO 80202-1847

SUBJECT: Qwest’s Change Request Response - CR # PC012302-1: Qwest to provide more detail in embargoed central office notifications.

AT&T is asking Qwest for more information regarding service order embargoes that occur because of switch conversions. During clarification meetings AT&T had several items that required information. AT&T would like the notices that are sent out about switch conversions to contain specific information about service order embargoes and what products are affected. AT&T is also interested in information about whether a service order embargo applies to LNP port-out activity. Finally, AT&T asked about the IMA 9.0 edit and what orders would be rejected because of this edit. AT&T was particularly concerned about LNP port-out activity regarding the IMA 9.0 edit.

Notices regarding trunk-side services are sent out 90 days and 30 days prior to conversion. These notices are sent to carriers (CLEC’s, IXC’s, and wireless providers) that have LIS, Feature Group, or Type II trunks in the affected switch. If any carrier would like to augment their existing trunks in the new switch, orders to disconnect from the old switch and connect to the new switch must be provided 60 days prior to the conversion. If the carrier only wants to have their trunks transferred on a “like-for-like” basis, the disconnect and new orders must be received 30 days prior to the conversion. Service orders for trunk side facilities are embargoed for 35 days during the conversion process. This interval is established as 30 days prior to the conversion until 5 days post conversion. These dates are stated on the notices.

For line side facilities a service order embargo is in place approximately 5 days prior to the conversion and continues until 2 days after the conversion. Centrex orders will have a standard 5 week embargo (10 days prior to the conversion and 4 weeks post conversion). Service orders with due dates falling within these periods will be rejected. The only exceptions are for disconnects, service denial/restoral, and LNP port-out activity. Some switch conversions (an ISDN only switch for example) have no associated service order embargo. Service order embargo dates are contained on the ICONN website (database http://www.qwest.com/cgi-bin/iconn/iconnembargoreport.pl?function=14).

The IMA 9.0 edit went into effect on February 23, 2002. This edit was put into place to reject line-side orders with due dates that fall within the embargo period. A patch was put into effect on February 27, 2002 to allow LNP port-out orders to flow through.

Sincerely,

Craig Suellentrop Interconnection Planner Qwest

Cc: Joan Wells, Senior Process Analyst, Qwest Mary Retka, Director Legal Issues, Qwest


Open Product/Process CR PC013102-1 Detail

 
Title: DMS100 SR/ALI
CR Number Current Status
Date
Area Impacted Products Impacted

PC013102-1 Completed
4/15/2009
Provisioning 911
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Kaster, Jim
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T has been officially served by Arapahoe County Colorado that current 911 default routing is inadequate. Current 911 call routing for some jurisdictions that define designated serving areas for service providers, is not routed using the ALI database, but is routed via selective router in the DMS 100 switches. If no number is found, then routing should be done by utilizing information associated with the incoming trunk group of the service provider. Current routing methods can, in some cases, route calls to the wrong PSAP, requiring the call to be re-routed to the correct PSAP, resulting in a loss of time in a possible life threatening situation. This issue impacts all CLEC's providing business or residential service.


Status History

01/30/02 - CR Submitted by AT&T.

01/31/02 - CR acknowledged by P/P CMP Manager.

02/06/02 - Clarification Meeting conducted with submitting CLEC.

02/08/02 - Clarification Meeting minutes transmitted to submitting CLEC & posted in CMP data base.

02/13/02 - Requested additional information from AT&T (Arapahoe County documents & list of mis-routed telephone numbers).

02/18/02 - Requested additional information from AT&T receicved.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status remains in "Clarification" due to request to meet with Arapahoe County. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/27/02 - Agenda forwarded to AT&T for technical discussion meeting scheduled for Monday, 03/04/02.

03/04/02 - Conducted technical information exchange meeting with AT&T.

03/04/02 - Received e-mail from AT&T advising that the document received for review at the technical information exchange meeting was not considered AT&T proprietary.

03/11/02 - Issued meeting minutes from technical information meeting to AT&T.

03/20/02 - CMP Meeting - AT&T presented its CR and Qwest discussed its White Paper that was being finalized. Qwest advised that there was a meeting scheduled for tomorrow at 9:00 am with the Colorado PUC, AT&T, Qwest and perhaps a couple of PSAPs. Qwest to send a copy of the White Paper to AT&T when it is approved. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. Qwest advised that the status would move to Evaluation. AT&T disagreed.

03/20/02 - Issued Qwest's White Paper, DMS 100 E9-1-1 Routing, to AT&T.

03/21/02 - Meeting held with Colorado PUC, AT&T and Qwest.

03/22/02 - AT&T requested, via e-mail, that the CR be statused in evaluation.

04/10/02 - CR status changed to Presented

04/10/02 - Draft response sent to originating CLEC and posted to the CMP database.

04/17/02 - CMP Meeting - Qwest presented its response. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would be status as Development.

04/23/02 - Formal response dated April 23, 2002 issued to CLECs. Notification CMPR.04.23.02.F.01260.Final_CR_Response.

05/15/02 - CMP Meeting - Qwest provided a status update. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Development.

06/12/02 - Conducted conference call with AT&T to address action items from the May CLEC Forum, 911 Breakout Session and to discuss disposition of the CR.

06/18/02 - Conducted conference call with AT&T to review initial framework and agreed to conduct two follow-on meetings with vendor, ILEC, CLEC, CO PUC, Intrado, NENA, Independents and RBOC participation. The first half day meeting is scheduled for July 23, 2002 and the second all day meeting is scheduled for July 30, 2002.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Development.

07/01/02 - Issued Mailout notification advising of subcommittee meetings scheduled for July 23, 2002 and July 30, 2002. Notification CMPR.07.01.02.F.01289.Default_Routing_Mtg.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status "Development" was not changed.

07/22/02 - Issued Mailout notification with meeting material for 7/23 conference call. Notification CMPR.07.22.02.F.01293.DefaultRoutingMtgDoc.

07/23/02 - Conducted CLEC and Industry Conference Call. It was agreed that the 7/30 Meeting with CLECs and Industry would be canceled and Qwest and AT&T would meet to discuss the outcome of the meeting and path forward.

07/30/02 - Issued meeting minutes from CLEC Conference Call held on 7/23 through mailout process. Notification CMPR.07.30.02.F.01302.MtgMinDefaultRouting.

07/30/02 - Conducted conference call with AT&T to discuss the 7/23 meeting and discuss the path forward.

08/02/02 - Issued meeting minutes from 7/30/02 conference call to AT&T.

08/21/02 - CMP Meeting - Qwest provided a status on CR. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

09/18/02 - CMP Meeting - Qwest provided a status on CR. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

10/09/02 - Received e-mail from AT&T advising that they were not going to be able to submit their plan as scheduled and this would impact the Novembe Colorado PUC meeting.

10/16/02 - CMP Meeting - Qwest provided a status on CR. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

11/20/02 - November CMP Meeting - Qwest provided a status on CR. ATT is working on process and planning to present to the Colorado PUC in January.

12/18/02 - December P/P CMP Meeting notes will be posted to the Project Meeting section. Proposal still in progress. ATT may present either in January or March as they have some data and issues that needs to be clarified before they can present their findings/decisions.

01/07/03 - Qwest - Jim Kaster advised ATT is working with the PUC and have decided to make their presentation in March. The process is still under development.

01/15/03 -CMP Meeting - Qwest - Jim Kaster advised ATT is working with the PUC and have decided to make their presentation in March. The process is still under development.

02/19/03 - February CMP Meeting minutes will be posted to the Project Meeting section.

03/19/03 - March CMP Meeting minutes will be posted to the Project Meeting section.

04/04/03 - Donna Osborne Miller advised it is okay to close this CR and when she receives a copy of the presentation it will be shared with the CLEC community.

4/16/03 - April CMP Meeting minutes will be posted to the database


Project Meetings

04/16/03 - April CMP Meeting Donna Osborne Miller agreed it was okay to close this item. A copy of the presentation will be included in the notes.

03/19/03 - March CMP Meeting James Kaster Qwest reported ATT gave a presentation to the Colorado PUC on March 13, 2003. This was a very forward looking presentation and the PUC is currently reviewing the information. This team will continue as an ongoing task force. Cindy Macy Qwest asked if ATT would be able to share the presentation with the Forum and also if we could close this CR since the team will be an ongoing task force. Donna –ATT agreed to check with Ervin Rea and let us know if we could close the CR and share the presentation. The suggestion was made to share the presentation at the next CLEC Forum. Donna will advise Cindy of her decision.

02/19/03 - February CMP Meeting Kaster–Qwest advised the team is targeting to present to the PUC in March. The date of the meeting was not known at this time. Sharon Van Meter – ATT asked if Ervin Rea from ATT is involved and Qwest advised yes.

01/15/03 - January CMP Meeting

Kaster-Qwest stated that AT&T will present their report to the FCC in March. The CR remains Development.

12/18/02 December CMP Monthly Meeting Qwest-Kaster and ATT-Spangler advised SME Jim W. and Rich Kaplin are finalizing the presentation. Jim W is working on obtaining the cost estimate and reviewing the data that Entrado provided. They have found some inaccuracies in the data from Entrado that need to be clarified. They have approximately 43 pages of data that needs to be paired down into a presentation. There is a 911 Task Force meeting in January and then again in March. The team would like to present at the January meeting if their data is accurate, otherwise they will continue working on the presentation and present in March. This CR will remain in Development status.

11/20/02 November CMP Monthly Meeting ATT (Spangler) advised they are continuing to work on this project. ATT will plan on presenting their process at the January Colorado PUC meeting. This project will remain in Development status.

10/16/02 October CMP Monthly Meeting ATT advised they are continuing to work on this project but do to additional investigation needed they will not be able to submit their plan as scheduled and will not be able to present at the November Colorado PUC meeting, but plan on presenting at the January meeting. This project will remain in Development status.

Subject: RE: PC013102-1 DMS 100 SR/ALI Change Request Action Item Date: Wed, 9 Oct 2002 19:03:06 -0400 From: "Spangler, Jonathan F, NCAM" To: "Martin, Rick" CC: "Boykin, Timothy (Tim), NCAM" , "Kaplan, Richard S (Rich), NLNS" , "Roth, Diane F, LGA" , "Morgenstern, Dale C, NLNS" , "Bruno, Vincent G, NLNS" , "Friesen, Letty S, LGA" , "Ann Adkisson" , "Carla Pardee" , "Donna Osborne-Miller" , "Ervin Rea" , "Esther Scherer" , "Sharon Van Meter" , "Teresa Bahner"

Per AT&T's action item for CR PC013102-1 DMS 100 SR/ALI, AT&T will not be able to provide a presentation regarding solutions to the 911 default routing in the Denver MSA. AT&T recognizes that this delay jeopardizes our plan to present our solutions to the CO 911 Task Force to be held in November.

If you have any questions, please let me know.

Jonathan Spangler Carrier Performance - Western Region AT&T Local Services & Access Management Voice: 303-298-6240 Fax: 303-298-6455 Email: jfspangler@att.com Pager: 888-858-7243 pin 106241 or jonathan.spangler@my2way.com

09/18/02 September CMP Monthly Meeting Minutes

Qwest advised that AT&T was developing a plan for the Denver area to have 9-1-1 calls default routed by CLEC. Qwest indicated that they would then review the plan and if acceptable schedule a preliminary meeting with the Colorado PUC and another CLEC (ICG). The next step would be to present the plan to the PSAPs at the PUCs formal meeting in November. Eschelon asked if the CLECs would be involved in any of the meetings and if they would have a chance to review the plan. Qwest advised that the meeting in November might be open and they would provide notification when the meeting was taking place. Qwest also indicated that they would post AT&T’s plan to this CR in the CMP Product/Process Change Request Interactive report. The CR will remain in Development.

-

08/21/02 August CMP Monthly Meeting Minutes

Qwest advised that there was a meeting on July 23, 2002 with a wide range of participation including other ILECs, Nortel, NENA Working Committee Chairperson, BellSouth and Idaho PUC. The result of the meeting was that the NENA Working Committee would work towards a national standard, and for the Denver Market, AT&T would be developing a plan for default routing by CLEC. AT&T is currently working with BellSouth to put a recommendation to submit to Qwest for Qwest to pursue funding. The goal is to have everything complete by 10/15/02 for presentation to the PUC and PSAPs. AT&T advised that they concurred with Qwest’s status and appreciated everybody’s participation. They were participating in the NENA working committee and were happy with the progress. They indicated that they would be sending some minor comments to the minutes.

--

CLEC Change Request Qwest & AT&T Conference Call

July 30, 2002, 8:30 am (MT) Conference Call

877-572-8687, P/C 7994817 PC013102-1, DMS100 SR/ALI

Attendees: Ric Martin, Qwest Jim Kaster, Qwest Jim Winegarden, Qwest Matt Kruzick, Qwest Jonathan Spangler, AT&T Ervin Rae, AT&T Richard Kaplan, AT&T

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the meeting discussed.

Discussion Items Rich Kaplin indicated that based on 7/23/02 conference call, AT&T would like to pursue Tom Breen’s recommendation, for the Denver Market, as set forth in paragraph 2.13 of the 7/23/02 meeting minutes. The language from the meeting minutes is as follows: "Tom Breen responding as the NENA Network Technical Committee Chairperson indicated that if the need is to be able to default route at something more granular than the rate center, one would need to assume that the PSAPs play fair, and, with cooperation from Qwest, there would need to be negotiations with the PSAPs. Recommendation could be to get one default PSAP for a rate center or by carrier. Get a PSAP to volunteer to be the default PSAP for the rate center. If picked well, they would most likely be the PSAP handling most default routed calls anyway. Tom indicated that all PSAPs need to be involved in the process. Tom indicated that the long-term solution resides in NENA committees. He indicated that Tom Hinkleman could provide the pre-release final technical recommendation on rate center consolidation. It will be published by NENA shortly. Tom Breen stated that if the above could not be achieved, alternatively, all CLEC’s could ask to negotiate with Qwest for not using NPANXX based routing, however, once the TN/ESN is established (without the delete function on disconnects), the legacy record will remain and could misguide the call. This cannot be on a CLEC by CLEC basis because Number portability will mean that the NPA-NXX ranges will NOT be or will not remain unique to any given CLEC or ILEC. If the wild cards are to be removed it will require it being a switch wide process on each affected Selective Router/SR-ALI database. Tom Breen recommends trying to educate the PSAPs in the area on the technical limitations of the system, and ask them to cooperate in identifying a default PSAP per Rate Center, even if there has to be more than one to spread the load from all of the area’s carriers."

The general discussion was that we needed to look at the reduction in the number of trunks (7) going to the primary PSAPs in the Denver area. The general consensus was that there would be PSAP jurisdictional issues to overcome and we should first get the Colorado PUC buy-in and support from another CLEC. It was agreed that ICG would be an acceptable CLEC. In addition to the jurisdictional issues with the PSAP, the cost issues will need to be addressed.

It was agreed that Rich Kaplin would develop a plan with associated PSAP benefits for reducing the number of Trunks. Jim Winegarden would provide technical support to Rich. Jim Kaster would be Qwest’s point of contact for receipt of documentation of AT&T.

It was understood that the plan would look at the reduction in the number of trunks and does not change Qwest’s standard on default routing. Based on the PSAPs designated to the reduced number of trunks, Qwest will need to change their default wild card to that PSAP and update the NPA NXX, which will require a complete reload. This could be accomplished by staggered cuts.

The following plan was agreed to: - AT&T will submit a working plan by the end of September - Qwest will perform its cost evaluation by mid October - ICG support and participation will be obtained. - If Qwest agrees to move forward, Qwest will initiate a preliminary meeting with the PUC staff by the end of October. - Presentation will be made at the PUC Task Force meeting on November 14, 2002. - With support from the PUC, a presentation will be made to the PSAPs – timing to be determined.

It was agreed and recognized that participation in the NENA Default Path subcommittee was very important.

-

CLEC Change Request CLEC and Industry Conference Call

July 23, 2002, 8:30 am (MT) Conference Call

877-572-8687, P/C 7994817 PC013102-1, DMS100 SR/ALI

Attendees: Ric Martin, Qwest Linda McKelvey, Qwest Jim Kaster, Qwest Jim Winegarden, Qwest Mary Wallace, Adelphia Jonathan Spangler, AT&T Vince Bruno, AT&T Dale Morgenstern, AT&T Richard Kaplan, AT&T Bernard Brabant, Bell Canada – NENA Default Path Working Group Chairperson Tom Breen, BellSouth Gretchen Leedy, Cbeyond Michael Lipread, Cbeyond Susan Bumstead-Smith, Century Tel Sheila Stewart, Century Tel John Walker, Complete Telecommunications Amanda Owens, Eschelon David Frame, Eschelon Paul Hanser, Eschelon Wayne Hart, Idaho PUC Joe Schumacher, Intrado Steve Sipple, Nortel James Baron, Talking Nets Rana Peeling, US Link Kim Sattler, US Link

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the meeting discussed.

Jim Kaster provided background on the AT&T Change Request and directed participants to the CMP Web site to review the CR. Jim addressed the parties involved being the end user, independent telephone companies, CLECs, Qwest, Public Service Answering Point (PSAP) and the State. The PSAP and the State would be left to accept or reject any recommendations on Default Routing.

Discussion Items Jim Winegarden provided a brief history of 9-1-1 default routing. Jim Winegarden provided a technical explanation of Qwest’s 9-1-1 process. Jim explained that the main issue is with the period of time delay between when the end user has service and the related Service Order Input (SOI) order is entered into the Selective Router Database (SRDB). Jim also indicated that a concern with the use of 10 digit number in the SRDB is that with a disconnect, the number will always remain in the SRDB.

Rich Kaplan indicated that the basis for AT&T’s provisioning found some misroutes caused by the NPA-NXX wildcard. Their issue with Arapahoe County facilitated their issuance of the CR. Arapahoe County withdrew their request. They are still looking for a collective solution for reducing the time period for updates after SOI record submission. The TN Emergency Service Number (ESN) legacy records could still cause misroutes and would require removal. Need to address the first few hours new customers could go to any of the (40) PSAPs in Denver. Jim Kaster explained the PSAPs will transfer the call to the appropriate PSAP.

General consensus in the meeting was that the best thing that could be done is to get the most timely SOI order updates processed.

Tom Breen advised the AT&T’s situation is similar to what BellSouth did in Atlanta with their Rate Center consolidation and linking one primary default PSAP to the Rate Center. Tom indicated that the best solution is timely updates of the database, speed-up the front end processing and PSAP designation to the appropriate Rate Center.

Jim Kaster advised the he believed there was another National Emergency Number Association (NENA) Work Group addressing real time updates.

Rich Kaplan addressed their request on the removal of wild cards and route to the trunk group ESN.

Bernard Brabant indicated that if we’re talking Denver, Colorado has gone through a major rate center consolidation. Records in the Selective Router Database (SRDB) would increase, as every TN/ESN records would have to be transmitted and kept in the SRDB. One of the issue would be uploading that information, due to transport and interface limitations. Need to apply 1 rule nationally. Removal of NPA-NXX wild card would require assignment of trunk group default by Customer entity (Municipality, Region, County, State, Primary PSAP, etc.) and at a minimum by rate center. Canada has deployed a province wide 9-1-1 system arrangement where trunk group default is provided at the Customer/entity/Primary PSAP level. NENA should address the needs of the wireline, wireless and IP worlds.

Jim Winegarden indicated that a default by trunk group would only happen with an ANI failure or no record found.

Tom Breen indicated that in addition to the ALI Database Manager, it is the responsibility of all carriers to improve their service order provisioning process. This may require significant changes to exisiting Operational Support Systems.

Jim Kaster addressed the additional impacts imposed by states. Example is the State of Washington that SOI orders can’t be sent until midnight the day after cut.

Tom Breen addressed NENA future planning. Tier 1 data delivered with each 9-1-1 call would have the incoming call location coded into the call. There is a Powerpoint presentation that was presented at Indianapolis that he could share. Tom also indicated that they were looking at the ability to make the TN ESN address info on the fly and simultaneously update the SRDB (for calls made from a PBX or CTX) .

Vince Bruno suggested that there are some long term solutions, some not so long term solutions and some solutions available today. He wanted to know what solutions are available today (i.e. get SOI orders delivered more quickly, explore issue of disconnects to reduce exposure). Bernard Brabant indicated that the NENA Default Call Path Working Group was being reinstated and there would be a meeting around mid-August. The goal is to come up with a Technical Information Document (TID) on E911default routing standards. Tom Breen suggested using the data technical committee working on ALI database. With his Network Technical Committee hat on Tom Breen suggested the Denver area matter may require special arrangements to solve. His statement in no way implies any obligation on Qwest, AT&T, any other CLEC or any PSAP(s). Rich Kaplan asked if their request to remove wild cards is an option. Tom Breen indicated that the removal of wild card doesn’t correct the problem when there is old record information in the SRDB. Rich Kaplan asked if with a new customer assigned an existing TN, does the legacy record get removed with a disconnect? Jim Winegarden explained that there is no disconnect and the record will remain but the new SOI overlays the old record covering the TN.

Steve Sipple clarified that a range of TNs could not be batch and loaded into the SRDB. Each individual TN needs to be loaded. It was established that the DMS100 could not accept a single tape load of the SRDB and instead must be loaded through individual transactions. Bernard Brabant indicated that an Ethernet Interface Unit (EIU) card allows for faster transactions processing to the selective router. Bernard further indicated that Bell Canada is using an Intrado's Management System set of software applications that does process delete for those TNs that are currently in exception in the MS' SRDBQ file, by sending the deleted TN with the NPA NXX default ESN to the 9-1-1 SRDB (selective router switch) for an overwrite. Tom Breen indicated that some E911 SSPs don’t use that faster TCP/IP port yet, and it would require changes to their ALI DBMS-to-SR update processes.

Bernard Brabant cautioned that before deciding on the best way to go, we need to look at the overall impact. Bernard suggested interested parties are welcome to join his NENA working group. If interested they should send an e-mail to bernard.brabant@bell.ca.

Rich Kaplan asked if Qwest was confident that the 40 PSAPs could effectively transfer calls between PSAPs. Jim Winegarden said yes.

Rich Kaplan asked Tom Breen if he had any recommendations. Tom Breen responding as the NENA Network Technical Committee Chairperson indicated that if the need is to be able to default route at something more granular than the rate center, one would need to assume that the PSAPs play fair, and, with cooperation from Qwest, there would need to be negotiations with the PSAPs. Recommendation could be to get one default PSAP for a rate center or by carrier. Get a PSAP to volunteer to be the default PSAP for the rate center. If picked well, they would most likely be the PSAP handling most default routed calls anyway. Tom indicated that all PSAPs need to be involved in the process. Tom indicated that the long-term solution resides in NENA committees. He indicated that Tom Hinkleman could provide the pre-release final technical recommendation on rate center consolidation. It will be published by NENA shortly. Tom Breen stated that if the above could not be achieved, alternatively, all CLEC’s could ask to negotiate with Qwest for not using NPANXX based routing, however, once the TN/ESN is established (without the delete function on disconnects), the legacy record will remain and could misguide the call. This cannot be on a CLEC by CLEC basis because Number portability will mean that the NPA-NXX ranges will NOT be or will not remain uniqie to any given CLEC or ILEC. If the wild cards are to be removed it will require it being a switch wide process on each affected Selctive Router/SR-ALI database. Tom Breen recomends trying to educate the PSAPs in the area on the technical limitations of the system, and ask them to cooperate in identifying a default PSAP per Rate Center, even if there has to be more than one to spread the load from all of the area’s carriers.

Tom Breen explained that BellSouth’s plan is to move to a centralized Off-Board Selective Routing (OBR) Interface developed by Nortel (ENS00011). Initially they would default route by incoming trunk group and in the future the originating switch’s Tier 1 call data will likely contain the info to route to the correct PSAP. It is anticipated that the OBR database will NOT use wild cards.

Joe Schumacher indicates that Intrado processes SOI records three times a day: 3 AM, 11 AM, and 3 PM

It was agreed that the follow-on CLEC and Industry meeting scheduled for July 30, 2000 would be canceled. Qwest and AT&T will meet to address the discussions from today’s meeting and discuss the appropriate steps to be taken.

07/17/02 - July CMP Meeting Minutes: Qwest is moving forward with the list of attendees for meetings scheduled for July 23, 2002 and July 30, 2002. Meetings are to look at establishing an Industry recommendation on 911 Default Routing. CR status remains development.

06/18/02 Conference Call

Attendees:

Susie Bliss – Qwest Jim Kaster – Qwest Jim Winegarden – Qwest Ric Martin Qwest Jonathan Spangler – AT&T Ervin Rea – AT&T Rich Kaplan – AT&T Vince Bruno – AT&T Tim Boykin – AT&T

It was agreed that two follow-on meetings would be held.

First - July 23, 200 8:30 to 11:30 MT conference bridge 877-572-8687, ID 7994817 Second - July 30th 8:30 to 4:30, hosted by AT&T at their Denver office on Lawrence street.

06/12/02 Conference Call

Attendees:

Susie Bliss – Qwest Matt Kruzick – Qwest Jim Kaster – Qwest Jim Winegarden – Qwest Ric Martin Qwest Jonathan Spangler – AT&T Ervin Rea – AT&T Rich Kaplan – AT&T Vince Bruno – AT&T Dale Morgenstern – AT&T Tim Boykin – AT&T

Conference call was held with AT&T to address action items from the May CLEC Forum, 911 Breakout Session and to discuss disposition of the CR

Qwest advised that they had received written communication from Arapahoe County that the issue with AT&T has been put to rest. AT&T is to work with Arapahoe County on obtaining the written communication that Qwest received.

Both Parties agreed that the solution to AT&T’s Change Request should come from NENA. NENA has a subcommittee on the topic of Default Routing. In addition there is another subcommittee on the topic of Global Dynamic Updates. It was agreed that each party would review internally what each party could contribute to developing a recommendation to take to NENA.

It was agreed that there would be another conference call on Tuesday, 6/18 to review a high-level framework of what this recommendation should be to move forward. AT&T will issue a draft high-level framework document by Friday 6/14 for review on Tuesday.

-

CLEC Change Request Information Exchange Meeting March 4, 2002, 10:00 (MT) Conference Call PC013102-1, DMS100 SR/ALI

Attendees: Ric Martin, Qwest Linda McKelvey, Qwest Jim Kaster, Qwest Patty Joe Ryan, Qwest Jim Winegarden, Qwest Phil Linse, Qwest Jonathan Spangler, AT&T Ervin Rea, AT&T Tim Boykin, AT&T Letty Friesen, AT&T Vince Bruno, AT&T Dale Morgenstern, AT&T Richard Kaplan, AT&T

Introduction of Attendees Introduction of the participants on the Conference Call was made and the Agenda was reviewed. Qwest explained that the purpose of the meeting was for each party to provide an exchange of technical information for each to fully understand each others respective 911 network architectures. AT&T expressed that they wanted the CR to be expedited. AT&T indicated that they also wanted as an outcome of the meeting a perspective of a path forward with Action Items. Qwest advised that they would not commit to coming up with solutions.

Discussion Items AT&T provided a power point presentation of their Architecture via e-mail to all Qwest participants. AT&T clarified that the AT&T Proprietary Statement was not applicable and AT&T would send and e-mail stating such. AT&T reviewed page 2 of their presentation and indicated that bullet number 6 is where the issue resides. Qwest provided the following comments: ? Bullet 3- ALI processed into Intrado and next day file received. ? Bullet 4 & 5 – These bullets are strictly on ANI failures and PSAPs have been aware of this since the inception of 911. ? Bullet 6 – This issue is understood due to the memory constraints and is also understood by the PSAP community. Qwest further explained that the issue in Bullet 6 can’t happen within a few days and that there are memory constraints in the in the DMS100. There was discussion on Nortel upgrades – the ENS 005 for 911 provides all the features and ENS004 would accommodate 32mm records. The original switch feature only allowed 300,000 records in the table, which set the standards for default entries on NPA-NXX. The current switch capability has 800,000 records. Qwest explained that any upgrade would be like doing an office upgrade, which is time consuming and presents an inherent risk to break existing things that are in place. This would be communities that come in on the same trunk group which are tied to different NPA NXXs. For these communities, an ANI failure would pick the larger PSAP and this would show on the screen. Qwest didn’t know if these communities fell within the Denver area. AT&T indicated that they didn’t believe Arapahoe County is aware of this and then what would the solution be. Qwest indicated that all default routing goes to 1 PSAP and a check that was made indicated that the dBase hadn’t been updated. AT&T questioned whether this was ANI failures or what. Qwest advised that this was complete defaults where no record was found and when there was a check with the dBase folks the records were not in the dBase. AT&T questioned that calls went to Arapahoe for anywhere in the Denver Rate Center because the NPA NXX was pointed to Arapahoe, but could have gone anywhere based on the assigned wild card. Qwest indicated that they could validate if the NPA NXX is correct. Qwest asked if the problem was prevalent due to AT&T’s change in testing procedure. Qwest indicated that they were aware that AT&T has multiple NPA NXXs. AT&T asked to get a listing of the Wild Cards used by Qwest. Qwest indicated that on moves with LNP there is a current record and the customer would be miss routed until the record gets updated. AT&T advised that the LERG has all of their NXX codes. Qwest clarified that change in its standard use of the wild card would use up memory, have timing constraints, be costly and would have follow-on impact with existing customers. AT&T asked how there would be a breaking and fixing of the communities that come in from one trunk. Qwest explained that when the community was added, they told us which PSAP the call would go to (i.e. 999 goes to PSAP A, 998 goes to PSAP B and 997 goes to PSAP C). This would be set in the system with its default. Any orders for selective routing are set to the 7 digit if there is a wild card with the same NXX. AT&T indicated that they would not put in any record and the new design would have separate trunk groups and not have the wild card. Qwest explained that with a default ESN to the NXX and you ripped out the NXX would act in the same manner. With a trunk in for 998 PSAP B and you pulled the wild card out the call would have gone to PSAP B. If the number borders 998 and 997, the entry would still show PSAP C. AT&T asked how the system gets built. Qwest explained that it boils down to the state and whether they build per trunk groups or number of lines. It was explained that the PSAP builds to the number of trunks and look at the concentration. In Colorado you are required to build to the number of records, which depend on the number of trunks and switch capacity. Qwest asked how AT&T builds its system. AT&T explained that they monitor to P.01 grade of service and augment/add as required. AT&T stated that Arapahoe is asking to add 6 trunk groups. AT&T feels they are asking for something that can be done in another way. Qwest explained the concentration factor as follows: With 6 communities A – F 3 trunks each for 911 going to the Selective Router would mean a total of 18 trunks. If a PSAP only has 8 trunks they would have to look at the potential volume of calls that could come in from the 18 trunks knowing they can only handle 8. AT&T asked if there were any other issue with eliminating wild cards. Qwest explained that the use of wild cards saves memory. Eliminating wild card could adversely impact others. There would be a ripple effect – Qwest would need a new contract with Intrado. AT&T indicated that the Selective Router has a data field. Qwest indicated that the Selective Router dBase is linked to Intrado. AT&T questioned if the Intrado dBase – data field could look for the information. Qwest advised that if the wild cards are removed, Intrado would have to put it in the table. Intrado would have to do a reload with the entry for the wild card. Denver has approximately 3 mm customers that would have to be reloaded – this would mean down time. Further the switch is in a tandem arrangement which duplicates the effort. AT&T asked if there was any way of arriving at what the situation would be for doing Cap Hill and Broomfield. Qwest indicated that it would come down to time, money and risk. Risk would be the human factor, we really don’t know what they are receiving on a trunk group, etc. Qwest explained that Cap Hill was initially 20 tapes and 10 days brand new. We now have 2 switches. Qwest explained that the dual tandem switch was installed for disaster recover purposes. The tandem switch could not be used as a back-up and both switches would need to be done in parallel. AT&T asked if Qwest could quantify the effort. Qwest identified they would have their costs, Nortel costs and Intrado costs. Qwest couldn’t commit to having quantifiable costs. Qwest asked if AT&T’s dBase has been updated. AT&T indicated that they had an updated report. Qwest advised that they would evaluate the options.

Action Items AT&T is to provide Qwest with their NXXs. Qwest to provide AT&T a list of their wild cards. Qwest to report back to AT&T with a preliminary plan for responding. Qwest will obtain information on how many misrouted calls have been reported by the PSAP, Arapahoe County.

-

1:30 p.m. (MDT) / Tuesday 05th February 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC013102-1 "DMS100 SR/ALI"

Ervin Rea, AT&T Donna Osborn-Miller, AT&T Jonathan Spangler, AT&T Jim Kaster, Qwest Phil Linse, Qwest Christine Quinn-Struck, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Description: AT&T has been officially served by Arapahoe County Colorado that current 911 default routing is inadequate. Current 911 call routing for some jurisdictions that define designated serving areas for service providers, is not routed using the ALI database, but is routed via selective router in the DMS 100 switches. If no number is found, then routing should be done by utilizing information associated with the incoming trunk group of the service provider. Current routing methods can, in some cases, route calls to the wrong PSAP, requiring the call to be re-routed to the correct PSAP, resulting in a loss of time in a possible life threatening situation. This issue impacts all CLEC's providing business or residential service.

Expected Deliverables: DMS100 switches to be modified to ensure that the switch is routing calls according to the ALI database and not the selective router. Should a number not be located in the ALI database the routing should utilize information associated with incoming trunks.

1) Urban Ray reviewed the CR. Requested that "modified" be changed to "programmed" in the "Expected Deliverables" text. Basically, AT&T indicated that outside county "911" calls are being misdirected to Arapahoe County, CO. AT&T’s position is that programming of the router (Nortel DMS100) is required to correctly route using the Automatic Line Identification (ALI) database to the appropriate Public Service Access Provider (PSAP) (i.e., Arapahoe County). 2) Previous AT&T communications with Qwest were identified. Urban Ray, AT&T agreed to forward correspondences to the CRPM. 3) Qwest asked for a listing of any phone numbers that were misdirected to the Arapahoe County PSAP, if available, for Qwest investigation. Urban Ray, AT&T indicated he may speak with Arapahoe County in the near future and will request the listing. 4) Jonathan Spangler, AT&T asked if Qwest could respond to the CR in the February 20, 2002 Monthly Product & Process CMP Meeting. The CRPM indicated that due to the short timeframe, Qwest could give a status update & review the CR with the CLEC community.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Confirmed.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & AT&T confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will solicit input from CLEC community.


CenturyLink Response

April 23, 2002

Donna Osborne-Miller and Ervin Rea LSAM Managers AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC013102-1 DMS100 SR/ALI

This letter is in response to AT&T’s Change Request PC013102-1 requesting Qwest to modify its DMS100 switches to ensure that the switch is routing calls according to the ALI database and not the selective router. Further, if a number cannot be located in the ALI database, AT&T is requesting that the routing utilize information associated with incoming trunks, as one possible solution supported by the manufacturer.

On March 21, 2002, Qwest and AT&T held a meeting with the Colorado Public Utilities Commission (PUC) Staff. In the meeting, the issue of timely ALI database updates was discussed and it was agreed that timely updates would reduce default routing occurrences. It was agreed that the parties would hold off on pursuing default routing by trunk group ESN until a meeting could be held with the PUC and other industry stakeholders. The parties also agreed to participate in the appropriate Industry Forum on Global Dynamic Updates. In addition a meeting is to be scheduled by the PUC Staff with Arapahoe PSAP, Qwest and AT&T to review specific issues and discuss how the parties can address the Arapahoe PSAP’s concerns.

After the meeting Qwest and AT&T agreed that the CR should be placed in a hold status while the aforementioned issues are addressed.

At April 17, 2002 CMP Monthly Meeting it was agreed that the CR would be status as Development until further direction is agreed to.

Sincerely,

Richard H Martin Change Request Project Manager


Open Product/Process CR PC020802-1 Detail

 
Title: Correct and accurate transmission of ADUF or category 011 DUF records.
CR Number Current Status
Date
Area Impacted Products Impacted

PC020802-1 Completed
7/17/2002
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner: Zimmerman, Alan
Director:
CR PM:

Description Of Change

CLECs depend on accurate and correct transmission of access DUF records (category 011 or ADUF) in order to bill IXCs access records. Qwest is not transmissting complete accurate DUF records for category 011, or ADUF records. Consequently AT&T and other CLECs are unable to accurately and completely bill other IXCs.

Modification:

Revised Category reference from "013" to "011"


Status History

02/08/02 - CR Submitted by AT&T

02/08/02 - CR acknowledged by P/P CMP Manager.

02/11/02 - Scheduled Clarification Meeting by e-mail notification to AT&T for 02/15.

02/15/02 - Conducted Clarification Meeting with AT&T.

02/19/02 - Issued Clarification Meeting Minutes to AT&T.

02/24/02 - Issued Revised Clarification Meeting Minutes to AT&T.

03/14/02 - AT&T issued e-mail requesting additional input on the fixes for DUF records.

03/20/02 - CMP Meeting - AT&T presented its CR. Qwest to set-up a meeting with CLECs. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would move to Evaluation.

04/04/02 - CLEC Notification, CMPR.04.04.02.F.01250.CR_Mtg_Logistics, issued scheduling conference call per Action Item 1.

04/10/02 - Issued Qwest's Draft Response dated April 5, 2002 to AT&T.

04/10/02 - Voice Mail received from AT&T requesting that the CLEC conference call scheduled for 4/12/02 be rescheduled.

04/11/02 - CLEC Notification, CMPR.04.11.02.F.01253.CR_MTG_Cancelled , issue to cancel Conference Call.

04/17/02 - CMP Meeting - Qwest Presented its response. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would be status as Development.

04/19/02 - Formal response dated April 5, 2002 issued to CLECs. Notification CMPR.04.19.02.F.01258.Final_CR_Responses.

04/26/02 - Conducted CLEC Conference Call to review system fixes implemented by Qwest to address third party test issues.

05/03/02 - Issued meeting minutes from CLEC Conference call to CLEC participants for comments.

05/09/02 - Issued meeting minutes from CLEC Conference Call to CLEC Community. Notification CMPR.05.09.02.F.01263.Mtg_Minutes_4_26_02.

05/15/02 - CMP Meeting - Qwest advised that the CLEC Conference Call was conducted and meeting minutes issued. Eschelon advised that Qwest's answers to questions were not accurate. Eschelon to send e-mail to Qwest. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would remain in Development.

06/17/02 - Conducted conference call with Eschelon to clarify their concerns on Qwests response to Action Item No. 2.

06/18/02 - Issued e-mail to Eschelon confirming that the issue of CICs being 0000 in the 110125 access records was limited to the Central Region.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status was changed to CLEC Test.

06/25/02 - Issued e-mail to Eschelon and copied AT&T with clarifications to questions raised by Eschelon at the 4/26/02 CLEC conference call.

07/03/02 - Follow-up telephone conversation with Eschelon to confirm that clarifiation response was acceptable. Eschelon to advise.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Completed.


Project Meetings

07/17/02 - July CMP Meeting Minutes:

AT&T agreed to close this Change Request

Subject: Clarification Response to Questions from 4/26/02 CLEC Conference Call Date: Tue, 25 Jun 2002 09:06:57 -0600 From: Richard Martin Organization: Qwest Communications International, Inc. To: Kathy Stichter , wdmarkert CC: Alan Zimmerman , "Pardee, Carla"

Kathy/Bill,

Based on our conference call, Monday June 17, 2002, the following clarifications were made to the previous questions asked and anwered from our 4/26/02 CLEC Conference Call to review System Fixes Implemented Pursuant to Third Party Tests on DUF Transmission:

Meeting Minute item 3.2 - The original question had to do with why access records appear on the DUF with zero's in the CIC. The original answer discussed Feature Group A usage. There is one more circumstance when an access record would show a CIC of zero's. That has to do with 110125 records in the Central region when Qwest is the underlying provider of the 8XX service.

Those records currently go out with a zero CIC as well.

Meeting Minute item 3.3 - It was confirmed that Eschelon will be getting two separate files for Meet Point Billing and DUF. The type of file and mehtod of transmission will depend on the agreements made between Eschelon and Qwest.

To: wdmarkert@eschelon.com, Richard H Martin/Mass/USWEST/US@USWEST cc:

Subject: 0000's in the CIC

Hello; Yesterday I mentioned that I thought that the issue of CICs being 0000 in the 110125 access records was limited to the Central region. I have since confirmed that this is correct. Central is the only region where this occurs. As discussed in our call yesterday, this is usage that was carried by Qwest, so we would be the billable carrier. This should be the only FG-D usage you see with 0000 in the CIC field.

Have a good day!

Alan Zimmerman Qwest Wholesale Billing Manager (303)896-8346

--

CLEC Conference Call

April 26, 2002 10:00 am (MDT) Conference Call TEL: 877-564-8688 CODE: 8973036 System Fixes Implemented Pursuant to Third Party Tests on DUF Transmission (Product/Process CR PC020802-1)

Attendees: Ric Martin, Qwest Wendy Thurnau, Qwest Brad Wickes, Qwest Alan Zimmerman, Qwest Carla Pardee, AT&T Jonathan Spangler, AT&T Kathy Stichter, Eschelon Bill Markert, Eschelon Jack Mungia, Eschelon Deb Hoffman, US Link

Introduction of Attendees Introduction of the participants on the Conference Call was made. Ric Martin explained that the call was a result of an Action Item from March’s CMP Monthly Meeting under Change Request PC020802-1. Details on the CR can be viewed in the CLEC Change Request – Product/Process Interactive Report located at the following URL: http://www.qwest.com/wholesale/cmp/changerequest.html This call will discuss the system fixes that were implemented by Qwest to become compliant with third party tests on the transmission of DUF Records and provide an update on the Central Regions compliance. Ric Martin requested that all CLEC participants send their e-mail address for receipt of meeting minutes.

Review of System Fixes Alan Zimmerman explained the 3rd Party Testing of the DUF conducted by KPMG Consulting and Cap Gemini, Ernst & Young (CGE&Y). The tests involved thousands of calls, and about 43 different call types. Both KPMG and CGE&Y have now concluded that Qwest’s DUF does adequately reflect usage made from Resale and UNE lines. To get to this successful conclusion, Qwest had to make several system changes, as detailed in KPMG’s Exceptions 3036, 3037, 3113 and 3098, as well as CGE&Y IWO 2129. Alan explained that these system changes are generally grouped into two categories: Pending Order File implementations and specific Local Measured Service issues, with a few additional fixes for specific other circumstances. Alan described the fixes and fix dates from those KPMG Exceptions, and answered questions from Eschelon and AT&T. The major fixes discussed included: Pending Order File Process --The pending order file (POF) Process was installed September 13th to more precisely handle usage made within a few days of customer conversion between local service providers. --The Western region had some inconsistencies in the way local measured service usage made on conversion day was handled. This was fixed Nov. 22. --8XX usage did not go to POF process in Western region until Nov 12. Central region had some specific circumstances where 8XX usage delayed in the POF process could be dropped. These circumstances were fixed November 20. --There were timing issues with POF processing in Central such that conversions done via a C order posted on a Thursday or Friday could have some of the usage released from POF for processing before all toll guides and databases were updated. This was fixed Feb. 7th. Local Measured Service (LMS) Records --Central & Eastern had problems that caused a very small percent of Local Measured Svc usage to error. These were fixed in December 2001. --Sent Paid LMS calls that were operator assisted were not properly sent on the DUF in the Western region. This was fixed Nov 22. --Central region LMS calls that originated from a UNE and billed to a resold line did not get a DUF record passed to the reseller until Dec 17. Additional Fixes --WATS attempts that originated from UNEs and did not complete did not have a DUF record generated for the Central region until Feb 18th. --Toll calls that intraLATA calls originated from a coin phone, were sent paid (not alternately billed), were carried by Qwest, and terminated to a UNE account did not have access records generated on the DUF until March 28th. --The Eastern region had a problem that resulted in duplicate records being generated to the DUF when an operator handled LMS call was made. This duplicate record condition was fixed 2/04.

Questions Raised During Discussion AT&T asked what products were covered and Qwest confirmed UNE-P and Resale. Eschelon asked what 0 meant and Qwest replied that if it comes from Qwest and it is a 0, bill Qwest. Qwest was requested to advise what condition access calls show up with a kick of 5123 versus 0 in all 3 regions. Eschelon asked what the meet point billing is on the same DUF. Qwest to provide response.

Closing Ric Martin advised that meeting minutes would be issued to the CLEC participants for review before posting to the CLEC community. Also responses to the Qwest action items would be issued to the all CLEC participants.

Subject: FW: CR PC020802-1 - Clarification Date: Thu, 14 Mar 2002 12:00:18 -0500 From: "Pardee, Carla D, NCAM" To: CC: "Hayes, Robert W (Bob), NCAM"

Ric:

AT&T has been discussing this CR (asking for correct and accurate transmission of DUF records) internally. AT&T would like to know the scope of the problem that was fixed. Did this fix correct only billing systems for UNE-P, or did this DUf transmission problem extend to meet point billing records as well? Does this fix have anything to do with the recent notification about the UNE-P records credits? We would like to set up another meeting to discuss this, or, if it is appropriate to discuss it in the CMP meeting next week, we are amenable to that as well. Let me know what works best for you. Thank you.

ps - I don't have Allan Zimmerman's correct e-mail address, if you wouldn't mind forwarding this to him also. Thank you.

Carla Dickinson Pardee Manager - LSAM (303) 298-6101

Revised (2/24/02) CLEC Change Request Clarification Meeting

2:30 p.m. (MDT) / Friday February 15, 2002 Conference Call TEL: 877-564-8688 CODE: 8973036 PC020802-1, Correct and Accurate Transmission of ADUF, DUF Records

Attendees: Carla Pardee, AT&T Richard Martin, Qwest Lynn Stecklein, Qwest Peggy Esquibel-Reed, Qwest Alan Zimmerman, Qwest Mark Pomeroy, Qwest Doug Warren, Qwest

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Carla advised that the 013 DUF was to transmit Access records. She indicated that the ADUF records were not being transmitted correctly for UNE-P. She indicated that AT&T didn’t believe they were getting all DUF records and subsequently couldn’t bill their IXCs. Carla indicated that she thought that this was something the ROC was monitoring. Alan advised that the test were in the 3036 ROC Test. Alan further stated that the tests indicated that the Eastern and Western regions were 100% compliant. He indicated that the Central region is having issues with access of records received within a couple of days from a Change Order. Carla asked if there was any documentation on this. Alan advised that the documentation is on the WEB under Exception 3036. Alan explained that there is no Category 013, it is 011 for UNEs. Ric explained that there was a Systems Change to split the ADUF and ODUF records

Confirm Areas & Products Impacted It was confirmed that AT&T was interested in the product covered under Cat 011, which is Switched Access. . Confirm Right Personnel Involved It was confirmed that this is a Product/Process CR and Alan Zimmerman is the appropriate SME.

Identify/Confirm CLEC’s Expectation It was confirmed that AT&T wants confirmation that the Central Region is in compliance with providing 100% of the records.

Identify any Dependent Systems Change Requests It was confirmed that there is a System CR to break out Category 010 from 011.

Establish Action Plan (Resolution Time Frame) Qwest will report back on Central compliance progress by March’s CMP meeting


CenturyLink Response

April 5, 2002

Carla Pardee LSAM Manager AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC020802-1 Correct and Accurate Transmission of ADUF or Category 011 DUF Records

This letter is in response to AT&T’s Change Request PC020802-1 requesting accurate and correct transmission of access DUF records (category 011 or ADUF).

During the February 15, 2002 Clarification Meeting, Qwest advised that the 3036 ROC Tests indicated Qwest’s Western and Eastern Regions were 100% compliant with issuance of DUF records. Qwest’s Central Region was still under testing by KPMG.

On Wednesday, KPMG officially closed the last issues associated with the DUF test for the 13 state ROC test area. These last issues had to do with correct population of Indicator 4 and the matches of calls made to DUF records passed in the Central region. KPMG found no records with incorrect Indicator 4 values, and found about 96% of the calls expected on the DUF. KPMG has now sent us the calls that comprise the four- percent of expected calls that KPMG did not find. Qwest will investigate these messages to see if any problems are found. Historically, however, there have been several percent of KPMG's expected calls that did not generate AMA records, did not complete a billable call, did not in fact belong to a wholesale account, or were passed on the DUF but were missed by KPMG. So Qwest expects to be able to explain essentially all the KPMG calls with these valid reasons. That analysis has just begun.

Qwest will provide the results of the analysis when they become available.

Sincerely,

Alan Zimmerman (303)896-8346 azimmer@qwest.com

Cc: Susan Burson


Open Product/Process CR PC090401-4 Detail

 
Title: Clarify Qwest’s process on completing LSRS day after due date
CR Number Current Status
Date
Area Impacted Products Impacted

PC090401-4 Completed
11/14/2001
Ordering and Billing LNP
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

QWEST notified CLEC community LSRS would complete orders day after at 11:59 pm of install date to coincide with disconnect in switch.. Qwest escalation center is stating that orders can start closing as early as 3pm with the possibility of closing even sooner with disconnect to follow. Interconnect has stated that if Qwest determines that there is a large volume of orders to close, they can decide a random time to start the process. AT&T would like to understand why this time frame fluctuates if the closing of these orders causes the disconnect in the switch to shift to an earlier time. AT& T is requesting a flow chart or documentation explaining and listing the backend systems for this process.


Status History

09/04/01 - CR Received from Donna Osborne-Miller of AT&T

09/04/01 - Status changed to New - To be Reviewed

09/04/01 - Updated CR sent to Tim Bessey and Donna Osborne-Miller of AT&T

09/21/01 - Clarification Meetings held with CLEC's.

10/11/01 - Draft Response posted to database.

10/17/01 - CMP Meeting: Draft response presented. Qwest to revise and issue final response. It was agreed that current status be changed CLEC Test.

10/17/01 - Draft response issued to CLEC Community

11/01/01 - Sent final response to Donna OsBorne-Miller at AT&T

11/06/01 - Sent revised final response to Donna OsBorne-Miller at AT&T

11/06/01 - AT&T reply to Qwest final response dated November 6, 2001. Qwest only considers business days in the LNP process.

11/14/01 - AT&T moved to close this CR at the November CMP meeting.

11/16/01 - Matt Rossi issued Final Response Document to the CLEC Community.


Project Meetings

November 6, 2001 AT&T reply to Qwest final response dated November 6, 2001 Joan Wells Qwest LNP Process Manager

RE: CR Form #PCCR090401-4

The intent of this change request was to clarify Qwest’s LNP process and to address any discrepancies in the information provided by their Denver Interconnect Center on August 15th, August 17th, August 24th and August 31st to AT&T. Qwest’s Denver Interconnect Center stated on multiple conference calls (to AT&T Broadband and to LNS) that calendar days, instead of business days, would be counted in the LNP process. Discussions with Qwest at the October 17th Product and Process CMP meeting clarified that Qwest uses business days.

AT&T understands this to mean that if a port is scheduled on a Friday or Saturday, Qwest will not jeopardize the end customer by closing the LSR or removing the switch translation any earlier than the next business day. Next business day is defined as the following Monday at 11:59 p.m. AT&T wants to clarify that holidays do not constitute a Qwest business day. Therefore, Friday, Saturday or Sunday ports would not be disconnected out of the switch until the following Tuesday at 11:59 p.m. if Monday is a designated holiday.

Qwest states that their Interconnect Centers have been advised and are aware of this process. The process states that the ten (10) digit unconditional trigger and switch translations associated with the end user customer’s telephone number will not be removed, nor will Qwest disconnect the customer’s billing and account information, until 11:59p.m. (local time) of the next business day after the due date.

AT&T interprets this to mean Qwest has provided documentation and training to the typists at Sierra Vista, Phoenix, and Duluth Centers, both Interconnect Service Centers, the RCMAC center and any additional Qwest centers directly related to the LNP process. AT&T Broadband will reference Qwest’s letter dated October 29, 2001 to restore loss of dial tone when it is a direct result of non-adherence to Qwest’s LNP process by any Qwest employee of these centers. AT&T further expects the duty supervisors to be well versed in this process and provide consistent action and information based on this process.

Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes

Friday, September 21st, 2001 Alignment/Clarification Meeting

Donna Osborne-Miller, dosborne@att.com,AT&T Terry Bahner, tbahner@att.com, AT&T Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Linda Miles, llmiles@qwest.com, Qwest Russ Urevig, rurevig@qwest.com, Qwest Joan Wells, jmwell2@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest Ric Martin, rhmart2@qwest.com, Qwest

Introduction of Attendees Donna, Terry, Kathy, Linda, Russ, Joan, Kate, and Ric Review Requested (Description of) Change Clarify process to complete LSRS the day after due date. Confirm Areas & Products Impacted Areas: Ordering and Billing Products: LNP Confirm Right Personnel Involved Joan is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. After the clarification meeting, it was determined that Linda and Russ will not need to be involved in this CR. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Identify/Confirm CLEC’s Expectation AT&T has asked Qwest to clarify the process for completing LSRS the day after due date. Per AT&T, “Qwest notified the CLEC community LSRS would complete orders day after at 11:59 p.m. of install date to coincide with disconnect in switch. Qwest escalation center is stating that orders can start closing as early as 3 p.m. with the possibility of closing even sooner with disconnect to follow. Interconnect has stated that Qwest determines that there is a large volume of orders to close, they can decide a random time to start the process. AT&T would like to understand why this time frame fluctuates if the closing of these orders causes the disconnect in the switch to shift to an earlier time. AT&T is requesting a flow chart or documentation explaining and listing the backend systems for this process.” Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Joan will clarify this process via a flowchart and written formal response draft. She will forward this documentation to Kate by the morning of 10/5/01. Kate will review and forward this information to Michael Belt to store in the CR database by 10/8/01 for CLEC review. This information can then be reviewed and discussed by the CLEC Community at the October CMP Meeting. Donna and Terry can view this information on the CR database and this CR can then be reviewed and discussed by the CLEC Community at the October CMP Meeting. Corrections/updates can then be made at that time.


CenturyLink Response

Wholesale Product/Process Final Response

November 6, 2001

Ms. Terry Bahner Ms. Donna Osborne-Miller AT&T Communications

This letter is in response to CLEC Change Request PCR090401-4, dated September 4th, 2001, title of change: Clarify Qwest’s process on completing LSR’s day after due date. This Change Request pertains to the implementation of the new LNP process involving stand alone LNP port out service order requests.

Description of Change as noted in CR: QWEST notified CLEC community LSRS would complete orders day after at 11:59 pm of install date to coincide with disconnects in switch.. Qwest escalation center is stating that orders can start closing as early as 3pm with the possibility of closing even sooner with disconnect to follow. Interconnect has stated that if Qwest determines that there is a large volume of orders to close, they can decide a random time to start the process. AT&T would like to understand why this time frame fluctuates if the closing of these orders causes the disconnect in the switch to shift to an earlier time. AT& T is requesting a flow chart or documentation explaining and listing the backend systems for this process.

Implementation of this Qwest business process change was included in the IMA 8.0 release and was deployed effective August 20th, 2001.

The change is as stated: The ten (10) digit unconditional trigger and switch translations associated with the end user customer’s telephone number will not be removed, nor will Qwest disconnect the customer’s billing and account information, until 11:59p.m. (local time) of the next business day after the due date. Internal Qwest systems have been adjusted to accommodate this process change.

* Order completion and disconnect of translation’s will not occur prior to 11:59 p.m. the next business day following the due date.

* The subscription date to ASMS is sent to match the CLEC requested due date as available per the standard interval guide.

* The FOC is sent and matches the ASMS subscription date requested by the CLEC as available per the standard interval guide.

* An effective billing date to discontinue account billing is added to the order to match the actual port subscription date as requested by the CLEC and as available per the standard interval guide.

* Additional notification and a reminder of this current process was sent to the Interconnect Center’s through an internal communicator dated 10/29/01. The title was “Qwest response to CLEC questions concerning the current LNP Port Out process of holding switch translations and order completion until the next business day at 11:59pm.” * The process agreement is as stated: The ten (10) digit unconditional trigger and switch translations associated with the end user customer’s telephone number will not be removed, nor will Qwest disconnect the customer’s billing and account information, until 11:59p.m. (local time) of the next business day after the due date.

For due date changes or cancellation’s on existing LSR’s the following process should be followed:

Due Date Changes * You must notify Qwest via LSR supplement or notification to the ISC if you require a DD change for your port activity * Notifications of DD changes via a LSR supplement should be made as soon as possible on the DD and prior to 8:00 PM Mountain Time. * Late notification of DD changes will require that you call the ISC prior to 12:00 noon on the day after the DD (in the end-users' time zone) and issue a LSR supplement via IMA or IIS to confirm the request. If the port due date falls on a Saturday, the CLEC should notify the ISC no later than the following Monday by noon of the DD change. * Late DD change notifications after 12:00 noon the day after the DD, will require you to contact the Call Center Representative at 888-796-9087 to initiate an escalation ticket for these late changes. The CLEC should also issue a LSR supplement via IMA or IIS to confirm the request. The CLEC should also issue a LSR supplement via IMA or IIS to confirm the request.

Cancels * You must notify Qwest via LSR supplement or notification to the ISC if you require a cancel of the port activity. ? Notifications of DD cancels via a LSR supplement should be made as soon as possible on the DD and prior to 8:00 PM Mountain Time. * Late notification of DD cancels will require that you call the ISC prior to 12:00 noon on the day after the DD (in the end-users time zone) and issue a LSR supplement via IMA or IIS to confirm the request. . If the port due date falls on a Saturday, the CLEC should notify Qwest no later than the following Monday by noon of the cancellation. * Late cancel notifications after 12:00 noon the day after the DD will require you to contact the Call Center Representative at 888-796-9087 to initiate an escalation ticket for these late cancels. The CLEC should also issue a LSR supplement via IMA or IIS to confirm the request.

Qwest Interconnect Service Center hours of operation to support the functions described above are: 6 AM to 8 PM Mountain Time, Monday-Friday 7 AM to 5 PM Mountain Time on Saturday

With the implementation of this new process, the CLEC is still responsible for notifying Qwest if they are unable to meet their requested port due date. Service order completion and disconnect of switch translation’s are not scheduled to occur anytime prior to the 11:59 p.m. time frame the next business day following the due date. However, the port subscription message was sent for the initial CLEC desired due date and changes or cancellation’s must occur as outlined above or as noted in the supplement information listed in the Product catalog.

Sincerely,

Joan Wells Process Manager Local Number Portability

CC: Margaret Bumgarner Lorna Dubose Constance Overly Kate Spry


Open Product/Process CR PC110201-2 Detail

 
Title: Partial turn up of circuits on multiple related LSRs
CR Number Current Status
Date
Area Impacted Products Impacted

PC110201-2 Completed
2/20/2002
Ordering, Test and Turn-up of facilities Unbundled Loop, UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Osborne, Deb
Director:
CR PM:

Description Of Change

CLECs have the ability to submit multiple circuits on an LSR or multiple LSRs and relate them to each other. However, if circuits are related by same or related orders, Qwest testers require CLECs to complete or sup all LSRs that are related if a few circuits fail testing. AT&T wants Qwest to allow CLECs to complete LSRs that have circuits that test good and to sup out LSRs with circuits that fail testing. An example of this problem of related orders is with a hospital SEAP0104650. 7 of 10 circuits tested good. Because 3 circuits on related LSRs failed testing, Qwest’s policy stated the work done on the 7 good circuits would have to be worked back and all 10 LSRs needed to be sup’d for a new due date. Qwest’s policy to do all or none causes excess re-work and problems associated with working-back circuits to Qwest.

Modification - 11/27-01:

The CR will focus on accepting partial LSRs that are related to multiple LSRs and will also evaluate any differences on managed cuts versus coordinated cuts.


Status History

11/02/01 - CR received by Donna Osborne - Miller of AT&T

11/02/01 - CR status updated to Submitted

11/02/01 - Updated CR sent to Donna Osborne-Miller of AT&T

11/12/01 - Left voice messages for Donna and Jonathon at AT&T to schedule clarification meeting.

11/14/01 - CMP Meeting - AT&T presented its CR.

11/19/01 - Clarification Meeting scheduled with AT&T for 11/27..

11/27/01 - Conducted Clarification meeting with AT&T.

11/27/01 - Issued Clarification Meeting Minutes to AT&T.

12/04/01 - Issued e-mail to AT&T requesting additional information.

12/12/01 - CMP Meeting - CLEC Clarification was made on the CR. Qwest advised that its current practice allows what the CR is requesting. Qwest to formalize its response. Status of CR changed to Evaluation.

01/08/02 - Issued Qwest's Draft Response dated December 27, 2001 to AT&T and posted to dBase.

01/16/02 - CMP meeting - Qwest presented its Draft Response. It was agreed that the CR could move into CLEC Test.

01/21/02 - Issued Qwest's Response dated December 27, 2001 to CLEC Community.

02/20/02 - CMP Meeting - It was agreed that the CR could be Closed. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/20/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

Subject: CR PC110201-2 Date: Tue, 04 Dec 2001 13:18:28 -0700 From: Richard Martin Organization: Qwest Communications International, Inc. To: Jonathan Spangler CC: Mark Coyne , Deborah Osborne

Jonathan,

This e-mail is a follow-up to the voice mail I left yesterday. In the voice mail I indicated that we were still looking to get the names of the individuals that provided the direction referenced in our 11/27 Clarification Meeting. In addition, I advised that it appears that the PON referenced in the CR, SEAP0104650, is not in Qwest's system. Could you please double check the PON number or provide the related LSRs.

Thanks for your cooperation,

Ric

CLEC Change Request Clarification Meeting

Date: November 27, 2001, 9:30 (MT) Place: Conference Call Conference Call-In No.: 877-542-1728 CR No.: PC110201-2, Partial Turn-up of circuits on multiple related LSRs

Attendees: Ric Martin, Qwest Mark Coyne, Qwest Connie Winston, Qwest Jonathan Spangler, AT&T Horacce Fluker, AT&T Shelia Dizon-Crun, AT&T

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Jonathan Spangler provided two (2) examples where they were advised that they had to SUPP all LSRs when partial LSRs or Circuits were completed.

First – AT&T had issued 10 separate LSRs that were related to one another and 7 of the 10 were good circuits. Qwest personnel, including supervision and after the initial escalation, advised AT&T that they would only do all 10. Second – AT&T had several circuits on one LSR. One circuit was a DSL TN and they couldn’t port all TNs. This was resolved by AT&T issuing a SUPP to remove the DSL TN.

It was agreed that this CR would only focus on the first example and AT&T would evaluate if they wanted to issue a Change Request on the second example. In addition to evaluation the first example, AT&T wanted Qwest to advise of any differences for handling managed cuts versus coordinated cuts. AT&T advised that they wanted, in the first example, to be able to complete the 7 LSRs and SUPP out the other 3. Connie Overly advised that she believed that was Qwest’s policy. Jonathan advised that this was contrary to what AT&T was told in their Quality Service Manager call. In addition Qwest’s associate, supervisor and escalation manager advised otherwise. Qwest is to confirm the policy. Qwest requested AT&T to provide the names of the individuals that center.

Confirm Areas & Products Impacted The products listed on the CR are the products AT&T want to ensure is covered. . Confirm Right Personnel Involved Qwest had the appropriate SMEs involved.

Identify/Confirm CLEC’s Expectation AT&T wanted clarification on Qwest’s policy and documentation of the policy.

Identify any Dependent Systems Change Requests There is no corresponding System CR

Establish Action Plan (Resolution Time Frame) AT&T will advise of the Qwest personnel involved in the example. Qwest will confirm its policy and provide documentation Qwest will provide appropriate communication of correct policy. The CR will be Clarified with the CLECs at December’s CMP and Qwest will advise on the above.

-


CenturyLink Response

Wholesale Product Marketing

December 27, 2001

Jonathon Spangler ILEC Relations Manager AT&T

This letter is being sent in response to CLEC Change Request Form # PC110201-2. PC110201-2 pertains to a request to change the due date on one or more LSRs that were previously submitted in a group of related PONs. This response addresses the current IMA process for changing the due date on one or more LSRs within a group of related PONs allowing the remaining PONs to be processed.

IMA Process:

A supplemental LSR should be issued for the PON requiring the due date change. The value entered in LSOG field 25 SUP should be “3” because there will be other changes on the LSR in addition to the due date change.

The value entered in LSOG field 51 RPON should be blank to indicate that this PON is no longer part of a related group.

The value of LSOG field 14 DDD should contain the new desired due date.

The value of LSOG field 10 PGofPageof should follow the LSOG business rules for the product specified on the LSR.

The LSOG business rules are documented on the Qwest website http://www.qwest.com/wholesale/clecs/lsog.html.

Sincerely, Deborah Osborne Process Specialist


Open Product/Process CR PC110201-1 Detail

 
Title: Qwest Rate Center Maps
CR Number Current Status
Date
Area Impacted Products Impacted

PC110201-1 Completed
3/20/2002
LNP
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Saunders, Craig
Director:
CR PM:

Description Of Change

Qwest determines the Rate Centers. AT&T needs to mirror the Rate Center areas for residential LNP. What is the process for obtaining Rate Center Maps from Qwest?


Status History

11/01/01 - CR received from Sharon Van Meter of AT&T

11/02/01 - CR status updated to Submitted

11/02/01 - Updated CR sent to Sharon Van Meter of AT&T

11/14/01 - CMP Meeting - AT&T presented its CR in open forum. Qwest would expand CR to include CLLI codes, Eschelon requested DA maps also be included. AT&T asked that the clarification meeting be held with all CLEC community.

11/16/01 - Held Clarification Meeting with AT&T, Eschelon and Worldcom (see meeting minutes and Eschelon e-mail).

12/12/01 - CMP Meeting: AT&T presented this CR, Qwest SME in attendance. Discussion on the level of detail and the location needed for each map. Status changed to Evaluation. Qwest will present their draft response at the January CMP meeting.

12/18/01 - Requested example rate map from LeiLani Hines (Worldcom). She posted to Qwest via mail the same day.

12/21/01 - Map received by Qwest. Craig Saunders has copy.

01/04/02 - E-mail from AT&T requesting map examples

01/04/02 - E-mail response to AT&T

01/04/02 - E-mail from Eschelon requesting additional information on Qwest response content

01/09/02 - E-mail from Qwest asking for AT&T address to forward map example.

01/09/02 - E-mail from Qwest responding to Eschelon e-mail on Qwest response content

01/10/02 - Draft response dated 01/10/02 posted to the CMP database and issued to AT&T. Status changed to "Presented"

01/16/02 - January CMP meeting. Qwest presented their response. Eschelon asked if they will be able to use these maps for predicting rates for their lines. Qwest took an action to respond to this request at the February CMP meeting. Status will remain in "Presented" status.

01/18/02 - E-mail with AT&T mailing address for map example

01/18/02 - Clarification e-mail from Eschelon

01/18/02 - Map request e-mail from Eschelon

02/20/02 - February CMP meeting: Qwest will have the rate center maps on the wholesale web site by the end of this week. There will also be a web form to enable CLECs to order maps to a street level detail. CR status changed to "Development" until CLECs are notified of URLs. CR status will then change to CLEC Test status. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

03/01/02 - Formal response dated 03/01/02 posted to the CMP database. Response was updated to include the URL for rate center maps

03/01/02 - Formal response dated 03/01/02 issued to CLECs. Notification number: CMPR.03.01.02.F.01233.CR_Responses

03/04/02 - Formal response dated 03/01/02 posted to web in the Product & Process Interactive report URL: http://qwest.com/wholesale/cmp/changerequest.html CR Status changed to "CLEC Test"

03/20/02 - March CMP Meeting: CLECs agreed to close CR. CR Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

01/18/02 Map request e-mail from Eschelon

Subject: RE: Clarification on Rate Maps/document to determine zones for lo op rates Date: Fri, 18 Jan 2002 17:13:09 -0600 From: "Clauson, Karen L." To: Todd Mead CC: Kathleen Stichter , "Morrisette, Garth M." , Susan Travis Todd: Garth has indicated that we also need the rate center maps as well. Please send copies to Kathy Stichter. Thanks.

01/18/02 Clarification e-mail from Eschelon

Subject: RE: Clarification on Rate Maps/document to determine zones for lo op rates Date: Fri, 18 Jan 2002 17:12:04 -0600 From: "Clauson, Karen L." To: Todd Mead CC: Kathleen Stichter , "Morrisette, Garth M." , Susan Travis I will be in Denver for the CMP Re-design meeting on Tuesday-Thursday. We can discuss on a break, if you would like. Otherwise, you can arrange a call with Kathy Stichter and Garth Morrisette while I am out, if Kathy can find a suitable time for you. Essentially, we are simply asking for the documentation that allows us to determine where our lines (and future lines) fall within the zones that have been established for geographically deaveraged loop rates. For example, a newspaper article in Denver said that Zone 1 (the most dense zone) covered most of the city of Denver. What are the boundaries of that Zone? Do you have a list of wire centers/CLLI code by zone (where the zone is defined by wire centers) or a map that shows these zones? We need this information for AZ and CO. I am copying Susan Travis of WCOM, because she had this same request, and she may have other states.

01/18/02 E-mail with AT&T mailing address

Subject: RE: Your Address Date: Fri, 18 Jan 2002 12:50:10 -0500 From: "Van Meter, Sharon K, NCAM" To: "Todd Mead" CC: "Saunders, Craig" Todd, Thanks for the reminder. 1875 Lawrence St. Room 8-15 Denver, CO 80205 Thanks for your help. Sharon Van Meter Western Region LSAM 303-298-6041 303-540-1637 (pager)

--Original Message-- From: Todd Mead [mailto:tmead@qwest.com] Sent: Friday, January 18, 2002 10:42 AM To: Van Meter, Sharon K, NCAM Cc: Saunders, Craig Subject: Your Address Sharon, Please send me you mailing address and we will send you a copy of the map you requested. Thanks Todd

01/09/02 E-mail from Qwest responding to Eschelon e-mail on Qwest response content

Subject: Re: Qwest Rate Center Maps Date: Wed, 09 Jan 2002 16:09:55 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: "Clauson, Karen L." CC: "Van Meter, Sharon K, NCAM" , jmschu4@qwest.com, susan.a.travis@wcom.com, "Saunders, Craig" , "Stichter, Kathleen L." Karen, Yes! The Qwest response presented at next week's CMP meeting will encompass the information you refer to below. Thanks Todd

01/09/02 E-mail from Qwest asking for AT&T address to forward map example.

Subject: Re: Qwest Rate Center Maps Date: Wed, 09 Jan 2002 16:07:41 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: "Van Meter, Sharon K, NCAM" CC: jmschu4@qwest.com, susan.a.travis@wcom.com, klclauson@eschelon.com, "Saunders, Craig" Sharon, The map the Qwest individual referred to in the CMP meeting is the same as the example Worldcom sent us. Sharon, if you can send me your address I will make sure a copy is sent to you for your review. Thanks Todd

01/04/02 E-mail from Eschelon requesting additional information on Qwest response content

Subject: RE: Qwest Rate Center Maps Date: Fri, 4 Jan 2002 11:26:00 -0600 From: "Clauson, Karen L." To: Todd Mead , "Van Meter, Sharon K, NCAM" CC: jmschu4@qwest.com, susan.a.travis@wcom.com, klclauson@eschelon.com, "Saunders, Craig" , "Stichter, Kathleen L." Todd: Thanks for the helpful response. Since Sharon asked specifically about the rate center maps, I wasn't sure that your response below deals with the Distribution Area (DA) maps requested by Eschelon. Will we be getting the DA maps at the January meeting? Also, at the meeting in December, we discussed whether the CLECs were actually requesting the correct items to meet their objectives (e.g., being able to identify customers in zones for geographically deaveraged rates). I believe this caem up because Qwest said that it didn't know if it had maps of the type requested. If not, then Qwest must look at something else to make these determinations. We asked that, if we had not requested the documentation used by Qwest for this purpose, that such documentation also be produced. Have you determined yet whether Qwest has different documents/maps and, if so, will that be provided at the January meeting? Thanks, Karen

01/04/02 E-mail response to AT&T

From: Todd Mead [SMTP:tmead@qwest.com] Sent: Friday, January 04, 2002 11:14 AM To: Van Meter, Sharon K, NCAM Cc: jmschu4@qwest.com; susan.a.travis@wcom.com; klclauson@eschelon.com; Saunders, Craig Subject: Re: Qwest Rate Center Maps Sharon, Thanks for your e-mail. At the December CMP meeting, we had a general clarification on this CR where you presented the business reasons for submitting this CR and then the Qwest SME's asked you several questions pertaining to the exact nature of information you were after with these rate center maps. The following are notes I documented from the December CMP clarification meeting: - What states you wanted maps for (Washington, Utah, Colorado, Oregon, Minnesota, Arizona & New Mexico) - What level of detail (you want to be able to see what rate center a specific address is located in) - What format you are after (CLECs prefer electronic, however hard copy would do) - Whether you wanted to only see major metro areas i.e.. Denver, Aurora, Smokey Hills etc. CLECs agreed to this - Eschelon wanted to know if these maps would show how each customer is being served i.e. RSU (Qwest responded they would not and Eschelon responded that they may submit a separate CR). - Worldcom wanted to know if the maps show the CILLI detail (they had some examples from previous USWest maps). We have since contacted LeiLani and she has forwarded a copy of these old maps to the Qwest SME to review to help their response preparation. - You also want the response to include the process for getting these maps updated At the January CMP meeting (01/16/02) Qwest will present their response to your CR. The Qwest team is currently working on this response and I will e-mail it to you (plus Eschelon and Worldcom) as soon as I receive it from the Qwest SME. The response will also be posted to the CMP database and published on the web no later than next Friday (01/11/02). If I have missed something here, I would be more than happy to discuss this with you. You can call me anytime today to discuss this. Regards Todd

01/04/02 E-mail from AT&T requesting map examples

Subject: Qwest Rate Center Maps Date: Fri, 4 Jan 2002 10:49:43 -0500 From: "Van Meter, Sharon K, NCAM" To: CC: , , Todd, I haven't heard anything about the deliver of the Rate Center Maps. It was my understanding that you would contact me and deliver some maps for my review. Please advise. Sharon Van Meter Western Region LSAM 303-298-6041 303-540-1637 (pager)

12/18/01 e-mail from Worldcom to Qwest

Todd, Sure, I will put one in the mail today. LeiLani Hines Worldcom Carrier Management

12/18/01 e-mail from Qwest to Worldcom

Leilani, The Qwest SME would like to see the copy of the map you have. Could you please send him one? Thanks, Todd

> From: Stichter, Kathleen L. > Sent: Friday, November 16, 2001 3:18 PM > To: 'mbelt@qwest.com' > Subject: PC110201-1 > > Mike, > Qwest has a web site http://www.qwest.com/iconn/ that a CLEC can go to and > click on Outside Plant Jobs Greater than $100K to get information on the > build jobs Qwest is planning. Once at this web page the details Qwest > gives are: > State, WireCenter, Job #, Fiber/Cooper, Quantity, Location i.e. DA/CLLI, > Ready for Service and Completion Date. The information populated in the > Location field is either CLLI or DA (Distribution Area). The DA data is a > number i.e. 310211. This number, for the distribution, means nothing to > Eschelon without a map detailing the bounderies down to street level > detail of the specific distribution area. > Thanks > > Kathy Stichter > ILEC Relations Manager > Eschelon Telecom Inc

3:00 p.m. (MDT) / Thursday 16th Nov 2001 Clarification Meeting Conference Call

Attendees: Sharon Van Meter / AT&T Matt Kruzic / Qwest Jacob Barlow / Qwest Jan Attebarry / Qwest Craig Saunders / Qwest Mary Anderson / Qwest Michael Belt / Qwest Kathy Stichter / Eschelon (called later) Tom Dixon / Worldcom (called later)

Review Requested (Description of) Change: AT&T – Qwest Rate Center maps to be public information to the CLEC Community Eschelon & Worldcom would like the DA and CLLI Maps also included with this CR.

Products Impacted - LNP

Identify/Confirm CLEC’s Expectation - Yes the expectations of the CR are understood, need to clarify the issue of Proprietry Qwest information.


CenturyLink Response

March 1, 2002

Sharon Van Meter Manager AT&T 1875 Lawrence St. Denver, CO 80205

SUBJECT: Qwest’s Change Request Response - CR # PC110201-1 Qwest Rate Center Maps

REQUEST: Qwest determines the Rate Centers. AT&T needs to mirror the Rate Center areas for residential LNP. What is the process for obtaining Rate Center Maps from Qwest?

Additional clarifications/requests: Requested maps at a street level detail. Requested maps for MSA’s in Arizona, Colorado, Washington, Utah, Oregon, Minnesota, & New Mexico Prefer electronic, however paper will do. Requested maps at a level to determine DA areas. Requested maps at a CLLI level detail. Requested a process to update maps.

RESPONSE: Qwest has provided, on the Qwest Wholesale web site, the same rate center maps that Qwest uses and updates on a quarterly basis. The URL is:

www.qwest.com/wholesale/network/ratecentermaps.html

Qwest does not solely rely upon rate center maps to determine number portability. Qwest, as well as other companies, relies upon the Local Exchange Routing Guide (LERG) as the official guide to determine the portability of a number. Qwest determines whether a number is available for porting by looking at the customers switch information, both from and to, which reflects the serving rate center. As determined by the FCC, Qwest does not permit the porting of the numbers between two different rate centers.

Currently the Rate Center maps used by Qwest and provided on the wholesale website do not have the capability to provide wire center street level detail. Maps of DA’s are available through the Qwest Wholesale web site by following the process outlined under the URL:

www.qwest.com/wholesale/pcat/remotecollocation.html

Requesting multiple DA’s in a particular wire center will enable CLEC’s to ascertain the description of the wire center boundary.

In regard to the request for maps where Qwest plans fiber and copper jobs greater than $100,000, Qwest has plot maps that are available for review as outlined in SGAT section 10.8.2.4. Qwest agrees to provide CLEC access to relevant plats upon receiving a bona fide request for such information as stated in the SGAT.

Sincerely,

Craig Saunders Staff Advocate Policy & Law Qwest

CC: Barry Orrel, Director Legal Issues, Qwest Jim Eitel, Director Legal Issues, Qwest Lydia Eiguren, Senior Director Business Development, Qwest John Hayat, Staff Advocate Policy & Law, Qwest Mary Retka, Director Legal Issues, Qwest


Open Product/Process CR PC102601-1 Detail

 
Title: RSID/ZCID assignment for UNE P. (reference Systems CR # SCR012302 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC102601-1 Completed
1/16/2002
Billing Unbundled Loop, UNE-P
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner: Zimmerman, Alan
Director:
CR PM:

Description Of Change

Currently Qwest assigns only one RSID/ZCID per company. RSID/ZCID is an indicator that drives the daily usage files for all products within a CLEC. AT&T has multiple usage products within Qwest’s system. AT&T has a need to receive separated Meet Point/IXC usage files by product. Qwest is currently sending separate usage files to several locations by product. Due to RSID/ZCID assignment, Qwest will send duplicate files of the same data to two locations. For AT&T, this creates duplicate files and unnecessary records that AT&T is not able to eliminate. AT&T receives separate files from all other ILECs, and it appears that the RSID/ZCID is driving this concern. If Qwest will assign a new RSID/ZCID for AT&T business UNE-P Meet Point/IXC records which would be transmitted separately from the MEET Point/IXC currently going to Statton Island. Consequently, AT&T requests that Qwest assign a new RSID/ZCID specifically for AT&T UNE-P business products.


Status History

10/25/01 - CR Received from Carla Dickinson Pardee AT&T

10/26/01 - CR status changed to Submitted

10/26/01 - Updated CR sent to Carla Dickinson Pardee of AT&T

11/09/01 - Contacted Carla Dickinson from AT&T to schedule Clarification Meeting. She is on vacation from 11/9/01 - 11/19/01.

11/12/01 - Went ahead and tentatively scheduled a Clarification Meeting for 11/20/01 and left voice message for Carla to confirm time is okay.

11/14/01 - CMP Meeting - AT&T Presented its CR.

11/20/01 - Qwest rescheduled the clarification meeting for 11/27/01.

11/27/01 - Conducted Clarification Meeting with AT&T.

11/30/01 - Issued Clarification Meeting Minutes to AT&T.

12/03/01 - Issued revised Clarification Meeting Minutes to AT&T.

12/03/01 - AT&T, Carla Dickinson-Pardee advised that the meeting minutes were correct.

12/12/01 - CMP Meeting - CLEC clarification on the CR was made. Qwest advised that a large Systems CR would need to be developed. Qwest received input from AT&T that they would need 1 new RCID/ZCID now and more in the future. Qwest explained the difficulties with duplicating the various rates (USOCs) for each RCID/ZCID. To manually do this would create potential errors. Qwest to review options. CR status is changed to Evaluation.

01/08/02 - Issued Qwest's Draft Response dated December 28, 2001 to AT&T and posted to dBase.

01/09/02 - AT&T Acknowledged Qwest's response and provided preliminary requirements for the Systems Change Request.

01/16/02 - CMP Meeting - Qwest presented its Draft Response. Qwest will work with AT&T to issue a Systems CR on their behalf. It was agreed that the CR could be closed and a Systems CR issued with the Systems CR listed in the Title Section.

01/21/02 - Issued Qwest's Response dated December 28, 2001 to CLEC Community.

01/22/02 - Issued Draft Systems CR to AT&T and received their concurrence.

01/23/02 - Submitted Systems CR on behalf of AT&T.

01/23/02 - Responded to AT&T via e-mail that the products to be covered under the Systems CR could be defined at the Systems CR Clarification meeting.


Project Meetings

Subject: RE: Systems CR for PC102601-1 Date: Tue, 22 Jan 2002 16:17:16 -0500 From: "Pardee, Carla D, NCAM" To: "Richard Martin" , "Alan Zimmerman"

Ric, thanks, it looks good. My only question is which products it would impact. Although I only checked UNE-P, it seems as though this could/would impact all products across the board. Is that true? Thank you.

Carla Dickinson Pardee Manager - LSAM (303) 298-6101

Subject: RE: CR PC102601-1 Draft Response Date: Wed, 9 Jan 2002 09:49:06 -0500 From: "Pardee, Carla D, NCAM" To: "Richard Martin" CC: "Alan Zimmerman" , "Faber, Vicki L, BNSVC" , "Boykin, Timothy (Tim), NCAM" , "Spangler, Jonathan F, NCAM" , "Bahner, Teresa L (Terry), NCAM" , "Rea, Ervin E, NCAM" , "Smith, Troy V"

Richard and Alan:

Thank you for your response re: AT&T's change request for additional assignments of RSID/ZCID. Since Qwest would be faced with several issues if multiple RSID/ZCID values are assigned, AT&T would like to pursue a Systems CR to create another mechanism for CLECs to segment customers for loss/completion reports and DUF files, etc. As explained in the initial CR, AT&T has several business units that need separate transmission of certain files. AT&T requested RSID/ZCID values because AT&T understood that RSID/ZCID values drove transmission of these various files. AT&T is open to Qwest creating some other value for driving these various data files.

Thank you for your response. I look forward to discussing and resolving this matter further in the CMP forum.

Carla Dickinson Pardee Manager - LSAM (303) 298-6101

CLEC Change Request Clarification Meeting

November 27, 2001, 2:00 pm (MT) Conference Call

866-289-7092 PC102601-1, RCID/ZCID assignment for UNE-P

Attendees: Ric Martin, Qwest Mike Marshall, Qwest Mark Early, Qwest Joni Dokken, Qwest Carl Sear, Qwest Carla Dickinson-Pardee, AT&T

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change Carla advised that with the growth of AT&T’s different businesses they cannot split off the associated products in their DUF Files. They would like to have a separate RSID/ZCID number assigned to their various business products. Carla indicated that other ILECs use OCNs for assignment of the business products. Qwest advised that the RSID/ZCID number was the equivalent of the ACNA. Currently the ACNAs follow Qwest guidelines for their use. Qwest explained that the usage records on the DUF come out per EMI OBF guidelines. Within the EMI OBF guidelines are different record types that identify different types of calls and features, buth these call types and features are not packed separately on the DUF. Qwest further explained that within the DUF Files the category 01 and 10 records are sent in a separate pack from category 11 records, but both packs are sent on the same file. The files are created by ACNA. AT&T indicated that they would like to see the RSID/ZCID further broken down within the CAT 10 file. Qwest indicated that there could be a review to determine hotw to separate feeds for each transmission, but this would require with the billing system capabilities. Before any changes could be initiated, the issue would have to be discussed and agreed to through CMP.

Confirm Areas & Products Impacted The products listed on the CR are the products AT&T wants to ensure is covered. . Confirm Right Personnel Involved Qwest’s Owner will be revised to Alan Zimmerman. Carl Sear, Joni Dokken and Mike Marshall will also support Qwest’s evaluation. Alan is out of the office this week and Qwest will coordinate its evaluation when he returns.

Identify/Confirm CLEC’s Expectation AT&T would like to have the ability to identify the various UNE-P business products to reflect the billing to their various companies.

Identify any Dependent Systems Change Requests There is no corresponding System CR

Establish Action Plan (Resolution Time Frame) Qwest will evaluate various options. This CR will be clarified with the CLEC Community at the December CMP Meeting.


CenturyLink Response

Wholesale Service Delivery

December 28, 2001

Carla Dickinson Pardee LSAM Manager AT&T

This letter is in response to the CLEC Change Request Form #PC102601-1 regarding RSID/ZCID Assignment for UNE-P. Qwest would like to close this Product/Process CR and open a new Systems CR to properly consider the best way of meeting this business need.

Today, the assignment of an RSID/ZCID value drives a lot of business processes in Qwest. USOC rates are maintained for each RSID/ZCID, Loss/Completion reports are generated for each RSID/ZCID, separate bills are generated, security and authorizations are specific per RSID/ZCID, etc. To assign multiple RSID/ZCID values per CLEC would create potential issues with contract updates, authorizations, etc. Qwest would prefer to create another mechanism for CLECs to tell Qwest how to segment customers for purposes of Loss/Completion reports, Daily Usage Feeds and any other system interfaces CLECs desire to have segmented.

This new separation mechanism would need to be accomodated on the LSR and IMA, as well as the other systems involved. A Systems CR would be required to accomplish this. Qwest will open the Systems CR on AT&T’s behalf.

If you have any questions, feel free to e-mail me or call me. Happy New Year!

Sincerely,

Alan Zimmerman (303)896-8346 azimmer@qwest.com


Open Product/Process CR 5579296 Detail

 
Title: NPA NXX supplemental form submissions
CR Number Current Status
Date
Area Impacted Products Impacted

5579296 Withdrawn
7/10/2001
Ordering LIS, SS7, Switched Services
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: To Be Determined
Director:
CR PM:

Description Of Change

SGAT language states that the submission of the form is optional and “will never be required”. Translations refuses to complete routing of new trunks if the form is not submitted. Either the SGAT language must be changed or the form made optional.


Status History

6/06/01 – CR received by Ervin Rea of AT&T 6/07/01 – Status changed to New – to be evaluated 7/09/01 – Status changed to New – to be Clarified

7/10/01 – Clarification requested via email from AT&T (MR) 7/18/01 – Status changed to Canceled as per July CICMP Industry Team Meeting


Project Meetings


Open Product/Process CR PC090401-1 Detail

 
Title: Request for Qwest to separate daily usage files by separating category 01 and 010 from category 011. (reference Systems CR # SCR111901 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC090401-1 Completed
11/14/2001
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Zimmerman, Alan
Director:
CR PM: Thomte, Kit

Description Of Change

AT&T is requesting Qwest to separate daily usage files, separating Category 01 and 010 from category 011

Request for Qwest to separate daily usage files by separating category 01 and 010 from category 011. Categories 01 and 010 separate daily usage records for end users while category 011 tracks billing for other carriers. AT&T separates billing entities by these functions. AT&T believes that other carriers utilize this same process. AT&T believes would be more efficient if the daily usage files were separate in this manner.


Status History

08/30/01 - CR received from Donna Osborne-Miller of AT&T

09/04/01 - Status changed to New - To be reviewed

09/04./01 - Updated CR sent to Donna Osborne-Miller of AT&T

09/12/01 - Clarification meeting held with AT&T. AT&T to get CLEC community acceptance.

09/21/01 - ATT will not have opportunity to present at community meeting until 10/15/01

10/17/01 - CMP Meeting: Discussions with CLEC community conducted regarding CR. SBC indicated that they were receiving separate billing records for daily usage. Alan Zimmerman, Qwest to draft reply for next CMP (November 14, 2001). No change to "Current Status."

11/01/01 - Draft response issued

11/07/01 - Draft response updated to indicate if approved this will need to become a system CR

11/14/01 - CMP meeting it was agreed that this request can be closed. A system CR will be opened by Qwest to allow the work to be prioritized.

11/26/01 - Final response issued to CLECs


Project Meetings

09/12/01 - Clarification meeting on PCCR 090401-1. In attendance Carla Dickinson Pardee and Troy Smith from ATT. Alan Zimmerman and Kit Thomte from Qwest.

Alan indicated that he was familiar with this subject. He believed it had been submitted once before but did not have the support of the other CLECs at that time. Alan indicated that he thought some of the CLECs might see the need for this now.

Alan stated the issue: In the current environment two usage files containing the same data are sent to two locations. ATT would like to have the file containing message types 01 and 10 split out on one file. The other file should contain message type 11, to be distributed separately.

Carla indicated she would take this CR to the next community meeting to propose this change to other CLECs.


CenturyLink Response

November 6, 2001

This letter is in response to the CLEC Change Request Form #PC090401-1. This Change Request requests that the Daily Usage Feed (DUF) be split into two pieces - with local usage (generally Category 1 & 10 EMI records) on one file, and access usage (Category 11 records) on a separate file.

Today, both local usage and access usage is sent on a single DUF file for each CLEC. It is fairly straight-forward to separate this usage into two files. To do so requires some small programming changes, as well as some JCL and NDM/Connect: Direct changes for every CLEC that chooses to have their DUF split into two pieces. This would be a medium-sized effort. This CR will be moved to the Systems CMP process in order to prioritize this system work.

Qwest would implement this CR in such a way that those CLECs that wish to continue to receive their DUF file as one file (like today) would be able to continue with that implementation. Those that wish to receive two separate files would be able to do so, having those two files sent to two different destinations (assuming connections exist) or to the same destination as the CLEC desires.

Any CLEC who would like to have their DUF split in two as this CR requests may send an e-mail to me at azimmer@qwest.com to be included in the deployment of this functionality. If you have any questions, feel free to e-mail me or call me at the number below.

Sincerely,

Alan Zimmerman (303)896-8346


Open Product/Process CR PC090401-2 Detail

 
Title: UNE P to UNE L Bulk Conversion Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC090401-2 Completed
3/20/2002
N/A
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Urevig, Russell
Director:
CR PM:

Description Of Change

AT&T would like to establish an efficient process with Qwest to convert AT&T customers residing on the Qwest UNE-P platform to the Qwest UNE-L platform on a Bulk LSO basis.

The process would include a minimum of the following steps:

- CLEC will provide prior notification of intent to convert via a list (spreadsheet?) identifying the LSO and number of TNs

- CLEC will provide ONE LSR PER CUSTOMER LOCATION for conversion.

- Qwest will provide a SPOC for each LSO conversion on the same due date.

- Qwest will perform a Loop Qualification for each LSR.

- Qwest will provide Loop Qualification results to CLEC.

- CLEC will have option to make supplemental changes or cancel LSRs per results of loop qualification.

- CLEC will schedule conversion to begin on Due Date no earlier than 4:00 PM. All conversions within the LSO will be completed by 12:00 Midnight.

Time Intervals for conversions shall be monitored and shall conform to the existing performance standards set in the current Qwest hot cut agreement.


Status History

08/30/01 - CR Received from Carla Dickinson of AT&T

09/04/01 - Status changed to New - To be Reviewed

09/04/01 - Updated CR sent to Donna Osborne-Miller and Carla Dickinson of AT&T

09/17/01 - Clarification meeting held. With AT&T.

09/28/01 - Draft response posted to database.

10/17/01 - CMP Meeting: Qwest presented response. A separate meeting will be conducted with AT&T and Qwest to further address the response and future implementation. CLEC community agreed to the separate meeting with just AT&T in attendance. No change to "Current Status."

11/07/01 - Working with Qwest Project Management team to establish meeting.

11/14/01 - CMP Meeting it was agreed that all CLEC's needed to be invited to the session scheduled with AT&T for Friday Nov. 16th. As a result the meeting will be postponed until Nov. 26th or 30th. To accommodate the time that is required to notify all CLECs of the meeting. It was agreed that the CR would be placed into development status.

with AT&T

11/19/01 - Notification was sent to all CLECs regarding a meeting to discuss the two questions that came out of the Oct. CMP meeting

11/30/01 - Held meeting with AT&T regarding questions that came up during the CMP meeting in Oct. All CLECs were invited to the session11/30/01 - Held meeting with AT&T

12/12/01 - CMP Meeting - Qwest reviewed status of CR. Meeting 11/30 resolved all issues. Qwest's response on Appointment Scheduler needs to be finalized and will be discussed at the Systems Meeting. AT&T advised that if the response was acceptable, the CR could be placed into CLEC Test.

12/13/01 - Per Judy Schultz, AT&T, was satisfied with the presentation on Appointment Scheduler and the CR could be placed into CLEC Test.

12/28/01 - Qwest's formal response dated 9/28/01 issued to CLECs.

01/16/02 - Qwest provided an update on Appointment Scheduler and indicated that a special override will be used for out of hour cuts. AT&T requested that the CR remain in CLEC test until the presentation on Appointment Scheduler tomorrow at the Systems CMP Meeting.

01/29/02 - Received e-mail confirmation from AT&T that they would like the CR to remain in CLEC Test until they have gone through the IMA 9.0 training.

02/18/02 - Received e-mail from AT&T advising that the training on IMA 9.0 did not demonstrate the override capability of Appointment Scheduler. Qwest to investigate and advise.

02/20/02 - CMP Meeting - Qwest clarified the issue regarding Appointment Scheduler that the Override feature was included and will review with AT&T. The CR will remain in CLEC Test. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/20/02 - CMP Meeting - It was agreed that the CR could be closed.

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

November 30, 2001

Qwest held a community meeting with AT&T regarding two questions that came up during the October CMP meeting. Other CLECs were invited and several participated.

Jonathan Spangler from AT&T had inquired if the orders would go through the QCCC. Russ Urevig stepped through the process. In the process he identified that in fact the QCCC will be the point of contact for the coordinated after hours cut. Jonathan indicated he had received some push back when trying to schedule other projects.

The second question was regarding charges associated with the after hours cut. Russ explained that the normal after hours charges would apply.

Jonathan brought up an additional issue. He wanted to know what the impacts would be to these projects when the 9.0 IMA Release goes in and the CLECs are required to use Appointment Scheduler. Russ indicated he was not sure that these types of cuts were included in the 9.0 release for Appointment Scheduler. Qwest to follow up with system SME’s regarding the System Change Request.

-

09/17/01 - Introduction of Attendees Jonathan Spangler Carla Dickinson Pardee Russ Urevig Kit Thomte

Kit made introductions of people that were in attendance on the conference call Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} AT&T would like Qwest to develop a process that would allow for the conversion of customers residing on UNE P to UNE L. CLECs will identify specific TN’s within the CO that need to be converted. This would occur initially via a spreadsheet with LSR’s to follow. The spreadsheet would be used by Qwest to determine if the line actually could be converted. Prior to this the CLECs will use the raw loop pre qualification tool to verify TN’s of end users being converted. The CLECs want to minimize the amount of down time for the customers so the cuts should be performed between 4 PM and 12:00 Midnight. The volumes anticipated are not very precise yet. AT&T will provide more information as it becomes available. Russ inquired how AT&T would like to handle a scenario where the end user has multiple lines and only a portion of the lines are being migrated. Would they set up separate accounts?? Jonathan said he would need to check that out. Confirm Areas & Products Impacted {read from change request, modify if needed} At this point only 1FR’s will be submitted, at some point this process might include DSL.

Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} At this point Russ believes a person from network should be involved, this probably would be Deni Toye. A process person for UNE P should either be involved or review the process that is established. Eventually a SME from Retail should be aware of the process.

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)} Qwest needs to provide a process that will address this type of migration. This process needs to be put in place quickly with the worst case scenario being implementation in December of 2001.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} An existing CR would resolve the necessity of this CR. Russ Urevig agreed to identify this CR and let us know the status.

Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when) Russ will run this CR past his supervisor and the migration team that works on these issues. Russ should have a response by close of business on Monday Sept. 24th The detailed action plan will be provided after the session on the Sept. 24th.

09/12/01 - Susie Bliss is the Director 402-422-8006 Kit Thomte is the Project Mgr. 303 896-6776 Russ Urevig is the Owner 218 723-5800 Donna Osborne Miller gave me has provided the name of an individual to participate in a clarification meeting. Have not heard from the individual yet.


CenturyLink Response

September 28, 2001 Wholesale Product Marketing

Jonathan Spangler, LSAM Supervisor Donna Osborne-Miller, LSAM Manager AT&T Local Services

CC:Russ Urevig Susie Bliss Linda Miles Kit Thomte

This letter is in response to your CLEC Change Request Form PCCR090401-2 dated August 30, 2001.

Request:

AT&T would like to establish an efficient process with Qwest to convert AT&T customers residing on the Qwest UNE-P platform to the Qwest UNE-L platform on a Bulk LSO basis. The process would include a minimum of the following steps: CLEC will provide prior notification of intent to convert via a list (spreadsheet?) identifying the LSO and number of TNs CLEC will provide ONE LSR PER CUSTOMER LOCATION for conversion. Qwest will provide a SPOC for each LSO conversion on the same due date. Qwest will perform a Loop Qualification for each LSR. Qwest will provide Loop Qualification results to CLEC. CLEC will have option to make supplemental changes or cancel LSR's per results of loop qualification. CLEC will schedule conversion to begin on Due Date no earlier than 4:00 PM. All conversions within the LSO will be completed by 12:00 Midnight. Time Intervals for conversions shall be monitored and shall conform to the existing performance standards set in the current Qwest hot cut agreement

Qwest Response:

Conversion from UNE P to UNE L on a Bulk LSO basis can be handled as a project. The CLEC can contact their Account Service Manager to advise of the intent to Bulk convert on an LSO basis. By the conversion being handled as a project, the specifics such as due dates and individual tester, SPOC can be coordinated.

The CLEC can request raw loop data for an entire wire center. The RLD tool provides data in bulk format to the Co-Providers about loop make-up characteristics at the wire center level. The data includes CLLI code, load coil, bridged tap, wire gauge, cable and pair make-up, and similar information on a loop-by-loop basis.

There is a web-site maintained by Qwest where Co-Providers may access the RLD tool. To gain access to the web-site, Co-Providers must obtain a digital certificate from Qwest. The RLD tool is presented in an ASCII text file and can be downloaded to an Excel format or database built by the Co-Provider. The web-site address is http://ecom.uswest.com.

CLEC’s are encouraged to use the Pre-order function in IMA for Loop Qualifications. The results of the Loop Qualification are given to the CLEC. If an LSR is submitted and the loop does not qualify then the LSR would be rejected. A CLEC has the option to make supplemental changes or to cancel an LSR. For any due date requests outside the normal business hours appropriate charges would be billed.

Sincerely,

Russell Urevig Wholesale Service Delivery Process Team


Open Product/Process CR 5579794 Detail

 
Title: Request Qwest to deliver Verification report in Excel or Access format versus flat text file.
CR Number Current Status
Date
Area Impacted Products Impacted

5579794 Withdrawn
7/10/2001
TBD SS7, LIS, Switched Services
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: To Be Determined
Director:
CR PM:

Description Of Change

SGAT language states that the submission of the form is optional and "will never be required". Translations refuses to complete routing of new trunks if the form is not submitted. Either the SGAT language must be changed or the form made optional.


Status History

6/06/01 – CR received by Donna Osborne Miller of AT&T

New - to be clarified – to discuss in 6/20 CICMP Meeting 6/07/01 – Status changed to New – to be evaluated

7/09/01 – Status changed to New – to be Clarified

7/10/01 – Clarification requested via email from AT&T (MR) 7/18/01 – Status changed to Canceled as per July CICMP Industry Team Meeting – being tracked in Systems CICMP


Project Meetings


Open Product/Process CR 5548341 Detail

 
Title: Collocation end to end testing
CR Number Current Status
Date
Area Impacted Products Impacted

5548341 Completed
11/14/2001
Ordering Collocation
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Nelson, Steve
Director:
CR PM:

Description Of Change

AT&T would like the assistance of Qwest to do End to End testing from the AT&T collocation space through the MDF on Qwest’s side of the collocation space. In today’s world, Qwest tests the cabling on the Qwest side of the MDF. AT&T tests the cabling on the AT&T side of the MDF. This cabling represents DS3, DS1 and DS0 circuits. At this time, neither company is testing through the MDF to assure continuity from end to end. As AT&T actually starts ordering local services on the circuits, there is no assurance, without the end to end testing, that the service for the customer will actually work when it is turned up. If AT&T tries to turn up a customer and there is no continuity, the service for the customer is delayed, which causes poor customer service. AT&T is willing, and has offered, to pay Qwest for the time it takes to conduct these tests.

8-01 AT&T request add’l testing documents in regards to end to end testing.


Status History

05/11/01 - CR received by Donna Osborne Miller of AT&T

05/14/01 - CR logged and status changed to New – To be Evaluated

05/16/01 - Status changed to Reviewed – Under consideration

06/18/01 - Qwest will perform tests on the Loop from the horizontal side of the ICDF in the Qwest serving Central Offices to the Network Interface Device (NID) on the end user’s premises. In addition to this testing and the provisioning option chosen by AT&T, continuity testing is also performed when the collocation is turned over to AT&T for acceptance. AT&T certainly has the opportunity to do their own continuity testing of the terminations between their collocation space and the vertical side of the ICDF if the proper installation of these facilities (by AT&T) have come under question. . Qwest currently offers six provisioning options, three which give the CLEC the ability to have joint, cooperative testing to the Unbundled Loop from end to end. An AT&T technician being in the collocation space and a Qwest technician potentially being on the customer’s premises. This “piece” of cable between AT&T’s collocation space and the vertical side of the ICDF is the responsibility of AT&T and is paid for, by AT&T, as part of the collocation build out. With that stated, AT&T is responsible for the testing, maintenance and subsequent repair if they were to find trouble in this cable “piece”. Due to the above noted procedures which are followed when testing the Unbundled Loop and the fact that AT&T owns the piece of cable they are requesting Qwest to test, this CICMP request should be denied and AT&T should continue to be responsible for testing their network components (DP)

07/12/01 - Drafted Response sent to CICMP team via email (MR)

08/09/01 - Meeting scheduled to discuss Qwest’s response to CR regarding End to End testing for August 15th. Meeting announcement sent July 27th and a reminder sent 08/06/01. Meeting materials will be distributed prior to the meeting. (MR)

08/15/01 - CLEC CMP Meeting Product & Process CR 5548341. Steve Nelson has reviewed the issue and has set-up a meeting for today. Minutes will be issued after the meeting.

08/16/01 - Revised Process sent to AT&T, but not accepted

08/28/01 - Two add’l testing process documents provided to AT&T , CO DVA Process and HOT Cut Process. Send by Steve Nelson , Authored by Steven Hilleary.

08/31/01 - Sent memo to Sharon Van Meter requesting acceptance of Qwest Position papers as acceptable to AT&T.

09/04/01 - AT&T forwarded response for review by Dennis Mckeon

09/14/01 - AT&T acceptance response received from Sharon Van Meter for End to End testing.

09/19/01 - CMP Meeting - It wa agreed that the CR would move into CLEC Test. Qwest to combine 2 processes and issue a formal document by 10/05/01.

10/17/01 - CMP Meeting: Qwest issued process documentation in meeting. Formal document to be forwarded to CLEC community via e-mail. No "Current Status" change.

10/19/01 - Qwest document combining 2 processes entered into database.

10/23/01 - Qwest technical documentation transmitted to originating CLEC (AT&T).

11/14/01 - CMP Meeting - it was agreed that the CR could be "Closed."


Project Meetings

Subject: Re: CR 5548341 End to End Testing Date: Mon, 24 Sep 2001 09:04:36 -0700 From: Steve Nelson Lyman McKee wrote:

Steve, My understanding from the CMP 9-17-01 meeting is that you are going prepare a combined document for the end to end testing for distribution to the CLEC community.

That documentation will include the CO DVA Process and the Hot Cut Process as authored by Steven Hilleary and Jerry Jenson.

My notes indicate you were targeting 10-3-01 as having that completed and available for distribution to the CLEC community for their review. This CR would then be reviewed for comments and closure at the 10-17 CMP meeting.

I will be on vacation from 9-25-01 until 10-10-01.

Please forward response and documentation to Matt Rossi for distribution to the CLEC community.

Also forward a copy to mbelt@qwest.com for updating the CMP database.

Lyman McKee 303-896-5260


CenturyLink Response

Steve Hilleary Central Office Staff 402 Valley Ave. NW Puyallup, WA. 98371 shillea@uswest.com

Memorandum To: Central Office Directors

September 21, 2001

LX - - DVA (48 Hour) DIAL TONE TESTING REQUIREMENTS

There has been some confusion about the requirement, documented in the CO DVA PROCESS, for the CO to perform a Dial Tone test on DVA for Unbundled Dial Tone Capable Loops (NC Code LX - -). The requirements are:

1. ALL orders provisioning LX - - circuits MUST be checked for Dial Tone at the ICDF CFA. This includes both HOT CUT (Reuse of Facility) and Basic New (Vacant Facility) orders. 2. If the CO performs this test prior to the DVA and: A. Dial Tone is present the results must be logged in the order OSSLOG, using the OSSRMK screen in WFA-C. B. Dial Tone is NOT present the CO personnel MUST arrange to retest for Dial Tone on the DVA Critical Date by either: - Completing the DVA step partially and reloading the step to the DVA date. - Completing the DVA step and manually handling the order for retest (Manual holding bin) - Completing the DVA step and creating their own work request to retest on the DVA, loading this item to themselves or someone else. If someone else is loaded, the person loading the request must check to ensure that person is scheduled to work and that they know the item is loaded to them. 3. If the test is performed on the DVA and: A. Dial Tone is present the results must be logged in the order OSSLOG, using the OSSRMK screen in WFA-C. B. Dial Tone is NOT present, the testing CO personnel MUST contact the Implementer or Coordinator assigned to work the order (check the OSSOI screen in WFA-C). If none is assigned them must call the toll free number for the Design Service Center handling the order and give the trouble condition to the first implementer or coordinator they reach. Any Center personnel receiving this call SHOULD take the report and initiate Center activity for CLEC notification. This test failure MUST be logged in the OSSLOG. 4. If the time between DVA critical date and Due Date commitment time is greater that two (2) business days, the DSC/QCCC Implementer or Coordinator will determine this and hand off an SPL48 ticket requesting a Dial Tone retest two business day before commitment date. This should be the only time the CO would expect such a handoff.

The important points to remember are: - The CO is ultimately responsible for ensuring this Dial Tone test is peformed. - The CO must arrange their own retest if working DVA steps prior to DVA and NO DIAL TONE is found. - SPL48 tickets will only be generated by the DSC/QCCC under the situation stated in item (4.) above.

Please cascade this memo through your organizations. If you have any questions or comments, please contact me.

Cc: Central Office Senior Directors Deborah Heckart Fred Aesquivel


Open Product/Process CR 5582078 Detail

 
Title: Expanding Qwest Interconnect Center’s hours
CR Number Current Status
Date
Area Impacted Products Impacted

5582078 Completed
1/23/2006
Pre-Ordering All Products
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

Change Qwest’s Interconnect Center’s hours of support. Expand the window: 6am MST to 10pm MST Sunday through Saturday


Status History

06/06/01 - CR received from Donna Osborne Miller of AT&T

06/07/01 - Status changed to New – to be evaluated

07/09/01 - Reviewed under consideration

07/09/01 - LNP product team to discuss on 7/17/01 – will report status during the July 18th Monthly CICMP Meeting (LD)

08/09/01 - Response Pending resolution or concurrence from Qwest’s interconnect Service Center (LD)

08/15/01 - CLEC CMP Meeting Product & Process CR 5582078. Qwest is waiting on response Call volume from AT&T, which will be provided by 9/3.

08/27/01 - Alignment clarification meeting held; Terry Bahner indicated that forecast would be available on 9/4/01 (MJB)

09/04/01 - AT&T Forecast Data Provided

09/07/01 - Status update meeting conducted with AT&T; AT&T forecast data clarified (MJB)

09/19/01 - Status update provided at CMP (MJB)

09/20/01 - Draft Qwest response sent to AT&T (MJB)

10/17/01 - CMP Meeting: AT&T indicated CR should be in Deferred rather than Denied Status, and would like CR revisited in 6 months rather than 1 yr., per the response. Qwest to issue revised response incorporating a six month revisit.

10/26/01 - Qwest Final Response posted to CLEC Community.

11/06/01 - Qwest received reply to final response. Qwest has three areas of concern (see Nov. 6, AT&T reply in Project Meetings).Qwest has agreed to change the CR status to "Deferred" until the May 2002 Product and Process CMP meeting.

11/2/05 - Update sent to AT&T.

1/23/06 - Status changed to Completed


Project Meetings

11/2/05 Update to CR - E-mail send to AT&T

To discuss order processing or status, including Firm Order Confirmation (FOC) and Service Order Confirmation (SOC) Notice, or to send associated information to the appropriate Center for processing, contact our Customer Service Centers. Based on the location of your end-user and the type of service you requested, Local or Access Services, our Service Center numbers are:

LSRs for Interconnect Resale Services, Asynchronous Transfer Mode (ATM) Services, Resale Frame Relay, Complex Resale, Centrex, Local Number Portability (LNP), Interim Number Portability (INP), Unbundled Local Loops and Elements: Location Contact Fax Hours of Operation Interconnect Service Center (ISC) 888-796-9087 888-796-9089 - FAX Monday-Friday 6:00 AM - 10:00 PM Mountain Time Saturday 7:00 AM - 6:00 PM Mountain Time

Qwest's Service Center is available to assist with your needs and, if additional assistance is required you will be transferred to the Customer Service Inquiry and Education (CSIE) Center until 8:00 PM MTN Time Monday – Friday. If additional assistance is required after 8:00 PM or on Saturday, Qwest will coordinate a call back or provide additional assistance as needed.

November 6, 2001

Joan Wells Qwest LNP Process Manager

RE: CR Form #5582078

AT&T understands Qwest has denied its request to expand Qwest’s Interconnect Centers hours as stated at the October 17, 2001 monthly CMP meeting. Qwest has agreed to change the CR status to “deferred” until the May 2002 Product and Process CMP meeting. AT&T has three areas of concern with Qwest’s response:

AT&T recognizes NeuStar’s standard hours of operation do not include Saturday or Sunday; however, Qwest’s own action of providing support on Saturday acknowledges Saturday as an important port day for AT&T Broadband regardless of NeuStar’s hours of operation. Therefore, AT&T believes NeuStar’s standard hours of operation is not a determining factor for Qwest in regards to expanding its hours of support for Saturday or specifically, Sunday.

Although “port activity may currently be scheduled for any desired frame due time”, there are switches within Qwest’s network that cannot be set mechanically. Does Qwest have edits built into its systems to reject or defer LSRs in this scenario? How can these switches be identified?

The last concern centers on the 24-hour AMSC level of support that Qwest has offered. In the October 17 Product and Process CMP meeting, Qwest stated that the technicians at the AMSC center do not have access to Qwest’s provisioning systems for LNP. Offering this center as an alternative to expanding the Interconnect Centers hours only delays and provides a false expectation to CLECS trying to resolve outstanding porting issues. Therefore, AT&T does not believe this as an acceptable alternative to our change request.

AT&T believes continued discussions need to take place as AT&T’s business volumes continue to grow with Sunday porting activity.

Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes September 7, 2001 2:15 p.m.

Attendees:

Terry Bahner (AT&T), Donna Osborne-Miller (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Joan Wells (Qwest), Michael Buck (Qwest), Todd Mead (Qwest)

Qwest clarified some information regarding the forecast information provided by AT&T on 9/5; the forecast information provided is a projection of daily volume in all markets within Qwest territory

Action Items: - Lorna Dubose (Qwest) to communicate forecast information to Ken Beck and Toni Dubuque (9/10) - Lorna Dubose (Qwest) to provide Qwest response (9/14/)

###

Monday, August 27, 2001 1 p.m. Attendees: Terry Bahner (AT&T) Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) Terry explained that AT&T is interested in a window of Qwest support for LNP on Sundays after NPAC comes up. There is also a desire for Qwest support into the evening hours during the week. As an example, Terry cited the fact that AT&T gets orders until 10 p.m. (daylight time) in Salt Lake City. Lorna explained that Qwest center management could evaluate the possibility of expanded hours once the appropriate forecasting information is provided. The information to be included in the forecast: Expected volume by day and hour; any fluctuations expected (e.g. due to daylight savings time). Terry explained that she expected to be able to provide Qwest with forecast data by September 4. Lorna indicated that Qwest would attempt to examine forecast data prior to the September CMP meeting. Qwest will aim to provide a response prior to the September CMP meeting, but the formulation of a response might not be possible. Action Items: - Terry Bahner (AT&T) to provide Qwest with forecast volumes by 9/4/01 - Lorna Dubose (Qwest) to provide Qwest center management with forecast by 9/5/01 - Lorna Dubose (Qwest) to develop Qwest response by working with center management (tentative target: 9/7/01; with Michael Buck to organize walk-through meeting with AT&T during early week of 9/10/01)

###

LNP Meeting Notes 8/13/01

Attendees: Lorna Dubose Matt Rossi Terry Bahner Donna Osborne-Miller CR #5582078 – Expand Qwest’s interconnect center’s hours - Lorna currently waiting on response from the Qwest Interconnect Hours - Terry to give estimate to Lorna on call volume to expect


CenturyLink Response

Wholesale Product/Process October 24, 2001

Ms.Terry Bahner, Ms. Donna Osborne-Miller, AT&T

This letter is in response to CLEC Change Request Form #5582078, dated June 6, 2001. This Change Request pertains to a request by AT&T to Expand Qwest’s Interconnect Center hours to include a window of 6am MST to 10pm MST, Sunday through Saturday.

At this time, Qwest has no plans to expand the Interconnect Center hours. The following are some of the reasons that Qwest has made this decision: Currently, Qwest’s published normal hours of work are Monday – Friday 7am MST to 7pm MST. These hours are in parity in both Qwest Wholesale and Qwest Retail. Qwest Interconnect Center’s hours have already been previously expanded to 6am MST to 8pm MST Monday-Friday and 7am – 5pm MST on Saturday’s. NeuStar’s standard hours of Operation for the NPAC are Monday – Friday 7am – 7pm CST/CDT. The Qwest Interconnect Center hours currently exceeds this standard. Economic conditions currently do not facilitate an increase in head count to support the proposed increase in order activity and expansion. Lack of support from downstream systems, currently operating under the standard business hours. System maintenance necessities (i.e. scheduled down time) do not support expansion. Access to automated systems for order input is already available. Port activity may currently be scheduled for any desired frame due time in those switches where the ten digit triggers are set mechanically. 24-hour support is currently available through the Account Maintenance Support Center (AMSC) in handling repair issues that are a result of number portability.

At this time, Qwest will not expand its Interconnect Center hours further. Qwest had originally proposed that we review the expansion request again in one year, but at Clec request, Qwest has agreed to review again in six months.

Sincerely, Joan Wells Qwest LNP Process Manager

September 20, 2001

DRAFT RESPONSE For Review By CLEC Community and Discussion at October CMP Meeting Wholesale Product/Process Ms.Terry Bahner, Ms. Donna Osborne-Miller, AT&T

This letter is in response to CLEC Change Request Form #5582078, dated June 6, 2001. This Change Request pertains to a request by AT&T to Expand Qwest’s Interconnect Center hours to include a window of 6am MST to 10pm MST, Sunday through Saturday. At this time, Qwest has no plans to expand the Interconnect Center hours. The following are some of the reasons that Qwest has made this decision: Currently, Qwest’s published normal hours of work are Monday – Friday 7am MST to 7pm MST. These hours are in parity in both Qwest Wholesale and Qwest Retail. Qwest Interconnect Center’s hours have already been previously expanded to 6am MST to 8pm MST Monday-Friday and 7am – 5pm MST on Saturday’s. NeuStar’s standard hours of Operation for the NPAC are Monday – Friday 7am – 7pm CST/CDT. The Qwest Interconnect Center hours currently exceeds this standard. Economic conditions currently do not facilitate an increase in head count to support the proposed increase in order activity and expansion. Lack of support from downstream systems, currently operating under the standard business hours. System maintenance necessities (i.e. scheduled down time) do not support expansion. Access to automated systems for order input is already available. Port activity may currently be scheduled for any desired frame due time in those switches where the ten digit triggers are set mechanically. 24-hour support is currently available through the Account Maintenance Support Center (AMSC). At this time, Qwest will not expand its Interconnect Center hours further. Qwest will review this expansion request again in one year.

Sincerely,

Joan Wells Qwest LNP Process Manager

CC: Lorna Dubose Judy Schultz Margaret Bumgarner Michael Buck Todd Mead


Open Product/Process CR 5582099 Detail

 
Title: LNP switch disconnect timing
CR Number Current Status
Date
Area Impacted Products Impacted

5582099 Completed
12/12/2001
Billing LNP
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Dubose, Lorna
Director:
CR PM:

Description Of Change

Change current switch disconnect process to where disconnect occurs immediately after AT&T Broadband activates the number.


Status History

06/06/01 - CR received from Donna Osborne Miller of AT&T

06/07/01 - Status changed to New to be evaluated

07/09/01 - Reviewed under consideration

07/09/01 - LNP product team to discuss on 7/17/01, will report status during the July 18th Monthly CICMP Meeting (LD)

08/09/01 - Qwest is soliciting proposals from vendors such as Telcordia to include a time and cost estimate to accommodate this request. Qwest has received a time and cost proposal from Telcordia and has solicited a proposal from another vendor to prepare a business case and cost study analysis for a solution to this request. Target completion for business case and cost study tentatively set for end of September 2001 (LD)

08/19/01 - Process change implemented related to this request was implemented; going forward, Qwest will complete disconnect orders for LNP on the day after the due date (MJB)

08/27/01 -- alignment clarification meeting held; Lorna Dubose reiterated that Qwest is awaiting time and cost from second vendor; cost analysis still expected to be done during month of September (MJB)

09/7/01 -- Status update meeting conducted with AT&T; anticipated dates remain same (MJB)

09/18/01 - Internal status update meeting; target response date updated (MJB)

09/19/01 -- Status update provided at CMP (MJB)

10/05/01 - Time and cost from final vendor received 2 weeks later than expected

10/10/01 - Draft response posted to database

10/17/01 - Qwest to internally establish whether there is an impact to IMA.

11/06/01 - Received AT&T's reply to Qwest Final Response. AT&T Broadband will continue to operate under the process formally introduced on August 20th, 2001. AT&T will look forward to a future solution in 2002 and move CR Status to CLEC Test mode during the November 14, 2001CMP Meeting.

11/09/01 - Issued revised response to AT&T.

11/13/01 - Issued final response to CLEC Community and posted to Web.

11/14/01 - CMP Meeting: CR to remain in Presented status. Judy Schultz to raise associated action item and address at December CMP Meeting.

12/12/01 - CMP Meeting: Qwest denied request, status changed to denied.

12/12/01 - AT&T requested status changed to Deferred as they may want to revisit this CR at a later date.

12/19/01 - AT&T written response to Qwest position

12/28/01 - Formal response dated 11/9/01 issued to CLECs


Project Meetings

12/19/01 AT&T written response to Qwest position December 19, 2001 Lorna Dubose LNP Wholesale Product Manager Qwest Communications 1801 California Street Denver, Colorado 80202 RE: CR5582099 Dear Lorna: AT&T understands Qwest has denied CR5582099. It will be placed in deferred status until AT&T is able to review Qwest’s self-reporting data for OP-17 PID which measures LNP switch disconnect timing. Qwest took an action item in the December CMP meeting to find out when this measurement will be included in Qwest’s Performance Results Reports. Currently, Qwest does not provide data to the CLECS for OP-17 PID and the CLECS do not have access to the internal data Qwest referenced in its response to AT&T November 9th, 2001. AT&T submitted this CR with the intent to eliminate loss of dial tone. We do not believe the 73% reduction in loss of dial tone Qwest stated is an acceptable standard. AT&T Broadband still experiences loss of dial tone in spite of the August mechanization of holding both the switch translations and the service orders until 11:59 P.M. of the next business day after the port due date. Qwest would be able to perform at 100% if they would adopt the process of disconnecting from the switch once the CLEC activated the number in NPAC. AT&T is disappointed Qwest will no longer pursue an avenue which would truly insure a stable platform for the end customer to port his telephone number. Sincerely, Terry Bahner Supervisor AT&T Local Services Access Management Western Region

Cc: Tim Boykin Sharon Van Meter Donna Osborne-Miller

November 14 - CMP Meeting Callan-Qwest described the CR and the Qwest response. Bahner-AT&T stated that she did not want the CR to be closed as she had just received the response. She also noted that Qwest has not shared its PID data with AT&T. Clausen-Eschelon stated that this CR should not be in CLEC test. Bahner-AT&T stated that she was under the impression that Qwest was moving toward a solution to the CR, but that the recent response was a denial. Callan-Qwest stated that Qwest had evaluated the potential solution and was not prepared to accept the risk of changing a stable system platform, which would be the result of moving forward with a solution to the CR. Dixon-Worldcom asked if this measure was in the PAP. Callan-Qwest stated that it is a PID and it is also a PAP, except in Arizona. Dixon-Worldcom stated that this was inconsistent with his understanding of the Qwest agreements. He understood that Qwest would automatically incorporate all of the ROC measures into the Arizona filing. Callan-Qwest stated that it was her understanding that this had not been requested as a PAP in Arizona. Schultz-Qwest stated that Qwest would take an action item and report at the next meeting. She stated that the CR is denied and asked what status AT&T wanted to leave it in. Bahner-AT&T stated that she would like it left as Presented until next month.

November 6, 2001 AT&T Response to our final position on the CR. Lorna Dubose Qwest LNP Wholesale Product Manager

RE: CR Form #5582099 This letter is in response to the status you provided at the October 17, 2001 Product and Process CMP meeting. We look forward to Qwest implementing a system change that would disconnect the TN out of the switch immediately after AT&T Broadband activates the number. This change would eliminate unnecessary loss of dial tone between Qwest and AT&T Broadband, reduce the number of work backs and snap backs and in general, provide continuity to the LNP process. In the interim, AT&T Broadband will continue to operate under the process formally introduced on August 20th, 2001.

We look forward to the next status in November and a possible implementation date in 2002.

Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes

Internal Status Update Meeting (9/18/01 4:30 p.m.) Attendees: Michael Buck (Qwest), Lorna Dubose (Qwest) Internal cost analysis still on track for 9/28/01 completion. Lorna updated target date for formal AT&T response to 10/12/01.

###

September 7, 2001 2:15 p.m.

Attendees:

Terry Bahner (AT&T), Donna Osborne-Miller (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Joan Wells (Qwest), Michael Buck (Qwest), Todd Mead (Qwest)

Qwest provided a status update on this CR. Qwest has received time and cost estimates from 2 vendors to date. Qwest will be seeking a time and cost estimate from a third vendor. The addition of a third vendor is not expected to adjust the dates communicated in the August 27, 2001 Clarification Meeting. AT&T asked whether Qwest has yet committed to performing the change requested in this request. In response to a question from Sharon, Lorna indicated that Qwest has not yet committed to doing the work requested in this CR. The decision whether or not do the work is dependent upon the cost analysis scheduled for completion by 9/28/01.

Action Items:

- Lorna Dubose (Qwest) to create cost analysis based upon vendor time and costs by 9/28/01 - Lorna Dubose (Qwest) to develop Qwest response based upon cost analysis (tentative target: 10/5/01)

###

Monday, August 27, 2001 1 p.m. Attendees: Terry Bahner (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) Terry confirmed that the goal of this CR is to have Qwest provide a response regarding AT&T’s desire that LNP disconnects not be released until a corresponding activate transaction is received from NPAC indicating that AT&T service is operational.

Terry indicated that previous action taken by Qwest (i.e. delayed posting of disconnects until due date plus 1 day) is helpful, but does not address the core of this request. Lorna reiterated that Qwest is still seeking vendor time and cost estimates to provide the functionality requested by AT&T.

Lorna expects to develop a cost analysis based upon vendor responses by the end of September. At that time Qwest will make a decision whether or not to pursue the vendor proposals.

Lorna does expect to be able to provide an interim status update at the September CMP meeting. As of August 29, 2001 time and cost bids have been received from both vendors involved in this CR.

Action Items: - Lorna Dubose (Qwest) to create cost analysis based upon vendor time and costs by 9/28/01 - Lorna Dubose (Qwest) to develop Qwest response based upon cost analysis (tentative target: 10/5/01)

###

LNP Meeting Notes - 8/13/01

Attendees: Lorna Dubose Matt Rossi Terry Bahner Donna Osborne-Miller

- Qwest looking at long term solution - Price bid expected from Telcordia by 8/27 - Price bid expected from another vendor 08/30 - Cost analysis and internal analysis to be conducted by Qwest 09/28 - Estimated implementation date set for no earlier than Q1 2002


CenturyLink Response

November 9, 2001

Ms. Terry Bahner Ms. Donna Osborne-Miller

AT&T

This letter is in response to your CLEC Change Request Form, number 5582099 dated June 6, 2001 – LNP Switch Disconnect Timing.

Request: Change current switch disconnect process to where disconnect occurs immediately after AT&T Broadband activates the number.

Response: Qwest understands the goal is to eliminate disconnection of customers in error. Qwest has agreed to Performance Measurement OP-17 - Timeliness of Disconnects Associated with LNP Orders with a standard of 98.25%. Qwest is in full support of this measure and has committed to this standard.

In August, Qwest completed the mechanization of the solution to hold the switch translations and the service orders until 11:59 P.M. of the next business day after the port due date. Initial analysis of internal data from before and after the implementation indicates a 73% reduction in loss of dial tone and an 84% reduction in workbacks.

Qwest did evaluate several vendor proposals outlining a system solution to time the switch disconnect with the port activation. Qwest believes that our current process and recent system mechanization has provided a reliable and stable platform for the completion of port orders. As a result of the analysis of the vendor proposals, and the service improvements from our own internal system changes; we will not be pursuing any additional system enhancements. No further action is planned. Sincerely,

Maureen Callan Group Product Manager


Open Product/Process CR 5582212 Detail

 
Title: 3 day LNP LSR interval for Megabit Line
CR Number Current Status
Date
Area Impacted Products Impacted

5582212 Completed
11/14/2001
Billing LNP
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

Qwest considers a megabit line as a complex and requires a 5 day interval. Since LNP is porting number only and does not need the special facilities, it should be treated as a ported number and have a 3 day interval


Status History

06/06/01 – CR received from Donna Osborne Miller of AT&T 6/07/01 – Status changed to New – to be evaluated

07/09/01 – LNP product team to discuss on 7/17/01 – will report status during the July 18th Monthly CICMP Meeting (LD) 7/18/01 - New to be

08/09/01 – This CR pending further investigation with Complex Services (Megabit). (LD)

08/27/01 -- alignment clarification meeting held; Lorna Dubose indicated that she was working with appropriate product and process groups to address this request.(MJB)

09/7/01 -- Response walkthrough meeting conducted with AT&T (MJB)

09/14/01 -- AT&T letter responding to Qwest position received; response revision underway (MJB)

09/19/01 -- Status update provided at CMP

10/04/01 - Draft Response added to database

10/17/01 - CMP Meeting: Qwest presented draft response to CLEC Community and made status change to CLEC Test .

10/24/01 - Qwest Response issued to CLEC Community

11/06/01 - received AT&T's reply to Qwest Final Response. AT&T will move to close CR at November 14, 2001 CMP Meeting.

11/14/01 - CMP Meeting: AT&T moved to Close CR.


Project Meetings

November 6, 2001

Joan Wells Process Manager Local Number Portability

RE: CR Form #5582212 AT&T has submitted LSRs requesting the new 3-day service interval for Megabit service established after April 4th, 2001. At this point in time, only a small number of orders have been pushed out to the previous 5-day interval. AT&T considers this a coaching issue within Qwest and has socialized it with the typing centers and the Denver Interconnect center during our weekly conference calls. We will close this CR at the November 14th, 2001 Process and Product CMP meeting. Thank you for providing AT&T Broadband the tools to identify the appropriate USOCS. Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes

September 14, 2001

Lorna Dubose LNP Wholesale Product Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Your letter dated September 5, 2001 regarding change request 5582212 – 3-day interval Megabit Line

Dear Lorna:

AT&T believes Qwest has, in part, addressed CR 5582212. Going forward, any local service request to port an end-user’s telephone number that Qwest currently lists as a Megabit service qualifies for the 3-day interval if the Megabit service was installed with Qwest after April 4, 2001. AT&T would prefer this 3-day interval apply to all Megabit services regardless of the April 4th date.

Qwest has indicated AT&T Broadband can determine this date by reviewing the customer service record. AT&T Broadband has yet to determine if a Qwest install timestamp is present next to the USOC. AT&T would like Qwest to issue a unique USOC to help identify Megabit services installed after April 4th to assist in acquiring the 3-day interval. Your consideration to this request would be appreciated.

Sincerely,

Terry Bahner Supervisor Local Services Access Management Western Region

CC: Tim Boykin Sharon Van Meter Mitchell Menezes

###

September 7, 2001 2:15 p.m.

Attendees:

Terry Bahner (AT&T), Donna Osborne-Miller (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Joan Wells (Qwest), Michael Buck (Qwest), Todd Mead (Qwest)

The Qwest response to this CR was presented; multiple clarification questions were asked and answered:

Q: Why is April 4, 2001 date important? A: This is the date when the process change for engineering megabit requests as non-design took place

Q: So the service offered did not change after April 4? A: Correct. Only an internal process was changed. The megabit service offered did not change.

Q: How should CLEC determine the customers’ install date? A: The necessary information should be available in the CSR (Customer Service Record). In Qwest internal systems both the USOC and the date are visible. Also, another option is to ask the customer when their service began.

Action Items:

- Terry Bahner (AT&T) to confirm that necessary information is available in the CSR visible to AT&T (9/13) - Terry Bahner (AT&T) to take Qwest response to AT&T stakeholders (9/13)

###

Monday, August 27, 2001 1 p.m. Attendees: Terry Bahner (AT&T), Sharon Van Meter(AT&T), Lorna Dubose (Qwest), Michael Buck (Qwest), Todd Mead (Qwest)

Terry clarified that the request for a reduced interval for LNP of megabit lines applies only to the ported number NOT the facilities. Terry indicated that AT&T had put in place procedures to inform customers of the impact to megabit facilities when AT&T ports only the number. Lorna indicated that she was working with appropriate product and process groups to address this request.

Action Items: - Lorna Dubose (Qwest) to formulate Qwest response by 9/5/01 - Michael Buck (Qwest) to organize a walk-through meeting with AT&T during late week of 9/3/01.

###

LNP Meeting Notes – 8/13/01

Attendees: Lorna Dubose Matt Rossi Terry Bahner Donna Osborne-Miller

- Lorna scheduled meeting with Megabit Product Manager on 8/16 - Status update will be given to Terry Bahner after that meeting


CenturyLink Response

October 04, 2001 Ms.Terry Bahner, AT&T

This letter is in response to CLEC Change Request Form, number 5582212 – 3 day LNP LSR interval for Megabit Line, dated June 6, 2001.

Request: Qwest considers a megabit line as a complex and requires a 5-day interval. Since LNP is porting a number only and does not need the special facilities, it should be treated as a ported number and have a 3 day interval.

Response: After meeting with the Megabit Product Manager and the Interconnect Service Centers, it has been determined that as of April 4, 2001, Qwest implemented a new process for engineering Megabit service and it is now considered a non-design/simple service. Therefore, end-user customers that ordered Megabit service after April 4, 2001 had their service installed as non-design/simple service. This type of Megabit service can have a 3-day interval, which is the same as simple LNP orders today. However, if the Megabit end-user service was installed prior to April 4, 2001, the service is still considered a design/complex service. This requires service interval timeframes that allow Qwest systems to accurately remove the switch translations and process the order completion. Appropriate intervals for the Complex Product type will continue to apply. These intervals are shown in the LNP Product Catalog under Standard Intervals for LNP or the Service Intervals for Interconnection & Resale located at Qwest.com.

New USOC’s were developed for this network platform change. Effective 04-04-01, the Basic and Pro Services using the HRL++ USOCs will be grandparented and may not be used for ordering new services. The new Qwest DSL basic line 1FB/1FR, AFK/AFH Usoc’s are GRL++ and will be used after the 04-01-01 date.

The Select Service using HRC++ USOCs also, are no longer available for use.

Grandparented USOC’s are as follows: HRCA1, HRCA3, HRCA5, HRCWM & HRL51, HRL53, HRL55, HRL5M, HRLA1, HRLA3, HRLA5, HRLAM, HRLB3, HRLB5, HRLBM, HRLC1, HRLC3, HRLC5, HRLCM, HRLD1, HRLD3, HRLD5, HRLDM, HRLE1, HRLE3, HRLE5, HRLEM, HRLF1, HRLF3, HRLF5, HRLFM, HRLG1, HRLG3, HRLG5, HRLGM, HRLW1, HRLW3, HRLW5, HRLWM

New USOC’s are as follows: GRLA1, GRLA3, GRLA5, GRLAM, GRLB1, GRLB3, GRLB5, GRLBM, GRLC1, GRLC3, GRLC5, GRLCM, GRLD1, GRLD3, GRLD5, GRLDM, GRLE1, GRLE3, GRLE5, GRLEM, GRLF1, GRLF3,GRLF5, GRLFM, GRLG1, GRLG3, GRLG5, GRLGM, GRLSM, GRLW1, GRLW3, GRLW5, GRLWM, GRLYM.

This list in not inclusive of all products provisioned with DSL. If further information is needed, please consult your Service Manager or a USOC guide.

In conclusion: In order to qualify for the 3-day interval, it will be necessary for the CLEC to know when Qwest installed the end-user’s Megabit service (before or after April 4, 2001) and whether the account meets the required criteria for requesting a 3-day interval. If the CLEC is unable to obtain the date of the installation information from the CSR or is unable to determine by the USOC, then additional consultation with the end user by the CLEC may be needed to find out when their Megabit service was installed, prior to or after the April 4th, 2001 date. Should the CLEC submit an LSR with a 3-day interval request and Qwest determines that the Megabit service does not qualify for the simple interval, then the FOC would be sent to the CLEC with the appropriate Design/Complex interval due date.

Discussion has occurred with the Interconnect Service Centers to reinforce this change that was previously documented, and sent out to the Centers, when the change occurred in April. Qwest will continue to follow the service interval guidelines for simple and complex services as outlined in the Product Catalog (PCAT).

Sincerely, Joan Wells Process Manager Local Number Portability


Open Product/Process CR 5582288 Detail

 
Title: Qwest counts Saturday as a business day
CR Number Current Status
Date
Area Impacted Products Impacted

5582288 Denied
11/14/2001
Billing LNP
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Dubose, Lorna
Director:
CR PM:

Description Of Change

Qwest’s current process is to count Monday-Friday as business days. Would like it to be Monday-Saturday so Saturday will count as one of the three day intervals for LNP

Description changed resulting from 8/27/01 meeting.

The app date calculation for all LNP requests will reflect a 7 p.m. daily cut-off time rather than the 3 p.m. cut-off currently in place. Any LNP request received prior to 7 p.m. will receive an app date of the current date. Any LNP request received after 7 p.m. will receive an app date of the next business day.


Status History

06/06/01 - CR received from Donna Osborne Miller of AT&T

06/07/01 - Status changed to New – to be evaluated

07/09/01 - Reviewed under consideration

07/09/01 - LNP product team to discuss on 7/17/01 – will report status during the July 18th Monthly CICMP Meeting (LD)

08/09/01 - Currently Qwest is adhering to the NPAC standard business hours which do not include Saturday as a regular business day. NPAC business hours are included in the Qwest LNP Product catalog. (LD)

08/23/01 - UR# 2491 has been initiated to update the APP date calculation to incorporate a 7 p.m. cut-off as opposed to the currently used 3 p.m. cut-off (MJB)

08/27/01 - alignment clarification meeting held; altered scope for this CR reconfirmed by Terry and Lorna; Lorna indicated that a new Qwest User Request (UR # 2491) has been created to support the requested change. Work is underway to prioritize the request and determine when it will be implemented. This information will be provided in the Qwest response for this CR. (MJB)

09/05/01 - Qwest response provided.

09/07/01 - Walk Through meeting held with AT&T

09/14/01 - AT&T letter responding to Qwest position received; response revision underway (MJB)

09/19/01 - Status update provided at CMP; Qwest re-evaluating position.

09/20/01 - UR 2491 implemented in production

10/10/01 - Qwest draft response posted to database.

10/17/01 - CMP Meeting: Qwest presented its draft response. AT&T requested that the CR status be left as presented, AT&T to review internally

11/06/01 - AT&T reply to Qwest response dated 10-10-01. AT&T recognizes the CR is denied by Qwest but is disappointed at the restriction placed on Saturday ports which Qwest had previously honored under the 3-day SIG (submissions of LSRs on Wednesday). Any additional action concerning this change request will be handled in a different venue when prudent.

11/14/01 - CMP Meeting - Qwest presented its response. AT&T requested that the status be changed to "Denied."

12/06/01 - Qwest formal response (dated 10/10/01) transmitted to CLEC community.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

November 6, 2001 AT&T reply to Qwest response dated 10-10-01 Lorna Dubose Qwest LNP Product Manager

RE: CR Form #5582288 AT&T understands Qwest is denying our request to include Saturday as a business day in the SIG. In addition, Qwest is denying our request to manually change orders submitted prior to 7 p.m. MST on Wednesday to reflect a Saturday install date in lieu of a system change.

AT&T appreciates Qwest expanding the LSR submission deadline from 3 p.m. to 7 p.m. MST with the IMA 8.0 release. We are disappointed at the restriction placed on Saturday ports which Qwest had previously honored under the 3-day SIG (submissions of LSRs on Wednesday). Any additional action concerning this change request will be handled in a different venue when prudent. Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes

September 14, 2001

Lorna Dubose LNP Wholesale Product Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Your letter dated September 5, 2001 regarding change request 5582288 - Saturday as a business date

Dear Lorna:

It was not the intention of AT&T to worsen the service delivery to our customers by accepting the LNP Service Intervals in the State 271 Workshops. Section 10.2.5.2 LNP Standard Intervals has been reviewed and AT&T does not believe this section prevents Qwest from processing the change request to include Saturday as a business date for the LNP product. In fact, AT&T can find no dialogue from the 271 workshops which addressed omitting Saturday as a business day when determining LNP intervals.

Before the IMA 8.0 upgrade the weekend of August 18th, Qwest honored a 3-day interval for a Saturday install as long as AT&T Broadband submitted the LSR prior to 3 p.m. MST on Wednesday. Qwest’s typing center set expectations that AT&T passed on to its customers by providing a FOC with the 3-day interval.

Qwest has stated Saturday cannot be counted in the standard interval. Per Qwest, all local service requests must be submitted prior to 3pm MST on Tuesday to receive the Saturday install date. While AT&T understands Qwest has implemented and updated their systems to reflect its intervals, AT&T believes changes to the same system including Saturday as a business day can also be accomplished in an upcoming release. Though AT&T realizes Qwest is extending its business day from 3:00 p.m. to 7:00 p.m. MST, it does not satisfy the CR5582288 AT&T submitted. Saturday is a critical install day for AT&T Broadband. Qwest’s shift in process and the failure to inform AT&T of this change created an undue and sudden burden for AT&T Broadband’s customers.

Therefore, AT&T would like to partner with Qwest to implement a change as previously practiced by Qwest which includes Saturday. In the interim, AT&T is requesting Qwest to manually change orders submitted prior to 3:00 p.m. MST on Wednesday to reflect a Saturday install date. Thank you for your consideration.

Sincerely,

Terry Bahner Supervisor Local Services Access Management Western Region

CC: Tim Boykin Sharon Van Meter Mitchell Menezes

###

September 7, 2001 2:15 p.m. Attendees:Terry Bahner (AT&T), Donna Osborne-Miller (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Joan Wells (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) The Qwest response to this CR was presented. AT&T reiterated concerns presented in an e-mail from August 30, 2001. The concerns centered on the fact that from June 1 until August 20 Qwest had used a process that allowed for a 3-day interval. After August 20 Qwest adjusted its process, requiring that requests be received by 3 p.m. Tuesday to qualify for a Saturday install. AT&T understands Qwest’s position that the process in place from June 1 through August 20 was incorrect. Furthermore, AT&T understands Qwest’s position that a reversion of process is necessary to remain compliant with guidelines decided in 271 Workshops. However, AT&T believes that Qwest should have been more effective in communicating the process change which resulted in an increase in the necessary interval to support a Saturday install. Qwest indicated that effective communication is a key element to implementing changes that affect CLECs.

Action Items: - Terry Bahner (AT&T) to provide confirmation of response acceptance (9/13)

### E-Mail from Terry Bahner (AT&T) to Qwest Thursday, August 30, 2001 12:15 p.m.

It's clear from the Qwest-Broadband call I facilitated this morning that Qwest has changed their process regarding the 3 day interval proces+U3when it pertains to a Saturday install date. From June 1st (PCNRN051601-1) to August 18, Qwest FOC'd a Saturday install date using the 3 day interval guide. As long as the LSR was sent prior to 3pm mst on Wednesday, Qwest gave the Saturday install date. On August 20th, Qwest changed its process. The LSR must be submitted on Tuesday before 3pm to have a Saturday install date. Qwest now states the due date interval guidelines do not include Saturday. Qwest has indicated the process was always in place and it was incorrectly interpreted by Qwest Escalations and typists and was therefore granted in error. AT&T reviewed the RN on multiple conference calls with Qwest and was told the requested Saturday date would be met. Further more AT&T was never informed the RN was a test/trial subject to change and/or interpretation by Qwest. AT&T considered the notification sent by Qwest on June 1st as a product and process change not a temporary fix as so indicated on this morning's call. While I welcome the extension of 3pm mst to the tentative 7pm mst, it no longer meets the intent of the CR. Therefore, please pursue with AT&T's request to include Saturday in Qwest's due date interval guidelines.

Thank you. Terry L. Bahner AT&T LSAM

###

Monday, August 27, 2001 1 p.m. Attendees: Terry Bahner (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) Terry re-confirmed AT&T understands CR scope resulting from 8/14/01 meeting. To wit, the app date calculation for all LNP requests will reflect a 7 p.m. daily cut-off time rather than the 3 p.m. cut-off currently in place. Any LNP request received prior to 7 p.m. will receive an app date of the current date. Any LNP request received after 7 p.m. will receive an app date of the next business day.

In follow-up, Terry clarified: This is separate from agreeing to the current app date calculation Qwest has adopted August 20 (IMA 8.0 release) for LNP orders which now negatively impacts AT&T Broadband’s provisioning process and directly affects our market entry. AT&T will submit a separate change request to Qwest to resolve the additional day added to the LNP service interval if Qwest continues the new app date calculation process. This change request’s intent was to further extend the timeframe in submitting LSRs to facilitate a 3-day install; however, Qwest’s new app date calculation has negated this. Lorna indicated that a new Qwest User Request (UR # 2491) has been created to support the requested change. Work is underway to prioritize the request and determine when it will be implemented. This information will be provided in the Qwest response for this CR.

Lorna indicated that efforts had been underway to (piggyback) this CR on an existing user request in an attempt to complete the change sooner. However, that effort failed and new UR (2491) was issued.

Action Items: - Lorna Dubose (Qwest) to formulate Qwest response by 8/31/01 - Michael Buck (Qwest) to organize a walk-through meeting with AT&T during week of 9/3/01.

###

LNP Meeting Notes 08/13/01 Attendees: Lorna Dubaose Matt Rossi Terry Bahner Donna Osborne-Miller

NPAC does not currently consider Saturday as a business day AT&T gave an example: if LSR submitted 3:01 pm on Friday - Monday is day 1, AT&T would like Saturday as day 1 Joan Wells mentioned at last CICMP that hours might be expanded to 7pm MST AT&T said that 7pm wold be sufficient and CR could be closed


CenturyLink Response

October 10, 2001

Wholesale Product Marketing Ms. Terry Bahner and Ms. Donna Osborne, AT&T

This letter is in response to your letter dated September 14, 2001, regarding Change Request 5582288 – Saturday as a business day.

Qwest acknowledges AT&T’s acceptance of the agreed upon 271 Workshop LNP Service Intervals.

As stated in your letter, before the IMA 8.0 release, Qwest would honor a three day interval for a Saturday install for LSR’s submitted prior to 3:00 p.m. Mountain Time on Wednesdays. However, after the IMA 8.0 release each CLEC, will need to submit its LSR for flow-through LNP orders on Tuesday by 7:00 p.m., Mountain Time, in order to have a Saturday due date.

Qwest identified the need to implement system logic to obtain parity between our manual and mechanized processes, company policies, as well as documentation. As a result, IMA was upgraded to support the company Service Interval Guide (SIG), which excludes the calculation of Saturdays, Sundays, and Holidays.

Qwest recognizes Saturday is a critical install day for AT&T Broadband and will continue to offer Saturdays, Sundays, and Holidays as due dates in our switches where the 10-digit unconditional LNP trigger can be set automatically. However, the CLEC will need to submit the LSR within the appropriate interval timeframe as far as business days.

At this time, Qwest appreciates AT&T offer to partner with us to include Saturday as a business day, however, Qwest declines, and will continue to support the agreed upon 271 Workshop intervals and existing company practice for the use of Business days. Thank you for your request.

Sincerely,

Lorna Dubose LNP Product Manager


Open Product/Process CR 5582295 Detail

 
Title: Qwest does not cancel LSR after confirming FOC via pending “C” order. (reference Systems CR # SCR092601 1)
CR Number Current Status
Date
Area Impacted Products Impacted

5582295 Completed
4/17/2002
Billing LNP
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Wells, Joan
Director:
CR PM: Thomte, Kit

Description Of Change

Qwest’s current process is to cancel LSR after FOC has been sent because of a pending “C” order. AT&T Broadband wants no cancel of FOC once sent by Qwest. FOC should stand.


Status History

06/06/01 - CR received from Donna Osborne Miller of AT&T 6/07/01 – Status changed to New – to be evaluated

07/09/01 - LNP product team to discuss on 7/17/01 – will report status during the July 18th Monthly CICMP Meeting (LD)

07/18/01 - New to be clarified

08/09/01 - This functionality is included in the IMA 8.0 release scheduled for deployment on August 19th 2001 (LD)

08/19/01 - IMA 8.0 was implemented with requested change; if an FOC has been issued for an LSR, the LSR will no longer be cancelled by Qwest because of pending orders (MJB)

08/27/01 - Alignment clarification meeting held; Terry Bahner indicated that initial results from IMA change look promising; AT&T will continue to monitor for next 30 days and then CR will be closed if no new issues arise (MJB)

09/07/01 - Walk through meeting held with AT&T

09/10/01 - Qwest internal meeting to review CR response along with process under development by Loretta Huff (MJB)

09/14/01 - Response received from AT&T

09/19/01 - Status update provided at CMP

09/28/01 - Draft response posted to database

10/17/01 - CMP Meeting: Qwest presented draft response. AT&T requested clarification on JEP process. Joan Wells explained JEP's don't apply to LNP. No status change to CR.

10/24/01 - Qwest Response finalized and issued to CLEC Community.

11/06/01 - AT&T Reply to Final Response dated 10-24-01. AT&T expects Qwest to adhere to its commitment to allow a jeopardy notification after a FOC instead of a non-fatal error after an FOC as submitted under SCR092601-1.

11/14/01 - CMP Meeting - AT&T request CR remain in CLEC Test until after discussion at the Systems CR meeting

11/15/01 - Discussed at Systems CMP meeting. There are interim process solutions available for SCR092601-1 Qwest will discuss at the December CMP meeting. This CR should be closed on agreement from CLEC community.

12/12/01 - CMP Meeting: Jill Martain (Qwest) presented the interim process solution for SCR092601-1 to the CLECs. After Jill's presentation AT&T requested this CR to remain in CLEC Test.

01/16/02 - January CMP meeting: Qwest presented timing interval proposal. CLECs requested further dialogue on this issue. CR Status changed to "Development"

01/23/02 - Meeting arranged for 01/31/02 with AT&T to investigate the top reasons that cause error conditions after an FOC has been issued

01/31/02 - Meeting held with AT&T to investigate the top reasons that cause error conditions after an FOC has been issued

02/07/02 - Meeting minutes for 01/31/02 meeting sent to AT&T

02/08/02 - Followup meeting to 01/31/02 meeting with AT&T. Top reasons that cause error conditions after an FOC has been issued were presented.

02/11/02 - Meeting minutes for 02/08/02 meeting sent to AT&T

02/12/02 - Meeting minutes for 02/08/02 meeting added to CMP database

02/20/02 - February CMP meeting: Qwest presented the latest agreements as outlined in the meeting minutes. Qwest and AT&T agreed to continue to work together to resolve the effect on due dates when a jeopardy condition is identified after the App date. Manual process for sending a jeopardy notice after an FOC has been issued, was implemented 02/18/02. CR status changed to "CLEC Test" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/21/02 - E-mail from T.Bahner AT&T, reporting system issue and asking for clarification on jeopardy and DD process for LNP

02/22/02 - Response e-mail from Qwest clarifying AT&T question on jeopardy and DD process for LNP

03/06/02 - Letter from AT&T offering a counter proposal to the matrix Qwest has presented for CR5582295

03/08/02 - Revised response from Qwest with updated matrix (supplemental information)

03/20/02 - March CMP Meeting. Revised matrix presented and agreed to by the CLECs. CR to remain in CLEC Test for one more month. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/22/02 - Revised response dated 03/21/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/08/02 - Qwest e-mail asking if revised matrix is meeting CLEC needs

04/08/02 - Reply e-mail from AT&T agreeing that revised matrix is working, but seeking clarification on PCAT update

04/11/02 - Reply e-mail from Qwest with response to PCAT question

04/17/02 - April CMP Meeting: CLECs agreed to close CR. Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site


Project Meetings

04/11/02 - Reply e-mail from Qwest with response to PCAT question

Subject: CR # 5582295 Update Date: Thu, 11 Apr 2002 09:15:41 -0600 From: "Todd Mead" Organization: Qwest Communications International, Inc. To: Terry Bahner

Terry, Please see below in response to your question about PCAT update:

"The LEFV fid alone is not necessarily cause for the CLEC to be sent a jeopardy notification. Only if the FOC has been sent to the CLEC would we send a jeopardy notification. And the current process of jeopardy after FOC states that in all conditions where an FOC is sent and Qwest has found a problem with the request, we will follow the jeopardy after FOC process. No matter what, if it has been FOC'd and Qwest finds a problem with the LSR, we will follow the jeopardy after FOC process.

Thanks

Todd

03/06/02 Letter from AT&T offering a counter proposal to the matrix Qwest has presented for CR5582295

1875 Lawrence St. Denver, CO 80202-1847

March 6, 2002

Todd Mead CMP Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: CR5582295, SCR092601, & Matrix

Dear Todd:

AT&T still has concerns surrounding the interim manual process of how and when Qwest issues a jeopardy after sending the CLEC a FOC for an LSR. We have two specific concerns. This first is the introduction of the Application Date (APP) as a tool to determine AT&T Broadband’s due date when orders are issued a jeopardy condition. And the second is the subjective use of the term "renegotiated".

AT&T believes Qwest could proactively minimize disruption to the customer if Qwest would maintain the CLEC ordered due date more frequently than is possible with the Qwest proposal.

AT&T proposes the following changes to achieve this objective:

1. Jeopardy Condition identified within 24 hours then original FOC’d due date will be maintained - Identified within 24 hours after LSR submission by CLEC - CLEC notified within 24 hours after LSR submission by CLEC - Jeopardy cleared within 4 business hours

Jeopardy Condition identified within 24 hours then original FOC’d due date will be renegotiated - Jeopardy not cleared within 4 business hours

2. Jeopardy Condition identified more than 24 hours then original FOC’d due date will be maintained - Identified more than 24 hours after LSR submission by CLEC but before the due date - CLEC notified more than 24 hours after LSR submission by CLEC but before the due date - Jeopardy condition is Qwest’s fault and CLEC clears the condition within 4 business hours

Jeopardy Condition identified more than 24 hours then original FOC’d due date will be renegotiated - Jeopardy condition is CLEC’s fault and CLEC clears the condition within 4 business hours - Jeopardy condition is not cleared within 4 business hours

3. Jeopardy condition identified on or after the due date - Qwest will immediately work with CLEC to resolve end user customer impact. No negotiated due date

AT&T would like written rules about the meaning of “renegotiated”. AT&T believes the renegotiated interval should have minimal customer impact and never exceed the standard service interval for LNP.

AT&T believes Qwest has reasonable time to identify all errors during the first 24 hours. If an error is discovered and the error is related to a Qwest CSR, a pending retail order or any error Qwest fails to identify, AT&T believes the FOC’d due date should be maintained. Our proposed changes define and clarify the process. We believe this will reduce misinterpretation of the process and provide a consistent response from Qwest during the escalation process.

AT&T appreciates Qwest extending the courtesy call to a third week. This allowed sufficient time for AT&T to verify the jeopardy was being received via EDI. It also provided sufficient time for AT&T to provide Qwest examples of when the process broke.

Sincerely,

Terry Bahner Supervisor AT&T Local Services Access Management Western Region 303-298-6149

Cc: Tim Boykin Sharon Van Meter Donna Osborne-Miller

02/22/02 Response e-mail from Qwest clarifying AT&T question on jeopardy and DD process for LNP

Subject: Re: CMP 2/20/2002: Action Item & Clarification Date: Fri, 22 Feb 2002 16:45:31 -0700 From: "Joan Wells" To: "Bahner, Teresa L (Terry), NCAM" CC: "Jill Martain" , Jill"

02:00 p.m. (MDT) / Friday 08 February 2002

Followup meeting to Investigate top reasons for error condition after FOC

Terry Bahner, AT&T Jonathan Spangler, AT&T Sharon Van Meter, AT&T Donna Osborne-Miller, AT&T Jill Martain, Qwest Joan Wells, Qwest Ric Martin, Qwest Michael Keegan, Qwest Christine Quinn-Struck, Qwest

Jill Martain presented the following historical values : Total LSRs submitted for AT&T in December for LNP was 15,121. Total Non-Fatal errors issued after FOC , 28. Of those 28, 13 were identified on the same day, 7 next day but within 24-hours, 8 after 24-hours.

Joan Wells discussed: The Service Interval Guide for Resale and Interconnection Services The Matrix for resolving Jeopardy Conditions and Effect on the DDD. The Qwest Ordering Screening Process The root cause for PON ZXDNV25275001 TN 303 463-0715 See attached PDF file "CR5582295 Interval Guide & jep matrix" which documents the above.

Joan Wells will revise the Qwest response to reference the discussion outlined in 2.2. The Qwest response will also indicate the desire by Qwest to work with AT&T to minimize changes to the AT&T FOC’d DD.

-

02:00 p.m. (MDT) / Thursday 31 January 2002

Investigate top reasons for error condition after FOC

Terry Bahner, AT&T Jonathan Spangler, AT&T Sharon Van Meter, AT&T Donna Osborne-Miller, AT&T Tim Boykin, AT&T Vernise York, AT&T Cynthia Linenberger, AT&T Ed Longstreet, AT&T Kerri Burke, AT&T Cheryl Moilanen, AT&T Scott Eicher, AT&T Jill Martain, Qwest Joan Wells, Qwest Ric Martin, Qwest Michael Keegan, Qwest Brandi Bentley, AT&T

Jill Martain provided a recap on the progress of CR 5582295 and Systems CR SCR 092601-1 stating we are still moving forward with a February 18 implementation. The process change will discontinue sending a non-fatal error notice after a FOC if an error condition is identified, and will send a jeopardy notice instead. If the error condition is identified within 24-hours, only a jeopardy notice will be sent. If it is after the 24th hour, a courtesy call (for LNP only) will also be made to notify the CLEC of the error condition. Clarification was made it is a courtesy call and the jeopardy notice is the official notification of the jeopardy condition. Jill further explained that if the jeopardy condition was responded to within 4-hours the orders would remain in the system and if no response was received the service orders would be canceled but the LSR would remain in a jeopardy condition for 30-business days. If at the end of 30-business days the LSR is still in a jeopardy status, the LSR would be rejected back to the CLEC..

Jill explained that the error report indentified several types of rejects. AT&T asked if Qwest had an idea of what the numbers were. Jill advised that she did not have time to review the details. AT&T asked for a listing of the areas of the error and the numbers. Jill explained that some problems came about when the order was pending disconnect then the Quality Checkers would notice a retail dissconnect that came through. She also indicated that some problems occur when there is a dfferent address then the one on the LSR.

AT&T asked if Qwest would honor the due date if AT&T issued their Sup. Qwest indicated that it was dependent on the time the Sup came in. Qwest clarified the process advising that when an error condition occurs after an FOC, Qwest will send a Jep notice, not a non-fatal error. The Jep would be sent back the same way the request was received (i.e. EDI, fax, etc.). Qwest explained that the LSR Order will stay in Jep status for 30 days. Qwest will only Jep the order in the first 24 hrs. On the 25th hour, Qwest will send the Jep and place a call. Qwest needs the Sup turnaround within 4 hrs and Qwest will respond in 24 hours after receipt of Sup. Qwest would issue an FOC, which would start the calculation over. AT&T advised that Qwest should still honor the due date if the Sup was issued within the time interval, especially if the Jep was due to a Qwest error. AT&T suggested that we have another meeting to address this question.

Joan Wells discussed the quality check process. A quality check typically takes place within the first day after the FOC. Qwest cannot commit to this timeframe due to potential volume and resource issues.

A question was raised on whether AT&T could have the Due Date. It was clarified that this would be only for LNP. Joan Wells indicated that she would have to go back to the team.

Qwest provided the root cause for the TN example that AT&T provided . The initial reject was due to a wrong address; however, that was corrected by AT&T Broadband. All following actions were the result of a Qwest agent mishandling this order after that FOC was sent. Joan Wells said this person was individually coached.

Action Plan Qwest will review the due date issue and revise its response to CR 5582295 as required. Qwest will pull historical data to identify the percentage of AT&T LSRs that are receiving an error condition after a FOC.. Qwest will set-up another meeting for Friday, February 8, 2002, from 2:00 PM to 4:00 PM. The manual process for all products associated with SCR 092601-1 is scheduled for implementation on 2/18

--

November 6, 2001 AT&T Reply to Final Response dated 10-24-01 Joan Wells Qwest LNP Process Manager

RE: CR Form #5582295

AT&T has stated in previous correspondence to Qwest and at the monthly CMP Product and Process forum the seriousness surrounding Qwest’s process to send a FOC then fatal reject it without notification to the CLECS. AT&T understands Qwest’s current process providing a 4-hour window for response to a non-fatal error notice. However, examples have been shared with Qwest on weekly calls where this process continues to fail. Therefore, AT&T expects Qwest to adhere to its commitment to allow a jeopardy notification after a FOC instead of a non-fatal error after a FOC as submitted under SCR092601-1. This was presented as a walk on at the October 18 Systems CMP meeting by Jill Martain as a candidate for the IMA 10.0 release scheduled for 2002. The CLEC community unanimously agreed to include the LNP product for this CR. Jill Martain concurred.

In regards to AT&T system changes, AT&T anticipated the need to update their IBICS system only after Qwest discounted the use of jeopardy codes on previous calls. When Qwest announced they would pursue using jeopardy codes (Loretta Huff calls August 31, 2001 and September 5th respectively) and informed AT&T that system changes were not required, AT&T did not pursue modifying IBICS since it is currently capable of handling jeopardy codes. AT&T OSS anticipates the upgrade to IMA 10.0 with SCR092601-1 to resolve this issue.

In the interim, AT&T expects Qwest to continue to follow its current 4-hour window process and make every effort to call AT&T Broadband before issuing a fatal reject. AT&T also expects Qwest to socialize this process with all centers directly involved with the LNP process with special emphasis on the Sierra Vista and Phoenix Centers and the duty supervisor in any Qwest Interconnect Center which provisions AT&T Broadband LSRs.

AT&T does not believe this CR has been fully addressed until SCR092601-1 can be implemented or Qwest discontinues its process of fatal rejecting an LSR without CLEC notification.

Sincerely, Terry Bahner AT&T Local Services – LSAM Western Region

CC: Sharon Van Meter Tim Boykin Donna Osborne-Miller Mitch Menezes

September 14, 2001

Lorna Dubose LNP Wholesale Product Manager Qwest Communications 1801 California Street Denver, Colorado 80202

RE: Your letter dated September 5, 2001 regarding change request 5582295 – Cancel after the FOC

Dear Lorna:

Qwest has forwarded two proposals to AT&T. The first was discussed with Loretta Huff from Qwest on Friday, August 31st. The second proposal, Qwest letter sent September 5th, was based on Qwest changing its process and AT&T making changes to IBICS. Ms. Huff, in a conference call, indicated to the CLEC community that Qwest would utilize jeopardy codes on local service requests to alert the CLEC community when an LSR is rejected.

Qwest has taken an action item to internally review which process will be the final resolution to CR 5582295. AT&T has stopped all plans to augment its EDI system based on Ms. Huff’s proposal. AT&T believes the CR has not been sufficiently addressed. Please let me know when Qwest would like to schedule a conference call to discuss the final resolution for CR 5582295.

Sincerely,

Terry Bahner Supervisor Local Services Access Management Western Region

CC: Tim Boykin Sharon Van Meter Mitchell Menezes

Internal Response Clarification Meeting (9/10/01 3:30 p.m.)

Attendees: Joan Wells, Mark Coyne, Jill Martain, Todd Mead, Michael Buck

Mark and Jill explained the context of the Loretta Huff process. Joan provided information regarding Qwest response provided to AT&T. It was determined that the already provided Qwest response was probably accurate and not affected by the Loretta Huff response. However, Joan took an action item to review the Loretta Huff process. Following the review, Joan will update the CR response as necessary.

Action Items:

- Jill Martain to provide Joan Wells with the Loretta Huff process given to the CLECs - Joan Wells to review process and update CR response as necessary (target due date: 9/26/01)

September 7, 2001 2:15 p.m. Attendees: Terry Bahner (AT&T), Donna Osborne-Miller (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Joan Wells (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) Before the Qwest response was presented AT&T indicated that the information contained in the response was contrary to information presented in another meeting held on September 6. Because of this inconsistency, AT&T requested that Qwest clarify the response before AT&T would accept it. Terry Bahner did confirm that the incidence of this situation (i.e. rejection of LSRs after FOC) had been much reduced since installation of IMA 8.0. However, Terry indicated that she was aware of a few situations where an LSR was rejected after FOC. Joan Wells and Lorna Dubose both reiterated that according to guidelines in the PCAT there were some situations in which rejects might occur after an FOC. To rule out system bugs or non-compliance with process Terry will provide examples to Lorna for investigation

Action Items: - Mike Buck (Qwest) to gather additional data from Judy Schultz (9/7) -- completed 9/7/01 - Mike Buck (Qwest) to schedule meeting with Loretta Huff (Qwest), Mark Coyne (Qwest), Joan Wells, and Lorna Dubose (9/10) -- completed 9/10/01 - Qwest to formalize single consistent response to this request (9/12) - Terry Bahner (Qwest) to provide Lorna Dubose (Qwest) examples of rejected requests after FOC (9/14)

Monday, August 27, 2001 1 p.m. Attendees: Terry Bahner (AT&T), Sharon Van Meter (AT&T), Lorna Dubose (Qwest), Michael Buck (Qwest), Todd Mead (Qwest) Terry confirmed that initial indications are that IMA 8.0 fix seems to be working; original problem has occurred only once since IMA 8.0 release. Further testing is still required, but Terry is please with the results. Terry will continue her efforts to confirm/test recent change and report to Lorna as necessary. Terry also provided further information on a second aspect for this CR. Concurrent with the change to IMA, another change was made to AT&T’s IBICS system. The IBICS system change required some coordination with Qwest systems that resulted in the involvement of Cim Chambers (among others). At this point, AT&T recognizes a system change is required in order to receive the final reject from Qwest. AT&T has asked its vendor to supply the patch. The estimated time the patch will be ready is within 30 days. No systems changes have been made at this point in time to recognize a final reject after a FOC. Evaluation will begin once the patch has been installed. Like the changes to IMA 8.0, AT&T needs to evaluate the fix for its efficacy. Terry does not anticipate any further action needed by Qwest to support either the Qwest IMA changes or the AT&T IBICS changes. But until AT&T installs patch and completes confirmation testing Terry would like this CR to remain open. The time frame for observation is dependent on the system patch and Qwest’s newly adopted process to consistently call the Broadband centers prior to the final reject. Allowing AT&T Broadband a four hour window to change or cancel the LSR. Terry also expressed concern that AT&T’s new system, Launch Now, might have the same limitation that resulted in the changes to IBICS. However, Terry agreed that should problems be identified with Launch Now, she would open a new CR to address any Qwest involvement that might be required to support AT&T’s modifications to their system. Action Items: - Terry Bahner (AT&T) to provide Michael Buck with e-mail of Qwest contacts involved with IBICS issue (completed 8/28/2001) - Michael Buck (Qwest) to contact Qwest contacts involved with IBICS issue to confirm no further Qwest involvement needed (completed 8/30/01) - Terry Bahner (AT&T) to provide Lorna with any additional feedback on the results of AT&T confirmation testing for recent IMA changes. Terry to provide confirmation testing results feedback based on when the patch has been installed by AT&T’s vendor. The estimate is 30 days. Terry will provide Qwest a tentative date no later than September 19th CMP if patch has not already been installed. If no issues are identified as part of AT&T confirmation testing, CR to be subsequently closed.

LNP Meeting Notes - 8/13/01

Attendees: Lorna Dubose Matt Rossi Terry Bahner Donna Osborne-Miller

- AT&T getting rejects after FOC - They are not seeing the cancel notification/no phone call – cannot act on 4 hr interval for action - AT&T report that they are still receiving rejects - Terry to get examples of rejected LSRs from the Denver Center (PON numbers) to Lorna and Joan


CenturyLink Response

See revised response dated 03/21/02 with updated matrix (listed as supplemental information)

October 24, 2001 Wholesale Product/Process Ms. Terry Bahner AT&T Communications

This letter is in response to CLEC Change Request Form #5582295, dated June 6, 2001, title of change: Qwest does not cancel LSR after confirming FOC via pending “C’ order. This Change Request pertains to CLEC receipt of an order request cancellation, after having already received a Firm Order Confirmation (FOC). One resolution of this Change Request is specific to LNP Port Out and involved an update to a Qwest internal system. Qwest business process in the IMA 8.0 release was deployed effective August 20th, 2001. A check for pending orders on LNP Port Out requests will now be made, before the FOC is issued. If a pending order exists, the order is placed for manual review.

Additionally, Qwest examined our exception handling processes, including the notifications issued by Qwest in exception situations. The analysis revealed that current Qwest processes sometimes resulted in a non-standard series of notifications, such as an FOC after a reject notice or an FOC after an LSR completion.

To address concerns about exception handling processes, a call was held with a small number of CLEC’s on 8/31/01 to solicit their input on Qwest’s current process. After considering the input that was provided, Qwest is taking the following current actions:

In those cases where an error is discovered after an FOC is sent, Qwest will continue to follow its current process of following the non-fatal reject process. This process was documented in a notice issued on 7/26/01. The process was also documented in IMA EDI 7.0 Disclosure, Addendum #6, released on 8/30/01 and in IMA EDI 8.0 Disclosure, Addendum #1, released on 9/04/01. The current versions of the disclosure documentation states that the CLEC has 2 hours to respond to the non-fatal error notice.

A documentation notice will be sent 9/24/01 indicating that in the situation where an FOC has been sent in error, a 4-hour window will be given for responding to the non-fatal error notice. The EDI Disclosure document will be updated following resolution of the Change Management Process (CMP) Change Request (CR) described below. (Product Specific to LNP, Qwest will allow a 4-hour window for response to a non-fatal error notice, whether or not the FOC has been previously sent.)

Due to CLEC input during the 8/31/01 call requesting a different process be followed, Qwest has opened a CR through the Change Management Process (CMP) for CLEC consideration. The purpose of SCR092601-1 will be to address the process of sending jeopardy notifications instead of following the non-fatal reject process, once the FOC has been sent to the CLEC.

Currently there are internal system limitation’s involving the inability to send jeopardy notification’s in association with Local Number Portability service order requests. This system change is being looked into with completion of the change request SCR092601-1. There is no time frame available for this system change at this time.

Local Number Portability Service Order requests will continue to follow the non-fatal reject process until such time that a system change can be implemented.

Related to this Change Request, AT&T had anticipated the need to update their IBICS system. In response to this perceived need Qwest previously provided systems expertise and answers to questions in support of AT&T planning efforts for intended modifications to their IBICS system. In a status update meeting held on August 27, 2001 AT&T indicated that no further Qwest support was likely to be needed in support of AT&T’s IBICS system modifications. Furthermore, in a letter dated September 14, 2001, AT&T has indicated that all plans to augment its EDI systems have been halted. Should AT&T elect to make IBICS system modifications, Qwest believes that the necessary information has already been provided. The change to Qwest process (via IMA) and the potential change to AT&T’s IBICS system will need to be evaluated to ensure their effectiveness. This confirmation testing effort is the responsibility of AT&T. Qwest understands that AT&T will notify Qwest of any issues that arise during testing of these changes, should they occur. However, it is noted that upon implementation of the new jeopardy process after FOC, that AT&T system changes may no longer be necessary.

It is anticipated that no further Qwest involvement is necessary with regard to this Change Request and that further involvement will center around SCR092601-1.

Sincerely,

Joan Wells Process Manager Local Number Portability

CC: Mark Coyne Loretta Huff Michael Belt Jill Martain Lorna Dubose Margaret Bumgarner Michael Buck Todd Mead


Open Product/Process CR 5582318 Detail

 
Title: Decommission process
CR Number Current Status
Date
Area Impacted Products Impacted

5582318 Completed
11/14/2001
Pre-Ordering Collocation
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Nelson, Steve
Director:
CR PM:

Description Of Change

Qwest has recently changed their Collocation Decommission Policy. AT&T objects to the fact that Qwest made this process change unilaterally – without the input of AT&T. Objections that AT&T has regarding the new policy are:

·1: A certified letter - stating that either no customers were ever installed in the collo or if customers were installed, AT&T has notified them their service will be disconnected or moved - and a copy of the decommission application must to be sent to the Account Team Representative. Prior to this process change, AT&T was not required to do this. We have processed approximately 10 decommission applications so far this year and have not sent a certified letter for any of them.

Resolution: AT&T wants to send the application via email only as before.

2. The decommission process reads "The completion of a decommission request and 100% payment of any outstanding financial obligation, will terminate the billing of recurring charges for the site." What this means to AT&T is that we should be current on any bills for the collocation we are decommissioning. What this means to Qwest is that if there is any outstanding bills - either non recurring or recurring - due for any collocation in Qwest territory, they will NOT process the decommission application until all bills for all sites are paid. AT&T may incur additional monthly charges for the collocation being decommissioned since the application is on hold.

Resolution: It is AT&T’s request that only the non recurring and recurring bills for the collocation being decommissioned be subject to scrutiny.

3. Since Qwest charges AT&T a flat fee to decommission a site, AT&T has inquired about the possibility of conducting a site visit to ensure that Qwest has completed the decommissioning of the site. Qwest has denied AT&T this final site visit. Although Qwest may disconnect power cables, conduct a site visit and complete database work, they do not actually tear down the actual site. Qwest is hoping to lease the space to another CLEC and will not have to rebuild the space. Qwest assures AT&T that if the space is leased within a year of the decommissioning, AT&T will reimbursed some monies for the collo space.

Resolution: AT&T would like proof that the work has been completed.


Status History

06/06/01 - CR received by Donna Osborne Miller of AT&T

06/07/01 - Status changed to New – to be evaluated

06/25/01 - Status changed to Reviewed – Under consideration

06/25/01 - Revised CR submitted by AT&T

07/09/01 - Completed Draft Response

07/12/01 - Drafted Response sent to CICMP team via email (MR)

07/27/01 - 90 day review process for Joint Planning process for Cancel ,Decom and change of Responsibility Offering letter distributed.

08/09/01 - Proposed meetings for a collaborative re-design of the Collocation Cancellation, Decommission, and Change of Responsibility product offerings began. Meeting notice sent on July 27th with a reminder sent August 6th.

09/12/01 - Joint planning meeting held, chaired by Steve Nelson

09/14/01 - AT&T verbal notice received from Sharon Van Meter to not close this CR as the Decommission process is still being worked on.

09/19/01 - CMP Meeting - Qwest provided status of CLEC meetings to develop the process.

10/10/01 - Template agreement to be finalized with AT&T, chaired by Steve Nelson.

10/17/01 - CMP Meeting: Steve Nelson to finalize decommission policies and procedures with CLEC community. No status change.

10/31/01 - Qwest response submitted to database CLEC Community.

11/14/01 - CMP Meeting - AT&T moved to "Close" CR.


Project Meetings

New Interim Procedures to Terminate or Decommission An Existing Collocation Site

As a result of your feedback concerning Qwest’s recently issued Decommission procedures for existing Collocation sites, Qwest is adopting an interim plan for 90 days. During this interim 90-day period, Qwest will hold a series of meetings and conference calls with the industry to develop mutually acceptable procedures to follow concerning this issue. Please review the interim changes and the calendar of meetings below. We sincerely hope that you will participate.

Interim Changes Effective August 9, 2001 • Qwest will no longer issue a Quote of $3455 for each decommission before monthly recurring billing stops.

Qwest is waiving the Decommission Quote charges effective immediately with issuance of this announcement. Future pricing will be reviewed as part of the “Future Procedures Modifications Process” as described below.

• Qwest will credit past decommission quotes paid and any monthly charges paid past the date of acceptance of the valid application. CLECs can contact their Wholesale Project Manager regarding past decommissions processed or currently being processed.

• The vacating CLEC submitting the “Collocation Application for Cancel, Decommission, or Change of Responsibility” will no longer be required to be current on all billing for all collocation sites, including both monthly and non-recurring quotes before Qwest will process a decommission request.

• The interim requirement will state that a CLEC must be current on “all billing for the specific site for which the decommission application is submitted” for Qwest to decommission a site.

• Qwest will no longer require receipt of the quote charges to stop billing. Monthly billing will stop effective with the valid receipt of a decommission application.

• Applications will no longer need to be sent via certified mail for processing. “Electronic submission of requests to decommission a site can be sent to colo@qwest.com”

Future Procedures Modifications Process Qwest intends to issue future procedures that are acceptable to those parties concerned. For Qwest to implement satisfactory procedures, CLEC feedback is needed and valued. At the completion of this joint 90-day effort, the revised product procedures will be priced, and if appropriate, a template offered by Qwest for an amendment to the CLEC/Qwest

Interconnection Agreements. Please join Qwest in participating in the following calendar of meetings. These meetings will be chaired by Steve Nelson, Group Product Manager Collocation. He can be reached on 303-896-6357. Interested CLECs are encouraged to participate.

Kick-off meeting

August 9th, from 9am to 3pm, 1801 California, Executive Conference room, 23rd floor. Conference bridge: 877-542-1778, pass code 6904985.

1. Review existing product offerings and proposed changes, gather information on additional proposed changes, understand all concerns. Here is a brief outline of the discussion: 2. Agree to as many items as possible initially, table for future review those items requiring detailed response, and respond to disputed items by next meeting for resolution. 3. Capture voting record of participants on each issue, and dissenting opinion as agreed to by the team. 4. Prioritization of changes and timelines. 5. Review costing of current products. Items included in the costing model. 6. Discuss how other ILECs handle cancellation, decommission, change of responsibility or network transfer.


CenturyLink Response

"The below response does not include the attachments referenced in the response. Please see the CMP Web Site for complete response to include Cancellation and Decommissioning Procedures"

October 31, 2001 Sharon Van Meter Manager, AT&T 1875 Lawrence St., 10th floor Denver, Colorado 80202

CC: William Campbell Steve Nelson Jane Lacy

This letter is in response to CLEC Change Request Form #5582318, dated June 25, 2001. This Change Request pertains to several issues regarding the Decommission product offering. On July 9th Qwest committed to partnering with the CLEC industry to resolve the issues identified in the Change Request Form specifically referring to decommission procedures. In addition, Qwest expanded this effort to review the product offerings for Cancellation, and Change of Responsibility. Throughout the month of August, September and October representatives from Qwest and the CLEC industry met to review the procedures for administering a Cancellation and Decommission request. The Qwest/CLEC Forum meetings will continue as we work together to revamp the Change of Responsibility product offering procedures. Successful resolution was achieved for those items addressed in the Decommission Change Request Form. Your efforts were instrumental in this partnership effort.

The following is a summary of the issues identified in the Decommission Change Request Form and the resolution for each: AT&T objected to process changes unilaterally without input from AT&T. Qwest committed to participate in a joint effort to review the Cancel, Decommission, and Change of Responsibility product offerings with CLEC industry and met that commitment. AT&T objected to the requirement to submit a certified letter stating that AT&T customers were notified of the disconnect or move. Qwest agreed to modify the process and allow both the application and confirmation notice to be sent electronically to the rfsmet@qwest.com mailbox. AT&T objected to the requirement that 100% payment of any outstanding financial obligation must be met in order to terminate billing of recurring charges. Qwest modified the procedures to state that financial obligations must be met with respect to the collocation site that is being decommissioned only. We further defined the financial obligations to include all non-recurring and monthly recurring charges must not be greater than thirty (30) days past due. AT&T objected to when the monthly recurring charges would cease. Qwest agreed that the billing end date will coincide with the date of a valid Decommission Application submit date. AT&T felt that they should be entitled to some monies for reimbursable elements at the Decommission site. Qwest agreed that a CLEC would be eligible for reimbursement on the re-usable elements for up to one (1) year from the Decommission Application submit date.

The following is the implementation schedule for the revised Cancellation and Decommission procedures: 11/15/01 - CMP Notification 12/01/01 - CLEC Review Period 12/15/01 - Revised Cancellation and Decommission procedures posted on the Collocation PCAT 01/01/02 - Effective date for the revised Cancellation and Decommission procedures

In summary, Qwest believes that we have satisfied your concerns regarding the Decommission and Cancellation procedures and therefore are considering this Change Request closed.

Sincerely,

Steve Nelson Group Collocation Product Manager


Open Product/Process CR PC021903-1CM Detail

 
Title: Change to Section 8.0 of the CMP Document
CR Number Current Status
Date
Area Impacted Products Impacted

PC021903-1CM Completed
4/15/2009
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Buhler, Dean
Director:
CR PM: White, Matt

Description Of Change

AT&T believes that in Section 8.0, under the heading, "Application to Application OSS Interface", the language should read as follows: In the event that IMA EDI major releases are implemented more than six months apart, any CLEC desiring to delay retirement of the previous release should submit a CR requesting the delay. Qwest will review and grant the retirement delay up until the required test window for the next Major Release. The second sentence should be changed to read as follows: Qwest will review and grant the retirement delay up until sixty days after the Release Production Date for trhe next Major Release.


Status History

02-20-03 - CP presented at the CMP Systems Meeting

02-25-03 - AT&T submitted redlined language illustrating requested change

03-11-03 - Ad Hoc Meeting

03-16-03 - Discussed at CMP Meeting

04-19-03 - Discussed at CMP Meeting

04-28-03 - Vote Meeting

05-16-03 - Ad Hoc Meeting

05-20-03 - Vote Notification distributed

05/21/03 - Discussed at CMP Meeting

05-27-03 - Passed by unanimous vote at Ad Hoc Meeting


Project Meetings

CMP Meeting 06-18-03

White-Qwest stated that the change was implemented on 5/30. Quintana-CPUC asked if the new language was in the PCAT. White-Qwest stated that he would find out and send Quintana an e-mail. ======================================= 05-21-03 CMP Meeting

White-Qwest provided a status.

======================================== Ad Hoc – Vote Meeting Minutes 05-27-03

Attendees Matt White – Qwest Rene Albersheim – Qwest Wendy Green – Qwest Lori Mendoza - Allegiance Liz Balvin – MCI Mike Zulevic - Covad Sharon Van Meter – AT&T

White-Qwest described the purpose of the meeting, explained that the standard for quorum was 6 carriers and stated that the voting standard was unanimity. He stated that Qwest had received Eschelon’s vote ahead of time and that with it, quorum had been established. He asked if there were any questions. There were none.

White-Qwest opened the balloting. The carriers on the line all cast their vote by voice as follows:

Qwest – Yes Allegiance – Yes Covad – Yes MCI – Yes AT&T – Yes

White-Qwest stated that Eschelon’s e-mail vote was ‘Yes’ the CR had passed by unanimous vote. He asked how the change should be implemented. Van Meter-AT&T stated that AT&T would like it implemented with a Level 1 Notification. There were no objections. White-Qwest thanked the attendees and adjourned the call.

=====================================================

Ad Hoc Meeting Minutes 05-15-03

Attendees Wendy Green – Qwest Matt White – Qwest John Finnegan – AT&T Lori Mendoza – Allegiance Liz Balvin – MCI Stephanie Prull – McLeod Bonnie Johnson – Eschelon Monica Avila – Vartec

White-Qwest welcomed the attendees and describes the purpose of the meeting. He asked if any of the participants had comments about the proposed language.

Balvin-MCI stated that her concern is that the way the language is written, Qwest can mess up the migration immediately before the sunset date and the CLEC can be left high and dry. Green-Qwest stated that by the time the release sunsets, Qwest will have migrated many CLECs. Similarly, Qwest tries not to schedule any migratations on the last weekend to allow for a week of cushion. Balvin-MCI stated that the possibility still exists for Qwest to require a CLEC to use the GUI. Finnegan-AT&T stated that MCI’s issue is that they may not be up and running on the new release in time. He stated that the language that was added addresses the possibility of stopping earlier than the 60th day. Balvin-MCI stated that her biggest concern is that there is nothing in the language that covers the CLECs if Qwest has any fault in the reason that the CLEC hasn’t successfully migrated. She asked what would happen if MCI realizes that, after migration, there are issues that are Qwest’s fault. She asked what the CLEC’s recourse was at that time. White-Qwest stated that Balvin’s concern was not within the scope of this CR. He stated that this CR was originated by AT&T to allow CLECs to skip releases, not to discuss the finer points of migration difficulties. Balvin-MCI stated that this doesn’t get to the point of telling the CLECs that they would need to get the GUI if they failed to migrate to the new release. Finnegan-AT&T stated that it sounded like MCI’s preference would be to extend the release a little further. Balvin-MCI stated that was what she was after if it is a Qwest issue that has fouled up the migration. Finnegan-AT&T asked if MCI was concerned about not being able to get onto the newest release. Balvin-MCI stated that the language as it stands has a hole in it. There is no guarantee that the CLECs will not get high and dry if Qwest messes up the migration. White-Qwest stated that this problem would apply to all situations when a release is sunsetting. He explained that was why it is necessary to do a new CR to address this issue. Finnegan-AT&T stated that the proposed language was originally set up to allow CLECs to skip releases. He stated that MCI is bringing up an additional issue to address what happens if a CLEC cannot get on a release. Balvin-MCI asked if AT&T was comfortable with the language as it sits. Finnegan-AT&T stated that he was comfortable that the language allows AT&T to skip releases. He explained that he shared the concern about the successful migration, but could see that being in a new CR. Balvin-MCI stated that her issue is outside the scope of this CR. She stated that she would want to add new language for normal and extended sunsets. Finnegan-AT&T asked if the team could include language that allowed the release to be extended further. Green-Qwest asked what happened when Qwest technically cannot extend the release any further, because Qwest can technically only support three releases. Balvin-MCI stated that was a good point. She stated that the 60 day retirement delay is usually bumping up against the forth version. She asked if there were ever periods when Qwest intends to do a migration, and has to postpone it. Green-Qwest stated that she has never seen that happen. Balvin-MCI asked if there had ever been a migration that Qwest has messed up. Green-Qwest stated that there had not. Balvin-MCI stated that she recognized that this would be a rare occurrence. She stated that she felt like this language is to cover Qwest and there is a chance for CLECs to be left high and dry. She stated that she did not want to upset the AT&T change request but did not know how to get around covering CLECs in this instance. She stated that language could read “If Qwest is unable to migrate a company, the 60 day retirement extension will be extended to allow the CLEC to successfully migrate.” Finnegan-AT&T stated that he did not know how to address MCI’s concern and move forward with this CR. Balvin-MCI stated that the language as proposed gets to what the CLECs are after. She stated that the other issue will be a separate CR.

Balvin-MCI stated that she would need to get with her internal contacts to develop a new CR. She stated that she was fine if the group voted on this one as it stands.

White-Qwest stated that Qwest would propose a date to vote on the change and distribute the appropriate notification.

========================================

Ad Hoc – Vote Meeting Minutes 04-28-03

Attendees Matt White – Qwest Dean Buhler – Qwest Wendy Green - Qwest Bonnie Johnson – Eschelon Liz Balvin – MCI Lori Mendoza – Allegiance Stephanie Prull – McLeod Donna Osborne-Miller – AT&T

White-Qwest described the purpose of the meeting, explained that the standard for quorum was 5 carriers, and that the voting standard was unanimous. He stated that quorum had been established and asked if there were any questions.

Johnson-Eschelon asked how Qwest kept track of who migrated. Green-Qwest stated that Qwest tracked conversions very quickly. She stated that Qwest wouldn’t retire the release until Qwest knew that all CLECs had successfully converted. Balvin-MCI stated that the language permitted Qwest to retire a release after all CLECs had converted without verifying that the conversions had been successful. She recommended that the language include “If all CLECs have successfully converted from the release.” Johnson-Eschelon recommended that the language include the phrase “successfully converted.” White-Qwest stated that Qwest would take the language back and attempt to address the concern. He explained that Qwest would then schedule another Ad Hoc meeting to discuss the additional proposed language. He stated that following that Ad Hoc meeting, Qwest could schedule a second vote meeting. He asked if there were any questions about the next steps. There were none. White-Qwest thanked the attendees and adjourned the meeting.

=================================================

04-16-03 - CMP Meeting

White-Qwest described the CR and noted that the CMP community needed to vote on the proposed language. Menezes-AT&T stated that this proposed language ensured that a CLEC could skip a release. He also noted that the second timeline would be included in the CMP Document. White-Qwest proposed that the vote be held on 4/28.

====================================================

03/19/03 CMP Meeting

Menezes-AT&T stated that because Buhler was not able to join the call AT&T and Qwest would have an off-line conversation about the Qwest proposed language. White-Qwest stated that he would schedule an Ah Hoc meeting to discuss the agreed-to language with the CMP community.

=====================================================

Ad Hoc CMP Meeting March 10, 2003

Attendees: Matt White – Qwest Wendy Green – Qwest Beth Foster – Qwest Dean Buhler – Qwest Renee Albersheim - Qwest Sue Stott – Qwest Donna Osborne-Miller – AT&T Mitch Menezes – AT&T John Finnegan – AT&T Carla Pardee – AT&T John Berard – Covad Mike Zulevic - Covad Bonnie Johnson – Eschelon Kim Isaacs – Eschelon Lori Mendoza – Allegiance Becky Quintana – CPUC

White-Qwest started the meeting by welcoming the attendees, explaining the purpose of the meeting, and asking AT&T to describe their CR.

Finnegan-AT&T stated that this CR was submitted so the language in the document allowed CLECs to skip on release if they wished. Quintana-CPUC asked if this impacted PO18 or PO19. Finnegan-AT&T stated that he would investigate if the PID description needed to be changed.

Buhler-Qwest stated that having to extend the old release would cause Qwest additional resource requirements and cost. He continued that Qwest did not disagree with the nature of the request but that Qwest was developing additional language to propose to minimize some of the effects of the change. He stated that Qwest would present these proposed changes at the March 19, 2003, CMP Monthly Meeting. Finnegan-AT&T stated that AT&T had no problem with that.

White-Qwest stated that the vote would not be held at the March 19, 2003, CMP Meeting, but the attendees at that meeting would decide when to hold a vote. Menezes-AT&T asked if the vote could be held between monthly meetings. White-Qwest stated that it could.

The meeting was adjourned.


Open Product/Process CR PC022703-5 Detail

 
Title: Subject line for PTA email notification changed.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-5 Completed
7/9/2003
Provisioning UNE-L
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Toye, Deni
Director:
CR PM: Harlan, Cindy

Description Of Change

The subject of the email notification for PTA only reads "PTA". AT&T would like the subject line to include the Qwest contact name, phone number and the PON. Qwest has limited each company to one (1) email mailbox. AT&T has multiple centers using this notification. Today, AT&T has to open each message and read the information contained in the body of the notification. By adding the Qwest contact name, phone number and PON in the subject line, different centers will be able to easily identify which orders are theirs.

Expected deliverable: Change the PTA email notification to include the Qwest contact name, phone number and the PON


Status History

02/27/03 - CR Submitted by ATT

02/27/03 - CR acknowledged by System CMP Manager

3/3/03: Changed from System to Product Process CR and reacknowledged to ATT

3/5/03: Scheduled Clarification call with customer for 3/10 2:30 - 3:30 mst

3/10/03: Held Clarification call with ATT

3/17/03: Emailed Clarification notes and posted to the database

3/19/03: March CMP Meeting Minutes will beposted to the database

4/8/03 - Posted response to database

4/16/03 - April CMP Meeting minutes will be posted to the database

5/9/03 - Notification to advise of change in PTA email subject line

5/21/03 - May CMP Meeting minutes posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database

7/1/03 - QCCC did another test with ATT and Deni advised the test worked. Sharon-ATT will notify me that it is okay to close.

7/9/03 - Sharon ATT advised it is okay to close this CR as the test worked fine


Project Meetings

06/18/03 June CMP Meeting Minutes Deni Toye-Qwest advised CR currently in CLEC Test and all seems to be working okay. Deni asked if Qwest could close the CR. Sharon-ATT advised that ATT has not received any PTA email notifications yet. Deni checked and saw that ATT is set up, so ATT has not needed to be notified of any NDT PTA emails. Sharon agreed she would verify with her ATT contacts and contact Cindy to advise it is okay to close or request another test and then close the CR. LaiLani-MCI asked Deni to clarify when the process is used. Deni advised on LX- - types of service that have signed up for the PTA NDT Notifications.

05/21/03 May CMP Meeting Minutes Cindy Macy – Qwest advised this change was made on May 12, 2003. Deni – Qwest has reviewed the change and no problems have been found. Sharon – ATT will check with her team and potentially close in June. This CR will move to CLEC Test.

04/16/03 April CMP Meeting Minutes PC022703-5 Subject Line for PTA email notification changed

Deni Toye – Qwest advised we will accommodate this Request. Deni reviewed the response and advised Qwest will make this change targeting the middle of May. The NDT PTA email subject line will be changed to include PTA, Initiator Name, Initiator Phone Number and the PON. This will be made as a Level 1 change. This CR will move to Development status.

- 03/19/03 March CMP Meeting Minutes Sharon Van Meter – ATT reviewed and clarified the CR with the CLEC Community. She explained this request will impact all CLEC PTA emails. McLeod advised they support the change and would sign up for PTA notification if the subject line contained the tester name, number and PON. This CR will move to Presented status.

Clarification Meeting PC022703-5 2:30- 3:30 March 10, 2003 1-877-572-8687 3393947#

Attendees Deni Toye Qwest Denny Graham Qwest Brett Fesler Qwest Sharon Van Meter ATT Cindy Macy Qwest

Meeting Agenda:

1.0 Introduction of Attendees Attendance notes

2.0 Review Requested (Description of) Change Sharon ATT reviewed the Change Request with the team. Sharon and Deni discussed what information was requested to be in the Subject Line. Sharon advised the Qwest tester contact name and number and the PON from the LSR. Sharon advised this information would help ATT identify who needs to work the email notification at ATT. This will allow ATT to not have to open each email and determine who to assign it to.

Deni explained that the QCCC center does not divide their testing functions between their testers. Each tester can be assigned any testing job. Deni clarified this as Qwest didn’t understand the purpose of having the Qwest tester name and number on the PTA email subject line. Sharon agreed she would verify this information with her peers. (Sharon did reply after the clarification call that ATT would like the ‘ATT Initiator of the PON and his/her phone number).

Sharon advised that Verizon and Southwestern Bell provides this information on their test verification emails.

Deni asked if ATT wanted this change on just the PTA email or also the Test Results email. Sharon advised she would check on that and let us know. (Sharon replied this applies to just the PTA email)

Deni also asked if the words ‘PTA’ could remain on the email subject line. Sharon advised yes, PTA should remain on the subject line. The request would be to add to the PTA email subject line the ATT Initiator name and number and PON. Example: PTA – Initiator name/number/PON.

Deni confirmed if this change is made it would impact all CLECs.

3.0 Confirm Areas & Products Impacted Provisioning area impacted Unbundled Loop 2/4 wire is the product line that is impacted by this request

4.0 Confirm Right Personnel Involved Attendees are the correct personnel

5.0 Identify/Confirm CLEC’s Expectation PTA should remain on the subject line. The request would be to add to the PTA email subject line the ATT Initiator name and number and PON. Example: PTA – Initiator name/number/PON.

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) Sharon will present this CR at the March CMP Meeting to the CLEC Community Qwest will investigate the request and reply at the April CMP Meeting


CenturyLink Response

For Review by CLEC Community and Discussion at April 16, 2003 CMP Meeting

April 8, 2003

Sharon Van Meter ATT

SUBJECT: Qwest’s Change Request Response – CR # PC022703-5 AT&T Subject Line Change PTA

This is in response to AT&T’s Change Request CR PC022703-5. This CR requests that Qwest change the subject line of the NDT PTA email notification to include the Initiator Name, Initiator Phone Number and the PON.

Qwest accepts this CR. Qwest will have the subject line contain PTA, Initiator Name, Initiator Phone Number and the PON, in that order. Qwest anticipates this change will be made in the early part of May.

Sincerely,

Deni Toye Process Specialist Qwest


Open Product/Process CR PC022703-1 Detail

 
Title: Seeking to reduce the interval of a FOC for the ASR associated with Dark Fiber from day thirteen (13) to day two (2) where Dark Fiber is reserved through the IRI process.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-1 Completed
8/14/2003
Ordering Unbundled Dark Fiber
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Rein, Kathy
Director:
CR PM: Harlan, Cindy

Description Of Change

When requesting Dark Fiber, the CLEC first must submit an IRI (Initial Record Inquiry) order for Qwest to determine if Dark Fiber is available in a specific location and can ask that the fiber be reserved at that time. If Qwest comes back with an answer of "yes" - the fiber is reserved for a specific amount of days. Further along in the process, the CLEC issues an ASR to complete the Dark Fiber ordering process. The interval for completion of the ASR is twenty (20) business days with a FOC being delivered at day thirteen (13). Since the fiber is already reserved and there shouldn't be any facilities issues, AT&T is asking that the FOC be delivered on day two (2) and not on day thirteen (13).

Expected Deliverable:

Reduce the FOC interval for a Dark Fiber order from day thirteen (13) to day two(2)


Status History

02/27/03 - CR Submitted by ATT

02/27/03 - CR acknowledged by P/P CMP Manager

3/5/03 - Contacted ATT and scheduled Clarification Meeting for 3/13/03 3:00 -4:00

3/13/03 - Held Clarification Meeting

3/19/03 - March CMP meeting minutes will be posted to the project meeting section of the data base

4/8/03 - Entered response in database

4/16/03 - April CMP Meeting minutes will be posted to the database

4/29/03 - Notification of SIG changes sent out effective 6/12/03, comment cycle ends 5/13/03

5/21/03 - May CMP Meeting minutes will be posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database

7/16/03 - July CMP Meeting minutes posted to the database

8/4/03 - Left message for Sharon - ATT to verify okay to close

8/14/03 - Sharon advised it is okay to close this CR


Project Meetings

July 16, 2003 CMP Meeting Minutes Kathy Rein-Qwest advised ATT has submitted LSRs and the FOC has been provided. Sharon Van Meter – ATT advised she will check and let Cindy know if it is okay to close this item. She would like to validate internally that the LSRs are processing correctly.

June 18, 2003 CMP Meeting Minutes Kathy Rein advised we implemented the new FOC interval on May 30, 2003. We have processed ASRs using the new 5-day interval. Per Sharon’s request at the May CMP meeting, we did look again at publishing the interval but Qwest has determined this product will follow the existing guidelines in place for OCN products. Kathy Rein asked to move this to CLEC Test and Sharon advised yes. ATT is okay with the response and they have submitted some orders for this product. They will monitor the orders to make sure they get the 5-day interval.

May 21, 2003 CMP Meeting Kathy Rein - Qwest provided status that the interval for UDF was updated in the SIG to reflect 'Individual case basis'. ICB was used because UDF falls into the OCN product line and also matchs the OCN interval. Sharon Van Meter - ATT asked if the FOC would mean that Qwest could provide the service? Kathy explained the FOC does not guarantee service. Sharon asked why is the FOC not published? Qwest replied UDF matches the OCN product line. Sharon requested Qwest to look into publishing an interval in the SIG. Kathy Rein-Qwest agreed she would discuss this with the Product Manager and report back at the June CMP Meeting.

April 16, 2003 CMP Meeting PC022703-1 Seeking to reduce the interval of a FOC for the ASR associated with Dark Fiber from day thirteen (13) to day two (2) where Dark Fiber is reserved through the IRI process

Kathy Rein – Qwest reviewed our response. Sharon Van Meter – ATT asked what the FOC would mean to ATT. Does it mean Qwest will be able to provide the service? Kathy explained the FOC does not guarantee service. The IRI process is a ‘paper process’ and identifies on paper that facilities are available. The way to ensure facilities are available if by performing a field visit. Sharon asked if there is a charge for a field visit and Qwest replied yes. Sharon asked why the FOC would not be published. Qwest replied UDF is on the line of OCN products and OCN has an unpublished date. Qwest advised we will move this CR to Development and provide a target implementation date at the May meeting.

March 19, 2003 CMP Meeting Sharon Van Meter ATT reviewed and clarified the CR with the CLEC community. Sharon said that during the Clarification call Qwest asked if the interval was published by other RBOCs. Sharon advised Verizon and SBC’s interval is not published. SBC verbally gives a 20 day interval with a FOC on day 5. This CR will move to Presented.

Clarification Meeting Thursday March 13, 2003 1-877-572-8687 3393947# CR PC022703-1 Reduce FOC interval UDF

Attendees Sharon Van Meter – ATT Pat Finley – Qwest Kathy Rein – Qwest Janet Leonard – Qwest Cindy Macy - Qwest Title:

Meeting Agenda: 1.0 Introduction of Attendees Attendees Introduced

2.0 Review Requested (Description of) Change Sharon Van Meter reviewed and clarified the CR. Sharon explained the process, as she understands it. The IRI process occurs first. This determines if resources are available and reserves them if available. The CLEC has to have a Collocation in place and this is an augment to the Collocation. Then the ASR gets processed to link to the Collocation. Sharon was given a 20-day interval and the FOC back on day 13.

Janet Leonard – Qwest asked who gave ATT the 13-day interval. Sharon advised the Des Moines person provided the interval (Debbie Mayhan). Janet advised in Minnesota we have 15 orders where we have reserved the dark fiber, we are working on the Collocation piece and then the ASR will be issued.

Pat Finley – Qwest asked what are the FOC intervals for other RBOCs? Sharon agreed to check on. Pat explained her research of other RBOCs finds no one has a published FOC.

Sharon advised Qwest has done a good job, Deb Mayhan has been very helpful.

ATT doesn’t want to get into the order and find out Qwest can’t deliver. The entire up front work is done in the Collocation so why does ATT have to wait for the FOC? ATT wants to make sure they are able to get service especially because they are spending money augmenting the Collocation site.

Pat Finley – Qwest explained when you reserve Dark Fiber it is not a guarantee the fiber is available. This is all based on paper records, which should be accurate, but are not guaranteed. Janet Leonard – Qwest explained the reservations are based on records and ICA language advises the customer they may want to do a field visit to make sure the fiber is available. SGAT 9.7.3.5.

Janet asked what does the CLEC want on Day 2? Sharon advised Confirmation that facilities are available so we do not get down the road and find out facilities is not available. Janet advised a field verification is recommended to guaranteed the reservation and charge associated with this. Pat said the DF request is usually reliable without the Field Verification but not guaranteed. The FOC is issued the day after the Design (DLR) is issued. This still doesn’t guarantee the order won’t go held. Janet recapped the FOC doesn’t guarantee the order won’t go held and we do not have a published FOC on DF in the SGAT.

Sharon – ATT clarified she would like to see a published FOC date which is less than 13 days. ATT doesn’t want to do the work to the Collocation site (add risers etc.) for no reason if they do not get the service.

Janet advised the APOT information is needed for Dark Fiber. There has to be a fiber termination. A copper termination does not work. The Service Interval Guide (SIG) has an ICB interval for OCN services. Dark Fiber does not have an interval and various products do not have a FOC date.

3.0 Confirm Areas & Products Impacted Okay

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation Sharon – ATT clarified she would like to see a published FOC date which is less than 13 days.

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) ATT will clarify / present this CR at the March CMP meeting on 3/19/03. Qwest will meet to review the CR and determine our response.


CenturyLink Response

For Review by CLEC Community and Discussion at the June 16, 2003 CMP Meeting

June 11, 2003

AT&T Sharon Van Meter

SUBJECT: Qwest’s Change Request Response - CR # PC0220703-1 Request to reduce the FOC interval associated with Unbundled Dark Fiber.

This letter is in response to AT&T’s Change Request (CR) PC0220703-1. This CR requests that Qwest reduce the interval of a FOC for the ASR associated with Dark Fiber from day thirteen (13) to day two (2) where Dark Fiber is reserved through the IRI process.

Qwest provided the following response at the April Product Process CMP Meeting and Qwest has implemented the following change:

-Qwest will reduce the design due date to business day four (4) for Unbundled Dark Fiber (UDF) ASRs, thereby reducing the expected FOC delivery return date to business day five (5) - The UDF FOC delivery response date will remain unpublished - The Service Interval Guide will be updated to reflect a ICB FOC interval for UDF

During the May 21, 2003 Product Process CMP meeting ATT asked whether Qwest could publish the interval in the SIG. Qwest maintains our position that all fiber based OCN products have an ICB interval at this time. UDF will continue to have an ICB interval. Product volumes do not support a standard interval at this time.

Sincerely,

Kathy Rein Qwest – Senior Process Analyst

For Review by CLEC Community and Discussion at the April 16, 2003 CMP Meeting

April 8, 2003

AT&T Sharon Van Meter

SUBJECT: Qwest’s Change Request Response - CR # PC0220703-1 Request to reduce the FOC interval associated with Unbundled Dark Fiber.

This letter is in response to AT&T’s Change Request (CR) PC0220703-1. This CR requests that Qwest reduce the interval of a FOC for the ASR associated with Dark Fiber from day thirteen (13) to day two (2) where Dark Fiber is reserved through the IRI process.

Qwest accepts this Change Request with the conditions identified below: * Qwest will reduce the design due date to business day four (4) for Unbundled Dark Fiber (UDF) ASRs, thereby reducing the expected FOC delivery return date to business day five (5) * The UDF FOC delivery response date will remain unpublished * The Service Interval Guide will be updated to reflect a ICB FOC interval for UDF

Reducing the design due date will effectively reduce the expected FOC return by half. Qwest is presently addressing the internal impacts to implement these changes and anticipates implementation by end of second quarter. Qwest requests that this CR move to “development ” status.

Sincerely,

Kathy Rein Qwest – Senior Process Analyst


Open Product/Process CR PC022703-2 Detail

 
Title: Training or Infobuddy or the RPD Database.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-2 Withdrawn
4/15/2009
Product & Process Research
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Orman, Susan
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently Qwest provides a product database known as RPD or Infobuddy. This database is not very user friendly when it comes to finding some products or processes. AT&T requests training, preferably web based or via a conference call, to train CLECs how to better locate information in this database. Such training would be equally beneficial for Qwest and CLECs .

Expected Deliverable

AT&T requests training, preferably web based or via a conference call, to train CLECs how to better locate information in this database


Status History

02/27/03 - CR Submitted by ATT

02/28/03 - CR acknowledged by P/P CMP Manager

3/5/03 - Contacted customer to schedule Clarification Meeting for 3/10 1:00

3/10/03 - Held Clarification Meeting with ATT. ATT advised they will withdraw this CR as during the clarification call Qwest provided helpful information on InfoBuddy/RDB. ATT will try to use the information first and then if need by they will issue another CR or discuss with their Service Managers. I advised Carla she needs to present this CR as withdrawn at the March CMP meeting and then we will change the status if other CLECs agree.

3/17/03 - Emailed and posted the Clarification Meeting Notes

3/19/03 - March CMP Meeting minutes will be posted to the Project Meeting section


Project Meetings

March 19, 2003 - CMP Meeting Minutes Carla Pardee ATT said we had the Clarification meeting and as a result of that meeting she agreed to Withdraw the CR. Carla explained she was having difficulty using RPD. When she would do a search and the Service Manager would do the same search different results would display. Qwest expained during the Clarification call that the CLECs choose their own search engine and this can alter the search results. Carla also clarified that Product terms are different based on what RBOC you are working with, so sometimes you have to search on different terms based on what RBOC you are working with. Bonnie, Liz and Stephanie (Eschelon, World Comm and McLeod) all agreed they have difficulty using RPD. Comments were made stating RPD is not logically arranged. When you use the Table of Contents you can’t figure out where to go. Bonnie explained if you want to find information on Listings you should be able to go to Listings. The categories of Residential and Business are too large.

Sue McNa – Qwest explained that RPD is the Redacted Retail Methods and Procedures. Sue asked what are the CLECs using RPD for. McLeod advised they have been referred to RPD for order examples. Eschelon said for CF variables. Sue advised the Business Procedures, LSOG, and PCATs are the correct document to use for Wholesale information. Sue agreed it seems as if we need to make our PCAT, LSOG and Business Procedures more complete. It was agreed this CR would be closed and an AI would be opened to look at how and why RPD is being used and try to incorporate information CLECs need from RPD but is missing from our PCATs, business procedures and/or LSOG. We will work to direct our customers to our Wholesale Documentation, rather than the redacted retail M&Ps. Additional information provided after the CMP Meeting: Qwest has training in place called ‘Wholesale Web Tour’. This training takes customers through the various documentation contained on the web. This training is currently available to the CLEC Community.

Clarification Meeting 1:00 – 2:00 March 10, 2003

1-877-572-8687 3393947#

PC022703-2 Attendees Susan Orman- Qwest Diane Morrel – Qwest Michael Thompson – Qwest Cindy Macy – Qwest Carla Pardee - ATT Title:

Meeting Agenda:

1.0 Introduction of Attendees Attendance noted

2.0Review Requested (Description of) Change Carla Pardee – ATT reviewed the change request and also advised she is planning on withdrawing this CR but wanted to still talk to us about this so Qwest understands her concern. Carla explained ATT has been referred by their Service Managers to Infobuddy / RPD to find out information about certain subjects/questions they have. When ATT searches the RPD what they see is different that what the Service Manager views. This makes it difficult to discuss the information found as a result of a search in RPD. Carla requested if there was any training on RPD that would help them find the information they are looking for.

Susan Orman – Qwest explained that the ‘search engine’ is not something that Qwest provides. Each CLEC provides their own search engine, which is why the searches sometime deliver different results. There isn’t any training on how to enter search criteria, as this is a standard, yet individual way to query the web.

Carla advised sometimes the product name is different based on what RBOC you are dealing with and this also causes confusion on how to search for product information. The Qwest attendees advised Carla that the CLECs should be able to describe the product and the Service Manager may be able to suggest a few names to search by.

Carla asked about the Table of Contents and said it was not very logical. Michael Thompson explained the TOC was developed by the Retail organization and may not match the Wholesale organization order/view. The Redacted database does not have a sort except by date. The search engine determines how data is sorted/displayed. Diane suggested you look at the data by Product. If the lower level details that you are looking for are offered for more than one product, the data will be available by each product. You could search by many different products and then search again and find the lower level data you need. Diane suggested you filter by Wholesale first, as that will eliminate the Retail data that you may not be interested in.

Carla agreed she would try the suggestions we offered and withdraw her CR. Qwest agreed we would send an internal email to our Service Management team providing them with this concern and clarifications around the RPD, with the intent of them being better able to answer CLEC questions around RPD and Infobuddy.

Cindy advised Carla after the Clarification Meeting that she should present the CR at the March CMP Meeting and move to withdraw it.

3.0 Confirm Areas & Products Impacted Training / RPD

4.0 Confirm Right Personnel Involved Agreed

5.0 Identify/Confirm CLEC’s Expectation Carla will withdraw CR

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) Carla will withdraw the CR at the March CMP meeting


Open Product/Process CR PC022703-3 Detail

 
Title: Request for Medical Expedite Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-3 Completed
2/27/2003
Pre-Order, Ordering, Provisioning, Maint. & Rep UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Sunins, Phyllis
Director:
CR PM: White, Matt

Description Of Change

Currently, Qwest does not provide a process for expediting service requests for medical purposes, see Qwest website at http://www.qwest.com/wholesale/clecs/execscover.html/. The requested process would allow a CLEC to request service expedites when an end user has a medial condition that would require telephone service due to the probability of a medical emergency. This process would greatly benefit all CLECs and end users in need. AT&T does not believe providing this process would require an expensive development process by Qwest. This process is provided in all other ILEC regions nationwide.

Expected Deliverable:

May 2003


Status History

02/27/03 - CR Submitted by ATT

02/28/03 - CR acknowledged by P/P CMP Manager

03/14/03 - Clarification Meeting

03/19/03 - CR Presented at CMP Meeting

04/09/03 - Initial Response sent

04/16/03 - Qwest initial response presented at CMP Meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting


Project Meetings

CMP Meeting 07-16-03

Pardee-AT&T stated that the CR could be closed.

=================================================== CMP Meeting 06-18-03

Sunins-Qwest stated that the change was implemented on 6/5. She asked that the change be moved to CLEC Test. Pardee-AT&T agreed.

========================================================== CMP Meeting 05-21-03

White-Qwest stated that the response to comments was sent 5/20. He recommended keeping the CR in Development until the CLECs had an opportunity to review the final documentation. ==========================================

04-16-03 - CMP Meeting

Sunins-Qwest presented the response. She stated Qwest already had a process in place but that it was not yet documented externally. She explained that Qwest would report on the progress of documenting the policy at the May CMP Meeting. Pardee-AT&T asked what the externally undocumented process was. Sunins-Qwest stated that she would verify the current requirements. (In an e-mail on April 22, Sunins-Qwest communicated to Pardee-AT&T that, on the LSR, there needed to be a “Y” in the EXP field, the LSR needed to be marked for manual, and the Remarks need to be populated with “Medical Emergency.”) The CR was moved into development status.

=============================================

03-19-03 CMP Meeting

Pardee-AT&T presented the CR. White-Qwest asked if there were other CLECs who were interested in expanding this CR to products other than UNE-P. Prull-McLeod stated that she would like to see it expanded to all resale products. Johnson-Eschelon stated that she would like to see it expanded to all unbundled products. Sechser-US Link asked if there was a Qwest department where CLECs can register emergency numbers that would automatically receive priority if there were maintenance and repair orders opened for them. White-Qwest stated that he would find out.

============================================

Clarification Meeting 10:00 AM (Mountain Time) / Friday, March 14, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Phyllis Sunnis – Qwest Michael Whitt – Qwest Joy McConnell-Couch – Qwest Carla Pardee – AT&T Kevin Battin – AT&T

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Pardee-AT&T reviewed the description change. Battin-AT&T stated that Qwest has expedite reasons, but they are directed at business customers. He stated that AT&T needed this option for consumers with medical conditions. He stated that AT&T understands that is not currently available through Qwest.

Sunins-Qwest asked if the only product AT&T was requesting this service for was UNE-P. Pardee-AT&T stated that UNE-P is only one that AT&T was looking for, but she felt that other CLECs would probably request this for additional products at the CMP Meeting.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm AT&T’s expectation. Pardee-AT&T stated that the other ILECs around the country have a process similar to the one AT&T is requesting.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for AT&T to present the CR at the March Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

April 9, 2003

INITIAL RESPONSE For Review by CLEC Community and Discussion at the April 16, 2003, CMP Product/Process Meeting

Carla Pardee AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC022703-3

This memo is in response to AT&T CR PC022703-3. This CR requests a Medical Expedite Process for all resale products. Qwest Response: Accepted

Qwest currently allows CLECs to request medical expedites for both designed (Complex/Resale, Unbundled, etc.) and non-designed products offered by Qwest Interconnection services.

The "medical" expedite reason is not currently contained in external documentation. Qwest is researching the appropriate manner in which to communicate this additional expedite reason and will update the CMP community on the progress of this research at the May 2003 CMP Meeting.

Sincerely, Phyllis Sunins Sr Process


Open Product/Process CR PC022703-4 Detail

 
Title: System solution for the Collocation Transfer of Responsibility process.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-4 Denied
2/27/2003
Ordering Collocation: Physical, Virtual, Adjacent, ICDF Collocation
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Lacy, Jane
Director:
CR PM: White, Matt

Description Of Change

When a CLEC issues an application for the Transfer of Responsibility of a Collocation from one CLEC to another, the assuming CLEC can issue LSRs at any time during the transfer process. However, the assuming CLEC cannot issue any ASR orders; i.e. to augment trunk groups, for fifty (50) calendar days. While AT&T recognizes the fact that Qwest needs to "freeze" its databases and ensure that all circuits are transferred correctly, fifty (50) days is too long and limits the assuming CLEC from augmenting the services in the collocation space. Qwest states that the fifty (50) days "freeze" allows all circuit order changes to be done. Many of these changes are system changes; however, there is also manual work to be done. AT&T is requesting this process to be automated and is looking for a system solution to reduce the interval for the ASR restriction.

Expected Deliverable:

AT&T is requesting that the Transfer of Responsibility for Collocation be automated and a system solution be implemented to reduce the interval for the ASR restriction.


Status History

02/27/03 - CR Submitted by ATT

02/27/03 - CR Acknowledged by PP CMP Manager

03/07/03 - Clarification Meeting

03/19/03 - Presentation at CMP Meeting

04/09/03 - Initial Response Sent

04/16/03 - Qwest initial response presented at CMP Meeting

05/21/03 - Qwest response presented at CMP Meeting


Project Meetings

05-21-03 - CMP Meeting

Lacy-Qwest presented the Qwest denial. Van Meter-AT&T asked if any of the manual work could be mechanized or any of the current mechanized processes done in parallel. Lacy-Qwest stated that she had researched every process and that there was no way to further streamline the system. The CR was closed as denied.

=============================================

04-16-03 - CMP Meeting

Nelson-Qwest presented the Qwest response. Van Meter-AT&T asked if there was no moratorium on LSRs as the minutes indicated. Nelson-Qwest stated that the minutes were incorrect and that there was a 5 day freeze. The CR was moved to evaluation status.

============================================================

03-19-03 - CMP Meeting

Van Meter-AT&T presented the CR. The CR was moved to presented.

=================================================================

Clarification Meeting 3:00 PM (Mountain Time) / Friday, March 7, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Jeff Cook – Qwest Jane Lacy – Qwest Lillian Robertson – Qwest Peggy Englert - Qwest Cindy Kalakis - Qwest Sharon Van Meter – AT&T

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Van Meter-AT&T reviewed the description change.

Lacy-Qwest what is an acceptable timeframe? Van Meter-AT&T was recently in interconnection agreement negotiations with Qwest and had proposed 30 days. She continued that she’d be happy with 21 days.

Robertson-Qwest asked if AT&T had any ideas for ways for Qwest to improve this process. Van Meter-AT&T stated that she’d like to see a script run that automatically updated all the collocation information.

Lacy-Qwest stated that during the 50 day freeze there was no moratorium on LSRs. Qwest agreed that the CLECs wouldn’t have to write ASRs, instead Qwest would write them manually. She stated that this is one step in a long sequential process. Van Meter-AT&T stated that the CLEC was put in a difficult position if it didn’t have enough trunks during this period. She stated the in such a case issuing LSRs didn’t do the CLEC any good.

Lacy-Qwest asked if AT&T would rather issue the ASRs for the DS3s and trunks? Van Meter-AT&T stated that the 50 day freeze had only happened to AT&T once, and that at that time AT&T didn’t have many ASRs to issue. She explained that she was concerned that 50 days is a long time for a company not to be able to issue orders.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm AT&T’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for AT&T to present the CR at the March Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

May 14, 2003

RESPONSE For Review by CLEC Community and Discussion at the May 21, 2003, CMP Product/Process Meeting

Sharon Van Meter AT&T Communications

SUBJECT: Qwest’s Change Request Response - CR #PC022703-4

This letter is in response to CLEC Change Request PC022703-4. This CR is a request by AT&T to automate the process to transfer ASR circuits from a vacating CLEC to an assuming CLEC in order to reduce the moratorium interval to submit ASR orders.

Qwest’s current process that enables the transfer of ASR type circuits from a vacating CLEC to an assuming CLEC requires coordination between several internal organizations that have responsibility for overseeing the updates to the affected databases. The record activity that occurs in the affected databases must be done sequentially and can only progress to the next downstream system once the step has been completed and any errors that were detected have been corrected. ASR orders received during the transfer process could cause the existing circuits that are in the process of being transferred to reject. Additionally, if change orders were processed prior to the completion of the transfer, it could obscure the correct CLEC to be notified in cases of maintenance, blockage, and/or overflow issues. It is a regulatory requirement that Qwest notify the carrier of capacity issues related to blocking.

Responding to a request to transfer ASR type circuits from a vacating CLEC to an assuming CLEC involves the following activities: - Update the billing system with the new ACNA, CIC, BAN, contact information, etc. - Update the TIRKS database with the new ACNA, MCN, BTN. - Update to the call record detail database with the new ACNA. - Update to the trunk record database with the new ACNA. Consideration is also given in the coordination of these database updates so as to avoid usage fallout at the time the bill is generated.

The moratorium imposed on the placement of the circuits is necessary in order to allow time for each impacted database to be updated. In addition there are timing requirements that must be taken into consideration when coordinating the updates to each database. Careful evaluation was given to determine if there were any processes that could be automated, which could reduce the moratorium time frame. Unfortunately an automated solution was not identified. Due to the nature of this type of request, the complexity and coordination involved among multiple systems prohibit Qwest from being able to remove the moratorium on placing ASR orders until the transfer is complete. Qwest respectfully declines this change request for the following reason: Technologically not feasible – automation opportunities, to reduce the moratorium on ASR orders, are not available.

Sincerely, Jane Lacy Product Manager

=========================================================

April 9, 2003

INITIAL RESPONSE For Review by CLEC Community and Discussion at the April 16, 2003, CMP Product/Process Meeting

Sharon Van Meter AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC022703-4

This is a preliminary response regarding AT&T CR PC022703-4.

There are a number of issues to be analyzed in answering this request. For this reason, Qwest would like to move this Change Request into the Evaluation Status to provide a complete answer to this request.

Qwest will provide a status update at the May CMP meeting and will outline their response at that time.

Sincerely,

Jane Lacy


Open Product/Process CR PC022703-6 Detail

 
Title: UNE P to UNE L Bulk Conversion
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-6 Completed
4/15/2009
Ordering, provisioning, Billing Unbundled Loop, UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Urevig, Russell
Director:
CR PM: Harlan, Cindy

Description Of Change

1. PROVIDE ELECTRONIC ACCESS TO AT&T TO CHECK ILEC CFA INVENTORY PER EXISTING CFA PROCESS.

2. PARTNER TO RESOLVE CFA INVENTORY DISCREPANCIES PRIOR TO BULK CONVERSION PROJECT PLAN DEFNITION.

3. AGREE ON FORMAT/PROCESS TO TRANSMIT PROJECT TRACKING PLAN (WHEN AND WHAT).

4. ESTABLISH PROJECT TEAM AND DEDICATE RESOURCES (AT&T AND ILEC).

5. DEFINE "BULK CONVERSION SCOPE" (I.E., LINES PER LSO, LSO’S PER NIGHT).

6. ESTABLISH PROJECT TRACKING NUMBER AND KEY MILESTONES.

7. STANDARD WINDOW OF TIME TO DO BULK CONVERSIONS (POST 5:00 PM LOCAL TIME).

8. ESTABLISH COORDINATION OF BULK CONVERSIONS VIA OPEN CONFERENCE BRIDGE AT TIMES OF CONVERSION.

9. DEDICATED TEAM IDENTIFIED AND CONTRACT DETAIL SHARED (INCLUDE ESCALATION DETAIL - WHO/HOW).

- TECHNICIAN.

- PROJECT MANAGER.

- ESCALATION CHAIN.

10. DEFINE ANY SPECIAL ORDERING INSTRUCTIONS.

11. PROCESS ORDERS VIA SPREADSHEET IDENTIFYING ALL PERTINENT CUSTOMER/LINE DETAIL. NOTE: AT&T WILL PROVIDE ONE LSR PER CUSTOMER LOCATION FOR CONVERSION.

12. ACKNOWLEDGEMENT OF RECEIPT OF SPREADSHEET AND COMMITMENT TO SCHEDULED BULK CONVERSION DATE.

13. IDENTIFY ALL POTENTIAL CUSTOMER/LINE REJECTS IN TIME TO RESOLVE PRIOR TO THE BULK CONVERSIONS.

- BUSY CFA.

- DATA MISMATCH.

- FACILITY QUALIFICATIONS, INTEGRATED SLCs - TIMEFRAME TO AVOID FOC REJECTS?

14. DETERMINE/AGREE UPON LAST DATE TO FREEZE TARGET BULK CONVERSION LIST - 5 DAYS (NO MORE CUSTOMER/LINES ADDED).

15. 24-48 HOURS PRIOR TO CONVERSION PERFORM READINESS TESTS AND RESOLVE ANY IDENTIFIED ISSUES.

- ANI VERIFICATION AT MDF OF NEW CIRCUIT AND EXISTING ILEC CIRCUIT.

- PRE-WIRE.

- LOOP QUALIFICATION TEST.

- DIAL TONE CHECK.

16. AT NIGHT OF CONVERSION:

- PARTICIPATE IN PRE-CUT CALL

- MAINTAIN AVAILABILITY DURING CUTS

- CUT ONE LINE AT A TIME.

- COMPLETE ALL SCHEDULED CUTS AND ACKNIOWLEDGE PROJECT COMPLETION

- RESPOND TO ALL SERVICES OUTAGE CONDITIONS THAT RESULT FROM CONVERSION (WILL ROLL BACK TO UNE-P IF NO RESOLUTION).

17. PROCESS TO RESTORE ALL SERVICE OUTAGE CONDITIONS IDENTIFIED POST-CONVERSIONS.

18. DO NOT INCLUDE P TO L BULK CONVERSION LINES AT ILEC LOSS AND COMPLETION REPORT.

Expected Deliverable:

Modify CR # PC090401-2 with expected process in place with documentation by June 2003.


Status History

02/27/03: CR Received

03/03/03: Acknowledgement sent to ATT

03/05/03: Contacted customer. Discussed proprietary questions and agreed to schedule Clarification Call for March 17, 2003.

03/17/03: Held Clarification Meeting. CR was resubmitted without any proprietary reference.

03/19/03: March CMP Meeting notes will be posted to the database

4/8/03: Posted response to database

4/16/03 - April CMP Meeting minutes will be posted to the database

5/21/03 - May CMP Meeting minutes will be posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database. Agreed to move this CR to Development.

7/8/03 - See PC061803-1 for denial response for items that Qwest will not be implementing from this CR

7/16/03 - July CMP Meeting minutes posted to the database

8/20/03 - August CMP Meeting minutes - see project meetings section

9/17/03 - Sep CMP meeting notes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP Meeting minutes will be posted to the database


Project Meetings

12/17/03 December CMP Meeting Russ Urevig – Qwest provided status and the dates that this process was implemented. Russ asked if it was okay to close this CR. Carla Pardee – ATT advised it is okay to close. Bonnie Johnson – Eschelon asked if the regional Batch Hot Cut process will replace this process? Russ advised yes. John Berard – Covad asked if Line Splitting is also being reviewed by the TRO? Russ advised yes. Carla Pardee – ATT advised they are aware that the TRO will address this process so that is why they are okay with closing this CR. The status will move to Closed.

11/19/03 November CMP Meeting Russ Urevig – Qwest advised the PCAT change was submitted and the comments cycle has ended. This CR will move to CLEC test.

10/15/03 October CMP Meeting minutes Russ Urevig – Qwest advised on September 22 updates were made to the UBL General section. The Notification went out October 2, 2003. The comment cycle ends October 23, 2003. No comments have come in as of yet. Russ asked if we could move this to CLEC Test. ATT requested we leave in Development until the comment cycle ends. The notification dates were reviewed after the October Meeting and it was determined the correct date that the comment cycle ended was October 9, 2003. Carla Pardee – ATT was advised and Carla agreed to issue an informal comment. The status of this project will move to CLEC Test.

9/17/03 September CMP meeting minutes Cindy Macy – Qwest advised the documentation team is currently reviewing the document and they hope to have this out for review by the end of the month.

8/20/03 August CMP meeting mintues Russ Urevig-Qwest advised the document should be available at the end of the month for CLEC review. This CR will stay in Development. Carla Pardee-ATT advised this is okay.

7/16/03 July CMP Meeting Minutes Russ Urevig-Qwest advised that Qwest is continuing to work on all items on this CR except 3, 4, 9, 11, 12 and 18. Qwest is in progress of updating the Migrations and Conversion PCAT to include the Bulk Conversion process and links to existing procedures that support the Bulk Conversion process. Russ advised PC061803-1 was opened to track the denial items of 3, 4, 9, 11, and 12. Item 18 is a system change and if ATT wants to pursue this item they should issue a systems CR. Carla – ATT advised she is okay with this response. This CR will stay in Development status.

6/18/03 June CMP Meeting Minutes Russ Urevig – Qwest explained there are 18 items on this CR and we want to accept the CR and document the bulk conversion process and work together on performing bulk conversions. There are some items that we can’t provide within our process; such as accepting LSRs with a spreadsheet and provided a dedicated team. Other items we will implement. The response provides details for each item. Carla Pardee advised ATT is disappointed with Qwest’s response but we do not choose to pursue it any further. Carla advised the spirit of the request was to process conversions in a bulk manner via a spreadsheet, after hours, with a dedicated team. Qwest is not providing a bulk conversion. Carla advised she will submit a systems CR for the Loss and Completions report. Russ advised we will move forward on the items that we agreed to. Bonnie asked if this is a denial or not. ATT advised they will not pursue this any longer. Kit advised we can open a CR and deny the items we will not provide and move these items into Development. Bonnie advised we need to add language into CMP for a partial denial or change in CR description or create a new status. Bonnie will open a new CR.

5/21/03 May CMP Meeting Minutes Russ Urevig – Qwest advised we have looked at this process and believe we can provide documentation updates and links in the Migrations and Conversion PCAT. There were 18 items listed on this CR. Some of the items requested we can provide and some items we will not be able to provide. A systems CR needs to be issued for item #18. ATT agreed they would look at this. Qwest is still evaluating this CR. Cindy Macy – Qwest will schedule another meeting to review the CR.

4/16/03 April CMP Meeting PC022703-1 UNE P to UNE L Bulk Conversions Russ Urevig – Qwest reviewed the response and advised we are currently investigating what it will take to implement some of the process steps identified in the CR. As a result of our internal meetings Qwest will be able to determine what can be supported and review that process with ATT. Qwest will move this CR to Evaluation status.

03/19/03 March CMP Meeting Carla Pardee ATT reviewed and clarified the CR as a Walk On. This CR is similar to another CR that ATT submitted 1 ½ years ago. We now want to modify the CR and make sure the process is documented as a package for UNE P to UNE L Conversions.

Clarification Meeting March 17, 2003 1:00 – 2:00 PM MST 1-877-572-8687 3393947# PC022703-6

Attendees Carla Pardee – ATT Mitch Menendez – ATT Ervin Rea – ATT Vicki Faber – ATT Lisa Tyler – ATT Lydell Peterson – Qwest Kit Thomte – Qwest Russell Urevig – Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees Introduced

2.0 Review Requested (Description of) Change Carla Pardee – ATT reviewed and clarified the CR. Carla advised ATT does not need this CR to be proprietary and would like to Walk On the CR at the March CMP Meeting. Qwest – Cindy Macy advised that the Service Management team as a Project can handle this CR and does not need to go through the CMP Process. It was agreed we would review the CR and then make the determination on how to handle it.

ATT advised they would prefer to leave the CR in the CMP Process, as they would like the process formally documented. Mitch – ATT asked if Qwest sees this as something unique for ATT? Qwest replied no, most of the items are standard process. We have not done bulk LSO conversion out of hours. Carla asked about #11 – Process orders on a spreadsheet and Qwest agreed that was not a standard item either.

Carla reviewed the CR in detail. #1 – Russ advised today the CLEC has the ability to validate the CFA in the Pre-Order overview – Loop Qual, Appendix F.

#2 – Russ advised the process for resolving a discrepancy of a busy CFA assignment is via Escalations. Mitch asked if this process is documented and Russ advised he would check.

ATT advised they would like to cut down the number of transactions. This is why Bulk Activity is requested.

3-6 no comments

#7 – Window of time to do bulk conversions (post 5pm). Russ advised this might be handled as a CHC – OOH conversions. Ervin advised ATT is not interested in having each one a CHC or paying for CHC. They would want to negotiated this item. Russ advised we do not have a Bulk Rate for cuts. We would have to look into this.

8-10 no comments

#11 Russ advised Qwest would expect an LSR per customer. Ervin advised they would like to process via a spreadsheet. Russ advised our systems would need individual LSRs but the spreadsheet could be used as a backup / tracking document.

12 – 17 no comment

#18 – Do not include lines in the Loss and Completion report. Russ advised the SOPS generate a report today. Any activity triggers items to this report. Ervin explained they do not want to have these accounts show up on the report, as we are not loosing them. Mitch asked if the SOPS would generate a loss and completion report. Russ advised yes, we would have to match the RSID/ZCID, the loss on the UNE P side would occur, and the completion on the UNE L side would occur. Ervin asked if we could use a Project number and identify these on the report. Russ advised this would be a SOP system change. Vicky said she would check on, as they would prefer this not to show on the report. Ervin said we are creating activity but not creating revenue for anyone. It is really a wash in actual customer impacts. Lisa advised ATT is concerned about the message CLECs get from this data showing up on the Loss and Completion report. Russ confirmed the IMA notification would provide enough to show the LSR is complete. ATT asked if the cycle time for the Loss versus the Completion is the same. Russ advised both reports are run at the end of the day. He is not sure if the cycle times are exact to each other.

Ervin advised ATT would like a ‘New Process’ documented to pull this process all together, instead of reviewing multiple piece part processes.

Russ asked if a dispatch to the Demarc would be required – Ervin advised no.

Qwest asked when are the cuts planned? ATT advised most likely Monday – Friday, as Saturday or Sunday would impact cost and resources and overtime rates.

ATT explained they would like one document to use that tells them: How to do this Where to go (what systems to use) Identifies contacts

Cindy Macy Qwest advised ATT that other CLECs may want to provide input to this process. ATT advised that is okay.

3.0 Confirm Areas & Products Impacted UNE P

4.0 Confirm Right Personnel Involved May need to include Monica Manning

5.0 Identify/Confirm CLEC’s Expectation Single Process documented

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) ATT will walk this on to the March CMP Meeting Qwest will meet to determine our response


CenturyLink Response

June 11, 2003

For Review by CLEC Community and Discussion at the June 18, 2003 CMP Product Process Meeting

AT&T Ervin Rea Manager

SUBJECT: Qwest’s Change Request Response - CR PC022703-6 UNE-P to UNE-L Bulk Conversion

This letter is in response to ATT Change Request PC022703-6 UNE P to UNE L Bulk conversion. This CR requests that Qwest provide a process to perform UNE P to UNE L Bulk Conversions within a single LSO for a single CLEC, and document the process on the Wholesale Web site.

This CR has prompted several internal department meetings to discuss the 18 items listed. Qwest agrees with the basic context of the CR and accepts the CR request to create an informational guide section in the PCAT for Bulk Conversion.

This information would be best located in the Migrations/Conversion PCAT, providing direction for both normal hour and out of hour conversion. The information provided will be general rules to follow for planning, scheduling, escalating, monitoring and completing a Bulk Conversion. Product specific information or process specific information on creating requests will be available through links to those respective PCATs.

We have included the 18 separate requests that were made on this CR and we have responded to each item separately. (See below)

Change Description Request: Qwest Response: 1. PROVIDE ELECTRONIC ACCESS TO AT&T TO CHECK ILEC CFA INVENTORY PER EXISTING CFA PROCESS. This functionality currently exists in IMA as a pre-order tool: Validate CFA. Additional information about this pre-order functionality can be found in the Pre-Order Overview PCAT. 2. PARTNER TO RESOLVE CFA INVENTORY DISCREPANCIES PRIOR TO BULK CONVERSION PROJECT PLAN DEFNITION. There is a process for Busy CFA, this process was developed in response to a previous CR 5464735 to handle CFA discrepancies via the escalations desk. This process is called Confirming Busy CFA, links can be found in the Pre-Order Overview PCAT. These links will place you in the Loop Qualification and Raw Loop Data Job CLEC Job Aid. This section will provide step by step information on who to call and the required information to resolve the issues.

3. AGREE ON FORMAT/PROCESS TO TRANSMIT PROJECT TRACKING PLAN (WHEN AND WHAT).

The Qwest process for conversion requires individual LSRs for each end user address. Additional fields on the LSR enable project tracking by the CLEC (e.g., LSR field number 22 PROJECT - Project Identification).

4. ESTABLISH PROJECT TEAM AND DEDICATE RESOURCES (AT&T AND ILEC). Qwest will utilize the current work force trained to handle conversions of this kind.

5. DEFINE "BULK CONVERSION SCOPE" (I.E., LINES PER LSO, LSO’S PER NIGHT). Because Qwest will use the standard process for conversions, no scope definition is required.

6. ESTABLISH PROJECT TRACKING NUMBER AND KEY MILESTONES. The Project Identification field on the LSR is used to keep the requests associated together. The CLEC can populate the project identification field and use this information for their tracking.

7. STANDARD WINDOW OF TIME TO DO BULK CONVERSIONS (POST 5:00 PM LOCAL TIME). This is negotiated based on resources available for out of hour cuts. Normal business hour cuts are based on product type. (e.g. UBL hours of business are 8am to 5pm, for out of hours cut times are 5:01pm to 7:59 am.) The type of installation determines the specific cut time.

8. ESTABLISH COORDINATION OF BULK CONVERSIONS VIA OPEN CONFERENCE BRIDGE AT TIMES OF CONVERSION. Qwest will participate on a CLEC provided conference bridge to advise acceptance of loop, testing requirements, etc. The conference bridge number would be required as the number for the IMPCON contact number. This contact number will flow to the tester as part of the CLEC contact information.

9. DEDICATED TEAM IDENTIFIED AND CONTACT DETAIL SHARED (INCLUDE ESCALATION DETAIL - WHO/HOW). - TECHNICIAN. - PROJECT MANAGER. - ESCALATION CHAIN. Qwest will utilize the current work force trained to handle conversions of this kind. If there is a need to contact the escalation desk, Qwest has defined contacts for each type of escalation. Additional information is located in the Expedites & Escalations Overview PCAT

10. DEFINE ANY SPECIAL ORDERING INSTRUCTIONS. No special ordering instructions are required, as the CLEC will use existing order instructions. These LSRs will follow the normal process by product, with project identification optionally included by the CLEC.

11. PROCESS ORDERS VIA SPREADSHEET IDENTIFYING ALL PERTINENT CUSTOMER/LINE DETAIL. NOTE: AT&T WILL PROVIDE ONE LSR PER CUSTOMER LOCATION FOR CONVERSION. The Qwest process for conversion requires individual LSRs for each end user location. Additional fields on the LSR enable project tracking by the CLEC (e.g., LSR field number 22 PROJECT - Project Identification).

12. ACKNOWLEDGEMENT OF RECEIPT OF SPREADSHEET AND COMMITMENT TO SCHEDULED BULK CONVERSION DATE. The Qwest process for conversion requires individual LSRs for each end user location. Additional fields on the LSR enable project tracking by the CLEC (e.g., LSR field number 22 PROJECT - Project Identification).

13. IDENTIFY ALL POTENTIAL CUSTOMER/LINE REJECTS IN TIME TO RESOLVE PRIOR TO THE BULK CONVERSIONS. - BUSY CFA. - DATA MISMATCH. - FACILITY QUALIFICATIONS, INTEGRATED SLCs - TIMEFRAME TO AVOID FOC REJECTS CLEC’s have the pre-order tools to do this today. We will provide links in the to these existing procedures e.g., Pre-Order Overview PCAT, Loop Qualification and Raw Loop Data CLEC Job Aid, etc. These activities should be done during pre-order to make sure the request meets the requirements for the product ordered.

14. DETERMINE/AGREE UPON LAST DATE TO FREEZE TARGET BULK CONVERSION LIST - 5 DAYS (NO MORE CUSTOMER/LINES ADDED). Conversion interval dates are based upon standard intervals for the product the CLEC is converting to. Refer to the SIG (standard intervals guide) for the product you are converting to.

15. 24-48 HOURS PRIOR TO CONVERSION PERFORM READINESS TESTS AND RESOLVE ANY IDENTIFIED ISSUES. - ANI VERIFICATION AT MDF OF NEW CIRCUIT AND EXISTING ILEC CIRCUIT. - PRE-WIRE. - LOOP QUALIFICATION TEST.

- DIAL TONE CHECK. Existing procedures located in the Unbundled Local Loop - 2-Wire or 4-Wire Analog (Voice Grade) Loop - V15.0 PCAT states: Conversion or Change request with new CFA: Qwest verifies for dial tone at your CFA 48 hours after Qwest's APP (application) date. If Qwest finds No Dial Tone (NDT), Qwest will retest 48 hours prior to due date. If dial tone is still not present, Qwest will email the NDT results to you through Qwest's Provider Test Access (PTA) email system. You will receive the NDT PTA email notification approximately 24 to 36 hours prior to the due date. Qwest will email only when there is No Dial Tone. You will need to supply the dial tone by the due date or supplement the LSR, changing the due date. Performance testing available on 2-Wire or 4-Wire Analog (Voice Grade) Loops is also defined with this PCAT.

ANI – The testing capability is not available 24-48 hours in advance as the line is not available until cut time. .

Pre Wire = Yes Loop Qual = Qwest performs all standard testing to qualify the loop; additional testing will only be performed if requested and would result in additional charges. Dial Tone = Yes

16. AT NIGHT OF CONVERSION: - PARTICIPATE IN PRE-CUT CALL

- MAINTAIN AVAILABILITY DURING CUTS

- CUT ONE LINE AT A TIME.

- COMPLETE ALL SCHEDULED CUTS AND ACKNIOWLEDGE PROJECT COMPLETION

- RESPOND TO ALL SERVICES OUTAGE CONDITIONS THAT RESULT FROM CONVERSION (WILL ROLL BACK TO UNE-P IF NO RESOLUTION). -Qwest always performs a pre-cut call to validate the CLEC is ready for the lift and lay to happen.

-If the CLEC provides a continuous conference bridge number on the LSR, Qwest can provide staff at the start and completion of each cut. Qwest will not stay on the call for 24 hours but will be available when needed.

-Coordinated Hot Cuts (CHC=Y) provide for a specific time if the CLEC would like to request that capability. CHC=N or blank allows the cut to start during normal hours or out of hour conversions.

Roll Back to UNE-P is not an option if the circuit has been accepted by the CLEC. Qwest works with the CLEC in normal lift and lays, until the circuit is accepted. The CLEC needs to make sure the correct translation path is selected to the co-location point prior to conversion. This is normal business operation.

17. PROCESS TO RESTORE ALL SERVICE OUTAGE CONDITIONS IDENTIFIED POST-CONVERSIONS. If there is a need to contact the escalation desk, Qwest has defined contacts for each type of escalation. Additional information is located in the Expedites & Escalations Overview PCAT.

18. DO NOT INCLUDE P TO L BULK CONVERSION LINES AT ILEC LOSS AND COMPLETION REPORT. This item needs to be re-submitted through a system CR; there would be coding changes required on the Loss/Completion reports generated by the service order processors.

Sincerely,

Russell Urevig Sr Process Analyst Wholesale Service Delivery

April 8, 2003

For Review by CLEC Community and Discussion at the April 16, 2003 CMP Product Process Meeting

AT&T Ervin Rea Manager

SUBJECT: Qwest’s Change Request Response - CR PC022703-6 UNE-P to UNE-L Bulk Conversion

This letter is in response to ATT Change Request PC022703-6 UNE P to UNE L Bulk conversion. This CR requests that Qwest provide a specific process to perform UNE P to UNE L bulk Conversions within a single LSO for a single CLEC, and document the process on the Wholesale Web site.

Qwest held a clarification meeting with AT&T on Monday March 17 to discuss the individual items on CR PC022703-6 UNE-P to UNE-L Bulk Conversion. Further clarification of the CR identified this method would include but not be limited to: inventory discrepancy corrections per conversion, test requirements, dedicated resources, conference bridges, conversion volume size, hours of conversions, outage conditions, and Loss and Completion reports.

During our discussion several items were found to be duplicates from a previous CR PC090401-2 which was moved to complete status on March 20, 2002. Qwest identified several items that required additional discussion with several key departments within Qwest, such as Test and Turn-up, Central office Technician, Circuit Design and Product Management.

Qwest has schedule internal meetings to discuss the following items:

*Availability to provide dedicated people to coordinate out of hour cuts for specific LSO’s. (Loop/Local Service/Switching Office )

* Ability to perform pre-cut readiness testing to identify and resolve installation issues.

* Determine quantities per LSO, which can be cut during out of normal hour operations.

* Can cuts occur on a one line at a time basis to minimize problems?

* Can the Loss/Completion reports be stopped, when a CLEC is changing an end user from UNE-P to UNE-L and the CLEC is not changing?

* Installation options and or associated rates with out of normal hours cuts.

These are all items which need to be discussed interactively with departments as re-scheduling of personnel may be require to meet the needs of these conversions. Qwest would like to place this CR in Evaluation Status until we finish our investigation of the items identified above.

Sincerely,

Russell Urevig Sr Process Analyst Wholesale Service Delivery


Open Product/Process CR PC032603-1 Detail

 
Title: Standardization of USOCs across regions
CR Number Current Status
Date
Area Impacted Products Impacted

PC032603-1 Crossover
7/27/2009
Ordering UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Paxton, Mallory
Director:
CR PM: Harlan, Cindy

Description Of Change

Today Qwest requires CLECs to use different USOCs for ordering certain features depending on the territory in which the features are ordered. For example, Qwest requires different USOCs for ordering hunt,ing, speed dial 8 and speed dial 30 depending on whether they are ordered in the western or central regions. AT&T requests that Qwest simplify this ordering process by requiring use of only one standard USOC for features ordered across all regions. By simplifying this process, Qwest would streamline the process and eliminate various opportunities for error, which would benefit both Qwest and the CLEC community.

Expected Deliverable:

3rd quarter 2003.


Status History

3/26/03 CR Received

3/27/03 CR Acknowledged and entered in database

4/1/03 LWTC to schedule Clarification Meeting for 4/3/03

4/3/03 Carla requested to reschedule Clarification Meeting for week of 4/7/03. I have reserved tentative dates of 4/10 and 4/11 for clarification meeting. Carla and I will confirm date on 4/8/03

4/8/03 Carla confirmed to hold Clarification meeting on 4/10/03.

4/10/03 Held CLEC Clarification Call

4/16/03 - April CMP Minutes will be posted to the Project Meeting section of the database

5/14/03 - Sent response to CLEC via email and posted to database on 5/13

5/21/03 - May CMP Meeting Minutes posted to database. CLEC community agreed to not deny this CR but to cross over to Systems for the Hunting / IMA part and open an Action Item to gather additional usocs to have reviewed.

6/5/03 - Changed to closed as AI052103-2 is open to gather additional usoc information to potentially streamline. Agreed to not open a Systems CR until we gather additional information on usocs to potentially streamline.


Project Meetings

05/21/03 May CMP Meeting - Mallory Paxton – Qwest reviewed the analysis that was done on both speed dial and hunting usocs. Mallory advised Qwest is denying this request due to it being economically infeasible. Qwest does suggest a systems CR be opened to request the changes to the hunting usocs be done in IMA. Mallory explained the LSR forms provide enough detail that the system could determine what hunting usoc is needed based on how you fill out the forms. Some products have been standardized by OBF and the LSR forms reflect the details necessary. Carla- ATT thanked Mallory for her investigation and explaination.

The CLECs requested that instead of denying this request we cross it over to systems to work the hunting request as a Systems CR. An Action Item will also be opened to gather and track other products / usocs that could be streamlined. A notification will go out requesting the CLECs to send ‘usocs in need of streamlining’ and ‘top problem usocs’ to cmacy@qwest.com. A meeting will then be scheduled to review the list and determine next steps. Additional CRs may be opened to address items on the list. Bonnie Johnson suggested that Qwest also make a recommendation identifying which usocs could be combined. Call Forwarding / Busy / DA is one example.

4/16/03 April CMP Meeting - PC032603-1 Standardization of USOCs across regions

Carla Pardee – ATT presented this CR to the CLEC Community. Carla explained that on the Clarification Call discussion took place how it may be helpful to identify specific USOCs that ATT would like standardized. She provided Hunting and Speed dial 8 and 30 as the USOCs she would like included in the scope of this CR. Lynn Powers – Tel West added that many CLECs support this CR. Having multiple USOCs is an expense for the CLECs.

Clarification Meeting 9:00 – 10:00 a.m. April 10, 2003 1-877-572-8687 3393947#

PC032603-1 Standardization of USOCs across regions Attendees Anthony Washington – Qwest Carla Pardee – ATT Dusti Bastian – Qwest Anne Robberson – Qwest Laurel Neher – Qwest Cindy Macy – Qwest

Meeting Agenda:

1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change Carla reviewed the CR. Carla explained today there are several features that required different USOCs to be used based on what region and/or switch you are ordering out of. Carla provided examples for Hunting and Speed Dial. The hunting requires HTG for Central and HSO for Western. The Speed Dial requires E8C for Central and ESL for Western. The LSR form / IMA asks you to put the USOC on the LSR. Carla explained this CR is similar to the Call Forwarding Simplification CR. Qwest asked Carla if this request is just for Feature USOCs or Class of Service and Line USOCs also? Discussion took place regarding the USOCs are assigned and provided by Telcordia. Qwest has multiple systems by Region and those systems are set up to require different USOCs. This is driven from when there was a Pacific Northwester Bell, Mountain Bell and Northwestern Bell. Qwest also explained that this request is very large and it may be helpful if Carla was able to identify a set of USOCs that are causing ATT the most trouble. Carla advised she would provide the most critical USOCs and limit the scope of the CR. Carla will provide at the April CMP meeting examples of specific USOCs that she would like to have 1 USOC per feature across the Region.

3.0 Confirm Areas & Products Impacted Qwest asked about the products impacted and Carla advised UNE P. Qwest explained that these USOCs are also used in other product lines such as Retail and Resale. If a change was made to these USOCs it may impact other product lines also.

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation Carla would like specific USOCs to have 1 USOC per feature across the Region. USOCs include (as provided at the April CMP Meeting): Hunting, Speed Dial 8, Speed Dial 30

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) Carla will present this CR at the April CMP Meeting Qwest will provide our response at the May CMP Meeting


CenturyLink Response

May 14, 2003

For Review by CLEC Community and Discussion at the May 21, 2003 CMP Meeting

Carla Pardee AT&T

SUBJECT: Qwest’s Change Request Response – CR # PC032603-1 Standardization of USOCs Across Regions

This is Qwest’s response to AT&T’s Change Request CR PC032603-1 requesting the standardization of the following six USOCs across regions: 1. E8C and ESL (8-Number Speed Calling) 2. E3D and ESF (30-Number Speed Calling) 3. HSO and HTG (Series Hunting)

In evaluating this request, Qwest considered both the technological and the financial impacts of the requested change, and we looked at the two products, Hunting and Speed Calling separately.

The Hunting USOCs are used for billing only—not for provisioning—so Qwest’s network systems would not be impacted by the standardization of these USOCs. The Level of Effort to implement this change for Hunting would be approximately 16,000 hours.

The Speed Calling USOCs are provisioning USOCs and would require changes to Qwest’s network systems as well as the product and process changes needed to implement the Hunting change. The Level of Effort to implement the change for Speed Calling, which reflects the additional costs of network changes, would be approximately 17,000 hours.

This request is denied because it is economically not feasible.

However, Qwest would like to address the difficulty CLECs have in ordering Hunting. Qwest respectfully recommends that AT&T open a Systems CR to have Qwest use the hunting fields on the LSOG 7 HGI form to populate the USOCs on the service order, rather than requiring the CLECs to provide these USOCs in the FEATURE field of the product-specific form. (This would be a solution similar to the solution currently under development for IMA Release 14.0 for blocking USOCs). If AT&T prefers, Qwest can open this CR on their behalf.

Sincerely,

Mallory Paxton Senior Process Analyst Qwest Services Corporation


Open Product/Process CR PC022703-9X Detail

 
Title: Support Production Defect Report (crossed over from SCR022703 09)
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-9X Denied
2/18/2004
All
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Winston, Connie
Director:
CR PM: Harlan, Cindy

Description Of Change

Revised Description of Change - Submitted 08-13-03

AT&T is requesting a report for all known IMA EDI & IMA GUI problems.

This report will be a list of IMA EDI and GUI problems currently

identified either internally identified by QWEST or reported by a CLEC

thru the ISC Help Desk or Service/Account Manager. The report will

identify all open issues that are pending investigations. Once an issue

has been reported and determined to be a problem/clarification/defect

issue it should be noted on the report with the appropriate QWEST

Trouble Ticket # as it goes through the phases within QWEST well before

it makes it to the Event Notification process. Once an event

notification issued for the problem, the notification number would be

referenced on this report. This gives CLEC one central point of

reference for all IMA EDI & GUI problems. The CLECs can use this report

to:

(1) find out the current status of their IMA EDI or GUI problem

(2) determine if a new problem has already been identified and the

current status

(3) proactively address problems that have been identified by other

CLECs that have potential impacts to their business

Similar to the SBC's Defect Report, the QWEST report should include

the:(1)Trouble Ticket(TT) Number, (2) IMA Version(s) Impacted, (3)

Indicator whether problem impacts IMA GUI, EDI or both (4)Indicator

whether the defect is impacting production code or code only in the SATE

environment, (5) Date the TT was opened, (6) Short Description used to

identify the Problem - for example the actual message being returned

from QWEST, (7) REQTYP and ACT values impacted,(8) Event notification

Number (9) Status of the Fix(Pending Analysis, In Analysis, Pending

Development, IN Development, Pending Testing, In Testing, Pending Prod

Migration, Pending Prod Validation, CLOSED), (10) Status Comments,

(11)Target Implementation/Resolution Date

All Closed Issues should be moved to a separate document or EXCEL Tab

(similar to SBC's Defect Documentation) and retained for 3 months.

Any IMA problems that are currently in analysis and haven't been

reported via event notification should be placed on this report is

activated.

Description of Change - Submitted 02-27-03

QWEST currently support a Manual Indicator, which is used to indicate that the Remarks field contains information that needs manual attention and this field will also be used on occasion as part of a workaround. However a centralized list doesn’t seem to exist to indicate the known workarounds in place in which the Manual Indicator and Remarks are used.

AT&T is requesting that a Production Defect Issues List separate from the CR log be created and maintained. This reported would indicated:

- States impacted

- Products (REQTYP/ACT) impacted

- QWEST assigned Severity Level

- Current Workaround in Place

- Manual Indicator value for workaround

- Remarks required to identify this specific workaround

- Pending Long Term Solution with CR reference

- Target Implementation


Status History

2/27/03 CR Submitted

3/3/03 CR Acknowledged

3/3/03 CR Posted to web

3/3/03 Info Requested from CLEC: Email sent to AT&T requesting Clarification Call Availability

3/6/03 Clarification Meeting Scheduled: Clarification Meeting Scheduled for March 12, 2003, based on AT&Ts Availability.

3/12/03 Clarification Meeting Held: See Project Meetings Section for notes.

04/16/03 Discussed at CMP Meeting

05/21/03 - Qwest response presented at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

7/24/03 - Ad hoc meeting held with ATT

8/4/03 - Scheduled CLEC review ad hoc meeting to review report and further define CR description

8/21/03 - Discussed at CMP Meeting

9/9/03 - Posted response to database

9/17/03 - Sep CMP meeting notes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/12/03: Updated CR with new description

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/8/03 - Removed CR description related to the updated CR that ATT sent in. That CR became PC111903-1 - Please see that CR# for the description. CR PC022703-9X description will remain in place.

12/17/03 - Dec CMP meeting notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/10/04 - emailed response to CLEC

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/30/04 - Added supplimental information to database under open project PC111903-1 - emailed difference between PC022703-9x and PC111903-1 to Donna Osborne Miller - ATT March 16, 2004.


Project Meetings

February 18, 2004 CMP Meeting Connie Winston – Qwest advised that this CR is the one ATT originally issued. This was discussed during the Global Action Item meetings. IT looked at specific data elements on the request and we are planning on providing these via PC111903-1. Donna Osborne Miller – ATT advised we understood when Carla submitted the other CR, Qwest would deny this CR. Donna said she thought that Qwest would identify the parts of this original CR that would not be met but the new CR PC111903-1. Qwest agreed that we would identify the data elements that are not being met by the new CR and send this information to ATT and populate it in the database. This CR will change to Denied Status.

January 21, 2004 This is the original CR that was written with more depth and was reviewed as part of the Global Action Item meeting. The CLECs requested that Qwest create PC111903-1 Web site Notifier to replace this CR. Connie advised we are still evaluating if any piece parts of this CR can be incorporated. Otherwise, we will deny this CR. We hope to finish this in February. This CR will remain in Evaluation Status.

- December 17, 2003 Connie Winston – Qwest reported that this CR is part of the Global Action Item discussion. We anticipate for those meetings to wrap up in January. We will determine if we have met the intent of this CR or should be closed, withdrawn or crossed over. We will then finalize the action needed. This CR will stay in Evaluation Status.

November 19, 2003 Kit Thomte – Qwest advised that this CR was talked about Tuesday during the Global Action Item meeting. This CR was updated with the new title and description. Carla Pardee – ATT advised they would like to keep the old CR open and use the new CR description and title to open a different/new CR. Cindy Macy – Qwest asked if ATT would like to have the new CR clarified or had this happened during the Global Action Item meeting. Carla advised she would like Qwest to hold a Clarification Call for the new CR.

October 15, 2003 Judy Schultz – Qwest advised this is being addressed as part of the Global Action item that was discussed Tuesday October 14. Qwest is currently developing a hybrid Event Notification report as a resolution. The report would be downloadable and available via a url. The status will be changed to Evaluation.

September 17, 2003 Connie Winston – Qwest reviewed the response to this CR. Donna Osborne-Miller ATT advised that Phyllis Burt-ATT redlined the response and that she would like to review this with the group. Donna explained that ATT Consumer disagrees with the statement that Qwest’s Event Notification process is triggered immediately. An example of this is portrayed by PC032803-1. Clear resolution, timelines and work arounds, specifically for Alphabetical Blocking did not occur. This was first reported on July 11, 2003 and the Event Notification was issued 1 month later. The existing process at Qwest determines what information goes into the Event Notification. Not all issues are captured, Qwest decides what to publish. The CLECs want to be able to share their system issue and work arounds with each other. Connie Winston explained some information on Event Notifications is proprietary. Connie agreed we would include a discussion around Event Notifications in the lock up meeting. Connie suggested we look at the CMP guidelines on timeframes as those guidelines are requiring notification to go out, sometimes before we have completed our investigation, thus making the notification not as conclusive as it would be at a later date. Approximately 1300 tickets are taken in one month. Not all of these fit the Event Notification guidelines. We do not want to send notifications out on all 1300 tickets as that would overwhelm the CLECs and Qwest. We would need to develop criteria around what Event Notification to include. Liz advised they have issued trouble reports that could impact other CLECs that have not been turned into an Event Notification. The CLECs advised there is not an Event Notification tracking mechanism. This report would provide a wide view of Event Notifications. Phyllis Burt-ATT advised she does not feel comfortable that Qwest is tracking and managing trouble tickets. It doesn’t seem as if Qwest has a view of total number of open, closed, severity levels and priorities. Qwest advised this CR will be discussed during the lock up session, held the Tuesday before the next CMP meeting. This date is Tuesday October 14, 2003.

CMP Meeting 08-20-03

White-Qwest stated that there was an ad hoc call on 8/11. Following that call AT&T issued a new description of change. Winston-Qwest stated that Qwest was evaluating the new description and the documents AT&T provided. The CR was moved to Evaluation.

===================================

Ad Hoc Meeting – 08-11-03

Attendees Matt White-Qwest Beth Foster-Qwest Kyle Kirves-Qwest Randy Owens-Qwest Liz Balvin–MCI Donna Osborne-Miller-AT&T Carla Pardee-AT&T Phyllis Burt-AT&T

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Foster-Qwest if she had any questions for AT&T.

Foster-Qwest asked if AT&T could update the description of change for the CR with the information that Burt-AT&T had provided in her 7/30 e-mail to Cindy Macy-Qwest. She also stated that Qwest’s practice is to distribute event notifications in accordance with the CMP document’s timelines and that this usually happened immediately. Burt-AT&T stated that her experience was that this was not always the case. She cited the alphabetical blocking issue as an example of when Qwest had received a trouble ticket from a CLEC and had taken quite a while to initiate an event notification. Foster-Qwest asked if AT&T wanted information on the report for all trouble tickets before they are captured in an event notification. Burt-AT&T stated that she wanted all the issues for IMA that came through the help desk captured on the report. Foster-Qwest and Burt-AT&T discussed the headings used in the SBC report and how they may be applicable to Qwest troubles.

White-Qwest asked if there were any additional questions. There were none. White-Qwest thanked the attendees and adjourned the call.

====================================================

Ad Hoc Meeting 07-24-03

Attendees Matt White – Qwest Mallory Paxton – Qwest Linda Sanchez-Steinke - Qwest Phyllis Bert – AT&T Sharon Van Meter – AT&T Regina Mosely – AT&T Connie Nelson- USLink Bonnie Johnson – Eschelon Kim Isaacs – Eschelon

White-Qwest described the purpose of the meeting. Bert-AT&T stated that the 5/14 Qwest response addressed part of the issue. She explained that AT&T really wanted a a central place to see production issues. She stated that she had forwarded SBC’s defect report that she would like Qwest to create a report similar to. Paxton-Qwest stated that the SBC report looked like a spreadsheet that identifies system defects. Bert-AT&T stated that it was and that Qwest would need to modify it to match Qwest’s event notification processes. Paxton-Qwest stated that it looked like the dates on the report were target dates, not release dates. She asked if the SBC reprot was on line. Bert-AT&T stated that it was. Paxton-Qwest clarified that what AT&T wants Qwest to do is take system problems and create an online tool to give CLECs a holistic view of the troubles. Bert-AT&T agreed. Paxton-Qwest stated that the report looked like a catalogue of event notification that indicates when manual activity is required.

Van Meter-AT&T asked if Qwest will include Bert’s information as additional information in the CR interactive report. White-Qwest stated that he would.

Bert-AT&T stated that she wanted the original acceptance solution as well. Paxton-Qwest suggested that she submit an additional CR requesting that change. Bert-AT&T stated that she would.

======================================= CMP Meeting 07-16-03

White-Qwest stated that AT&T had provided feedback to the Qwest 5/14 response and that he recommended that Qwest hold and Ad Hoc meeting to discuss the issues. Osborne-Miller-AT&T agreed.

============================================= CMP Meeting 06-18-03

Osborne-Miller-AT&T stated that she would send any comments from AT&T about Qwest’s proposed implementation to White-Qwest. ========================================================== CMP Meeting 05-21-03

Paxton-Qwest reviewed the Qwest response. Osborne Miller-AT&T stated that the response sounded interesting and inviting. She stated that she would take it back to her folks and let Qwest know if they had any concerns. White-Qwest stated that he would set up an Ad Hoc meeting to discuss any issues that Osborne Miller-AT&T identified. The CR was moved to Development. ==========================================

04-16-03 - CMP Meeting

White-Qwest described the CR and stated that Qwest would have a response at the May CMP Meeting.

==========================================================

March 20, 2003 Systems CMP Meeting Discussion: SCR022703-09 Support Production Defect Report (Originated by AT&T) Donna Osborne-Miller/AT&T presented the CR. John Gallegos/Qwest stated that this is for documentation and we are looking at this CR to be a crossover to Product/Process. John asked if AT&T agreed. Donna Osborne-Miller/AT&T stated to Phyllis Burt (AT&T) that there are no systems implications for this request so it will be crossed-over to the Product/Process forum. Phyllis Burt/AT&T asked how the determination is made as to whether a request is systems or product/process. John Gallegos/Qwest stated that if it is determined that there is a manual solution, the business keeps track of the CR and is a Product/Process definition. Kit Thomte/Qwest stated that these things are handled on the operation’s side of the house. Bonnie Johnson/Eschelon stated that she is in full support of this and asked for the product’s to be expanded to All products. Kit Thomte/Qwest asked if the business was agreeable to the expansion of products. Donna Osborne-Miller/AT&T asked if Qwest would revise to All products. Peggy Esquibel-Reed/Qwest stated that she would revise the CR to change Impacted Product’s to All. Stephanie Prull/McLeod stated that she would also like this for All products. Mallory Paxton/Qwest stated that she agreed that this should be for All products. Donna Osborne-Miller/AT&T asked if there was agreement and understanding that this CR gets crossed-over to Product/Process. Mallory Paxton/Qwest stated that she is in full agreement that this is Product/Process. Mallory stated that she is currently working on something similar to this and this is a documentation issue. Kit Thomte/Qwest stated that this CR would be crossed-over to Product/Process.

-

Clarification Meeting - March 12, 2003 Attendees: Donna Osborne-Miller/AT&T, Phyllis Burt/AT&T, Regina Mosley/AT&T, Carla Pardee/AT&T, Diane Burt/AT&T, John Blaszczyk/AT&T, Peggy Esquibel-Reed/Qwest, Monica Manning/Qwest, Terri Kilker/Qwest, John Gallegos/Qwest, Berkley Loggie/Qwest, Lynn Stecklein/Qwest, Wendy Green/Qwest, Jan Martin/Qwest, Denise Martinez/Qwest, Shelley Mason/Qwest, Rob Mitchell/Qwest, Laurel Nolan/Qwest, Shonna Pasionek/Qwest, Mallory Paxton/Qwest, Joan Pfeffer/Qwest, Deb Roth/Qwest, Carl Sear/Qwest, Kerri Waldner/Qwest, Scott Carne/Qwest

Reviewed CR Description: QWEST currently support a Manual Indicator, which is used to indicate that the Remarks field contains information that needs manual attention and this field will also be used on occasion as part of a workaround. However a centralized list doesn’t seem to exist to indicate the known workarounds in place in which the Manual Indicator and Remarks are used. AT&T is requesting that a Production Defect Issues List separate from the CR log be created and maintained. This reported would indicated: - States impacted - Products (REQTYP/ACT) impacted - QWEST assigned Severity Level - Current Workaround in Place - Manual Indicator value for workaround - Remarks required to identify this specific workaround - Pending Long Term Solution with CR reference - Target Implementation

Expected Deliverables: To be compatible with Release 14.0.

Confirmed Impacted Interface: Process & Documentation

Confirmed Products: UNE-P POTS

Discussion: There were no questions or comments.

Action Plan: This CR will be presented by AT&T at the March 20th CMP Meeting and Qwest will be providing the CR response.


CenturyLink Response

February 10, 2004

For Review by CLEC Community and Discussion at the February 2004 CMP Meeting Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Revised Response - PC022703-9X-“Support Production Defect Report.”

This response is in regards to AT&T’s CR PC022703-9X. This CR was originally denied in September 2003 due to no reasonable demonstrable business benefit. Upon further discussion with AT&T and other CLECs, Qwest agreed to include this CR in the discussions that were held at the Global Action Item Meetings (held on September 12, 2003; October 14, 2003; November 4, 2003; November 18, 2003; December 16, 2003). AT&T agreed to update this CR in accordance with discussions held between Qwest and the CLEC community for updating the Event Notifications Production Support Website. Initially, AT&T updated the existing CR, PC022703-9X, only to retract their update and request that a new CR, PC111903-1 (Web Site Notifier), be issued. Qwest took the action item of reviewing the original, unchanged CR, PC022703-9X, to determine if any components of the original CR should be subject to ongoing review.

Qwest’s original denial of this request stated the following:

AT&T requests that Qwest provide a log of all IMA EDI and GUI issues identified either by Qwest or by a CLEC (via a Wholesale Systems or ISC Help Desk trouble ticket or Service/Account Manager). AT&T also requests that the report identify all open issues pending investigation.

Qwest reviewed this revised request and determined that items AT&T requested be included in a log are already identified within the Event Notifications. Qwest publishes Event Notifications, according to the CMP guidelines, for each issue identified as either a problem, or an item requiring clarification, when it is a CLEC impacting issue. Qwest's Event Notification process is triggered immediately upon identification of an item as CLEC impacting. Log updates would be produced no sooner than Qwest currently issues Notifications.

The existing process ensures a full review of the issue and prevents CLEC proprietary trouble tickets that do not result in an event notification from being shared with the entire community.

Finally, it would require additional Qwest resources to implement and maintain the AT&T request. Duplication of effort in initial publication and again as updates are made to those issues introduces additional cost and complexity into the negotiated CMP process.

Qwest's existing process of providing notifications with workarounds, business impacts, and channels for escalation works effectively and includes the information AT&T is requesting. Qwest respectfully denies this change request because the change does not result in a reasonably demonstrable business benefit.

Based on the agreements at the Global Action Item meetings, the CLECs have agreed to issue PC111903-1 to address the improvements in Qwest’s trouble ticket reporting, and ongoing discussions will be tracked against that CR. Therefore, this CR remains in a denied status, effective September 2003, for no demonstrable business benefit.

Sincerely, Connie Winston Director, Information Technology

September 9, 2003

Donna Osborne-Miller AT&T

CC: Lynn Notarianni Beth Foster Kit Thomte

SUBJECT: Qwest’s Change Request Response - PC022703-9X “Support Production Defect Report (crossed over from SCR022703-09)”

CR Description: AT&T’s revised change request states:

Qwest Response: AT&T requests that Qwest provide a log of all IMA EDI and GUI issues identified either by Qwest or by a CLEC (via a Wholesale Systems or ISC Help Desk trouble ticket or Service/Account Manager). AT&T also requests that the report identify all open issues pending investigation.

Qwest reviewed this revised request and determined that items AT&T requested be included in a log are already identified within the Event Notifications. Qwest publishes Event Notifications, according to the CMP guidelines, for each issue identified as either a problem, or an item requiring clarification, when it is a CLEC impacting issue. Qwest's Event Notification process is triggered immediately upon identification of an item as CLEC impacting. Log updates would be produced no sooner than Qwest currently issues Notifications.

The existing process ensures a full review of the issue and prevents CLEC proprietary trouble tickets that do not result in an event notification from being shared with the entire community.

Finally, it would require additional Qwest resources to implement and maintain the AT&T request. Duplication of effort in initial publication and again as updates are made to those issues introduces additional cost and complexity into the negotiated CMP process.

Qwest's existing process of providing notifications with workarounds, business impacts, and channels for escalation works effectively and includes the information AT&T is requesting. Qwest respectfully denies this change request because the change does not result in a reasonably demonstrable business benefit.

Sincerely,

Connie Winston, Director, Information Technology Qwest

* August 13, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the August 20, 2003, CMP Product/Process Meeting

Donna Osborne Miller AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC022703-9X

This is an updated response regarding AT&T CR PC022703-9X (Support Production Defect Report – crossed over from SCR022703-9).

Qwest reviewed this request and provided the initial response at the May 21, 2003 Product/Process CMP Meeting. AT&T reviewed Qwest’s response and provided additional information during an Ad Hoc meeting held on July 24, 2003. The additional information that AT&T provided included an example of a report that identifies a listing of ‘Event Notifications.’ AT&T requested that Qwest hold an Ad Hoc meeting with the CLEC Community to review the report. Qwest scheduled and held this meeting on August 11, 2003. During the meeting, AT&T agreed to modify the description of change to clarify this request.

While it assess this CR, Qwest would like to move it into Evaluation Status. Qwest will provide a status update at the September CMP meeting and will outline their response at that time.

Sincerely,

Connie Winston Qwest

========================================================= May 14, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the May 21, 2003, CMP Product/Process Meeting

Donna Osborne-Miller AT&T

SUBJECT: AT&T Change Request – CR PC022703-9X

This letter is in response to AT&T Change Request PC022703-9X. This CR is a request by AT&T for Qwest to create a centralized list of known workarounds.

Qwest accepts this CR and is currently working to create an appropriate update to the Resale and Interconnection Ordering Overview PCATs to satisfy AT&T’s request. This update will create a new section in the PCAT that will contain links to documented manual processes or workarounds in product-specific PCATs or other procedure PCATs.

For example, in the Migrations and Conversions PCAT, there is a documented manual process for Courtesy Disconnects. The new section in the Ordering Overview PCAT may read:

“Manual Requests Required” Manual handling (Manual Indicator ‘Y’) is required to process the following types of requests. - Courtesy Disconnects (This hotlink would take a reader to the Migrations PCAT.) - Other Documented Process - Etc.”

This text is a proposed example only and is subject to change. Qwest will provide an update on the documentation change at the June CMP meeting.

Sincerely,

Mallory Paxton Senior Process Analyst

============================================

DRAFT RESPONSE to SCR022703-09 March 13, 2003

RE: SCR022703-09 Support Production Defect Report

Qwest has reviewed the information submitted as part of Change Request SCR022703-09. Based upon the scope of this CR as agreed to in the Clarification Meeting (held March 12, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 1050 to 1750 hours for this Change Request.

At the March Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

Sincerely, Qwest


Open Product/Process CR PC042303-1 Detail

 
Title: AT&T requests that Vendor Meet (coordinated dispatch) requests for non design POTS service be at specific times.
CR Number Current Status
Date
Area Impacted Products Impacted

PC042303-1 Crossover
7/29/2009
Maintenance Repair UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Suellentrop, Craig
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently Qwest provides a four hour window for the vendor meet at the customer premise. This four hour window places undue buden on AT&T and AT&T vendors on coordinated dispatches. The current process used is to contact the CLEC center thirty minutes in advance of dispatch arrival. This is not enough lead time for AT&T or it's vendors to ensure that the actual meet takes place, since the Qwest tech will not wait for AT&T's vendor. AT&T had established with Verizon, Bell South and with SBC, a Memorandum of Understanding (MOU) around coordinated dispatches. Under these agreements, all AM-scheduled vendor meets are to occur at 9AM(local time) and all PM vendor meets are to occur at 1PM (local time). Wait time for either tech is limited to 30 minutes. Development and implementation of this process reduced "missed" vendor meets by 73% withing the first two months.

Expected Deliverable:

ATT requests a similar process as described above. (MOU) This would include any system changes necessary by Qwest to be implemented to support this type of process. Implementation of this process/system change would allow both AT&T and QWEST to better manage situations requiring a coordinated dispatch, resulting in fewer "no access" or "vendor meet ,no show" and would reduce missed commitments for these reasons.


Status History

4/23/03 CR Received

4/24/03 CR Acknowledged

05/09/03 Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/09/03 - Revised response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database - agreed to cross over this CR. See SCR042303-01X for continuing project status

10/28/03 - Changed status to closed as this was crossed over to systems


Project Meetings

October 15, 2003 CMP Meeting Craig Sullentrop – Qwest advised it has been determined that this CR has impacts to RBE, which are visable to CEMR. As a result of this, the CR needs to be crossed over to Systems. ATT uses Mediacc, and there are not changes to Mediacc, however other CLECs use RCE. Donna Osborne Miller advised okay to cross over to Systems.

September 17, 2003 CMP Meeting Craig Suellentrop – Qwest reported that an internal status meeting is scheduled for next week. The development is on track and estimated time frame is December 2003. Liz asked Craig to refresh her memory and Craig advised this is for the joint meet which has to be requested.

CMP Meeting 08-20-03

Suellentrop-Qwest stated that the CR should stay in development because there were a number of internal systems that had to move through the 90 day development cycle. Osborne-Miller-AT&T asked when she could expect delivery. Suellentrop-Qwest stated that he estimated implementation would come in December 2003.

=================================

CMP Meeting 07-16-03

Sullentrop-Qwest presented the Qwest acceptance. He stated that when Qwest developed the full solution it would follow the appropriate notification process. He stated that this might entail systems changes, but he wasn’t sure if they would be CLEC facing changes. Zimmerman-AT&T asked for Qwest’s tentative implementation date. Sullentrop-Qwest stated that he thought it would take at lease a couple of months. Osborne-Miller-AT&T asked if the systems changes would involve IMA. Suellentrop-Qwest stated that he didn’t think they would involve prioritized systems. He stated that he would have much more information at the August CMP Meeting. He stated that Qwest was looking at a 30 minute meeting window. Zimmerman-AT&T stated that was good. Suellentrop-Qwest stated that this new process would be available for systems other than electronic bonding. Johnson-Eschelon stated that Eschelon had submitted a CR in 2001 (PC092801-2) for the same thing and Qwest denied it. She asked why Qwest was accepting AT&T’s. White-Qwest stated that he would research the reason and correspond directly with Johnson.

=================================== CMP Meeting 06-18-03

Suellentrop-Qwest asked that the CR be moved into Evaluation status. Osborne-Miller-AT&T stated that AT&T would forward their contacts in the other ILECs to Qwest. ========================================================== CMP Meeting 05-21-03

Osborne Miller-AT&T presented the CR. Suellentrop-Qwest stated that UNE-P and resale products are affected by this. Stichter-Eschelon stated that she had opened a similar CR that was denied. Johnson-Eschelon asked if there should be a CMP process to review previously denied CRs. Osborne Miller-AT&T stated that Verizon, SBC and Bellsouth have all converted to a similar process after AT&T presented them with the data. Suellentrop-Qwest asked AT&T to send the appropriate data to White-Qwest. ========================================== Clarification Meeting Friday, May 09, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Craig Suellentrop – Qwest Anthony Washington – Qwest Donna Osborne-Miller – AT&T Craig Zimmerman – AT&T Lydia Braze – AT&T Paulita Moore – AT&T

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Osborne-Miller-AT&T reviewed the CR. Suellentrop-Qwest verified that this CR was for UNE-P and resale and that the request was for 24 hours advance notification. Zimmerman-AT&T stated that he envisioned a 24 to 48 hour notification. He explained that AT&T submitted the initial dispatch request via electronic bonding system and then followed up with a call. Zimmerman-AT&T asked if any other CLECs have approached Qwest with similar requests. Suellentrop-Qwest stated that he seemed to remember a similar request around 2 years ago. Zimmerman-AT&T stated that this request only applies to only 1-2% of total dispatches in any area.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm AT&T’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for AT&T to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Response - CR PC042303-1

This CR requests that vendor meets for non-designed products be made at a specific date and time. AT&T has suggested that all AM vendor meets could take place at 9:00 am and all PM vendor meets take place at 1:00 pm.

A Joint Meet involves Qwest, CLECs, and possibly third party vendors, meeting at a designated location to isolate hard-to-find faults, verify existing trouble and diagnosis, and resolve chronic and repeat problems. Qwest accepts this change request to allow CLECs to request a joint meet at a specific time. Qwest proposes this CR be moved into development status. Qwest needs to finalize the mechanics of this process, including how far in advance a joint meet request must be made and any system changes that will be required.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Cathy Augustson, Lead Process Analyst, Qwest

========================================== June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, Monthly CMP Product/Process Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Response - CR PC042303-1 “AT&T requests that Vendor Meet (coordinated dispatch) requests for non-design POTS service be at specific times.”

This CR requests that vendor meets for non-designed products be made at a specific date and time. AT&T has suggested that all AM vendor meets could take place at 9:00 am and all PM vendor meets take place at 1:00 pm.

The current vendor meet process for non-designed products gives the customer a 4-hour window for the vendor meet. Because of the complexity in evaluating this request, including possible systems changes that may be required, Qwest requests that this CR be moved into Evaluation Status. Qwest will provide an updated response at the July CMP meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest


Open Product/Process CR PC042303-2 Detail

 
Title: AT&T requests that pre dispatch calls be limited to specific scenarios, primarily address mismatches, no access situations and/or vendor meets requests.
CR Number Current Status
Date
Area Impacted Products Impacted

PC042303-2 Completed
4/15/2009
Maintenance Repair UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Suellentrop, Craig
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest performs pre-dispatch calls throughout the day to CLECs prior to dispatching out to customers premise. AT&T believes pre dispatch calls on ALL dispatches places an undue burden on their call centers. Due to previous volumes of calls from other ILECs, AT&T utilized Electronic Bonding for repair. AT&T does not see value in pre-dispatch calls except under very limited conditions as noted in the title of change. The JIA clearly states that "dispatch authorization implied when item referred". Since authorization for the dispatch is already implied, AT&T does not want to incur the addtiional supplier call volume to simply inform us that dispatch is now occurring. The information whould be transmitted electronically through EB.

Expected Deliverable:

Do not call to dispacth on any other that specific scenarios noted in Title of change. Utilize EBTA for "other" dispatch situations.


Status History

4/23/03: CR Received

4/24/03: CR Acknowledged

05/09/03 Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/09/03 - Revised response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/17/03 - Notification distributed PROS.10.17.03.F.03633.Maintenance_V19

11/13/03: Notification distributed PROS.11.13.03.F.001050.FNL_Maintenance_V19

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP meeting minutes will be posted to the database


Project Meetings

CMP Meeting 12/17/03 - Jamal Boudhaouia – Qwest advised the document notification number and dates. The comment cycle closed and no comments were received. Jamal asked if we could close this CR. Carla Pardee – ATT advised it is okay to close this CR.

CMP Meeting 11/19/03 Craig Suellentrop – Qwest advised the PCAT has been updated and no comments have been received. Implementation is scheduled for December 1, 2003. This CR will remain in CLEC Test.

CMP Meeting 10/15/03 Craig Suellentrop –Qwest advised pre-dispatch calls will only occur when the CLEC requests them. The notification will go out October 17. This CR will move to CLEC Test Status.

CMP Meeting 9/17/03 Craig advised the notification is almost ready. The documentation team is currently reviewing the documentation. This is a Level 3 change.

CMP Meeting 08-20-03

Suellentrop-Qwest stated that Qwest was finalizing the training and the documentation. He stated that the documentation should be in the review site within the next two weeks. Zulevic-Qwest asked if the change was UNE-P specific. Suellentrop-Qwest stated that the change was for all non-design products.

================================================

CMP Meeting 07-16-03

Osborne-Miller-AT&T described the Qwest acceptance and asked if the response would apply to MEDIACC. Suellentrop-Qwest stated that MEDIACC users would use the comments field. While CEMR users would have a button to select. Zimmerman-AT&T stated that this sounded good. Osborne-Miller-AT&T and Johnson-Eschelon stated that they were very pleased with Qwest’s acceptance of this CR. CR moved to Development.

================================================= CMP Meeting 06-18-03

Suellentrop-Qwest presented the Qwest response. Johnson-Eschelon stated that she thought Qwest was going to check to see if Qwest could use the Call Before Dispatch option in CEMR and only perform the pre-dispatch call for those CLECs. Suellentrop-Qwest stated that it was Qwest’s policy to call regardless of whether the CLEC checks “Call Before Dispatch” in CEMR. He stated that he will check to see if this was an option. Osborne-Miller stated that AT&T was split on the proposed solution in the response. ========================================================== CMP Meeting 05-21-03

Osborne Miller-AT&T presented the CR. Suellentrop-Qwest asked what the other CLECs thought about this request. Johnson-Eschelon stated that Eschelon wanted the calls to continue. She suggested that there might be a systems solution to determine which CLECs wanted the call. Balvin-MCI stated that she would like to see a list of all calls the AT&T would not want. Zimmerman-AT&T stated that AT&T wanted only the CRs denoted in the CR. Johnson-Eschelon stated that there was a field in CEMR for a call before dispatch. She stated that Eschelon wanted the calls. She stated that this should be the CLEC’s option regardless of the reporting medium. ========================================== CLEC Change Request – PC042303-2 Clarification Meeting Friday, May 09, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Craig Suellentrop – Qwest Anthony Washington – Qwest Donna Osborne-Miller – AT&T Craig Zimmerman – AT&T Lydia Braze – AT&T Paulita Moore – AT&T

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Osborne-Miller-AT&T reviewed the CR. Suellentrop-Qwest asked if AT&T was asking for this change to apply to all trouble tickets. Zimmerman-AT&T stated that most of the tickets are electronically submitted, but that the intent would be for the change to apply to all. He explained that AT&T has a separate line for LEC technicians to call in to. That line does not get a higher priority than customer calls. As a result, because Qwest calls in status reports that do not require AT&T action the supplier line is flooded with unnecessary calls. This call volume and causes AT&T to miss the important action-required calls. Suellentrop-Qwest stated that he understood the request. He stated that he would also be interested to hear other CLEC opinions of this request. Osborne-Miller-AT&T asked if there was any way Qwest would implement this process only for AT&T. Suellentrop-Qwest stated that Qwest would prefer an universal policy.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm AT&T’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for AT&T to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Response - CR PC042303-2 “AT&T Requests that pre-dispatch calls be limited to specific scenarios, primarily address mismatches, no access situations, and/or vendor meet requests”

This CR requests that the pre-dispatch call made by the Qwest repair technician prior to leaving to the end-user location is only made when there are address mismatches, no access situations, and/or vendor meet requests. AT&T believes that making the pre-dispatch call on all dispatches places an undue burden on their call centers.

The current non-designed repair process for outside technicians requires a courtesy call to the customer of record (both wholesale and retail) prior to leaving to the end-user location. At the May 21 CMP meeting other CLECs requested that this process not be changed and that they want Qwest to make the pre-dispatch call. Therefore, this request was denied at the June CMP meeting.

However, the question was raised about using a box titled, “Call Before Dispatch” in the CEMR application. This function is also available to Qwest’s repair agents on manually reported trouble. The CLEC community was agreeable to the idea of Qwest only performing the pre-dispatch calls when requested via the above mentioned methods. If this is still the case, Qwest accepts this request and will issue a Level 3 notification to implement the modified process.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Cathy Augustson, Lead Process Analyst, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest

====================================== June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, Monthly CMP Product/Process Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Response - CR PC042303-2 “AT&T Requests that pre-dispatch calls be limited to specific scenarios, primarily address mismatches, no access situations, and/or vendor meet requests”

This CR requests that the pre-dispatch call made by the Qwest repair technician prior to leaving to the end-user location is only made when there are address mismatches, no access situations, and/or vendor meet requests. AT&T believes that making the pre-dispatch call on all dispatches places an undue burden on their call centers.

The current non-designed repair process for outside technicians requires a courtesy call to the customer of record (both wholesale and retail) prior to leaving to the end-user location. At the May 21 CMP meeting other CLECs requested that this process not be changed and that they want Qwest to make the pre-dispatch call.

Therefore, Qwest respectfully denies this change request because the requested change does not result in a reasonably demonstrable business benefit; this request will negatively impact other CLECs.

However, Qwest would like to address AT&T’s concern regarding placing an undue burden on their call center. As Qwest understands, AT&T has a supplier line and the hold times could be quite lengthy. Qwest would like to propose a process that on the courtesy pre-dispatch calls, the technician would wait in a Voice Response Unit (VRU) for at least a set period of time (say 90 seconds). After this time the technician would drop the call. This would relieve most of the volume into the call center. When there are address mismatches, no access situations, and/or vendor meet requests, the technician would wait on the line until someone is reached. If someone answers the phone, or if the call is routed to voice mail, the process in place today would not change.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Cathy Augustson, Senior Process Analyst, Qwest


Open Product/Process CR PC042303-3 Detail

 
Title: Clarification of Service Interval Guide Installation Instructions for UNE P Conversion as Specified.
CR Number Current Status
Date
Area Impacted Products Impacted

PC042303-3 Withdrawn
5/21/2003
Preordering, Ordering UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Rein, Kathy
Director:
CR PM: Harlan, Cindy

Description Of Change

The Qwest Service Interval Guide (“SIG”) currently states the following for “Activity/Feature – Conversion as Specified for Retail, Resale or UNE-P POTS to UNE-P POTS: “Orders are submitted for two main purposes: 1) To convert an existing resale/retail lines to UNE-P with changes, and 2) To request an additional line. Depends on changes requested. For instance, addition of another line would follow New Installs Guidelines”. This guideline is confusing to AT&T, as well as other CLECs. The guidelines distinguishes and clarifies the request for an additional line, however the interval for requesting conversion as specified to convert an existing resale/retail line to UNE-P with a change is not clear. Does this mean that a CLEC follows the addition or change of CO features listed later in the SIG, or some other interval ? AT&T requests that Qwest clearly identify this interval in its published SIG for each type of conversion as specified change. The clarification requested by AT&T is a minor change involving very few resources by Qwest.

Expected Deliverable:

July 2003


Status History

4/23/03: CR Received

4/24/03: CR Acknowledged

4/28/03: Contacted Carla-ATT to schedule clarification call

4/29/03: Scheduled Clarification call for 5/2/03

5/02/03: Held clarification meeting. Rec'd e-mail from Carla Pardee at AT&T they have decided to withdraw change request as it is duplicate of AI041603-1 submitted by Liz Balvin.

5/06/03: Status of CR changed to pending withdrawal.

5/21/03: May CMP Meeting minutes will be posted to the database


Project Meetings

May CMP Meeting - An Action Item is open for this same request (see AI041603-1). This request will be Withdrawn. Carla-ATT agreed this was okay.

Fri 5/2/03 9:49 AM From: Pardee, Carla D, CSLSM [cdickinson@att.com] To: ljsanch@qwest.com; cmacy@qwest.com Linda - Based on our Clarification call today, and the representations from Michael Whitt, AT&T is withdrawing this CR. Thank you for your assistance in this matter.

Carla Dickinson Pardee AT&T Local Services & Access Management 1875 Lawrence Street, Suite 8-38 Denver, Colorado 80202 Phone: 303-298-6101

CLEC Change Request Clarification Meeting 9:00 a.m. (MDT) / 5/2/03 1-877-562-8687, 3393947 PC042303-3 Clarification of Service Interval Guide Installation Instructions for UNE-P Conversion as Specified.

Attendees Carla Pardee, AT&T, LSAM Manager Laurel Neher, Qwest, Staff Advocate Policy & Law Kathy Rein, Qwest, Process Specialist Michael Whitt, Qwest, Product Manager UNE-P Linda Sanchez-Steinke, Qwest, Change Request Project Manager

Introduction of Attendees Introductions of the participants on the Conference Call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of change requested in the CR was reviewed. Carla indicated that AT&T would like to have the Service Interval Guide clearly specify UNE-P conversion installation guidelines.

Confirm Areas & Products Impacted UNE-P Conversions

Confirm Right Personnel Involved Qwest confirmed that the right personnel were involved in the conference call.

Identify/Confirm CLEC’s Expectation Michael Whitt explained that there are changes planned to this section of the SIG that will make the language more clear. These changes will be sent out on or around 5/23/03. The language proposed to change is the conversions as specified for existing retail or resale to UNE-P POTS 3 business days. In Colorado and Minnesota only 2 business days. When adding additional lines, new installation guidelines apply. Carla said that AT&T may withdraw this CR because of the already existing action item open for MCI/Worldcom. Identify any Dependent Systems Change Requests

Establish Action Plan (Resolution Time Frame) Carla will send Linda Sanchez-Steinke an e-mail to withdraw this change request.


Open Product/Process CR PC050503-4CM Detail

 
Title: Allow Originating CLEC to invite other CLECs to its Clarification Meeting for a System CR
CR Number Current Status
Date
Area Impacted Products Impacted

PC050503-4CM Completed
8/20/2003
CMP Operations
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Harlan, Cindy
Director:
CR PM: Harlan, Cindy

Description Of Change

Add language from Section 5 of the Product/Process CMP Document to System section of the CMP Document. Language states:

"Within eight (8) business days after receipt of a complete CR, the CRPM coordinates and holds a clarification meeting with the Originating CLEC and Qwest’s SMEs. If the originating CLEC is not available within the above specified time frame, then the clarification meeting will be held at a mutually agreed upon time. Qwest will not provide a response to a CR until a clarification meeting has been held. The CR originator may invite representatives from other companies to participate on the clarification call. Such participation is not intended to replace the presentation of the CR at the Monthly CMP Meeting."

Expected Deliverable

Allow Originating CLEC to invite other CLECs to its Clarification Meeting for a System CR


Status History

05/05/03 - CR Submitted

05/07/03 - Acknowledged CR

5/9/03 - Scheduled Clarification Call

5/13/03 - Held Clarification Call

5/14/03 - Sent Clarification Notes and Red Line to CLEC

5/21/03 - May CMP Meeting Minutes will be posted to the database

5/27/03 - Vote Notification and Vote Ballot sent to CLEC community advising vote will take place during June CMP Meeting

6/18;/03 - June CMP Meeting Minutes will be posted to the database and Vote results will be posted to the minutes and the website

7/7/03 - Updated CMP Document posted to database

7/16/03 - July CMP Meeting Minutes will be posted to the database

8/20/03 - August CMP Meeting Minutes will be psoted to the database


Project Meetings

August 20, 2003 CMP Meeting Minutes Kit Thomte-Qwest explained the language was reviewed and it was agreed that it was okay as written. Sharon VanMeter-ATT agreed it was okay to close this CR.

July 16, 2003 CMP Meeting Minutes Cindy Macy – Qwest advised the CMP document was updated and published on July 7, 2003. This CR will move to CLEC Test. Conversation took place regarding making additional updates to this section of the CMP document to further clarify the intent. See AI052103-1 for more information.

June 18, 2003 CMP Meeting Minutes Cindy Macy – Qwest read the requested language change to the CMP document and explained what a vote of ‘yes’ and a vote of ‘no’ means. The quorum was 6 CLECs and the voting standard was unanimity. The quorum was established as there were 12 CLECs available to vote. The CLECs included Cox Communications, Eschelon, Tel West, US Link, McLeod, Covad, NcTelcom, North Star Access, AT&T, Allegiance, Qwest and MCI. A vote was taken on this CR and the vote passed with 12 ‘yes’ votes and 0 ‘no’ votes. Matt White-Qwest asked if it was okay to implement this change with a Level 1 Notification. The CLECs agreed. The language identified in the CR will be incorporated into CMP Process Section 5.1.4.

May 21, 2003 CMP Meeting Minutes Sharon Van Meter – ATT presented this CR and reviewed the Red lined changes. The CLECs do not believe they need an input meeting as they understand the request. The Vote for this CR will be scheduled during the June CMP meeting.

Clarification Meeting

May 13, 2003

1-877-572-8687 3393947#

PC050505-5CM Allow originating CLEC to invite other CLECs to its Clarification Meeting for a system CR Attendees Sharon Van Meter – ATT Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change ATT reviewed the CR. Sharon explained ATT wants to be able to invite other CLECs to Systems Clarification Meetings. ATT is hoping this will allow the CR to be resolved faster. Cindy – Qwest asked how would this make the CR be resolved faster. Sharon explained that the scope would get clarified earlier and Qwest would not have to wait until the Monthly CMP meeting to start working on the CR. I advised Sharon that the P/P side begins working on the CR as soon as the initial clarification meeting is held. Qwest does not wait until after the Monthly CMP Meeting. Sharon explained that this was talked about in Redesign and it got voted down as some CLECs thought it would be mandatory to invite other CLECs. This is not mandatory; it is options if the originating CLEC wants to invite others. Sharon explained she has talked to the other CLECs and she believes she has their support at this time. Cindy advised Sharon that we need to identify in the CMP Process the section to update and then redline it. Cindy agreed she would do that for Sharon and send it to Sharon. Cindy also suggested that we make the paragraph in P/P section 5.3 match the Systems section 5.1.4. This will involve adding 2 sentences to Section 5.1.4 to make it match Section 5.3. Sharon agreed and will review the red lined paragraph when Cindy sends it. (See Below).

The new Section 5.1.4 would read as below, with the changes identified in Red: Within eight (8) business days after receipt of a complete CR, the CRPM coordinates and holds a clarification meeting with the CR originator and Qwest’s SME(s). If the originator is not available within the above specified time frame, then the clarification meeting will be held at a mutually agreed upon time. Qwest may not provide a response to a CR until a clarification meeting has been held. The CR originator may invite representatives from other companies to participate on the clarification call. Such participation is not intended to replace the presentation of the CR at the Monthly CMP Meeting.

3.0 Confirm Areas & Products Impacted All CR Clarification Meetings

4.0 Confirm Right Personnel Involved Cindy advised she would check with the Systems CMP team to see if we are missing anything.

5.0 Identify/Confirm CLEC’s Expectation Sharon would like the paragraph referenced in the redline document in the Systems section 5.1.4 to match the same paragraph in section 5.3.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) ATT will present the CR at the May CMP Meeting Qwest will review the Vote process and set this CR up for a vote. Voting involves sending out a vote notification, offering 3 meetings times to hold the vote, establishing a quorum, ballot, unanimous vote, and vote disposition. This will be discussed at the May CMP meeting.


Open Product/Process CR PC050703-1 Detail

 
Title: Change Qwest Wholesale CMP Website to make it easier to search, retrieve and view CRs.
CR Number Current Status
Date
Area Impacted Products Impacted

PC050703-1 Completed
5/3/2004
Operations
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Thomte, Kit
Director:
CR PM: Andreen, Doug

Description Of Change

AT&T is asking Qwest to make it easier to search, retrieve, and view a specific CR document on the Qwest Wholesale CMP Website. Although anyone can sort by CR, Originator Company, Current Status, Most Recently Updated, CR Project Manager, and CR Title - once the sort is completed, the CR cannot be accessed to read the document. AT&T is requesting that once the sort is completed, we can click on the CR number and it will bring up that specific CR. Another option might be to have a "search" field and by typing in the CR number, the CR would be retrieved and the document could be read. If these are not viable options, AT&T is asking Qwest to come up with suggestions/solutions.


Status History

05/07/03 - CR Submitted

05/07/03 - Acknowledged CR

05/12/03 - Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

09/17/18 - CMP Meeting Thomte indicated that Qwest is continuing to pursue improvements to this web site.

02/25/04 - Qwest originated notice PROS.02.25.04.F.01418.CMP_WEBSite_ProcessOpt

3/18/03 - Status changed to CLEC Test

3/17/04 - Notes will be posted from March CMP meeting

3/25/04 - Qwest originated notice PROS.03.25.04.F.01508.WebCR_InteractiveReports

4/7/04 - Qwest initiated notice PROS.04.08.04.F.01559.FNL_WebCR_InteractiveRepo


Project Meetings

04/21/04 CMP Meeting Doug Andreen, Qwest said that two comments were received during the comment cycle. One coment asked for a find capability covering the entire database. In order to make that capability available the effective date was moved from April 15 to April 23. Notice was sent that it is Qwest’s intention to remove the old Interactive Reports and remove the Prototype designation from the new reports on the 23rd.. The CR was moved to Completed. - 03/17/04 March CMP Meeting Kit Thomte, Qwest said that it was agreed last month to put this CR in CLEC Test status. The Interactive Report prototype is now on the web and comments internally have been positive. The CLECs agreed to review. The CR will remain in CLEC Test Status.

-- 2/18/04 CMP Meeting Kit Thomte and Doug Andreen, Qwest said the prototype will be available 3/25 and will be located next to the existing Interactive Report on the Qwest Web Site. It will contain six different sorts for the data. The format is somewhat changed although the content remains the same. Kit asked if the CLECs would agree to move this CR to test since the prototype will be available in a week. The CLECs agreed to move the CR to test.

- CMP Meeting 1-21-04 Thomte Qwest indicated that hopefully we might have a prototype for the meeting next month. The issue is continuing to be worked. The CR will remain in Development status.

-- CMP Meeting 12-17-03

Thomte Qwest indicated that hopefully we might have a prototype for the meeting in January. The issue is continuing to be worked. The CR will remain in Development status.

- CMP Meeting 10-15-03 Thomte Qwest indicated that this CR is still being worked. Qwest is trying to find the appropriate vendor to handle these updates. This CR will reamin in Development status.

CMP Meeting 09-17-03 Thomte indicated that Qwest is continuing to pursue improvements to this web site. CMP Meeting 08-20-03

Van Meter-AT&T stated that she liked the new report format but she would still like to be able to search by CR number. Balvin-MCI stated that she would like the ability to copy from the report and paste into other applications. White-Qwest stated that Qwest was still working on developing a more robust report format.

==============================================

CMP Meeting 07-16-03

White-Qwest stated that the new report format would be posted on 7/16. He recommended that the CR be left in Development status because Qwest was developing a more robust solution. Van Meter-AT&T agreed.

================================================== CMP Meeting 06-18-03

White-Qwest presented the response. Van Meter-AT&T and Hines-MCI stated that they were fine with the proposed change. Van Meter-AT&T asked that Qwest distribute a notice when the change became effective. White-Qwest agreed and asked to move the CR into Development. ========================================================== CMP Meeting 05-21-03

Van Meter-AT&T presented the CR. White-Qwest confirmed that the CLECs used the “sort by originator” option in the interactive report the most. All attendees agreed. ============================================

Clarification Meeting Monday, May 12, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Sharon Van Meter – AT&T Liz Balvin – MCI Bonnie Johnson – Eschelon Mike Zulevic – Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Osborne-Miller-AT&T reviewed the CR. She stated that she most frequently used the Sort by Originator button to find a CR when she didn’t know the number. She stated that it would be helpful if the buttons to link to the CR details were contained within that report. White-Qwest asked the other CLEC representatives if they also used the Sort by Originator function most frequently. All attendees responded that the most frequently used sort was the Sort by Originator. Van Meter-AT&T suggested that Qwest implement some sort of GUI front end that allows users to find a specific CR by inputting the number or to sort the CRs by originator/CRMP/status/title/etc. White-Qwest stated that he would query the attendees at the upcoming meeting to find out if all the CLECs used Sort by Originator most frequently.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm AT&T’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for AT&T to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, CMP Product/Process Meeting

Sharon Van Meter AT&T

SUBJECT: Qwest’s Change Request Response - CR #PC050703-1

This is an initial response to AT&T CR PC050703-1. This CR requests that Qwest Change Qwest Wholesale CMP Website to make it easier to search, retrieve and view CRs.

Qwest accepts this Change Request. Qwest recommends that the changes to implement this request be implemented in with a phased approach. Qwest is still researching an appropriate means of providing more comprehensive linking in the current report and the possibility of providing a GUI front-end to the report. However, to meet the CLECs’ stated need, Qwest is prepared to immediately modify the existing Interactive Report as attached.

Sincerely,

Matt White Qwest


Open Product/Process CR PC061103-1ES Detail

 
Title: Intercept CLEC customer calls to Qwest Repair Center
CR Number Current Status
Date
Area Impacted Products Impacted

PC061103-1ES Completed
8/18/2004
Maintenance repair UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Boudhaouia, Jamal
Director:
CR PM: Andreen, Doug

Description Of Change

Currently, when an AT&T UNE-P end-user customer calls the Qwest repair line (800-573-1311), the call is routed to a Qwest representative, who then provides the customer with an AT&T 800 number. AT&T requests that Qwest change this procedure so that the call is intercepted when the customer enters their TN, and the customer should hear a branded message to the AT&T 1-800 repair number (800-288-2747).

There are several reasons for this request: AT&T customers should not be speaking to a Qwest representative; it would be much more efficient to route the call directly to AT&T; it eliminates potential representative errors, and; it reduces the number of calls to the Qwest center.

Expected Deliverable:

August 2003


Status History

06/11/03 - CR Received

06/12/03 - CR Acknowledged

06/18/03 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/24/03 - Held Clarification Meeting

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/21/03 - Qwest received escalation from AT&T

10/21/03 - Qwest issued notificaiton, CMPR.10.21.03.F.01597.EscalationNotification

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/28/04 - Qwest generated notice PROS.07.28.04.F.01932.InterceptCLEC_CustCalls

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

9/16/04 CMP Meeting Minutes Doug Andreen requested the CR be moved to Completed Status. Donna Osborne-Miller said that Joyce Atwell had been doing some follow-up and Donna had not heard from her as yet. She requested that the CR stay open and that she would have the information to Doug by the end of the week. If AT&T has no objections it was agreed to close out of cycle. The CR will remain in Test until Donna gets back with Doug.

8/18/04 CMP Meeting Mark Gonzales reported that the work was complete and that a notice was sent on July 28 effective July 29. The CR will be moved to Test status.

7/21/04 July CMP Meeting Denny Graham – Qwest reviewed the response and advised that Qwest is looking at the process and products impacted. Qwest will move this CR to Evaluation status. We will provide an updated status in August.

-- 06/16/04 June CMP Meeting Jamal Boudhaouia with Qwest said that the changes are on track for implementation in third quarter. Carla Pardee with AT&T said that after looking over the changes being made to the VRU, it is not clear how this is different from what is currently done. Jamal said that we want to identify the CLEC end user as not a Qwest customer when a CLEC end user calls the VRU unintentionally. Upfront checks will be done to determine if the end user is Qwest’s or a CLEC’s and convey the message that they are not Qwest’s customer if they are a CLEC end user. Carla asked Jamal to explain the series of checks. Jamal said that the number input by the end user is checked to determine if Qwest, AT&T, Sprint, other CLEC, etc., is the service provider for the end user and then provide the CLEC number if we have it. Carla Pardee with AT&T agreed to the changes being made after the explanations given by Jamal. This CR will remain in Development status.

05/19/04 May CMP Meeting Jamal Boudhaouia with Qwest said that we are in the process of starting to code and implementation is tentatively scheduled for third quarter 2004. The VRU response for Option 2 will be changed. Jamal summarized the VRU changes that will be made and a document summarizing the changes will be attached to this CR. Carla Pardee with AT&T said we thought the call would be intercepted and go to the CLEC serving the account, but since we agreed in September to what Jamal explained it will be accepted. We would like commitment that the implementation will take place during July, August or September 2004. Jamal said the implementation is scheduled for third quarter 2004. Liz Balvin with MCI said it should be taken into consideration the number of times Qwest is used in the VRU because we would not want a CLEC end user customer to talk with a Qwest representative. Bonnie Johnson with Eschelon suggested that the VRU options be written and attached to this CR and Jamal agreed to provide. This CR will remain in Development status.

04/21/04 April CMP Meeting Jamal Boudhaouia with Qwest said that implementation is scheduled for third quarter 2004 and that he will give an update at the May meeting. This CR will remain in Development status.

03/17/04 March CMP Meetng Ev Montez with Qwest said the funding for the project has been approved and that a firm date for implementation has not been provided because IT has not prioritized projects. Carla Pardee with AT&T said that the CR has been out there for a long time and AT&T wants to get the implementation date. Ev said she would provide an update at the April meeting or before if available. This CR will remain in Development status.

-- 02/18/04 February CMP Meeting Jamal Boudhaouia with Qwest said that funding for the project has been approved and will provide a date for implementation as soon as available. Bonnie Johnson said that she has asked several times and has not received an answer about the Qwest retail VRU project and when that is scheduled for implementation or has it been implemented. Jamal said that the project hasn’t been implemented and all changes will be incorporated and will include the CR requested changes. Bonnie said that Qwest hasn’t made clear what the implementation date will be. Carla Pardee with AT&T said that the changes were supposed to be effective in April. Jamal said there is currently no date for implementation. Carla said that the CR is important to AT&T and would like to see solid dates next month adding that the CR was escalated previously and did not do any good. Judy Schultz with Qwest said that we had just received word that funding was approved on Friday and IT will determine the dates as soon as possible. The dates will be provided, if available, before the March meeting. Bonnie said that Qwest had already provided the implementation date of April, (comment begin from Eschelon) 2004 but now states that this was just approved. Judy said all changes had to be reevaluated by Noteabart. (comment end from Eschelon). This CR will remain in Development status.

01/21/04 January CMP Meeting Jamal Boudhaouia with Qwest provided an update that there is no date for implementation. Bonnie Johnson with Eschelon thought this was going to be worked in conjunction with a Qwest retail project. Judy Schultz with Qwest said that this is one of the projects subject to the funding approval process. Even projects that had previously been approved are subject to the new approval process. Qwest will find out when the internal project for the VRU will be worked and how these two projects are connected. This CR will remain in Development status. (Begin comment from Bonnie Johnson - Eschelon) Qwest took an action to review this CR. Bonnie said this CR was waiting for an update already underway for the VRU. That was the delay after this was opened in June 2003. (end comment).

12/17/03 December CMP Meeting Jamal Boudhaouia with Qwest said that the CR is in development status and have no update on timeframe for implementation. Carla Pardee with AT&T said they would like to see progress on this CR by next month or AT&T will escalate the CR. This CR will remain in Development status.

11/19/03 November CMP Meeting Craig Suellentrop said that Qwest has accepted this CR and will make changes to the VRU. Work will be going on in the Qwest VRU and will provide implementation dates as soon as available. Carla Pardee with AT&T said that this CR has been open since June and AT&T would like a formal commitment on the timeframe. This CR will remain in Development Status.

10/15/03 October CMP Meeting Craig Suellentrop said that Qwest is looking at redesigning the repair VRU and plan to include changes for this CR at the same time. Carla Pardee with AT&T said AT&T is anxious to get the changes in place and asked for the implementation date. Craig said he hopes to have implementation dates for the November CMP meeting. Carla asked if the changes Qwest is looking at to make to the VRU should be included in a Qwest initiated CMP CR. Craig said it is still being looked at and determination has not been made if a CR will be required. This CR will remain in Development Status.

09/17/03 September CMP Meeting Craig Suellentrop said that Qwest accepts this CR with an implementation expected in 90 - 120 days. When a customer calls into the repair VRU between 11:30 p.m. - 5 a.m. the system accessed by the VRU to perform the ownership check may be down and the caller will automatically be transferred to a repair agent. However, during this time the system used by Qwest’s repair agents can still identify if a line is owned by a CLEC and will be able to direct the end-user to their local carrier. This CR will be moved to Development status.

08/20/03 August CMP Meeting Craig Suellentrop with Qwest reviewed the draft response to this CR. Craig said that Qwest has mapped the different ways that end users can get into repair VRU and now need the LOE. Qwest will have an update at the September meeting. This CR will be moved to Evaluation status.

07/16/03 July CMP Meeting Carla Pardee with AT&T presented this CR. Craig Suellentrop with Qwest explained the current repair VRU process. When an end user calls into repair they enter the telephone number they are calling about. If the end user presses 1 for a repair agent the VRU does no ownership check and the repair agent inputs the telephone and if the telephone number is CLEC owned the repair agent refers the end user to their alternate provider. If the end user presses 2 for automatic ticket entry and the number is CLEC owned, the VRU will respond that the number is not serviced by Qwest. Then the end user can press 1, if they are the customer for the account. If it is a TN owned by an alternate service provider, the VRU reads the repair number for end user to call for repair services. If the VRU does not recognize the TN, it reads contact your service provider for assistance. Carla with AT&T would like the VRU to respond when the end user enters a telephone number owned by alternate provider, by intercepting the call and routing it to the correct company. Craig will provide the VRU process to the CLEC Community for input on changes.

CLEC Change Request Clarification Meeting

2:00 p.m. (MT) / Tuesday, June 24, 2003

1-877-572-8687 PIN 3393947 # PC061103-1 Intercept CLEC customer calls to Qwest Repair Center

Name/Company: Donna Osborne-Miller, AT&T Dave Fane, AT&T Lydia Braze, AT&T Cathy Garcia, Qwest Craig Suellentrop, Qwest Michael Whitt, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of the change requested in the CR was reviewed. Currently, when an AT&T UNE-P end-user customer calls the Qwest repair line (800-573-1311), the call is routed to a Qwest representative, who then provides the customer with an AT&T 800 number. AT&T requests that Qwest change this procedure so that the call is intercepted when the customer enters their TN, and the customer should hear a branded message to the AT&T 1-800 repair number (800-288-2747). There are several reasons for this request: AT&T customers should not be speaking to a Qwest representative; it would be much more efficient to route the call directly to AT&T; it eliminates potential representative errors, and; it reduces the number of calls to the Qwest center. Dave Fane clarified that the intercept should be implemented for all CLEC customers, not just AT&T customers, and that the end user should be routed to the correct CLEC branding. In the testing, Dave used an AT&T test number and called into repair 6 or 8 times with different results.

Confirm Areas & Products Impacted Product impacted UNE-P

Confirm Right Personnel Involved Qwest confirmed that Craig Suellentrop & Cathy Garcia are correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation AT&T would like this change to be effective in August 2003 .

Identify any Dependent Systems Change Requests No dependent change requests were identified.

Establish Action Plan (Resolution Time Frame) AT&T will present this CR at the July CMP Meeting and Qwest will provide response at the August CMP. Donna Osborne-Miller requested that Qwest provide a response or an update if available at the July CMP.

06/18/03 June CMP Meeting Carla Pardee, Lydia Braze and Dave Fane with AT&T reviewed the walk on CR PC061103-1. Dave said that customers within the Qwest territory without Qwest local service call Qwest repair and AT&T would like the IVR to have the ability to route customers to AT&T and identify that the TN does not belong to Qwest. Other ILECs have this ability and it reduces calls to the repair center, mistakes made by repair representatives, and reduces call time for end users, who sometimes are involved in a call taking up to 3-4 minutes before the repair representative recognizes that the customer is not a Qwest customer. Eschelon, U S Link and McLeod all said they support this change request. Lynne Powers with TelWest asked if the end user would be inputting their telephone number and Dave said that is what occurs in the PacBell region. There will be a clarification call on this change request.


CenturyLink Response

September 9, 2003

For Review by the CLEC community and discussion at the September 17, 2003 CMP Meeting

Carla Pardee AT&T

SUBJECT: Qwest’s Change Request Response - CR PC061103-1 "Intercept CLEC customer calls to the Qwest Repair Center"

This CR requests that when a CLEC end-user calls into Qwest repair “the call is intercepted when the end-user enters their TN, and the customer should hear a branded message to the [CLEC] 1-800 repair number.

The August response illustrated Qwest’s current Voice Response Unit (VRU) scripting when an end-user calls into Qwest repair. For this CR Qwest investigated the possibility of performing the ownership check and replaying the same scripts for Option 2 as are performed for Option 1.

Qwest accepts this CR and will make the changes indicated above. The systems accessed for this ownership check may be down for maintenance nightly between 11:30 pm and 5:00 am Mountain Time. Therefore, during this period, it may not be possible to perform the ownership check. However, the system used by Qwest’s repair agents will still detect if a line is owned by a CLEC and the agent will direct the end-user to call his or her local carrier.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Cheryl Rock, Senior Process Analyst, Qwest

August 13, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the August 20, 2003 CMP Meeting

Carla Pardee AT&T

SUBJECT: Qwest’s Change Request Response - PC061103-1 "Intercept CLEC customer calls to the Qwest Repair Center"

AT&T’s CR requests that when a CLEC end-user calls into Qwest repair "the call is intercepted when the end-user enters their TN, and the customer should hear a branded message to the [CLEC] 1-800 repair number."

The attached document illustrates Qwest’s current Voice Response Unit (VRU) scripting when an end-user calls into Qwest repair. For this CR, Qwest investigated the possibility of performing the ownership check and replaying the same scripts for Option 2 as are performed for Option 1.

The direct number to get into repair for all 14 states in Qwest’s local service region is 1-800-573-1311. However, other Qwest VRU systems have options allowing the caller to transfer to Local Network repair. Callers coming from these other systems do not always input their TN into the repair VRU. Because of this, Qwest has to map all of the various methods of getting into the repair VRU and determine how/if an ownership check can be conducted. Qwest is now in the process of getting an estimate for feasibility to perform the ownership check.

Qwest will provide a revised response at the September CMP meeting with the findings of this research.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Cheryl Rock, Senior Process Analyst, Qwest


Open Product/Process CR PC062603-03 Detail

 
Title: Business Rules Clarificaiton calls and event notification updates through the Addendum processs
CR Number Current Status
Date
Area Impacted Products Impacted

PC062603-03 Completed
7/12/2004
All All
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Owen, Randy
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T requests that the Business Rules be opened up for clarification and that event notification updates be incorporated into the Addendum process. We seek Qwest adoption of SBC's process of a standard conference be established to address issues or concerns with the event notification and addendum updates. This SBC process includes conference call logistics: date, time and bridge number. They also send out a notification capturing the questions and answers provided durig the conference call.

Expected deliverable: Adoption of SBC process relative to Business Rules Clarification and event notificattionupdates through the Addendum process


Status History

06/26/03 - CR Submitted

06/30/03 - CR Acknowledged

07/02/03 - CR Posted to Web

07/11/03 - Held Clarification Meeting

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/31/03 - Held Ad Hoc Meeting with CLEC community

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/09/03 - Held Ad Hoc Meeting with CLEC community

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/05/04 - Qwest sent SYST.03.05.04.F.01458.15.0_Comb_CLEC_QuestLog Combined Question Log for 15.0

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/23/04 - Qwest sent Level 3 PROS.04.23.04.F.01600.Addendum_Process_Update, proposed effective date 6/7/04

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/21/04 - Qwest sent final notice PROS.05.21.04.F.01679.FNL_AddendumProcessUpdate, effective date 6/7/04

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - July CMP Meeting minutes will be posted to the database


Project Meetings

07/21/04 July CMP Meeting Randy Owen – Qwest advised that all items on this CR have been met. The process is in place and working. The CLECs agreed to close this CR. This CR will move to Completed status.

06/16/04 June CMP Meeting Donna Osborne-Miller with AT&T said that AT&T is migrating to 15.0 and the business partners submitted questions to the Q&A process and responses were received. The Qwest responses asked that the questions be submitted through the external documentation process and the response was sent within 14 days. Regina Mosley is not on the call today and is available tomorrow to discuss during the systems meeting. Randy Owen with Qwest said that the questions submitted were not determined to be related to EDI. Liz Balvin with MCI said there were USOC driven questions and the business rules are not in the EDI disclosure. This CR will remain in CLEC Test status.

05/19/04 May CMP Meeting Randy Owen with Qwest said that the CR is in CLEC test with 15.0 and that we are waiting for feedback. Carla Pardee from AT&T said they would start 15.0 in June. Randy asked if they could look at other CLECs information. Amanda Silva with VCI said there was a business rule for conversion on TN and the business rule is there but got rejected. There was supposed to be an event notification regarding the work around. Randy took the two trouble ticket numbers and will provide information at Thursday’s meeting. Liz Balvin with MCI said she attended one of the conference calls and has recommendations for improvement: 1) Highlight in the ticket that a conference call will be taking place. Put in bold type. 2) On the call Qwest should bring forth what the changes were, what it is changing from and what is it changing to. Unless you have the event notification during the call it is hard to understand what is changing. Add what interface is impacted by this change. Randy said he would take this back and can probably accommodate the request. Bonnie Johnson with Eschelon said this is AT&T’s CR and they could be viewing the CR differently than Qwest. This CR should be allowed to go into a different status. Eschelon had submitted a CR to change the CMP document to add a re-open status and Qwest voted no. (Begin Bonnie’s comment) Bonnie said that Eschelon will not be closing CR’s until we go into the release that the CR was implemented in. Bonnie recommended that Qwest and the CLECs find a status that appropriately reflects this situation. (end Bonnie’s comment) Linda Sanchez-Steinke said that the CR is not ready to be closed. This CR will remain in CLEC Test status

04/21/04 April CMP Meeting Randy Owen with Qwest advised that we have held conference calls with the release as a trial and we are drafting the implementation notification that will include a comment cycle and plan to have the notification out at the end of this week. Donna Osborne-Miller asked for an update on the action item opened for the escalation process. Randy said that this was related to the question log and he was still researching the action item on the system side. This CR will remain in CLEC Test status.

03/17/04 March CMP Meeting Randy Owen with Qwest said that the combined question log will be provided with 15.0 and two or three event calls have taken place. Donna Osborne-Miller said that discussion on the wrap-up of the global action items would take place during the Systems meeting tomorrow. Phyllis Burt with AT&T said she would provide feedback on the question and answer log and the event log. This CR will move to CLEC Test status. -- Thu 2/19/04 3:59 PM From: Sanchez Steinke, Linda To: 'Osborne-Miller, Donna, NKLAM' Subject; RE: Phyllis's items for documentation

Thank you Donna, I forwarded to Beth Foster, Kyle Kirves, and Randy Owen.

Linda Sanchez-Steinke 303-382-5768

Thu 2/19/04 2:55 PM From; Osborne-Miller, Donna, NKLAM [dosborne@att.com] To: Sanchez Steinke, Linda cc: New Cr, Cmp Subject; Phyllis's items for documentation

Hi Linda, Can you be sure to give this list to Beth Foster? It pertains to our conversation pertaining to PCO62603-03 and the Q&A log breakout of categories.

thank you, Donna

Attachment Category breakdown based on IMA Appendix Categories for Collective Q&A Migration

A.1 ADDRESS VALIDATION A.2 APPOINTMENT RESERVATION A.3 TN APPOINTMENT CANCELLATION A.4 CONNECTING FACILITY ASSIGNMENT A.5 CUSTOMER SERVICE RECORDS A.6 DESIGN LAYOUT RECORD (DLR) RETURN A.7 FACILITY AVAILABILITY QUERY A.8 LISTINGS RECONCILIATION A.9 LOOP QUALIFICATION A.10 MEET POINT A.11 RAW LOOP A.12 SERVICE AVAILABILITY A.13 TELEPHONE NUMBER ASSIGNMENT B.1 END USER B.2 LOCAL SERVICE REQUEST C.1 CENTREX RESALE SERVICES C.2 DIRECTORY LISTING C.3 DID RESALE SERVICE C.4 HUNT GROUP INFORMATION C.5 LOOP SERVICE C.6 LOOP SERVICE WITH NUMBER PORTABILITY C.7 NUMBER PORTABILITY C.8 PORT SERVICE C.9 RESALE C.10 RESALE FRAME RELAY C.11 RESALE PRIVATE LINE C.12 RESALE SPLIT C.13 UNE CENTREX 21 (P OR STAR) SPLIT D.1 BILLING COMPLETION NOTICE D.2 COMPLETION RESPONSE D.3 DIRECTORY SERVICE CONFIRMATION AND ERROR DETAIL (DSRED) RESPONSE D.4 LOCAL RESPONSE D.5 PROVIDER NOTIFICATION D.6 SERVICE ORDER STATUS INQUIRY D.7 STATUS UPDATES D.8 PENDING SERVICE ORDER NOTIFICATION GENERAL/OTHER

02/18/04 February CMP Meeting Beth Foster with Qwest said that this CR has been discussed at the global action item meetings and last week Qwest met with AT&T and Liz Balvin with MCI. Qwest took action items from that meeting and determined that meeting minutes will be provided and posted on the production support page along side the trouble ticket information which is currently populated on the Wholesale Web site. There was discussion regarding the timeframe of posting meeting minutes. Connie Winston with Qwest said they would post the minutes within 3 days and would strive to get completed as soon as possible. Connie also said that Qwest would capture necessary information, necessary action items and a general re-cap of the meeting intent. Phyllis Burt mentioned that issues of importance to Qwest might not be the same as those that are important to the CLEC. Connie suggested that the CLEC could provide a red-line of meeting minutes back to Qwest.

Donna Osborne-Miller with AT&T said that we could put this CR into CLEC test and see how the process works.

Beth said that another action item was to look at how to handle the business rules clarification piece of the request, and noted that AT&T had initially asked that the Disclosure documentation be updated when CLECs ask for clarification. Qwest would like to start a single Q&A log with 15.0 release and provide the log on the wholesale website out where the EDI Documentation FAQ pages currently resides. This single Q&A log will provide needed clarification to documentation, a way to see documentation before the addendum is posted, and, will allow everyone to see what questions other CLECs have had and how Qwest has responded. Beth explained that the process for EDI will be covered by the CLECs EDI Implementation Teams, and included in the body of the Q&A document that will be posted.

Randy Owen with Qwest said an e-mail address would be set up for CLECs to send questions.

Phyllis Burt requested the Q&A log be categorized by topic, such as Appointment Scheduling. Randy Owen will take that action item to see if this is feasible. Donna Osborne-Miller said the Q&A log would be cumbersome if not broken out by fields.

Beth asked if everyone agreed that the process trial could begin with 15.0, and once the documentation was posted the CR could move into CLEC test for AT&T feedback. All agreed and Beth said that a Systems Notification will be sent stating that the Q&A log will be located on the Wholesale Web Site, under OSS, IMA, EDI Documentation under the FAQ link. This CR will move to Development Status.

Fri 2/13/04 8:38 AM From; Linda Sanchez-Steinke To; 'dosborne@att.com' Subject; Updated Draft Response PC062603-03

Hi Donna -

As a follow up to yesterday's meeting regarding PC062603-03, attached is the updated draft response.

As we discussed, Qwest took the following action items; documentation addendum notification meeting minutes, question and answer log. We will give an update at the CMP meeting.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

Meeting Minutes PC062603-03 Business Rules Clarification calls and event notification update through the Addendum process CMP Product & Process February 12, 2004 1-877-572-8687, Conference ID 3393947# 2:00 p.m. - 2:30 p.m. Mountain Time

PURPOSE

This meeting was held to discuss CR PC062603-03. The following is the write-up of the discussions, action items, and decisions made in the working session.

List of Attendees: Liz Balvin - MCI Regina Mosley - AT&T Phyllis Burt - AT&T Donna Osborne-Miller - AT&T Beth Foster - Qwest Randy Owen - Qwest Kyle Kirves - Qwest Lynn Stecklein - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

Linda Sanchez-Steinke with Qwest welcomed all attendees and explained that Qwest scheduled this meeting to discuss changes that have been implemented to address this CR.

Kyle Kirves said that Qwest has made progress in the following areas; providing clearer information in the event notifications, revisited the event notification template, provide additional reasons behind severity issues, schedule conference calls on major impacts, and have initiated a CR to change the CMP document Section 12. A good example of Qwest’s effort to improve is the 2/13 conference call clarifying Event Notification 674340. AT&T said they appreciated these efforts.

Phyllis Burt with AT&T asked when clarification calls would take place. Kyle said they would take place for addendum changes. Phyllis Burt and Donna Osborne-Miller asked about meeting minutes from the clarification calls and Kyle said that minutes would be recapped in disclosure. Phyllis added AT&T prefers to get minutes as soon as possible because of the impacts to production. Randy Owen and Kyle Kirves agreed to address this action item and respond at Product Process CMP.

Phyllis Burt asked about the question and answer log and said that with IMA 11 AT&T had lots of questions. Kyle said that in the addendum there will be a "change from" and a "change to" identification. Beth Foster added that the event notification would be in disclosure. Donna asked what the timing would be and Kyle answered that it may be two weeks after notification.

Phyllis Burt said that when working with Wendy Green last year they wanted to have the ability to have clarifications added to the document about how the system behaves and didn’t want to wait until the next IMA release to get clarification updated.

Beth Foster suggested that documentation changes could be made via the documentation request website. Kyle stated the website is for everything but disclosure document changes. Randy added that many times documentation changes have coding changes and is concerned about that. Kyle said that documentation rejects are not representative of what the system is doing, for simple clarification that represents enhancement to documentation. Phyllis said that AT&T builds systems from the documentation and then it will become a production problem. Beth said a trouble ticket should be opened for production problems. Phyllis said that AT&T asks questions and looks at the question log and gives them a good clarification and this is not in the Qwest disclosure document. Liz Balvin with MCI said we would want to assure that clarifications don’t get lost in the flow of the next release. Phyllis will provide examples of clarification questions and answers. Randy Owen said that Qwest had been considering a single Q&A log with all CLEC questions and clarifications. Liz added that the while Qwest might think clarification, it may be CLEC code impacting to have the update in the addendum especially from the EDI standpoint.

Qwest will provide an update to the open action items at the Product Process CMP.

01/21/04 January CMP Meeting Connie Winston with Qwest said that this issue has been worked through oversight and in the emergency meetings. Qwest can initiate a quick meeting and CLECs are also able to initiate meetings. Carla Pardee with AT&T said that there had been a meeting held on loss and completion. Connie also said there are potential CMP language changes being proposed. Qwest will have an updated response in February. This CR will remain in Evaluation status.

12/17/03 December CMP Meeting Connie Winston with Qwest said this CR has been discussed in the Global Action Item meetings and expects that the Global Action Item meetings will be wrapping up in the January timeframe. This was also discussed at the Oversight meeting and whether the new process will meet the intent of this CR.

11/19/03 November CMP Meeting Kit Thomte with Qwest said that this CR was being discussed with the Global Action Item meeting 11/18/03. This CR will remain in Evaluation status.

10/15/03 October CMP Meeting Kit Thomte with Qwest said that this CR was discussed at the 10/14/03 Global Action item meeting. It was agreed this CR would remain in Evaluation status.

09/17/03 September CMP Meeting Connie Winston with Qwest provided an update and said that Qwest is reviewing what we can do better. Qwest has implemented calls to appropriate CLECs. When faxing becomes only solution Qwest is raising the severity level because there is no way for the CLEC to Communicate with Qwest. Liz Balvin said that a severity level 1 or 2 is fine and that 3 or 4 is not acceptable. Bonnie Johnson said there is a difference in the definition of immediately. Connie said that at Event Notification closure Qwest is providing clearer information about what we did and what we are doing. Monica Avila with VarTec provided an example that when Qwest end user fields went from optional to conditional, it required coding outside of the release. Liz Balvin said that because the fields were optional, had Qwest lifted the edits as emergency patch, then CLEC coding wouldn’t have to change. Connie said there was concern not knowing documentation was wrong CLECs didn’t know the CR made it into the release. Liz said by TN and SANO didn’t know back end changes were taking place. Liz said that address information needs to match SAV response. SAV needs to be in disclosure and in addendum for optional to conditional. Connie said that we are reviewing when it makes sense to reference the PCAT. Liz said that if it impacts coding then is should be in disclosure. Connie would like to roll this CR into the discussion of the Global Action item. It was determined that 10/14 from 10 a.m. –5 p.m. would be a good timeframe to discuss the CRs. This CR will remain in Evaluation Status.

Ad Hoc Meeting Minutes PC062603-03 Business Rules Clarification calls and event notification updates through the Addendum processs CMP Product & Process September 9, 2003 1-877-572-8687, Conference ID 3393947# 8:00 a.m. - 8:45 a.m. Mountain Time

PURPOSE

At the August CMP Meeting, participants agreed to hold a conference call to provide additional clarity and explain Phyllis Burt’s series of questions and statements about intent and meaning of the change request. The following is the write-up of the discussion.

List of Attendees: Julie Pikar - U S Link Jen Arnold - U S Link Kim Issaacs - Eschelon Donna Osborne-Miller - AT&T Phyllis Burt - AT&T Regina Mosley - AT&T Tom Hyde - Cbeyond Byron Dowding - Alltel Stephanie Prull - McLeod Randy Owen - Qwest Kyle Kirves - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss and get further clarification about the AT&T CR PC062603-03. At the August CMP meeting, Qwest provided the draft denial response and Phyllis Burt with AT&T provided a counter proposal at the CMP meeting and asked that Qwest provide an updated response at the September meeting.

Donna Osborne-Miller with AT&T provided the denial response red-lined with a series of questions and statements written by Phyllis Burt. Kyle Kirves with Qwest had received the questions/statements. Phyllis Burt with AT&T said that the purpose of the CR was to provide clearer information in event notifications. Phyllis said that when event notifications are not clear, AT&T goes to their implementation manager and then calls the help desk and try to get answers, but production problems are not clear. Phyllis said that with the SBC process there is a clarification call where questions can be asked. The issue is, if workarounds conflict with other business rules, then something else can fail. When AT&T Consumer converts from IMA 12 to 13 Phyllis will have to go back through the event notifications for the 13.0 release and look at to see if there is anything they would need to consider.

Phyllis said that the purpose behind the CR is to make sure there are not long gaps in time on production impacts. AT&T suggests that there is a need for good clarification and AT&T has hundreds of questions in their Q&A log, and weeks go by and questions linger and wait. AT&T wants to find other avenues to head off production problems.

Stephanie Prull with McLeod will not go back and look at Event Notifications for releases. McLeod will only do what is documented in the Disclosure and try to code to the business rules. McLeod stated that they should not have to implement to anything other than the business rules. If McLeod has a CR or UR when going in then will code to it.

Phyllis reiterated that there are two big things in the red-lined response: 1) AT&T wants to make sure that they understand the work around and that it is not conflicting with other rules so they don’t have to re-word the workaround. 2) AT&T would like clarification around the current impact and if they will receive rejects or jeopardies based on that impact.

Kim Issacs said that Eschelon uses EDI and GUI (used for resale & UNE-P) and if they receive a work around notice and it conflicts with business rules Kim will call the help desk. Kim sometimes can wait up to two days to get an answer on what the product impact and issues are. In addition, they get communication of workarounds and then get rejects from the centers.

Phyllis and Stephanie both have concerns with the PCRM ticket 167601 (LNUM) and still can’t explain what the impacts are to their companies. Randy Owen with Qwest said that he didn’t have specifics, and knows that the issue is discussed every day trying to get to a solution.

U S Link said they are not on EDI, but share frustrations with process and support the AT&T CR. Randy said that we would take this information back and look at it further. Randy said that the CLECs should call the technical escalations if they are waiting too long on open trouble tickets that are severity level 3 and should escalate to severity level 2.

Phyllis said that she suggests Qwest look at the proposal of having CLEC calls because questions and problems will be brought up as a group and would trigger discussions. With the technical escalation process, McLeod may raise an issue and AT&T may raise another issue, but discussion as a group would help.

Randy said that he would like to know the rules and timing of the potential CLEC call. Kim said that having all CLECs on a call (for LNUM issue) would have helped. Stephanie Prull said that a call would not be needed on every event notice, but suggested that on event notices that the CLECs send an e-mail saying they want a call and if several CLECs sent an e-mail then Qwest should have a call.

Phyllis said that AT&T just requests calls on workarounds event notifications that change a business rules and documentation appears not to be working the way Qwest says it is working.

Phyllis also said that the second part of the red-lined document that with IMA 11 have Q&A log with major gaps. The next major release these will be worked into the addendum process.

Randy said that we will take that back also and that if there is a bug identified or is this enhancement which would have to be in the next major release.

Phyllis discussed the documentation for service address validation when look at Qwest Documentation it appears copied from pre-order, order and SANO populated. Phyllis said that what needs to be done is a documentation change.

Linda asked if there were any other questions or additional information to provide. There were no additional comments or questions.

08/20/03 - August CMP Meeting Connie Winston with Qwest reviewed the draft response for this CR. Connie said that the information provided in the Event Notification Closure should include additional information that identifies the change, what was changed and what it was changed to. CLECs can also use the Technical Escalations to get more clarity in Event Notification. Donna Osborne-Miller with AT&T said that Phyllis Burt has provided documentation to the CLEC Community on Event Notifications and Donna will e-mail to Linda Sanchez-Steinke. Discussion continued when Connie Winston came into the CMP meeting. What AT&T would like is to hold an Ad Hoc meeting and provide additional clarity and explain Phyllis Burt’s counter proposal’s intent and meaning. Liz said that CLECs see the addendum as changes to EDI / GUI and want the ability to comment on the addendum. This CR will be moved to Evaluation status and Qwest will provide a revised response at the September meeting.

8/20/03 4:53 p.m. Sent by: "Osborne-Miller, Donna, NKLAM" To: Linda.Sanchezsteinke@qwest.com> cc: cmpcr@qwest.com> Subject: Phyllis's counterproposal to documentation CR Linda,

Here is the redline document Phyllis composed that I spoke with Connie about this morning.

Thank you, Donna

ATTACHMENT - PC062603-03 Response - FEEBACK.doc

AT&T is seeking a clear understanding of the problem via a clarification call so all CLECs have a clear understanding of the problem/issue and the impact to their business so that they can make the appropriate business decisions. Currently, the event notification issued today are very vague as to the actually QWEST problem and the impact to the CLEC business. How can I identify this problem in production today? Is QWEST currently rejecting these orders, sending jeopardies or are the orders completing successfully but not being provisioned correctly?

AT&T is requesting whenever a workaround is document that a clarification call to clearly communicate (1) the workaround in detail (2) the current impact to the CLECs order or service in production Example: (a) A notification for PCRM Ticket Number: 167601 has been issued several times. Initially it was not clear which Products were impacted. The extent of the change required and what happens to our orders when this occurs is still unknown. I’ve personally tried getting an answer via the contact number provided on the notification. A QWEST TT has been open since Friday August 15.

AT&T is not requesting that the entire CLEC Q&A log be provided. QWEST has requested that AT&T provide the exact disclosure document update in the Q&A log. AT&T is requesting that CLECs that request documentation of clarifications provided in the Q&A and provide the exact wording required for the update to the Disclosure Document should be able to get these worked into the next Addendum update issued.

AT&T Consumer disagrees that the current process is working effectively. If this were the case, I would not be making this request. The current notification process only provides confusion due to the lack of in depth analysis

Ad Hoc Meeting Minutes PC062603-03 Business Rules Clarification calls and event notification update through the Addendum process CMP Product & Process July 31, 2003 1-877-572-8687, Conference ID 3393947# 9:00 a.m. - 9:30 a.m. Mountain Time

PURPOSE

At the July CMP Meeting, participants agreed to hold a conference call to discuss and gain input from CLECs on this CR. The following is the write-up of the discussions, action items, and decisions made in the working session.

List of Attendees: Liz Balvin - MCI Stephanie Prull - McLeod USA Regina Mosley - AT&T Phyllis Burt - AT&T Donna Osborne-Miller - AT&T Kyle Kirves - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

Linda Sanchez-Steinke with Qwest read the change request description: AT&T requests that the Business Rules be opened up for clarification and that event notification updates be incorporated into the Addendum process. We seek Qwest adoption of SBC's process of a standard conference be established to address issues or concerns with the event notification and addendum updates. This SBC process includes conference call logistics: date, time and bridge number. They also send out a notification capturing the questions and answers provided during the conference call.

Donna Osborne-Miller with AT&T said there were copies of the e-mail handout provided at the July CMP meeting and asked if CLECs on the call had the opportunity to look at the documentation. Liz Balvin asked if AT&T would give an overview. Linda Sanchez-Steinke with Qwest said the handout is also included in the body of the CR in the interactive report.

Phyllis Burt with AT&T provided an overview of the handout. Phyllis explained how the SBC process of event notification is different from the Qwest process. In the Qwest event notifications there is an e-mail address to send questions to. SBC’s process for appending business rules documentation includes a set conference call within 3-5 days of the notification. This set conference call time is convenient because it allows everyone to have an hour free on their calendar and the opportunity, during event notification, to discuss issues or questions and understand how business rules are impacted. The meeting minutes from the conference calls are included in the final notification and that allows everyone unable to attend the conference call ability to read the minutes for additional information. AT&T is looking for Qwest to provide this type of process. Phyllis also said that if Qwest had this type of conference call it would provide the opportunity to discuss the change and the impact. That way everyone would understand how to communicate and what the business rule is. In addition, sometimes CLECs get different answers from different people at Qwest and we are all trying to understand and seek clarity to the blocking issues.

Liz Balvin with MCI said the SBC process seems to be a more expeditious approach.

Kyle Kirves with Qwest asked if CLECs were talking about providing PCAT and LSOG updates or addendum and disclosure document impacts. Phyllis Burt with AT&T said the Qwest notification explains that something is happening but there is no addendum. Kyle Kirves asked if CLECs were looking for information in the disclosure notification and if they want the notification to provide what the documentation change will be. Phyllis said yes.

Linda Sanchez-Steinke with Qwest asked if there were any additional questions. There were no questions.

07/16/03 July CMP Meeting Donna Osborne-Miller with AT&T presented this CR. Donna stated that AT&T would like Qwest to adopt the SBC process to address issues and concerns with event notifications and addendum updates. Donna said that they receive many event notifications from Qwest and the SBC process includes a clarification call 1-3 days after the notification to understand impacts. In addition, meeting notes are posted with a question and answer log. With EDI implementation 250-300 questions have been asked and some of the questions are not answered. Today, CLECs share their logs with other CLECs, MCI shares their log and McLeod shares their log. Judy Schultz with Qwest asked if the clarification call would take place during the production support timeframe. Donna said she is not sure if there is commonality between this CR and the CR for System Defects. Liz Balvin with MCI commented that if the Q& A logs were made public then they may not have to go to EDI teams which would be less work for Qwest. The CLEC community agreed to hold an ad hoc meeting to discuss this CR and Donna Osborne-Miller will provide the dates available for AT&T SMEs to Linda Sanchez-Steinke.

CLEC Change Request Clarification Meeting

2:00 p.m. (MDT) / Friday, July 11, 2003

1-877-260-8255 7616533# PC062603-03 Business Rules Clarification calls and event notification updates through the Addendum processs

Name/Company: Donna Osborne-Miller, AT&T Carla Pardee, AT&T Phyllis Burt, AT&T Regina Mosley, AT&T Kyle Kirves, Qwest Dan Busetti, Qwest Wendy Thurnau, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change AT&T’s CR requests that Qwest adopt SBC’s process of a standard conference to address issues or concerns with event notification and addendum updates. Phyllis Burt with AT&T read the e-mail below at the Clarification Meeting for participants on the call:

(1) Several Event Notifications have come out that required discussion (see below). This CR is requesting that QWEST provide a clarification call for notifications that impact CLECS. The call should be held within 1-3 business days after the announcement at a set standard time for example (11am Mountain/12pm Central/1pm Eastern). (a) The initial notification should include the addendum summary if impacts the disclosure documents. (b) The appropriate SMEs should attend the clarification call to answer any issues/concerns and a walkthrough of the appropriate documentation should be completed. (c) The closure notifications should include meeting minutes from the clarification call and the new addendum version should be posted on the Disclosure document website with a reference to the closure notification #.

Event Notification: 85434 IMA EDI GUI Initial Closure 061803 "Description of Trouble: CLECs may be experiencing difficulty processing POTS and UNE-P POTS orders on the Resale form when attempting to change a line level USOC and a non-line level USOC on the same order. Business Impact: CLECs may not be able to process POTS or UNE-P POTS orders on a single form when a line level and a non-line level USOC is changing. Qwest Proposed Work Around: CLECs should send the requests for line and non-line level USOCs separately. Alternatively, CLECs may submit their orders, mark the request for manual handling, and provide instructions in the REMARKS."

Event Notification: 75800 IMA EDI GUI 060503 Initial-Closure Description of Trouble: CLECs may be experiencing difficulty processing conversion LSRs with a Block Activity (BA) = N (no change to existing blocking). Business Impact: CLECs may be experiencing difficulties retaining existing blocks during conversion. Qwest Proposed Work Around: CLECs should use the Feature Activity (FA) = V to recap blocking USOCs.

(2) QWEST/CLEC Q&A log clarification should be captured in the Addendum. There should be a monthly process to submit clarification updates. Followed by a standard monthly event notification and review as discussed above.

Phyllis also said that MCI had quite a few questions when migrations were done and it would have been helpful to have Q & A logs for other CLECs to refer to. SBC identifies a timeline when the answers to questions will be given and includes center personnel and OSS personnel in their clarification calls for notifications that impact CLECS.

Phyllis said that it would have been helpful for the April release to have included a Qwest/CLEC Q&A log because code wasn’t in the business rules. In addition, Phyllis has a concern that if IMA 10 or 11 had a clarification log then they could refer back to it for IMA 12 and 13. Whatever other CLECS have learned has not been documented in the disclosure document.

Donna asked Kyle to provide an overview of the addendum process Qwest currently practices. Using the example above ( event 85434), Kyle described how this notification would justify an addendum. Specifically, he stated that, in this case, if the system were not functioning as documented, and the issue compromised the CLEC’s ability to process transactions, then a notification would be issued, and an addendum published. Situations that Qwest finds worthy of an addendum are those instances where the system is not functioning as documented. Clarification types of issues do not necessitate an addendum.

Confirm Areas & Products Impacted The area of this Change Request impacts addendum notifications.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation AT&T’s expectation is that Qwest adopt the SBC process relative to Business Rules Clarification and even notification updates through the addendum process.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) AT&T will present this CR at the July CMP meeting.

To: Sanchez Steinke, Linda, Donna Osborne-Miller From: Burt, Phyllis S, CSCIO [phyllissburt@att.com] Sent: Fri 7/11/03 1:56 PM Subject: RE: Clarification call for the documentation CR Here's some additional information for our call today.

(1) Several Event Notifications have come out that required discussion (see below). This CR is requesting that QWEST provide a clarification call for notifications that impact CLECS. The call should be held within 1-3 business days after the announcement at a set standard time for example (11am Mountain/12pm Central/1pm Eastern). (a) The initial notification should include the addendum summary if impacts the disclosure documents. (b) The appropriate SMEs should attend the clarification call to answer any issues/concerns and a walkthrough of the appropriate documentation should be completed. (c) The closure notifications should include meeting minutes from the clarification call and the new addendum version should be posted on the Disclosure document website with a reference to the closure notification #.

Event Notification: 85434 IMA EDI GUI Initial Closure 061803 "Description of Trouble: CLECs may be experiencing difficulty processing POTS and UNE-P POTS orders on the Resale form when attempting to change a line level USOC and a non-line level USOC on the same order. Business Impact: CLECs may not be able to process POTS or UNE-P POTS orders on a single form when a line level and a non-line level USOC is changing. Qwest Proposed Work Around: CLECs should send the requests for line and non-line level USOCs separately. Alternatively, CLECs may submit their orders, mark the request for manual handling, and provide instructions in the REMARKS."

Event Notification: 75800 IMA EDI GUI 060503 Initial-Closure Description of Trouble: CLECs may be experiencing difficulty processing conversion LSRs with a Block Activity (BA) = N (no change to existing blocking). Business Impact: CLECs may be experiencing difficulties retaining existing blocks during conversion. Qwest Proposed Work Around: CLECs should use the Feature Activity (FA) = V to recap blocking USOCs.

(2) QWEST/CLEC Q&A log clarification should be captured in the Addendum. There should be a monthly process to submit clarification updates. Followed by a standard monthly event notification and review as discussed above.

Thanks,

Phyllis


CenturyLink Response

March 9, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the March 2004 CMP Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Revised Response - PC062603-03 "Business Rules Clarification calls and event notification updates through the Addendum process"

This response is a supplementary response to AT&T’s CR PC062603-03. Originally, Qwest denied this CR at the August CMP meeting. In response to a series of questions and statements provided by AT&T, and as a result of an ad hoc call held on 09/09/03, Qwest reviewed the points raised by the CLECs.

As a result of the discussions held at the Global Action Items Meetings (held on September 12, 2003; October 14, 2003; November 4, 2003; November 18, 2003; December 16, 2003), Qwest believes that the spirit of the original request has been met.

Qwest is using this document to supplement its response to the request dated February 11, 2004. Subsequent to the February 11 response, a meeting was held to discuss any gaps between Qwest’s understanding of the request, and the request’s intent. During that meeting, two gaps were discussed. They were:

- AT&T requested that meeting minutes from any discussion around “Addendum to Disclosure Documentation” notifications be provided to the CLECs. Qwest committed to provide meeting minutes for these sessions no later than three (3) business days after the meeting. As the notification form itself is not designed to capture meeting minutes from the discussion, Qwest will record minutes from the meetings and publish them to the Production Support web site under the notification number. CLECs will have an opportunity to provide redlined edits to the minutes back to Qwest. - If any updates to the notification itself are required, Qwest will make those changes and republish the notification within one (1) day. - Regarding clarification to business rules, Qwest stated that it will continue to observe its established process for addendums and clarifications. Where “bugs” are identified, Qwest will publish a notification, documenting the bug, to be followed up by an addendum. For clarifications that do not constitute bugs, Qwest will capture the clarification in its Question/Answer log. Further, Qwest will start a single Q&A log with the15.0 release and provide the log on the wholesale website where the EDI Documentation FAQ pages currently reside. This single Q&A log will provide needed clarification to documentation, a way to see documentation before the addendum is posted, and, will allow everyone to see what questions other CLECs have had and how Qwest has responded.

It was agreed that the process trial could begin with 15.0, and once the documentation was posted, the CR could move into CLEC test for AT&T feedback.

Qwest maintains that the original request has been satisfied.

Sincerely,

Connie Winston Director, Information Technology Qwest

February 11, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the February 2004 CMP Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Revised Response - PC062603-03 "Business Rules Clarification calls and event notification updates through the Addendum process"

This response is a supplementary response to AT&T’s CR PC062603-03. Originally, Qwest denied this CR at the August CMP meeting. In response to a series of questions and statements provided by AT&T, and as a result of an ad hoc call held on 09/09/03, Qwest reviewed the points raised by the CLECs.

As a result of the discussions held at the Global Action Items Meetings (held on September 12, 2003; October 14, 2003; November 4, 2003; November 18, 2003; December 16, 2003), Qwest believes that the spirit of the original request has been met.

Qwest responds to these items by stating that, since the implementation of IMA EDI Release 14.0 on December 8, 2003, Qwest has made best efforts to invigorate the notification process. Qwest maintains that by revisiting its process, providing training to notifications authors, and revising the notification template itself. Qwest itemizes its actions taken to address this CR as follows:

- Qwest is endeavoring to provide clearer information in the event notifications; and positive feedback from the CLECs indicates that Qwest has made significant progress on this front. - Qwest has a contingency plan in place to initiate calls with CLECs for high-profile, major impact event notifications and announce the conference calls in the body of the event notification. Qwest does not recognize the feasibility of initiating calls for every event, but will comply with major impact events, as stated. - As always, Qwest has worked to mitigate issues quickly; however, some production gaps will always exist due to prioritization of issues for resolution. - Qwest’s new internal process allows for event notification authors to work with the Interconnect Service Centers to generate appropriate, working workarounds that are approved by both Qwest and the CLEC. - Qwest now provides complete descriptions of impacts and error messages resultant from the issue, and has a separate place on the event notification form for capturing the error message verbatim. - Qwest now captures changes in documentation resulting in the body of the notification itself, in a “Change From:” and “Change To:” format. - As part of change request PC010704-1CM, Qwest is working toward language changes in the CMP document. The language change describes process improvements regarding notifications and documentation changes that cover some of the requests in this CR. Specifically, Qwest has updated the CMP document to demonstrate the following commitment regarding notifications, workarounds, and conference calls to CLECs:

Qwest will attempt to make a software patch when the system is not working as defined in the technical specifications and/or the GUI systems documentation, and issue an event notification clearly defining the change.

If Qwest determines that a software patch is not feasible, and/or Qwest or any CLEC identifies a Patch Release of software or related systems documentation changes that may impact CLEC production coding, Qwest will issue an event notification, initiate a Technical Escalation, and request a joint meeting between Qwest and the CLECs in order to discuss the particular Patch Release. Qwest will notify CLECs of the joint meeting in which Qwest will review the Patch Release, the proposed solution, and the variables which affect the resolution. In all instances, these joint meetings are exempt from the five (5) business day advance notification requirement described in Section 3.0. At this joint meeting, Qwest and the impacted CLECs will discuss how the pending Patch Release will affect their code. Qwest and the impacted CLECs will discuss any potential resolution options and implementation timeframes. In the event that agreement cannot be reached between Qwest and the impacted CLECs regarding the type of Patch Release to be implemented, the parties will attempt to negotiate an appropriate workaround.

Qwest maintains that the original request has been satisfied.

Sincerely,

Connie Winston Director, Information Technology Qwest

September 10, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the September 2003 CMP Meeting

Donna Osborne-Miller AT&T

CC: Lynn Notarianni Beth Foster Kit Thomte

SUBJECT: Qwest’s Change Request Response - PC062603-03

This response is a supplementary response to AT&T’s CR PC 062603-03. Originally, Qwest denied this CR at the August CMP meeting. In response to a series of questions and statements provide by AT&T, and as a result of an ad hoc call held on 09/09/03, Qwest is currently reviewing the points raised by the CLECs.

Qwest proposes moving this Change Request into Evaluation Status while we continue to investigate to provide workable solutions. Qwest would like to add this item as a topic for discussion for the meeting on September 19th. Qwest will then provide an updated response no later than the October CMP Meeting.

Sincerely,

Connie Winston Director, Information Technology Qwest

August 12, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the August 20, 2003 CMP Meeting

Donna Osborne-Miller AT&T

CC: Lynn Notarianni Beth Foster Kit Thomte

SUBJECT: Qwest’s Change Request Response - PC062603-03

CR Description: AT&T’s original change request states:

AT&T requests that the Business Rules be opened up for clarification and that event notification updates be incorporated into the Addendum process. We seek Qwest adoption of SBC's process of a standard conference be established to address issues or concerns with the event notification and addendum updates. This SBC process includes conference call logistics: date, time and bridge number. They also send out a notification capturing the questions and answers provided during the conference call.

Qwest Response: AT&T requests that Qwest adopt a regular call to address notifications issues that pertain to documentation changes or addenda to the Disclosure Documentation, and provide SMEs to answer the questions on the calls. In many cases, Qwest has not identified specific, word-for-word documentation impacts with the publication of the initial notification. Nor is that information available with the publication of the closure in all cases (in some cases, we are able to insert the Disclosure Documentation change into the closure, but this is typically a “documentation only” change notification). This is due to the fact that all documentation changes are reviewed by our System Requirements team. This System Requirements review is thorough and time consuming and would not be able to be completed during the timelines required by the notifications process in the CMP Document, Section 12.7. It involves research into field impacts, review of every instance to the field, cross-document impacts, systems and code impacts, and more. It is conducted over a period of time far greater than those involved in the notifications process.

Qwest maintains that both a.) the initial notification cannot include the documentation impacts and b.) the clarification call would not be able to clarify the documentation changes, as there would be insufficient detail available at the time of the proposed call. Moreover, the Qwest resources who would be needed on the calls are those who would be working to remedy the issue. Having them on the calls removes them from working to effectively solve the problem, and would lengthen the time to resolve.

If AT&T is requesting that all, or individual CLEC QA logs be provided as a part of the addendum process, this is not a logistically feasible business practice, because publishing these logs would require edits to every QA log for confidentiality.

Qwest's existing process of providing notifications with workarounds, business impacts, and channels for escalation works effectively, and allows for targeted responses to customer concerns. Publishing the clarifications made to each individual CLEC to all other CLECs does not add a demonstrable business benefit to the process, to the CLECs, and would require Qwest to assume an additional two to three resources to implement the solution AT&T is proposing. Qwest will, however, endeavor to enhance its notifications pertaining to Disclosure Documentation by including the change in the body of the closure notification. For Disclosure Documentation changes that would constitute an addendum, Qwest will include the documentation change in a “Change From—Change To” format similar to the change summaries in the addenda themselves.

Qwest respectfully denies this change request because the change does not result in a reasonably demonstrable business benefit and is economically not feasible.

Sincerely,

Connie Winston, Director, Information Technology Qwest


Open Product/Process CR PC062603-1 Detail

 
Title: Industry Compliance Request LX N 02QB9.00H Loop
CR Number Current Status
Date
Area Impacted Products Impacted

PC062603-1 Denied
8/20/2003
Preordering, Ordering Unbundled Loop, UNE, Loop,
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Buckmaster, Cindy
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

AT&T requests that Qwest retain and enhance the LX-N 02QB9.00H unbundled loop facility.

Other CLECs have no plans to discontinue this facility. In fact many are making enhancements with parameters, making this a viable facility for AT&T needs.

AT&T request that this facility be metallic only, unloaded and have a maximum distance of 12,000 feet using 24 gauge copper, or 9,000 feet using 26 gauge equivalent copper. In addition, it is requested that this facility have a maximum total bridge tap of no more than 2,500 feet, with no single bridge tap being longer than 2,000 feet.

Expected Deliverable:

Qwest to retain and enhance this facility


Status History

06/26/03 - CR Received

07/02/03 - CR Acknowledged

07/02/03 - Contacted customer to advised CR received

07/11/03 - Held Clarification Meeting

07/15/03 - Updated CR in CMP database with changes received from AT&T

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

08/20/03 August CMP Meeting Bob Mohr with Qwest reviewed the draft response for this CR. When evaluating this CR, Qwest determined that aggregation of inventory and assignment systems would require a system enhancement and the manual process would be too costly. The LX-N can continue to be ordered. This CR will be moved to Denied status.

07/16/03 July CMP Meeting Donna Osborne-Miller with AT&T presented this CR. AT&T would like Qwest to maintain the NCI code for this facility. Kate Pedersen with AT&T said that in a conversation with Bill Wycoff with Qwest he had stated the facility offering would be eliminated. Cindy Buckmaster with Qwest said that her understanding was that in the migration to Industry Spectrum Management Standards, those services would not be eliminated but would be merged into a specific spectrum class. Kate indicated that analysis matched her understanding.

CLEC Change Request Clarification Meeting

10:00 a.m. (MDT) / Friday, July 11, 2003

1-877-562-8687 3393947# PC062603-1 Industry Compliance Request LX-N 02QB9.00H Loop

Name/Company: Donna Osborne-Miller, AT&T Sharon Van Meter, AT&T Kate Pedersen, AT&T Lydia Braze, AT&T Phil Law, AT&T Jen Arnold, U S Link Cindy Buckmaster, Qwest Denny Graham, Qwest Bill Wycoff, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change AT&T’s CR requests that Qwest not eliminate the LX-N 02QB9.00H loop. Many other ILECs offer this loop as an option and this option works well for AT&T. AT&T had heard that Qwest may be eliminating the option and would like to have the option continued.

Cindy Buckmaster with Qwest said that the designation of the HDSL facility (provided by the NCI code) defines the capability of a non-loaded loop, and further clarified that an HDSL capable loop is not a product offering. This is important to understand in determining if AT&T would like a new product announced or the maintenance going forward of the availability of the specified HDSL facility. AT&T said that they are fine with the continuation of the availability of the facility offering with the changes that would contain the following loop limiting parameters; 12,000 ft. maximum loop length for 24 gauge cable that includes Bridged Tap (BT), 9,000 ft. maximum length for 26 gauge cable that also includes BT. BT would be limited to 2,000 ft. maximum length for an individual BT, and a total bridge tap limit of 2,500 ft.

Cindy Buckmaster further explained that the NCI code identifies the facility and the NC is the classification of the product. The designation of LX-N tells Qwest that the customer wants a non-loaded loop. Prior to widespread availability of HDSL, Qwest selected the facility for the CLEC, and now, the CLEC has the ability to choose the facility by specifying the 02QB9.00H NCI code. Neither of these parameters limits the loop length or amount of bridged tap.

Phil Law with AT&T asked Bill Wycoff with Qwest if the .00H designator means that Qwest applies spectrum for HDSL so they know how to manage. Bill Wycoff said the LX-N triggers the facility and the .00H is the electrical interface. The interface code is informational to Qwest for possible spectrum management purposes and does not affect loop design or performance.

Bill Wycoff with Qwest asked Phil if AT&T orders a facility to a premises and there are no loops that meet the limitations set by AT&T above, if they want to receive a reject. Phil answered yes, AT&T would prefer a reject rather than get a loop with 5,000 feet of bridged tap.

Confirm Areas & Products Impacted The area of this Change Request impacts Unbundled loop, and UNE

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation AT&T’s expectation is that Qwest keep and enhance the LX-N 02QB9.00H facility.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) AT&T will present this CR at the July CMP meeting.


CenturyLink Response

August 13, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the August 20, 2003 CMP Meeting

Donna Osborne-Miller AT&T

SUBJECT: Qwest’s Change Request Response - PC062603-1 "Industry Compliance Request LX-N 02QB9.00H Loop"

This CR requests that Qwest retain and enhance the LX-N 02QB9.00H unbundled loop facility.

In the interpretation of NC/NCI (Network Channel/Network Channel Interface) codes as provided by AT&T (LX-N 02QB9.00H), CLECs must refer to the UBL Technical Publication 77384. As indicated in Section 3 of this publication, the primary point of reference is the NC Code, which tells Qwest what facility type the CLEC is requesting. In the case of an NC Code equal to LX-N, the CLEC is requesting a metallic facility free of Load Coils. Where that facility is available in the Qwest inventory, or where incremental facility work can be accomplished to create such a facility, the non-loaded loop will be provisioned for the CLEC.

The secondary point of reference is the NCI Code, which provides operational information ONLY regarding the number of conductors the CLEC will be connecting at the interface (ICDF). Contrary to the proposal of AT&T, Qwest does not assign the facility for the NCI Code specified based on Loop Length or Bridged Tap. Rather, the loss parameter, of the facility requested, is measured at the interface and can be influenced by a number of elements, including Loop length and Bridged Tap length. Qwest processes are in place to ensure that the loss limits of the facility requested are in compliance with the specifications of the Technical Publication.

The Protocol Option part of the NCI, i.e., 00H, is informative to Qwest of the CLEC applied, electrical signal. This is used for spectrum management information.

None of these elements provide the limitations defined by AT&T (loop length, segment gauge, bridged tap limits). Therefore, these NC/NCI codes alone will not provide AT&T the specific facility they desire.

Qwest reviewed current assignment and inventory systems to determine if the necessary information can be gleaned and aggregated to accommodate this request. As Qwest systems currently consider only segment information and can’t aggregate the segments, this is not a viable option. Qwest would require System modifications that are expected to cost in excess of $1M to accommodate this request. Once the capability was installed, the system would logically need to be enhanced to accommodate specifications of each CLEC as their equipment may have facility needs different than the HDSL equipment in focus.

Qwest reviewed the manual process required to fill in where the system modification would be too costly. This manual process is likely to include expenses associated with: - Development of a means to identify a CLECs technical specifications - Additional assignment personnel to research potential facilities matching restrictions identified by the CLEC - Engineering time to review unqualified loops and create jobs to qualify the loops - Construction jobs may be required involving more construction personnel. - Additional network involvement to condition the loop (remove Load Coils and Bridged Taps) where applicable - A process to identify the required work on the customer’s records (perhaps on the CLECs bill)

A conservative estimate of the annual cost of providing this loop would be in excess of $250,000. Again, the identification of unique technical specifications, due to CLEC specific equipment and services requested, would only exaggerate this cost as well.

It is recommended instead that CLECs can use the Raw Loop Data Tool to provide the visibility to the likelihood that facilities are available to meet their request.

Although the CLEC can continue to order the LX-N Unbundled Loop, the technical specifications indicated by the CLEC, (maximum distance of 12,000 feet using 24 gauge copper or 9,000 feet using 26 gauge copper and a maximum total bridged tap of no more than 2,500 feet, with no single bridged tap being longer than 2,000 feet), cannot be guaranteed by Qwest. Therefore, Qwest respectfully denies the request because it is economically not feasible due to the cost to implement the request as identified above.

Sincerely,

Cindy Buckmaster Manager Product Management


Open Product/Process CR PC061803-1 Detail

 
Title: UNE P to UNE L Bulk Conversion
CR Number Current Status
Date
Area Impacted Products Impacted

PC061803-1 Denied
6/18/2003
Provisioning, Ordering, Billing Unbundled Loop, UNE P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Urevig, Russell
Director:
CR PM: Harlan, Cindy

Description Of Change

This CR was opened to track the denial items from the original CR PC022703-6 UNE P to UNE L Bulk Conversion. See PC022703-6 for more details.


Status History

6/18/03: Opened CR to track denial per discussion from the June CMP meeting

7/8/03: Input response in database

7/16/03: July CMP Meeting minutes posted to the database


Project Meetings

June P/P CMP Meeting - It was agreed to open a new CR for the items that Qwest will deny on PC022703-6. See PC022703-6 for more information.

July P/P CMP Meeting: Russ Urevig – Qwest reviewed the response to this CR. This CR was opened to track the denial items from PC022703-2. Qwest is unable to support items 3, 4, 9, 11, and 12. ATT advised they do not have any further questions. This CR will move to Denied status.


CenturyLink Response

July 9, 2003

For Review by CLEC Community and Discussion at the July 16, 2003 CMP Product Process Meeting

AT&T Ervin Rea Manager

SUBJECT: Qwest’s Change Request Response - CR PC061803-1 (PC022703-6) UNE-P to UNE-L Bulk Conversion

Qwest’s response to this CR was presented to the CLEC Community at the June 18, 2003 Product Process CMP Meeting. This CR requested 18 different functions in the Bulk Conversion process. Qwest’s response was to accept the CR and most of the functions identified, but not all 18 items.

After Qwest presented the response at the June CMP meeting, AT&T advised they do not wish to pursue the functions that Qwest will not support. Qwest recommended splitting the CR and putting the denial items on a separate CR.

Qwest opened CR PC061803-1 to track the denial. Qwest is unable to support items 3, 4, 9, 11 and 12 due to economically not feasible reasons.

Items 3, 11 and 12 pertain to processing requests via a spreadsheet. This would be a manual process for Qwest as we have mechanized systems in place that require each LSR to be entered individually. This type of request currently flows through without manual handling. Items 4 and 9 pertain to having a dedicated team assigned to work Bulk Conversions. Qwest will use our current employees as required to maintain our dialy work schedules, all employees have been trained on UNE-P and pots conversions to Unbundled loop. Qwest feels that creating a dedicated force for these conversions may impact our overall installation preformance. At the June Product Process CMP Meeting Qwest advised item 18 would be a systems change and a system CR should be opened by AT&T. Carla Pardee - AT&T advised she will open a systems CR if they wish to pursue.

Qwest will implement the other changes requested on this CR. Those items include 1, 2, 5, 6, 7, 8, 10, 13, 14, 15, 16 and 17. Please see PC022703-6 for status and response information.

Sincerely,

Russell Urevig Sr Process Analyst Wholesale Service Delivery


Open Product/Process CR PC071103-1 Detail

 
Title: Histogram of cleared troubles UNE P New Circuit Failure
CR Number Current Status
Date
Area Impacted Products Impacted

PC071103-1 Withdrawn
8/20/2003
Provisioning, Maintenance & Repair UNE-P, UNE
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: Suellentrop, Craig
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Request a report be developed that will provide the number of trouble tickets, for service established during the previous 30 days, closed by trouble cleared code.

Expected Deliverable:

Monthly report of trouble codes by frequency


Status History

07/11/03 - CR Submitted

07/14/03 - CR Acknowledged

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/14/03 - Received voice mail from Donna Osborne-Miller will be withdrawing this CR at August CMP

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

08/20/03 August CMP Meeting Donna Osborne-Miller with AT&T said she would like to withdraw this CR. This CR will be moved to withdrawn status.

CLEC Change Request Clarification Meeting

1:00 p.m. (MDT) / Tuesday, July 22, 2003

1-877-572-8687 3393947# PC071103-1 Histogram of cleared troubles UNE-P New Circuit Failure

Name/Company: Sharon Van Meter, AT&T John Blaszczyk, AT&T Jeanne Whisenant, Qwest Kit Thomte, Qwest Dan Busetti, Qwest Danelle Haynes, Qwest Kathy McBride, Qwest Doug Slominski, Qwest Craig Suellentrop, Qwest Michelle Thacker, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Linda read the title and description of the change request. In summary AT&T’s CR requests that Qwest provide a report that will provide the number of trouble tickets for service established during the previous 30 days, closed by trouble cleared code.

John Blaszczyk with AT&T said that he wasn’t sure that a CR is needed and explained that AT&T and the Qwest Service Management Team had a Service Improvement meeting two weeks ago. AT&T would like to see new circuit failure improvement. Qwest new circuit failure is 4-6% compared to 1-2% for other ILECs. John said that AT&T would like to understand the root cause of the failure and looking at data in a histogram is the beginning of analyzing the data. AT&T would like to understand if the failures are associated with something AT&T is doing in the ordering and provisioning process, or translations. Kathy McBride with Qwest asked if the definition of new circuit failure is the same for other ILECs. John answered yes the definition is the same.

John also said that AT&T receives analysis from Qwest on Access products and the purpose of this request for UNE-P is to derive initiatives to lower circuit failure and get numbers down to a reasonable level. Danelle Haynes with Qwest said the service management team was providing an analysis of 35 UNE-P failures per month and understood that Ervin submitted the CR because the report would be required monthly going forward. John said the report would not be needed going forward, but may take data for 3-5 months. Doug Slominski with Qwest said that Ervin wanted all closed codes for every new circuit failure by trouble codes and the underlying data is located in the OP5 PID. Doug has provided this type of report for one month to AT&T utilizing underlying PID data and information in CEMR by trouble ticket. This effort took approximately 2 days. John said that it would be less time consuming to have a mechanized report on a monthly basis to monitor what is causing failures.

Kit, Linda, John and Sharon discussed whether AT&T needed to submit a CR for this request, if AT&T would withdraw the CR, or if AT&T would provide revisions to the CR. Linda will provide Sharon a copy of the submitted CR for updates.

Confirm Areas & Products Impacted Area impacted is repair.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation AT&T’s would like information on new circuit failures trouble cleared codes .

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) AT&T will present this CR at the August CMP meeting.

-- 07/16/03 July CMP Meeting Donna Osborne-Miller with AT&T reviewed the walk on CR PC071103-1. There will be a clarification call on this change request.


Open Product/Process CR PC092203-1 Detail

 
Title: UNE P migration testing
CR Number Current Status
Date
Area Impacted Products Impacted

PC092203-1 Denied
12/17/2003
Testing UNE-P
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: Suellentrop, Craig
Director:
CR PM: Harlan, Cindy

Description Of Change

It is requested that Qwest perform testing of UNE-P loops at 48 hours prior to migration to a CLEC. Any degradation of service noted will Jep the order and Qwest will perform work necessary to bring service to optimal level.


Status History

09/22/03 - CR Submitted

09/23/03 - CR Acknowledged

9/26/03 - Contacted ATT to schedule Clarification call

10/2/03 - Clarification call scheduled for 10-2 10:00 - 11:00 am

10/2/03 - Conference call problems-needed to reschedule for October 6

10/6/03 - Held Clarification Call - changed product impacted to UNE-P and area to Testing as a result of the clarification call

10/10/03- Posted clarification notes

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/10/03 - Emailed response to CLEC

12/17/03 - Dec CMP notes will be posted to the database

1/5/04 - There is a MCI systems CR that is requesting similar changes. This CR was denied at the December meeting.


Project Meetings

December 17, 2003 CMP Meeting Jamal Boudhaouia – Qwest read the CR request and reviewed Qwest’s response. Jamal advised this CR is being denied for economically not feasible reasons. Ervin Rea – ATT advised he understands Qwest’s issues but he had hoped that Qwest would identify a way to automate this function. For example, when the order is completed, a MLT test should automatically run, and if an issue is found then a repair ticket would be created and fixed. After the line is repaired the order would complete. Ervin advised he would like to have a system CR issued. Liz Balvin – MCI said she has a systems CR opened for a similar change and would be okay with having her CR updated to reflect Ervin’s request. Discussion also took place about whether or not the CR should be crossed over to systems. Ervin advised the goal is to deliver a working line to end users. Liz advised test results could be delivered via CEMR and IMA could kick off the test when the order completes. Kit advised we will determine the correct way to handle this request.

November 19, 2003 CMP meeting Craig Suellentrop – Qwest reviewed the response. Craig advised Qwest will be placing this CR in Evaluation as there are similar CRs in progress and Qwest wants to review these CRs together. Liz Balvin – MCI said MCIs CR is a systems CR requesting MLT and results to be published via CEMR or IMA. Ervin Rea-ATT made additional comments regarding this CR and the similarity to MCI’s CR. Ervin advised he is okay if we perform the test after migration and before the Service Order Completion (SOC) notice is distributed. Ervin would like to see test results if possible also. The test results could be made available either on the SOC, in CEMR or IMA. The CLECs advised they would like the process change implemented first, and if the process change creates positive results, the system change could then be implemented. The CLECs suggested we look at this CR in phases if we need to. Qwest agreed to schedule another CLEC review to discuss the similarities of the CRs. Bonnie Johnson – Eschelon verified that she requested for Qwest to look at all UNE P products.

October 15, 2003 CMP meeting Ervin Rae – ATT presented the CR. Ervin recapped that this request is for Qwest to perform a test on the line prior to migrating the customer to the CLEC. This is for UNE-P. ATT has a circuit failure of 4-5% on LSRs submitted to Qwest, which is 2 times more than other LECs. Other LECs have implemented migration testing and the failure rate has decreased 4% (down to 1%). Bonnie Johnson – Eschelon asked if we can add additional products to this CR. Cindy Macy – Qwest advised it would increase the scope of the CR as additional representatives would need to be involved. We may need to have another clarification meeting. Bonnie advised she would like to include Resale POTS/Centrex 21 and Centrex Plus, and UNE P POTS/Centrex 21 and Centrex Plus. Liz Balvin – MCI advised MCI has asked for DSL test results. Liz asked is this what ATT is asking for? Ervin advised no, they are just requesting a test be perfomed prior to migration. Ervin advise Qwest can determine what type of test but he would like to make sure dial tone is on the line and noise is not on the line. This is a preventative measure test. Bonnie advised this testing is currently done on UBL, and asked why it wouldn’t be done on other products? Cindy agreed to discuss the additional products with the internal team to identify impacts to the scope of this CR. This CR will move to Presented Status.

Clarification Call October 6

Bob Mohr Qwest Russ Urevig Qwest Terri Kilker Qwest Monica Manning Qwest Joy McConnell Couch Qwest Craig Suellentrop Qwest Deni Toye Qwest Ervin Rea ATT

Ervin reviewed the CR and explained the new circuit failure rate is 2 times higher than any other ILEC. Bell South had the same problem and they impemented a process to test their line before they migrated it over to the CLEC. Ervin said this would be done on a migration from POTS to UNE P. Ervin said we should determine the type of test, but basically the request would be to run a MLT test to make sure equipment is okay, the line is not noisy and that the line has dial tone.

Terri Kilker Qwest asked if this is on any type of migration - such as conversion as specified or conversion as is or moves. This would normally be on non design and a C order, possibly a T order. Ervin agreed this would be on UNE-P migrations. Ervin advised this should improve our maintenance and repair as repair tickets would go down.

The team discussed on UNE P we usually do the same day turn up, so the timing of the test could not be 48 hours in advance in most cases. Ervin advised he doesn't care when the test is done, just as long as the line it tested before Qwest does the migration to the CLEC.

Cindy Macy-Qwest advised that ATT will present the CR at the October CMP meeting.


CenturyLink Response

December 9, 2003

For Review by the CLEC community and discussion at the December 17, 2003 CMP Meeting

Ervin Rae AT&T

SUBJECT: Qwest’s Change Request Response - CR PC092203-1 "UNE-P Migration Testing"

This CR requests that Qwest perform testing of UNE-P loops prior to migration to a CLEC. It also requests that any degradation of service noted cause a JEP in the order and for Qwest to repair the line. Other CLECs requested that other non-designed products be included in this CR. This would include Resale POTS, Centrex 21 and Centrex Plus, and UNE-P POTS, Centrex 21 and Centrex Plus. The test that Qwest would perform would be an MLT test.

Currently, the large majority of UNE-P orders are conversions, most of which flow through our systems today. There is not a center for non-designed services that performs testing on non-dispatched orders. Qwest receives about 20,000 UNE-P orders per week for conversions. All of these orders would need to be dropped out and manually handled to run an MLT test. Performing these MLT tests is estimated to require over 1600 hours of work per week for UNE-P orders alone. Therefore, Qwest is denying this request because it is economically infeasible.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Terri Kilker, Senior Process Analyst, Qwest

November 11, 2003

For Review by the CLEC community and discussion at the November 19, 2003 CMP Meeting

Ervin Rae AT&T

SUBJECT: Qwest’s Change Request Response - CR PC092203-1 “UNE-P Migration Testing”

This CR requests that Qwest perform testing of UNE-P loops prior to migration to a CLEC. It also requests that any degradation of service noted cause a JEP in the order and for Qwest to repair the line. Other CLECs requested that other non-designed products be included in this CR. This would include Resale POTS, Centrex 21 and Centrex Plus, and UNE-P POTS, Centrex 21 and Centrex Plus. The test that Qwest would perform would most likely be an MLT test.

Currently, the large majority of UNE-P orders are conversions, which flow through. There is not a center for non-designed services that performs testing on orders. This is a major change to process and Qwest requests additional time to fully evaluate the impacts. In addition, MCI change request SCR102803-1: Qwest to perform MLT testing and provide CLEC results for DSL provisioned services appears to be asking for a very similar outcome. Qwest proposes that these two CR’s be evaluated to determine if they can be combined.

Sincerely, Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Terri Kilker, Senior Process Analyst, Qwest


Open Product/Process CR PC092903-1 Detail

 
Title: Joint Inventory Process (previous name: New Collocation Process)
CR Number Current Status
Date
Area Impacted Products Impacted

PC092903-1 Completed
6/16/2004
Collocation
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Nelson, Steve
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T requests that Qwest, with the input of AT&T and other CLECs, develop a process where Qwest dispatches a person to verify information related to a Collocation site. For example, if AT&T needs information related to the APOT/CFA or power terminations or any other element associated with the Collocation site, Qwest will dispatch an employee to the specific Collocation site and verify existing information or provide additional information back to AT&T. The new process should include the application, intervals, RFS (ready for service date) and any other components relevant to the new process.

Expected Deliverable

Qwest and CLECs develop a process to verify existing information or provide additional information associated with a specific Collocation site. This new process should be available by the end of 2003.


Status History

09/29/03 - CR Submitted

10/01/03 - CR Acknowledged

10/3/03 - Contacted customer to schedule clarification call

10/9/03 - Held Clarification call

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/1/03 - Scheduled CLEC input meeting on 12-9 to review process

12/9/03 - Reviewed the process with CLEC community

12/16/03 - Posted meeting notes

12/17/03 - Dec CMP Meeting notes will be posted to the database

12/19/03 - Held ad hoc meeting

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/4/04 - Held Ad Hoc Meeting to review process udpates

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/17/04 - March CMP meeting notes will be posted to the project meeting section

3/23/04 - Notification PROD.03.23.04.F.01498.COLLOGENERALV21

4/21/04 - April CMP meeting notes will be posted to the project meeting section

4/30/04 - PROC.04.20.04.F.01581.FNL_ColloGeneralV21

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section


Project Meetings

June 16, 2004 CMP Meeting notes: Steve Nelson – Qwest advised this process was effective May 7. Qwest developed and tested the process with 5 CLECs in 10 locations. The Amendment and PCAT posted May 7. Qwest would like to close this CR. Carla Pardee – ATT advised it is okay to close the CR. This CR will move to Completed Status.

May 19, 2004 CMP Meeting notes: Cindy Macy – Qwest reported status for Steve Nelson. This CR was effective May 7. This CR will move to CLEC Test Status.

April 21, 2004 CMP Meeting notes: Cindy Macy – Qwest provided the status for Steve Nelson. The documentation for this process was distributed March 23. The process should be effective May 7. Qwest has been conducting trials with some of the CLECs to test out this process. Bonnie Johnson – Eschelon wanted to mention a potential gap in the testing process. Eschelon has a point of contact designated and Qwest was working with some one other than the point of contact. Qwest was working with their normal switching contacts at Eschelon, but we prefer for them to work with the dedicated person assigned to the test. Cindy advised that she would provide this feedback. This CR will remain in Development Status.

March 17, 2004 CMP Meeting notes: Steve Nelson – Qwest reported that this CR is in progress and we are working on a Beta trail. We are performing Joint Inventory tests with ATT, TCG, MCI, Eschelon, 180 Communications and Sprint. We have completed the Inventory with 180 Communications in Montana. The CR is in development and moving along quite nicely. This CR will remain in Development Status.

February 18, 2004 CMP Meeting Cindy Macy – Qwest provided status for Steve Nelson. Cindy advised that the team met with the CLECs on February 4, 2004. The process and forms were reviewed. Qwest advised a Joint Inventory process trial would be held with some of the CLECs. Qwest will use the trial to work out any gaps in the process. This CR will remain in Development Status.

Joint Inventory Process February 4, 2004 - 1:00 – 2:30 p.m. MST

In attendance: Steve Nelson – Qwest Steve Kast – Qwest Bill Fellman – Qwest Rene Lerma – Eschelon Mary Ann Wiborg – Qwest Cindy Macy – Qwest Lillian Robertson – Qwest Teresa McKenzie – Qwest John Waltrip – Qwest Kathy Battles – Qwest Cheryl McCombe – ATT Peggy Englert – Qwest

Cindy Macy – Qwest opened the call and reviewed the agenda. Steve Nelson – Qwest reviewed the four documents at a high level and asked if there were any questions or concerns with the forms or process. Eschelon and ATT advised they are okay with the forms and process.

Steve Nelson – Qwest explained we would like to start the trial and perform a joint inventory on 2 sites per CLEC. Qwest would like to do this on a mix of locations and a mix of types of collocation sites (virtual, cageless, caged, etc). The trial will be done at no cost, as it will help Qwest with our cost pricing study. Our draft cost estimate is approximately 19.25 hours at $1500.00.

Steve reviewed each section of the Joint Inventory form; service level, virtual equipment, grounding, synchronization, power, administrative lines, space, and notes. Rene – Eschelon asked if we included CLEC to CLEC direct collocation sites? Qwest advised no, we don’t keep records of CLEC to CLEC facilities.

Steve reviewed the process flow diagram. This process is a 60-day process. Qwest has tried to be responsive to the CLECs needs. The CLECs advised they are okay with the flow and intervals and the process looks good. Steve Nelson advised that we would update the process if needed after the trial.

Steve reviewed the PCAT. Steve advised an amendment would be required. Steve reminded the team that there is not any time to repair or test during the inventory. Steve reviewed the description, terms, ordering , and procedures. Steve advised that if the CLECs have more than one site per location and they want them both inventoried, it would be best to schedule them together, however each site would require a separate application.

Steve advised that Qwest will be using Telric based pricing, instead of market based pricing. This allows Qwest to bill a set amount and get the process completed faster and at the lowest cost to the CLEC customer.

Bill Fellman – Qwest asked Steve to clarify what the ‘maximum of two scheduled visits’ means. The team advised this is regarding the reschedule / cancellation / charge policy if the CLEC has to reschedules a joint inventory two times. The CLECs on the call stated this seemed fair.

Steve Nelson – Qwest advised if there are discrepancies between billing and actual equipment located at the site, the billing will be corrected.

Steve Nelson and Peggy Englert – Qwest discussed the trial. Peggy’s team will contact the four CLECs that expressed and interest (180, ATT, Sprint, Eschelon) to obtain a proposed and prioritized list of sites to inventory. Qwest would like a mix of locations and types of sites to inventory.

Next Steps: Collocation Service Managers will contact and work with CLECs to obtain a proposed and prioritized list of sites to inventory CLECs will have a target date of February 13 to submit an application form to Qwest (this would start the process) Steve Nelson will prepare Amendment by February 20 Steve Nelson will start the documentation process by February 20 Qwest will work with the CLECs during the trial The team will get back together after the trial to discuss results Final pricing studies will be prepared.

January 21, 2004 CMP Meeting Steve Nelson – Qwest advised they have developed the preliminary price structure. Qwest will do a trial with four CLECs and two Collocation sites each to help determine the correct pricing. The Amendment is in progress and it will be posted to the web site soon. The Application form, Inventory form, processes, and Product description will be available for the meeting that is scheduled next week on January 30. This CR will remain in Development Status.

December 19, 2003 Ad Hoc Meeting PC092903-1 Joint Inventory Process

In Attendance: Bob Alex – Qwest John Waltrip – Qwest Steve Nelson – Qwest Stacy Meisenhiemer – Sprint Bonnie Johnson – Eschelon Lillian Robertson – Qwest Kathy Battles – Qwest Rene Lerma – Eschelon Cindy Macy – Qwest Peggy Englert – Qwest Mary Simon – 180 Communications

Cindy Macy – Qwest opened the call and reviewed the agenda for the meeting. We will be reviewing the Application form, the Inventory form, and the high level flow and critical intervals.

Steve Nelson – Qwest began by reviewing the draft intervals: Day 2 Quote Day 20 Identify Inventory participants Day 35 Perform Joint Inventory Day 55 Distribute the results of the Joint Inventory Day 60 Hold follow up call to review the results

Steve advised the pricing study is not completed as of yet. The preliminary cost is $1250.00. Steve would like to conduct Beta tests with CLECs to get a better judge of time and effort. Steve advised next steps are to finalize the forms and cost. The team will meet again the 3rd week in January.

John Waltrip – Qwest reviewed the Inventory and Application forms. John explained the engineer fills out the Inventory form and gives it to the SICM. Rene – Eschelon asked if Qwest could mirror what is on the APOT sheets. John advised Qwest will review the APOT form, if inventory differs than what is on the current APOT, we will then update the APOT. Kathy Battles – Qwest advised for ATT some jobs are old or they bought out another customer, so ATT may not have current APOT forms.

Rene – Eschelon asked if this process applies to a CLEC to CLEC connection. John advised no, as Qwest does not inventory that equipment.

Rene – Eschelon commented about the price and asked why managers will be gathering all the information. If managers are gathering the information the cost would be higher, and that is basically administrative work. Steve Nelson reviewed how the work is broken out between groups and explained that is how we have the work assigned. Steve would like to do a Beta trial for free with 3-4 of the CLECs, on 1-2 Collocation sites each. The trial will allow us to refine our time, cost and forms. Steve would like to do the trial in the January time frame. Steve advised he would work with Peggy Englert’s team to contact the CLECs to arrange the Beta trial. The CLECs participating in the calls advised they would be interested in the Beta test. That would include ATT, Eschelon, 180 and Sprint.

Cindy Macy – Qwest asked Steve to consider that the timing of the trial and the release of the documented process can occur at the same time. Steve advised they would target publishing the document so it can be reviewed in the February time frame.

December 17, 2003 CMP Meeting Steve Nelson – Qwest reported that the team held a meeting on December 9 to review the process. There was a lot of participation and good discussion took place. The team agreed to meet again on December 19 to review the Application form and Inventory form. Steve explained the process will include a joint inventory of collocation sites that look at everything that is at the site. Liz Balvin – MCI asked if we made any progress on the cost analysis? Steve reported that the cost estimate is available but the final cost study will take 3-4 weeks to complete. The team will meet again in January to discuss the cost study more. This CR will stay in Development status.

PC092903-1 Joint Inventory Process Ad Hoc Meeting December 9, 2003

In attendance: Eric Yohe – Qwest Peggy Englert – Qwest Carla Pardee – ATT Cindy Roni – Eschelon Rene Lerma – Eschelon Bonnie Johnson – Eschelon Liz Balvin – MCI Cheryl McCombs – ATT Michelle Brandt – ATT John Waltrip – Qwest John Lawrence – Qwest Bob Alex – Qwest Kim Isaacs – Eschelon Steve Nelson – Qwest Kathy Battles – Qwest Louis Ruiloba – ATG Paul Hansen - Eschelon

Cindy Macy – Qwest opened the call and advised the purpose of today’s meeting is to review the draft Joint Inventory Process and gather input from the CLECS and make sure we are on track with expectations.

Steve Nelson – Qwest reviewed in detail the Process Flow, which was distributed as part of the notification of the meeting. Steve advised the Application and Inventory form are under development and will be reviewed at our next meeting. Steve advised Qwest would offer a Joint Inventory application for virtual sites also.

Steve Nelson – Qwest asked if the CLECs would like to identify what inventory they think they have at each site, or if the CLECs would like Qwest to identify what is actually at the site. Rene Lerma – Eschelon advised Qwest should identify what inventory is at each site. The CLECs agreed.

Rene Lerma – Eschelon asked for timeframes and intervals to accomplish the different steps in the process. Steve Nelson – Qwest advised the draft timelines are expected to be as follows:

Application submitted by CLEC Up front work that Qwest needs to do to schedule the Joint Visit: 15–20 days after receipt of application Schedule and conduct the Joint Visit: 20-45 days Review results: 55-60 days Schedule and hold wrap up call: 7-10 days

Other actions based on results of visit: Billing changes Database changes Augment work (if needed)

Steve Nelson – Qwest discussed pricing. The plan is that pricing will not include a QPF. An amendment will be done. Steve will look at a Telric Pricing study to determine price and present this to the team. Qwest would like to charge one rate to have a Joint Inventory done. This simplifies the process and pricing and allows the CLECs to budget appropriately for the work. Billing would be done in BART.

Rene Lerma – Eschelon asked what would the results of the inventory look like, what would be sent to the CLECs? Steve Nelson – Qwest advised there is an Inventory Form that will be used. We will review this at the next meeting. It is a 3-page form, that would include items such as termination feeds, power feeds, fused locations, BDFB locations, frame id, block locations, DSC bay panel, etc.

Steve Nelson – Qwest advised that Qwest would not do testing at the same time of the Joint Inventory. No additional work would be done at the same time. This is to keep costs low for performing a Joint Inventory.

The team also discussed that Qwest could accept the application form to begin the inventory process without advance payment. The request would be irrevocable. Payment should be made by good faith. If the process is requested, then the payment will be made.

Liz Balvin – MCI asked if there would be time for additional questions. Cindy Macy – Qwest advised the team will meet again, and after the process is documented it will go out for review and comment.

Next Steps: Meet again on December 19, 2003 Review forms (application and inventory form)

November 19, 2003 CMP Meeting Steve Nelson – Qwest recapped the CR request from ATT. ATT would like Qwest to develop a process where Qwest dispatches a person to verify and inventory information related to a Collocation site. Steve reviewed Qwest’s response. Qwest accepts this CR and is working to develop the process to perform a comprehensive inventory of an existing Collocation site. SICMs will be involved with performing the comprehensive inventory. Steve is calling this process a ‘Joint Inventory Process’. As a result of this process billing corrections may be needed. Steve advised he will work with Cindy to schedule another CLEC review meeting. Topics of discussion at the meeting include high-level process flow, deliverables, costing model and ordering process. The CLECs agreed that Qwest could change the title of the CR to ‘Joint Inventory Visit’.

October 15, 2003 CMP Meeting Michelle Brandt – ATT reviewed the CR and explaind ATT is looking for a joint survey process where Qwest would dispatch a person to a Collocation site to help provide information about the Collocation site, such as power information. Steve Nelson – Qwest advised a good clarification call was held and the Qwest team will be meeting internally to work out the details. The status will be moved to Presented.

October 9, 2003 1-877-552-8688 7146042# PC092903-1 New Collocation Process

Attendees Steve Nelson – Qwest Lillian Robertson – Qwest Denise Martinez – Qwest Cheryl McCombs-ATT Rich Powers – ATT Peggy Englert – Qwest Janet Leonard – Qwest Ben Campbell – Qwest Bob Alex – Qwest Doug Andreen – Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees introduced 2.0 Review Requested (Description of) Change Rich Powers – ATT reviewed the Change Request. Rich explained ATT is looking for a mechanism to have a joint site survey done on particular Collocation sites. ATT needs to inventory some of their Collocation sites to determine type of space, size of space, and especially the power arrangement. ATT needs to update their inventory so they are ordering correctly, and to improve access planning. Rich explained there is a gap in their power inventory, at the assignment level. They are interested in the BDFB inventory, relay rack, fuse, etc. Cindy Macy – Qwest asked Rich if they need this on all Collocations or only certain sites and certain situations. Rich said they would like to be able to request this ‘as needed’. Steve Nelson – Qwest asked what level of detail is needed? Is this the circuit working level? Rich advised no, the total number of terminations is good. Lillian Robertson – Qwest asked Rich to clarify what was meant by ‘the new process should include the application intervals, RFS and any other components relevant to the new process’. Rich explained they would want to understand the intervals for ordering a site survey, for completing a site survey. Specifically, ATT is requesting A Joint Site Survey –1. The Terminations, 2 – Power Assignment of feeds needed and 3. How the Power is fused. Qwest asked what additional information is needed: Rich explained that for DS0 terminations, Qwest provides entire picture of CFA. If ATT orders power, Qwest only sends information about the power ordered, not the entire power inventory at the collocation. Cindy Macy-Qwest asked if the site survey would be requested before an order is placed? Rich advised normally yes, as they would like to have the records correct before an order is placed. Rich explained if he wanted to do a joint survey with Qwest, how would he go about ordering that? ATT would like Qwest to develop a process to perform a joint survey. Identify such things as intervals related to this request. Kathy Battles – Qwest advised that ATT bought several sites from another company that they do not have complete records on. The SICMs have done some survey of sites but additional help is needed. Ben Campbell – Qwest clarified that ATT is looking for power data first, and then other features are helpful, but the power components are critical. Rich advised power, then cross connects and then space information is needed. (In that order). Rich – ATT explained they are building a database to store this information; power inventory system. 3.0 Confirm Areas & Products Impacted Collocation Site Survey 4.0 Confirm Right Personnel Involved Team agreed the right personnel are involved. Ben Campbell / Steve Nelson would be the lead on this CR. 5.0 Identify/Confirm CLEC’s Expectation Process to request a Joint Sight Survey of Collocation Sites Intervals for this process 6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) ATT will present the CR at the October CMP Meeting Qwest will provide our Response at the November CMP Meeting


CenturyLink Response

November 11, 2003 For Review by the CLEC community and discussion at the November 19, 2003 CMP Meeting

Lydia Braze AT&T

SUBJECT: Qwest’s Change Request Response - CR PC092903-1

“New Collocation Process”

This CR requests “Qwest, with the input of AT&T and other CLECs, develop a process where Qwest dispatches a person to verify information related to a Collocation site. For example, if AT&T needs information related to the APOT/CFA or power terminations or any other element associated with the Collocation site, Qwest will dispatch an employee to the specific Collocation site and verify existing information or provide additional information back to AT&T. The new process should include the application intervals, RFS and any other components relevant to the new process.”

We have many collocation processes and procedures today which meet some of these needs. Qwest currently offers a comprehensive walk-through by a State Interconnect Manager (SICM) with the customer when the final 50% of the non recurring quote is paid. This procedure will still be offered. We provide APOT/CFA which includes a cumulative listing of all CLEC termination cables and entrance facilities. This will continue. Qwest offers a site visit associated with an Available Inventory request before order submission. Qwest offers up to three site visits after payment of the initial 50% on a collocation application. We plan to continue to provide these services. As per the CR, however, it was understood that AT&T wants a comprehensive process to ensure all aspects of the collocation site are accurate including terminations, power, space, type of collocation, APOT/CFA, and billing rate elements and quantities. This process relates to previously completed sites. Qwest accepts this CR and will work with the CLEC community to offer a new comprehensive process which can be submitted at the CLEC’s request. It will be priced out and offered as an amendment. The following is a high level overview of what services Qwest is prepared to offer to meet the CR request. A clarification call was held with AT&T on October 9, 2003. Subsequent to that call a cross-functional team was put together to start to frame what this added process would look like. The process being proposed looks like this in Qwest’s vision: · A separate application will be developed for these requests. · Every effort will be made to minimize the costs for this process. · Inventoried items will include space, power, and terminations. · A knowledgeable Qwest employee will be selected to conduct the joint visit such as a SICM or delegated employee. · Appointments will be jointly scheduled. · The timeframe from application to completion of the joint visit will be discussed and determined as part of the joint planning development of this CR. · Records and billing will be corrected upon completion of the joint visit. Any prior monthly recurring adjustments will be based on the CLEC’s ICA. · Detailed planning prior to the visit will include review of all engineering records. · CPMC will coordinate the overall end to end process. We will schedule calls to jointly develop this process as requested. Qwest will provide a format of the newly proposed process, intervals, deliverables, and pricing. The CLEC community will have the opportunity to partner with Qwest in the development and finalization of the process. An amendment will be prepared for CLEC to participate in this new process offering.

Sincerely, Stephen C. Nelson Product Management Qwest

Cc: Ben Campbell Bill Campbell


Open Product/Process CR PC101303-1 Detail

 
Title: Blocking Feature Request
CR Number Current Status
Date
Area Impacted Products Impacted

PC101303-1 Withdrawn
11/24/2003
Provisioning UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Paxton, Mallory
Director:
CR PM: Andreen, Doug

Description Of Change

AT&T is requesting a feature that would allow it to block customers from making long distance calls by using operator assistance. This feature would allow CLECs to protect itself against customers from continuing to make long distance calls when the customer is in arrears.

Expected Deliverable:

February 2004


Status History

10/13/03 - CR Submitted

10/14/03 - CR Acknowledged

10/20/03 - Held Clarification Meeting

10/27/03 Sent Clarification Meeting Minutes

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/24/03 - Status Changed to Withdrawn


Project Meetings

11/19/03 Nov. CMP Meeting Carla Pardee AT&T presented the CR requesting blocking customers from making long distance calls by using operator assistance. She had intended to withdraw the CR but wants to test some existing features a bit more before she does so. She said the remaining problem is that Long Distance Toll Restriction does not block 411 or 555-1212 calls. AT&T is still researching. Bonnie Johnson Eschelon added that she believes that Custom Net Blocking is the only way to block these calls and Eschelon is very interested in a block to block only DA calls. This CR will remain in Pending Withdrawal status.

- Clarification Meeting 3:30 (Mountain Time) / Tuesday October 20, 2003

1-877-521-8688 1456160# PC101303-1; Blocking Feature Request

Attendees Jo Ann Samonek, AT&T Carla Pardee, AT&T Anthony Washington, Qwest Mallory Paxton, Qwest Terri Kilker, Qwest Doug Andreen, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Doug read and reviewed the CR. The CR requests a feature that would allow AT&T to block customers from making long distance calls by using operator assistance. This feature would allow CLECs to protect itself against customers from continuing to make long distance calls when the customer is in arrears. Carla stated that in discussions with others at AT&T since she had submitted the CR she was given to believe there might be an existing product that would meet the needs of AT&T. AT&T felt that Billed Number Screening combined with CustomNet and Long Distance Restriction could be a solution. She confirmed that UNE-P is the only impacted product. Terri and Mallory explained that Billed Number Screening combined with Long Distance Restriction might provide the needed capabilities. Long Distance Restriction prevents calls being dialed that begin with a 0 or 1. Billed Number Screening covers 3rd number billed calls made from a different phone. The consensus was that CustomNet capabilities would not be needed. The PCAT now reflects which types of call apply to each service. AT&T will test Billed Number Screening and Long Distance Restriction as a possible solution in the next few days and let Doug know of the results. Doug will then advise the group on what further direction this CR will take, AT&T may withdraw the CR after testing or an additional clarification meeting may be scheduled.

Confirm Areas and Products Impacted UNE-P

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation AT&T would like this feature available by February 2004.

Identify any Dependant Systems Change Requests TBD pending AT&T testing

Establish Action Plan Carla Pardee with AT&T will get information on testing Billed Number Screening and Long Distance Restriction to Doug Andreen within the next few days. If testing is not successful an additional clarification meeting will be held. If testing is successful Carla may withdraw this CR at the November CMP meeting.


Open Product/Process CR PC103003-1CM Detail

 
Title: Language Changes to Qwest Wholesale Change Management Process Document re: Notification of Planned Outages
CR Number Current Status
Date
Area Impacted Products Impacted

PC103003-1CM Withdrawn
2/18/2004
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Maher, Jim
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T seeks to change the language of the last sentence in section 12.1 It states: Planned Outage Notification will be sent to CLECs and appropriate Qwest personnel no later than two (2) calendar days after the scheduling of the OSS Interface maintenance activity.

AT&T Proposed language: At the beginning of each month Qwest posts the forecast of the current month and two (2)months of system availability. The three (3) months system availability forecast notes planned changes to standard system availability. This forecast will be posted electronically in a calendar format.


Status History

10/30/03 - CR Submitted

11/03/03 - CR Acknowledged

11/4/03 - Contacted ATT to schedule clarification call - offered 3 times for call. ATT will call me back to advise.

11/6/03 - ATT called back and confirmed clarification meeting for 11/11 12-1:00

11/11/03 - Held clarification call

11/20/03 - Nov CMP meeting minutes will be posted to the database

12/5/03 - Contact ATT to schedule ad hoc meeting to discuss process and language

12/10/03 - Held ad hoc meeting with ATT to discuss CR in more detail and to ensure Qwest understands ATT issues

12/17/03 - Dec CMP notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/17/04 - Held ad hoc meeting with ATT

3/5/04: CMPR.03.05.04.F.01460.CalPostPlannedOutageFore


Project Meetings

February 18, 2004 CMP Meeting Jim Maher-Qwest advised we held several CLEC meetings to discuss this CR. In those meetings, Qwest had agreed to monitor the Planned Outage process during January and February. During this time the three Planned Outage notices had a 19-day advance time frame. Qwest has developed a forecast document ‘Potential Planned Outages’. This was modeled after the example that ATT provided from Verizon. The intent of this document is that Qwest would post the outage dates that they believe are potentially going to occur. The final communication would occur as defined in the current CMP Process. There was a language change requested by ATT, but ATT agreed that was not necessary. Qwest will meet a 15-day advance notification for most of the potential planned outages identified in the CMP document. There may be some emergency outages that will meet the minimum requirements identified in the CMP process. Additionally Qwest will update and post the Planned Outage Forecast calendar to the web site quarterly. Qwest requested for ATT to withdraw the CR. ATT advised they are happy with the document / calendar. Carla Pardee – ATT said she didn’t get a chance to share the final document with other CLECs due to schedule issues. ATT stated they would withdraw the CR and that they believed the other CLECs will be happy with the forecast calendar.

February 17, 2004 Ad hoc meeting PC103003-1CM Planned Outage Notification

In attendance: Pat Moran - ATT Jim Maher- Qwest Carla Pardee – ATT Cindy Macy – Qwest

Cindy Macy – Qwest advised that we wanted to meet again to see how the process is working, to review the draft ‘Potential Planned Outage’ document, and determine if we should withdraw the CR as there would not be a language change, if the Potential Planned Outage calendar is acceptable.

Pat Moran – ATT reviewed the calendar and clarified her expectations. Pat reviewed the March 19, 20 and 21 date scenario. Jim explained that the Friday March 19 outage is less likely to occur, than the Saturday March 20 and Sunday March 21 outage. Pat suggested that we identify this on the calendar.

Jim reviewed that the January notices all provided 19 days of advance notification. IT is working on being more proactive with this process. Pat thanked Qwest for their efforts.

Pat advised that she would like Qwest to provide notification on the items identified on this calendar 15 days in advance. Pat explained that Qwest should be able to do this, as we are already aware of the potential and we should know if the release would impact system availability within 15 days. Jim agreed that this should be possible for items identified on the ‘Potential Planned Outage calendar’. Jim advised that there would not be a change to the language in the CMP, and this was agreed to by ATT. Jim clarified that there could be situations when Planned Outages required a shorter notification interval, and that these would be the exception based on the work Qwest had done. Pat stated she understood those exceptions could take place, but wanted as much advance notification as possible.

The group discussed whether we could withdraw the CR at the February CMP meeting. Carla and Pat Moran – ATT discussed the proposed solution and agreed that if Qwest published this calendar and updates it quarterly, and we provide 15 days advance notification for outages identified on this calendar, than they would agree to withdraw the CR.

Carla and Pat – ATT asked when we would identify 2005 dates. Jim advised this would be a rolling calendar so by the end of the 3rd quarter 2004 we should have a start on 2005 dates.

The team agreed to discuss at the February CMP meeting and withdraw the CR.

January 21, 2004 CMP Meeting Carla Pardee- ATT advised the last Planned Outage Notifications were sent out with much more advance notice and ATT is glad about this. Carla would like to have another meeting scheduled so we can discuss this with her internal representatives that are impacted by this process. Jim Maher – Qwest advised we have had 3 planned outages in January and all three notifications provided 19 days advance notice. Cindy Macy – Qwest will schedule another review meeting to discuss the CR and determine next steps.

December 17, 2003 CMP Meeting Cindy Macy – Qwest reported that we held a CLEC meeting on December 10 to discuss the Planned Outage Notification process. Qwest has met internally and we are reviewing the reasons why Planned Outage Notifications are occurring. Planned Outage Notification are at times related to issues that are uncovered during system releases. Qwest is reviewing the possibility of whether we could provide a quarterly notification that identifies when we think possible Planned Outages would be needed. We could publish that notification and then if the Planned Outage is truly needed we could use the existing Planned Outage Notification process to notify again. Qwest and the CLECs in attendance agreed to meet again in January. This CR will move to Development Status.

November 19, 2003 CMP Meeting Carla Pardee – ATT presented this CR. Pat Moran – ATT recapped the issues ATT has experienced due to short notice of planned outages. Carla advised that ATT would like Qwest to forecast out 90 days and publish their planned outages. This will give ATT advance notice and time to respond to system availability. ATT is looking for a list of scheduled down time 90 days in advance, and 60 days advance notice if there is any changes to that schedule. In mid-October ATT was given 2 days notice on additional downtime.

Clarification Meeting November11, 2003 1-877-552-8688 7146042#

PC103003-1CM Notification of Planned Outage Attendees Par Moran – ATT Liz Balvin – MCI Kim Isaacs – Eschelon Kyle Kirves – Qwest Carla Pardee – ATT Jim Maher – Qwest Randy Owen – Qwest Bonnie Johnson – Eschelon Cindy Macy – Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Attendees introduced 2.0 Review Requested (Description of) Change Cindy Macy – Qwest explained this CR is a request to change the Change Management Process document. This CR will require a vote at a monthly CMP meeting. Carla Pardee – ATT reviewed the change request. Carla explained she will be representing all Product Proces CRs. Donna will represent all System CRs. Carla explained they need to have the notification time increased when ever Qwest does planned outage notfications. Carla advised other ILECs provide 30-90 days notice. Qwest provides 2 days notice and this is not enough time to respond and prepare out centers. This causes problems. Jim Maher – Qwest attempted to explain the difference between what Qwest calls Scheduled Maintenance/Scheduled Outages, the OSS Release Calendar, Event Notifications and Planned Outage Notifications. Scheduled Maintenance is what takes place during regular scheduled downtime (night time down time). System Availability time is published on the OSS Hours of Availability document. System Release information is available on the Release Calendar and Release Notification documents. Planned outages are used for correcting system behaviors that are not causing immediate impacts to CLECs but they do need to be corrected quickly. Event Notification are used to notify the CLECs of system issues that impact the CLECs. The CLECs advised they believe Qwest has to know about scheduled downtime more than 2 days in advance. Jim explained part of the confusion is terminology as our scheduled downtime is down in the hours the system is not available. We do not notify about scheduled downtime as that is identified in the OSS Hours of Availability document. Planned Notifications are used to extend regular system downtime. Qwest uses the Planned Notifications to fix system issues that need to be addresses and cannot be accommodated in the regular system downtime. Pat Moran – ATT explained they receive hourly notifications from other ILECs on scheduled downtime. Carla – ATT advised she gets pre-notifications from Qwest and filters them to her people. Carla and Pat can review these notification to see if Pat needs to get additional ones.

ATT advised 2 days is not enough time to react to an extended downtime schedule. More detail on the functions impacted would be helpful as that would save us time in determining the impacts. Carla – ATT advised she would send the schedule that Verizon publishes as they publish downtime several months in advance. Bonnie Johnson – Eschelon asked if Qwest should really be using Event Notifications for these outages. Jim Maher – Qwest explained that these are not CLEC impacting so they are not really Event Notifications. They are correcting system behavior issues that are not currently visible to the CLECs. Qwest agreed we would meet internally to discuss and review data. Qwest would schedule an additional CLEC ad hoc meeting after we do some preliminary investigation. ATT will present this CR at the November CMP meeting. 3.0 Confirm Areas & Products Impacted Planned System Outage Notifications 4.0 Confirm Right Personnel Involved Correct people involved 5.0 Identify/Confirm CLEC’s Expectation For Qwest to provide additional time on Planned Outage Notifcations 6.0 Identify any Dependent Systems Change Requests none 7.0 Establish Action Plan (Resolution Time Frame) ATT will present the CR at the November CMP Meeting Qwest will schedule another ad hoc meeting after we complete our investigation.


Open Product/Process CR PC110303-1 Detail

 
Title: UNE P Standard Interval Guide
CR Number Current Status
Date
Area Impacted Products Impacted

PC110303-1 Denied
1/21/2004
UNE-P
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: Washington, Anthony
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

The current standard interval guide (SIG) provides that an order for UNE-P POTS service that is a flow through order, without dispatch, will be delivered in =< 3 days, except for Colorado and Minnesota which will be =<2 days. The requested change is that this service should be delivered =<.5 days. This service is a migration of the customer and primarily a records change only. There is no installation required for these orders and they should not have the same SIG as new installation orders.

Expected Deliverable:

Service for UNE-P will be delivered on the same day as the order is received, if received prior to 3:00pm.


Status History

11/03/03 - CR Submitted

11/04/03 - CR Acknowledged

11/12/03 - Held Clarification Meeting

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

01/21/04 January CMP Meeting Anthony Washington with Qwest reviewed the Qwest response. Carla Pardee with AT&T said they appreciated the detail provided in the denial response. Bonnie Johnson said that even though changes were made in the SIG, there would not be much customer impact because non-dispatch orders were already being completed in the morning. Terri Kilker with Qwest (Begin comment from Bonnie Johnson - Eschelon) agreed and said that additional network resources were added to meet the changed timeframe for the non-dispatch orders. (Begin comment from Bonnie Johnson - Eschelon) Bonnie said she was happy to hear about the additional resources because orders dropping or erroring out of the Qwest switch, the orders not being addressed by network and leaving the customer out of service has always been problematic. (end comment). Joyce Perry with AT&T asked about the cut off time for orders to be sent. Carla Pardee said that this information is in the SIG. This CR will be moved to Denied status.

Wed 1/14/04 10:18 AM From: Rea, Ervin E, NKLAM [eerea@att.com] To: Sanchez Steinke, Linda Subject: RE: Qwest Revised Draft Response PC110303-1 Linda

Can the final letter be more specific on the below statement?

"Contrary to their assumption, Qwest finds that even though a billing name change is part of the migration, a complex set of systems and resources must interact to ensure orders are completed properly. If an interval of 12 hours or less were attempted, significant system and headcount impacts would put an undue economic burden on Qwest."

Perhaps a list of systems, resources and activities would be helpful.

Ervin Rea Voice mail: 303.298.6306 VO: 303.657.2937 PCS: 720.530.7381 Text messages: 7205307381@mobile.att.net

Tue 1/20/04 4:34 PM From: Sanchez Steinke, Linda To: Rea, Ervin E, NKLAM [eerea@att.com] Subject: RE: Qwest Revised Draft Response PC110303-1 Ervin -

In speaking with Anthony Washington the systems impacted are those identified in the Qwest response.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

12/17/03 December CMP Meeting Linda Sanchez-Steinke with Qwest read the Qwest response and asked that the CR be moved to Evaluation status and Qwest will provide an update at the January meeting. This CR will be moved to Evaluation status.

11/19/03 November CMP Meeting Ervin Rea with AT&T presented this CR and said that currently the SIG relates that UNE-P conversions interval is less than or equal to 3 days and in Colorado and Minnesota is less than or equal to 2 days. Since the UNE-P conversion is a records change and doesn’t require a technician visit it should be accomplished in a .5 day interval. Bonnie Johnson with Eschelon asked if this interval change would apply to conversions with switch changes. Ervin said the CR applies when no technician is dispatched to the customer site. Liz Balvin with MCI said they would like to include "migrate as is" and "migrate as specified". Anthony Washington with Qwest asked if this would include technicians in the central office being dispatched. Ervin said that the central office technicians are not being dispatched to the customer site and the .5 day due would apply on these orders. This CR will be moved to presented status.

CLEC Change Request Clarification Meeting

11:00 a.m. (MDT) / November 12, 2003

1-877-572-8687 3393947# PC110303-1 UNE P SIG

Name/Company: Ervin Rea ATT Ann Adkinson ATT Kim Isaacs Eschelon Carla Pardee ATT Anthony Washington Qwest Craig Suellentrop Qwest Danielle Haynes Qwest Cindy Macy Qwest Liz Balvin MCI Lydell Peterson ATT

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Cindy Macy Qwest opened the call and reviewed the agenda.

Ervin Rea ATT reviewed the CR with the team. Ervin advised that ATT would like the UNE – P standard interval to be changed to 12 hours. Currently in Colorado and Minnesota it is less than 2 days, and in all other states it is less than 3 days. Ervin advised these are generally billing only changes as they are just migrating the service from Qwest to a CLEC.

Cindy Macy Qwest asked if this request is for all UNE- P products, such as DSL, Centrex etc. Ervin advised it is for all conversions as is, not for new installs.

Anthony Washington Qwest advised we usually migrate the service in one day. If it doesn’t happen in one day, it is normally because there is some kind of problem, either with the order or the service that needs to be corrected first.

Liz Balvin MCI advised she would like the CR to include Conversion as specified also. MCI’s orders are done as ‘Conversion as Specified’ as they usually are disconnecting a feature. Liz advised they don’t usually add features. These are currently 3 days and Liz would like ‘Conversion as specified’ changed to the 12 hours standard interval.

Ervin Rae ATT asked for Qwest to determine if we can change both types of conversions; ‘Conversion as is’ and ‘Conversion as specified’. If each type of conversion requires a different SIG, than Qwest should proceed in that manner.

Ervin Rea ATT advised UNE-P has been in the market for 2 + years so he believes it is time for the interval to be improved.

Confirm Areas & Products Impacted Provisioning

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation AT&T is requesting Service for UNE-P will be delivered on the same day as the order is received, if received prior to 3:00pm.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Next steps are for ATT to present this CR at the November meeting. Qwest will prepare a response for the December meeting.


CenturyLink Response

January 13, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the January 2004 CMP Meeting

Ervin Rea AT&T

SUBJECT: "Qwest’s Change Request Revised Response - PC110303-1 "UNE-P Standard Interval Guide"

This letter is in response to CLEC Change Request PC110303-1. This CR is a request by AT&T asking Qwest to change the standard interval for non-dispatch UNE-P "As-Is", and "As-Specified" conversions from the current 3 days (2 in CO & MN) to less than or equal to 12 hours.

By way of background, it is important to note that Qwest has already made a change that reduces the interval for UNE-P POTS. As of December 23, 2003 Qwest updated the Service Interval Guide (SIG) to reflect the reduction in the service interval for UNE-P POTS and Resale POTS (Residence and Business) for non-dispatch orders. The change takes effect on January 15, 2004. All non-dispatch UNE-P POTS and Resale POTS (Residence and Business) orders will be completed by 8 a.m. on the due date. Current operational documentation for these products or business procedures are found on the Qwest Wholesale Web Site at this URL: http://www.qwest.com/wholesale/guides/sig/index.html

While there have been changes made to the service interval for UNE-P POTS, Qwest is denying the request for a further reduction to a 12 hour or less service interval guideline for this CR due to it being economically not feasible. The following information supports this decision.

AT&T has stated that the current migration interval for all non-dispatch UNE-P orders, whether they are "As Is" or "As Specified", should be changed to 12 hours or less. AT&T contends that these orders are, for the most part, just billing name changes and shouldn’t require 2 to 3 days for completion. Contrary to their assumption, Qwest finds that even though a billing name change is part of the migration, a complex set of systems and resources must interact to ensure orders are completed properly. If an interval of 12 hours or less were attempted, significant system and headcount impacts would put an undue economic burden on Qwest.

After an analysis of the impact to Qwest systems and workforce, Qwest has determined that a minimum of 1,100 hrs/week in ISC staff support would be required. This 15% increase in headcount represents the SDCs necessary to extract "As-Is" or "As Specified" requests, as IMA does not have the ability to do so today, and watch the work queue to ensure that the FOC is received by the customer by the desired due date.

The systems/process modifications would include:

? Significant changes to IMA to identify "As-Is" or "As Specified" requests, and the creation of an external work queue designed to accept the request. Changes to IMA would not diminish the need for an increase in headcount.

? FTS modifications would include service interval table updates.

? The FOC interval for a mechanized "As-Is" request is 24 hours, and the FOC interval for a manual request is 48 hours. These intervals would also have to be shortened in conjunction with the service conversion interval.

Although Qwest is declining this request, Qwest continues to evaluate service intervals associated with UNE-P products.

Sincerely,

Anthony Washington Product Management Qwest

December 5, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the December 2003 CMP Meeting

Ervin Rea AT&T

SUBJECT: Qwest’s Change Request Response PC110303-1 UNE-P Standard Interval Guide

This letter is in response to AT&T’s Change Request (CR) PC110303-1. This CR requests that Qwest Service for UNE-P be delivered on the same day as the order is received, if received prior to 3:00 pm.

Qwest is currently evaluating this request and proposes moving this Change Request into Evaluation Status while we continue to investigate. Qwest will provide an updated response at the January 2004 CMP meeting.

Sincerely,

Anthony Washington Product Manager


Open Product/Process CR PC110403-1ES Detail

 
Title: Update accuracy of FAM records
CR Number Current Status
Date
Area Impacted Products Impacted

PC110403-1ES Completed
8/18/2004
Pre-ordering, Ordering UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Owen, Randy
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently AT&T is experiencing difficulties with Qwest maintained FAM “Feature Availability Matrix” file being up to date. AT&T has been experiencing problems with the FAM file showing inaccurate USOCs or feature availability within NPA/NXX’s when a CSR shows that an existing Qwest customer has the features. AT&T believes this FAM file should be updated, at a minimum, weekly and that CLECs should be aware of updates to the FAM. This information must be readily available to Qwest as its own customers have the availability to obtain some features that CLECs are shown, via the FAM File, are unavailable. All CLECs will obtain valuable data from current, accurate and thoroughly updated information within the FAM file. AT&T therefore requests that these updates be made immediately and continually.

Expected Deliverable:

December 2003


Status History

11/04/03 - CR Submitted

11/05/03 - CR Acknowledged

11/10/03 - Contacted CLEC to schedule clarification call

11/10/03 - Scheduled clarification call for 11/14

11/14/03 - Held Clarification Call

11/19/03 - Nov meeting minutes will be posted to the database

12/10/03 - Emailed response to CLEC

12/15/03 - Held CLEC ad hoc call to further discuss the FAM file

12/17/03 - Dec meeting notes will be posted to the database

12/22/03 - Emailed notes to CLECs

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

2/27/04 - Jean Novak advised she communicated with Bonnie regarding the ICONN database. The ICONN database is different than the FAM file.

3/17/04 - March CMP meeting notes will be posted to the project meeting section

3/22/04 - Added ES to CR number as CR was escalated

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/5/04 - ATT Escalated this CR a second time

5/6/04 - CMPR.05.06.04.F.01652.CMPEscalationNotification

5/12/04 - Escalation letter sent to ATT

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/9/04 - MCI reported issue on FAM file. Randy Owen working with MCI on correcting the file transmission

8/16/04 - August CMP meeting mintues will be posted to the database


Project Meetings

8/16/04 CMP Meeting Mintues Randy Owen – Qwest advised that last month we asked the CLECs to review the file and identify any questions or issues. Randy advised that Qwest does not have any open issues and would like to close this CR. Carla Pardee – ATT advised she has checked with her centers and it is okay to close the CR. This CR will move to Completed Status.

July 21, 2004 CMP Meeting notes: Randy Owen – Qwest advised MCI did open a ticket on the FAM file as they identified missing USOCs. A trouble report was called in and Qwest has fixed the problem. Liz Balvin – MCI asked the CLECs to try and review the FAM file to make sure there are not other issues. The CLECs would like to leave this in CLEC Test one more month.

June 16, 2004 CMP Meeting notes: Randy Owen – Qwest advised this CR was implemented and is being updated weekly. Randy asked the CLECs if they have any questions or have reviewed the updated FAM file. Carla Pardee – ATT advised the updates look accurate and current. This CR will move to CLEC Test Status.

May 19, 2004 CMP Meeting notes: Randy Owen – Qwest advised that we are on schedule with a target date of May 31 to update the FAM file on a weekly basis. Carla Pardee – ATT advised that we are pleased that this is happening. Liz Balvin – MCI clarified that we started the clean up on May 6. Randy Owen advised that the data was updated on May 6, there wasn’t a clean up, but the data is now current as of May 6. We are targeting to start the weekly update in the May 31 time frame. Liz asked what day of the week will the file be updated? Randy advised that we have not determined that yet. It is dependant upon the day the legacy system updates. Qwest needs to confirm the schedule before we can provide the day of the week that the file will be updated. Cindy Macy – Qwest asked the CLEC community if it is okay to release this update with a Level 1 change since this CR was escalated. The CLECs agreed that is okay. This CR will move to Development status.

April 21, 2004 CMP Meeting notes: Randy Owen – Qwest advised that we are moving forward on this CR. We are scheduling with our development team. We do not have a target date as of yet. Liz Balvin – MCI advised that they are looking to develop against this file. We are looking forward to having it updated weekly. This CR will stay in Evaluation Status.

March 17, 2004 CMP Meeting notes: Randy Owen – Qwest reported that he does not have any additional updates for this project. Qwest is still waiting for funding approval. Carla Pardee – ATT advised that she is upset and doesn’t understand why this is not funded. This CR requires minimal resources. She has expressed her concern for the past few months. ATT has a real need for this file to be updated and she would like to escalate the CR. Susie advised that ATT should go ahead and escalate the CR. This CR will stay in Evaluation Status.

February 18, 2004 CMP Meeting Connie Winston – Qwest advised that we have not gotten approval as of yet for this CR. We are still waiting for approval. Carla Pardee – ATT advised that ATT is disappointed that this did not get approved as it is a critical issue and it doesn’t seem as if this CR requires a lot of resources, so we do not understand the lack of approval. Bonnie Johnson – Eschelon asked is this one is like the ICON database? Connie advised she is not sure. Bonnie advised that her Service Manager (Jean Novak) told her that the fix would take place on March 1, 2004. Connie advised that maybe an update is scheduled but not the entire fix. Cindy Macy – Qwest agreed to check with Jean Novak. This CR will remain in Evaluation Status.

Janaury 21, 2004 CMP Meeting Connie Winston – Qwest advised that this CR is in the same situation as some of the others. We are waiting to schedule and we hope to have a date in February. Carla Pardee – ATT asked what is the current process for updating the FAM file? Connie advised it is not being updated in a timely fashion. It has to be done manually and it is a huge manual effort. The way that we update FAM is that SONAR tracks availability by switch via tables in SONAR. This information is downloaded to a server and it becomes available to Qwest. This data should be published to FAM. We are working to get this update done in a mechanized fashion and looking at SONAR going away. Liz Balvin – MCI asked about the BPL edit that will reject the LSR if the feature is not available, that is part of 15.0. Connie Winston said this edit goes against the SAQ, not the FAM. Bonnie Johnson asked is there a need for the FAM file? Connie advised her understanding is that ATT wants to use it as a sales tool up front. Bonnie asked can it be used just from IMA so we don’t have to maintain two sources. Connie advised FAM is downloadable and in a bulk format, while IMA is an individual selection. The intent is both tools will use the same source in the future. Bonnie advised this is critical to our business as we use this information to offer products. Bonnie advised this is so critical that we will take another route if we don’t get it from CMP.

December 17, 2003 CMP Meeting Connie Winston – Qwest reported that we are still evaluating this CR. We are having a difficult time getting a process built for the updates and determining what that looks like. We are still looking at this CR and will change the status to Evaluation.

December 15, 2003 Ad hoc meeting PC110403-1 FAM File Ad Hoc Meeting

In attendance: Nicole James – Qwest Dave Fane - ATT Liz Balvin – MCI Phyllis Burt – ATT John Gallegos – Qwest Lydell Peterson – Qwest Carla Pardee – ATT Cindy Macy – Qwest Randy Owen – Qwest Kim Chambers – Qwest

Cindy Macy – Qwest opened the call and explained that the purpose of the call is to review the issues associated with the FAM file and how the CLEC community uses the file. ATT requested this additional meeting with Qwest.

Carla – ATT advised that ATT uses the file to figure out which features are available prior to submitting orders. Qwest doesn’t hard reject the LSRs when the data is not accurate. We may or may not get the feature provisioned. We do not know until our customer calls and tells us the feature is not working. Dave Fane – ATT advised that every other ILEC they work with sends and error report back that identifies the feature is not available. Then we update our file and don’t request the feature again. ATT would like Qwest to reject the order when we don’t detect the feature.

John Gallegos – Qwest explained that this feature will be available in 15.0 EDI. This functionality is available today via SAQ in EDI. The CLECs said they do not have that EDI transaction built and they were told to use the FAM file as an alternative until 15.0 is available.

ATT advised they assumed they would get rejects if the feature was not available. Qwest advised we are not billing the CLECs for features they are not getting. ATT advised we are billing our end users as we believed the feature did get provisioned.

John Gallegos – Qwest advised he understands there is a gap in the FAM file data, and that the feature is available via the SAQ in EDI and that 15.0 will reject upfront if features are not available.

Liz Balvin – MCI asked if out of sync conditions are identified in the file so the CLECs can avoid those areas. John Gallegos- Qwest advised the file is too large as there are many switches and features and NPAs available in each state.

Liz Balvin – MCI asked if Qwest is eliminating the FAM file after 15.0. John Gallegos – Qwest advised we are looking at all options. The concern that Qwest has is being able to support the FAM file going forward. We are doing everything we can to update the file. Qwest has manually updated the file. The last update was the end of September. This takes a considerable amount of time and manual effort.

Carla – ATT advised they just wanted to reconfirm their need to access the FAM file. Liz Balvin – MCI advised that it is important to make sure the FAM file is updated. Phyllis Burt – ATT asked what is the correct process if we have trouble using the FAM file? Do we submit a trouble ticket to the Help Desk? John Gallegos advised it would probably be considered a Sev 3 ticket. John advised he can not give a timeframe as to when the trouble ticket / problem would be corrected. John assured the CLECs that Qwest is working on this issue and trying to determine the best action to take.

November 19, 2003 CMP Meeting Carla Pardee – ATT reviewed and presented this CR. Carla advised that ATT uses the FAM file to look at usoc availability by switch. Carla advised the data is not always accurate and ATT attempts to provide these features to their customers. ATT does not find out the feature is not available until their customer contacts them to report the feature is not working. This creates billing errors also. Bonnie Johnson – Eschelon asked if this was the ICON database. Carla advised you can access ICON and FAM on the web. Liz Balvin – MCI advised that MCI has also experienced situations when the SOC notice says the feature was provisioned, when it really isn’t available.

PC110403-1 Clarification Call Update Accuracy of FAM file November 14, 2003

In attendance: Monica Manning – Qwest Gary Berroa – Qwest Leo Demitriadis – ATT Nicole James – Qwest Doug Andrean – Qwest Cindy Macy – Qwest Carla Pardee – ATT Michael Whitt – Qwest

Cindy Macy – Qwest opened the call, introduced attendees and reviewed the agenda.

Carla Pardee – ATT reviewed the CR. Carla advised ATT has had problems with the FAM file not being up to date. The file shows inaccurate USOC feature availability information. ATT uses this file often. We order a feature and if Qwest doesn’t support the feature we don’t receive a reject on the LSR. Qwest continues to provision service. The order completion occurs and billing occurs but we don’t really provision the feature as it is not available. This causes billing errors to our end users. Leo Demitriadis – ATT explained ATT would like to have a change control log file we they know what has changed, or to have the file updated when ever the data changes, or to have it updated on a regular schedule.

The team reviewed how to access the file to make sure we are all talking about the same file. The URL for instructions on how to access the file is;

Doug Andrean – Qwest asked how often is the file updated. ATT advised they do not know.

Micheal Whitt – Qwest asked if UNE –P was the product that ATT is concerned with. ATT advised yes.

Nicole James – Qwest asked if ATT has an example of errors that you have found? Carla advised she will send Qwest an example. She believes she has an example in Minnesota.

Mallory Paxton – Qwest asked how does ATT know when it is not accurate. Carla advised they do not know until their customer calls them back to advise they did not get the feature provisioned.

The team agreed they understand the request. Cindy Macy – Qwest advised this CR will be on the agenda for the November CMP meeting and ATT will present the CR. Qwest will provide a response at the December meeting.


CenturyLink Response

For Review by the CLEC Community and Discussion at the December 17, 2003 CMP Meeting

December 9, 2003

AT&T Carla Dickinson Pardee LSAM Manager

SUBJECT: CR # PC110403-1 Update accuracy of FAM records

This letter is in response to AT&T’s Change Request (CR) PC110403-1. This CR requests that: - Qwest update the accuracy of FAM records

Qwest is currently reviewing the processing and functionality provided by the FAM file. Qwest requests that this CR be placed in Evaluation status. AT&T has also requested an additional meeting be held to discuss the FAM file in more detail. Qwest will schedule the additional meeting.

Sincerely,

Connie Winston Qwest Communications


Open Product/Process CR PC111103-1 Detail

 
Title: Snap Back Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC111103-1 Withdrawn
12/17/2003
Maintenance Repair, Provisioning LNP, UNE - P
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: To Be Determined
Director:
CR PM: Harlan, Cindy

Description Of Change

When performing a UNE-P migration and a CLEC determines that one or more numbers is experiencing a no dial tone (NDT) situation it is requested that the following happen: The CLEC be able to make a phone call to the Qwest provisioning center and request that the migration stop and Qwest would establish the customer's service on the Qwest network. If the migration has completed Qwest would take the customer back and bring the customer's service up to an active status with dial tone. CLEC would issue a supp to their LSR indicating that the due date would change because of a facility issue and provide a new due date. It is further requested that when a customer is being provisioned through the LNP process and the CLEC determines that there is an NDT situation that the same process cited above take place and that the customer be physically taken back onto the Qwest network. For this process to work with the LNP process the notification to Qwest would need to take place prior to Qwest removing the customer from their switch. Consequently it is requested that the translations not be taken out of the Qwest switch until 11:59pm, switch time, the day after completion of the port.

Expected Deliverable:

Improvement of performance measures regarding OP-5 performance indicator (% trouble within 30 days). Improved customer satisfaction as a result of no loss of dial tone.


Status History

11/11/03: CR Received

11/12/03: CR Acknowledged

11/12/03: Sent similar CR to ATT to determine if this is a dup request and if we can change this CR to pending withdrawl

11/13/03: Ervin Rea ATT advised this CR is similar to PC081403-2. He is willing to withdraw this CR as long as PC081403-2 is on the November agenda and a resolution can be reached that will provide ATT the opportuntiy to ensure that our customers don't go out of service in a UNE-P conversion situation. Email forwarded to Joan Wells-Qwest to review.

11/13/03: Sent email to Ervin to advise we wil change to pending withdraw status and he will ask questions about PC081403 to make sure the Workback process meets his needs

11/19/03: Discussed the related CR PC081403 at the November CMP meeting. Ervin Rea agreed that CR seems to be meeting the needs of this CR. Qwest will present this CR at the December CMP meeting as pending withdraw.

11/20/03: Ervin Rea - ATT replied via email and agreed to withdraw this CR.

12/17/03: December CMP meeting the CLECs agreed to withdraw this CR. Notes will be posted to the database.


Project Meetings

December 17, 2003 CMP Meeting Cindy Macy – Qwest advised that this CR was submitted and it was determined that the Work Back Process CR PC081403-2 is similar to what this CR is asking for. Ervin Rea – ATT agreed to change the CR to pending withdraw status after the Clarification Call. ATT agreed to withdraw this CR at the December meeting. The status will change to Withdraw.


Open Product/Process CR PC111903-1 Detail

 
Title: Website for Event Notifiers
CR Number Current Status
Date
Area Impacted Products Impacted

PC111903-1 Completed
10/20/2004
pre-ordering provisioning ordering billing m/r
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Owen, Randy
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T and other CLECs desire Qwest to provide a website listing all Event Notifiers that have been submitted by Qwest for the past 90 days. This website will provide, at a minimum, the event number, description of event, date submitted, system used with version number, status (i.e. pending analysis, closed, initial, etc), severity level, and region effected. AT&T further requests that the description be complete enough to enable a CLEC to search any field by product, date, and trouble type. AT&T also requests that the website would have the functionality so that CLECs could sort by column, however, internal analysis management would be up to each individual CLEC.

Expected Deliverable:

By January 2004, AT&T expects the following deliverable: A website listing all Event Notifiers sent by Qwest for the past 90 days. The website will provide, at a minimum: 1) event number; 2) complete description of event; 3) date submitted; 4) system type with Version number; 5) status; 6) severity level; and 7) region effected.


Status History

____________________________________________________

11/19/03 CMP Meeting

Kit Thomte – Qwest advised that this CR was talked about Tuesday during the Global Action Item meeting. This CR was updated with the new title and description. Carla Pardee – ATT advised they would like to keep the old CR open and use the new CR description and title to open a different/new CR. Cindy Macy – Qwest asked if ATT would like to have the new CR clarified or had this happened during the Global Action Item meeting. Carla advised she would like Qwest to hold a Clarification Call for the new CR.

_________________________________________________________________________________________

11/19/03: CR Received (CR came in on 11/12 but ATT was not sure if they wanted to update existing CR PC022703-9 or create new one. During Nov 19 CMP meeting ATT advised they would like to open new CR and agreed for Qwest to accept CR and schedule clarification call.

11/21/03: Acknowledge CR

11/24/03: Scheduled Clarification Call for 12/4

12/4/03: Held clarification call

12/17/03 - December CMP notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/17/04 - March CMP meeting notes will be posted to the project meeting section

3/30/04 - Added supplimental information on project identifying the differences between PC022703-9x and PC111903-1

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/2.04 -CMPR.07.01.04.F.01853.Event_Notification_Rept (New tool available )

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - Aug CMP meeting notes will be psoted to the project meeting section

9/15/04 - September CMP Meeting minutes will be posted to the database

9/28/04 - PROS.09.28.04.F.02106.WebEventNotification effective immediately

10/7/04 -Donna - ATT advised this has been deployed and is okay to close at October Meeting

10/20/04 - October CMP Meeting minutes will be posted to the database


Project Meetings

10/20/04 CMP Meeting Minutes: Randy Owen – Qwest advised that this CR was deployed on September 28. We have not gotten any negative feedback from the CLECs. The tool is working as we expect. Donna Osborne-Miller ATT advised it is okay to close. This CR will move to Completed Status.

9/15/04 CMP Meeting Mintues: Randy Owen – Qwest advised that we are still on track for deployment September 30, 2004. This CR will remain in Development Status.

8/16/04 CMP Meeting Mintues: Randy Owen – Qwest advised that last month the CLEC Community identified some issues and changes associated to this CR. Randy advised that Qwest will be able to make changes to the following fields: Status Column, Combine GUI/EDI when both are affected, Work Around Section, Notices affecting the release, and Patch date. Qwest is targeting implementation near September 30. Cindy Macy – Qwest asked the CLEC Community if it is okay to implement these with a Level 1 Notification. The CLEC Community agreed that was okay. This CR will remain in CLEC Test Status.

July 21, 2004 CMP Meeting Notes Randy Owen – Qwest advised that this was deployed on July 2. Qwest has not received any comments as of yet. Donna Osborne-Miller ATT advised that she does have feedback from Phyllis Burt. When you export the report the status field is not available. The field needs to identify ‘common’ if the event impacts both EDI and GUI. Liz Balvin – MCI said she also identified this same issue. In addition, MCI would like the ‘Work Around Solution’ identified on the spreadsheet, also would like to know what release is impacted, and would like the Patch Date information. Stephanie Prull – Eschelon noticed on a ticket that it says ‘Qwest will initiate a call on XX date’. Steph asked if this is accurate as she thought that verbiage would only appear on tickets that warrant a call. Randy Owen – Qwest advised this is a bug that we are working on. Randy summarized the issues as Status Column, Common/EDI/GUI, work around on spreadsheet, release number, and patch date. Randy will check on these items and provide an update as to what Qwest can do. This CR will move to CLEC Test Status.

June 16, 2004 CMP Meeting notes: Randy Owen – Qwest advised we have had some challenges in the development stage of this CR. The target date is June 30. We are making progress and plan on delivering in the June 30 timeframe. This CR will remain in Development Status.

May 19, 2004 CMP Meeting notes: Randy Owen – Qwest advised that the development team has provided a target date of June 14 for this CR. Randy advised this will provide a download, with sort capability and a more complete picture of outstanding items. This CR will remain in Development Status.

April 21, 2004 CMP Meeting notes: Randy Owen – Qwest advised that we are working with our development team on this CR. We do not have a firm date as of yet, but development is targeting May. Liz Balvin and Bonnie Johnson asked if this included the downloading capability. Randy advised yes. This CR will stay in Development Status.

March 17, 2004 CMP Meeting notes: Randy Owen – Qwest advised that funding for this CR has been approved. This is an update from last month. We are waiting to schedule this CR. Carla asked for the schedule information to be sent to her as soon as possible. This CR will move to Development Status.

February 18, 2004 CMP Meeting Connie Winston – Qwest advised this CR also did not get approved as of yet. We are working on this and should have an update soon. This CR will remain in Evaluation Status.

January 21, 2004 CMP Meeting Connie Winston – Qwest advised this is the CR that was opened as part of the Global Action Item meetings. The work is not scheduled as of yet. Carla Pardee-ATT asked when is this planned for scheduling. Connie advised she does not have a definite date as of yet but hopes to have a schedule in February. Liz confirmed that this report would look like a spreadsheet of the Event Notification Report. Connie agreed. Liz asked about the additional details and root cause analysis information that was discussed. Connie advised we did not agree to provide that information. That information would be very labor intensive to provide. Liz advised it would be helpful to know what the problem was. Carla agreed that more detail is better. Bonnie said they want to know what made it break, how did we stop it (work around), and what is going to fix it going forward. Connie said that it takes a lot of over head to put together that level of detailed information on the event notification. The CLECs asked if Qwest looks at the reject code to find out if multiple CLECs are impacted. Connie advised Qwest does this, and looks at the global picture and sometimes the data does show a different perspective. This CR will move to Evaluation Status.

December 17 CMP Meeting Carla Pardee – ATT presented this CR. Connie Winston – Qwest advised that this CR is related to the Global Action Item meetings and was opened as a result of PC022703-9X. This CR will move to Presented Status.

Clarification Call PC111903-1 Website for Event Notifiers

December 4, 2003 11: 00 – 11:30 a.m. MT

Attendees: Jim Recker – Qwest Kim Isaacs – Eschelon Kyle Kirves – Qwest Steph Prull – Eschelon Bonnie Johnson – Eschelon Carla Pardee – ATT Randy Owen – Qwest

Cindy Macy – Qwest opened the call and clarified for the users that this CR was opened as a result of decisions made at the Global Action Item meeting. PC022703-9X originally requested similar functionality, but through the Global Action Item meetings agreement was reached that a new CR would be opened (PC111903-1).

Carla Pardee - ATT reviewed the CR. Carla described the functionality that ATT is looking for. A website that displays all event notification, with event number, complete description of event, date submitted, system type and version number, status, severity level and region affected.

The CR also states that this website would display event notifications that have been submitted in the past 90 days. The team clarified the better way to display event notifications is to make them available for 30 days after they have been implemented. The clock would start when they are implemented.

Kim Isaacs – Eschelon asked if the description included the work around information. Randy Owen said they should be able to include this in the description, or include it as a field on the report. The plan is to use the event notification form. There may be an issue to the amount of space available on the web site. The original event notification is always available to view the work around information.

Bonnie Johnson – Eschelon suggested we show a field work around ‘yes or no’ and then if yes is populated you could view the work around information on the original event notification.

Discussion took place regarding sorting by system. Randy Owen – Qwest advised that system is a separate field on the event notification, so you should be able to sort by that field on the report. Sort functionality would be provided so users could sort by any specific field.

The CLECs asked on average how many event notifications are there in a 30 day period? Randy estimated at less than 30 and greater than 10.

Steph Prull – Eschelon requested the ability to sort by ‘individual version’. For example, if an event impacted multiple versions, to list the versions individually so the CLECs could view events by version. If a CLECs wanted to see all events that affect V13, they could sort by individual version.

The team agreed the right personnel were involved and that Qwest understood the CLECs expectations. This CR impacts all products and any area that an event notification could be issued on.

Next steps are for this CR to be presented by ATT at the December CMP meeting. Qwest will prepare a response at the January CMP meeting.

11/19/03 CMP Meeting Kit Thomte – Qwest advised that this CR was talked about Tuesday during the Global Action Item meeting. This CR was updated with the new title and description. Carla Pardee – ATT advised they would like to keep the old CR open and use the new CR description and title to open a different/new CR. Cindy Macy – Qwest asked if ATT would like to have the new CR clarified or had this happened during the Global Action Item meeting. Carla advised she would like Qwest to hold a Clarification Call for the new CR.


CenturyLink Response

For Review by the CLEC Community and Discussion at the January 21, 2003 CMP Meeting

January 14, 2003

AT&T Carla Dickinson Pardee LSAM Manager

SUBJECT: CR # PC111903-1 Web site for Event Notifier

This letter is in response to AT&T’s Change Request (CR) PC111903-1. This CR requests that Qwest provide a web site for Event Notifiers.

Qwest understands the requested change and the enhancements are under evaluation. Qwest will move this CR to Evaluation status.

Sincerely,

Connie Winston Qwest Communications


Open Product/Process CR PC120803-1 Detail

 
Title: Associated Move Orders
CR Number Current Status
Date
Area Impacted Products Impacted

PC120803-1 Completed
7/26/2004
Billing, Maintenance/Repair, Provisioning UNE, UNE-P, Resale, Unbundled Loops, Products where T&F issued when there is a move
Originator: Adkisson, Ann B.
Originator Company Name: AT&T
Owner: Davis, Qiana
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Revised Description of Change 02-03-04

When a CLEC submits a move order (M) Qwest creates two orders, a to (T) and from (F) order. The problem resides in the fact that these orders are associated with each other but no action is taken when the T order is placed in jeopardy and the F order is not stopped. Clarification calls with Qwest has indicated that the F order is "always" worked prior to the T order. This process is a guarantee that the customer will be taken out of service prior to the T order being completed regardless of jeopardy, and the jeopardy will cause the the customer to be out of service for a longer period of time. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is no electronic/mechanical means of associating the T order to the F order. Some scenarios are:

1) customer has X number of TN's and is moving within a building and retaining the same TN's.

2) customer has X number of TN's is moving to another building within the same rate center and retaining the same TN's.

3) Customer has X number of TN's and is moving within the same rate center but does not want to keep all of the TN's.

4) customer has X number of TN's and is moving and wants to change TN's and have a forwarding message on the old TN's.

In each of these instances the customer is taken out of service with the creation of the two orders and the F order being worked, or batched, prior to the T order being completed. Since it is a Qwest process to create two orders it would be Qwest responsibility to ensure a process that would prevent taking the customer out of service.

Revised Expected Deliverable (02-03-04):

That no customer would be taken out of service on any move order.

Original Description of Change (12-08-03):

When a CLEC submits a move order (M) Qwest creates two orders, a to (T) and from (F) order. The problem resides in the fact that these orders are not associated as related orders. It is an industry standard that related orders be associated in the RORD field in an effort to ensure that service is not interrupted. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is not electronic/mechanical means of associating the T order to the F order. Since these orders are not associated as RORD the F order is completed and the customer is taken out of service resulting in a disconnect in error.

Original Expected Deliverable (12-08-03):

Expected Deliverable: Processes be changed to associate all T&F orders to each other. That systems be modified to ensure that if a related T order is jeopardized that the F order is automatically placed in a jep status and the work to disconnect the order is stopped. Expected result will reduce, if not eliminate, disconnects in error because of a jeopardized T order. In the month of November AT&T had 10 disconnects in error because of jeopardized T orders. In the event the F order is completed before the T order on the due date and the T order is jepped, Qwest should immediately re-instate the service in an effort to prevent an out of service condition .


Status History

12/08/03 - CR Submitted

12/09/03 - CR Acknowledged

12/15/03 - Held Clarification Meeting

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/26/03 - Changed title of CR to Associated Move Orders

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/28/04 - Held second Clarification Meeting

02/03/04 - Change request revised by AT&T, see description of change and expected deliverable

02/06/04 - Held Clarification Meeting

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/05/04 - Qwest sent PROS.03.05.04.F.01462.NetCommCallCustRec.doc, effective immediately

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/22/04 - Qwest sent PROS.04.22.04.F.01594.Ord_Overview_V50 proposed effective date 6/4/04

05/19/04 - Qwest sent final notice PROS.05.19.04.F.01686.FNL_Ord_Overview_V50 effective date 6/4/04

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

07/21/04 July CMP Meeting Linda Sanchez-Steinke with Qwest said the PCAT update was effective on 6/4/04, the CR is in CLEC Test status and we would like to close. Carla Pardee with AT&T said she would check for any open issues on this CR and e-mail whether or not this can be completed. This CR will remain in CLEC Test status and move to completed after AT&T agrees to close.

06/16/04 June CMP Meeting Linda Sanchez-Steinke with Qwest said the PCAT update was effective on 6/4/04. This CR will move to CLEC Test status.

05/19/04 May CMP Meeting Qiana Davis with Qwest said there was one comment received on the Pre-ordering PCAT. Qwest will provide a response back today. The proposed effective date is 6/4/04. This CR will remain in Development status.

04/21/04 April CMP Meeting Qiana Davis with Qwest said there will be level 3 changes made to the Pre-ordering PCAT that will include the interim manual process and the can be reached number. Tomorrow at the Systems meeting the CR for the systems solution will be presented. Bonnie Johnson with Eschelon said she was really excited that the changes were being made because recently Eschelon had a customer move and the customer was out of service for an entire day. Donna Osborne-Miller with AT&T said that she will alert Ervin Rea that the PCAT will be coming out soon and to make any comments. This CR will move to Development status.

03/17/04 March CMP Meeting Qiana Davis with Qwest said the T & F process is used for both Retail and Wholesale orders. In researching the T & F process, Qwest has initiated an MCC because in rare instances, technicians were not adhering to the process of calling the customer to find out the disposition of the F order when the T order is held. Qwest is updating the PCAT process for the can be reached number because sometimes the number forwards to voice mail. In addition, Qwest will be sending a level 3 notification for a manual interim process allowing population of the FDT field. This interim process will allow the F order to be delayed if the T order will be held. Qwest will also submit a systems CR for the 17.0 release to mechanize the manual process. Bonnie Johnson with Eschelon asked what IMA changes need to be made. Qiana said the details are still being worked out and that the DFDT field edits will be lifted to allow a value to be input and that will be used to inform the technician to hold the F order. Bonnie asked if this would give the ability to communicate if the T order is held the F should be held. Qiana said the field is currently used for a time value and the edit will be lifted to indicate hold the F order. Bonnie asked what work is being done in the backend systems to force the holding of the F order. Qiana said the technician would be informed to hold the F order until a call is received and this will be an interim manual handling process. Bonnie asked Qiana to keep everyone updated of the progress. Ervin Rea with AT&T said he was surprised and glad that Qwest had found a way to associate the T & F orders, and asked if orders would no longer be disconnected at 12:01 a.m. Qiana said yes, if the order has the DFDT field populated it will allow the F order to be held. This CR will move to Development status.

- 02/18/04 February CMP Meeting Qiana Davis with Qwest reviewed the draft response and said that AT&T had revised the CR on 2/3/04 and that Qwest is evaluating the modifications and require additional time to respond to the CR. Qiana added that Qwest would provide an update in March. Carla Pardee with AT&T said AT&T had determined that a process does exist, however AT&T has had several examples where the orders are disconnected. Carla also said they have been working with their service management team on this issue as well. Qwest will provide an update in March. This CR will be moved to Evaluation status.

CLEC Change Request Clarification Meeting

2:30 p.m. (MDT) / Friday February 6, 2004

1-877-572-8687 3393947# PC120803-1 Associated Move Orders

Name/Company: Ann Adkisson, AT&T Carla Pardee, AT&T Ervin Rea, AT&T Cheryl Peterson, AT&T David Belanger, AT&T Joyce Perry, AT&T Jim Recker, Qwest Mike Lanoue, Qwest Jerry Jenson, Qwest Qiana Davis, Qwest Pat Torkelson, Qwest Brenda DeFilippo, Qwest Doug Slominski, Qwest Lydell Peterson, Qwest Danelle Haynes, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested Change Linda Sanchez-Steinke with Qwest said that we are holding this clarification call to discuss the revisions AT&T made to the CR on 2/3/04.

Linda read the description of change; When a CLEC submits a move order (M) Qwest creates two orders, a to (T) and from (F) order. The problem resides in the fact that these orders are associated with each other but no action is taken when the T order is placed in jeopardy and the F order is not stopped. Clarification calls with Qwest has indicated that the F order is "always" worked prior to the T order. This process is a guarantee that the customer will be taken out of service prior to the T order being completed regardless of jeopardy, and the jeopardy will cause the the customer to be out of service for a longer period of time. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is no electronic/mechanical means of associating the T order to the F order. Some scenarios are:

1) customer has X number of TN's and is moving within a building and retaining the same TN's.

2) customer has X number of TN's is moving to another building within the same rate center and retaining the same TN's.

3) Customer has X number of TN's and is moving within the same rate center but does not want to keep all of the TN's.

4) customer has X number of TN's and is moving and wants to change TN's and have a forwarding message on the old TN's.

In each of these instances the customer is taken out of service with the creation of the two orders and the F order being worked, or batched, prior to the T order being completed. Since it is a Qwest process to create two orders it would be Qwest responsibility to ensure a process that would prevent taking the customer out of service.

Expected Deliverable: That no customer would be taken out of service on any move order.

Ervin Rea with AT&T said that this CR was revised as a result of the CMP clarification meeting 1/28/04 and the CMP meeting 1/21/04. If Qwest always works the F order first and if the F order is in a batch that is disconnected shortly after midnight on the due date then the business customer is always going to be out of service. Additionally, if there is a jep on the T order, then the business customer will be out of service for an extended amount of time.

Cheryl Peterson with AT&T said that when she did a search on the Qwest web site, searching for “Move” she found three processes that say the F order is due the day after the due date of the T. The port within process http://www.qwest.com/wholesale/downloads/2003/030513/DNLDPortWithinProcess1005-13-03.doc

Cheryl asked if there is an existing ordering process in place, would there be a need for a CR. Linda Sanchez-Steinke with Qwest said that she was not sure if a CR would be required for adherence of the process and would take the question back.

Ervin said that he would still want to have adherence to the process through Service Management. Jim Recker with Qwest asked if we find the process is correct would that satisfy the request. Ervin said no it would not satisfy the request. The process should say that there should not be a disconnect of the F location.

Confirm Areas & Products Impacted Primarily UNE-P and POTS Residence and Business. Other products include Resale, Unbundled Loops and any products T&F orders are issued for when there is a move and there is a jeopardy situation.

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting.

Identify/Confirm CLEC’s Expectation Expected Deliverable: That no customer would be taken out of service on any move order.

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan This CR will be discussed at the February 18, 2004 CMP Meeting

Tue 2/3/04 11:46 AM From: Pardee, Carla D, NKLAM [cdickinson@att.com] To: Sanchez Steinke, Linda cc: Rea, Ervin E, NKLAM, Adkisson, Ann B, NKLAM, Perry, Joyce M, NKLAM, Peterson, Cheryl J, NKLAM, Peterson, Lydell Subject: Amended PC 120803-1 Linda - per the Audix I left you a few minutes ago, please find the amended language to PC 120803-1. AT&T would like to set up another meeting to discuss this, at your earliest convenience - if possible this Friday, or early next week. I know we discussed submitting a new CR, but AT&T prefers to amend the language so that we don't lose any additional time resolving and implementing this CR. Please feel free to call me at 303-647-2234 if we need to discuss further. As usual, thanks for your assistance and help with this change request!

CLEC Change Request Clarification Meeting

8:30 a.m. (MDT) / Wednesday January 28, 2004

1-877-572-8687 3393947# PC120803-1 Associated Move Orders

Name/Company: Ann Adkisson, AT&T Carla Pardee, AT&T Irvin Rea, AT&T Sheryl Peterson, AT&T David Belanger, AT&T Joyce Perry, AT&T Jim Recker, Qwest Mike Lanoue, Qwest Jerry Jenson, Qwest Jeanette Barns, Qwest Qiana Davis, Qwest Kit Thomte, Qwest Pat Torkelson, Qwest Brenda DeFilippo, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested (Description of) Change Linda Sanchez-Steinke with Qwest said that we are holding a second clarification call to discuss this CR and the CR may be amended as a result of this clarification meeting. Linda read the description of change; When a CLEC submits a move order (M) Qwest creates two orders, a to (T) and from (F) order. The problem resides in the fact that these orders are not associated as related orders. It is an industry standard that related orders be associated in the RORD field in an effort to ensure that service is not interrupted. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is not electronic/mechanical means of associating the T order to the F order. Since these orders are not associated as RORD the F order is completed and the customer is taken out of service resulting in a disconnect in error.

Expected Deliverable: Processes be changed to associate all T&F orders to each other. That systems be modified to ensure that if a related T order is jeopardized that the F order is automatically placed in a jep status and the work to disconnect the order is stopped. Expected result will reduce, if not eliminate, disconnects in error because of a jeopardized T order. In the month of November AT&T had 10 disconnects in error because of jeopardized T orders. In the event the F order is completed before the T order on the due date and the T order is jepped, Qwest should immediately re-instate the service in an effort to prevent an out of service condition.

David Belanger with AT&T said the description of change sounds like what the UNE-P group is looking for and if Qwest relates the T&F orders the issue will be resolved. Irvin Rea with AT&T said that the problem is the two orders are not related beyond creation of the orders. Joyce Perry with AT&T said the problem is that Qwest works the F order around mid-might before the T order is worked. AT&T wants the T order worked first, then if the T is jeoped the F be jeoped at the same time. Irvin clarified that AT&T doesn’t want the F order worked until the T order is completed.

Brenda DeFilippo with Qwest asked if the T & F orders have different phone numbers. AT&T said that in some cases there would be different phone numbers. David Belanger said the T order must complete when worked before the F order and then the F order should have 24 hours to complete.

Sheryl Peterson with AT&T asked her group if they really understand the process.

Mike Lanoue with Qwest gave examples of different types of orders 1) if in same central office, same telephone number same wire center 2) in different central office, different telephone number Irvin said if the CLEC issues a move order, RORD has to be filled out by Qwest

Qiana Davis with Qwest asked if the only type of orders that we would be concerned with were move orders and the activity of T. Irvin answered yes. Qiana asked if the orders are residence or business accounts and if the business is still located at the from address. Irvin said both Business and Residence. David Belanger said that the business is not always still located at the old address and sometimes someone goes back to the old address to answer phones. Qiana asked if the T order is jeoped would remote call forwarding help the situation. Irvin answered that partial remote call forwarding and David added that the disconnect recording is played.

Sheryl Peterson with AT&T asked if the normal Qwest process was to batch down stream the orders worked at night. Sheryl clarified her question and said not batch as CLEC sending volumes, but talking about on due date working in the appropriate central offices. Jim Recker said that if frame due time is not requested, the F will be worked shortly after midnight on the due date.

Brenda DeFilippo with Qwest said if T&F and the same TN, those are worked together. If T&F with different TN then the F comes through as disconnect. Irvin said that when issuing a move order with action of T, then create 2 orders, the F order should have a disconnect date of the day after the T is due. Brenda asked if same TN at different location. Jeanette Barns asked if the customer has vacated the location.

AT&T had further discussion on whether or not all the products with scenarios were captured in the CMP CR submitted; same TN, different TN, customer has already moved from location and intercept message.

As a result of this clarification meeting, AT&T will meet internally and determine what exact change they are requesting; and identify products and scenarios for this change request. AT&T will either submit revisions and scenarios to this change request or submit a new change request.

Confirm Areas & Products Impacted Currently CR reads: UNE-P, All POTS, Resale, Unbundled Loops and any products T&F orders are issued for when there is a move and there is a jeopardy situation.

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting.

Identify/Confirm CLEC’s Expectation

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) AT&T will meet internally meet determine what revisions are needed to the current CR or submit a new CR.

01/21/04 January CMP Meeting Ervin Rea with AT&T presented this CR and said when a CLEC submits a move order, Qwest creates two orders, an install and a disconnect. These two orders should be associated so that if something goes wrong with the install then the disconnect does not get worked. Ervin asked if the F order is worked first thing in the morning. Qiana Davis with Qwest said yes, Qwest works the disconnect order first. Ervin said that if the T is jeoped then AT&T wants to put the customer back in service. Qiana said that the F is worked to release the facilities. Ervin asked why the TN can’t be working in both locations. Qiana said that Qwest does offer Dual Service.

Bonnie Johnson with Eschelon said that she sent an e-mail concerning when a dispatch is required on T&F orders, a technician working on the T order that is jeoped and the F is worked in the switch. Bonnie’s concern is connected to this CR and her service manager had called about the question. Linda Sanchez-Steinke with Qwest said she did not understand that the question was related to the CR. Bonnie also said that Dual Service requires two different due dates (Begin comment from Bonnie Johnson – Eschelon) and that is not what we are asking for. Bonnie said that for example, if the ”F” side of the T&F is flow through the customers service would be disconnected at the old location after midnight on the due date because of the way Qwest service orders flow through the system (D’s and F’s or disconnects go first) and Qwest agreed. Then if the “T” side required a dispatch and the tech could not instal until 5PM on the due date, the customer could be out of service for serveral hours. (end comment). Jim Recker with Qwest asked if AT&T requests frame due time on their orders. Ervin said that the orders may not be designed services. Liz Balvin with MCI added that DFDT is desired, and is not guaranteed that disconnect will be completed at the desired time. Qiana asked AT&T to identify the products. Ervin said that the products are Resale, UNE-P, Unbundled Loops.

Qwest will arrange an additional clarification meeting for additional questions and the CR may need to be modified based on the clarification meeting output. Mike Zulevic with Covad said that when he worked on UNE-P orders if they resided in the same central office the same person did the work. If there was an F in another central office, the F was worked at midnight on the due date. Bonnie said there are two pieces to the CR; What should be done when the T order goes into jeopardy status and what needs to be done to relate the two orders. This CR will move to Presented status.

Wed 12/24/03 9:01 AM To: Sanchez Steinke, Linda From: Pardee, Carla D, NKLAM [cdickinson@att.com] cc: Rea, Ervin E, NKLAM Subject: RE: PC120803-1 Move Orders Associated Sorry for the delay in getting back to you Linda - been getting kicked off of my computer. I believe we agreed to change it to "Associated Move Orders." Thanks for taking care of this. Happy Holidays

From: Sanchez Steinke, Linda Sent: Tuesday, December 23, 2003 2:15 PM To: Pardee, Carla D, NKLAM Subject: PC120803-1 Move Orders Associated

Carla -

During the CMP meeting did AT&T agree to change the name of this CR to "Associated Move Orders" or something different than currently titled?

Would you let me know the title and I will change in the database.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

Tue 12/16/03 9:24 AM From; Johnson, Bonnie J. [bjjohnson@eschelon.com] To: Sanchez Steinke, Linda cc: Subject; Question for AT&T CR

Linda, Here is my question: As it relates to a T&F order, excluding a jeopardy on the "T" order, does Qwest always keep the "F" side of the order (customers service at the old location) working until the "T" side is installed. I would like the answer for tech dispatch and flow through orders that do not require a dispatch.

It was always my understanding that the Qwest tech had the "F" order worked (switch) after he installed the new line at the prem Can you confirm and tell me how it works when there is no tech?

I am asking the question because I hear the CLECs continue to talk about their customers being impacted and out of service with moves even if a jeopardy condition does not exist. Perhaps we could address both issues if there is one.

Thanks!

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

12/17/03 December CMP Meeting Ervin Rea with AT&T discussed this CR and said when a CLEC submits a move order, Qwest creates a T&F order. The T order is to install at the new location and the F order is to disconnect at the old location. If something happens to the T order, the F order completes. When the F order completes, then the CLEC has to scramble to get the service back up at one of the locations. AT&T would like the T & F orders linked so that if anything happens to the T order then the F order is jep’d at the same time. Carla thinks there are system implications and wants this addressed as soon as possible to identify. Connie Winston will work with the business to see how systems are effected. CLEC Change Request Clarification Meeting

8:30 a.m. (MDT) / Monday December 15, 2003

1-877-572-8687 3393947# PC120803-1 Move Orders Associated

Name/Company: Ann Adkisson, AT&T Patty Garnier, AT&T Carla Pardee, AT&T Colleen Forbes, AT&T Kim Isaccs, Eschelon Bonnie Johnson, Eschelon P.J. Koller, Priority One Telecommunications Shon Higer, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested (Description of) Change Linda Sanchez-Steinke with Qwest read the description of change from the submitted change request; When a CLEC submits a move order (M) Qwest creates two orders, a to (T) and from (F) order. The problem resides in the fact that these orders are not associated as related orders. It is an industry standard that related orders be associated in the RORD field in an effort to ensure that service is not interrupted. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is not electronic/mechanical means of associating the T order to the F order. Since these orders are not associated as RORD the F order is completed and the customer is taken out of service resulting in a disconnect in error.

Carla Pardee with AT&T & P.J. Koller with Priority One Telecommunications, discussed the products impacted would include; UNE-P, All POTS, Resale, Unbundled Loops and, any products where T&F orders are issued when there is a move and there is a jeopardy situation.

Bonnie Johnson with Eschelon had a question regarding jeopardy conditions, related to dispatch of technician on T & F orders. Bonnie will e-mail the question to Linda Sanchez-Steinke.

Confirm Areas & Products Impacted UNE-P, All POTS, Resale, Unbundled Loops and any products T&F orders are issued for when there is a move and there is a jeopardy situation.

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting.

Identify/Confirm CLEC’s Expectation Linda Sanchez-Steinke read the Expected Deliverable; Processes be changed to associate all T&F orders to each other. That systems be modified to ensure that if a related T order is jeopardized that the F order is automatically placed in a jep status and the work to disconnect the order is stopped. Expected result will reduce, if not eliminate, disconnects in error because of a jeopardized T order. In the month of November, AT&T had 10 disconnects in error because of jeopardized T orders. In the event the F order is completed before the T order on the due date and the T order is jepped, Qwest should immediately re-instate the service in an effort to prevent an out of service condition.

Identify any Dependent Systems Change Requests Carla Pardee said there may be a systems change request and she would check on any systems change requests issued.

Establish Action Plan (Resolution Time Frame) AT&T will walk on this CR at the December CMP Meeting. Qwest will provide a response in February.


CenturyLink Response

March 9, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the March 2004 CMP Meeting

Ann Adkisson AT&T

SUBJECT: Qwest’s Change Request Response - PC120803-1 Associated Move Orders

Description of request (partial): (Revised Description of Change 02-03-04) When a CLEC submits a move order (M) Qwest creates two orders, a (T) and from (F) order. The problem resides in the fact that these orders are associated with each other but no action is taken when the T order is placed in jeopardy and the F order is not stopped. Clarification calls with Qwest has indicated that the F order is "always" worked prior to the T order. This process is a guarantee that the customer will be taken out of service prior to the T order being completed regardless of jeopardy, and the jeopardy will cause the customer to be out of service for a longer period of time. When Qwest works the T order and the technician determines that the order cannot be completed as expected (either jeopardized for some reason or there is no access to the new site) there is no electronic/mechanical means of associating the T order to the F order.

Response: Qwest and CLECs acknowledge the long-standing process for outside moves is a two order process for all non-designed services (e.g., Resale and UNEP POTS) and some designed services (e.g., Unbundled Loops). For non-designed services, the association of the two orders is inherent within the process in that there is always a T order associated with an F order. Designed services utilize "critically related order" (e.g., CRO) entries to relate two orders, (e.g., N and D order types). These order and process designs are used for both Qwest Retail and Wholesale accounts and are an integral part of both Qwest systems and processes. To change these would require a complete redesign of multiple systems, internal processes/documentation and training at an extraneous cost to Qwest without real benefit. Instead, Qwest has reviewed and analyzed the existing process for outside moves and has summarized the processes and findings as follows.

T & F orders in the same central office with no change to the telephone numbers are automatically sequenced and the provisioning is coordinated in the Qwest systems for both dispatched and non dispatched orders. If the T & F are located in different wire centers with same day due date, sequencing does not occur and the F order is worked on due date after 12:01 A. M.

There are two basic reasons for "jeopardizing" the T & F orders; Qwest reasons or Customer reasons. When an order is jeopardized for Qwest reasons (e.g., CF - Qwest Facilities are not available), the T order is delayed until Qwest facilities become available. At the point Qwest determines the T order is going to be delayed, the customer of record is contacted to determine if the F order should continue through the process to disconnect the existing service. Qwest makes every attempt to contact the customer of record to determine the disposition of the "F" order. If the T portion of the order is CF'd (held for no facilities), and the customer of record is not contacted the F order will be put on hold until the customer of record is contacted.

The Designed service process generates various order types within Qwest and is dependent upon the product type. If a designed service order is jeopardized, Qwest will contact the customer to determine if the customer wants to continue forward with disconnect activity. The orders are critically related and are worked together.

Additionally, in response to Cheryl Peterson’s finding within the PortWithin process document (http://www.qwest.com/wholesale/downloads/2003/030513/DNLDPortWithinProcess1005-13-03.doc), which states "On a full conversion, Qwest will issue the disconnect of the trunks and facility at the old location, due one business day after the port order DD". This process acts as a product process guide specifically for the DID product.

Findings: In reviewing/analyzing the processes and associated examples, Qwest determined: - Qwest technicians, on rare occasions, were not adhering to the process of contacting the customer of record a jeopardy situation. - the "can be reached" information provided by the CLEC does not provide the technician with a "live person" with whom the technician can work the issue of the pending disconnect.

Conclusion: Qwest accepts this CMP CR and has identified the following activities to enable closure: - We are in the process of enhancing the CLEC documentation (PCAT) for T&F orders to reinforce the importance of supplying a can be reached number which allows Qwest to contact the customer of record. - We have issued a Communicator to selected Network groups to reinforce the process of contacting the customer in jeopardy situations to determine the disposition of the F orders (disconnect). - Qwest currently offers specific optional services to the CLECs that may remedy some of the unique requirements of some move activities, e.g., dual service, overlapping service, etc. Qwest’s PCAT(s) will be updated by 4/19/04 to provide CLECs with more detailed information about these options. - Qwest will continue to review its current processes and seek opportunities for improvement.

Sincerely,

Qiana Davis - Sr. Process Analyst, Wholesale Service and Delivery Jim Recker - Staff Advocate, Qwest

February 6, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the February 2004 CMP Meeting

Ann Adkisson AT&T

SUBJECT: Qwest’s Change Request Response - PC120803-1 Associated Move Orders

AT&T is requesting process and system changes related to T and F orders. "The problem resides in the fact that these orders are associated with each other but no action is taken when the T order is placed in jeopardy and the F order is not stopped".

On January 28, 2003, a second clarification meeting was held to review the description of the requested change. As a result of this meeting, AT&T decided to meet internally and amend the initial CMP CR to now include the exact change requested along with detailed scenarios.

On February 3, 2004, Qwest received the amended version of CMP CR PC-120803-1 and are currently evaluating the change request. Therefore, we require additional time to investigate and will provide a response at the March CMP meeting.

Sincerely,

Qiana M. Davis FTS Process Specialist


Open Product/Process CR PC112403-1 Detail

 
Title: Request for blocking feature for 411 and 555 1212
CR Number Current Status
Date
Area Impacted Products Impacted

PC112403-1 Withdrawn
10/17/2007
Resale, UNE-P
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Coyne, Mark
Director:
CR PM: Stecklein, Lynn

Description Of Change

AT&T is requesting a single USOC, territory wide, that will block 411 and 555-1212.


Status History

11/24/03 - CR Submitted

11/24/03 - CR Acknowledged

12/11/03 - Held Clarification call

12/17/03 - Clarification Minutes sent

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Presented

01/02/04 - AT&T requests that CR be expanded to include a block on reaching (O) Operators.

01-08-04 - Held second Clarification call

01-14-04 - Response posted

01-15-04 - Sent minutes

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Evaluation

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

2/18/04 - Status changed to Deferred


Project Meetings

10/17/07 Product/Process CMP Meeting

Mark Coyne-Qwest stated that Qwest contacted AT&T and they agreed to withdraw this CR. Bonnie Johnson-Eschelon asked for the description and status of this CR. Lynn Stecklein-Qwest stated that this CR is in a deferred status and is a request for a blocking feature for 411 and 555-1212. She said that AT&T completed testing and no longer needed this request. Bonnie Johnson-Eschelon stated that they would like to take a look to see if there is any interest in sponsoring this CR. She said that she may be thinking of another CR that was denied. Laurie Fredricksen-Integra stated that she could not find the CR on the agenda. Lynn Stecklein-Qwest stated that we just found out yesterday that AT&T wanted to withdraw so it is not in the package. She said that this discussion will be in the meeting minutes for their review

E-mail From AT&T

Hi Lynn, Sorry for the delay in responding to you.... it's taken awhile to find someone to provide input to this issue. Since it seems there is no longer support for this change and there is an existing solution, I would support withdrawing this CR. Thanks for your patience. Kathy

- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Monday, September 24, 2007 11:49 AM To: LEE, KATHY T, ATTCORP Cc: Esquibel-Reed, Peggy Subject: FW: PC112403-1 Request for blocking feature for 411 and 555-1212

Hi Kathy, The attached CR is currently in a deferred status. In January of 2006, AT&T stated that they were checking internally to determine if the testing with CustomNet Option 1 would satisfy the needs of this CR. (see below) Can you let me know if that testing is complete and if you want this CR to remain in a deferred status or if the testing met the needs of the request? If it has, we can place the CR in a Pending Withdrawal status for the October CMP Meeting. Thanks for your help in advance. Lynn Stecklein Qwest Wholesale CRPM

Lynn, I've finally found a person who is interested in this. We need to keep this open for now. We are checking on the testing. I'll try to get more status in a few days - after this specific person checks on the testing. Thanks. Sharon

- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Monday, January 23, 2006 10:09 AM To: Van Meter, Sharon K, NEO Subject: RE: PC112403-1 Request for blocking feature for 411 and 555-1212

Hi Sharon,

Have you heard anything on whether AT&T has completed their testing?

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

--Original Message-- From: Van Meter, Sharon K, NEO [mailto:svanmeter@att.com] Sent: Wednesday, November 02, 2005 11:26 AM To: Stecklein, Lynn Cc: Esquibel-Reed, Peggy Subject: RE: PC112403-1 Request for blocking feature for 411 and 555-1212

Lynn,

I'm checking internally - I'll let you know as soon as I hear something.

Sharon

E-mail send to AT&T 11/2/05

Hi Sharon,

We have been researching change requests that are currently in deferred status. The attached CR PC112403-1 (Request for blocking feature for 411 and 555-1212) is currently in deferred status. The project meeting minutes dated 2/18/04 states the following:

‘Carla Pardee, Qwest said that she is waiting for AT&T to conclude their testing with CustomNet Option 1 to see if this will satisfy the needs of this CR. She would like to move the Status to Deferred until AT&T completes testing.’

Can you let me know if AT&T has concluded the testing of the Customer Net Option 1? And, is so, does it meet your needs?

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

2/18/04 CMP Meeting Carla Pardee, Qwest said that she is waiting for AT&T to conclude their testing with CustomNet Option 1 to see if this will satisfy the needs of this CR. She would like to move the Status to Deferred until AT&T completes testing.

-- 1/21/04 January CMP Meeting Aaron Smith, Qwest stated a Clarification Call was held on January 8 and that Operator blocking had just been added to the CR at that time. On the call it was felt CustomNet option 1 might meet the requirements of the CR. Carla Pardee, AT&T said that AT&T had evaluated CustomNet before but wanted something simpler. AT&T is now re-evaluating. Bonnie Johnson, Eschelon stated Eschelon would submit a separate CR for a 411 block only. The CR will stay in Evaluation.

- Clarification Meeting 2:00 p.m. (MDT) / Thursday January 8, 2004 1-877-521-8688 1456160 PC 112403-1Request Blocking Feature for 411 and 5551212.

Attendees Carla Pardee, AT&T Dave Fane, AT&T Liz Balvin, MCI Kim Isaacs, Eschelon Patti Leo, Qwest Doug Andreen, Qwest Aaron Smith, Qwest Marty Cruze, Qwest Jo Wees, Qwest Carolyn Vance, Qwest Rose Bochnicek, Qwest John Gallegos, Qwest

Meeting Agenda: 1.0Introduction of Attendees

Introduction of participants on the conference call was made and the purpose of the call discussed.

2.0Review Requested (Description of) Change

Doug Andreen, Qwest read the CR description: AT&T is requesting a single USOC, territory wide, that will block 411 and 555-1212. And added that recently AT&T had requested to add blocking operator (O) calls which is why we wanted to have a second clarification call with a wider audience than the first.

Carla Pardee, AT&T added that the intent is to block long distance call completion on customers that have delinquent bills.

Dave Fane added that this is a customer by customer block for customers not paying their bills.

Carolyn Vance, Qwest asked if the object was not to complete the call.

Dave answered yes with the same messages that are normally used.

There was much discussion around appropriate blocks to 411, 555-1212, O+ and 0- calls with the following outcome. CustomNet option 1 will block will block 411and 555-1212. 0+ calls are routed to an operator for alternate billing but cannot be billed to the owner TN. This was acceptable to AT&T. O- calls are completed to an operator but the operator’s screen indicates that calls cannot be charged to the owner TN and that the call may not be transferred to DA. However, calling card calls will not be blocked. This would have to be blocked separately in LIDB as done today.

AT&T agreed to test option 1 CustomNet to see if it would fully meet their needs and to let Doug know.

Kim Isaacs, Eschelon expressed a desire to have this CR appended to for a 411 block only.

Doug advised in order to not confuse the testing of CustomNet option 1 by AT&T and a block for 411 only that a new CR should be submitted.

Kim will submit the new CR.

3.0Confirm Areas & Products Impacted UNE-P

4.0Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0Identify/Confirm CLEC’s Expectation AT&T will test CustomNet option 1 to see if it meets their requirements for this CR.

6.0Identify any Dependent Systems Change Requests None

7.0Establish Action Plan (Resolution Time Frame) An update on testing will be made to Doug and also at the January CMP meeting.

- 12/17/03 December CMP Meeting Carla Pardee, AT&T presented this CR asking for a territory wide USOC that gives the ability to block a customers ability to reach a 411 or 5551212 DA operator. Carla realizes that Custom Net and Toll Block Restriction provides several features but not a single USOC as described above. Bonnie Johnson, Eschelon supports the CR saying Eschelon has customers who need to block the ability to reach DA operators without interfering with long distance capabilities. The CR was moved to Presented status.

- CLEC Change Request Clarification Meeting 12:30 p.m. (MDT) / Thursday December 11, 2003 1-877-521-8688 1456160# PC 112403-1Request Blocking Feature for 411 and 5551212. Attendees: Name/Company: Carla Pardee, AT&T Yolanda Bennett, AT&T Doug Andreen, Qwest Mallory Paxton, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Doug read the CR description: AT&T is requesting a single USOC, territory wide, that will block 411 and 555-1212.

Carla Pardee, AT&T added that she realizes that Custom Net and Toll Blocking offers a variety of features but AT&T desires a single USOC that blocks 411 and 555-1212.

Mallory Paxton, Qwest asked Carla if they want this only to block these two features.

Carla said yes.

Mallory asked if this was an option in other RBOCS?

Yolanda answered that it was available but she was unsure if it was a single feature.

Doug asked if the purpose was to block customers who owed bills from making long distance calls?

Carla answered yes.

Confirm Areas & Products Impacted UNE-P

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation By February 2004, AT&T requests that Qwest implement a single USOC, Qwest territory wide, that will block 411 and 555-1212.

Identify any Dependent Systems Change Requests None

Establish Action Plan (Resolution Time Frame) Carla will present for AT&T at the December CMP meeting.


CenturyLink Response

January 8, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the January 2004 CMP Meeting

Carla Pardee LSAM Manager AT&T

SUBJECT: Qwest’s Change Request Response PC112403-1 Request for blocking feature for 411 and 555-1212

This letter is in response to AT&T’s Change Request (CR) PC112403-1. This CR requests that Qwest provide a single USOC territory wide to block access to DA operators using 411 and 555-1212. Recently, AT&T added to the original CR a request to also block access to Operator (O) calls using the same USOC.

Qwest is currently evaluating this request and proposes moving this Change Request into Evaluation Status while we continue to investigate. Qwest will provide an updated response at the February 2004 CMP meeting.

Sincerely,

Aaron Smith Manager Product Management


Open Product/Process CR PC030504-1 Detail

 
Title: Qwest Premise Visits for Wirechecks and Subsequent Billing to CLECs (AT&T Local)
CR Number Current Status
Date
Area Impacted Products Impacted

PC030504-1 Denied
6/16/2004
Billing, Maintenance & Repair UNE-P, all non-design products
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Gonzales, Mark
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

AT&T requests that Qwest implement a process to validate accurate billing for premise visits for wirechecks and subsequent maintenance issues by holding billing for 60 days preferably (30 days minimum) to ensure that a maintenance issue is properly billed. At the present, Qwest may dispatch a maintenance technician to an AT&T UNE-P end user premise and initially not discover a problem, but subsequently another dispatch is made which does reveal a Qwest issue. Qwest bills for the first premise visit, even though the billing should not have occurred as it was a Qwest issue, ultimately. AT&T simply requests that Qwest hold itself responsible for maintenance billing for 60 days to ensure appropriate and accurate billing to CLECs.

Expected Deliverable:

AT&T expectation is that Qwest deliver this 60 day process for validating maintenance bills no later than July 1, 2004.


Status History

03/05/04 - CR Submitted

03/09/04 - CR Acknowledged

03/15/04 - Held Clarification Call

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

06/16/04 June CMP Meeting Mark Gonzales with Qwest reviewed the denial response. Carla Pardee with AT&T said we are disappointed with the response. AT&T has learned that tickets are kept open 14 days prior to billing. Bonnie Johnson with Eschelon said that design services tickets are kept open 14 days, however, the non-design services tickets are not. Carla said AT&T is disappointed and will not escalate the CR. Liz Balvin with MCI asked if the Arizona ruling prevented the CR from being accepted. Mark Gonzales said that the systems changes and the resources required made it economically not feasible and Susie Bliss with Qwest said that without the system changes and the resources, it is not clear if the requirement would be met to bill within 30 days. Bonnie Johnson with Eschelon asked if AT&T revised the CR and asked to hold tickets two weeks, would the CR be denied. Mark Gonzales said Qwest would still deny the CR based on the cost for systems changes and resources. This CR will be moved to Denied status.

5/27/04 10:43 a.m. From: Pardee, Carla D, NEO [cdickinson@att.com] To: Sanchez Steinke, Linda Subject: RE: AT&T PC030504-1 Linda - I have been asked to push back on Qwest on this request. Since the phone numbers have been provided, the dates and times should be evident to Qwest. If this is not the case, please let me know. Thanks for your continued assistance on this one.

--Original Message-- From: Sanchez Steinke, Linda [mailto:Linda.SanchezSteinke@qwest.com] Sent: Wednesday, May 26, 2004 6:50 PM To: Pardee, Carla D, NEO Subject: FW: AT&T PC030504-1

Carla - Did you find the dates for these ticket examples.

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

05/19/04 May CMP Meeting Mark Gonzales with Qwest said that we are evaluating this CR and will have an update at the June meeting. This CR will be moved to Evaluation status.

5/7/04 1:08 p.m. From: Linda Sanchez-Steinke To: Carla, Pardee Subject: RE: AT&T PC030504-1 Carla - Would you be able to find out the dates and ticket numbers for these repairs?

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

5/4/04 11:50 a.m. From: Pardee, Carla D, NEO [cdickinson@att.com] To: Sanchez Steinke, Linda Subject: RE: AT&T PC030504-1

Linda - here are the examples from Grant. Sorry for the delay, he was using the wrong e-mail address. Thanks.

Date: 5/4/04 10:41 From: Brown, Benjamin G (Grant), CSPMG [bgbrown@att.com] To: Pardee, Carla D, NEO, Riplinger, Linda K, CMOPM Subject: RE: Qwest Maintenance Wirecheck 30-60 Day Hold - AT&T PC030504-1

Here is what I sent to Linda S.

--Original Message-- From: Brown, Benjamin G (Grant), CSPMG Sent: Wednesday, April 21, 2004 10:37 AM To: 'linda.sanchez-steinke@qwest.com' Subject: Examples for CR PC030504-1

Linda,

I was told to forward these examples supporting CR PC030504-1 to you.

480.836.8691 602.268.4706 480.946.0773

Grant Brown AT&T

5/3/04 4:19 p.m. From: Pardee, Carla D, NEO [cdickinson@att.com] To: Sanchez Steinke, Linda Linda - and I followed up with Linda Riplinger and she said that Grant had sent three examples to you, I will find out what is going on! Sorry for the delay.

From: Sanchez Steinke, Linda [mailto:Linda.SanchezSteinke@qwest.com] Sent: Monday, May 03, 2004 3:47 PM To: Pardee, Carla D, NEO Subject: RE: AT&T PC030504-1

Hi Carla - Welcome back from vacation! I just wanted to let you know that I did not receive examples-- at CMP when Grant presented, he said he would provide to Donna. When Donna was out, I left a voice mail for Bern Seigler on Friday and haven't heard back.

Let me know if you have anything.

Linda Sanchez-Steinke Qwest CRPM 303-382-5768

4/30/04 9:32p From: Osborne-Miller, Donna, NEO [dosborne@att.com] To: Linda Sanchez-Steinke @qwest.com Subject: Out of Office AutoReply: Examples PC030504-1 I will be out of the office beginning Monday, April 26, 2004, with an undetermined return date. In my abscence please contact Bern Seigler, 770-248-2127. Thank you, Donna

4/30/04 9:24 a.m. From: Linda Sanchez-Steinke To: 'dosborne@att.com' Subject: Examples PC030504-1 Hi Donna -

At the April CMP, Grant Brown said that he would provide you some examples, and I'm wondering if you received any. This was on the CR PC030504-1 "Qwest Premise Visits for Wirechecks and Subsequent Billing to CLECs (AT&T Local)".

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

04/21/04 April CMP Meeting Donna Osborne-Miller with AT&T presented this CR. Grant Brown with AT&T will forward examples to Donna and she will forward to Linda Sanchez-Steinke at Qwest.

Bonnie Johnson with Eschelon fully supports this CR and would like to add all non-design products to the scope of this CR. Bonnie added that design products have an effective process that holds the ticket for two weeks prior to billing. When CLECs go through the dispute process it takes time and resources and Eschelon has one person working full time on this. Many times there are multiple repair tickets and they end up being a Qwest repair problem in the end.

Mike Zulevic with Covad supports this CR and said that Covad has problems reconciling billing on line shared and line splitting products.

Liz Balvin with MCI said that recently a CR for MLT testing prior to service order completion on DSL was denied because it was economically not feasible. There is a 51% failure rate on those circuits. Liz added that she has requested more information on that denial and there are many failures after handing off circuits to the CLECs.

Jen Arnold with U S Link said she also supports this CR.

Kit Thomte with Qwest asked if there would be billing examples provided. Grant said that these would be TN’s. Qwest doesn’t provide the TN level detail and would need help to determine if these were billed. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

1:30 p.m. (MDT) / Monday March 15, 2004

1-877-572-8687 3393947# PC030504-1 Qwest Premise Visits for Wirechecks and Subsequent Billing to CLECs (AT&T Local)

Name/Company: Linda Riplinger, AT&T Carla Pardee, AT&T Bud Witte, Qwest Designed Services Alice Matthews – Qwest Wholesale Terri Kilker – Qwest Wholesale Shirley Tallman – Qwest Network Mark Gonzales – Qwest Network Alan Braegger – Qwest Designed Services Field Laura Baird – Qwest POTS Field Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested (Description of) Change Linda Sanchez-Steinke with Qwest read the description of change from the submitted change request; AT&T requests that Qwest implement a process to validate accurate billing for premise visits for wirechecks and subsequent maintenance issues by holding billing for 60 days preferably, (30 days minimum), to ensure that a maintenance issue is properly billed. At the present, Qwest may dispatch a maintenance technician to an AT&T UNE-P end user premise and initially not discover a problem, but subsequently another dispatch is made which does reveal a Qwest issue. Qwest bills for the first premise visit, even though the billing should not have occurred, as it was a Qwest issue, ultimately. AT&T simply requests that Qwest hold itself responsible for maintenance billing for 60 days to ensure appropriate and accurate billing to CLECs. Shirley Tallman with Qwest asked if wirechecks and premise visits were the same as TIC (Trouble Isolation Charges). Bud Witte with Qwest asked if these were maintenance of service charges. Linda Riplinger provided an example: a trouble ticket was issued for condensation on the wires and Qwest determines there isn’t condensation, but then there is a subsequent trouble ticket and trouble found on the Qwest side. Bud Witte explained the process on the designed services side is to delay billing 14 days and asked if billing was done on anything over 30 days. Alice Matthews with Qwest said that work over 30 days drops out and does not bill. AT&T said that other RBOCs are moving from 30 to 60 days and the 14 day billing delay would not be sufficient.

Confirm Areas & Products Impacted UNE-P POTS

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting.

Identify/Confirm CLEC’s Expectation Linda Sanchez-Steinke read the Expected Deliverable; AT&T expectation is that Qwest deliver this 60 day process for validating maintenance bills no later than July 1, 2004.

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) AT&T will present this CR at the April CMP Meeting. Qwest will provide a response in May.


CenturyLink Response

June 8, 2004

For Review by the CLEC Community and Discussion at the June 2004 CMP Meeting

Carla Pardee AT&T

SUBJECT: Change Request Response – PC030504-1 “Qwest Premise Visits for Wirechecks and Subsequent Billing to CLECs (AT&T Local)”

This letter is in response to AT&T’s Change Request PC030504-1. This CR requests that Qwest implement a process to validate accurate billing for premises visits for wirechecks and subsequent maintenance issues by holding billing for 60 days preferably, (30 days minimum), to ensure that a maintenance issue is properly billed.

An analysis was performed to determine the implementation costs of this CR including resources and systems. A total of 2000 billed tickets were used which represents all CLECs volume of billed tickets for one month. Currently Qwest does not have a work group to analyze non-design tickets once they have been closed by the technician. In order to analyze the tickets Qwest would be required to deploy a new dedicated work group to perform the work function at an estimated cost $351,878 annually. This change would also require System modifications estimated at $1,020,000.

In addition, the State of Arizona ordered in, Docket Number T00000A-97-0238, that Maintenance and Repair charges must be processed and billed in a timely manner. The Arizona Commission stated that Maintenance and Repair charges must appear on the bill within two bill cycles after the ticket close date. The ticket close date is the date the work was completed. To comply with Docket Number T00000A-97-0238, Maintenance and Repair tickets must be processed within 30 calendar days of the date the work was completed.

Qwest respectfully denies this change request because it is economically not feasible and because regulatory reasons prohibit the change as requested.

Sincerely,

Mark Gonzales Staff Advocate Qwest Communications

May 11, 2004

For Review by the CLEC Community and Discussion at the May 19, 2004 CMP Meeting

Carla Pardee AT&T

SUBJECT: Qwest’s Change Request Response - PC030504-1 "Qwest Premise Visits for Wirechecks and Subsequent Billing to CLECs (AT&T Local)"

This letter is in response to CLEC Change Request (CR) PC030504-1. This CR requests that Qwest implement a process to validate accurate billing for premise visits for wirechecks and subsequent maintenance issues by holding billing for 60 days preferably, (30 days minimum), to ensure that a maintenance issue is properly billed.

Qwest is currently evaluating this change request and propose moving this CR into Evaluation Status while a complete answer to the request is prepared.

Sincerely,

Mark Gonzales Staff Advocate Qwest


Open Product/Process CR PC051804-1 Detail

 
Title: Clear and Consist Error Message when Requested Service Address is not Within Qwest Territory/Service Area
CR Number Current Status
Date
Area Impacted Products Impacted

PC051804-1 Completed
8/18/2004
Pre-ordering UNE-P, Resale Products, UNE-L
Originator: Pardee, Carla
Originator Company Name: AT&T
Owner: Pent, Anne
Director:
CR PM: Andreen, Doug

Description Of Change

Currently Qwest provides multiple error messages when a requested service address is not within Qwest territory or service area. AT&T is requesting an interim process (M&P) be developed by Qwest which would advise Qwest agents to send one consistent and accurate error message when a potential end-user is not Qwest’s service area. AT&T requests an error message such as “Requested service address is outside Qwest’s territory “. This change request is being submitted as an interim process for Qwest to develop until a permanent process, as set forth in AT&T’s pending change requests SCR040204-01 and SCR040204-02 can be implemented.


Status History

05/18/04 - CR Submitted

05/20/04 - CR Acknowledged

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/4/04 - Qwest generated notice PROS.08.03.04.F.01939.C05_SX_Jeopardies

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

9/16/04 CMP Meeting Minutes Doug Andreen reported that a notice had been sent August 3, effective August 10 and requested the CR be moved to Completed Status. Donna Osborne-Miller said that Joyce Atwell had been doing some follow-up and Donna had not heard from her as yet. She requested that the CR stay open and that she would have the information to Doug by the end of the week. If AT&T has no objections it was agreed to close out of cycle. The CR will remain in Test until Donna gets back with Doug.

- 8/18/04 CMP Meeting Doug Andreen reported that a notice had been sent August 3, effective August 10 and requested the CR be moved to Test. The CR will be moved to Test.

-- 7/21/04 July CMP Meeting Anne Robberson, Qwest stated this CR will be accepted. Liz Balvin, MCI verified that the CR is requesting a clear message be sent to the CLECs if an address is not serviced by Qwest. Carla Pardee, AT&T said there is a real sense of urgency around this request and asked if there were any time frames for implementation. Donna Osborne-Miller, AT&T added that there is a Systems CR in the works for this and it was recommended that this issue also be addressed from the Process side because of the long timeline to implement the systems request. Jill Martain, Qwest said we would investigate the timeframe. The CR will be moved to Development.

Meeting Minutes CMP June Meeting Carla presented this CR as a walk-on last month. There were no further questions. The CR will move to Presented Status.

- Time/Date: Place: Conference Call-In No.: CR No.:CLEC Change Request Clarification Meeting 11:00 a.m. (MDT) Wednesday, May 26, 2004 1-877-521-8688 1456160# PC051804-1 Clear and Consist Error Message when Requested Service Address is not Within Qwest Territory/Service Area Attendees Kim Isaacs, Eschelon Carla Pardee, AT&T Phyllis Burt, AT&T John Daugherty, AT&T Peggy Esquibel-Reed, Qwest Communications Anne Robberson, Qwest Communications Shirley Tallman, Qwest Communications Doug Andreen, Qwest

Meeting Agenda:Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change

Doug Andreen, Qwest read the full description of the CR as follows: Currently Qwest provides multiple error messages when a requested service address is not within Qwest territory or service area. AT&T is requesting an interim process (M&P) be developed by Qwest which would advise Qwest agents to send one consistent and accurate error message when a potential end-user is not Qwest’s service area. AT&T requests an error message such as Requested service address is outside Qwest’s territory . This change request is being submitted as an interim process for Qwest to develop until a permanent process, as set forth in AT&T’s pending change requests SCR040204-01 and SCR040204-02 can be implemented.

Carla explained that the two SCRs have been initially denied but that there was some discussion at the May CMP meeting and Qwest is taking a second look.

Doug asked if we should modify this CR to reflect a permanent solution rather than an interim process since the two SCRs may be denied. After some discussion it was agreed not to modify the CR but keep in mind that any process designed here may be needed on a permanent rather than an interim basis.

Doug verified the product impacts as UNE-P only. Carla said that they might want to extend to Resale and Kim agreed. Doug will modify the CR to reflect Resale also.

Carla verified that they need this put in place as soon as possible and that the ASAP or no later than July 15 date specified on the CR was to indicate the urgency involved.

At this point the call was opened up to questions/clarifications from Qwest. Anne and Shirley had no questions at this time.

Doug explained the timeframes for next steps. This CR was a walk-on in the May CMP meeting. It will be formally presented by AT&T in the June meeting and the Qwest response would be due at the July meeting.

Phyllis asked why it would take so long to implement an M&P change. To her mind it should be easy to do.

Shirley explained that research needs to be done to determine when in Qwest processes it is determined that the address is out of area.

Anne asked if the address could also be an apartment complex that is owned by a different company. Carla answered yes, that this was part of the problem.

Shirley added that her sense is that at the time of order issuance that Qwest does not know if the address is one not serviced by Qwest and that this is discovered later on the order process. Anne added that it might not be till the order hits Network that the address if found to be out of area.

John added that those reasons were why AT&T was looking for a system solution to help identify an out of area address as early in the process as possible.

Phyllis asked if from a process perspective there was a way to shorten the timeframe.

Doug said he would look into this. However the timeframes were established following the CMP process. Also if the SCRs moved forward they would be votable candidates for the 17.0 release which would be released in April 2005. (After the meeting Peggy informed Doug that AT&T had asked that these CRs be Late Adders into the 16.0 Release and AT&T was then notified, by Qwest, that the CRs were looking to be denied. Peggy stated that if the CRs do in fact move forward, they will be eligible for the 17.0 vote).

Anne asked if AT&T could send some examples for her to look into. Phyllis said she would get examples to Carla who will forward to Doug for distribution at Qwest.

There were no further questions or discussion and the meeting was adjourned.

3.0Confirm Areas & Products Impacted JUNE and possible expansion to Resale

4.0Confirm Right Personnel Involved Yes

5.0Identify/Confirm CLEC’s Expectation Implemented ASAP or no late than July 15

6.0Identify any Dependent Systems Change Requests SCR040204-01 and SCR040204-02

7.0Establish Action Plan (Resolution Time Frame) AT&T will present the CR at the June CMP meeting with a response being in the July timeframe.


CenturyLink Response

July 13, 2004

For Review by CLEC Community and Discussion at July’s CMP Meeting.

Carla Pardee LSAM Manager AT&T

SUBJECT: Qwest’s Change Request Response - CR # PC051804-01 - Clear and Consist Error Message when Requested Service Address is not Within Qwest Territory/Service Area

This is in response to AT&T’s request for a clear and consistent message when an LSR is submitted with a service address not serviced within Qwest territory.

Qwest accepts this CR as requested. Qwest currently has reject reason codes that are being returned when this scenario is identified at service order creation. The Reject codes are 801 for IMA version 15.0 users and 901 for IMA versions 13.0 and 14.0. The process being addressed is when this scenario is identified after service order creation, during the provisioning process. Qwest will agree upon verbiage to use and implement the verbiage as a Comment/Remark into the existing Jeopardy notification process for Error conditions identified after an FOC has already been sent.

In summary, we are working on the process as described in this CR and will be giving an update in the July CMP meeting.

Sincerely,

Anne Robberson Sr. Process Analyst Qwest


Open Product/Process CR PC060204-1 Detail

 
Title: Tone on Line
CR Number Current Status
Date
Area Impacted Products Impacted

PC060204-1 Crossover
7/27/2009
Maintenance / Repair UNE, Transport (EUDIT), Loop, UNE-P, EEL (UNE-C)
Originator: Rea, Ervin
Originator Company Name: AT&T
Owner: Graham, Denny
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T requests the ability to request that the ability be given to request and receive "Tone on the Line" for maintenance issues in an effort to locate the correct pair in a Demarc.

Expected Deliverable:

When AT&T, or it's designated vendor, is trying to locate the correct pair to connect a customer from the Demarc to CPE they would request that a tone be placed on the line. The expected result of this action will reduce the number of requested vendor meets, the number of trouble tickets being issued to request a "Tag and Locate". By having Tone on Line a customer's vendor can better isolate any troubles that may occur from the Demarc to CPE and or inside wire. The expected result will be a savings in resources and cost by both the CLEC and Qwest.


Status History

06/02/04 - CR Submitted

06/02/04 - CR Acknowledged

6/7/04 - Contacted Ervin Rea - ATT on vacation until 6-14 - lwtc to set Clarification meeting for 6-15

6/15/04 - Held Clarification call

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/14/04 - Emailed response to ATT

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/10/04 - Posted resposne to database and sent response to CLEC

8/16/04 - August CMP meeting mintues will be posted to the database


Project Meetings

8/16/04 CMP Meeting Mintues Denny Graham – Qwest advised we are still reviewing the impacts from this CR. We have determined there are system impacts so we will cross this CR over to systems. Stephanie Prull – Eschelon asked what systems are impacted. Denny advised this is still under review, but CEMR and Mediacc are systems that have been identified at this point. This CR will cross over to systems. This CR will move to Closed Status.

July 21, 2004 CMP Monthly Meeting Notes: Denny Graham – Qwest reviewed the response and advised that Qwest is looking at the process and products impacted. Qwest will move this CR to Evaluation status. We will provide an updated status in August.

June 16, 2004 CMP Monthly Meeting notes: Kit Thomte – Qwest explained that we have had some difficulty with our conference bridge numbers. We have contacted our service provider and they are correcting the problem. Bonnie Johnson – Eschelon advised she understands it was a problem with the bridge, and not that it was posted incorrectly on the calendar. Cindy Macy – Qwest apologized for the confusion and explained that she contacted the originator of the CR to provide a different call in number, but did not think to contact any other CLECs. Bonnie advised that is okay as she understands the issue. Bonnie suggested in the future though, if CLECs are having trouble connecting to conference bridge numbers that they should page the Project Manager. The CLEC community agreed that would be a good solution.

Ervin Rea – ATT presented the CR. Ervin explained that 10% of their trouble tickets are to tag and locate a loop at the DMARC or NID. This CR is asking for the ability to request when needed an identification tone be placed on the line. This would allow the CLEC to locate the line that they need to provision or repair without Qwest having to send a truck out to tag the line. This should apply to UNE – Loop, UNE-P and EEL products. Bonnie Johnson – Eschelon advised that she would like to include all UNE-P including Resale products as Eschelon experiences this issue a lot also. Bonnie advised that all POTS orders are dropping to manual handling asking for a tag. Eschelon’s statistics for this issue are similar to ATT. Ervin Rea – ATT said he has forward SBCs ‘Tone on line’ process to Cindy Macy at Qwest. Ervin advised there is a system or center to contact to request the tone be placed on the line. We talked with Service Management and they advised that there is not a process available to the CLEC at this time. We know it is available to Qwest. John Berard – Covad advised it would be best to mechanize this type of activity and not have to call a center. This CR will move to Presented Status.

Clarification Call - PC060204-1 Tone on Line June 15, 2004 1:30 – 2:30 p.m.

In attendance: Ervin Rea – ATT Denny Graham – Qwest Cindy Macy – Qwest

Ervin Rea – ATT reviewed the CR. Ervin explained that 10-12% of the trouble tickets that ATT issues to Qwest requests that a technician goes out to tag and locate the cable pair. This CR requests that an identification tone is placed on the line so the ATT technician can locate the line themselves. This eliminates the need to have Qwest dispatch a truck to locate the DMARC/NID. Ervin said this should reduce the trouble ticket volume by 10-12 % and save resources. Ervin advised he has talked with the other CLECs and they also support this CR. This will reduce the cost that CLECs pay to Qwest for a truck roll. Ervin advised that he understands that Qwest provides this ability to Qwest technicians. Ervin advised he is not sure of the process, but a Central Office technician could put the tone on the line.

Cindy Macy – Qwest asked Ervin what products is he requesting this service on. Ervin advised it would be UNE – P non design mostly, EEL could apply which may be designed.

Cindy Macy – Qwest asked Ervin if they want this on all lines automatically or do they want to request it only when they are unable to locate the cable pair. Ervin advised this would only be requested if they could not locate it, not on all lines automatically. This would apply to both Provisioning and Repair.

Denny Graham – Qwest advised he understands what Ervin is requesting. He will have to investigate the current process. Denny advised he is not sure how the CLEC would request this to be done, and what time frames would be required.

Ervin Rea – ATT advised that Bell South has a process for Tone on Line. Ervin will send Cindy a copy of that process. Cindy will distribute to Denny to review.

Ervin Rea – ATT advised they checked with Service Management first and were told that this is not available today.

The group discussed the current process that to tag and locate a line in the first 10 days, there is no charge and it is requested on the LSR. This is done as a supplement to the LSR. There is a charge to tag and locate after the 10th day and this is requested on a repair ticket.

Cindy Macy – Qwest advised that we will review the request and provide a response at the July CMP meeting. Ervin will present the CR at the June CMP meeting.


CenturyLink Response

For Review by the CLEC Community and Discussion at the August 18, 2004 CMP Meeting

August 10, 2004

AT&T Ervin Rea Senior Specialist

SUBJECT: CR # PC060204-1

This letter is in response AT&T’s Change Request (CR) PC060204-1 Tone on Line. This CR requests that Qwest provide the ability to AT&T to request and receive “Tone on the Line” for maintenance issues in an effort to locate the correct pair in a Dmarc.

Qwest is crossing over this CR to a systems CR as the implementation of the Tone on the Line request will consist of updates to existing Qwest systems. Qwest will provide an updated response at the September CMP Systems meeting.

Sincerely,

Denny Graham Qwest Communications

For Review by the CLEC Community and Discussion at the July 21, 2004 CMP Meeting

July 21, 2004

AT&T Ervin Rea Senior Specialist

SUBJECT: CR # PC060204-1

This letter is in response AT&T’s Change Request (CR) PC060204-1 Tone on Line. This CR requests that Qwest provide the ability for the CLEC community to receive ‘Tone on the Line’ when requested for maintenance and provisioning issues. Providing ‘Tone on the Line’ helps to locate the correct pair in a Demarc.

Qwest would like to leave this CR in evaluation status. Qwest needs to look at the individual products and provisioning processes that are impacted by this request. Qwest will provide an updated response at the August CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Denny Graham Qwest Communications


Open Product/Process CR PC112603-1X Detail

 
Title: Qwest to identify and rate AT&T's Special Needs Customers for OS/DA assisted calls.
CR Number Current Status
Date
Area Impacted Products Impacted

PC112603-1X Completed
12/15/2004
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Trees, Anne
Director:
CR PM: Harlan, Cindy

Description Of Change

AT&T would like to invoke the use of the DI and SOE LSOG fields in order to provide OS/DA service to AT&T Special Needs customers. There are two fields that we believe may accomplish this: SOE and DI. The SOE identifies the type of service/equipment associated with the line in LIDB. The DI identifies for LIDB that the end user has a disability that requires special handling for OS/DA calls. We believe that these two fields will provide Qwest TOPS/OSPS centers the ability to recognize such a customer without the customer having to tell the operator of their disability and will rate the assisted call with DDD rates


Status History

Status History for Systems CR SCR112603-01

11/26/03 - CR submitted

11/26/03 - CR acknowledged

11/27/03 - Requested AT&T's availability for clarification call

12/8/03 - Clarification meeting held on 12/8/03

12/8/03 - Status changed to evaluation

12/17/03 - Discussed at the December Systems CMP Meeting - See Systems Distribution Package - Attachment B

2/11/04 - Draft Response Issued

12/11/04 - Interface changed to IMA Common

4/22/04 - LOE issued

4/28/04 - Status changed to Presented

5/29/04 - Discussed at the May CMP Systems Meeting - See Systems Distribution Package - Attachment I

7/2/04 - CR crossed over to Product and Process - PC112603-1X

7/14/04 - Sent email to ATT advising them of potential cross over

7/21/04 - PP CMP meeting minutes will be posted to the database

8/11/04 - Scheduled CLEC ad hoc meeting to review process on 8-200-4

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database

9/22/04 - PROD.09.22.04.F.02084.OperatorServicesV13 Effective November 6, 2004

10/20/04 - October CMP Meeting minutes will be posted to the database

11/17/04 - November CMP Meeting minutes will be posted to the database

1/4/05 - Sharon Van Meter - ATT gave an okay to close this CR


Project Meetings

December CMP Meeting Minutes Cindy Macy – Qwest advised that this CR was effective November 6. Qwest would like to change the status of this CR to Completed. Sharon Van Meter – ATT advised that she needs to verify this CR and she will contact Cindy Macy off-line to advise if it is okay to close.

11/17/04 November meeting minutes Cindy Macy – Qwest advised the PCAT was effective November 6. This CR will move to CLEC Test Status.

10/20/04 October meeting minutes Cindy Macy – Qwest advised the notification went out September 22 and the effective date is November 6. This CR will remain in Development Status.

9/15/04 CMP Meeting Minutes: Cindy Macy – Qwest provided status and advised that the documentation should be available next week for review and comment. This CR will remain in Development Status.

8/20/04 Ad hoc Meeting

Anne Trees - Qwest Elizabeth Hamilton - Qwest Donna Osborn Miller - ATT Cindy Macy - Qwest

Cindy introduced the team and advised the purpose of this call is to review the draft process and address Donna's question regarding mechanizing the solution. Anne and Elizabeth reviewed the process. Donna advised that she has talked with representatives who perform this function and they are okay with implementing the process as described in the Clarification Call notes and then if needed, later, issue another CR to request mechanization of the process. Donna explained they thought it would be cumbersome to fill out forms for multiple special needs customers. Donne asked if they had a large number of customers to set up, could it be done via a spreadsheet so they do not have to fill out 2000 forms. Elizabeth advised Donna that if this occurs we can discuss the best way to accomplish the large update. Elizabeth was open to a spreadsheet type of update. Potentially the accounts could be broken down between the Regions (Central, Western and Eastern) and that may help. If this is needed you should contact and work with your Service Manager first. Donna asked how soon do the updates occur. Anne and Elizabeth advised generally within a 48 hour time frame and this includes the receipt and turn around. Donna thanked the team for having the call and advised she is okay with the process.

8/16/04 CMP Meeting Mintues: Cindy Macy – Qwest advised that an ad hoc meeting is scheduled for Friday August 20 to review the process. Donna Osborne-Miller ATT asked for a systems person to be at the meeting as they would like to have the form mechanized. It is a labor intensive process to fill out the form and send it in manually. Cindy advised Qwest will try to invite a systems person, and will discuss this at the ad hoc meeting. This CR will remain in Development Status.

7/21/2004 CMP Meeting Minutes: Jill Martain – Qwest advised that this CR was crossed over from systems to product process this month. Anne Trees – Qwest advised that effective with the August CRIS release the DUF records will be rated. This is step 1 of the process. The screen codes will be updated at the operator station. The operator will know that the customer is a special needs customer. Qwest will handle and rate the call appropriately and pass the information to the DUF file. The PCAT and Operator Services Questionnaire will be updated. The target date for implementation is in September. Donna Osborne-Miller verified that the CLEC will have to identify the customer as special needs. Anne advised that the Directory Assistance Questionnaire is filled out by the CLEC and that is where the CLEC identifies which customers need this service. These questionnaires are forwarded to the operator services group, which enter the codes into their system, and that drives the correct handling of the call. Liz Balvin – MCI asked how long does Qwest anticipate for this process to take? Anne advised she would check on this and advise Cindy Macy. Cindy advised she will include this information in the notes. Anne provided the following update: The CLECs will only be filling out an attachment to the OS/DA Questionnaire to implement the Special Needs screening codes. They will fax the completed attachment directly to the OIS group. This is the same process they do today for other screen code updates. So the special needs screening code updates will follow the existing process. Once the complete and accurate attachment is received by the OIS group they will implement within a two business day timeframe. They will not need to complete the OS/DA questionnaire to add, change or delete screen codes including the Special Needs screen codes. This CR will move to Development status.

5/20/04 Systems CMP Meeting

Peggy Esquibel-Reed/Qwest stated that the LOE for this CR is 2350 to 2600 hours. This action item will be closed.

12/17/03 CMP Systems Meeting

Donna Osborne-Miller/AT&T stated that the clarification call was held and presented the CR. Donna said that AT&T would like the operator to stay on the line until the call is completed. Judy Schultz/Qwest said that we may have to split this CR into a System and Product/Process CR. Judy stated that the request to have the operator stay on line until the call is completed would most likely be a process change. Connie Winston stated that the interface needs to change from ‘other’ to IMA Common. Liz Balvin/MCI asked if ‘other’ interface is really the operator platform. Connie Winston/Qwest said that if we set this up it would be IMA. Donna Osborne-Miller/AT&T also want the DDD call rated. Connie Winston/Qwest stated the rate is based on the code given to us. Liz Balvin/MCI said that the rate would be populated on the order via IMA.

12/8/03 Clarification Meeting

Attendees: Donna Osborne-Miller - AT&T, Jo Ann Symenec - AT&T, Al Paris - AT&T, David Fane - AT&T, Kim Isaacs - Eschelon, Ann Trees - Qwest, John Gallegos - Qwest, Shonna Pasionek - Qwest, Connee Moffat

Review Description of Change AT&T is requesting that Qwest identify and rate AT&Ts Special Needs Customers for OS/DA assisted calls.

Discussion Donna Osborne-Miller - AT&T stated that they would like the Operator to stay on the line until the call is completed. Anne Trees - Qwest asked what kind of request is this associated with - IXC, Facility Based, UNE-P. Donna Osborne-Miller - AT&T said that it is UNE-P. John Gallegos/Qwest stated that Qwest understood this request and had no other questions.

Identify/Confirm CLECs Expectation AT&T would like to invoke the use of the DI and SOE LSOG fields in order to provide OS/DA service to AT&T Special Needs Customers.

Establish Action Plan AT&T will present this CR in the December CMP Systems Meeting.


CenturyLink Response

Final Response

April 22, 2004

RE: SCR112603-01 Qwest to identify and rate AT&T's Special Needs Customers for OS/DA assisted calls

Qwest has reviewed the information submitted as part of Change Request (SCR112603-01). Based upon the scope of this CR as agreed to in the Clarification Meeting (held December 8, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 2325 to 2600 hours for this IMA Change Request with no SATE impacts.

At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request.

This Change Request is an eligible candidate for the IMA 17.0 prioritization vote.

Sincerely, Qwest

DRAFT RESPONSE December 11, 2003 RE: SCR112603-01

Qwest has reviewed the information submitted as part of AT&T's Change Request SCR112603-01. Based upon research that has been conducted following the Clarification meetings (held November 18 and December 8, 2003) Qwest is still examining the issue. Qwest will continue to research the problem and provide an updated response at the March Systems CMP Meeting.

At the December Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received into further evaluation of this Change Request.

Sincerely, Qwest


Open Product/Process CR pc081904-1 Detail

 
Title: The capability for ATT to re MLT (Mechanize Loop Test) a TN during the open referral time.
CR Number Current Status
Date
Area Impacted Products Impacted

pc081904-1 Withdrawn
9/15/2004
maintenance repair UNE
Originator: Jones, Lucy
Originator Company Name: AT&T
Owner: Rehm, Peggy
Director:
CR PM: Harlan, Cindy

Description Of Change

This functionality will allow ATT to 'see' the condition of the line during the repair interval by Qwest. This will allow ATT to re-MLT a line if the customer calls in to close a ticket if they fixed the line themselves. We need to have the ability to MLT a line to prevent repeat trouble reports and cancel unnecessary dispatches, and validate the repair. Expected impact will be to reduce Qwest truck rolls and Qwest ACD time on manual calls.

Expected deliverable: Revised Process ATT desires the capability to re-MLT at during open referral time.


Status History

8/19/04 - CR Received

8/23/04 - CR Acknowledged

8//23/04 - Contact customer to discuss CR / verify phone number

8/26/04 - Held Clarification call

9/15/04 - September CMP Meeting minutes will be posted to the database


Project Meetings

9/15/04 CMP Meeting Minutes: Jill Martain – Qwest advised that during the Clarification call it was determined that this functionality already exists and ATT will remove the restriction in their system. This CR will be withdrawn.

Clarification Call PC081904-1 MLT a TN during the open referral time

Attendance: Joyce Atwell – ATT John Wright – ATT Justin Sewell - Qwest Communications Jim Recker - Qwest Communications Cindy Macy - Qwest Communications

Cindy Macy - Qwest Communications opened the call and reviewed the agenda. Cindy explained that Qwest has met internally on this CR before the Clarification Call and we believe that we already provide the functionality that ATT is requesting.

Joyce Atwell introduced John Wright and explained that he is the requestor of this functionality. John explained that ATT is blocking the ability to perform MLT with Qwest so he is not aware if this feature works or not. John will work with his lab organization to remove the restriction and then test the feature.

Justin advised that Qwest added this feature in the 2001 time frame. John advised that ATT wanted to make sure that Qwest is aware that ATT will begin using this feature. Justin advised it is okay to begin using the feature. ATT believes it will reduce the number of Qwest dispatches.

John advised it will take several weeks for ATT to remove the feature. The team agreed that this CR will be withdrawn at the September CMP meeting. After ATT removes the feature they will test the functionality. If they have any trouble at that time they would contact the Help Desk to report a trouble report. If ATT determines they need to issue another CR they will do that at a later date.


Open Product/Process CR PC101904-2 Detail

 
Title: To Modify Change Request Form to Include 'Impacts LSOG Forms'
CR Number Current Status
Date
Area Impacted Products Impacted

PC101904-2 Completed
4/2/2005
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Owen, Randy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

AT&T requests that Qwest include all of the LSOG forms and place these pieces of vital information in the Product Impacted section of the CR rather than focusing on a particular product. This will allow us to make better use of limited release resources by implementing common functionality at a broader level instead of only focusing on specific REQ Type and/or ACT types.

Expected Deliverables: To modify the existing CR form to include , Impacts LSOG Forms”.


Status History

10/19 CR Submitted

10/20 CR acknowledgement sent

10/28/04 Updated description per AT&T request

11/1/04 Held Clarification Call

11/17/04 - Discussed at the November Product Process CMP Monthly Meeting.

11/19/04-Held Meeting with AT&T (and CLECs) to discuss Qwest's approach for CR.

12/7/04 - Emailed Qwest Response to Sharon Van Meter, AT&T

12/15/04 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/05/05 - Ad Hoc Meeting Held

01/19/2005 - Discussed in the January Product Process Monthly CMP Meeting

02/10/05 - PROS.02.10.05.F.02545.Change_Request_Form [Comment Cycle 2/11 - 2/17]

02/16/2005 - Discussed in the February Product Process Monthly CMP Meeting

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting

04/20/2005 - Discussed in the Monthly Product/Process CMP Meeting

05/02/2005 - Status changed to Completed.


Project Meetings

May 2, 2005 E-mail from AT&T: Peggy, It's okay to close this CR. Thanks. Sharon

- April 26, 2005 Email Sent to AT&T: Hi Sharon, I hope you had a great vacation! Sharon, the CR that AT&T submitted, PC101904-2 To Modify Change Request Form to Include 'Impacts LSOG Forms' was implemented on March 3rd and was moved to CLEC Test at the March CMP Meeting. The new form has already been used to submit new CRs and is working great. Are you ready to close the CR? The meeting minutes from the April CMP Meeting are as follows: PC101904-2 To Modify Change Request Form to include ‘Impacts LSOG Forms’ Jill Martain-Qwest stated that this change was effective on March 3rd and is currently in CLEC Test. Jill stated that AT&T could not attend and Qwest would like to close this CR off-line with AT&T. There was no dissent to close the CR off-line. Please let me know if you are okay to close the CR. I appreciate it. Thanks, Peggy Esquibel-Reed Qwest Wholesale Change Management

-- April 20, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this change was effective on March 3rd and is currently in CLEC Test. Jill stated that AT&T could not attend and Qwest would like to close this CR off-line with AT&T. There was no dissent to close the CR off-line.

- March 16, 2005 Product Process CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that this was effective on March 3rd and that the CR submittal Form was revised and posted to the web site, and noted that the CMP Document was also updated with the update to Appendix D. Peggy stated that this CR moves to CLEC Test.

-- February 16, 2005 Product Process CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that the Level 2 notice was out on February 10th and that the effective date was March 3, 2005. This CR remains in Development status.

-- COMMUNICATOR EXCERPT: Announcement Date: February 10, 2005 Effective Date: March 03, 2005 Document Number: PROS.02.10.05.F.02545.ChangeRequestForm Notification Category: Process Notification Target Audience: CLECs, Resellers Subject: CMP - Change Request Form Level of Change: Level 2 Associated CR Number or System Release Number: CLEC CR # PC101904-2

Summary of Change: On February 10, 2005, Qwest will post planned updates to its Wholesale Change Management Process Change Request Form to include revised documentation. These will be posted to the Qwest Wholesale Document Review Site located at http://www.qwest.com/wholesale/cmp/review.html.

In response to the CLEC initiated CR PC101904-2, Qwest has updated the Wholesale Change Management Process Change Request Form to include additional LSOG information. In discussion during the January CMP monthly meeting, it was agreed that this Change Request would follow a Level 2 notification timeline. Upon becoming operational, in conjunction with the CR form update on the CMP operational URL, the sample Change Request form in Appendix D in the Change Management Process document will be updated to include this as the current CR example. This document is found at the following URL: http://www.qwest.com/wholesale/cmp/whatiscmp.html. This does not change the CMP process in any way; it is only an update to the sample form.

Current operational documentation for this business procedure is found on the Qwest Wholesale Web Site at this URL: http://www.qwest.com/wholesale/cmp/changerequest.html.

-- January 19, 2005 Product Process CMP Meeting Discussion Peggy Esquibel-Reed/Qwest stated that there was an ad-hoc meeting on January 5th for the final review of the proposed changes to the form and CLEC concurrence was obtained. Peggy stated that AT&T has requested that a shorter comment cycle be given for this CR in order for the form to be implemented sooner. Peggy asked for CLEC concurrence for a Level 2 notice, which is a 7-day comment cycle. There was no opposition to a Level 2 notice. Jill Martain-Qwest stated that the Level 2 notice would be sent and noted that the status remains as Development.

January 5, 2005 Ad Hoc Meeting Minutes: Date: January 5, 2005 CR No & Title: PC101904-2 To Modify Change Request Form to Include ‘Impacts LSOG Forms’ Introduction of Attendees: Phyllis Burt-AT&T, Chris Terrell-AT&T, Jeff Sonnier-Sprint, Bonnie Johnson-Eschelon, Amanda Silva-VCI, Jennifer Arnold-TDS Metrocom, Kim Isaacs-Eschelon, Peggy Esquibel Reed-Qwest, Hank Martinez-Qwest, Randy Owen-Qwest, Anne Robberson-Qwest Conference Call Discussion: Peggy Esquibel Reed-Qwest stated that the purpose of the call was for final review of the Draft version 14 of the CMP CR Submittal Form and to discuss a shorter comment cycle, per the request of AT&T. Peggy Esquibel Reed-Qwest stated that the form is the same that has been discussed in previous calls and the December CMP Meeting. Peggy stated that the additions to the form include new areas for Form/Transaction/Process Impacted (IMA Only) for Order, LSR Activity, Pre-Order, and Post Order. Peggy asked if all was any opposition to the new form, version 14. Phyllis Burt-AT&T stated that AT&T was okay with the form. Jennifer Arnold-TDS Metrocom stated that TDS Metrocom was also okay with the form. Peggy Esquibel Reed-Qwest asked if everyone else was okay with the implementation of version 14. There were no additional comments or questions. Peggy Esquibel Reed-Qwest stated that it seems that all are in agreement that Qwest is to proceed with version 14 of the form. Peggy Esquibel Reed-Qwest stated that at the December CMP Meeting, AT&T asked if there could be a shorter comment cycle so this form could be implemented sooner and used, as it will be very helpful to the CLECs and to Qwest. Peggy asked if there was any opposition to a Level 2 notice being sent for a shorter comment cycle. There was no opposition brought forward. Peggy Esquibel Reed-Qwest stated that Qwest would obtain final concurrence to the Level 2 notice at the January CMP Meeting, and then the notice would go out for the implementation of the form, version 14. There were no additional questions or comments.

-- December 15, 2004 Product/Process CMP Meeting Discussion: Connie Winston-Qwest stated that the more information that is known and is agreed upon, the better. Connie stated that specific product’s would still be called out. Sharon Van Meter-AT&T asked if the form that will be implemented is the same form that was provided for the conference call Connie Winston-Qwest responded yes. Jill Martain- Qwest stated that the field for 'all' products would not be incorporated. Jill stated that the 45-day notice would be sent and at the end of the comment cycle, the CR will move to CLEC Test. Sharon Van Meter-AT&T stated that maybe the comment period could be shorter as this new form will be very helpful. Jill Martain-Qwest asked if the CLECs would like another ad hoc meeting prior to the 45-day notice being sent. Sharon Van Meter-AT&T responded yes and noted that on the ad hoc call, she will ask if all are agreeable to a shorter comment cycle. Jill Martain-Qwest stated that this CR would move to Development Status.

December 6, 2004 Emailed Qwest Response to Sharon Van Meter, AT&T: Sharon, Attached is the Qwest Response to PC101904-2 To Modify Change Request Form to Include 'Impacts LSOG Forms'. Thank you, Peggy Esquibel-Reed Qwest CMP CRPM

-- November 19, 2004 Meeting Minutes: Attendees: Sharon Van Meter-AT&T, Stephanie Prull-Eschelon, Kathy Stichter-Eschelon, Sue Wright-XO, Chris Terrell-AT&T, Nancy Saunders-Comcast, John Berard-Covad, Bonnie Johnson-Eschelon, Phyllis Burt-AT&T, Hank Martinez-Qwest, Anne Robberson-Qwest, Judy DeRosier-Qwest, Peggy Esquibel Reed-Qwest

Peggy Esquibel Reed-Qwest stated that the purpose of the meeting was to review the DRAFT CR Submittal Form that was emailed to Sharon at AT&T, which is the mock-up of the revised CR Form. Peggy stated that Qwest wanted to review and obtain input to make that we were headed in the right direction for the delivery of this request. Peggy Esquibel Reed-Qwest read the CRs description for the call participants. Peggy stated that the current version of the CR submission form is located on the Wholesale web site if the participants would like to pull it up and compare to the draft mock-up as we discuss the suggested changes. Peggy Esquibel Reed-Qwest stated that the draft version 14 has no changes until page 2 of the form. Peggy stated that the proposed changes are under the Area Impacted section and is so that the CR originator can provide as much information as you can. Peggy stated that the new information was derived from the LSOG Forms and are categorized by Pre Order, Order, Post Order, and LSR Activity. Peggy stated that the information is optional, as is the current information in the Area Impacted Section. Peggy stated that the CR originator would indicate any boxes that would be applicable to the request. Peggy stated that the section is optional but noted that the more information that is provided to Qwest, the less chance for problems down the road as far as what the request covered. Peggy then asked the call participants to review the draft mock-up and provide feedback. Sharon Van Meter-AT&T asked if all the impacted forms were under the new categories. Hank Martinez-Qwest responded yes. Sharon Van Meter-AT&T asked that if in the Products Impacted Section of the form, if they check LNP, can the form provide a pop-up list of all the applicable forms for LNP. Hank Martinez-Qwest stated that it would then become a more interactive form. Judy DeRosier-Qwest stated that MSWord does have the capability to do drop down’s but can then only pick one-at-a-time; it would be more complicated if more than one Pre Order item is impacted. Sharon Van Meter-AT&T stated that she was just wondering and to leave the request as a paper form for this CR. Stephanie Prull-Eschelon asked if Cancel should be with Post Order. Hank Martinez-Qwest stated that it should appear with Order and will be corrected. Sharon Van Meter-AT&T asked that the check box named Other be explained. Stephanie Prull-Eschelon asked if it would be used if the CR originator was proposing a new form. Hank Martinez-Qwest said yes. CLEC Community stated to keep Other as a check box. Phyllis Burt-AT&T stated that she liked the draft form. John Berard-Covad stated that Liz (Balvin-Covad) had a suggestion for him to bring forward. John stated that Liz would like to see a check box for all forms below. Hank Martinez-Qwest stated that the designation of All has created problems in the past and that Qwest was moving away from the global designation of All. Hank stated that in the submission of a CR, there is thought and clarity that is needed so the request can be as complete as it can and not be subject to interpretation of ‘All’. John Berard-Covad asked if the forms listed in the draft CR form are the Industry forms. Hank Martinez-Qwest responded yes. Stephanie Prull-Eschelon asked if the originator can select only an order form or if needs to select a form and product(s). Hank Martinez-Qwest stated that the current process would not change of selecting the impacted areas, including the form and products. Stephanie Prull-Eschelon asked that if the End User form is selected and it has a potential to impact all products, can Qwest provide an LOE for the specified product and an LOE for all products that would be applicable for the End User Form. Hank Martinez-Qwest stated that this can be cumbersome but if that would be beneficial to the CLECs and to Qwest, Qwest can look into doing that. Bonnie Johnson-Eschelon stated that was the real intent of this CR. Hank Martinez-Qwest stated that the CR was driving to include the forms and not the products. Stephanie Prull-Eschelon stated that the CLECs want to provide Qwest with as much information as they can and would like an LOE for the specific product checked, and an LOE for all products that would be applicable for the specified form. Bonnie Johnson-Eschelon stated that in the Products part of the form, they want the option to check all products for the form, or to check the specific product(s). Hank Martinez-Qwest stated that we may all be speaking of the same thing and the question is how to display it on the form. Hank stated that for example, Port Service can be several forms and sub sets of products. Qwest needs to know if the request is for all in the subset or maybe just part of the subset. Hank stated that the Clarification Call helps drive that discussion. Stephanie Prull-Eschelon stated for example, in the Order section, the form can have a check box for all products and if that All box is not checked, Qwest would then know to look in the Products section. Hank Martinez-Qwest stated that it would be very helpful that if a form is selected in the Order Section, that a selection be made in the LSR Activity section. Stephanie Prull-Eschelon and Sharon Van Meter-AT&T stated that LSR Activity would be helpful. Hank Martinez-Qwest stated that the CR originator should populate the impacted form and the impacted products, to determine the scope of the CR. Bonnie Johnson-Eschelon stated that the CLECs want, in the impacted products sections, a check box for all products for the specified Form. Hank Martinez-Qwest stated that LSR Activity is also important. Bonnie Johnson-Eschelon stated that the CLECs do not want Qwest to reinvent the wheel but do want all products if there would be no substantial difference to the LOE. Bonnie stated that the CLECs need to get a clear understanding of what Qwest is doing. Bonnie Johnson-Eschelon stated that a check box for All may not be wanted for LSR Activity. Stephanie Prull-Eschelon stated that the all check box needs to be in the product list, not below Pre-Order, Order, Post Order, or LSR Activity. Sharon Van Meter-AT&T and Phyllis Burt-AT&T agreed. Stephanie Prull-Eschelon asked if Qwest only relates products to Order and maybe Pre-Order. Hank Martinez-Qwest stated for Order only. Hank stated that Pre Order and Post Order are product independent. Bonnie Johnson-Eschelon stated that in the Impacted Products sections, the All check box needs to clearly state that it applies to Order Forms only. Hank Martinez-Qwest asked if the CLECs Community likes the areas of Pre-Order, Order, Post Order, and LSR Activity. Stephanie Prull-Eschelon stated yes and noted that the check box for Cancel needed to be moved. Stephanie Prull-Eschelon stated that an All check box needs to be in the Product section. There were no other questions or comments. Peggy Esquibel Reed-Qwest stated that Qwest would consider the suggested changes and provide a response or status prior to the December CMP Meeting.

-- November 17, 2004 Product Process CMP Meeting Discussion: Sharon Van Meter – ATT presented the CR. Sharon reviewed the CR description and advised that ATT’s expected deliverable is to identify the specific LSOG forms on the CR form. Sharon advised there is a meeting on Friday to review the CR form. This CR will move to Presented Status.

Time/Date: Place: Conference Call-In No.: CR No.:CLEC Change Request Clarification Meeting

2:00 p.m. (MT) / Monday November 1, 2004

1-877-521-8688 1456160# PC101904-2 To Modify Change Request Form to include Impacts LSOG Forms Attendees Attended Conference Call Name/Company: Kim Isaacs, Eschelon Stephanie Prull, AT&T Phyllis Burt, AT&T Sharon Van Meter, AT&T Rosalin Davis, MCI Jim Recker, Qwest Randy Owen, Qwest Connie Winston, Qwest Cindy Macy, Qwest Doug Andreen, Qwest Title:

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change This was a combined clarification call for two AT&T CRs. PC101904-1 was covered first. Then Sharon Van Meter read and reviewed this CR. This CR requests that all of the LSOG forms be placed in the Product Impacted section of the CR rather than focusing on a particular product. Doug verified that what AT&T is requesting is that the LSOG forms be placed on the Change Request Form so the CLECs can fill out what forms are affected when submitting a request. Phyllis answered yes and that the CLECs hoped this would be helpful for Qwest to see the request at the form level. Stephanie Prull said this can be used as a limiting tool since for instance there are fifteen products on the Resale form. Randy Owen asked how that would have helped the TN SANO issue. Phyllis felt this was done piecemeal and that products kept getting added when it probably would have been easier to do all at once. Stephanie added that this is an attempt to give all the information at once and then determine (if the LOE is too high for instance) if we need to piecemeal. Phyllis asked if the LOE would be lower to implement all at once. Randy responded that in some cases yes but probably not always. It depends on the scope of the request and the release pattern and would have to be evaluated on a case by case basis. There were no further questions. 3.0 Confirm Areas & Products Impacted Potentially all products 4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0 Identify/Confirm CLEC’s Expectation To add LSOG forms to Change Request Form 6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) The CR will be presented at the November CMP meeting.


CenturyLink Response

December 3, 2004

RESPONSE For Review by CLEC Community and Discussion at the December 15, 2004, CMP Product/Process Meeting

Sharon Van Meter AT&T

SUBJECT: AT&T’s Change Request Response - CR #PC101904-2

This is in response to the AT&T submitted CR PC101904-2. This CR requests a Modification to the existing CMP CR submittal form to include the impacted LSOG forms.

A clarification call was held on 11/01/04 to discuss the request and a subsequent meeting was held on 11/19/04 with AT&T and members of the CLEC Community.

Qwest accepts this CR. Qwest will modify the CMP CR submittal form to include the impacted LSOG forms in four new areas of the CMP CR submittal form. The four new areas are categorized as Order, LSR Activity, Pre-Order, and Post-Order. The LSOG Form names will be listed under the appropriate category.

Qwest will provide a status update of the work to implement this CR at the December CMP meeting.

Sincerely,

Qwest


Open Product/Process CR PC101904-1 Detail

 
Title: Modify Release Commitment Deliverables
CR Number Current Status
Date
Area Impacted Products Impacted

PC101904-1 Denied
12/15/2004
Other systems include: IMA EDI GUI, Mediacc
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Owen, Randy
Director:
CR PM: Harlan, Cindy

Description Of Change

Section 5.2.3 (Design)of the CMP document states, “ Qwest engineers define the architectural and code changes required to complete the work associated with each candidate. The design work is completed on the candidates, which have been packaged. In 5.2.4 of the CMP document it states: Commitment- After design, Qwest will present a commitment list of CRs that can be implemented. Qwest will provide an updated LOE for each candidate and the estimated total capacity of the Release. These candidates become the committed candidates for the release. When Qwest presents the Release Commitment list at CMP, AT&T would like Qwest to also present a detailed summary of HOW the CR is going to be developed and delivered based on the design work completed on the candidates. By revealing this information, CLECs can obtain a better understanding of the scope and the limitation of the expected deliverable in order to make the necessary business decision based on the upcoming releases. It also gives Qwest and CLECs a final opportunity to make any additional comments/clarification s to eliminate any surprises at delivery.

Expected Deliverable:

Qwest will modify it’s commitment deliverables by communicating to the forum, exactly how systems change requests are going to be developed and delivered.


Status History

10/19/04 CR Received

10/21/04 CR Acknowledged

10/25/05 - Contacted ATT to schedule clarification call. ATT advised they may revised the CR description and we should wait to hold the clarification call until then.

11/1/04 - Held Clarification Meeting

11/17/04 - November CMP Meeting minutes will be posted to the database

12/7/04 - Qwest Response emailed to AT&T

1/6/05 - Sent email to ATT - At the last CMP meeting you asked Qwest to update the denial response to state that 'there is no Qwest demonstrable business benefit', as there is a benefit to the CLEC. Qwest does not believe that we need to add the statement to the denial reason as we do believe and understand if the CLEC issued the CR that the CLEC believes there is a benefit to them. We are also unable to change denial reasons as they are part of the CMP guidelines. I will add this email note to the project status section of the CR. ATT requested the information be added to the project that they believe there is benefit to ATT, but not Qwest.


Project Meetings

December CMP Meeting Minutes

Connie Winston – Qwest recapped that this request is asking for additional CR development information earlier in the process. Connie advised that we do not have additional information or clarity before the Release Walk Through. Qwest has made some assumptions in the past at the walkthrough meetings. Qwest will work to add more clarification and discuss assumptions at the walk through meetings. Jill Martain – Qwest added that we are now also reviewing the spreadsheet of products at the Clarification calls which helps Qwest obtain additional clarity. Jill advised we will be updating the CR form also per the CR request PC101904-2. Liz Balvin – Covad advised the CLECs are trying to avoid getting to far down the path and have CLECs expecting one thing and Qwest going another direction. Liz asked if Qwest has considered publishing a draft version of the Walkthrough document sooner. (Insert comment from Eschelon) Connie stated that Qwest doesn’t believe that providing draft version of the walk through would help the issue. (End comment) Connie advised that being more clear at the Clarification meetings will help Qwest and if we find that we need more clarification we will bring it to the CLEC Communities attention. For example, Qwest found an issue on the Parse and Structure CR and brought this to CMP to further define. Liz Balvin – Covad asked if Qwest is concerned about the CLECs bringing forth too many changes. Connie advised no. Qwest believes it would be a repeat of the Clarification call. Liz Balvin – Covad said at the clarification meeting CLECs only understand what they expect the changes need to be and it is not until Qwest publishes the draft specs that CLECs may identify issues. Connie agreed that is true and that is the 73-day time frame that Qwest provides. Connie said that Qwest doesn’t believe we are missing a lot of items and we need to be more stringent around bringing our assumptions forward. Sharon Van Meter – ATT would like us to change the denial to reflect ‘no demonstrable Qwest business benefit’ (insert comment from Eschelon) instead of no demonstrable benefit because the CLECs believe that there is a benefit to this CR. Jill said this CR will move to Denial Status.

December 7, 2004 Email Sent to Sharon Van Meter,AT&T: Sharon, I have attached a copy of the Qwest Response for your submitted CMP CR, PC101904-1 Modify Release Commitment Deliverables. The CR will be included in the Distribution Package for the December Product/Process Meeting, scheduled for December 15th. Thank you, Peggy Esquibel-Reed Qwest CMP CRPM

-- 11/17/04 November meeting minutes Sharon Van Meter – ATT presented the CR. Sharon reviewed the CR description and read sections 5.2.3 and 5.2.4 from the CMP Document. Sharon explained their expected deliverable is to have Qwest provide additional information up front instead of later in the process. Stephanie Prull – Eschelon explained that the LNP UBL TN/SANO issue is an example of what they are trying to improve with this process. Stephanie advised that if we would have received more information sooner and discussed this in more detail it would have helped us react earlier. This CR will move to Presented Status.

Clarification Call PC101904-1 Modify Release Commitment Deliverables November 1, 2004 2:00- 3:00 MT

In Attendance: Roslyn Davis – MCI Sharon VanMeter – ATT Phyllis Burt – ATT Kim Isaacs – Eschelon Cindy Macy – Qwest Doug Andreen – Qwest Connie Winston – Qwest Jim Recker – Qwest Randy Owen – Qwest Stephanie Prull - Eschelon

The purpose of this meeting is to review the CR and ensure Qwest understands the CLECs expectations.

Phyllis and Sharon – ATT reviewed the CR. ATT explained that they need something that helps the CLECs understand the scope and limitations of the CR more clearly and earlier on in the process. The Disclosure Document provides us with much of this information but it is needed earlier on in the process.

Eschelon provided the example of TN and SANO. When this was deployed they didn’t realize it was only for certain products. We need to understand the limitations, differences or exceptions.

Cindy Macy – Qwest asked what would help the CLECs understand this. Is it another meeting, or documentation, more information on edits? Sharon – ATT advised that maybe a meeting to review the documentation earlier in the cycle would help. Sharon – ATT advised that the CLEC Walkthrough doesn’t provide enough information.

Stephanie advised that we have special walkthrough on specific CRs if the CLECs feel like they need it. Ones that are more complicated generally. Maybe we should do this more often.

Randy Owen – Qwest asked if we are trying to build a process around exceptions. Stephanie Prull – Eschelon advised scope issues happen quite often.

Stephanie advised that today we get the information 45 days prior to implementation (final disclosure). The walkthrough is day 68-58 generally. Stephanie said that if we have only 2 releases a year maybe we could adjust the dates.

Randy Owen – Qwest advised he understands the CLECs request and we will review the issue. Cindy Macy – Qwest advised that this CR would be presented at the November CMP meeting by ATT. Qwest will provide a response at the December meeting.


CenturyLink Response

December 8, 2004

For Review by CLEC Community and Discussion at the December 2004 CMP Meeting

Sharon Van Meter AT&T

SUBJECT: Qwest’s Change Request Revised Response - PC101904-1 "Modify Release Commitment Deliverables"

This document is a response to AT&T’s PC101904-1 "Modify Release Commitment Deliverables."

AT&T requests that Qwest present at the CMP release commitment : "a detailed summary of HOW the CR is going to be developed and delivered based on the design work completed on the candidates. By revealing this information, CLECs can obtain a better understanding of the scope and the limitation of the expected deliverable. It also gives Qwest and CLECs a final opportunity to make any additional comments/clarifications to eliminate any surprises at delivery."

A clarification call was held on 11/01/04 to discuss the request. AT&T is requesting at the CMP Scope commitment a detailed analysis of the means and requirements of delivery. AT&T is asking for detailed requirements that Qwest provides as part of its IMA EDI Draft Disclosure publication and walkthrough. It should be noted that scope commitment occurs five weeks prior to Qwest publication of IMA EDI Draft Disclosure documentation, or 108 days prior to the release date. Initial Draft Disclosure documentation publication occurs 73 days prior to the implementation. Therefore, in effect, AT&T is requesting detailed documentation about the scope of changes for a candidate 35 days prior to current CMP commitments.

Qwest is already addressing some of the concerns brought forward by this CR. During the Clarification Calls on System CRs, Qwest now discusses more detailed information to identify and understand the specific product, activity type and request type. Qwest also is working on enhancing the CR form (via another CR,) which will allow for additional detail and specifications to be identified earlier in the process. The intent of these changes is to gather additional data earlier in the process and allow for a more detailed discussion of the change.

Currently, Qwest provides a complete a set of documentation at IMA EDI Draft Disclosure publication and the walkthrough. This should, however, be considered a Draft version. Changes do occur between publication of the Draft and the Final (at day 45). To provide the documentation any earlier than the Draft Disclosure point in the timeline would actually provide less value as many issues are addressed between scope commitment and publication of the Draft Disclosure. Qwest believes that the timeline of 73 days prior to release is the optimal point for publication of the documentation, providing for both a large window for the fielding of questions and concerns and a relatively stable set of documents. And, at this point in the timeline, Qwest believes that it publishes technical specifications that address both the business requirements (WHAT the candidate changes do) and the systems requirements (HOW Qwest will deliver it) for the candidate and the release.

AT&T also requested additional meetings to be held earlier in the process to discuss the CR. Qwest would not have additional information to provide to the CLECs earlier in the process and additional meetings would take time away from the resources working on the CR, thus delaying the progress and delivery of the Disclosure Documentation walkthrough.

When circumstances come about as a normal part of trial and testing during the release week, Qwest adheres to its standard process and protocols around notifying of the issue, and works quickly and with the CLECs to resolve it.

Therefore, Qwest is denying this request as providing no demonstrable business benefit.

Sincerely, Connie Winston Director, Information Technology, Qwest


Open Product/Process CR PC112904-1 Detail

 
Title: Rate Quotes and Number Referrals from Qwest Operator Services
CR Number Current Status
Date
Area Impacted Products Impacted

PC112904-1 Completed
7/20/2005
Operator Services
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Trees, Anne
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

AT&T requested, from our local Service Management Team, the current process for an AT&T Local Services customer to request a rate quote and/or number referral. This was the answer: I checked with our process and product folks on this, and at this point, Qwest is providing an "approximate" charge based on Qwest rates. If you would like to pursue having this process changed to either "quote the rates" or change our response to refer the customers back to their local telephone company for the OS Services (local card, operator), I'd recommend that you open this through the CMP Process.

AT&T is requesting that Qwest change its process to allow a CLEC to choose the response for quoting rates and/or referring an AT&T Local customer to the appropriate phone number. The response might include a rate quote provided by AT&T for its rates or a referral to an 800# provided by AT&T Local Services.


Status History

11/29/04 - CR Submitted

11/29/04 - AT&T Provided Clarification Call Availability

12/01/04 - CR Acknowledged

12/6/04 - Clarification Scheduled for December 14, 2004, based on CR originator's availability.

12/9/04 - Clarification Meeting Held. See Project Meetings Section for Meeting Minutes.

12/15/04 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/19/2005 - Discussed in the January Product Process Monthly CMP Meeting

02/16/2005 - Discussed in the February Product Process Monthly CMP Meeting

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting

04/19/2005 - PROS.04.19.05.F.02827.NewQuestionnairesV16 (Level 3)

04/19/2005 - PROD.04.19.05.F.02833.Operator_Services_V15 (Level 3)

04/20/2005 - Discussed in the Monthly Product/Process CMP Meeting

05/12/2005 - PROD.05.13.05.F.FNL_Operator_Services_V15 (Level 3)

05/18/2005 - Discussed in the Monthly Product Process CMP Meeting

05/19/2005 - PROS.05.19.05.F.02906.FNL_NewCustQuestionV16 (Level 3)

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

07/20/2005 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

July 20, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that this request was effective on June 8, 2005 and asked if the CR could be closed. Sharon Van Meter-AT&T said that the CR could be closed.

- June 15, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that this was effective on June 3, 2005 and would like to move to CLEC Test. This CR is now in CLEC Test.

May 18, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that the notices had been sent and that the proposed effective date is June 3, 2005. Sharon Van Meter-AT&T asked that once this is effective, if the Questionnaires needed to be updated before they could use this new process. Peggy Esquibel Reed-Qwest responded yes. This CR remains in Development status.

April 20, 2005 Product Process CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that notices were sent on April 19th for the PCAT changes, the OS Questionnaire and the New Customer Questionnaire and that the proposed effective date is on June 3rd. Peggy then noted that this CR would remain in Development status. Liz Balvin-Covad asked if they would be able to use them on the effective date. Peggy Esquibel Reed-Qwest stated yes.

-- March 22, 2005 Adhoc Meeting Attendees: Sharon Van Meter - AT&T, Carol Kearney - AT&T, Anne Trees - Qwest, Elizabeth Hamilton - Qwest, Marty Cruze - Qwest, Lynn Stecklein - Qwest

Lynn Stecklein - Qwest stated that a request was made by AT&T in the March CMP Meeting that Qwest schedule an adhoc meeting to discuss the proposed changes to the PCAT and the Questionnaire. Sharon Van Meter - AT&T provided the history of this CR for Carol Kearney (AT&T). Anne Trees - Qwest stated that the Qwest solution is that in most cases we will be able to provide a rate quote to the Customer. Carol Kearney - AT&T asked if Qwest considered the number referral. Anne Trees - Qwest said that we did not due to some limitations associated with the number referral. Carol Kearney - AT&T asked if Qwest will be able to identify the AT&T Customer. Anne Trees - Qwest said that we will be able to identify the Customer. Carol Kearney - AT&T asked if this feature will be available for all Customers or just AT&T Anne Trees - Qwest stated that this feature will be available for any CLEC. Carol Kearney - AT&T stated that AT&T Management has placed a freeze on rate increases. She asked what rate does the Operator quote if rates are not provided. Anne Trees - Qwest said that the rate quote defaults to the Qwest rate. Carol Kearney - AT&T said that she hopes the rates are close and said that she needs to go back to her Management Team to determine what rates AT&T will provide. Anne Trees - Qwest stated that if AT&T chooses not to provide rates, we will quote Qwest rates. Anne said that is up to AT&T but that the vehicle will be there. Anne said that the Customer will provide the rate information on the DA Questionnaire. Carol Kearney - AT&T asked if there was a charge for this feature. Anne Trees - Qwest said that there is no charge. Carol Kearney - AT&T asked how long would it take for Qwest to begin quoting the rates they provide. Elizabeth Hamilton - Qwest said that the turnaround time is approximately four weeks. Sharon Van Meter - AT&T said that Qwest only chose to quote the rates and asked if it might be possible to refer the Customer back to the 800 number. Anne Trees - Qwest stated that we did not pursue due to system limitations and that one percent of Customers ask for a rate quote. Anne said that rate quotes are available in Arizona, Colorado, Washington, Oregon, New Mexico, Idaho, and Utah. Anne said that this feature is not availble in Montana, Iowa, Nebraska, Minnesota, Wyoming and South Dakota. She said that the information will be provided by OCN and State. Anne also said that if the Customer's rates change, the Questionnaire needs to be updated. Anne asked if AT&T was Facility Based. Sharon Van Meter - AT&T said that she was not sure. Elizabeth Hamilton - Qwest stated that Facility Based and UNE are both treated by OCN and with the same rates. Sharon Van Meter - AT&T asked if there will be links letting them know where to find information for this feature. Elizabeth Hamilton - Qwest said yes. Sharon Van Meter - AT&T asked if Qwest could include which PCAT and where in the PCAT this information can be found. Anne Trees - Qwest said that the update will be in the Operator Services PCAT under Optional Features. Marty Cruze - Qwest asked if/when there are OSPS conversions does the PCAT need to be updated. Anne Trees - Qwest said yes and that we will be working towards getting the other States functional. Carol Kearney - AT&T asked when this feature will be functional. Anne Trees - Qwest said that we are currently working on getting the PCAT and Questionairre updated and should be functional by the end of April. Sharon Van Meter - AT&T asked what Level of Notification will be sent. Anne Trees - Qwest said that a Level 3 Notification will be sent. Sharon Van Meter - AT&T explained the comment cycle to Carol Kearney (AT&T). Carol Kearney - AT&T asked if this applies to DA rates and what does Qwest quote today. Anne Trees - Qwest said that the Questionnaire includes DA and that they can change the DA rate. Anne said that Qwest quotes the Qwest DA rate today. There were no other questions.

March 16, 2005 Product Process CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that Qwest was still working on the PCAT updates and the updates to the OS Questionnaire and that the CR remains in Development status. Sharon Van Meter-AT&T requested that another call be scheduled once the process has been determined and prior to the PCAT updates going into effect. Peggy Esquibel Reed-Qwest agreed to schedule the call with AT&T. This CR remains in Development Status.

- February 16, 2005 Product Process CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that we can provide the functionality in the Central and Western regions and will move forward in the updating of the PCAT and the OS/DA questionnaire, with the appropriate notices. Peggy stated that in the Eastern region, this is technically not possible due to the equipment in that region. This CR moves to Development status.

-- January 19, 2005 Discussed in the January Product Process Monthly CMP Meeting Peggy Esquibel-Reed/Qwest stated that the Clarification Meeting was held in December and that internal meetings are continuing in order to discuss this request. Peggy stated that Qwest would like to move this CR to Evaluation Status and that a status would be provided in the February CMP Meeting. Sharon Van Meter/AT&T asked if there was any status at all. Susie Bliss/Qwest stated that this request is looking expensive and noted that we are continuing to look at options. Susie stated that new technology would be needed for this request as it is very complex. Bonnie Johnson/Eschelon stated that she sees an economically not feasible denial coming. Jill Martain/Qwest stated that this CR moves to Evaluation Status.

-- December 15, 2004 Product/Process CMP Meeting Discussion: Sharon Van Meter-AT&T presented the CR and stated that the Clarification call had been held. Sharon stated that if the calling party asks for the rate to interrupt a line or to do a busy line verify, that Qwest may quote the rate or refer the caller to their local company. Sharon stated that Qwest has stated that the cost for a local collect call or for alternately billed calls cannot be provided. Jill Martain-Qwest asked if there were any questions or comments. Liz Balvin-Covad stated that she thought it was Qwest’s policy to refer the end user because Qwest can identify if is a CLEC customer. Sharon Van Meter-AT&T stated that if the CLEC is Facility Based, Qwest can identify if the caller is a non-Qwest customer. Sharon stated that they do not want Qwest rates quoted and that this process cannot be across the board, it needs to be each CLECs option. Susie Bliss-Qwest asked if this information was discussed at the Clarification call. Sharon Van Meter-AT&T stated yes.

December 9, 2004 Clarification Meeting Minutes Attendees: Sharon Van Meter-AT&T, Peggy Esquibel Reed-Qwest, Anne Trees-Qwest, Carolyn Vance-Qwest

Review Requested CR Description: Peggy Esquibel-Reed-Qwest reviewed the CR Title, Number, and Description. Peggy Esquibel-Reed-Qwest confirmed the Product impacted is Operator Services. Sharon Van Meter-AT&T stated that she issued the CR as a result of her Service Managers recommendation. Sharon asked what Qwest does when AT&T Local dials 0 and requests a rate quote for a local collect call, calling card call, busy line verify, interrupt a line, or if the operator completes the call. Anne Trees-Qwest stated that if an AT&T end user dials 0 and asks for the cost for the person that the call is being billed to, that person may not be an AT&T end user customer. Sharon Van Meter-AT&T stated that was correct. Anne Trees-Qwest stated that the originator is billed if the call is not alternately billed and Qwest normally quotes Qwest rates. Sharon Van Meter-AT&T stated that AT&T wants the operator to refer the person requesting the rate quote to their local company and to give the requestor the local provider telephone number; or for the operator to quote the local provider's rate. Sharon stated that the option needs to be the CLECs choice as some CLECs do want Qwest rates quoted. Anne Trees-Qwest asked if AT&T was re-rating the calls and noted that Qwest currently only quotes Qwest rates because Qwest only knows Qwest rates. Sharon Van Meter-AT&T stated that if the Qwest rate is $1.00 and AT&Ts rate is $1.50, the operator needs to say that the AT&T rate is $1.50. Anne Trees-Qwest asked to confirm that AT&T would then bill their end user at Qwest's rate. Sharon Van Meter-AT&T responded yes. Sharon stated that if AT&T wants Qwest to quote a rate, AT&T would bill whatever that quoted rate is. Anne Trees-Qwest asked to confirm that this request is for busy line verify or busy line interrupt and is not for alternately billed clls. Sharon Van Meter-AT&T stated that was correct. Sharon noted that if the request is for a rate quote to interrupt a line, Qwest should quote the AT&T rate and AT&T would bill the customer the amount of the quoted rate. Sharon stated that another solution would be that the Qwest operator could refer the caller to their local provider, or could refer the caller to the local provider's telephone number. Sharon stated that AT&T does not want Qwest rates quoted to the CLECs customer. Anne Trees-Qwest stated that Qwest does not maintain other companies rates and stated that this request is not for alternately billed calls. Anne again stated that this request would cover busy line verify or busy line interrupt, operator assisted calls. Anne stated that if the request is for the cost of a collect call, Qwest quotes Qwest rates. Sharon Van Meter-AT&T stated that that would be an alternaltely billed call and Qwest rates would be quoted. Sharon stated that all are in agreement. Sharon stated that she understands that the request is not for alternatley billed calls. Sharon Van Meter-AT&T asked if the Qwest operator can tell if the caller is an AT&T customer. Anne Trees-Qwest stated that the term AT&T customer is perplexing and stated that it could mean AT&T local customer, QPP, Facility Based with AT&T having their own switch. Anne stated that she needs to research to see if the operator can identify if the call is from an AT&T switch, if a reseller, or if UNE-P. Carolyn Vance-Qwest stated that if the call comes in from an ILEC or an IXC, we would know that the NPA NXX is not Qwest's. Carolyn stated that identification would also need to go down to the 10-digits and she does not know that an operator station can determine if the call is a CLEC call or can identify which CLEC. Anne Trees-Qwest stated that the request is dependant on if the NPA NXX owner can be identified. Anne stated that Qwest would do some research. Sharon Van Meter-AT&T asked if this request might be possible if Qwest can identify that the NPA NXX is not a Qwest customer. Anne Trees-Qwest stated that Qwest would discuss internally. There were no additional questions or comments. Peggy Esquibel-Reed-Qwest stated that Qwest would provide a status at the January CMP Meeting. The call was adjourned.

- December 6, 2004 Email Sent to AT&T: Sharon, I hope you had a great vacation. I have scheduled the Clarification Call for PC112904-1 Rate Quotes and Number Referrals from Qwest Operator Services. Call details are as follows: DATE: Tuesday, December 14, 2004 TIME: 9:00 am MT CALL IN: 1-877-564-8688, conference id of 8571927 Peggy Esquibel-Reed Qwest CMP CRPM


CenturyLink Response

Revised Response - February 16, 2005 This CR will be implemented for the Central and Western regions and will move forward in the updating of the PCAT and the OS/DA questionnaire. This CR will not be implemented in the Eastern region, due to technical limitations in the Eastern region equipment.

For Review by the CLEC Community and Discussion at the January 19, 2005 CMP Meeting

January 10, 2005

AT&T Sharon Van Meter

SUBJECT: CR # PC112904-1 Rate Quotes and Number Referrals from Qwest Operator Services

This letter is in response to AT&T’s Change Request (CR) PC112904-1 Rate Quotes and Number Referrals from Qwest Operator Services. This CR requests that Qwest change its process to allow CLECs to choose the response that Qwest Operators state when quoting charges to any other local service company customer. AT&T requests that this process be an option that each CLEC may choose or not choose to utilize.

Qwest would like to leave this CR in evaluation status as it needs to continue to look at the existing process. Qwest will provide an updated response at the February CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Anne Trees, Sr. Process Analyst Qwest Communications


Open Product/Process CR PC020705-1 Detail

 
Title: Buried Service Wire Process Change
CR Number Current Status
Date
Area Impacted Products Impacted

PC020705-1 Denied
7/20/2005
Provisioning NA
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Rehm, Peggy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

AT&T very rarely knows when Buried Service Wire is needed. When Qwest determines that the service is needed, Qwest needs confirmation that AT&T will pay for the Buried Service Wire fee. Today Qwest sometimes notifies AT&T via a jeopardy, on the due date, that Buried Service Wire is needed. Notifying AT&T on the due date is a big dis-satisfier for the AT&T customer as they are expecting the service to be delivered on the due date. Sometimes Qwest completes the service without notifying AT&T that the service is needed – which is a good thing for the customer. AT&T is looking for Qwest to develop a process to notify CLECs, on the customer due date, that Buried Service Wire is needed and allow the CLEC to accept the charges while the technician is still on the customer’s site.

Expected Deliverable:

AT&T expects Qwest to develop and implement a process for CLECs to accept the Buried Service Wire fee while the outside technician is still at the customer premises.


Status History

02/07/2005 - CR Submitted

02/08/2005 - CR Acknowledged

02/09/2005 - Clarification Meeting Scheduled for February 14, 2005.

02/16/2005 - Discussed in the February Product Process Monthly CMP Meeting, as a walk-on request.

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting

04/20/2005 - Discussed in the Monthly Product/Process CMP Meeting

05/18/2005 - Discussed in the Monthly Product Process CMP Meeting

05/24/2005 - CMPR.05.24.05.F.02951.BuriedSvcWire_AdHocMtg (scheduled for June 1st)

06/01/2005 - Ad Hoc Meeting Held

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

07/20/2005 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

July 20, 2005 Monthly Product Process CMP Meeting discussion: Chris Viveros-Qwest advised that Qwest investigated this CR and found that there would be multiple processes to put in place. He said that there is a low volume so it is not economically feasible to work this request. Sharon Van Meter-AT&T said that she is very disappointed with the denial. Sharon asked what they are supposed to do if they have a problem with the process. She asked if they are supposed to work with their Service Managers and said that they need a clear direction for the future. Chris Viveros-Qwest stated that the CLECs should work with their Service Managers and that we will make sure that process will happen. Sharon Van Meter-AT&T said that when this issue was talked about in the adhoc meetings the only problem was the authorization for payment. She said that they wanted Qwest to call for authorization and then was told that wasn’t the problem. She said that then they talked about the fact that it takes too many resources to reschedule the process and that they needed to work with their Service Managers and escalate if appropriate. Chris Viveros-Qwest said that he was not clear regarding the gaps in the current process. Laurie Frederickson-Integra asked if the Engineer is contacted to get an estimate. Chris Viveros-Qwest said that the existing process is to schedule an Engineer to go look at the work that needs to be done and then provide the estimate. Bonnie Johnson-Eschelon asked if there was any room for improvement in the process because AT&T is struggling. She said that maybe the documentation needs to be looked at. Sharon Van Meter-AT&T said that this doesn’t always happen and that it may just be a training issue or a documentation issue. She said that she will go back and talk with her people. Bonnie Johnson-Eschelon asked if a jeopardy happens on the due date, doesn’t Qwest call the CLEC, and why couldn’t this happen during the call. Chris Viveros-Qwest advised that originally we thought we were just talking about authorization but that wasn’t the case. He said it is also about displacing the jeopardy process which is currently used for gaining authorization for payment, doing the work, billing and rescheduling the work. Sharon Van Meter-AT&T said that this is an administrative issue and they don’t have any way to reschedule. Laurie Frederickson-Integra asked if this was for buried or aerial. Chris Viveros-Qwest said that this is specific to buried Laurie Frederickson-Integra said that on aerial the tester will call on the due date and that they will do it on that day. Sharon Van Meter-AT&T said that the subsequent order to bury can’t happen because the customer order would be completed. Laurie Frederickson-Integra said that the jeop is not completed. Jill Martain-Qwest stated that this CR will be closed in denied status and if the CLECs run into any problems with this issue, they need to contact their Service Manager. Sharon Van Meter-AT&T said that she would like it on record that if the Service Manager requests that they submit a CR, she will not be happy.

-- June 15, 2005 Monthly Product Process CMP Meeting discussion: Jim Recker-Qwest stated that an ad hoc meeting had been held with the CLEC Community and that Qwest had asked for examples and information to help understand the volume. Jim stated that Qwest needs the data in order to identify the volume of orders that require Buried Service Wire. Jim noted that AT&T is looking for data. Sharon Van Meter-AT&T stated that information was sent to Qwest on June 8th and noted that examples had been previously provided. Sharon stated that historically, the volume for AT&T could be 4-6 per month. Sharon stated that the average is about 2 per month. Sharon stated that her June 8th email also asked if Qwest could complete the work but keep the order open until the subsequent work is performed. Jim Recker-Qwest stated that Qwest continues to discuss internally in order to identify a solution for this request. Jim stated that Qwest Retail also uses the existing process for Buried Service Wire. Jim stated that this CR remains in Evaluation status for further analysis. Sharon Van Meter-AT&T stated that if Qwest cannot accommodate to call AT&T when the technician is at the premise and needs to reschedule, then AT&T requests that the process be simplified. Sharon stated that the scheduling of the subsequent work should be simpler. Jim Recker-Qwest stated that Qwest is looking at the current process and stated that a viable solution would also be helpful to Qwest. Jim stated that Qwest is working diligently to see what can be done. [Comment received from Eschelon: Jim stated that Qwest is working diligently to see what can be done but Qwest can’t get to the meat of how to do this]. Jim noted that Qwest understands AT&Ts problem and is looking to see if can a viable solution can be determined. Jim stated that a status would be provided in the July CMP Meeting. Jill Martain-Qwest stated that this CR remains in Evaluation status.

June 8, 2005 Email Received from AT&T: Peggy, AT&T would like Qwest to proceed with a solution for CR #PC020705-1. AT&T agrees that for the month of April 2005, there were no Buried Service Wire issues. However, historically, AT&T experiences an average of two Buried Service Wire issues a month. It is a big dissatifier for AT&T's customer when service is not provided on the expected due date for any reason, including Buried Service Wire issues. On the ad hoc call held last week, Qwest stated that costly internal process changes need to be made to satisfy AT&T's expectations for the CR. My understanding is that Qwest doesn't have any way to track the billing of the Buried Service Wire cost or the subsequent dispatch of the technician to complete the Buried Service Wire process once the original service order is completed. Is there some way to complete the work on the due date, hold the original order open until the subsequent work is completed and then complete the original order? When a due date is missed due to a Buried Service Wire issue, another dissatifier is rescheduling the due date for completion of the service. As Qwest considers a solution to the CR, please consider streamlining the process for rescheduling the original due date completion. Sharon Van Meter AT&T Western Region LSAM

June 1, 2005 Ad Hoc Meeting ATTENDEES: Sharon Van Meter-AT&T, Kim Isaacs-Eschelon, Rosalin Davis-MCI, Liz Balvin-Covad, Jim Recker-Qwest, Shirley Tallman-Qwest, Russ Urevig-Qwest, Alan Braegger, Lydell Peterson-Qwest, Laura Baird-Qwest, Chris Viveros-Qwest, Chris Quinn Struck-Qwest, Peggy Esquibel Reed-Qwest MEETING DISCUSSION: Peggy Esquibel Reed-Qwest stated that this call was scheduled at the request of AT&T. Chris Viveros-Qwest reviewed the CR and provided a high level background of what has occurred with this request and stated that he would like to better understand the driver of this request and discuss how the current process satisfies part of the request. Chris stated that we would like to gather any additional data that could help in determining a solution. Chris then asked Sharon Van Meter (AT&T) if the driver of the request is to eliminate delays in providing the end user service when there is a need for a buried service wire on the due date. Sharon Van Meter-AT&T said yes. Chris Viveros-Qwest stated that the difficulty has been that the scenario was talked about at the highest level. Chris stated that sometimes the technician can temporize the drop and the customer gets service, and sometimes there is a wait for a technician. Chris stated that this is a case of a new drop vs. reinforcing a drop. Chris stated that when a technician goes out on the due date and sees that a new drop is needed and needs to be buried, the technician will temporize a drop, as long as it can safely be dropped and does not lie across a driveway. Sharon Van Meter-AT&T asked to confirm that a new drop would be placed at the location as long as it is not unsafe. Chris Viveros-Qwest said yes and that it is at no charge. Chris stated that in this scenario, there is no issue in regard to payment authorization. Chris stated that the delay is when there is a need to place another drop or when reinforcing the existing drop. The current process is a resulting jeopardy and referral to an engineer. Chris stated that this could mean a site visit in order to determine if the current threshold has been exceeded. If it has been, Qwest would need authorization from the customer. Chris stated that this means that the service is not completed and in jeopardy status, and is referred for the drop to be buried. The order is then scheduled for the drop and the order gets completed. Sharon Van Meter-AT&T asked if the current service would remain but an additional drop would be needed. Chris Viveros-Qwest stated yes and the customer would have more than 1 line. Sharon Van Meter-AT&T asked if the engineer would look to get authorization for the drop. Chris Viveros-Qwest stated that the engineer needs to determine the estimated cost and if the cost is within the state specific threshold, Qwest would place the drop with no additional charge. If there is a cost, Qwest would bill as authorized. Chris stated that we need to come up with a way to get the work done and noted that the authorization of charges is not the real issue. Chris stated that we need to focus on what part of the current process needs to be changed and Qwest believes that a process change to get customer service on the due date would be a significant change. Chris stated that a new process would need to be developed to get the work completed. Chris then stated that we would need to consider the volume, benefit, and cost. Chris stated that Qwest analyzed April data and found no jeopardies due to this reason. Sharon Van Meter-AT&T stated that she was not involved in this issue in April or May. Chris Viveros-Qwest stated that a piece of this request is cared for in the existing process and that the rest would require significant changes and Qwest does not see the volume. Sharon Van Meter-AT&T stated that she agreed that AT&T did not provide all the facts and that this started with getting the technician authorization of charges. Chris Viveros-Qwest stated that the current process does not have the technician putting in additional drops, in this scenario. Chris stated that a new process would be needed to instruct the technician to do a new drop. Chris stated that this is service order driven, the service order would be in jeopardy, a referral would be needed to the technician, an estimate would need to be determined, the estimate would need to be given to the customer, billing would need to occur, and then the drop could be scheduled. Chris stated that to provide the customer service, there is no current process to get the drop buried. Chris then stated that the new process would not be driven by the original service order. Sharon Van Meter-AT&T asked if this would be an internal process to Qwest and the CLECs would not be involved because authorization was already given. Chris Viveros-Qwest stated that we would still have the same interface points and stated that if there was a charge, Qwest would expected the CLEC to pay the charge. Chris then stated that replacing the service order driven process with a new process is never easy or inexpensive. Chris stated that Qwest is struggling with justifying taking this work on when the volume or frequency does not support it. Sharon Van Meter-AT&T stated that she agreed that it is not frequent but noted that when it does happen, it causes AT&T a lot of grief and is a big dissatisfier. Chris Viveros-Qwest stated that Qwest Retail is also unhappy when this occurs. Sharon Van Meter-AT&T stated that she needs to check with her internal customer to discuss and stated that they would probably want Qwest to proceed with this request. Sharon said that she would see if this request should be pursued. Chris Viveros-Qwest stated that was fair. Sharon Van Meter-AT&T asked if any other CLECs were having problems. Liz Balvin-Covad asked Sharon what would be pursued if there was already an existing process. Sharon Van Meter-AT&T stated that when the installer finds no room on the pair, the order is placed in jeopardy status on the due date and authorization is needed for Qwest to lay another drop. Chris Viveros-Qwest clarified that when there is a need for an additional drop, the customer does not get the service, evaluation needs to be done, the buried service wire needs to be scheduled, and then the service to the customer needs to be rescheduled. Chris stated that a new drop would be placed, as long as it was safe, the customer would get service, and there would be an immediate referral to get the temporary drop buried. Liz Balvin-Covad asked if the new process was to make this happen on the due date and not jeopardize the order. Chris Viveros-Qwest said that was the request from AT&T and where Qwest is struggling to come up with a justification. Liz Balvin-Covad asked if on the due date is where the current process does not accommodate. Chris Viveros-Qwest stated that the issue is the delay in getting the end user service (Retail & Wholesale). Liz Balvin-Covad asked if this was only when a new drop is required. Chris Viveros-Qwest said when Qwest knows up-front there is already a process in place. Sharon Van Meter-AT&T stated that they will probably go forward with the request but needs to go back internally and give them the information that was provided on this call. Chris Viveros-Qwest stated that if AT&Ts decision is to proceed with the request, Qwest needs AT&T to identify the frequency because Qwest cannot find where this problem has occurred so it must be infrequent. Liz Balvin-Covad stated that this would benefit Retail as well because it would eliminate a 2nd dispatch. Chris Viveros-Qwest stated that the drop would be place, if it was safe to do so, and would still need to be buried. Chris stated that it would help to see if the benefit outweighs the cost. Sharon Van Meter-AT&T asked if there was another alternative to meet the customers due date. Chris Viveros-Qwest stated that we could not determine another solution. Shirley Tallman-Qwest stated any alteration to the current process would mean a change to that process and would be very expensive. Chris Viveros-Qwest stated that the driver is that we rely on the service order to get activities done and if the service order is completed, we no longer have the driver. Liz Balvin-Covad asked why there would be additional cost and asked if this could result in a 3rd dispatch. Liz stated that if we can get the service up and all were happy, it should mean 1 less dispatch. Liz stated that this would be positive for Wholesale and for Retail. Chris Viveros-Qwest stated that the additional cost is to provide service on the due date when a temporary drop is needed. To then bury the drop is additional cost for Retail and for Wholesale. Chris stated that each step up to the buried drop is triggered from the original service order. Liz Balvin-Covad asked that if the service order completion was rescheduled and the drop was then buried at that time, if there would there be additional cost in that scenario. Sharon Van Meter-AT&T stated that the service order is prompting Qwest to go to the location, and once the temporary drop is placed, the service order is completed and then there is no driver to get the drop buried. Chris Viveros-Qwest stated that to get the drop buried, there are additional steps that are needed. Liz Balvin-Covad asked if the additional cost is for the process to accommodate the trigger that gets the drop buried. Chris Viveros-Qwest stated that the additional cost is to find an alternate path for having the triggers occur and have an established process with the service order driving the steps. Liz Balvin-Covad stated that she did understand. Jim Recker-Qwest stated that the state tariffs drive the charges. Chris Viveros-Qwest stated that there could be instances where additional drops would result in charges. Sharon Van Meter-AT&T stated that AT&T is willing to accept charges to get the drops buried and thought the issue was regarding payment of the charges. Chris Viveros-Qwest stated there was that focus and that the first roadblock was authorization of payment, and then Qwest looked deeper into the process. Liz Balvin-Covad asked if Qwest did not charge for the first visit. Chris Viveros-Qwest said that was correct. Liz Balvin-Covad stated that she thought there was a double dispatch fee. Chris Viveros-Qwest said there was not. Sharon Van Meter-AT&T asked if they could issue a follow-up order to get the drop buried, so Qwest could do the work without messing-up the back-end systems. Chris Viveros-Qwest stated that he did not know if that would be viable and that timing could be an issue because he would wonder if the follow-up order could be executed in time to allow the technician to completed the work without leaving the premise. Liz Balvin-Covad stated that completing the service order would start the billing process. Chris Viveros-Qwest stated that if the process is changed to not put the order in jeopardy status, the service order would complete and then there is no way to bill for the buried service wire. Chris stated that a separate bill would be needed to bill for it and a process for curbing the steps. A second order from a CLEC would probably not alleviate the need for process changes and an alternative path might still be needed. Sharon Van Meter-AT&T asked that if there were no instances of volume, if Qwest would not do this request anyway. Chris Viveros-Qwest stated that Qwest is not willing to go to the expense if we cannot warrant the expense to the benefits. Sharon Van Meter-AT&T stated that she had no further questions. Chris Viveros-Qwest stated that we appreciated AT&T working through this with us to see if the volumes are there. Sharon Van Meter-AT&T asked in the analysis of the jeopardies, if both Retail and Wholesale were looked at and none were found. Russ Urevig-Qwest stated that he looked at jeopardies in IMA for the month of April. Russ stated that looking at AT&T jeopardies, he found none. Russ stated that he then looked at the next 2 highest CLECs and found none. He then spot checked the rest. Russ stated that there were 267 jeopardies in April. Russ stated that he could not check on the Retail side because he does not have access to their data. Sharon Van Meter-AT&T stated that she would take this back internally and see if AT&T wants to pursue this request. Liz Balvin-Covad stated that there was a post completion process implemented and asked if that process could accommodate what AT&T was looking for and stated that the billing would already have been kicked-off. Russ Urevig-Qwest stated that the order would have completed and any billing would not exist on the service order. Russ stated that we would have the same problem and that it could not be kicked out for review. There were no additional questions or comments. Peggy Esquibel Reed-Qwest stated that Qwest would wait for the email from AT&T to see if they wanted to pursue this request and noted that a status would be provided at the June CMP Meeting.

May 18, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that Qwest is continuing to evaluate this request and would provide a status next month. Sharon Van Meter-AT&T questioned why there is still no status. Sharon said Qwest has not provided status for two or three months in a row. Jill Martain-Qwest stated that Qwest is still looking at options to potentially come to an agreement for a viable option. Jill noted that she was aware that there are items being discussed such as the current process and the billing or charges associated to Buried Service Wires. Jill stated that options are still being explored. Jim Recker-Qwest stated that a call could be scheduled to present AT&T with Qwest’s findings so far. Jim noted that internally there are questions that are still being discussed. [Comment from Eschelon: Jim said they thought Qwest had things covered but then more questions came up.] Sharon Van Meter-AT&T stated that her people are looking to her for status and that she needs to provide them with some information. Sharon stated that she would like a meeting fairly quickly. This CR remains in Evaluation status.

April 20, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that Qwest was still evaluating this request and the status remains in Evaluation. Jill stated that there would be a status at the May CMP Meeting.

-- March 16, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that Qwest is reviewing this request internally and more information would be provided at the April CMP Meeting. This CR moves to Evaluation status.

-- March 15, 2005 Ad Hoc Meeting: Attendees: Sharon Van Meter-AT&T, Bonnie Johnson-Eschelon, Kim Isaacs-Eschelon, David Balenger-AT&T, Jen Arnold-TDSMetroCom, Phyllis Sunins-Qwest, Russ Urevig-Qwest, Shirley Tallman-Qwest, Lydell Peterson-Qwest, Laura Baird-Qwest, Alan Braegger-Qwest, Peggy Esquibel Reed-Qwest

Peggy Esquibel Reed- Qwest stated that the purpose of this meeting was for additional discussion regarding the Buried Service Wire Process Change CR that was submitted by AT&T. Russ Urevig-Qwest stated that we wanted to discuss how to handle the buried service wire issue when it is encountered, from an outside technician perspective. Russ stated that one of the issues is when the technician goes out to perform an install, the drop is full, and the tech needs to drop a line. Russ stated that Qwest needs to obtain acceptance of the charges, and then possibly drop the wire above ground. Russ stated that another concern is that Qwest has a certain obligation to perform a certain amount of duty. Russ stated that Qwest would attempt a call in order to obtain acceptance of charges, and noted that the hold time would be a maximum of 5-minutes. Russ stated that the technician would obtain the acceptance of the charges and note that the charges were accepted. Russ stated that Qwest would then proceed with the process of getting the wire buried. Sharon Van Meter-AT&T asked which telephone number the Qwest technician received on his service order; if it was an 800# or the TN of the co-provider. Russ Urevig-Qwest stated that we would need to look at unbundled loops, UNE-P, and general products. Alan Braegger-Qwest stated that what is requested is the LCON TN, but mostly gets the TN of the CLEC, and sometimes the TN of the end user customer. David Balenger-AT&T stated that the fields are populated with either individual extension numbers or with an 800 #s for automated requests, in addition to an end user contact. David then noted that AT&T does not receive a telephone call to advise that the work was completed. Alan Braegger-Qwest stated that Qwest would not call the end user for billing issues. Sharon Van Meter-AT&T asked if the technician would have the number of the CLEC and noted that it would need to flow to Qwest. Alan Braegger-Qwest stated that the technician does get the telephone number of the CLEC. Russ Urevig-Qwest stated that Qwest does call for unbundled loops but does a call for UNE-P, to advise that the work was completed. Russ stated that he would validate the telephone number received on non-designed orders and stated that Qwest needs an established timeframe to obtain approval of charges. Sharon Van Meter-AT&T stated that as long as the TN is on the LSR, she understands that the Qwest technician cannot stay on the line very long. Russ Urevig-Qwest stated that when an outside technician goes out to perform an installation and a drop is needed, and the safety requirements are not met, Qwest would jeop the order unless AT&T requires a call. Russ stated that Qwest would still need acceptance of the charges and the order would go into a delayed status. Sharon Van Meter-AT&T asked if Qwest would install the wire and bury the wire at the same time. Russ Urevig-Qwest stated yes and noted that a safety issue could be if the wire would have to lie across a driveway. Sharon Van Meter-AT&T stated that Qwest should make a call, in all cases, and that if AT&T is not reached, the order should be jeop’ed. Sharon stated that this would need to be built into the process. Russ Urevig-Qwest asked Alan Braegger (Qwest) if that could be made the standard practice. Alan Braegger-Qwest stated that he would want to do that and noted that currently there is a lot of hold time. David Balenger-AT&T stated that this would be acceptable, as AT&T would not expect that the technicians wait. David stated that AT&T could tell Qwest, right there, if they would accept the charges. Russ Urevig-Qwest stated that if the contact TN was an 800#, the expectation is that it would be manned. David Balenger-AT&T stated that if the Qwest technician leaves a message for a call-back, waits 5 minutes, then leaves; it is acceptable to AT&T. Russ Urevig-Qwest stated that Qwest needs all to understand that there would be a maximum hold time of 5 minutes. David Balenger-AT&T asked if then the LSR would need to be resubmitted with the approval in the Remarks. Russ Urevig-Qwest stated yes. Lydell Peterson-Qwest asked if the IMPCON and the LCON TNs are on the LSR. David Balenger-AT&T stated that they were both on the LSR and noted that the IMPCON is the AT&T TN and the LCON is the number of the end user customer. Lydell Peterson-Qwest asked to confirm that the IMPCON TN is the number that the Qwest Technician is to call to obtain acceptance of the charges, and that the LCON is the local end user customer and should not be contacted, by the Qwest technician. Russ Urevig-Qwest also asked to confirm that the TN that the technician would look for is the IMPCON, which is the CLEC and is an 800#. David Balenger-AT&T stated that some do have 800#’s but that some have extension numbers. Russ Urevig- Qwest stated that Qwest would need to validate that the information is captured from the LSR flows down to the service order, then flows to the technician’s service order. Russ Urevig-Qwest stated that a concern for Qwest is that the CLEC Community understands that Qwest understands the request but has requirements on the Qwest side as well, and that Qwest will have a maximum hold time of 5 minutes. Russ stated that all need to be okay with that. David Balenger-AT&T stated that he looked at an LSR and that the LSR has the Initiator and the IMPCON. David stated that the Initiator is the agent in the Center and that the IMPCON contains the generic 800#. David noted that the LSR he looked at has the PON of ZXPH02871778. Russ Urevig-Qwest stated that he would look at the service order and asked which field’s TN was Qwest to call. David Balenger-AT&T stated that Qwest should call the TN contained in the Initiator field. Russ Urevig-Qwest stated that he would look at the PON provided, along with the service order that was created, in order to see what TN is on the service order. David Balenger-AT&T stated that it should have the name of Patty Garnier with the TN of 480 649-4913, unless is a different field on the Qwest side. David stated that it could also show ‘Tech on duty’ with the TN of 800 235-1070. Russ Urevig-Qwest asked for the due date. David Balenger-AT&T stated that the due date is pending, as Qwest is currently processing the LSR. David stated that the requested due date is March 18th. Sharon Van Meter-AT&T stated that AT&T was okay with the 5 minute hold time and stated that when the process was written that the 5 minute hold time needed to be very specific in the documentation. Russ Urevig-Qwest stated that it would be written in the process. Lydell Peterson-Qwest asked to confirm that the expectation would be the same for the states of Oregon and Washington, and that the LSR would need to be resubmitted with the appropriate USOCs. Russ Urevig-Qwest responded yes and stated that the process would be consistent across the Qwest 14-state territory. Shirley Tallman-Qwest asked that when Qwest calls the CLEC and the CLEC authorizes the charges, if the order would need to be supped to indicate that the charges were authorized. Alan Braegger-Qwest stated that the USOCs would need to be added without a supp and stated that Qwest would need to internally work that and other items out, in order to accommodate this request. Lydell Peterson-Qwest asked for clarification that the Qwest technician would call the CLEC, the CLEC would authorize the charges, the Qwest technician would perform the work, and the CLEC would send a supp. Russ Urevig-Qwest stated that in the past, a follow-up supp would be required, so that the authorization of charges would be in writing. Russ stated that the technician does complete out a UNE-P order, so he would need to check to see if a supp would be jeop’d because the work was completed. Russ stated that he would review to see if a supp would need to be required or if a supp would not be needed. Russ stated that maybe Qwest could proceed with the activity and add the charges to the order without a supp. Sharon Van Meter-AT&T stated that when the Qwest technician calls AT&T and AT&T okays the charges, the technician could perform the work and AT&T could immediately submit a supp, because the work would not be completed for a little bit of time. Russ Urevig-Qwest stated that for non-designed, the technician would have their work for the day and if a supp 3 (for other) is received during that day, it may or may not flow through the system, so there could be a timing issue in regard to the processing of the supp. Alan Braegger-Qwest suggested that if the line could not be dropped, that the service order be closed, so the CLEC would have control of the line, and then Qwest would perform the work later. David Balenger-AT&T asked how the CLEC would be notified that the work was done. Russ Urevig-Qwest stated that Qwest needs to make sure that the wire is in the ground and noted that the CLEC would not be notified, as it would be an internal ticket number. David Balenger-AT&T asked that if the end user calls 2 weeks later and says that they still have no service, who would the CLEC call. Russ Urevig-Qwest stated that the work could still be pending and noted that it could be pending several months out. David Balenger-AT&T asked how the CLEC would know what the timeframe is in order to tell their customer. Shirley Tallman-Qwest stated that Qwest does have an internal buried service wire desk that the CLECs Service Manager could contact. Lydell Peterson-Qwest stated that AT&Ts concern is how they find out when the wire would be buried. Russ Urevig-Qwest asked if the CLECs wanted documented, in the PCAT, how to gather information. Sharon Van Meter-AT&T responded yes and stated that the PCAT will need to be very clear. Russ Urevig-Qwest stated that another concern, for Qwest, is that when Qwest calls the CLEC and obtains acceptance of the charges, without paperwork and only the notes that the Qwest technician makes, that we don’t fall into billing disputes claiming that the charges were not authorized via an LSR. Sharon Van Meter-AT&T asked if the technician would know what the charges would be. Alan Braegger-Qwest stated that the technician’s don’t provide estimates of charges because it is difficult to provide a quote because at that time they would not be opening a trench, burying the wire, and closing the trench. Sharon Van Meter-AT&T stated to David Balenger (AT&T) that they would assume that the charges would be reasonable and accept the charges. Sharon asked that if the billed amount were $10,000, what David would do. David Balenger-AT&T stated that AT&T would need to discuss off-line. David stated that their end user doesn’t even pay the $250. David stated that AT&T would need to discuss with Product off-line. Sharon Van Meter-AT&T asked if Qwest would know is a regular order or would Qwest not know until the trench is dug if it was a standard order. Alan Braegger-Qwest stated that the technician could say that it ‘appears’ to be standard but Qwest would not really know so cannot provide a quote. Sharon Van Meter-AT&T stated that if AT&T authorizes the charges, AT&T is authorizing the charges. David Balenger-AT&T stated that AT&T needs to discuss internally. Sharon Van Meter-AT&T stated that she has no issue with that and noted that AT&T would clarify internally. Sharon asked if before the process was set, if there would be another call. Russ Urevig-Qwest stated that the PCAT would be specific about all the information. Lydell Peterson-Qwest asked that after Qwest receives the verbal authorization of charges, if there could be a Record only supp in order to avoid a Qwest said-CLEC said situation. David Balenger-AT&T stated that the situation currently occurs. Russ Urevig-Qwest stated that in that instance, Qwest would not install; Qwest will only install if has authorization of charges. Russ noted that confusion on either side could occur. Russ stated that Qwest does have a concern that charges are reimbursed once they are accepted. Russ Urevig-Qwest stated that Qwest will meet internally to look at the provided LSR example, look at the field data for names and TNs, look at the service order, and will see what flows to the outside technician. Sharon Van Meter-AT&T asked if any other CLECs had questions or concerns. Bonnie Johnson-Eschelon stated that she was okay and had no questions or concerns. Jennifer Arnold-TDSMetroCom stated that she was also okay and had no questions or concerns.

February 16, 2005 Product Process CMP Meeting Discussion, walk-on request: Sharon Van Meter-AT&T reviewed the CR and the expected deliverable. There were no questions or comments.

February 14, 2005 Clarification Meeting: Attendees: Sharon Van Meter-AT&T, Bonnie Johnson-Eschelon, Kim Isaacs-Eschelon, David Balenger-AT&T, Amanda Silva-VCI, Phyllis Sunins-Qwest, Russ Urevig-Qwest, Shirley Tallman-Qwest, Lydell Peterson-Qwest, Jim Recker-Qwest, Peggy Esquibel Reed-Qwest

Review Requested (Description of) Change: Peggy Esquibel Reed-Qwest reviewed the CR’s description and expected deliverable and asked AT&T if they had additional information to share. Sharon Van Meter-AT&T stated that there was no additional information regarding the specific request but would like to note that AT&T went to their Service Manager to resolve this prior to issuing the CR, in an attempt to prevent a CR from being needed. Sharon stated that there had already been several conference calls discussing this issue. Russ Urevig-Qwest stated that he was familiar with the request. Peggy Esquibel Reed-Qwest confirmed that this CR was for Provisioning and that the Impacted Products were not applicable. Lydell Peterson-Qwest stated that Qwest would like examples from AT&T to assist with the investigation of this change request. Sharon Van Meter-AT&T stated that for AT&T, they have from 0-3 instances per week and stated that AT&T has already provided 1 example and stated that there are not other examples. Sharon stated that AT&T expects Qwest to move forward without further examples. Bonnie Johnson-Eschelon asked what Qwest needed examples of. Lydell Peterson-Qwest stated that examples are needed of move orders that received a jeopardy because buried service wire was needed. Bonnie Johnson-Eschelon asked if Qwest does not track jeopardies for buried service wire. Lydell Peterson-Qwest stated yes, Qwest does track them. Russ Urevig-Qwest stated that on the due date, when we go out, the technician may need to open an activity. David Balenger-AT&T asked that if buried service wire is needed, if can Qwest pull by jeopardy, by region code. Russ Urevig-Qwest stated that he would need to check to see if Qwest had that data. David Balenger-AT&T stated that this issue keeps resurfacing and asked what the requested examples would provide Qwest. Russ Urevig-Qwest stated that Qwest is looking for specific examples in order to investigate because Qwest is not experiencing this issue with other CLECs. Bonnie Johnson-Eschelon asked if something different was supposed to happen instead of the orders being jeop’d for buried service wire. David Balenger-AT&T stated that AT&T does not want a jeopardy on the due date and a new interval. David stated that AT&T wants the contact information utilized and for Qwest to accept a verbal yes. Bonnie Johnson-Eschelon stated that maybe Qwest has not experienced this with other CLECs because that had not been brought up. Bonnie asked what Qwest needed examples of if Qwest knows which jeopardizes are for buried service wire. Bonnie asked if what AT&T is really requesting is the ability to approve charges and that the due date is not really the issue. Sharon Van Meter-AT&T stated yes, AT&T would like to tell Qwest that AT&T accepts the fee for buried service wire and mark for manual handling, but no one wants that. David Balenger-AT&T stated that when they have to tell their customer that they have to send the order back, it is dissatisfying to the customer. Russ Urevig-Qwest stated that if the technician is out and they need to drop a wire, the technician needs approval. Russ stated that there are occasions when the technician gets the approval on the same day but that we cannot dig on the same day due to circumstances. Russ asked if AT&T is asking for a clear process for Qwest to make an attempt to obtain the approval of the cut on the day that the technician is out. Russ stated that approval is needed for trenching expenses. David Balenger-AT&T stated that the wording in the PCAT states that Qwest should do this and that AT&T automatically accepts the fees. David stated that a call to obtain the approval should not be needed, due to the language in the PCAT. Russ Urevig-Qwest stated that this is state specific and noted that in certain states; Qwest can go ahead and drop if meets state requirements. Sharon Van Meter-AT&T stated that the PCAT states that when submitting a request for buried service wire on the original or supplemental, you are authorizing or accepting the charges. David Balenger-AT&T stated that AT&T realizes that Qwest may not know the day of but AT&T is not asking for a site visit on every move order. Bonnie Johnson-Eschelon asked if this happens mostly for residential locations. Russ Urevig-Qwest stated that happens just as often for business and residential locations. Bonnie Johnson-Eschelon stated that Eschelon was receiving jeopardizes but that they were really for conduit. Russ Urevig-Qwest stated that is true and that are being addressed separately from this CR. Amanda Silva-VCI stated that VCI’s experience on a jeop’d order was that Qwest needed $375 for additional work on tribal land and asked if could be an example. Amanda provided the LSR ID of 13340389. Amanda then stated that a jeopardy had not yet been received because this just occurred. Sharon Van Meter-AT&T asked if the PCAT language meant anything because they do not know that buried service wire is needed when they submit the LSR. Russ Urevig-Qwest stated that if the submitter knows that the facilities are full, and most businesses do know, and that there will be a buried service wire issue, the submitter can note the information in remarks and mark for manual handling. Bonnie Johnson-Eschelon asked if Qwest could do a blanket approval for AT&T. Sharon Van Meter-AT&T stated that AT&T would always approve the charges. Russ Urevig-Qwest stated that there are difficulties with doing a blanket approval. Jim Recker-Qwest asked if all CLECs would want to do that. Bonnie Johnson-Eschelon said no. Phyllis Sunins-Qwest stated that with Symmetry & Symphony, can only have billable fields and that this would need internal discussion. Jim Recker-Qwest asked to confirm that for this request, it is specifically for service wire (2 or 3 pair) and not for larger service wire cables, which are conduit. Sharon Van Meter-AT&T confirmed that this request was only for buried service wire and not for conduit. Bonnie Johnson-Eschelon asked what the possibility was for adding a field in IMA. David Balenger-AT&T stated that they still would not know that buried service wire is needed when the submitted the LSR. Sharon Van Meter-AT&T stated that would then be a separate CR. David Balenger-AT&T stated that it would also require more automation on AT&Ts part. Russ Urevig-Qwest stated that exclusions would also be needed. Bonnie Johnson-Eschelon said okay. Jim Recker-Qwest asked if the size of the drop needed to be specified. Russ Urevig-Qwest stated that if residential or business needs a drop, either 4 or 6 pair needs to be specified. Jim Recker-Qwest asked if the end user customer of record is asked for the size. Russ Urevig-Qwest stated that internal discussion is needed to look into the cost differences that the CLEC would need to approve. Bonnie Johnson-Eschelon asked if that question was asked of the Retail customer. Jim Recker-Qwest stated that he just wanted to make sure that he had all the facts. Bonnie Johnson-Eschelon asked if there was a current process on the Retail side that could be mirrored. Russ Urevig-Qwest stated that he would need to look into that. There were no additional questions or comments regarding the request. Peggy Esquibel Reed-Qwest stated that this CR has been requested to be walked-on at the February CMP Meeting and that the CR would also be scheduled for formal presentation at the March CMP Meeting.


CenturyLink Response

July 12, 2005 REVISED RESPONSE For Review by the CLEC Community and Discussion at the July 20, 2005 CMP Meeting

TO: Sharon Van Meter AT&T Communications

SUBJECT: CLEC CR-PC020705-1 Buried Service Wire Process Change

Description of Change: AT&T very rarely knows when Buried Service Wire is needed. When Qwest determines that the service is needed, Qwest needs confirmation that AT&T will pay for the Buried Service Wire fee. Today Qwest sometimes notifies AT&T via jeopardy, on the due date, that Buried Service Wire is needed. Notifying AT&T on the due date is a big dis-satisfier for the AT&T customer as they are expecting the service to be delivered on the due date. Sometimes Qwest completes the service without notifying AT&T that the service is needed - which is a good thing for the customer. AT&T is looking for Qwest to develop a process to notify CLECs, on the customer due date, that Buried Service Wire is needed and allow the CLEC to accept the charges while the technician is still on the customer’s site.

Qwest Response: During the ad hoc calls, AT&T clarified that this request is for a Buried Service Wire Process to be developed in order for the end user customer to get service on the due date, when it is has been identified that an additional drop is required.

Qwest does not inventory "Drops" or "Buried Service Wire" and therefore has no indication that an additional drop is required until the technician arrives at the service location. At that time the technician checks the existing drop for capacity to determine if there is in fact spare capacity. If there is no spare capacity, the technician places the order in jeopardy. The service order in jeopardy triggers an indication that a Qwest representative needs to survey the situation at the service location to determine the cost to augment the drop. This information is then sent to the requestor for approval. Upon approval to proceed, the jeopardy will be updated and trigger handoff to the Buried Service Wire (BSW) group. Once this work is complete, the BSW group releases the order from jeopardy and a new due date is scheduled to complete the service request.

Qwest has researched and analyzed how to meet the expected deliverable of providing service on the original due date. In order to accomplish that, Qwest has determined that it would require the following changes:

- A new process for technician’s to obtain written CLEC authorization to place the drop on the due date. This would entail CLECs being willing to authorize charges without receiving a quote since the site survey will not have taken place.

- Installation procedure changes to reflect that technician’s may temporize additional drops when the CLEC has authorized AND it is safe to do so. This would result in the technician completing the service order as there is no jeopardy. This would also entail re-training technicians on the change in procedure.

- A new process for triggering what the jeopardy triggers currently. Namely, the Qwest representative surveying the site to determine the cost of the augment.

- A new means of scheduling the drop work with the BSW group

Qwest is respectfully denying this request due to economic infeasibility, based on the costs to implement the multiple process changes required, compared to the low volume of requests requiring a Buried Service Wire augment as estimated by AT&T and by Qwest’s research.

Sincerely, Qwest Communications

For Review by the CLEC Community and Discussion at the April 20, 2005 CMP Meeting

April 12, 2005

AT&T Sharon Van Meter

SUBJECT: CR # PC020705-1 Buried Service Wire Process Change

This letter is in response to AT&T’s Change Request (CR) PC020705-1 Buried Service Wire Process Change. This CR requests that Qwest develop a process to notify CLECs, on the customer due date, that Buried Service Wire is needed and allow the CLEC to accept the charges while the technician is still on the customer’s site. AT&T expects Qwest to develop and implement a process for CLECs to accept the Buried Service Wire fee while the outside technician is still at the customer premises.

Qwest would like to place this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. Qwest will provide an updated response at the May CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Jim Recker, Qwest Communications


Open Product/Process CR PC112105-1 Detail

 
Title: AT&T requests an installation date of less that 3 days on expedites when a CNR condition has been resolved
CR Number Current Status
Date
Area Impacted Products Impacted

PC112105-1 Completed
5/5/2006
Design
Originator: Van Meter, Sharon
Originator Company Name: AT&T
Owner: Tallman, Shirley
Director:
CR PM: Stecklein, Lynn

Description Of Change

AT&T has signed the Expedite ICA Amendment. If a CNR occurs on an order and AT&T supps that order – per Qwest’s interval – AT&T wants the ability to be able to request an expedited due date earlier than the 3 day required interval. AT&T is willing to pay the $200 per day charge associated with the expedite request.


Status History

11/21/05 - CR submitted

11/23/05 - CR acknowledged

11/28/05 - Clarification Meeting scheduled

11/30/05 - Clarification Meeting held

11/30/05 - Status changed to Clarification

12/14/05 - Discussed in the December Product/Process CMP Meeting - See Attachment C in the Distribution Package

12/14/05 - Status changed to Presented

1/18/06 - Status changed to Evaluation

1/18/06 - Discussed in the January Product/Process CMP Meeting - See Attachment C in the Distribution Package

2/16/06 - Status changed to Development

2/16/06 - Discussed in the February Product/Process CMP Meeting - See Attachment C in the Distribution Package

3/1/06 - PROS.03.01.06.F.03710.Expedites_EscalationsV35 - Level 3

3/15/06 - Discussed in the March Product/Process CMP Meeting - See Attachment C in the Distribution Package

4/15/06 - Status Changed to CLEC Test Due to April 15, 2006 Implementation

4/19/06 - Discussed in the April Product/Process CMP Meeting - See Attachment C in the Distribution Package

5/5/06 - Status changed to Completed


Project Meetings

5/5/06 E-mail From AT&T

Hi Lynn, Sorry for not responding earlier... our work centers haven't had the opportunity to try to use this option yet, however, I think it is safe to close. If something comes up when the <3 day request is used, we can address it with the work center. Thanks! Kathy

From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Friday, May 05, 2006 9:57 AM To: Lee, Kathy T, GBLAM Subject: PC112105-1 AT&T Requests an Installation Date of Less Than 3 Days on Expedites

Hi Kathy,

Were you able to determine if AT&T was ok to close this CR? See meeting minutes below.

Thanks!

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770 4/19/06 Product/Process CMP Meeting

Jill Martain-Qwest stated that this request was implemented on April 17th and is working fine. Jill stated that this is currently in CLEC Test and asked if the Change Request could be closed.

Kathy Lee-AT&T stated that she has not heard of any issues and has not asked if there were any. Kathy stated that she would check and close the CR off-line.

3/15/06 Product/Process CMP Meeting

Jill Martain-Qwest stated that a notice was sent and that this CR will become effective on 4/15/06. This CR will remain in Development.

2/15/06 Product/Process CMP Meeting

Jill Martain-Qwest stated that this CR has been accepted and that we are moving forward with PCAT changes. She said that a Level 3 will be sent out next week. Sharon Van Meter-AT&T asked if they would be able to take advantage of this functionality immediately. Jill Martain-Qwest said that said that the PCAT changes need to be made and that the changes will go into effect in 45 days. Sharon Van Meter-AT&T said thank you. Lynn Hankins-Covad asked what the interval would be. Jill Martain-Qwest said that they will be able to request a shorter than normal interval. She said that a Supp should be issued requesting the new due date and that the EXP should be populated. Qwest will then determine if that interval can be met and will send the FOC. Jill said if the interval cannot be met, Qwest may contact the CLEC with an alternate date.

1/18/06 Product/Process CMP Meeting

Shirley Tallman - Qwest stated that this CR is still under review. Jill Martain - Qwest said that this CR will move to Evaluation.

12/14/05 Product/Process CMP Meeting

Sharon Van Meter/AT&T stated that AT&T has signed the Expedite ICA Amendment. Sharon said that if a CNR occurs on an order and AT&T supps that order – per Qwest’s interval – AT&T wants the ability to be able to request an expedited due date earlier than the 3 day required interval. Sharon said that AT&T is willing to pay the $200 per day charge associated with the expedite request. Sharon said that during the clarification call it was confirmed that this request is for design products only. Jill Martain/Qwest said that this CR will move to a Presented Status.

11/30/05 Clarification Meeting6.4 Process for Creating Product/Process CMP Monthly Meeting Distribution Package

Attendees: Sharon Van Meter - AT&T, Laurie Dalton - Qwest, Jim Recker - Qwest, Kathy Ocken - Qwest, Barbara Fanning - Qwest, Phyllis Sunins - Qwest, Lynn Stecklein - Qwest

Review CR Description Sharon Van Meter - AT&T stated that AT&T has signed the Expedite ICA Amendment She said that If a CNR occurs on an order and AT&T supps that order - per Qwest’s interval - AT&T wants the ability to be able to request an expedited due date earlier than the 3 day required interval. Sharon stated that AT&T is willing to pay the $200 per day charge associated with the expedite request.

Discussion: Lynn Stecklein - Qwest asked what products were impacted by this request. Sharon Van Meter - AT&T said that she thought it would impact all products. Laurie Dalton - Qwest stated that this would not apply to all products because we don't bill expedite charges on non-design. Laurie asked if this applied to the LSR and the ASR. Sharon Van Meter - AT&T said yes. Jim Recker - Qwest asked about held orders and CNR scenarios. Sharon Van Meter - AT&T said that scenarios with no facilities would be a different issue. She said that AT&T just wants to have the option when the CNR situation is cleared to expedite for a shorter interval. Laurie Dalton - Qwest asked if the order was already expedited and the customer wasn't ready and AT&T wanted to expedite again, there would be 2 expedite charges. Sharon Van Meter - AT&T said that Qwest will have to be sure to quote both charges. Sharon said that she did not think this scenario would happen very often.

Establish Action Plan Lynn Stecklein - Qwest said that AT&T will present this CR in the December Product/Process Meeting.


Open Product/Process CR PC031203-2X Detail

 
Title: Resolve Disconnect of Account Number (Cross Over from SCR031203 02)
CR Number Current Status
Date
Area Impacted Products Impacted

PC031203-2X Completed
6/20/2007
UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Pent, Anne
Director:
CR PM: Stecklein, Lynn

Description Of Change

When a CLEC migrates a multi-line account and then sometime later the customer requests to disconnect the main number, this must be supported through system or operation. Disconnecting the BTN on a Muliline account means that a new Account Number may have to be assigned and these rules must be known. One of the remaining numbers may have to attain BTN status with Directory Listing treatment applied to it.


Status History


Project Meetings

6/22/07 E-mail From AT&T Hi Lynn, I joined the call late… sorry about that. I checked Leo Dimitriatis and he concurs that it is OK to close this CR. Thanks very much for all of your assistance with this. Kathy

- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Friday, June 22, 2007 1:49 PM To: LEE, KATHY T, ATTCORP Subject: Question on PC031203-2X Resolve Disconnect of Account Number

Hi Kathy, I believe you missed the discussion in the June Product/Process CMP Meeting on SCR031203-2X Resolve Disconnect of Account Number. Here is what was discussed: PC031203-2X Resolve Disconnect of Account Number (Cross Over from SCR031203-02)

Mark Coyne-Qwest stated that this CR was a crossover from Systems and was implemented on 6/4/07. Mark asked if AT&T was ok to close.

No one from AT&T was on the bridge.

Mark Coyne-Qwest stated that we would work offline with AT&T.

I wanted to check with you to determine if this CR can be closed. I have attached a copy of the CR.

Thanks!

Lynn Stecklein

Qwest Wholesale CMP

-- 6/20/07 Product/Process CMP Meeting

Mark Coyne-Qwest stated that this CR was a crossover from Systems and was implemented on 6/4/07. Mark asked if AT&T was ok to close. No one from AT&T was on the bridge. Mark Coyne-Qwest stated that we would work offline with AT&T.

5/16/07 Systems CMP Meeting

Mark Coyne-Qwest stated that this CR was crossed over from Systems and is scheduled for implementation on June 4th. Mark then noted that the Level 2 Notice would be going out on May 14th. Mark asked if there were any questions or comments. There were none.

-- 4/18/07 Product/Process CMP Meeting

Mark Coyne-Qwest stated that this CR was a crossover from Systems and was discussed in the March CMP Meeting.

Lynn Stecklein-Qwest stated that a notification will be sent to update the documentation.

3/21/07 Product/Process CMP Meeting

Mark Coyne-Qwest stated that this Systems CR was submitted by AT&T and will be crossed over to a Product/Process CR.

Lynn Stecklein-Qwest stated that this System CR, as Mark said, was submitted by AT&T requesting a solution for when a CLEC migrates a multi-line account and then sometime later their customer requests to disconnect the main number. AT&T stated that disconnecting the BTN on a multi-line account means that a new account number may have to be assigned and that they did not know what the rules were for when this happened. Lynn said that during the requirements review for this CR it was determined that this request can be accommodated with a Process change instead of a System change. She said that a clarification call was held with AT&T and other CLECs on March 1 to communicate the process solution. Lynn said that during that meeting, Qwest stated that when a customer has a multi-line account and the main BTN is being removed from the account, the customer has the option of using specific fields (i.e. NAN) to select what remaining TN they would like to use as the new BTN. If no notification is received from the CLEC then the next logic line number will be assigned as the new BTN. Lynn stated that AT&T agreed that this process would work for them and stated that they preferred this to a system change. She said that that this process is documented in various PCATs and updates will be made for this CR.

Mark Coyne-Qwest stated that the system CR will be closed and will cross over to a Product and Process CR.

3/1/07 Additional Clarification Meeting

SCR031203-02 Resolve Disconnect of Account Number

Attendees: Chris Terrell-AT&T, Kathi Lee-AT&T, Leo Dimitriatis-AT&T, Kim Isaacs-Eschelon, Anne Pent-Qwest, Lynn Stecklein-Qwest

Lynn Stecklein-Qwest stated that the purpose of this meeting was to communicate a solution for this change request that would require no system work. If everyone agreed with this solution we would cross this CR over to a Product/Process CR.

Anne Pent-Qwest cited the example of a 5 line account with the main billing TN (BTN) being removed from the account. Anne said that you have the option of using the NAN field on selecting what remaining TN you would like to use as the new BTN.

Leo Dimitriatis-AT&T reviewed the scenario of a 5 line account and 4 TNs are being left behind and belong to Qwest. Leo said that they would have the option of choosing the BTN.

Anne Pent-Qwest stated that we would take the next logic line number if no notification is received from the CLEC. She said that the TNs on the CSR may not be sequential.

Leo Dimitriatis-AT&T said that the next logic line number would then become the BTN and asked if the account would be updated with the 4 remaining TNs.

Anne Pent-Qwest stated that happens prior to completion.

Leo Dimitriatis-AT&T said that after the migration occurs, they will see the newly assigned BTN. He said that this is a good scenario.

Kim Isaacs-Eschelon asked what happens to the listing associated with the old BTN.

Anne Pent-Qwest said that we don’t make the listing change. She said that the FOC on a ported number has a remarks section to indicate if the listing is to be changed.

Kim Isaacs-Eschelon said that with a Resale or QPP account, you have 1 CSR with the Main Listing and the other number on another CSR with no listing. Kim asked if the listing would apply to the BTN. Kim also asked if the phone book would have a different listing.

Anne Pent-Qwest said that they would.

Kim Isaacs-Eschelon asked if a new account number could be requested as non- published.

Anne Pent-Qwest said no and that the customer would have to make a change.

Leo Dimitriatis-AT&T asked if the listings still belonged to Qwest in the scenario discussed above with the 4 remaining TNs.

Anne Pent-Qwest said that the listings do belong to Qwest. She said that the decision was made not to assume and that the end user would have to call Qwest to make a change.

Chris Terrell-AT&T said that she understood that Qwest would use the next logical number on the CSR for the new BTN. She asked how the customer would know.

Leo Dimitriatis-AT&T said that after the BTN was migrated the BCN will have that information and the customer can look at the CSR and that the rules will be reflected in the CSR. He asked how Qwest would handle the scenario where you have 5 lines migrating to AT&T on one order and the customer wants to disconnect the TN that happens to be the BTN.

Anne Pent-Qwest stated that you can designate if the customer has a preference for the main line or the next number to be the BTN and this information will be on the FOC.

Leo Dimitriatis-AT&T asked about listing treatment with using the next logical number.

Anne Pent-Qwest stated since you own the account in this instance the listing would have to ‘O’ and ‘I’ ‘d for the remaining TN.

Chris Terrell-AT&T asked if this was done on a disconnect order.

Anne Pent-Qwest said that this would be done on a partial C order with an ACT of ‘C’.

Leo Dimitriatis-AT&T said that on the change order for the account they could include the listing. He also said that if they don’t use the FOC, they will assume that Qwest has used the next logical line number and that no listing treatment is applicable.

Chris Terrell-AT&T asked if Qwest would do anything with the listing for the TN.

Anne Pent-Qwest said that if the main TN is disconnected the listing will stay the same.

Leo Dimitriatis-AT&T stated that they do support this solution. He said that Verizon Business uses the next logical number and automatically assigns the main listing when a BTN is disconnected.

Anne Pent-Qwest said that is what we will do and said that if you want a change to let us know.

Leo Dimitriatis-AT&T said that with this solution there are no changes for AT&T except to let their operations people know.

Chris Terrell-AT&T said that the ‘NAN’ field is a good thing and that they would prefer to let Qwest know what they prefer.

Leo Dimitriatis-AT&T asked if this process was documented.

Anne Pent-Qwest stated that this process is documented in various PCATs and will be updated with the Product/Process CR.

Lynn Stecklein-Qwest stated that this CR will be discussed in the March Product/Process CMP Meeting on March 21, 2007.

10/31/06 Additional Clarification Meeting

Chris Terrel - AT&T, Kathy Lee - AT&T, Leo Dimitriatis - AT&T, Chuck Anderson - Qwest, Anne Pent - Qwest, Lynn Stecklein - Qwest Communications

Lynn Stecklein - Qwest stated that the purpose of this meeting is to further clarify this change request.

Chuck Anderson - Qwest asked if this request was associated with a migration request on a number that is a BTN that is disconnected between the time the conversion happens.

Leo Dimitriatis - AT&T stated there are 2 cases - the 1st is when a customer wants to disconnect the BTN that has a WTN. Leo asked what the process is for the WTN and how to obtain the WTN housing. He said that 2nd scenario is when you migrate a multi-line account with a WTN and BTN and the BTN migrates to Qwest and the WTN belongs to AT&T.

Chris Terrell - AT&T asked what if you have one BTN with multiple WTNs on the account - what is the BTN to WTN status.

Chuck Anderson - Qwest stated that he needed to investigate the WTN with the next highest sequence.

Leo Dimitriatis- AT&T asked what the CLEC needs to do when the BTN has been elevated. He said that they need to know what happens to the remaining WTNs and which WTN is elevated to BTN.

Chuck Anderson - Qwest said that we just need to figure out the notification or disclosure process when the BTN has been taken off the account and which WTN becomes the BTN.

Leo Dimitriatis - AT&T asked what happens if you have 1 BTN and 1 main listing.

Chuck Anderson - Qwest stated that we need to talk with the Listing SME. He said that this may not require system work and would just be a process change.

Chris Terrel - AT&T stated that they would prefer an enhancement without system work.

2/16/05 Systems CMP Meeting - IMA 18.0 Candidate Discussion

Chris Terrell-AT&T stated that they would like to leave this CR open and is a medium priority for AT&T.

7/22/04 CMP Systems Meeting

Jill Martain/Qwest stated that Qwest would distribute the ballot on July 27th, it is due back to Qwest on July 30th, and Qwest would email the initial prioritization list to the CLECs on August 3rd. There were no questions.

Donna Osborne-Miller/AT&T stated this was low for AT&T.

8/21/03 CMP Systems Meeting

Phyllis Burt/AT&T stated that AT&T’s interest was moderate.

4/17/03 CMP Systems Meeting Donna Osborne-Miller/AT&T reviewed the description of change. John Gallegos/Qwest stated that the LOE is 1700 to 2800 hours for this request. The status will be changed to presented.

4/3/03 Clarification Meeting Introduction of Attendees Phyllis Burt - AT&T, Donna Osborne-Miller - AT&T, Curt Anderson- Qwest, Berkley Loggie - Qwest, Joan Pfeffer - Qwest, Shon Heiger, John Gallegos - Qwest, Mark Early

Review Requested Description of Change When a CLEC migrates a multi-line account and then sometime later the customer requests to disconnect the main number, this must be supported through system or operation. Disconnecting the BTN on a Muliline account means that a new Account Number may have to be assigned and these rules must be known. One of the remaining numbers may have to attain BTN status with Directory Listing treatment applied to it.

Confirm Areas & Products Impacted UNE-P Pots, IMA Common

Confirm Right Personnel Involved All appropriate personnel were involved in the clarification call.

Identify/Confirm CLECs Expectation When a BTN has been disconnected, one of the remaining TNs will have to be the BTN.

Identify any Dependent Systems Change Requests NA

Establish Action Plan This change request was a walk on in the March CMP Systems Meeting and will be presented in the April Meeting by AT&T.

4/1/03 Clarification Meeting Customer not present, meeting rescheduled.

3/20/03 CMP Systems Meeting Donna Osborne-Miller/AT&T presented the CR. Phyllis Burt/AT&T said that she was not real familiar with this CR but thought that the description of change was self explanatory. If you lose the main number how do you get a new main listing. It currently doesn’t allow us to do a new main listing. Bonnie Johnson/Eschelon said that they have run into this with EDI. The answer is that when you migrate the BTN, regardless if you identified the new BTN you want, Qwest says that it’s an optional field. It is automatically processed as non-published. We have no say of what it should be and if the customer wants it any different they have to call Qwest Retail. Liz Balvin/WorldCom said that it sounds like the request is for after the fact. Connie Winston/Qwest noted that Qwest will schedule the clarification call and that this CR will be eligible for the 15.0 release Donna Osborne-Miller/AT&T suggested that AT&T send out the information regarding the clarification call to the other CLECs.


Open Product/Process CR 5608142 Detail

 
Title: LNP repair interval
CR Number Current Status
Date
Area Impacted Products Impacted

5608142 Denied
11/14/2001
Repair LNP
Originator: Thiessen, James
Originator Company Name: Avista Communications
Owner: Dubose, Lorna
Director:
CR PM:

Description Of Change

Currently, Qwest has a 24-hour commit tine for all LNP trouble tickets that are opened. These tickets can be escalated every ½ hour, but all the escalation does is guarantee that the ticket will be worked within 24 hours. Would like to see this reduced to a more reasonable amount of time.


Status History

6/13/01 - CR received from Jim Thiessen of Avista Communications 6/18/01 – Status changed to New – to be Evaluated 7/09/01 - Reviewed under consideration

7/09/01 - LNP product team to discuss on 7/17/01 – will report status during the July 18th Monthly CICMP Meeting (LD)

8/09/01 - Status report will be given by Lorna Dubose and Joan Wells during the August CICMP Meeting

8/15/01 - CLEC CMP Meeting Product & Process CR 5608142. Joan indicated that with implementation of repair issue within 48 hours of port, or 48 hours after port should correct the issue. Jim Beers advised that a clarification meeting would be set-up and chaired by Judy Schultz, or her designee. J Schultz L Dubose By next meeting

8/22/01 - CR under review (MJB)

8/23/01 -- Qwest called Jim Thiessen (Avista) to set up clarification meeting; awaiting call back

8/27/01 -- Qwest called Jim Thiessen (Avista) to set up clarification meeting; awaiting call back #2

08/30/01 - Jim Thiessen (Avista) returned call; if no meeting on 09/04/01 then first meeting on 09/17/01.

09/05/01 - Qwest response posted to database

09/19/01 -- Status update provided at CMP (MJB)

09/21/01 -- Response walkthrough meeting with Avista (MJB)

09/24/01 -- Meeting minutes sent to Avista (MJB)

10/10/01 - Qwest response posted to database.

10/17/01 - CMP Meeting: Qwest presented draft response. Additional clarification meeting with Jim to occur regarding concerns, Loop with LNP. New CR may need to be opened.

11/09/01 - Issued Revised Response dated 11/09/01 to Avista.

11/14/01 - CMP Meeting - Qwest advised that the response denies the CR request, status changed to Denied. Eschelon would like Qwest to explain why a 24 hour commitment was not feasible.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

September 21, 2001 11:00 a.m. Change Request Response Walkthrough

Attendees:

Jim Thiessen (Avista), Lorna Dubose (Qwest), Margaret Bumgarner (Qwest), Todd Mead (Qwest), Tom Davis (Qwest), Michael Buck (Qwest)

Qwest presented the draft response to the change request. Jim (Avista) indicated that the change request was intended to correct a problem that occurs once every three or four months. (The problem has not occurred since the CR was issued in early June.) The issue is that if there is problem at the time of the port, Avista would like to have it resolved in less than 24 hours to prevent or reduce the amount of time a customer is left without service. In the past, Avista had been instructed to call the LNP LAB for resolution. When this has happened resolution has taken up to 24 hours.

Margaret (Qwest) indicated that she believes that the repair escalation process has subsequently changed. She believes the process is for the CLEC to call the ISC for issues within 48 hours of the port and that the ISC would make the call to the LNP Lab. Margaret believed that the new process was covered in a notice issued in late May.

Jim (Avista) indicated that if the process Margaret described would satisfy his concern and his intent for writing the CR.

Lorna took a few action items to confirm the process for Avista in a revised response.

Action Items: - Lorna Dubose (Qwest) to confirm process for dealing with LNP Lab (due 9/26) - Lorna Dubose (Qwest) to write revised response (due 9/26)


CenturyLink Response

November 9, 2001

Mr. Jim Thiessen

Avista Communications

This letter is in response to your CLEC Change Request Form, number 5608142 dated June 13, 2001 – LNP Repair Interval.

Request: Currently, Qwest has a 24-hour commit time for all LNP trouble tickets that are opened. These tickets can be escalated every ½ hour, but all the escalation does is guarantee that the ticket will be worked within 24 hours. Would like to see this reduced to a more reasonable amount of time.

Response: Repair intervals were agreed to at the performance measurement workshops under the auspices of the Regional Oversight Committee (ROC) and the Arizona TAG. MR-11 LNP Trouble Reports cleared within 24 hours was established as a measure of the interval agreed upon. The standard is parity with MR-3C Results for Retail Residence. Qwest will continue to be consistent with these agreements.

Qwest Call Center Agents will review any pending order information for accuracy and establish contact with the appropriate repair center, if necessary. The ISC will issue a work queue ticket and agree to provide regular status to the CLEC at regular intervals until resolution.

Sincerely,

Maureen Callan Group Product Manager


Open Product/Process CR PC112003-1 Detail

 
Title: Differentiate between Loop MUX combos and EELs due to different FCC treatment (TRO Order)
CR Number Current Status
Date
Area Impacted Products Impacted

PC112003-1 Completed
6/16/2004
Billing, EEL (UNE-C), Loop MUX Combo
Originator:
Originator Company Name: Cbeyond Communications
Owner: Finley, Pat
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Seperately identify LMCs and EELs on bills


Status History

11/20/03 - CR Submitted

11/21/03 - CR Acknowledged

11/24/03 - Spoke with Morgan Halliday, he will call back & schedule clarification meeting

12/01/03 - Clarification Meeting scheduled 12/4

12/04/03 - Held Clarification Call

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/17/04 - Qwest issued PROD.02.17.04.F.01369.EEL_V25, Level 1 effective 2/18/04, provides download in billing section w/ EEL/LMC Class of Service and EEL USOCs

02/17/04 - Qwest issued PROD.02.17.04.F.01371.LMC_V21, Level 1 effective 2/18/04, provides download in billing section w/ EEL/LMC Class of Service and LMC USOCs

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

06/16/04 June CMP Meeting Linda Sanchez-Steinke with Qwest said she e-mailed Cbeyond asking to close the CR on 5/20 and 6/1 and did not receive a response. In the 6/1 e-mail to Stephan Calhoun and Tom Hyde at Cbeyond, Linda said if she had not heard back, the CR would close on 6/3. It was agreed this CR would move to Completed status.

Date: 6/1/04 7:55 a.m. To: 'tom.hyde@cbeyond.net', 'stephan.calhoun@cbeyond.net' From: Sanchez Steinke, Linda Subject: FW: CMP CR PC112003-1

Tom & Stephan -

As a follow up to the e-mail message attached, I will be closing change request PC112003-1 on Thurdsay 6/3/04. If you have any questions, please respond back to me before 6/3/04.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

--Original Message-- From: Sanchez Steinke, Linda Sent: Thursday, May 20, 2004 8:03 AM To: 'Stephan.Calhoun@cbeyond.net'; 'tom.hyde@cbeyond.net' Subject: CMP CR PC112003-1

Stephan & Tom -

As a follow up to yesterday's CMP meeting, we discussed closing this CR. The CLEC community suggested that I e-mail and find out if Cbeyond agrees to close. Please let me know.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

Date: 5/20/04 8:03 a.m. From; Sanchez Steinke, Linda To; 'Stephan.Calhoun@cbeyond.net'; 'tom.hyde@cbeyond.net' Subject: CMP CR PC112003-1

Stephan & Tom -

As a follow up to yesterday's CMP meeting, we discussed closing this CR. The CLEC community suggested that I e-mail and find out if Cbeyond agrees to close. Please let me know.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

05/19/04 May CMP Meeting Pat Finley with Qwest reported during the April meeting Stephan Calhoun with Cbeyond said that a USOC appeared on EEL and LMC bills that had a UNE-P definition. This USOC is shared between UNE-P, EEL and LMC. Service Delivery has requested that this description be corrected. Pat said that the USOC will have a new description. Liz Balvin with MCI asked if notification would be provided. Susan Lorence with Qwest said there usually is no notification. Bonnie Johnson with Eschelon said the billing folks would need to know. Susan said if there is a product change or product name change, then there could be PCAT changes. Liz asked if the USOC would continue to say NRC for UNE-C. Pat said that the USOC will remain the same, but the description will be more generic. Susie Bliss with Qwest asked Liz if her question was, is something going to look different on the bill. Liz agreed. Bonnie said that people who are processing bills will see one thing one month and another the next. Susie asked Sami Hooper if the bill phrase is going to change. Sami Hooper with Qwest said that the USOC FID finder is generic and that the central CRIS bill singled out UNE-P. Bonnie and Liz both said that Qwest may receive questions for that change in the definition of the USOC and would be good to get a notice. Susan Lorence asked if Bonnie and Liz were concerned the billing reps would need to be provided information so they know that this is the reason for the change. (Bonnie’s comment insert here) Susie Bliss said that Qwest billing SDCs could notify the CLECs of changes of this nature. Do we have an action item open for this issue? (end Bonnie’s comment) Linda Sanchez-Steinke with Qwest will e-mail Cbeyond for approval to close this CR.

04/21/04 April CMP Meeting Pat Finley with Qwest said that during last month’s meeting some items discussed need to be corrected. Qwest has developed the TRAK FID, which uniquely identifies EEL & LMC. PCAT changes identify the USOCs used for LMC and EEL. Last month Liz Balvin with MCI had asked if monthly training could be provided to the center. In speaking with the process specialist, training is provided on an as needed basis when we identify a problem, and won’t be done on a monthly basis. Also last month, Bonnie Johnson with Eschelon had asked if a review was done on all customer’s bills, and that was not the case. Specific questions Cbeyond had on their billing, when their circuits were converted to EEL and LMC were researched.

Bonnie Johnson with Eschelon asked why, if there is a known problem, and if there was not a review of all CLEC accounts, that the expectation is the CLECs prove there is a problem. Pat Finley responded there is not a widespread problem and Cbeyond had given specific instances where EEL and LMC conversion orders were issued. Bonnie asked if service management could notify their customers, that Qwest should do notification. Bonnie asked if other customers had these conversions done. Pat said that if any company has problems they could contact their service manager for resolution. Bonnie said that since a problem has been uncovered that you may want to get with service managers, who could contact their customers. Kit Thomte with Qwest said that Linda Sanchez-Steinke will contact the directors over the service management team to make them aware.

Stephan Calhoun with Cbeyond joined the call and said that as Cbeyond was investigating, they found that circuit IDs with inconsistencies. They found circuit IDs that have no relationship to what Qwest provisioned and the circuit ID has been changed to fit with EEL or LMC. Further, Cbeyond is concerned that the circuit ID has no connection to what is in the provisioning system and asked how do Eschelon or other CLECs know that their circuit IDs are correct. Pat Finley said that the Cbeyond issue was corrected. Stephan said he is suspicious and concerned that this could happen elsewhere and the circuit ID has been altered and is out of sync with billing and provisioning. Stephen added he is unsure how to protect Cbeyond. Pat said that she did not know of other instances where this was occurring and that the problem was isolated to one or two individuals in the center who were then covered on the correct procedures.

Stephan said reconciling the invoice, knowing that potential is there not to reflect the correct circuit IDs, and there is not a dedicated rep for the Cbeyond orders. Pat said there is not a way to compare the provisioning system against the billing system because they are separate operating systems and would be glad to work on specific examples. Stephan said that the examples of the circuit ID not matching the FOC and SOC were given to their Service Manager.

Stephen asked if the TRAK FID was as far as Qwest would go to resolve this CR. Pat answered that separate classes of service would not be provided and the PCAT changes identifying the USOCs used for LMC and EEL and the TRAK FID were done to address the CR.

Stephan asked if certain USOCs descriptions would be included in the billing because they are seeing inconsistencies. On EEL orders they see UNE-P USOCs. Pat said that some USOCs used may be private line and borrow many USOCs. Stephan said he sent the examples but these may have gone only to the service manager. Kit said we would get with the service manager to investigate.

Jen Arnold with U S Link said the man number on the circuit ID changes and they are finding, particularly in a re-use situations, the man number may be the same for more than one circuit ID. This was brought to service management and has not been answered yet. Kit said there was no one on the call to answer the question and said they should wait to hear from service management.

Bonnie Johnson said she is generally frustrated whenever there is an issue or problem that the CLEC must submit a CR, ask for documentation, etc. and would like to see Qwest take a more active role is resolving issues. Qwest has an obligation to let CLECs know when something has been found through the discovery process, or through researching a CR, and should get the problem fixed for all CLECs. Donna Osborne-Miller said this seems to be a reasonable request and Qwest should notify the CLECs. Bonnie said we can discuss off line where to go to get Qwest to take a more active approach. This CR will move to CLEC Test status.

03/17/04 March CMP Meeting Pat Finley with Qwest said that an ad hoc meeting was held on 3/5/04 to address concerns raised by Stephan Calhoun with Cbeyond. Tom Hyde with Cbeyond attended the call for Stephan. Pat reviewed that the CR was submitted asking for separate classes of service for EELs and LMCs. Pat explained that the TRAK FID uniquely identifies EEL & LMC. Cbeyond had 14 instances where the conversion of circuits from private line was done incorrectly and orders were issued to correct the circuit IDs. Pat said Interstate classes of service are not being assigned on new installations of service and the interstate classes of service were used for the conversion of private line. Qwest has no plans to charge higher rates for interstate vs. intrastate and UNE’s are billed at TELRIC rates. PCAT changes were issued in February to provide a download to map USOCs and class of service. During the ad hoc meeting, Tom said he had not reviewed the changes. Liz Balvin with MCI asked if training would be reinforced to eliminate errors from occurring. Pat said that training has been provided to the center to make sure the correct processes are followed. Liz added that monthly training might be helpful because of turnover in representatives inputting the orders. Pat said that she would suggest monthly training to the process person. Bonnie Johnson with Eschelon said that if Cbeyond had problems with inaccuracies in circuit IDs that there may have been other CLECs with the same problem and asked if a review was done. Pat said that a report was pulled for all customers. Bonnie asked if corrections and credits had been done. Pat said corrections and credits were given if appropriate. This CR will move to Development status.

- Ad Hoc Meeting Minutes PC112003-1 March 5, 2004 1-877-572-8687, Conference ID 3393947# 9:00 a.m. - 10:00 a.m. Mountain Time

List of Attendees: Tom Hyde - Cbeyond Kathy Stichter - Eschelon Kim Isaacs - Eschelon Rodney Johnson - SBC Pat Finley - Qwest Robyn Libadia - Qwest Gayla Samarripa - Qwest Sami Hooper - Qwest Jennifer Fisher - Qwest Susie Johnson - Qwest Sue Kriebel - Qwest Peggy Esquibel-Reed - Qwest Lynn Stecklein - Qwest Linda Sanchez-Steinke - Qwest

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss CR PC112003-1 agenda topics: - Qwest will not establish separate Class of Service for EEL & LMC - Qwest assigning interstate Classes of Service on new EEL/LMC requests - Determine if EEL/LMC services established as new connect or conversion - Jurisdiction of EEL/LMC - EEL/LMC XUMAX Interstate, UBNWN Intrastate Rates - PCAT updates

The following is the write-up of the discussions and action items from the working session.

- Qwest will not establish separate Class of Service for EEL & LMC. Pat Finley with Qwest explained that separate classes of service will not be provided for EEL and LMC. Qwest has developed the TRAK FID on the CSR which identifies EELs and LMC circuits. Pat added that Qwest will not count LMCs in the calculation of LIS trunking to EEL ratio.

- Qwest assigning interstate Classes of Service on new EEL/LMC requests. Pat Finley said that Qwest did have a deviation from the process and orders for the conversion were issued with Interstate classes of service. Additional training has been provided to the center and the center is in the process or writing orders to correct. Tom Hyde with Cbeyond said that he is concerned that UNE billing deviates from Telcordia standards with respect to USOCs. Pat said the EEL and LMC PCATs have been updated to include a download of USOCs for interstate and intrastate. Tom said that he has not reviewed the PCAT. Sami Hooper with Qwest said that the Chan Term is the same as special access but has a unique class of service and ZCID. Tom Hyde said that the rate is driven by the ZCID. Sami said that the rate is driven by class of service, USOC and the company code or ZSID makes the rate unique. Tom said he is concerned that class of service is irrelevant to billing of basic Chan Term which is a finished service. Pat said that the company code makes rating unique and several UNEs borrow retail USOCs. The interconnection agreement provides rates. Tom said he was concerned that the PCAT will be ambiguous, an audit of billing will provide different information and the only method to audit is a manual method. The interoffice mileage and fixed charges are charged incorrectly. Pat said the USOC definitions will be the same and this is not unique to LMC and EEL. The rating is done per the interconnection agreement. Susie Johnson said that Gia is correcting the incorrectly billed multiple fixed mileage charges.

- Determine if EEL/LMC services established as new connect or conversion. Tom said that Qwest has asked him to identify which were new connect circuits and which were converted circuits and that everything was being assigned Interstate. Pat said that Qwest knows how the services were established, either new connect or conversion.

- Jurisdiction of EEL/LMC. Pat Finley said that 14 circuits have the incorrect circuit ID and are being corrected via record orders.

- EEL/LMC XUMAX Interstate, UBNWN Intrastate Rates. Pat Finley said that Qwest has no plans to charge a higher rate for interstate vs. intrastate and UNE’s are billed at TELRIC. Tom Hyde said he doesn’t care for CRIS billing for UNE-P, that it was probably ok a couple years ago and is causing grief because of the lack of consistency and manual work involved to audit bills. CRIS billing is not part of CMP CR PC112003-1 and was not discussed further.

- PCAT updates. Pat Finley said the PCAT was updated and provides a download to map USOCs and class of service. Tom said he has not reviewed the changes made to the PCAT. Pat said that the combination of USOCs are unique. Sami said that is correct and the PCAT identifies the nonrecurring USOCs and the FID identifies if EEL or LMC. LMC has no mileage. Tom said that the bill will subtract LMC mileage and it was billed in error, identified in manual audit. Pat said that if orders are issued correctly the ZCID, etc. drives billing. Pat explained that establishing a new unique classes of service for LMC is cost prohibitive due to the conversion required to the embedded base. Tom said that a new USOC can’t be cost prohibitive. Tom added that the circuit ID is being corrected and has helped.

There were no additional questions and Linda said that meeting minutes would be provided in the body of the change request.

02/18/04 February CMP Meeting Pat Finley with Qwest said the examples Cbeyond provided following the January meeting were examples of circuits with jurisdiction based on the class of service. There were hundreds of circuits converted correctly via record orders and the 10 circuits provided as examples were issued incorrectly, and required record orders to fix. Pat explained that the PCATs for EEL and LMC were updated and now contains a downloadable list of USOCs for interstate and intrastate. The USOC list, combined with the TRAK FID on the CSR differentiates LMC and EEL and there is no need to establish separate classes of service. The work associated with establishing separate classes of service is prohibitive because of the conversion to the embedded base.

Pat said that the e-mail received from Stephan Calhoun on 1/22/04, confuses the request with other CRs requesting billing changes and believe that this CR can be closed.

Stephan Calhoun with Cbeyond said the PCAT updates are appreciated and that he was only able to review the Qwest response on this CR yesterday. Stephan said he has concerns with the 2/3/04 Qwest response and asked that Pat read through the response.

Pat read the draft response. Stephan said that his understanding is that usually classes of service define the product but not the jurisdiction. Pat disagreed saying that the jurisdiction of many Qwest products is identified by class of service.

Stephan also said that interstate class of service was assigned to conversion orders that were issued last year, are also being assigned on new requests for EEL and LMCE. Pat said that the interstate EEL and LMC classes of service are only used to convert to Special Access circuits.

Stephan said that he doesn’t understand the reason UMX was changed to new EEL and LMC. Cbeyond has not made any changes in the way the services were ordered. Pat Finley said that interstate was only used for conversion orders only.

Stephan said that Cbeyond is concerned that billing doesn’t support the Qwest response. The billing department was not able to identify what was converted and what was a new order. There seems to be a disconnect with the policy and what is actually done. Pat explained that the Billing Center is able to access history information on the services, and to tell what is new and what was converted. Stephen said that the billing manager, service manager and process manager were unable to determine and planned to contact the product manager. Stephan has provided examples to their service manager.

Stephan is also concerned that the recurring interstate and intrastate EEL do not bill the same as UNE. Pat said that PLT has different rates and is a finished service. Interstate and intrastate EEL and LMC are billed the same recurring rates. Stephan said LMC jurisdiction is based on FCC definition and doesn’t seem to fit. Stephan said the concern is not the rate itself, but the rate elements, and asked what would keep Qwest from applying different rates to interstate and intrastate. Pat asked if the concern is that Qwest may raise UNE rates that are interstate. Pat explained that Qwest is obligated to make these UNEs available to CLECs at TELRIC rates.

Judy Schultz with Qwest said there are many concerns with this CR and suggested that an ad hoc meeting be scheduled to discuss. This CR will remain in Evaluation status.

Thu 1/22/04 3:41 PM From; Stephan Calhoun [Stephan.Calhoun@cbeyond.net] To: Sanchez Steinke, Linda, Finley, Pat J cc; Morgan Halliday, Tom Hyde Subject; RE: Qwest Draft Response PC112003-1 (Differentiate LMC from EEL) - Cbeyond Response Linda/Pat,

I apologize for not getting this to you prior to yesterday's call. I got wrapped up in some other Qwest CRs that we received responses to at the same time. It appears that Qwest has addressed the regulatory concerns raised by the TRO in its response to this CR. Unfortunately, the billing implications on this CR appear to have been forgotten. Cbeyond has 3 specific concerns to Qwest's response:

1. Providing fields on the CSR for services that are billed in CRIS is not the same as for services billed in IABS. In the CRIS system, the CSR is not part of the bill. The CSR is provided as a separate file that is not in the same format as the invoice and is also not an OBF/industry standard format. Even this is a bit of a misnomer, the CSR is actually a collection of files per subaccount on an invoice. If an invoice has 2,000, the CSR is actually comprised of 2,000+ files. This is a partial explanation of why Cbeyond considers the delivery of information on the CSR as insufficient in addressing the billing concern of this CR.

2. Qwest has demonstrated through reports from the billing group (because Qwest doesn't actually put the class of service on the bill), that it uses or appears to use 2 different classes of service and thus 2 different sets of USOCs for the same bandwidth level, product, and jurisdiction as it applies to EELs and LMCs. Please find the attached examples.

3. An even broader concern, and perhaps the subject of another CR, is that Qwest has failed to map the USOCs & Classes of Service that it bills for LMCs & EELs to a product. Conversely, the PCATs for LMCs and EELs do not define the classes of service or USOCs to be applied to the elements that define each product. Obviously, Qwest has this defined somewhere in their system, but has failed to publish it to the CLEC community.

Again, I apologize if my comments caught you off guard as that was truly not my intent. I only saw the Qwest response the morning of the call and grew very concerned about what the response did not address.

Sincerely, Stephan

01/21/04 January CMP Meeting Pat Finley with Qwest said that Qwest held the Clarification meeting on 12/4/03 and that Qwest had sent an e-mail to Morgan Halliday stating that Qwest does not count EELs in the LMC ratio to LIS trunking. Pat reviewed the Qwest response and said that we will not establish unique classes of service for EELs and LMCs and that Qwest has created a way to distinguish EEL and LMC for the TRO by using TRAK FID. The TRAK FID information is available for CLECs on the CSR. Pat said that Qwest needed to distinguish between EELs and LMCs and has no intention of counting LMCs in the LIS trunking ratio.

Stephen Calhoun with Cbeyond said he is confused by the response because in December he received one answer and then in January received another answer. The CSR is not part of the bill and is not populating the difference between EEL and LMC on the bill. It is a different process to view the CSR as opposed to looking at the bill. The Cbeyond concern is based on reports received from the billing team where LMCs and EELs have different classes of service and USOCs. LMCS or EELs could be either class of service. Stephen will provide examples.

Pat Finley said there are 12 classes of service and they vary according to whether service is intrastate or interstate and the bandwidth requested. Stephen said these are brand new DS1 level, local installs and they have different classes of service assigned. In addition, when reviewing the PCAT there is a lack of documentation because LMC and EEL have no USOC mapping available to see the classes of service. Bonnie Johnson said that in reconciling bills, Qwest provides data is in so many different places, and there is a general concern that bills don’t provide enough detail to reconcile. (Begin comment from Bonnie Johnson – Eschelon) Bonnie said all of her personnel vendor bills contain the detail you need to know what you are paying for. (end comment). Carla Pardee with AT&T and Liz Balvin with MCI said they agree with Bonnie’s comments. This CR will move to Evaluation status.

Mon 1/5/04 1:12 PM From; Linda Sanchez-Steinke To; 'tom.hyde@cbeyond.net' cc: Pat Finley Subject; Change Request PC112003-1

Tom -

The attached e-mail was sent to Morgan Halliday a couple of weeks ago regarding change request PC112003-1, titled "Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)". I realize that with the holidays Cbeyond may not have had an opportunity to respond.

Would you please let me know if Pat Finley's attached e-mail provides the information needed to resolve the change request or if the change request is still needed.

Thank you

Linda Sanchez-Steinke Change Request Project Manager Qwest 303-382-5768

--Original Message-- From: Finley, Pat J Sent: Tuesday, December 16, 2003 4:43 PM To: 'morgan.halliday@cbeyond.net' Cc: Sanchez Steinke, Linda; Libadia, Robyn; Romano, Anthony Subject: Qwest's response to PC112003

Mr. Halliday, I wanted to provide you a formal response to the primary concerns you raised on the clarification call we had on December 4, 2003, for the Change Request titled "Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)." You asked that Qwest provide you in writing, assurances that we will not count Loop-MUX combinations (LMCs) in the calculation of LIS trunking to EEL ratio, to determine service eligibility. Please consider this written confirmation, that Qwest has no intention of counting LMCs in the calculation of the LIS trunking to EEL ratio as specified in the service eligibility criteria of the Triennial Review Order. We hope this satisfies your request. Please contact me at 303 896-8466, if you have any questions.

12/17/03 December CMP Meeting Cbeyond presented this CR and said Cbeyond would like to be able to differentiate LMX and EELs class of service on billing invoices. Liz Balvin with MCI asked how they come on the bills today. Stephen Calhoun said that Qwest provides Cbeyond additional information on a spreadsheet to help differentiate, and Qwest does not have the ability to separate LMX and EEL class of service. Jamal Boudhaouia with Qwest asked if Cbeyond orders LMX by itself, or if it is part of the whole circuit being provisioned. Stephen Calhoun said there are definite differences and if look at two DS1’s there is no differentiation between LMX and EEL and there are many implications, TRO order, Performance Management Plan, Regulatory side and billing. Jamal asked if the CR is based on the TRO order and if Cbeyond is asking for differentiation between the classes of service because of TRO implications. Judy Schultz with Qwest said that we may need another clarification meeting to get clear what the CR is requesting. Bonnie Johnson with Eschelon said that she was at the clarification meeting and felt that the CR request was clear. Kit Thomte said that Pat Finley the SME was not on the call and Kit felt that the discussion wasn’t helpful if she was not involved in the discussion. This CR will move to Presented status.

Tue 12/16/03 4:43 PM From; Pat Finley To; 'morgan.halliday@cbeyond.net' cc: Sanchez Steinke, Linda; Libadia, Robyn; Romano, Anthony Subject; Qwest's response to PC112003 Mr. Halliday, I wanted to provide you a formal response to the primary concerns you raised on the clarification call we had on December 4, 2003, for the Change Request titled "Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)." You asked that Qwest provide you in writing, assurances that we will not count Loop-MUX combinations (LMCs) in the calculation of LIS trunking to EEL ratio, to determine service eligibility. Please consider this written confirmation, that Qwest has no intention of counting LMCs in the calculation of the LIS trunking to EEL ratio as specified in the service eligibility criteria of the Triennial Review Order. We hope this satisfies your request. Please contact me at 303 896-8466, if you have any questions.

CLEC Change Request Clarification Meeting

2:00 p.m. (MDT) / Thursday December 4, 2003

1-877-572-8687 3393947# PC112003-1 Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)

Name/Company: Morgan Halliday, Cbeyond Tom Hyde, Cbeyond Stephen Calhoun, Cbeyond Kim Isaccs, Eschelon Bonnie Johnson, Eschelon Pat Finley, Qwest Carl Sear, Qwest Tony Romano, Qwest Paul Johnson, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested (Description of) Change Linda Sanchez-Steinke with Qwest read the description of change from the submitted change request; Seperately identify LMCs and EELs on bills. Tom Hyde with Cbeyond said that the primary part of the TRO is the ratio of, or test for EELs (high cap) to LIS trunking with the new service eligibility criteria. Since Qwest uses the same classes of services and USOCs for EELs and LMCs as are used for PLTS. Pat Finley with Qwest clarified that the TRO ratio is the number of interconnection trunks to EELs, however LMCs (Loop Mux Combinations) are excluded from the ratio requirement. Tom answered that Cbeyond would be satisfied if Qwest will acknowledge in writing that LMC is to be excluded from the service eligibility criteria (safe harbor), and therefore would be excluded from the LIS trunking to EEL ratio, that would satisfy Cbeyond’s concern.

In the CPAP Qwest is lumping EELs and LMCs together. Tom said that Qwest is the only ILEC that has EELs and LMCs under the same class of service.

Confirm Areas & Products Impacted Loop Mux Combo and EEL billing

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting

Identify/Confirm CLEC’s Expectation Extablish different class of service for LMCs and EELs

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) Cbeyond will present this CR at the December CMP meeting. Qwest will provide a response in January 2004.


CenturyLink Response

February 3, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the February 2004 CMP Meeting

Morgan Halliday Cbeyond Communications, LLC

SUBJECT: Qwest’s Change Request Draft Response - PC112003-1 "Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)"

This letter is in response to the CLEC Change Request PC112003-1, that requests LMC (Loop Mux Combination) be assigned a unique class of service, to separately identify LMC from EEL (Enhanced Extended Loop) due to requirements in the Triennial Review Order (the Order). Qwest will not establish a separate class of service for LMC. Qwest will provide a link to a downloadable document in both the EEL and LMC PCATs that will identify USOCs that are utilized with XUMAX and UBNWN classes of service. This action will enable our customers to map EEL/LMC classes of service to USOCs for billing. The estimated costs to establish a separate class of service for LMC and convert the embedded base are considerable. Establishing a separate LMC class of service will not solve all of the billing issues Cbeyond has raised in subsequent meetings on this Change Request.

In the email Mr. Calhoun sent to Qwest dated 1-22-2004, he listed examples of EEL and LMC circuits that have two different classes of service (interstate and intrastate) with two different sets of USOCs for the same bandwidth, product and jurisdiction. When Cbeyond’s PLT (Private Line Transport) circuits were converted to either EEL or LMC, the jurisdiction, circuit id, and billing USOCs remained the same as when billed and provisioned as PLT circuits. To prevent service interruptions during the conversion, the class of service on the PLT record is converted to the EEL/LMC equivalent. There is no difference in recurring billing between the inter- and intrastate EEL/LMC classes of service and USOCs. The use of both retail and EEL/LMC product specific USOCs is explained in detail in the LMC and EEL PCATs.

In addition to the downloadable spreadsheet we will make available in the PCATs, we have established the TRAK FID and datasets that allow you and Qwest to differentiate between LMC and EEL. With this differentiation, Qwest will not include LMC circuits in your LIS to EEL ratio requirements per the Order service eligibility requirements. We believe these actions will address your specific concerns with billing associated with EEL and LMC. Your other pending change requests will help resolve the other issues you have raised with Qwest’s bills.

Sincerely,

Pat Finley Product Manager

January 13, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the January 2004 CMP Meeting

Morgan Halliday Cbeyond Communications, LLC

SUBJECT: Qwest’s Change Request Response - PC112003-1 "Differentiate between Loop-MUX combos and EELs due to different FCC treatment (TRO Order)"

This letter is in response to the CLEC Change Request PC 112003-1, that requests EELs (Enhanced Extended Loops) and LMCs (Loop Mux Combinations) be assigned unique classes of service, to separately identify the services due to requirements of the Triennial Review Order (the Order). Qwest has researched this issue, and we will not be establishing separate classes of service and USOCs (Universal Service Order Codes) for EELs and LMCs. We have however, provided a method for you to validate, or identify EEL from LMC circuits, by using a FID (Field Identifier) called TRAK, which is a tracking code. If the circuit is an EEL, the dataset, or entry following TRAK FID on the CSR (Customer Service Record) will be IEEL. This entry will be shown following the class of service on the CSR. LMC circuits will be identified by the dataset ILMC after the TRAK FID. This information has been added to all EEL and LMC accounts in our embedded base, and it is a required service order entry on new EEL and LMC requests. We are able to produce reports that display the information, and we are working on producing reports from our order processing system to ensure the entries are appropriately made, when required. We are confident that this will allow us to validate the 24-to-1 EEL to interconnection trunk ratio specified in the Order (paragraph 608). Please recall that the Order provides for tests based on the service eligibility criteria conducted by an independent auditor to insure that high capacity combinations such as DS1 and DS3 EELs are used for local voice service. As noted in the Order, if Qwest requests an audit, the independent auditor will evaluate compliance with the service eligibility criteria. The compliance testing will be designed by the independent auditor, and Qwest will provide all documentation requested to satisfy standard auditing principles. The independent auditor will perform an "examination engagement", and issue an opinion regarding Qwest’s and the CLECs compliance with the service eligibility criteria (paragraph 626).

Sincerely,

Patricia J. Finley Product Manager Qwest Communications, Inc.


Open Product/Process CR PC120605-1EX Detail

 
Title: EEL Maintenance Window Change
CR Number Current Status
Date
Area Impacted Products Impacted

PC120605-1EX Completed
3/20/2006
Provisioning EEL
Originator: Hyde, Tom
Originator Company Name: Cbeyond Communications
Owner: Libadia, Robyn
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Perform a change to an existing EEL circuit during maintenance window (after 10PM MT)

Expected Deliverable:

Exception required due to short interval Loop Concentrator Multiplexer (LCM)..


Status History

12/06/2005 - CR Submitted As An Exception Request. Pre Meeting and Exception Meeting was Requested.

12/07/2005 - Acknowledged CR and Exception Request.

12/08/2005 - CMPR.12.08.05.F.03549.ExceptionRequest_PreMtg

12/12/2005 - Exception Pre-Meeting Held

12/13/2005 - CMPR.12.13.05.F.03564.ExceptionVoteRequired

12/14/2005 - Discussed in the Monthly Product/Process CMP Meeting, as a Walk-On.

12/29/2005 - Exception Vote Held

01/06/2006 - CMPR.01.06.06.F.03605.ExceptionVoteDisposition

01/18/2006 - Discussed in the Monthly Product Process CMP Meeting

01/19/2006 - PROD.01.19.06.F.03629.EEL_LMC_Out_of_Hours (Level 2)

01/19/2006 - PROD.01.19.06.F.03631.TRRO_EEL_and_LMC

02/02/2006 - CMPR.02.02.06.F.03677.AdHocMeeting_PC120605-1EX

02/09/2006 - Ad Hoc Meeting Held

02/09/2006 - Status changed to CLEC Test due to the implementation on February 9, 2006.

02/09/2006 - PROD.02.09.06.F.03695.TRRO_EEL_LMC_OutHours_Upd

02/09/2006 - PROD.02.09.06.F.03693.EEL_-_LMC_OutHours_Update (Level 1)

02/15/2006 - Discussed in the Monthly Product Process CMP Meeting

03/02/2006 - PROD.03.02.06.F.03735.EEL_LMC_Rearrangemnt (Level 1 Product Notice)

03/02/2006 - PROD.03.02.06.F.03737.TRRO_EEL_LMC_Rearrgmnt (Product Notice)

03/15/2006 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

March 20, 2006 Email Received from Cbeyond: I’m OK to close

- March 20, 2006 Email Sent to Cbeyond: Good Morning Tom, The CLEC that had an issue regarding MN was okay to close the CR. They are pursueing via other avenues and were okay with the CR closing. I believe that really does close the CR in it's entirety. Please let me know if you are in concurrence to closing out the CR. I have attached a copy of the CR. It contains a copy of the email received from the CLEC that had objected to the closure, and then provided the approval to close. Thank you Peggy Esquibel-Reed Qwest Wholesale CMP

-- March 20, 2006 Email Received from Cbeyond: Peggy: I’m fine with closing for Colorado. I understand that there were some CLECs that were concerned with keeping open for MN.

-- March 17, 2006 Email Sent to Cbeyond: Hello Tom, This email is to ask if you have any objection to closing your CR PC120605-1EX EEL Maintenance Window Change. This change was effective on February 9th. During the March 15th CMP Meeting, there was no objection from the CLEC Community to the closure. Please let me know if the CR can be closed or if you feel that it needs to remain in CLEC Test. If you are not yet ready to close the CR, will you please provide me with details as to what issues you are having in regard to this change? I will then do some reasearch and assist with any problem resolution. Thanks, Tom. I hope to hear from you soon. Peggy Esquibel-Reed Qwest Wholesale CMP

- March 15, 2006 Email Received from Eschelon: Hello Jill, I had a chance to speak with Bonnie regarding our objection to the exclusion of MN for this product. You can close the change request if no other CLECs have an objections. Eschelon is pursuing other avenues to address our concerns. Thanks an have a great evening. Kim Isaacs Eschelon Telecom, Inc.

-- March 15, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this effort was implemented on February 9th and noted that all the submitted questions have been responded to. Jill asked if this CR was ready to be closed. Kim Isaacs-Eschelon stated that Eschelon has a standing dispute in Minnesota and would like the CR to remain open. Jill Martain-Qwest stated that Qwest does not have the capability to provide this in MN at this time and stated that she can have a conversation with Eschelon. Kim Isaacs-Eschelon stated that the MN Commission stated that there are steps that Qwest could take to offer in MN and that the Commission did not anticipate Qwest not making the offer in MN. Jill Martain-Qwest stated that she would check into it and then she could have a discussion off-line with Eschelon. Kim Isaacs-Eschelon asked that Qwest provide them with the information regarding the steps Qwest is taking for Minnesota. Jill Martain-Qwest said okay. This CR remains in CLEC Test. NOTE: After the CMP meeting, Eschelon submitted an e-mail to Qwest stating that they were OK to close the CR if there we no other objections from other CLECs. Qwest will check with Cbeyond off-line to see if the CR can be closed.

-- March 1, 2006 Emails Sent to Eschelon (Kim Isaacs) and McLeod (Chelsea Payne): In regard to your request associated with notification PROD.02.09.06.F.03693.EEL-LMCOutHoursUpdate, Qwest is not refusing to offer UNEs in Minnesota. The issue is that Qwest does not have approved rates in Minnesota that can be charged to install or rearrange EEL outside of the normal business hours. Qwest is in the process of investigating next steps. Until such time that Qwest has the ability to charge an appropriate non-recurring rate in MN, Qwest is not offering the ability to provision new or rearrange existing EEL circuits outside of normal business hours. Qwest continues to offer the ability to perform rearrangement and change orders on EEL circuits during normal business hours and will work with the CLECs to minimize any down time to their end user customers. Thank you, Susan Lorence Qwest CMP Manager

- February 21, 2006 Email Received from McLeod: McLeodUSA objects to the level 1 change announced on February 9, 2006 (Document #PROD.02.09.06.F.03693.EEL-LMCOutHoursUpdate related to CLEC CR# PC120605-1EX) regarding the inability to schedule EEL coordinated project installations out of hours due to the fact that rates have not been established in a given area. McLeodUSA specifically would like to note this objection in the state of Minnesota. While Qwest may not have a Commission approved rate in Minnesota, this should have no bearing on whether or not this service should be offered to McleodUSA. The Commission issued an order dated 10-2-2002 on Docket: P-421/CI-01-1375 which provided a process for Qwest to address new UNE prices and prices under development which includes Qwest submitting a cost study to get their rate - not do deny CLECs access to the product. Based on this order, McleodUSA requests that Qwest offer EEL Out of Hours installations in Minnesota and update the PCAT language to indicate that in states that do not contain the appropriate rates that Qwest will negotiate a rate with the CLEC. Thank You, Chelsea Payne

February 20, 2006 Email Received from Eschelon: At the 2-9-06 PC120605-1EX EEL Maintenance Window Change ad hoc call, Qwest announced that Qwest would withdraw its EEL Out of Hours Installations offering in the state of Minnesota because Qwest failed to establish commission approved rates in the Minnesota. Eschelon expressed our concerns with Qwest's position on the ad hoc call but we agreed to allow the change request to move forward in the other states, so that Qwest’s change in its position in MN would not delay CBeyond’s request in other states. On the call, Eschelon reserved our rights to comment and object to Qwest's position. Eschelon submits this objection. While Qwest currently may not have a Commission approved rate in the Minnesota Exhibit A, the Minnesota Commission addressed this issue in its order dated 10-2-2002 on Docket: P-421/CI-01-1375. The Minnesota Commission did not provide that Qwest would simply refuse to offer UNEs and services in Minnesota. The Minnesota Commission found that Qwest has an “obligation to provide all of its UNEs and services at just, reasonable and nondiscriminatory rates pursuant to the Act’s $9 201(b) and 202(a)”[1]. Furthermore, the Minnesota Commission provided a process to address new UNE prices and prices under development. The proper process is for Qwest to submit a cost study and get a rate not to deny CLECs access to the product.

Based on the Minnesota Commission order, Eschelon requests that Qwest offer EEL Out of Hours installations in Minnesota and update the PCAT language to indicate:

If this offering is not included in your current ICA, an amendment will be required. Out of Hours Project Coordinated Installations are offered in states that contain the appropriate rates found under Miscellaneous Charges in Section 9.20 of Exhibit A for the specific state. In states that do not contain the appropriate rates found under Section 9.20 of Exhibit A Qwest will negotiate a rate with the CLEC. In Minnesota, Qwest needs to file a cost study for this rate.

[1] 10-2-2002 MN Commission Order Docket: P-421/CI-01-1375

Thank you. Kim Isaacs Eschelon Telecom, Inc.

February 15, 2006 Monthly Product Process CMP Meeting Discussion: Robyn Libadia-Qwest stated that Qwest began offering the out of hours for EEL & LMC on February 9th. Contract language was updated and is posted. Robyn noted that there was an ad hoc meeting that was held on February 9th in order for Qwest to further clarify the offering. Robyn then stated that an amendment would be required and that it is available for the states that have the appropriate rates. Robyn stated that would be all states with the exception of Minnesota. Robyn stated that during the February 9th ad hoc meeting, there was agreement that a Level 1 Notice would be sent on February 9th, with an effective date of February 10th. Robyn then noted that the CR is in CLEC Test. Bonnie Johnson-Eschelon stated that she had indicated on the ad hoc call that she was okay with a Level 1 Notice so that Cbeyond could take advantage, but that Eschelon could have concerns regarding the Minnesota issue. Bonnie then noted that Kim (Isaacs-Eschelon) will send information to the CMP CR mailbox. Jill Martain-Qwest stated that based on the discussion, the CR would remain in CLEC Test for another month.

February 9, 2006 Ad Hoc Call (CMPR.02.02.06.F.03677.AdHocMeetingPC120605-1EX) ATTENDEES: Tom Hyde-Cbeyond, Julie Pickar-TDS MetroCom, Rosalin Davis-Verizon Business, Bonnie Johnson-Eschelon, Kim Isaacs-Eschelon, Laurie Fredricksen-Integra, Janie Williamson-Integra Peggy Esquibel Reed-Qwest, Susan Lorence-Qwest, Jill Martain-Qwest, Sami Hooper-Qwest, Ev Montez-Qwest, Vicki Dryden-Qwest, Chris Quinn Struck-Qwest DISCUSSION: Peggy Esquibel Reed-Qwest stated that today’s call was scheduled in order to communicate some information regarding the CMP Change Request submitted by Cbeyond, PC120605-1EX; EEL Maintenance Window Change. The request was asking that a change to an existing EEL circuit could be performed after 10:00 p.m. MT. The CR was submitted as an exception request, for implementation in a shorter then normal timeframe. The exception vote was held in December and was granted. This CR was then scheduled to be implemented on February 9th, which is today. Last week, we became aware of some information that we need to communicate to you and immediately scheduled this call in order to pass that information to you. Due to the timeframes in the CMP Document pertaining to the scheduling of ad hoc calls, today was the earliest that the call could be held. With that, I will turn the call over to Robyn Libadia, who will share that information with you. Robyn Libadia-Qwest stated that because this was an exception CR, a notice was sent to the CLEC Community. Robyn then noted that while developing the process it came to light that this offering would not apply for the state of Minnesota. For coordinated project installations scheduled to commence out of hours, or rescheduled by a CLEC to commence out of hours, additional nonrecurring charges will be applied to each EEL circuit for the work performed by Qwest outside of normal business hours. If this offering is not included in your current ICA, an amendment will be required. Robyn stated that the offering is still effective today, February 9th, but cannot offer the process in Minnesota. Robyn stated that clarification will be added to the EEL & LMC PCATs and stated that Qwest would like to issue a Level 1 Notice for the immediate clarification. Tom Hyde-Cbeyond stated that he was okay with the Level 1 Notice request. Robyn Libadia-Qwest asked if there were any other thoughts. Bonnie Johnson-Eschelon asked to clarify that Qwest offered out of hours for other products in Minnesota. Robyn Libadia-Qwest stated that could be and noted that she could only address products that she is responsible for. Robyn stated that in order to offer EEL & LMC, a cost docket will need to be filed and commission approval would be needed. Jill Martain-Qwest stated that Qwest still wanted to offer this process in as many states as possible. Bonnie Johnson-Eschelon stated that she was okay with a Level 1 Notice so Cbeyond could obtain benefit in Colorado. Bonnie then noted that she may later have comments regarding the change itself. Jill Martain-Qwest asked Bonnie to please send them to the CMP mailbox. Jill then stated that it sounds like Qwest is okay to proceed with the Level 1 Notice. There were no additional questions or comments. Peggy Esquibel Reed-Qwest thanked the call participants and adjourned the call.

- January 18, 2006 Monthly Product Process CMP Meeting Discussion: Robyn Libadia-Qwest stated that this CR had an exception granted via a vote and stated that the effort was moving forward to implement out of hours coordinated installs for EEL and LMC products. Robyn stated that the PCAT updates had been completed and would be published on January 23rd. She also stated amendment language had been drafted and would be made available. Robyn requested consensus from the CLECs to treat this CR as a Level 2 Notice so that Qwest could move forward with an effective date and implementation date of February 13th. There was no objection to the Level 2 Notice. Tom Hyde-Cbeyond asked when the amendments would be published. Robyn Libadia-Qwest stated that they would be published by the February 13th effective date. Tom Hyde-Cbeyond asked for the publication date. Robyn Libadia-Qwest stated that she did not yet have a date but that it would be no later than February 13th. Tom Hyde-Cbeyond stated that it would have to be published earlier. Tom stated that he would like sooner so he could have time to review them and make sure that they are acceptable. Robyn Libadia-Qwest stated that she would see if the request for earlier publication could be accommodated. Jill Martain-Qwest stated that all CLECs would need to have a signed amendment in order to participate. This CR moves to Development Status.

- December 29, 2005 Exception Vote Meeting Minutes: In attendance: Cindy Harlan-Qwest Sharon Van Meter-ATT

Cindy Harlan reviewed that the purpose of this meeting is to conduct the vote on PC120605-1EX to determine whether or not this CR will be handled as an exception CR. This vote was previously scheduled to take place on December 22, 2005, but quorum was not achieved at that time.

Cindy then conducted the vote: Sharon Van Meter - ATT advised her vote is yes Eschelon-yes via email TDS-yes via email Qwest Corporation-no via email Time Warner Telecom-yes via email

Cindy advised 2/3 majority vote of yes was received so this CR will be handled as an Exception.

-- December 14, 2005 Product Process CMP Meeting Discussion: Tom Hyde/Cbeyond stated that Cbeyond’s Interconnection Agreement currently allows addition of DS1 Loops and gives provisions for out of hour’s provisions to be done. Tom stated that his CR is to add EEL to the same provisions. Tom stated that he requested a walk-on to present the CR. Tom stated that Cbeyond needs the ability to meet Cbeyond’s TRRO requirements with a March 2006 deadline. Tom stated that he did not intend this CR to be a TRRO only change and noted that it is an ongoing change request. Jill Martain/Qwest stated that the vote is scheduled to take place on December 22nd. There were no questions or comments.

- Exception Pre-Meeting December 12, 2005 ATTENDEES: Kim Isaacs-Eschelon, Gary Tilley-McLeod, Jeff Raymond-McLeod, Kim Hartz-McLeod, Bonnie Johnson-Eschelon, Lynn Hankins-Covad, Tom Hyde-Cbeyond, Rosalin Davis-MCI, Peggy Esquibel Reed-Qwest, Robyn Libadia-Qwest, Jean Novak-Qwest, Sami Hooper-Qwest, Ev Montez-Qwest, Shirley Tallman-Qwest Peggy Esquibel Reed-Qwest stated that an exception change request was received from Cbeyond and that the purpose of this pre-meeting was to review the change request, answer questions, agree to the date/time for the vote meeting, and for Qwest to communicate what a vote of yes would mean and what a vote of no would mean. Peggy stated that Cbeyond is seeking an exception to the normal implementation timeline for this Level 4 change request. Peggy reviewed the CRs Description: (PC120605-1EX EEL Maintenance Window Change) the CR is asking Qwest to perform a change to an existing EEL circuit during maintenance window (after 10PM MT). Peggy then asked Tom Hyde (Cbeyond) if he had any other information regarding the request that they would like to share with the call participants, and also asked if he would share the business need that has prompted the exception request for a shorter implementation timeframe. Tom Hyde-Cbeyond stated that his CR is addressing a change from lower to higher loops, such as going from a DS1 to a DS1 Transport or from a DS1 to a DS3. Tom stated that the request is to prevent customer outages. Tom then stated that the CR was prompted due to TRRO. Tom stated that TRRO is the driver and noted that the deadline for conversions is March 11, 2006. Peggy Esquibel Reed-Qwest then asked if there were any questions regarding the CR. Bonnie Johnson-Eschelon asked Cbeyond if he is requesting that the EEL product to be able to make changes on EEL, whenever they are, after hours. Tom Hyde-Cbeyond stated that he submitted the request because EELs are silent in their Interconnection Agreement. Tom then stated that DSI Loops currently say that it can be done out of hours and Cbeyond is now looking for out of hours conversions and coordination in order to prevent end user downtimes. Tom stated that Voice Grade is not included in the request because Voice Grade is seldom isolated. Tom Hyde-Cbeyond then noted that TRRO is the driver of the exception request and stated that Cbeyond would have made the request anyway. Tom stated that it is not equitable to do for some products but not for EEL. Bonnie Johnson-Eschelon stated that Eschelon had recently run into the same situation, but was not TRRO related, changing from one central office to another. Bonnie then asked if this Cbeyond CR included that and would care for it. Tom Hyde-Cbeyond stated that his CR is for converting from EEL to non-EEL. Bonnie Johnson-Eschelon asked if EEL to EEL was outside of hours. Tom Hyde-Cbeyond stated that the CR is generic and that it should fall under that. Robyn Libadia-Qwest stated that the implementation of the request would be generic as well. Tom Hyde-Cbeyond asked with the vote being on December 22nd, when Qwest would be implementing the requested change. Peggy Esquibel Reed-Qwest stated that the vote does first need to be conducted and based on the outcome of the vote, will need to then go back and determine, from a CMP perspective, when the requested change could be implemented. Peggy Esquibel Reed-Qwest stated that the vote is scheduled to occur on December 22, 2005 at 1:00 p.m. MT. Peggy then noted that emailed votes would be accepted up until that date and time. Peggy stated that the reminder regarding the email option for votes is for those who will be on vacation and stated that the Vote Notice and Ballot would be out tomorrow. There was no dissent to the date and time for the vote meeting. Peggy then stated that a vote of ‘yes’ will indicate a preference to allow PC120605-1EX, EEL Maintenance Window Change, to be implemented prior to the normal implementation timeline for this Level 4 Change Request. A vote of ‘no’ will indicate a preference that PC120605-1EX, EEL Maintenance Window Change, not be implemented prior to the normal implementation timeline. Peggy asked if there were any questions regarding the yes/no vote. There were no questions. Peggy then noted that according to the CMP Process, a 2/3majority vote will be required for this Exception Request to be granted and that the vote would be on December 22nd and per the request of Cbeyond, the CR would be posted to the Wholesale CMP web site to be a walk-on for this Wednesday’s CMP Meeting.


Open Product/Process CR PC030618-1CM Detail

 
Title: CMP Document Update to Eliminate the Technical Escalations Contact List
CR Number Current Status
Date
Area Impacted Products Impacted

PC030618-1CM Completed
5/16/2018
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is proposing that the Technical Escalations Contact List that is posted to the external web page at https://www.centurylink.com/wholesale/systems/productionsupport.html be eliminated. The Technical Escalations Contact List is referenced in the CMP document under Section 5.4.3 – Level 2 Changes.

• The Technical Escalations Contact List provides both CLEC and CenturyLink Technical Contact information.

• Similar to the POC reports, the CLEC information has received minimal updates since the creation of the Technical Escalations document in 2002.

• The CenturyLink Technical Escalation List is not used by customers.

• If there was a technical escalation by a customer, it would most likely go through the Service Management team or the Wholesale Systems Help Desk.

Here is the proposed update to the Change Management Process document:

5.4.3 Level 2 Changes

Level 2 changes are defined as changes that have minimal effect on CLEC operating procedures. CenturyLink will provide notification of Level 2 changes at least twenty-one (21) calendar days prior to implementation.

Level 2 Change Categories are:

• Contact Information updates excluding time critical corrections (Expedites and Escalations Overview (http://www.CenturyLink.com/wholesale/clecs/exescover.html), Wholesale Customer Contacts (http://www.CenturyLink.com/wholesale/clecs/customercontacts.html), DELETE Technical Escalations Contact List (http://www.CenturyLink.com/wholesale/systems/productionsupport.html) END DELETE, CMP Points of Contact (POCs, CenturyLink POC changes only) http://www.centurylink.com/wholesale/cmp/index.html

This CR is part of the Simplify CMP effort in 2018.


Status History


Project Meetings

5/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR is associated with a Technical Escalations Contact that had never been used on the CenturyLink side and was out of date on the CLEC contents. The vote was taken last month with unanimous agreement to make the change to remove the Technical Escalation contact list. Mark referenced Page 24 of the CMP distribution package that contained the various notices that were distributed associated with the change. Some additional outdated documents were also archived. The CR is now in CLEC Test as of May 7, 2018, and we would like to move it to a Completed status. He asked if there were any objections. There were none.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR is associated with a Technical Escalations Contact that has never been used on the CenturyLink side and is out of date on the CLEC contents. An Ad Hoc Call was conducted April 2, 2018 due to customer comments. Call participants agreed upon the proposed CMP Document update. The CMP Vote notification was issued on April 4, 2018 for the April Monthly Meeting and is included in the package along with the ballot. Mark stated that the quorum for the was the same and asked Susan to take the vote.

Susan Lorence – CenturyLink reviewed the proposed changes to Section 5.4.3 of the CMP document and what a vote of “Yes” and “No” meant as depicted on the voting Ballot in the CMP package. She asked if there were any questions. There were none. Susan stated that we have received three votes by mail, but one of the mail-in voters was on the call and assumed that they would vote by phone. The vote was then conducted and the results are listed in the table:

Voting Carrier Participant Vote TDS Metrocom Rod Cox (by email) Yes Velocity Telecom Jim Hickle (by email) Abstain Granite Telecommunications Jonathan Kronewitter (by phone) Yes POPP Communications Rebekah Byland (by phone) Yes Comcast Andrea Smith (by phone) Yes Allstream Kim Isaacs (by phone) Yes Met Tel John Nugent (by phone) Yes NOTE: Though Mark Coyne, CenturyLink, was not asked for his vote during the Voting process, his vote was also a “Yes” vote.

Susan Lorence – CenturyLink said the vote was unanimous and proposed that we make the agreed upon changes to Section 5.4.3 of the CMP document at the same time as we make the document updates for the prior CR so that we change the CMP document once. There were no objections. Susan also proposed that the update to the Web pages be made via a Level 1 notification. There were also no objections. She thanked everyone for the support for these CMP document updates.

Mark Coyne– CenturyLink said that we will be issuing two new CRs for the Simplify CMP project for the May meeting. The two CRs that were mentioned were the changes associated with eliminating the Performance Indicator Definitions (PID) wording in Section 2.6 and eliminating the CMP dispute resolution process and mailbox in Section 15.0. Mark said we would have ad hoc calls for these CRs.

FINAL Ad hoc meeting minutes April 2, 2018

PC030618-1CM CMP Document Update to Eliminate the Technical Escalations Contact List

Attendees: Rebekah Byland – POPP Communications Kim Isaacs – Allstream Andrea Smith – Comcast Darin Bray – CenturyLink Greg Johnson – CenturyLink Rita Urevig – CenturyLink Lee Gomez – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink relayed the purpose of the Ad Hoc call which was to review the proposed changes to the CMP document associated with two CenturyLink CRs. Due to some CLEC questions received from Kim Isaacs – Allstream prior to the March Monthly CMP meeting, CenturyLink scheduled the Ad Hoc call to discuss the proposed changes. For each CR, the calendar includes a current copy of the CR, the proposed change to the CMP document and the Allstream question.

PC030618-1CM CMP Document Update to Eliminate the Technical Escalations Contact List. Susan Lorence – CenturyLink said this CR was presented in March and was associated with the Simplify CMP project that is focused on cleaning up CMP processes and the CenturyLink website that have not been used in years, in some cases since the establishment of CMP in 2002. Susan pointed those on the call to the Production Support page and said we want to clean this page up, such as removing the POODLE info from 2014 and the Technical Escalation Process that has not been used. This technical escalation process is for CLECs and CenturyLink to call each other if there is a system problem. Susan said we checked with those listed on the contact list under CenturyLink and they have never received a customer escalation call. The thought is that customers are using the WSHD, the repair number or their service manager if they want to escalate an issue. The proposed CMP document update is to remove this Escalations contact list from the CMP document under Section 5.4.3 Level 2 changes. Susan said the question from Kim Isaacs – Allstream was whether this information is available anywhere else. It is not. This info is only in the download.

Kim Isaacs – Allstream said if she calls the WSHD and wants to escalate, will the names on the CenturyLink list be contacted.

Susan Lorence – CenturyLink said she thought the WSHD has their own list of escalation contacts depending on the type of problem.

Darin Bray – CenturyLink said the WSHD has two levels – an outage and an escalation. Darin said an escalation typically refers to a ticket that is already open to give it a higher severity. If an existing ticket is escalated, the WSHD will determine which department is working on it and move it to the next level for that type of problem. Darin said if a customer is calling about a system outage, the WSHD will call the bridge which will then have a SWAT opened.

Kim Isaacs – Allstream said if she has concern about a technical issue she can also take it to her Account manager and follow their normal escalation process. Kim said she is OK with this proposed change.

Susan Lorence – CenturyLink asked if POPP and Comcast had any questions about this change.

Kim Isaacs – Allstream said as the systems have become stable over the years, especially with the implementation of EDI, this process has served its purpose.

Andrea Smith – Comcast said she agrees with Kim. Andrea said she circulated this change within Comcast and did not hear any concerns back about it going away.

Susan Lorence – CenturyLink said we will provide meeting minutes from the call today for both CRs. We will send two vote notices for the April meeting making the changes that were discussed and agreed upon. She thanked those on the call for their discussion and attendance.

The Ad hoc meeting was adjourned at 11:30 AM MT.

3/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that is the second new CR to be presented that is part of the Simplify CMP project that was discussed last month. He asked Susan Lorence – CenturyLink to present.

Susan Lorence – CenturyLink told callers that the Technical Escalations Contact List is posted to the external web page at https://www.centurylink.com/wholesale/systems/productionsupport.html. It provides both CLEC and CenturyLink Technical Contact information. Similar to the POC reports, the CLEC information has received minimal updates since the creation of the document in 2002 and contains outdated information. The CenturyLink Technical Escalation List has been maintained though it has not been used. Susan said in speaking with the CenturyLink listed contacts, there have been no requests for technical escalation assistance. We would like to send a Level 4 notification to eliminate this process which will require an update to the CMP document under Section 5.4.3 Level 2 changes. Moving forward, if there were a technical escalation, it would more likely go through the Service Management team or the Wholesale Systems Help Desk. She asked if there were any questions on the proposed changes. There were none. She added that CenturyLink had received a comment from Allstream asking if the CenturyLink contact names were captured anywhere else. Susan said that this CR will be included in the ad hoc call that would be set up for CR PC110117-1CM that was discussed previously. She asked if there were any questions or comments. There were none.


Open Product/Process CR PC030618-2 Detail

 
Title: Eliminate External documentation request CMP mailbox
CR Number Current Status
Date
Area Impacted Products Impacted

PC030618-2 Completed
6/20/2018
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is proposing that the CMP External Documentation mailbox be eliminated. The mailbox was established back in 2003 associated with CMP CR PC030603-1 - Documentation process to allow CLECs to request documentation of existing processes, including documentation on the Qwest Wholesale web site.

The CenturyLink proposal is to eliminate this process, the ExDocReq@centurylink.com mailbox and the web page at https://www.centurylink.com/wholesale/clecs/exdocprocessrequest.html which was established in 2003 to allow CLECs to request external documentation updates.

• The last documentation request from a CLEC was received in 2015. There have only been 3 requests in the past 10 years.

• Eliminate the separate “external documentation request” mailbox and web page.

• If a CLEC would like CenturyLink to consider an external documentation update, depending on the type of change, either a CR should be issued or send an email to the CMPComm mailbox.

This CR is part of the Simplify CMP effort in 2018. There are no updates required to the CMP document.


Status History


Project Meetings

6/20/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR is in CLEC Test. The Final level 4 notice was sent on May 9, 2018 with an effective date of May 24, 2018 when it was moved to CLEC Test. Mark asked if there were any objections to moving this CR to a Completed status. There were none.

5/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR is part of the Simplify CMP project. The request is to eliminate the external documentation request CMP Mailbox ExDocReq@centurylink.com and the associated web page at https://www.centurylink.com/wholesale/clecs/exdocprocessrequest.html that is part of this process. A Level 4 notification was sent on April 9, 2018 to eliminate this process and the associated web page. There were no comments during the comment cycle. The Final notice was sent on May 9, 2018 with an effective date of May 24, 2018. For historical purposes, a copy of the various documents that are available on this web page have been placed on the Product/Process Document Review Archive. This includes: • The spreadsheet capturing the requests submitted to the mailbox • A copy of the CLEC External Documentation Request Process Guide • The CLEC External Process Clarification Request Process Guide • The Process Clarification Meeting resolution CenturyLink will send a Level 1 Web notice effective as of May 24, 2018 to remove any references to this URL from our web site and make any changes to other CenturyLink external documentation. We will review this one again in the June meeting. He asked if there were any questions. There were none.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented the prior month. The CR is to eliminate the external documentation request CMP Mailbox ExDocReq@centurylink.com and also the associated web page at https://www.centurylink.com/wholesale/clecs/exdocprocessrequest.html that is part of this process. Mark reminded those on the call that going forward, if a CLEC would like CenturyLink to consider an external documentation update, a CR can be issued or an email can be sent to the CMPComm mailbox. The initial notice was distributed on April 9, 2018. The Comment cycle started on April 10 and goes thru April 24. The Final notice is due May 9 with an effective date of May 24, 2018. As part of the final notice, for historical purposes, CenturyLink will post the documents that are being eliminated. This CR will be reviewed again in May. He asked if there were any questions. There were none.

03/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this is a new CR to be presented which is part of the Simplify CMP project that was discussed last month. This CR is to eliminate the external documentation request CMP Mailbox ExDocReq@centurylink.com that was established back in 2003 to allow CLECs to request updates to documentation. There is also a web page at https://www.centurylink.com/wholesale/clecs/exdocprocessrequest.html that is part of this process. Mark said the last documentation request that was received from a CLEC occurred in 2015. Only three requests have been received in the past ten years. Mark said if a CLEC would like CenturyLink to consider an external documentation update, either a CR should be issued or an email can be sent to the CMPComm mailbox. CenturyLink would like to send a Level 4 notification to eliminate this process. He asked if there were any questions. There were none.


Open Product/Process CR PC032118-1 Detail

 
Title: Remove ICO NNI from MOE Resale PCAT
CR Number Current Status
Date
Area Impacted Products Impacted

PC032118-1 Completed
5/16/2018
Ordering Resale MOE
Originator: Schlachter, Paul
Originator Company Name: CenturyLink
Owner: Schlachter, Paul
Director:
CR PM: Hansen, John

Description Of Change

Remove reference to ICO NNI (Independent Company) from Metro Ethernet (MOE) Resale PCAT.


Status History


Project Meetings

5/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the April meeting and reminded callers that it was to remove the reference to ICO NNI (Independent Company) from Metro Ethernet (MOE) Resale PCAT. This is a documentation cleanup effort. No customer impacts. A Level 2 notice was distributed on April 28, 2018, with an effective date of May 14, 2018. This CR has been moved to CLEC Test as of Monday. Since there are no customers, CenturyLink would like to move this CR to Completed. There were no objections.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this is a new CR to be presented by Paul Schlachter.

Paul Schlachter – CenturyLink presented the CR and advised that this Meet Point offering for ICO NNI service from 2016 had never been rolled out. ICO NNI is included in the Resale MOE PCAT. Paul said there are no system changes or edit changes associated with this.

Mark Coyne – CenturyLink confirmed with Paul that this was simply a document cleanup and he agreed. Mark asked callers that since there were no customers with this service, CenturyLink would like to distribute a Level 2 notice to make these changes. He asked if there were any objections. There were none.


Open Product/Process CR PC032818-1 Detail

 
Title: Grandfather Purchase Plus Reward Plan
CR Number Current Status
Date
Area Impacted Products Impacted

PC032818-1 Completed
6/20/2018
Ordering Resale Packages
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Effective June 15, 2018, CenturyLink will grandfather the Purchase Plus Reward Plan. There are currently no wholesale customers with this pricing plan.


Status History


Project Meetings

6/20/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated this CR is also in CLEC Test as of June 15, 2018. CenturyLink had requested that we send a level 2 notification since there were no wholesale customers on the pricing plan. The notice was sent on May 25, 2018 with an effective date of June 15, 2018. Mark asked if there were any objections to moving this CR to Completed status. There were none.

5/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the April meeting. This CR was to grandfather this pricing plan that was not being used by any customer. CenturyLink requested that a Level 2 notice be sent to make these changes. The notice will be sent on May 25, 2018 to be effective on June 15, 2018. We will review this one again in the June meeting. He asked if there were any questions. There were none.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this is a new CR to be presented by Lee Brummett.

Lee Brummett – CenturyLink told callers that this CR was to grandfather this pricing plan that was not being used by any customer. The CR has a proposed effective date of June 15, 2018.

Mark Coyne – CenturyLink asked callers that since there were no customers on this payment plan, CenturyLink would like to distribute a Level 2 notice to make these changes. He asked if there were any objections. There were none.


Open Product/Process CR SCR090418-1 Detail

 
Title: Grandfather Frame Relay and Asynchronous Transfer Mode Service
CR Number Current Status
Date
Area Impacted Products Impacted

SCR090418-1 Completed
3/20/2019
Ordering
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Qwest Corporation d/b/a CenturyLink QC plans to file and post material to grandfather its Frame Relay and Asynchronous Transfer Mode Service.

UPDATE July 25, 2018 from CR Originator:

As of October 15, 2018, or as soon after that date as authorized by the relevant regulatory commissions, CenturyLink QC Frame Relay service and CenturyLink QC ATM service will no longer be available to new customers or for new orders from existing customers.

Existing customers of these services will be grandfathered as follows:

• Existing contracts for these services will not be renewed.

• Customers with a contract that expires prior to March 1, 2019 may retain their CenturyLink QC Frame Relay and/or QC ATM service covered by that contract on a month-to-month basis per the terms of their contract until March 1, 2019.

• Customers with a contract that expires after March 1, 2019 may retain their CenturyLink QC Frame Relay and/or QC ATM service covered by that contract until the expiration of that contract. At that time, the current service will be considered end-of-life, and will no longer be supported.


Status History


Project Meetings

03/20/19 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR has been in CLEC Test since October 15, 2018. March 1, 2019 is the date that this product was eliminated. We would like to move this CR to a Completed status. Mark asked if there were any objections. There were none.

02/20/19 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR has been in CLEC Test since October 15, 2018. The effective date of the grandfathering of these products is March 1, 2019. We will consider moving the CR to a Completed status in the March CMP meeting.

01/16/19 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR is now in CLEC Test and will remain there until the effective date of March 1, 2019 when the product will be eliminated.

12/12/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR is now in CLEC TEST. The CR will remain in CLEC Test until the effective date of March 1, 2019 when the product will be eliminated.

11/14/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR was moved to CLEC Test on October 15, 2018 and will remain in CLEC Test until the product elimination date of March 1, 2019. Mark reminded customers of information shared in the July 2018 Monthly CMP meeting: "Customers with a contract that expires after March 1, 2019 may retain their CenturyLink QC Frame Relay and/or QC ATM service covered by that contract until the expiration of that contract. At that time, the current service will be considered end-of-life and will no longer be supported. " Mark asked if there were any other questions or comments. There were none.

10/17/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated the Level 4 final notice, to grandfather these services, was sent on September 28, 2018 with an effective date of October 15, 2018. The CR is now in CLEC TEST. The product elimination date is March 1, 2019. Mark asked if there were any other questions or comments. There were none.

9/19/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated the Level 4 initial notice to grandfather these services was sent on 8-31-18 and the comment cycle ended on 9-15-18. No comments were received. The final notice is due on 9-28-18 with an effective date of 10-15-18. The product elimination date is 3-1-19. Mark asked if there were any other questions or comments. There were none.

8/15/18 Product Process CMP Meeting Mark Coyne – CenturyLink said this CenturyLink CR was presented in the May CMP meeting by Lee Brummett - CenturyLink. At that time, no planned effective date was identified. In the July meeting, Lee relayed that the date to grandfather these services was going to be October 15, 2018 and that CenturyLink also had identified a date to eliminate the product which is scheduled for March 1, 2019. During the July meeting, there was a request for clarification of how the product elimination would work. Mark then relayed the specific information as included in the July meeting minutes. He said in July there was also a question about how grandfathering would impact hosting based on ATM service.

Jamal Boudhaouia – CenturyLink explained that if a CLEC has DSL Hosting Services that uses the CenturyLink ATM switch as the aggregator, it will not be affected by the grandfathering of this product at this time.

Kim Isaacs – Allstream asked when they can expect to receive the list of circuits that are impacted.

Mark Coyne – CenturyLink stated that list should be received in the next week or so and said the level 4 notice will be sent at the end of August.

7/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in May. The CR originator, Lee Brummett, relayed that at that point in time, the planned effective date to grandfather these services was still being determined.

Lee Brummett – CenturyLink relayed that the Grandfather date is planned for October 15, 2018. The date for product elimination is March 1, 2019.

Kim Isaacs – Allstream asked if a product elimination date was relayed when the CR was presented in May.

Lee Brummett – CenturyLink said he did not think so but there is now a date for product elimination.

Kim Isaacs – Allstream said she thought the CenturyLink resale broadband network is based on ATM service and asked how it will work to eliminate that. She said that Allstream was not going to be growing their ATM network so when the product was going to be grandfathered, that was not a problem. The March 2019 elimination date will be an issue.

Lee Brummett – CenturyLink stated he will check with the Product Manager.

Susan Lorence – CenturyLink said if Lee can get the information soon, we can include it in the meeting minutes.

07-25-18 INFO RECEIVED FROM LEE BRUMMETT As of October 15, 2018, or as soon after that date as authorized by the relevant regulatory commissions, CenturyLink QC Frame Relay service and CenturyLink QC ATM service will no longer be available to new customers or for new orders from existing customers.

Existing customers of these services will be grandfathered as follows: • Existing contracts for these services will not be renewed.

• Customers with a contract that expires prior to March 1, 2019 may retain their CenturyLink QC Frame Relay and/or QC ATM service covered by that contract on a month-to-month basis per the terms of their contract until March 1, 2019.

• Customers with a contract that expires after March 1, 2019 may retain their CenturyLink QC Frame Relay and/or QC ATM service covered by that contract until the expiration of that contract. At that time, the current service will be considered end-of-life and will no longer be supported.

Kim Isaacs - Allstream asked if CenturyLink was going to be filing with the FCC and states.

Lee Brummett - CenturyLink confirmed yes.

Mark Coyne – CenturyLink asked Lee to insure we get the CR updated with this new information. He said based on the mid October grandfathering date, CenturyLink will send out a Level 4 notice in late August.

Kim Isaacs - Allstream stated CenturyLink will have to contact customers directly for some states for the elimination piece. March 2019 will only provide 5 months and that is not enough time to move ATM/Frame Relay. Kim said she thought CenturyLink retail/government accounts will also have a problem.

6/20/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated this CR was presented in the May meeting to advise customers of CenturyLink’s plan to grandfather Frame Relay and Asynchronous Mode Service. There was no planned effective when the CR was presented.

Lee Brummett – CenturyLink advised that the effective date is still pending.

Mark Coyne – CenturyLink said when the effective date is confirmed, a Level 4 notice will be sent.

05/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this was a new CR and asked Lee Brummett to present.

Lee Brummett – CenturyLink stated that the purpose of this CR was to advise customers of CenturyLink’s intention to file and post material to grandfather Frame Relay and Asynchronous Mode Service. There is no effective date at this time.

Kim Isaacs – Allstream asked for confirmation that grandfathering meant that the existing service remained available though no changes would be allowed.

Lee Brummett – CenturyLink concurred. He stated that CenturyLink was in the process of identifying customers subscribing to the products.

Kim Isaacs – Allstream stated that some of the ATM circuits supported the CenturyLink Broadband for Resale product and wanted to be sure they were not going to have a problem with those circuits.

Lee Brummett – CenturyLink said the circuits would be grandfathered.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.


Open Product/Process CR PC060618-1 Detail

 
Title: Enhance WSS Badge Access Tool
CR Number Current Status
Date
Area Impacted Products Impacted

PC060618-1 Completed
10/17/2018
Originator: Albritton, Trey
Originator Company Name: CenturyLink
Owner: Albritton, Trey
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be modifying our WSS External portal used by CLEC’s to enhance record keeping and overall control of physical building locations. The changes are as follows:

1) ACNA will now be required for each building address request

2) The number of locations requested will expand from 5 to 10

3) Customers will no longer be able to request additional sites via the “Reason for Access” field on the WSS form.


Status History


Project Meetings

10/17/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised the effective date for this CR, to enhance the Workplace Self-Service (WSS) external portal for access badges, was originally August 22, 2018. At that time, the CR was moved to CLEC Test. CenturyLink identified a problem and Event notification 10445461 was issued on August 27, 2018. The previous version of the web tool was reloaded. On October 5, 2018, the Web team resolved the problem and the updates to the Badge tool were reloaded in Production. CenturyLink issued a Level 1 web notice to relay to all wholesale customers that the changes associated with this CR were once again available. On October 11, 2018, we sent a closure notice for the Event notice. Mark asked if anyone had any questions or objections to moving the CR to a Completed status. There were none.

9/19/18 Product Process CMP Meeting Mark Coyne – CenturyLink advised that the effective date for this CR was 8-22-18. The CR was moved to CLEC Test on that date. CenturyLink did identify a problem with the WSS external portal and issued an Event notification 10445461 on 8-27-18. The previous version of the web tool was reloaded while the SME team continues to work on the issue. We will review this CR again in October. Mark asked if there were any questions or comments. There were none.

8/15/18 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in June by Trey Albritton – CenturyLink associated with a change to the WSS Badge Tool. The Level 4 notice was distributed on July 17, 2018. No comments were received during the comment cycle. The Final Notice was sent on August 7, 2018 and it has a planned effective date of August 22, 2018. Mark said we will review this CR in the September meeting. He asked if anyone had any questions. There were none.

07/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in June associated with some changes to the WSS Badge Tool. The Level 4 notice was distributed on July 17, 2018. The CLEC comment cycle ends August 1, 2018 with the final notice due August 7, 2018 for an effective date of August 22, 2018. Mark asked if there were any other questions. There were none.

06/20/18 Product Process CMP Meeting Trey Albritton – CenturyLink presented this new CR by identifying the changes as included the Description Section for the Workplace Self-Service (WSS) external portal for access badges. Trey said the changes will enhance record keeping and expand location requests. Trey asked if there were any questions.

Kellie Halabrin – CenturyLink asked for clarification on the change related to the “Reason for Access” field.

Trey Albritton – CenturyLink said this field has been used to identify additional sites when the number of sites was greater than five. With this change, that field can no longer be used. Trey gave the example that if a customer is requesting 15 sites, they will have to issue two requests, one with 10 and another with 5.

Nancy Taylor – Allstream said Allstream has several ACNAs and asked if they would have to submit a request for each.

Trey Albritton – CenturyLink said each ACNA and their affiliates would be preloaded. When a customer wants to make a request, they will submit it for each appropriate company. Trey said each company is operating under separate agreements.

Nancy Taylor – Allstream asked about collocations and said they may have separate cages under separate agreements.

Trey Albritton – CenturyLink said the customer will have to make a separate request for each ACNA for a specific location. The tech will then have access to each site on the one badge. Multiple requests can be made on the same form for different ACNAs. It will not have to be done one at a time. Trey said in regard to more than five sites, it is rare to see greater than 10 at the same time. The planned effective date is after August 1, 2018. He said that CenturyLink will send notification out to all customers as required as well as send specific info to each Customer point of contact.

Mark Coyne – CenturyLink provided the reminder that we will send a 45 day level 4 CMP notice. Mark asked if there were any other questions. There were none.


Open Product/Process CR PC092818-1 Detail

 
Title: Discontinue Ethernet with Extended Transport Service
CR Number Current Status
Date
Area Impacted Products Impacted

PC092818-1 Completed
12/12/2018
Ethernet with Extended Transport (EwET)
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Qwest Corporation d/b/a CenturyLink QC plans to file and post material to discontinue Ethernet with Extended Transport (EwET) service. There are no Resale customers.

The effective date of this change will be November 30, 2018, or as soon as the necessary regulatory approval can be obtained.


Status History


Project Meetings

12/12/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that a Product notice was sent on November 9, 2018 with an effective date to discontinue this service as of November 30, 2018. There were no CLEC comments. The CR is in CLEC Test. Mark asked if there were any objections to moving this CR to a Completed status. There were none.

11/14/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR was presented in the October CMP meeting. During that meeting, CenturyLink announced there are no Resale customers and requested that a Level 2 notice be sent to grandfather the product. There were no objections. On November 9, 2018, CenturyLink submitted a Level 2 Product notice PROD.RESL.11.09.18.F.17004.ResaleMOEV45 that will be effective on November 30, 2018 to discontinue this service. Mark asked if there were any questions. There were none.

10/17/18 Product Process CMP Meeting Lee Brummett – CenturyLink said we are planning to file to discontinue Ethernet with Extended Transport Service with an effective date of November 30, 2018. Lee said there are no Resale customers.

Kim Isaacs – Allstream said she knows Commercial agreements are not part of CMP but wondered if CenturyLink will be reaching out to those customers under the Wholesale Data Services Agreement (WDSA) to inform them of this.

Lee Brummett – CenturyLink said he will validate it but he believes these customers were checked and no circuits were impacted.

Mark Coyne – CenturyLink said based on the fact that there are no Resale customers, he asked if there were any objections to sending a level 2 CMP notification to inform customers of this change. The notice would likely be sent around November 9, 2018. There were no objections.

Kim Isaacs – Allstream noted that if there are impacted circuits under the WDSA, she thought a 30 day or possibly a 90 day notice would be required.

Susan Lorence – CenturyLink said we will include an FYI in the meeting minutes as to whether there are any WDSA customers.

October 24, 2018 NOTE: Though outside the scope of CMP, Lee Brummett – CenturyLink confirmed that there are no WDSA customers for Ethernet with Extended Transport Service. There are also no IXC customers with this service.


Open Product/Process CR PC110117-1CM Detail

 
Title: CMP Doc change to modify hours of Wholesale System Help Desk (WSHD)
CR Number Current Status
Date
Area Impacted Products Impacted

PC110117-1CM Completed
5/16/2018
Wholesale Systems Help Desk
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is proposing that the hours of operation for the Wholesale System Help Desk (WSHD) be reduced due to the low volume of CLEC calls for the last 90 minutes of the business day. The current hours of operation are Monday thru Friday, 6 AM to 7 PM MT. The new hours of operation that CenturyLink is proposing are Monday thru Friday, 6 AM to 5:30 PM MT.

During the October 2017 monthly CMP meeting, CenturyLink proposed a Process Trial to run from November 20, 2017 through February 20, 2018 to determine the feasibility of this change in the WSHD hours. During this three month trial, the CenturyLink WSHD will utilize an on-call pager during the window of 5:30 PM MT to 7 PM MT to respond back to customer calls.

A redline of the Change Management Process document will be provided.

Proposed Implementation Date: 4/1/18


Status History


Project Meetings

05/16/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR is associated with the change in the WHSD hours due to low call volume. The vote was taken last month with unanimous agreement to make the change to end the WSHD hours at 5:30 PM but between 5:30 to 7, the WSHD will provide pager coverage. Mark referenced Page 24 of the CMP distribution package that contained the various notices that were distributed associated with the change. The CR is now in CLEC Test as of May 7, 2018, and we would like to move it to a Completed status. He asked if there were any objections. There were none.

04/18/18 Product Process CMP Meeting Mark Coyne – CenturyLink said that this CR was associated with the 90-day trial for the WSHD to use a pager the last 90 minutes of the business day Monday thru Friday. The call volume is extremely low. An Ad Hoc Call was conducted April 2, 2018 due to customer comments. Call participants agreed upon adding language regarding the pager usage to the CMP Document update. The CMP Vote Notification was issued on April 4, 2018 to relay a vote would occur in the April Monthly Meeting. The notice is included in the package along with the ballot. He asked Susan Lorence to review the voting procedure and take the vote.

Susan Lorence – CenturyLink reviewed the CMP Vote process as included in Section 17.0 of the CMP document. The key points of the CMP voting process are: each entity is entitled to a single vote regardless of any affiliates and quorum must be established. Susan said quorum is based on 62.5% of the average CLEC and CenturyLink entities in attendance at the last six monthly CMP meetings, October 2017 through March 2018. The average number of entities in attendance during this period was five so the quorum for the vote was three thus quorum was met. Susan reviewed the proposed changes to Section 12.7 of the CMP document and what a vote of “Yes” and “No” meant as depicted on the voting Ballot in the CMP package. She asked if there were any questions. There were none. Susan said we received three votes by mail, but one of the mail-in voters was on the call and assumed that they would vote by phone. The vote was then conducted and the results are listed in the table:

Voting Carrier Participant Vote TDS Metrocom Rod Cox (by email) Yes Velocity Telecom Jim Hickle (by email) Abstain Granite Telecommunications Jonathan Kronewitter (by phone) Yes POPP Communications Rebekah Byland (by phone) Yes Comcast Andrea Smith (by phone) Yes Allstream Kim Isaacs (by phone) Yes Met Tel John Nugent (by phone) Yes NOTE: Though Mark Coyne, CenturyLink, was not asked for his vote during the Voting process, his vote was also a “Yes” vote.

Susan Lorence – CenturyLink said the vote was unanimous and proposed that we make the agreed upon changes to the CMP document and to the Web pages via a Level 1 notification. There were no objections to this approach.

Ad hoc meeting minutes FINAL April 2, 2018

PC110117-1CM CMP Doc change to modify hours of Wholesale System Help Desk (WSHD)

Attendees: Rebekah Byland – POPP Communications Kim Isaacs – Allstream Andrea Smith – Comcast Darin Bray – CenturyLink Greg Johnson – CenturyLink Rita Urevig – CenturyLink Lee Gomez – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink relayed the purpose of the Ad Hoc call which was to review the proposed changes to the CMP document associated with two CenturyLink CRs. Due to some CLEC questions received from Kim Isaacs – Allstream prior to the March Monthly CMP meeting, CenturyLink scheduled the Ad Hoc call to discuss the proposed changes. For each CR, the calendar includes a current copy of the CR, the proposed change to the CMP document and the Allstream question.

PC110117-1CM CMP Doc change to modify hours of Wholesale System Help Desk (WSHD) Susan Lorence – CenturyLink provided some background on the CR and the 90 day trial that occurred that ended in February.

Mark Coyne – CenturyLink said in the March CMP monthly meeting, CenturyLink reviewed the results of the 90 day trial where the WSHD used a pager and customer callback from 5:30 PM to 7 PM MT. Mark said only two calls came into the WSHD during that time and both were received in mid-December. One call was associated with a request for a digital certificate and the other call was associated with repair that was not appropriate for the WSHD. Based on the trial results, CenturyLink is proposing a change to Section 12.7 of the CMP document to change the normal hours of operation for Monday thru Friday to end at 5:30 PM MT vs. 7:00 PM MT. There is no change to the Saturday hours nor the handling of Severity 1 and 2 tickets. Mark said the WSHD message that states “if your matter is urgent, leave a message and CenturyLink will call back” will also remain in place.

Kim Isaacs – Allstream asked where in the CMP document is the use of a pager referenced.

Mark Coyne – CenturyLink said a pager is not currently referenced in the CMP document nor is it included as part of the proposed change. Mark said the CSIE will continue to be available for ordering questions until 7:00 PM MT Monday thru Friday and that this WSHD change is specific to questions regarding technical or system questions.

Kim Isaacs – Allstream said with the LSR consolidation still planned, she would like to see some reference added to the CMP document regarding the use of a pager for the 90 minute window.

Mark Coyne – CenturyLink said as stated in the monthly CMP meetings, CenturyLink is trying to simplify some of the wording in the CMP document so our preference was not to add language. Mark said an approach might be to add some reference to the WSHD pager in the Customer Contact Business Procedure.

Kim Isaacs – Allstream said she was not in favor of adding it to the PCAT since that document could be changed. She said she wants wording included in the CMP document that relays that the WSHD is available until 7:00 PM MT – either via a phone or a pager.

Susan Lorence – CenturyLink said that Kim mentioned the LSR consolidation but that during the ASR Consolidation implementation weekend, CenturyLink provided a Consolidation “Help line” to customers to address consolidation concerns. The window for the “Help line” was reduced by a week since things were going well. Susan asked if knowing that CenturyLink would do that again would suffice.

Kim Isaacs – Allstream said she did not want to give up something that is currently available in CMP and her ICA. She said maybe CenturyLink wanted to talk about lowering OSS charges as part of this but otherwise she did not want to give it up for nothing.

Mark Coyne – CenturyLink said customers would not lose any coverage during the window of 5:30 -7:00 PM MT; the WSHD would still be available.

Kim Isaacs – Allstream said it would not be in writing that CenturyLink has a long-term commitment to that coverage. She said Allstream has had problems with other companies on the east coast and wanted it in writing. She was sorry that CenturyLink would be punished for another company’s bad behavior.

Mark Coyne – CenturyLink we would take it back and look at what that language would look like.

Rebekah Byland – POPP Communications said she agreed with Kim that it was good to have it in writing that they could still receive assistance otherwise it will appear that WSHD coverage ends at 5:30 PM.

Mark Coyne – CenturyLink said he wanted to confirm what type of coverage was being requested. Was it systems issues or outages or an ordering issue?

Kim Isaacs – Allstream said the request was coverage for systems issues via the WSHD pager and not ordering issues. Allstream is working across multiple time zones and they have a group of personnel on the west coast.

Susan Lorence – CenturyLink said it sounds like if CenturyLink includes additional wording in the CMP document about pager coverage between 5:30 to 7:00 PM MT, that a CMP vote in April could occur.

Kim Isaacs – Allstream said yes.

There was no other questions or comments about this CR.

The Ad hoc meeting was adjourned at 11:30 AM MT.

3/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink said the trial for this CR ended February 20, 2018. CenturyLink had been tracking calls since November 2017. He reminded callers that the CR is associated with the trial procedure for Wholesale System Help Desk (WSHD) personnel to use a pager for customer call back during the following WSHD hours of operation: Monday - Friday 5:30 PM - 7:00 PM MT. Mark asked Darin Bray – CenturyLink to review the trial results.

Darin Bray – CenturyLink said he is a Lead on the WSHD. Darin said they have been monitoring calls during the trial and he has not seen a lot of change in the calls received. Most calls occur before 5:30 PM MT. During the trial, five calls came in before that time and they carried over past the 5:30 PM timeframe and were resolved by the WSHD. Darin said he could not tell if other calls came in after 5:30 PM MT if the caller does not leave a voice mail. He said there were two voicemails left in December. There was little or no change in the average speed of call handling time and the time to answer.

Susan Lorence – CenturyLink confirmed with Darin that of the two voicemails that were left in December during the 90 day trial, one requested a digital certificate and was assisted by the WSHD. The other had a request that was not appropriate for WSHD and the caller provided an incorrect call back number. No action was taken.

Darin Bray – CenturyLink agreed.

Mark Coyne – CenturyLink asked if there were any questions for Darin. There were none. He added that the proposed language change in the CMP document would occur in Section 12.7 NOTIFICATION INTERVALS with a change to the M-F 7 PM MT timeframe to change it to end at 5:30 PM MT. Mark said the voice mail process would be that if a customer called in any time after the 5:30 PM MT time frame, the recording would advise that it the matter was urgent, the customer should leave a message. The same callback process would be in place for the WSHD to call them back. The proposed language change will be voted on in the April CMP meeting. He advised that a comment was received from Allstream regarding the use of the process of paging and that it be included in the CMP document. Mark said that since Allstream was not on the call, CenturyLink will set up an ad hoc call prior to the April CMP meeting to walk through Allstream’s concern. All are welcome to join the call and hopefully any issues will be resolved so that the vote may proceed in April. He asked if there were any questions. There were none.

2/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink said the trial for this CR ended February 20, 2018. He reminded callers that the CR is associated with the trial procedure for Wholesale System Help Desk (WSHD) personnel to use a pager for customer call back during the following WSHD hours of operation: Monday - Friday 5:30 PM - 7:00 PM MT. Mark said we would like to continue with the pager process while the results are reviewed. The plan is to share the outcome of the trial in the March CMP meeting. Mark said that CenturyLink would likely be sending a proposed redline of the CMP document for consideration. Mark asked if there were any questions. There were none.

01/17/18 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR is associated with the trial procedure for Wholesale System Help Desk (WSHD) personnel to use a pager for customer call back during the following WSHD hours of operation: Monday - Friday 5:30 PM - 7:00 PM MT. There is no change to the Saturday schedule. The ninety (90) day trial started on November 20, 2017 and ends on February 20, 2018. At the end of the three-month process trial, CenturyLink will evaluate the results. Mark said the early numbers received from the WSHD indicate that there are few to no calls during this window. He said it looks like we will try to move forward with a proposed change to the CMP document to make a change to the current hours that are documented. Mark asked if anyone has used the pager process and asked if there is any positive or negative feedback.

Kim Isaacs – Allstream asked to confirm the trial hours.

Mark Coyne -CenturyLink confirmed that it was the 1-1/2 hour period between 5:30 PM - 7:00 PM MT. He asked if there were any questions. There were none.

12/13/17 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in the November CMP meeting but the changes were actually discussed in October. Mark reminded everyone that the trial procedure is to use a pager for customer call back during the Wholesale System Help Desk (WSHD) Monday - Friday 5:30 PM - 7:00 PM MT hours of operation. There is no change to the Saturday schedule. The ninety (90) day trial started on November 20, 2017 and ends on February 20, 2018. At the end of the three-month process trial, CenturyLink will evaluate the results. He reminded callers that the customer will be asked to leave a message. The WSHD professional will contact the customer within 15 minutes. From that point, the WSHD call will be conducted business as usual. No documentation updates will be made. Mark asked if there were any questions. There were none.

11/15/17 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this new CR was discussed in the October CMP monthly meeting as a Walk-on. A Change Management CR was issued associated with proposed Process Trial which announced on November 1, 2017. The trial will start November 20, 2017 and run until February 20, 2018. CenturyLink will be trialing the use of a pager for customer call back during the following hours of operation: Monday - Friday 5:30 PM - 7:00 PM Mountain Time with no change to the Saturday schedule. The customer will be asked to leave a message. The WSHD professional will contact the customer within 15 minutes. From that point, the WSHD call will be conducted business as usual. This is a Process Trial only. No documentation updates will be made. At the end of the three-month process trial, CenturyLink will evaluate the results. Mark asked if there were any questions. There were none.

PRELIMINARY DISCUSSION PRIOR TO CR BEING SUBMITTED BY CENTURYLINK 10/18/17 Product Process CMP Meeting Mark Coyne - CenturyLink relayed that in the September monthly meeting, CenturyLink provided a brief update on the Process Trial associated with Wholesale Systems Help Desk (WSHD) and the Customer Service Inquiry and Education (CSIE) Center. [For more detailed information about the trial, refer to Notification PROS.MISC.08.22.17.F.15839.ProcessTrialLSRQuestions available on the CNLA at http://wholesale.centurylinkapps.com/cnla.] Mark said that that trial was going smoothly internally and externally. At the midpoint of that trial, Mark said the WSHD is also looking at reducing their hours of operation. To support their possible changes, the team pulled some data since the WSHD/CSIE trial started in September. It shows that the call volume into the WSHD Option 3 is down approximately 30%. Mark said that included in the package are some call volumes for the WSHD reflective of the last four months from 5:30 PM to 7:30 PM Monday thru Friday. The data for that time period shows that the WSHD receives approximately two calls per week. Based on that data, concurrent with the previous trial, CenturyLink would like to propose an additional process trial that would run from November 1, 2017 through January 31, 2018. During the WSHD hours of 5:30 PM to 7:00 PM MT Monday through Friday, calls into the WSHD would utilize an On Call pager to return customer calls. Saturday hours would remain the same and the CSIE hours (WSHD Option 1) would also remain 7:00 AM to 7:00 PM MT Monday through Friday as they are today. CenturyLink would review the results in early February 2018. Mark asked if there were any questions.

Kim Isaacs – Allstream expressed concern that the timeframe would result in calls being handled via pager starting at 4:30 PM PT and asked if the timeframe for the pager could be adjusted to 6:00 PM – 7:00 PM MT.

Mark Coyne – CenturyLink stated that the proposal from Kim could be considered, but asked if the trial could proceed as planned and then determine the final timeframe for the pager at the conclusion.

Kim Isaacs – Allstream stated that she would like for her west coast provisioning team to be ensured support until their business day was complete.

Mark Coyne – CenturyLink offered to take the request back to the WSHD and that a reply would be included via meeting minutes. Mark asked those on the call if there were any other concerns besides the 5:30 PM to 6:00 PM MT window. There were none. Mark advised that CenturyLink would submit a Change Request in the November Monthly CMP meeting to address these issues in preparation for an eventual proposed change. He said in good faith, CenturyLink believes the data showing the low call volume supports some changes being made and that CenturyLink wants to find a good approach for all parties.

NOTE: At the conclusion of the October Monthly Systems Meeting, there was additional discussion about the newly proposed WSHD process trial. That content is being included here for continuity vs. in the October System monthly meeting minutes.

Mark Coyne – CenturyLink said that James Clement – CenturyLink was on the call as a SME representing the WSHD. Mark said James would provide some additional information about the level of support that would continue to occur for the hours that would be covered by the pager.

James Clement – CenturyLink said he wanted to be sure that customers understood that at this time, CenturyLink is not requesting that we change the WSHD hours of operation. James said the current hours will remain the same. He said the difference is that rather than having an agent waiting in an office for a call, the “on call” agent would have a pager and they would respond within 15 minutes. The agent would then handle the call business as usual – either assist the customer or create a ticket for further investigation. James said CenturyLink would be able to handle what was required in the Service Level Agreement (SLA).

Mark Coyne – CenturyLink asked Kim if that information would allow her to consider keeping the trial as originally proposed.

Kim Isaacs – Allstream said she wanted to take this back to her team to check further. Kim said they have previously had some issues with other east coast carriers where the lack of support has caused problems.

Mark Coyne – CenturyLink said he would like to leave the trial as proposed until he hears back from Kim once she has had a chance to follow-up internally. Mark asked if Kim could respond by Friday, October 20.

Kim Isaacs – Allstream said she could respond by then.

James Clement – CenturyLink said he wanted to be sure to understand what the concern was since hours were not changing.

Kim Isaacs – Allstream said it was the “on call” pager that she wanted to check on.

10-25-17 UPDATE: Subsequent to the CMP monthly meeting, CenturyLink heard from Kim Isaacs – Allstream. Based on Kim’s follow-up and some additional information, Kim agreed that the trial could proceed as originally planned: the WSHD would utilize an on call pager during the hours of 5:30 PM to 7:00 PM MT Monday through Friday. An additional note to this is that the WSHD Process trial was originally planned to begin on November 1 but has been delayed to begin starting on November 20, 2017 and will continue for 90 days. A notification will be sent on November 1 with the specific details.


Open Product/Process CR PC040214-1 Detail

 
Title: Elimination of the automatic delivery of the LNP Reports via connect enterprise
CR Number Current Status
Date
Area Impacted Products Impacted

PC040214-1 Withdrawn
1/21/2015
Reports 911/E911
Originator: Eckhoff, Kevin
Originator Company Name: CenturyLink
Owner: Eckhoff, Kevin
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be eliminating the automatic delivery of six LNP migration reports. The six reports are:

1. Unlock Exception Report

2. Migrate Expired Report

3. Migrate Received/Not Unlocked Report

4. Migrate Pending Report

5. Successfully Migrated TN’s Report

6. Auto Unlock Exception Report

This information is currently already available on demand via our CenturyLink Web Portal or by request from the Centurylink 911 Operations group.

These six reports are being eliminated in the following states: Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana, Oregon.

The reports will continue to be delivered via the current process in the following states: Arizona, New Mexico, North Dakota, South Dakota, Minnesota, Utah, Washington.

This change has a rolling implementation date depending on state migrations. The current planned Carrier migration dates are as follows and these end dates are when the reports will be eliminated for each state:

10/24/14 CR updated by originator to show a delay in Iowa, Nebraska and Wyoming in addition to Colorado.

8/25/14 Table updated to show a delay in CO

State End Effective Date

Colorado DELAYED

5/1/14 REVISED IMPLEMENTATION TABLE:

State End Effective Date

Colorado September 22, 2014

Iowa November 10, 2014

Nebraska January 26, 2015

Wyoming February 16, 2015

Montana March 23, 2015

Idaho April 20, 2015

Oregon June 8, 2015

This table was REVISED as of 5/1/14

Colorado May 30, 2014

Iowa August 1, 2014

Nebraska August 29, 2014

Wyoming October 3, 2014

Idaho November 7, 2014

Montana February 12, 2015

Oregon March 19, 2015

Expected Deliverables/Proposed Implementation Date: Phased implementation starting June 1, 2014 for Colorado.


Status History


Project Meetings

1/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said that on January 7, 2015, this CR was moved to Pending Withdrawal by the CR owner, Kevin Eckhoff. Per the SME team, this CR is no longer necessary due to a different corporate direction being taken with our existing partner Intrado. Mark relayed Intrado will remain the chosen ALI database vendor for 911/E911 services in the CenturyLink (Qwest) fourteen states. We will be moving this to a Withdrawn status. Mark asked if there were any questions. There were none.

12/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. It is associated with eliminating the automatic delivery of the LNP reports in seven states. Mark said a notification was sent in November 2014 and the states of Colorado, Iowa, Nebraska, and Wyoming remain delayed until further notice. No additional updates have been received from the SME team.

11/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is associated with eliminating the automatic delivery of the LNP reports in seven states and it remains in CLEC Test. Mark said in October, the originator updated the CR to show a delay in Iowa, Nebraska and Wyoming in addition to the Colorado delay that was already in effect in Colorado. A level 1 notice will be distributed shortly to relay this most recent delay.

10/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. The date for the first state of Colorado to eliminate the delivery of reports has been delayed and the date for Iowa is now also TBD. Mark said a notice was sent on September 23, 2014 to relay the migration dates for Iowa, Nebraska and Wyoming are being updated. Once the revised dates are set, CenturyLink will send a notification to update the PCAT. In the meantime, customers with established connectivity with CenturyLink and Intrado, Inc. in Colorado and Iowa should continue to send duplicate files to each company until advised otherwise. Mark said no other updates have been received from the Project team at this time.

9/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test. The first state where the delivery of the reports is to be terminated is Colorado and the planned date was to be September 22, 2014 but as relayed last month, that state has been delayed. Mark said the end effective dates for the other states remain as planned.

8/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR which is in CLEC Test is associated with eliminating the automatic delivery of the LNP reports in the following seven states: Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana and Oregon. The first state where the delivery of the reports will be terminated is Colorado and the planned date was to be September 22, 2014. Mark said there has been a delay which may impact the planned date for elimination of the other states. He said a notice will be sent once the new date for Colorado has been determined.

Kim Isaacs – Integra said asked if the delay is due to the emergency ruling by the Colorado Commission order on PS ALI.

Mark Coyne – CenturyLink said he was not sure but he thought that was part of it. Mark asked if there were any other questions. There were none.

7/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test and will be until the last state of Oregon goes into effect on June 8, 2015. This CR is associated with eliminating the automatic delivery of the LNP reports in the following seven states: Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana and Oregon. The first state where the delivery of the reports will be terminated is Colorado on September 22, 2014.

Bonnie Johnson – Minnesota Department of Commerce asked why the CR was in CLEC Test if the effective date for the first state had not been reached.

Susan Lorence – CenturyLink said procedurally, the CR is moved to CLEC Test at the end of the CMP notification cycle. The CR remains in CLEC Test as each effective date passes for each state.

Mark Coyne – CenturyLink said the notification effective date was in May 2014.

6/18/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR associated with eliminating the automatic delivery of the LNP reports in the following seven states is in CLEC Test. The states are Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana and Oregon. The final notice and response to CLEC comments were sent on May 16 and recaps the dates for the reports to be eliminated for each state and the CR and the PCAT have also been updated. Mark said there will be some additional information about the 911/E911 related change to this CR under Attachment F- Walk-ons. The CR will be left in CLEC Test until June 8, 2015 when the last state of Oregon becomes effective. Mark asked if there were any questions. There were none.

5/21/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in April and the initial level 4 notice was sent on April 28 to relay that the automatic delivery of the LNP reports would be eliminated in the impacted states of Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana and Oregon. A subsequent notification was sent on May 1 which clarified the dates in the April 28 notice and provided an extension of the state by state timeline to terminate delivery of the reports. Mark gave the example of the first state Colorado which has the extended date of September 22, 2014. The final notice and response to CLEC comments was sent on May 16 and has an effective date of June 1. Mark said a Web notice was sent which introduced a WebDBMS tool. CenturyLink received CLEC comments on that notice that included comments related to ICA language. Mark said our SME team is working on the response to CLEC comments which is due May 22, 2014.

Kim Isaacs – Integra said CenturyLink has piece mealed out notifications related to this project and this has caused confusion. Kim said she is not sure whether the WebDBMS tool is the only tool available for CLECs to interact with the SOI files and related reports. Kim said connectivity for Colorado is to be established by May 30 with files sent to both Intrado and CenturyLink by June 1 and they had not heard from anyone and it would not happen. Kim said this should have been one CR for the CenturyLink move away from Intrado. The various notifications should be addressed similar to how the LSOG changes are handled. Kim suggested holding an ad hoc call.

Mark Coyne – CenturyLink said the SMEs were not able to join this call but that once the final notice and response to comments was sent on May 22, CenturyLink would establish an ad hoc call if necessary.

Kim Isaacs – Integra said she would review the response to comments to determine if there were additional concerns. She asked if there were two ways to interact with CenturyLink regarding the SOI files or was the only mechanized means for interaction the WebDBMS tool.

Susan Lorence – CenturyLink said she thought the SOI files could continue to be FTP’d but that the SMEs would need to confirm that.

Kim Isaacs – Integra said she thought FTP or NDM was going to remain available but had not heard from CenturyLink regarding establishing connectivity.

Susan Lorence – CenturyLink said we would try to include a response to Kim’s questions with the final notice to be sent tomorrow.

Kim Isaacs – Integra said she assumed the people involved with this change were new and not as familiar with CMP.

Mark Coyne – CenturyLink said there were lessons to be learned with this project and that Kim’s input was valid. Mark asked if there were any other questions. There were none.

4/19/14 Product/Process CMP Meeting Kevin Eckhoff – CenturyLink presented the new CR. He said the automatic delivery of six LNP migration reports will be eliminated in Colorado, Iowa, Nebraska, Wyoming, Idaho, Montana, Oregon since the reports will be available on the (4/29/14 Updates received from Integra in CAPS) EMBARQ web TOOL. The reports will continue to be delivered for the remaining states as they are today. Kim Isaacs – Integra asked if this CR was related to the CenturyLink migration away from Intrado.

Kevin Eckhoff – CenturyLink said yes, CenturyLink was taking the work back from Intrado for the specified states and was moving them to the ALI database that has been managed by CenturyLink for over 20 years.

Kim Isaacs – Integra asked why this was a Product Process CR versus a System CR since customers would have to now log into (4/29/14 Updates received from Integra in CAPS) THE EMBARQ [delete A] portal instead of automatically delivery. Kim said she wanted to be clear that with this change, the [INTEGRA’S] [delete ASSUMPTION] EXPECTATION is that the existing Embarq/CenturyLink portal will now fall under QC CMP guidelines. ANY SYSTEMS USED TO CONDUCT BUSINESS UNDER OUR CENTURYLINK/QC ICAS NEED TO BE IMPLEMENTED AND MANAGED UNDER THE CENTURYLINK/QC CMP PROCESS.

Mark Coyne – CenturyLink said we would get with the SME team to determine if the CR needed to be crossed over to a System CR and would also follow CMP parameters.

Randee Ryan – Comcast asked if the other states would remain with Intrado.

Kevin Eckhoff – CenturyLink said yes, the other states would remain with Intrado.


Open Product/Process CR PC013014-1CM Detail

 
Title: Change to the CMP document to replace references to CEMR and MEDIACC with "Trouble Reporting” systems
CR Number Current Status
Date
Area Impacted Products Impacted

PC013014-1CM Completed
4/16/2014
Change Mangement Process Document
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

The CEMR GUI and the MEDIACC application to application interface have been retired as of 1/31/14. CenturyLink is proposing that references to CEMR and MEDIACC be replaced with references to "Trouble Reporting” systems. These updates would be both in the CMP document and on the CMP CR form.

Updates to remove CEMR and MEDIACC are in the following sections of the CMP document.

3.3 CenturyLink Wholesale CMP Web Site

5.1.4 Systems Change Request Origination Process

11.0 APPLICATION-TO-APPLICATION INTERFACE TESTING

13.2 Changes to an Existing GUI

Appendix D: SAMPLE change request form

Redlined word document attached.

The proposed implementation date is 4/1/14.


Status History


Project Meetings

4/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the CMP Vote was conducted in the March 2014 monthly meeting and the vote to update the CMP document was unanimous. The notification that provided the Voting results was distributed on March 26, 2014. The Level 1 notification to update the CMP document was distributed on April 9, 2014. Mark said the new CR form and SCRP form were also posted to the wholesale web at that time. Mark requested that the CR which is in CLEC Test be moved to Completed status. There were no objections.

3/19/14 Product/Process CMP Meeting Mark Coyne– CenturyLink said the CR had been presented in the February CMP monthly meeting and the redlined language had been reviewed. The Change Management CR vote notice had been sent out on March 5 and a copy of the notice and ballot is included in the CMP package. Mark said Susan Lorence - CenturyLink would review the vote instructions and conduct the vote.

Susan Lorence – CenturyLink identified Section 17 of the CMP document provided the instructions on how to conduct a CMP Vote. The key points of the CMP voting process are: each carrier is entitled to a single vote regardless of any affiliates; a change to the CMP document requires a unanimous vote per Section 2.1 of the document; and finally, quorum has to be established. Susan said quorum was based on 62.5% of the average CLEC and CenturyLink attendance at the last six monthly CMP meetings, September 2013 through February 2014. The average CLEC and CenturyLink attendees during this period was eight so the quorum for today’s vote meeting would be five. That number had been met so the vote can be conducted. Susan asked if there were any questions. There were none. Susan said the redlined CMP document was posted to the Wholesale calendar and relayed the CMP document sections that were to be updated with this CR. A CLEC or CenturyLink vote of “yes” indicates the updates to the CMP document would be made, and a CLEC or CenturyLink vote of “no” indicates that those changes will NOT be made. Susan conducted the vote and the results are listed in the table below:

Voting Carrier Voting Participant VOTE Sprint Jeff Sonnier (by email) YES Comcast Cable Randee Ryan (by phone) YES Integra Kim Isaacs (by phone) YES TWCable Victor Gaither (by phone) YES Granite Lisa Lynn (by phone) YES MegaPath Liz Tierney (by phone) YES Midcontinent Communications Emily Davis (by phone) YES Verizon Chad Warner (by phone) YES Windstream Al Finnell (by phone) YES CenturyLink Mark Coyne (by phone) YES

With the unanimous vote to update the CMP document, Susan proposed that the CMP document be updated with a level 1 notification. There were no objections. Susan said someone had identified a couple areas where the CMP document had not been rebranded and asked if those could be included with this CMP notification. There were no objections.

2/19/14 Product/Process CMP Meeting Mark Coyne– CenturyLink presented this new CR that was mentioned in the January CMP meeting. During that meeting, Kim Isaacs- Integra suggested that CenturyLink replace the specific system names CEMR and MEDIACC in the CMP document with a more generic reference. Mark said CenturyLink took that suggestion as indicated in the redlined CMP document that is posted separately to the Wholesale calendar for today’s meeting. Mark said the Sections of the CMP document that have been redlined are Sections 3.3 - CenturyLink Wholesale CMP Web Site, 5.1.4 - Systems Change Request Origination Process, 11.0 – Application-to-Application Interface Testing, 13.2 - Changes to an Existing GUI, and Appendix D: SAMPLE Change Request form. Mark said the planned effective date is April 1, 2014 and that CenturyLink plans to send out a vote notice for the March monthly meeting to update the CMP document as indicated. Per Section 2.1 of the CMP document, any updates to the CMP document require a unanimous vote. Mark asked if there were any questions. There were none.

1/15/14 Product/Process CMP Meeting (NOTE THIS IS PRIOR TO THE CR BEING ISSUED BY CENTURYLINK) New “CM” Change Request Mark Coyne – CenturyLink said CenturyLink will be issuing a new “Change Management” Change Request soon to remove references to CEMR and MEDIACC and add CEMR-MTG and MTG to the Change Management Process document and the Change Request form. Mark said we plan to present the CR next month.

Kim Isaacs - Integra said we may want to consider a generic term, i.e., Trouble Reporting system, vs. a specific system name in the updates to the CMP document.

Mark Coyne – CenturyLink said that is a good thought to include in our CMP CR proposal.

Kim Isaacs - Integra said in regard to Performance reporting, we need to look at the wording to insure there are not metrics that are specific to CEMR. Kim referenced the example of when the company switched from EDI to XML but said there was no reporting specific to EDI. Kim said she would look into any updates required there associated with CEMR and MEDIACC.

Mark Coyne – CenturyLink said we would discuss both of these areas in the February meeting. He asked if there were any questions. There were none.


Open Product/Process CR PC100516-1 Detail

 
Title: Customer Not Ready Process for ASR Requests Requiring a Build
CR Number Current Status
Date
Area Impacted Products Impacted

PC100516-1 Completed
1/18/2017
Provisioning Resale - MOE, PLT
Originator: Lyke, Cindy
Originator Company Name: CenturyLink
Owner: Bratetic, Pat
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is experiencing delays in being able to deliver service to the CLEC when a build is required on an ASR. When the delay is related to a customer situation (i.e., backboard, conduit, etc., is required), CenturyLink is implementing the following timelines for a required response from the customer. Implementing these procedures allows time for the customer to determine feasibility for the construction required, and to communicate back to CenturyLink the commitment to move forward, and/or the date that their construction will be completed. If the customer does not respond within the following timelines, the order will be cancelled:

• Scheduling and completing the Site Survey within 30 calendar days of CenturyLink contacting the end user for the initial site visit.

• Once the Site Survey is completed, within 60 calendar days, if the customer doesn’t accept requirements and commit to move forward with the build, the ASR will be cancelled. If the customer does accept requirements, but can’t meet the due date that was FOC’d, customer must SUPP the desired due date on the order to the date the customer construction will be complete.

• If the customer is not ready to install the service on the committed DD, the customer will have 90 calendar days to SUPP the desired due date on the order to the date the customer construction will be complete or the order will be cancelled.

If the customer doesn’t respond positively with the information needed to move forward within the designated timelines, the ASR will be cancelled and the customer can resubmit the ASR when those timelines are known. The new request should carry the Customer Desired Due Date of when the construction will be completed.


Status History


Project Meetings

1/18/17 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR had an effective date of December 2, 2016 and the CR has been in CLEC Test since then. During the December CMP meeting, it was requested that the CR be kept open another month. Mark said that we would like to move this CR to a Completed status. There were no objections.

12/14/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in October and the initial notice was sent October 21, 2016. One customer comment was received. CenturyLink sent the final notification and response to comments on November 16, 2016 with a planned effective date of December 2, 2016. This CR has been in CLEC Test as of that date. Mark said we would like to move this CR to a Completed status.

Kim Isaacs - Electric Lightwave asked to keep this CR open another month since there are not many of these. Kim said she wants to insure the process and information is as CenturyLink identified on a build.

Mark Coyne – CenturyLink said we will keep this open another month.

11/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this was a new CenturyLink CR that was presented last month. During the meeting, there was a question about a tariff filing. Following the monthly call, CenturyLink clarified the verbal response given during the monthly call and the CenturyLink response was also included in the draft meeting minutes. On October 21, 2016, CenturyLink sent the level 4 initial notification. Mark said there was one customer comment. The final notice and CenturyLink response to comments will be sent today with the planned effective date of December 2, 2016. Mark asked if there were any questions. There were none.

10/19/16 Product/Process CMP Meeting Cindy Lyke – CenturyLink presented this new CenturyLink CR. Cindy said CenturyLink is implementing a standard approach for customer response time that will align with other providers in the industry. When a build is required and a delay is related to a customer situation, if the customer does not respond within specified timelines, the order will be cancelled. Cindy recapped the key actions required at the 30, 60, and 90 calendar day intervals as listed in the CR. Cindy said this change will free up resources by creating efficiencies for both CenturyLink and our customers to focus on builds that are site ready. This change is targeted for an effective date of December 1, 2016. Kim Isaacs - Electric Lightwave asked whether tariff and catalogue updates would be required for Special Access, Private Line and MOE products and whether the process would apply to retail and resale.

Cindy Lyke – CenturyLink said that was correct for access services.

NOTE: 10-25-16 UPDATE following the CMP meeting from the SME team that was provided to ELI via email This CR and the new process are related to orders that require a build and are focused on working with our customers to get those orders moving forward with a commitment date from the customer so they don’t sit stagnant for long periods of time. With this new process and CR, there are NOT any tariff changes required. This process is not related to the language that is in the current tariffs as those requests do not follow the standard ordering processes as normally defined in the tariffs.

The SME team shared that they are looking at the overall language that currently resides in Section 5 of the tariffs around DD changes and the cancellation policy; they are working to create consistency across all CenturyLink tariffs. The SME team indicated that they are planning a tariff change that will be communicated in a Reseller notice that is currently planned to go out later this month. They wanted to relay this information so that when the Reseller notice is distributed, there would not be confusion with the changes being proposed with this Level 4 CR. With the planned Tariff change/reseller notice, CenturyLink will be issuing a level 3 “change in process” notice to coincide with the intrastate tariff changes.

Mark Coyne – CenturyLink asked if there were any questions. There were none. He said that CenturyLink will update the documenation and will send a level 4 notification with an effective date of December 1, 2016.


Open Product/Process CR PC111516-1 Detail

 
Title: Remove USOC AGB in North Dakota
CR Number Current Status
Date
Area Impacted Products Impacted

PC111516-1 Completed
12/14/2016
Resale
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Remove the USOC AGB in North Dakota. There are no customers with this USOC. The tariff effective date was 12/1/15.


Status History


Project Meetings

12/14/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR to remove one USOC in North Dakota was presented last month. The effective date of the tariff was actually December 15, 2015. Since there were no customers, CenturyLink requested that a level 1 notice be sent. There was customer agreement with that approach and the notice was sent on November 17, 2016 effective immediately. The CR is in CLEC Test and we would like to move this CR to a Completed status. There were no objections.

11/16/16 Product/Process CMP Meeting Lee Brummett – CenturyLink presented this walk-on CR posted separately to the calendar. Lee said this USOC which is specific to North Dakota was used for additional lines. Lee said there was one retail customer that had the service but they were transitioned to another product. There are no longer any customers that have this USOC.

Mark Coyne – CenturyLink said since there are no customers, CenturyLink would like to send a level 1 notice to be effective immediately. Mark asked if there were any objections. There were none.


Open Product/Process CR PC112116-1 Detail

 
Title: Add 3rd Party Manhole and Vault Access Construction Guidelines document to PDR PCAT
CR Number Current Status
Date
Area Impacted Products Impacted

PC112116-1 Completed
3/15/2017
Poles, Ducts and Rights of Way
Originator: Hansen, John
Originator Company Name: CenturyLink
Owner: Hansen, John
Director:
CR PM: Lorence, Susan

Description Of Change

Add a link in the Poles, Ducts and Rights of Way (PDR) Product Catalog (PCAT) to include the 3rd Party Manhole and Vault Access Construction Guidelines document that has been created to give direction to third party or other companies that access CenturyLink’s manholes and vaults.


Status History


Project Meetings

3/15/17 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC test since the effective date of February 2, 2017. We would like to move this CR to a Completed status. Mark asked if there were any objections. There were none.

2/15/17 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CMP Notification for this CR was distributed on December 19, 2016. The notice relayed that CenturyLink would be adding a link to the 3rd Party Manhole and Vault Access Construction Guidelines which will give direction to companies that access CenturyLink's manhole and vaults. Mark said there was one CLEC comment during the comment cycle. The Final notification and CenturyLink response to comments were sent January 18, 2017. The CR has been in CLEC test since the effective date of February 2, 2017. Mark said we would keep this CR in CLEC Test and review it in the March meeting. Mark asked if there were any questions. There were none.

1/18/17 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month. A Level 3 notification (the notice should have been a level 4 notification and it is being treated as such by CenturyLink) was distributed on December 19, 2016 to add a link to the 3rd Party Manhole and Vault Access Construction Guidelines. Mark said the CLEC comment cycle ended January 3, 2017 and we had one CLEC comment. The final notification and CenturyLink response to comments is to be sent today with a planned effective date of February 2, 2017.

Kim Isaacs – Electric Lightwave said that she had submitted the comment to insure that there would be no retroactive requirements from CenturyLink in regard to any existing customer arrangements, e.g., slack cable in a manhole, to which CenturyLink had previously agreed was OK.

Mark Coyne – CenturyLink said if there was prior approval by both parties, there was no issue but if there was not prior approval, there could be some remediation for those situations.

Kim Isaacs – Electric Lightwave said there may need to be more discussion about what constitutes “prior approval” to confirm agreement. Kim said her assumption is that if Electric Lightwave completed work in a manhole and CenturyLink reviewed the work and there was no identification of any issues during the CenturyLink inspection, Electric Lightwave would assume that constituted CenturyLink approval. Kim asked if that was correct.

Mark Coyne – CenturyLink said that was what was being clarified as part of the response to comments. If more discussion was required, CenturyLink could schedule something. Mark said he hopes that both sides are in agreement.

12/14/16 Product/Process CMP Meeting John Hansen – CenturyLink presented this new CR. John said CenturyLink makes post-installation inspections and has experienced a large amount of remediation scenarios due to improper work in manholes and vaults. In an effort to lessen rework, a set of guidelines has been created defining what the expectations are for the CLECs and 3rd parties that perform work in our manholes and vaults. The result is a document titled 3rd Party Manhole and Vault Access Construction Guidelines that CenturyLink is adding to the PDR PCAT to help protect the integrity of CenturyLink’s vaults and underground systems and is not intended to override any terms of a customer’s ICA. John asked if there were any questions.

Mark Coyne – CenturyLink said this CR was the result of a level 3 notice that was sent in November. We received a customer request to retract the notice and issue a CR instead.

Kim Isaacs – Electric Lightwave said CenturyLink used “guidelines” in the CR title. It was also just stated that the guidelines do not override the ICA. Kim asked what happens if a customer does not follow the guidelines and wondered if there would be issues on whether the document is applicable.

John Hansen – CenturyLink said the document is not published as a set of rules but is a guide to customers who are working underground on how to do things. If the guidelines are not followed and CenturyLink finds something is not right, it would be at the customer’s expense to make it right.

Kim Isaacs - Electric Lightwave then described a scenario where they were told to do some remediation due to slack cable in a CenturyLink manhole. Kim said her outside plant had a good reason for this and that after it was presented to CenturyLink, CenturyLink understood the rationale. Kim asked if there was room for discussion.

John Hansen – CenturyLink said yes there is room for discussion. The document is designed to be common sense rules for working in the vaults.

Mark Coyne – CenturyLink said that was the reason for using the word guidelines.

Kim Isaacs - Electric Lightwave said it was good to have the communication like the scenario that she provided.

Mark asked if there were any questions. There were none.


Open Product/Process CR PC021517-1 Detail

 
Title: Eliminate CenturyLink Search PCAT
CR Number Current Status
Date
Area Impacted Products Impacted

PC021517-1 Completed
5/17/2017
CenturyLink Search (aka QSearch)
Originator: Gomez, Lee
Originator Company Name: CenturyLink
Owner: Gomez, Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink Search (AKA) QSearch is an Electronic Directory Assistance (EDA) Service. Since the first availability of this product prior to 2004, there have been no inquiries or show of interest.

CenturyLink would like to eliminate this product effective 4/30/2017.


Status History


Project Meetings

5/17/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that the final notification was sent April 14, 2017 with an effective date of April 30, 2017. There were no customer comments. This CR has been in CLEC Test since the April 30 date. CenturyLink would like to move this to a Completed status. There were no objections.

4/19/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented last month by Lee Gomez. CenturyLink sent a Level 4 notice to eliminate the PCAT. The final notification PROD.MISC.04.14.17.F.15477.FnlElimCenturyLinkSrch was sent April 14, 2017 with effective date of April 30, 2017. No customer comments were received. This CR will be moved to CLEC Test as of that date.

3/15/17 Product/Process CMP Meeting Lee Gomez – CenturyLink presented this new CR to eliminate the CenturyLink Search which was previously known as QSearch. Lee said there has been no show of interest in this product and we would like to eliminate as of the end of April. Lee asked if there were any questions.

Susan Williams – CenturyLink asked how this product was offered.

John Hansen – CenturyLink confirmed this product was not in the ICA and said there was agreement to send this notification as a level 4 with an April 30, 2017 planned effective date.

There were no other questions.


Open Product/Process CR PC022417-1 Detail

 
Title: Grandfather Dual OC768 OWS Channels
CR Number Current Status
Date
Area Impacted Products Impacted

PC022417-1 Completed
4/19/2017
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Qwest Corporation d/b/a CenturyLink QC plans to file and post material to grandfather Protected, Unprotected and Unprotected Dual OC768 OWS Channels. No Wholesale customers have this service. The USOCs are

FDCPP, FDCPU and FDCPD.


Status History


Project Meetings

4/19/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented last month by Lee Brummett. This CR was submitted to grandfather Protected, Unprotected and Unprotected Dual OC768 OWS Channels. CenturyLink sent this as a Level 2 notice to eliminate the PCAT. No customer comments on initial notification sent March 16, 2017. The Effective date was April 6, 2017 and the CR is in CLEC Test as of that date. CenturyLink would like to move this to a Completed status. There were no objections.

3/15/17 Product/Process CMP Meeting Lee Brummett – CenturyLink presented this new CR to grandfather Protected, Unprotected and Unprotected Dual OC768 OWS Channels. Lee said there are no wholesale customers with this service and the effective date is March 31, 2017.

Mark Coyne – CenturyLink said with that effective date of March 31, 2017, we would like to send this notice as a Level 1 CMP notice since there are no customers.

Kim Isaacs – Electric Lightwave said that timing is tight and that grandfathering a product is not normally sent as a Level 1 CMP notice.

Mark Coyne – CenturyLink said we typically send a Level 2 CMP notice when there are no customers but with the effective date the end of March, we were considering a Level 1 notice.

Kim Isaacs – Electric Lightwave said for continuity purposes, she would prefer to stick with the Level 2 CMP notice. She said CenturyLink could explain the rationale in the notice. Kim asked if this product is in the Service Catalogue.

John Hansen – CenturyLink said we would include some wording in the body of the CMP notice that this product offering will be grandfathered as of March 31, 2017 in the Tariffs or Services Catalog but that the PCAT documentation update will be effective as of April 6, 2017.

Kim Isaacs – Electric Lightwave said that was good.


Open Product/Process CR PC030617-2 Detail

 
Title: Grandfather selected Centrex products
CR Number Current Status
Date
Area Impacted Products Impacted

PC030617-2 Completed
8/16/2017
Selected Centrex products
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Grandfather Centron, Centron 50, Centron XI, Centraflex II, Centraflex III in all CenturyLink QC states.


Status History


Project Meetings

8/16/2017 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated this CR is to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, Centraflex III, in all CenturyLink QC states. The planned effective date was July 20, 2017 which was right after the CMP meeting in July. The CR has been in CLEC Test since then. Mark asked if there were any objections to moving this CR to a COMPLETED status. There were none.

7/19/2017 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated this CR is to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, Centraflex III, in all CenturyLink QC states. The Level 4 final notification was distributed July 5, 2017. There were no CLEC comments. The planned effective date is July 20, 2017. We will move the CR to CLEC Test and consider moving it to a Completed status next month. Mark asked if there were any questions. There were none.

6/21/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that CenturyLink advised last month that the planned effective date for this CR to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, Centraflex III, in all CenturyLink QC states. The Level 4 Notification is now planned for distribution June 5, 2017 with a planned effective date of July 20, 2017. Mark asked if there were any questions. There were none.

5/17/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that CenturyLink advised last month that the planned effective date for this CR to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, Centraflex III, in all CenturyLink QC states has been moved from May 31, 2017 to July 2017. The Level 4 Notification is now planned for distribution June 5, 2017 with a planned effective date of July 20, 2017. Mark asked if there were any questions. There were none.

4/19/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented last month by Lee Brummett. This CR was submitted to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, and Centraflex III, in all CenturyLink QC states as of May 31, 2017. The effective date has since been extended until July 2017 and a Level 4 notification is scheduled to be distributed once the date is determined.

3/15/17 Product/Process CMP Meeting Lee Brummett – CenturyLink then presented this CR to grandfather selected Centrex products, i.e., Centron, Centron 50, Centron XI, Centraflex II, Centraflex III, in all CenturyLink QC states as of May 31, 2017. Lee asked if there are any questions.

Kim Isaacs – Electric Lightwave requested confirmation that this CR is for grandfathering and that CenturyLink will only accept disconnects.

Lee Brummett – CenturyLink said that was correct.

Mark Coyne – CenturyLink asked if there were any more questions in regard to this CR or the prior CR. There were none.


Open Product/Process CR PC060517-1 Detail

 
Title: Grandfather CenturyLink Home Phone Package
CR Number Current Status
Date
Area Impacted Products Impacted

PC060517-1 Completed
9/20/2017
Resale
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Hansen, John

Description Of Change

Effective August 18, 2017, CenturyLink will grandfather CenturyLink Home Phone Package. USOC PGOQW

08-11-17 update: Per CR originator, the effective date has been changed to September 16, 2017.


Status History


Project Meetings

9/20/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR has been in CLEC Test as of September 16, 2017. It is associated with grandfathering the CenturyLink Home Phone Package, USOC PGOQW. The effective date was originally planned for August 18, 2017 but on August 11, 2017, an update to the CR was submitted to delay the planned effective date to September 16, 2017. A revised final notification was distributed on that date to communicate the effective date change for all of the Legacy Qwest states. On September 15, 2017, CenturyLink distributed a Level 1 Product notification PROD.RESL.09.15.17.F.15716.HomePhoneExtraPkg that makes the replacement package available in the remaining Legacy Qwest states as of September 16. Effective as of July 15, 2017, the new replacement package was available in the states of Nebraska, Oregon, and Arizona. Mark stated that we would like to move this CR to a COMPLETED status and asked if there were any objections. There were none.

8/16/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this change request is associated with grandfathering the CenturyLink Home Phone Package, USOC PGOQW. The final notice was distributed August 3, 2017 with an effective date originally planned for August 18, 2017. No comments were received. On August 11, 2017, an update to the CR was submitted to delay the planned effective date to September 16, 2017. A revised final notice was distributed on that date to communicate the effective date change for all of the CenturyLink QC states. Effective as of July 15, 2017, the new replacement package is already available in the states of Nebraska, Oregon, and Arizona. The Home Phone Extra Package replacement will be available in the remaining CenturyLink QC states as of September 16 also. We will discuss this CR again next month.

7/19/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated this new CR was presented last month by Lee Brummett. The Level 4 initial notice was sent on July 5, 2017. The comment cycle closes July 20, 2017. The change has a planned effective date of August 18, 2017. In the June CMP meeting, Lee relayed that the replacement package will be announced on June 28, 2017 with an effective date of June 29, 2017. The Tariff notice was distributed June 22, 2017. CenturyLink sent a Level 1 notice on July 14, 2017 announcing the availability of the new package in the states of Nebraska, Oregon, and Arizona. We will be sending a Level 1 notification on August 11, 2017 to announce that replacement package with an effective date of August 12, 2017 for the rest of the CenturyLink QC region. Mark asked if there were any questions. There were none.

6/21/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this was a new CR to be presented by Lee Brummett.

Lee Brummett – CenturyLink said that, with the effective date of August 18, 2017 this package would be grandfathered in all CenturyLink QC states.

Kim Isaacs – Allstream asked how the package grandfathering would be handled. If a call forward number needed to be changed, would it require removing the package code?

Lee Brummett – CenturyLink stated that a replacement package would be available on July 15, 2017 in the states of Nebraska, Oregon, and Arizona and in the remaining states on August 12, 2017. A new document will be made available describing the new Home Phone Package.

Janean Van Dusen- CenturyLink stated that changes to call forwarding numbers and PIC changes could be made to existing packages despite the grandfathering, but no addition or swapping of features would be allowed.


Open Product/Process CR PC080117-1CM Detail

 
Title: CMP Doc change to eliminate maintenance of CLEC POC information and CLEC POC reports
CR Number Current Status
Date
Area Impacted Products Impacted

PC080117-1CM Completed
11/15/2017
CMP POC report
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is proposing that the CMP maintenance of CLEC Points of Contacts (POC) and the POC Reports that are posted on the CMP website be eliminated. The reports are posted to the Wholesale CMP website at http://www.centurylink.com/wholesale/cmp/index.html. Most Customer contact information is very out of date. Examples include:

o CMP primary and secondary contacts have changed

o Companies have merged, combined, are no longer in existence

o Company contacts are no longer active or have changed companies

CenturyLink is proposing changes to the CMP document that require only the CenturyLink POC information be maintained on the CMP website. The references to the POC reports will be removed.

A redline Change Management Process document will be provided.


Status History


Project Meetings

11/15/17 Product Process CMP Meeting Mark Coyne – CenturyLink reminded customers that a vote was taken in the October CMP monthly meeting and unanimous approval was received. All notifications have been distributed and all associated changes to the Website have been made. He stated that the CR is in CLEC Test as of October 24, 2017 and that CenturyLink would like to move this CR to a completed status. There were no objections.

10/18/17 Product Process CMP Meeting Mark Coyne – CenturyLink reminded callers that the idea to eliminate the CLEC POC information was initially discussed in the July Monthly CMP meeting. CLEC and PUC feedback and agreement on the initial CenturyLink proposal was received. In August, CenturyLink presented the new CR and reviewed the CenturyLink plan for CLEC input. CenturyLink also provided a view of the proposed redline changes to the CMP document and a view of what the CMP main page may then look like. These changes were discussed in detail in an ad hoc meeting that followed the September Monthly CMP meeting. A CMP notification was distributed on October 4, 2017 to relay a vote will occur in the October monthly meeting. Mark relayed that a copy of that notification was included in the CMP package. He then turned the meeting over to Susan Lorence- CenturyLink to explain the voting process and take the vote.

Susan Lorence – CenturyLink relayed that the proposed CMP document updates have been posted to the calendar for the meeting along with the proposed updates to the web page. She then reviewed the CMP Vote process as included in Section 17.0 of the CMP document (which is available at http://www.centurylink.com/wholesale/cmp/index.html). The key points of the CMP voting process are: each entity is entitled to a single vote regardless of any affiliates and quorum must be established. Susan said quorum is based on 62.5% of the average CLEC and CenturyLink entities in attendance at the last six monthly CMP meetings, April 2017 through September 2017. The average number of entities in attendance during this period was seven so the quorum for the vote was four. Quorum was met with the one email vote and 5 CLECs plus CenturyLink in attendance. Susan reviewed what a vote of “Yes” and “No” meant as depicted on the voting Ballot in the CMP package and asked if there were any questions. The vote was then conducted and the results are listed in the table:

Voting Carrier Voting Participant VOTE LS Networks Valerie Starr (by email) YES POPP Communications Rebekah Byland (by phone) YES Granite Kristi Hyacinthe (by phone) YES Allstream Kim Isaacs (by phone) YES TDS Metrocom Rod Cox (by phone) YES Windstream Lynn Denton (by phone) YES CenturyLink Mark Coyne (by phone) YES

Susan confirmed that the vote was unanimous and asked if there were any objections to updating both the CMP Document and the CMP main web page via two Level 1 notifications. There were no objections.

9/20/17 Ad Hoc CMP Meeting - following monthly CMP meeting Ad hoc meeting minutes - FINAL September 20, 2017

Attendees: Andrea Smith – Comcast Kim Isaacs – Allstream Nancy Taylor – Allstream Joyce Oliveira – Granite Jonathan Kronewitter – Granite Victoria Holland – Granite Kristi Hyacinthe – Granite Rebekah Byland – POPP Communications Larry Stevens – Iowa Utilities Board Bonnie Johnson – Minnesota Department of Commerce Lan Nguyen – Neustar Inc Emily Arnoldy – Midcontinent Communications Valerie Starr – LS Networks Denise Martinez – CenturyLink Kathy Miller – CenturyLink Tonya Woods – CenturyLink Lee Brummett – CenturyLink Nicole James – CenturyLink Rita Urevig – CenturyLink BL Marcom – CenturyLink Janean Van Dusen – CenturyLink Linda Harmon – CenturyLink Susan Williams – CenturyLink Angie Thomas – CenturyLink Tracy Strombotne – CenturyLink Renee Albersheim – CenturyLink Doris Luttrell – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink said that during the monthly meeting, Mark Coyne – CenturyLink already reviewed a brief history of the CR. She then asked those on the call to open up the redlined CMP Document that was posted to the calendar. Susan said she searched on POC and Contact to identify what would possibly need to be updated due to this proposed change. In addition to the POC changes, the proposed updates included the removal of Fax/Facsimile references.

Those on the call then walked through each of the proposed changes to each Section of the CMP Document.

Kim Isaacs – Allstream said she had a question about the inclusion of the word “assumed” in Section 2.2 Change Management Point-of-Contact. Kim asked if the CenturyLink CLEC Questionnaire asked for the designated CMP POC and if that contact could be used instead of the word “assumed”. She said some of the other companies require a CMP contact to be identified.

BL Marcom – CenturyLink said he would look at the CLEC Questionnaire.

Susan Lorence – CenturyLink then continued to review the proposed updates. In Section 3.3, she asked those on the call if the current wording that refers to how to access archived CMP information would suffice rather than adding the proposed wording later in the same Section. There was no customer preference identified and Liz Tierney – Global Capacity who originally requested the ability to get to historical data was not on the call so Susan said we would add the proposed wording in the bullet.

Susan Lorence – CenturyLink referred customers to Section 17.1 - Voter to discuss the need for a backup third party in case a CLEC was not available for a specific CMP vote.

Kim Isaacs – Allstream said the way it reads is that the most recent customer representative attending the CMP meetings could send an email designating that someone else could provide the vote.

BL Marcom – CenturyLink said though the CenturyLink CLEC Questionnaire has lots of contacts identified, he could not find a CMP POC referenced in the document.

Kim Isaacs – Allstream said it must have been another ILEC then.

Susan Lorence – CenturyLink asked if there were any other thoughts customers had on this Section 17.1. There were none. The review of the redlined document continued. Susan referred customers to Section 17.4.2 and said these proposed updates were more in line to how the voting has really occurred over the years and reflects that the POC list has not been maintained.

Kim Isaacs – Allstream said she thought that the proposed updates to this section looked ok.

The remainder of the proposed redline changes to the CMP document were reviewed.

Kim Isaacs – Allstream said she would like to discuss how the assumed POC would work when there are multiple representatives that attend the monthly CMP meeting like Allstream and Granite.

Susan Lorence – CenturyLink said she assumed that Kim would be the POC for Allstream and that if Kim could not attend a meeting where a CMP vote was to be taken that Kim would have communicated her vote to Nancy Taylor – Allstream who also regularly attends. Susan asked if that would be correct.

Kim Isaacs – Allstream said that is how the language reads. Kim said she thought she would have either let CenturyLink know that was going to occur or that she could also vote by email.

Susan Lorence – CenturyLink said the situation with Granite is worth discussing since there are four representatives. Susan asked if they would designate a main POC in that instance.

Joyce Oliveira – Granite said Jonathan Kronewitter – Granite would be their main POC.

Kim Isaacs – Allstream asked about a theoretical situation that may not pertain specifically to a CMP vote. Because we are talking about eliminating the CLEC primary POC since the contact list has not been well maintained, Kim asked what happens to those customers who do not attend CMP on a regular basis. If there was an issue, Kim asked how CenturyLink would get input.

Susan Lorence – CenturyLink said maybe it would be a good idea to walk through and talk through some different areas to see how the information would be communicated. • For a meeting like the Ad hoc call today, CenturyLink distributes a meeting notice via CenturyLink MAILOUTs to all who have signed up to receive that various categories of notices. • For Monthly meetings minutes, CenturyLink sends the meeting minutes to those who attend the call. If we have a new CLEC attendee, we search for the new person’s contact information in CCDB or ask another representative from that company to either send us their email or forward the meeting minutes. • For a new Change Request, the customer must submit the CR to the CMP CR mailbox which provides their contact information. Often another person from the company is CC’d when the CR is submitted which provides additional contacts. There is also a line on the CR form to include the current email address. • For the CMP Escalation, Dispute and Postponement processes, the submitting company must send each of those requests to the appropriate mailbox which provides an email with the contact information of a specific person. • For CR Prioritization of a release for IMA, CenturyLink distributes the Release prioritization form via MAILOUT. We expect one Release Prioritization form response back to the CMPCR mailbox from a company. If more than one Prioritization form is submitted for a specific company, CenturyLink would follow-up with that company.

Mark Coyne – CenturyLink asked if Kim was concerned with the idea of having a single POC.

Kim Isaacs – Allstream said a single POC provides some efficiency and that she wants to confirm the logistics of various areas. She said what we have talked about are good solutions for the various areas. Kim said if it is problem, it can be changed. Kim asked what are the next steps.

Susan Lorence – CenturyLink said we will send a CMP Vote notice for the October meeting with the changes we just talked through. We will likely propose that the updates to the CMP document be implemented with a level 1 notice similar to how we have done it in the past. Susan referred those on the call to the third document posted to the calendar which shows the CMP main page updates that John Hansen – CenturyLink proposed. These were good updates to provide information about the various CMP mailboxes. Susan asked if there were any questions. There were none.

Kim Isaacs – Allstream said she thinks it looks good.

Susan Lorence – CenturyLink thanked everyone for the review and discussion and for coming to agreement on what CenturyLink believes will be a positive change.

The Ad hoc meeting was adjourned at 10:00 AM MT.

9/20/17 Product Process CMP Meeting Mark Coyne – CenturyLink reminded callers that the idea to eliminate the CLEC POC information was initially discussed in the July Monthly CMP meeting. CLEC and PUC feedback and agreement on the initial CenturyLink proposal was received. In August, CenturyLink presented the new CR and reviewed the CenturyLink plan for CLEC input. CenturyLink also provided a view of the proposed redline changes to the CMP document and a view of what the CMP main page may then look like. On September 6, a CMP meeting notice CMPR.MEET.09.06.17.F.15894.AdHocMtgCRPC080117-1CM was sent to all customers to advise that an Ad Hoc call would follow this meeting. Mark said in the interim, CenturyLink continues to maintain the POC list Business as Usual; the most recent update was made as of September 13, 2017.

8/16/17 Product Process CMP Meeting Mark Coyne – CenturyLink stated this CR is a result of discussion that occurred in last month’s meeting where CenturyLink introduced the idea that we would like to eliminate the CLEC POC report since the Customer contact information is very out of date. Mark said there was good discussion during the call last month and that there was agreement that CenturyLink would issue a CMP CR to update the CMP document. The July Monthly CMP meeting minutes have been added to the new CR.

Susan Lorence – CenturyLink said that Section 2.1 of the CMP document identifies how a change to the CMP must occur. She said to allow all CLECs to be aware of and provide input to this change request, our proposal is to send a meeting notice relaying that at the end of the September monthly meetings, we would be discussing the proposed CenturyLink redlined language changes. If we come to agreement on the changes to the CMP document in September, we propose that we take a vote during the October CMP meeting. Susan asked if there were any questions about using that input approach. There were none. CenturyLink is continuing business as usual to post any requested CLEC POC information updates. Susan then reviewed the CenturyLink proposed changes:

• Post only the CenturyLink CMP Contact information and include some information about the four CMP mailboxes on the main CMP page • Eliminate the POC report and POC update web page • Provide a way to request a copy of the last POC report of historical content • Update the CMP document with more generic references for POC and contacts

Susan pointed those on the call to the third document posted to the Wholesale calendar which is the CenturyLink proposed CMP document changes for review prior to the September meeting. She said John Hansen – CenturyLink has created a redline example of proposed changes to the main page of the CMP website which is on page 21 in the monthly package. Susan asked if there were any questions. There were none.

PRELIMINARY DISCUSSION PRIOR TO CR BEING SUBMITTED BY CENTURYLINK 7/19/17 Product Process CMP Meeting - Under Attachment E in the CMP Package - Proposed Modifications to CMP Framework

Mark Coyne – CenturyLink stated that there was an item on the agenda to discuss. CenturyLink would like to explore eliminating the CMP Points of Contact (POC) Report as it is outdated. He asked Susan Lorence to elaborate.

Susan Lorence – CenturyLink stated that when the report was recently updated, it became apparent that the report may not be relevant and that we wanted to present some ideas and discuss how valuable the report was to members of CMP. Susan said two additional documents are posted to the calendar entry; a Word document identifying the instances of the term “POC” and “contact” in the CMP Document with highlights as to potential necessary changes, and a copy of the current POC report. The POC report is lengthy and contains companies and contacts that are no longer valid. Options include only posting the company contacts that are active or to only post CenturyLink CMP contacts and eliminate the POC report altogether. Susan said she thought most customers are not even aware of the POC report. Susan referred to the Word document and said there are two designations included for review: those instances that will likely require a change to the CMP document and those instances where it is not likely a change will be required. She asked those on the call what their thoughts were about the POC reports.

Bonnie Johnson – Minnesota Department of Commerce stated she had a lot of experience with this report and that she used to be very good about making updates but even her current number is incorrect. Bonnie said that she had not accessed the report in a long time and would not be opposed to its elimination. She suggested that CenturyLink could send an email to all contacts on the list and see which ones came back or CenturyLink could send a CMP notice advising that the current information would be eliminated and allow contacts to sign up anew.

Susan Lorence – CenturyLink said that certainly was one approach to start with a clean state. Susan said it would be time consuming to send an email to all contacts because those on the report are only the contacts that indicate they can be published externally. There are many more contacts in the database.

Kim Isaacs – Allstream stated that she had not used the POC report in a long time either. Her purpose in referring to the report was to find information regarding the initiator of a CR. Kim suggested that CenturyLink might consider adding CR Initiator contact information to the CR form and including it in the posted CR.

Susan Lorence – CenturyLink said another option vs. making a change to the CR that is displayed externally is for a person to use the meeting minutes that are distributed to garner the contact information for a particular CR.

Mark Coyne – CenturyLink stated that it would come down to whether companies would commit to keeping the report updated or would they simply maintain their own internal lists.

Rebecca Byland – POPP Telecom stated that they maintain their own list and do not use the POC report and would not be affected if the report were removed.

Liz Tierney – Global Capacity stated that she also does not use the POC report regularly and knows it is a significant commitment to maintain the data. Liz asked if CenturyLink could maintain the list for historical purposes since though contacts change, the report might be useful to be able to get a telephone number to try to contact someone within a company.

Susan Lorence – CenturyLink stated that was the current status of the list as basically a historical document and wondered if that would be meaningful.

Bonnie Johnson – Minnesota Department of Commerce said she understood Liz’s point about historical data but thought that having outdated information posted might be worse than having no information. Bonnie said if there is no value identified in maintaining the data, it might be best to remove it and just keep it for historical reference.

Susan Lorence – CenturyLink said it does not appear the changes to the CMP document will be that significant. She asked if it was agreeable that we create a Change Management CR and present it in the August meeting to discuss an approach to eliminate the report, provide capability to get to historical data, and post CenturyLink Points of Contact.

Kim Isaacs – Allstream stated that she was in agreement but would have to look at the language in the CMP document especially around voting.

Susan Lorence – CenturyLink said the CMP language around POCs for a CMP vote had not been strictly used in the past since the POC data was potentially out of date.

Mark Coyne – CenturyLink stated that he thought this was a good approach and that we would readdress the issue in the August CMP meeting.


Open Product/Process CR PC102417-1 Detail

 
Title: Removal of coin direct dial feature for 1+ IntraLATA calls
CR Number Current Status
Date
Area Impacted Products Impacted

PC102417-1 Completed
3/22/2018
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Hansen, John

Description Of Change

Eliminate the coin direct dial feature for IntraLATA and InterLATA calls from the tariff. This product was grandfathered about 2 years ago. We are not eliminating the service only removing this specific feature.


Status History


Project Meetings

03/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink reminded callers that this CR is to eliminate this feature that was grandfathered two years ago. The effective date was originally January 17, 2018 but was changed to March 12, 2018. The CR is in CLEC Test. CenturyLink would like to move this CR to a Completed status. There were no objections.

02/21/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that a CenturyLink CR was presented to eliminate this feature. A Level 2 notice was sent on December 27, 2018. No comments were received. The change originally had an effective date of January 17, 2018. On February 9, 2018, CenturyLink sent a notice to advise that the effective date has been changed to March 12, 2018. CenturyLink will leave this CR open and revisit in the March CMP meeting. Mark asked if there were any questions. There were none.

01/17/18 Product Process CMP Meeting Mark Coyne – CenturyLink stated that a CenturyLink CR was presented to eliminate this feature. A Level 2 notice was sent on December 27, 2018. No comments were received so no final notice is required. The change has an effective date of today, January 17, 2018. The CR will be moved to CLEC Test and will be considered for closure in the February meeting.

12/13/17 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was submitted by CenturyLink and was presented by Lee Brummett in the November monthly meeting. A Level 2 notice will be sent on December 27, 2017 with an effective date of January 17, 2018. Mark asked if there were any questions. There were none.

11/15/17 Product Process CMP Meeting Mark Coyne – CenturyLink stated that this was a new CR submitted by CenturyLink and asked Lee Brummett to present.

Lee Brummett – CenturyLink stated that this CR was to eliminate the coin direct dial feature for IntraLATA and InterLATA calls from the tariff. This product was grandfathered about two years ago and that CenturyLink is not eliminating the service only removing this specific feature. The proposed effective date at this time is expected to be January 15, 2018.

Mark Coyne – CenturyLink asked if there were any questions. There were none. Mark proposed sending the notification regarding this CR as a Level 2. There were no objections.


Open Product/Process CR PC090314-1CM Detail

 
Title: Change the WSHD hours of operation [TITLE REVISED 10 7 14 TO REMOVE: and replace the WSHD hours in the CMP document with a link to the Customer Contact Business Procedure]
CR Number Current Status
Date
Area Impacted Products Impacted

PC090314-1CM Completed
12/17/2014
Originator: Kelly, Joni
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

This CR request stems from the direction that CenturyLink IT would like to close the WSHD an hour earlier based on the most recent IT study from June 2013 through May 2014. That study shows only 11 calls were made during the last hour. Century Link would like to reduce the Wholesale System Help Desk Hours (WSHD) hours of operation from (Monday-Friday 6:00 a.m. - 8:00 p.m. (MT) and Saturday 7:00 a.m. - 3:00 p.m. MT) to Monday – Friday 6am to 7pm and Saturday from 7am to 2pm MT.

When Qwest initiated Change request PC100610-1CM in 2010, the discussion indicated that CenturyLink would revisit changing the WSHD hours after a period of time. After further study, the WSHD volume of calls has continued to be very low during the last hour.

10-7-14 UPDATE Though CenturyLink would still like to remove the WSHD hours from Section 12.7 of the CMP document, CenturyLink is retracting that language change from this CR based on CLEC feedback during the September CMP when the CR was presented. [delete CenturyLink would also like to remove the WSHD hours of operation from Section 12.7 of the Change Management Process document. Instead of continuing to publish the WSHD hours of operation in the CMP document, CenturyLink is proposing the CMP document be revised to refer to the WSHD hours of operation in the Customer Contact PCAT. This will avoid out of synch conditions when the hours are on multiple pages on the web. Going forward, any future proposed changes to the WSHD hours of operation would continue to be subject to the appropriate CMP process. end delete]

See attached redline of the CMP document for the proposed changes.

REVISED Section 12.7 AS OF 10-7-14:

12.7 Notification Intervals

CenturyLink will distribute notifications during the WSHD normal hours of operation (Monday-Friday 6:00 a.m. - [INSERT 7:00] [DELETE 8:00] p.m. (MT) and Saturday 7:00 a.m. - [INSERT 2:00] [DELETE 3:00] p.m. MT). CenturyLink will continue to work severity 1 problems outside of the WSHD hours of operation, and will communicate with the CLEC(s) as needed. A severity 2 problem may be worked outside the WSHD normal hours of operation on a case-by-case basis.

Notification Intervals are based on the severity level of the ticket, the ticket’s Disposition code (e.g., Initial, Update, Closure, etc.), and status changes.

The chart below indicates the response intervals a CLEC can expect to receive after reporting a trouble ticket to the WSHD. Beginning with the issue’s immediate acceptance as multi-CLEC impacting issue, CenturyLink will create and distribute the Initial notification.

Original REDLINE CHANGES TO CMP DOC

12.7 Notification Intervals

CenturyLink will distribute notifications during the WSHD normal hours of operation. [DELETE(Monday-Friday 6:00 a.m. - 8:00 p.m. (MT) and Saturday 7:00 a.m. - 3:00 p.m. MT).] CenturyLink will continue to work severity 1 problems outside of the WSHD hours of operation, and will communicate with the CLEC(s) as needed. A severity 2 problem may be worked outside the WSHD normal hours of operation on a case-by-case basis. [ADD For information in regard to WSHD hours, refer to the CenturyLink Customer Contact Business Procedure available at http://www.centurylink.com/wholesale/clecs/customercontacts.html. ]

Notification Intervals are based on the severity level of the ticket, the ticket’s Disposition code (e.g., Initial, Update, Closure, etc.), and status changes.

The chart below indicates the response intervals a CLEC can expect to receive after reporting a trouble ticket to the WSHD. Beginning with the issue’s immediate acceptance as multi-CLEC impacting issue, CenturyLink will create and distribute the Initial notification.


Status History


Project Meetings

12/17/14 Product/Process CMP Meeting Mark Coyne– CenturyLink said the Wholesale System Help Desk (WSHD) hours of operation update went into effect on November 18, 2014. The updates to the external documentation and the CenturyLink website, including Section 12.7 of the CMP Document, went into effect on that date. Mark said last month, Integra requested that we keep the CR open another month. CenturyLink has not heard of any issues since this went into effect. Mark asked if it was OK to move the CR to a Completed status. There were no objections.

11/19/14 Product/Process CMP Meeting Mark Coyne– CenturyLink said that in the October 15, 2014 CMP monthly meeting, the vote was conducted on the planned reduction in the WSHD hours of operation and that vote was unanimous. Mid October, CenturyLink sent a Level 3 notice to update the WSHD hours in the Customer Contact Business Procedure and on the CenturyLink website with an effective date of November 18, 2014. In addition, CenturyLink sent a level 1 notice to update Section 12.7 of the CMP Document and to also include some additional HELP TEXT updates in the CORA and CEMR-GUI where WSHD hours were listed. Mark said all updates were made with the effective date of November 18, 2014. On that date, the CR was moved to CLEC Test. Mark asked if it was OK to move the CR to a Completed status.

Kim Isaacs – Integra requested the CR be held open another month.

Mark Coyne – CenturyLink said that would be fine.

10/15/14 Product/Process CMP Meeting Mark Coyne– CenturyLink said the CR had been presented in the September CMP monthly meeting. The original CR proposed changing the Wholesale Systems Help Desk (WSHD) hours as well as removing the WSHD hours from the CMP document and replacing them with a link to the Customer Contact business procedure. Mark said based on discussion in the September CMP meeting where Integra indicated they would vote “no” on the proposed change to remove the WSHD hours from the CMP document, CenturyLink revised the CR to remove that proposed change. Mark relayed a vote notification had been distributed with the following proposed change:

SECTION of CMP Document - 12.7 Notification Intervals CenturyLink will distribute notifications during the WSHD normal hours of operation (Monday-Friday 6:00 a.m. - 78:00 p.m. (MT) and Saturday 7:00 a.m. - 23:00 p.m. MT).

Susan Lorence – CenturyLink identified Section 17.0 of the CMP document provided the instructions on how to conduct a CMP Vote. The key points of the CMP voting process are: each carrier is entitled to a single vote regardless of any affiliates, quorum must be established, an email vote for a carrier not at the meeting counts toward quorum, and a change to the CMP document requires a unanimous vote. Susan said quorum was based on 62.5% of the average CLEC and CenturyLink attendance at the last six monthly CMP meetings, April 2014 through September 2014. The average CLEC and CenturyLink attendees during this period was ten so the quorum for today’s vote meeting would be six which had been met. Susan then reviewed the votes that had been received via email and then asked those carriers on the call to provide their vote: The results are listed in the table:

Voting Carrier Voting Participant VOTE Ednetics, Inc. Susan Pharis (by email) YES Comcast Randee Ryan (by email) ABSTAIN Midcontinent Communications Emily Davis (by email) YES AT&T Frank Behnke (by phone) YES Granite Lisa Lynn (by phone) YES Integra Kim Isaacs (by phone) YES Sprint Jeff Sonnier (by phone) YES CenturyLink Mark Coyne (by phone) YES

With the unanimous vote of Yes to update the CMP document, Susan proposed that the CMP document be updated with a level 1 notification that would become effective on the same date as the level 3 notification that would be sent to update the Customer Contact business procedure with the revised WSHD hours.

Kim Isaacs – Integra asked if the updates to the CMP document would be held?

Susan Lorence – CenturyLink said yes so the CMP document update and the Customer Contact business procedure would remain in synch.

Kim Isaacs – Integra said she did not have any issue with that approach.

Susan Lorence – CenturyLink thanked everyone and said the CMP vote notification would be sent this week.

9/17/14 Product/Process CMP Meeting Joni Kelly – CenturyLink presented the new CR to update the CMP document related to the Wholesale System Help Desk (WSHD). Joni covered the reason why she was requesting the last hour of the day be cut back and reviewed data for a study she conducted from June 2013 through May 2014. Joni said she had also looked at the WSHD call data for the months of June 2014 through August 2014 and said no calls had been received during the last hour she was requesting the cutback.

Kim Isaacs – Integra asked if the WSHD personnel only had to take inbound calls. She asked if the WSHD could not be performing other jobs during that time.

Joni Kelly – CenturyLink said they could but during that window, there was no work for them and that she had looked at it.

Mark Coyne – CenturyLink asked if there were any more questions on the WSHD change in hours. There were none. He then provided why the request was being made to remove the hours from Section 12.7 of the CMP document indicating that it would make the CMP document consistent with how other Customer facing Center hours are changed per CMP. Mark said changes to other center hours are not specified in the CMP but are handled as a level 3 change in process under Section 5.4.4. Mark said CenturyLink would like to remove the hours and add a link to the Customer Contact PCAT where the hours are currently listed today.

Kim Isaacs – Integra said system support is vital. She said she would vote “No” to removing the hours from the CMP document since that would allow CenturyLink to change the hours further going forward. Kim said she wanted a say to any decrease in hours.

Mark Coyne – CenturyLink said that input could be provided via the level 3 CMP notice.

Kim Isaacs – Integra said a vote is not required with a level 3 notice. She can object to the change and CenturyLink can implement over a CLEC objection.

Mark Coyne – CenturyLink asked if there were others that wanted to provide input. There were none. Mark said he did not think an ad hoc call was required and that we would follow Section 2.1 which requires a unanimous vote which will be taken at the next CMP meeting on October 15. Mark said a mailout will be sent soon to identify that the vote will be taken at the October meeting and will include the voting instructions.

Liz Tierney – MegaPath asked if the hours are changed and there are issues, could they be reversed.

Joni Kelly – CenturyLink then relayed the after hours support process. She said once the WSHD closes, a CLEC can still call and will get a message that says the WSHD is closed. Joni said the customer can leave a message; the customer will receive a call back from WSHD personnel within 15 minutes to determine what the issue is and it will follow the ticket process.

Liz Tierney – MegaPath said that was helpful.

Susan Lorence – CenturyLink asked if that process was the same process as today.

Joni Kelly – CenturyLink said that is the same process as today and that she receives very few call-outs after hours.

Mark Coyne – CenturyLink said we would review the discussion and decide next steps based on the comment from Integra.


Open Product/Process CR PC091014-1 Detail

 
Title: Introduce changes to Technical Publication 77384
CR Number Current Status
Date
Area Impacted Products Impacted

PC091014-1 Completed
1/21/2015
Originator: Boudhaouia, Jamal
Originator Company Name: CenturyLink
Owner: Boudhaouia, Jamal
Director:
CR PM: Lorence, Susan

Description Of Change

As agreed to in the MN Docket 09-1066 Settlement, CenturyLink is sponsoring the introduction of the Changes to Technical Publication 77384. The edited document is attached to this CR.

NOTE: Redlined chapters 1, 2, 3, 5, 6, and 8 of Tech Pub 77384 were attached to the CR submission.


Status History


Project Meetings

1/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink advised that this CR has gone thru the level 4 notification process and was moved to CLEC Test as of January 5, 2015. He advised that CenturyLink would like to move this to Completed status and asked if there were any objections. There were none.

12/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial Level 4 notice was sent on November 12, 2014. The final notice and the CenturyLink response to CLEC comments were sent on December 16, 2014. The planned effective date is January 5, 2015. 11/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month by Jamal Boudhaouia – CenturyLink. There was an Ad hoc call on October 29 to review the proposed Tech Pub 77384 chapter updates. CenturyLink sent the level 4 notification on November 12 with a planned effective date of January 5, 2015. Mark said in addition to the planned revisions discussed on the ad hoc call, there were some chapters that only had rebranding. Mark asked if there were any questions. There were none.

10/29/14 Ad hoc CMP Meeting Introduce changes to Technical Publication 77384

Attendees: Kim Isaacs – Integra, Bonnie Johnson – Minnesota Department of Commerce, Laurie Roberson – Integra, Glenn Neal – CenturyLink, Jamal Boudhaouia – CenturyLink, Mark Coyne – CenturyLink, John Hansen – CenturyLink, Susan Lorence – CenturyLink

Susan Lorence – CenturyLink provided a brief agenda and background on this CR. She indicated that questions would be captured as the chapters Jamal Boudhaouia – CenturyLink reviewed the changes in the redlined Tech Pub 77384 chapters dated 5-25-12 that were posted to the wholesale calendar entry.

Jamal Boudhaouia – CenturyLink then began the review of each redlined chapter. Jamal said those on the call were already familiar with the proposed changes associated with the MN Docket 09-1066 Settlement agreement. As agreed, CenturyLink is taking the proposed Tech Pub 77384 updates through CMP so all CLECs would have the opportunity to review them.

Technical Publication 77384, Chapter 1. Jamal Boudhaouia – CenturyLink reviewed the redline updates. There were no additional proposed changes to this chapter.

Technical Publication 77384, Chapter 2. Jamal Boudhaouia – CenturyLink reviewed the redlined updates. He said in Section 2.3, there is an update from Qwest to CenturyLink. There were no additional proposed changes to this chapter.

Kim Isaacs – Integra said that she had found the references to Qwest that remain also.

Technical Publication 77384, Chapter 3. Kim Isaacs – Integra said that she found a couple instances related to xDSL Capable Loops that were an oversight where there is wording that indicates the NCIs do not affect performance, specifically in Sections 3.4.3 and 3.8.3.

Jamal Boudhaouia – CenturyLink agreed and said the sentence “The NCIs do not affect transport designs or performance” will be removed since this is a global change.

Kim Isaacs – Integra asked if in Section 3.8.3 whether wording should be added indicating that CenturyLink will provision the best available loop.

Jamal Boudhaouia – CenturyLink said he agreed and that CenturyLink would use the same wording as in the other chapters for this.

Bonnie Johnson – Minnesota Department of Commerce said the second sentence of 3.8.3 remains that says the NCI codes are informative to CenturyLink and should be removed.

Susan Lorence – CenturyLink said it was a surprise that there were still changes to be made after all of the prior review.

Kim Isaacs – Integra said that was because the group was working with multiple redlines of the Tech Pub.

Jamal Boudhaouia – CenturyLink recapped the various changes that would be made to Chapter 3, Section 3.8.3: • Remove the sentence indicating NCs does not affect transport • Change the last sentence to reflect the customer has the option to inspect copper facilities. • Insert the sentence that CenturyLink will provision best available loop. • Remove the NCI codes are informative to CenturyLink.

The specific updates will be reflected in the revised redline version.

There was agreement that all chapters of the Tech Pub will need to be given a once over.

Susan Lorence – CenturyLink said all chapters would be checked for the change from Qwest to CenturyLink, including chapters 4 and 7.

Technical Publication 77384, Chapter 5. Jamal Boudhaouia – CenturyLink reviewed the redlined updates in Section 5.1.

Kim Isaacs – Integra said the redline in Section 5.3 covers multiple options.

Jamal Boudhaouia – CenturyLink said in Section 5.5, he would make sure the title is clear. There were no additional proposed changes to this chapter.

Technical Publication 77384, Chapter 6. Jamal Boudhaouia – CenturyLink reviewed the redlined updates. He said the Table of Contents would be updated to reflect 6.2 Performance Parameter Tests.

Bonnie Johnson – Minnesota Department of Commerce said she checked Section 6 to insure the two changes had been made and they had.

Jamal Boudhaouia – CenturyLink said a global change will be made with the last sentence in Section 6.1 related to CenturyLink taking into account NC and NCI codes when assigning, etc. facilities will be made to Chapter 3, Section 3.4.3 where it says they are informative. The content in Section 3.8.3 associated with being “free of faults” will be put in Chapter 6.1 to replace the related sentence. Jamal said we will add the sentence to 6.1 regarding assigning, etc. facilities for xDSL.

Susan Lorence – CenturyLink reiterated that the redline revisions will be posted along with the meeting minutes.

Kim Isaacs – Integra said in Section 6.2, the Loop Loop should be corrected.

Jamal Boudhaouia – CenturyLink said the remaining changes in Chapter 6 had been agreed to.

All agreed there were no additional proposed changes to Chapter 6 at this time.

Technical Publication 77384, Chapter 8. Jamal Boudhaouia – CenturyLink said there were no additional redlined updates other than the change from Qwest to CenturyLink.

All agreed there were no additional proposed changes to this chapter at this time but a final review will be made.

Susan Lorence – CenturyLink proposed the following approach for review of the revisions that were identified on the call: • CenturyLink will provide the redlined Tech Pub 77384 Chapter revisions by November 5 associated with the ad hoc meeting minutes. • If the Tech Pub 77384 revisions cannot be made by that time, the ad hoc meeting minutes would be more explicit. • Following the review of the meeting minutes, CenturyLink would then send a level 4 notice with any additional revisions on November 12. • The planned effective date of the Tech Pub 77384 updates would be January 5, 2015.

There were no disagreements with this approach. Susan thanked everyone for taking time to review the Technical Publication 77384 updates.

The meeting was adjourned at 11:35 AM Mountain Time.

10/15/14 Product/Process CMP Meeting Jamal Boudhaouia – CenturyLink presented this new CR which introduces the changes to the Unbundled Loop Technical Publication as agreed to in the Minnesota Docket 09-1066 Settlement.

Susan Lorence – CenturyLink said the Ad Hoc call to review the proposed Tech Pub 77384 updates is scheduled for October 29, at 11 AM MT and a CMP meeting notification will be sent shortly.

Kim Isaacs – Integra asked if the redlined chapters to Tech Pub 77384 will be posted online.

Susan Lorence – CenturyLink said due to the size of the documents, they would be posted to the Wholesale calendar entry for the Ad Hoc call.


Open Product/Process CR PC010715-1 Detail

 
Title: Technical Publication 77351, CenturyLink Engineering Standards – General Equipment Requirements
CR Number Current Status
Date
Area Impacted Products Impacted

PC010715-1 Completed
4/15/2015
Technical Publications
Originator: Olave, Jesse
Originator Company Name: CenturyLink
Owner: Olave, Jesse
Director:
CR PM: Lorence, Susan

Description Of Change

Legacy Qwest Technical Publication 77351 is being updated to reflect the new company name of CenturyLink and to incorporate various legacy company standards into a single document. This document will also provide additional clarification to existing standards.

Redlined Tech Pub Chapters to be submitted separately.


Status History


Project Meetings

4/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test as of April 3, 2015. Mark said that last month CenturyLink shared a cross reference matrix that was developed that provides the list of changes that were made to TP 77351 that is anticipated will have an impact on the upcoming TP 77350 changes. We checked on the status of changes to TP 77350 and it still appears the new CMP CR will be issued by late April which would mean ad hoc meetings would likely begin in mid May. Mark asked if there were any objections to moving this TP 77351 CR to a Completed status. There were none.

3/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial notification associated with the Technical Publication (TP) 77351 updates was sent on February 17, 2015. The final notice and CenturyLink response to CLEC comments will be sent March 19, 2015 with a planned effective date of April 3, 2015. Mark said based on an Action Item taken during Ad Hoc calls in January and February 2015, Jesse Olave – CenturyLink developed a matrix that is included in the CMP package. The matrix provides the list of changes that were made to TP 77351 that is anticipated will have a direct impact on upcoming changes to be made to TP 77350. The matrix will also be posted to the Document Review Archive site associated with distribution of the final notice. Mark said many of the changes to TP 77351, which is associated with engineering requirements, will not be duplicated in TP 77350, which is associated with installation requirements. The matrix only reflects the planned updates to TP 77350 that are a direct result of updates to TP 77351; it is not an all inclusive list of the planned updates. Mark said the CR associated with the changes to TP 77350 will likely be issued in late April and ad hoc meetings are expected to begin in May.

Kim Isaacs – Integra asked for clarification of the references in the matrix where it states “No reference in current 77350” and whether it means that they would be added?

Mark Coyne – CenturyLink stated we will get an answer from Jesse Olave and the response would be included in the meeting minutes Kim Isaacs – Integra stated that it looked as if the TP 77350 column was the existing language that is going to be changed to match TP 77351.

Mark Coyne – CenturyLink stated that was correct.

NOTE – CMP CALL FOLLOWUP: After following up with Jesse Olave – CenturyLink, he confirmed that the same changes as occurred in TP 77351 will be made to 77350. The column in the matrix is what is in existence currently.

Kim Isaacs – Integra thanked the team that put the matrix together.

2/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented by Jesse Olave - CenturyLink in January and an ad hoc call occurred following the regular monthly CMP meeting. On February 3, a second ad hoc meeting occurred to complete the review of the remaining TP 77351 chapters. Mark said the Meeting minutes are posted to the CMP CR and an updated copy of the CR is posted the Wholesale calendar for today’s meeting. Based on discussion in the ad hoc call, there were some updates made to the TP. A 45 day level 4 CMP notification was distributed February 17, 2015 with planned effective date of April 3, 2015. Mark said we are following up on Action Items specifically the question as to when TP 77350 will be ready for CLEC review and how can we make that review more effective now that TP 77351 has been reviewed. He relayed Jesse Olave is developing a matrix to compare the differences between the two TPs.

Kim Isaacs – Integra asked if CenturyLink would know the TP 77350 timeline next month.

Mark Coyne – CenturyLink said it should be available by next month.

02-03-15 Ad Hoc Meeting

Attendees: Victor Gaither – Time Warner Cable Kim Isaacs – Integra Bonnie Johnson – Minnesota Department of Commerce Laurie Roberson – Integra Jesse Olave – CenturyLink Diana Unser – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Williams – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink relayed the purpose of the call is for attendees to review planned updates to Technical Publication (TP) 77351. She said that we got through approximately one third of the TP updates on the last call and hoped to complete the remaining chapter review on the call today.

Jesse Olave – CenturyLink said we left off on TP 77351 Chapter 6A. The call began with the review of zip file 3. He proposed reviewing each section, relaying that he would focus on the changes that provided more detail or where there was a change to the TP that would impact customers. He said he would skip the minor and grammatical changes.

Chapter 6B Auxiliary Framing - Low Type Jesse Olave – CenturyLink then reviewed the following sections in Section 6. Section 6B.4.1 – Added a Note to the Exhibit to provide more detail for the engineers.

Kim Isaacs – Integra asked what the implications were for a (2/2/15 Updates received from Integra in CAPS)[delete CUSTOMER]CLEC. She asked if existing cages would be grandfathered.

Jesse Olave – CenturyLink said it was likely that 95% of the changes in the TP did not change the standard but only provided more detail. Jesse said the revisions did not change requirements for what was currently built.

Diana Unser – CenturyLink said if customers were in a line up, then customers must match what was currently built. If they were in their own cage, that was not the case.

Kim Isaacs – Integra said if there was a virtual collo, we must follow the standard that was there. Kim asked if there (2/2/15 Updates received from Integra in CAPS)[WAS GOING TO BE [delete WERE] retroactive work.

Diana Unser – CenturyLink said as long as there is not a service hazard, then no change was required to existing space but if the space was reclaimed or there was a hazard, that would be different. Diane said most of the updates were to make the document more understandable or to provide a quick reference. She said a safety hazard is always addressed as soon as it is identified.

Section 6B.7 - Added a new bullet for clarification.

Section 6B.2-E2-2G - Added a new exhibit to clarify the existing standard. Jesse Olave – CenturyLink asked if there were any other question on 6B. There were none.

Chapter 6C Auxiliary Framing - High Type Jesse Olave – CenturyLink relayed that the Table of Contents appears like it has all changed but it was simply to add hyperlinks.

Kim Isaacs – Integra asked if Jesse had investigated the other Tech Pubs that referenced TP 77351 and how they are impacted. Kim said she was concerned that the cites (2/2/15 Updates received from Integra in CAPS) [TO TP 77351] IN THE OTHER TECH PUBS were not accurate any longer. Diana Unser – CenturyLink said Jeff Bostow – CenturyLink did not yet have a specific date as to when he will be ready for review. Diana said TP 77355 (Grounding - Central Office and Remote Electronic Equipment Environments) and 77385 (Power Equipment and Engineering Standards) have both been updated. She said these other Tech Pubs feed TP 77350 which will be the last one for updates.

Kim Isaacs – Integra said there are specific (2/2/15 Updates received from Integra in CAPS) SECTION NUMBER references[delete TO] IN these other Tech Pubs in TP 77351. She is concerned they will be out of synch.

Diana Unser – CenturyLink said not necessarily. The Section numbers were purposely not changed to keep them in synch due to references from other documents. CenturyLink does not want to renumber everything. Diana said it made the most sense internally to make the engineering updates and then determine updates to other documents.

Kim Isaacs – Integra said she thought that TP 77351 (2/2/15 Updates received from Integra in CAPS)SECTIONS had been rearranged which COULD [delete WOULD]could be a problem FOR THE OTHER TECH PUBS THAT REFER TO TP 77351. It made the most sense to her to review the changes to the TP simultaneously since TP 77350 is the one referenced in their ICAs.

Jesse Olave – CenturyLink said that Jeff Bostow – CenturyLink had been working with him concurrently to insure TP 77350 was in synch with this one. Jesse said he thought TP 77350 would soon follow.

Diana Unser – CenturyLink said that was why Jeff Bostow – CenturyLink was involved to insure TP 77351 changes were incorporated in TP 77350, e.g., clarifications and numbering updates. The previous documents TP 77355 and TP 77385 tie back to TP 77350 similar to TP 77351. Diana reiterated that Jeff Bostow – CenturyLink had been involved in all of the other TP updates and that TP 77350 should be following soon.

Kim Isaacs – Integra said it would be much easier and nice for (2/2/15 Updates received from Integra in bold or caps) [delete CUSTOMERS] CLECs to see how TP 77351 impacts TP 77350 since TP 77350 is the document referenced in their ICAs.

Susan Lorence – CenturyLink said we have noted Kim’s point that it would have been easier for (2/2/15 Updates received from Integra in bold or caps) [delete CUSTOMERS] CLECs to do these simultaneously. Susan suggested CenturyLink SMEs will meet internally to see how the review of TP 77350 can be expedited based on the other related TP updates.

Kim Isaacs – Integra said that would be very helpful since TP 77350 is so large and that this singular approach is not very efficient.

Jesse Olave – CenturyLink then reviewed the remaining changes in Chapter 6C. Section 6C.3 – Added a Note to contact Real Estate for any new ceiling racks to evaluate structural integrity.

Section 6C.5 – Added clarification for cable rack sizing and support. Jesse said the remaining exhibits are the same.

Chapter 6D Rolling Ladders Jesse Olave – CenturyLink said this chapter is not one that applies as much. He said a general note was added about rolling ladders. CenturyLink is migrating away from using these ladders. He asked if there were any questions. There were none.

Chapter 6E Earthquake and Disaster Bracing Jesse Olave – CenturyLink then provided information associated with the changes made in this chapter. Section 6E.1 – The reference to use Telcordia for zone rating is the only one retained.

Section 6E.2.2 – Added clarification to provide additional information for existing standards.

Section 6E.3.2 – Added a Figure to show what the standard means. Jesse said there are no changes to the remaining exhibits and said that concludes the changes to 6E. He asked if there were any questions. There were none. Chapter 6F Cable Distribution Systems For Conventional Floor Supported Systems Jesse Olave – CenturyLink said a new Section 6F.3 was added to provide information from CenturyLink internal documents that goes into more detail around engineering requirements and guidelines for internal and external engineers. He asked if there were any questions. There were none. Chapter 6G Fiber Protection System (FPS) - Cable Distribution for Fiber Optic Cable Jesse Olave – CenturyLink said in this Section, CenturyLink did move information around. Fiber Cable information was moved to Chapter 3 and Chapter 10 which left the Chapter 6G to be Fiber Protection.

Kim Isaacs – Integra asked if the information moved intact or was the wording changed. Kim asked if the changes had practical impacts.

Jesse Olave – CenturyLink said the wording and formatting was changed to be more logical and to provide more organization to the content. He said the intent of the content remained the same.

Section 6G.7 – This Section was moved to 6A and 6B. Section 6G.2 – Information was added and the organization of the information was modified to improve the flow. Section 6G.2.1 – Added some bullets to provide more clarification on what is allowed. Section 6G.2.7 – Added this new section to provide a reference for the engineers. Section 6G.10 and 6G.11 – Two sections were removed that do not apply. Jesse asked if there were any questions. There were none.

Chapter 7 Frame and Aisle Lighting Jesse Olave – CenturyLink said this Chapter was divided into three sections: Section A - Fluorescent Type Lighting, Section B - Appliance Outlets And Miscellaneous Conduit and Section C Emergency Lighting. He said the Table of Contents was updated to provide hyperlinks allowing access to the Figures but the overall intent was to clarify the differences between the types of lighting.

Section 7A.4 – This information was previously in internal documentation and the intent was to make it available to engineers. Some updates were formatting and rebranding. Jesse asked if there were any questions.

Kim Isaacs – Integra asked if Jesse would identify a practical change.

Jesse Olave – CenturyLink said he would identify any practical changes to CLECs.

Section 7B – The information that was added was to provide clarification and more detail to existing standards. Jesse asked if there were any questions. There were none.

Section 7C – This section provides more detail and definition on what it is and the existing standards. Some heading information was removed but detail information was retained and clarification was added.

Chapter 8 Internal Network and Operations Support Systems Jesse Olave – CenturyLink said this Chapter is related to CenturyLink internal operational support. The various sections provide the requirements for alarming and support in the CenturyLink network.

Kim Isaacs – Integra said when CLECs see “OSS”, they think of functional applications like ordering. Kim asked if CenturyLink would identify this is internal and could Jesse remove the ‘and” to make it clear that it was not functional system related.

Jesse Olave – CenturyLink and Diana Unser – CenturyLink said they were OK to remove the “and” in the Chapter title. Jesse asked if there were any questions. There were none.

Chapter 9 Alarms and Operational Support Systems Jesse Olave – CenturyLink said this Chapter is also related to CenturyLink internal operational support. He said the grammatical changes that were made do not change the intent of the content. Jesse referenced the change from CO to network facility that has occurred throughout the TP.

Chapter 10 Wire, Cable and Fiber Cable Requirements Jesse Olave – CenturyLink said a new section was added to reference Fiber Cable requirements. The information came from Chapter 6G. Jesse reviewed the various sections. He identified that some content was removed since it was no longer valid. He said some content was added to refer back to TP 77385.

Section 10.4 – The majority of information was in Section 6G so is showing here as all being added new. Jesse said that CenturyLink believed it was a better fit here. He asked if there were any questions. There were none.

Chapter 11 Network Facility Equipment Building Environment Requirements Jesse Olave – CenturyLink said this section is associated with equipment building and NEBS requirements. He said the intent remains the same but more detail was added for various sections of GR63 and GR1089. Additional detail was provided to identify where information comes from.

Section 11.3 – The temperature changes in this section reflect the NEBS requirements

Kim Isaacs – Integra asked if the maximum rate of temperature change was correct.

Jesse Olave – CenturyLink said he would check.

NOTE: Per review by Jesse Olave after the Ad hoc call, this has been reviewed and has been determined to be accurate and matches what is outlined in GR63. No changes will be necessary to this statement or values associated with this section. Section 11.4 – This section was added as a new section on its own.

Sections 11.5 through 11.11 – The majority of this information remains the same. It is consistent with what was previously published and has the same intent. Jesse said the map in Figure J-1 related to EARTHQUAKE ZONING MAP was changed to reflect the continental United States vs. the 14 state Legacy Qwest region. He asked if there were any questions. There were none.

Chapter 12 General Interaction Requirements Jesse Olave – CenturyLink said the information that was added is intended to guide engineers during equipment removal. There were also rebranding changes made. The Table A that was removed was the same table as in Chapter 11. Other updates were to include clarification for the engineers.

Chapter 13 Raised Floors Environments Jesse Olave – CenturyLink said the information in this chapter is new to provide engineers with guidance for this environment and provided a review of the various sections.

Kim Isaacs – Integra asked if the raised floor the standard for legacy Qwest states.

Jesse Olave – CenturyLink said no. For new environments, this might be a better solution but it is not considered the standard. Jesse said the grounding requirements in this chapter were reviewed by Curtis Ashton – CenturyLink and coincide with the requirements in TP 77355. Jesse said these requirements are mainly for the National side of CenturyLink. He asked if there were any questions. There were none.

Chapter 14 Acronyms/Glossary Jesse Olave – CenturyLink said there were minor changes to add new definitions or provide more information.

Chapter 15 References Jesse Olave – CenturyLink said information was updated to provide more current release references for the various documents that are listed.

Jesse Olave – CenturyLink asked if there were any overall questions about the review. There were none.

Susan Lorence – CenturyLink said the next steps are to send the meeting minutes out and to follow-up on any Action Items that were identified during the calls. Once Jesse makes the agreed upon updates to the TP, a level 4 CMP notification will be sent for the 14 state region that follows the normal CMP review and comment cycle. Susan said a separate notification will be sent for the remaining CenturyLink states that will have the same planned effective date as the CMP notice. The CenturyLink SME team will follow-up with Jeff Bostow, CenturyLink owner of TP 77350, to determine when his TP will be available for review and find the best approach to identify changes in his document that were already discussed here. Susan asked if there were any questions. There were none. She thanked everyone for their participation and feedback.

The meeting was adjourned at 11:05 AM Mountain Time.

01/21/2015 Ad Hoc Meeting minutes (following CMP monthly meeting) Attendees: Randee Ryan – Comcast Kim Isaacs – Integra Laurie Roberson – Integra Liz Tierney – Megapath Victor Gaither – Time Warner Cable Jesse Olave – CenturyLink Diana Unser – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Mark Coyne – CenturyLink suggested that we start walking through each redlined chapter of TP 77351 that was posted to the Wholesale calendar.

Jesse Olave – CenturyLink said there are lots of changes redlined in these Technical Publication (TP) updates however the majority of the changes are clarifications and adding additional detail to the information that was already there.

Kim Isaacs – Integra said she had an overall question first – what was the CLEC implication to changing the wording from “Central office” to “network facility”.

Jesse Olave – CenturyLink said there are no implications. The intent is to use a more general term vs. a central office environment.

Technical Publication 77351, Chapter 2. Jesse Olave – CenturyLink said reviewed the redline updates where additional information and clarifying information was added. Jesse said in Table 2.1, EQUIPMENT AISLE SPACING, some requirements were changed and reviewed those changes however Jesse said the absolute minimum requirements in this instance remains the same.

Diana Unser – CenturyLink and Jesse Olave – CenturyLink pointed to the specific points that were added that impact spacing requirements.

Kim Isaacs – Integra asked when customers are adding equipment to a collocation, are these the standards that should be used?

Diana Unser – CenturyLink said yes. There are still the same limitations on a variety of requirements but it is part of the form that customers have to fill out to add additional equipment to an existing space.

Kim Isaacs – Integra said what if adding equipment to an existing space, have the standards changed so that equipment could not be added without re-engineering?

Diana Unser – CenturyLink said it depends on what is added but it could prompt CenturyLink to go to Real Estate for a reevaluation of what is being requested and what currently exists in the space. Diana said the goal is for both customer equipment and CenturyLink equipment continues to work as it should.

Jesse Olave – CenturyLink said the intent of this section of the document has not changed but it is to provide more details as to the engineering requirements.

Diana Unser – CenturyLink said CenturyLink would follow the same process and decision criteria for an existing space and the additional details are to have the engineer made the good decisions.

Jesse Olave – CenturyLink asked if there were additional questions and said if something comes up he could definitely review an area again.

Technical Publication 77351, Sections 2.2.1.4 and 2.2.4. Jesse Olave – CenturyLink said this section was updated to provide additional information. Some of the content was only available internally before and was added to assist in engineering decisions.

Technical Publication 77351, Sections 2.5.1 Jesse Olave – CenturyLink said this section was updated to change the minimum size of the door to be more the size of a normal door.

Technical Publication 77351, Sections 2.5.3 Jesse Olave – CenturyLink said this section was not changed but was updated to provide more detail and to provide options available.

Technical Publication 77351, Sections 2.5.5 Jesse Olave – CenturyLink said this section was updated to provide additional information.

Kim Isaacs – Integra asked if there were changes or was it only to provide more detail.

Jesse Olave – CenturyLink said that is correct. The intent has not changed but more detail is being added.

Kim Isaacs – Integra said this update should not impact them since they are already meeting the standards.

Diana Unser – CenturyLink said correct but it should help customer engineers also so they don’t have to ask as many questions.

Technical Publication 77351, Sections 2.7.6 Jesse Olave – CenturyLink said this section is new but it is consistent with TP 77385. He asked if there were any other questions on Chapter 2. There were none.

Technical Publication 77351, Chapter 3 Jesse Olave – CenturyLink said there are a lot of redlines in this chapter because it was reorganized, more definitions and detail was added format changes were made.

Technical Publication 77351, Sections 3.2 and 3.3 Jesse Olave – CenturyLink said the specific requirements in these sections have not changed. References are now more generic and some subsections were added to provide more detail.

Technical Publication 77351, Section 3.4 Jesse Olave – CenturyLink said new subsections were added to provide additional detail to internal and external engineers. Some information was previously internal and is being added here. Jesse said some of this information used to be in Section 6.G but has been pulled up in the Tech Pub as a better fit here.

Laurie Roberson – Integra said some of the information was in Chapter 6 and some was internal information. She asked if she looked at Chapter 6, would was moved be clear?

Jesse Olave – CenturyLink said yes but some of the wording was updated during the move but it should still be clear.

Diana Unser – CenturyLink said also more Figures were added to help everyone.

Jesse Olave – CenturyLink reviewed the additional subsections that were added or moved. He asked if there were any questions.

Kim Isaacs – Integra asked if in Section 3.4.1.1, was there a new sentence about the POI and manhole and asked about the closest manhole and splice cases.

Diana Unser – CenturyLink said there is a separate TP for this. Diana said manhole Zero is typically very crowded and it is not recommended for everything. It cannot support a lot of splice cases due to space requirements.

Kim Isaacs – Integra said the statement that it was not used as a POI was a concern since some are.

Jesse Olave – CenturyLink said they would revisit this wording but that the TP was to set the standard and some sites may not meet the standard but for those a letter of deviation is required like today.

Kim Isaacs – Integra said a letter of deviation may delay the process and this is a blanket statement.

Jesse Olave – CenturyLink said they would revisit the wording in Section 3.4.1.1, bullet item 2, last sentence and would work with Regulatory Compliance to see if clarification is required. He asked if there were any more questions for Chapter 3. There were none. Jesse recommended skipping a review of Chapter 4 which has few changes and relates to TP 77385. He also recommended skipping Chapter 5 since the update that was made did not impact Legacy Q and the Chapter relates to TP 77355.

Kim Isaacs – Integra asked if the changes in Chapter 4 and 5 then synch up with the current TPs?

Jesse Olave – CenturyLink said yes they do. The TP author for the two TPs reviewed the chapters to insure they were in synch. Technical Publication 77351, Chapter 6, Section A Jesse Olave – CenturyLink said there are a lot of redlines but they relate to formatting changes to be able to hyperlink to the Table of Contents. Changes were made to rebrand the document to CenturyLink. Jesse said a new Section 6A.2.3 was added to include criteria about cable racks that does not exist in Legacy Q.

Kim Isaacs – Integra had a question about the first added sentence in Section 6A.1 that states “Any material referenced throughout the chapter refers to currently approved CenturyLink material.” Jesse Olave – CenturyLink said CenturyLink only orders CenturyLink approved material so the statement is included to state that specifically for the engineers.

Kim Isaacs – Integra said that made sense.

Jesse Olave – CenturyLink said there was an update to Section 6A.4.1, Table 2 which was really a correction. He reviewed the updates through Section 6A.7 relaying that additional direction, clarifying information and recommendations were added for the engineers. Jesse said a lot of the information was previously in 6G but was moved here. Jesse said most of Section 6A.8 was eliminated. He said the majority of the information in Section 6A.9 is the same but is now organized differently. He said Section 6A.9.1.A and Section 6A.9.1.B were broken out to address Cable Hole for floors and walls separately.

Kim Isaacs – Integra asked if there were significant changes in this area.

Jesse Olave – CenturyLink said it was mostly a clarification of standards and the additional of more details. The intent of these sections did not change.

Laurie Roberson – Integra identified a typo is Section 6A.9.2 in the first bullet.

Jesse Olave – CenturyLink said for Section 6A.9.3 there were some minor changes to use Project Number instead of Order number and to also add a “Fire Assembly Number or Engineering Judgement Number” and “Responsible Party Contact Information”. This information is now required to provide who is responsible. Jesse said all of the remaining exhibits in this section did not change but some new exhibits were added for clarification. The exhibits were updated to allow a hyperlink to them. Jesse asked if there were any questions on Chapter 6A. There were none.

Mark Coyne – CenturyLink said we have made it through two of the five TP files and proposed another call to review the remaining three.

Jesse Olave – CenturyLink said Chapter 2 had the most actual changes so a two hour call should allow the remaining chapters to be reviewed. He said Chapters 10-12 and 14, 15 had minimal changes. He said Chapter 13 is a new chapter on Raised Floor environments for engineers.

Susan Lorence – CenturyLink asked the group if they would prefer a two hour call or two one hour calls.

Randee Ryan – Comcast said they would prefer one two hour call.

All agreed a two hour call would be preferred.

Susan Lorence – CenturyLink proposed the date of February 3 and that was what participants agreed upon.

Kim Isaacs – Integra said there was an Action Item that the CenturyLink SME team would review the other TPs to see how these TP 77351 updates impacted them.

Jesse Olave – CenturyLink confirmed that action item and said CenturyLink appreciated the feedback. He said 77350 was already being looked at 77353 and 77385 were already reviewed and are line.

The meeting was adjourned at 11:00 AM Mountain Time.

01/21/2015 Monthly Product Process CMP Meeting Mark Coyne – CenturyLink said Jesse Olave - CenturyLink would be presenting this CR but relayed that at the conclusion of the CMP meeting, Jesse would review the redline chapters which were available on the CMP monthly meeting calendar entry.

Jesse Olave – CenturyLink described the Tech Pub and advised that the document was being updated to reflect the new company name of CenturyLink and to incorporate various legacy company standards into a single document. Jesse said the intent of the document had not changed but updates would provide additional detail and clarification to existing standards to make it more user-friendly. He stated that the published Version G was the baseline and some of the chapters were rearranged and that some content was moved between chapters.

Kim Isaacs – Integra stated that this TP does not apply to CLECs and does not appear in their ICA, but rather applies to suppliers and engineers. She asked if the changes being made would impact TPs that are included in their ICA. Kim said she was interested in knowing the changes the CLECs would have to make based on these TP changes and if it applied to new collocations or if CenturyLink would use the changes to monitor compliance issues to existing collocations. Kim said she understood that the TP said existing environments would be grandfathered but asked how would that be managed.

Jesse Olave – CenturyLink said the requirements relay to how equipment is deployed to be NEBS level 3 compliant and said that the intent of this TP had not changed with the previous version, but that it provided more detail and CenturyLink was making provisions to supply more cooling, for example, via aisle spacing. The existing environments that complied with the previous TP version were not impacted. He said if there were exceptions to the existing environments, those would need to continue to grow as required.

Kim Isaacs – Integra stated that is the problem. Kim wanted to know when the TPs in their ICA would be updated so that she will know as a CLEC what those standards would be. Kim said this is not a TP that CLECs would reference.

Diana Unser – CenturyLink stated that the TP was accessible and CLECs could refer to it.

Kim Isaacs – Integra said it was not what governed their ICA terms. CLECs would defer to the TPs in their ICA and that this TP would not be the governing document and that she was concerned they would be out of sync which was a problem.

Mark Coyne – CenturyLink asked if the concern was that updates to this document would result in necessary changes to other documents mentioned in the ICA.

Kim Isaacs – Integra confirmed and stated that she didn’t know which updates to TP 77351 would affect them.

Mark Coyne – CenturyLink stated we would take an action item and follow up.

Jesse Olave – CenturyLink said he was not familiar with the ICA process.

Kim Isaacs – Integra said any updates to the current ICA would require an amendment and gave an example of TP 77350 which was in their ICA.

Jesse Olave – CenturyLink stated that the author of TP 77350 was making corresponding updates to TP 77351 and that CLECs would see those updates soon.

Kim Isaacs – Integra asked if there was any concern with holding off on the changes to TP 77351 until TP 77350 was available so they can compare the changes in both.

Jesse Olave – CenturyLink said he understood the concern but holding off on the changes to TP 77351 would impact the timing of when other CenturyLink regions would use this document.

Diana Unser – CenturyLink said TP 77351 is basic engineering for regulated spaces and is a predecessor to TP 77350 which refers to installation. Because of that, TP 77351 has to be updated first and may trigger an update TP 77350. Diana said CLECs should ask if they have any questions based on what is currently done.

Kim Isaacs – Integra recommended that CenturyLink identify what changes in TP 77351 would impact them.

Mark Coyne – CenturyLink proposed that when CenturyLink reviewed the TP 77351 updates, that the SME team would identify what might lead to a future update of the other TPs.

Diana Unser – CenturyLink yes they could. Diana reiterated that the majority of updates to TP 77351 were clarifications; there were not a lot of changes.

Kim Isaacs – Integra said that would work but said since the document was so large, more than one call would be necessary. Kim asked if content had been moved without redlining since large sections were added but it was difficult to find the related deletion.

Jesse Olave – CenturyLink stated that some moves were made but since the document was so large, there are deletions in one chapter that were added to a different chapter. Jesse said that did not happen often but he could identify those sections during the review.

Mark Coyne – CenturyLink stated that we would follow this approach during the review. He asked if everyone was OK with that approach.

Kim Isaacs – Integra said she was not 100% comfortable but was OK to move forward for now.


Open Product/Process CR PC010715-2 Detail

 
Title: Spectral Interference Cause Code/Analysis Code
CR Number Current Status
Date
Area Impacted Products Impacted

PC010715-2 Completed
2/17/2016
Unbundled Loop
Originator: Boudhaouia, Jamal
Originator Company Name: CenturyLink
Owner: Boudhaouia, Jamal
Director:
CR PM: Lorence, Susan

Description Of Change

As agreed to in the MN 1066 Settlement Agreement; CenturyLink will be introducing a new code to be used as stated below:

CenturyLink will introduce spectrum interference Cause Code using the Integra criteria in Attachment B. CenturyLink will submit a CMP CR. The code should be implemented no later than 6 months after this settlement agreement is approved by the Commission.

The Criteria Document is also attached.


Status History


Project Meetings

02/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since May 2015. There was a desire to keep this CR open until the Network Trial was established. A Network notification was distributed on January 21, 2016 to relay there would be a six month Technical Trial from February 1, 2016 through July 31, 2016. Mark said we would like to move this CR to a Completed status. There were no objections.

01/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test.

Jamal Boudhaouia – CenturyLink said that through a series of meetings with the MN DOC and certain CLECs, there is agreement on the network trial that will be conducted on four DSLAMs. He said a network trial notice will be distributed on January 21, 2016 to relay the trial will start on February 1, 2016 and will last for six months. Jamal will review the trouble tickets on the four DSLAMs for spectral interference issues and will provide a monthly report as well as conduct a meeting to review the results.

Susan Lorence – CenturyLink said that now that the network trial is to begin, she requested consideration that this CR be moved to a Completed status in the February CMP monthly meeting. There were no comments to this proposed request.

12/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test and said he had not heard Jamal Boudhaouia – CenturyLink on the call.

Susan Lorence – CenturyLink said she heard from Jamal and that he is unable to attend the call today. Susan said Jamal relayed that he had received the data he needed and would be sending it out in the next day or so for his meeting on Friday, December 18, 2015 at 11AM MT.

Laurie Roberson – Integra said that Jamal’s meeting is on the wrong date on the Wholesale calendar.

Susan Lorence – CenturyLink said she would make the update following the CMP call.

11/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR, though it is in CLEC Test, is being kept open until the Network Trial has been completed.

Jamal Boudhaouia – CenturyLink said regarding the calls related to the Technical Trial, the group has had to change direction as to which DSLAMs will be considered. Jamal said he has provided the CLECs and MN DOC with five DSLAMS to consider and is waiting on retrieval on archive information. He said a call will be set up for early December as to next steps.

NOTE: On November 19, 2015, a General notification GENL.ANNC.11.19.15.F.14095.FNLPlnngMtgNtwkTechTrial was sent to relay the next meeting date of December 3, 2015. The notice is available on the Customer Notification Letter Archive (CNLA) at http://wholesale.centurylinkapps.com/cnla.

10/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink stated this CR has been requested to remain open until the network technical trial is completed. Jamal Boudhaouia – CenturyLink sent a meeting notice on October 13, 2015 to relay there is a final planning meeting on Wednesday, October 28, 2015 for the network technical trial. That meeting is posted to the Wholesale calendar. Mark asked Jamal Boudhaouia – CenturyLink if he had anything to add.

Jamal Boudhaouia – CenturyLink stated that he would send the remaining data for the October 28, 2015 meeting no later than Monday, October 26, 2015.

09/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink stated this CR has been in CLEC Test since May 8, 2015 but that during the call last month, there is a desire to keep this CR open until the Network Trial has completed. Mark said we will continue to monitor it each month.

Bonnie Johnson – Minnesota Department of Commerce asked if she had missed the follow-up documentation that was to be sent after the last network call.

Jamal Boudhaouia - CenturyLink said he had provided some of the information but was still researching the trouble ticket history of the cross boxes.

Bonnie Johnson – Minnesota Department of Commerce said she would like the CenturyLink commitments to be met and expressed concern that this has been delayed for so long.

Jamal Boudhaouia - CenturyLink said he agreed and that he is trying to pull the information from the archives.

Mark Coyne – CenturyLink stated the concern would be noted.

08/19/15 Product/Process CMP Meeting Susan Lorence – CenturyLink stated that his CR had an effective date of May 8, 2015 when an update to the Maintenance and Repair Business Procedure went into effect. The CR has been held open for some additional calls that CenturyLink has been conducting. A call was held on Tuesday, August 18, 2015 to talk about finalizing the Network Trial. Susan asked if it was acceptable to close this CR at this point.

Bonnie Johnson – Minnesota Department of Commerce requested that it remain open through the Network Trial.

Kim Isaacs – Integra agreed.

Susan Lorence – CenturyLink stated that it would remain open through the Trial.

07/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC test. A meeting invite was sent on July 12, 2015 for a customer conference call on Tuesday, July 28, 2015 to finalize the Trial requirements.

Bonnie Johnson – Minnesota Department of Commerce initially thought that meeting date might not work due to being out of the office but then determined the date would work after all.

Jamal Boudhaouia – CenturyLink said if anyone had not seen the meeting invite to let him know.

Mark Coyne – CenturyLink said the CR would remain in CLEC Test.

6/17/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC test. The CenturyLink CR owner Jamal Boudhaouia was not on the call. Mark said in the May CMP call, Kim Isaacs – Integra was going to do some checking on this CR.

Kim Isaacs – Integra said she had checked and said she believes this CR is related to the Spectrum Management trials in Minnesota so she prefers the CR be left open.

Mark Coyne – CenturyLink said Jamal is working on getting the trials moving.

Bonnie Johnson – Minnesota Department of Commerce said she agreed with Integra that this CR needed to be left open. Bonnie said while Jamal is out, she is working with Tom Freeberg – CenturyLink to identify potential 2015 DSLAM deployments that are scheduled in Minnesota. Mark Coyne – CenturyLink said the CR would remain in CLEC Test.

5/20/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was moved to CLEC Test as of May 8, 2015. This CR is associated with an update to an existing Trouble Code associated with spectrum interference per the Minnesota Docket 1066 and Mark asked if there was any objection to moving this CR to a Completed status.

Kim Isaacs – Integra asked if this CR was to put the spectrum interference code in place and was not about the process for developing the spectrum interference trial.

Susan Lorence - CenturyLink said that was true. Jamal Boudhaouia - CenturyLink had a separate effort associated with the spectrum interference trial where meetings had been held to discuss that piece.

Kim Isaacs – Integra said there had not been a recent meeting on it and asked to keep the CR open until she could do more checking.

Mark Coyne – CenturyLink said yes we would review the CR in June.

4/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial Level 4 notification was sent early March 2015 and the CLEC comments were due to close mid March but we received a request from Bonnie Johnson - Minnesota Department of Commerce to extend the formal comment cycle until a CenturyLink call related to a 1066 document requirement was conducted. Mark said that call occurred on March 20, 2015. During that call, CenturyLink agreed to retract the original Level 4 notice and resend a new notice with additional information. The revised level 4 notice was sent on March 26. The CLEC Comments were due last Friday, April 10. CLEC comments were received and the final notice and CenturyLink response to comments is due April 23 with an effective date of May 8. Mark asked if there were any questions. There were none.

3/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial Level 4 notification was sent on March 2, 2015. The CLEC comments were due to close on March 17, 2015 but we received a request from Bonnie Johnson - Minnesota Department of Commerce to extend the formal comment cycle until a CenturyLink call related to a 1066 document requirement was conducted. That call had been rescheduled from March 11, 2015 to March 20, 2015, due to a CenturyLink issue. Based on the request from Bonnie, the CLEC comment cycle was extended until March 23, 2015. Mark said the final notice is scheduled for April 1, 2015 with a planned effective date of April 16, 2015.

2/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink reminded everyone that this CR was presented by Jamal Boudhaouia last month. He said the CenturyLink SME team is currently reviewing the Cause Codes to confirm which code to use. Once that is determined, CenturyLink will be sending a level 4 notice.

1/21/15 Product/Process CMP Meeting Jamal Boudhaouia - CenturyLink presented this new CR that was part of the MN 1066 Settlement Agreement that CenturyLink will introduce spectrum interference Cause Code/Analysis Code when there may be spectrum interference issues on unbundled loops. Jamal referenced Attachment B for the critieria to be used. Jamal said the Cause Code has not yet been established.

NOTE: The Attachment B referenced in the CR and in the CMP meeting has been posted to the Wholesale calendar for the January 2015 CMP monthly meeting. For reference purposes, it is also included at the end of these meeting minutes.

Mark Coyne – CenturyLink asked if the new code would be introduced with a level 4 notification once it had been determined.

Jamal Boudhaouia – CenturyLink confirmed.

Mark Coyne- CenturyLink asked if there were any questions. There were none.


CenturyLink Response

3/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial Level 4 notification was sent on March 2, 2015. The CLEC comments were due to close on March 17, 2015 but we received a request from Bonnie Johnson - Minnesota Department of Commerce to extend the formal comment cycle until a CenturyLink call related to a 1066 document requirement was conducted. That call had been rescheduled from March 11, 2015 to March 20, 2015, due to a CenturyLink issue. Based on the request from Bonnie, the CLEC comment cycle was extended until March 23, 2015. Mark said the final notice is scheduled for April 1, 2015 with a planned effective date of April 16, 2015.


Open Product/Process CR PC042915-1 Detail

 
Title: Technical Publication 77350, CenturyLink, Telecommunications Equipment Installation Guidelines
CR Number Current Status
Date
Area Impacted Products Impacted

PC042915-1 Completed
8/17/2016
Technical Publication
Originator: Bostow, Jeff
Originator Company Name: CenturyLink
Owner: Bostow, Jeff
Director:
CR PM: Lorence, Susan

Description Of Change

Formerly titled Qwest Technical Publication 77350 has been revised to reflect the company name change from Qwest Communications to that of CenturyLink. In addition, this revised publication seeks to incorporate various legacy company standards into a one-company approach to Inside Plant (ISP) installation guidelines. These revised guidelines also provide a needed update to existing standards.

Expected Deliverables/Proposed Implementation Date: 08-01-15


Status History


Project Meetings

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test as of July 1, 2016 and asked if the CR could be moved to Completed status. There were no objections.

7/20/16 Product/Process CMP Meeting PC042915-1 Technical Publication 77350, CenturyLink, Telecommunications Equipment Installation Guidelines PC011516-1 CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Requirements and Testing on Technical Standards associated with CenturyLink Telecommunications Equipment Installation Guidelines (Tech Pub 77350) Mark Coyne – CenturyLink said he would provide an update on these two CRs at the same time. Both CRs are in CLEC Test as of July 1, 2016. Mark said a Level 3 notice was sent on July 6, 2016 to implement a further change to the CLEC Badge Access Request web site and the CLEC Badge Access Request Job Aid to include a wording update about the Badge acknowledgement process; the wording had originally been included as part of the final notice for these two CRs that was distributed on June 16, 2016. Mark said CenturyLink received a postponement request from Integra to delay implementation of the additional wording changes. Due to the postponement request, CenturyLink retracted that update and resent the redlined language as a Level 3 change on July 6, 2016 with an effective date of August 19, 2016. Mark said the specific information about the postponement request is available as Postponement #3 on the CMP Oversight Committee & Escalation/Dispute Information website at http://www.centurylink.com/wholesale/cmp/escdisp.html under Postponement Archive.

Kim Isaacs – Integra said she submitted comments on the Level 3 change that states Integra objects to the added language in the Badge Access tool. Kim said the process is covered by their ICA and has similar terms governing collocation access. (7-29-16 Updates received from Integra in CAPS) CENTURYLINK ALLOWS ONLY [delete WITH] one point of contact (POC) for each company [delete ALLOWED], that POC is an administrator and is not the right person to acknowledge the process for each badge holder or for their company.

Mark Coyne – CenturyLink said CenturyLink will review the Integra comments with our legal and SME team.

Kim Isaacs – Integra said her concern is that CenturyLink is (7-29-16 Updates received from Integra in CAPS) TRYING TO USE [delete USING] this same badge access site for CLECs and [delete THEIR SUB-CONTRACTORS] CENTURYLINK’S CONTRACTORS and those CenturyLink relationships are different. Kim said she thinks the badge acknowledgement language is redundant since the CLEC has an ICA but said she can understand the language being necessary when there is not an ICA.

Mark Coyne – CenturyLink said it might be that CenturyLink needs to include additional language like “unless otherwise specified within the ICA”.

Liz Tierney – Global Capacity said that she thinks adding requirements at the Collocation Access site is not needed. Liz said the ICA is explicit regarding access and that we need to remove barriers. Mark Coyne – CenturyLink said we will consider the comments and provide the CenturyLink response with the Final notice due August 4, 2016. Mark asked if there were questions. There were none.

6/15/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said he would provide an update on this CR and CR PC011516-1at the same time since they are related. He said there were several notifications that were distributed associated with these changes: two level 4 notices and one Level 3. The initial notices were sent on May 25, 2016 that included a formal comment cycle that ended June 9. CenturyLink did receive customer comments. The final notices and response to comments are due on June 16, 2016. The changes will become effective on July 1, 2016. The CRs will then be moved to CLEC Test and will be reviewed in the July CMP meeting. Mark asked if there were questions. There were none.

5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said in the April monthly CMP meeting, he had reviewed the additional CenturyLink proposed language updates to Chapter 2. Mark said Kim Isaacs – Integra had requested examples of some scenarios associated with the Chapter 2 redlined language. Based on this request, the CR originator Jeff Bostow – CenturyLink added some examples within the Tech Pub for reference. On May 2, 2016, an Ad Hoc call was conducted to review the newly proposed changes to Chapter 2. The call participants agreed to the proposed wording. Also on the Ad Hoc call, participants reviewed the September 2015 Action Item list to determine if the remaining open Action Items from January 2016 could be closed. There were no outstanding issues. Mark said the final version of the proposed changes to Chapter 2, the final version of the Action Item list, and the meeting minutes for the May 2, 2016 call are all posted to the Wholesale calendar. A level 4 notice timeline was then agreed to that has an effective date of July 1, 2016. Mark said that following the Ad Hoc call, the CenturyLink SME team had to tweak the notification timeline somewhat to provide some additional time on the front end to add some clean up for Level 0 changes and to synch up redlines and the Table of Contents. The revised timeline sticks with a Tech Pub 77350 Issue O effective date of July 1, 2016 but has the Level 4 notice going out on May 25, 2016. Mark asked if there were any questions. There were none.

05/02/16 Ad hoc meeting minutes Attendees: Brendan Hamel – Granite Kim Isaacs – Integra Laurie Roberson – Integra Jeff Bostow – CenturyLink Rita Urevig – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink went over an agenda for the meeting and then a brief history of the two CRs, PC042915-1 and PC011516-1. Susan said that during the meeting, she would like to take down specific Action Items that need to be resolved versus capturing detailed discussion of the examples that may be included in the Tech Pub.

CR PC042915-1 Technical Publication 77350 Jeff Bostow – CenturyLink then reviewed the CenturyLink proposed Tech Pub 77350 language dated April 28, 2016 that is posted to the CMP calendar entry for the meeting. The wording updates are associated with the CenturyLink response to questions posed during the CMP monthly meeting on April 20, 2016. Jeff spoke to Section 2.1.2 of the Tech Pub and said there are two types of Methods of Procedure (MOP) – General and specific. The MOP is required for CenturyLink and their subcontractors due to PUC requirements in case there is a service interruption; it shows the scope of the work and who is performing it. A MOP is not required if a CLEC is working solely within their space – caged or cageless. Jeff said the wording updates to Section 2.1.2 are to show a MOP is required if any work is performed in the shared space and has included examples in the Tech Pub wording to show when a MOP will be required. Jeff asked if the new language met what the group intended.

Kim Isaacs – Integra said she needed to run the newly proposed language passed her CO technicians. She said she did not think the CLEC could do any of the work listed.

Jeff Bostow – CenturyLink said that was correct but there have been some occasions where a CLEC has started performing some of this work themselves.

Kim Isaacs – Integra thanked Jeff for the examples and said she would review the new Tech Pub wording internally but that the proposed CenturyLink wording since mid April has been a good balance. Kim said she thought there would not likely be issues with these newly proposed updates. With the April 15, 2016 CenturyLink wording in Section 2, Integra believes they are protected for the day to day work they perform in their collocation space.

Jeff Bostow – CenturyLink said excellent. Susan Lorence – CenturyLink said the examples were added due to the Integra requests during the April monthly CMP call. She then referred call participants to Section 2.1.4.2 to review those wording changes. Susan said she thought Integra had reviewed the 04-15-16 wording and Jeff had made some updates to address the requests from the Monthly call.

Kim Isaacs – Integra said she liked Jeff’s 04-28-16 updates which make the responsibilities clearer.

Jeff Bostow – CenturyLink said the wording is intended to say a CLEC can perform their normal business routine in their collocation space but when work is required in the shared space, the Tech Pub wording applies.

Susan Lorence – CenturyLink asked if there were any other changes in Section 2 that had to be discussed. There were none. Susan then referred call participants to the Action Item list from September 2015 posted to the calendar to see if open items remain. She thought the open items were originally related to the Tech Pub wording changes that were just discussed and the Competency Test/badging wording which will be discussed next. Susan asked about the Action Item 16 related to Network Change Management System (NCMS) process.

Kim Isaacs – Integra said she was fine on that one.

Jeff Bostow – CenturyLink said the NCMS process now covers all of CenturyLink – Local and National.

Susan Lorence – CenturyLink said we will show Action Item 16 completed. She asked about Action Item 5 related to the badging process and whether she could refer that item to the Competency Test CR. No one disagreed. Susan said we will now show all of the Action Items Completed. Susan asked about discussion of a timeline.

Jeff Bostow – CenturyLink said Integra needed some time to review the wording.

Kim Isaacs – Integra said she could reply back by May 11, 2016 as to the whether Integra was OK with the most recently proposed Tech Pub 77350 wording changes.

Susan Lorence – CenturyLink asked Brendan Hamel – Granite if Granite could also meet a May 11, 2016 to provide any concerns.

Brendan Hamel – Granite said he could meet that date.

Susan Lorence – CenturyLink asked for any concerns to be sent to the CMPCOMM@centurylink.com mailbox by May 11, 2016.

PC011516-1 CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Testing Susan Lorence – CenturyLink then pointed call attendees to the third document posted to the Wholesale calendar associated with the CLEC Competency Test CR. Susan said this draft document was created by John Hansen - CenturyLink in a Business Procedure format from the draft Competency Test Process Guide that Jeff had reviewed in the ad hoc meeting in January 2016.

Jeff Bostow – CenturyLink said this document has basically the same content as the CenturyLink internal document but has more of a CMP format. He said this document only applies to work outside of normal CLEC business activities. When a CLEC needs to expand their current model, an Inside Plant Central Office Installation Technician would be required which is an industry title that has been in existence for 30 years or so. Jeff said the Competency Test was developed after some problems in network installation attributed to human error. The Competency Test was aligned with the badging process depending on the work that is to be performed. Jeff said there are two types of testing that are aligned with Telcordia/Ericsson levels: Central Office Equipment (COE) Installer only (Level 1-3) and COE plus Power (Level 4). If the person taking the test successfully passes the Competency Test questions, their badge reflects certification to work in the CO to that level and it allows CenturyLink to be aware of subcontractor capabilities. Jeff said CenturyLink has been pleased with the result of the Competency Test process.

Kim Isaacs – Integra said she has reviewed the Business Procedure and asked how the Competency Test would appear.

Jeff Bostow – CenturyLink said a button would be added to the newly revised CenturyLink badging process to have a CLEC self identify up front to see if they are performing their normal work activities. That should allow no disruption to a CLECs current process. The Competency Test only is required if the CLEC indicates they are going to perform installation work. Jeff said he was not aware of when the newly revised badging website was to be reinstated.

Susan Lorence – CenturyLink said the newly revised badging website and Collocation – CenturyLink Premises Access Overview Business Procedure are to be effective May 18, 2016. CenturyLink is working on the response to CLEC comments that will be posted on May 3, 2016. Following the effective date of May 18, 2016, CenturyLink will work with the SME team to revise this Competency Test documentation and possibly the Collocation – CenturyLink Premises Access Overview Business Procedure to incorporate any changes in the process for CLEC testing.

John Hansen – CenturyLink said he wants to insure there is only one location to update associated with each of the processes.

Kim Isaacs – Integra said she wants to minimize confusion on these processes. Integra has a special point of contact (SPOC) for badging.

John Hansen – CenturyLink said the original information in the Competency Test documentation was not correct as it pointed to the old badging process and it will have to be updated. The first iteration of the badging tool does not have the Competency Test information included since the Tech Pub 77350 and Competency Test related issues were not yet resolved. CenturyLink wanted to get the revised badging website in production before making these Tech Pub related changes. John said there will be some radio buttons that ask what the CLEC scope of work will be. If it is the normal CLEC Collocation work, then the process will flow as today. If the work includes a broader scope, e.g., power work, it will stop the process and require the Competency Test. John asked if that made sense.

Kim Isaacs – Integra said yes.

Susan Lorence – CenturyLink said we will need to clarify in the documentation if a CLEC technician already has a badge and that needs to be expanded to include a further scope of work, e.g., COE or COE plus power, how does the process of competency testing and re-badging occur.

Kim Isaacs – Integra said she will have a chance to review the revised process when the CMP notice is sent. She is thinking if a MOP is required, it could be a trigger internally for Integra to determine if a Competency Test is required.

Jeff Bostow – CenturyLink said the process will apply to both the CLEC and their subcontractor. He said today a CLEC does not have to file a MOP if they are working in their space.

Kim Isaacs – Integra said if their project meets the requirements for a general or detail MOP, their internal process might be tied to the MOP to indicate the Competency Test may be required. Kim said Integra already uses the approved CenturyLink subcontractors for work and they probably have already been tested.

Susan Lorence – CenturyLink said it sounds like we can talk about a timeline for submitting the two Level 4 changes. With the May 11 date for CLEC responses for review of the most recent Tech Pub 77350 updates, the May 18 date for the effective date of the Badging website, Susan proposed that we notify with the two level 4 notifications as of May 19, 2016 with a 45 day timeline.

John Hansen – CenturyLink said he thought that would work from a documentation perspective.

Kim Isaacs – Integra agreed that the two processes for the Tech Pub and the Competency Test should be notified separately.

Brendan Hamel – Granite said he was OK with the May 19 date.

Susan Lorence – CenturyLink proposed that we may need to tweak the notification timelines somewhat but that we would work the various dates to make the changes become effective as of July 1, 2016.

Jeff Bostow – CenturyLink said that will be Issue O of Tech Pub 77350 that will become effective.

All agreed that it was very exciting to think that after the lengthy discussions, these Tech Pub and Competency Test changes will become effective as of July 1, 2016.

Susan Lorence – CenturyLink thanked everyone for their time and said CenturyLink will relay the timeline in the May CMP meeting.

The Ad hoc meeting was adjourned at 11:00 AM MT.

4/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was discussed in March CMP meeting. He said on March 30, 2016, CenturyLink received proposed wording from Integra. On April 13, 2016, CenturyLink scheduled Ad hoc call for this CR and the CR associated with CLEC Competency Testing. Due to unforeseen circumstances, this meeting to review CenturyLink alternately proposed language will have to be rescheduled.

Susan Lorence – CenturyLink stated that the meeting would be rescheduled for May 3, 2016 from 9:00-10:30 AM MT.

Kim Isaacs – Integra stated that May 3-4 was an LNPA working group meeting.

Susan Lorence – CenturyLink offered to move the date to May 2, 2016 from 10:00-11:30 AM MT. There were no objections.

Mark Coyne – CenturyLink asked to take a few minutes to review the CenturyLink proposed wording to get a head start on the issues to be proactive in advance of the next ad hoc call.

Susan Lorence – CenturyLink directed callers to the fourth document on the Wholesale Calendar following the monthly meeting that included the proposed CenturyLink wording. [NOTE: For document references, the Ad Hoc meeting is now on the May 2, 2016 Wholesale calendar entry.]

Mark Coyne – CenturyLink stated that the first proposal in Section 2.1 was accepted by CLECs. He then advised that the next proposed wording example was in Section 2.1.2 and presented the fact that CenturyLink’s intention was to take both exclusion wording proposed by the CLECs and the inclusion wording proposed by CenturyLink and present both in the document to cover the concerns of both parties.

Kim Isaacs – Integra asked for examples prior to the Ad Hoc call of the last sentence in Section 2.1.2 of the CenturyLink proposed language which states: If CLEC equipment is installed or work is done that is not installed solely in a “Caged Location” area or a “Cageless Location” space and/or potentially affects the CenturyLink network, the MOP standard shall apply.

Mark Coyne – CenturyLink asked Kim and other customers if the additional CenturyLink proposed wording was acceptable with the exception of the addition of the examples.

Kim Isaacs – Integra stated that she wants to discuss the wording with her business units but that the wording appears to be moving in the right direction.

Mark Coyne – CenturyLink said he thought the use of the words “may” and “shall” addressed the concerns on both sides. Mark then moved to Section 2.1.4.2 and presented the proposed Integra wording and the CenturyLink proposed changes saying the intent is to have both parties covered. Mark asked if there were any questions on this prior to the Ad Hoc call.

Kim Isaacs – Integra also asked for examples for this section ahead of the Ad Hoc call. She asked if the term “facility footprint” could be further defined and for clarification of the information in the last sentence.

Susan Lorence – CenturyLink stated that she would review the last sentence wording with Jeff Bostow - CenturyLink to get it clarified.

Kim Isaacs – Integra requested examples of what work would require a Competency exam by a CLEC technician.

Liz Tierney – Global Capacity stated that she agreed that these efforts were moving in a positive direction. Liz said their ICAs don’t allow them in the CenturyLink space.

Mark Coyne – CenturyLink asked if there were any other questions on this CR. There were none.

3/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said the last Ad Hoc call for this CR was held on January 28, 2016. The main concern with the proposed changes to the Tech Pub 77350 within the CLEC community seems to be with the use of the term “Service Supplier” to refer to CLECs and their subcontractors. Mark said on February 19, 2016, CenturyLink had received proposed redlined language for Chapter 2 of the Tech Pub 77350 from Liz Tierney, Global Capacity. That redlined language is included in the CMP package on pages 24 thru 51. Mark said CenturyLink had reviewed the CLEC proposed language with our SME team which includes Regulatory and Compliance representatives. CenturyLink has provided some alternative wording to be added to Chapter 2, Paragraph 2.1.5.1 which is also in the CMP package on page 52. Mark said the current approach is to add a NOTE that defines when a CLEC/CLEC Subcontractor will not be considered a “service supplier” in the context of the Tech Pub. Mark said hopefully this approach makes it clearer. He said that customers will likely want to have some time to review this proposed language within their companies.

Armando Fimbres - Oregon Public Utility Commission asked when CLEC comments should be returned to CenturyLink.

Mark Coyne – CenturyLink said we would like CLEC comments back within the next week to 10 days and would then hold a call to review both this CR and the CLEC Competency Test CR toward the end of March or early April. He said we could also hold the review in the April meeting.

Liz Tierney – Global Capacity said the wording that CLECs proposed and the CenturyLink wording are saying the same thing. Liz said CLECs already have wording in their ICAs to restrict them from certain CO space. The CLEC wording identifies that the Competency Test is required when the CLECs needs to be in the shared space. Liz said she would review both sets of wording changes.

Mark Coyne – CenturyLink said our approach would be to use the original CenturyLink redline Tech Pub wording and the new CenturyLink NOTE which hopefully provides a more simplified approach to exclude a CLEC/CLEC Subcontractor when they are working in their own CO space.

Kim Isaacs – Integra said there is a sentence in Section 2.1.2 of the proposed Tech Pub that states that the Tech Pub applies to CLECs in their Caged or Cageless space. Kim said that wording and the new CenturyLink wording seems mutually exclusive and asked if that sentence was specific to the MOP. Kim said a further clarification may be required here to indicate something about the MOP standard applying.

Mark Coyne – CenturyLink asked CLECs to consider this section and the new CenturyLink proposed wording and see if there are any further CLEC proposed changes. He asked if any CLEC proposed changes could be provided by the end of the month.

Kim Isaacs – Integra said the CLECs would need two weeks to review and propose changes.

Mark Coyne – CenturyLink said once the CLEC proposed wording is received, CenturyLink will then determine if the meeting to review the changes will be during the April monthly meeting. He said the CenturyLink proposed wording being added in Section 2.1.5.1 also impacts the CenturyLink CR for the Competency Test.

Kim Isaacs – Integra said she did not understand when a CLEC tech would be required to take the Competency Test.

Mark Coyne – CenturyLink said he thinks it is anytime a CLEC is outside of their Collo space.

Liz Tierney – Global Capacity said the CLECs are restricted today from being outside that Collo space.

Kim Isaacs – Integra said with the CenturyLink NOTE and their ICA language, it does not appear that a CLEC would be in the CenturyLink space. The question is then when would a CLEC need to take the Competency Test.

Mark Coyne – CenturyLink said we would take that question back to our SME team.

02/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said two Ad Hoc calls had been held in September 2015 to review the planned updates to Tech Pub 77350. Two January calls were held to review Action Items and the CenturyLink responses to the Tech Pub review calls held last September. Mark said the CLEC community is considering clarifying language to add to the Tech Pub associated with the key Action Items. Once those additional redlines are received, CenturyLink will schedule another ad hoc call to review the CLEC proposed language. Mark asked if there were any questions. There were none.

01/28/16 Ad hoc meeting minutes FINAL Attendees: Larry Couch – Action Communications Kim Isaacs – Integra Nancy Swanson – Mobius Communications Victor Gaither – TW Cable Carl Caughran – CenturyLink Jeff Bostow – CenturyLink Renee Albersheim – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink provided a brief history of this CR for those players that were new. Susan said that the CenturyLink SME team had met with Legal and Regulatory on one of the new Action Items from the January 7, 2016 Ad hoc meeting which was to consider adding wording specific to CLECs in Section 16 of the Tech Pub 77350 that the “ICA Controls”. Susan read the following response from the Legal and Regulatory team:

The CenturyLink Legal and Compliance teams have determined that no additional updates to Tech Pub 77350 are required. They believe the Tech Pub has general applicability. The ICA that is negotiated with each customer has the general terms that apply to all aspects of their business with CenturyLink. The Legal team believes that adding wording to the Tech Pub would be unnecessarily duplicative.

Susan said that any customer that has concern with this approach and wished to discuss it further should have their Legal representative contact the CenturyLink Legal representative Jeff Nodland at Jeff.Nodland@CenturyLink.com. Susan then provided a status on the second Action Item from the January 7 call which was to create a CR to provide documentation on the Competency Testing. The CR was initialed by Jeff Bostow – CenturyLink and was presented at the January monthly CMP meeting. That CR is PC011516-1, CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Requirements and Testing on Technical Standards associated with CenturyLink Telecommunications Equipment Installation Guidelines (Tech Pub 77350), and there will be a separate Ad Hoc call for that new CR following this meeting.

Kim Isaacs – Integra said she was disappointed that CenturyLink was not going to add the “ICA Controls” wording to the Tech Pub. She said [2/8/16 Updates received from Integra in CAPS] CENTURYLINK’S DECISION this will require THAT INTEGRA COMPLETE an extensive legal review of the Tech Pub as they [ delete DO WITH] WOULD WITH ANY CHANGES TO THE TERMS OF with their ICA. Kim said that will add considerable time to the Tech Pub timeline and said AS AN ILLUSTRATION they have been in ICA negotiations for five years. Kim asked if Jeff understood the implications.

Jeff Bostow – CenturyLink asked if this issue only applied to the current revisions as the majority of the Tech Pub was from the last update in 2007 and would not be up for review and negotiation.

Kim Isaacs – Integra said the wording that a CLEC is synonymous with “Service Supplier” changes the [2/8/16 Updates received from Integra in CAPS] [delete SCOPE] APPLICABILITY of the Tech Pub and is a big issue. It was previously viewed that “Service Supplier” applied to a CenturyLink contractor vs. a CLEC or their contractors. Kim said the Tech Pub would now require their legal review to consider every instance of Service Supplier and insert Integra to determine impact ESPECIALLY ANY ADDITIONAL LIABILITY OR INDEMNIFICATION LANGUAGE IN THE TECH PUB.

Jeff Bostow – CenturyLink said that the use of Service Supplier in the Tech Pub means any CenturyLink employee, CLEC or subcontractor entity that is solely working in the shared local network space to conduct inside plant installation or removal activity. Jeff gave examples of the IOF area, footprint, stored program controls. Jeff said a caged space is exempt.

Kim Isaacs – Integra said there is no issue with the Tech Pub standards as listed. She said she has talked with her technicians and they understand it clearly. Kim said they already have language in their ICA that addresses indemnification and liability and this adds to it and will take a long time to review. Kim said it is not clear in the definition what shared space means [2/8/16 Updates received from Integra in CAPS] AND ANY EXCEPTIONS THAT APPLY TO CLECS.

Jeff Bostow – CenturyLink said with the scope of the Tech Pub77350, it already implies that the person this applies to is an Inside Plant Supplier (ISP).

Kim Isaacs – Integra said [2/8/16 Updates received from Integra in CAPS] IT IMPLIES BUT DOESN’T SAY AND the first time ISP is used is Section 2.1.11.

Jeff Bostow – CenturyLink read Section 2.1.4.2 which is also included under Action Item 1 of the Action Item matrix.

Kim Isaacs – Integra said that language needs to be [2/8/16 Updates received from Integra in CAPS] [delete MORE CLEAR] CLEARER.

Susan Lorence – CenturyLink asked if Integra would want to take that language back to their legal team for review and redline.

Carl Caughran – CenturyLink said he has reviewed this specific language in the field and they believe it is very clear and understandable that a customer can be in their cage without certification but if they are in the shared space, certification is required. Carl said he thinks Jeff has done a great job to protect CLECs since it was not clear previously.

Kim Isaacs – Integra agreed it was not clear previously and [2/8/16 Updates received from Integra in CAPS] IT STILL NEEDS TO CLEARER said she will work with her Ops team and legal to add more clarity.

Susan Lorence – CenturyLink said ICA terms are outside of CMP and wondered if Kim will have her legal team work with CenturyLink’s.

Kim Isaacs – Integra said she will send the redlined language to the CMP mailbox which allows review in CMP and then CenturyLink can review with legal. Kim said she will also include wording about how this applies to day to day operations.

Susan Lorence – CenturyLink said that will work great and then CenturyLink can send to the CenturyLink review team.

Jeff Bostow – CenturyLink said the title of the Tech Pub is key to what it applies to – equipment installation guidelines.

Victor Gaither – TW Cable said looking at Section 2, using the definition of a shared space, a level 4 lead would have to be certified to work there. Victor said this is different in how he deals with other ILECs for the shared space and said he thought CenturyLink should be consistent with how the industry handles cage and cageless which is an open environment. He said this document implies that any work in the cageless space requires a level 4 certification.

Kim Isaacs – Integra said she agreed.

Victor Gaither – TW Cable said his concern is that there needs to be clarity around the CLEC owned space, whether caged or cageless, and that a customer can work in their own space. He said he agreed that if the work extends out of the CLEC space, then the Level 4 certification applies.

Jeff Bostow – CenturyLink described two network terms used previously: CO Tech (Central Office Tech) who does the day to day work, and the COEIT (Central Office Installation Tech) who builds the network.

Victor Gaither – TW Cable said he works with two Collo teams across the nation and that ILEC Collo is more complex. He said their Tier 2 is likely the same as CenturyLink Level 1-3 and that their Tier 1 are those that do installs, test, and is allowed to do power work, etc. which may equate to CenturyLink Level 4. Victor said his local teams need to understand who can do which work for work assignment.

Kim Isaacs – Integra said she agreed with Victor. She said the Tech Pub is not clear and if they are bound to the Tech Pub, it needs to be specific with no wiggle room.

Carl Caughran – CenturyLink said again that he believes the CenturyLink field is very clear with the revised Tech Pub wording in Section 2.1.4.2 and that there is no confusion there.

Susan Lorence – CenturyLink said it sounds like Integra took an action item to redline Section 2.1.4.2 language to make it more clear. Then CenturyLink will take that wording back to the CenturyLink review team for consideration.

Victor Gaither – TW Cable said he thinks there is agreement that when looking at inside plant, cage or cageless, Level 1-3 can work in their own space but anything else requires Level 4 and thought that was consistent with the industry which was important. Victor said that needs to be clear in the document.

Kim Isaacs – Integra said she will review Section 2 in its entirety to propose some redline that will make it abundantly clear. Kim said she understands Jeff’s intent but does not think the Tech Pub [2/8/16 Updates received from Integra in CAPS] [delete SAYS THAT] CAPTURES CENTURYLINK’S INTENT.

Victor Gaither – TW Cable said if Kim can propose some words that are more exact, everyone wins.

There was further discussion and disagreement among those on the call as to whether the redlined Tech Pub language was clear or not. It was believed that the intent might be clear but that there could limitations that could be interpreted in the language.

Susan Lorence – CenturyLink said she thought the plan of action is for Kim to review Section 2 and propose some wording that will add clarity. CenturyLink will then review that wording with our Legal and Compliance team to see if we can resolve this main point of contention. She said the other action items do not seem like they will take much time.

Kim Isaacs – Integra agreed that the Tech Pub standards are not the problem and said she had reviewed the Action Items and did not have any concerns.

The Ad hoc meeting was adjourned at 1:55 PM MT.

01/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said two Ad Hoc calls had been held in September to review the Tech Pub 77350 updates. The CR originator, Jeff Bostow – CenturyLink, then investigated the identified Action Items from the two calls. On January 7, 2016, an Ad Hoc meeting was conducted to review the CenturyLink response to each Action Item. Another Ad Hoc call is scheduled for January 28, 2016 to continue to review the Action Item matrix and provide feedback on the meeting that the CenturyLink SME team agreed to hold with CenturyLink Legal. Mark said we hope to provide a response from the CenturyLink Legal team prior to the next meeting. As part of the discussion in the January 7, 2016 Ad Hoc call, CenturyLink agreed to issue a new CR to capture the process for Competency Testing for the CLEC technicians. Mark said if all goes well in the January 28, 2016 Ad Hoc call, CenturyLink will propose a Level 4 notice be sent by early February with an expected implementation date of mid March. Mark asked if there were any questions. There were none. [1/29/16 Updates received from Integra in CAPS] BASED STATEMENTS CENTURYLINK MADE ON THE 1/28/16 AD HOC CALL – IT IS INTEGRA UNDERSTANDING THAT THE INTENT OF THE CHANGES TO TECH PUB. 77350 ONLY WHEN THE CLEC CHOOSES TO HAVE ITS EMPLOYEES INSTALL OR DECOMMISSION A COLLOCATION SPACE; OR WORK WITH POWER. ONCE THE CLEC COLLOCATION SPACE IS ESTABLISHED, DAY TO DAY OPERATIONS, EQUIPMENT OR CARD ADDITIONS, TECH PUB 77350 STANDARDS MINIMALLY APPLIED TO THE CLEC’S ACTIVITY WITH THE EXCEPTION BEING HEALTH AND SAFETY.

01/07/16 Ad hoc meeting minutes Attendees: Brendan Hamel – Granite Telecommunications Laurie Roberson – Integra Kim Isaacs – Integra Carl Caughran – CenturyLink Jeff Bostow – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink said this call was to review the CenturyLink responses to the Action Items that were taken during Ad Hoc calls on September 23, 2015 and September 30, 2015. The call participants referred to the Action Item matrix posted to the Wholesale calendar.

Action Item 1 - Section 2.1.4.2 Jeff Bostow – CenturyLink reviewed the proposed changes to Section 2.1.4.2 as listed in the matrix.

Kim Isaacs – Integra relayed that this was not the direction that she had expected the redline Tech Put language for this Action Item to take. She indicated she was expecting to see a statement that where terms differ or there is a conflict, the terms of the ICA control. She mentioned competency assessments and the need for a statement that their ICA controls if there are issues concerning these assessments. Kim said the entirety of the Tech Pub 77350 is part of the ICA and the redlined wording could imply these rules to be retroactive for customers. She did not understand the reference to “equipment placed” which she felt might be construed as requiring retrofit to meet standards.

Jeff Bostow – CenturyLink said there was no intent for this Tech Pub to imply any retrofitting. The scope was all on a going forward basis. He said he was trying to meld the needs of the business with needs of the CLEC community.

Kim Isaacs – Integra said there was a need to clearly delineate the difference between service supplier and the CLECs and that there are different terms that control. She said it is the same as Chapter 2, Par. 2.1.5.1 where there was an attempted definition of CLEC. This issue was problematic within most of the document and could open up for more misunderstanding and conflict.

Jeff Bostow – CenturyLink asked if that was the premise of other CLECs.

Brendan Hamel – Granite Telecommunications stated that Granite had no problems to this point but would continue to investigate.

Kim Isaacs – Integra asked if Granite currently takes the CenturyLink competency test.

Brendan Hamel – Granite Telecommunications said his role was to update the guides and would speak to his department directly.

Kim Isaacs – Integra said she will need additional time for review and would ask Integra techs about the possibility to take the test before they apply for and are granted an access badge. Kim said her concern was if they use the resource and there is a problem. The Tech Pub currently reads that the Integra techs must meet the Level 4 competency within the system. Jeff Bostow – CenturyLink said the issue is whether the tech is performing in a caged space or any part of the shared CenturyLink footprint. Jeff said the direction is not to be punitive but to insure the sanctity of the network and those working on it perform with competency.

Kim Isaacs – Integra said she understood that there is a need for all to meet OSHA, NEC, and UL standards but there is a history between CLECs and CenturyLink of being competitors and that CenturyLink could potentially use this requirement to not let Integra into the CO. Kim said with over 12 years of job experience, there was a need for clear language that CLECs can agree to and appropriate technical standards but that the ICA prevails. Susan Lorence - CenturyLink said we need to take this back to CenturyLink legal for guidance.

Kim Isaacs – Integra said she needed review by her legal team also but believed the legal folks from each company will also disagree.

Action Item 2 - Section 2.1.6 Jeff Bostow – CenturyLink reviewed the proposed wording change.

Kim Isaacs – Integra said as she had mentioned before, her concern is about CLEC synonyms and use of the term “service supplier.” She believed that some applied to CLEC and some applied to CenturyLink and that it was strange that these terms were synonymous.

Jeff Bostow – CenturyLink said with the Tech Pub 77350 initial mission/scope, that the existing terminology was correct. But as the Tech Pub title suggests, Telecommunications Equipment Installation Guidelines, it is not intended to be about personnel. He asked if that was acceptable.

Kim Isaacs – Integra said she would need to run it past her legal team. Action Item 3 - Section 2.1.11 and 15.2.3 Kim Isaacs – Integra said that the ICA identifies each partner’s responsibility for the build out of a location. CLECs have not previously had the requirement to take the competency test. That would be based on each customer.

Jeff Bostow – CenturyLink said if there was an outage, CenturyLink would be liable. He gave an example of an accidental human error that causes an outage during a hot power cutover. Jeff said a report would need to be filed with the PUC and that there could be a fine involved. Several Tech Pubs, 77350, 77351 and 77385, were being clarified across the CenturyLink 38 states as a company standard. Language was being tightened up and that technicians would get badged if deemed competent. He said, with due respect, the process is a defense mechanism for CenturyLink on who gets access to facilities.

Kim Isaacs – Integra said, also with due respect, there is a reason to be careful. Kim said the industry has matured but this requirement could be misconstrued to make competition more difficult. The technical specifications are not the issue. The issue is when a tech is in a facility, there is no ability to look at the ICA and how a violation has to be addressed. She said she does not know what to do with this as the CO techs have not had this competency requirement previously and with this, now they must access a web site and determine the required competency test(s).

Jeff Bostow – CenturyLink said vendors have access to the competency test outside the firewall and any vendor has access.

Kim Isaacs – Integra said there is no process or methodology in the PCATs or the ICA associated with CLECs and competency testing. The Tech Pub needs to address this. Kim said she is trying to protect Integra interests and consider what has occurred in the past.

Jeff Bostow – CenturyLink said nothing is going to change on how CLECs gain access to their enclosed space. He said he could see the point about embedded entity. Access is addressed under a separate umbrella as a CLEC customer. He stated that these access requirements are not to be misconstrued as retroactive.

Carl Caughran – CenturyLink said there is a distinction in regard to types of CO space. CenturyLink is protecting our interests and this is addressing general space not collocation space. If a CLEC tech is trying to install in the general space, rules are mandated. Carl said he understands that Kim is trying to protect against rogue CO managers and that the wording in the Tech Pub under Section 2.1.11 says if a CLEC tech is working in their space, there is no need to provide proof of competency.

Kim Isaacs – Integra stated that point is exactly what she is asking for but currently it is not clearly stated in the Tech Pub. Kim said the matrix says that for this Action Item but that wording is not in the Tech Pub and should be added. She asked where in 2.1.11 that was stated.

Jeff Bostow – CenturyLink confirmed it does not say that in the Tech Pub.

Kim Isaacs – Integra said she has two key points in the discussion that the Tech Pub needs to provide some protection for the CLECs: 1) The reference that the ICA controls. 2) The requirement around competency testing.

Jeff Bostow – CenturyLink said if a reference is added to the Tech Pub for a specific component of the ICA and that the ICA controls, the reference implies “separate but equal” and he does not want it to mislead anyone.

Kim Isaacs – Integra said there should be a specific section of the Tech Pub to address how the Tech Pub applies to CLECs and their ICA.

Susan Lorence – CenturyLink said CenturyLink needs to take a step back and let Legal figure out how they propose addressing this issue. If competency testing for CLECs remains, CenturyLink could then issue a CR to let the CLEC community know what was expected.

Kim Isaacs – Integra said Section 16 of the Tech Pub could be updated to elaborate on how the Tech Pub applies to CLECs and that a policy statement could be added at the beginning of the document to refer to Section 16 for CLECs.

Jeff Bostow – CenturyLink said that is a shield of defense of the customer to add the reference to the ICA in one section.

There was some discussion on how to best draft wording between CenturyLink and CLECs for Section 16 so that nothing is lost. There was agreement that CenturyLink would draft wording and review with their legal team and that it could be exchanged between CenturyLink and CLECs. It would then be available for review by all participants in the next ad hoc meeting.

Susan Lorence – CenturyLink proposed the next ad hoc meeting be scheduled for January 21, 2016 at 10 AM MT. A meeting notification would be sent. She said we only made it through three Action Items but thought that these three were critical to resolve and could impact the resolution on the remaining Action Items.

The Ad hoc meeting was adjourned at 11:00 AM MT.

NOTE: Due to conflicts, CenturyLink is moving the next ad hoc meeting planned for January 21, 2016 to January 28, 2016. A meeting notification will be sent by January18, 2016.

12/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said two ad hoc calls were held in September to review the Tech Pub 77350 updates. CenturyLink has created a matrix that provides the Action Items from those meetings. A CMP meeting notice was sent to schedule a call for December 17 at 9:30 AM MT. Mark said if the December 17 Ad hoc call goes as planned, we will propose sending the level 4 notice out for formal review and comment on the Tech Pub 77350 updates by the end of year with an expected implementation date in early February. Mark asked if there were any questions. There were none.

NOTE: Due to a last minute conflict, a meeting notification was sent on December 16, 2015 to relay the Tech Pub 77350 Ad Hoc call was moved to January 7, 2016 at 10 AM MT.

11/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the SME team has been working on the Action Items. Considering various schedules and the Thanksgiving holiday, the meeting was planned for December 1 but has subsequently been moved to December 9. The matrix of the Action Items and the CenturyLink responses will be provided prior to the Ad hoc call.

NOTE: As of November 24, 2015, it appears the date will need to be moved again to later in December. Date and time to be confirmed via a Meeting notice.

10/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said there were two ad hoc calls to review the redlined Tech Pub 77350; one was held on September 23 and one on September 30. CenturyLink is creating a matrix of all of the Action Items from the two meetings and an ad hoc meeting is planned for November 5 to review the CenturyLink responses associated with each Action Item. The meeting notice will be sent soon.

Kim Isaacs – Integra stated that she would be traveling the first week of November and asked if the call could be rescheduled.

Mark Coyne – CenturyLink stated that we would check with Jeff Bostow as to his schedule for the week of November 9, 2015.

NOTE Update as of October 28, 2015: After review of Jeff Bostow’s schedule and consideration for the Thanksgiving Holiday, the follow up Ad Hoc meeting for this CR and Tech Pub 77350 will be December 1, 2015 at 9:00 AM. A meeting notice will be sent in November.

Mark Coyne – CenturyLink said if the meeting the week of November 9 goes as planned, CenturyLink will likely send a Level 4 CMP notification by mid November with an effective date planned for late December. Mark asked if there were any questions. There were none.

9/30/15 CMP Ad Hoc Meeting Attendees: Phil Thomas – Birch Laurie Roberson – Integra Kim Isaacs – Integra Laura Biel – Consolidated Telcom Jeff Bostow – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink said the meeting minutes from the Ad Hoc call on September 23, 2015 had been sent that morning. Susan relayed that as agreed on that first Ad Hoc call, she had focused on capturing the Action Items and asked everyone to take a quick look at those to insure the approach was satisfactory. Susan said Action Item 2 was an important one and that a SME call had been held on September 29, 2015 to start the discussion but there was no resolution as of yet. If necessary, any new issues would be cross referenced back to Action Item 2. The plan was to use the same approach for this September 30 call and that once we get through the review of the redline Tech Pub 77350 updates, a matrix would be created of all of the Action Items. We would then track them on the matrix for moving them to Completion and cross reference any Tech Pub updates as appropriate.

Kim Isaacs – Integra said the initial list of Action Items looks good but she will need to check her own notes.

Jeff Bostow – CenturyLink began the call where we had left off with a review of redlines with Chapter 7.

Action Item 10 Section 8.2 – Correct the typo in the new sentence from “blank ink” to “black ink”.

Action Item 11 Section 8.1 – Review content of this section to insure that the redlined updates fully delete related content and that there are no remaining sentence fragments.

Action Item 12 Section 8.3.2 – Review and clarify whether this section is applicable to CLECs. This Action Item is associated with Action Item 2 and we will cross reference it to that one.

Kim Isaacs – Integra said this Tech Pub is included in their ICA. Kim wants the Tech Pub sections/content clear as to what applies to CLECs vs. CenturyLink and their suppliers/contractors. In that way, Kim said that will avert the potential for being considered in breach of their contract.

Jeff Bostow – CenturyLink said he understands and wants that clear also. Jeff then asked what the process will be to review the Action Item matrix in order to eventually close each one.

Susan Lorence – CenturyLink said the plan will be to schedule a follow-up Ad hoc call in several weeks to review the Action Item matrix. That will allow time for the Action Items to be resolved by Jeff and his SME team. In the Ad Hoc call, we will review each Action Item and any related Tech Pub updates to insure the Action Item can be closed.

Action Item 13 Section 8.8.1 – Remove “Standard Configuration document…” and replace with PEG. Relates to global Action Item 7.

The changes to Tech Pub Chapters 9, 10 and 11 are based on previous Tech Pub updates to Tech Pubs 77385, 77351 and 77355. The changes to these chapters came from both Curtis Ashton – CenturyLink and Jesse Olave – CenturyLink.

Action Item 14 Section 12.3 – Review paragraph for completeness. This section relates to Action Item 1 and reference to a customer’s ICA. There was a question as to whether the contacts listed in the Tables applied to both CenturyLink and CLECs.

Kim Isaacs – Integra said their ICA addresses the requirements for handling of hazardous materials and agreed updates related to Action Item 1 will help clarify roles and responsibilities.

Jeff Bostow – CenturyLink said that in Chapter 13 and 14 and the related workbook, the forms that are directly applicable to CLEC intervention are the General Method of Procedure (GMOP) and Detailed Method of Procedure (DMOP) forms. Jeff said the workbook changes were generally not changes to the forms themselves but were changes to contact information and changes related to rebranding. Jeff said he is willing to discuss any of the forms.

Action Item 15 Is the term and CenturyLink position of State Interconnect Collocation Manger (SICM) still valid? Should the term be replaced or deleted? Perform global search for this term.

Action Item 16 Chapter 15.9 – The Planned Network Activity Registration (PNAR) process is being replaced by the Network Change Management System (NCMS). Is that process/system and related documentation available outside the CenturyLink firewall? Similarly, is the Change Management Document 0013, Revision 1.0 Doc 0013 available outside of the firewall?

Jeff Bostow – CenturyLink completed the review the final Tech Pub Chapters and asked if there was anything that should be excluded or included in the Tech Pub.

Kim Isaacs – Integra said she may find additional questions during the formal review cycle but did not have any more at this time. The first couple chapters took the time but the remaining chapters went more quickly.

Susan Lorence – CenturyLink asked if any others on the call had any questions. There were none. Susan said in several weeks, she would schedule a one hour follow-up Ad Hoc call to review the status of the Action Item/Matrix. She thanked everyone for their patience and participation on the call.

The Ad hoc meeting was adjourned at 11:30 AM Mountain Time.

9/23/15 CMP Ad Hoc Meeting Attendees: Bernard Dawson – Birch Russ Coleman – Birch Scott Barnett – Birch Phil Thomas – Birch Russ Hamman – Birch Mike Krind – Birch Juan Ornelas – Birch Laurie Roberson – Integra Kim Isaacs – Integra Tracy Fisher – Integra David Boileau – Integra Jeff Bostow – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink reviewed the purpose of the Ad Hoc call and provided a brief background on the CR PC042915-1 associated with updates to Tech Pub 77350. Susan proposed that the meeting minutes from the call consist of Action Items that are identified as each Chapter and sections of the redlined Tech Pub are reviewed. There were no objections.

Jeff Bostow – CenturyLink said the reason for the Tech Pub 77350 proposed changes was to merge the RBOC and ILEC requirements. Jeff said that the changes are consistent with previous updates to Tech Pubs 77351, 77355, and 77385. He said the changes are all future focused and are for new buildout or future building configurations and will not impact current installations. Jeff asked if that was a fair assessment.

Kim Isaacs – Integra said that was her understanding also but said there are some changes in Chapter 2 regarding certification testing that she had not seen before in other Tech Pubs.

Jeff Bostow – CenturyLink said these Tech Pub updates are consistent with the other Tech Pub updates and that they are seamless and benign in their CLEC impact. Jeff said all the page number and section references will be trued up with the final version once the redlines are accepted. There is a global change from Qwest to CenturyLink.

Kim Isaacs – Integra asked if there would be more detail added for the Reason for Reissuance and asked if the new requirements would be included in this section.

Jeff Bostow – CenturyLink said yes, it would and that the History Log would capture the changes in more detail.

Kim Isaacs – Integra said if the History Log will contain more detail of the changes, then it would work to point to the History Log for the details in the Reason for Reissuance.

Jeff Bostow – CenturyLink said he would include a high level view of the new requirements in the Reason for Reissuance and then reference more detail that would be provided in the History Log. Jeff than began review of the redlined Tech Pub.

Section 2.1.1.1 Kim Isaacs – Integra said she needed to check with her team on the fairness of the advance notification. Kim also asked what happens if their ICA differs from the requirements included in the Tech Pub.

Susan Lorence – CenturyLink said the CMP notifications include a statement that the ICA rules.

Action Item 1 Section 2.1.4.2 – CenturyLink will work with legal to add a reference to the ICA.

Action Item 2 Section 2.1.6 – CenturyLink will provide some clarity to roles and responsibilities relative to the terms a) Service Supplier, b) Contractor and c) CLEC/CLEC sub contractor(s). CenturyLink will work with legal to further delineate accountability and requirements in both a cage and cageless environment. Kim Isaacs – Integra said it is clear how Section 2.1.2 applies to equipment but it is not clear how the requirements apply to CLEC subcontractors.

Jeff Bostow – CenturyLink said this will be good to clarify the accountability if there was a disruption in service and who might have caused the situation in conjunction with PUC reporting requirements.

Section 2.11 – There was considerable discussion as to how CenturyLink insures CenturyLink CO Techs know what they are doing in the CO. They are required to take online competency exams and receive a specific clearance level.

Action Item 3 Since CLEC CO techs are not required to take the CenturyLink competency exams, there needs to be appropriate clarity in the Tech Pub on what standards apply to CLECs and which ones do not.

Kim Isaacs – Integra said this is to assist in preventing a CLEC from being expelled from a CO for reasons that are not quite clear.

Action Item 4 Will CenturyLink allow a CLEC or CLEC subcontractor to voluntarily take a competency exam which is outside of the firewall. If so, what would that process be.

Jeff Bostow – CenturyLink described the competency exam and how the exam is related to access requirements via the badge system.

Kim Isaacs – Integra said Integra has had issues with the badging process in the past.

Action Item 5 There needs to be a better understanding of the CenturyLink badging process for CLECs and how that may relate to the potential problem of an inability to gain building access. There have been problems with this in the past.

Action Item 6 There was a name change throughout the Tech Pub from CO Operations to Business and Consumer Markets group however the responsibilities are the same. CenturyLink needs to confirm the contact information did not change and should also investigate if a more generic term can be used to prevent future Tech Pub updates if there is a work group name change when there is not a corresponding contact number change.

Action Item 7 Section 2.4.8.1 and 2.4.8.2 – There is a reference to Planning and Engineering Guidelines (PEG). CLECs do not have access to the PEG so CenturyLink needs to also add applicable Tech Pub reference numbers. CLOSED Jeff Bostow – CenturyLink added a reference to Tech Pubs 77351, 77355, and 77385.

NOTE: A short break was taken.

Action Item 8 Section 3.1.7 – CenturyLink will perform a global search on PEG to also include the applicable Tech Pub reference(s). Jeff will review each occurrence and evaluate what updates are required.

Action Item 9 Section 3.9 – CenturyLink will perform a global search to change any Telcordia reference to Ericsson. Jeff will review each occurrence and evaluate what updates are required.

Jeff Bostow – CenturyLink completed the review of Chapter 6.

Kim Isaacs – Integra said once the information is received on Action Item 2, it will help with the review of the remaining chapters.

Susan Lorence – CenturyLink thanked everyone for their participation on the call and reminded those on the call that there is another review meeting on Wednesday, September 30, 2015. The meeting was adjourned at 11:00 AM Mountain Time.

9/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been on hold since May while Jeff Bostow – CenturyLink continued to resolve some remaining open points. The redlined chapters of Tech Pub 77350 were sent in by Jeff the first of this month. On September 9, 2015, a notification was sent to confirm the two ad hoc calls scheduled for September 23 and September 30. The redlined chapters of Tech Pub 77350 chapters have been posted to the Wholesale calendar and the cross reference matrix of related changes between Tech Pub 77351 and Tech Pub 77350 will also be posted.

Kim Isaacs – Integra said she wanted to confirm that the changes to Tech Pub 77350 will not be backward looking changes.

Mark Coyne – CenturyLink said he thought like the changes to Tech Pub 77351, these are forward looking changes. (9/25/15 Updates received from Integra in CAPS) [NOTE: ON THE 9/23/2015 TECH PUB 77350 AD HOC CALL – JEFF BOSTOW CENTURYLINK CONFIRMED THE CHANGES WERE FORWARD LOOKING AND RETROFITTING WOULD NOT BE REQUIRED.]

08/19/15 Product/Process CMP Meeting Susan Lorence – CenturyLink said this CR was presented in May by Jeff Bostow – CenturyLink. Jeff has been working on resolving some remaining open points and expects to have the final versions of the TP 77350 chapters by end of August. We have tentatively scheduled two ad hoc calls September 23, 2015 and September 30, 2015 that will each be two hour calls to review the proposed changes to TP 77350. A meeting notice will go out early September and we will post the two dates to the Wholesale calendar as placeholders. Susan asked if there were any comments. There were none.

07/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in May by Jeff Bostow – CenturyLink. Mark said that there are a few open points that are still being resolved by Real Estate and the National Network SMEs. The plan is to have the final version of the Technical Publication by end of July and ad hoc calls will be scheduled in August. Mark asked if there were any questions. There were none.

6/17/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month by Jeff Bostow – CenturyLink and that there are a couple open points that are still being resolved associated with Real Estate and the National Network. Jeff has indicated that he hopes to have the final version of the Technical Publication by end of July and ad hoc calls will be scheduled then in early August. Mark asked if there were any questions. There were none.

5/20/15 Product/Process CMP Meeting Jeff Bostow – CenturyLink presented this new CR. He said this CR was the companion CR to a CR associated with Technical Publication 77351 related to Engineering which had a review completed previously this year. Jeff said the next step was to use those completed Engineering requirements to take an aggressive approach to realign CenturyLink under one plan associated with installation requirements. Jeff said there are significant differences across all CenturyLink states but that this Tech Pub will closely resemble the legacy Qwest 14 state region into a one company mindset.

Susan Lorence - CenturyLink said when Jeff was ready, we would schedule an ad hoc call to begin review of the redlined Tech Pub 77350 chapters.

Jeff Bostow – CenturyLink said he is working toward an August 1 date for a 45 day notification cycle.

Mark Coyne – CenturyLink asked if there were any questions for Jeff. There were none.

Susan Lorence - CenturyLink said ad hoc calls had been planned to start once this CR was introduced but just recently Jeff identified that there remain some open points with Real Estate and the National Network SMEs. Susan said Jeff is continuing to work with those teams on any remaining issues and that ad hoc calls will be scheduled as soon as those remaining issues are resolved which may be in July.

Kim Isaacs – Integra asked if these Tech Pub updates are based on the engineering changes that were reviewed previously. She said her understanding was that no rework was required as to what was currently installed with these Tech Pub updates unless there were safety violations.

Mark Coyne – CenturyLink said that was correct as stated with Tech P ub77351 updates.

Kim Isaacs – Integra asked for confirmation that Tech Pub 77350 changes would be on a go forward basis also and that the updates would not require re-engineering of the current environment.

Jeff Bostow – CenturyLink said that was correct. There would not be a need for retrofitting the embedded based with these changes to Tech Pub 77350.


Open Product/Process CR PC070115-1 Detail

 
Title: Grandfather some Resale Public Access Line Service USOCs
CR Number Current Status
Date
Area Impacted Products Impacted

PC070115-1 Completed
9/16/2015
Resale PAL
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

Effective as soon as possible, CenturyLink will continue using the following USOCs: 5FO, 14C, A6F, 5FP, A6J, 12R, 12E, and 1NH on a “grandfathered” basis only for those customers who are currently receiving service under those USOCs in the legacy Qwest territory in all 14 states.


Status History


Project Meetings

9/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR to grandfather specific Resale PAL USOCs became effective August 19, 2015 and is in CLEC Test. There were no customer comments. Mark said we would like to move this CR to a Completed status and asked if there were any objections. There were none.

08/19/15 Product/Process CMP Meeting Susan Lorence – CenturyLink said this CR was presented by Lee Brummett – CenturyLink in the July CMP monthly meeting. A Level 4 notice was sent on July 16, 2015. The final Level 4 notice was sent on August 4, 2015 with an effective date of August 19, 2015. We will discuss moving it to Completed status next month. Susan asked if there were any questions. There were none.

07/15/15 Product/Process CMP Meeting Lee Brummett. – CenturyLink presented this new CR associated with grandfathering certain USOCs associated with resale PAL. Lee said the Level 4 notification would be sent on Thursday, July 16, 2015 with an effective date of August 19, 2015. Lee said CenturyLink will be making the appropriate tariff filings. He asked if there were any questions. There were none.


Open Product/Process CR PC071515-1 Detail

 
Title: Eliminate FBDL Help Ticket reporting process
CR Number Current Status
Date
Area Impacted Products Impacted

PC071515-1 Completed
9/16/2015
Directory Listings
Originator: Gomez, Lee
Originator Company Name: CenturyLink
Owner: Gomez, Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink established a process in early 2000 to allow customers the ability to receive a report of open/closed trouble tickets specific to Directory Listing issues. This process was initially established to assist wholesale customers in understanding status of multiple trouble tickets that their company representatives had opened.

This report has not been requested by any customer in at least 10+ years. CenturyLink is planning to eliminate this process and reporting capability.

Related documentation is included in the Directory Listing Provider Business Procedure at http://www.centurylink.com/wholesale/clecs/dirlistuser.html.

Expected Deliverables/Proposed Implementation Date: October 2015


Status History


Project Meetings

9/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented by Lee Gomez – CenturyLink last month. We received agreement last month to send a Level 2 notification vs. a typical level 4 notification since customers had not requested this report for over 10 years. There were no customer comments so a final notice was not required. The CR was moved to CLEC test on September 15, 2015. Mark asked if there were any objection so to moving this CR to a Completed status.

Kim Isaacs – Integra asked if this change was due to the change in vendor for Directory listings.

Lee Gomez – CenturyLink said this had nothing to do with the change in the Listing vendor. Lee said she was reviewing some process documentation and realized we still had this FBDL Help Ticket report available. After some checking, she saw this report process had not been used by customers in over 12 years.

Mark Coyne – CenturyLink said with that in mind, was it OK to move this CR to Completed status.

Kim Isaacs – Integra said that was OK.

08/19/15 Product/Process CMP Meeting Lee Gomez – CenturyLink presented the CR and stated that this was to eliminate a report that had not been used in over 12 years.

Kim Isaacs – Integra asked if this was related to the Call Center Ticket report.

Lee Gomez – CenturyLink stated that it was not; this report is specific to FBDL.

Susan Lorence – CenturyLink asked if CLECs would oppose sending this notice as a Level 2 versus a Level 4 notice. The document to be updated is the Directory Listing Provider Business Procedure. There were no objections.


Open Product/Process CR PC011516-1 Detail

 
Title: CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Requirements and Testing on Technical Standards associated with CenturyLink Telecommunications Equipment Installation Guidelines (Tech Pub 77350)
CR Number Current Status
Date
Area Impacted Products Impacted

PC011516-1 Completed
8/17/2016
Network
Originator: Bostow, Jeff
Originator Company Name: CenturyLink
Owner: Bostow, Jeff
Director:
CR PM: Lorence, Susan

Description Of Change

Create a new CenturyLink Business Procedure for CLEC Competency Testing on Telecommunications Equipment Installation Guidelines.

CenturyLink is updating Technical Publication 77350, Telecommunications Equipment Installation Guidelines that includes a requirement for CLECs and all CenturyLink-approved Inside Plant (ISP) Service Suppliers to meet certain competency levels 1-4 for authorization to perform central office-based installation /removal services within CenturyLink Local Network Facilities. This new Business Procedure will specify the process and timeline for CLEC representatives to obtain a successful competency certification to the CenturyLink Central Office Engineering/Installation/Technical Standards Policy. Competency certification will be obtained for Service Suppliers by accessing the following link and determining individually which level of certification is needed based on Scope of Work and subcontracted necessity: http://www.centurylink-supplier-certification.com/.


Status History


Project Meetings

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has also been in CLEC Test since July 1, 2016. He relayed that an additional change in process had occurred associated with the CLEC Badge Access Request web site to include wording changes about the Badge acknowledgement process. That change has a proposed effective date of August 19, 2016. Mark said since the original reason for the CR has been implemented, we would like to move this CR to a Completed status.

Kim Isaacs - Electric Lightwave said if CenturyLink moves the CR to a Completed status, it would be over their objections. Kim said Electric Lightwave has objected to the legal terms that CenturyLink has added to the Badge Access Request web site. Kim said they are continuing to ask CenturyLink to remove the terms or make a modification to them.

Mark Coyne – CenturyLink said that the CenturyLink has made note of the concerns that Electric Lightwave has expressed. Mark said he thinks we are at the point of agreeing to disagree.

Kim Isaacs - Electric Lightwave said her concern is that the legal language added to the Badge Access Request web site does not appear to provide any benefit to CenturyLink and the change in wording is requiring Electric Lightwave to change their process so that they have someone that can respond to the legal aspect of the badge process. Kim said with the ICAs and the Tech Pub, what benefit does this wording provide CenturyLink.

Mark Coyne – CenturyLink said we have captured the Electric Lightwave objections in the minutes. In checking with the CenturyLink legal team, not all of the ICAs have the specific wording to protect the shared facility space so this additional language is necessary. Mark said the terms protect not just CenturyLink but all customers. CenturyLink has always been in agreement that the terms of the ICA supercede the PCATs. Mark said we will capture this exchange in the minutes and move the CR to a Completed status.

Armando Fimbres – Oregon PUC asked what are the consequences of the additional language.

Mark Coyne – CenturyLink said if a dispute were to arise, CenturyLink would fall back on the terms of the agreement.

Kim Isaacs - Electric Lightwave said this change is being implemented over their objection and that they reserve the right to reopen this if the process becomes a problem. Kim said she is not sure how CenturyLink will implement this.

Mark Coyne – CenturyLink said we will leave it up to our Legal team.

7/20/16 Product/Process CMP Meeting PC042915-1 Technical Publication 77350, CenturyLink, Telecommunications Equipment Installation Guidelines PC011516-1 CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Requirements and Testing on Technical Standards associated with CenturyLink Telecommunications Equipment Installation Guidelines (Tech Pub 77350) Mark Coyne – CenturyLink said he would provide an update on these two CRs at the same time. Both CRs are in CLEC Test as of July 1, 2016. Mark said a Level 3 notice was sent on July 6, 2016 to implement a further change to the CLEC Badge Access Request web site and the CLEC Badge Access Request Job Aid to include a wording update about the Badge acknowledgement process; the wording had originally been included as part of the final notice for these two CRs that was distributed on June 16, 2016. Mark said CenturyLink received a postponement request from Integra to delay implementation of the additional wording changes. Due to the postponement request, CenturyLink retracted that update and resent the redlined language as a Level 3 change on July 6, 2016 with an effective date of August 19, 2016. Mark said the specific information about the postponement request is available as Postponement #3 on the CMP Oversight Committee & Escalation/Dispute Information website at http://www.centurylink.com/wholesale/cmp/escdisp.html under Postponement Archive.

Kim Isaacs – Integra said she submitted comments on the Level 3 change that states Integra objects to the added language in the Badge Access tool. Kim said the process is covered by their ICA and has similar terms governing collocation access. (7-29-16 Updates received from Integra in CAPS) CENTURYLINK ALLOWS ONLY [delete WITH] one point of contact (POC) for each company [delete ALLOWED], that POC is an administrator and is not the right person to acknowledge the process for each badge holder or for their company.

Mark Coyne – CenturyLink said CenturyLink will review the Integra comments with our legal and SME team.

Kim Isaacs – Integra said her concern is that CenturyLink is (7-29-16 Updates received from Integra in CAPS) TRYING TO USE [delete USING] this same badge access site for CLECs and [delete THEIR SUB-CONTRACTORS] CENTURYLINK’S CONTRACTORS and those CenturyLink relationships are different. Kim said she thinks the badge acknowledgement language is redundant since the CLEC has an ICA but said she can understand the language being necessary when there is not an ICA.

Mark Coyne – CenturyLink said it might be that CenturyLink needs to include additional language like “unless otherwise specified within the ICA”.

Liz Tierney – Global Capacity said that she thinks adding requirements at the Collocation Access site is not needed. Liz said the ICA is explicit regarding access and that we need to remove barriers. Mark Coyne – CenturyLink said we will consider the comments and provide the CenturyLink response with the Final notice due August 4, 2016. Mark asked if there were questions. There were none.

6/15/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said he would provide an update on this CR and CR PC011516-1at the same time since they are related. He said there were several notifications that were distributed associated with these changes: two level 4 notices and one Level 3. The initial notices were sent on May 25, 2016 that included a formal comment cycle that ended June 9. CenturyLink did receive customer comments. The final notices and response to comments are due on June 16, 2016. The changes will become effective on July 1, 2016. The CRs will then be moved to CLEC Test and will be reviewed in the July CMP meeting. Mark asked if there were questions. There were none.

5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink reminded callers that this CR is tied to the Tech Pub 77350 CR and was also reviewed on the Ad Hoc call on May 2, 2016. Mark said Jeff Bostow – CR provided a high level review of the proposed Competency Test process which includes a new Business Procedure which was created by the SME team. This CR also requires additional revisions to the Collocation Badging Process to tie it to the Competency certification. On a side note, Mark relayed that the Collocation Badging Process rewrite of the website and the CenturyLink Premises Access Overview Business Procedure Version 8 became effective today, May 18, 2016. Mark said the planned timeline for the Competency Test is the same as the Tech Pub 77350 which has the July 1, 2016 effective date. Mark asked if there were any questions. There were none.

05/02/16 CMP Ad Hoc Meeting Attendees: Brendan Hamel – Granite Kim Isaacs – Integra Laurie Roberson – Integra Jeff Bostow – CenturyLink Rita Urevig – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink went over an agenda for the meeting and then a brief history of the two CRs, PC042915-1 and PC011516-1. Susan said that during the meeting, she would like to take down specific Action Items that need to be resolved versus capturing detailed discussion of the examples that may be included in the Tech Pub.

CR PC042915-1 Technical Publication 77350 Jeff Bostow – CenturyLink then reviewed the CenturyLink proposed Tech Pub 77350 language dated April 28, 2016 that is posted to the CMP calendar entry for the meeting. The wording updates are associated with the CenturyLink response to questions posed during the CMP monthly meeting on April 20, 2016. Jeff spoke to Section 2.1.2 of the Tech Pub and said there are two types of Methods of Procedure (MOP) – General and specific. The MOP is required for CenturyLink and their subcontractors due to PUC requirements in case there is a service interruption; it shows the scope of the work and who is performing it. A MOP is not required if a CLEC is working solely within their space – caged or cageless. Jeff said the wording updates to Section 2.1.2 are to show a MOP is required if any work is performed in the shared space and has included examples in the Tech Pub wording to show when a MOP will be required. Jeff asked if the new language met what the group intended.

Kim Isaacs – Integra said she needed to run the newly proposed language passed her CO technicians. She said she did not think the CLEC could do any of the work listed.

Jeff Bostow – CenturyLink said that was correct but there have been some occasions where a CLEC has started performing some of this work themselves.

Kim Isaacs – Integra thanked Jeff for the examples and said she would review the new Tech Pub wording internally but that the proposed CenturyLink wording since mid April has been a good balance. Kim said she thought there would not likely be issues with these newly proposed updates. With the April 15, 2016 CenturyLink wording in Section 2, Integra believes they are protected for the day to day work they perform in their collocation space.

Jeff Bostow – CenturyLink said excellent. Susan Lorence – CenturyLink said the examples were added due to the Integra requests during the April monthly CMP call. She then referred call participants to Section 2.1.4.2 to review those wording changes. Susan said she thought Integra had reviewed the 04-15-16 wording and Jeff had made some updates to address the requests from the Monthly call.

Kim Isaacs – Integra said she liked Jeff’s 04-28-16 updates which make the responsibilities clearer.

Jeff Bostow – CenturyLink said the wording is intended to say a CLEC can perform their normal business routine in their collocation space but when work is required in the shared space, the Tech Pub wording applies.

Susan Lorence – CenturyLink asked if there were any other changes in Section 2 that had to be discussed. There were none. Susan then referred call participants to the Action Item list from September 2015 posted to the calendar to see if open items remain. She thought the open items were originally related to the Tech Pub wording changes that were just discussed and the Competency Test/badging wording which will be discussed next. Susan asked about the Action Item 16 related to Network Change Management System (NCMS) process.

Kim Isaacs – Integra said she was fine on that one.

Jeff Bostow – CenturyLink said the NCMS process now covers all of CenturyLink – Local and National.

Susan Lorence – CenturyLink said we will show Action Item 16 completed. She asked about Action Item 5 related to the badging process and whether she could refer that item to the Competency Test CR. No one disagreed. Susan said we will now show all of the Action Items Completed. Susan asked about discussion of a timeline.

Jeff Bostow – CenturyLink said Integra needed some time to review the wording.

Kim Isaacs – Integra said she could reply back by May 11, 2016 as to the whether Integra was OK with the most recently proposed Tech Pub 77350 wording changes.

Susan Lorence – CenturyLink asked Brendan Hamel – Granite if Granite could also meet a May 11, 2016 to provide any concerns.

Brendan Hamel – Granite said he could meet that date.

Susan Lorence – CenturyLink asked for any concerns to be sent to the CMPCOMM@centurylink.com mailbox by May 11, 2016.

PC011516-1 CLEC/CLEC Subcontractor Inside Plant (ISP) Competency Testing Susan Lorence – CenturyLink then pointed call attendees to the third document posted to the Wholesale calendar associated with the CLEC Competency Test CR. Susan said this draft document was created by John Hansen - CenturyLink in a Business Procedure format from the draft Competency Test Process Guide that Jeff had reviewed in the ad hoc meeting in January 2016.

Jeff Bostow – CenturyLink said this document has basically the same content as the CenturyLink internal document but has more of a CMP format. He said this document only applies to work outside of normal CLEC business activities. When a CLEC needs to expand their current model, an Inside Plant Central Office Installation Technician would be required which is an industry title that has been in existence for 30 years or so. Jeff said the Competency Test was developed after some problems in network installation attributed to human error. The Competency Test was aligned with the badging process depending on the work that is to be performed. Jeff said there are two types of testing that are aligned with Telcordia/Ericsson levels: Central Office Equipment (COE) Installer only (Level 1-3) and COE plus Power (Level 4). If the person taking the test successfully passes the Competency Test questions, their badge reflects certification to work in the CO to that level and it allows CenturyLink to be aware of subcontractor capabilities. Jeff said CenturyLink has been pleased with the result of the Competency Test process.

Kim Isaacs – Integra said she has reviewed the Business Procedure and asked how the Competency Test would appear.

Jeff Bostow – CenturyLink said a button would be added to the newly revised CenturyLink badging process to have a CLEC self identify up front to see if they are performing their normal work activities. That should allow no disruption to a CLECs current process. The Competency Test only is required if the CLEC indicates they are going to perform installation work. Jeff said he was not aware of when the newly revised badging website was to be reinstated.

Susan Lorence – CenturyLink said the newly revised badging website and Collocation – CenturyLink Premises Access Overview Business Procedure are to be effective May 18, 2016. CenturyLink is working on the response to CLEC comments that will be posted on May 3, 2016. Following the effective date of May 18, 2016, CenturyLink will work with the SME team to revise this Competency Test documentation and possibly the Collocation – CenturyLink Premises Access Overview Business Procedure to incorporate any changes in the process for CLEC testing.

John Hansen – CenturyLink said he wants to insure there is only one location to update associated with each of the processes.

Kim Isaacs – Integra said she wants to minimize confusion on these processes. Integra has a special point of contact (SPOC) for badging.

John Hansen – CenturyLink said the original information in the Competency Test documentation was not correct as it pointed to the old badging process and it will have to be updated. The first iteration of the badging tool does not have the Competency Test information included since the Tech Pub 77350 and Competency Test related issues were not yet resolved. CenturyLink wanted to get the revised badging website in production before making these Tech Pub related changes. John said there will be some radio buttons that ask what the CLEC scope of work will be. If it is the normal CLEC Collocation work, then the process will flow as today. If the work includes a broader scope, e.g., power work, it will stop the process and require the Competency Test. John asked if that made sense.

Kim Isaacs – Integra said yes.

Susan Lorence – CenturyLink said we will need to clarify in the documentation if a CLEC technician already has a badge and that needs to be expanded to include a further scope of work, e.g., COE or COE plus power, how does the process of competency testing and re-badging occur.

Kim Isaacs – Integra said she will have a chance to review the revised process when the CMP notice is sent. She is thinking if a MOP is required, it could be a trigger internally for Integra to determine if a Competency Test is required.

Jeff Bostow – CenturyLink said the process will apply to both the CLEC and their subcontractor. He said today a CLEC does not have to file a MOP if they are working in their space.

Kim Isaacs – Integra said if their project meets the requirements for a general or detail MOP, their internal process might be tied to the MOP to indicate the Competency Test may be required. Kim said Integra already uses the approved CenturyLink subcontractors for work and they probably have already been tested.

Susan Lorence – CenturyLink said it sounds like we can talk about a timeline for submitting the two Level 4 changes. With the May 11 date for CLEC responses for review of the most recent Tech Pub 77350 updates, the May 18 date for the effective date of the Badging website, Susan proposed that we notify with the two level 4 notifications as of May 19, 2016 with a 45 day timeline.

John Hansen – CenturyLink said he thought that would work from a documentation perspective.

Kim Isaacs – Integra agreed that the two processes for the Tech Pub and the Competency Test should be notified separately.

Brendan Hamel – Granite said he was OK with the May 19 date.

Susan Lorence – CenturyLink proposed that we may need to tweak the notification timelines somewhat but that we would work the various dates to make the changes become effective as of July 1, 2016.

Jeff Bostow – CenturyLink said that will be Issue O of Tech Pub 77350 that will become effective.

All agreed that it was very exciting to think that after the lengthy discussions, these Tech Pub and Competency Test changes will become effective as of July 1, 2016.

Susan Lorence – CenturyLink thanked everyone for their time and said CenturyLink will relay the timeline in the May CMP meeting.

The Ad hoc meeting was adjourned at 11:00 AM MT.

4/20/16 CMP ProdProc Meeting Mark Coyne – CenturyLink reminded callers that this CR is tied to the Tech Pub 77350 CR and is also related to an update to the Collocation Badging Process. Mark said a Level 3 Notice associated with the badging website rewrite is out for review with a comment cycle end date of April 27, 2016 and an effective date of May 18, 2016. There is a download associated with the Competency Test proposed Process that has been placed in the CMP template format that will be reviewed in the ad hoc call.

Kim Isaacs – Integra stated that they had intended to ask for clarifications during the Tech Pub Ad hoc call and now the comment cycle would end prior to the Ad hoc call.

Mark Coyne – CenturyLink asked if Integra could follow the CLEC comment protocol and submit comments to the CMP mailbox so that CenturyLink could try to be prepared to discuss during the Ad Hoc call.

Kim Isaacs – Integra said that would be acceptable but would include a statement that there may be more questions brought up in the Ad Hoc call.

Susan Lorence – CenturyLink advised callers that during the original discussion in January, 2016, Jeff Bostow had provided a draft procedure of the Competency Testing procedure. John Hansen – CenturyLink has placed the information in a CMP template form and that version has been attached to the ad hoc meeting calendar entry. Revisions will be necessary, but that draft is available for review prior to the Ad Hoc call.

3/16/16 CMP ProdProc Meeting Mark Coyne – CenturyLink said the CenturyLink SME team has been reviewing the Competency Test process and how it relates to the Collocation - Premises Access Overview Business Procedure. We had hoped the Tech Pub 77350 wording would help to clarify the process. Mark said we had planned to schedule a call at the end of March to review the redline business procedure and how it relates to the Competency Test screen shots but we will wait to determine when to schedule the next ad hoc call.

Kim Isaacs – Integra said she had previously asked to review the Competency Test questions to confirm they apply to the activities that a CLEC would perform in the CO shared space.

Mark Coyne – CenturyLink said he thought that might occur as part of the review in April.

Susan Lorence – CenturyLink said she was not sure if Jeff Bostow – CenturyLink wanted to share the actual Competency Test questions but we can see if anything has changed.

Kim Isaacs – Integra said that a CLEC would never touch a power plant so those questions on the Competency Test would not pertain to the work a CLEC would perform.

Liz Tierney – Global Capacity said she was not sure why Jeff would have concerns about sharing the questions and why they would be proprietary.

Mark Coyne – CenturyLink said we will take that Action Item back to Jeff. Mark asked if there were any other questions. There were none.

02/17/16 CMP ProdProc Meeting Mark Coyne – CenturyLink said this new CR was presented last month by Jeff Bostow – CenturyLink and there was lots of discussion about the CR associated with Competency Test requirements when a CLEC is performing installation or removal work in the common space. Jeff Bostow – CenturyLink said he has information on the Action Item on the current mode of access and the future mode. Kim Isaacs – Integra said the question [03/07/16 Updates received from Integra in CAPS] ASKED was WHETHER AND how the Competency Test would be tied to the access badge. There is also concern that the Competency Test will have questions that are not associated with work a CLEC would perform and that Integra would like to review the Competency Test questions.

Jeff Bostow – CenturyLink said the Competency Test content has not been divulged. He said there was an Action Item to see how access is provided today. Jeff said the current process identifies the use of the Collocation Web site however that site is being rewritten. Jeff then described the current manual process: The Wholesale CLEC application form is completed and then sent to a contact within CenturyLink depending on the CLEC location. The form is processed internally and once approved, the badge number is assigned and the badge is sent to the CLEC individual requesting the access. Jeff then described the planned process once the Collocation website is back in production which is to designate a point of contact. [NOTE: Any changes to the current process associated with the rewrite of the Collocation web tool will be notified via CMP.] Jeff said there will be two buttons that will be associated with different types of CLEC access to CenturyLink space. Depending on the button selected, the requestor will be routed appropriately. If the Competency Test is not required, Jeff said the assumption is that the CLEC will be working in their defined space.

Kim Isaacs – Integra said a CLEC may have an employee that does work in their defined space as well as performing installation or removal work in the shared space.

Jeff Bostow – CenturyLink said if there is specific power work, it would be covered in a MOP and CenturyLink has responsibility to do that power work so a Competency Test Level 4 is not required.

Susan Lorence – CenturyLink recapped that Jeff is currently working within the CenturyLink SME team to determine how the current process will be revised to accommodate the Competency Test.

Jeff Bostow – CenturyLink said that was correct and that he is working with the SME team to update the screen shots and will revise [03/07/16 Updates received from Integra in CAPS] [delete THE]what was previously shared.

Kim Isaacs – Integra said her understanding of the January 28, 2016 Ad Hoc Call was that a CLEC employee/subcontractor will need the Competency Test if they are building a new collocation (caged or cageless) or decommissioning a collocation.

Jeff Bostow – CenturyLink said if the CLEC is in their cage, they perform that work today with no restrictions.

Kim Isaacs – Integra asked how that works if the CLEC/subcontractor is bringing in equipment through the shared space. She said that is where the revised Tech Pub is unclear as to what will be required. It appears things are working fine currently and there are no issues with the competency of the CLEC employee/subcontractor. Kim said the Tech Pub says CenturyLink can ask a CLEC to leave if there is a concern and said the proposed process seems open to interpretation.

Jeff Bostow – CenturyLink said if a CLEC is moving in equipment and bumps into a power source, those accidents can occur and this is intended as protection of the CenturyLink network. Jeff said this requirement is a safeguard for CenturyLink to insure that any construction or removal of equipment – especially in an unstaffed office – is performed successfully. It is not intended to be restrictive. Jeff said if things are working fine and the CLEC is working just within their cage, that is not prohibited but asked what happens if there is an incident.

Kim Isaacs – Integra said she understands the need for protection and standards but [03/07/16 Updates received from Integra in CAPS] DOES not UNDERSTAND CENTURYLINK’S [delete THE] need to make a CLEC synonymous with a CenturyLink Service Supplier.

Jeff Bostow – CenturyLink said there was a situation with a collocator which did not go well which reaffirmed the need for more standards.

Susan Lorence – CenturyLink asked about the CLEC Action Item to propose clarifying language in Section 2. Then CenturyLink would take the proposed wording to the CenturyLink legal team.

Mark Coyne – CenturyLink said he thought CenturyLink was waiting to send out the formal 45 day notice until the various revisions could be fit together and reviewed with the CLEC community. Mark said we could review the changes on a CMP call.

Jeff Bostow – CenturyLink said yes, the process would be reviewed by Mark Rice – CenturyLink Physical Security. Jeff asked if it was typical to take a poll of call attendees to understand if others on the call had the same concerns as Integra.

Liz Tierney – Global Capacity said she is concerned if there is no documentation that defines the Competency Test. Liz said Global Capacity is nationwide in CenturyLink COs and have not had issues so far. Liz said she needs to understand how the current process might change.

Susan Lorence – CenturyLink asked if the CLECs could propose some language to Section 2 and that CenturyLink would then schedule a call at the end of the March CMP call to review the proposed process.

Kim Isaacs – Integra said the [03/07/16 Updates received from Integra in CAPS] CLEC PROPOSED language HAS BEEN [delete SHE HAS] drafted AND has been sent out for review which WILL also INCLUDE [delete INCLUDES] Integra legal review since the Tech Pub is part of their contractual requirements so she was not sure whether it would be available for review in the March meeting.

Mark Coyne – CenturyLink said we could wait until the April CMP meeting which may tie in with the Event Notice associated with the Collocation portal that has a planned effective date for end of 1st quarter.

Susan Lorence – CenturyLink said we may be in a chicken and egg situation if we have to agree on the Tech Pub language as part of the introduction of the updated Collocation portal and the CLEC review of the revised process of the Competency Test.

Kim Isaacs – Integra [03/07/16 Updates received from Integra in CAPS] AGREED WITH SUSAN AND ASKED CENTURYLINK TO CONFIRM WHETHER [delete SAID] these revisions are not due to a current problem with CLECs but are due to CenturyLink moving to a more contractual workforce.

Jeff Bostow – CenturyLink said CenturyLink has to trust that vendors know what they are doing and the only thing CenturyLink has is the Competency Test to provide an assessment of skill level before work begins in a shared space.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.

01/28/16 CMP Ad Hoc Meeting Attendees: Liz Tierney – Global Capacity Kim Isaacs – Integra Valerie Starr – LS Networks Dave Rands – LS Networks Mark Anderson – LS Networks Scott Church – LS Networks Victor Gaither – TW Cable Frankie Nelson – Windstream Jeff Bostow – CenturyLink Carl Caughran – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink provided a brief background of this Change Request (CR) that is related to CenturyLink CR PC042915-1, Technical Publication 77350, associated with Telecommunications Equipment Installation Guidelines. Susan said the most recent meeting for the Tech Pub77350 CR was held on January 7, 2016 and there were two Action Items that were the result. The first Action Item was specific to considering additional language in the Tech Pub. The second Action Item was to create a CR that would provide the process and parameters around the use of a Competency Test by the CLEC community.

Jeff Bostow – CenturyLink said the Inside Plant (ISP) Competency Test was originally developed due to some outages that were determined to be due to human error. With the merger of Legacy-Qwest and Legacy-CenturyLink, there was the need to insure that no matter which facility footprint was being accessed, the Central Office Equipment Installation Tech (COEIT) has the experience and knowledge required to perform the installation as required in Tech Pub 77350. The document provides the five steps to utilize the Competency Test tool. Jeff said the first step in the process is to route the person to the correct site, Inside Plant (ISP), Outside Plant (OSP), or National. If OSP is selected, then the ISP Competency Test is not required.

Kim Isaacs – Integra said this is the first time OSP has come up. Kim said if the CLEC is working in the CO common space – performing installation or removal work, they will require the Competency Test. If it is a day to day job, no Competency Test is required.

Jeff Bostow – CenturyLink said that was true.

Kim Isaacs – Integra asked if the test was required to run conduit.

Jeff Bostow – CenturyLink said that the OSP work did not apply since there was no bandwidth nor was there the knowledge to take the Competency Test. He said they still access the Competency Test, designate “OSP” via the radio button to signal to CenturyLink an acknowledgement of their need to get an access badge but will not be permitted in certain workspace.

Kim Isaacs – Integra asked if the test was tied to the badging process for CLEC access.

Jeff Bostow – CenturyLink said he did not think so since that is tied to the ICA. He said the Central Access Control Center has a process to differentiate OSP, ISP and CLEC access needs. If ISP, they will route the person to the Competency Test. Levels 1-3 are for basic entry level work and Level 4 is for critical work, e.g., working with power, work that might require back out, etc. Jeff said this is especially beneficial for everyone involved if the office is not staffed.

Scott Church – LS Networks asked about a CLEC caged Collo and a cageless Collo since that is open.

Jeff Bostow – CenturyLink relayed some different types of work to be completed but said the Competency Test does not apply to work being done in the CLEC specific space – caged or cageless – as long as the tech is not going outside of their space.

Scott Church – LS Networks asked about a third scenario of CLEC to CLEC cabling and gave the examples of a common room.

Jeff Bostow – CenturyLink said if the CLEC to CLEC is going through any shared space for any reason, then the Competency Test is necessary but if it CLEC to CLEC directly in a common room, then the Competency Test would not be required.

Scott Church – LS Networks said that makes sense.

Liz Tierney – Global Capacity said her understanding is if a tech is only in the CLEC space, no certification is required. If a CLEC hires their own contractor to work in common space, certification is required but it would not be required if they hire CenturyLink to do the work.

Jeff Bostow – CenturyLink said that was correct.

Scott Church – LS Networks said the Competency Test is required if it goes out of the Collo area but if it stays in their space or a segregated Collo space, it is not required.

Jeff Bostow – CenturyLink said that was correct.

Victor Gaither – TW Cable said based on the scenarios just discussed, he did not have an issue.

Kim Isaacs – Integra asked for an example of a Level 1 type job.

Jeff Bostow – CenturyLink said the main difference between Levels 1 through 3 is the experience. The tech performs the same functions. Jeff then provided a detailed example of the set up work in a new environment.

Kim Isaacs – Integra said those activities are required if a CLEC is building a new caged or cageless space and asked if there is another scenario once the space is established, e.g., adding a shelf to a bay.

Jeff Bostow – CenturyLink said if the CLEC is in their own space with no other interconnectivity, certification is not required for that.

Victor Gaither – TW Cable asked if CenturyLink provides a list of certified contractors.

Jeff Bostow – CenturyLink said CenturyLink has a list of suppliers that have passed the Competency Test. He said if a person has failed the Competency Test, they are allowed one additional attempt otherwise the person must wait one week to retest.

Victor Gaither – TW Cable said he was looking for a current list of CenturyLink certified contractors.

Jeff Bostow – CenturyLink said that information is proprietary and he could not provide it.

Kim Isaacs – Integra said per their ICA, that list was available.

Victor Gaither – TW Cable said their company has access to the approved contractor list and also has a list of approved equipment. Victor said that seems consistent with the industry.

Jeff Bostow – CenturyLink said once a contractor has demonstrated a specific competency level, a CLEC can subcontract to them and no additional Competency Test is required if another company works with that contractor.

Victor Gaither – TW Cable said a company can do the work for themselves or hire someone certified who can.

Jeff Bostow – CenturyLink said the Competency Test is mandatory within CenturyLink for all 38 states.

Liz Tierney – Global Capacity asked if those certified will have a different access card and whether those that currently have a badge are impacted.

Jeff Bostow – CenturyLink said he will need to investigate that. NOTE: 2/8/16 UPDATE from Jeff Bostow -- The badge is the access card; they are one and the same (unless a different arrangement was made for the CLECs via the ICA process). The only difference is the Competency Level designation (there is a “P” placed on the badge of those who certify to Competency Level 4). Investigation is continuing on this Action Item.

Victor Gaither – TW Cable said that is important to confirm the impact to the badging process. He said his understanding is that a CLEC can perform work in their environment but if they want to veer out, the Competency Test is required.

Jeff Bostow – CenturyLink said nothing changes in how a CLEC wants to do work in their space. If the CLEC does work outside their space, they must be certified. Jeff said the competency levels have been around at least 35 years since they were established he thought through BellCore which was changed to Telcordia and is now Ericsson. He said there is a National site like this local network site and the Competency Test is required to do work in each but there are certain differences between the two tests. Jeff provided some information specific to the National access process.

Susan Lorence – CenturyLink said we are here for the Local process and that we will take an Action Item to figure out how the badging process works with the Competency Test.

Liz Tierney – Global Capacity said she thought the current badging process does not provide access to inside plant and that there will be some differentiation between those certified and not to identify where they are allowed. Liz said she wants to confirm the badging process will not change.

Jeff Bostow – CenturyLink said he thinks once a customer has an access badge, they are allowed in the inside plant space. The intent is that a company stay in their own space. Today a customer can begin doing inside plant work with no certification but going forward, if they begin work outside their space, it will be determined if that person has the required certification.

Carl Caughran – CenturyLink said during the MOP process, it would be determined if certification was required.

Liz Tierney – Global Capacity said she did not want her techs to be caught with no access under their ICA.

Susan Lorence – CenturyLink said we have this as an Action Item.

Valerie Starr - LS Networks asked about the online badging process and said since last October, the Collocation access site has been down. Valerie said she was not notified the site of this and it is very frustrating to have to go through the old process filling out a form and then having to check multiple times for status.

Victor Gaither – TW Cable said if there was a significant business change, the process would be taken through CMP.

Susan Lorence – CenturyLink said yes but this problem was originally identified as a trouble ticket so an Event Notification was sent. The original thought was that it was a simple fix but then IT determined a larger problem existed and the tool is being rewritten. Susan said the Collocation site should be available end of 1st quarter and that CenturyLink would take an Action Item to follow-up on this and to send a broad notification when the site is to be back up. Mark Coyne - CenturyLink said there is a Trouble Ticket associated with this problem which is tracked each month in the Systems CMP package. Mark said there was now a dedicated person to work the requests until the site is back up and hoped it was working better.

Valerie Starr - LS Networks said no, it is not. She said the web site flowed smoothly but this manual process does not. Valerie said she has been cc’ing her Account manager on each request to get some help.

Susan Lorence – CenturyLink asked how the Collo access site fits into the Competency Test.

Jeff Bostow – CenturyLink said the Collo access site is for a CLEC or vendor and is used to gain access to outside plant or to the vault. Once there is an indication that the person is an ISP, they will be routed to the Competency Test for the appropriate testing level.

Kim Isaacs – Integra said she did not think her techs would identify as an ISP.

Jeff Bostow – CenturyLink said he agreed they would identify as a CLEC to get the badge and not have to go through the Competency Test.

Kim Isaacs – Integra asked if there would be a CLEC button.

Jeff Bostow – CenturyLink said no and that was the basis of the “Service Supplier” issue that is under discussion associated with the Tech Pub 77350 CR.

Scott Church - LS Networks asked if the CLEC tech was supposed to identify as a Service Supplier.

Jeff Bostow – CenturyLink said yes if they were going to work in the ISP space.

Susan Lorence – CenturyLink asked if there was a general understanding of the Competency Test process, who and when the test applied.

Victor Gaither – TW Cable said yes but would like it included in the meeting notes.

Kim Isaacs – Integra asked if their techs would be tested on work they would not perform.

Jeff Bostow – CenturyLink said the test is benign and that the test is aligned with the existing Tech Pubs. It is an open Tech Pub test that is assessing how successful previous training has been.

Susan Lorence – CenturyLink asked if Jeff could provide examples of some of the questions on the Competency Test.

Jeff Bostow – CenturyLink said no.

Frankie Nelson – Windstream asked if they were building racks within their cage, does the Competency Test apply.

Jeff Bostow – CenturyLink said the test does not apply. He said CenturyLink would not be involved in a CLEC space unless a blatant fire, life or safety issue was observed.

Scott Church - LS Networks asked about construction of bays in a caged and cageless space.

Jeff Bostow – CenturyLink said the Competency Test is required to install a bay in cageless space but thought CenturyLink did that work.

Kim Isaacs – Integra asked if a CLEC Tech could take Levels 1-3.

Jeff Bostow – CenturyLink said there is no charge when a CLEC Tech takes the test for the first time. For example, if they take the COE Only test (Level 1-3) and pass, everything is good. If the same CLEC Tech then wants to test for COE plus Power, they are required to pay a one-time charge for the second test and there is no history of the first test.

Susan Lorence – CenturyLink asked if the Action Items are resolved surrounding the Competency Test, can CenturyLink proceed with CMP notification without the Tech Pub issues being resolved.

Kim Isaacs – Integra said the timing is strange.

Jeff Bostow – CenturyLink said he thought the Tech Pub should be resolved first and then the Competency Test.

Susan Lorence – CenturyLink thanked everyone for the discussion. There are two Action Items and we will try to include the responses in the meeting minutes: 1) The question about how the Competency Test ties into the badging process; 2) The status of the Collo web site.

The Ad hoc meeting was adjourned at 3:00 PM MT.

01/20/16 CMP ProdProc Meeting Jeff Bostow – CenturyLink presented this new walk-on CR submitted by CenturyLink associated with the Tech Pub 77350 rewrite. Jeff said with the one company approach within CenturyLink, there is a desire to insure the Tech Pub 77350 is followed which includes an assessment of anyone who will attain an access badge for any CO work. The Competency Test is to insure that those requesting access have the wherewithal to perform the work. The CR is associated with capturing the web site and process to be used. Jeff said this Competency Test is not intended to train anyone but is to assess what should already be known. Kim Isaacs – Integra said she had been on the January 7, 2016 call and that she disagreed with Jeff’s statement that it was agreed the CR would be beneficial. Kim said Integra is not aware of any persistent problem with [1/29/16 Updates received from Integra in CAPS] [Delete INTEGRA] WITH THE CLEC’S employees skill level.

Jeff Bostow – CenturyLink said the Competency Testing is for anyone that would leave their dedicated CO space which includes CenturyLink employees, external contractors/suppliers, CLECs and CLEC subcontractors.

Kim Isaacs – Integra asked if a customer’s caged spaces are not subject to this Competency Testing but cageless spaces would require the Competency Testing. Kim said her understanding is that any job that requires a MOP will require a Competency level 4 lead resource to supervise the job. CenturyLink has not demonstrated that there is a persistent issue and thus this is adding an extra burden to CLECs. Kim said that she has not seen the test so she is not aware what it covers but wants to insure the test [1/29/16 Updates received from Integra in CAPS]WOULD ONLY [Delete COVERS] COVER the work activities that a CLEC [Delete WILL] WOULD perform IN A CO. Her concern is that a “one size fits all” Competency Testing might not fit since there are actions that a CLEC may never do in a CO. [1/29/16 Updates received from Integra in CAPS] BASED STATEMENTS CENTURYLINK MADE ON THE 1/28/16 AD HOC CALL – IT IS INTEGRA UNDERSTANDING THAT COMPETENCY TESTING IS ONLY REQUIRED FOR CLEC EMPLOYEES WHEN THE CLEC CHOOSES TO HAVE ITS EMPLOYEES INSTALL OR DECOMMISSION A COLLOCATION SPACE; OR WORK WITH POWER. ONCE THE CLEC COLLOCATION SPACE IS ESTABLISHED, DAY TO DAY OPERATIONS, EQUIPMENT OR CARD ADDITIONS DO NOT FALL UNDER THE COMPETENCY TESTING REQUIREMENTS.

Mark Coyne – CenturyLink said the purpose of the call today is to present the CR and that Kim is bringing up good questions. Mark said the next step is for CenturyLink to conduct an Ad Hoc call to review the CR and the Competency Testing process. He said CenturyLink would like to establish an Ad Hoc call to immediately follow the Tech Pub 77350 call on January 28 and that a separate meeting notice would be sent.

Kim Isaacs – Integra said she is concerned that the in depth calls related to a CR are not handled on the CMP monthly call. The CMP monthly calls are a standing two hour call and have been for over ten years and believes that time should be used to allow more people to participate and provide input. Kim said on the last Tech Pub 77350 Ad Hoc call, only Integra and Granite attended and that more CLEC participation is needed since these are impactful changes and having an Ad Hoc call is not working.

Mark Coyne – CenturyLink asked other customers on the call to weigh in and asked if they were supportive of extending the monthly call vs. holding a separate Ad Hoc call for those customers interested in a specific topic.

Victor Gaither – Time Warner Cable said he was flexible as to when CenturyLink would hold an Ad Hoc call but wanted more information on the scope of the new CR. Victor asked what type of work CenturyLink was talking about that would require the Competency Testing, for example, power work, fiber distribution panel, circuit work, etc. Victor said for work in a dedicated space, he did not think the Competency Testing is an issue for the CLEC employees/agents; the CLEC has the responsibility to insure their technicians are trained. Victor said he wants more information on the scope and when this might be implemented and that he also is concerned about his resources and that it seems like this is a big deal.

Jeff Bostow – CenturyLink said CenturyLink had a recent spate of installation related outages and found that some of the people erecting iron work, running cable, etc. did not have the proper training to do installation of inside plant. Jeff said he was talking about the technicians that build the network vs. those maintaining the network and used the example of the carpenter that builds a house vs. the owner of the house. Jeff said the installation job impacts the success of the next job and if someone does not know what they are doing and accidently causes an outage, CenturyLink is accountable to the PUC.

Kim Isaacs – Integra asked if the outages Jeff referred to were caused by a CLEC.

Jeff Bostow – CenturyLink said no, the outages were caused by human error. He said the Competency Testing is not fool proof but should help identify who knows how to perform the work and who does not.

Kim Isaacs – Integra said she does not have a problem with the Tech Pub 77350 standards but that a CLEC is contracted to CenturyLink to meet the standards and this Competency Testing seems like an extra step on who is allowed into a CO. Kim said the Competency Testing levels 1-4 may not be appropriate. In regard to how cageless space is handled, Integra has a workforce that is trained to work in that space and there has not been an issue the CenturyLink can point to. Kim said this is difficult to understand. Victor Gaither – Time Warner Cable asked if a cageless collocation is in scope.

Jeff Bostow – CenturyLink said yes it would be and gave examples of running cable or power or timing shelf synchronization.

Victor Gaither – Time Warner Cable asked if there was differentiation on the types of work to be done and the level of competency.

Jeff Bostow – CenturyLink said yes that the competency levels are taken from what was originally Telcordia (now Ericsson). Jeff said the four competency levels are industry standard and gave some examples of level 1-4 with the highest level requiring power certification. Jeff said when there is an outage, it has to be explained and how it was done incorrectly. The Competency Testing is to protect the network especially in a shared space.

Kim Isaacs – Integra said the Tech Pub 77350 now reads that if there is a MOP being worked by a level 1-3 technician, a level 4 lead is required to supervise the work.

Jeff Bostow – CenturyLink said that is correct.

Kim Isaacs – Integra said the Tech Pub 77350 requires CLECs/subcontractors to follow the same standards.

Victor Gaither – Time Warner Cable said if they have level 4 work, they resource that differently. Victor said he needs to read the Tech Pub and join the call next week.

Susan Lorence – CenturyLink asked if there was agreement to schedule a call for this CR following the Tech Pub call on January 28, 2016 since those resources may be the same.

Kim Isaacs – Integra said when contentious issues are pushed to an Ad Hoc call, attendance is lower.

Mark Coyne – CenturyLink said he will get with the CMP team to see if we can incorporate more discussion on the monthly CMP call. Depending on the topic, we will need to weigh what is most appropriate.

Armando Fimbres – Oregon PUC said he thought the recent discussion was good and wondered if the Ad Hoc calls can be added to the end of the CMP call.

Mark Coyne – CenturyLink said we have done that in the past but it also depends on the timing of when the CR is submitted. Mark asked if there were any more questions for Jeff. There were none.


Open Product/Process CR PC020216-1 Detail

 
Title: Eliminate Directory Listing Migration Daily Report
CR Number Current Status
Date
Area Impacted Products Impacted

PC020216-1 Completed
5/18/2016
Directory Listings
Originator: Gomez, Lee
Originator Company Name: CenturyLink
Owner: Gomez, Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink currently offers CLECs the option to request a Directory Listing Migration Daily Report to use to verify the completion of Conversion/Migration orders to FBDL.

This report has not been requested by any customer in at least 10+ years. CenturyLink is planning to eliminate this process and reporting capability.


Status History


Project Meetings

5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is associated with the elimination of this daily Directory Listings Migration report that customers have not requested in over 10 years. No comments were received on the level 4 notification to update the Directory Listing Providers Business Procedure. Mark said this CR has been in CLEC Test since May 5, 2016 and we would like to move it to a Completed status. There were no objections.

4/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the February meeting by Lee Gomez. The Level 4 notification to update the Directory Listing Providers Business Procedure was distributed March 21, 2016 via a Process notification. The comment cycle ended on April 5, 2016 and no comments were received. Mark said the final notice is due to be distributed April 20, 2016 with a proposed effective date is May 5, 2016. There were no comments.

3/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in the February meeting and that a level 4 notification to update the Directory Listing Providers Business Procedure had gone out March 15, 2016 with a proposed effective date of April 29, 2016.

CenturyLink NOTE: The level 4 notification to update the business procedure was distributed on March 21, 2016 and has a proposed effective date May 5, 2016.

02/17/16 Product/Process CMP Meeting Lee Gomez – CenturyLink presented this new CR. Lee said is does not appear any customer has ever requested this report and we would like to eliminate it. Lee asked if there were any questions. There were none.


Open Product/Process CR PC021116-1 Detail

 
Title: Eliminate Busy Line Verify and Busy Line Interrupt
CR Number Current Status
Date
Area Impacted Products Impacted

PC021116-1 Completed
12/14/2016
Operator Services
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

UPDATE March 15, 2016:

CenturyLink will eliminate the Busy Line Verify and the Busy Line Interrupt features from Operator Services Products and Services in the legacy Qwest fourteen states. This change is targeted for May 6, 2016 in all states except OR and WA. Oregon is most likely to be effective July 1, 2016. The WA date is pending.

ORIGINAL ENTRY: Effective May 6, 2016, CenturyLink will eliminate the Busy Line Verify and the Busy Line Interrupt features from Operator Services Products and Services in the legacy Qwest fourteen states.


Status History


Project Meetings

12/14/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said all states are in effect. Mark said we would like to move this CR to a Completed status. There were no objections.

11/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said all states are in effect. All states except Nebraska, Washington, and Oregon went into effect as of May 6, 2016. Oregon was effective on October 1, 2016. Washington was effective as of October 7, 2016. Nebraska went into effect November 15, 2016. Mark said we will leave the CR in CLEC Test and will review it in December. Mark asked if there were any questions. There were none.

10/19/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said the status of this CR is the same as last month. There are multiple effective dates dependent on the state: All states are in effect as of May 6, 2016 except Nebraska, Washington, and Oregon. Oregon is now in effect as of October 1, 2016. Washington is now in effect as of October 7, 2016. Nebraska has a proposed effective date of November 15, 2016. The related level 4 notices were sent on September 30, 2016. Mark asked if there were any questions. There were none.

9/21/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said the status is the same as last month for this CR that has multiple effective dates. All states are in effect as of May 6, 2016 except Nebraska, Washington, and Oregon. For Oregon, the effective date is October 1, 2016. For Washington, the final notice is to go out on September 22, 2016 with an effective date of October 7, 2016. Nebraska has a proposed effective date of November 15, 2016. The Nebraska level 4 notices will be sent early October.

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that all states went in effect on May 6, 2016 except Nebraska, Washington and Oregon. Oregon has an effective date of October 1, 2016. Washington still has a planned effective date of October 7, 2016; a level 4 CMP notice will be sent in August. Nebraska now has a planned effective date of November 15, 2016 and a level 4 notice will be sent the end of September. Mark asked if there were questions. There were none.

7/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said there are multiple effective dates for this CR. As relayed last month, all states are in effect except Nebraska, Washington and Oregon. Oregon has an effective date of October 1, 2016. Washington now has a planned effective date of October 7, 2016; a level 4 CMP notice will be sent in August. The effective date for Nebraska is still pending. Mark asked if there were questions. There were none.

6/15/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said there are multiple effective dates for this CR. All states are in effect except Nebraska, Washington and Oregon. Oregon has an effective date of October 1, 2016. The effective dates for Washington and Nebraska are yet to be determined.

5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said there are multiple effective dates for this CR that was presented in February. For all states except Washington and Oregon, a set of Level 4 Product and Process notices was sent with an effective date of May 13, 2016. Another set of Product and Process notices was sent for Oregon that originally had an effective date of June 1, 2016 but CenturyLink will instead send the Level 4 final notices for Oregon with an effective date of October 1, 2016.

Armando Fimbres – Oregon PUC asked if the new date for Oregon was the result of discussion.

Mark Coyne – CenturyLink said yes, per the SME team, the date was moved to October 1, 2016.

NOTE: As of May 25, 2016, the effective date for Nebraska is NOT May 13, 2016 afterall. Implementation in Nebraska is on HOLD at this time.

4/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the February meeting by Lee Brummett. There are multiple effective dates for this CR. One set of Level 4 Product and Process notices were sent on April 12, 2016 for all states except Washington and Oregon to be effective on May 13, 2016. Mark noted that the tariff effective date is actually May 6, 2016 but our Level 4 notifications were delayed. The Level 4 Product and Process notices for Oregon were sent on April 18, 2016 with an effective June 1, 2016. Currently, no date has been set to discontinue services in Washington. There were no comments.

3/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was also presented in the February meeting and that there were some questions in the meeting about the status of tariff filings. Mark said Lee Brummett – CenturyLink had submitted an update to the CR on March 11, 2016 which indicated that this change is targeted for May 6, 2016 in all states except Oregon and Washington. Oregon is most likely July 1, 2014. The Washington date is pending.

Lee Brummett – CenturyLink then reviewed the update that he provided to the CR on March 15, 2016. The update states: For the CenturyLink ILEC companies, the only FCC tariffs with BLV/BLI are the access tariffs. There will be an FCC 214 application for legacy Qwest which will be filed at a later date. All other tariffs with BLV and BLI are intrastate tariffs which will be filed with the state public utility commissions in accordance with their rules and filing requirements. A revised CR was also posted to the CMP wholesale calendar. Lee asked if there were any questions.

Kim Isaacs – Integra said with the FCC 214 application to be filed later, she wondered when it would be coming through.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.

02/17/16 Product/Process CMP Meeting Lee Brummett – CenturyLink presented this new CR to eliminate the Busy Line Verify and the Busy Line Interrupt features in the legacy Qwest fourteen states effective May 6, 2016. Lee said the reseller notice will be issued soon.

Kim Isaacs – Integra asked if this impacts CLSP [CenturyLink Local Services Platform]. Kim asked if there had been a 214 FCC filing and what date that would occur and also asked about the state filings to discontinue service.

Lee Brummett – CenturyLink said it would impact CLSP but would have to check on the date of the 214 FCC filing.

Kim Isaacs – Integra said AT&T is doing something similar and has a 214 filed with the FCC. Kim asked if the May 6, 2016 date is for Retail and Wholesale. Kim said Integra would need to update their tariffs also to follow CenturyLink dates.

Lee Brummett – CenturyLink said it is for both Retail and Wholesale and will have to check on the dates of the various state and federal filings.

Mark Coyne – CenturyLink [03/07/16 Updates received from Integra in CAPS] SAID IF POSSIBLE CENTURYLINK WOULD INCLUDE THE ANSWERS TO THESE QUESTIONS IN THE MEETING MINUTES AND THEN asked if there were any other questions. There were none.


Open Product/Process CR PC033016-1CM Detail

 
Title: Change to the CMP document to remove the references to CORA and EXACT 5/10/16 UPDATE: to include EXACT
CR Number Current Status
Date
Area Impacted Products Impacted

PC033016-1CM Completed
7/20/2016
Wholesale CMP document
Originator: Coyne, Mark
Originator Company Name: CenturyLink
Owner: Coyne, Mark
Director:
CR PM: Lorence, Susan

Description Of Change

With the upcoming Access Service Ordering and Billing Systems Consolidation project, the access ordering system CenturyLink Online Request Application (CORA) will no longer be a production system. The references to CORA [5/10/16 UPDATE in caps] AND EXACT on the current Change Request form will be removed and replaced with “Wholesale ACCESS Ordering Interface” as a more generic term.

5/10/16 UPDATE: Remove reference to EXACT and also Include the word “Access” as in “Wholesale Access Ordering Interface” on the revised CR form.


Status History


Project Meetings

7/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said a Level 1 Process notification was distributed on July 12, 2016, effective immediately, to update the CMP Document and the CR form to use the term “Wholesale Access Ordering Interface” instead of CORA or EXACT. Mark said the CR is in CLEC Test and asked if there were any objections to moving it to a Completed Status. There were none.

6/15/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR to revise the CMP CR form to replace CORA and EXACT with “Wholesale Access Ordering Interface” was unanimously voted on last month to allow the change. He said a Level 1 CMP notification would be sent soon.

5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was revised following the April monthly call to include the removal of EXACT along with CORA on the redlined CR form and to update the new CR systems entry to be specific to Access ordering, i.e., “Wholesale Access Ordering Interface”. A Vote notification was sent on May 11, 2016 along with a redlined CMP CR form with those updates and they are all included in the CMP package. Mark said a unanimous vote is required to update the CMP document.

Susan Lorence – CenturyLink then reviewed the CMP Vote process as included in Section 17.0 of the CMP document which is available at http://www.centurylink.com/wholesale/cmp/index.html. The key points of the CMP voting process are: each entity is entitled to a single vote regardless of any affiliates and quorum must be established. Susan said quorum will be based on 62.5% of the average CLEC and CenturyLink entities in attendance at the last six monthly CMP meetings, November 2015 through April 2016. The average number of entities in attendance during this period was eight so the quorum for today’s vote meeting is five. Quorum was easily met since there are nine entities in attendance. Susan then reviewed what a vote of “Yes” and “No” meant as depicted on the voting Ballot in the CMP package and asked if there were any questions. The vote was then conducted and the results are listed in the table:

Voting Carrier Voting Participant VOTE Midcontinent Communications Emily Davis (by phone) YES AT&T Jacob Rubin (by phone) YES Granite Judi O’Day (by phone) YES Integra Kim Isaacs (by phone) YES Global Capacity Liz Tierney (by phone) YES LS Networks Valerie Starr (by phone) YES Custom Call Jay Bodapati (by phone) YES TW Cable Sultan Kahn (by phone) YES CenturyLink Mark Coyne (by phone) YES

The vote was unanimous to make the changes to the CMP CR form. Susan proposed that we make the update with a Level 1 CMP notice and said she did not think we needed to wait until the effective date of the Access System Consolidation which is August 1, 2016. She asked if there were any objections to that approach. There were none.

4/20/16 CMP ProdProc Meeting Mark Coyne – CenturyLink presented the CR and advised callers that it is associated with the Access Service System Consolidation project. The CR is attached and includes a redlined CMP CR form for both EXACT and CORA to change systems names to a generic “Wholesale Ordering Interface.” He advised that the original CR only included CORA, but CenturyLink realized that EXACT should be removed as well. CenturyLink will revise the CR. The CMP vote to update the CMP document is proposed for the May meeting and a unanimous vote is required to proceed.

Kim Isaacs – Integra suggested that the replacement verbiage on the form be considered as “Wholesale Access Ordering Interface.”

Mark Coyne – CenturyLink stated that in light of forthcoming local service ordering changes, that would be included with the planned update to the CR.

Armando Fimbres – Oregon PUC asked for clarification regarding the voting process and asked if it would be a majority of those on the call at the time of the vote.

Mark Coyne – CenturyLink clarified that a unanimous vote is required to update the CMP document as long as we have established quorum on the call.

Susan Lorence – CenturyLink added that there is an email option as well if people cannot attend the monthly meeting in May. The meeting notice defines the way to vote via email.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.


Open Product/Process CR PC051216-1 Detail

 
Title: Discontinuation of 64k voice grade requirements on fiber when a copper network is retired
CR Number Current Status
Date
Area Impacted Products Impacted

PC051216-1 Completed
8/17/2016
Process and Documentation
Originator: Karpowich, Steve
Originator Company Name: CenturyLink
Owner: Karpowich, Steve
Director:
CR PM: Lorence, Susan

Description Of Change

[NOTE: CR revisions as of 06-14-16 are included in all caps.]

The FCC has relieved LECs of the requirement to provide a voice channel in the event the LEC retires its copper network IN A FIBER TO THE CURB (FTTC) AND FIBER TO THE HOME/PREMISE (FTTH, FTTP) AREAS. The CenturyLink Product team has determined it will no longer provide a 64Kbps voice channel in areas where it has undertaken such a fiber overbuild and copper retirement.

In its Memorandum Opinion and Order (FCC 15-166), issued December 28, 2015, the Federal Communications Commission relieved LECs of the obligation to provide a 64Kbps voice channel on fiber when the LEC overbuilds its copper network with fiber and retires its copper plant in a service area.

CENTURYLINK WILL CONTINUE TO OFFER THE CLEC COMMUNITY A 64 KBPS CHANNEL AS A REPLACEMENT OF AN ANALOG VOICE GRADE COPPER LOOP IN AREAS WHERE CENTURYLINK IS REPLACING THE FEEDER PORTION OF THE LOOP WITH FIBER.

CenturyLink will continue to make Voice Resale available in areas affected by copper retirements. CenturyLink will also work with any impacted customers to review its service offerings and to suggest any potential alternatives.

Proposed Implementation Date:7/1/16


Status History


Project Meetings

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was moved to CLEC Test as of August 1, 2016. He asked if there were any objections to moving it to a Completed status. There were none.

7/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in May. Following an Ad Hoc call on June 7, 2016, the CR was revised and the updates were reviewed in the June CMP monthly meeting. A level 4 notice was distributed on June 22, 2016 and the associated final notice was sent on July 15, 2016 with an effective date of August 1, 2016. We will review the CR in the August CMP meeting. Mark asked if there were questions. There were none.

6/15/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was a Walk-on that was presented in May. An Ad Hoc call was held on June 7, 2016 that included considerable discussion regarding how a hybrid loop is defined in relation to this CR. Mark said the draft meeting minutes were sent for review June 14, 2016 along with a revision to the CR that was submitted by the originator. A revised copy of the CR has since been posted to the CMP calendar which Mark then reviewed. With the revisions that had been made, CenturyLink would like to send the Level 4 notice after June 22, 2016. Mark said there were no documentation updates to be made associated with this CR so it would be a notification only.

Kim Isaacs – Integra said the updates look OK but that her assumption about the revised CR wording is that it means (6-24-16 Updates received from Integra in CAPS) THAT THE 64 K CHANNEL IS NOT AVAILABLE ONLY when CenturyLink retires its copper network and replaces it with fiber to the curb and fiber to the premise. She asked if that was correct.

Jamal Boudhaouia – CenturyLink said that was correct.

Susan Lorence – CenturyLink said it sounded like a CR revision was not required and that the meeting minutes were sufficient to capture the clarification.

Kim Isaacs – Integra said that was fine and she could not think of any documentation that needed to be updated.

06-07-16 FINAL meeting minutes from Ad hoc call Attendees: Bonnie Johnson – MN DOC Bruce Linseheid– MN DOC Diane Dietz – MN DOC Linda Jensen – MN DOC Greg Doyle – MN DOC Armando Fimbres – Oregon PUC Susan Travis – CO PUC Teresa Ferguson – CO PUC Lynn Notarianni – CO PUC Kim Isaacs – Integra Doug Denney – Integra Laurie Roberson – Integra Jamal Boudhaouia – CenturyLink Steve Karpowich– CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink went over the agenda for the meeting and then a brief history of the CR. Susan said Jamal Boudhaouia – CenturyLink had provided a copy of the FCC order, FCC-15-166A1, which was posted to the calendar.

Steve Karpowich– CenturyLink provided an overview of the CR and said the order FCC-15-166A1 came out last year and that CenturyLink had issued the CR to notify through CMP that CenturyLink would not provide 64Kbps voice channel when switching from copper to fiber.

Jamal Boudhaouia – CenturyLink referred call participants to paragraphs 55 to 66 of the FCC order which provides the specific requirements for the CenturyLink CR. Jamal said there is a new requirement to provide notification of copper retirement with 180 day lead time which used to be 95 days. He said he has provided some notifications to some call participants of some upcoming copper retirements for the 180 day lead time.

Kim Isaacs – Integra said the Copper retirement order is different than the 64Kbps Forbearance order.

Jamal Boudhaouia – CenturyLink said he agreed they are different orders. Jamal said the first FCC order is associated with when CenturyLink is putting fiber to the premise, to the DLC or to the curb and the requirement is now to issue the Network Disclosure at least 180 days prior to the planned cutover date. Jamal said the CenturyLink notification goes to the FCC and all customers. For those customers specifically impacted by the copper retirement, he provides the list of those impacted circuits that have to be moved to a different product. Jamal said the Forbearance order identifies if ILECs are retiring copper in an area and installing fiber to the home or curb, CenturyLink no longer is required to provide a 64Kbps channel. Jamal said the CLECs will no longer be able to order the 64Kbps loop in this situation.

Kim Isaacs – Integra said the FCC Forbearance order did not change the requirement for ILECs to provide the hybrid loops.

Jamal Boudhaouia – CenturyLink said it did. Jamal asked what is a hybrid loop channel.

Kim Isaacs – Integra said then read the following information from C.F.R 47 §51.319 that had been included in an email Kim sent on 5-18-16 following the CMP monthly call:

(iii) Narrowband services. When a requesting telecommunications carrier seeks access to a hybrid loop for the provision of narrowband services, the incumbent LEC may either: (A) Provide nondiscriminatory access, on an unbundled basis, to an entire hybrid loop capable of voice-grade service (i.e., equivalent to DS0 capacity), using time division multiplexing technology; or (B) Provide nondiscriminatory access to a spare home-run copper loop serving that customer on an unbundled basis.

Kim Isaacs – Integra said forbearance was not provided for these services.

Jamal Boudhaouia – CenturyLink said he needed to take this back to CenturyLink legal for review.

Doug Denney – Integra said CenturyLink needed to look at the hybrid loop definition and this would be more clear.

Teresa Ferguson – CO PUC asked for clarification of the footnote.

Jamal Boudhaouia – CenturyLink said the wording Kim referenced is in Footnote 172 of FCC-15-166A1.

Kim Isaacs – Integra said USTelecom did not ask for forbearance from this rule. Forbearance was specific to the 64Kbps rule.

Armando Fimbres – Oregon PUC asked if CenturyLink legal had provided their final review of this order.

Jamal Boudhaouia – CenturyLink said yes, for fiber to the home and fiber to the curb.

Kim Isaacs – Integra said this was the discussion during the CMP monthly meeting which was why the reference was sent after the meeting and questioned why there was no final response.

Jamal Boudhaouia – CenturyLink said that was not his understanding of the discussion. Jamal said now there are two architectures under discussion: fiber to the DLC and fiber to the curb and we need to get a good definition of a hybrid loop. He said the order under consideration has fiber and copper.

Kim Isaacs – Integra said the FCC defines a hybrid loop is a loop with both fiber optic cable and copper.

Doug Denney – Integra said in this case, Footnote 172 calls the hybrid loop a fiber loop and that CenturyLink needs to look at C.F.R 47 §51.319.

Jamal Boudhaouia – CenturyLink said he thinks so but needs to have further internal review.

Susan Lorence – CenturyLink said that the question of the definition of a hybrid loop is an open point. The next agenda item was grandfathered loops.

Jamal Boudhaouia – CenturyLink said once we agree on the definition, the existing 64Kbps loops would be grandfathered and would not be required to be disconnected. If the loop is copper, if a customer does not want them converted to fiber based, they must be removed according to FCC rules. Jamal said he would continue to issue the copper retirement notifications to all customers but now under the new timeline. The individual reports will go to the appropriate customers and will include the impacted circuits along with the timing of when a decision must be made.

Kim Isaacs – Integra said Copper retirement and the 64Kbps are two separate FCC orders. She asked if CenturyLink will use the copper retirement process for customers not getting a 64Kbps channel.

Jamal Boudhaouia – CenturyLink said yes, the two orders are separate. He said the copper retirement notices will continue to go to all customers as well as an FCC submittal. He said once forbearance is in effect, individual customers will follow the forbearance rules if there are LX- - loops that are impacted.

Bonnie Johnson – MN DOC said CenturyLink currently provides a report to each customer when copper loops are eliminated and asked if CenturyLink will do this for the 64Kbps.

Jamal Boudhaouia – CenturyLink said yes for those customers that are impacted.

Lynn Notarianni – CO PUC said there is a statement in Para 66 of FCC-15-166A1 that says: “…Meanwhile, a competitive LEC that has already requested and obtained access to an unbundled 64 kbps channel will have reasonably incurred costs in putting the channel to use, such as connecting the channel to a self-provisioned switch. Relieving an incumbent of its unbundling obligation in these circumstances would risk stranding the competitor’s investment with no clear offsetting benefit to the incumbent. Accordingly, we find it is appropriate to require incumbents to maintain access to channels made available under the 64 kbps unbundling requirement that are in use as of the adopted date of this order. “ Lynn asked how that paragraph is reconciled between the Copper retirement and Forbearance orders.

Jamal Boudhaouia – CenturyLink if there is an existing 64Kbps channel, those will stay in place. But once forbearance is in place, the 64 Kbps unbundling is not an option.

Lynn Notarianni – CO PUC said Paragraph 66 then only applies if the loop is already built out.

Jamal Boudhaouia – CenturyLink said yes, those loops are grandfathered so there is no stranded investment in place. Jamal asked if that answered the question.

Lynn Notarianni – CO PUC said that clarifies the CenturyLink interpretation.

Susan Lorence – CenturyLink asked if there were more questions about the reports.

Bonnie Johnson – MN DOC said no.

Kim Isaacs – Integra asked if the order impacts hicap circuits.

Jamal Boudhaouia – CenturyLink said no; these are not impacted.

Susan Lorence – CenturyLink said if CenturyLink can resolve the hybrid loop question, then CenturyLink will include the response in the meeting minutes. If there is an issue with the interpretation, Jamal will request another ad hoc call. When the meeting minutes are sent out for review, participants can then also identify if another ad hoc call is required.

Kim Isaacs – Integra asked if the CR would be revised.

Jamal Boudhaouia – CenturyLink said it would be. [NOTE: As of 6-14-16, Steve Karpowich – CenturyLink, CR originator, modified the CR to address the hybrid loop question. The revised CR is attached to the email associated with these meeting minutes.] Susan Lorence – CenturyLink asked if everyone is in agreement with the updates to the CR, CenturyLink would like to send the level 4 notification on June 21, 2016. She said that will provide a week after the meeting minutes are distributed to identify any issues.

Kim Isaacs – Integra and Jamal said that would be fine if there are no issues with the updated CR.

Armando Fimbres – Oregon PUC asked what CLECs are on the call.

Susan Lorence – CenturyLink said only Integra was on the call to represent the CLEC community. She said it was disappointing that there were not more CLECs that joined the call. She said the draft meeting minutes and updated CR would be available for the CMP meeting and the proposed timeline would be reviewed there.

The Ad hoc meeting was adjourned at 3:10 PM MT.

05-18-16 Content of EMAIL received from Kim Isaacs - Integra following CMP monthly meeting NOTE: Content in all caps was highlighted in email.

Clarification Needed on Change Request PC051216-1

I am hoping we will find that we are all the same page and I just misunderstood CenturyLink’s intent. As discussed on today’s CMP call, Integra believes that Change Request PC051216-1 Discontinuation of 64K voice grade requirements on fiber when copper network is retire needs to be modified to clarify that the discontinuation of the 64K voice grade channel apply only in cases where CenturyLink has deployed fiber to the premise (FTTP, FTTH). The forbearance the FCC granted in its Memorandum Opinion and Order (FCC 15-166) was “very limited” answering “USTelecom requests forbearance on a nationwide basis for all incumbent LECs from application of section 51.319(a)(3)(iii)(C) of the Commission’s rules, which requires unbundling of a 64 kbps voice-grade channel to provide narrowband services over fiber WHERE AN INCUMBENT LEC RETIRES A COPPER LOOP IT HAS OVERBUILT WITH A FIBER-TO-THE-HOME OR FIBER-TO-THE-CURB LOOP.” (¶ 55).

Rule: 51.319(a)(3)(iii)(C) says: (C) An incumbent LEC that retires the copper loop pursuant to paragraph (a)(3)(iv) of this section shall provide nondiscriminatory access to a 64 kilobits per second transmission path capable of voice grade service over the fiber-to-the-home loop or fiber-to-the-curb loop on an unbundled basis.

In the case where CenturyLink is retiring cooper but not deploying FTTH or FTTC, the FCC did not grant ILECs forbearance from C.F.R 47 §51.319 (a)(2) (iii)(A) Hybrid Loops for Narrowband services. (2) Hybrid loops. A hybrid loop is a local loop composed of both fiber optic cable, usually in the feeder plant, and copper wire or cable, usually in the distribution plant. (i) Packet switching facilities, features, functions, and capabilities. An incumbent LEC is not required to provide unbundled access to the packet switched features, functions and capabilities of its hybrid loops. Packet switching capability is the routing or forwarding of packets, frames, cells, or other data units based on address or other routing information contained in the packets, frames, cells or other data units, and the functions that are performed by the digital subscriber line access multiplexers, including but not limited to the ability to terminate an end-user customer's copper loop (which includes both a low-band voice channel and a high-band data channel, or solely a data channel); the ability to forward the voice channels, if present, to a circuit switch or multiple circuit switches; the ability to extract data units from the data channels on the loops; and the ability to combine data units from multiple loops onto one or more trunks connecting to a packet switch or packet switches. (ii) Broadband services. When a requesting telecommunications carrier seeks access to a hybrid loop for the provision of broadband services, an incumbent LEC shall provide the requesting telecommunications carrier with nondiscriminatory access to the time division multiplexing features, functions, and capabilities of that hybrid loop, including DS1 or DS3 capacity (where impairment has been found to exist), on an unbundled basis to establish a complete transmission path between the incumbent LEC's central office and an end user's customer premises. This access shall include access to all features, functions, and capabilities of the hybrid loop that are not used to transmit packetized information. (III) NARROWBAND SERVICES. WHEN A REQUESTING TELECOMMUNICATIONS CARRIER SEEKS ACCESS TO A HYBRID LOOP FOR THE PROVISION OF NARROWBAND SERVICES, THE INCUMBENT LEC MAY EITHER: (A) PROVIDE NONDISCRIMINATORY ACCESS, ON AN UNBUNDLED BASIS, TO AN ENTIRE HYBRID LOOP CAPABLE OF VOICE-GRADE SERVICE (I.E., EQUIVALENT TO DS0 CAPACITY), USING TIME DIVISION MULTIPLEXING TECHNOLOGY; OR (B) PROVIDE NONDISCRIMINATORY ACCESS TO A SPARE HOME-RUN COPPER LOOP SERVING THAT CUSTOMER ON AN UNBUNDLED BASIS.

I don’t see the need for an ad hoc call, if CenturyLink updates the PC051216-1 to say something similar to the following:

The FCC has relieved LECs of the requirement to provide a voice channel in cases where the LEC retires its copper network and has overbuilt with a fiber-to-the-home (FTTH) or fiber-to the-curb (FTTC) loop. The CenturyLink Product team has determined it will no longer provide new** 64Kbps channel in areas where it has retired a copper and overbuilt with a FTTH or FTTC. In its Memorandum Opinion and Order (FCC 15-166), issued December 28, 2015, the Federal Communications Commission relieved LECs of the obligation to provide a 64Kbps voice channel on fiber when the LEC retires copper loops it has overbuilt with FTTH and FTTP

CenturyLink will continue to make Voice Resale available in areas affected by copper retirements when it has overbuilt with FTTH or FTTC.

Proposed Implementation Date: 7/1/16 **Note** The FCC “grandparented” rule 51.319(a)(3)(iii)(C) so there will not be an impact to any embedded base of 64K channels being provided in service areas where copper has been retired and CenturyLink has overbuilt with FTTH and FTTC.

The above addresses only the clarity needed for change request PC051216-1. I haven’t had the opportunity to discuss the need for an amendment internally yet. Thank you. ** 5/18/16 Product/Process CMP Meeting Steve Karpowich – CenturyLink presented this Walk on CR. Steve said the FCC relieved LECs of the requirement to provide a voice channel (64 kb/s) when the copper network is retired. Steve said CenturyLink is planning to go that direction and is providing notice. He said we will work with customers to consider possible alternatives.

Kim Isaacs – Integra (5-27-16 Updates received from Integra in CAPS) STATED (delete ASKED IF) this ONLY APPLIES TO (delete IS) copper (delete ONLY) retired WHEN CENTURYLINK DEPLOYS FIBER to the premise.

Steve Karpowich – CenturyLink said he thought that was true but will investigate further. He thought we are getting rid of unbundled copper loop if we retire copper.

Bonnie Johnson - Minnesota Dept of Commerce said when there is a copper retirement, CenturyLink provides a spreadsheet 90 days ahead of time and asked if the report will include all loops in the future.

Steve Karpowich – CenturyLink said that was correct.

Jamal Boudhaouia – CenturyLink said we provide that list today and not just xDSL loops.

Kim Isaacs – Integra said (5-27-16 Updates received from Integra in CAPS) VOICE SERVICE IS ONLY IMPACTED if the copper is retired to the premise. (delete ,) WHEN COPPER IS RETIRED IN THE FEEDER, DISTRIBUTION, OR WHEN A FIBER BASED DLC IS DEPLOYED only xDSL loops are impacted. Voice (ANALOG DS0 UNE LOOPS) and DS1 LOOPS are not impacted.

Jamal Boudhaouia – CenturyLink said the Forebearance rule does not specify. When replacing copper with fiber, the 64Kbps channel will not be available which is the change of law.

Kim Isaacs – Integra said that she disagreed with that interpretation.

Jamal Boudhaouia – CenturyLink said if we disagree, we may need more discussion. Jamal said we will look at the rule again but DS1 was not impacted. Currently, Jamal said he sends all the copper loops and then the CLEC determines which ones can be transferred to 64K.

Kim Isaacs – Integra said (5-27-16 Updates received from Integra in CAPS) (delete THERE) are many EXISTING VOICE/ANALOG loops that are impacted and asked if all of those had to be changed to resale voice. [NOTE: THE FCC FORBEARANCE ORDER “GRANDPARENTED” THE 64K CHANNEL WHEN AN ILEC DEPLOYED FIBER TO THE HOME/PREMISE SO THE FORBEARANCE WILL NOT IMPACT EXISTING SERVICES PROVIDED ON 64K CHANNELS]

Jamal Boudhaouia – CenturyLink said if it is a DS0 channel and the copper is not retired, those are not impacted. If everything is moved to fiber to the premise, those are impacted. Jamal said for direct copper fed homes with no cross box that is being entirely replaced, or it is split, then copper is no longer available to premise. He will now send the retirement disclosure and ask customers to make a change based on this new rule.

Kim Isaacs – Integra said that the Order says the LEC is required to serve the CLEC with (5-27-16 Updates received from Integra in CAPS) VOICE GRADE DS0 LOOPS WHEN THERE IS A FIBER FED DCL AND THE PREMISE IS SERVED BY COPPER (delete A FIBER FED LOOP).

Jamal Boudhaouia – CenturyLink said that is not what the order says.

Kim Isaacs – Integra gave the example of new Greenfield fiber and said they don’t have access today. Kim said if it is fiber to the premise with a straight fiber circuit, there is no access to 64K.

Jamal Boudhaouia – CenturyLink said he did not think they would solve this and would need to review the language and suggested an Ad Hoc call to discuss.

Kim Isaacs – Integra agreed that an Ad Hoc is required.

Bonnie Johnson - Minnesota Dept of Commerce said her question is outstanding. When CenturyLink retires copper and notifies CLECs of the impacted xDSL loops, the voice grade loops swing to the fiber fed. Bonnie said it sounds like that will no longer occur and asked if the voice grade loops will now appear on the CenturyLink spreadsheets that are sent.

Jamal Boudhaouia – CenturyLink said if the loops are straight copper, they are all included today on the list that is sent. Jamal said if it is an F1 change, he asks for everything on the report not just xDSL.

Kim Isaacs – Integra said she disagrees; she only sees xDSL and some DS0 but does not see all loops. Kim said her ICA says DS0 are provided on hybrid loops.

Jamal Boudhaouia – CenturyLink said that is the change of law that allows CenturyLink to present this CR.

Bonnie Johnson - Minnesota Dept of Commerce asked if there will need to do an amendment before this process is changed.

Jamal Boudhaouia – CenturyLink said he needed to investigate that.

Mark Coyne – CenturyLink said Jamal will provide the language in the order for the minutes and we will set up an Ad Hoc call.

Susan Lorence – CenturyLink asked if some examples from Kim would be helpful before having a call.

Kim Isaacs – Integra said she could provide an example where all circuits are not provided. (5-27-16 Updates received from Integra in CAPS) [NOTE: EXAMPLE FROM CENTURYLINK’S FCC COPPER RETIREMENT FILING 5/4/2016 NETWORK DISCLOSURE 788 – INDICATES NON-LOADED LOOPS ARE IMPACTED (VOICE GRADE DS0 LOOPS ARE NOT CONSIDERED “NON-LOADED COPPER LOOPS”) ALL OTHER LOOP TYPES REMAIN AVAILABLE.

INTEGRA INSERTED TABLE BELOW (For a better view of this table, refer to the meeting minutes posted to the Wholesale calendar at http://wholesalecalendar.centurylinkapps.com/cal/2016/5)

STATE WIRE CENTER PLANNED COMPLETION OR RETIREMENT DATE DA (s) Job # Replacing AZ McClintock TEMPAZMC 07-15-2016 N/A N.067002 Growth in distribution area requires CenturyLink to cut facilities to fiber fed digital loop carrier system (DLC). After the cut to DLC, copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.] END TABLE

Liz Tierney – Global Capacity said she was trying to distinguish between xDSL and voice grade and what the difference was for conversion. Liz asked how the xDSL would be impacted.

Jamal Boudhaouia – CenturyLink said the LX-- for voice grade will move to a new NC/NCI combination and there are other loops impacted. Jamal said xDSL is impacted since it has to be copper all of the way.

Mark Coyne – CenturyLink asked if there were any other questions prior to the Ad hoc call. There were none.


Open Product/Process CR PC060116-1 Detail

 
Title: Eliminate Regional paper reports Report names are ECS1/2 in Central and 51034/5, 50414 in Eastern
CR Number Current Status
Date
Area Impacted Products Impacted

PC060116-1 Completed
9/21/2016
Originator: Pontinen, Tom
Originator Company Name: CenturyLink
Owner: Pontinen, Tom
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink would like to eliminate the CRIS originated paper reports that were developed pre-Divestiture related to Toll settlements. Reports are sent to all ILECs and CLECs which receive records from CenturyLink. A large number of customers have requested not to receive them. These report formats differ by CRIS region: Eastern/Western/Central.

Western Report distribution was halted over 15 years ago. Reports are named ECS1/2 in Central and 51034/5, 50414 in Eastern.

Data on the reports includes:

Record counts for Wireless, Wireline Transit records

Record count for originating and terminating Switched Access records (Jointly Provided Switched Access - JPSA)

Count of DA, National DA messages

Count of Operator Handled messages

Sent Collect/Received Collect messages

NOTE: An example of one of the reports can be provided.

Data on the reports reflect records sent from CenturyLink to the ILECs/CLECs in industry standard format (records for access billing, records for end user billing, copy records, etc.). If the related data is sent to a customer’s Service Bureau, these reports may be distributed to the Service Bureau vs. to the customer.

CenturyLink believes these paper reports can be discontinued because much of the data can be found in the following locations:

• The report file transmittal information accompanying these records

• The header and trailer records within the data files

• LEXCIS billing reflects much of the information on the paper reports.


Status History


Project Meetings

9/21/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC TEST as of September 1, 2016. There were no CLEC comments. Mark asked if there were any objections to moving this CR to a Completed status. There were none.

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said the initial Level 4 notice was sent on July 12, 2016 and the final notice was sent on August 11, 2016. There were no CLEC comments. Mark said there were no document updates for this CR but there is a document posted to the Document Review site that has examples of the paper reports that will be eliminated. To insure coverage, CenturyLink has been sending a copy of the initial notice along with the paper reports that are generated to the customers that normally receive the reports to let them also know the reports are being discontinued. The planned effective date for this change is September 1, 2016. Mark asked if there were questions. There were none.

7/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month. A Level 4 notification was sent on July 12, 2016. There are no documentation updates associated with this change but CenturyLink did post some information to the Document Review site associated with the notification that included some examples of the paper reports that are to be eliminated. The planned effective date for this change is September 1, 2016.

6/15/16 Product/Process CMP Meeting Tom Pontinen – CenturyLink presented this new CR. He said the report was originally designed before switched access and was for independent company settlements. Tom said CenturyLink does not think the reports are needed any longer and eliminating these paper reports will save thousands of print pages each month.

Kim Isaacs – Integra asked if the reports or data is available electronically vs. paper.

Kathy Pearce - CenturyLink said these are paper reports only distributed via US Mail.

Susan Lorence – CenturyLink said she thought the report data was available in other electronic forms.

Kathy Pearce - CenturyLink said the information on the paper reports has similar information as to what is on the electronic toll and access report files that are distributed. Kathy said the data and trailer records on the data files also carry totals and are currently available to customers.

Mark Coyne – CenturyLink said we will move forward with the CR then.


Open Product/Process CR PC062316-1 Detail

 
Title: Eliminate Directory Publisher List and Directory Delivery List products [7/20/16 Update to remove Directory Assistance List]
CR Number Current Status
Date
Area Impacted Products Impacted

PC062316-1 Completed
10/19/2016
Directory Listings Directory Listings
Originator: Gomez, Lee
Originator Company Name: CenturyLink
Owner: Gomez, Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink currently has the following products available for Wholesale; Directory Publisher List and Directory Delivery List and these are products focused towards Publishers. Since the first availability of these products in 2004, there have been no inquiries or show of interest in either of these products.

CenturyLink would like to eliminate both products and the related documentation effective 9/1/2016.

7-20-2016 DESCRIPTION UPDATE TO REMOVE the product Directory Assistance List from the products being eliminated at this time.


Status History


Project Meetings

10/19/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is in CLEC Test as of October 6, 2016. There were no CLEC comments. Mark asked if there were any objections to moving this CR to a Completed status. There were none.

9/21/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said there were no CLEC comments submitted on the level 4 notification that was sent on August 22, 2016. The final notice will be sent September 21, 2016 with the planned effective date of October 6, 2016.

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said Lee Gomez – CenturyLink presented this CR last month to eliminate three Directory Listings reports. Mark said that Kim Isaacs – Electric Lightwave had relayed in last month’s call that she found the Directory Assistance List product in their ICA in Section 10.6. Lee investigated this and on July 20, 2016, Lee revised the CR to remove the Directory Assistance List (DAL) product. Mark said a level 4 notification will be sent in August with a planned effective date of October 6, 2016. Mark asked if there were questions. There were none.

7/20/16 Product/Process CMP Meeting Lee Gomez – CenturyLink presented this new CR to eliminate three Wholesale Directory Listing products: Directory Publisher List, Directory Delivery List and Directory Assistance List. Lee said the products are focused on publishers who want to create a phone book and those who provide directory assistance. The products have been available since 2004 but have had no show of interest from customers.

Kim Isaacs – Integra asked if the products are in the Interconnection Agreement (ICA).

Lee Gomez – CenturyLink said they are not in the ICA but are documented in the PCATs.

Kim Isaacs – Integra said she found the Directory Assistance List product in their ICA in Section 10.6 and read a portion of that section.

Lee Gomez – CenturyLink said it could be a terminology issue but that she could be wrong. Lee said she will take the question back to her legal team for review.

Mark Coyne – CenturyLink said if possible, CenturyLink will provide an update with the meeting minutes.

NOTE: As of 7-20-16, Lee Gomez - CenturyLink revised the CR to remove the Directory Assistance List (DAL) product as there is reference to it in the ICA. Lee will be meeting with legal to discuss possible changes.


Open Product/Process CR PC090611-1 Detail

 
Title: Eliminate 5 USOCs in Nebraska.
CR Number Current Status
Date
Area Impacted Products Impacted

PC090611-1 Completed
2/15/2012
Resale
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be eliminating the following USOCs in Nebraska: 1VT and 1V3 (Measured package service), ESY6N and ESY65 (Custom Calling Feature Package) and SSV (Secretarial Answer Service). All USOCs have previously been grandfathered. Currently there are no wholesale/resale customers with these services.


Status History


Project Meetings

02/15/2012 Product Process Monthly Meeting Mark Coyne – CenturyLink said the effective date for this CR was 1-7-12 and that the CR was now in CLEC Test. Mark asked if CenturyLink could move the CR to a Completed status. There were no objections.

01/18/12 Product Process Monthly Meeting Mark Coyne – CenturyLink said the effective date was January 7, 2012 and that the CR was now in CLEC Test. Mark indicated we would revisit the CR in February.

12/14/11 Product Process Monthly Meeting Mark Coyne – CenturyLink said a Level 2 notice would go out on December 16, 2011 with an effective date of January 7, 2012.

11/16/11 Product Process Monthly Meeting Mark Coyne – CenturyLink advised that it would be a Level 2 notice to go out on December 16, 2011 with an effective date of January 7, 2012.

10/19/11 Product Process Monthly Meeting Mark Coyne – CenturyLink stated the CR had been presented last month and that there was agreement that since there were no customers, a level 2 notice would be sent in December with an effective date of January 7. No other questions were raised.

9/21/11 Product Process Monthly Meeting Lee Brummett – CenturyLink presented the CR that was associated with five previously grandfathered USOCs in Nebraska that were now to be eliminated. He said the implementation date had been pushed from November to January 7, 2012. Lee requested that since there were no Wholesale customers, we would like to reduce the notice to a Level 2.

Mark Coyne – CenturyLink said since no one had objected, CenturyLink would proceed with a Level 2 notice.


Open Product/Process CR PC030712-1 Detail

 
Title: 7/12/12 Revised Eliminate 23 Billing USOCs and 105 Universal Special Assembly Codes. ORIGINAL TITLE Eliminate 26 Billing USOCs and 166 Universal Special Assembly Codes.
CR Number Current Status
Date
Area Impacted Products Impacted

PC030712-1 Completed
9/19/2012
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CR Revised 07-12-12 CenturyLink will be eliminating 23 billing USOCs across the 14 states: 13FBE, 1LC2N, 1LC2Y, 1LC4N, 1LC4Y, 1LMFS, 27ECD, 48C, 4N9, 91V, 91X, FW4, LCQSF, LCQSZ, P5V, SC4, SSV, SV7SM, WK1SK, WK5SK, WP5SX, ZZ3BR, ZZ3HJ.

07-12-12 CenturyLink will NOT be removing P5P, SVGSK, SVMSK AND VMT.

CR Revised 07-12-12 CenturyLink will be eliminating 105 USACs across the 14 states: #AAAO, #AAC9, #ACA3, #ADA5, #AEAT, #AECQ, #AFH6, #AFLJ, #AFM9, #AFNA, #AGCK, #AJDU, #AJF9, #AJJJ, #AJL3, #AJLJ, #AJMD, #AJME, #AJMF, #AJNE, #AJNF, #AJNJ, #AJNL, #AJNM, #AKC2, #AKC5, #AKC7, #BAC1, #BAE9, #BAEA, #BAES, #BAEV, #BAF6, #BAFA, #BAG1, #BAG2, #BAG3, #BAG8, #BAGH, #BAGO, #BAHA, #BAHK, #BAHL, #BAHN, #BAHO, #BAHP, #BBAE, #BBCR, #BBDC, #BBEA, #BBEN, #BBEP, #BCEL, #BCF6, #BCG5, #CAJ2, #CAJ3, #CAJ4, #CAJ5, #CAKK, #CAMG, #CANE, #CANL, #CANM, #CANN, #CANO, #CANP, #CANQ, #CANR, #CANS, #CBBN, #CDA6, #CHDP, #CJEM, #CJEN, #CJEO, #CKEM, #CLHM, #CMF1, #CMF2, #CMFY, #CMFZ, #CMKE, #CML9, #CMLU, #CMMD, #CMTS, #DHPA, #DHPB, #DHSS, #DHST, #DHWN, #DHY8, DKBR, #DKBS, #DKBU, DKBY, #DKBZ, #DKCA, #DKCG, #DKCL, #DKCM, #DKCN, #DKCP, #DKDO, #DKDV, #DKF2 , #DKF6 , #DKF7 , #DKF9 , #DMFT , DMFU , #DMFV , #GHAD , #GLAR , #LALY, and #LAFB

07-12-12 CenturyLink will NOT be removing #AADP, #CBCK, #CBCR, #CBDH, #CBF4, #CBGC, #CEAX, #CFB3, #CFB4, #CFB7, #CFCF, #CFD3, #CFD4, #CFD5, #CFEE, #CJEJ, #CJEK, #CMBD, #CMDC, #CMPX, #CMQ3, #CMQ4, #DCF2, #DCFC, #DHAL, #DHFX, #DHQQ, #DHTP, #DHXB, #DHXC, #DHXE, #DHYW, #DKBM, #DKBQ, #DKDW, #DKDX, #DKDY, #DKEG, #DLA1, #DMC6, #DMC7, #DMFS, #FFB1, #GPHQ, #LACB, #LAG8, #LAKA, #LALF, #LAMN

CenturyLink will be eliminating 26 billing USOCs across the 14 states: 13FBE, 1LC2N, 1LC2Y, 1LC4N, 1LC4Y, 1LMFS, 27ECD, 48C, 4N9, 91V, 91X, FW4, LCQSF, LCQSZ, P5P, P5V, SC4, SSV, SV7SM, SVGSK, SVMSK, WK1SK, WK5SK, WP5SX, ZZ3BR, ZZ3HJ.

3-16-12 Update: There is one Resale customer that has the USOC LCQSZ.

CenturyLink will be eliminating 166 USACs across the 14 states: #AAAO, #AAC9, #AADP, #ACA3, #ADA5, #AEAT, #AECQ, #AFH6, #AFLJ, #AFM9, #AFNA, #AGCK, #AJDU, #AJF9, #AJJJ, #AJL3, #AJLJ, #AJMD, #AJME, #AJMF, #AJNE, #AJNF, #AJNJ, #AJNL, #AJNM,

#AKC2, #AKC5, #AKC7, #BAC1, #BAE9, #BAEA, #BAES, #BAEV, #BAF6, #BAFA, #BAG1, #BAG2, #BAG3, #BAG8, #BAGH, #BAGO, #BAHA, #BAHK, #BAHL, #BAHN, #BAHO, #BAHP, #BBAE, #BBCR,

#BBDC, #BBEA, #BBEN, #BBEP, #BCEL, #BCF6, #BCG5, #CAJ2, #CAJ3, #CAJ4, #CAJ5, #CAKK, #CAMG, #CANE, #CANL, #CANM, #CANN, #CANO, #CANP, #CANQ, #CANR, #CANS, #CBBN, #CBCK, #CBCR, #CBDH, #CBF4, #CBGC, #CDA6, #CEAX, #CFB3, #CFB4, #CFB7, #CFCF, #CFD3, #CFD4, #CFD5, #CFEE, #CHDP, #CJEJ, #CJEK, #CJEM, #CJEN, #CJEO, #CKEM, #CLHM, #CMBD, #CMDC, #CMF1, #CMF2, #CMFY, #CMFZ, #CMKE, #CML9, #CMLU, #CMMD, #CMPX, #CMQ3, #CMQ4, #CMTS, #DCF2, #DCFC, #DHAL, #DHFX, #DHPA, #DHPB, #DHQQ, #DHSS, #DHST, #DHTP, #DHWN, #DHXB, #DHXC, #DHXE, #DHY8, #DHYW, #DKBM, #DKBQ, #DKBR, #DKBS, #DKBU, DKBY, #DKBZ, #DKCA, #DKCG, #DKCL, #DKCM, #DKCN, #DKCP, #DKDO, #DKDV, #DKDW, #DKDX, #DKDY , #DKEG , #DKF2 , #DKF6 , #DKF7 , #DKF9 , #DLA1 , #DMC6 , #DMC7 , #DMFS , #DMFT , DMFU , #DMFV , #FFB1 , #GHAD , #GLAR , #GPHQ , #LACB, #LAG8, #LAKA, #LALF, #LALY, #LAMN, and #LAFB

3-16-12 Update: There are no CLEC or Resale customers that have any of the USAC codes.

NOTE: The spreadsheet of USOCs and USACs with a description (if available) will also be attached to the CR whenever it appears in the CMP Product Distributuion package and when CMP notification is provided.


Status History


Project Meetings

09/19/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the effective date for both CRs was 8/31/12 and that both are in CLEC Test and we would like to move them to Completed. There were no objections.

08/15/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the Level 4 final notices for both CRs are due 8/16/12 with a planned effective date of 8/31/12 for both.

07/18/2012 CMP Monthly Prod/Proc Meeting Mark Coyne - CenturyLink recapped the Change Request, stated that the title and description and been revised, and asked Lee Brummett to provide an update.

Lee Brummett – CenturyLink provided an update on these two CRs stating that the effective date of August 31, 2012.

Mark Coyne – CenturyLink stated that the Level 4 notice on these was scheduled for July 19, 2012.

Kim Isaacs – Integra asked if a clean list of USOCs would be included with the notice.

Susan Lorence – CenturyLink asked for clarification that the CLECs would rather see the list as depicted in the package or as a final list with only the affected USOCs listed.

Kim Isaacs – Integra asked for a clean list.

06/20/2012 CMP Monthly Prod/Proc Meeting Lee Brummett – CenturyLink provided an update on these two CRs stating that the final list of USOCs would be available for the July monthly meeting and that the Level 4 notice would be sent afterwards with an effective date of August 31, 2012.

Mark Coyne – CenturyLink asked if there were any questions. There were none.

05/16/12 Product Process Monthly Meeting Mark Coyne – CenturyLink relayed that a NOTE had been included on the list of USOCs on the second CR to clarify discussion from the prior monthly meeting and read the following Note: IF A USOC APPEARS IN THE DEFINITION COLUMN THAT IS DIFFERENT FROM THE USOC IN COLUMN 2, CENTURYLINK IS PROVIDING ABBREVIATED USOC AS A GENERAL REFERENCE. THIS IS NOT AN INDICATION THAT THE ABBREVIATED USOC IS BEING REMOVED. Mark said the SME team is continuing to review the list of USOCs and do not yet have an effective date. When we do have an actual date, the normal notification process will be followed. Mark asked if there were any questions. There were none.

4/18/12 Product Process Monthly Meeting Mark Coyne – CenturyLink advised that a list was included in the package. He relayed there were questions last month regarding the definitions and that the SME team has included an update in the package. Lee Brummett – CenturyLink added that the list is still being cleaned up and there is not a concrete date for the grandfathering or making the USOCs obsolete. If any changes are needed to any accounts, CenturyLink will work with the individual CLECs to make those changes. Kim Isaacs – Integra stated that they had concerns that there were USOCs on the list that were indicated as not found, yet were in PCATs. She said Integra has customers for some of these USOCs, for example, the ESX USOC, Call Waiting. Lee Brummett – CenturyLink clarified that the ESX USOC itself is not being removed, but rather those with additional characters such as “ESX /” and “NNK /”. The ESX and NNK USOCs would remain, but others such as the example given were being addressed and would be removed. Kim Isaacs – Integra noted that the list did include that ESX = Call Waiting next to “ESX /”. Mark Coyne – CenturyLink indicated that was to let the CLEC community know what service or feature the basic USOC described, but that the feature or service itself was not being eliminated. Bonnie Johnson – Integra asked if it could be assumed that if any CLEC had “ESX /” on a CSR, it would be changed to reflect “ESX”. Lee Brummett – CenturyLink stated that was correct. Susan Lorence – CenturyLink stated that in the future, CenturyLink would add a note to the USOC lists to clarify why the general USOC definition was included.

3/21/12 Product Process Monthly Meeting Lee Brummett – CenturyLink stated that CenturyLink will be eliminating 26 billing USOCs across the 14 states. That specific USOC will be replaced with another as soon as it’s decided the replacement code.

Bonnie Johnson – Integra asked if these were specifically billing USOCs.

Lee Brummett – CenturyLink stated that there were no rates associated with the codes.

Susan Lorence – CenturyLink stated that and that there is one Resale customer that has the USOC LCQSZ and that there were no customers with the Universal Special Assembly Codes.

Kim Isaacs – Integra asked what was meant about replacements.

Lee Brummett – CenturyLink stated that the USOC will be replaced with another as soon as it’s decided the replacement code.

Kim Isaacs – Integra asked for confirmation that the USOCs would be eliminated.

Lee Brummett – CenturyLink agreed.


Open Product/Process CR PC030712-2 Detail

 
Title: 7/12/12 Revised Eliminate 264 Billing USOCs . ORIGINAL TITLE: Eliminate 330 Billing USOCs.
CR Number Current Status
Date
Area Impacted Products Impacted

PC030712-2 Completed
9/19/2012
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CR Revised 07-12-12 CenturyLink will be eliminating 264 billing USOCs across the 14 states.

These USOCs are:

13C1S, 18LA1, 18LSO, 1FLPL, 1LFCK, 1LFOK, 1LFSK, 1M84X, 1M8OO, 1M8SX, 1M8WO, 255PC, 27EKT, 29F5J, 29O1J, 29O1R, 29OBJ, 2EGAB, 2EGO1, 2EH14, 2EH2O, 2EHAB, 2EHO1, 2EJA1, 2EJA2, 2EJOO, 2HG , 2T3 , 38G , 38G28, 3KKVY, 43C , 45NF1, 48JA8, 48JO1, 48NAB, 48NDB, 48NDC, 4N9ST, 4OT , 4RC2A, 4TBXX, 4TGAB, 4TMG8, 4TMOO, 4TNAA, 4TNBA, 4TNNT, 4TNOC, 4TNSX, 4TO , 4TP , 59Y , 5LKSX, 8CJBT, 8QX28, 8QXKS, 96T , 96TAA, 96VAB, 96VO1, 96Y14, 96YAB, 96YDB, 96YO1, 96YSX, 98M35, 98MNI, 98MSC, A69SX, A6X , ACB , AMH , B1T , BECSK, BECSY, BFM , BMH , BP1AX, BP2AX, C16E6, C16V6, CBT99, CJD , CTY, CW1SX, CW9 , D2A2S, D56SX, D8D35, D8D81, D8DOT, D8DS1, D8DSX, D8FBX, D8FS1, D8FSX, DAZ17, DAZ25, DAZ33, DAZ99, DAZAA, DAZOO, DCMAA, DDX29, DGHOO, DGK , DGKAA, DGKST, DHSSZ, DJGA1, DJHO9, DL5SC, DLC25, DLC27, DLC49, DLCC4, DLCSX, DLJ18, DLJ23, DMVEX, DMZ , DNY2O, DP3OA, DQL99, DQLOO, DR5/R, DSDO1, DSEG8, DUXN4, E9B , ED7 , EJ9AX, ESCH3, ESN , ETAXA, EWUS4, EXBJX, EXLCF, EXLCH, EXTSO, EZUC2, FO3NP, FVW5Q, FVW5Z, FVWKQ, G4888, GHA2O, GHB28, GHB2O, H2YFA, H2YFD, H3JT7, H5FDX, HOGO3, HOHTC, HOLPE, HOPTF, HOQ , HUJ , HUJSW, IN501, JK94P, JKHDR, JKHSX, JKWS4, JKWS6, JKWSB, JKWST, JKWSX, K1JXX, K59 , K5B2X, K5BST, K5BSX, K6HS6, K6HSX, KEMCB, KEMCM, KU2SK, KV2 , LPDXG, LPZXJ, LTG , LTTDA, LXP2X, LXP4X, LXPXX, MAW , MBZSC, MCL15, ME5 , MPL , MPQSX, MRAGC, MWXSX, NDS , NF2WA, NF2WB, NF2WC, NF2WD, NTF , NTFM4, NTFM6, NTFX3, P89.., PCHSG, PCHSN, PNXCH, PNXSX, PRMCU, PTZAP, PXBSY, QAS , RCTO6, RJCO2, RTCXN, RTCXQ, RTVXH, RX7SO, S4841, S4843, S4847, S4857, S4859, S4PST, S4PSZ, S7VS6, S7VST, SCL , SCT , SD7MS, SD7SC, SDM25, SDM2F, SV7 , SVM , T1YAZ, T3S , TAX , TAXS6, TAXSN, TCC , TEEPN, TFA , TFASC, TFAST, TFSST, TFSSX, TL9AC, TL9AX, TL9AZ, TLAB1, TLAB3, TLAS1, TLAS2, TLAS3, TLASC, TLASG, TLASW, TNE2X, TNE4X, VUMAA, W3PBJ, W3PBT, WUPSN, L1VF8

07-12-12 CenturyLink has added one USOC to the original list - L1VF8.

07-12-12 CenturyLink will NOT be removing 1CP, 24MAB, 24MBC, 27ESX. 2EJAA, BOA, BZV, CUDXX, D8FS3, DHSCC, DHSSX, DHSSZ, DJFOO, DJG2S, EE8AX, ESK, ESX /, EWW, F84, FMRSC, GQD, KV2, KVW, L1V, L1VF8, MO6P, MO6Z, NNK /, NPB, PMKAE, PMKBE, PMKBF, RFNC1, RFNC2, RFNC3, RFNCA, RFNG1, RFNG2, RFNG3, RFNG4, RFNG5, RFNG6, RFNN1, RFNN2, RFNN3, RFNNA, RFNR1, RFNS1, RFNU1, RFNU2, RFNU3, RFNU4, RFNU5, RFNU6, SDM, SEA72, SEA92, SET, SJ63X, SR63X, TCJS6, TCJST, , TNEXX, TTP, UCDAZ, YYOAX, ZZZ

ORIGINAL DESCRIPTION: CenturyLink will be eliminating 330 billing USOCs across the 14 states.

These USOCs are:

13C1S, 18LA1, 18LSO, 1CP , 1FLPL, 1LFCK, 1LFOK, 1LFSK, 1M84X, 1M8OO, 1M8SX, 1M8WO, 24MAB, 24MBC, 255PC, 27EKT, 27ESX, 29F5J, 29O1J, 29O1R, 29OBJ, 2EGAB, 2EGO1, 2EH14, 2EH2O, 2EHAB, 2EHO1, 2EJA1, 2EJA2, 2EJAA, 2EJOO, 2HG , 2T3 , 38G , 38G28, 3KKVY, 43C , 45NF1, 48JA8, 48JO1, 48NAB, 48NDB, 48NDC, 4N9ST, 4OT , 4RC2A, 4TBXX, 4TGAB, 4TMG8, 4TMOO, 4TNAA, 4TNBA, 4TNNT, 4TNOC, 4TNSX, 4TO , 4TP , 59Y , 5LKSX, 8CJBT, 8QX28, 8QXKS, 96T , 96TAA, 96VAB, 96VO1, 96Y14, 96YAB, 96YDB, 96YO1, 96YSX, 98M35, 98MNI, 98MSC, A69SX, A6X , ACB , AMH , B1T , BECSK, BECSY, BFM , BMH , BOA , BP1AX, BP2AX, BZV , C16E6, C16V6, CBT99, CJD , CTY , CUDXX, CW1SX, CW9 , D2A2S, D56SX, D8D35, D8D81, D8DOT, D8DS1, D8DSX, D8FBX, D8FS1, D8FS3, D8FSX, DAZ17, DAZ25, DAZ33, DAZ99, DAZAA, DAZOO, DCMAA, DDX29, DGHOO, DGK , DGKAA, DGKST, DHSCC, DHSSX, DHSSZ, DJFOO, DJG2S, DJGA1, DJHO9, DL5SC, DLC25, DLC27, DLC49, DLCC4, DLCSX, DLJ18, DLJ23, DMVEX, DMZ , DNY2O, DP3OA, DQL99, DQLOO, DR5/R, DSDO1, DSEG8, DUXN4, E9B , ED7 , EE8AX, EJ9AX, ESCH3, ESK , ESN , ESX./, ETAXA, EWUS4, EWW , EXBJX, EXLCF, EXLCH, EXTSO, EZUC2, F84 , FMRSC, FO3NP, FVW5Q, FVW5Z, FVWKQ, G4888, GHA2O, GHB28, GHB2O, GQD , H2YFA, H2YFD, H3JT7, H5FDX, HOGO3, HOHTC, HOLPE, HOPTF, HOQ , HUJ , HUJSW, IN501, JK94P, JKHDR, JKHSX, JKWS4, JKWS6, JKWSB, JKWST, JKWSX, K1JXX, K59 , K5B2X, K5BST, K5BSX, K6HS6, K6HSX, KEMCB, KEMCM, KU2SK, KV2 , KVW , L1VF8, LPDXG, LPZXJ, LTG , LTTDA, LXP2X, LXP4X, LXPXX, MAW , MBZSC, MCL15, ME5 , MO6P , MO6Z , MPL , MPQSX, MRAGC, MWXSX, NDS , NF2WA, NF2WB, NF2WC, NF2WD, NNK /, NPB , NTF , NTFM4, NTFM6, NTFX3, P89.., PCHSG, PCHSN, PMKAE, PMKBE, PMKBF, PNXCH, PNXSX, PRMCU, PTZAP, PXBSY, QAS , RCTO6, RFNC1, RFNC2, RFNC3, RFNCA, RFNG1, RFNG2, RFNG3, RFNG4, RFNG5, RFNG6, RFNN1, RFNN2, RFNN3, RFNNA, RFNR1, RFNS1, RFNU1, RFNU2, RFNU3, RFNU4, RFNU5, RFNU6, RJCO2, RTCXN, RTCXQ, RTVXH, RX7SO, S4841, S4843, S4847, S4857, S4859, S4PST, S4PSZ, S7VS6, S7VST, SCL , SCT , SD7MS, SD7SC, SDM , SDM25, SDM2F, SEA72, SEA92, SET , SJ63X, SR63X, SV7 , SVM , T1YAZ, T3S , TAX , TAXS6, TAXSN, TCC , TCJS6, TCJST, TEEPN, TFA , TFASC, TFAST, TFSST, TFSSX, TL9AC, TL9AX, TL9AZ, TLAB1, TLAB3, TLAS1, TLAS2, TLAS3, TLASC, TLASG, TLASW, TNE2X, TNE4X, TNEXX, TTP , UCDAZ, VUMAA, W3PBJ, W3PBT, WUPSN, YYOAX, ZZZ.

3-16-12 Update: There are three customers that have the USOC MPL. The remainder of these USOCs do not have any customers.


Status History


Project Meetings

09/19/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the effective date for both CRs was 8/31/12 and that both are in CLEC Test and we would like to move them to Completed. There were no objections.

08/15/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the Level 4 final notices for both CRs are due 8/16/12 with a planned effective date of 8/31/12 for both.

07/18/2012 Monthly CMP Prod/Proc Meeting Mark Coyne - CenturyLink recapped the Change Request, stated that the title and description and been revised, and asked Lee Brummett to provide an update.

Lee Brummett – CenturyLink provided an update on these two CRs stating that the effective date of August 31, 2012.

Mark Coyne – CenturyLink stated that the Level 4 notice on these was scheduled for July 19, 2012.

Kim Isaacs – Integra asked if a clean list of USOCs would be included with the notice.

Susan Lorence – CenturyLink asked for clarification that the CLECs would rather see the list as depicted in the package or as a final list with only the affected USOCs listed.

Kim Isaacs – Integra asked for a clean list.

06/20/2012 Monthly CMP Prod/Proc Meeting Lee Brummett – CenturyLink provided an update on these two CRs stating that the final list of USOCs would be available for the July monthly meeting and that the Level 4 notice would be sent afterwards with an effective date of August 31, 2012.

Mark Coyne – CenturyLink asked if there were any questions. There were none.

05/16/12 Product Process Monthly Meeting Mark Coyne – CenturyLink relayed that a NOTE had been included on the list of USOCs on the second CR to clarify discussion from the prior monthly meeting and read the following Note: IF A USOC APPEARS IN THE DEFINITION COLUMN THAT IS DIFFERENT FROM THE USOC IN COLUMN 2, CENTURYLINK IS PROVIDING ABBREVIATED USOC AS A GENERAL REFERENCE. THIS IS NOT AN INDICATION THAT THE ABBREVIATED USOC IS BEING REMOVED. Mark said the SME team is continuing to review the list of USOCs and do not yet have an effective date. When we do have an actual date, the normal notification process will be followed. Mark asked if there were any questions. There were none.

4/18/12 Product Process Monthly Meeting Mark Coyne – CenturyLink advised that a list was included in the package. He relayed there were questions last month regarding the definitions and that the SME team has included an update in the package. Lee Brummett – CenturyLink added that the list is still being cleaned up and there is not a concrete date for the grandfathering or making the USOCs obsolete. If any changes are needed to any accounts, CenturyLink will work with the individual CLECs to make those changes. Kim Isaacs – Integra stated that they had concerns that there were USOCs on the list that were indicated as not found, yet were in PCATs. She said Integra has customers for some of these USOCs, for example, the ESX USOC, Call Waiting. Lee Brummett – CenturyLink clarified that the ESX USOC itself is not being removed, but rather those with additional characters such as “ESX /” and “NNK /”. The ESX and NNK USOCs would remain, but others such as the example given were being addressed and would be removed. Kim Isaacs – Integra noted that the list did include that ESX = Call Waiting next to “ESX /”. Mark Coyne – CenturyLink indicated that was to let the CLEC community know what service or feature the basic USOC described, but that the feature or service itself was not being eliminated. Bonnie Johnson – Integra asked if it could be assumed that if any CLEC had “ESX /” on a CSR, it would be changed to reflect “ESX”. Lee Brummett – CenturyLink stated that was correct. Susan Lorence – CenturyLink stated that in the future, CenturyLink would add a note to the USOC lists to clarify why the general USOC definition was included.

3/21/12 Product Process Monthly Meeting Lee Brummett – CenturyLink stated that CenturyLink will be eliminating 330 billing USOCs across the 14 states and that there were three customers that have the USOC MPL. That specific USOC will be replaced with another as soon as the replacement code is determined.

Kim Isaacs – Integra stated that the USOCs all had “definition unknown” but that there were familiar USOCs on the list: NDS, NNK, and some RTB USOCs. (4/2/12 Updates received from Integra in CAPS) KIM SAID SHE WAS SURE SOMEONE HAD CALLER ID.

Janean Van Dusen – CenturyLink stated that she wasn’t sure why the list stated that there was no definition except that in the look-up table it was not defined.

Bonnie Johnson – Integra confirmed that they looked familiar to her (4/2/12 Updates received from Integra in CAPS)AND CONFIRMED THAT ESX WAS CALL WAITING FOR ALL 14 STATES IN CL’S USOC FINDER.

Susan Lorence – CenturyLink stated that CenturyLink would work to get a revised list and include it with the meeting minutes if possible.

Mark Coyne – CenturyLink asked Lee if the date of elimination of these USOCs was undetermined.

Lee Brummett – CenturyLink said that was true.


Open Product/Process CR PC071312-1 Detail

 
Title: Elimination of Call Queuing
CR Number Current Status
Date
Area Impacted Products Impacted

PC071312-1 Completed
10/17/2012
Call Queuing
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is planning on eliminating the Call Queuing product. This product is available in all 14 states.

Call Queuing is an Advanced Intelligent Network (AIN) product that provides end-users with the ability to offer callers, who would normally reach a busy signal or voice mail, the opportunity to stay on the line (in queue) and have their call answered in person.

Customer documentation is available at http://www.centurylink.com/wholesale/clecs/features/callqueuing.html.

There are currently no Resale customers that have this product.


Status History


Project Meetings

10/17/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the effective date for the level 2 notice was 10/2/12. There were no (10/26/12 Updates received from Integra in CAPS) WHOLESALE customers. Mark said the CR is in CLEC Test and we would like to move the CR to Completed status.

There were no comments.

09/19/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR was presented in July. CenturyLink had proposed sending the customer notice as a level 2 since there were no customers and there were no objections. Mark relayed the tariff effective date for elimination is 10/1/12 but CenturyLink did not send the notice in time so the documentation update will be effective October 2, 2012. Mark relayed again there were no customers.

08/15/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the CR was presented last month. Because there were no customers, CenturyLink had proposed sending the customer notice as a level 2 and there were no objections. Mark relayed the planned effective date for elimination is 10/1/12 so the initial notice will go out early September.

07/18/12 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this was a walk-on item.

Lee Brummett – CenturyLink presented the CR and indicated that this product would be eliminated in all 14 States. There are no Resale customers with this product. The effective date for elimination is October 1, 2012.

Mark Coyne – CenturyLink asked if Lee was proposing a Level 2 request since there were no customers.

Lee Brummett – CenturyLink agreed.

Mark Coyne – CenturyLink asked if there were any objections from CLECs that this be presented as a Level 2 change. There were none.


Open Product/Process CR PC073112-1 Detail

 
Title: Retirement of MOE UNI Combinations – TLS to SPP and TLS to SMP
CR Number Current Status
Date
Area Impacted Products Impacted

PC073112-1 Completed
12/12/2012
Metro Ethernet
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Hansen, John

Description Of Change

08/15/12 REVISED Description

Eliminating combinations of EVCs and UNIs services as a result of Network changes, specifically the EVCs connecting a TLS UNI combined with Service Provider Ports (SPP) or TLS UNI combined with Service Multiplexer Ports (SMP). No Moves, Adds, or Changes on these existing service configurations. Repair will continue to operate business as usual.

Original Description of Change: Eliminating combinations of UNI services as a result of Network changes, specifically the TLS UNI combined with Service Provider Ports (SPP) or TLS UNI combined with Service Multiplexer Ports (SMP).


Status History


Project Meetings

12/12/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR had an effective date of 11/17/12 and that we would like to move the CR to a Completed status. There were no objections.

11/14/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the level 4 retirement notice was sent on 11/2/12 with an effective date of 11/17/12. There were no CLEC comments. A Technical Publication notice was sent on 11/02/12 also with an effective date of 11/17/12. Mark said CenturyLink would move the CR into CLEC Test on that date and would review the CR in December.

10/17/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the level 4 retirement notice was sent on 10/3/12 with an effective date of 11/17/12. A Technical Publication notice will be sent on 11/02/12 also with an effective date of 11/17/12. Mark relayed there are wholesale customers on this product.

09/19/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed this CR was presented last month and subsequently revised the same day. Mark said the CR was revised to include EVCs combinations and also included the following statement: No Moves, Adds, or Changes on these existing service configurations. Repair will continue to operate business as usual. Mark said there is also a revised effective date which will now be mid November 2012. There will be two notices that are distributed associated with this CR – a level 4 retirement notice and additionally a Technical Publication notice. Mark asked if there were any questions. There were none.

08/15/12 Product/Process CMP Meeting Lee Brummett – CenturyLink presented the CR. Lee said he will be revising this CR to include EVCs combinations. NOTE: CR WAS REVISED ON 8/15/12. REVISIONS ARE AVAILABLE AT http://www.centurylink.com/wholesale/cmp/cr/CRPC073112-1.html. The revision includes the following statement: No Moves, Adds, or Changes on these existing service configurations. Repair will continue to operate business as usual.

Kim Isaacs – Integra asked what “retirement” means. She asked if “retirement” means the current combinations can remain on an account. She asked how this impacts moves/add/changes and if a configuration exists and a change is required, will customers be required to remove the combination.

Lee Brummett – CenturyLink said yes, current combinations that exist today can remain on an account. He said he will need to verify what occurs if there are moves, adds or changes and provide that information later. He said what exists today can stay. Lee said the planned effective is October 15, 2012.

Kim Isaacs – Integra asked what the volumes are and what the business reason was for the change. Lee Brummett – CenturyLink said he did not know the volumes but that there are wholesale customers. Lee said the equipment is no longer supported for these combinations.

Mark Coyne – CenturyLink said we will then keep this as a level 4 notification.

Susan Lorence – CenturyLink asked if we can include the information in the meeting minutes as well as updating the CR. There were no objections.

Kim Isaacs – Integra asked if something happens to the equipment, will it be supported or require a change out.

Lee Brummett – CenturyLink said existing connections will be supported but that he will validate whether there was enough equipment if something happens to an existing combination. Mark Coyne – CenturyLink asked if there were any questions. There were none.


Open Product/Process CR PC090612-1 Detail

 
Title: Collocation Transfer of Responsibility Spreadsheet
CR Number Current Status
Date
Area Impacted Products Impacted

PC090612-1 Completed
12/12/2012
Collocation
Originator: Morlan, Sue
Originator Company Name: CenturyLink
Owner: Morlan, Sue
Director:
CR PM: Hansen, John

Description Of Change

Collocation - Transfer of Responsibility Spreadsheet. The Transfer of Responsibility Spreadsheet has been updated to include the following products: LSR Type Circuits, LIS Facilities and Trunks, and ACESS – Private Line Circuits.


Status History


Project Meetings

12/12/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR had an effective date of 11/5/12. There were questions in the November meeting and the CR was left open. Mark said we would like to move the CR to a Completed status. There were no objections.

11/14/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the level 4 final notice was sent on 10/19/12 with an effective date of 11/5/12. There were no CLEC comments. Mark said the CR is in CLEC Test and we would like to move the CR to Completed status.

Kim Isaacs – Integra said she would like to confirm that the only change on this CR was to combine the ASR and LSR products on the one spreadsheet.

Mark Coyne – CenturyLink said that is what he thought as well but we will confirm that with the originator.

Susan Lorence – CenturyLink asked if the response to Kim’s question could be included in the meeting minutes.

Kim Isaacs – Integra said yes. FOLLOW-UP NOTE: Sue Morlan – CenturyLink provided the following response after the CMP call. The only change that was made to the Transfer of Responsibility Spreadsheet was to add LIS Facilities and Access Private Line Circuits products to it. There were no other changes made to the process or products.

10/17/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the level 4 initial notice was sent on 9/20/12 and had a comment cycle that ended on 10/5/12. There were no CLEC comments. The final notice is due 10/19/12 with an effective date planned for 11/5/12.

09/19/12 Product/Process CMP Meeting Sue Morlan – CenturyLink presented the CR. She said the spreadsheet currently has one tab and that the CR is proposing that new tabs will be added for additional products, e.g., Private Line Circuits.

Kim Isaacs – Integra said per the CR description, the spreadsheet was also to include LIS Facilities and Trunks.

Sue Morlan – CenturyLink said the current spreadsheet is out of date.

Kim Isaacs – Integra said today (10/1/12 Updates received from Integra in CAPS) THE PROCESS IS TO [delete THEY] submit separate spreadsheets and asked if the new process is to put them all on the same spreadsheet.

Sue Morlan – CenturyLink said yes – all on the same spreadsheet is the intent which will make it easier. Sue asked if there were any other questions; there were none.

Mark Coyne – CenturyLink said the level 4 notice would be sent 9/20/12 with an 11/5/12 effective date.


Open Product/Process CR PC092712-1 Detail

 
Title: Discontinue Frame Relay Service Term plans
CR Number Current Status
Date
Area Impacted Products Impacted

PC092712-1 Withdrawn
1/16/2013
Resale
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will discontinue the offering of Frame Relay Service term plans that are longer than 12 months.


Status History


Project Meetings

1/16/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR was discussed last month. The CR had been placed in a Pending Withdrawal status and that CenturyLink would like to move it to Withdrawn. Mark asked if there were any additional questions. There were none.

12/12/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said that last month a question had been raised about a product resale notice. Mark relayed a reseller notice was sent on 11-15-12 to relay that at this time, CenturyLink no longer plans to discontinue the offering of FRS term plans that are longer than 12 months. Mark asked if there were any additional questions. There were none.

11/14/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the original plan was for CenturyLink to send the level 4 notice for this CR with a planned effective date of 11/17/12 but that the effective date is still being determined. There are wholesale customers so this will remain a level 4 notification.

Lee Brummett – CenturyLink said he had no further update on the effective date at this time.

Kim Isaacs – Integra said she thought a notice had been distributed on this product change with an effective date of 11/17/12.

Lee Brummett – CenturyLink said a reseller notice had been sent but that date had been changed.

Kim Isaacs – Integra said no notice had been sent and Integra was still under the assumption the change was to occur. Kim requested a follow-up notice be sent. Lee Brummett – CenturyLink said he would check.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.

FOLLOW-UP NOTE: A reseller notice was sent on 11-15-12 to relay that CenturyLink no longer plans to discontinue the offering of FRS term plans that are longer than 12 months at this time. See Notice number PROD.RESL.11.15.12.F.10696.MOEFR14States.

10/17/12 Product/Process CMP Meeting Lee Brummett - CenturyLink presented this new CR. Lee said that CenturyLink was initially looking at an effective date of Mid November but said that date may change. Mark Coyne - CenturyLink asked if there were any questions. He said there were wholesale customers so this would be issued as a level 4 notification.


Open Product/Process CR PC032613-1 Detail

 
Title: Eliminate Scan Alert USOCs in WA & OR
CR Number Current Status
Date
Area Impacted Products Impacted

PC032613-1 Completed
5/21/2014
Scan-Alert
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Hansen, John

Description Of Change

CenturyLink will be eliminating Scan Alert in WA & OR. CenturyLink will not offer a replacement product. The following USOCs will be eliminated: ASP, SNK, SEPSB, NR9SA, REAFO. The target implementation date is July 31, 2013.

6-12-13 UPDATE: The most current effective date for the withdrawal of Scan Alert is now AUGUST 31, 2013.

7-16-13 UPDATE: Effective August 31, 2013, Scan Alert will be grandfathered in the states of Oregon and Washington. Effective December 1, 2013 Scan Alert will be eliminated in the states of Oregon and Washington.


Status History


Project Meetings

5/21/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since August 31, 2013 when it was grandfathered in Washington and Oregon. The product was terminated as of April 30, 2014 and orders were written for any last remaining customers. Mark said we would like to move the CR to Completed status. He asked if there were any objections. There were none.

4/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. The Scan Alert product was grandfathered in Washington and Oregon effective last August 31, 2013. The product will be eliminated as of April 30, 2014. On April 21, 2014, CenturyLink will send a level 1 courtesy reminder notice that Scan alert will be terminated as of April 30, 2014.

3/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC Test. The product grandfathering effective date in Washington and Oregon was August 31, 2013 and the product will be eliminated as of April 30, 2014. CenturyLink pulled a list of remaining customers mid March. Any accounts with the product will be contacted by their Service Manager. CenturyLink will send a level 1 notice as a reminder that Scan Alert will be terminated April 30, 2014. Mark asked if there were any questions. There were none.

2/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC Test. The product grandfathering effective date in Washington and Oregon was August 31, 2013 and the product will be eliminated as of April 30, 2014. CenturyLink will be pulling a list of remaining customers in early March. CenturyLink will send a level 1 notice at the end of April as a reminder that Scan Alert will be terminated April 30, 2014. Mark asked if there were any questions. There were none.

Discussion following coverage of CR PC090413-1 Laurie Roberson – Integra asked if CenturyLink would be pulling another list of Scan Alert USOCs to see what remains. Laurie said she thought they had removed all of theirs but would like a checkpoint.

Susan Lorence – CenturyLink said CenturyLink plans to pull the Scan Alert list again in March and will send the results through Service Management.

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC test. CenturyLink will be pulling a customer list in March to see what customers still have the product. We will send a level 1 notice to customers toward the end of April as a reminder that Scan alert will be terminated as of April 30, 2014. Mark asked if there were any questions. There were none.

12/11/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC test. The planned effective date to grandfather the product in WA and OR was August 31, 2013 with a revised plan to eliminate the product now as of April 30, 2014. Notification of this revised date was sent in November. Mark said CenturyLink will send a level 1 notice to customers at the end of April to provide a reminder that Scan alert will be terminated as of April 30, 2014.

Kim Isaacs – Integra asked if CenturyLink will provide another report of customer accounts to see if any Scan alert USOCs remain. Kim said she thought Integra had addressed all of their accounts but would appreciate confirmation.

Mark Coyne – CenturyLink said CenturyLink will provide another list of any Scan alert USOCs that remain in the early March timeframe.

11/20/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the effective date for grandfathering was August 31, 2013 with the plan to eliminate the Scan alert product as of December 1, 2013. On November 15, 2013, a regulatory notice and a revised CMP final notification was also sent that extends the product elimination date for both Washington and Oregon until April 30, 2014. In regard to the Final notice for the Tech Pub 77333, Mark said that the final notice was also sent last Friday. CenturyLink is continuing with the removal of the Tech Pub 77333 as of December 1, 2013 since no new scan alert products could be ordered since August 31, 2013. Mark said CenturyLink will send a level 1 reminder notice to customers around the end of April to remind customers that Scan alert will be terminated as of April 30, 2014. Mark asked if there are any questions. There were none.

10/16/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the status for this Change Request is the same as last month. The CR is in CLEC Test. The effective date for grandfathering was August 31, 2013. CenturyLink will send a level 1 reminder notice to customers on November 27 to remind customers that Scan alert will be terminated as of December 1, 2013.

Laurie Roberson – Integra asked since December 1, 2013 is a Sunday, will the product stop working on Monday, December 2.

Lee Brummett - CenturyLink said he believes it is December 1. He said he would validate that and CenturyLink would include the information in the meeting minutes.

NOTE: Following the CMP call, Lee Brummett - CenturyLink confirmed that the product will not stop working on December 1. CenturyLink will begin writing the disconnect orders with a December 2 due date for any accounts that still have the Scan alert product.

09/18/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been moved to CLEC Test as of the planned effective date of August 31, 2013 for grandfathering Scan Alert in Washington and Oregon. Scan Alert will then be eliminated in these states as of December 1, 2013. Mark said a current list of impacted customers has been distributed by the service management team. Janean Van Dusen – CenturyLink confirmed that the list had been sent by Service mangers to impacted customers.

Kim Isaacs – Integra confirmed she had received the list.

Al Finnell – Windstream also confirmed the list had been received.

Mark Coyne – CenturyLink said a level 1notice would be sent on November 27 to remind customers that Scan alert will be terminated as of December 1.

08/21/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the planned effective date for grandfathering is August 31, 2013 and that Scan Alert will be eliminated in Washington and Oregon with an effective date of December 1,2013. Mark said CenturyLink will send a level 1 notice to customers on November 27 to remind customers that Scan alert will be terminated as of December 1.

Kim Isaacs – Integra asked whether CenturyLink Service Managers would send out a list of customers that still had the product and to insure that no new customers had added the product before the grandfather effective date as of August 31.

Mark Coyne – CenturyLink said we would follow-up to have another list sent out after the August 31 date.

07/17/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the planned effective date is August 31, 2013 however, CenturyLink now plans to grandfather services as of August 31 instead of terminating the service as of that date. Scan alert in Washington and Oregon will now be eliminated with an effective date of December 1, 2013. CenturyLink will send the initial Level 4 notice on July 19; the notice will indicate both the August 31 date to grandfather the product and the December 1 date to eliminate the product. Mark said CenturyLink will also send a level 1 notice to customers on November 27 to remind customers that Scan alert will be terminated as of December 1.

Kim Isaacs – Integra asked whether CenturyLink would continue to accept only disconnect orders as of August 31 and asked if the service would continue to work. She said retail flyers were sent in Washington that the service was going away and asked if additional notice will be sent.

Mark Coyne – CenturyLink said disconnect orders would continue to be accepted. He said we will check on whether another Washington notice will be sent and would include that information in the meeting minutes if possible. Mark asked if there were any other questions. There were none.

FOLLOW-UP NOTE: At this time, CenturyLink Retail does not plan on sending any additional update in Washington until possibly the November timeframe.

06/19/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the revised planned effective date is now August 31, 2013. The initial level 4 notice will be sent around July 17. Mark relayed a Resale notification was sent on April 23.

Kim Isaacs – Integra asked whether the resale notice will be updated with the new date.

Mark Coyne– CenturyLink said we typically do not renotice with the change in date. He said the resale notices include the statement “This is to advise you of changes to a CenturyLink retail service offering. Please be advised that retail offers that are subject to Commission approval may change. Resellers should monitor filings since CenturyLink will not provide notification of changes.”

05/15/13 Product/Process CMP Meeting Susan Lorence – CenturyLink said the CR was presented by Lee Brummett in April and that there had been quite a bit of discussion around the notification process and identification of impacted customers.

Lee Brummett – CenturyLink relayed that a Reseller notification had been sent on April 23. Lee also relayed that the list of impacted customers had been sent out on April 18 to Service Managers and that the effective date now appears as if it will be mid August vs. July 31.

Kim Isaacs – Integra asked whether the notice will be sent as a level 4 change.

Susan Lorence– CenturyLink said it would be a level 4 since there are customers.

Kim Isaacs – Integra asked why there was a change in the effective date.

Lee Brummett – CenturyLink said the change in effective date was due to CenturyLink system and order work that needed to be completed.

Kim Isaacs – Integra asked if the alarm companies have been notified. She asked if the retail side had contacted the alarm companies.

Lee Brummett – CenturyLink said Wholesale has not notified the alarm companies but the retail side had contacted them.

Susan Lorence– CenturyLink asked if there were any questions. There were none.

04/17/13 Product/Process CMP Meeting Lee Brummett – CenturyLink presented the new CR. Lee said there will not be a replacement product and there is a list of USOCs associated with this product elimination. The planned effective date is July 31, 2013.

Kim Isaacs - Integra asked the difference of the product being eliminated vs. grandfathered and asked if customers will actually be taken down.

Lee Brummett – CenturyLink said the product is being eliminated. Lee said customers can contact the existing alarm providers to request cellular back up.

Kim Isaacs - Integra identified that the timeline and logistics to make changes and to contact customers for this type of product was tight.

Curtis Ashton – CenturyLink asked if the scenario was that the CLEC buys alarm transport from CenturyLink.

Janean Van Dusen – CenturyLink said yes.

Curtis Ashton – CenturyLink said there was reference to using a cellular modem instead but said some more internal discussion needs to talk place as cell phones are currently not allowed in the Central Office.

Kim Isaacs - Integra said in this instance the service is provided to the end user and asked if the modem would be located at the end user location or the Central Office.

Lee Brummett – CenturyLink said he thought the equipment was at the end user site.

Kim Isaacs - Integra asked the number of wholesale customer that have this product. She thought Integra had some.

Janean Van Dusen – CenturyLink said there were less than 200 in Wholesale.

Nancy Taylor - Integra asked for the list of customers within each impacted company.

Mark Coyne – CenturyLink said there was approximately 90 days before the product was being eliminated and asked when the CMP notice would be distributed.

Susan Lorence – CenturyLink said the CMP Level 4 notice timeline for this is 45 days. We will get the list of impacted customers to each Service Manager so they can work with their customers. Susan said we may set up an ad hoc call to discuss the process.

Mark Coyne – CenturyLink said the notice would go out mid June.

Kim Isaacs - Integra said she was concerned if things did not get moved to wireless that alarms could go down. She said getting the list of accounts to start work with customers was important so the customer could then contact their alarm service. The alarm service then needs to take action which can all take time.

Janean Van Dusen – CenturyLink said the alarm companies on the retail side are being notified that this is coming and that the service has been failing for years. Janean relayed the vendor no longer provides equipment and there are no replacement parts.

Kim Isaacs - Integra said she agreed it has been failing for awhile but some customers are less savvy and may not have a good reason to change. The CLEC may not have a wireless service where they are.

Mark Coyne – CenturyLink said we would provide the list of customers and get an ad hoc call together if necessary.

Kim Isaacs - Integra said a 90 day notice was required and she was not comfortable to take systems off line causing security systems and alarms to fail.

Susan Lorence – CenturyLink said we have the concerns captured and if we have additional information or follow-up, we will provide that in the meeting minutes. The customer lists will be distributed through each Service Manager.

Kim Isaacs - Integra asked what the regulatory requirements were to notify customers and indicated that may be different per state.

Janean Van Dusen – CenturyLink said that is the reason for these Wholesale notices through CMP and that we are not notifying end users. [NOTE: The customer lists for this product have been provided to Service Managers to share with impacted companies.]

Kim Isaacs - Integra said if Integra has to notify their end users, a certain amount of advance notice is required especially if the service is eliminated. Kim said she was concerned current timing may not allow enough advance notice to occur.

Mark Coyne – CenturyLink asked if Kim was asking for someone from CenturyLink to investigate notification timelines.

Kim Isaacs - Integra said she will investigate date requirements but that the schedule must include the regulatory requirements.

Mark Coyne – CenturyLink asked if there were any questions. There were none.


Open Product/Process CR PC050113-1 Detail

 
Title: Eliminate Free DA Call Allowance in AZ
CR Number Current Status
Date
Area Impacted Products Impacted

PC050113-1 Completed
8/21/2013
Directory Assistance
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be eliminating the one free call allowance for Directory Assistance in Arizona. The planned effective date is Aug 1, 2013.


Status History


Project Meetings

8/21/13 Product/Process CMP Meeting Mark Coyne– CenturyLink relayed that the planned effective for this CR was August 1, 2013 and that the CR is in CLEC Test. No CLEC comments were received during the Comment cycle. Mark said we would like to move this CR to a Completed status. There were no objections.

7/17/13 Product/Process CMP Meeting Mark Coyne– CenturyLink relayed that this CR was presented in the May meeting. The Level 4 CMP notice was sent in June. No CLEC comments were received. The final notice will go out on July 17 with an effective date of August 1, 2013.

6/19/13 Product/Process CMP Meeting Mark Coyne– CenturyLink relayed that this CR was presented last month and that a Level 4 CMP notice will go out today, June 19, with an effective date of August 1, 2013.

5/15/13 Product/Process CMP Meeting Lee Brummett – CenturyLink presented this new CR which has an effective date of August 1, 2013.

Susan Lorence– CenturyLink relayed that this will be a level 4 CMP notice that will be sent mid June.


Open Product/Process CR PC073113-1 Detail

 
Title: Eliminate default to live operator feature for Intercept
CR Number Current Status
Date
Area Impacted Products Impacted

PC073113-1 Completed
2/18/2015
Resale Intercept
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be eliminating the default live operator functionality for Intercept Service in Iowa, Minnesota, Nebraska, North Dakota, and South Dakota. The intercept platform is manufacture discontinued and CenturyLink is upgrading to new technology. This live operator functionality was previously discontinued in the other legacy Qwest states when the intercept platform was upgraded in 4th quarter 2010.

Expected Deliverables/Proposed Implementation Date: These changes will be phased in by state/lata between late November 2013 through March 2014.


Status History


Project Meetings

2/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said CenturyLink had migrated the last state of Nebraska from the live operator feature as of February 13, 2015. Effective as of that same date, a Level 1 notification was sent to synch up documentation and remove the related wording in the PCAT. Mark said we would like to move this CR to a Completed status and asked if there were any objections. There were none.

1/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said the Migration for Iowa, North Dakota, South Dakota and Minnesota has been completed. Mark said the it was determined that the planned Nebraska migration end date was not going to be met so a time critical correction notice was sent January 20, 2015 to update the Nebraska Migration Completion date to be February 13, 2015. Mark asked if there were any questions. There were none.

12/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. Mark said the Migration for Iowa, North Dakota and South Dakota has been completed. Mark said the Minnesota migration dates to default to a live operator for Intercept were incorrect in our PCAT matrix and a notice was sent on December 12, 2014 to correct the Minnesota Migration Start Date to be December 4, 2014 and the Minnesota Migration Completion date to be January 6, 2015. In the November CMP monthly meeting, we relayed the SME team was looking at moving the state of Nebraska migration into 2014. That will not occur afterall. As indicated in the matrix, Nebraska will start on January 7, 2015 and end no later than January 23, 2015.

11/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. Mark said the Migration for Iowa and North Dakota has been completed and South Dakota is on track to complete December 3 or earlier. The date for Minnesota for the migration to be completed is December 10. Mark said the SME team has indicated that they may move the state of Nebraska up to 2015 from a January 7, 2014 start date. If that is the case, a notice will be forthcoming.

10/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013 and the status the same as last month. With the notice sent in August, some migration Start and Completion Dates were revised as well as the states of Minnesota and Nebraska were moved to be the last states to migrate. The list of specific migration dates are in the Intercept PCAT.

9/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013. A notice was sent on August 22, 2014 to revise the Migration Start Dates and Migration Completion Dates and change the order of the migrations moving Minnesota and Nebraska to the end.

8/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013. A notice was sent mid June to relay a delay of 90 days in the migration start dates. Mark said CenturyLink would be sending another Level 1 notice in the next few days to further revise the timeline for the Eastern states in the Intercept PCAT.

Kim Isaacs – Integra asked if the OS DA date delays are associated with problems in the CenturyLink IP platform.

Mark Coyne – CenturyLink said he could not answer that and that no SMEs were on the call but that we would include a response in the meeting minutes.

NOTE – CMP CALL FOLLOWUP: Per the CenturyLink SME team, the new CenturyLink OS/DA network, including the conversion to IP signaling, is very large and complicated due to the number of End offices involved and trunking requirements. The design, engineering and provisioning processes have taken somewhat longer than originally anticipated.

7/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013. A notice was sent June18, 2014 to relay that the migration start dates were pushed out by approximately 90 days. Mark said all eastern state timelines had been revised and the revised timeline is included in the Intercept PCAT. The examples of Iowa and South Dakota were provided that they would be completed October 9, 2014 and November 11, 2014 respectively. Mark asked if there were any questions. There were none.

6/18/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013. He said a notice had been sent to relay that the migration start dates have been pushed out by approximately 90 days and provided the example of Iowa which now has a migration Start Date of September 30, 2014. He said all eastern state timelines are being revised and the revised timeline will be included in the Intercept PCAT.

5/21/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink said the status is the same as last month. This CR has been in CLEC Test since December 2, 2013 and will remain there until October 20, 2014 when South Dakota completes migration. Mark said the first state to begin migration is Iowa which will begin on June 26, 2014. All eastern state timelines were revised and the revised timeline has been included n the Intercept PCAT. Mark asked if there were any questions. There were none.

4/16/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013. The CR has a new completion date of October 20, 2014. Mark said the migration for Iowa was to begin on March 17 but CenturyLink sent a notice in March relaying a delay to the migration start date for the five states. Iowa will now begin migration as of June 26, 2014. Mark said the state migration timelines were revised and has been included in the PCAT.

3/19/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR has been in CLEC Test since December 2, 2013 and will remain there until June 16, 2014. Mark said the migration for Iowa began March 17 and is expected to be completed April 11. The detailed dates for the other eastern states are in a table in the Intercept Services PCAT. CenturyLink will send a Level 1 notice to remove the “live operator” intercept language and the state implementation table from the PCAT when the last state has migrated.

2/19/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR will remain in CLEC Test until June 16, 2014 when the last state of South Dakota is migrated from the live operator feature. The detailed dates for the Eastern region state migration are included in a matrix in the Intercept Services PCAT. Mark said once the final implementation date is reached, CenturyLink will send a Level 1 notice to remove the “live operator” intercept language and the state implementation table from the PCAT.

1/15/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR has been in CLEC Test since December 2, 2013 and will remain there until June 16, 2014 when the last state of South Dakota is migrated from the live operator feature. The detailed dates for the Eastern region state migration are included in a matrix that is in the Intercept Services PCAT. Mark said once the final implementation date has passed, a Level 1 notice will be sent to remove the “live Operator” intercept language and the state implementation table from the PCAT.

12/13/2013 Product/Process CMP Meeting Mark Coyne – CenturyLink said the final notice was sent November 15 and the CR was moved to CLEC Test on December 2. The CR will stay in CLEC Test until June 16, 2014 when the last state of South Dakota is migrated from the “live operator” feature. Mark said that once South Dakota has migrated, a Level 1 notice will be sent to remove the “live operator” intercept language and the state implementation table from the PCAT.

11/20/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the Level 4 initial notice was submitted on October 17, 2013. It included the plan for staggered elimination dates for Intercept services default to a live operator on a state by state basis. Mark relayed the effective dates that were included in the initial notice began with Iowa effective December 2, 2013 and extended thru April 3, 2014 for the last state of South Dakota. The final notice was due last Friday, November 15 and it was sent with a revised matrix that relayed that the elimination dates have been postponed until a start date of March 17, 2014 for Iowa and ending in South Dakota effective June 16, 2014. Mark said the effective date of December 2 will remain for the Intercept Services PCAT. The PCAT is being updated to include the detailed list of revised effective dates on a state by state basis. Once the final implementation date has passed for the last state, a Level 1 notice will be sent to remove from the PCAT the “live Operator” intercept language and the state implementation table. Mark asked if there were any questions; there were none.

10/16/13 Product/Process CMP Meeting Lee Brummett – CenturyLink said the plan to implement this Change Request is to submit a level 4 notice that will include a Notice timeline that shows an effective date for the first state that the live operator feature will be eliminated. CenturyLink will also include a table in the PCAT that provides the phased implementation date by state. Lee said the effective dates range by state from early December 2013 through early April 2014. Once the final implementation date has passed for the last state, a Level 1 notice will be sent to remove the intercept language and the state implementation table from the PCAT.

Kim Isaacs – Integra asked if the implementation is a whole state at a time.

Lee Brummett – CenturyLink said yes.

Susan Lorence – CenturyLink said we will not send a CMP notice for each state but will send one notice that includes a matrix with the phased state implementation dates.

09/18/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month. Mark said one level 4 notice will be going out soon. The notice would include phased implementation dates by state/lata starting between late November 2013 ending through March 2014. He said the effective dates are still being determined.

Lee Brummett – CenturyLink said that was correct.

8/21/13 Product/Process CMP Meeting Lee Brummett – CenturyLink presented the new CR that eliminates the live operator feature in Nebraska, Minnesota, North Dakota, South Dakota and Iowa. Lee said this capability was eliminated in the other legacy Qwest states in late 2010. The CR would have a phased effective date by state/lata beginning in late November 2013 through March 2014.

Kim Isaacs – Integra asked for further information about the product elimination.

Lee Brummett – CenturyLink said the product is associated with the Intercept functionality when a phone has been disconnected. There will no longer be a live operator that will be available as the default option that explains the service has been disconnected. Mark Coyne– CenturyLink said this was only in the Eastern region and that it had been previously eliminated in the other states.


Open Product/Process CR PC090413-1 Detail

 
Title: Eliminate Business Complete a Call (BCAC)
CR Number Current Status
Date
Area Impacted Products Impacted

PC090413-1 Completed
3/19/2014
Resale
Originator: Brummett , Lee
Originator Company Name: CenturyLink
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be eliminating Business Complete a Call (BCAC). Due to enhancements in the Operator Services (OS)/Directory Assistance (DA) platform, the BCAC product will no longer be supported or available. BCAC is a service in Minnesota, New Mexico and Oregon where business pay a fee to allow customers to use directory assistance and complete the call to their business and not charge the customer for DA call completion. There are no substitute products available.


Status History


Project Meetings

3/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR has been in CLEC Test since December 15, 2013 when BCAC was eliminated in Oregon. The elimination date for Minnesota and New Mexico was February 28, 2014. CenturyLink sent a level 1 reminder notice with an effective date of February 28, 2014 to decommission the BCAC PCAT and remove references to BCAC from other documents. As of February 28, CenturyLink began writing orders to remove BCAC from accounts where it still existed and that effort has since been completed. Mark said we would like to move this CR to Completed status and asked if there were any objections. There were none.

2/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR will remain in CLEC Test until February 28, 2014 which is the effective date for Minnesota and New Mexico. BCAC was eliminated in Oregon as of the December 15, 2013. Mark said a level 1 reminder notice will be sent on February 27 with an effective date of February 28 to remove references to BCAC from the Resale Features Matrix and the Complete-A-Call documents. The BCAC document will be removed from the Wholesale web but a copy of the document will remain on the Document Review Archive site.

Susan Lorence – CenturyLink said this week the SME team pulled a list of the accounts that still have the BCAC feature and 10 remain in the two states. CenturyLink will issue orders after February 28 to remove the feature.

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is in CLEC Test as of December 15, 2013 and will remain there until February 28, 2014 which is the effective dates for Minnesota and New Mexico. Mark asked if there were any questions. There were none.

12/11/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR was presented in September to eliminate BCAC in Minnesota, New Mexico and Oregon. In the November meeting, Kim Isaacs - Integra asked about a tariff notice and whether one had been sent. Mark relayed Tariff notices had not previously been sent for this product elimination. The tariff notice for Oregon was then sent on November 25, 2013 with a December 15, 2013 effective date. The tariff notice for Minnesota and New Mexico was sent on November 27, 2013 with a February 28, 2014 effective date. The CMP final notice was sent on November 27 that included the two different effective dates for the three states. The CR will be moved to CLEC Test as of December 15, 2013.

11/20/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said CR was presented in September to eliminate BCAC in Minnesota, New Mexico and Oregon. The list of impacted customers was sent out through the Service Management team in Mid October.

Kim Isaacs - Integra said they had just received the list of impacted customers from their Service Manager and had to ask for the list. Kim asked if BCAC was a tariffed product. She said they had not received any tariff notices so the assumption is that this is not tariffed.

Lee Brummett – CenturyLink said he did not think they were tariffed

Susan Lorence – CenturyLink said we will investigate and include in the meeting minutes.

NOTE: Tariff notices had not previously been sent for these products. The tariff notice for Oregon was sent on November 25, 2013 with a December 15, 2013 effective date. The tariff notice for Minnesota and New Mexico was sent on November 27, 2013 with a February 28, 2014 effective date.

Kim Isaacs - Integra asked, similar to Scan Alert, what was the number of days required for a regulatory notification to eliminate the product. She said if the product is not tariffed, she assumed there was no regulatory lead time.

Mark Coyne – CenturyLink said we would include the information in the meeting minutes. Mark said the Final notice is due November 27 and will include the proposed effective date of December 15, 2013.

10/16/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said Lee Brummett presented this new Change Request in September to eliminate the Business Complete a Call service in Minnesota, New Mexico and Oregon. A level 4 notice will be sent the end of October to meet the proposed effective date of December 15, 2013. Mark said CenturyLink planned on sending out the lists of impacted customers through the Service Management team and asked if those had been received. Meeting participants indicated those lists had not been received.

Lee Brummett – CenturyLink said a new list had been created and will be sent through the Service Management team in the next several days.

Mark Coyne – CenturyLink asked if there were any questions; there were none.

09/18/13 Product/Process CMP Meeting Lee Brummett – CenturyLink presented this new CR to eliminate the BCAC service in Minnesota, New Mexico and Oregon. Lee said the proposed effective date is targeted for December 15, 2013.

Kim Isaacs – Integra asked if the feature is available to all customers and whether it is a USOC or FID.

Lee Brummett – CenturyLink said it is available for all in the identified three states. Lee said CenturyLink is pulling a list of wholesale customers.

Kim Isaacs – Integra said that was good that wholesale customers would receive a list of existing accounts.

Mark Coyne – CenturyLink said that since there are customers on this service, CenturyLink would send out a level 4 notification associated with the change.


Open Product/Process CR PC090413-2 Detail

 
Title: Change facility types for ordering of OS and DA services.
CR Number Current Status
Date
Area Impacted Products Impacted

PC090413-2 Completed
9/16/2015
Ordering Operator Services (OS) and Directory Assistance (DA) and Coin
Originator: Karstens, MIke
Originator Company Name: CenturyLink
Owner: Karstens, MIke
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink is planning on changing how Operator Services (OS) and Directory Assistance (DA) traffic is terminated in CenturyLink facilities. This will require customers to issue new orders for OS and/or DA services and busy line verify and busy line interrupt. As part of this change in facilities, Coin traffic will be separated into unique trunk groups. NOTE: Actual functional and system ordering requirements are not changing. New trunk orders will involve changing Z locations, combining of traffic and signaling types.

Expected migration is to begin as early as 1st quarter 2014 thus requiring customer order issuance beginning sometime late 4th quarter 2013.


Status History


Project Meetings

09/16/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. He said there are still a few CLEC customers that have not migrated despite CenturyLink’s continued efforts since second quarter to contact them to determine what their plans are. These remaining customers do not currently have OS, DA or COIN service under the previous MF trunking and will have to go through the “business as usual” process now instead of working with the CenturyLink Network migration team to establish service under the new platform. Mark said we are proposing that we move this CR to a Completed status and asked if there was any objection. There was none.

08/19/15 Product/Process CMP Meeting Susan Lorence – CenturyLink said this CR remains in CLEC Test but CenturyLink had a milestone to report. As of July 24, 2015, CenturyLink successfully completed the Operator Services (OS) and Directory Assistance (DA) and Coin network changes. There were a few customers that had not migrated prior to that date and our SME team is working with them. Susan said on July 24, CenturyLink sent a Product and Web notice to update the PCATs and Questionnaires to remove information that was temporarily placed in the documents to assist customers during the migration process. The final step is for customers to complete an update to the CLEC questionnaire to insure it matches their OS and DA offering. The CR will remain open for another month while we complete the transition for those few customers. Susan asked if there were any questions. There were none.

07/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. CenturyLink is in the final days of completing the OS and DA migrations. The SME team is working to contact any remaining customers to test and migrate them prior to the critical date of July 24, 2015. Mark said that as he indicated in the June meeting, a notification was sent in early June to remind customers that they will not have any OS, DA or COIN service if those customers have not migrated by 5 PM July 24. Mark asked if there were any questions. There were none.

6/17/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test and CenturyLink is in the last weeks of completing the OS and DA migration activities. The SME team is focusing on migrating all customers by July 24, 2015. In the CMP package, there is a copy of the Level 1 notification that was sent to remind companies of the July 24, 2015 date. Service Managers are continuing to contact customers regarding testing and migration activities. Mark said CenturyLink is requesting that customers have appropriate technical support available when migration calls are scheduled so the planned migration does not have to be rescheduled. The last step will be that customers update the CLEC questionnaire to match their OS and DA offering.

5/20/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test as CenturyLink is in the last months of completing the OS and DA migration activities. Mark said the SME team recently modified the CLEC and ILEC migration schedule to focus on the completion of Eastern migrations by May 29, 2015. The focus would then be on the Western states by June 24, 2015 and finally the Central region states by July 24, 2015. A Level 1 CMP product notification was sent late April to relay that revised schedule. Mark said since the team is focused on trying to work with each customer just once, customers that have services across regions may migrate sooner but all CLEC and ILEC traffic is expected to be migrated by July 24, 2015. Mark asked if there were any questions. There were none.

4/15/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. Mark said the CenturyLink SME team is continuing to monitor the service order schedule and planned migration date which is scheduled to be completed by May 21, 2015 but they believe there is a possibility that the CLEC and ILEC migration dates may slip by several weeks. He said we will share any updates as soon as we know. The service order issuance matrix from the PCATs is again in the CMP package for reference purposes.

3/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR continues to remain in CLEC Test. The revision to the Directory Assistance PCAT associated with the process change for requesting Directory Assistance Call Completion (DACC) became effective March 12. Mark said the Service order issuance matrix from the PCAT was again in the CMP package for reference purposes. Service managers have continued to contact customers regarding service order issuance. Planned customer service order issuance is occurring more slowly than expected. CenturyLink is continuing to monitor the project schedule. As of now, the planned migration dates appear to be on track with the expectation that it will be completed by May 21, 2015.

2/18/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR also remains in CLEC Test. Mark relayed Service managers have continued to contact customers according to the planned service order issuance schedule by state. For reference purposes, we have included the current Service order issuance matrix from the PCATs in the CMP package. Planned customer service order issuance is occurring albeit somewhat slower than expected. Mark said we are continuing to monitor the service order and planned migration schedules but as of now, we appear to be on track.

1/21/15 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. Based on a recent SME team review, CenturyLink sent a notification to revise the matrix to indicate a change in the planned migration start dates in some of states, specifically, the plan is to focus on the completion of the Eastern region migration dates first. There have also been some delays within CenturyLink due to migration complexity. Mark relayed the revised Service order issuance matrix from the PCATs is included in the CMP package for reference purposes. CenturyLink anticipates migration completion by May 21, 2015.

12/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR remains in CLEC Test. Service managers are continuing to work with customers as the Start Dates for Service Order Issuance for each state roll around. Mark said that next month we will include the SERVICE ORDER ISSUANCE TIMELINE matrix from the PCAT in the CMP package for reference purposes to allow us to more easily track the migration start dates for the remaining states each month going forward. Mark asked if there were any questions. There were none.

11/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink reminded call participants what this CR was associated with updates to the OS and DA PCAT that went into effect October 16. That PCAT update included dates for the Planned Network migration to begin. Mark said Service managers have been working with customers for awhile. The planned network migration for Iowa began on November 17, 2014 and is expected to complete mid December. Mark said North Dakota, South Dakota and Minnesota are to begin their network migration in early December. He also provided a reminder that as each state migration progresses, customers will need to disconnect the OS/DA MF trunks approximately thirty days from the migration start date. Mark said there is a download in the OS and DA PCATs that have the planned dates for each state.

10/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the final notices for the CLEC and Resale Customer Questionnaires and the OS and DA updates were sent in mid September and early October. The effective date for the update to the OS and DA PCAT is October 16 and it includes the begin dates for the Planned Network migration. Mark reminded call participants that this planned network change requires orders to be written to create new SS7 trunks and then to disconnect the OS/DA MF trunks. Service managers continue to work with customers based on each state timeline. All Traffic Migration is expected to be completed by May 21, 2015.

9/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said a final web notice for the customer questionnaire updates was sent on September 12 with an effective date of September 27. The OS and DA PCAT updates were sent on September 11 that included dates for the Planned Network migration to begin. Mark asked if there were any questions. There were none.

8/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said a web notice was sent on August 12 to relay updates are being made to the CLEC and Resale Customer Questionnaires associated with a change in process. The updates are to Sections OD.1 through OD.8 to incorporate changes in how customers order Operator Services (OS), Directory Assistance (DA) and Coin traffic. Mark said the notice also relayed updates to the Resale Questionnaire to add Section OD.1. Mark said the August 12 notification confirmed a response to Integra that had been asked in the prior meeting. CLECs will be required to complete and submit a new Questionnaire associated with the change from MF trunking to SS7 signaling.

Kim Isaacs – Integra asked if a customer was not using CenturyLink for OS or DA, would the customer still be required to update the Questionnaire?

BL Marcom - CenturyLink said he thought that the update would be relatively minor.

Kim Isaacs – Integra said there will be option then to indicate a customer was a facilities-based provider but not using CenturyLink. Mark Coyne – CenturyLink said the Customer Questionnaires will include effective dates on a state by state basis and the effective dates will be shared with the CMP final notification. He said the state effective dates will be approximately 30 to 60 days from the Proposed Finish date that is on the Service Order Issuance Timeline available in the OS or DA PCATs. Mark said service managers have begun working with customers for the state of Iowa and North Dakota on the orders that will be required to update their network.

Susan Lorence – CenturyLink said the sixty day lead time by state for the Service Manager customer contact was per customer request when the CR was initially reviewed.

Kim Isaacs – Integra asked how it was going to look on the Questionnaire with the state by state effective dates. Would customers be required to enter updates multiple times as each state is effective.

BL Marcom - CenturyLink said he thought that once a customer indicated they were not using CenturyLink, multiple updates would not be required. He said he would confirm if it matters if you enter for all states or by state.

Kim Isaacs – Integra that was good to confirm responses.

NOTE – CMP CALL FOLLOWUP: Per the CenturyLink SME team, with the Level 3 Customer Questionnaire final notification to be sent on September 11, 2014, a further revision will be made to the CenturyLink Questionnaire to add another high level checkbox - and related check boxes per state - to indicate if a customer that currently has OS/DA service wishes to disconnect their service with CenturyLink. If a current customer does check the “disconnect” box(es), they can disconnect by state if desired or they can disconnect all of their states at one time. At that point, no further action is required for this Section of the Questionnaire. It is up to the customer as long as they disconnect the trunks by the end of the migration. If customers are migrating, they should update the Questionnaire as their state(s) migrate to allow CenturyLink to have accurate information on a state by state basis. This update will be clarified as part of the final Level 3 CMP notification.

7/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC Test and that last month, Anne Trees – CenturyLink had provided a project status and had relayed there was a planned change in the state by state service order issuance dates. A notice was sent out on June 23 to relay the revised dates. Mark said to meet the 60 day lead time requested by customers during previous discussion related to this CR, Service managers will begin contacting customers for Iowa early August with the orders that are required. There are PCAT and CLEC Questionnaire updates required and Mark said the notice will be going out approximately the first week in August. Mark relayed that last month, Integra had asked whether new Questionnaires will be required for the revised sections for OS and DA and that Anne Trees had said she thought so but would know for sure in August.

6/18/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is currently in CLEC Test and the Process SME Anne Trees – CenturyLink is on the call to provide a project status.

Anne Trees - CenturyLink provided a recap of the purpose of the CR. She then relayed that due to unforeseen circumstances related to the Network build-out, there is a planned change in the start date by state for customers that require service orders to be written. Anne said a notice will be sent June 23 to relay there will be an approximate 60 day delay to that service order issuance timeline. Anne said as previously agreed upon, the CenturyLink Service Managers will be contacting customers approximately 60 days prior to the service order issuance start date in the timeline for each state with the required information. Anne said the Operator Services (OS) and Directory Assistance (DA) PCATs and the CLEC Questionnaire updates are in progress and will be sent approximately the first week of August.

Kim Isaacs – Integra asked whether customers would have to complete a CLEC Questionnaire update for the modified OS and DA sections or whether a customer’s current settings would be migrated.

Anne Trees - CenturyLink said she was still working through that with the IT team but that she believed customers would have to update the Questionnaire since the current content was for MF signalling and the network configuration and trunking would be different. Anne said CenturyLink would provide that update as to what needs to occur in August.

Mark Coyne – CenturyLink asked if there were any questions. There were none.

5/21/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is also currently in CLEC Test. On April 1, 2014, a notice was sent to revise the customer Service Order Issuance timeline for OS and DA services. The first state will be Iowa which has a planned start date for service order issuance of August 4. Mark said the CenturyLink SME Anne Trees will be on the call next month to provide a project status and to talk about the reports that will be sent to customers for the first states to require orders to be written. She will also talk about the CLEC Questionnaire updates. Mark asked if there were any questions. There were none.

4/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is also currently in CLEC Test. On April 1, 2014, a notice was sent to relay a delay of another 90 days to the customer Service Order Issuance timeline for OS and DA services. Mark said the first state of Iowa will now begin on August 4 with a proposed finish date of September 15. The updated timeline has been included in the impacted PCATs.

3/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR remains in CLEC Test. CenturyLink had sent a notice mid January to relay a delay in the network build out and that the Service Order Issuance timeline had been updated to reflect a 90 calendar day delay. Mark said the current schedule indicates Iowa customers will need to start writing orders in May but that we will have an updated status in the April CMP meeting.

2/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is currently in CLEC Test. CenturyLink sent a notice on January 21, 2014 to relay that due to unforeseen circumstances related to completing the network build out, all of the dates in the timeline for customer Service Order Issuance were delayed approximately 90 calendar days. Mark said that CenturyLink will send a notice during the second quarter to make related updates to the Customer Questionnaire and PCAT.

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is currently in CLEC Test. He said in December 2013, Anne Trees – CenturyLink provided a project update to review the status of the reports being sent to customers for the first states to require orders to be written. Mark said the CenturyLink network team is in the process of completing the network build out and that out SME team is monitoring that effort closely for any impacts to planned dates. Our SME team is planning on providing the planned migration dates per state in the February meeting. Mark said we are planning to update the PCAT with the Service Order Issuance Timeline dates but we are holding off a little bit longer so we can hopefully also include the planned migration dates. Mark asked if there were any questions. There were none.

12/11/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is currently in CLEC Test and said Anne Trees – CenturyLink Process would provide an update on the customer next steps.

Anne Trees – CenturyLink provided a brief update on the purpose of the CR and the customer impacts. Anne said the conversion is by state and that Service Managers will be contacting each impacted customer approximately 60 days prior to the planned order writing date. The Service Manager will verify a customer’s trunks, provide the new trunks and the new Z location for orders to be written to change from MF to SS7, and the dates for the orders. Anne said the first states are Iowa and North Dakota with five customers that will be contacted this week. Anne said even if a customer is located in multiple states, they will still convert on a state by state basis and then provided the approximate number of customers for each state. Anne said if a customer is an ILEC and CLEC, the ILEC Service Manager will also be contacting them with a different process for ILECs. After the Due Date, someone from either CenturyLink Service Management or Network will contact each customer to let them know when the traffic will be migrated and the date that the disconnect orders would need to be written. Anne said initial order writing will begin in February and go through approximately July and disconnect orders will go through the end of 2014.

Al Finnell – Windstream asked for a copy of the state by state timeline.

Anne Trees – CenturyLink said the timeline was originally provided in the notice.

Susan Lorence – CenturyLink said we would post the migration timeline in the PCAT so it is readily available there and send a copy of the migration timeline out.

Al Finnell – Windstream said that would help inform his contacts to let them know what is coming so they can better prepare.

Anne Trees – CenturyLink said a customer’s Service Manager will also have the timeline and can relay the schedule for each customer. Anne said we are also working on updating the PCAT and the customer questionnaire and those proposed updates should go out in late January for review.

Kim Isaacs – Integra said she understands the trunk Z Loc is changing to an IP switch. Kim asked if CenturyLink (12/20/13 Updates received from Integra in CAPS) [delete WAS] IS using THE IP SWITCH [delete THAT] for DA and asked when CenturyLink retail was migrating.

Anne Trees – CenturyLink said CenturyLink retail was following the same migration schedule and process as CLEC customers on a staged conversion beginning in Iowa.

Kim Isaacs – Integra asked what were CenturyLink plans if something did not work as planned and asked would the project timeline be pushed out if that should occur.

Anne Trees – CenturyLink said that is always possible but that the timeline between each state should be sufficient to accommodate addressing any problems. Anne also said the schedule was based on picking smaller states to begin the transition to allow issues to be resolved but if there was a bigger issue and it could not be corrected in time, CenturyLink would notify customers of any changes in the timeline.

Kim Isaacs – Integra asked if this change should be seamless to end users.

Anne Trees – CenturyLink said definitely.

Mark Coyne – CenturyLink asked if there were any questions. There were none.

11/20/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was reviewed in detail in the October CMP monthly meeting. CenturyLink sent the level 4 notice on October 21 to relay the planned changes to all CLEC and resale customers. The comment cycle ended November 5, 2013. No comments were received. The final notice was sent on November 15. Mark said included in that final notice was information that identified we have made some changes to the initially proposed migration dates. CenturyLink has made revisions to the Service Order Issuance Timeline to establish the new trunks. A document that includes those revisions has been posted to the Document Review Archive site associated with the initial notification. Mark said the main updates were to extend the migration periods for each state from a 22 day window to a 30 day window and to modify slightly the order of the state migrations. Mark also said updates to the CLEC questionnaire will occur as we get closer to the planned migration of traffic.

10/16/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this Change Request was presented in September associated with planned changes that CenturyLink will be making to our network/facilities associated with Operator Services (OS) and Directory Assistance (DA) services. A CMP notice was sent out on October 2 to relay that we would be discussing this Change Request in the October CMP monthly meeting. Mark proposed that since all customers are not impacted by this change that we wait to review this Change Request until we complete the regular Product/Process and System CMP meetings. Mark said we have several SMEs that are on the call to review this Change Request in more detail and that we will also review the Walk on from Integra associated with this Change Request at that time.

* NOTE: The following meeting minutes are a summary of discussion that occurred at the end of the System CMP meeting but are being included here associated with the OS DA Change Request.

Participants that were on this portion of the monthly call included representatives from Charter Communications, Iowa Network Services, Integra, Sprint, Popp, Valley Telecom Group, Comcast, and CenturyLink.

Mark Coyne – CenturyLink recapped that the Change Request was presented in the September CMP meeting by Ryan Blackman and pointed participants to where to locate the “white paper” in the Product Process CMP Distribution package that would be reviewed. Mark said following the document presentation, we would review the Walk on request from Integra associated with the Change Request.

Marty Cruze – CenturyLink began the more detailed discussion by asking participants to go to the Call Flow diagrams that were identified as Attachment B following the Change Request whitepaper. Marty said there was a Call Flow included for PMO (Present Method of Operation) and FMO (Future Method of Operation); he then walk through each of the Call Flows. When the Call Flow review was complete, Marty then went back to the beginning of the OS DA white paper and reviewed the content on a paragraph by paragraph basis. Marty said the Customer Existing Service Scenarios in the document relate to the possible service combinations and indicate what would be required from each customer as far as order writing for each of the nine scenarios. Marty said the process is basically the same to address each of the Service Scenarios. It is to create new SS7 trunks (for separate OS and DA trunks or combined trunks) and then to disconnect the OS/DA MF trunks. Marty asked if there were any questions about the various Service Scenarios.

Kim Isaacs – Integra asked a question about Coin and BLV/BLI and whether the Z loc would be changing.

Marty Cruze – CenturyLink said yes it probably would change. Marty said the orders would likely be written from the CLEC end office to the new Operator Services switch. The facilities will only go to the tandem but the trunk orders will go through to the operator switch location. Kim Isaacs – Integra asked how long the MF trunks would remain up related to the disconnect.

Marty Cruze – CenturyLink said the trunks would likely remain up approximately 30 days. Marty then reviewed Attachment A which is the Proposed Service Order Issuance Timeline. Marty said the order issuance timeline is not the same as the migration timeline. He said the idea is to get the trunks in and tested before migration begins. The migration would include customer traffic as well as CenturyLink traffic. Marty asked if there were any questions; there were none.

Janet Harper – Charter said the document appears to be thorough but said there would likely be questions as they get deeper involved.

Mark Coyne – CenturyLink said the best approach to deal with questions is for customers to send them to either the CMPComm@centurylink.com or the CMPCR@centurylink.com mailboxes.

Janet Harper – Charter asked when the BLV/BLI trunks will remain MF, will they have a different Z location.

Marty Cruze – CenturyLink confirmed that was correct. The Service Manager team will tell customers what the Z location will be.

Janet Harper – Charter asked how soon that information would be received and asked the type of interval which would be used.

Anne Trees – CenturyLink said we do not have an exact timeframe yet since it depends on what state a customer is in. Anne said she would be meeting with the Service Managers soon to provide them the specific CLEC information and then the Service Managers will be getting with each customer. Anne said the plan is to get information to customers at least 22 to 30 days prior to order issuances begins.

Janet Harper – Charter requested confirmation that customers would hear back at least 30 days prior to order issuance beginning.

Kim Isaacs – Integra requested the information sooner than that and asked if CenturyLink knew approximately how many ASRs would be required to be issued for each customer.

Anne Trees – CenturyLink asked what timeframe would work best and said she would then get with Service Management.

Kim Isaacs – Integra suggested that it would be good to get high level information, e.g., volume, about 60 days prior to ASR issuance, and then provide more detailed information 30 days prior.

Janet Harper – Charter said that would work well for them also.

Anne Trees – CenturyLink said that was good feedback and that she would try to work toward the 60 day lead time for high level info and then more details at a 30 day time period.

Susan Lorence - CenturyLink said there was some initial discussion that customers might not need to follow an exact timeframe by state and asked whether that was the case now.

Anne Trees – CenturyLink said she would need to look at that for each customer. She said orders for ILECs and Qwest end offices were being done at the same time which would make a difference. Anne said there is some flexibility but it could be an issue if orders are issued too early.

Diana Rasmussen – CenturyLink it could be and that would have to be looked at individually for each customer but would like to keep it at a 22 day interval.

Lori Burchett – CenturyLink asked if it made a difference if customers were going to make additional changes to their network.

Anne Trees – CenturyLink that would make a difference is changes are made. She said it really depends on the customer and their volume. Anne said meetings will continue with Service Managers in November and December to get them prepared. She said she would work toward the 60 day lead time but asked about CMP notification.

Susan Lorence - CenturyLink said now that the CR and information had been presented in this meeting, we still had to send the level 4 notice to all customers. She said there were no external documentation updates required so the planned approach was to post the whitepaper for review and follow the normal 45 day CMP notice timeline. Susan said we may need another ad hoc call if there were too many questions from customers who had not attending this call today. If the questions were more customer specific, Service managers could work directly with their customer. Susan the plan was to get the notice issued by early November with a mid December effective date. Susan suggested we could start the process sooner and send the level 4 notice earlier and get an effective date of early December. She asked if there were any issues with that. There were none.

Mark Coyne – CenturyLink asked if there were any other questions for the SME team on this. There were none. Mark asked if the Integra earlier question had been addressed.

Kim Isaacs – Integra said it had.

Mark Coyne – CenturyLink said we would then look at the ICA question that Integra had sent in as a Walk on for this Change Request. Mark said the first ICA section that was referenced, Section 7.2.2.9.5 7.2 in the Walk on document, indicates that OS ad DA trunking would rely on MF signaling but said if you look further at that section, it indicates that if SS7 options become available, parties would work toward that. Mark said the CenturyLink Contract and Legal believes that language covers this situation and that an amendment is not required. Mark said if customers felt an amendment was required, we would work with them on that. Mark asked if that addressed the Integra concern.

Kim Isaacs – Integra said she would take it back to her Contract and Legal team for further review.

Mark Coyne – CenturyLink asked if there were any other questions for the SME team on this. There were none.

09/18/13 Product/Process CMP Meeting Ryan Blackmun – CenturyLink presented this new CR for Mike Karstens. Ryan said there would be a CMP ad hoc call in the next couple weeks to address this CR and that following the call, service managers would work with impacted customers.

Kim Isaacs – Integra asked whether this was going to be considered an administrative change to change the Z Location and whether charges would apply.

Ryan Blackmun – CenturyLink said he did not know specifics for each company but he did not think there would be charges for this change.

Kim Isaacs – Integra said the prior CR (9/27/13 Updates received from Integra in CAPS) [PC090413-1 ELIMINATE BUSINESS COMPLETE A CALL] indicated CENTURYLINK WAS MAKING changes in the OS and DA platform and asked if that was why the Z location had to change.

Marty Cruze – CenturyLink confirmed this CR was due to changes in the CenturyLink platform to go to an IP architecture where it can. Marty said the Coin traffic was different because dumb payphones require special handling.

Kim Isaacs – Integra asked if (9/27/13 Updates received from Integra in CAPS) [delete AN] IP architecture was mandated for OS DA.

Marty Cruze – CenturyLink said IP is mandated for the platform that CenturyLink is moving to.

Kim Isaacs – Integra said if a customer had OS DA TDM traffic, it would change to IP.

Marty Cruze – CenturyLink said no, CenturyLink would change signaling to IP. Customers would change to go from MF signaling to SS7 for OS and DA.

Kim Isaacs – Integra confirmed for OS DA, the change was to SS7.

Marty Cruze – CenturyLink said Coin and BLV and BLI would remain on MF.

Kim Isaacs – Integra said she looked forward to the ad hoc call.

Mark Coyne – CenturyLink said the ad hoc call would take place in the next couple weeks.

Al Finnell – Windstream asked for clarification on when the call would actually take place.

Mark Coyne – CenturyLink explained CenturyLink was waiting to schedule the call based on whether we have a Face to Face CMP meeting in October.


Open Product/Process CR PC101413-1 Detail

 
Title: Change to NG911 Trunks Standard Interval
CR Number Current Status
Date
Area Impacted Products Impacted

PC101413-1 Completed
1/15/2014
Ordering NG911
Originator: Carroll, Jim
Originator Company Name: CenturyLink
Owner: Carroll, Jim
Director:
CR PM: Lorence, Susan

Description Of Change

CenturyLink will be lengthening the Next Generation (NG) 911 Trunk Standard Interval for provisioning from the standard 12-business day Due Date to a 22 business day Due Date. This will allow the appropriate timeline for complex translations to occur.

Expected Deliverables/Proposed Implementation Date

Mid December 2013 or earlier


Status History


Project Meetings

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR is currently in CLEC Test as of December 16, 2013. On that date, the interval due date of 22 business days became effective due to the increased complexity of turning up the NG911 circuits. Mark said we would like to move this CR to a Completed status and asked if there were any objections. There were none.

12/11/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said when the CR was presented in October, CenturyLink requested that we send a level 2 notification vs. a level 4 notification. The level 2 notice to change the current interval due date to a longer due date interval of 22 business days was sent on November 25 with an effective date of December 16. Mark said on December 16 we will move the CR to CLEC Test.

11/20/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented last month associated with Next Gen 911 Trunk FOC Coordination. Jim Carroll, CenturyLink, had provided some background indicating that CenturyLink is replacing the current 911 network infrastructure with an IP based network and that it is a multi stage process that includes considerable complexity to turn the circuits up. This CR includes plans to change the current interval due date which is a standard 12-business days to a longer due date interval of 22 business days. Mark relayed that the planned effective date for the new Due date interval is mid December so we will be sending out the level 2 notice soon.

10/16/13 Product/Process CMP Meeting Next Gen 911 Trunk FOC Coordination and CenturyLink Walk On Change Request PC101413-1 - Change to NG911 Trunks Standard Interval Mark Coyne – CenturyLink reviewed the walk on request from Integra.

Jim Carroll – CenturyLink said the approach with Next Generation (NG) 911 is to replace the current network infrastructure with an IP based network. Jim said it is a multi stage process. The current stage is for carriers to move to new routers which go by a variety of terms for these emergency gateways. Jim said that the complexity to turn the circuits up has grown significantly. Because of this, Jim said he issued the Walk on CMP Change Request to extend the Due Date to account for the extra work that is required. Jim then presented the new CenturyLink Change Request PC101413-1 which extends the current due date of a standard 12-business day Due Date to a 22 business day Due Date.

Kim Isaacs – Integra said Thank you and requested a place holder for the OS DA Change Request to see if the trunking orders may be impacted similarly.

Mark Coyne – CenturyLink said that CenturyLink would like to propose that the Change Request be implemented on a level 2 21 day timeline vs. the normal timeline for this type of change which would be 45 days. Mark asked if there were any objections. There were none.

David Garland – Iowa Network Services asked if the new Change Request was limited to specific states and whether it would impact Iowa.

Jim Carroll – CenturyLink said the Change Request is not limited to specific states but to where the Emergency services trunks are migrating to the CenturyLink NG platform. Jim said in Iowa there is an interesting layering but this change only applies when CenturyLink migrates away from legacy analog for wireline in Iowa. Jim said it does impact activity associated with TCS which is a layer.

Mark Coyne – CenturyLink asked if there were any other questions. There were none.


Open Product/Process CR PC111413-1 Detail

 
Title: Remove Tech Pub 77354 Guidelines for Product Change Notices
CR Number Current Status
Date
Area Impacted Products Impacted

PC111413-1 Completed
2/19/2014
Documentation - Technical Publications
Originator: Brown, JB
Originator Company Name: CenturyLink
Owner: Brown, JB
Director:
CR PM: Lorence, Susan

Description Of Change

Remove Tech Pub 77354 from the CenturyLink external website as it is obsolete. CenturyLink is utilizing the Telcordia Document GR 209 in place of this Tech Pub.

Expected Deliverables/Proposed Implementation Date: January 2014


Status History


Project Meetings

2/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said there had been a question last month about the initial level 4 notice for this CR that was answered as part of the meeting minutes. This CR was moved to CLEC Test on January 24, 2014. As of that date, the obsolete Tech Pub 77354 was removed from the CenturyLink website. Mark said CenturyLink would like to move this CR to Completed status. There were no objections.

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is associated with removing the obsolete Technical Publication 77354 from the CenturyLink external website. CenturyLink is utilizing the Telcordia Document GR 209 in place of this Tech Pub. Mark said the planned effective date is January 24, 2014 and we will move the CR to CLEC Test at that time.

Kim Isaacs - Integra said there was a problem on the initial notice and somehow Integra did not receive a copy of it. Kim said she had reviewed the Document Review site when she received the Final notice and wanted to confirm that this Tech Pub is for suppliers of telecommunications to Legacy Qwest and not for purchasing services from Legacy Qwest.

Susan Lorence – CenturyLink said we would need to follow-up on this and get back with Kim since the CR originator was not on the call. She said we would investigate and include the information in the meeting minutes and also a separate email.

Kim Isaacs - Integra said that was fine. Kim asked if there were any other CLECs that had not received the initial notice.

Randee Ryan – Comcast said she did not specifically remember the notice.

Susan Lorence – CenturyLink said this is the first she has heard of a problem and would look into the problem further. Susan said if this was a big concern, we could extend the effective date to remove the Tech Pub from the website.

Kim Isaacs - Integra said she reviewed the Tech Pub and that she thought it was for companies supplying Legacy Qwest with equipment. She said if CenturyLink can confirm that, she did not think a delay to removing the Tech Pub was necessary.

Susan Lorence – CenturyLink she would investigate that and get back as soon as possible. Susan said she would send an email to all customers on the CMP call to provide that information.

Mark Coyne – CenturyLink asked if there were any other customers that might have a problem with removing the Tech Pub as of January 24, 2014.

Al Finnell – Windstream said that it was fine with him if in the email, we confirmed the purpose was not for CLEC/Resellers.

Frank Behnke - ATT said that was fine also.

NOTE: The following email was sent on January 21, 2014 to CLECs participating in the CMP January call with an explanation as to what occurred with the “mailout” of the initial notice and next steps in regard to this CR.

This is a follow-up from the January 15, 2014 CMP Product Process monthly meeting in regard to CR PC111413-1, Remove Tech Pub 77354 - Guidelines for Product Change Notices.

Kim Isaacs – Integra identified on the call that she had not received the initial Level 4 notice in conjunction with this CR PC111413-1. (That initial notice that was sent December 13, 2013 is attached.) Upon further investigation, it has been determined that the notice was inadvertently distributed to Legacy CenturyLink CLECs rather than Legacy Qwest CLECs. We apologize for that error. That explains why no one from Integra or Comcast -- nor any Legacy Qwest CLEC -- received the initial notice. However Legacy Qwest CLECs did receive the final Level 4 notice that was sent on January 9, 2014 associated with this change. (That notice is also attached.) NOTE: Legacy Qwest Resellers did receive the initial and the final notice.

With that said, I checked with the CR originator JB Brown and JB confirmed that this Tech Pub 77354 is not for services purchased from legacy Qwest. The Tech Pub is associated with the process to maintain “goods”, i.e., Equipment and Software. It outlines the requirements and agreements between legacy Qwest and our Suppliers for maintaining those products that have been purchased. As stated in the CR, CenturyLink is currently utilizing the Telcordia Document GR 209 (Issue 6) in place of this obsolete Tech Pub.

With that response from JB, it confirms the point made by Kim Isaacs during the monthly call that this Tech Pub 77354 is for suppliers of telecommunications TO Legacy Qwest and not for purchasing services FROM Legacy Qwest.

Based on that point, we believe that those on the January call agreed that we could move forward with removing the Tech Pub 77354 from the Centurylink Tech Pub site.

If that is NOT the case and anyone believes that we need to HOLD on retiring the Tech Pub 77354, please let me know before January 24, 2014.

12/11/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said this was a walk on CR last month associated with plans to remove Tech Pub 77354 from the CenturyLink external website. Mark said CenturyLink will be sending the level 4 notice on December 13, 2013 with the expected implementation date of January 24, 2014. Mark asked if there were any questions. There were none.

11/20/13 Product/Process CMP Meeting JB Brown – CenturyLink presented this new walk on CR to remove an old USWest Tech Pub 77354 from the CenturyLink external website. Jim said in 2011, CenturyLink purchased Telcordia Document GR 209 which replaces this Tech Pub.

Mark Coyne – CenturyLink said CenturyLink will send a level 4 - 45 day CMP notice before the end of the month to meet a proposed implementation date of January 2014. Mark asked if there were any questions. There were none.


Open Product/Process CR PC010907-1 Detail

 
Title: Changes To Scheduled Customer Due Dates
CR Number Current Status
Date
Area Impacted Products Impacted

PC010907-1 Denied
3/21/2007
Ordering LNP
Originator: Kagele, Tim
Originator Company Name: Comcast
Owner: Heiland, Venessa
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

To implement a process enhancement that allows a CLEC to change (sup order) the customer’s scheduled due from the current scheduled date to the next day for simple porting of customer telephone numbers when the end customer is unable to be home on scheduled date, rather than wait the standard 4 business day interval to reschedule the port.

Comcast believes the requested process change is technically feasible for the following reasons: 1) Qwest’s current porting process retains the customer’s telephone number in the switch for up to 48 hours after the 10 digit trigger is placed on the line, 2) NPAC subscription has already been created and concurred - no additional work would be needed by either party, and 3) CLEC would be obligated to send an order supplement through normal channels to change the scheduled DD to the next day thereby keeping ordering and billing records correct.

Expected Deliverable:

To Be Discussed


Status History

01/09/2007 - CR Submitted

01/09/2007 - CR Acknowledged

01/09/2007 - Customer Contacted For Clarification Meeting Availability


Project Meetings

March 21, 2007 Product Process CMP Meeting: Mike Whaley-Qwest stated that Qwest received this request, from Comcast, and has internally reviewed it. Mike stated that Qwest’s processes are based on the standard LNP working group meetings and the OBF ATIS National Forums. Mike noted that this change would only be for 1 company and Qwest interfaces with many companies. Mike then stated that Comcast also expressed that they would also need to make system changes on their side for this request and agreed that the request would only impact their company. Mike stated that this request is denied due to no reasonable or demonstrable business benefit. Mark Coyne-Qwest asked if there were any questions or comments. There were none. This CR is Closed in Denied Status.

February 21, 2007 Product Process CMP Meeting: Tim Kagele-Comcast presented the CR and stated that the Industry Process is that when a CLEC schedules a port, the interval is 4-days and noted that Comcast has issues when the customer cannot be home at the time of the appointment. Tim stated that Qwests current process is to leave the number in the switch up to 48-hours. Tim stated that Comcast would like the process revised for a next day assurance on a supp. Tim noted that he Comcast wants an FOC on a 1-day due date change, instead of waiting for the standard 4-day norm. Tim noted that a discussion with the CLECs has occurred. Mark Coyne-Qwest asked if there were any questions regarding this request. There were none brought forward. Mark Coyne-Qwest stated that Qwest will review and evaluate the request and would provide the response in March.

-- January 17, 2007 Clarification Meeting Attendees: Kim Isaacs-Eschelon, Steph Prull-Eschelon, Tim Kagele-Comcast, Peggy Esquibel Reed-Qwest, Venessa Heiland-Qwest, Denise Martinez-Qwest, Jamal Boudhaouia-Qwest, Vicki Dryden-Qwest, Connee Moffatt-Qwest, Anne Pent-Qwest, Cindy Buckmaster-Qwest Review Requested (Description of) Change: Peggy Esquibel Reed-Qwest reviewed the CR, and asked to confirm that this request is for LNP. Tim Kagele-Comcast said yes. Peggy Esquibel Reed Then asked if there was any additional information to share. Tim Kagele-Comcast stated that this request is for when they have a customer who is unable to be home on the scheduled due date and may need to reschedule the appointment for the following day or for the next day. Tim stated that the Industry is a 4-day process and he is requesting a process change for a next day supp. Tim then noted that the last data that he received from Qwest indicated that 10-11% of Comcast’s volume would benefit from this change. Venessa Heiland-Qwest asked if Comcast calls their customers a day ahead of the appointment to confirm the appointment with the end user. Tim Kagele-Comcast stated that they usually do in order to make sure that the time has not changed for the end user. Venessa Heiland-Qwest stated that of that 10%, two-thirds of them are due date changes and late notifications, to Qwest, on or after the due date of the Qwest order. Venessa then noted that Qwest is notified during the 48-hour interval and that it causes problems for Qwest. Venessa stated that if the LSR due date is today and it falls into that 10% category, Qwest would receive a due date change of the next day or the next day, on two-thirds of the LSRs. Tim Kagele-Comcast asked if Venessa was saying that Comcast is currently following up with a supp to change the due date. Venessa Heiland-Qwest said yes. Tim Kagele-Comcast noted that was the current process. Venessa Heiland-Qwest stated that a concern for Qwest is that the orders would not flow through and would be handled manually. Tim Kagele-Comcast asked if then the interval would be re-FOC’d. Venessa Heiland-Qwest said correct and if the request (LSR) was sent 24-hours later it would result in a missed FOC. Tim Kagele-Comcast stated that was because it is live in the switch and they would then send a supp. Venessa Heiland-Qwest noted that is why the timer starts over. Anne Pent-Qwest asked if Comcast could notify Qwest earlier, if that would help. Venessa Heiland-Qwest stated that it would help considerably. Tim Kagele-Comcast stated that Comcast could adjust their process to notify in advance but is looking for flexibility in the process. Peggy Esquibel Reed-Qwest asked if there were any additional questions or comments. Tim Kagele-Comcast stated that this request should not impact any other CLECs ordering processing. Steph Prull-Eschelon asked Tim if Comcast was sending the supp after the Qwest order due date and asked how they are sending orders, if via EDI or GUI. Tim Kagele-Comcast said they send 95% of their orders via EDI. There were no additional questions or comments regarding the request. Peggy Esquibel Reed-Qwest stated that this CR would be scheduled for presentation at the February 21, 2007 CMP Meeting and noted that the Qwest Response would be provided around March 13, 2007.


CenturyLink Response

Qwest Response

March 7, 2007

To: Tim Kagele, Comcast

CC: Venessa Heiland, Qwest LNP process manager Peggy Esquibel-Reed, Qwest Change Management This letter is in response to CLEC Change Request number PC010907-1 'Changes To Scheduled Customer Due Dates' with regard to Local Number Portability.

CR Description: To implement a process enhancement that allows a CLEC to change (sup order) the customer’s scheduled due from the current scheduled date to the next day for simple porting of customer telephone numbers when the end customer is unable to be home on scheduled date, rather than wait the standard 4 business day interval to reschedule the port.

Expected Deliverable: Comcast requests modification of current flow through processes and systems. This includes changes to permit order supplements to be sent through normal channels to change the scheduled due date to the next day to keep ordering and billing records correct.

History: Qwest held a clarification meeting on January 17, 2007, with Comcast and other members of the CLEC Community.

Qwest Response: Qwest has completed an analysis for PC010907-1 and has determined that a change as proposed does not provide a reasonable demonstrable business benefit.

Qwest’s LNP sup intervals are compliant with the industry recommended standards. Qwest does not implement changes to accommodate requests that are not consistent with industry standards. Qwest’s policy is to adhere to industry standards. Therefore, Qwest respectfully denies your request for CR PC010907-1 'Changes To Scheduled Customer Due Dates'

Sincerely, Qwest Corporation


Open Product/Process CR PC010705-1 Detail

 
Title: Reduce the Interval Time Required for a 'simple' Port
CR Number Current Status
Date
Area Impacted Products Impacted

PC010705-1 Denied
3/16/2005
Ordering LNP
Originator: Law, Rachel
Originator Company Name: Comcast
Owner: Rein, Kathy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Reduction in business day interval from three business days to one business day for a simply residential one line account. Comcast request would be for a resident 'CB' REQTYP 'Z' ACT


Status History

01-07-2005 - CR Submitted

01-10-2005 - CR Acknowledged

01-10-2005 - Email Sent to Linda Minasola, Comcast, Requesting Clarification Meeting Availability.

01-11-2005 - Email Received from Comcast, with Meeting Availability

01-11-2005 - Clarification Meeting Scheduled for January 17, 2005

01-17-2005 - Clarification Meeting Will be Rescheduled.

02/16/2005 - Discussed in the February Product Process Monthly CMP Meeting

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting


Project Meetings

April 27, 2005 Email Sent to Liz Balvin, Covad: Liz, This email is to provide you with information that you requested from Jill Martain. Comcast is aware of the denial and had no comments or questions. In response to your questions regarding PC010705-1 Reduce the Interval Time Required for a ‘simple’ Port: Q: How are work-back orders handled today? A: How work backs are handled is defined in the LNP PCAT-the issue is not how work backs are handled but the fact that Qwest believes the shortened interval will increase the number of work backs and the risk of the end user customer being out of service.

Q: How would the trigger setting be affected? A: Triggers must be set by 11:59PM the day before the port. With a 3 day interval it gives Qwest 2 days to correct issues and problems that may occur on a port request, to comply with the 11:59PM deadline. With a 1 day interval, Qwest would only a have few hours to detect problems and correct them and trigger intervals would be missed. Having the 10 digit trigger set allows calls to properly route to the CLEC’s switch when to port is activated.

April 21, 2005 Email Received from Liz Balvin, Covad: Jill, Here are the questions I had regarding last months CMP meeting minutes: Comment: Was the initiator (Comcast) present during this readout? Please provide more details. How are work back orders handled today? How would the trigger setting be affected? Thanks in advance for your help, Liz Balvin Covad Communications

- March 16, 2005 Product Process CMP Meeting Discussion: Kathy Rein-Qwest stated that the requested change to the due date interval purposes a risk to Qwest and to the end user customer. Kathy noted that with the current interval, there are work back orders that need to be done and a shortening of the interval would increase the number of the work back orders. Kathy also stated that a shortening of the intervals would affect the triggers and it would not allow sufficient time to correct errors or detect issues. Kathy stated that Qwest is respectfully denying this request for no demonstrable business benefit and asked for questions or comments. None were brought forward. Jill Martain-Qwest stated that this CR would be closed in Denied Status.

-- February 16, 2005 Product Process CMP Meeting Discussion: Nancy Sanders -Comcast presented the CR. Liz Balvin-Covad asked if this was for a 10-digit trigger. Nancy Sanders-Comcast stated yes and noted that this request was for 1-line only. Jill Martain-Qwest stated that this CR would move to Presented status.

January 27, 2005 Clarification Meeting Minutes: ATTENDEES: Linda Minasola-Comcast, Amanda Silva-VCI, Peggy Esquibel Reed-Qwest, Kathy Rein-Qwest, Russ Urevig-Qwest Peggy Esquibel Reed-Qwest reviewed the CRs Description and asked Comcast if there was additional information. Linda Minasola-Comcast stated that this request is for ACT=Z, as is. Linda then stated that the title should be 'simple', not 'simply'. Peggy agreed to make the correction for Comcast. Kathy Rein-Qwest asked if this request was for a POTS Type residential End User. Linda Minasola-Comcast stated yes, via EDI and GUI. Kathy Rein-Qwest asked if Comcast was requesting the same work back availability with a 1-day port. Linda Minasola-Comcast stated yes, it would follow the same current procedure. Russ Urevig-Qwest asked if Comcast if the request would not come through IIS if cannot sunmit via IMA. Linda Minasola-Comcast stated that this would not be for a manual order, at all. Amanda Silva-VCI asked to confirm that ACT=Z was for porting. Kathy Rein-Qwest stated that Z or V or for porting. Linda Minasola-Comcast stated that ACT=Z is for a cutover with 1 order porting to 1 single line, 1 TN only. Order is to port as is with no directory listing change and a 1-day turnaround. Linda stated that this request is for 1 new line, no additions, no sharing, 1 TN only and is very clean and simple. Russ Urevig-Qwest asked if the request included if there was 1 TN moving off of an account. Linda Minasola-Comcast stated is 1 account, 1 conversion only with no back-end needed for managing the account. There were no additional questions or comments. Peggy Esquibel Reed-Qwest stated that this CR is scheduled for presentation, by Comcast, at the February CMP Meeting.

January 20, 2005 Email Sent to Comcast: Good Morning Linda, I have scheduled the Clarification Call to occur as follows: DATE: Thursday, January 27, 2005 TIME: 11:00 a.m. MT CALL IN: 1-877-564-8688, conference id 8571927# Thank you, Peggy Esquibel-Reed Qwest CMP CRPM

January 20, 2005 Email Received from Comcast: Peggy I am available Monday 24th @1100 AM, Thursday 27th @ 1100 AM. Kerri Burke on our team would also be available for Monday 24th after 1:00 PM to the end of day. Linda

- January 19, 2005 Email Sent to Comcast: Linda, Unfortunately the proposed date/time, below, did not work as it is the date/time of the monthly Qwest/CLEC CMP Meeting. A Clarification Call is really required in order for Qwest and the CLEC Community to ask clarifying questions regarding your submitted request. Questions on the call and the responses to those questions sometimes do prompt other questions. Open dialogue is critical. Can someone attend, for Comcast, on your behalf that will be able to answer questions? Or, can you tell me when you will be available for a call? Thank you, Peggy Esquibel-Reed Qwest CMP

- January 18, 2005 Email Received from Comcast: Peggy I am sorry I was not available for this call yesterday. Is it possible to send me question or concerns you might have in reference to Comcast's CR proposal? I do have from 9-11 open Wednesday, January 19. I will be behind close doors after Wednesday working on a project! Linda LindaMinasola@cable.comcast.com

January 17, 2005 Email Sent to Comcast: Linda, We missed you on the call today. Please advise me of your availability, several options would be great, and I will reschedule the Clarification Call. Thank you, Peggy Esquibel-Reed Qwest CMP CRPM

January 12, 2005 Email Received from Comcast: Peggy Thank you, I have updated my calendar for this meeting. Linda

January 11, 2005 Email Sent to Comcast: Good Morning, I have scheduled the Clarification Call for PC010705-1 to take place as follows: DATE: Monday, January 17, 2005 TIME: 3:00 p.m. MT CALL IN: 1-877-564-8688, 8571927# Thank you, Peggy Esquibel-Reed Qwest CMP CRPM

- January 10, 2005 Email Received from Comcast: Peggy It looks like Wednesday, January 12th after 1:00 PM, then again Monday after 10:00 AM Linda Hobmann-Minasola

- January 10, 2005 Email Sent to Comcast: Hi Linda, Please advise me of your availability for the Clarification Meeting to discuss your submitted CMP CR requesting to Reduce the Interval Time Required for a 'Simply' Port. As soon as I receive your availability, I will schedule the call and send you the call-in information. Thank you, Peggy Esquibel-Reed Qwest CMP CRPM


CenturyLink Response

March 8, 2005

For Review by the CLEC Community and Discussion at the March 2005 CMP Meeting

Linda Minasola Comcast

This letter is in response to CLEC Change Request number PC010705-1, dated 1/7/2005, and titled: Reduce the Interval Time Required for a 'simple' Port.

CR Description as written by Comcast: "Reduction in business day interval from three business days to one business day for a simply residential one line account. Comcast request would be for a resident 'CB' REQTYP 'Z' ACT"

Qwest Response: Qwest’s three business day interval is currently shorter than the 4 days recommended by the FCC which includes 24 hours for the FOC. Qwest’s three day interval absorbs the FOC interval, whether the request is electronic or manual.

The proposed change to the due date interval would pose potential risks to Qwest and to the customer. Porting triggers must be set by 11:59PM the day before the due date. A shortened interval to 1 day would not allow Qwest sufficient time to correct errors or detect issues when the triggers are not automatically set. Additionally, with the current interval today, Qwest is often requested to work back port orders due to out of service conditions. A shortening of the porting interval would most likely increase the number of customer service issues and result in increased work backs for Qwest.

Qwest is therefore denying your request for PC010705-1, Reduce the Interval Time Required for a 'simple' Port for no demonstrable business benefit due to the increased risk of customers service outages and due to the fact that shortening the interval would increase the risk of the triggers not being set and worked timely within the NPAC existing interval of 18-business hours.

Sincerely, Qwest


Open Product/Process CR PC010702-1 Detail

 
Title: For Qwest to develop appropriate blocking for Directory Assistance and National Directory Assistance for Resellers
CR Number Current Status
Date
Area Impacted Products Impacted

PC010702-1 Completed
2/20/2002
Ordering, Billing & Other Resale: Toll restriction, possible new USOC
Originator: Harsila, Roy
Originator Company Name: Comm South Companies, Inc.
Owner: Van Dusen, Janean
Director:
CR PM:

Description Of Change

At this time, Comm South Companies, Inc. uses the appropriate toll restriction USOC for our blocking; however, the toll restriction does not block any types of Directory Assistance calling. Qwest provides to their customer's the product of Dial Lock, which is USOC: OC4, that blocks Directory Assistance. Qwest has stated that this product was not developed to be used by Resellers. Other RBOC's include this type of blocking in the toll restriction option. I would like to see Qwest add the Directory Assistance blocking feature in the toll restriction. At this time, Comm South Companies, Inc. is being billed thousands of dollars for Directory Assistance and then we have to bill our end users, if Qwest would add this Directory Assistance blocking functionality in their toll restriction product it would help reduce these charges.


Status History

1/7/02 - CR Submitted by Comm South Companies, Inc.

1/7/02 - CR acknowledged by P&P CMP Manager

1/9/02 - Comm South contacted to coordinate clarification call. Call scheduled for 1/15/02

1/15/02 - Clarification call held.

1/15/02 - Draft meeting minutes from clarification call issued to Comm South Companies

1/25/02 - Draft response dated 01/24/02 posted to CMP database and issued to Comm South Companies. Status changed to "Presented"

2/19/02 - E-mail from Comm South asking follow-up questions

2/20/02 - February CMP meeting: Qwest response dated 01/24/02 presented to CLECs. Comm South agreed their request had been answered. CR status changed to "Completed". Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the P/P CMP Meeting Distribution Package 03/20/02

2/22/02 - Formal response dated 01/24/02 issued to CLECs - Document Number: CMPR.02.22.02.F.01229.CR_Responses

3/20/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

02/19/02 E-mail from Comm South asking follow-up questions Subject: CR Form PC010702-1 Date: Tue, 19 Feb 2002 12:52:25 -0600 From: Roy Harsila To: "'tmead@qwest.com'" To whom it may concern: Thank you for the response to the CR that I submitted. I do have some questions pertaining to CustomNet, and these questions are as follows: The definition of CustomNet is as follows: "CustomNet provides operator screening when originating a call by dialing 0/0+, thereby restricting the types of calls billed to third number, collect or calling card depending on the Call Screening Code used." My questions are as follows. 1) Could a call get passed the operator without the call being alternately billed? If this is possible, who is responsible for the bill of this call, Qwest or Comm South or the end user? 2) When will the nonrecurring charge for the CustomNet be applicable? On every order type? Thank you for your time. Sincerely, Roy Harsila Comm South Companies, Inc. 972-643-6417

--

01/15/02 Alignment/Clarification Meeting 10:00 a.m. (MST) / Tuesday 15th January 2002

Attendees: Roy Harsila / Comm South Companies Todd Mead / Qwest Janean Van Dusen / Qwest Jolene Wees / Qwest

Review Requested (Description of) Change: Roy introduced the CR. Janean asked whether the Directory blocking was for local or long distance? Roy responded for both local and National. Jolene asked whether retail have this product? Need someone from retail on the call. Jolene recommended Sandy Foster.

Area Impacted: Ordering, Billing & Other Products Impacted: Resale: Toll restriction, possible new USOC

Confirm Right Personnel Involved: Janean is the owner for this CR. She will need to coordinate with people in retail to assist with response.

Identify/Confirm CLEC’s Expectation: For Qwest to add the Directory Assistance blocking functionality in the toll restriction product or develop a USOC that can be used by Reseller's to block all types of Directory Assistance.

Establish Action Plan: This CR can be walked on this month. However, the General Clarification will take place during the February CMP Meeting (02/20/02). Qwest response will be presented in the March CMP Meeting (03/20/02)


CenturyLink Response

FORMAL RESPONSE

January 24, 2002

Roy Harsila Carrier Relations Manager Comm South Companies, Inc.

CC: Bill Campbell

This letter is in response to your CLEC Change Request Form, number PC010702-1 – For Qwest to develop appropriate blocking for Directory Assistance and National Directory Assistance for Resellers.

REQUEST: At this time, Comm South Companies, Inc. uses the appropriate toll restriction USOC for our blocking; however, the toll restriction does not block any types of Directory Assistance calling. Qwest provides to their customer's the product of Dial Lock, which is USOC: OC4 that blocks Directory Assistance. Qwest has stated that this product was not developed to be used by Resellers. Other RBOC's include this type of blocking in the toll restriction option. I would like to see Qwest add the Directory Assistance blocking feature in the toll restriction. At this time, Comm South Companies, Inc. is being billed thousands of dollars for Directory Assistance and then we have to bill our end users, if Qwest would add this Directory Assistance blocking functionality in their toll restriction product it would help reduce these charges.

RESPONSE: Qwest understand the problem Comm South is facing with unapproved charges being made against its network. Qwest has a product called CustomNET that will provide the National and International Directory Blocking product for Comm South. Details about this product can be found at:

http://www.qwest.com/wholesale/clecs/features/customnet.html#prod

If you have any questions or would like to purchase this product, please contact your Service Manager.

Sincerely,

Janean Van Dusen Product Manager


Open Product/Process CR PC011502-1 Detail

 
Title: Joint testing of Qwest installed transmission cables
CR Number Current Status
Date
Area Impacted Products Impacted

PC011502-1 Completed
4/15/2009
Ordering, Maintenance/Repair Colocation, UDIT, Unbundled loop, UNE, LIS / Interconnect
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Campbell, Ben
Director:
CR PM: Harlan, Cindy

Description Of Change

Provide a 60 calendar day "window of opportunity" for joint testing, at no additional charge, of newly installed transmission cables and cables associated with installation of virtual splitter collocation, to ensure no electrical faults (ie; opens, grounds, reversals, etc.) between the CLEC collocation arrangement and the Qwest DS0, 1 or 3 ICDF.

Additional Information: Covad has experienced a significant number of cable augments with electrical faults, requiring a technician dispatch to the central office.


Status History

01/14/02 - CR Submitted by Covad.

01/15/02 - CR acknowledged by P/P CMP Manager.

01/18/02 - Coordinated optional dates/times for Clarification Meeting with Covad.

01/23/02 - Conducted Clarification Meeting with Covad.

01/28/02 - Issued Clarification Meeting Minutes to Covad.

02/20/02 - CMP Meeting - CLEC Community Clarification held. It was agreed that the CR would move to Evaluation. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/13/02 - Issued Qwest's Draft Response dated March 11, 2002 to Covad.

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 11, 2002. The participants agreed that the CR could move into Development. Qwest to contact Covad, who was not in attendance, to confirm that they agree to move the CR to Development.

03/21/02 - Telephone conversation with Covad - Qwest reviewed its response and explained the discussions at the CMP Meeting. Covad was in agreement to move into Development and see how the facility installations are improving.

03/22/02 - Formal response dated March 11, 2002 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses.

04/17/02 - CMP Meeting - Qwest provided a status on the process development. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Development.

05/15/02 - CMP Meeting - Qwest provided a status on the process development. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Development.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status will remain in Development.

06/27/02 - Issued Mailout notification of CLEC conference call to review product description. Notification CMPR.06.27.02.F.01284.ICDF_Meeting.

07/11/02 - CLEC conference call held to review the ICDF Joint Testing product offering and the Test Access Points document

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status "Development" was not changed.

08/06/02 - Issued Mailout notification of CLEC conference call scheduled for 8/16/02 to review revised product description. CMPR.08.06.02.F.01308.Joint_Testing_Mtg.

08/09/02 - Issued Mailout notification with meeting material for 8/16/02 conference call. Notification CMPR.08.09.02.F.01313.Mtg_Material.

08/21/02 - CMP Meeting - Qwest provided a status on issuance of the Level 3 notification. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

09/18/02 - CMP Meeting - Qwest provided a status on issuance of the Level 3 notification. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

10/16/02 - CMP Meeting - Qwest provided a status on issuance of the Level 3 notification. Minutes on this CR to be posted to the Project Meetings section. Status to remain in Development.

10/17/02 - Contacted Covadd to advise new issue identified and process document is still under review.

11/05/02 - Notification due out 11-06, comment cycle 11-07 - 21, publish plan date 11-21.

11/20/02 - CMP Monthly Meeting agreed to move this CR to CLEC Test status.

12/06/02 - No comments received. Final Notification sent out 11-27 effective 12-12. Move to close this CR at the December CMP meeting.

12/10/02 - Contacted Covad to check if process working. No orders have gone through this process as of yet so we will plan on leaving this project in CLEC Test.

12/18/02 - December P/P CMP Meeting minutes will be posted to the Project Meeting section. PCAT completed and no comments came in. Qwest and Covad discussed the forms that are used to order this product and agreed that the product has not been ordered yet so we will leave the CR in CLEC Test until the product is ordered and working.

01/15/03 - CMP Meeting - CR remains in CLEC Test.

02/19/03 - Feb CMP Meeting - CR remains in CLEC Test. Product has been ordered and is going through the entire process. Should be able to close this CR after order is completed. CMP Meeting minutes will be posted to the Project Meeting Section.

3/11/03 - Qwest Steve Nelson checking on 3 pending jobs for Covad - quote has been issued but not accepted yet. Nelson will be advised when the jobs go to joint testing.

3/19/03 - March CMP Meeting minutes will be posted to the database

4/16/03 - April CMP Meeting minutes will be posted to the database

5/16/03 - May CMP Meeting minutes will be posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database

7/16/03 - July CMP Meeting minutes posted to the database


Project Meetings

07/16/03 July CMP Meeting Minutes John Berard – Covad advised on one test there was a scheduling issue between the technicians. Steve Nelson – Qwest explained that was at the Dry Creek Central Office and the technicians were not able to coordinate their schedules. Qwest has completed multiple tests successfully with Covad and Integra. The SICMs were present at all tests. One of the tests included 400 DSO lines, which were tested without any defects. The test with Integra had one defect, which was later cleared. Qwest reviewed the process and explained if there are problems we will continue to work with the CLECs. John Berard – Covad agreed to close this CR.

06/18/03 June CMP Meeting Minutes Steve Nelson – Qwest reported the Dry Creek test is still pending. Qwest and Covad completed the test in Washington. They tested 200 cables, all were good, and we found 2 splitter card problems that we resolved. The joint test took 1 hour to do the test, and 1-hour travel time each way. Qwest will reduce the interval to 1 hour. Mike Zulevic-Covad advised we need to work on sharing and recording test results. Covad requested to leave in CLEC Test one more month.

05/21/03 May CMP Meeting Minutes Steve Nelson – Qwest reported he is monitoring two RFS; one for Covad and one for Cyber Mesa. There is a call scheduled today which will set up the time for the Joint Test to occur. Steve and Mike will try to attend the Joint test. Steve will advise Cindy Macy when the joint test is scheduled and completed. This CR will remain in CLEC Test.

04/16/03 April CMP Meeting PC011502-1: Joint Testing of Qwest Installed Transmission Cables

Steve Nelson – Qwest reported a total of 13 joint test results have been submitted and are pending from 3 different CLECs. None are completed as of yet so we are unable to report on the test results until they go through that phase. These requests came in with Augment orders. Steve advised Qwest will be updating the document to include improvements on the process. Steve is working with the CPMC and will get the RFS dates and call Mike Zulevic. Mike advised he would like to keep this CR open until an order has gone through the entire process. This CR will remain in CLEC Test status.

03/19/03 March CMP Meeting Steve Nelson – Qwest reported Covad has issued orders and Qwest is waiting for Covad to accept the quote. After Covad accepts the quote Steve Nelson will monitor the process to make sure the joint test goes okay. Mike Zulevic agreed to check and see why Covad has not accepted the quote as of yet. Steve Nelson agreed to call Mike with BAN numbers.

02/19/03 Steve Nelson-Qwest and Mike Zulevic-Covad advised they have updated the Interconnection Agreement and Covad has placed augment orders. We are now waiting for the orders to go through the entire process which normally has a 45-60 day interval to complete. After the orders go through the entire process we will determine a close date.

01/15/03 January CMP Meeting

White-Qwest described the CR. Zulevic-Covad stated that Qwest and Covad were in the process of amending Covad’s interconnection agreement and that when that was complete Covad would begin placing orders. This CR remains in CLEC Test.

12/18/02 December CMP Monthly Meeting Minutes Qwest - Nelson advised the PCAT was published and no comments were received. Nelson reported he is working with Covad to clarify how to order the product. Section M of the Collocation Order Form and the Joint Testing at ICDF Form is used for ordering. Covad advised an amendment to their Interconnect Agreement will be issued to modify the increments. The team agreed another CR would need to be issued and handled as a Level 2. This CR will be left in CLEC Test until an order is placed for the product or until the team determines otherwise.

11/20/02 November CMP Monthly Meeting Minutes Qwest (Steve Nelson) reported the PCAT was updated and posted for review with the comment cycle ending 11-21. It was agred to move this CR to CLEC Test.

10/18/02 October CMP Monthly Meeting Minutes Qwest reported the process document for the Test Access Points is under review and anticipated to be available for review effective October 18, 2002. The Qwest documentation review team surfaced an issue after the CMP meeting that is currently under investigation. This issue will impact the October 18 availability date. The document will remain in review and this project will remain in Development status.

09/18/02 September CMP Monthly Meeting Minutes

Qwest advised that documentation on the Joint Test Process should be published by the end of next week. Comments from the last collaborative review meeting are being incorporated into the document and the Collo Application form is being updated. The CR will remain in Development

-

08/21/02 August CMP Monthly Meeting Minutes

Qwest provided a status update on issuance of the Initial Notification. They indicated that the process with being revised to incorporate the CLECs request to have Qwest contact the CLEC to notify when they are ready and that there would be no additional QPF. Covad advised that they had a conversation with the Collocation Product Manager and he provided the same update.

-

07/17/02 - July CMP Meeting Minutes: Qwest stated a meeting was held July 11, 2002 to discuss the proposed product offering. Qwest stated another meeting is planned for the first week of August with the CLECs to discuss proposed resolutions to the questions raised during the July 11 meeting. Qwest will issue a notice to the CLEC community containing proposed dates for the meeting.

CLEC conference call held to review the ICDF Joint Testing product offering and the Test Access Points document

10:00 a.m. (CST) / Thursday, July 11, 2002 Conference Call TEL: 877.521.8687 CODE: 5699655 PC011502-1 Joint testing of Qwest installed transmission cables

Attendees Brent Debrock Cbeyond Communications Al Villiam Allegiance Steve Marks Allegiance David Stauter Allegiance Mike Zoulvik Covad Beckey Neesen Covad Byron Dowing Alltel Laurel Burke Qwest Jerry Bocke Eschelon Lana Messenger FreeTel Communication Mike Keegan Qwest Benjamin Campbell Qwest Johnathan Spangler AT&T

Introduction of the participants on the Conference Call was made. Qwest explained that the purpose of the call was to review the IDCF Joint Testing product offering and the Test Access Points document.

Qwest discussed the new process offering of Joint Testing, and the Test Access Points Document. The CLEC community expressed that they want: 1) Qwest to take an active role in the test process during Joint Test 2) CLECs do not want to pay for the Joint Test if there are errors found in the Qwest installed Cable.

Qwest stated it would explore these two requests to see if they can be incorporated into the new product offering. Based upon this new feedback, Qwest will delay delivery of the Joint Test Process until resolution on these additions have been resolved. Qwest stated that it would set up another meeting to review the Joint Test Process once a decision is made on their request.

Qwest asked Eschelon if the Test Access Points Document provided the detail requested by Eschelon at the June 19, 2002 CMP meeting (reference Action Item AI041702-1 "Prepare high level documented process of what CLECs are allowed to do in Qwest Central Offices". Eschelon replied the document has not yet been reviewed.

CLEC Change Request Clarification Meeting

12:30 p.m. (MDT) / Wednesday 23 January 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC011502-1 “Joint Testing of Qwest Installed Transmission Cables”

Attendees: Michael Zulevic, Covad Jeffery B. Cook, Qwest Richard Martin, Qwest Peter Wirth, Qwest

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Mike indicated that he recognized that at the time the tie cables are placed, they do not do an actual test when the tie cables are terminated to the equipment. They were looking to be able to do continuity tests, etc before they terminated to the equipment and wanted a period of time for them to do their test and acceptance. Jeff asked why Covad wanted to test DS1 & 3 cables. Mike advised that they wanted to ensure that installation was correct. It was agreed that Covad didn’t want to limit the scope to the cables at the colo splitter arrangement and wanted to cover actual installation(s) at their colo location. Mike confirmed that they were looking for a formal test and turnover process and wanted an acceptance period after actual installation of the facility took place. This would be a joint testing process. Mike indicated that he would be willing to have discussion on the interval time of 60 days. Covad is limited to the number of techs that cover various states and a reasonable time would be required for their techs to get from place to place.

Confirm Areas & Products Impacted It was confirmed that Covad would like any products covered to be included in the process. . Confirm Right Personnel Involved Jeff indicated that Laurel Burke would probably take ownership of the CR and he would help facilitate.

Identify/Confirm CLEC’s Expectation It was confirmed that Covad is looking for a process for Test and Turnover of facility installations to their collocations.

Identify any Dependent Systems Change Requests There is no corresponding System CR

Establish Action Plan (Resolution Time Frame) Ric advised that the CR would be clarified with the CLEC Community at the next CMP Meeting and Qwest will verbally present potential solutions.


CenturyLink Response

March 11, 2002

Michael Zulevic Director Technical Regulatory Support Covad Communications

SUBJECT: Qwest’s Change Request Response - CR # PC011502-1 Joint Testing of Qwest Installed Transmission Cables

This letter is in response to your Change Request PC011502-1 requesting a formal test and turn up process and an acceptance period after the collocation installation work completes – after Ready For Service (RFS). Covad envisions this process as joint testing at no additional cost to take place within 60 days of the RFS that allows for scheduling of their technicians.

Qwest is committed to providing quality facilities installations by the RFS date and Qwest’s warranty obligations will be enforced. Qwest installation forces perform continuity testing where appropriate when the collocation is turned over to Covad for acceptance. We perform quality audits on a random basis to check the quality of our work on the collocation CLEC cable installations. Streaker tests are performed on Line Sharing installations.

Recent results of Qwest internal quality audits have identified the following as it relates to the line sharing installations performed as a project in the summer of 2000: ? Of 249 jobs checked, 25.7% had some percentage of defects. ? One way to describe it is in # of pairs provisioned - (1 pair/job w/problem) x (25.7% of jobs w/connection problems)/300 pairs/job = 0.086% of all terminations wired had problems open/cross/reversal problems. ? This type of error is not common, but not unheard of in Telecommunications Installation. ? 7 jobs (3%) had the cards not seated in the splitter. Normally, Central Office Equipment installation hands off cards to the CO Operations for final test/turn-up. Line Sharing differed from this ingrained work-norm, and thus resulted in 2% of those jobs exhibiting this problem. ? 3 (1%) of the jobs had items that were found to be attributed to CLEC-issues (e.g. telling Qwest to cannibalize circuits that already had jumpers run for CLEC-customers, and 1 item that was traced back to the Customer Premise - end user equipment). ? 5 jobs had a combination of the above issues.

Given the newness of the product and associated processes and technologies, this project proved more challenging than any standard collocation build. Thus, the quality of those standard builds are even better than the Line Sharing results.

After the facility installation has been turned-over and the CLEC has had the opportunity to terminate their bulk end of the cable, full testing of the terminations between their collocation space and the vertical side of the ICDF can be done by the CLEC. In the case that these CLEC test indicate Qwest-defects, Qwest is willing to revisit the site and resolve any such defects for no additional charge should they exceed a 2% threshold. The attached diagram captures the existing test points as they are defined today in the Unbundled Loop process and collocation test access.

The piece of cable between the CLEC’s collocation space and the vertical side of the ICDF (commonly referred to as CLEC cabling) is the responsibility of CLEC and is paid for by the CLEC, as part of the collocation build out. With that stated, the CLEC is responsible for the testing, maintenance and subsequent repair if they were to find trouble in this cable “piece” after any acceptance or continuity test on their part requiring Qwest installation revisit initially.

Qwest evaluated the possibility of having a coordinated Joint Test on a regularly scheduled basis, but determined quality results indicate it would not be productive to do so and would indeed be costly. Nevertheless, we are willing to Joint Test should a CLEC still feel the need for such a service and agree to do so under our Special Request process and price the service accordingly.

We are committed to define the Joint Test process over the next few months.

Sincerely,

Steve Nelson Group Product Manager-Collocation

Cc: Laurel Burke Mary Retka William Campbell

(See end of this CR Detail Report for Attachment)


Open Product/Process CR PC011502-2 Detail

 
Title: Collocation Point of Demarcation cross connect wiring documentation
CR Number Current Status
Date
Area Impacted Products Impacted

PC011502-2 Completed
7/17/2002
Ordering, Maintenance/Repair Collocation, UDIT, Unbundled Loop, UNE, LIS / Interconnect
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Burke, Laurel
Director:
CR PM:

Description Of Change

Provide documentation at every Point of Demarcation cross-connect point, clearly available to both Qwest and CLEC technicians, which clearly describes the appropriate method of making cross-connects, in order to eliminate reversed circuits and/or incorrectly wired circuits. This documentation will provide a consistent product for CLECs and establish a common understanding between the CLEC and Qwest technicians as to the proper wiring of DS0 (UNE and Line Shared), DS1 and DS3 circuits, eliminating unnecessary trouble reports and costly dispatches.

Additional Information: Covad has experienced a significant number of incorrectly wired customer circuits. These include incorrectly wired DS0 UNE and Line Shared services and also DS1/3 services which have been delivered with the transmit and receive conductors reversed, requiring a technician dispatch to the central office.


Status History

01/14/02 - CR Submitted by Covad.

01/15/02 - CR acknowledged by P/P CMP Manager.

01/18/02 - Coordinated optional dates/times for Clarification Meeting with Covad.

01/21/02 - Clarification Meeting conducted with submitting CLEC.

01/21/02 - Clarification Meeting minutes transmitted to submitting CLEC.

02/18/02 - Follow-up clarification meeting conducted with submitting CLEC.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/12/02 - Qwest draft response posted to database and sent to submitting CLEC

03/13/02 - Qwest draft response posted to Web

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 20, 2002. Covad not present at meeting. It was agreed that the CR status be changed to Development . Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/21/02 - Revised draft response dated March 20, 2002 sent to Covad and posted to database.

03/21/02 - Telephone conference with Covad - Qwest explained the discussion at the CMP Meeting. Covad requested another call for more clarification regarding Qwest draft response.

03/21/02 -2nd Telephone conference call with Covad. Covad agreed to provide list of busiest CO's where they would like to see diagrams for DS1 and DS3 posted in bays at cross connects. This list will be sent to CRPM by March 29. Qwest will investigate cost of getting decals of the diagrams created in order to maintain fire rating in the bays.

03/21/02 - Snap shot of the diagrams for DSX1 & 3 crossconnection taken directly from the T1X1 T1.102 ANSI Standard document sent to Covad

04/10/02 - Revised response sent to originating CLEC and posted to CMP database

04/17/02 - CMP Meeting - Qwest presented its final response . CR status as Development unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/19/02 - Formal response dated April 10, 2002 issued to CLECs. Notification CMPR.04.19.02.F.01258.Final_CR_Responses.

05/15/02 - CMP Meeting - CR status "Development" unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/19/02 - CMP Meeting -- Covad was not present at meeting. CR status "Development" unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Completed.


Project Meetings

07/17/02 - July CMP Meeting Minutes: Qwest stated all collocation point of demarcation cross-connect wiring documentation had been placed in the central offices. Covad agreed to change status to closed.

9:00 a.m. (MDT) / Monday 18th February 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC011502-2 "Collocation Point of Demarcation cross-connect wiring diagram" [Follow-up Meeting]

Michael Zulevic, Covad Laurel Burke, Qwest Steven Hilleary, Qwest Michael Lanoue, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Description: Provide documentation at every Point of Demarcation cross-connect point, clearly available to both Qwest and CLEC technicians, which clearly describes the appropriate method of making cross-connects, in order to eliminate reversed circuits and/or incorrectly wired circuits. This documentation will provide a consistent product for CLECs and establish a common understanding between the CLEC and Qwest technicians as to the proper wiring of DS0 (UNE and Line Shared), DS1 and DS3 circuits, eliminating unnecessary trouble reports and costly dispatches. Additional Information: Covad has experienced a significant number of incorrectly wired customer circuits. These include incorrectly wired DS0 UNE and Line Shared services and also DS1/3 services which have been delivered with the transmit and receive conductors reversed, requiring a technician dispatch to the central office.

Additional discussion occurred regarding specifics of the request. Covad indicated that it would like to have wiring diagrams in the collocation areas for the cross connects for DS0/DS!/DS3 circuits. Steve Hilleary & Michael Lanoue, Qwest indicated that current test procedures should identify polarity (transmit/receive) reversals, unless "loop backs" are utilized during testing. Qwest will review procedures and determine if "loop backs" are allowable. Laurel Burke, Qwest requested more recent specific examples dealing with the CR from Covad. Qwest will conduct the CLEC community clarification in the 20-Feb-02 meeting, to solicit any additional input.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Appropriate products & areas identified in CR.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Covad confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC " what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)"} Covad is requesting Qwest to provide process/documentation available to both Qwest and CLEC at the ICDF detailing the correct cabling (& terminations) for a cross-connection.. Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR.

--

10:00 a.m. (MDT) / Monday 21th January 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC011502-2 "Collocation Point of Demarcation cross-connect wiring diagram"

Michael Zulevic, Covad Shirley Tallman, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change: Description: Provide documentation at every Point of Demarcation cross-connect point, clearly available to both Qwest and CLEC technicians, which clearly describes the appropriate method of making cross-connects, in order to eliminate reversed circuits and/or incorrectly wired circuits. This documentation will provide a consistent product for CLECs and establish a common understanding between the CLEC and Qwest technicians as to the proper wiring of DS0 (UNE and Line Shared), DS1 and DS3 circuits, eliminating unnecessary trouble reports and costly dispatches. Additional Information: Covad has experienced a significant number of incorrectly wired customer circuits. These include incorrectly wired DS0 UNE and Line Shared services and also DS1/3 services which have been delivered with the transmit and receive conductors reversed, requiring a technician dispatch to the central office.

Michael Zulevic, Covad reviewed CR stressing the following: 1) focus primarily on DS1 and DS3 cross-connects utilizing ICDF’s; 2) polarity (Transmit/Receive) of connections incorrectly wired; and 3) need process/documentation for access by both Qwest & CLEC to completed connection correctly, thus avoiding cross-connection re-work. Examples were cited in the Seattle, WA and Minneapolis, MN CO’s. Covad indicated that Susan Early, Qwest [Covad account manager] is aware of incorrect wiring examples. Incorrect wiring results in service affecting conditions, along with need for re-work.

Shirley Tallman, Qwest asked clarifying questions and indicated that research with the methods group appears to be warranted to identify current Qwest practice, and determine what could be done to address the CR.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Appropriate products & areas identified in CR.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Covad confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Covad is requesting Qwest to provide process/documentation available to both Qwest and CLEC at the ICDF detailing the correct cabling (& terminations) for a cross-connection.. Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR; or provide an expedited response to the CR.


CenturyLink Response

April 10, 2002

COVAD Communications Michael Zulevic Director Technical Regulatory Support

SUBJECT: Qwest’s Change Request Response - CR # PC011502-2 Collocation Point of Demarcation cross-connect wiring documentation

This letter responds to COVAD Communications’ Change Request PC011502-2 requesting the posting of the DS1/3 circuit wiring diagram on the Central Office ICDF DSX frames. Covad indicated that the purpose of the diagram posting was to eliminate reversed circuits as in line sharing situations and other incorrectly wired circuits as well as to provide cross connection wiring consistency between CLEC and Qwest technicians.

Qwest maintains responsibility for correctly provisioning cross connections on all order types. Qwest Central Offices contain a large and variable number of InterConnection Distribution Frame ("ICDF") Digital Signal Level X(DSX) frames, estimated to exceed 10, 000 frames, that would in turn require a large number of DSX circuit cross connection diagrams. Qwest also recognizes that concerns and questions arise surrounding the provisioning of DS1 or DS3 cross connections. Therefore, Qwest will provide a copy of the Qwest Method and Procedure ("M&P") in each Central Office location. Central Office personnel responsible for provisioning and repairing DS1/DS3 circuits will be able to access the M&P. The M&P will be available beginning in June 2002. Further, after following the office wiring steps loaded into Qwest systems for the order, Qwest ensures that the proper transmit to receive connectivity has been achieved by performing the proper post wiring tests.

Qwest reiterates its commitment to correctly wire cross connections on all types of orders and believes that providing the Qwest M&P in each Central Office will alleviate the concerns expressed. If Covad has information related to specific instances of improper wiring, Qwest continues to request that Covad provide such information so that Qwest can take the appropriate action.

Sincerely,

Laurel L. Burke Staff Adovcate Technical Regulatory Interconnection Planning Local Networks

cc: Deborah Heckart, Director Program/Project Management Mary Retka, Director Legal Issues


Open Product/Process CR PC011502-4 Detail

 
Title: Documentation of block and splitter port numbering for Virtual Splitter Collocation
CR Number Current Status
Date
Area Impacted Products Impacted

PC011502-4 Completed
5/15/2002
Ordering, Maintenace / Repair Colocation, UDIT, UNE, LIS / Interconnect
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Cook, Jeff
Director:
CR PM:

Description Of Change

Provide documentation at every ICDF cross-connect point, clearly available to both Qwest and CLEC technicians, which clearly describes the relationship between the Covad tie cable numbering, splitter port/card numbering and the numbering of the combined voice/data and voice only cross-connect blocks on the Qwest side of the ICDF. Qwest’s decision to cable and number using a 1 to 96 numbering convention instead of 1 to 100, as is the convention used by Covad’s tie cables and equipment, has resulted in serious provisioning and trouble isolation problems.

Additional Information: Qwest agreed to provide this documentation when this problem was discovered during the initial deployment of splitters. Covad preferred to have the installations re-wired using the 1 to 100 convention, but agreed to the posting of documentation. This documentation is not currently posted in Qwest central offices. When a trouble report is identified with a customer using Covad tie pair 26, Qwest technicians must know that the customer’s service is on pair 25 on the Qwest cross-connect blocks. Without clear and available documentation available to the Qwest and CLEC technicians, service could be interrupted for the wrong customer, and resolution of the original trouble report will be further delayed.


Status History

01/14/02 - CR Submitted by Covad.

01/15/02 - CR acknowledged by P/P CMP Manager.

01/18/02 - Coordinated optional dates/times for Clarification Meeting with Covad.

01/23/02 - Clarification Meeting conducted with submitting CLEC.

01/23/02 - Clarification Meeting minutes transmitted to submitting CLEC.

02/07/02 - Draft response (dated 02/06/02) transmitted to submitting CLEC and posted in CMP data base.

02/20/02 - CMP Meeting - Qwest presented "Draft" response. CR status changed to "Development. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/22/02 - Qwest "Formal" response (dated 02/06/02) posted in CMP data base.

02/28/02 - Qwest "Formal" response reissued to incorporate an updated Qwest / CLEC Interconnect Distribution Frame (ICDF) Cable Numbering table

03/20/02 - CMP Meeting - Qwest povided update. It was announced that the Job Aid will be complete and deployed in the Central Offices by April 1, 2002. Covad was not at the meeting. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/21/02 - Telephone conference with Covad - Qwest explained the discussion at the CMP Meeting. It was agreed CR status would remain in Development.

04/17/02 - CMP Meeting - CR status changed to CLEC Test. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

05/15/02 - CMP Meeting - CR status changed to Completed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.


Project Meetings


CenturyLink Response

February 28, 2002

Michael Zulevic Director, Technical Regulatory Support Covad Communications

The following response was originally issued in a letter dated February 6, 2002. It is being reissued to incorporate an updated Qwest / CLEC Interconnect Distribution Frame (ICDF) Cable Numbering table (see attachment).

SUBJECT: Change Request Form Number PC011502-4 “ Documentation of Block and Splitter Port Numbering for Virtual Splitters,” dated January 14, 2002.

Qwest has evaluated the Change Request (CR) PC011502-4, and has determined the following:

? Covad is correct with their assessment of the potential confusion that may arise from the different cable wiring schemes utilized by Qwest and the CLECs at the Interconnection Distribution Frame (ICDF). Qwest or CLEC technicians may incorrectly install or service these connections, resulting in potential customer service impacts.

? Qwest will draft a “Job Aide Table” identifying the relationship between the Qwest and CLEC cable wiring schemes. The table will augment the existing information in the current internal Central Office Job Aide. The table will be placed within the vicinity of the individual ICDF(s) in the Central Office (CO) on the back of the previously agreed to existing job aide as discussed with the Federal Communications Commission (FCC). The target date for issuing the “Job Aide Table” is March 31, 2002. Qwest will notify the CLEC community of formal issuance via the Notification Process through the Change Management Process (CMP).

Sincerely,

Jeff Cook Network Planner – Technical Regulatory Qwest

Cc: Mary Retka, Director Legal Issues, Qwest Brett Fesler, Associate Product Manager, Qwest

Attachment (See Supplemental Information)


Open Product/Process CR PC011502-3 Detail

 
Title: Provide test documentation for all collocation activity including transport cable augments
CR Number Current Status
Date
Area Impacted Products Impacted

PC011502-3 Completed
4/17/2002
Ordering, Maintenance / Repair Collocation, UDIT, Unbundled Loop, UNE, LIS / Interconnect
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Burke, Laurel
Director:
CR PM:

Description Of Change

Provide documentation to CLECs upon completion of new collocation activity or augments to existing collocations, that specify all tests performed to ensure that the work completed by Qwest, or a Qwest designated vendor, was completed properly. These test records must reflect the absence of any physical or electrical faults, including incorrect numbering of cables or cross-connect blocks. Completion of test records is a requirement of Covad’s non-ILEC contractors and the same requirements must apply to Qwest. This requirement has always been placed upon Qwest’s contractors when they are performing work for Qwest.

Additional Information: Covad has experienced a significant number of incorrectly cabled, or designated tie cables from Qwest which has resulted in our not being able to remotely provision customer service.


Status History

Evaluation."01/14/02 - CR Submitted by Covad.

01/15/02 - CR acknowledged by P/P CMP Manager.

01/18/02 - Coordinated optional dates/times for Clarification Meeting with Covad.

01/21/02 - Clarification Meeting conducted with submitting CLEC.

01/21/02 - Clarification Meeting minutes transmitted to submitting CLEC & posted in CMP data base.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/12/02 - Qwest draft response posted to database and sent to submitting CLEC

03/13/02 - Qwest draft response posted to Web

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 1, 2002. Covad not present at meeting. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/21/02 - Telephone conference with Covad - Qwest explained the discussion at the CMP Meeting. Covad was in agreement that the CR would move into CLEC Test.

03/22/02 - Formal response dated 03/01/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/17/02 - CMP Meeting - CR status changed to Completed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.


Project Meetings

10:30 a.m. (MDT) / Monday 21th January 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC011502-3 "Provide test documentation for all collocation activity including transport cable augments"

Michael Zulevic, Covad Laurel Burke, Qwest Cathy Paradiso, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change: Description: Provide documentation to CLECs upon completion of new collocation activity or augments to existing collocations, that specify all tests performed to ensure that the work completed by Qwest, or a Qwest designated vendor, was completed properly. These test records must reflect the absence of any physical or electrical faults, including incorrect numbering of cables or cross-connect blocks. Completion of test records is a requirement of Covad’s non-ILEC contractors and the same requirements must apply to Qwest. This requirement has always been placed upon Qwest’s contractors when they are performing work for Qwest. Additional Information: Covad has experienced a significant number of incorrectly cabled, or designated tie cables from Qwest which has resulted in our not being able to remotely provision customer service.

Michael Zulevic, Covad reviewed the CR and added the following points: 1) Covad is requesting testing/acceptance documentation for collocation augment and new location builds; 2) documentation to be available upon turn-over to CLEC; 3) provides some assurances to CLEC that collocation space has been properly installed/tested; and 4) Covad’s experiences have been that some problems (i.e., grounding, cable labeling, etc). Covad also suggested that some type of co-acceptance by Qwest & the CLEC may assist in this request.

Examples of occurrences were requested by Laurel Burke & Cathy Paradiso, Qwest. Examples were transmitted earlier to Laurel Burke.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Appropriate products & areas identified in CR.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Covad confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Covad is requesting Qwest to provide documentation available to both Qwest and CLEC for collocation space augments/builds to document install/testing status for acceptance. Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR; or provide an expedited response to the CR.


CenturyLink Response

March 1, 2002

Michael Zulevic Director Technical Regulatory Support Covad Communications

SUBJECT: Qwest’s Change Request Response - CR # PC011502-3 Testing Documentation

This letter provides a draft response to your CLEC Change Request Form, number PC011502-3 dated January 14, 2002 - "Provide test documentation for all collocation activity including transport cable augments". Covad requested that documentation be provided upon the completion of collocation activity specifying all tests that performed to ensure cabling work by Qwest or a Qwest designated vendor, was completed properly. During the Change Management Process forum, February 20, 2002, Covad provided further clarification indicating that they would limit this request to virtual and line sharing collocations. Since no discussion included remote collocation applications, this response only addresses central office based virtual collocation and the installation of line sharing.

As part of its standard procedure, Qwest performs cable tests where needed and appropriate. As the CLEC community recognized during the forum, testing of the bulk cable in the physical collocation job does not provide much value as the cable is not terminated to CLEC equipment. However, continuity testing associated with virtual like collocations, including line sharing does not have the same limitation. Thus, on a going forward basis, Qwest agrees to provide the completed Cable Test Record (COE) document RG47-0157 (attached to this response), beginning April 1, 2002, to CLECs involved with new or augmented virtual collocations and line sharing orders, upon CLEC request.

Sincerely,

Laurel L. Burke Staff Advocate Technical Regulatory Interconnection Planning, Local Networks Qwest

cc: Mary Retka, Director, Technical Regulatory Interconnection Planning David Fong, Director, Qwest Central Office Technologies Installation Chuck Points, Director, Qwest Central Office Technologies Installation


Open Product/Process CR PC020502-1 Detail

 
Title: Eliminate Requirement to Provide Tie Cable Specification (Reference Systems CR # SCR020502 1x)
CR Number Current Status
Date
Area Impacted Products Impacted

PC020502-1 Completed
5/15/2002
Ordering, Maintenance/Repair Collaction, Private Line, UDIT, Unbound Loop, UNE, LIS /Interconnect
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: earley, Susan
Director:
CR PM:

Description Of Change

This Change Request seeks to eliminate the requirement to provide tie cable type or technical specifications of tie cable on LSRs and ASRs.

Products Impacted: Any products requiring tie cables to a collocation arrangement.

Qwest policy currently requires Covad to provide specific information relative to the tie cable assigned for use on a LSR/ASR. This information includes the type and gauge of cable of the assigned facility (CFA). If this information is not included or is not in agreement with Qwest records, the LSR/ASR is rejected, which results in delays for Covad customers. Covad believes that it should not be necessary to provide tie cable technical specifications on an LSR. This information is available to Qwest, as they originally installed the tie cables and determined the appropriate technical specifications at that time. This information should be available to them in TIRKS, if required. Further, Qwest is the only ILEC that requires this information to be provided on an LSR/ASR, indicating that the Qwest process is not consistent with industry "Best Practices."

Covad has experienced a significant number of order rejections for DS0, 1 and 3 services due to the omission of tie cable technical information or perceived discrepancies relating to these specifications resulting in delayed customer service provisioning.


Status History

02/04/02 - CR Submitted by Covad

02/05/02 - CR acknowledged by P/P CMP Manager.

02/06/02 - Left voice mail messages on M Zulevic's office and cellular phone to advise of available time for clarification conference call.

02/11/02 - Scheduled Clarification meeting with Covad for 2/15/02.

02/15/02 - Conducted clarification meeting with Covad.

02/19/02 - Issued Clarification Meeting Minutes to Covad.

02/21/02 - Sent Covad e-mail requesting response to a couple of questions.

03/01/02 - Sent e-mail to Covad requesting an additional clarification meeting be scheduled. Changed Owner in dBase to Crystal Soderlund.

03/07/02 - Conducted additional Clarification Meeting with Covad.

03/11/02 - Issued additional Clarification Meeting Minutes to Covad.

03/18/02 - Covad sent e-mail with an example.

03/20/02 - CMP Meeting - Qwest presented the CR to the participants in Covad's absence. Qwest indicated that to implement the CR would require a Systems Change Request. Qwest will provide its response next month. It was agreed that the CR would move to Evaluation. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/21/02 - Telephone conference with Covad - Qwest explained the discussion at the CMP Meeting. Covad was in agreement that the CR would move into Evaluation.

04/10/02 - Issued Qwest's Draft Response dated April 3, 2002 to Covad.

04/17/02 - CMP Meeting - Qwest presented its response. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that a Systems Cross Over CR would be created on behalf of Covad. Qwest to respond to Action Items.

04/19/02 - Formal response dated April 3, 2002 issued to CLECs. Notification CMPR.04.19.02.F.01258.Final_CR_Responses.

04/24/02 - Issued Systems CR to cmpcr@qwest.com on behalf of Covad.

04/24/02 - Sent e-mail to Covad requesting ILEC contacts.

04/24/02 - Received e-mail from Covad requesting that Qwest work through the TIRKS User Group or Telcordia.

04/30/02 - Sent e-mail to Covad inquiring on CO identification.

04/30/02 - Received e-mail from Covad advising that they were waiting on a TIRKS report from Qwest.

05/02/02 - Sent e-mail to Covad responding to Covad's 4/30/02 e-mail.

05/07/02 - Conducted Clarification call with Covad to review the requirements for Action Item No. 1.

05/10/02 - Issued Meeting Minutes from 5/7/02 conference call to Covad.

05/15/02 - CMP Meeting - Qwest advised that a Systems CR was issued and provided its response to the Action Item. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed to close the CR, track the Systems CR and open a Global Action Item for CFA validation..


Project Meetings

CLEC Change Request Additional Clarification Meeting

May 7, 2002 9:00 am (MDT) Conference Call TEL: 877-564-8688 CODE: 8973036 PC020502-1, Action Item No. 1

Attendees: Mike Zulevic, Covad Judy Hotovec, Covad Becky Neessen, Covad Ric Martin, Qwest Susan Earley, Qwest Crystal Soderlund, Qwest

Introduction of Attendees and Purpose of Meeting Introduction of the participants on the Conference Call was made. Ric explained that the purpose of the call was to clarify the action item requirements identified in April’s CMP meeting versus the requirement that was discussed in a Covad/Qwest conference call after the CMP meeting.

Review of Action Item Requirements Ric explained that it was Qwest’s understanding from the April CMP meeting that Covad was to identify a Central Office (CO) to Qwest (Susan) and Qwest Crystal would validate the CFA information at that CO. A subsequent conference call between Qwest and Covad identified the action that Qwest was to advise if a report could be generated from TIRKS to provide all of Covad’s CFA information for all COs. Ric asked which direction Covad wanted Qwest to take. Mike advised that there is a miss-match with the cable gauge information on the final CFA and what is in TIRKS. He understood the System CR needs, but indicated that would take a while to get through the process. He would like to have a 100% validation of their CFA information. Becky indicated that at the call between Qwest and Covad, Bill Fellman was to do a sampling of COs. Susan advised that she could do a sampling of a few offices. It was agreed that Covad would provide 4 COs which Qwest would validate the CFA information for each CO. Covad is to provide their APOT information, which Qwest will validate against. Becky advised that it would be a day or two before she could provide the information. Mike re-emphasized the need to have a 100% validation and would like to get a mechanized dump from TIRKS. Susan advised that she wasn’t aware if there had ever been an electronic dump. Susan will follow-up to determine if this is feasible. Judy indicated that there should be an OVC & APOT dump query. Qwest advised that they would respond to the items by May’s CMP meeting, or sooner.

Subject: RE: CFA Validation Date: Thu, 2 May 2002 12:24:11 -0600 From: "Susan Earley" To: "Michael Zulevic" CC: "Richard Martin" , "Susan Earley" , "Crystal Soderlund" , "Beckie Neesen (E-mail)"

In the meeting we had last month on line sharing and line splitters. I thought Becky brought this up and Bill Fellman was going to check with Tirks staff to see if they could run some kind of report to pull the CFA information for all of Covad's collos. Other then pulling up each one individually Bill and I knew of no way to pull all the collo information at once. I have left Bill a message asking about this. I will get back to you as soon as I hear from Bill.

Susan

--

Subject: RE: CFA Validation Date: Tue, 30 Apr 2002 17:08:49 -0700 From: "Michael Zulevic" To: "Richard Martin" CC: "Susan Earley" , "Crystal Soderlund" , "Beckie Neesen (E-mail)"

Ric,

According to Beckie, we are still waiting to see how you can provide us with a report from TIRKS that will allow us to validate it against our systems. Maybe Susan has an update on this.

Mike Z.

From: Richard Martin [mailto:rhmart2@qwest.com] Sent: Tuesday, April 30, 2002 2:04 PM To: Mike Zulevic Cc: Susan Earley; Crystal Soderlund Subject: CFA Validation

Mike,

At the last month CMP meeting, you requested that Qwest validate CFA information. Crystal Soderlund would work with Susan Early on this. You were to get with Susan to identify a Central Office they can take a look at.

Please let me know if this was your understanding and if you have had a chance to provide the information to Susan.

Thanks

Ric

--

Subject: RE: Action Item from April's CMP on CR PC020502-1 Date: Wed, 24 Apr 2002 16:07:48 -0700 From: "Michael Zulevic" To: "Richard Martin"

Ric,

I would like Qwest to find out why your TIRKS system has this requirement when other ILECs don't. My thought was for Qwest to use it's contacts from TIRKS user groups, or Telcordia, to determine if there is an easy way to address this. I don't think any contacts we may have would be useful in making this determination.

Mike Z.

--

Subject: Action Item from April's CMP on CR PC020502-1 Date: Wed, 24 Apr 2002 15:18:52 -0600 From: Richard Martin Organization: Qwest Communications International, Inc. To: Mike Zulevic

Mike,

At April's CMP meeting, we took an action item to contact ILECs regarding their practice of not requiring cable gauge information.

With the issuance of the Systems CR, do you still want Qwest to pursue this item. If so, could you provide the various contacts at the other ILECs that you deal with on the subject.

Thanks

Ric

Subject: APOT cable gauge problem Date: Mon, 18 Mar 2002 15:08:30 -0700 From: "Michael Zulevic" To: "Richard Martin" CC: "Judi Hotovec"

Ric,

Here is another example of the problem we are having with the cable guage. I'm told this office in Denver has become a major problem.

Thanks for your help.

Michael Zulevic Director- External Affairs Office(520)575-2776 Cel(303)884-5657 Fax (520)575-2785

Order# 1900877, pon# 1519719 out of central office DNVRCOCH on pair 8 > has the cable gauge info as 24-NL. The correct cable gauge for this CO > is pairs 1-300 = 26-NL pairs 301-900= 24-NL. Could you change this > information for me?

-

CLEC Change Request Additional Clarification Meeting

March 7, 2002 8:00 am (MDT) Conference Call TEL: 877-564-8688 CODE: 8973036 PC020502-1, ASR/LSR Cable Specification

Attendees: Mike Zulevic, Covad Judy Hotovec, Covad Richard Martin, Qwest Diana Rasmussen, Qwest Crystal Soderlund, Qwest

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the call discussed

Additional Change Request Clarification Covad provided clarification that they would provide the cable name and/or cable pair number as required. They do not inventory the cable specification (i.e. cable gauge) and would prefer not to provide this. They indicated that no other ILEC required cable gauge information. They advised of past experience where the cable gauge changed and they were not aware. Qwest advised that they use TIRKS to inventory the cable information. Covad indicated that they thought the other ILECs also used TIRKS. Qwest advised that from the ASR stand point, the CLEC was required to provide the cable information if they were responsible for the cable assignment. Qwest advised that they would need to check what IMA validates in TIRKS and what is required for a partial/full flow through. It was agreed that the product type would cover UBL, UDIT and maybe Private Line, but would exclude shared loop. Qwest confirmed that the cable information is provided with the APOT and any revisions would generate a revised APOT.

Action Plan Qwest advised that they would be prepared to provide verbal options at the next CMP meeting.

Subject: CR PC020502-1 Date: Thu, 21 Feb 2002 10:50:24 -0700 From: Richard Martin Organization: Qwest Communications International, Inc. To: Mike Zulevic CC: Karen Kraas , Diana Rasmussen , Laurel Burke

Mike,

Could you please address the following questions:

1. What field(s) on the LSR and ASR do you populate with the tie cable specifications that causes the reject/delay?

2. I believe the LSR numbers you provided on our clarification call are Covad's internal LSRs. They do not appear in our system. Could you provide the corresponding Qwest LSR or PON.

Thanks

Ric

CLEC Change Request Clarification Meeting

2:30 p.m. (MDT) / Friday February 15, 2002 Conference Call TEL: 877-564-8688 CODE: 8973036 PC020502-1, Collocation Point of Demarcation cross-connect wiring

Attendees: Mike Zulevic, COVAD Richard Martin, Qwest Jeff Cook, Qwest Diana Rasmussen, Qwest Karen Krass, Qwest Laurel Burke, Qwest Bob Mohr, Qwest

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Mike advised that on LSRs and ASRs information requested relates to the make-up of the specific tie-cable (1.e. 22/24 ga. Or 734/735 cable). Qwest provides the cable information. If COVAD doesn’t provide the cable information, or the cable information is different than what is in Qwest’s database, their order is delayed or rejected. Qwest advised that the cable information was part of the APOT number. It was confirmed that in IMA, this is a mandatory field. Qwest asked if there was a timing issue with providing the cable specification. Mike advised that there wasn’t a timing issue, but was concerned that there is no real value for the information, since Qwest has the information. Qwest advised that the cable information is provided in the APOT. COVAD indicated that sometimes the preliminary & final do not match up. COVAD provided the LSR examples: 1773574, 1738856, and 1850263. Qwest will look into these examples to determine what the downstream impact would be if the cable specification wasn’t provided.

Confirm Areas & Products Impacted COVAD advised that they would be interested in addressing any product that requires a tie cable going back to their Collo. . Confirm Right Personnel Involved Ric advised that we would need to identify another SME for this CR. The examples provided were for LSR. The SME on the call was responsible for Collo and dealt with ASRs. Qwest will identify the appropriate SME. Ric advised that if an additional clarification meeting were required, they would coordinate.

Identify/Confirm CLEC’s Expectation COVAD confirmed that they would like to remove the mandatory requirement to provide the cable specifications with the LSR/ASR.

Identify any Dependent Systems Change Requests It was confirmed that there is no corresponding Systems Change Request.

Establish Action Plan (Resolution Time Frame) Qwest to obtain appropriate SME(s). The CR will be open to the CLEC community clarification at March’s CMP Meeting.


CenturyLink Response

April 3, 2002

Michael Zulevic Director, Technical Regulatory Support Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC020502-1 Eliminate Requirement to Provide Tie Cable Specification

This letter is in response to Covad’s Change Request PC020502-1 requesting that Qwest revise its LSR and ASR requirement for providing tie cable type or technical specification (i.e. cable gauge).

The APOT CFA data for cable gauge information is a requirement for the Qwest TIRKS database. If the cable gauge information is not passed via the service order, it does not allow the order to flow through without manual design intervention. This could cause delays for the CLEC and an increase in costs and resources for Qwest to perform this manual work. Increasing manual intervention defeats Qwest’s goal to promote flow through mechanization.

Programming for retrieving the cable gauge information from TIRKS and passing it to the order would require multiple systems changes. A Systems Change Request would be required to accomplish this. If Covad would like to pursue the systems changes that could accommodate their Change Request, Qwest will open a Systems Change Request on Covad’s behalf.

Sincerely,

Crystal Soderlund Sr Process Analyst

Cc: Diana Rasmussen Karen Kraas Susie Bliss


Open Product/Process CR PC101802-1 Detail

 
Title: Electronic Access to Demarc Information
CR Number Current Status
Date
Area Impacted Products Impacted

PC101802-1 Crossover
7/27/2009
Ordering, Repair UNE and line shared loops, Unbundled Loop
Originator: Cutcher, Minda
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: White, Matt

Description Of Change

Revised Description of Change

Submitted 02-11-03

PC101802-1 – Description of Change

Currently, Covad obtains demarc information from Qwest as part of the joint acceptance testing process. In the event that demarc in not transmitted at that time, Covad can obtain demarc info by calling Qwest’s Interconnect Group. By making demarc info available offline, electronically, Qwest will eliminate the need to staff this function and Covad and other CLECs can access that information at any time. All CLEC’s require demarc information on any install performed by Qwest regardless of the product. The CLEC itself or a Vendor will need to finish or extend the install to the customer and often cannot locate the line or circuit. The result is a call to obtain the information.

Expected Deliverable

Electronic Access to demarc information

==============

Currently, Covad obtains demarc information from Qwest as part of the joint acceptance testing process. In the event that demarc in not transmitted at that time, Covad can obtain demarc info by calling Qwest’s Interconnect Group. By making demarc info available offline, electronically, Qwest will eliminate the need to staff this function and Covad and other CLECs can access that information at any time.

Expected Deliverable

Electronic Access to demarc information


Status History

10/18/02 - CR Submitted by Covad

10/18/02 - CR acknowledged by P/P CMP Manager.

10/23/03 - Qwest and CLEC mutually agreed to hold Clarification Meeting on 11/5

11/05/03 - Held Clarification Meeting

11/20/02 - CR Presented at CMP Meeting

12/11/02 - Qwest response e-mailed to originator

12/11/02 - Qwest response inserted in the interactive report and posted to the Web site

12/18/02 - Qwest response presented at the CMP Meeting

01/15/03 - Qwest revised response presented at the CMP Meeting

02/07/03 - Qwest conducted Ad Hoc Meeting

02/12/03 - Qwest response e-mailed to originator

02/19/03 - Qwest response presented at CMP Meeting

03/17/03 - Qwest conducted Ad Hoc Meeting

03/19/03 - Discussion at CMP Meeting

04/16/03 - Discussion at CMP Meeting

05/21/03 - Discussed at CMP Meeting - Crossed over to systems


Project Meetings

05-21-03 - CMP Meeting

Buckmaster-Qwest presented the response and stated that the CR would cross over to the systems side for development and implementation. The CR was crossed over.

======================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that Qwest had researched the Eschelon request from the March meeting and determined that it would signifigantly change the scope and cost of the solution. She suggested that current testing had shown that 100 percent of the samples included binding post information. She cautioned that Qwest could not guarantee that information would be in the report. She asked the CLECs to evaluate the strength of the Qwest solution and submit another CR if they felt that it did not meet their specific needs. The CR was moved to development status.

================================================

03-19-03 - CMP Meeting

White-Qwest stated that an Ad Hoc meeting to discuss this CR was held on 3/17. He stated that Qwest presented a proposed solution at this meeting and, based on questions here, would present a formal response to the web after this meeting and present it at the April CMP Meeting. Johnson-Eschelon asked if binding post information would be available to the CLECs. Buckmaster-Qwest stated that binding post information would be available for POTS and designed services when it was available. She stated that the focus of this CR was on the information that was in WFA/C for designed services; primarily the location of the demarc. She stated that this database may include additional information, and that Qwest would provide all information it had. She stated that she had reviewed several examples and that all of them had the information Bonnie was interested in. Johnson-Eschelon stated that she did not want to alter this CR and would submit a separate CR if there were many instances where there was no binding post information. Buckmaster-Qwest pointed out that Qwest provides the CLECs demarc information two times, by voice and e-mail, immediately following the completion of work. Mendoza-Allegiance stated that the Qwest technicians should provide binding post information. Buckmaster-Qwest stated that the description of change for this CR did not include changing the processes for Qwest technicians. Zulevic-Covad agreed that the CR was only written to obtain access to demarc information. Thomte-Qwest asked Zulevic and Johnson if they would be amenable to opening an additional CR for this if necessary. Johnson-Eschelon and Zulevic-Covad stated that they would.

==================================================

Ad Hoc Meeting 10:00 a.m MT, March 17, 2003

Attendees Matt White – Qwest Cindy Buckmaster – Qwest Dan Busetti – Qwest Jeanne Whisenant – Qwest Dave Hahn - Qwest John Berard – Covad Rick Paine – US Link Lori Mendoza – Allegiance Liz Balvin – WorldCom Terrance Morgan - WorldCom Erica Beamus – WorldCom Jeff Gelwick - WorldCom Stephanie Prull – McLeod USA Bonnie Johnson – Eschelon

White-Qwest welcomed attendees and explained the purpose of the meeting. He asked Buckmaster to review the potential solution Qwest had identified for the CR.

Buckmaster-Qwest reviewed the issues identified on the prior Ad Hoc call and stated that Dan Busetti came up with a potential solution. Busetti-Qwest reviewed the solution. He stated that Qwest would add functionality in CEMR to meet this request. He stated that for non-design circuits, CLECs would go to the non-design services action page and select a radial button to view the demarc information. He stated that a similar process would be in place for design services.

Mendoza-Allegiance asked if this functionality would include orders that have been dispatched or only those that have not been dispatched. Buckmaster-Qwest stated that Qwest would provide any information Qwest has. She explained that there would be occasions when Qwest doesn’t have all the information. She clarified that Qwest would not dispatch just to provide information to the database. She stated that the information for Designed Services would be pulled from WFA/C. She stated that information is populated into the database by Qwest technicians at many different locations. Johnson-Eschelon stated that at the previous Ad Hoc meeting Buckmaster had stated that the times when information was not available would be rare. Buckmaster-Qwest stated that at the previous Ad Hoc call the participants discussed that the Demarc information is most important in multi-tenant environments. She stated that binding post information was ancillary to the original request. She explained that Qwest would provide all the information that it can. Johnson-Eschelon asked if Qwest would provide binding post info if it is available. Buckmaster-Qwest stated that Qwest would.

Mendoza–Allegiance asked how the information got into the database if the order was not dispatched. Buckmaster–Qwest stated that if a technician anywhere provides the information, it would provided to the CLECs. She stated that Qwest was not modifying the existing processes for Qwest technicians. She stated that any information in the databases would be available to the CLECs. She explained that POTS has a different source than the Design Services side. Busetti–Qwest stated that LMOS was the database that Qwest would be be pulling the POTS information from. He stated that this database, if properly populated, includes terminal and binding post information.

Berard–Covad asked if specials would be pulled from WFA-C. Busetti–Qwest stated that the would.

Berard–Covad asked if Qwest was setting up a separate database and if Qwest could send the information to the CLECs. Busetti–Qwest stated that Qwest would not send reports to the CLECs, but that the functionality would take a live look at the data in WFA/C and LMOS at the time of the request. Berard–Covad stated that he was happy to hear that it was a live look. He confirmed that when CLECs went into CEMR and made a request it would be live look. Busetti–Qwest stated that the information would be pulled directly from WFA/C and LMOS.

Mendoza-Allegiance asked how the data would be in these databases. Busetti–Qwest stated that it would be in the database as long as the circuit is alive. Prull–McLeod asked how long it took the technicians to update the information in the database. Buckmaster–Qwest stated that she would check. She stated that it was updated within the same workday and that the practice is to do it as soon as the work is completed.

Mendoza–Allegiance asked if the technicians would go out on the plant test date for designed services. Buckmaster–Qwest stated that she needed to check to get an accurate answer to that question.

White-Qwest asked if this met Covad’s intent for the request. Berard–Covad stated that Covad would still like the information sent to them, but that this was a good solution. Buckmaster-Qwest stated that the information is delivered to the CLECs twice for Designed Service circuits: verbally upon closure, and via e-mail within 48 hours of closure. Berard-Covad stated that was good to hear. He stated that Covad could work with that.

White-Qwest stated that Qwest would present a verbal response at the March 19 CMP Meeting and would post a written response on the interactive report following the meeting. He thanked the attendees and adjourned the meeting.

==================================================================

02-19-03 - CMP Meeting

Buckmaster-Qwest presented the Qwest response. Zulevic-Covad stated that his preference was to have the information sent to the CLECs, and his second preference was to have Qwest make the information available to the CLECs. Buckmaster-Qwest stated that she understood that this CR requested three things: 1. An electronic means of accessing information regarding the Demarc and Binding Post location - for orders that were provisioned by Qwest at the CLEC’s request. 2. The CLECs would like this information for both Designed and POTS. 3. Provided as soon as possible upon completion of Qwest’s work. There were no further questions.

==========================================================

Ad Hoc Meeting 02-07-03

Attendees Matt White – Qwest Cindy Buckmaster – Qwest Deni Toye - Qwest Bonnie Johnson - Eschelon Rick Paine – U.S. Link Kelly Hamilton – U.S. Link Karla Kaatz – 180 Communications Mike Zulevic – Covad Glenn Gill – ATG

White-Qwest announced attendees and explained that the purpose of this meeting was to allow Qwest to ask Covad some questions about the CR.

Buckmaster-Qwest stated that she thought the Covad was requesting demarc information in an accessible form so the company could route its technicians properly. Zulevic-Covad stated that this was the gist of the request. Johnson-Eschelon stated that she would like Qwest to give the demarc information including the where the cross-connect is made. She would like the information to include terminal and binding post information. Zulevic-Covad stated that he would revise the Description of Change to reflect this information.

Buckmaster-Qwest asked if the location of the demarc information was only important for large (primarily commercial) buildings. Zulevic-Covad stated that the majority of the sites they wanted demarc information for were commercial sites or large buildings, but there were some unique residential locations they also needed it for.

Buckmaster-Qwest stated that the demarc information may not be available on 100% of the circuits. Zulevic-Covad asked if the Qwest installation technicians reported the demarc information into WFA. Buckmaster-Qwest stated that she did not know. Toye-Qwest stated that the demarc information was communicated via the PTA e-mail after and order is completed. Johnson-Eschelon stated that the e-mail did not include binding post information except for T1’s. She stated that they CLECs were asking for a report that included POTS.

Buckmaster-Qwest stated that she might have to issue a response that commits to only giving the CLECs the information that Qwest currently has. Johnson-Eschelon stated that she understood that the information might not be everything the CLECs would like. Buckmaster-Qwest stated that currently the demarc information is supplied to the CLECs at two different times: verbally when the order is closed and electronically (via e-mail) within 48 hours after the order is closed.

Johnson-Eschelon stated that the real issue was the CLECs are having a problem finding demarc locations and binding post assignments. As a result, the CLECs call QCCC. She stated that completing this CR would result in a small call flow to the center. Zulevic-Covad stated that Covad calls the QCCC to determine demarc information for every order their technicians went on. He stated that he was not sure that Qwest had the complete information for every call.

Buckmaster-Qwest recapped that the CLECs were looking for an electronic method to access information on demarc and binding post locations. Gill-ATG stated that the appropriate means to communicate this information would be on the loop DLR/DSR. Johnson-Eschelon stated that the DLR is not available soon enough. Buckmaster-Qwest reviewed that the CLECs want access to the information about the physical location that Qwest did its work. Johnson-Eschelon stated that Buckmaster had adequately summarized the essence of the request. Zulevic-Covad stated that the CLECs wanted this information as soon as the Qwest technicians finish their work.

Zulevic-Covad stated that he was not familiar with the PTA e-mail results. He stated that that method of communication would not work for POTS.

Buckmaster-Qwest recapped that the CLECs were looking for: 1. An electronic means of accessing information regarding the Demarc and Binding Post location - For orders that were provisioned by Qwest at the CLEC’s request 2. The CLECs would like this information for both Designed and POTs services 3. Provided as soon as applicable after the close of the order

There were no further questions. White-Qwest and Buckmaster-Qwest thanked the attendees and adjourned the meeting.

===================================================================

01/15/03 - CMP Meeting

Moreland-Qwest presented the Qwest response. White-Qwest recommended the CR be placed in Evaluation status when it is crossed over. Johnson-Eschelon asked if a representative from IT could explain in more detail why the CR needed to be crossed over. Schultz-Qwest stated that they could. The CR was crossed over to systems with a status of Evaluation.

===================================================================

12/18/02 - CMP Monthly Product/Process Meeting

Moreland-Qwest described the CR and presented the Qwest response. Berard-Covad stated that Qwest was looking at a database but Covad was open to Qwest introducing any type of electronic means of presenting the information, not just EDI. He stated that Covad would prefer EID, however. Boudhaouia-Qwest stated that stated that Verizon doesn’t have a database and Qwest is trying to determine if there is a feasible way for Qwest to make this information available to the CLECs. Johnson-Eschelon stated that regardless of how Verizon delivers, the fact is that they do make the information available and Qwest does not. She continued that this would be a good change for all companies involved. The attendees agreed to move the CR into Evaluation status.

===================================================================

11/20/02 - CMP Monthly Product/Process Meeting

Berard-Covad presented the CR. He stated that Covad wanted electronic access to demarc information and was given that access by other ILECs. White-Qwest asked which ILECs provided this information and how they provided it. Berard-Covad stated that Verizon provides CLECs a downloadable file that contained demarc information and updated this file four times a day. He stated that the information included floor/closet/binding post or language like “northwest corner of the basement.” Schultz-Qwest asked how having electronic access to this information helped Covad. Berard-Covad stated that it allowed them to access the information at any time and that Covad was hoping to streamline the process in the future to allow JAT without a phone call. Berard-Covad stated that Covad would prefer a file be sent to them every day, but would be happy with a download. Spangler-AT&T and Johnson-Eschelon stated that they would prefer delivery as well and that this should apply to all resale products as well. The CR status was updated to Presented.

===================================================================

CLEC Change Request – PC1018002-1 Clarification Meeting 2:00 PM (Mountain Time) / Tuesday, November 5, 2002

1-877-550-8686 2213337#

Attendees Matt White – CRPM Minda Cutcher – Covad Brett Fesler – Qwest Neil Houston - Qwest

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Cutcher-Covad reviewed the CR and stated that Covad was seeking the same information about the physical location of demarcs at customer prems through electronic means as they got when they called the interconnect center QCCC. She said an example would be to say the demarc was in the northwest corner of the basement of a building.

Houston-Qwest confirmed that Covad was seeking a physical description so the Covad Technician could find the demarc.

Cutcher-Covad stated that they currently get the information during Joint Acceptance Testing, and that she would like a means to access the information electronically. She stated that Qwest must have a database in which it records this information and surmised that to grant this request, Qwest could design a means for Covad to access that database.

Houston-Qwest asked if Covad was seeking a Web site format.

Cutcher-Covad stated that they weren’t necessarily seeking a Web site that could be accessed 24x7, just a means of getting the information electronically during normal business hours. She stated that other ILECs (Verizon and PacBell) had offered this functionality to Covad.

Houston-Qwest stated that he would work with some of his contacts at those companies to understand how they offered this information to CLECs.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the November Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

May 14, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the May 21, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC101802-1

Qwest accepts this change request. Qwest will implement a solution to this request in the CEMR release currently scheduled for implementation in first quarter 2004.

Functionality, scheduled for inclusion in this release, will include: - For Designed services – any information related to demarc location and binding post termination available - For Non-Designed services – any information related to binding post termination available.

There may be instances when no information is available in the source data. In such instances, the information will not be available via the new functionality. Additionally, Qwest will continue to provide customers with all applicable demarc/binding post information, by voice and e-mail, immediately following completion of work to connect a designed services circuit.

Qwest will provide updates on the progress of the implementation of this solution at Monthly CMP Product/Process Meetings.

Sincerely, Cindy Buckmaster Product Manager

==============================================================================

February 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC101802-1

Qwest recently conducted an Ad Hoc Clarification meeting with several CLECs that revealed additional complexity in this CR. Qwest recommends this CR remain in Evaluation Status while Qwest fully explores a potential solution. Qwest will provide a status of Qwest’s research at the March CMP meeting.

Sincerely, Cindy Buckmaster Product Manager

=================================================================================

January 6, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the January 15, 2002, CMP Product/Process Meeting

Minda Cutcher VP Government and External Affairs Covad Communications

SUBJECT: Qwest’s Change Request Revised Response - CR #PC101802-1

This is a revised response regarding Covad CR PC101802-1.

The scope of this request is extremely large and detailed, as there are literally tens of thousands of demarc locations in Qwest’s fourteen-state region.

Qwest has researched the requirements to accomplish this request and has found it to be technically feasible. Implementing this request, however, will require changes to IMA. As a result, Qwest recommends that this CR cross over to become a Systems CR.

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest

=================================================================

December 6, 2002

DRAFT RESPONSE For Review by CLEC Community and Discussion at the December 18, 2002, CMP Product/Process Meeting

Minda Cutcher VP Government and External Affairs Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC101802-1

This is a preliminary response regarding Covad CR PC101802-1.

The scope of this request is extremely large and detailed, as there are literally tens of thousands of demarc locations in Qwest’s fourteen-state region.

Covad indicated that Verizon provides a database for CLECs to get this information themselves, eliminating the need to call. Qwest research determined that Verizon currently supplies CLECs with demarc location information on an order by order basis using an existing database called Wholesale Provisioning Tracking System (WPTS) which they created for CLECs to track orders (see URL below). Demarc location information is only available for orders that have been dispatched and completed. Verizon’s system does not accumulate the information as an ongoing repository for general searches, thus there is no Verizon demarc database. At this time, Qwest does not have a similar WPTS-type database available and this request would require development of such a database.

Qwest recommends that this CR be placed in Evaluation status until Qwest completes an evaluation of the scope and feasibility of the process changes necessary to implement the Covad request.

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest


Open Product/Process CR PC101802-3ES Detail

 
Title: Interval reduction for Line Sharing, Line Splitting and Loop Splitting Services from 3 to 2 days
CR Number Current Status
Date
Area Impacted Products Impacted

PC101802-3ES Completed
2/19/2003
Provisioning Line sharing, line splitting and loop splitting
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: White, Matt

Description Of Change

Covad would like a shorter interval for Qwest’t completion of Line Shared LSRs. The current 3 day interval does not meet our business needs and given the maturing of the provisioning process, a reduction to 2 days seems both reasonable and realistic. This is particularly true in light of BellSouth’s recent voluntary reduction of their interval to 2 days. This interval should also be applicable to Line Splitting and Loop Splitting.

Expected Deliverable

Reduction of interval from 3 to 2 days effective Dec. 1, 2002


Status History

10/18/02 - CR Submitted by Covad

10/18/02 - CR acknowledged by P/P CMP Manager.

10/22/02 - Qwest and CLEC (Mike Zulevic) mutually agreed to hold clarification meeting on 11/06/02

11/06/03 - Held Clarification Meeting

11/20/02 - CR Presented at CMP Meeting

12/11/02 - Qwest response e-mailed to originator

12/11/02 - Qwest response inserted in the interactive report and posted to the Web site

12/18/02 - Qwest response presented at the CMP Meeting

01/15/03 - Qwest revised response presented at the CMP Meeting

01/29/03 - Qwest conducted Ad Hoc Meeting.

02/12/03 - Qwest response e-mailed to originator

02/19/03 - Qwest response presented at CMP Meeting

03/05/03 - CR escalated by Covad

03/06/03 - AT&T indicated Escalation participation


Project Meetings

02-19-03 - CMP Meeting

Buckmaster-Qwest presented the revised Qwest denial. Zulevic-Covad stated that he found the number of resources Qwest claimed it required to shorten the interval by one day to be mind-boggling. He asked if Qwest’s DSL was a flow-though process. Buckmaster-Qwest stated that she did not know if it was a flow through process. Zulevic-Covad stated that the Qwest DSL interval was a 5 day end-to-end interval. He stated that the intervals for Line Sharing, Line Splitting and Loop Splitting services were not end-to-end. Covad often took more than 2 days to finish their portion of the provisioning process. He stated that this was not parity. He stated that Qwest could continue with whatever recommendation it liked. White-Qwest stated that Qwest was denying the CR. Zulevic-Covad stated that he would escalate the CR.

=========================================================

Ad Hoc Meeting 01-29-03

Attendees Matt White – Qwest Cindy Buckmaster – Qwest Deb Smith – Qwest Judy Schultz - Qwest Mike Zulevic – Covad Liz Balvin – WorldCom Sam Tenerelli – WorldCom Sharon Van Meter – AT&T

White-Qwest announced attendees and explained that the purpose of this meeting was to allow Qwest to clarify its reason for denying this CR and to answer and CLEC questions that were not addressed at the January CMP Meeting. He asked Buckmaster-Qwest to review the Qwest Response to the CR. Buckmaster-Qwest reviewed the response. She stated that Qwest was denying the CR for economic infeasibility because of resources impacts, including addition of resources, and volume of orders. She stated that the cost to Qwest when taken into consideration with the volume of Line Sharing orders compared to the volume of like orders resulted in the economic infeasibility conclusion.

Balvin-WorldCom stated that there was discussion at the Monthly Meeting around products with two-day intervals. Buckmaster-Qwest stated that the only Qwest products with two-day intervals involved record work. She explained that none of these products had any technician intervention.

Van Meter-AT&T stated that she would like to see more detail in the response. Schultz-Qwest stated that Qwest would revise the response.

Balvin-WorldCom stated that there was a Systems CR that involved flowthrough that might influence Qwest’s decision to deny this CR. Schultz-Qwest suggested that the Product/Process CR remain in Denied status and that Buckmaster-Qwest review the Systems CR to further analyze its relevance to the Product issues. Zulevic-Covad stated that it would be fine to leave the CR in Denied status but that he wanted Qwest to consider that there was another ILEC that had voluntarily changed their intervals. He also asked that Qwest reevaluate this request when the flowthrough CR was completed.

Balvin-WorldCom stated that she would like to see a more detailed discussion of the rationale for denying the CR for economic infeasibility. White-Qwest asked if there were any additional questions. There were none. Schultz-Qwest thanked the attendees.

======================================================================================

01/15/03 - CMP Meeting

Smith-Qwest presented the Qwest response. Zulevic-Covad stated that he had forwarded additional information to Qwest after Qwest had distributed the response. He asked if that information changed Qwest’s response to the CR. Smith-Qwest stated that it did not. Buckmaster-Qwest stated that the information had not changed Qwest’s response, that Qwest was exceeding their obligation of parity with retail, and that the request was economically infeasible. She continued that there was an agreement between Qwest and Covad in March 2002 when Qwest had voluntarily revised the interval from 5 to 3 days that Covad would not approach Qwest for another interval reduction. Balvin-Worldcom asked for clarification of the reason the CR was economically infeasible. Buckmaster-Qwest stated that the work to implement the CR was extremely manually intensive and costly, especially in light of the relatively low volume of orders. Balvin-Worldcom asked if there was a systems CR open that might help this process change be less expensive. Zulevic-Covad stated that there was a systems CR open for line sharing flow through. Buckmaster-Qwest stated that the change requested in PC101802-3 would not be facilitated by the systems CR. She stated that this change did not involve order fallouts. She continued that there were three manual changes Qwest would need to make to the IMA system, the FOC system and the Operations system to implement this change. Zulevic-Covad asked if the same cost would apply if the interval were reduced to 4 days. Buckmaster-Qwest stated that the same costs would still apply. She stated that in order for this interval to change in any way, Qwest would have to implement extensive manual handling of orders. She stated that the issue behind the denial of this CR was the amount of manual operations and the relatively low volume of orders. Zulevic-Covad stated that he did not recall any agreement that Covad would not request an additional reduction of this interval. Balvin-Worldcom recommended that the CR remain open for an additional month for Qwest to conduct additional research. Buckmaster-Qwest stated that additional would not change Qwest’s response. Zulevic-Covad recommended rewriting the response to more clearly emphasize the reasons that the CR was economically not feasible. Thomte-Qwest stated that Qwest would hold an ad hoc meeting before the next monthly meeting to discuss this CR. The CR remains in Evaluation.

=========================================================================================

12/18/02 - CMP Monthly Product/Process Meeting

Smith-Qwest presented the Qwest response. The attendees agreed to move the CR into Evaluation status.

=========================================================================================

11/20/02 - CMP Monthly Product/Process Meeting

Zulevic-Covad presented the CR. He stated that BellSouth already offered shorter intervals, and that Qwest should be able to as well. Burke-Qwest stated that she had no questions. The CR status was updated to Presented.

=========================================================================================

CLEC Change Request – PC1018002-3 Clarification Meeting 10:30 AM (Mountain Time) / Wednesday, November 6, 2002

1-877-550-8686 2213337#

Attendees Matt White – CRPM Laurel Burke – Qwest Crystal Soderlund – Qwest Deb Smith – Qwest Mike Zulevic – Covad Make Lanoue - Qwest

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Zulevic-Covad reviewed the CR. He stated that Covad would most prefer an interval of 1 day, but would be happy with a 2 day interval.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Smith-Qwest stated that the current interval for line splitting and line sharing was 3 days, and the interval for loop splitting was 5 days.

Zulevic-Covad stated that loop splitting was not a product Covad currently used (although that may soon change) and that Covad was OK with an interval other than 2 days for Loop Splitting, but they want some reduction of the current interval. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Burke-Qwest stated that the current Line Sharing CR may be related to this one.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the November Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

February 12, 2003

AMENDED RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Revised Response - CR #PC101802-3

This letter is in response to CLEC Change Request PC101802-03. This CR is a request by Covad to reduce the interval for Line Sharing, Line Splitting and Loop Splitting from 3 days to 2 days as Covad suggested that BellSouth had done.

This response confirms Qwest’s denial of this CR, for the reasons identified in the January 8, 2003, response, and clarifies the justification for the economically not feasible reason for denial. The following are the major reasons supporting Qwest’s decision to consider the CR economically not feasible:

Line Sharing Volumes: - Total In-Service Line Sharing Orders as of 12/31/02 – 26,083 (average 1,400 incremental lines per month). - Total In-Service UBL* Orders as of 12/31/02 – 483,308 (average 14,000 incremental lines per month). - Line Sharing represents just 5% of the total of these 2 product lines (10% of the average monthly volumes). - This is considered a Low Volume of requests.

Process Changes: - One additional Resource in the Service Center to move Orders more quickly. - A minimum of 60 to 90 additional Central Office Resources across Qwest’s 14 state region to move Orders more quickly. (Line Sharing is currently ordered in 12 of Qwest’s 14 in-region states)

The economic magnitude of adding the indicated resources is too large for the small number of orders. Therefore, Qwest has determined that reducing the interval on Line Sharing orders is economically not feasible. Qwest respectfully declines this change request.

The Line Sharing product is already provisioned in an interval that is shorter than the Retail interval. As the requirement is parity with retail, this requirement is more than met with the current interval.

Qwest continuously evaluates its ability to deliver products in a more timely fashion. If such an opportunity presents itself in the future, Qwest will implement and notify CLECs via the established processes.

Sincerely, Cindy Buckmaster Product Manager

*The comparison made to UBL is made solely on the basis of the functions required to install both services. These functions are comparable for both the Order Processing and Central Office provisioning.

==========================================================================

January 6, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the January 15, 2002, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Revised Response Response - CR #PC101802-3

This letter is in response to CLEC Change Request PC101802-03. This CR is a request by Covad to reduce the interval for Line Sharing, Line Splitting and Loop Splitting from 3 days to 2 days as Covad suggested that BellSouth had done.

At this time, Qwest has no plans to reduce the interval for the Line Sharing, Line Splitting and Loop Splitting Products. Qwest is denying this request because it is economically not feasible. The following are the major reasons supporting Qwest’s decisions:

Installation intervals for these products were negotiated during the ROC TAG forums held in 2001 and 2002. SGAT Exhibit C Service Interval Tables provides the agreed upon intervals. Qwest will continue to be consistent with these agreements.

Qwest retail interval for the DSL product is 5 business days. As the wholesale interval is already less than retail, Qwest is not inclined to reduce the wholesale interval further. This is consistent with the discussions that took place with the CLECs earlier in 2002, when Qwest reduced the interval from 5 to 3 business days on Line Sharing and Line Splitting.

Both system and process changes would be required. System changes are required any time an interval is modified. These system changes are both manually intensive and time consuming, therefore costly. Due to low volumes of new Line Sharing and Line Splitting requests, and the lack of Loop Splitting requests, changes to the system for the small volume of Line Sharing products would be prohibitive. (The Line Sharing, Line Splitting and Loop Splitting products represent less than 5% of the total product volumes.) In addition, Qwest processes cannot guarantee a 2-business day interval causing potential problems with missed commitments for the end user customer.

Upon reviewing BellSouth’s service interval guide, Qwest has found that Qwest is already providing a comparable interval to BellSouth’s, if not superior in some cases. BellSouth applies their interval differently than Qwest. BellSouth applies their 2-business day interval after the request goes through their LSR processing interval. The LSR processing interval ranges from 10 business hours (or 1 business day) to 24 business hours (or 2 ½ business days). Total order completion interval for BellSouth is their service interval added to their LSR processing interval, which is 3 – 4 ½ business days. Qwest, on the other hand applies their 3 business day interval at the time the LSR is received (application date). Qwest includes the LSR processing time within their 3-business day interval; thus Qwest’s total order completion interval is 3 days.

In any case, it is Qwest’s understanding that BellSouth applies the interval that matches their retail offering. Qwest’s retail offering is currently 5 business days.

Therefore, Qwest respectfully declines this change request.

Sincerely, Debra Smith Product Manager

=================================================================

December 6, 2002

DRAFT RESPONSE For Review by CLEC Community and Discussion at the December 18, 2002, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC101802-3

This is a preliminary response regarding Covad CR PC101802-3.

Qwest has reviewed the current Line Sharing provisioning interval. There are a number of issues to be analyzed in answering this request. For this reason, Qwest would like to move this Change Request into the Evaluation Status to provide a complete answer to this request.

Qwest will provide a status update at the January CMP meeting and will outline their response at that time.

Sincerely,

Debra Smith Product Manager Qwest Corporation


Open Product/Process CR PC102102-1 Detail

 
Title: Dual Inventory of DSL tie cables in TIRKS and SWITCH/FOMS
CR Number Current Status
Date
Area Impacted Products Impacted

PC102102-1 Completed
10/21/2002
Ordering Collocation, Physical, Virtual
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Cook, Jeff
Director:
CR PM: White, Matt

Description Of Change

Revised Request: Covad requests that beginning April 1, 2003, we have the capability to check the availability of or place orders to use our DS0 tie cables for either Line Sharing or UNE/second line DSL services. This capability would not be required for existing TIE cables that are used for Line Sharing, Line Splitting or Loop Splitting in conjunction with a Common Area Splitter Collocation arrangement. These TIE cables are cabled to the splitter port either directly or through a hard-wired arrangement using the existing 410 block. Currently, we must designate the type of service we intend to provide on each cable in advance and if we find we need to re-designate the use of a specific tie cable, we are assessed a cable reclassification charge. SBC currently provides the capability to check the availability of both Line Sharing and UNE/second line DSL services. Having to declare the use of tie cables in advance greatly inhibits our ability to efficiently use our investment in tie cable.

Expected Deliverable

April 1, 2003

Original Request: Covad requests that our collocation DS0 tie cables be inventoried in both TIRKS and SWITCH/FOMS so that we can use our available inventory of tie cables for either Line Sharing or UNE/second line DSL services. Currently, we must designate the type of service we intend to provide on each cable in advance and if we find we need to re-designate the use of a specific tie cable, we are assessed a cable reclassification charge. The concept of dual inventorying has been proven in SBC and is no longer an issue. Having to declare the use of tie cables in advance greatly inhibits our ability to efficiently use our investment in tie cable.

Expected Deliverable

Dec. 1, 2002


Status History

10/21/02 - CR Submitted

10/21/02 - CR Acknowledged

10/25/02 - Qwest and CLEC (Mike Zulevic) mutually agreed to hold clarification meeting on 11/06/02

11/06/03 - Held Clarification Meeting

11/20/02 - CR Presented at CMP Meeting

12/11/02 - Qwest response e-mailed to originator

12/11/02 - Qwest response inserted in the interactive report and posted to the Web site

12/18/02 - Qwest response presented at the CMP Meeting

01/02/03 - Held additional Clarification Meeting

01/03/02 - Covad submitted revised Description of Change

01/06/03 - Qwest hosted Ad Hoc Meeting

01/15/03 - Qwest presented revised response as CMP Meeting. Attendees agreed to cross CR over to Systems. New CR number will be SCR102102-1X.


Project Meetings

01/15/03 - CMP Meeting

Cook-Qwest presented the Qwest response. White-Qwest recommended the CR be placed in Evaluation status when it is crossed over. Zulevic-Covad stated that this was fine. The CR was crossed over to systems with a status of Evaluation.

===========================================

Ad Hoc Meeting 1:00 PM (Mountain Time) / Monday, January 6, 2003

Attendees Matt White – Qwest Jeff Cook – Qwest Becky Neesen – Covad John Berard – Covad Kim Issacs – Eschelon Bonnie Johnson - Eschelon Sharon Van Meter – AT&T

Introduction of Attendees White-Qwest welcomed all attendees and described the purpose of the meeting. He explained that Qwest and Covad had had further discussions about the request over the last several weeks and that Qwest had identified several differences between Qwest and SBC’s architecture that made the request, as written, difficult to implement. After discussion of these differences, Covad had revised their description of change. White-Qwest asked Cook-Qwest to describe the network architecture differences. Cook-Qwest explained the differences between the Qwest network architecture and the SBC architecture. He stated that in order to grant the Covad request as it was currently written Qwest would have to rewire much of its existing network in order to allow CLECs using Common Area Splitter Collocation the ability to use its DSL terminations from the DSLAMs for either xDSL Unbundled Loops or Line Sharing-type services. He stated that he had some questions about Covad’s request as it pertained to their intentions to use it to provision xDSL Unbundled Loops through the data only 410 termination block.

Neesen-Covad stated that her understanding was that this request now asks that Covad will be able to look up all future and presently unused facilities on the same functionality. Cook-Qwest stated that this was his impression. Neesen-Covad asked if this only applied to collocated splitters or for both collocated and common area splitters. Cook-Qwest stated that it only applied to only collocated splitters. Neesen-Covad stated that Covad has set a soft due date of April 1, 2003. She explained that Covad is doing an internal OSS change and may end up changing the date.

White-Qwest stated that Qwest’s analysis had revealed that in order to fully meet Covad’s request there were IMA changes that needed to be made. He explined that this required the CR to be crossed over into the systems side of CMP. Berard-Covad asked for an explanation of the IMA implications. Cook-Qwest stated that Qwest was looking at doing a dual look into both inventories and implementing an up-front ability to look into both systems on a pre-order basis.

Neesen-Covad stated that Covad’s original objective was to minimize collocation costs, use existing inventory on command and reduce wiring errors. Berard-Covad asked how this would work to convert existing blocks? Jeff-Qwest stated that there had been no discussion of blocks would be converted. He explained that if a block used a common area splitter, it would not be converted.

White-Qwest asked if there were any other questions. There were none. White-Qwest thanked the participants and adjourned the meeting.

=======================================================================

Additional Clarification Meeting 2:00 PM (Mountain Time) / Thursday, January 2, 2003

Attendees Matt White – CRPM Jeff Cook – Qwest Scott Sharket – Qwest Mike Zulevic – Covad Becky Neesen – Covad

Introduction of Attendees Cook-Qwest welcomed all attendees and reviewed the request and his reason for calling the meeting. He explained the differences between the Qwest network architecture and the SBC architecture. He stated that in order to grant the Covad request as it was currently written Qwest would have to rewire much of its existing network in order to allow CLECs using Common Area Splitter Collocation the ability to use its DSL terminations from the DSLAMs for either xDSL Unbundled Loops or Line Sharing-type services. He stated that he had some questions about Covad’s request as it pertained to their intentions to use it to provision xDSL Unbundled Loops through the data only 410 termination block.

Zulevic-Covad stated that Covad was trying to establish a situation where Covad could convert existing DSO’s to line sharing without extensive delays.

Neesen-Covad stated that Qwest currently enforces a 90 day interval and completed work often includes errors.

Cook, Zulevic and Neesen discussed several potential ways to overcome the gap between the request and what was physically possible on the Qwest network. The three agreed that this request would be better implemented of the description was rewritten to be more forward looking.

Sharkey-Qwest asked if Covad was interested in this functionality for pre-order as well as ordering.

Neesen-Covad stated that they were.

White-Qwest stated that he and Cook would revise the Description of Change and forward it to Zulevic and Neesen for review.

==================================================================

12/18/02 - CMP Monthly Product/Process Meeting

Cook-Qwest described the CR and presented the Qwest response. Zulevic-Covad stated that if Qwest had any questions when it was deciding options to pursue it should contact Covad for an ad hoc meeting. Van Meter-AT&T asked that she also be included in the ad hoc meeting. She also asked how Qwest would determine the best solution. Cook-Qwest stated that Qwest would decide based on the most efficient option that fully satisfied the CLEC request. Balvin-WorldCom stated that Qwest should document all the options it is considering and why it chooses to pursue, or not pursue, each. Zulevic-Covad stated that he would like to see this option because Covad may opt to use the SCRP to fund a systems change that Qwest feels is too expensive. White-Qwest stated that he would work with Cook-Qwest and Zulevic-Covad to set up an ad hoc meeting. The CR was moved into Evaluation status.

===================================================================

11/20/02 - CMP Monthly Product/Process Meeting

Zulevic-Covad presented the CR. He stated that SBC had already allowed its wholesale customers to do a one-time conversion of DSO tie cables to both databases for no charge. Cook-Qwest stated that he had no questions. The CR status was updated to Presented.

===================================================================

CLEC Change Request – PC102102-1 Clarification Meeting 2:00 PM (Mountain Time) / Wednesday, November 6, 2002

1-877-550-8686 2213337#

Attendees Matt White – CRPM Jeff Cook – Qwest Brett Fesler – Qwest Mike Zulevic – Covad Becky Neesen – Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Zulevic-Covad reviewed the CR. He stated that there is a delay if Covad uses the existing inventory for tie pairs with line sharing because the pairs need to be reclassified from UNE to line sharing. He stated that this was because Qwest maintains two different databases for the two inventories. He continued that there was a similar problem at SBC until SBC solved by adopting a dual inventory system where the same pairs were inventoried in TIRKS and SWITCH/FOMS. He summarized that Covad wanted some way to utilize tie cables from either service without additional cost of delay to transfer.

Zulevic-Covad stated that he had recently come from a meeting with Steve Nelson. He stated Nelson was aware of this CR and would probably send someone to work on it.

Fesler-Qwest stated that he worked with Nelson’s group and was the product SME for this CR.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the November Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

January 6, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the January 15, 2002, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Revised Response - CR #PC102102-1

Qwest conducted a meeting on January 6th to discuss with the CLECs Covad’s request for dual inventory of tie cables. From this meeting, it was determined that one solution to Covad’s request is to have the IMA systems automatically check SWITCH and TIRKS to ensure that the requested pair is not in use in either system. This verification will be required on all Line Sharing, Line Splitting, Loop Splitting (excluding orders requesting the use of Common Area Splitters), and xDSL capable loops. Qwest recommends that this CR crossover to become a Systems CR. It should be understood that Qwest cannot agree to implement this solution until Qwest determines its operational functionality and/or the cost associated with it.

Sincerely,

Jeff Cook Staff Advocate – Policy & Law

===============================================================

December 6, 2002

DRAFT RESPONSE For Review by CLEC Community and Discussion at the December 18, 2002, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC102102-1

Currently, Qwest does not have an automated process in place to inventory the DS0 terminations in both the TIRKS and SWITCH systems. Duplicating DS0 terminations in both systems requires there be a mechanism to synchronize assignments for DS0 terminations between the systems. As a result, manual processes would be necessary to ensure the DS0 inventories in TIRKS match those in SWITCH.

To better understand this issue and to gain clarity around how SBC has successfully employed this capability, Qwest pursued a very high-level explanation from SBC of the SWITCH/TIRKS enhancements implemented by SBC. While on the surface it appears that SBC does maintain a dual inventory of DS0 terminations, Qwest has not yet been able to determine how SBC maintains the data in both systems to ensure inventory consistency and accuracy.

Qwest would like to move this Change Request into the Evaluation Status in order to explore the potential options available to address this request. Qwest will provide a readout of where we are at the December CMP meeting and will outline the next steps to be accomplished at the January CMP meeting.

Sincerely,

Jeff Cook Staff Advocate – Policy & Law Qwest


Open Product/Process CR PC122302-1 Detail

 
Title: Removal of DAML's to allow installation of DSL
CR Number Current Status
Date
Area Impacted Products Impacted

PC122302-1 Completed
4/15/2009
Pre-Ordering, Provisioning, Ordering Unbundled Loop - Line Share DSL
Originator: Berard, John
Originator Company Name: Covad
Owner: Boudhaouia, Jamal
Director:
CR PM: Harlan, Cindy

Description Of Change

In the 1990's many customers began to request a second line into their homes for dial up modem internet access. This created a high demand for outside plant facilities. In order to meet this demand, Qwest deployed DAML technology which multiplexed one copper line into two lines. As customers now desire the always on DLS Technology in many cases it is no longer necessary to use a DAML to serve thses customers since DSL is deployed over a single copper line.

Covad requests that Qwest remove DAML's at locations where the end users are currently only served one voice line to the premise. In addition, Covad would like Qwest to create a process where we can request the removal of a DAML when the customer is currenlty using their second line for dial up and are now seeking DSL.

DAML - Digital Added Main Line

Expected Delivery:

A process to flag DAML's that are currently only serving one voice line that is served via a DAML and allow for the removal of the DAML in the placement of the DSL order. (This order should be allowed to be placed against DAML's that have one or two working voice lines to the premise.


Status History

12/23/02 - CR Acknowledged

12/27/02 - CR posted to CMP Database

12/27/02 - Contacted customer- Covad, John Berard. John is out of office until 1/6/03. I will schedule clarification meeting with John on 1/6/03.

01/02/03 - Scheduled Clarification Meeting with Covad and Qwest SME for 1/8/02.

01/08/03 - Held Clarification Meeting with Covad and Qwest SME. John Berard advised Mike Z will present this CR at the January CMP meeting as he will not be attending the January Qwest CMP meeting.

01/09/03 - Clarification Meeting notes entered in database and provided to Covad

01/15/03 - CR presented at CMP Meeting

02/11/03 - Initial Response posted to database and emailed to Covad

2/19/03 - February CMP Meeting minutes will be posted to the Project Meeting section. Changed status to Evaluation.

3/11/03 - Posted Response to database

3/12/03 - Emailed Response to Covad

3/13/03 - Corrected Response to reflect 5 day interval and emailed to Covad

3/19/03 - March CMP Meeting minutes are posted in the Project Meeting section

4/16/03 - April CMP Meeting minutes are posted in the Project Meeting section

5/21/03 - May CMP Meeting minutes are posted in the Project Meeting section


Project Meetings

05/21/03 - May CMP Meeting Minutes Jamal – Qwest advised the State, TN and Wire Center data is available on the ICONN web site as of April 15, 2003. Covad agreed to close this CR.

04/16/03 - April CMP Meeting PC122302-1: Removal of DAMLs to allow installation of DSL

Jamal B – Qwest advised this report is available on the ICONN web site as of today. The CLEC can access by wire center/TN. This CR will move to CLEC Test and potentially close in May. John Berard – Covad asked if there is a DAML against the order and there is 1 line or DAML is removed, do we get a jep back? Jamal replied that if you place an order and line has a single line DAML the order will be jep. For the double line DAML the order will be rejected. Mike Zulevic asked what the intervals are. Jamal advised removal of a DAML is 5 days, and conditioning interval is 15 days. Mike asked if the process is going to be documented in one place with dates for each procedure. Cindy Buckmaster replied there is a link from the PCAT to the assignments document. This discussion will continue when we get to the CR that this conversation relates to.

03/19/03 - CMP Meeting Neil Houston – Qwest reported the CR has been accepted and Qwest also has initiated a CR that addresses this. Neil reported we are currently developing a process for flagging DAMLs and this will be placed on the ICONN web site by April 15, 2003. Mike Zulevic asked when the prototype will be ready. Neil advised approximately 2 weeks. We agreed to move this CR to Development status until April 15 and then move to CLEC test.

02/19/03 - CMP Meeting

Neil Houston–Qwest provided the initial response to this CR. Qwest advised we do not presently remove DAMLs for our retail customers. However, should Qwest change this policy Qwest will remove DAMLs for Wholesale customers in substantially the same time and manner. Qwest advised they are reviewing this in more detail. Qwest also described how the CLECs can use the Raw Loop Data Tool to determine the presence of a DAML. Qwest advised this CR will stay in evaluation status until our analysis is complete. An update will be provided at the March CMP meeting. Mike Zulevic-Covad clarified they would like to request the removal of DAMLs when there are 2 lines, one is disconnected and the 2nd line is used for high speed data transmission.

01/15/03 - CMP Meeting

Zulevic-Covad presented the CR. The CR moves to Presented.

Clarification Meeting January 8, 2003 1-877-561-8688 7385723# CR PC122302-1 Removal of DAMLs to allow installation of DSL

Attendees Name/Company: John Berard Covad Neil Houston Qwest Russ Urevig Qwest Brett Fesler Qwest Heidi Moreland Qwest Cindy Macy Qwest

Meeting Agenda: 1.0 Introduction of Attendees Team members introduced themselves. Neil Houston will be the lead SME on the CR

2.0 Review Requested Change John Berard Covad reviewed the CR with the team. We discussed what DAML (Digital Added Main Line) or UDC (Universal Digital channel) technology is. John and Russ explained it is a piece of network equipment that is placed on a facility. It multiplexes the TN across the facility so the provider is able to service multiple lines from one facility (analog service is provided). John explained 2 situations how this service could be used: 1st- end user that has a second line in house and provided a UDC. This 2nd line has been disconnected but is being serviced via a UDC and now the customer wants DSL. We would need to disconnect the UDC.

2nd-end user has 2nd line served over UDC and is using a dial up and now wants DSL. We would need to convert or disconnect the UDC.

Qwest confirmed to remove the UDC it would require a dispatch

Qwest should be able to identify if the customer has UDC via LFACS and Raw Loop Data Tool. It is identified as a carrier, not via a usoc on the CSR.

The team clarified this CR only applies when the end user who has a UDC is the only customer on the line. If the end user had a second line and the UDC is servicing more than one customer we could not remove the UDC. This CR would only apply to single customer situations.

Qwest asked John to provide examples / account information of customers that have UDC so we can investigate this CR and determine what the account looks like in our systems and identify the impacts of this CR. John will send to Cindy Macy-Qwest account examples. Accounts in different states would give us the best sample to investigate. We would like data on UDC that serve 1 and 1+ customers in multiple states.

Heidi Qwest asked if other ILEC/CLECs provide this data and Neil Houston advised Bell South may provide this data.

3.0 Confirm Areas & Products Impacted Unbundled Loop, Lineshare DSL, Line splitting, Distribution Feeder, Customers with existing service or service already in place at location. Pre Ordering, Ordering, Provisioning IMA EDI GUI and Bulk Extract Pre Qual Database and EDI

4.0Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation John confirmed he is looking for a process to FLAG these customers. Potentially something in Raw Loop Data tool that would identify the customer has UDC, or be able to extract data and perform a query against the data to identify the TNs that have UDC

6.0 Identify any Dependent Systems Change Requests none

7.0Establish Action Plan (Resolution Time Frame) Next steps will be for John or Covad representative to ‘Clarify this CR’ at the January CMP meeting. John advised he will not attend the January meeting but Mike Z will be there to clarify the CR. John will send to Qwest Cindy Macy examples of customers with UDC on their service so we can investigate. Qwest will meet internally and begin investigation of this CR to determine the impacts.


CenturyLink Response

For Review by CLEC Community and Discussion at the March 19, 2003 CMP Meeting

March 11, 2003

Covad Communications John Berard

SUBJECT: Qwest’s Change Request Response - CR # PC122302-1 Process to remove DAMLs off line to provide DSL to Qwest Customers

This letter is in response to Covad Communications Change Request (CR) PC122302-1. This CR requests that Qwest create a process to remove Digitally Added Main Lines (DAMLs) off of working residential lines, to enable Covad Communications to provide DSL data service to Qwest’s voice customers.

Qwest uses many different technologies to provision voice services to its end user customers. DAMLs, also known as Universal Digital Channels (UDCs) in Qwest’s Network, are one of these technologies and are deployed throughout the Network to meet growth and service demands for POTS (voice) service. The voice paths that are constructed by use of the DAMLs are local loops and the DAML is an essential element of such loops. In addition to customer requests for POTS voice service, loops derived from DAMLs can be used to provision resold, UNE-P and Internet dial-up services to CLECS.

Qwest accepts this Change Request with the conditions identified below and will remove DAMLs for wholesale customers in the same time and manner that DAML’s are removed for Qwest’s retail customers. This process will align with the process change currently being submitted by Qwest on CR PC022403-7, Perform UDC Removal for Line Shared orders at no charge to the CLEC/DLEC. DAMLs will be removed at no charge and only where the following conditions apply: - Loop used for line sharing will be non-design - DAML serves only one end user customer premise - 2 line DAML only - Only 1 voice line in service (only 1 channel is being used, the other channel is vacant) - 5 day provisioning interval will apply to the orders for DAML removal

This CR also requests that Qwest implement a process to flag DAMLs that are currently only serving one voice line. Qwest is presently investigating the appropriate means to inform the CLECs and Qwest retail of the existence of this situation. This information will be available via the ICONN web site by April 15, 2003.

Qwest requests that this CR remain in the Evaluation Status. Qwest will provide an update at the April CMP.

Sincerely,

Neil Houston Staff Advocate Policy & Law

Cc: Mary Retka

INITIAL RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003 CMP Meeting

February 12, 2003 Covad Communications John Berard

SUBJECT: Qwest’s Change Request Response - CR # PC122302-1 Process to remove DAMLs off line to provide DSL to Qwest Customers

This letter is in response to Covad Communications Change Request (CR) PC122302-1. This CR requests that Qwest create a process to remove Digitally Added Main Lines (DAMLs) off of working residential lines, to enable Covad Communications to provide DSL data service to Qwest’s voice customers.

Qwest uses many different technologies to provision voice services to its end user customers. DAMLs are one of these technologies and are deployed throughout the Network to meet growth and service demands for POTS (voice) service. The voice paths that are constructed by use of the DAMLs are local loops and the DAML is an essential element of such loops. In addition to customer requests for POTS voice service, loops derived from DAMLs can be used to provision resold, UNE-P and Internet dial-up services to CLECS.

Qwest does not presently remove DAMLs for its retail customers in order to provision digital services. However, should Qwest change this policy, Qwest will remove DAMLs for wholesale customers in substantially the same time and manner.

This CR also requests that Qwest implement a process to flag DAMLs that are currently only serving one voice line. Qwest presently has a process in place that identifies the use of DAMLs. The Raw Loop Data Tool (RLDT) indicates the presence of a DAML when queried, the Pair Gain Type field will indicate UDC where the loop is provisioned via a DAML. Additionally, telephone numbers and addresses served by a DAML will indicate UDC in the Terminal I and Cable Name fields.

Qwest requests that this CR be placed in Evaluation Status. Qwest will provide an update at the March CMP.

Sincerely,

Neil Houston Staff Advocate Policy & Law

Cc: Mary Retka


Open Product/Process CR 4302321 Detail

 
Title: CSR Form Sub Account Number Field
CR Number Current Status
Date
Area Impacted Products Impacted

4302321 Withdrawn
2/18/2000
Originator: Grigsby, Geoff
Originator Company Name: Covad
Owner: Routh, Mark
Director:
CR PM: Routh, Mark

Description Of Change

Begin placing a field on the CSR form that USW would populate with the sub-account number. This is necessary because the sub-account number is required to disconnect and USW does not tract this number, which may happen many years after the installation was completed.


Status History

11/17/99 Submitted11/19/99 Received email submission11/22/99 Logged and provided title/complete email. Received status of New – To be industry reviewed. Sent email to Geoff Grigsby on CR status.

12/15/99 During the industry team meeting questions arose as to whether there maybe a misunderstanding and the CR might be a training issue. Barbara Peterson has the action item to contact you about this one. Also, Tona is to contact Geoff. Status change “New – To be clarified”

12/30/99 Sent email to Geoff on CR status change and requested quick clarification.12/31/99 Cory Hamiltorn, Training and Services, responded to this CR to Geoff to clarify training issue.

02/02/00 Sent email to Goeff and Bogdan on CR Form update to version 04, included text of Cory’s email above, and noted the CR has a status of “New – To be clarified”

02/18/00 Status change to Cancelled – Clarification not completed. Sent email to Geoff and Bogdan that CR is cancelled per CICMP. That is, a CR is automatically cancelled if it remains in New – To be clarified for 60 or more days.


Project Meetings


Open Product/Process CR 4302410 Detail

 
Title: DSL Pre qualification Loop Length Tool
CR Number Current Status
Date
Area Impacted Products Impacted

4302410 Withdrawn
1/24/2000
Originator: Grigsby, Geoff
Originator Company Name: Covad
Owner: Routh, Mark
Director:
CR PM: Routh, Mark

Description Of Change

DSL CLECs need to know actual loop length in order to determine what speed DSL service can be provided to a Customer. Using air feet to determine these speeds is only an estimate and the carrier must submit a request and wait for USW to respond. Often the order must be downgraded but this takes time while USW investigates loop length and rejects the order and a SUPP must be submitted. Providing an interactive tool that would give actual loop length prior to submitting the order would reduce costs for both CLECs and USW by preventing the resubmission of orders.


Status History

11/17/99 Submitted

11/19/99 Received email submission11/22/99 Logged and validated. Received status of New – To be industry reviewed. Sent email to Geoff Grigsby on CR status.

12/15/99 During the industry team meeting questions arose as to whether this was a duplicate of Rhythms #4261631 "Enhancements to ADSL Loop Pre-qualification". Tona Moore was to talk to Geoff about this.

12/29/99 Sent email to Geoff on CR status with request for quick resolution.

01/24/00 Cancelled – Co-Provider. Combined with CR 426163102/02/00 Sent email to Geoff and Bogdan


Project Meetings


Open Product/Process CR PC101201-2 Detail

 
Title: Maintenance Conditioning
CR Number Current Status
Date
Area Impacted Products Impacted

PC101201-2 Completed
1/16/2002
Ordering, Repair UNE and Shared Loop
Originator: Moham, John
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM:

Description Of Change

Qwest should redefine and implement a process for conditioning when required by an ILEC Trouble Ticket in its maintenance processes or when a conditioning issue actually exists in the field but not in the Qwest LMU returns.

CLEC’s should not be required to place a (C) change order to add USOC’s to the circuit if the order is closed. A verbal authorization from the CLEC or a Qwest Technician should suffice.

This type of conditioning should be performed in a maximum of 3 to 5 business days. These circuits should be considered “Loops Out of Service” and should have the conditioning issues addressed in reduced intervals compared to the current 15 business day provisioning interval that is currently in place.

Conditioning:

- Load Coils

- Bridge Tap (Further definition is required here. Will Qwest remove all bridge tap or excessive bridge tap)


Status History

10/11/01 – CR received from John Moham of Covad

10/12/01 – CR status changed to Submitted

10/12/01 – Updated CR sent to John Moham of Covad

10/24/01 - Clarification Meeting Scheduled with Covad for 10/25/01.

10/25/01 - Clarification Meeting Held with Covad.

10/31/01 - Sent draft response dated 10/29/01 to Covad.

11/14/01 - CMP Meeting - CR was clarified with the CLECs. Qwest to review its draft response and re-issue.

12/06/01 - Revised draft response dated 11/30/01 posted to CMP database and issued to the originating CLEC.

12/12/01 - CMP Meeting: Qwest response presented to CLECs, agreement obtained to change status to CLEC Test

12/28/01 - Formal response dated 11/30/01 issued to CLECs

01/16/02 - January CMP meeting. CLECs agreed there had been no new issues and agreed to close this CR. CR Status changed to "Completed"


Project Meetings

10:00 am (MDT) / Thursday, Oct 25th, 2001 Alignment/Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PC101201-2- Maintenance Conditioning Request John Moham, jmoham@covad.com , Covad Larry Gindlesberger, Lgindles@covd.com, Covad Nancy Hoag, nhoag@qwest.com,Qwest Cindy Buckmaster, cbuckma@qwest.com, Qwest Brett Fesler, bfesler@uswest.com , Qwest Cliff Dinwiddie, cdinwid@qwest.com, , Qwest Ann Danielsen, aldanie@qwest.com, Qwest Michael Belt, mbelt@qwest.com, Qwest Introduction of Attendees Introductions, Ann Danielsen should be in attendance (Repair) - Courtesy Copy Review Requested (Description of) Change 1. Qwest should redefine and implement a process for conditioning when required by an ILEC Trouble Ticket in its maintenance processes or when a conditioning issue actually exists in the field but not in the Qwest LMU returns. (Accuracy of the Raw Loop Data Tool) i.e. - Loop qual, ADSL/RLD - check loop makeup = 10K no loads. Can’t get signal, have tech test for load and find that it is loaded. This adds 15 days to the interval at commitment date. This is on line sharing and IDSL (ISDN Capable Loop).

2. CLEC’s should not be required to place a (C) change order to add USOC’s to the circuit if the order is closed. A verbal authorization from the CLEC or a Qwest Technician should suffice.

No change order for conditioning during the maintenance process

3. This type of conditioning should be performed in a maximum of 3 to 5 business days. These circuits should be considered “Loops Out of Service” and should have the conditioning issues addressed in reduced intervals compared to the current 15 business day provisioning interval that is currently in place.

Change interval from 15 to 5 days only on maintenance process

Conditioning: - Load Coils - Bridge Tap (Further definition is required here. Will Qwest remove all bridge tap or excessive bridge tap) Not All but maximum to 6kf Confirm Areas & Products Impacted Areas: Ordering, Repair Products: Unbundled Loop, UNE, Loop Confirm Right Personnel Involved Cliff Dinwiddie - Lead Brett Fesler - Assist Nancy Hoag/ Cindy Buckmaster - Assist Ann Danielsen - Assist (Repair) Michael Belt - Coordinate CR Cradle to Grave Identify/Confirm CLEC’s Expectation Expectations of the CR are understood. Identify any Dependent Systems Change Requests N/A Establish Action Plan (Resolution Time Frame) Majority of the request is within “Loop Conditioning Refund Draft” being reviewed by CLEC community. Nancy Hoag transferring to Training, Cindy Buckmaster to Facilitate

Cliff Dinwiddie to formulate DRAFT Qwest Response prior to dry-run meeting November 6, 2001 and present at CMP meeting November 14, 2001.


CenturyLink Response

11-30-01

John Moham TAC Manager, ILEC Repair Covad Communications

CC: Bill Campbell Debra Smith Dennis Pappas Bernadette Derlein Betty Heid

This letter is in response to your CLEC Change Request Form, number PCCR101201-2 dated October 11, 2001 – Maintenance Conditioning.

Qwest’s loop conditioning process is standard across both the unbundled loop family of interconnection products and the shared loop family of interconnection products.

Request:

1. Qwest should redefine and implement a process for conditioning when required by an ILEC Trouble Ticket in its maintenance processes or when a conditioning issue actually exists in the field but not in the Qwest LMU returns. (Accuracy of the Raw Loop Data Tool) i.e. - Loop qual, ADSL/RLD - check loop makeup = 10K no loads. Can’t get signal, have tech test for load and find that it is loaded. This adds 15 days to the interval at commitment date. This is on line sharing and IDSL (ISDN Capable Loop). Qwest Response:

CLECs can use the ADSL Loop Qualification and RLD tools, in addition to other IMA based loop qualification tools, to identify the existence of Load Coils and/or Excessive Bridged Tap prior to placing an order. Qwest will always attempt to assign facilities that do not require conditioning. However, there may be some situations where the only way to fulfill a request requires Qwest to condition the loop. Qwest will not condition a loop without CLEC approval.

To simplify the process, CLECs have the option to pre-approve conditioning by entering a ‘Y’ in the SCA field of the LSR. If this field carries the ‘Y’, all Load Coils and Bridged Tap will be removed, with the exception of stub cable. The pre-approval option provides the following benefit: - If conditioning is required, the LSR will flow through the provisioning process without delay, - If the pre-approval is not included on your LSR and conditioning is required, Qwest will reject your LSR and you will need to submit a new LSR.

Pre-Approval inclusion will not have any negative impacts on your order. Qwest will still attempt to locate facilities that do not require conditioning. CLECs can request the standard interval and if Qwest can assign the loop to facilities that do not require conditioning, the requested interval will be honored. Conditioning charges will only apply if conditioning actually occurs.

Therefore, assuming the CLEC is ordering a non-loaded loop (LX-N – 2/4 wire non-loaded, LXR- - ADSL Capable, AD-- - ISDN Capable, ADU- - xDSL-I Capable):

- If the LSR is submitted with a “Y” in the SCA field, Qwest will attempt to assign a facility free of Load Coils and Bridged Tap. If Load Coils and/or Bridged Tap is present on the facility assigned, Qwest will dispatch to ensure that the circuit will meet the parameters specified by the CLEC in the LSR. - If the LSR is submitted without Conditioning authorized (with an “N” in the SCA field or with the SCA field blank), Qwest will attempt to assign a facility free of Load Coils and excess Bridged Tap. If Load Coils and/or excess Bridged Tap is present on the facility assigned, Qwest will reject the LSR advising the CLEC that conditioning is required and the CLEC will return to the step above. - If the LSR is submitted without Conditioning authorized (with an “N” in the SCA field or with the SCA field blank), Qwest will attempt to assign a facility free of Load Coils and excessive Bridged Tap. If such a facility can be found, it will be assigned and the request will be processed. In this situation, the facility assigned can have Bridged Tap on it that does not exceed the limits identified by the NC/NCI Code specified by the CLEC in the LSR. - If the CLEC requires that additional Bridged Tap be removed (i.e. the CLEC now wants Qwest to condition the loop), that request will come through the Service Delivery Center. The CLEC will need to submit an LSR authorizing Bridged Tap Removal by entering a ‘Y’ in the SCA field. The standard 15 Business Day Conditioning Interval will apply. - If Load Coils and/or excessive Bridged Tap are not identified by Qwest as present on the facility assigned, and the proper NC/NCI code were used to indicate a Non-Loaded facility, Qwest should be able to identify their presence in Test & Turn-Up. If the Test doesn’t indicate the presence of Load Coils and/or excessive Bridged Tap, and the loop is subsequently turned over with Load Coils and/or excessive Bridged Tap on it, Qwest will handle the issue in the repair environment. This process will not require the CLEC to submit a supplemental LSR. This repair process will be completed within 5 Business Days. In this scenario: - If the CLEC originally entered a ‘Y’ in the SCA field of the LSR, Qwest will remove any Load Coils and all Bridged Tap (see question 3 below). - If the CLEC originally entered a ‘N’ in the SCA field of the LSR or left the SCA field blank, Qwest will remove only the Load Coils and excessive Bridged Tap. Bridged Tap that doesn’t interfere with the services specified in the NC/NCI Code combination will not be removed. - No charges will be assessed to the CLEC.

Request:

2. CLEC’s should not be required to place a (C) change order to add USOCs to the circuit if the order is closed. A verbal authorization from the CLEC or a Qwest Technician should suffice.

No change order for conditioning during the maintenance process

Qwest Response:

As stated above, CLECs will not be required to authorize the removal of Load Coils and/or excessive Bridged Tap inadvertently missed by Qwest. CLECs are still required to request conditioning if additional Bridged Tap removal is requested and can do so per the process previously defined.

Request:

3. This type of conditioning should be performed in a maximum of 3 to 5 business days. These circuits should be considered “Loops Out of Service” and should have the conditioning issues addressed in reduced intervals compared to the current 15 business day provisioning interval that is currently in place.

Change interval from 15 to 5 days only on maintenance process

Qwest Response:

As stated above, if the circuit was incorrectly conditioned by Qwest, it will be corrected within 5 business days. If the CLEC would like additional Bridged Tap removed, the standard 15 Business Day Conditioning Interval will apply.

Request:

4. Conditioning: - Load Coils - Bridge Tap (Further definition is required here. Will Qwest remove all bridge tap or excessive bridge tap)

Qwest Response:

If requested by the CLEC (with a ‘Y’ in the SCA field), Qwest will remove all Bridged Tap (except stub cable). If Conditioning was not requested, Qwest will ensure that the circuit meets the acceptable standards of the NC/NCI codes requested and will remove the amount of Bridged Tap necessary to meet those standards.

Request:

5. Additional questions were asked during the clarification session. These questions and answers are provided collectively in this section.

a. Where are the processes documented for the conditioning interval and the maintenance process? - The conditioning interval can be found in the Service Interval Guide. More information regarding the process associated with intervals as they apply to your request can be found in the Product Catalog (PCAT) at: http://www.qwest.com/wholesale/pcat/interconnection.html - Additional information regarding Maintenance processes can also be found in the PCAT at: http://www.qwest.com/wholesale/pcat/interconnection.html

b. How are identified data-base errors corrected? A ‘yellow’ response on the RLD or ADSL Loop Qual Tool does not prohibit the CLEC from ordering the service. Upon receipt of the request, Qwest will attempt to assign an adequate facility. If necessary, a Technician will be dispatched to resolve discrepancies in facility record. Once those discrepancies are resolved, the Qwest Technician is responsible for providing an update to the database. As those discrepancies are resolved, the CLEC request can be completed.

Two tools have been deployed to provide a vehicle for Qwest Technicians to get corrected information back to the data-base.

They are: 4.1 Internet A url has been deployed so that field forces can access the Qwest Web Site. This site is used to update facility data, based on actual measurements. This is an internal url and will be used by Qwest personnel only. 4.2 FAX A form has been developed that allows a technician to note the same information that is input into the Qwest Web Site. The form should be filled out as the readings are being taken. At the end of the day, hand the form(s) to your supervisor. The supervisor, or designee, will fax the forms daily.

This, too, is an internal process only. As the Qwest employee is the only person updating the database, documentation regarding the process is not publicly provided.

Sincerely,

Cindy Buckmaster Group Manager – UBL Product Management


Open Product/Process CR PC101201-1ES Detail

 
Title: Shared Loop Data Parameters
CR Number Current Status
Date
Area Impacted Products Impacted

PC101201-1ES Denied
12/12/2001
Repair Unbundled Loop, Line Shared Loop
Originator: Moham, John
Originator Company Name: Covad
Owner: Dinwiddie, Cliff
Director:
CR PM: Thomte, Kit

Description Of Change

Qwest representation should work with the CLEC community to develop parameters for the support of DSL on Shared Loop circuits.

These test results should be standardized utilizing the CEMR MLT test and 77S test unit utilized by Qwest Central Office Technicians.

These standards should also drive processes to repair existing loops or LST (Line and Station Transfer) working voice but not in service data loops to acceptable loops out of the end users serving terminal. They should also drive process implementation for Qwest Network or Complex Network Service technicians to be dispatched out to address the identified loop quality issues.

Loop Standards on:

Capacitance

Resistance

DC and AC signatures

Voltage


Status History

10/11/01 - CR Received from John Moham of Covad

10/12/01 - CR status changed to Submitted

10/12/01 - Updated CR sent to John Moham of Covad

10/22/01 - Clarification Meeting held with Covad.

11/14/01 - CMP Meeting - CR was clarified with the CLECs. Qwest to prepare its draft response

11/28/01 - Received draft test parameters from Covad (Proprietary information)

12/05/01 - Draft response dated 12/5/01 posted to CMP database.

12/07/01 - Draft response issued to the originating CLEC. Status changed to Presented.

12/12/01 - CMP Meeting: Qwest response presented to CLECs, change request was denied.

12/28/01 - Formal response dated 12/5/01 issued to CLECs

01/11/02 - Qwest revised response superceding Qwest Response dated 12/05/01 posted to the CMP database

01/14/02 - Formal Escalation received from Covad, status changed to "Escalated"

01/15/02 - Qwest response sent acknowledging receipt of Formal Escalation from Covad (PC101201-1-E04).

01/15/02 - Escalation posted to the web: http://qwest.com/wholesale/cmp/escalations_dispute.html

01/15/02 - All CLECs notified this CR has been escalated

01/16/02 - January CMP meeting. Planned readout agenda item was canceled due to CR being escalated on 1/14/02

01/22/02 - Qwest issued binding response to Escalation E-04 dated 01/22/02 to Covad

01/22/02 - Qwest posted binding response to Escalation E-04 dated 01/22/02 to the web: http://qwest.com/wholesale/cmp/escalations.html

02/20/02 - February CMP meeting: Status update provided. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

03/20/02 - March CMP Meeting: Status update provided to CLECs. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/17/02 - April CMP Meeting: Status update provided to CLECs. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

05/15/02 - May CMP Meeting: Qwest advised that the CR was still in an Escalated status.

06/19/02 - June CMP Meeting: Qwest advised that the CR was still in an Escalated status.

07/08/02 - Per the agreement reached with the CLECs during the June Product and ProcessCMP meeting regarding escalated status this CR will carry the appropriate status prior to the escalation


Project Meetings

1:00 p.m. (MDT) / Monday, Oct 22nd, 2001 Alignment/Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PC101201-1- Shared Loop Data Parameters John Moham, jmoham@covad.com , Covad Larry Gindlesberger, Lgindles@covd.com, Covad Sheila Hoffman, shoffman@covad.com ,Covad Michael Lanoue, mlanoue@qwest.com, Qwest Brett Fesler, bfesler@uswest.com , Qwest Steve Hilleary, shillea@qwest.com , Qwest Deborah Heckart, dheckar@qwest.com , Qwest Michael Belt, mbelt@qwest.com, Qwest Introduction of Attendees Introductions Review Requested (Description of) Change Shared Loop Data Parameters – Qwest representation should work with the CLEC community to develop parameters for the support of DSL on Shared Loop circuits. These test results should be standardized utilizing the CEMR MLT test and 77S test unit utilized by Qwest Central Office Technicians. These standards should also drive processes to repair existing loops or LST (Line and Station Transfer) working voice but not in service data loops to acceptable loops out of the end users serving terminal. They should also drive process implementation for Qwest Network or Complex Network Service technicians to be dispatched out to address the identified loop quality issues. Loop Standards on: - Capacitance - Resistance - DC and AC signatures - Voltage Actual Testing of the lines doesn’t incorporate several tests they would like to occur. Detailed list to be provided by John Moham Confirm Areas & Products Impacted Area: Repair, Additional Defined Testing Products: Unbundled Loop, Line Sharing, UNE, Loop Confirm Right Personnel Involved Michael Lanoue indicated Ann Danielsen might need to be brought in depending on Qwest response to Covad request. If the Pre-qualification test package accepted, Terry Meehan might also need to be involved if dispatch is required. Identify/Confirm CLEC’s Expectation General Ideas of the parameters of the Loop testing which led to Quality issues. List of specific tests to be provided by John Moham by COB, Wed Oct 24, 2001. John would like to set up trial for developing testing parameters. Michael indicated other test that might be available or already in place(Loop length, JEP and Feedback Quality) but might have cost implications if implemented. Identify any Dependent Systems Change Requests N/A Establish Action Plan (Resolution Time Frame) Michael Lanoue to provide DRAFT response a couple days after receipt of Testing List (Criteria) provided by John Moham on Wednesday, Oct 24, 2001. This response to be provided/discussed at the November CMP Meeting to be held November 14, 2001.


CenturyLink Response

January 11, 2002

John Moham Covad Communications TAC Manager - ILEC Repair Denver COE Line Sharing Data Parameters

CC: Kathleen Lucero Steve Hilleary Deborah Heckart Brett Fesler Mike Lanoue

This letter supercedes Qwest Response dated 12/05/01 that responded to your CLEC Change Request PC101201-1 dated 10/12/01 Shared Loop Data Parameters.

This Change Request asks Qwest to engage in a collaborative effort with CLECs to establish testing provisioning and repair parameters for DSL on shared loops including: - a minimum set of standards; - standardized testing utilizing CEMR MLT and 77S test sets; - a loop repair process that requires a LST if the provisioned loop does not meet CLEC standards; and - a loop repair process that dispatches a Qwest technician if the loop has quality issues. Minimum Testing Parameters

Qwest is disinclined to develop a minimum set of provisioning and repair standards that would “qualify” a particular facility to carry Line Sharing for two reasons: - Difficulty in developing a “standard”. This is accentuated by the varied requirements of the multiple vendors, types of DSL, and quality of service deployed by CLECs. Developing the test parameters for an “acceptable” circuit for all CLECs would be a time and resource consuming activity for all parties and one not prudent to do in light of the following. - The minimum standards for provisioning and repair of a metallic loop are already being developed in an industry forum, American National Standards Institute (ANSI) T1E1.3. In order to prevent duplicative development and implementation efforts, Qwest believes the ANSI forum to be the most appropriate to address this issue. While Qwest denies this request to work independently with the CLECs on a set of minimum standards, Qwest is more than willing to work collaboratively with the CLECs and other industry participants to develop a set of national standards in the appropriate industry forum.

Additionally, Qwest Technical Publication 77406 Interconnection - Shared Loop outlines the minimum set of transmission standards that a facility can support. The transmission characteristics defined in the technical publication provide the CLEC with information regarding the minimum requirements that a facility must support to be delivered to a CLEC based on the Network Channel and Network Channel Interface (NC/NCI) codes that the CLEC includes on the Local Service Request (LSR). CEMR MLT and 77S Test Sets

In the clarification call for this Change Request, Covad indicated it would like to utilize Customer Electronic Maintenance and Repair (CEMR) Metallic Loop Test (MLT) for pre-provisioning xDSL loop qualification. Qwest has already addressed this issue in 271 workshops. CEMR MLT is a repair tool that provides CLEC testers in the repair process the capability to evaluate transmission characteristics of a metallic loop connected to a Qwest switch.

The reasons presented in the workshops for Qwest’s objection to using MLT in a provisioning process are twofold. First, MLT is an intrusive test that will disrupt voice services. While this is not a concern for repair scenarios, it is a real concern when MLT is being triggered electronically through CEMR. Secondly, to ensure the protection of Customer Proprietary Network Information (CPNI), MLT has a front end edit that limits access for a specific loop to the Local Exchange Carrier of record for that loop. In pre-order activity, MLT will not allow CLECs to access metallic loops it does not “own”.

However, in the Pre-Ordering process, Qwest can and does provide facility characteristic information to CLECs based on facility records via the Raw Loop Data Tool (RLDT). The data included in the RLDT is the same underlying data that Qwest utilizes to qualify loops for its retail xDSL product offerings. This data can be used, much the same way Qwest uses it, to qualify loops for CLEC xDSL services.

During the provisioning process to deliver shared loop products to CLECs, Qwest does use test sets, including the 77S, to identify load coils on a loop. Additionally, Qwest tests the electrical continuity of the data path for every shared loop provisioned for CLECs prior to circuit delivery.

Once the shared loop is provisioned for the CLEC, the CLEC can perform a MLT through CEMR.

Loop Repair LSTs

The Change Request indicates, "These standards should also drive processes to repair existing loops or Line and Station Transfer (LST) working voice but not in service data loops to acceptable loops out of the end users serving terminal." Qwest believes that existing repair processes sufficiently care for this concern. Again, Qwest delivers shared loop circuits according to the parameters outlined in Technical Publication 77406. Please review the response to Change Request PC101201-2 regarding loop conditioning during the repair process.

Loop Repair Dispatch

Qwest will dispatch a technician to a network DMARC at a customer premises only if trouble is isolated to the Outside Plant portion of the Qwest network. Qwest will not agree to dispatch its technicians unless the circumstances of a trouble ticket dictate such activity.

Sincerely,

Cliff Dinwiddie Senior Manager Global Wholesale Product Marketing


Open Product/Process CR PC102301-1 Detail

 
Title: Implementation of Covad’s IVR Testing Tool by Qwest for use in the field provisioning and repair process
CR Number Current Status
Date
Area Impacted Products Impacted

PC102301-1 Denied
9/18/2002
Repair, Field Provisioning Stand Alone Loops
Originator: Zulevic, Michael
Originator Company Name: Covad
Owner: Gianes, Tim
Director:
CR PM: Thomte, Kit

Description Of Change

IVR is an automated voice response (dial-in) system by which Qwest technicians can perform a one way “pre-test” of a loop prior to formal cooperative (two way) acceptance testing with Covad. IVR takes the Qwest tech through the same process as the two way test and will feed back results to the Qwest tech. If the loop tests good, the Qwest tech would then perform the coop test and loop turn-over with Covad. If a fault is discovered during the IVR test, the Qwest tech would then have the opportunity to correct the deficiency prior to turn-over to Covad. This process has been implemented in another ILEC and Verizon specifically asked for its use to improve their provisioning efficiency as part of its recent recovery efforts in NYC. Eventually, the goal will be to eliminate the need for cooperative testing, saving both Covad and Qwest time and resources, improving operational efficiencies for both.


Status History

10/23/01 - CR Received by Minda Cutcher of Covad Communications

10/23/01 - CR status changed to Submitted

10/23/01 - Updated CR sent to Minda and Susan Early

11/01/01 - Clarification Meeting Held with Covad.

11/14/01 - CMP Meeting - CR was clarified with the CLECs. Qwest to prepare its draft response.

12/03/01 - Additional clarification questions submitted to Covad via e-mail

12/05/01 - Received responses to e-mail questions

12/05/01 - Draft response dated 12/03/01 posted to CMP database and issued to the originating CLEC. Status changed to Presented.

12/12/01 - CMP Meeting: Qwest response presented to CLECs, agreement obtained to change status to Development. Covad to supply answers to balance of questions listed in response.

12/28/01 - Formal response dated 12/3/01 issued to CLECs

01/03/02 - Kick-off meeting for trial implementation held between Covad and Qwest

01/04/02 - Meeting minutes for Kick-off meeting issued to Covad

01/10/02 - E-mail update from Covad on Kick-off meeting actions

01/11/02 - E-mail from Qwest responding to Covad

01/16/02 - January CMP meeting. Qwest provided a status update to the CLEC community. CR Status remains in "Development"

01/29/02 - E-mail from Qwest providing update to Covad

02/06/02 - Reply e-mail from Covad

02/07/02 - Qwest response e-mail to Covad

02/13/02 - E-mail from Covad advising change of personnel

02/13/02 - E-mail response, Qwest waiting for new Covad contact to move forward with trial.

02/20/02 - February CMP meeting: Status update provided to CLEC community. Michael Zulevic will replace Minda Cutcher as the Covad representative for this CR. Qwest are waiting for Covad’s response to two questions before moving on with the trial. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/22/02 - Information E-mail from Qwest to new Covad CR owner

02/22/02 - Return E-mail from Covad

02/27/02 - Status report from Qwest posted in CMP database

03/20/02 - March CMP Meeting: Status update provided to CLECs, CR status to remain in "Development". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/22/02 - E-mail from Covad asking to begin trial without providing test parameters associated with IVR capability to Qwest

03/29/02 - Qwest left a voice mail with Covad informing them of an April 15th start date for the trial

04/17/02 - April CMP Meeting: Status update provided to CLECs. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/25/02 - Covad and Qwest met to discuss the status of the trial, meeting minutes from the session were posted to the data base pending approval from participating parties

05/06-02 - Qwest sent email to COVAD indicating that Qwest had begun the trial with COVAD

05/15/02 - May CMP Meeting: Qwest advised that they started the trial using Qwest historical data. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/19/02 - June CMP Meeting: CR status remains in "Development". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07-09-02 - July CMP session will have an update of status to reflect Qwest approach

07/17/02 - July CMP Meeting: CR status remains in "Development". Meeting minutes posted to this CR's Project Meetings section.

08/21/02 - August CMP Meeting: CR status remains in "Development". Meeting minutes posted to this CR's Project Meetings section and CMP Web site

09/11/02 - Sent Covad Revised Response

09/18/02 - September CMP Meeting: CR status changed to "Denied". Meeting minutes posted to this CR's Project Meeting section and CMP Web site


Project Meetings

09/18/02 September CMP Meeting Qwest (Gianes) reviewed the request and provided high level information regarding the rationale for the denial. Covad (Cutcher) indicated that Covad was very disappointed in the outcome of this CR. Things seemed to be progressing well and now Qwest is the only ILEC that is unwilling to use the IVR test tool. Worldcom (Balvin) inquired if this was an attempt to reduce resources and if so why would Qwest not be in favor of this approach? AT&T (Spangler) inquired if this was denied based on resource allocation? Qwest indicated that they reviewed statistics prior to the trial and during the trial of IVR and did not see any tangible improvements. A discussion ensued regarding Copper Max and IVR. Qwest (Beck) indicated that Qwest had selected a tool and was moving forward with the strategy. Covad indicated that this CR had been in the works for a while and Copper Max had not been discussed at that point. Long term Covad thinks this tool provides a more efficient process for Qwest, Covad seems to be getting mixed messages. Qwest replied that deploying Copper Max expands internal test capability that creates improved test isolation benefiting a broader base of the CLEC community and is not limited to a single CLEC. Covad viewed the decision as a regulatory response to an issue and would welcome a discussion with anyone from Qwest. This CR was updated to "Denied" status.

08/21/02 - August CMP Meeting Minutes Qwest (Gianes) indicated that a revised document had been provided, the document is being reviewed by the Network organization. A point of concern has been raised regarding the lack of information regarding the test parameters behind IVR. COVAD (Zulevic) inquired if the agreement was being expanded beyond provisioning? Gianes indicated that in the last session with COVAD (Mindy and John) agreed not to go beyond provisioning at this time. This CR will remain in “Development” status.

07/17/02 - July CMP Meeting Minutes: Qwest (Gianes) provided an update indicating that both COVAD and Qwest were happy with the results of the trial. Qwest would like to roll out the process within the fourteen states. Two regions have been trained so far, but actual implementation is pending legal approval. This process would be not be applicable to repair. This CR will continue with a status of "Development" Revised response will be provided prior to the next meeting.

To: "Berard, John" cc: "Zulevic, Michael" , "Cutcher, Minda" , "Linda Hendricks" , "Deni Toye" , "Mary Pat Cheshier" , "Alan D Braegger" , Michael Raleigh/Mass/USWEST/US@USWEST, "Kurtis L Preston" , "Rick Mabry" , "Diane L Diebel" , Kathleen Thomte/Mass/USWEST/US@USWEST

Subject: Re: IVR Trial with Covad

John, I still have not received the list of service orders from you that you had agreed to send for this trial. This list was to enable both company's to work from the same "database" for tracking purposes and determination of final results. I understand that the list may require updating on a weekly basis due to the service order intervals. That is not a problem. Would you also let me know what has happened regarding providing Qwest the On Time Performance (OTP) report we discussed. It was our impression that this was one of your critical measures of success in previous deployments of the IVR tool to other ILECs. Last week we decided to move forward without the service order list from Covad by asking Mike from the QCCC to pull a 30 day historical and future DD report. This will assist Kurt and Rick in determining which higher volume wire centers to focus on within the geography we discussed as we progress from the limited "dry run" with a few orders to the full scope of the trial. At this point we will use the future service order data we pulled as our baseline going forward to track and determine usage, IVR performance, etc. Also, Alan from the Qwest field staff, has developed a more refined flow chart which we have shared with the field director for use by the technicians. This provides an accurate and more straightforward chart of what the field technicians will experience when using the Covad IVR. I will be glad to share at our next joint status meeting. Please contact me regarding when you will be able to provide the future service order list and the OTP report at your earl

04/25/02 To: "Berard, John" cc: "Cutcher, Minda" , "'tgianes@qwest.com'" , "Zulevic, Michael" , "Deni Toye" , "Alan D Braegger" , lkhendr@qwest.com, Kathleen Thomte/Mass/USWEST/US@USWEST, "Rick Mabry" , "Kurtis L Preston" , "Mary Pat Cheshier" , Michael Raleigh/Mass/USWEST/US@USWEST, "Diane L Diebel"

Subject: Re: QWEST Trial of Covad IVR Loop Test Tool

Everyone, Here is a what I believe we agreed to on todays call: The trial will start Monday April 29th as scheduled. All parties agree that since Covad orders Coordinated Installation with Cooperative Test only, Qwest will utilize the IVR test during the Cooperative Testing portion of the test and turn up. As the field technicians become more comfortable with the IVR tool they have the option of utilizing the IVR at any point during their installation activity as long as it does not jeopardize Qwest meeting the Coordinated Install timeframe. Qwest will begin the trial by having a technician access sample Covad service orders and run through the IVR process. The technician will provide the Qwest team immediate feedback regarding their experience. John will send to Tim a list of pending Covad service orders so both Covad and Qwest will be working from the same list. This is critical in providing accurate results at the end of the trial. John is still pursuing providing an On Time Performance (OTP) report to Qwest since this is where Covad indicates there will be a significant benefit. John agrees a report of this type will be a valuable measure of success at the end of the trial. Minda confirmed that Qwest is the only ILEC with whom Covad orders Coordinated Installs. Based on the nature of Coordinated Install orders, Qwest performs extensive workstep completion confirmation prior to a field tech being dispatched to the premise. Minda agrees that because Qwest applies a very structured approach to Coordinated Installs this may minimize the extent of the benefit to Qwest that other ILECs have experienced with the IVR. Everyone also agrees that Qwest will continue to perform and document their required Core tests and follow established Coordinated testing agreements as they do today. Utilizing the IVR does not negate any current processes. Minda also agrees that if Qwest experiences a Fail situation via the IVR but successfully has passed standard Qwest core tests in the same area, Qwest will not default to the Covad test result but will contact Covad and work through the variance on a case by case basis as they do today. Tim will update the Trial Document to specify that Qwest will only enter the numeric portion of the PON number when accessing the IVR tool. Tim will schedule a follow up with the QCCC and the field to confirm the tracking spreadsheet detail Qwest will utilize to provide trial results on the orders submitted by Covad. Tim will schedule a joint meeting with Covad within the first 2 weeks of the trial to discuss progress and address concerns and opportunities.

I have tried to capture our conversation acccurately and completely and ask that you send me any corrections to what I have stated by end of day tomorrow. If there are no corrections or after making corrections I will ask that Kit Thomte incorporate these notes into our ongoing tracking of the original CR.

Tim Gianes 303 703-2199 03/22/02 - E-mail from Covad asking to begin trial without providing test parameters associated with IVR capability to Qwest

From: "Michael Zulevic" To: "Todd Meade" , "Michael Keegan" Cc: "Berard, John" Subject: IVR documentation Date: Fri, 22 Mar 2002 11:16:38 -0700

Todd,

Per our discussion yesterday, Covad does not see the need to provide our test perameters associated with our IVR capability to Qwest. Covad considers this to be proprietary information. As I stated yesterday, I would be willing to certify that our test perameters are within the technical specifications of your UNE loop offering. Once again, the IVR capability is in use in Verizon and the capability is now being deployed in SBC. BellSouth is also working with us to deploy the capability there as well. Covad has not been "required" to provide technical documentation to any of these ILECs as a condition of use. It must be understood that the IVR is a test capability, developed for use by Covad, that we are agreeing to allow Qwest and other ILECs to use, to assist them in their provisioning process. If, after a joint trial is completed, Qwest determines they have no need for this test capability, there is no obligation to continue with it's use. I would like to begin the trial as soon as possible, as trials with other ILECs have resulted in a significant improvement in the delivery of UNE loops. Please let me know if this informaion is sufficient to start the trial, and when we can get it started.

Thanks,

Michael Zulevic Director- External Affairs Office(520)575-2776 Cel(303)884-5657 Fax (520)575-2785

02/27/02 - Status report from Qwest posted in CMP database

Subject: Covad IVR Meeting 2/27/02 Date: Wed, 27 Feb 2002 16:12:46 -0700 From: "Tim Gianes" To: Todd Mead CC: "Frederick M Aesquivel Iii" Todd, I participated on a call today with Michael Zulevic and John Berard with Covad. John was involved in the deployment of the Covad IVR to Verizon. We discussed the 2 pending requests which were: - Utilization of the Covad circuit ID instead of the PON to activate the IVR - Full disclosure of specific tests activated (by circuit type) within the IVR and the related test parameters set for each Pass/Fail decision

John felt he could locate the IVR development document which should contain this information and send me a copy. Michael questioned the need for Qwest to have this data. I explained that this would allow us to insure that Covad & Qwest agree on the standard tests and test parameters utilized by the IVR before requiring field technicians to accept the Pass/Fail status from the IVR. It will be very beneficial to the field and center technicians to understand what the IVR is running, not just the net result, so they can better determine what action to take. Having the test detail will also promote buy-in from the field to actively use the IVR tool if they see the potential value of the test results.

I have agreed that Qwest will utilize the PON# which is present on the Worddoc. Micheal stated that the PON numbers were unique and would not cause Qwest to inadvertently intrude on another Covad circuit in error. Since Covad currently does not always provide their circuit ID on the LSR, requiring this would create an unnecessary step for Covad. Despite Qwest's preference to use the Covad circuit ID there is no compelling system or process related reason to not use the PON# as preferred by Covad. If using the PON becomes a problem, the process will have to be amended to revert to the circuit ID.

I am awaiting delivery of the detailed IVR document from Covad. Upon receipt, review, and agreement on tests & test parameters we will set a definite trial start date. Regarding the trial, I confirmed with Michael that Denver metro was the agreed location and 60 days the agreed trial duration. I also mentioned, and they concurred, that at the end of the trial we would gather performance results data as defined in my original response to the CR and determine future action.

Tim Gianes 303 703-2199

02/22/02 Return E-mail from Covad

Subject: RE: CR Interactive Report Date: Fri, 22 Feb 2002 20:02:53 -0700 From: "Michael Zulevic" To: "Todd Mead" CC: "Gianes, Timothy" Todd, I am looking for answers to your questions and sent an email to Tim earlier today asking about your availability for a clarification call this Weds. with one of our people who facilitated the implementation in Verizon. Hopefully, we can get this back on track real soon. Thanks, Michael Zulevic Director- External Affairs Office(520)575-2776 Cel(303)884-5657 Fax (520)575-2785

02/22/02 Information E-mail from Qwest to new Covad CR owner

From: Todd Mead [mailto:tmead@qwest.com] Sent: Friday, February 22, 2002 12:02 PM To: mzulevic@Covad.COM Cc: Gianes, Timothy Subject: CR Interactive Report Mike, As promised, here is the link to our interactive report where you can see the latest on your CR(s). This report is updated every 2 days. http://qwest.com/wholesale/cmp/changerequest.html (click on the Product/Process link) As regards to PC102301-1 IVR Testing Tool, there are two outstanding issues. Qwest is waiting for Covad to supply a response to these issues before we move on with the trial. The issues are: - Please provide the test detail behind each of the IVR options by product and respond in particular to the discrepancy on the loop length issue. - Would Covad be able to provide their circuit ID on every order so we could use that rather than the PON? You may already provide the circuit ID already but wanted verification it is standard procedure to include it on all ISRs. After your meeting with Mindy, please let me know if you want me to set something up with Qwest personnel. Thanks Todd

02/13/02 E-mail response, Qwest waiting for new Covad contact to move forward with trial.

From: Tim Gianes 02/13/2002 03:18 PM To: "Cutcher, Minda" Subject: RE: IVR Trial Status (Document link: Tim Gianes) Thanks for the heads up Mindy. I hope you are moving into something else you will be enjoying, Thanks for helping and providing the information you have. I will await the decision fom Covad on who our contact will be and will look for the requested data from that person going forward. Good luck! Tim Gianes 303 703-2199

02/13/02 E-mail from Covad advising change of personnel

From: "Cutcher, Minda" on 02/13/2002 12:52:26 PM To: Tim Gianes Subject: RE: IVR Trial Status Tim, As a result of some internal reorgs at Covad, someone else is going to be driving this forward with you. It will likely be Mike Zulevik, but I will keep you posted. It will take us a few weeks to transition. Mindy

02/07/02 Qwest response e-mail to Covad

Subject: RE: IVR Trial Status From: Tim Gianes 02/07/2002 09:16 AM To: "Cutcher, Minda" cc: Todd S Mead , Michael Keegan , Deni Toye , Terrance L Meehan , Linda Hendricks Subject: RE: IVR Trial Status (Document link: Todd S Mead) Mindy, I was expecting you to be able to provide the test detail behind each of the IVR options by product and respond in particular to the descrepancy on the loop length issue I mentioned. Also, would Covad be able to provide their circuit ID on every order so we could use that rather than the PON? You may already provide the circuit ID already but wanted verification it is standard procedure to include it on all ISRs. Thanks. Tim Gianes 303 703-2199

02/06/02 Reply e-mail from Covad

Subject: RE: IVR Trial Status From: Cutcher, Minda" on 02/06/2002 05:29:48 PM To: Tim Gianes , Todd S Mead , Michael Keegan cc: Deni Toye , Terrance L Meehan , Linda Hendricks Subject: RE: IVR Trial Status Tim, Help me out here. Are you looking for me to give you some more info or are you chasing the info? Mindy

01/29/02 E-mail from Qwest poviding update to Covad

Subject: IVR Trial Status Date:01/29/2002 04:02 PM From: tgianes@qwest.com To: mcutcher@covad.com, Todd S Mead/Mass/USWEST/US@USWEST, "Michael Keegan" cc: "Deni Toye" , "Terrance L Meehan" , Linda Hendricks/COMPLEX/USWEST/US@USWEST Mindy, Todd and Mike, Here is an update after the meeting I had with the Qwest Unbundled Services Process team. They expressed a couple of concerns that I believe can be resolved without much delay. As soon as we close on these issues we should be able to start a trial. First: They are strongly recommending that we use the Covad circuit ID instead of the PON number. We would have to insure that the circuit ID is posted to the LSR up front by Covad. This circuit number should appear on the Worddoc that the field techs work from. Second: They have requested a detailed description of the specific tests (with acceptance parameters) that are run at each option of the IVR and for each service type. I did receive a document titled Covad Loop Test Logic which seems to describe some of Covad's test acceptance parameters. Within that document for instance under Loop Length it shows that 15K is the acceptable parameter for ADSL. If this is built into the IVR parameters we would fail the test when in fact I don't believe these circuits have this requirement. For those that do have a length restriction it is 18K not 15K. We all agreed that long term there is the potential for incremental time savings, depending to a large degree on the detail provided by the IVR. Hence the desire to still pursue the trial. I will complete the trial document when I have these last 2 elements. The test parameters by option will be included in the trial documentation that I will distribute to the field. Please call with any questions/clarifications. It may be beneficial to have a quick call with the IVR SME to quickly work through the test options issue. Tim Gianes 303 703-2199

01/11/02 E-mail from Qwest responding to Covad

Subject: Re: Status at Last Date: Fri, 11 Jan 2002 09:02:58 -0700 From: "Tim Gianes" To: "Cutcher, Minda" CC: tmead@qwest.com, tgianes@qwest.com Mindy & Todd, My responses are in red after the question. "Cutcher, Minda" on 01/09/2002 08:44:26 PM To: tmead@qwest.com, tgianes@qwest.com Subject: Status at Last Todd and Tim, At last, here's my status on Action Items: 6.1 complete 6.2 the answer is yes to all (with the exception of the request on "fail to access") however, I think Covad could provide some generic data on system up time, which would drive to the same info (yes?). =Generic up time data would be helpful.= However, the catch is that to collect all this data requires a programming request, which could take between 2-4 weeks, depending on workload in our IT group. On the I-Report stuff, my understanding is that Covad will provide Qwest with a list of all orders that used IVR, then Qwest would run the I-Report analysis. Please confirm. =This is correct. Will need Qwest order numbers and related repair ticket numbers as well. Based on agreed definition of "I" report........submitting a repair ticket within 30 days of the service order DD.= 6.3 complete 6.6 sounds like Tim and I have more work to do on this. Let me know when would be a good time to discuss further. =Todd, could you schedule a 30 minute meeting? Looks like late (after 4 pm) on the 16th or 18th, or anytime on the 21st would be ok at this time.= If you have any questions, etc. let me know. Otherwise, let's talk about next steps to implementation. Mindy 253-323-2481 (efax) 781-649-0703 (p) 978-869-7376 (m)

01/10/02 E-mail update from Covad on Kick-off meeting actions

Subject: Status at Last Date: Wed, 9 Jan 2002 19:44:26 -0800 From: "Cutcher, Minda" To: tmead@qwest.com, tgianes@qwest.com Todd and Tim, At last, here's my status on Action Items: 6.1 complete 6.2 the answer is yes to all (with the exception of the request on "fail to access") however, I think Covad could provide some generic data on system up time, which would drive to the same info (yes?). However, the catch is that to collect all this data requires a programming request, which could take between 2-4 weeks, depending on workload in our IT group. On the I-Report stuff, my understanding is that Covad will provide Qwest with a list of all orders that used IVR, then Qwest would run the I-Report analysis. Please confirm. 6.3 complete 6.6 sounds like Tim and I have more work to do on this. Let me know when would be a good time to discuss further. If you have any questions, etc. let me know. Otherwise, let's talk about next steps to implementation. Mindy 253-323-2481 (efax) 781-649-0703 (p) 978-869-7376 (m)

01/04/02 Meeting minutes for Kick-off meeting

11:00 a.m. (MDT) / Thursday 3rd January 2002

Attendees: Todd Mead / Qwest Tim Gianes / Qwest Mindy Cutcher / Covad

Purpose of the meeting was to develop the framework for the IVR trial scheduled to begin on the 28th January 2002 and lasting for approximately 2 months.

Identify/Answer CLEC/Qwest Questions About Trial : Location of trial – Denver Metro area. Tim will verify with local field director Duration of trial will be approximately 2 months During the trial, all existing loop tests will continue as before. Qwest technicians will still provide continuity tests to Covad as requested and Qwest center technicians will continue to provide Covad required circuit turn-up test results.

Establish Action Plan (Resolution Time Frame): 6.1 Mindy will provide Tim a password for IVR by Monday (01/07/02) / Mindy 1/7/02 6.2 Mindy will provide details on reporting capability of IVR. Specifically: - Number of times Qwest accesses the Covad IVR - Number of times Qwest attempts to access IVR but fails (new request) - Number of circuits tested by Qwest via the IVR - Number of circuits that Passed the required IVR tests - Monthly summary of failed tests by state - Identify all circuits tested via the IVR by Qwest to run batch report for “I” Reports 6.3 Mindy needs to confirm what type of circuit the IVR testing tool should be used for. / Mindy 1/7/02 6.4 Todd to forward the ppt and pdf file attached to original CR onto Tim. / Todd 1/3/02 6.5 Tim will produce a trial document outlining the trial purpose, what will be measured during the trial and the expected outcomes. / Tim 1/14/02 6.6 Ideally, this trial should capture the number of times the IVR test generated a ‘pass’ but Covad found a problem with the circuit. Both Qwest and Covad will explore options for collecting this data. / Tim/Mindy 1/14/02

12/05/01 Answers to additional clarification questions, received from Covad:

Answers to the questions are embedded below. Keep in mind that we offer this to the ILECs as an additional testing tool for their use and have not had the opportunity to do any rigorous data gathering and analysis. That might be something we can build in to the trial if Qwest decides to go forward.

- What is the availability time of the IVR? I have assumed 24x7 but have there been unscheduled downtimes over the past 6 months and if so how many and for how long? The system is designed to be on 24X7. It is the same system Covad field techs and Agents use to test orders.

- What are the specific circuit types that are included in their process with Verizon? LX--? etc. It can be used to test any UNE loop... just not line share.

- Has COVAD tracked the success rate for accessing the IVR and completing the tests? If so what is the rate? No data on this.

- Is part of the agreement that if the tests come back positive, COVAD technicians will accept the test results without question and complete the order? No this is just to be used as a tool for the ILEC Tech at this time. It is not a replacement for test and accept.

- Has COVAD measured the actual usage of the IVR tool by Verizon.....what % of the orders that qualify are tested by Verizon utilizing the IVR? It has only been used as a interim test tool not for test and accept so no data on this.

- What % of the orders tested by the IVR and accepted by COVAD have had an "I" report (repair ticket within 30 days of turnup)? No data on this.

- What are the specific test parameters utilized by the IVR for each test run? It is the same parameters that are used by our agents when they test the loop for test and accept.

10:00 am (MDT) / Thursday, November 01, 2001

Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PC102301-1- IVR Testing

Minda Cutcher, mcutcher@covad.com , Covad Fred Aesquivel III, faesqui@qwest.com, Qwest Michael Belt, mbelt@qwest.com, Qwest

Introduction of Attendees Introduction, Fred, Mike, Minda / T. Meehan and T. Gianes left call per Fred’s request.

Review Requested (Description of) Change Implementation of Covad’s IVR Testing Tool by Qwest for use in the field provisioning and repair process. The Request was reviewed and fully understood.

Confirm Areas & Products Impacted Areas: Field Provisioning and Repair Products: Unbundled Loop/ Stand Alone Loops

Confirm Right Personnel Involved Fred Aesquivel will coordinate SME’s for review and response Michael Belt – Coordinate CR

Identify/Confirm CLEC’s Expectation Covad would like to implement IVR testing with Qwest. The Integrated Voice Response (IVR) unit is an automated, menu-driven tool allowing technicians to run loop tests, loop diagnostics, perform open, short, and quiet tests, and send a tone across the ILEC loop without calling for assistance. IVR is an automated voice response (dial-in) system by which Qwest technicians can perform a one way “pre-test” of a loop prior to formal cooperative (two way) acceptance testing with Covad. IVR takes the Qwest tech through the same process as the two-way test and will feed back results to the Qwest tech. If the loop tests "good", the Qwest tech would then perform the coop test and loop turnover with Covad. If a fault were discovered during the IVR test, the Qwest tech would then have the opportunity to correct the deficiency prior to turnover to Covad. This process has been implemented in another ILEC and Verizon specifically asked for its use to improve their provisioning efficiency as part of its recent recovery efforts in NYC. Eventually, the goal will be to eliminate the need for cooperative testing, saving both Covad and Qwest time and resources, improving operational efficiencies for both.

Identify any Dependent Systems Change Requests N/A

Establish Action Plan (Resolution Time Frame) Fred Aesquivel III to coordinate with Verizon on previous IVR testing from trial done in April/May in Massachusetts regarding loop turnover with Bell Atlantic.


CenturyLink Response

September 5, 2002

Michael Zulevic Covad

SUBJECT: Qwest’s Revised Change Request Response - CR #PC102301-1 Implementation of Covad’s IVR Testing Tool by Qwest

This is in response to Covad’s Change Request (CR) PC102301-1. This CR requests that Qwest implement Covad’s IVR Testing Tool for use in the field for Unbundled Loop provisioning and repair to warrant Qwest’s Technical Publications parameters. Qwest utilizes its own test tools for Unbundled Loop provisioning and repair. The use of Covad’s IVR tool requires adding an additional and redundant step to the Unbundled Loop provisioning process and Unbundled Loop repair process.

Utilization of Covad’s IVR tool obligates Qwest to stand ready to evaluate and accept any request from other CLECs to trial their respective test platforms into Qwest’s processes in a nondiscriminatory manner. Additionally regulatory requirements prohibit Qwest from providing different levels of service to CLECs. Utilization of a CLEC provided provisioning and repair tool or process may benefit some CLECs over others by creating disparate service levels.

Since acceptance of this request from Covad would open Qwest to accepting similar requests from all CLECs, Qwest has determined that utilization of the Covad IVR testing tool would be cost prohibitive to implement. Qwest would incur additional and unrecoverable costs related to turning up and completing service orders and/or repair tickets. * Cost estimates are based on order volumes (300,000) across the 14 states for a minimum of 300 existing CLECs who could each make similar requests of Qwest and which Qwest may have to honor for parity purposes. * Qwest would incur additional costs related to initial & required ongoing employee training for any testing tool that could be provided by the CLECs. Depending on the service types included, provisioning and/or repair application, and the complexity of the tool, employee-training costs or initial deployment could run $100,000 per request or potentially $30M if all CLECs made similar requests of Qwest. Considering the increasing complexity of providing comprehensive training to manage multiple CLEC test vehicles, ongoing and refresher training costs would be substantial. * Qwest already performs and documents internal tests based on ANSI standards. Utilizing test tools from CLECs would not only duplicate those tests but would require Qwest to spend a minimum of an additional 3-5 minutes per order at a cost of $690,000 - $1,150,000 per year based on regional order volumes. *Qwest would also incur additional costs related to required operational trials, process documentation and revisions, and the complexity of managing numerous process requirements for multiple tools. This is not measurable at this point due to the unknown nature of each potential request, but is recognized as a valid concern and real cost to Qwest.

The requested change does not result in a reasonably demonstrable business benefit to Qwest or Covad. In fact performance data during the trial does not support that service levels improved for Covad. Utilizing multiple test platforms requires Qwest to create multiple processes, requiring the Qwest Network Technician to determine which process/platform to use for which CLEC. This creates potential for human error, potentially degrading service quality and performance results.

As stated above, adapting the IVR tool into Qwest’s processes creates legal, economic and service quality performance liabilities for Qwest. Qwest respectfully declines to implement Covad’s IVR tool into its Network processes.

Sincerely,

Tim Gianes Senior Project Manager

cc: Paul Kirchhoffer, Diane Diebel, Mary Retka, Barry Orrel

12-03-2001

Minda Cutcher VP ILEC Relations Covad

CC: Fred Aesquivel Douglas Lange Todd Mead

This letter is in response to your CLEC Change Request Form, PC102301-1 dated 10/23/01 entitled “Implementation of Covad’s (IVR) Testing Tool”.

After having reviewed your request I was also able to interview John Reed with Verizon, a current user of the Covad IVR testing tool. Unfortunately John was unable to provide documented data regarding several critical measures. However, he was very positive in his feedback as a whole and felt that the tool has provided improved efficiencies when completing service orders with Covad.

Thank you for agreeing to respond to these and other questions I have recently submitted to you. The answers will greatly assist us as we move forward. - Percent of usage of the IVR tool for qualified orders? - Specific test parameters of the tool for each test? - Specific circuit types included in the process? - Have there been system access issues…..if so how often etc? - Rate of “I” reports (repair tickets within 30 Days) on IVR tested orders?

Based on some positive feedback from Verizon, the fact that there is no cost to Qwest, and the apparent benefit to all parties of utilizing the IVR tool, I am recommending that Qwest move forward by conducting a trial. The purpose of the trial would be to develop a documented process and to help Qwest & Covad establish data validating the usage and gained efficiencies of the IVR tool. The trial would be conducted in a metro area agreeable to both parties for a minimum period of 2 months beginning no later than January 28th, 2002. The results of the trial and answers to the above questions will determine further action regarding this initial Change Request. If Qwest ultimately decides to accept the new process, it will be with the understanding that Covad, and any other CLEC requesting this process, must provide the IVR, test vehicle, and process and usage documentation at no cost to Qwest.

Sincerely,

Timothy Gianes Senior Project Manager - Qwest Communications


Open Product/Process CR PC093003-1 Detail

 
Title: Loop Test IVR application from Covad
CR Number Current Status
Date
Area Impacted Products Impacted

PC093003-1 Denied
11/19/2003
Provisioning, Maintenance / Repair Unbundled Loop, UNE Loop
Originator: Berard, John
Originator Company Name: Covad
Owner: Gianes, Tim
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Covad is requesting that Qwest allow it’s field Technicians to use Covad’s Loop Test IVR application when contacting Covad to perform Test and Acceptance on a loop. Currently Qwest Technicians use option number 1 when contacting Covad for loop acceptance, Covad is requesting that the Qwest Technicians now use Option number 4 to contact Covad and perform the loop acceptance testing via the Loop Test IVR application. Once the test has been completed the Qwest Tech will hit Option 0 to be connected to a Covad Agent to provide demarc information and receive a confirmation number.

Attachments: Overview of Loop Test IVR process and enhancements, Detailed M & P for Covad’s Loop Test IVR

Covad would also like to make this tool available for Qwest Maintenance and Repair Tech’s when trouble shooting a Covad loop.


Status History

09/30/03 - CR Submitted

10/02/03 - CR Acknowledged

10/08/03 - Held Clarification meeting

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

11/19/03 November CMP Meeting Tim Gianes with Qwest reviewed the draft response and said that we appreciate the changes that have been made to the IVR testing tool and said that should help Covad. The primary reason the CR being denied is the high cost for Qwest to implement this CR, and the potential for having multiple tools for multiple CLECs implemented that would then require Qwest technicians to be trained on each of the different tools. Qwest would also continue to perform the standard tests that are done today.

John Berard with Covad said he would respond formally to the denial response. John added that the IVR testing tool would reduce time in the call, and reduces, rather than increases, the testing time. John said he did not understand the $30M figure provided in the denial response because the same system is used today by Qwest to send tone and test a line and it is the same system POTS test use for the retail side. The tool is more efficient and the electronic delivery of demarc information on another CR under development will not have the advantage of the IVR Tool. In addition, the IVR testing could be done 24 x 7. John also said there was no CLEC opposition to the IVR tool when he discussed at the CLEC only call and no CLECs were concerned that Qwest would be doing something special for Covad over other CLECs. Testing the loop with the tool is like getting your balance on a credit card.

Tim Gianes explained that the $30M training issue is related to performing a different test for each CLEC customer across the 14 states. Carla Pardee with AT&T asked if the test is available in other ILEC locations. John answered yes, that Qwest is the only ILEC that has denied. Liz Balvin with MCI asked if Qwest is concerned that if this CR is accepted, then other CLECs may ask that their testing capability be implemented.

Judy Schultz with Qwest said that what Qwest does for Covad would have to be done for other customers and the training for specific customer testing tools is the concern. Tim Gianes said that Qwest doesn’t use the IVR to do testing and Qwest uses standard tests.

John Berard said that the tool adds option 4 for the loop test, which can be done remotely, and the call goes into the same exact IVR. John added that Qwest wasn’t willing to trial the test in one garage. In contrast, SBC has been asking if they can offer this testing to other CLECs. Tim Gianes responded that Qwest did perform a trial and technicians did use the tool. It wasn’t that the tool was not useable, but Qwest did not want to be in a position where other CLECs that had testing tools would request implementation of their testing tool. John said that Qwest should be open to other tools.

Liz Balvin said that the tool may cut down on jeopardies caused by not being able to contact CLECs. Tim Gianes said that Qwest would not gain efficiency when dealing with multiple tools for multiple customers and from a Qwest perspective technicians would have to be trained on multiple customer tools. The reason for the denial was not due to the quality of the tool. This CR will be moved to Denied status. Covad will send a formal response.

10/15/03 October CMP Meeting John Berard with Covad presented this new CR. John said the IVR loop test application. When a Qwest tech is in the field and finished installing a loop at the NID can perform continuity testing on UNE using this front end system. The system asks the tech to input the PONE number and verifies at the right central office and correct loop. The test includes putting a short on the loop and taking the short off, then pressing “0” and getting a Covad agent to get the demar information. Qwest requested that Covad submit this CR because this is a process change and can be used for products. Jim Recker asked if worked for DLC. John said yes. Kit Thomte asked how this CR is different from the CR denied last September. John said the difference is that the previous CR was a tool that required the Qwest tech to be on the line with the Covad agent when the continuity testing was done. The new CR allows the Covad agent to see the test. Jamal Boudhaouia asked if Covad would share the technical parameters, noise level and threshold. John said he will take that question back to Covad. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

3:00 p.m. (MDT) / Wednesday October 7, 2003

1-877-572-8687 3393947# PC093003-1 Loop Test IVR application from Covad

Name/Company: John Berard, Covad Denny Graham, Qwest Craig Suellentrop Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Linda Sanchez-Steinke read the Description of Change from the CR; Covad is requesting that Qwest allow it’s field Technicians to use Covad’s Loop Test IVR application when contacting Covad to perform Test and Acceptance on a loop. Currently Qwest Technicians use option number 1 when contacting Covad for loop acceptance, Covad is requesting that the Qwest Technicians now use Option number 4 to contact Covad and perform the loop acceptance testing via the Loop Test IVR application. Once the test has been completed the Qwest Tech will hit Option 0 to be connected to a Covad Agent to provide demarc information and receive a confirmation number. Covad would also like to make this tool available for Qwest Maintenance and Repair Tech’s when trouble shooting a Covad loop. Linda said there was also an Overview of the Loop Test IVR process Power Point presentation and M&P for Covad’s Loop Test IVR attached to the CR.

Linda mentioned there had been a similar CR submitted by Covad last year. John Berard said that this tool will give extra features. This tool will work similarly to credit card companies when calling into customer service, this will enable the ability to get information about the account.

When Qwest wants to do test and acceptance, input the PON number via the IVR, hit 0 to be directed to the agent. The Covad system has captured information and is already pulling up the account. There are seven other features when installing POTS, technicians call into the switch to test on the loop. The features allow testing that can be done without the assistance of a Central Office Technician. Craig asked if Covad requests to have the tool used with unbundled loop with cooperative testing. John said yes and added that other ILECS like it. John said he had gone over the details of the tool with Denny & Craig in a previous meeting.

Confirm Areas & Products Impacted Maintenance / Repair Provisioning

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation Covad is requesting that the Qwest Technicians now use Option number 4 to contact Covad and perform the loop acceptance testing via the Loop Test IVR application. Covad would also like to make this tool available for Qwest Maintenance and Repair Tech’s when trouble shooting a Covad loop.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) John will present this CR at the October CMP Meeting. Qwest will provide a response at the November CMP meeting.


CenturyLink Response

November 11, 2003

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting

Name:John Berard Title:Operations Support Company: Covad

SUBJECT:Qwest’s Change Request Response PC 093003-1 Covad IVR Testing Tool

This letter is in response to CLEC Change Request (CR) PC093003-1. This CR requests that Qwest implement Covad’s IVR Testing Tool for use in the field for Unbundled Loop provisioning and repair to warrant Qwest’s Technical Publications parameters. Qwest utilizes its own test tools for Unbundled Loop provisioning and repair. The use of Covad’s IVR tool requires adding an additional and redundant step to the Unbundled Loop provisioning process and Unbundled Loop repair process. Although it appears that the Covad Testing Tool & utilization process has been modified, the fundamental reasons for this rejection are the same as the reasons for the earlier rejection of PC102301-1 submitted in early 2002.

Utilization of Covad’s IVR tool obligates Qwest to stand ready to evaluate and accept any request from other CLECs to trial their respective test platforms into Qwest’s processes in a nondiscriminatory manner. Additionally regulatory requirements prohibit Qwest from providing different levels of service to CLECs. Utilization of a CLEC provided provisioning and repair tool or process may benefit some CLECs over others by creating disparate service levels.

Since acceptance of this request from Covad would open Qwest to accepting similar requests from all CLECs, Qwest has determined that utilization of the Covad IVR testing tool would be cost prohibitive to implement. Qwest would incur additional and unrecoverable costs related to turning up and completing service orders and/or repair tickets. Cost estimates are based on order volumes (300,000) across the 14 states for a minimum of 300 existing CLECs who could each make similar requests of Qwest and which Qwest may have to honor for parity purposes. Qwest would incur additional costs related to initial & required ongoing employee training for any testing tool that could be provided by the CLECs. Depending on the service types included, provisioning and/or repair application, and the complexity of the tool, employee-training costs or initial deployment could run $100,000 per request or potentially $30M if all CLECs made similar requests of Qwest. Considering the increasing complexity of providing comprehensive training to manage multiple CLEC test vehicles, ongoing and refresher training costs would be substantial. Qwest already performs and documents internal tests based on ANSI standards. Utilizing test tools from CLECs would not only duplicate those tests but would require Qwest to spend a minimum of an additional 3-5 minutes per order at a cost of $690,000 - $1,150,000 per year based on regional order volumes. Qwest would also incur additional costs related to required operational trials, process documentation and revisions, and the complexity of managing numerous process requirements for multiple tools. This is not measurable at this point due to the unknown nature of each potential request, but is recognized as a valid concern and real cost to Qwest.

The requested change does not result in a reasonably demonstrable business benefit to Qwest or Covad. In fact performance data during the trial does not support that service levels improved for Covad. Utilizing multiple test platforms requires Qwest to create multiple processes, requiring the Qwest Network Technician to determine which process/platform to use for which CLEC. This creates potential for human error, potentially degrading service quality and performance results.

As stated above, adapting the IVR tool into Qwest’s processes creates legal, economic and service quality performance liabilities for Qwest. Qwest respectfully declines to implement Covad’s IVR tool into its Network processes.

Sincerely,

Tim Gianes Senior Project Manager

cc: Paul Kirchhoffer, Diane Diebel, Mary Retka, Barry Orrel


Open Product/Process CR PC071403-1 Detail

 
Title: Good Faith Estimate of Construction Charges
CR Number Current Status
Date
Area Impacted Products Impacted

PC071403-1 Denied
11/19/2003
Pre-ordering, Ordering, Billing UNE, DS1, DS0
Originator: Berard, John
Originator Company Name: Covad
Owner: Boudhaouia, Jamal
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Covad requests that Qwest provide a good faith estimate of construction charges (at no cost) for wholesale customers. Qwests current process requires that the requesting CLEC provide a non-refundable fee up front in order for Qwest to determine an estimate of the construction costs. In many cases it might cost upwards of $1000 to provide an estimate of these costs to our end users. With non-refundable charges of this magnitude it makes it impossible for us to use the current process which causes us to cancel the order rather than potentially moving ahead with the order. It must also be noted that Qwest currently provides this estimate to it’s retail customers at no charge.

Expected Deliverable:

Qwest revises their current process to provide free of charge a good faith estimate of construction charges. Covad is looking for this process change as soon as possible.


Status History

07/14/03 - CR Submitted

07/15/03 - CR Acknowledged

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

11/19/03 November CMP Meeting Jamal Boudhaouia with Qwest reviewed the draft response. John Berard with Covad said parity with retail was not addressed in the denial response and would like it addressed in the denial letter. Jamal said that Qwest is looking at modifying the retail tariffs. Bonnie Johnson with Eschelon said that Qwest has addressed recovery of costs in the denial response. Jamal responded that it is in the fourth paragraph of the denial response. John asked if Qwest is looking at the retail tariffs in order to bring to parity. Jamal said in the response the CLECs agreed to what is currently in the SGAT and Qwest will look at the tariffs to see what can be done and come back to SGAT and TRO Compliance. Kit Thomte with Qwest asked if we could open an Action Item to track the retail tariffs. John agreed that an Action Item should be opened. John asked about the parity issue. Jamal said Qwest is still looking at modifying the Retail tariffs.

John said that the way he understands the Qwest engineer job, that for $1500 the job is fully engineered. When you have someone provide an estimate for work on your house, it is not fully engineered and materials are not purchased. There should be the ability for the engineer to tell in one hour what size cable would be needed how much and then just provide an estimate. If additional information was included in the jeopardy notice; there is no F1 cable CLECs can probably estimate that themselves or there is no F2 distribution. Jamal said that Qwest has not looked at providing that detail of information in a jeopardy notice. Jamal added that the engineers can look at LFACS and could look at the kind of cable required for a job but wouldn’t know if it should be aerial, buried, or if there is a need to bore. In addition, the field engineer needs to survey in order to see any obstacles.

John said that the engineer could look at the cable plat. Jamal said that engineering would need to additionally look at burying the cable or bore etc. Jamal added that the process and proposed changes will be introduced in the SGAT and will be TRO compliant.

Liz Balvin with MCI asked if the QPF is designed. Jamal said that the CR requested a good faith estimate at no cost. Construction will be re-evaluating and will bring in line with the TRO.

John said that he would like the parity issue and how it will be resolved addressed in the denial letter and an Action Item opened to review the retail tariffs. Judy Schultz suggested that Covad send in a new CR regarding the jeopardy process. John asked Qwest to update the denial letter to address the parity concern noted in the CR. This CR will be moved to Denied status.

Eschelon Comments on Meeting Minutes - I made several statements regarding this issue and none are noted. Since it is difficult to talk and write I don’t have my comments noted. If you cannot update the minutes with my comments, I can ask if other CLECs noted them. If not then I would like the minutes to reflect my concern that my comments were not noted.

10/15/03 October CMP Meeting Jamal Boudhaouia with Qwest reviewed the revised draft response. Jamal said that the QPF is closely related to the Crunec process which is not in place. Qwest is evaluating this CR and will provide an updated response at the November CMP Meeting. John Berard asked if Qwest has reviewed the retail process where currently the retail estimate is provided at no charge. Jamal said we are evaluating the retail process. Bonnie Johnson said she disagrees that QPF is related to the Crunec process. This CR will remain in Evaluation status.

09/17/03 September CMP Meeting Denny Graham with Qwest said that Qwest is evaluating this response and will provide an updated response at the October CMP Meeting. This CR will move to Evaluation status.

08/20/03 - August CMP Meeting Mike Zulevic with Covad presented this CR. Mike said that Covad would like to receive an estimate of construction changes up front at no charge. Quote Preparation Fees are between $1100-$1500 for a quote to provide facilities and Covad would like to see the costs up front, without having to spend $1100-$1500 on a non-refundable quote, similar to the Colorado Private Line Tariff. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

9:00 a.m. (MDT) / July 23, 2003

1-877-572-8687 3393947# PC071403-1 Good Faith Estimate of Construction Charges

Attendees Name/Company: John Berard, Covad Denny Graham, Qwest Cindy Buckmaster, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Linda read the description of change from Covad’s CR as follows: Covad requests that Qwest provide a good faith estimate of construction charges (at no cost) for wholesale customers. Qwest’s current process requires that the requesting CLEC provide a non-refundable fee up front in order for Qwest to determine an estimate of the construction costs. In many cases it might cost upwards of $1000 to provide an estimate of these costs to our end users. With non-refundable charges of this magnitude it makes it impossible for us to use the current process which causes us to cancel the order rather than potentially moving ahead with the order. It must also be noted that Qwest currently provides this estimate to it’s retail customers at no charge.

The meeting was opened for questions; Cindy Buckmaster explained that Qwest has a Quote Preparation Fee (QPF) for up front engineering preparation for the quote. Cindy asked John if Covad would like to be billed for the full amount rather than receiving a bill for the quote prep fee and then a bill for construction. John said that Covad would rather receive an estimate within + - 20% and the estimate not be fully engineered.

Cindy explained that if Qwest has DS0 plant to make a DS1 the quote prep fee is $300 as long as Qwest doesn’t have to place plant. There are additional charges for construction and the QPF for this type of charge is not $1500. If Qwest has to construct plant, the QPF is $1500 and again there are additional charges for construction. Conditioning as defined by the FCC is removal of load coil and bridge tap. Removal of those elements doesn’t change the DS0 into DS1 it is just an unloaded DS0. The function Qwest performs to change DS0 plant into DS1 capable goes beyond conditioning and is considered construction.

John said that with a retail estimate there is no up front construction charge and is a parity issue.

Confirm Areas & Products Impacted Products impacted are DS1 & DS0 UNE Loops.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation Provide a construction estimate free of charge on DS1 & DS0 UNE Loops

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Covad will present this CR at the August CMP meeting.

07/16/03 July CMP John Berard with Covad reviewed the walk on CR PC071403-1. There will be a clarification call on this change request.


CenturyLink Response

November 11, 2003

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest Change Request Response CR # PC071403-1 Good Faith Estimate of Construction Charges

This letter is in response to Covad Communications Change Request (CR) PC071403-1. This CR requests that Qwest provide a good faith estimate of construction charges (at no cost) for wholesale customers.

It is appropriate to evaluate construction charges on an Individual Case Basis (ICB). Few construction projects are the same in terms of scope and nature thus, requiring separate evaluation by Qwest Engineers to determine what elements may need to be constructed. For example, construction costs vary depending on the size and type of cable being placed and the method used to place the cable, as well as the environment where the placing is being done. There currently are no standard placing costs that apply universally. This is why Qwest developed the Quote Preparation Fee (QPF) charge based on Qwest cost studies of the operations required providing the cost of UNE construction. QPF’s allow Qwest to recover the cost of the Engineering work required to complete this evaluation. This element is in-place and approved across jurisdictions for other Wholesale products as well.

Before Qwest begins the evaluation process and expends any resources, the QPF must be submitted. Upon acceptance, this QPF is subtracted from the total cost of the job and the balance is submitted to the CLEC for payment. Upon payment by the CLEC of the identified construction costs, the construction will begin.

The Good Faith Estimate referenced in this CR applies to developing an estimate of construction charges for UNEs that do not exist in the Qwest Network and therefore need to be built. Qwest and the CLEC community have agreed that Qwest can implement a Quote Preparation Fee (QPF) for the work that Qwest Engineers and planners perform to develop such an estimate. This is documented in Section 19.3 of the SGAT, which states: A quote for CLEC’s portion of a specific job will be provided to CLEC. QPF is provided in writing and is binding for ninety (90) business days after the issue date. When accepted, the CLEC is be billed the quoted price and construction commences after receipt of payment. If CLEC chooses not to have Qwest construct the facilities, Qwest reserves the right to bill CLEC for expenses incurred for producing the engineered job design.

To assure an accurate price quote, Qwest engineering must provide diligence to the quote preparation. There is a substantial cost to investigate and prepare an accurate quote. In accordance with the SGAT, Qwest is entitled to recover these costs through the QPF.

Therefore, Qwest respectfully denies the request because it is economically not feasible due to the burden of the cost to provide the construction quote being borne solely by Qwest.

Although Qwest is declining this request, Qwest acknowledges that the definition of construction is changing in light of the TRO and recognizes that it may have an affect on the QPF and the constructions charges.

Sincerely,

Jamal Boudhaouia Staff Advocate

cc:Mary Retka, Barry Orrel, Ev Montez

-- October 1, 2003

REVISED DRAFT RESPONSE For Review by the CLEC Community and Discussion at the October 15, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest Change Request Response - CR # PC071403-1 Good Faith Estimate of Construction Charges

This letter is in response to Covad Communications Change Request (CR) PC071403-1. This CR requests that Qwest provide a good faith estimate of construction charges (at no cost) for wholesale customers.

Qwest views this request as related to the recent changes to the DS1 construction policy. The latest CMP notice PROS.09.18.03.01198 DS1CapableLoopProc posted on September 18, 2003 was open for comments until September 30, 2003.

Qwest is currently evaluating the QPF (Quote Prep Fee) and the CRUNEC process and would like to request that this CR be kept in an Evaluation Status. Qwest will provide an update at the November Meeting.

Sincerely,

Denny Graham Staff Advocate Policy and Law

September 9, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the September 2003 CMP Meeting

John Berard Covad

SUBJECT: Qwest’s Change Request Response - PC071403-1 "Good Faith Estimate of Construction Charges"

This letter is in response to Covad Communications Change Request (CR) PC071403-1. This CR requests that Qwest provide a good faith estimate of construction charges (at no cost) for wholesale customers.

Qwest is currently evaluating this request and proposes moving this Change Request into Evaluation Status while we continue to investigate. Qwest will provide an updated response at the October CMP meeting.

Sincerely,

Denny Graham Staff Advocate Policy and Law


Open Product/Process CR PC040204-1 Detail

 
Title: Collocation Final Invoice sent electronically via e mail rather than paper
CR Number Current Status
Date
Area Impacted Products Impacted

PC040204-1 Denied
7/21/2004
Billing Collocation
Originator: Berard, John
Originator Company Name: Covad
Owner: Nickell, Mark
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently Qwest emails the initial quote/bill for Collocation augments or new installations to CLEC’s via e-mail. The intial payment is made using this quote/bill. However, when it comes to the final payment Qwest will only send a paper copy. Covad is requesting that the same process for the initial bill be used for the final bill.

This process is easier for Covad to process payment to Qwest. In turn Qwest will receive a quicker turn around on payments.

Here is an example of the initial bill that we receive via e-mail:


Status History

04/02/04 - CR Submitted

04/05/04 - CR Acknowledged

04/07/04 - Contaced customer to schedule Clarification call for Monday 4-12

4/15/04 - Held Clarification Call on 4-15

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/12/04 - Emailed response to Covad

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/3/04 - Met with CLEC to discuss proposal. CLECs requested that we identify if the initial and final billing can be done in IABS. This CR will continue in evaluation.

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/14/04 - Emailed response to Covad

7/21/04 - July CMP Meeting notes will be posted to the project meeting section


Project Meetings

July 21, 2004 CMP Meeting minutes: Mark Nickell – Qwest reviewed the response and advised that the impact to BART is $108,000, and the impact to IABS is $275,000. Qwest is denying this CR due to economically not feasible reasons. John Berard – Covad stated that the amount is not real high, as compared to other estimates. Is there a cut off on the dollar amount? Mark Nickell – Qwest advised he was just involved in another situation that would have cost $15,000 and that was not approved. Insert comment from Bonnie Johnson – Eschelon: Mark said anything over $20,000 takes the request to a different threshold. End comment from Eschelon. Insert comment from Qwest: CMP process does not have a threshold set. Mark’s comment would have to be referencing a different process. End comment from Qwest. Liz Balvin – MCI stated that doesn’t the elimination of paper provide Qwest a savings? Mark advised that some of the BART billing processes are manual and these would not go away for Qwest. The bar code is used on the paper bill. There is a low volume so there was not a benefit to Qwest. Mark advised that Qwest took this back multiple times and looked at the manual process, the BART process and the IABS process. Qwest advised this CR will be changed to Denied status.

June 16, 2004 CMP Meeting minutes: Mark Nickell – Qwest recapped the CR. Mark advised that Qwest is continuing our investigation to determine the level of effort for converting BART billing to IABS. Kathy Stitcher – Eschelon asked about the two questions that came up on the previous ad hoc call. Mark answered the questions advising that IABS can handle billing for non recurring charges and electronic billing is provided via IABS if the customer is willing to subscribe to the electronic billing format. John Berard – Covad asked how long does Qwest anticipate it will take to finish the investigation. Mark Nickell - Qwest advised he anticipates a few more weeks. This CR will remain in Evaluation Status.

PC040204-1 Collocation Final Invoice sent electronically via email rather than paper Ad Hoc Meeting Thursday June 3, 2004 1:00 – 2:00

In attendance: Kathy Stichter Eschelon Debra Knopp Qwest Communications Mark Nickell Qwest Communications Chad Warner MCI John Berard Covad Kim Isaacs Eschelon Sandy Thomas Qwest Communications Cindy Macy Qwest Communications

Cindy Macy – Qwest reviewed the purpose of the call. Cindy Macy advised that Qwest held the Clarification Call in April and have been reviewing options to address the CR. Qwest would like to share this information with the CLECs and gather additional data. Cindy asked John Berard-Covad to summarize what Covad is requesting with this CR.

John Berard – Covad explained that they currently receive the initial bill via email. The final bill comes via paper though. A paper bill takes longer to process. Covad would like to get the final bill via email also. Cindy Macy – Qwest asked John to clarify if this is the bill for recurring charges also, or just the non recurring charges from the Collocation quote. John advised it is just the non recurring charges. The monthly recurring charges are billed from IABS.

Mark Nickell – Qwest explained the items that the team reviewed to try and address Covad’s request. Mark advised there would be impacts to the BART billing systems. The team also looked at manual processes. The manual efforts will not replace the paper bill. The team came up with an ‘email notification’ that notifies the CLEC that the request to product a bill has been sent to BART. There would not be charges on the email notice and the CLECs need to still submit the bar code from the BART bill with their payment. The draft example – email template was reviewed with the team.

Debra Knopp – Qwest clarified that the 1st email is the quote. The 1st paper bill has a scan code (from BART). And the final bill has a scan code (from BART). Debra said that Covad will use the quote to pay their bill but that isn’t the correct process. When this happens it usually hold up posting of the payment (approximately 10 days) as the bar code is not included with the payment and BART has to investigate and manually process the payment. Kathy Stichter verified that BART sends out the initial and final bill.

John Berard – Covad advised that the email wouldn’t meet their needs as we could not remit payment with it. John advised he didn’t want Qwest to waste their time if it doesn’t really meet our needs.

Kathy Stichter asked what was the rational to place the billing for non recurring in BART and the recurring in IABS? Mark Nickell advised that he is not sure as that was determined quite some time ago, but probably because BART is a ‘one time’ billing mechanism used for a variety of miscellaneous billing activities.

The CLECs asked if Qwest would look into what it would take to move the non recurring billing from BART to IABS.

Mark Nickell – Qwest advised he would check on the following three items:

1. Does IABS provide electronic billing? 2. Does IABS provide non recurring billing? 3. Can IABS provide the bill for nonrecurring charges for Collocation initial and final bills, instead of BART?

Cindy Macy advised next steps are to gather this information and provide status at the June CMP meeting. Another ad hoc call may be held.

May 19, 2004 CMP Meeting notes: Mark Nickell – Qwest advised that we have evaluated several different options and would like to have an ad hoc meeting with Covad to ensure our potential solution will meet Covad’s needs. John Berard – Covad advised all we are looking for is an email to be sent. Kathy Stichter – Eschelon advised this is important to Eschelon also and we would like to participate in the ad hoc meeting. Kathy asked why this meeting isn’t open to all the CLECs. Cindy Macy – Qwest advised it can be open to all the CLECs, the question was just directed to Covad as this is a Covad CR. Cindy advised she will post a meeting to the CLEC calendar. This CR will move to Evaluation Status.

April 21, 2004 CMP Meeting notes: Mike Zulevic – Covad presented this CR. Mike advised that Covad is trying to address how the bills are sent to us. Emails are used on the initial quote and paper is sent on the final bill. Paper delays the process. Covad would pay the bill faster if they got the bill via email. Kathy Sticheter – Eschelon advised that they would like to see this as well. Steve Nelson – Qwest advised that we held a Clarification call and we understand the request. Steve advised that this CR will transition to Mark Nickell. Mark introduced himself to the team. This CR will move to Presented Status.

Clarification Meeting

April 16, 2004

1-877-552-8688 7146042#

PC040204-1 Collocation Final Invoice sent electronically via email rather than paper Attendees Name/Company:

Steve Nelson – Qwest Peggy Englert – Qwest Marie Chang – Covad John Berard – Covad Kim Isaacs - Eschelon Mark Nickel – Qwest Fred Howard – Qwest Lillian Robertson - Qwest Cindy Macy – Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change John Berard – Covad reviewed the change request. John explained that Covad has to follow 2 processes to pay the bill, in 2 different ways. John advised that paper is cumbersome and not efficient. The turn around time for payment would be faster if the bill was received via email. Marie Chang – Covad advised if we get a paper copy than we have to scan or fax and store the bill. We could process the bill electronically if we received it via email. Storing the paper copy takes a lot of time and space. Steve Nelson – Qwest explained that we request the invoice from Omaha once we know when the RFS is scheduled (30 days prior to RFS date), the invoice is then created and it goes to the customer. In some states the final invoice is different than the quote due to taxes. Marie Chang - Covad advised they can’t pay until they get the final invoice, but it can be received via email. Peggy Englert – Qwest advised revisions to the quote can happen. Steve asked if Kim Isaacs-Eschelon had any additional questions. Kim advised no, she is okay. 3.0 Confirm Areas & Products Impacted Collocation invoices

4.0 Confirm Right Personnel Involved Team agreed Steve Nelson would take the lead.

5.0 Identify/Confirm CLEC’s Expectation Covad would like to receive the final invoice via email, instead of paper.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) Covad will present the CR at the April CMP Meeting Qwest will provide our Response at the May CMP Meeting


CenturyLink Response

For Review by CLEC Community and Discussion at the July 21, 2004 CMP Meeting

July 13, 2004

Covad Communications John Berard, Director-Operations Support

SUBJECT: Covad’s Change Request Response – CR #PC040204-1 Collocation final invoice sent electronically via email rather than paper

This letter is in response to Covad Communications Change Request (CR) PC040204-1. Currently Qwest emails the initial quote / bill for Collocation augments or new installations to CLECs via e-mail. This initial payment is made using this quote / bill. However, Qwest sends its collocation final invoice using a paper format. Covad’s request for an e-mail invoice method is based on the premise that it is easier for Covad to process payments to Qwest. Covad further believes that the e-mail final invoice method would shorten the invoice to payment interval. This CR requests that Qwest uses the same process for the final invoice that is used on the initial bill.

Qwest has completed the investigation and identified system development and implementation costs for the BART billing system are economically infeasible. The IT estimate is $108,000. In addition, the identified system development and implementation costs for moving the Collocation non recurring billing from BARTS to IABS, which can bill electronically, are economically infeasible. The IT estimate is $275,000.

As an alternative, Qwest has also looked at performing this process manually. Creating manual email invoices for all final bills is very time intensive. In addition, a manually generated email would not represent a readily auditable document. Qwest would not have the level of tracking that is needed to effectively support billing disputes.

The other concerns for this process included: • Increase in errors and delays because of manual processing (Qwest). Past experience has shown that the more manual the process, the higher the error rate and subsequent issues. • Increase in the interval because of manual processing (CLEC and Qwest). The bar code, issued by BART, allows semi mechanized processing of payments. Bypassing this process will actually increase Qwest’s processing interval.

As a result of this investigation, Qwest denies this change request due to it being economically not feasible based on system impacts.

Sincerely,

Mark Nickell Collocation Product Manager Qwest

For Review by the CLEC Community and Discussion at the May 19, 2004 CMP Meeting

May 12, 2004

Covad John Berard Director – Operations/Change Management

SUBJECT: CR # PC040204-1 Collocation Final Invoice

This letter is in response to Covad’s Change Request (CR) PC040204-1 Collocation Final Invoice. Currently Qwest emails the initial quote / bill for Collocation augments or new installations to CLECs via e-mail. This initial payment is made using this quote / bill. However, when it comes to the final payment Qwest will only send a paper copy. The email method is easier for Covad to process payment to Qwest. In turn Qwest will receive a quicker turn around on payments. This CR requests that Qwest uses the same process for the final invoice that is used on the initial bill.

Qwest would like to leave this CR in evaluation status as it needs to continue looking at the process and costs associated with sending an email final invoice. Qwest will provide an updated response at the June CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely, Mark Nickell Collocation Product Manager Qwest Communications


Open Product/Process CR PC040204-2 Detail

 
Title: Online System for Collocation applications
CR Number Current Status
Date
Area Impacted Products Impacted

PC040204-2 Denied
9/15/2004
Collocation
Originator: Berard, John
Originator Company Name: Covad
Owner: Nelson, Steve
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently Qwest uses a spreadsheet format for its collocation applications. Covad finds this method to be cumbersome and is requesting that Qwest consider implementing an on-line system for submitting collocation applications. Both SBC and BellSouth have an on line system rather than the spreadsheet version that Qwest uses.

Here are links to their systems:

https://clec.sbc.com/clec_colldb/colldb/collapp/login/autologin.cfm?action=ColloDBMainmenuEx&IsClec=Yes

https://collocation.bellsouth.com/NASApp/colo/ColoDispatchServlet?htbColoPage=colo.ui.COLOLogOff&source=lkLogoff&

Please note that Covad is willing to provide a password to Qwest to review these systems if they are un able to obtain from SBC and BellSouth.

Expected Deliverable:

Provide as soon as possible.


Status History

04/02/04 - CR Submitted

04/06/04 - CR Acknowledged

4/8/04 - Contacted customer to schedule clarification call for 4-12

4/8/04 - Rescheduled Clarification Call with Covad

4/15/04 - Held Clarification Call

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/12/04 - Emailed response to Covad

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database


Project Meetings

9/15/04 CMP Meeting Minutes Mark Nickell – Qwest advised that he will provide the response to this CR. Mark also advised that Steve Nelson has left Qwest, something that Steve wanted to do, and Mark will take over Steve’s Collocation responsibilities. Mark acknowledged Steve’s efforts on this CR. Mark advised after the investigation and analysis was completed the cost of delivering this CR is in excess of $540,000. Qwest denies this CR due to economically not feasible reasons. This CR will move to Denied Status.

8/16/04 CMP Meeting Mintues Steve Nelson – Qwest provided status that Qwest is still working with Bell South and we are doing our own evaluation internally on cost. This CR will remain in Evaluation Status.

July 21, 2004 CMP Meeting notes: Cindy Macy – Qwest provided status on this CR. Qwest is in the process of working with Bell South to review their Collocation system. This CR will remain in Evaluation status.

June 16, 2004 CMP Meeting notes: Steve Nelson – Qwest advised that we are in communication with Bell South about their Collocation system. SBC didn’t response so Qwest is not pursuing this any longer. Steve advised that Qwest had some personnel changes in IT. We are still evaluation the CR and should have additional information in the July meeting. The CR will remain in Evaluation Status.

May 19, 2004 CMP Meeting notes: Steve Nelson – Qwest advised that we reviewed the 18 different application forms and obtained a cost to mechanizing the system using internal resources. The cost for this is prohibitive. Steve has made contact with SBC, and has not received a response. Steve has also made contact with Bell South, and they are interested in selling the application to Qwest. Bell South provided a non disclosure document to Qwest on Monday. Qwest is working to get the non disclosure document signed. Qwest has prepared questions to ask Bell South and will continue to pursue this. Susie Bliss- Qwest advised that we have looked at this in the past and it has been very expensive. Bonnie Johnson – Eschelon asked if this is something that will also benefit Qwest. Steve Nelson advised he would like to see the system mechanized, but it will probably be too expensive. This CR will move to Evaluation Status.

April 21, 2004 CMP Meeting notes: Mike Zulevic – Covad presented this CR and advised that Covad is looking at ways to mechanize and streamline their Collocation process. Covad would like to be able to pull up a screen, populate the data and send it to Qwest, instead of using a spreadsheet and emailing applications to Qwest. Steve Nelson – Qwest advised that he will work on this CR and will have a response to this CR next month. Steve advised that Qwest is aware of the existing systems from SBC and Bell South. Steve advised that Qwest did try to implement a mechanized system a few years ago and failed. This CR will move to Presented Status.

Clarification Meeting

April 16, 2004

1-877-552-8688 7146042#

PC040204-2 Online System for Collocation Application Attendees Name/Company:

Steve Nelson – Qwest Peggy Englert – Qwest Marie Chang – Covad John Berard – Covad Kim Isaacs - Eschelon Mark Nickel – Qwest Fred Howard – Qwest Lillian Robertson - Qwest Cindy Macy – Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change John Berard – Covad reviewed the change request. John gave an example of Bell South’s system that is used for Collocation. Their system is easier to use. Marie Chang Covad advised that their system has features such as error checking, and there is less email going back and forth to clarify the application. Covad also receives a confirmation on line from Bell South. Marie explained that with Qwest’s system there is a lot of information to store. The information is in multiple spreadsheets so it is hard to keep track of revisions. Steve Nelson – Qwest advised that he understands Covad’s concern and that Qwest would like an automated system also. It would help reduce the order errors that occur. Steve advised that Qwest will take a look at this request. Steve advised Covad that Qwest did try to implement a system in the past and spent a large amount of money but failed to get the system implemented. 3.0 Confirm Areas & Products Impacted Collocation invoices

4.0 Confirm Right Personnel Involved Team agreed Steve Nelson would take the lead.

5.0 Identify/Confirm CLEC’s Expectation Covad would like a mechanized Collocation system.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) Covad will present the CR at the April CMP Meeting Qwest will provide our Response at the May CMP Meeting


CenturyLink Response

RESPONSE For Review by CLEC Community and Discussion at the September 16, 2004 CMP Meeting

September 8, 2004

Covad Communications John Berard, Director-Operations Support

SUBJECT: Covad’s Change Request Response – CR #PC040204-2 Online System for Collocation Application.

This letter is in response to Covad Communications Change Request (CR) PC040204-2. This CR requests that Qwest consider implementing an online system for collocation applications. Currently Qwest uses a spreadsheet format for its collocation applications. Covad finds this method to be cumbersome and suggests that both SBC and BellSouth have online systems to which Covad offers to provide a password to Qwest.

Qwest has completed the investigation and found system costs to be economically infeasible. The IT estimate for creating an online ordering system similar to that of SBC and Bell South systems is between $540,000 and $1,080,000 for Qwest system development work that includes gathering requirements, designing the system changes, developing and testing the system changes and deploying them to the users. Qwest was unable enter into negotiations to purchase Bell South’s or SBC’s systems or to gather specific data regarding those systems. In fact, SBC refused to discuss their system with Qwest and negotiations with Bell South were terminated after four months of stalemate regarding terms under which their system could be discussed. Had Qwest been able to purchase an existing system from Bell South or SBC, Qwest would still incur additional costs to adapt the system to Qwest’s ordering processes, products and procedures, mitigating any possible economic savings.

Qwest’s Collocation application forms can be submitted via email to rfsmet@qwest.com and the Excel format allows for cost effective and timely maintenance of the forms as products are enhanced and changed. Qwest manually validates the Collocation application and interacts personally with the CLECs. The order validation process in the Collocation Project Management Center (CPMC) consists of acceptance or communication of areas in need of clarification or change. CPMC management employees are available for review of applications and conduct calls with customers as needed or requested. The manual validation process normally takes less than 24 hours.

As a result of this investigation, Qwest denies this change request due to it being economically not feasible based on the system impacts.

Sincerely,

Stephen C. Nelson Collocation Product Manager Qwest

For Review by the CLEC Community and Discussion at the May 19, 2004 CMP Meeting

May 12, 2004

Covad John Berard Director – Operations/Change Management

SUBJECT: CR # PC040204-2 Online System for Collocation

This letter is in response to Covad’s Change Request (CR) PC040204-2 Online System for Collocation. This CR requests that Qwest develop an online system for collocation applications. Currently Qwest uses a spreadsheet format for its collocation applications. Covad finds this method to be cumbersome and is requesting that Qwest consider implementing an on- line system for submitting collocation applications.

Qwest would like to leave this CR in evaluation status as it needs to continue to look at the costs for purchasing and implementing an existing system from other ILECs. Qwest will provide an updated response at the June CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely, Stephen C. Nelson Collocation Product Manager Qwest Communications


Open Product/Process CR PC031804-1 Detail

 
Title: Repair Interval Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC031804-1 Withdrawn
4/15/2009
Maintenance / Repair, Ordering, Billing UNE, UNE Loop
Originator: Berard, John
Originator Company Name: Covad
Owner: To Be Determined
Director:
CR PM: Andreen, Doug

Description Of Change

Covad proposes that a product be developed to provide a four hour MTTR when ordered on the LSR for UNE Loops or other specified services or offerings currently provided with a longer MTTR. This product would be ordered on a circuit specific basis and not necessarily applicable to entire product groups. Covad is willing to explore the development of an expedited joint repair process as part of a four hour MTTR product offering.

Expected Deliverable:

As soon as possible.


Status History

03/18/04 - CR Submitted

03/18/04 - Received e-mail from John Berard stating Covad was retracting the CR

03/19/04 - CR Acknowledged & Retract e-mail sent to John Berard

03/22/04 - CR Closed see below

March 22,2004

Dear John Berard,

Thank you for participating in the Qwest Change Management Process (CMP).

We have received your Change Request (CR) submission titled, "Special Service Protection (SSP) for UNE Loops."

Per your discussion with Kit Thomte on March 22, 2004 we would ask that you route this request through you service manager. As you and Kit discussed, your service manager with product management can best make the determination if meeting this request would require a new product introduction.

Should you and your service manager conclude that the request does not require a new product we would be glad to introduce it through the CMP process at that time.

Sincerely,

Doug Andreen

Change Request Project Manager

Qwest

303-382-5777


Project Meetings

03/22/04 -

March 22,2004

Dear John Berard,

Thank you for participating in the Qwest Change Management Process (CMP).

We have received your Change Request (CR) submission titled, "Special Service Protection (SSP) for UNE Loops."

Per your discussion with Kit Thomte on March 22, 2004 we would ask that you route this request through you service manager. As you and Kit discussed, your service manager with product management can best make the determination if meeting this request would require a new product introduction.

Should you and your service manager conclude that the request does not require a new product we would be glad to introduce it through the CMP process at that time.

Sincerely,

Doug Andreen Change Request Project Manager Qwest 303-382-5777


Open Product/Process CR PC031804-2 Detail

 
Title: Special Service Protection (SSP) for UNE Loops
CR Number Current Status
Date
Area Impacted Products Impacted

PC031804-2 Withdrawn
4/15/2009
Maintenance Repair, Provisioning UNE Loop
Originator: Berard, John
Originator Company Name: Covad
Owner:
Director:
CR PM: Andreen, Doug

Description Of Change

Covad proposes that a product be developed which can be ordered with a UNE Loop that will provide Special Service Protection at all cross-connects points in the Qwest network. This protection has been provided by Qwest for critical customer circuits (i.e.; alarm circuits, high capacity data circuits, emergency services circuits, etc.) for many years and Covad would like the option of ordering this for certain UNE Loops. These cross connect points, as well as the protector frame "heat coils" are either red, or have red devices attached that alert the technician to take special steps prior to initiating invasive actions for testing or maintenance. These cross connect points are "protected" at all possible points both in the central office, as well at field connection points.

Expected Deliverable: As soon as possible


Status History

3/18/04 Submitted

3/22/04 Acknowledged CR see below

March 22,2004

Dear John Berard,

Thank you for participating in the Qwest Change Management Process (CMP).

We have received your Change Request (CR) submission titled, "Special Service Protection (SSP) for UNE Loops."

Per your discussion with Kit Thomte on March 22, 2004 we would ask that you route this request through you service manager. As you and Kit discussed, your service manager with product management can best make the determination if meeting this request would require a new product introduction.

Should you and your service manager conclude that the request does not require a new product we would be glad to introduce it through the CMP process at that time.

Sincerely,

Doug Andreen

Change Request Project Manager

Qwest

303-382-5777


Project Meetings

3/22/04 -

March 22,2004

Dear John Berard,

Thank you for participating in the Qwest Change Management Process (CMP).

We have received your Change Request (CR) submission titled, "Special Service Protection (SSP) for UNE Loops." Per your discussion with Kit Thomte on March 22, 2004 we would ask that you route this request through you service manager. As you and Kit discussed, your service manager with product management can best make the determination if meeting this request would require a new product introduction.

Should you and your service manager conclude that the request does not require a new product we would be glad to introduce it through the CMP process at that time.

Sincerely,

Doug Andreen Change Request Project Manager Qwest 303-382-5777


Open Product/Process CR PC032504-1 Detail

 
Title: Special Service Protection (SSP) for UNE Loops
CR Number Current Status
Date
Area Impacted Products Impacted

PC032504-1 Completed
10/20/2004
Originator: Berard, John
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad proposes that a product be developed which can be ordered with a UNE Loop that will provide Special Service Protection at all cross-connects points in the Qwest network. This protection has been provided by Qwest for critical customer circuits (i.e.; alarm circuits, high capacity data circuits, emergency services circuits, etc.) for many years and Covad would like the option of ordering this for certain UNE Loops. These cross connect points, as well as the protector frame "heat coils" are either red, or have red devices attached that alert the technician to take special steps prior to initiating invasive actions for testing or maintenance. These cross connect points are "protected" at all possible points both in the central office, as well at field connection points.

Expected Deliverables: As soon as possible.


Status History

3/25/04 CR Submitted

3/25/04 CR Acknowledged

3/30/04 Contact John Berard to offer Clarification call on 4-5 10:00 am

4/9/04 Held Clarification Call

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/12/04 - Emailed response to Covad

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database

10/20/04 - October CMP Meeting minutes will be posted to the database


Project Meetings

10/20/04 CMP Meeting MInutes Cindy Buckmaster – Qwest advised that we reviewed the 19 examples that Covad sent. We also reviewed additional orders to ensure the circuits are being tagged correctly. Cindy advised that we are 100% compliant for circuits in the Central Office. We are 96% compliant for circuits in the field. The reason for the 96% in the field is that if the cross box is wired with only a certain type of wire, extra wire of that type is in the cross box for the technician to use to mark the circuits. This wire may not be red. The same wire is used for Qwest and CLEC circuits so all are treated the same. Cindy advised that Qwest would like to close this CR. Liz Balvin – Covad asked for an explanation of the original request and Cindy reviewed the request. Liz advised she understands and it is okay to close the CR. This CR will change to Completed Status.

9/15/04 CMP Meeting Minutes Cindy Buckmaster – Qwest advised that we performed a test review on 19 order examples to make sure circuits were correctly tagged. The test was successful. This week Covad sent examples that Qwest will also review to make sure circuits are correctly tagged. Qwest will provide status at the next monthly CMP meeting. This CR will remain in CLEC Test Status.

8/16/04 CMP Meeting Mintues Cindy Buckmaster – Qwest advised this process was implemented and effective August 3. John Berard – Covad asked how will Covad know this process is in place. John requested a review by Qwest of a set number of examples. Cindy agreed to propose the review suggestion to Network. If agreed, Qwest will select a few Central Offices and have the Supervisor check to make sure the circuits were tagged. John Berard – Covad will send the order information that will be verified to Cindy Macy for 6 orders installed after August 3, 2004 (two in each region). If an audit is agreed to, Qwest will add additional circuits to the list to create a statistically valid sample. This CR will move to CLEC Test Status.

July 21, 2004 CMP Meeting notes: Cindy Buckmaster – Qwest recapped the request. Cindy advised that Qwest currently marks anything above a DS0 circuit (not analog circuits), and with this CR Qwest has expanded the process to include DSL circuits (not including POTs process requests for Line Sharing and Line Splitting). In order to make the information available to the technicians we have updated the tech books. Tech book updates occur every 12 – 18 months. We have to train the technicians and we anticipate this to be completed the middle of August. Qwest will issue a Level 1 notification when this becomes effective. This CR will remain in Development status.

June 16, 2004 CMP Meeting notes: Cindy Macy – Qwest advised this CR is in progress. The technician books need to be updated. Training the technicians will occur after the books are updated. Qwest anticipates implementing this towards the end of July. This CR will remain in Development Status.

May 19, 2004 CMP Meeting notes: Cindy Buckmaster – Qwest reviewed the response and advised that Qwest will support this CR. Cindy recapped the intent of the CR, reviewed Wholesale’s current process, explained the parity of the process with Retail for analogous circuits and potential impacts of additions beyond what Qwest has agreed to in this response. Cindy advised that Qwest will support this process on additional products identified in the response. This CR will move to Development status.

April 21, 2004 CMP Meeting notes: Mike Zulevic – Covad presented this CR. Mike explained that Covad would like for Qwest to provide SSP on certain UNE Loop type services. This would provide the ability to specify on a loop by loop basis when the order is placed that protectors are needed on the frame. Today most are black, except the SSP ones have red protectors. This tells the technician that the circuit should not be opened unless they get an okay from the customer. This is done on cross connects also, and on outside plant. These circuits are not to be moved without the proper release from the customer. This has been in place for 40 – 50 years on SSP. We need it now on additional data circuits. Bonnie Johnson – Eschelon asked what would the customer use the circuit for? Mike advised burglar alarms, data, FAA, control and monitor traffic lights, fire department and some are POTS lines. In the future VOIP lines will need this. Cindy Buckmaster – Qwest asked if Mike was aware of Qwest’s Telecommunications Service Priority (TSP). This allows the customer to identify critical and expedited circuits. Cindy Buckmaster also clarified that the type of circuits are data, not POTS circuits. Mike advised some are ordered as 2Wire loop non loaded, but they are data capable loops. Cindy verified they are not 2Wire analog loops? Mike agreed Covad’s loops are not analog, but other CLECs may have 2W analog loops. Cindy advised we will look into this CR. This CR will move to Presented Status.

Clarification Meeting April 9, 2004 1-877-552-8688 7146042# PC032504-1 Special Service Protection for UNE Loops

Attendees John Berard – Covad Cindy Buckmaster - Qwest Denny Graham – Qwest Cindy Macy – Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change John Berard – Covad reviewed the change request. John explained that this service is already offered on other products, such as Switch net 56 and DDS. Cross connection equipment is red flagged which alerts technicians to take special steps before working on the facility. John advised Covad would like to be able to request this service on specific accounts provided via UNE Loop also. Covad is launching a new product and some of those customers will be consider their service critical and may want the protection service available to them. Cindy Buckmaster verified the product lines that John is requesting this service to be available include Analog, digital capable loops including non-loaded, XDSL-I, ADSL, ISDN and DS1 and DS3. John agreed. Denny Graham advised that Qwest marks the facilities in the central office by placing red heat coils and jumpers or red caps and in the field by placing red jumpers or red caps. Denny advised that process changes would be required. Cindy Buckmaster advised we would have to look at the service order process and determine the impacts. Additionally we need to look at the practice on a geographic basis to ensure we incorporate the correct process and color used. Qwest will evaluate the viability of the service requested. Cindy Buckmaster asked John what their interval was for deploying their new product that would benefit from this service. John advised in the next month.

3.0 Confirm Areas & Products Impacted Cindy Buckmaster verified the product lines that John is requesting this service to be available include Analog, digital capable loops including non-loaded, XDSL-I, ADSL, ISDN and DS1and DS3 .

4.0 Confirm Right Personnel Involved Team agreed that Lori Langston needed to be involved.

5.0 Identify/Confirm CLEC’s Expectation Provide SSP on identified products. 6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) Covad will present the CR at the April CMP Meeting Qwest will provide our Response at the May CMP Meeting


CenturyLink Response

May 12, 2004

For Review by the CLEC Community and Discussion at the May 19, 2003 CMP Meeting

John Berard Covad

SUBJECT: Qwest’s Change Request Response - PC032504-1 “Special Service Protection (SSP) for UNE Loops ”

‘Covad proposes that a product be developed which can be ordered with a UNE Loop that will provide Special Service Protection at all cross-connects points in the Qwest network. This protection has been provided by Qwest for critical customer circuits (i.e.; alarm circuits, high capacity data circuits, emergency services circuits, etc.) for many years and Covad would like the option of ordering this for certain UNE Loops. These cross connect points, as well as the protector frame “heat coils” are either red, or have red devices attached that alert the technician to take special steps prior to initiating invasive actions for testing or maintenance. These cross connect points are “protected” at all possible points both in the central office, as well at field connection points.’

Qwest concurs with Covad’s request, currently performs this function for many circuits and will further expand that process as identified below.

In the evaluation of this request Qwest considered a number of factors: 1) Intent of the CR, 2) Current Wholesale process, 3) parity of that process with Retail process for analogous circuits, 4) Potential Impacts of Additions Beyond that Agreed to Here-in.

Each of these steps is addressed in this response. 1) Intent of the CR – based on the conversation in both the clarification meeting and in the subsequent CMP meeting it is Qwest’s interpretation that the CLECs want to ensure data integrity and avoid unnecessary down time. It is anticipated that by identifying certain ‘services’ by ‘color-coding’ the jumpers and other equipment could draw the attention of technicians causing them to exercise additional caution in their presence. Based on that assumption, it may help to re-iterate Qwest’s current practice of ‘marking’ circuits for Special Service Protection.

2) Current Wholesale Process – as mentioned at CMP and in other CRs currently under review, Qwest does mark some circuits to draw a technician’s attention to the need to operate carefully when in their presence. Those circuits currently include a) All Telecommunication Service Priority (TSP) Circuits – as mentioned before, that application is made to the Government, Qwest manages those circuits as identified by the applicable contacts at the City, State and Federal level, b) All Designed Data Services – including High Capacity Services (DS1 and above), all ISDN Circuits, and all Designed Data Capable Circuits. Each of those circuits are currently ‘marked’ according to a standard practice. The Central Office equipment is marked with Red Heat Coils and Jumpers and field terminations and cross connects are ‘marked’ with red cross jumpers, tags and/or termination caps. At present, Qwest is already marking the dispatched UBLs ordered as ISDN Capable, xDSL-I Capable, ADSL Compatible or DS1/DS3 at parity with Retail.

3) Parity of that Process with Retail Process for analogous circuits – This is at parity with what Qwest currently provides in its Retail environment. As DSL is provisioned via the Plain Old Telephone Service (POTS) flow for Retail, none of the Retail DSL capable circuits are specially marked. In the past, Qwest did not assume that all LX-N circuits were data, however, as the CLEC Unbundled Requests (for Unbundled Network Elements) flows via the Designed Service Flow, Qwest is prepared to offer to mark (in the manner defined above) all dispatched Data Capable UBL circuits including the 2/4 wire Non-Loaded Loop (where the NC Code = LX-N). Effective with this notice, Qwest will mark these circuits (by class only – Data Capable) similar to the marking already provided for ISDN/xDSL-I and DS1/DS3. This (List Document Name) attachment 2 offer is for DSL only and not for DSL/Analog or split services (i.e. Line Sharing, Line Splitting, Loop Splitting or the Shared Distribution Loop). Additionally, this offer is for circuits on a going forward basis and not for the embedded base of UBL circuits.

4) Potential Impacts of Additions Beyond that Agreed to Here-in - an effort to mark any other circuits (i.e., Sharing, Line Splitting, Loop Splitting, Shared Distribution Loop or the Analog UBL), not in parity with those done in current practice, will be denied for two reasons, Economic In-feasibility and No Measurable Benefit to both Qwest and the CLEC. The first reason would be due to the fact that Qwest would need to equip and re-train all technicians who currently work on POTS circuits to mark specified voice grade CLEC circuits. With 2,000 POTS Technicians currently doing this work that cost is expected to be in excess of $200K. Additional changes to the systems would be required to allow a method for CLECs to identify which circuits they would like to ‘mark’. Although the information could be added in Remarks up-front, for no or little additional cost, down-stream systems would need to carry this information to the field and would require mechanization. The second reason, No Measurable Benefit to both Qwest and the CLEC, would be based on the outcome that all CLEC circuits would be marked as un-interruptible and would disrupt the efficient use of the current network design and quickly dissipate use of any plant that would allow the provision of services requiring special plant configurations (i.e., having a Voice Grade circuit on a non-loaded loop with no option to move that non-loaded configuration for Data use). This provides no benefit to the network and would further cost Qwest the economic imbalance of providing a service to the CLECs that it isn’t equipped to provide for its own end-users.

In summary, Qwest will mark all Data Capable CLEC circuits per their local practice to draw technicians’ attention to the fact that the circuit carries un-interruptible traffic.

Sincerely, Cindy Buckmaster Manager Product Management


Open Product/Process CR PC021904-1 Detail

 
Title: Enhancement to existing Expedite Process for Provisioning
CR Number Current Status
Date
Area Impacted Products Impacted

PC021904-1 Completed
7/20/2005
pre order, order, provisioning UNE, Transport (including EUDIT), Loop, UNE-P, Line share, Line Splitting, loop splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Martain, Jill
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad requests that Qwest provide a formal process to expedite an order that requires an interval that is shorter than what is currently available for the product.

No expected deliverable listed

Updated the title as a result of the Clarification call


Status History

02/20/04 CR Recieved

02/20/04 CR Acknowledged

2/23/04 - Contacted John Berard - Covad to set up Clarification Call

2/27/04 - Held Clarification call

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/12/04 - Emailed response to Covad

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/15/04 - PROS.06.15.04.F.01792.ExpeditesV11

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/1/04 - Scheduled ad hoc meeting for 7/9 to discuss project, comments and plan

7/9/04 - Held ad hoc meeting

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - Notification for ad hoc meeting scheduled for 9-22-04

9/15/04 - September CMP Meeting minutes will be posted to the database

9/22/04 - CLEC Ad hoc meeting held to review expedite reasons / causes

10/20/04 - October CMP Meeting minutes will be posted to the database

11/17/04 - November CMP Meeting minutes will be posted to the database

12/15/04 - December meeting minutes will be posted to the database

12/16/04 - Scheduled ad hoc meeting for January 6

1/6/05 - Ad hoc meeting held

1/19/05 - Jan CMP meeting minutes will be posted to the database

2/16/05 - Feb CMP meeting minutes will be posted to the database

3/16/05 - March CMP Meeting minutes will be posted to the database

4/20/05 - April CMP Meeting minutes will be psoted to the database

5/18/05 - May CMP meeting minutes will be posted to the database

6/15/05 - June CMP meeting minutes will be posted to the database

7/20/05 - July CMP meeting minutes will be posted to the database


Project Meetings

July CMP Meeting Minutes: Jill Martain – Qwest advised that this went into effect on 6/16/05. Jill asked if it was ok to close this CR. Liz Balvin advised the CR could be closed. This CR will move to Completed Status.

June CMP Meeting Minutes: Jill Martain – Qwest advised that this process is effective June 16 and we would like to move this CR to CLEC Test on June 16th. There was not any objection to change the status to CLEC Test.

May CMP Meeting Minutes: Jill Martain – Qwest advised that the PCAT documentation went out for review on May 9. The comment cycle will close on May 24 and become effective June 23, 2005. This CR will remain in Development Status.

April CMP Meeting Minutes: Jill Martain - Qwest advised that we are working internally to get the three expedite reasons implemented. Jill stated that after meeting internally, we determined that a slight modification was needed. Qwest wants the new Expedite reasons directed to our Business Services. Jill stated that in our ad hoc calls with the CLECs, we did talk about the critical impact to Business customers. Jill recapped the criteria for use of the new Expedite reasons: National Security Business Services unable to dial 911 due to previous order activity Business Service where hunting, call forwarding or voice nail features are not working correctly due to previous order activity where the customer business is being critically affected. Bonnie Johnson - Eschelon asked if there is a definition of business services.

Jill Martain - Qwest advised it would be for more complex business and 1FB type service and this excludes residential and 1FR.

Bonnie Johnson - Eschelon asked for this to be documented.

Jill Martain – Qwest confirmed it would be changed to reflect Business Classes of Service in the actual updates. Liz Balvin - Covad asked if the examples that Qwest looked at were based on Qwest customers.

Jill Martain – Qwest advised the examples were provided by both CLECs and Qwest and discussed in ad hoc meetings.

Liz Balvin – Covad agreed that we should provide definition of Business Services and also asked that the notice reflect that residential would not be included. Liz also confirmed that this does not affect the Expedite process that requires an amendment.

Jill Martain – Qwest confirmed that it does not impact that process. Jill advised the documentation will be updated and sent out for review. Bonnie said thank you for the good results.

This CR will remain in Development Status.

March CMP Meeting Minutes: Jill Martain - Qwest advised that we are still working internally on this request and are hopeful that within the next month the PCAT changes will be available to review with the three additional Expedite reasons. This CR will remain in Development Status. [Comment received from Eschelon: Jill Martain - Qwest advised that we are still working on additional scenarios internally and waiting for internal approval on this request and are hopeful that within the next month the PCAT changes will be available to review with the three additional Expedite reasons.]

February CMP Meeting Minutes: Jill Martain - Qwest advised we are still waiting for final internal approval. Qwest is hoping to have final status next month. This CR will remain in Development Status.

January CMP Meeting Minutes Cindy Harlan/Qwest advised that an ad hoc meeting was held on January 6th. Qwest proposed adding the following as valid Expedite reasons: if access to 911 is not available, if the order is for National Security, and for certain Features in specific situations. The CLECs were receptive to these changes. Qwest has started the process to get final internal review and approval. Additional status will be provided next month. This CR will remain in Development Status.

CLEC Ad Hoc Meeting PC021904-1 Expedite Process January 6, 2005

In attendance: Kari Burke – Comcast Jeff Yeager – Accenture Sharon Van Meter – ATT Chris Terrell – ATT Linda Minesola – Comcast Amanda Silva – VCI Jill Martain – Qwest Wayne Hart – Idaho PUC Kim Isaacs- Eschelon Bonnie Johnson – Eschelon Pete Staze – Eschelon Jennifer Arnold – TDS Metro Steve Kast – MCI Thomas Soto - SBC

Cindy Harlan – Qwest took attendance and reviewed the agenda. The purpose of this call is to discuss options for additional expedite reasons. Cindy explained that Qwest has been reviewing expedites and would like to discuss potentially having Features be considered as a valid expedite reason under certain circumstances. Qwest would like to discuss what the criteria would be and identify Features that cause major impact to the CLECs. We also can potentially add a valid expedite reason if you are unable to dial 911 service and to expedite for National Security reasons. Cindy asked the CLECs to identify what Features create the most impact to the CLECs so we can build some criteria. Cindy advised that Qwest is unable to open other reasons for expedites as we do not have the resources to support that effort.

Bonnie Johnson – Eschelon stated that she didn’t think additional resources would be needed to support this. Bonnie said Eschelon’s Expedite manager is on the call and she would like him to share with us the large impacting items. Pete advised that when customers are unable to receive calls this impacts them as if they are out of service. For business customers if they can’t receive calls it impacts their revenue.

Jill Martain – Qwest asked if normally there would be an original order to install the service and another one to correct it. Bonnie advised yes, or something changed on one of their features, such as voice mail service, either with their vendor or the equipment, and that causes a need for an expedite. The customer may not understand what they have ordered. Jill asked if it was a fair request that Qwest ask the CLEC for the order number or PON. Bonnie advised that they normally provide this anyway and it is fair, but she does not believe it should be a requirement as there are other reasons too. Jill asked if we could better define and refine the criteria for Hunting so we can go to Retail and Network and discuss further, and publish a reason that is allowable. Otherwise we would negate the standard interval if we automatically allowed expedites on all Hunting requests. Bonnie said it should be an urgent customer situation and their service is not working the way it should be. Bonnie advised that Qwest needs to trust the CLECs request and hope that the CLECs are not abusing the process. Pete Stave – Eschelon advised there are additional steps needed to expedite an order and it is not always easy so we do not request an expedite unless it is necessary.

Jill suggested that we set criteria for this to be an ‘urgent customer situation where Hunting or Call Forwarding features are not working correctly and the customer can explain why and provide a service order and/or PON’. The CLECs agreed with this criteria.

Jill asked if there were other features that need to be discussed. Amanda – VCI stated that Features don’t pertain to VCI very much, but what happens if a customer is disconnected in error and it is the CLECs error. This happens a few times a month usually due to a disconnect for non payment in error. Jill advised this would need to be handled as a new LSR with standard interval. Another request was made for voice mail set up incorrectly. This can be added to a wrong number for example.

Jill agreed that the items and criteria identified should be workable. Qwest needs to review this internally and determine impacts. Status will be provided at our CMP meeting and we will plan on reviewing the draft process prior to it being published in the PCAT. Another ad hoc meeting will be scheduled at that time.

December CMP Meeting Minutes Cindy Macy – Qwest advised that an ad hoc meeting is scheduled for January 6 to review and further define some options for expanded Expedite reasons. This CR will remain in Development Status.

11/17/04 November meeting minutes Cindy Macy – Qwest advised that Qwest is currently reviewing the expedite process and meeting internally to determine if there are any changes that can be made to the process. This CR will remain in Development Status.

10/20/04 October CMP Meeting Minutes Cindy Macy – Qwest advised that Qwest held an ad hoc meeting. We are reviewing the expedite reasons from the CLECs and the data gathered for potential changes. We hope to have additional information next month. Qwest will hold an ad hoc meeting to review our findings. This CR will remain in Development Status.

PC021904-1 Enhance Expedite Process Ad Hoc Meeting September 22, 2004

In Attendance: Pete Stave – Eschelon Colleen Forbes - ATT Kim Isaacs – Eschelon James Leblanc – McLeod Bonnie Johnson – Eschelon Jean Novak - Qwest Communications Lori Nelson – Mid-Continent Terri Lee - SBC Donna Osborne Miller – ATT Chris Quinstruck - Qwest Cherron Halpern - Qwest Communications Rhonda Velasco – Oregon Telecom Sue Diaz - Qwest Communications Mark Sieres – Advanced Telecom LeiLani Hines – MCI Brandon McGovern–Advanced Telecom Valerie Estorga - Qwest Communications Roslyn Davis - MCI Christina Valdez - Qwest Communications Scott Ellefson – Qwest John Berard – Covad Dave Miller – Advanced Telecom Michelle Thacker - Qwest Communications Lydell Peterson - Qwest Phil Hunt – McLeod Leti Mudlo - Qwest Robin Jackson – Time Warner Diane Solomonson - Qwest Jolene Brown – Time Warner Stacy Berg – Time Warner Steve Kast - Qwest Communications Jim Christener – McLeod Mark Ashen Brenner – McLeod Chris Voorhees - McLeod Jennifer Fischer - Qwest Communications Diane Johnson – Qwest Michelle Sprague – McLeod Dawn Tafoya - Qwest Communications Jill Martain - Qwest Communications

Cindy Macy – Qwest Communications introduced the attendees and reviewed the agenda. Cindy advised that the purpose of this call is to discuss what is causing the need to expedite. Qwest would like to identify from a CLEC perspective why they expedite. Jill Martain – Qwest added that we would like to identify for non design documentation changes and process changes that could help reduce expedites. Cindy advised that Qwest would like to hear from each CLEC represented so we can gather input and determine what changes could be made to reduce the need for expedites.

Bonnie Johnson – Eschelon advised that Qwest’s appointments for new installs and moves in some states were 3 weeks out. This was due to resource issues (no technicians available). Eschelon can not give their customers a 3 weeks due date. We are expediting from a customer service perspective. This was happening in WA/CO/AZ on POTS service.

Colleen – ATT advised that when they submit their orders they have to use appointment scheduler and the date that comes back is what they have to put on their order. They will then call and expedite as the date is not acceptable for their customers. Donna Osborn Miller – ATT advised that they also engage their account teams to help.

Stacy – Time Warner advised that when the due dates is out 2-3 weeks, we have to expedite, and then Qwest wants to charge for the expedite. It is wrong for Qwest to charge for an expedite when the due date is way past standard interval.

Colleen – ATT advised many times the customer is disconnected and needs their service. The disconnect can be due to the customer moving early, an error on Qwest or the CLECs part, the order not getting processes correctly, or a jeopardy.

Bonnie Johnson – Eschelon advised specific to features, our customers have urgent needs. If their call forwarding was set up incorrectly (gave wrong number, or error in programming), and the calls are going to another number it can cause major issues. If a business forwards these calls to a residence, or if there is an emergency and the customer is not able to receive calls it causes major issues for all parties. Call Forwarding generally has a 1-3 day standard interval and a business can not loose calls for 3 days, nor can a residence customer receive calls from a business in error for 3 days. Colleen – ATT advised other LECs have same day turnaround if the order is received before 3p.m.

Jim – McLeod advised orders that are placed in jeopardy for no access are often done in error. The customer says they were available but the technician never came to the door. Then later it is determined that the technician couldn’t find the building, or couldn’t gain access. Sometimes the customer does give the wrong address and they are now out of service.

Robin Jackson and Stacy Berg – Time Warner advised they have lots of trouble with orders being issued incorrectly. They put information on the LSR that matches the CSR. Then the order gets rejected for address issues. They have to send it in and fix it later, and try to get a new due date. Time Warner also reported that when they build a subscription they send it in and Qwest has to release it. The ‘create’ needs to be done 3 days ahead and SOA has to concur. Time Warner wants to know if this is the official process. They work with the LNP team and this process is not working well. Cindy advised she will have the Service Manager contact Robin and Stacy. (robin.jackson@twtelecom.com, Stacey.berg@twtelecom.com)

Dave – Advanced Telecom advised they will get an FOC and the due date is okay. Then on the due date or the day before they will get a jeopardy notice which then needs to be expedited as they have given a due date to their customer.

Bonnie – Eschelon advised when there is an equipment install or vendor meet and we have to coordinate three companies it is very difficult and we usually have to expedite to get the companies represented and the services coordinated and installed.

Bonnie – Eschelon also advised that hunting causes an out of service condition as sometime equipments is needed or there are circular hunting issues and the calls go no where.

Pete – Eschelon advised that coordinated loops installed on LNP are complex and all parties have to be available to keep the customer service from going down.

Lori – Mid-Continent advised that if voice mail is not working the customer perceive this as their service not working. If the call forwarding number is incorrect (wrong area code and the voice messaging needs to be corrected) we have to place an order to fix the issue.

Nicki – Mid-Continent advised sometimes their customers have urgent needs related to their job or personal situation. For example, the customer could be on active duty and need service right away.

John Berard – Covad advised if something goes wrong in the process and the customer gets disconnected in error, it could be the CLECs error, then Covad has to issue another order with a new due date. Sometimes the order is issued as a new order and it should have been a move order so the due date is different.

Dave – Advanced Telecom advised that Qwest does not reject orders consistently. They can submit 10 orders the same and on the 11th order they get a reject. The representative interprets the business rule differently and now we are a day behind. We can talk to 4 different representatives and we can get 4 different answers.

Bonnie – Eschelon confirmed that for non design the same process and charges will apply to Retail. Jill Martain – Qwest confirmed that would occur. Jill – Qwest advised our direction is to not implement a fee for expedites on non design. We are trying to understand some reasons and causes for expedites and address them from a process and documentation perspective. Bonnie advised that is great.

Nicki – Mid-Continent advised she requested an expedite for medical reasons and was asked for a doctors note. Nicki advised this is confidential information. Jill advised it is part of the process to request a note. Our centers are trying to follow the process and make sure the expedite is valid.

Colleen – ATT advised recently we had a customer that filed a PUC complaint and it was on the news so it was a huge issue that needed to be resolved. Jill advised if there are extenuating circumstances you can go through the Escalations process. This is not the norm but under special conditions we do handle escalations.

Cindy – Qwest advised our next steps are to look at the input that was received today and the process. We will determine areas that we can impact to reduce the need to expedite and provide status at the next CMP meeting. Additional ad hoc meetings may be held.

9/15/04 CMP Meeting Minutes Cindy Macy – Qwest advised that there is an ad hoc meeting scheduled for Wednesday, September 22 to discuss the reasons for expedites. The intent is to look at the cause of expedites to determine if there are improvements that can be made to reduce the number of expedites. This process focuses on non design services. This CR will remain in Development Status.

8/16/04 CMP Meeting Mintues Jill Martain – Qwest advised that Qwest has done additional work on this CR and determined that we won’t be able to implement the same process for non design that we implemented for design. We are doing root cause analysis on the data and will determine reasons why expedites are needed. Qwest will meet with each of the CLECs after we have the data and work through the expedite reasons. John Berard – Covad asked some questions about the Expedite V14 PCAT. Jill recapped the process and advised the CLECs that if they have questions they can call her to discuss. John Berard – Covad verified if the error was caused by Qwest than there would not be a charge to expedite. Jill advised that is correct. Bonnie Johnson – Eschelon advised she tried to expedite a feature and the escalation group and Service Manager said they were not able to do this. Bonnie submitted a comment on this issue as Eschelon believes this is an existing process. Bonnie advised her definition of an existing process is if Qwest is performing the process it is an existing process. Bonnie and Jill discussed the issue and agreed that the issue was the difference between what Eschelon sees as an existing process and what Qwest views as an out of compliance. Jill told the center to go ahead and continue to handle feature expedites until we are able to resolve this issue. Bonnie appreciated this as it takes away the immediate pain to Eschelon. Bonnie advised that Eschelon has formed an internal team to review documentation against current process and previous CRs. They are focusing on DSL initially. Bonnie and Jill agreed that Eschelon should submit a CR to determine how to handle the situation when there is disagreement between when Qwest is out of compliance versus when Qwest is performing an existing process. This CR will remain in Development Status.

July 21, 2004 CMP Meeting Minutes: Cindy Macy – Qwest advised that the team held an ad hoc meeting on July 9. During the ad hoc meeting, Jill Martain reviewed the PCAT and addressed comments on the process. Cindy advised that this process is effective July 31 in most states. The following identifies exceptions: AZ 8/5, Northern Idaho and NE 8/2, NE 8/6, WA affects only Access Services. The FCC#1 is effective July 31. Qwest will continue to work on the non design process. Additional status will be provided later. Liz Balvin – MCI advised that the clarification and the updates that were discussed helped a lot. Jill advised those updates have been made. This CR will remain in Development status.

PC021904-1 Expedite Process Ad Hoc Meeting July 9, 2004 10:00 – 11:00 a.m. MT

In attendance: Eric Yohe – Qwest Liz Balvin – MCI Valerie Estorga – Qwest Susan Lorence – Qwest Jackie DeBold – US Link Steve Kast – Qwest Teresa Castro – Vartec Stephanie Prull – Eschelon Sue Lamb – 180 Comm John Berard – Covad Jill Martain – Qwest Ann Atkinson – ATT Julie Pickar – US Link Donna Osborn Miller – ATT Cindy Macy – Qwest

Cindy Macy – Qwest reviewed the history of the CR. Cindy explained that this process was notified on June 15, 2004 and then retracted on June 29, 2004. Cindy reviewed the agenda and purpose of the meeting.

Jill Martain – Qwest advised the intent of the PCAT update was to address the new expedite process on design products. Currently we are not able to include non design products in the process. We will schedule additional ad hoc meetings to discuss non design products and CLEC caused error expedite situations.

Jill advised that July 31 is the tariff effective date. Interstate filings will occur next, and there are a couple states that may go a little later, but each state is in progress of getting the tariffs approved.

Liz Balvin – MCI verified V11 only impacts design services. Jill advised the list of products that are in the pre-approved section are all design products.

Jill advised there will be two processes. ‘Expedites that Require Approval’ (current process) and the new process ‘Approved Expedite Request’ for identified design services products. Jill reviewed the PCAT and process in more detail.

Stephanie Prull – Eschelon asked how Qwest will notify the CLEC when Qwest can not meet the expedited date. Jill advised that when the CLEC calls in Qwest will get the name of the person who requested the change and work with them. Stephanie asked what happens if we use the EXP field? Jill advised Qwest would send back the FOC with the PIA value. Stephanie asked if the Retail customers get charged on the ‘Expedite Requiring Approval’ process. Jill advised no, and neither would the CLECs, unless they sign up for the new process.

Liz Balvin – MCI asked for more clarity on the non design process. Jill advised that the Expedite Process that requires approval applies to non design services or Interconnection Agreements that do not carry the ‘per day’ expedite rate. Jill agreed to clarify that all non design service expedites or design services expedites if your contract is not amended, will not carry a charge. Non design products can only be expedited for the conditions listed currently. We are still trying to accommodate some CLEC reasons for non design expedites. We will continue working on this and we will have additional calls with the CLECs. Retail follows these same procedures. Jill advised we will work on this in phases.

Jill explained that when you amend your contract there are not reasons for expedites any longer. Qwest agrees to expedite and there is a charge for all expedites.

John Berard – Covad asked if there is a separate charge on design products if there is a fire. Jill advised no, the same charge applies. If Qwest causes the error than there is not a charge.

Stephanie Prull – Eschelon asked when the amendment will be available. Jill advised the target date is July 26. Stephanie asked how this new process affects resource assignment of network technicians. Jill advised we have the resources to cover expedited requests. We have performed volume forecasts. An expedited request and a regular request are equally weighted.

Jill summarized the Pre Approved Expedite process. The CLECs must amend their ICA, the estimated cost to expedite is 200.00 per day, and eligible products are identified in the PCAT.

Stephanie Prull – Eschelon advised that currently the CLECs have special reasons for an expedite that are not included in the list. The CLEC calls the center and works with Qwest to address these situations. Jill advised we need to follow our process, and we will still handle unique conditions. They may need to be escalated.

Liz Balvin – MCI asked if this will be implemented on the Access side. Jill advised the tariff target date is July 31 for Access products. Liz asked Jill to include the tariff reference in the response to comments. Jill advised the exception is the Washington tariff is not being filed at this time.

Jill reviewed the comments to make sure she had addressed the CLECs concerns in today’s meeting. The CLECs agreed that the comments have been addressed during today’s meeting. Jill advised she will make updates to the PCAT based on today’s call.

June 16, 2004 CMP Meeting notes: Jill Martain – Qwest advised for design product the Level 3 notification went out on June 15. For non-design we are still investigating if the process is feasible. The CR will remain in Development Status.

May 19, 2004 CMP Meeting notes: Jill Martain – Qwest advised that Qwest will accept this CR with the caveat to implement this on a product by product basis. There may be some products that this process will not be implemented for. For those products, the old process will stay in place. There will be a cost to expedite and amendments will need to be done. The approximate cost is in the $150.00 - $400.00 price range. A per day improvement charge would be assessed. Jill advised that the target list of phase 1 products is included in the response. Qwest is targeting July 31 for implementation. Bonnie verified that this will apply to Retail also. Jill advised yes, and a tariff would be filed. Jill will provide an update next month. This CR will move to Development Status.

April 21, 2004 CMP Meeting notes: Jill Martain – Qwest reviewed the response for this CR. Jill advised that Qwest would like to leave this CR in Evaluation Status as we look at individual products for expedites. Jill asked the CLEC community if they are willing to pay just and reasonable charges to expedite. Bonnie Johnson - Eschelon stated that these charges should apply to retail customers as well. Liz Balvin – MCI asked how this would work. Are the prices driven by what is on our Interconnection Agreement? Jill Martain advised there would be charges in the ICA, and the amendment would have to be written. Bonnie said they would have to be commission approved rates. Jill advised she is not the expert on this process but she believes so. Liz Balvin clarified that if the CLECs are not willing to opt in to the contract, then they would follow the process that is effective today. Jill advised yes. Bonnie advised we do have situations when we have requested an expedite and Qwest denies it. Then the end user customer goes directly to Qwest and the expedite occurs. Jill advised we will keep this perspective in mind. This CR will move to Evaluation Status.

March 17, 2004 CMP Meeting John Berard – Covad presented the CR and explained that Qwest’s Expedite Process is written based on certain situations, such as Medical Emergencies. However if the CLEC makes an error, there isn’t a process to expedite for a CLEC error reason and the CLEC has to take a regular interval. We want a process to request a faster interval, and we are willing to pay for it. Eschelon supports the request and would like to understand what type of opportunities are available for our Retail customers and if they get charged for an expedite. Bonnie advised that they have had trouble getting their customer in service, and if their customer contacts our Retail organization themselves, they get service in okay. Ervin Rae – ATT advised that he has heard that Qwest leadership is in the process of reviewing our Expedite Process. Jill Martain – Qwest advised that we can take a look at all of these aspects and also review PC081403-1 as this CR is also requesting a ‘Restoral Request Process’. This CR will move to Presented Status.

Clarification Meeting February 27, 2004 1-877-552-8688 7146042# PC021904-1 Expedite Process for Provisioning – enhancements to existing process

Attendees John Berard – Covad Bryan Comras – Covad Mark Gonzales – Qwest Heidi Moreland – Qwest Jill Martain - Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change John Berard – Covad reviewed the change request. John explained that Covad would like the title of the CR updated, as this is really a request for an enhancement to the existing expedite process. Cindy agreed to update the CR. John advised that the expedite process is limited today to certain types of orders and processes. For example, medical emergencies. We may find that it is Covad’s error that caused the customer to be disconnected. We would like to be able to get our customers restored quicker than standard interval, when it is our error. We are willing to pay for this service. Other ILECs provide this service. We would like the criteria to be expanded to allow an expedite when the CLEC makes an error. Cindy Macy – Qwest asked for an example of this happening today. John Berard – Covad and Bryan Comras – Covad advised this relates to the Jeopardy process. When Covad fails to complete the order, but we complete the work at the DMARC the customer has service, but we do not close out the records so Qwest doesn’t think the customers service is working. Qwest issued a jeopardy notice and since we didn't respond to that notice within 30 days Qwest then cancelled the orders and the service gets disconnected. Covad then goes back and resends the order, but we have to wait the standard interval and that is too long for the end user customer to wait, especially if it is a business account. John Berard – Covad advised disconnects can also happen when the end user selects migration to a new ISP provider. This isn’t as critical as the down time is usually very limited as they are hooked up to the new provider. Heidi Moreland – Qwest asked how often this happens? Bryan – Covad replied approximately 20 times per month for Qwest, or once a day on average. Bryan advised that we get faster turn around time on certain products. Heidi confirmed that Shared Loop has a shorter standard installation interval than an unbundled xDSL-capable loop. Heidi advised that thethat the customer could be disconnected when the sync test fails and the notice is not cleared. The DSLAM port is done by the CLEC and the customer is in service. If a supplement is not sent by the CLEC, and if there is no response in 30 days, then the line gets cancelled and pulled down. Covad advised it shouldn’t matter what the history or circumstances are, if we are willing to pay for the expedite.

3.0 Confirm Areas & Products Impacted DSL, Line Share, Designed and DSL Products (all products) This applies to any one that was in service and has gone out of service and needs to be set back up due to Customer or end-user error.

4.0 Confirm Right Personnel Involved Jill agreed to get with Joan Wells regarding the Workback / Restoral Request process

5.0 Identify/Confirm CLEC’s Expectation Covad would like the ability to pay for an Expedited due date (restoral of disconnected end user) Covad would like to treat these like trouble reports and get the end user back in service in one day. 6.0 Identify any Dependent Systems Change Requests PC081403-1 Work Back Restoral Request

7.0 Establish Action Plan (Resolution Time Frame) Covad will present the CR at the March CMP Meeting Qwest will provide our Response at the April CMP Meeting


CenturyLink Response

For Review by CLEC Community and Discussion at the May 19, 2004 CMP Meeting

May 12, 2004

Covad Communications John Berard, Director-Operations Support

SUBJECT: Covad’s Change Request Response – CR #PC021904-1 Enhance Expedite Process for Provisioning

This letter is in response to Covad Communications Change Request (CR) PC021904-1. This CR requests that Qwest enhance the expedite process to allow for an interval that is shorter than what is currently available for the product.

Qwest will accept PC021904-1 Enhancement to existing Expedite Process, with the caveat that it will be looked at and implemented on a product by product basis. Qwest will continue to look at all of the individual products to determine if we will implement these changes. For those products which the expedite criteria/process does not change, Qwest will leave the existing expedite criteria and process in place. Additionally, as discussed previously, expedite charges will become applicable for all expedites except those that are due to Qwest caused reasons and amendments will be required to existing Interconnection agreements to implement those charges. If a CLEC chooses not to amend their Interconnection Agreement, the current expedite criteria and process will be used.

The first phase of implementing a change to the expedite process will be around those products that are Designed Services. A list of those products is shown below. For Designed services, an expedite charge is applicable for each day that the due date is improved (unless the expedite is due to a Qwest caused reason). We are targeting an implementation date of July 31, 2004, pending approval of the Interstate FCC#1 tariff, individual state tariffs and Interconnection agreements.

Following are a list of products that will be included in Phase 1: Product UBL all except 2w/4w analog Analog PBX DID Private Line (DS0, DS1, DS3 or above) ISDN PRI T1 ISDN PRI Trunk ISDN BRI Tr unk Frame Relay Trunk DESIGNED TRUNKS (Includes designed PBX trunks) Trunk MDS / MDSI DPAs (multiple DPAs or FX, FCO) Trunk UBL DID (Unbundled digital trunk)

For Review by the CLEC Community and Discussion at the April 21, 2003 CMP Meeting

April 14, 2004

Covad John Berard Director – Operations/Change Management

SUBJECT: CR # PC021904-1 Enhance Expedite Process for Provisioning

This letter is in response to Covad’s Change Request (CR) PC021904-1 Enhance Expedite Process for Provisioning. This CR requests that Qwest enhance the Expedite process to allow for an interval that is shorter than what is currently available for the product.

Qwest would like to leave this CR in evaluation status as it needs to continue to look at the individual products and provisioning processes that are impacted by this request. Qwest will provide an updated response at the May CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Jill Martain Qwest Communications


Open Product/Process CR PC011604-1 Detail

 
Title: All Joint Maintenance and Trouble Isolation Documentation be placed in the same location on the Qwest Web Site
CR Number Current Status
Date
Area Impacted Products Impacted

PC011604-1 Denied
6/16/2004
Web Site
Originator: Berard, John
Originator Company Name: Covad
Owner: Graham, Denny
Director:
CR PM: Andreen, Doug

Description Of Change

Covad requests that joint maintenance and trouble isolation be placed in the same location on the Qwest web site. This would include wiring diagrams for connecting DS1/3 circuits on their ICDF, number conversion chart for splitters located in the common area, splitter card RMA process, process for strapping out defective data lines that impair voice, synch testing for new services, synch testing for trouble isolation, etc. Covad believes that this will assist both the Qwest and Covad operations technicians in insuring that the proper processes are being followed.

Expected Deliverable: As Soon as Possible


Status History

01/16/04 - CR Submitted

01/16/04 - CR Acknowledged

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status will remain in Submitted

2/11/04 - Held Clarification call

2/17/04 - Sent clarification call minutes

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

2/18/04 - Status changed to Presented

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/26/04 - Qwest sent notice of ad hoc meeting CMPR.04.26.04.F.01603.Ad_Hoc_Mtg 5/4/04 3-4 MDT

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/15/04 - Qwest sent notice NETW.07.15.04.F.01877.Websites_for_PC011604-1

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

7/21/04 July CMP Meeting Denny Graham, Qwest stated his action item to put together a list of URLs for sites researched as part of this CR has been completed. This list was sent as a Level 1 notice on July 15. John Berard, Covad said he has seen the list and agrees that this fulfills the commitment. This concludes the action item and the CR will be removed from the active file. The CR is already in Denied status.

-- 6/16/04 CMP June Meeting Denny Graham, Qwest summarized the denial response that stated all the examples submitted by Covad were available on the Qwest website and that, if needed, training on navigating the Qwest web site was available. Based on this and the cost of developing and maintaining a separate web page the CR was being denied because the requested change is economically not feasible and also does not result in a reasonably demonstrable business benefit (to Qwest or the requesting CLEC) or customer service improvement. Bonnie Johnson, Eschelon asked if it would be less work to have one page and link to the various processes. Jamal Boudhaouia, Qwest answered that creating and maintaining a separate repository based on feedback from developers is economically not feasible. Bonnie then asked if it would be possible to provide a job aide with bookmarks to the various sites. Jamal said his understanding is that if Covad could find these sites that they obviously know how to access them. Bonnie asked if Qwest could provide the information to all the CLECs or is this Covad’s responsibility. John Berard, Covad added that a word document with hyperlinks would suffice. Susie Bliss, Qwest asked if John had this. John answered no, but that he knows the concern is maintenance and he would be ok with a one time word document. Bonnie asked if Jamal was providing such a document for Qwest. Jamal said they are doing the research for Qwest. Liz asked if Qwest could point out where these sites are. Susie asked if we could put a list of the sites that were researched as part of the CR with hyperlinks in the denial. John added there were only 6 or 7 sites. Jamal said yes and would take as an action item since the denial had already been sent. Bonnie asked for confirmation that Qwest would provide the information on a one time basis. The CR status will be changed to Denied.

- 5/19/04 CMP May Meeting Minutes Denny Graham, Qwest said that since the last meeting an additional clarification call was held and that Covad had provided examples to Qwest that are now under evaluation. Denny said a response will be available at the June meeting. The CR will stay in Evaluation.

- Ad Hoc Meeting Minutes PC011604-1 All Joint Maintenance and Trouble Isolation Documentation be placed in the same location on the Qwest Web Site CMP Product & Process 5/4/2004 1-877-521-8688, Conference ID 1456160 3:00 p.m. – 4:00 p.m. Mountain Time

PURPOSE

To move ahead with the evaluation of this CR.

List of Attendees: Carla Pardee, AT&T Liz Balvin, MCI Mike Zulevic, Covad John Berard, Covad Jennifer Arnold, U S Link Emily Baird, POPP Telecom Steve Collier, Eschelon Denny Graham, Qwest Communications Jarby Blackmun, Qwest Communications Jim Recker, Qwest Communications Erin Martin, Qwest Communications Mike Johnson, Qwest Communications Kit Thomte, Qwest Communications Doug Andreen, Qwest Communications

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

John Berard, Covad reviewed the purpose of the CR. He said that when Covad technicians are working in the COs they need to look at what procedures to follow through one central location.

Mike Zulevic, Covad said that on points of termination and other situations this would be for both CLECs and Qwest and should help avoid misunderstandings between the two.

Doug Andreen, Qwest asked if this should be limited to CO processes. Mike answered no that it should include appropriate maintenance processes also.

Doug asked if all the processes were now located on the Qwest website. Mike said for the most part yes although some might be classified as proprietary.

Jim Recker, Qwest said that he wants to make sure that we don’t go down the wrong path by trying to do everything at once. So if we can pick one item and move forward to model and see if this can be done. With the proprietary information and information not on the web site we have to work through how to proceed.

Mike stated that the vast majority of data resides on soft copy and he could send sever examples.

Kit Thomte, Qwest asked Mike if he could send two or three examples to look at. Mike agreed and will send them to Doug.

Mike said the wiring schemes would be specific to Covad but all other information should be standard for all CLECs.

Denny Graham, Qwest asked if the wiring schemes were CO specific. Mike said no, that what he is proposing is generic information on how Qwest does things.

Kit asked what happens if Qwest and the CLECs miscommunicate. Mike offered an example where a Qwest technical wired a DS 1 circuit straight through when Covad expected something else. This resulted in three technicians being involved at different times and eventually the circuit was out of service. If there was a place to go to verify the wiring the problem could have been avoided.

Liz Balvin, MCI asked if Qwest was placing some M&Ps on the site. Jim said that Qwest could work with some process people to determine what should go on the site.

Liz brought up that Qwest technicians may also have suggestions. Jim agreed to hold a meeting with some of the Qwest technician’ supervisors s to get their input.

Mike pointed out that these documents already exist and it’s a matter of getting them together. He also said that Jamal Boudhaovia would be familiar with the CO documents.

Jim asked Mike how he got copies of the documents now. Mike said that through a variety of ways email etc. Mike said for instance the PCAT for Sync Testing is out there but not the easiest to locate for field technicians.

It was agreed that Qwest will review the documents that Covad will send and schedule another ad-hoc call after the review and meeting with Qwest technician’s supervisors.

4/21/04 April CMP Meeting Denny Graham, Qwest asked the request be moved to Evaluation and stated that Qwest is still awaiting examples from John Berard on how Covad technicians access this information. Mike Zulevic, Covad said that much of this documentation resides on the technicians own hard drives or on various places on the web site. Mike said he would talk to John about the examples but the idea is to bring the documentation into one web site for use by the CLECs and Qwest. Mike stated that some of the documentation resides on Qwest proprietary databases. The CLECs also need access to this information as they are common or mutually agreed to processes. Mike said this would really be a repository for common information. Bonnie Johnson, Eschelon offered as an example the process around dispatch after normal access hours. If the documentation were in a common area there would be no dispute about what the process should be. Denny stated that what Qwest needs is where the CLEC technicians go to get the information. Kit Thomte, Qwest said that Qwest will organize an ad-hoc meeting as a way to start dialogue. Denny asked if any of the documentation in the CR was specific to Covad. Mike said the wiring diagrams were but all other categories were not. Liz Balvin, MCI said that Qwest would also benefit from gathering all the documentation in one place. The CR will move to Evaluation.

- 03/17/04 March CMP Meeting Denny Graham, Qwest stated that Qwest is evaluating the request in cooperation with Covad. Doug Andreen, Qwest further stated that Qwest is awaiting examples of how a typical search is done today from Covad. John Berard, Covad said he would forward the examples. It was agreed no screen shots are needed. This CR will remain in Presented status.

-- 2/18/04 CMP Meeting This was a walk-on CR by Covad in January. Doug Andreen, Qwest in John Berard’s absence stated that a Clarification call was held and the intent of the CR is to provide a method of easy access to documentation that the Qwest and CLECs technicians commonly use in trouble isolation and maintenance work. The CR calls for the documentation to be located or accessible from a common point on the web. Jim Recker, Qwest added that John would provide us with examples of processes Covad now uses to find the documentation. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting 2:30 p.m. (MDT) / Wednesday February 11, 2004 1-877-521-8688 1456160# PC011604-1 All Joint Maintenance and Trouble Isolation Documentation be placed in the same location on the Qwest Web Site

Attendees John Berard, Covad Liz Balvin, MCI Kim Isaacs, Eschelon Jim Recker, Qwest Mike Johnson, Qwest Alice Matthews, Qwest Doug Andreen, Qwest Jarby Blackmun, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Doug read and reviewed the CR. Covad requests that joint maintenance and trouble isolation be placed in the same location on the Qwest web site. This would include wiring diagrams for connecting DS1/3 circuits on their ICDF, number conversion chart for splitters located in the common area, splitter card RMA process, process for strapping out defective data lines that impair voice, synch testing for new services, synch testing for trouble isolation, etc. Covad believes that this will assist both the Qwest and Covad operations technicians in insuring that the proper processes are being followed. John Berard, Covad added that the request came from their technicans. He also wanted to add two items to the list of documentation ie. The Qwest Test Point Documents and the MOP form. Mike Johnson, Qwest asked if all documents have been identified. John answered with the two additions and the documents on the CR that all have been. Doug Andreen, wanted to clarify that no change in any document is needed but they just need to somehow be located together on the web. John indicated that was correct. John further stated that using a table to link to the documents current locations would be acceptable. Jim Recker, Qwest brought up that we would need to find out how the documents are being arranged today and their current locations. Mike asked if there was a time frame for this CR. John answered no but as soon as reasonably possible. Jim asked how Covad technicians located the documents today. John said that a lot of the time the technician would call his office. He will then try to get in the correct section and then do a search. Jim asked if he could provide an example. John said he would email an example to Doug for distribution to the group. Jim questioned if what John was interested was sort of a front door. John replied that would work. Confirm Areas & Products Impacted Documentation placement on web.

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation Implementation to be as soon as possible

Identify any Dependent Systems Change Requests None

Establish Action Plan (Resolution Time Frame) John will present the CR for Covad at the February CMP meeting. The response will be due at the March meeting.

1/21/04 January CMP Meeting Mike Zulevic, Covad walked-on this CR which calls for the placement of all documentation used by technicians in a common location on the Web. He said most of the documentation is available but is located in several different locations. He is calling for a grouping perhaps by process or a functional grouping for the technician. Examples of the type of documentation would be demarc information, DS1-3 ICDFs and how they are wired out, blank form for MOP etc.


CenturyLink Response

June 8, 2004

REVISED RESPONSE For Review by the CLEC Community and Discussion at the June 16, 2004 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest Change Request Response CR PC011604-1 All Joint Maintenance and Trouble Isolation Documentation be placed in the same location on the Qwest Web Site

This letter is in response to Covad Communications Change Request (CR) PC011604-1. This CR requests that Qwest place all joint maintenance and trouble isolation documentation in the same location on the Qwest web site.

The documentation referenced in this CR and provided to Qwest as examples already exist on the Qwest Wholesale Website. Additionally, Qwest has existing training material available on the Qwest Wholesale Website for the user. The training is located at http://www.qwest.com/wholesale/training/iltdescwhtour.html and outlines how to navigate within the Wholesale website.

To place joint documentation on a single website would require the addition of a new location within the existing Wholesale website. The requested information would then need to be identified on the existing location(s) and linked to the new site. Developing this new site would merely duplicate the information that is already available. The estimated cost of providing this request is $125,000 per year.

Therefore, Qwest respectfully denies the request because the requested change is economically not feasible and also does not result in a reasonably demonstrable business benefit (to Qwest or the requesting CLEC) or customer service improvement. As an alternative it is recommended that both Qwest and the CLEC instruct the individual technicians to maintain bookmarks that would enable them to rapidly locate pertinent documentation.

Sincerely, Denny Graham

-- March 9, 2004

For Review by the CLEC community and discussion at the March 18, 2004 CMP Meeting

John Berard Covad

SUBJECT: Qwest’s Change Request Response - CR PC011604-1 "All Joint Maintenance and Trouble Isolation Documentation be placed in the same location on the Qwest Web Site"

This CR as submitted by Covad requests that joint maintenance and trouble isolation be placed in the same location on the Qwest web site. This would include wiring diagrams for connecting DS1/3 circuits on their ICDF, number conversion chart for splitters located in the common area, splitter card RMA process, process for strapping out defective data lines that impair voice, synch testing for new services, synch testing for trouble isolation, etc. Covad believes that this will assist both the Qwest and Covad operations technicians in insuring that the proper processes are being followed.

Qwest is evaluating this request in cooperation with Covad. Qwest is awaiting a response from John Berard in answer to a request from Qwest for examples of Covad’s current process to access this information. With this input Qwest can compare the Qwest Processes and the Covad processes to determine the feasibility of providing this request.

At this time the CR is still in the clarification stage. Upon receipt of the Covad process, Qwest will move the CR into the Evaluation status.

Sincerely,

Denny Graham Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Cheryl Rock, Senior Process Analyst, Qwest


Open Product/Process CR PC051403-4 Detail

 
Title: Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting
CR Number Current Status
Date
Area Impacted Products Impacted

PC051403-4 Completed
8/18/2004
Provisioning / Maintenance & Repaire Loop Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Moreland, Heidi
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad requests that Qwest extend their existing process of sync testing on provisioning of line share orders to include Sync Testing for Trouble Tickets on Loop Splitting. In addition, Covad requests that the current process of provisioning for line sharing be expanded to include Loop Splitting.

Expected Deliverable

As soon as possible


Status History

06/30/03 - Opened CR for Loop Splitting product on behalf of Covad, Loop Splitting product removed from CR PC051403-1

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/14/04 - Qwest issued PROD.01.14.04.F.01233.LoopSplittingV16 proposed effective date 2/28/04

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/12/04 - Qwest issued Final notice PROD.02.12.04.F.01321.FNL_Loop_Split_V16 will become operational 2/27/04

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/25/04 - Qwest issued PROD.02.25.04.F.01413.Retract_Loop_Split_V16

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/11/04 - Qwest issued PROD.05.11.04.F.01660.PCAT_Updates, proposed effective date 6/25/04

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/10/04 - Qwest issued PROD.06.10.04.F.01766.FNL_PCAT_Updates, CMP - FINAL NOTICE - Loop Splitting - V18.0 effective date 6/25/04

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/16/04 - August CMP meeting mintues will be posted to the database


Project Meetings

8/16/04 CMP Meeting Mintues Heidi Moreland advised this report has been in CLEC Test for one month and Qwest would like to close this CR. John Berard – Covad advised it is okay to close. John advised they have set up the process and provided emails. The process has not been used yet but if there is a problem Covad will let us know. This CR will move to Completed Status.

07/21/04 July CMP Meeting Heidi Moreland – Qwest advised that this CR was effective June 25. Qwest will move this CR to CLEC Test status.

06/16/04 June CMP Meeting Heidi Moreland with Qwest gave an update that the Loop Splitting PCAT was sent out for review and will become effective on 6/25/04. Heidi asked if this CR could move to CLEC Test and later in the meeting, all decided it could move to CLEC Test after the PCAT is effective, but should remain in Development status until the PCAT is effective. After reviewing the CMP Document, Section 5.8, Qwest believes that the work needs to be completed for each status type (i.e. CLEC Test) before the status is changed. Status should only be changed upon agreement in the Monthly Meeting. This CR will remain in Development Status. This CR would move to CLEC Test in July as the effective date is 6/25/04.

05/19/04 May CMP Meeting Heidi Moreland with Qwest gave an update that the Loop Splitting PCAT was sent out for review and comment on 5/12/04 and the proposed effective date is 6/25/04. This CR will remain in Development status.

-- 04/21/04 April CMP Meeting Heidi Moreland with Qwest gave an update that the Loop Splitting PCAT would be out in the next week or so and will include a comment cycle. This CR will remain in Development status.

03/17/04 March CMP Meeting Heidi Moreland with Qwest gave an update that the Loop Splitting V16 PCAT was ready to be implemented on 2/27 and was retracted because the jep code, S1 used for Sync Test on Line Sharing, will not work for Loop Splitting because Loop Splitting follows the design services flow and new jep code will require work in IMA. The solution identified, and discussed with Covad last week, requires the use of the PTA notice process on DVA, and then if sync testing fails on the due date, Qwest will jep the order C01. John Berard with Covad said that the PTA process would work for their operations group. Ervin Rea asked if CO1, since the jep code effects performance, would be appropriate when sync test fails. Heidi said that if sync test fails it is due to the CLEC equipment not being ready and therefore CO1 would be valid. Heidi said we could hold an ad hoc meeting to discuss the process further. It was agreed that an ad hoc meeting was not needed and Heidi will get the PCAT updated. This CR will remain in Development status.

-- 02/18/04 February CMP Meeting Heidi Moreland with Qwest gave an update that the Loop Splitting V16 PCAT adding sync testing for provisioning and repair requests will become effective on 2/27/04. This CR will remain in Development status.

01/21/04 January CMP Meeting Linda Sanchez-Steinke with Qwest gave an update that the Loop Splitting V16 PCAT adding sync testing for provisioning and repair requests was posted on 1/14/04 as a Level 3 notification. The comment cycle will close on 1/29/04 and the proposed effective date is 2/28/04. This CR will remain in Development status.

12/17/03 December CMP Meeting Heidi Moreland with Qwest said the PCAT changes will be out in the January timeframe for review. This CR will remain in Development status.

11/19/03 November CMP Meeting Heidi Moreland with Qwest reviewed the revised response and said that the process is under development. At the December meeting there will be a status update. This CR will remain in Development status.

10/15/03 October CMP Meeting Heidi Moreland with Qwest reviewed the revised response and said that Qwest will implement this change request. Carla Pardee asked what date this would be implemented. Heidi Moreland said that we do not have an implementation date. This CR will move to Development status.

09/17/03 September CMP Meeting Heidi Moreland with Qwest gave an updated response that Qwest is evaluating this request. Covad agreed this CR remain in Evaluation status.

08/20/03 August CMP Meeting Heidi Moreland with Qwest provided an update that Qwest is investigating providing Sync testing for Loop Splitting. Loop Splitting follows the design flow using TIRKS and the two databases, TIRKS and Switch/FOMS do not communicate with each other. Qwest would like to keep this CR in evaluation status while during further investigation and will provide an update at the September meeting.

07/16/03 July CMP Meeting Craig Suellentrop with Qwest explained that this CR was opened to address Sync testing for Loop Splitting. Craig presented the response for this CR saying that Qwest needs more time to evaluate sync testing for the Loop Splitting product. This CR will move to Evaluation status.


CenturyLink Response

November 11, 2003

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT:Qwest’s Change Request Response - PC051403-4 Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting

This letter is in response to CLEC Change Request PC051403-4. This CR is a request by Covad for Qwest to extend the existing process of Synchronization Testing on Line Sharing requests to include the Loop Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Loop Splitting. This CR has been accepted and is currently under development. Qwest will expand the current provisioning process to include Sync Testing on Loop Splitting. For Loop Splitting repair, Qwest will perform Sync Testing upon CLEC request..

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest

Craig Suellentrop Staff Advocate Policy and Law Qwest

-- October 1, 2003

REVISED DRAFT RESPONSE For Review by the CLEC Community and Discussion at the October 15, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest’s Change Request Response - PC051403-4 "Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting"

This letter is in response to CLEC Change Request PC051403-4. This CR is a request by Covad for Qwest to extend the existing process of Synchronization Testing on Line Sharing requests to include the Loop Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Loop Splitting. Qwest is accepting this CR for Sync Testing on Loop Splitting provisioning and repair and ask that it be moved into the development stage.

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest

Craig Suellentrop Staff Advocate Policy and Law Qwest

September 9, 2003

REVISED DRAFT RESPONSE For Review by the CLEC Community and Discussion at the September 17, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest’s Change Request Response - PC051403-4 "Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting"

This letter is in response to CLEC Change Request PC051403-4. This CR is a request by Covad for Qwest to extend the existing process of Synchronization Testing on Line Sharing requests to include the Loop Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Loop Splitting. Qwest is requesting an additional extension of the evaluation period for this CR for Sync Testing on Loop Splitting provisioning and repair.

Today, for central office based Shared Loop DSLAMS, Qwest populates the Synchronization Testing protocol (i.e., DMT, etc.) into our Switch/FOMS database. This works well for central office based Line Sharing and Line Splitting products since they follow the POTS process flow and Switch/FOMS is utilized for POTS services. The Loop Splitting product follows Qwest’s designed service process and as such uses the TIRKS database. Switch/FOMS and TIRKS are not compatible systems nor are they linked to transfer information. Qwest is requesting this CR remain in evaluation status to enable further systems capability analysis. The complexity of the systems issues requires deep analysis from many departments and Qwest continues to explore possible options. Qwest will provide a revised response at the October CMP meeting.

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest

Craig Suellentrop Staff Advocate Policy and Law Qwest

August 13, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the August 20, 2003 CMP Meeting

John Berard Director - Operations Support Covad Communications

SUBJECT: Qwest’s Change Request Response - PC051403-4 "Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting"

This letter is in response to CLEC Change Request PC051403-4. This CR is a request by Covad for Qwest to extend the existing process of Synchronization Testing on Line Sharing requests to include the Loop Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Loop Splitting. Qwest is requesting an extension of the evaluation period for this CR for Sync Testing on Loop Splitting provisioning and repair.

Today, for central office based Shared Loop DSLAMS, Qwest populates the Synchronization Testing protocol (i.e., DMT, etc.) into our Switch/FOMS database. This works well for central office based Line Sharing and Line Splitting products since they follow the POTS process flow and Switch/FOMS is utilized for POTS services. The Loop Splitting product follows Qwest’s designed service process and as such uses the TIRKS database. Switch/FOMS and TIRKS are not compatible systems nor are they linked to transfer information. Qwest is requesting this CR remain in evaluation status to enable further systems capability analysis. Qwest will provide a revised response at the September CMP meeting.

Sincerely,

Heidi Moreland Staff Advocate Policy and Law Qwest

Craig Suellentrop Staff Advocate Policy and Law Qwest

July 2, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the July 16, 2003 CMP Meeting

John Berard Director Operations Support Covad

SUBJECT: Qwest’s Change Request Response - CR 051403-4 "Sync Test for Loop Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Loop Splitting"

This CR requests that Qwest extend the existing process of Sync Testing on Line Sharing requests to include the Loop Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Loop Splitting.

Since the Loop Splitting product follows Qwest’s designed services process while Line Sharing and Line Splitting follow the non-designed process, this request is much more complex than PC051403-1. Different systems are used for designed products and a different process would be required. Because of this complexity, Qwest needs additional time to evaluate this request. This change request should be placed in evaluation status.

Sincerely,

Craig Suellentrop, Staff Advocate-Policy & Law, Qwest Heidi Moreland, Staff Advocate-Policy & Law, Qwest

Cc: Mary Retka, Director, Legal Issues Jamal Boudhaouia, Staff Advocate-Policy & Law, Qwest Debra S. Smith, Product Manager, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Michael Lanoue, Lead Process Analyst, Qwest


Open Product/Process CR PC051403-1 Detail

 
Title: Sync Test for Line share and Line Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Line Splitting.
CR Number Current Status
Date
Area Impacted Products Impacted

PC051403-1 Crossover
7/27/2009
Maintenance, Repair, Provisioning Line Sharing, Line Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Suellentrop, Craig
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Covad requests that Qwest extend their existing process of sync testing on provisioning of line share orders to include Sync Testing for Trouble Tickets on Line Sharing and Line Splitting. In addition, Covad requests that the current process of provisioning for line sharing be expanded to include Line Splitting.

Expected Deliverables:

As soon as possible.


Status History

05/14/03 - CR Received

05/15/03 - CR Acknowledged

05/19/03 - Clarification Meeting scheduled

05/20/03 - Held Clarification Meeting. CR changed to reflect Line Sharing Product only for sync testing per John Berard with Covad.

05/21/03 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/28/03 - Received change request e-mail from John Berard with changes to change request, posted in database

05/30/03 - Left voice mail for John Berard with date to schedule additional clarification meeting

06/13/03 - Held second Clarification Meeting

06/18/03 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/16/03 - Created cross over CR, SCR051403-01X


Project Meetings

07/16/03 July CMP Meeting Craig Suellentrop with Qwest presented the response for this CR. Because of the systems work necessary to select sync testing and request the protocol for testing, this CR will be crossed over to Systems and will be discussed at the Systems meeting 7/17/03. Covad agreed to cross over the change request to Systems.

06/18/03 June CMP Meeting John Berard with Covad presented this CR. Covad would like to have the capability of sync testing for line sharing maintenance and would also like to have sync testing available for line splitting and loop splitting, both provisioning and maintenance. Craig Suellentrop said that he received the e-mail from John about the 102 characters allowed in the remarks section of CEMR and if the character limit would not be enough room to identify the protocol for sync testing. John said that the remarks field is written over and suggested use of another field. John said that as an interim solution, the remarks field could be used until a longer-term systems solution can be implemented. Qwest will provide a response on this CR at the July CMP meeting and this CR will be moved to Presented status.

From: Berard, John [jberard@covad.com] To: Linda Sanchez-Steinke, Craig Suellentrop, Heidi Moreland, Michael Zulevic Subject: RE: PC051403-1 Clarification Meeting Minutes Date: 6/17/03 Linda:

I did check with our repair group and it would be no problem to provide the protocol when a trouble ticket is opened... However, for the lineshare family of products there is only 102 characters allowed in the comment section of CEMR. If you would like Covad to provide this when we open the ticket the comment space limitations would need to be removed. Or allow us to use another field to provide this information.

John Berard Director - Operations Support/Change Mgt - Covad Office # 1 720 208 2109 Cell Phone # 1 303 881 8652 eFAX # 1 707 549-5332 Pager 3038818652@mobile.att.net Mailing Address: 7901 Lowry Blvd Denver, CO 80220

CLEC Change Request Clarification Meeting 10:00 a.m. (MDT) / Friday, June 13, 2003 1-877-562-8687 3393947# PC051403-1 Sync Test for Line share, Loop Splitting, and Line Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Line and Loop Splitting.

Name/Company: Mike Zulevic, Covad John Berard, Covad Craig Suellentrop, Qwest Heidi Moreland, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Covad request that Qwest extend their existing process of sync testing on provisioning of line share orders to include Sync Testing for Trouble Tickets on Line Sharing and Line and Loop Splitting. In addition, Covad requests that the current process of provisioning for line sharing be expanded to include Line and Loop Splitting. Craig Suellentrop asked if Covad would be able to provide the protocol when a trouble ticket is submitted. John or Mike will check on that and get back to Linda.

Confirm Areas & Products Impacted Line Sharing, Line Splitting and Loop Splitting Maintenance Trouble Tickets Line and Loop Splitting Provisioning

Confirm Right Personnel Involved Qwest confirmed that Craig Suellentrop and Heidi Moreland are correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation Provide sync testing on Line Sharing and Line and Loop Splitting trouble tickets and provide sync testing on Line and Loop Splitting provisioning orders.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Covad will present this CR at the June meeting and Qwest will provide a response at the July meeting.

05/21/03 May CMP Meeting John Berard - Covad reviewed the walk on CR PC051403-1 Sync Test for Line Sharing on Maintenance Trouble Tickets. They want to use the same test capability to isolate trouble in CO. They want this done on Line Sharing, Line Splitting, and all shared services. John Berard with Covad will update the products and areas impacted on this change request and e-mail to Linda Sanchez-Steinke.

CLEC Change Request Clarification Meeting 11:00 a.m. (MT) / May 20, 2003 1-877-572-8687 Conf. ID 3393947 # PC051403-1 Sync Test for Line sharing on Maintenance Trouble Tickets Attendees Attended Conference Call Name/Company: John Berard, Covad Director Operations Support Jamal Boudhaouia, Qwest Network Technical / Regulatory Craig Suellentrop, Qwest Network Technical / Regulatory Deb Smith Product Management Linda Sanchez-Steinke, Qwest Change Request Project Manager

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The change request asks that Qwest expand the existing synchronization testing available for line sharing provisioning, to repair. Deb Smith asked if the request was for UNE and said that Qwest offers sync testing on line sharing only. John Berard with Covad said that the change request should be revised to reflect just line sharing product. Craig Suellentrop asked if Covad would expect sync testing on every trouble report and if Covad would provide the protocol type. John said Covad would like the ability to request sync testing on trouble reports and would like Qwest to be able to reference the protocol that was provisioned and if it was not possible, it would be acceptable for Covad to provide the protocol on the trouble report.

Confirm Areas & Products Impacted Product impacted is Line sharing. The change request will be updated to reflect Line sharing only.

Confirm Right Personnel Involved Qwest confirmed that Jamal Boudhaouia, Craig Suellentrop, Deb Smith, are the correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation Covad is requesting that Qwest develop a sync testing process for Line sharing maintenance. Identify any Dependent Systems Change Requests No dependent change requests were identified. Craig Suellentrop identified that changes may be required for CEMR.

Establish Action Plan (Resolution Time Frame) Covad would like to present this CR as a walk-on at the May 21, 2003 CMP meeting.


CenturyLink Response

July 2, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the July 16, 2003 CMP Meeting

John Berard Director Operations Support Covad

SUBJECT: Qwest’s Change Request Response - CR 051403-1 "Sync Test for Line sharing and Line Splitting on Maintenance Trouble Tickets and Sync Testing for provisioning of Line Splitting"

This CR requests that Qwest extend the existing process of Sync Testing on Line Sharing requests to include the Line Splitting product. Covad also requests that Sync Testing be implemented for repair tickets on Line Sharing and Line Splitting.

Qwest accepts this change request to perform sync testing in the Central Office for Line Splitting on provisioning, and for both Line Sharing and Line Splitting on repair.

Qwest will perform Sync Testing in the Central Office on Line Sharing and Line Splitting repair tickets upon CLEC request. When the CLEC issues a repair report, the CLEC will need to provide Qwest with the appropriate protocol to test (DMT-T1.413, DMT-G.LITE, DMT-G.DMT or CAP) as well as provide the setting for Rate Limiting and Auto Sync (On or Off). Qwest will also expand the current provisioning Sync Testing process to include Line Splitting.

These changes to the repair process require updates to CEMR/RCE to allow the CLEC or Qwest’s repair agent to select the options noted above. Therefore, this CR will be crossed-over to Systems. Qwest intends to implement the requested changes in mid-August, 2003.

Sincerely,

Craig Suellentrop, Staff Advocate-Policy & Law, Qwest Heidi Moreland, Staff Advocate-Policy & Law, Qwest

Cc: Mary Retka, Director, Legal Issues Jamal Boudhaouia, Staff Advocate-Policy & Law, Qwest Debra S. Smith, Product Manager, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Michael Lanoue, Lead Process Analyst, Qwest


Open Product/Process CR PC051403-2 Detail

 
Title: Adding Zone information to Bills
CR Number Current Status
Date
Area Impacted Products Impacted

PC051403-2 Withdrawn
9/17/2003
Billing UNE, Unbundled Loop, 2-Wire Non-loaded Loop, ISDN Compatible Loop, 2-Wire Digital Loop, UNE-P
Originator: Berard, John
Originator Company Name: Covad
Owner: Kilker, Terri
Director:
CR PM: Harlan, Cindy

Description Of Change

Revised Request

Currently Qwest does not reflect the Zone information on the Bill. USOC rates vary by Zone. Knowing the Zone is needed in order to reconcile our bills. In addition, Covad requests that all one-time charges on our bill include USOC’s.

Original Request

Currently Qwest does not reflect the Zone information on the Bill. USOC rates vary by Zone. Knowing the Zone is needed in order to reconcile our bills.

Expected Deliverables:

As soon as possible.


Status History

5/14/03: CR Received

5/15/03: CR Acknowledged

05/20/03: Description of Change Revised by Covad

05/28/03: Clarification Meeting

06/18/03 - Discussed at CMP Meeting

07/09/03 - Qwest response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

07/25/03 - Updated list of products impacted; Unbundled Loop 2-Wire Non-Loaded Loop, ISDN Compatible Loop, 2-Wire Digital Loop, ISDN Basic Rate Loop, 2 Wire ADSL

8/21/03 - Discussed at CMP Meeting

9/17/03 - This CR will be closed and tracked by SCR063030-03IG. Sep CMP meeting notes will be posted to the database


Project Meetings

9-19-03 John Berard agreed to withdraw this CR as SCR061703-03IG has an implementation date of 06-2004.

9-17-03 CMP Meeting Terri Kilker – Qwest advised we have worked with Covad to review the additional products and determined those products are not zone billed so zone information would not be shown on the bills. The outstanding problem on this CR regarding non-recurring USOC charges in Western was reviewed. It was determined that systems CR SCR061703-03IG will take care of this problem. John would like to know the implementation date of the SCR061703-03IG. John didn’t want to combine this request with the other request if it would increase the delivery timeframe.

CMP Meeting 08-20-03

Kilker-Qwest presented the revised acceptance response. Stichter-Eschelon stated that there was an open systems CR that covered this same subject. White-Qwest stated that these two CRs were being worked in conjunction. The CR was moved into Development status.

=================================================

Ad Hoc Meeting Minutes PC051403-2 Adding Zone information to Bills CMP Product & Process July 25, 2003 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:30 a.m. Mountain Time

PURPOSE

At the July CMP Meeting, participants agreed to hold a conference call and include CLEC technical experts for a discussion about products beyond UNE-P CLECs desire rate zone and USOC information. The following is the write-up of the discussions, action items, and decisions made in the working session.

List of Attendees: Mike Olser - Covad Candy Davis - Covad John Berard - Covad Lori Mendoza - Allegiance Liz Balvin - MCI Stephanie Prull - McLeod USA Terri Kilker Qwest Crystal Soderlund - Qwest Carl Sear - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest provided brief history of the change request and said that Qwest arranged this meeting to discuss what products CLECs desire rate zone and USOC information in their bill. John Berard with Covad said that Covad had found when performing bill reconciliation they are not getting all zone information they need to receive. Candy Davis with Covad said that some states, Colorado, Minnesota, and Oregon are missing the zone on the spreadsheet provided. Carl said that he had investigated the rate zone examples and determined they were Line Sharing examples. Crystal Soderlund with Qwest said that Line Sharing is billed at a flat rate and not rate zoned. There are missing USOCs for non-recurring charges in the western region. Carl is investigating the missing USOCs.

To clear up confusion about why some accounts have USOCs and some don’t, Crystal explained that BANs for unbundled loop and line sharing were sometimes combined due to the initial implementation timeframes required for the product. As Qwest finds these BANs they are separated and currently the products are billing on separate BANs.

Candy asked if it would be accurate to say they can get USOC and zone information on electronic as well as paper bills. Carl said yes USOC and rate zone information is provided in both formats and that line sharing is not billed by rate zone but is a flat rated charge. Carl asked if Covad gets EDI or ASCII. Candy answered they receive BOS BDT. Carl will ask the BOS BDT SME if USOCs appear on those bills.

Terri asked that Covad provide examples where they are not getting rate zone and USOC information on other UNE products beside line sharing and Qwest will investigate.

Qwest asked if there were any additional comments. No comments were made.

CMp Meeting 07-16-03

Kilker-Qwest presented the response. She stated that Qwest needed more information from Covad because the product list in the CR description did not include many of the products in the example file Covad provided. Berard-Covad stated that he would send White a comprehensive list of all products Covad wanted this change to apply to. White-Qwest stated that there was an Ad Hoc Meeting scheduled for 7/24 to discuss this change.

======================================== CMP Meeting 06-18-03

Berard-Covad presented the CR. =================================================== Clarification Meeting Tuesday, May 27, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Terri Kilker – Qwest John Berard – Covad Mike Osler – Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Berard-Covad reviewed the CR. Kilker-Qwest asked if this is specific to any particular service. Berard-Covad stated that it would be for UNE Loops and Line Share Loops. Kilker-Qwest asked if Covad was associating line sharing with the loops or UNE-P. Berard-Covad stated that is was for both. He asked if this was a defect or just not a current service. Osler-Covad stated that Covad receives the information for some states but not others. He stated that he had some examples pulled together. Kilker-Qwest stated that she’d like to see the examples.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the June Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

August 13, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the August 20, 2003 CMP Meeting

John Berard, Covad

SUBJECT: Qwest’s Change Request Response – CR # PC051403-2 (Adding Zone Information to Bills)

Qwest amends its earlier acceptance of this change request to now include Unbundled Loop products in addition to UNE-P, based on an Ad-Hoc meeting held on July 25, 2003 with Covad and other interested CLECs.

To briefly recap the events of the meeting, Covad provided a list of additional products for which they were requesting zone and USOC billing detail, in along with the UNE-P products in their original request. The additional products identified were Unbundled Loop (2-Wire Non-Loaded Loop, ISDN Compatible Loop, 2-Wire Digital Loop, ISDN Basic Rate Loop, 2-Wire ADSL) and Shared Loop (Line Sharing.)

In addition to the request for zone and USOC billing detail on the Unbundled Loop and Shared Loop products, Covad clarified that they believe they are currently missing zone or USOC information on some of their Unbundled Loop billing.

Qwest informed Covad and the other CLECs in attendance that Shared Loop (Line Sharing) is not billed based on zones, therefore, zone information cannot be provided. The CLEC representatives in attendance expressed their understanding with Qwest’s position on this issue.

After the meeting concluded, Qwest reviewed additional examples of Unbundled Loop bills that Covad maintained were missing zone or USOC information. As a result of this investigation, Qwest did uncover a condition restricted to the Western region where the English description and rate for any nonrecurring USOC appears on the bill, but the USOC does not appear. Trouble ticket number 197112 has been issued on the condition, and as of this date is pending investigation.

Sincerely,

Terri Kilker Process Specialist Qwest

============================================================= July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

SUBJECT: Qwest’s Change Request Response – CR # PC051403-2 (Adding Zone Information to Bills)

This is in response to Covad’s Change Request CR PC051403-2. This change request asks that zone information be reflected on Qwest billing so that Covad can reconcile its bills. Additionally, Covad requests that Qwest include USOCs for one-time charges on its bills.

Qwest has reviewed examples provided by COVAD and finds that for UNE-P products (which may or may not include line splitting), Qwest is currently providing the zone and USOC information; therefore, Qwest accepts this change request for UNE-P.

As a result of its investigation of the examples provided by Covad, Qwest now believes that Covad may have intended this change request to encompass more than UNE-P products. If Covad confirms that it intended for its change request to extend beyond UNE-P products, Qwest recommends that the change request be moved into evaluation status. Qwest would further recommend that Covad revise its change request to provide a precise list of products for which it desires zone and USOC information, and an ad-hoc meeting be scheduled where all appropriate subject matter experts at Covad and Qwest can review Covad’s requirements.

Sincerely,

Terri Kilker Process Specialist Qwest


Open Product/Process CR PC051403-3 Detail

 
Title: Request for Bi Weekly Technical Meetings on Pre Qual Issues
CR Number Current Status
Date
Area Impacted Products Impacted

PC051403-3 Completed
10/15/2003
PreOrdering, Ordering UNE
Originator: Berard, John
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad is requesting that Qwest provide by-weekly forums to discuss and review Pre-Qual Issues. Currently SBC provides this forum and we have found it very useful. Here is a link to the SBC Forum: https://clec.sbc.com/clec/shell.cfm?section=124 (It is listed as CLEC Technical Forum) The Forum is run by the Pre-Qual Product Manager.

Expected Deliverable:

As soon as possible.


Status History

5/14/03: CR Received

5/14/03: CR Acknowledged

5/23/03: Contact customer

5/27.03: Held clarification meeting

6/3/03: Sent clarification meeting notes to Covad

6/18/03: June CMP Meeting Mintues will be posted to the database.

7/8/03: Posted Response to database

7/16/03: July CMP Meeting Minutes will be posted to the database.

8/20/03: August CMP Meeting Mintues - see notes

9/3/03 : Notification for CLEC Forum distributed. 1st meeting scheduled for 9-11

9/17/03: CMP meeting notes will be posted to the database

9/17/03: Sep CMP Meeting minutes will be posted to the database

9/18/03: Notification for CLEC Forum distributed. 2nd meeting scheduled for 9-25

9/25/03: 2nd meeting held.

10/15/03 - Oct CMP meeting minutes will be posted to the database

1/23/03 - Corrected status to show completed


Project Meetings

October 15, 2003 CMP Meeting Cindy Buckmaster – Qwest advised two meetings have been held. The meeting on October 9 was cancelled. The next scheduled meeting is October 23, 2003. Discussion took place regarding why the meeting was cancelled. A variety of reasons were given, such as minimal agenda items, facilitator schedule conflict, action items still under investigation. Cindy Buckmaster requested that the CLECS send in additional agenda items prior to the meeting. John Berard – Covad agreed to close this CR.

September 17, 2003 CMP Meeting Cindy Macy-Qwest reported that the first meeting was held on September 11, 2003. There was a good turnout and the meeting was productive. Cindy advised the next scheduled meeting is September 25, 2003. Please be prepared with agenda items for the following meeting so Qwest can prepare and provide the information the CLECs are interested in. Bonnie Johnson-Eschelon advised they were told the purpose of the meeting is not to address process issues regarding DSL ordering. Some of the questions they have tie to a process but also related to loop qualification. Cindy Macy explained the intent of this forum is not to replace existing channels that you have. For example, if a change to a process is needed that should come in via CMP, or a change to the system, or if you have a question that your Service Manager would help you with, you should continue to use existing channels. This forum is to provide training and information regarding the Loop Qual tools and documentation. Bring questions to the forum and if it needs to be redirected it will be.

Qwest Loop Qual CLEC Technical Forum Minutes – September 11, 2003 Meeting

Attendees CLECs/Company: Qwest: Derek Hodges – Allegiance Ken Beck Laurie Mendoza – Allegiance Barb Brohl Jackie Stiles – AT&T Cindy Buckmaster Karen Uchida – AT&T Conrad Evans John Berard – Covad Dave Hahn Shiva Sharif –Covad Cheeron Halpern Kelly Morris – Electric Lightwave Lucy Higley* Chairperson Joanna Brower – Eschelon Cheri Hurless Kim Isaacs – Eschelon Lori Langston Katie James – Eschelon Cindy Macy Bonnie Johnson – Eschelon Dave Manica Todd Miller – Eschelon Dennis Pappas Dave Pries – Eschelon Crystal Soderlund Pete Scove – Eschelon Michelle Thacker Liz Balvin – MCI Russ Urevig Chad Warner - MCI Robert Weinstein Kathy McClenahan – Sun River Telecom Eric Yohe Ray Shannon – Sun River Telecom Jennifer Arnold – US Link Kathy Bryant – US Link Jackie Diebold – US Link Donna Dix – US Link Julie Pickar – US Link Jodie Thompson – US Link Kelly Tiegen – US Link

Summary of Meeting Lucy Higley opened the meeting, welcomed the participants to the forum, reviewed the agenda and took roll. Each CLEC and Qwest attendee shared their individual role with the group. The meetings will be held on the 2nd and 4th Thursdays of the month from 9-11 Mountain Time. Minutes and agendas will be posted on the Qwest Wholesale website at: http://www.qwest.com/wholesale/training/tradeShow.html

Cindy Buckmaster set the stage for the Forum which was requested by Covad via CMP CR #PC051403-03. She indicated that the forum’s focus is to educate and provide information about all the Qwest tools available for loop qualification. She also noted that the forum’s intent is not to discuss ordering and provisioning issues. Any issues that come out of the forum that result in enhancements to the tools will go through the normal CMP process. John Berard asked that the forum include discussion of upcoming enhancements to the tools.

Lucy Higley then walked through the Qwest Loop Qualification tools available to the CLECs. The review included discussion of: o Qwest DSL for Resale Tool o Unbundled ADSL Tool o Raw Loop Data Tool o Wire Center Raw Loop Data Tool o Manual Loop Make-up Look Up Process Documentation for these Tools can be located at in the Loop Qualification and Raw Loop Data CLEC Job Aid at: http://www.qwest.com/wholesale/downloads/lqrldclecjobaid.pdf

Conrad Evans then reviewed the August queries of the Raw Loop Data Tool submitted by Allegiance. One solution that was proposed by Qwest to the “no data found” issue was to ensure address validation is completed prior to submitting a query for the IMA tools. This will result in a higher response rate from the tools. Conrad also recommended that CLECs utilize the Raw Loop Data Tool “unassigned by address” query if identification of spare facilities is required at a location with no working service. Qwest suggested that the Manual Look Up Process can also be utilized if the query response is, “no data found”. John Berard mentioned that Covad had uncovered loops with unusually long/excessive lengths when utilizing the Wire Center Tool and had submitted them to Qwest for analysis. Qwest indicated that this is very helpful and appreciates getting this feedback, so the information in the tool can be made as accurate as possible. Lucy Higley mentioned that the loops in question had been corrected and now should appear with appropriate loop lengths.

John Berard asked if the tool provides data on pending jobs in LFACS and if so if this information is updated. He has seen responses that indicate a job is scheduled for 1997 which seems to be out-of-date. Dennis Pappas indicated that this information is not available for individual pending jobs.

Barb Brohl then did a wrap-up of the discussion and took several action items to be covered in the next few meetings.

Action Items

A follow-up meeting will be set up by Cheri Hurless, the Qwest Account Manager for Allegiance, to review the August queries they submitted in more detail. Laurie Mendoza of Allegiance will communicate to the other CLECs the outcome of that meeting.

Kim Issacs from Eschelon mentioned that they were receiving more responses of “no data found” on the Qwest DSL for Resale queries since Release 13.0 was implemented. She asked if something was added to the tool in 13.0 that would have caused the undetermined response rate to increase. Eschelon will provide their Qwest Service Manager, Jeff Tietz, with examples of this issue for further evaluation by Qwest.

Kelly Tiegen of US Link mentioned that after conversion of a customer from retail to an unbundled loop, they are not able to find the loop using the Qwest DSL for Resale query. US Link will send examples of this to their Qwest Service Manager, Dave Hahn, so that further investigation of the issue can take place. US Link may need to execute a different query to obtain the information they need.

Next Meeting will be in 2 weeks on Thursday, September 25th, 2003 9:00 AM – 11:00 AM Mountain Time; (10:00 – 12:00 Central; 11:00 – 1:00 Eastern; 8:00 – 10:00 Pacific)

Call in Number: 1.877.521.8688 Passcode: 3392394

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ August 20, 2003 Monthly Meeting notes Cindy Macy-Qwest advised we have a person in place that will be facilitating these meetings. Her name is Lucy Higley. We have the first meeting planned for September 11. A notification will go out advising of this. Lori Mendoza-Allegiance advised they have been trying to perform a ‘qualify by address’ using the RLD tool and no data comes up in the tool. She was advised she needs to resubmit these manually to have the tool updated. Liz Balvin-MCI advised they don’t use the qualify by address but they do search by TN and it is difficult to get data sometimes too. The CLECs requested at the first meeting to start going through the logistics and limitations of the tool and then understand the data. The CLECs requested for Qwest to begin investigation on the issue reported regarding no data in the tool. They would like Qwest to provide status on this issue at the first meeting. Cindy Macy-Qwest requested for the CLECs to send issue description and examples to her at cynthia.macy@qwest.com and I will forward those to the team. Bonnie Johnson-Eschelon advised she had hoped this meeting would be held earlier as we reported that we would try to set it up for mid-August.

July 16, 2003 Monthly Meeting notes Cindy Buckmaster reviewed Qwest’s response and advised Qwest accepts this CR. Cindy advised Qwest is currently working to identify the person who will lead this meeting. The plan is for Qwest to initially review and clarify the in-place on-line documentation and address any questions. Additional issues that are identified will then be addressed. We anticipate the forum to begin the middle of August. This CR will move to Development.

June 18, 2003 Monthly Meeting notes John Berard – Covad explained they want to meet with the Product and Technical team to discuss and understand the data and issues on PreQual functions. This process is in place with SBC. Meeting would help to drive clarity, review examples directly associated to PreQual questions and functions. All CLECS could attend to go through issues and agenda. Eschelon and ATT are in support of this.

Clarification Meeting

May 27, 2003 1-877-572-8687 3393947# PC051403-3 Request for Bi-Weekly Technical Meetings on Pre-Qual Issues

Attendees Dave Manica – Qwest Dave Hahn – Qwest John Berard – Qwest Craig Suellentrop – Qwest Cindy Macy – Qwest

Meeting Agenda 1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change John Berard – Covad reviewed the change request. John explained that Covad pulls data from Qwest’s Raw Loop Data tool and then loads the data into Covad’s PreQual too. Covad uses their PreQual tool so their customers can PreQual their line. Covad finds inconsistencies in the data so they would like to meet with Qwest on a regular basis to understand the data. Covad said SBC holds a call with Covad so they can work through technical and data issues. This is a fast way to resolve questions and issues. Covad would like to have a standing biweekly meeting set up with Qwest. Cindy Macy – Qwest asked what Covad would want on the BiWeekly agenda. Covad replied the items might change based on the current issues. The agenda with SBC covers items such as: review of the previous minutes, loop length questions, TN# missing from database, tool / system enhancements, service address level vs. loop level, loop medium codes copper and fiber, technical and product related discussions. John – Covad advised he would like to have Product and Technical representatives from Qwest attend the call. Dave Manica asked if Covad had certain error reports that Qwest could investigate. Covad advised yes and this would be a good agenda item. Covad provided their contact at SBC – John Milan Product Manager. Qwest can contact this person to discuss their process if needed. Cindy – Qwest asked John if all CLECs could attend this meeting. John advised yes it would be open to the CLEC Community.

3.0 Confirm Areas & Products Impacted PreQual tool at a Bulk and Individual Level

4.0 Confirm Right Personnel Involved Dave Manica, Craig Suellentrop, Michelle Thacker

5.0 Identify/Confirm CLEC’s Expectation Qwest to meet with Covad BiWeekly or as needed to discuss Loop Qual issues

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) Covad will present the CR at the June CMP Meeting Qwest will provide our Response at the July CMP Meeting


CenturyLink Response

For Review by the CLEC Community and Discussion at the July 16, 2003 CMP Meeting

July 8, 2003

Covad John Berard

SUBJECT: Qwest’s Change Request Response – CR #PC051403-1 Request for Bi-Weekly Technical Meetings on Pre-Qual Issues

This letter is in response to Covad’s Change Request (CR) PC051403-1. This CR requests that Qwest establish a Bi-Weekly Technical Meeting on Pre-Qual Issues.

Qwest accepts this CR and is currently developing: * A process and the structure of a Bi-Weekly Technical Forum focused on use and interpretation of the Raw Loop Data Tools * Qwest will chair the calls and we will have resources available to answer questions asked during the forum * Qwest proposes that the first few meetings will be dedicated to bringing the CLECs up to date on where documentation regarding the tool can be found. Subsequent meetings will be structured to fit the CLECs Raw Loop Data needs. * The forum effectiveness will be monitored to determine future meeting need and frequency

Qwest requests this CR be placed in Development Status and will provide an update at the August CMP Meeting.

Sincerely,

Cindy Buckmaster Qwest

Cc: Barb Brohl


Open Product/Process CR PC051903-1 Detail

 
Title: Real Time API Connection to Raw Loop Data
CR Number Current Status
Date
Area Impacted Products Impacted

PC051903-1 Crossover
7/27/2009
Pre Ordering, Ordering UNE - Line Sharing, Line splitting, Loop Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner:
Director:
CR PM:

Description Of Change

Covad is requesting the implementation of a new Real Time Interface connection to Pre-Qual Raw Loop Data. Currently BellSouth has this type of interface, which has greatly increased Covad’s ability to determine the loop characteristics early on in the ordering process (pre-order).

The major advantage of this system is that it allows a DLEC/CLEC real time access to LFACS data. This information is critical to the ability of a DLEC to determine early on if the high frequency portion of the loop can handle DSL service. Here is a description of BellSouth’s system:

The information contained in LQS (Loop Qual System) is derived from the Loop Engineering Assignment Data(LEAD) Database and provides a “best effort” response regarding a loop’s ability to support BellSouth’s ADSL service.

The LEAD Database is a once-per-month-per-wire-center “snapshot” of the information

contained in the Loop Facilities Assignment and Control System (LFACS) Database.

1/30th of all wire centers are updated every day. Currently there is a 98% accuracy rate

on returned responses within LQS.

Here's a public link to the LQS (Loop Qualification System, aka SuperLoopy)

document:

http://www.interconnection.bellsouth.com/guides/bpobr/pdf/lqs.pdf

This document is mainly LQS Application focused. The Java API is briefly mentioned,

referencing the following, more technical link (however, it is not public):

http://lqs.bellsouth.com

All the data accessible from the application and more is available via the API.

Eric Fogle is the appropriate BellSouth contact for additional information on this system. The effort via OBF, for which he was the CLEC workshop chair, was very much along these lines.

Eric Fogle can be reached at 404-927-3433, Eric.Fogle@BellSouth.com

Expected Deliverable:

As soon as possible


Status History

5/19/03: CR Received

5/20/03: CR Acknowledged

5/23/03: Contacted customer to schedule Clarification call

5/30/03: Held Clarification Call - discussed this would potentially cross over to systems

6/18/03: June 18 P/P CMP meeting minutes will be posted to the database- obtained ok to cross CR over to systems SCR051903-1


Project Meetings

June CMP Product Process CMP Meeting Notes Cindy Macy - Qwest advised during the Clarification call it was determined that this CR should be a systems CR. Covad agreed that this should cross over to systems.

CLEC Change Request – PC051903-1 Clarification Meeting Friday May 30, 2003

Attendees Cindy Macy – Qwest CRPM Michelle Thacker - Qwest Communications Dave Manica - Qwest Communications Craig Suellentrop – Qwest Communications John Berard – Covad Raj – Covad Shiva Sharif – Covad Cindy Buckmaster - Qwest Communications Cliff Dinnwiddie - Qwest Communications

Introduction of Attendees Macy-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Berard-Covad reviewed the CR. Berard explained they would like access to the individual TN Loop Qualification data that is the most current via a synchronous API. This data is available in IMA currently but via EDI or GUI and Covad would like to access via an API connection.

Covad currently uses the Raw Loop Data tool to access loop qual data. They download the data to their own tool. This data is not always current or accurate. Covad wants the most current data, at an Individual TN level, via an API connection. Covad would like a Pre Qual API connection to IMA. Currently Covad also has access to Pre Qual EDI but this is not a fast enough response time due to the volume of data they download.

Qwest and Covad discussed if there were certain data elements that were needed. Covad advised they would like access to the same data that they get from Pre Qual IMA EDI today, except in a synchronous API connection. If they want additional data elements added that would be a different CR.

The team discussed that this should be a systems CR. Cindy agreed to check with the systems team and cross this CR over.

Confirm Areas and Products Impacted Macy-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved Macy-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation Macy-Qwest reviewed the request to confirm Covad’s expectation.

Identify any Dependant Systems Change Requests Macy-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan Macy-Qwest asked attendees if there were any further questions. There were none. Macy-Qwest stated that the next step was to cross this CR over to systems.


Open Product/Process CR PC021403-1 Detail

 
Title: Bulk Loop Qual Data Refresh Intervals
CR Number Current Status
Date
Area Impacted Products Impacted

PC021403-1 Denied
5/21/2003
Pre-Ordering, Provisioning, Ordering UNE, Line Sharing, Line Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Diamond, Paul
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad requests that Qwest revise their existing data refresh interval from the current 1 month to a minimum of every two weeks with a preference of once a week. Qwest’s current process causes false positive and false negative results for Covad’s bulk prequal tool because of outdated data.

Expected Deliverable:

As soon as possible.


Status History

02/14/03 - CR Submitted by Covad

02/17/03 - CR acknowledged by P/P CMP Manager

2/19/03 - CR posted on the web

2/19/03 - CR presented by Covad at the Feb. CMP Meeting

2/20/03 - Contacted customer to schedule clarification meeting

2/26/03 - Held Clarification Meeting with customer

3/11/03 - Entered Response in database

3/12/03 - Sent Response to Covad

3/19/03 - March CMP Meeting minutes will be posted to the Project Meeting section

4/8/03 - Posted response to database

4/16/03 - April CMP Meeting minutes will be posted to the database

5/14/03 - Sent response to CLEC via email and posted to database on 5/13

5/21/03 - May CMP Meeting Minutes will be posted to the database


Project Meetings

May 21, 2003 CMP Meeting Minutes Jamal B – Qwest reviewed the response and explained their investigation determined it was economically infeasible due to hardware/cpu and software system costs. Cindy Macy – Qwest explained approximately 40 central offices are processed every night, thus by the end of the month all central offices are updated. To increase the frequency of processing requires system upgrades. The status of this CR will change to denied.

April 16, 2003 CMP Meeting PC021403-1 Bulk Loop Qual Data refresh Intervals

Paul Diamond – Qwest advised we are still investigating what is involved to answer this request. Qwest would like to leave this CR in Evaluation Status. John Berard-Covad advised that was okay.

March 19, 2003 CMP Meeting Cindy Macy – Qwest advised we are reviewing the system and process impacts for updating the refresh intervals. We are looking at the volume of changes that occur and alternate methods of obtaining current information. Bonnie Johnson – Eschelon advised that John Berard – Covad sent an email that also requested the individual query tool to be included in this CR. I advised the same data updates the Bulk and Indivual queries so by default the individual query would be impacted. This CR will move to Evaluation status.

Clarification Meeting February 26, 2003 10:00 – 11:00 1-877-572-8687 3393947#

PC021403-1 Bulk Loop Qual Refresh Intervals Attendees John Berard – Covad Paul Diamond – Qwest Michelle Thacker – Qwest John Gallegos – Qwest Cindy Macy – Qwest

Meeting Agenda: Introduction of Attendees Attendance was noted

Review Requested (Description of) Change John Berard Covad advised the data in the Bulk Loop Qual tool is not fresh (current) enough. Other ILECs (Bell South) refresh this data every 2 weeks and they have a real time interface. All other ILECs refresh weekly. Qwest updates data every 20 days and sometimes it takes up to 2 months. On occasion Covad has to issue a trouble report to get the data refreshed. Covad would like Qwest to refresh data weekly.

Michelle Thacker-Qwest verified we are not talking about the IMA interface. The IMA interface is a single telephone number qualification.

John explained they pull a download of the data (flat file) and load it into their own tool. They look at the data by wire center and look for a current refresh date. Paul Diamond-Qwest verified Covad goes to the ecom.qwest site and access the Raw Loop Data (RLD) Tool from a url. A digital certificate is needed. Cindy Macy-Qwest asked if the data is bulk updated every 30 days or if it is a ‘rolling 30 days’. John Berard-Covad explained each wire center gets updated on its own 30 day schedule so there are new updates each day based on all the different wire centers. Each individual wire center only updates around every 30 days. John would like the wire center data updated on a rolling 5-10 business day period.

Cindy Macy-Qwest recapped the comments from Mike Zulevic from the February CMP meeting when Mike presented the CR to the CLEC community. Mike Zulevic said they find errors in the data, positive and negative tests, the loops really is or isn’t qualified, they want the data updated every 2 weeks or weekly. Mike also asked if the bulk data is the same as the TN view data. Qwest advised ‘yes’.

Michelle Thacker-Qwest advised she does not support the ECOM site. Most of this support comes from the IT side. John Gallegos-IT agreed he would identify a resource to help the team. John would provide to Cindy Macy-Qwest that person’s name by 2-27-03. Paul Diamond advised David Manica-Qwest from Product Management is knowledgeable on the RLD tool.

Confirm Areas & Products Impacted UNE Loop, Line Sharing

Confirm Right Personnel Involved The team discussed we need to find additional resources to help us understand the Raw Loop Data Tool and the impacts from this CR. John Gallegos advised he would identify an IT resource. John Berard-Covad advised he would be glad to meet with us again and invite one of his technical people from Covad . Cindy Macy agreed she would check further to identify another business resource knowledgable on RLD tool. Paul Diamond advised he contacts David Manica for questions on RLD tool.

Identify/Confirm CLEC’s Expectation To provide more current data in the RLD tool (refresh every 2 weeks)

Identify any Dependent Systems Change Requests John Berard-Covad advised SCR112002-1 is open to add 3 new data fields to the IMA PreQual tool.

Establish Action Plan (Resolution Time Frame) Qwest will meet to begin investigation of CR and our Initial Response will be provided at the March 19, 2003 CMP Meeting.

2/19/03 February CMP Meeting - This CR was discussed as a walk-on CR at the February CMP Meeting. Mike Zulevic- presented it for John Berard and explained Covad was interested in a more current refresh of data to be every 2 weeks or weekly, to prevent errors in data, invalid determinations of positive and negative, the loop is or isn't really qualified. The question was asked if the data is the same in bulk and individual form and Qwest- Houston replied it was.


CenturyLink Response

For Review by CLEC Community and Discussion at the May 21, 2003 CMP Meeting

May 14, 2003

Covad Communications John Berard

SUBJECT: Covad’s Change Request Response – CR #PC021403-1 Bulk Loop Qual Data Refresh Intervals

This letter is in response to Covad Communications Change Request (CR) PC021403-1. This CR requests that Qwest revise their Bulk Loop Qual data refresh interval from the current 1 month to every two weeks with a preference of once a week.

Qwest has completed the investigation and identified system impacts for changing the data refresh intervals. The impact to make this change is estimated at 6,000 hours and hardware and software costs of $1.7M. The total of hardware, software and resource costs would be a more than $2.0 million and could grow based upon capacity requirements.

As a result of this investigation, Qwest respectfully denies this change request due to it being economically not feasible based on the system impacts.

Sincerely,

Jamal Boudhaouia Technical Regulatory

April 9, 2003

For Review by CLEC Community and Discussion at the April 16, 2003, CMP Product/Process Meeting

John Berard Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC021403-1 Bulk Loop Qual Data Refresh Intervals

This letter is in response to Covad Communications Change Request (CR) PC021403-1. This CR requests that Qwest revise their Bulk Loop Qual data refresh intervals from the current one month to every two weeks with a preference of once a week.

There are a number of issues to be analyzed in answering this request. For this reason, Qwest would like to leave this Change Request in Evaluation Status.

Qwest will provide a status update at the May CMP meeting.

Sincerely,

Paul Diamond Qwest Corporation

CC: Mary Retka

For Review by CLEC Community and Discussion at the March 19, 2003 CMP Meeting

March 11, 2003

Covad Communications John Berard

SUBJECT: Covad’s Change Request Response – CR #PC021403-1 Bulk Loop Qual Data Refresh Intervals

This letter is in response to Covad Communications Change Request (CR) PC021403-1. This CR requests that Qwest revise their Bulk Loop Qual data refresh interval from the current 1 month to every two weeks with a preference of once a week.

Qwest is currently investigating and reviewing the following impacts from this request.

- The refresh process that updates the data (system and process impacts) - The volume of change - Alternate methods of obtaining current information

Qwest will schedule an additional Clarification Call with Covad to ensure we understand how this data is viewed after it is extracted from the Raw Loop Data Tool.

Qwest requests this CR be placed in Evaluation Status and will provide an update at the April CMP Meeting.

Sincerely,

Qwest


Open Product/Process CR PC031103-1 Detail

 
Title: Convert Common Area Splitter Collocation to Cageless Shelf at a time Collocation
CR Number Current Status
Date
Area Impacted Products Impacted

PC031103-1 Completed
4/21/2004
Maintenance, Repair Collocation - Physical, Virtual
Originator: Berard, John
Originator Company Name: Covad
Owner: Nelson, Steve
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Revised Description of Change (07-14-03):

To facilitate the CLEC’s option to perform maintenance, Covad requests the following changes.

1. Qwest allow the CLEC to access the front of the splitter shelf for testing thereby permitting test of a splitter card by the CLEC (Diagram A).

2. Qwest will allow the CLEC to perform maintenance on the splitter cards including replacement as necessary.

3. Qwest will continue to provision the CAS and will control the engineering configuration database for CAS. For new circuits, Qwest will install and provision the new splitter cards as necessary.

4. Qwest will continue to maintain the splitter shelves and Common Area Splitter bays.

5. CLEC’s will have the option to perform maintenance on the splitter cards or continue to have Qwest control all maintenance.

6. If the CLEC impairs a Qwest voice customer during the maintenance of the splitter cards Qwest may temporarily remove the data portion of the circuit.

7. The monthly recurring fees will be adjusted to remove the maintenance cost for those CLECs electing to perform the CAS splitter card maintenance.

8. The CAS shelves will be clearly designated to identify those shelves maintained by Qwest or the CLEC.

Original Description of Change (03-11-03):

Covad requests to be allowed to convert any or all existing Common Area Splitter Collocation arrangements to Cageless Shelf at a time Collocation. The current arrangement, being a type of Virtual Collocation, requires Qwest technicians to perform all maintenance associated with the splitters and splitter cards. While this process has worked in some central offices, Covad continues to experience problems related to improperly performed maintenance including splitter cards removed in error, splitter cards not installed properly, splitter cards replaced unnecessarily and cards removed as defective which cannot be located. Further, Covad and Qwest have not been able to jointly develop and document a workable process for the replacement of defective splitter cards. Covad has been trying to resolve these problems for over three years but continues to have the same experiences. These problems, coupled with the high non-recurring costs, have caused Covad to begin placing splitters in its own collocation arrangements, as additional capacity is required. It is Covad’s hope that by converting the existing splitter capacity from Common Area Splitter Collocation to some form of Cageless Shelf at a time Collocation, most of the maintenance problems will be resolved. This proposal would remove the splitter maintenance responsibility from Qwest and place it with Covad. This conversion may also require adjustments to existing monthly recurring charges applicable to the current product.

Expected Deliverable:

As Soon As Possible


Status History

03-12-03 - CR Acknowledged

03-26-03 - Clarification Meeting held

04-16-03 - Presented at CMP Meeting

05/21/03 - Qwest response presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

08/21/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/12/04 - Qwest sent PROD.01.12.04.F.01237.ComAreaSplitColloV11 proposed effective date 2/26/04

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/11/04 - Qwest issued Final notification PROD.02.11.04.F.01324.FNL_Common_Area_Splitter effective date 2/26/04

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

04/21/04 April CMP Meeting Steve Nelson with Qwest said that John Berard with Covad said we would be able to close this CR. Mike Zulevic with Covad agreed this could be closed. Mike said they are 70% complete with labeling splitters and will let Steve know when they are 100% complete. This CR will move to Completed status.

- 03/17/04 March CMP Meeting Steve Nelson with Qwest gave the update that the PCAT changes were effective on 2/26/04 and the contract amendment is available. This CR will move to CLEC Test status.

-- 02/18/04 February CMP Meeting Dave Williams with Qwest said that the PCAT changes will be effective on 2/26/04 and a contract amendment will be available at the same time. This CR will remain in Development status.

1/21/04 January CMP Meeting Dave Williams with Qwest provided an update to this CR and said changes for the PCAT were released 1/12/04 and the proposed effective date is 2/26/04. Mike Zulevic asked if the change would be available across the board on 2/26/04. Dave said yes. This CR will remain in Development status.

12/17/03 December CMP Meeting Dave Williams with Qwest provided an update to this CR which allow the CLEC to maintain POTS splitter cards. Dave said changes for the PCAT should be out soon. This CR will remain in Development status.

11/19/03 November CMP Meeting Dave Williams with Qwest provided an update to this CR and said we will be submitting level 3 changes for the PCAT and plan to have available in the December timeframe. Dave will send a copy to Mike Zulevic and John Berard for comments. This CR will remain in Development status.

10/15/03 October CMP Meeting Dave Williams with Qwest provided an update to this CR which provides CLECs the option to do maintenance or have Qwest do the maintenance on splitter cards. There will be changes made to the PCAT in November. This CR will remain in Development status.

09/17/03 September CMP Meeting Dave Williams provided an update to this CR and said that we have moved forward with a trial beginning 8/25 in Seattle areas and the trial has been well received by both Qwest and Covad. There will be a process change written in the next few weeks. This CR will remain in Development status.

CMP Meeting 08-13-03

White-Qwest presented the Qwest acceptance of the revised Covad Description of Change. Zulevic-Covad stated that Qwest and Covad were testing the process in 15 Central Offices in Washington state. He stated that it looked as if the process was progressing very well.

============================================

CMP Meeting 07-16-03

White-Qwest presented the status and stated that Covad had submitted a revised description of change that Qwest was working on. Williams-Qwest stated that Qwest would probably start a trial with Covad on August 1. Berard-Covad stated that this was good progress. CR remains in Development. ============================================== CMP Meeting 06-18-03

Williams-Qwest presented the Qwest response. Zulevic-Covad stated that he had reviewed the response and that the Qwest recommended solution addressed a majority of his concerns. He asked how to proceed. White-Qwest recommended that Covad revise their description of change to align with the Qwest recommendation. He stated that he could forward a suggestion to Zulevic for approval. Zulevic-Covad agreed. White-Qwest stated that the change request would move into Development.

========================================================== CMP Meeting 05-21-03

White-Qwest presented the Qwest response and suggested the CR be moved to Evaluation status. ==========================================

04-16-03 - CMP Meeting

Zulevic-Covad presented the CR. Williams-Qwest stated that another option would be to move the splitters to the cageless lineup. Zulevic-Covad stated that this was to difficult logistically. Williams-Qwest asked if Covad expected Qwest to develop a per shelf collocation cost. Zulevic-Covad stated that he expected a monthly recurring rental rate. Williams-Qwest asked if Covad had discussed this issue with any other CLECs. Zulevic-Covad stated that he had not and that this would probably create a bifurcated process for Qwest. Williams-Qwest stated that he would query other DLECs for interest. Van Meter-AT&T stated that AT&T would like to be involved in any development calls for this CR.

==========================================================

Clarification Meeting Wednesday, March 26, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Dave Williams – Qwest Jeff Cook – Qwest Mike Zulevic – Covad John Berard – Covad Becky Neesen - Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Berard-Covad reviewed the CR. Zulevic-Covad this has been a tough issue for both companies and that Covad was just looking for a possible solution.

Williams-Qwest asked if Covad was intending to physically move splitters. Zulevic-Covad stated that there was no move necessary; Covad would just take over maintenance of splitters. Williams-Qwest stated that the issue was that when Covad provisions loops Qwest sometimes makes mistakes.

Cook and Williams had no further questions.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved. He stated that Lillian Robertson would also be involved in analyzing this CR. Williams-Qwest stated that he would work with Robertson on this CR.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the April Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

August 12, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the August 20, 2003, CMP Product/Process Meeting

John Berard Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC031103-1

Qwest accepts this revised CR and proposes offering an optional maintenance program for Common Area Splitter configurations.

Diagram A, attached, depicts a typical configuration for a CAS

In this configuration Qwest maintains the common area splitter configuration and all provisioning of loops. Presently Qwest also performs all maintenance on the splitter shelf including splitter card installation and replacement. Qwest also keeps records of CAS in the administrative/engineering system SWITCH/FOMS.

The current DMARC separating the CLEC controlled cabling from the Qwest network is the rear of the splitter shelf as shown in Diagram A. The CLEC also has access to the ICDF frame and specifically the voice block for testing purposes (Diagram A).

Under this revised plan, the CLEC would have the option to have Qwest perform the maintenance, as is currently the practice, or the CLEC could perform the splitter card maintenance.

To facilitate the CLEC’s option to perform maintenance, Qwest proposes the following changes.

1. Qwest will allow the CLEC to access the front of the splitter shelf for testing thereby permitting test of a splitter card by the CLEC (Diagram A). 2. Qwest will allow the CLEC to perform maintenance on the splitter cards including replacement as necessary. 3. Qwest will continue to provision the CAS and will control the engineering configuration database for CAS. For new circuits, Qwest will install and provision the new splitter cards as necessary. 4. Qwest will continue to maintain the splitter shelves and Common Area Splitter bays. 5. CLEC’s will have the option to perform maintenance on the splitter cards or continue to have Qwest control all maintenance. 6. If the CLEC impairs a Qwest voice customer during the maintenance of the splitter cards Qwest may temporarily remove the data portion of the circuit. 7. The monthly recurring fees will be adjusted to remove the maintenance cost for those CLECs electing to perform the CAS splitter card maintenance. 8. The CAS shelves will be clearly designated to identify those shelves maintained by Qwest or the CLEC.

This solution addresses Covad’s primary concern of maintenance of the CAS and enables Covad and other CLECs to dispatch their technicians to correct a defective splitter card without having to generate a trouble/maintenance ticket through Qwest.

For Qwest, the proposed solution will require training and process updates but will not require the introduction of an entirely new product that would be cost prohibitive.

The CLECs also have the option to place the splitters in their collocation site eliminating any maintenance issues.

Sincerely,

David Williams Qwest Wholesale Product Manager 303-896-8166

================================================ June 11, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, CMP Product/Process Meeting

John Berard Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC031103-1

Covad has requested a change to the common area splitter product as follows: “Covad requests to be allowed to convert any or all existing Common Area Splitter Collocation arrangements to Cageless Shelf at a time Collocation.” In response to this CR Qwest provides the following response.

1. Issue 1. Covad requested to convert all existing Common Area Splitter Collocation arrangements to Cageless Shelf at a time Collocation. In order to change what now is a virtual collocation product to a cageless product, Qwest would require the development of a brand new product. Qwest's cageless collocation process is based on a per bay basis so this would not follow as a simple variation to the existing cageless collocation process. The Common Area Splitters are currently provisioned and maintained by Qwest. In a proposed conversion to a cageless product, a new provisioning process would be required in addition to a reconfiguration of the network to redefine the DEMARC. Qwest billing software changes would also be required. All of these changes would require significant funding from Qwest and none are practical when Common Area Splitter collocation is an optional process and experiences low ordering volumes. The CLEC always has the option to locate the splitters into their collocation space. The chart below summarizes the required effort to implement a new common area splitter (CAS) proposed by Covad.

Task Person Months Define New Product 4 Create M&P 1 Define Provisioning Process 4 Create M&P 1 Implement software changes for billing system 3 Update PCAT and documentation 2 Create Amendment Language 2 Total 17

Qwest rejects this portion of the request because it is not economically feasible.

2. From Qwest’s further evaluation of this change request, it appears that Covad’s primary issue is maintenance of the splitter and, specifically, the splitter cards. While there was no documentation provided with this CR to indicate that any maintenance issues exist, Qwest proposes offering an optional maintenance program for Common Area Splitter configurations to address Covad's apparent concern.

Diagram A, attached, depicts a typical configuration for a CAS

In this configuration Qwest maintains the common area splitter configuration and all provisioning of loops. Presently Qwest also performs all maintenance on the splitter shelf including splitter card installation and replacement. Qwest also keeps records of CAS in the administrative/engineering system SWITCH/FOMS.

The current DMARC separating the CLEC controlled cabling from the Qwest network is the rear of the splitter shelf as shown in Diagram A. The CLEC also has access to the ICDF frame and specifically the voice block for testing purposes (Diagram A).

Under this revised plan, the CLEC would have the option to have Qwest perform the maintenance, as is currently the practice, or the CLEC could perform the splitter card maintenance.

To facilitate the CLEC’s option to perform maintenance, Qwest proposes the following changes.

1. Qwest will change the DMARC for CAS and allow the CLEC to access the front of the splitter shelf for testing thereby permitting test of a splitter card by the CLEC (Diagram A). 2. Qwest will allow the CLEC to perform maintenance on the splitter cards including replacement as necessary. 3. Qwest will continue to provision the CAS and will control the engineering configuration database for CAS. For new circuits, Qwest will install and provision the new splitter cards as necessary. 4. Qwest will continue to maintain the splitter shelves and Common Area Splitter bays. 5. CLEC’s will have the option to perform maintenance on the splitter cards or continue to have Qwest control all maintenance. 6. If the CLEC impairs a Qwest voice customer during the maintenance of the splitter cards Qwest may temporarily remove the data portion of the circuit. 7. The monthly recurring fees will be adjusted to remove the maintenance cost for those CLECs electing to perform the CAS splitter card maintenance. 8. The CAS shelves will be clearly designated to identify those shelves maintained by Qwest or the CLEC.

This solution addresses Covad’s primary concern of maintenance of the CAS and enables Covad and other CLECs to dispatch their technicians to correct a defective splitter card without having to generate a trouble/maintenance ticket through Qwest.

For Qwest, the proposed solution will require training and process updates but will not require the introduction of an entirely new product that would be cost prohibitive.

The CLECs also have the option to place the splitters in their collocation site eliminating any maintenance issues.

Sincerely,

David Williams Qwest Wholesale Product Manager 303-896-8166

======================================

May 14, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the May 21, 2003, CMP Product/Process Meeting

John Berard Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC031103-1

This is a preliminary response regarding Covad CR PC031103-1. This CR requests that CLECs be allowed to convert any or all existing Common Area Splitter Collocation arrangements to Cageless Shelf at a time collocation.

Qwest is currently working internally to identify a solution to this request. Because there are a large number of issues Qwest must analyze, Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the June CMP meeting.

Sincerely,

Dave Williams Product Manager Qwest Corporation


Open Product/Process CR PC012703-1 Detail

 
Title: Shorten Loop Conditioning Interval from 15 to 5 days
CR Number Current Status
Date
Area Impacted Products Impacted

PC012703-1 Denied
1/27/2003
Pre-ordering, Ordering, Provisioning UNE Line Share & Line Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Moreland, Heidi
Director:
CR PM: White, Matt

Description Of Change

Covad requests that Qwest reduce its current provisioning interval for Loop Conditioning to a standard of 5 days. This will place it more in line with industry averages.

Expected Deliverable

Covad requests that Qwest reduce its current provisioning interval for Loop Conditioning to a standard of 5 days


Status History

01/27/03 - CR Submitted by Covad

01/27/03 - CR acknowledged by P/P CMP Manager

01/30/03 - Clarification Meeting scheduled for 2/3/03

02/03/03 - Clarification Meeting conducted

02/19/03 - CR presented at the CMP Meeting

03/16/03 - Qwest response presented at CMP Meeting

04/16/03 - Qwest revised response presented at CMP Meeting


Project Meetings

04-16-03 - CMP Meeting

Moreland-Qwest presented the Qwest denial response. Berard-Covad stated that Covad was evaluating whether to escalate this issue. The CR was moved to denied status.

===========================================================

03-19-03 - CMP Meeting

Smith-Qwest stated that Qwest would like to continue to evaluate this CR. CR moved to evaluation status.

==============================================================

02-19-03 - CMP Meeting

Zulevic-Covad presented the CR. He stated that Qwest is currently processing orders in less than the 15 day interval; in many cases in fewer than 5 days. He stated that this caused both Qwest and Covad excess work. He stated that if Qwest established a 5 day interval, Covad understood that there would be instances when Qwest could not meet the interval. White-Qwest stated the CR would move to Presented status.

==============================================================

Clarification Meeting 3:00 PM (Mountain Time) / Monday, February 3, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Deb Smith – Qwest Bob Mohr – Qwest Neil Houston – Qwest John Berard – Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Berard-Covad reviewed the CR. Smith-Qwest asked which products this CR was for. Berard-Covad stated that it was for the products that Covad ordered: UNE unbundled loops and line sharing. White-Qwest asked which ILECs Covad was referring to in its description. Berard-Covad stated that SBC and Bell South had 5-10 day intervals and that Qwest had the longest interval at 15 days.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the February Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

April 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the April 16, 2003, CMP Product/Process Meeting

03/28/03

Mike Zulevic Director – GEA Covad Communications

SUBJECT: Qwest’s Change Request – CR PC012703-1

This letter is in response to CLEC Change Request PC012703-1. This CR is a request by Covad for Qwest to reduce its current provisioning interval for Loop Conditioning to a standard of 5 days.

Qwest is denying this request because it is economically not feasible. The following supports this decision:

Covad has stated that the current interval causes excess work for both Qwest and Covad. Contrary to that assumption, Qwest finds that the opposite is true for Qwest work. After an analysis of the impact to Qwest workforces, Qwest has determined an additional 150-185 resources would be required to respond to a 5 day interval. This would include: - 25-30 Engineering resources to issue jobs more quickly - 5 resources in the Construction Management Centers to process the jobs through on an escalated basis - A minimum of 120–150 Field resources across the 14 state region to complete the conditioning work

Economic conditions currently do not facilitate an increase in head count to support the proposed interval reduction.

Qwest has voluntarily initiated the use of Line Moves and Removal of UDCs in order to provision Line Sharing, ADSL-capable Unbundled Loops and Qwest retail DSL products (see CR #PC022403-5, PC022403-6, PC022403-7 and PC022403-8). Qwest feels that this initiative will reduce the need for line conditioning for many orders as well as reduce the provisioning interval for those orders utilizing a Line Move.

Qwest has also initiated a new Bulk Deload project, which will be to both the CLECs and Qwest’s advantage in responding to their customers’ service requests by eliminating the need to require line conditioning for many orders. Qwest has notified the CLEC community of this project through the Joint Planning Process.

Covad has stated that SBC and Bellsouth line conditioning intervals are at 5-10 days. Qwest respectfully disagrees. Qwest research of similarly situated ILECs indicate: - SBC has a 10 business day interval - Bellsouth has an 11-12 business day interval: the standard interval of 11 business days and the LSR processing interval of 3-24 hours equals the total service interval - Verizon has a 15 business day interval

Qwest finds the Qwest current line conditioning interval of 15 business days to be within the nationwide standard.

Sincerely, Heidi Moreland Staff Advocate Policy and Law

=======================================================================

March 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the March 19, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC012703-1

This is a preliminary response regarding Covad CR PC012703-1.

Qwest has reviewed the current Loop Conditioning interval. There are a number of issues Qwest must analyze before answering this request. For this reason, Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the April CMP meeting.

Sincerely,

Debra Smith Product Manager Qwest Corporation


Open Product/Process CR PC012703-2 Detail

 
Title: DATA Migration Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC012703-2 Completed
4/15/2009
Pre-ordering, ordering, provisioning UNE Line Sharing & Line Splitting
Originator: Berard, John
Originator Company Name: Covad
Owner: Soderlund, Crystal
Director:
CR PM: Harlan, Cindy

Description Of Change

Covad requests that Qwest develop and document a Data Migration process with minimal or no disruption of service. This migration process should be from CLEC to CLEC, CLEC to ILEC, ILEC to CLEC and apply to all data services including but not limited to second line, line sharing, loop splitting, and line splitting.

Expected Deliverable

As soon as possible.


Status History

01/27/03 - CR Submitted by Covad

01/27/03 - CR acknowledged by P/P CMP Manager

1/31/03 - Contacted customer to schedule Clarification Meeting

2/3/03 - Clarification Meeting scheduled for 2/5/03 1:00 - 2:00 MDT.

2/5/03 - Held Clarification Meeting. John Berard agreed this CR does not include second line, or loop splitting.

2/11/03 - Sent Clarification Meeting notes to Covad, and posted to the database

2/19/03 - February CMP Meeting minutes will be posted to the database. Status of CR changed to presented.

3/19/03 - March CMP Meeting minutes will be posted to the database.

4/16/03 - April CMP Meeting minutes will be posted to the database

5/21/03 - May CMP Meeting minutes will be posted to the database

6/2/03 - Set up CLEC Review Meeting to review the logistics and content of the Data Migrations PCAT for Thursday June 12

6/12/03 - Held CLEC Meeting to review PCAT updates. Covad agreed to review each scenerio in more detail and review the LSOG for LSR issuance instructions. Covad will advise Qwest of any further issues at the June CMP Meeting. Qwest agreed to change the scenerio document from a search engine link to a link within the PCAT.

6/18/03 - June P/P CMP meeting minutes will be posted to the database

7/1/03 - John reviewed the scenario document and advised he would like the following 2 scenarios added: - ILEC Voice migrated to CLEC Voice/DLEC DSL (linesplit)

- CLEC Voice/DLEC DSL (Linesplit) migrated to ILEC Voice/DLEC DSL (Lineshare). Crystal will review the request and provide information at July CMP.

7/16/03 - July P/P CMP Meeting minutes will be posted to the database

8/20/03 - August CMP Meeting minutes will be posted to the database

9/17/03 - Sep CMP meeting notes will be posted to the database


Project Meetings

September 17, 2003 CMP Meeting Minutes Linda Miles – Qwest advised that last month this CR moved to CLEC Test. The scenarios requested and comments received are included in the documentation. Covad agreed to close this CR.

August 20, 2003 CMP Meeting Minutes Crystal Soderlund-Qwest advised the scenarios are available as direct links in the document. This is more user friendly. Crystal advised she also added one additional scenario that wasn’t requested before. The document is available on the web. The CLECs agreed to move this CR to CLEC test.

July 16, 2003 CMP Meeting Minutes Crystal Soderlund – Qwest advised that Qwest has agreed to change the PCAT to include a direct link to the scenarios within the PCAT. Crystal thanked the CLECs for reviewing the scenarios and providing additional input. Two additional scenarios were received that are not in the matrix. These scenarios are in the LSOG. Crystal advised she will add the scenarios to the matrix and put the direct link into the PCAT. This should be available to review for comment by the end of July via the Notification process. This CR should move to CLEC Test next month.

June 18, 2003 CMP Meeting Minutes Crystal – Qwest advised we had a further clarification call scheduled with the CLECs last week and Qwest agreed to update the document as a direct hyperlink. John Berard-Covad agreed to go through each scenario and determine if any are missing. John will send to Cindy Macy any additional scenarios that he would like added to the document. Qwest requested the CLECs to have this review done by Wednesday June 25. Covad agreed that would be acceptable.

PC012703-2 Data Migrations

Ad Hoc CLEC Input Meeting June 12, 2003 10:00 – 11:00 a.m. 1-877-572-8687 3393947#

In Attendance: Chad Warner – MCI Jeremy Mead – Covad John Berard – Covad Kit Thomte – Qwest Stephanie Prull – McLeod Bonnie Johnson – Eschelon Donna Osborne Miller – ATT Susan Lorence – Qwest Sharon Van Meter – ATT Crystal Soderlund– Qwest Cindy Macy – Qwest Eric Yohe – Qwest Linda Miles – Qwest Dave Hahn – Qwest Russell Urevig – Qwest Monica Manning – Qwest Deb Smith – Qwest Hiedi Moreland – Qwest Mike Johnson – Qwest

Cindy Macy – Qwest opened the call and explained the purpose of this call was to review the updates that have been made to the Migration and Conversion PCAT as a result of PC012703-1. The team reviewed the updates to make sure we understood the logistics of accessing the updated scenarios and also be able to ask questions about the content of the scenarios.

Crystal Soderlund – Qwest advised the team how to access the Migration and Conversion PCAT via the Wholesale Web Site. The team reviewed the document and Crystal pointed out the blue link that would take you to the search engine where you could open the scenario document.

John Berard - Covad asked why does this link take us to another search engine where there are multiple documents to select from? There is a list of 340 documents or exhibits. John questioned why this document is not part of the PCAT and advised it looks like a testimony document as it says Declaration in the title. Covad explained they are not comfortable with the accuracy of the document if it is outside of the PCAT. Crystal advised this document was identified to her by another CLEC and it contains the information Qwest used to roll out the product. Covad requested the document to be included in the PCAT as part of the PCAT and not be viewed via a separate search engine. Crystal agreed she would make a direct link to this document within the PCAT.

Cindy Macy – Qwest asked the CLECs if the content of the PCAT was adequate? Does the PCAT contain all the scenarios and is there enough detail on each scenario? John Berard – Covad explained they have begun looking at the scenarios but have not gone through each one yet. Crystal explained within the PCAT there is a link to the LSOG. The LSOG gives you direction on how to fill out the LSR/forms for the product you are offering. Cindy Macy – Qwest asked if there were any exceptions to the rule for ordering these products in the LSOG? If so those exception may need to be put in the PCAT.

Crystal Soderlund – Qwest agreed to make direct links to the scenario document in the PCAT. John Berard – Covad agreed to review the scenarios and let us know at the June CMP meeting if there are any scenarios that he is missing. If any CLEC reviews the document and has identified missing scenarios please send them to cmacy@qwest.com.

May 21, 2003 - CMP Meeting Minutes Crystal Soderlund – Qwest advised she has responded to the comments that came in. Crystal clarified the procedures and added additional details based on the comments. The Migrations PCAT is a ‘general and procedural’ PCAT, opposed to a product specific PCAT. Within this PCAT Crystal has added links that will bring you to more detailed documents that provide many different product scenarios for Migrations. This approach was taken as it would be very cumbersome to include all of the scenarios in the Migrations PCAT. Links are commonly used through out the PCATs. This link is a little different than other links though. The link initially brought you to another list of documents that you then needed to access to view. Crystal has changed it so the links will take you to the actual document, instead of a list of documents.

Covad asked what these documents were and if they fall under the same rules as PCATs, or are they owned by a group outside of CMP/Wholesale? Cindy Macy – Qwest agreed she would check on this item.

Covad expressed their concern that the level of detail for Data Migrations is not the same as Voice Migrations. Crystal asked for Covad to review the scenarios provided and let us know what scenerio is missing and we will then document the missing scenerio. Crystal explained the scenerios identify the type of LSR to submit, and then you have to go to the LSOG to get information on how to submit the LSR.

Cindy Macy – Qwest agreed to schedule a meeting to review the Migrations PCAT: logistics on how to get to the document and the content of the document will be reviewed. The Service Manager should also be invited.

April 16, 2003 - CMP Meeting PC012703-2: Data Migration Process

Crystal Soderlund – Qwest advised this process will be available on April 17, 2003. Qwest has issued updates to theMigrations PCAT. A url for two separate job aides on the web is provided. We have implemented an internal process to tie the two orders together. Mike Zulevic asked if this process includes Line Sharing and Line Splitting. Crystal advised yes. Cindy Macy – Qwest asked Crystal if this was done using a Level 1 Notification. Crystal advised yes. Qwest confirmed with the CLECs that it was okay to issue this as a Level 1 so the process is available for use asap. Mike Zulevic advised Level 1 is okay. If he has any questions on the document he will be able to get those answered since the CR is still open.

March 19, 2003 - CMP Meeting Cindy Macy Qwest reported the team met again on March 18 to clarify the Loop Splitting impacts to the CR. The differences between Loop Splitting, Line Sharing and Line Splitting were discussed. Agreement was reached that this CR will address multiple order situations as that is what causes the line to be down, opposed to a lift and lay move. Qwest is working to develop the process to tie multiple orders together to limit the amount of down time. Qwest also agreed to review the Data Migrations process and make it more clear, using the Voice Migrations process as an example. Mike Zulevic requested Qwest provide clarity on the steps to perform the Data Migration.

February 19, 2003 - CMP Meeting

Mike Zulevic–Covad presented this CR and explained the process associated with moving data line customers is not documented and causes confusion. Covad explained when data lines are converted the lines go down and the customer looses data that is being transmitted. Covad would like this process documented on the web site. Brett Fesler–Qwest asked if Loop Splitting was included with this CR. Zulevic agreed to discuss this with John Berard and let us know. Qwest agreed to continue working on the CR without Loop Splitting. If Loop Splitting is added we will meet again to clarify.

Comment from Mike Zulevic: I did discuss excluding loop splitting from the migrations CR with John Berard. Although loop splitting is not as critical for Covad right now as line sharing and splitting, it could be in time. It will still need to be documented, in my opinion, as there could well be migrations between a loop splitting service and a line sharing or splitting service where the same cable pair will be reused and possibly the same common area plitter. If Qwest wishes to have a seperate CR opened just for loop splitting, I think we would agree to do so, if it would make things easier for you in moving forward more quickly with the other migrations scenarios. Let me now if this would help.

Clarification Meeting CR PC012703-2 Data Migrations February 5, 2003 1-877-572-8687 3393947#

Attendees Name/Company: John Berard – Covad Crystal Soderlund – Qwest Brett Fesler – Qwest Deb Smith – Qwest Eric Yohe – Qwest Hiedi Moreland – Qwest (covered via notes) Linda Sanchez-Steinke – Qwest Cindy Macy - Qwest

Meeting Agenda:

1.0 - Introduction of Attendees Attendance was noted

2.0 - Review Requested (Description of) Change The group reviewed the CR Description in detail. The group clarified the products/services impacted and discussed the scope of the CR. The group determined the differences between this CR (PC012703-2 Data Migrations) and CR PC012703-4 Coordinated Hot Cuts for Data Migration. The key difference is this CR PC012703-2 is requesting a Process improvement and CR PC012703-4 CHC for Data Migrations is requesting a Product offering.

Brett asked John to clarify what a Data Migration order/service includes? John advised it would apply to an existing Line Sharing Order on an end users line. If the end user wants to go to another 3rd party voice provider but keeps the data with Covad, this would be a change to the Line Splitting account.

Deb Smith clarified Line Splitting is for UNE P POTS and Line Sharing is for Retail POTS.

John said this CR is requesting to minimize the amount of time the line goes down when doing a conversion from one provider to another on the data line. Cindy asked John to clarify the amount of time the lines have been down and how often this is happening. John advised the volume of this product offering has potential for increasing. John didn’t have a specific expectation of an acceptable down time during a cut over. CR PC012703-4 is for a CHC that would designate a specific cut over time.

Brett asked if we were able to build the process so there was no down time would there not be a need for CR PC012703-4. John advised potentially that CR would not be necessary if there was not any down time for the customer who is migrating.

The group discussed how this process works today. Crystal advised when going from Line Sharing to Line Splitting today a LSR is submitted to migrate the Line Share to UNE-P. At the same time the Service is migrated the Line Share is removed. The 2nd order is placed to make UNE-P. The LSR is submitted by the CLEC asking for Line Split to be added to the account. Because 2 orders are created the data line portion can be down for a period of time.

This CR applies to when there are 2 orders. On UBL DLEC to DLEC conversions there is only one order so this CR would not apply to one order situations. DLEC to DLEC is a ‘lift and lay’ process.

Crystal clarified that CLEC to CLEC UBL Migrations are available today and there is a PCAT in place. Because this is already in place, the reference to ‘second line’ in this CR does not apply. The group verified Loop Splitting is a Facility Based Provider service (existing UBL adding a splitter to a new provider). This scenerio does not fit within this CR either. John advised it is okay to remove Loop Splitting. John advised he will confer with Mike Zulevic to make final determination.

3.0 - Confirm Areas & Products Impacted Line Splitting and Line Sharing

4.0 - Confirm Right Personnel Involved All agreed the correct personnel are involved

5.0 - Identify/Confirm CLEC’s Expectation John said this CR is requesting to minimize the amount of time the line goes down when doing a conversion from one provider to another on the data line.

6.0 - Identify any Dependent Systems Change Requests CR PC012703-4 Coordinated Hot Cut on Data Migrations

7.0 - Establish Action Plan (Resolution Time Frame) Covad will present this CR to the CLEC Community at the February CMP Meeting Qwest will work to determine our response to this CR and have an initial response due March 12.


CenturyLink Response

For Review by the CLEC Community and Discussion at the March 19, 2003 CMP Meeting

March 11, 2003

Covad Communications John Berard

SUBJECT: Qwest’s Change Request Response – CR #PC012703-2 Data Migrations

This letter is in response to Covad Communications Change Request (CR) PC012703-2. This CR requests that Qwest reduce the CLEC down time during a Data Migration Order, and to clarify external documentation.

Qwest accepts this CR and is currently investigating and reviewing: ? Ways to internally tie the orders together to decrease the down time of the data portion of the loop ? External documentation for potential updates (LSOG and PCAT)

In addition, Qwest will schedule a subsequent clarification call with Covad to discuss the Loop Splitting product and the impacts to this CR.

Qwest requests this CR be placed in Evaluation Status and will provide an update at the April CMP Meeting.

Sincerely,

Crystal Soderlund

cc: Linda Miles


Open Product/Process CR PC012703-3 Detail

 
Title: Collocation 'Partial' Decommissioning
CR Number Current Status
Date
Area Impacted Products Impacted

PC012703-3 Denied
1/27/2003
Billing, Provisioning Collocation, Physical and Virtual
Originator: Berard, John
Originator Company Name: Covad
Owner: Nelson, Steve
Director:
CR PM: White, Matt

Description Of Change

Covad requests that Qwest provide a partial decommissioning product similar to the current decommissioning product that will include all collocation componants to include but not be limited to space, termination, bays, and power.

Expected Deliverable: Provide as soon as possible. Amend existing product to include this request.


Status History

01/27/03 - CR Submitted by Covad

01/27/03 - CR acknowledged by P/P CMP Manager

01/30/03 - Clarification Meeting scheduled for 2/3/03

02/03/03 - Clarification Meeting conducted

02/19/03 - CR presented at the CMP Meeting

03/19/03 - Qwest Response presented at CMP Meeting

04/16/03 - Qwest Revised Response presented at CMP Meeting


Project Meetings

04-16-03 - CMP Meeting

Nelson-Qwest presented the Qwest response. Zulevic-Covad stated that he had no questions but that Covad and Qwest differed in opinion in this issue. He stated the CR should be closed as denied because Covad’s description of change inferred that they wanted pricing similarities. Zulevic-Covad stated that he disagreed with Qwest’s assessment that this was a service that should be performed for a charge. The CR was moved to denied. Subsequent to the CMP Meeting, Zulevic-Covad contacted Nelson-Qwest by phone. Zulevic-Covad has stated that Qwest could close the CR as partially accepted because Covad can partially decommission a site, but not at the terms Covad requested. Zulevic-Covad asked that Qwest capture in the minutes Covad’s disappointment that Qwest was unwilling to perform this work without charge.

===============================================

03-19-03 - CMP Meeting

Nelson-Qwest presented the Qwest response. Zulevic-Covad stated that the current Qwest process the Nelson described meets Covad’s needs, but that Covad is also seeking a reimbursement similar to total decommissioning when another CLEC picks up unused collocation elements. Nelson-Qwest stated that this facet was not included in the description of change or mentioned on the clarification call. He stated that he would analyze that request. Zulevic-Covad stated that he was not satisfied with the high costs Qwest was charging. Nelson-Qwest stated that Qwest’s charges were approved by a commission or negotiated in Covad’s interconnection agreement, and were not part of CMP. The CR was moved to evaluation.

=================================================

02-19-03 - CMP Meeting

Zulevic-Covad presented the CR. Nelson-Qwest asked if Covad expected the partial decommissioning service to be performed at no charge. Zulevic-Covad stated that he expected it to be a small charge, because, in many cases, Qwest would only be updating its records. White-Qwest stated that the CR would be moved to Presented status.

==================================================

Clarification Meeting 1:00 PM (Mountain Time) / Monday, February 3, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Steve Nelson – Qwest John Waltrip – Qwest Jeff Cook – Qwest Lillian Robertson – Qwest John Berard – Covad

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Berard-Covad reviewed the CR. Waltrip-Qwest asked if the request was to give up space, power, etc on a partial basis. Berard-Covad responded that it was. Nelson-Qwest asked if the request was to the bay level or to the shelf level. Berard-Covad stated that he was primarily concerned with individual bays or terminals. Waltrip-Qwest asked if Berard was familiar with the Inverse Augment Product. Berard-Covad stated that he was not intimately familiar with it but would ask Neesen-Covad if that product addressed this request.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Covad’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Covad to present the CR at the February Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

April 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the April 16, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Revised Change Request Response - CR #PC012703-3

This memo is in response to Covad CR PC012703-3. This CR requests “…that Qwest provide a partial decommissioning product similar to the current decommissioning product that will include all collocation components to include but not be limited to space, termination, bays, and power.”

Qwest Response: Accepted

The request is accepted for the following reason: Qwest currently allows CLECs to reduce portions of an existing collocation site. To request this service a CLEC must complete the collocation application form “New/Change/Augment Application”. On this form, the CLEC must specify the work to be performed. In response to this form Qwest will issue a quote per the ICA or established timelines in the SGAT, as appropriate. Commissions, through cost docket hearings, arbitration, or through negotiations, approve the rates associated with this service.

Qwest also has an existing product that allows CLECs to power down DC power at a lesser cost, when an amendment is signed between Qwest and the individual CLEC.

Key work steps associated with reducing terminations, bays, or space is as follows: Receive application, validate, schedule, and distribute. (CPMC) Conduct 48 hour call where requested or needed. (Team of Network SMEs) Open a planning document and procure funding to process the job. Space planning and power engineering review to determine potential impacts. Determine feasibility. Begin IOF engineering job. Route to OSP if anything involving entrance facilities removal. Assign floor space changes, terminations, power changes. Monitor payment for timely acceptance. Request field visit to validate existing and changes (reductions or removals) Develop quote input. Enter job into COE-FM or OSP-FM. Schedule installation forces. Monitor payment and timely acceptance. Procure material as required. Track job progress and project manage all work steps, timelines, and resolve gaps or jeopardies. Complete field work and complete an Installation Completion Notification. Update applicable data bases such as TIRKs and SWITCH. Issue a revised APOT(s).

Qwest has a legitimate business reason to be compensated for these work functions and has no plans to reduce pricing which is based on cost models filed with the commissions or negotiated rates through Interconnect Agreements. This portion of the request (partial decommissions at no cost like full decommissions) which was identified during the clarification call on Feb. 3, 2003 is outside the CMP process since pricing is subject to commission ordered rate elements and or negotiations.

In the March 19, 2003 CMP Meeting, Covad asked whether any partial decommissioned infrastructure could be reused and, thus, be reimbursable. This request significantly changes the scope of this CR. By definition, Qwest’s decommission product and available inventory product descriptions require fully decommissioned sites for posting and reimbursement, if a subsequent CLEC requests the site. In situations where a CLEC occupies a cage, Qwest only posts vacated collocation space to the Web site if the CLEC completely vacates the space and the CLEC termination cable remaining in the cage meets applicable engineering standards. When a CLEC still occupies a portion of their cage space, any “partially decommissioned” site termination cable would be useless to other CLECs because the original CLEC is still occupying the site where the cable terminates. Qwest occasionally mines out partially decommissioned cable, but only in situations where it is necessary to relieve cable rack congestion. In a situation where a CLEC occupies cageless space, Qwest brings power and terminations to a cageless bay lineup and installs them to the equipment bay. This installation requires H-taps for power to be placed on each bay, and the cable and ground cable to be cut to length. Power cable running to a CLEC site is not CLEC cable nor is it reimbursable today under available inventory. Partially decommissioned power can not be reimbursed. Cageless bays are removed by the CLEC in most cases.

In summary, Qwest currently allows CLECs to reduce portions of an existing collocation site but has no plans to reimburse CLECs for a partial decommission.

Sincerely, Steve Nelson Qwest Product Manager

==============================================================

March 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the March 19, 2003, CMP Product/Process Meeting

Mike Zulevic Director - GEA Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC012703-3

This memo is in response to Covad CR PC012703-3. This CR requests “…that Qwest provide a partial decommissioning product similar to the current decommissioning product that will include all collocation components to include but not be limited to space, termination, bays, and power.”

Qwest Response: Accepted

The request is accepted for the following reason: Qwest currently allows CLECs to reduce portions of an existing collocation site. To request this service a CLEC must complete the collocation application form “New/Change/Augment Application”. On this form, the CLEC must specify the work to be performed. In response to this form Qwest will issue a quote per the ICA or established timelines in the SGAT, as appropriate. Commissions, through cost docket hearings, arbitration, or through negotiations, approve the rates associated with this service.

Qwest also has an existing product that allows CLECs to power down DC power at a lesser cost, when an amendment is signed between Qwest and the individual CLEC.

Key work steps associated with reducing terminations, bays, or space is as follows: Receive application, validate, schedule, and distribute. (CPMC) Conduct 48 hour call where requested or needed. (Team of Network SMEs) Open a planning document and procure funding to process the job. Space planning and power engineering review to determine potential impacts. Determine feasibility. Begin IOF engineering job. Route to OSP if anything involving entrance facilities removal. Assign floor space changes, terminations, power changes. Monitor payment for timely acceptance. Request field visit to validate existing and changes (reductions or removals) Develop quote input. Enter job into COE-FM or OSP-FM. Schedule installation forces. Monitor payment and timely acceptance. Procure material as required. Track job progress and project manage all work steps, timelines, and resolve gaps or jeopardies. Complete field work and complete an Installation Completion Notification. Update applicable data bases such as TIRKs and SWITCH. Issue a revised APOT(s).

Qwest has a legitimate business reason to be compensated for these work functions and has no plans to reduce pricing which is based on cost models filed with the commissions or negotiated rates through Interconnect Agreements. This portion of the request (partial decommissions at no cost like full decommissions) which was identified during the clarification call on Feb. 3, 2003 is outside the CMP process since pricing is subject to commission ordered rate elements and or negotiations.

Sincerely, Steve Nelson Qwest Product Manager


Open Product/Process CR PC012703-4 Detail

 
Title: Coordinated Hot Cuts for Data Migrations
CR Number Current Status
Date
Area Impacted Products Impacted

PC012703-4 Denied
3/19/2003
Provisioning UNE - Loop, Line Share and XDSL
Originator: Berard, John
Originator Company Name: Covad
Owner: Fesler, Bret
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Covad is requesting that Qwest develop a process similar to the UNE-P Hot Cut process that can be applied to DATA Migrations.

Expected Deliverable: As soon as possible.


Status History

01/27/03 - CR Submitted by Covad

01/27/03 - CR acknowledged by P/P CMP Manager

01/30/03 - Scheduled Clarification Meeting 2/3/03

02/03/03 - Held Clarification Meeting

02/19/03 - February CMP Meeting - Covad presented this CR. Meeting minutes will be posted to this CR's Project Meetings section.

03/12/03 - Issued Qwest draft response to John Berard at Covad

03/19/03 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

03/19/03 March CMP Meeting Brett Fesler with Qwest presented the Qwest draft response and explained that this CR would require a change that would take all non-design orders and put them into the design flow. Deb Smith said there is a coordinated option for unbundled loops that is available with designated cut time. In the PCAT for Unbundled Loops, new and existing are available with cooperative testing at a designated appointment time. Mike Zulevic said he would take this back to Covad and determine if they will escalate. The CR status was changed to Denied.

02/19/03 February CMP Meeting Mike Zulevic with Covad presented this CR. Mike said that Covad is looking for a specific time to cut service for data migration and provide the customer with very little interruption in service. Mike said that Line Sharing, Line Splitting, Loop Splitting are the products Covad would like to be able to specify cut time. Brett Fesler with Qwest asked if the end user would have the same data provider. Mike said the end user may want to change data providers; an example would be that a Qwest end user may want to go to a different voice provider and have Covad as their data provider. The CR status was changed to Presented.

CLEC Change Request Clarification Meeting

2:00 p.m. (MT) / February 3, 2003

1-877-572-8687 PIN 3393947 # PC012703-4 Coordinated Hot Cuts for DATA Migrations

Name/Company: John Berard, Covad Director Operations Support Crystal Soderlund, Qwest Sr. Process Analyst Heidi Moreland, Qwest Network Technical / Regulatory Neil Houston, Qwest Network Technical / Regulatory Laurel Neher, Qwest Network Technical / Regulatory Russ Urevig, Qwest Sr. Process Analyst Brett Fesler, Qwest Product Management Rosemarie Ferris, Qwest Lead Process Analyst Linda Sanchez-Steinke, Qwest Change Request Project Manager

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The change request asks that Qwest develop a process similar to the UNE-P Hot Cut process that can be applied to DATA Migrations. Laurel Neher said that Qwest has a Hot Cut Process for Unbundled Loop and does not have a Hot Cut Process for UNE-P. John Berard said that Covad is asking for a coordinated cut in the center that will minimize downtime for the customer. Neil Houston stated that the Unbundled Loop hot cut process takes a matter of minutes. Laurel asked what product Covad would be ordering. John responded that it would be a Line Shared Loop, a Qwest Voice Grade that has linesharing and Covad is migrating to another carrier. Crystal Soderlund asked what the difference was between change request PC012703-2, DATA Migration Process and this change request, PC012703-4 Coordinated Hot Cuts for DATA Migration. John explained that the difference is that PC012703-2 is asking for a process and PC012703-4 is asking for a Coordinated Hot Cut process. Rosemarie Ferris asked if we have a Qwest voice grade linesharing with Covad, the linesharing is going to another carrier, or another carrier is loosing it, or it is moving over to a line shared loop.

Crystal Soderlund asked if the request is for DLEC to DLEC changes, then it appears the two change requests are asking for the same thing, when changing from DLEC to DLEC data portion doesn’t go down. John said Covad would like a coordinated process for moving from one DLEC to another DLEC, with the new connect and disconnect happening at the same time, someone assigned to take responsibility for both orders and a minimal period of down time. Crystal said that with Line sharing to Line splitting the end user doesn’t experience data going down and there is a coordinated installation option. Crystal said that Linesharing has only a basic option and wanted to clarify which products are involved: Linesharing, UNE-P Linesplitting, Loop splitting. All of them per John. Crystal asked if this would be on line share to loop split orders and Johns replied yes. Laurel asked if when changing voice provider, but data provider is the same, there is a period where that is open. When changing DLECs Line Sharing to splitting voice provider changing and keeping the DLEC or changing the DLEC. Per John that is accurate. John said that this CR is for a coordinated hot cut process as a premium service which will ensure that it makes it through the process without downtime. Heidi asked if this is just a basic offering or if there would be a selected time. Crystal said yes coordinating of orders when changing DLEC or changing sharing to splitting. Would be ok if systems would be coordinated and orders worked at the same time. John will go back to Covad folks and determine if it is enough to offer with minimum down time to make sure the data portion stayed up or if the CR should be asking for a specific point in time for a coordinated cut. John will e-mail to Linda Sanchez-Steinke.

During the Clarification Meeting for PC012703-2, John said the difference between CR’s is that PC012703-4 is asking for a Hot Cut process with a specific time for the Hot Cut to take place.

Confirm Areas & Products Impacted Products impacted are Linesharing, UNE-P Linesplitting, Loop splitting, when changing DLECS line sharing to splitting voice provider changing and keeping DLEC or changing DLEC.

Confirm Right Personnel Involved Qwest confirmed that Heidi Moreland, Crystal Soderlund, are the correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation Covad is requesting that Qwest develop a coordinated Hot Cut process for DATA Migrations

Identify any Dependent Systems Change Requests No dependent change requests were identified. Change Request PC012703-2 is similar and Covad will confirm that PC012703-4 is not the same request.

Establish Action Plan (Resolution Time Frame) John Berard will present this CR at the February CMP Meeting.


CenturyLink Response

March 5, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the March CMP Meeting

John Berard Director Operations Support Covad Communications

SUBJECT: Qwest’s Change Request Response - CR #PC012703-4 This letter is in response to CLEC Change Request PC012703-4. This CR is a request by Covad to do Coordinated Hot Cuts on Data Migrations for Line Sharing, Line Splitting, and Loop Splitting.

Qwest has investigated the creation of a new installation option that would allow coordinated hot cuts to take place at a particular time to be specified by the CLEC.

This request would require an additional installation option that would take all Line Sharing and Line Splitting products out of their non-design flow. As a result of the change in flow, Qwest internal system changes would be required to allow orders to go to the designed services flow. Additionally, order intervention would be required, with significant resources in the QCCC to handle the increased volume.

As a result of this investigation, Qwest respectfully denies this change request due to it being economically not feasible because the economic magnitude of adding additional resources is too large for the number of orders.

Sincerely,

Brett Fesler Associate Product Manager


Open Product/Process CR PC050905-1 Detail

 
Title: Reduce Intervals
CR Number Current Status
Date
Area Impacted Products Impacted

PC050905-1 Completed
4/7/2006
Provisioning UBL 2/4 Wire Non Loaded, LineSplit/Shared
Originator: Balvin, Liz
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Revision Received 05/24/2005 (revised description and products:

Covad seeks reduction of the following intervals applied by Qwest:

1) DSL line shared/split disconnect orders reduced to 24 hours.

2) CFA only supplemental orders (post FOC, pre completion) reduced to 24 hour interval for line shared/split and 2/4 wire non-loaded loops

Expected Deliverable:

1) That Qwest will perform DSL line shared/split disconnect orders within 24 hours (current interval 3 days).

2) That Qwest will process CFA only supplemental orders within 24 hour interval (currently 72 hours) for line shared/split and 2/4 wire non-loaded loops. For example, if the CFA change request is made before the due date has passed than the due date remains the same or if the CFA change request is made on the due date or after the due date has passed, Covad requests the 24 hour interval instead of the current 3 day interval.

------------------------------------------------------------------------------------------------------

Original Description:

Covad seeks reduction of the following intervals applied by Qwest:

1 Stand alone DSL line shared/split disconnect orders reduced to 1 day.

2) CFA only supplemental orders (post FOC, pre completion) reduced to 24 hour interval for line shared/split and xDSL qualified loops.

Expected Deliverable:

That Qwest will perform stand alone DSL line shared/split disconnect orders within 24 hours (current interval 3 days). In addition, that Qwest will process CFA only supplemental orders within 24 hour interval (currently 72 hours) line shared/split and xDSL qualified loops.

Orig Products: UBL xDSL, Line Split/Shared


Status History

05/09/2005 - CR Submitted

05/10/2005 - CR Acknowledged

05/18/2005 - Discussed in the Monthly Product Process CMP Meeting

05/18/2005 - Clarification Meeting Held

05/24/2005 - Revised CR Received from Covad

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

07/20/2005 - Discussed in the Monthly Product Process CMP Meeting

08/17/2005 - Discussed in the Monthly Product Process CMP Meeting

09/21/2005 - Discussed in the Monthly Product Process CMP Meeting

10/19/2005 - Discussed in the Monthly Product Process CMP Meeting

11/16/2005 - Discussed in the Monthly Product Process CMP Meeting

12/14/2005 - Discussed in the Monthly Product Process CMP Meeting

01/09/2006 - PROS.01.09.06.F.03573.Interconnect_SIG_V59 (level 2)

01/18/2006 - Discussed in the Monthly Product Process CMP Meeting

01/30/2006 - Status Changed to CLEC Test Due to January 30, 2006 Implementation

02/15/2006 - Discussed in the Monthly Product Process CMP Meeting

03/15/2006 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

April 7, 2006 Email Received From Covad: Peggy, The testing has been confirmed. This CR can be closed. Thank you, Lynn Hankins

-- April 7, 2006 Email Received From Covad: Peggy, I haven’t heard back yet. It’s on my list and I will let you know as soon as I hear back from our Ops. Thanks, Lynn

- April 7, 2006 Email Sent to Covad: Good Morning Lynn - This email is a follow-up to the emails below. Is Covad ready for closure of the Reduce Intervals CR? Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

March 31, 2006 Email Received From Covad: Hi Peggy, I have requested information from our Ops department on this CR - I will inquire again on Monday to see if there are any issues that would prevent closure, based on the testing. Thanks, and have a nice weekend. Lynn

- March 31, 2006 Email Sent to Covad: Hello Lynn, This email is just a follow-up to see if you have had the opportunity to validate the changes made as a result of Covad's Product Process CMP CR PC050905-1 Reduce Intervals. The effort was implemented on January 30th. Please let me know if you are ready to close the CR or if you did find an issue with the implementation, please let me know what the issue is and I can assist in getting the issue resolved. Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

March 15, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this effort deployed on January 30th and asked if the CR was ready to be closed. Lynn Hankins-Covad asked that the CR remain open another month, as she has not been able to check. Jill Martain-Qwest advised Covad that if they determine that the CR could be closed before the next CMP meeting that they could send an email to close during the month. Lynn Hankins-Covad advised she would check, and if possible, she will let Qwest know off-line. This CR remains in CLEC Test.

-- February 15, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this CR deployed on January 30th and asked for closure. Lynn Hankins-Covad asked that the CR remain open another month. This CR remains in CLEC Test.

January 18, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that the Level 2 Notice was sent on January 19th with a targeted implementation date of January 30th. Jill stated that this CR would move to CLEC Test on January 30, 2006.

- December 14, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this is still on target for a January 28, 2005 deployment. This CR remains in Development status.

-- November 16, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this effort was targeted for January 28, 2006 and noted that the notice would be sent in early December. This CR remains in Development status.

-- October 19, 2005 Monthly Product Process CMP Meeting Discussion: Anthony Washington/Qwest stated that Qwest is accepting the remaining portion of this request and is tentatively looking at implementation in February, due to changes needed in back-end systems. Jill Martain/Qwest stated that the implementation date is not yet finalized and that the February date is very tentative. Jill stated that this CR moves to Development Status. Jill noted that the CFA portion was already solved. Liz Balvin/Covad agreed.

-- September 21, 2005 Monthly Product Process CMP Meeting Discussion: Peggy Esquibel-Reed/Qwest stated that Qwest is continuing to work internally on this request and is currently looking at the costs for changes to back-end system changes that may be able to meet this need. Peggy stated that Qwest would like to leave this CR in Evaluation status and that a status would be provided in the October CMP Meeting.

August 17, 2005 Monthly Product Process CMP Meeting discussion: Peggy Esquibel Reed-Qwest stated that Qwest is still evaluating this request and noted that Qwest has met internally at least once per week in order to discuss this CR. Peggy stated that this CR remains in Evaluation and that a status would be provided in September. [Comment received from Eschelon: Liz Balvin-Covad asked Qwest if we need an ad-hoc meeting. Liz said she does not want the CR to be denied. Liz said Qwest was looking at systems solutions and asked if that was still Qwest’s path. Qwest said they will keep an ad-hoc meeting in mind.]

- July 20, 2005 Monthly Product Process CMP Meeting discussion: Anthony Washington-Qwest said that this CR is for Line Sharing and Line Splitting. He said that the Line Sharing portion of this CR is still in evaluation. Anthony said that we have to figure out how we can determine the 1 day’s intervals versus a standard interval and then be able to prioritize the orders. Liz Balvin-Covad clarified that the disconnect interval reduction from 3 to 1 days, and the CFA change on Due Date for Line Sharing and Line Splitting is in Evaluation. Anthony Washington-Qwest advised yes. Deb Smith-Qwest added that UBL 2/4 wire non loaded was addressed post FOC and pre completion via CR5548229 (the verbal sup process). Liz Balvin-Covad said that she thought they could not do the CFA change. Liz said that the documentation was not very clear and that she will check on this. Liz advised that they still want the Line Splitting/Line Sharing. Jill Martain-Qwest stated that this CR will remain in Evaluation Status.

June 15, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that Qwest is internally evaluating this request and that a status would be provided at the July CMP Meeting. This CR is in Evaluation status.

- May 18, 2005 Clarification Meeting Attendees: Liz Balvin-Covad, Nicole-Covad, Kim Isaacs-Eschelon, Bonnie Johnson-Eschelon, Peggy Esquibel Reed-Qwest, Heidi Moreland-Qwest, Crystal Soderlund-Qwest, Jo Wees--Qwest, Deb Smith-Qwest, Shirley Tallman-Qwest, Anne Robberson-Qwest, Paul Schlacter-Qwest, Anthony Washington-Qwest

Review Requested (Description of) Change: Peggy Esquibel Reed-Qwest reviewed the CR Title and Description and stated that the products indicated on the CR are UBL, DSL, Line Splitting, and Line Sharing. Peggy also noted that this CR is requesting a process change for Provisioning. Peggy then asked Covad if they had additional information to provide to Qwest. Nicole-Covad stated that currently for line shared and line split and when the voice is disconnected, the DSL is automatically disconnected within 24-hours. Nicole stated that the first item in the CR is requesting that stand alone DSL be in synch. Nicole stated that the second item in the CR is if it is identified that the CFA needed to be changed that they get a 3-day interval. Crystal Soderlund-Qwest asked Covad to further explain what Covad means by stand alone DSL. Liz Balvin-Covad stated that when they have a shared service, they are requesting a disconnect of the DSL only. Crystal Soderlund-Qwest asked if when requesting a disconnect of a line split or a shared line. Nicole-Covad stated is for the DSL portion of shared service. Crystal Soderlund-Qwest asked if this was for the data portion. Liz Balvin-Covad stated that the line in question is already split, voice and data, and if the provider disconnects the voice, the data portion is also to be automatically disconnected. Liz stated that if they disconnect the DSL only, it is a 3-day interval. Crystal Soderlund-Qwest stated that line sharing and Qwest DSL are 2 different products. Liz Balvin-Covad stated yes and that the DSL would be Covad provided DSL. Deb Smith-Qwest asked if this was just for shared services or if there is an impact to unbundled loops. Crystal Soderlund-Qwest asked if xDSL was qualified loops. Liz Balvin-Covad stated that it would be a stand alone DSL and noted that this CR has 2 different scenarios. Nicole-Covad stated that the first scenario applies to shared lines with the disconnect interval reduced to 1-day. The second scenario is when there is a CFA change, the interval is reduced to for stand alone DSL, the UNE line/UBL) and for line share. Anthony Washington-Qwest asked if this was for loop splitting. Nicole-Covad stated that this CR has 2 requests. UBL and shared loop. Nicole stated that if a CFA change is needed, they want a 24-hour interval instead of 3 days for shared lines and 5 days for UBL. Liz Balvin-Covad stated that the DSL product is a 2/4 wire non-loaded loop. Crystal Soderlund-Qwest asked if these were T1’s. Liz Balvin-Covad stated is 2/4 wire non-loaded loops, sDSR, not T1 or higher. Liz stated this would be for a DS0. Liz then noted that Covad does not purchase Qwest ADSL qualified loops. Crystal Soderlund-Qwest asked to confirm that item 1 in the CR should state that line sharing and line splitting need to be reduced to a 1-day interval and item 2 should state CFA changes for line shared/line splitting and 2 & 4 wire non splitting loaded loops. Liz Balvin-Covad said yes and stated that she would send in a revised CR. Crystal Soderlund-Qwest asked for example, a line shared request for slot 26 to be used; Qwest sends an FOC but is prior to completion. The request comes in today, May 18th, so May 23rd would be the due date on a 3-day interval. On May 19th, is post completion and Covad then wants a splitter change to slot 40. Crystal asked if Covad then wanted a May 20th due date. Nicole-Covad stated that normally, the only CFA change is when Qwest notifies them of a synchronization problem. Nicole stated that id Covad confirms that there is a problem with the CFA, they resubmit with a new assignment. Nicole stated that this is when they want a 1-day interval from when they submit the order. Nicole stated that if they receive a jeopardy on the CFA and Covad confirms the problem, they would resubmit on May 19th and would want the CFA completed on May 20th, not May 23rd. Kim Isaacs-Eschelon asked if there was a repair process for a CFA change. Nicole-Covad stated that this is for when the order is not yet completed, so they cannot go through repair. Kim Isaacs-Eschelon asked if this was for when the CFA was busy. Nicole-Covad said yes. Crystal Soderlund-Qwest asked that if the order is jeop’d on day 1, and there is a request to change the CFA, Covad wants a 1-day interval. Nicole-Covad said yes, with the impression that all the other work has been done, such as cross connects. Nicole stated that Covad does not want to affect the customer’s voice. This is for when no additional work is needed; they just need to switch to another card; and for UBL, if the pair is bad and the fieldwork has already been done. This would just be a pair change in the C.O. Deb Smith-Qwest asked to confirm that this would already be down to the due date since all the work has been done. Nicole-Covad said yes and noted that it could be on the FOC date or on the day before. Deb Smith-Qwest stated that on UBL 2/4 wire non-loaded loop; they should get the FOC long before the due date and is a 5-day interval. Deb stated that fieldwork may be done on the PTD but is close to the due date. Nicole-Covad stated that the C.O. work would be done and is done on the FOC date. Nicole stated that the fieldwork is done and the line is complete and Qwest tests or does co-operative testing. Then there could be a problem with the CFA assignment. If Covad reassigns the CFA, they currently wait 5-days, when the work is already done. Nicole stated that Covad does not know that there is a problem until the FOC date. Nicole stated this is where they want the 1-day interval. Crystal Soderlund-Qwest asked to confirm that a 1-day interval is requested if is on or after the original due date, or anytime during the process. Nicole-Covad stated anytime during the process. Crystal Soderlund-Qwest asked to confirm that if there is a CFA issue for a slot or splitter, the order is due today and there is a bad pair or splitter, Covad is asking for a 1-day interval. Crystal stated this would be a total 4 to 6-day interval. Kim Isaacs-Eschelon stated that this request sounds familiar and stated that there is a CR regarding a same day pair change the day of the cut, submitted by Allegiance. Kim stated that the CR number is 5548229 and noted that it was completed. Peggy Esquibel Reed-Qwest stated that Qwest would look at that CR. Liz Balvin-Covad asked what the escalation process was. Nicole-Covad stated that when the order is jeop’d for failure of a synch test, Covad disputes. If agreement is reached and a new CFA is sent, they want a sooner due date. Liz Balvin-Covad stated that of the Allegiance CR was completed; there should be a process in place. Peggy Esquibel Reed-Qwest stated that Qwest would look into the Allegiance CR. Liz Balvin-Covad stated that the Allegiance CR was for a post completion maintenance problem. Kim Isaacs-Eschelon stated that Allegiance asked for on the due date. Liz Balvin-Covad asked if Qwest understood what Covad was requesting. Deb Smith-Qwest stated that Covad is requesting a reduction to 1-day if it comes in today and that the 1-day would be at the end of business tomorrow. Liz Balvin-Covad said yes. Deb Smith-Qwest asked what if the due date was today and the CFA change was tomorrow. Nicole-Covad stated that if the due date were today and they were told today that there was a CFA problem, they are asking for a new due date of tomorrow. Deb Smith-Qwest asked if Covad only wants the 1-day interval for CFA’s on the due date and for the day before the original due date, the interval is not to be reduced. Nicole-Covad stated that if is jeop’d the day before or 2-days before the due date. Nicole stated that the expectation is to avoid pushing out the due date. Nicole stated that if the due date has passed, they want the interval to be 1-day. Crystal Soderlund-Qwest asked if that could also be clarified on the revision to the CR. Deb Smith-Qwest asked to confirm that the requested outcome is to not push out the due date when the CFA issue is identified prior to the due date. Nicole-Covad said yes and will clarify that on the revision being sent. Crystal Soderlund-Qwest stated that a 24-hour interval could be different than a 1-day interval, depending on the time that the request comes into Qwest. Liz Balvin-Covad said yes and would also clarify that on the CR revision. Peggy Esquibel Reed-Qwest asked if there were any additional questions or comments. There were none brought forward. Peggy then stated that this CR is scheduled for presentation at the June CMP Meeting and that Qwest would internally review the request.

-- May 18, 2005 Monthly Product Process CMP Meeting discussion: Liz Balvin-Covad stated that this CR had 2 pieces and stated that the first piece is that Covad would like a reduction that when Covad processes a line split, they would like the interval reduced to 1-day. Liz stated if it is a DSL disconnect, it is a 3-day interval. [Comment from Covad: Liz Balvin-Covad stated that this CR had 2 part 1) that the a DSL only disconnect be processed within 1 day Liz stated that currently if the voice is disconnected, the DSL automatically is brought down and done so within a day but if the DSL requires disconnection, Qwest imposes a 3-day interval.] Liz then stated that the second piece is for the ability to change the CFA on a supplemental order, post FOC and pre completion. Liz stated that the clock starts again if they need to change the CFA. Liz noted that the Clarification Call is scheduled for this afternoon. This CR moved to Presented status.

May 16, 2005 Email Received from Covad: Peggy, My internal contact was out of the office last week. I have a note out and should have back to by COB today with clarification call options. Thanks, Liz Balvin Covad Communications

-- May 16, 2005 Email Sent to Covad: Hi Liz, This email is just to follow-up on the item below. Will you send me several dates & times for the call? I will then get it scheduled and send you the call-in information. Thanks much, Peggy Esquibel-Reed Qwest Wholesale CMP

May 10, 2005 Email Sent to Covad: Hello Liz, Will you please advise me of your availability for the Clarification Call to discuss your request to Reduce Intervals? Several options would be greatly appreciated. Thanks much, Peggy Esquibel-Reed Qwest CMP


CenturyLink Response

October 14, 2005

Revised Response for Review by the CLEC Community and Discussion at the October 19, 2005 Product Process CMP Meeting

TO: Liz Balvin, Covad

SUBJECT: Qwest’s Revised Response for PC050905-1 Reduce Intervals

Description of Change: Covad seeks reduction of the following intervals applied by Qwest: - DSL line shared/split disconnect orders reduced to 24 hours. - CFA only supplemental orders (post FOC, pre completion) reduced to 24 hour interval for line shared/split and 2/4 wire non-loaded loops

This Covad Change Request, PC050905-1, is asking Qwest to perform DSL line shared/split disconnect orders within 24 hours (current interval 3 days) and that Qwest will process CFA only supplemental orders within 24 hour interval (currently 72 hours) for line shared/split and 2/4 wire non-loaded loops. For example, if the CFA change request is made before the due date has passed than the due date remains the same or if the CFA change request is made on the due date or after the due date has passed, Covad requests the 24 hour interval instead of the current 3 day interval.

Revised Qwest Response: Qwest provided a response for the CFA portion of the request which stated that with the CFA verbal supplement process that is currently in place; Qwest believes that the CFA issue has been resolved for Unbundled Loops. Please see the July 12, 2005 Qwest Response for details.

Qwest is accepting the remaining portion of this request, which is the DSL line shared/split disconnect orders reduction to 24 hours. Implementing this change will involve changes to back-end systems and Qwest is currently assessing when those changes can be implemented. When the implementation date is determined, Qwest will follow the appropriate notification timelines and will communicate the implementation date at a monthly CMP Meeting. Qwest would like to move this Change Request to Development Status.

Sincerely, Qwest

-- July 12, 2005

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the July 20, 2005 CMP Meeting

TO: Liz Balvin, Covad

SUBJECT: Qwest’s Change Request Response - PC050905-1 Reduce Intervals

Description of Change: Covad seeks reduction of the following intervals applied by Qwest: - DSL line shared/split disconnect orders reduced to 24 hours. - CFA only supplemental orders (post FOC, pre completion) reduced to 24 hour interval for line shared/split and 2/4 wire non-loaded loops

Qwest Response: This Covad Change Request, PC050905-1, is asking Qwest to perform DSL line shared/split disconnect orders within 24 hours (current interval 3 days) and that Qwest will process CFA only supplemental orders within 24 hour interval (currently 72 hours) for line shared/split and 2/4 wire non-loaded loops. For example, if the CFA change request is made before the due date has passed than the due date remains the same or if the CFA change request is made on the due date or after the due date has passed, Covad requests the 24 hour interval instead of the current 3 day interval.

As it relates to the Shared Service products Qwest is evaluating what all of the changes and resources that are needed would entail for this effort. We are determining how we can identify a 1 day interval vs. a standard interval and once identified, if we can ensure that we can comply with completing a 1 day interval, or a CFA post FOC, pre-completion by the requested time frame. Qwest would like to leave this portion of PC050905-1 in Evaluation status.

In regard to the 2/4 wire Non Loaded Unbundled Loop, as a result of an Allegiance Change Request (5548229 Same Day Pair Change During Test and Turn-up (day of cut)) completed 8/21/2002), Qwest implemented a process to allow CLECs to have a CFA change before or on the due date for Unbundled Loop services, including the 2/4 wire Non Loaded. These processes allow this activity to happen via Verbal Supplements.

Information is located in the Ordering Overview Business Procedure at http://www.qwest.com/wholesale/clecs/ordering.html section Verbal Supplements on LSRs: "Changes to an existing service request must be made via a supplement as described above. Qwest will only accept a verbal supplement change request for one of the following reasons: - CFA or slot change on the due date - etc.

Note: For Unbundled Loop, verbal CFA or slot changes may be made up to three days prior to the due date".

Therefore, if the CLEC determines that their CFA is defective after FOC, but pre completion, the CLEC will contact the QCCC with the new CFA and provide their representative’s name and phone number. The QCCC will initiate the work activities within Qwest to perform the CFA change. A new FOC will be sent to the CLEC following the standard FOC guidelines. It is not necessary for the CLEC to issue a supplement to their LSR for these types of CFA changes.

With the CFA verbal supplement process that is in place, Qwest believes the CFA issue has been resolved for Unbundled Loops.

Sincerely, Qwest


Open Product/Process CR PC060105-1 Detail

 
Title: Update Lines in Service Report
CR Number Current Status
Date
Area Impacted Products Impacted

PC060105-1 Denied
8/17/2005
Lines in Service Reporting
Originator: Balvin, Liz
Originator Company Name: Covad
Owner: McGhghy, Laura
Director:
CR PM: Stecklein, Lynn

Description Of Change

Add special billing number and address information

Expected Deliverable:

That Qwest will add to the special billing number and address information to the lines in service reports currently generated on a monthly basis.


Status History

6/1/05 - CR submitted

6/2/05 - CR acknowledged

6/3/05 - Clarification Meeting Scheduled

6/8/05 - Clarification Meeting Held

6/15/05 - Status changed to Presented

6/15/05 - Discussed in the June CMP Product/Process Meeting

7/20/05 - Status changed to Evaluation

7/20/05 - 6/15/05 - Discussed in the July CMP Product/Process Meeting

8/9/05 - Response sent to Covad

8/17/05 - Discussed in the August CMP Product/Process Meeting


Project Meetings

11/2/05 E-mail from Covad

Thanks Lynn. Please note in the CR the following on behalf of Covad:

Qwest’s response does not provide sufficient information to question the dollars assessed that resulted in the denial of this CR. Qwest houses the information requested and it is not required to access the Inventory Systems to extract and send to the billing systems which contains this information.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Wednesday, October 26, 2005 9:55 AM To: Balvin, Elizabeth Cc: Hankins, Lynn Subject: RE: PC060105-01 Update Lines in Service Report

Liz,

I have attached a revision of the denial on PC060105-01 Update Lines in Service Report that includes a breakdown of the estimated costs. Let me know if you have further questions.

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

--Original Message-- From: Balvin, Elizabeth [mailto:ebalvin@covad.com] Sent: Monday, October 17, 2005 1:31 PM To: Stecklein, Lynn Subject: RE: PC060105-01 Update Lines in Service Report

Lynn,

Covad requests a breakdown of the estimated costs = $726, 730.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Monday, October 17, 2005 10:31 AM To: Balvin, Elizabeth Subject: RE: PC060105-01 Update Lines in Service Report

Hi Liz,

This is in response to your e-mail below regarding PC060105-1 Update Lines in Service Report. We did research your request asking Qwest to merge the data from two systems – 1 Billing and 1 Lines in Service. The second denial that was sent to you (attached) covers the cost for doing that merge. In order to do the merging correctly, Qwest would have to invest in hardware and development time to create the rules associated with the merge and which data is used, etc. As stated in the denial – ‘It is possible for Qwest to combine the two systems so that the billing information requested is included in the Lines In Service Report, however the cost to complete the systems work to do this merge and implement business rules for the merging process would be $726, 730. Therefore, Qwest denies this CR as being economically infeasible’

Let me know if you have additional questions or concerns.

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770 --Original Message-- From: Balvin, Elizabeth [mailto:ebalvin@covad.com] Sent: Friday, October 07, 2005 4:22 PM To: Stecklein, Lynn Subject: RE: PC060105-01 Update Lines in Service Report Lynn,

I believe Qwest mis-understood my “clarifying” request…as identified in the updated response:

Qwest’s Lines in Service report was built as a response to a CMP request and currently is created from data contained in Qwest’s Network back-end systems, which inventory the circuits and lines by the circuit ID/working telephone number. These systems are not used for billing or account maintenance; rather, they are used for inventory and trouble reporting only. For this reason, the source system does not contain the SBN or billing address, nor are the fields available to contain this information. The billing systems, which contain this information, don’t communicate with the inventory and trouble reporting systems.

I understood that the back-end systems used to generate the “lines in service” report did not house the SBN or billing address but the fact is that Qwest does “house” this information. Thus, I continue to request that the “existing” information be extracted “from whatever source” and provided for on the “Line In Service Report”. The original request did not ask that the back-end systems be expanded to house this information, thus I don’t believe an updated request is needed.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Friday, September 30, 2005 11:54 AM To: Balvin, Elizabeth Subject: PC060105-01 Update Lines in Service Report

Hi Liz,

This is a follow up to the discussion we had in the August CMP Meeting regarding the denial on PC060105-01 Update Lines in Service Report. (See Meeting Minutes below) We have determined that the cost to combine the two systems so that the billing information you are requesting is included in the Lines in Service Report is economically not feasible. The denial attached has been revised to reflect the new project description and costs. Let me know if you have any questions.

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

8/17/05 CMP Meeting

PC060105-1 Update Lines In Service Report

Liz Balvin - Covad stated that she had questions regarding the denial. She said that Qwest refers to backend systems to generate the reports and wants to understand what the system has. Liz said that she wants the SBN at a minimum and would like a call to further discuss.

Laura McGhghy - Qwest stated that the data we are currently providing is existing data. {Comment received from Eschelon: from the MR-8 report]. She said that she was not sure what other systems would be needed for additional data and what that level of effort would be. [Comment received from Eschelon: Laura said they don’t have the fields in LMOS and TIRKS.]

Liz Balvin - Covad said that they would like to expand the report. She said that the report is an extract from LMOS and Tirks [Comment received from Eschelon: and she did not ask that Qwest get the data from those systems.] Liz said that she needs to expand the line and service report to create fields there and extract data elsewhere.

Laura McGhghy - Qwest said that she would take back to determine if possible.

Liz Balvin - Covad asked if the $500K to expand was because of LMOS and Tirks.

Laura McGhghy - Qwest said yes.

Liz Balvin - Covad said that Qwest already has the information and that they are just asking for the information on the report. [Comment received from Eschelon: Liz said wherever Qwest extracts the data from works for her.]

Laura McGhghy - Qwest said that we will look at that possibility.

Jill Martain - Qwest stated that we will talk offline with Covad.

8/17/05 Product/Process CMP Meeting

Liz Balvin - Covad stated that she had questions regarding the denial. She said that Qwest refers to backend systems to generate the reports and wants to understand what the system has. Liz said that she wants the SBN at a minimum and would like a call to further discuss. Laura McGhghy - Qwest stated that the data we are currently providing is existing data. {Comment received from Eschelon: from the MR-8 report]. She said that she was not sure what other systems would be needed for additional data and what that level of effort would be. [Comment received from Eschelon: Laura said they don’t have the fields in LMOS and TIRKS.] Liz Balvin - Covad said that they would like to expand the report. She said that the report is an extract from LMOS and Tirks [Comment received from Eschelon: and she did not ask that Qwest get the data from those systems.] Liz said that she needs to expand the line and service report to create fields there and extract data elsewhere. Laura McGhghy - Qwest said that she would take back to determine if possible. Liz Balvin - Covad asked if the $500K to expand was because of LMOS and Tirks. Laura McGhghy - Qwest said yes. Liz Balvin - Covad said that Qwest already has the information and that they are just asking for the information on the report. [Comment received from Eschelon: Liz said wherever Qwest extracts the data from works for her.] Laura McGhghy - Qwest said that we will look at that possibility. Jill Martain - Qwest stated that we will talk offline with Covad.

7/20/05 Product/Process CMP Meeting

Lynn Stecklein - Qwest stated that Covad is requesting the Special Billing Name and Address be included on the existing Service Report. She said that this information is not available in the tool that is used today to extract the data for the Service Report. She said that this CR will be placed in Evaluation to determine if other options are available. Liz Balvin - Covad asked that Qwest look to include the SBN at a minimum. Jill Martain - Qwest that this CR will be moved to an Evaluation Status.

6/15/05 Product/Process Meeting

Liz Balvin - Covad stated that they are requesting that Qwest add the special billing number and address information to the lines in the service reports currently generated on the performance measurement website. Liz stated that they are asking for this information because of the lack of Circuit ID on Line Shared Bills. Liz said that the Line Share Report has the TN and that Qwest’s bills track to the SBN. Liz said that they are asking for the SBN and address to be added as a double check to make sure they are looking at the correct end user and would help in eliminating disputes. Jill Martain - Qwest stated that this CR will move to Presented.

6/8/05 Clarification Meeting

Attendees: Liz Balvin - Covad, Laura McGhghy, Lynn Stecklein - Qwest

Review Description of Change Liz Balvin - Covad stated that they are requesting that Qwest add the special billing number and address information to the lines in service reports currently generated on a monthly basis and said that this information is not in the current file. Liz stated that this essentially impacts their Line Share Orders. Liz said that the SBN is the tracking mechanization for Qwest and that they would like the tracking mechanization to be the TN. Liz said that they would use this information to sync up their lines with the bill and that the address would be an additional validation. Liz said that Qwest tracks to TN because they have the voice part of the line and they have the data portion. Liz said that this information would help in eliminating disputes.

Laura McGhghy - Qwest asked for an example of the SBN.

Liz Balvin - Covad provided the example of SBN (503 T22-1828)

Laura McGhghy - Qwest asked if the address they were looking for was the end user address.

Liz Balvin - Covad said that they were looking for the end user address.

Establish Action Plan Lynn Stecklein - Qwest said that Covad will present this CR in the June 15th Product/Process Meeting


CenturyLink Response

August 9, 2005

Qwest Response For Review by the CLEC Community and Discussion at the August 17, 2005 CMP Meeting

TO: Liz Balvin Covad

SUBJECT: Covad’s Change Request Response - PC060105-1 Update Lines in Service Report

CR Description: Covad’s change request states:

Add special billing number and address information

Covad is requesting that Qwest will add the special billing number and address information to the lines in service reports currently generated on a monthly basis.

Qwest Response:

Qwest has reviewed the change requested with this CR and has determined the following:

Qwest’s Lines in Service report was built as a response to a CMP request and currently is created from data contained in Qwest’s Network back-end systems, which inventory the circuits and lines by the circuit ID/working telephone number. These systems are not used for billing or account maintenance; rather, they are used for inventory and trouble reporting only. For this reason, the source system does not contain the SBN or billing address, nor are these fields available to contain this information. The cost to add the additional fields to the back-end systems and to populate the fields with the information from the Service Order Processor is $500,000.00.

Due to the low volume of Customer’s requesting this report and the costs associated with implementing this request, Qwest denies this change request due to economic infeasibility.

Sincerely,

Qwest


Open Product/Process CR PC072604-1 Detail

 
Title: Line Sharing Provisioning Interval
CR Number Current Status
Date
Area Impacted Products Impacted

PC072604-1 Denied
10/20/2004
ordering, provisioning UNE, Line sharing family of products
Originator: Berard, John
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: Andreen, Doug

Description Of Change

Covad proposes that a one day interval be provided for all Line Sharing Family of products that do not require a field dispatch. Qwest has shown that this is possible as outlined in the attached two accessible letters. (See Supplemental Information)

Expected Deliverable: As soon as possible


Status History

7/26/04 - CR submitted

7/28/04 - CR acknowledged

8/5/04 - Held Clarification Call

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/16/04 CMP Meeting Minutes Cindy Buckmaster reported that there has been an ad-hoc call and she would like to move this CR to Evaluation status and will have the full response next month. The CR will move to Evaluation Status.

8/18/04 CMP Meeting John Berard presented the CR saying that Covad is looking for a one day interval on line share orders. He had seen some notices with one day intervals from Qwest and is looking for the same thing in Wholesale. The CR will move to Presented status.

-- Clarification Meeting

1:00 p.m. (MDT) / Thursday August 5, 2004

1-877-521-8688 1456160# PC072604-1 Line Sharing Provisioning Interval Attendees

John Berard, Covad Doug Andreen, Qwest Heidi Moreland, Qwest Crystal Soderlund, Qwest Bob Mohr, Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0Review Requested (Description of) Change Doug Andreen, Qwest read and reviewed the CR. The CR is titled Line Sharing Provisioning Interval and the description reads Covad proposes that a one day interval be provided for all Line Sharing Family of products that do not require a field dispatch. Qwest has shown that this is possible as outlined in the attached two accessible letters. Doug ask John Berard, Covad if he had anything to add to the description and he said not really that it was pretty self explanatory Heidi Moreland, Qwest asked if the request was for Line Sharing only or did it include Line Splitting or all the shared loop products. John answered that Line Sharing as the primary product with Line splitting being nice to have. John also added that the CR just includes those orders that involve CO work only. There were no further questions and the meeting was concluded. 3.0 Confirm Areas & Products Impacted Line Sharing and Line Splitting 4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0 Identify/Confirm CLEC’s Expectation To be done as soon as possible. 6.0 Identify any Dependent Systems Change Requests TBD 7.0 Establish Action Plan (Resolution Time Frame) John Berard, Covad will present the CR at the August CMP meeting. Qwest will respond at the September meeting.


CenturyLink Response

October 12, 2004

For Review by the CLEC Community and Discussion at the October 20, 2004 CMP Meeting

TO: John Berard Director Operations Support COVAD Communications

SUBJECT: CLEC CR - PC072604-1 Line Sharing Provisioning Interval

Covad proposes that a one day interval be provided for all Line Sharing Family of products that do not require a field dispatch and states “Qwest has shown that this is possible as outlined in the attached two accessible letters”. (See Supplemental Information)

This request is respectfully denied due to No Measurable Benefit to both Qwest and the CLEC.

The intervals offered in the documentation attached to the CR were short in duration and limited in scope – thus promotional. Promotional offerings by Qwest are not mechanized and therefore limited in order to provide a service for customers that would otherwise either not be accommodated or that would take time and costly system changes to effect. These promotional offerings were noticed to the CLEC community so that they too could take advantage of this interval during this time frame in this market. They are neither, by virtue of their short term nature, permanent nor extendable outside of the designated market.

Permanent interval changes, as mentioned above, affect both the systems and the work force. CLEC intervals are set to ensure parity and/or to provide a competitor a meaningful opportunity to compete. Qwest’s intervals were evaluated during Third Party testing, in some cases specific product intervals were ruled upon by state commissions and Qwest’s actual commercial performance (which is driven by existing intervals) was repeatedly found acceptable by the FCC in its evaluation of Qwest’s 271 applications. Additional changes are accommodated as process changes are made that can reduce the interval or where retail intervals are likewise reduced (where there is a comparable retail equivalent product).

COVAD has also entered a Commercial Agreement with Qwest that went into effect on October 2, 2004. That document states that the Line Sharing interval shall be Three (3) Business Days. While a CMP change in interval could be negotiated between the parties prior to October 2, such a change would be in effect at most 10 days in duration when that CMP negotiation would be superceded by the stated interval in your Commercial Agreement.

Because of their intensive nature, interval changes are costly and difficult to price. As Qwest is not required to undertake the substantial, costly modifications and upgrades to its systems and processes to allow a CLEC to order UNEs and other services at an interval different than the standard interval for the product and there is negative measurable benefit to Qwest and no demonstrable gain over the options already offered to the CLEC, this request is respectfully denied.

Sincerely,

Qwest

- September 8, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the September 2004 CMP Meeting

John Berard Director Operations Support Covad

SUBJECT: Qwest’s Change Request Response PC072604-1 Line Sharing Provisioning Interval

This letter is in response to Covad’s Change Request (CR) PC072604-1. This CR requests that Qwest provide a one day interval for all Line Sharing Family of products that do not require a field dispatch.

Qwest is currently evaluating this request and proposes moving this Change Request into Evaluation Status while we continue to investigate. Qwest will provide an updated response at the October 2004 CMP meeting.

Sincerely,

Cindy Buckmaster Product Manager - Qwest


Open Product/Process CR PC081705-1 Detail

 
Title: First Right of Refusal Procedures
CR Number Current Status
Date
Area Impacted Products Impacted

PC081705-1 Denied
3/15/2006
Billing, Notification Line Split/Shared
Originator: Balvin, Liz
Originator Company Name: Covad
Owner: Buckmaster, Cindy
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest currently lacks procedures surrounding existing shared lines whereby the TN is ported and the circuit remains available for use. Covad seeks the right to maintain DSL on existing circuit in the event the telephone number is ported off Qwest’s switch. Scenarios include (but may not be limited to): Existing services = 1) line splitting 2) line sharing and an LNP order is received to port number to 1) cable 2) VoIP or 3) wireless. Procedures to consider surround notification allowing first right of refusal and billing changes.


Status History

8/17/05 - CR submitted

8/18/05 - CR acknowledged

8/25/05 - Clarification Meeting held

8/25/05 - Status changed to clarification

9/21/05 - Status changed to presented

9/21/05 - Discussed in the September Product/Process CMP Meeting - See Distribution Package Attachment C

10/11/05 - Draft Response Issued

10/11/05 - Status changed to Evaluation

10/10/05 - Discussed in the October Product/Process CMP Meeting - See Distribution Package Attachment C

11/16/05 - Discussed in the November Product/Process CMP Meeting - See Distribution Package Attachment C

12/14/05 - Discussed in the December Product/Process CMP Meeting - See Distribution Package Attachment C

1/18/06 - Discussed in the January Product/Process CMP Meeting - See Distribution Package Attachment C

1/31/06 - Additional Clarification Meeting held with Covad

2/15/06 - Discussed in the FebruaryProduct/Process CMP Meeting - See Distribution Package Attachment C

3/15/06 - Status changed to Denied

3/15/06 - Discussed in the March Product/Process CMP Meeting - See Distribution Package Attachment C


Project Meetings

3/15/06 Product/Process CMP Meeting

Cindy Buckmaster-Qwest stated that the denial response is located in the March Distribution Package. Cindy said that Covad is requesting the right to maintain the DSL on an existing circuit in the event the telephone number is ported off Qwest’s switch. She said that CMP is a process for is a warehousing effort for all CLECs and would not be fair to Qwest as information related to ports away from other providers will not be available and could not be pro-actively noticed. She said that this would be a CPNI violation to other providers and that we can’t accept this request via CMP. Lynn Hankins-Covad stated that she would have to get back to Qwest. Lynn asked if the reason for the denial is that divulging Qwest information is confidential. Cindy Buckmaster-Qwest said that we can divulge Qwest information as a CLEC but cannot divulge any other CLECs information. She said that this makes it unfair to Qwest as a CLEC. Lynn Hankins-Covad stated that she would get back to Qwest and that she may request an adhoc meeting.

2/15/06 Product/Process CMP Meeting

Cindy Buckmaster-Qwest stated that another clarification meeting was held with Covad because of the changes in personnel on this request. She said that Qwest fully understands the request and that a response will be provided in the March CMP Meeting. Lynn Hankins-Covad asked if Qwest received the 2 e-mails she sent to Lynn Stecklein (Qwest). Lynn Stecklein-Qwest stated that the 2 e-mails were received and that Qwest is currently reviewing. Lynn asked if there was a specific question Covad wanted to address now.

Lynn Hankins-Covad said no, that she was confirming that the e-mails were received.

Jill Martain-Qwest said that this CR will remain in Evaluation and a response will be provided in the March Meeting.

1/31/06 Adhoc Meeting with Covad

Attendees: Lynn Hankins - Covad, Cindy Buckmaster - Qwest, Paul Schlater - Qwest, Alan Braegger - Qwest, Shirley Tallman - Qwest, Jamal Boudhaouia - Qwest, Lori Burchett - Qwest, Lynn Stecklein - Qwest

Lynn Stecklein - Qwest stated that Qwest requested an additional clarification meeting with Covad in the January CMP Meeting to further discuss this CR.

Cindy Buckmaster - Qwest stated that several of the SMEs working on this CR were no longer with Qwest and that we wanted to get a clear understanding of what Covad was requesting on this CR.

Lynn Hankins - Covad said that they were Covad is looking to maintain DSL on existing circuits in the event the telephone number is ported off Qwest’s switch. She also said that they would like to know 1st if the line is taken down and would like to keep with no downtime to the customer.

Cindy Buckmaster - Qwest said that Covad would not be the Voice Provider and that Covad's principal product is the DSL. She said that the voice provider is the controller of the circuit.

Lynn Hankins - Covad said that they would notification whether or not Qwest or the CLEC is the owner of the line.

Cindy Buckmaster - Qwest asked if Lynn Hankins (Covad) was aware of any other CR submitted in the past requesting the same thing as this CR.

Lynn Hankins - Covad stated that she was not aware of any.

Cindy Buckmaster - Qwest stated that this CR will remain in Evaluation and that Qwest will provide a response if the March Product/Process CMP Meeting.

1/18/06 Product/Process CMP Meeting

Cindy Buckmaster - Qwest said that several SMEs are no longer with Qwest and that we would like to have a meeting with Covad to discuss this CR. Lynn Hankins - Covad stated that she was fine with having another adhoc meeting. Jill Martain - Qwest said that Lynn Stecklein (Qwest) will contact Lynn Hankins (Covad) to schedule a meeting.

12/14/05 Product/Process CMP Meeting

Jill Martain/Qwest stated that we are still evaluating all options and feasibility on this CR. She said that this CR will remain in evaluation and that we will provide a status in the January CMP Meeting.

11/16/05 Product/Process CMP Meeting

Lynn Stecklein/Qwest stated that this request was placed in evaluation last month. She said that internal discussions are still underway to ensure all potential solutions are reviewed and analyzed. She stated that an updated response will be provided in the December CMP Meeting

10/19/05 Product/Process CMP Meeting

Anthony Washington/Qwest said that we would like to place this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. He said that Qwest will provide an updated response at the November CMP meeting. Jill Martain/Qwest stated that this CR will move to Evaluation status.

9/21/05 Product/Process CMP Meeting

Liz Balvin/Covad stated that they are seeking the right to maintain DSL on existing circuit in the event the telephone number is ported off Qwest’s switch. Bonnie Johnson/Eschelon asked if this is just for line sharing. Liz Balvin/Covad stated it would apply to Line Splitting and Line Sharing when the number is ported out. Jill Martain/Qwest stated that this CR will move to presented.

E-mail send to Covad

Hi Liz,

In the Line Sharing environment, the orders are issued directly by the DLEC.

In the case of Line Splitting, Qwest understands that DLECs can issue orders under the 'owning' carriers (Customer of Record) log in as per arrangement between the CLEC and DLEC. LSOG 6-LSR field 7b is listed as DLEC CCNA - CCNA (Customer Carrier Name) for DLEC (Data Local Exchange Carrier) The Customer of record is required to populate this field for Line Splitting, which is how Qwest identifies the DLEC.

Let me know if you have additional questions.

Thanks,

Lynn Stecklein Qwest Wholesale CRPM 303 382-5770

8/31/05 E-mail from Covad

Lynn,

Thanks, I do have an additional question. In the Line Sharing environment, while the orders are issued by DLECs under owning carriers company code information, how does Qwest identify the DLEC?

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Wednesday, August 31, 2005 8:20 AM To: Balvin, Elizabeth Subject: Re: PC081705-01 First Right of Refusal Procedures

Hi Liz,

This is in response to your question regarding how Qwest identifies the line is shared. Qwest floats FIDS after the Line Assignable USOC that is shared and that is how we recognize it. The Line Splitting product mirrors the Line Share product in this way. Let me know if you have further questions.

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

--Original Message-- From: Balvin, Elizabeth [mailto:ebalvin@covad.com] Sent: Monday, August 29, 2005 1:37 PM To: Stecklein, Lynn Subject: RE: PC081705-1 First Right of Refusal Procedures

Lynn,

To follow-up on when the line that exists is line splitting (UNE-P plus DSL):

Covad would like to understand how Qwest identifies the line is shared?

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Tuesday, August 23, 2005 9:22 AM To: Balvin, Elizabeth

8/25/05 Clarification Meeting

Attendees: Liz Balvin - Covad, Crystal Soderlund - Qwest, Heidi Moreland - Qwest, Ellen McArthur - Qwest, Anthony Washington - Qwest, Lynn Stecklein - Qwest

Review Description of Change Lynn Stecklein - Qwest reviewed the CR description. Covad stated that Qwest currently lacks procedures surrounding existing shared lines whereby the TN is ported and the circuit remains available for use. Covad seeks the right to maintain DSL on existing circuit in the event the telephone number is ported off Qwest’s switch. Scenarios include (but may not be limited to): Existing services = 1) line splitting 2) line sharing and an LNP order is received to port number to 1) cable 2) VoIP or 3) wireless. Procedures to consider surround notification allowing first right of refusal and billing changes.

Discussion: Crystal Soderlund - Qwest asked if the customer was currently with Covad or would this apply to any owner of shared service and if this was Line Splitting would Covad be the owner. Liz Balvin - Covad said no. Liz asked asked how they maintain a number porting on a standalone disconnect of voice. Liz said that she would like a process implemented to notify Covad and asked how Qwest maintains the DSL on the loop. Crystal Soderlund - Qwest said that we don't because we lose it. Liz Balvin - Covad stated that Verizon has a manual workaround today where they provide a spreadsheet for losses. Crystal Soderlund - Qwest stated that Qwest has a process to notify the voice provider via the loss and completion report. Heidi Moreland - Qwest asked if Covad wanted wanted this information before the disconnect was completed. Liz Balvin - Covad said that they would prefer the information prior to the disconnect completion and that this would prevent customer downtime. Crystal Soderlund - Qwest said that with line splitting, the loss is not to the voice provider. Crystal said that line splitting should be removed from this CR. She said that Qwest would not know because we only have 1 customer of record. Liz Balvin - Covad stated that she needed to check internally on the line splitting portion of the CR

Confirm Areas and Products Impacted Line Split/Shared

Establish Action Plan Liz Balvin - Covad will present this CR in the September 21st Product/Process CMP Meeting


CenturyLink Response

March 9, 2006

For Review by CLEC Community and Discussion at the March 2006 CMP Meeting

Lynn Hankins Covad Communications

SUBJECT: Change Request Response - PC081705-1 First Right of Refusal

This letter is in response to Covad’s Change Request (CR) PC081705-1. Covad is requesting the right to maintain the DSL on an existing circuit in the event the telephone number is ported off Qwest’s switch. The CR includes scenarios for Line Splitting and Line Sharing where an LNP order is received to port a number to a cable, VOIP or Wireless provider.

Qwest has evaluated this CR and finds that implementing Covad’s request would require proactive notification. Additionally, it would only be technically feasible to perform this function in circumstances where the voice circuit belongs to Qwest.

ILECs such as Qwest are obligated to treat all service providers in a similar fashion. Since Qwest is only aware of the request in those instances where the porting or disconnection of a Qwest voice circuit is required, Qwest cannot provide proactive notification in 100 percent of the cases where porting or disconnecting a voice circuit will also affect a corresponding DSL service. This would create an uneven playing field, and would pose serious legal problems concerning the entire porting process.

For the reasons cited above, Qwest respectfully denies the request.

Sincerely,

Qwest Corporation

10/11/05 Draft Response

For Review by the CLEC Community and Discussion at the October 17th CMP Meeting

October 11, 2005

Covad Liz Balvin

SUBJECT: CR # PC081705-1 First Right of Refusal Procedures

This letter is in response to Covad's Change Request (CR) PC081705-1 First Right of Refusal Procedures. This CR requests that Qwest Covad seeks the right to maintain DSL on existing circuit in the event the telephone number is ported off Qwest’s switch. Scenarios include (but may not be limited to): Existing services = 1) line splitting 2) line sharing and an LNP order is received to port number to 1) cable 2) VoIP or 3) wireless. Procedures to consider surround notification allowing first right of refusal and billing changes.

Qwest would like to place this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. Qwest will provide an updated response at the November CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Qwest


Open Product/Process CR PC072203-1 Detail

 
Title: Extend length of time CLEC’s have to respond on Jeop Notices
CR Number Current Status
Date
Area Impacted Products Impacted

PC072203-1 Denied
10/15/2003
Ordering, Provisioning Affects any product ordered on an LSR
Originator: Morris, Kelly
Originator Company Name: Electric Light Wave (ELI)
Owner: Martain, Jill
Director:
CR PM: Harlan, Cindy

Description Of Change

ELI proposes that Qwest extend the 4 business hour response time on Jeop Notices to 8 business hours, or 1 business day. Qwest needs to allow the CLEC more time to receive the jeop notice, research, and communicate the jeop notice to the applicable parties.

Currently when Qwest sends the CLEC a Jeop Notice, the CLEC is only given 4 business hours to respond. If the CLEC does not respond, meaning supping the order, within those 4 hours, the order is internally canceled with Qwest. Most often, the CLEC is required to supp out the due date when this happens because Qwest has canceled the internal order and requires standard interval to re-work the order.

Qwest does not take in to consideration that the CLEC has called within that 4 business hour time frame and tried to resolve the jeop. Qwest does not consider this a response within the 4 business hours, even when Qwest opens a trouble ticket for the CLEC. Qwest also needs to take into consideration the time zone differences when expecting the CLEC to respond within 4 hours. If the CLEC is in the Pacific time zone, and the jeop notice was sent from a Qwest center in the Central time zone, the CLEC may only have 2 hours to respond depending on the time the jeop notice was sent to the CLEC.

Expected Deliverable:

ELI proposes that the jeop notice response time be revised and implemented immediately.


Status History

07/22/03 - CR Submitted

07/23/03 - CR Acknowledged

7/28/03 - Customer contacted

7/30/03- Clarification call held

8/20/03 - August CMP meeting held

9/9/03 - Posted response to database

9/17/03 - Sep CMP notes will be posted to the database

10/8/03 - Sent response to CLEC

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section


Project Meetings

10/15/03 CMP Meeting Ellen McArthur – Qwest that she is providing the response as Jill Martain is on vacation. Ellen reviewed the response and advised that Qwest is denying this change for economically not feasible reasons. Making this change would create the risk of completing the orders early or not being able to meet the due date when the supplement is received on the same day as the due date. This change would cause potential rework and additional manual work for Wholesale and Network representatives. The status will be changed to Denied.

9/17/03 CMP Meeting Jill Martain – Qwest reviewed the response. Jill requested this CR move to Evaluation. Liz Balvin-MCI asked if ELI is working with Qwest on this CR. Cindy Macy-Qwest advised that Kelly Morris-ELI did reply to my email when I sent her the response.

8/20/03 CMP Meeting Kelly Morris-ELI explained she is asking for Qwest to extend the Jeop respond time from 4 to 8 hours. Kelly explained they are Pacific Time and if the Jeop comes in at end of day they actually only get 1 hour to work to Jeop. They loose up to 3 hours of the Jeop response time based on time zone and working hour differences. Stephanie Prull-McLeod and Bonnie Johnson-Eschelon agreed and advised they support this CR. Stephanie explained they have Saturday provisioning issues. Integra also stated that they believe the majority of CLECs would support this request. This CR will move to Presented status.

CLEC Change Request – PC072203-1 Clarification Meeting Wednesday, July 30, 2003

1-877-572-8687 3393947#

Attendees Cindy Macy – CRPM Jill Martain – Qwest Denise Martinez – Qwest Phyllis Sunins – Qwest Kelly Morris – ELI Shaby Bellow – ELI Nicole Johnson – ELI Lynn Kellas - ELI

Introduction of Attendees Cindy Macy-Qwest welcomed all attendees and reviewed the request. Cindy went through the CMP process steps so the team is aware of what to expect.

Review Requested (Description of) Change Kelly Morris – ELI reviewed the CR. ELI explained the difficulty they have with a 4 hour JEP response. Because their office hours are 8:00 – 5:00 and they are in the Pacific time zone they generally only get 2 hours to respond.

Jill explained Qwest JEP process is from 7 am to 7pm. So if a JEP goes out at 7pm MST the customer would have until 11am MST to respond.

Kelly advised this equates to a customer response by 10am PST. That only gives ELI 2 hours to process the JEP. Generally it takes ½ hour to discuss this with the centers so there is minimal time to handle the JEP.

Confirm Areas and Products Impacted Cindy confirmed this CR applies to all products that have a 4 hour JEP response time. Some JEP times are different (30 days) but this CR applies to 4 hour response time frame JEPS.

Confirm Right Personnel Involved Cindy confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation The team agreed they understand the CLECs expectation.

Identify any Dependant Systems Change Requests No dependant CRs are open.

Establish Action Plan Cindy asked attendees if there were any further questions. There were none. Cindy stated that the next step was for Kelly Morris - ELI to present the CR at the August Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

October 8, 2003

For Review by CLEC Community and Discussion at the October 15, 2003, CMP Product/Process Meeting

Kelly Morris ELI

SUBJECT: CLEC Change Request Response - CR #PC072203-1

This CR is asking for Qwest to extend the time frames in which the CLEC has to respond to an error condition identified after a FOC from four to eight business hours.

Qwest reviewed jeopardy notices that were issued after a FOC that utilized a Jeopardy Code of C05 and SX from August 1 to September 8, 2003, to see what the impacts could be if we were to extend the time frames of the jeopardy notices from 4 to 8 business hours.

Extending the time frame to 8 business hours in essence allows one extra business day for the CLEC to respond to the jeopardy notice and potentially shortens Qwest provisioning interval by approximately 4 business hours (as we already allow a 4 hour response window for these types of jeopardies.) We looked to see what the impacts would be in the Wholesale side if the time frames were extended.

Meetings were held to determine what would need to transpire in order for the customer to maintain the due date. It was determined that additional hand-offs within the Service Delivery organization would need to take place to manually track and monitor each of the orders if the time frames were extended. Manual hand-offs between organizations and potential supplements of the service orders may need to occur to ensure that the orders do not get completed in error while we are waiting for a response from the CLEC. Additionally, when the supplemental LSR is received, manual handling would be required to contact the Network organization to advise them that the order is now ready to be installed and get the order back into the provisioning process. For certain designed services, escalations may be required to get the design complete, the DLR issued and the central office and outside technicians rescheduled.

Qwest’s estimate for the manual work required within the Wholesale organizations alone is $400,000.00 annually to be able to maintain this process. This does not take into consideration the manual time and additional resources that would be required from the Network organization to ensure that the due date could be met. Due to the economic impacts and the fact that orders will require additional manual handling due to the risks of either completing the order early or not being able to meet the due date when the supplement is received on the same day as the due date, Qwest denies this request for economically not feasible reasons.

Jill Martain Wholesale Markets Process Organization

September 9, 2003

For Review by CLEC Community and Discussion at the September 17, 2003, CMP Product/Process Meeting

Kelly Morris ELI

SUBJECT: CLEC Change Request Response - CR #PC072203-1

This is a preliminary response regarding the ELI CR PC072203-1. This CR requests an extension of the time frames required to respond to jeopardy notices from four to eight business hours.

Qwest is currently working internally to identify if a solution or a different option to this request can be implemented. Because there are a number of complex issues involved with extending the existing timelines, Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the October CMP meeting.

Sincerely, Jill Martain Wholesale Markets Process Organization


Open Product/Process CR PC072203-2 Detail

 
Title: Expand PTA, Auto Acceptance, for all UNE Loop and EEL/LMC Products
CR Number Current Status
Date
Area Impacted Products Impacted

PC072203-2 Denied
10/15/2003
Provisioning, Test & Turn up Unbundled Loop, UNE, EEL (UNE-C), LMC
Originator: Morris, Kelly
Originator Company Name: Electric Light Wave (ELI)
Owner: McConnell-Couch, Joy
Director:
CR PM: Harlan, Cindy

Description Of Change

ELI proposes that Qwest make available the option for auto acceptance (PTA) of circuits to cover all UNE Loop and EEL/LMC Products.

Currently Qwest and ELI have agreed on auto acceptance (PTA) for all DS1 circuits ordered on ASR’s. ELI would like to have auto acceptance (PTA) for UNE Loop and EEL/LMC circuits ordered on LSR’s. ELI was told auto acceptance (PTA) was not an option for these LSR products. However 50% of ELI’s UNE Loop and EEL/LMC circuits had been auto accepted by Qwest. Once ELI took this issue to Qwest for resolution, all auto acceptance for these products was stopped. ELI would like Qwest to auto accept all UNE Loop and EEL/LMC circuits, not just some. ELI has provided Qwest with orders that were auto accepted by Qwest, and can provide CMP with those examples.

Expected Deliverable

ELI proposes that auto acceptance (PTA) be made available for all UNE Loop and EEL/LMC Products immediately


Status History

07/22/03 - CR submitted

07/24/03 - CR Acknowledged

7/28/03 - Contacted customer

7/31/03 - Held Clarification Call

8/20/03 - CMP Status Meeting

9/9/03 - Posted response to database

9/17/03 - Sep CMP meeting notes will be posted to the database

10/8/03 - Sent response to CLEC

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section


Project Meetings

10/15/03 CMP Meeting Joy McConnell Couch – Qwest reviewed the response. Joy explained due to low volumes, estimated system and business enhancement costs this CR is denied for economically not feasible reasons. In addition, this change does not result in a customer service improvement in some cases. The status will be changed to Denied.

9/17/03 CMP Meeting Joy McConnell Couch reviewed the response. Joy advised this is a complex process and Qwest would like to move the CR to Evaluation.

8/20/03 CMP Meeting Kelly Morris-ELI presented the CR and explained they are requesting the same Auto Accept process on UBL/EEL and LMC orders that is in place for private line services ordered via an ASR. Kelly explained on (PTD) Plant Test Date the circuit is installed and tested. If it tests okay, an email PTA goes out and the CLEC is given 24-48 hours to respond. If no response is received the circuit is accepted. No further questions were asked. This CR will move to Presented status.

Clarification Meeting

Thursday July 31, 2003 10:30 – 11:30 1-877-572-8687 3393947# PC072203-2 Auto Accept PTA for UNE Loop / EEL

Attendees Kelly Morris – ELI Lynn, Gayla and Marlene - ELI Ann Binkley – Qwest Jeanne Whisenant - Qwest Robin Libadia-Qwest Denny Graham – Qwest Kathy Ocken – Qwest Joy McConnell Couch – Qwest Deni Toye – Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees introduced. Cindy Macy – Qwest reviewed the process and explained what to expect from the call and next steps in the CMP process.

2.0 Review Requested (Description of) Change Kelly Morris ELI reviewed the change request. Kelly and the ELI team explained Qwest is doing Auto Acceptance for PLT services currently. Occasionally Qwest was also performing Auto Acceptance for UNE products. Qwest later told us that Auto Acceptance was not available on UNE products. ELI would like the same ‘Auto Acceptance’ process that is offered to PLT products for UNE products. Kathy Ocken explained the Auto Acceptance process. This process is available for PLT provisioning; DSO and Non-Muxed DS1 for example. On Plant test date the circuit is installed and tested per national standard. When the circuit is good the PTA form is filled out. The form is sent via email to the customer. If we have not heard back from the customer on FOC’d due date, then the billing begins. If a problem is found the CLEC can call the Provisioning Tech within 30 days to work on or open Trouble report. Kathy explained Auto Accept PTA is only offered on Private Line service ordered via ASR. It is not an LSR offered service. Deni Toye explained Qwest has a UBL PTA process but it is a different process . It is for NDT notification and test results. The test results of the NDT are emailed to the CLEC 24 to 36 hours before the due date. The test results are emailed to the CLEC after verbal acceptance. It is available on DS0 to OCN products. Gayle – ELI NOC Supervisor recommends Qwest offer this service on UNE as it cuts down on phone calls between companies, helps provide server faster to the end user customers and allows ELI to schedule their technicians better. If the line does not test okay, ELI has not had any problems with Qwest being able to fix the trouble on the line. Kathy Ocken advised Qwest does have a generic document for ASR ordered service that offers Auto Acceptance. She advised this was provided to the Service Managers. This is only for ASR services though.

3.0 Confirm Areas & Products Impacted UNE, Unbundled Loop, EEL, LMC I am currently trying to confirm with ELI what the impacted products are. There was a question regarding UNE Loop versus Unbundled Loop and which one ELI is asking for. I will update the database when I get confirmation on this from ELI.

4.0 Confirm Right Personnel Involved Network will take the lead on this CR.

5.0 Identify/Confirm CLEC’s Expectation ELI would like the same ‘Auto Acceptance’ process that is offered to PLT products for UNE products.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) ELI will present the CR at the August CMP Meeting Qwest will provide our Response at the September CMP Meeting


CenturyLink Response

October 8, 2003

For Review by the CLEC Community and Discussion at the October 15, 2003 CMP Meeting

Kelly Morris ELI

SUBJECT: Qwest’s Change Request Response - PC072203-2 “Expand PTA, Auto Acceptance, for all UNE Loop and EEL/LMC Products”

This letter is in response to CLEC Change Request PC072203-2. This CR is a request by ELI for Qwest to extend the existing process of Provider Tested Access (PTA) used for Interexchange Carrier Private Line orders to include the UNE Loop and EEL/LMC products.

Qwest is denying this request to implement the specified PTA process on the EEL/LMC products because the requested change is not economically feasible. This change also does not result in a customer service improvement. The following supports this decision:

Expected low order volumes and estimated system and business enhancement costs of $150,000 do not support the implementation of this process. Today, cooperative testing is performed to ensure EEL/LMC circuits are provisioned and accepted by the CLEC. This current process facilitates a positive experience for the customer by minimizing potential service degradation resulting from repair calls after the due date. The specified PTA process does not apply to unbundled loop products as other optional test processes currently exist for these products.

Sincerely,

Joy McConnell-Couch Staff Advocate Policy and Law Qwest

- September 9, 2003

For Review by CLEC Community and Discussion at the September 17, 2003, CMP Product/Process Meeting

Kelly Morris ELI

SUBJECT: Qwest’s Change Request Response - CR #PC072203-2

This is a preliminary response regarding the ELI CR PC072203-2. This CR requests expansion of the Interexchange Carrier Private Line PTA Auto Acceptance process to the UNE loop and EEL/LMC products.

Qwest is currently working internally to identify if a solution to this request can be implemented. Because there are a number of complex issues involved with expanding the existing process for use with the requested unbundled products, Qwest requests moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the October CMP meeting.

Sincerely, Joy McConnell-Couch Staff Advocate Policy and Law


Open Product/Process CR PC072303-1 Detail

 
Title: Customer Not Ready ("CNR") jeopardy notice should not be sent by Qwest to CLECs before 5 PM local time on the due date (for basic install)
CR Number Current Status
Date
Area Impacted Products Impacted

PC072303-1 Completed
2/18/2004
Provisioning Any product with test and accept of a circuit on a basic install and the current process applies.
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Martain, Jill
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Customer Not Ready ("CNR") jeopardy notice should not be sent by Qwest to CLECs before 5 PM local time on the due date (for basic install). If a CLEC is not ready to test at the time Qwest calls on the due date, the CLEC has until 5 PM to call Qwest and test and accept the circuit. Qwest should not place the Local Service Request ("LSR") in a customer not ready jeopardy status, because the customer is ready within the required time frame.

Qwest does not provide CLECs with a specified time on the due date when testing and acceptance will take place. Testing and acceptance may occur any time before 5 pm local time. As long as the CLEC is ready to test and accept the circuit before 5pm on the due date, therefore, the customer is ready on the due date. Nonetheless, Qwest places a "CNR" jeopardy on an LSR if Qwest calls a CLEC to test and accept the circuit on the due date and the CLEC is not ready to test and accept the circuit at the time Qwest calls. Even if the CLEC communicates to Qwest that it will call Qwest back on the due date and before 5 PM local time, Qwest places the request in a CNR jeopardy status. Qwest should not use the CNR jeopardy notice for this situation. CNR is not a valid jeopardy code, because the CLEC is ready before 5pm (i.e., on the due date).. By incorrectly using the CNR jeopardy for this situation, , Qwest forces CLECs to manage CNR jeopardy notices that have no validity. Qwest is causing CLECs additional work in the CLECs workflow process for no valid reason. Qwest should change the process on issuing CNR jeopardy for this situation. Eschelon has reviewed the "C" list of jeopardy codes located in the Qwest IMA User Guide, and there is no customer jeopardy ("C" list) that applies to this situation. As a matter of fact, this situation does not present a jeopardy situation at all because the order is not in "jeopardy."

Expected Deliverable

Develop, document, and train a process to manage requests for basic install circuits in situations in which the CLEC is ready on the due date (before 5pm), although perhaps not at the first time that Qwest chooses to call.. Cease using a CNR jeopardy for the situation described above, because the customer IS ready on the due date (as the Qwest basic install definition is from 8 AM to 5 PM local time).


Status History

07/23/03 - CR Submitted

07/24/03 - CR Acknowledged

07/31/03 - Held Clarification Meeting

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/26/03 - Had conversation with Bonnie Johnson and would be ok with Eschelon to hold jep until 6 p.m. Mountain time

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/06/03 - Held Ad Hoc Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/05/03 - Qwest issued PROS.12.05.03.F.01131.ProvisioningV29 proposed effective date 1/19/04

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/02/04 - Qwest issued PROS.01.02.04.F.01222.FNL_ProvisioningV29 CMP FINAL NOTICE on Provisioning and Installation Overview V29.0 effective 1/19/04

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

02/18/04 February CMP Meeting Jill Martain with Qwest said the final notice was sent on 1/2/04 and the PCAT was effective 1/19/04. Stephanie Prull asked if Qwest is holding the jep statuses in IMA. Jill said that a system CR would be required to hold jep statuses from the inquiry functionality, only the jeopardy notices were being held in IMA. This CR will be moved to Completed status.

01/21/04 January CMP Meeting Jill Martain with Qwest said that the final notice was sent 1/2/04 and was effective 1/19/04. It was agreed that this CR would move to CLEC Test status. 12/17/03 December CMP Meeting Jill Martain with Qwest said she would like to talk about this CR & PC081403-1 which are in Development (see PC081403-1 for more information). Additional information on jepoardies was discussed in the CLEC ad hoc meeting. Bonnie Johnson with Eschelon said she had received Susan’s note this morning and this is not tied to the 6 p.m. jeopardies. This CR will remain in Development status.

11/19/03 November CMP Meeting Jill Martain with Qwest said that the CR is in progress and expects deployment in December 2003. This CR will remain in Development status.

Thu 10/23/03 3:06 PM From: Bonnie Johnson to: Linda Sanchez-Steinke Subject: RE: PC072303-1 Jeopardies Hi Linda, I have received no feedback. I perceive that to mean we are OK.

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724

Thu 10/23/03 2:18 PM From: Linda Sanchez-Steinke To: Bonnie Johnson Subject: PC072303-1 Jeopardies Hi Bonnie -

I wanted to follow up with you and find out if any CLECs provided feedback to you about holding jeopardies (those listed in the supplemental information included in the CR) until 6 p.m. Mountain time.

Would you let me know if you have received feedback from companies that did not want to move forward with the proposal?

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-965-0972

10/15/03 October CMP Meeting Phyllis Sunins with Qwest said that we held an ad hoc meeting last week and at the meeting the CLECs agreed to hold jeopardy notifications until 6 p.m. Mountain time. Qwest expects to implement this change in December 2003. Jill Martain will open a Qwest initiated CR to review the jeopardy process. Bonnie Johnson with Eschelon said that at the ad hoc meeting CLECs were given time to review the list of jeopardy codes and hasn’t received negative feedback from any CLECs. Bonnie will call Linda Sanchez-Steinke next week if she does receive feedback from CLECs that do not want jeopardy notification held until 6 p.m. Mountain time. Phyllis added that she is doing a study of August jeopardy data. Liz Balvin with MCI needs additional definition of C31 and C34 jeopardy codes. Phyllis said that Eschelon had asked for additional documentation around jeopardy codes and the documentation will be available at the end of the month. Liz said she would wait for the documentation to be distributed and will submit comments. This CR will remain in Development status.

Ad Hoc Meeting Minutes PC072303-1 October 6, 2003 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:30 a.m. Mountain Time

List of Attendees: Lori Mendoza - Allegiance Donna Osborne-Miller - AT&T Regina Mosley - AT&T Phyllis Burt - AT&T Ann Adkisson - AT&T Carla Pardee - AT&T Julie Pikar - U S Link Jen Arnold - U S Link Kim Isaacs - Eschelon Bonnie Johnson - Eschelon Jeanne Whisenant - Qwest Lori Dalton - Qwest Dave Hahn - Qwest Jill Martain - Qwest Phyllis Sunins - Qwest Deny Toye - Qwest Russ Urevig - Qwest Linda Sanchez-Steinke - Qwest

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss CR PC072303-1 and synergies between PC081403-1.

Jill Martain with Qwest explained the attachment to the notification for the ad hoc meeting is a list of jeopardy types, other than "C" type jeopardies, that Qwest proposes be sent at 6 p.m. Mountain time. Jill further explained that the proposal eliminates sending jeopardy notifications for situation that are identified early in the day but later resolved by Qwest on the same date. Bonnie Johnson with Eschelon said there were a lot of duplicate jeopardies for weather / work force and asked for further explanation. Jill explained that Qwest tracks internally the jeopardies by work group and the work groups are identified by the letter codes. Deny Toye with Qwest said that the "B" jeps are central office and "C" jeps are customer jeps.

Jill asked if it would cause a problem to send the jeopardies listed on the spreadsheet at 6 p.m. Mountain time. Bonnie said that CLECs would be left hanging and it would be too late to contact the customer if didn’t receive them until 6 p.m. Deny said that when Qwest gets to the due date that we make a call and the CLEC would have been notified via telephone call if placing the order in jeopardy. Bonnie said that helped to know that CLECs will get a call on the due date if the order is in jeopardy and then they can call customers. Deny will check all products that Qwest makes a telephone call on due date if the order is placed in jeopardy. Jill said that she will submit an additional CR to re-address the jeopardy process.

Kim Isaacs said that she has submitted a documentation request asking for additional explanation of jeopardy meaning.

Lori Mendoza will get input from Allegiance, Donna Osborne-Miller will get input from AT&T, Bonnie said she would send something out to the community asking for additional input. Linda asked if there were any additional questions. No questions were asked and Linda said that we would discuss this CR at the October CMP meeting.

09/17/03 September CMP Meeting Jill Martain with Qwest said that Qwest accepts this CR and will be making changes to a backend system to hold CNR jeopardies until 6 p.m. Mountain time. The targeted date for implementation is December 2003. Jill explained that Qwest would like to expand holding all jeopardies sent mechanically except with unbundled loop before FOC, for conditioning and facility reasons. Bonnie Johnson with Eschelon said she was not sure if they could be acting on those and if they would agree to hold until 6 p.m. There will be an ad hoc meeting scheduled and Jill will provide a list of jeps to be considered with the notification. This CR was moved to Development status.

08/20/03 - August CMP Meeting Bonnie Johnson with Eschelon presented this CR. Bonnie explained that Eschelon is asking that the circuit not be put into CNR status until 5 p.m. local time on the due date. Lori Mendoza with Allegiance supports this CR. Lori asked if Bonnie included in the CR the situation when the customer is not able to stay late when there is a Qwest problem. Bonnie said that in those situations, it would not be appropriate to put the order in CNR status. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

8:15 a.m. (MDT) / Thursday, July 31, 2003

1-877-572-8687 3393947# PC072303-1 Customer Not Ready ("CNR") jeopardy notice should not be sent by Qwest to CLECs before 5 PM local time on the due date (for basic install)

Name/Company: Bonnie Johnson, Eschelon Kim Isaacs, Eschelon Stephanie Prull, McLeod Liz Balvin, MCI Sharon Van Meter, AT&T Mike Zulevic, Covad Denny Graham, Qwest Jeanne Whisenant, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. Review Requested (Description of) Change Linda read the description of change from the CR submitted by Eschelon; Customer Not Ready ("CNR") jeopardy notice should not be sent by Qwest to CLECs before 5 PM local time on the due date (for basic install). If a CLEC is not ready to test at the time Qwest calls on the due date, the CLEC has until 5 PM to call Qwest and test and accept the circuit. Qwest should not place the Local Service Request ("LSR") in a customer not ready jeopardy status, because the customer is ready within the required time frame.

Qwest does not provide CLECs with a specified time on the due date when testing and acceptance will take place. Testing and acceptance may occur any time before 5 pm local time. As long as the CLEC is ready to test and accept the circuit before 5pm on the due date, therefore, the customer is ready on the due date. Nonetheless, Qwest places a "CNR" jeopardy on an LSR if Qwest calls a CLEC to test and accept the circuit on the due date and the CLEC is not ready to test and accept the circuit at the time Qwest calls. Even if the CLEC communicates to Qwest that it will call Qwest back on the due date and before 5 PM local time, Qwest places the request in a CNR jeopardy status. Qwest should not use the CNR jeopardy notice for this situation. CNR is not a valid jeopardy code, because the CLEC is ready before 5pm (i.e., on the due date).. By incorrectly using the CNR jeopardy for this situation, , Qwest forces CLECs to manage CNR jeopardy notices that have no validity. Qwest is causing CLECs additional work in the CLECs workflow process for no valid reason. Qwest should change the process on issuing CNR jeopardy for this situation. Eschelon has reviewed the "C" list of jeopardy codes located in the Qwest IMA User Guide, and there is no customer jeopardy ("C" list) that applies to this situation. As a matter of fact, this situation does not present a jeopardy situation at all because the order is not in "jeopardy."

Jeanne Whisenant with Qwest asked if this CR was for all orders sent through IMA. Bonnie Johnson with Eschelon answered yes this is for LSRs sent through IMA where the CNR process applies, and said Eschelon issues private line and LIS trunking orders on ASR. Jeanne explained the ASR process is manual and that CNR letters are sent by the SDC on due date and no longer than 2 business days after the due date. Bonnie said this CR doesn’t apply to orders submitted via ASR because it is not an automated process.

Liz Balvin with MCI said she supports this change request, and said that MCI may not meet the time when Qwest initially calls but will get back to Qwest by the end of the day.

Sharon Van Meter with AT&T also supports this CR.

Confirm Areas & Products Impacted The area of this Change Request impacts orders submitted via LSR where CNR process applies.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation Develop a process where the jeopardy notice will not be sent by Qwest before 5 p.m. local time on the due date.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Eschelon will present this CR at the August CMP meeting.


CenturyLink Response

September 9, 2003

DRAFT RESPONSE

For Review by the CLEC Community and Discussion at the September 17, 2003 CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response - PC072303-1 Customer Not Ready ("CNR") jeopardy notice should not be sent by Qwest to CLECs before 5 PM local time on the due date (for basic install)."

QWEST Response:

Qwest accepts this change requested by Eschelon, however, a back end system change will be required to hold the CNR jeopardy notifications until 6 PM Mountain time. This system change is due to the fact that Qwest put mechanization in place previously to provide timely jeopardy notification to our CLEC community.

Qwest has targeted this process change to take place in December 2003 and will provide notification to the CLEC Community.

Sincerely,

Jill Martain Manager Process Management


Open Product/Process CR PC063003-1CM Detail

 
Title: CMP CR status of "reactivate" added to statuses available for a CR.
CR Number Current Status
Date
Area Impacted Products Impacted

PC063003-1CM Completed
10/27/2003
CMP Process
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Sanchez-Steinke, Linda
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

A CLEC agrees to close a CR in good faith with the belief that the changes implemented in the CR satisfied the intent and request of the CR. A CLEC may determine that the requested changes in the CR were not satisfied and there is not compliance to the new process issue. When this occurs, there is no process that allows a CLEC to request that a CR be reactivated. A CLECs only alternative is to submit a new CR asking for the same thing that was originally requested. For example; Eschelon submitted a CR in April of 2001 requesting accurate loss and completion reports. Several steps were taken by Qwest to meet that goal. In May of 2002, after the CR had been closed, it was discovered that the loss report contained both internal and external losses. The original CR specifically requested that the loss report contain only those losses where the customer changed to another Local Service Provider and not losses that resulted from a CLECs LSR activity. Then, in early 2003, Eschelon communicated to Qwest that there were losses that were not appearing on the loss report. Eschelon recently requested that the original CR be reactivated until the CLECs were receiving an accurate loss report. Qwest told Eschelon there was no provision in the CMP process that allowed for the reactivation of a CR. Qwest often pressures CLECs to close CRs. If an issue is not discovered in the “CLEC test” phase, the CLEC is left with no option of reactivating a CR. There are occasions where a problem is not identified in the CLEC test phase and the problem is not a compliance to new process issue (though the CLEC test phase should include Qwest training and a reasonable expectation of compliance to the new process). If a CLEC closes a CR in good faith, and there is reasonable cause to reactivate the CR, the status of reactivate should be available to a CLEC.

Eschelon asks that the following language be added to the end of Section 5.8 (Change Request Status Codes) in the CMP Document:

? Re-Activated - The CR receives a Re-Activated status when a previously closed CR has been requested to be re-opened. Reasons include the CR was not implemented correctly and/or not completely as requested with further test results.

NOTE: It may be Qwest or another CLEC that determines the CR was not correctly implemented. In addition, “include” would mean includes but not limited to...there may be other reasons.

Expected Deliverable:

Qwest will add reactivate status to the list of CMP CR statuses. A CLEC should not have to open a new CR or action item to fulfil the request of the original CR and the issue is not compliance to the new process.


Status History

06/30/03 - CR Received

07/01/03 - CR Acknowledged

07/16/03 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/17/03 - Received revised proposed changes to CMP document, will replace original proposed changes

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/15/03 - Qwest sent meeting notification CMPR.09.15.03.F.01567.AdHocMtg_CR_Reactivate, meeting date 9/22/03

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/22/03 - Held Ad Hoc Meeting to discuss proposed language - Meeting minutes will be posted to this CR's Project Meetings section.

09/26/03 - Rec'd e-mail from Bonnie Johnson, question whether Qwest would re-activate CRs examples and Red-line Document

09/29/03 - Sent e-mail to Bonnie Johnson, did not receive Red-line document

10/13/03 - Qwest sent notification CMPR.10.13.03.F.01589.AdHocMtg to discuss language 10/20/03

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/17/03 - Qwest sent notification CMPR.10.17.03.F.01594.AdHocMeeting, cancelled 10/20/03 meeting to discuss language

10/20/03 - Qwest sent notification CMPR.10.20.03.F.01595.AdHocMtgVoteReq, vote on language 10/27/03

10/27/03 - Held Ad Hoc Meeting to vote on Eschelon proposed language - Meeting minutes will be posted to this CR's Project Meetings section.

11/03/03 - Qwest issued CMPR.11.03.03.F.01007.VoteDisposition, Vote Disposition Notification


Project Meetings

Ad Hoc Meeting Minutes PC063003-1CM CMP CR status of "reactivate" added to statuses available for a CR CMP Product & Process October 27, 2003 1-877-572-8687, Conference ID 3393947# 10:30 a.m. - 11:00 a.m. Mountain Time

PURPOSE

At the October CMP Meeting, participants agreed to hold a conference call to conduct voting on the proposed changes to the CMP Document, CR PC063003-1CM, “CMP CR status of "reactivate" added to statuses available for a CR”. The following is the write-up of the discussion.

List of Attendees: Lori Mendoza, Allegiance Julie Pikar, U S Link Liz Balvin, MCI Bonnie Johnson, Eschelon Kim Issaacs, Eschelon Tom Hyde, Cbeyond Communications Sue Stott, Qwest Lynn Notarianni, Qwest Linda Sanchez-Steinke, Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to vote on CMP CR PC063003-1CM. Linda explained that quorum is 6 and we have established quorum with 7 attendees. Linda asked if everyone was clear on what we were voting on and asked if anyone is uncomfortable voting out loud that they could e-mail their vote and would arrange for cmpcr@qwest.com to be monitored to receive the vote. The following votes were provided by meeting participants: Eschelon voted yes Allegiance voted yes MCI voted yes U S Link voted yes Cbeyond voted yes

Linda read the e-mail votes: AT&T voted yes Qwest voted no

Linda said the result of the vote is 6 - yes and 1 - no and said the standard for a vote on changing the CMP document is a unanimous vote, and because this vote was not unanimous, the changes will not be incorporated into the CMP. Linda said she would provide notification of the vote disposition.

Lynn Notarianni asked if there had been discussions about the language change. Bonnie Johnson said that Qwest wants to be the driver of the decision to reactivate a CR. The CLECs had proposed that a re-activated CR be voted on, and with a two-thirds majority, the CR would be re-activated. There is no difference between a unanimous vote and Qwest determining if the CR should be re-activated. We were going to have another ad hoc call for discussion and that was cancelled so that we could vote on the CLEC proposed language.

Liz Balvin said that this will cause the CLECs to leave CRs open when they can’t test. Bonnie said that we have already started to see that happening.

Linda asked if there were any questions. No questions were asked.

10/15/03 October CMP Meeting Linda Sanchez-Steinke with Qwest said she had received Bonnie Johnson’s two e-mails stating that Eschelon would like to have a vote taken on the Eschelon proposed language. Bonnie said the 10/20/03 ad hoc meeting should be cancelled and asked that a meeting to vote be scheduled. Bonnie said that Qwest’s proposed language was not acceptable and the wording requiring "unanimous vote" is the same as "Qwest determining" if the deliverable was not met. Linda said that possible dates for the vote meeting are 10/24 p.m. and 10/27. Linda will e-mail Bonnie with possible dates and appropriate notification for the vote will be sent.

Mon 10/13/03 4:14 PM From; Bonnie Johnson Eschelon To; Linda Sanchez-Steinke Qwest Subject; FW: Change Manangement: Meeitng Agenda & Material: GN: CMP Ad Hoc Meeting, Effective Immediately

Linda, Will we be voting on my version at this meeting. I really don't want to spend anymore time passing this document back and forth. I will not agree to Qwest's new language so I requested we vote on my last version.

Please let me know.

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724

Mon 10/13/03 5:55 AM From; Bonnie Johnson Eschelon To; Linda Sanchez-Steinke Qwest Subject; Change Management Notice: Meetings: GN: CMP-Ad Hoc Mtg on Rea ctivate CR: Effective Immedaitely

Linda, I will not accept Qwest's proposed language to a unanimous vote. With a unanimous vote the language of "Qwest determines" might as well remain in the document. We can move directly to a vote on my last proposed language so Qwest can vote no and have the final decision....again.

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724

Sent Wed 10/8/03 12:40 PM From; Linda Sanchez-Steinke Qwest To; Bonnie Johnson Eschelon Subject; RE: Change Management Notice: Meetings: GN: CMP-Ad Hoc Mtg on Rea ctivate CR: Effective Immedaitely

Hi Bonnie -

In response to your examples of CRs, on the first example, CR 5522887, while this would require a clarification meeting to clearly identify what would be required to close the request, Qwest would probably agree to re-activate this CR.

The second example, SCR060702-01, Qwest would probably disagree to re-activate this CR because there are other Systems CMP CRs that have been opened to enhance this functionality.

The third example, SCR032602-1, is in CLEC test and wouldn’t be eligible for re-activation since it is not closed.

We would like to arrange another ad hoc meeting to discuss additional changes made to the re-activate lanaguage and we're looking at 10/20 9:30-10:30 Mountain, let me know if that would work for you.

Thank you

Linda Sanchez-Steinke 303-965-0972

Date: Mon 9/29/03 10:11 AM From; Johnson, Bonnie J. [bjjohnson@eschelon.com] To: Linda Sanchez-Steinke (E-mail) Subject; RE: Change Management Notice: Meetings: GN: CMP-Ad Hoc Mtg on Reactivate CR: Effective Immedaitely

Hi Linda, Here you are!

Sorry!

Date: Mon 9/29/03 9:05 AM From: Sanchez Steinke, Linda To: 'Johnson, Bonnie J.' Subject; RE: Change Management Notice: Meetings: GN: CMP-Ad Hoc Mtg on Reactivate CR: Effective Immedaitely

Hi Bonnie -

I received your e-mail and read through the attachment of the CMP document and do not see any red-line from you. Did you track the changes made? Maybe you can give me a call.

Linda Sanchez-Steinke CRPM Qwest 303-965-0972

Date: Fri 9/26/03 4:10 PM From; Johnson, Bonnie J. [bjjohnson@eschelon.com] To; Linda Sanchez-Steinke (E-mail) cc; Subject: FW: Change Management Notice: Meetings: GN: CMP-Ad Hoc Mtg on Reactivate CR: Effective Immedaitely

Linda, I have red lined the attached document with my changes. I am also adding the examples discussed on our call this week. I would like Qwest to communicate Qwest's position on what response Qwest would give if a CLEC requested the CR be reactivated. I am certain there are other examples for Eschelon and other CLECs. I will send more as I get them.

5522887 CLECs need clear loss information, particularly with respect to resale customers. If loss information is not communicated effectively, two providers may bill one customer at the same time. To prevent such problems and ensure accuracy, Qwest should provide loss and completion information in a more organized, clear manner. Currently, Qwest includes all activity on a CLEC account that has outward action of a line or loop on a service order. For example, a migration from resale to loops appears as a loss, even though the customer has not changed providers. A loss should be limited to lines leaving the CLEC to go to another provider. The loss report should only reflect information of those customers that have changed to a different local service provider. The completion report should include order activity initiated by the CLEC, regardless of the activity type requested. Eschelon requested this CR be reactivated and Qwest responded no. The request was very clear and to date Eschelon is not receiving accurate loss reports.

SCR060702-01 Z-Tel is requesting the ability to migrate customers as specified without having to list changes to the customer's current feature set. For example, when placing a customer migration order with Qwest, we are required to list the old line class of service with a feature activity code of 'change from', and list the new line class of service with an activity code of 'change to'. In addition, we must list all change and removes for all of the existing features on the account and adds for all of the new features that do not currently exist on the account. This practice is commonly referred to in the industry as a migrate as is with changes, not a migrate as specified. Z-Tel needs the ability to convert customers as we specify without having to list and map changes, adds or removes. SBC, Verizon, and BellSouth all provide this pure migrate as specified capability for UNE-P customers and we are asking Qwest to do the same. Expected Deliverable: The ability to truly migrate a customer as specified. Qwest implemented this CR but does not apply to hunting, blocks and listings. CR not implemented as requested.

SCR032602-1 Currently when submitting a request in IMA using the request type of "P" for Centrex, the CSR is not recapped in IMA. As a result, the LSR is much more manually intensive to complete. In addition, there is a greater chance the CLEC could submit the LSR and receive a reject stating "all lines and/or services were not addressed on the LSR". This causes delays in processing LSR's and additional work for Qwest SDC's who manually type the service orders. This CR is still in CLEC test because tickets are open...however, the implementation of this CR was not fulfilled. It does not hsave the same functionality as the recap function for other products. If this were closed and Eschelon asked to have it reactivated...what would Qwest's response be?

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

Ad Hoc Meeting Minutes PC063003-1CM "CMP CR status of "reactivate" added to statuses available for a CR" CMP Product & Process September 22, 2003 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:30 a.m. Mountain Time

PURPOSE

At the September CMP Meeting, participants agreed to hold a conference call to discuss Eschelon submitted CR PC063003-1CM, CMP CR status of "reactivate" added to statuses available for a CR CMP document. The following is the write-up of the discussion.

List of Attendees: Donna Osborne-Miller - AT&T Bonnie Johnson - Eschelon Kim Isaacs - Eschelon Connie Winston - Qwest Beth Foster - Qwest Sue Stott - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss CR PC063003-1CM. Qwest provided proposed language changes to the CMP document along with the meeting notification.

Linda asked Bonnie for feedback on the proposed CMP document changes. Linda read the proposed change made to Section 5.1.4, addition of Section 5.1.4.1 Reactivation Requests. Bonnie asked how Qwest would care for CRs that a CLEC submits if the CLEC is not on the same version of EDI and how the process of opening a re-activated CR would work. Linda said that RA would be added as a suffix to the original CR number. Bonnie stated that she did not like the idea of Qwest making the determination as to whether or not a CR would be reactivated, she noted that she would like that to be more a collaborative effort between Qwest and the CLECs. Bonnie asked if Qwest determines the requested deliverable is within the scope of the original CR, then, what will the process be if the CLECs disagree with Qwest. Linda said that the process would follow the CMP document.

Bonnie said that she thought Qwest would provide additional wording on how Qwest will care for CR’s when a CLEC is on an EDI version, then cut to the next version of EDI, and what was changed in the CR doesn’t work. Bonnie noted that she had understood that Qwest was going to provide an additional status for such CRs. Linda asked if deferred status would be appropriate for those CRs where the CLEC is on a different version of EDI. Bonnie agreed to review the language around deferred status and will determine if deferred would be the correct status.

Beth Foster with Qwest said that she was unaware of Qwest offering another status for CRs. Beth stated that Qwest’s proposed language would allow for a systems CR to be closed upon implementation and re-activated once the CLEC cuts to the next version of the release. Beth reviewed the following example: If in systems we close an IMA CR with the implementation of 13.0 and then the CLEC cuts over to 14.0, the CLEC could then request a re-activated status if they discovered some problems with their CR once they cut to 14.0. If it was determined that the CR was in fact, not implemented per the expected deliverables of the CR, then the CR would be re-activated. The re-activated CR would then be handled using the production support guidelines in section 12.0 of the CMP document. The re-activated CR would be discussed at the monthly systems CMP meetings in conjunction with the CRs that are in the status of ‘CLEC-Test’, where it would remain open until the production support process resolved the open issue.

Bonnie noted that she would like to have a more collaborative decision in determining whether a CR is re-activated and will work with the other CLECs and draft language. Donna Osborne-Miller with AT&T said she also wanted a more collaborative approach and is concerned that Qwest alone would determine if the CR is re-activated.

Bonnie agreed to make changes to the red-line CMP document for Qwest to review and provide a few examples. Qwest will schedule another ad hoc meeting to discuss once they receive the red-lined language from Eschelon.

09/17/03 September CMP Meeting Linda Sanchez-Steinke with Qwest said there would be an ad hoc meeting on 9/22/03 to discuss this CR.

08/20/03 August CMP Meeting Bonnie Johnson with Eschelon explained if a CR was moved into re-activate status it would be because the original CR had not been fulfilled. Judy Schultz with Qwest explained when the CR goes through CLEC test, and then, if it needs to be reactivated, we would need to explain what the specific problem is that initiated reactivation. The CR number could have an RA suffix and note the date closed and the date re-opened. In addition we would need some communication about what piece of the CR was not addressed and bring the information forward for the CLEC Community at the CMP meeting. Bonnie explained that on the Systems side when a CR is implemented and the CLEC is not on the same version of EDI, they would not want to be forced to close the CR. Bonnie suggested that we could do another type of status. Judy said she would give that some thought and clarified Bonnie’s concern about EDI. Judy said that she understands that if a CLEC on EDI submits a CR that is worked in higher version, the CLEC is not in a good position to close the CR. Bonnie said that she might want an additional status. Judy said that Qwest would draft language to the CLECs and set up an Ad Hoc Call to discuss the draft language.

07/16/03 July CMP Meeting Bonnie Johnson with Eschelon presented this CR which proposes changes to Section 5.8 Change Request Status Codes. Bonnie said that when closing a CR sometimes the CLEC test phase doesn’t allow enough time to identify issues or problems with the CR. Two examples were the CRs for loss and completion and migrate by TN. If the CLEC is on EDI and submits a systems change request they don’t have the ability to test until they move to that version of EDI. Compliance issues are not part of this CR and the only situation that the re-activate status would be used if for the deliverable of the CR hasn’t been completed. Judy Schultz with Qwest asked about CR numbering assignment. Bonnie suggested we keep the original CR number. Judy has a concern that the CR would look like it had been open for a long time. Donna Osborne-Miller asked if the CR number could be followed by RA. Liz suggested that the clock start when re-activated. Bonnie would like to work collectively to resolve and if this CR is not implemented then they would leave CRs open longer and not be pushed to close them. Judy said she appreciates Bonnie testing and closing CRs promptly and perhaps if this change is implemented that the CR could be earmarked with the date it was re-activated. This CR will be moved to presented status.

CLEC Change Request Clarification Meeting

8:00 a.m. (MDT) / Friday, July 11, 2003

1-877-562-8687 3393947# PC063003-1CM

Name/Company: Bonnie Johnson, Eschelon Stephanie Prull, McLeod Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Eschelon’s CR requests that the CMP Document, Section 5.8 be changed to add “Re-Activated” as a status code for change requests. Bonnie Johnson with Eschelon said that she is trying to add “Re-activated” as an additional status for situations where a change request wasn’t implemented or honored. An example would be a CR was submitted, and worked, and then closed after CLEC test. Then after CLEC Test, issues or problems that hadn’t been identified during CLEC Test are identified. The change request is not referring to change request compliance or training issues. Bonnie provided an additional example of a change request submitted by Eschelon to convert by TN, part of the 12.0 release. The end state of the LSR is what Eschelon wanted in the change request. After the CR was completed, Eschelon found it did not apply to blocking, hunting or listing. With the lag time with EDI, CLEC’s weren’t on the same version and didn’t understand the impact until they had gone to the 12.0 version. Stephanie Prull added that McLeod usually skips a release for the GUI or EDI and McLeod wouldn’t be aware of a problem until they are in the same release. An additional example Bonnie provided was a CR Eschelon submitted for loss and completion reports. The options are to open a new CR or leave the existing CR open longer. Qwest is persistent in closing CRs after CLEC test and CLEC test may not provide enough time to determine if there are problems. Stephanie asked if there would be a limit on how long the CR was in completed status and be changed to “Re-Activated” status. Bonnie answered that there would be no time limit and that we may get input from Qwest and the CLEC community.

Confirm Areas & Products Impacted The area of this Change Request impacts the CMP process section 5.8

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation Change Section 5.8 to add Re-activated as a status code.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Eschelon will present this CR at the July CMP meeting.


Open Product/Process CR PC070202-2X Detail

 
Title: Time & Material Repair Charges Invoice Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC070202-2X Completed
2/18/2004
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Recker, Jim
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently Qwest leaves a "Time and Materials Invoice" with its retail customers during a repair visit when the trouble was not found in the Qwest network. Qwest does not supply anything to CLECs. This "Invoice" would assist Eschelon in reconcilling its bill. Eschelon asks Qwest to develop, document and train an adhered to process to supply CLECs with this same "Invoice" or something similar, with the same detail, that will state the charges that Qwest plans to bill at the time of the repair visit. The "Invoice" should contain the Qwest repair ticket number, the number or circuit ID which was reported in trouble, the customer's name and address, the Qwest technicians name and telephone number, the date, the USOCs that Qwest will bill and the quantity of each USOC.

Additional Information:

A process to supply CLECs with an "Invoice" of repair charges at the time of the repair visit.


Status History

07/02/02 - CR Submitted

07/02/02 - CR Acknowledged

07/03/02 - CR Posted to Web

07/09/02 - Clarification Meeting Scheduled

07/10/02 - Clarification Meeting Held

07/12/02 - CLEC Provided information, meeting minutes sent to Eschelon

07/17/02 - CMP Meeting - Status changed to clarification

08/14/02 - Draft Response issued

08/19/02 - Issued Mailout Notification to CKECs confirming the Synergy Meeting for Multiple Tickets and Billing CRs scheduled for 8/27/02 2:00 p.m.

08/21/02 - CMP Meeting - Qwest presented it draft response dated 8/13/03. This CR will move to Evaluation status and will be discussed at the Synergy Meeting.

08/28/02 - Crossover CR issued SCR070202-1X

04/07/03 - Crossover CR issued PC070202-2X. Development work is underway and scheduled for completion near the end of June.

4/16/03 - April CMP Meeting minutes will be posted to the database

5/21/03 - May CMP Meeting Minutes will be posted to the database

6/18/03 - June CMP Meeting Minutes will be posted to the database

7/16/03 - July CMP Meeting Minutes will be posted to the data base

8/2003 - August CMP Meeting Minutes will be posted to the data base

9/9/03 - Followed up with Kathy Stichter and she replied the system was working fine

9/17/03 - Sep CMP meeting notes will be posted to the database

10/17/03 - Oct CMP meeting minutes will be posted to the database

10/20/03 - Notification of Ad Hoc Meeting distributed - meeting date 10-28

10/28/03 - Held Ad Hoc meeting to review user guide and system

11/19/03 - Nov CMP meeting mintues will be posted to the database

12/10/03 - Checked with Kathy Stitcher to find out if she is having any new issues. Kathy confirmed she has not identified any new issues.

12/17/03 - Dec CMP meeting notes will be posted to the database

12/16/03 - PROS.12.16.03.F.01170.MainRepairInvoiceTool - Level 1 user guide update

1/21/04 - Jan CMP meeting minutes will be posted to the database

2/2/04 - Met with Kathy Stitcher and reviewed user guide updates - still checking on update time for ND

2/10/04 - Sent email to Kathy explaining the time period for updates is less for ND, but approximately two weeks covers both ND/D - Kathy emailed back that it is okay to publish the user guide with that information

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section


Project Meetings

February 18, 2004 CMP Meeting Jim Recker – Qwest advised that we made changes to the User Guide to help clarify and correct information regarding frequency of ticket updates and circuit id entry. We reviewed the Guide with Kathy Stitcher – Eschelon before we published it. Kathy agreed it met her needs and approved the changes. Kathy Stitcher – Eschelon advised she is fine with the changes and it is okay to close this CR. Kathy thanked Qwest for making the changes. Stephan Calhoun – Cbeyond asked if this tool is specific to a certain product. Jim Recker – Qwest advised no, it contains design and non design repair tickets. Kathy Stitcher – Eschelon advised this tool give CLECs a heads up on what will be billed. We use it to look at the invoice and CLEC repair system and compare charges. This CR will move to Completed status

January 21, 2004 CMP Meeting Jim Recker – Qwest advised that we reviewed the user guide and we are in the process of scheduling the user guide updates. The user guide was not correct and it is being corrected. This CR will remain in CLEC Test Status.

December 17, 2003 CMP Meeting Minutes Jamal Boudhaouia – Qwest advised the notice for the User Guide updates went out December 16, 2003. The document identified the three changes that Kathy Stitcher requested. Kathy advised she would review the notice and User Guide during the call and report if there are any issues. Kathy reviewed the User Guide and advised that the tickets are not updated as the User Guide specifies. Tickets are sent to the invoice tool 2 weeks after the ticket is closed and it shows up in the tool 2 days after that. Kathy also said the Circuit id search (appendix A) is not accurate either. The appendix says to enter the circuit id exactly the way it is in our system. On the serial number you have to have 10 characters. You have the / and 10 characters. If you have 6-digit serial number you have to enter 4 spaces. Kathy said we need to say this field is not optional or change the serial number. Jamal advised he would check into the changes that were made and provide status next month.

November 19, 2003 CMP Meeting Minutes Craig Suellentrop – Qwest advised that we had a CLEC review meeting and looked at the tool and user guide. The circuit id search was completed successfully. The User Guide updates are underway. The User Guide updates will include information about the circuit id search and also that Internet Explorer is the required browser. Kathy Stitcher – Eschelon advised tickets should be updated within 2 weeks. Kathy advised she reviewed the tickets on 11-18 and the most current ticket was dated 10-31, so the update is taking a little over 2 weeks. . Kathy stated that Qwest should correct the language in the user guide to reflect that design tickets will not show for 2 weeks and 2 days.

CLEC Ad Hoc meeting October 28, 2003 PC070202-2X Repair Invoice Tool

In attendance: Kim Issacs – Eschelon Alice Mathew – Qwest Dan Busetti – Qwest Craig Suellentrop – Qwest Kathy Stitcher – Eschelon Sheldon Anderson – Qwest Joe Blepp – Bulls Eye Telecom Cindy Macy – Qwest

Cindy introduced the team members and explained the plan is to review the user guide and also go through the tool for the people that have CEMR user ids. Dan Busetti – Qwest reviewed the user guide and helped the users log on.

Kathy Stitcher – Eschelon asked if CEMR is down and we call the ticket in, opposed to entering it directly to CEMR, would it be in the Repair Invoice Tool? Dan advised no, it must be entered into CEMR directly,

Dan reviewed the Design and Non Design screens with the team. Dan explained how to export data to a report. Kathy advised she has done this function and it works fine. Dan explained that if you need to print the report you must export the data to excel first.

Kathy Stitcher – Eschelon asked if users are supposed to have two different log in ids. Dan advised you can use your regular CEMR log in id.

Kathy asked if users are supposed to have a different digital certificate, as she gets ‘page not found’? Dan advised no, try to redownload the digital certificate or reload the browser. Kathy also said she experiences trouble when trying to open the application, it seems as if it times out often. Dan Busetti advised he has let his application sit more than 15 minutes and does not have time out issues. Dan advised Internet Explorer is the browser that should be used as this may be causing some problems. Kathy requested in a later voice message to also update the user guide to advise that Internet Explorer is the ‘require’ browser, not the suggested browser, as many functions do not work with the Netscape browser.

Cindy suggested that if problems are found to be sure and call them into the Wholesale Help Desk. Bonnie advised that is not always the best route to handle problems. Discussion continued and it was agreed that a user review/help session is sometimes what is needed, opposed to opening trouble tickets. Cindy agreed that we should be more aware of scheduling these type of reviews on new systems.

Kathy Stitcher advised she has trouble with the circuit id format. She takes the format from the Completion Report and it is different that what this tool accepts. Dan reviewed the correct format. Kathy asked if this is in the user guide? Dan advised no, and agreed to get the user guide updated. Kathy advised she is able to access tickets with circuit id now.

Kathy advised she is only able to get invoices from the 13th, and today is the 28th. Dan confirmed there is a 2-week lag in data.

The team agreed the issues were addressed.

10/15/03 October CMP Meeting Craig Suellentrop – Qwest reported that there are not any open trouble reports on this system and he is not aware of any current issues. Craig requested to close this CR. Kathy Stitcher – Eschelon advised she is having trouble getting a match in the system using a circuit number. Kathy is not aware of what the correct format is for a circuit id. Qwest advised to use the circuit id as identified on the FOC. Kathy Stitcher – Eschelon advised the date range selection works but then you have to page through data to find the invoice you want. Cindy Macy – Qwest offered to schedule a meeting to review the system, user guide and address questions about how to use the system. A CLEC Ad Hoc meeting will be scheduled. Jen Arnold – US Link would like to attend the call. This CR will remain in CLEC Test Status. Kathy Stichter – Eschelon advised that in an earlier conversation Qwest advised that the CKT ID may be formatted as it appears in WFA and that since Eschelon does not have access to WFA Kathy would not know what the formatting is.

9/17/03 September CMP Meeting Craig Suellentrop-Qwest advised this CR was moved to CLEC Test last month and that he proposed we move this CR to Close status. Kathy Stitcher advised she went to look for tickets last week and was unable to find them in the system. Kathy explained she uses the Completion Report and then she views the accounts in RTCI. The tickets she was looking for were not in the system. Dan Busetti-Qwest advised they are aware of this issue and still working on it. Kathy opened a trouble report on September 12, ticket number 301456. Craig advised he will follow up with the help desk and we will leave this CR in CLEC Test status.

8/20/03 CMP Meeting Craig Suellentrop-Qwest advised the problem that Kathy reported last month was determined to be a problem with how the system is doing the ‘ownership check’. A work around is in place and the issue is scheduled to be fixed by September 11. Kathy Stitcher-Eschelon advised that Diana Ward and Dan Busetti were very helpful in getting this figured out. Kathy advised she is now experiencing a different problem. When she is in the tool it gives her ‘This page is not available’ message. She has to back out and this basically logs her off. She then has to start the process all over again and it works. This has happened with multiple functions, such as download and adding date ranges. Craig agreed he would report this to the IT team. Cindy Macy-Qwest advised that Kathy should also contact the Wholesale Help Desk and put in a trouble ticket. This way the correct process is being followed. Kathy agreed to contact the WHD.

7/16/03 July CMP Meeting Minutes Craig Suelletrop-Qwest advised this was deployed the end of June. Kathy Stitcher-Eschelon advised she tried to log on yesterday and she did not get the digital certificate login screen. She did get access to the application but there was not any data for her to review. Craig advised he will check on these items and get back to Kathy. Craig will check with the development team. This CR will stay in CLEC Test.

06/18/03 June CMP Meeting Minutes Craig – Qwest advised we responded to comments last week. Cindy – Qwest asked if we could move this to CLEC Test. Bonnie-Eschelon advised it should stay in Development until the process implements.

05/21/03 May CMP Meeting Minutes Craig Suellentrop – Qwest advised this CR was crossed over from the Systems meeting. This tool is under development and planned for deployment near the end of June. Craig reviewed the screen shots that are included in the package. Bonnie Johnson – Eschelon asked if the data in this tool is loaded from the previous day or if it gets loaded 2 weeks after the order closes and when it is sent to the bill. Craig advised this data should not be used as billing data, it is prebilling data. Craig agreed he would find out how current the information is. The CLEC preference is that it would be ‘next day’ data. This CR will stay in development status.

4/16/03 April CMP Meeting

PC070202-2X Time and Material Repair Charges Invoice Process Craig Suellentrop – Qwest advised this CR was crossed over from the Systems meeting. This tool is under development and planned for deployment near the end of June. Kathy Stitcher said she has been involved in this CR. Qwest agreed we would see if any report mock ups can be provided to the CLECs. This CR will stay in development status.

3/17/03 - Meeting held to discuss Eschelon's concerns. Eschelon would not have to apply for another Digital Certificate and could existing. The ticket information would be provided on a daily basis. Lynn Stecklein/Qwest will contact Kathy Stichter on 3/24/03 when she returns from vacation and provide status and update on Eschelon's concerns and questions.

3/6/03 - Contacted Kathy Stichter/Eschelon regarding Qwest developing a Web Tool to provide this information stead of sending the ticket information via e-mail. Kathy raised three concerns: 1. Don't want to have to apply for another Digital Certificate and asked if they could use there existing certificate. 2. Eschelon would have to look at tickets pro-actively. 3. How often would web be updated with ticket information. Kathy also indicated she would be on vacation until March 24, 2003 and would not be able to provide an answer until that time. 3/3/03 - Talked with Kathy Stichter/Eschelon regarding the description of change. Per Kathy ok to revise the description to remove any reference that Qwest will provide the cost or the total cost of each USOC.. Eschelon agreed that they will identify the rates and total cost associated with each USOC.

1/16/03 CMP Systems Meeting Dan Busetti/Qwest stated that this Change Request is in design. Dan stated that we are providing an updated LOE but it is still not scheduled. Kathy Stichter/Eschelon asked if we would have the implementation date in the February Systems CMP Meeting. Connie Winston/Qwest said that we could work towards that. Kit Thomte/Qwest said that this action item would remain open.

Additional Clarification Meeting / Conference Call Time/Date: 11:00 a.m. (MDT) / Thursday, September 12, 2002 Place: TEL 877.564.8688 Conference Call-In No.: CODE: 8571927 CR No.: CLEC Change Request SCR070202-1X "Time & Material Repair Charges invoice process"

Introduction of Attendees: Kathy Stichter, Eschelon, ILEC Relations Manager Dan Busetti, Qwest, Lead IT Analyst Craig Suellentrop, Qwest, 271 Network Technical Regulatory Roszan Jarman-Konkel, Qwest, Lead QA Engineer Justin Sewell, Qwest, Software Development Engineer Peggy Esquibel-Reed, Qwest, CRPM

Meeting Purpose: This CR was crossed over from a Product & Process CR. Additional clarification is needed form a systems perspective.

Review Requested (Description of) Change: Kathy Stichter/Eschelon stated that when Qwest goes out for repair for a Retail customer, there is a Time & Material invoice left with the customer to advise what will be billed. They leave an RG25-0015; she has a copy of one that was provided to her from one of her customers. Eschelon requests the same type of information provided to them before the charges are billed. Eschelon can then review the information for possible disputes and can check into subsequent tickets. Eschelon is requesting this information prior to the bill. Once is on the bill, is very time consuming to find the charges and to determine if the charges are applicable.

Discussion: Dan Busetti/Qwest asked what type of information is she seeing on the RG25-0015. Kathy Stichter/Eschelon stated the ticket number, customer address, city, state, billing telephone number, customer name, check box for installation visit or repair visit, technician’s name, total labor hours & minutes, list of USOCs, USOC description’s, quantity, cost, and total lines. Dan Busetti/Qwest asked if Eschelon’s request was for Maintenance & Repair charges. Kathy Stichter/Eschelon responded yes, repair only for designed and non-designed services. Dan Busetti/Qwest asked what information Eschelon needs. Kathy Stichter/Eschelon stated ticket number, customer BTN or circuit ID, whatever trouble was found on, USOC, quantity, labor hours, and what is being billed for. For non-designed, it would be a TIC and designed would be dispatch & increments of time charges. Dan Busetti/Qwest asked - how soon do you want the information? Kathy Stichter/Eschelon responded - immediately. The information is left for Retail on the premise as the technician is leaving. Is thinking a daily report. Dan Busetti/Qwest - immediately or the day after? Kathy Stichter/Eschelon - yes, the day after would work. Dan Busetti/Qwest - how do you want to receive the report? Kathy Stichter/Eschelon - via Email. Dan Busetti/Qwest - someone will be looking at the form and do the compilations? Kathy Stichter/Eschelon - yes, I will be doing that. Dan Busetti/Qwest - do you want the Eschelon ticket number? Kathy Stichter/Eschelon - Ideally, yes. Dan Busetti/Qwest - a report the next day would be okay, would get Tuesday’s work on Wednesday? Kathy Stichter/Eschelon - yes, that would be okay. Dan Busetti/Qwest asked Craig Suellentrop/Qwest if he missed anything. Craig Suellentrop/Qwest stated that Dan captured the key issues. Craig stated that it could differ by CLEC and/or by state. Craig asked for verification that the CLECs would get their own rates. Kathy Stichter/Eschelon stated yes, does not expect Qwest to provide the rates, only the increments. Craig Suellentop/Qwest stated that the CLEC ticket number is contained in CEMR Dan Busetti/Qwest stated that on the report, it would be received the next day with the Qwest ticket number, possibly the CLEC ticket number, circuit ID or WTN, date of dispatch. Kathy Stichter/Eschelon - the WTN would be better than the BTN. Dan Busetti/Qwest asked Craig Suellentrop/Qwest if general information regarding the Maintenance of service charge is left with the End Users. Craig Suellentrop/Qwest stated he believes so but will verify for Dan.

There were no other questions or comments. The meeting was adjourned.

-- 07/17/02 - July CMP Meeting Minutes: Eschelon presented their Change Request. CR status is clarification

Alignment/Clarification Meeting Conference Call Time/Date: 2:00 p.m. (MDT) / Wednesday, July 10, 2002 Place:TEL: 877.521.8688 Conference Call-In No.: CODE: 7901848 CR No.:CLEC Change Request PC070202-1"Time & Material Repair Charges invoice process"

Kathy Stichter, Eschelon, ILEC Relations Manager Craig Suellentrop, Qwest, 271 Network Technical Regulatory Alice Matthews, Qwest, Process Specialist Michael Keegan, Qwest, CMP Manager

Introduction of Attendees Attendees introduced.

Review Requested (Description of) Change Description: Currently Qwest leaves a "Time and Materials Invoice" with its retail customers during a repair visit when the trouble was not found in the Qwest network. Qwest does not supply anything to CLECs. This "Invoice" would assist Eschelon in reconcilling its bill. Eschelon asks Qwest to develop, document and train an adhered to process to supply CLECs with this same "Invoice" or something similar, with the same detail, that will state the charges that Qwest plans to bill at the time of the repair visit. The "Invoice" should contain the Qwest repair ticket number, the number or circuit ID which was reported in trouble, the customer's name and address, the Qwest technicians name and telephone number, the date, the USOCs that Qwest will bill, the quantity of each USOC, the cost of each USOC, the total cost and the reason for the charge.

Discussion: Eschelon is requesting that the same type of time & material invoice that is generated by Qwest technicians for Qwest retail customers be generated for the CLECs prior to billing and mailed to the CLEC for review and signature.

Qwest indicated that they understood the scope of this CR. Craig Suellentrop will coordinate the production of the Qwest response. N/A

Confirm Areas & Products Impacted Areas Impacted: Maintenance/Repair Products Impacted: Centrex, Unbundled Loop, UNE Loop, UNE-P, Resale N/A

Confirm Right Personnel Qwest confirmed the correct personnel were on the call.

Identify/Confirm CLEC’s Expectation A process to supply CLECs with an "Invoice" of repair charges at the time of the repair visit.

Identify any Dependent Systems Change Requests None

Establish Action Plan (Resolution Time Frame) Eschelon can present this Change Request to the CLEC community at the July Product/Process CMP meeting scheduled for July 17 Qwest will issue draft response to this Change Request by Aug 14 (one week prior to the Aug 21 CMP meeting). Qwest will discuss the draft response at the Aug 21 CMP meeting.


CenturyLink Response

REVISED RESPONSE

January 17, 2003

RE: SCR070202-1X Time & Material Repair Charges invoice process

Qwest has reviewed the information submitted as part of Change Request SCR070202-1X. Based upon the scope of this CR as agreed to in the Clarification Meeting, Qwest is able to provide an estimated Level of Effort (LOE) of 1500 to 2000 hours for this Change Request.

Qwest will review release schedules and development timetables in an effort to evaluate options for potential scheduling of Change Request SCR070202-1X

Sincerely, Qwest

See Crossover SCR070202-01X

August 13, 2002

DRAFT RESPONSE for PC070202-1 For Review by CLEC Community and Discussion at August’s CMP Meeting

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR PC070202-1 “Time and Material Repair invoice process.”

This CR states that Qwest leaves a ‘Time and Materials Invoice’ with its retail customers during a repair visit when the trouble was not found in the Qwest network. The CR requests that Qwest supply CLECs with this same ‘invoice’ or something similar, with the same detail that will state the charges that Qwest plans to bill at the time of the repair visit.

Qwest does leave a Time and Materials Invoice with retail customers when a repair dispatch will result in a charge. This invoice is informational in nature. The technician that is dispatched leaves it at the premises. The actual bill (for both wholesale and retail customers) is generated through automated systems and manual processes that occur when a technician closes a trouble ticket. Qwest does not have a billing relationship with CLEC end-users; therefore, Qwest’s process is to not leave invoices with CLEC end-users. CLECs may use electronic maintenance and repair systems (CEMR) to view trouble ticket history as it appears in Qwest’s systems. This information would be valuable in disputing or substantiating repair charges.

Qwest does not have an organization that is responsible for collecting and distributing these invoices. Qwest believes that a systems CR should be opened to generate an automated report that would provide CLECs with data regarding maintenance and repair billing in the timeframe requested. A meeting will be scheduled for late August to discuss CR’s involving maintenance and repair billing, including this CR. Further clarification and direction for this CR will be determined after this meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Susie Bliss, Director-Process Management, Qwest Alice Matthews, Senior Process Analyst, Qwest


Open Product/Process CR PC030603-1 Detail

 
Title: Documentation process to allow CLECs to request documentation of existing processes, including documentation on the Qwest Wholesale web site.
CR Number Current Status
Date
Area Impacted Products Impacted

PC030603-1 Completed
4/21/2009
PreOrder, Ordering All
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Coyne, Mark
Director:
CR PM: Harlan, Cindy

Description Of Change

Eschelon asks Qwest to develop a quick and effective process for CLECs to obtain readily accessible documentation for existing Qwest processes without having to go through the full, lengthy Change Request (CR) process for each Qwest undocumented process. Qwest has a duty to provide clearly documented processes. When Qwest fails to do so, the burden should not be on CLECs to use CMP to obtain something that Qwest should already have in place without further action by CLECs. Nonetheless, in recent months, Eschelon has had to submit a series of CRs to obtain documented processes for several of Qwest existing processes. (For example, see OC123102-1, PC112502-1 and PC010603-1.) . This is time consuming and a burden to CLECs, even though the duty to provide documentation belongs to Qwest. Simply obtaining documentation for an existing process should not take as many steps and as much time as actually changing a process or system. The reality is that the local service ordering guide (LSOG) and Product Catalog (PCAT) do not always provide needed information, such as information needed for a CLEC to process an accurate LSR, particularly when manual handling is required. Although Qwest has existing internal processes, Qwest has not documented many of those processes for CLECs. Without adequate documentation, when the process breaks down, CLECs are forced to spend unnecessary time and resources debating with Qwest representatives about the process itself, when those challenges could be avoided by simply pointing to mutually accessible documentation that clearly states the process for all involved. Instead, unnecessary escalations waste CLEC and Qwest resources. To avoid this scenario, Qwest needs to provide clear documentation that is readily accessible to CLECs. When Qwest fails to do so, Qwest should have a process in place to obtain the documentation without submitting a CR. CLECs should be involved in development of this process to ensure it meets their needs. The process could include, for example, a CLEC notice of an undocumented process to a specified Qwest single point of contact for this issue and a designated interval for responding to the request and circulating the new documentation that will be posted on the web site. With such a process, the necessary documentation could be provided much more quickly to the CLECs.

Expected Deliverable:

Qwest to develop a process to provide adequate and complete documentation on the Qwest Wholesale web site, in a user-friendly location and format, for existing processes identified by a CLEC or CLECs. Because these are Qwest existing processes and do not require development, the time to document the process should be minimal. Therefore, the process to obtain the documentation should be quick and easy.


Status History

3/6/03: Received CR from Eschelon

3/10/03: Acknowledged CR by P/P CMP Manager

3/12/03: Contacted Customer and scheduled Clarification Meeting for 3/18/03 9:30 - 10:00

3/18/03: Held Clarification Meeting

3/19/03: March CMP Meeting minutes will be posted to the database

4/16/03 - April CMP Meeting minutes will be posted to the database

4/24/03 - Notification advising of CLEC review meeting scheduled for May 14 from 11:30 - 1:00 mst.

5/14/03 - Reviewed Draft process with CLEC Community. Agreed to set up trial with 3 CLECs.

5/21/03 - May CMP Meeting Minutes will be posted to the database

6/3/03 - Training was held for CLECs participating in the trial (Eschelon, ATT and Allegiance). The trial will start effective June 16, 2003.

6/18/03 - June CMP Meeting Minutes will be posted to the database. Bonnie agreed to move this CR to CLEC Test status.

7/16/03 - July CMP Meeting Minutes posted to the database

7/30/03 - Held meeting to gather input from the trial. See notes for details.

8/9/03 - Documentation process released Level 1 (trial CLECs agreed to Level 1)

8/20/03 - August CMP Meeting Minutes - see notes

9/10/03 - Provided existing process information to Eschelon: An existing process is a Qwest standard operating methodology that is normally or usually followed and not included in external Qwest documentation available to CLECs.

9/17/03 - Sep CMP meeting notes will be posted to the database


Project Meetings

September 17, 2003 CMP Meeting Minutes Cindy Macy – Qwest advised this process is in place and working. Cindy Macy did forward to Bonnie the information regarding ‘existing process’. Bonnie Johnson-Eschelon advised she appreciated the response but she will escalate if the documentation team is not in agreement with her documentation requests. Cindy Macy explained that the Documentation team will pull together the SMEs and the CLEC to discuss the CR if there are any questions or concerns about accepting the CR. This group would try to resolve the questions, and if not it could be escalated to Mark Coyne and Sue McNa. Bonnie agreed to close this CR.

August 20, 2003 CMP Meeting Minutes Mark Coyne – Qwest advised the trial ended July 7. Twelve requests came in. Three requests have been completed. Five will publish in two weeks. Two were closed per the CLECs. Two were originally denied and are now back in review. The team met on July 28 to review the trial. As a result of the trial three updates were requested: 1- send confirmation back This has been implemented

2- provide submit button The developer advised the tab button is used to move between fields and the enter key is used to submit the form

3- escalation / review process The process is updated to include a clarification / review call if needed

Training began on August 4 and the process was implemented August 11. Since then, five additional requests have come in and are being worked on.

Bonnie asked for status regarding her question “what is the definition of an existing process?” Is a process considered ‘existing’ if it is documented internally at Qwest but not documented for CLECs? Or is it any process that is being used by Qwest. Cindy Macy – Qwest advised the definition of an existing process is being looked at. Bonnie advised this affects Level 2 notices also. Liz confirmed the documentation process includes documenting ‘gaps’ in existing processes. Cindy Macy – Qwest advised the concern is over documenting individual case processes that are unique. Cindy Macy – Qwest advised additional information will be provided at the next meeting.

CLEC Change Request – PC030603-1 Meeting minutes - Review Documentation Process trial Wednesday, July 30, 2003

Attendees Cindy Macy – CRPM Mark Coyne – Qwest Jackie Cole – Qwest Carla Pardee – ATT Bonnie Johnson – Eschelon Kim Issacs – Eschelon Lori Mendoza – Allegiance Liz Balvin - MCI

Cindy Macy -Qwest welcomed all attendees and reviewed that the purpose of this meeting is to obtain input on how the Documentation trial went. The main concern has to do with accepting and denying Documentation CRs.

Carla Pardee – ATT shared that she believed this was a very good step for Qwest and it has been easy to use so far. She also said that she is very happy that we will be including certain system documentation in the process.

Bonnie Johnson – Eschelon advised she is frustrated about the level of detail on manual processes and that these are not documented clear enough. Bonnie advised the PCAT put together by Joan Wells for Port Within is an example of a process that is documented to the correct level of detail. Bonnie advised the CLECs need the level of detail to send a good LSR and not have to guess or get the LSR rejected. Bonnie also said this process is easier and quicker and it has a lot of benefits.

Lori Mendoza – Allegiance explained her Service Manager worked with Russ Urevig on a process and got the PCAT updated without any CR (CLEC documentation or CMP). The team agreed this can happen with an internal documentation request. The team agreed the Service Managers or process specialist can and do initiate requests on their own.

Mark and the CLECs discussed the CR request for RPON. This was a CR that was originally denied. Mark agreed to add additional detail to the PCAT overview regarding RPON. Mark’s concern has to do with exception processing or situations that are unique or handled as an individual case. Qwest can not document every unique or possible condition. Mark agreed when there is a concern over denying a documentation CR the documentation team will hold a (15 minute) conference call with the product process person, service manager, documentation team and CLEC to discuss and clarify.

Liz Balvin – MCI advised she also has concerns over the use of LA versus SA. Mark asked for examples of this problem and he would be glad to investigate. He will leave this documentation request open until we get examples to proceed. **We have not received examples as of August 5. Please forward examples for us to continue working on this item.

Kim Issacs- Eschelon had the following questions: 1. Submission process - If you hit enter after or at the end of the sentence this sends the CR, even though you may only be ½ done filling out the request. Jackie agreed she would check on this. 2. After submit, the confirmation doesn’t send back the description, only a confirmation. Jackie advised this should be fixed and she will check on it. 3. On denials – the CLECs would like to talk to the process person or get a reason why the CR was denied. Mark advised the documentation team will put together a conference call to discuss requests that are denied. 4. When a request has been accepted what Level will it be? The team discussed the level and agreed none of the documentation requests will be handled as a level 0. The request is for them to be at least a Level 1

Bonnie and Mark discussed the concern over Level 2 Bullet #8 and the definition of an existing process. Bonnie asked what is considered an existing process? What is the criteria for an existing process? Is a process that is being used considered an existing process? Cindy Macy agreed she would clarify the intent of this bullet.

The group discussed this process will be available on the web site August 11. We discussed the level that this process should be released under and the team agreed we should use a Level 1 Notification.

July CMP Meeting Minutes - Mark Coyne – Qwest reported the trial completed last week on July 11, 2003. There were twelve CRs received. Eight were accepted. Out of the eight accepted, one is published and seven are in progress. Of the four remaining one was closed, one was published and two were denied. The target implementation date in the middle of August. We have a meeting scheduled for the week of 7/21 to review the trial results. The CLECs would like to discuss the denial CRs and determine if there is a change that can be made to the denial step. Mark explained Qwest struggles with the level of detail and how much exception processing we document. Bonnie gave an example of LA versus SA and how that causes much confusion in LSR processing. Bonnie requested for the level of detail to not allow for anything to be left to interpretation. She would like to have the information needed to successfully submit the LSR without it being rejected. Bonnie explained she is asking for the same opportunity to have the same information that is available to Qwest. Mark Coyne – Qwest advised this may lead Qwest to revisit the scope and criteria of the Documentation Process. Bonnie Johnson – Eschelon stressed that the process is working, we just have this one glitch to work on. Mark Coyne – Qwest advised we will discuss more next week. This CR will stay in CLEC Test.

June CMP Meeting Minutes - Mark Coyne advised they have received 4-5 documentation requests and are working on them. The training is completed for the CLECs, Service Managers and 50% of the Product/Process Specialists. Qwest would like to move this to CLEC Test. Bonnie advised that was okay.

May CMP Meeting Minutes -

Mark Coyne – Qwest advised we met with the CLECs on May 14, 2003. There was good participation and the process was received very well. Qwest will make minor updates based on comments received. Qwest will trial the process with 3 CLECs: Eschelon, ATT and Allegiance. Qwest will train the 3 CLECs on June 3, with the trial taking place the middle of June – middle of July. Implementation will occur the first week of August. Qwest will leave this CR in Development status. Bonnie Johnson – Eschelon commented the documentation team did a very good job on the process.

PC030603-1 Documentation Process Ad Hoc Meeting May 14, 2003

Review CLEC Documentation Request Process with CLEC Community

In Attendance: Sheila Raunig – Qwest Candice Mowers – Qwest Sharon Van Meter – ATT Donna Osborne Miller – ATT Susan Lamb – Open Access Lori Mendoza – Allegiance Bonnie Johnson – Eschelon John Berard – Covad Jeff Tietz – Qwest Kim Issacs – Eschelon Jackie Cole – Qwest Jill Martain – Qwest Jen Arnold – US Link Sue Mcna – Qwest Cindy Macy – Qwest Mark Coyne – Qwest Liz Balvin – Qwest

Cindy Macy Qwest reviewed the purpose of the meeting and discussed what steps the team has gone through so far. Everyone confirmed they had a copy of the process material to be reviewed.

Mark Coyne reviewed the process in detail. The process was discussed with the following questions/answers provided.

Donna Osborne-Miller reviewed the Scope table and discussed what was in and out of scope.

Bonnie Johnson asked why there are multiple times / places in the process that the scope is reviewed. Mark advised there is a first cut high level view by the documentation team when the request comes in and then the SME makes the lower level more detailed review.

Sharon Van Meter asked if the comment cycle still applied, as she wanted to be sure they had the opportunity to comment if they were not happy with the process documentation. Mark advised yes, the Level 1 / 2 comments cycle would apply. Sue Mcna advised the documentation would be placed on the document review web site as it is done today.

Liz Balvin asked if Qwest is subject to this same process. Sue Mcna advised we are using a version of this same process today. The internal requests are subject to the same ‘in scope/out of scope’ review.

Mark Coyne reiterated the work will be handled first in / first out.

Bonnie Johnson asked if all the fields are required on the Request form. Mark advised no. Bonnie said they might not have data for all the fields. Bonnie wanted to make sure the ‘Detailed Description of Change’ allowed for unlimited or adequate space. Jackie – Qwest advised she would double check the space available and make sure it is large enough.

Bonnie Johnson asked if Qwest would be matching the requests for synergies since we will be handling them FIFO (first in first out). Mark advised we would look at people’s workload and synergies to manage the volume.

Cindy asked if we could move existing CRs to this process if the timing was appropriate. The team agreed that would be okay if the timing worked. Carla asked about a CR that was currently in the response cycle. The team agreed this one would not be a good candidate as it is almost through the process.

Mark advised we would like to trial this process initially. Cindy asked for 2-4 CLECs to trial the process. Eschelon, ATT and Allegiance volunteered to participate in the trial. Sheila – Documentation team advised Qwest would schedule a training session with the trial CLECS. The team agreed to trial the process for approximately a 1-month time frame. The trial team will meet again to review and provide input to the process during the trial.

The CLECs advised the process was well done and very few questions or changes were needed.

Thanks, Cindy Macy

4/16/03 April CMP Meeting - PC030603-1 Documentation Process

Mark Coyne – Qwest advised we are currently meeting to develop a process to support this CR. We are reviewing the CR internally and then will set up a meeting to review and gather input from the CLEC Community. Qwest would like to move this CR to Development status.

3/19/03 March CMP Meeting Minutes - This CR was walked on during the March CMP meeting Bonnie Johnson advised we held the Clarification call on March 18 and she believes Qwest understands the request. Bonnie advised the CLECs would like a process, outside of the CMP process, to advise Qwest about documentation that is missing, in error, or lacking information. Bonnie advised they sometimes need more detail than is in the LSOG. CLECs go to their Service Manager for help but the end result is not updated in the documentation so they continue to go through the same problem. Bonnie advised it is not her responsibility to issue a CR to have the documentation updated after they figure out how to issue the LSR. Sue McNa recapped Bonnie’s request and advised Qwest agreed to look at the CR and brainstorm to determine how to handle this request. Sue advised we want to address how the CLECs can best communicate documentation issues to Qwest and also provide prioritization of the work they identify.

Clarification Meeting March 18, 2003 1-877-572-8688 3393947#

PC030603-1 Documentation Process to allow CLECs to request documentation of existing processes, including documentation on the Qwest Wholesale Web Site

Attendees Jill Martain – Qwest Judy DeRosier – Qwest Sue McNa – Qwest Bonnie Johnson - Eschelon Nancy Chapman – Qwest Cindy Macy - Qwest

Meeting Agenda 1.0 Introduction of Attendees Attendees Introduced

2.0 Review Requested (Description of) Change Bonnie reviewed and clarified the CR. Bonnie explained she is asking for existing processes that are not documented on the Qwest Wholesale web site to be documented without going through the CMP process. It is Eschelon’s belief that Qwest should have these processes documented. Bonnie would like an easy way for the CLECs to be able to request the process to be documented.

Bonnie explained they have been working with the Service Management team on LSR processes such as rejects. We will get an email from Qwest that explains how to issue the LSR. This information should already be on the web site. The responsibility falls on the CLEC to issue the CR and get the process documented. Bonnie would like a process outside of CMP for documentation requests.

Sue Mcna asked for Bonnie to share her thoughts on how this would work, what the CLECs would like.

Bonnie explained possibly a Level 2 Notification would still be required such as ‘Document an existing process that has not been documented before’. The process should be quick and efficient for Qwest too. The process may need a Project Manager.

Sue Mcna said Qwest values the input from the CLECs. We don’t always know what documentation is missing. How would the CLECs notify Qwest of missing / errors in documentation?

Bonnie offered the idea of having it as a ‘standing agenda item’ at the end of the Monthly CMP Product Process Meeting.

Bonnie provided another example of a documentation issue using the documentation links. They do not always link you to the correct process or the process is not detailed enough to help. Then the LSR gets rejected. The LSOG is not always to the level of detail that is needed. They need more details on the ‘Business Rules’.

Bonnie also suggested the web site provide look ups by Process not Product. Sue Mcna advised restructuring the web site would be a huge effort.

Sue clarified what Bonnie is suggesting is an: - easy way to communicate to Qwest missing documentation - errors in documentation - gaps or missing information in documentation

Sue asked how the CLECs would prioritize the requests. Suggestions were possibly by identifying what processes are critical or most problematic.

Cindy agreed she would set up an internal working session meeting to begin discussing the CR. Bonnie will present this CR at the March 19 CMP meeting.

3.0 Confirm Areas & Products Impacted Documentation

4.0 Confirm Right Personnel Involved Mark Coyne, Jill Martain, Joann Garramone, Candace Mauers, Service management resource

5.0 Identify/Confirm CLEC’s Expectation Sue clarified what Bonnie is suggesting is an: - easy way to communicate to Qwest missing documentation - errors in documentation gaps or missing information in documentation

6.0 Identify any Dependent Systems Change Requests None

7.0 Establish Action Plan (Resolution Time Frame) Bonnie will present at the March CMP Meeting Cindy will set up internal meeting to begin working on resolution


CenturyLink Response

For Review by the CLEC Community and Discussion at the May 21, 2003 CMP Meeting

May 14, 2003

Eschelon Bonnie Johnson

SUBJECT: Qwest’s Change Request Response – CR #PC030603-1 Documentation Process to allow CLECs to request documentation of existing processes

This letter is in response to Eschelon’s Change Request (CR) PC030603-1. This CR requests that Qwest establish a process for the CLECs to request documentation on existing processes or gaps in existing processes.

Qwest accepts this CR and is currently developing: ? A Process to address documentation updates outside of CMP ? A Process for tracking and completing external documentation updates

In addition, Qwest has scheduled a walkthrough of the process with Eschelon and other CLECs. This meeting is scheduled for May 14, 2003 from 11:30 – 1:00 MST.

Qwest requests this CR be placed in Development Status and will provide an update at the June CMP Meeting.

Sincerely,

Mark Coyne Qwest


Open Product/Process CR PC012004-1ES Detail

 
Title: Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail.
CR Number Current Status
Date
Area Impacted Products Impacted

PC012004-1ES Denied
4/21/2004
Pre-Ordering, Ordering, Billing
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Thacker, Michelle
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail. The detail should include: (when applicable) escalation ticket number, date received, caller name, caller call back TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, closing sub code. The customer name and TN optional. Qwest has provided this information to Eschelon before and has this detail.

The detail should include: (when applicable) escalation ticket number, date received, caller name, caller call back TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, closing sub code. The customer name and TN optional. Qwest has provided this information to Eschelon before and has this detail.

Expected Deliverable:

Include escalation ticket detail with the monthly escalation ticket report or develop a new report to provide the detail separate from the existing report Qwest provides to the CLEC.


Status History

01/20/04 - CR Submitted

01/22/04 - CR Acknowledged

02/04/04 - Held Clarification Meeting

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/02/04 - Qwest received escalation from Eschelon

06/04/04 - Qwest issued notification CMPR.06.03.04.F.01756.EscalationNoticeEschelon

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

06/16/04 June CMP Meeting Kit Thomte with Qwest said this CR had been escalated and the response sent to Eschelon. Bonnie Johnson with Eschelon said that Qwest did respond to the escalation and explained she was disappointed with the denial and the comment of gathering data for CLECs. Eschelon gathers data for Qwest that Qwest already has and Eschelon will make of point of mentioning it in the future when Qwest asks Eschelon to gather data. Bonnie also asked that blanket coverage be provided to the CSIE employees explaining they should provide the closing code and sub-code reasons when the CLEC asks for the information. Jen Arnold with TDS Metrocom/USLink asked if it was appropriate to get status codes that are spelled differently, e.g. pre-ordering, and will e-mail Linda Sanchez-Steinke. This CR will remain in Denied status.

05/19/04 May CMP Meeting Michelle Thacker with Qwest said that this CR was denied last month and there was an action item opened to research additional information that could be provided in the report. Qwest is unable to provide additional data and the CLEC already provides the requested data with the opening of the call center ticket. Bonnie Johnson with Eschelon said that Qwest was going to find out what additional information was available. Susie Bliss with Qwest said that it is expensive to pull the information and we are not required to compile your data. Stephanie Prull with Eschelon said that the original intent of the CR was to be able to use the report as a training tool, and the current report provides data that we are unable to determine who might be making errors. Eschelon is not always tracking the way they should. Susie said that she understands but we are not able to provide any more at this point. This CR will remain in Denied status.

04/21/04 April CMP Meeting Michelle Thacker with Qwest said that after researching this CR Qwest determined that it was economically not feasible to produce manual spreadsheets because it takes 91 hours to produce the spreadsheets for only 14 CLECs. Before an escalation ticket can be opened, the CLEC name opening the ticket, LSR ID or PON, are data that the CLEC already has.

Bonnie Johnson with Eschelon said that the report provided today to the CLECs could include those data fields that can be electronically pulled. Bonnie said she would have a problem if the current report couldn’t be expanded to include those specific fields that are critical. Bonnie asked that it be communicated which fields can be provided. Caller Name TN and Subcode are critical information contained in the specific fields, and would be critical for the report. Michelle said that CLECs would have that information within their company. Bonnie said that there is a need to reconcile the data. Kim Issacs with Eschelon added that some tickets have been coded as Eschelon but are not tickets opened by Eschelon. Michelle said she would continue to research the separate report, and the current report from the database provides statistical information and counts the numbers of tickets.

Bonnie asked if Qwest uses reports from the escalation database for quality review and training. Michelle said that there are manual reports pulled, like the one Eschelon received from their service manager. These reports are used to sample tickets and work through spreadsheets and word documents. The samples are then discussed with supervisors and coaches and used for training. Bonnie said there might be some type of “crystal” program that would pull data electronically that could be used to provide the report requested and may help Michelle if she no longer needed to pull the manual report. This CR will remain in Evaluation status.

Sent 4/19/04 6:58 a.m. From: Johnson, Bonnie J. [bjjohnson@eschelon.com] To: Sanchez Steinke, Linda, Johnson, Bonnie J. Subject: RE: Draft Response PC012004-1

Linda, I would like Qwest to determine what additional they could add to the existing escalation ticket report that would not need to be manually produced. For example, the sub codes and TN of caller...etc.

Thanks you,

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

03/17/04 March CMP Meeting Michelle Thacker with Qwest said investigation and research is being conducted on this CR and asked if it could be moved to evaluation status and an updated response be provided at the April CMP meeting. This CR will move to Evaluation status. - 02/18/04 February CMP Meeting Bonnie Johnson with Eschelon presented this CR. Bonnie said this is an extension to the CR just closed and this CR asks for more detail than the report currently provides. Eschelon’s service manager has provided a report that included the level of detail required to address Eschelon’s training needs. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

1:00 p.m. (MDT) / Tuesday February 3, 2004

1-877-572-8687 3393947# PC012004-1 Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail.

Name/Company: Bonnie Johnson, Eschelon Kim Isaacs, Eschelon Michelle Thacker, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting. Review Requested (Description of) Change

Linda Sanchez-Steinke with Qwest read the description of change; Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail. The detail should include: (when applicable) escalation ticket number, date received, caller name, caller call back TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, closing sub code. The customer name and TN optional. Qwest has provided this information to Eschelon before and has this detail.

The detail should include: (when applicable) escalation ticket number, date received, caller name, caller call back TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, closing sub code. The customer name and TN optional. Qwest has provided this information to Eschelon before and has this detail.

Expected Deliverable: Include escalation ticket detail with the monthly escalation ticket report or develop a new report to provide the detail separate from the existing report Qwest provides to the CLEC.

Bonnie Johnson with Eschelon said that the report Jean Novak provided was for February 2003 Escalation tickets. The report provided to Eschelon in April identified a high number of calls for account ownership. After researching the calls, Eschelon made internal changes and also discovered the loss report was inaccurate. Bonnie said she is disappointed that the original report did not include detailed information and it will be helpful to have additional details in the existing report as currently Eschelon doesn’t not have details about who made the calls and what department calls are being made from. Bonnie said that the report could be provided through the existing report or through the service manager.

Michelle Thacker with Qwest asked if Eschelon tracks the calls made to Qwest. Bonnie said that only one group is tracking calls and there are many departments that call Qwest.

Michelle asked if Eschelon asks the SDC for critical information on the ticket such as status or Product reason code, close code and sub close code. Bonnie said that she didn’t know if all departments were requesting that information. Bonnie said that Provisioning, Maintenance and Repair departments all make calls and the Billing group fields complaints for double billing, but primarily service delivery makes the calls.

Bonnie added that she is hopeful that with 14.0, information will be stored and will have the capability to search by TN which will help reduce the number of calls and will provide order number and due date.

Michelle asked if Jean would be tracking calls before and after the release. Bonnie said when Qwest provided the report in April 2003, no analysis was performed, just the report was provided.

Confirm Areas & Products Impacted Pre-Ordering, Ordering, Billing

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting.

Identify/Confirm CLEC’s Expectation Include escalation ticket detail with the monthly escalation ticket report or develop a new report to provide the detail separate from the existing report Qwest provides to the CLEC. I dentify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) Eschelon will present this CR at the February CMP Meeting and Qwest will provide a response in March.


CenturyLink Response

April 12, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at April’s CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: "Qwest’s Change Request Response - CR # PC012004-1 (Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail)"

This letter is in response to CLEC Change Request (CR) PC012004-1. This CR is a request by Eschelon to establish a process whereby CLECs can receive, on a monthly basis, ticket detail including (when applicable) escalation ticket number, date received, caller name, caller TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, and closing sub code. The customer name and TN is optional.

Currently CLECs can request via their Service Manager a statistical report of their activity with the Call Handling Centers. These reports are sent monthly and contain the following data: - Total Tickets Received - Total Tickets Received by Date Across Tier - Total Tickets Received by Product Across Tier - Total Tickets Resolved Across Tier - Total Tickets Resolved by Reason Code Across Tier - Total Tickets Resolved by Product Across Tier

In assessing this request, Qwest evaluated the scope in relationship to the Change Management Process, business benefit, feasibility and the financial impact to implement this process.

Today, CLECs provide Qwest with the following details in order to open a call center database ticket: - Caller name - CLEC Representative - Caller TN - Call back number for CLEC Representative - PON or LSRID - End User Name - End User Telephone Number - Product (although this can be obtained by pulling a copy of the LSR) - A detailed explanation of their reason for calling

Once this detail is input on the ticket the Qwest Representative begins to research and gather additional information to assist the CLEC. A ticket cannot be opened properly if the CLEC does not provide the detail above.

Other requested fields such as Service Order Number, Escalation Ticket Number, Date Ticket Opened/Date Ticket Closed, and Close Code are available upon request from the Call Center Representative.

The remarks field detail requested by the CLEC contains data that may be confidential, proprietary, or extraneous to the information requested by the CLEC. Confidential data includes, but is not limited to, proper names of Qwest personnel, intracompany telephone numbers for Qwest personnel, data that may be a cut and paste from an internal website, etc. Qwest currently has no system that can read or parse confidential data from the remark fields. In order to accommodate this request, Qwest must manually retrieve data from the Call Center database, review each ticket, parse confidential/proprietary data and prepare the report to be sent to the CLEC. This currently would be an excel spreadsheet.

Eschelon sent along with the change request a copy of an excel spreadsheet that contained call center ticket data from February 2003 provided by Qwest. This report, in fact, was manually produced using the steps above.

Qwest performed analysis to determine the amount of time required to produce an excel report of tickets. A total of 8332 tickets were reviewed for 6 CLECs for an average of 1389 per CLEC for one month. The average time to parse an Excel spreadsheet was 39 hours, which consisted of reading and editing 214 tickets per hour. Today, we have 14 CLECs subscribing to the original request which is 1289 average tickets per CLEC X 14 CLECs = 19,446 tickets to parse with an average of 214 per hour. The hours of manual work per month for only 14 CLECs would be 91 hours. It is expected the number of CLECs requesting the monthly report will increase if the requested data is available.

Qwest respectfully denies this change request because it is economically not feasible, cost prohibitive to implement the request and because the requested change does not result in a reasonably demonstrable business benefit. CLECs currently provide Qwest with data to open a call center ticket, therefore, CLECs would already have some of the data they are requesting Qwest provide to them. Qwest provides detail requested via other sources.

Sincerely,

Michelle Thacker Sr. Process Analyst Qwest Communications

March 9, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the March 17, 2004 CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response - PC012004-1 "Include escalation ticket detail along with the monthly escalation ticket report or create a separate report to provide the detail"

This letter is in response to CLEC Change Request (CR) PC012004-1. This CR is a request by Eschelon to establish a process whereby CLECs can receive, on a monthly basis, ticket detail including (when applicable) escalation ticket number, date received, caller name, caller TN, PON, LSR ID, product, complete date, reason for call (code opened under), service order number, remarks, closing code, and closing sub code. The customer name and TN is optional.

Qwest is currently evaluating this change request and propose moving this CR into Evaluation Status while a complete answer to the request is prepared.

Sincerely,

Michelle Thacker Sr. Process Manager Qwest


Open Product/Process CR PC022304-1 Detail

 
Title: Develop a web based electronic interface to enter and maintain the New Customer Questionnaire
CR Number Current Status
Date
Area Impacted Products Impacted

PC022304-1 Denied
5/19/2004
New Customer Questionnaire
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Lewis, Judy
Director:
CR PM: Andreen, Doug

Description Of Change

Eschelon is requesting that Qwest develop a web based electronic interface to enter and maintain information on the New Customer Questionnaire. The current Word version of the New Customer Questionnaire makes viewing the current information and updating the information difficult for CLECs. Eschelon requests that this web based tool allow multiple CLEC users to view the most current CLEC profile data and allows a CLEC to update individual sections of the CLEC profile as needed. Eschelon believes a web based New Customer Questionnaire would streamline the process to make needed updates to the questionnaire saving the CLEC and Qwest time and resources

Expected Deliverable:

1. Create a secure web based electronic New Customer Questionnaire

2. Develop questionnaire sections so only sections requiring updates will need to be submitted


Status History

02/23/04 - CR submitted

02/25/04 - CR acknowledged

03/01/04 - Held Clarification call

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to Presented

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

7/21/04 July CMP Meeting Judy Lewis, Qwest stated that this month we have researched the Verizon questionnaire. Doug Andreen obtained a paper copy of the Questionnaire and spoke to the Verizon contact. The Verizon Questionnaire would require changes to naming conventions among other items to implement at Qwest. Judy also pointed out that this Questionnaire is similar to the one used by SBC. Judy said we are in the same position where there is no funding for this request. Bonnie Johnson, Eschelon said she understands the CR is in denial status and appreciated Qwest’s efforts in researching the additional companies. The CR will move to inactive as it was already in Denied status.

-- 6/16/04 CMP Meeting Minutes Judy Lewis, Qwest said since the last meeting she had looked at SBC’s questionnaire and found many similar items. The major difference is that the SBC model is designed to get the information to the entity it affects. Therefore, the program would require many modifications to work at Qwest. Judy did add she reviewed a word document of the system since she was not able to obtain access to the on-line system. Kim Isaacs, Eschelon said that Verizon is rolling out an electronic profile. Judy asked for a contact at Verizon and Kim said it was Gee GeeVanvig at 212-240-7841. Judy will contact Verizon. This CR will remain in denied status.

5/19/04 May CMP meeting Judy Lewis, Qwest summarized the response by saying that a list of requirements were sent to IT along with a request for a level of effort. The LOE came back with 16,600 hours to do the front end system work and data base development combined with the necessary testing and maintenance required. Therefore Qwest is denying this CR because it is economically not feasible. John Berard, Covad asked if the Bell South system was an option. It is called the On Line Profile System. Judy said that Qwest could look at that. Bonnie Johnson and Kim Isaacs, Eschelon said that this information was provided in the clarification call and Kim added that SBC believes that it is a help to them also. Judy said she didn’t recall getting a contact name. Ken Beck, Qwest said that he could call and obtain a contact. Susie Bliss, Qwest said that the denial would stand but we would check into the SBC system. She added that she would have Steve and Mark take a look as well. Liz Balvin, MCI said that it would help everyone if the system were mechanized. Bonnie asked if we could open an action item on this issue. Susie said yes. The CR will move to Denial but remain open.

- 4/21/04 April CMP Meeting Judy Lewis, Qwest stated that the requirements have been developed and a LOE has just been received. She said a response would be available next month. Bonnie Johnson, Eschelon asked if any of the development previously done could be used to satisfy this CR. Judy replied that this had been checked and the development did not meet today’s requirements. The CR will be moved to Evaluation.

-- 03/17/04 March CMP Meeting Bonnie Johnson, Eschelon presented this CR calling for a New Customer Questionnaire that is web based and would be updateable by individual section. She stated that there is difficulty in updating the current questionnaire and that she hoped some work that might have been started one or two years ago could be used in developing the new questionnaire. She also stated that SBC has a questionnaire that is web based. Bonnie said that the SBC questionnaire takes the same path as it did previously once the updates are made. AT&T also supports the request. Ervin Rae, AT&T added that Sprint has this type of questionnaire but is having some problems with version control. This CR will be moved to Presented status.

-- CLEC Clarification Call 11:00 a.m. (MDT) / Monday March 1, 2004

1-877-521-8688 1456160# PC022304-1 Develop a web based electronic interface to enter and maintain the New Customer Questionnaire Attendees Attended Conference Call Name/Company: Kim Isaacs, Eschelon Bonnie Johnson, Eschelon Doug Andreen, Qwest Judy Lewis, Qwest Carrie Bell, Qwest Jennifer Beach, Qwest Ryan Hinkins, Qwest

Meeting Agenda:

1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change Doug read the CR description: Eschelon is requesting that Qwest develop a web based electronic interface to enter and maintain information on the New Customer Questionnaire. The current Word version of the New Customer Questionnaire makes viewing the current information and updating the information difficult for CLECs. Eschelon requests that this web-based tool allows multiple CLEC users to view the most current CLEC profile data and allow a CLEC to update individual sections of the CLEC profile as needed. Eschelon believes a web based New Customer Questionnaire would streamline the process to make needed updates to the questionnaire saving the CLEC and Qwest time and resources. The expected deliverables are to create a secure web based electronic New Customer Questionnaire and Develop questionnaire sections so only sections requiring updates will need to be submitted.

Kim Isaacs, Eschelon added that recently she needed to update both the Qwest questionnaire and the SBC GUI profile and found it much easier to update the SBC GUI. She feels that we would also get more accurate information from an on-line version. It would also save time and resources for both Qwest and the CLECs.

Bonnie Johnson, Eschelon said that this used to be a frequent topic of conversation in the CMP meetings and that the CLECs were told quite some time ago that Qwest had started work. So there may be some work already done.

Doug Andreen, Qwest stated that Qwest would look into any work that had been started.

Jennifer Beach, Qwest asked if the amendments should also be added to the questionnaire.

Bonnie Johnson answered yes after Judy Lewis, Qwest clarified that we were talking about the product amendments.

Jennifer Beach asked if there should be edits for quality and business rules and Kim replied yes that would be fine.

Judy Lewis, Qwest asked if the SBC GUI was set up with digital certificates and Kim replied that it was.

Judy also asked if on the SBC system if multiple Eschelon employees can use the system at the same time. Kim replied yes but there are edits around who can submit the profile and who has read only capabilities.

Ryan Hinkins, Qwest asked how long the SBC GUI had been active.

Kim replied since January and added that each different section is routed mechanically to the appropriate employee in SBC.

Ryan asked how access control was envisioned.

Kim said either digital certificates or by id and password.

Bonnie added that there would have to be one type for update capabilities and one for read only or view capabilities.

Ryan asked if SBC allows read only and change.

Kim said yes for Eschelon 2 employees can make changes and the remainder is read only.

Judy said then it similar to what we have in IMA. Kim answered yes. Ryan verified that what your looking for is ability to retrieve, update and submit. Kim said yes with an added qualifier that SBC has time stamp and will reject sections with errors through status messages on the web.

Ryan asked if there were different questionnaires for different states. Kim answered no, just one questionnaire but with the option to select states and contacts.

Judy asked if the previous information in SBC was put in the GUI or if Eschelon had to load. Kim answered that Eschelon had to populate initially.

3.0 Confirm Areas & Products Impacted Web based questionnaire

4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0 Identify/Confirm CLEC’s Expectation The expected deliverables are to create a secure web based electronic New Customer Questionnaire and Develop questionnaire sections so only sections requiring updates will need to be submitted.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) Eschelon will present at the March CMP meeting.


CenturyLink Response

May 12, 2004

RESPONSE For Review by CLEC Community and Discussion at the May 19, 2004, CMP Product/Process Meeting

Kim Isaacs ILEC Relations Process Analyst Eschelon Telecom

SUBJECT: Qwest’s Change Request Response - CR 022304-1

This is Qwest’s response to Eschelon’s request to develop a web-based electronic interface to enter and maintain the New Customer Questionnaire.

A list of requirements was drafted that included Eschelon’s input from the clarification call held on March 1. A request for Level of Effort (LOE) along with the list of requirements was made to the Qwest IT department regarding this change request. The estimated time to complete the front end system and database development, combined with the necessary testing and maintenance required was approximately 16, 600 hours. Qwest is denying this CR because it is economically not feasible.

Sincerely,

Judy Lewis Customer Account Consultant

April 5, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the April 21, 2004 CMP Meeting

Kim Isaacs ILEC Relations Process Analyst Eschelon Telecom

SUBJECT: Qwest’s Change Request Response PC022304-1 "Develop web based electronic interface to enter and maintain the New Customer Questionnaire"

This letter is in response to CLEC Change Request (CR) PC022304-1. This CR is a request by Eschelon for Qwest to develop a web based electronic New Customer Questionnaire.

Qwest is currently evaluating this change request and propose moving this CR into Evaluation Status while a complete answer to the request is prepared.

Sincerely,

Judy Lewis Qwest


Open Product/Process CR PC120903-1 Detail

 
Title: Qwest will track "access required" information in its systems when Qwest installs new service, or when Qwest dispatches on the repair of an existing line/circuit. Qwest will make the information available to CLECs for use when a CLEC opens arepair ticket
CR Number Current Status
Date
Area Impacted Products Impacted

PC120903-1 Completed
10/20/2004
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Tolman, Don
Director:
CR PM: Andreen, Doug

Description Of Change

Title: Qwest will track "access required" information in its systems when Qwest installs new service, or when Qwest dispatches on the repair of an existing line/circuit. Qwest will make the information available to CLECs for use when a CLEC opens a repair ticket for a CLEC end user customer.

Eschelon requests that Qwest develop and train a process that tracks if Qwest will require access to the customer premise to perform repair and maintenance work. Qwest does not track this data for lines/circuits it installs/repairs. As a result Qwest is causing an unnecessary delay for CLECs customers repair interval. For Qwest to complete its work to repair a line, Qwest process always requires a CLEC to communicate access hours for access to the customer premise, however, Qwest does not always need access from the customer/building owner for Qwest to complete the required repair and maintenance work to repair the Qwest caused trouble. For example, if a CLEC opens a ticket at 4 PM because a customer is out of service, and the CLEC designates access hours of 8 AM to 5 PM for the customer and Qwest cannot dispatch by 5 PM that day, Qwest could put the ticket in a "No Access" status until 8 AM the next morning. Eschelon has provided examples to its Service Management team where Qwest put tickets in a "No Access" status after access hours , the trouble was in the Qwest network and Qwest did not require the customer end user or building owner to provide access. If Qwest tracked "Access required" information in its systems and made that information available to the CLECs when opening a ticket, the CLEC could set clear expectations for repair intervals with its own customers and Qwest could set clear expectations and interval with the CLECs. Because Qwest does not track this information, the decision is left to Qwest personnel to make a decision on whether Qwest needs access to its equipment. In addition, if Qwest and a CLEC knew when access was required, the number of unnecessary dispatches and associated charges to the CLEC could be reduced.


Status History

12/09/03 - CR Submitted

12/11/03 - CR Acknowledged

12/18/03 - Held Clarification Call

12/26/03- Clarification Minutes sent

01/07/04 - Updated Clarification Call minutes sent to CLECs

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Presented

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

2/18/04 - Status changed to evaluation

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to development

4/20/04 - Qwest generated notification PROS.04.20.04.F.01593.Track_CLEC_Access_Rqmts

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/20/04 - Qwest generated notice PROS.07.20.04.F.01884.MaintenanceV34

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/18/04 - Qwest generated notice PROS.08.18.04.F.01983.FNL_MaintenanceV34

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

10/20/04 CMP Meeting Minutes Doug Andreen reported that this process was effective September 3rd and would like to close the CR. Eschelon agreed and the CR will move to completed status.

9/16/04 CMP Meeting Minutes Don Tolman reported that the updates to the PCAT were implemented on September 3rd. He requested that the CR be moved to Test and Eschelon concurred. The CR will move to Test Status.

-- 8/18/04 CMP Meeting Don Tolman reported that the PCAT changes have been out for comment. Two were received, one about streamlining around NIU access and one that required clarification. Susan Lorence said the response to comments goes out today. Bonnie Johnson added that she hoped Qwest took Eschelon’s recommendations for clarity, and Don assured her they had. The CR will be affective September 3. The CR will stay in Development.

-- 7/21/04 July CMP Meeting Doug Andreen, Qwest reported that there was one outstanding question from Bonnie that Don Tolman has answered. Bonnie added that the documentation was out for review as of yesterday July 20. The CR will remain in Development.

6/16/04 CMP June meeting minutes Don Tolman, Qwest provided an update on activities since the last meeting. The process surrounding entering access information in circuit notes will be placed in the Overview of the M&R PCAT. He said he is getting ready to establish timeframes for comment and response. Bonnie Johnson, Eschelon asked when this would be issued for review and Don responded within the week. He added that Qwest people have been asked to start following the new process to acquire information and enter it in the circuit notes and OSLOG notes. Bonnie asked if we would proceed like we do today if there is no definite information. Don answered yes that Qwest would validate with the customer of record and proceed. Liz Balvin, MCI wanted to verify that the information would be available in CEMR and also in BTA. Don said it should be. Doug Andreen, Qwest added that the information would not show up in CEMR until after the fall release. John Berard, Covad questioned if the information would be in a separate field or in the notes field. Don explained there is a field in the circuit notes for NIU Access = Y or N and is part of the testing information that is emailed to the CLECs. If yes is populated it means that Qwest can access the NIU without assistance from either the CLEC or the end user. This information will be kept in the circuit notes and also the OSLOG. When a repair ticket is issued the technicians will validate NIU access field. John then asked which products are covered. Don said unbundled basic products. John asked if this included XDSL and Don said yes. The CR will remain in Development.

- 5/19/04 May CMP meeting Don Tolman, Qwest said that as Qwest installs a service Qwest will note in testing information that is emailed to the CLECs NIU Access = Y or N. If yes is populated it means that Qwest can access the NIU without assistance from either the CLEC or the end user. This information will be kept in the circuit notes and also the OSLOG. When a repair ticket is issued the technicians will validate NIU access field. If yes we still validate for changes with the customer. If Qwest is unable to make contact and the Y is checked then Qwest will make the assumption that access to the NIU is still available and dispatch accordingly. Qwest will put this information into the M&R PCAT under the title of “No Access Information”. Don also noted that if Qwest tries to access the location based on the information in the system and there is no access to the NIU, there will be dispatch charges associated with the trouble ticket. Bonnie Johnson, Eschelon asked if we were to verify with the end user if the building had undergone construction, and they say no, would that be sufficient or does end user need to contact the building manager to verify access. Don answered that he will give examples in the PCAT. Bonnie also asked when doing a repair will the appropriate access information be gathered or updated. Don answered yes. Lastly Bonnie asked if field is blank will it be populated on repair visits. Don answered yes to this also. Doug Andreen, Qwest added that this information will be available in CEMR with the fall release. The timing of the PCAT and notices have yet to be finalized. The CR will remain in Development.

4/21/04 April CMP Meeting Don Tolman, Qwest said that the process has been confirmed with all repair centers and that Qwest is seeing access information being populated. He requested that the CR be moved to CLEC Test. Bonnie Johnson, Eschelon asked if on new installs and repair call if Qwest is going to input access information. Don stated yes, but since the information can change it requires updating when subsequent calls are made to the CLEC. Bonnie asked if Don could quantify at the time of the install or repair ticket how often this information changes. Don stated he could not quantify but it is likely when for instance Qwest terminates to a room not yet built or to an outside location. He further clarified that if Qwest terminates to a closet and notes that a key is needed that information needs to be verified on subsequent calls as to who has the key. Don said we would capture the information to know if access is needed for Qwest NIU. Bonnie asked if the information could be in CEMR and documented in the PCAT that the last demark might be on the customer premise. Don answered that he would take it off line to see if this could be done. The CR will stay in Development.

-- 03/17/04 March CMP Meeting Don Tolman, Qwest covered the response to this CR stating that Qwest has reviewed with Repair Managers the necessity to test to the last point of availability and then call/email the customer of record. He also stated that on repair tickets entered electronically the location and circuit access information should be filled in to aid Qwest in making every attempt to fix the problem. Repair technicians have been advised to obtain this information on calls to the repair centers. Bonnie Johnson, Eschelon asked if Qwest was going to enter the information in its systems and Don answered yes. Bonnie also asked if Qwest would dispatch even after hours and Don said they will. It has been validated that Qwest will test to the last point. John Berard, Covad asked if access required information would be in the notes field and Don answered that if entered through CEMR there are specific fields for this information. Bonnie reiterated that if the CLECs have access information then Qwest wants them to pass the information along and Don said yes. This CR will be moved to Development status.

- 2/18/04 CMP Meeting Don Tolman, Qwest stated that Qwest is currently reviewing the request and will provide a complete response in the March meeting. He requested the CR be moved to Evaluation status.

-- 1/21/04 January CMP Meeting Bonnie Johnson, Eschelon presented this CR. It is designed to provide information regarding if the end user customer or building manager is needed to access the demarc. Late in the day some tickets are put in “no access” status by Qwest when the customer was not needed to access the demarc. She is asking that Qwest note in their systems if the customer has to give access to the demarc when Qwest does an install or repair on a going forward basis. (She also stated to Doug Andreen later in the meeting that DS1 and above are the biggest concern because of customer impact). The CR will move to Presented status.

-- 1/7/04 Clarification to statement made in Clarification Meeting 12/18 (see Below) additional information is in parentheeses. Roszan Jarman-Konkel, Qwest said that in the design world, there is an ability to enter three days worth of premise ( and circuit) access(hours via CEMR.)

Clarification Meeting 8:00 a.m. (MDT) / Thursday 12/18, 2003 1-877-521-8688 1456160# PC120903-1 Qwest will track access required information in it’s systems

Attendees

Kim Isaacs, Eschelon Bonnie Johnson, Eschelon Julie Pickar, U S Link Doug Andreen, Qwest Roszan Jarman-Konkel Paul Hanser, Eschelon Curt Anderson, Qwest Tom McAldine, Eschelon Jim Recker, Qwest Jean Novak, Qwest

Doug Andreen read the full title of the CR as follows: Qwest will track access required information in its systems when Qwest installs new service, or when Qwest dispatches on the repair of an existing line/circuit. Qwest will make the information available to CLECs for use when a CLEC opens a repair ticket for a CLEC end user customer.

Bonnie Johnson, Eschelon explained the reason for the request is that a few months ago Eschelon noticed on POTS and Design that numerous tickets were going to a no access status. Through analysis Eschelon found that on certain tickets Qwest did not need access to the premise to clear the ticket. Eschelon then asked Qwest if they track access needs for the Demarc or circuit. The answer was no. The CR therefore is for Qwest to develop a tracking mechanism to track access information in its systems when installing new service or on the repair of an existing line/circuit.

Doug asked if this would be on a going forward basis and Eschelon answered yes.

Tom McAldine, Eschelon gave an example where a ticket is opened at 3 p.m., Qwest troubleshoots till 6 p.m. and finds the trouble to be outside the serving central office. Eschelon cannot contact the customer and the ticket is then put off till 6 a.m. the next day. Tom said in many cases Qwest will find that in order to fix the problem no premise access was required. Tom further stated that Qwest’s policy is to troubleshoot all the way to customer premise.

Curt Anderson, Qwest clarified that what is asked for is to first ensure that Qwest is following process that is now in place and second, to begin tracking access requirements.

Bonnie answered yes, but the CR is not designed for the compliance issue as this is being addressed by other means.

Jim Recker, Qwest asked if Eschelon was asking for the location of the NIU? Bonnie answered yes.

Roszan Jarman-Konkel, Qwest said that in the design world, there is an ability to enter three days worth of premise access.

Jim asked if this were for design or POTS since different systems are used.

Bonnie answered both.

Doug asked of it was fair to say most of the existing problems are on the design side. Bonnie answered yes DS1 and above are the main areas.

Tom added that the main point was looking beyond the end office to the fiber hut etc. i.e. the equipment between the end office and equipment needing premise access.

Bonnie added that some of the existing information on the Qwest work docs is incomplete and Tom agreed. Confirm Areas & Products Impacted All new service and all lines and circuits that require Qwest repair.

Confirm Right Personnel Involved Cathy Garcia needs to be added. Doug will ensure this happens as she is on vacation now.

Identify/Confirm CLEC’s Expectation These expectations were confirmed. 1. Qwest will develop and train a process that will track whether access is required for future repairs for all new installs and repairs to existing lines circuits. 2. Qwest will make the information available to CLECs when a CLEC opens a repair ticket. 3. Qwest will complete any systems work required to implement the process.

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) Bonnie will present the CR at the January CMP meeting with a response being in the February timeframe.


CenturyLink Response

March 9, 2004

For Review by the CLEC Community and Discussion at the March 2004 CMP Meeting

Bonnie Johnson Senior Manager, ILEC Relations Eschelon Communications

SUBJECT: Qwest Change Request Response CR # PC120903-1 Description of CR: Qwest will track access required information in its systems when Qwest installs new service, or when Qwest dispatches on the repair of an existing line/circuit. Qwest will make the information available to CLECs for use when a CLEC opens a repair ticket for a CLEC end user customer.

For example, if a CLEC opens a ticket at 4 PM because a customer is out of service, and the CLEC designates access hours of 8 AM to 5 PM for the customer and Qwest cannot dispatch by 5 PM that day, Qwest could put the ticket in a No Access status until 8 AM the next morning. Eschelon has provided examples to its Service Management team where Qwest put tickets in a No Access status after access hours, the trouble was in the Qwest network and Qwest did not require the customer end user or building owner to provide access. If Qwest tracked Access required information in its systems and made that information available to the CLECs when opening a ticket, the CLEC could set clear expectations for repair intervals with its own customers and Qwest could set clear expectations and interval with the CLECs. Because Qwest does not track this information, the decision is left to Qwest personnel to make a decision on whether Qwest needs access to its equipment. In addition, if Qwest and a CLEC knew when access was required, the number of unnecessary dispatches and associated charges to the CLEC could be reduced.

The Qwest Operations Staff has reviewed the problem described above and have covered this issue with the repair managers of the maintenance centers. The repair managers are covering all technicians on the requirement to test to the last access point in the circuit that is available. When premise access is needed, Qwest technicians will call or send an electronic message to the CLEC to validate access to the network interface devise before establishing No Access time.

Also, the CEMR user online help provides the following information to the CLEC for inputting of their trouble tickets and access information.

The online help is available to the customers at: http://www.qwest.com/wholesale/systems/WebHelp/Introduction.htm This is CEMR version 2.0 and is supported by Netscape Communicator version 7.0 and Internet Explorer version 5.5.

Access Hours (00:00-23:59 Local Time)

Location The location of the premises where the trouble ticket is submitted, for a Qwest technician to access, if required. Enter the earliest and latest times that a Qwest technician can access the premises for three days, starting on the day the trouble report is entered. You must enter the time in the military format, and the earliest time must be prior to the latest time. For example, 8:00 a.m. must be entered as 08:00, and 1:00 p.m. must be entered as 13:00. You cannot use 24:00 to indicate 12:00 a.m. Enter 23:59 instead. If premises access is not available on these dates, enter normal business hours for both the earliest and latest times. Then, in the Description field, enter No prem access until (specific date).

Circuit The location of the circuit, for a Qwest technician to access, if required. Enter the earliest and latest times that a Qwest technician can access the circuit for three days, starting on the day the trouble report is entered. You must enter the time in the military format, and the earliest time must be prior to the latest time. For example, 8:00 a.m. must be entered as 08:00, and 1:00 p.m. must be entered as 13:00. You cannot use 24:00 to indicate 12:00 a.m. Enter 23:59 instead. If circuit access is not available on these dates, please enter normal business hours for both the earliest and latest times. Then, in the Description field, enter No prem access until (specific date).

Additionally, in an effort to strengthen obtaining correct access, Qwest has made it mandatory for the repair answering centers to obtain all access information, circuit, premise and local contacts as they enter the trouble ticket.

Again all technicians will be required to test to the last access point in the circuit that is available. When premise access is needed, Qwest technicians will call or send an electronic message to the CLEC to validate access to the network interface device before establishing No Access time.

Sincerely,

Don Tolman Qwest Communications


Open Product/Process CR PC030204-1 Detail

 
Title: Qwest to develop and implement a Directory Assistance only block.
CR Number Current Status
Date
Area Impacted Products Impacted

PC030204-1 Denied
4/21/2004
Centrex, Resale, Switched Service, Switching, UNE-P, UNE Other
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Stouffer, Jim
Director:
CR PM: Andreen, Doug

Description Of Change

Eschelon requests Qwest develop a block that allows blocking for local directory assistance (411 and 555-1212). Qwest currently only offers the ability to block 411 and 555-1212 through the Custom-net block. Customers do not always want to block direct dial long distance but do have a need to block local directory assistance. Custom-net forces the End User Customer to use an alternate billing method for long distance. Alternate billing for long distance is difficult to use because it requires a calling card or third party billing and can be very costly. Eschelon’s customers are often forced to absorb the cost of unauthorized directory assistance calls because the consequence of fraud or misuse on a calling card can be catastrophic to a business owner. Qwest should provide a blocking in a manner that meets customers needs. Qwest should not “package” directory assistance blocking so that a customer is forced to have additional blocks they do not need. The functionality does exist in at least the DMS100 and 5E switch to block only local directory assistance without requiring a customer use alternate billing for long distance.

Expected Deliverable:

Qwest will offer a block to block local directory assistance calls only without requiring additional blocks that a customer may not need.


Status History

3/2/04 CR Submitted

3/3/04 CR Acknowledged

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to Presented

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/12/04 - Sent Bonnie Johnson email and example of notification with url link to SGAT web site (see below)

__________________________________________________________________________________________

Announcement Date:

April 26, 2004

Effective Date: April 27, 2004

Document Number:

Notification Category: Process Notification

Target Audience: CLECs, Resellers

Subject: Wholesale Interconnection Agreements & Amendments –SGATs

Summary of Change:

On April 27, 2004, Qwest will post updates to its Wholesale Product Catalog that includes new/revised documentation for Wholesale Interconnection Agreements & Amendments – SGATs. This material becomes effective on April 27, 2004.

SGATs:

Qwest is replacing the Wyoming Exhibit A with the correct version dated 10-16-02.

Redline SGAT documents are found at URL: http://www.qwest.com/about/policy/sgats/

Actual updates are found on the Qwest Wholesale Web site at this URL:

http://www.qwest.com/wholesale/clecs/sgatswireline.html

You are encouraged to provide feedback to this notice through our web site. We provide an easy to use feedback form at http://www.qwest.com/wholesale/feedback.html. A Qwest representative will contact you shortly to discuss your suggestion.

Sincerely,

Qwest

_______________________________________________________________________________________________________________


Project Meetings

5/12/04 - Announcement Date: April 26, 2004 Effective Date: April 27, 2004 Document Number: Notification Category: Process Notification Target Audience: CLECs, Resellers Subject: Wholesale Interconnection Agreements & Amendments - SGATs

Summary of Change: On April 27, 2004, Qwest will post updates to its Wholesale Product Catalog that includes new/revised documentation for Wholesale Interconnection Agreements & Amendments - SGATs. This material becomes effective on April 27, 2004.

SGATs: Qwest is replacing the Wyoming Exhibit A with the correct version dated 10-16-02. Redline SGAT documents are found at URL: http://www.qwest.com/about/policy/sgats/ Actual updates are found on the Qwest Wholesale Web site at this URL: http://www.qwest.com/wholesale/clecs/sgatswireline.html

You are encouraged to provide feedback to this notice through our web site. We provide an easy to use feedback form at http://www.qwest.com/wholesale/feedback.html. A Qwest representative will contact you shortly to discuss your suggestion.

Sincerely, Qwest

-- 04/21/04 April CMP Meeting Sandy Foster, Qwest explained that when this CR was opened it was thought that Directory Blocking might be a software option in the switch. This was later found not to be true. Since CustomNet blocks other items along with directory assistance the only other alternative was found to be Customized Routing. If this did not meet the need of the CLECs then a new product would be needed. The CR on that basis was denied. Bonnie commented on the length of time it took to get this denial since it was obvious to her a current product did not exist. Sandy stated it was felt Qwest needed to do due diligence on the CR. Connee Mofffatt, Qwest also stated that she had hoped the software option would have been true. She also added that if it is a product that can be purchased that poses different problem from a translation that needs to be done on each switch. Bonnie asked how to handle this type of request in the future. Kit Thomte, Qwest stated that generally going forward such requests should start with the Special Request Process. Bonnie said that if a product is not currently offered a Special Request is needed, but she understands that on this CR Qwest was looking for an alternative. The CR is denied.

-- 03/17/04 March CMP Meeting Bonnie Johnson, Eschelon presented this CR that requests a block for directory assistance. She is aware that Qwest offers a block through CustomNet but that this product blocks direct dial LD at the same time. Bonnie said long distance blocks can be managed through account codes by the customer. She said she knows the feature is available on the DMS 100 and 5E switches. Connee Moffatt, Qwest stated that this is not a software feature. Bonnie and Connie agreed that the need is for a translation capability rather than an existing software feature. The status will be moved to Presented.

- Clarification Meeting 9:30 a.m. (MDT) Thursday March 11, 2003 1-877-521-8688 1456160# PC030204-1 Qwest to develop and implement a Directory Assistance only block.

Attendees: Kim Isaacs, Eschelon Stephanie Prull, Eschelon Connee Moffatt, Qwest Nancy Sanders, Comcast Emily Baird, POP Communications Doug Andreen, Qwest Sandy Foster, Qwest Bonnie Johnson, Eschelon Carla Pardee, AT&T

1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

2.0 Review Requested (Description of) Change Doug Andreen, Qwest read the full description of the CR as follows: Eschelon requests Qwest develop a block that allows blocking for local directory assistance (411 and 555-1212). Qwest currently only offers the ability to block 411 and 555-1212 through the Custom-net block. Customers do not always want to block direct dial long distance but do have a need to block local directory assistance. Custom-net forces the End User Customer to use an alternate billing method for long distance. Alternate billing for long distance is difficult to use because it requires a calling card or third party billing and can be very costly. Eschelon’s customers are often forced to absorb the cost of unauthorized directory assistance calls because the consequence of fraud or misuse on a calling card can be catastrophic to a business owner. Qwest should provide a blocking in a manner that meets customers needs. Qwest should not package directory assistance blocking so that a customer is forced to have additional blocks they do not need. The functionality does exist in at least the DMS100 and 5E switch to block only local directory assistance without requiring a customer use alternate billing for long distance.

Doug asked Bonnie Johnson, Eschelon if she was asking for one identifier across the region. Bonnie said this would be preferable but Eschelon is not opposed to more if there are differences in switches or regions.

Sandy Foster, Qwest asked if by not blocking long distance is Eschelon leaving themselves open to misuse in that area.

Bonnie answered that there has been a long-standing need for a directory assistance block only without having to use alternate billing for long distance.

Sandy stated that she has not witnessed a need from Qwest customers and wondered why the need from Eschelon customers. Bonnie answered that she does recognize a need among Qwest customers also.

Connee Moffatt, Qwest asked if Eschelon is asking for this on the DMS10 or Erickson switches. Bonnie answered no, not specifically that she had put these two in because she knows the functionality exists.

Emily Baird, POP Telecom said they have several customers who would like to block directory assistance but who need long distance capabilities and use/have codes that manage that inside the line. Bonnie echoed that this is an important point.

It was noted that Comcast and AT&T also support this CR.

3.0 Confirm Areas & Products Impacted All services that have Qwest switch translations

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation Qwest will offer a block for directory assistance calls only without requiring additional blocks that customer may not need.

6.0 Identify any Dependent Systems Change Requests None identified.

7.0 Establish Action Plan (Resolution Time Frame) Eschelon will present the CR at the March CMP meeting with a response being in the April timeframe.


CenturyLink Response

For Review by the CLEC Community and Discussion at the April 21, 2004 CMP Meeting

Bonnie Johnson Director Carrier Relations Eschelon Telecom

SUBJECT: Qwest’s Change Request Response - PC030204-1 Qwest to develop and implement a Directory Assistance only block.

This letter is in response to CLEC Change Request PC030204-1. This CR is a request by Eschelon for Qwest to develop and implement a local service Directory Assistance (411) only block.

Qwest does not currently offer a 411 block on a standalone basis. We have analyzed our existing product offerings and, other than CustomNet, found one option, Customized Routing that Eschelon might be interested in: Customized Routing http://www.qwest.com/wholesale/pcat/customrouting.html

CustomNet http://www.qwest.com/wholesale/clecs/features/customnet.html

If this product offering does not meet Eschelon’s customers’ needs, a request should be submitted using the SRP (Special Request Process) as detailed in your ICA. SRP http://www.qwest.com/wholesale/preorder/bfrsrprocess.html

On this basis Qwest respectfully denies this request as being out of the scope of the CMP process.

Sincerely,

Sandy Foster Product Manager Qwest

-- April 8, 2004


Open Product/Process CR PC030204-2 Detail

 
Title: Qwest will red line and provide the changes made to the SGAT, Amendments and Negotiation Template in its Process notices.
CR Number Current Status
Date
Area Impacted Products Impacted

PC030204-2 Denied
4/21/2004
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Williams, Susan
Director:
CR PM: Harlan, Cindy

Description Of Change

Eschelon requested and Qwest implemented a red line process to notify CLECs of changes to documents and/or PCATs. However, Qwest does not use this red line method or any method to identify changes it is making on SGAT, Amendment or Negotiation Template process notices. Eschelon asks that Qwest red line and provide CLECs with the changes being made in these documents. A CLEC should not have to do a comparison of documents to identify the process changes Qwest is making in the Qwest notices. A CLEC is required to do a comparison to determine the changes that have been made because Qwest does not provide a record of the changes.

Expected Deliverable:

Qwest will send a red line attachment of changes along with the Process Notification for the SGAT, Amendment and Negotiation Template.


Status History

3/2/04 CR Submitted

3/3/04 CR Acknowledged

3/5/04 Contacted CLEC to schedule Clarification call

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/21/04 - April CMP meeting notes will be posted to the project meeting section


Project Meetings

April 21, 2004 CMP Meeting notes: Cindy Macy – Qwest reviewed the response for this CR. Cindy advised that Bonnie and I have been passing emails on this CR. Bonnie Johnson explained that Eschelon is just asking for the document to be attached to the notification or linked. We are not asking to change the process. Cindy advised that this CR is being denied as these documents are outside of the scope of CMP. The notices that are sent for SGAT, Amendments and Negotiation Templates are non CMP notices. Cindy clarified the difference between a CMP and non CMP notice. CMP notices have a Level 1-4 associated to them. Liz Balvin – MCI advised that the request is to make a process change to the notification process which is part of CMP. Cindy clarified that there are two parts to this CR. There is the request to link the notice to the documents and to also produce these documents in redlined format. Jarby Blackmun – Qwest advised there would be issues with space limitation on sender and receiver’s mailbox if we attached the SGAT to the notice. Bonnie advised she did not ask for redlined versions of the Amendments and Negotiation Templates, even though she thinks they should be produced. Bonnie advised she just wants to have the redlined SGAT linked to the notification so they do not have to search a website for the document. Bonnie advised that she will use the right process to ask for further assistance on the other documents. Cindy agreed that she would hold an internal meeting to determine if we can provide a link to the redlined version of the SGAT. Kit Thomte – Qwest advised that this CR will stay in denied status, but we will open an action item on the linking question. This CR will move to Denied Status.

March 17, 2004 CMP Meeting notes: Bonnie Johnson – Eschelon advised that we held a clarification call on Monday. Bonnie worked with Neil Houston during the call to show him on the website what she was requesting. She believes Qwest understands what Eschelon is requesting. Bonnie explained that they are not requesting for Qwest to change the process, just to attach either the redlined document (SGAT, Amendments and Negotiations Templates) to the notices or to provide a direct link to the document. Bonnie explained they just want access to the document so they know what is being changed. Currently there is a link to a web site, and then you have to search for the document on the web site. Bonnie would like the notice to have a direct link to the document, in redlined version. This CR will move to Presented Status.

PC030204-2 Redline SGAT, Amendments and Negotiation Templates

Clarification Call March 15, 2004 3:00 – 4:00

In attendance: Neil Houston – Qwest Cindy Pierson – Qwest Bonnie Johnson – Eschelon Cindy Macy – Qwest Kim Isaacs – Eschelon

Cindy Macy – Qwest opened the call and reviewed the agenda.

Bonnie Johnson – Eschelon reviewed the CR. Bonnie explained that they are having some degree of difficulty when reading the notices to determine what has changed to the SGATs, Amendments and Negotiations Templates. Bonnie would like to have a redlined version linked to each notice when changes are made to these documents. Currently a link is provided but it is to a web site and then you have to look for the right document. Bonnie would like the documents linked, just like the PCATs are linked to the notices. Bonnie explained she does not want to change the process; she just wants access to the documents that are changing. Bonnie stepped through the path to the documents, and explained how she would like that changed.

Cindy Pierson – Qwest asked if the documents are on the document web site, does this make it part of the CMP process. Bonnie advised that it doesn’t have to be part of CMP. Level 1 notices do not have comment cycles.

Cindy Macy – Qwest verified that these are changes to the state level documents, not to individual CLEC documents. Bonnie agreed and advised she is not asking to change the process; she just needs to understand what has changed.

The team agreed that they understand the request. Next steps are for Bonnie to present the CR at the March CMP meeting, and for Qwest to provide a response at the April CMP meeting.


CenturyLink Response

April 14, 2004

For Review by CLEC Community and Discussion at the April 21, 2004 CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: Change Request Response – CR #PC030204-2 ‘Provide Redline SGAT, Negotiation Template and Amendments in its Process notices’

This letter is in response to Eschelon’s Change Request (CR) PC030204-2. This CR requests that Qwest provide redlined versions of its SGAT, Negotiation Template and Amendments in its Process notices.

Qwest denies this CR on the basis that it is outside the scope of the Change Management Process as SGAT, Negotiation Template and Amendment documents do not fall within CMP.

The CLEC community currently has multiple avenues to provide input to the Amendment documents. These documents are then migrated into the SGATs. In addition, Qwest already provides redline versions of the SGAT documents via a link from the Wholesale web site.

Sincerely,

Qwest Communications


Open Product/Process CR PC070804-1 Detail

 
Title: Develop more efficient and effective process for ASR jeopardies
CR Number Current Status
Date
Area Impacted Products Impacted

PC070804-1 Completed
9/10/2012
Ordering and Provisioning All products where CLEC sends an ASR
Originator:
Originator Company Name: Eschelon
Owner: Sunins, Phyllis
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Qwest notifies a CLEC of an ASR jeopardy via a phone call or voice mail message. This is not an effective or efficient process because there is no record of that the jeopardy notification for the ASR. For a CLEC to effectively manage jeopardies on services the CLECs order for their customers, CLECs require some record (non verbal) of the jeopardies Qwest sends to the CLEC with consist information on the jeopardy. For example, each CLEC may have a different process to manage jeopardies. Qwest should provide consistent information in a template format and provide the information using a process that allows a CLEC to chose how they would like to manage jeopardies. Qwest currently uses the phone and voice mails to notify CLECs of ASR jeopardies. This process is not consistent with LSRs and does not allow the CLEC to a choice on how to manage their jeopardies. The CLEC cannot use the same internal process for ASRs as LSRs because the process is so different. If the C:LEC Service Delivery representative is not available at the time Qwest calls, or is not able to retrieve the message for any reason, potentially Eschelon could be unaware of the jeopardy for a period of time. This could cause delays in delivery of service to the customer. In addition, there could be disputes about dates, times and content of conversation held between Qwest and CLEC when Qwest calls the CLEC. Qwest should use the same process as Qwest uses for LSRs, even if the mode of communication cannot be system generated. E-mail with a standard template (like LSR jeopardy notices) would be more efficient for CLECs. Qwest recently implemented a new process using E-mail for providing a CLEC status on a LSRs after order/LSR completion. Qwest should consider the same kind of solution for ASR jeopardies.

Expected Deliverables: Qwest and CLEC will collaboratively develop a new process for ASR jeopardies that provides the CLEC consistent jeopardy information in a non-verbal communication mode.


Status History

7/8/04 - CR Submitted

7/8/04 - CR Acknowledged

7/12/04 - Contacted Bonnie at Eschelon to schedule clarification call for 7-20-04

7/20/04 - Held Clarification call - this CR will be presented at the August CMP meeting

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database

10/20/04 - October CMP Meeting minutes will be posted to the database

11/17/04 - November CMP Meeting minutes will be posted to the database

12/14/04 - Scheduled ad hoc meeting for Jan 10

12/15/04 - December meeting minutes will be posted to the database

1/10/05 - Ad hoc meeting held

1/19/05 - Jan CMP Meeting minutes will be posted to the database

2/2/05 - Notification of ad hoc meeting sent CMPR.02.02.05.F.02525.CMP_Ad_Hoc_mtg_PC070804-1 scheduled for 2/14/05 2:30 pm mtn

2/14/05 - Ad hoc meeting held

2/16/05 - Feb CMP Meeting minutes will be posted to the database

02/21/05 - Related Change Request PC022105-1 - This CR will be changed to Deferred Status as a result of PC022105-1

3/16/05 - March meeting minutes will be posted to the database

4/14/05 - Changed status to Closed/archived


Project Meetings

08/15/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that in the July meeting, CenturyLink had asked the owner of each Deferred CR to determine if it should remain in Deferred status, is it should be Withdrawn, or whether it should be re- evaluated. Mark then reviewed the status of each CR as listed on the Attachment:

PC070804-1 Develop more efficient and effective process for ASR jeopardizes - CR Status changed to Closed. Per Kim Isaacs, Integra: CR can be closed with a note that this request was met when Qwest implemented the C/NR in QORA.

Kim Isaacs – Integra wondered if the CR should show Closed or show as crossed over to systems.

Susan Lorence – CenturyLink said she was going to investigate when this functionality was implemented and reference that CR and then show the CR as Completed.

Kim Isaacs – Integra agreed.

March CMP Meeting Minutes: Jill Martain - Qwest advised that this CR will move to Deferred Status as Qwest will work the 'initial jeopardy email' piece of this CR using PC022105-1. Bonnie Johnson - Eschelon advised that she issued the new CR as she wanted the CR titled to reflect accurately what Qwest is doing. Bonnie agreed to move forward with the piece that Qwest will implement and Bonnie advised that it is okay to move this CR to Deferred Status.

February CMP Meeting Minutes: Cindy Harlan - Qwest advised that Qwest held an ad hoc call on Monday February 14. The purpose of the call was to review Qwest's proposed process and obtain a decision from the CLEC community regarding whether to move forward or defer the CR. Bonnie agreed that she would provide a decision at the February CMP Meeting. Bonnie Johnson - Eschelon reported at the February CMP meeting that she took this back internally and would like to move forward implementing the email on initial facility jeopardy notifications. Bonnie advised that she is deciding how she wants to move forward with the CR. There was some discussion around either moving forward with the existing CR or deferring the existing one and creating a new one. Bonnie advised that she does not want to loose the work that has been done as the CLECs may want to revisit this, if something changes at Qwest as it may be possible to implement the rest of this CR at a later time. Cindy Harlan - Qwest advised we can work together to determine how to implement some of the work and defer the rest. Liz Balvin-Covad asked who would receive the email jeopardy. Jill advised an email address needs to be populated in the initiator field on the ASR and that is where the email jeopardy would be sent. Jill advised that Qwest has internal work that needs to be done to implement this. This CR will remain in Development Status.

PC070804-1 ASR Jeopardy Process Ad Hoc Call February 14, 2005

In attendance: Jeff Sonnier – Sprint Cindy Dahlstedt - Qwest Communications Bill Trefts – Time Warner Communications Bonnie Johnson – Eschelon Bob Eggert – SBC Rosyln Davis – MCI Kathy Oaken - Qwest Communications Doug Denny – Eschelon Phyllis Sunins - Qwest Communications Cindy Harlan - Qwest Communications

Cindy Harlan reviewed the history of the CR. This CR requested that a process similar to LSR jeopardy process be implemented for ASRs. Qwest reviewed the ASR jeopardy process and offered to provide a email jeopardy on initial facility jeopardy condition (pre-RID), on Post RID jeopardy condition, and to utilize the current CNR jeopardy process. Cindy explained that the CLECs mentioned a concern regarding ‘piece parting’ the process and causing inconsistencies, but would check with their organization and provide feedback during this ad hoc call.

Bonnie Johnson – Eschelon recapped her concern about the process being inconsistent and using different methods. Bonnie explained that Eschelon didn’t want to defer the CR without getting other CLEC input. Bonnie advised that the Qwest representatives (who work the process delay orders on ASRs) in Des Moines are experienced and changing the process may cause inconsistencies. Bonnie said if Qwest implements the email jeopardy on the initial facility jeopardy, Eschelon would like the CR functionality request that Qwest is unable to provide to stay in deferred status, as something may change in the future and allow Qwest to implement her request. Bonnie further explained that some type of system or process change, or center movement may occur that creates an opportunity for Qwest to look at this request again.

Bill Trefts – Time Warner expressed his desire to have Qwest implement the email jeopardy on the initial facility jeopardy condition. Bill advised he is the Escalations manager and when the Time Warner representative gets a voice message, the rep can be on vacation and Time Warner is not able to address the jeopardy. Phyllis Sunins – Qwest advised the CLECs would need to set up a ‘group email box’ that allows multiple people to access, otherwise, if the initiator is on vacation and no one is checking their email, the same problem would occur. Phyllis clarified that the Qwest representative would not call if no response was received via the email. The email initial jeopardy would have basic information on it as currently sent for LSR jeopardy notifications, e.g. Jeopardy Code & explanation. Next steps in the process are that Qwest would provide an FOC if a date became available, or call within 72 hours to provide additional jeopardy information.

Bonnie said it sounds as if the CLECs would like to consider implementing the email jeopardy on the initial facility jeopardy only. Bonnie advised Eschelon would prefer to have the full functionality that was requested on this CR, and if we implement the initial jeopardy, Eschelon would still like to have the request stay on the back burner, maybe put in defer status. Bonnie said that Qwest could implement the initial jeopardy with a new CR, and place this CR in deferred status. Cindy Harlan – Qwest agreed that we can determine the best way to handle the logistics of the CR.

Cindy Harlan – Qwest asked the other CLECs if they had additional input from their organizations. Jeff Sonnier – Sprint advised he does not have specific information from his organization as they use LSRs primarily, and he does not work on the ASR side. Phyllis advised that the Sprint Service Manager, Mark Tsypin worked with Sprint on the ASR side. Phyllis advised Jeff to contact Mark to discuss further.

Roslyn Davis – MCI advised using email is acceptable. Roslyn asked if Qwest would call if there is not a response to the email. Phyllis explained that the e-mailed jeopardy notification of a facility problem would be a 1 way communication . Phyllis advised that Qwest would not call to follow up on that the initial e-mailed facility jeopardy was received. The only initial facility notification would be the email jeopardy. The next step of the process is either the FOC or a phone call within 72 hours to provide more information. Phyllis advised the CLECs that they would need to set up a ‘group or community email box’ for this process to work effectively.

Bonnie advised she would like to take this back and discuss again. Bonnie advised she will provide status and a decision at the Feb. 16 CMP meeting. Phyllis advised if Qwest does move forward with the email initial jeopardy notice on facility conditions, Qwest has internal work that needs to be done. Bonnie advised okay and will provide an update at the February CMP meeting.

January CMP Meeting Minutes Cindy Harlan/Qwest advised that an ad hoc meeting was held on January 10th and Qwest proposed the following jeopardy process. The email jeopardy could be sent Pre-RID which would addresses the initial facility jeopardy, a Post-RID email jeopardy could be sent at due date, and continue utilizing the existing CNR jeopardy process. Cindy advised that during the January 10th ad-hoc call that Eschelon expressed that they wanted to receive the 72 hour jeopardy details via email. Qwest is unable to provide this jeopardy via email due to the manual efforts involved. As a result of the ad hoc call the CLECs agreed to take this back to their operations centers to see if the recommendation would work. Bonnie Johnson/Eschelon advised their view is that if we piece part the process it may do more harm than good. Right now, the process is consistent and experienced people are performing the process. If we piece part the process, each stage of the process would be handled differently and cause confusion and provide an opportunity to not be in compliance. Bonnie said Eschelon does not need another process to measure compliance on. Bonnie asked the other CLECs to take the issue to internal operations personnel and get feedback. Jill Martain/Qwest advised that we will then schedule another ad hoc meeting to review this with the CLEC Community. Bonnie suggested that we could possibly put the CR in Deferred Status. Bonnie said that if for example, Qwest were to shift work from the current centers and new people are doing the work we could reinstate the CR. Jill advised we can schedule an ad hoc meeting to get input for other CLEC operational organizations and then determine next steps or Deferring this CR. This CR will remain in Development Status.

PC070804-1 ASR Jeopardy Process Ad Hoc Meeting January 10, 2005

In attendance: Phyllis Sunins - Qwest Cindy Dahlstedt – Qwest Sharon Van Meter – ATT Jo McCleen – ATT Amanda Silva – VCI Bob Eggert – SBC Bonnie Johnson – Eschelon Jennifer Arnold – TDS Metro Roslyn Davis – MCI Cindy Harlan – Qwest Gary Pierce – DSAT

Cindy Harlan – Qwest reviewed the history of this CR and the purpose of the meeting. Cindy explained that the team has met several times. At the last meeting Qwest offered to implement an email jeopardy process for the initial jeopardy only. The CLECs requested for Qwest to go back and see if an email process for the entire life cycle of the jeopardy and for all jeopardy types is possible.

Phyllis reported that Wholesale has looked at the request and determined that we can provide notifications in 1 of 3 ways:

PRE-RID: Implement a process that addresses the initial facility jeopardy. POST-RID -Network has an existing process that addresses a jeopardy at due date. CNR - CNR jeopardy process is currently available and would not change.

Phyllis summarized that Qwest can offer a pre-RID email jeopardy that is sent to the email id in the initiator field on the ASR if populated. Cindy Dahlsteadt explained the PTA post RID jeopardy process. The CLEC would have to be set up to have PTA (provider test access). A test is done on PTD and the test results are emailed to the CLEC. The order is closed on the due date (5 days later). The jeopardy goes out on the due date, not PTD. This is for Qwest jeopardy, not CNR.

Sharon Van Meter – ATT asked if this is for all products types. Phyllis advised yes it would be for any product ordered via ASR. . Bonnie Johnson – Eschelon, said she was looking for something that resembled the LSR jeopardy process. Bonnie advised what she is looking for is the jeopardy that is sent within 72 hours, that has more detailed information, to be sent via email.

Phyllis advised that we have looked at the process and we are trying to make a process work with the resources that we have. We are not able to provide the 72 hour jeopardy via email as that increases the manual work. We did received objections from an IXC customer and we have to develop a process to meet their needs too.

Sharon Van Meter – ATT asked if it would help the manual effort if the process was just for local service first and then add the IXC customer later. Bonnie advised she needs this process for Private Line customers.

Bonnie advised they need to know the level of detail on the jeopardy so they know whether they should offer other alternatives to their customers. Bonnie said she will check with her operations centers and see if they can make Qwest’s recommendation work.

Phyllis also said that based on the feedback, Qwest does have internal work to do to accomplish the PRE-RID e-mail notification so we can’t implement the PRE-RID process until that is complete. We will leave the CR in development until the delivery date is determined.

Sharon Van Meter – ATT confirmed that the meeting notes will capture the summarized process so the CLECs can all check with their organizations and provide status back to Qwest.

Cindy Harlan – Qwest advised notes will be taken and posted to the web. Qwest will Look for status from the CLECs in the near future.

December CMP Meeting Minutes Cindy Macy – Qwest advised an ad hoc meeting is scheduled for January 10. We are reviewing this request internally and having discussions with our customers who order via an ASR to determine impacts. Liz Balvin – Covad asked if this CR is specific to Interconnect products and if it is could that information be put on the meeting notification. Jill Martain – Qwest advised that Eschelon did request for this process to apply to all products ordered via an ASR. Kim Isaacs asked Cindy Macy to verify that we did include PLT. Cindy advised yes PLT was specifically requested. Cindy advised that during the last ad hoc meeting Qwest presented an option and the CLEC community was not happy with that option and asked Qwest to expand the scope for it to cover all jeopardy types and the entire life cycle of the jeopardy. Qwest has been reviewing the request based on a process that supports all products. Jill advised that although Qwest is reviewing this process for all products that the specific products/process for this forum is specifically around Interconnect products. Qwest will review our findings at the ad hoc meeting in January. This CR will remain in Development Status.

11/17/04 November meeting minutes Phyllis Sunins – Qwest advised we held an ad hoc meeting on November 12. Phyllis reviewed the CR request and advised that Qwest proposed that we could send an email jeopardy on the initial jeopardy by responding to the email address that is populated in the initiator field on the ASR for jobs held for engineering. Phyllis advised issues were discussed regarding the email field and whether this should be required or not. (insert comment from Eschelon) AT&T expressed concern about making the E-Mail field mandatory (end comment). Some CLECs had concerns and they expressed if this was changed (insert) and that field was made a mandatory field that (end insert) it needs to be coordinated with an ASOG release. The CLECs would need to identify the impacts to their organizations as they would potentially need a separate email address to receive the jeopardy from Qwest. The request was made to extend the email jeopardy process to all jeopardy conditions, not just K jeps, and the entire life cycle of the jeopardy, not just the initial jeopardy. Qwest will review the request and another ad hoc meeting will be scheduled for a later date. This CR will remain in Development Status.

PC070804-1 ASR Jeopardy Process Ad Hoc Meeting November 12, 2004

In attendance: Liz Balvin – Covad Diane Friend – Time Warner Sharon VanMeter – ATT Stephanie Prull – Eschelon Tomas Soto = SBC Phyllis Sunins – Qwest Cindy Macy – Qwest Terri Lee – SBC Lori Nelson – Mid-Continent Comm Jeff Sonier – Sprint Lynn – ELI Bonnie Johnson – Eschelon Bonnie Marnie – TDS MetroComm

Cindy Macy – Qwest reviewed the CR and explained that Eschelon requested that Qwest provide email jeopardy notifications so the process is more consistent with the LSR jeopardy process and that the jeopardy information is documented.

Phyllis Sunins – Qwest reviewed the draft process that Qwest put together. Phyllis explained that the ASR process is not as mechanized as the LSR process. Phyllis explained with the new ASR process the notification would go to Interexchange and Wireless customers also. The key action that the CLEC needs to take is to populate the email address in the field on the ASR. Phyllis advised Qwest would create an email jeopardy notification that will be patterned after the information that is provided on the LSR jep. The format will be different as the LSR jep is generated by a system. The ASR jep would be generated manually and sent via email.

Bonnie Johnson – Eschelon thanked Qwest for including the other Interexchange products and customers in this process. Bonnie asked what information would be on the email? Would the same jep codes be used for ASRs as LSRs? Phyllis advised yes for UBL and Interexchange products. Phyllis advised that PCAT would be sent out for CLEC review as part of this CR.

Bonnie Johnson – Eschelon asked why is this just for the initial jeopardy? Phyllis advised in the LSR world we have the jeopardy process mechanized and the conditions are different between LSRs and ASRs. Phyllis explained there are several other variables and process changes that would have to be developed if we look at more than the initial jeopardy. For example the time frame for the CLECs to respond on an ASR jep would have to be determined. The process becomes much more manual as the systems are not mechanized and for Qwest to pull the information needed and create the manual jeopardy notification is more time consuming than making a phone call.

Phyllis advised she would like to start with the draft process that she proposed and look at improving it, if possible, at a later date. Qwest feels that we can send an email jeopardy notification on the initial jeopardy if there is an engineering job opened. This would be for K jeps only. Phyllis advised we would follow the same patter as LSRs as we will provide the initial jeopardy via email and then follow up 72 hours later to provide additional information. The second jeopardy that provides more information would be a phone call. Bonnie Johnson – Eschelon advised this is the situation that they need and want the information to be in writing. Phyllis advised there is not mechanization in place to do this.

Bonnie Johnson – Eschelon asked if Qwest could change the process to include only K jeopardy notifications but for the entire life cycle, not just for initial jeps. Phyllis advised this increases the cycle time for the SDCs. Phyllis asked if the second email would need to carry the initial jeopardy information? This would require a single mail location for all jeps to be sent from.

Bonnie asked what the time frame is today for a call back from CLECs on phone call jeps? Phyllis advised Qwest has an open but reasonable time frame. Phyllis advised the work goes back and forth between Qwest and the CLECs for approximately 10-20% of the K jeps, so it becomes an interactive process. Bonnie advised the CLECs prefer the entire flow be done via email.

Phyllis explained the additional work will impact the SDCs. Bonnie asked how it would impact the SDCs. Phyllis explained that today they place a phone call and can resolve the issue verbally. Tomorrow we will have to manually check each ASR to determine how to handle it (phone call or email) and gather data to populate the email template.

Diane Friend – Time Warner asked if Qwest required the email field to be populated. Phyllis advised no, that OBF says it is optional. Phyllis advised approximately 80% is populated today. Diane said that Qwest could make it a required field, but they would have to notify all of their operating partners and it would have to be implemented with an ASOG upgrade. ATT expressed their concern if Qwest tries to make it required, as they would have to make programming changes. Qwest is also concerned that if the emails are not monitored it could increase calls into the centers.

Phyllis advised this process would impact the CLECs operating centers also as they would need to make sure they had a designated email address that could be used, or each representative would have to have their own email addresses, and if they were gone the jep would not be worked.

Bonnie asked if we could look at the process and see if we could extend it to the entire jeopardy life cycle for either all jeps or just K jeps.

Cindy Macy – Qwest advised that Qwest looked at the process and determined that we could provide an email jep on initial K jeps only. The process has many variables and became very manual if we provided email jeps on anything else. Phyllis agreed that we can review the request and see if there is anything that we can do.

Phyllis agreed our next steps are to look at the ASR email field (optional or required) and to check the feasibility of sending additional jep notifications via email. We will have to look at the impacts to our centers. Qwest will do further investigation and have another ad hoc meeting.

The CLECs need to determine the impact to their operations also, as this change will impact their centers also.

10/20/04 CMP Meeting Minutes Cindy Macy – Qwest advised that this process is under development. We are planning on holding an ad hoc meeting to review the draft process in early November. Bonnie Johnson – Eschelon asked if we are able to include Private Line Services in the process. Jill Martain – Qwest advised that we are including this product in the review. It is too soon to tell if it will be accepted but we are looking at the process for all products. This CR will remain in Development Status.

9/15/04 CMP Meeting Minutes Cindy Macy – Qwest reviewed the CR request and advised that Qwest is accepting this CR. Qwest is developing a draft ASR Jeopardy process that will focus on Interconnect products ordered via the ASR. Bonnie Johnson – Eschelon commented that the response states that Qwest is focusing on Interconnect products. Bonnie advised that the CLEC Community needs this process to handle additional products ordered via the ASR process, in particular PLT services. Jill Martain – Qwest advised that our focus is on Local Interconnect products as that is what CMP addresses, but Qwest will review the other products and determine what makes the most sense. Bonnie asked what other forum is available for the CLECs to use to address the other products. Jill advised that we will have that discussion if the decision is to not include additional products but for now we will continue working on the draft process. Cindy Macy advised that ad hoc meetings will be set up to review the draft process. This CR will remain in Development Status.

8/16/04 CMP Meeting Mintues Bonnie Johnson – Eschelon presented this CR. Bonnie explained that Eschelon previously submitted a systems CR that Qwest denied for economic reasons. Eschelon understands that this process can not be fully mechanized, but would like an electronic notification that is similar to LSRs. The current ASR jeopardy process is done via voice mail. This doesn’t provide any consistency or tracking. The Clarification Call was held and Eschelon did request the PLT product to be included in this process. Eschelon wants PLT included, especially with Qwest’s TRO position on Unbundled Loop. This CR will move to Presented Status.

PC070804-1 Develop more efficient and effective process for ASR jeopardies Clarification Call July 20, 2004 12:00 1:00

In attendance: Phyllis Sunnis Qwest Liz Balvin MCI Kim Isaacs Eschelon Stephanie Prull Eschelon Connie Nelson US Link Paul M Johnson Qwest Cindy Macy Qwest

Cindy began the call and introduced the attendees. Cindy reviewed the agenda and asked Bonnie Johnson Eschelon to review the CR with the team.

Bonnie Johnson Eschelon advised that she submitted a systems CR asking for mechanized jeopardy for QORA and requested an interim manual process until the system work could be done. The system CR was denied for economically not feasible reasons. Qwest also stated there were issues as this process affects Interexchange customers. Bonnie advised Qwest that if this impacts Interexchange customer they should be included, as she is okay with them attending the meetings. Bonnie was advised to issue a Product Process CR. Additional conversation occurred with Qwest stating that the CMP process is for CLEC customers, not Interexchange customers, so the analysis that is done is based on impacts to Interconnection processes and customers. We do not utilize the CMP process to implement process for Interexchange customers. We only use the CMP process for Interconnection. Qwest also stated that if the process works for Interexchange than it may be implemented, but that would be handled outside of CMP.

Bonnie continued to review the CR with the team. Bonnie explained that the voice mail process for ASR jeopardies leaves room for problems, lack of communication, and no documentation. Bonnie would like to work with Qwest to develop a more efficient and effective process. Bonnie would like for Qwest to look at an alternative such as email. The process that is used for ‘Notification after completion’ may work as a model as it was developed manually first. The voice mail process does not always work as we have a group that manages jeopardies and if we can’t auto forward information to this group it causes delays. Bonnie advised they would like consistency to the LSR side; such as a standard form, standard jeopardy codes. When a jeopardy code is used, it means the same thing whether it is an ASR or an LSR. Eschelon would like an alternative to voice mail.

Liz Balvin MCI advised that it is appropriate to work together to get the process cleaner and to use appropriate jep codes and reasons. This will benefit everyone.

Bonnie stressed that Eschelon has no objection to including IXC and Wireless customers if we need an open forum. Bonnie said that their main focus is LSRs, but with TRO, if Qwest gets their wish, DS1 capable loops go away and Special Access will increase, thus increasing ASR activity.

Phyllis Sunnis Qwest advised that based on past history on the LSR side we have made improvements in this area. We will have ad hoc meetings to discuss this process and work to make it more consistent and efficient. Phyllis advised that for CMP purposes we focus on Interconnect products so we can meet the CLEC needs. We do not want to impede the CMP process with additional players. We want to address the CLEC concerns first. This does not preclude the process from being implemented for additional ASR products, but that will not be included in the CMP process for this CR.

Liz Balvin MCI asked if we have different personnel that handle ASR and LSRs. Phyllis advised it depends on the function, such as ordering, provisioning and billing. Liz stated that wouldn’t Qwest want a standard process for personnel to follow. Phyllis advised that the CMP process is for CLEC needs. Qwest may choose to implement a process for both LSR and ASR products but the focus with this CR is for Interconnect products handled via an ASR. These products include LIS, UDIT, UDF, 911/PS ALI.

Cindy Macy Qwest recapped that CMP is for Interconnection products and certain Interconnection products are handled via an ASR.

Bonnie asked if Private Line was included. Phyllis advised it does not include Private Line that is ordered out of FCC #1 tariff. Bonnie asked how could that product be included. Phyllis advised she will have to check further. Bonnie advised the DS1 capable loop is the CLEC comparable to the Private Line for Retail.

Cindy advised that Qwest will begin to work on this CR. This CR will be presented by Eschelon at the August CMP meeting.


CenturyLink Response

September 8, 2004

RESPONSE For Review by the CLEC Community and Discussion at the September 16, 2004 CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response - PC070804-1 “ASR Jeopardy Process”

Eschelon is requesting Qwest to develop a more efficient and effective process for ASR jeopardizes. Eschelon would like a process that provides consistency and tracking

Qwest accepts this CR and is in the process of developing an ASR Jeopardy Process that focus’ on the Interconnect products ordered using the ASR process. Qwest will schedule ad hoc meetings to review the draft process with the CLEC Community. This CR will move to Development Status.

Sincerely,

Phyllis Sunins Process Specialist


Open Product/Process CR PC081403-1 Detail

 
Title: Jeopardy Notification Process Changes (new title). Delayed order process modifed to allow theCLEC a designated time frame to respond to a released delayed order after Qwest sends an updated FOC (old title).
CR Number Current Status
Date
Area Impacted Products Impacted

PC081403-1 Completed
7/21/2004
Provisioning Private Line, Resale, Unbundled Loop, EEL (UNE-C), UNE-P
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Sunins, Phyllis
Director:
CR PM: Harlan, Cindy

Description Of Change

Changed the description of this CR as a result of synergies with PC072303-1. During the October 15 CMP meeting we discussed whether we should close/leave open/ or update CR PC081403-1 'Delayed order process modified to allow the CLEC a designated time frame to respond to a released delayed order'. The reason we wanted to close/leave open or update PC081403-1 is because PC072303-1 is meeting many of the needs. Bonnie Johnson agreed to change this CR, as long as we retained the original CR description.

********************************************************************************

Change Jeopardy Notices sent on DVA and PTD for Designed Services

After analysis of Due Dates that are being missed when jeopardy

notices are sent prior to the Due Date, Qwest is proposing that only

specific jeopardy conditions be sent to the CLEC on the critical date of DVA

and PTD. On DVA, Qwest would prefer to only send jeopardy notices for

facility and plug-in issues. The jeopardy codes would be those that start

with a "K" (facility reasons) or on a jeopardy code of V25 (PICS/BRI

plug-ins required.) For the critical date of PTD, Qwest would continue to

send all jeopardy notices except those that end in "33" (work force issues)

i.e., B33, E33, P33. The reason for eliminating the "33" jeopardy code is

due to the fact that Qwest is not missing Due Dates for this reason and is

causing unnecessary jeopardy notices being sent to the CLEC. Along with these proposed changes, Qwest would also like to hear suggestions from the CLEC community any changes they feel would benefit the overall jeopardy notification process. Changes being implemented with PC072303-01, Expanding the Jeopardy Notifications to 6 p.m. Mountain Time are also helping the overall jeopardy process.

Expected Deliverable:

Change the jeopardy notification process to reduce unnecessary

jeopardy notices being sent to the CLEC when the Due Date is not in jeopardy

and to improve the overall jeopardy notification process.

***********************************************************************************

Qwest will contact the CLEC to test and accept only after the updated FOC has been sent and a designated time frame has passed. Qwest will not put the order in a CNR (customer not ready) jeopardy status until this time frame has passed and the CLEC is not ready.

When Qwest puts a CLECs request in delayed for facilities jeopardy status, Qwest should be required to send the CLEC an updated FOC when the delayed order is released and allow the CLEC a reasonable time frame to prepare to accept the circuit. Qwest releases orders form a held status (in some cases the CLEC has not even received an updated FOC) and immediately contacts the CLEC to accept the circuit. Because Qwest does not allow the CLEC a reasonable amount of time to prepare for the release of the delayed order, the CLEC may not be ready when Qwest calls to test with the CLEC. Qwest then places the request in a CNR jeopardy status. Qwest should modify the Delayed order process, to require Qwest to send an updated FOC and then allow a reasonable amount of time for the CLEC to react and prepare to accept the circuit before contacting the CLEC for testing.

Expected Deliverable:

Qwest will modify, document and train a process, that requires Qwest to send an updated FOC and allow a CLEC a reasonable amount of time (from the time the updated FOC is sent) to prepare for testing before Qwest contacts the CLEC to test and accept the circuit. Qwest should cease applying a jeopardy status of CNR to delayed orders that are released and the CLEC has not been provided a reasonable amount of time to prepare to test/accept the circuit.

This should apply to all orders where the delayed order process is followed and testing is required.


Status History

08/14/03 - CR Submitted

08/15/03 - CR Acknowledged

8/19/03 - LWTC for Bonnie regarding Clarification Meeting

8/26/03 - Held Clarification Call

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/6/03 - Held CLEC Ad Hoc call to discuss synergys between this CR and PC072303-1

10/8/03 - Sent response to CLEC

10/10/03 - Sent email to Bonnie to request change of statusto withdraw due to syncergy's with other CR PC072303-1

10/13/03 - Bonnie advised she would like to keep open and reference PC072303-1 and Jill's new CR when it is issued

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section

10/30/03 - Changed the description of this CR as a result of synergies with PC072303-1. During the October 15 CMP meeting we discussed whether we should close/leave open/ or update CR PC081403-1 'Delayed order process modified to allow the CLEC a designated time frame to respond to a released delayed order'. The reason we wanted to close/leave open or update PC081403-1 is because PC072303-1 is meeting many of the needs. Bonnie Johnson agreed to change this CR, as long as we retained the original CR description.

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/1/03 - Scheduled CLEC ad hoc meeting for 12/8/03 to review jep codes/content

12/5/03 - CMPR.12.05.03.F.01144.JeopardyProcessHandout

12/8/03 - Held ad hoc meeting to review jep codes / content

12/17/03 - Dec CMP Meeting notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/4/04 - Held ad hoc meeting with CLECs

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4//12/04 - Sent document to document review site

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section


Project Meetings

July 21, 2004 CMP Meeting notes: Cindy Macy – Qwest advised that this CR was implemented May 27. Qwest would like to close this CR. Bonnie Johnson – Eschelon advised she is having a problem with compliance to this process. Bonnie asked if there is additional work going on for this CR? Jill advised we put the process in place to identify and work critical jeopardy codes so the CLECs do not have to worry about the interim jeopardy codes. In addition the process includes providing additional details on the jeopardy within 72 hours if we are not able to send an FOC within that time frame. Jill Martain – Qwest asked if this is a compliance issue or a process problem. Bonnie said it is hard to determine at times, but she is willing to close this CR and handle the compliance issue with the Service Manager. The CLECs agreed to close the CR.

June 16, 2004 CMP Meeting notes: Cindy Macy – Qwest advised this process was implemented May 27. No comments came in for this CR. We would like to move this CR to CLEC Test Status.

May 19, 2004 CMP Meeting notes: Cindy Macy – Qwest advised this process will be implemented May 27. No comments were received. Cindy thanked Phyllis Sunins and Jill Martain for all of their work on this CR. Qwest held several input sessions with the CLECs to work out issues prior to releasing the documentation. This CR will remain in Development Status.

April 21, 2004 CMP Meeting notes: Phyllis Sunins – Qwest advised that the updates to the documentation have posted to the documentation site. The comment cycle is open with customer feedback due by April 27. This CR will remain in Development Status.

March 17, 2004 CMP Meeting notes: Agreement was reached that the initial jeopardy notice would continue to be sent as documented (based on current system functionality). Qwest proposed that an updated Jeopardy Notification with additional detailed remarks would be sent within 72 hrs from when the Initial Jeopardy was sent if a solution to the delayed condition has not been reached. The proposal means that within 72 hrs from the initial Jeopardy Notification, the CLEC will receive one of the following: 1. FOC confirming original Due Date 2. FOC confirming revised Due Date based on Network resolution of the Jeopardy condition including details on the delay. 3) An “updated” Jeopardy Notification with more specific details of the Jeopardy condition. An FOC will follow when the revised Due Date has been determined.

In addition, Qwest will discontinue critical date jeopardy notifications and continue due date jeopardy notifications. (Critical date jeopardy notifications will still go out until a system enhancement can be made to change this, but the CLECs can disregard them). Phyllis will revise the PCAT to identify jeopardy codes where “The Due Date is in Jeopardy” (YES/NO) so that you can ignore “Critical Date” Jeopardy Codes that do not impact the Due Date until a separate enhancement can be made. The PCAT update has been forwarded to the external documentation team. Bonnie Johnson – Eschelon stated that she wants to make sure that we get documentation to support the process that an FOC must be sent before a customer not ready jeopardy occurs. Phyllis advised she is still working on this issue with an interdepartmental team . Phyllis advised that Jean Novak – Service Manager has had meetings with Network to respond to the examples that Eschelon forwarded as “inaccurate Jeopardy Notices and is still working on the issue. Jean is working on ‘inaccurate jeopardy notices’ and Phyllis is working on ‘when you don’t get an FOC’. Bonnie Johnson advised Qwest can contact us anytime during the day to accept the service. If we are contacted after 5PM we don’t want the jeopardy to be considered a customer not ready. Bonnie advised she wants this information in the PCAT. This CR will stay in Development Status.

PC081403-1 Jeopardy Notification Process Ad hoc meeting March 4, 2004

In attendance: Kim Isaacs – Eschelon Phyllis Sunins – Qwest Julie Pickard – US Link Bonnie Johnson – Eschelon Regina Mosely – ATT Cheryl Peterson – ATT Phyllis Burt – ATT Carla Pardee – ATT Jill Martain – Qwest Jim McClusky – Accenture Donna Osborne Miller – ATT Peggy Rehn – New Start Stephanie Prull – Eschelon

Cindy Macy – Qwest opened the call and reviewed the agenda items. Phyllis Sunins – Qwest thanked Kim Isaacs – Eschelon for providing examples that Phyllis investigated. Phyllis asked if the CLECs had the chance to review the documentation and if they had any questions.

Bonnie Johnson – Eschelon said she reviewed the documentation and summarized the changes. Bonnie verified that Qwest is proposing to omit critical jeopardy notifications, but not due date impacting jeopardy notifications. All of the CLECs agreed to this change as previous meetings so this change is okay to implement.

Bonnie asked if the mechanical notifications are the ones that will not be updated with additional information. Phyllis advised that it could be a manual notification also, as the same notification goes out, it is just that the process is manual.

Phyllis explained we could send additional information on the updated notification. Qwest does not always have enough information when we first determine a jeopardy condition. If we try to provide more information in the beginning, the chances are that the information will not be very accurate. We do not want to convey a service issue if it really isn’t a problem. Phyllis advised Qwest would send additional information within 72 hours.

Bonnie confirmed that the CLEC should always receive the FOC before the due date. Phyllis agreed, and confirmed that Qwest cannot expect the CLEC to be ready for the service if we haven’t notified you. Bonnie asked about the CNR in error? (When the CLEC has gotten a CNR without a FOC). Jill Martain – Qwest advised that we believe eliminating the ‘critical date’ jeopardies will take care of the bulk of the problem with CNR jeopardies.

Jill advised this solution would be implemented in two phases. The CLECs will get jeopardy notices, but you can ignore the ‘critical date’ jeopardy notices. These jeopardies are identified on the matrix that Phyllis put together. System changes are needed to stop these jeopardies and that will take awhile to get implemented. We would like to implement this process and monitor the impact and see if it has reduced the number of issues.

Cindy Macy – Qwest asked how will the CLECs know which jeopardy codes to ignore? Jill and Phyllis asked for the CLECs preference to how they would like this identified on the matrix. Agreement was reached to add a column to the matrix (3rd column) and call it ‘Due Dates in Jeopardy’.

Phyllis Burt – ATT asked if these codes are going away and we wouldn’t see them on the order. Phyllis – Qwest advised these are not due date impacting codes, they are interim steps before the due date. These codes will not go away until the system changes can be made. The CLECs do not need to take action on these codes.

Bonnie Johnson – Eschelon asked Stephanie about the EDI impacts. Can we ignore these or do we have to change any code? Stephanie said so far it seems as if this will work for us.

Bonnie confirmed that Qwest would provide additional information on Jeopardies within 72 hours from distribution of the initial jeopardy notification. Jill agreed and summarized that we will publish the process as a Level 3 with a comment cycle. If the CLECs need to meet again before we publish the document please advise Cindy Macy. The CLECs should monitor the process after it is implemented to determine if it has improved.

Next steps: Publish documentation Level 3.

February 18, 2004 CMP Meeting Phyllis Sunins – Qwest advised that she is working with Kim Isaacs – Eschelon and analyzing some examples that were sent in. Qwest did find a few process compliance examples that are being addressed. Cindy Macy – Qwest will provide a document to address Eschelon’s examples and this will be reviewed during the ad hoc meeting the first week in March. This CR will remain in Development Status.

Ad Hoc Call January 23, 2004 PC081403-1 Jeopardy Process

In attendance: Liz Balvin – MCI Karen Severson – Telephone Associates Kim Isaacs – Eschelon Phyllis Sunins – Qwest Jill Martain – Qwest Stephanie Prull – Eschelon Trudy Hughs – Idea One Shirley Richard – Idea One Rosie Glastell – Idea One Bonnie Johnson – Eschelon Colleen Sponseller – MCI Mary Hunt – MCI Carla Pardee – ATT Linda Sanchez-Steinke – Qwest Cindy Macy – Qwest Nancy Sanders – Comcast

Cindy Macy – Qwest opened the call and reviewed the agenda. Cindy advised that we will discuss providing more detail on Jep Notices, review the improvements as a result of the CNR 6pm Jep CR, and discuss examples that were sent in regarding subsequent FOC not sent.

Jill Martain reviewed the agenda and advised that Phyllis Sunins will provide additional details regarding the work that has been completed. Phyllis will share where we have been, where we are and where we want to go with this CR.

Phyllis began the discussion and asked the CLECs how the jeopardy notification process change to 6pm is going? Kim Isaacs – Eschelon advised she had gathered a couple weeks worth of data. It does appear there has been an effect. The impact is not as great as she thought it would be, but they will continue to monitor the change. Kim explained she noticed an interesting situation and Eschelon saw that quite a few sups of due date, then FOC on due date and then Jep on sup. Kim will send examples to Phyllis to investigate.

Rosemary – Idea One asked why is Qwest holding the jep until 6 PM. Phyllis explained a CR was issued to implement a new process. Effective with the new process a jeopardy notification is not sent when a jeopardy condition is cleared the same day by 6 PM. Kim Isaacs – Eschelon advised this process is only on mechanized jeps, not manual jeps.

Phyllis said the next topic to discuss is the request for additional wording on jeps. Phyllis explained that we can provide more detail on subsequent jeps. The first jep that goes out is considered a preliminary jep, with a preliminary view of the issue. Qwest does not know additional details until the engineer does investigation and finds out more. Our target is that within 72 hrs Qwest would either send an FOC or another jeopardy notification with additional detail. Bonnie Johnson – Eschelon advised the mechanical jeps are not detailed enough.

Phyllis advised another idea that may be possible is to use HEET, which is used on the ASR side. This is a web tool to check status on delayed orders. It may be possible to implement for LSRs. Rosemary – Idea One asked what is RTT. Phyllis advised RTT is a Referral Tracking Tool that tracks facility shortages. RTT is Engineering’s database for resolving facility situations referred to them. Bonnie advised she would like to review other alternatives if HEET is not a viable solution.

Today Qwest sends jeopardy notifications for both Critical Date Jeopardies and Due Date Jeopardies. Phyllis discussed the idea of sending jeopardy notifications that would impact the Due Date only. Qwest would discontinue sending jeopardy notifications for jeopardies on Critical Dates that are cleared the same day or the next day and the Due Date is still met. As an example; Qwest sends jeopardy notifications for PICs – V25 (plug in network cards) problems. This jeopardy situation is resolved so that the Due Date is met. Another example is Jeopardy Notifications for Work Force Issues (33’s). Qwest works with our Work Forces to readjust their loads so that the Due Date is met. Bonnie Johnson – Eschelon agreed they do not want to see jeps for ‘interim date’ issues. If the end due date is impacted, then they need to know. Idea One and MCI supported Bonnie’s comment. Phyllis confirmed that the due date jep would still happen, (Qwest could discontinue the Critical Date jeopardies which are cleared by Due Date) . If the Due Date will be missed, it is part of Qwest’s Network Processes to call the CLEC on the Due Date. In addition, the CLECs will receive their jeopardy notification after 6 PM. MCI verified when the jep is sent it comes as an 865 EDI transaction, and the FOC is an 855 EDI transaction.

Bonnie advised they do want more detail on what the jep’d problem is. They need to know if it is a F1 pair, or the street needs to be dug up. She would like more detail on one jep in particular: ‘Local Facility not available’. Bonnie asked when does this jep occur. What situation causes this jep to be assigned?

Phyllis discussed the two examples that Eschelon sent in. 1) One was a jeopardy notification sent for a PICs issue, no FOC was sent & then CNR. – This was an example of a Critical Date Jeopardy that would be addressed by the proposal of not sending Critical Date Jeopardy Notifications as the situation is cleared so that the Due Date can be met, thus the CLEC would expect Qwest to deliver on the Due Date.

2) The other example is a Network compliance issue, which Phyllis is working with Network to correct.

Bonnie thanked Phyllis for reviewing the examples. Bonnie advised that if they receive a CNR jep, and the CLEC has not received the FOC, they would escalate the situation. Bonnie advised they want the order worked without having to sup the order and they would like the jep lifted. Bonnie advised she would like to develop a process of how we will handle this situation when we get a CNR and didn’t get the FOC.

Phyllis summarized our next steps:

Kim Isaacs will send examples to Phyllis of orders sup’d on due date

CLECs will continue to monitor 6pm jeps

Jill / Phyllis will review wording of jeps to add more detail

Bonnie brought up a concern on the time required for getting funding to implement the “Due Date only” Jeopardy notifications (from a mechanical perspective). She proposed having Qwest furnish a list of “Critical Date” jeopardy notifications which could be “disregarded on an interim basis. Phyllis will research this request. This information will be worked via the CMP process and additional meetings.

January 21, 2004 CMP Meeting Jill Martain – Qwest advised that we met with the CLECs last month and agreed to monitor the JEP process and then meet again in January to review additional information that can be put on the Jeopardy notice. We have a meeting scheduled for January 23 to discuss this further. Bonnie sent in two examples where they did not get a subsequent FOC and the order was jep’d for CNR. Bonnie advised that Qwest needs to find a way to get the FOC to the CLEC. The impact to our business is that we are forced to supp the order and take a new due date. Qwest no longer takes the hit on the held order in this situation too. Bonnie advised that Qwest needs to aggressively tackle this issue as it impacts our business, end users and held orders. It is high profile and critical and it needs to be fixed. Jill Martain – Qwest advised we have the examples and we are prepared to talk in more detail at the Friday meeting. This CR will remain in Development Status.

- December 17, 2003 CMP Meeting Jill Martain – Qwest advised we had an ad hoc meeting to review the updated Jeopardy matrix. Jill is working with the centers to provide additional information on the Jeopardy notices. The team agreed to monitor the impact of the change to 6pm jep notices and meet again next month to review any additional changes needed and to review enhanced jeopardy description information. Bonnie Johnson – Eschelon advised she will monitor internally the impact to the change in jeopardy time frames and provide feedback at our next meeting. (Included comment from Bonnie Johnson in the following sentence). Bonnie said this CR is not related to CR to change the jeopardy to 6pm). This CR will remain in Development Status.

Clarification Call PC081403-1 Jeopardy Notification Process

December 8, 2003 3:00 – 4:00

In attendance: Valerie Estorga – Qwest Valerie Star – NoaNet Oregon Marty Petrowski – WAN Tel Oregon Kim Isaacs – Eschelon Anne Atkinson – ATT Jill Martain – Qwest Phyllis Burt – ATT James McClusky – Accenture Donna Osborne Miller – ATT Steph Prull – Eschelon Ray Smith – Eschelon Cheryl Peterson – ATT Carla Pardee – ATT Wayne Hart – Idaho PUC Bonnie Johnson – Eschelon Cindy Macy – Qwest

Cindy Macy – Qwest introduced the attendees and reviewed the purpose of the call. Cindy verified the attendees had the Jeopardy Notification matrix.

Jill Martain – Qwest explained we have held discussions with the CLECs in hopes of improving the jeopardy process. Jill would like to review the matrix and allow the CLECs to ask questions and voice their concerns.

Jill explained the change to send jeopardy notification at 6pm was effective over the weekend. This applies to all mechanized jeopardy codes. The intent of this change should reduce the number of jeopardies sent, as Qwest clears many jeopardies through out the day.

Jill explained there are some manual jeopardies that are not part of this process, such as C)% and SX. Based on investigation, we are looking at sending jeopardies on Facility and Plug in equipment issues. These would be K and V25 – PICS jeps. Possibility exists to eliminate all 33 work force jeps. This will allow us to reduce the number of jeps sent on certain phases of the order.

Bonnie Johnson – Eschelon said she would be glad to try this process and see what improvement it makes.

Marty – WAN Tel asked if Qwest could send more information on the jep notification. If the description / content / reason why Qwest is placing the order in jep, would help the CLEC understand and address the problem. For example, if Qwest says there are local facility issues but does not say what kind of issue, the CLEC can not take action on the issue. It is very difficult for the CLEC to find more out about the issue too. Jill agreed she would see if we could provide more detail on why the order was placed in jeopardy. Jill said if more information can be included she would try to get that implemented as soon as possible.

Bonnie Johnson – Eschelon agreed that providing adequate information on jeopardy notices is critical for the CLEC to look at alternative solutions.

Steph Prull – Eschelon asked if the process could be revised to include the correlation between the ‘reason code’ and the ‘jeopardy detail code’ on the jeopardy notice. The Disclosure document has the reason code but does not have a correlation to the jeopardy detail code. Jill advised she would look into this.

Kim Isaacs – Eschelon asked about C09 as this code seems in conflict with the held order process. Jill advised C09 would not occur on a held order situation. Jill advised jeps are per order, not per LSR.

Bonnie Johnson – Eschelon asked about the CR request regarding when the CLEC gets a jep, and then Qwest does not allow the CLEC time to react to the FOC (4 hour minimum). Jill asked Bonnie if we could wait and determine the impact of the 6pm jep time change as this change should reduce the number of jeps and reduce this issue. Bonnie agreed we could discuss this later if it is still an issue.

Bonnie also asked if there was a CLEC forum planned for January. Cindy advised she did not know but would check on. Bonnie suggested we talk about it at the December CMP meeting, and that possibly a better time for the Forum would be in February.

Jill agreed to check on the following items:

1 – adding content to the jeopardy description to make it more informative 2 – check how reason codes match to jep codes in the Disclosure document

Next Steps: The team agreed to meet again around the week of January 13 to review how the 6pm jeopardy change has impacted the process and to determine our next steps

Novmeber 19, 2003 CMP Meeting Jill Martain- Qwest advised this CR was revised to say that the CR was going to revisit the existing Jeopardy process, including what notices should be sent to the customer and then also discuss the content of those notices. Bonnie Johnson – Eschelon agreed updating the CR was okay. Jill Martain-Qwest advised the next step is to schedule an ad hoc meeting to review information and gather input. John Berard – Covad advised he has a jeopardy request item to be included in this CR.

Oct 15, 2003 CMP Meeting Phyllis Sunins – Qwest reported that she is doing a study of the August data and that there are synergies with this CR and PC072303-1. Jill Martain will also open a new CR to address the overall Jeopardy Process. Bonnie Johnson – Eschelon advised she would like to keep this CR open and reference it to PC072303-1 and Jill’s new CR. Discussion took place regarding maybe the scope of this CR should be changed, instead of Jill creating a new CR. Cindy agreed she would talk to Jill about this. Liz Balvin – MCI advised she has some questions about what certain jep codes mean. A documentation CR has been issued to request definition of jep codes. The team advised that Liz should respond during the comment cycle and ask about the jep codes she is interested in (C31 and C34). John Berard – Covad asked how many jeps are resolved the same day? Bonnie Johnson – Eschelon said she did not know numbers but Jill implied the majority of jeps are resolved the same day. This CR will move to Development Status.

10/6/03 Ad Hoc Meeting

Lori Mendoza Allegiance Russ Urevig Qwest Deni Toye Qwest Phyllis Burt ATT Julie Pickar US Link Dave Hahn Qwest Jeanne Whisnet Qwest Laurie Dalton Qwest Ann Adkinson ATT Jill Martain Qwest Phyllis Sunins Qwest Carla Pardee ATT Jen Arnold US Link Kim Issacs Eschelon Bonnie Johnson Eschelon Donna Osborne Miller ATT Regina Mosely ATT

Jill Martain discussed the synergy's between PC072303-1 and this CR and the issue that came up in the CLEC Forum about FOCs not being sent after a delayed order is released. Jill explained she would like to implement changing the jep timeframe to 6 pm as identified in PC072303-1. As a result of this change it will address many of the issues with not enough time to respond to a jep. Jill referred to this as Phase 1. Jill will issue a Qwest CR to modify the Jep Process and make additional changes as needed. Changes such as define jep codes, determine when to send jeps, and for what conditions. Jill said she certainly can accommodate some time frames in between FOC and Jep. Jill referred to this as Phase 2. Bonnie agreed that Jill's new CR and implementing the changes for PC072303-1 will take care of this CR. Changing the jep times will take care of most of these issues.

- 9/17/03 CMP Meeting Bonnie Johnson – Eschelon presented the CR to the CLEC Community. Bonnie advised this continues to be a problem. Eschelon does not normally get an FOC after a delayed order gets released. Sometimes we get the FOC and we do not have time to react. Qwest needs to make certain that if we release an order from delayed status that the CLEC gets an FOC, and has time to react before the order is put in a CNR jep. This happens often. Our service delivery personnel escalate with the tester and the FOC group. Jill Martain is working on the issue with not receiving an FOC. This was brought up at the CLEC forum. Cindy Macy-Qwest asked if the changes associated to PC072303-1 – changing the time when Qwest jeps for CNR, would meet this CR. Bonnie advised no, because in this case the order is being released from delayed status and the original FOC has already occurred.

CLEC Change Request – PC081403-1 Clarification Meeting Tuesday August 26, 2003

1-877-552-8688 7146042#

Attendees Cindy Macy – CRPM Russ Urevig – Qwest Phyllis Sunins – Qwest Laurie Dalton – Qwesst Bonnie Johnson – Eschelon Deni Toye – Qwest Stephanie Prull – McLeod Julie Picker - US Link

Introduction of Attendees Cindy Macy-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Bonnie Johnson-Eschelon reviewed the CR. Bonnie explained that ½ the time they do not get an FOC after the order is released. This problem is being addressed by Jill Martain and is not part of this CR but it is an issue that impacts this CR. The CLEC needs time to react to the released LSR and to accept the circuit.

Phyllis explained the jep could be placed early in the morning and the tech working on the it may get a solution the same day. This creates a timing difficulty. The current process is for the order to be jep’d, Qwest would send an FOC when they find out the issue has been taken care of, and then if the customer is not ready the LSR is put in CNR.

Bonnie advised they would like a 2-4 business hour time frame to respond to the FOC before Qwest puts the LSR in CNR.

The process today does not give a time frame on the FOC, it gives a date but no time frame.

Confirm Areas and Products Impacted Macy - Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved Macy - Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation Macy-Qwest reviewed the request to confirm Eschelon’s expectation.

Identify and Dependant Systems Change Requests Macy-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan Macy-Qwest asked attendees if there were any further questions. There were none. Macy-Qwest stated that the next step was for Eschelon to present the CR at the September Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

October 8, 2003

For Review by CLEC Community and Discussion at the October 15, 2003, CMP Product/Process Meeting

Bonnie Johnson Eschelon

SUBJECT: CLEC Change Request Response - CR # PC081403-1

This is a preliminary response regarding the Eschelon CR PC081403-1. This CR requests that the ‘Delayed order process be modified to allow the CLEC a designated time frame to respond to a released delayed order after Qwest sends and updated FOC. Qwest will contact the CLEC to test and accept only after the updated FOC has been sent and a designated time frame has passed. Qwest will not put the order in a CNR (customer not ready) jeopardy status until this time frame has passed and the CLEC is not ready’.

Qwest believes this CR has synergies with the Eschelon CR PC072303-1 ‘Customer Not Ready (CNR) jeopardy notice should not be sent by Qwest to CLEC before 5 PM’. Qwest proposes moving this Change Request into Evaluation Status while we investigate the commonalities further and will provide a status update at the November CMP meeting.

An Ad Hoc Meeting is scheduled for Monday, October 6, 2003 from 10:00 – 11:30 a.m. MST to discuss CR# PC072303-1 and PC081403-1.

Sincerely,

Phyllis Sunins Wholesale Markets Process Organization


Open Product/Process CR PC081403-2 Detail

 
Title: Workback process/products expanded to include additional products and allow partial workbacks. Qwest will post the process and products included in the Business Procedure section of the web site.
CR Number Current Status
Date
Area Impacted Products Impacted

PC081403-2 Completed
8/18/2004
Products to be defined through a collaborative effort including Qwest and the CLEC Community
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest should expand the current work back process to include additional products and partial workbacks. Qwest currently allows workbacks for only LNP (Local number portability) orders and requires the entire LSR to be worked back. CLECs sometimes have a need to request a workback on only a portion of an LSR or for products outside of the current products this process applies to (LNP). The current Qwest documentation for the workback process is located in the Qwest LNP PCAT (titled end user out of service) and does not define that a CLEC is required to do the workback on an entire LSR. Qwest documentation should not leave this to interpretation. Qwest should provide clear documentation of the entire process in the Business Procedure section of the web site. This should include a detailed process and the products the workback process applies to.

Expected Deliverable:

Qwest will develop, document and train an expanded "workback" process to include additional products and partial workbacks. Qwest should allow the CLEC to do workbacks on partial LSRs and include additional products. Qwest should post this as a "process" under the business procedure section of the Qwest Wholesale web site.


Status History

08/14/03 - CR Submitted

08/15/03 - CR Acknowledged

8/19/03 - LWTC for Bonnie regarding Clarification meeting date

8/26/03 - Held Clarification Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/8/03 - Sent response to CLEC

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP meeting minutes will be posted to the database

1/2/04 - Notification distributed to review draft process on 1/12/03

1/8/03 - PROD.01.08.04.F.01226.LNP_V25

1/12/03 - Held CLEC ad hoc meeting to review draft process

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/6/04 - Sent Ad Hoc meeting notification for CLEC meeting on 4-16

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/18/04 - PROS.05.18.04.F.01688.ExpeditesV9

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - August CMP meeting mintues will be posted to the database


Project Meetings

8/16/04 CMP Meeting Mintues Cindy Macy – Qwest advised that the PCAT was implemented and effective June 29. Cindy asked if we could close this CR. Kim Isaacs – Eschelon advised it is okay to close the CR. This CR will move to Completed Status.

July 21, 2004 CMP Meeting notes: Cindy Macy –Qwest advised that this CR was effective June 29. Qwest will move this CR to CLEC Test status.

June 16, 2004 CMP Meeting notes: Jill Martain – Qwest advised that comments were received and responded to for this CR. This CR will be effective June 29. The CLECs agreed to move this CR to CLEC Test on June 29. Bonnie Johnson – Eschelon advised that she would prefer for Qwest to be consistent and move things to CLEC test after the effective date, but not before. While reviewing the Change Management Process document section 5.8, Qwest believes that the work needs to be completed for each status type (i.e. CLEC Test) before the status is changed. Status should only be changed upon agreement in the Monthly Meeting. This CR will remain in Development Status. This CR would move to CLEC Test in July as the effective date is June 29.

May 19, 2004 CMP Meeting notes: Jill Martain – Qwest advised that the documentation for this CR was released on May 18 and should be implemented July 2. This CR will remain in Development Status.

April 21, 2004 CMP Meeting notes: Jill Martain – Qwest provided status on this CR for Joan Wells. Jill advised that Qwest held another adhoc meeting with the CLECs. We will update the PCAT with additional information that will clarify the process. We also discussed and documented how Workback for other products should follow the Expedite process. This documentation should be updated by the end of the month. Bonnie Johnson – Eschelon advised that this topic covers such a broad scope, that it makes sense for it to be in the Expedite and Escalation process. Bonnie confirmed that Qwest will tell the CLECs what to do on a case by case basis, but because it is documented then Qwest will know there is a process to follow. Bonnie said Eschelon submitted this CR because during an escalation Qwest told Eschelon that Qwest did not do workbacks. Bonnie said after Qwest documents the process Qwest employees will know that a process exists. This CR will remain in Development Status.

CLEC Ad Hoc Meeting PC081403-2 Work Back Process CR April 16, 2004

In attendance: Jennifer Fischer - Qwest Communications Bonnie Johnson – Eschelon Kim Isaacs – Eschelon Jill Martain - Qwest Communications Kathy Rein - Qwest Communications Stephanie Prull – Eschelon Pete Budner - Qwest Communications Chris Quinn-Struck Qwest Communications Julie Picker – US Link Joan Wells - Qwest Communications Cindy Macy - Qwest Communications

Cindy Macy – Qwest took attendance and explained the purpose of the call was to review the changes that had been made so far as a result of this CR, and the proposed changes needed to close the CR.

Joan Wells - Qwest Communications explained that she updated the PCAT and there were concerns with the updates that were made. Joan clarified the updates and verified that there were not process changes as a result of the updates, except to add the language around full and partial workbacks. Bonnie Johnson – Eschelon agreed and confirmed that it was a misunderstanding regarding when the escalation process was being used.

Joan Wells advised that Qwest will use existing expedite processes for the expansion to other products with additional language added.. And that this information will be included in the existing Escalation and Expedites PCAT.. Joan advised Wholesale will handle the customer requests; they will not be referred to Retail. Bonnie Johnson – Eschelon advised she was happy about this. Joan advised the method of restoral is ICB, based on the actual situation, and the Customer Service group will advise the CLEC how to proceed with restoral and whether an LSR is needed.

Bonnie Johnson – Eschelon wanted to make sure that there will be enough level of detail for the centers to determine what course of action is needed to restore the service. Joan advised yes. Bonnie asked about the 24 hour restriction. Joan confirmed it is a 24 hour, not 24 business hour timeframe.

Bonnie advised she is okay with updating the process if the documentation provides enough level of detail for the centers to take action. Joan agreed and advised she is planning on getting the documentation released soon. The plan would be to move this CR to CLEC Test in May, and close in June.

March 17, 2004 CMP Meeting notes: Bonnie Johnson – Eschelon advised that she is concerned that Qwest has stated that we can not workback a customer if the port has taken place. If this is the case, then Qwest has changed the process as we currently do this today. Joan Wells – Qwest advised that we did not change anything in the PCAT regarding this. What was changed is that we added that you can now request a full and partial workback. No other language was changed and it has been this way for the past two years. Bonnie Johnson – Eschelon asked if Qwest is aware that workbacks are occurring even when the port has been completed. Joan Wells – said it could be possible that this happens, but it is not in the process. Ervin Rae – ATT advised they average 50-60 a day, after the subscription has been completed. Joan Wells – Qwest advised we average 50 workbacks a month total. Bonnie Johnson asked is it possible there is another piece that we are missing. Joan Wells advised that we don’t disconnect the customer until 2 days after the due date, at 11:59 the next business day. We already pull these from the completion workload and give extra time. Qwest is not sure if we are in a position to workback customers for no charge, after the port has taken place, as at least 2+ days have already gone by. Bonnie Johnson asked why does Qwest hold the account if they are not willing to do a workback? Bonnie asked if Qwest can still do this on the subscription piece? Joan advised that Qwest will have the ability to do this by canceling the subscription and order. The opportunity is there but we shouldn’t do this without a charge. Joan confirmed that the process was not changed, our response was to document full and partial workbacks. If further documentation is needed it would be outside the scope if this CR. Ervin Rae – ATT advised this needs to be expanded to include all products. Joan Wells advised this piece is still being worked on and is under development. Jill Martain – Qwest advised that the Covad CR PC021904-1 Enhancements to Expedite Process is similar to this request, and she will try to work the issue on that CR also. Bonnie advised that she needs to take this back and talk to additional people in her organization. Bonnie confirmed that Qwest’s position is that we do not do a workback after the port has been complete. When this occurs it is using the escalation process. Maybe Qwest needs to update the PCAT to include the escalate process if workbacks are needed after the service order has completed. Joan Wells said that volume is low. Bonnie Johnson will check with her team and get back to us. This CR will remain in Development Status.

February 18, 2004 CMP Meeting Cindy Macy – Qwest provided status for Joan Wells. The first part of this process was published and implemented. Joan is working on the process for the additional products. Joan is working with Retail to identify impacts. This CR will remain in Development Status.

January 21, 2004 CMP Meeting Cindy Macy – Qwest advised that Joan Wells – Qwest held an ad hoc meeting on January 12 and reviewed the draft process. Joan took some points to incorporate into the process and review. The documentation is in progress. This CR will remain in Development Status.

Ad-hoc Meeting 1:00 p.m. (MDT) / Monday January 12, 2004

1-877-552-8688 7146042 PC 081403-2

Attended Conference Call Name/Company: Carla Pardee, AT&T Donna Osborn-Miller, AT&T Cheryl Miller, AT&T Andrea Niles, AT&T David Bellinger, AT&T Joyce Perry, AT&T Bonnie Johnson, Eschelon Kim Isaacs, Eschelon Kim Sutton, Cox Communication Carol Roland, Cox Communication Carla Cox, 180 Communication Janet Harper, 180 Communication Joan Wells, Qwest Susie Wells, Qwest Terri Kilker, Qwest Linda Harmon, Qwest

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change Joan Wells, Qwest reviewed the Draft Proposal process and scenarios. This is for Part II Workback Expansion Proposal to include additional products.

The following were questions or clarifications made during the meeting:

David Bellinger, AT&T asked what the intervals would be for getting the customer back in service. Joan said she would have to check but in any case they would mirror the existing timeframes.

Joan verified that this process is to cover when orders have completed and has nothing to do with LNP or number portability in general.

Cheryl Peterson, AT&T asked what time orders are completed. Joan answered that it often depends on the type of order.

Kim Isaacs, Eschelon ask if process steps 6-10 is for when the account is UNE-P with another CLEC. Joan answered yes and that she will clarify in document.

Bonnie Johnson, Eschelon asked if Restriction 4 was also the practice in Retail as well. Joan said yes that there are no parity issues.

Bonnie commented that process steps 11 through 13 are where most of these cases fall and customers are impacted. She stated the purpose of the CR was to have a different process from going through the Retail front door since the area between Wholesale and Retail is often painful to the customer and CLEC. Bonnie is not asking that Retail not be involved but to have a process where someone knowledgeable handles the situation and where the customer or CLEC does not have to start at the Retail front door. Joan stated that Wholesale couldn’t handle Retail involvement she agreed to look into what could be done. Bonnie said if we could get resolution to the front door issue that she is fine with the process. AT&T and 180 Communication agreed

Joan stated that Part 1 of the documentation should be out in a few weeks. She also said she will try to have an update for the January CMP meeting and will continue to evaluate the need for another meeting.

December 17, 2003 CMP Meeting Joan Wells – Qwest advised she has sent the documentation for Partial Work backs on LNP to the documentation team. She also has a draft proposal available for the other products that she would like to review with the CLECs. A meeting will be scheduled the week of January 5 to review the draft proposal. Bonnie Johnson – Eschelon requested to have the process sent out in advance so it could be reviewed prior to the meeting. Joan agreed and advised it would be included in the meeting notification ahead of the meeting date. This CR will remain in Development Status.

November 19, 2003 CMP Meeting Joan Wells reviewed Qwest’s response and identified the products that will be addressed with this CR. Joan explained she would like to call this process the ‘Restoral Request’ process. Ervin Rea-ATT asked what are the requirements to get the customer back in service? Joan advised they are developing those requirements as part of this CR. Basically the process would consist of the customer contacting the Call Center to advise of the problem. A ticket is issued. A supplement may need to be issued to the LSR depending on if the work or LSR is completed. The service would follow an expedite process to restore. Qwest is looking into the criteria to determine when a restoral request is allowed and when charges would be incurred to reinstate the service.

Oct 15, 2003 CMP Meeting Cindy Macy – Qwest advised she would page Joan to the call as she is on vacation. Bonnie Johnson – Eschelon said she has reviewed the response and understands Qwest will begin working on the partial workback process for LNP and the other products are under review. Bonnie advised we did not need to page Joan to the meeting. This CR will move to Development Status.

Sept 17, 2003 CMP Meeting Bonnie Johnson advised we had a good clarification call. There were attempts made a reeling in the scope of this CR. Bonnie advised she would like the process expanded on product where it is workable. Today, Workback is on LNP and it is all or nothing. Bonnie requested for Qwest to expand where this can be done and also to be able to do a partial Workback. Joan asked if another ad hoc meeting may be appropriate to gather additional issues, on a product by product basis from other CLECs. Any product that is can be included on should be included. This request is clearly asking for these product and when a CLEC can do a Workback. Judy Schultz asked if it was appropriate for Qwest to prepare a recommendation. Bonnie agreed for Qwest to review scenarios and do this on a case by case basis. Bonnie advised this request is a result of an escalation. Escalations usually drive process improvements. Susie Bliss advised Qwest would also look at volumes and costs.

CLEC Change Request – PC081403-2 Clarification Meeting Tuesday, August 26, 2003

1-877-552-8688 7146042#

Attendees Cindy Macy – CRPM Dusti Bastian – Qwest Mallory Paxton – Qwest Joan Wells – Qwest Sharon Van Meter – ATT Bonnie Johnson - Eschelon

Introduction of Attendees Macy-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Bonnie Johnson-Eschelon reviewed the CR. Bonnie explained the PCAT defines a work back process, however it is for LNP only and does not include partial work backs. Eschelon had a situation where they were trying to work back the DSL portion of a cut and could not do a partial work back. Qwest did do this but it was very difficult.

Joan Wells asked if Bonnie wanted work backs available to new products or products associated to LNP? Bonnie advised there are multiple situations when this may be needed. For example, when we are converting a customer from Qwest Retail to Eschelon UNE-P.

Joan Wells advised the work back process was put in place when Qwest was disconnecting customers and the CLECs were having trouble getting the customer installed on the same due date. This is not occurring very much any more. On a conversion there is usually no facility change that occurs so there wouldn’t be a work back situation. Bonnie advised there can be circumstances that cause facility changes and thus the need for a work back; such as Qwest record issues that show the DSL on the wrong line, or PBX that causes trouble on the line, credit card machines etc. Bonnie agreed it is not a high percentage of times that this happens, but it is important when it does happen.

The group discussed that there are many variables and it could be a different process based on each circumstance. The group tried to determine the scope of the CR as the process may be different based on each product or situation. Joan Wells advised she can not document what the CLEC needs to do for their part of the work back.

Joan asked if the CLECs would be willing to pay for this service. Bonnie advised under certain circumstances it makes sense. Mallory Paxton – Qwest advised in some cased it would involve Qwest doing a New Connect. Joan Wells advised there should be parameters around how much time can go by to determine if a work back is a valid option.

Bonnie advised she would like this in the Business Process section of the PCAT, and not be product specific. Cindy Macy-Qwest advised this would imply the process would be a high level process about work backs in general and not be specific to each product. Mallory advised the process would be different for different products so a general process may not provide a lot of value. Some things to consider are the time constraints, charges, process by product, identify the limitations of the process versus all the conditions that it could apply to.

Bonnie advised UNE-P and Resale are the most commonly ordered products so it would make sense to document it for those two products. Additionally, adding information to the LNP product to include partial work backs is needed. Bonnie advised she would lke the process defined and documented so we have a process to follow. It doesn’t have to cover the universe.

Confirm Areas and Products Impacted Cindy Macy-Qwest reviewed the scope of the CR.

Confirm Right Personnel Involved Cindy Macy-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation Cindy Macy-Qwest reviewed the request to confirm Eschelon’s expectation.

Identify and Dependant Systems Change Requests Cindy Macy-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan Macy-Qwest asked attendees if there were any further questions. There were none. Macy-Qwest stated that the next step was for Eschelon to present the CR at the September Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

Response Update

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting November 11, 2003

Eschelon Bonnie Johnson Sr. Manager ILEC Relations

SUBJECT: CR # PC081403-2 Workback process/products expanded to include additional products and allow partial workbacks. Qwest will post the process and products included in the Business Procedure section of the web site.

This letter is being issued to provide an updated response on the development of Eschelon’s Change Request (CR) PC081403-2. This CR requests that:

· Qwest expand the existing LNP workback process to allow partial workbacks · Qwest expand the workback process to include additional products Qwest is currently in the development stages of both a new “Workback”(WB) process for LNP that will include partial restorals and a new expanded Workback process that will be identified as a “Restoral Request” (RR) for the Resale / UNE-P POTS and Resale / UNE-P Centrex 21 products. Qwest will provide an updated status on the process development at the December CMP meeting.

Sincerely, Joan Wells Sr. Process Analyst Qwest Communications

For Review by the CLEC Community and Discussion at the October 15, 2003 CMP Meeting

October 8, 2003

Eschelon Bonnie Johnson Sr. Manager ILEC Relations

SUBJECT: CR # PC081403-2 Workback process/products expanded to include additional products and allow partial workbacks. Qwest will post the process and products included in the Business Procedure section of the web site.

This letter is in response to Eschelon’s Change Request (CR) PC081403-2. This CR requests that: ? Qwest expand the existing LNP workback process to allow partial workbacks ? Qwest expand the workback process to include additional products

Qwest accepts this request. Qwest will change the workback process for Local Number Portability and Loop Service with Local Number Portability to include partial workbacks. This change will be identified and documented within the current workback process located in the existing LNP PCAT.

Qwest is currently reviewing the workback process expansion request and its applicability to other products and processes that it will apply to. Qwest requests that this CR be placed in development status. Qwest will provide an update at the November CMP meeting.

Sincerely,

Joan Wells Sr. Process Analyst Qwest Communications


Open Product/Process CR PC070103-3 Detail

 
Title: DSL Volume provider and data migration process to prevent extended DSL outage
CR Number Current Status
Date
Area Impacted Products Impacted

PC070103-3 Completed
2/15/2004
Ordering, Provisioning line/loop splitting and sharing, UNE LOOP, UNE P Resale
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: James, Nicole
Director:
CR PM: Stecklein, Lynn

Description Of Change

Eschelon and Covad jointly submit this request. This request applies to all types of DSL (Qwest Retail, Qwest resold DSL, volume provider DSL, CLEC DSL, etc.). Any migration of voice, data or voice/data should be handled by Qwest with a single Local Service Request (“LSR”) with only minimal interruption to service.

An end user customer should be able to obtain one due date for installation/functioning of both voice and data. Carriers should be able to place a single LSR to convert physical DSL service (regardless of the identity of the ISP) to any provider without undue service interruption. Regardless of the ISP (or of the sharing scenario, if any), customer switches that involve both voice and data should be performed with (1) one LSR, and (2) no extended service disruption. With this request, we seek, for example, to: (1) ensure that the use/presence of a DSL Volume provider does not adversely impact conversions/conversion intervals when switching providers. (If a conversion would not result in an extended outage or longer intervals if a non-volume DSL provider is involved, then the same conversion should not result in an extended outage or longer intervals if a volume DSL provider is involved); and (2) to convert (using a single LSR) a customer’s existing DSL service regardless of how service is provided [including various sharing scenarios (e.g., line sharing/splitting; loop sharing/splitting)] without extended service interruption to data or voice providers.

#1

There should be no exception to the process for volume providers. Currently, when a customer switches from Qwest Retail DSL and Qwest ISP service to a CLEC, Qwest processes allow a CLEC/DLEC, using one LSR, to (a) convert the DSL and change the ISP (for resale/UNE-P), or (b) perform a partial conversion (such as leaving the line and DSL with Qwest Retail for one line and converting the remaining lines in the account to CLEC) – both without disconnecting the DSL. In contrast, when the customer has DSL service from a volume provider, Qwest will disconnect the DSL in both of these scenarios. The disconnect is not momentary. It results in a DSL outage for the customer for the length of the entire interval required to add the DSL again (5 days or more). Such outages are harmful to competition, because customers are reluctant to switch carriers when faced with such an extended DSL outage. The presence or absence of a volume provider should not affect the result. In any case, such an extended DSL outage should not occur. CLECs should be able to request these conversions using one LSR.

#2

The current process that does not require DSL disconnects (see #1a and #1b) should be expanded to include the types of conversions that currently result in DSL disconnects/outages, cannot be ordered using one LSR, or both. When switching carriers, an end user customer should be able to obtain one due date for installation/functioning of both voice and data and should not experience extended DSL outages. This result should not depend on the product that the customer currently uses or to which it is switching. Currently, the result does vary by product. For example, if a customer is on line sharing (with Qwest Retail voice and Covad data) and wants to switch to a UNE-P line splitting product (with CLEC voice and Covad data), Qwest will disconnect the DSL. Again, the disconnect is not momentary and results in an extended DSL outage. Even though the data is staying with Covad in this example, Qwest requires disconnection of the line sharing product and re-establishment of the UNE-P line splitting product as a physical matter. In reality, however, this should just be a pure records change for data and should not affect the customer’s service. CLECs should be able to request these conversions using one LSR.

Expected Deliverable:

Qwest will develop, document and train a process(es) that meets the needs described in the above Description of Change. The process will expand the current one to avoid DSL disconnects/outages in situations that currently result in disconnects/outages; it will allow use of a single LSR for ordering these conversions; and it will not include any exception for volume providers. If different parts of this CR can be done earlier than others, please describe the options to CLECs. Also, if different methods would be used to provide these conversions (such as a coordinated hot cut type elective option), please describe. Eschelon and Covad bring these issues together in one CR so that portions of the request do not fall between the cracks.

Text of e-mail message from Bonnie Johnson:

“Scenario #1

Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and hasQwest DSL with the DVDP FID. Eschelon sends conversion request and retains Qwest DSL but changes the ISP host (we do these today when the customer does not have volume provider arrangement).

Scenario #2

Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and has Qwest DSL with the DVDP FID. Eschelon sends conversion request and requests the line with Qwest DSL with volume provider stay with Qwest and Eschelon converts all or a part of the remaining account (we do these today when the customer does not have volume provider arrangement).

Scenario #3

Qwest Retail customer is converting to Eschelon (Facility based) and has Qwest DSL with or without a volume provider. Eschelon converts the line with DSL to a DSL (XDSL-I) capable loop.”


Status History

07/01/03 - CR Received

07/02/03 - CR Acknowledged

07/16/03 - CR Discussed at CMP Monthly Meeting

08/04/03 - Sent e-mail question to Bonnie Johnson re: Scenario #2, rec'd e-mail response from Bonnie Johnson re: Scenario #2

08/06/03 - Sent e-mail question to Bonnie Johnson re: Scenario #3

08/08/03 - Rec'd e-mail response from Bonnie Johnson re: Scenario #3

08/20/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/30/03 - Held clarification meting with Bonnie Johnson re: Scenario #1

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/26/04 - Qwest Issued PROS.01.26.04.F.01274.MigrationsV14 Level 1 effective 1/27/04

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database

10/20/04 - October CMP Meeting minutes will be posted to the database

11/17/04 - November CMP Meeting minutes will be posted to the database

12/4/04 - Release due date 12-4

12/15/04 - December meeting minutes will be posted to the database

1/3/05 - Eschelon requested copy of notice number on this CR - provided information to Kim Isaacs ( PROD.10.28.04.F.02243.ResaleUNE_DSL, PROD.11.19.04.F.02316.FNL_ResaleUNE_DSL)

1/19/05 - Discussed in the January Product/Process Meeting - See attachment C in the distribution package.

2/16/05 - Discussed in the February Product/Process Meeting - See attachment C in the distribution package.

3/16/05 - Discussed in the March Product/Process Meeting - See attachment C in the distribution package.

2/16/05 - Status changed to completed


Project Meetings

3/16/05 Systems CMP Meeting Discussion:

Jill Martain/Qwest stated that this CR was closed in the February CMP Meeting.

2/16/05 Product Process CMP Meeting

Jill Martain - Qwest stated that this CR was effective 12/4/04 and that we addressed the global concern Eschelon raised last month regarding notifications. Jill said that notifications should now include the CR number in the title and the notes.

Bonnie Johnson - Eschelon said that she was ok to close this CR. She said that the problem is with DSL and typing errors on the DD and it is hard to determine if the problem is due to the global concern she raised last month. Bonnie thanked Qwest for the additional information on the notifications.

1/19/05 CMP Meeting

Lynn Stecklein/Qwest stated that this CR was effective December 4, 2004 and should be ready to close. Bonnie Johnson/Eschelon said that she has a global concern associated with notifications. Bonnie said that the notification for this CR did not include the CR number that the notice was associated to and asked if Qwest could include the CR number on the notices. She stated that she would like to keep this CR open another month. Jill Martain/Qwest stated that we will take an action item to review the notification issue. Jill Martain/Qwest stated the CR would remain in CLEC test.

December CMP Meeting Minutes Cindy Macy – Qwest advised this CR was effective December 4. This CR will move to CLEC Test Status.

11/17/04 November meeting minutes Cindy Macy – Qwest advised this CR is still on track for December 2004 due date. This CR will remain in Development Status.

10/20/04 CMP Meeting Minutes Cindy Macy – Qwest advised this CR is still on track for December 2004 due date. This CR will remain in Development Status.

9/15/04 CMP Meeting Minutes Cindy Macy – Qwest advised this CR is still on track for target deployment in December 2004. This CR will remain in Development Status.

8/16/04 CMP Meeting Mintues Cindy Macy – Qwest advised that the target implementation date is December 2004. There is system work that needs to occur that is in progress. This CR will remain in Development Status.

07/21/04 July CMP Meeting: Cindy Macy – Qwest advised that this CR is effective October 18. The PCAT is currently being updated. This CR will remain in Development status until the CR is implemented in October.

06/16/04 June CMP Meeting Linda Sanchez-Steinke with Qwest said there is no new information since April’s update and implementation is tentatively scheduled for 10/16/04. This CR will remain in Development status.

-- 05/19/04 May CMP Meeting Linda Sanchez-Steinke with Qwest said last month’s update was that implementation is tentatively scheduled for 10/16/04. This CR will remain in Development status.

04/21/04 April CMP Meeting Anthony Washington with Qwest gave an update that the implementation date is tentatively scheduled for 10/16/04. We are currently finalizing the requirements. Bonnie Johnson with Eschelon asked if there were systems impacted. Anthony said FTS and Integrator are impacted. This CR will remain in Development status.

03/17/04 March CMP Meeting Linda Sanchez-Steinke with Qwest gave an update that funding approval has been received and we are waiting for an implementation date and will give an update on the implementation date at the April meeting or before if available. John Berard asked if all requirements for development were complete and which systems were being changed. Linda said the systems were not CLEC facing and could not answer if development was completed. This CR will remain in Development status.

- 02/18/04 February CMP Meeting Anthony Washington with Qwest provided an update that we have received funding approval and are waiting for an implementation date. This CR will remain in Development status.

01/21/04 January CMP Meeting Russ Urevig with Qwest gave an update that the Migration/Conversion PCAT will contain a link for unbundled loop scenarios and will explain if a single or a combination of LSRs is required. The documentation will be available in the late January timeframe and will be located at the end of the ordering section in the Migration/Conversion PCAT. This CR will remain in Development status.

12/17/03 December CMP Meeting Russ Urevig with Qwest said that there were questions submitting orders and the scenarios for migrations and conversions. Bonnie Johnson with Eschelon added they need to know how to submit the LSRs. Russ asked if the CR should be left open for this documentation change. Linda Sanchez-Steinke with Qwest said that the CR should remain open due to systems changes needed. This CR will remain in Development status.

11/19/03 November CMP Meeting Anthony Washington with Qwest gave an update on Scenario #1 and said that Qwest accepts this CR and the process changes will be initiated. Updates will be provided as the project moves forward. Jamal Boudhaouia with Qwest added that the CLECs should understand that the CLEC should provide the end user a modem and a profile should be ready and built in the new ISP to additionally minimize downtime. Bonnie Johnson with Eschelon said she did understand. Bonnie added that Qwest had announced PCAT changes associated with scenario #3 and needs to provide additional information on how to submit an LSR when ordering four voice retail lines to convert to an unbundled loop and one data line is converting to an unbundled loop with DSL service. Russ Urevig said that he is doing research and will determine if a PCAT update is needed. This CR will move to Development status.

10/15/03 October CMP Meeting Deb Smith with Qwest gave an update on Scenario #3 and #4. Updates have been made to PCATS for Line Sharing, Loop Splitting, Line Splitting, Unbundled Loops and Migrations and Procedures. The procedure identifies if 1 or more LSRs are needed and explains that downtime will not exceed 45 minutes. Kim Isaacs with Eschelon asked if the DSL notices were in the UNE loop PCAT. Deb Smith said the unbundled loop PCAT went out as a level 2 on 10/1/03. Kim said that she will review the changes and added that she didn’t know that the CR was associated with the PCAT.

Anthony Washington with Qwest gave an update on Scenario #1. Qwest SME’s held a meeting with Bonnie Johnson to discuss looking at separate service orders to resolve the CR. Qwest is re-evaluating and will have an update at the November meeting. This CR will remain in Evaluation status.

Meeting Minutes PC070103-3 September 30, 2003 1-877-572-8687, Conference ID 3393947# 1:00 p.m. - 1:45 p.m. Mountain Time

List of Attendees: Bonnie Johnson - Eschelon Janean Van Dusen - Qwest Cindy Schwartze - Qwest Anthony Washington - Qwest Michael Whitt - Qwest Linda Sanchez-Steinke - Qwest

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss CR PC070103-3 and Bonnie’s request at the September CMP meeting to review whether the process could be accomplished by Qwest initiating two service orders.

Bonnie said at the September CMP meeting, Qwest denied this CR because it was economically unfeasible due to changes to systems that would have to be done. Eschelon would like to convert customers with no downtime on DSL when a customer has a volume service provider. From a process perspective, issue an order to disconnect DSL volume service provider and ISP then consecutively issue an order to install Qwest DSL ISP of choice. This process would re-install the service order so the customer is not without DSL service.

Cindy Schwartze asked if Eschelon wants Qwest to take the LSR and if it has VISP remove that and keep the same speed, change the host and there will no outage of DSL. Bonnie agreed.

Bonnie said the response at September CMP didn’t make sense because systems would not need to be changed to accomplish, when it can be done by changing a process. An order could be issued with Qwest DSL staying or changing and another order, with one due date, the date of conversion, getting rid of the host and getting a new one. The request is not to have any downtime.

Anthony Washington asked how much downtime, Bonnie said that we have discussed this and Linda said that 45 minutes downtime had been identified as acceptable in the change request.

Janean Van Dusen said that we have legal and contractual obligations with the volume ISP.

Bonnie said that when the LSR is sent in, Qwest allows the disconnect of the volume ISP. Bonnie suggested that if we look at this as a process solution, we could use 2 service orders to accomplish the same thing, the volume ISP would go away, and the customer would not have the 5 day lag time without DSL. It is not logical that system changes would be required to accomplish the change request.

Cindy asked if this example would be accurate: Eschelon wants to issue 1 LSR to convert the account, remove the VISP, add or change what is existing for Qwest DSL with the same due date. Cindy further explained that today Eschelon issues 1 LSR to convert and remove the VISP and 1 LSR to add Qwest DSL and host. Bonnie said that the second LSR can’t be submitted until the VISP order is completed.

Michael Whitt asked if Eschelon would be willing to send more than 1 LSR. Bonnie said it is not Eschelon’s preference and it would leave more room for gaps and rejects in error. Bonnie asked if they would get IMA up front errors.

Cindy asked if there was a question about different modems for the end user and new I-host. Anthony said he did not believe that has anything to do with Qwest.

Cindy asked if the VCI/VPI would be an issue. Bonnie said that Qwest resale or Qwest retail change, VCI/VPI, on Qwest Q host on the same day.

Cindy said the CLEC gets the VCI/VPI within 1 hour and Integrator does translations.

Bonnie said that Eschelon is currently using this process with customers on Qwest retail DSL with Qwest ISP. Volume ISP is a contractual agreement. If it is not a Volume ISP and the costs are $1 M, what systems need to be changed and why does the process work currently when there is not a volume ISP.

Cindy Schwartze said that the VISP isn’t a resale-able product. Originally we rejected LSR’s because it wasn’t a resale-able product. Cindy said that Qwest needs to get everyone together for an estimate of what it would take.

Michael Whitt said that we can’t promise that the response will be different and said that we have been working on a way to provide the change requested. Bonnie said that the CMP process states that if the CR is denied that Qwest should provide details.

Linda asked if there were any additional questions. No questions were asked and Linda said that we would discuss this CR at the October CMP meeting.

09/17/03 September CMP Meeting Deb Smith with Qwest explained this CR was submitted jointly by Eschelon and Covad and was divided into Scenarios 1 through 4.

Deb read the draft response for Scenario 3, a Qwest Retail customer is converting to Eschelon (Facility based) and has Qwest DSL with or without a volume provider. Eschelon converts the line with DSL to a DSL (xDSL-I) Capable Loop. Qwest and Eschelon agreed that downtime will not exceed 45 minutes on these type of requests and will update the Unbundled Loop PCAT with this information.

Deb read the draft response for Scenario 4, Line Sharing, Line Splitting and Loop Splitting, has been addressed in a CR PC012703-2 and Qwest has updated the Migration and Conversion PCAT addressing the need for more than 1 LSR for each migration or conversion possible. The PCAT will be updated to reflect the 45 minute timeframe and will get the information to the documentation team by Friday. Notification of updated PCAT will be provided to the CLEC Community.

Anthony Washington read the draft response for Scenario #1. Liz Balvin with MCI said that the CMP document says that if a CR is denied as economically not feasible, then Qwest should provide some details around the costs in excess of one million dollars. Bonnie Johnson with Eschelon stated she wants Qwest to go back to the drawing board and determine if this can be done by issuing separate service orders. Eschelon wants to have Qwest DSL that same day and not 5 days later. A separate call will be held to discuss alternate process solutions to implement this scenario.

Anthony read the response for Scenario #2, Qwest is currently providing this capability. This CR will remain in Evaluation status.

CMP Meeting 08-20-03

Smith-Qwest presented the response; Qwest is still evaluating the request. The request was moved to Evaluation status.

===========================================

Sent: Fri 8/8/03 5:48 AM From: Bonnie Johnson To: Linda Sanchez-Steinke RE: Question Scenario #3 PC070103-3 Hi Linda, The customer in this scenario would be converting both voice and data to the CLEC. No services would be left with Qwest.

Let me know if this helps!

Have a good day!

Bonnie Johnson Sr. Manager ILEC Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724

Sent: Wed 8/6/03 1:31 PM To: Bonnie Johnson From: Linda Sanchez-Steinke Subject: Question Scenario #3 PC070103-3

Bonnie - Below is a question from Deb Smith, on CR PC070103-3. Would you respond back to me and I'll e-mail on to Deb.

Thank you Linda Sanchez-Steinke CRPM Qwest 303-965-0972

Scenario #3 Qwest Retail customer is converting to Eschelon (Facility based) and has Qwest DSL with or without a volume provider. Eschelon converts the line with DSL to a DSL (XDSL-I) capable loop.

Bonnie,

We need a bit more clarification on scenario #3. Our understanding of scenario #3 is that a Qwest Retail customer is converting both voice and data to Eschelon. Is that correct? If so, this would be a conversion to an Unbundled Loop xDSL-I reusing existing facilities (if facilities qualify). If the voice portion is remaining with Qwest, this is not a conversion and would require a new Unbundled Loop to the premise.

Any additional clarification would be greatly appreciated.

Thank you, Deb Smith

Mon 8/4/03 11:48 A From: Bonnie Johnson To: Linda Sanchez-Steinke RE: PC070103-3 Scenario #2

Linda, I clarified all of this on the clarification call, however, if Qwest needs further information then we need a call. Yes Qwest currently offers partial conversions but the DSL is disconnected at the time of conversion when they have a volume provider. Bonnie Johnson Sr. Manager ILEC Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724

From: Linda Sanchez-Steinke To: Bonnie Johnson Sent 8/4/03 8:36 Bonnie -

I am backfilling for Matt White and Anthony Washington had a question about PC070103-3, scenario #2.

The following is Anthony's question: Scenario #2 appears to be a partial conversion, which Qwest already makes available to CLECs. Therefore, explain how the scenario differs from a partial conversion, and or, revise the scenario in a manner that differs from scenario #1 and #3.

Bonnie, I've attached the scenarios and would you e-mail me back, if needed we can get Anthony on a conference call.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-965-0972

Clarification Meeting - 07-21-03

Attendees Matt White Deb Smith Crystal Soderlund Cindy Schwartze Janean Van Dusen Karen McClemic Bonnie Johnson John Berard

(NOTE: Prior to this meeting, Johnson-Eschelon forwarded three scenarios that involved the change requested in this CR. The text of this e-mail is included at the end of these minutes.)

White-Qwest described the purpose of the meeting and asked the Qwest attendees if they could articulate their questions to Bonnie.

Smith-Qwest thanked Johnson for the scenarios she provided by e-mail. She stated that there is mention in the CR of line splitting and line sharing. Johnson-Eschelon stated that Berard should send Qwest examples of these scenarios. Berard-Covad stated that he would send those examples. He stated that what he wanted to address is the down time that is involved with a conversion. Smith-Qwest asked if Covad was seeking to issue only one LSR. Berard-Covad stated that he was interested in only one LSR and the issue of the 5 days of down time.

Johnson-Eschelon stated that whatever process Qwest develops, even if it involves that CLECs need to send a separate LSR that piggybacks on the first one one, the due dates should match. Soderlund-Qwest asked what product Johnson was referring to. Johnson-Eschelon stated that she was interested in Resale, UNP-P, UNE loop, line sharing and line splitting. Soderlund-Qwest asked what the conversion would be from. Johnson-Eschelon stated that this was a very large CR that may have to be done in pieces. She emphasized that she wanted to ensure that no piece slipped through the cracks.

Schwartze-Qwest stated that she had reviewed the scenarios Johnson had send and that she wanted to better understand scenario 1. She explained that the CR included information about converting to resale or UNE. She asked if Johnson understood, that with 13.0, Qwest would remove the DVDP FID and then the CLECs would need to submit another LSR. She stated that he understanding was the Eschelon did not want to submit the additional LSR or be subjected to the 5-day due date. Johnson-Eschelon stated that all the work happens on the due date. Schwartze-Qwest asked if Eschelon wanted to be able to provide the new I-host to Qwest rather than disconnecting the DSL and having to order the feature on the line.

Van Dusen-Qwest asked what the difference was between scenarios 1 and 2. Johnson-Eschelon stated that scenario 2 is where the customer wants to keep DSL with MSN and Eschelon wants to opportunity to leave it behind. She stated that was doing a partial conversion where Eschelon leaves the line and DSL as they are. She explained that she was asking for a partial conversion but that she wanted the line and DSL to stay as a Qwest retail account. She stated that this would occur if a customer has 5 lines wherein one is 1FB with Qwest DSL with MSN and Eschelon wants to convert the other 4 lines. Smith-Qwest asked of the 3rd scenario referred only to unbundled capable XDSL-I. She confirmed that Eschelon wanted Qwest only to be validating that the line was DSL capable, not validating the dial tone. Johnson-Eschelon stated that Eschelon wants to reuse the facilities and turn it into a DSL capable loop.

Berard–Covad stated that he could prioritize the scenarios that have already been identified. He stated that Covad could not live with a 5-day disconnect. He explained that Covad wanted voice and DSL to have same due date. Soderlund-Qwest asked Berard and Johnson could provide Qwest with a prioritized list of all the examples that fell under this change. Johnson-Eschelon stated that she had provided her examples and that numbers 1 and 2 were her top priority. She explained that every example left the customer without service. She stated that she did not want Qwest to work these examples in series. She stated that she expected to work on these examples in parallel. Soderlund-Qwest stated that she wanted to ensure that Eschelon and Covad were on the same page when it came to the examples. She explained that Qwest needed to be sure that Eschelon’s and Covad’s priorities are the same. Berard-Covad stated that he would take Johnson’s examples and add any additional ones that he felt were appropriate. Johnson-Eschelon stated that Eschelon and Covad were jointly submitting the CR and that the big scope of the CR is that we don’t want our customers to be without DSL service. She stated that the intent of the CR is to have Qwest develop a process to avoid a situation where customers are making decisions to change to Eschelon or Covad and then changing their minds because they will be without service for 5 days. She explained that she want processes to stop this impact on the customers and that she did not want to have to prioritize her examples. She stated that Eschelon wanted them all to have top priority. She explained that she understood that each product might have a different timeframe depending on the scope of the change, but that she did not want to send a prioritized list because the CR is asking for Qwest to develop processes. Soderlund-Qwest thanked he for her input.

White-Qwest asked if there were any additional examples needed. Smith-Qwest asked if Covad was going to provide more examples. Berard-Covad stated that he would go through existing documentation and send any additional examples to White-Qwest. Berard-Covad asked if there were any instances when the DSL does not go down. Schwartze-Qwest stated that with the DVDP arrangement, DSL goes down on all sides. She stated that she was concerned about line sharing/splitting and loop sharing and asked if Berard could send outage examples for these products. Berard-Covad stated that the big examples for Covad are line sharing and line spliting. Johnson-Eschelon stated that she understand that there would be some outage time on the dure date because work must occur. Smith-Qwest stated that Berard had said that 45 minutes would be an acceptable amount of down time. Berard-Covad stated that he was fine with that. He understood that Qwest needed time to move and test the cross connects.

Johnson-Eschelon stated that she agreed. She also stated that her biggest challenge is getting the DVPIVCI info off Q-host. Schwartze-Qwest stated that she had been told that the integrator refreshes every hour. Johnson-Eschelon stated that her problem was with it getting translated.

White-Qwest confirmed that there were no more questions. Johnson-Eschelon asked that if Qwest had any questions that they contact her for an impromptu meeting or call.

Text of e-mail message from Bonnie Johnson:

Scenario #1 Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and hasQwest DSL with the DVDP FID. Eschelon sends conversion request and retains Qwest DSL but changes the ISP host (we do these today when the customer does not have volume provider arrangement).

Scenario #2 Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and has Qwest DSL with the DVDP FID. Eschelon sends conversion request and requests the line with Qwest DSL with volume provider stay with Qwest and Eschelon converts all or a part of the remaining account (we do these today when the customer does not have volume provider arrangement).

Scenario #3 Qwest Retail customer is converting to Eschelon (Facility based) and has Qwest DSL with or without a volume provider. Eschelon converts the line with DSL to a DSL (XDSL-I) capable loop.

07-17-03 Clarification Meeting

Attendees Matt White - Qwest Deb Smith – Qwest Heidi Moreland - Qwest Crystal Soderlund - Qwest Monica Manning - Qwest Karen McClimek - Qwest Janean Van Dusen - Qwest Cindy Schwartze - Qwest Terry Kilker - Qwest Anthony Washington - Qwest John Berard - Covad

White-Qwest welcomed the attendees and explained the purpose of the call. He asked Berard-Covad to review the change. Berard-Covad reviewed the change. On any data migration CLECs should submit a single LSR for both voice and data. Similarly, the migration should get one due date for voice and data and there should be no more than 30-45 minutes of down time instead of five days. Soderlund-Qwest asked if Berard was talking about all of the shared products for this CR. Berard-Covad stated that he was. Smith-Qwest what UNE-P products the CR was referring to. Berard-Covad stated that the CR sought that the existing UNE P migration process now be linked to the data product. He stated that it encompasses many different scenarios and that Covad was looking for no down time for customers who ask for no down time. There was further discussion of different scenarios that this CR may apply to. Various Qwest SME’s asked that Berard and Johnson create a list of all possible scenarios that this CR would apply to so they could more appropriately respond to the request. Berard-Covad stated that he would like to have another clarification call with Johnson-Eschelon on the line. He stated that Covad and Eschelon would produce a list of all possible scenarios. White-Qwest stated that he would schedule another clarification call. He thanked the attendees and adjourned the meeting.

============================================ CMP Meeting 07-16-03

White-Qwest stated that this CR will have the clarification meeting on 7/17. Johnson-Eschelon presented the CR. CR to Presented status.


CenturyLink Response

November 11, 2003

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting

Bonnie Johnson Director Eschelon Telecom Inc. 720 2nd Avenue South, Suite 1200 Minneapolis, MN 55402

SUBJECT:Qwest’s Change Request Revised Response PC070103-3 DSL Volume provider and data migration process to prevent extended DSL outage

This letter is in response to CLEC Change Request PC070103-3, scenario number one, re-evaluation. This CR is a request by Eschelon for Qwest to reduce its current provisioning interval for VISP conversions from the standard 5 days to a much more reasonable timeframe.

Qwest will accept this request. The following provides details surrounding this decision.

Qwest will allow CLECs to submit one LSR to convert VISP end users. The conversion process involves changing the host through a C & T action on the service order; therefore, Qwest will remove the VISP arrangement while not taking down the DSL service. This will alleviate the need for CLECs to submit two LSRs, one to remove the VISP and another to add the DSL service five days later.

The conversion process will maintain the DSL service but the host change will require the standard five day interval.

The new conversion process will impact several systems. After an analysis of the impact, Qwest has determined that more then 350 hours is required to complete systems changes, and develop and document the new process. Therefore, Qwest will schedule and complete the system changes, and develop the new process as soon as possible, and will provide updates as they become available.

Sincerely,

Anthony Washington Product Management Qwest

September 30, 2003

REVISED DRAFT RESPONSE For Review by CLEC Community and Discussion at the October 2003 CMP Meeting

Bonnie Johnson Eschelon

John Berard Covad

SUBJECT: Qwest’s Change Request Response - PC070103-3

Scenario #1 "Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and has Qwest DSL with the DVDP FID. Eschelon sends conversion request and retains Qwest DSL but changes the ISP host."

During the September 17th CMP meeting Qwest denied Scenario #1 of CR PC070103-3 based on it being economically unfeasible. At that time, we were asked if it would be possible to accept the CR if Qwest Wholesale changed the process to allow one LSR and two services orders.

Currently we are re-evaluating this process change and identifying all the of the necessary process and systems changes that would be impacted. Therefore, we require more time to verify if it is possible to provide a minimal outage situation when a CLEC wishes to change the ISP host.

Sincerely,

Anthony Washington Product Manager

September 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the September 17, 2003 CMP Meeting

Bonnie Johnson Eschelon

Mike Zulevic Covad

SUBJECT: Qwest’s Change Request Response - PC070103-3

This letter is in response to CLEC CR PC070103-3. This CR is a joint request from Covad and Eschelon to request that migrations (voice, data or voice/data) are obtained with a single LSR and minimal interruption of service. Clarification calls were held on July 17 and 21 to further identify the migration scenarios. Eschelon provided Qwest four scenarios. In this response, Qwest will provide responses to each of the scenarios separately.

Scenario #1 "Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and has Qwest DSL with the DVDP FID. Eschelon sends conversion request and retains Qwest DSL but changes the ISP host."

Qwest response: The proposed change to the existing retail DSL product and processes would require resource allocation and expenditures associated with legacy systems and software specifications in excess of one million dollars. Information Technology redesigns would include systems changes to the electronic business to business system for each VISP provider, which would require considerable funding and a redirection of scarce technology resources. This would also include, to a significant extent, additional expense for producing and implementing changes to system performance and functionality of the Qwest VISP Graphical User Interface (GUI) and XML Interface, as well as require manual interaction to allow for communications with respect to Qwest retail customer changes and current status. Additional changes likely include significant modifications to existing ordering and processing systems and functionality, which would be a considerable burden at a great expense to Qwest.

Qwest respectfully denies Scenario #1 of this CR based on economic unfeasibility.

Scenario #2 "Qwest Retail customer is converting to Eschelon (Resale or UNE-P) and has Qwest DSL with the DVDP FID. Eschelon sends conversion requests and requests the line with Qwest DSL with volume provider stay with Qwest and Eschelon converts all or a part of the remaining account."

Qwest response: Qwest allows partial conversions of existing Qwest retail end user accounts to UNE-P or Resale services. In the instance where an existing retail end user account has more than one (1) line and one (1) or more of those lines has Qwest DSL Host Volume Discount Program arrangements (indicated by the presence of a DSL USOC followed by a ‘DVDP’ FID), CLEC may convert the entire account or specify certain lines for conversion.

If CLEC chooses to convert lines with DSL Host Volume Discount Program arrangements, as noted in the UNE-P with Qwest DSL PCAT, the (http://www.qwest.com/wholesale/pcat/unepqdsl.html) and similarly in the Resale DSL PCAT (http://www.qwest.com/wholesale/pcat/resaledsl.html), "Qwest will remove the DSL USOC and the DVDP FID from the account. This activity will remove end-user DSL functionality".

If CLEC chooses to convert only lines without DSL Host Volume Discount Program arrangements, the remaining retail lines with the DSL Host Volume Discount Program arrangements will remain in service.

Because Qwest currently offers this capability, Qwest accepts this Scenario of the CR.

Scenario #3 "Qwest Retail customer is converting to Eschelon (Facility based) and has Qwest DSL with or without a volume provider. Eschelon converts the line with DSL to a DSL (xDSL-I) Capable Loop."

Qwest response: Unbundled Loop Scenario #3 is a conversion of Qwest Retail customer’s service to the CLEC requested xDSL-I Unbundled Loop. The CLEC would submit 1 LSR to convert the Qwest Retail customer to the requested xDSL-I Unbundled Loop service with or without number portability. A disconnect will be performed on the end customer’s Qwest Retail service at the time of the migration activities.

During the PC070103-3 clarification meeting held on July 21, 2003, Covad, Eschelon and Qwest agreed that their request required that the activities of the migration not exceed 45 minutes. The migration activities would include the termination at the ICDF and any associated tests. For the Unbundled Loop services the migration work activities won’t exceed the 45-minute time frame.

Qwest accepts Scenario #3 of this CR. Qwest will update the Unbundled Loop General PCAT to reflect the migration activities will not exceed 45 minutes.

Scenario #4 Line Sharing, Line Splitting and Loop Splitting

Qwest response: In accordance with the Qwest response to PC012703-2, Data Migrations, the Migrations and Conversions Procedural PCAT (http://www.qwest.com/wholesale/clecs/migrateconvert.html) has been updated (in accordance with CMP timelines) with CLEC input on identification of the Data Migration scenarios for Line Sharing, Line Splitting and Loop Splitting. In that documentation, Qwest identifies, by scenario, whether a specific migration would require 1 LSR or multiple LSR’s. If the migration request currently requires more that 1 LSR, Qwest has provided the IMA (15.0) release that effects the change to 1 LSR.

During the PC070103-3 clarification meeting held on July 21, 2003, Covad, Eschelon and Qwest agreed that the activities of the migration will not exceed 45 minutes. The migration activities would include the ‘lift and lay’ of the cross connects and any associated tests. For the Line Sharing, Line Splitting, and Loop Splitting services the migration work activities won’t exceed the 45-minute time frame.

Qwest accepts Scenario #4 of this CR. We have responded, identified and documented the Line Sharing, Line Splitting and Loop scenarios as a result of PC012703-2, Data Migrations. Qwest will update the Data Migration scenarios for Line Sharing, Line Splitting and Loop Splitting (downloadable links) to reflect the 1 LSR vs. multiple and the IMA (15.0) release that effects the change to 1 LSR. Qwest will update the Line Sharing, Line Splitting, and Loop Splitting PCATs to reflect the migration activities will not exceed 45 minutes.

Sincerely,

Deb Smith Product Manager

Anthony Washington Product Manager

August 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the August 20, 2003 CMP Meeting

Bonnie Johnson Eschelon

Mike Zulevic Covad

SUBJECT: Qwest’s Change Request Response - PC070103-3

This is a preliminary response regarding the Eschelon/Covad CR PC070103-3. This CR requests a DSL Volume provider and data migration process to prevent extended DSL outage.

Qwest is currently evaluating this request. Because this request involves the creation of a complex and wide-reaching process, there are a large number of issues Qwest must analyze. Qwest proposes moving this Change Request into Evaluation Status and while we continue to investigate and provide an updated response.

Qwest will provide a status update at the September CMP meeting.

Sincerely,

Deb Smith Product Manager


Open Product/Process CR PC082703-1 Detail

 
Title: Qwest to form CEMR User group
CR Number Current Status
Date
Area Impacted Products Impacted

PC082703-1 Completed
1/21/2004
Maintenance / Repair
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Foster, Beth
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Eschelon requests that Qwest form a CEMR Users group. The group would meet every two weeks (or with some designated frequency) and discuss CEMR challenges. The group would also recommend modifications and improvements to increase CEMR usage. Qwest communicates to the CLEC Community (both in CMP and through the Qwest Service Management Team) that Qwest has an interest in increasing CEMR usage. Eschelon has communicated many CEMR challenges through the Service Management Team, however, Eschelon feels that having Qwest SMEs talk directly to the CLEC CEMR users would be more effective and efficient. The group could collectively decide what system and/or process changes could be requested to increase the usage of CEMR.

Expected Deliverable:

Qwest will form a CEMR Users group, track issues to resolution and follow through with Qwest/CLEC recommended changes that result from the CEMR Users group. The group should meet on a regular basis and include CLEC CEMR Users and Qwest CEMR SMEs.


Status History

08/27/03 - CR Submitted by Eschelon

08/29/03 - CR Acknowledged

09/11/03 - Held Clarification Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/15/04 - Qwest issued CMP Implementation Notice Level 1 PROS.01.15.04.F.01249.CEMR_UserGroup effective 1/16/04

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

1/21/04 January CMP Meeting Linda Sanchez-Steinke with Qwest gave an update that Qwest issued CMP Implementation Notice Level 1 effective 1/16/04 that stated the CEMR user group would hold meetings, and the next meeting will be held on 1/28/04 from 9:30 AM -10:30 AM. Linda asked if this CR could be moved to Completed status. Bonnie Johnson agreed that the CR could be closed and said that in reading the notes from the last CEMR Users Group meeting she wanted to make clear that the intent of the meetings is to bring CEMR issues and challenges forward. Bonnie said she sensed that the Qwest employees are not accepting of changes to CEMR that are suggested by the CLECs. Connie Winston said that she would bring the issues up and discuss with the employees. Liz Balvin asked if the intent of the User Group is to bring forward issues and identify changes that could take place in CEMR. Bonnie said yes and the meetings are much like the DSL Loop Qual users group. The first meeting was a kick off and the users guide was reviewed. Then the CLECs presented a wish list and explained issues, and challenges which opened up discussion on how to do things in the system. Bonnie said this has been helpful because of all the work involved when submitting a CR. Bonnie has submitted one CR and will submit additional CRs. (Begin comment from Bonnie Johnson – Eschelon) Bonnie said that the decision to open CRs would not be made on the calls and only wants Qwest tell Eschelon if the functionality already exists or if a CR is required. (end comment). Liz brought up that it would be helpful to have a systems architecture overview at the next CLEC Forum. Qwest will open an Action Item. This CR will move to Completed status.

12/17/03 December CMP Meeting Linda Sanchez-Steinke with Qwest gave an update that the CEMR group had met on 11/21 and will meet on 12/18. Bonnie Johnson with Eschelon said that this group is beneficial with the CEMR upgrade. Bonnie encouraged other CLECs to send in their “wish list” because it helps determine if changes are feasible, provide a better way to get information or if functionality is there already. Beth Foster with Qwest said that the 12/18 meeting will be held at 9:00 Mountain time. This CR will move to CLEC Test status.

11/19/03 November CMP Meeting Linda Sanchez-Steinke with Qwest said that Beth Foster has scheduled the first CEMR CLEC Technical Forum on 11/21/03. This CR will remain in Development Status.

10/15/03 October CMP Meeting Bonnie Johnson with Eschelon said that she had received the draft response from Qwest and that the user’s group would meet monthly. Beth Foster with Qwest talked with Bonnie after the CR was discussed and said that the user’s group would start after the next CEMR release. This CR will be moved to Development Status.

09/17/03 September CMP Meeting Bonnie Johnson with Eschelon presented this CR. Bonnie said we held the Clarification Meeting and she submitted the CR because Eschelon wants to increase CEMR usage and recently filled out a survey about CEMR. By Qwest forming a CEMR users group, there would be an opportunity to discuss roadblocks, challenges and discuss high level feasibility for changes. CRs would be issued through the CMP process and the user group would not bypass CMP. MEDIACC is different enough from CEMR that it would not be included in this user group. This CR will be moved to Presented Status.

CLEC Change Request Clarification Meeting

2:00 p.m. (MDT) / Thursday September 11, 2003

1-877-572-8687 3393947# PC082703-1 Qwest to form CEMR User group

Name/Company: Bonnie Johnson, Eschelon Jeanne Whisenant, Qwest Dan Busetti, Qwest Elle Dornan, Qwest Beth Foster, Qwest Cathy Garcia, Qwest Craig Suellentrop Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Eschelon requests that Qwest form a CEMR Users group. The group would meet every two weeks (or with some designated frequency) and discuss CEMR challenges. The group would also recommend modifications and improvements to increase CEMR usage. Qwest communicates to the CLEC Community (both in CMP and through the Qwest Service Management Team) that Qwest has an interest in increasing CEMR usage. Eschelon has communicated many CEMR challenges through the Service Management Team, however, Eschelon feels that having Qwest SMEs talk directly to the CLEC CEMR users would be more effective and efficient. The group could collectively decide what system and/or process changes could be requested to increase the usage of CEMR. Bonnie said the CR was issued because increasing electronic usage and repair is one of Qwest’s desires. Eschelon is one of the top users of CEMR. When Bonnie met with the Repair Manager and one of the users of CEMR at Eschelon and filled out the recent survey and they had good ideas. Recently Covad submitted a CR for a User’s Group for Loop Qual.

Bonnie said that forming a CEMR users group and having users talk directly to Dan would be beneficial for everybody and would increase usage. Frequency probably every month. Beth said this is a good idea and asked if this group is similar to the SATE process. Bonnie said her preference is that the CEMR Users Group meeting be held at a designated time different from CMP, because the subset of people at Eschelon that would be attending are not part of the CMP meetings. The CEMR Users Group meeting could be helpful for 6 months, until they have worked through all issues. Beth mentioned that SATE was a separate meeting and then participation dropped off and asked if we could add to the CR that the frequency of the meeting be revisited in six months. Bonnie said that the CEMR users Group, when participants are identified the group could determine the frequency of their meetings.

Bonnie provided an agenda item example sent to her Service Manager; what are the short/long term plans for CEMR. Additional topics would include the physical system, what changes make sense and are feasible to submit for CRs. Bonnie said that CEMR and MEDIACC are just different enough that they should be kept separate. Dan and Cathy agreed.

Dan asked if the Users Group would focus on technical issues. Bonnie said that we would specifically talk about the system itself. When she filled out the survey, the repair person had a lot of ideas for improvement and making the system more user friendly. Other CLECs would provide their input also and the group could discuss logical changes that could be submitted. Bonnie said that she realizes she would have to submit CRS for changes. It may be helpful for Qwest to understand possible changes to make to CEMR by having the CLECs list reasons they call in a trouble ticket rather than use CEMR. Eschelon calls in tickets when it is close to conversion time and they don’t own the account.

Cathy Garcia asked if something is identified as a possible change how quickly they would expect to get the change completed. Bonnie said that there are several CEMR releases throughout the year and usually if a CR is submitted they can get it into the next release.

Confirm Areas & Products Impacted Maintenance / Repair

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation Qwest will form a CEMR Users group, track issues to resolution and follow through with Qwest/CLEC recommended changes that result from the CEMR Users group. The group should meet on a regular basis and include CLEC CEMR Users and Qwest CEMR SMEs.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Bonnie will present this CR at the September CMP Meeting. Qwest will provide a response at the October CMP meeting.


CenturyLink Response

October 1, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the October 15, 2003 CMP Meeting

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response – PC082703-1 “Qwest to form CEMR User group”

This letter is in response to Eschelon's Change Request (CR) PC082703-1. This CR requests that Qwest form a CEMR Users group.

Qwest accepts this CR and will move forward with the following:

- A process and the structure of a Monthly Technical Forum focused on use of the CEMR application.

- Qwest will chair the calls and will have resources available to answer questions asked during the forum.

- Qwest proposes that the first few meetings will be dedicated to bringing the CLECs up to date with CEMR functionality. Subsequent meetings will be structured to fit the CLECs needs for understanding and using the CEMR interface.

- The forum effectiveness will be monitored to determine future meeting need and frequency.

Qwest requests this CR be placed in Development Status and will provide an update at the November CMP Meeting.

Sincerely,

Beth Foster Qwest


Open Product/Process CR PC063003-1X Detail

 
Title: Flow through report made available to each CLEC in a timely manner. This long term request is for the information in IMA on a real time basis.
CR Number Current Status
Date
Area Impacted Products Impacted

PC063003-1X Denied
1/21/2004
All
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: McArthur, Ellen
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest should make available a report for each CLEC that reports errors causing a flow through eligible order to drop from the flow through process. Qwest currently does not provide this data though it does have the data internally at Qwest. Qwest did provide the data at one time; however, in the report Qwest provided included those errors caused by Qwest’s required manual processes. Therefore, the report was of no benefit. Qwest should develop a report that will provide each CLEC information needed to prevent flow through eligible orders from dropping out of the flow through process. The report should contain only valid information. The report should not include that information that is a result of Qwest’s required manual and workaround processes.

Expected Deliverable:

Qwest will make available a flow through error report for each CLEC. Qwest will ensure the data is valid and does not include those flow through eligible errors that are a result of Qwest’s required manual processes. Long term - the data would be available in IMA on a real time basis.

(Manual Solution CR created for short-term solution: PC063003-1MNX)


Status History

06/30/03 CR Submitted

07/01/03 CR Acknowledged

07/01/03 Related Change Request: CR Created for long-term request: PC063003-1X

07/01/03 Info Requested From CLEC: Sent email to Bonnie Johnson/Eschelon asking for Clarification Meeting Availability.

07/09/03 Clarification Meeting Held: See Project Meetings Section for Meeting Minutes

07/29/03 Status Changed: CR Placed in Evaluation and Impacted Interface Changed to 'Other'

8/20/03 CR crossed over to Product Process

9/17/03 - Sep CMP meeting notes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP Meeting minutes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database


Project Meetings

January 21, 2004 CMP Meeting Ellen MacArthur – Qwest reviewed the denial. Ellen said that Qwest has denied this request for economically not feasible reasons due to the additional resources that would be needed to manually produce the report. Bonnie Johnson – Eschelon advised she is surprised that this has taken so long to deny. Bonnie asked per this denial, is Qwest stating that everything that goes through IMA and that drops out has a reject or error. We are talking about orders that drop from flow through and that we have to manually type. Do all orders always get an up front edit or reject or non-fatal error? Ellen advised orders that are marked manual handling will drop. Bonnie advised she is not talking about those. Bonnie asked can’t Qwest separate the CLECs from the larger report? Ellen advised that is the difficult process. The report is large and requires a lot of manual investigation, and we have found that a majority of the errors are Qwest errors. The errors that are the responsibility of the CLECs are a small percentage, and those are provided to the CLECs via other means (rejects, errors, etc). Connie Winston agreed that Qwest rejects the majority of errors. We do drop some for pending order issues. Bonnie advised based on the denial letter, if something falls out of flow through it is not CLEC caused. Ellen advised the majority of the CLEC errors are identified via rejects and edits. If it is not caught by the center, it could be an error. This CR will move to Denied Status.

December 17, 2003 CMP Meeting Ellen McArthur – Qwest advised she is still working on the error analysis. This is a larger effort than originally expected. IT is still working on the LOE also. Bonnie Johnson – Eschelon asked about the short term and long term request. Bonnie advised the notes imply Qwest is working on the short term request but not the long term request. Bonnie would like to get the long term request in front of IT / IMA to determine impacts. She would like to have this worked on simultaneously. Kit advised we can talk to IT and talk about this at the systems meeting this afternoon. This CR will remain in Development Status.

November 19, 2003 CMP Meeting Ellen McArthur – Qwest advised that during this month Qwest has identified a tagging process for the 1000+ errors that can occur. Error validation, data loading, data testing and changes to screens are all underway and progress is being made. The CLECs asked how will they get access to the report? Ellen advised that is under development but it is anticipated to be sent via email. If you are interested in receiving the report you would sign up with your Service Manager and the report would come via email. Bonnie Johnson- Eschelon asked if we have a timeline for this effort yet. Ellen advised IT is developing the Level of Effort at this time. The question was asked regarding the long-term request to provide these results via IMA and how that would be handled. It was agreed the CR would probably be crossed over to systems at that time.

October 15, 2003 CMP Meeting Ellen MacArthur – Qwest advised she has taken over this project from Shon Higer. Current activities include loading, validating and testing the data. This is a very large effort but progress is being made. Bonnie Johnson – Eschelon asked when the validation of data will be completed. Ellen advised she does not have a timeline as of yet. Judy Schultz-Qwest asked for Ellen to determine a timeline and let us know next month. This CR will remain in Development Status.

September 17, 2003 CMP Meeting Shon Higer advised he is currently validating data, getting ready for an initial data load, identifying delivery method, fields to include, security and CPNI requirements. Bonnie asked will this report be delivered on a real time basis. The most critical is getting accurate and timely data and delivery. Bonnie advised she is looking for a report that tells the CLECs what they can fix. Shon advised this is a manual report, it is not directly from IMA. Connie advised IMAs understanding of manual processes is not as clear as Shon’s understanding. Shon is working on filtering the data. Bonnie asked if we discussed the frequency of the report. Shon asked Bonnie for her preference? Bonnie advised weekly or biweekly. Shon explained it takes several days for all the data to come together. Bonnie agreed biweekly is okay. Shon advised the plan is to have one report for EDI and one report for GUI. This report will be a good training tool. Discussion took place regarding analyzing the ‘error data’ to drive system changes and improvements. Jill Martain advised Qwest does open CRs as a result of data analysis. If Qwest opens CRs as a result of analysis we can reference that in the CR. Qwest advised we opened two CRs originally but due to the solution we will close PC063003-1XMN and retain PC063003-1X.

August 21, 2003 Systems CMP Meeting Discussion: Kit Thomte/Qwest stated that this CR would be crossed-over to Product/Process. There were no questions or comments.

- August 13, 2003 Email Sent to Bonnie Johnson/Eschelon: Hi Bonnie, This email is in regard to your submitted CMP CR’s SCR063003-01 Flow through report made available to each CLEC in a timely manner. This long-term request is for the information in IMA on a real time basis, and SCR063003-01MN Flow through report made available to each CLEC in a timely manner with regular frequency (short term). In reviewing these requests and based on the discussion that took place on July 9th conference call, it has been determined that there really is no coding to be done for these, they look to be generation of reports. This results in these CR’s being crossed over to Product/Process during the August Systems CMP Meeting and the Impacted Release being revised from IMA to ‘Other’ for both of these CR’s. They will be included in the August Product/Process CMP Meeting distribution package, as well as the Systems distribution package. Shon Higer will attend the Product/Process Meeting to answer any questions in regard to this. If you do have questions prior to the CMP Meeting, please send them to me and I will assist in getting the answers for you. Thank you, Peggy Esquibel-Reed Qwest CRPM -- Systems

- CLARIFICATION MEETING - July 9, 2003 ATTENDEES: Bonnie Johnson (Eschelon), Stephanie Prull (McLeod), Julie Pickar (USLink), Jackie Diebold (USLink), Peggy Esquibel Reed (Qwest, Shon Higer (Qwest), Nicole James (Qwest), Berkley Loggie (Qwest), Kimberly Powers (Qwest), Deb Roth (Qwest) REVIEW CR DESCRIPTION: Peggy Esquibel-Reed (Qwest) reviewed the CR description: Qwest should make available a report for each CLEC that reports errors causing a flow through eligible order to drop from the flow through process. Qwest currently does not provide this data though it does have the data internally at Qwest. Qwest did provide the data at one time; however, in the report Qwest provided included those errors caused by Qwest’s required manual processes. Therefore, the report was of no benefit. Qwest should develop a report that will provide each CLEC information needed to prevent flow through eligible orders from dropping out of the flow through process. The report should contain only valid information. The report should not include that information that is a result of Qwest’s required manual and workaround processes. Expected Deliverable: Qwest will make available a flow through error report for each CLEC. Qwest will ensure the data is valid and does not include those flow through eligible errors that are a result of Qwest’s required manual processes. Long term - the data would be available in IMA on a real time basis. (Manual Solution CR created for short-term solution: SCR063003-01MN) CONFIRMED IMPACTED INTERFACE: IMA Common CONFIRMED IMPACTED PRODUCT’S: All DISCUSSION: Bonnie Johnson (Eschelon) stated that she would like the report to look like the jeopardy report and stated that it goes directly to the person who made the request, via a notification. Bonnie stated that she would leave it up to Qwest how to do the report. Shon Higer (Qwest) asked if the request is for a separate notification for the flowthrough errors. Bonnie Johnson (Eschelon) stated yes and that it would contain why order did not flow through. Shon Higer (Qwest) asked if the report is to be downloadable. Bonnie Johnson (Eschelon) responded yes. Bonnie Johnson (Eschelon) asked Stephanie Prull (McLeod) if the EDI report should be a report or real-time? Bonnie stated that would need something such as the PON. Stephanie Prull (McLeod) stated that for EDI, she would like a report. Bonnie Johnson (Eschelon) stated that the report should have a contact name. Bonnie Johnson (Eschelon) stated that the report would help in identifying how to send orders. Bonnie stated that if Qwest cannot prevent something from appearing on the report would like an indicator to flag that. Deb Roth (Qwest) asked that if the report is downloadable, is it to be daily and how long should the report be available? Bonnie Johnson (Eschelon) stated that she would like the report to be available for 2-weeks if it is a daily report or if the report is a weekly report, needs available for a month. Stephanie Prull (McLeod) agreed with Bonnie. Deb Roth (Qwest) stated that there could be more than one reason for the fallout and asked if the CLECs want to see all the incorrect fields? Bonnie Johnson (Eschelon) stated yes, if three fields are wrong, report the three fields. Bonnie Johnson (Eschelon) stated that the report is more critical for the GUI. There were no additional questions or comments. ACTION PLAN: This CR to be presented at the August Systems CMP Meeting. The call was ended.


CenturyLink Response

January 2, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the January 21,2004 CMP Product/Process Meeting

Bonnie Johnson Eschelon

SUBJECT: Flow through report made available to each CLEC in a timely manner. The long-term request is for the information in IMA on a real time basis. CR # PC063003-1X

This CR is asking Qwest to make available a CLEC-specific report of CLEC errors which cause a flow through eligible order to drop from the flow through process.

Qwest attempted to develop a mechanized solution to deliver an individual CLEC report as requested. Due to the complexity of the error messages that are received, and the variance in failure reasons that can occur within a single error message, Qwest has been unable to define a mechanized means in which to correctly tag specific error messages as CLEC caused. Furthermore, the requested Report would include fewer than 1% of flow-through eligible LSRs that have a CLEC-caused error.

In 2002, Qwest had provided to CLECs an ad-hoc manual report. The Report was manually created and provided during a time when the flow-through results were less robust and when system and process changes were undergoing additional improvements. Over the past year and a half, Qwest has made many improvements to its system and manual processes and more than 99% of LSRs containing CLEC created errors now receive fatal reject or error notifications. Qwest continues to enhance systems and introduce process changes to ensure LSRs are being submitted correctly in order to reduce all error conditions. Additionally, the Reject and Error Notification Process was implemented to report to the CLEC that there are one or more fatal or non-fatal errors on a LSR that is prohibiting either a LSR to be submitted into IMA, or is prohibiting orders to be created correctly. These notices currently provide an error reason and explanation.

Since Qwest already provides the information on an LSR by LSR basis and has resources available to the CLEC to help ensure that they submit LSRs correctly (i.e., the PCATs and reject and error notifications) Qwest is denying this request. Qwest sees no demonstrable business benefit in utilizing manual resources to report Qwest vs. CLEC caused errors for the small percentage of LSRs that did not have fatal reject or error notifications sent to the CLEC. Additionally, it is not economically feasible for Qwest to dedicate necessary resources to this effort when almost all CLEC caused reasons are already being provided on reject and error notifications.

Ellen McArthur Wholesale Markets Process Organization

Draft Response

August 13, 2003

SCR063003-01 Flow through report made available to each CLEC in a timely manner. This long-term request is for the information in IMA on a real time basis.

Based on information received during the Clarification Call (held July 9, 2003) and additional research, this CR will be crossed-over to Product/Process at the August CMP Meetings. There is no system coding to be performed for this effort.

Sincerely, Qwest


Open Product/Process CR PC063003-1MNX Detail

 
Title: Flow through report made available to each CLEC in a timely manner with regular frequency (short term).
CR Number Current Status
Date
Area Impacted Products Impacted

PC063003-1MNX Crossover
7/27/2009
All
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Higer, Shon
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest should make available a report for each CLEC that reports errors causing a flow through eligible order to drop from the flow through process. Qwest currently does not provide this data though it does have the data internally at Qwest. Qwest did provide the data at one time; however, in the report Qwest provided included those errors caused by Qwest’s required manual processes. Therefore, the report was of no benefit. Qwest should develop a report that will provide each CLEC information needed to prevent flow through eligible orders from dropping out of the flow through process. The report should contain only valid information. The report should not include that information that is a result of Qwest’s required manual and workaround processes.

Expected Deliverable:

Qwest will make available a flow through error report for each CLEC. Qwest will ensure the data is valid and does not include those flow through eligible errors that are a result of Qwest’s required manual processes. Short term the report should be provided on Friday for data the week before.

(Mechanized Solution CR Created for long-term request: PCR063003-1X)


Status History

06/30/03 CR Submitted

07/01/03 CR Acknowledged

07/01/03 Related Change Request: CR Created for long-term request: PC063003-1X

07/01/03 Info Requested From CLEC: Sent email to Bonnie Johnson/Eschelon asking for Clarification Meeting Availability.

07/09/03 Clarification Meeting Held: See Project Meetings Section for Meeting Minutes

07/29/03 Status Changed: CR Placed in Evaluation and Impacted Interface Changed to 'Other'

8/20/03 August CMP Meeting minutes posted to the database

9/17/03 - Sep CMP meeting notes will be posted to the database. This CR was closed and PC063003-1X will be used to track this CR


Project Meetings

September 17, 2003 Product Process CMP Meeting (see PC063003-1X) Shon Higer advised he is currently validating data, getting ready for an initial data load, identifying delivery method, fields to include, security and CPNI requirements. Bonnie asked will this report be delivered on a real time basis. The most critical is getting accurate and timely data and delivery. Bonnie advised she is looking for a report that tells the CLECs what they can fix. Shon advised this is a manual report, it is not directly from IMA. Connie advised IMAs understanding of manual processes is not as clear as Shon’s understanding. Shon is working on filtering the data. Bonnie asked if we discussed the frequency of the report. Shon asked Bonnie for her preference? Bonnie advised weekly or biweekly. Shon explained it takes several days for all the data to come together. Bonnie agreed biweekly is okay. Shon advised the plan is to have one report for EDI and one report for GUI. This report will be a good training tool. Discussion took place regarding analyzing the ‘error data’ to drive system changes and improvements. Jill Martain advised Qwest does open CRs as a result of data analysis. If Qwest opens CRs as a result of analysis we can reference that in the CR. Qwest advised we opened two CRs originally but due to the solution we will close PC063003-1XMN and retain PC063003-1X.

August 21, 2003 Systems CMP Meeting Discussion: Kit Thomte/Qwest stated that this CR would be crossed-over to Product/Process. There were no questions or comments.

- August 13, 2003 Email Sent to Bonnie Johnson/Eschelon: Hi Bonnie, This email is in regard to your submitted CMP CR’s SCR063003-01 Flow through report made available to each CLEC in a timely manner. This long-term request is for the information in IMA on a real time basis, and SCR063003-01MN Flow through report made available to each CLEC in a timely manner with regular frequency (short term). In reviewing these requests and based on the discussion that took place on July 9th conference call, it has been determined that there really is no coding to be done for these, they look to be generation of reports. This results in these CR’s being crossed over to Product/Process during the August Systems CMP Meeting and the Impacted Release being revised from IMA to ‘Other’ for both of these CR’s. They will be included in the August Product/Process CMP Meeting distribution package, as well as the Systems distribution package. Shon Higer will attend the Product/Process Meeting to answer any questions in regard to this. If you do have questions prior to the CMP Meeting, please send them to me and I will assist in getting the answers for you. Thank you, Peggy Esquibel-Reed Qwest CRPM -- Systems

- CLARIFICATION MEETING - July 9, 2003 ATTENDEES: Bonnie Johnson (Eschelon), Stephanie Prull (McLeod), Julie Pickar (USLink), Jackie Diebold (USLink), Peggy Esquibel Reed (Qwest, Shon Higer (Qwest), Nicole James (Qwest), Berkley Loggie (Qwest), Kimberly Powers (Qwest), Deb Roth (Qwest) REVIEW CR DESCRIPTION: Qwest should make available a report for each CLEC that reports errors causing a flow through eligible order to drop from the flow through process. Qwest currently does not provide this data though it does have the data internally at Qwest. Qwest did provide the data at one time; however, in the report Qwest provided included those errors caused by Qwest’s required manual processes. Therefore, the report was of no benefit. Qwest should develop a report that will provide each CLEC information needed to prevent flow through eligible orders from dropping out of the flow through process. The report should contain only valid information. The report should not include that information that is a result of Qwest’s required manual and workaround processes. Expected Deliverable: Qwest will make available a flow through error report for each CLEC. Qwest will ensure the data is valid and does not include those flow through eligible errors that are a result of Qwest’s required manual processes. Short term the report should be provided on Friday for data the week before. (Mechanized Solution CR Created for long-term request: SCR063003-01) CONFIRMED IMPACTED INTERFACE: Web Interface CONFIRMED IMPACTED PRODUCT’S: All DISCUSSION: Bonnie Johnson (Eschelon) stated that she also wants orders to flow through and would like to prevent service orders from erring out. Shon Higer (Qwest) asked what type of data is being requested. Bonnie Johnson (Eschelon) stated that she has a copy of a spreadsheet of a report, for the GUI, and stated that she had received it from Kimberly Walden at Qwest. Bonnie sent copy of the spreadsheet to pesquib@qwest.com. Stephanie Prull (McLeod) stated that she had an EDI spreadsheet and sent it to Peggy (Esquibel Reed) as well. Bonnie Johnson (Eschelon) and Stephanie Prull (McLeod) stated would like on the report: PON, Request type, Reason for fallout in English description or code number, TN, LSR ID, Error code and description, contact name, and what to look at i.e. LCC. Stephanie Prull (McLeod) stated that the GUI report did contain different data than the report for EDI. Shon Higer (Qwest) asked if the EDI report needed to be separate from the GUI report. Bonnie Johnson (Eschelon) and Stephanie Prull (McLeod) stated yes. There were no additional questions or comments. ACTION PLAN: This CR to be presented at the August Systems CMP Meeting. The call was ended.


CenturyLink Response

Draft Response

August 13, 2003

SCR063003-01MN Flow through report made available to each CLEC in a timely manner with regular frequency (short term).

Based on information received during the Clarification Call (held July 9, 2003) and additional research, this CR will be crossed-over to Product/Process at the August CMP Meetings. There is no system coding to be performed for this effort.

Sincerely, Qwest


Open Product/Process CR PC112503-2 Detail

 
Title: Adjustment Recognition
CR Number Current Status
Date
Area Impacted Products Impacted

PC112503-2 Crossover
7/27/2009
Billing
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Maynard, Elaine
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest adjustments appear with only the date that Qwest issued the adjustment, a description such as “credit adjustment” and the amount. When Eschelon submits a dispute, Qwest requires the bill date of the disputed amount, the USOC and/or the description of the disputed amount, the TN or CKT ID of the disputed amount and the amount in dispute. Qwest should return the same information (we supply) on its adjustments. Without the bill date, TN or CKT ID and USOC it is extremely time consuming and sometimes impossible to determine what Qwest is adjusting. Many times Eschelon has to contact Qwest for the needed information. Sometimes even Qwest can not determine what the adjustment was for. Eschelon requests that Qwest return the same information Eschelon supplies on its disputes i.e. the bill date, the USOC (or description, if a USOC is not applicable) and the TN or CKT ID on all adjusted amounts that appear on any of Qwest’s bills including the BillMate Adjustment file.

Expected Deliverables - Qwest will include all the information Eschelon supplies on a dispute i.e. the bill date, TN or CKT ID and USOC (or description) on all adjusted amounts that appear on any of Qwest’s bills including the BillMate Adjustment file.


Status History

11/25/03 - CR Submitted

11/26/03 - CR Acknowledged

12/09/03 - Held Clarification Meeting

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

12/17/03 December CMP Meeting Kathy Stichter with Eschelon presented this CR. Kathy said that she submitted the CR because of problems figuring out adjustments on bills. Liz Balvin with MCI said MCI supports this CR and that they are unable to determine if adjustments are PAP payments or the result of a dispute. Kit Thomte with Qwest said we would like to cross over this CR to Systems because of billing system implications. Kathy Stichter agreed and this CR will be moved to Presented status and crossed over to Systems.

CLEC Change Request Clarification Meeting

2:00 p.m. (MDT) / Tuesday December 9, 2003

1-877-572-8687 3393947# PC112503-2 Adjustment Recognition

Name/Company:

Kathy Stitcher, Eschelon John Gallegos, Qwest Brenda Kerr, Qwest Elaine Maynard, Qwest Peggy Esquibel-Reed, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Qwest welcomed all attendees to the meeting.

Review Requested (Description of) Change Linda Sanchez-Steinke with Qwest read the description of change from the submitted change request; Currently Qwest adjustments appear with only the date that Qwest issued the adjustment, a description such as “credit adjustment” and the amount. When Eschelon submits a dispute, Qwest requires the bill date of the disputed amount, the USOC and/or the description of the disputed amount, the TN or CKT ID of the disputed amount and the amount in dispute. Qwest should return the same information (we supply) on its adjustments. Without the bill date, TN or CKT ID and USOC it is extremely time consuming and sometimes impossible to determine what Qwest is adjusting. Many times Eschelon has to contact Qwest for the needed information. Sometimes even Qwest can not determine what the adjustment was for. Eschelon requests that Qwest return the same information Eschelon supplies on its disputes i.e. the bill date, the USOC (or description, if a USOC is not applicable) and the TN or CKT ID on all adjusted amounts that appear on any of Qwest’s bills including the BillMate Adjustment file

Kathy Stitcher said that the reason the description of the disputed amount should be included is because toll usage types charges have no USOC associated with them. ; for instance toll usage type charges have no USOC associated with them. The last statement in the CR is mainly in connection with BillMate. The adjustment file should appear on all adjustments for bills. With maintenance and repair, TIC is a big problem and the billing reps lump a bunch of adjustments together rather than give the information item by item.

Elaine Maynard clarified that Eschelon is looking for the bill adjustments item by item rather than in a lump adjustment. Kathy Stitcher said that she usually knows what the adjustment will be ahead of time, however, when she looks at the bill it doesn’t match up. Kathy also said that she wasn’t sure if the CR should be Product & Process or Systems.

Brenda Kerr asked if the request is for all regions and states. Kathy responded yes.

Confirm Areas & Products Impacted Billing

Confirm Right Personnel Involved Correct Qwest personnel were involved in the clarification meeting

Identify/Confirm CLEC’s Expectation Qwest will include all the information Eschelon supplies on a dispute i.e. the bill date, TN or CKT ID and USOC (or description) on all adjusted amounts that appear on any of Qwest’s bills including the BillMate Adjustment file.

Identify any Dependent Systems Change Requests No dependent Systems Change Requests

Establish Action Plan (Resolution Time Frame) Eschelon will present this CR at the December meeting. Qwest will provide a response in January.


Open Product/Process CR PC102303-1 Detail

 
Title: 10,000 lines billed on Summary BANs before opening a new Summary BAN.
CR Number Current Status
Date
Area Impacted Products Impacted

PC102303-1 Completed
5/19/2004
Resale, Unbundled Loop, UNE Loop, UNE-p, EEL (UNE-C)
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Kriebel, Sue
Director:
CR PM: Andreen, Doug

Description Of Change

Currently, Qwest caps the number of lines billed on a Summary BAN at 2,500. Then it will close the existing BAN and open a new BAN. Eschelon processes each BAN separately for reconciliation, dispute and payment. For each Summary BAN Eschelon completes several tasks. Each new Summary BAN means we must duplicate these tasks, which is extremely time consuming. Eschelon asks Qwest to allow 10,000 lines per Summary BAN. Also Qwest needs to provide more than 30 days notice before opening a new Summary BAN.

Expected deliverables. Qwest will add the maximum of 10,000 lines to each of our summary BANs before opening new ones.


Status History

10/23/03 CR Recieved

10/24/03 CR Acknowledge

11/03/03 Held Clarification Call

11/10/03 Minutes sent

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status changed to presented

12/10/03 - Draft response issued

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Evaluation

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Development

2/2/04 - Qwest initiated notice PROS.02.02.04.F.01294.CRIS_V24

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/3/03 - Qwest initiated notice PROS.03.03.04.F.01425.FNL_CRIS_V24

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to Test

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

5/19/04 CMP Meeting May Meeting Doug Andreen, Qwest provided status for Sue Kriebel. Doug reported that Sue had checked with both IT and the Service Delivery Centers to see if there was a way the centers could manually monitor the number of sub-accounts by CLEC and the volume of order activity for a given CLEC. Sue’s findings are if the Centers change their process to monitor by CLEC based on level of order activity it would increase the time spent monitoring this process. Qwest does not have the additional resources needed to monitor this on a CLEC by CLEC basis vs. the current 6,000 sub-account limit used for reporting/monitoring. Also, when looking at future mechanized solutions, in order to incorporate a CLEC specific threshold would require a database that would house each CLEC’s limit. This would increase the Level of Effort for mechanization if and when this work was to proceed. Therefore, at this time we cannot commit to raising the limit from 6,000 on an individual CLEC basis. Liz Balvin, MCI clarified that the 6,000 limit was 6,000 plus in flight orders. Bonnie Johnson, Eschelon said the reality is that higher volume CLECs will exhaust at around 10,000 where lower volume CLECs will exhaust at a lower number. Doug said yes. Liz asked to clarify the mechanization of this effort. Doug said that it was only meant to point out that if and when there was mechanization of this effort that tracking by individual CLEC would necessitate a higher level of effort to implement. Doug asked if the CR could be closed. Bonnie pointed out that the original CR asked for a 10,000 limit and that isn’t where Eschelon will end up. The CR will be moved to Completed status.

4/21/04 April CMP Meeting Sue Kriebel, Qwest stated all the work is complete on this CR and asked if it could be closed. Liz Blavin, MCI pointed out that the limit is actually 6,000 instead of 10,000 as stated in the title. Bonnie Johnson, Eschelon asked if there was a way to determine each CLEC volume separately and set different limits for each. She stated the object would be to set the volume based on the average number of orders a CLEC has in process (or in flight) at any one time. For instance some CLECs would never have 4,000 orders in flight and therefore could be given a higher limit than 6,000. Sue said it is now a manual monitoring process which she hopes at some point to mechanize. Bonnie asked if mechanization would be to count the order when it comes in. Sue said yes. Liz verified that the concept was to have the in flight orders counted in determining the ceiling and still not exceed 10,000. Sue said she would look into this. This CR will stay in CLEC Test.

-- 03/17/04 March CMP Meeting Doug Andreen, Qwest reported that the PCAT moving the limit from 2,000 to 6,000 lines will be effective tomorrow 3/18. This CR will be moved to CLEC Test status.

-- 2/18/04 CMP Meeting Sue Kriebel, Qwest said that an MCC notice has been issued to the centers reinforcing the minimum three day notice that Qwest must give the CLECs before opening a new BAN. Further, the PCAT covering the 6,000 limit per BAN will be published 3/18. This CR will stay in Development.

1/21/04 January CMP Meeting Sue Kriebel, Qwest answered three action items from the last meeting. First she explained that the 6,000 cap on BANs refers to sub-accounts and that there can be many lines under a sub-account. Second, there is only one active BAN at a time and that re-activating an account is a manual process. If a BAN is re-activated there will still be only one active BAN. Lastly, regarding the minimal time to notify a CLEC of a new BAN, she will send out notification to reinforce this standard. Sue also said PCAT changes would be forthcoming on the new 6,000 limit. Carla Pardee, AT&T said that she thought CLECs would be notified when they are getting close to exhausting a BAN. Sue agreed but said this is the notification of a new BAN being activated. Connie Winston, Qwest added that the BAN takes into account the RSID, product and state. The CR will move to Development status.

- 12/17/03 December CMP Meeting Sue Kriebel, Qwest reviewed the draft response increasing the lines per BAN to 6,000 from 2,000 without an increase to the current notification interval to open a new BAN. Liz Balvin, MCI clarified the existing process of when a BAN is close to the maximum that Qwest send a email to the CLEC with three days notice to open a new BAN. Carla Pardee, AT&T stated they have been getting one day notice. She further stated that 6,000 is better than 2,000 and she would accept the response but that it is really not acceptable when dealing with large volumes. Sue said she would clarify the process to ensure three day notice. Sue explained that if we use the 6,000 limit by the time the BAN is closed we could have and have had 2,000 to 3,000 additions processed. Carla noted that AT&T has accounts that have exceeded the limit but have not been noticed. Sue explained that it depends on the type of product for instance UNE-L carries less processing risk than UNE-P because usage is on the UNE-P which makes it more complex. Kathy Stichter of Eschelon said she was ok with the 6,000 limit and that the time span was not an issue at Eschelon. Kathy asked what the difference was between a line and a sub-account? Sue took this as an action item. Later in the meeting Kathy asked if BANs previously closed that had less than 6000 lines could be re-opened. Sue Kriebel said she would investigate. The CR status was moved to Evaluation.

- 11/19/03 Nov. CMP Meeting Kathy Stichter - Eschelon presented this CR to increase the lines billed on Summary BANs from 2,000 to 10,000. She stated that each time a new BAN is opened Eschelon reviews, reconciles and handles dispute resolutions separately. Carla Pardee AT&T added that AT&T supports this CR. Liz Balvin - MCI said that MCI had submitted a CR sometime ago for this and it was denied. Liz stated she would like to see no limit on BANs, but that 10,000 is better than 2,000. Also, she has just submitted a similar CR requesting multiple BANs per product per state. Doug said the same SMEs will be looking at both CRs. Kathy stated she has 20 BANs in Minnesota for Resale alone and is trying to consolidate these. Carla added that the 2,000 restriction on BANs seems to be just recently enforced by Qwest. She has several that are over 2,000 lines and it never seemed to be a problem. Kathy agreed that it was not being enforced before. This CR will move to Presented status.

--

Clarification Meeting: 3:00 p.m. (MDT) / Monday November 3, 2003

1-877-521-8688 1456160# PC102303-1 10,000 lines billed on Summary BANs before opening a new Summary BAN.

Attendees: Name/Company: Carla Pardee, AT&T Kathy Stichter, Eschelon Doug Andreen, Qwest Kerri Waldner, Qwest Brenda Kerr, Qwest Cindy Macy, Qwest Wendy Thurnau, Qwest Paul Johnson, Qwest Anne Robberson, Qwest Lynn Loftus, Qwest

Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested Description of Change: Doug read the CR description: Currently, Qwest caps the number of lines billed on a Summary BAN at 2,500. Then it will close the existing BAN and open a new BAN. Eschelon processes each BAN separately for reconciliation, dispute and payment. For each Summary BAN Eschelon completes several tasks. Each new Summary BAN means we must duplicate these tasks, which is extremely time consuming. Eschelon asks Qwest to allow 10,000 lines per Summary BAN. Also Qwest needs to provide more than 30 days notice before opening a new Summary BAN.

Kathy Stichter - Eschelon said that entire process is extremely time consuming on the Eschelon side each time a new BAN is utilized.

Carla Pardee – AT&T added that AT&T had been informed on short notice that they would have to close the existing BAN and begin using a new BAN.

Anne Robberson - Qwest said she believed that the limit on BANs was a system restriction. She also stated that the limit is 2000 lines per BAN.

Kathy and Carla both stated that they did not believe this to be true since they both have existing BANs with many more lines than 2,500.

Kathy said that the number of BANs that are opened directly multiplies the process.

Carla stated she was notified a week ago by Qwest’s billing department that they were exhausting BAN numbers.

Kathy said she has 69 BANs for CRIS alone. She said ideally she would like to see one BAN per state and that she would like to see 45 if not 60 days notice given before opening new BANs.

Kerri Waldner - Qwest asked Kathy if she had any trends on how fast BANs were being exhausted. Kathy responded that she did not.

Kathy added that a third issue (along with 1. The 2000 limit and 2. Insufficient advanced notification) is that it seems Qwest is just starting to enforce the line limit on BANs

Confirm Areas & Products Impacted Resale, Unbundled Loop, UNE Loop, UNE-P, EEL (UNE-C)

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation Identified on initial CR: Allow 10,000 lines billed on Summary BANs before opening a new Summary BAN. Identified during call: Eschelon needs 45 to 60 days’ notice before opening a new summary BAN.

Identify any Dependent Systems Change Requests Eschelon would like the change applied to both CRIS and IABS.

Establish Action Plan (Resolution Time Frame) Kathy will present for Eschelon at the November CMP meeting.


CenturyLink Response

December 02, 2003

For Review by the CLEC Community and Discussion at the December 17, 2003 CMP Meeting

Kathy Stichter Senior Invoice Validation Analyst Eschelon Telecom

SUBJECT: Qwest Change Request Response - CR # PC102303-1 10,000 Lines billed on Summary BANs before opening a new Summary BAN

After reviewing CR # PC102303-1, Qwest has determined that it will raise the current standard of 2,000 Sub Accounts per Summary BAN to 6,000 Sub Accounts per Summary BAN. This is a business decision that was made that is sensitive to the request from the CLEC community to increase the size of the Sub Accounts per Summary BAN, but is also sensitive to the Qwest Billing SDC’s who have to manage the Summary Accounts.

As to the second issue of requesting a 30 day notification prior to closing a Summary BAN cannot be accommodated. Once the Summary BAN has reached the 6,000 Sub Account limit, it will be closed and a new Summary BAN issued as is currently done. To continue to leave the Summary Account open for an additional 30 days to notify the CLEC after it has reached the Sub Account limit would continue to increase the number of Sub Accounts posting to the Summary BAN to an unacceptable level before it could be closed. Sincerely, Carl Sear Sr. Process Analyst Qwest Communications


Open Product/Process CR PC102803-1 Detail

 
Title: Improve Search Functionality of the Qwest Wholesale Website to minimize selections
CR Number Current Status
Date
Area Impacted Products Impacted

PC102803-1 Completed
8/3/2012
Qwest Wholesale Website
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Blackmun, Jarby
Director:
CR PM: Andreen, Doug

Description Of Change

Eschelon asks Qwest to improve the efficiency of the Qwest Wholesale Website search function. The CLEC community depends on the information Qwest provides on the Qwest Wholesale Website to obtain information on Qwest’s process, products, SGATs and OSS. The current search functionality of the Qwest Wholesale Website provides too many results and impedes a CLEC’s ability to quickly obtain important information. For example, on 10-14-03 Qwest sent a CMP notice regarding the grandparenting of Single Service in AZ. To fully understand the impact of this product retirement, Eschelon wanted to review the product information for Single Service on the Qwest Wholesale Website. Using the search function on the Qwest Wholesale Website, we received 12,300 results. A handful of these results did not pertain to wholesale but were Qwest retail information and Qwest corporate information. It is a burden to expect the CLECs to search through 12,300 results to find the information pertinent to a product. The above is one example of the struggles a CLEC faces when attempting to find specific information on the Qwest Wholesale Website. Improving the search functionality and CMP notice process is critical to a CLECs ability to find the information necessary for a CLEC to do business with Qwest. Qwest will also benefit if CLECs have better access to information on the Qwest Wholesale Website. Easy access to information may decrease the number of calls to the ISC, Qwest Service managers, WSHD and the Qwest CMP team.

Expected Deliverable:

1. Allow a CLEC an option to search the Qwest Wholesale Website only.

2. Allow a CLEC the option to search each subsection (Product & Process, Resources, OSS, Network, Training, Notices and Forums, Customer Service) on the Qwest Wholesale Website.

3. Qwest will start including a link to the Product on the Qwest Website on all CMP notifications that are grandparenting products.


Status History

10/28/03 - CR Submitted

10/29/03 - CR Acknowledged

11/05/03 Held Clarification Call

11/11/03 Meeting minutes sent

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status changed to presented

12/10/03 - Draft response issued

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Evaluation

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status will remain in Evaluation

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

08/15/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that in the July meeting, CenturyLink had asked the owner of each Deferred CR to determine if it should remain in Deferred status, is it should be Withdrawn, or whether it should be re- evaluated. Mark then reviewed the status of each CR as listed on the Attachment:

PC102803-1 Improve Search Functionality of the Qwest Wholesale Website to minimize selections - Status changed to Completed by Kim Isaacs, Integra: Request 1 and Request 3 have been completed. I continue to believe that search functionality of the website can be improved. CenturyLink can close this CR and note that Request 2 was denied and was not completed.

8/18/04 CMP Meeting Jarby Blackmun said in April or May she reported about Phase 1 updates which consisted of technical changes to how the search engine functions. There has been one additional update since then involving the ability to group by location. Since that time, Phase 2 has been placed on indefinite hold. Bonnie questioned moving the CR to Deferred Status and questioned if there was a notice for the last of the Phase 1 changes. Jarby said no, that it was a non-impacting change. Bonnie asked about instructions on the web site, saying once she gets to Wholesale she wants to stay within the Wholesale parameters. Jarby said entering wholesale as the first word of any search will keep the search inside Wholesale. The CR will move to Deferred Status.

7/21/04 CMP July Meeting Doug Andreen, Qwest reported that this is still in the requirements gathering phase and there is nothing new to report. Jarby Blackmun, Qwest hopes to have an update next month. The CR will remain in Evaluation.

-- 6/16/04 June CMP meeting minutes Doug Andreen, Qwest said there is no new information this month and that IT is currently in the gathering and evaluation stage of search requirements. The CR will remain in Evaluation.

5/19/04 CMP May Meeting Doug Andreen, Qwest said that IT is currently in the gathering and evaluation stage of search requirements. There is no clear timeline available as yet. The CR will remain in Evaluation.

-- 4/21/04 April CMP Meeting Jarby Blackmun, Qwest offered some new information on this CR. The general status is that Qwest has strengthened its infrastructure using spidering, fail-over growth (similar to redundancy), spell check capabilities, and meta data improvements. Current tasks include requirements gathering and technical improvements. Jarby said she will work with project leads to evaluate technical capabilities to achieve desired search category needs addressed in the CR. There is no timetable on the effort. Bonnie Johnson, Eschelon thought that the CR was going to be deferred. Kit Thomte, Qwest said that was considered since there didn’t seem to be much movement but now that there is movement we should leave in evaluation. The CR will remain in Evaluation.

03/17/04 Kit Thomte, Qwest noted that there may not be movement on this CR for some time. She suggested that the CR be moved to deferred status or deny status. Bonnie Johnson, Eschelon said she would rather see a deny than deferred status. The CR will be denied and an action item opened to track any movement on this issue. The CR will remain in Evaluation status while the denial is being formulated.

-- 2/18/04 CMP Meeting Doug Andreen, Qwest stated there is no new information this month. The CR will remain in Evaluation status.

- 1/21/04 CMP Meeting Doug Andreen, Qwest stated there is no new information this month. The CR will remain in Evaluation status.

-- 12/17/03 December CMP Meeting Jarby Blackmun, Qwest reviewed the draft response. Kathy Stichter of Eschelon said she had looked over the response and tried the recommendations and still often was getting over 1,000 responses. Jarby agreed that if the type is Wholesale with other key words the system will look for any of the words making our best response to put more information in the notifications. Bonnie Johnson, Eschelon asked who would head up the effort to make sure the notification has current links. Jarby advised that this would be the Product Managers' and Process Managers via the documentation process. These managers have been advised. Bonnie also questioned what status this CR would be in. It was agreed to move the status to Evaluation.

11/19/03 Nov CMP Meeting Kim Isaacs - Eschelon, presented the CR to improve the search capabilities of the Wholesale web site to be able to search only Wholesale, and to be able to search each category separately. She said Eschelon is encouraging the use of the web site and that many responses to searches is discouraging use. Bonnie Johnson - Eschelon, added that on a recent search for a grandfathered product, 12,300 results were returned. She further said that on the Clarification call Jarby Blackmun - Qwest, had indicated that changes to this site was in the works on a global level and that in the interim Jarby is investigating if more information can be added to the grandfather notices. Jarby added that the Wholesale search engine is the same engine driving the entire Qwest.com website. She also added that the capabilities described in the CR would be input to the Qwest effort to revamp Qwest.com. This CR will move to Presented status. Kim Issacs/Eschelon added that Eschelon asked Qwest to add links to notices to locate information contained in either the PCATS or Retail information. Qwest said it would work with the notice group to accomplish.

- Clarification Meeting

11:30 p.m. (MDT) / Wednesday November 5, 2003

1-877-521-8688 1456160# PC102803-1 Improve Search Functionality of the Qwest Wholesale Website to minimize selections

Attendees: Name/Company: Kim Isaacs, Eschelon Bonnie Johnson, Eschelon Jarby Blackmun, Qwest Doug Andreen, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Doug read the description of the CR as follows: Eschelon asks Qwest to improve the efficiency of the Qwest Wholesale Website search function. The CLEC community depends on the information Qwest provides on the Qwest Wholesale Website to obtain information on Qwest’s process, products, SGATs and OSS. The current search functionality of the Qwest Wholesale Website provides too many results and impedes a CLEC’s ability to quickly obtain important information. For example, on 10-14-03 Qwest sent a CMP notice regarding the grandparenting of Single Service in AZ. To fully understand the impact of this product retirement, Eschelon wanted to review the product information for Single Service on the Qwest Wholesale Website. Using the search function on the Qwest Wholesale Website, we received 12,300 results. A handful of these results did not pertain to wholesale but were Qwest retail information and Qwest corporate information. It is a burden to expect the CLECs to search through 12,300 results to find the information pertinent to a product. The above is one example of the struggles a CLEC faces when attempting to find specific information on the Qwest Wholesale Website. Improving the search functionality and CMP notice process is critical to a CLECs ability to find the information necessary for a CLEC to do business with Qwest. Qwest will also benefit if CLECs have better access to information on the Qwest Wholesale Website. Easy access to information may decrease the number of calls to the ISC, Qwest Service managers, WSHD and the Qwest CMP team.

Bonnie and Kim had nothing to add to the description or expected deliverables.

Jarby stated that the request was clear to her.

Kim mentioned that Eschelon is trying to encourage use of the website in her company and that the current search abilities are a hindrance.

Jarby said that Qwest.com has one search engine that covers the entire website and that there is recognition with Qwest as to the need to improve the search engine.

Bonnie stated that when the redesign architecture is done the needs of Wholesale and the CLECs need to be included.

Jarby said that those concerns were and will be included and that she believes this could be on the books for next year.

Doug explained the next steps including presenting the CR at the November CMP meeting and then having the response during the December cycle.

Kim thought that in the interim if there could be a link established to the grandparented USOCS or a better description given in the notifications that this would help.

Jarby said she would check with Susan Lorence and Mark Coyne on what could be done with the grandparenting issue. Jarby said she would also explore ways to do better searches on the existing engine since they are all a bit different this could make a good degree of difference.

Kim and Bonnie agreed this could help.

Confirm Areas & Products Impacted Qwest Wholesale Website

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation These expectations were confirmed. 1. Allow a CLEC an option to search the Qwest Wholesale Website only. 2. Allow a CLEC the option to search each subsection (Product & Process, Resources, OSS, Network, Training, Notices and Forums, Customer Service) on the Qwest Wholesale Website. 3. Qwest will start including a link to the Product on the Qwest Website on all CMP notifications that are grandparenting products.

Identify any Dependent Systems Change Requests None identified.

Establish Action Plan (Resolution Time Frame) Kim will present the CR at the November 19 CMP Meeting. Response will be made during the December cycle.


CenturyLink Response

December 3, 2003

For Review by the CLEC Community and Discussion at the December 17, 2003 CMP Meeting

Kim Isaacs ILEC Relations Process Analyst Eschelon Telecom

SUBJECT: Qwest Change Request Response - CR # PC102803-1 Improve Search Functionality of the Qwest Wholesale Website to minimize selections

This letter is in response to Eschelon Communications Change Request CR # PC102803-1. This CR requests that Qwest provide improved search capabilities on the wholesale public web site and that Qwest include a link to the product on the Qwest Website on all CMP notifications regarding grandparented products. The request also include the need to refine searches to subsections within the Wholesale site, e.g. Product & Process, Resources, OSS, Network, Training, Notices and Forums, Customer Service.

The current web search engine covers all content associated with the qwest.com site architecture. This includes all html sites and associated documents found within the qwest.com/wholesale. To narrow a search to content found only within the wholesale site architecture, a user must enter the word wholesale in the search prompt box and any other specific word or phrase description. When the search returns its results, only look at results that contain the word wholesale and the other words or phrases, e.g. wholesale, poles, ducts, right of way. As an example, if a result shows the phrase poles, but does not show wholesale, the search pulled results from outside the wholesale architecture.

To further narrow a search, click on the advanced link (next to the search button), which should aid in refining a search. Choosing words or phrases that are specific to an inquiry can narrow a search. Example: searching for poles, ducts and right away will narrow the search and provide fewer responses than poles.

Browsers (Explorer, Netscape, AOL) generally contain an option to search within an HTML web page. As an example, in Explorer, look under the Edit Menu and select the Find on this Page tool. This will allow a user to search only within that page.

Qwest will include links to the appropriate product PCAT or will include the product manager contact information.

Sincerely,

Jarby Blackmun Senior Manager Wholesale Communications Initiatives


Open Product/Process CR PC101001-1 Detail

 
Title: Process for CLEC to get end user service corrected without an additional LSR when Qwest typed the original order incorrectly.
CR Number Current Status
Date
Area Impacted Products Impacted

PC101001-1 Completed
3/20/2002
Repair Centrex, Resale, Unbundled Loop, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: McMahon, Cheryl
Director:
CR PM:

Description Of Change

Currently when Eschelon calls Qwest repair, if the customer service record (CSR) does not match what Eschelon ordered, Qwest repair refuses to open a ticket and instead tells Eschelon to issue an order to correct the problem. Eschelon will investigate and determine that what the LSR asked for is different than what Qwest typed. If an end user customer needs to wait for Eschelon to send through a LSR and Qwest to issue an order the end user would be without the service for several days. This is a hardship for the end user customer. Eschelon asks Qwest to develop, document, distribute and train an adhered to process for Eschelon repair to call Qwest repair and have the end user customer service fixed without Eschelon issuing another LSR. Eschelon asks that the process include Qwest repair transferring Eschelon to the appropriate person within Qwest who will issue an order with the same day DD to fix the problem that was caused by Qwest typing the original order incorrectly.


Status History

10/08/01 - CR Received from Kathy Stichter or Eschelon

10/10/01 - CR logged and status changed to Submitted

10/10/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

10/19/01 - Held Clarification Meeting with Eschelon

11/14/01 - CMP Meeting - CR was clarified with the CLECs. Qwest to prepare its draft response.

12/05/01 - Draft response dated 12/04/01 posted to CMP database and issued to the originating CLEC. Status changed to Presented.

12/12/01 - CMP Meeting: Qwest response presented to CLECs, agreement obtained to change status to CLEC Test

12/28/01 - Formal response dated 12/4/01 issued to CLECs

01/16/02 - January CMP meeting. Eschelon experienced pushback from a center on this process (12/19/01). CLECs also asked where this process is documented. Qwest will open an action item (Action # 1). CR to remain in CLEC Test Status.

01/24/02 - E-mail from Eschelon citing an out-of-process example - Action # 2 opened

02/08/02 - Resolution to Action # 2 posted to CMP database

02/20/02 - February CMP meeting: Action # 2 closed. Global Action Item opened to address Qwest internal communication of processes developed in CMP. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/27/02 - Revised response to Action # 1 posted to CMP database

03/20/02 - CMP Meeting - It was agreed that the CR could be closed, CR status changed to Completed. Action #1 closed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

01/24/02 E-mail from Eschelon citing an out-of-process example Subject: FW: PC101001-1 Draft Response Date: Thu, 24 Jan 2002 09:27:46 -0600 From: "Stichter, Kathleen L." To: tmead@qwest.com CC: "Johnson, Bonnie J." Todd, Please pass this example onto the correct people who can make sure that the tier 0 office in Sierra Vista is covered. I am currently and have been on a call for the last 20+ minutes with one of our repair coordinators and Qwest. Our customer, 602-252-4650, has a Resale MEL line which was installed on LSR 3859136. The CFN is a local number but Qwest issued the order using a 1 before the 10 digit TN. When callers dial 602-252-4650 they get intercept stating they do not have to dial a 1 before the number. They, of course, are not dialing a 1, the central office switch is. Our repair coordinator called Interconnect 888-796-9087 and reached the tier 0, William, who stated that he could not take a ticket from a repair technician. He could only take a ticket from Eschelon sales or provisioning. William got another Qwest employee on the line, Diane, who also had the same understanding. Our repair coordinator added me on and Diane agreed to take the ticket and warm transfer us to the Tier 1 in the Minneapolis Center. Julie in Minneapolis took our information and is having an order issued to correct the original incorrect order. Julie did know that our repair coordinators can call into Interconnect. Our repair coordinators do not have the time to try and convince Qwest to take our issues. I do not have the time to sit on an escalation along with another employee, when Qwest, Sierra Vista is out of process. Please let me know when and how the office in Sierra Vista is covered on this process. Thanks Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

Friday, 10/19/01, 10:00am MST Alignment/Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PCCR101001-1 Stichter, Kathleen, klstichter@eschelon.com, Eschelon Telecom Frederickson, Chris, N/A , Eschelon Telecom Danielsen, Ann, aldanie@qwest.com, Qwest McMahon, Cheryl, cmmcmah@qwest.com, Qwest Belt, Michael, mbelt@qwest.com, Qwest

Introduction of Attendees Kathleen, Ann, Cheryl, Chris & Michael Review Requested (Description of) Change Process for CLEC to get end user service corrected without an additional LSR when Qwest typed the original order incorrectly. Reviewed and understood Confirm Areas & Products Impacted Area: Repair and Interconnect Service Center

Confirm Right Personnel Involved Ann Danielsen indicated right people were involved might need Mark Coyne approval for the LSR portion of the CR. ((Michael, there needs to be involvement from Wholesale support of the ISC/CSIE) Identify/Confirm CLEC’s Expectation Yes we fully understand expectations of the CR. Mike Belt to Coordinate with Mark Coyne regarding LSR Issues.

Identify any Dependent Systems Change Requests N/A

Establish Action Plan (Resolution Time Frame) Process in place via web, Ann to develop draft Qwest response for the Network Repair Portion of the CR. (again, the response needs to have ownership from the ISC/CSIE Wholesale group)M. Belt to forward draft response template with sample response for processing.


CenturyLink Response

December 4, 2001

Kathleen Stichter ILEC Relations Manager Eschelon

CC: Mark Coyne Ann Danielsen

This letter is in response to your CLEC Change Request Form, number PC 101001-1 dated 10/10/01 – Process for CLEC to get end user service corrected without an additional LSR when Qwest typed the original order incorrectly.

Request: Currently when Eschelon calls Qwest repair, if the customer service record (CSR) does not match what Eschelon ordered, Qwest repair refuses to open a ticket and instead tells Eschelon to issue an order to correct the problem. Eschelon will investigate and determine that what the LSR asked for is different than what Qwest typed. If an end user customer needs to wait for Eschelon to send through a LSR and Qwest to issue an order the end user would be without the service for several days. This is a hardship for the end user customer. Eschelon asks Qwest to develop, document, distribute and train an adhered to process for Eschelon repair to call Qwest repair and have the end user customer service fixed without Eschelon issuing another LSR. Eschelon asks that the process include Qwest repair transferring Eschelon to the appropriate person within Qwest who will issue an order with the same day DD to fix the problem that was caused by Qwest typing the original order incorrectly.

Qwest Response: Qwest Repair Process When a CLEC calls the Repair Center to report trouble on their end users service, the Repair Center will issue a repair ticket and forward the ticket to the appropriate screening group. If the screening group determines the problem needs to be resolved with a service order, the screener will refer the problem to the Interconnect Service Center (ISC). The ISC will initiate the subsequent order resulting from a Qwest error on the LSR or will contact the CLEC on errors resulting from a CLEC error on the LSR.

Interconnect Service Center Process CLEC reports of service problems or outages within 72 hours of order activity should be directed to the Interconnect Service Center (ISC) at 1-888-796-9087. The ISC agent will ascertain all pertinent information, create a database trouble ticket and attempt to warm transfer the CLEC to a Customer Service Inquiry and Education Service Delivery Consultant (CSIE SDC). If a CSIE SDC cannot be reached directly, the ISC agent will refer the trouble ticket to the CSIE SDC and advise the CLEC that they will receive a call back within 2 hours. The CSIE SDC will investigate the trouble ticket by reviewing the LSR and associated service order(s).

If a discrepancy is found on a completed service order (ordered product and/or services were not delivered), the CSIE SDC will issue a new service order to correct the problem. Every effort will be made to provide a same day Due Date for the new order. If no discrepancies are found on the completed service order, the CSIE SDC will either warm transfer the CLEC (if the CLEC is on the line) or refer the problem on behalf of the CLEC to the appropriate QWEST repair center. Resale POTS or PAL service trouble reports are handled by the Repair Call Handling Center (RCHC) at 1-800-573-1311 for residential service or 1-800-954-1211 for business service. Trouble reports for all other products are handled by the Account Maintenance Support Center (AMSC) at 1-800-223-7881.

Sincerely,

Cheryl McMahon Senior Process Analyst

Monica Manning IMA Process Specialist


Open Product/Process CR PC091901-1 Detail

 
Title: Qwest to form a Quality Team
CR Number Current Status
Date
Area Impacted Products Impacted

PC091901-1 Completed
6/19/2002
Pre-Ordering, Ordering Centrex, LNP, Resale
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

Qwest to form Quality Team to review and improve the end to end processes for:

CLEC on-net to resale reuse of facilities

CLEC on-net to resale new facilities

Resale CLEC to resale CLEC (same CLEC) move including port within

Change orders requesting a TN change reusing TNs from old location and changing them at the new location requiring port within.

The team to include Qwest SMEs from each of its’ functional areas:

Order distribution center

Service order processing

Assignments

Switch technicians (RCMAC)

Network dispatch in

Network dispatch out

LNP center

Eschelon has offered to serve as the prototype for this Quality Team which will benefit all CLECs. It is yet to be determined how these orders will be identified. Eschelon’s expectation is that the Quality Team at Qwest will watch the flow of each order and determine the process gaps that are causing CLEC customers a significant amount of service disruption and down time. In addition, the Quality Team should remain in place until process improvements are made and proven effective.


Status History

09/17/01 - CR received by Kathy Stichter of Eschelon

09/19/01 - CR status changed to Submitted

09/21/01 - Updated CR sent to Kathy

09/24/01 - Scheduled clarification meeting with Eschelon

09/28/01 - Notified CLEC of cancellation of meeting

10/05/01 - Judy Schultz to coordinate with Lynn Powers to establish Qwest position

10/17/01 - CMP Meeting: CLEC community & Qwest agreed to enter Quality Team meeting minutes into CR database. Meetings are generally conducted on a 1 to 2 week frequency. "Current Status" changed to Clarification.

11/14/01 - CMP Meeting this Process Change was reviewed as a separate part of the agends. Toni Dubuque reviewed the primary topics that are being addressed by the Quality team. Toni indicated that the Quality team will probably remain active through the end of 2001. Eschelon expressed their appreciation for what has been accomplished by this team.

12/12/01 - CMP Meeting - Toni Dubuque, Qwest provided an update for the quality team. She indicated that overall progress has been made with various CR related issues, and that the team will continue into next year. A situation was identified, "Change of local service provider and customer moves," that requires process modification in order to prevent future customer outages. The team is working the process modifications & flow sheets; and will conduct a validation exercise with Eschelon in the near future. "CR Status" remains as "Presented."

01/16/02 - CMP Meeting - Toni dubuque, Qwest indicated that Quality Team is working primary issues identified in original CR "Description of Change." Most issues have been addressed and balance should be completed within the next 30 to 60 days. CLEC community agreed to change CR Status to "Development."

02/20/02 - Qwest provided a status update. CR status remains in "Development." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/20/02 - CMP Meeting - It was agreed that the CR would remain in Development. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

03/22/02 - Qaulity Team Meeting conducted with Eschelon.

04/17/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would remain in Development.

05/15/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would move into CLEC Test..

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status was changed to Completed.


Project Meetings

CMP Quality Meeting Minutes 3-22-02

Specifics: Purpose of Meeting: resolve Port In/Within order issues Meeting Dates: March 22,2002 Time: 1pm CST Meeting Chair: Toni Dubuque Next Meeting:Complete

Attendees: Toni Dubuque, Qwest Cust Svc Oprns Bonnie Johnson, Eschelon Joan Wells, Qwest Process Claudia Meredith-Trump, Qwest

Agenda: - Finalize flows - Finalize test process

- Port-in flows have been re-done on Power Point with specific language on process to be used in the 3 Port in scenarios and 8 Port within scenarios. These were reviewed by the team and are in an understandable format for training. - Training will be done by Qwest in the Mpls center CSIE team and documents shared with all other appropriate centers for review. - Joan will work with the product team to get specific scenarios updated in PCAT - Eschelon will do test order week of April 1st. Claudia will monitor flow and get specifics back to Bonnie for confirmation of order process.

The committee feels that they have completed the objective of improving the documented processes for unique situations involving Port In and Port within orders. This work will benefit all customers who order LNP. Order routing changes have eliminated the problems with moving orders from center to center within Qwest.

Purpose of Meeting: Resolve Port In/Within order issues Meeting Dates: January 23,002, Time: 1130am CST Call-in Bridge: 877-572-868, ID: 811-0227 Meeting Chair: Toni Dubuque Next Meeting:February 7,2002 3-4pm CST

Name/Presentation Toni Dubuque, Qwest Cust Svc Oprns/x/ Joan Wells, Qwest Process/x/ Bonnie Johnson, Eschelon/x/ Claudia Meredith-Trump, Qwest/x/ Chris Siewert,, Qwest Ctr Mgmt/x/ Barb Vigoren, Eschelon/ / Mary Madill, Qwest Ctr Mgr/ / Frank Lopez, Qwest Ctr Mgr/ /

Agenda: - Finalize flows - Finalize test process - Address Action Items - Determine next meeting

- Port-in flows are final and have been issued within Qwest; scenarios 1-3 are attached. - Port-within flows are work-in-progress to add all products - Test accounts have been set up and by 1-25 a test order will be submitted by Eschelon for monitoring and ensuring process for Scenario 3 is working; have already used process on live orders for Scenario 2. - During root cause process, we had identified a learning about procedures between RCMAC and Complex Translations (CT) that we wanted to investigate and tighten communications. On port-in C-orders, if the NPA-NXX of the end user has never been loaded into a DMS-10 or Ericsson Switch, Complex Translations must load before RCMAC does work. Communication is done by fax. We have added step in process for order writer to call CT to ensure load is complete prior to order flowing downstream. - Port-in coordination product is in detail design and pricing for both retail and wholesale. This will take care of end users who have special needs and cannot afford downtime. Joan is our representative and will keep us updated on progress. (CR open also) - Auto routing of port-in/within orders by MPI will be implemented 3-20-02. Good news – screening will be eliminated.

Action Items: Item/Assigned to/Status/Completion Date 1. Determine an interim process for cutting over end users who handle emergency call (doctors, hospitals) to eliminate inability to receive calls on due date (FDT 8am, work done anytime between 8-5pm)/Joan Wells/Same as #2/Work in progress 2. Communicate potential date of new coordination process/product for port in orders that will eliminate downtime (in definition stage)/Joan Wells/See above/Work in progress 3. Meet with Network process to investigate gaps in handling C action orders in complex translations/Joan/Chris/Completed / see notes above/1-23-02 Set up test accounts 612-302 and 612-721/Joan/Completed/1-23-02 Test Scenario 3/Joan/Bonnie// Finalize Port within flows/Joan/Should be done by 2-1/

Next meeting will be the last formal session. We will reconvene team to do live test when actual order is received by Eschelon.

CMP Quality Meeting Minutes 01-07-02

Specifics: Purpose of Meeting: resolve Port In/Within order issues Meeting Dates: December 18, 2001 Time: 2pm CST Call-in Bridge 877-572-868 811-0227 Meeting Chair: Toni Dubuque Next Meeting: January 9, 2002 @ 2pm CST

Attendees: Name Present Name Present Toni Dubuque, Qwest Cust Svc Oprns x Joan Wells, Qwest Process x Bonnie Johnson, Eschelon x Claudia Meredith-Trump, Qwest x Al Kiehn, Qwest Ctr Mgmt x Barb Vigoren, Eschelon x Mary Madill, Qwest Ctr Mgr Frank Lopez, Qwest Ctr Mgr

Agenda: - Review flows and clarify any questions - Set up process for live customer SPOC monitoring - Determine next meeting

Flows were presented by Joan Wells indicating the different scenarios regarding special circumstances for Port in, Port within orders.

- End user is with Q retail or current CLEC NSP/end user moving to new location requesting to move existing TN’s and change to a new reseller provider, new facilities/Q port in activity flow - Existing resale account, no service provider change to 2 current locations – original location with account history to be disconnected and TN’s moved to newest account locations where new TN’s exist that will be disconnected/Port within activity flow - Existing resale account port within/T &F dual service requested, number change at T location upon completion of F order activity flow - End user is with Q retail or current CLEC NSP/end user moving to new location already served by same reseller requesting Port, will be disconnecting existing TN’s and replacing with port in in TN’s, reuse existing facilities/Q port in activity flow

There were a number of questions and clarifications done on the flows. This used the majority of the time allotted for the meeting. Another meeting was set to regroup and finalize flows.

Quality Team - Qwest/Eschelon LNP Order Issues: Revision 5 Team Members: Sponsor - Toni Dubuque Q Team - Mark Coyne, Ray Burton, Mary Madill, Joan Wells, Russ Urvig E Team - Bonnie Johnson

Meetings: Sept 10, 2001 @ 10:30am CDT Sept 17, 2001 @ 2:00pm CDT (rev 2) Sept 26, 2001 @ 930am CDT (rev 3) Oct 5,2001 @ 930MDT/1030amCDT (rev 4) Oct 12, 2001 Oct 26, 2001 @ 230pmCDT (rev 5) NEXT MTG Nov 7, 2001 @ 900am CST Call-In Number: 877-847-3567 pc600-2974

ISSUE 1: Mis routing of orders causing missed commitments - CLOSED * Port within orders should go to Cheyenne for processing * Port in orders should go to Phoenix for processing * Screeners in Dallas must make determination based on remarks field * States manual handling * Move - port within or port between CLEC to CLEC ACTION ITEMS: * NPI field on LSR (determines port in or within) not used by Q. Eschelon has put in a CR for consideration. This field also then could be used to route LSR to right center without manual handling Owner: Mark and Joan * Retrain Dallas to handle current LSRs and screen to right center Owner: Ray * Identify unique req. type for these types of orders for ease in mechanized routing Owner: Joan Wells * With Virtual Center, should Duluth also be trained to handle the port in orders? The volume has been small so expertise has been centralized. Owner: Mary Status - Rev 1: This training took place the week of 9-3-01 with clarification on how to recognize the difference in order to route properly. The current process dictates that any misrouted order to be special handled and not go into regular flow (calls are placed between centers) Status - Rev 2: * An user request to use the NPI field in conjunction with the req. type will be filed by week ending 9-21 so that IMA can automatically route the orders to the proper center for processing. The NPI field is in use at Q on the Resale LSR form. 30-day notification will need to be made to all CLECs prior to implementation. No definite date yet but will target EOY. * The req. type change will not be required since routing will be accomplished through the NPI field. Req. type changes must go through OBF so the option selected for implementation should be more timely. * There were no failures in routing last week for Eschelon. Center managers are stressing the need to review the entire LSR before processing. Daily 3pm calls between centers are identifying each routing failure and preparing direct feedback to the SDC. * Volumes will dictate the move of port-in orders CLEC to CLEC to Duluth. * E is calling on any orders that do not carry telephone # and name of a Phoenix SDC. This is an indication to them that we potentially had a failure in routing. Status - Rev 3 * Routing problems significantly improved * CR for NPI field delayed due to further investigation; all problems resolved and will be issued on 10-8-01 by Joan Wells Status = Rev 5 * UR filed and kick-off meeting held with IT; projected implementation scheduled for late 1st qrt ’02 or early 2nd qrt * Decision made to implement as a going forward change ISSUE 2: Reuse of facilities on Port within orders - CLOSED

* Circuit ID given by E, if available * If reuse is not done, FOC must be noted in the remarks that new facilities are being used so that E can dispatch tech for cross-connect work. Failure to dispatch causes end-user out-of-service condition ACTION ITEMS: * Review process to verify what needs to take place within centers Owner: Mary/Joan/Russ Urvig * Look at Loop Reclamation policy and clarify obligation to reuse facilities Owner: Toni Status - Rev 2: * Clarification needed on product definition pertaining to Q discretion on reuse. Process/Product will get together to clarify and bring back to team concise definition. * Gap still exists when reuse not chosen as option. Order writers not aware of issue at time of FOC so do inform customer. Need to revise process to determine best method of notification. Status - Rev 3: * Policy is to reuse facilities whenever possible preventing dispatch for Q or for CLEC * When reuse is not the available option, our tech should be doing cross-connect work so no dispatch required by CLEC Status - Rev 5: * Process working and full understanding established

ISSUE 3: Trouble Shooting Port in/Port within orders

* When trying to back out orders that have gone bad, Q/E needs to understand internal flow to enhance trouble shooting skills ACTION ITEMS: * Review process and document key points for both Q CSIE team and E Owner: Joan Wells Status - Rev 2: * E indicated that there are numerous areas of failure for these types of work backs often causing outages of up to 3 days. They are recommending focal points within the center to deal with these orders so that expertise will be built and that data can be collected for root cause analysis. This suggestion will be looked at for feasibility and reported out at next meeting (Owner: Toni) Status - Rev 3: * Root cause will be done on all failures with gap analysis and recommended action. (Owner: Claudia Meredith-Trump) First read out on 10-5 * Focal points process to be discussed on 10-5

Status - Rev 5 * Root cause analysis done on 5 failures on 10-5 and 1 failure on 10-26 * Findings: * SO writing orders found for both sending and receiving parties; discussed process adherence and provided feedback to all employees touching orders * CLEC owning customers did not disconnect in switch on a timely basis; early detection of this in trouble shooting process can reduce impairment issues * CSIE personnel reviewed failure points and areas to intervene before additional complications add to length of impairment * Will continue process to look at every failure for additional learning

ISSUE 4: Problem for Port in – working in both switches * Calls going both ways in switch * E would like to coordinate the time between the techs for delivering new facilities ACTION ITEMS: * Review process to id gaps and areas for improvement Owner: Joan Wells Status - Rev 2: * Problem lies with FDT and when triggering takes place at both customer locations (giver/receiver). Joan has made one change to Q to default FDT from 5pm to noon. More investigation to follow on other issues and potential process improvements. Status - Rev 5 * Eschelon filed CR to request options; Joan Wells working on research for options

ISSUE 4: Identifying ways to minimize errors ACTION ITEMS: * Look at using NPI as first characters of PON to capture and track orders for trouble shooting Owner: Ray and Bonnie Status - Rev 2: * E will use effective 9-27 so that Q can capture orders and do root cause. Screening process will stay the same so that we ensure SDC still looks at entire LSR to determine correct routing. Status - Rev 5 * Continue to use field; screening failures minimal; feedback and process review continues with employees

ISSUE 5: Telephone number swap Added 9-17-01 * E will write up issue so right Q people on team to handle * Problem definition: Eschelon has a customer with a ported number (usually resale). They are going to move within the same CO so dual service is not an option. So they establish the customer at the new location with a new telephone number and leave the old number working. When the customer is moved and at the new premise, they need to disconnect the old ported number and reestablish it at the move location - also disconnecting the temporary telephone number. How can they do this?

Status - Rev 3: * Joan to read out on 10-5 Status - Rev 5 To clarify this answer, I checked with Retail on their processes for Port Within (T&F) and also Dual and Overlapping Service, which our Wholesale processes mirror. Retail does not allow dual service if you are porting your telephone number within. This means if the end user has a telephone number currently, that was either previously ported in or a native TN to the switch, and are now moving to a new switch and want to do a port within, they would not be able to have dual service, because of the LRN routing that is taking place through the NPAC. Incoming calls cannot be routed to more than one switch at a time, so this would cause problems with the end user receiving their incoming calls.

If the end user currently has a TN that was previously ported in and now wants to do a T&F to a new location within the same switch, this would not be considered a port within and the limitation involving the dual service would then be dependent upon the switch type, the product type, the line type (bridge taps etc.) and the region. There are methods in Infobuddy that outline the restrictions and rules for dual service, as well as facility check, which helps to determine if dual service is an option in these situations.

So, if dual service is desired, but not available, what the Reseller would have to do, is request a New connect at the new location with new TN's. Then, when they want the service at the old location disconnected, they would have to submit two related requests. One to do a number change at the new location as a port within, indicating the new numbers and another request to disconnect the number at the old location, using port out fids. Qwest would then process the disconnect, using the port out fids and the number change using the port in fids. These would be manual orders, with good remark entries needed from the Reseller as to what exactly is needed on the orders. Standard port due date intervals would apply.

* Process change to be made to allow move and port on one LSR; this will not change Dual service issue but will help with other order issues that cause CLEC to do two LSRs to accomplish task. Effective date yet to be determined. Will continue to monitor progress

Quality Team - Qwest/Eschelon LNP Order Issues: Revision 3 Team Members: Sponsor - Toni Dubuque Q Team - Mark Coyne, Ray Burton, Mary Madill, Joan Wells, Russ Urvig E Team - Bonnie Johnson

Meetings: Sept 10, 2001 @ 10:30am CDT Sept 17, 2001 @ 2:00pm CDT (rev 2) Sept 26, 2001 @ 930am CDT (rev 3) Oct 5,2001 @ 930MDT/1030amCDT (rev 4) Call-In Number: 877-847-3567 pc600-2974

ISSUE 1: Misrouting of orders causing missed commitments

* Port within orders should go to Cheyenne for processing * Port in orders should go to Phoenix for processing * Screeners in Dallas must make determination based on remarks field * States manual handling * Move - port within or port between CLEC to CLEC ACTION ITEMS: * NPI field on LSR (determines port in or within) not used by Q. Eschelon has put in a CR for consideration. This field also then could be used to route LSR to right center without manual handling Owner: Mark and Joan * Retrain Dallas to handle current LSRs and screen to right center Owner: Ray * Identify unique req type for these types of orders for ease in mechanized routing Owner: Joan Wells * With Virtual Center, should Duluth also be trained to handle the port in orders? The volume has been small so expertise has been centralized. Owner: Mary Status - Rev 1: This training took place the week of 9-3-01 with clarification on how to recognize the difference in order to route properly. The current process dictates that any misrouted order to be special handled and not go into regular flow (calls are placed between centers) Status - Rev 2: * An user request to use the NPI field in conjunction with the req type will be filed by week ending 9-21 so that IMA can automatically route the orders to the proper center for processing. The NPI field is in use at Q on the Resale LSR form. 30-day notification will need to be made to all CLECs prior to implementation. No definite date yet but will target EOY. * The req type change will not be required since routing will be accomplished through the NPI field. Req type changes must go through OBF so the option selected for implementation should be more timely. * There were no failures in routing last week for Eschelon. Center managers are stressing the need to review the entire LSR before processing. Daily 3pm calls between centers are identifying each routing failure and preparing direct feedback to the SDC. * Volumes will dictate the move of port-in orders CLEC to CLEC to Duluth. * E is calling on any orders that do not carry telephone # and name of a Phoenix SDC. This is an indication to them that we potentially had a failure in routing. Status - Rev 3 * Routing problems significantly improved * CR for NPI field delayed due to further investigation; all problems resolved and will be issued on 10-8-01 by Joan Wells ISSUE 2: Reuse of facilities on Port within orders

* Circuit ID given by E, if available * If reuse is not done, FOC must be noted in the remarks that new facilities are being used so that E can dispatch tech for cross-connect work. Failure to dispatch causes end-user out-of-service condition ACTION ITEMS: * Review process to verify what needs to take place within centers Owner: Mary/Joan/Russ Urvig * Look at Loop Reclamation policy and clarify obligation to reuse facilities Owner: Toni Status - Rev 2: * Clarification needed on product definition pertaining to Q discretion on reuse. Process/Product will get together to clarify and bring back to team concise definition. * Gap still exists when reuse not chosen as option. Order writers not aware of issue at time of FOC so do inform customer. Need to revise process to determine best method of notification. Status - Rev 3: * Policy is to reuse facilities whenever possible preventing dispatch for Q or for CLEC * When reuse is not the available option, our tech should be doing cross-connect work so no dispatch required by CLEC

ISSUE 3: Trouble Shooting Port in/Port within orders

* When trying to back out orders that have gone bad, Q/E needs to understand internal flow to enhance trouble shooting skills ACTION ITEMS: * Review process and document key points for both Q CSIE team and E Owner: Joan Wells Status - Rev 2: * E indicated that there are numerous areas of failure for these types of work backs often causing outages of up to 3 days. They are recommending focal points within the center to deal with these orders so that expertise will be built and that data can be collected for root cause analysis. This suggestion will be looked at for feasibility and reported out at next meeting (Owner: Toni) Status - Rev 3: * Root cause will be done on all failures with gap analysis and recommended action. (Owner: Claudia Meredith-Trump) First read out on 10-5 * Focal points process to be discussed on 10-5

ISSUE 4: Problem for Port in - working in both switches * Calls going both ways in switch * E would like to coordinate the time between the techs for delivering new facilities ACTION ITEMS: * Review process to id gaps and areas for improvement Owner: Joan Wells Status - Rev 2: * Problem lies with FDT and when triggering takes place at both customer locations (giver/receiver). Joan has made one change to Q to default FDT from 5pm to noon. More investigation to follow on other issues and potential process improvements.

ISSUE 4: Identifying ways to minimize errors ACTION ITEMS: * Look at using NPI as first characters of PON to capture and track orders for trouble shooting Owner: Ray and Bonnie

Status - Rev 2: * E will use effective 9-27 so that Q can capture orders and do root cause. Screening process will stay the same so that we ensure SDC still looks at entire LSR to determine correct routing.

ISSUE 5: Telephone number swap Added 9-17-01 * E will write up issue so right Q people on team to handle * Problem definition: Eschelon has a customer with a ported number (usually resale). They are going to move within the same CO so dual service is not an option. So they establish the customer at the new location with a new telephone number and leave the old number working. When the customer is moved and at the new premise, they need to disconnect the old ported number and reestablish it at the move location - also disconnecting the temporary telephone number. How can they do this?

Status - Rev 3: * Joan to read out on 10-5

Quality Team - Qwest/Eschelon LNP Order Issues: Revision 2 Team Members: Sponsor - Toni Dubuque Q Team - Mark Coyne, Ray Burton, Mary Madill, Joan Wells, Russ Urvig E Team - Bonnie Johnson

Meetings: Sept 10, 2001 @ 10:30am CDT Sept 17, 2001 @ 2:00pm CDT (rev 2) Sept 26, 2001 @ 930am CDT (rev 3) Call-In Number: 877-847-3567 pc600-2974

ISSUE 1: Misrouting of orders causing missed commitments

* Port within orders should go to Cheyenne for processing * Port in orders should go to Phoenix for processing * Screeners in Dallas must make determination based on remarks field * States manual handling * Move - port within or port between CLEC to CLEC ACTION ITEMS: * NPI field on LSR (determines port in or within) not used by Q. Eschelon has put in a CR for consideration. This field also then could be used to route LSR to right center without manual handling Owner: Mark and Joan * Retrain Dallas to handle current LSRs and screen to right center Owner: Ray * Identify unique req type for these types of orders for ease in mechanized routing Owner: Joan Wells * With Virtual Center, should Duluth also be trained to handle the port in orders? The volume has been small so expertise has been centralized. Owner: Mary Status - Rev 1: This training took place the week of 9-3-01 with clarification on how to recognize the difference in order to route properly. The current process dictates that any misrouted order to be special handled and not go into regular flow (calls are placed between centers) Status - Rev 2: * An user request to use the NPI field in conjunction with the req type will be filed by week ending 9-21 so that IMA can automatically route the orders to the proper center for processing. The NPI field is in use at Q on the Resale LSR form. 30-day notification will need to be made to all CLECs prior to implementation. No definite date yet but will target EOY.

* The req type change will not be required since routing will be accomplished through the NPI field. Req type changes must go through OBF so the option selected for implementation should be more timely.

* There were no failures in routing last week for Eschelon. Center managers are stressing the need to review the entire LSR before processing. Daily 3pm calls between centers are identifying each routing failure and preparing direct feedback to the SDC.

* Volumes will dictate the move of port-in orders CLEC to CLEC to Duluth. * E is calling on any orders that do not carry telephone # and name of a Phoenix SDC. This is an indication to them that we potentially had a failure in routing. ISSUE 2: Reuse of facilities on Port within orders

* Circuit ID given by E, if available * If reuse is not done, FOC must be noted in the remarks that new facilities are being used so that E can dispatch tech for cross-connect work. Failure to dispatch causes end-user out-of-service condition ACTION ITEMS: * Review process to verify what needs to take place within centers Owner: Mary/Joan/Russ Urvig * Look at Loop Reclamation policy and clarify obligation to reuse facilities Owner: Toni Status - Rev 2: * Clarification needed on product definition pertaining to Q discretion on reuse. Process/Product will get together to clarify and bring back to team concise definition. * Gap still exists when reuse not chosen as option. Order writers not aware of issue at time of FOC so do inform customer. Need to revise process to determine best method of notification.

ISSUE 3: Trouble Shooting Port in/Port within orders

* When trying to back out orders that have gone bad, Q/E needs to understand internal flow to enhance trouble shooting skills ACTION ITEMS: * Review process and document key points for both Q CSIE team and E Owner: Joan Wells Status - Rev 2: * E indicated that there are numerous areas of failure for these types of work backs often causing outages of up to 3 days. They are recommending focal points within the center to deal with these orders so that expertise will be built and that data can be collected for root cause analysis. This suggestion will be looked at for feasibility and reported out at next meeting (Owner: Toni)

ISSUE 4: Problem for Port in - working in both switches * Calls going both ways in switch * E would like to coordinate the time between the techs for delivering new facilities ACTION ITEMS: * Review process to id gaps and areas for improvement Owner: Joan Wells Status - Rev 2: * Problem lies with FDT and when triggering takes place at both customer locations (giver/receiver). Joan has made one change to Q to default FDT from 5pm to noon. More investigation to follow on other issues and potential process improvements.

ISSUE 4: Identifying ways to minimize errors ACTION ITEMS: * Look at using NPI as first characters of PON to capture and track orders for trouble shooting Owner: Ray and Bonnie

Status - Rev 2: * E will use effective 9-27 so that Q can capture orders and do root cause. Screening process will stay the same so that we ensure SDC still looks at entire LSR to determine correct routing.

ISSUE 5: Telephone number swap Added 9-17-01 * E will write up issue so right Q people on team to

-

Quality Team - Qwest/Eschelon LNP Order Issues: Revision 1 Team Members: Sponsor - Toni Dubuque Q Team - Mark Coyne, Ray Burton, Mary Madill, Joan Wells E Team - Bonnie Johnson

Meetings: Sept 10, 2001 @ 10:30am CDT Sept 17, 2001 @ 2:00pm CDT Call-In Number: 877-847-3567 pc600-2974

ISSUE 1: Misrouting of orders causing missed commitments

* Port within orders should go to Cheyenne for processing * Port in orders should go to Phoenix for processing * Screeners in Dallas must make determination based on remarks field * States manual handling * Move - port within or port between CLEC to CLEC ACTION ITEMS: * MPI field on LSR (determines port in or within) not used by Q. Eschelon has put in a CR for consideration. This field also then could be used to route LSR to right center without manual handling Owner: Mark and Joan * Retrain Dallas to handle current LSRs and screen to right center Owner: Ray Status: This training took place the week of 9-3-01 with clarification on how to recognize the difference in order to route properly. The current process dictates that any misrouted order to be special handled and not go into regular flow (calls are placed between centers) * Identify unique req type for these types of orders for ease in mechanized routing Owner: Joan Wells * With Virtual Center, should Duluth also be trained to handle the port in orders? The volume has been small so expertise has been centralized. Owner: Mary

ISSUE 2: Reuse of facilities on Port within orders

* Circuit ID given by E, if available * If reuse is not done, FOC must be noted in the remarks that new facilities are being used so that E can dispatch tech for cross-connect work. Failure to dispatch causes end-user out-of-service condition ACTION ITEMS: * Review process to verify what needs to take place within centers Owner: Mary * Look at Loop Reclamation policy and clarify obligation to reuse facilities Owner: Toni ISSUE 3: Problem understanding timing of translations

* When trying to back out orders that have gone bad, E needs to understand internal flow to enhance trouble shooting skills ACTION ITEMS: * Review process and document key points for both Q CSIE team and E Owner: Joan Wells

ISSUE 4: Problem for Port in - working in both switches * Calls going both ways in switch * E would like to coordinate the time between the techs for delivering new facilities ACTION ITEMS: * Review process to id gaps and areas for improvement Owner: Joan Wells

ISSUE 4: Identifying ways to minimize errors

ACTION ITEMS: * Look at using MPI as first characters of PON to capture and track orders for trouble shooting Owner: Ray and Bonnie


Open Product/Process CR PC092801-1 Detail

 
Title: Process to improve cut over and ensure completion of incoming calls to CLEC customer, including step requiring Qwest technician to call from the Donor switch immediately after acceptance of the local loop by the CLEC for cut overs.
CR Number Current Status
Date
Area Impacted Products Impacted

PC092801-1 Denied
12/12/2001
Repair LNP, Unbundled Loop
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Diebel, Diane
Director:
CR PM:

Description Of Change

When a customer moves from Qwest to a CLEC, there are times when Qwest does not remove the customer’s telephone numbers from the Qwest switch at the appropriate time. This causes incoming calls to the CLEC customer to fail. This directly impacts the end-user customer, which can not receive those calls. When a customer leaves Qwest, ports its numbers to a CLEC, and the CLEC builds the numbers in its switch, some incoming calls will not complete to the customer because Qwest has not removed the numbers from the Qwest Donor Switch. Eschelon asks Qwest to change its process to ensure that the cut-over is successful and all calls are properly completed to the CLEC’s end users. Eschelon asks Qwest to add a step to its process at the time of test and turn-up of the CLEC loop acceptance. That step would require Qwest technicians to make a call from the Donor Switch to the customer’s numbers that were ported to ensure that Qwest has removed the numbers from its switch. Eschelon believes this process change would avoid the problem described. If additional steps are also needed to ensure a proper cut-over and completion of the incoming calls, Eschelon asks Qwest to identify those steps and ensure the proper result.


Status History

09/28/01 - CR Received from Kathy Stichter of Eschelon

09/28/01 - Status changed to Submitted

09/28/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

10/11/01 - Held Clarification Meeting

10/17/01 - CMP Meeting: Clarification conducted with CLEC community. "Current Status" changed to evaluation.

10/26/01 - Internal meeting to be held with Ken Olson for more clarification.

11/01/01 - Forwarded draft response, dated 10/26/01, to Eschelon

11/09/01 - Issued revised draft response dated 11/09/01 to Eschelon and posted to dBase.

11/14/01 - CMP Meeting: Eschelon moved this to CLEC Test.

11/16/01 - Matt Rossi issued Final Response to CLEC Community.

12/12/01 - CMP Meeting - there were no other issues with the CR. Eschelon indicated that the CR response was a denial. Status to be revised to Denied.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

Alignment/Clarification Meeting October 11th, 2001/11:00 p.m. (MDT) / Thursday, Conference Call 1-877-542-1728 PC7712487 # PCCR092801-1

Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Chris Frederickson, Eschelon Telecom Tina Schiller, Eschelon Telecom Deni Toye, dtoye@qwest.com, Qwest Diane Diebel, dlbail3@qwest.com, Qwest Steve Hilleary, shillea@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Introduction of Attendees Kathy, Chris, Tina, Deni, Diane, Steve, and Kate Review Requested (Description of) Change Process to improve cut-over and ensure completion of incoming calls to CLEC customer, including step requiring Qwest technician to call from the Donor switch immediately after acceptance of the local loop by the CLEC for cut-overs. Confirm Areas & Products Impacted Areas: Repair Products: Unbundled Loop Confirm Right Personnel Involved Diane is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Deb Heckart is also available for questioning. Deni and Steve are available to answer systems questions regarding Unbundled Loop. They will also compare notes with Joan Wells. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Identify/Confirm CLEC’s Expectation When a customer moves from Qwest to a CLEC, there are times when Qwest does not remove the customer’s telephone numbers from the Qwest switch at the appropriate time. This causes incoming calls to the CLEC customer to fail. This directly impacts the end-user customer, which can not receive those calls. When a customer leaves Qwest, ports its numbers to a CLEC, and the CLEC builds the numbers in its switch, some incoming calls will not complete to the customer because Qwest has not removed the numbers from the Qwest Donor Switch. Eschelon asks Qwest to change its process to ensure that the cut-over is successful and all calls are properly completed to the CLEC’s end users. Eschelon asks Qwest to add a step to its process at the time of test and turn-up of the CLEC loop acceptance. That step would require Qwest technicians to make a call from the Donor Switch to the customer’s numbers that were ported to ensure that Qwest has removed the numbers from its switch. Eschelon believes this process change would avoid the problem described. If additional steps are also needed to ensure a proper cut-over and completion of the incoming calls, Eschelon asks Qwest to identify those steps and ensure the proper result. require special handling. If the orders are not written correctly significant service affecting. Identify any Dependent Systems Change Requests No related system CR’s were identified, however Joan Wells may be working on this subject matter as well. Establish Action Plan (Resolution Time Frame) Diane will speak with Joan Wells to ensure we are not duplicating efforts. Diane will also clarify this process and give a response at the next CMP meeting on October 17th, 2001. At that time she will gather feedback and create a formal response to be reviewed at the November CMP meeting. This document will be forwarded to Kate Spry for processing. Kate will forward all examples from Kathy to team for investigation. After the formal response is created, Kate will review and forward this information to Mike Keegan to store in the CR database. This information can then be reviewed and discussed by the CLEC Community at the December CMP Meeting if needed. Deni and Steve will investigate examples and will bring feedback to meeting on Tuesday, October 16th. Kathy, Chris, and Tina can attend the October 17th, 2001 CMP meeting to review verbal response. Additional clarifications can be made at that time.


CenturyLink Response

November 9th, 2001 FINAL RESPONSE

Kathy Stichter ILEC Relations Manager Eschelon

CC: Deb Heckart Kate Spry Deni Toye Steve Hilleary Fred Aesquivel Joan Wells Russ Urevig Barry Orrel

This letter is in response to your CLEC Change Request Form, number PC092801-1 dated 9-28-01 – CR Title: Improve Cut-Over Process

The situation identified advises that when a customer moves from Qwest to a CLEC on UNE services, there are times when Qwest does not remove the customer’s telephone numbers from the Qwest switch at the appropriate time. This causes incoming calls to the CLEC customer to fail.

Eschelon has asked that Qwest add a step to its process at the time of test and turn-up of the CLEC loop acceptance. The request is to have Qwest technicians make a call from the Donor Switch to the customer’s numbers that were ported to ensure that they were removed from the Qwest switch.

Eschelon provide Qwest research indicates that this LSR request received from Eschelon was for a straight LNP order, not for UNE service.

The LSR requested disconnect of 3 numbers, the porting and disconnect of 651-735-4000 and the change of the BTN. When the Market Unit Service Deliver Coordinator (SDC) wrote the orders, the SDC failed to issue the order with the porting and disconnect of 651-735-4000. Thus the request was not sent to down stream systems to be worked. All work that was on the Qwest issued order was completed according to process by Network. SDC processes have been reviewed to ensure that these types of errors are addressed.

The requested PCCR was directed at UNE type orders. The example provided by Eschelon does not reflect this issue. UNE orders with LNP do have processes in place that ensures orders are ported prior to completing with the CLEC. Qwest processes do have steps in place to ensure that the line translations are completed in the Switch prior to advising the CLEC that the work has been completed.

Therefore, Qwest does not feel that a change to the current process is necessary at this time based on the results of the research. If the order was issued correctly, all work would have been completed accurately. Implementation of the proposed change would not have ensured this line was ported.

If Eschelon has examples of UNE services with LNP that illustrate problems related to the specific change request, please provide them and Qwest will review.

Straight (i.e., non-UNE related) LNP disconnect issues are being addressed in PCCR 5582099.

Sincerely,

Diane Diebel Director Process Management


Open Product/Process CR PC100101-1 Detail

 
Title: Use NPI (Number Port Indicator) field on LSR for requests for orders requiring Port In and Port Within information. (reference Systems CR # SCR083001 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC100101-1 Completed
11/14/2001
Pre-Ordering, Ordering Centrex, Resale, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

Currently the CLEC populates the NPI field with data that identifies Port In and Port Within information. The NPI field is not a recognized field for Qwest LSOG5. Qwest’s system routes the orders based on the REQTYP. Within the REQTYP requests can contain Port In and Port Within service. For requests that require Port In and Port Within, Qwest uses the remarks section of the LSR and the CLEC must also populate the Manual IND field with a Y. This process puts the onus on the CLEC and not Qwest to ensure Qwest routes the order to the correct center. These requests require special handling. If the orders are not written correctly significant service affecting problems, up to and including customers out of service for several days, arise on the due date. Eschelon asks that Qwest start using the NPI field to recognize that a request is for number porting.


Status History

09/30/01 – CR received by Kathy Stichter of Eschelon

10/01/01 – CR status changed to Submitted

10/01/01 – Updated CR sent to Kathy Stichter of Eschelon and Steve Sheahan of Qwest

10/10/01 - Held Clarification Conference Call with Eschelon

10/17/01 - CMP Meeting: Clarification conducted with CLEC community. "Current Status" changed to evaluation. A Qwest internal request is in process to utilize NPI field.

11/01/01 - Issued draft response dated 10/29/01 to Eschelon.

11/08/01 - Issued revised draft response dated 11/6/01.

11/14/01 - CMP Meeting: Eschelon completed and closed this CR and will open a Systems CR instead.

11/16/01 - Matt Rossi issued Final Response to the CLEC Community.


Project Meetings

Alignment/Clarification Meeting

11:00 p.m. (MDT) / Wednesday, October 10th, 2001 Conference Call 1-877-542-1728 PC7712487 # PCCR100101-1

Attendees: Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Bonnie Johnson, bjohnson@eschelon.com, Eschelon Telecom Connie Overly, coverly@qwest.com, Qwest Joan Wells, jmwell2@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Introduction of Attendees Kathy, Connie, Russ, Joan, and Kate Review Requested (Description of) Change Use NPI (Number Port Indicator) field on LSR for requests for orders requiring Port In and Port Within. Confirm Areas & Products Impacted Areas: Pre-Ordering and Ordering Products: Centrex, Resale, and UNE-P Confirm Right Personnel Involved Joan is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Connie is available for back-up questions. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Identify/Confirm CLEC’s Expectation Currently the CLEC populates the NPI field with data that identifies Port In and Port Within information. The NPI field is not a recognized field for Qwest LSOG5. Qwest’s system routes the orders based on the REQTYP. Within the REQTYP requests can contain Port In and Port Within service. For requests that require Port In and Port Within, Qwest uses the remarks section of the LSR and the CLEC must also populate the Manual IND field with a Y. This process puts the onus on the CLEC and not Qwest to ensure Qwest routes the order to the correct center. These requests require special handling. If the orders are not written correctly significant service affecting problems, up to and including customers out of service for several days, arise on the due date. Eschelon asks that Qwest start using the NPI field to recognize that a request is for number porting. Joan is very comfortable with what they are asking and can give a thorough response. Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Joan will clarify this process and give a response at the next CMP meeting on October 17th, 2001. At that time she will gather feedback and create a formal response to be reviewed at the November CMP meeting. This document will be forwarded to Kate Spry for processing. After the formal response is created, Kate will review and forward this information to Mike Keegan to store in the CR database. This information can then be reviewed and discussed by the CLEC Community at the December CMP Meeting if needed. Kathy and Bonnie can attend the October 17th, 2001 CMP meeting to review verbal response. Additional clarifications can be made at that time.


CenturyLink Response

Final Response Wholesale Product Marketing

November 6, 2001

Ms. Kathleen Stichter Eschelon Telecom

This letter is in response to Change Request Form, PC100101-1 – Use NPI (Number Port Indicator) field on LSR for requests for orders requiring Port In and Port Within.

Description of Change: “Currently the CLEC populates the NPI field with data that identifies Port In and Port Within information. The NPI field is not a recognized field for Qwest LSOG5. Qwest’s system routes the orders based on the REQTYP. Within the REQTYP requests can contain Port In and Port Within service. For requests that require Port In and Port Within, Qwest uses the remarks section of the LSR and the CLEC must also populate the Manual IND field with a Y. This process puts the onus on the CLEC and not Qwest to ensure Qwest routes the order to the correct center. These requests require special handling. If the orders are not written correctly significant service affecting problems, up to and including customers out of service for several days, arise on the due date. Eschelon asks that Qwest start using the NPI field to recognize that a request is for number porting.”

Definitions of Port Activity associated with this request include: ? Port In activity includes all service requests in which the end user is currently being served by another Network Service Provider and the end user does not currently reside in a Qwest switch. Qwest has received a Local Service Request to Port the end user into the Qwest switch. Current Wholesale activity includes Port In to Qwest Resell Services. ? Port Within (Location Portability) is the ability of end users to retain the same telephone number when moving from one service location, to another area that is served by different central offices within the same Rate Center and in some locations, within NPA and municipal boundaries. The end user is currently being served by Qwest as the network Service Provider and resides in a Qwest switch.

On the OBF LSOG 5 Resale form there is a field called the NPI field. (ref 11) Actually, this is a Qwest recognized field, but currently there are no edits in place involving this field. Current accepted entries for the NPI field that will be utilized are: C=Port In Working TN D=Port In Reserved TN Z=Port Within When this field is populated, then the Manual IND field should be set to “Y” and the remark should be populated with a positive entry. Qwest has issued a system change request to begin utilizing this field for proper routing of Port in and Port Within orders to the correct Interconnect Center work queues. Scheduled implementation will be in a future IMA release. It is believed that with implementation of this change, orders will be automatically routed to the correct Interconnect Center for processing. This should help to expedite the Port In/Port Within order received process and ensure that the correct Center doing the provisioning will have access to the order sooner. Qwest has also issued 2 internal communicators as a reminder of the current process for handling Port In and Port Within service requests. The first dated 09-04-01 is titled “Processing LSR requests when the manual Handling filed has an entry of “Y”, along with an entry in the Remark field”. The second, dated 10-26-01, titled “Correct processing of LSR Requests when manual handling “Y”, has been entered, along with a Remark entry requesting a Port In or Port Within”. Once verification of the completion time is known, notification will be sent via the CMP Process or CLEC notification. Qwest would like to close this CR and work issues related to future implementation through SCR083001-1, which relates directly to the system implementation of the NPI field.

Sincerely, Joan Wells LNP Process Manager


Open Product/Process CR PC100101-2 Detail

 
Title: Process for Feature Verification on CSRs not available through IMA or CEMR.
CR Number Current Status
Date
Area Impacted Products Impacted

PC100101-2 Completed
2/20/2002
Ordering, Repair Centrex, Resale, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: McMahon, Cheryl
Director:
CR PM:

Description Of Change

Eschelon asks Qwest to implement a process for CLECs concerning how they would get feature verification on CSRs (Customer Service Record) when IMA or CEMR does not give information. Currently Qwest has a process for Large CSRs but not all failures are for large CSRs.


Status History

09/30/01 - CR received by Kathy Stichter of Eschelon

10/01/01 - CR status changed to Submitted

10/01/01 - Updated CR sent to Kathy Stichter of Eschelon and Steve Sheahan of Qwest

10/03/01 - CR Clarification meeting scheduled to be held with Kathy Stichter of Eschelon on 10/08/01 via 09:30 AM MST conference call

10/08/01 - Clarification Meeting Held with Eschelon.

10/17/01 - CMP Meeting: CLEC community & Qwest conducted clarification discussion. Process for large CSR's is working; however, process (in place) for small CSR's may not be effective. Qwest requested information regarding number of occurrences (#/week) for both IMA and CEMR requests from CLEC community in order to modify current small CSR's process, as necessary. "Current Status" changed to Evaluation.

10/23/01 - Response from Eschelon: To:kthomte@qwest.com , Subject: Feature Verification Failures PC 100101-2 Kit, Our repair department says that they experience about 10 failures in CEMR each week when trying to retrieve feature verification information. Some folks do not use the feature verification anymore because they were always

getting a failure. For the ones that still try they experience about 10 failures in CEMR each week. Our repair department does not use IMA for feature verification. Please pass this information on to the correct people. Thanks, Kathy Stichter, ILEC Relations Manager, Eschelon Telecom Inc, Voice 612 436-6022, Email: klstichter@eschelon.com

11/09/01 - Draft response provided to Eschelon.

11/14/01 - CMP Meeting the Process Change response was reviewed by Qwest (IMA ,CEMR) three action items need to be addressed by Qwest prior to the next CMP session 1 Eschelon would like to see some data regarding how many error messages occur when performing Feature Verification and have them sorted by type 2 Revise the response to include interval associated with smaller requests 3 Find out the Qwest retail interval for Feature Verification.

12/05/01 - Issued revised draft response dated 12/5/01 to Eschelon.

12/12/01 - CMP Meeting - Qwest presented its revised response. It was agreed that the CR could be put into CLEC Test.

12/28/01 - Qwest's formal Response dated 12/5/01 to CLECs.

01/16/02 - CMP Meeting - Qwest advised that the User Guides were updated to include Qwest's response. Eschelon is to review the User Guides and Qwest is to follow-up with Eschelon to close.

01/29/02 - Telecon with Eschelon, Kathy Stichter - Eschelon didn't have any issues with the CR. We agreed that the CR would be left in CLEC Test until the February CMP Meeting for a final review with all CLECs before agreeing to close.

02/20/02 - CMP Meeting - It was agreed that the CR could be Closed. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/20/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

October 08,2001 9:30 MDT Alignment/Clarification Meeting 1770 - C 1-866 682-6249 Pass Code 7026857 PCCR 100101-2 Process for feature verification on CSRs not available through IMA or CEMR

Introduction of Attendees Kathy Stichter Eschelon Monica Manning Qwest Cheryl McMahon Qwest Kit Thomte Qwest

Kit identified the participants on the call as shown above. Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Reviewed the information contained on the CR and shared information that Kathy Stichter provided. The CR description asks Qwest to implement a process for CLECs concerning how they would get Feature Verification on CSRs (Customer Service Record) when IMA or CEMR does not give information. Currently Qwest has a process for Large CSRs but not all failures are for large CSRs.

Confirm Areas & Products Impacted {read from change request, modify if needed} Centrex, Resale and UNE P are the impacted products.

Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Monica Manning from Wholesale will address IMA Cheryl McMahon from Repair will address CEMR Dan Busetti did not participate but the CR did not appear to have system ramifications

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)} Eschelon would like a documented process explaining what they need to do when the information is not available. Monica indicated there are very specific messages for example 161error message BOSS CARS records were not available. In this instance the CLEC should contact the call center. In the case of connectivity issues they would call the help desk??? Kathy inquired if the process being discussed matched the process used for large CSRs Monica indicated that a communication should have been sent to the CLECs explaining the process. Monica would locate the communication associated with IMA. Cheryl McMahon will check out the CEMR process.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} Monica indicated that Mark Routh is having a call 10-9 regarding feature verification. Monica will let us know if they are related.

Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when}


CenturyLink Response

December 5, 2001

Kathleen Stichter ILEC Relations Manager Eschelon Telecom, Inc

This letter is being sent in response to CLEC Change Request Form # PC100101-2. PC100101-2 pertains to a request for a Feature Verification process for CSRs not available through IMA or CEMR. This response addresses the IMA and CEMR processes for Feature Verification on Small CSRs, when the CSR is not available. It also addresses the interval for Feature Verification for retail customers

IMA Process:

? If a CLEC attempts Feature Verification for a Small CSR (50 pages or less) in IMA and the CSR is unavailable, they may receive one of the following error messages: “Received Error From FNSGateway ResDup Account List: E105”, “Received Error From FNSGateway ResDup Account List: E106”, “Cannot Connect to April”. When one of these error messages is received, CLECs may submit their requests for Feature Verification via a new process for Small CSR Feature Verification. Unless significant issues are raised by the CLECs which are being resolved by the parties, the new process will take effect on December 17, 2001.

? When an IMA request for Small CSR Feature Verification is unsuccessful because the CSR is unavailable, CLECs will submit their requests to a designated e-mail address or fax number in the Interconnect Service Center. The request should be submitted to the Interconnect Service Center that normally processes the CLEC’s LSRs. The telephone number and state of the CSR being verified must be included in the request.

? The appropriate e-mail addresses and fax numbers for Small CSR Feature Verification follow: Denver Center – e-mail: kwalden@qwest.com; fax number (303) 383-7197, Minneapolis Center – e-mail: lahend1@qwest.com, rdrier@qwest.com, gfinnem@qwest.com or cranta@qwest.com; fax number (612) 663-0502.

? The commitment interval for completing and responding to Feature Verification requests for Small CSRs will be determined either by the number of pages in the CSR or individual negotiation. The standard interval for a CSR with 50 pages or less is 1-3 business days. During peak periods, it may be necessary to individually negotiate the commitment interval for a Feature Verification request.

? When the Feature Verification process is complete, the center Service Delivery Consultant will send an e-mail or fax response (determined by how the request was sent) to the CLEC. The Feature Verification response will include the verification process findings and a description of any corrective action taken.

Questions regarding IMA Feature Verification should be directed to the Interconnect Service Center at 1 888 796-9087.

CEMR Process:

? Feature Verification failures not related to service orders or occurring past the 72-hour order completion timeframe should be referred to the Repair Center via e-mail. The Repair Center e-mail address for Feature Verification requests is cemrfv@qwest.com. The Feature Verification request e-mail should include the telephone number and feature to be verified and the CEMR error message received.

? Requests for 3 or less Feature Verifications received Monday through Saturday from 6:00 a.m. until 6:00 p.m. will receive a response within 4 hours.

? Requests of 4 or more Feature Verifications will receive a response within 24-72 hours of the request.

? Requests received after 6:00 p.m. and before 6:00 a.m. Monday through Friday will be processed the following day using the guidelines based on the size of the request.

? Requests received after 6:00 p.m. Saturday and all day Sunday will be processed the following Monday and will follow the guidelines based on the size of the request.

To further assist the CLECs, the CEMR User Guide will be updated during December to include Feature Verification error messages (e.g., unable to retrieve switch data) and next step instructions to follow when an error is received in CEMR for Feature Verification.

Additionally Qwest was asked to provide the Qwest retail interval for Feature Verification. Automated feature verification is not available to retail customers. A retail customer notifies the repair center to initiate a repair ticket for feature troubles.

Sincerely, Monica Manning IMA Process Specialist

Cheryl McMahon Senior Process Analyst


Open Product/Process CR PC100101-3 Detail

 
Title: Qwest to issue orders for Port In and Port Within Correctly. (reference Systems CR # SCR083001 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC100101-3 Completed
11/14/2001
Pre-Ordering, Ordering Centrex, LNP, Resale, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM: Thomte, Kit

Description Of Change

When orders including Port In and Port Within are issued incorrectly they cause significant service affecting problems, up to and including customers out of service for several days. Eschelon asks Qwest to establish and provide a documented, trained and adhered to process to ensure orders are issued correctly for Port In and Port Within situations.


Status History

09/30/01 - CR received by Kathy Stichter of Eschelon

10/01/01 - CR status changed to Submitted

10/01/01 - Updated CR sent to Kathy Stichter of Eschelon and Steve Sheahan of Qwest

10/03/01 - CR Clarification meeting scheduled to be held with Kathy Stichter of Eschelon on 10/10/01 via 03:15 PM MST conference call

10/10/01 - Clarification meeting conducted with Eschelon.

10/17/01 - CMP Meeting: CLEC community & Qwest conducted clarification discussion. Qwest to provide response for next CMP Meeting (November 14, 2001). "Current Status" changed to Evaluation.

10/29/01 - Sent Draft Response to Kathy Stichter at Eschelon.

11/08/01 - Sent Updated Draft Response to Kathy Stichter at Eschelon.

11/14/01 - CMP Meeting the response to this Process Change was accepted and the request was closed. Systems CR 083001-1 was issued to implement the change.

11/26/01 - Final response sent based on outcome of CMP meeting


Project Meetings

October 10, 2001 3:15 MDT Alignment/Clarification Meeting 1770-C 877 847-0338 7022846 PCCR100101-3

Introduction of Attendees Kathy Stichter Eschelon Joan Wells Qwest Kit Thomte Qwest

Introduced attendees as mentioned above Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Kathy provided a history of why this CR had been submitted. Jeff Thompson recommended that this be submitted as a process CR because it is an order writing issue.

Confirm Areas & Products Impacted {read from change request, modify if needed}

Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Joan Wells is the person that deals with this subject.

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)}

Kathy indicated that the problem really comes from the orders being routed to the wrong center. As a result they end up being worked incorrectly. Joan indicated that MCC’s have been sent out regarding the process associated with how these requests should be routed. Long term the use of NPI should resolve the routing issues. Bonnie inquired if Joan could include in her request, that if manual handling is not indicated on the order could the NPI field be used to route the order rather than the manual handling.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} Another CR exists that is addressing the NPI field. Kit will get w Kate Spry to coordinate between these two CRs. Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when}


CenturyLink Response

Wholesale Product Marketing November 7, 2001

Ms. Kathleen Stichter Eschelon Telecom

This letter is in response to Change Request Form, PCCR100101-3 - Qwest to issue orders for Port In and Port Within Correctly, dated 09/30/2001. Description of Change: When orders including Port In and Port Within are issued, they cause significant service affecting problems, up to and including customers out of service for several days. Eschelon asks Qwest to establish and provide a documented, trained and adhered to process to ensure orders are issued correctly for Port In and Port Within situations.

Definitions of Activity: * Port In activity includes all service requests in which the end user is currently being served by another Network Service Provider and the end user does not currently reside in a Qwest switch. Qwest has received a Local Service Request to Port the end user into the Qwest switch. Current Wholesale activity includes Port In to Qwest Resell Services. * Port Within (Location Portability) is the ability of end users to retain the same telephone number when moving from one service location, to another area that is served by different central offices within the same Rate Center and in some locations, within NPA and municipal boundaries. The end user is currently being served by Qwest as the network Service Provider and resides in a Qwest switch.

Items of concern: 1) End User customers out of service for several days. * Port In service order requests are handled the same way as regular Resale New Connects. Dial tone is verified up to the Network Interface prior to completion. However, successful completion of the port often depends upon the disconnect of the switch translation’s that are currently being provided by the old Network Service Provider. Qwest currently processes the incoming request with a default frame due time of 12pm unless otherwise indicated by the Reseller. This helps to ensure that Qwest programming is completed prior to the disconnect of the old Network Service Provider, which Qwest requests to take place at 5pm. If translation’s are not removed from the old Network Service Provider’s switch, intra-office calls may be affected. Qwest has no way to determine if the old Network Service Provider as completed their piece of this process. * Port Within orders are handled the same way as regular Resale T&F orders. Dial tone is verified up to the Network interface, with a disconnect occurring at the old location in conjunction with installation at the new location. Inside wiring is generally the responsibility of the Resale Provider. * Qwest has an escalation process currently in place. The Clec/Reseller may contact the Interconnect Call Center at 800 796-9087 for support and open up an escalation ticket up to 48 hours after the port due date should a problem occur. * If requested, Qwest will do a root cause analysis on problem as they occur for continued process improvement.

2) Eschelon asks Qwest to establish and provide a documented, trained and adhered to process to ensure orders are issued correctly for Port In and Port Within situations. Qwest confirms that the Port In and Port Within processes are documented internally for those Qwest employees that process service order requests associated with this type of activity. This process is however, a manual process in which service orders requests must be screened and routed to the correct Interconnect Center. Qwest has also issued 2 internal communicators as a reminder of the current process for handling Port In and Port Within service requests. The first dated 09-04-01 is titled "Processing LSR requests when the manual Handling filed has an entry of "Y", along with an entry in the Remark field". The second, dated 10-26-01, titled "Correct processing of LSR Requests when manual handling "Y", has been entered, along with a Remark entry requesting a Port In or Port Within".

The Centers are continuing to do Root Cause analysis on problem orders (via the Quality Team), with direct feedback to the Center employees involved as needed. Qwest has also issued a request to have a system update done. Qwest will, with the correct use of the NPI field that currently appears on the Resale form, automatically route Port In and Port Within service order requests to the correct Interconnect Center for proper provisioning. This request was a result of PCCR100101-1.

After CLEC review, Qwest would like to request that this CR be closed, with further follow-up to take place in conjunction with PCCR100101-1.

Sincerely, Joan Wells LNP Process Manager


Open Product/Process CR PC100101-4 Detail

 
Title: Developed, documented, trained and adhered to process to make sure that customer’s old VM boxes are removed when a customer leaves Qwest for a CLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC100101-4 Completed
3/20/2002
Repair Centrex, Resale, Unbundled Loop, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Van Dusen, Janean
Director:
CR PM:

Description Of Change

When a customer leaves Qwest to order service with a CLEC and the customer had Qwest VM, Qwest does not consistently remove the customer’s old VM box. This causes the end user to experience trouble. Incoming calls to the end user could be routed to the old VM box that the end user no longer recognizes. When incoming callers leave messages in an old VM box the end user never gets the messages because they do not know to check the old box. Then the messages that are left and not deleted cause, what the end user identifies as, a constant stutter dial tone. The end user calls Eschelon believing the problem is with the Eschelon provided VM. Qwest is often unable to find the old VM box to tear it down because the Qwest CSR no longer exists. It sometimes takes weeks to get an old Qwest VM box removed, inconveniencing the end user. Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process to make sure customers’ old VM boxes are removed when a customer leaves Qwest for a CLEC.


Status History

09/30/01 - CR received by Kathy Stichter of Eschelon

10/01/01 - CR status changed to Submitted

10/01/01 - Updated CR sent to Kathy Stichter of Eschelon and Steve Sheahan of Qwest

10/10/01 - Clarification Meeting Scheduled for October 15, 2001 with Eschelon

10/15/01 - Held Clarification Meeting with Eschelon

10/15/01 - MCC Issued titled "VOICE MESSAGING-BUS/RES (BVMS/VMS)", asking to check for associated Call Forwarding features when removing Qwest Voice Messaging on a conversion to Resale

10/16/01 - Qwest Draft response posted to database.

10/17/01 - CMP Meeting - Clarification Conducted with CLEC Community, "Current Status" changed to Evaluation.

10/31/01 - Issued draft response dated 10/31/01 to Eschelon.

11/14/01 - CMP Meeting - Qwest presented its response. Eschelon stated that when call forward numbers are changed correctly, the Qwest voice-mailbox does not come down and interferes with call forwarding. Qwest advised that the response does not address this issue. It was recommended that another clarification meeting be held with Eschelon.

11/19/01 - Eschelon representative on vacation from 11/19-11/23 unavailable for clarification call

12/03/01 - Second clarification call held (earliest available time slot)

12/12/01 - CMP Meeting: Janean Van Dusen (Qwest) gave a status update. Revised response will be presented in January. Status remains in Presented.

12/14/01 - Qwest asked Eschelon for some recent examples of when the voice mailbox had not been removed correctly

12/17/01 - Reply e-mail from Eschelon, they will obtain examples

12/19/01 - An internal systems change request was created to ensure associated features are removed when a voice mail box is removed. Target implementation is early April 2002.

01/03/02 - E-mail from Qwest asking for examples

01/08/02 - Called Eschelon and discussed the need for an example(s) with Kathy.

01/10/02 - Action Item # 1 opened in response to E-mail from Eschelon asking for process example

01/16/02 - January CMP meeting. Qwest explained the process and system fixes they are implementing to help correct this problem. However, to get to the root cause Qwest needs examples from the CLECs. CLECs agreed to provide examples when this issue occurs again. CR status changed to "Development"

02/07/02 - Action Item # 1 (response to E-mail from Eschelon asking for process example) moved to pending closure

02/20/02 - February CMP meeting: Action item # 1 presented and closed. CLECs had no new examples to examine. General agreement obtained from CLECs to move this CR to CLEC Test and reevaluate at the March CMP meeting. CR Status changed to "CLEC Test" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

03/01/02 - Formal response dated 02/22/02 issued to CLECs. Notification number: CMPR.03.01.02.F.01233.CR_Responses

03/04/02 - Formal response dated 02/22/02 posted to the CMP database

03/04/02 - Formal response dated 02/22/02 posted to web in the Product & Process Interactive report URL: http://qwest.com/wholesale/cmp/changerequest.html

03/20/02 - CMP Meeting - It was agreed that the CR could be closed, CR status changed to Completed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

01/10/02 E-mail from Eschelon asking for process example Subject: FW: FW: PC100101-4 Examples Date: Thu, 10 Jan 2002 11:06:02 -0600 From: "Stichter, Kathleen L." To: tmead@qwest.com Todd, We do not have any current examples to supply Qwest. What did Qwest do that they think the issue is fixed? At the clarification meeting I asked to see the process Qwest uses. I have not seen that yet. Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

01/03/02 E-mail from Qwest asking for examples Subject: Re: FW: PC100101-4 Examples Date: Thu, 03 Jan 2002 10:28:55 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: "Stichter, Kathleen L." Kathy, Have you had any luck tracking down any examples? Todd

12/17/01 Reply e-mail from Eschelon Subject: FW: PC100101-4 Examples Date: Mon, 17 Dec 2001 08:01:15 -0600 From: "Stichter, Kathleen L." To: tmead@qwest.com Todd, I will see what we can get. Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

12/14/01 E-mail from Qwest, requesting examples from Eschelon Sent: Friday, December 14, 2001 5:29 PM To: Kathleen Stichter Subject: PC100101-4 Examples Kathy, We are having some difficulty identifying the process gaps that are causing the problem identified in your CR. It would be extremely helpful to get some examples from Eschelon. Either a previous example of this problem or ideally, one that you are currently attempting to get resolved. Any help would be appreciated. Thanks Todd

3:00 p.m. (MDT) / Monday 3rd December 2001 Clarification Meeting Kathy Stichter / Eschelon Chris Frederiksen / Eschelon Mallory Paxton / Qwest Janean Van Dusen / Qwest Todd Mead / Qwest Review Requested (Description of) Change Area Impacted - Repair Products - Centrex, Resale, Unbundled Loop, UNE-P Confirm Right Personnel Involved - Potential network involvement required, Janean will coordinate Identify/Confirm CLEC’s Expectation - Eschelon would like to see the process (either new or existing), that outlines exactly how old Voice Mail boxes are removed when a customer leaves Qwest for a CLEC. The process should include the Qwest contact information in the event of a VM box not being removed. Action Plan - After internal research, Qwest will supply a status at the December CMP meeting giving a timeframe for a revised response.

1:00 p.m. (MDT) / Monday, Oct 15th, 2001 Alignment/Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PCCR100101-4 Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Mallory Paxton, mpaxton@qwest.com, Qwest Janean Van Dusen, jvandus@qwest.com, Qwest Michael Belt, mbelt@qwest.com, Qwest Introduction of Attendees Kathy, Janean, Mallory, Michael Review Requested (Description of) Change Developed, documented, trained and adhered to process to make sure that customer’s old VM boxes are removed when a customer leaves Qwest for a CLEC. Confirm Areas & Products Impacted Area: Repair Products: Resale - Janean Van Dusen Confirm Right Personnel Involved Products: Resale - Janean Van Dusen Identify/Confirm CLEC’s Expectation The customer's CR requested a process to make sure customers VM boxes are removed on conversion of an end user from retail to resale. Identify any Dependent Systems Change Requests N/A Establish Action Plan (Resolution Time Frame) Janean VanDusen to provide response by 10/17/01


CenturyLink Response

February 22, 2002

Kathleen Stichter ILEC Relations Manager Eschelon Telecom

SUBJECT: Qwest’s Change Request Response - CR # PC100101-4 Developed, documented, trained and adhered to process to make sure that customer’s old VM boxes are removed when a customer leaves Qwest for a CLEC.

REQUEST: When a customer leaves Qwest to order service with a CLEC and the customer had Qwest VM, Qwest does not consistently remove the customer’s old VM box. This causes the end user to experience trouble. Incoming calls to the end user could be routed to the old VM box that the end user no longer recognizes. When incoming callers leave messages in an old VM box the end user never gets the messages because they do not know to check the old box. Then the messages that are left and not deleted cause, what the end user identifies as, a constant stutter dial tone. The end user calls Eschelon believing the problem is with the Eschelon provided VM. Qwest is often unable to find the old VM box to tear it down because the Qwest CSR no longer exists. It sometimes takes weeks to get an old Qwest VM box removed, inconveniencing the end user. Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process to make sure customers’ old VM boxes are removed when a customer leaves Qwest for a CLEC.

RESPONSE: Since mid-December 2001, Qwest have been asking CLECs for recent examples of Qwest not removing the customer’s old Voicemail box. However, CLECs have yet to experience any reoccurrence of this problem. Qwest communicated the process for adding, changing or disconnecting voice mailboxes to the CLEC community on January 29, 2002. Qwest believes that with the distribution of this documented process and on-going monitoring, this CR can be closed.

Sincerely,

Janean Van Dusen Product Manager Qwest

Cc: Bill Campbell, Director Product Management, Qwest Mallory Paxton, Senior Process Analyst, Qwest


Open Product/Process CR PC092801-2 Detail

 
Title: Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process for vendor meets.
CR Number Current Status
Date
Area Impacted Products Impacted

PC092801-2 Denied
1/16/2002
Repair Centrex, Resale, UNE-P, Unbundled Loop
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Aesquivel III, Frederick
Director:
CR PM:

Description Of Change

Eschelon would like Qwest to document a process for vendor meets. There are times when Eschelon calls Qwest repair to report trouble and Qwest says that no trouble was found or that the trouble was past the DMARC and Eschelon does not agree because Eschelon has determined that the trouble is with Qwest. Qwest will close the ticket. Eschelon will then try to reopen a ticket with Qwest and Qwest insists on a vendor meet since they say they found no trouble. Qwest would set up a vendor meet with Eschelon for a specific day and time. Now Qwest is saying that they will not set a specific time that they need a 4-hour window. Eschelon can not have a technician sitting around for 4 hours waiting for a Qwest technician to show up at a customer premise. Eschelon asks Qwest for its definition of a Vendor Meet. Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process for vendor meets with appropriate associated time frames. This process should state the steps that should take place, from beginning to end, on a vendor meet. It should specify under what conditions a vendor meet is required. It should state a window of 30 minutes or less for the time to meet on a specific date. It should state that a ticket is not closed until the CLEC authorizes the ticket to be closed. It should state that if the Qwest technician is going to be late that the technician is required to call the CLEC so they can advise their technician and their customer.


Status History

09/28/01 - CR received from Kathy Stichter of Eschelon

09/28/01 - CR status changed to Submitted

09/28/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

10/11/01 - Held Clarification Meeting

10/17/01 - CMP Meeting: Clarification conducted with CLEC community. "Current Status" changed to evaluation. Draft response to be written.

10/30/01 - Received Draft Response from Fred Aesquivel III.

11/01/01 - Forwarded draft response, dated 10/30/01, to Kathy Stichter

11/14/01 - CMP Meeting: Eschelon moved this to CLEC Test. Qwest requested that Eschelon provide examples of any push-back they are receiving regarding vendor meets.

11/16/01 - Matt Rossi issued Final Response to CLEC Community.

12/12/01 - CMP Meeting - Eschelon requested that the CR be left in CLEC Test. Eschelon to provide any input to Fred Aesquivel and Ric Martin, qwest.

01/16/02 - CMP Meeting - Eschelon had no examples to provide. They requested that the CR be placed into Denied status because Qwest's response didn't provide what was requested by the CR for POTS.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

10:30 p.m. (MDT) / Thursday, October 11th, 2001 Alignment/Clarification Meeting Conference Call 1-877-542-1728 PC7712487 # PCCR092801-2

Attendees: Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Deni Toye, dtoye@qwest.com, Qwest Fred Aesquivell III, faesqui@qwest.com, Qwest Don Tolman, dtolman@qwest.com, Qwest Carolyn Mills, camills@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Introduction of Attendees Kathy, Deni, Fred, Don, and Kate Review Requested (Description of) Change Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process for vendor meets. Confirm Areas & Products Impacted Areas: Repair Products: Resale, Centrex, UNE-P, and Unbundled Loop Confirm Right Personnel Involved Fred is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Deni and Don are available to answer process questions. Carolyn is filling in for questioning for Yvonne Philpot. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Identify/Confirm CLEC’s Expectation Eschelon would like Qwest to document a process for vendor meets. There are times when Eschelon calls Qwest repair to report trouble and Qwest says that no trouble was found or that the trouble was past the DMARC and Eschelon does not agree because Eschelon has determined that the trouble is with Qwest. Qwest will close the ticket. Eschelon will then try to reopen a ticket with Qwest and Qwest insists on a vendor meet since they say they found no trouble. Qwest would set up a vendor meet with Eschelon for a specific day and time. Now Qwest is saying that they will not set a specific time that they need a 4-hour window. Eschelon can not have a technician sitting around for 4 hours waiting for a Qwest technician to show up at a customer premise. Eschelon asks Qwest for its definition of a Vendor Meet. Eschelon asks Qwest to establish and provide a documented, trained and adhered to effective process for vendor meets with appropriate associated time frames. This process should state the steps that should take place, from beginning to end, on a vendor meet. It should specify under what conditions a vendor meet is required. It should state a window of 30 minutes or less for the time to meet on a specific date. It should state that a ticket is not closed until the CLEC authorizes the ticket to be closed. It should state that if the Qwest technician is going to be late that the technician is required to call the CLEC so they can advise their technician and their customer. Fred, Don, and Deni all agreed that the rep telling there was a 4 hour window was a mistake and that she just didn’t understand the process. Kathy said this was only a one time occurrence and the woman she spoke with was Linda Rogers out of the Utah Call Center regarding #(801) 546-7493. We currently have an internal process in place which explains the process for vendor meets which Fred will run by legal and verify that we can pass this on to the CLECs. This process was created on 8/31/00. Identify any Dependent Systems Change Requests No related system CR’s were identified. Establish Action Plan (Resolution Time Frame) Fred will clarify this process and will check with legal to verify that he can provide our internal documentation to the CLEC’s which explains the vendor meets process. Fred will give a response at the next CMP meeting on October 17th, 2001. At that time he will gather feedback and create a formal response to be reviewed at the November CMP meeting. This document will be forwarded to Kate Spry for processing. Fred will find out why this information is not posted to the web for the CLEC’s information and will also find out why the supervisor was not aware of this process which has been in place since 8/31/00. After the formal response is created, Kate will review and forward this information to Mike Keegan to store in the CR database. This information can then be reviewed and discussed by the CLEC Community at the December CMP Meeting if needed. Don will also make sure that this information is provided to the different centers for future reference. Kathy can attend the October 17th, 2001 CMP meeting to review verbal response. Additional clarifications can be made at that time.


CenturyLink Response

October 30, 2001 Final Response

Kathy Stichter ILEC Relations Manager Eschelon

CC: Terry Meehan Kate Spry

This letter is in response to the following CLEC Change Request Form PC092801-2 dated September 28, 2001. The Change Request is asking for clarification on definition and requesting several process changes from Qwest as outlined below:

* Eschelon is requesting Qwest’s definition of a vendor meet. Qwest’s joint meet definition includes: Qwest responds to CLECs requesting a joint meet to troubleshoot activities at an assigned location. Qwest, CLECs, and possibly third party vendors, meet to isolate hard-to-find faults, verify existing trouble and diagnosis, conduct joint studies on switch circuits and resolve chronic and repeat problems. All designated parties, including Qwest and the CLEC, will meet at a prearranged trouble location to test a particular circuit. Dispatch Out (WFA/DO) joint meets are classified as meets that take place outside the central office. Dispatch "In" (WFA/DI) joint meets take place inside the central office. These meetings are short and informal and result in a corrected fault.

Complex Service customers are requesting joint meet commitments on Service Assurance tickets (trouble reports). The customer is expecting a field technician to be on premise during a specified timeframe.

Note that the above response is from a Qwest process bulletin for Designed Services.

* Eschelon is requesting that Qwest implement a (documented, trained, and adhered to) process for vendor meet (specific date and time) for Plain Old Telephone Services (POTS). Qwest currently has this process in place for Designed Services. Based on initial analysis, given the volumes of POTS dispatched out trouble reports that Qwest processes, Qwest believes that providing all Retail and Wholesale customers the latitude to request a specific date and time would significantly increase the risk of maintaining current repair service performance levels for all customers. Qwest denies this Change Request as written.

* Eschelon is requesting that Qwest will not close any repair ticket until the CLEC authorizes the ticket to be closed. Qwest does not in all cases have direct access to all CLECs to perform “real time” transfer of trouble resolution and completion information. Waiting for a CLEC to clear voice mail and reply back to Qwest that they are authorized to close a specific ticket may result in increased trouble resolution time, missed appointments, and technician idle time. Qwest denies this Change Request as written.

* Eschelon is requesting that if a Qwest technician is going to be late (for the joint meet) that the technician be required to call the CLEC so they can advise their technician and customer. Not applicable unless the above requested process is deployed.

Again, please note that Qwest does have a process in place for joint meets on Design Services where the volumes are considerable lower, and the trouble types are generally more complex due to the nature of complex products and services.

Respectfully,

Frederick M Aesquivel III Director - Local Network Operations Support


Open Product/Process CR PC100401-1 Detail

 
Title: Process for Coordinated Hot Cuts on CLEC UBL to CLEC Resale. (Reference System CR # SCR100401 1x)
CR Number Current Status
Date
Area Impacted Products Impacted

PC100401-1 Denied
1/15/2003
Pre-Ordering, Ordering Centrex, Resale, UNE-P, UBL with LNP
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest only offers Coordinated Hot Cuts (CHC) on the unbundled product. Qwest should offer the option for coordination when a customer is converting from CLEC UBL (Unbundled Loop) to CLEC resale. Whether reuse of facilities or new facilities are requested the coordination of the Lift and Lay and/or install, porting, and translations requires coordination to ensure our end user customers do not experience service impacting issues for extended periods of time. Eschelon asks Qwest to offer coordination on CLEC UBL to CLEC resale cut-overs.


Status History

10/02/01 - CR received from Eschelon

10/04/01 - CR status changed to Submitted

10/04/01 - CR Updated and sent to Eschelon.

11/05/01 - Clarification Mtg Held with Eschelon.

11/12/01 - Had additional questions for Eschelon which were emailed to Kathy Stichter at Eschelon.

11/12/01 - Need to schedule another meeting with Eschelon. New questions have come up after further investigation. Left message for Kathy S. to call me to schedule.

11/14/01 - CMP Meeting - Eschelon presented the CR. It was determined that UBL with LNP needed to be added and that there should be another clarification meeting

11/19/01 - Received answers back from Eschelon, however Kathy S. is on vacation from 11/19-11/23 and I haven't yet heard back from her to be able to schedule nessessary meeting with her.

11/29/01 - Conducted additional clarification meeting with Eschelon.

11/29/01 - Eschelon provided clarification e-mail.

12/03/01 - Clarification Meeting Minutes issued to Eschelon.

12/12/01 - CMP Meeting - Qwest advised of the coordination effort required in addition to its LNP Managed Cut product and expressed concern in coordination with 3rd party CLEC. Eschelon advised they were only interested in Qwest internal coordination. Qwest to investigate whether the Network coordinated process could be used in-lieu-of developing a new product. Qwest to develop its response.

01/08/02 - Issued Qwest's Draft Response dated January 4, 2002 to Eschelon and posted to dBase.

01/16/02 - CMP Meeting - Qwest presented its draft response. Qwest advised that it would like to present another solution based on partnering with retail. CR will remain in Presented status and Qwest will address the issues from the CMP meeting.

01/31/02 - Received questions from Eschelon to be addressed in Qwest's response.

02/12/02 - Issued Qwest's Revised Draft Response dated 2/7/02 to Eschelon.

02/20/02 - CMP Meeting - Qwest presented its revised response. It was agreed that the CR could be moved to Development. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

02/22/02 - Qwest's formal response dated 2/7/02 issued to CLEC Community.

03/13/02 - Issued Development status update and answers to Eschelon's questions from the 2/20/02 CMP Meeting. Posted update in the CMP dBase under Qwest Response.

03/20/02 - CMP Meeting - Qwest provided a status update on the process development and responded to Eschelon's questions from February's CMP Meeting. The CR will remain in Development status. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/17/02 - CMP Meeting - Qwest provided a status updated and indicated that a Systems CR would need to be created to complete the process development. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed to issue a Systems CR.

04/24/02 - Issued Systems CR to cmpcr@qwest.com on behalf of Eschelon.

05/15/02 - CMP Meeting - Qwest advised that the Systems CR had been issued. It was agreed that the CR could be closed. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

01/07/03 - Re-opened CR, and activated, removed from archive, changed status from Completed to Evaluation on 1/7/03.

01/08/03 - Sent Qwest response to Bonnie Johnson at Eschelon

01/15/03 - January CMP Meeting - Qwest presented response. CR status changed to Denied. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

01/15/03 January CMP Meeting Kit Thomte with Qwest explained that this CR was crossed over from Systems to Product and Process, SCR100401-1X was closed, and Kit presented the denial response to this CR, PC100401-1. Kit explained that PC100401-1XMN has been opened to address the completion call manual process. Status of this CR will be changed to Denied.

12/19/02 Systems CMP Meeting Kit Thomte/Qwest said we’ve had a couple of discussions over the last few days on the this CR. Bonnie Johnson/Eschelon thought this CR had been denied and wanted Qwest to provide a status in this meeting. What we’ve agreed to do, is to close the existing systems CR, resurrect the original Product/Process CR, deny it, then create a sub-CR under the Product/Process CR with an MN suffix so that the things that Bonnie Johnson/Eschelon wanted would be addressed in the sub CR. Judy Schultz/Qwest- noted that Section 5.7 of the CMP Document states that if there is a systems change request with a manual process available, then a parent-child relationship CR would be created. The reason we went that route is that Bonnie Johnson/Eschelon felt that the original request was a deny and did not want to start with a new date. Bonnie Johnson/Eschelon stated that when this CR was originally opened, we were optimistic that it would happen, and it was crossed over to Systems to add a USOC. The systems CR does not apply any more. She also stated that it was very important to me because I asked for a specific product. Qwest stated that they are unable to fulfill that request so the CR has to be denied. They have some solutions that will alleviate some of the pain, so part of what I asked for can be provided. Jonathan Spangler/AT&T asked Bonnie Johnson/Eschelon if they are asking Qwest to do a coordinated hot cut. Bonnie Johnson/Eschelon noted from unbundled to resale or UNE-P. Jonathan Spangler/AT&T asked how is that different from what we’re building with Joan Wells/Qwest now. Bonnie Johnson/Eschelon said that is just with port-in. Jonathan Spangler/AT&T asked if we have clarification that the loop that the CLEC is using is a Qwest loop - Qwest is not going to reuse the facility. Bonnie Johnson/Eschelon said that the problem is you have the potential of a customer working at two switches. Judy Schultz/Qwest said that when we open this MN CR, we’ll bring that it forward to the next meeting and make sure we have all the right people on the telephone from Product and Process. Jonathan Spangler/AT&T stated that the CLEC to UNE-P CLEC discussion with Joan Wells/Qwest might help to see how we handle those orders. Mike Zulivac/Covad said that is something that Covad is interested in as well. If there is an opportunity to broaden the scope to include all types of coordinated hot cuts that may be beneficial. Jonathan Spangler/AT&T asked if they would have to define the scope of the MN CR. Bonnie Johnson/Eschelon said that Qwest has actually denied this, so I’m not sure that will help you Judy Schultz/Qwest said that there are piece parts that can be completed through a manual process change. She explained that that was what the MN suffix was to be used for. Once we have the experts in the room perhaps, we can address your concerns as well. Therefore, is everyone ok with us closing the systems CR, denying the original Product/Process CR and then having the appropriate SMEs in the room to discuss the MN CR. All agreed. Kit Thomte/Qwest said that this action item will be closed.

Subject: FW: CR Issues Related to CHC for UBL to Resale Conversions Date: Thu, 31 Jan 2002 13:10:11 -0600 From: "Stichter, Kathleen L." To: rhmart2@qwest.com CC: "Johnson, Bonnie J."

Ric, Please respond to Bonnie's questions and requests below. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc 612-436-6022 klstichter@eschelon.com

> --Original Message-- > From: Johnson, Bonnie J. > Sent: Sunday, January 20, 2002 7:14 PM > To: Stichter, Kathleen L. > Cc: Powers, F. Lynne; Clauson, Karen L. > Subject: CR Issues Related to CHC for UBL to Resale Conversions > > Kathy, > The following are the questions I would like to communicate to Ric Martin. > * Qwest indicated there was a documented process for Network services stating if there is a lift and lay involved, the lift and lay would be > done at or as close to the FDT as possible. Please confirm and provide documentation. * What is the jeopardy process when Qwest is unable to obtain an FOC > on the TN release from another CLEC. * What is the appropriate interval for UBL to Resale port in conversions. Please provide documentation. * Is there a standard interval for responding to an LSR requesting the release of TN's. What is the industry standard. What is Qwest's obligation > to obtain the response. > > In addition, Eschelon would like to move forward with the process recommendation for orders where new facilities are required. > > Thanks for your assistance. > > Bonnie Johnson

--

Subject: FW: Conference Call for CR for CHC Date: Thu, 29 Nov 2001 16:12:47 -0600 From: "Stichter, Kathleen L." To: rhmart2@qwest.com

Ric, Eschelon's intent on the CR was for both scenarios. So based on the call this morning, what Eschelon would be looking for would be 2 different processes. One for internal to Qwest only and one that would coordinate internally and externally with the CLEC (Eschelon) if the CLEC for the UBL was the same CLEC for the resale. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

--

CLEC Change Request Clarification Meeting

November 29, 2001, 9:30 am (MT) Conference Call

866.564.8688 PC100401-1, Process for Coordinated Hot Cuts on CLEC UBL to CLEC Resale

Attendees: Ric Martin, Qwest Joan Wells, Qwest Kathy Stichter, Eschelon

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the call was to reconfirm Eschelon’s requirements under the CR and review their e-mail dated 11/19/01.

Review CR Requirement an E-Mail Qwest explained that Qwest currently has a process for ordering a loop with LNP. Also there is currently coordination with Port-out activities. There currently is no coordination on Port-in activity. Qwest explained that there could be 2 scenarios for a coordination of a cut from CLEC UBL to CLEC Resale: 1. CLEC owns the UBL and Resale – Eschelon UBL want to go to Eschelon Resale. 2. A different CLEC Owns the UBL from the resale – Another CLEC owns the UBL and want to go to Eschelon Resale. Qwest advised that they could provide the coordination process internally to Qwest when the UBL and Resale are by the same CLEC.

Qwest currently doesn’t control the 3rd party CLECs release of a translation. Qwest doesn’t have a product offering for the Port-in coordination and would need to establish agreements for this activity with other CLECs.

Confirm Right Personnel Involved Qwest’s indicated that Joan Wells would be responsible for the internal Port-in coordination process, but Qwest Product Marketing would be responsible for development of any product offerings.

Action Plan Eschelon is to confirm if they want Qwest to develop a process for the two (2) scenarios listed in 2.2 above or only scenario 1. Qwest to review requirements for a product offering with Product Manager. Based on Eschelon’s answer to 7.1, Qwest to evaluate and develop response.

-

11/19/01 E-Mail from, Stichter, Kathleen L." wrote:

> Kate, > Bonnie Johnson has answered your questions below. > Thanks > > Kathy Stichter > ILEC Relations Manager > Eschelon Telecom Inc > Voice 612 436-6022 > Email klstichter@eschelon.com > > > --Original Message-- > > From: Johnson, Bonnie J. > > Sent: Friday, November 16, 2001 4:57 PM > > To: Stichter, Kathleen L. > > Subject: RE: [Fwd: PCCR100401-1, Questions] > > > > > > Kathy, > > See below! > > --Original Message-- > > From: Stichter, Kathleen L. > > Sent: Friday, November 16, 2001 1:30 PM > > To: Johnson, Bonnie J. > > Subject: FW: [Fwd: PCCR100401-1, Questions] > > > > Bonnie, > > Can you please answer the questions below and I will send the answers on > > to Kate? > > Thanks > > > > Kathy Stichter > > ILEC Relations Manager > > Eschelon Telecom Inc > > Voice 612 436-6022 > > Email klstichter@eschelon.com > > > > --Original Message-- > > From: Kate Spry [SMTP:kspry@qwest.com] > > Sent: Monday, November 12, 2001 3:28 PM > > To: klstichter@eschelon.com > > Subject: [Fwd: PCCR100401-1, Questions] > > > > Kathy, > > > > Could you please answer a few questions for us. Thanks. > > > > Kate Spry > > > > Joan Wells wrote: > > > > Thanks for your help, Kate. > > > > Questions about PCCR100401-1. > > > > 1) Would we ever have an Unbundled Loop conversion to a Resale account > > without LNP? No > > If so, in what scenario would this be? > > Would you want coordination for this as well? > > > > 2) I understand the CR to be specific to Port In to Resale from a CLEC > > that currently has the end user as an UBL. > > Qwest will make every attempt to reclaim the loop. Do you want > > coordination on the Port in even when Qwest is not reusing any facilities? > > Yes for the LNP and translations > > > > 3) If Qwest is unable to successfully negotiate managed cut arrangements > > with the outgoing CLEC, would you still want the internal Qwest Port In > > piece to be managed? Yes > > > > 4) If this is established as a product offering, charges may apply. Would > > this be satisfactory? Yes. > > > > 5) Are you wanting coordination for Port Within T&F's as well? No. > > However, we have had situations where the F comes down before the T goes > > up. I understand there will be some down time but this is for several > > hours. We would like the F side kept up until it is necessary to do > > translations on the port within and T side. > > > > << Message: PCCR100401-1, Questions >>

Return-Path:

-

Alignment/Clarification Meeting 10:30 p.m. (MDT) / Friday, November 5th, 2001 Conference Call 1-877-542-1728 Attendees: Kathleen Stichter, klstichter@eschelon.com, Eschelon Telecom Tina Schiller, tmschiller@eschelon.com, Eschelon Telecom Bonnie Johnson, bjjohnson@eschelon.com, Eschelon Telecom Russ Urevig, rurevig@qwest.com, Qwest Stacy Hartman, sscrogh@qwest.com, Qwest Mallory Paxton, mpaxton@qwest.com, Qwest Janean Van Dusen, jvandus@qwest.com, Qwest Laurel Neher, lneher@qwest.com, Qwest Debra Smith, dssmith@qwest.com, Qwest Kate Spry, kspry@qwest.com, Qwest

Eschelon asks Qwest to establish a process for Coordinated Hot Cuts on CLEC Unbundled Loop to CLEC Resale. Areas: Pre-Ordering and Ordering Products: Resale, Centrex, UNE-P Janean is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Lorna Dubose and/or Maureen Callan should be notified and brought into the response for answers regarding Migration. Stacie, Mallory, Laurel, and Debra will be available for any questions regarding their impacted areas. Kate will coordinate all necessary clarification meetings, complete meeting minutes, and review, forward, and store necessary documentation to database. Currently Qwest only offers Coordinated Hot Cuts (CHC) on the unbundled product. Qwest should offer the option for coordination when a customer is converting from CLEC UBL (Unbundled Loop) to CLEC resale. Whether reuse of facilities or new facilities are requested the coordination of the Lift and Lay and/or install, porting, and translations requires coordination to ensure our end user customers do not experience service impacting issues for extended periods of time. Eschelon asks Qwest to offer coordination on CLEC UBL to CLEC resale cut-overs. No related system CR’s were identified. Janean will clarify this process internally and will give a verbal response at the December CMP meeting. At that time she will gather feedback and create a formal response to be reviewed at the January CMP meeting. This document will be forwarded to Kate Spry for processing. After the formal response is created, Kate will review and forward this information to Mike Keegan to store in the CR database and will forward this information to Kathy S.. This information can then be reviewed and discussed by the CLEC Community at the January CMP Meeting if needed. Kathy can attend the December 2001 CMP meeting to review verbal response. Additional clarifications can be made at that time. A written formal response will be forwarded after that meeting is held and feedback is provided.


CenturyLink Response

January 7, 2003

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR # PC100401-1.Process for Coordinated Hot Cuts on CLEC UBL to CLEC Resale. Description of Change: Currently, Qwest only offers Coordinated Hot Cuts (CHC) on the unbundled product. Qwest should offer the option for coordination when a customer is converting from CLEC UBL (Unbundled Loop) to CLEC resale. Whether reuse of facilities or new facilities are requested the coordination of the lift and lay and/or install, porting, and translations requires coordination to ensure our end user customers do not experience service impacting issues for extended periods of time. Eschelon asks Qwest to offer coordination on CLEC UBL to CLEC resale cut-overs.

This update is to document what Qwest and the CLECs have agreed to with Eschelon’s CR Request as noted above. - As we discussed in the May 2002 CMP Product Process, this CR was moved to completed status. Qwest advised this CR would close and cross over as a reissue in systems CR to pursue the Completion Call process solution. - As we also advised in the August CMP Product Process meeting regarding action item AI051502-2, Retail is not going to pursue the CHC process. Eschelon agreed that the action item could be closed. - During the December CMP meeting, Eschelon requested a formal denial of this CR as presented. As discussed the CR as presented is technically not feasible for Qwest. - Qwest and the CLECs have been working on the alternative process and a viable “completion call” option has been agreed to with Eschelon. As a result of this, a new CR will be initiated by Qwest in the January Product Process meeting.

Meanwhile, Eschelon’s original CR #PC100401-1 is denied as technically not feasible and we will be working through the alternate process utilizing the Product Process CMP requirements.

Sincerely,

Joan Wells Process Analyst, LNP

- 03-08-2002

Eschelon Telecom Ms.Kathleen Stichter

Dear Ms. Stichter:

SUBJECT: Development Status Update - Change Request CR # PC100401-1. Process for Coordinated Hot Cuts on CLEC UBL to CLEC Resale

The following is an update on the developments of the Coordinated Hot Cuts:

At this time, Qwest is unable to confirm the Coordinated Port In process because it is still in the early stages of development. Should the Coordinated Port In process be developed and implemented, Qwest Wholesale will at that time look at the offering again.

In accordance with your direction at February’s CMP meeting, Qwest is moving forward with the “Completion Call” and will now concentrate on the development and costs associated with the Completion Call” process. Qwest will continue to provide status updates during the development process

Below are response to the action items from February’s CMP meeting:

1.) Eschelon has requested that the Wholesale Escalation Centers be made aware of the Network lift and lay process. Qwest Wholesale Process will educate the Escalation group about this existing Network process through an internal communicator and on the Qwest weekly LNP team call.

2.) Eschelon asked if the intervals stated are in the Standard Interval guide. Standard Intervals for Installation on Ported In TNs are based on the Product specific guidelines. However, the Desired Due Date is a tentative due date, until the Firm Order Confirmation (FOC) is received from the Old Service Provider (OSP) prior to releasing the Port In telephone number into our systems. The OSP will participate in the port activity. The Number Portability Administration Center, (NPAC) will anticipate receiving subscription activity (service orders) with matching DDD and Frame Due Time (FDT) released by both companies within the same timer windows. Qwest will process the request as quickly as possible, to try to accommodate the desired due date.

3.) Concerns were brought up about the process Qwest has when they are unable to obtain an FOC on the TN release from the current CLEC. Changes to the proposed process were requested by the CLECs, as well as verification of parity on this process with Qwest Retail.

These responses are as follows: Qwest expects to receive a reciprocal FOC response from the CLEC community when we request a Port Out into the Qwest Network and will not complete a Port In request to our network without receiving an FOC from the Old service Provider. ? Qwest will issue the number port LSR to the OSP and follow-up for 5 business days on simple services and Complex service orders. ? If Qwest has not received the FOC from the OSP, the SDC will contact the OSP directly to find out why a response has not been sent. ? Qwest will contact the Reseller requesting the Port In and let them know that an FOC response has not been received yet. The Resale Provider may also contact the current Provider to encourage an FOC response. ? Qwest will follow-up again in 5 business days, if still no response, Qwest will contact the Qwest Service Manager of the current CLEC for help in obtaining the FOC. ? Qwest will follow-up again in 5 business days, if still no response, Qwest will cancel the LSR sent to the Old Provider and reject the order back to the Reseller.

Note: As long as Qwest Wholesale continues to receive correspondence from the current CLEC (OSP) concerning the Port request, Qwest will continue to pursue the FOC response and the Port In activity.

During the February’s CMP meeting, Qwest Retail had stated that Retail would continue to process the Winback to Qwest request as long as they have continued correspondence from the current CLEC. If they are unable to get a response or receive confirmation from the CLEC, they will refer the request back to the Retail Sales force to contact the end user.

Sincerely,

Joan Wells Process Manager Local Number Portability Qwest

Cc: Lorna Dubose, LNP Product Manager, Qwest Joan Smith, Qwest Retail

-

02-07-2002

Eschelon Telecom Ms.Kathleen Stichter

SUBJECT: Qwest’s Change Request Response - CR PC100401-1 Process for Coordinated Hot Cuts on CLEC UBL to CLEC Resale

Description of Change: Currently, Qwest only offers Coordinated Hot Cuts (CHC) on the unbundled product. Qwest should offer the option for coordination when a customer is converting from CLEC UBL (Unbundled Loop) to CLEC resale. Whether reuse of facilities or new facilities are requested the coordination of the lift and lay and/or install, porting, and translations requires coordination to ensure our end user customers do not experience service impacting issues for extended periods of time. Eschelon asks Qwest to offer coordination on CLEC UBL to CLEC resale cut-overs.

The Initial response provided to Eschelon included consideration of offering increased coordination internally for Wholesale Port In activity. Qwest Wholesale proposed a more simplified process of a Completion Call. This Completion Call process would be available only when new facilities are being used. The Reseller would indicate in Remarks on the LSR, that they are requesting a Completion Call. Qwest would develop a new FID that could be placed in the Remarks sections of the order when issued, that would indicate to the outside Plant Technician (new facilities) that a completion call has been requested by the Reseller. This FID, along with the Reseller Contact Name and Number would appear on the order. Upon completion of the work, the Reseller would be notified by the outside Plant Technician, which would then allow them to complete any additional work needed.

After this proposal was made, Qwest Wholesale became involved with Qwest Retail in assisting with developing a different type of Coordinated Port In / Port Within process, which will include more than just offering a completion call.

At this time, Qwest is unable to confirm the offering, because it is still in the initial development stages.

Eschelon has requested responses to the following additional concerns:

1.) Eschelon would like to see the documented process for Network Services stating the details of the lift and lay process to help ensure that the lift and lay process takes place as close to the Frame Due time as possible.

This Qwest Internal process is documented in the Network Services, Central Office Job Aid, document CO-CL-01-0002/Rev.6. “Competitive Local Exchange Carrier (CLEC) to Qwest Migration”, dated 01/16/2002. Included in this document is the process for coordinating the movement of the customers telephone number, when number portability is involved, from CLEC to Qwest. The details include: the Central Office will be control for the coordination of the design services “IAD” disconnect and the Retail/Resale New Connect. When the correlation of the two orders has been identified by the C.O. personnel, which is created by the related order activity between the loop reclamation and the new install, the orders will be worked at the FDT (Frame Due Time) on the Retail/Resale order Due Date, or as close there after as possible. Testing of the cable pair and a test call to the number will be done to confirm porting. Qwest Wholesale has confirmed this process with Network and they have ensured us that Qwest personnel are aware of this process.

2.)What is the jeopardy process when Qwest is unable to obtain an FOC on the TN release from another CLEC.

Qwest expects to receive a reciprocal FOC response from the CLEC community when we request a Port Out into the Qwest Network and will not complete a Port In request to our network without receiving an FOC from the Old service Provider. ? Qwest will issue the number port LSR to the OSP and follow-up for 5 business days on simple services and Complex service orders.

? If Qwest has not received the FOC from the OSP, the SDC will contact the OSP directly to find out why a response has not been sent. ? Qwest will contact the Reseller requesting the Port In and let them know that an FOC response has not been received yet. ? Qwest will follow-up again in 5 business days, if still no response, Qwest will cancel the LSR sent to the Old Provider and reject the order back to the Reseller.

3.) What is the appropriate interval for UBL to Resale Port In conversions. Please provide documentation.

At this time an appropriate Due Date Interval for the Port In request with or with Loop Reclamation is 10 days. This coincides with the process of follow-up listed in issue 2.

4.) Is there a standard interval for responding to an LSR requesting the release of TN’s. What is the industry standard? What is Qwest’s obligation to obtain the response?

Industry standards are guidelines only. It is the expected that the FOC response of the CLEC should be reciprocal of that currently listed in the standard interval guide established by Qwest. Qwest is acting on behalf of the Reseller to complete this Port In request accurately and timely. After two attempts are made to contact the CLEC, the LSR will be rejected back to the Reseller, refer to response 2.

Sincerely,

Joan Wells Process Manager Local Number Portability Qwest

Cc: Lorna Dubose, LNP Product Manager, Qwest


Open Product/Process CR PC102901-1 Detail

 
Title: Qwest to include PON on Qwest Winback Orders.
CR Number Current Status
Date
Area Impacted Products Impacted

PC102901-1 Completed
4/17/2002
Ordering Centrex, Resale, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Pent, Anne
Director:
CR PM: Thomte, Kit

Description Of Change

Currently when Qwest Wins Back a customer from Eschelon and an order is issued on an Eschelon account Qwest does not enter a PON. When Qwest does not enter a PON on an order then the Loss and Completion Report does not include a PON. Eschelon asks Qwest to develop, document, distribute and train an adhered to process to use a PON on all orders issued on Eschelon accounts.


Status History

10/29/01 - CR Received by Kathy Stichter of Eschelon

10/29/01 - CR Status changed to Submitted

10/29/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

10/30/01 - Clarification meeting scheduled for Friday 11/02/01.

11/02/01 - Clarification Meeting held with Eschelon

11/14/01 - CMP Meeting - Eschelon presented its CR.

12/05/01 - Second clarification call held

12/12/01 - CMP Meeting: Eschelon presented its CR, Qwest SME in attendance, status changed to Evaluation. Discussion centered on whether the fix will be systems or process related. Eschelon was concerned about the timing of implementation if a systems fix is required. Qwest will explore both systems and process related fixes to this request. Qwest will present their draft response at the January CMP meeting.

01/10/02 - Draft response dated 01/10/02 posted to the CMP database and issued to Eschelon. Status changed to "Presented"

01/16/02 -January CMP meeting. Qwest presented their response to the CLEC community. CLECs agreed to change the status to "Development"

01/21/02 - Formal response dated 01/10/02 issued to CLECs

02/20/02 - February CMP meeting: Action item # 1 presented and closed. CR will remain in Development status until March CMP meeting. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/21/02 - Notification issued to CLECs with announcement of PON field enhancements on Loss & Completion report

03/20/02 - March CMP meeting. CLECs agreed to change CR status to "CLEC Test." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be

posted on the CMP Web site

04/01/02 - Sent Eschelon an e-mail asking for status on the system fix

04/01/02 - Reply e-mail from Eschelon - they continue to send daily reports to Qwest with missing PONs

04/09/02 - E-mail from Qwest explaining the two examples where there was no PON for winback orders

04/17/02 - April CMP Meeting: CLECs agreed to close CR. Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site


Project Meetings

04/09/02 - E-mail from Qwest explaining the two examples where there was no PON for winback orders

Subject: Qwest Winbacks - Loss Report Date: Tue, 09 Apr 2002 15:09:36 -0600 From: "Todd Mead" Organization: Qwest Communications International, Inc. To: Bonnie Johnson CC: Kathleen Stichter

Bonnie, Thanks for the update on this issue. Qwest continues to monitor and investigate the daily spreadsheet you send to Dee. Thus far, Qwest has discovered two examples from your spreadsheets where the PON field was left blank on Qwest Winbacks. However, both of these orders were processed on 3/14 (the edit was implemented 3/16). If these early orders are not touched between the issue date and completion date and were submitted prior to the 3/16 edit, then the PON field will remain blank. However, for any orders submitted after 3/16 you should not see the PON field blank for Winbacks. Please continue to monitor and forward any examples to Qwest.

Thanks

Todd

04/01/02 - Reply e-mail from Eschelon - they continue to send daily reports to Qwest with missing PONs

Subject: RE: CR Update Date: Mon, 1 Apr 2002 10:20:31 -0600 From: "Johnson, Bonnie J." To: Todd Mead , "Stichter, Kathleen L."

Todd, See below!

--Original Message-- From: Todd Mead [SMTP:tmead@qwest.com] Sent: Monday, April 01, 2002 9:46 AM To: Stichter, Kathleen Cc: Johnson, Bonnie Subject: CR Update

Kathy, I am looking for some feedback on two of your CRs that are currently in CLEC Test:

PC102901-1 "Qwest to include PON on Qwest Winback Orders" Hopefully you are now seeing the Loss reports with the PON field populated for winback orders? Check with Dee Lucket at Qwest. We continue to send "missing PON's" to her on a daily basis. Dee would be able to give you the compliance rate as she identifies which "missing PON's" are Qwest winbacks.

02/21/02 Notification issued to CLECs with announcement of PON field enhancements on Loss & Completion report

Announcement Date: February 21, 2002 Effective Date: March 16, 2002 Document Number: SYST.02.21.02.F.02589.PONFldLs-CmplRpt Notification Category: System Target Audience: CLECs, Resellers Subject: PON Field for Loss & Completion Report (Winback and Record Orders)

This notification is to advise Loss & Completion report users that, effective March 16, 2002, two enhancements to the Loss & Completion reports will be implemented:

- For Qwest ‘Winback’ orders, the Loss and Completions report will display “000015137896” as the PON. - For Qwest ‘Record’ orders, the Completions report will display “RECCOR” as the PON.

If you have any questions, please feel free to contact me at 303-896-2680.

Curt Anderson 271 IT PMO

Wednesday, 5th December, 2001 / 12:00 p.m. (MST)

Second clarification call

Attendees: Kathy Stichter / Eschelon Bonnie Johnson / Eschelon Anne Robberson / Qwest Donna Svendgaard / Qwest Todd Mead / Qwest

Identify/Confirm CLEC’s Expectation - Eschelon do not want to see any orders on the completion report without an accompanying PON - Eschelon do not require the use of the word “Win Back” on the completion report if this creates parity issues with Qwest Retail. Who the customer goes to is not important to Eschelon, confirmation that Eschelon should stop billing the customer is the issue here. - With the implementation of a suitable process, Qwest and Eschelon can stop the current process of sending and investigating daily spreadsheets of completion orders with no PONs.

Establish Action Plan Anne will set up a meeting with Resale before next CMP meeting (12/12/01) Anne will report progress at December CMP meeting A draft response will be posted to the web and presented at January’s CMP meeting

Friday, 2nd November, 2001 Clarification Meeting Conference Call 1-877-847-0338 PC7826706 # PC102901-1 Qwest to include PON on Qwest winback orders.

Meeting Minutes of Eschelon Meeting 11/2/2001

Attendees: Kathy Stichter, Eschelon Bonnie Johnson, Eschelon Mark Routh, Qwest CMP Manager Peggy Esquibel-Reed, Qwest CMP Todd Mead, Qwest CMP Mike Belt, Qwest CMP Mark Coyne, Qwest Wholesale Process Anne Robberson, Qwest Wholesale Process Nancy Walker, Qwest Wholesale Systems Barbara Campbell, Qwest Wholesale Systems Curt Anderson, Qwest Wholesale Systems

The above attendees met on Friday, 11/2/2001 to review the research findings for the data issues that Eschelon had identified on their Loss and Completions reports. The research findings and resulting Qwest actions are documented in a document titled “Eschelon Research Summary”. The details of the data researched are documented in a document titled “Eschelon Research Details”. In addition to the Qwest actions identified in the “Eschelon Research Summary”, the following action items were identified in the meeting:

Anne will complete the Issue Reference column on the Eschelon Research Details document and return the document to Nancy. Nancy will forward it on to Peggy for distribution to Eschelon. Mark Coyne will define and implement a process for identifying the Qwest winback orders on the list of orders with missing PONs that Eschelon delivers to Qwest daily. Nancy will contact Alan Zimmerman to discuss Eschelon’s use of the Loss and Completions Report. It appears that Eschelon is using the report to identify when a line was lost for the purpose of discontinuing account billing. This may not be an appropriate use of this report. Anne will research the “C” orders with TIC charges that appear on one of Eschelon’s daily missing PONs list and will determine whether or not these orders were written correctly. Anne will research the orders that were identified as missing the TRAK DCR RS on the Eschelon Research Details document and will determine what process failures caused the omission. The following URs and CRs were discussed as a result of this research. Curt will track the processing of these requests to provide status updates to his management prior to the next CMP meeting. 1. Missing or Inaccurate PON on Completion Report:

The Missing PON spreadsheet sent on 10/2 had 248 detail lines which reflected 118 orders with missing or inaccurate PONS. For these orders, the Completion Report correctly included the service order information that was present in the SOP. The SOP either did not have PONs for these orders or had the inaccurate PONs at the time the orders completed. The causes for the missing or inaccurate PONs were traced to the following seven order writing scenarios:

Of the 118 orders: A. 58 are Qwest Retail “winback” orders. These orders were initiated by Qwest Retail and do not include PONs. These orders appear on the Loss and Completions Reports for the CLEC that is losing the service to notify them of the impact to their business. Qwest Actions: - Anne will talk with the retail service center that processes “winback” orders to gather information about their process and will determine if their process can be changed to require entry of a PON. Eschelon has submitted CR #PC102901-1 requesting this process change. - Anne will talk with the process specialist for Loss and Completions Reporting to request that existing procedures and CLEC training be updated to include information about Qwest Retail “winback” orders appearing with no PON on Loss and Completions Reports.

B. 14 are orders that were initiated by Qwest Wholesale to record Trouble Isolation Charges that resulted from a repair call that was placed by Eschelon or by their end-user. It is Qwest’s policy to bill a Trouble Isolation Charge when a Qwest technician finds the problem to be on the end-user’s premise. Qwest Wholesale initiates orders to record these charges and stores the Account Number in the PON field since the SOPs require PON and no PON is available. These orders appear on the Completions Reports for the CLEC that “owns” the service to notify them of the impact to their business. Qwest Actions: - Anne will talk with the process specialist for CLEC Trouble Reporting to gather information about their process for recording Trouble Isolation Charges and will determine if their process can be changed to enter “TIC” as the PON. If this change is feasible and if all CLECs agree to it, Anne will create a UR to initiate a system change in the system that generates these orders. - Anne will talk with the process specialist for CLEC Trouble Reporting to request that existing procedures and CLEC training be updated to include information about orders initiated by Qwest to record Trouble Isolation Charges. - Anne will talk with the process specialist for Loss and Completions Reporting to request that existing procedures and CLEC training be updated to include information about Qwest orders for Trouble Isolation Charges appearing with an Account Number as the PON on Completions Reports.

C. 3 are “F” orders without PONs. “F” orders are one component of a transfer order. Transfer orders are comprised of a “T” order (identifying the transfer to information) and an “F” order (identifying the transfer from information). These transfer orders were submitted by Eschelon and processed by the Flow through processor which stores the PON on the “T” order but not on the “F” order. Qwest Actions: - Anne wrote a UR to initiate a system change in the Flow through processor to record the PON on the “F” order.

D. 17 are orders that were submitted by Eschelon and manually entered without PONs into the Western region SOP by Qwest Service Delivery Coordinators. The SOPs in the Eastern and Central regions include an edit to require PON on wholesale orders (RCID or ZCID is present) with inward activity. The Western region SOP does not include this edit. Since the SOP did not require PON, Service Delivery Coordinators incorrectly omitted the PON when entering these orders into the SOP. Qwest Actions: - Anne wrote a UR to initiate a system change to include an edit to require PON on wholesale orders with inward activity in the Western region SOP.

E. 13 are orders that were submitted by Eschelon and manually entered with inaccurate PONs into the Eastern and Central region SOPs by Qwest Service Delivery Coordinators. The SOPs in the Eastern and Central regions include an edit to require PON on wholesale orders (RCID or ZCID is present) with inward activity. Service Delivery Coordinators incorrectly entered an inaccurate value for the PON when entering these orders into the SOP. Qwest Actions: -On 9/21/01 Qwest distributed internally an MCC to re-emphasize the importance of the PON entered on the service order matching the PON on the LSR. The topic heading of the MCC was “Order Writing” and the heading stated “It is extremely important that the PON information entered on the service order matches the PON on the LSR.” This action was taken as result of research performed by Qwest in response to a separate CLEC inquiry relating to inaccurate PONs on Loss and Completions Reports. -Anne will notify the team leaders in the wholesale service centers that there are occurrences of inaccurate PONs on service orders and will request that they ensure that their teams are entering PONs correctly.

F. 12 are record orders that were initiated by Qwest Wholesale and do not include PONs. Record orders may be initiated by a CLEC or by Qwest Wholesale to correct system records. The SOPs do not require PON on record orders. Qwest Actions: -Anne will talk with the process specialist for record orders to gather information about their process for generating record orders and will determine if their process can be changed to enter “RECCOR” as the PON. If this change is feasible and if all CLECs agree to it, Anne will issue an MCC internally to implement the process change. -Anne will talk with the process specialist for Loss and Completions Reporting to request that existing procedures and CLEC training be updated to include information about record orders appearing with no PON on Completions Reports.

G. 2 are disconnect orders submitted by Eschelon and do not include PONs. The SOPs do not require PON on disconnect orders. Qwest Actions: -Anne will write a UR to initiate a system change to include an edit to require PON on wholesale disconnect orders in all regional SOPs. -Anne will talk with the process specialist for Loss and Completions Reporting to request that existing procedures and CLEC training be updated to include information about disconnect orders appearing with no PON on Completions Reports.

Attachment: The spreadsheet titled “Qwest Research on Orders with Missing PONs” cross references the 118 orders included on Eschelon’s spreadsheet of orders with missing PONs to the order writing scenario detailed above that resulted in the missing or inaccurate PON data on the Loss and Completions Reports.


CenturyLink Response

January 10, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc.

CC: Mark Coyne Sue Burson Carolyn Brown John Gallegos Connie Winston

This letter is in response to your CLEC Change Request Form, number PC102901-1 dated 10/29/01 Qwest to include PON on Qwest Winback Orders.

REQUEST: Currently, when Qwest wins-back a customer from Eschelon and an order is issued on an Eschelon account Qwest does not enter a PON. When Qwest does not enter a PON on an order then the Loss and Completion Report does not include a PON. Eschelon asks Qwest to develop, document, distribute and train an adhered to process to use a PON on all orders issued on Eschelon accounts.

RESPONSE: Qwest understands the difficulty the CLECs currently face when no PON is entered on the Loss & Completion Report for Qwest win-backs. To resolve this situation Qwest has initiated a systems related project that will ensure the PON field on the Loss & Completion Report is populated for Qwest win-backs.

Qwest has completed a systems change request on the behalf of Eschelon and resources have been assigned. The target implementation date for this project is in the second quarter, 2002. Qwest will provide a commitment date for implementation at the February CMP meeting.

Sincerely,

Anne Robberson Senior Process Analyst

Curt Anderson Project Manager


Open Product/Process CR PC120301-2 Detail

 
Title: Develop, distribute and train an adhered to process to provide CLECs with final APOT information at least 15 days before RFS.
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-2 Denied
2/20/2002
Ordering, Maintenance/Repair, Provisioning Collocation
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Mohr, Bob
Director:
CR PM:

Description Of Change

Qwest does not provide a CLEC with final APOTs until on or after the collocation ready for service (RFS) date. On that date, CLEC is required to pay all remaining nonrecurring charges and begin paying recurring charges for the collocation space. Yet, the collocation space is not functional because the associated UNEs, transport services and CLEC to CLEC routing cannot be ordered with any certainty until after the final APOT information is made available to CLEC. While Qwest will allow CLECS to place orders based upon preliminary APOT information provided before the RFS date, this does not guarantee that CLEC can utilize its space on the RFS date. If Qwest determines that the final APOT is different from the preliminary APOT, CLEC is required to submit a supplement to its service order, thereby delaying delivery of UNEs, transport and CLEC to CLEC routing. Eschelon asks Qwest to develop, distribute and train an adhered to process to provide CLECs with final APOT information at least 15 days before RFS so that CLECs can place orders in a time frame that enables them to actually utilize their collocation space on the RFS date. Eschelon needs to obtain the Final APOT information as soon as possible, because as the example noted below indicates, receiving the Final APOT information is by no means a guarantee that the information is correct. Correcting APOT issues takes time and coordination, which, if handled in the early stages of the order, can be resolved without affecting the established RFS date generated by Qwest and expected by Eschelon/Eschelon customers. Example: On one of Eschelon's ICDF, Eschelon made Final Payment on 8/23/01 (Final APOT expected on/about 8/24/01). Eschelon received Final APOT on 9/14/01 (22 days after Wire Transfer). Before the 9/14/01 date, Qwest revised the APOT information for this specific ICDF twice before it sent the Final/Corrected APOT information.


Status History

11/30/01 - CR received from Eschelon.

12/03/01 - E-Mail Acknowledgement issued to Eschelon Telecommunications

12/04/01 - CR posted to Qwest Wholesale Markets CMP Web page

12/07/01 - Eschelon contacted to schedule clarification call.

12/12/01 - CMP Meeting - Eschelon presented CR to CLEC Community.

12/14/01 - Clarification call conducted with Eschelon. Meeting minutes transmitted to Eschelon.

01/16/02 - CMP Meeting - Qwest conducted CLEC community clarification discussion. Eschelon indicated the need for advanced final APOT information in order to provision customers in advance of the ready for service (RFS) date. Qwest indicated that provisioning can be performed with advance preliminary APOT information. CLEC community agreed to change CR Status to "Evaluation."

02/08/02 - Qwest "Draft" response (dated 02/08/02) transmitted to submitting CLEC and posted in CMP data base.

02/20/02 - CMP Meeting - Qwest presented the "Draft" response. CR status changed to "Denied." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/22/02 - Qwest "Formal" response (dated 02/08/02) posted in CMP data base.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

2:00 p.m. (MDT) / Friday 14th December 2001 Conference Call TEL: 877.564.8688 CODE: 6265401 PC120301-2 "Develop, distribute and train an adhered to process to provide CLECs with final APOT information at least 15 days before RFS" Clarification Meeting

Kathleen Stichter, Eschelon Renee Lernes, Eschelon Karen Kraas, Qwest Laurel Burke, Qwest Barry Orrel, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Eschelon presented the CR. Eschelon requested that Qwest provide final Alternate Point of Termination (APOT) 15 day prior to the collocation Ready for Service (RFS) date (additional detail in CR). This was requested in order to allow the CLEC to conduct provisioning on advance of the RFS date & provide customer service on the RFS date.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} “Collocation” confirmed as appropriate. “Physical” & “ICDF Collocation” boxes under “Collocation” identified during conference call.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} N/A Qwest & Eschelon confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the January 2002 Monthly P&P CMP Meeting, a CLEC community clarification session will be conducted with Qwest providing potential options for addressing the CR.

6.0 Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} N/A PC120301-3.


CenturyLink Response

February 8, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc

SUBJECT: Qwest Change Request Response - CR PC 120301-02 Develop, distribute and train and adhered to process to provide CLECs with final APOT information at least 15 days before RFS

This letter responds to your CLEC Change Request Form, number PC120301-2 dated November 30, 2001 - Develop, distribute and train an adhered to process to provide CLECs with final APOT information at least 15 days before RFS. Eschelon requested this change so that "CLECs can place orders in a timeframe that enables them to actually utilize their collocation space on the RFS date." The change request provided one example of final APOT information being made available by Qwest days after the payment.

Qwest distributes the preliminary Alternate Point of Termination (APOT) fifteen (15) days prior to the Ready for Service (RFS) date. Final APOT is provided to the CLEC customer on the RFS date, provided the final 50% payment is received in full. The CLEC may then use the preliminary APOT to place service orders. The ordering process does not differ for a preliminary or a final APOT.

[Note: The order may not be turned up prior to the collocation RFS date, and receipt of final payment for the collocation must be received. When the orders are placed within the provisioning timeframe for the service, such service may be utilized and available to the CLEC on the date of the collocation RFS.]

During on-site completion of actual install work there may be changes to the engineering design work package or actual cables and blocks. Therefore, Qwest needs to continue to provide preliminary APOT 15 days prior to RFS with final APOT delivered on RFS and receipt of full payment.

Eschelon’s example dealt with an Interconnection Distribution Frame (ICDF) collocation. They noted their final APOT was provided several weeks following the final payment. During the walk-through with the State Interconnect Manager, discrepancies were noted that required engineering changes. Those changes were implemented and a revised final APOT provided to the customer at that time. However, the final payment was received prior to this implementation. Since work on the discrepancies was progressing, the final APOT was held until that work completed.

Sample data supports the decision not provide a final APOT 15 days prior to RFS. Forty (40) jobs were completed in 2001 for Eschelon. Seven and a half percent (7.5%) of APOT data were changed between the time of issuance of the preliminary APOT and tender of the final APOT. Also, 55% of the 40 jobs completed significantly ahead of the RFS date such that only a final APOT was issued enabling Eschelon to order services and provide their customers with service on or before the scheduled RFS date.

Sincerely,

Robert Mohr Product Manager Qwest

Cc: William Campbell, Qwest


Open Product/Process CR PC120301-3 Detail

 
Title: Implement an adhered to process to provide CLECs with accurate APOT information.
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-3 Completed
4/17/2002
Ordering, Maintenance/Repair Collocation
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Burke, Laurel
Director:
CR PM:

Description Of Change

Qwest provides inaccurate APOT information that prevents CLEC from providing service to its customers until the problems are resolved. This happens on approximately ten percent of Eschelon’s orders. Eschelon asks Qwest to implement a process and procedure for accurate APOT numbering so that CLECs can be assured that they will be able to provide service without delay to their customers. The process and procedure should include a requirement that Qwest personnel validate APOTs as they are entered into TIRKS.

Example #1 (Labeling of terminations in the CO(s) does not match the APOT information). A DS1 order could not be turned up due to incorrect labeling at the CLEC DS1 Spot Frame. APOT information indicated pairs 1-56 belonging to Eschelon, however, Qwest labeling at the Central Office indicated Pairs 1-28 + 33-60 belonging to Eschelon. Eschelon submitted the pending T1 order with APOT 29 and the order was accepted, indicating a labeling error at the Central Office. Errors such as this confuse the Eschelon Operations group and ultimately cause delays until the labeling issue is resolved/confirmed.

Example #2 (Information on Final APOT sheets sent to Eschelon does not match information loaded in TIRKS/IMA). Eschelon could not process DS0 orders due to incorrect information listed on the Final APOT sheet for a collocation. Eschelon submitted orders under one DS0 Cable name (as indicated on the Final APOT sheet). Qwest database was loaded with another DS0 Cable name. Consequently, Qwest was not recognizing orders issued with the DS0 Cable name identifier as the information did not exist in Qwest's systems. Eschelon helped to resolve the matter by sending its own technicians to the Central Office to verify the labeling of the DS0 Blocks. Eschelon discovered that Qwest labeled the APOT information on the Vertical Blocks differently then indicated on the APOT sheet. Qwest subsequently issued a corrected APOT sheet, two days after the problem was first discovered.

Example #3 (Information on Final APOT sheets sent to Eschelon does not match information loaded in TIRKS/IMA). Qwest rejected orders for an Eschelon Collocation due to what was perceived as an incorrect CLLI Code. Qwest informed the Eschelon Provisioning Group that the CLLI Code Eschelon used was incorrect. Qwest records indicated a different CLLI Code and would not process orders despite the fact that Eschelon used the CLLI Code identified on the Fianl APOT sheet on its orders. A service manager at Qwest helped resolve the issue and explained that the problem was due to internal miscommunication within Order Validation.


Status History

11/30/01 - CR received from Eschelon.

12/03/01 - E-Mail Acknowledgement issued to Eschelon Telecommunications

12/04/01 - CR posted to Qwest Wholesale Markets CMP Web page

12/07/01 - Eschelon contacted to schedule clarification call.

12/12/01 - CMP Meeting - Eschelon presented CR to CLEC Community.

12/14/01 - Clarification call conducted with Eschelon. Meeting minutes transmitted to Eschelon.

01/11/02 - Qwest draft response transmitted to Eschelon.

01/16/02 - CMP Meeting - Laurel Burke (SME) presented Qwest response. SME indicated that process improvements have been implemented since example provided by Eschelon occurred. Explanation provided regarding three (3) examples provided. CLEC community agreed to move CR Status to "CLEC Test." Michael Zulevic, COVAD provided list of potential issues to Qwest regarding CR via e-mail. Qwest to review.

02/11/02 - Qwest "Formal" response (dated 01/11/02) posted in CMP data base.

02/15/02 - Qwest "Formal" response (dated 01/11/02) transmitted to CLEC community.

02/20/02 - CMP Meeting - Eschelon internally waiting on any examples to conduct test of Qwest response. CR remains in "CLEC Test" status. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/20/02 - CMP Meeting - Eschelon requested that the CR remain in CLEC Test for another month.

04/17/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR could be closed.


Project Meetings

2:30 p.m. (MDT) / Friday 14th December 2001 Conference Call TEL: 877.564.8688 CODE: 6265401 PC120301-3 "Implement an adhered to process to provide CLECs with accurate APOT information" Clarification Meeting

Kathleen Stichter, Eschelon Renee Lernes, Eschelon Karen Kraas, Qwest Laurel Burke, Qwest Barry Orrel, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Eschelon presented the CR. Eschelon requested that Qwest provide accurate final Alternate Point of Termination (APOT) data to match TIRKS/IMA databases for correct provisioning of circuits (additional detail in CR). This was requested in order to allow the CLEC to conduct provisioning on advance of the RFS date & provide customer service on the RFS date.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} “Collocation” confirmed as appropriate. “Physical” & “ICDF Collocation” boxes under “Collocation” identified during conference call.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Eschelon confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the January 2002 Monthly P&P CMP Meeting, a CLEC community clarification session will be conducted with Qwest providing potential options for addressing the CR.

6.0 Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} N/A PC120301-2.


CenturyLink Response

January 11, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc

CC: Mary Retka, Qwest

This letter responds to your CLEC Change Request Form, number PC120301-3 dated November 30, 2001 – Implement an adhered to process to provde CLECs with accurate APOT information. Specifically, Eschelon asked Qwest to implement a process and procedure for accurate APOT numbering so that CLECs can be assured that they will be able to provide service without delay to their customers. The change request provided three examples of APOT information provided by Qwest and suggested that the process should include a requirement that Qwest personnel validate APOTs as they are entered into TIRKS.

Qwest previously committed and continues to commit to providing accurate Alternate Point of Termination (APOT) information. We also continue to commit to providing timely resolution of issues relating to information contained on the APOT. To this end, we revised and have implemented several internal processes to verify the accuracy of the APOT. Applicable process changes are addressed below in the context of the examples provided within the Change Request (CR).

- Example 1 describes a situation in which labeling of terminations in the Central Office did not match the APOT information. This job completed in April 2001 and the call to the APOT hotline occurred in November, seven months after the "Ready For Service" (RFS) date. Our investigation revealed that the State Interconnect Manager (SICM) and Eschelon representatives performed a walk through on this job; the APOT contained correct cable count pairs and matched the field cable count; the SICM identified where to connect their side of the terminations. The terminations were labeled correctly and TIRKS also reflects the correct cable count. However, the numbering associated with the jack locations did not match the locations identified on the APOT; for jobs other than ICDF collocations, the jack numbers do not appear on the APOT. Jack locations do not need to match the cable count numbers and in this case, the difference is apparently what caused confusion. This issue was resolved the business day after a call to the APOT hotline. In late June, early July 2001, CPMC personnel reevaluated their quality processes and implemented safeguards to ensure that correct information appears on the APOT; specifically, the state Project Manager is required to confirm that the APOT data matches TIRKS and that the DWP also matches the APOT. A process document (update issued 11/30/2001) reiterates that the Engineer must ensure that the actual installation is accurately reflected in both the APOT and the DWP. Additionally, Engineering revised its job aid on 8/28/2001 describing ICDF collocation engineering and its unique APOT in detail.

- Example 2 involved the inability of Eschelon to process DS0 orders based on incorrect TIRKS information. The APOT resulted from a job that completed in April but no call was made to the APOT hotline. There was a cable name error on the APOT; instead of an "s" the cable name contained a "d." The field and TIRKS correctly showed the "s," but there was a typographical error on the APOT. A revised final APOT was provided to Eschelon the morning of the second business day following the identification of the error to Collocation Project Management Center (CPMC) State Project Manager. Internal processes (updated 9/27/2001 and 11/30/2001) require the Engineer to verify the field installation information against the APOT, TIRKS, the design work package (DWP) as well as check any other affected engineering documents/systems for consistency. As changes are made and needs clarified (from sources such as the APOT hotline), engineering staff review and update the applicable job aids in addition to providing periodic training on issues, including APOT related ones, during monthly staff meetings. As indicated above, the CPMC State Project Manager is also required to manually check and validate that the APOT matches the parameters contained in the DWP. The CPMC audits compliance with this process on a monthly basis.

- Example 3 involved a rejection of orders because the CLLI code appeared to be incorrect on the final APOT. Upon notification of a building addition completion, Eschelon submitted an application for collocation space in the central office and was placed in the central office annex for which the addition had just been completed and for which a new CLLI had been assigned. The service center did not recognize the CLLI code associated with the collocation job (completed in April 2001) because it did not match the address or name of the central office on the order - a new name and physical address had been assigned to the building addition. However, the APOT, DWP and TIRKS were correct for the location of the collocation. The Account Service Manager was contacted and the situation explained sufficiently to allow the orders to process. Some unique situations will continue to arise and need to be addressed individually.

In summary, Qwest understands the concerns that result from order rejection, and has instituted the following measures to provide accurate APOT information:

- Internal process improvements (discussed above and) implemented by the Engineering, CPMC, and TIRKS organizations (effective July 2001);

- Qwest collocation engineering managers regularly provide training on and review of APOT job aids; and

- Continued operation of the "APOT Hotline" (refer to CR 5608156) to quickly and efficiently address any APOT discrepancies that may arise.

Qwest will continue to work with the CLEC community regarding APOT accuracy related issues.

Sincerely,

Laurel L. Burke Staff Advocate, Policy & Law Technical Regulatory Interconnection Planning


Open Product/Process CR PC120301-4 Detail

 
Title: Implement a process to insure Qwest adheres to ANSI Standard T1.102 and ANSI T1.104 for setting signal and loss level standards for DS3 cable length limitations.
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-4 Completed
4/17/2002
Ordering, Maintenance/Repair, Provisioning Collocation
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wycoff, William
Director:
CR PM:

Description Of Change

Qwest currently states that it will meet ANSI standards without defining how it will meet the standards. Qwest should commit to engineering a complete DS3 Circuit when the request for a CLEC to CLEC cross-connect is made through the Qwest ICDF. Eschelon asks that Qwest adhere to ANSI Standard T1.102 and ANSI T1.104 with the additional lineal footage, ICDF connections, connectors and DSX interfaces taken into consideration. Without such a standard, CLECs are not assured a clear DS3 signal. If it is discovered that a signal level of no less than -4.7 dBm is present on a single unbalanced coaxial line (20 Ga/26 Ga), Qwest will notify the CLEC that amplification is required and will appropriately amplify the signal to meet ANSI Standards (as identified in ANSI Standard T1.102 and ANSI T1.104). Additionally, Eschelon requires that the two-unbalanced coaxial cable paths are within ± .5 dBm of one another. Otherwise, corrective action is necessary to meet this requirement.

Example #1 (Qwest needs to engineer the entire path (CLEC to CLEC) when the cross-connect is made through the Qwest ICDF). A CLEC to CLEC cross-connect was made with a third party in a Central Office. When the entire lineal footage of the DS3 Circuit was taken into consideration, the DS3 signal was not within ANSI loss level standards. Qwest contends that it will engineer the DS3 cable/signal from the Qwest ICDF to each separate Co-Provider but that it is not responsible for the complete circuit, although all elements involved. (i.e. BNC connectors, ICDF Cross-connect points, and DSX interfaces) contribute significantly to overall signal loss. Since Qwest provisions all three segments of the circuit, Qwest must provision the complete circuit in such a way that meets the ANSI standard.


Status History

11/30/01 - CR received from Eschelon.

12/03/01 - E-Mail Acknowledgement issued to Eschelon Telecommunications

12/04/01 - CR posted to Qwest Wholesale Markets CMP Web page

12/07/01 - Eschelon contacted to schedule clarification call.

12/12/01 - CMP Meeting - Eschelon presented CR to CLEC Community.

12/14/01 - Clarification call conducted with Eschelon. Meeting minutes transmitted to Eschelon.

01/16/02 - CMP Meeting - Qwest conducted CLEC community clarification discussion. Eschelon requested that Qwest contact Paul Hauser, Eschelon to discuss additional technical issues regarding the CR. Eschelon asked that Michael Zulevic, COVAD be invited to the conference call. CLEC community agreed to change CR Status to "Evaluation."

01/18/02 - Follow-up clarification call conducted with Eschelon and Covad in attendance; minutes transmited to Eschelon and Covad.

02/08/02 - Qwest draft response (dated 02/06/02) posted in CMP database & transmitted to Eschelon.

02/20/02 - CMP Meeting - Qwest presented the "Draft" response. CR status changed to "CLCE Test." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/22/02 - Qwest "Formal" response (dated 02/06/02) posted in CMP data base.

03/20/02 - CMP Meeting - Eschelon requested that the CR remain in CLEC Test for another month until the have a chance to perform a test.

04/17/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR could be closed.


Project Meetings

8:00 p.m. (MDT) / Friday 18th January 2002 Conference Call TEL: 877.564.8688 CODE: 6265401 PC120301-4 "Implement a process to insure Qwest adheres to ANSI Standard T1.102 and ANSI T1.104 for setting signal and loss level standards for DS3 cable length limitations." [Follow-up]

Kathleen Stichter, Eschelon Paul Hanser, Eschelon Michael Zulevic, Covad Bill Wycoff, Qwest Jeff Ferra, Qwest Laurel Burke, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Clarification was obtained from Eschelon & Covad for the subject CR. The following items were discussed: 1) Paul Hanser, Eschelon identified two (2) types of CLEC to CLEC connections in Qwest CO facilities: 1) direct connection (i.e., no routing through Qwest ICDF; and 2) connection through Qwest ICDF(s). Direct connections, in general, exhibit fewer problems and mainly concern cable lengths and re-generation concerns. Connections routed through a Qwest ICDF(s) usually involve larger Qwest CO facilities that may involve multiple floors and require more detailed assessments of circuit cable lengths, regeneration, ICDF connection losses, and other connector losses (i.e., BNC). Eschelon expressed concern that proper engineering and testing of the end to end portion of the Qwest furnished curcuit (i.e., cabling, regeneration (if required), all related connections) need to be conducted properly prior to "throwing the cables over the fence into the co-location areas." 2) Michael Zulevic, Covad concurred with Eschelon and also requested cable continuity testing and documentation for the Qwest provided portion of the circuit at the conclusion of the construction phase; along with possible collaborative testing during the test & turn-up phase. 3) William Wycoff, Qwest asked Eschelon what signal levels are being transmitted and received from their co-location areas. Paul Hanser, Eschelon indicated that maximum transmit and minimum receive are indicative of signal levels.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} N/A. Discussed in previous clarification meeting.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} N/A. Discussed in previous clarification meeting.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to generate draft response for CMP Monthly Product & Process Meeting.

-

1:30 p.m. (MDT) / Friday 14th December 2001 Conference Call TEL: 877.564.8688 CODE: 6265401 PC120301-4 "Implement a process to insure Qwest adheres to ANSI Standard T1.102 and ANSI T1.104 for setting signal and loss level standards for DS3 cable length limitations" Clarification Meeting

Kathleen Stichter, Eschelon Renee Lernes, Eschelon Bill Kent, Eschelon Bill Wycoff, Qwest Jeff Ferra, Qwest Laurel Burke, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Eschelon presented the CR. Eschelon requested that the completed circuit provided by Qwest for CLEC to CLEC cross connect through a Qwest Interconnect Distribution Frame (ICDF) provide a signal level of no less than –4.7 dBm (additional detail in CR). Qwest is responsible for completing the cross connect circuit.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} “Collocation” confirmed as appropriate. “Physical” & “ICDF Collocation” boxes under “Collocation” identified during conference call.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Eschelon confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the January 2002 Monthly P&P CMP Meeting , a CLEC community clarification session will be conducted with Qwest providing potential options for addressing the CR.

6.0 Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts} None.


CenturyLink Response

February 6, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc

SUBJECT: Qwest Change Request Response - Number PC120301-4 (December 3, 2001) – Implement a process to insure Qwest adheres to ANSI Standard T1.102 and ANSI T1.104 for setting signal and loss level standards for DS3 cable length limitations.

Qwest has responsibility to engineer network elements within its Central Offices (CO) in an efficient manner. Qwest has engineering criteria establishing DSX-N cross-connect fields that are in compliance with ANSI Standard T1.102 for setting signal and loss levels using cable length limitations, signal source level control, and signal regeneration. It is unclear how ANSI Standard T1.104 relates to the signal level question.

To minimize equipment, the ICDF is not engineered as a DSX-N level point. According to Technical Publication 77386 on Interconnection and Collocation, Chapters 5 and 15, the engineering requirement is to design through the ICDF to a DSX-N point when accessing unbundled offerings such as Unbundled Loops, Unbundled Dedicated Interoffice Transport, etc. This principle was established circa 1996 in FCC Docket 93-192.

The CLEC-to-CLEC Cross-Connection (COCC-X) offering is defined as the CLEC’s capability to order a cross-connection from its Collocation in a Qwest Premises to its non-ajacent Collocation space or to another CLEC’s Collocation within the same Qwest Premises at the Interconnection Distribution Frame (ICDF). This is accomplished by the use of the CLEC’s Connecting Facilty Assignment (CFA) terminations residing at the same ICDF and at the same service rate level.

Qwest is providing clarification for the following activities to address this request:

- CLEC ordering procedure for cross-connection; - Qwest engineering data exchange with the requesting CLEC(s) for the cross-connection; - CLEC to CLEC cross connection within the Qwest Central Office (CO); - ICDF connections, and regeneration installation; and - Verification testing.

CLEC Ordering Procedure

CLEC to CLEC cross-connections are ordered through the Qwest EXACT-PC system using the Access Service Request (ASR) form. This form is used for ordering Access and Local Network Interconnection Services. Qwest processes the ASR and determines a ready for service (RFS) date for the connection.

The requesting CLEC(s) is required to assess the need for signal regeneration prior to submittal of the completed ASR form. An engineering data exchange can be arranged through the Qwest Wholesale Collocation Project Manager (http://www.uswest.com/wholesale/clecs/escalations.html)

Qwest Engineering Data exchange with requesting CLEC(s)

The requesting CLEC(s) are required to know the cable types and lengths from their equipment to the ICDF(s) in order to assess the need for signal regeneration. The need for regeneration may arise when the distances between the CLEC’s collocation equipment exceeds twice the cable length limitation criteria (table) when connected through the ICDF. The total cable length limitation from signal source to sink, without a DSX-N point is nominally, two times the shown length.

Qwest will provide the requesting CLEC(s) the type and length of cable between their physical space and the ICDF. Each CLEC uses this information to design the span between their equipment. The design is done to determine any need for regeneration. Regeneration is typically at the ICDF.

[Table in Supplemental Information]

Given the probability of having cable lengths that total less than the maximums, it has been and is the CLEC’s responsibility to set any transmit attenuators in their equipment. Given the possibility that total cable lengths from the Collocation spaces through the ICDF are longer than the table allows, there is the opportunity for a CLEC to request regeneration by using a specific Network Channel Interface (NCI) code on their order. The NCI is chosen from Table 6-5 of Tech Pub 77386 using one that calls for regeneration. CLEC to CLEC cross connects occur between two CLECs within a Qwest CO and use jumper cables at the ICDF to complete the link. There is no assured DSX-N level point in the circuit.

Figure A below illustrates the situation where there is a single, ICDF cross-connect to complete a CLEC-to CLEC circuit that needs a regenerator. There is no DSX-N level point assured in this circuit.

[Figure A in Supplemental Information]

Figure A: Single ICDF Connection with Regeneration

ICDF connections and regeneration installation

Qwest, following receipt of the ASR will perform ICDF connections and regeneration functions. Equipment additions for regeneration (if no spares are available) will be initiated. Qwest completes these activities and conducts verification testing.

Verification testing

Verification testing of the cross-connection will be conducted to assure compliance with the ASR. Cooperative testing on circuits will be conducted with Qwest and requesting CLEC(s) technicians.

Qwest will coordinate with the requesting CLEC and schedule the testing of the completed cabling, ICDF connections and regeneration. CLEC(s) will be responsible to terminate cabling into their respective collocation equipment prior to the testing effort.

Although circuit testing is the responsibility of the CLECs, Qwest will provide technician support of CLEC to CLEC circuit testing efforts and provide trouble-shooting support, as necessary to successfully complete an ASR. Such testing shall confirm that ASR ordered circuits perform to service objectives in ANSI Standard T1.510, Network Performance Parameters for Dedicated Digital Services for Rates Up to and Including DS3. Clauses 8.2 and 8.3 describe DS1 and DS3 testing, respectively.

Sincerely,

William R. Wycoff Services Planning Qwest

CC: Bill Campbell, Qwest Barry Orrel, Qwest Gale Perko, Qwest Mary Retka, Qwest


Open Product/Process CR PC120301-5 Detail

 
Title: Process where once an escalation ticket is opened and accepted that the issue stays with the CSIE group until the escalation is completed.
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-5 Completed
3/20/2002
Provisioning LNP, Resale, Unbundled Loop, UNE
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Thacker, Michelle
Director:
CR PM:

Description Of Change

Eschelon asks Qwest to develop and implement a process that once an escalation ticket is opened and accepted that it is not closed and stays with the CSIE group until the escalation issue is completed even if the Qwest Service Order completes during the course of the escalation. Eschelon experienced a customer who was out of service at 2pm on the DD of an order. Eschelon escalated and Qwest CSIE group opened and accepted the escalation. The Qwest CSIE group worked the ticket without resolution until the Service Order was completed. Qwest then closed the ticket without resolution and called Eschelon advising us to call the LNP repair desk.


Status History

11/30/01 - CR received from Eschelon.

12/03/01 - E-Mail Acknowledgement issued to Eschelon Telecommunications

12/04/01 - CR posted to Qwest Wholesale Markets CMP Web page

12/07/01 - Eschelon contacted to schedule clarification call.

12/10/01 - Clarification call scheduled for 18-Dec-01 due to conflicts with monthly Product & Process and Systems meetings (i.e., 12- & 13-Dec-01) & availablity of supporting technical staff to attend conference call.

12/12/01 - CMP Meeting - Eschelon presented CR to CLEC Community.

12/18/01 - Clarification Meeting conducted with Eschelon.

12/19/01 - Clarification Meeting Minutes transmitted to Eschelon.

01/08/02 - Qwest draft response (dated 01/04/02) posted in CMP database & transmitted to Eschelon.

01/16/02 - CMP Meeting - Michelle Thacker (SME) presented Qwest response. SME indicated that the example Eschelon provided was a one-time occurence and that training has been conducted with the CSIE group to properly handle escalation tickets through completion. CLEC community agreed to change CR Status to "CLEC Test." CLEC community requested modification to PCAT language to be consistent with Qwest response. PCAT language modification is being persued by Qwest.

02/14/02 - Qwest "Formal" response (dated 01/04/02) posted in CMP data base.

02/15/02 - Qwest "Formal" response (dated 01/04/02) transmitted to CLEC community.

02/20/02 - CMP Meeting - Qwest provided status update. CR remains in "CLEC Test." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/28/02 - PCAT updated with language that is consistent with this CR response URL: http://www.qwest.com/wholesale/clecs/maintenance.html

03/20/02 - March CMP Meeting: CLECs agreed to close CR. CR Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

02/28/02 - PCAT updated with language that is consistent with this CR response URL: http://www.qwest.com/wholesale/clecs/maintenance.html

Recent Service Request Activity If your service request was completed within the past 72 business hours contact Qwest's Interconnect Service Center (ISC) at 888-796-9087 for assistance. After researching the issue, the Customer Service Inquiry and Education Center (CSIE) will contact you regarding resolution of your issue.

3:30 p.m. (MDT) / Tuesday 18th December 2001 Conference Call TEL: 877.554.8688 CODE: 3269208 PC120301-5 “Process where once an escalation ticket is open and accepted that the issue stays with the CSIE group until the escalation is completed.” Name/Company:

Kathleen Stichter, Eschelon Bonnie Johnson, Eschelon Michelle Thacker, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Eschelon presented the CR. Eschelon requested that the process be confirmed as to handling of escalation tickets by CSIE. Eschelon expressed concern that once a trouble ticket is open, either the CSIE or repair group should handle through completion. Qwest confirmed with Eschelon that the ticket issue was a one-time occurrence.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Appropriate products & areas identified in CR.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Eschelon confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the January 2002 Monthly P&P CMP Meeting, Qwest will provide an explanation of the escalation ticket occurrence; and provide clarification to the procedure to be followed by Qwest CSIE and Repair, as required.


CenturyLink Response

January 4, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc.

CC: Peter Wirth, Chris Siewert

This letter is in response to your CLEC Change Request Form, number PC120301-5 dated 11/30/01 - Process where once an escalation ticket is opened and accepted that the issue stays with the Customer Service Inquiry and Education (CSIE) group until the escalation is completed.

Qwest currently has a repair referral process in place, which provides for CSIE responsibility of a CLEC issue until resolution. The process provides procedures for handling an out of service condition when service order activity is involved. Your experience with the Qwest CSIE team was an isolated incident

The repair referral process addresses: review of the service order; matching service order entries against the CLEC issued LSR; issuing a service order to correct inaccurate entries on the service order if found; contacting internal departments for assistance; and follow up to ensure end user customer receives service, etc. The Qwest Service Delivery Coordinator (SDC) utilizes this process in processing escalation tickets.

I have confirmed with Chris Siewert - Team Leader Minneapolis CSIE, that process retraining occurred shortly after this incident for the entire CSIE team.

Sincerely,

Michelle Thacker Process Specialist


Open Product/Process CR PC122701-1 Detail

 
Title: Qwest to offer line conditioning to qualify a loop for Qwest resale DSL service.
CR Number Current Status
Date
Area Impacted Products Impacted

PC122701-1 Denied
3/20/2002
Pre-Ordering, Provisioning Resale, Other (DSL)
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Pennington, Freddie
Director:
CR PM:

Description Of Change

To provision DSL on a line, the line needs to meet certain qualifications. These qualifications include but are not limited to loop length, insertion loss, no bridge taps and no load coils. Currently a significant number of 1FB POTS lines ordered do not qualify for Qwest resale DSL. At this time Qwest does not offer line conditioning to qualify a line for Qwest resale DSL. Eschelon asks Qwest to offer line conditioning so more loops qualify for Qwest resale DSL.


Status History

12/27/01 - CR Submitted by Eschelon

12/27/01 - CR acknowledged by P&P CMP Manager

01/02/02 - Eschelon contacted to coordinate clarification call

01/09/02 - Clarification meeting held.

01/11/02 - Draft clarification meeting minutes issued to Eschelon

01/28/02 - E-mail from Eschelon with working example

02/20/02 - February CMP meeting: General clarification with CLEC community. CR status changed to "Evaluation" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

03/12/02 - Draft response dated 02/25/02 issued to Eschelon. CR Status changed to "Presented"

03/20/02 - March CMP Meeting: CR was denied. CR Status changed to "Denied." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be

posted on the CMP Web site

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status

03/21/02 - Formal response dated 02/25/02 posted to CMP database

03/22/02 - Formal response dated 02/25/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses


Project Meetings

01/28/02 E-mail from Eschelon with working example

Subject: CR PC122701-1 Resale DSL Conditioning Date: Mon, 28 Jan 2002 11:30:42 -0600 From: "Stichter, Kathleen L." To: tmead@qwest.com CC: "Johnson, Bonnie J." Todd, Here is an example of why Eschelon is requesting Conditioning on resale DSL. Eschelon sold a DSL to a customer. When we went to pre-qualify the results were, Loop does not qualify for Megabit Service: insertion loss is too high. The customer went to Qwest and ordered DSL through Qwest. When investigated we found that Qwest offered to provision a new line with DSL to see if the new line would qualify. The new line did qualify for DSL. Now the customer has 1 extra line that they do not need and will be removing. This could have been avoided if this CR were accepted. One of the existing lines could have been conditioned to handle the DSL. Please get this information to the Qwest SMEs assigned to this CR. Thanks

Clarification Meeting

2:00 p.m. (MST) / Wednesday 9th January 2002 PC 122701-1 Qwest to offer line conditioning to qualify a loop for Qwest resale DSL service

Attendees: Kathy Stichter / Eschelon Tina Shiller / Eschelon Todd Mead / Qwest Bob Shaheen / Qwest Nadine Jensen / Qwest

Review Requested (Description of) Change: - Kathy read out the description from the change request: "To provision DSL on a line, the line needs to meet certain qualifications. These qualifications include but are not limited to loop length, insertion loss, no bridge taps and no load coils. Currently a significant number of 1FB POTS lines ordered do not qualify for Qwest resale DSL. At this time Qwest does not offer line conditioning to qualify a line for Qwest resale DSL. Eschelon asks Qwest to offer line conditioning so more loops qualify for Qwest resale DSL." - Bob qualified that you can have bridge tap on a DSL line, it just causes a loss of signal strength - Kathy stated that if there is anything stopping DSL going on the line they want to be able to order line conditioning up front. - This request is for a product that currently does not exist. It is not just something not available for Resale.

Areas Impacted: Pre-Ordering, Provisioning

Products Impacted: Resale DSL

Confirm Right Personnel Involved: Freddi Pennington is the owner of this CR. Todd will inform Freddi.

Identify/Confirm CLEC’s Expectation: New process or product

Establish Action Plan: Eschelon may present this CR at the January CMP meeting (01/16/02). General Clarification by the entire CLEC community will take place at the February CMP meeting (02/20/02) and Qwest will provide a response at the March CMP meeting (03/20/02). Freddi 03/20/02


CenturyLink Response

February 25, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc. 720 2nd Avenue South, Suite 1200 Minneapolis, MN 55402

SUBJECT: Qwest’s Change Request Response - CR # PC122701-1 Resale DSL Conditioning

Eschelon requested that Qwest provide a DSL line conditioning service for resale.

Qwest DSL product management does not offer DSL line conditioning service and it is not available to retail end-user subscribers.

Qwest does not offer for resale a service that it does not provide its own retail end-user subscribers.

Sincerely,

Freddi Pennington Resale/PAL/UNE-P Group Manager Qwest

Cc: William Campbell, Director Structure & Loops, Qwest Jasmin Epsy, Senior Director Product Marketing, Qwest Teresa Taylor, Senior Vice President Product Management, Qwest


Open Product/Process CR PC122701-2 Detail

 
Title: Qwest to allow 1FB POTS and DSL on one LSR.
CR Number Current Status
Date
Area Impacted Products Impacted

PC122701-2 Denied
3/20/2002
Ordering, Provisioning Resale, UNE-P, Other (DSL)
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Pennington, Freddie
Director:
CR PM:

Description Of Change

Currently to order a new line with Qwest resale DSL, Eschelon needs to submit 2 LSRs. One LSR for the POTS line and a subsequent LSR for the DSL. When 2 LSRs are issued Qwest does not know that the POTS line will eventually become DSL so facilities to provide a DSL capable loop are not taken into consideration. If Qwest allowed Eschelon to issue 1 LSR for the 1FB POTS line and the DSL then Qwest could provision the loop with DSL capable facilities, if available. Eschelon asks Qwest to allow 1FB POTS and DSL on 1 LSR.


Status History

12/27/01 - CR Submitted by Eschelon

12/27/01 - CR acknowledged by P&P CMP Manager

01/02/02 - Eschelon contacted to coordinate clarification call

01/08/02 - Clarification meeting held.

01/09/02 - Draft clarification meeting minutes issued to Eschelon

02/20/02 - February CMP meeting: General clarification with CLEC community. CR status changed to "Evaluation" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

03/12/02 - Draft response dated 02/27/02 issued to Eschelon. CR Status changed to "Presented"

03/20/02 - March CMP Meeting: CR was denied. CR Status changed to "Denied." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be

posted on the CMP Web site

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status

03/21/02 - Formal response dated 02/27/02 posted to CMP database

03/22/02 - Formal response dated 02/27/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses


Project Meetings

Clarification Meeting

2:00 p.m. (MST) / Tuesday 8th January 2002 PC 122701-2 Qwest to allow 1FB POTS & DSL on one LSR

Attendees: Kathy Stichter / Eschelon Todd Mead / Qwest Jeff Cook / Qwest Brett Fesler / Qwest Nadine Jensen / Qwest Janean Van Dusen / Qwest

Review Requested (Description of) Change: Kathy read out the description from the change request: Currently to order a new line with Qwest resale DSL, Eschelon needs to submit 2 LSRs. One LSR for the POTS line and a subsequent LSR for the DSL. When 2 LSRs are issued Qwest does not know that the POTS line will eventually become DSL so facilities to provide a DSL capable loop are not taken into consideration. If Qwest allowed Eschelon to issue 1 LSR for the 1FB POTS line and the DSL then Qwest could provision the loop with DSL capable facilities, if available. Eschelon asks Qwest to allow 1FB POTS and DSL on 1 LSR. There were no questions from Qwest.

Areas Impacted: Ordering, Provisioning

Products Impacted: Resale, UNE-P, Other (DSL)

Nadine is the owner of this CR. Nadine agreed she is the right person to provide the response to this CR, with the assistance of the other Qwest people on the call.

Identify/Confirm CLEC’s Expectation: - Qwest to allow Eschelon to submit one LSR for both the 1FB POTS and the Qwest resale DSL. - If Qwest accepts this CR, then Eschelon expects to see the resulting process documented and the appropriate level of training given to Qwest personnel.

Establish Action Plan: Eschelon may present this CR at the January CMP meeting (01/16/02). General Clarification by the entire CLEC community will take place at the February CMP meeting (02/20/02) and Qwest will provide a response at the March CMP meeting (03/20/02).


CenturyLink Response

February 27, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc. 720 2nd Avenue South, Suite 1200 Minneapolis, MN 55402

SUBJECT: Qwest’s Change Request Response - CR # PC122701-2 Qwest to allow 1FB POTS and DSL on one LSR

The original request from Echelon is that Qwest accept a single LSR for both the local service line (POTS) and DSL service at the same time.

Upon clarification, Eschelon is now requesting that Qwest: - Manually analyze the available facilities at the location - Choose a facility that supports DSL (if available) - Deploy local service (POTS) on a line that will support DSL

Qwest does not offer this type of pre-analysis of a facilities to its retail end-user subscribers. Qwest currently uses a mechanized system that qualifies a facilities based on certain metrics and the facility must already be in place in order to see if it is engineered to support DSL service.

In order for Qwest to do the requested analysis upfront, Qwest would need to remove the order from the automatic facility assignment flow and manually assign facilities to the local service line (POTS). Qwest has made extensive investments in the loop qualification tool and process. Qwest has made the business decision not to manually assign POTS facilities in order to allow the addition of DSL for retail end-user subscribers. This service is not a retail service and is not available for resale.

Sincerely,

Freddi Pennington Resale/PAL/UNE-P Group Manager Qwest

Cc: William Campbell, Director Structure & Loops, Qwest Jasmin Epsy, Senior Director Product Marketing, Qwest Teresa Taylor, Senior Vice President Product Management, Qwest


Open Product/Process CR PC122801-1 Detail

 
Title: Qwest to document, distribute and train an adhered to process to unlock numbers for 911.
CR Number Current Status
Date
Area Impacted Products Impacted

PC122801-1 Completed
4/17/2002
Ordering 911, LNP
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Dubose, Lorna
Director:
CR PM:

Description Of Change

When a number moves from Qwest to Eschelon, Eschelon sends a migration notice to Qwest's 911 data base administrator, Intrado. Intrado migrates the number from Qwest to Eschelon and then applies the new record. However, before Intrado can apply Eschelon's new record, Qwest must first unlock the number in the Intrado 911 data base. When Qwest fails to unlock the number, Intrado sends an error message 755, to Eschelon stating that Qwest has not unlocked the number and they can not apply the new record. Intrado will attempt to apply the new record each day for 14 days and will send the error message 755, to Eschelon each day unless Qwest unlocks the number. At the end of the 14 days, Intrado stops its attempts to apply the new record and sends an error message 760. This is time consumming for Eschelon to continually check the error messages. It is also time consumming if Eschelon has to resend the migration notice, which occurs if Qwest fails to unlock the number within the first 14 days from when Eschelon sent the first notice to Intrado. Another potentially dangerous problem could occur if Qwest fails to unlock the number and the new record is not applied. If the customer moves during the conversion, the 911 data base will have the incorrect information, which could cause an emergency vehicle dispatched to the incorrect location.

Eschelon asks Qwest to document, distribute and train an adhered to process to unlock numbers from the 911 data base so Intrado can apply the new records sent to them by Eschelon. If a current process exists, Eschelon asks to see the process and asks Qwest to improve the process or ensure adherence to the process.


Status History

12/28/01 - CR Submitted by Eschelon.

12/28/01 - CR acknowledged by P/P CMP Manager.

01/03/02 - Eschelon contacted to coordinate available times for clarification call.

01/09/02 - Clarification Meeting conducted with Eschelon.

01/11/02 - Issued Clarification Meeting Minutes to Eschelon.

02/20/02 - CMP Meeting - CLEC Community Clarification held. It was agreed that the CR would move to Evaluation. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/06/02 - Issued Qwest's Draft Response dated March 6, 2002 to Eschelon.

03/20/02 - CMP Meeting - Qwest presented its Draft Response dated March 6, 2002. It was agreed that the CR could move to CLEC Test.

03/29/02- Formal response dated March 6, 2002 issued to CLECs. Notification CMPR.03.29.02.F.01246.Final_CR_Response.

04/17/02 - CMP Meeting - It was agreed that the CR could be closed.


Project Meetings

CLEC Change Request Clarification Meeting

Date: January 9, 2002, 12:00 (MT) Place: Conference Call Location: 877-564-8688 Subject: PC122801-1, Qwest to document, distribute and train an adhered to process to unlock numbers for 911

Attendees: Ric Martin, Qwest Lorna Dubose, Qwest Joan Wells, Qwest Kathy Stichter, Eschelon Amanda Owens, Eschelon

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Eschelon reviewed the requirements of their CR. Lorna asked if Eschelon had any performance measurements on the percentage of 755 Errors and 760 Cancellations they were getting. Eschelon advised that they didn’t have any measurements. Amanda indicated that they would only receive one 755 Error message and it would remain until the number was unlocked or it went to 760. They do not get continuous 755 Error messages for the same number. Amanda indicated that they started with many error messages from 2 years ago. They have reduced that number. She has been working with Qwest'’ 911 database manager and that has worked a little. She indicated that she had a recent e-mail from Intrado including a new 760 report. Amanda will send report to Lorna Dubose. The report indicated that there were other carriers on the report other than Qwest. The group was unsure who was responsible for the other carriers. Qwest will look into this. Joan indicated that Qwest had a recent clarification call on the process and indicated that it was working for the other CLECs. She explained that per commission ruling, Qwest is required to hold the order until 11:59 the next business day. Amanda indicated that they send their records to Intrado 2 days before the Due Date. This would explain why Eschelon would receive 755 Error notices, which would remain for 4 days. Eschelon stated that they understood that Intrado issued the database, but they thought Qwest owned the database. Qwest will advise if they own the 911 database and what the control is. Joan advised that there is a current 911 process on the PCAT. There is a 911 LNP link in the process. Amanda indicated that she had the process. Kathy will review the process and advise whether they understand the requirements. Qwest will look into their action items and check with their 911 database manager on the process of the 911 database management. Eschelon will review the process.

Confirm Areas & Products Impacted The products listed on the CR referenced 911. Qwest advised that this was primarily LNP. Qwest will update the CMP database. . Confirm Right Personnel Involved Qwest had the appropriate SMEs involved. It was confirmed that Lorna Dubose would be the owner with Joan’s support.

Identify/Confirm CLEC’s Expectation Qwest confirmed that there was a process. Eschelon is to review and comment Qwest and Eschelon are to collectively review why the 760 numbers are not getting unlocked.

Identify any Dependent Systems Change Requests There is no corresponding System CR

Establish Action Plan (Resolution Time Frame) Qwest and Eschelon to review their action items and get back to discuss findings.


CenturyLink Response

March 6, 2002

Eschelon Communications Kathleen Stichler ILEC Relations Manager

SUBJECT: Qwest’s Change Request Response - CR # PC122801-1 Qwest Process to Unlock E911 Records

This letter is in response to your Change Request PC122801-1 requesting that Qwest document, distribute and train an adhered to process to unlock numbers for E911.

Eschelon and Qwest conducted a clarification meeting to review Qwest’s current process for unlocking E911 records. During this meeting, Qwest shared with Eschelon that the migrate unlock record should be issued to Intrado, on the customer due date, once the migrate as been completed at NPAC. If the migrate record is issued prior to the customer due date, a 755 or 760 error will be generated.

In addition to Qwest’s existing process, effective, February 25, 2002, Qwest moved forward with implementing the new NENA recommendations. These recommendations require the old provider to unlock the E911 record once a validation has been completed with the NPAC. Therefore, when the CLEC sends the migration record to Intrado, on the customer due date, the NPAC activation should be complete also. Qwest will perform a validation to the NPAC and unlock the customer record once the CLEC migration record is received at Intrado. Intrado will distribute a report to the CLEC identifying any discrepancies.

The E911 Product Catalog has been updated to reflect this enhancement, as well as the appropriate personnel trained.

Again, thank you for partnering with Qwest.

Sincerely,

Lorna Dubose LNP Product Manager Qwest


Open Product/Process CR 5236247 Detail

 
Title: Implement a process for CLECs to upload PIC information to Qwest to compare to the PICs in Predictor
CR Number Current Status
Date
Area Impacted Products Impacted

5236247 Withdrawn
8/15/2001
Originator: Douglas, Kerrie
Originator Company Name: Eschelon
Owner: Routh, Mark
Director:
CR PM: Routh, Mark

Description Of Change

We would like a process created to compare CLEC PIC information to what is in Qwest’s Predictor system. Although we understand that there is a Feature Verification section in CSR– the information is not real time. Ideally, we would like to upload a file to Qwest and have them run a query comparing the PIC information, which resides on a particular Qwest switch and then have the query results returned to the CLEC. We want this process to have the ability to be run on a nightly basis as needed. We would like Qwest to indicate what file format would work the best for Eschelon send for this type of query. If Qwest can return the query information in Excel, Access or common delimited format that would be preferred. The information we would like to have in compared is TN and PIC Codes.


Status History

11/17/00 New – To be validated

11/21/00 New – To be industry evaluated. Sent email to Kerrie Douglas and Pat Brolsma with CR # and Status

12/04/00 Status changed to Reviewed – Under consideration

12/05/00 Sent email to Lynne Powers with updated CR.

01/12/01 Status changed to New- to be reviewed. T-Shirt size and options to be presented at the 2/21/01 CICMP meeting. New status is based on new requirements for this CR.

01/12/01 Sent email to Lynne Powers and Judy Rixe with updated CR.

02/07/01 Status changed to Reviewed – Under Consideration. T-Shirt size Medium and options provided. Eligible for industry prioritization.

02/08/01 Sent email to Lynne Powers and Judy Rixe with updated CR.

08/15/01 Canceled - CLEC


Project Meetings


Open Product/Process CR PC073101-1 Detail

 
Title: ANAC in CO for CLEC to CLEC migrations
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-1 Completed
4/15/2009
Provisioning Unbundled Loop
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Urevig, Russell
Director:
CR PM: Thomte, Kit

Description Of Change

Institute, document, and distribute a consistent process for using Automatic Number Announcement Callback (ANAC) in the Central Offices (COs) for CLEC-to-CLEC migrations when Qwest is unable to match the telephone numbers (TNs) to circuits. Qwest would then ANAC (in the CO) to determine which TN corresponds to which circuit, before Qwest processes the order. Qwest could use this process for retail as well to prevent unnecessary dispatches.


Status History

07/30/01 – CR received by Kathy Stichter

07/31/01 – Status changed to New – To be Reviewed

08/06/01 – CR discussed by the internal Qwest CR review team and owner designated

08/09/01 – CR status will be given at the August CICMP Meeting

08/14/01- Clarification Meeting held with Eschelon

09/04/01- Draft response sent to Eschelon

09/06/01 - Eschelon confirmed acceptance of Qwest response.

09/19/01 - CMP Meeting - Eschelon felt Qwest denied their request; however, they agreed to defer the CR for any future action.


Project Meetings

Stichter, Kathleen L. on 09/06/2001 02:12:02 PM

To: jlbroo2@qwest.com

Subject: FW: PCCR 073101-1 ANAC in CO for CLEC to CLEC migrations

Jerri, Bonnie and I talked today and we accept your response. We can close the CR 073101-1 ANAC in CO for CLEC to CLEC migrations. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

Tuesday 14th August 2001 Attendees: Kathleen Stichter, Bonnie Johnson - Eschelon Telecom/ Linda Hendricks, Deni Toye, Steve Hilleary, Todd Mead

Review Requested (Description of) Change When a customer migrates from one CLEC to another CLEC/ILEC, there is no way to match the TN with the Circuit ID if the TN did not originate from a Qwest switch. Confirm Areas & Products Impacted Provisioning Unbundled Loop Confirm Right Personnel Involved (has anyone else within Qwest been involved with this issue?) This issue falls between Steve and Russ Urevig’s areas of responsibilities. Russ is believed to have held a conference call (outside CICMP Process) discussing this issue approximately 1 month ago. Steve is the owner of this CR and will take the lead in obtaining resolution. Todd will talk to Russ to see if any minutes and/or actions were issued from this earlier call Identify/Confirm CLEC’s Expectation Develop, document and communicate a process for addressing the issue of matching TN’s and circuit ID’s for TN’s not originating in a Qwest switch for CLEC-to-CLEC/ILEC migrations. Identify any Dependent Systems Change Requests Todd will talk to Russ to see if any previous CR’s have addressed related issues (specifically, updated documentation outlining Qwest’s commitment to match TN’s and Circuit ID’s on TN’s originating in a Qwest switch). Establish Action Plan (Resolution Time Frame) Steve to meet with Russ Urevig before this Friday to develop a plan Steve will develop a plan (including timeframe) by next Monday, for achieving resolution of this issue


CenturyLink Response

Wholesale Product Marketing August 30, 2001

Kathleen Stichter ILEC Relations Manager Eschelon Telecom, Inc

CC: Russ Urevig Matthew Rossi Steve Hilleary Jerri Brooks

This letter is in response to your CLEC Change Request Form, number PCCR073101-1 dated July 30, 2001.

Request: Institute, document, and distribute a consistent process for using Automatic Number Announcement Callback (ANAC) in the Central Offices (COs) for CLEC-to-CLEC migrations when Qwest is unable to match the telephone numbers (TNs) to circuits. Qwest would then ANAC (in the CO) to determine which TN corresponds to which circuit, before Qwest processes the order. Qwest could use this process for retail as well to prevent unnecessary dispatches.

Response: After discussing this issue with Steve Hilleary (Central Office Staff) the central office can not Automatic Number Announcement Callback (ANAC) of a circuit without a firm order to work from which identifies the circuit ID and the CFA location. They also need a firm order to charge the work activity to. If the telephone number originated within the Qwest switch, Qwest will ensure that the proper TN is applied to the same circuit during the migration, as it was when it moved from the Qwest switch. As an NSP (network service provider) Qwest does not get involved with transfer of TN’s on CLEC to CLEC migration for facilities based only. Central office work relating Circuit IDs to TNs is handled the same for both Wholesale and Retail. The associating of TN’s to circuits is performed at the order processing level. As stated above the CO requires a firm order to be able to ANAC a TN to a circuit.

Sincerely,

Russell J. Urevig Wholesale Process Manager


Open Product/Process CR PC073101-2 Detail

 
Title: Written process for handling and disputing Customer Not Ready orders; written notification of completion
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-2 Completed
12/12/2001
Ordering Unbundled Loop, Other
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Whisenant, Jeanne
Director:
CR PM:

Description Of Change

Qwest had provided inconsistent information about its processes for Customer Not Ready (CNR) situations and how to dispute a determination by Qwest that customer was not ready. Eschelon asks Qwest to provide a written policy on CNR situations and a written process for resolving disputes. First, with respect to Qwest’s policy, Qwest should state its policy and specifically whether its policy is to reject an LSR and cancel an order within a specified time and, if so, the basis for that policy. Second, with respect to disputes, Qwest should state the process for disputing a determination that the customer was not ready when the customer was ready (e.g., the loop was in fact installed and accepted). In the past, when Eschelon has called 1-888-796-9087 to dispute a CNR letter (such as when the order completed and all loops were accepted), Qwest reps at that number did not know how to handle Eschelon’s request. Eschelon has also tried calling the Qwest tester to request closure of the order. Verbal closure has not been consistent or met our needs. For example, the tester may complete all but one order on a PON. When the one remaining order is not completed, the entire PON is rejected instead of only the one order. This, in effect, takes down the circuits for the customer, even though those circuits may have been working on the CLEC network as long as 6 weeks. Qwest should notify CLECs of completion of the orders when CLEC accepts the loop.


Status History

07/30/01 - CR received by Kathy Stichter

07/31/01 - Status changed to New – To be Reviewed

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - CR status will be given at the August CICMP Meeting

08/10/01 - Clarification Meeting Held

08/29/01 - Sent Draft Response to Eschelon

09/12/01 - Eschelon commented on Qwest's draft response - "Qwest is not waiting five days for us clear up any issues, or supp the orders. They issue these CNR letters normally the day following the original cut which is why we receive so many. If they did allow the actual five day interval, are sup versions would clear these so CNR's are not generated. This is the process that has been explained, and in theory would work great if followed as outlined below". Qwest has schedule a walk-through for Friday 9/14.

09/19/01 - CMP Meeting - Qwest reviewed its draft response and advised that a walk through meeting was scheduled for 09/24/01. It was agreed that Qwest should proceed with the meeting.

09/24/01 - Walk Through meeting held with CLEC Community

09/27/01 - Qwest's draft response issued to CLEC Community.

10/17/01 - CMP Meeting: Qwest to issue formal response. CLEC community agreed to change "Current Status" to CLEC Test.

10/19/01 - Qwest Final Response issued to CLEC Community and posted to dBase.

11/14/01 - CMP Meeting - Eschelon provided examples to Qwest's Service Manager of receiving CNR after they had issued SUP and received a FOC. Account Team is following up.

12/12/01 - CMP Meeting - CLEC Community agreed to change "Current Status" to "Completed." Qwest service manger (Patrica Levene) followed up with Eschelon regarding CNR examples.


Project Meetings

September 24, 2001 Alignment/Clarification Meeting Ric Martin, Qwest Vivian Vigil, Qwest Kathleen Stichter, Eschelon Tina Schiller, Eschelon Donna Osborne-Miller, AT&T Peter Wirth, Qwest

Introduction Introductions of the participants on the Conference Call were made. Qwest advised that the purpose of the meeting was to review Qwest’s response, Eschelon’s e-mail comments and address any questions from the other CLEC.

Review of Eschelon’s Comments Eschelon advised that the Tester was not contacting them and they were encountering problems with person’s handling their Sup and still receiving the cancellation notice. Communications - Qwest explained that the tester doesn’t always contact the customer and that the actual dealing with the customer would come from the issuance of a notification from the Center. AT&T addressed that Qwest’s items 3 & 4 in the process should be rewritten to reflect the actual practice and that communications would occur within 5 days. Qwest will revise the language. Eschelon explained that when an order is put into a jeop status, the Tester will put the order as CNR and Eschelon would not be aware of this until they receive the cancellation notice. Qwest advised that the tester is responsible for noting our records the reason the customer has asked the order to status with a pending customer reasons. The tester should include in notes the name of the contact at Eschelon we took the jeop status form . Eschelon is to try to provide some examples. Eschelon also explained that a held order, or other delayed orders ,would be released and a new due date was established and not communicated to Eschelon. As a result of not receiving the communication, they would not be aware or prepared for the order causing the order to be status with a customer jeop. Eschelon was to track and provide examples. Qwest reviewed the CNR dispute process and everybody understood and was satisfied with this process. All parties agreed that with the revised language to items 3 & 4, the process would meet their requirements when followed.

Establish Action Plan (Resolution Time Frame) Qwest will issue revised draft response by 9/28. Eschelon will track and provide the example of any discrepancies to the process.

08/10/01 - Clarification Meeting Attendees: Ric Martin Qwest Vivian Vigil Qwest Kathy Stichter Eschelon Tina Scheller Eschelon

Description of the change was reviewed. Eschelon advised that the CR identified two issues. They were looking for a written policy describing the process for handling Customer Not Ready (CNR) and confirmation on Acceptance Test of an Order. Qwest advised that there was a previous Release Notice, RN5467145, Qwest Position Statement On Build Requirements for Unbundled Loops. Vivian e-mailed a copy to the participants. Vivian further explained the steps that occur internally within Qwest. These steps are:

1) If an order goes C01 for Customer reasons on the due date, (whether it be no test access, end user doesn't want or just CLEC not ready to accept) the order will be jeop’d C01, C02 or C03. 2) If there are orders that involve re-use of facilities, the tester will call the typist to push dates out to avoid an out of service condition. 3) The Qwest tester normally is actively working with the CLEC to resolve the customer issue within the first 5 days. Testers will work to resolve the acceptance issues. 4) On the 5th business day a Jeopardy notice will be sent to the designated contact provided by the CLEC and a CNR 30-day letter/notice. (This is 30 business days) 5) The PON detail and CNR reason are populated on the weekly spreadsheet as well as the cancel date. 6) The delayed CNR orders are reviewed weekly to determine if a sup or interaction with the tester indicate that the CNR issue has been resolved or resolution is in process. If the CNR order issue has been resolved, the order is removed from the spreadsheet. 7) Approximately 2 weeks later, a second notice is sent. The order continues to appear on the weekly spreadsheet sent to the CLEC. Two days prior to the cancellation date, a final notice will be sent to the Qwest Sr. Mgr. advising that the order in question will be canceled if immediate response/acceptance is not received. 8) The CNR order must be resolved within the 30-business day window as outlined in the CNR letter. Due date sup requests for a period greater than 30 business days, will not be accepted. 9) The CLEC can call direct to the tester and clear any outstanding pending acceptance issues or send a sup for a date they want to deliver the loop. The tester may arrange for a different date or time if the request is more involved and the tester cannot handle the acceptance issue at that time.

CNR disputes

1) If the CLEC has sent in a sup for a new due date or has accepted the loop, and the order continues to appear on the spreadsheet, the CLEC should call the call center at 1 –888-796-9087 and ask to be warm transferred to the Delayed order group to work the CNR issue. The call center will issue a ticket and transfer the CLEC to the Cheyenne Delayed Order Group. 2) The Delayed order tracking representative will work with the CLEC to determine what action needs to take place to insure the updated status of the order is identified. 3) The Team leads in the Testing groups have committed to working with the CLEC direct on acceptance issues to insure that the order is completed in all internal systems thus eliminating the CNR status and negating a cancel situation on the order. Confirm Areas & Products Impacted CR identified that Unbundled Loop and other products affected by CNR issues were impacted Confirm Right Personnel Involved Eschelon’s personnel were correct. Qwest’s person is actively involved and was representing the Process Lead for this process. Qwest’s account teams has been working with Eschelon prior to this CICMP request and have made strides in educating Eschelon and establishing the revised process we now follow. Identify/Confirm CLEC’s Expectation Eschelon advised that the response presented by Vivian provided the details they were seeking in the CR. Qwest will review with the Process Lead to determine if the Release Notice should be updated. Qwest committed that any order that they have called in as accepted and we still show open in WFAC will be referred to a coach in the testing centers. Eschelon will call the call center for assistance on CNR issues, and if the call center cannot resolve the issue, the call center will be aware to warm transfer to Cheyenne Delayed order group. The CICMP document stated that when they had called the call center, the call center did not know how to handle the call. Cheyenne will continue to note CRM the day we removed the completed order from the spreadsheet (if the order completes in between spreadsheet dates) so that the call center can advise of this type of status, call the tester to check on the status or transfer the call. Eschelon addressed an issue where 3 orders on a PON, two were complete and not on the spreadsheet, all were canceled when the 1 order wasn’t completed. This was on PON MN102918JCP. Vivian would look into this and advise Tina at 612-436-6401. Eschelon addressed another issue that Qwest will clarify: When orders are RRSO, how far out are the dates pushed when the call handler is called? Qwest advised that it was the understanding that it was 60 days. Qwest to advise where this is documented in the tester process and the typist process. Eschelon is understanding the push out is 30 days, Qwest explained the time frame is internal to Qwest, and they should still send a sup if they want a new date or call the tester as explained above and not use this date, as their next delivery date. Identify any Dependent Systems Change Requests There is no corresponding System CR Establish Action Plan (Resolution Time Frame) Qwest will respond to the CR by the end of August.


CenturyLink Response

October 19, 2001 FINAL RESPONSE

This letter is in response to the following Change Request Form No. PCCR073101-2, dated July 30,2001.

? Written Process for handling and disputing Customer Not Ready Orders

? Response: A meeting was held by the Cheyenne Center Manager, Vivian Vigil, on August 10, 2001. Vivian discuss the Customer Not Ready Process and confirmation on Acceptance Test of an order.

Vivian further explained the steps that occur internally within Qwest. These steps are:

1) If an order goes C01 for Customer reasons on the due date, (whether it be no test access, end user doesn't want or just CLEC not ready to accept) the order will be jeop’d C01, C02 or C03. 2) If there are orders that involve re-use of facilities, the tester will call the typist to push dates out to avoid an out of service condition. 3) The Qwest tester will jeop the order for customer reasons and wait for a sup for a new due date. 4) A Jeopardy notice and the CNR letter requesting a sup for a new due date within the 30 business day window is sent within 5 business days. 5) The PON detail and CNR reason are populated on the weekly spreadsheet as well as the cancel date. 6) The delayed CNR orders are reviewed weekly to determine if a sup or interaction with the tester indicate that the CNR issue has been resolved or resolution is in process. If the CNR order issue has been resolved, the order is removed from the spreadsheet. 7) Approximately 2 weeks later, a second notice is sent. The order continues to appear on the weekly spreadsheet sent to the CLEC. Two days prior to the cancellation date, a final notice will be sent to the Qwest Sr. Mgr. advising that the order in question will be canceled if immediate response/acceptance is not received. 8) The CNR order must be resolved within the 30-business day window as outlined in the CNR letter. Due date sup requests for a period greater than 30 business days, will not be accepted.

CNR disputes

1) If the CLEC has sent in a sup for a new due date or has accepted the loop, and the order continues to appear on the spreadsheet, the CLEC should call the call center at 1 –888-796-9087 and ask to be warm transferred to the Delayed order group to work the CNR issue. The call center will issue a ticket and transfer the CLEC to the Cheyenne Delayed Order Group. 2) The Delayed order tracking representative will work with the CLEC to determine what action needs to take place to insure the updated status of the order is identified.

The Team leads in the Testing groups have committed to working with the CLEC direct on acceptance issues to insure that the order is completed in all internal systems thus eliminating the CNR status and negating a cancel situation on the order.

Sincerely

Vivian Vigil Cheyenne Center-Coach CNR Orders Jeanne Whisenant Wholesale CNR Functional Support


Open Product/Process CR PC073101-3 Detail

 
Title: Interim process (until systems change) for IMA edits (7 10 digits)
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-3 Completed
10/17/2001
Ordering Centrex
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Overly, Connie
Director:
CR PM:

Description Of Change

In a separate, systems CR, Eschelon has requested a systems change to address the issue of IMA edits for 7-10 digits for Customer Forwarding Number (CFN) floats for features on Centrex lines. Qwest should develop an interim process to address this issue until a system change is made. Qwest should allow CLECs to use 10 digits on all orders, with Qwest’s Center editing the order if 7 is appropriate. Although Qwest has provided a paper guide to use for this purpose, the guide is manual and out of date. Qwest’s centers have electronic, up-to-date access to this information and can more easily make the determination.


Status History

07/30/01 - CR received from Kathy Stichter

07/31/01 - Status changed to New – To be Reviewed

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - CR status will be given at the August CICMP Meeting

08/21/01 - Clarification Meeting held with Eschelon

08/23/01 - MCC issued

08/31/01 - Sent Draft Response to Eschelon

09/06/01 - Eschelon confirmed acceptance of Qwest's response

09/19/01 - CMP Meeting -Eschelon acknowledges Qwest's response and agreed to move the CR into CLEC Test.

10/17/01 - CMP Meeting: It was agreed that the CR could be "Closed."


Project Meetings

Date: Thu, 6 Sep 2001 12:27:40 -0500 Subject: FW: CR 073101-3 Draft Response From: "Stichter, Kathleen L." To: rhmart2@qwest.com

Ric, We have read the response and agree that with the formal issuance of this response we can close this CR. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

August 21, 2001 Conference Call CRResponse073101-3.doc 866-289-7092 PCCR073101-3, Interim Process (until system change) for IMA edits (7-10) Attendees Name/Company:

Ric Martin, Qwest Kathy Rein, Qwest Kathleen Stichter, Eschelon

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed 2.0 Review Requested (Description of) Change 2.1 Description of the change was reviewed. Ric clarified that Eschelon was looking for the same capability in Centrex that currently exists in IMA for CFN floats. This is to allow Eschelon to put 10 digits and the center would edit down to 7 if required. Eschelon agreed with this clarification. 2.2 Kathy Rein advised that the system currently allow the customer to enter 10 digits. This is done in the free text field. The centers can edit the number to 7 digits if necessary and would issue an MCC to the Centers 3.0 Confirm Areas & Products Impacted 3.1 This issue impacts Ordering, repair and provisioning when using the Centrex product. 4.0 Confirm Right Personnel Involved 4.1 It was confirmed that the parties involved were the correct personnel to resolve the issue. Kathy Rein indicated that her manager would have to issue a response to the CR. 5.0 Identify/Confirm CLEC’s Expectation 5.1 The ability to input 10 digits and have the centers edit down to 7 meets Eschelon’s expectations. 6.0 Identify any Dependent Systems Change Requests 6.1 There is currently a systems Change Request, SRN073001-1 and is part of the CRs to be prioritized. 7.0 Establish Action Plan (Resolution Time Frame) 7.1 Kathy Rein will issue an MCC to the Centers clarifying the requirement to edit 10 digit inputs to 7 if required by 8/24/01. Kathy Rein 7.2 Kathy Rein will review with her Manager, Susie Wells, for issuance of a formal response to the CR. Ric will follow through with a date to respond. Ric Martin


CenturyLink Response

Wholesale Product Marketing

August 31, 2001

This letter is in response to the following CLEC Change Request Forms #PCCR073101-3, dated July 30, 2001. This Change Request pertains to Customer Forwarding Number (CFN) for the Centrex products. An interim process was agreed to on August 28,2001.

Qwest will allow CLEC’s to use 7,10 or 11 digit CFNs in the Feature Detail on Centrex CRS form of the LSR.

Qwest Service Center personnel will determine the number of digits needed 7 – 10 for local call forwarding and edit the order if necessary. Updates to Service Delivery M&Ps are not required, current process is accurate.

The following measures have been implemented:

A New Multi Channel Communicator (MCC) was issued on August 23, 2001 and distributed on August 24,2001. Issued to target Qwest internal personnel in the Wholesale Order Processing and Order Resolution, Error Group and Screeners organizations. MCC Subject Centrex 21, Centrex Plus, Centron Topic of the MCC: “Call Forward Number Format.” Emphasis placed on CFN numbers on all Centrex requests being verified for proper order formatting. States included in this communication are; AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NE, NM, OR, SD, UT, WA and WY.

Sincerely

Connie Overly Service Delivery Product Process


Open Product/Process CR PC073101-4 Detail

 
Title: Review of Redacted materials and parity in search capability
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-4 Completed
7/17/2002
Ordering, Billing, Repair, Prov. Other
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Thompson, Michael
Director:
CR PM:

Description Of Change

Develop a process to initially and periodically review redaction of materials to ensure that redaction is necessary and not overbroad. Also, ensure that search capability is of equal ease for Qwest and CLECs. Not all information available to Qwest is available to CLECs. For example, Qwest refers CLECs to “InfoBuddy,” but “InfoBuddy” is not available to CLECs in the same form as it is available to Qwest. CLECs access a “redacted” version of InfoBuddy. Although Qwest may have legitimate grounds for redacting certain truly proprietary information, not all information that has been redacted necessarily falls into those categories. For example, CLECs should have access to the same example forms, order examples, and other detailed information as Qwest. Qwest should provide to CLECs full information necessary to understand and order its products. For example, Eschelon asked Qwest for information relating to IDSL. Qwest referred Eschelon to InfoBuddy. Eschelon does not have access to InfoBuddy. Qwest was able to obtain more information about IDSL from InfoBuddy than Eschelon could obtain from the redacted materials. It also appeared that Qwest is able to search InfoBuddy with more ease than a CLEC can search the redacted materials. It is difficult to provide examples when we do not see the redacted information. But, based on statements by Qwest, it is apparent that Qwest is able to access more detailed information than available to CLECs. When that information would aid CLECs in ordering and provisioning, CLECs should also be able to access the information, with the same search and access capabilities available to Qwest.


Status History

07/30/01 - CR received by Kathy Stichter

07/31/01 - Status changed to New – To be Reviewed

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - Clarification Meeting held with Eschelon

08/30/01 - Draft response sent to Eschelon

09/12/01 - Walk Through on Qwest Response conducted with Eschelon. Eschelon to send websites internally for comments.

09/17/01 - Follow up review meeting held with Eschelon.

09/19/01 - CMP Meeting - Qwest reviewed draft response and explained purpose of "info-buddy". Qwest to review the redacted material, revise response and issue revised draft.

10/09/01 - Posted Final Response to database.

10/17/01 - CMP Meeting: Sue McNa, Qwest presented response. Eschelon requested presentation by Michael Thompson, Qwest regarding web aspects of response. Michael was not in attendance. Michael to present in next CMP meeting (November 14, 2001). No change to "Current Status."

11/14/01 - Michael Thompson, Qwest provided status regarding the clean up effort that is underway in the Database to ensure that the appropriate documents are available. A question was asked regarding the status of the search capability. Michael explained how the search capability works and that currently search by title is not available. Although Michael is working with Information Technologies to determine if search by title can be provided. Michael will provide update in December.

12/12/01 - CMP Meeting - Michael Thompson, Qwest provided a status update indicating the following: (1) business case for funding of RPD search engine modifications is in progress, and (2) clean-up of RPD is in progress & should be completed in January 2002. Eschelon indicated that review of the RPD shows improvement in the detail and number of documents available to the CLEC community. "CR Status" remains "Development."

01/16/02 - CMP Meeting - Michael Thompson, Qwest provided a status update indicating the following: (1) business case for funding of RPD search engine modifications is in progress with the Qwest IT group; and (2) clean-up of RPD is in progress & is scheduled for a 02/02/02 completion. CLEC notification will follow completion of clean-up. CR Status remains "Development."

02/01/02 - Web Notification trnsmitted to the CLEC community regarding Resale Product Database (RPD) update (effective 02/02/02).

02/02/02 - RPD update effective.

02/20/02 - CMP Meeting - Qwest provided CR status update. CR remains in "Development" status. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/08/02 - Qwest agrees to fund RPD search engine modifications.

03/20/02 - CMP Meeting - Qwest provided status update. It was announced that the enhancements to the Resale Products Data (RPD) search engine will be deployed by the end of May 2002. CR Action Item 1 closed. It was agreed that the CR status remain in Development. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/17/02 - CMP Meeting - CR status Development unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

05/15/02 - CMP Meeting - CR status "Development" unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

05/17/02 - Systems Notice issued that stated "RPD will provide an Enhanced Search Engine beginning June 14, 2002" issued to CLECs. Reference document number SYST.05.17.02.F.04055.RPD_Enh_SrchEngn.

06/19/02 - CMP Meeting - CR status changed to "CLEC Test". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07/17/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status was changed to Completed.


Project Meetings

09/17/01 - Clarification/Walk-through Meeting Introduction of Attendees Kathy Stichter, Eschelon Ric Martin, Qwest Sue Mcna, Qwest Michael Thompson Qwest Lynn Stecklein Qwest

Introduction of participants on the Conference Call was made. The purpose of the call was to discuss Qwest’s draft response dated August 28, 2001 to determine if the response met Eschelon’s expectations. Review of Response On September 11th a meeting was held to walk through the Wholesale websites with K Stichter. She indicated she wanted her team to review the websites as well and we would discuss on September 17th. K Stichter advised that she did not feel that the Wholesale websites would meet their needs. She felt that the websites were missing information necessary for Eschelon to do business. K Stichter provided one example: Call Pick Up was found in the website as well as CCMS. However, it does not tell a customer how to activate Call Pick Up. S Mcna advised that the Wholesale Website is work in progress. Some information will not be available until the end of the year. (i.e. Centrex/resale). K Stichter understands that the website is work in progress and still does not believe that all information will be there. She could not provide any additional examples but would share as they came up. K Stichter said that she also understands the proprietary issues on viewing Info Buddy. She does not want to view proprietary information. She only wants information to conduct business. M Thompson and L Stecklein will review the redacted materials guidelines and policy. R Martin requested that we update our response and develop an action plan on further implementation of the website. Scheduled monthly meetings to discuss progress could be initiated. The goal would be to have our response and plan accepted by Eschelon and the CR go into an implementation phase for development of the WEB site

09/12/01 - A meeting was held on 9/12/01 to discuss the Qwest Response with Eschelon. Attendees: Kathy Stichter - Eschelon, Sue Mcna, Michael Thompson, Lynn Stecklein, Ric Martin - Qwest The team discussed and provided a walk through with Kathy of the websites that Michael Thompson documented in the Qwest Response. Kathy advised that she needed to send a message within Eschelon requesting that everyone review the websites to determine if the information provided would meet their needs. A meeting has been scheduled on 9/17/01 at 3:00 p.m. MT to discuss results.

Thursday 9th August 2001 Attendees: Kathleen Stichter - Eschelon Telecom/ Sue Mcna, Michael Thompson,Todd Mead - Qwest

Eschelon want to see the same level of documentation as Qwest sees, when ordering services and getting repairs. Specific examples Eschelon quoted, included order documents for Call Forwarding (CF) products including CF Busy Line and CF Don’t Answer. Also documentation relating to IDSL (unspecified).

Eschelon expect to see the same level of documentation as Qwest views when ordering services and getting repairs.


CenturyLink Response

October 9, 2001 Revised Response Re: CR PC073101-4 Review of Redacted materials and parity in search capability

Qwest has conducted further investigation into the redaction methods associated with RPD.

Redaction Guidelines are available to Qwest Process Analysts and compliance is ensured through each Process Director. The Qwest Process Helper internal website contains all the documentation the Process Analysts need and use in their jobs, including redaction procedures and training. Information to be redacted from Qwest methods and procedures prior to release in RPD include: Billing and Collections procedures Sales/Promotions procedures Internal systems procedures

RPD is updated once per day with appropriate, non-redacted, information from internal methods and procedures.

Qwest Wholesale Markets met with documentation representatives from its own department as well as Qwest Retail Consumer Markets. Based upon this meeting, Retail has assigned a Redaction SME to further coach and respond to redaction questions by Retail process analysts. In addition, managers are reviewing redaction procedures with their teams in their team meetings. Process Analysts are being instructed to review their methods and procedures for proper redaction application.

Links from InfoBuddy (Qwest’s internal methods and procedures documentation system) to other internal systems/databases are not provided to CLECs as part of the RPD; rather information from these databases that is required for the CLEC to interface with Qwest will be provided at the Wholesale website; http://www.qwest.com/wholesale.

Qwest Wholesale Markets has embarked on a documentation audit and clean-up effort. Documentation available through RPD and the Wholesale website is being compared and analyzed to ensure consistency and alignment throughout. Corrections to website documentation will be completed to ensure all documentation required by a CLEC to be able to do business with Qwest is correct and available at the Wholesale website. Product Catalog, Procedural, System, Network and Training documentation is being created and/or updated and published at the wholesale website.

Michael L Thompson Lead Marketing Comm Coordinator

Cc: Sue Mcna

August 30, 2001 Final Response Wholesale Product Marketing This letter is in response to the following CLEC Change Request Forms # PCCR073101-4, dated July 30, 2001. This Change Request pertains to the Resale Product Database (RPD). INFOBUDDY versus the RPD INFOBUDDY is an internal database repository of Qwest’s methods, procedures and processes, and is intended for internal Qwest personnel only. INFOBUDDY is referred to in the context of external customers (CLEC’s) as the “Resale Product Document (RPD)”. It is common practice for the CLEC to be made aware of the Web Based RPD during the initial training by the Account Manager. It was inappropriate for the ISC and or the Account Team to refer to the RPD as INFOBUDDY. All ISC and or Account Team Members should refer the CLECs to Qwest Wholesale Markets Web Page (http://www.qwest.com/wholesale/), or the RPD.

Accessing and searching the RPD In the fourth quarter of 2000, the RPD was moved from a downloadable UNIX tarball file to a web based application. The UNIX file was very large (over 1 Megabyte), and caused problems with downloading, loading, and accessing the information. The Web Based RPD provides a method to access and search for methods, procedures, and process information in a consistent fashion as is offered in Qwest Retail environment.

CLEC Access to order examples Qwest Wholesale Markets evaluating the feasibility and best approach to make order examples available to CLECs. Do to the inherent nature of the RPD it might be determined that order examples can not be made available within the RPD. In order for order examples to be made available to CLECs, the following list some of the issues that Qwest Wholesale Markets will need to address regarding CLECs accessing order examples: Will providing order examples enable CLECs to fill out LSRs more accurately? Where will order examples will be located? Retail contact / owner of order examples? Wholesale Markets contact / owner of order examples? Type of order examples to be made available? Time line to make available order examples?

Qwest Wholesale Markets will report back to the CICMP Group the feasibility of providing order examples by August 30, 2001.

Response: August 14, 2001 Qwest continues to explore the methodology for providing order examples as part of overall product implementation documentation efforts. A review is currently underway that examines current documentation in the area of “Ordering.” Once this review is complete, Qwest will determine the appropriate means to access service order examples. We expect to have a preliminary plan prepared by August 30, 2001.

Response: August 29, 2001 On August 23, 2001, Qwest published the Local Service Ordering Guidelines (LSOG) that contains comprehensive guidelines for the preparation of all service orders that CLECs would use for placing an order.

The LSOG documents provide detailed form-by-form, field-by-field instructions for completing local service request manually, or via IMA. The LSOG is the tool that CLECs and Resellers should use to complete service request.

The LSOG contains both blank forms and sample forms within each product order document. CLECs were notified of the publication of the LSOG on August 22, 2001. The LSOG is found on the Qwest Wholesale Markets web site at http://www.qwest.com/wholesale/clecs/lsog.html.

The Qwest Wholesale Markets Web Page provides web-based training on manually completing local service request forms in the Introduction to Service Requests and Billing course. Qwest also provides IMA Training regarding how to use the IMA GUI to submit local service requests. There is also product specific training for completing all the processes associated with submitting local service requests.

In addition to the training, and LSOG information that is available on the Qwest Wholesale Markets Web Page, there are specific product catalogs (PCATs) that contain detailed product descriptions, pricing, features / benefits, applications, prerequisites, pre ordering, ordering, provisioning, maintenance, billing, training, contacts, and frequently asked questions.

Any CLEC or Reseller that has specific examples of a product, or products that they are not satisfied with the information that is available to them on the Wholesale Markets Web Page is encouraged to submit a change request via the CICMP process. Qwest will investigate the issue, and work with the customer to determine the best plan of action to meet their information needs.

The following are some helpful URLs

Wholesale Markets Web Page http://www.qwest.com/wholesale/

Training Web Page http://www.qwest.com/wholesale/training/

Training & Notices Introduction to Service Requests & Billing for CLECs & Carriers http://www.qwest.com/wholesale/training/tsc.html

IMA "Hands On" http://www.qwest.com/wholesale/training/iltdescimahandson.html

Training – Qwest 101 “Doing Business with Qwest” http://www.qwest.com/wholesale/training/iltdescqwest101.html

Facility-Based Providers - Welcome to Qwest Interconnection! http://www.qwest.com/wholesale/pcat/interconnection.html This web page contains Interconnection business procedures, forms, and product catalogs (PCATs).

Resellers - Welcome to Qwest Interconnection! http://www.qwest.com/wholesale/pcat/resale.html This web page contains Resell business procedures, forms, and product catalogs (PCATs).

Interconnect Mediated Access GUI http://www.qwest.com/wholesale/ima/gui/index.html

Service Intervals http://www.qwest.com/wholesale/guides/sig/index.html

Qwest USOC/FID Finder http://usocfidfind.uswest.com/prodquery/usocSearch.html

Michael L Thompson Lead Marketing Comm Coordinator


Open Product/Process CR PC073101-5 Detail

 
Title: Improve ZAP process and turn around time and post orders promptly
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-5 Completed
10/17/2001
Ordering Resale, Unbundled Loop, UNE-P, Other
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Coyne, Mark
Director:
CR PM: Thomte, Kit

Description Of Change

Qwest has indicated that it will post orders to CLEC billing accounts by the next bill cycle after the order is completed. In addition, Qwest said that an order completing on the last day of a month may not post by the next day, and the CLEC should allow time for the order to post on the next billing cycle. Therefore, if an order completes one day after a bill cyle, Qwest has at least 30 days to post it. When an order contains errors that prevent flow through to posting, the order falls to manual handling and is sent to a process called “ZAP.” If the order had not fallen to manual handling, it would have been posted within 1-3 days. When an order goes to “ZAP,” however, the period is much longer. Qwest says that it has the rest of the bill cycle to correct the errors in the order so that the order will post. If Qwest is going to send orders to “ZAP,” it needs to improve the turnaround time so that the posting of orders is not unreasonably delayed. If the ZAP turnaround time is not improved so that orders post within 1-3 days, CLECs will encounter problems when attempting to issue supplemental orders. In addition, Qwest should provide contact information and a process for resolving issues that have been sent to “ZAP.”


Status History

07/30/01 - CR received by Kathy Stichter

07/31/01 - Status changed to New – To be Reviewed 8/10/01 - Alignment meeting held 8/14/01 MCC issued and draft response prepared for discussion at next CICMP

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - CR status will be given at the August CICMP Meeting

08/10/01 - Clarification Meeting Held with Eschelon

08/13/01 - MCC issued

08/28/01 - Draft response sent to Eschelon

08/29/01 - Eschelon responded indicating the process sounded good if the people would use it. She sighted a recent example of a person saying they would not open a ticket because 30 days to work on the issue. Kathy asked if I would look into this

08/31/01- Sent email response to issue identified in 08/29/01 conference call

09/06/01 - Qwest sent confirmation on the additional distribution of the MCC.

09/07/01 - Eschelon confirmed acceptance of Qwest's response.

09/14/01 - Qwest issued response to Eschelon

09/19/01 - CMP Meeting - Eschelon advised that 09/18/01 a Qwest Center didn't follow the process. Qwest will investigate. Eschelon acknowledges Qwest's response and agreed to move the CR into CLEC Test.

10/09/01 - Mark Coyne spoke with Eschelon to see if other issues had occurred at this time. None were identified.

10/17/01 - CMP Meeting: It was agreed that the CR could be closed.


Project Meetings

09/07/2001 08:36:40 Stichter, Kathleen L. AM To: kthomte@qwest.com cc: "Johnson, Bonnie J." Subject: FW: FW: PCCR 073101-5 ZAP process turn around time

Kit, Thanks for the documentation. We are satisfied with the process. We can close this CR with the hope that everyone will follow the process. Thanks again.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

09/06/01 Subject: Re: FW: PCCR 073101-5 ZAP process turn around time From: "Kathleen Thomte" To: "Stichter, Kathleen L."

Kathy, I am attaching the distribution from the MCC associated with the ZAP process PCCR. Anyway as you scroll through you will see that it was sent to the coach at Aegis as well as the managers in the centers. I hope this will close this one out. Drop me an e-mail and let me know for sure. Thanks! Kit Thomte 303 896-6776

08/31/2001 04:28 PM Email To: klstichter@eschelon.com cc:

Subject: PCCR 073101-5 ZAP process turn around time Kathy,

I have been working with Christine Siewert in Minneapolis regarding PCCR 073101-5 ZAP process turn around time. Yesterday I received your e-mail indicating that the process is great but some work needed to be done to ensure that employees that deal with escalations understand the process. Bonnie Johnson outlined a specific example where a Tier 0 employee believed the time frame was thirty days. I verified which groups had actually received the Multi Channel Communicator initially and determined that the target audience needed to be expanded to include other work groups beyond those people correcting errors. The additional work groups were covered on this process on August 30th per Christine Siewert. I believe we have resolved this issue based on the coverage of additional work groups that have been advised of this process. If we need to discuss this issue further please contact me to set up a meeting early next week. Thanks,

August 10th, 2001 Attendees: Kathy Stichter & Bonnie Johnson - Eschelon, Todd Mead & Mark Coyne - Qwest CLEC Expectations Eschelon's expectations is for Qwest to commit to a standard order posting time-frame, regardless of the next billing cycle Once the time-frame is established. Eschelon needs to know the correct escalation procedure to use if this time- frame is not met.

Action Plan Mark will prepare a draft written including the process, time-frame and escalation procedure by August 17th. Mark will also prepare and send out a notification to all centers communicating the time-frame and escalation procedure in relation to the ZAP process. The draft written response will contain a copy of this notification. Kit worked with center Mgr. To get MCC covered with appropriate workgroup

MCC Sent out: August 13, 2001 Critical MCC Subject: Error Correction


CenturyLink Response

September 14, 2001 Wholesale Product Marketing Eschelon Telecom Kathy Stichter

This letter is in response to the following CLEC Change Request Forms #PCCR073101-5 dated July 30, 2001. This Change Request pertains to the ZAP process and turn around time.

The Qwest standard for ZAP resolution is 5 days. This is measured from the time the order completes in the SOP (Service order processor)to the time it post in CRIS.

In order to ensure the (5) day measure, the ISC should be working on an in-today out-today basis for CRIS errors. Every order in CRIS error should have an attempt made for correction on day (1). Should the order return to an error status on day (2), it should be worked before the orders on day (1) of CRIS error. Should an order error on day (3), the order should be referred to a SME within the center for resolution or referral to a CRIS programmer. Orders should be referred to a programmer no later than day (3) of CRIS error to ensure the (5) day measure it met.

If the CLEC determines that this is not occurring as it should they are to contact the ISC for assistance and follow the existing escalation process by calling 1-888-796-9087. The agent will assist the CLEC by opening a ticket and making sure the ticket gets forwarded to the proper group handling error correction.

An MCC ( Multi Channel Communicator) will be sent out all Center managers, team coaches and SDC’s handling error correction. This notice will go out effective 8/14/01. On August 30th the MCC distribution was expanded to include all Center managers and agents that represent Qwest.

Sincerely Mark Coyne Team Lead Process


Open Product/Process CR PC073101-6 Detail

 
Title: Process to consistently pull translations upon acceptance or order for loop with LNP
CR Number Current Status
Date
Area Impacted Products Impacted

PC073101-6 Completed
1/16/2002
Repair Unbundled Loop, LNP
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

In some cases, for orders for unbundled loop with LNP, Qwest completes CLEC orders to remove lines from Qwest switches before necessary work is done. Qwest does not pull the telephone numbers associated to the lines from its switches. Until it does so, CLEC’s customers experience trouble and cannot receive calls from Qwest customers (often within the same switch). Qwest should establish a process to ensure that Qwest consistently pulls translations upon acceptance of order.


Status History

07/30/01 - CR received by Kathy Stichter

07/31/01 - Status changed to New – To be Reviewed

08/06/01 - CR discussed by the internal Qwest CR review team and owner designated

08/09/01 - CR status will be given at the August CICMP Meeting

08/29/01 - Clarification Meeting Held with Eschelon

08/31/01 - Draft response sent to Eschelon

09/19/01 - CMP Meeting - Eschelon advised that the response didn't answer their CR. Qwest to readdress and issue revised response.

10/02/01 - Sent Updated Final response to Eschelon including requested updates.

10/17/01 - CMP Meeting: Reviewed Qwest response. Qwest to revise response to include current process and address network issues involved with switches.

11/01/01 - Sent Updated Final Response dated October 30, 2001 to Kathy Stichter at Eschelon.

11/14/01 - CMP Meeting - It was agreed that the CR could be moved into CLEC Test.

11/19/01 - Matt Rossi distributed revised Final Response dated 11/16/01 to CLEC Community.

11/19/01 - Forwarded revised Final Response dated 11/16/01 to Eschelon.

12/12/01 - CMP Meeting - Qwest reviewed the response to Action Items. Eschelon addressed its previous escalated trouble ticket. Qwest to set-up an internal meeting to review Qwest's root cause analysis and provide feedback.

01/16/02 - CMP Meeting - Qwest reviewed the response to Action Item 3. Escehlon agreed to close the CR. If they have future problems, they will open a new CR and reference back to this CR.


Project Meetings

08/29/01 - Establish a process to consistently pull translations upon acceptance of order for loop with LNP Confirm Areas & Products Impacted Areas: Repair and Provisioning Products: LNP & Unbundled Loop Confirm Right Personnel Involved Lorna is the ‘owner’ of this CR and will be the point of contact for future problems of this nature until the root cause is established and draft response issued. Joan will provide a written response to include feedback on the individual problem identified in the CR (PON MN102820DMM) Nancy will remain included in all correspondence on this issue Identify/Confirm CLEC’s Expectation Eschelon would like the see a process established to ensure Qwest consistently pulls translations upon acceptance of order Identify any Dependent Systems Change Requests No related system CR’s were identified Establish Action Plan (Resolution Time Frame) Joan has investigated PON MN102820DMM (example included in CR), with the involvement of the translation group and will forward a written response document to Lorna by


CenturyLink Response

November 16th, 2001 Final Response

Ms. Kathleen Stichter Eschelon Telecom

Dear Ms. Stichter:

A conference call was conducted with Eschelon on August 29th, 2001 at which time Qwest Product and Process reviewed and responded to the CR PCCR073101-6, Title of Change: Process to consistently pull translations upon acceptance of order for loop with LNP.

The problem was specific and noted an example of a block of 100 DID numbers that were not removed from switch translations in a timely manner, causing problems with the end user customer receiving incoming calls from other callers within the same switch.

The switch is noted as the 612 928 MPLSMNBEDS0 5E Switch. There is a current process in the 5E switch for setting the ten digit unconditional trigger automatically. Upon completion of this process and the port activity, this allows correct routing of calls, even though the translations may or may not have been disconnected. It has been confirmed that translation’s should be completed by the frame due time indicated on the Port order.

Because of the delay in time, investigating this exact situation was not possible Qwest has not received any additional examples of order activity in which the triggers or translations have caused problems for the end users. It has been determined that this was an isolated incident. Systems occasionally do have problems and in this instance, perhaps the triggers were not set properly. The process of setting triggers and releasing translations has been verified and is in order, so it is unclear as to why this situation occurred. Provided the mechanized triggers are being set properly, this concern of not pulling the translation’s in association with acceptance of the loop, should not affect the end user’s service and their ability to receive incoming calls, even if there is a delay in pulling the translation’s.

Eschelon has been advised that should they incur the situation in the future, they can contact Qwest for immediate investigation.

Should the CLEC require immediate release of translations upon activation of the Port, they may contact the ISC Call Center, 888-796-9087and open up an Escalation ticket. The Escalation representative can then contact the appropriate Qwest department to have the translations removed. The CLEC may contact the ISC Call Center 48 hours prior to and after the port due date. After that time, the CLEC must contact the Qwest AMSC repair group 1 800-223-7881 for assistance.

Through further discussion, it has been determined that additional information is needed in this response. The issues are as follows:

1.) Describe the current process of pulling translation’s associated with an Unbundled Loop with LNP.

Different types of coordinated and non-coordinated installs are offered on Unbundled Loop with LNP.

Coordinated * Clec currently indicates DFDT (Desired Frame Due Time) on Local Service Request, this time is placed on Qwest order for the install time of the UBL * CHC field populated * FDT (Frame Due Time) on Port Out C/D disconnect order is 11pm * When loop order is complete, implementor calls the switch translation’s to the complete the port C/D order, removing switch translations

Non-Coordinated * Clec currently indicates DFDT (Desired Frame Due Time) on Local Service request, this time is placed on Qwest order for the install time of the UBL * FDT (Frame Due Time) on the Port Out C/D disconnect order is 6pm. * Loop order is completed at DFDT (Desired Frame Due Time) and switch translations are disconnected automatically at 6pm.

Additional information on the Unbundled Loop Product, along with all types of installation’s available is located in the Qwest Product catalog at: http://qwest.com/wholesale/pcat/unloop.html

2.) Matrix on Network Switch types indicating when the 10 digit mechanized trigger can be set. (See Supplemental Information following this detail report for the Matrix)

Often, the number port is activated by the new Network Service Provider (NSP) prior to the designated FDT (Frame Due Time) of 6pm on non-coordinated loop with LNP. As long as, the 10 digit mechanized trigger has been set, correct call routing will take place until such time that the actual switch translation’s are disconnected. In those switch types where Qwest cannot set the 10 digit mechanized triggers, translation’s will not be removed until the 6pm time frame. This overlap of switch translations helps to ensure a smooth number port transition, until both the loop and number port are complete. Should the Clec require that the switch translations be disconnected prior to the 6pm time frame, they can contact the Interconnect Call Center and open an escalation request, otherwise this is an automated process and should be completed by 6pm to ensure correct call routing.

Action item from November CMP call: If the frame due time is 6pm to pull down the translations and the loop was installed at 12pm, Can we call to have the translations removed at 1pm? Yes, the Clec can call the ISC Call Center and open an escalation ticket requesting that the translations be pulled down earlier than the 6pm time frame. If this is done what will happen at 6pm? Nothing. The translations will have already been pulled down and the order would show as being worked in the system already. The order would simply go on to complete out and no changes to the translations would occur, because the work would show as already being done.

Sincerely, Joan Wells LNP Process Manager

-

October 30, 2001 FINAL RESPONSE

Ms. Kathleen Stichter Eschelon Telecom

Dear Ms. Stichter:

A conference call was conducted with Eschelon on August 29th, 2001 at which time Qwest Product and Process reviewed and responded to the CR PCCR073101-6, Title of Change: Process to consistently pull translations upon acceptance of order for loop with LNP.

The problem was specific and noted an example of a block of 100 DID numbers that were not removed from switch translations in a timely manner, causing problems with the end user customer receiving incoming calls from other callers within the same switch.

The switch is noted as the 612 928 MPLSMNBEDS0 5E Switch. There is a current process in the 5E switch for setting the ten digit unconditional trigger automatically. Upon completion of this process and the port activity, this allows correct routing of calls, even though the translations may or may not have been disconnected. It has been confirmed that translation’s should be completed by the frame due time indicated on the Port order.

Because of the delay in time, investigating this exact situation was not possible Qwest has not received any additional examples of order activity in which the triggers or translations have caused problems for the end users. It has been determined that this was an isolated incident. Systems occasionally do have problems and in this instance, perhaps the triggers were not set properly. The process of setting triggers and releasing translations has been verified and is in order, so it is unclear as to why this situation occurred. Provided the mechanized triggers are being set properly, this concern of not pulling the translation’s in association with acceptance of the loop, should not affect the end user’s service and their ability to receive incoming calls, even if there is a delay in pulling the translation’s.

Eschelon has been advised that should they incur the situation in the future, they can contact Qwest for immediate investigation.

Should the CLEC require immediate release of translations upon activation of the Port, they may contact the ISC Call Center, 888-796-9087and open up an Escalation ticket. The Escalation representative can then contact the appropriate Qwest department to have the translations removed. The CLEC may contact the ISC Call Center 48 hours prior to and after the port due date. After that time, the CLEC must contact the Qwest AMSC repair group 1 800-223-7881 for assistance.

Through further discussion, it has been determined that additional information is needed in this response. The issues are as follows:

1.) Describe the current process of pulling translation’s associated with an Unbundled Loop with LNP.

Different types of coordinated and non-coordinated installs are offered on Unbundled Loop with LNP.

Coordinated *Clec currently indicates DFDT (Desired Frame Due Time) on Local Service Request, this time is placed on Qwest order for the install time of the UBL *CHC field populated *FDT (Frame Due Time) on Port Out C/D disconnect order is 11pm *When loop order is complete, implementor calls the switch translation’s to the complete the port C/D order, removing switch translations

Non-Coordinated *Clec currently indicates DFDT (Desired Frame Due Time) on Local Service request, this time is placed on Qwest order for the install time of the UBL FDT (Frame Due Time) on the Port Out C/D disconnect order is 6pm. *Loop order is completed at DFDT (Desired Frame Due Time) and switch translations are disconnected automatically at 6pm.

Additional information on the Unbundled Loop Product, along with all types of installation’s available is located in the Qwest Product catalog at: http://qwest.com/wholesale/pcat/unloop.html

2.) Matrix on Network Switch types indicating when the 10 digit mechanized trigger can be set. (See document for matrix)

Often, the number port is activated by the new Network Service Provider (NSP) prior to the designated FDT (Frame Due Time) of 6pm on non-coordinated loop with LNP. As long as, the 10 digit mechanized trigger has been set, correct call routing will take place until such time that the actual switch translation’s are disconnected. In those switch types where Qwest cannot set the 10 digit mechanized triggers, translation’s will not be removed until the 6pm time frame. This overlap of switch translations helps to ensure a smooth number port transition, until both the loop and number port are complete. Should the Clec require that the switch translations be disconnected prior to the 6pm time frame, they can contact the Interconnect Call Center and open an escalation request, otherwise this is an automated process and should be completed by 6pm to ensure correct call routing.

Sincerely, Joan Wells LNP Process Manager

-

October 2, 2001 Wholesale Product Marketing Ms. Kathleen Stichter Eschelon Telecom

Re: Final Response for PCCR073101-6: Establish a process to consistently pull translations upon acceptance of order for loop with LNP Dated 07-30-01

Dear Ms. Stichter:

A conference call was conducted with Eschelon on August 29th, 2001 at which time Qwest Product and Process reviewed and responded to the CR PCCR073101-6, Title of Change: Process to consistently pull translations upon acceptance of order for loop with LNP.

The problem was specific and noted an example of a block of 100 DID numbers that were not removed from switch translations in a timely manner, causing problems with the end user customer receiving incoming calls from other callers within the same switch.

The switch is noted as the 612 928 MPLSMNBEDS0 5E Switch. There is a current process in the 5E switch for setting the ten digit unconditional trigger automatically. Upon completion of this process and the port activity, this allows correct routing of calls, even though the translations may or may not have been disconnected. It has been confirmed that translation’s should be completed by the frame due time indicated on the Port order.

Because of the delay in time, investigating this exact situation was not possible. Qwest has not received any additional examples of order activity in which the triggers or translations have caused problems for the end users. It has been determined that this was an isolated incident. Systems occasionally do have problems and in this instance, perhaps the triggers were not set properly. The process of setting triggers and releasing translations has been verified and is in order, so it is unclear as to why this situation occurred. Provided the mechanized triggers are being set properly, this concern of not pulling the translation’s in association with acceptance of the loop, should not affect the end user’s service and their ability to receive incoming calls, even if there is a delay in pulling the translation’s.

Eschelon has been advised that should they incur the situation in the future, they can contact Qwest for immediate investigation. Should the CLEC require immediate release of translations upon activation of the Port, they may contact the ISC Call Center, 888-796-9087and open up an Escalation ticket. The Escalation representative can then contact the appropriate Qwest department to have the translations removed. The CLEC may contact the ISC Call Center 48 hours prior to and after the port due date. After that time, the CLEC must contact the Qwest AMSC repair group 1 800-223-7881 for assistance.

Sincerely, Joan Wells LNP Process Manager


Open Product/Process CR 5579345 Detail

 
Title: Repair process for multiple lines on single report (Reference Systems CR # SCR112101 2)
CR Number Current Status
Date
Area Impacted Products Impacted

5579345 Completed
12/12/2001
Ordering Unbundled Loop, UNE-P, Resale
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: McMahon, Cheryl
Director:
CR PM:

Description Of Change

Develop a consistent repair process for receiving information about multiple lines for a single customer on a single report, without the use of facsimiles. In some instances, when Eschelon calls Qwest about a repair issue for a multiple-line account, Qwest will require Eschelon to call regarding the main line and then send information regarding the subsequent lines by facsimile. This is time consuming and inefficient for both parties. In other cases, the Qwest representative will take the information over the telephone for all of the lines. The latter approach is more efficient. In any case, a consistent approach is needed so that Eschelon may adequately train its employees in the proper procedure.

Modifications

08/22/01 - Added Systems Action Item 314, Get a copy of the process in the AMSC

08/22/01 - Added Systems Action Item 315, Set up an internal meeting to discuss the AMSC process throughout Qwest

08/22/01 - Added Systems Action Item 271, Determine why the CLEC's call in a trouble ticket on the first TN and then have to fax in trouble tickets for any other

08/22/01- Added Systems Action Item 323, check into how the retail business handles trouble with more than three lines.


Status History

06/06/01 - CR received by Lynne Powers of Eschelon

06/06/01 - Status changed to New to be evaluated

07/09/01 - Status changed to New - to be clarified

07/13/01 - Additional information requested of Eschelon to sight specific examples (MR-NH)

08/09/01 - CR being addressed currently by Qwest repair process personnel. (MR)

08/15/01 - CLEC CMP Meeting Product & Process, Eschelon advised that they would escalate Qwest's response of 07/31/01

09/04/01 - Draft Response issued to Eschelon

09/05/01 - Eschelon provided feedback on draft response - clarification meeting to be held

09/10/01 - Clarification Meeting Held. Eschelon would accept Qwest's response with revised language.

09/14/01 - Qwest's response issued to Eschelon

09/19/01 - CMP Meeting - Qwest presented its response. Eschelon requested that the response be discussed by the CLEC's at October's CMP Meeting.

10/17/01 - CMP Meeting: Qwest to revisit response presented in meeting; regarding issues for circuit credits, and restriction of placing only 5 circuits on a single ticket. No "Current Status" change.

11/01/01 - Revision, dated October 31, 2001, to the Qwest September 14, 2001 response was transmitted to the CLEC Community

11/09/01 - Issued revised response dated 11/7/01 to Eschelon. Response will be distributed to the CLEC Community and posted to the WEB.

11/14/01 - CMP Meeting - It was agreed that the CR could be placed into CLEC Test. It was agreed that Qwest would work with Eschelon to develop a System CR for modifying WFA to accept credits for multiple circuits on a single trouble ticket.

11/21/01 - Systems CR (SCR112101-2) drafted by CRPM and submitted for modifying WFA to accept credits for multiple circuits on a single trouble ticket.

12/12/01 - CMP Meeting - CLEC community agreed to change "Current Status" to "Completed."


Project Meetings

09/10/01 - A meeting was held on 9/10/01 to discuss CR5579345. Attendees: Kathy Stichter - Eschelon, Nancy Hoag, Chris Henderson, Lynn Stecklein - Qwest. Kathy requested clarification on the Qwest response regarding Unbundled Loop Services and how trouble is reported. Chris Henderson provided clarification on Qwest's policy. Kathy agreed to accept our response if Qwest agreed to revise/reword the verbiage associated with this issue. A supplement to the response will be provided by Nancy and Chris by 9/12/01.

Stichter, Kathleen L. on 09/05/2001 02:11:31 PM

To: lsteckl@qwest.com, mrossi@qwest.com cc: "Powers, F. Lynne" , "Clauson, Karen L." , "Walberg, Loren"

Subject: FW: CR#5579345 - Repair Process for multiple lines on single report

Lynn, The response is confusing. I need clarification. My major concern is design services which equates to unbundled loop for Eschelon. Does this response say: For Unbundled Loop Services, one trouble ticket will be issued for each separate case of trouble. Qwest inputs one case of trouble then gives that ticket number to the CLEC. The CLEC then faxes the additional cases of trouble to Qwest. The ticket number from the first case of trouble must be on the fax to be used as a cross-reference on all other cases of trouble. or For Non-Designed, Designed and Retail Services, multiple trouble reports will be accepted on a single repair ticket if all three (3) of the following criteria are met: 1. Same, exact trouble on each line, i.e. static on TN 333-333-3333, 333-333-3334 and 333-333-3335. 2. Same end user location 3. Same customer name for end user

There is a restriction on Designed Service trouble reports of five (5) cases of trouble per single repair ticket. No restrictions exist for Non-Designed Services. Please let me know. Either way the response does not meet our needs. What Eschelon is looking for is to report as many circuits (unbundled loops) for the same customer at the same address with one call. Qwest can issue as many tickets as it needs to issue but Eschelon should not have to fax additional circuits to Qwest when a customer has multiple circuits in trouble. I find it hard to believe that a Retail customer would need to fax information to Qwest on multiple circuits in trouble. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com


CenturyLink Response

Wholesale Product Marketing

November 7, 2001

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc

CC: Matthew Rossi

RE: CR #5579345 – Repair process for multiple lines on single report.

This letter is in response to your CLEC Change Request Form #5579345 dated June 6, 2001. It includes the updates that were agreed to in a joint meeting held with Qwest and Eschelon on September 10, 2001.

Qwest is providing procedures detailed in this letter to address multiple circuits on a single trouble ticket. Credit for circuit outages are also addressed.

? Change Request: “Repair process for multiple lines on single report Develop a consistent repair process for receiving information about multiple lines for a single customer on a single report, without the use of facsimiles. In some instances, when Eschelon calls Qwest about a repair issue for a multiple-line account, Qwest will require Eschelon to call regarding the main line and then send information regarding the subsequent lines by facsimile. This is time consuming and inefficient for both parties. In other cases, the Qwest representative will take the information over the telephone for all of the lines. The latter approach is more efficient. In any case, a consistent approach is needed so that Eschelon may adequately train its employees in the proper procedure.”

Qwest Response:

Qwest has developed a process for handling multiple ticket requests which will provide an option to the CLECs to either fax multiple requests or remain on line with the Repair Employee while the tickets are submitted.

Related “Trouble”

For Wholesale, Non-Design and Design Services, including Unbundled Loops, multiple trouble reports will be accepted on a single repair ticket if all three (3) of the following criteria are met:

- Same, exact trouble on each line, i.e. static on TN 333-333-3333, 333-333-3334 and 333-333-3335. - Same end user location - Same customer name for end user

There is a restriction on Design Services, including Unbundled Loops; trouble reports of five (5) cases of trouble per single repair ticket. No restrictions exist for Non-Design Services.

Unrelated “Trouble”

If the CLEC answers “no” to any of these three questions, then individual trouble reports must be submitted.

One trouble ticket will be issued for each separate case of trouble. Qwest will offer the option to the CLEC to input one case of trouble and fax the additional cases of trouble to Qwest. The ticket number from the first case of trouble must be on the fax to be used as a cross-reference on all other cases of trouble. If the CLEC chooses not to fax additional cases of trouble, the CLEC may remain on the line with the Repair Employee to submit all trouble tickets.

The CLEC is responsible to isolate trouble to a specific line when multiple lines exist for a customer at one location. If the CLEC requests, Qwest will perform the trouble isolation and appropriate charges will apply.

Credits for Circuit Outages

Qwest currently uses the WFA (Work Force Administrator) system for all trouble reporting. It was designed to only handle a single circuit per trouble report. Consequently, credits for circuit outages are limited to a single circuit per trouble report. The CLEC may request individual tickets to ensure credit, as appropriate, for each affected circuit.

Qwest is willing to assist Eschelon or any other CLEC in the preparation of a system Change Request that would investigate options to modify WFA to correct current deficiencies in the system for providing credits for more than one circuit.

Sincerely, Cheryl McMahon Senior Process Analyst

October 31, 2001

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc

CC: Matthew Rossi Chris Henderson

RE: CR #5579345 - Repair process for multiple lines on single report.

This letter is in response to your CLEC Change Request Form #5579345 dated June 6, 2001. It includes the updates that were agreed to in a joint meeting held with Qwest and Eschelon on September 10, 2001.

* Change Request: "Repair process for multiple lines on single report. Develop a consistent repair process for receiving information about multiple lines for a single customer on a single report, without the use of facsimiles. In some instances, when Eschelon calls Qwest about a repair issue for a multiple-line account, Qwest will require Eschelon to call regarding the main line and then send information regarding the subsequent lines by facsimile. This is time consuming and inefficient for both parties. In other cases, the Qwest representative will take the information over the telephone for all of the lines. The latter approach is more efficient. In any case, a consistent approach is needed so that Eschelon may adequately train its employees in the proper procedure."

Qwest Response:

Qwest currently uses the WFA (Work Force Administrator) system for all trouble reporting. This system is a Telecordia software system developed during the mid-1980’s time frame. It was designed to only handle a single circuit per trouble report. Any modifications to the software system for handling multiple circuits per trouble report would require a software modification by Telecordia. The cost for modification is roughly estimated in the hundreds of thousands of dollars. Currently, Qwest has no plans to modify WFA to accept multiple circuits per trouble report.

Qwest is providing procedures detailed in this letter to address multiple circuits on a single trouble ticket. Credit for circuit outages are also addressed.

Related "Trouble"

For Wholesale and Retail, Non-Designed and Designed Services, including Unbundled Loops, multiple trouble reports will be accepted on a single repair ticket if all three (3) of the following criteria are met:

- Same, exact trouble on each line, i.e. static on TN 333-333-3333, 333-333-3334 and 333-333-3335. - Same end user location - Same customer name for end user

There is a restriction on Designed Service, including Unbundled Loops; trouble reports of five (5) cases of trouble per single repair ticket. No restrictions exist for Non-Designed Services that meet the above criteria.

Unrelated "Trouble"

If the co-provider answers "no" to any of these three questions, then individual trouble reports must be submitted. If the co-provider has additional information that Qwest has no system access to, the information must be "faxed" to the appropriate repair center.

One trouble ticket will be issued for each separate case of trouble. Qwest inputs one case of trouble then gives that ticket number to the CLEC or Retail end user. The CLEC or Retail end user then faxes the additional cases of trouble to Qwest. The ticket number from the first case of trouble must be on the fax to be used as a cross-reference on all other cases of trouble.

The co-provider is responsible to isolate trouble to a specific line when multiple lines exist for a customer at one location. If the co-provider requests, Qwest will perform the trouble isolation and appropriate charges will apply.

Credits for Circuit Outages

Currently, only the circuit listed on the trouble ticket will receive credit. If multiple loops were put on one ticket, and multiple outages occurred, the CLEC would need to contact their Account Manager for additional credits.

To ensure process compliance by the Qwest Repair Center personnel, the center management has initiated a review of these Methods and Procedures.

Sincerely,

Chris Henderson Senior Process Analyst

Ann Danielsen Manager Process Management

-

September 14, 2001 Wholesale Product Marketing Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc

CC:Matthew Rossi Chris Henderson

RE: CR #5579345 Repair process for multiple lines on single report.

This letter is in response to your CLEC Change Request Form #5579345 dated June 6, 2001. It includes the updates that were agreed to in a joint meeting held with Qwest and Eschelon on September 10, 2001.

Change Request: Repair process for multiple lines on single report Develop a consistent repair process for receiving information about multiple lines for a single customer on a single report, without the use of facsimiles. In some instances, when Eschelon calls Qwest about a repair issue for a multiple-line account, Qwest will require Eschelon to call regarding the main line and then send information regarding the subsequent lines by facsimile. This is time consuming and inefficient for both parties. In other cases, the Qwest representative will take the information over the telephone for all of the lines. The latter approach is more efficient. In any case, a consistent approach is needed so that Eschelon may adequately train its employees in the proper procedure.

Qwest Response: For Wholesale and Retail, Non-Designed and Designed Services, including Unbundled Loops, multiple trouble reports will be accepted on a single repair ticket if all three (3) of the following criteria are met:

Same, exact trouble on each line, i.e. static on TN 333-333-3333, 333-333-3334 and 333-333-3335. Same end user location Same customer name for end user

There is a restriction on Designed Service, including Unbundled Loops, trouble reports of five (5) cases of trouble per single repair ticket. No restrictions exist for Non-Designed Services.

If the co-provider answers “no” to any of these three, then individual trouble reports must be submitted. If the co-provider has additional information that Qwest has no system access to, the information must be “faxed” to the appropriate repair center.

The co-provider is responsible to isolate trouble to a specific line when multiple lines exist for a customer at one location. If the co-provider requests, Qwest will perform the trouble isolation and appropriate charges will apply.

One trouble ticket will be issued for each separate case of trouble. Qwest inputs one case of trouble then gives that ticket number to the CLEC or Retail end user. The CLEC or Retail end user then faxes the additional cases of trouble to Qwest. The ticket number from the first case of trouble must be on the fax to be used as a cross-reference on all other cases of trouble.

To ensure process compliance by the Qwest Repair Center personnel, the center management has initiated a review of these Methods and Procedures.

Sincerely,

Nancy J. Hoag Wholesale Product Manager

July 13, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom, Inc

CC:Matthew Rossi Chris Henderson

RE: CR #5579345 Repair process for multiple lines on single report.

This letter is in response to your CLEC Change Request Form #5579345 dated June 6, 2001. Change Request: Repair process for multiple lines on single report Develop a consistent repair process for receiving information about multiple lines for a single customer on a single report, without the use of facsimiles. In some instances, when Eschelon calls Qwest about a repair issue for a multiple-line account, Qwest will require Eschelon to call regarding the main line and then send information regarding the subsequent lines by facsimile. This is time consuming and inefficient for both parties. In other cases, the Qwest representative will take the information over the telephone for all of the lines. The latter approach is more efficient. In any case, a consistent approach is needed so that Eschelon may adequately train its employees in the proper procedure.

Qwest Response: For both Non-Designed and Designed Services, except for Unbundled Loops, multiple trouble reports will be accepted on a single repair ticket if all three (3) of the following criteria are met:

1. Same, exact trouble on each line, i.e. static on TN 333-333-3333, 333-333-3334 and 333-333-3335. 2. Same end user location 3. Same customer name for end user

There is a restriction on Designed Service trouble reports of five (5) cases of trouble per single repair ticket. No restrictions exist for Non-Designed Services. If the co-provider answers (no) to any of these three, then individual trouble reports must be submitted. If the co-provider has additional information that Qwest has no system access to, the information must be (faxed) to the appropriate repair center.

The co-provider is responsible to isolate trouble to a specific line when multiple lines exist for a customer at one location. If the co-provider requests, Qwest will perform the trouble isolation and appropriate charges will apply.

For Unbundled Loop Services, one trouble ticket will be issued for each separate case of trouble. Qwest inputs one case of trouble then gives that ticket number to the CLEC. The CLEC then faxes the additional cases of trouble to Qwest. The ticket number from the first case of trouble must be on the fax to be used as a cross-reference on all other cases of trouble.

To ensure process compliance by the Qwest Repair Center personnel, the center management will conduct a review of these Methods and Procedures. Sincerely,

Nancy J. Hoag Wholesale Product Manager


Open Product/Process CR PC080301-1 Detail

 
Title: Identification of CSR cuscode process
CR Number Current Status
Date
Area Impacted Products Impacted

PC080301-1 Completed
8/15/2001
TBD Other
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Thacker, Michelle
Director:
CR PM:

Description Of Change

When a CLEC looks in IMA for a CSR (Customer Service Record) at times they find more than 1 live account with different cus codes for the same TN. There is no way for the CLEC to determine which live account to use when issuing the LSR. This causes the CLEC to issue the LSR on the incorrect account. Therefore, causing flow through issues and ultimately delays in service provisioning, which becomes customer affecting. Until the systems CR for IMA is worked Qwest should provide a documented process advising who to contact at Qwest that can identify which account established most recently. This would allow the CLEC to issue their LSR on the correct account.


Status History

8/03/01 - Updated CR sent to Kathy Stichter of Eschelon

8/03/01 - Status changed to New – To be Reviewed

8/03/01 - Updated CR sent to Kathy Stichter of Eschelon

8/06/01 - CR discussed by the internal Qwest CR review team and owner designated

8/09/01 - CR status will be given at the August CICMP Meeting

8/10/01 - Conference call held with Eschelon

8/15/01 - CLEC CMP Meeting Product & Process CR PCCR080301-1. Response was provided in the separate hand-out and issued. The response was accepted. Eschelon agreed to close. Closed


Project Meetings

August 10, 2001

Description of the change was reviewed. Eschelon was looking for a process advising who to contact at Qwest to identify the correct account when issuing a LSR. Qwest advised that Eschelon should contact the Interconnect Service Center at 1888-796-9087. Eschelon is to advise the Agent to process the LSR and make a referral to Order Resolution to correct account information. Qwest providing the contact point met with Eschelon’s expectations. Michelle will issue her formal response to the Change Request. Eschelon expressed a concerned on two accounts with RSID and ZSID issue. Details of the exact problem were not known and Eschelon was requested to research and present the issue via another CR, or at the Monthly Meeting. There is currently a systems Change Request, SCCR073001-4 Qwest will issue formal position to Matt Rossi week of 8/13/01


CenturyLink Response

August 13, 2001

Kathleen Stichter ILEC Relations Manager Eschelon Telecom, Inc

This letter is in response to the following CLEC Change Request Forms #PCCR080301-1 dated July 30, 2001. This Change Request pertains to the Duplicate CSR (one CSR for ZCID account and one CSR for RSID account).

Change Request: “When a CLEC looks in IMA for a CSR (Customer Service Record) at times they find more than 1 live account with different cus codes for the same TN. There is no way for the CLEC to determine which live account to use when issuing the LSR. This causes the CLEC to issue the LSR on the incorrect account. Therefore, causing flow through issues and ultimately delays in service provisioning, which becomes customer affecting. Until the systems CR for IMA is worked Qwest should provide a documented process advising whom to contact at Qwest that could identify which account established most recently. This would allow the CLEC to issue their LSR on the correct account.”

Response:

? If CLEC should encounter two CSRs when attempting to process an LSR, a call should be placed to the Interconnect Service Center (ISC) for assistance. The telephone number is 1-888-796-9087.

? The ISC agent will assist the CLEC by determining which CSR the CLEC needs to use to process their LSR.

? The ISC agent, if unable to assist the CLEC by determining the appropriate CSR or needs further investigation to clear the duplicate CSR problem will make a referral to the Customer Service Inquiry and Education Center for further assistance.

? A MCC (Multi Channel Communicator) will be sent to ISC personnel advising of this process upon release of this notification.

Sincerely

Michelle Thacker Process Specialist


Open Product/Process CR PC090601-1 Detail

 
Title: Written process for migration from CLEC to Qwest retail (Formerly Product & Process Action Item 32)
CR Number Current Status
Date
Area Impacted Products Impacted

PC090601-1 Completed
12/12/2001
TBD
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

Written process for Migration from CLEC to Qwest Retail

CLEC to Resale same CLEC ,e.g., customer on net with current CLEC has unbundled loop going to resale)

Resale to Resale ,e.g., same CLEC with customer moving from one central office to another central office


Status History

07/10/01 - During the CLEC to CLEC conversion interim call, it was asked that Qwest provide in writing the process that is in place to migrate from CLEC to Qwest Retail

08/31/01 - Draft response sent to Eschelon

09/06/01 - Eschelon provided comment to Qwest's response. Eschelon would like to see the back-end process.

09/19/01 - CMP Meeting - Qwest provided status update Eschelon requested that all CLEC's be involved in review. Qwest advised that a review meeting was re-scheduled for 09/25/01.

09/25/01 - Clarification Meeting took Place with CLEC's (Eschelon, Sprint, AT&T).

10/05/01 - This CR will be addressed by Toni Dubuque's quality team. Her team will provide status as it occurs

10/17/01 - CMP Meeting: CLEC community & Qwest agreed to address this CR independent of the Qwest Quality Team. Response to be incorporated in CR database. No change to "Current Status."

11/06/01 - Issued draft response dated 11/6/01.

11/14/01 - This issue was moved to CLEC Test. A response will be provided by Qwest as to when and where this will be documented in the PCAT.

12/06/01 - Formal response (dated 11/06/01) transmitted to the CLEC community.

12/12/01 - CMP Meeting - CLEC Community agreed to change "CR Status" to "Completed."


Project Meetings

9-25-01 1:30 MDT Introduction of Attendees Alignment/Clarification Meeting Kathy Stichter Eschelon Bonnie Johonson Eschelon Lynne Powers Eschelon Nancy Hoag Qwest Sandy Evans Sprint Donna Osborne - Miller AT&T Carolyn Brown Qwest Kit Thomte Qwest Russ Urevig Qwest

Kit introduced the attendees as identified above Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested}

Kit reviewed the PCCR that had been received and outlined the activities that had transpired over the last few weeks. Those activities included an initial response from Nancy Hoag at Qwest that provided the up front process. Kathy Stichter responded that Eschelon was actually looking for the back end process that includes: When the technicians go out to install new loops do they immediately port number(s), immediately get concurrence of number(s), what is the down time for the customer(s) and how do the technicians coordinate this. This has also been referred to Toni Dubuque to be addressed in the quality team she is forming. Lynn Powers clarified that everyone needs to understand how the process works today so the quality improvement team can use the existing process as a standard to allow for improvement within the process and minimize downtime for the customers. Providing the process will help Eschelon conduct their aspect of business in conjunction with Qwest. Confirm Areas & Products Impacted {read from change request, modify if needed} The request was clarified to be the following categories that need the existing process outlined *CLEC to Qwest Retail *CLEC to Resale same CLEC ,e.g., customer on net with current CLEC has unbundled loop going to resale) *Resale to Resale ,e.g., same CLEC with customer moving from one central office to another central office

Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} An inquiry was made whether Russ would be the correct person to look at the whole process. The group determined that with Carolyn and Char Cameron and Joan Smith (retail input) Russ Urevig and Mallory Paxton the group should be able to address the request.

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)} Providing the process associated with the three * items identified above will be the catalyst for the quality improvement team.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts}

Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when} Qwest and the CLEC customers are anxious to identify the processes, the time line will be updated based on a subsequent meeting that is scheduled for 10-01-01

Stichter, Kathleen L. on 09/06/2001 03:03:09 PM To: kthomte@qwest.com Subject: FW: Action Item 32

Kit, What we were actually looking for was the back end process. When technicians go out to install new loops do they immediately port numbers(s), immediately get concurrence of number(s), what is the down time for the customer(s) and how do the technicians coordinate this? We are going to tie this issue to the Toni Dubuque quality team that Toni is forming to identify and address problems with Qwest end to end processes as they relate to port in and port within. Thanks

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com


CenturyLink Response

Wholesale Process Management

November 06, 2001

Ms. Kathleen Stichter Eschelon Telecom

Dear Ms. Stichter:

A conference call was conducted with Eschelon on September 25, 2001 at which time Qwest Product and Process reviewed and responded to the PC090601-1, Title of Change: Written Process for migration from CLEC to Qwest Retail. Description of Change: During CLEC to CLEC conversion interim call, it was asked that Qwest provide in writing the process that is in place to migrate from CLEC to Qwest Retail. During the course of the call, it was determined that the actual request goes beyond the migration from a CLEC to Qwest Retail. Issues of concern are as follows: * CLEC to Qwest Retail * CLEC to Resale same CLEC, e.g., (customer on net with current CLEC has unbundled loop going to Resale.) ( Port In to Resale, same CLEC) * Resale to Resale, e.g., same CLEC with customer moving from one central office to another central office. (Port Within T&F Resale) This response letter outlines the three processes as listed above.

CLEC to Qwest Retail 1. Sale Consultant * Negotiates New Connect Order with end user * Obtains LOA (Letter of Authorization) / TPV * Places order on hold * Submits notification to the Retail Support Center 2. Retail Support Center * Receives notification of pending competitive order, verifies LOA/TPV, determines competitive type (Resale, Centrex Resale, LNP, etc.) * Completes form(s) when appropriate (Loss Notification, LSR) and submits to CLEC. * Receives FOC from CLEC * If reclaiming Unbundled Loop and there are multiple loops with multiple Tn’s request information from Wholesale Support * Issue disconnect of Unbundled Loop(s) related to the Competitive New Connect * Retrieves order, adds appropriate FIDs/USOCs and issues Port In to Qwest Retail order * Advises end user of firm DD and negotiates premise visit if needed. * Prepares and submits bill to end user 3. Npac * Receives 2 subscriptions, 1) Old provider CLEC 2) New Provider Qwest 4. Wholesale * Support Center will provide Retail with information on multiple loops with multiple Tn’s * Issue loss report for UBL (mechanized) 5. Network * If no Unbundled Loop to reclaim, Installer Visit required * Unbundled Loop reclamation, Lift and Lay in Central Office, or Cross Connect out in the field. * Order has the following FDT (Frame Due Time): 8:00am if Installer Access Time is 8:00 – 12:00 or All Day 12:01pm if Installer Access Time is 12:00 – 5:00 * If Installer is at premise and subscription has not been completed, but has been concurred by the CLEC (or 18 NPAC hours have been met), the Installer will call to have subscription completed in order to test and complete work order. * If port needs concurrence before activation, the Support Center will contact the CLEC for concurrence and have port activated. * Verifies dial tone up to the Network Interface and completes inside wiring as needed. 6. End User * Advised may experience out of service condition due to port activity * Advised Installer visit to premise may be needed. (If unable to reclaim an unbundled loop or other changes requested.) 7. Current Clec * CLEC receives LSR * Determines DD and send FOC to Qwest * Creates disconnect service Order to Port Out * Sends subscription to NPAC * Service Order completed on the DD in the CLEC requested switch at FDT of 5pm. * Discontinues billing end user CLEC to Resale (Same CLEC) (Port In Resale) 1. End User * Signs LOA and submits request to Reseller * Reseller has advised end user of firm DD * Advised may experience out of service condition due to port activity. * Upon completion of port activity, receives bill from New Provider/Reseller 2. Reseller * Wins new end user business * Submits LSR to Qwest * Receives FOC(Firm Order Confirmation) from Qwest with Firm DD * May request reuse of existing Unbundled Loop facilities * If Qwest is unable to reclaim Unbundled Loop for reuse of facilities, premise visit by Reseller technician is needed * Advises end user of firm DD and negotiates premise visit if needed. * Prepares and submits bill to end user 3. Qwest Wholesale * Receives LSR from Reseller * Submits LSR to End user current CLEC with FDT of 5pm, allowing for overlapping of translations until port complete * Receives FOC from current CLEC and creates FOC to Reseller * Add positive Remark entry on FOC if unable to reuse existing facilities (if reseller requested reuse). * Creates New Connect service order to Port In TN with due date based on availability in Appointment Scheduler . i.e.. AM, PM, All Day 8-5p (If premise visit required) * Creates disconnect service order if reusing facilities from an Unbundled loop and relates to New Connect service order. Order completion creates mechanical Loss Report * Submits port subscription to the NPAC * Service Order completed on the DD in Qwest Switch. 4. Npac * Receives 2 subscriptions, 1) Old provider CLEC 2) New Provider Qwest 5. Network * No Unbundled Loop to reclaim, requires Installer Visit based on Appointment Scheduler * Unbundled Loop reclamation, Lift and Lay in Central Office, or Cross Connect out in the field. * Completion dependent upon access time indicated by Appointment Scheduler * Order has the following FDT (Frame Due Time): 8:00am if Installer Access Time is 8:00 – 12:00 or All Day 12:01pm if Installer Access Time is 12:00 – 5:00 (Access Time may be dependent upon Central office limitations.) * If Installer is at premise and subscription has not been completed, but has been concurred by the CLEC (or 18 NPAC hours have been met), the Installer will call to have subscription completed in order to test and complete work order. If port needs concurrence before activation, the Escalation Group will contact the CLEC for concurrence and have port activated. * Installer verifies dial tone up to Network Interface 6. Current Clec * CLEC receives LSR * Determines DD and send FOC to Qwest * Creates disconnect service Order to Port Out * Sends subscription to NPAC * Service Order completed on the DD in the CLEC requested switch at FDT of 5pm. * Discontinues billing end user Resale to Resale (Port Within T&F) 1. Reseller * Negotiates End User T&F * Submits LSR to Qwest * Can provide access time per Appointment Scheduler * Received FOC(Firm Order Confirmation) from Qwest with Firm DD * Advises end user of firm DD * Negotiates premise visit as needed for inside wiring * Prepares and submits bill to end user 2. End User * Advised may experience out of service condition due to port activity * Advised Installer visit to premise may be needed. (If unable to reclaim an unbundled loop or other changes requested.) 3. Qwest Wholesale * Receives LSR from Reseller * Creates service order to Port Within (T&F) service with due date based on availability in Appointment Scheduler. i.e.. AM, PM, All Day 8-5p , if installation and premise visit required. FDT 8am. * Disconnect at current address & connection of service at new address must be done the same day (no dual or delayed service). * Creates FOC to Reseller * Submits port subscription to the NPAC * Service Order completed on the DD in new Qwest Switch and disconnected in old Qwest Switch. 4. Npac Receives 2 subscriptions, 1) Old provider Qwest 2) New Provider Qwest 5. Network * May requires Installer Visit and access based on Appointment Scheduler (Access can be dependent upon Central office limitations.) * Order has the FDT (Frame Due Time) of 8am. * Wire to Network Interface and verify dial tone. (No inside wiring) * Completes service order request

In most switch types the 10 digit mechanized trigger is automatically set by Qwest. Correct call routing will take place until such time that the actual switch translations are disconnected from the originating switch. This overlap of switch translations helps to ensure a smooth number port transition, until both the loop and or the number port are completed. The complete service order process of port in/port within should be completed no later than the 5pm access time, based on availability in Appointment Scheduler.

Sincerely, Joan Wells LNP Process Manager


Open Product/Process CR PC083001-2 Detail

 
Title: Process to ensure Qwest service managers are provided with and participate in training for resolving customer affecting issues and outages.
CR Number Current Status
Date
Area Impacted Products Impacted

PC083001-2 Completed
12/12/2001
Ordering, Billing, Repair N/A
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Sheahan, Steven
Director:
CR PM: Thomte, Kit

Description Of Change

Currently Qwest provides training on customer-impacting issues relating to products and services. However, it does not ensure that service managers are allowed to and/or do participate in the training. Instead, in some cases, the managers either do not attend at all or are provided the documentation only. As a result, the service managers can not efficiently and effectively resolve customer-impacting issues in the shortest possible time frame. Please implement a process to ensure and document that service managers participate in all Qwest provided training as it relates to products and services that impact CLECs and their customers.


Status History

08/30/01 - CR received from Kathy Stichter of Eschelon

08/30/01 - Status changed to New – to be clarified

08/30/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

09/21/01 - Clarification Meeting Scheduled for 05 Oct 01

10/05/01 - Clarification Meeting conducted with Eschelon

10/17/01 - CMP Meeting: Qwest conducted clarification with CLEC community. "Current Status" changed to Evaluation. Qwest to prepare draft response.

11/01/01 - Draft response dated October 29, 2001 issued to Eschelon, & CLEC community notified of draft response

11/14/01 - CMP Meeting - it was agreed that th CR could be moved into "CLEC Test."

11/21/01 - Qwest Final Response (dated October 29, 2001) transmitted for CLEC community distribution.

12/12/01 - CMP Meeting - CLEC Community agreed to change "CR Status" to "Completed." Toni Dubuque, Qwest to address action item regarding present assignment of Qwest service personnel on the Eschelon account (i.e, two (2) positions for sales, and two (2) positions for service), and feasibility of re-assigning service personnel to focus solely on Eschelon service issues (i.e., propose all four (4) positions address service).


Project Meetings

Alignment/Clarification Meeting

1:00 p.m. (MDT) / Friday, 05 October 2001 Teleconference call TELE: 1-866-289-7092 CODE: 7411826 # PCCR083001-2 Process to ensure Qwest service managers are provided with & participate in training for resolving customer affecting issues & outages.

Attendees Cathy Stichter Steven Sheahan Peter Wirth

Introduction of Attendees Attendees were introduced. Qwest representative Steven Sheahan was designated the “Subject Matter Expert” (SME) for the subject CR. Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Concurrence was received from both Eschelon and Qwest parties. Questions were raised by Steven Sheahan, Qwest to Eschelon regarding specific training issues of concern. Eschelon expressed concern regarding the volume of changes and associated documentation that the Qwest Service Manager needs to assimilate, in addition to performing routine daily duties.

Confirm Areas & Products Impacted {read from change request, modify if needed} No selected “Products Impacted” were indicated on the CR. However, Eschelon indicated that “All” products are potentially affected.

Confirm Right Personnel Involved {ensure the Qwest Product SMEs can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Concurrence was received from both Eschelon and Qwest parties regarding appropriate involved personnel.

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)} Eschelon is expecting a response from Qwest identifying: (1) current procedures used to meet the needs of the CR; and (2) any modifications or changes proposed by Qwest to allow Service Managers to more efficiently and effectively resolve customer-impacting issues via training.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts}

Eschelon did not identify any dependent CRs associated with the subject CR.

Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when} Qwest will internally discuss CR with all supporting SME staff, and discuss the CR in the next monthly CMP meeting (October 17, 2001).


CenturyLink Response

October 29, 2001 Wholesale Product/Process Stephen Sheahan, Qwest

This letter is in response to CLEC change request form PC083001-2 dated August 30, 2001.

Change Request: Qwest currently provides training on customer-impacting issues relating to products and services. However, it does not ensure that Service Managers are allowed to and/or participate in the training. Instead in some cases the managers either do not attend at all or are provided the documentation only. As a result, the Service Managers cannot efficiently and effectively resolve customer-impacting issues in the shortest possible time frame. Please implement a process to ensure and document that the Service Managers participate in all Qwest provided training as it relates to products and services that impact CLECs and their customers.

Qwest Response:

Qwest has in place individualized training plans for all of its Service Managers as it relates to Products, Processes and Services that are customer and non-customer impacting. Qwest also holds mandatory training sessions for Service Managers when substantial changes in process or products are made or when a new product is introduced. In some cases testing of the Service Manager is conducted after completion of a training module to demonstrate a minimum level of competence.

When minor changes in process or product offerings are made, Qwest provides via email communicator documentation that allows the Service Manager a point of reference to be able to identify the change in product or process. Also it includes the name of SMEs necessary to facilitate prompt investigation and response to CLEC customer questions.

Qwest management reviews training plans with individual Service Managers on a quarterly basis. Training is a component of the Service Managers overall rating to determine the level of attainment achieved in the Qwest quarterly bonus plan. Management reviews Service Manager training progress and tailors additional training programs, as necessary to better meet requirements associated with the Service Manager’s assigned CLEC accounts.

Sincerely,

Stephen P. Sheahan Qwest Wholesale Customer Service Operations


Open Product/Process CR PC083001-1 Detail

 
Title: Allow customers to move and change local service providers at the same time. (reference Systems CR # SCR101901 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC083001-1 Completed
4/17/2002
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Berry, Harriett
Director:
CR PM: Thomte, Kit

Description Of Change

The current Qwest process states that when a customer moves and wants to change local service providers they must first convert to the new local service provider with a subsequent move order or move with their current local service provider and subsequently convert to the new local service provider. This causes delays in a customer’s choice to change local service providers. It also forces the customer and/or CLEC to pay processing and installation charges for both a conversion and a move. In addition if the Qwest service order does not post to the CRIS system for the move or conversion in a timely manner, this can cause customer impacting issues due to the fact that the Qwest service order may not be processed accurately. Change Qwest process to allow an end user to select the local service provider of their choice when they move to their new location.


Status History

08/30/01 - CR received from Kathy Stichter of Eschelon

08/30/01 - Status changed to New, to be clarified

08/30/01 - Updated CR sent to Kathy Stichter and Steve Sheahan

09/12/01 - Clarification Meeting Scheduled for 09/17/01

09/17/01 - Clarification Meeting Held

09/26/01 - Qwest's draft response issued to CLEC Community

10/17/01 - CMP Meeting: CLEC community concurred with Qwest long term solution. Qwest to add interim process to response & re-issue. An internal User Request will be issued to initiate permanent change. No "Current Status" change.

11/01/01 - Revised draft response, dated October 31, 2001, transmitted to Eschelon (submitting CLEC).

11/07/01 - Issued updated draft response dated November 7, 2001 to Eschelon and posted to dBase.

11/14/01 - CMP Meeting - The CLEC participants agreed that the manual process can be implemented 12/01/01. IMA Systems CR has been issued SCR 101901-1. It was agreed that the CR could be moved to "CLEC Test."

11/21/01 - Qwest Final Response (dated 10/31/01) transmitted for CLEC community distribution.

12/12/01 - CMP Meeting - Eschelon requested to leave "CR Status" as "CLEC Test." No Eschelon customers were available to test the manual interim procedure detailed within the Qwest response (dated 10/31/01).

01/10/02 - Eschelon submitted example to Qwest indicating potential difficulty with the interim manual process. Harreitt Berry (SME) investigating.

01/16/02 - CMP Meeting - Status update provided indicating that Harriett Berry (SME) is in process of investigating Eschelon example (submited 01/10/02).

02/06/02 - Harriett Berry identified root cause of Eschelon example (submitted 01/10/02) as failure of adherence to interim manual process. Qwest management and staff located in the offending ordering facility were retrained on internal Qwest procedure (MCC issued 11/28/01), Internal Qwest procedure was re-issued (01/21/02) to Qwest Wholesale and Retail personnel.

02/14/02 - Response transmitted to Eschelon example (submitted -1/10/02).

02/20/02 - CMP Meeting - Qwest SME discussed response to Eschelon example. CR status remains in "CLEC Test." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02)

03/05/02 - E-mail from Qwest asking for recent out-of-process examples

03/10/02 - Reply e-mail from Eschelon, planning on having examples this week

03/20/02 - March CMP Meeting: CR to remain in CLEC Test awaiting example from Eschelon. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/01/02 - Sent e-mail to Eschelon asking if they have had an example to test this process

04/01/02 - Reply e-mail from Eschelon stating they are still waiting for their first example

04/17/02 - April CMP Meeting: CLECs agreed to close CR. Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site


Project Meetings

04/01/02 - Reply e-mail from Eschelon stating they are still waiting for their first example

From: "Johnson, Bonnie J." To: Todd Mead , "Stichter, Kathleen L."

Todd, See below!

--Original Message-- From: Todd Mead [SMTP:tmead@qwest.com] Sent: Monday, April 01, 2002 9:46 AM To: Stichter, Kathleen Cc: Johnson, Bonnie Subject: CR Update

Kathy, I am looking for some feedback on two of your CRs that are currently in CLEC Test:

PC083001-1 "Allow customers to move and change local service providers at the same time" Have you had any examples through to test this process? We are waiting for an example. I received information from our internal Provisioning Team that they will be certain to provide me the next customer we have engaging in this activity.

--

03/10/02 Reply e-mail from Eschelon, planning on having examples this week

Subject: RE: FW: PC083001-1 Allow customers to move and change local servi ce providers at the same time. Date: Sun, 10 Mar 2002 16:01:51 -0600 From: "Johnson, Bonnie J." To: Todd Mead , "Stichter, Kathleen L." CC: "Vigoren, Barbara J." , "Schiller, Tina M."

Hi Todd, I believe I should have some examples this week. Kathy will be back on 3/19/02.

Bonnie -

--

03/05/02 E-mail from Qwest asking for recent out-of-process examples

Subject: PC083001-1 Allow customers to move and change local service providers at the same time. Date: Tue, 05 Mar 2002 08:31:08 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: Kathleen Stichter

Kathy, I have taken over from Pete Wirth as the CRPM for this CR. My current understanding is that we are waiting for an Eschelon customer to test this manual procedure to ensure the process is working as originally designed?

Please let me know if that is your understanding of the current status and also, whether there have been any recent examples from Eschelon to test the manual procedure.

Thanks

Todd

--

Subject: Re: Example for CR PC083001-1 Date: Thu, 14 Feb 2002 14:58:39 -0700 From: Peter Wirth Organization: Qwest Communications International, Inc. To: "Stichter, Kathleen L." CC: "Berry, Harriett" References: 1

Kathleen;

Harriett Berry, Qwest identified the root cause of the Eschelon example (e-mail below) as a failure of adherence to the interim manual process by a Qwest employee. Qwest management and staff located in the ordering facility were retrained on the internal Qwest procedure (MCC issued on 11/28/01) contained within the Qwest CR response. The internal Qwest procedure was re-issued (01/21/02) to Qwest Wholesale and Retail personnel. Please let me know if any other examples occur regarding this issue. Thanks.

Peter Wirth Product & Process CMP CRPM pwirth@qwest.com 303.896.5190

--

"Stichter, Kathleen L." wrote:

Example of a recent LSR that did not work. This is confidential information not to be shared outside of Qwest CMP.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

--Original Message-- From: Stichter, Kathleen L. Sent: Tuesday, January 08, 2002 7:55 AM To: Johnson, Bonnie J.; 'cmeride@qwest.com' Subject: RE: UT-122101-Tuxedo By Lee-UT138677KMJ-Ver-OC-8014921614

Bonnie, This is the email I sent to Pat Levene yesterday for investigation. I will let you know when I get the information back from Pat Levene.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 Email klstichter@eschelon.com

--

09/17/01 - Attendees Bonnie Johnson - Eschelon Harriettt Berry - Qwest Russ Urevig - Qwest Susie Wells - Qwest Peter Wirth - Qwest

Introduction of Attendees Attendees were introduced. Qwest representatives representing -Resale-- (Mallory Paxton) and -UNE-P- (to be determined) were not available for the meeting. Harriett Berry, Qwest will identify and include missing representatives for further activities regarding the subject CR.

Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Concurrence was received from both Eschelon and Qwest parties. Questions were raised by Russ Urevig, Qwest regarding applicability to -Resale- markets. Eschelon provided clarifications. Harriett Berry (Qwest) will review CR will representatives not in attendance.

Confirm Areas & Products Impacted {read from change request, modify if needed} Harriett Berry, Qwest confirmed selected -Products Impacted,- as appropriate for the CR.

Confirm Right Personnel Involved {ensure the Qwest Product SMEs can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Harriett Berry, Qwest identified the following Qwest personnel to assist in providing a response to Eschelon: - Qwest CLEC Migration Team

Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC- what does Qwest have to do in order to close this CR? (in measurable terms i.e. provide a documented process, change a process to include training etc)} Eschelon is expecting a response from Qwest identifying: (1) current procedures used to meet the needs of the CR (and any required modifications, as feasible); (2) identification of any factors (i.e., regulatory, etc.) that may preclude procedure modifications to meet the CR -Description of Change-; and (3) approximate time table for procedural changes, as applicable.

Identify any Dependent Systems Change Requests {Note any connected CRs and the potential impacts}

Eschelon did not identify any dependent CRs associated with the subject CR.

Establish Action Plan (Resolution Time Frame) {state action required, who will be responsible and by when} Qwest will internally discuss CR with all supporting SME staff to determine time frame for response to Eschelon. Discussions to occur on 24 September 2001 (afternoon).


CenturyLink Response

Qwest Wholesale Product Marketing

October 31, 2001

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc.

This letter is in response to the following CLEC Change Request Forms #PCCR083001-1 and pertains to allowing customers to move and change local service providers at the same time.

Qwest has evaluated the subject Change Request (CR) and has determined the following:

1) Eschelon is correct in their assessment of the Qwest service order procedure for customers that physically change address and desire a new local service carrier for Centrex, Resale and UNE-P products. The current process does require two service orders to accomplish an end user move and migration.

2) We propose combining the two step process so that only one order is issued to concurrently change both customer address and Local Service Provider. The Local Service Request (LSR) would be issued with Activity Type V (for conversion) with the EUMI (End User Move Indicator) populated with Y.

Since Qwest does not currently utilize the EUMI field, an Interconnect Mediated Access (IMA) System software upgrade will be required to implement that field.

3) Qwest is initiating an internal change for the IMA System software upgrade. This change will be managed under the CMP Systems Change Request SCR101901-1.

4) The following manual interim process will be in effect until SCR101901-1 is implemented:

- The co-provider will only need to submit a single LSR for service orders to “change the end user’s provider and move at the same time.”

- This process has been designed specifically for the following: 1) an end user move, change of co-provider, same telephone number, and keeping same product; and 2) end user move, change of co-provider, same telephone number, change product (within same product family only).

- The manual process will require the LSR to contain ACT of V (for conversion as specified), Manual Indicator of Y, and then remarks to provide information regarding the end user move.

- Note that this is a new process in addition to existing processes for porting in and conversion (product conversions, moves, etc.). This process is also for end user conversion and move at the same time and does not include the addition of new lines.

Should you have any questions regarding this response please contact Peter Wirth, CR Project Manager at (303) 294-1642. He can coordinate any follow-up meetings, if necessary, to discuss this response.

Sincerely,

Harriett Berry Qwest CLEC Migration Team

--

MIGRATION/END USER MOVE INTERIM MANUAL PROCESS

Issue one LSR to migrate and move the end user

ACT Type = V Manual Indicator = Y Remarks = Include end user move information including new address


Open Product/Process CR 5608156 Detail

 
Title: Process and Procedures for consistent APOT numbering
CR Number Current Status
Date
Area Impacted Products Impacted

5608156 Denied
9/19/2001
Ordering Unbundled Loop
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Nelson, Steve
Director:
CR PM:

Description Of Change

Please provide a process and procedures for consistent APOT numbering. Qwest apparently uses different conventions in different central offices (“COs”) for numbering APOTs. This leads to problems when, for example, a typist at Qwest copies and pastes information for one CO and uses it for another. Also, there appears to be a discrepancy between physical numbering and the information reflected in TIRKs. To the extent that inconsistencies exist today, please develop and distribute a process for correcting those inconsistencies. The inconsistencies create serious problems for CLECs. For example: In one situation, the augment was labeled at the ICDF as starting with number 1. But, the collocation term sheets and IMA (TIRKS) indicated that the augmented APOT starts at a higher number. Therefore, pending orders could not be completed to the APOT on which they were ordered.


Status History

06/13/01 – CR received from Lynne Powers of Eschelon 6/18/01 – Status changed to New – to be Evaluated

07/09/01 – Status changed to Reviewed – Under Consideration

07/13/01 – Drafted response sent to CICMP team via email (MR)

08/06/01 – Conference call with Steve Nelson and Lynne Powers of Eschelon held to discuss proposed CR response. Additional action taken by Qwest to resolve and respond to this issue.

08/15/01 – CLEC CMP Meeting Product & Process. Qwest advised that additional action items were taken by Steve Nelson and response will be revised and re-released.

08/27/01 - Qwest sent draft response to Eschelon.

08/27/01 - Teleconference held with Eschelon to review response. Eschelon is to obtain their SME's comments.

08/29/01 - Received Eschelon's SME's comments.

08/30/01- Revised draft response issued to Eschelon.

09/19/01 - CMP Meeting - Qwest reviewed its response and advised that they had to deny the request. Eschelon will evaluate whether to escalate .

09/21/01 - Qwest response issued to CLEC Community

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

08/27/01 E-mail Stichter, Kathleen L. wrote:

Kate, Here is Gerry's reply. Gerry is director of our switch operations. Please send this on to whoever needs to see it. Thanks Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com Kathy: When we assign a APOT/CFA we hard wire directly to the ICDF from our UE9000's. By having the APOT's in numerical sequence it allows for our LENS and the PM Terminal/Node Number(which is the APOT/CFA) to match up one to one. Example ...If I have an APOT of PST05 pair 12 for the Orchard CO it matches directly to LEN ORCH 0 00 1 12. By reusing the same numbering, i.e. ALT02 1-300 and PST05 1-300 the PM Terminal/Node Number will not match up with the LEN assignment. Thanks Gerry P.S. I can print out examples at a later date. Gerry


CenturyLink Response

August 28, 2001 Wholesale Product Marketing Ms. Lynne Powers Vice President, Eschelon Telecom

Dear Ms. Powers:

I conducted a conference call with Eschelon on August 6th, 2001 at which time Qwest reviewed and responded to the letter written by myself, dated July 13, 2001. Eschelon clarified their request as, “Can they have sequential DS0 cable counts when they submit an augment for additional 100 DS0 cables.” They do not want 2 different naming conventions that have the same numbering system. Eschelon wants each new cable name to have its own associated cable counts.

According to Gerry Boeke from Eschelon, when they assign an APOT/CFA, they hard wire directly to the ICDF from their UE9000's. By having the APOT's in numerical sequence it allows for their LENS and the PM Terminal/Node Number, which is the APOT/CFA, to match up one to one (i.e...If you have an APOT of PST05 pair 12 for the Orchard CO it matches directly to LEN ORCH 0 00 1 12). By reusing the same numbering (i.e. ALT02 1-300 and PST05 1-300), the PM Terminal/Node Number will not match up with the LEN assignment.

Qwest does not believe it is a realistic expectation that cable counts always match exactly with LENS and Cable Counts. It will not and does not need to do so. Although administration would be easier for Eschelon, this is not practical on the part of Qwest. Existing working circuits are currently operating with different cable counts.

I have worked with John Waltrip, IOF EPOC methods manager, regarding this clarification. John’s response is as follows: “This issue is a scenario where a CLEC places an augment order to supplement facilities already in a given Central Office. The original facilities may have been built based on a cable naming convention that is now superseded (e.g. an original DS0 cable may have been called/counted as ALT02, 1-300); the new convention would carry a name like PDT05, 1-400 (for an additional 400 - or a total of 700). As a result, his response was that our practice is to not attempt a continuous count of old to new cable names for the same comparable circuit, (e.g. establishing the PDT05 with a count of 301-700) for the following reasons:

Our system has been in place for over a year and changes would mess-up live circuits. All CLECs are using this same system, so they rely on it as well. Other interfaces rely on this such as TIRKS, LFACS, etc. Sequence number is not critical when they place orders. The 1-300 gap in the PDT05 cable becomes an administrative fail point, not knowing that a PDT05, 1-300 count does not exist would cause the types of data base administration, as well as engineering and Service Delivery, problems that we have been cleaning up for the past 2 years. It is also possible that different types of DS0 cables go to different types of frame locations like line sharing. Different databases are also involved like LFACS for line sharing. If a customer has DS1 service it could be a UNE or Finished Service and can be configured with or without regeneration, all of these are now uniquely identified through our new naming convention. This in turn is desired to eliminate potential wiring errors and customer effecting trouble. Future mergers and acquisitions are causing conflicting databases also. The current new naming convention addresses and eliminates this problem. When two CLECs merge, each will have different cable counts. The TIRKS data base is universal in nature and tracks and monitors all circuits.

In summary, we acknowledge the needed additional work on behalf of individual CLECs to ensure accurate CFA is submitted on provisioning orders. We also acknowledge Qwest is committed to furnishing accurate information and timely resolution of issues as they occur in the provisioning and maintenance process relating to APOT information. For all the above mentioned reasons, we respectfully deny your request.

Sincerely

Stephen C. Nelson Collocation Group Product Manager

July 13, 2001

Ms. Lynne Powers Vice President, Eschelon Telecom

Dear Ms. Powers:

This letter is in response to your CLEC Change Request form number 5608156 dated June 13, 2001.

“Please provide a process and procedures for consistent APOT numbering. Qwest apparently uses different central offices (CO’s) for numbering APOT’s. This leads to problems when, for example, a typist at Qwest copies and pastes information for one CO and uses it for another. Also, there appears to be a discrepancy between physical number and the information reflected in TIRKS. To the extent that inconsistencies exist today, please develop and distribute a process for correcting those inconsistencies. The inconsistencies create serious problems for CLEC’s. For example: In one situation, the augment was labeled at the ICDF as starting with number1. But, the collocation term sheets and IMA (TIRKS) indicated that the augmented APOT starts at a higher number. Therefore, pending orders could not be completed to the APOT on which they were ordered.” Response: Our cable naming convention has undergone evolution over the last six years. When cable names were first assigned to the CLEC cables, the same cable names, e.g. ALT01, were often assigned to multiple CLEC’s. Despite that convention, their corresponding circuits could still be built and turned up since the unique cables were built in TIRKS with the CLEC’s unique CLLI code, e.g. HG5. CLLI codes are assigned by CLONES in order as CLEC’s come into an office, e.g. if a CLEC is the first physical in office A they would typically be assigned HG1, if they were the 8th CLEC they would be assigned HG8., etc. The current naming convention does assign unique cable names to CLEC cables in a given office. The unique name is established based on factors such as the type of collocation, type of circuit, and the 11 character of the unique CLLI codes assigned to the CLEC. (Attachment A is our current Cable Naming Convention) Cable names assigned using the old convention are not incorrect. They are simply not as descriptive as the current naming convention. Qwest explored the cost of converting the millions of cable names over to the new convention in place currently. The estimated cost was in the millions of dollars. Word documents would have to be cut along with new APOT’s etc. Therefore the decision was made to do several things on a going forward basis. One, through attrition the old cable names over time as changes occurred. Two, we would formalize our methods and train all personnel on the new cable naming configuration. Three, we would establish a “Hot Line” for CLEC’s to resolve immediate discrepancies through their Account Representative. Fourth, we would do a major data base reconciliation of all major cities. Fifth, each augment of a site would require a new APOT in its entirely including existing cable names. Qwest has a process for handling discrepancies in provisioning or repair traced to APOT forms. We have established an interval Hot Line to ensure items referred by CLEC customers to their Account Service Manager are responded to within 5 hours by an engineer for resolution. The engineer will identify and work to eliminate and resolve the issue. The engineer will report back to the account representative within 24 hours on the resolution or estimated resolution of the problem. All of these action items have associated methods and procedures which Qwest employees have been trained on. Attachment C and D of the Configuration Options Policy in the PCAT identifies our cable naming convention and samples of APOT’s by type of collocation. (I have attached sample copies of APOT’s )

In summary, although it is more difficult for Qwest and CLEC’s to administer cable names based on the different naming configurations, we do not plan to “convert” all past APOT’s. All existing APOT’s have correct information for submittal or provisioning and repair requests. The Hot Line will assist where discrepancies occur. Our methods have been standardized. We will work with any specific CLEC to resolve any items of concern regarding particular CLEC site APOT’s through your Service Manager.

Sincerely Stephen C. Nelson Collocation Group Product Manager


Open Product/Process CR 5608163 Detail

 
Title: Process for resolving incorrect CSR information
CR Number Current Status
Date
Area Impacted Products Impacted

5608163 Completed
9/19/2001
Ordering Other
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Hoag, Nancy
Director:
CR PM:

Description Of Change

Please provide a process for resolving incorrect CSR information (on either a Qwest or another co-provider’s CSR). Before converting an account, errors in the CSR are sometimes detected. For example, a customer’s CSR shows only 4 lines even though the customer confirms that it added a 5th line six months ago. For some reason, the 5th line has not posted yet. Because the CLEC is ordering “conversion as specified” (and not new), because the customer already has the 5th line in place, the order does not get through the up-front edits. This is particularly true with Release 7.0. Another example is the situation in which the customer has changed addresses but the CSR still shows the old address. The CLEC is unable to submit a conversion. If the CLEC attempts to process the order, the customer’s lines may get moved back to the old address, or the customer may get back-billed. There is no process to follow when this happens.


Status History

06/13/01 – CR received from Lynne Powers of Eschelon 6/18/01 – Status changed to New – to be Evaluated

07/09/01 – Status changed to Reviewed – Under Consideration

07/13/01 – Drafted Response sent to CICMP Team via email (MR)

07/13/01 - MCC issued by Qwest

08/06/01 – Nancy Hoag of Qwest to address and close with Kathy Stichter of Eschelon

08/15/01 – CLEC CMP Meeting Product & Process Qwest response dated 07/13/01 presented, Qwest advised that an MCC would be issued.

08/24/01 - Qwest redistributed MCC to center coaches

08/24/01 - Qwest issued draft response to Eschelon

08/29/01 - Sent draft Qwest Response and MCC for Eschelon feedback.

08/30/01 - Received confirmation from Kathy Stichter from Eschelon that the draft response answered their CR and we could consider the CR Closed.

09/19/01 - CMP Meeting it was agreed that the CR could be closed.


Project Meetings

Stichter, Kathleen L. on 08/30/2001 07:52:07 AM

To: jlbroo2@qwest.com Subject: FW: Draft response to CR 5608163

Jerri, Thanks. This does answer our CR 5608163. We can consider this CR closed.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

From: Jerri Brooks [SMTP:jlbroo2@qwest.com] Sent: Wednesday, August 29, 2001 10:16 AM To: klstichter@eschelon.com Cc: Richard H Martin; Lynn Stecklein; Nancy J Hoag Subject: Draft response to CR 5608163

Hello Kathy,

Please see the attached draft response from Nancy Hoag concerning CR 5608163. Please confirm via e-mail if this response meets your needs or if we need to set up a walk through meeting to discuss the issue further. I am also forwarding you a copy of an e-mail MCC sent out on 7/13/01, it contains the process to be followed for CSR's. Thanks, Jerri Brooks (303) 294-1290

(See attached file: 1Eschelon Response CSR Information-update.doc)


CenturyLink Response

August 23, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom, Inc

CC: Mallory Paxton Matthew Rossi

This letter has been updated from the original July 13, 2001 written response to your CLEC Change Request Form #5608163 dated June 13, 2001.

Provide a process for resolving incorrect CSR information on either a Qwest or another co-provider’s CSR.

Response: Two options are available when the CSR is incorrect.

The CLEC can Check Manual Handling "Y" and explain in Remarks, for example, "Convert As Is. End User added fifth line 612-253-1234 6/29—CSR shows only four lines."

Open an escalation ticket with the Call Center. If this is the option selected, the CLEC should recognize that the ticket may still result in a manually-handled request, since Qwest may not be able to provide a current CSR in time to meet the CLEC’s needs.

These processes are in place today. They have been documented in the Internal Service Delivery M&Ps for the centers and have been communicated to all Qwest Center personnel. To ensure process compliance in all Qwest centers; a Multi-Channel Communicator (MCC) was released on July 13, 2001. The MCC reiterated the existing options as described above, to resolve incorrect CSR information. To further enforce this process, the MCC was redistributed to the Center Coaches on August 24, 2001

Sincerely,

Nancy J. Hoag Wholesale Product Manager

July 13, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom, Inc

CC:Mallory Paxton Matthew Rossi

This letter is in response to your CLEC Change Request Form #5608163 dated June 13, 2001

Provide a process for resolving incorrect CSR information on either a Qwest or another co-provider’s CSR.

Response: Two options are available when the CSR is incorrect.

1. The CLEC can Check Manual Handling “Y” and explain in Remarks, for example, “Convert As Is. End User added fifth line 612-253-1234 6/29—CSR shows only four lines.”

2. Open an escalation ticket with the Call Center. If this is the option selected, the CLEC should recognize that the ticket may still result in a manually-handled request, since Qwest may not be able to provide a current CSR in time to meet the CLEC’s needs.

These processes are in place today, they have been documented in the Internal Service Delivery M&Ps for the centers, and have been communicated to all Qwest Center personnel.

Sincerely, Nancy J. Hoag Wholesale Product Manager


Open Product/Process CR 5608171 Detail

 
Title: Process for allowing Qwest testers and repair personnel access to IMA GUI
CR Number Current Status
Date
Area Impacted Products Impacted

5608171 Completed
10/17/2001
Ordering Other
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Paxton, Mallory
Director:
CR PM:

Description Of Change

Please develop a process and put procedures in place to provide Qwest testers (particularly in Omaha) and Qwest repair personnel access to IMA-GUI. In addition, please train these individuals to access IMA-GUI. They need the ability to view the same information that the CLEC is looking at when they are discussing and attempting to resolve issues.

8-29-01 Scope of request changed from UnBundled Loop to Resell (non design) features.


Status History

06/13/01 - CR received from Lynne Powers

06/18/01 - Status changed to New – to be Evaluated

07/09/01 - Status changed to Reviewed – Under Consideration

08/29/01 - Clarification Meeting with Eschelon and unbundled Loop

08/30/01- Clarification Meeting with Eschelon and Resale

08/31/01- Sent Draft Qwest response to Eschelon.

09/19/01 - CMP Meeting - Eschelon advised that they required additional time to evaluate and requested that all the CLEC's review the response. Qwest will issue draft response.

09/25/01 - Qwest's response issued to CLEC Community.

10/17/01 - CMP Meeting: It was agreed the CR can be "Closed."


Project Meetings

8-30-01 Conference call with Eschelon (Kathy Stichter) Qwest Resale SME: Mallory Paxton, Change Management: Ric Martin, Lyman McKee

Mallory talked with Coach at 1-800-223-7811. Not aware of problem Where Eschelon and Qwest resources not being able to view the same information.

Eschelon views IMA-GUI, Qwest views RCE-GUI (LMOS)

Agreement reached to have Eschelon provide trouble ticket data to Mallory when Eschelon/Qwest views are not the same. Problem is infrequent.

Monitor windows established to be August 31 to October 1st. If nothing is reported CR is subject to be closed.

Mallory to prepare Qwest response position paper to Matt Rossi target 8-31-01.

8-29-01 Conference call with Eschelon (Kathy Stichter); Qwest Unbundled Loop SME’s: Linda Hendricks, Catherine Garcia, Chris Henderson, Deni Toye, Russ Urevig Change Management: Richard Martin, Lyman McKee

Kathy Stichter reviewed CR request situation. Results: Determine CR was not addressing Unbundled Loop, Eschelon is satisfied with QCCC process. Problems are with Resale (Non –design) features. Request as written indicated problem was Un-bundled Loop. Kathy provided calls placed to 1-800-223-7811 option 1 are where the problem existed.

Identified Mallory Paxton and JoAnn Garromone as Qwest SME.


CenturyLink Response

August 31, 2001

Kathy Stichter Eschelon Telecom Inc CC : Matt Rossi This memo is a response to the CLEC Change Request CR 5608171 regarding discrepancies between the information available to Qwest repair personnel and that viewed by a CLEC in IMA. The CR was opened by Eschelon. In fact-finding sessions with Eschelon, it was determined that the problem is confined to calls to the AMSC at 1-800-223-7811, Option 1. The AMSC has reviewed the data visible to their repair personnel, who are looking at an RCE GUI which interfaces with LMOS (the Classic US West repair system). The information on the RCE GUI has been compared to the IMA information viewed by a CLEC calling the center and found to be the same, although the two systems are cosmetically different. Eschelon has no current examples of problems encountered when their employees called the AMSC and the AMSC could not see the same information as Eschelon was seeing. Eschelon has agreed to refer any such problems which occur in the next month to me so that I can research them with the AMSC and at the end of September to consider closing this CR if the problems are no longer occurring or have been resolved to their satisfaction.

Mallory Paxton Resale Process Specialist Email: mpaxton@qwest.com Phone: 206-345-3384


Open Product/Process CR 5608177 Detail

 
Title: Process Improved process for CLEC to CLEC re use facilities process and ensure nondiscrimination
CR Number Current Status
Date
Area Impacted Products Impacted

5608177 Completed
8/15/2001
Ordering Other
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Hoag, Nancy
Director:
CR PM:

Description Of Change

Please improve the CLEC-to-CLEC re-use of facilities process and ensure nondiscrimination. Attached to this CR are Eschelon’s CR# 5263137 and 5263569, which Eschelon asks Qwest to re-open. The re-use of facilities process is not working as described. While CLECs are experiencing problems, Qwest retail is able to re-use facilities without difficulty. Four examples of this have been provided to the CICMP managers. The first two examples are Local Service Requests received from Qwest. In the Remarks section, one states: “Unbundled loop returning to Qwest to provide end user local service.” The other LSR states in the Remarks section: “Loops will be returned to Qwest.” These show that Qwest is able to re-use the facilities for its retail customers (without problems or requesting circuit id information from Eschelon). The other two examples are reject notices. Both contain the following reject message: “records indicate this circuit and slot not working unable to disc.” These examples show that Eschelon is unable to disconnect because Qwest is reclaiming the loop, without prior notice to Eschelon. Eschelon previously submitted CR 5263569 relating to loop reclamation. Attached to that CR is an example of an error message that states: “ the circuit requested to be disconnected is currently in the loop reclamation process and is scheduled for disconnect.” Qwest appears to have simply changed the wording of the reject message to remove the reference to the reclamation process, while continuing its practice of reclaiming loops to re-use them for Qwest retail. A nondiscriminatory process is needed to allow CLECs to re-use facilities as well. The current process is either flawed or Qwest’s representatives have not been trained adequately.


Status History

6/13/01 - CR received from Lynne Powers of Eschelon 6/18/01 – Status changed to New – to be Evaluated

6/20/01 - Process implementation for enhanced Circuit ID Process to be verified and presented in interim meeting to be scheduled by Qwest prior to the July CICMP Meeting. (MR)

6/25/01 - Status changed to Reviewed – Under Consideration

7/10/01 - Interim conference call conducted to discuss CLEC to CLEC conversions – meeting minutes sent to the CICMP team on 7/12/01 (MR)

7/13/01 - Drafted response sent to the CICMP Team via email (MR)

8/07/01 - Eschelon and Allegiance confirmed that LSRs are being submitted and handled properly in relation to Qwest’s process on Circuit ID attainment. (MR)

8/09/01 - Revised CR response distributed to the CICMP team via email. (MR)

8/15/01 - CLEC CMP Meeting Product & Process CR 5608177. It was agreed that the CR was closed due to successful processing of LSRs with revised procedure for CKTIDs.


Project Meetings

Subject: CR-5608177 Date: Sun, 26 Aug 2001 19:40:15 -0500 From: "Stichter, Kathleen L." To: rhmart2@qwest.com

Ric, Sorry about forgetting. Yes you were correct we did close this CR.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com


CenturyLink Response

August 7, 2001

This letter is in response to the following CLEC Change Request Forms #5263137, dated December 1, 2000 and #5608177 and #5608353, dated June 13, 2001. All of these Change Requests pertain to the CLEC to CLEC Migration process. The revised process was released via the Co-Provider Industry Change Management Process (CICMP) on May 25, 2001.

Re-use of facilities for CLEC to CLEC carrier changes, improving the CLEC to CLEC reuse of facilities process and to ensure nondiscrimination.

Response: The Qwest Release Notification Forms #5393537 (CLEC Unbundled Loop to CLEC Unbundled Loop), #5393543 (CLEC Unbundled Loop to CLEC Resale), and #5467108 (CLEC LNP with Unbundled Loop to CLEC Unbundled Loop) Revision B, released on May 25, 2001, noted changes in the Pre-Order section that the requirement to obtain the Circuit Identification Number from the OLSP” is optional. Both Eschelon and Allegiance provided Qwest with examples of orders that were rejected by Qwest due to no Circuit Identification Number provided. After gap analysis, it was determined that additional training of Qwest Service Center personnel and updates to Service Delivery M&Ps were required. The following measures have been implemented:

An updated Multi Channel Communicator (MCC) New or Changed Information Procedure was issued on July 9, 2001. Issued to target Qwest internal personnel in the Wholesale Customer Care, Customer Service, Error Group, Held Order/Escalation, Order Processing and Order Resolution organizations. Topic of the MCC: CLEC to CLEC Migration of an Unbundled Loop and Unbundled Loop to other products. CLEC to CLEC Migration is defined as; unbundled to unbundled, unbundled to resale, unbundled to Centrex resale. Emphasis placed on processing orders without circuit ids (ECCKT’s) on LSR requesting migration. States included in this communication are; AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NE, NM, OR, Outside 14 State Region, SD, UT, WA and WY. All internal job aids and on-line support documentation have been updated. Qwest Service Center specific training sessions are currently in progress for both center coaches and center personnel. The training will be on going to ensure process compliance.

Sincerely

Nancy J. Hoag Qwest Wholesale Product Team


Open Product/Process CR 5263137 Detail

 
Title: Re use facilities for CLEC CLEC carrier changes
CR Number Current Status
Date
Area Impacted Products Impacted

5263137 Completed
11/14/2001
Ordering Centrex, Resale, Unbundled Loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Urevig, Russell
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest should change its process so that Qwest will re-use facilities for CLEC-to-CLEC carrier changes. When an end-user customer changes carriers from one CLEC to another, Qwest has indicated to Eschelon that CLECs must order new facilities, because Qwest does not allow a CLEC to request re-use of the same facilities used by the other CLEC to serve the same customer. In one situation, for example, Eschelon placed an order to change an end-user customer from the on-net facilities of another CLEC to the on-net facilities of Eschelon. Qwest indicated that Eschelon must order new facilities and, when Eschelon did so, Qwest placed the order in held status. The other CLEC provided its PONs to Eschelon for that CLEC’s disconnect of its loops. Eschelon re-submitted the order, identified the PONs, and requested re-use of those facilities. Qwest responded that CLECs are not allowed to request re-use of CLEC facilities. Eschelon cancelled the order and resubmitted it later. The order again went in held status. The order is still in held status. (Eschelon has provided the specific information for this and other situations to its account manager.) Ordering new facilities, instead of re-using facilities, can result in delay, additional costs, and service disruption or downtime. Please modify Qwest’s processes so that Qwest will re-use facilities for CLEC-to-CLEC carrier changes.


Status History

12/01/00 - Submitted

12/01/00 - New to be validated

12/04/00 - New to be reviewed

12/06/00 - Status changed to Reviewed - under consideration

12/06/00 - Will Discuss during UNE-P discussion marked as agenda item in the Product/Process CICMP Meeting (12/20/00)

12/15/00 - CR still under investigation but will address in the CICMP Meeting (12/20/00)

01/10/01 - Will be addressed during the 1/11 through 1/12 CLEC to CLEC UNE-P meeting and results discussed in the January CICMP Meeting (RU)

02/14/01 - Product Announcement for a formalized process to enable CLEC to CLEC conversions of Unbundled Loop with Re-use of facilities or same loop type services communicated to CICMP team via email and posted on CICMP web site. ( RN # 5393537). (RU – MR)

02/21/01 - Closing CR is dependant on requested revision to RN #5393543 – CLEC Unbundled Loop to CLEC Resale

03/19/01 - Revision to RN #5393543 complete and undergoing internal approval. Date of Release pending approval. (BD)

03/27/01 - Revision to RN #5393537 - CLEC Unbundled Loop to CLEC Unbundled Loop Re-use of Facilities - Revision A sent to CICMP team. BD-MR)

04/18/01 - Additional revision needed to CLEC Unbundled Loop – CLEC Unbundled Loop and CLEC Unbundled Loop – Resale release notifications previously released to incorporate new policy on obtaining Circuit ID from OLSP (MR)

04/30/01 - Revision "B" to RN #5393537, RN #5393543, and RN #5467108 sent to CICMP team incorporating new procedure for obtaining Circuit ID’s. (MR)

05/16/01 - Lynne Powers request to remain open to verify newly implemented circuit attainment process to be put in place on 5/25. (MR)

06/20/01 - Process implementation for enhanced Circuit ID Process to be verified and presented in interim meeting to be scheduled by Qwest prior to the July CICMP Meeting. (MR)

07/10/01 - Interim conference call conducted to discuss CLEC to CLEC conversions – meeting minutes sent to the CICMP team on 7/12/01 (MR)

07/13/01 - Drafted response sent to the CICMP Team via email (MR)

08/07/01 - Qwest response dated 08/07/01presented.

08/28/01 - CR Closed per telecon between R. Martin, Qwest and K. Stichter, Eschelon.

09/19/01 - CMP Meeting - agreed to move CR to CLEC Test Status

10/17/01 - CMP Meeting: No "Current Status" change

11/14/01 - CMP Meeting - it was agreed that the CR could be closed.


Project Meetings

Email 08/28/01 Kathy, This confirms our conversation this morning that Change Request 5263137 can be closed based on Qwest's response dated August 7, 2001 presented at the 8/15/01 meeting. In addition, this is based on Qwest tracking System Action Item 308 as a separate request and addressing the quality issued experienced during cut-over. Thanks for your cooperation. Regards, Ric


CenturyLink Response

August 7, 2001 This letter is in response to the following CLEC Change Request Forms #5263137, dated December 1, 2000 and #5608177 and #5608353, dated June 13, 2001. All of these Change Requests pertain to the CLEC to CLEC Migration process. The revised process was released via the Co-Provider Industry Change Management Process (CICMP) on May 25, 2001.

Re-use of facilities for CLEC to CLEC carrier changes, improving the CLEC to CLEC reuse of facilities process and to ensure nondiscrimination. Response: The Qwest Release Notification Forms #5393537 (CLEC Unbundled Loop to CLEC Unbundled Loop), #5393543 (CLEC Unbundled Loop to CLEC Resale), and #5467108 (CLEC LNP with Unbundled Loop to CLEC Unbundled Loop) Revision B, released on May 25, 2001, noted changes in the Pre-Order section that the requirement to obtain the “Circuit Identification Number from the OLSP” is optional. Both Eschelon and Allegiance provided Qwest with examples of orders that were rejected by Qwest due to no Circuit Identification Number provided. After gap analysis, it was determined that additional training of Qwest Service Center personnel and updates to Service Delivery M&Ps were required. The following measures have been implemented:

An updated Multi Channel Communicator (MCC) New or Changed Information Procedure was issued on July 9, 2001. Issued to target Qwest internal personnel in the Wholesale Customer Care, Customer Service, Error Group, Held Order/Escalation, Order Processing and Order Resolution organizations. Topic of the MCC: “CLEC to CLEC Migration of an Unbundled Loop and Unbundled Loop to other products.” CLEC to CLEC Migration is defined as; unbundled to unbundled, unbundled to resale, unbundled to Centrex resale. Emphasis placed on processing orders without circuit ids (ECCKT’s) on LSR requesting migration. States included in this communication are; AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NE, NM, OR, Outside 14 State Region, SD, UT, WA and WY. All internal job aids and on-line support documentation have been updated. Qwest Service Center specific training sessions are currently in progress for both center coaches and center personnel. The training will be on going to ensure process compliance.

Sincerely Nancy J. Hoag Qwest Wholesale Product Team

July 13, 2001 This letter is in response to the following CLEC Change Request Forms #5263137, dated December 1, 2000 and #5608177 and #5608353, dated June 13, 2001. All of these Change Requests pertain to the CLEC to CLEC Migration process. The revised process was released via the Co-Provider Industry Change Management Process (CICMP) on May 25, 2001.

Re-use of facilities for CLEC to CLEC carrier changes, improving the CLEC to CLEC reuse of facilities process and to ensure nondiscrimination.

Response: The Qwest Release Notification Forms #5393537 (CLEC Unbundled Loop to CLEC Unbundled Loop), #5393543 (CLEC Unbundled Loop to CLEC Resale), and #5467108 (CLEC LNP with Unbundled Loop to CLEC Unbundled Loop) Revision B, released on May 25, 2001, noted changes in the Pre-Order section that the requirement to obtain the “Circuit Identification Number from the OLSP” is optional. Both Eschelon and Allegiance provided Qwest with examples of orders that were rejected by Qwest due to no Circuit Identification Number provided. After gap analysis, it was determined that additional training of Qwest Service Center personnel and updates to Service Delivery M&Ps were required. The following measures have been implemented:

An updated Multi Channel Communicator (MCC) New or Changed Information Procedure was issued on July 9, 2001. Issued to target Qwest internal personnel in the Wholesale Customer Care, Customer Service, Error Group, Held Order/Escalation, Order Processing and Order Resolution organizations. Topic of the MCC: “CLEC to CLEC Migration of an Unbundled Loop and Unbundled Loop to other products.” CLEC to CLEC Migration is defined as; unbundled to unbundled, unbundled to resale, unbundled to Centrex resale, unbundled to retail. Emphasis placed on processing orders without circuit ids (ECCKT’s) on LSR requesting migration. States included in this communication are; AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NE, NM, OR, Outside 14 State Region, SD, UT, WA and WY. All internal job aids and on-line support documentation have been updated. Qwest Service Center specific training sessions are currently in progress for both center coaches and center personnel. The training will be on going to ensure process compliance.

Sincerely Nancy J. Hoag Wholesale Product Manager


Open Product/Process CR 5263637 Detail

 
Title: Installation of adequate facilities and reduction in number of held orders
CR Number Current Status
Date
Area Impacted Products Impacted

5263637 Denied
2/20/2002
Ordering Centrex, Resale, Unbundled Loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Buckmaster, Cindy
Director:
CR PM:

Description Of Change

Modify Qwest’s processes to ensure installation of adequate facilities and reduction in the number of held orders. Through recurring rates, Qwest is being compensated for expanding its network to account for new growth. Qwest will build facilities for its own retail customers. (In Arizona arbitration's, for example, Qwest reported that it installs 3 lines per customer to anticipate growth.) However, Qwest will not do so for CLECs in similar situations. Qwest has rejected orders from Eschelon for the stated reason that “no jobs planned in the near future for this area.” (Examples of such rejections were provided to Eschelon’s account team on August 30, 2000.) The orders are placed in held status indefinitely, with no date for completion. When asked about these rejections, Qwest indicated it believes it has no obligation to build. At the last CICMP meeting, Qwest again confirmed that it is Qwest’s policy not to build additional UNE's when Qwest is out of capacity, but Qwest will build for a retail customer’s order. As indicated, however, Qwest is being compensated for such growth and would build for its own retail customer in the same situation. Please modify Qwest’s practices to build in these situations and to provide notice to CLECs as to when held orders will be completed. In the meantime, until such processes are in place, please institute a process to provide to CLECs (perhaps through a website) a list of those areas for which Qwest has jobs planned, a list of areas for which no jobs are planned, and a description of the nature of the jobs planned. Because Qwest has access to this information for its planning purposes, parity requires that CLECs also have access to the same information for their planning purposes.

Modification

08/22/01 - Added Action Item 25, Advance Notification of future builds.

08/22/01 - Added Action Item 28, Resale Orders vs. Unbundled Loop Orders-Held Order Process

08/22/01 - Added Action Item 29, State Specific Rules for future build policy


Status History

12/01/00 - Submitted

12/01/00 - New - to be validated

12/04/00 - Status changed to New – To be reviewed

12/06/00 - Status changed to Reviewed – Under Consideration

12/06/00 – Will Discuss during UNE-P discussion marked as agenda item for 12/20 Product/Process CICMP Meeting

12/15/00 – CR still under investigation but will address at the 12/20 CICMP Meeting (SB - BC)

1/10/01 - Documentation currently being created by Qwest personnel and will be addressed during the January CICMP Meeting (CB).

1/15/00 - The question of whether or not Qwest will build to provide UBL facilities for CLECs is currently under review. Some additional work is necessary to determine if precedent has been set due to past actions or previous sideline agreements. The Product Team is resolving this issue and should have a new policy statement by 1/31/01 (CB).

1/26/01 - Due date changed due to corporate strategy involvement and moved tentatively to 2/28/01 (CB)

3/15/01 - Document complete pending approval by Legal. Expected delivery 3/16/01. (CB)

3/19/01 - Tentative approval date pushed to 3/21/01. Date of document release pending internal approval. (CB)

3/27/01 - RN #5467145 - Qwest Position Statement on Build Requirements for Unbundled Loops released to the CICMP team. Qwest accepts build responsibility for primary analog voice grade circuits. Where facilities don’t exist for these requests, Qwest will initiate an engineering work order to build. (CB)

4/18/01 - Statement regarding advanced notice on future builds required to Complete this CR. (MR)

5/14/01 - Policy statement concerning advance notification of future builds has been drafted and is currently under review by Qwest Legal and Public Policy. Tentatively marked for release on 5/30/01. (NH)

5/30/01 - Policy statement held due to language. Date of Distribution TBD

6/18/01 - Build Policy tentatively scheduled for release on 8/1/01 (DG)

8/09/01 - CR Response distributed to the CICMP Team along with a drafted Response to a supplemental email submitted by Karen Clauson. (MR)

08/15/01 - Eschelon did not accept Qwest's response dated 08/09/01

09/19/01 - CMP Meeting - Qwest advised that they are still evaluating the CR.

09/21/01 - Meeitng held with Eschelon. Matrix developed with list of action items.

10/17/01 - CMP Meeting: Qwest to transmit revised response to Eschelon & notify CLEC community within next few days. No "Current Status" change.

10/18/01 - Issued Qwest Response dated October 15, 2001 with Attachments to the CLEC Community.

10/18/01 - Received e-mail comments from Eschelon on Qwest's 10/15/01 response

10/29/01 - Conducted Clarification meeting with Eschelon to review their e-mail comments to Qwest's 10/15/01 Response.

11/14/01 - CMP Meeting - Qwest advised that PCATs should be published in November. Eschelon requested Qwest explain why rearrangement of the Qwest network requires special construction and that Qwest answer their 11 questions.

11/16/01 - Revised PCAT Language was posted to the WEB for both General Resale and Genera UBL..

12/12/01 - CMP Meeting - Qwest provided an update on the process development on Special Construction. Qwest advised that the process should be completed in January and Qwest will respond to Eschelon's questions after that time. It was agreed that the CR should be placed into Development.

01/16/02 - CMP Meeting - Qwest advised that the document on the Special Construction package was very much in draft form. Qwest reviewed the draft process which is to primarily introduce the process and secondarily answer Eschelon's questions. CLECs are to provide feedback to the document. The CR will remain in Development.

02/01/02 - Posted Updated Special Construction Process with Answers to Eschelon's questions to the database.

02/01/02 - Issued Updated Special Construction Process to Eschelon.

02/20/02 - CMP Meeting - Qwest reviewed the two additional questions raised at last month's CMP meeting that were incorporated into Qwest's Special Construction Process. Qwest advised that the Special Construction PCAT language would be issued April 5, 2002. Qwest requested that the CR be closed. Eschelon advised that they felt the CR should be denied because Qwest isn't reducing the number of held orders, but rather canceling them. It was agreed that the CR would be statused as Denied. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

Clarification Meeting

October 29, 2001 Conference Call

866-289-7092 5263637, Installation of Adequate Facilities Attendees: Ric Martin, Qwest Susie Bliss, Qwest Kathleen Stichter, Eschelon

1.0 Purpose Review Qwest’s October 15, 2001 response and Eschelon’s e-mail dated October 18, 2001 2.0 Review Documents and Clarify Requirements 2.1 Ric Martin reviewed Eschelon’s e-mail and clarified that Eschelon wanted to clearly see the written policies and specific exceptions to the policies. 2.2 Susie Bliss explained that, to the maximum extent practical, policies specific to products would be contained in the product PCATs. Susie advised that Qwest agreed to clarify our policies and state any exceptions to the policy. Qwest is in the process of updating the General Unbundled Loop PCAT and the General Resale PCATs. Qwest is clarifying the exceptions under the Tariff, Regulations and Policy section of the above PCATs. Susie advised that within the next couple of weeks the two specific products would be updated in the PCAT to clearly define the policies and ensure that exceptions are clearly stated. 2.3 Kathy Stichter asked if there were any other exceptions like Minnesota. Susie Bliss explained that there were no other current exceptions. 2.4 Susie Bliss advised that as additional rulings get handed down, Qwest would update the PCATs accordingly and issue the requisite notifications. 2.5 Kathy Stichter asked about Qwest’s retail policy. Susie Bliss advised that the Qwest Resale is the Qwest Retail policy. 2.6 Susie Bliss is to provide the approximate timeframe for publishing the General Resale and General Unbundled Loop PCATs. 2.7 Ric Martin will communicate the dates to the CLEC Community via the requisite notifications. 2.8 Ric Martin advised that with the Update of the PCATs, it would be Qwest’s intent to move the CR into a CLEC Test Phase to allow the CLEC’s review the PCAT language. 2.9 Kathy Stichter stated that the above actions should meet their expectations.

--

RE: Response - CR 5263637 - Installation of Adequate Facilities - Fourth Attempt Date: Thu, 18 Oct 2001 13:36:33 -0500 From: Clauson, Karen L. ,klclauson@eschelon.com> To: Matthew Rossi , mrossi@qwest.com CC: Powers, F. Lynne,flpowers@eschelon.com, "Stichter, Kathleen L,. Thank you for the response. We will review it internally. With respect to state-specific issues, we had asked Qwest to identify any state-specific exceptions. Qwest agreed to do so. Eschelon also asked that Qwest modify its written policy to state the exceptions in the policy, instead of using a general footnote that refers to exceptions without stating what those exceptions are. As written, the policy does not reflect those exceptions. The policy has not been modified so that a CLEC reading it would know how the policy applies in each state. The reply refers to the Minnesota merger agreement as "one such exception." This suggests that there are other exceptions, but Eschelon does not know what they are. Please identify the exceptions and modify the written policy to list the exceptions so that CLECs reading the policy can identify how the policy operates in each state. Thank you.


CenturyLink Response

"The below response does not include the attachments referenced in the response field. Please see Supplemental Information following the Detail Report."

October 15, 2001

Lynn Powers Vice President, Eschelon Telecom, Inc.

CC: Matthew Rossi

This letter is issued to amend Qwest’s response letter dated August 9, 2001 and is in response to your CLEC Product & Process Change Request 5263637. Request –

? Modify Qwest’s processes to ensure installation of adequate facilities and reduction in the number of held orders. Through recurring rates, Qwest is being compensated for expanding its network to account for new growth. Qwest will build facilities for its own retail customers. (In Arizona arbitration's, for example, Qwest reported that it installs 3 lines per customer to anticipate growth.) However, Qwest will not do so for CLECs in similar situations. Qwest has rejected orders from Eschelon for the stated reason that “no jobs planned in the near future for this area.” (Examples of such rejections were provided to Eschelon’s account team on August 30, 2000.) The orders are placed in held status indefinitely, with no date for completion. When asked about these rejections, Qwest indicated it believes it has no obligation to build. At the last CICMP meeting, Qwest again confirmed that it is Qwest’s policy not to build additional UNEs when Qwest is out of capacity, but Qwest will build for a retail customer’s order. As indicated, however, Qwest is being compensated for such growth and would build for its own retail customer in the same situation. Please modify Qwest’s practices to build in these situations and to provide notice to CLECs as to when held orders will be completed. In the meantime, until such processes are in place, please institute a process to provide to CLECs (perhaps through a website) a list of those areas for which Qwest has jobs planned, a list of areas for which no jobs are planned, and a description of the nature of the jobs planned. Because Qwest has access to this information for its planning purposes, parity requires that CLECs also have access to the same information for their planning purposes.

Response –

As discussed earlier, currently Qwest has no plans to modify the existing policy or processes regarding Qwest’s obligation to build new facilities. The issues addressed in your CR have been discussed in workshops. Some of the issues have been resolved. Rulings have been received in 10 of the 12 workshops to date. In each ruling, the Commissions support the Qwest position that the ILEC is not required to build additional facilities to deliver to a CLEC.

In order to help identify the current status of the issues we put together a summary outlined in Attachment A. This status was as of October 1, 2001. Attachment B documents our replies to the questions associated with this CR. We appreciate the time you spent clarifying each of your questions. Qwest will review our current PCATs to ensure they reflect the current status of any past rulings and we will continue to do so as states rule on the issues at impasse.

Finally, between the August 7th reply, the August 9th reply, and the attached, Qwest believes we have addressed the issues associated with this CR and we need to let the regulatory process determine the next steps.

Sincerely,

Susie Bliss Qwest Wholesale Process Director

--

August 9, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom Inc.

CC:Matthew Rossi Cindy Buckmaster Denny Graham

This letter is in response to your CLEC Change Request Form #5263637 dated December 1, 2000

Change Request: “Installation of Adequate Facilities and Reduction in Number of Held Orders” “Modify Qwest’s processes to ensure installation of adequate facilities and reduction in the number of held orders. Through recurring rates, Qwest is being compensated for expanding its network to account for new growth. Qwest will build facilities for its own retail customers. (In Arizona arbitration, for example, Qwest reported that it installs 3 lines per customer to anticipate growth.) However, Qwest will not do so for CLECs in similar situations. Qwest has rejected orders from Eschelon for the stated reason that “no jobs planned in the near future for this area.” (Examples of such rejections were provided to Eschelon’s account team on August 30, 2000.) The orders are placed in held status indefinitely, with no date for completion. When asked about these rejections, Qwest indicated it believes it has no obligation to build. At the last CICMP meeting, Qwest again confirmed that it is Qwest’s policy not to build additional UNEs when Qwest is out of capacity, but Qwest will build for a retail customer’s order. As indicated, however, Qwest is being compensated for such growth and would build for its own retail customer in the same situation. Please modify Qwest’s practices to build in these situations and to provide notice to CLECs as to when held orders will be completed. In the meantime, until such processes are in place, please institute a process to provide to CLECs (perhaps through a website) a list of those areas for which Qwest has jobs planned, a list of areas for which no jobs are planned, and a description of the nature of the jobs planned. Because Qwest has access to this information for its planning purposes, parity requires that CLECs also have access to the same information for their planning purposes.”

Qwest Response: Qwest interprets both the FCC Telecom Act and subsequent UNE Remand to state that ILECs are obligated to make the existing network available to CLECs via unbundling. Qwest believes that this means that Qwest is not obligated to construct new facilities at its expense at the request of a CLEC.

The first part of this Change Request requires that Qwest ensure installation of adequate facilities. Qwest recognized that holding CLEC requests led to the mis-interpretation that Qwest was willing to construct these UNEs at some point in the future. As this isn’t the case, Qwest issued the Qwest Network Build Position for the Unbundled Loop (UBL) Product and ensured all operational work groups adhered to this practice. In short, the Position statement states,

Qwest will construct facilities for UBL that are in alignment with its Eligible Telecommunications Carrier (ETC) obligation to provide basic local exchange service in the retail markets. This means that Qwest will construct facilities to satisfy the primary DS0 - Analog (voice grade) lines for UBL as Qwest constructs these facilities for it’s own end-users.

The Primary services identified above are specific to the set number of lines per address. Address is defined as the specific Unit (Loc).

When the CLEC submits a request for a Secondary DS0-Analog (voice grade) line, DSL, ISDN, DS1 or DS3 service, the normal assignment process will be followed in its entirety. If no facilities can be found, and there is No Planned Engineering Job, the LSR will be rejected (the CLEC will receive a Reject Notice) and the Order will be cancelled. The CLEC now has the opportunity to request construction by filing the proper request through their Account Team.’

In this Statement, Qwest agrees to ensure adequate facilities to support Primary DS0-Analog (voice grade) requests only.

The second issue in this Change Request deals with Held Orders. In various sections of the Request, Eschelon requires Qwest to reduce the number of held orders, not leave held orders in held status indefinitely, with no date for completion and to provide notice to CLECs as to when held orders will be completed.

As Qwest believes the ILECs are not obligated to provide more than the existing network for the CLECs, it follows that the ILECs are not obligated to hold and review old CLEC requests on a regular basis. Therefore, Qwest’s implementation of the Network Build Position for the Unbundled Loop (UBL) Product ensured that all operational work groups were in alignment not to hold requests where facilities are not currently available.

A third issue in this Change Request indicates that Qwest confirmed its policy not to build additional UNEs when Qwest is out of capacity. This issue is not entirely accurately represented. UNEs and retail services utilize the same physical facilities. Where facilities are exhausted, Qwest retail customers will suffer in the same fashion as CLEC customers. Where facilities are exhausted, Qwest will not have the ability to provide additional lines to any customer, retail or CLEC. In most of these circumstances, Qwest is working to reinforce the availability of facilities in these areas.

The issue here is the availability of compatible facilities. For analog (voice grade) services, many types of facilities can be used. However, for some services, copper facilities are required. If Qwest has facilities that are not compatible for the services the CLEC is intending to deliver, Qwest will not construct compatible facilities for the CLEC.

Finally, this Change Request addresses the availability of information related to plans for Network Builds. In response to this request, Qwest is announcing a Network Build Disclosure Web site.

The Network Build Disclosure will notify the CLEC community of Outside Plant (OSP) growth jobs that exceed $100,000 in expense. The disclosure will consist of number of copper pairs or fiber strands placed per distribution area in wire centers, an estimated ready for service date and the final completion dates when job is complete. NOTE: Qwest will reserve the right to cancel jobs due to business decisions and will not be held liable for cancellations. This disclosure will be made September 30,2001 and will be continued on a monthly basis thereafter. Jobs will be dropped from the list 30 days after actual completion date is announced. Customers will be able to view the latest information regarding Qwest’s growth and major expansions in Qwest local serving area. This will help them to identify areas where additional facilities will be available for growth. This disclosure will be located on the Qwest’s external website located at www.qwest.com/wholesale/iconn/

Denny Graham Qwest Staff Compliance Representative

Cindy Buckmaster Nancy Hoag Qwest Wholesale Products


Open Product/Process CR 5263569 Detail

 
Title: Loop reclamation
CR Number Current Status
Date
Area Impacted Products Impacted

5263569 Completed
12/12/2001
Ordering Centrex, Resale, Unbundled Loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Urevig, Russell
Director:
CR PM:

Description Of Change

Perform loop reclamation for CLECs and provide prior notice of Qwest’s loop reclamation. Qwest has indicated that it will not perform loop reclamation to prevent a CLEC order from going into held status. In contrast, when Qwest “wins back” a customer from a CLEC, Qwest will perform loop reclamation and will do so without prior notice to the CLEC. For example, as shown in the example below, when Eschelon has placed a disconnect order on a UNE loop, Eschelon has received a rejection notice from Qwest indicating that Qwest has already disconnected the loop as a result of loop reclamation. Qwest disconnected the loop without prior notice to Eschelon. Because of this practice, an order will be processed (and not go into held status) for a Qwest retail customer, whereas a CLEC order would go into held status. The CLEC end-user customer would experience a delay (and possibly additional costs and service disruption), whereas the Qwest end-user would not. Please modify Qwest’s processes to perform loop reclamation for CLECs and provide prior notice of Qwest’s loop reclamation.


Status History

12/01/00 - Submitted

12/01/00 - New - to be validated

12/04/00 - Status changed to New – To be reviewed

12/06/00 - Status changed to Reviewed – Under Consideration

12/06/00 - Will Discuss during UNE-P discussion marked as agenda item for 12/20 Product/Process CICMP Meeting

12/15/00 - CR still under investigation but will address at the 12/20 CICMP Meeting (SB)

01/10/01 - Will be addressed during the 1/11 – 1/12 CLEC to CLEC UNE-P meeting and results discussed in the January CICMP Meeting (RU)

02/14/01 - Product Announcement for a formalized process to enable CLEC Unbundled loop to CLEC resale communicated to CICMP team via email and posted on CICMP web site. ( RN # 5393543). (RU – MR)

02/21/01 - Closing CR is dependant on requested revision to RN 5393543 – CLEC Unbundled Loop to CLEC Resale

03/19/01 - RN Revision complete and undergoing internal approval. Date of release pending approval. (BD)

03/27/01 - Revision to RN #5393543 - CLEC Unbundled Loop to CLEC Resale - Revision A as well as RN #5467108 - CLEC LNP with Unbundled Loop to CLEC Resale - Revision A released to the CICMP Team. (MR-BD)

04/16/01 - Additional revision needed to CLEC Unbundled Loop – CLEC Unbundled Loop and CLEC Unbundled Loop – Resale release notifications previously released to incorporate new policy on obtaining Circuit ID from OLSP (MR)

04/30/01 - Revision “B” to RN #5393537, RN #5393543, and RN #5467108 sent to CICMP team incorporating new procedure for obtaining Circuit ID’s. (MR)

05/18/01 -CICMP team requests verification of implemented process to close CR

(MR)

06/20/01 - Process implementation for enhanced Circuit ID Process to be verified and presented in interim meeting to be scheduled by Qwest prior to the July CICMP Meeting. (MR)

07/10/01 - Interim conference call conducted to discuss CLEC to CLEC conversions – meeting minutes sent to the CICMP team on 7/12/01 (MR)

08/15/01 - CLEC CMP Meeting Product & Process CR 5263569. Qwest response dated 08/13/01 presented. Eschelon requested process improvement plan.

08/29/01 - Qwest issued revised draft response dated 08/27/01.

08/29/01 - Eschelon indicated that response didn't adequately answer the CR and requested that a clarification meeting be held.

09/04/01 - E-mail sent to Kathy Stichter to verify the question being posed in the CR. Kathy Stichter confirmed via e-mail on 9/6 that Qwest does understand their request.

09/12/01 - Eschelon provided comments.

09/18/01 - Review meeting held with Eschelon

09/19/01 - CMP Meeting - Qwest advised that they were developing an implementation plan and should have a response and plan the week of 10/01/01.

10/09/01 - Russ Urevig (Qwest) reported that all Centers have been trained, to include the three regions of Seattle, Phoenix & Omaha.

10/17/01 - CMP Meeting: Qwest to transmit revised response to Eschelon & notify CLEC community within next few days. No "Current Status" change.

10/19/01 - Revised response posted to web (response dated 09 October 2001).

11/14/01 - CMP Meeting - Qwest provided status of its implementation. It was agreed that the CR could be moved to Development

12/07/01 - Letter (dated 12/04/01) regarding process the CLEC community will need to follow to assist Qwest in Loop Reclamation, and crediting to the CLEC’s received and posted into CMP data base.

12/12/01 - CMP Meeting - Russ Urevig, Qwest presented procedure for CLECs to follow to assist Qwest in Loop reclamation, and crediting to the CLECs. Allegiance and Eschelon indicated that the procedure has been implemented and was satisfied with current results. CR "Present Status" was changed to "Completed." Eschelon requested that the CMP track further progress of actual CLEC loop reclamations in the future.


Project Meetings

11:30 a.m. (MDT) / Tuesday 18th September 2001 Clarification/Walk-through Meeting

Kathy Stichter, Eschelon Jerri Brooks, Qwest Ric Martin, Qwest Russ Urevig, Qwest Nancy Hoag, Qwest Linda Miles, Qwest Carolyn Brown, Qwest

Introduction of Attendees Introduction of participants on the Conference Call was made. The purpose of the call was to discuss Qwest’s Action Plan for CR 5263569 Loop Reclamation, and to share the plan at a high level with Eschelon. Review of Response Russ Urevig reviewed the draft point paper that lays out the tentative Action Plan. R. Urevig stated that Qwest Recognizes there is an issue with Loop Reclamation and that a cross-functional team is looking at improving the process. R. Urevig stated training documentation for order writers is scheduled to be completed by mid September. R. Urevig stated there will be a trial program to test the process within the next 3-5 weeks. R. Urevig stated there is a non-competitive group within Qwest who will do the disconnect/reclamation with side by side training from Regional Support Groups. R. Urevig stated there will be a meeting on Friday 9/21/01 to discuss the Action Plan, Time Estimates and Recommended Changes. R. Urevig will provide the action plan with timeline and recommended changes to CMP group and Kathy Stichter of Eschelon.

09/12/01 - Email Jerri, Bonnie and I talked today. What Eschelon wants Qwest to modify their process to perform Loop Reclamation on all disconnect orders and if that is not possible to at least notify Eschelon when they have performed a Loop Reclamation.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

From: Jerri Brooks [SMTP:jlbroo2@qwest.com] Sent: Tuesday, September 04, 2001 5:29 PM To: klstichter@eschelon.com Subject: CR 5263569

Kathy, Just a note to clarify that we are still working through the issues concerning this CR and an updated Qwest Response. First of all we want to clarify your Request as - "Eschelon wants Qwest to modify its process to perform loop reclamation for CLEC's and provide prior notice to Qwest's loop reclamation."

If that statement is actually what you are requesting then we agree with you. I believe there is currently an effort underway between Qwest groups to conduct a process gap analysis. Immediately after the gap analysis is completed an Action Plan will be drafted with milestones, commitment dates, etc. I will keep you posted as we make progress on this CR. Please give me a call and we can discuss any other questions you may have. Thanks, Jerri 303-294-1290


CenturyLink Response

Wholesale Product Marketing

December 4, 2001

CC: Russ Urevig

This letter is in response to your CLEC Change Request Form #5263569 dated December 1, 2000. The letter will identify the process the CLEC community will need to follow to assist Qwest in Loop Reclamation, and crediting to the CLEC’s.

We are requesting the CLEC’s to provide to their service manager in spreadsheet form the following information:

- The Qwest circuit ID ie; 3.LXFU.00012..nw - The PON number from which the circuit was established - The port back TN - The port back Date - The state in which the circuit was provided

The service manager will be the interface into Qwest and establish a time line in which the process of clean up will start with the Interconnect service center. The Interconnect center will provide the service manager an estimated completion date for each CLEC. The individual CSR established for circuits will be credited back to the Port Out/Port In date to Qwest of that TN specified. For those circuits that can not be credited through the normal process the service manger will be involved with the billing credit process and assist the Interconnect service center to credit each CLEC.

Sincerley,

Russ Urevig Senior Process Analyst

October 9, 2001 Final Response Lynne Powers Eschelon Telecom Vice President, Customer Operations

CC: Russ Urevig Susie Bliss Jerri Brooks Joan Smith

This letter is in response to your CLEC Change Request Form # 5263569 dated December 1, 2000.

Change Request ? Perform loop reclamation for CLECs and provide prior notice of Qwest’s loop reclamation. Qwest has indicated that it will not perform loop reclamation to prevent a CLEC order from going into held status. In contrast, when Qwest “wingback” a customer from a CLEC, Qwest will perform loop reclamation and will do so without prior notice to the CLEC. For example, as shown in the example below, when Eschelon has placed a disconnect order on a UNE loop, Eschelon has received a rejection notice from Qwest indicating that Qwest has already disconnected the loop as a result of loop reclamation. Qwest disconnected the loop without prior notice to Eschelon. Because of this practice, an order will be processed (and not go into held status) for a Qwest retail customer, whereas a CLEC order would go into held status. The CLEC end-user customer would experience a delay (and possibly additional costs and service disruption), whereas the Qwest end-user would not. Please modify Qwest’s processes to perform loop reclamation for CLECs and provide prior notice of Qwest’s loop reclamation.

Qwest response ? During our investigation we found that at times, the Small Business and Consumer groups were not always doing total loop reclamation on the end-users returning to Qwest for local services. Qwest has escalated this issue and pulled together a team from the Wholesale and Retail organizations to review current process and develop a new process to do full reclamation of facilities to provision loops. Extensive training on the new procedure has started. We are phasing in the new process as training is completed. Retail has made the commitment to perform full loop reclamation of facilities by Nov. 1, 2001. Additionally, we are developing a plan to address prior loops that should have been reclaimed. That plan will be completed by 10/26/01. Finally Qwest is investigating how we would notify customers of loss alerts. The initial project plan should be complete by 11/1.

We are confident that the Retail organization understands the importance of loop reclamation and we will continue to monitor and make improvements on this process.

Sincerely,

Susan Bliss Director – Process Management


Open Product/Process CR 5371475 Detail

 
Title: Allow non design affecting due date changes for unbundled loop orders
CR Number Current Status
Date
Area Impacted Products Impacted

5371475 Denied
10/17/2001
Ordering Unbundled Loop
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Hoag, Nancy
Director:
CR PM:

Description Of Change

At present, for unbundled loop orders, Qwest imposes a 5-day interval for a supplemental order, even if the only change is to move out the due date. For example, a CLEC's customer may have scheduled an appointment for a Friday. On Thursday, the end-user customer notifies the CLEC that Friday will no longer work, and the end-user customer asks to change the date to Monday instead. Under Qwest's current policy, the CLEC must deny the customer's request, because Qwest will impose a 5-day interval. With that interval, the earliest date available to the end-user customer will be the following Thursday. This is true even though the change does not affect design, and the date is pushed out (not moved up).

For POTs resale and on the design side for DSOs, the due date can be changed in less than 5 days, provided that the change is not design-affecting. Qwest should change its process to similarly allow due date changes in less than 5 days (when not design-affecting) for unbundled loop orders.


Status History

02/01/01 - Submitted 2/01/01 New to be validated

02/01/01 - New to be reviewed

02/05/01 - Reviewed under consideration

02/05/01 - Discussed during Qwest CR review. Will be discussed in the February CICMP Meeting (CB)

02/08/01 - Qwest is currently reviewing and formulating a solution which will be discussed in the March CICMP Meeting (CB)

02/21/01 - CR Transitioned to Systems CICMP for resolution 3/7/01 - CR transitioned to Product/Process

03/21/01 - CR Transitioned back to Product/Process (MR)

04/06/01 - Interval for non design-affecting due date changes for unbundled loop orders has been reduced to 3 days. Process will be discussed during the April CICMP Industry Team Meeting (DS – MR)

04/18/01 - Written documentation around the stated 3-day interval required from Qwest in order to complete this CR (MR)

05/15/01 - Qwest will now accept a version or a SUP of a LSR for a non- design effecting change with a 3-day interval. Release documentation illustrating this reduces standard interval is currently being drafted by Qwest and will tentatively be communicated by 6/01/01. (RU)

06/12/01 - Qwest issued release notice PDRN 061901-1, FCC ISP Order.

06/18/01 - Qwest is unable to reduce the standard interval for non-design effecting due date changes for unbundled loop orders to less than 3 days due to required 48 hour advance work scheduling restriction of Qwest central office and outside technicians and coordinator/implimentor.

07/13/01 -Qwest process personnel looking at alternative options to satisfy this request – update will be given during the July 18th monthly CICMP Meeting. (MR) Nancy Hoag to draft response by 8/9/01 to discuss at CICMP

08/09/01 - CR Response sent to the CIMCP team via email for discussion during the August CICMP Industry Team Meeting. (MR)

08/15/01 - CLEC CMP Meeting Product & Process CR 5371475. Qwest presented its response dated 08/13/01. Eschelon to review to determine whether to escalate. Qwest to provide documentation on escalation procedures.

09/04/01 - Qwest issued draft revised response

09/06/01 - Comments received by Eschelon - review meeting to be scheduled

09/07/01 - Qwest provided feedback to Eschelon's comments

09/14/01 - Qwest response issued to Eschelon

09/14/01 - Qwest conducted a Walk-through on Qwest's 09/04/01 response with Eschelon. Eschelon agreed to accept Qwest's 09/04/01 response. Qwest to issue meeting minute.

09/19/01 - CMP Meeting - Qwest reviewed its draft response. Eschelon advised that they felt Qwest denied the CR and wanted to defer the CR.

10/17/01 - CR "Denied" based on discussion during October 2001 CMP Monthly Meeting

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

Friday 14th September 2001 Introduction of Attendees Kathy Stichter, Eschelon Bonnie Johnson, Eschelon Chris Siewert, Qwest Jerri Brooks, Qwest Ric Martin, Qwest Pat Levene, Qwest Nancy Hoag, Qwest

Introduction of participants on the Conference Call was made. The purpose of the call was to discuss Qwest’s draft response dated September 4, 2001 and Eschelon’s e-mail comments. Review of Response N Hoag reviewed the Change from 5 days to 3 days. B Johnson indicated that there would be a rare occasion where they might need less than 3 days. She provided the example of when a customer was moving lines and they couldn’t make Friday due to equipment, or other issues. She would like Qwest to work with them to improve the date from the improved 3 days. Bonnie indicated that a VP expedite could be difficult to obtain. N Hoag explained that the primary reason that Qwest could not commit to improve on the days was due to CO and Technician resource were typically committed between those days. C Siewert advised that, in these situations, Eschelon could look into switching out an existing order. If that can’t be done, then they would have to move to VP Escalation. Eschelon asked how DS0 orders were handled. C Siewert advised that they would call in for available time and if none were available, they would move to VP Escalation. B Johnson indicated that the VP Escalations have improved. They will play the new process by ear and attempt to get times improved as required. Eschelon asked if, on POP Orders, the customer was willing to pay for overtime, could Qwest accommodate the request. C Siewert advised that Saturday is a normal workday and didn’t believe OT could be accommodated. C Siewert asked B Johnson to provide the Order No. they were looking to have Monday and she will investigate. B Johnson advised that they will go through the escalation process and we could close this CR. K Stichter agreed. N Hoag will issue the draft response formally to M Rossi for issuance to Eschelon.

09/07/2001 08:56:12 AM Nancy Hoag on

To: klstichter@eschelon.com cc: lsteckl@qwest.com

Subject: CR 5371475

Kathy,

Please review the attached letter. Under the "Qwest Response" bullet, you will see that the processes for Retail and Complex Resale DSO's were included:

These are the same Methods & Procedures used by Qwest Service Delivery for all Designed Services, including Wholesale DSO. For due date changes on Qwest Wholesale POTS as well as Qwest Resale and Retail Non Designed Services, Appointment Scheduler is used to determine the next available appointment time.

As for the second issue, I plan on meeting with Steve Sheahan, Toni Dubuque and Bonnie Johnson to discuss how Qwest can best accommodate Eschelon's needs with respect to critical ICB escalations. I consider this issue as an action item, separate from the CR that was submitted. If you could provide me Bonnie's email address, I will forward the information once the meeting has been scheduled.

Nancy J. Hoag Wholesale Products/Unbundled Loop

-- 9/6 e-mail from K Stichter

Lynn, We understand the Response. What we are looking for are 2 items that Eschelon previously requested and we thought were agreed to by Nancy Hoag. They are: 1. Documentation stating the Retail DSO and Complex Resale DSO process for DD changes that do not affect the design. 2. Notice of communication with Toni Dubuque on how Eschelon would escalate any critical ICB issues. We look forward to seeing this documentation. Thanks.

Kathy Stichter ILEC Relations Manager Eschelon Telecom Inc Voice 612 436-6022 E-Mail klstichter@eschelon.com

From: Lynn Stecklein [SMTP:lsteckl@qwest.com] Sent: Tuesday, September 04, 2001 3:41 PM To: Stichter, Kathleen L. Cc: rhmart2@qwest.com; Jerri Brooks; Joann Garramone Subject: CR5371475 - Allow non design affecting due date changes for unbundled loop orders

Hello Kathy, Attached you will find the Qwest Response for the above Change Request. Please confirm via E-Mail if this response meets your needs or if we need to set up a walk through to discuss the issue further. Thanks, Lynn 303 294-1664


CenturyLink Response

September 4, 2001 Wholesale Product Marketing Lynne Powers Eschelon Telecom Vice President, Customer Operations

CC: Russ Urevig Matthew Rossi

This letter is in response to your CLEC Change Request Form #5371475 dated February 1, 2001.

Change Request: Allow non design-affecting due date changes for unbundled loop orders. At present, for unbundled loop orders, Qwest imposes a 5-day interval for a supplemental order, even if the only change is to move out the due date. For example, a CLEC’s customer may have scheduled an appointment for a Friday. On Thursday, the end-user customer notifies the CLEC that Friday will no longer work, and the end-user customer asks to change the date to Monday instead. Under Qwest’s current policy, the CLEC must deny the customer’s request, because Qwest will impose a 5-day interval. With that interval, the earliest date available to the end-user customer will be the following Thursday. This is true even thought the change does not affect design, and the date is pushed out (not moved up). For POTs resale and on the design side for DSOs, the due date can be changed in less than 5 days, provided that the change is not design-affecting. Qwest should change its process to similarly allow due date changes in less than 5 days (when not design-affecting) for unbundled loop orders.

Qwest Response:

Per the Wholesale Unbundled Loop Methods & Procedures for Qwest Service Delivery, due date changes have a minimum 3-day interval. If a shorter than 3-day interval is required by a CLEC, they must follow the attached escalation guidelines as provided by your Service Manager.

This change was submitted via the Qwest Release Notification process, Log # PCRN061901-1, on June 19, 2001 by Russ Urevig

These are the same Methods & Procedures used by Qwest Service Delivery for all Designed Services, including Wholesale DSO. For due date changes on Qwest Wholesale POTS as well as Qwest Resale and Retail Non-Designed Services, Appointment Scheduler is used to determine the next available appointment time.

Qwest is unable to further reduce the due date change intervals for the Unbundled Loop Product, due to Central Office and Field Technician load and resource constraints on Designed Service orders.

Sincerely,

Nancy J. Hoag Wholesale Product Team

August 13, 2001

Wholesale Product Marketing

Lynne Powers Eschelon Telecom Vice President, Customer Operations

CC: Russ Urevig Matthew Rossi

This letter is in response to your CLEC Change Request Form #5371475 dated February 1, 2001.

Change Request: “Allow non design-affecting due date changes for unbundled loop orders. At present, for unbundled loop orders, Qwest imposes a 5-day interval for a supplemental order, even if the only change is to move out the due date. For example, a CLEC’s customer may have scheduled an appointment for a Friday. On Thursday, the end-user customer notifies the CLEC that Friday will no longer work, and the end-user customer asks to change the date to Monday instead. Under Qwest’s current policy, the CLEC must deny the customer’s request, because Qwest will impose a 5-day interval. With that interval, the earliest date available to the end-user customer will be the following Thursday. This is true even thought the change does not affect design, and the date is pushed out (not moved up). For POTs resale and on the design side for DSOs, the due date can be changed in less than 5 days, provided that the change is not design-affecting. Qwest should change its process to similarly allow due date changes in less than 5 days (when not design-affecting) for unbundled loop orders.”

Qwest Response:

Per the Wholesale Unbundled Loop Methods & Procedures for Qwest Service Delivery, due date changes have a minimum 3-day interval. If a shorter than 3 day interval is required by a CLEC, they must follow the escalation guidelines.

This change was submitted via the Qwest Release Notification process, Log # PCRN061901-1, on June 19, 2001 by Russ Urevig

These are the same Methods & Procedures used by Qwest Service Delivery for all Designed Services, including Wholesale DSO. For due date changes on Qwest Wholesale POTS as well as Qwest Resale and Retail Non-Designed Services, Appointment Scheduler is used to determine the next available appointment time.

Qwest is unable to further reduce the due date change intervals for the Unbundled Loop Product, due to Central Office and Field Technician load and resource constraints on Designed Service orders.

Sincerely,

Nancy J. Hoag Wholesale Product Team


Open Product/Process CR 5432820 Detail

 
Title: Update SAG records to match LEC records
CR Number Current Status
Date
Area Impacted Products Impacted

5432820 Completed
9/19/2001
Pre-Ordering Centrex, Unbundled Loop
Originator: Sprague, Michelle
Originator Company Name: Eschelon
Owner: Thompson, Jeff
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Not getting an appropriate match in SAG, during the address validation process. The LEC record address is being used in the attempt to validate against SAG, but the SAG records do not match the LEC records. Requesting that Qwest performs a mass update on the SAG files to correspond with the LEC records, or that the LEC records are revised to match the SAG address files.


Status History

3/05/01 – Received CR from Mark Routh – CICMP Manager – Systems

3/07/01 – Status changed to New – To be Reviewed

3/07/01 – Status changed to Reviewed – Under Consideration 3/07/01 – Discussed in March CR review meeting

3/07/01 – Qwest is not able to modify the SAG and will not change the LEC. (JT)

3/21/01 – Unable to close due to McLeod’s absence at the March CICMP meeting. (MR)

4/16/01 – Unable to cancel CR due to Michelle Sprague’s absence from the April CICMP Industry Forum. (MR)

5/18/01 - Unable to cancel CR due to Michelle Sprague’s absence from the April CICMP Industry Forum. (MR)

6/20/01 - Unable to cancel CR due to Michelle Sprague’s absence from the April CICMP Industry Forum. (MR)

7/11/01 – Email sent to Michelle Sprague to close CR – Clarification on response requested.

08/28/01 - Response emailed to Michelle Sprague at McLeod USA

08/28/01 - Walk through meeting held

08/29/01 - Michelle Sprague closed CR via email to Qwest

09/19/01 - Response Accepted at the 09/19/2001 CMP Forum

09/19/01 - CR Closed at the 09/19/2001 CMP Forum


Project Meetings

Email from Michelle Sprague, McLeod USA August 29, 2001 Concurs with the closing of CR5432820.

Tuesday, August 28, 2001, Walk through Meeting Attendees: Michelle Spraque - McLeod, Peggy Esquibel-Reed, Todd Mead, and Irene Haskins/Qwest CLEC Expectations: McLeod would like Qwest to perform a mass update on the SAG files to correspond with the LEC records, or that the LEC records are revised to match the SAG address files. Mcleod agreed to close the CR and open another to address the following questions: During the address validation process via EDI, when performs an AVQ Hit, SAG address is returned. When performs a CSRQ Hit, the address from the CSR is returned. When the ISC gets an order from a CLEC, does the ISC use the address from the SAG or from the CSR? Which is the correct data source to use? Can the CLEC use just one of these data sources instead of both? Does the ISC use the SAG or the MSAG (911 address)? Which should be used?

Wednesday, August 15, 2001, CLEC CMP Meeting Product & Process. Lynne Powers questioned how SAG records get updated. Jeff Thompson advised that he wasn't sure how Telcordia issues updates, but Qwest can't get Telcordia to utilize Qwest's database. Jeff indicated that he would do some research on finding out how to get updates to Telcordia for their database. Mcleod provided Michelle Sprague as their contact at 319-790-7402.


CenturyLink Response

August 27, 2001

Michelle Sprague OSS Manager, McLeod USA

This letter is in response to the following CLEC Product & Process Change Request Form #5432820.

Request:

Not getting an appropriate match in SAG, during the address validation process. The LEC record address is being used in the attempt to validate against SAG, but the SAG records do not match the LEC records. Requesting that Qwest performs a mass update on the SAG files to correspond with the LEC records, or that the LEC records are revised to match the SAG address files.

Qwest agreed to investigate and report on what the process was for updating the SAG.

Qwest Response: * SAG is a Telecordia product. * Qwest is not able to modify the SAG and will not change the LEC. * The CLEC SAG book is a hybrid, it’s a Telecordia product and is an extract of the PREMIS database. It is created monthly. The CLEC SAG takes the QWEST SAG and additional information is extracted from the database and concatenates the two. Items not appropriate are not extracted and an item such as an NPA wire center that isn’t in the regular SAG book is added. * Qwest process for updating the SAG: - The Address Management Center’s are responsible for the data in PREMIS. Any service order fall-out or addresses that need to be updated, they are the group that does the work. - Should the CLEC find an address range that is incorrect, the CLEC calls interconnect and give’s them that information. - Interconnect contacts the AMC. - The AMC verifies with the appropriate county to make sure is valid and if it is, they update the database. - The following months extract will contain the new information. - Data is only extracted or updated once a month.

Jeffery L. Thompson Director, Information Technologies


Open Product/Process CR PC032801-2 Detail

 
Title: Process regarding circuit identification for CLEC to CLEC carrier changes
CR Number Current Status
Date
Area Impacted Products Impacted

PC032801-2 Completed
8/15/2001
Ordering Centrex, Resale, Unbundled loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Urevig, Russell
Director:
CR PM:

Description Of Change

Qwest recently announced a process regarding CLEC-to-CLEC carrier changes that required the CLEC acquiring the customer to obtain the circuit identification (“i.d.”) from the donor CLEC. (At the previous CICMP meeting, Qwest indicated that its retail group should be following the same process and should not be using loop reclamation for this purpose. Qwest’s use of the loop reclamation process to date, however, demonstrates that Qwest does have access through its own record to accurate circuit i.d. information.) A problem arises when Qwest changes the circuit i.d. after assigning it to a CLEC but without notification to the CLEC. The donor CLEC will provide the old circuit i.d. information to the acquiring CLEC, because the donor CLEC is unaware that Qwest has changed the circuit i.d. Then, the acquiring CLEC will encounter problems in the CLEC-to-CLEC exchange because the circuit i.d. information is inaccurate. Qwest should develop a procedure to ensure that circuit i.d. information is correct and for dealing with and escalating problems when they arise. Inaccurate circuit i.d. information should not delay CLEC orders and customers.


Status History

3/26/01 – CR Received from Karen Clauson of Eschelon

3/28/01 – CR Logged and status changed to New – To be Evaluated

4/06/01 – Status changed to Reviewed – Under Consideration 4/06/01 – Discussed in April CR Review Meeting.

4/16/01 – Qwest will address this during the April CICMP Industry Team Meeting (LW)

4/18/01 – “Patch” for obtaining circuit ID from OLSP to accept LSRs required to complete this CR (MR)

4/20/01 – “Patch was put in place to allow request on an action code of “C” with no required Circuit ID.

6/20/01 – Process implementation for enhanced Circuit ID Process to be verified and presented in interim meeting to be scheduled by Qwest prior to the July CICMP Meeting. (MR)

7/10/01 – Interim conference call conducted to discuss Advanced Notification of CKID changes – meeting minutes sent to the CICMP team on 7/12/01 (MR)

7/13/01 – Drafted response sent to the CICMP Team via email (MR)

8/07/01 – Eschelon and Allegiance confirmed that LSRs are being submitted and handled properly in relation to Qwest’s process on Circuit ID attainment. (MR)

8/09/01 – Revised CR response distributed to the CICMP team via email. (MR)

8/15/01 – CLEC CMP Meeting Product & Process CR PCCR032801-2. It was agreed that the CR was closed due to successful processing of LSRs with revised procedure for CKTIDs. Closed

3/28/02 Qwest response posted to CMP database. Response had been posted to the Web as a stand alone document within the Change Request Archive.


Project Meetings


CenturyLink Response

July 10, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom, Inc

CC: Russ Urevig Matthew Rossi

This letter is in response to your CLEC Change Request Forms, numbers PCCR032801-2 and PCCR032801-3 dated March 26, 2001.

* "Advance notice of circuit identification changes. A problem arises when Qwest changes the circuit id after assigning it to a CLEC but without notification to the CLEC. Qwest should develop a process for notifying other carriers when circuit id information is changed. Inaccurate circuit information should not delay CLEC orders and cutovers."

* Response: The existing process used in centers today states: "Anytime a change is made to a CLEC request, including changing the circuit ID (identifier), SBN (subscriber billing number), due date or specified appointment time, and the changes are NOT requested by the CLEC, a "new" FOC must be issued and the changes identified in the remarks of the new FOC."

To ensure process compliance, a MCC (Multi Channel Communicator) was re-distributed on July 2, 2001, to all centers in AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NM, OR, Outside 14 State Region, SD, UT, WA, and WY.

Sincerely,

Nancy J. Hoag Wholesale Product Manager


Open Product/Process CR PC032801-3 Detail

 
Title: Advance notice of circuit identification changes
CR Number Current Status
Date
Area Impacted Products Impacted

PC032801-3 Completed
7/18/2001
Ordering Centrex, Resale, Unbundled loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Urevig, Russell
Director:
CR PM:

Description Of Change

A problem arises when Qwest changes the circuit i.d. after assigning it to a CLEC but without notification to the CLEC. Qwest should develop a process for notifying other carriers when circuit i.d. information is changed. Inaccurate circuit i.d. information should not delay CLEC orders and cut overs.


Status History

3/26/01 CR Rec. from K. Clauson of Eschelon 3/28/01 CR Logged and status changed to New To be Evaluated 4/06/01 Status chg. to New To be Clarified 4/06/01 – Discussed in April CR Review Meeting

4/06/01 – Clarification needed by Eschelon, request sent via email to Lynne Powers, Karen Clauson and Jessica Johnson (MR)

5/14/01 – Sited examples faxed by Jessica Johnson of Eschelon and currently being investigated by Qwest (MR) 5/14/01 Status chg. to New - To be Evaluated 5/16/01 Status changed to reviewed - under consideration

6/15/01 – Russ Urevig to speak with Jessica Johnson on sighted examples. Will be discussed at the 6/20 CIMCP meeting. (RU-MR)

6/20/01 – Process of Advanced Notification to be discussed in interim CLEC meeting prior to July CICMP meeting (MR)

7/10/01 – Interim conference call conducted to discuss Advanced Notification of CKID changes – meeting minutes sent to the CICMP team on 7/12/01 (MR)

7/13/01 – Drafted response sent to the CICMP Team via email (MR)

07/18/01 - CMP Meeting - It was agreed that the CR could be closed.


Project Meetings


CenturyLink Response

July 10, 2001

Lynne Powers Vice President, Customer Operations Eschelon Telecom, Inc CC:Russ Urevig Matthew Rossi

This letter is in response to your CLEC Change Request Forms, numbers PCCR032801-2 and PCCR032801-3 dated March 26, 2001.

“Advance notice of circuit identification changes. A problem arises when Qwest changes the circuit id after assigning it to a CLEC but without notification to the CLEC. Qwest should develop a process for notifying other carriers when circuit id information is changed. Inaccurate circuit information should not delay CLEC orders and cutovers.”

Response: The existing process used in centers today states: “Anytime a change is made to a CLEC request, including changing the circuit ID (identifier), SBN (subscriber billing number), due date or specified appointment time, and the changes are NOT requested by the CLEC, a “new” FOC must be issued and the changes identified in the remarks of the new FOC.”

To ensure process compliance, a MCC (Multi Channel Communicator) was re-distributed on July 2, 2001, to all centers in AZ, CO, IA, ID-N, ID-S, MN, MT, ND, NM, OR, Outside 14 State Region, SD, UT, WA, and WY.

Sincerely, Nancy J. Hoag Wholesale Product Manager


Open Product/Process CR PC032801-4ES Detail

 
Title: Advance notice of profile and rate changes
CR Number Current Status
Date
Area Impacted Products Impacted

PC032801-4ES Denied
12/12/2001
Ordering Other
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner: Burson, Sue
Director:
CR PM: Thomte, Kit

Description Of Change

Qwest requires CLECs to complete customer questionnaires/profiles, in addition to entering into interconnection agreements with Qwest, when CLECs enter a Qwest state. Periodically, the questionnaires/profiles are updated, agreements are amended, or rates change. When these documents are completed or rates change, Qwest generally makes changes in its systems to reflect such changes. For example, if a CLEC signs an amendment to its interconnection agreement that contains new rates, Qwest may load additional USOCs with those rates into a table that is specific to that CLEC in that state. Before the USOCs and rates are loaded, Qwest’s systems reject orders for items associated with those USOCs. After they are loaded, the systems will process the orders. While some of these changes may be apparent to the CLEC because they coincide with execution of such documents, sometimes Qwest makes unanticipated changes to the system or the codes. For example, Eschelon has been ordering coordinated cutovers in Minnesota for some time. Suddenly, without notice to Eschelon, Qwest’s systems began to reject those orders. Upon inquiry, Qwest’s representatives indicated that Qwest had performed a “scrub on interconnect contracts” pursuant to which Qwest unilaterally determined that Eschelon could not order coordinated cutovers in Minnesota because Eschelon had not signed a contract amendment proposed by Qwest. Only after Eschelon demonstrated that its existing contract, without amendment, provides for coordinated cutovers did Qwest restore Eschelon’s ability to use the functionality of IMA to order coordinated cutovers. In the meantime, Eschelon’s orders were disrupted. If Qwest had notified Eschelon sufficiently in advance of its “scrub” of Qwest’s plans, Eschelon could have addressed the issue at that time and avoided the disruption to its ordering and provisioning processes. Qwest should implement a process to provide advance notice to CLECs before changes are made to the CLEC’s profile and rates in Qwest’s systems. The notice should be sufficiently detailed to allow the CLEC to understand the implications of the change and should be provided sufficiently in advance of any change to allow the CLEC to object, if necessary. A process should be put in place to handle objections to changes before the changes are made.


Status History

03/26/01 - CR Received from K. Clauson of Eschelon

03/28/01 - CR Logged and status changed to New – To be Evaluated

04/06/01 - Status changed to Reviewed – Under Consideration

04/06/01 - Discussed in April CR Review Meeting

04/16/01 - Qwest will address this during the April CICMP Industry Team Meeting (TK - SC)

04/18/01 - Qwest is currently working this issue (AZ)

05/14/01 - Qwest has identified 3 circumstances (1) Contract amendment or new contract in which the Qwest Service manager will provide notification, (2) Cost Dockets or state PUC rulings in which letters are mailed to effected CLECs, (3) Internal maintenance required in which a process is currently being developed in which the Qwest Service managers will provide notification to the CLEC. Written documentation will be prepared by Qwest and communicated externally, tentative time frame for notification TBD. (AZ)

08/09/01 - CR Response sent to the CICMP team via email and included in the August CICMP Distribution Package. (MR)

08/15/01 - CLEC CMP Meeting Product & Process Qwest's response dated 08/03/01 was presented

09/19/01 - CMP Meeting -Qwest provided status update.

09/27/01 - Qwest's draft response posted to database.

10/17/01 - CMP Meeting: Qwest presented draft response. Qwest to revisit response and address "Clarification on how CLEC gets notification on rate and USOG changes." No "Current Status" change.

11/09/01 - Revised Draft Response dated 11/09/01sent to Eschelon and posted in dBase.

11/14/01 - CMP Meeting - Qwest presented its revised response. CLECs expressed concern over changes to rate table without advance notifications. Qwest requested that this subject be reviewed off-line. It was agreed that this would be an agenda item for next month's CMP meeting.

12/12/01 - CMP Meeting - Alan Zimmerman, Qwest presented an update to the current Qwest response regarding advance notice of profile and rate table changes. A written summary of this update has been posted in the CMP database. Qwest indicated that an internal validation (scrub) of the profile and rate tables is currently in progress for all CLECs. This validation addresses USOCs and SGAT rates, and should be completed this year. The CLEC community requested a redline of the validation changes prior to incorporation into billing. Qwest indicated that no feasible mechanism is available to provide advance notification for the validation exercise. However, Qwest will provide final USOG and SGAT rates for all CLECS when the validation effort is completed. Eschelon requested that the current validation effort by Qwest be stopped until an advanced notice procedure is in place. Discussions resulted in Qwest committing to re-look ways to provide advance notice for the validation exercise. Qwest committed to instituting a new process by March 1, 2002 to provide advance notice to the CLECs for the following rate change catalysts: (1) future rate validation efforts, (2) cost dockets, (3) new/existing interconnect agreements, (4) bill errors/disputes, and (5) new product implementation and product price changes. "Current Status" of CR remains in "Presented" status.

01/03/02 - Formal escalation received from Eschelon.

01/04/02 - Qwest transmitted acknowledgement of receipt to Eschelon. Escalation posted in Qwest Wholesale WEB page [http://www.qwest.com/wholesale/cmp/escalations.html].

01/07/02 - Allegiance, Covad, Integra and Worldcom notified Qwest of participation in formal escalation submitted by Eschelon (01/03/02).

01/08/02 - AT&T notified Qwest of participation in formal escalation submitted by Eschelon (01/03/02).

01/11/02 - Qwest formal escalation response transmitted to Eschelon and associated participating CLECs; and posted in Qwest Wholesale WEB page [http://www.qwest.com/wholesale/cmp/escalations.html].

01/16/02 - CMP Meeting - Susan Burson, Qwest provided update and overview of Qwest response (01/11/02) to the formal escalation submitted by Eschelon.

01/25/02 - Qwest formal escalation revised response transmitted to Eschelon and associated participating CLECs; and posted in Qwest Wholesale WEB page [http://www.qwest.com/wholesale/cmp/escalations.html].

01/31/02 - Eschelon submitted response to Qwest formal escalation revised response [http://www.qwest.com/wholesale/cmp/escalations.html].

02/08/02 - Qwest responsed to Eschelon response (dated 01/31/02) [http://www.qwest.com/wholesale/cmp/escalations.html].

02/12/02 - Eschelon responsed to Qwest response (dated 02/08/02) [http://www.qwest.com/wholesale/cmp/escalations.html].

02/20/02 - CMP Meeting - Susan Burson, Qwest provided update on the formal escalation submitted by Eschelon. Qwest will provide a response to the most recent Eschelon escalation communication (dated 02/12/02). CR remains in "Escalated" status. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

02/21/02 - Qwest responsed to Eschelon response (dated 02/12/02).

02/22/02 - Qwest response to Eschelon posted in Wholesale WEB page [http://www.qwest.com/wholesale/cmp/escalations.html].

03/20/02 - March CMP Meeting: Status update was presented. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/17/02 - April CMP Meeting: Qwest provided a status update. CR status remains "Escalated." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

05/15/02 - May CMP Meeting: CR status remains "Escalated." Qwest deferred discussion to the presentation that occurred later in the meeting

07/08/02 - Per the agreement reached with the CLECs in the June Product and Process CMP meeting regarding escalated status this CR will carry the appropriate status prior to the escalation


Project Meetings


CenturyLink Response

CLEC Rate Notification Process (Submitted by Alan Zimmerman, Qwest & presented in the December 12, 2001 Product & Process Monthly CMP Meeting)

Document Overview

The purpose of this document is to describe the different factors that drive rate changes, as well as outline the process by which Qwest will notify CLECs of these changes. It is important to note that contractual obligations may supersede the guidelines outlined below.

Rate Change Catalysts and Notification Processes

Qwest has identified five main categories of items that drive rate changes – validation efforts, cost docket changes, interconnect agreements and amendments, bill errors/disputes, and new products/product pricing changes. Brief descriptions of these categories and the process by which the CLECs are notified are found below:

? Rate Validation Efforts

Qwest recently carried out a rate validation effort, to verify that bills properly reflect the rates ordered by the State Commission and/or the rates modified as a result of contract negotiations. Following the completion of the Rate Validation efforts, profiles will be available for each CLEC by state, by product which will detail the rates they are currently being charged.

Qwest will develop a process by March 1, 2002 so that if Qwest undertakes comprehensive validation efforts in the future, notification of any corrections will be provided to the CLECs at least 10 days before changes are made to the billing systems. Notification will include the product affected, the currently billed and the new rate, the effective date of the rate change, and the rate implementation date.

? Cost Dockets

Cost dockets are state-mandated rates, determined by the Public Utilities Commission (PUC) for each state. Generally, state governments do not mandate notification timeframes for cost docket rate changes, however, Qwest will be implementing a new process in which CLECs will receive two notifications.

The first notification to the CLEC occurs when an interconnect agreement is updated in Qwest’s interconnect agreement repository. At this point, the CLEC can request a copy of the updated interconnect agreement from their service manager. By March 1, 2002 Qwest will develop a process for a second notification to occur at least 10 days prior to the implementation of the new interconnection agreement rates in the billing system. The notices will contain information regarding the product that is changing, the new rate, the effective date of the change, and in the case of the second notice, the planned implementation date.

? New/Existing Interconnect Agreements

The purpose of a new interconnect agreement is to establish billing for all products included in the agreement. Each product is assigned a negotiated or a state-mandated rate. Amendments are used to either add a new product to an interconnect agreement, or change the rate of an existing product. CLEC Rate Notification Process

The CLEC is notified when an interconnect agreement is received by the contract implementation specialist. A second notification, that identifies CLEC ordering can occur, is initiated by the Service Manager when the agreement is finalized. Note: The PUC will send Qwest & the CLEC notification when they accept or reject an interconnect agreement.

? Bill Errors/Disputes

When a CLEC reports a rate discrepancy, the Billing SDC will fix the bill to reflect the correct In addition the SDC will notify a Contract Implementation Specialist to initiate a system rate change so that the rate can be fixed going forward.

If a Billing SDC notices that a CLEC is being charged the wrong rate they will fix the bill to reflect the correct rate and call the CLEC to notify them of the change to their bill. In addition the SDC will notify a Contract Implementation Specialist to initiate a system rate change so that the rate can be fixed going forward. ? New Product Implementation and Product Price Changes

CLECs will be made aware of the availability of new products through the CMP process. On an individual CLEC basis, interconnect agreements can then be amended to include the new product. Please refer to the New/Existing Interconnect Agreements section above.

Occasionally, Qwest product managers initiate product rate changes (for non-cost docketed products) as a result of a costing analysis. These new rates are loaded into the SGAT and available to new CLECs through the creation of interconnect agreements, and to existing CLECs through the interconnect agreement re-negotiation/amendment process.

? General

If at any time a CLEC has a question about a specific product or rate, Qwest Billing Representatives are available to handle such inquiries. To request a profile of all rates by state, by product, a CLEC should contact their Service Manager.

Wholesale Product Marketing

November 9, 2001

Lynn Powers Vice President, Eschelon Telecom, Inc.

CC: Matthew Rossi

This letter in response to your CLEC Product & Process Change Request Form number PCCR032801-4. ? Request - Qwest should implement a process to provide advance notice to CLECs before changes are made to the CLEC’s profile and rates in Qwest’s systems. The notice should be sufficiently detailed to allow the CLEC to understand the implications of the change and should be provided sufficiently in advance of any change to allow the CLEC to object, if necessary. A process should be put in place to handle objections to changes before the changes are made. ? Response – The profile problems Eschelon was experiencing are based on two different root causes and Qwest is committed to improving the overall process. Listed below are the root causes of the recent problems and our process improvements and recommendations: 1. Qwest performed a scrub of the database and made changes without customer notification or input based on the output of the scrub. Effective 7/18, Qwest implemented a process to notify Co-providers when USOCs available to them are deleted from the ordering systems for normal maintenance purposes. This notification will happen at least 10 days in advance of the actual deletion, and would be provided through the Service Manager or via a direct letter. In the case of a USOC being deleted for all Co-providers, a common letter will be sent to all. In the case of individual Co-provider effects, the Service Manager will provide this notification directly to the affected Co-provider. An exception to this advance notification might be made in the case of system outages or other extreme events, however these should be very rare. As a normal course of business, ten days advanced notification would be provided. 2. Recently Eschelon experienced a problem with placing orders for Coordinated Loop cuts in Colorado. This is where Eschelon turned up their switch for the first time and began attempting to place orders. The root cause of this problem was based on recent agreements between the companies and the uncertainty of which rates needed to be loaded into our systems for this work. As soon as we discovered the system needed a rate in order to process the orders, we immediately escalated internally. Based on your experience, Qwest wants to take an additional look at our internal processes to determine if cross-functional resources and additional processes are required.

? In the August CMP meeting, Eschelon asked how to obtain a current copy of a CLEC’s valid USOCs to be used for verification. This is done on a state by state basis via the Service Manager, who can have a report pulled from the CPS (formerly known as CPPD) system with all USOCs loaded for that CLEC by state. This report would contain all USOCs that the CLEC can order in that state. This would enable a CLEC to proactively identify circumstances that cause problems like those in paragraph number 2 above.

? At the October meeting, Eschelon asked for further clarification on the process of notifications for cost docket and contract/amendment implementations. As discussed in the May and August CMP meetings, there are processes already in place for these situations. In the case of rate case or cost docket implementations that affect multiple CLECs, Qwest sends a letter to each CLEC affected informing the CLECs of the implementation. This notification is generally at least 10 days before the implementation. In the case of individual contracts or amendments that are implemented for a specific CLEC, that CLEC’s service manager will notify the CLEC of the implementation date, and the particular products being implemented. This notification will be done when the implementation date is determined. ? For new product introductions, current practice is that a product announcement is sent to all CLECs advising of the availability date for that product at least 30 days prior to the availability. This is currently being discussed in the CMP Redesign meetings. ? As communicated in a November 1st notification, Qwest is currently undertaking a major validation of rates for all CLECs in all states. To the extent rate discrepancies are discovered, Qwest will make the necessary changes to the rate tables in order to put those rates in sync with the current contracts and cost docket rulings. At the conclusion of that effort, targeted for early December, Qwest will send a USOC report to each affected CLEC so that the CLEC can validate the rates loaded for their USOCs.

I believe this addresses all the issues raised by this CR. If you would like to discuss the response in detail. I can be reached at (303)896-8346 or azimmer@qwest.com. Have a good day!

Alan Zimmerman Qwest Wholesale Process Manager

-- August 3, 2001

Lynn Powers Vice President, Eschelon Telecom, Inc. CC:Matthew Rossi

This letter in response to your CLEC Product & Process Change Request Form number PCCR032801-4. Request: Qwest should implement a process to provide advance notice to CLECs before changes are made to the CLEC’s profile and rates in Qwest’s systems. The notice should be sufficiently detailed to allow the CLEC to understand the implications of the change and should be provided sufficiently in advance of any change to allow the CLEC to object, if necessary. A process should be put in place to handle objections to changes before the changes are made. Response: As discussed at the 5/14 CICMP meeting, processes already exist within Qwest for notifying Co-providers of changes when rate cases or other regulatory activity has occurred. There are also existing processes enabling service managers to advise Co-providers of changes due to contract implementations or changes. There is no process for notifying Co-providers when USOCs are changed as a course of maintenance within Qwest systems.

Effective 7/18, Qwest implemented a process to notify Co-providers when USOCs available to them are deleted from the ordering systems for normal maintenance purposes. This notification will happen at least 10 days in advance of the actual deletion, and would be provided through the Service Manager or via a direct letter. In the case of a USOC being deleted for all Co-providers, a common letter will be sent to all. In the case of individual Co-provider effects, the Service Manager will provide this notification directly to the affected Co-provider. An exception to this advance notification might be made in the case of system outages or other extreme events, however these should be very rare. As a normal course of business, ten days advanced notification would be provided.

If you have any questions or comments about this policy, feel free to contact Alan Zimmerman at (303)896-8346 or azimmer@qwest.com. Have a good day!

Alan Zimmerman Qwest Wholesale Process Manager


Open Product/Process CR PC123002-1 Detail

 
Title: Migrate and move documentation on Qwest Wholesale Web site for the process used when the customer is converting and moving to a different CO and remaining in the same rate center.
CR Number Current Status
Date
Area Impacted Products Impacted

PC123002-1 Completed
12/30/2002
Provisioning, Ordering Resale, UNE-P
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Anderson, Jill (Merry)
Director:
CR PM: White, Matt

Description Of Change

As a result of the Quality Team lead by Toni Dubuque (Closed CR PC091901-1), Joan Wells Qwest Process Specialist documented process flows on the Qwest Wholesale web site. These process flows included customers that were changing to a new Local Service Provider (LSP) and moving to a new Central Office (CO) but were within the same rate center, as well as those customers that were remaining in the same CO. When the EUM field was activated with the implementation of 11.0 (applies to only customers changing their LSP and moving within the same CO), Qwest updated the documentation for the use of the EUM field, but Qwest removed the documentation that once applied to both scenarios. Under the process that exists but now is not documented on the Wholesale Web site, customers keep their existing TNs, but the order requires a port within. Eschelon personnel referred to these process flows for submitting “migrate and move” LSRs. Removing the documented process flows for this type of LSR can cause LSR errors up to and including customer out of service conditions. In addition, CLECs that have not been involved in this issue to date may not know this process is available to them. Eschelon asks Qwest to restore to the Qwest Wholesale web site the process used when the customer is converting and moving to a different CO and remaining in the same rate center.


Status History

12/30/02 - CR Submitted

01/02/03 - CR Acknowledged

01/10/03 - Clarification Meeting

01/15/03 - CR Presented at CMP Meeting

02/12/03 - Qwest response e-mailed to originator

02/19/03 - Qwest response presented at CMP Meeting

03/19/03 - Update presented at CMP Meeting

04/16/03 - Update presented at CMP Meeting

05/21/03 - Discussed at CMP Meeting


Project Meetings

05-21-03 - CMP Meeting

This CR was implemented with the changes in PC100401-1XMN.

==================================================

04-16-03 - CMP Meeting

Wells-Qwest stated that Qwest would respond to CLEC comments to the changes on 4/28 and implement the changes on 5/13. No status change.

=====================================================

03-19-03 - CMP Meeting

Anderson-Qwest stated that the documentation in support of this change would be out for CLEC review on 4/1.

======================================================

02-19-03 - CMP Meeting

Anderson-Qwest presented the Qwest response. Johnson-Eschelon stated that all she was asking for was for Qwest to document the existing process. She appreciated Qwest’s acceptance of the CR but was curious about why it would take until April 1 to distribute the documentation for review. She asked if it was because the documentation would represent a combined process. Anderson-Qwest stated that Johnson-Eschelon was correct; the integrated process document was more functional but took longer to develop. White-Qwest stated that the CR would move into Development status.

=========================================================

01/15/03 - CMP Meeting

Johnson-Eschelon presented the CR. CR moved to Presented.

============================================================

Clarification Meeting 1:30 PM (Mountain Time) / Friday, January 10, 2003

1-877-550-8686 2213337# PC123002-1; Migrate and move documentation on Qwest Wholesale Web site for the process used when the customer is converting and moving to a different CO and remaining in the same rate center

Attendees Matt White – CRPM Bonnie Johnson – Eschelon Jill Anderson – Qwest Joan Wells - Qwest

Introduction of Attendees White-Qwest welcomed all attendees and asked Johnson to review the request.

Review Requested (Description of) Change Johnson-Eschelon reviewed the submitted description of change. She stated that she just wanted the manual process back out on the web site. Well-Qwest stated that there is a CR that will change the process for Port-In. Once that CR is approved, Qwest may create documentation for both CRs at the same time. Johnson and Wells discussed the means of documenting this change. Wells-Qwest stated that Jill Anderson will take over that piece to get this documented. Anderson-Qwest stated that she had no questions. Johnson-Eschelon described a related process that she would submit a CR for in the near future. Wells-Qwest stated that was fine and that she could take a look at it when the CR came in. Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Eschelon’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Eschelon to present the CR at the January Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

February 12, 2003

INITIAL RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003, CMP Product/Process Meeting

Bonnie Johnson Eschelon Communications

SUBJECT: Qwest’s Initial Change Request Response - CR #PC123002-1

This change request is accepted. Qwest will add documentation to the Wholesale web site to address this issue. This documentation will be included in a general document, which will also include the Port In Trial process (CR-PC081302-1). Qwest will provide a status of this documentation effort at each Monthly CMP Product/Process Meeting until this change is implemented.

Qwest recommends this CR be updated to Development status.

Sincerely,

Jill Anderson Process Analyst


Open Product/Process CR PC010603-1 Detail

 
Title: MEL (market expansion line) LSR process documented on Qwest Wholesale web site.
CR Number Current Status
Date
Area Impacted Products Impacted

PC010603-1 Completed
4/15/2009
Ordering Resale MEL
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Kilker, Terri
Director:
CR PM: Harlan, Cindy

Description Of Change

Eschelon is asking Qwest to document, on its wholesale web site, the process to submit an LSR for a MEL. Although Qwest has an existing process, Qwest has not documented that process for CLECs. Therefore, when the process breaks down, CLECs are forced to spend unnecessary time and resources debating with Qwest representatives about the process itself, when those challenges could be avoided by simply pointing to mutually accessible documentation that clearly states the process for all involved. Instead, unnecessary escalations waste CLEC and Qwest resources. For example, when Eschelon submitted LSRs for two customer requests, Qwest rejected the requests in error. The escalation process went to tier 3 before resolution was reached and Qwest instructed its personnel that the LSR(s) Eschelon submitted were valid. The requested due dates were missed as a result of the LSRs rejected in error. (Specifically, for these examples, PON CUT2238471TIH1 was submitted on 9/25/02 requesting a due date of 9/30/02. After escalating to tier 3, the service was provided to the customer with a due date of 10/3/02. Another example is PON MN232901MCH sent 10/30/02 with a requested due date of 11/6/02. After escalating to tier 3, the due date of the service was 11/15/02.) In both cases, Eschelon's reputation was damaged with the customer because of Qwest rejects in error._Throughout the escalation process, a CLEC has nothing to refer to with respect to Qwest's process on how to submit an LSR for a MEL. This significantly impacts a CLECs productivity and results in a CLEC not meeting the customer's expectations due to Qwest errors. If Qwest provided the documentation on its web site, unnecessary escalations should be avoided because CLECs could refer the initial Qwest representatives to the process without having to escalate the issue.

Deliverable: Adequate and complete documentation on the Qwest Wholesale web site, in a user-friendly location and format, of the process to submit an LSR for a MEL.

Date: Because this is an existing process, the time to create the documentation on the Wholesale Web site should be minimal.


Status History

01/06/03 - CR Submitted by Eschelon

01/06/03 - CR acknowledged by P/P CMP Manager

01/09/03 - Contacted Bonnie Eschelon to schedule clarification meeting. Offered 3 times via email. Pending confirmation back from Eschelon of Clarification Meeting date/time. Linda Sanchez-Steinke will conduct Clarification Meeting.

1/15/03 - January CMP Meeting - this CR was discussed ealier than required. The clarification call was held after the Jan CMP meeting. Changed this CR to Presented.

01/15/03 - Held clarification meeting

01/21/03 - Clarification Meeting Minutes sent to Bonnie Johnson

01/22/03 - Changed dates to reflect an initial response date of February 12

2/12/03 - Posted Response to database and sent to Eschelon

2/19/03 - February CMP Meeting - meeting minutes will be posted to Project Meeting section.

3/11/03 - Entered Response in database

3/12/03 - Emailed Response to Eschelon

3/19/03 - March CMP Meeting minutes will be posted to the Project Meeting section

3/25/03 - Notification sent out. Announcement Date: March 25, 2003, Proposed Effective Date: May 9, 2003

Document Number: PROS.03.25.03.F.01042.LSOG_Updates

4/16/03 - April CMP Meeting minutes will be posted to the database

5/21/03 - May CMP Meeting minutes will be posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database. Eschelon agreed to close this CR.


Project Meetings

06/18/03 June CMP Meeting Minutes Terri Kilker – Qwest advised the process was published and moved to CLEC Test last month. One comment was received and responded to. Terri asked if it was okay to close this item and Bonnie Johnson-Eschelon advised it was okay to close.

05/21/03 May CMP Meeting Minutes - Terri Kilker Qwest advised this process went out for review on March 31. A comment was submitted to Qwest and it has been responded to. The document was updated on May 9, 2003. We will move this CR to CLEC Test and hopefully close next month..

04/16/03 April CMP Meeting - PC010603-1 MEL: (Market Expansion Line) LSR process documented on Qwest Wholesale web site

Terri Kilker Qwest advised this process went out for review on March 31. A comment was submitted and Qwest is in the process of reviewing the comment. The Comment Response is due April 26, 2003. The implementation date is set for May 9, 2003.

03/19/03 March CMP Meeting - Terri Kilker Qwest provided the CR response. Terri advised the process has been updated and is scheduled for release by March 30, 2003 as a Level 3 Notification. The LSOG and PCAT will contain specific information regarding MEL. Internal documentation will then be made available and the SDC will be trained on the changes. No system changes are required. Bonnie Johnson – Eschelon will review the changes when they are released.

02/19/03 February CMP Meeting - Terri Kilker–Qwest provided the initial response to this CR. Qwest will update the MEL order process documentation. In addition, we are looking at test orders to determine if system changes are needed. We plan on completing the assessment by February 28. At that time we will know what activities need to occur and will determine the implementation plan / schedule. Bonnie Johnson–Eschelon requested that we update the documentation first to clarify the process and then if system changes are needed make additional documentation updates when the system change is complete. Qwest agreed and advised they are planning on updating documentation first.

01/15/03 January CMP Meeting - This CR was included in the package earlier than required. Bonnie did discuss this CR during the January meeting. The Clarification call was held on 1-51-03 after the CMP Meeting. This CR will be changed to presented status.

CLEC Change Request Clarification Meeting

2:00 p.m. (MT) / Wednesday, January 15, 2003

1-877-572-8687 PIN 3393947 # PC010603-1 MEL (market expansion line) LSR process documented on Qwest Wholesale web site. Attendeeds Name/Company: Bonnie Johnson, Eschelon Sr. Manager ILEC Relations Terri Kilker, Qwest Process Analyst Janean Van Dusen, Qwest Product Manager Linda Sanchez-Steinke, Qwest Change Request Project Manager

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of the change requested in the CR was reviewed. Bonnie explained that Eschelon is having problems submitting orders for MEL, expending time and energy on rejects because there is no documentation to refer to when Eschelon puts in orders. The LSR asks for service address and Eschelon provides the central office address as the service address location and orders are rejected that have the billing address used for the service address. Eschelon is asking that the process for MEL order submission be documented on the Wholesale web site.

Confirm Areas & Products Impacted Product impacted is Resale MEL.

Confirm Right Personnel Involved Qwest confirmed that Terri Kilker and Janean Van Dusen are correct personnel to resolve the CR. Bonnie added that Jeff Tietz, Service Manager, has assisted with escalations on MEL orders.

Identify/Confirm CLEC’s Expectation Eschelon is asking that the process for MEL order submission be documented on the Wholesale Web site.

Identify any Dependent Systems Change Requests No dependent change requests were identified.

Establish Action Plan (Resolution Time Frame) Bonnie Johnson presented this CR at the January CMP Meeting.


CenturyLink Response

For Review by CLEC Community and Discussion at March’s CMP Meeting

March 11, 2003

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response – CR # PC010603-1 (MEL (market expansion line) LSR process documented on Qwest Wholesale web site.)

This is in response to Eschelon’s Change Request CR PC010603-01. This CR requests that Qwest clarify and document the LSR order process when ordering the Qwest Market Expansion Line (MEL).

Qwest will post planned updates to its Wholesale Product Catalog that include new and revised documentation for the Resale – Market Expansion Line (MEL) – V3.0 no later than March 31, 2003. These will be posted to the Qwest Wholesale Document Review Site located at http://www.qwest.com/wholesale/cmp/review.html.

Sincerely,

Terri Kilker Process Specialist Qwest

February 12, 2003

INITIAL RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003 CMP Product/Process Meeting

Bonnie Johnson Eschelon

SUBJECT: Qwest’s Change Request Response CR # PC010603-01 MEL (Market Expansion Line) LSR process documented on Qwest Wholesale Web site.

This is in response to Eschelon’s Change Request CR PC010603-01. This CR requests that Qwest clarify and document the Local Service Request (LSR) ordering process for the Qwest Market Expansion Line (MEL) product.

Qwest accepts this CR and will review and clarify the following external documents pertaining to MEL:

* Local Service Ordering Guidelines http://www. qwest.com/wholesale/clecs/lsog.html * Product Catalogs http://www. qwest.com/wholesale/pcat/resalemel.html

As a result of our investigation of Eschelon’s CR, Qwest is also working with its systems operations teams to review the IMA/FTS processes as they relate to use of the Service Address and Billing Address fields used for completion of MEL orders. This is necessary for Qwest to determine whether a system change is required to allow the use of different addresses in the SA and BA fields. We anticipate this assessment will be completed by February 28, 2003, at which time we will develop an implementation schedule for any changes required beyond the provision of documentation.

Sincerely,

Terri Kilker Process Specialist Qwest


Open Product/Process CR PC100401-1XMN Detail

 
Title: LNP Port In/Port Within Completion Call (Crossover SCR100401 1X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC100401-1XMN Completed
7/16/2003
Ordering, Provisioning LNP, Resale: Resale CTX, POTS, DSS, DID, UNE: UNE CTX, POTS, DSS, DID
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Wells, Joan
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

To implement the Port In/Port Within Completion Call process Qwest will utilize the Remarks field of the LSR. Port In and Port Within activity currently use manual processes for order issuance. The Resale or UNE-P Provider will use the Manual IND = Y, with an added Remark entry, " Completion Call requested, CCON Name & CBR". Upon receipt of the LSR, the Centers will then add the necessary USOC to the order and network will follow through with the Completion Call to the Provider. This process as outlined will require SOPS changes, as well as CRIS rating implementation. One-time charges for the Completion Call offering have not yet been determined. The USOC will be $0.00 rated at this time.

Expected Deliverable

Upon completion of the Qwest field work on Port In and Port Within service orders, Qwest outside field technicians will contact the Resale/UNE-P Provider by telephone and confirm that the Qwest work has been completed and that dial tone has been confirmed up to the Network interface. Qwest requests that the CCON/CBR be a staffed telephone number or have call message capability to allow for this completion information to be transferred efficiently.


Status History

01/07/03 - Opened CR PC100401-1XMN, Cross Over CR SCR100401-1X was closed

01/15/03 - January CMP Meeting - This CR was discussed, CR is in Evaluation status. Meeting minutes will be posted to this CR's Project Meetings section.

02/10/03 - Issued Qwest draft response to Bonnie Johnson at Eschelon

02/12/03 - Draft Response posted to the web site

02/19/03 - February CMP Meeting - Qwest presented draft response. Meeting minutes will be posted to this CR's Project Meetings section.

03/12/03 - Issued Qwest revised draft response to Bonnie Johnson at Eschelon

03/19/03 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/28/03 - Qwest issued PROS.03.28.03.F.01045.Port_In_Within Port In V1.0 and Port Within V1.0 Wholesale Product Catalog new documentation

04/16/03 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/21/03 - May CMP Meeting - Meeting minutes will be posted to this cR's Project Meetings section.

06/18/03 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

07/16/03 July CMP Meeting Joan Wells with Qwest said that documentation became effective on 5/13/03 and Qwest has received a couple of requests. Bonnie Johnson with Eschelon said the process is working well and would like to close this CR. This CR will move to Completed status.

06/18/03 June CMP Meeting Joan Wells with Qwest said that documentation became effective on 5/13/03 and proposed that the CR be moved to Completed status. Bonnie Johnson with Eschelon said they would like to leave the CR open for one more month to allow time to train Eschelon employees and to make sure that the process is working properly. This CR will remain in CLEC Test.

05/21/03 May CMP Meeting Joan Wells with Qwest said that on 5/13/03 PROS.03.28.03.F.01045.PortInWithin Port In V1.0 and Port Within V1.0 Wholesale Product Catalog new documentation became effective. There were no questions and this CR was moved to CLEC Test.

- 04/16/03 April CMP Meeting Joan Wells with Qwest said that documentation has been provided on the document review website and the comment cycle has been completed. Qwest will respond to comments by 4/28/03 and the effective date is 5/13/03. This CR will remain in Development status.

- 03/19/03 March CMP Meeting Joan Wells with Qwest reviewed the revised draft response. Bonnie Johnson with Eschelon asked if on 4/1/03 documentation will be available for review or is 4/1/03 the implementation date. Joan Wells answered that the 4/1/03 date is the date Qwest is targeting documentation to be available for review. This CR remained in Development status.

- 02/19/03 February CMP Meeting Joan Wells with Qwest reviewed the draft response. Bonnie Johnson with Eschelon asked if it would be possible for the tech to call when on the way to the location rather than calling when the work is completed. Joan clarified that Eschelon would like Qwest to call on the way to the location instead of calling when the work is completed and Bonnie agreed. Joan said Qwest will research the tech calling when on the way to the location and provide an updated response. The CR status will remain in Evaluation.

2/13/03 From: Linda Sanchez-Steinke To:"Johnson, Bonnie J." cc

Subject:Re: FW: Draft Response, PC100401-1XMN

Hi Bonnie -

I received your e-mail regarding the CR PC100402-1XMN, "LNP Port In / Port Within Completion Call" and will get back with you when I have more information.

Thank you

Linda Sanchez-Steinke Change Request Project Manager Qwest 303-965-0972

2/11/03 From: Bonnie Johnson To:"'ljsanch@qwest.com'" cc:"Johnson, Bonnie J." , "Isaacs, Kimberly D."

Subject: FW: Draft Response, PC100401-1XMN

Hi Linda, Thank you for the response. Would there be any possibility that the process could be changed to have the tech call when leaving for the customer site? Please let me know.

Thanks,

Bonnie Johnson Sr. Manager ILEC Relations Eschelon Telecom, Inc. Phone: 612 436-6218 Fax: 612 436-6318 Cell:612 743-6724

01/15/03 January CMP Meeting Kit Thomte and Connie Overly with Qwest explained that this CR was opened to address the manual process identified for completion calls on LNP Port In/Port Within. Qwest will provide status as the process progresses through to implementation and will follow the CMP notification process once ready for deployment. This CR will remain in Evaluation status.


CenturyLink Response

March 3, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the March CMP Meeting

Bonnie Johnson Sr. Manager ILEC Relations Eschelon

SUBJECT: Qwest’s Change Request Response - CR # PC100401-1XMN

This is in response to the Qwest CR opened on behalf of Eschelon, Change Request PC100401-1XMN, requesting that Qwest implement a Port In/Port Within Completion Call process.

Qwest accepts this CR, noting necessary changes: - The CBR must be a local or toll free number. - Per CLEC request, Qwest will place the call notification upon dispatch to the premise, instead of upon work completion.

Qwest will utilize the Remarks field of the LSR. Port In and Port Within activity currently use a manual processes for order issuance. The Resale or UNE-P Provider will use the Manual IND = Y, with an added Remark entry, "Pre-Completion Call requested, CCON Name & CBR".

Qwest requests that the CCON/CBR be a staffed telephone number or have call message capability to allow for this information to be transferred efficiently, thus, limiting the effort to one attempt.

Qwest will update, document and train new internal practices. External CLEC documentation will occur in conjunction with CR’s PC081302-1 and PC081302-1. Updates to Qwest Internal and External Documentation are targeted to be available for review by April 1, 2003.

Sincerely,

Joan Wells Process Specialist Qwest


Open Product/Process CR PC091202-1x Detail

 
Title: Show prorated calculations and charges per USOC on BillMate SOACTVTY file (Work will be delivered via an EXCEL Macro in lieu of a BillMate change, with Eschelon's concurrence) (Cross over from SCR091202 01)
CR Number Current Status
Date
Area Impacted Products Impacted

PC091202-1x Completed
4/15/2009
Centrex, Resale, UBL, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: McDonald, Jud
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently on the BillMate SOACTVTY file, when service order activity takes place, Qwest combines the rates for some or all of the USOCs on a given service order before calculating the prorated charge. This makes it difficult to validate each charge. Eschelon asks Qwest to show the prorated calculations and charges for each USOC separately on the BillMate SOACTVTY file. This affects the states of AZ, CO, OR, UT, and WA for Resale & UNE-P. For Unbundled Loop it affects the states of OR & WA.

Expected Deliverable:

The BillMate SOACTVTY files will show the prorated amount for each USOC separately.


Status History

09/12/02: CR submitted

09/12/02: CR acknowledged

09/12/02: Kathy Stichter/Eschelon provided Clarification Meeting availability

09/17/02: Clarification Meeting scheduled for September 30, 2003

09/30/02: Clarification Meeting held. See Project Meetings Section for Meeting Minutes.

10/07/02: Status changed to Evaluation

10/17/02: Discussed at October Systems CMP Monthly Meeting

10/31/02: Status changed to Development

01/16/03: Discussed at January Systems CMP Monthly Meeting

01/17/03: Provided the Excel Macro and assicated user guide to Eschelon per their email request.

01/20/03: Crossed over this CR from Systems to Product Process

02/10/03: Sent email to Kathy Stitcher Eschelon offering assistance/checking status on use of Macro Excel file

02/19/03: February CMP meeting minutes will be posted to the Project Meeting section of the database.

02/27/03: Training Notification TRNG.02.27.03.F.02211.BillMateJob Aid distributed

03/19/03: March CMP Meeting Minutes posted to the database

4/16/03 - April CMP Meeting minutes will be posted to the database


Project Meetings

April 16, 2003 - CMP Meeting Kathy Stitcher advised it is okay to close this item.

March 19, 2003 - CMP Meeting Cindy Macy Qwest reported this was implemented with a Training Notification on 02/27/03. Bonnie Johnson advised Kathy Stitcher is on vacation this week and she did not authorize anything to be closed. We will leave this open till next month.

Feb 19, 2003 - CMP Meeting Jud McDonald–Qwest advised the macro was originally delivered January 17. Cindy Macy–Qwest followed up with Kathy Stitcher–Eschelon to find out if the macro met their needs. Eschelon reported one item on the macro wasn’t totaling correctly. The macro was reviewed and one bug was found and has been fixed. Kathy reported the macro works well. Qwest will deliver Phase 2 (the macro to the web site) with a Training Notification by February 28, 2003.

January 16, 2003 Systems CMP Meeting Discussion: Peggy Esquibel-Reed/Qwest stated that this effort will be implemented in 2 phases. Peggy stated that the EXCEL Macro is currently in development and that the macro will be made available to all CLECs, per request. - Phase 1: EXCEL Macro is targeted for 1/17/03 implementation. It is an interim process to request the EXCEL Macro via an emailed request to zimmer@qwest.com. - Phase 2: The long term solution and has a targeted implementation date of February 28, 2003. The EXCEL Macro will then become available via the web; details are currently being defined. A job aid/user guide will also be made available. Notification process will be followed. Peggy Esquibel-Reed stated that in lieu of no systems work for this request, this CMP CR will be crossed over to Product and Process. Kathy Stichter/Eschelon asked for the email address to send her request. Peggy Esquibel-Reed/Qwest stated the email address is azimmer@qwest.com

October 31, 2002 Email sent to Kathy Stichter/Eschelon: Thanks for the prompt reply. I have forwarded your decision on to IT. The reason option #1 was determined to be a very large effort is because this systematic change would need to be made for all CLECs and even though Eschelon is only asking about 5 states, the change would be required in all 14 Qwest states; so as to keep our processing consistent across all CRIS billing regions. Peggy Esquibel-Reed Qwest CRPM -- Systems

October 30, 2002 Email from Kathy Stichter/Eschelon: Peggy, While I can understand why Western (Oregon and Washington) could be a large effort to change because it encompasses resale, unbundled loop and UNE-P I can not understand why Central (Arizona, Colorado and Utah) would be a large effort because only our resale and UNE-P bills show the fraction lumped for more than one USOC. The unbundled loop, as far as I can tell, does not lump the USOCs together to determine the fractional charge. We will try option 2. Thanks Kathy Stichter Senior Invoice Validation Analyst Eschelon Telecom, Inc 612-436-6022 klstichter@eschelon.com

October 29, 2002 Solution Options Meeting - Attendees: Kathy Stichter/Eschelon, Peggy Esquibel-Reed/Qwest, Sue Kriebel/Qwest, Jud McDonald/Qwest, Doug Warren/Qwest, Alan Zimmerman/Qwest Peggy Esquibel-Reed/Qwest recapped the 2 options in the 10/25/02 Draft Qwest Response. Option 1) Qwest to provide a new column on the BillMate SOACTVTY file to provide prorated amount for each separate USOC. This option would require an estimated Level of Effort of Extra Large. Option 2) Qwest to provide a means, most likely an EXCEL Spreadsheet, that will perform the calculation function. This spreadsheet will be provided to a CLEC upon request. Requests for this spreadsheet can be made via email to azimmer@qwest.com. The estimated Level of Effort for Option 2 is 24 hours. Alan Zimmerman/Qwest stated that option 2 would be an EXCEL Macro that could be either in EXCEL or Access. Kathy Stichter/Eschelon stated that she did send the options to Bill Markert (Eschelon) and has not heard back from him. Kathy does not want to make a final decision withought his input. Kathy stated that the initial thought could be for option 1 but needs to discuss with Bill (Markert) before a decision is made. Kathy asked if for option 2, would it need to be requested each month? Alan Zimmerman/Qwest responded that no, a CLEC would only need to request it once and would get it every month. It will take about 30-seconds to run. Alan Zimmerman/Qwest stated that option 1 would be an extra large effort due to the rounding differences issue. Qwest would need to change how OCCs are calculated and is a huge effort for a penny difference due to rounding problem. Kathy Stichter/Eschelon asked if the macro would also give these penny differences each month. Alan Zimmerman/Qwest stated that the amounts would be given with 6 or 7 decimal places and the CLEC could use their rounding process and round up or down. Peggy Esquibel-Reed/Qwest stated to please keep in mind that option 2 could be delivered a lot sooner than option 1 due to the difference in the level of efforts. Kathy Stichter/Eschelon stated that she will discuss with Bill (Markert) and will send Peggy Esquibel-Reed/Qwest an email with their decision.

October 17, 2002 Systems CMP Meeting Discussion: Kathy Stichter/Eschelon presented CR and stated that the CR is Evaluation status. Michael Buck/Qwest stated that the response indicates that Qwest is researching the request. Jeff Thompson/Qwest stated that Qwest is looking at this CR and what it would take. We have had clarification meeting and we will be scheduling a follow up meeting to discuss what we’ve discovered and what options we think we can provide to you.

-- Clarification Meeting September 30, 2002 Attendees: Kathy Stichter/Eschelon, Peggy Esquibel-Reed/Qwest, Carl Sear/Qwest, Doug Warren/Qwest, and Jean Novak/Qwest CR Description of Change was reviewed: Currently on the BillMate SOACTVTY file, when service order activity takes place, Qwest combines the rates for some or all of the USOCs on a given service order before calculating the prorated charge. This makes it difficult to validate each charge. Eschelon asks Qwest to show the prorated calculations and charges for each USOC separately on the BillMate SOACTVTY file. This affects the states of AZ, CO, OR, UT, and WA for Resale & UNE-P. For Unbundled Loop it affects the states of OR & WA. There was no additional comment or information. Products impacted: Centrex, Resale, UBL, UNE-P. CLEC Expectation/ Expected Deliverable: The BillMate SOACTVTY files will show the prorated amount for each USOC separately. Discussion: Carl Sear/Qwest stated that the paper bill shows the same as ASCII, at the line level. If there are multiple TNs, they are combined; WTN is at line level line level is prorated. Jean Novak/Qwest/ stated that this information was provided to Bill Markert (Eschelon) by Carl Sear & Alan Zimmerman at the last CLEC Forum. Carl Sear/Qwest stated that for this request, functionality may need to be changed and that could be quite a bit bigger LOE. Kathy Stichter/Eschelon asked why this works in some states and not in others. Carl Sear/Qwest stated that it could be due to regional differences. Kathy Stichter/Eschelon provided some examples and Carl Sear/Qwest looked at them and provided explanations for each, i.e. 1 circuit only so does show separate information. Carl Sear/Qwest stated that on the ASCII bill, it can be determined which USOCs are associated to each line item. Kathy Stichter/Eschelon stated that she could that but it takes more time. Kathy Stichter/Eschelon provided a MN example, USOCs are separate, not combined. Carl Sear/Qwest stated that he would need to check into how Eastern region functions for UNE accounts. Western & Central functionality differs. Carl will look at regional differences on how fractionalizing is done. Kathy Stichter/Eschelon stated that USOCs are combined in Western and not in Central & Eastern Carl Sear/Qwest stated that in Western are combined for single and multiple lines. Central are separate on single lines and multiple lines by TN. Eastern will be checked into. Kathy Stichter/Eschelon stated would like to know if the functionality can be changed, what will be changed, and if cannot change functionality, why. There were no other questions or comments.


CenturyLink Response

Revised Draft Response January 10, 2003

RE: SCR091202-01 (Show prorated calculations and charges per USOC on BillMate SOACTVTY file (Work will be delivered via an EXCEL Macro in lieu of a BillMate change, with Eschelon's concurrence)

Qwest will deliver the agreed upon EXCEL Macro in two phases; an interim phase and the long term solution phase. The EXCEL Macro is currently in development. The macro will be made available to all CLECs. - Phase 1: EXCEL Macro will be available for use by the CLECs, targeted implementation date is January 17, 2003. This interim process is to request the EXCEL Macro via an emailed request to azimmer@qwest.com. - Phase 2: The long term solution has a targeted implementation date of February 28, 2003. The EXCEL Macro will then become available via the web; details are currently being defined. A job aid/user guide will also be made available. The notification process will be followed.

Sincerely, Qwest

Revised Draft Response

October 25, 2002

RE: SCR091202-01 (Show prorated calculations and charges per USOC on BillMate SOACTVTY file)

Qwest has reviewed the information submitted as part of Change Request SCR091202-01. Based upon research that has been conducted following the Clarification Meeting (held on September 30, 2002), Qwest is providing the following options:

Option 1) Qwest to provide a new column on the BillMate SOACTVTY file to provide prorated amount for each separate USOC. This option would require an estimated Level of Effort of Extra Large.

Option 2) Qwest to provide a means, most likely an EXCEL Spreadsheet, that will perform the calculation function. This spreadsheet will be provided to a CLEC upon request. Requests for this spreadsheet can be made via email to azimmer@qwest.com. The estimated Level of Effort for Option 2 is 24 hours.

This change request is currently in 'Evaluation' status.

Sincerely, Qwest

Draft Response

October 7, 2002

RE: SCR091202-01 (Show prorated calculations and charges per USOC on BillMate SOACTVTY file)

Qwest has reviewed the information submitted as part of Change Request SCR091202-01. Based upon research that has been conducted following the Clarification Meeting (held September 30, 2002) Qwest is still examining the issue. Qwest will continue to research the problem and provide an updated response at the November Systems CMP Meeting.

At the October Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received at the next Monthly Systems CMP Meeting into further evaluation of this Change Request.

Sincerely, Qwest


Open Product/Process CR PC112502-1 Detail

 
Title: CSR process documentation to correct inaccuracies for Qwest CSR’s posted on the Qwest Wholesale web site.
CR Number Current Status
Date
Area Impacted Products Impacted

PC112502-1 Completed
2/19/2003
Pre-ordering, Provisioning, Ordering Qwest CSR related. Could apply to all products where LSR is dependant on accurate Qwest CSR.
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Manning, Monica
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Previously Eschelon requested a process be developed to correct a CSR for a customer prior to the conversion. Qwest completed the CR and issued an MCC on 7/13/01 with two options (see CR 5608163) however, the process was never documented on the Qwest Wholesale web site (or any CLEC facing document). Often Qwest CSR’s have inaccurate information and need to be corrected to minimize adverse impact to the CLEC or customer at the time of conversion. Since the implementation of this process, Eschelon has experienced a significant amount of LSR rejects in error using the process outlined in the closed CR. Because there is no documentation for that process for Eschelon to refer the Qwest CSIE to, Eschelon has the onus to point out the closed CR and details to Qwest on its own process. In addition, Eschelon is aware of this process, however, a new CLEC or a CLEC that does not participate in CMP may not even know this process exists and may still be referring the end user to Qwest Retail to have their records updated. This may leave the customer feeling like the new Local Service Provider they have selected cannot meet their needs. Qwest employees have the benefit of internal Qwest process documentation used for its Wholesale customers. Qwest has an obligation to provide documentation on the Wholesale web site that mirrors the MCC’s that are generated at Qwest so the CLECs are aware of all processes and have a documented process to refer to when escalating issues with Qwest. Consequently, as a result of this process not being documented on the Qwest Wholesale web site, Eschelon sometimes has to rely on its Service Management Team (Tier 3 and above) to resolve the issue. These reject in error issues could be easily resolved at the Tier 1 or even Tier 0 level if the CLEC and Qwest had access to the same documentation in a readily accessible format. The escalation process is time consuming and has a negative impact on CLECs productivity and wastes valuable time and resources for both the CLEC and Qwest.

Expected Deliverable

Document on the Qwest Wholesale web site the existing defined process for correcting an inaccurate CSR prior to conversion (CR 5608163). CLECs have already waited several months for the process. Per the CMP process section 2.4.4 Qwest had an obligation to modify is external as well as its internal documentation and train all appropriate Qwest personnel as to change. If Qwest had done so, Eschelon would not have to train Qwest personnel on the appropriate procedures as it has had to do. Also per section 2.4.4 the documentation and training should have taken place by the implementation date therefore implementation is already past due and should be completed without delay.


Status History

11/25/02 - CR Submitted by Eschelon

11/26/02 - CR acknowledged by P/P CMP Manager

12/03/02 - Scheduled Clarification call with Bonnie Johnson on 12/4/02

12/04/02 - Held Clarification call

12/10/02 - Clarification meeting minutes issued to Eschelon

12/18/02 - December CMP Meeting - Eschelon presented CR to CLEC Community. CR status changed to Presented. Meeting minutes will be posted to this CR's Project Meetings section.

01/08/03 - Issued Qwest draft response to Bonnie Johnson at Eschelon

01/08/03 - Draft Response posted to the web site

01/15/03 - January CMP Meeting - Qwest presented draft response. Meeting minutes will be posted to this CR's Project Meetings section.

01/30/03 - Qwest issued Process Notification PROS.01.30.03.F.00996.OrderingV24, effective immediately

02/19/03 - February CMP Meeting - CR will move to completed status. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

02/19/03 February CMP Meeting Linda Sanchez-Steinke with Qwest stated that Qwest issued Process Notification PROS.01.30.03.F.00996.OrderingV24, effective 1/30/03. Bonnie Johnson with Eschelon said that the change request could be closed. The CR status was changed to Completed.

01/15/03 January CMP Meeting Michelle Thacker with Qwest presented the draft response to this CR and said that CLEC facing documentation changes are already in progress and they are targeted for review January 31, 2003. This CR is in Presented status.

12/18/02 December CMP Meeting Bonnie Johnson with Eschelon presented this CR and explained that CR5608163 was submitted and in response to that CR, Qwest provided two options to correct CSRs prior to customer conversion. Eschelon is asking that the process for updating the CSR be posted on the Qwest Wholesale web site for viewing as soon as possible because the process is not changing, but needs to documented for CLECs. Judy Schultz and Bonnie discussed that this should be a Level 1 change because the existing process is not changing, but is being documented. This CR will move to Presented status.

CLEC Change Request Clarification Meeting

December 4, 2002, 3:00 p.m. (MT) Conference Call 1-877-554-8688 PIN 1930099 # PC112502-1 CSR process documentation to correct inaccuracies for Qwest CSR’s posted on the Qwest Wholesale web site.

Attendees Name/Company: Bonnie Johnson, Eschelon Kim Issacs, Eschelon Monica Manning, Qwest Michelle Thacker, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of the participants on the Conference Call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of change requested in the CR was reviewed. Bonnie said the CR is asking for the 2 processes for CSR corrections, described in CR 5608163, be documented on the Wholesale Web site because Eschelon still gets rejects in error and then have to escalate to service management to resolve.

Confirm Areas & Products Impacted Bonnie & Kim indicated that all products are impacted.

Confirm Right Personnel Involved Qwest confirmed that the right personnel were involved in the conference call.

Identify/Confirm CLEC’s Expectation Eschelon would like Qwest to document, on the wholesale web site, the two options for updating a CSR, 1) indication of manual handling with remarks, and 2) opening an escalation ticket with the Call Center. Eschelon uses both processes and still receives rejects in error that are difficult to resolve. Bonnie said that Eschelon knows up front that the CSR is wrong and supp the LSR for manual handling and have received rejects from the SDC and then are told that the customer should call the business office to update the CSR. Eschelon then has to go to the service management team and provide the closed CR number, explain how the process should work, before the CSR gets updated. Kim and Bonnie said they would like to take out the need to escalate these rejects in error and feel that with the previous CR, documentation on the Qwest web site there should have been provided.

Establish Action Plan (Resolution Time Frame) This CR will be presented by Bonnie for review CLEC Community Review at the December CMP Meeting.


CenturyLink Response

January 3, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at January’s CMP Meeting

Bonnie Johnson Sr. Manager ILEC Relations Eschelon

SUBJECT: Qwest’s Change Request Response - CR # PC112502-1 (CSR process documentation to correct inaccuracies for Qwest CSR’s posted on the Qwest Wholesale web site.)

This is in response to Eschelon’s Change Request PC112502-1, requesting that Qwest provide documentation on the Wholesale Web Site that provides details explaining how a CLEC issues an LSR when the CSR has inaccuracies.

Qwest accepts this CR and will update CLEC facing documentation. Updates to Qwest External Documentation are targeted to be available for review by January 31, 2003.

Sincerely,

Michelle Thacker Process Specialist Qwest


Open Product/Process CR PC093002-06X Detail

 
Title: NPA NXX with corresponding CLLI and Rate Zone documentation somewhere on Qwest Wholesale web site (Cross over CR SCR093002 06X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC093002-06X Denied
11/20/2002
Billing UNE, UNE-P, Loop
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Maynard, Elaine
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently neither the Qwest paper bill nor the BillMate MONSERV (monthly service) file show an associated CLLI code for each UNE-P ANI or UNE Loop ANI. Since Qwest charges deaveraged zone rates it is essential that Eshelon know what zone each ANI is in. Eschelon has to look in the LERG using the NPA and NXX to find the CLLI for each ANI. Then Eschelon needs to look up the associated Rate Zone. This is an extra step and extremely time consumming. Eschelon asks Qwest to provide documentation, in Excel spreadsheet format, on its Wholesale web site which lists each NPA-NXX with its associated CLLI and Rate Zone. This is an alternative to a denied CR, SCR061902-01, which asked for this information on the BillMate MONSERV file.


Status History

09/30/02 - CR Submitted

10/01/02 - CR Acknowledged

10/04/02 - Clarification Meeting Scheduled

10/07/02 - Clarification Meeting Held

10/07/02 - Status changed to clarification

10/07/02 - Cross-over CR (PC093002-06X) Created

10/16/02 - October CMP Meeting - Minutes on this CR to be posted to the Project Meetings section. CR status updated to Presented.

11/13/02 - Issued Qwest draft response dated 11/5/02 to Kathy Stitcher at Eschelon

11/15/02 - Draft Response posted to the web site

11/20/02 - November CMP Meeting - Qwest presented draft response CR. CR status changed to Denied. Meeting minutes will be posted to this CR's Project Meetings section.

12/16/02 - Issued Qwest final response dated 11/5/02 to Kathy Stitcher at Eschelon


Project Meetings

11/20/02 November CMP Meeting Elaine Maynard with Qwest, reviewed the Qwest draft response and gave historical information regarding the Eschelon denied Systems Change Request, SCR061902-01. Elaine said that the IT representative had suggested that it would be possible to provide a downloadable spreadsheet with NPA/NXX CLLI and rate zone information. When this Product and Process CR was investigated, Qwest then determined that providing the NPA/NXX and CLLI in downloadable format would be a breech of the Telcordia contract. Kathy Stitcher with Eschelon asked if the CR was denied. Elaine said it is being denied due to contract and copyright restriction with Telcordia.

-- 10/16/02 October CMP Meeting Michael Buck gave historical information about previous system change request that was denied and said that Qwest had an alternative approach and Eschelon submitted the CR as Product and Process. There was agreement to cross-over the system CR and we will look to close the systems CR. Eschelon presented the CR to the CMP participants and explained that they need associated information to identify correct deaveraging. Qwest had proposed that the web site could have an Excel spreadsheet with the information needed. Dennis Martinez with Qwest asked if the spreadsheet would be static and contain only updates from the LERG. Kathy Stitcher with Eschelon agreed. Qwest understands the requested deliverables and the CR will be updated to Evaluation Status.

10/7/02 Clarification from Kathy Stichter

Kathy Stichter/Eschelon called to confirm that Eschelon did not want the interactive web site. They want the spreadsheet only.

10/7/02 - Clarification Meeting

Introduction of Attendees - Kathy Stichter - Eschelon, Bonnie Johnson, Eschelon, Ric Martin - Qwest, Beth Foster - Qwest, Dennis Martinez - Qwest, Lynn Stecklein - Qwest

Review Requested Change Lynn Stecklein - Qwest reviewed the request. Eschelon is requesting that Qwest provide documentation, in an Excel spreadsheet, on its Wholesale web site which lists each NPA NXX with its associated CLLI and Rate Zone. Currently, Eschelon is using the LERG to get the CLLI information and find it very time consuming.

Confirm Areas & Products Impacted This change request applies to UNE and UNE-P.

Confirm Right Personnel Involved The Product/Process CRPM (Ric Martin) attended the call because this CR will be handled as a crossover to Product/Process.

Identify/Confirm CLECs Expectation Dennis Martinez/Qwest confirmed that Eschelon was looking for Web functionality. Eschelon agreed. Dennis Martinez/Qwest also confirmed that Eschelon wanted the spreadsheet only and did not want interactive functionality. Kathy Stichter/Eschelon said that she would verify and get back to Lynn Stecklein/Qwest. Bonnie Johnson/Eschelon asked if this web site existed. Dennis Martinez/Qwest said that it does not exist today and that he website will most likely be added to the Wholesale web site. Dennis Martinez/Qwest also said that there might be a gap with number portability. Kathy Stichter/Eschelon said that did not appear to be a problem for Eschelon.

Identify any Dependent Systems Change Requests This will be handled as a Product/Process Crossover. This CR is an alternative to a denied CR, SCR061902-01.

Establish Action Plan Lynn Stecklein/Qwest will create the Crossover CR. The Crossover CR (PC093002-06X) will be presented in the October CMP Systems Meeting.


CenturyLink Response

November 5, 2002

Kathy Stitcher ILEC Relations Manager Eschelon

SUBJECT:Qwest’s Change Request Response - CR #PC093002-06X Request for NPA/NXX with corresponding CLLI and Rate Zone documentation on the Qwest Wholesale Web Site

This CR requests that Qwest provide documentation, in Excel spreadsheet format, on its Wholesale web site which lists each NPA-NXX with its associated CLLI and Rate Zone.

Qwest has investigated the creation of downloadable Excel Spreadsheets that would provide by State, all CLLIs within the state, all NPA/NXX combinations valid for each CLLI, and, the Geographic Deaveraging Zone that is applicable.

It is noted that this information is already currently available. The NPA/NXX can be used to perform a look up on the LERG to determine the associated CLLI or the CLLI can be used to perform a look up on the LERG to determine the NPA/NXXs associated with a particular CLLI. The Qwest web site for Geographic Deaveraging (http://www.qwest.com/wholesale/guides/geozone.html) can be used to view or download a spreadsheet that displays the associated CLLI code and zone.

As a result of this investigation, Qwest must respectfully deny this change request due to legal implications. By providing the information, we would breech our contract and copyright agreement with Telcordia. These restrictions prohibit Qwest from providing the information in the format requested or in any format beyond what is currently provided.

Sincerely,

Elaine Maynard Senior Process Analyst Qwest


Open Product/Process CR PC101402-1 Detail

 
Title: BillMate access and training for Qwest billing representatives, billing managers and service managers
CR Number Current Status
Date
Area Impacted Products Impacted

PC101402-1 Completed
10/14/2002
Billing
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Kriebel, Sue
Director:
CR PM: White, Matt

Description Of Change

Currently Eschelon uses BillMate files to validate charges, determine amounts to dispute and to determine amounts to submit for payment to Qwest. Qwest employees do not have access to or training for our BillMate files. The fact that Qwest employees can not see our BillMate files causes confusion between Eschelon and Qwest when trying to reconcile disputes. When Eschelon calls Qwest to question rates in anticipation of a potential dispute, or when there is a question as to the charges on the bill, Qwest continually asks for examples from Eschelon because the representatives do not see what we see. This creates significant work for Eschelon. Also Qwest figures never reconcile to Eschelon figures. Eschelon requests that Qwest provide access and training to its employees that interact with Eschelon.


Status History

10/14/02 - CR submitted

10/15/02 - CR acknowledged

10/21/02 - Clarification Meeting scheduled for 8:30-9:30 AM MT, 10/22/02

10/22/02 - Clarification Meeting held

11/20/02 - CR Presented at CMP Meeting

12/11/02 - Qwest response e-mailed to originator

12/11/02 - Qwest response inserted in the interactive report and posted to the Web site

12/18/02 - Qwest response presented at the CMP Meeting

01/15/03 - CR discussed at CMP Meeting

02/19/03 - CR discussed and Closed at CMP Meeting


Project Meetings

02-19-03 - CMP Meeting

White-Qwest described the CR and asked Eschelon if Qwest could close the CR. Stichter-Eschelon stated that, during the January CMP Meeting, she had asked if Service Managers would have access to the Billmate information. White-Qwest stated that he had phoned Stichter-Eschelon a week following the January meeting to discuss this issue. He stated that Qwest Service Managers would have access to Billmate information and that Qwest Billing Representatives could add Qwest Service Managers onto calls when CLECs were disputing bills. Masztaler-Qwest stated that Billing Representatives were the CLECs first contact with billing disputes and they would have access to Billmate. If requested, Qwest’s Service Management teams would partner with the Billing Representatives to resolve billing issues. Kriebel-Qwest agreed with this description. Stichter-Eschelon stated that the CR could be closed.

=====================================================

01-15-03 - CMP Meeting

White-Qwest asked Eschelon if they had had an opportunity to exercise the new process. Stichter-Eschelon asked if Service Managers had access to BillMate. White-Qwest stated that he would check to see if the Service Managers had access to the system and call Stichter off-line. Stichter-Eschelon stated that it was fine with Eschelon if only the Billing Representatives have access to BillMate. CR moved to CLEC Test.

========================================================

12/18/02 - CMP Monthly Product/Process Meeting

Kriebel-Qwest described the CR and presented Qwest’s response. White-Qwest proposed that the CR be placed into development status and the Qwest distribute a Level 1 notification to announce the change. The attendees agreed. The CR was moved into Development status.

========================================================

11/20/02 - CMP Monthly Product/Process Meeting

Stichter-Eschelon presented the CR. She stated that Eschelon uses Bilmate but the Qwest billing representatives do not, and cannot understand Eschelon’s concerns because they cannot look at the same screen Eschelon looks at. Sear-Qwest asked what Stichter meant by her statement in the CR about “blank spaces.” Stichter-Eschelon stated that this referred to columns in Billmate that were not populated. She stated that the billing representatives could not see these blank fields and Eschelon thought these columns ought to be populated. Schultz-Qwest asked if Eschelon had submitted CRs to address the issue of blank columns. Stichter-Eschelon stated that they had two active CRs out on this issue. Pardee-AT&T asked that this request be expanded to include CRIS and CABS/IABS billing. Burson-Qwest stated that this expansion would require a huge effort and asked Pardee-AT&T to clarify her request. Pardee-AT&T stated that she would like to leave the Eschelon CR as it was currently submitted. Johnson-Eschelon stated that she was concerned about Sear-Qwest’s comment that the Qwest representatives would be unable to assist Eschelon if there was missing information on the bill. Sear-Qwest stated that requests for additional information to be included on the bill should be sent through CMP. Schultz-Qwest stated that if there is additional information needed on the bill it should be requested with a systems CR. Stichter-Eschelon asked if she could ask the billing representatives for additional information in another form, like a spreadsheet. Burson-Qwest stated that she could. Stichter-Eschelon stated that the language in the description of change section the referenced blank or missing columns could be removed. The CR status was updated to Presented.

=========================================================

CLEC Change Request Clarification Meeting 8:30 AM (Mountain Time) / Tuesday October 22, 2002

1-877-550-8686 2213337# PC101402-1; BillMate access and training for Qwest billing representatives, billing managers and service managers

Attendees Matt White – CRPM Kathy Stichter – Eschelon Carl Sear – Qwest Mark Gonzales – Qwest Paul Diamond – Qwest

Introduction of Attendees White-Qwest welcomed all attendees and asked Stichter to review the request.

Review Requested (Description of) Change Stichter-Eschelon stated that Eschelon uses BillMate files to validate charges, determine amounts to dispute and to determine amounts to submit for payment to Qwest. She explained that Qwest employees do not have access to or training for our BillMate files and that causes confusion between Eschelon and Qwest when trying to reconcile disputes. She continued that when Eschelon calls Qwest asking to have all columns populated in BillMate, or when Eschelon questions rates in anticipation of a potential dispute, or when there is a question as to the charges on the bill, Qwest always asks for examples from Eschelon because the billing representatives can not see what Eschelon sees. She concluded that this creates significant work for Eschelon as Qwest billing figures never match Eschelon billing figures. Eschelon requests that Qwest provide access and training to its employees that interact with Eschelon.

Confirm Areas and Products Impacted White-Qwest asked meeting attendees if the Qwest Service, Account and Billing representatives were the only Qwest representatives impacted. The attendees agreed. Sear-Qwest clarified that there was no system involved and that the bill Stichter was referring to was a file sent to Eschelon.

Confirm Right Personnel Involved White-Qwest asked meeting attendees if the appropriate Qwest personnel were involved. Diamond-Qwest stated that Qwest may need to involve someone from billing after further review of the request and its impacts. Diamond-Qwest asked whom Stichter was dealing with within Qwest. Stichter-Eschelon stated that Eschelon dealt primarily with Terry Clooke, Vicky Keller and Scott Martin in regards to these issues.

Identify/Confirm CLEC’s Expectation White-Qwest asked Stichter if Eschelon's expectation was that all Qwest billing and service representatives who dealt with Eschelon would have access to and be trained on BillMate. Stichter-Eschelon agreed.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they were aware of any other CRs related to this request. The attendees stated that there were none.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Eschelon to present the CR at the November Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

December 6, 2002

RESPONSE For Review by CLEC Community and Discussion at the December 18, 2002, CMP Product/Process Meeting

Bonnie Johnson Eschelon Communications

SUBJECT: Qwest’s Change Request Response - CR #PC101402-1

This is a preliminary response regarding Eschelon CR PC101402-1.

Qwest will arrange for training and access to BillMate ASCII bill files by the Qwest Billing Centers upon request of individual CLEC’s, for the purpose of reconciling bills and disputes. CLEC’s can contact Carl Sear, 303-965-4465, to make the request, with an expected implementation time frame of 60-90 days.

If the volume of requests becomes such that technical restraints become an issue, Qwest will open a change request through CMP.

Qwest recommends this CR be updated to Development status.

Sincerely,

Carl Sear Process Specialist Qwest


Open Product/Process CR PC032801-5 Detail

 
Title: Legacy CR Re institute notification structure to allow CLECs to receive mail out notices by classification
CR Number Current Status
Date
Area Impacted Products Impacted

PC032801-5 Completed
4/18/2001
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

On August 25, 2000, Qwest distributed a notice to CLECs in which Qwest stated: "We have had requests from you our customers asking that Qwest have the ability to separate our notifications, and send those notifications to specific persons at your company. We are pleased to announce that we are now ready to implement such a notification structure" (copy of notice attached). At that time, Eschelon did not need to take advantage of the notification structure. Since then, the number of notices have increased, and it is inefficient for both Eschelon and Qwest to continue to send the notices without separating them. Notices do not reach the correct parties and, as a result, both companies spend time dealing with inquiries about products and requests for notices that could have been avoided if the notices reached the appropriate parties. Therefore, Eschelon asked to take advantage of the notification structure, which has only been in place since August. Qwest’s Senior Service Manager indicated that there is no longer a way to separate these emails by category. Please re-institute the notification structure to allow CLECs to receive mail-out notices by classification. If the emails are more targeted, they are more likely to achieve Qwest’s objective in sending them.


Status History

3/26/01 - CR Received from Karen Clauson of Eschelon

3/28/01 - CR Logged and status changed to New - To be Industry Evaluated

3/28/01 - Updated CR sent to Karen Clauson, Lynne Powers and Jessica Johnson of Eschelon.

4/06/01 - Status changed to Reviewed - Under Consideration

4/06/01 - Updated CR sent to Lynne Powers, Jessica Johnson, Karen Clauson and Janet Houston

4/18/01 - Status changed to Complete as per April CICMP Industry Forum

4/23/01 - Updated CR sent to Lynne Powers, Jessica Johnson, Karen Clauson and Janet Houston

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR PC070202-1X Detail

 
Title: Time & Material Repair Charges invoice process. (Crossover CR SCR070202 01X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC070202-1X Completed
9/18/2002
Maintenance/Repair Centrex, Unbundled Loop, UNE Loop, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Suellentrop, Craig
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest leaves a "Time and Materials Invoice" with its retail customers during a repair visit when the trouble was not found in the Qwest network. Qwest does not supply anything to CLECs. This "Invoice" would assist Eschelon in reconcilling its bill. Eschelon asks Qwest to develop, document and train an adhered to process to supply CLECs with this same "Invoice" or something similar, with the same detail, that will state the charges that Qwest plans to bill at the time of the repair visit. The "Invoice" should contain the Qwest repair ticket number, the number or circuit ID which was reported in trouble, the customer's name and address, the Qwest technicians name and telephone number, the date, the USOCs that Qwest will bill, the quantity of each USOC, the cost of each USOC, the total cost and the reason for the charge.

Expected Deliverable

A process to supply CLECs with an "Invoice" of repair charges at the time of the repair visit.


Status History

07/02/02 - CR Submitted by Eschelon

07/02/02 - CR acknowledged by P/P CMP Manager

07/03/02 - CR posted to Web

07/09/02 - Eschelon contacted to set up clarification call for 07/10/02 at 2:00 PM MDT

07/10/02 - Clarification call held

07/12/02 - Clarification call meeting minutes sent to Eschelon

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Clarification.

08/14/02 - Issued Qwest draft response to Kathy Stichter with Eschhelon

08/19/02 - Issued Mailout Notification to CLECs confirming the Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled for 8/27/02, 2:00 pm MT. Notification CMPR.08.19.02.F.01317.CMP_CR_Mtg.

08/21/02 - CMP Meeting - Qwest presented its draft response dated 8/13/02. This CR will move to Evaluation status and will be discussed at the Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled for 8/27/02, 2:00 pm MT.

8/27/02 - CR included in the Synergy Meeting for Multiple Trouble Tickets & Billing CRs. See Meeting Notes in Attach O, Sept Systems CMP Package.

08/28/02- Crossover CR issued SCR070202-1X

09/18/02 - September CMP Meeting - CR will move to Completed. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/18/02 September CMP Meeting This CR has been moved to a cross over SCR070202-01X. Last Thursday a clarification call was held LOE is being investigated. CRPC070202-1 will be moved to “Completed” status.

08/21/02 - August CMP Meeting Minutes: Qwest reviewed its draft response and advised that this CR would be reviewed in conjunction with other CRs related to trouble tickets, repair charges, etc. scheduled for August 27, 2002. The CLEC participants agreed to have this CR reviewed at that meeting. Eschelon stated that the systems CR timeframe may be too long for Eschelon and would like to see the data that Qwest provides to its retail end users because the retail invoice provides quite a bit of information such as; Name of technician and date. Qwest said that we don’t want to mail an invoice and that the system report may capture data Eschelon would like to receive. Eschelon agreed we don’t want to mail the invoice. This CR was moved to evaluation status.

07/17/02 - July CMP Meeting Minutes: Eschelon presented their Change Request. CR status is clarification

Alignment/Clarification Meeting Conference Call Time/Date: 2:00 p.m. (MDT) / Wednesday, July 10, 2002 Place:TEL: 877.521.8688 Conference Call-In No.: CODE: 7901848 CR No.:CLEC Change Request PC070202-1"Time & Material Repair Charges invoice process"

Kathy Stichter, Eschelon, ILEC Relations Manager Craig Suellentrop, Qwest, 271 Network Technical Regulatory Alice Matthews, Qwest, Process Specialist Michael Keegan, Qwest, CMP Manager

Introduction of Attendees Attendees introduced.

Review Requested (Description of) Change Description: Currently Qwest leaves a "Time and Materials Invoice" with its retail customers during a repair visit when the trouble was not found in the Qwest network. Qwest does not supply anything to CLECs. This "Invoice" would assist Eschelon in reconcilling its bill. Eschelon asks Qwest to develop, document and train an adhered to process to supply CLECs with this same "Invoice" or something similar, with the same detail, that will state the charges that Qwest plans to bill at the time of the repair visit. The "Invoice" should contain the Qwest repair ticket number, the number or circuit ID which was reported in trouble, the customer's name and address, the Qwest technicians name and telephone number, the date, the USOCs that Qwest will bill, the quantity of each USOC, the cost of each USOC, the total cost and the reason for the charge.

Discussion: Eschelon is requesting that the same type of time & material invoice that is generated by Qwest technicians for Qwest retail customers be generated for the CLECs prior to billing and mailed to the CLEC for review and signature.

Qwest indicated that they understood the scope of this CR. Craig Suellentrop will coordinate the production of the Qwest response. N/A

Confirm Areas & Products Impacted Areas Impacted: Maintenance/Repair Products Impacted: Centrex, Unbundled Loop, UNE Loop, UNE-P, Resale N/A

Confirm Right Personnel Qwest confirmed the correct personnel were on the call.

Identify/Confirm CLEC’s Expectation A process to supply CLECs with an "Invoice" of repair charges at the time of the repair visit.

Identify any Dependent Systems Change Requests None

Establish Action Plan (Resolution Time Frame) Eschelon can present this Change Request to the CLEC community at the July Product/Process CMP meeting scheduled for July 17 Qwest will issue draft response to this Change Request by Aug 14 (one week prior to the Aug 21 CMP meeting). Qwest will discuss the draft response at the Aug 21 CMP meeting.


CenturyLink Response

See Crossover SCR070202-1X

August 13, 2002

DRAFT RESPONSE For Review by CLEC Community and Discussion at August’s CMP Meeting

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR PC070202-1 “Time and Material Repair invoice process.”

This CR states that “Qwest leaves a ‘Time and Materials Invoice’ with its retail customers during a repair visit when the trouble was not found in the Qwest network.” The CR requests that Qwest “supply CLECs with this same ‘invoice’ or something similar, with the same detail that will state the charges that Qwest plans to bill at the time of the repair visit.”

Qwest does leave a Time and Materials Invoice with retail customers when a repair dispatch will result in a charge. This invoice is informational in nature. The technician that is dispatched leaves it at the premises. The actual bill (for both wholesale and retail customers) is generated through automated systems and manual processes that occur when a technician closes a trouble ticket. Qwest does not have a billing relationship with CLEC end-users; therefore, Qwest’s process is to not leave invoices with CLEC end-users. CLECs may use electronic maintenance and repair systems (CEMR) to view trouble ticket history as it appears in Qwest’s systems. This information would be valuable in disputing or substantiating repair charges.

Qwest does not have an organization that is responsible for collecting and distributing these invoices. Qwest believes that a systems CR should be opened to generate an automated report that would provide CLECs with data regarding maintenance and repair billing in the timeframe requested. A meeting will be scheduled for late August to discuss CR’s involving maintenance and repair billing, including this CR. Further clarification and direction for this CR will be determined after this meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Susie Bliss, Director-Process Management, Qwest Alice Matthews, Senior Process Analyst, Qwest


Open Product/Process CR PC062702-12 Detail

 
Title: Update Qwest back end systems to show DSL feature information for Repair
CR Number Current Status
Date
Area Impacted Products Impacted

PC062702-12 Withdrawn
10/17/2007
Provisioning Resale - Centrex Plus/Centron UNE-P - Centrex Plus/Centron
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Bliss, Susan
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Currently when a CLEC orders the DSL feature on a Cntrex Plus or Centron line, the order can be processed and installed, however, the critical technical information needed to manage the DSL after installation does not flow to Qwest back end systems. Though the DSL feature appears on the CSR, technical information needed for repair on the DSL feature does not appear in any of Qwest's systems. The result is an inability to get a customers DSL service repaired once installed.

Expected Deliverable:

Capture the critical information needed for DSL feature on a Centrex Plus/Centron line. Develop an interim process for the CLEC's to work with repair until that is done. Identify all existing DSL on CLEC's accounts when the fix is in place and populate the information needed in the systems. Identify any other Qwest product this may apply to.

Expected Deliverable:

Update Qwest systems to capture the critical information needed for DSL feature on a Centrex Plus/Centron line. Develop an interim process for the CLEC's to work with repair until that is done. Identify all existing DSL on CLEC's accounts when the fix is in place and populate the information needed in the systems. Identify any other Qwest product this may apply to.


Status History

06/27/02 CR submitted

07/1/02 - CR acknowledged

07/2/02 - Clarification Meeting scheduled

07/10/02 - Clarification Meeting held

07/10/02 - Status changed to clarification

07/17/02 - July CMP Meeting: CR status changed to "Presented". Meeting minutes posted to this CR's Project Meetings section.

08/14/02 - Sent Draft Response to Eschelon

08/21/02 - August CMP Meeting: CR status changed to "Development" Meeting minutes will be posted to this CR's Project Meeting section and the CMP Web site.

09/18/02 - September CMP Meeting: CR status will remain in "Development" Meeting minutes will be posted to this CR's Project Meeting section and the CMP Web site.

10/16/02 -October CMP Meeting: This CR will remain in "Development" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.

11/20/02 - November CMP Meeting: This CR will remain in "Development" Meeting minutes posted to this CR's Project Meeting section and the CMP Web site.

12/12/02- Provided updated status to Eschelon regarding this CR.

12/18/02 - Eschelon agreed that the status of the Cr could change to Deferred. P


Project Meetings

October 17, 2007 October CMP Meeting

Mark Coyne-Qwest stated that Eschelon had been contacted regarding this CR and agreed to withdraw this request. This CR will now drop off the list. Bonnie Johnson-Eschelon nodded in agreement. This CR moves to Withdrawn status.

October 3, 2007 Email Sent to Eschelon: Thanks Bonnie. I will place the CR in Pending Withdrawal status; and do the formal withdrawal at the October CMP Meeting. Looking forward to seeing you.

- October 3, 2007 Email Received From Eschelon: Hi Peggy, Eschelon agrees to withdraw this CR per your request based on the fact that Qwest has made changes that provide Eschelon with this information. Bonnie Johnson Director Carrier Relations

October 3, 2007 Email Sent to Eschelon: Good Morning Bonnie, RE: PC062702-12 Update Qwest Back End Systems to Show DSL Feature Information for Repair This email is in regard to a CMP CR that Eschelon submitted, to Qwest, in June 2002, requesting DSL feature information. Attached to this email is a copy of that Change Request. In the 5+ years since this CR was submitted, there have been some changes. The Qwest DSL product was grandparented via PC110205-2 and as of January 28, 2006, Qwest offers Qwest DSL (transport only - no ISP) as a non-common carrier service via a commercial agreement only. Because Qwest DSL is no longer a product that can utilize the CMP Process, will Eschelon agree to withdraw PC062702-12? Thank you, in advance, for your prompt reply. Peggy Esquibel-Reed Qwest Wholesale CMP

12/18/02 December CMP Meeting Qwest Susie Bliss reported that the short-term process is working. The order volume does not justify mechanizing another solution. CLEC Community and Eschelon (Johnson) agreed to move this CR to Deferred Inactive status.

11/20/02 November CMP Meeting

Qwest (S Wells) indicated that the interim process was still functioning. Qwest has a request out to determine the magnitude of change that might be required. That information should be available soon. Qwest (S Wells) indicated that they were expecting some information back from Eschelon. Eschelon indicated that they had responded. Qwest clarified that they were still waiting for concurrence on the list of existing Centrex with DSL accounts. Eschelon indicated that they were having someone look over the list, and would be sending concurrence or additions as soon as possible. This CR will remain in Development status.

10/16/02 October CMP Meeting

Qwest (Wells) provided status on the four components of the CR. Only one component remains open. A response is due in mid October outlining a proposed mechanical solution. The implementation plan will be developed for early November. This CR remains in Development status.

09/18/02 September CMP Meeting Qwest (Bliss) this CR has three components:

1. The interim process: The interim process seems to be working well from a Qwest perspective. A handful of orders came in and have been processed using the interim solution. Eschelon (Bonnie) is aware of the interim process but hasn’t received any feedback from her personnel. Bonnie will use the orders provided by Susie to take back internally for feedback. The interim process is applicable to all CLECs submitting orders that fit the criteria.

2. Long term system solution: Exploration of a mechanized solution is ongoing.

3. Embedded base: This addresses the existing customers, the repair centers need to have the information available, this is not completed but the list of customers will be available soon.

Participants agreed that this CR will remain in "Development" status

08/21/02 - Auguast CMP Meeting Minutes Qwest (Bliss) indicated that the CR was still open. Qwest and Eschelon are ready to trial a manual process that was established on August 6th. On August 6th a request came in from Eschelon but Qwest was unaware the request was to trial this manual process. Qwest is assessing the feasibility of a mechanized solution. Eschelon is working on a forecast to determine if Qwest should pursue a mechanized solution. Meanwhile, Qwest has received a worksheet that identifies all existing DSL on CLEC's accounts and are working towards ensuring the Repair Center has the needed information. This CR was moved to"Development" status.

07/17/02 - July CMP Meeting Minutes: Eschelon (Johnson) reviewed the CR and indicated that the appropriate information does not show up in the repair systems. This problem is not experienced by Qwest Retail customers because Retail does not use DPA. DPA is not a problem in Western region. Qwest (Bliss) indicated that this was an issue that was being addressed by the DSL Swat Team.

7/10/02 Clarification Meeting

Attendees: Bonnie Johnson - Eschelon, Susie Wells - Qwest, Kit Thomte - Qwest, Cindy Schwartz - Qwest, Paulette Westerfield - Qwest, Dan Busetti - Qwest, Jean Novak - Qwest

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change

Bonnie Johnson - Eschelon reviewed the change request. Currently when a CLEC orders the DSL feature on a Centrex Plus or Centron line, the order can be processed and installed but the critical information does not flow through to repair. The result is an inability to get a customers DSL service repaired once installed.

She also said that this problem only applies to the Eastern and Central Regions only.

Confirm Areas and Products Impacted Bonnie Johnson said that the Products impacted are Resale - Centrex Plus/Centron and UNE-P Centrex Plus/Centron

Confirm Right Personnel Involved Susie Wells will be the SME at this time.

Identify/Confirm CLECs Expectation Bonnie Johnson confirmed that Eschelon would like Qwest to develop an interim process that would capture the critical information needed for the DSL feature on a Centrex Plus or Centron line and provide the information to repair.

Identify any Dependent Change Requests Lynn Stecklein advised Bonnie Johnson that Qwest has determined that this change request will be handled as a Product/Process CR. Bonnie Johnson asked why this would not be considered a system request and Lynn Stecklein said that the CLECs do not have access to the interface/system impacted. The interface impacted is internal to Qwest.

Establish Action Plan (Resolution Time Frame) Lynn Stecklein will create a Product/Process CR. This CR will comply with the CMP Product/Process CR process and is eligible for presentation at the appropriate July Monthly CMP meeting


CenturyLink Response

For Review by CLEC Community and Discussion at December CMP Meeting

December 10, 2002

Bonnie Johnson Senior Manager ILEC Relations Eschelon

SUBJECT: CR PC062702-12 Update Qwest back end systems to show DSL feature information for Repair

When we discussed this during last month’s CMP meeting, there were two outstanding issues. Those issues and their current status is as follows: 1. What was the long term implementation plan? Current status: we received the estimate for the system changes and the benefits do not outweigh the expenses at this time due to the low volume of orders. We recommend moving this to an inactive deferred status and if the volume of orders get in the range of 400 orders, we would reopen the CR at that time. The existing process that we implemented July 29, 2002 does fulfill the requests of this CR and we have not encountered any problems with the new process. 2. We needed concurrence from Eschelon on the list of existing Centrex with DSL accounts. Current status: Qwest has received confirmation from Eschelon that the embedded base of accounts is in agreement between the two companies.

Given the above, Qwest is recommending that we defer this CR pending a change in order volumes and would like to discuss this during the December CMP meeting.

Sincerely,

Susie Bliss Director Process Management Qwest

-- October 3, 2002

Bonnie Johnson Senior Manager ILEC Relations Eschelon

SUBJECT: CR PC062702-12 Update Qwest back end systems to show DSL feature information for Repair

There are four pieces to the CR. They are: Capture the critical information needed for DSL features on a Centrex Plus/Centron line. Develop an interim process for the CLEC's to work with repair until that is done. Identify all existing DSL on CLEC's accounts when the fix is in place and populate the information needed in the systems. Identify any other Qwest products this may apply to.

The CR is still open. The current status is as follows: Open - Qwest is currently investigating potential implementation of a long term mechanized solution. An automated system solution is still in discovery. Qwest has less than 20 occurrences of the service requirement, both from correction to the embedded base and new service activity. We expect to have system recommendations by October 18 and an implementation plan by November 1, 2002.

Closed - Qwest has developed a manual process by which Qwest's repair personnel will have access to the information they need to take repair reports on DSL service provided with Resold/UNE-P Centrex Plus and Resold/UNE-P Centron. After an order completes in the SOP, Qwest's personnel will manually intervene to stop the order processing before the order posts in CRIS. The repair record is automatically created based on the way the order is written following the manual process. The manual process after the fact is only to get the order to post correctly to generate an accurate CSR. We have successfully trialed the manual process on eight orders that have been submitted by Eschelon.

Closed - Qwest has identified all accounts that required updated repair records, and has issued orders to correct those records effective September 27, 2002.

Closed - This situation is unique only to Central and Eastern Region Resold and UNE-P Centrex and Centron.

Sincerely,

Susie Bliss Director Process Management Qwest

August 13, 2002

Bonnie Johnson Senior Manager ILEC Relations Eschelon

SUBJECT: CR PC062702-12 Update Qwest back end systems to show DSL feature information for Repair

There are four pieces to the CR. They are: Capture the critical information needed for DSL features on a Centrex Plus/Centron line. Develop an interim process for the CLEC's to work with repair until that is done. Identify all existing DSL on CLEC's accounts when the fix is in place and populate the information needed in the systems. Identify any other Qwest products this may apply to.

The CR is still open. The current status is as follows: Open - We are pursing a system solution to capture this information. We are looking at a few possible solutions and will report the current status at the next CMP meeting. Open - Qwest has developed a manual process by which Qwest's repair personnel will have access to the information they need to take repair reports on DSL service provided with Resold/UNE-P Centrex Plus and Resold/UNE-P Centron. After an order completes in the SOP, Qwest's personnel will manually intervene to stop the order processing before the order posts in CRIS. At that time, Qwest personnel will add the appropiate repair organization information to the order. Finally the order will be released to continue through its normal processing and posting to CRIS. We will trial the interim process with Eschelon. Open - Qwest is still looking at how we would identify these accounts and ensure the Repair Center has the needed information. Closed - This situation is unique only to Central and Eastern Region Resold and UNE-P Centrex and Centron.

Sincerely,

Susie Bliss Director Process Management Qwest


Open Product/Process CR PC071202-1 Detail

 
Title: Use Qwest design services ticket number in the PON on Service Orders for Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges so that information is shown on the completion report.
CR Number Current Status
Date
Area Impacted Products Impacted

PC071202-1 Withdrawn
9/18/2002
Billing / Maintenance Repair Unbundled Loop
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Matthews, Alice
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently Qwest issues orders to bill Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges for design services trouble tickets when the trouble was not found in the Qwest network. The completion report sent to Eschelon includes a PON TIC and then information. Sometimes that information is a billing telephone number (BTN) and sometimes the information is the Qwest ticket number. During the reconciliation process Eschelon has found that when Qwest uses the Qwest ticket number in the PON it is easier to find the original Eschelon ticket for reconciliation purposes. Therefor Eschelon requests that Qwest implement a process to use the Qwest repair ticket number in the PON so that the PON would be TIC + the Qwest repair ticket number.

Expected Deliverable

A process to ensure that the PON on service orders for Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges include the Qwest repair ticket number so that information is shown on the completion report..


Status History

07/12/02 - CR Submitted by Eschelon.

07/12/02 - CR acknowledged by P/P CMP Manager.

07/16/02 - Eschelon contacted and clarification meeting scheduled for 07/16/02 at 10:30 a.m. (MDT)

07/16/02 - Clarification call held with Eschelon

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Clarification.

07/18/02 - Clarification Call meeting minutes were sent to Eschelon

08/19/02 - Issued Mailout Notification to CLECs confirming the Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled for 8/27/02, 2:00 pm MT. Notification CMPR.08.19.02.F.01317.CMP_CR_Mtg.

08/21/02 - CMP Meeting - This CR is being reviewed in Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled ro 8/27/02, 2:00 pm MT. CR will be moved to evaluation status.

8/27/02 - CR included in the Synergy Meeting for Multiple Trouble Tickets & Billing CRs. See Meeting Notes in Attach O, Sept Systems CMP Package.

9/11/02 - Issued Qwest draft response dated 9/11/02 to Kathy Stitcher at Eschelon

09/18/02 - September CMP Meeting - Qwest presented draft response. CR will move to Withdrawn. Meeting minutes will be posted to this CR's Project Meetings section.

09/27/02 - Issued Qwest Revised Response dated 9-24-02 to Kathy Stitcher at Eschelon. CR Withdrawn.


Project Meetings

09/18/02 September CMP Meeting Qwest reviewed the draft response and Eschelon said they don’t need the PON for the completion report if the billing office will give the Qwest trouble ticket number on the spreadsheet. Qwest said the billing office can provide the trouble ticket number on the spreadsheet and will update the response to indicate the Qwest trouble ticket number will be on the spreadsheet until the related systems CRs are completed. Eschelon said they would withdraw the CR and this CR status will be changed to “Withdrawn.”

-

08/21/02 - August CMP Meeting Minutes: Eschelon reviewed their CR requesting that Qwest trouble ticket number be included with their PON because it would provide another piece of information to help Eschelon verify charges. Qwest advised that this CR would be reviewed in conjunction with other CRs related to trouble tickets, repair charges, etc. scheduled for August 27, 2002. The CLEC participants agreed to have this CR reviewed at that meeting and will be changed to evaluation status.

07/17/02 - July CMP Meeting Minutes: Eschelon presented their Change Request. CR status is clarification.

Clarification Call Time/Date: 10:30 a.m. (MDT) / Tuesday, July 16, 2002 Place: Conference Call Conference: TEL: 877.521.8688 Call-In: CODE: 7901848 CR No: PC071202-1 "Use Qwest design services ticket number in the PON on Service Orders for Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges so that information is shown on the completion report."

Attendees: Kathy Stichter, Eschelon, ILEC Relations Manager Alice Matthews, Qwest, Sr Process Analyst - Billing Craig Suellentrop, Qwest, 271 Network Technical Regulatory Bob Mohr, Qwest, Product Manager Michael Keegan, Qwest, CMP Manager

Introduction of Attendees Attendees introduced. Review Requested (Description of) Change Description:

Currently Qwest issues orders to bill Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges for design services trouble tickets when the trouble was not found in the Qwest network. The completion report sent to Eschelon includes a PON TIC and then information. Sometimes that information is a billing telephone number (BTN) and sometimes the information is the Qwest ticket number. During the reconciliation process Eschelon has found that when Qwest uses the Qwest ticket number in the PON it is easier to find the original Eschelon ticket for reconciliation purposes. Therefor Eschelon requests that Qwest implement a process to use the Qwest repair ticket number in the PON so that the PON would be TIC + the Qwest repair ticket number.

Discussion: Qwest asked if the scope of the change request is for the design services side only. Eschelon agreed, and confimed that non design (resale) is excluded.

Confirm Areas & Products Impacted Areas Impacted: Billing and Maintenance/Repair Products Impacted: Unbundled Loop Confirm Right Personnel Qwest confirmed the correct personnel were on the call.

Identify/Confirm CLEC’s Expectation A process to ensure that the PON on service orders for Maintenance of Service Charges, Dispatch Charges and Optional Testing Charges include the Qwest repair ticket number so that information is shown on the completion report.. Identify any Dependent Systems Change Requests None Establish Action Plan (Resolution Time Frame) Eschelon can present this Change Request to the CLEC community at the August Product/Process CMP meeting scheduled for August 21 Qwest will issue draft response to this Change Request by Sep 11 (one week prior to the Sep 18 CMP meeting). Qwest will discuss the draft response at the Sep 18 CMP meeting. Alice Matthews will coordinate the production of the Qwest response.


CenturyLink Response

September 24, 2002

Kathleen Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Revised Response – PC071202-1 “Use Qwest design services ticket number in the PON on Service Orders for Maintenance of Service Charges, Dispatch Charges, and Optional Testing Charges so that information is shown on the completion report.”

This CR requests that Qwest populate the Qwest trouble ticket number as the data in the PON field of service orders issued to generate Designed Services Maintenance of Service, Dispatch and Optional Testing charges. This Change Request was discussed during the CR synergies meeting between Qwest and the CLEC Community on August 27, 2002. During that discussion Eschelon indicated that they issued this Change Request because they are concerned two other CRs: SCR042902-01 and SCR060402-04, may not be implemented or may be delayed. In addition, Eschelon indicated that their solution of choice is for Qwest to provide the CKT ID or Telephone Number, Qwest ticket number, CLEC ticket number and date work was completed on all bill formats (as requested in SCR042902-01 and SCR060402-04).

If implemented, CR PC071202-1, would provide only the Qwest ticket number, which is only one of the data elements Eschelon has specified as critical. With this CR, the Qwest trouble ticket number would appear on the Completion Report in lieu of the account information, e.g., AN, MAN or SBN, that appears today. The implementation of this CR would result in providing different information not more information.

Implementation of this Change Request would require scripting changes to populate the PON field with the Qwest ticket number and, due to PON field character limitations, Qwest would no longer be able to populate the billing account information. Because this CR would change a process changed at the CLEC’s request in February 2002, Qwest asked for feedback from the CMP Community at the September 18th Product and Process CMP Meeting.

At the CMP Meeting, Eschelon agreed to withdraw this CR, and, the Qwest Billing Center will provide the Qwest trouble ticket number on the CLEC spreadsheet until SCR042902-01 and SCR06402-04 are completed.

Sincerely,

Alice Matthews Senior Process Analyst, Qwest

Cc: Sue Burson, Director Process Management, Qwest Alan Zimmerman, Manager Process Management, Qwest Craig Suellentrop, Staff Advocate Policy and Law, Qwest

September 11, 2002

Kathleen Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response – PC071202-1 “Use Qwest design services ticket number in the PON on Service Orders for Maintenance of Service Charges, Dispatch Charges, and Optional Testing Charges so that information is shown on the completion report.”

This CR requests that Qwest populate the Qwest trouble ticket number as the data in the PON field of service orders issued to generate Designed Services Maintenance of Service, Dispatch and Optional Testing charges. This Change Request was discussed during the CR synergies meeting between Qwest and the CLEC Community on August 27, 2002. During that discussion Eschelon indicated that they issued this Change Request because they are concerned two other CRs: SCR042902-01 and SCR060402-04, may not be implemented or may be delayed. In addition, Eschelon indicated that their solution of choice is for Qwest to provide the CKT ID or Telephone Number, Qwest trouble ticket number, CLEC trouble ticket number and date work was completed on all bill formats (as requested in SCR042902-01 and SCR060402-04).

If implemented, CR PC071202-1, would provide only the Qwest trouble ticket number, which is only one of the data elements Eschelon has specified as critical. With this CR, the Qwest trouble ticket number would appear on the Completion Report in lieu of the account information, e.g., AN, MAN or SBN, that appears today. The implementation of this CR would result in providing different information not more information.

Implementation of this Change Request would require scripting changes to populate the PON field with the Qwest trouble ticket number and, due to PON field character limitations, Qwest would no longer be able to populate the billing account information. Because this CR seeks to change a process changed at the CLECs’ request in February, 2002, Qwest would like to solicit feedback from the CMP Community at the September 18th Product & Process Monthly CMP Meeting before proceeding with this request.

Sincerely,

Alice Matthews Senior Process Analyst, Qwest

Cc: Sue Burson, Director Process Management, Qwest Alan Zimmerman, Manager Process Management, Qwest Craig Suellentrop, Staff Advocate Policy and Law, Qwest


Open Product/Process CR PC100102-1CM Detail

 
Title: Change format on the Web change notification form to a Red Line format
CR Number Current Status
Date
Area Impacted Products Impacted

PC100102-1CM Completed
4/15/2009
Notification Process Notification Process
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Blackmun, Jarby
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently the web change notification form is sent in a format where the changes are highlighted with 'add' and 'delete' to identify changes being made to the document. It is very difficult to identify what is changing in the document using the current format. I have had repeated feedback from several Eschelon employees who are required to review these documents that they are not certain they have fully captured the changes taking place. Since most people are familiar with the Red Line format for understanding changes, Qwest should change to a Red Line format. The CLEC runs the risk of interpreting a change incorrectly that may impact the ability to do business or negatively impact a customer.

Expected Deliverable:

Qwest will change to a Red Line format for Web Change Notification Forms.


Status History

09/30/02 - CR Submitted by Eschelon

10/01/02 - CR Acknowledged by CRPM P/P Manager

10/03/02 - CR Posted to Web

10/03/02 - Customer contacted and scheduled clarification call for 10/09/02 9:30 am mdt

10/09/02 - Clarification call completed with Eschelon

10/15/02 - Provided Clarification Meeting notes to Eschelon and posted to database

10/16/02 - October CMP Meeting - Collective CLEC clarification occurred at the October CMP Meeting. Minutes will be posted to the Project Meetings section.

10/22/02 - Proposed 3 meeting options via the Notification mailout process.

10/24/02 - Posted October 31 as meeting choice via Notification mailout process. Completed mailout notification with agenda, and attachments (documents to review)

10/31/02 - Held October 31 meeting to further discuss CR. Agreement was reached to vote on CR at November 20 P/P CMP Meeting. Notification to vote will be sent out November 1, 2002. Qwest will determine if other options are available. If so, Qwest and notify CMP Community that discussion of options will take place at the November CMP Meeting.

11/01/02 - Vote Notification CMPR..11.01.02.F.01352.CMP_Mtg_Vote distributed via mailout process. In addition, if Qwest is able to develop an alternate option in regard to this topic, this will be identified via a notification by November 12, 2002. This notification will briefly discuss the option and call for discussion at the November 20, 2002 Product Process meeting.

11/12/02 - Notification distributed advising of Qwest's effort (trial Nov.11-27) to determine the feasibility of providing redline documents as a means to assess changes to documentation, and delivery of redlined documents will require a change in the Level 1 notification delivery process. Qwest suggests to delay the vote until the results of the trail are available (early December).

11/20/02 - November CMP Meeting - discussed the trial that Qwest is conducting to determine feasibility of providing redlined documents and explained the potential impact to the Web Notification form for Level 1 changes. Proposed and reached agreement to delay the vote until after the trial.

11/26/02 - Notification sent out offering 3 meeting options to review resutls of Red Lined Trial

12/03/02 - Notification sent out advising meeting scheduled for December 10, 2002 from 9:00 - 10:30 am mdt

12/04/02 - Notification sent out providing attachments to use during meeting; results of trial and changes to the CMP document.

12/10/02 - Held CLEC Meeting and shared Qwest's proposal for changes to the CMP process and described the new method to access Level 1 changes. Qwest agreed they can change to Red Line updates for Level 1-4 CRs. CLECs and Qwest agreed we would vote on the proposal at the December CMP Meeting. Qwest agreed to distribute a Vote Notification by 12/11/02.

12/11/02 - Vote Notification distributed via mailout process. VOTE will take place during 12-18 Product Process CMP Meeting.

12/18/02 - December P/P CMP Meeting notes will be posted to the Project Meeting Section. Vote took place and passed with a 'yes' vote. Changed status to Development.

01/02/03 - Level 1 Notification sent out advising this process is effective January 6, 2003. Will propose to change this CR to CLEC Test status at the January meeting.


Project Meetings

12/18/02 - December CMP Monthly Meeting Minutes Qwest-Blackmun explained we are able to update PCATs using Red Lined instead of Green Highlight for Level 1-4 changes. In addition, for Level 1 changes the Web Notification form would not be used any longer. Instead, the PCAT would be updated and posted to the Archive Document review site. World Com-Balvin asked if the History Log would still be referenced and the changed identified on that. Qwest advised yes. The vote process was then explained and conducted. The change passed by unanimous vote 7 ‘Yes’ and 0 ‘No’. White-Qwest proposed the change to the CMP Document be made in combination with the change from CR PC102502-1CM in a January 6, 2003, Level 1 notification. The attendees agreed.

12/10/02 - CLEC / Qwest Meeting to review trial results Held CLEC Meeting and shared Qwest's proposal for changes to the CMP process and described the new method to access Level 1 changes. Qwest agreed we can change to Red Line updates for Level 1-4 CRs. CLECs and Qwest agreed we would vote on the proposal at the December CMP Meeting. Qwest agreed to distribute a Vote Notification by 12/11/02.

11/20/02 - November CMP Monthly Meeting Minutes Qwest advised a trial is underway until November 27 to determine the impact to changing to Red Line format. Due to the trial Qwest is requesting the vote be delayed until after the trial is completed. Qwest explained if we are able to change to Red Lind format a change to the Web Notification process would also need to occur as the Microsoft Word program does not accommodate 'cut and paste' of Red Lined changes from one document to another. If the result of the trial allows Qwest to change to Red Lined format we will also present the suggested change to the Web Notification process. It is anticipated the change for Level 1 Web Notifications would be to post the description of the change and the PCAT document to the web site minus a comment cycle, instead of cutting and pasting the updated sections to the Web Notification form. Eschelon and other CLECs in attendance agreed to postpone the vote until after the trial. Qwest agreed they would offer 3 options for meetings to review the results of the trial. After the results are reviewed a meeting will be held to vote on this CR.

10/31/02 - CLEC Input Meeting held to discuss this CR. Scope was confirmed that this CR affects Web Notification forms and all Levels of PCATs. Green highlighted and Red lined documents were reviewed and compared. Discussion of concerns from CLECs and Qwest occurred. No feasible options were agreed upon during the meeting. Agreement was reached that Qwest would determine if we have any options to present. In addition, Qwest would issue the Vote Notification so a vote could take place at the November Monthly Product Process CMP meeting, if Qwest is not able to determine other acceptable options.

10/16/02 - October CMP Monthly Meeting Minutes Eschelon clarified the CR and reasons for submitting the CR. Qwest confirmed this CR will follow section 2.1 of the CMP process. Agreement was reached on the input approach. Qwest will propose multiple meeting dates. The agreed upon meeting will be held to gather additional data, understand the scope of the CR to make sure the CLEC community is aware of what will be voted on, and potentially identify new options for document updates. The CMP process identifies a vote would not occur earlier than the November meeting. Eschelon requested an example of both update methods (Green highlight and Red Lined) be shared in the meeting. Notification of meeting time options will be sent out via the Notification process.

CLEC Change Request Clarification Meeting Time/Date: 9:30 p.m. (MDT) / Wednesday 9th October 2002 Conference Call-In No.: 1-877-561-8688 7385723# CR No.: PC100102-1CM Change format of the Web change notification form to a Red Line Format

Attendees: Bonnie Johnson – Eschelon Jarby Blackmun – Qwest Mark Coyne – Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees

1.1 Introduction of the participants on the Conference Call was made and the purpose of the call discussed.

2.0 Review Requested (Description of) Change

2.1 Reviewed the details of the change request and confirmed that Bonnie requested updates to the PCAT be made using Red Line format instead of Green Highlight format. This applies to Level 1- 4 changes. Bonnie sent in a redlined version of the CMP process identifying changes should be made to Level 1, but we clarified she is requesting the change be made to Level 1- 4.

3.0Confirm Areas & Products Impacted It was confirmed that Bonnie is requesting changes to the ‘Notification Process’.

4.0Confirm Right Personnel Involved Jarby Blackmun will be the SME on this CR. Mark Coyne will participate.

5.0Identify/Confirm CLEC’s Expectation Eschelon requests Qwest to change to a Red Line format for Web Change Notification forms (update PCATs using Red Line format, just as Tech Pubs are done)

6.0 Identify any Dependent Systems Change Requests None

7.0Establish Action Plan (Resolution Time Frame) Bonnie will present this CR to the CLEC community at the October 16 CMP P/P Monthly Meeting.


Open Product/Process CR PC021502-1 Detail

 
Title: Collocation: Construction Process (in, near or affecting CLEC collocation space)
CR Number Current Status
Date
Area Impacted Products Impacted

PC021502-1 Completed
5/15/2002
Other: Collocation/construction Colocation
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Burke, Laurel
Director:
CR PM:

Description Of Change

Eschelon requests a written, trained, and adhered to nondiscriminatory process that addresses proper procedures when Qwest and/or its vendors perform construction activities in buildings that house CLEC collocations. Eschelon provides two examples demonstrating that Qwest’s current procedures are inadequate and discriminatory and in need of revision:

January 2002/Qwest’s Minneapolis Orchard Central Office: Qwest's Orchard Central Office is currently under construction for a new addition. That addition includes modification to the existing mechanical system, as well as additional floor space. Eschelon leases space, from Qwest, for a collocation in the Orchard Central Office. During a dispatch, in January 2002, Eschelon's technician discovered dirt, dust and metal shavings on its collocation equipment. Photographs showing the extent of the problem are attached. Qwest would not expose its own equipment to these conditions. Qwest had not notified Eschelon of this construction or the potential impact on Eschelon’s collocation space. When Eschelon discovered the problem, Eschelon immediately contacted Qwest to report the problem, request resolution, and obtain assurances that this serious problem would not be repeated. During later visits to this collocation site, Eschelon discovered excessive temperature levels that could also damage its equipment. Cleaning the equipment required 'powering down' the equipment, resulting in customer outages. Qwest removed all essential cooling to the area and replaced it with a fan, an inadequate solution. Qwest would not find that a fan would be adequate to cool its own equipment. The problem also required one of Eschelon's technicians to be available for the time period while a vendor was completing the clean up. This tied up a technician who should have been doing other work. This incident caused down time for our customers and forced Eschelon to incur unnecessary time and expense and could have caused major damage to our equipment. Eschelon believes that at least two other CLEC collocation spaces were adversely affected by the same construction. Qwest has an obligation to protect the CLEC collocation equipment with at least as much care, as it would use to protect its own equipment. Eschelon asks Qwest for an improved process to ensure that our collocations are protected during construction in any Qwest building that houses one of our collocations.

March 2001/Denver Main Central Office: On March 15, 2001, Eschelon conducted a site survey of its physical collocation located at the Denver Main Central Office. The conditions discovered at the site indicated a deliberate breach in security and potential damage to our equipment. Qwest had not notified Eschelon of this construction or the potential impact on Eschelon’s collocation space. When Eschelon discovered the problem, Eschelon contacted Qwest immediately asking for resolution of the following issues:

1. Eschelon's cage was accessed without Eschelon authorization or knowledge. A Qwest approved contractor removed the pins securing Eschelon's collocation cage to gain access and Qwest security failed to notify Eschelon of the intrusion. Eschelon pays security charges on a monthly basis and expects Qwest to provide and maintain a secure environment. Eschelon told Qwest that this matter is of utmost importance as the integrity of Eschelon's collocation equipment was jeopardized.

2. A 1 inch copper pipe running across the span of Eschelon's cage was installed. The location and height of the pipe severely restricted Eschelon's ability to expand the existing cable ladder racking for future growth. Additionally, the pipe was believed to be a water pipe, which if ruptured, had significant potential for causing damage to personnel and property.

3. There was a significant amount of dust within the cage and on the collocation equipment. This presented an operational issue with Eschelon's hardware and its ability to operate properly. Eschelon asked Qwest to thoroughly clean Eschelon's collocation cage and the surrounding area.

4. There were two additional 1/2 inch copper pipes running across the cage at ceiling height. These pipes also posed a significant problem, as they appeared to be water pipes serving the cooling unit adjacent to Eschelon's cage. The same potential for damage to personnel and property existed.

Both of these examples involved serious problems concerning the integrity of Eschelon's collocation cage. Eschelon had to escalate the issues within Qwest in an attempt to resolve them. An after-the-fact clean up, however, is not a satisfactory remedy. The breaches to security and integrity to the collocation cannot be undone. Eschelon also had to incur unnecessary time and expenses, in addition to its customers experiencing unjustified downtime.

Qwest would not expose its own equipment to such conditions or allow CLECs to treat Qwest’s space and equipment in this same manner. One can only imagine how Qwest would react if a CLEC removed the pins to a Qwest door to get around a lock securing access to the Qwest area of a building. On a much smaller scale, recently, a Vice President of Qwest in charge of Qwest’s network directly contacted Eschelon’s Executive Vice President of Operations and Engineering to allege that Eschelon’s equipment was causing a Qwest fire alarm near Eschelon’s cage to go off. Eschelon was able to show that was not the case. Nothing in Eschelon’s cage had caused the alarm to sound. Eschelon believes that the Qwest fire protection system in that building has had false alarms before, for reasons unrelated to collocation. The mere proximity of a CLEC collocation to a fire protection device that sounded a false alarm was sufficient to draw an immediate call from Qwest’s top management.

In contrast, Eschelon has had difficulty in getting appropriate attention to the very serious issues that have occurred with respect to violations of its collocation space. Eschelon had to expend substantial resources escalating these issues to obtain after-the-fact resolutions. Even after the first situation was resolved, and assurances were received that the problem would not occur again, serious problems occurred again, this time in the Orchard Central Office. In response to its escalation of the most recent situation (Orchard Central Office), Qwest provided Eschelon with a written response that said: “Throughout the life of this construction project, Qwest has insured that all methods of procedures (MOP’s) were followed and that dust protection was appropriate and in place.” Please review the enclosed photographs in light of this statement. Obviously, if following the current procedures at Qwest produces this result, the current procedures are inadequate.

Qwest needs to promptly establish an improved process. Eschelon requests that a solution be developed and implemented quickly to avoid further serious breaches.

The law and interconnection agreements provide support for Eschelon’s request. Examples include:

47 U.S.C. § 551(c)(6): Incumbent local exchange carrier has -- “The duty to provide, on rates, terms, and conditions that are just, reasonable, and nondiscriminatory, for physical collocation of equipment necessary for interconnection or access to unbundled network elements at the premises of the local exchange carrier, except that the carrier may provide for virtual collocation if the local exchange carrier demonstrates to the State commission that physical collocation is not practical for technical reasons or because of space limitations” (emphasis added).

Minnesota Qwest-Eschelon interconnection agreement, Second Amendment: “USW shall provide Collocation in a nondiscriminatory manner on rates, terms and conditions that are just, reasonable and nondiscriminatory.” § 2.1; see also Part A, § 4.


Status History

02/14/02 - CR Submitted by Eschelon.

02/15/02 - CR acknowledged by P/P CMP Manager.

02/19/02 - Contacted Kathy Stichter, Eschelon, to coordinate Clarification Meeting - Tentative date is Tuesday 2/26/02.

02/20/02 - CMP Meeting - Eschelon introduced its CR and routed documentation for review. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

02/22/02 - Received e-mail from Eschelon with additional evaluation of Orchard site on 2/18/02.

02/26/02 - Conducted Clarification Meeting with Eschelon.

02/28/02 - Issued Clarification Meeting Minutes to Eschelon.

03/20/02 - CMP Meeting - Eschelon presented its CR. Qwest advised they are looking at gaps in their existing processes. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would move to Evaluation.

04/10/02 - Issued Qwest's Draft Response dated April 9, 2002 to Eschelon.

04/17/02 - CMP Meeting - Qwest presented its response. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. It was agreed that the CR would be status as CLEC Test.

04/19/02 - Formal response dated April 9, 2002 issued to CLECs. Notification CMPR.04.19.02.F.01258.Final_CR_Responses.

05/15/02 - CMP Meeting - Eschelon advised that the CR could be closed.


Project Meetings

CLEC Change Request Clarification Meeting

February 26, 2002, 12:00 (MT) Conference Call

877-564-8688 PC021502-1, Collocation: Construction Process (in, near or affecting CLEC collocation space)

Attendees: Ric Martin, Qwest Clyde Just, Qwest Laurel Burke, Qwest Chuck Frauenfeld, Qwest Paul Williams, Qwest Deb Heckart, Qwest Steve Sheahan, Qwest Kay Daugaard, Qwest Kathy Stichter, Eschelon Paul Hanser, Eschelon Bonnie Johnson, Eschelon

Introduction of Attendees Introduction of the participants on the Conference Call were made and the purpose of the call discussed Ric advised that there were two issues surrounding the Change Request. The first deals with the issues at the Orchard Central Office and the second deals with the process change requested in the Change Request. Ric advised that it would be best to discuss the first issue in a separate meeting and focus on the process in this meeting. Steve Sheahan would facilitate the meeting with Eschelon personnel with Kathy Stichter. Eschelon agreed with this path forward.

Review Requested (Description of) Change Kathy reviewed the requirements of their CR and their expected deliverable. Bonnie advised that Eschelon was aware that there is a documented process, but the concern is that it is not being followed 100%. Paul Hanser indicated that Eschelon would like to be involved in the planning process and be made aware of the construction activity. They want to know how the equipment is going to be protected and that it is kept cool and clean. Paul indicated that Eschelon would like to be involved in the project planning phase. Paul Williams asked if Eschelon would like to be notified on all construction activity. Paul Hanser indicated that they were more interested in the building construction activity rather than equipment installations. It was confirmed that Eschelon would prefer to be notified when there is facility construction as opposed to equipment installations. Paul clarified that some equipment installations could create a fair amount of dust (i.e. drilling through thick concrete) and they would want to be made aware of this type of installation. Ric confirmed that the process followed for construction activity is Technical Publication 77350. Clyde asked what name would Eschelon want Qwest to contact. Paul Hanser indicated that they would like the name on the emergency list provided to each Central Office, or the 800 number on their Collo cages contacted. This allows the call to go to operations that coordinate Eschelon’s activities. Clyde expressed concern that not all CLECs operate in the same manner. The only consistency is the name on the application. Paul Hanser advised that the person on the application and the associated number may change, but the posted 800 number remains the same. Qwest advised that this could be difficult to get a consistent approach from all CLECs. Ric asked Eschelon if discriminatory meant the same process for all parties involved. Kathy added that all equipment is treated the same for Qwest and CLECs.

Confirm Areas & Products Impacted It was confirmed that the CR addressed Collocation equipment. . Confirm Right Personnel Involved Ric advised that there are several SMEs that will be working on the CR. Laurel Burke will be the Owner identified on Qwest’s reports, but the other SMEs are Howard Cooper, Real Estate, Jerry Jenson, C.O. Staff, and Jeff Bostow, Technical Publications.

Identify/Confirm CLEC’s Expectation Eschelon confirmed that their expectation is their written statement under Expected Deliverable in the Change Request.

Identify any Dependent Systems Change Requests There is no corresponding System CR

Establish Action Plan (Resolution Time Frame) Qwest will facilitate a separate meeting to review the Orchard Construction activity. Ric advised that the CR will have the Community CLEC clarification and Qwest will present potential options at the March 20th CMP meeting.


CenturyLink Response

April 09, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc.

SUBJECT: Qwest Change Request Response - CR PC021502-1 Collocation: Construction Process (in, near or affecting CLEC collocation space)

This letter responds to Change Request PC021502-1 requesting that Qwest develop a written, trained and adhered to nondiscriminatory process that addresses proper procedures when Qwest and/or its vendors perform construction activities in buildings that house CLEC collocations. Additionally, the two (2) examples described in your Change Request will be addressed in Attachment 1 to this letter.

Eschelon suggested that the process include the following:

1. Improved Qwest process for building construction activity in Central Offices that house CLEC collocations.

Qwest’s process for building construction utilizes a project management approach. Due to the nature of individual building construction activity, project design drawings and specifications documents embody the performance expectations associated with each construction project. The very specific nature of such projects and the quantity of detailed information associated with these projects prohibit Qwest from providing a detailed building construction process in this response. However, Qwest provides below a description of activities common across building construction projects.

Qwest Building Construction Project Management

When a project is initiated, Local Design Construction teams, coordinated by Real Estate Project Managers, develop project plans and specifications in conjunction with Registered Professional Consulting Architects/Engineers and selected Qwest General Contractors. Prior to entering into a contract with Qwest (Real Estate), these consultants and contractors must have a demonstrated track record of proficiency while working with electronic equipment environments. Methods used to demonstrate this include checking work references from other clients and reviewing the contractors project portfolio. Local teams may then choose projects small in scope to evaluate the contractor for larger projects such as Central Office building additions.

The Local Design Construction team assembles the project work scope and customizes it according to the specific project at hand. The documentation and scope of the project work utilizes engineering and operational elements from Qwest policy documents, engineering and operational standards, as well as engineering guideline documentation specifically applicable to Central Office projects. Building environment specifications, or operational standards, commonly contain aspects of several Qwest and industry standards. Examples of these standards include:

? Class 100,000 clean room requirements for airborne particulate control (reference Qwest Regional Policy REGN 000-010-019RG); ? Temperature control requirements meeting industry standards (reference Bellcore (Telcordia) Network Equipment Building Systems (NEBS) document NEBS GR-63-CORE, and REGN 000-010-019RG); ? Technical Publication 77350 for equipment isolation and protection; ? National Electrical Code (NEC) specifications; and ? Project specific Methods of Procedure ("MOP").

Real Estate Consultants and Contractors use Qwest policies and standards in project documents and are held accountable for performing and utilizing these policies and standards. Local Design Construction teams are reminded on each project about the consequences of not following and/or failing to perform to these policies and standards, including the potential for contract termination or probation. In fact, during 2001, Qwest terminated contracts with three (3) real estate contractors and placed two (2) others on probation for failing to adhere to documented policies and standards.

Additionally, before construction begins, an approved MOP document must be posted. The construction contractor must describe all tasks associated with a project that may represent a direct threat to service such as AC Power work affecting DC power and work generating airborne debris open to working equipment, in order to describe the method for protecting the equipment from the threat. The Local Network Central Office Manager and/or Supervisor reviews the MOP and approves the equipment protection strategies - validating that those strategies are present and to be utilized during the construction activity.

Finally, Qwest provides contractors with explicit expectations regarding adherence to standards and an audit mechanism for ensuring compliance. The Introduction to Qwest Technical Publication 77350 provides "the material and workmanship requirements for personnel working in Qwest Central Offices and provide the basis for audit and evaluation of a job." Contractors are individually responsible for adhering to Qwest standards as well as applicable law and industry standards. When work operations jeopardize the network or fail to comply with safety standards, Qwest employees may expel contractors from the facility. Qwest employees are encouraged to stop construction work in progress to question a threat to personnel safety or risk to working equipment. Also, when problems are identified with a specific Real Estate contractor, a thorough root cause analysis is completed and appropriate action taken up to and including termination of a contractor.

2. Provide Advance Notification to and coordination with affected CLECs of construction occurring in Qwest Central Offices containing CLEC collocations. The General Mailout notification process would not be adequate.

Qwest agrees to provide CLECs with an Advance Notification process providing notice of building construction in Qwest Central Offices containing CLEC collocations. Advance Notification will provide targeted email to CLECs collocated in the affected Central Office at the time the project is funded by Qwest. The email, provided by the Collocation Project Management Center ("CPMC") will include the Central Office affected, description of the construction activity, date construction is planned to begin, date construction is planned to complete, and a Qwest contact name and number for the project. The Qwest contact can be used by CLECs to identify environmental issues or concerns during the project. Qwest will also provide status updates in the event the project changes significantly, i.e. the start date is moved forward or the scope of the activity increases. This process will be implemented effective May 2002 or as soon thereafter as possible in compliance with the agreed upon notification schedule. The following real estate work will be the subject of CLEC notifications: ? Building Additions ? HVAC Infrastructure Modifications ? Electrical Infrastructure Modifications ? Building Work for Space Rearrangements or Compartmentation ? Roof Replacement ? Other Building work that could affect the equipment environment

3. Ensure measures are in place to protect the collocation equipment environment including but not limited to protection from:

? Dust ? Dirt ? Metal Shavings ? Adverse Temperature conditions

Qwest contractors performing building construction work within Qwest Central Offices are required to apply appropriate industry standards in an effort to limit and control dust, dirt, metal shavings and temperature variations. As stated earlier, prior to starting any work activity the work steps for protecting working equipment must be documented in a MOP, Method of Procedure. After construction starts and during Real Estate building construction activities, the real estate contractors apply specific environmental requirements as described in the project design and specifications documents.

Qwest requires its contractors to adhere to specific aspects of American Society of Heating, Refrigerating and Airconditioning Engineers (ASHRAE) industry standards as it relates to Class 100,000 clean room requirements (described in Qwest Regional Policy REGN 000-010-019RG). These requirements provide specific airborne particulate standards that in turn are used for isolating working equipment from construction zones. Typically project specifications state that all construction work shall comply with Class 100,000 clean room requirements and must maintain a Class 100,000 environment in the Central Office environment regardless of any activity construction or otherwise. This means that airborne particulates of 0.5 micron and larger cannot exceed a count of 100,000 in one cubic foot of air.

Qwest requires its contractors to meet ASHRAE Class 100,000 requirement by specifying two methods in its project specifications:

? Isolation/Vacuum: Isolate working equipment form the construction zone, pressurize and seal for migration of airborne construction debris; o If isolation is not possible, then directly extract dust dirt and debris by using a HEPA vacuum with the operation of cutting and drilling tools. ? Filtration: If filtration of airborne particulates is questionable then particulate monitoring with instrumentation is used. Particulate counting monitors the environment only at one point in the room environment and is not necessary if the construction zone is isolated.

In addition to ASHRAE requirements, Qwest contractors must adhere to Section 2 of Tech Pub 77350 that specifically addresses Qwest’s expectations of personnel including employees, contractors and suppliers, while performing construction activities within Central Office buildings:

2.3.6 The cutting, filing, drilling, and milling or painting of the Qwest approved auxilliary framing, cable rack, etc., shall be done outside of the equipment area. When drilling of equipment or structures, that can not be removed from the facility, proper protection, and the use of HEPA vacuum shall be required. 2.3.7 General cleaning of the equipment facility or storage area in which work is being done shall be performed by the Service Supplier during the entire installation or removal process. Care shall be taken to generate a minimal amount of airborne dust. 2.3.8 The Service Supplier shall use only a High Efficiency Particulate Arrestor (HEPA) vacuum, capable of filtering particles larger than .3 microns in size, and equipped with a static dissipative hose in QWEST facilities to capture dust and chips from the drilling of floors, walls, ceiling, ironwork, and equipment during the uncrating process, and while cleaning cable racks and equipment. 2.3.9 The Service Supplier shall be aware of conditions that may result in equipment thermal shock (failure or degraded service brought on by a rapid change in temperature) and take steps to prevent its occurrence.

4. Prohibit unauthorized entry into CLEC space and ensure that CLEC security is not breached.

Qwest has documented procedures regarding physical security associated with CLEC collocations. Refer to Qwest’s PCAT under heading Central Office Security.

Additionally, in order to provide more direction to Qwest suppliers performing duties in Central Offices with CLEC collocations, pursuant to the agreed upon notification process, Qwest proposes replacement of Section 16.1.6 of Tech Pub 77350 to read as:

Qwest requires emergency access to all cages for safety purposes. Combination locks (or combination lock-boxes, with a key inside to unlock a keyed padlock) must be provided by the CLEC and attached to each cage. This will provide the Qwest representative with emergency access into the cage when needed. Qwest also requires that the CLEC forward the combination code to its cage lock to the appropriate personnel, e.g., State Interconnect Collocation Manager (SICM). The CLEC’s representative (emergency contact phone number located on the CLEC cage placard) must also retain the combination.

Qwest reserves the right to access CLEC enclosure when work is required in the Qwest-owned space above the cage (this includes access to the overhead ironwork, cable racking, electrical conduit, etc.). CLEC enclosure space will not be entered by anyone, for any reason, without first contacting the CLEC representative and the Qwest State Interconnect Collocation Manager and obtaining the required approval(s).

Qwest is committed to protecting CLEC equipment collocated in Qwest premises when performing activities within a Qwest Central Office that may reasonably be foreseen or predicted to harm such equipment. While Qwest strives to provide an environment for equipment to operate throughout its expected life cycle, it is reasonable to expect that some failures from environmental support equipment or personnel cannot always be avoided. Qwest does require its suppliers (including Qwest personnel) to comply with all published Qwest standards, applicable laws as well as industry standards and disciplines noncompliance. However, since Qwest can not provide a 100% event free environment for its network facilities and equipment, it in turn cannot provide this to CLECs. Nonetheless, Qwest remains committed to protecting and responding to the needs of the CLEC equipment environment with timely responses to correct adverse environmental events.

In response to the two (2) incidents identified by Eschelon in the Change Request, Attachment 1 provides Qwest’s evaluation of the incidents and the corrective action initiated by Qwest.

Sincerely,

Laurel L. Burke Staff Advocate, Policy & Law Technical Regulatory Interconnection Planning Local Networks, Qwest Corporation

cc: Mary Retka, Director, Legal Issues Barry Orrel, Director, 271 Technical Regulatory Paul Williams, Jr, Manager, Real Estate Wolfgang Wiewel, Director, Real Estate

Attachment 1

Eschelon described two locations, Minneapolis Orchard and Denver Main, where they believe Qwest’s current procedures failed to protect Eschelon's equipment effectively resulting in discrimination. Qwest’s evaluation and response to the issues are set forth below.

January-February 2002/Qwest’s Minneapolis Orchard Central Office

? Eschelon’s technician discovered dirt, dust and metal shaving on its collocation equipment ? Qwest had not notified Eschelon of this construction or its potential impact on Eschelon’s collocation space. ? During later visits to the site, Eschelon discovered excessive temperature levels that could also damage its equipment ? Cleaning the equipment required “powering down” the equipment which in turn resulted in customer outages ? Qwest removed all essential cooling to the area and replaced it with a fan ? Eschelon provided a technician to be available for the time period while a vendor was completing the clean-up ? Eschelon believes that at least two other CLEC collocations spaces were adversely affected by the same construction ? Qwest has an obligation to protect the CLEC collocation equipment with at least as much care as it would use to protect its own equipment ? Dust problem continued after the professional cleaning of the equipment. ? The lack of environmental control at this Qwest C.O. disturbs Eschelon. Eschelon does not believe Qwest equipment is subjected to similar environmental conditions. ? Eschelon requires that Qwest take immediate action to have their equipment cleaned again by a professional service. ? Eschelon will be submit their internal cost to Qwest for our clean-up effort ? Dust was also observed on other CLEC’s equipment.

Qwest Response:

Qwest Real Estate completed a root cause investigation of the Orchard environmental event and discovered the following:

? Project documentation for the construction related activity conveyed the proper information about Class 100,000 clean room requirements and the proper environmental temperature control requirements to the supplier. ? An approved MOP was in place identifying the required protection for working equipment ? Contractor provided protection in the form of dust partition walls separating the construction zone from working equipment. ? Contractor provided supplemental cooling equipment with the proper high efficiency filtration for temperature and airborne particulate control. ? Contractor failed to achieve proper room pressurization to prevent particulate migration from the construction zone to working equipment. ? Contractor failed to recognize the lack of room pressurization after the first event and a repeat of the migration occurred within days after the first event. ? The lack of proper pressurization was caused by incorrect placement of temporary floor fans and created improper air-flow and pressurization in the working equipment area. Incorrect fan placement provided a recirculating air-flow which allowed transport of airborne and non-airborne construction debris to the working equipment area.

Qwest Real Estate completed a root cause investigation of the Orchard environmental event and concluded the following:

? Qwest Real Estate concluded the root cause was contractor error, meaning the contractor was provided with appropriate environment specifications to protect equipment but did not perform to those specifications. ? Qwest confirmed that air filtration and temperature control was adequately provided in all areas of the Central Office and that the same high efficiency filtration was provided to the CLEC area during construction activity. ? It was observed that Qwest equipment was also soiled due to particulate migration from construction activities. ? The contractor did provide proper pressurization and sealing procedures in the MOP but failed in the attempt to properly pressurize and seal the working equipment area from the construction zone. ? While it was observed that measures were in place and seemed to be properly applied, the contractor failed to identify the recirculating air flow/ negative pressurization that resulted in subsequent environmental problems a few days later.

Qwest action taken:

? Contractor has been placed on probation. ? Lack of information to the contractor was not an issue, but Qwest will verify going forward that all construction documents contain the Class 100,000 clean room requirement with improved awareness. ? Temporary air flow, pressurization and sealing of construction zones will be added as specific MOP check list items to address and will be standard for all projects requiring construction zone isolation. ? Placement of floor fans and other temporary cooling equipment will be secured to prevent tampering. ? Contractors will be reminded that they are responsible for placement and operation of all temporary air movement as well as pressurization equipment to achieve and maintain environmental conditions. ? The MOP will require contractors to observe particulate accumulation and soiling of equipment surfaces before and periodically during construction activity and will address reporting this information to the Central Office Manager and the Real Estate Project Manager. ? Advance Notification process will identify people to contact for concerns about construction debris, temperature control and other environmental issues. ? To prevent the potential for pressurization and/or construction zone seal failure, only Real Estate contractors/agents will be permitted to provide fans and/or other means of cooling during construction periods.

March 2001/Denver Main Central Office

? Eschelon’s collocation cage was accessed without Eschelon's authorization or knowledge. A Qwest approved contractor removed the pins securing Eschelon’s collocation cage to gain access and Qwest security failed to notify Eschelon of the intrusion. ? A 1-inch copper pipe running across the span of Eschelon’s cage was installed. The location and height of the pipe restricted Eschelon’s ability to expand the existing cable ladder racking for future growth. Additionally, the pipe was believed to be a water pipe, which, if ruptured, had significant potential for causing damage to personnel and property. ? There were two (2) additional ½-inch copper pipes running across the cage at ceiling height. These pipes appeared to be water pipes serving the cooling unit adjacent to Eschelon’s cage. ? There was a significant amount of dust within the cage and on the collocation equipment. Eschelon asked Qwest to thoroughly clean Eschelon’s collocation cage and the surrounding area.

Qwest response:

The Qwest State Interconnect Manager ("SICM") for Colorado arranged a meeting between himself, Eschelon representatives shortly after Eschelon notified Qwest of the problems in March 2001, the Qwest Real Estate Manager and the contractor performing work in the Qwest Central Office at the time Eschelon voiced their concern. The contractor was remodeling space in the west half of the 7th floor of Denver Main to support future equipment placement in that area.

? The meeting was held at Denver Main and the investigation resulted in the contractor being directed to perform several additional tasks: ? Remove copper pipes placed at the 8' level above the Eschelon cage; ? Place piping pans under the existing water pipes to ensure that no dripping water would fall into Eschelon's cage; ? Have Eschelon's space and equipment cleaned; ? Make arrangements with Eschelon PRIOR to entering their space to correct the pipe related issues; ? Take steps to ensure no further unauthorized entry would occur by adhering to the access guidelines and permissions required. ? The Central Office Supervisor indicated that he had not been contacted by the contractor for permission to enter the collocation cage; he also indicated that he had no way to access the cage as he did not have a combination or the key. Qwest action taken:

? The SICM and the Real Estate Manager reiterated to the contractor that they must have specific permission to enter CLEC space using first the number located on the cage. Product Catalog ("PCAT") language has been provided since this occurrence that clarifies Qwest personnel and vendor roles while working in CLEC physical collocations. Additionally, Qwest proposes to add additional clarity in its Technical Publication 77350 regarding contractor requirements relating to CLEC security while working in Qwest buildings. ? The SICM reviewed collocation access requirements with the Central Office supervisor. ? Qwest employees are now encouraged and expected to question any activity that does not comply with security guidelines. ? Eschelon provided the appropriate access information to the Central Office supervisor. ? Following the submittal of this change request, a Design Construction Director and Project Manager physically confirmed that leak protection had been installed and conforms to that for other equipment in Denver Main. ? The temporary applications of filters for all new ductwork grilles, registers and diffusers will be a MOP checklist item. o Qwest will reconfirm the application of temporary filtration on all new ductwork outlets is contained in construction documents.

Finally, upon acceptance of this response by the CLEC community, Qwest Real Estate will issue a document to alert Qwest Real Estate Design Construction Field Directors of all actions contained in this Change Request response. This alert will require confirmation that all construction documents contain the items specified herein.


Open Product/Process CR PC022802-1 Detail

 
Title: Qwest DSL services live until CLEC services installed
CR Number Current Status
Date
Area Impacted Products Impacted

PC022802-1 Completed
1/15/2003
Maintenance/Repair, Provisioning Resale, Unbundled Loop, UNE
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Bliss, Susan
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

When a customer has ancillary products, such as DSL, on one of their lines, it is Eschelon’s understanding that Qwest handles the provisioning of the DSL in a different department, within Qwest, than the normal line provisioning. It has been Eschelon’s experience that the department that handles the DSL does not recognize the FDT on an order and that it does not receive updates to orders as quickly. This will cause the DSL to go down before a scheduled time on a conversion and will also cause the DSL to go down when a supplement to the LSR is issued to change a DD.

Eschelon sent a request on 1/30/02 to convert service for a customer. The conversion to Eschelon Unbundled Loop service was due on 2/9/02. Although the line was equipped with DSL, Eschelon was not aware of the DSL because it was not reflected on the CSR. Eschelon did not find out that the line was equipped with DSL until the conversion had started. It became necessary to push-out the Due Date (DD) for the conversion of this service to a later date, because of the DSL. Eschelon followed a Qwest process by sending a supplement for a DD change and escalating with Qwest. Qwest took down the DSL service. Eschelon opened a repair ticket. Qwest gave a 24-hour commitment. This customer was without their DSL for 24 hours because Qwest had already removed it, not waiting for the conversion to complete. If Qwest had completed the order in the Service Order Processor, the customer could have been without DSL for up to 10 days because the customer would have had to place a new order.

On another LSR to convert both the customer’s voice lines and DSL, with an original DD of 2/20/02, Eschelon issued a supplement for a DD change. Following the Qwest process, Eschelon issued the supplement 2/19/02 at 3:31 PM and escalated with Qwest. The customer’s voice lines remained in service however Qwest took down the DSL service on 2/20/02.

Eschelon asks Qwest to develop, document and train an adhered to process to keep all ancillary services working, as is, until the conversion to the CLEC is complete, accepted and Qwest translations are completed. Eschelon also asks Qwest to include in the process a more ‘real time’ flow of order changes to the departments that provision the DSL services.

Expected Deliverable

A developed, documented, trained and adhered to process to ensure ancillary products, such as DSL, remain working with Qwest until the conversion to a CLEC is complete, the services are working with the CLEC and the conversion is accepted by the CLEC.


Status History

02/28/02 - CR Submitted by Eschelon.

02/28/02 - CR acknowledged by P/P CMP Manager.

03/06/02 - Eschelon contacted via phone and email to establish date and time for clarification call (call to be made 03/07/02 @ 10:00 a.m. MST)

03/07/02 - Clarification call held with Eschelon

03/08/02 - Clarification meeting minutes sent to all participants for review

03/12/02 - Clarification meeting minutes posted to database

03/20/02 - CMP Meeting - Eschelon introduced CR as Walk-on. CR status changed to Clarification. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

04/17/02 - CMP Meeting - Eschelon introduced CR. CR status changed to Evaluation. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

05/08/02 - Issued Qwest draft response dated May 8, 2002 to Eschelon and changed status to presented.

05/15/02 - CMP Meeting - CR status "Presented" unchanged. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/18/02 - Issued Revised Qwest response dated June 18 , 2002 to Eschelon

06/19/02 - CMP Meeting -- CR status changed to "Evaluation". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07/11/02 - Issued Revised Qwest response dated July 10, 2002 to Eschelon

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status "Evaluation" was not changed.

08/16/02 - Issued Revised Qwest response dated August 15, 2002 to Eschelon

08/21/02 - August CMP Meeting: CR was changed to CLEC Test. Minutes on this CR to be posted to the Project Meetings section.

09/09/02 - Posted e-mail from Bonnie Johnson dated 9/3/02

09/19/02 - September CMP Meeting: CR was changed to Development. Minutes on this CR to be posted to the Project Meetings section.

10/10/02 - Issued Revised Qwest response dated October 2 , 2002 to Eschelon

10/16/02 - October CMP Meeting - Minutes on this CR to be posted to the Project Meetings section.

11/13/02 - Issued Revised Qwest response dated November 7, 2002 to Eschelon

11/20/02 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/10/02 - Issued Revised Qwest draft response dated 12/6/02 to Kathy Stitcher at Eschelon

12/11/02 - Revised Draft Response posted to the web site

12/16/02 - Issued Product Notification PROD.12.16.02F.00886.CR_Update_DSL Service

12/18/02 - December CMP Meeting - Qwest presented revised draft response to this CR. CR status changed to CLEC Test. Meeting minutes will be posted to this CR's Project Meetings section.

01/15/03 - January CMP Meeting - CR status changed to Completed. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

01/15/03 January CMP Meeting Bonnie Johnson with Eschelon suggested that this CR be moved to Completed status. This CR will move to Completed status.

12/18/02 December CMP Meeting Cindy Schwartze presented the Qwest updated response and said that Qwest had adjusted an internal DSL system to recognize normal processing when Frame Due Time is entered on an order. Frame Due Time (FDT) on orders accepted after 12/17/02 will be recognized in the Qwest internal DSL system. The level 1 notification of this Qwest internal system change was sent on Monday, December 16th and the change was implemented on December 17th. Eschelon suggested that this CR be moved to CLEC Test and the CLEC Community agreed.

11/20/02 November CMP Meeting Cindy Schwartze reviewed the Qwest updated response dated 11/7/02 and said Qwest expects to implement changes 12/15/02. The change will adjust an internal Qwest system to recognize and adjust normal processing when the Frame Due Time is populated and will keep Ancillary services, such as DSL up and working until the CLEC services are installed. This CR will remain in Development status.

- 10/16/02 October CMP Meeting Susie Bliss reviewed the revised response dated October 2, 2002 and said that she had not been made aware of any recent outages since the August 30th outage. Bonnie Johnson with Eschelon said that they are working around the problem. Susie said the technical team recommendations will be made by 10/18/02 and the implementation plan will be developed by 10/30/02. The CR will remain in Development status.

- 09/18/02 September CMP Meeting Qwest provided an update on this CR, which was put into CLEC test at the August CMP Meeting. There was one case where DSL went down in error. Qwest is having a technical meeting later this week to discuss work that needs to be done to resolve the problem and will provide a read-out at the October CMP meeting. Because there is further work required on this CR, Qwest and Eschelon agreed to move this CR to Development status.

-- From: Bonnie Johnson@eschelon.com on 9/3/02 4:48p To: "'ljsanch@qwest.com'" , jlnovak@qwest.com cc: "Clauson, Karen L." , "Knudson, Ronda K." , "Johnson, Bonnie J."

Hi Jean and Linda, I would like to provide you an example of DSL being taken down prior to cut. In this case, the customer was so upset Eschelon had to push the cut. If this customer cancels the conversion I will let you know. I am uncertain who will provide this example to Susie Bliss.

Please read below.

The Perfect Blend DD 8/30/02 @11:30 cst. At ~10:30am TNT was notified by Sales Rep the customer's DSL service was down. Because the customer was so upset about the DSL being disconnected the conversion was put on hold with the Qwest tester and the order was sup'd in IMA for new dd. Qwest DSL repair was contacted, An Eschelon tester stayed on line with repair for ~1 hr until service was re-established. The tester verified with the customer their service was up and running. Roughly 2 hours of downtime for the end user.

Thanks,

Bonnie

08/21/02 - August CMP Meeting Minutes: Qwest provided an update on the DSL SWAT team findings and the process improvements that have been put in place. Qwest requests feedback from the CLEC community on DSL orders disconnected in error. Eschelon said that migration orders were going well and that they have people watching conversion orders. This CR will be moved to CLEC test and Eschelon will let Qwest know of problems.

07/17/02 - July CMP Meeting Minutes: Eschelon stated there are multiple issues associated with DSL. There are weekly calls between Eschelon and their Qwest Service Managers to discuss DSL issues. Eschelon requested to keep this CR in Evaluation status. Qwest asked what it would take in Eschelon’s view to take this CR to completed status. Eschelon replied zero orders going down . Qwest stated that trials on DSL orders have been successfully performed. It was agreed to keep the Eschelon and Qwest teams working closely together on DSL issues. CR status remains evaluation.

Alignment/Clarification Meeting Time/Date:10:00 a.m. (MDT) / Thursday 7 March 2002 Place: Conference Call Conference Call-In No.: TEL: 877.564.8688 CODE: 6265401 PC022802-1 "Qwest services live until CLEC services installed"

Attendees: Kathleen Stichter, Eschelon Tina Schiller, Eschelon Jeffery B. Cook, Qwest Michael Keegan, Qwest Deni Toye, Qwest Russ Urevig, Qwest Brett Fesler, Qwest Michael Whitt, Qwest Cindy Buckmaster, Qwest

Introduction of Attendees Attendees introduced.

Review Requested (Description of) Change Description: When a customer has ancillary products, such as DSL, on one of their lines, it is Eschelon’s understanding that Qwest handles the provisioning of the DSL in a different department, within Qwest, than the normal line provisioning. It has been Eschelon’s experience that the department that handles the DSL does not recognize the FDT on an order and that it does not receive updates to orders as quickly. This will cause the DSL to go down before a scheduled time on a conversion and will also cause the DSL to go down when a supplement to the LSR is issued to change a DD. Eschelon sent a request on 1/30/02 to convert service for a customer. The conversion to Eschelon Unbundled Loop service was due on 2/9/02. Although the line was equipped with DSL, Eschelon was not aware of the DSL because it was not reflected on the CSR. Eschelon did not find out that the line was equipped with DSL until the conversion had started. It became necessary to push-out the Due Date (DD) for the conversion of this service to a later date, because of the DSL. Eschelon followed a Qwest process by sending a supplement for a DD change and escalating with Qwest. Qwest took down the DSL service. Eschelon opened a repair ticket. Qwest gave a 24-hour commitment. This customer was without their DSL for 24 hours because Qwest had already removed it, not waiting for the conversion to complete. If Qwest had completed the order in the Service Order Processor, the customer could have been without DSL for up to 10 days because the customer would have had to place a new order. On another LSR to convert both the customer’s voice lines and DSL, with an original DD of 2/20/02, Eschelon issued a supplement for a DD change. Following the Qwest process, Eschelon issued the supplement 2/19/02 at 3:31 PM and escalated with Qwest. The customer’s voice lines remained in service however Qwest took down the DSL service on 2/20/02. Eschelon asks Qwest to develop, document and train an adhered to process to keep all ancillary services working, as is, until the conversion to the CLEC is complete, accepted and Qwest translations are completed. Eschelon also asks Qwest to include in the process a more ‘real time’ flow of order changes to the departments that provision the DSL services.

Confirm Areas & Products Impacted Unbundled Loop UNE (Unbundled Network Elements) Resale

Confirm Right Personnel Cindy Buckmaster indicated her group will take responsibility for coordinating the response to this CR.

Identify/Confirm CLEC’s Expectation A developed, documented, trained and adhered to process to ensure ancillary products, such as DSL, remain working with Qwest until the conversion to a CLEC is complete, the services are working with the CLEC and the conversion is accepted by the CLEC.

Identify any Dependent Systems Change Requests None.

Establish Action Plan (Resolution Time Frame) Initial Qwest Response to Eschelon will be coordinated/delegated by Cindy Buckmaster. She will attempt to have the draft response issued by April 10.


CenturyLink Response

December 6, 2002

DRAFT REVISED RESPONSE For Review by CLEC Community and Discussion at December’s CMP Meeting

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT:Qwest’s Change Request Revised Response - CR PC022802-1 Qwest DSL services live until CLEC services installed.

On December 16, 2002 Qwest will send out a Level 1 notification to all CLECs regarding the implementation of this CR. The notification will remind CLECs that the internal DSL system change will be implemented on December 17, 2002. This change will adjust the internal system to recognize and adjust normal processing when Frame Due Time is present on the CLEC order. CLEC orders received after December 17, 2002 with a Frame Due Time will then be recognized by this system.

Sincerely,

Susie Bliss Director Process Management Qwest

- November 7, 2002

DRAFT REVISED RESPONSE For Review by CLEC Community and Discussion at November’s CMP Meeting

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT:Qwest’s Change Request Revised Response - CR PC022802-1 Qwest DSL services live until CLEC services installed.

As Qwest communicated during the October 16, 2002 CMP meeting, we were working with the DSL technical team to develop some options on how we could meet the requests of this CR. We also committed to having an implementation plan developed by 10/30/02.

We have researched our options, developed our implementation plan and are driving towards a solution. Our solution is targeted for implementation no later than December 15, 2002. This solution will adjust an internal DSL system to recognize and adjust normal processing when Frame Due Time is entered on an order. This internal system change will enable the process to keep ancillary services, like DSL, working as is, until the conversion to the CLEC is complete and accepted. This adjustment will also keep ancillary services, like DSL, working as is when supplementing or canceling a disconnect order.

Again, we are committed to identifying and implementing solutions so DSL is kept live during a conversion. We will continue to work with the technical team on this system enhancement through CLEC evaluation to ensure success.

Sincerely,

Susie Bliss Director Process Management Qwest

- October 2, 2002

DRAFT REVISED RESPONSE For Review by CLEC Community and Discussion at October’s CMP Meeting

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT:Qwest’s Change Request Revised Response - CR PC022802-1 Qwest DSL services live until CLEC services installed.

Qwest agreed at the September 18, 2002 CMP Meeting to provide an updated response to Eschelon’s Change Request PC022802-1, which requested the following:

-Qwest develop a process which keeps ancillary services like DSL working as is, until the conversion to the CLEC is complete and accepted. -Qwest develop a process which keeps ancillary services like DSL working as is, when supplementing or canceling a disconnect order.

First, Qwest understands the importance of keeping the DSL live during conversions and is committed to working with customers when outages occur. For the Retail/Resale to UNE-P orders, our July 11th process improvements are still working and 201 orders were processed successfully from July 26 - September 23.

Secondly, Qwest recently had an outage on August 30th. The SWAT team investigated the outage and it was an unbundled loop order with DSL. A Technical SWAT team was then pulled together. This team is identifying short and long term mechanical solutions and will have options and recommendations by October 18th, 2002. From there Qwest expects to have an implementation plan developed by October 30th.

Finally, we are committed to identifying and implementing solutions so that DSL is kept live during a conversion. We will continue to monitor and implement solutions when/if problems arise.

Sincerely,

Susie Bliss Director Process Management Qwest


Open Product/Process CR PC012902-2 Detail

 
Title: System Outage Notification
CR Number Current Status
Date
Area Impacted Products Impacted

PC012902-2 Completed
4/17/2002
Other: Qwest backend systems
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Ames, Tamara
Director:
CR PM: Thomte, Kit

Description Of Change

Currently when Qwest's backend systems experience problems or outages that affect CLECs, the CLECs are not notified. This can cause considerable time and energy. For example, sometime around 1/14/02, CARS was experiencing a problem so Service Orders would not post. Eschelon can not complete all of its tasks in its systems to bill a customer until the Qwest Service Order posts. Eschelon starts checking following the fifth business day after the DD and continues to check until the Qwest Service Order posts. This is very time consumming.


Status History

01/28/02 - CR Submitted by Eschelon.

01/29/02 - CR acknowledged by P/P CMP Manager.

02/01/02 - CLEC contacted to schedule clarification meeting; telephone message left to schedule meeting.

02/05/02 - Clarification Meeting conducted with submitting CLEC.

02/08/02 - Clarification Meeting minutes transmitted to submitting CLEC & posted in CMP data base.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/12/02 - Draft response dated 03/01/02 issued to Eschelon. CR Status changed to "Presented"

03/20/02 - March CMP Meeting: Qwest presented their response, CLECs agreed to change CR Status to "CLEC Test." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/21/02 - Formal response dated 03/01/02 posted to CMP database

03/22/02 - Formal response dated 03/01/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/09/02 - Update e-mail from Eschelon on System Outage Notification Process

04/09/02 - Reply e-mail from Qwest with modification proposal

04/09/02 - Return e-mail from Eschelon acknowledging modification

04/17/02 - April CMP Meeting: CLECs agreed to close CR. Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site


Project Meetings

04/09/02 - Return e-mail from Eschelon acknowledging modification

Subject: FW: PC012902-2 System Outage Notification Date: Tue, 9 Apr 2002 14:18:53 -0500 From: "Stichter, Kathleen L." To: tmead@qwest.com CC: "Johnson, Bonnie J."

Todd, If Qwest does not send an Initial Event Notification when it resolves the issue within an hour then I do believe that the Closure Notification should indicate that it is initial and closure. It would decrease confusion. Thanks for the proposal.

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc 612-436-6022 klstichter@eschelon.com

--

04/09/02 - Reply e-mail from Qwest with modification proposal

Subject: Re: PC012902-2 System Outage Notification Date: Tue, 09 Apr 2002 11:42:43 -0600 From: Todd Mead Organization: Qwest Communications International, Inc. To: "Stichter, Kathleen L." Kathy, I have talked to the people here about this example and they told me the following:

"If an event occurs that is settled rather quickly (within 1 hour), we only send out a Closure Notification since the event has passed. No Initial Notification is required. To decrease confusion, I believe we could accommodate this request by simply checking both the Initial and Closure boxes, and putting the date and time in the Closure Box. But the name of the document and subject line will read Closure only."

Could you let me know if what they propose above will help you. If it does, they can implement immediately.

Thanks

Todd

--

04/09/02 - Update e-mail from Eschelon on System Outage Notification Process

Subject: RE: PC012902-2 System Outage Notification Date: Tue, 9 Apr 2002 10:08:56 -0500 From: "Stichter, Kathleen L." To: tmead@qwest.com

Todd, I am monitoring the process. Qwest sent one Event Notification, which dealt with SOPAD, it was a closure. We never did get the initial. I do not know why.

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc 612-436-6022 klstichter@eschelon.com

--

02/05/02 - Clarification Meeting conducted with submitting CLEC.

11:30 a.m. (MDT) / Tuesday 05th February 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC012902-2 "System Outage Notification"

Attendees: Kathleen Stichter, Eschelon Ken R. Olson, Qwest Stephen Sheahan, Qwest Monica Manning, Qwest Peter Wirth, Qwest

Introduction of Attendees: Attendees introduced.

Review Requested (Description of) Change: Currently when Qwest's backend systems experience problems or outages that affect CLECs, the CLECs are not notified. This can cause considerable time and energy. For example, sometime around 1/14/02, CARS was experiencing a problem so Service Orders would not post. Eschelon can not complete all of its tasks in its systems to bill a customer until the Qwest Service Order posts. Eschelon starts checking following the fifth business day after the DD and continues to check until the Qwest Service Order posts. This is very time consumming. Requested Deliverables: A process to notify CLECs when a Qwest backend system experiences problems or outages that directly or indirectly affect CLECs.

Kathy Stichter, Eschelon reviewed the CR description. Backend systems identified relating to the CR include CARS and BOSS, with potential others. Ken Olson addressed the Eschelon CARS example. He did provide notification to Eschelon, via e-mail of the outage (01/14/02). Qwest issues notifications to the CLECs for front-end systems when outages occur.

Confirm Areas & Products Impacted: Appropriate products & areas identified in CR.

Confirm Right Personnel Involved: Qwest & Eschelon confirmed appropriate personnel were in attendance; however the Qwest Systems representative did not attend.

Identify/Confirm CLEC’s Expectation: Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR; or provide an expedited response to the CR.


CenturyLink Response

March 1, 2002

Ms. Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc.

SUBJECT: Qwest’s Change Request Response - CR #PC 012902-2 System Outage Notification

REQUEST: Currently when Qwest's backend systems experience problems or outages that affect CLECs, the CLECs are not notified. This can cause considerable time and energy. For example, sometime around 1/14/02, CARS was experiencing a problem so Service Orders would not post. Eschelon can not complete all of its tasks in its systems to bill a customer until the Qwest Service Order posts. Eschelon starts checking following the fifth business day after the DD and continues to check until the Qwest Service Order posts. This is very time consuming.

RESPONSE: Qwest has developed a new Unplanned Event Notification process that is based upon the newly approved Change Management Process (CMP) guidelines (See Production Support, Section 11.0). This process was launched on February 1, 2002.

Qwest is also completing the Unplanned Event Notification process document that will be available on the Wholesale Web site.

Qwest will continue to send Notifications that specifically correlate to the CMP approved systems.

Sincerely,

Tamara Ames IT 271 CLEC NOTIFICATION TEAM Qwest

cc: Barbara Spence, Director Information Technology, Qwest


Open Product/Process CR PC012902-1 Detail

 
Title: Deaveraged Rate Zones by Address
CR Number Current Status
Date
Area Impacted Products Impacted

PC012902-1 Completed
5/15/2002
Pre-Ordering, Ordering, Billing, Provisioning Unbundled Loop, Une
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Buckmaster, Cindy
Director:
CR PM: Thomte, Kit

Description Of Change

Loop rates are based upon geographically deaveraged rates, so the rates vary by zone. Eschelon needs to know what rate Qwest will bill for each Unbundled Loop we order. Qwest must have a means of determining the rate zone per address in order to bill the CLEC correctly. Eschelon asks Qwest for the documentation that allows Eschelon to determine where our existing lines and our future lines fall within the zones that have been established for geographically deaveraged loop rates. Such information should be posted on Qwest's Wholesale web page.


Status History

01/28/02 - CR Submitted by Eschelon.

01/29/02 - CR acknowledged by P/P CMP Manager.

02/01/02 - CLEC contacted to schedule clarification meeting; telephone message left to schedule meeting.

02/05/02 - Clarification Meeting conducted with submitting CLEC.

02/08/02 - Clarification Meeting minutes transmitted to submitting CLEC & posted in CMP data base.

02/20/02 - CMP Meeting - CLEC community clarification conducted. CR status changed to "Evaluation." Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02).

03/12/02 - Draft response dated 03/01/02 issued to Eschelon. CR Status changed to "Presented"

03/12/02 - CLEC Notification PROD.03.12.02.F.00733.UNE_C_&_P_Deaverage with PCAT updates concerning Geographic Deaveraging

03/20/02 - March CMP Meeting: Qwest presented their response, CLECs agreed to change CR Status to "CLEC Test." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/21/02 - Formal response dated 03/01/02 posted to CMP database

03/22/02 - Formal response dated 03/01/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/17/02 - April CMP Meeting: CLECs requested to keep CR open and provide a status update at May CMP meeting. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

05/15/02 - May CMP Meeting: Eschelon agreed that the CR could be closed.


Project Meetings

03/12/02 - CLEC Notification PROD.03.12.02.F.00733.UNEC&PDeaverage with PCAT updates concerning Geographic Deaveraging

Announcement Date: March 12, 2002 Effective Date: April 11, 2002 Document Number: PROD.03.12.02.F.00733.UNEC&PDeaverage Notification Category: Product Notification Target Audience: CLECs, Resellers Subject: Updates for UNE-C, UNE-P ISDN BRI and Geographic Deaveraging Beginning April 11, 2002, Qwest will issue updates to its Wholesale Product Catalog that includes new/revised documentation for UNE-C, UNE-P ISDN BRI and Geographic Deaveraging.

The UNE-C PCAT will be modified to include links to the new Geographic Deaveraging PCAT and the CLEC Requested UNE Construction (CRUNEC) process. The UNE-P ISDN BRI PCAT will be updated to include USOCS UGUST, UGUFM on the downloadable USOCs table. The Geographic Deaveraging PCAT will provide general information on Geographic Deaveraging pricing for Unbundled Local Loop, Unbundled Network Elements-Platform (UNE-P) and Unbundled Network Element Combination (UNE-C) with state specific effective dates. Geographic Deaveraging zones may be applied based on distance from the Central Office (CO) or by the wire center.

You will find a summary of these updates on the attached Web Change Notification Form. Actual updates are found on the Qwest Wholesale Web site at these URLs:

UNE-C: http://www.qwest.com/wholesale/pcat/unec.html UNE-P ISDN BRI: http://www.qwest.com/wholesale/pcat/unepisdnbri.html Geographic Deaveraging: http://www.qwest.com/wholesale/clecs/geodeavg.html

You are encouraged to provide feedback to this notice through our web site. We provide an easy to use feedback form at http://www.qwest.com/wholesale/feedback.html. A Qwest representative will contact you shortly to discuss your suggestion.

--

02/05/02 - Clarification Meeting conducted with submitting CLEC.

11:00 a.m. (MDT) / Tuesday 05th February 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC012902-1 "Deaveraged Rate Zones by Address"

Kathleen Stichter, Eschelon Bernadette Derlein, Qwest Stephen Sheahan, Qwest Craig Saunders, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Description: Loop rates are based upon geographically deaveraged rates, so the rates vary by zone. Eschelon needs to know what rate Qwest will bill for each Unbundled Loop we order. Qwest must have a means of determining the rate zone per address in ordeer to bill the CLEC correctly. Eschelon asks Qwest for the documentation that allows Eschelon to determine where our existing lines and our future lines fall within the zones that have been established for geographically deaveraged loop rates. Such information should be posted on Qwest's Wholesale web page. Requested Deliverables: Easily accessable, user friendly, current and accurate documentation used for billing deaveraged loop rates. This could be by address, wire center, CLLI, so long as it is clear which lines fall within which zones.

Kathy Stichter, Eschelon reviewed the CR description. Bernadette Derlein, qwest indicated that the requested information for AZ, CO, WY & MT may be extracted from IMA when using the "Address Validation" capability, and referencing the RTD fields for the appropriate zone. A cross-reference can then be made to the applicable SGAT, Exhibit A for rates. Spread sheets should have been distributed to the CLECs for the states in the Qwest region containing similar information (Qwest to verify). CLECs will need to otain zone maps from the commission to determine rates using the spreadsheets.

Issues identified in the meeting include: (1) spreadsheet availability [Qwest item] ; (2) zone map availability from commission [Qwest item]; and (3) availability of a web based system for Loop rates [Qwest item].

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Appropriate products & areas identified in CR.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & Eshelon confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC – what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)} Qwest to evaluate CR. During the February 2002 Monthly P&P CMP Meeting, Qwest will either solicit input from CLEC community & provide potential solutions to the CR; or provide an expedited response to the CR.


CenturyLink Response

March 1, 2002

Kathy Stichter ILEC Relations Manager Eschelon Telecom, Inc

SUBJECT: Qwest’s Change Request Response - CR # PC 012902-1: Deaveraged Rate Zones by Address

This letter is in response to your Change Request PC012902-1, requesting documentation to allow CLECs to determine where their existing and future lines fall within the zones that have been established for geographically deaveraged loop rates.

For the states of AZ, CO, WY and MT the zones are distance sensitive from the Central Office to end user premis. CLECs currently can input an end user address through IMA using “address validation”. The RTZ field will populate with the appropriate zone in relation to the address. The CLEC would then cross-reference the zone with the applicable rate either in their contract or SGAT Exhibit A.

For the remaining states (MN, IA, SD, ND, NE, OR, WA, NM and UT) the zones are based on wire center. As Cost Dockets were completed by state the CLEC community received CLEC Notifications in regards to the De-Averaging. In the CLEC Notification, a spreadsheet provided wire center in relation to the zone. The CLEC would then be able to cross-reference the zone with the applicable rate in their contract or SGAT. CLEC Notifications are provided with this response.

In response to this CR, Qwest will provide the CLECs with a spreadsheet that will reflect the zones based on wire center for MN, IA, SD, ND, NE, OR, WA, NM and UT. This information will be located on the Qwest Wholesale Website in April. The URL and the date to be published will be provided to the CLEC Community by March 25, 2002

Zone maps for distance sensitive states AZ, CO, MT, WY are available at the state commissions office. As these maps are not electronic, Qwest will not publish them on the Wholesale website at this time.

Sincerely,

Bernadette Derlein Unbundled Loop Product Manger Qwest

Cc: Cindy Buckmaster, Manager Product Management, Qwest Debra S Smith, Product Manager, Qwest Bill Campbell, Director Product Management, Qwest Todd Mead, Change Management, Qwest


Open Product/Process CR 5527214 Detail

 
Title: Legacy CR Utilization of Stranded DS0 Terminations
CR Number Current Status
Date
Area Impacted Products Impacted

5527214 Withdrawn
5/11/2001
Ordering, Provisioning
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

Qwest should develop a process to allow CLECs to reclaim stranded DS0 terminations. Qwest previously permitted CLECs to purchase DSO terminations in less than 100 block increments. Under this policy, Qwest would nonetheless deliver an entire 100 pair cable block to the CLEC and terminate all 100 pair at the ICDF. However, only the pairs ordered by CLECs were activated in TIRKS. Qwest then changed its policy and began requiring CLECs to purchase terminations only in 100 block increments. Once this policy was in effect, Qwest did not continue numbering terminations in sequence. For instance, at one site, Eshelon had ordered 549 terminations under the initial policy. Qwest provided Eschelon with 600 terminations but only activated 549 of the terminations. When Eschelon ordered additional terminations to that site after the policy change, Qwest provided Eschelon with a separate 100 termination block beginning at 600, thereby stranding the terminations between 550 and 600 that had already been wired.

Eschelon asked that Qwest provide a process by which CLECs can order, pay for and use the stranded DS0 terminations that were delivered and terminated by Qwest but not ordered by the CLEC. Qwest (through Keith Rice) informed Eschelon that Qwest has no product offering to manage the process of filling in the DS0 termination holes and will not be developing one in the foreseeable future.

Qwest should provide CLECs with a process to use the unused but connected DS0 terminations to ensure efficient use of the network. The connections are wired and ready to go. Qwest should accept payment for each unutilized pair and activate each pair in TIRKS. This would provide Qwest with additional revenue and enable the efficient use of both Qwest and CLEC networks. Please modify Qwest’s processes to enable CLECs to purchase and use the unused DS0 terminations that resulted from Qwest’s decision to fill orders out of sequence when it changed its policy to require CLECs to purchase DS0 terminations in 100 block increments. Please identify any rate Qwest would propose to charge


Status History

5/01/01 - CR received from Jessica Johnson of Eschelon

5/01/01 - Status changed to New - To be Validated

5/01/01 - Status changed to New - To be Evaluated

5/01/01 - Updated CR sent to Jessica Johnson, Lynne Powers, Karen Clauson and Janet Houston

5/11/01 - Status changed to Canceled - Co-Provider

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR 5527234 Detail

 
Title: Legacy CR Change the due date on the service order, instead of using a "hard hold"
CR Number Current Status
Date
Area Impacted Products Impacted

5527234 Completed
6/20/2001
Ordering Unbundled Loop, related items such as voice mail and DSL
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

When Qwest stops a cutover on the day of cut due to a Qwest issue, Qwest should change the actual due date in the Service Order Processor (SOP) on both the disconnect and the "n" order for loop installations, using the appropriate jeopardy code (indicating the reason the original due date is not met). If a cutover is stopped on the day of cut due to a CLEC issue, the CLEC submits a supplemental order, which causes the due date to be changed on the service orders. When a cutover is stopped on the day of cut due to a Qwest issue, however, Qwest testers currently use what they refer to as a "hard hold" on the service order that is disconnecting the customer’s existing service. This holds the line translations from completing through RCMAC. Nonetheless, many times, the service order in the SOP completes, and downstream departments complete their work. Because Qwest uses a "hard hold," the actual due date the cutover is performed is changed but the related service orders do not reflect the new date. It is unclear whether there is a jeopardy notice on the new connect installing the loop has a due date change in the SOP and reflects the appropriate jeopardy code or if the order appears to be completing on the original due date with no jeopardy code assigned to it.

This process creates customer-affecting problems. In many cases, the "hard hold" fails to work as intended, and the customer loses service completely. Because the service order has completed, it may be difficult to obtain the same facilities and OE to rebuild the customer in a timely manner. Even if the "hard hold" works as intended, the customer’s service can still be affected. For example, when a "hard hold" is used for an order for a customer with voice mail, the forwarding features are still functioning (because the "hard hold" holds the line translations from completing through RCMAC) but the mailbox portion of the customer’s voice mail is taken down (because the due date on the service order was not changed to reflect the hold). Qwest takes down the mailbox because, without a due date change, one group at Qwest does not know that the other has changed the date for completion of the order. The calls are forwarded, but there is no mailbox to receive them. This problem is not limited to voice mail and affects other areas, such as DSL. Qwest should stop using the "hard hold" and instead change the due date on the service order itself.


Status History

4/27/01 - CR received from Karen Clauson of Eschelon

5/01/01 - Status changed to New - To be Validated

5/01/01 - Status changed to New - To be Evaluated

5/01/01 - Updated CR sent to Jessica Johnson, Lynne Powers, Karen Clauson and Janet Houston

5/16/01 - Status changed to Reviewed - Under consideration

6/20/01 - CR status changed to Complete - Process Deployed as per Lynne Powers or Eschelon

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR 5579338 Detail

 
Title: Legacy CR Access to DSL pre qualification information
CR Number Current Status
Date
Area Impacted Products Impacted

5579338 Withdrawn
7/12/2001
Ordering Resale, Unbundled Loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

Please improve CLEC access to the DSL pre-qualification information to reduce the number of error messages and give CLEC at least the same access to the same information as Qwest receives. Often, when Eschelon uses Qwest’s IMA-GUI loop pre-qualification tool, the result is indeterminate. Instead of a yes or no response, Eschelon receives an error message. For example, the error message may indicate that the address and telephone number did not match. When Eschelon then calls Qwest, Qwest is able to run the request and receive a yes or no answer, even though Qwest is using the same address and telephone information used by Eschelon. In some cases, the customer already has DSL (and wants to upgrade speed, etc.). Even though the customer already has DSL, Eschelon cannot get pre-qualification information using IMA-GUI. But, when Eschelon calls Qwest, Qwest is able to retrieve the information using its internal systems. Eschelon has been working with Qwest to try to resolve this issue. Recently, Qwest has indicated that the issue may be addressed in Release 9.0, which will not occur until the end of the year. That is too long to wait. Also, no documentation has been provided as to what changes will be made during Release 9.0 and whether any changes will fully address the issue. Qwest should improve the process for notifying CLECs of such changes and providing documentation to them, as well as shorten the time needed to make necessary changes.


Status History

6/06/01 - CR received from Lynne Powers of Eschelon

6/06/01 - Status changed to New - to be evaluated

6/06/01 - Updated CR sent to Lynne Powers of Eschelon and Janet Houston

7/12/01 - Status changed to Cancelled - Co-Provider

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR 5263671 Detail

 
Title: Legacy CR Facilities and Processes when Qwest uses IDLC
CR Number Current Status
Date
Area Impacted Products Impacted

5263671 Completed
4/18/2001
Ordering
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

Modify Qwest’s processes to provide facilities, despite Qwest’s use of integrated pair gain (IDLC). Currently, Qwest’s IRRG states:

Unbundled Loops can only be established on copper or Universal Digital Loop Carrier (UDLC). Integrated Digital Loop Carrier (IDLC) cannot be used for an Unbundled Loop service at this time. Qwest has chosen not to unbundle IDLC because of the expense of providing equipment to "groom" the DS0 lines. During the Unbundled Loop facility assignment, an attempt will be made to Line and Station Transfer (LST) the IDLC loop to UDLC or copper. If there are no facilities available to complete the LST, the Co-Provider will be notified that the order has been placed into a held status. (Emphasis added.)

The FCC has said that "[t]he BOC must provide competitors with access to unbundled loops regardless of whether the BOC uses [IDLC] technology . . ." (BellSouth Second Louisiana 271 Order, 187 and SBC Texas 271 Order, 248.) The processes outlined in Qwest’s IRRG are not consistent with this requirement. In some cases, Qwest does not identify that IDLC is being used until the day of cut. When the discovery is made, Qwest may not dispatch a technician. Instead, Qwest delays the order or places it in held status. Qwest does so for all lines, even though facilities may be available for some of the lines. Please modify Qwest’s processes to be consistent with the FCC’s order. Also, please modify Qwest’s processes to identify earlier (before the day of cut) that IDLC is being used. If use of IDLC is not identified until the day of cut, ensure that a technician is available to resolve the issue that day (rather than delaying the order). If Qwest indicates that it does not have facilities for all lines, change Qwest’s processes so that the lines for which facilities are available may be installed (when the line configuration supports


Status History

12/01/00 New - To be validated. Date Submitted field changed from 11/29/00 to 12/01/00 to match email receipt date.

12/04/00 Status changed to New - To be reviewed. Sent Updated CR to Lynne Powers

12/06/00 Status changed to Reviewed - Under Consideration

4/18/01 - Status changed to Complete

4/23/01 - Updated CR sent to Lynne Powers, Jessica Johnson, Karen Clauson of Eschelon.

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR 5322587 Detail

 
Title: Legacy CR Process for Ordering and Use of Universal Digital Channels (UDC).
CR Number Current Status
Date
Area Impacted Products Impacted

5322587 Completed
4/18/2001
Ordering Centrex, Resale, Unbundled Loop, UNE-P
Originator: Powers, Lynne
Originator Company Name: Eschelon
Owner:
Director:
CR PM:

Description Of Change

Develop and distribute methods and procedures for ordering and use of Universal Digital Channels (UDC). Identify when loops meet the qualifications for use of UDCs and under what circumstances UDCs can be used. For example, identify when UDC is a suitable alternative for serving a customer whose order would otherwise go into held status because facilities are unavailable or the customer is currently being served using Integrated Digital Loop Carrier (IDLC). Develop and distribute methods and procedures for ensuring that the quality of service will not be adversely affected due to use of UDC and, if quality is adversely affected, restoring the customer's quality of service. If costs are associated with UDC, identify those costs and circumstances when they apply.


Status History

1/02/01 - New-To be validated

1/04/01 - Status changed to New-To be Reviewed and send to Lynne Powers and Judy Rixe

1/10/01 - Status changed to Reviewed - Under Consideration and updated CR sent to Lynne Powers and Judy Rixe

4/18/01 - Status changed to Complete as per the April CICMP Industry Forum

4/23/01 - Updated CR sent to Lynne Powers, Karen Clauson , Jessica Johnson of Eschelon

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR PC050902-1 Detail

 
Title: Offer expedites on Qwest resale DSL feature order
CR Number Current Status
Date
Area Impacted Products Impacted

PC050902-1 Completed
8/21/2002
Pre-Ordering, Ordering, Provisioning
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Schwartze, Cindy
Director:
CR PM: Thomte, Kit

Description Of Change

Currently Qwest policy does not allow a CLEC to expedite any request to add the DSL feature whether the DSL was disconnected in error by Qwest or the CLEC has a need to expedite the request due to customer needs. DSL is a specific service and not related to the dial tone itself. As a result, in some cases Eschelon customers are negativly impacted without the use of DSL even if they have dial tone. Eschelon requests that Qwest develop, train and adhere to a process to expedite the DSL feature order for Qwest resale DSL.


Status History

05/08/02 - CR Submitted by Eschelon

05/09/02 - CR acknowledged by P/P CMP Manager

05/10/02 - CR posted to Web

05/14/02 - Established Clarification meeting with Eschelon

05/15/02 - CMP Meeting: Eschelon introduced their CR.

05/20/02 - Held Clarification meeting with Eschelon.

05/24/02 - Distributed minutes from Clarification call to Eschelon

06/19/02 - June CMP Meeting: CR status changed to "Presented" Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07/10/02 - Sent Qwest Initial Response to Eschelon

07-17-02 - July CMP Meeting: CR status changed to "CLEC Test". Meeting minutes posted to this CR's Project Meetings section

08/15/02 - Sent Qwest Revised Response to Eschelon

08-21-02 - August CMP Meeting: CR status changed to "Completed" Meeting minutes posted to this CR's Project Meetings section and the CMP Web site.


Project Meetings

August CMP Monthly Meeting Minutes

Qwest (Dinwiddie) indicated that the revised response discussed in the July Product and Process CMP meeting had been provided to the CLEC community. Eschelon (Johnson) indicated that the CR could move to “Completed” status

-

07/17/02 - July CMP Meeting Minutes: Qwest (Dinwiddie) provided an overview of the CR and the initial response that had been provided to Eschelon. Qwest indicated that it does not have a process available to install Retail DSL in a shorter than standard interval. Thus, no expedited process exists for the installation new Resale DSL. However, Qwest recently reduced the interval for both Retail and Resale DSL from 10 days to 5 days. Eschelon (Johnson) indicated that shortening the interval does help and is beneficial. Also inquired if Service Managers could assist with future expedites? Qwest indicated that the Service team had provided assistance in the past and would continue to do so. Qwest (Bliss) iterated that an MCC has been produced to assist SDCs in expediting the restoration of Resale DSL service that was disconnected in error by Qwest. She also indicated that a Swat Team has been established and meets daily to review DSL issues. Eschelon (Johnson) indicated its agreement with Qwest’s approach and requested that Qwest’s initial written response be modified to reflect (a) the process improvements for the expedited reconnection of Resale DSL disconnected in error by Qwest, and (b) the intent of the Service team to remain responsive to expedited installation requests for Resale DSL. Qwest (Dinwiddie) agreed to modify the initial written response. The CR will move to "CLEC Test" and Qwest will provide the revised written response in advance of the August CMP meeting.

Time/Date: 3:00 p.m. (MDT) May 20, 2002 Place: Conference Call-In No.: 1-877 550-868 1885858 CR No.:CLEC CR 050902-1 Change Request Clarification Meeting

Attendees Attended Conference Call Name/Company: Bonnie Johnson Eschelon Senior Manager ILEC Relations Neil Houston Qwest Network Regulatory Cindy Schwartze Qwest Wholesale Process Bob Shaheen Qwest Retail DSL Product Manager Kit Thomte Qwest Wholesale CRPM Linda Miles Qwest Wholesale Process

Meeting Agenda: Offer expedites on Qwest resale DSL feature order Action 1. Introduction of Attendees CRPM introduced all attendees and reviewed the agenda 2.0 Review Requested (Description of) Change The attendees reviewed the Change Request that was submitted by Eschelon.

3.0 Confirm Areas & Products Impacted The attendees agreed that the impacted products would be DSL resale as indicated on the CR.

4.0 Confirm Right Personnel Involved The attendees also agreed that the appropriate subject matter experts were on the call.

5.0 Identify/Confirm CLEC’s Expectation On occasion a DSL Resale is disconnected in error. This could occur for various reasons, such as the DSL being associated with the wrong line on the Customer Service Record. Or the customer makes a change and for some reason Qwest can change the voice order but the system associated with the DSL order aren’t updated in time. Also when requests are submitted to Qwest if the end customer or Eschelon is wanting the service earlier than the ten day interval, no process exists within Qwest to achieve an earlier due date.

The end result for Eschelon is they receive the same answer when they attempt to expedite a due date or disconnect in error.

Eschelons objective is to have a process that will allow CLECs to have an option to expedite when either a disconnect in error occurs or when the customer requires a shorter interval.

Bob Shaheen asked for a clarification regarding moves, is this a Qwest to Eschelon move? It would be the Eschelon customer moving to a new location.

Cindy Schwartze inquired about the types of requests that might be made.. Conversion Qwest to CLEC Disconnect in error New connect

6.0 Identify any Dependent Systems Change Requests Neil indicated that the closure of the other DSL CR 022802-1 might resolve at least one aspect of this CR. Bonnie indicated that a process still would need to be available for those times when a expedite is required.

7.0 Establish Action Plan (Resolution Time Frame) Qwest is prepared to review this CR in a collaborative clarification at the June Product and Process monthly meeting.


CenturyLink Response

August 14th, 2002

Bonnie Johnson Sr. Manager, ILEC Relations Eschelon Telecom 730 Second Avenue South, Suite 1200 Minneapolis, MN 55402

SUBJECT:Qwest’s Change Request Response - CR #PC050902-1 Offer Expedites on Qwest Resale DSL Feature Order

Eschelon’s Change Request petitioned for the following: *Currently Qwest policy does not allow a CLEC to expedite any request to add the DSL feature whether the DSL was disconnected in error by Qwest or the CLEC has a need to expedite the request due to customer needs. DSL is a specific service and not related to the dial tone itself. As a result, in some cases Eschelon customers are negativly impacted without the use of DSL even if they have dial tone. Eschelon requests that Qwest develop, train and adhere to a process to expedite the DSL feature order for Qwest resale DSL. *Qwest will develop and implement an expedite process for the feature order of Qwest resale DSL.

Qwest has documented and communicated several internal process improvements around the restoral of Resold DSL service when disconnected by Qwest in error. This was communicated to impacted Qwest organizations via a Multi-Channel Communicator (MCC) dated 07/16/02, Call Handling Procedures Supporting Resale/UNE P DSL Orders, issued by Michelle Thacker. CLECs should continue to utilize the Expedites & Escalations Overview business procedures document. This document can be accessed at the following link: http://www.qwest.com/wholesale/clecs/exescover.html

Additionally, effective June 21st, 2002, Qwest significantly reduced both the Retail and Resale Qwest DSL standard provisioning interval from 10 business days to 5 business days. This improvement is outlined in announcement PROS.06.26.02.F.00487.SIGUpdateDSL dated May 31st, 2002. The archived announcement can be accessed at the following link: http://www.qwest.com/wholesale/notices/cnla/bysubcat/1,1834,16,00.html

Qwest does not have a process available to install new Retail or Resale Qwest DSL within a shorter than standard interval; however, Qwest’s Wholesale Sales and Service Organization remains available to receive escalation requests on an individual case basis.

The following references are provided for your review:

Qwest Resale General Product Catalog, Located at the following link: http://www.qwest.com/wholesale/pcat/resalegeneral.html *Qwest's retail telecommunications products and services are available for resale by Competitive Local Exchange Carriers (CLECs) to their end-users. The term 'Resale' generally refers to the 'resale' of fully finished Residential, Business, Private Line and Integrated Services Digital Network (ISDN) services. This means that Qwest provides the end-to-end service all the way to the end-user, with your brand instead of Qwest

Template SGAT/Contract Language at 6.2.3: Qwest shall provide to CLEC Telecommunications Services for resale that are at least equal in quality and in substantially the same time and manner that Qwest provides these services to itself, its subsidiaries, its affiliates, other Resellers, and Qwest's retail end users. Qwest shall also provide resold services to CLEC in accordance with the Commission's retail service quality requirements, if any.

Qwest Business Procesures Product Catalog (PCAT) Expedites & Escalations Overview, Located at the following link: http://www.qwest.com/wholesale/clecs/exescover.html * If your service request was completed within the past 72 business hours, contact Qwest's Interconnect Service Center (ISC) at 888-796-9087 for assistance; otherwise utilize your normal trouble-reporting channel into the appropriate Center for repair call handling, trouble report creation, status updates, and escalation management. *Expedites: Requests for an improved standard interval, Individual Case Basis (ICB) or committed to ICB (Ready for Service (RFS) + Interval) date Escalations: Requests for status or intervention around a missed date. *Expedites - While Qwest standard intervals, defined in our Service Interval Guide (SIG) identify reasonable intervals, at times a valid expedite situation can occur such as: * Fire * Flood * National emergency * Conditions where your end-user is completely out of service (primary line) * Disconnect in error by Qwest * Requested service necessary for your end-user's grand opening event delayed for facilities or equipment reasons with a future RFS date * Delayed orders with a future RFS date that meet any of the above described conditions. * If an expedite situation occurs, call the assigned Qwest Wholesale Center Representative responsible for processing your service requests. All expedite requests require approval to ensure resource availability. The Qwest Wholesale Center Representative will coordinate with you and Qwest internal organizations to resolve. Expedite charges may apply. If your expedite request is denied, denial reason(s) will be provided. * The PCAT indicates that expedite/escalation requests can be directed to the Wholesale LSR Service Center at 888-796-9087.

Sincerely,

Cliff Dinwiddie Sr. Manager, Product Strategy & Regulatory Support Qwest

July 10th, 2002

Bonnie Johnson Sr. Manager, ILEC Relations Eschelon Telecom 730 Second Avenue South, Suite 1200 Minneapolis, MN 55402

SUBJECT:Qwest’s Change Request Response - CR #PC050902-1 Offer Expedites on Qwest Resale DSL Feature Order

Eschelon’s Change Request petitioned for the following: *Currently Qwest policy does not allow a CLEC to expedite any request to add the DSL feature whether the DSL was disconnected in error by Qwest or the CLEC has a need to expedite the request due to customer needs. DSL is a specific service and not related to the dial tone itself. As a result, in some cases Eschelon customers are negativly impacted without the use of DSL even if they have dial tone. Eschelon requests that Qwest develop, train and adhere to a process to expedite the DSL feature order for Qwest resale DSL. *Qwest will develop and implement an expedite process for the feature order of Qwest resale DSL.

Qwest has formed a DSL Swat team that is meeting daily to investigate root causes of DSL issues raised by customers. Currently, Qwest is reviewing and trialing some improved internal escalation processes around the restoral of Resold DSL service when disconnected by Qwest in error. As we learn more, Qwest will be advising the CLECs of any changes utilizing the existing CMP processes.

Effective June 21st, 2002, Qwest significantly reduced both the Retail and Resale Qwest DSL standard provisioning interval from 10 business days to 5 business days. This improvement is outlined in announcement PROS.06.26.02.F.00487.SIGUpdateDSL dated May 31st, 2002. The archived announcement can be accessed at the following link: http://www.qwest.com/wholesale/notices/cnla/bysubcat/1,1834,16,00.html Qwest does not have a process available to install new Retail or Resale Qwest DSL within a shorter than standard interval.

The following references are provided for your review:

Qwest Resale General Product Catalog, Located at the following link: http://www.qwest.com/wholesale/pcat/resalegeneral.html

Qwest's retail telecommunications products and services are available for resale by Competitive Local Exchange Carriers (CLECs) to their end-users. The term 'Resale' generally refers to the 'resale' of fully finished Residential, Business, Private Line and Integrated Services Digital Network (ISDN) services. This means that Qwest provides the end-to-end service all the way to the end-user, with your brand instead of Qwest.

Template SGAT/Contract Language at 6.2.3: “Qwest shall provide to CLEC Telecommunications Services for resale that are at least equal in quality and in substantially the same time and manner that Qwest provides these services to itself, its subsidiaries, its affiliates, other Resellers, and Qwest's retail end users. Qwest shall also provide resold services to CLEC in accordance with the Commission's retail service quality requirements, if any.

Sincerely,

Cliff Dinwiddie Sr. Manager, Product Strategy & Regulatory Support Qwest


Open Product/Process CR PC053002-1 Detail

 
Title: Real Time Dispute of TIC, Maintenance of Service Charges and Dispatch Charges.
CR Number Current Status
Date
Area Impacted Products Impacted

PC053002-1 Denied
9/18/2002
Billing, Maintenance / Repair Centrex, Resale, UNE Loop, UNE-P
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Suellentrop, Craig
Director:
CR PM:

Description Of Change

Currently a CLEC disputes a TIC, Maintenance of Service Charge or Dispatch Charge after the charge appears on the bill. Most of the time the CLEC knows before Qwest bills the charge, whether the charge is legitemate or not. Eschelon asks Qwest to develop, document, communicate and train a process to allow CLECs to dispute miscellaneous repair charges before Qwest bills them. This process would save Qwest the time and resources needed to issue an order to bill the charges and issue the paper work to adjust the charges billed in error. This process would also save research time needed to determine whether the charge is in error or not.


Status History

05/30/02 - CR Submitted by Eschelon

05/30/02 - CR acknowledged by P/P CMP Manager

05/31/02 - CR posted to Web

06/04/02 - Contacted Eschelon and scheduled Clarification Meeting for 06/05/02.

06/05/02 - Conducted Clarification Meeting conference call with Eschelon.

06/07/02 - Issued Clarification Meeting minutes to Eschelon.

06/19/02 - CMP Meeting - Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. CR status was changed to Presented.

07/10/02 - Initial response sent to Eschelon and posted to the Web

07/17/02 - CMP Meeting - Meeting minutes posted to this CR's Project Meetings section. CR status was changed to Evaluation.

08/08/02 - Issued Mailout Notification to CLECs advising that the CR will be reviewed with other similar CRs. Notification CMPR.08.08.02.F.01312.Mtg_Proposal.

08/14/02 - Issued Qwest's Supplemental Response dated August 13, 2002 to Eschelon.

08/19/02 - Issued Mailout Notification to CLECs confirming the Synergy Meeting for Multiple Trouble Ticket and Billing CRs scheduled for 8/27/02, 2:00 pm MT. Notification CMPR.08.19.02.F.01317.CMP_CR_Mtg.

08/21/02 - CMP Meeting - Qwest presented its Supplemental Response dated August 13, 2002. This CR to be included for discussion in the CLEC conference call scheduled for 8/27. Minutes on this CR to be posted to the Project Meetings section. Status was changed to Evaluation.

8/27/02 - CR included in the Synergy Meeting for Multiple Trouble Tickets & Billing CRs. See Meeting Notes in Attach O, Sept Systems CMP Package.

09/11/02 - Issued Qwest's revised response dated September 6, 2002 to Eschelon.

09/18/02 - CMP Meeting - Qwest presented its Revised Response dated September 6, 2002. Minutes on this CR to be posted to the Project Meetings section. Eschelon indicated that since a part of the respnse was denied the CR should be status as denied. Meeting participants agreed.


Project Meetings

09/18/02 September CMP Monthly Meeting Minutes

Qwest reviewed the draft response. Qwest advised that Designed Services currently accommodate Eschelon’s request. However, the only way to accommodate Non-Designed Services is to create an MCO, and, to do that is not economically feasible due to the volume of calls received. Qwest said that the system CRs assist the dispute process for Maintenance of Service charges and TIC charges. Eschelon said that for Designed Services the Qwest technician very seldom advises if there will be a charge for the trouble ticket, unless Eschelon specifically asks if there will be a charge. Qwest will open a Global Action Item and will evaluate the situation. Eschelon indicated that since a part of the CR was denied, the CR should be status as Denied. It was agreed that the status of this CR would be Denied.

--

08/21/02 August CMP Monthly Meeting Minutes

Qwest advised that the response remained the same as last month for Designed Services. The Non Designed Services will be reviewed in conjunction with other CRs related to trouble tickets, repair charges, etc. scheduled for August 27, 2002. The CLEC participants agreed to have this CR reviewed at that meeting. It was agreed that the CR status would be changed to Evaluation.

--

07/17/02 - July CMP Meeting Minutes: Qwest presented the initial response as follows: The current repair process for Designed Services Trouble Tickets supports this request by allowing CLECs to dispute charges before they are billed. For Designed Services Qwest uses a Maintenance Control Organization (MCO) to manage trouble tickets. Qwest’s process is to hold a Designed Services Trouble Ticket for two weeks after closure before sending the charges to billing. When Qwest is discussing the resolution of Designed Services Trouble Tickets with the CLEC, the MCO technician will advise the CLEC that charges will be applied. If the CLEC disputes the resolution of the ticket, the ticket will not be closed. If a CLEC was advised during a previous Trouble Ticket that charges would be applied and that ticket has not been sent to billing, the CLEC can dispute that with the MCO technician during a subsequent Trouble Ticket. After the charges have been sent to billing, the CLEC must contact their Billing Representative to dispute any charges.

Because Qwest does not use an MCO for Non-Designed Trouble Tickets, the above process cannot be applied to these tickets. Qwest will continue to investigate alternatives that meet the needs of both Qwest and the CLECs. Qwest intends to respond to this CR regarding Non-Designed Trouble Tickets at the August CMP meeting.

Eschelon asked how Qwest will confirm the CLEC was not charged for the initial trouble ticket when a second trouble ticket for the same problem has been issued. Qwest agreed to investigate. Eschelon stated that the Qwest stated policy of having a closed trouble ticket sit at the center for two weeks prior to it being sent to billing has not been their experience. Eschelon stated they are not allowed enough time to confirm with their customer the problem has been fixed prior to trouble ticket being closed. AT&T stated they are having the same problem. Eschelon would like the opportunity to test prior to trouble ticket being closed. Eschelon asked why can’t Non-Designed Trouble Tickets remain open for 24 hours. Qwest responded there is no place to hold them. Qwest stated the response will be revised in August to address the Non-Design Trouble Ticket portion of this CR. CR status was changed to evaluation.

CLEC Change Request Clarification Meeting

June 5, 2002, 9:00 a.m. (MT) Conference Call 877-564-8688 PC053002-1, Real Time Dispute of TIC, Maintenance of Service Charges and Dispatch Charges

Attendees: Ric Martin, Qwest Alice Matthews, Qwest Craig Suellentrop, Qwest Bob Mohr, Qwest Kathy Stichter, Eschelon

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed

Review Requested (Description of) Change Kathy indicated that Eschelon was looking to be able to dispute TIC and MOS charges on a real time basis. They want a process to dispute charges they do not believe are legitimate before they get billed. She explained that she realized that repair personnel close the tickets which get forwarded to the center which in turn gets a service order issued that goes to billing. She also explained that she understood that TIC was for resale (non-design) and MOS was for Design services. She indicated that she realized that there would be two (2) processes involved and that it would be handled differently for each situation. Craig questioned how would they know if there was going to be a charge. Kathy indicated that per Eschelon’s ICA they are to be notified before the ticket is closed. She explained that CEMR provides them with an e-mail notification after a ticket is closed. Ric asked if this was the same for Design and Non-design. Kathy wasn’t sure, but Craig thought it was the same. Kathy was going to investigate. Kathy advised that Eschelon wants a dispute process before the charges are billed and believed it would be best if the process occurred before the ticket was closed. Craig indicated that for loops on the design side, they should be getting a coordinated closure and Eschelon’s Tech shouldn’t agree to close if they felt the charge wasn’t correct. Kathy advised that, for the most part, they are getting a call on design, but cannot get with the customer in a reasonable time that is within the required timeframe. Ric asked if Kathy had received the Question and Answers from the CLEC forums on Maintenance and Repair. In the May Mailout there was a dispute resolution matrix. It was agreed that the CR request was asking for more than what was on the matrix.

Confirm Areas & Products impacted It was confirmed that the products are those covered by Non-Design Services (Resale and Centrex) and Designed Services (UNEs)

Confirm Right Personnel Involved Qwest confirmed that Craig was the Lead SME for this CR. Qwest will need to bring some repair personnel into the evaluation.

Identify/Confirm CLEC’s Expectation It was confirmed that Eschelon was looking for a process to allow them to dispute charges before they get billed.

Identify any Dependent Systems Change Requests Eschelon submitted a Systems CR, SCR060402-04, which has to do with information being added to the bills. Kathy advised that per Alice’s comments at the CLEC forum, the information is not on the bills. Kathy to submit examples to Ric.

Establish Action Plan (Resolution Time Frame) Ric advised that the CR would have the CLEC Clarification at the CMP Meeting on June 19th. After the meeting Qwest will evaluate and present its response by the next CMP meeting.


CenturyLink Response

September 6, 2002

Kathleen Stichter Eschelon

SUBJECT: Qwest’s Revised Change Request Response - CR PC053002-1 “Real Time Dispute of TIC, Maintenance of Service and Dispatch Charges.”

This CR requests that Qwest develop “a process to allow CLECs to dispute miscellaneous repair charges before Qwest bills them.” During the clarification call with Eschelon and at the General Clarification at the June CMP meeting, the two repair processes (designed and non-designed) and the fact that the solution may be different for the different processes were discussed.

At the July CMP meeting Qwest responded that the current Designed Services process meets this request. Qwest uses a Maintenance Control Organization (MCO) to manage Designed Services trouble tickets. The process for Designed Services is to hold trouble tickets for two weeks after closure before sending charges to billing. When Qwest is discussing the resolution of Designed Services trouble tickets with the CLEC, the MCO technician will advise the CLEC that charges will be applied. If the CLEC disputes the resolution of the ticket, the ticket will not be closed. If a CLEC was advised during a previous trouble ticket that charges would be applied and that ticket has not been sent to billing, the CLEC can dispute that with the MCO technician during a subsequent trouble ticket. After the charges have been sent to billing, the CLEC must contact their Billing Representative to dispute any charges.

Because of the large number of Change Requests related to Maintenance and Repair a meeting was held on August 27, 2002 to discuss possible synergies between the various CRs. It was agreed at the August CMP meeting to defer the response regarding Non-Designed Services trouble tickets until after the August 27 meeting. At that meeting Eschelon agreed that the Designed Services process met their needs. It was also determined that this CR should have its own response to address the Non-Designed process. Qwest agreed to supply a revised response at the September CMP meeting. However, Qwest believes that the Systems CRs CRs SCR030702-1 – CLEC Trouble Ticket Cross Reference and SCR042902-01 – Use CLEC Internal Repair Ticket number on CLEC bill to identify maintenance and repair charges will aide CLECs in auditing their bills and address some of the CLECs underlying concerns.

Because Non-Designed trouble tickets are generally less complex and have much larger volumes, Qwest doesn’t use an MCO technician to manage their closure. For non-designed trouble tickets the technician that resolves the trouble closes the ticket. Any applicable charges are then automatically sent to billing for inclusion on the next bill. Waiting for a customer to clear voice mail and reply back to Qwest before closing a Non-Designed trouble ticket may result in increased resolution time, missed appointments, and technician idle time. It is not economically feasible for Qwest to create a new organization to manage non-designed trouble tickets, and at this time Qwest’s systems are not technically capable of holding non-designed trouble tickets before charges are sent to billing. Therefore, Qwest respectfully denies this request as it relates to the Non-Designed trouble ticket process.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Alice Matthews, Senior Process Analyst, Qwest Catherine R. Garcia, Lead Process Analyst, Qwest Don Tolman, Manager-Process Management, Qwest

--

August 13, 2002

Kathleen Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Supplemental Change Request Response - CR PC053002-1 “Real Time Dispute of TIC, Maintenance of Service and Dispatch Charges.”

This CR requests that Qwest develop “a process to allow CLECs to dispute miscellaneous repair charges before Qwest bills them.” During the clarification call with Eschelon and at the General Clarification at the June CMP meeting, the two repair processes (designed and non-designed) and the fact that the solution may be different for the different processes was discussed.

At the July CMP meeting Qwest responded that the current Designed Services process meets this request. Qwest also said that investigation of alternatives for the Non-Designed Process would continue and further information would be available at the August CMP meeting. However, because of the large number of Charge Requests related to Maintenance and Repair billing, a meeting will be scheduled for late August to discuss all of these, including this CR. Further clarification and direction for this CR will be determined after this meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest

--

July 10, 2002

Kathleen Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR PC053002-1 "Real Time Dispute of TIC, Maintenance of Service and Dispatch Charges."

This CR requests that Qwest develop "a process to allow CLECs to dispute miscellaneous repair charges before Qwest bills them." During the clarification call with Eschelon and at the General Clarification at the June CMP meeting, the two repair processes (designed and non-designed) and the fact that the solution may be different for the different processes was discussed.

The current repair process for Designed Services Trouble Tickets supports this request by allowing CLECs to dispute charges before they are billed. For Designed Services Qwest uses a Maintenance Control Organization (MCO) to manage trouble tickets. Qwest’s process is to hold a Designed Services Trouble Ticket for two weeks after closure before sending the charges to billing. When Qwest is discussing the resolution of Designed Services Trouble Tickets with the CLEC, the MCO technician will advise the CLEC that charges will be applied. If the CLEC disputes the resolution of the ticket, the ticket will not be closed. If a CLEC was advised during a previous Trouble Ticket that charges would be applied and that ticket has not been sent to billing, the CLEC can dispute that with the MCO technician during a subsequent Trouble Ticket. After the charges have been sent to billing, the CLEC must contact their Billing Representative to dispute any charges.

Because Qwest does not use an MCO for Non-Designed Trouble Tickets, the above process cannot be applied to these tickets. Qwest will continue to investigate alternatives that meet the needs of both Qwest and the CLECs. Qwest intends to respond to this CR regarding Non-Designed Trouble Tickets at the August CMP meeting.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Don Tolman, Manager-Process Management, Qwest Alice Matthews, Senior Process Analyst, Qwest


Open Product/Process CR PC053002-1X Detail

 
Title: Indicate which USOCs a CLEC is currently ordering to advise of rate changes (Crossover CR SCR053002 01)
CR Number Current Status
Date
Area Impacted Products Impacted

PC053002-1X Denied
7/18/2002
All
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Burson, Sue
Director:
CR PM: Thomte, Kit

Description Of Change

Currently when Qwest discovers an error in what it has billed a CLEC or when a rate is changing it sends a high level notification and then follows with a spreadsheet of the changes. Currently Qwest is populating the spreadsheet with all of the USOCs that a CLEC is allowed to order via its Interconnection Agreement. Eschelon wants to see somewhere on the spreadsheet which USOCs it is actually ordering. Qwest sent Eschelon a spreadsheet in February and Eschelon was currently only using 1 USOC out of over 3000 represented. The process took hours to look up each USOC to determine what Qwest was incorrectly billing and what would actually impact Eschelon's current invoices.

Expected Deliverables: Spreadsheets with rate changes should indicate which USOCs the CLEC is currently ordering. An alternative is that only USOCs that are currently or have been billed by Qwest to CLEC in the past is reflected on the rate notification rate sheet.


Status History

5/30/02 - CR Submitted by Eschelon

5/30/02 - CR acknowledged

5/31/02 - Requested Eschelon's availability for Clarification call

6/04/02 - Clarification Meeting scheduled

6/06/02 - Clarification Meeting held

6/06/02 - Status changed to clarification

6/06/02 - Cross-over CR created (Cross-over CR SCR053002-01)

6/19/02 - June CMP Meeting: CR status changed to "Presented". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

7/10/02 - Sent initial response to Eschelon

7/18/02 - July CMP Meeting: CR status changed to "Denied". Meeting minutes posted to this CR's Project Meetings section.


Project Meetings

07/17/02 - July CMP Meeting Minutes: Qwest (Kriebel) reviewed the CR initial response. Qwest has determined that providing only the specific CLEC USOC that was ordered rather than what is available to them from the contract is cost prohibitive. The CR will carry a "Denied" status.

SCR053002-01 Clarification Meeting

2:00 p.m. (MDT) /Thursday June 6,2002

877 570-8688 Conference ID 7807739 SCR053002-01 Attendees Name/Company:

Kathy Stichter - Eschelon Michael Buck - Qwest Kit Thomte - Qwest Kristen Hathway - Qwest Lynn Stecklein - Qwest

Meeting Agenda: Introduction of Attendees Introductions of the participants on the conference call were made and the purpose of the call was discussed.

Review Requested (Description of) Change Kathy reviewed the change that Eschelon is requesting as follows: Qwest sends a high level notification and then follows with a spreadsheet of the rate change. Qwest is populating the spreadsheet with all of the USOCs that a CLEC is allowed to order via interconnection. Eschelon would like to see somewhere on the spreadsheet which USOCs they are actually ordering.

Confirm Areas & Products Impacted Eschelon verfied that all Products would be impacted with this change request

Confirm Right Personnel Involved All appropriate Personnel were involved

Identify/Confirm CLEC’s Expectation Eschelon would like to see somewhere on the spreadsheet which USOCs they are actually ordering.

Identify any Dependent Systems Change Requests

Michael Buck asked why Eschelon submitted this request as a system change. He explained that a change to a spreadsheet would be considered a process change. Kathy Stichter said that she was not aware that this would be considered a process change or else Eschelon would have submitted a Process CR. Michael Buck said that this change request would be handled as a Cross-over CR and Kathy Stichter said that was not a problem.

Establish Action Plan (Resolution Time Frame) A Cross-over CR will be created on behalf of Eschelon. The CR# will be PC053002-1X.


CenturyLink Response

July 8, 2002

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR #PC053002-1X Indicate which USOCs a CLEC is currently using somewhere on the spreadsheet sent to a CLEC to advise of rate changes

Qwest provides 10-day advance CLEC notification for any corrections to rates in a CLEC's contract. The notification is provided via an excel spreadsheet that enables the manipulation of the data by the CLEC to sort against their billing records. In order to provide the most comprehensive information regarding rate corrections, Qwest notifies CLECs of changes to any rates in their contract. This is due the fact that all contracted rates are loaded in the billing system and can be ordered at any time.

Providing only the specific CLEC USOCs that have been ordered would be cost prohibitive and could prevent Qwest from correcting rates in the billing system in a timely manner. Providing this additional information on the rate correction CLEC notification would require approximately 60 additional Qwest resources for the CLEC notification process to be completed in a timely manner.

Future rate validation efforts will result in a lesser number and size of notifications than CLEC’s may have received to this point, and thus will be smaller in size of impact to CLEC’s regarding comparing the data to their billing records.

Denied – Economically not feasible – low demand, cost prohibitive to implement the request, or both.

Sincerely,

Susan Burson Director Process Management Qwest

Cc: Christie Doherty, Judy Taylor, Toni Dubuque, Joan Masztaler


Open Product/Process CR PC053002-2X Detail

 
Title: Supply current rate, new rate and effective date when issuing rate changes (Cross over CR SCR053002 02)
CR Number Current Status
Date
Area Impacted Products Impacted

PC053002-2X Denied
7/18/2002
All
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Burson, Sue
Director:
CR PM: Thomte, Kit

Description Of Change

Currently when Qwest discovers an error in what it has billed a CLEC or changes a rate it sends a high level notification and then follows with a spreadsheet of the changes. Currently Qwest is populating the spreadsheet with 1minus discount, ending with a percentage or Qwest will provide a tariffed rate rather than the rate less the discount percent that shows up on the invoice. Eschelon asks Qwest to supply the actual incorrect rate (money amount) and the actual correct rate (money amount). Example, if Eschelon is billed $10.00 for a line and the $10.00 is the rate that shows on the bill, and that rate changes to $9.00, then on the notification, Eschelon should see $10.00 as existing rate and $9.00 as new rate. Also, the effective date of the corrected rate should be when the rate was first billed incorrectly. It should not be an effective date made up by Qwest.

Expected Deliverables: Spreadsheets with rate changes should show the actual rate (money amount) being billed incorrectly and not the percentage or tariffed rate. Spreadsheet should show the correct rate that will be billed going forward (money amount). Effective dates should be date when rate was first billed incorrectly.


Status History

5/30/02 - CR Submitted

5/30/02 - CR Acknowledged

5/31/02 - Requested Eschelon's availability for clarification call

6/04/02 - Clarification Meeting Scheduled

6/06/02 - Clarification Meeting Held

6/06/02 - Status changed to clarification

6/06/02 - Cross-over CR created (SCR053002-02)

6/19/02 - June CMP Meeting: CR status changed to "Presented". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

07/10/02 - Sent Eschelon initial response

07/17/02 - July CMP Meeting: CR status changed to "Denied". Meeting minutes posted to this CR's Project Meetings section.


Project Meetings

07/17/02 - July CMP Meeting Minutes: Qwest (Kriebel) reviewed the response. Qwest has determined that providing the specific rate as opposed to the percentage as it appears in the contract is economically not feasible. Eschelon (Stichter) questioned why so many of the notifications carried the date of November 1. She also asked if the notification carried the date that the change will occur. This CR will carry a "Denied" status.

SCR053002-02 Clarification Meeting

2:00 p.m. (MDT) /Thursday June 6,2002

877 570-8688 Conference ID 7807739

Attendees Name/Company:

Kathy Stichter - Eschelon Michael Buck - Qwest Kit Thomte - Qwest Kristen Hathway Qwest Lynn Stecklein - Qwest

Meeting Agenda: Introduction of Attendees Introductions of the participants on the conference call were made and the purpose of the call was discussed.

Review Requested (Description of) Change Kathy Stichter reviewed the change that Eschelon is requesting as follows: When Qwest discovers an error in what they have billed, they populate the spreadsheet with a discount instead of the actual incorrect rate and correct rate. She also said that the effective date is a random date.

Confirm Areas & Products Impacted This request applies to all products.

Confirm Right Personnel Involved All appropriate personnel are involved in this change request.

Identify/Confirm CLEC’s Expectation Eschelon would like the spreadsheets to reflect the actual rate being billed incorrectly and not the percentage or tariffed rate. Kathy Stichter also said the Eschelon would like the date to reflect the actual effective date, not just any date.

Identify any Dependent Systems Change Requests Michael Buck asked why Eschelon submitted this request as a system change. He explained that a change to a spreadsheet would be considered a process change. Kathy Stichter said that she was not aware that this would be considered a process change or else Eschelon would have submitted a Process CR. Michael Buck said that this change request would be handled as a Cross-over CR and Kathy Stichter said that was not a problem.

Establish Action Plan (Resolution Time Frame) A Cross-over CR will be created (PC053002-2X)


CenturyLink Response

July 8, 2002

Kathy Stichter ILEC Relations Manager Eschelon

SUBJECT: Qwest’s Change Request Response - CR #PC053002-2X Supply current rate and new rate when issuing changes sent to CLECs via spreadsheet. Effective date of correction should go back to when the rate was first billed incorrectly, not an arbitrary date chosen by Qwest as to when the rate is effective.

When Qwest provides CLEC notification for any corrections to a CLEC's billing rates, Qwest provides the current and corrected rate in the manner that it appears in the contract. For UNE rates, facility based OS/DA usage rates and unbundled switching rates, the dollar amount is what is provided in the CLEC contract. So Qwest provides the dollar amount for the current rate and the corrected rate. For Resale (USOC and usage rates) and toll usage rates, the percent discount is the rate provided in the CLEC contract. So for Resale (USOC and usage) and toll usage rate corrections, Qwest provides the percent of Resale (1 minus the Resale percent discount). The CLEC can refer to the Retail Tariff (http://tariffs.uswest.com:8000/) to obtain the actual dollar amount against which the percent discount is applied.

Providing the actual resale (USOC and usage) and toll usage money amounts would be cost prohibitive and could prevent Qwest from correcting rates in the billing system in a timely manner. Providing this additional information on the rate correction CLEC notification would require approximately 50 additional Qwest resources for the CLEC notification process to be completed in a timely manner.

Future rate validation efforts will result in a lesser number and size of notifications than CLEC’s may have received to this point, and thus will be smaller in size of impact to CLEC’s regarding comparing the data to their billing records.

The effective date is provided on all CLEC rate correction notifications. The effective date is generally when the rate was first billed incorrectly (e.g. the contract or cost docket effective date).

If the CLEC has any specific questions regarding a CLEC notification for a rate correction (including the effective date for the rate correction), the CLEC can contact their Qwest Billing Representative.

Partially Denied - Economically not feasible – low demand, cost prohibitive to implement the request, or both.

Sincerely,

Susan Burson Director Process Management Qwest

Cc: Christie Doherty, Judy Taylor, Toni Dubuque, Joan Masztaler


Open Product/Process CR PC063005-2 Detail

 
Title: Expand the option of requesting that the service at the old address not be disconnected until the service at the new address is working to include Centrex Plus and Centron Products.
CR Number Current Status
Date
Area Impacted Products Impacted

PC063005-2 Completed
1/18/2006
Ordering & Provisioning Resale, UNE-P, Centrex Plus, Centron
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Wells, Susie
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Currently, when an end user customer, on a Centrex common block, requests a move there is no process that ensures the end user customer’s service at their old address remains working until the service at the new address is installed. This can lead to unnecessary service interruptions for the end user customer. Qwest has a current process for POTS and Centrex 21 outlined in the Ordering Overview, which allows the CLEC the option of requesting that the service at the old address not be disconnected until the service at the new address is working. Eschelon has had recent discussions with our Service Management team regarding expanding the current process to include Centrex Plus and Centron products. Eschelon’s Service Manager communicated that the addition of Centrex Plus and Centron to the current POTS and Centrex 21 optional move process is feasible. Eschelon is requesting that Qwest add Centrex Plus and Centron products to the current move process which allows the CLEC the option of requesting the old address not be disconnected until the service at the new address is working.

Expected Deliverable:

Make the current POTS and Centrex 21 option to request the old address not be disconnected until the service at the new address is working applicable to Centrex Plus and Centron products.


Status History

06/30/2005 - CR Submitted

07/01/2005 - CR Acknowledged

07/05/2005 - Clarification Call Scheduled for July 11, 2005

07/11/2005 - Clarification Call Held

08/17/2005 - Discussed in the Monthly Product Process CMP Meeting

09/21/2005 - Discussed in the Monthly Product Process CMP Meeting

10/19/2005 - Discussed in the Monthly Product Process CMP Meeting

10/20/2005 - PROS.10.20.05.F.03395.OutsideMoveCTX (Level 3)

11/16/2005 - Discussed in the Monthly Product Process CMP Meeting

11/18/2005 - PROS.11.18.05.F.03472.FNLOutsideMoveCTX (Level 3 Final)

12/05/2005 - Status Changed to CLEC Test Due to Implementation on December 5, 2005

12/14/2005 - Discussed in the Monthly Product Process CMP Meeting

01/18/2006 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

January 18, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this CR was implemented on December 5th and asked for closure. Kim Isaacs-Eschelon stated that the CR could be closed.

- December 14, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this change was effective on December 5th and asked Eschelon if they have had the opportunity to test the change. Kim Isaacs/Eschelon asked that the CR remain in CLEC Test for testing.

- November 16, 2005 Monthly Product Process CMP Meeting Discussion: Peggy Esquibel-Reed/Qwest stated that the notice was sent on October 20th with a proposed effective date of December 5th. Peggy then noted that this CR would be placed in CLEC Test on 12/5/2005. Stephanie Prull/Eschelon asked if there is an associated Systems CR for the FDT changes. Jill Martain/Qwest stated that there is no Systems CR and stated that one could be opened if Stephanie felt that one was needed. Stephanie Prull/Eschelon stated that it should be consistent and may submit a Systems CR. Bonnie Johnson/Eschelon asked if there was a manual process in place that works. Jill Martain/Qwest stated that there will be with the implementation of this CR. Kim Isaacs/Eschelon stated that the Notice says that you must add FDT XX information in the Remarks section of the LSR form and mark for manual handling. Peggy Esquibel-Reed/Qwest noted that the Qwest Response, presented in the September CMP Meeting, says that portions of the criteria that will be required for POTs and CTX 21 service will be used for the manual Centrex Plus/Centron move orders, due to the implementation of an IMA 18.0 Systems CR SCR040204-03 (IMA to Allow Frame Due Time of XX). The TOS must equal 1 or 3, the DDDO and DDD must be the same day, the telephone number at both the old address and new address must be the same, FDT XX is only applicable on non designed business customers, FDT XX only applicable when ACT = C and LNA = T (existing Centrex Plus/Centron outside move process), and in addition, the FDT XX must be in the remarks of the LSR. FDT XX is not allowed by IMA in the DFDT field for this product type. Susie Wells/Qwest asked if there were additional questions. Susie stated that Centrex and Centron are manual anyway and will add this process based on Remarks. Susie noted that the same criteria is being used as the process for POTS. Stephanie Prull/Eschelon thanked Qwest for the information and stated that she would think about the need for a Systems CR. This CR remains in Development Status.

October 19, 2005 Monthly Product Process CMP Meeting Discussion: Peggy Esquibel-Reed/Qwest stated that the notice would be going out soon and that Qwest was looking at a December timeframe for implementation. Peggy then stated that the CR remained in Development Status.

- September 21, 2005 Monthly Product Process CMP Meeting Discussion: Susie Wells/Qwest stated that Qwest accepts this CR and stated that portions of the criteria that will be required for POTs and CTX 21 service will be used for the manual Centrex Plus/Centron move orders, due to the implementation of an IMA 18.0 Systems CR SCR040204-03 (IMA to Allow Frame Due Time of XX). Susie noted that the TOS must equal 1 or 3, DDDO and DDD must be the same day, the telephone number at both the old address and new address must be the same, and FDT XX is only applicable on non designed business customers. Susie then noted that new for this CR is that the FDT XX only applicable when ACT = C and LNA = T (existing Centrex Plus/Centron outside move process), the FDT XX must be in the remarks of the LSR, and the FDT XX is not allowed by IMA in the DFDT field for this product type. Susie stated that the Ordering Overview PCAT would be updated and will follow normal timeline. Susie stated that a status would be provided at the October Product Process CMP meeting. There were no questions or comments. Jill Martain/Qwest stated that this CR moves into Development status.

- August 17, 2005 Monthly Product Process CMP Meeting discussion: Kim Isaacs-Eschelon presented the CR and stated that there is a current process for POTS and Centrex 21 and she would like it expanded. Bonnie Johnson-Eschelon stated that she would like to note that Eschelon worked through their Service Manager in order to determine feasibility and their Service Manager said that it was feasible. Jill Martain-Qwest stated that CR moves to presented status.

- July 11, 2005 Clarification Call Attendees: Kim Isaacs-Eschelon, Susie Wells-Qwest, Janean Van Dusen-Qwest, Jim Recker-Qwest, Peggy Esquibel Reed - Qwest

Review Description of Change Peggy Esquibel Reed-Qwest stated that Eschelon is requesting that Qwest Expand the option of requesting that the service at the old address not be disconnected until the service at the new address is working to include Centrex Plus and Centron Products.

Discussion: Kim Isaacs-Eschelon stated that they contacted their Service Managers (Jean and Josh) because they had customer’s who had lost their service. Kim said that they sent examples to their service managers and that this situation could result in escalations.

Susie Wells-Qwest asked if Eschelon wanted the same process that exists today on 1FR/Centrex 21 T/F orders and that the due date on the orders would be on the same day.

Kim Isaacs-Eschelon said yes.

Jim Recker-Qwest asked if this would only be on T/F orders.

Kim Isaacs-Eschelon said yes and that the due date would be on the same date if the customer is moving off a Centrex Common Block. Kim asked if this would be done on a T/F or D/N (i.e. if the were moving from a Common Block to a different product).

Susie Wells-Qwest said that the type of order would be a C and N order. She said that a move order on Centrex Plus/Centron is actually a change order. Susie said that 1 order is necessary in the Central Region and 2 orders in the Western and Eastern Regions. She said that if there is a move and is changing from one product to another product; this would be a different process.

Kim Isaacs-Eschelon asked if Qwest would consider those types of moves.

Susie Wells-Qwest said that when the customer changes products, they may experience some type of service outage.

Kim Isaacs-Eschelon said that she understood and that she wanted to avoid the N order being jeop’d.

Susie Wells-Qwest asked if Eschelon’s concern was if the order was jeop’d at the new address and if this request was to stop the jeop, or if this request was because the customer didn’t want their service disconnected until the new service was installed.

Kim Isaacs-Eschelon said that it is both and that they are marking for manual with the ACT = T with the same conditions: Business only, no change in TNs and the same due date.

There were no additional questions or comments.

Confirm Areas and Products Impacted Peggy Esquibel Reed-Qwest confirmed that the areas impacted are Ordering and Provisioning and the products impacted are Resale, UNE-P, Centrex Plus and Centron

Establish Action Plan Peggy Esquibel- Reed-Qwest said that Eschelon will present this CR in the August 17, 2005 CMP Meeting and that the Qwest Response was due in September.


CenturyLink Response

September 13, 2005

RESPONSE For Review by the CLEC Community and Discussion at the September 21, 2005 CMP Product/Process Meeting

TO: Bonnie Johnson Eschelon

SUBJECT: PC063005-2 Expand the option of requesting that the service at the old address not be disconnected until the service at the new address is working to include Centrex Plus and Centron Products.

This is in response to the Eschelon’s submitted CMP CR PC063005-2. This CR requests that the Centrex Plus and Centron products be added to the existing POTS and Centrex 21 option, to request the old address not be disconnected until the service at the new address is working.

A clarification call was held on July 11, 2005 for discussion of this request, and this CR was presented at the July 20, 2005 Product Process CMP Meeting.

Qwest accepts this CR. Centrex Plus and Centron move requests are a manual process. Qwest will add the FDT XX option to request the old address not be disconnected until the service at the new address is working as part of the manual process that is currently in place.

Portions of the criteria that will be required for POTs and CTX 21 service will be used for the manual Centrex Plus/Centron move orders, due to the implementation of an IMA 18.0 Systems CR SCR040204-03 (IMA to Allow Frame Due Time of XX): - TOS must equal 1 or 3 - DDDO and DDD must be the same day - Telephone number at both the old address and new address must be the same - FDT XX is only applicable on non designed business customers - FDT XX only applicable when ACT = C and LNA = T (existing Centrex Plus/Centron outside move process) - In addition, the FDT XX must be in the remarks of the LSR. - FDT XX is not allowed by IMA in the DFDT field for this product type

Updates to the Ordering Overview PCAT will be made and will follow the normal implementation timeline for this Product Process Change Request.

Qwest will provide a status update of the work to implement this CR at the October Product Process CMP meeting.

Sincerely, Qwest


Open Product/Process CR PC062906-1 Detail

 
Title: Ability to Request Dual Service on Partial Moves
CR Number Current Status
Date
Area Impacted Products Impacted

PC062906-1 Completed
10/18/2006
Order - LSR Resale - POTS, UNE-P POTS/Centrex 21
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Coyne, Mark
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest should allow dual service on partial move requests. Eschelon is requesting the ability to request Dual Service for partial move requests because Eschelon has several customers that request this option.. Currently CLECs have to find an alternate solution to accommodate the customer’s needs. The alternative solutions are generally complicated, leave room for error and down time, and often don’t fully meet customer’s needs.

Several End User customers need and request Dual Service with partial moves for a number of reasons. For example, a small business end user customer is moving just one department to a new location and it is necessary during this transition period that calls ring into both the new and old location

Expected Deliverables:

Eschelon is requesting the ability to request Dual Service for partial move requests.


Status History

6/29/06 - CR submitterd

6/29/06 - CR acknowledged

7/13/06 - Clarification Meeting Held

7/13/06 - Status changed to Clarification

7/19/06 - Status changed to Presented

7/19/06 - Discussed in the July Product/Process CMP Meeting

8/16/06 - Discussed in the AugustProduct/Process CMP Meeting

8/16/06 - Status changed to Development

8/25/06 - PROD.08.25.06.F.04148.Dual_Service_V4

9/14/06 - PROD.09.14.06.F.04169.Dual_Service_V5

9/19/06 - Status changed to CLEC Test

9/20/06 - Discussed in the September Product/Process CMP Meeting - See Attachment D in the Distribution Package

10/18/06 - Discussed in the October Product/Process CMP Meeting - See Attachment D in the Distribution Package

10/18/06 - Status changed to Completed


Project Meetings

10/18/06 Product/Process CMP Meeting

Susan Lorence-Qwest stated that this CR was implemented on 9/15/06 and asked if everyone was ok to close. There was no objection to closure.

9/20/06 Product/Process CMP Meeting

Mark Coyne - Qwest stated that this request was noticed on August 25th and became effective on September 15th. He said that the status will change to CLEC Test.

8/16/06 Product/Process CMP Meeting

Mark Coyne-Qwest stated that this CR was presented in the July Product/Process CMP Meeting. Becky Ferrington-Qwest stated that Qwest’s recommendation for this request is in line with discussion that took place with Eschelon in the clarification meeting. Becky reviewed the following proposed change for Partial Moves: This restriction is specific to requesting Dual Service and a Partial Move on the same LSR. However, if the end-user has multiple lines and wants to move only one of the lines with Dual Service, you can achieve this via 2-LSRs. First, request a deconsolidation LSR (ACT = N, Manual Indicator = Y, remarks describing the TN/s that you want to establish on a separate account) for the old location. Subsequently, submit a second LSR to do a full move of the account to the new address and establish the Dual Service. You can submit both LSRs at the same time, if you use a related purchase order number (RPON) on both and drop each for manual handling. The 2-LSR process described above is exclusive to simple deconsolidation and full move with dual service. Any other change activity (such as adding or removing features) associated to these requests should be made only on the Move request and will default to the intervals described in the Service Interval Guide (SIG) Kim Isaacs-Eschelon stated that this recommendation sounded good. Mark Coyne-Qwest stated that this CR will move to development.

7/19/06 Product/Process CMP Meeting

Kim Isaacs-Eschelon presented this change request. She said that Qwest should allow dual service on partial move requests. Eschelon is requesting the ability to request Dual Service for partial move requests. She said that the clarification call was held last week and that Qwest is looking at documenting a 2 LSR process.

Mark Coyne - Qwest stated that this CR will move to a presented status and that we will provide a response in the August CMP Meeting.

July 13, 2006 Clarification Meeting Introduction of Attendees: Kim Isaacs-Eschelon, Steph Prull-Eschelon, Becky Ferrington-Qwest, Joanne Ragge-Qwest, Carol McKenzie-Qwest, Anders Ingemarson-Qwest, Denise Martinez-Qwest, Lee Gomez-Qwest, Anne Robberson-Qwest, Chuck Anderson-Qwest, Lynn Stecklein-Qwest, Mark Coyne-Qwest, Sandy McGee-Qwest, Shirley Tallman-Qwest, Peggy Esquibel Reed-Qwest

Review Requested (Description of) Change: Lynn Stecklein-Qwest Reviewed the CRs description and asked Eschelon if they had additional information to share regarding this request. Kim Isaacs-Eschelon stated that this request was submitted because the end user customer is looking for a solution and to eliminate confusion. Becky Ferrington-Qwest stated that we generally don't allow for a partial move on the retail side. Becky said that we may have a solution that would involve using the existing process and revising the process that would require 2 LSRs instead of 4 LSRs. Kim Isaacs-Eschelon said that the this process may be a viable solution. Steph Prull-Qwest stated that this CR was issued as a Produc/Process and that the 2 LSR process eliminates the potential for system impacts. Becky Ferrington-Qwest stated that she would verify timing issues and LSR order types There were no additional comments or questions.

Establish Action Plan & Resolution Time Frame: Lynn Stecklein-Qwest stated that this CR is due for presentation at the July 19, 2006 Product/Process CMP Meeting, Qwest would internally review the request, and that Qwest would provide the response to the CR by August 16, 2006.


Open Product/Process CR PC080204-1 Detail

 
Title: Escalation Code and sub code, including examples, documented on Qwest’s Wholesale web site
CR Number Current Status
Date
Area Impacted Products Impacted

PC080204-1 Completed
4/20/2005
Pre Order Ordering Provisioning Escalation process
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Thacker, Michelle
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest will publish its escalation code and sub codes with examples of when Qwest uses the codes. When a CLEC opens an escalation ticket with Qwest for any reason, Qwest said it would provide the escalation close out code and sub code to the CLEC at the CLEC’s request. However, the CLEC cannot verify if it agrees with the code and sub code Qwest used to close the escalation ticket, because Qwest does publish an exhaustive list of its escalation close out code and sub codes. Eschelon may choose to escalate the code and sub code Qwest used to close the ticket, but is unable to so because the CLEC does not have the codes and sub codes that are available when Qwest closes a CLEC ticket. Qwest should also include examples of when Qwest uses a particular code and sub code while closing a CLEC escalation ticket.

Expected Deliverable: Qwest will publish the available escalation codes and sub codes Qwest uses when closing out a CLEC escalation ticket. Qwest will include examples of when specific codes are used.


Status History

8/2/04 - CR submitted

8/2/04 - CR acknowledged

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/20/04 - October CMP Meeting minutes will be posted to the project meeting section

11/17/04 - November CMP Meeting minutes will be posted to the database

12/13/04 - Sent out escalation product code document and scheduled adhoc meeting for Jan 5

12/14/04 - Rescheduled ad hoc meeting per Eschelon's request for Jan 6

12/15/04 - December meeting minutes will be posted to the database

1/6/05 - Ad hoc meeting held

1/19/05 Discussed in the January Product/Process Meeting - See attachment C in the Distribution Package

2/3/05 - Communicator Issued PROS.02.03.05.F.02494.OrderingV65, Expedites and Escalations Overview V18

2/16/05 Discussed in theFebruary Product/Process Meeting - See attachment C in the Distribution Package

2/3/05 - PROS.02.03.05.F.02494.OrderingV65_ExpediteV18

3/16/05 - Status changed to CLEC Test

3/16/05 - Discussed in the March Product/Process CMP Meeting - See Attachment C - Product/Process Distribution Package.

4/20/05 - Discussed in the April Product/Process CMP Meeting - See Attachment C - Product/Process Distribution Package

4/20/05 - Status changed to completed.


Project Meetings

4/20/05 Product/Process CMP Meeting Discussion

Jill Martain - Qwest stated that this request was effective on 2/24/05 and that this CR will be closed.

3/16/05 Product/Process CMP Meeting Discussion

Michelle Thacker - Qwest stated that this request was effective on February 24th. She said that this will move to CLEC Test with the expectation of closing in April 2/16/05 Product/Process CMP Meeting

Michelle Thacker - Qwest stated that the targeted implementation is February 24, 2005.

Jill Martain - Qwest stated that this CR will remain in a Development Status.

1/19/05 Product/Process CMP Meeting

Michelle Thacker/Qwest stated that an adhoc meeting was held January 6, 2005 to review the product reason codes. Michelle stated that the notification will go out the 1st week of February and will be published the 3rd week of February. Michelle stated that it will be published in the ordering overview. Bonnie Johnson/Eschelon thanked Qwest for considering publishing in the Escalation/Expedite PCAT because that is where people would look for it. Michelle Thacker/Qwest said that there will be a link and that there will be a pull down menu in ordering overview.

PC080204-1 Escalation Product Reason Codes Ad Hoc Meeting January 17, 2005

Cox Communications requested that Qwest schedule an adhoc meeting to discuss the Product Reason codes that were reviewed with the CLEC Community on January 6, 2005. Cox indicated that they did not receive the notification on the date change of the original meeting. Cindy Harlan reviewed what was discussed in the adhoc meeting held on January 6. Cox asked where they could locate this information. Cindy advised that this information will be sent via a level 4 notifcation upon completion. Chuck Ploughman stated that Cox could request to receive notifications directly. Cox said that they would look into receiving the notifications directly. There were no other questions.

January 6, 2005

In attendance: Gary Price – DSET Kim Isaacs – Eschelon Sharon Van Meter – ATT Michelle Thacker – Qwest Amanda Silva – VCI Bonnie Johnson – Eschelon Cindy Harlan – Qwest

Cindy Harlan – Qwest advised the purpose of the call is to review the Product Reason code document that was distributed.

Michelle Thacker – Qwest explained the Product Reason codes are used to categorize escalation calls to the Wholesale Center.

Bonnie Johnson – Eschelon asked if this is an exhaustive list. Michelle advised it is not a total list. Exceptions are codes that are used for a 30 day period to identify a specific or limited condition and codes for pay phone products, or control cards. Bonnie reviewed the list and asked Michelle to explain the Typing error code. Is this used when the LSR is accurate but something was omitted? Michelle agreed. Kim Isaacs- Eschelon asked about the Jep after FOC code and what happens if the Jep was in error? Michelle advised the centers assign these codes based on the information that they have at the time of the call. Qwest is not trying to focus on whose fault the issue is. Qwest is trying to resolve the issue and the center is just capturing data about the call. The focus is on addressing the issue, not updating the data. Bonnie advised more detail helps with a training issue of SDCs. Michelle advised the SDC decides how a ticket is coded based on the resolution of that ticket. They can not spend a lot of time on recording the data.

Michelle advised the document will be a pull down list in the PCAT. Discussion took place regarding locating the document in the Ordering Overview or the Escalations section. This document will be released with a Level 4 Notification.

Sharon Van Meter – ATT asked if this was for all products, except payphones. Michelle advised yes.

Bonnie asked if we could name the middle column to state ‘examples of this product reason code’. Michelle agreed.

Cindy recapped next steps are to complete the document updates and get these ready to be released via Level 4 Notification. Status will be provided at the next CMP meeting.

December CMP Meeting Minutes Cindy Macy – Qwest advised an ad hoc meeting is scheduled for January 6 to review the product sub codes. The product subcodes document was sent out for review with the meeting notification. This CR will remain in Development Status.

11/17/04 November meeting minutes Cindy Macy – Qwest advised that this process in under development and the PCAT should be available in the next few weeks. This CR will remain in Development Status.

10/20/04 CMP Meeting Minutes Michelle Thacker, Qwest explained that a draft will be available in mid November for review and that she would like to move the CR to development status. Bonnie Johnson, Eschelon wanted to ensure that the list of codes would be exhaustive while the examples may not be. Michelle said the temporary codes to collect data will not be included in the list. Michelle used the example of when BOSS was down in February there was a temporary code created in addition to the three regular codes for this area. The temporary code was for “impact from Boss being down”. There was discussion around this issue. It was determined that when the center is called the temporary code could be given to the CLEC and that Michelle will explain and give examples of the temporary codes in the documentation. The CR will move to development.

- 09/16/04 CMP September Meeting Michelle Thacker reported that Qwest will accept the CR and will post codes to the Wholesale web but not as part of the PCAT. Bonnie asked if the web would cover both codes and sub-codes. Michelle said yes and will also contain brief descriptions of each code. The CR will move to Development Status.

-- 08/18/04 CMP Meeting Bonnie Johnson presented the CR saying that Qwest and Eschelon did have a Clarification call, and that Eschelon is asking Qwest to provide on the Wholesale web site the codes and sub codes used in closing escalations. The problem is that while Qwest knows the codes meaning, Eschelon does not. (Comment begin) Bonnie said Eschelon wants to validate the codes Qwest uses when closing out a ticket and cannot do so because Eschelon does not know the list of codes (end comment). This CR will be moved to Presented status.

-- 11:00 a.m. (MDT) / Thursday August 12, 2004 1-877-521-8688 1456160# PCPC080204-1 Escalation Code and sub code, including examples, documented on Qwest’s Wholesale web site Attendees Attended Conference Call Name/Company: Bonnie Johnson, Eshcelon Stephanie Prull, Eschelon Kim Isaacs, Eschelon Doug Andreen, Qwest Michelle Thacker, Qwest Jim Rucker, Qwest Title:

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change Doug read the title of the CR which is Escalation Code and sub code, including examples, documented on Qwest’s Wholesale web site”. The reading of the description was waived since everyone on the call has a good understanding of what is requested. Eschelon’s expectation is that Qwest will publish the available escalation codes and sub codes Qwest uses when closing out a CLEC escalation ticket. Qwest will include examples of when specific codes are used. Michelle said in past meetings she believed these codes were referred to as ‘Close codes Bonnie said yes and added that Eschelon is not asking for an exhaustive list but rather a definition of a category or a code. For example, XX is the code for when the telephone number is wrong. Like closing codes on service orders. Michelle said for example if Qwest didn’t type the telephone number correctly, or on an out of service, would want the codes associated. Bonnie said yes, though out of service is pretty self explanatory. Bonnie also suggested that if a list was sent to Eschelon that they could indicate the ones that are not clearly understood. Bonnie said she would leave it to Michelle on how to work it. There were no further questions or comments. 3.0 Confirm Areas & Products Impacted Areas impacted are Pre-Ordering, Ordering, Provisioning, and the Escalation process. 4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting. 5.0 Identify/Confirm CLEC’s Expectation Eschelon’s expectation is that Qwest will publish the available escalation codes and sub codes Qwest uses when closing out a CLEC escalation ticket. Qwest will include examples of when specific codes are used. 6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) Eschelon will present the CR at the August CMP Meeting. A response from Qwest will be given at the September meeting.


CenturyLink Response

October 12, 2004

For Review by CLEC Community and Discussion at the October 2004 CMP Meeting

Bonnie Johnson Director Carrier Relations Eschelon Telecom

SUBJECT: Qwest’s Change Request Response PC080204-1 Escalation Code and sub code, including examples, documented on Qwest’s Wholesale web site

This letter is a revised response to Eschelon’s Change Request (CR) PC080204-1. This CR requests that Qwest provide escalation codes and sub codes, including examples, on the Qwest Wholesale web site.

In the original response Qwest accepted the request and indicated that the information would be located outside of the Product Catalogue. After a review of the best location to place the information it was determined that the most appropriate location is a downloadable file in the Ordering Overview section of the PCAT. As agreed in the Clarification call, this will not be a totally exhaustive list but rather cover the codes, sub-codes and descriptions that are frequently used. The list will be updated as needed by Qwest.

As indicated in the original response, Escalations will continue to follow the existing process as currently documented in “Expedites and Escalations”.

Qwest will provide a status update at the November CMP Meeting.

Sincerely,

Michelle Thacker Process Manager - Qwest

-- September 13, 2004

For Review by CLEC Community and Discussion at the September 2004 CMP Meeting

Bonnie Johnson Director Carrier Relations Eschelon Telecom

SUBJECT: Qwest’s Change Request Response PC080204-1 Escalation Code and sub code, including examples, documented on Qwest’s Wholesale web site

This letter is in response to Eschelon’s Change Request (CR) PC080204-1. This CR requests that Qwest provide escalation codes and sub codes, including examples, on the Qwest Wholesale web site.

Qwest accepts this request and will move forward to place codes, sub codes and explanations on the Qwest Wholesale web site. The information will be located outside of the Product Catalogue and will be updated on an as needed basis.

Escalations will continue to follow the existing process as currently documented in Expedites and Escalations.

Qwest will provide a status update at the October CMP Meeting.

Sincerely,

Michelle Thacker Process Manager - Qwest


Open Product/Process CR PC100104-1 Detail

 
Title: Track and Archive External Documentation Requests
CR Number Current Status
Date
Area Impacted Products Impacted

PC100104-1 Completed
7/20/2005
Other: External Documentation Request Process
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Cole, Jaqueline
Director:
CR PM: Stecklein, Lynn

Description Of Change

Eschelon requests that External Documentation Requests be tracked and archived on the Qwest Wholesale web site. Currently External Documentation Requests are tracked and archived internally at Qwest. Eschelon believes having this information available on the Qwest Wholesale website would be valuable to the CLECs and Qwest. Having the External Documentation Requests tracked and archived on the Qwest Wholesale web site would decrease duplicate requests and decrease unnecessary calls and emails to the documentation team regarding the status of external documentation requests.

Expected Deliverable: Track and Archive External Documentation Requests on the Qwest Wholesale Website.


Status History

10/1/04 - CR Submitted

10/4/04 - CR Acknowledged

10/13/04 - Clarification call held

11/17/04 - November CMP Meeting minutes will be posted to the database

12/15/04 - December meeting minutes will be posted to the database

1/19/05 - Discussed in the January Product/Process CMP Meeting

2/16/05 - Discussed in the February Product/Process CMP Meeting

3/16/05 - Discussed in the MarchProduct/Process CMP Meeting

4/20/05 - Discussed in the April Product/Process CMP Meeting

5/9/05 - PROS.05.09.05.F.02890.CLEC_ExDocReq_Process

5/18/05 - Discussed in the May Product/Process CMP Meeting

6/8/05 - PROS.0608.05.F.02999.FNL_CLEC_ExDocReq_Process - Proposed changes will become operational 6/23/05

6/15/05 - Discussed in the June Product/Process CMP Meeting

7/20/05 - Discussed in the July Product/Process CMP Meeting

7/20/05 - Status changed to Completed


Project Meetings

7/20/05 Product/Process CMP Meeting

Jill Martain - Qwest stated that this CR was effective on June 23rd and asked if this CR could be closed.

Kim Isaacs - Eschelon said that Eschelon was ok to close and that this request has met their needs.

6/15/05 Product/Process CMP Meeting

Jill Martain - Qwest stated that this request will become effective on June 23, 2005 and will remain in Development.

5/18/05 Product/Process CMP Meeting

Jackie Cole - Qwest stated that a notification was sent on 5/9/05 and that the CLEC comment cycle ends 5/24/05. She said that this request will be effective on 6/23/05. This CR will remain in Development.

5/9/05 PROS.05.09.05.F.02890.CLECExDocReqProcess

Timeline: Planned Updates Posted to Document Review Site Available May 09, 2005 CLEC Comment Cycle on Documentation Begins Beginning May 10, 2005 CLEC Comment Cycle Ends 5:00 PM, MT May 24, 2005 Qwest Response to CLEC Comments (if applicable) Available June 08, 2005 Proposed Effective Date June 23, 2005 4/20/05 Product/Process Meeting

Jackie Cole - Qwest stated that an adhoc meeting was held to present the requested enhancements to the web interactive view. Jackie said that during that meeting an additional request was made to show the ‘denied’ and ‘closed’ status. Jackie said that we did review the request and have determined that we cannot provide this information. She stated that we would like to move forward with this request as originally presented with the archived report and the detailed description. Bonnie Johnson - Eschelon asked if they were to look at the history in the interactive view would they be able to see the history and status of the request. Jackie Cole - Qwest stated that they would be able to see the Documentation #, description of request, current status, start date, last date updated, initiators name, PCAT name, the documented URL and a detailed description of the request. Bonnie Johnson - Eschelon asked if they would be able to get to the document itself. Jackie Cole - Qwest said yes, just like the PCAT. Bonnie Johnson - Eschelon said that they would not be able to see the history of the request. Jackie Cole - Qwest said that their Service Managers would be able to access the detailed information and history. Kim Isaacs - Eschelon asked if the URL is blank would that mean that the documentation was not updated. Kim said that their concern is that it may look as if a request for documentation was completed but that it was actually denied. Jackie Cole - Qwest agreed that the URL will be blank. Bonnie Johnson - Eschelon said can we assume that if the URL is blank then the request would indicate a denied status and that the request was not satisfied. Qwest confirmed that would be the case. Liz Balvin - Covad asked how soon these changes would be implemented. Jackie Cole - Qwest stated that a 45 day notification would be sent to the CLECs. Susan Lorence - Qwest said that the 45 day notification could be shortened. Bonnie Johnson - Eschelon said that she was ok with the 45 day notification. Bonnie asked if this view will show historical data over 45 days and the current view for anything less than 45 days. Jackie Cole - Qwest said that anything older that 45 days can be viewed in the archive report and anything less that 45 days will show the current view. Jill Martain - Qwest stated that this CR will remain in Development

3/18/05 Adhoc Meeting

Attendees: Kim Isaacs - Eschelon, Chris Terrell - AT&T, Jackie Cole - Qwest, Mark Coyne - Qwest, Lynn Stecklein - Qwest

Jackie Cole - Qwest stated that the purpose of this meeting was to discuss changes associated with PC100104-1 Track and Archive External Documentation Request). Jackie stated that in a previous adhoc meeting, the CLEC Community requested that Qwest research the feasibility to add an archive report and detailed description. Jackie stated that Qwest was able to accommodate these items. Jackie referred participants to the URL for review.

Kim Isaacs - Eschelon stated that these changes work for Eschelon.

Chris Terrell - AT&T agreed.

Kim Isaacs - Eschelon asked if Qwest would be able to show when a request was denied.

Jackie Cole - Qwest stated that she would have to research whether or not this would be feasible and provide an update in the April CMP Meeting.

There were no other questions or comments.

3/16/05 Product/Process CMP Meeting

Jackie Cole - Qwest stated that we will be able to implement the 3 action items requested in the last adhoc meeting. She stated that the test website is being readied and that a CLEC adhoc meeting will be scheduled to review. Jill Martain - Qwest stated that this CR will remain in Development.

2/16/05 Product/Process CMP Meeting

Jackie Cole - Qwest stated that an adhoc meeting was held on 2/15/05 to review the URL changes with the CLEC Community. Jackie said that we have 3 action items from this meeting to research. She stated that we will be scheduling another adhoc meeting in the next couple of weeks.

2/15/05 Adhoc Meeting

Attendees: Kim Isaacs - Eschelon, Roslyn Davis - MCI, Sharon VanMeter - AT&T, Amanda Silva - VCI Company, Liz Balvin - MCI, Chris Terrell - AT&T, Jackie Cole - Qwest, Carrie Bell - Qwest, Gary Berroa - Qwest, Mark Coyne - Qwest, Lynn Stecklein - Qwest

Lynn Stecklein - Qwest stated that the purpose of the meeting was to review the URL that supports PC100104-1 (Tracking and Archive External Documentation Requests). Lynn asked everyone to refer to the URL that provided in the notification sent 2/7/05.

Jackie Cole - Qwest provided an overview of the proposed changes located at http://www.qwest.com/wholesale/cmp/review/clecs.html. She said that the proposed spreadsheet includes the EDR number, request, Company, current status, last update and initiator.

Kim Isaacs - Eschelon asked if Qwest could create an archived report of what has been completed and could Qwest provide the description of the request.

Jackie Cole - Qwest said that we would take Eschelon's request as an action item to determine if their request could be accommodated.

Chris Terrell - AT&T asked if Qwest could provide a link to the document (s) that were changed.

Jackie Cole - Qwest stated that she would need to take this as an action item to determine if AT&T's request would be feasible. Jackie summarized the action items and stated that we would provide a status in the next few weeks.

1/19/05 Product/Process CMP Meeting

Jackie Cole/Qwest stated that the development team continues to work on the external website. She said that an adhoc meeting will be scheduled to review in mid February.

December CMP Meeting Minutes Jackie Cole – Qwest advised that we are still looking at a couple of different designs for the external web site and the level of effort. Once we have the design document we will schedule an ad hoc meeting with the CLECs. This CR will remain in Development Status.

11/17/04 November meeting minutes Qwest will accept this request and work to provide the functionality discussed in the Clarification Call. Jackie advised the External Documentation Request number, title, description and current status will be provided. Jackie advised that we will have another ad hoc call when Qwest is ready to present more details. This CR will move to Development Status.

10/20/04 CMP Meeting Minutes Kim Isaacs presented this CR saying that Eschelon is requesting external documentation be tracked on the Wholesale web site similar to the way CRs are tracked today. This will be used to monitor status and check for duplication before new requests are submitted. Doug Andreen, Qwest added that the clarification call has been held and Qwest has a good idea of what is required. The CR will move to presented status. Comment from Eschelon: Bonnie said this information would be beneficial and said though it streamlined the documentation request process, the history is missing.

Time/Date: Place: Conference Call-In No.: CR No.: CLEC Change Request Clarification Meeting

2:00 p.m. (MDT) / Wednesday October 13, 2004

1-877-521-8688 1456160# PC100104-1 Track and archive external documentation requests Attendees Attended Conference Call Name/Company: Kim Isaacs, Eschelon Doug Andreen, Qwest Jackie Cole, Qwest Jim Recker, Qwest Mark Coyne, Qwest Title:

Meeting Agenda:Action 1.0Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0Review Requested (Description of) Change Doug read and reviewed the CR. The CR requests that External Documentation Requests be tracked and archived on the Qwest Wholesale web site. Kim stated that External Documentation Requests are tracked internally by Qwest and would like to see this available to the CLECs. The business need for the CLECs is twofold. First to be able to check before submitting a request if a similar or duplicate request has already been submitted. Second, is to check the status on existing requests, similar to what is available through the Interactive Report on CR requests. Mark asked what level of detail Eschelon wanted. Kim said the description, current status, and status history i.e. when accepted, posted, denied, completed etc. There was discussion around how many status codes are used in the documentation process and if any other fields would be needed on the web version of the report. There were no further questions. 3.0Confirm Areas & Products Impacted No products or areas, only Wholesale Web site. 4.0Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0Identify/Confirm CLEC’s Expectation Track and archive documentation requests on the Wholesale web site 6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) Kim will present the CR at the October CMP meeting and Qwest response will be due in the November time frame.


CenturyLink Response

November 9, 2004

For Review by CLEC Community and Discussion at November’s CMP Meeting

Kim Isaacs ILEC Relations Process Analyst Eschelon

SUBJECT: Qwest’s Change Request Response - CR # PC100104-1

This is in response to Eschelon’s request that External Documentation Requests be tracked and archived on the Qwest Wholesale web site.

Qwest accepts this request and will move forward to provide the functionality as discussed on the Clarification call which includes: Document request number, Title of request, brief description of request and current status.

External Documentation Requests will continue to follow the existing process as currently documented.

Qwest will provide a status update at the December CMP Meeting. Sincerely, Qwest


Open Product/Process CR PC090704-1 Detail

 
Title: CLECs and Qwest will develop, and Qwest will document a new process, which allows CLECs to notify Qwest when Qwest makes changes to an undocumented existing process and it impacts any CLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC090704-1 Completed
7/20/2005
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Martain, Jill
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

When Qwest changes process without CLECs knowledge, the CLEC is significantly impacted because there was not opportunity to react, document and train Qwest’s change in its process. Eschelon has made every attempt over the last several years to have Qwest document its existing processes at the level of detail that is clear, concise and understood by both Qwest and CLECs. CLECs have requested documentation of these processes through CRs and, most recently, the documentation process which allows a CLEC to request Qwest documentation or to clarify CLEC facing documentation for an existing process. Process and/or policy documentation requires a level of detail that will eliminate differences in interpretation by the CLEC and Qwest employees using the processes. Eschelon has communicated to Qwest CMP in the past, that CLECs definition of an existing process is a process or policy that Qwest is using and there is no CLEC facing documentation. This includes any process or policy that Qwest has internal documentation to the contrary, however, CLECs are unaware of the correct process because Qwest never provided CLEC documentation. If Qwest chooses to change the process where Qwest is doing something that differs from Qwest’s internal documentation, Qwest should submit a CMP CR to change that process. In addition, the MCC process does not apply in these cases because the MCC process applies only to those processes documented for the CLEC where CLEC/Qwest should be following the correct documented process but is not. Recently, Qwest implemented a new expedite process for installation on certain products. Qwest said the existing expedite process was not impacted, however, when Qwest trained the new process internally Qwest did change the existing process. Qwest had always processed expedite requests for orders other than installation at CLECs request. When Qwest implemented the new expedite process, Qwest would no longer accept non-installation related expedite requests from CLECs. Qwest did not provide CLECs documentation for non-installation related expedites the Escalation and Expedite PCAT, and Qwest said the existing process for expedites was not changing so when Qwest would no longer accept these requests, this was a change to CLECs that CLECs did not anticipate or prepare for. Qwest should not change existing process without submitting a CMP CR to do so.

Expected Deliverables: Qwest and CLECs will collaboratively develop and Qwest will document a process to react to situations where Qwest changes an existing process for which Qwest provided CLEC documentation.


Status History

9/7/04 CR submitted

9/8/04 CR acknowledged

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/22/04 - Qwest generated notice CMPR.09.22.04.F.02085.Ad-hoc_meeting

10/13/04 - Qwest generated notice CMPR.10.13.04.F.02150.Ad-Hoc_Meeting

10/26/04 - Qwest generated notice CMPR.10.26.04.F.02215.Ad-hoc_meeting

10/28/04 - Qwest generated notice CMPR.10.28.04.F.02242.Updated_Documents

10/29/04 - Qwest generated notice CMPR.10.29.04.F.02245.Ad-hoc_Meeting

11/17/04 - November CMP Meeting minutes will be posted to the database

12/15/04 - December meeting minutes will be posted to the database

12/17/04 - Scheduled ad hoc meeting for 1/7 to review Process with CLECs

1/7/05 - Ad hoc meeting held

01/19/2005 - Discussed in the January Product Process Monthly CMP Meeting

02/16/2005 - Discussed in the February Product Process Monthly CMP Meeting

03/15/2005 - CMPR.03.15.05.F.02700.CMP-Ad_Hoc_Meeting

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting

03/16/2005 - CMPR.03.16.05.F.02708.AdHocMtgURLChanges

03/24/2005 - Ad Hoc Meeting Held. See Project Meetings Section for Meeting Minutes.

04/08/2005 - PROS.04.08.05.F.02798.CLECImpChgProcClrfctnRqst (Level 4)

04/20/2005 - Discussed in the Monthly Product/Process CMP Meeting

05/06/05 - PROS.05.06.05.F.2870.FNL_ImpChgProcClrfctnRqst (Level 4)

05/18/2005 - Discussed in the Monthly Product Process CMP Meeting

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

07/20/2005 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

July 20, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that this request was effective on May 23, 2005 and asked if the CR could be closed. Bonnie Johnson-Eschelon said that the CR could be closed.

-- June 15, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that this was effective on May 23, 2005 and Qwest would like to move this CR to CLEC Test. There was no dissent to the status of CLEC Test.

May 18, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that the Final Notice was sent on May 6th and that the proposed effective date is May 23, 2005. This CR remains in Development status.

-- April 20, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that the notice was sent on April 8th and that the comment cycle runs thru April 23rd. Jill then noted that this would become effective on May 23rd and that the status remains as Development.

- March 24, 2005 Ad Hoc Meeting Minutes ATTENDEES: Carol Desborough-Wisor, Tom Larson-Cox, Kim Isaacs-Eschelon, Sharon Van Meter-AT&T, Bonnie Johnson-Eschelon, Bob Eggert-SBC, Rosalin Davis-MCI, Julie Pickar-TDSMetroCom, Stephanie Prull-Eschelon, Peggy Esquibel Reed-Qwest, Gary Berroa-Qwest, Carrie Bell-Qwest, Jackie Cole-Qwest, Jill Martain-Qwest

Peggy Esquibel Reed-Qwest stated that there have already been several discussions regarding this Change Request and that this ad hoc meeting was scheduled in order to review the process that was developed for PC090704-1 which is titled CLECs and Qwest will developed, and Qwest will document a new process, which allows CLECs to notify Qwest when Qwest makes changes to an undocumented existing process and it impacts any CLEC. Peggy stated that the URLs that will be used in the ad hoc call were provided in the meeting notification that was sent on March 16th. Peggy stated that one of the URLs contains the CLEC Process Clarification Change Request Form and the other URL is for the Process document. Gary Berroa-Qwest stated that one of the URLs contained the CLEC External Process Clarification Request form and the other link is the Process document that can be uploaded and saved to the user’s desktop. Gary then directed the call participants to open the link that contained the form and stated that the fields with an asterisk were required fields. Gary then walked through the fields on the form. Jill Martain-Qwest stated that the form is slightly different than what was previously discussed and noted that we wanted it to be similar to the existing process. Bonnie Johnson-Eschelon stated that the fields titled ‘Detailed Description of Change’ and ‘Description of Change Impacted CLEC’ could be interpreted to mean the same thing. Bonnie asked if the ‘Description of Change Impacted CLEC’ was for the impact to the CLEC. Jill Martain-Qwest stated yes, it is for the CLEC to indicate what they experienced and the impact to the CLECs normal course of business. Bonnie Johnson-Eschelon asked if the field could be named differently. Jill Martain-Qwest suggested that the field name be changed to something like ‘Description of How the Change Impacted the CLEC’. Bonnie Johnson-Eschelon stated that she agreed with the field name change. Gary Berroa-Qwest stated that the change could be made and asked if there were any other questions or comments. There were none brought forward. Peggy Esquibel Reed-Qwest asked if all on the call were okay with what was presented. Bonnie Johnson-Eschelon stated that she liked the form and noted that she likes electronic forms. The CLEC Community agreed with Bonnie. Gary Berroa-Qwest stated that the other link is the CLEC External Process Clarification Request and noted that at the bottom is a hyperlink for the Process Guide. Bonnie Johnson-Eschelon asked if the Process Guide contained the language that was previously agreed to. Jill Martain-Qwest stated yes and noted that the only change will be to the form. Gary Berroa-Qwest stated that the web site will have a link to the form and will have the ability to upload the Process Guide. Jill Martain-Qwest stated that when there are items that had a resolution and were closed, it would be similar to the existing external process. Bonnie Johnson-Eschelon stated that she likes that it is on the same web page as it is then all in one location. Peggy Esquibel Reed-Qwest stated that it sounds like everyone likes what they saw. Bonnie Johnson-Eschelon stated yes and stated that she appreciated the work and effort. Peggy Esquibel Reed-Qwest stated that we would then proceed with the implementation of this process with the appropriate notifications. There were no additional comments or questions.

- March 16, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that we are working to get the web up and working and noted that an ad hoc call had been scheduled for March 24th. This CR remains in Development status.

-- February 16, 2005 Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that we were working on how to implement this on the web to look like the existing external documentation process. Jill stated that we would schedule ad ad-hoc meeting to take place in March for review and feedback. This CR remains in Development status.

January 19, 2005 Product Process CMP Meeting Discussion Jill Martain/Qwest stated that there was an ad-hoc meeting on January 7th for review of the process. Jill stated that an agreement was reached and noted that Qwest is working internally to determine what needs to be done and how it will be done. Bonnie Johnson/Eschelon stated that she had asked for the post-order process and noted that Qwest does not want to consider that. Bonnie stated that she has asked Qwest if the post completion process could be followed. Jill Martain/Qwest stated that was for a different change request but can be discussed now. Bonnie Johnson/Eschelon asked why Qwest did not want to use the post completion process. Bonnie stated that she has discussed this with Covad, and Covad does not want any post completions. Bonnie stated that she had talked with Liz (Balvin/Covad) and that Liz told her that as long as Qwest is reviewing the examples to eliminate the problem causing post completions she is okay using the post completion process. Jill Martain/Qwest stated that with the previous agreement Qwest agreed to document the existing process, which was a telephone call. Jill agreed to take back and review if Qwest can utilize the Post Completion Process. Bonnie Johnson/Eschelon stated that she would rather that the post completion process be followed since this was a post completion issue. Jill Martain/Qwest stated that she would revisit and look at the pros and the cons.

PC090704-1 CLEC Impacting Change Process Ad Hoc Meeting January 7, 2005

In Attendance: Amanda Silva – VCI Kathy Stitcher – Eschelon Jill Martain – Qwest Pete Budner – Qwest Cindy Harlan – Qwest Bob Eggert – SBC Bonnie Johnson – Eschelon

Cindy Harlan – Qwest opened the call and reviewed the agenda. Cindy advised that this process was requested by Eschelon as a means to address an escalated situation when a process changes and it negatively impacts the CLECs. Jill Martain – Qwest advised that we have reviewed the process internally and made a few changes. The purpose of this call is to review the changes and discuss next steps.

Jill Martain – Qwest stepped through each section of the process. Jill reviewed the scope of the process and when it would be used.

Bonnie Johnson – Eschelon asked if a phone call instead of email could be used for section 3.2. Jill explained a phone call is better as discussion needs to take place in this step. Jill agreed that in section 3.2.2 an email could be sent to capture the discussion.

Bonnie also suggested that Doug’s name be removed from the process document. Jill agreed. Bonnie asked what EDCR stood for. Jill replied External Documentation Change Request.

Bob Eggers asked if the request is out of scope is it still posted historically? Jill advised that is one of the next steps that we need to take. We need to meet with the web team to create a location on the web to store these, and model it after the External Documentation Change Request.

Next Steps include: Create the online form to submit Make web updates Provide notification of the process

December CMP Meeting Minutes Jill Martain – Qwest advised that we are continuing with our internal review. We have some updates to the process as a result of our reviews and some additional work to make the process and form available to the CLECs. An ad hoc meeting will be schedule to review the proposed changes with the CLECs after the first of the year. This CR will remain in Development Status.

11/17/04 November meeting minutes Jill Martain – Qwest advised an ad hoc meeting was held and feedback on the draft proposal was received. Qwest will meet internally and then will schedule another ad hoc meeting with the CLECs. The CR will remain in Development Status.

10/20/04 CMP Meeting Minutes Jill Martain, Qwest stated that there had been one ad-hoc call and that Qwest was in the process of developing the form for review at the next ad-hoc meeting to be held October 27. Bonnie added that she thought the ad-hoc meeting had been a great start. The CR will move to development.

-- Ad Hoc Meeting Minutes PC090704-1 CLECs and Qwest will develop, and Qwest will document a new process, which allows CLECs to notify Qwest when Qwest makes changes to an undocumented existing process and it impacts any CLEC. CMP Product & Process October 27, 2004 1-877-521-8688, Conference ID 1456160# 9:00 a.m. – 10:00 a.m. Mountain Time

PURPOSE

To review the rough document and form for this process

List of Attendees: Jen Arnold – TDS Bonnie Johnson – Eschelon Kim Isaacs – Eschelon Kathy Stichter - Eschelon Lynn Kellas – Electric Light Wave Mark Matson – SBC Telecom Rosalin Davis - MCI Jill Martain – Qwest Jim Recker – Qwest Doug Andreen - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Doug Andreen explained that the purpose of the meeting was to review the document and form associated with this CR.

Jill Martain walked through the document. She said Qwest struggled with the title of the process and further discussion determined that if any of the CLECs had a better title to please submit.

Bonnie Johnson asked what types of situations were covered in section 1.0. Jill said situations where something was being viewed one way by the CLEC’s and a different way by Qwest.

Liz Balvin of Covad had submitted three questions in advance of the meeting. The first involved Impact to the CLEC and if the CLEC would have to prove impact. Jill answered that the impact is determined by the submitting CLEC. Changes could occur during meetings that follow by mutual agreement. Eschelon said this is ok as long as long as it is defined at the CLEC level. The second question concerned making the document less vague with respect to “short term course of action” and “until meetings can be scheduled”. The words “within one business day” were inserted at three places in the document to clarify time frames. The third question concerned CLECs having input to problem resolution. Jill explained that it would be a mutual decision of how to get to resolution, via CR, MCC, etc.

It was also clarified that the intent is to have this on the web in the same place as the External Documentation Process. Kim Isaacs asked if the information would be tracked and Jill answered that this was being looked into. Jill further clarified that out of scope problems would be resolved by Qwest calling the initiator.

It was agreed that the updated document would be distributed via notice tomorrow October 28th and that CLECs would forward comments or red-lines by close of business Wednesday November 3rd. The next meeting was scheduled for Thursday November 18, 9 a.m. Mountain time.

-- Time/Date: Place: Conference Call-In No.: CR No.: CLEC Change Request Ad-Hoc Meeting

October 7, 2004 9:00 p.m. – 10:00 p.m. Mountain Time

1-877-521-8688, Conference ID 1456160# PC090704-1

Attendees Attended Conference Call Name/Company: Jen Arnold – TDS Bonnie Johnson – Eschelon Kim Isaacs, Eschelon Stephanie Prull, Eschelon Kathy Stiester, Eschelon David Bellinger, AT&T Rosalin Brewer, AT&T Rosalin Davis, MCI Amanda Silva, BCI Liz Balvin, Covad Jill Martain, Qwest Communications Jennifer Fisher, Qwest Doug Andreen, Qwest Communications Title:

Meeting Agenda: Action 1.0 Introduction of Attendees Introductions were made and the purpose of the call discussed. 2.0 Minutes Doug Andreen read and reviewed the CR. The CR requests that CLECs and Qwest will develop, and Qwest will document a new process, which allows CLECs to notify Qwest when Qwest makes changes to an undocumented existing process and it impacts any CLEC. He also said that at this meeting we wanted to get to the root cause of the problem from both a CLEC and Qwest perspective, establish a high level outline of the process, and establish next steps. Bonnie Johnson added that this process would be for the times when Qwest unknowingly does something different. Of course, when Qwest knows, they would handle the situation through the CMP process. Jill Martain proposed the following steps as a high level view to resolve the CR issues: 1. Determine a method in which the CLEC can communicate their concern/issue to Qwest, i.e., the comment or cmpcr mailbox. 2. Schedule an ad-hoc meeting to discuss the problem, establish the cause and correction and decide together how to move forward. 3. Decide if PCAT changes, notices, etc. are needed. Some discussion ensued and it was agreed that the above points were an excellent start. It was further agreed to use a yet to be developed template to communicate to Qwest in a standard manner via the cmpcr mailbox. These emails will carry a special Subject line so they are easily identifiable for special handling. It was decided the template would include a description of the issue (the situation before and the existing situation), any associated PCATs, manual processes, Technical Publications, etc., a history of steps taken so far i.e. Repair ticket numbers, escalation tickets, contact with Qwest employees including the CLECs Service Manager, additional SMEs the CLEC would like involved, any proposed solutions, and an assessment on the impact this is having on the CLEC. It was further agreed that the degree of impact would be expressed as high, medium, or low. If a high impact , the CLEC would be contacted within 24 hours to determine an immediate course of action. If a medium or low impact is indicated the regular timeframe for an ad-hoc meeting (5 days) would apply. Bonnie stated she would like to see these distributed to other CLECs. The method for doing this has yet to be devised. Also Bonnie added that this process would be for items where the CLEC has at least already visited with their Service Manager and determined this is the route to go. 3.0 Next Steps/Action Plan Qwest will design a rough draft of the form and process. The next meeting will be October 27, 9 – 10 am. Mountain time. Qwest will forward the form and process before the meeting.

Time/Date: Place: Conference Call-In No.: CR No.: CLEC Change Request Clarification Meeting

September 13, 2004 3:00 p.m. – 3:30 p.m. Mountain Time

1-877-521-8688, Conference ID 1456160# PC090704-1

Attendees Attended Conference Call Name/Company: Jen Arnold – TDS Bonnie Johnson – Eschelon Kim Isaacs, Eschelon Donna Osborne-Miller, AT&T Emily Baird, POP Telecom Liz Balvin, Covad Jim Recker, Qwest Communications Sue Kriebel, Qwest Communications Jill Martain, Qwest Communications Doug Andreen, Qwest Communications Title:

Meeting Agenda: Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. 2.0 Review Requested (Description of) Change Doug Andreen read and reviewed the CR. The CR requests that CLECs and Qwest will develop, and Qwest will document a new process, which allows CLECs to notify Qwest when Qwest makes changes to an undocumented existing process and it impacts any CLEC. Bonnie Johnson summarized the description of the CR and said that it is designed to cover situations such as the Design Process Expedite Process as discussed at last month’s CMP meeting where Qwest had always accepted requests but all of a sudden would not. She stated that Eschelon’s interpretation of and existing process is something that Qwest is doing globally whether it is internally documented at Qwest or not. When a process stops and CLECs are impacted, CLECs need a way to react since they cannot see the process change. Jill Martain said such cases are examples where Qwest might view this as a compliance issue while the CLECs view it as a change to existing process Bonnie said we need to collaboratively determine a process for when this happens, for instance when a Qwest employee tells us “Oh no, we got an MCC covering that”. Liz Balvin asked if there was an MCC sent out or if they were going by the final Product Notification. There was much discussion around the Expedite process in specific and what this CR would accomplish. . Discussion continued to state that in the case of expedites, the PCAT was silent on the activity types for expedites. Qwest’s intent is that it applies to all order activity types and the CLEC viewed the PCAT for installation activity only. This CR would implement steps the CLECs and Qwest would follow to resolve these types of situations. It was stated that the MCC or notification processes should not be confused with the intent of this CR. Bonnie stated for situations where Qwest has a document that says “do this” and the CLEC has a different viewpoint of the existing process. This CR is for unique situations where Qwest views an issue as a compliance matter and the CLECs view it as a process change. Jim Recker asked if this would encompass more than Installation and Repair. Jill answered yes that it would cover all areas. Doug pointed out that the CR was not received before the cutoff for the September meeting. Bonnie said she would like to walk it on this month. Therefore, the CR will be walked on at the September 16 CMP meeting.

3.0 Confirm Areas & Products Impacted 4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting. 5.0 Identify/Confirm CLEC’s Expectation Qwest and CLECs will collaboratively develop and Qwest will document a process to react to situations where the CLECs and Qwest have different viewpoints on process issues/changes that have a direct impact on the CLEC community where the existing documentation needs clarity. 6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) The CR will be walked on at the September 16 meeting. Response will be due at the November CMP meeting.


Open Product/Process CR PC033104-1 Detail

 
Title: Redesign the archive change request information on the Qwest Wholesale web site to allow search and print functionality
CR Number Current Status
Date
Area Impacted Products Impacted

PC033104-1 Completed
7/21/2004
Web site search functionality
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Andreen, Doug
Director:
CR PM: Andreen, Doug

Description Of Change

Eschelon asks Qwest to restructure the design of the archived CRs on its web site to allow search and print functionality. In its current structure, there is so much data contained in the Product/Process and System archived CR storage that search and print functionality is either hindered ort cannot be performed at all. Qwest and the CLECs will collaboratively determine how to separate the data so functionality is restored but archived CRs can be found easily.

Expected Deliverable:

Qwest will redesign the archive change request information on the Qwest Wholesale web site to allow search and print functionality.


Status History

03/31/04 - CR Submitted

03/31/04 - CR Acknowledged

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/17/04 - Qwest initiated notification PROS.06.15.04.F.01791.Web_CR_Archive_Report

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

7/21/04 July CMP Meeting Doug Andreen, Qwest said that a prototype version was placed on the website June 15. The comment cycle began on June 16 and completed on June 22. No comments were received. Therefore, the change became effective July 6. There were no comments in the meeting and the CR will be moved to Completed status.

- Meeting Minutes CMP June Meeting Doug Andreen, Qwest said the site is now up and running. He said the CLEC notification went out yesterday and the comment cycle starts today. Effective date is scheduled for July 6. John Berard, Covad asked if this is still an Adobe file. Doug said no. John asked if it could be downloaded as an Adobe file. Doug said he would check. Doug said it will work for download the same way as the new Interactive Report. (After the meeting it was found that the file can be downloaded as an Adobe (pdf) file or a text file but it will only download the specific level of the file you are in at the time. For instance, if you are in the CR Index, the download will only contain the Index and will not have links to the detail file. If you are in a Detailed Record the download will only contain that record. However, the file can be downloaded as an html file, and if downloaded at the Index level, will maintain links to the Detailed information.) Bonnie Johnson, Eschelon added that she is anxious to try the new search capabilities. Liz Balvin asked if individual CRs can be printed. Doug answered yes. This CR will move to Test Status

Meeting Minutes CMP May Meeting Doug Andreen, Qwest summarized the response saying that Qwest accepts the CR and is proceeding to design the Archive change request information in the same manner as the recently completed rewrite of the Interactive Report. He added that this design effort should be finished between now and the next meeting so the intent is to notice the CLEC Community and then post to the Web as a Prototype just as was done with the Interactive Report rewrite. The CR will move to Development.

-- 4/21/04 April CMP meeting Bonnie Johnson, Eschelon presented this CR and stated the plan is to design it in the same way as the Prototype Interactive Report. The CR will move to Presented.

- 10:30 (MST) / Wednesday April 7, 2004

1-877-521-8688 1456160# PC033104-1

Attendees Bonnie Johnson, Eschelon Cindy Macy, Qwest Communications Doug Andreen, Qwest Communications

Meeting Agenda:Action 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

2.0 Review Requested (Description of) Change Doug read and reviewed the CR. The CR requests a redesign of the Archive CR Report to allow search and print functionality

Bonnie stated that the current structure there is so much data that search and print functionality is either hindered or cannot be performed. It calls for Qwest and the CLECs to collaboratively determine how to separate the data so functionality is restored.

Cindy asked if Bonnie could elaborate on the search and print function capabilities.

Bonnie stated that no new capabilities are needed but just to restore the functionality of these items. Search in particular has been crashing. The intent is to minimize the data.

(It is noted this CR was originally an action item and had been discussed in the last CLEC meeting. At that meeting it was discussed that if the Prototype Interactive Reports were approved in the April CLEC meeting that the Archive could follow the Interactive Report format and be broken into sections by the year the CRs had been initiated. ) 3.0Confirm Areas & Products Impacted Archive report for Product and Process and Systems CRs.

4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting.

5.0 Identify/Confirm CLEC’s Expectation Redesign the Archive Report to restore/allow search and print functionality of CRs.

6.0 Identify any Dependent Systems Change Requests None 7.0 Establish Action Plan (Resolution Time Frame) Bonnie will present this CR at the April meeting and a response will be due in the May timeframe.


CenturyLink Response

May 12, 2004

DRAFT RESPONSE For Review by CLEC Community and Discussion at the May CMP Meeting

Bonnie Johnson Senior Manager ILEC Relations Eschelon

SUBJECT: Qwest’s Change Request Response - CR # 033104-1

This is in response to Eschelon’s request to redesign the archive change request information on the Qwest Wholesale web site to allow search and print functionality.

Qwest accepts this CR and will proceed to design the archive change request information in the same manner as the recently completed rewrite to the Interactive Report.

Qwest will provide an updated status in the June CMP meeting.

Sincerely,

Doug Andreen Qwest


Open Product/Process CR PC111504-1 Detail

 
Title: Excessive Repair/DSL hold time escalation contact information
CR Number Current Status
Date
Area Impacted Products Impacted

PC111504-1 Denied
1/19/2005
Maintenance Repair
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Colton, Nick
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest will develop a process and/or provide and document contact information on how a CLEC can escalate when calling the Qwest repair and DSL technical support centers using a contact other than the number a CLEC calls to report the trouble. Qwest publishes only one number for its Repair and DSL technical support center. Qwest’s current escalation process asks the CLEC to escalate using that number. However, when the reason for escalation is that the CLEC cannot get through to report the trouble, and Qwest has the CLEC on hold for excessive periods of time, that same number is of no use to the CLEC and the CLEC cannot escalate. For example, Eschelon had brought excessive hold times for Qwest’s DSL support center as an issue to Eschelon’s service Management Team twice in the last several months. In February of 2004, Eschelon discovered Qwest started taking repair calls for MSN. This resulted in significant hold times for almost every call between 45 minutes and one hour. Eschelon brought this issue to our Service Managers again in October of 2004. The hold times this time had spiked to about 30 minutes per call. In both cases, Eschelon was unable to escalate individual occurrences of excessive hold times to Qwest because Qwest’s escalation process requires the CLEC to escalate using the same number the CLECs calls to report the trouble and was only able to report the problem as a global issue to Qwest. Qwest should provide an escalation process and/or contact over and above escalating through the number Qwest asks a CLEC to call to report the trouble.

Expected Deliverable:

Qwest will develop a process and/or provide and document contact information on how a CLEC can escalate when calling the Qwest repair and DSL technical support centers using a contact other than the number a CLEC calls to report the trouble.


Status History

11/15/04 - CR Received

11/17/04 - CR Acknowledged

11/19/04 - Contacted CLEC and scheduled Clarification call for 12/3

12/3/04 - Held Clarification Call

12/15/04 - December meeting minutes will be posted to the database

12/28/04 - Requested information from Eschelon

1/12/05 - Emailed response to CLEC


Project Meetings

1/19/05 Product/Process CMP Meeting

Georgeanne Weidenbach/Qwest stated that Qwest undertook to reduce hold time issues in its DSL Technical Support Center by implementing shift changes as well as adding a significant number of agents in the fourth quarter of 2004. Georgeanne said that Qwest plans to continue evaluating needs and adding agents as resources permit in 2005. She also stated that Wholesale Customers can submit repair tickets, effective December 2004, on-line using CEMR. Georgeanne said that Qwest has not experienced hold time issues associated with its other repair centers. Bonnie Johnson/Eschelon stated that she sent the denial to their Service Manager and advised that they would be paging them if the hold time is excessive. Jill Martain/Qwest stated that this CR would be closed.

From: Johnson, Bonnie J. [mailto:bjjohnson@eschelon.com] Sent: Wednesday, December 29, 2004 2:33 PM To: Macy, Cynthia; Johnson, Bonnie J. Cc: Peterson, Pete; Isaacs, Kimberly D. Subject: RE: PC111504-1 Excessive Repair DSL hold time

Hi Cindy, Your request would be very time consuming. Perhaps if Qwest had requested we provide that information on a going forward basis when we had the clarification call, Eschelon could have done that. In addition, I believe Qwest is required to report hold time or time to answer information so chances are Qwest already has the data you are asking for.

To go back would and gather the information would be too difficult, if we could gather it at all. I will ask Pete Peterson our RSB Manager if he could forward examples on a going forward basis, however.

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

--Original Message-- From: Macy, Cynthia [SMTP:Cynthia.Macy@qwest.com] Sent: Wednesday, December 29, 2004 2:26 PM To: Johnson, Bonnie J. Subject: RE: PC111504-1 Excessive Repair DSL hold time

Bonnie,

Thank you very much for the information. I have forwarded this on to the team working on this CR.

We would also appreciate it if you could please provide a list of Qwest ticket numbers (Designed Services) or Phone numbers (POTS & DSL) that were reported to Qwest repair that had the excessive hold time while trying to make the initial report.

It would be nice to have the date and time the circuits were reported as well but not necessary. This information will help us determine the scope of the potential problem and where we may have an issue with hold time i.e. center, day of week, time of day, Holidays, volumes of tickets with excessive hold time, etc.

I appreciate your efforts obtaining this information. If you can provide this for the past tickets and for future tickets that would be great.

Let me know if you have any questions. Thanks, Cindy

Cindy Harlan Wholesale Change Management Qwest 303-382-5765

--Original Message-- From: Johnson, Bonnie J. [mailto:bjjohnson@eschelon.com] Sent: Wednesday, December 29, 2004 12:36 PM To: Macy, Cynthia; Johnson, Bonnie J.; Isaacs, Kimberly D. Cc: Peterson, Pete Subject: RE: PC111504-1 Excessive Repair DSL hold time

Hi Cindy, The number Eschelon is calling for DSL (as well as other repair) are the numbers posted on Qwest's web site.

http://www.qwest.com/wholesale/clecs/maintenance.html

Contacts Interconnect Service Center (888-796-9087): * To submit Trouble Reports within 24 hours of Service Order Confirmation.

QCCC Warranty Group (866-549-3846 option 5) * To submit Trouble Reports on UNEs within 30 calendar days of Service Order Completion

AMSC (800- 223-7881): * Telephone Number * Non-Designed Service * Centrex Service * Shared Loop Service * Designed Service DSO, DS1, and DS3 circuit number * Unbundled Loop Service

RCHC (888-405-0083): * Non-Design POTS: * Resale - Simple Residential (1FR) * Resale - Simple Business (1FB) * UNE-P POTS Qwest Digital Subscriber Line (DSL) Technical Support Center (800-247-7285) * Resale * UNE-P * UNE-STAR

In addition, as you can see from the repair escalation web site, Qwest does not provide alternate numbers for escalation. You have to escalate through the main TN and Qwest provides no information at all on DSL escalations.

http://www.qwest.com/wholesale/customerService/escalation.html

Tier Repair Contacts Non-Design Services Designed Services Info To Provide 1 Qwest AMSC, CRSAB, or RCHC initial Trouble report 800-223-7881 800-223-7881 Non Design: Telephone Number Designed Services Circuit ID, CLLI code, 2/6 code or trunk group 2 Status 800-223-7881 800-223-7881 Non Design: Telephone Number Designed Services Qwest ticket number 3 Escalations Note: The appropriate Escalation Manager's name & number will be provided after the Designed Test Center is contacted after level one escalation at the technician level. Level two and three will occur at the line manager and center manager level. Levels four and five will occur at the Director and Vice president level as noted in tiers six and seven. 800-223-7881 800-223-7881 Non Design: Telephone Number Designed Services Qwest ticket number

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

--Original Message-- From: Macy, Cynthia [SMTP:Cynthia.Macy@qwest.com] Sent: Wednesday, December 29, 2004 11:40 AM To: Johnson, Bonnie J.; Isaacs, Kimberly D. Cc: Macy, Cynthia Subject: PC111504-1 Excessive Repair DSL hold time

The team working on this CR needs to know what the exact phone numbers are that you are calling. Would you please provide the actual telephone numbers that are dialed that you are experiencing excessive hold time on.

Thank you, Cindy

Cindy Harlan Wholesale Change Management Qwest 303-382-5765

December CMP Meeting Minutes Kim Isaacs – Eschelon presented the CR. Kim advised that Eschelon is requesting escalation contact information for cases when there are excessive hold times for DSL repair and regular repair. The first level escalation number is the same as the second level escalation number. When the CLEC can’t get through on the first number they have no other alternative number to contact. John Berard – Covad asked if there was not a 3rd level number that was different. Cindy Macy – Qwest advised that there is only one number to contact for DSL repair and regular repair so if there is an issue getting through it seems as if there is not an alternative available. This CR will move to Presented Status.

Clarification Call: PC111504-1 Excessive Repair / DSL hold time escalation contact information

December 3, 2004 1:0 0 – 2:00 p.m. MT

In attendance:

Paul Schlachter – Qwest Communications Kim Isaacs – Eschelon Jen Arnold – TDS Roslyn Davis – MCI Randy Owen - Qwest Communications Tim Francis - Qwest Communications Paul Diamond - Qwest Communications Jim Recker - Qwest Communications Bonnie Johnson – Eschelon John Berard – Covad Cindy Macy - Qwest Communications

Cindy Macy – Qwest opened the call and advised that this is the Clarification call for PC111504-1 Excessive Repair / DSL hold time escalation contact information. Cindy advised that we will have Eschelon review the CR that they submitted. We will make sure Qwest understands the CLECs expectations and discuss next steps.

Bonnie explained for DSL repair there is a number to call to report tickets and this is the same number to use if you have an escalation. There is only one number to call for any issue the CLECs may have. Bonnie explained the Service Managers are the escalation point for the CSIE group for provisioning, but for repair there isn’t another contact available.

Bonnie advised they are experiencing excessive hold times for Qwest DSL repair and for basic repair also. When a call is made to the repair line we can be on hold for up to 45 minutes. The problem is that there is not another number to call if we can’t get through on the repair line. It doesn’t matter if we have an escalation as we can’t get through any sooner. Bonnie clarified that it is not the repair call that needs to be escalated, but the fact that we can’t get through. We need another way to contact repair when the main line hold time is excessive.

Cindy Macy – Qwest asked about the comment on the CR that mentions that Eschelon has worked with Service Management on past incidents. Bonnie explained that they worked with Service Management in February 2004 and October 2004. Service Management investigated why the hold time was so long and provided that information to Eschelon. They did not put anything in place to reduce the hold time or discuss an alternate way to contact repair when hold times are long.

Paul – Qwest asked for the average call hold time? Bonnie advised that in February it was 45 minutes, October was 30 minutes and November is 25-30 minutes. Bonnie said she understands that the nature of doing business will occasionally cause delays, but we need to get a process or other avenue in place to address the excessive hold time when it occurs. This should not go on for extended periods of time.

The team clarified that Eschelon is asking for a process to contact repair (both DSL and regular repair) when the main number has excessive hold time. Cindy verified this could be a pager, email, another phone number or another person to contact. Bonnie advised yes, that they need an alternate process to contact repair when the hold time on the phone number is excessive.

Cindy advised the next step is for Eschelon to present the CR at the December CMP meeting. Qwest will have an internal meeting to review what can be done and a response will be provided at the January CMP meeting.

There were no other questions.


CenturyLink Response

For Review by the CLEC Community and Discussion at the January 19, 2005 CMP Meeting

January 11, 2005

Eschelon Bonnie Johnson Director, Carrier Relations

SUBJECT: CR # PC111504-1 Excessive Repair / DSL hold time escalation contact information

Qwest undertook to reduce hold time issues in its DSL Technical Support Center by implementing shift changes as well as adding a significant number of agents in the fourth quarter of 2004. Also, Qwest plans to continue evaluating needs and adding agents as resources permit into 2005. Further, Wholesale customers may submit repair tickets (including DSL repair tickets, effective December 2004) on-line using CEMR. Qwest has not experienced hold time issues associated with its other repair centers. Qwest is meeting or exceeding its repair measures in these centers. With the operational improvements that Qwest has already made, Qwest is denying this request because the requested change does not result in a reasonably demonstrable business benefit (to Qwest or the requesting CLEC) or customer service improvement.

Sincerely, Qwest Communications


Open Product/Process CR PC050405-1 Detail

 
Title: Provide individual WTNs (Working Telephone Number) with all NRCs (Non Recurring Charge)
CR Number Current Status
Date
Area Impacted Products Impacted

PC050405-1 Completed
2/15/2006
Billing Resale, UNE-P, Centrex
Originator: Stichter, Kathy
Originator Company Name: Eschelon
Owner: Kilker, Terri
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Currently, Qwest does not provide the individual WTNs with each NRC. For example, on a new install of 4 lines, for the same customer with different WTNs, all the NRCs show the main number on the service order, i.e. the BTN (Billing Telephone Number). Because of this, Qwest is issuing incorrect BillMate Soactvty files. From looking at the Qwest BillMate Soactvty file, Eschelon does not know for which lines Qwest is billing NRCs, making validation of bills more time consuming. Eschelon asks Qwest to provide the correct telephone number for each NRC, on the BillMate Soactvty files.

Expected Deliverable:

Qwest will identify each NRC, on the BillMate Soactvty files, with the correct telephone number.

(See related Systems CR SCR050405-04)


Status History

05/04/2005 CR submitted

05/05/2005 CR acknowledged

05/13/2005 Clarification Call Held

05/18/2005 Discussed in the Monthly Product Process CMP Meeting

06/07/2005 Initial Evaluation Response Sent to Eschelon, via Email

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

07/20/2005 - Discussed in the Monthly Product Process CMP Meeting

08/17/2005 - Discussed in the Monthly Product Process CMP Meeting

09/21/2005 - Discussed in the Monthly Product Process CMP Meeting

10/19/2005 - Discussed in the Monthly Product Process CMP Meeting

11/16/2005 - Discussed in the Monthly Product Process CMP Meeting

12/14/2005 - Discussed in the Monthly Product Process CMP Meeting

12/16/2005 - PROS.12.16.05.F.03536.Individual_WTNs_for_NRC (Level 1)

12/27/2005 - Status Changed to CLEC Test Due To December 19, 2005 Implementation

01/18/2006 - Discussed in the Monthly Product Process CMP Meeting

02/15/2006 - Discussed in the Monthly Product Process CMP Meeting

02/15/2006 - Status Changed to Completed. Concurrence Received at Monthly CMP Meeting.


Project Meetings

February 15, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this was deployed in December and asked Eschelon if they were ready to close the CR. Kathy Stichter-Eschelon stated that the CR could be closed. This CR moves to Completed status.

January 18, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this is the manual piece of this effort and was implemented on December 19th. Jill asked if there was any objection to closing the CR. Kathy Stichter-Eschelon asked for the CR to remain open for another month so she can get a few more bills. Kathy stated that she did not think that this was working properly but was not sure if it is the manual or mechanized portion. Kathy stated that she would have a better feel next month. Jill Martain-Qwest stated that the CR would remain in CLEC Test.

December 14, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this effort is in process and still on target for December 19, 2005. This CR remains in Development Status.

-- November 16, 2005 Monthly Product Process CMP Meeting Discussion: Terri Kilker/Qwest stated that this CR is in Development and is on target for the December timeframe. Terri stated that the notice would be going out. Jill Martain/Qwest stated that Qwest will be sending a Level 1 Notice for this effort due to no PCAT Updates. Kathy Stichter/Eschelon asked when the notice would be sent. Terri Kilker/Qwest stated that it would be sent in the near future. Terri then advised Kathy (Stichter/Eschelon) that she had sent her an email in response to her EDI question. Kathy Stichter/Eschelon stated that she did receive the email.

October 19, 2005 Monthly Product Process CMP Meeting Discussion: Terri Kilker/Qwest stated that this CR is currently in Development and is on target for a December Release. Jill Martain/Qwest stated that this CR remains in Development status.

- September 21, 2005 Monthly Product Process CMP Meeting Discussion: Terri Kilker/Qwest stated that this request includes a Product Process and a Systems CR. Terri stated that the Systems CR (SCR050405-04) is currently targeted for implementation on December 17th and that it is Qwest’s preference to implement the manual piece in conjunction with the system changes. Terri then asked if Eschelon would like to withdraw the Product Process CR, as the work would be done via the systems CR. Bonnie Johnson/Eschelon stated that she was opposed to withdrawing the Product Process CR and that she would like to see the implementation date on the Product Process CR match the systems implementation date. Bonnie stated that Qwest pushes dates out on systems CRs and stated that she wants a firm tentative date. Bonnie stated that she can live with a December 17th date but if the system piece gets moved out, she would like Qwest to move forward with the Product Process piece. Kathy Stichter/Eschelon stated that there is still a process piece involved so she is confused on the request to withdraw. Kathy asked if Qwest did process changes with systems CRs. Jill Martain/Qwest stated that there are occasionally PCAT updates needed for a systems change. Terri Kilker/Qwest stated that it is a reasonable request to have the dates match. Bonnie Johnson/Eschelon stated that the request was that if the systems piece was not implemented, they wanted the Product Process CR implemented in a timely manner. Bonnie stated that she would like Qwest to commit to the December 17th date, in the body of the CR, in case the date on the systems CR gets pushed out. Kathy Stichter/Eschelon stated that she does not have a problem with the December date and noted that the 2 CRs are separate requests. Kathy stated that she understands that Qwest wants to work them together but also sees no problem in implementing the Product Process CR in December if the system CR gets pushed out. Kathy stated that she is leery about putting the process changes in the systems CR. Liz Balvin/Covad stated that any systems CR requiring a process change should be done at the same time, but it is cleaner to keep them separate. Kathy Stichter/Eschelon stated that some orders do not flow through and needs a process that will train folks of what to do with those orders. Liz Balvin/Covad stated that if a system change is not going to implement for several years, the process piece needs to be done sooner then the systems piece. Bonnie Johnson/Eschelon stated that the current manual piece will continue to be manual after the system CR goes in and that makes this one a little different. Terri Kilker/Qwest stated that there are products that currently do not flow through and will continue to not flow through after this CR is implemented. Terri asked if Eschelon’s expectation was if the systems CR gets pushed out, that the manual process would cover the products that currently do not flow through. Kathy Stichter/Eschelon said yes. Jill Martain/Qwest stated that both the Product Process and the Systems CR would remain open with the targeted date of December 17th. Jill then noted that this CR moves to Development Status.

August 17, 2005 Monthly Product Process CMP Meeting discussion: Terri Kilker-Qwest stated that we are beginning the development portion on the systems CR and have identified the products that will require the addition of the WTN behind the NRCs. Terri stated that the systems CR may be targeted for April 2006. Terri then asked if this Product Process CR was still needed. Jill Martain-Qwest asked how firm the April 2006 date was. Terri Kilker-Qwest stated that it is a targeted date and that may know more in September. Jill Martain-Qwest stated that Qwest is still evaluating this Product Process CR, pending the firm implementation date for the Systems CR Kathy Stichter-Eschelon stated that if the date for the systems CR is April 2006, that they cannot wait that long to implement the Product Process CR, with the Systems CR. Bonnie Johnson-Eschelon asked to confirm that the date for the Systems CR was April 2006. Terri Kilker-Qwest stated that it is currently targeted for April 2006, but noted that it could change. Bonnie Johnson-Eschelon asked if there were many pieces to the request. Terri Kilker-Qwest stated that several back-end systems are involved. Bonnie Johnson-Eschelon asked if that was for the April 2006 date. Terri Kilker-Qwest said yes. Jill Martain-Qwest stated that the April 2006 targeted date is not yet a firm date. [Comment received from Eschelon: and we would wait to see target date. Jill said there could be room in other releases so Qwest could bring it in then.] Terri Kilker-Qwest stated that she would like to note that the manual piece is very small and that the majority of the impacted products do flow through. Terri stated that the real benefit is with the systems CR and not with the manual piece. Terri stated that because the manual piece will provide a smaller benefit, for products that do not flow-through; it does not make sense to implement the manual process prior to the system change. Terri stated that we need to ensure that not everything can be dropped for manual handling in order to get the WTN on the order. Bonnie Johnson-Eschelon stated that she understood that for the products that do flow through but there are products that don’t flow through and noted that they could be more than it appears. Kathy Stichter-Eschelon asked if more would be known in September, as far as the date goes. Jill Martain-Qwest stated that we are working towards that. [Comment received from Eschelon: but cannot guarantee Qwest will have a target date in September.] Kathy Stichter-Eschelon stated that if they don’t get anything this month, another month to start the Product process piece is a concern. Jill Martain-Qwest stated that we are working to get the date and noted that she does understand the concern for the systems and the Product Process efforts. This CR remains in Evaluation status.

- July 20, 2005 Monthly Product Process CMP Meeting discussion: Jill Martain-Qwest stated that there is a System CR associated with this CR. She said that we have the LOE for the System CR and would like to withdraw this CR. Jill said that we can accommodate both the manual and system work on the same CR. Kathy Stichter-Eschelon said that she did not understand why they had to wait on the manual piece. Jill Martain-Qwest said that we prefer to implement at the same time from a consistency perspective. Kathy Stichter-Eschelon said that they prefer to have the manual piece implemented. Jill Martain-Qwest said that the manual piece would only take care of the manual orders and that the flow through orders would not be supported. Kathy Stichter-Eschelon asked when this CR could be implemented. [comments to minutes from Eschelon 7/28/05: Kathy Stichter-Eschelon said she could not agree to wait to implement the process CR until the systems CR is worked and asked when the systems CR could be implemented.] Jill Martain-Qwest stated that she did not know at this point but that she would check. Jill said that this is the only billing CR. Liz Balvin-Covad asked if there was a way to implement the manual process. Jeff Sonnier-Sprint asked if Qwest could identify the orders that would drop to manual. Liz Balvin-Covad asked what products this CR impacted. Kathy Stichter-Eschelon said this request impacts TN based products. Jill Martain-Qwest said that we will look at when the system piece can be implemented and then decide on the manual piece. She said that Qwest will work offline with Eschelon and that this CR will remain in Evaluation Status.

- June 22, 2005 Email Received from Eschelon: Peggy, My intent was that this would be going forward. Thanks Kathy Stichter

-- June 21, 2005 Email Sent to Eschelon: Hi Kathy, We have been meeting internally to discuss the change requests asking that the WTNs be provided with NRCs and would like clarification on one item. Can you clarify if Eschelon's intent is that this effort be done only on a going forward basis? This will assist us in the scope of this request and ensure that our discussions have the correct focus for these requests. Thanks, I appreciate the information. Peggy Esquibel-Reed Qwest CMP CRPM

-- June 15, 2005 Monthly Product Process CMP Meeting discussion: Terri Kilker-Qwest stated that this CR is in Evaluation status and noted that Qwest is in the process to identify which products need to be included in this effort, other than TN based and non-design products. Terri stated that a status would be provided at the July CMP Meeting. Jill Martain-Qwest stated that this CR would move to Evaluation status.

May 18, 2005 Monthly Product Process CMP Meeting discussion: Kathy Stichter-Eschelon stated that Eschelon submitted a Product Process CR and a Systems CR. Kathy stated that the Product Process CR is for orders that are manually handled. Bonnie Johnson-Eschelon stated that it was noted on the Clarification Call that Eschelon feels that they should not have to issue a CR to get an accurate bill and stated that she would appreciate expeditious care for this CR. Liz Balvin-Covad asked Eschelon if they were not receiving a TN at all. Kathy Stichter-Eschelon stated that this request is for TN based products and not for those with circuits. Kathy stated, for example, that if there are 5 TNs on an account, they would get 1 NRC and it shows the BTN, which is fine. Kathy stated that the other 4 are then lumped together without the actual lines being identified. [Comment from Eschelon: Kathy said Qwest told her that flow through orders are not created to show the TN. Bonnie Johnson-Eschelon asked Kathy to verify that with some products it does show up. Kathy confirmed that some products that are manually typed have the information.] Liz Balvin-Covad stated that they are required to identify them on the orders. [Comment from Eschelon: Liz Balvin-Covad stated that this is a substantial issue if Qwest is not carrying this information through to billing and required to identify them on the bill.] Jill Martain-Qwest stated that Qwest is reviewing the requests to see what can be done. Jeff Sonnier-Sprint asked if this was just recently beginning to happen. Kathy Stichter-Eschelon stated that it was just brought to her attention but did not know if it is a recent problem. Jeff Sonnier-Sprint stated that if it is a recent problem that it should be a maintenance issue and not a CR. Jill Martain-Qwest stated that it is not a recent issue and noted that the team is looking into the request to determine what options we have. This CR moved to Presented Status.

May 13, 2005 Clarification Meeting SCR050405-04 / PC050405-1 Provide Individual WTNs (Working Telephone Number) with All NRCs (Non-Recurring Charge)

Attendees: Kim Isaacs-Eschelon, Kathy Stichter-Eschelon, Stephanie Prull-Eschelon, Peggy Esquibel Reed-Qwest, Terri Kilker-Qwest, Alan Zimmerman-Qwest, Jami Larson-Qwest, Brenda Kerr-Qwest, Jim Recker-Qwest

Review Requested (Description of) Change: Peggy Esquibel Reed-Qwest reviewed the CR Title and Description. Both CRs contain the same title and description. Peggy asked Eschelon if they had additional information to share and asked for Eschelon to explain the differences in these requests. Kathy Stichter-Eschelon stated that the Product Process CR was submitted requesting that the WTN be added to the service order manually for the situations where it cannot be added mechanically. Kathy stated that the Systems request is for an edit. Kathy stated that if an edit were placed in the SOP, then the Product Process CR would not be needed. Terri Kilker-Qwest asked to confirm that if the ability to apply this to the order was provided, that it would eliminate the manual process. Kathy Stichter-Eschelon stated that when Eschelon asked their Service Manager about this, they said that the SDC does not float the WTN behind the NRC USOCs. Kathy Stichter-Eschelon stated that their ICA states that Qwest will provide an accurate bill and without the WTN with the USOC Qwest does not provide an accurate bill. Kathy stated that the current bill shows a quantity of 4 instead if displaying them separately. Kathy stated that was not an accurate bill so a CR should not be necessary from Eschelon. Peggy Esquibel Reed-Qwest stated that she would note Eschelon’s statement. Stephanie Prull-Eschelon asked if there was a system limitation to add the WTN or if there was just no edit or process. Terri Kilker-Qwest stated that there was not for UNE-P and that for PBX, the process was automatically written. Terri noted that this would require edits for flow through and that the other manual process would need additional processes developed. Stephanie Prull-Eschelon asked if this could manually be done and asked to confirm that there just was not a current process in place. Terri Kilker-Qwest said correct. Kim Isaacs-Eschelon stated that their ICA states that they are to get a correct bill and asked if this should be a defect and treated as such. Alan Zimmerman-Qwest stated that Qwest and Eschelon won’t agree on the interpretation of the ICA and noted that Qwest believes that a correct bill is provided. Peggy Esquibel Reed-Qwest asked if this request was specifically for BillMate. Kathy Stichter-Eschelon stated that the CRIS should hit all output. Stephanie Prull-Eschelon stated that the expectation is that it should flow through to all FTP Files. Teri Kilker-Qwest asked to confirm that this request is for Resale, UNE, and UNE-P. Kathy Stichter-Eschelon stated that it is for any product that is TN based, not for UNE Loops or designed circuits. Stephanie Prull-Eschelon asked if the current process, for UNE-P PBX, was established internally to make things easier. Terri Kilker-Qwest stated that only one person established the process and is using it for their own product. Terri noted that this person just started doing it. Kathy Stichter-Eschelon stated that it would be easier for the SDCs to explain the charges if they had the associated TN with the USOC. Peggy Esquibel Reed-Qwest asked if there were any additional questions or comments. There were none brought forward. Peggy then stated that this CR is scheduled for presentation at the May CMP Meeting and that Qwest would internally review the requests.


CenturyLink Response

For Review by the CLEC Community and Discussion at the June 15, 2005 CMP Meeting

June 6, 2005

Kathy Stichter Eschelon

SUBJECT: CR # PC050405-1 Provide individual WTNs (Working Telephone Number) with all NRCs (Non-Recurring Charge)

This letter is in response to Eschelon's Change Request PC050405-1 Provide individual WTNs (Working Telephone Number) with all NRCs (Non-Recurring Charge). This CR requests a manual process for the WTN to be provided for each Non-Recurring USOC on a service order. This effort will assist in validation of the bills.

Qwest would like to place this CR in evaluation status in order to continue with analysis of this request and look at viable solutions for this change request. Qwest will provide an updated response at the next CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely, Qwest


Open Product/Process CR PC022105-1 Detail

 
Title: ASR Initial Jeopardy Sent to E mail Address on ASR
CR Number Current Status
Date
Area Impacted Products Impacted

PC022105-1 Denied
7/29/2005
Ordering, Provisioning, Delayed Orders All Local ASR Products
Originator: Johnson, Bonnie
Originator Company Name: Eschelon
Owner: Sunins, Phyllis
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest will send the initial jeopardy for an ASR to the E-mail address the CLEC provides on the ASR. If the E-mail address is blank, Qwest will call the number listed on the ASR with the information. Please see PC070804-1. This CR is part of a formal process because Qwest could satisfy only a part of the CR. Business needs are included in that CR.

Expected Deliverable:

Qwest will develop, document and adhere to a process to send the initial jeopardy for an ASR to the E-mail address the CLEC provides on the ASR.


Status History

02/21/2005 - CR Submitted

02/21/2005 - Related Change Request, PC070804-1, will move to Deferred Status at March CMP.

02/22/2005 - CR Acknowledged

3/3/05 - Discussed with Bonnie Johnson that this CR will implement the work that was agreed to on PC070804-1. The work that Qwest was not able to implement will be deferred using PC070804-1. This CR will be discussed at the March meeting and moved to Development status as the work is in progress as a result of PC070804-1.

3/16/05 - CMP meeting minutes will be posted to the database

4/20/05 - CMP Meeting minutes will be posted to the database

5/18/05 - CMP Meeting minutes will be posted to the database

6/15/05 - CMP Meeting minutes will be posted to the database

6/14/05 - Level 3: PROS.06.14.05.F.02992.Re-Notice_ProvisioningV64 effective 7-29-05 and NonCMP: PROS.06.14.05.F.02993.Re-Notice_IXC_WSP_JEP

6/05 Sent test email to Eschelon, SBC and Covad

7/20/05 - CMP Meeting minutes will be posted to the database

7//29/05 - changed status to CLEC Test

8/17/05 - CMP Meeting minutes will be posted to the database

9/13/05 - Send Response to Eschelon

9/21/05 - CMP meeting minutes will be posted to the database


Project Meetings

PC022105-1 ASR Initial Jeopardy Process Ad Hoc Meeting October 20, 2005

In attendance: Kim Isaacs – Eschelon Sharon VanMeter – ATT Jeff Yeager – Accenture Diane Friend – Time Warner Sue Wright – XO Jeff Sonier – Sprint Jill Martain – Qwest Liz Balvin – Covad Phyllis Sunins – Qwest Cindy Harlan – Qwest Stephanie Prull – Eschelon Bob Eggert – SBC

Cindy Harlan – Qwest advised that Eschelon requested this ad hoc meeting to discuss the differences between the CNR Jeopardy Process and the ASR Jeopardy Process as it relates to the manner in which Qwest notifies the CLEC of the Jeopardy condition.

Kim Isaacs – Eschelon reviewed the history of the CRs and stated that the CLEC Community believes there is a business need to make changes to this process. QORA does not allow the CLEC to see when an order is in jeopardy status. Kim advised that we do not understand how a change can be made to the CNR process and not the ASR Initial Jeopardy process.

Phyllis Sunins – Qwest discussed some of the detailed steps for each process and explained the differences between the two processes. Basically, these two processes are not the same as different people perform each process, different systems are used to perform / track the process, different functions are performed for a CNR jep and an ASR Initial Jep, and each process has different time frames. Phyllis further explained that the change that was made to the CNR process was impacted due to the ASOG 31 release effective October 10. The CNR process was using an industry field on the ASR form. This field was removed effective with ASOG 31 release, so Qwest had to make a change to the process to support the Industry change.

Bob Eggert – SBC asked if there is any way that Qwest can make enhancements to these tools. Jill Martain – Qwest stated that at the October CMP meeting we agreed to look at QORA platform capabilities and see if that helps with these issues. Kim Isaacs – Eschelon said that she is concerned that they asked for this quite some time ago, and now we are saying that we may be able to do this. That would be great but it is concerning. Jill said Qwest did not purchase this functionality so it was not available.

Phyllis asked if there were any additional questions. The CLEC community had no further questions.

September CMP Meeting Minutes: Phyllis Sunins/Qwest advised that we implemented this change on 7-29-05 and the CR remained in CLEC Test for the following month. She said that during the CLEC Test cycle we determined the manual process was very resource intensive and delayed other steps in the jeopardy process. Phyllis said that at the August CMP meeting we agreed that we would change the process back to the original process, issue a Level 3 notification, and a denial on this CR. She said that Qwest also agreed to look at the manual process to see if there was anything that could be done. Phyllis advised that because we have customers that objected to the process and because it was optional we had to create multiple processes, the cost to mechanize this process is economically not feasible as documented in response to the System CR SCR030204-04. She said that we are denying this request based on the costs to implement the process.

Bonnie Johnson/Eschelon said that she didn’t believe that there was necessarily CLEC agreement, but did understand from the last meeting that Qwest was retracting the process. Bonnie said that we need to care for this situation in the CMP document. She said that this needs to be denied, if Qwest is not going to implement the process.

Liz Balvin/Covad advised that she is disappointed, as Qwest is doing manual work today and we should look at mechanizing this. Liz advised she appreciates the creative thinking and hopes that Qwest continues to look outside of the box to try to alleviate some of our own pain and manual work.

Jill Martain/Qwest advised that the costs don’t make it feasible for Qwest to implement this. She said that we would have to totally mechanize this to be effective. Jill asked Bonnie if she is looking for a specific section of the CMP document to be updated. Jill advised that we have changed the project to denied. Jill said that this is a unique situation and it should be an anomaly. Bonnie advised that she is concerned that this will set precedence and that Qwest will decide later that we can’t implement a change that we already agreed to. Bonnie advised if we are faced with this again than we will have to discuss how to handle this. She said that she was not sure that in the future she would agree to allow Qwest to deny the change after the fact.

This CR will move to Denied Status.

August CMP Meeting Minutes:

Jill Martain – Qwest said during the CLEC Test cycle this CR has been difficult for Qwest to implement. The manual work involved has been very resource intensive. We are finding that it is delaying other steps in the jeopardy process. Qwest will need to issue a Level 3 notification to revise the process to what it was previously. At this time, we don’t know how we can manage this process as the time and effort to put the manual notices out are too resource intensive. Jill explained that we have not been in this position before, and shared two options for what Qwest can do with the actual CR. Option 1 – Issue Level 3 to change the process and close the CR, or Option 2 – Issue Level 3 to change the process and deny the CR. Bonnie Johnson – Eschelon advised that she will have to think about how we should handle this. If the end result is we are not going to implement the process as we agreed, then it should be denied. Bonnie asked if there is any opportunity for the System CR to be worked. Are any changes to QORA possible? Bonnie said that originally the CR was denied for economic infeasibility, but maybe this can be looked at again. Jill Martain – Qwest advised that we can look at it again, but it probably isn’t feasible. Bonnie advised that Qwest needs to put something in the CMP document to cover this situation, such as a new category of Reversed, or the CR should be denied. Liz Balvin-Covad advised she does not understand why the level of effort has become overwhelming. Jill Martain advised it is a compounding effect based on the volumes and the additional steps and manual work for the resources to fill out the notice. The process sounds easy but when you look at the volume it adds small steps and delays other steps along the way, putting critical tasks at risk. Liz Balvin asked if there was a way to have one point of contact per CLEC entity. Jill Martain-Qwest advised that it is not the same email address all of the time. It is potentially a different person per order. Liz Balvin-Covad advised that the CLECs like the idea of having a tracking method. [Comment received from Eschelon: Covad was very excited when this process was implemented.] Jill Martain-Qwest advised we will go back and do some research on the systems work. Bonnie Johnson-Eschelon asked that maybe we can mechanize just the initial jeopardy step. The previous system denial was for the entire process, so maybe if we just mechanize the initial jeopardy it would make a difference.

Liz Balvin-Covad asked if maybe we could just mechanize the email itself as it appears the email is a well liked process. Jill Martain-Qwest advised we will talk to the team internally and see if there are any options that can be addressed.

July CMP Meeting Minutes: Jill Martain – Qwest advised that this process is in effect on July 29, 2005 and Qwest sent the test emails to Eschelon, Covad and SBC.

Liz Balvin – Covad asked if they could send another test email to someone in their organization.

Cindy Harlan - Qwest advised yes, please just send me their email address and we will take care of that.

Jill Martain - Qwest asked if we could move this to CLEC Test on 7/29.

Kim Isaacs – Eschelon agreed that it is okay to move to CLEC Test on 7/29.

June CMP Meeting Minutes: Jill Martain – Qwest advised this process is effective July 29. Qwest anticipates that we will be able to test the mailbox sometime the week of June 27. Bob Eggert – SBC asked if Qwest would have a standard email response for the email jeopardy. Bob advised the subject line needs to be standard and something that everyone can support to prevent the emails from being rejected as SPAM. Cindy Harlan – Qwest advised that we did receive the email suggestion that Bob sent in and appreciated the suggestion. Cindy advised that our Process Specialist is in the process of creating the standardized email form. The CLECs suggested that we make the Subject line of the ASR Jeopardy to be as follows: ASR Jeopardy Notice PON# XXXX. Cindy advised that it is expected that these emails will come from one common email mailbox with a qwest.com address. Cindy will verify this information with the Process Specialist and advised Bob Eggert – SBC. This CR will remain in Development Status.

May CMP Meeting Minutes: Phyllis Sunins-Qwest advised that the PCAT should be available for review on 5/23/05, with a comment cycle from 5/24/05 to 6/7/05 and implementation scheduled for 7/7/05. Phyllis advised that Qwest would like to test the group mailbox that was set up for this effort with a couple CLECs. Bonnie Johnson (Eschelon) and Liz Balvin (Covad) advised that they would be glad to participate. Phyllis Sunins-Qwest advised that Cindy Harlan (Qwest) would contact them in the near future to arrange for the test. Phyllis then confirmed that for the test we would need orders submitted via ASR that have jeopardy conditions.

April CMP Meeting Minutes Jill Martain – Qwest advised we are moving forward to develop this process internally. Jill said that we hope to have the timelines for implementation next month.

March CMP Meeting Minutes Jill Martain - Qwest advised that this CR was submitted by Eschelon to implement the initial jeopardy as discussed on PC070804-1. Qwest is working internally to get this implemented. This CR will move to Development Status.

February CMP Meeting Minutes/Clarification: Cindy Harlan - Qwest advised that Qwest held an ad hoc call on Monday February 14. The purpose of the call was to review Qwest's proposed process and obtain a decision from the CLEC community regarding whether to move forward or defer the CR. Bonnie agreed that she would provide a decision at the February CMP Meeting. Bonnie Johnson - Eschelon reported at the February CMP meeting that she took this back internally and would like to move forward implementing the email on initial facility jeopardy notifications. Bonnie advised that she is deciding how she wants to move forward with the CR. There was some discussion around either moving forward with the existing CR or deferring the existing one and creating a new one. Bonnie advised that she does not want to loose the work that has been done as the CLECs may want to revisit this, if something changes at Qwest as it may be possible to implement the rest of this CR at a later time. Cindy Harlan - Qwest advised we can work together to determine how to implement some of the work and defer the rest. Liz Balvin-Covad asked who would receive the email jeopardy. Jill advised an email address needs to be populated in the initiator field on the ASR and that is where the email jeopardy would be sent. Jill advised that Qwest has internal work that needs to be done to implement this. This CR will remain in Development Status.


CenturyLink Response

September 13, 2005 For Review by the CLEC Community and Discussion at the September 21, 2005 CMP Meeting

To: Bonnie Johnson, Eschelon

Subject: PC022105-1 ASR Initial Jeopardy Sent to Email Address on ASR

Description of Change: Qwest will send the initial jeopardy for an ASR to the E-mail address the CLEC provides on the ASR. If the E-mail address is blank, Qwest will call the number listed on the ASR with the information.

Qwest Response: Qwest implemented this change effective July 29, 2005. The CR remained in CLEC Test status for 30 days after implementation. During the CLEC Test cycle it was determined that this CR is very resource intensive. Qwest found that this process is delaying other steps in the jeopardy process.

As agreed during the August CMP Meeting, Qwest advised that they will issue a Level 3 Notification to reinstate the process to the way it was previous to this CR. (Qwest will reinstate the process to contact the CLEC via phone call, instead of using E-mail PROS.09.07.05.F.03226.ProvisiongASRJEP effective October 22, 2005). Qwest also agreed to look at the manual steps involved in this process to see if there are any changes that can be made to eliminate the resource impact.

Qwest reviewed possible options for mechanizing the email portion of the ASR jeopardy process. Based on the multiple steps required in this process, mechanizing the email portion of the ASR jeopardy process would not reduce the manual effort to a level that provides a reasonably demonstrable business benefit. In addition, the cost to implement the multiple process and system changes is economically not feasible as determined previously in SCR030204-04. Qwest is denying this request due to economic infeasibility, based on the costs to implement the multiple process and system changes required.

Sincerely, Qwest


Open Product/Process CR PC122606-1X Detail

 
Title: Change EUMI Field and End User Address Requirements for Port Within Ordering Process #1 to avoid CLEC LSR Submission Errors and Qwest Reject in Errors (cross over from SCR122606 01)
CR Number Current Status
Date
Area Impacted Products Impacted

PC122606-1X Completed
6/20/2007
Ordering LNP
Originator: Isaacs, Kim
Originator Company Name: Eschelon
Owner: Coyne, Mark
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Qwest’s current Port Within Ordering Process number #1 states: End-user has existing Qwest Retail/Resale/UNE-P POTS Account, End-user moving to new location, Conversion to a New Resale/UNE-P Provider, Move existing TNs, Different C.O., Same Rate Center, New Facilities (Includes conversion from RSID to ZCID or ZCID to RSID):

Instructs CLECs to populate the EUMI Field = N (even though the end user is moving) and provide the new address in the remarks and drop the order to manual handling. When Qwest implemented this process, Eschelon commented that it is counter-intuitive and may cause unnecessary delays for some Port Within requests. Over the past year, Eschelon has experienced a number of Qwest rejects in error when populating the EUMI =N and the Old Address on the End User Form as instructed by the Port Within Ordering Process Number #1. Eschelon has provided the rejects in error to our service management team but the rejects in error continue to occur. For example, in December, Eschelon opened the following escalation tickets to have Qwest correct rejects in error: 26015615, 26017558. This is delaying LSR processing and costing both Eschelon and Qwest valuable resources to open escalation tickets for each occurrence. Therefore, Eschelon is requesting the Qwest update the EUMI Field requirements to support an EUMI = Y with the new address on the End User Form when a CLEC requests a Port Within Conversion and Move (Port Within Ordering Process Number #1). Thank you.

EXPECTED DELIVERABLE:

Qwest will update the EUMI Field requirements to support an EUMI = Y with the new address on the End User Form when a CLEC requests a Port Within Conversion and Move (Port Within Ordering Process Number #1).


Status History


Project Meetings

June 20, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was implemented on May 11th and asked if this CR was okay to close. Kim Isaacs-Eschelon said yes. This CR is now in Completed Status.

May 16, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was another cross over from Systems and will be implemented on May 11th. Mark stated that this CR is currently in CLEC Test and asked if there were any questions. There were no questions. Mark then noted that Qwest would be looking to close this CR next month.

- April 18, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this Eschelon CR was also crossed over from Systems in the March CMP Meeting. Mark then noted that a Level 3 Notice was sent on March 29th and that this change will become effective on May 11, 2007. Mark stated that no comments were received during the comment cycle. Mark stated that this CR would be moved to CLEC Test on May 11th. Mark asked if there were any questions. There were none brought forward.

- March 21, 2007 Product Process CMP Meeting: Venessa Heiland-Qwest stated that Eschelon had stated that it is counter intuitive when an EUMI=N is used when the end user is moving. Venessa stated that this request was investigated and noted that there is a current process in place for EUMI=Y and that these port scenarios could be added to that existing process. Venessa stated that this CR will be accepted as a process change and that the CR would cross over to the Product Process area. Venessa then noted that there would be an update to the PCAT to accommodate this requested change. Mark Coyne-Qwest asked if there were any questions. There were none. This CR is crossed over to Product Process and is in Presented status.

Date: March 6, 2007 Proposed Process Solution Meeting: ATTENDEES: Kim Isaacs-Eschelon, Peggy Esquibel Reed-Qwest, Venessa Heiland-Qwest DISCUSSION: Peggy Esquibel Reed-Qwest stated that this meeting is for Qwest to propose a Process Solution for this systems submitted CMP CR. The proposed solution was briefly discussed in the February CMP Meeting and Venessa would like to discuss it with you today. If there is no objection to the proposed solution, the CR will be crossed-over to a Product process CR and proceed down that path. Venessa Heiland-Qwest stated that there is an existing process for EUMI=Y and stated that it requires ACT=V and that the customer code be provided. Venessa asked if that same process would work for this request and asked if Eschelon saw any stumbling blocks to this solution. Kim Isaacs-Eschelon stated that the proposed solution would work. Venessa Heiland-Qwest stated that this would then be a documentation change and would proceed as a process change. Venessa stated that the old address would then be placed in Remarks. Kim Isaacs-Eschelon asked if the proposed solution would alter the auto population of the LSO on the End User Form or would impact it. Venessa Heiland-Qwest said no. Kim Isaacs-Eschelon noted that the proposed solution would also benefit Qwest. Venessa Heiland-Qwest stated that it would benefit Eschelon, Qwest, and the rest of the CLECs. Kim Isaacs-Eschelon stated that she agreed. Venessa Heiland-Qwest then noted that the typists would not need to look-up which process to use, there would be just one consistent process. Kim Isaacs-Eschelon then stated that the proposed solution would work for Eschelon. Peggy Esquibel Reed-Qwest stated that a Process CR would then be created and that the cross over, to Product Process, would be done during the March Monthly CMP Meeting. The call was concluded.


Open Product/Process CR PC072505-1X Detail

 
Title: Cable Pair & Binding Post Identification (CR Crossed over to SCR072505 1X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC072505-1X Crossover
2/20/2013
Ordering UNE-P, Resale
Originator: Lynn, Lisa
Originator Company Name: Granite Telecommunications
Owner: Martinez, Denise
Director:
CR PM: Lorence, Susan

Description Of Change

1/2/2013 UPDATE: Receive the identification of Cable Pair and Binding Post information upon Completion not when the order reaches Confirmed status.

Product types: We use the C/P/BP information for POTs; Centrex; Trunks and Resale. Please note this is not currently needed for T1s.

*****Original CR

Identification of cable pair and binding post information when the order reaches confirmed status (FOC). The cable pair and binding post information is currently provided via repair after the order is completed.

Expected Delivery:

ASAP


Status History

07/25/2005 - CR Submitted

07/25/2005 - CR Acknowledged

07/25/2005 - Email Sent to Granite Telecomm, Requesting Clarification Meeting Availability

08/04/2005 - Clarification Meeting Held. See Project Meetings Section for Meeting Minutes.

08/17/2005 - Discussed in the Monthly Product Process CMP Meeting

09/21/2005 - Discussed in the Monthly Product Process CMP Meeting

10/19/2005 - Discussed in the Monthly Product Process CMP Meeting

10/25/2005 - CMPR.10.25.05.F.03416.AdHocMeeting_PC072505-1

11/01/2005 - Ad Hoc Meeting Held

11/16/2005 - Discussed in the Monthly Product Process CMP Meeting

12/07/2005 - CR Placed in Deferred Status, at the Request of the CR Originator

12/14/2005 - Discussed in the Monthly Product Process CMP Meeting


Project Meetings

03/20/13 Product/Process CMP Meeting Mark Coyne - CenturyLink said there were no remaining CLEC CRs under Product and Process but relayed to call participants that the Granite CR PC072505-1, Cable Pair & Binding Post Identification, was crossed over to Systems last month and will be talked about under the Systems package.

02/20/13 Product/Process CMP Meeting Mark Coyne - CenturyLink reviewed the background on this CR: Granite had revised the CR in early January to receive the Cable Pair and Binding Post information upon Completion instead of at Confirmed status; CenturyLink subsequently sent a draft response for Granite to consider using CEMR since the information was available there today; Granite then responded requesting that CenturyLink move forward with the CR to modify IMA and that Granite would use CEMR as an interim solution. Based on that, Mark reviewed the response that CenturyLink had sent that proposed that the CR be crossed over to a System CR to evaluate a system solution with the hope of providing an LOE at the March meeting.

Tracy Strombotne – CenturyLink asked what would be the new system CR number.

Mark Coyne – CenturyLink said the new CR would be SCR072505-1X. Mark asked if there were any additional questions. There were none.

1/16/13 Product/Process CMP Meeting Mark Coyne - CenturyLink said this was a CR that was on the Deferred list. Granite Telecommunications re-presented the CR last month. Then on January 2, Lisa Lynn, Granite, revised the CR to request the identification of Cable Pair and Binding Post information upon Completion not when the order reaches Confirmed status. In addition, the product types were updated to request the information on POTs; Centrex; Trunks and Resale. Considering the revised CR, CenturyLink sent a draft response on January 9 to request Granite consider using CEMR for cable pair and binding post information since it is available there today. This requested content is available immediately vs. revising IMA. Mark said that since Granite was not on the call today, we would contact them to determine if they had considered the CenturyLink proposal. If so, CenturyLink will request moving the CR to a Completed status next month. Mark asked if there were any questions.

Kim Isaacs – Integra questioned whether a status of Completed was the appropriate status for the CR since the CR was originally requesting the functionality in IMA.

Susan Lorence – CenturyLink said we could approach Granite to revise the CR to indicate that getting the cable pair information from CEMR was sufficient since the capability that was being requested was available.

Kim Isaacs – Integra said OK.

There were no other questions.

12/12/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said this was a CR that was on the Deferred list. CenturyLink had contacted Granite Telecommunications who indicated they wanted to move forward with it. As the CenturyLink SME team reviewed the CR, there were some questions about the CR since it had been so long since the CR was active.

Lisa Lynn – Granite Telecommunications presented the CR again. The main reason for the CR was to identify where the line is for their wire techs. Lisa said the products impacted are POTS, Centrex, Trunks and T1s.

Denise Martinez - CenturyLink said in the original description of the CR, the request is for the information to be provided at the FOC. Denise said that at FOC, there could be subsequent changes in the assignment. Denise asked if it was OK to send the information at completion instead as that was more appropriate.

Lisa Lynn – Granite Telecommunications said she would have to check.

Jamal Boudhaouia - CenturyLink said from a network perspective, the information cannot be relied on until completion as CenturyLink may find that the initial facility assignment prior to completion may not be suitable and they may be changed.

Denise Martinez - CenturyLink requested confirmation that the only information being requested was the Cable Pair & Binding Post Identification.

Lisa Lynn – Granite Telecommunications said yes.

Kim Isaacs – Integra asked if this was for resale products only instead of unbundled loop.

Lisa Lynn – Granite Telecommunications said not just resale but also unbundled loop.

Kim Isaacs – Integra said the demarc information is in CEMR when the order completes but was not sure if the cable pair and binding post information was always there currently. (12/19/12 Updates received from Integra in CAPS) IT SHOULD BE QUITE EASY TO ADD CABLE AND PAIR INFORMATION IN CEMR OR BRING IT OVER TO THE COMPLETION NOTICE. Jamal Boudhaouia - CenturyLink said that was a good point and that we would investigate that.

Mark Coyne – CenturyLink asked if there were any additional questions. There were none. Mark confirmed that Lisa would investigate the open questions and get back with CenturyLink so we can proceed with the evaluation of the CR.

11/14/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said this was a CR that was on the Deferred list. CenturyLink contacted Granite Telecommunications to see what they wanted to do with the CR and the response was that they wanted to move forward with it. Granite was unable to make the CMP call today to re-present the CR and answer questions from the SME team about the intent. Mark said we will either have an ad hoc within the next couple weeks or will review the CR in the December CMP meeting. Mark asked if there were any questions; there were none.

10/17/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said this was a CR that was on the Deferred list several months ago and that CenturyLink is following up with Granite Telecommunications to check on this CR. He said we will propose moving this CR to Pending withdrawal in the November meeting.

08/15/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that in the July meeting, CenturyLink had asked the owner of each Deferred CR to determine if it should remain in Deferred status, is it should be Withdrawn, or whether it should be re- evaluated. Mark then reviewed the status of each CR as listed on the Attachment:

PC072505-1 - Cable Pair & Binding Post Identification – Still under investigation.

March 17, 2006 Email Sent to Granite: Hello Lisa, This email is just to follow-up on your submitted CMP CR to Qwest. The CR is PC072505-1 Cable Pair & Binding Post Identification. The CR is currently in Deferred status, awaiting your decision as to whether Qwest's proposed solution is acceptable to Granite. Please let me know if you have made your decision and what that decision is. If you have not yet made your decision and need more time, let me know that as well. The CR can remain in Deferred status until you are ready. Thank you, Peggy Esquibel-Reed Qwest Wholesale Change Management

- December 14, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this CR is pending the decision from Granite, to see if they would accept Qwest’s proposed solution. Jill noted that Granite has requested that the CR be placed in Deferred Status until they can do some testing internally and make their decision.

Bonnie Johnson/Eschelon stated that Eschelon has an interest in sponsoring this CR if Granite chooses to withdraw their request. Bonnie stated that she did not want the effort stopped. Jill Martain/Qwest stated that the effort is not stopping, Granite just wanted to perform some internal tests before they decide whether Qwest’s proposed solution would work for them. Jill stated that Qwest would continue to follow-up, with Granite, and once they make their decision, the CR would move out of deferred status and would be back on the agenda for discussion at CMP.

December 7, 2005 Email Received from Granite: Hi Peggy, Thanks for your assistance. I hope to contact you in the near future. Happy Holidays. Lisa

-- December 7, 2005 Email Sent to Granite: Hi Lisa, It may be better to place the CR in Deferred Status...for now. Once you make your decision, please let me know and we can then take it out of Deferred Status and see what you want to do regarding the proposed solution. There is no set amount of time that the CR must remain in Deferred; so if you have your decision soon, we can remove it from Deferred and proceed with the next step, at that time. Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

December 7, 2005 Email Received from Granite: Hi Peggy, Thanks for your quick response. Apparently, we have to test "how the messages come in, how big they are, if our system can support it". At this time, our team is not ready to do this. Would it be best to put the CR in deferred status until we take this preliminary step? Thanks, Lisa

-- December 7, 2005 Email Sent to Granite: Good Morning Lisa, Thanks for the email. I am a little confused as to what you plan to test. There have been no changes, and nothing implemented so far, as a result of this CR. This CR can’t be implemented until we know which path to pursue and that is based on your accepting the proposed solution or not accepting it. If it is Granite’s preference, we can place the CR in a Deferred Status until you make your decision. Let me know. Thanks much, Peggy Esquibel-Reed Qwest Wholesale CMP

-- December 7, 2005 Email Received from Granite: Hi Peggy, We will contact you as soon as we are ready to test the possible solution. Again, thanks for all of your assistance. Thanks, Lisa

December 6, 2005 Email Received from Granite: Hi Peggy, I forwarded this email to get a response for you and unfortunately I didn’t get one. Let me try again and get back to you asap. Thanks for your diligent follow-up. Lisa

December 6, 2005 Email Sent to Granite: Hello Lisa - This email is a follow-up to see if Granite has made their decision regarding PC072505-1. Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

- November 30, 2005 Email Sent to Granite: Good Morning Lisa, This email is just to follow-up to see if you have made a decision to accept Qwest’s proposed solution for your CMP CR for Cable Pair and Binding Post Identification. Please let me know if the solution is acceptable so we can proceed with the development effort. If the proposed solution will not fit your need and is not accepted, let me know that as well. If more time is needed for you to make your decision, please let me know when the decision is anticipated. I appreciate it. Thanks much, Peggy Esquibel-Reed Qwest Wholesale CMP

- November 16, 2005 Monthly Product Process CMP Meeting Discussion: Denise Martinez/Qwest stated that the original request was that the Cable Pair and Binding Post information be provided on the FOC. Denise stated that Qwest investigated the request and determined that it could not be done via the FOC because the information is not yet available and a delay in the FOCs is not desirable. Denise stated that an alternate solution was presented to the CLEC Community, to provide the information via the PSON. Denise stated that at a minimum the PSON Header and a message indicating that there has been no activity would be provided. The majority of the PSONs would contain Cable Pair and Binding Post information. Denise then stated that the CLECs asked if the information could also be provided on the Completion Notice and noted that it could be. Denise stated that the information would be provided on both the PSON and on the Completion Notice. Denise stated that both Notices would contain a disclaimer that states that the assignments could change up to and including the Due Date. Denise stated that this solution was proposed and that it is pending the approval of the CR originator. Stephanie Prull/Eschelon asked why the Completion Notice would have a disclaimer when the order is already done at that point. Denise Martinez/Qwest stated that the same information is needed on both notices and that on the Completion Notice it would identify if there was a change to the assignments from when the PSON was issued. Bonnie Johnson/Eschelon stated that on the Completion Notice when the information is sent, because the order has completed, the information should not have changed. Bonnie asked if Qwest wanted the information from the PSON mirrored on the Completion Notice. Denise Martinez/Qwest said yes and stated that it is a snapshot at a different point in time of the process. Denise stated that there had been problems in the past in getting the notices in synch and would like to avoid that risk if can, of having them be different. Bonnie Johnson/Eschelon said that in reality, the information on the Confirmation Notice would not have changed. Denise Martinez/Qwest stated that it shouldn’t. Jill Martain/Qwest stated that there could be a timing issue that may result in the information being different. Denise Martinez/Qwest stated that in a rare instance, it could happen. Denise stated that more would be known when it is developed and tested. Jill Martain/Qwest stated that the CR remains in Evaluation, pending the approval of the proposed solution, from Granite Telecommunications.

November 9, 2005 Email Received from Granite: Hi Peggy, Our EDI group needs to do user and analyst testing and they have a few things ahead of this issue. We are estimating that it will be several weeks before the group can take on this project. Until then, there are no necessary next steps required of Qwest. We will keep you posted on the progress. Thanks for your assistance.

Lisa

November 4, 2005 Email Sent to Granite: Lisa, Thank you for meeting with us on November 1st to discuss the proposed solution for your submitted CMP CR for Cable Pair and Binding Post Identification. This email is a follow-up to see if the solution presented on that call is workable for you. If the proposed solution is acceptable to you and you would like us to proceed with that option, let me know so we can then proceed. Please let me know ASAP so we can determine next steps. Thanks much, Peggy Esquibel-Reed Qwest Wholesale CMP

November 1, 2005 Ad Hoc Meeting Minutes: ATTENDEES: Jeff Sonnier-Sprint, Joyce Philo-McLeod, Sharon Van Meter-AT&T, Bonnie Johnson-Eschelon, Jody Thompson-TDS, Stephanie Prull-Eschelon, Jennifer Arnold-TDS, Chelsea Payne-Mcleod, Rosalyn Davis-MCI, Kim Tosi-Granite, Lisa Mui-Granite, LouAnn Miller-McLeod, Peggy Esquibel Reed-Qwest, Jim Recker-Qwest, Shirley Tallman-Qwest, Chris Viveros-Qwest, Denise Martinez-Qwest

DISCUSSION: Peggy Esquibel Reed-Qwest stated that the ad hoc call was for Qwest to present a proposed solution to Granite and the CLEC Community, for PC072505-1 Cable Pair and Binding Post Identification. Peggy stated that at the October CMP Meeting, Qwest had indicated that we are unable to provide the information on the FOC, because at FOC, there are no assignments yet. This call is for discussion of the proposed solution. Denise Martinez-Qwest stated that at FOC, the data is not yet available and noted that it would also result in FOCs being delayed. Denise stated that no one wants delays in the FOCs. Denise stated that an Assignments Section would be added to the PSON when the PSON is created. Denise stated that it would include a header and that it would display ‘no activity for section’. Denise stated that when the data was then available, another PSON would be sent. Denise stated that also added to the PSON would be a disclaimer that would state that the assignments could change on and including on the due date. Denise then asked for questions. Lisa Mui-Granite stated that she was not familiar with the PSON. Denise Martinez-Qwest stated that the PSON is sent after the FOC. Denise noted that it is not the completion; it is the Pending Service Order Notice. Denise stated that it is a snapshot of the service order after the FOC and pre-completion. Denise noted that updated PSONs are sent when there has been an update to a service order. Lisa Mui-Granite asked if they could be viewed via IMA. Denise Martinez-Qwest yes and noted that they could not be viewed in the FAX Gateway. Lisa Mui-Granite stated that they do not currently get PSONs. Denise Martinez-Qwest stated that it is a snapshot of the SOP and noted that they could request to start receiving them. Sharon Van Meter-AT&T stated that not all request a PSON and asked what would be done for those CLECs. Denise Martinez-Qwest stated that they would need to request the PSONs in order to get the information. Lisa Mui-Granite stated that she would discuss this proposed solution with their IT people to see why PSONs are not currently requested. Lisa stated that this could be tremendously helpful. Denise Martinez-Qwest stated that the information may or may not change on the due date. Bonnie Johnson-Eschelon asked if the information did change on the due date, if another PSON would then be sent. Denise Martinez-Qwest stated that it could and noted that it would depend on timing. Denise stated that if the last PSON was sent and then the information changed, it would then be time for a Completion Notice to be sent. Bonnie Johnson-Eschelon asked if the updated information could then be on the Completion Notice. Denise Martinez-Qwest stated that Qwest would internally discuss that request. Lisa Mui-Granite asked if Granite could view the service order. Denise Martinez-Qwest stated that they could view the service order via the PSON. Lisa Mui-Granite stated that she needed to speak internally to see if this solution is acceptable for them. Lisa asked if this was the only solution. Denise Martinez-Qwest said yes and stated that no one want delays in the FOCs. Peggy Esquibel Reed-Qwest asked if there were any other questions. Bonnie Johnson-Eschelon advised Granite that Eschelon does receive the PSONs for EDI and GUI and stated that she and/or Stephanie Prull (Eschelon) would be happy to discuss with Granite. Stephanie Prull-Eschelon asked if this was a Systems CR. Peggy Esquibel Reed-Qwest stated that the CR was submitted as a Process change and stated that if today’s proposed solution was acceptable, the CR would be crossed over to a Systems CR. Bonnie Johnson-Eschelon asked if Qwest would look into providing the information on the Completions Notice. Denise Martinez-Qwest stated that Qwest would look into that. Jim Recker-Qwest asked if there was feedback from other CLECs. Joyce Philo-McLeod stated that she would check and see if McLeod receives PSONs or if they would need further development. Joyce asked if they could be viewed in IMA. Denise Martinez-Qwest stated that they can view via IMA if they have requested PSONs. Stephanie Prull-Eschelon stated that McLeod would need to certify for PSON and then they would see them. There were no additional questions. Peggy Esquibel Reed-Qwest asked Granite to please let her know if this solution was acceptable to them.

-- October 19, 2005 Monthly Product Process CMP Meeting Discussion: Jim Recker/Qwest stated that this request is for Cable Pair and Binding Post to be provided on the LSR FOC. Jim stated that we are unable to do that because at FOC, there are no assignments yet. Jim then stated that Qwest has a potential solution and that an ad hoc meeting was being scheduled for Qwest to present the potential solution and for discussion. Jim stated that this CR would remain in Evaluation Status pending the outcome of the ad hoc meeting.

-- September 21, 2005 Monthly Product Process CMP Meeting Discussion: Jim Recker/Qwest stated that Granite is requesting that the cable pair and binding post be placed on the order at FOC. Jim stated that another call was held, with Granite, yesterday in order to communicate that some information is currently available to Granite, in CEMR. Jim stated that we are continuing to evaluate this request. Jim noted that when the information is put on the order, at FOC, it has not yet gone through the assignment process. Jim said that changes to the PSON may be an option but if the cable pair & binding post information is placed on the PSON, that information could change and may not be the final assignments. Jim stated that based on the call yesterday, with Granite, we are still looking into items internally to see if we can move forward with this request. Bonnie Johnson/Eschelon stated that she understands Qwest’s concern regarding the information on the PSON possibly changing and noted that the assignments could change in the course of the installation process. Bonnie asked if that was a common occurrence. Jim Recker/Qwest stated that he was trying to get some numbers around that. There were no additional comments. Jill Martain/Qwest stated that this CR would move to Evaluation status.

-- August 17, 2005 Monthly Product Process CMP Meeting discussion: Peggy Esquibel Reed-Qwest stated that Granite Telecommunications is requesting that Cable Pair & Binding Post Information be provided sooner and that currently the information is provided via repair. This CR moves to presented status.

-- Clarification Meeting-August 4, 2005 Attendees: Lisa Mui-Granite Telecomm, Kim Tosi-Granite Telecomm, Kim Isaacs-Eschelon, Peggy Esquibel Reed-Qwest, Janean Van Dusen-Qwest, Jim Recker-Qwest, Becky Ferrington-Qwest, Denise Martinez-Qwest, Alan Braegger-Qwest, Terri Kilker-Qwest, Gary Stacy-Qwest, Caroline Myers-Qwest

Review Requested (Description of) Change: Peggy Esquibel Reed-Qwest read the CRs description: Identification of cable pair and binding post information when the order reaches confirmed status (FOC). The cable pair and binding post information is currently provided via repair after the order is completed.

Obtain the Business Need from the CR Originator: Peggy Esquibel Reed-Qwest asked Granite Telecom for their business reason for the requested change or for information as to what problem has been encountered that prompted this request. Granite Telecomm stated that they need the information as soon as the FOC. As soon as the order confirms, they schedule the installer and they would look for the information. If they wait until the order completes, it is a longer wait for their end user customer to get service. They now have to call repair for the information.

Additional Discussion: Becky Ferrington-Qwest asked if the requested product set is UNE-P POTS. Lisa Mui-Granite Telecom stated that it is for any installation but that the bulk for Granite is POTS. Lisa Mui-Granite asked for the likelihood of getting this request. Peggy Esquibel Reed-Qwest stated that Qwest will need to analyze the request and stated that the next step is for Granite to present this CR to the CLEC Community at the August 17th Monthly CMP Meeting and then Qwest would provide a response in September. There were no additional questions or comments

Confirmed Impacted Area(s): Ordering

Confirmed Impacted Products: All


CenturyLink Response

February 15, 2013

To: Lisa Lynn Cc: New Cr, Cmp Subject: CenturyLink Draft Response to Granite Change Request (CR) PC072505-1 Cable Pair & Binding Post Identification

Good morning, Lisa, With the February CMP Monthly meeting scheduled for February 20, 2013, we are proposing that your Change Request PC072505-1, Cable Pair & Binding Post Identification, be crossed over to a System CR. We are proceeding with the evaluation of the CR as a system change to IMA. As a crossover, the Product Process CR will be closed and CenturyLink will open CR SCR072505-1X on your behalf with a reference to the original Product Process CR. Please let me know if you have any questions. Here is the link to the calendar entry for this meeting http://wholesalecalendar.centurylinkapps.com/detail/385/2013-02-20. We hope you are able to attend. Thank you, Susan Lorence CenturyLink CR Project Manager ** January 9, 2013

TO: Lisa Lynn Granite Telecommunications

SUBJECT: CR # PC072505-1 Cable Pair & Binding Post Identification

This letter is in response to Granite Telecommunications Change Request PC072505-1, Cable Pair & Binding Post Identification. The original CR requested the cable pair and binding post information be made available when the order reaches confirmed status (FOC). During the December 12, 2012 monthly CMP meeting, this CR was re-reviewed since it had been in a “Deferred” status in CMP since late 2005. During the December discussion, the CenturyLink SME team identified that the cable pair and binding post information could not be depended upon prior to completion. It was relayed that CenturyLink may find that the initial facility assignment prior to completion may not be suitable and must be changed. Based on that discussion, on January 2, 2013, per your request, the CR was revised to: • Receive the identification of cable pair and binding post information upon completion versus when the order reaches confirmed status. • Capture the specific product types impacted as POTs, Centrex, and Resale.

In the original CR, it was specifically noted that “the cable pair and binding post information is currently provided via repair after the order is completed.” With the original CR requesting the information at FOC, the solution of utilizing the repair system information was not identified as a viable approach. During the December call, use of CEMR was suggested as a way to access cable pair and binding post information. Now that the CR has been revised to request that CenturyLink provide the cable pair and binding post information upon completion, consideration of using the data currently available in the repair system has become more viable.

Rather than making system changes in IMA to provide the cable pair and binding post information upon completion, CenturyLink would like to propose that Granite utilize that information that is currently available in CEMR. The CenturyLink SME team has confirmed that this information is consistently available in CEMR for all of the product types you have identified. To access this information in CEMR, a customer utilizes the Non-design screen, selects the Demarc tab and enters the TN that is being investigated. An example of what is returned is attached to this response.

Again, since the cable pair and binding post information is currently available, CenturyLink is proposing that no system changes be made to IMA to provide this same information. CenturyLink would like to walk through this screen capability during the January CMP monthly meeting and would like to further discuss whether this existing capability will suffice to meet the Granite business reason for this requested change.

Sincerely, Susan Lorence CenturyLink CR Project Manager

NOTE: Attachment specific to CEMR screen shot is not available in CMP database.

* September 13, 2005

For Review by the CLEC Community and Discussion at the September 21, 2005 Product Process CMP Meeting

TO: Lisa Mui Granite Telecommunications

SUBJECT: CR # PC072505-1 Cable Pair & Binding Post Identification

This letter is in response to Granite Telecommunications Change Request PC072505-1 (Cable Pair & Binding Post Identification). This CR requests the identification of cable pair and binding post information when the order reaches confirmed status (FOC). The cable pair and binding post information is currently provided via repair after the order is completed.

A clarification call was held on August 4, 2005 for discussion of this request, and this CR was presented at the Product Process Monthly CMP Meeting on August 17, 2005. Qwest has requested another call with Granite Telecommunications, for further discussion of this Change Request.

Qwest would like to place this CR in evaluation status in order to continue with analysis of this request. The current process was developed via several previously submitted Product Process and Systems CMP CRs. Qwest is continuing to and look at viable solutions for this change request. Qwest will provide an updated response at the next CMP meeting. Qwest requests that this CR move to Evaluation status.

Sincerely, Qwest


Open Product/Process CR PC020514-1X Detail

 
Title: Syncing XML and LSOG Publications(CR Crossed over from SCR020514 1X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC020514-1X Completed
3/19/2014
Wholesale Ordering
Originator: O’Day, Judi
Originator Company Name: Granite Telecommunications
Owner: Martinez, Denise
Director:
CR PM: Lorence, Susan

Description Of Change

With the May 20, 2013local release, several fields were removed from use in the CenturyLink LSOG including the field LSR:AUTHNM. However, this field is still present in the current XML publications. When attempting to submit an LSR converting lines from a different CLEC, CenturyLink returns an error stating that “AUTHNM is required” despite this field no longer being available per the LSOG. Furthermore, even if the AUTHNM field is populated (which should be valid per the current XML) the PON is still sent back for the error “AUTHNM is required”.

Expected Deliverables: Sync the CenturyLink published information in the LSOG and the XML guidelines so that CLECs will know which information is correct. Reinstate the AUTHNM field in the LSOG or update the LSOG to indicate another appropriate location for this information.


Status History


Project Meetings

3/19/14 Product Process CMP Meeting Mark Coyne – CenturyLink said this CR was a cross over from System CR SCR020514-1X that occurred in the System meeting last month. After review with Granite and Integra, it was determined there was not a system issue but a clarification needed to be made to the documentation. Mark said CenturyLink sent a level 1 notification on February 27 which was effective immediately to update the Port In PCAT. The notice identified that some providers require an authorization name in order to port a number to a new provider and in that case, the authorization name must be placed in the Remarks field. The CR is currently in CLEC Test and CenturyLink would like to move this CR to Completed status. Mark asked if there were any objections. There were none.

2/19/14 Systems CMP Meeting Jhett Jones – Granite presented the new CR that is associated with IMA Release documentation. Jhett said he thinks the XML documentation is out of synch with fields that were removed from the LSOG May 2013. Jhett said their concern is the AUTHNM field that is causing some order problems when converting from a losing CLEC to Granite. An error is received from CenturyLink that AUTHNM is required. Jhett said this request is to synch up the LSOG and XML documentation.

Susan Lorence – CenturyLink relayed that a clarification call had been held on February 13, 2014 and that during that call, it was determined that the system documentation was correct. Susan said the suggested approach was to cross this CR over to a Product Process CR and that CenturyLink would like to make an update to the PCAT to add clarification around the use of AUTHNM. Susan asked if that plan was still agreeable to Granite.

Judi O’Day – Granite said that was still agreeable.

Susan Lorence – CenturyLink said that we believe this documentation update is not related to a change in process but is only adding a clarification to the PCAT and CenturyLink would like to send a level 1 notice that would be effective immediately.

Kim Isaacs – Integra asked whether if updates would be to the Port In PCAT and whether the update was to show that AUTHNM should be placed in the Remarks vs. the AUTHNM field since some carriers may require it.

Janean Van Dusen – CenturyLink said yes, those are the updates that would be made to the Port In Business Procedure.

Susan Lorence – CenturyLink said a lot of investigation has occurred associated with this ordering situation and that CenturyLink would then be sending a level 1 notice to make the documentation update.


Open Product/Process CR PC120301-1 Detail

 
Title: Porting of Centrex designated numbers
CR Number Current Status
Date
Area Impacted Products Impacted

PC120301-1 Completed
1/16/2002
Provisioning
Originator: Nikolaisen, Greg
Originator Company Name: HBC Telecom
Owner: Wells, Joan
Director:
CR PM:

Description Of Change

We get numbers that are resold to McCleod that have been marked as "Centrex", and cannot be ported in the normal way. These either have not been portable, or have taken weeks to accomplish, wasting both of our man hours to get it done manually. We need to have these ported just like any normal number. These are not really Centrex numbers in reality, somehow they have been marked as Centrex when they were resold to McCleod.


Status History

11/30/01 - CR received from HBC Telecom.

12/03/01 - E-Mail Acknowledgement issued to HBC Telecom.

12/03/01 - Greg Nikolaisen, HBC Telecom, contacted via voice mail indicated Greg will be out of office through 12/5/01. Sent e-mail requesting available dates for clarification meeting and requesting examples.

12/06/01 - Conducted Clarification Meeting with HBC Telecom.

12/12/01 - CMP Meeting - HBC was not on the call to present its CR. Qwest reviewed what was discussed at the Clarification meeting. CR Status to change to Clarification.

12/18/01 - Issued Meeting Minutes to HBC Telecom.

01/10/02 - E-mail received from HBC Telecom indicating that they are not experiencing any further problems.

01/11/02 - Issued Qwest's Draft Response dated 1/10/02 to HBC Telecom.

01/16/02 - CMP Meeting - Qwest presented its Draft Response. Qwest indicated that HBC had confirmed via e-mail that the issue had been fixed. It was agreed that the CR could be closed.

01/21/02 - Issued Qwest's Response dated 1/10/02 to CLEC Community.


Project Meetings

Subject: CMP for Centrex portiing Date: Thu, 10 Jan 2002 16:20:32 -0600 From: greg.nikolaisen@hbci.com To: rhmart2@qwest.com CC: barbf@hbci.com, chagedorn@hbci.com

Rick,

With the changes that were done, the reason that we opened the CMP has been fixed. We now can port Centrex designated numbers. The need for this CMP is gone. Please cancel.

Thanks for the help on this matter.

Greg Nikolaisen

-

CLEC Change Request Clarification Meeting

December 6, 2001, 3:00 p.m. (MT) Conference Call 877-564-8688 PC1120301-1, Porting Centrex Designated Numbers

Attendees: Ric Martin, Qwest Joan Wells, Qwest Susie Wells, Qwest Greg Nikolaisen, HBC Telecom Barb Ferguson, HBC Telecom

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change Greg indicated that they had no problems porting numbers from Qwest, except for numbers that are designated as Centrex. These were numbers apparently resold to McLeodUSA, or another reseller. Greg advised that the problem was encountered when they were trying to enter the order into IMA-GUI. He indicted that they had one order that they were trying to work for weeks and Joshua Nielson, Qwest, was able to get it to all of a sudden go through IMA. Greg thought the system might be looking for the main Centrex group number. Qwest questioned the HBC’s interface to the NPAC. HBC indicated that they weren’t having any problems once the order made it into NPAC. HBC advise that they were have to put in a due date the day before 18:00 hours the due date in IMA. Qwest advised that the due dates should be the same. It was explained that this shouldn’t be a problem. Qwest looked up the reference order LSR 3578825, 3 TNs, and confirmed they were a Centrex line. Qwest also confirmed the due dates were in NPAC. Qwest showed the due date in IMA as the 9th. Qwest asked HBC to provide previous examples that Qwest could research. Susie explained that there has been problems in the east with Centrex orders and that Qwest was relaxing the edit. Qwest thought this might correct the problem. HBC is to try and recreate the situation with Qwest on the line. HBC will contact Joan Wells (801) 239-4597 on Monday. It was felt that this was more of an IMA issue than a Porting process issue.

Confirm Areas & Products Impacted The product identified was the area being impacted.

Confirm Right Personnel Involved Joan Wells is the SME for LNP and Susie Wells is the SME for Centrex

Identify/Confirm CLEC’s Expectation HBC wants the porting (ordering) of TNs with Centrex designations to happen as planned. HBC would like to determine the root cause for the problem.

Identify any Dependent Systems Change Requests There is no dependent systems CR.

Establish Action Plan (Resolution Time Frame) HBC to provide examples and try to recreate the problem with Qwest on-line. Qwest to investigate the issues. Qwest advised that the path forward would be as follows: ? Since this CR was received after the 3 weeks prior to the CMP, McLeodUSA will present this CR at the December CMP Meeting. ? The CR will have the collective CLEC clarification at the January CMP Meeting. ? Qwest will begin to identify solutions that can be offered at the January CMP Meeting. ? Qwest will develop its response for the February’s CMP Meeting

--

Subject: CR PC120301-1 Date: Mon, 03 Dec 2001 15:23:01 -0700 From: Richard Martin Organization: Qwest Communications International, Inc. To: "Nikolaisen, Greg"

Greg,

I understand from your voice mail that you will be out until Wednesday. I wanted to see what dates would be good for you to set-up a clarification call with Qwest's SME. Also, in reading the CR, it would be benificial if you could have some examples provided for Qwest to look into.

Please respond by e-mail or phone.

Thanks

Ric 303-896-9823


CenturyLink Response

Wholesale Product Marketing

January 10, 2002

Mr. Greg Nikolaisen, HBC Telecom

This letter is in response to Change Request, PC120301-1 – Porting of Centrex Designated Numbers from Qwest.

Description of Problem: The CLEC encountered problems specifically in the Eastern Region, when trying to enter orders into the GUI to port numbers. The problem was occurring only when the numbers that the CLEC was trying to Port were residing on a CTX.

In Qwest’s Eastern Region, there was a problem when trying to cross reference a working CTX telephone number to the main BTN of the CTX. This internal error, along with an edit in the GUI that was effective in the 8.0 release was causing the GUI to reject any CSR requests saying the number could not be found or was invalid. The problem was corrected internally on December 18th,and the edit was relaxed in the GUI. Any numbers that are a part of a CTX should cross reference appropriately to the main BTN allowing the CLEC to pull the WTNs in order to place their order to Port correctly.

Sincerely, Susie Wells Centrex Process Manager


Open Product/Process CR PC040105-01 Detail

 
Title: Qwest Directory Assistance (DA) Database Lookups for CLECs
CR Number Current Status
Date
Area Impacted Products Impacted

PC040105-01 Denied
12/14/2005
Originator: Jensen, Corey
Originator Company Name: HickoryTech
Owner: Stouffer, Jim
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest Operators will not look up DA Listings for CLEC numbers if they are not stored in the Qwest SDG Database.

Expected Deliverable:

Qwest Operators will look up CLEC Listings in the National Database anytime a number is not found in the internal Database


Status History

4/1/05 - CR Submitted

4/1/05 - CR Acknowledged

4/7/05 - Clarification Meeting Held

4/7/05 - Status changed to clarification

5/18/05 - Status changed to Presented

5/20/05 - Discussed at the May Product/Process CMP Meeting.

6/2/05 - Status changed to Evaluation

6/15/05 - Discussed at the June Product/Process CMP Meeting.

7/20/05 - Discussed at the July Product/Process CMP Meeting

8/17/05 - Discussed at the August Product/Process CMP Meeting

9/12/05 - Revised response issued

9/21/05 - Discussed at the September Product/Process CMP Meeting

10/19/05 - Discussed at the October Product/Process CMP Meeting

11/7/05 - CMPR.11.07.05.F.03447.Ad_Hoc_Meeting

11/16/05 - Discussed at the November Product/Process CMP Meeting.

12/14/05 - Discussed at the December Product/Process CMP Meeting.

12/14/05 - Status changed to Denied


Project Meetings

E-mail from Hickory Tech

Hello Lynn - We are working on getting the list of questions together for you. I hope to have them soon. Thanks, Pam --Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Friday, December 16, 2005 3:41 PM To: Pam Lehrke Cc: Martain, Jill; Foster, Sandy Subject: FW: December CMP Meeting Minutes for Review and Feedback

Hi Pam,

Peggy forwarded your message to me. I am sorry you missed the December CMP Meeting. I am curious as to what CMP 12-month schedule you are referring to. I checked the Wholesale Website and the current calendar does reflect the date as December 14th.

Is there anyway you can submit your questions/comments to me so that I can refer them to the appropriate subject matter experts?

Thanks,

Lynn Stecklein Qwest Wholesale CRPM 303 382-5770

--Original Message-- From: Esquibel-Reed, Peggy Sent: Friday, December 16, 2005 2:25 PM To: Stecklein, Lynn Subject: FW: December CMP Meeting Minutes for Review and Feedback

--Original Message-- From: Pam Lehrke [mailto:Pam.Lehrke@HickoryTech.com] Sent: Friday, December 16, 2005 1:09 PM To: Esquibel-Reed, Peggy Subject: RE: December CMP Meeting Minutes for Review and Feedback

Hi Peggy -

I was unaware of the changed date for this months CMP meeting. I was using the CMP 12-month schedule. We have further comments/questions on our issue, please advise as to how we are to proceed.

Thank you,

Pam Lehrke

HickoryTech

--Original Message-- From: Esquibel-Reed, Peggy [mailto:Peggy.Esquibel-Reed@qwest.com] Sent: Friday, December 16, 2005 1:54 PM To: Johnson, Bonnie J.; Isaacs, Kimberly D.; Van Meter, Sharon K, NEO; Dianne.Friend@twtelecom.com; sue.wright@xo.com; lhankins@covad.com; laurie.fredricksen@integratelecom.com; Tom Hyde; Sanders, Nancy; Sonnier, Jeff J [NTK]; Stichter, Kathleen L.; rosalin.davis@mci.com; lynnkellas@eli.net; christerrell@att.com; Prull, Stephanie A.; Pam Lehrke; Julie Pickar (E-mail) Cc: Stecklein, Lynn Subject: December CMP Meeting Minutes for Review and Feedback

Hi All,

I have attached the meeting minutes from the December Product/Process and Systems CMP Meetings. Please review the documents to ensure that your comments were captured accurately. You need only to review your statements. Please provide your proposed changes no later than 8:00 a.m. MT, Wednesday, December 21, 2005.

Please track your changes.

Have a Safe a Happy Holiday!

Peggy Esquibel-Reed

Qwest Wholesale CMP

12/14/05 Product/Process CMP Meeting

Sandy Foster/Qwest stated that Qwest has spent an extensive amount of time reviewing the existing process and potential solutions associated with this request. Sandy said that Qwest has determined that it is economically not feasible for Qwest to search the National DA Database every time a local listing is not found in Qwest’s Regional DA Database and is denying this request. Bonnie Johnson/Eschelon asked if Qwest does this for retail 100% of the time. Sandy Foster/Qwest said no and that Qwest has no idea where the call is coming from. Bonnie Johnson/Eschelon asked if something could happen in the process to determine if it happens with one provider more often. Sandy Foster/Qwest said no, not to her knowledge. She said that the process as outlined is an equitable search procedure across the board. Pati Leo/Qwest agreed. Jill Martain/Qwest stated that this CR will be closed.

11/16/05 Product/Process CMP Meeting

Lynn Stecklein/Qwest stated that an adhoc meeting was held on 11/15/05 to communicate Qwest’s proposal on this CR. She said that the CLECs indicated the proposal will not meet their needs. Lynn stated that Qwest agreed to take back the concerns raised by the CLECs and provide an updated response in the December CMP Meeting. Bonnie Johnson/Eschelon stated that Qwest said that the original CR was economically not feasible and wanted to know if that is what the response will be in December. Jill Martain/Qwest stated that to implement the CR would be very costly and that we are looking into suggestions from yesterday’s call to determine costs.

10/19/05 Product/Process CMP Meeting

Sandy Foster/Qwest stated that after extensively reviewing this request our findings have determined that this change is too costly. Sandy said that we are looking at an alternative and hope to have the proposal completed by no later that the 1st of next week. She said that she hopes that this proposal can be beneficial to both Qwest and the CLECs. Pam Lehrke/Hickory Tech stated that she is interested in seeing the proposal as soon as possible. Liz Balvin/Covad said that providing an alternative is better that a flat out denial.

9/17/05 Product/Process CMP Meeting

Lynn Stecklein/Qwest said that Qwest continues to explore all options associated with this request. She said that we have determined that to implement this CR as written would be very costly to implement. Lynn said that we have talked with Hickory Tech since the last CMP Meeting and they have asked Qwest to consider another alternative. She said that we are researching to determine the feasibility of this option. She said that our goal is to provide the response in the October Meeting. 8/17/05 Product/Process CMP Meeting

Lynn Stecklein - Qwest said Qwest continues to evaluate this CR. She said that we are in the process of reviewing Hickory Tech’s issue against our policy and found complexities that needed to be addressed before responding to this CR. Lynn said to further complicate this analysis, Qwest just recently learned that the current relationship of our National Database Vendor has changed. She said that this change has added additional complexities that we are analyzing and that we will work towards providing a response in September.

7/20/05 Product/Process CMP Meeting

Lynn Stecklein - Qwest stated that our intent was to provide a response in this meeting. She said that an adhoc meeting was held with the CLEC Community to further understand and clarify Hickory Tech’s issue. She said that Qwest is currently reviewing the information from that meeting against our policy and have found complexities that need to be addressed before we can provide a response.

Jill Martain - Qwest stated that this CR will remain in Evaluation status.

6/15/05 Product/Process CMP Meeting

Jill Martain - Qwest stated that an adhoc meeting was held yesterday and that this request is still in Evaluation. She said that Qwest would provide a readout in the July CMP Meeting.

5/18/05 CMP Product/Process Meeting

Pam Lehrke - Hickory Tech stated that this request has to do with whether a CLEC houses their Directory Listings in the Qwest Database. Pam said that they have experienced situations and through testing have found that when the listing is not in the Qwest database, the Qwest operator will not do a lookup in the National Database. Pam said that they would like Qwest to look up CLEC listings in the National Database anytime a number is not found in the internal Qwest database. Jill Martain - Qwest asked if there were any questions. Jody Baker- North Star Access asked what is Qwest’s policy regarding Qwest looking in the National Database for listings that are not in the Qwest database. Jill Martain - Qwest stated that the subject matter experts were not available to answer this question and suggested that that an adhoc meeting be scheduled to discuss further. Jill said that the status of this CR will move to Presented.

4/7/05 Clarification Meeting

Attendees: Pam Lehrke - Hickory Tech, Sandy Foster - Qwest, Russ Urevig - Qwest, Lori Simpson - Qwest, Carol Mckenzie - Qwest, Pati Leo - Qwest, Lynn Stecklein - Qwest

Review Description of Change Pam Lehrke - Hickory Tech stated that today Qwest operators will not look up DA listings for CLEC numbers if they are not stored in the Qwest SDG Database. She said that they would like Qwest operators to look up CLEC listings in the National Database anytime a number is not found in the internal Qwest Database.

Discussion: Lynn Stecklein - Qwest asked what is the SDG database. Pam Lehrke - Hickory Tech said that the Qwest database that houses listing information. Russ Urevig - Qwest asked if this included Facility based listings. Pam Lehrke - Hickory Tech said yes. She said that sometimes when a listing is not found the Qwest operator will expand the search to a National Database. Lori Simpson - Qwest asked if this is always the case. Pam Lehrke - Qwest stated that they had approximately 40 test calls and never once got a find. Lori Simpson - Qwest stated that Qwest includes th primary listing of CLECs in the Qwest Database. Lori asked if the caller could be anyone. Pam Lehrke - Hickory Tech said that the caller could be any client of Qwest looking for a listing or any local service provider. Pam said that it appeared that it was up to the operator's discresion to bounce over to another database. There were no other questions.

Confirm areas and Products Impacted Directory Assistance

Establish Action Plan Lynn Stecklein - Qwest stated that Hickory Tech will present this request in the May Product/Process CMP Meeting.


CenturyLink Response

December 7, 2005

Final Response

SUBJECT: PC040105-01 (Qwest Directory Assistance (DA) Database Lookups for CLECs

This letter is in response to Hickory Tech’s request that Qwest Communications Directory Assistance (DA) operators look up CLEC listings in the National DA database any time that a number is not found in Qwest’s Regional DA database.

Qwest reviewed its existing process and determined that every additional second spent on a search costs us approximately $1 million annually. This cost does not include the additional costs that Qwest would incur for each listing that is accessed from the National DA listing database. A dip into a national database automatically adds on at least 18 seconds to a search. This is at a minimum. Additionally, due to the numerous national databases that are available for use, there is no guarantee that the listing that is being requested is available in the national database(s) that Qwest uses. Consequently, it is not economically feasible for Qwest to guarantee that it would search the National DA database every time a local listing is not found on Qwest’s Regional DA database.

Qwest proposed a compromise solution that was rejected by the CLEC community. Qwest also explored alternative options suggested by the CLECs that might be beneficial to both the CLEC community and Qwest. However, these solutions proved costly as well since they either require Qwest to develop a new interface to accept a different electronic feed, or, be too resource intensive to manually load additional listing information.

Qwest does have a process available to the CLEC community that allows CLEC listings to be shown in the Qwest Listing database which would guarantee that these listings are available by the Qwest DA agent. This process is outlined in the White Pages Directory Listings PCAT.

Qwest continues to endeavor to provide a comprehensive Directory Assistance while ensuring that the costs and service remain competitive. On this basis, Qwest denies this request because it is economically not feasible.

Sincerely,

Qwest

For Review by the CLEC Community and Discussion at the September 21, 2005 CMP Meeting

September 21, 2005

Hickory Tech Pam Lehrke

SUBJECT: CR # PC040105-01 Qwest Directory Assistance (DA) Database Lookups for CLECs

This letter is in response to Hickory Tech's Change Request (CR) PC0240105-01 Qwest Directory Assistance (DA) Database Lookups for CLECs. This CR requests that Qwest Operators look up CLEC listings for CLEC numbers if they are not stored in the Qwest SDG Database.

Qwest would like to keep this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. Qwest will provide an updated response at the October CMP meeting.

Sincerely,

Qwest Communications

For Review by the CLEC Community and Discussion at the June 15, 2005 CMP Meeting

June 2, 2005

Hickory Tech Pam Lehrke

SUBJECT: CR # PC040105-01 Qwest Directory Assistance (DA) Database Lookups for CLECs

This letter is in response to Hickory Tech's Change Request (CR) PC0240105-01 Qwest Directory Assistance (DA) Database Lookups for CLECs. This CR requests that Qwest Operators look up CLEC listings for CLEC numbers if they are not stored in the Qwest SDG Database.

Qwest would like to place this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. Qwest will provide an updated response at the July CMP meeting. Qwest will move this CR to Evaluation status.

Sincerely,

Qwest Communications


Open Product/Process CR PC120213-1 Detail

 
Title: Updates to the Poles, Ducts and Right of Way Process Automatic Refund of Excess Make Ready Charges [Related CRs are PC120213 2 and PC120213 3]
CR Number Current Status
Date
Area Impacted Products Impacted

PC120213-1 Denied
4/3/2014
Pre-order(Quotes & Field Verification) and Billing Poles, Ducts, Right of Way
Originator: Isaacs, Kim
Originator Company Name: Integra
Owner: Karpowich, Steve
Director:
CR PM: Lorence, Susan

Description Of Change

01-30-14 CR REVISED DESCRIPTION:

Integra requests the following changes to the Poles, Ducts and Right of Way process:

1. Automatic Refund of Excess Make Ready Charges; currently when CenturyLink’s actual Make Ready costs are less than the Make Ready charges paid by the CLEC, CenturyLink requires that the CLEC request a refund within 60 days. Integra requests a change in the existing process which would require that CenturyLink automatically refund (via check or credit) excess Make Ready charges paid by the CLEC.

Expected Deliverables/Proposed Implementation Date (if applicable):

Upon completion of this change request, Integra expects that;

1. CenturyLink with automatically refund (via check or credit) any excess Make Ready charges paid by the CLEC

[NOTE: After discussion in the January

2014 CMP meeting, CR PC120213-1 is being split into three related CRs to address each of the requested changes separately. Related CRs are PC120213-2 and PC120213-3]

*************

12-2-13 Original CR: Integra requests the following changes to the Poles, Ducts and Right of Way process:

1. Automatic Refund of Excess Make Ready Charges; currently when CenturyLink’s actual Make Ready costs are less than the Make Ready charges paid by the CLEC, CenturyLink requires that the CLEC request a refund within 60 days. Integra requests a change in the existing process which would require that CenturyLink automatically refund (via check or credit) excess Make Ready charges paid by the CLEC.

2. Extension of Inquiry Review Quote Acceptance Interval; Under the current process, a CenturyLink CenturyLink Inquiry Review quote is valid for only 30 days from the date the CLEC receives the quote. Integra requests that the quote acceptance interval be extended to a minimum of 90 days.

3. Monitoring of Approved CenturyLink Contractors during CLEC Field Verification; CLECs have the option of using a CenturyLink approved contractor when conducting Field Verifications for underground facilities. CenturyLink’s current practice is to have a CenturyLink employee monitor the contractor (already approved by CenturyLink) at the CLECs expense. Integra requests a change in the policy, if CenturyLink feels it is necessary to monitor contractors they have previously ”approved” then CenturyLink should not charge the CLEC for the monitoring.

Expected Deliverables/Proposed Implementation Date (if applicable):

Upon completion of this change request, Integra expects that;

1. CenturyLink with automatically refund (via check or credit) any excess Make Ready charges paid by the CLEC

2. CLECs will have a minimum of 90 days to accept an Inquiry Review quote.

3. When CLEC choses to use a CenturyLink approved contractor to complete a Field Verification for underground facilities, CenturyLink will not require the CLEC to pay for the monitoring of the approved contractor.


Status History


Project Meetings

4/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was submitted by Integra last December with three proposed changes in process. CenturyLink requested the CR be broken into three related CRs. Mark reviewed the draft response for this proposed change. He said after extensive consideration by the SME team to automatically refund any excess Make Ready charges paid by the CLEC, CenturyLink is denying this CR on the grounds that there is no reasonably demonstrable business benefit. The SME team found the volume of this type of situation is low and that rarely do the CenturyLink quotes come back under the Make Ready charges paid by the CLEC so there is typically nothing left to refund. Mark also said the SME team found no instances of this Excess Make Ready Charge refund situation specific to Integra. Mark asked if there were any questions; there were none.

3/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CenturyLink SME team is still evaluating this CR and is considering the volume of this type of activity. We hope to send the draft response for the April meeting. Mark asked if there were any questions. There were none.

2/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this is the first of the three requested changes by Integra on the original CR. Mark said a draft response was sent on February 12 indicating this CR is still being evaluated and that we hope to have an answer by the March meeting. Mark asked if there were any questions. There were none.

1/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that the CR was presented last month by Kim Isaacs – Integra and that the CenturyLink SME team is still investigating each of the three proposed changes. Mark said that we would like to propose that we break the CR up into three separate but related CRs as we continue to move forward in our investigation.

Kim Isaacs - Integra said that was not a problem.

12/11/13 Product/Process CMP Meeting Kim Isaacs - Integra presented the new CR which requests three process changes associated with Poles, Ducts and Right of Way (PDR) as listed in the CR. Kim asked if there were any questions. There were none.

Mark Coyne – CenturyLink relayed that a clarification call had been held on December 9, 2013 and that the meeting minutes from the call would be posted soon. Mark said the CR would be moved to Presented status and the SME team would be evaluating the proposed changes.

12/9/13 Clarification Call Meeting Minutes Attendees: Kim Isaacs – Integra Laurie Roberson – Integra Susan Lorence-CenturyLink Mark Coyne-CenturyLink John Hansen-CenturyLink Steve Karpowich-CenturyLink Rita Urevig-CenturyLink Maggie Burgoyne-CenturyLink Cindy Schwartze-CenturyLink Tammy Meyer-CenturyLink

Susan Lorence – CenturyLink introduced the call and explained the purpose of the call. She asked Kim Isaacs from Integra to present the Change Request (CR). She suggested that they present the change and the deliverable at the same time for each of the three issues included in the CR.

Kim Isaacs-Integra presented the first issue which was the automatic refund of excess Make Ready costs.

Susan Lorence-CenturyLink asked for clarification as to where the current process was documented and wanted to confirm if it was in the Interconnection Agreement (ICA).

Kim Isaacs-Integra confirmed. She explained that all three of these issues were items that the CenturyLink ICA negotiators had asked Integra to bring through CMP.

Susan Lorence-CenturyLink asked for other questions; there were none. Susan clarified that the request is for customers to not have to initiate any excess amount of Make Ready charges and that CenturyLink would automatically issue the excess credit amount. She also clarified that it is unclear whether the current process was a check or a credit.

Kim Isaacs-Integra said that she thought the current process was only that a credit was available.

Susan Lorence-CenturyLink asked if Integra was insistent on receiving a check instead of a credit.

Kim Isaacs-Integra stated that she felt they would be willing to accept a credit if it was going to be automatic and a check would become an issue. She then presented the second item in the CR. She stated that they would like the quote to remain open until a resolution was reached, but that as a compromise, a minimum of 90 days would be sufficient.

Susan Lorence-CenturyLink reiterated that the current process only kept the quote open for 30 days and once that had elapsed; the process had to begin anew.

Kim Isaacs – Integra concurred.

Susan Lorence-CenturyLink asked if the CenturyLink SMEs had any questions. There were none.

Kim Isaacs – Integra presented the third and final issue in the CR.

Mark Coyne-CenturyLink asked how that was billed.

Kim Isaacs – Integra responded that it was billed Time and Materials. She stated that there was a CLEC Field Verification Option but that they had to use a CenturyLink-approved contractors and an employee to watch the contractor.

Susan Lorence-CenturyLink asked if it was in the ICA.

Kim Isaacs – Integra said that it was and that there was something in the PCAT, but nothing about the payment requirement.

Susan Lorence –CenturyLink stated that rates and charges were outside the scope of CMP, but that this had process change implications.

Kim Isaacs – Integra said the issue is really the need for monitoring.

Susan Lorence –CenturyLink asked if there were other questions from CenturyLink SMEs. There were none. She concluded the meeting by reminding Integra that they would present the CR at the next CMP meeting on Wednesday, December 11, 2013. She also asked if the CR could be split into three different CRs if necessary.

Kim Isaacs – Integra said that she felt initially that would not be an issue.

Susan Lorence-CenturyLink concluded the call at 9:16 AM MT.


CenturyLink Response

April 3, 2014

Kim Isaacs, Integra

SUBJECT: Integra CR PC120213-1, DRAFT RESPONSE for Review This letter is in response to CLEC Change Request PC120213-1, Updates to the Poles, Ducts and Right of Way Process -Automatic Refund of Excess Make Ready Charges

CR Description: Integra requested the following change to the Poles, Ducts and Right of Way (PDR) process: Automatic Refund of Excess Make Ready Charges. Currently, when CenturyLink’s actual Make Ready costs are less than the Make Ready charges paid by the CLEC, CenturyLink requires that the CLEC request a refund within 60 days. Integra requests a change in the existing process which would require that CenturyLink automatically refund (via check or credit) excess Make Ready charges paid by the CLEC. Upon completion of this change request, Integra expects that CenturyLink will automatically refund (via check or credit) any excess Make Ready charges paid by the CLEC.

NOTE: This specific change was originally one of three requested changes on Integra CR PC120213-1. After discussion in the January 2014 CMP meeting, CR PC120213-1 was split into three related CRs to address each of the requested changes separately. This CR now only addresses the first of the three requested changes related to the Make Ready Process.

History: A clarification meeting was held on December 9, 2013 with Integra and CenturyLink representatives in attendance. The CenturyLink SME team has completed an analysis of the requested change associated with the PDR Make Ready Process.

CenturyLink Response: After consideration of the requested PDR change, CenturyLink is denying this Integra Change Request to automatically refund (via check or credit) any excess Make Ready charges paid by the CLEC on the grounds that there is no reasonably demonstrable business benefit or significant customer improvement benefit. During the SME team investigation, they found the volume of this type of situation is relatively low. The SME team determined that rarely do the CenturyLink quotes come back under the Make Ready charges paid by the CLEC so there is typically nothing left to refund. In addition, the SME team found no instances of this Excess Make Ready Charge refund situation specific to Integra. If Integra can show some recent examples of this situation, the SME team will reconsider this change request further.

Sincerely, Susan Lorence CenturyLink Wholesale CMP Project Manager 402 422-4999

February 12, 2014 Kim Isaacs Integra

SUBJECT: Integra CR PC120213-1, DRAFT RESPONSE for Review

This letter is in response to CLEC Change Request PC120213-1, Updates to the Poles, Ducts and Right of Way Process - Automatic Refund of Excess Make Ready Charges

CR Description: Integra requested the following change to the Poles, Ducts and Right of Way (PDR) process: Automatic Refund of Excess Make Ready Charges. Currently when CenturyLink’s actual Make Ready costs are less than the Make Ready charges paid by the CLEC, CenturyLink requires that the CLEC request a refund within 60 days. Integra is requesting a change in the existing process which would require that CenturyLink automatically refund (via check or credit) excess Make Ready charges paid by the CLEC.

NOTE: This specific change was originally the first requested change included on Integra CR PC120213-1. After discussion in the January 2014 CMP meeting, CR PC120213-1 was split into three related CRs to address each of the requested changes separately.

Upon completion of this change request, Integra expects that CenturyLink with automatically refund (via check or credit) any excess Make Ready charges paid by the CLEC.

History: A clarification meeting was held on December 9, 2013 with Integra and CenturyLink representatives in attendance.

CenturyLink Response: The CenturyLink SME team is still completing an analysis of this requested change associated with the PDR Process. We hope to be able to share our response in the March CMP meeting.

Sincerely,

Susan Lorence CenturyLink CR Project Manager


Open Product/Process CR PC082712-1X Detail

 
Title: Download multiple/all .txt files option for Wire Center Tool (Crossed over from SCR082712 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC082712-1X Completed
1/16/2013
Originator: Prull, Steph
Originator Company Name: Integra
Owner: Hansen, John
Director:
CR PM: Hansen, John

Description Of Change

Integra is requesting the ability to choose to download and save selected or all Wire Center CLLIs as an option. We would like to be able to have

a way to have the files download without manual intervention for every file. Integra would continue to see the files as .txt files.

Integra expects Centurylink to provide a way to automatically download selected or all files in the Wire Center CLLI/RLD tool on the web.

https://rld.qwest.com/rld/


Status History


Project Meetings

1/16/13 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR was discussed last month and said we would like to move the CR to a Completed status but before doing that, Mark asked if anyone had used the functionality yet.

Steph Prull – Integra said that yes, Integra had successfully used the new capability and it was OK to move the CR to Completed.

12/12/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CR was originated by Integra as System CR and was crossed over to a Product Process CR during the November CMP monthly meeting with the approval by Integra. Mark said the Level 1 notice will be a sent as a “process option that does not supercede the current process” on 12-12-12 effective immediately with an update to the Raw Loop Data Job Aid.

Kim Isaacs – Integra asked about an earlier notice that had been distributed and this change.

Mark Coyne – CenturyLink said that there was a mix-up in notices and that the correct notice for this CR was going out today.

NOTE: The issue was that a notification had been sent on 12/3/12 that had a process option for a 30K address validation but had the document update for the wire center update associated with the above CR. There was a correction notification sent on 12/11/12 to correct the posted job aid doc on the archive site to match the 12/3/12 notice. The notice for the Wire Center CR was sent on 12/12/12 for those content updates.

Mark Coyne – CenturyLink asked if there were any additional questions. There were none.


Open Product/Process CR PC082808-1IGXES Detail

 
Title: Design, Provision, Test and Repair Unbundled Loops to the Requirements requested by CLEC, including NCI/SECNCI Code Industry Standards
CR Number Current Status
Date
Area Impacted Products Impacted

PC082808-1IGXES Denied
3/13/2009
Originator: Johnson, Bonnie
Originator Company Name: Integra
Owner: Mohr, Bob
Director:
CR PM: Stecklein, Lynn

Description Of Change

In October 2007, Integra notified its Qwest service management team that Integra was experiencing issues with Qwest’s provisioning and repair of xDSL circuits (provisioned on Non-Loaded Loops). Integra and its related entities (“Integra”) have continued to work with its Qwest service management team to address these issues. For example, in May of 2008, Integra provided an example to its Qwest service management team in which HDSL2 service was working fine for Integra’s end user customer; Qwest made a Qwest-initiated change to its network which disrupted the customer’s HDSL2 service; Integra opened a trouble ticket to restore service; and Qwest repair told Integra that Qwest would test and repair only to voice grade parameters, which meant that the end user customer’s HDSL2 service no longer worked (i.e., was permanently disrupted).

Integra communicates the type of service it intends to provide on 2/4 Wire Non-Loaded Loops by using the appropriate NCI/SECNCI codes on the Local Service Request (LSR). However, Qwest has indicated that it now designs, provisions and repairs the circuits to voice grade parameters measured at 1004 Hz, regardless of the NCI/SECNCI code requested on the LSR. The Network Code NC: LX-N indicates that a CLEC is ordering within the Non-Loaded Loop family. As discussed below, it supports a number of digital services depending upon the NCI/SECNCI codes provided on the LSR (e,g., Digital DS0 Level, Advanced Digital Transport, ADSL, Basic Rate ISDN, HDSL2 …). Therefore, an order of LX-N with the NCI code of 02QB9.00H and a secondary NCI code (“SEC”) of NCI 02DU9.00H tells Qwest that it needs to provision, test, and repair for HDSL2 capable service. For example, Qwest needs to ensure that the loop meets the appropriate performance parameters. Each digital service has its own parameters, such as:

• Voice grade analog circuit with Loss at 0 to -8.5 dB at 1004 Hz

• ISDN service Loss at less than 40 dB at 40 kHz

• ADSL service Loss at less than 41 dB at 196 kHz

• HDSL2 service Loss at less than 28 dB at 196 kHz.

When Integra raised the issue of Qwest limiting digital services to voice grade parameters with its Qwest Service Management team, Qwest responded by indicating that “Qwest does not provision requests to meet a specific facility or technology, but rather provisions a class of service, based on the NC codes the CLEC orders.” Integra continues to believe that its current Interconnection Agreements (“ICAs”) require Qwest to provide unbundled loops that transmit digital signals in addition to voice-grade service, etc. Integra reserves its rights under its ICAs. At the same time, in an effort to resolve this issue and at the request of Qwest, Integra is requesting in CMP that Qwest develop and maintain the process and procedures needed to design, provision, test and repair Unbundled Loops so that the circuit will conform to the requirements requested by CLEC, including compliance with the industry standards for the NCI/SECNCI code provided on the LSR. On 7/23/08, Qwest proposed that Integra submit a change request in CMP, including asking Qwest to design, provision, test and repair services in way that takes into account NCI/SECNCI codes standards instead of just the NC codes. Integra includes that request in this CR.

Qwest’s Technical Publication 77384 indicates that a number of advanced digital services are provisioned on Non-Loaded Loops (NC: LX-N), using a variety of NCI/SECNCI codes (for example: Advanced Digital Transport in a variety of spectrum classes, Basic ISDN – NCI: 02QC5.OOS, HDSL - NCI: 02QB9.00H). Qwest’s Technical Publications indicate that the NCI/SECNCI codes conform to the various ANSI standards for the specific digital service. However, as noted earlier, the Qwest service management team confirmed that it is Qwest’s current practice to design, provision, test and repair these digital services delivered on Unbundled Loops based on the NC code which delivers voice grade parameters measured at 1004Hz, even though each digital service has its own parameters for optimum performance. Integra is requesting that Qwest use the industry standards for NCI/SECNCI codes provided on the LSR when designing, provisioning, testing and repairing Unbundled Loops. For example, an Unbundled Loop ordered on the LSR with the Basic ISDN NCI: 02QC5.OOS should be designed, provisioned, tested and repaired per industry standards using a loss based on 40 kHz, not the voice grade 1004 Hz. Additionally, an Unbundled Loop ordered on an LSR with HDSL NCI 02QB9.00H should be provisioned using loss based on 196 kHz. When Qwest grandparented the ADSL compatible loop (only for CLECs without any ADSL compatible loop terms in their ICAs), Qwest pointed to the 2 Wire Non-Loaded Loop as an alternative to the ADSL compatible loop. However, per Qwest’s current stated position regarding designing, provisioning, testing and repairing to the NC code only, the 2 Wire Non-Loaded Loop would not be a reliable or serviceable alternative to an ADSL compatible loop. For a 2 Wire Non-Loaded loop to be a viable alternative to an ADSL compatible loop, Qwest should design, provision, test and repair digital capable Non-Loaded loops (such as HDSL capable or ADSL compatible loops) based on the NCI code as well.

While Qwest has said that it does not provision requests to meet a specific facility or technology, it should provision requests in compliance with industry standards and as ordered by CLEC, including providing working digital capability/compatibility when that capability is ordered. The SGATs, like the recent Qwest-Eschelon Minnesota and Arizona ICAs (§9.2.2.3), define 2/4 wire non-loaded loops as “digital capable” loops. The SGATs and the recent Qwest-Eschelon ICAs (§9.2.2.1.1 & 9.2.2.1.2) provide that use of the words “capable” and “compatible” to describe Loops means that Qwest assures that the Loop meets the technical standards associated with the specified Network Channel/Network Channel Interface codes, as contained in the relevant technical publications and industry standards. Qwest’s stated position that its current process recognizes only the “Network Channel” code but not the “Network Channel Interface” is inconsistent with this long-established principle. Similarly, the Qwest-Integra Oregon ICA has been in place since 2000 (for Integra as well as other CLECs, as it is based on the Qwest-AT&T ICA). That ICA (Att. 3, §2.1 and subparts) defines an unbundled loop to include loops that transmit digital signals and provides that CLEC may order special copper loops unfettered by any intervening equipment and which do not contain any bridged taps, so that CLEC may use the loops for a variety of services by attaching appropriate equipment. For example, when a CLEC orders an HDSL2 capable loop (identified on the LSR by using the NC code of LX-N with the NCI code of 02QB9.00H and a SEC code of NCI 02DU9.00H), the CLEC should receive a loop unfettered by intervening equipment so that CLEC may provide working HDSL2 service over the HDSL2 capable loop by attaching appropriate equipment. Regarding repair after a Qwest maintenance or modernization event, the SGATs and recent Qwest-Eschelon ICAs (§9.1.9) provide that network maintenance and modernization activities will result in UNE transmission parameters that are within transmission limits of the UNE ordered by CLEC. If CLEC orders a 2/4 wire non-loaded loop that is digital capable (such as ADSL compatible or HDSL2 capable), then the loop must be restored to the appropriate digital capable level after a Qwest maintenance or modernization event. In short, if a loop qualifies for a digital service, the circuit should work (and continue working) for that digital service.

Qwest will design, provision, test and repair Unbundled Loops to the requirements ordered by CLEC, including industry standards for the NCI/SECNCI codes provided on the LSR. Qwest should take into account NCI/SECNCI code standards, and not just the NC codes. When a CLEC orders a 2/4 wire non-loaded loop for providing a digital service (e.g., as identified using the applicable NCI/SECNCI code on the LSR), Qwest will not limit the design, provisioning or repair of 2/4 wire non-loaded loops to voice grade parameters (e.g., measured at 1004 Hz). After repairs and Qwest network maintenance and modernization changes, the end user customer’s service should work for the service ordered by CLEC.


Status History


Project Meetings

3/20/09 Escalation #45 Initiated by Integra at:http://www.qwest.com/wholesale/cmp/escdisp.html

3/18/09 Prod/Proc CMP Meeting Bob Mohr-Qwest reviewed the denial response that can be located in the CR description as follows: The Unbundled Non Loaded Loop product was developed to interface with various applications contained in Technical Publication 77384. For Unbundled Loop LX-N Network Channel (NC) codes, the NCI codes are informational only, as stated in the above mentioned Technical Publication and do not affect transport designs or performance. The associated NC code requires that the service use non-loaded, metallic facilities free of faults (grounds, shorts, noise, or foreign voltage). The CLEC has responsibility to inspect the character of the facilities, e.g. gauge, length, etc and determine that the facility is appropriate for their specific application. Because Qwest is under no obligation to provide the product in the manner requested by CLEC, and Qwest is only obligated to provide a Non Loaded Loop to the broader standards listed in Technical Publication 77384, this Change Request to Design, Provision, Test and Repair Unbundled Loops to the requirements of the NCI code required a business discussion regarding the benefit to providing Non Loaded Loops in this manner vs. the cost to do so. That is, because there is no obligation to provide Non-Loaded Loops in this manner, the decision to implement this CR becomes one of economics. Absent the CLEC community agreement to negotiate in good faith to perform cooperative testing, this request becomes economically not feasible for Qwest. Therefore, Qwest respectfully denies this request. Bonnie Johnson-Integra commented that from Integra’s perspective hearing that NC/NCI codes are informational only is a surprise and they don’t agree.(3/27/09 Comments to minutes received from Integra) Bonnie said Qwest can name a product whatever it wants, but it doesn’t change Qwest’s obligations. Bonnie said that they are escalating this and the other denied CR. She said that Integra has provided detailed information .(3/27/09 Comments to minutes received from Integra) in its CRs and in the response about testing and Qwest hasn’t responded .(3/27/09 Comments to minutes received from Integra) to any detail. Bonnie said that .(3/27/09 Comments to minutes received from Integra) you do not negotiate in CMP. You negotiate ICAs they don’t agree that Qwest doesn’t have an obligation to what has been negotiated in the ICAs and have a right to this type of loop and Qwest can’t continue negotiate. She said that they want a revised response for both CRs .(3/27/09 Comments to minutes received from Integra) the respond to the cites and detail Integra provided. Liz Balvin-Covad said that Qwest is provisioning a product they can’t test and turn up in a mechanized way. Bob Mohr-Qwest said that Qwest is provisioning a non loaded loop product with an HDSL interface. Liz Balvin-Covad asked if this was being done manually. Bob Mohr-Qwest said it uses the standard provisioning Unbundled Loop provisioning process. Kim Isaacs-Integra asked Qwest to explain an HDSL interface. Jamal Boudhaouia-Qwest said that we provide a 2-4 wire non loaded loop with the capability to transport multiple protocols. Jamal said we give access to the Raw Loop data through IMA and we don’t restrict the use of the loop. He said that we let the CLEC determine what protocol they want to support. Kim Isaacs-Integra said if they find the loop there is no way to reserve the most compatible loop. Jamal Boudhaouia-Qwest said that it is the same for Qwest with no reservation and it is first in first out. Kim Isaacs-Integra said that Qwest .(3/27/09 Comments to minutes received from Integra) has already said it does this for itself. Qwest service runs through the CSA guidelines. Jamal Boudhaouia-Qwest said that is a finished service and (3/27/09 Comments to minutes received from Integra) and has a USOC associated with an NC/NCI code. He referred to tech pub 77384. The CLEC community has the opportunity to order the DS-1 capable loop that is the same as the retail offering that Qwest offers its end users. Kim Isaacs-Integra said they provide the NC/NCI code. Jamal Boudhaouia-Qwest said that the NC/NCI codes are for information only as documented in tech pub 77384. Bonnie Johnson-Integra said that the industry drives the NC/NCI codes and Qwest tech pubs are intended to be based on the industry standard. She asked if Qwest was insinuating that they develop a product and pick the NC/NCI codes out of a hat. Liz Balvin-Covad said the loop is provisioned to the specified NC/NCI codes but you don’t provision to the HDSL functionality. Jamal Boudhaouia-Qwest said that you could qualify a loop for HDSL and that the NC code determines the type of loop being requested. Kim Isaacs-Integra said that in reality you order HDSL or ADSL using LX-N and the appropriate NC/NCI codes. Kim said that pre-qual, in the past, has delivered a loop that does not support the functionality. She said that when a bridge tap issue is identified, Qwest says they only need to provide to voice grade standards and still does not understand why NC/NCI codes are informational only. Jamal Boudhaouia-Qwest said that the NCI codes are used for spectrum management purposes within copper.(3/27/09 Comments to minutes received from Integra) but not for provisioning or testing. The language in the ICAs and the negotiation template provides the reasons for the CLECs to provide Qwest with the correct NC/NCI code combinations. Liz Balvin-Covad asked why Qwest only provisions to voice grade. Jamal Boudhaouia-Qwest said that network was built and managed to voice grade. However, we provision the non-loaded loop to a higher grade than voice grade. As most every one here knows, voice grade can run on loaded loops. So Qwest provisions the non-loaded loops to a higher grade than voice grade. Liz Balvin-Covad asked what happens when it is non loaded and when you test and run into the situation that it has to be conditioned. Kim Isaacs-Integra said that the argument with Qwest is the definition of excessive bridge tap and the amount of bridge interference. Kim said that there are issues with the digital and voice grade parameters. Jamal Boudhaouia-Qwest said that digital data services, by definition, encompass any digital bits ranging from 9.6KB up to 20 Megs and digital data service could be supported on bridge tap. Jamal said that he wanted to get back to Covad’s question of manual vs. mechanized. Liz Balvin-Covad asked when they order 2/4 wire that is in their contracts, does Qwest have the ability to assign the loop electronically. Jamal Boudhaouia-Qwest said it is assigned electronically and that the order will flow through IMA. Liz Balvin-Covad asked if the USOC was available. Jamal Boudhaouia-Qwest said the USOC is not available for the HDSL capable loop. Liz Balvin-Covad-asked if HDSL is a Qwest supported functionality. Jamal Boudhaouia-Qwest said HDSL is a protocol to provide DS1 which could be provided using multiple technologies HDSL, AMI, SONET etc. He said that HDSL is just one of the protocols. Jamal said that using the 2/4 wire non loaded loop, the mux will generate the HDSL signal to transport DS1. Liz Balvin-Covad asked what excessive bridge tap is and will Qwest remove. Kim Isaacs-Integra said that is where they run into trouble. Jamal Boudhaouia-Qwest said that there are different requirements for different protocols and technologies. Liz Balvin-Covad-asked why this CR was being denied for economically not feasible reasons. Bob Mohr-Qwest said that the CR is being denied because of the cost of the equipment to perform the testing and the training required for the technicians to perform HDSL testing. Jamal Boudhaouia-Qwest said that we don’t do manual testing from the Central Office for Qwest today. Jamal said that after provisioning the testing is done through the centers. He said that we have asked the CLEC community to negotiate a testing process for HDSL similar to what tests Qwest performs for itself. Also, Qwest would be able to negotiate the technical parameters to test to with the CLEC community. He said that to make sure that the facility meets the requirements of the services to be provisioned on the loop, we need to consider the added length at the Central Office and the Customer Premises. He said that a 2000 feet copper segment could be added to the loop length and testing end-to-end becomes critical in the delivery of the service to the end user. Kim Isaacs-Integra said that (3/27/09 Comments to minutes received from Integra) Qwest she was assuming that the CLEC was making no consideration for the length in office and the end user location. Kim said that they make the calculation and place their order and Qwest auto assigns the loop with no load coil. She said that some will work and asked if Qwest was refusing to determine the location of the bridge tap. Bonnie Johnson-Integra said that Qwest (3/27/09 Comments to minutes received from Integra) said that they don’t do this testing for themselves and that they assign the facility following the CSA guidelines. She said that Qwest is expecting them to do testing that they don’t do for themselves and that they want parity that is currently in their contract. Jamal Boudhaouia-Qwest said that he respectfully disagreed. He said that he is asking for cooperative testing to mirror what Qwest does for itself. He said that the CLEC would be to interject a signal from their center and Qwest technicians in the field would receive the signal. Liz Balvin-Covad asked if there was a cost associated with cooperative testing. Bob Mohr-Qwest said that we have not looked at that. Liz Balvin-Covad asked what Qwest will do if they do the cooperative testing and determine excessive bridge tap. Bob Mohr-Qwest said that if cooperative testing is done and excessive bridge tap is causing impediments and the CLEC authorizes conditioning, Qwest will remove excessive bridge tap as is our process today. Julia Redman-Carter-PAETEC asked if Qwest would waive it. Bonnie Johnson-Integra said that (3/27/09 Comments to minutes received from Integra) Qwest said the test in not done in the CO because Qwest said they are not equipped to do that. Jamal Boudhaouia-Qwest said that we don’t have testing equipment in the CO and is very inefficient to do the testing in the CO. Jamal said that to do HDSL signal testing it would be done in the centers and that the CLECs can do this. Liz Balvin-Covad asked if the CLEC can launch that test. Jamal Boudhaouia-Qwest said yes, they can interject the signal. Bonnie Johnson-Integra asked what Centers Qwest was referring to. Jamal Boudhaouia-Qwest said that he was referring to the provisioning, maintenance and alarm centers. Jamal said that he did not know how the CLECs operate their business but that most telecom companies have some type of network operation center that is used to monitor the health on the network. Bonnie Johnson-Integra asked for more information on the repair aspect and that she did not understand how Qwest can deny. Bonnie said that the FCC requires that Qwest (3/27/09 Comments to minutes received from Integra) not limit testing to test to Voice Grade parameters. Jamal Boudhaouia-Qwest said since Integra is referencing the FCC requirements, the question becomes one of a legal nature. Bonnie Johnson-Integra said that they asked this question in the escalation and want a complete response. Mark Coyne-Qwest said that this question has been addressed in previous meetings and we believe that it has been answered. Julia Redman-Carter-PAETEC asked that Qwest provide the legal response. Mark Coyne-Qwest said that we will take this into consideration. Bonnie Johnson-Integra said that this before this CR was originated, they tried to resolve with their Service Manager and were told that they need to take the issue to CMP. Bonnie said that when they presented this CR they did not feel that they needed to bring this to CMP. She said that Qwest should respond to all citations in the escalation and respond to the (3/27/09 Comments to minutes received from Integra) to the Integra’s response to testing. Liz Balvin-Covad asked if the limits to test only to voice grade is limited to 2 wire non loaded. Jamal Boudhaouia-Qwest said that it is called out in the tech pub and does specify 2 and 4 wire. Jamal said that he will send to Mark and will be provided in the notes. Kim Isaacs-Integra said that the tech pub says 2 or 4 wire is tested to voice grade parameters.

2/18/09 Prod/Proc CMP Meeting Mark Coyne-Qwest said that this CR is currently in a development status and will remain as is based on the discussions regarding cooperative testing. (2/26/09 Comments to minutes received from Integra) Bonnie Johnson-Integra asked if we were going to discuss this CR on the call today. Mark Coyne-Qwest said that the last CMP Meeting Integra took an action to provide a response to Qwest regarding the cooperative testing. Bonnie Johnson-Integra said that Integra provided Qwest a formal response on 2/4/09 and has not received anything back and needs to decide on next steps. She said that she wanted the 2/4/09 response included in the body of the CR. (3/2/09 Comments to minutes received from Integra) Mark Coyne – Qwest stated Qwest has Integra’s response Bonnie Johnson – Integra indicated that Integra provided Qwest with Integra’s response on 2/4/09 and asked if there was confusion at Qwest. Bonnie asked if Qwest has taken any action on Integra’s response. Mark Coyne – Qwest stated actions have been taken but the SME team is not prepared to discuss them at this time. Lynn Stecklein-Qwest said that she would get the response posted. Mark Coyne-Qwest said if Integra’s position is to not test, Qwest will look at a response. Liz Balvin-Covad asked why Qwest required testing on the HDSL product when it is not required on the 2 – 4 wire that has 6 installation options available. Bob Mohr-Qwest said that we have had lengthy discussions on why we need this for HDSL. Bonnie Johnson-Integra said that in the Denial on implementing the USOC the issue was a financial liability. Bonnie said that they would like Qwest to implement a manual process and add a remark to assign the appropriate loop when submitting orders. Mark Coyne-Qwest said that Jamal has addressed the manual process. Jamal Boudhaouia-Qwest said that even with the manual process, cooperative testing is still a required. He said that Qwest has stated their position in the past and has been document in previous meeting minutes. 2/26/09 Comments to minutes received from Integra) Doug Denney-Integra asked Qwest to clarify that it’s position is that even though Qwest is unable to test the loop, CLECs should be able to test. Jamal Boudhaouia-Qwest said that Qwest’s position has previously been documented. Bonnie Johnson-Integra asked why Qwest was reluctant to speak to the process for those who have not been in those meetings. She asked what Qwest was going to do about repair if the HDSL loop is working and then needs repair. Bob Mohr-Qwest said that we need cooperative testing on a repair basis. Liz Balvin-Covad asked if there was a charge for the cooperative testing because Qwest is saying they can’t do without both parties. Bob Mohr-Qwest said that has not been identified. Doug Denney-Integra asked in a repair situation for HDSL, is Qwest going to undertake what Qwest does for themselves, i.e. checking for bridge tap and load coil. Jamal Boudhaouia-Qwest said the (3/2/09 Comments to minutes received from Integra) electrical testing is done as stated previously the tests have been described. Bonnie Johnson-Integra asked if Qwest’s process going forward is to continue to test to voice grade level and not to the HDSL standard. Bob Mohr-Qwest said this (2/26/09 Comments to minutes received from Integra) has not been decided the CR is requesting to test to those limits. Bonnie Johnson-Integra asked if we do nothing with the CR, will Qwest continue test to voice grade level and would it be status quo for voice grade only. Bonnie said that (2/26/09 Comments to minutes received from Integra) Jamal said in a previous meeting he was unaware that was taking place and she never received a response to that question. Jamal Boudhaouia-Qwest said that we did talk to this in previous meetings and that he will review the minutes. Doug Denney-Integra said that Qwest’s denial on the exception CR states that there is a financial risk and asked what Qwest was referring to. Bob Mohr-Qwest said that the financial liability is associated with the cost of equipping and training the technicians to perform the test at this level. Doug Denney-Integra said that the other CR doesn’t ask Qwest to do this and that they only want the USOC implemented. He said he was not sure how that fits into the rejection of the CR. Bob Mohr-Qwest said that the CR would be a half solution without testing and would shift additional liability to the repair process and Qwest is not willing to implement a partial solution. Doug Denney-Integra said that Integra is (3/2/09 Comments to minutes received from Integra) still reviewing Qwest’s denial of the other CR and may have more questions.

2/4/09 Integra Response On the January 21, 2009 CMP call, Integra agreed to consider the comments that Qwest had made on that call and respond in writing. Integra provides this response to Qwest. Please ensure that this response in included in the detail for CR PC082808-1IGX.

The Issue

Integra believes that Qwest has not appropriately framed the issue. Qwest focuses on one issue (Qwest’s view of testing) to the exclusion of the larger issues outlined in Integra’s change request (CR). Qwest’s approach suggests that Qwest may stop all progress on all aspects of the CR if one issue that it claims is “critical” is not handled in the manner proposed by Qwest. Integra disagrees with that approach.

In the January 21st CMP meeting, Qwest (Jamal) erroneously said that Integra’s “original CR calls for a test process” (see footnote 1) and that this is a “new process.” (see footnote 2) That is simply not the case, as is clear from reading the entire CR. It is also apparent from the CR’s title, which does not request a “test process” but asks Qwest to “Design, Provision, Test, and Repair Unbundled Loops to the requirements requested by CLEC, including NCI/SECNCI Code Industry Standards.” In other words, even when using existing processes (including existing testing), Qwest needs to apply the applicable NCI/SECNCI codes. The example provided by Integra in the first paragraph of the CR makes this even more clear:

For example, in May of 2008, Integra provided an example to its Qwest service management team in which HDSL2 service was working fine for Integra’s end user customer; Qwest made a Qwest-initiated change to its network which disrupted the customer’s HDSL2 service; Integra opened a trouble ticket to restore service; and Qwest repair told Integra that Qwest would test and repair only to voice grade parameters, which meant that the end user customer’s HDSL2 service no longer worked (i.e., was permanently disrupted).

In this example, Qwest already has a process for testing as part of a repair. The issue is that Qwest personnel, when using that process, should not take the position that Qwest will test “only to voice grade parameters” but instead should test to the standard applicable for the requested service (e.g., a loop capable of carrying data). As pointed out in the CR, it has long been established (e.g., in the SGATs and in ICAs, such as those cited in the CR going back to 2000) that use of the words “capable” and “compatible” to describe Loops means that Qwest assures that the Loop meets the technical standards associated with the specified Network Channel/Network Channel Interface codes, as contained in the relevant technical publications and industry standards. Therefore, this is a process that had long been in place (until recently, when Qwest starting telling Integra that it would test only to voice grade parameters). Qwest needs to restore compliance with the ICA terms requiring testing to the appropriate levels.

The above example involved a repair. The same is true for loop installations. During the CMP clarification call, Qwest (Jamal) asked Integra how Qwest would provide the test results to Integra. Integra responded:

“Doug Denney-Integra said that there are different installation options that exist today and some of those require different degrees of test results being provided by Qwest. He said that those are described in the Carrier’s contracts and when we set up the cost for those options. He said they are not attempting to (9/12/08 Comments to minutes from Integra) change the process of providing test results with regard to provisioning loops.” (see footnote 3) (Emphasis added) Integra asked Qwest in its CR to perform the tests Qwest is currently obligated to perform per the ICAs for the installation option ordered. As noted above, Qwest should be testing to the levels appropriate for the type of circuit ordered.

Installation

Qwest provides CLEC with multiple types of loops and, for each, various installation options. Types of Unbundled Loops and Assignment of Those Loops Qwest provides multiple types of loops to Integra and other CLECs. For example, Qwest’s ICA negotiations template in Section 9.2.2.2 addresses “Analog (Voice Grade) Unbundled Loops” and in Section 9.2.23 addresses “Digital Capable Loops – DS1 and DS3 Capable Loops, Basic Rate (BRI) ISDN Capable Loops, 2/4 Wire Non-Loaded Loops and xDSL-I Capable Loops.” Section 9.2.2.3 provides that digital capable loops, including “2/4 Wire Non-Loaded Loops,” are “capable of carrying specifically formatted and line coded digital signals.” That means that, when Qwest delivers the loop, it must deliver a loop capable of providing data to the CLEC to have met its obligation to provide the digital capable loop ordered by the CLEC. There is no exception in 9.2.2.3 for providing a loop that is not digital capable and then later, after imposing extra work and delays upon CLEC, providing a different loop that is digital capable. Qwest’s ICA negotiations template Section 9.2.2.3 also states: Qwest will provision digital Loops in a non-discriminatory manner, using the same facilities assignment processes that Qwest uses for itself to provide the requisite service. (emphasis added) A key problem that exists today, however, is that Qwest is not meeting this commitment. For CLECs, Qwest’s facilities assignment process does not select/assign the best (most qualified loop available for the type of loop ordered by the CLEC. Instead, it is just as likely, or more likely, to assign a voice grade (see footnote 4) loop to fill a CLEC request for a digital capable loop. In contrast, for Qwest retail, Qwest automatically assigns the best (most qualified) loop available for the type of loop ordered by Qwest retail.(see footnote 5) Every day that this situation continues is another day of discrimination, and so Qwest should make every effort to accelerate resolution of this problem. Existing Loop Installation Options

Qwest also offers multiple loop installation options (basic, coordinated, cooperative testing, etc.). Qwest lists its installation option offerings in its ICA negotiations template Section 9.2.2.9, which provides that the options are available for all types of loops, though the price may vary by option. Section 9.2.2.9.1 provides that “Basic Installation” is available for all “new or existing Unbundled Loops,” which includes for example 2/4 Wire Non-Loaded Loops. For a basic installation of a loop, Section 9.2.2.9.1 provides that Qwest completes its work and Qwest calls the CLEC, and for new service Qwest conducts performance testing but does not provide the test results to CLEC. As indicated above (and reflected in the 9/9/08 CMP Clarification Call minutes), Integra is not attempting to change this option (which in most, if not all, Qwest states is available to CLECs at a commission-approved rate).

As Integra understands Qwest’s current proposal, however, Qwest is seeking to alter this option – by removing the basic option altogether for HDSL (2 and 4 wire non loaded loops) and insisting instead on not only a more expensive installation option (cooperative testing) but also requiring time consuming and costly joint meets in circumstances when they are unnecessary and not required for Qwest retail. For Qwest retail, however, Qwest assigns a loop following CSA guidelines and, if it does not work, will perform the repair. (see footnote 6) To be nondiscriminatory, a basic installation option must remain available to CLECs for digital capable loops.

Specifically, Qwest admitted that for comparable types of service, Qwest does not perform or require its staff to perform the work it seeks to require CLECs to perform. Qwest said:

Jamal Boudhaouia - He said that we will check to see if the bridge tap is interfering with it. He said that Qwest does not do HDLS [sic] test in the CO because we are not equipped to do that and the equipment is very expensive. (12/30/08 Comments to minutes received from Integra) When we hook to the HDSL mux we test remotely - it works or doesn't work - we don't have the ability to test the raw loop, we look for open shorts, bridge tap, or Load Coils that we missed. (see footnote 7) (Emphasis added)

In other words, Qwest “does not do HDSL2 tests in the CO” for every installation for itself, but Qwest is attempting to force HDSL2 tests in the CO upon CLECs by requiring joint cooperative testing in the case of every loop installation. This is inefficient and creates unnecessary work, delay, and expense for CLECs. For example, if a CLEC that has 50 collocations throughout a city has ordered loops with the same due date for 3 installations in 3 unmanned collocations spread far apart in that city, Qwest would require CLEC to dispatch technicians all over town that day to jointly test for problems, even though the loops may in fact work when delivered (and should work, if proper facilities are assigned). For CLECs, Qwest proposes to require joint testing 100% of the time.

In contrast, Integra’s position is much more efficient, because it isolates joint testing to those limited circumstances when joint testing is truly required. Per Integra’s position, when Qwest assigns a loop capable of carrying data consistent with industry guidelines, in most cases the loop should work as intended. Therefore, no joint testing is required. Even assuming the loop does not work upon delivery, CLEC will be able to perform tests once it hooks up its equipment. Qwest’s existing processes require CLEC to perform trouble isolation before reporting trouble to Qwest and to submit its test results with its trouble report. (See Qwest’s ICA negotiations template Sections 12.3.3.5 & 12.3.4.) As with any other basic loop installation after which the loop does not work, the companies may agree on the cause of the problem and the solution. If the CLEC reports that its tests indicate, for example, that excessive bridged taps are interfering with its HDSL2 service and Qwest agrees, no joint meet its required. (see footnote 8) Only in the sub-set of installations for which the loop does not work and the companies do not agree on trouble isolation may joint testing be required. (see footnote 9) This is a far more efficient than Qwest’s proposal to require joint testing for 100% of installations.

As discussed above, a key problem that Integra’s CR is attempting to address is that, when Qwest provides a digital loop with a basic installation to CLECs, the facilities assignment process should take care of as many problems in advance of loop delivery as the facilities assignment process for Qwest retail. For example, if a Qwest retail customer that orders a digital service is unlikely to be assigned an analog facility with excessive bridged taps, a CLEC that orders a digital service should also be just as unlikely to be assigned an analog facility with excessive bridged taps. Once Qwest’s facilities assignment process is nondiscriminatory, the need for CLECs to request repairs after a basic installation should be reduced accordingly. In other words, repairs following installations that are caused by Qwest delivering a voice grade loop when in fact a digital loop was ordered should be substantially reduced, if not eliminated.

Qwest is legally and contractually obligated to deliver the loop a CLEC orders within the industry standard parameters for that loop. Qwest appears to have taken the position, however, that if CLECs will not agree to order and pay for cooperative testing (despite the availability in its ICAs of basic installation at Commission-approved rates), Qwest will not implement the USOC for CLECs that will allow Qwest’s systems to assign a loop for CLECs that will support the type of service the CLEC ordered. Qwest refers to this as “Gate one.” (see footnote 10) Qwest is basically saying it will not do one without the other. (see footnote 11) As Qwest knows from previous communications, Integra does not agree. There is no legitimate reason to link the two. Qwest needs to bring its facilities assignment process into compliance and make it nondiscriminatory. If implementing the USOC for CLECs is the means by which Qwest may do that (at least for one of the products, HDSL), Qwest should have done it by now given its obligations but certainly should not delay it any longer by attaching inappropriate pre-conditions to implementing the USOC. (see footnote 12) Integra will comply with the installation option provisions in its ICAs, including basic installation. Qwest needs to ensure that, before delivering a loop, Qwest is first assigning a loop that meets the industry standards for that type of loop. Qwest cannot cure its failure to appropriately assign a loop on a nondiscriminatory basis by shifting the burden to CLECs to perform work that would not be necessary if the assignment process worked as it should. Once it works as it should, there may be little or no need for joint testing or repair, because the delivered loop will work as intended for the service ordered.

To be nondiscriminatory, a proper facilities assignment process should be automated for CLECs, just as it is for Qwest retail. Qwest should ensure the process is automated, including implementation of a USOC(s) if that serves this purpose. With respect to the USOC for HDSL, Integra has submitted a separate CR for Implementation of USOC to Correct Facilities Assignment for HDSL” to attempt to ensure that the USOC is implemented without delay.

Until the facilities assignment process is automated for all affected products, and without waiving any rights, Integra asks Qwest as an interim measure to train its personnel to use the existing manual process (by which remarks in an order cause an order to fall out for manual handling) so that, when a remark indicates that the facility being ordered is a digital capable service (e.g., HDSL2), Qwest personnel will assign the type of facility needed for the digital capable loops (including compliance with industry standards). CLECs preferring automatic facilities assignment will be able to avoid this manual process by not using remarks. Footnotes: Qwest should deliver a loop capable of supporting the type of service ordered by the CLEC, which will reduce problems at installation and reduce the number of needed repairs to make the service work as intended.

Repair, including repairs following Qwest maintenance and modernization activities

The example that was included in the first paragraph of Integra’s CR (copied in part above) involved a repair not associated with an installation. A Qwest process already exists that enables CLECs to make comments when submitting trouble reports. When a CLEC, as part of those comments, identifies the facility to be repaired as a digital capable facility (e.g., HDSL2), Qwest needs to treat that facility accordingly. For example, Qwest personnel cannot (as they did in the example) tell the CLEC that Qwest will test and repair only to voice grade parameters, even though the facility is supposed to be capable of carrying data. (see footnote 13)

To the extent that problems, such as the one in the example, occur because of inadequate training, Qwest should promptly train its personnel as to the appropriate parameters for services capable of carrying data. Once a facility is identified (by CLEC or Qwest) as a digital capable service (e.g., HDSL2), there should be no more instances when Qwest personnel as a matter of policy refuse to test to the industry standards/parameters for that service.

To the extent that problems, such as the one in the example, occur because Qwest repair personnel are relying on circuit ID or other indicators suggesting that a loop is an analog loop when in fact it is a digital capable loop, Qwest should promptly train its personnel to accept input from CLECs as to the type of service. For example, if a CLEC tells Qwest in written remarks or on a telephone call (consistent with applicable Qwest process) that a facility was ordered as HDSL2, the Qwest repair personnel should not take the position that Qwest will not treat it for testing and repair purposes as HDSL2 because the circuit ID or other indicator suggests otherwise. Qwest should test and repair it per the applicable industry standards for the digital capable service identified by CLEC.

There is no reason to wait for implementation of a USOC to ensure that repairs are performed in a manner appropriate for the service ordered by the CLEC. Even after a USOC(s) is implemented for new ordering, digital capable loops (including HDSL2 circuits) will exist in the embedded base. If Qwest does not identify these facilities itself, Qwest will have to rely on information provided by CLEC as to the type of facility ordered when facilities in the embedded base need repair. Qwest should be relying on that CLEC-provided information now.

Qwest has identified no systems change or other change that is needed before implementing the requested training. Certainly, there is no legitimate reason to tie Qwest’s position on testing at installation to testing for these repairs.

Footnote 1 - See http://wholesalecalendar.qwestapps.com/detail/10/2009-01-21 and link to minutes from 1/21/09 CMP Product/Process meeting. Footnote 2 - See http://wholesalecalendar.qwestapps.com/detail/10/2009-01-21 and link to minutes from 1/21/09 CMP Product/Process meeting. Footnote 3 - See http://www.qwest.com/wholesale/cmp/cr/CRPC082808-1IGX.html minutes from 9/9/08 clarification meeting. Footnote 4 - Because Qwest used the term “voice grade” to describe the type of loop it was then testing to (see above example from the first paragraph of the CR), Integra uses that term in this response for ease of reference. Footnote 5 - See, e.g., http://www.qwest.com/wholesale/cmp/cr/CRPC082808-1IGX.html minutes from 12/17/08 CMP meeting (Jamal Boudhaouia-Qwest - “The Qwest HDSL2 goes through the CSA guidelines and Qwest will do remote testing from the center.”; “Qwest said that we have to take the necessary steps for the centers and LFACs to make sure the facility is qualified. He said that we have 2 extra steps - the technician needs to be equipped and that we have the insertion for the CSA guidelines.”); see also See http://wholesalecalendar.qwestapps.com/detail/10/2009-01-21 and link to minutes from 1/21/09 CMP Product/Process meeting. (Jamal Boudhaouia-Qwest – “Qwest retail does not use a manual process.”) Footnote 6 - See http://www.qwest.com/wholesale/cmp/cr/CRPC082808-1IGX.html minutes from 12/17/08 CMP meeting (quoted below). Footnote 7 - See http://www.qwest.com/wholesale/cmp/cr/CRPC082808-1IGX.html minutes from 12/17/08 CMP meeting. Footnote 8 - This assumes that Qwest is not enforcing a policy of testing only to voice grade parameters even when the CLEC informs Qwest that its service is supposed to be capable of carrying data, as discussed below regarding repairs. Ensuring Qwest’s personnel are properly trained in this regard is one of the purposes of Integra’s CR. Footnote 9 - When a joint meet is required, the Qwest-Eschelon approved ICAs in MN, OR, and UT provide for joint repair appointments. See 9.2.5.2.1. Footnote 10 - See http://www.qwest.com/wholesale/cmp/cr/CRPC082808-1IGX.html minutes from 11/12/08 CMP meeting. Footnote 11 - See http://wholesalecalendar.qwestapps.com/detail/10/2009-01-21 and link to minutes from 1/21/09 CMP Product/Process meeting. Jamal at Qwest said if CLECs can not complete co-op testing we need to re-analyze the CR. Footnote 12 - See http://wholesalecalendar.qwestapps.com/detail/10/2009-01-21 and link to minutes from 1/21/09 CMP Product/Process meeting. “Doug Denney-Integra (1/30/09 Comments to Minutes received from Integra) said while we would all like 100% perfection there is the opportunity for and improvement along the way. He asked why we want to delay the USOC and manual process because of the testing issue when by using the USOC we could get to 80% improvement today. Footnote 13 - See, e.g., Qwest-Eschelon OR ICA: “9.1.9 In order to maintain and modernize the network properly, Qwest may make necessary modifications and changes to the UNEs in its network on an as needed basis. Such changes may result in minor changes to transmission parameters. If such changes result in the CLEC’s End User Customer experiencing a degradation in the transmission quality of voice or data, such that CLEC’s End User Customer loses functionality or suffers material impairment, Qwest will assist the CLEC in determining the source and will take the necessary corrective action to restore the transmission quality to an acceptable level if it was caused by the network changes. . . .” (emphasis added).

1/21/09 Product/Process CMP Meeting

Bob Mohr-Qwest said that Qwest met with the Database administrator to develop the timeline and systems requirements for the implementation of the USOC. Bob said that the table changes will be worked with the system release in (1/30/09 Comments to Minutes received from Integra) mid April. He said that joint cooperative testing is a critical component for the success of this effort. Bob said that between now and April we will make necessary changes to the PCAT, Tech Pubs, Contract Language, and Internal documentation. This will include changes for ISDN BRI and ADSL Non Loaded ordering as well. Bob said that Cooperative testing must be included in that solution.

Bonnie Johnson-Integra said Integra proposed, until the USOC can be put in place, implementation (1/30/09 Comments to Minutes received from Integra) of a manual work around to bring relief. The work around is to drop to manual handling and the type of loop would be identified in the Remarks. Bonnie said that Qwest responded that they were not implementing manual process. Why can’t Qwest implement Integra’s proposal

Jamal Boudhaouia- Qwest said that LFACs will look for a HDSL qualified Facility when the new USOC is present. He said that based on the NC codes the USOC will be assigned. He said that if the USOC is not there LFACs doesn’t know what to assign and that the remarks is informational only. He said that IMA will drive LFACs to assign the correct facility.

Bonnie Johnson-Integra said that (1/30/09 Comments to Minutes received from Integra) for a period of time in the past, Qwest used this process for ADSL. Today there is a process where if the order does not flow through, it will drop to manual assignments and are there are codes associated with the process. Bonnie asked if the concern was that the Qwest resources would not know what kind of loop to assign and couldn’t Qwest train their people on this process.

Jamal Boudhaouia-Qwest said that to drop every loop to manual handling is economically not feasible and there will be delays during provisioning and additional hold time.

Bonnie Johnson-Integra said that it didn’t sound like this is a system or training issue (1/30/09 Comments to Minutes received from Integra) but that Qwest was concerned about the volume of orders and that Integra is only proposing that HDSL2 loops be dropped to manual handling, not all loops.

Jamal Boudhaouia-Qwest said that another concern is what triggers would have to be put in place for LFACs and IMA.

Bonnie Johnson-Integra said that Integra is only proposing that HDSL2 loops be dropped to manual handling not all loops. She said that they would identify for Qwest that this is HDLS2. She said they are not asking Qwest to make the decision on their own. She said that they will indicate in Remarks and should not require more work on the Qwest side.

Jamal Boudhaouia-Qwest said that the manual process will cause issues down the line due to human error etc. He said that this process would impact all CLECs and not just Integra. (1/30/09 Comments to Minutes received from Integra) Qwest has not thought about a manual process. Qwest hasn’t discussed what changes in systems would be required.

Liz Balvin-Covad asked for clarification on the issue. (1/30/09 Comments to Minutes received from Integra) You (Integra) have the right to order this type of loop?

Bonnie Johnson-Integra said that (1/30/09 Comments to Minutes received from Integra) Qwest is provisioning and repairing to a voice grade level.

(1/30/09 Comments to Minutes received from Integra) Liz Balvin-Covad said because there is no USOC?

Jamal Boudhaouia-Qwest said it is provisioned as a 2 wire loaded loop. (1/30/09 Comments to Minutes received from Integra) The product developed doesn’t provision HDSL. The NCI/SECNCI codes were used for information only.

Bonnie Johnson-Integra said (1/30/09 Comments to Minutes received from Integra) Qwest should install based on the NC/NCI codes.

Jamal Boudhaouia-Qwest said that we have never offered the product to HDSL parameters. He said that Integra wants a process to ensure HDLS2 Unbundled loops are provisioned correctly.

Liz Balvin-Covad asked why the NC/NCI codes aren’t driving this.

Jamal Boudhaouia-Qwest said that the NC/NCI codes never drove this and we want to assign a USOC and drive to all downstream. He said that Qwest wants a robust process to make sure we have codes and logic in place.

Bonnie Johnson-Integra said (1/30/09 Comments to Minutes received from Integra) based on the Industry Standards for the NC/SECNCI they should be HDSL2 capable. Bonnie said that Integra did not feel they should have to submit a CR but that is what Qwest told us to do so here we are.

Liz Balvin-Covad asked why Qwest could not support a manual process. (1/30/09 Comments to Minutes received from Integra). Liz stated she was surprised, shocked to hear that Qwest is not using the NCI/SECNCI codes. This is industry standard. Covad relies heavily on xDSL Loops. I am just shocked. I am not saying you are lying, Jamal, I am just shocked.

Bonnie Johnson – Integra indicated that this is our position as well.

Liz Balvin – Covad stated this appears to be a defect in the downstream systems.

Jamal Boudhaouia – Qwest stated Qwest is trying to implement a robust process. We are where we are.

Liz Balvin – Covad requested manual support.

Jamal Boudhaouia-Qwest said that we don’t believe manual handling is the right way to do this and that cooperative testing is critical to the process.

Doug Denney-Integra asked why the joint testing is critical to the process. (1/30/09 Comments to Minutes received from Integra) In past calls Qwest indicated that it doesn’t test for themselves.)

Jamal Boudhaoia-Qwest said each equipment manufacturer has specific standards. He said that we have proposed critical joint testing for the complete provisioning and acceptance. He said that we test remotely without a technician and Qwest can’t do this on their own to insure we have delivered a quality loop. Bonnie Johnson-Integra said they will take this back internally and that they wanted to make sure they were on the same page. Kim Isaacs-Integra said that currently when you have a repair situation, all Qwest will do is test to analog VG. She said that ticket will say maintain to the appropriate level. (1/30/09 Comments to Minutes received from Integra) Kim asked why Qwest could not implement the repair process. Jamal Boudhaouia-Qwest said that the repair scenario is different than provisioning because it is not driven by input/output. Dan Wiger-Integra asked what a cooperative test would look like (1/30/09 Comments to Minutes received from Integra) on the installation process what does Qwest do for itself and what is expected. The testing parameters are still an open issue. He asked if Qwest is suggesting some type of test if , for example, our equipment is hooked up and the circuit won’t pass, would they be asked to do something or will Qwest initiate a process and fix the problem. Qwest implied that coop testing is needed on repairs. Jamal Boudhaouia-Qwest said (1/30/09 Comments to Minutes received from Integra) testing parameter would apply to provisioning and repair and that we would have to agree on the parameters. Dan Wiger-Integra said that they would know as the customer to repair back to the HDSL. He said that cooperative testing for repair would be a challenge. He asked if it was open/out would Qwest fix to the standard. Jamal Boudhaouia-Qwest said that the loop is hooked up to the Mux and HDSL has different parameters different than Nortel, for example. He said that we would fix it so that it is easier for you to interject a signal. Dan Wiger-Integra said (1/30/09 Comments to Minutes received from Integra) Qwest can fix metallic trouble but the challenges would be more on HDSL. Basic faults are easier to diagnose but that Multi band Mux remote capabilities would be a problem. We would ask Qwest to repair to parameters. Jamal Boudhaouia-Qwest said that we will agree to the concept of the proprietary process, the test parameters depend on what they want to see and on your testing capabilities. He said that Qwest will negotiate and agree on parameters. Dan Wiger-Integra asked is (1/30/09 Comments to Minutes received from Integra) Qwest positioning that it does not have the resources, trained or personnel in the CO to test with the Field and the CLEC will the CO resource. Jamal Boudhaouia-Qwest said that we would not be in parity with retail. (1/30/09 Comments to Minutes received from Integra) If CLEC can not complete co-op testing we need to re-analyze the CR. He said that it is much more than training and resources but do they have the equipment to do the testing. Dan Wiger-Integra asked if the pair was not working, would Qwest (1/30/09 Comments to Minutes received from Integra) Retail would test through the vendor equipment and do further testing on the frame to the technician in the field – Qwest in Wholesale – CLEC CO Test. Jamal Boudhaouia-Qwest said that HDSL parameters don’t have the capability nor have the technician in the CO to test to HDSL parameters. Dan Wiger-Integra said (1/30/09 Comments to Minutes received from Integra) stated that Qwest retail would seek another pair and that they would have to take this back. Doug Denney-Integra said that said that Integra wanted to get the manual process going so that they could work on how to handle testing going forward. Jamal Boudhaouia-Qwest said that Integra’s CR requested Design, Provision, Test and Repair Unbundled Loops to the requirements requested by the CLEC. He said that with this new process, Qwest expects provisioning will be better than before for HDSL requirements. He said that the original CR calls for a test process. Doug Denney-Integra (1/30/09 Comments to Minutes received from Integra) said while we would all like 100% perfection there is the opportunity for and improvement along the way. He asked why we want to delay the USOC and manual process because of the testing issue when by using the USOC we could get to 80% improvement today. Jamal Boudhaouia-Qwest said (1/30/09 Comments to Minutes received from Integra) to propose a new process if this will not work. He did not understand the objections to cooperative testing. He said that everyone needs to be comfortable with the testing and we want to meet the CLECs needs so that we don’t have issues going forward. He said that he would be open to another discussion. Bonnie Johnson-Integra said that when a CR requires system work in the past a workaround has been implemented. She said that Integra believes that Qwest can assign a loop without cooperative testing as it does for itself. (1/30/09 Comments to Minutes received from Integra) Jamal Boudhaouia-Qwest said that Qwest Retail does not use a manual process. (1/30/09 Comments to Minutes received from Integra) Bonnie Johnson-Integra said she was not stating that Qwest does this using a manual process and that Qwest retail could have a USOC they use. Dan Wiger-Integra said that Qwest has identified 3 steps in the process from this discussion: 1. Implement a new process/manual process, 2. implementing the USOC with cooperative testing will provide a quality loop and 3.final details on testing and how it will work. Bonnie Johnson-Integra said that it appears that Qwest is unwilling to move forward without implementing the USOC and won’t do one without the other. Jamal Boudhaouia-Qwest said that Qwest is not unwilling to discuss a manual process and Integra’s CR is requesting a testing process. Bob Mohr-Qwest said that Qwest wants assurance that with cooperative testing, we meet the HDSL test standard. Mark Coyne-Qwest summarized that based on Qwest’s response we will go back and look at the manual process, move forward with implementing the USOC and work together on joint testing. Mark Nickell-Qwest asked when Integra would respond to the question on joint testing. Bonnie Johnson-Integra said that they would review internally and provide a timeframe for a response to the CMP CR mailbox.

12/17/08 Product/Process CMP Meeting Bob Mohr-Qwest said that we wanted to provide an update from the last call. He said that we have held meetings with our sub teams to address the support of the (12/30/08 - Comments to minutes received from Integra) HDSL USOC and provisioning guidelines. The team has completed the analysis and determined that LFACs will look for a HDSL qualified Facility when the new USOC is present. He said that the team will meet on January 8th to work through the implementation steps and establish timelines associated with the implementation of the USOC. The team will also address non loaded BRI and ADSL loops. He said the 2nd sub team is working on the testing criteria and several outstanding issues from last month’s CMP meeting were discussed. He said that the implementation plan depends on the CLECs testing to 196 KHz and is critical to the implementation team. Jamal Boudhaouia-Qwest said that conditioning on the bridge tap and load coil will be performed (12/30/08 - Comments to minutes received from Integra) when we detect excessive bridge tap and have as we do today and that we will get authorization to remove it. Kim Isaacs-Integra asked if it would be done on the near and far end on the bridge tap and interference bridge tap too. Jamal Boudhaouia-Qwest said that far and near is part of the CSA guidelines and is very clear. He said that we will consider from a process perspective the automatic authorization to remove the bridge tap to make it compatible. Kim Isaacs-Integra said that they can populate the SCA field on the 1st order to approve authorization. Jamal Boudhaouia-Qwest said that we assume authorization because of ease and efficiency. He said you can choose to follow the same process. Kim Isaacs-Integra said that it should be based on if the field is populated and that the existing process says that we communicate to Qwest whether we approve the condition. Jamal Boudhaouia-Qwest said that he could go either way. He provided examples of how Qwest performs testing. (12/30/08 Comments to minutes received from Integra) Kim Isaacs – Integra indicated that Integra would prefer to use the existing process to approve conditioning. Jamal Boudhaouia-Qwest provided examples of how Qwest performs testing. DS1 service (12/30/08 Comments to minutes received from Integra) using HDSL2 – Qwest owns both ends, MUX on CO end of loop to customer prem. The Qwest HDSL2 goes through the CSA guidelines and Qwest will do remote testing from the center. HDSL is not a complete standard more focused to loop make up but each equipment manufacturer has specific standards. BRI – Testing is done remotely. UBL – Test is done on frame on most loops and the technicians are equipped with that ability. HDSL – CSA guidelines are used and hook up to the (12/30/08 Comments to minutes received from Integra) HDSL equipment and do remote. The HDSL is how loop should be done and have different parameters on how they test depending upon the manufacturer’s specifications. It is different for Lucent or any other manufacturer. We do the testing remotely and the tester reads the performance. Jamal asked that the CLECs test remotely or coordinate with the Qwest tester to cooperatively test with Qwest. He said that we don’t know how you test to 196 KHz and it depends on your Mux. Dan – Integra said that Qwest has various vendor technicians and has various test standards for HDSL. He said that if they are expected to do (12/30/08 Comments to minutes received from Integra) continuity testing how do they logistically accomplish this with HDSL and what is the next step. He said that Qwest can have the CO tech put the test devise on the loop asked why Qwest is not able to do this on HDSL. Jamal Boudhaouia-Qwest said that we don’t do 196 KHz on our own and that we do performance but they are driven by the vendor equipment. Our Technician is not equipped and the tools are very expensive to do 196 KHz. He said the equipment itself has certain parameters between the NIU or the technician would have a laptop to do remotely. Dan-Integra asked if the CLEC orders (12/30/08 Comments to minutes received from Integra) HDSL it is the industry standard to run multi-band test and Qwest does not run an insertion loss for high frequency. He asked how Qwest would know if the HDSL is a qualified loop. Jamal Boudhaouia-Qwest said that is the question associated to the CR. He said that today Qwest doesn’t perform or guarantee tests. Dan-Integra asked Qwest to confirm that Qwest itself does not perform test. Jamal Boudhaouia-Qwest said that on raw copper loop the tech on the other end doesn’t interject test parameters (12/30/08 Comments to minutes received from Integra) Qwest connects the loop to the HDSL equipment and tests remotely. Dan-Integra asked if Qwest would perform the test for HDSL signaling for themselves if the circuit doesn’t work. Jamal Boudhaouia-Qwest said no and that typically (12/30/08 Comments to minutes received from Integra) Qwest looks for overlooked bridge tap or load coil and removes these if found – the practice of testing the loop don’t do is driven by CO Mux. Qwest tests remotely. Dan-Integra said that with the Mux you don’t have the technician. He said that you order the facility and hook up to the vendor equipment and it doesn’t work. He said that a loop issue is found. He asked how they could cooperatively test by sending the tone for every ADSL and hand off a qualified loop. (12/30/08 Comments to minutes received from Integra) Dan stated it sounds as though Qwest is just using vendor testing. Jamal Boudhaouia-Qwest said that we don’t have the equipment or technicians trained for HDSL signaling. He said Qwest does not have the capability to test raw loops. He said that we will check to see if the bridge tap is interfering with it. He said that Qwest does not do HDLS test in the CO because we are not equipped to do that and the equipment is very expensive. (12/30/08 Comments to minutes received from Integra) When we hook to the HDSL mux we test remotely - it works or doesn't work - we don't have the ability to test the raw loop, we look for open shorts, bridge tap, or Load Coils that we missed. Most of the time we don't test using test equipment in the CO. Qwest is not equipped to do the testing in every central office. Dan-Integra asked if Qwest’s position was that when the CLEC orders an HDSL Loop Qwest wants the CLEC to be part of the Loop Qual testing. Jamal Boudhaouia-Qwest said (12/30/08 Comments to minutes received from Integra) LFAC will do the Loop Qualification. We don’t know the capability of the CLEC. He said that we are asking for cooperative testing and what other parameters beside 196 KHz to test to because 196 KHz may not interject the signal. Dan-Integra said that they would review the recommendation internally. He asked if they agree to cooperative testing would the standard be jointly defined. Jamal Boudhaouia-Qwest said (12/30/08 Comments to minutes received from Integra) yes we are willing to jointly define compliance standards that some CLECs can’t test remotely with 196 KHz. Doug Denney-Integra (12/30/08 Comments to minutes received from Integra) said that Qwest indicated some COs are equipped with test with this 196 KHz testing standard and asked if Qwest’s position is the same, regarding testing of the loop, even in offices where the capability to test the loop exists. Jamal Boudhaouia-Qwest said that is correct from a process perspective. He said that in these offices the process we are introducing with this CR would be across the board. Bonnie Johnson-Integra asked when Qwest includes new technology or service is the criteria included in the binder group. Jamal Boudhaouia-Qwest assuming that Qwest knows the NC/NCI codes in the binder group are running each pair is assigned the correct codes in the cable. He said that he tried to make manage spectrum management process – DS1 on it if the separate CO based HDSL and ADSL interfere with the CO based – interference will appear after a certain amount of time and that is how the spectrum if we know the codes in binder group. Kim Isaacs-Integra asked how Qwest gets the NC/NCI information to manage spectrum etc. Jamal Boudhaouia-Qwest said that it is driven by the service order and that is how they get assigned to the cable. Kim Isaacs-Integra said that (12/30/08 Comments to minutes received from Integra) service modifier LFXU is for 2 Wire Analog and Non Loaded Loops and they all carry the same service modifier code and asked how Qwest could manage spectrum correctly/interference on the loop. Jamal Boudhaouia-Qwest said that (12/30/08 Comments to minutes received from Integra) historically the NC/NCI codes were not loaded. He said that when we have a UBL the NC/NCI codes need to be correct on the loop and that is what we are trying to do going forward in order to manage spectrum.. Kim Isaacs-Integra asked how Qwest determines the NC/NCI codes on LXFU. Jamal Boudhaouia-Qwest said that if we have LXFU would be able to manage with NC/NCI codes and we are looking at the total technical parameters with the NCI/SECNCI going forward. Kim Isaacs-Integra said when assigning HDSL, LFACs will find the loop upfront and asked if the NC codes will be tied to the circuit so when you manage spectrum you aren’t going to have interference. Jamal Boudhaouia-Qwest said that when the USOC is input, IMA will drive the correct NCI codes. Bonnie Johnson-Integra said that the reason they are asking is because they have had an ongoing issue for 2 years. She said that Qwest network personnel told them that the repair commit time for LXFU 2-4 wire Non-Loaded Loop is 24 hours when the SIG indicates it is 4 hours. She said that Qwest said they determine repair commit time by the service code modifier and not the NC/NCI code and that they can’t differentiate between 2 & 4 wire analog and a 2/4 Wire Non-Loaded Loop. She said that they are concerned with the challenge in repair when there are 600 pairs on the binder group and is Qwest looking at 600 orders. She said that going forward there will be a different USOC but will still have the service code modifier. She said that we may need to take a closer look at this with HDSL & being included and LXFU modifier. Jamal Boudhaouia-Qwest said that we are not looking at 600 pairs. He said that there are 25 pair cables and if the services apart in each binder group there won’t be an interference issue. He said that he was not aware of the repair time and will take as an action item. He said that what he envisions going forward is that the new USOC will drive NC/NCI codes and HDSL will be assigned. Bonnie Johnson-Integra asked if we could do research on how they can differentiate between a VG loop and an HDSL loop. Jamal Boudhaouia-Qwest said that we can research.

11/19/08 Product/Process CMP Meeting

Bob Mohr-Qwest said that we had questions from the adhoc meeting held 11/12 and would like to provide an update. Bob said that the 1st question is associated with the embedded base of circuits. He said the question was will Qwest update the circuit with the USOC as needed when the CLEC opens repair tickets and indicates this is a 2 wire non-loaded loop with HDSL NC/NCI codes. Bob said that if the circuit is identified and qualifies as HDSL, Qwest will change to the new USOC. He said that if the circuit does not meet the guidelines we will ask that it be moved to a service that qualifies. Bonnie Johnson-Integra said that when we are talking about repair we are talking about 2 buckets. She said that the 1st bucket is when a circuit is working and Qwest does a network modification resulting in the circuit not working. She said that there should never be a case when the circuit worked and now doesn’t qualify because of the network modification (11/26/08 Comments to minutes received from Integra) because per Jamal on the ad hoc call, an address qualifies or it does not. Jamal Boudhaouia-Qwest said that is correct. (11/26/08 Comments to minutes received from Integra) we will look at this situation on an individual case basis. Bonnie Johnson-Integra said that going forward they should not have to open up a ticket in this situation (11/26/08 Comments to minutes received from Integra) because Qwest will not install the circuit if it does not qualify. Jamal Boudhaouia-Qwest there should be no repair issue and that the circuit should work and continue to work going forward. Bonnie Johnson-Integra said that if the circuit does not qualify and you request that the circuit be moved to another facility should only apply to circuits prior to this process. She said that the circuits Bob is referring to are those that don’t meet the guidelines. Bob Mohr-Qwest said he was referring to the embedded base. Bonnie Johnson-Integra asked if these would be circuits that never worked. Jamal Boudhaouia-Qwest said that if there have been 4 or 5 repair tickets on a circuit there may be a problem. He said that if the circuit has always worked properly, it should work going forward. Julia Carter-Redman-McLeodUSA said that their concern is that they have a circuit that has worked properly for years (11/26/08 Comments to minutes received from Integra) a change occurs in Qwest’s network and now the circuit doesn’t work. Qwest’s response is that the circuit meets the standar for test per NCI code and CLEC now has to re-order because it has the wrong NCI codes. Jamal Boudhaouia-Qwest said that the issue is to provide correct NCI codes. Julia Redman-Carter-McLeodUSA said that the (11/26/08 Comments to minutes received from Integra) circuit has been working for years and the codes in the beginning worked and now there is a repair issue. Qwest is now claiming it doesn’t work because the NCI codes are wrong.and we have to reorder with the now correct NCI codes. Jamal Boudhaouia-Qwest said that we are talking about 2 different issues. Mark Coyne-Qwest said that McLeodUSA’s issue doesn’t fall into the description of the CR and that we have captured their concern. Bonnie Johnson-Integra said that their CR is asking for Qwest to install and provision circuits based on the NCI/SECNCI codes. She said that Qwest was only installing to voice and their CR addresses ADSL. Jamal Boudhaouia-Qwest said that we are trying to make sure that the NC/NCI codes expected on the request are to provision UBL. He said that our expectation is that the NCI codes in the PCAT and ICA are correct going forward. Julia Redman-Carter-McLeodUSA confirmed that this (11/26/08 Comments to minutes received from Integra) addresses only installation and provisioning on a going forward basis. Jamal Boudhaouia-Qwest said yes. Julia Redman-Carter-McLeodUSA said that they don’t want (11/26/08 Comments to minutes received from Integra) to have to reorder something that has been working and now stops working. PAETEC want the service repaired based on the standard for the service we originally ordered and received.

Kim Isaacs-Integra said that the NCI & SECNCI codes used for the service should work to those standards. She said that if the NCI code is different than what you wanted, the circuit won’t work per the standard. Julia Redman-Carter-McLeodUSA said that she still has a problem with a circuit working for years (11/26/08 Comments to minutes received from Integra) though it may have the ‘wrong’ codes – and now Qwest won’t repair and PAETEC may need to re-order again because of Qwest changes. Kim Isaacs-Integra said if you have an embedded circuit with a 2 wire non loaded loop NCI and it is working as ASDL and then it stops working, Qwest will repair to NCI code standards based on ADSL. Jamal Boudhaouia-Qwest said that we could talk further about this is an adhoc meeting. Jamal said that we test and manage to current NCI codes. Bonnie Johnson-Integra said if the current codes are HDSL capable and the circuit was working and then it doesn’t, Qwest is going to have to remove the bridge taps. Mark Coyne-Qwest said that these were good discussion points for an adhoc meeting. Bonnie Johnson-Integra asked why these discussions have to take place outside of a CMP Meeting. (11/26/08 Comments to minutes received from Integra) Bonnie said we have the participants on the call now and Qwest seems to always be trying to get things outside of CMP. Mark Coyne-Qwest said that he was not sure we had all the right SMEs on the call. (11/26/08 Comments to minutes received from Integra) Bonnie Johnson-Integra asked Jamal and Bob it that was true. Jamal Boudhaouia-Qwest said that McLeod’s issue is outside of the CR and said that he was not prepared to discuss this concern. Julia Redman-Carter-McLeodUSA said that she was not able to join the adhoc meeting. Bonnie Johnson-Integra confirmed that Qwest will change the circuit if it qualifies and if a circuit has worked for a year it should still work. Jamal Boudhaouia-Qwest agreed that circuit should qualify and that if the circuit does not work, Qwest will take a look at it and place it on a facility that works. Julia Redman-Carter-McLeod said that they should not have to make changes to make it work. Bonnie Johnson-Integra asked if the confusion is that in the past McLeodUSA was using NCI codes not associated with HDSL and that is the difference from the CR. Julia Redman-Carter-McLeodUSA said (11/26/08 Comments to minutes received from Integra) that per the NCI/SECNCI codes the testing standard applied should be to HDSL codes per PCAT. She asked that if the circuit was working previous years and meets the designated standard per the NCI code but not the ADSL standard so that the circuit is working as it has been for the previous years, then does CLEC have to re-order with the now correct codes. Jamal Boudhaouia-Qwest said that we are not asking the CLEC to re-order but if the circuit never worked we are asking that it be moved to a different service. He said that if the circuit qualifies and has the correct codes Qwest will apply the USOC. Laurie Roberson-Integra said that if the circuit has been working for a year and quits and it qualifies, Qwest will restore it. She said if there is a Qwest network change and it doesn’t qualify per the rules Qwest will not restore. Jamal Boudhaouia-Qwest said that based on tests and if the circuit worked intermittently and doesn’t meet standards, Qwest will ask the CLEC to change it. Laurie Roberson-Integra asked if the circuit worked before and now it doesn’t will Qwest try and fix the issue. Jamal Boudhaouia-Qwest said that he wanted to emphasize the standard test of 96HZ and if the circuit falls outside of the standard, Qwest will ask the CLEC to change it. Bonnie Johnson-Integra said that it is a case-by-case basis and that McLeodUSA’s issue is a different issue and not related to this CR. Jamal Boudhaouia-Integra agreed and said it is a totally different spectrum issue (HDSL with ADSL) and that the remote D-Slam has no affect on ADSL. Kim Isaacs-Integra asked how Qwest will address bridge tap removal (near and far end) during the design and provisioning phase and what will Qwest do if it interferes with the service. Jamal Boudhaouia-Qwest said that would fall under the conditioning process and said he was not familiar with the current practice. Kim Isaacs-Integra asked if Qwest could provide a response. Mark Coyne-Qwest said that we will provide a response in the meeting minutes. Jamal Boudhaouia-Qwest addressed the question regarding what additional work and HDSL2 testing requirements need to be added to this process. He said that the technicians need to be equipped with HDSL tier testing and be able to read and understand DB levels. They will need to check for load coils going forward and test to the correct range. Bonnie Johnson-Integra asked if this additional work (11/26/08 Comments to minutes received from Integra) because the circuit will now be designed is related to Qwest wanting to increase from 3 to 5 day intervals. Jamal Boudhaouia-Qwest said that we have to take the necessary steps for the centers and LFACs to make sure the facility is qualified. He said that we have 2 extra steps - the technician needs to be equipped and that we have the insertion for the CSA guidelines. Bonnie Johnson-Integra asked when Qwest adds the USOC could she assume that it goes through LFACs to find the facility or does it fall out for manual handling. She said that she knew some will flow through. Jamal Boudhaouia-Qwest said that they would go through LFACs. Kim Isaacs-Integra asked if they would be auto assigned. Jamal Boudhaouia-Qwest said that he did not have the details but that the center will have to look for the correct facility. He said that extra time is needed in trying to mirror the design process and it is not an automatic process. He said all DS1s go through the design process. Jamal Boudhaouia-Qwest addressed whether coordinated/cooperative testing will be required, and if so, does that mean basic install will not be available for these loops. He said that cooperative testing will have basic install testing with coordinated cooperative testing or have CLEC requested timeframes. Bonnie Johnson-Integra asked Qwest to confirm that plain basic installation was not available and has to be basic with cooperative test. Jamal Boudhaouia-Qwest said that was correct. Kim Isaacs-Integra said that on a basic install with DS1 or analog, Qwest is doing some test with a verbal response and asked if there was anything additional that needs to be done with HDSL. Bob Mohr-Qwest asked if they were referring to a finished DS1. Kim Isaacs-Integra said that with any loop order they can request basic install and Qwest will test to standard with a run test and asked what additional activity they need to do with cooperative testing. Bob Mohr-Qwest said that performance testing may be required and was not certain if there was a different test. He said that with the basic option, test results are not provided. Jamal Boudhaouia-Qwest said that we need to look at DS1 capable loops. He said that we will look at DS1 testing requirements to see what the CLEC has to do. Jamal said that he envisioned that the testing could be done remotely by the Qwest technician and CLEC with the same test results. Kim Isaacs-Integra (11/26/08 Comments to minutes received from Integra) asked if Qwest wanted us to send the 196 kHz down the loop and it will loop back. Bonnie Johnson-Integra said that with cooperative test you need the CLEC for something vs. just testing to the parameters and calling us. Bonnie said that they may have additional questions. Mark Coyne-Qwest said that if there are any other questions to send to cmpcr@qwest.com.

November 12, 2008 adhoc meeting Attendees: Bob Mohr–Qwest, Jamal Boudhaouia-Qwest, Doug Allen-AT&T, Kim Isaacs-Integra, Bonnie Johnson-Integra, Loriann Burke-XO Communications, Joyce Bilow–Paetec, Laurie Roberson-Integra, Doug Denney-Integra, Jo Wees-Qwest, Susan Lorence-Qwest

Susan Lorence-Qwest stated the purpose of the call is to discuss CR PC082808-01IG, Design, Provision, Test and Repair Unbundled Loops to the requirements requested by CLEC, including NCI/SECNCI Code Industry Standards, and for Qwest SMEs to provide a high level concept of the proposed solution. Bob Mohr-Qwest relayed that since the last ad hoc call, there have been several meetings to evaluate what would be required to provision specific interfaces for the Non Loaded loops to industry guidelines. The key is for downstream groups to be able to identify the unique interface. Bob relayed we would like to share the concept of a 2 gate approach to qualifying and provisioning the HDSL loop interface. Bob Mohr-Qwest said the team had researched how the NC/NCI codes are processed today for the specific interfaces and found that the majority of downstream systems rely on a unique USOC along with NC/NCI combination. Qwest found an existing USOC (U2UXX) that is defined today as a HDSL Unbundled Loop. The USOC is not used for any other application and LFACS can assign a Qual Code to validate availability of a facility that meets the HDSL guidelines. Bob relayed that if a facility exists then LFACS assigns facility and the order has made it through gate 1 otherwise the order is rejected. Jamal Boudhaouia - Qwest relayed that the determination in Gate 1 is if there is any capable facility available. (11/21/08 - Comments to minutes received from Integra) HDSL CSA Guidelines T1.418 recommendation would be used to determine capability. He relayed he wanted to be sure everyone was clear on the guidelines.

Bonnie Johnson-Integra asked Qwest to confirm that with the USOC, Qwest would be able to identify in LFACS whether or not there was a facility and that this was the current process that any order takes through Gate 1 11/21/08 – Comments to minutes received from Integra) and not a new process. Bonnie raised the question on what would occur if there was no facility. She indicated she disagreed that if there was no facility, Qwest would reject rather than treat as a delayed order.

Bob Mohr-Qwest said (11/21/08 – Comments to minutes received from Integra) rejected might be the wrong word and he said he would take that issue back to his SME team.

Bonnie Johnson-Integra (11/21/08 – Comments to minutes received from Integra) said that Qwest was focused on the HDSL and said the change was broader than HDSL and questioned whether Qwest was looking for other unique USOCs.

Bob Mohr-Qwest (11/21/08 Comments to minutes received from Integra) recommendation with respect to digital products other than HDSL2 to order the corresponding digital compatible or capable loops. at the same price as non-loaded loops but there was not that latitude with HDSL.

Bonnie Johnson-Integra asked if new USOCs will also be obtained for the other Non-Loaded Loop Interfaces such as ISDN BRI and xDSL-I.

Qwest relayed the concept for other interfaces such as BRI ISDN, and xdsl-I should be ordered using the existing NC code for that UBL (xDSL-I and BRI ISDN Capable UBLproducts). This will ensure that these services are provisioned using industry guidelines and testing. ADSL interfaces should be ordered using the NC code of LXR- and this will drive the specific ADSL tests and parameters.

Kim Isaac-Integra (11/21/08 Comments to minutes received from Integra) said that it appears Qwest was stepping away from the ADSL loop through grandfathering the product. This ADSL loop may disappear in the next round of ICAs.

Bob Mohr–Qwest said there is no plan to grandfather ISDN BRI Capable and xDSL-I Capable Loop, but that Qwest was looking into the issue related to grandfathering of the product ADSL (11/21/08 Comments to minutes received from Integra) and possibly un-grandparenting the ADSL capable loop product.

Bonnie Johnson-Integra asked about the timeframe for that and Bob Mohr-Qwest relayed that he did not have that information at this point.

Bob Mohr-Qwest said at this point in the process, Gate 1 had been passed and that Gate 2 involved the actual provisioning and testing of the order. Bob relayed that with the additional testing and coordination, a change to the interval from 3 to 5 days is required. There was also the need to explore whether a cooperative test was required and whether that was operationally feasible. Bob relayed that the call was needed to explore those two areas: the interval change from 3 to 5 days and cooperative testing.

There was discussion on why there was a need for the increased interval. (11/21/08 Comments to minutes received from Integra) Jamal Boudhaouia - Qwest relayed that the 2 wire non loaded loop is a 3 day interval because it is not designed. The increased interval was due to the additional testing time that was required to test the 196khz frequency And because the circuit would now be a designed service and different test sets and technicians trained for this testing are needed on each end of the circuit.

Bonnie Johnson-Integra questioned what the expectation was around cooperative testing vs. a coordinated testing.

Discussion occurred the around the types of testing, various cost issues and how often these type of circuits would be ordered vs. the required test equipment.

(11/21/08 Comments to minutes received from Integra) Bonnie Johnson – Integra asked if Qwest was going to require coordinated/cooperative testing.

(11/21/08 Comments to minutes received from Integra) Bob Mohr – Qwest said that from a product perspective Qwest needs to determine the cost vs. the return.

(11/21/08 Comments to minutes received from Integra) Bonnie Johnson – Integra indicated she would take this back internally. She asked Qwest if they are currently doing any testing for 2-wire loops.

Jamal Boudhaouia - Qwest relayed that today there is no requirement to perform (11/21/08 Comments to minutes received from Integra) HDSL tests. He said Qwest tests for load coils only.

Jamal Boudhaouia – Qwest (11/21/08 Comments to minutes received from Integra) said the qual code for the 1st gate will be the CSA Guidelines. The specific guidelines indicate that if there are no facilities, the order would be rejected.

(11/21/08 Comments to minutes received from Integra) Susan Lorence – Qwest indicated that there was an earlier question regarding the difference between rejected and delayed orders.

(11/21/08 Comments to minutes received from Integra) Jamal Boudhaouia – Qwest said for HDSL, there is no recommendation on a standard. ANSI T1.418 is the standard that references HDSL2 on the other hand if certain guidelines are not met, the address does not qualify which would be a reject vs. following the delayed order process. Jamal referenced that the CSA guidelines must be met.

(11/21/08 Comments to minutes received from Integra) Kim Isaacs - Integra questioned whether qualifications were based on gauge or distance only because we can request conditioning to remove load coils and interfering bridge tap

Jamal Boudhaouia - Qwest relayed it was based on gauge and distance and that it was a mathematical calculation.

Jamal Boudhaouia–Qwest relayed he would provide the specific guidelines. NOTE: The T1E1 Technical Report #28 is the guideline that Jamal Boudhaouia cited, specifically Section 3.1 depicts the CSA Guidelines that are Industry Standard.

Bonnie Johnson-Integra relayed that if the parameters are considered during loop qualification, the order should not get rejected.

Jamal Boudhaouia–Qwest indicated that if a customer uses the Raw Loop data tool, that chances are good that if it qualifies, the facility will still be available however there is no guarantee that some other provider did not order those facilities. The Raw Loop data tool does not reserve facilities.

Bonnie Johnson-Integra stated again there is a difference between an address that does not qualify and (11/21/08 Comments to minutes received from Integra) address that does qualify but no facilities which is the difference between a reject and a delayed order.

Jamal Boudhaouia–Qwest relayed (11/21/08 Comments to minutes received from Integra) that is a good point and Qwest would take that into consideration.

Bob Mohr-Qwest said he would take an action item: what to do with ADSL.

Bonnie Johnson - Integra questioned whether Qwest was looking for concurrence before the CR moves forward on the two areas of extending the interval from 3 to 5 days and the question of testing.

Bob Mohr-Qwest said the idea was to share the concept while Qwest continues to investigate the testing and other issues. He questioned whether Qwest was on track and moving in the right direction.

Bonnie Johnson-Integra (11/21/08 Comments to minutes received from Integra) said that provisioning and repairing the loops to the NC/NCI code is where we need to be. We will not discuss whether we believe Qwest should have been doing this all along under our ICA on this call. Integra cannot dictate how to get to the solution but knows where we need to end up and wants to get there.

Jamal Boudhaouia–Qwest said Qwest wants to get there as well with a process that will work.

Susan Lorence-Qwest confirmed that Qwest would provide the Carrier Service Area (CSA) guidelines and asked for questions. Qwest relayed information had been provided on the direction and status of the CR and Qwest has additional items to think about.

10/15/08 Prod/Proc CMP Meeting Mark Coyne-Qwest stated that Bob Mohr-Qwest will provide an update. Bob stated that the team reviewed the change and stated that no IMA (10/22/08 Comments to minutes received from Integra - in bold) or system changes are necessary, so this CR will cross over to Product/Process. Bob stated that they looked at one change and solution and the concept failed. Bob stated that Qwest has other solutions but those were more complex and the team is evaluating the changes that need to be made. Bob stated that we would like to schedule an adhoc meeting in about two weeks to review the status and potential new solutions. Bonnie Johnson-Integra asked if the adhoc meeting will be to update the CLECs or to present a solution for the CR. Bob Mohr – Qwest stated that is what Qwest hopes but he did not want to set any misconceptions but the existing solutions are more complex. Bob stated that in the next 2 weeks our objective is to research, test, and look at financials. Mark Coyne – Qwest thanked Bob for the update.

9/17/08 Systems CMP Meeting Susan Lorence-Qwest said that this request was submitted as a Product/Process CR. This CR is in the Systems Package because an industry guideline CR has to be submitted as a system CR per the CMP Document. If determination is made that there are no system changes the CR will be crossed over to a Product/Process CR. Bonnie Johnson-Integra said (9/25/08 Comments to minutes from Integra in bold) she will not read the entire CR request but that there have been a number of discussions with Qwest on these types of circuits and there is a lot of background and history. At a high level, Qwest advised Integra that regardless of the NCI code on requests for 2w/4w non loaded loops, Qwest installs, provisions and repairs to a voice grade level. She said that they are asking Qwest to provision and repair circuits based on the industry standards for the NCI/SECNCI Code instead of just the NC code. Susan Lorence-Qwest said that we held a clarification meeting on September 9th. She said that Bonnie provided ANSI T1.418 as the Industry Guideline. Bonnie Johnson-Integra said that was provided as an example and may not cover all of them. Qwest has a lot of codes already referenced in the tech pubs. We talked in the clarification call about the industry guideline CR having to be submitted as a system CR. She said that if there if no system work, the CR would be crossed over to a Product/Process CR. She said that they have been trying to address this issue for quite some time and have a concern about any delay. She said that there have been so many people engaged up to the VP level and they would like Qwest to respond ASAP on how soon this can be done. Susan Lorence-Qwest said that the SME team is already looking at the CR and that we will have a response by the next CMP meeting. She said that we hope to provide a response on whether we are accepting the change and whether there is system work involved. She said that once we determine if there is no system work involved, the CR will be crossed over to Product/Process. Bonnie Johnson-Integra said that they don’t believe they should have had to issue this CR but Qwest recommended that they do. She said that there are industry guidelines that Qwest should be repairing and provisioning their circuits to. She said that they have been trying to get this resolved for over a year and they don’t want to wait month after month for a response and will not be very patient. She said that anything Qwest can do to expedite the process would be appreciated.


CenturyLink Response

March 13, 2009

For Review by CLEC Community at the March 18, 2009 CMP Product/Process Meeting

Bonnie Johnson Integra

Subject: Integra Change Request - CR #PC082808-1IGX

This CR is requesting to Design, Provision, Test and Repair Unbundled Loops to the Requirements requested by CLEC, including NCI/SECNCI Code Industry Standards.

Additional detail for this change request can be found at: http://www.qwest.com/wholesale/cmp/changerequest.html

Qwest Response:

The Unbundled Non Loaded Loop product was developed to interface with various applications contained in Technical Publication 77384. For Unbundled Loop LX-N Network Channel (NC) codes, the NCI codes are informational only, as stated in the above mentioned Technical Publication and do not affect transport designs or performance. The associated NC code requires that the service use non-loaded, metallic facilities free of faults (grounds, shorts, noise, or foreign voltage). The CLEC has responsibility to inspect the character of the facilities, e.g. gauge, length, etc and determine that the facility is appropriate for their specific application.

Because Qwest is under no obligation to provide the product in the manner requested by CLEC, and Qwest is only obligated to provide a Non Loaded Loop to the broader standards listed in Technical Publication 77384, this Change Request to Design, Provision, Test and Repair Unbundled Loops to the requirements of the NCI code required a business discussion regarding the benefit to providing Non Loaded Loops in this manner vs. the cost to do so. That is, because there is no obligation to provide Non-Loaded Loops in this manner, the decision to implement this CR becomes one of economics. Absent the CLEC community agreement to negotiate in good faith to perform cooperative testing, this request becomes economically not feasible for Qwest. Therefore, Qwest respectfully denies this request.

Sincerely

Qwest Corporation


Open Product/Process CR PC050409-1CM Detail

 
Title: Increased clarity in Qwest initiated proposed documentation changes, including avoiding overlapping notices and modifying notices if an overlapping change is unavoidable.
CR Number Current Status
Date
Area Impacted Products Impacted

PC050409-1CM Completed
7/15/2009
Originator: Johnson, Bonnie
Originator Company Name: Integra
Owner: Coyne, Mark
Director:
CR PM: Stecklein, Lynn

Description Of Change

Integra and its affiliates (“Integra”) and McLeod dba PAETEC (“McLeod”) request that, when Qwest initiates a proposed PCAT or Technical Publication change (both of which involve posting of redlined changes per CMP Document Section 2.5), Qwest allow the full CMP cycle to complete for that change before initiating additional proposed changes to the same PCAT or Technical Publication. In other words, the notices/timelines should not overlap. When Qwest initiates multiple, overlapping proposed changes to a single document (or any red lined document associated with a Qwest notice), it causes a situation in which CLECs are unable to consider the impact of that change based on all of changes Qwest is collectively proposing. This denies CLECs an opportunity to comment on changes in their entirety because, depending on the type of notice, CLECs may not be aware of a change that has already been made but is not reflected in a posted red lined document.

To illustrate, if a CLEC receives notices by category (e.g., product or process), Qwest could make a red lined change as a product notice and another overlapping change to the same PCAT as a process change. Considering that the same CLEC employee may not review both types of notices, an employee would not be aware that one red lined PCAT does not accurately reflect the PCAT as it will appear when the previous change goes in to effect. That could significantly impact how the CLEC may comment on, or react to, the change.

An example occurred with respect to the expedite PCAT. Qwest initiated a series of overlapping proposed PCAT changes that were so complicated that, on Nov. 18, 2005 in PROS.10.19.05.F.03380. ExpeditesEscalationsV30, Qwest had to provide the following timeline, in response to CLEC complaints of confusion: (See attached example)

Naturally, CLECs would like to avoid such confusing and overlapping Qwest changes and proceed in an orderly manner to review and respond to proposed changes. Qwest should not propose additional changes to the same PCAT in a manner that prevents CLECs from readily knowing the full impact and relationship of the changes.

Another example (also involving expedites): Qwest recently indicated it intended to make overlapping PCAT changes (relating to compliance with an Arizona Commission order in the Eschelon Arizona complaint case against Qwest, Docket No. T-03406A-06-0257) with respect to the expedite PCAT. Integra expressed concern in a Nov. 26, 2009 email to Qwest, in which Integra said: “Part of the problem that led to the AZ expedites case was due to Qwest using overlapping notices, causing confusion, and we had hoped that experience would have led to Qwest not issuing notices so close in time.” Qwest has not provided any assurance that it will not make overlapping changes going forward.

Qwest should not send multiple, overlapping notices regarding changes to the same PCAT or Technical Publication. With appropriate planning on Qwest’s part and attention to the CMP deadlines, any instance in which an overlapping change is needed would be rare. In such rare instances, if it is necessary to make additional changes to the same PCAT or Qwest Technical Publication before the previous changes have gone into effect, and a change will not be reflected in the red line, Qwest should communicate in the notice for the additional changes that there is a pending notice/change that is not reflected in the red line associated with the additional changes, and Qwest should provide the notice number and link to the proposed changes in the previous notification, as described in the enclosed proposed redline of Section 2.6 of the CMP Document.

Qwest will make mutually agreeable changes to the CMP Document to implement this CR (such as the proposed changes shown in the enclosed proposed redline of Section 2.6 of the CMP Document). The purpose of the changes will be to ensure that, absent an urgent or critical business need to do so, Qwest will not send notices that overlap, for a single PCAT or Technical Publication (or any document Qwest is red lining as a part of the associated notice of change). Qwest will allow the applicable CMP deadlines to complete before initiating additional proposed changes. In unusual circumstances, due to an urgent or critical business need, Qwest may issue overlapping notices but only if it follows the procedures outlined above (and in the attached proposed changes to the CMP Document) to ensure that CLECs are aware that there are other pending proposed changes to the same document.


Status History


Project Meetings

7/15/09 Product/Process CMP Meeting

Mark Coyne-Qwest said that this CR is proposing updates to Section 2.5 of the CMP Document to add increased clarity in Qwest-initiated proposed documentation changes, including avoiding overlapping notices and modifying notices if an overlapping change is unavoidable. Mark said that a vote will be conducted today.

Lynn Stecklein-Qwest said the redline is included in the distribution package. Quorum is 7 and has been achieved. In Section 2.1 of the CMP document it states that incorporating a change into the Change Management Process requires unanimous agreement.

A vote of ‘Yes’ will indicate a preference that Section 2.5 of the CMP Document be updated to include clarity in Qwest initiated proposed documentation changes, including avoiding overlapping notices and modifying notices if an overlapping change is unavoidable.

A vote of ‘No’ will indicate a preference that Section 2.5 of the CMP Document not be updated to include clarity in Qwest initiated proposed documentation changes, including avoiding overlapping notices and modifying notices if an overlapping change is unavoidable.

Lynn said Qwest has received 3 ‘Yes’ votes from Qwest, Verizon Business and Comcast via e-mail. One abstain vote was received from Action Communications, Inc. The meeting participants voted as follows: Integra – Yes, PAETEC – Yes, Covad – Yes, TDS Metrocom – Yes, Time Warner Telecom – Yes

The vote was granted with 8 ‘Yes’ votes, 0 ‘No’ votes and 1 ‘Abstain’ vote. A vote disposition notice will be sent and the change will be made to the CMP document.

6/20/09 Product/Process CMP Meeting

Mark Coyne-Qwest said that in the May meeting we had a discussion regarding Integra’s changes to Section 2.5. Mark said that Integra presented their redline changes and Qwest also submitted its proposed changes to that language. Mark said that Integra has reviewed the change and has made additional changes. Mark said that we are in the process of reviewing and hope to bring this to a close in July.

Bonnie Johnson-Integra said that the document on the calendar is the redline that she and Julia used after Qwest redlined their changes. Bonnie said they accepted those changes and what you see is language that is currently not in the CMP document. She said that when we reach consensus there will be a lot more changes than this. She said it easier to accept changes rather than work from the original CMP document.

5/20/09 Product/Process CMP Meeting

Bonnie Johnson-Integra said that this CR was submitted as a joint request by Integra and PAETEC. Bonnie said that it is an ongoing challenge for the CLECs when there are multiple notices issued for one PCAT. She said that one of the problems is that until a proposed change is effective and if another change goes out for the same PCAT; the redline doesn’t include the final result of the notice that is not yet effective. Bonnie said that this could impact the end result and how they view the subsequent changes of the other language being changed. They are proposing that Qwest avoid doing multiple overlapping changes unless it’s required, i.e. a regulatory change or to change a phone number. If for some reason Qwest needs to issue an overlapping notice, Qwest needs to identify there is another pending change to that document that has not yet posted and is not reflected in this redline.

Julia Redman-Carter PAETEC said that the process of having changes that aren’t yet effective is sometimes referred to as stacking. She said that if Qwest does stack they need to let the CLECs know what is being stacked. They need the full picture so that they can make an informed decision (5/28/09 Comments to minutes received from PAETEC in CAPS) AND NOT realize TILL LATER THAT there WERE other pieces they may not HAVE been aware of WHEN ORIGINALLY REVIEWED. Mark Coyne-Qwest said that Qwest can appreciate what the CLECs are saying in this CR. He said that it is a challenge for the documentation team that updates the PCATs when this occurs. Mark said that we do try to keep this to a minimum but based on business needs that come along it does happen. Mark questioned the sentence in the proposal where it states that this needs to happen on rare occasions and asked how the CLECs define rare.

Bonnie Johnson-Integra said some level 1 changes impact the way they do business and those occasions are rare and considered immediate, i.e. correcting a phone number or if you have a regulatory change. Bonnie said that it sounds like this may help Qwest as well.. It appears when Qwest reviews a tech pub or PCAT and makes a change other things are done that need clarity or clean up. She said that it appears that when Qwest identifies changes are needed, they issue level 1, 2, 3 etc. Bonnie said that something to consider is that unless those level 1’s or 2’s are critical business needs or something that impacts the way they do business with Qwest, is to issue those changes in one change rather than issuing separate levels for 1 PCAT. She said that their recommendation is, rather than doing all changes in separate notices, do them at the highest level of change.

Mark Coyne-Qwest said that he realizes these types of changes do present difficulty for the documentation team to track and is a challenge to both Qwest and the CLECs. Mark said we took at look to determine how often this has occurred and found only found 17 occurrences in the past 2 years. Mark said that this is in relation to approximately 977 notices and is less than 1%. He said that these situations will continue to occur on a rare basis as it has in the past. He said that we are in full agreement with the 2nd part of the CM request which is how we relate those changes on the notice to make sure the CLEC are aware of those changes. Mark said that he liked the idea of cross referencing or pointing the CLEC to the notice so the CLECs can determine the impact. He said there is a concern with the statement in the proposal that Qwest will not initiate a proposed change. Mark said we can’t say that we will never initiate a change and that the proposal does include except in certain conditions. He said that we have a counter proposal with language in the 1st piece to accommodate our business needs, but at the same recognizing that this is a rare occasion. Mark said that if this happens we will address it with information on the notice. Bonnie Johnson-Integra said that PAETEC and Integra will look at the counter proposal and is good to hear we are in agreement that we need to care for the issue. Bonnie said that they can’t agree with the change from “will” to “should” because it does not give them any certainty.

Mark Coyne-Qwest asked that the CLECs review the entire counter proposal and let us know what concerns and comments they have and we will go back and take a look at “will” vs. “should”.

Bonnie Johnson-Integra asked Qwest to let them know what they are trying to achieve by changing the language to not having any certainty. She said that “should” won’t work for the CLECs and “will” won’t work for Qwest but until they know what the concern is, she doesn’t know what to propose.

Julia Redman-Carter-PAETEC asked if Qwest would consider the idea when there are previous changes not yet effective, to note in the document that there are changes under review that are not yet effective and in the document redline highlight those changes.

Mark Coyne-Qwest said that we don’t have a problem pointing back to the Document Review site so that you can see the related notice.

Julia Redman-Carter-PAETEC said if there was another solution (5/28/09 Comments to minutes received from PAETEC in CAPS) THAT MIGHT BE EASIER for Qwest other than providing the information in the notice, they will entertain other suggestions. THE PURPOSE OF THE PROPOSED CHANGE IS to be able to identify ALL the APPLICABLE changes in those situations SO WE CAN MAKE INFORMED DECISIONS.

Mark Coyne-Qwest said that he didn’t see a problem on the 2nd piece of providing the notice number and providing a link back to the document review site rather than including the information on the subsequent notice. Mark addressed the comment from Integra on the “will” vs. “should” and it was phrased it in the 1st sentence that Qwest will attempt to avoid issuing or initiating those types of changes.

Bonnie Johnson-Qwest said that if there is an overlap notice it needs to address how you are going to handle and the result if that happens. She said that the 1st part talks about the effort or attempt and the 2nd part should have certainty if unavoidable.


Open Product/Process CR PC020409-1EXES Detail

 
Title: Qwest will implement the USOC to correct the facility assignment for HDSL
CR Number Current Status
Date
Area Impacted Products Impacted

PC020409-1EXES Denied
2/17/2009
Provisioning, Ordering Unbundled Loop, Loop
Originator: Johnson, Bonnie
Originator Company Name: Integra
Owner: Mohr, Bob
Director:
CR PM:

Description Of Change

Integra and its entities (“Integra”) submits this change request (CR) to address a single issue – implementation of a Universal Service Ordering Code (“USOC”) for HDSL (2 and 4 wire non loaded loops) to correct assignment of facilities. Qwest has indicated that there is a USOC already recognized by Telcordia/industry standards that would help ensure that facilities assigned to CLECs meet the parameters and industry standards applicable to the specific HDSL product ordered by the CLEC. Qwest, however, has not yet implemented its use for CLECs. (Qwest has not yet indicated whether it uses this USOC for Qwest retail or, if not, how assignment of facilities is physically performed for Qwest retail. Qwest should provide this information.) Qwest should implement the USOC expeditiously.

This CR does not replace in any way Integra’s CR PC082808-1IGX (which is broader), and it should not delay the processing of that CR. Implementation of a USOC was not specifically mentioned in the description of change in that CR, whereas here Integra is specifically requesting USOC implementation for HDSL. Integra reserves its rights as to CR PC082808-1IGX. It appears from CMP discussions related to PC082808-1IGX that implementation of the USOC may be bogged down by other issues, so Integra has also submitted this CR to attempt to avoid delay in implementing the USOC. If implementation of the USOC assists in resolving some of the issues raised in CR PC082808-1IGX, as suggested by Qwest, then the companies may address that situation at the time.

CLECs communicate the type of service they intend to provide on 2/4 Wire Non-Loaded Loops by using the appropriate NCI/SECNCI codes on the Local Service Request (LSR). Qwest, however, told Integra personnel that Qwest provisions circuits to voice grade parameters, regardless of the NCI/SECNCI code requested on the LSR (e.g., even if the code indicates a digital capable service, rather than a voice grade service). Qwest has suggested that the resulting problems may be at least partially alleviated if Qwest implements this USOC because, once Qwest assigns the USOC to a service, doing so will allow it to flow through facility assignment to better identify a facility capable of supporting HDSL2 service. Although Qwest had said that work on USOC implementation is currently underway and scheduled to be implemented in mid April of 2009, Qwest has since suggested that it may stop work on the USOC if CLECs do not agree to an unrelated Qwest proposal. Qwest should not tie implementation of the USOC to other issues. Doing so will cause an unnecessary delay and may cause discriminatory conditions to continue.

Qwest’s ICA negotiations template Section 9.2.2.3 states:

Qwest will provision digital Loops in a non-discriminatory manner, using the same facilities assignment processes that Qwest uses for itself to provide the requisite service. (emphasis added)

A key problem that exists today, however, is that Qwest is not meeting this commitment. For CLECs, Qwest’s facilities assignment process does not select/assign the best (most qualified) loop available for the type of loop ordered by the CLEC (e.g., HDSL). Instead, it is just as likely, or more likely, to assign a voice grade loop to fill a CLEC request for a digital capable loop. In contrast, for Qwest retail, Qwest automatically assigns the best (most qualified) loop available for the type of loop ordered by Qwest retail. Every day that this situation continues is another day of discrimination, and so every effort should be made to accelerate resolution of this problem. As Qwest has suggested that implementation of this USOC will assist with this issue for HDSL, Qwest should promptly implement the USOC.

Expected Deliverables/Proposed Implementation Date (if applicable):

Qwest will implement the USOC no later than mid April of 2009.


Status History


Project Meetings

2/18/09 Prod/Proc CMP Meeting

Mark Coyne-Qwest said that this exception CR was submitted by Integra. He said that a vote was conducted on 2/17/09 and the CR was denied. He said that a copy of the denial can be found on the Wholesale Calendar. Bonnie Johnson-Integra said Qwest traditionally sends a formal denial and asked when it would be sent. Lynn Stecklein-Qwest said that the denial was posted in the Qwest response section of the CR but that a formal denial letter would be sent. Bonnie Johnson-Integra said that she had additional questions on PC082808-1IGX. (Captured above)

Exception CR Vote Required Meeting Minutes – PC020409-1EX February 17, 2009 Attendees: Bonnie Johnson-Integra, Loriann Burke-XO, Julia Redman-Carter-McLeod, Mindy Chapman-Neustar, Bob Mohr-Qwest, Mark Nickell-Qwest, Jamal Boudhaouia, Mark Coyne-Qwest, Susan Lorence-Qwest Lynn Stecklein-Qwest stated that the purpose of this meeting is to review and conduct a vote on the Exception Request submitted by Integra to implement a USOC to correct the facility assignment for HDSL. She said that Integra and its entities (Integra) have submitted this change request to address a single issue - implementation of a Universal Service Ordering Code (USOC) for HDSL (2 and 4 wire non loaded loops) to correct assignment of facilities. Integra is seeking the following exceptions: • Implement the USOC no later than mid April of 2009 • This exception CR will not replace Integra s CR PC082808-1IGX and should not delay the processing of the CR. Lynn said that Quorum is eight and has been achieved. She reviewed the yes and no vote as follows: A vote of - Yes will indicate a preference to allow the implementation of the USOC to correct the facility assignment for HDSL no later than mid April 2009 and not delay the processing of PC082808-1IGX. A vote of - No will indicate a preference to NOT allow the implementation of the USOC to correct the facility assignment for HDSL and not delay the processing of PC082808-1IGX.

Bonnie Johnson-Integra said that she wanted to make sure that we were voting on whether this CR would be treated as an exception.

Lynn said that we were.

She said that Section 16.4 of the CMP Document states that - If the Exception Request is for a general change to the established CMP timelines for Product/Process changes, a two-thirds majority vote will be required unless Qwest or a CLEC demonstrates, with substantiating information, that one of the criteria for denial set forth in Section 5.3 is applicable. If one of the criteria for denial is applicable, the request will not be treated as an exception. E-mail votes with a vote of yes have been received from: Covad, Comcast Cable, Jaguar Communication, Live Wire Networks, Quantum Communications, Verizon Business During the call Integra, McLeod and XO voted yes. Lynn said that Qwest voted no. She said as stated earlier in section 16.4, this section allows for the CR to not be granted as an exception if one of the criteria for denial is applicable. She said that Bob Mohr (Qwest) will provide information on why the request will not be granted as an exception CR based on the standards set forth in Section 5.3. Bob Mohr-Qwest said this Exception Change Request requires a business discussion regarding the obligation to provide the HDSL Capable Loop USOC and the cost to do so. Absent the obligation to provide an HDSL Capable Loop, the decision to implement this Exception CR becomes a financial decision. Absent the CLEC community agreement to perform cooperative testing, this HDSL Capable Loop USOC implementation becomes a financial liability to Qwest. Qwest therefore respectfully denies this Exception CR to implement an HDSL Capable Loop USOC without including the cooperative test requirement as it is economically not feasible.

Bonnie Johnson-Integra said that Qwest is willing to do this for themselves but not for Wholesale.

Lynn Stecklein-Qwest said that this CR will be closed and the formal denial response will be sent to Integra and posted to the Wholesale Calendar.


CenturyLink Response

February 17, 2009

Qwest Response Exception Vote Required Meeting

Bonnie Johnson Integra

SUBJECT: CLEC Change Request Response - CR #PC020409-1EX

This CR submitted by Integra and its entities (“Integra”) is requesting to address a single issue – implementation of a Universal Service Ordering Code (“USOC”) for HDSL (2 and 4 wire non loaded loops) to correct assignment of facilities. Qwest has indicated that there is a USOC already recognized by Telcordia/industry standards that would help ensure that facilities assigned to CLECs meet the parameters and industry standards applicable to the specific HDSL product ordered by the CLEC. Qwest, however, has not yet implemented its use for CLECs. (Qwest has not yet indicated whether it uses this USOC for Qwest retail or, if not, how assignment of facilities is physically performed for Qwest retail. Qwest should provide this information.) Qwest should implement the USOC expeditiously.

This Exception Change Request requires a business discussion regarding the obligation to provide the HDSL Capable Loop USOC and the cost to do so. Absent the obligation to provide an HDSL Capable Loop, the decision to implement this Exception CR becomes a financial decision. Absent the CLEC community agreement to perform cooperative testing, this HDSL Capable Loop USOC implementation becomes a financial liability to Qwest. Qwest therefore respectfully denies this Exception CR to implement an HDSL Capable Loop USOC without including the cooperative test requirement as it is economically not feasible.

Sincerely,

Qwest Corporation


Open Product/Process CR PC060111-4 Detail

 
Title: Need for a Process/Policy on what net neutrality information a reseller should disclose, and the manner in which the Qwest reseller should disclose that information to its customers.
CR Number Current Status
Date
Area Impacted Products Impacted

PC060111-4 Denied
7/20/2011
Resale Any resale product impacted by the FCC Net Neutrality order
Originator: Johnson, Bonnie
Originator Company Name: Integra
Owner: Campbell, Bill
Director:
CR PM: Lorence, Susan

Description Of Change

The FCC issued its order on Net Neutrality (FCC 10-201; 25 FCC Rcd 17905; GN Docket No 09-191 and WC Docket No. 07-52). The order will be effective around August 1, 2011. Resellers of Qwest internet access products will need to provide Net Neutrality disclosure language for those Qwest internet access products. Confusion may result if the disclosures are different. Please provide Qwest’s disclosure language and if needed, a process for carriers to obtain and use that language.


Status History


Project Meetings

7/20/11 Product Process Monthly CMP Meeting Mark Coyne – CenturyLink – provided an update on CR status. Qwest response/denial (7/28/11 Updates received from Integra in CAPS) WAS sent (7/28/11 Updates received from Integra in CAPS) ON 7/14 and included in (7/29/11 Updates received from PAETEC in italicized CAPS) SAID [Deleted RELAYED] CMP package. As part of CMP the response/denial was reviewed. QWEST‘S RESPONSE INDICATED [DETERMINED], THAT IT WAS DETERMINED THAT THE PRODUCTS ASSOCIATED WITH THE NET NEUTRALITY ORDER ARE RELATED TO INTERNET ACCESS (HSI, QVR, QWB) BECAUSE THESE INTERNET ACCESS PRODUCTS ARE OUTSIDE OF THE SCOPE OF CMP. HOWEVER, DURING THE CLARIFICATION CALL, IT WAS AGREED THAT UPON QWEST'S REVIEW OF THE FINAL ORDER, IT WILL BE DETERMINED WHAT CHANGES AND NOTIFICATIONS ARE REQUIRED TO THE QWEST CUSTOMER. QWEST WILL ALSO THEN NOTIFY THEIR WHOLESALE CUSTOMERS VIA A NON-CMP NOTICE. Requested to move CR to denied status if no objection.

Bonnie Johnson- Integra said she was fine with that.

6/15/11 Product Process Monthly CMP Meeting Bonnie Johnson- Integra said the CR was to request a process associated with the Net Neutrality order that has no known date right now. She said during the Clarification call, it was identified that the order only impacts HSI resale products that Qwest said are under commercial agreements and not part of CMP. Qwest is going to deny the CR (6/23/11 Updates received from Integra in CAPS) WITH A NOTE THAT [delete AND] will state that when the order is received, Qwest will review and provide information to the commercial agreements notification group.

Mark Coyne – Qwest clarified those services are outside of the scope of CMP and that Qwest was preparing the denial response.

Bonnie Johnson- Integra said though Qwest is denying the CR, there was agreement on the process that will be used to communicate. Once the order comes out, Qwest will determine the disclosure and send a notice to Commercial agreement carriers.

Mark Coyne – Qwest said yes. There were no other questions.

6/13/11 Clarification Meeting Attendees: Bonnie Johnson-Integra, Kim Isaacs – Integra, Mark Coyne-CenturyLink, Jamal Boudhaouia -CenturyLink, Bill Campbell -CenturyLink, Susan Lorence-CenturyLink

Bonnie Johnson-Integra said the net neutrality order is to go into effect around August 1, 2011 and for the products Integra resells, they require net neutrality disclosure and their requirements should be same as Qwest and they do not want to forward customers to the Qwest website.

Jamal Boudhaouia -CenturyLink asked which products she was referring to and said it was a proposed order from the FCC.

Bonnie Johnson - Integra said she is not an expert on net neutrality and was maybe making an assumption that Qwest was developing disclosure on impacted products and that it would impacts products that resellers resell.

Jamal Boudhaouia -CenturyLink said based on his analysis, the proposed order impacts the products that are internet access offered to mass markets and small business customers and the only customers impacted are HSI.

Bonnie Johnson-Integra said OK and asked if they have commercial agreements on those.

Bill Campbell -CenturyLink said yes.

Bonnie Johnson-Integra said if Qwest believes those are the products requiring disclosure, then Integra should mirror it.

Jamal Boudhaouia -CenturyLink said by definition, it only impacts products associated with internet access and the only product that is offered for resale is QWB via commercial agreement.

Bill Campbell -CenturyLink said QVR is also offered.

Bonnie Johnson-Integra said she is not debating which products Qwest believes require disclosure but that for those products that do, Qwest and Integra should work together.

Jamal Boudhaouia -CenturyLink said the order was FCC 10-201 adopted December 21, 2010 and released December 23, 2010.

Bonnie Johnson-Integra said it appears the effective date is August 1.

Jamal Boudhaouia -CenturyLink said he respectfully disagreed based on where the order was in the FCC order process.

Bonnie Johnson-Integra said it may not be August 1 but whatever date, she would like to get it done.

Jamal Boudhaouia -CenturyLink said he did not disagree but based on the FCC process, he thought the earliest date would be October 15, 2011.

Bill Campbell -CenturyLink questioned whether a declarative statement had to be issued.

Jamal Boudhaouia -CenturyLink said no but it was open for debate the type of required disclosure within the industry. He said once the order was effective, resale disclosure requirements would be determined.

Bill Campbell -CenturyLink said when the general business changes are determined, retail would make some decisions, and he would send a non-CMP notice to HSI wholesale customers.

Bonnie Johnson-Integra said she thought the CR would remain on HOLD until decisions are made but wanted a plan of action.

Susan Lorence-CenturyLink said she understood the products are related to internet access (HSI, QVR, QWB) that are outside of the scope of CMP and she did not want to keep the CR open.

Bonnie Johnson-Integra said to respond to the CR as suggested and close the CR.

Bill Campbell -CenturyLink and Jamal Boudhaouia -CenturyLink agreed that that plan would work

Bill Campbell -CenturyLink said upon Qwest/CTL review of the final order, it will be determined what changes and notifications are required to the Qwest customer. Qwest will also then notify their wholesale customers via a non-CMP notice.

Susan Lorence-CenturyLink said the SME team would confirm this approach and asked if there were any other questions and there were none.


CenturyLink Response

July 14, 2011 To: Bonnie Johnson, Integra

CC: Kim Isaacs – Integra, Mark Coyne - Qwest, Jamal Boudhaouia – Qwest, Bill Campbell - Qwest, Susan Lorence-Qwest

This letter is in response to CLEC Change Request PC060111-4, Need for a Process/Policy on what net neutrality information a reseller should disclose, and the manner in which the Qwest reseller should disclose that information to its customers

CR Description: The FCC issued its order on Net Neutrality (FCC 10-201; 25 FCC Rcd 17905; GN Docket No 09-191 and WC Docket No. 07-52). The order will be effective around August 1, 2011. Resellers of Qwest internet access products will need to provide Net Neutrality disclosure language for those Qwest internet access products. Confusion may result if the disclosures are different. Please provide Qwest’s disclosure language and if needed, a process for carriers to obtain and use that language.

Expected Deliverable: Qwest will work with Resellers of Qwest’s internet access products to develop a process so Resellers can obtain the net neutrality disclosure language and use that language for Qwest resale products impacted by the FCC net neutrality order.

History: The CR was submitted on June 1, 2011 and a clarification meeting was held on June 13, 2011 with Integra and Qwest representation. The CR was presented in the June CMP monthly meeting.

Qwest Response: As part of the discussion in the Clarification call on June 13, 2011, it was determined that the products associated with the Net Neutrality order are related to internet access (HSI, QVR, QWB). Because these internet access products are outside of the scope of CMP, Qwest is denying this CR for that reason. However, during the clarification call, it was agreed that upon Qwest's review of the final order, it will be determined what changes and notifications are required to the Qwest customer. Qwest will also then notify their wholesale customers via a non-CMP notice.

Sincerely, Qwest Corporation


Open Product/Process CR PC070816-1X Detail

 
Title: Add reporting functionality to the CLEC Badge Access Request Web site (See Crossover CR SCR070816 1X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC070816-1X Completed
2/15/2017
Collocation Access premise process
Originator: Roberson, Laurie
Originator Company Name: Integra
Owner: Cederberg , Annmarie
Director:
CR PM: Lorence, Susan

Description Of Change

Integra requests CenturyLink add Report functionality to the CLEC Badge Access Request website. The reporting function would allow CLECs to generate reports that provide the CLEC with the ability to view badge holders access level by CenturyLink central office or card reader.

Currently, CLECs request this report from their service manager. Based on the amount of time it takes CenturyLink to fulfill a report request, Integra believes it would be more efficient if CLECs have the ability to generate their own reports. Providing the CLECs the ability to efficiently inventory their access badges may lower the number of duplicate badge requests and issues surrounding badge access which should result in efficiency gains for both CenturyLink and the CLECs.

Expected Deliverables/Proposed Implementation Date (if applicable): The ability to generate ad hoc reports that would show an inventory of badge holders current access by central office or card reader.


Status History


Project Meetings

2/15/17 Product/Process CMP Meeting Mark Coyne – CenturyLink recapped some history for this CR. It was submitted as a System CR but was crossed over to Product Process in August 2016. CenturyLink proposed a three month Process Trial that ended on December 31, 2016. Following the trial, the CenturyLink Security team evaluated the results. CenturyLink submitted a level 4 process notification on January 9, 2017 to have customers directly email the CenturyLink Security team mailbox to request a Badge Access Report. The Final notice was sent on January 26, 2017. The CR has been in CLEC Test since the effective date of February 10, 2017. Mark said we would like to move this CR to a COMPLETED status and asked if there were any objections. There were none.

1/18/17 Product/Process CMP Meeting Mark Coyne – CenturyLink said the three month Process Trial ended on December 31, 2016. The CenturyLink Security team evaluated the results and determined they would move forward with the change in process to have customers directly email the CenturyLink Security team mailbox to request a CLEC Badge Access Report. The intent is that the Badge Access Report will be provided within 3 business days. Mark said a level 4 process notification was distributed January 9, 2017 with a planned effective date of February 10, 2017. Mark asked if there were any questions. There were none.

12/14/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this ELI CR is in the last month of a Process trial. So far there have not been problems filling the CLEC Badge Access Report requests within the three business day window. After the trial ends on December 31, the CenturyLink Security team will evaluate the results. Based on their evaluation of the volume of requests and the timing of the report turn-around, it is likely a Level 3 change in process notification will be sent after the first of the year. Mark asked if there were any questions. There were none.

11/16/16 Product/Process CMP Meeting COVERED UNDER ATTACHMENT C Mark Coyne – CenturyLink said this ELI CR is in the middle of a three month Process trial to have customers directly email the CenturyLink Security team mailbox to request the CLEC Badge Access Report. The trial is to determine volume of requests and the timing of the report turn-around by the CenturyLink Security team. Mark said in talking with Mark Rice, CenturyLink, there has been no problem so far filling the report requests in the three business day timeline. Mark said following the end of the trial on December 31, 2016, CenturyLink will evaluate the results. If CenturyLink determines a change should be implemented, the appropriate level of CMP notification will be sent to formalize the process. Mark asked if there were any questions. There were none.

10/19/16 Product/Process CMP Meeting COVERED UNDER ATTACHMENT C Mark Coyne – CenturyLink said this is one of the ELI Crossover CRs. In the September CMP meeting, we reviewed the updated CenturyLink response that stated that CenturyLink would be initiating a three month Process trial to determine how many customer requests would be received each month for the badge holder report and whether the proposed turnaround time of three business days is valid for the Security team to fulfill the report request. A copy of the Process notification that was sent on September 26, 2016 to announce the trial is included in the package. The trial is scheduled from October 1, 2016 through December 31, 2016. Mark said that at the completion of the Process Trial, CenturyLink will evaluate the results to determine if a change to the current process is appropriate. If so, CenturyLink will implement the change through the appropriate level of CMP notification to formalize the process updates available to all customers.

Kim Isaacs - Electric Lightwave said they had submitted a Walk On request regarding the Process Trial and asked if it should be discussed with this CR.

Mark Coyne – CenturyLink said yes. He said the Walk on request was received on October 18, 2016 and that it was posted to the Wholesale calendar. He then read in part the ELI Walk on: The notice does not state what information is required to request the badge report and we would like clarification on that.

Kim Isaacs - Electric Lightwave said ELI had trialed the report request process. The request took CenturyLink longer than the planned three business days to fulfill but there was no word why. Kim asked if it would make the report process more efficient if the customer included their RSID and/or ACNAs when the report request is made. She said a Service Manager is closer to the customer’s account than the CenturyLink Security team and asked if including a little more information might be helpful. Kim said it might work better if CenturyLink does not have to assume what the customer wants and can pull the correct report right away.

Mark Rice – CenturyLink said the ELI report request was sent correctly. He said previously, the CenturyLink Security team had a process established to send a report to Integra at the first of each month so when the ELI request came in to the mailbox, he thought the report had already been delivered. Mark said the problem occurred within the Security team and that he sent the requested ELI report on October 18. The report normally includes all entities for a customer. Mark said if a customer was requesting a “traffic report” or an “access report” for a specific person or time period, that was a different type request. Kim Isaacs - Electric Lightwave said since the trial was open to all customers, was there a standard request that should be used.

Mark Rice – CenturyLink said the Security team has a standard format for the Badge Card Holder report and that is the only information that can be provided from CenturyLink. Mark said he takes the responsibility that the ELI requested report was not delivered within the planned time period of three business days.

Susan Lorence – CenturyLink asked if it was appropriate as Kim had suggested for customers to provide the ACNAs or RSID to the CenturyLink Security team on the email request.

Mark Rice – CenturyLink said that he had all of the information he needed to create the report.

Kim Isaacs - Electric Lightwave said the process could be changed in the future if CenturyLink determines that more information is needed.

Mark Coyne – CenturyLink once the trial is complete, CenturyLink will assess the results and can make an additional change then if appropriate. Mark asked if there were any more questions. There were none.

COVERED UNDER ATTACHMENT F Mark Coyne – CenturyLink said we had already discussed the Walk on from Electric Lightwave under Attachment C with CLEC CR PC070816-1X - Add reporting functionality to the CLEC Badge Access Request Web site. [see Walk on received on 10-18-16 that is posted separately to CMP calendar entry.]

9/21/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this is one of the ELI Crossover CRs. A Draft response was reviewed last month that stated the CenturyLink SME team needed additional time to consider the broader revisions associated with the proposed process change. Mark then reviewed the revised response (included in the CMP package) that had the following key points:

• The CenturyLink SME team is proposing that a process trial be conducted between October 1, 2016 and December 31, 2016. • The process trial would track the number of customer requests received each month and determine if the turn-around time of three business days to return the report to the customer is valid.

Mark said CenturyLink will send a notification to all CLEC and Reseller customers to inform them of the Security team mailbox and the availability of the trial within CenturyLink QC. At the end of the Process trial, CenturyLink will evaluate the results and will then send the appropriate CMP notification to formalize the process updates available to customers.

Kim Isaacs - Electric Lightwave asked if the evaluation would possibly include crossing the CR back to systems to add the requested reporting functionality.

Mark Coyne – CenturyLink said that adding a report that customers could request directly was not possible. The Trial was to confirm the volume and timing for the Security team.

Kim Isaacs - Electric Lightwave asked if it was to confirm the CenturyLink Security team can keep up with the three business day turn around for report requests from the customer.

Mark Coyne – CenturyLink said correct and asked if there were any other questions. There were none.

8/17/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this is a Crossover CR from the Systems side. The Systems CR SCR070816-1X was presented last month by Kim Isaacs – Electric Lightwave. The CR is associated with the CLEC Badge Access Request process. A clarification call was held on July 18, 2016 and based on discussion during the Clarification call, it was agreed that the CR would crossover to Product Process for a change in process. Mark said that CenturyLink had sent a Draft response on August 11, 2016 (8-26-16 Updates received from Electric Lightwave in CAPS) WITH A PROPOSED EFFECTIVE DATE but after additional discussion with the SME team, a revised draft response had been sent on August 12, 2016. He then reviewed the Draft response which stated that additional time was needed by the SME team to consider the broader revisions to the current process. CenturyLink will continue to evaluate this CR. He said until CenturyLink has a proposed effective date, CenturyLink will continue business as usual.

Kim Isaacs - Electric Lightwave asked if the CR would be in Evaluation status.

Mark Coyne – CenturyLink said the CR has been Accepted.

Susan Lorence - CenturyLink said the CR is in a status of Cross over for the first month and then CenturyLink will move it to Evaluation status.

Kim Isaacs - Electric Lightwave confirmed the existing process would remain in place while the CR is being evaluated.

Mark Coyne – CenturyLink said yes.


CenturyLink Response

September 16, 2016

Kim Isaacs, Electric Light Wave Laurie Roberson, Electric Light Wave

SUBJECT: Change Request PC070816-1X, CenturyLink Updated Response for Review

This letter includes an updated response to Electric Light Wave/Integra’s Crossover Change Request PC070816-1X, entitled “Add reporting functionality to the CLEC Badge Access Request Web site”.

CR Description: Integra requests CenturyLink add Report functionality to the CLEC Badge Access Request website. The reporting function would allow CLECs to generate reports that provide the CLEC with the ability to view badge holders access level by CenturyLink central office or card reader. Currently, CLECs request this report from their service manager. Based on the amount of time it takes CenturyLink to fulfill a report request, Integra believes it would be more efficient if CLECs have the ability to generate their own reports. Providing the CLECs the ability to efficiently inventory their access badges may lower the number of duplicate badge requests and issues surrounding badge access which should result in efficiency gains for both CenturyLink and the CLECs.

Updated CenturyLink Response: During the August CMP monthly meeting, CenturyLink reviewed the revised Draft response sent on August 12, 2016 which stated that the Change Request would be crossed over to Product Process. The revised CR response also stated that the SME team needed additional time to consider the broader revisions required before implementing the proposed process to have customers send their request for a report directly to the CenturyLink Security team mailbox.

After further consideration, the CenturyLink SME team is proposing that a process trial be conducted between October 1, 2016 and December 31, 2016. The trial would determine the number of customer requests for the badge holder report that are received each month in the CenturyLink Security team mailbox. The Security team would also determine if the requested turnaround time of three business days to fulfill the report request is valid.

CenturyLink will send notification of the Process trial to all CLEC and Reseller customers in CenturyLink QC. At the completion of the Process trial, CenturyLink will evaluate the results to determine if a change to the current process is appropriate. If so, CenturyLink will implement the change through the appropriate level of CMP notification to formalize the process updates available to all customers.

Please let us know if you have any questions about this proposed process trial. Sincerely, Susan Lorence CenturyLink Wholesale CR Project Manager

* August 12, 2016

Kim Isaacs, Integra Laurie Roberson, Integra

SUBJECT: Integra System Change Request SCR070816-1X, CenturyLink Response for Review REVISED

This letter is in response to Integra System Change Request SCR070816-1, entitled “Add reporting functionality to the CLEC Badge Access Request Web site”.

CR Description: Integra requests CenturyLink add Report functionality to the CLEC Badge Access Request website. The reporting function would allow CLECs to generate reports that provide the CLEC with the ability to view badge holders access level by CenturyLink central office or card reader. Currently, CLECs request this report from their service manager. Based on the amount of time it takes CenturyLink to fulfill a report request, Integra believes it would be more efficient if CLECs have the ability to generate their own reports. Providing the CLECs the ability to efficiently inventory their access badges may lower the number of duplicate badge requests and issues surrounding badge access which should result in efficiency gains for both CenturyLink and the CLECs.

History and CenturyLink Response: This System CR was received on July 8, 2016 and was presented as a walk-on in the July 2016 Monthly Systems CMP meeting. A Clarification call was held on July 18, 2106 with Integra and CenturyLink representatives present. During the Clarification call, there was agreement to cross the CR over to a Product Process CR, PC070816-1X, to implement a process change. The CenturyLink Security team will provide a direct email address for customers to request the report versus continuing to request the report through their Service Manager. The report will be returned to customers within three business days. The data on the report will include badge id, first and last name, company, access level and card reader as it does currently.

This CR will be reviewed as a Crossover CR during the August 2016 Product Process CMP meeting. Following further discussion on August 12, 2016 with the CenturyLink SME team, additional time is needed to consider the broader revisions to the current process. CenturyLink will continue to evaluate this CR and does not yet have a proposed effective date.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager

**

August 11, 2016

Kim Isaacs, Integra Laurie Roberson, Integra

SUBJECT: Integra System Change Request SCR070816-1X, CenturyLink Response for Review

This letter is in response to Integra System Change Request SCR070816-1, entitled “Add reporting functionality to the CLEC Badge Access Request Web site”.

CR Description: Integra requests CenturyLink add Report functionality to the CLEC Badge Access Request website. The reporting function would allow CLECs to generate reports that provide the CLEC with the ability to view badge holders access level by CenturyLink central office or card reader. Currently, CLECs request this report from their service manager. Based on the amount of time it takes CenturyLink to fulfill a report request, Integra believes it would be more efficient if CLECs have the ability to generate their own reports. Providing the CLECs the ability to efficiently inventory their access badges may lower the number of duplicate badge requests and issues surrounding badge access which should result in efficiency gains for both CenturyLink and the CLECs.

History and CenturyLink Response: This System CR was received on July 8, 2016 and was presented as a walk-on in the July 2016 Monthly Systems CMP meeting. A Clarification call was held on July 18, 2106 with Integra and CenturyLink representatives present. During the Clarification call, there was agreement to cross the CR over to a Product Process CR, PC070816-1X, to implement a process change. The CenturyLink Security team will provide a direct email address for customers to request the report versus continuing to request the report through their Service Manager. The report will be returned to customers within three business days. The data on the report will include badge id, first and last name, company, access level and card reader as it does currently.

This CR will be reviewed as a Crossover CR during the August 2016 Product Process CMP meeting. CenturyLink is moving forward with a level 4 notification to update the Collocation -Premises Access Overview PCAT. At this time, the proposed effective date will be September 27, 2016.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager


Open Product/Process CR PC070816-2X Detail

 
Title: Add CLLI code (8 digit) option for Building Search to the CLEC Badge Access Request Website (See Crossover CR SCRC070816 2X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC070816-2X Completed
12/14/2016
Collocation Access premise process
Originator: Roberson, Laurie
Originator Company Name: Integra
Owner: Cederberg , Annmarie
Director:
CR PM: Lorence, Susan

Description Of Change

Integra requests that CenturyLink add a CLLI code search option to the CLEC Badge Access Request website. Currently the system has an option to search by “Building ID”, however, the CLEC community does not use Building ID. In addition, CenturyLink bills charges associated with access badges using the CLLI code. The CLLI code is an industry standard code that the CLEC community uses to easily identify central offices. Adding this field would allow the CLEC to quickly identify the central office they need access to.

Expected Deliverables/Proposed Implementation Date (if applicable): To be able search by CLLI code under Building Search in the CLEC Badge Access web site.


Status History


Project Meetings

12/14/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this ELI CR has been in CLEC Test since November 15, 2016 when the 8 digit CLLI code search option was implemented in the Badge Access Request web tool. Mark said we would like to move this CR to a Completed status.

Kim Isaacs - Electric Lightwave said there are no objections. Kim said any issues they have encountered have been due to new people on their side and said thank you.

Mark Coyne – CenturyLink said we will move this to Completed then.

11/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this ELI CR is in CLEC Test as of November 15, 2016 when the 8 digit CLLI code search option was implemented in the CenturyLink Badge Access Request web tool. Mark said we will leave the CR in CLEC Test and will review it in December. Mark asked if there were any questions. There were none.

10/19/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this is the second ELI Crossover CR. On October 11, 2016, CenturyLink sent an updated CR response to ELI. Mark then reviewed the key points in the response as included in the package. The CenturyLink response indicates that the planned effective date had been moved to November 15, 2016. This change is due to the CenturyLink SME team needing some additional time to review some inconsistencies in the CLLI code data. Mark asked if there were any questions. There were none.

9/21/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this is the second ELI Crossover CR. He said the draft response was reviewed last month which also proposed this CR be a cross over to Product Process. Kim Isaacs - Electric Lightwave had expressed concern about the crossover to Product Process from Systems but agreed to it as long as the concern was noted. Mark then reviewed the updated response (included in the CMP package) that stated CenturyLink is planning to implement the CLLI code (8 digit) Building Search option in the CLEC Badge Access Request Website with an effective date of November 1, 2016. Mark asked if there were any questions.

Kim Isaacs - Electric Lightwave said she did not have any and said thank you.

FROM 8/17/16 System CMP Meeting Minutes Mark Coyne – CenturyLink said this was the other CR of the two new System CRs presented by Electric Lightwave last month associated with the CLEC Badge Access Request process. Mark then reviewed the CenturyLink Draft Response that was sent on August 11, 2016 and said that based on further investigation by the CenturyLink SME team, CenturyLink accepts this CR and believes this CR should also be crossed over to Product Process. At this time, the proposed effective date would be early October 2016. Mark asked if Electric Lightwave was OK to Cross this CR over to Product Process.

Kim Isaacs - Electric Lightwave said historically, that has occurred with web functionality CRs but Electric Lightwave disagrees that web functionality is Product Process vs. Systems. Kim said that they agree to disagree on this but, with that noted, is OK to cross the CR over.

Mark Coyne – CenturyLink said based on that, the CR will be a Cross over CR next month.

Bonnie Johnson – MN Dept of Commerce asked why web functionality is being addressed by CenturyLink as Product Process. She said she agrees with Electric Lightwave that it has always been Systems.

Susan Lorence – CenturyLink said the reason is that a Systems CR has a longer implementation/notification cycle than a Product Process CR. Also, a system CR would require CenturyLink to use some of the allotted system hours for the year and that was not needed for this CR. Susan also referenced the existing Level 2 Product Process Change Category that CenturyLink felt best fit this type of change: • Changes to eliminate/replace existing Web functionality will be available for twenty-one (21) days until comments are addressed. (Either a demo or screen shot presentation will be available at the time of the notification for evaluation during the twenty-one (21) day cycle.) Susan said this type of web update is not like a web change to a GUI. She said that type of CR would have to remain a System CR and asked if that explanation helped.

Bonnie Johnson – MN Dept of Commerce said thank you.

Mark Coyne – CenturyLink asked if there were any other comments and asked Kim if she wanted to keep the comment that they disagreed with this approach.

Kim Isaacs - Electric Lightwave said yes, she believes web functionality should be a system change.


CenturyLink Response

October 11, 2016

Kim Isaacs, Electric Light Wave Laurie Roberson, Electric Light Wave

SUBJECT: Change Request PC070816-2X, CenturyLink Updated Response for Review

This letter includes an updated response to Electric Light Wave/Integra’s Crossover Change Request PC070816-2X, entitled “Add CLLI code (8 digit) option for Building Search to the CLEC Badge Access Request Website”.

CR Description: Integra requests that CenturyLink add a CLLI code search option to the CLEC Badge Access Request website. Currently the system has an option to search by “Building ID”, however, the CLEC community does not use Building ID. In addition, CenturyLink bills charges associated with access badges using the CLLI code. The CLLI code is an industry standard code that the CLEC community uses to easily identify central offices. Adding this field would allow the CLEC to quickly identify the central office they need access to.

Updated CenturyLink Response: During the September CMP monthly meeting, CenturyLink reviewed the UPDATED CR response which stated that after further analysis, the CenturyLink SME team had revised the proposed effective date and was planning to implement the CLLI code (8 digit) Building Search option in the CLEC Badge Access Request Website with an effective date of November 1, 2016. The SME team is continuing to work on some data cleanup issues with the CLLI codes in the CLEC Badge Access Request web tool and has REVISED the PLANNED EFFECTIVE date to be November 15, 2016.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager

* September 15, 2016

Kim Isaacs, Electric Light Wave Laurie Roberson, Electric Light Wave

SUBJECT: Change Request PC070816-2X, CenturyLink Updated Response for Review

This letter includes an updated response to Electric Light Wave/Integra’s Crossover Change Request PC070816-2X, entitled “Add CLLI code (8 digit) option for Building Search to the CLEC Badge Access Request Website”.

CR Description: Integra requests that CenturyLink add a CLLI code search option to the CLEC Badge Access Request website. Currently the system has an option to search by “Building ID”, however, the CLEC community does not use Building ID. In addition, CenturyLink bills charges associated with access badges using the CLLI code. The CLLI code is an industry standard code that the CLEC community uses to easily identify central offices. Adding this field would allow the CLEC to quickly identify the central office they need access to.

Updated CenturyLink Response: During the August CMP monthly meeting, CenturyLink reviewed the Draft response which stated that the Change Request was accepted for implementation. The CenturyLink response also recommended that the CR be crossed over to a Product Process CR to implement the enhanced web functionality to the CLEC Badge Access Request Website. At that time, the proposed effective date was to be early October 2016.

After discussion in the monthly meeting, it was agreed that CenturyLink would note the concerns expressed by Electric Light Wave/Integra and could then crossover the CR to Product Process PC070816-2X. After further analysis, the CenturyLink SME team has revised the proposed effective date and is planning to implement the CLLI code (8 digit) Building Search option in the CLEC Badge Access Request Website with an effective date of November 1, 2016.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager


Open Product/Process CR PC120213-2 Detail

 
Title: Updates to the Poles, Ducts and Right of Way Process Extension of Inquiry Review Quote Acceptance Interval See related CR: PC120213 1
CR Number Current Status
Date
Area Impacted Products Impacted

PC120213-2 Completed
5/21/2014
Pre-order(Quotes & Field Verification) and Billing Poles, Ducts, Right of Way
Originator: Isaacs, Kim
Originator Company Name: Integra
Owner: Karpowich, Steve
Director:
CR PM: Lorence, Susan

Description Of Change

Integra requests the following changes to the Poles, Ducts and Right of Way process:

Extension of Inquiry Review Quote Acceptance Interval; Under the current process, a CenturyLink CenturyLink Inquiry Review quote is valid for only 30 days from the date the CLEC receives the quote. Integra requests that the quote acceptance interval be extended to a minimum of 90 days.

[NOTE: This specific change was originally the second requested change included on Integra CR PC120213-1. After discussion in the January

2014 CMP meeting, CR PC120213-1 is being split into three related CRs to address each of the requested changes separately.

Expected Deliverables/Proposed Implementation Date (if applicable):

Upon completion of this change request, Integra expects that:

CLECs will have a minimum of 90 days to accept an Inquiry Review quote.


Status History


Project Meetings

5/21/2014 Product/Process CMP Meeting PC120213-2 and PC120213-3 Mark Coyne – CenturyLink relayed that on April 16, the Final notice had been sent with an effective date of May 1, 2014. Mark said the CRs are both in CLEC Test and that we would like to move them both to a Completed status.

Kim Isaacs – Integra said that was fine.

4/16/2014 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that on March 28, CenturyLink sent a level 3 notice that incorporated the process changes for both CRs. The comment cycle just ended and there was one CLEC comment received. The final notice will be sent April 16 with an effective date of May 1, 2014. Mark asked if there were any questions; there were none.

3/19/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the draft responses to accept each of these CRs were reviewed in the February CMP monthly meeting. Mark said CenturyLink is combining the document updates for these two CRs on one level 3 notice which is close to being ready to be distributed. Our SME team is going back to review the language in current ICAs to insure there are no issues there. The level 3 notice should be going out early next week with a planned effective date of late April or early May. Mark asked if there were any questions. There were none.

2/19/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that this CR relates to a CR that CenturyLink requested be broken up last month into three separate CRs. This CR is the second of the three requested changes by Integra. Mark said CenturyLink had sent a draft response on February 12 to accept this CR and that CenturyLink will be extending the PDR Inquiry Review Quote Acceptance Interval to 90 days. The CR is in Development status and CenturyLink will be issuing a Level 3 notification to implement the modified process. Mark asked if there were any questions. There were none.


CenturyLink Response

February 12, 2014

Kim Isaacs Integra

SUBJECT: Integra CR PC120213-2, DRAFT RESPONSE for Review

This letter is in response to CLEC Change Request PC120213-2, Updates to the Poles, Ducts and Right of Way Process Extension of Inquiry Review Quote Acceptance Interval.

CR Description: Integra requested the following change to the Poles, Ducts and Right of Way (PDR) process: Extension of Inquiry Review Quote Acceptance Interval. Under the current process, a CenturyLink Inquiry Review quote is valid for only 30 days from the date the CLEC receives the quote. Integra requests that the quote acceptance interval be extended to a minimum of 90 days.

NOTE: This specific change was originally the second requested change included on Integra CR PC120213-1. After discussion in the January 2014 CMP meeting, CR PC120213-1 was split into three related CRs to address each of the requested changes separately. Upon completion of this change request, Integra expects that CLECs will have a minimum of 90 days to accept an Inquiry Review quote.

History: A clarification meeting was held on December 9, 2013 with Integra and CenturyLink representatives in attendance. The CenturyLink SME team completed an analysis of the requested change associated with the PDR Process.

CenturyLink Response: CenturyLink accepts this Integra Change Request to extend the PDR Inquiry Review Quote Acceptance Interval to 90 days and will issue a Level 3 notification to implement the modified process.

Sincerely,

Susan Lorence CenturyLink CR Project Manager


Open Product/Process CR PC120213-3 Detail

 
Title: Updates to the Poles, Ducts and Right of Way Process Monitoring of Approved CenturyLink Contractors during CLEC Field Verification See related CR: PC120213 1
CR Number Current Status
Date
Area Impacted Products Impacted

PC120213-3 Completed
5/21/2014
Pre-order(Quotes & Field Verification) and Billing Poles, Ducts, Right of Way
Originator: Isaacs, Kim
Originator Company Name: Integra
Owner: Karpowich, Steve
Director:
CR PM: Lorence, Susan

Description Of Change

Integra requests the following changes to the Poles, Ducts and Right of Way process:

Monitoring of Approved CenturyLink Contractors during CLEC Field Verification; CLECs have the option of using a CenturyLink approved contractor when conducting Field Verifications for underground facilities. CenturyLink’s current practice is to have a CenturyLink employee monitor the contractor (already approved by CenturyLink) at the CLECs expense. Integra requests a change in the policy, if CenturyLink feels it is necessary to monitor contractors they have previously ”approved” then CenturyLink should not charge the CLEC for the monitoring.

[NOTE: This specific change was originally the third requested change included on Integra CR PC120213-1. After discussion in the January

2014 CMP meeting, CR PC120213-1 is being split into three related CRs to address each of the requested changes separately.

Expected Deliverables/Proposed Implementation Date (if applicable):

Upon completion of this change request, Integra expects that:

When CLEC choses to use a CenturyLink approved contractor to complete a Field Verification for underground facilities, CenturyLink will not require the CLEC to pay for the monitoring of the approved contractor.


Status History


Project Meetings

5/21/2014 Product/Process CMP Meeting PC120213-2 and PC120213-3 Mark Coyne – CenturyLink relayed that on April 16, the Final notice had been sent with an effective date of May 1, 2014. Mark said the CRs are both in CLEC Test and that we would like to move them both to a Completed status.

Kim Isaacs – Integra said that was fine.

4/16/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that on March 28, CenturyLink sent a level 3 notice that incorporated the process changes for both CRs. The comment cycle just ended and there was one CLEC comment received. The final notice will be sent April 16 with an effective date of May 1, 2014. Mark asked if there were any questions; there were none.

3/19/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed the draft responses to accept each of these CRs were reviewed in the February CMP monthly meeting. Mark said CenturyLink is combining the document updates for these two CRs on one level 3 notice which is close to being ready to be distributed. Our SME team is going back to review the language in current ICAs to insure there are no issues there. The level 3 notice should be going out early next week with a planned effective date of late April or early May. Mark asked if there were any questions. There were none.

2/19/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that this CR again relates to a CR that we requested be broken up last month into three separate CRs. This CR is the third of the three requested changes by Integra. Mark said CenturyLink had sent a draft response on February 12 to accept this CR and that CenturyLink will be modifying the process that when a CLEC chooses to use a CenturyLink approved contractor to complete a Field Verification for underground facilities, CenturyLink will not require the CLEC to pay for the monitoring of the approved contractor. The CR is in Development status and CenturyLink will be issuing a Level 3 notification to implement the modified process.


CenturyLink Response

February 12, 2014 Kim Isaacs Integra

SUBJECT: Integra CR PC120213-3, DRAFT RESPONSE for Review

This letter is in response to CLEC Change Request PC120213-3, Updates to the Poles, Ducts and Right of Way Process - Monitoring of Approved CenturyLink Contractors during CLEC Field Verification

CR Description: Integra requested the following change to the Poles, Ducts and Right of Way (PDR) process: Monitoring of Approved CenturyLink Contractors during CLEC Field Verification. CLECs have the option of using a CenturyLink approved contractor when conducting Field Verifications for underground facilities. CenturyLink’s current practice is to have a CenturyLink employee monitor the contractor (already approved by CenturyLink) at the CLECs expense. Integra requests a change in the policy, if CenturyLink feels it is necessary to monitor contractors they have previously ”approved” then CenturyLink should not charge the CLEC for the monitoring.

NOTE: This specific change was originally the second requested change included on Integra CR PC120213-1. After discussion in the January 2014 CMP meeting, CR PC120213-1 was split into three related CRs to address each of the requested changes separately. Upon completion of this change request, Integra expects that when a CLEC chooses to use a CenturyLink approved contractor to complete a Field Verification for underground facilities, CenturyLink will not require the CLEC to pay for the monitoring of the approved contractor.

History: A clarification meeting was held on December 9, 2013 with Integra and CenturyLink representatives in attendance. The CenturyLink SME team completed an analysis of the requested change associated with the PDR Process.

CenturyLink Response: CenturyLink accepts this Integra Change Request associated with the PDR Process and the CLEC use a CenturyLink approved contractor to complete a Field Verification for underground facilities. CenturyLink will issue a Level 3 notification to implement the modified process.

Sincerely,

Susan Lorence CenturyLink CR Project Manager


Open Product/Process CR PC053112-1 Detail

 
Title: Standard Formatting of PTA Notifications
CR Number Current Status
Date
Area Impacted Products Impacted

PC053112-1 Completed
10/17/2012
Provider Test Notifications
Originator: Prull, Stephanie
Originator Company Name: Integra
Owner: Ocken, Kathy
Director:
CR PM: Lorence, Susan

Description Of Change

Integra is requesting that Centurylink create a process or procedure that will create a standard format with standardized information for the Provider Test Notifications. This includes all PTA Notices.

The notices should be delimited in a way that could be parsed by other applications or readers. The requested format is a colon delimited format with each data field on its own line.

The main field/data names should always be consistent if they are applicable to all the forms. I.E All notices say ‘PON Number’ for the CLEC PON associated to the email. Or ‘LEC/USW/CLINK Order Number’ for the Centurylink Service Order Number.

The field/data names that are applicable for the various forms should always be present and consistent even if they may not be applicable for that particular test result.

The content of the data should be consistent across all service centers and users filling in the forms. I.E. All Serial number formats are separated by a ‘.’ Or ‘/’ for an ECCKT. All Telephone numbers are separated by a ‘-‘ in the correct positions. CFA information should be in a consistent format.

The subject lines of the emails have a consistent and recognizable format. I.E. The subject includes the Carrier PON, the Type of Testing, and the Date of testing. PTA: SP-1234567-DS1,UBL - XDSL, 05162012

The header of the form will always be consistent. I.E. the header will always be USW(or appropriate name)/CLEC followed by the type of Testing. Also the names used will be consistent – Integra or Integra Telecom one or the other will always be used.

Yes/No Answers will be consistent in using the full word in all CAPS.

Non applicable fields will be consistently left blank or flagged as NA.

DESIRED DELIVERABLE: Centurylink will implement and enforce a procedure that creates a standardization that all CLECs will be able to rely on for easy reading or parsing of the notifications.


Status History


Project Meetings

10/17/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the final notification was sent on 9/7/12 with an effective date of 9/24/12. The CR is in CLEC Test. Mark said we would like to move the CR to Completed and asked if there were any questions. There were none.

09/19/12 Product/Process CMP Meeting Mark Coyne – CenturyLink said the level 4 initial notification was sent on 8/17/12 and the final notice was sent 9/7/12 with the planned effective date of 9/24/12; there were no CLEC comments. This CR would be revisited in October.

08/15/12 Product/Process CMP Meeting Mark Coyne - CenturyLink relayed that last month we said the initial notice was planned for early August with a planned effective date of 9/17/12. Mark said instead the initial notice will go out on 8/17/12 with a planned effective date of 9/24/12.

Kathy Ocken – CenturyLink relayed that downloads have been created for the Unbundled Local Loop - General Information and the Unbundled Local Loop - 2-Wire or 4-Wire Analog Loop PCATs to provide the agreed upon format and an example of the PTA notices.

Mark Coyne – CenturyLink asked if there were any questions. There were none.

07/18/2012 CMP Prod/Proc Meeting Mark Coyne - CenturyLink recapped the Change Request and asked Kathy Ocken from CenturyLink to provide an update on the request.

Kathy Ocken – CenturyLink stated that the planned implementation date is September 17, 2012. CenturyLink will be able to meet most of the line items in the request however some are still in development. One of the items, “each data field on its on line”, may be affected when text wrapping occurs in specific readers. All other requirements seem to be managed.

Kim Isaacs – Integra stated that Steph Prull was not able to join the call, but asked for confirmation on the wrapping issue.

Kathy Ocken – CenturyLink stated that Outlook seemed to be the email reader that most commonly wrapped text, but other readers seemed to not have that issue.

Liz Tierney – Megapath Inc. asked for clarification that the information was there and that it was simply formatting when received by the CLEC.

Kathy Ocken – CenturyLink stated that it seemed as if Outlook was not recognizing a “carriage return”.

Mark Coyne – CenturyLink stated that the Level 4 notification associated with this change would likely go out the early part of August for an effective date of September 17, 2012.

06/20/2012 CMP Prod/Proc Meeting Steph Prull – Integra presented the CR. Steph said PTA notices should have consistent information and be delimited in a way that could be parsed by other applications.

Mark Coyne – CenturyLink asked if there were any questions. There were none. He added that a clarification call was held June 11, 2012. CenturyLink is currently evaluating the CR.

06/11/12 Clarification Call Meeting Minutes Attendees: Steph Prull – Integra, Kim Isaacs – Integra, Laurie Roberson – Integra Kathy Ocken – CenturyLink, Ann Robberson – CenturyLink , Sue Leuschen - CenturyLink, Bob Mohr – CenturyLink, Mark Coyne -CenturyLink, John Hansen - CenturyLink, Susan Lorence - CenturyLink

Susan Lorence – CenturyLink took attendance and asked Steph Prull – Integra to give an overview of her Change Request (CR).

Steph Prull – Integra stated that Integra was looking for standardization of the PTA notifications sent from CenturyLink. Steph said important pieces of information that are needed in Integra systems are not always consistent or formatted in the same manner by CenturyLink. This change request asks for consistency and clarity with all notifications so that they will be easier to interpret.

Susan Lorence – CenturyLink stated that she would like to go over each point in the CR so that CenturyLink would have a clear understanding of what Integra was proposing. The first line stated standard format. Susan stated that they are currently sent via E-mail and asked for confirmation that Integra was not asking for delivery in a different format.

Steph Prull – Integra said yes. Since the form was not an industry standard, email was fine but it needed to be consistent.

Susan Lorence – CenturyLink asked for clarification regarding Integra’s request that this applies to “all PTA notices”, i.e., to which products they are referring.

Steph Prull – Integra stated DSL, Unbundled Loop, T-1 and any other products for which they receive a PTA notification.

Susan Lorence – CenturyLink said the CR requests that the notifications be delimited by a colon to allow parsing by other applications. She asked Kathy Ocken – CenturyLink if it was true that colon delimiters were used today.

Kathy Ocken – CenturyLink stated that was correct, that the colon separated the field name from the detail.

Steph Prull – Integra stated that Integra was fine with that but that they have found notices where that was not the case and that they wanted it consistent.

Susan Lorence – CenturyLink asked about the CR line requesting that the main data field name be consistent if applicable to all forms, e.g., PON and the CenturyLink order number. This is a request to standardize the name.

Steph Prull – Integra stated it did not necessarily matter what the field names were as long as they were consistent and said as an example that they may see all three CenturyLink company names today.

Susan Lorence – CenturyLink asked Steph to elaborate on the next part of the CR regarding that the field/data names that are applicable for the various forms should always be present and consistent.

Steph Prull – Integra said that every field should be included on a PTA notice. If there were twenty fields possible, Integra would like to see all twenty fields with each notice even if there is no data populated instead of missing fields if there is no data.

Kathy Ocken – CenturyLink asked if she were referring to the test results PTAs.

Steph Prull – Integra confirmed that it was the test results PTAs.

Sue Leuschen – CenturyLink asked if Integra wanted all fields provided even if there was no data associated with that field in a particular notification.

Steph Prull – Integra stated that she is requesting that the field be left blank or populated with “NA” on the fields that were not required and that she could send some examples if necessary. In some cases, the field is missing from the test results, or it would be blank or have “NA”. Steph said if all fields were present and populated in a consistent manner, it would be easier to interpret especially for people who are new to reading the results.

Susan Lorence – CenturyLink asked if Integra was looking for a single combined form or if they were looking for a standard per type of PTA?

Steph Prull – Integra confirmed that they are asking for a standard form per type of PTA; she said they are not looking for one form for everything. She said she is not particular whether it is blank or NA just that it is consistent.

Susan Lorence – CenturyLink asked for any clarification regarding the CR Description line that addressed content of the data being consistent across all service centers and users filling in the forms.

Steph Prull – Integra confirmed that those familiar with formatting could figure it out no matter how it was presented but those new to the industry had trouble if the formatting was inconsistent and how to enter it into their systems. She said they have seen that the same CenturyLink person may not be consistent.

Susan Lorence – CenturyLink asked for clarification regarding the CR Description that addressed subject lines of the emails.

Steph Prull – Integra stated that the subject lines are not consistent and that what she included were the most common set of information. They would like to see enough information to be able to determine where the notices should be sent internally in their company and that the subject be consistently formatted.

Susan Lorence – CenturyLink asked if these are the suggested fields and asked if Integra only wanted these fields.

Steph Prull – Integra confirmed that those are the only fields that Integra needs but that she is not against seeing more fields as long as CenturyLink lets them know. Her personal preference is that those three fields start the subject line and if additional information is included, any extra would be added to the end.

Susan Lorence – CenturyLink asked for clarification regarding the CR Description that addressed the header will always be consistent. Susan asked how CenturyLink would know what appropriate Integra name that Integra would want there?

Steph Prull – Integra stated that it was not clear how the data was populated, if it were table driven or hand typed. Steph said if the SMEs could educate Integra as to what was used to populate, CenturyLink and Integra could work together to determine how this was addressed as long as consistency is considered. She said this field was not as important as some of the others.

Susan Lorence – CenturyLink said it was good that Integra was open on this requirement since this might be difficult from a CLEC standpoint.

Steph Prull – Integra said it would help for them to know where the data was coming from, they may be able to better address it.

Susan Lorence – CenturyLink read the CR Description line requesting Yes/No Answers be consistently all caps.

Steph Prull – Integra said yes and that it would help when the data were to be parsed.

Susan Lorence – CenturyLink stated that the last point on the CR Decsription, blank or NA, had already been addressed.

Steph Prull – Integra agreed that one or the other would be fine as long as it were consistent.

Susan Lorence – CenturyLink asked if there were any other questions. There were none. Susan said it sounds like CenturyLink understands what Integra is asking and detailed investigation would ensue. If necessary, additional calls may be requested to cover any uncertainties or potential solutions that need to be presented.

The call was concluded at 9:22 AM MT.


Open Product/Process CR PC060812-1EX Detail

 
Title: Allow a CLEC to request conditioning/remove all conditioning on a single trouble report.
CR Number Current Status
Date
Area Impacted Products Impacted

PC060812-1EX Completed
10/17/2012
Maintenance and Repair Unbundled Loop
Originator: Isaacs, Kim
Originator Company Name: Integra
Owner: Mohr, Bob
Director:
CR PM: Lorence, Susan

Description Of Change

This change would allow CLECs to request “Conditioning and/or Remove All Conditionings” on a single trouble report which indicates that the CLEC is pre-authorizing both Conditioning/Remove All Conditioning on a single trouble report in the event that Conditioning does not bring the xDSL circuit into the performance parameters. Integra’s positions on the need to submit this change request are contain in CenturyLink change request PC072010-1ES Revised Change in Process for xDSL Capable Loops, e.g. Non-Loaded and ADSL Compatible Loops (aka xDSL Services). See: http://www.centurylink.com/wholesale/cmp/cr/CR_PC072010-1ES.html

Integra submitted this request as an exception because CenturyLink/Qwest has agreed to this approach and has already done ground work related to this request.

6/15/12 – REVISION: The Exception Process requested above is to implement conditioning/remove all conditioning on a single trouble report in Minnesota using a 31 day implementation schedule. Implementation of condition/remove all conditioning on a single trouble report in other 13 states will follow the CMP Document Level 4 Product/Process guidelines.

Expected Deliverables/Proposed Implementation Date: Qwest/CenturyLink will expeditiously implement a process that allows a CLEC to request condition/remove all conditioning on a single trouble report.


Status History


Project Meetings

10/17/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the Exception request specific to Minnesota went into effect on 8/6/12. The final notice for the remaining states was sent on 8/17/12 with phased effective dates starting 9/4/12 and ending 9/24/12. The CR is in CLEC Test. Mark said we would like to move the CR to Completed.

Kim Isaacs – Integra said that was fine.

09/19/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the Exception request specific to Minnesota went into effect on 8/6/12. For the remaining states, all remaining states are now in effect except for Idaho and Washington which will go into effect on 9/24/12. Mark said the CR will then be moved into CLEC Test. Mark asked if anyone has used the process and how the process is working to date?

There were no CLEC responses.

Mark Coyne- CenturyLink said it did not sound like it had been used.

08/15/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said the level 3 notice related to the Integra Exception request specific to Minnesota went into effect on 8/6/12. For the remaining states, the initial level 3 notice went out 7/23/12 that includes a phased implementation. He said the final notice will be sent 8/17/12 and it will show the phased effective dates starting 9/4/12 through 9/24/12 for the remaining states.

07/18/2012 CMP Prod/Proc Meeting Mark Coyne - CenturyLink recapped the Change Request and activities to date. The Level 3 notice was distributed on July 6, 2012 with an effective date of August 6, 2012. Mark asked Bob Mohr for an update.

Susan Lorence – CenturyLink stated that there was a document posted to the calendar that Bob will be speaking to.

Bob Mohr - CenturyLink indicated that the Minnesota implementation was scheduled for August 6, 2012. The SME team has completed the process and is in progress of training the Minnesota team. CenturyLink received comments from Integra on the Conditioning download and agrees to accept those changes. He stated that a new notice would be distributed on July 23, 2012 regarding implementation in the remaining states. The roll-out schedule is included in the document posted to the calendar.

07/02/12 Exception Vote Meeting Minutes Attendees: Laurie Roberson – Integra, Liz Tierney – Megapath, Al Finnell – Windstream, Joyce Bilow – Windstream, Bob Mohr – CenturyLink, Jamal Boudhaouia – CenturyLink, Mark Coyne – CenturyLink, Susan Lorence – CenturyLink Susan Lorence – CenturyLink opened the call and identified that for this second vote meeting for the exception portion of CR PC060812-1EX, it was not required to reach quorum on the call for the vote to be taken. Susan provided the background for the CR as available on the Status History for this CR on the Product Process Interactive report.

Susan Lorence – CenturyLink then asked Laurie Roberson – Integra if she had anything that she wanted to share in regard to this CR.

Laurie Roberson – Integra said no she did not.

Susan Lorence – CenturyLink read what a vote of “Yes” and “No” would mean in regard to this CR. She then asked each Company representative on the call to state their vote. Susan identified that CenturyLink had received two votes via email.

Each Voting Carrier and their vote is listed in the table below: Voting Carrier Voting Participant VOTE Integra Laurie Roberson (by phone) Yes MegaPath Liz Tierney (by phone) Yes Windstream Al Finnell (by phone) Yes CenturyLink Mark Coyne (by phone) Yes Velocity Jim Hickle (by email) Yes TDS Metro Rod Cox (by email) Yes

Susan Lorence – CenturyLink relayed that the Integra request for the exception was granted and shared the following planned timeline for Minnesota ONLY for a level 3 notice for the “change in process” to be sent with a 31 day timeline: o Level 3 notice announcement date: 7/6/12 o Formal CLEC comments cycle: 7/7/12 – 7/21/12 o Final notice and response to comments, if applicable: 7/22/12 NOTE: THIS NOTIFICATION WILL BE SENT ON SUNDAY which is normally not the case for notifications. o Effective date: 8/6/12

Laurie Roberson – Integra asked if CenturyLink would share the timeline for the remaining states in the July CMP meeting.

Susan Lorence – CenturyLink said yes; the SME team is currently determining the rollout schedule for the remaining states. Susan asked if there were any other questions. There were none.

The call ended at 11:10 AM MT.

06/27/12 Exception Vote Meeting Minutes Attendees: Kim Isaacs – Integra,Laurie Roberson – Integra, Jawaid Bazyar - FORETHOUGHT.net, Bob Mohr – CenturyLink, Jamal Boudhaouia – CenturyLink, Don DeLand – CenturyLink, Donovan Trevarrow – CenturyLink, Mark Nickell – CenturyLink, Mark Coyne – CenturyLink, Susan Lorence – CenturyLink Susan Lorence – CenturyLink opened the call and identified that for the CR exception vote to be taken, quorum had to be reached per Section 17.0 of the CMP document. Quorum for the call is eight. Susan identified that CenturyLink had received three votes via email that would provide for representation of six which would not reach quorum. Susan relayed that if the call needed to be rescheduled, the vote would be postponed for three business days and that for the second exception call, the vote will be taken regardless of whether quorum was established. Susan said that the call-in Bridge would remain open for ten minutes to allow other attendees to join the call; ten minutes is the normal window for walkthroughs. Susan asked call participants if that was an appropriate timeframe.

Kim Isaacs – Integra agreed.

By 10 minutes after the call had started, no other attendees joined the bridge.

Susan Lorence – CenturyLink read the specific wording from Section 17.4.1 in regard to the process when quorum is not reached and said she would reschedule the call for Monday, July 2. Susan asked Integra for the best times for the call to be scheduled based on their calendar.

Kim Isaacs – Integra said she would be out of the office on that day but said that Laurie Roberson – Integra would be available on Monday.

Susan Lorence – CenturyLink said she would schedule a second Exception Vote call for Monday and would send out a notification to inform CLECs that a vote had not been taken; customers who had sent in email votes would also be informed no vote had been taken. Susan relayed that assuming that the exception is approved on Monday, the CenturyLink SME team had come up with the following tentative timeline for Minnesota ONLY for a level 3 notice for the “change in process” to be sent with a 31 day timeline: o Level 3 notice announcement date: 7/6/12 o Formal CLEC comments cycle: 7/7/12 – 7/21/12 o Final notice and response to comments if applicable: 7/22/12 NOTE: THIS NOTIFICATION WILL BE SENT ON SUNDAY which is normally not the case for notifications. o Effective date: 8/6/12 Susan Lorence – CenturyLink also relayed that during the July 18 CMP meeting, CenturyLink would provide the planned implementation timeline for the remaining states. Susan asked if there were any questions. There were none. The call ended at 10:45 AM MT.

06/20/2012 CMP Prod/Proc Meeting Kim Isaacs – Integra presented the CR that was also submitted as an exception request. The CR has since been revised to ask for a 31-day implementation in Minnesota only with the other states to follow the CMP Level 4 Product/Process procedures.

Mark Coyne – CenturyLink added that an exception pre-meeting was held June 13, 2012. CenturyLink has revised the CR to capture Kim’s changes. An exception vote meeting is scheduled for June 27, 2012. Mark relayed that the notice and voting specifics are posted to the wholesale calendar for that date. Some email votes have already been received. CenturyLink SMEs are working to develop the process.

Bonnie Johnson – Minnesota Department of Commerce asked if it would be implemented in Minnesota 31 days from the vote or on what date the 31 day clock would start.

Mark Coyne – CenturyLink responded that, depending on the outcome of the vote, CenturyLink would see how quickly it could be implemented.

06/13/12 Clarification Call and Pre-Meeting Exception Call Meeting Minutes Attendees: Kim Isaacs – Integra, Laurie Roberson – Integra, Al Finnell – Windstream, Joyce Bilow – McLeod dba Windstream, Jim Hickle – Velocity, Emily Davis – Midcontinent Communications, Chris Viveros – CenturyLink, Jill Seals – CenturyLink , Lucy Davis – CenturyLink, Jamal Boudhaouia – CenturyLink, Bob Mohr – CenturyLink, Mark Coyne – CenturyLink, John Hansen – CenturyLink, Susan Lorence – CenturyLink

Susan Lorence – CenturyLink took attendance and explained the reason for the call. Susan said two things were key to address in the pre-meeting: clarify the CR and develop a clear statement of what the exception vote of “yes” and “no” means. Susan asked Kim Isaacs – Integra to give an overview of her Change Request (CR). Kim Isaacs – Integra said that the CR requests that CenturyLink expeditiously implement a process that allows a CLEC to request conditioning/remove all conditioning on a single trouble report. Kim said this would be similar to the provisioning process and that she believes the xDSL amendment allows the ability to request this. Integra said the exception is to implement this as soon as possible. Jamal Boudhaouia – CenturyLink asked for clarification based on discussions in the Minnesota 1066 Docket. Jamal said that the (6/20/12 Updates received from Integra in CAPS) [delete EXPEDITED] process would be specific to Minnesota.

Kim Isaacs – Integra asked about the other states.

Jamal Boudhaouia – CenturyLink said CenturyLink is not saying “no” to the other states but until the impact is known, it would be Minnesota only.

Kim Isaacs – Integra asked if another CR would be required for the other states or would the process be phased similar to the original xDSL process.

Jamal Boudhaouia – CenturyLink said the original CR was phased but that CenturyLink is still evaluating this process change. Jamal said CenturyLink is focusing on Minnesota and evaluating the need for an amendment in the other states. Kim Isaacs – Integra said that Integra disagrees with the CenturyLink position. Integra believes the current amendment allows conditioning/remove all on a single ticket.

Jamal Boudhaouia – CenturyLink says CenturyLink understands the Integra position.

Kim Isaacs – Integra asked if there was commitment for the other thirteen states.

Jamal Boudhaouia – CenturyLink said at this point there is not commitment but that CenturyLink may be looking at a phased approach at a later time but that we need to determine the impact to the Network organization.

Kim Isaacs – Integra said CenturyLink should have a good idea of the impact on repair based on the current process for installation. Kim said the data is available on how often conditioning/remove all is requested on LSRs and that CenturyLink could make some assumptions.

Jamal Boudhaouia – CenturyLink said the processes and organizations are different between provisioning and repair.

Chris Viveros – CenturyLink said it was not clear on the point that the LSR provisioning data would be used to estimate the impact to repair on a working circuit.

Kim Isaacs – Integra said she does not think there is high volume on installation where there has been conditioning and then CenturyLink has had to do “remove all”. She said needing both conditioning/remove all on installation is higher than on an existing circuit. Kim said if the volume is not high on installation, it will not be high on repair.

Chris Viveros – CenturyLink said CenturyLink was not implying that the volume would be overwhelming. He said the impact is more than quantity, it is the foreignness of the process. Chris said conditioning is part of provisioning and the issue is how to insert a provisioning step in the repair flow. He said we have allowed conditioning on repair but now the requirement is to determine the type of conditioning necessary. Chris said he understood the Integra exception request to implement more quickly in Minnesota since there were negotiations there.

Kim Isaacs – Integra said she thought CenturyLink the repair centers were the same in all states and no center was Minnesota only. Kim said she thought not including all states vs. just doing the process in Minnesota would be more difficult. Kim said the techs are currently doing the steps on two separate tickets and she did not understand why one ticket was more impacting.

Jamal Boudhaouia – CenturyLink said if it only impacts the center, that would be true. Jamal said the center has to send the request to the outside field. He said the provisioning process is totally different than conditioning, the technicians are different. Jamal said CenturyLink needs to understand the impact to the outside forces. It is much more involved work during the repair process than provisioning and different steps and resources are involved. . Kim Isaacs – Integra (6/20/12 Updates received from Integra in CAPS) [delete ASKED IF] QUESTIONED WHY combining the conditioning and remove all on a single ticket would cause the outside field techs too much confusion.

Jamal Boudhaouia – CenturyLink said it is not confusion but identifying what process to follow. It is combining two processes – conditioning and remove all and doing that effectively in repair.

Kim Isaacs – Integra said she was very disappointed.

Jamal Boudhaouia – CenturyLink said it was noted.

Kim Isaacs – Integra asked if Integra could get a commitment to start with Minnesota and then expeditiously phase the process in within the other states.

Jamal Boudhaouia – CenturyLink said he cannot commit to that today.

Jim Hickle - Velocity asked what could be committed to and over what timeframe. He asked what the normal implementation timeline was across the fourteen states.

Jamal Boudhaouia – CenturyLink said he could not commit to anything but would take it back.

Chris Viveros – CenturyLink said it depends on what is being implemented.

Jim Hickle - Velocity said he thought that CenturyLink had a normal implementation timeline for fourteen states and that it was frustrating for it to take this long to make a decision. He said it should be acceptable to both sides to say, barring unforeseen problems, the process could be implemented in six months. Susan Lorence – CenturyLink said she wanted to get back to the CMP process for this CR. Jim Hickle – Velocity said that getting to a timeline for implementation was within the realm of the CR.

Susan Lorence – CenturyLink recapped that CenturyLInk was looking at Minnesota for the exception and that CenturyLink is considering the impact to the other states. Susan asked if everyone understood what (6/20/12 Updates received from Integra in CAPS) [delete THE CR WAS ACTUALLY] CENTURYLINK IS asking for.

Kim Isaacs – Integra said yes.

Susan Lorence – CenturyLink explained the normal level 4 CR timeline and said the CR was asking for CenturyLink to expeditiously handle the state of Minnesota. She asked once the process for Minnesota was identified, would a 21 day implementation timeline be appropriate and then a normal phased implementation timeline would be used for the other states? Susan said we needed something to be defined as the exception to the CMP process.

Kim Isaacs – Integra said she thought that the exception request would be to have Minnesota implemented on a 21 day cycle and then the remainder of the states implemented on a phased approach.

Susan Lorence – CenturyLink asked Kim to send in a revision to the CR to make that specific as part of the CR exception request.

Kim Isaacs – Integra said she would take that back.

Susan Lorence – CenturyLink said from a CMP perspective, we need a clear understanding of what is being requested for the exception vote to occur. She said we do have a clear understanding of the process change that the CR is requesting. Regarding the actual exception vote, Susan said per Section 16.3 of the CMP document, if the vote was to occur in the June monthly CMP meeting, the CR would have had to have been received 13 days prior to the CMP meeting. Susan proposed that the CR be presented in the June meeting and that the exception vote be taken five business days later on June 27.

Susan Lorence – CenturyLink asked if there were any other questions on the CR or on the exception request. There were none. Susan said CenturyLink would wait to hear back from Kim on submitting the update to the CR that specifies the actual exception for the CR.

Kim Isaacs – Integra said correct.

Susan Lorence – CenturyLink asked if there were any other points to discuss before the call was ended. There were none.

The call was concluded at 9:30 AM MT.


Open Product/Process CR PC072905-1 Detail

 
Title: Title Revision 08/10/2005: Delivery Interval for UBL ADSL and for 2 Wire Non Loaded UBL (Orig Title:Delivery Interval for ADSL and xDSL Capable Loops)
CR Number Current Status
Date
Area Impacted Products Impacted

PC072905-1 Completed
2/16/2006
Provisioning UBL ADSL, 2-wire non-loaded UBL
Originator: Worthen, Brian
Originator Company Name: InTTec, Inc.
Owner: Buckmaster, Cindy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Qwest’s retail DSL product (line-share and Standalone) now have delivery times of 3 business days. It would be appropriate for ADSL and xDSL capable loops used by CLECs for DSL delivery to have the same Service Delivery Interval.

Expected Deliverable:

11/1/05


Status History

07/29/2005 - CR Submitted

08/01/2005 - CR Acknowledged

08/01/2005 - Email Sent to InTTec, Requesting Clarification Meeting Availablility

08/10/2005 - Clarification Meeting Held

08/17/2005 - Discussed in the Monthly Product Process CMP Meeting

09/21/2005 - Discussed in the Monthly Product Process CMP Meeting

10/19/2005 - Discussed in the Monthly Product Process CMP Meeting

11/16/2005 - Discussed in the Monthly Product Process CMP Meeting

12/14/2005 - Discussed in the Monthly Product Process CMP Meeting

01/09/2006 - PROS.01.09.06.F.03565.Interconn_SIG_V60 (Level 2)

01/18/2006 - Discussed in the Monthly Product Process CMP Meeting

01/30/2006 - Status Changed to CLEC Test Due to January 30, 2006 Implementation

02/15/2006 - Discussed in the Monthly Product Process CMP Meeting

02/16/2006 - Status Changed to Completed With the Concurrence of the CR Originator (via email)


Project Meetings

February 16, 2006 Email Sent to InTTec: Brian, It sounds like you are okay to close the CR. That will complete it out. Thanks much!

-- February 16, 2006 Email Received From InTTec: Peggy, Great! Thank you so much. This completes our transaction, I believe. Brian Worthen InTTec Inc

February 16, 2006 Email Sent to InTTec: Brian, Your request was implemented on January 30th. I have attached a copy of the Level 2 Notice that was sent on January 9th, which has additional information. Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

- February 15, 2006 Email Received From InTTec: Peggy, Not sure I understand. Does that mean the 3 day delivery interval was implemented? Brian Worthen InTTec Inc

- February 15, 2006 Email Sent to InTTec: Good Afternoon Brian, This email is in regard to the CMP CR that you submitted, PC072905-1 Delivery Interval for UBL ADSL and for 2-Wire Non-Loaded UBL. This CR was implemented on January 30, 2006. The CLEC Community had no objection to the closure of this CR, during this morning’s Monthly CMP Meeting and I now need to see if you also agree that this CR can be closed. Will you please respond to this email and let me know if this CR can be closed. If there is an issue that is preventing your concurrence to closing this CR, please provide me with details and I will see what I can do to help with the resolution of any issues. Thanks much, Peggy Esquibel-Reed Qwest Wholesale CMP

-- February 15, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that this CR was implemented on January 30th and that Qwest would work to close the CR off-line, with the CR originator. Jill then asked if there was any objection to closure. There was no objection.

January 18, 2006 Monthly Product Process CMP Meeting Discussion: Jill Martain-Qwest stated that the Level 2 Notice was out on January 9th with a targeted date of January 30th. Jill then noted that this CR would move to CLEC Test on January 30, 2006.

- December 14, 2005 Monthly Product Process CMP Meeting Discussion: Jill Martain/Qwest stated that this CR is on target for January 28th deployment. This CR remains in Development Status.

-- November 16, 2005 Monthly Product Process CMP Meeting Discussion: Deb Smith/Qwest stated that the targeted effective date for this change is early February because of coordination that is needed with back-end systems. Deb then noted that the notice would be sent around the 2nd week of January. This CR remains in Development Status.

-- October 19, 2005 Monthly Product Process CMP Meeting Discussion: Deb Smith/Qwest stated that Qwest has completed the research for this CR and is accepting this CR. Deb noted that details are being finalized, along with the implementation date, and more information would be provided in the November CMP Meeting. Jill Martain/Qwest noted that back-end system changes are needed for this CR as well and noted that this CR is in Development Status.

-- September 21, 2005 Monthly Product Process CMP Meeting Discussion: Deb Smith/Qwest stated that Qwest would like to move this CR to Evaluation status in order to continue with the analysis to reduce the interval to 3 business days. There were no comments or questions. This CR moves to Evaluation Status.

- September 1, 2005 Ad Hoc Call ATTENDEES: Heidi Moreland-Qwest Deb Smith-Qwest Alan Breager-Qwest Shirley Tallman-Qwest Brian Worthen-InTTec Inc. Jo Wees-Qwest Kathy Ocken-Qwest Gary Stacy-Qwest Cindy Harlan-Qwest

Cindy Harlan-Qwest reviewed the CR and the purpose of this call. Cindy advised that Qwest has begun reviewing this request and that we have a few additional questions.

Deb Smith-Qwest advised that we have a Quick Loop process already available for 2/4 wire UBL non loaded. Deb directed the team to the PCAT where this process is documented. Deb explained some of the specific requirements that would allow your request to qualify as a Quick Loop. The work could not require a dispatch out to the end user location. It does not include conditioning. It would include only central office activities.

Brian Worthen-InTTec asked about a new loop order. Brian said that sometimes there is a Qwest TN at the premise, but his order is a new order.

The team reviewed the PCAT, Tech Pub, SIG, and discussed the different NC/NCI combinations, and the different LSR activity types that are valid for Quick Loop. Jo Wees-Qwest explained if an order comes in trying to order something that is not eligible for Quick Loop, IMA would not allow the Quick Loop due date.

Brian confirmed that he is looking for the same interval on new orders, not on conversions, as he does very few conversions. Deb advised that the Quick Loop Process does not apply to new orders. Deb thanked Brian for the clarification and advised that we have the additional information that we needed, so we will continue to review this request.

Cindy confirmed that we will provide Qwest’s response and additional status at the September CMP meeting.

August 30, 2005 Email Sent to InTTec: Good Morning Brian, This email is a follow-up to the voicemail message that I left for you late last week. We would like to have another discussion with you regarding your submitted CMP CR, PC072905-1 Delivery Interval for UBL ADSL and for 2-Wire Non-Loaded UBL. Will you let me know when you are available to talk with us? Several dates and times would be great. As soon as I receive your availability, I will schedule the call and send you the call-in information. Thanks much, Peggy Esquibel-Reed Qwest Wholesale Change Management

- August 25, 2005 Voicemail Left for InTTec, requesting a meeting to discuss this CR.

- August 17, 2005 Monthly Product Process CMP Meeting discussion: Peggy Esquibel Reed-Qwest read the CR Description. [Comment received from Eschelon: Peggy said the title was revised to delivery of Q DSL in 3 days.] Jill Martain-Qwest stated that this CR moves to presented status.

August 10, 2005 Clarification Meeting Minutes Attendees: Brian Worthen-InTTec, Peggy Esquibel Reed-Qwest, Deb Smith-Qwest, Kathryn Ocken-Qwest, Heidi Moreland-Qwest, Jo Wees-Qwest

Peggy Esquibel Reed-Qwest reviewed the CRs Description and asked InTTec if they had additional information to provide. Brian Worthen-InTTec stated that there was no additional information. Peggy Esquibel Reed-Qwest casked to onfirm that the impact was to Provisioning for UBL ADSL and xDSL. Brian Worthen-InTTec stated it is for what is in the SGAT, Exhibit A. The USOCs are U23WX and UY2FX Qwest noted that UY2FX is for 2-wire non-loaded loop and not for xDSL, and asked for clarification of the USOCs/Products. It was asked for confirmation that this request is for U23WX = 2-wire non-loaded UBL, and UY2FX = ADSL UBL Brian Worthen-InTTec said yes. Brian Worthen-InTTec stated that currently these products have a 5 business day interval and that Retail's interval is currently a 3-day delivery. There were no additional questions or comments. Peggy Esquibel Reed-Qwest stated that InTTec is scheduled to present this CR to the CLEC Community at the August 17th CMP Meeting and that Qwest's response/status is due in mid-September


CenturyLink Response

October 10, 2005

Revised Response For Review by the CLEC Community and Discussion at the October 19, 2005 Product Process CMP Meeting

TO: Brian Worthen InTTec, Inc.

SUBJECT: CR # PC072905-1 Delivery Interval for UBL ADSL and for 2-Wire Non-Loaded UBL

Qwest has completed the analysis for this Change Request and will accept this request. Specific details are being finalized, along with the implementation date.

Qwest would like to move this CR to Development status and will provide additional details in the November CMP Meeting.

Sincerely, Qwest

September 13, 2005

For Review by the CLEC Community and Discussion at the September 21, 2005 Product Process CMP Meeting

TO: Brian Worthen InTTec, Inc.

SUBJECT: CR # PC072905-1 Delivery Interval for UBL ADSL and for 2-Wire Non-Loaded UBL

This letter is in response to the Change Request submitted by InTTec, Inc., PC0729505-1 (Delivery Interval for UBL ADSL and for 2-Wire Non-Loaded UBL). This CR requests an interval of 3 business days for UBL ADSL and for 2-wire Non-Loaded UBL.

A clarification call was held on August 10, 2005, and a revision to the CR was then received on August 10th. Internal calls were held in order to discuss this request and another call was requested with the CR originator. Another call then occurred on September 1st, for education purposes and for further clarification of this request. Clarification was obtained that InTTec is looking for the same interval for new orders, not on conversion orders.

Qwest would like to place this CR in evaluation status in order to continue with analysis of this request. Qwest will provide an updated response at the next CMP meeting. Sincerely, Qwest


Open Product/Process CR PC060514-1 Detail

 
Title: CLLI Change Order Process Requested
CR Number Current Status
Date
Area Impacted Products Impacted

PC060514-1 Denied
10/15/2014
Ethernet / MOE Orders
Originator: Mereau , Matt
Originator Company Name: Level 3
Owner: Morrell, Diane
Director:
CR PM: Lorence, Susan

Description Of Change

Today if an Ethernet order were to follow a flow through order process with CenturyLink and an incorrect CLLI or Switch were assigned where a customer could not access, By current process CenturyLink requires Level3 to submit a new Install/Disco order to get the order assigned to a new switch. Ideally we should not have to submit any new orders as this is essential a CenturyLink mistake. In summary if CenturyLink is not able to provide a quick resolution where they assign incorrect CLLI’s we would at minimal like to be able to submit a change order instead of install/disco with standard sla.

Expected Deliverables/Proposed Implementation Date: ASAP


Status History


Project Meetings

11/19/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said he was going to provide a status on this CR even though it is not included in the package this month. Mark said we heard back from Matt Mereau – Level 3 and Matt had no issues with us closing this CR in a Denied status as being economically not feasible due to the low volume. Mark said the CenturyLink response indicated that the SME team had reviewed the Level 3 PONs and provided feedback on each of them. Mark said CenturyLink had also identified that going forward, internal steps had been invoked to insure adherence to the stated process.

10/15/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said the CenturyLink SME team investigated the five PONs from Level 3 that were examples of the reason this CR was submitted. That information was sent to Matt Mereau - Level 3 in early September. Matt requested a call to better understand the information. On September 18, a call was held with Service Management and the SME team to review each PON. Matt said he would look for additional PONs but also said the conditions surrounding this CR do not appear to be as significant as originally thought. Mark said a draft response was sent to Matt that denies this CR as being economically not feasible due to low volume. Mark relayed CenturyLink also implemented steps to insure process adherence as indicated in the draft CenturyLink response included in the package. CenturyLink will follow-up with Matt to see if there are any questions about the denial.

9/17/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was submitted by Level 3 and was presented in the August monthly meeting. The Clarification call had been held on June 12. The CenturyLink SME team investigated the five PONs from Level 3 where this scenario was thought to be a problem. CenturyLink sent an email to Matt Mereau – Level 3of the specifics of the PON investigation. Follow-up with Matt resulted in a request to meet with the CenturyLink Service Manager and the SME team on 9/18/14 to review the specific situation of each PON. In the August monthly CMP call, Matt said he thought he had another PON occurrence which is still pending. Mark said depending on the result of the SME team and Service management team discussion, we may have a process clarification to make in the CenturyLink documentation.

8/20/14 Product/Process CMP Meeting Mark Coyne – CenturyLink introduced the CR that was submitted by Level 3 and said the Clarification call had been held on June 12.

Matt Mereau – Level 3 then presented the CR. Matt said that at times during CenturyLink Flow through, the incorrect CLLI may get assigned which then prevents their customers from access where the circuit is dropped. When that happens, the CenturyLink resolution is for a disconnect and new connect to be submitted causing a delay in delivery to the end user when the timeline starts over again. Matt said he is asking for a Change order process to shorten the delivery time. He said volume is not high but the current process impacts customer satisfaction.

Tracy Strombotne – CenturyLink asked what the volume of this is.

Mark Coyne – CenturyLink said that based on the Clarification call, it was shared the volume was not high. Mark said the SME team investigated five examples of PONs that MM submitted. Mark said the SME team is still investigating these but it appears three of the five examples were related to inside wiring and the other two were related to CenturyLink installing to a dedicated vs. a shared site. For those related to inside wire, a PCAT update may be required or an internal process update. The SME team will be responding to Level 3 on the specifics of these soon. A draft CR response should be available for the September meeting.

Matt Mereau – Level 3 said he agrees the volume is relative low but he had another one that came to his attention. Matt said he would submit the PON to the CMPCR mailbox for further investigation by CenturyLink.

Kim Isaacs – Integra said if an error has been made by CenturyLink, it was not right for CenturyLink to apply a standard interval to the corrective orders and follow a normal flow.

Mark Coyne – CenturyLink said CenturyLink would take that into account.

7/16/14 Product/Process CMP Meeting Mark Coyne – CenturyLink asked if anyone from Level 3 had joined the call. This CR is a carryover from the June CMP meeting. The Clarification call was held on June 12. The CenturyLink SME team is investigating five examples of the PONs where this has been a problem. The CR will hopefully be presented in the August CMP meeting.

6/18/14 Product/Process CMP Meeting Mark Coyne – CenturyLink said this was a new CR from Level 3 but the originator Matt Mereau was not able to be on the call today so the CR will be officially presented in the July CMP meeting. Mark said the Clarification call was held on June 12 and that during the call, CenturyLink requested information as to frequently this occurred and requested examples. The CR originator said he thought he had about six or so occurrences of this situation since the first of the year and would send those PONs. Mark said CenturyLink had received five PONS and that the CenturyLink SME team was reviewing the service requests.

6/12/14 CMP Clarification Meeting Attendees: Matt Mereau – Level 3 Laurie Roberson – Integra Paul Schlachter – CenturyLink Pat Bratetic – CenturyLink Mark Coyne – CenturyLink John Hansen – CenturyLink Susan Lorence – CenturyLink

Susan Lorence – CenturyLink opened the call and recapped the purpose of the clarification call. She relayed that the CR had originally been requested as an Exception CR but that after discussion with Matt Mereau – Level 3 as to what that meant per CMP, it was determined that it would follow the normal CMP CR process.

Matt Mereau – Level 3 then presented the new CR. Matt said occasionally Level 3 receives an escalation where the incorrect CLLI or Switch is assigned to the order and that it is not determined until the service is delivered to their customer. It then becomes an escalation to try to get the situation quickly resolved. The current process requires a disconnect and a new install order to resolve. Matt said he was told by his CenturyLink Service Manager Scott Ellefson that the problem is because the order follows a flow through process and that when the switch is assigned, it is not known that the switch assigned could not be accessed until the technician arrives. Matt asked if CenturyLink has seen this situation before.

Paul Schlachter – CenturyLink said CenturyLink is aware of the situation and that was a good description.

Matt Mereau – Level 3 said he is hoping to establish a process to correct the problem more quickly.

Paul Schlachter – CenturyLink asked whether Level 3 knew the volume of occurrences and could provide some examples.

Matt Mereau – Level 3 said he could provide examples. The current volume is not huge. Matt said there may have been 6 in the last year but it causes the Level 3 customers to have a bad experience which needs to change.

Paul Schlachter – CenturyLink asked if Level 3 is testing during “test and turn up” or whether Level 3 is waiting until equipment is placed.

Matt Mereau – Level 3 said they are waiting until the vendor completes the installation and cannot get to the location.

Paul Schlachter – CenturyLink said that sounds like it might be a different scenario in that the order was assigned to a dedicated closet.

Matt Mereau – Level 3 said he is getting his information from Scott Ellefson and that maybe he is getting the scenarios mixed up. He said the issue is that Level 3 cannot get to equipment because it is in a lock down closet for another customer.

Paul Schlachter – CenturyLink said that was why the examples will be good to figure out the scenario(s).

Matt Mereau – Level 3 said he can provide the examples and asked if PONs are required.

Paul Schlachter – CenturyLink said yes and to send them to the CMPCR mailbox.

Laurie Roberson – Integra asked if the desired switch that Level 3 wants is on the original order.

Matt Mereau – Level 3 said he thinks it is assigned by CenturyLink flow through.

Paul Schlachter – CenturyLink said the customer provides the actual address and a flow through CLLI. He has seen a couple instances where there is only one device in a location and it is not that the CLLI is incorrect but it cannot be connected to, like a locked closet.

Laurie Roberson – Integra asked what happens if a new order is written, why does the problem not reoccur.

Paul Schlachter – CenturyLink he needs to see the examples to see what the situation is, if the device was placed at wrong location, or if customer was expecting a certain floor and CenturyLink used an existing device rather than place a new device.

Laurie Roberson – Integra said if the order has a specific suite, CenturyLink may use a device that does not serve the suite.

Matt Mereau – Level 3 said like a common room.

Paul Schlachter – CenturyLink said that was correct, CenturyLink would connect to the demarc point. If inside wire was required to connect, it is up to the technician to determine depending on the distance.

Laurie Roberson – Integra asked if a CenturyLink tech is dispatched on these, how does a CenturyLink tech get access and install to a private location not owned by that customer.

Paul Schlachter – CenturyLink said that was why he needed to see the examples to see the scenario and to figure out why a disconnect and install was said to be the solution.

Laurie Roberson – Integra said she knows Ethernet is more complicated but if this happens on DS0, it goes to Repair to correct. She said a disconnect/install seems harsh.

Paul Schlachter – CenturyLink said from the CR Description, it seemed the situation was an incorrect CLLI but it sounds like it may be an incorrect device.

Matt Mereau – Level 3 said he understood the problem was caused because of flow through based on the address and that a site survey does not occur prior because the address implies the building is lit.

Paul Schlachter – CenturyLink said that was correct. Based on the address and what is in the building, CenturyLink tries to use an existing CLLI to go flow through so AQCB is not used to build new.

Matt Mereau – Level 3 said it would take a couple days to identify some PONs and he would try to provide a variety but he felt the discussion summed up the situation. He said you can imagine what happens with customer satisfaction when a customer’s interval goes from 30 or 60 days to 120.

Susan Lorence – CenturyLink said the SME team will look at the examples and that we may need to reconvene to review options – possibly other than the disconnect/reconnect identified on the CR.

Matt Mereau – Level 3 said that sounds like a good plan.

Susan Lorence – CenturyLink reviewed the next steps: the examples would be provided to the CMP CR mailbox, the CR would be presented by Matt at the monthly CMP meeting on Wednesday, June 18, 2014 at 9 AM MT, participating CLECs would have the opportunity to ask questions, and then the SME team will evaluate the examples to determine next steps. Susan said a CR can be accepted or denied based on Section 5.3 of the CMP document. She said she would post the meeting minutes to the Wholesale calendar and any updates that may be required can be sent back to the CMPCR mailbox. Susan asked if there were any other questions. There were none.

The clarification call concluded at 2:25 PM MT.


CenturyLink Response

October 9, 2014

Matt Mereau – Level 3

This letter is in response to Level 3 Change Request PC060514-1, entitled “CLLI Change Order Process Requested”.

CR Description: Today if an Ethernet order were to follow a flow through order process with CenturyLink and an incorrect CLLI or Switch were assigned where a customer could not access, by current process CenturyLink requires Level 3 to submit a new Install/Disco order to get the order assigned to a new switch. Ideally we should not have to submit any new orders as this is essential a CenturyLink mistake. In summary, if CenturyLink is not able to provide a quick resolution where they assign incorrect CLLI’s, we would at minimal like to be able to submit a change order instead of install/disco with standard sla. The requested implementation date for this functionality is as soon as possible. History: This Change Request was received on June 5, 2014. A Clarification call was held on June 12, 2014 with Level 3, Integra and CenturyLink representatives present. During the Clarification call, Matt Mereau, Level 3, agreed to provide some examples of the order scenario for CenturyLink SMEs to investigate. Matt provided five PONs on June 13, 2014.

Due to scheduling conflicts, the CR was not presented by Matt Mereau, Level 3, until the August 20, 2014 monthly Product Process CMP meeting.

On September 4, 2014, an email was sent to Level 3 that provided the details of the investigation of the five PONs by the CenturyLink SME team. Further follow-up with Level 3 resulted in the establishment of a call between Level 3 and CenturyLink SMEs and Service Management to review the information. That call occurred on September 18, 2014. Following the call, Matt Mereau, Level 3, planned to get with his Provisioning team and also do some research to see if there were other PONs that were this scenario. The plan was to send that data to CenturyLink by October 6. No additional data is available at this time.

CenturyLink Response: As a result of the CenturyLink investigation of the five Level 3 PONs associated with this CR and discussion with Level 3 on the September 18, 2014 call that included the CenturyLink SME team and Service Management, Level 3 identified that the conditions surrounding this CR do not appear to be as significant as originally thought. The CenturyLink SME team had identified that four of the five PONs investigated were related to device issues and only one of those four PONs resulted in the need to issue a disconnect and new connect to ensure both the CenturyLink and the customer inventories were kept in sync. The remaining PON was waiting on a related ASR. CenturyLink relayed that, as always, any CenturyLink inventory issues are being addressed as they come to light.

Based on the low volume of this scenario and the estimated very high cost to implement a technical solution to allow a change order to correct an inventory problem instead of requiring a disconnect and install order, CenturyLink is denying this CR due to being economically not feasible.

To ensure process adherence in the CenturyLink Centers on how to handle this order scenario, as of September 2014, the CenturyLink internal process for correcting a device assignment was clarified and reviewed with the Center personnel. For those order scenarios that require a disconnect/add, CenturyLink relayed that no one-time charges will be accessed to the customer, termination liability will not be impacted and an expedited Due Date (DD) can be requested by the customer at no charge.

Sincerely,

Susan Lorence CenturyLink Wholesale CR Project Manager


Open Product/Process CR PC072303-2 Detail

 
Title: Add circuit numbers on invoices for ITP DSO Physical Co lo
CR Number Current Status
Date
Area Impacted Products Impacted

PC072303-2 Withdrawn
8/20/2003
Billing
Originator: Yedersberger, Bernie
Originator Company Name: LTDS
Owner: Harlan, Cindy
Director:
CR PM: Harlan, Cindy

Description Of Change

On Account No. 319 Z01-2842 039 I would like to have the circuiti numbers added to "summary of accounts"

Expected Deliverable

Please add circuit numbers to Account No. 319 Z01-2842 039 on August 1, 2003 invoice


Status History

07/23/03 - CR Submitted

07/24/03 - CR Acknowledged

7/28/03 - Contacted customer

8/4/03 - Held clarification call and changed status to pending withdrawl

8/20/03 - CMP meeting - see meeting notes


Project Meetings

August 20 CMP Meeting: Cindy Macy-Qwest explained the CLEC issued this CR but she really just had a question to ask. She was not familiar with the CMP process. Crystal Soderlund was able to answer her questions and she requested the CR be withdrawn. The CLECs agreed it was okay to withdraw this CR.

Clarification Meeting

August 4, 2003 1-877-572-8687 3393947# PC072303-2 Add circuit numbers on invoices for ITP DS0 Physical Co-Lo

Attendees Bernie Yedersberger – LTDS Carl Sear – Qwest Lillian Robertson – Qwest Janet Leonard – Qwest Crystal Soderlund – Qwest Cindy Macy - Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees introduced. Cindy Macy – Qwest reviewed the CMP process and next steps so the team is aware of what to expect.

2.0 Review Requested (Description of) Change Cindy Macy – Qwest introduced Bernie and explained she is the Accounts Payable person for LTDS. Bernie is trying to match the Qwest bill charges to their end user accounts so they can bill appropriately. Bernie explained they have service on 319-Z01-3191 161 which is an ADSL Qualified Loop. This bill shows the circuit numbers so she can match this to her end user account. Bernie wanted to know if we could put the circuit number on her 319-Z01-2842 039 Line Share account. Crystal Soderlund – Qwest explained the ADSL Qualified Loop account is a design service and those types of accounts have a circuit number. The Line share account is a POTS account and those accounts have telephone numbers. Crystal pointed on the bill where to find the WTN and explained how this number could be used to match to your end user account. Bernie thanked Crystal and explained she would like to withdraw this CR as she really just had a question to ask, and did not intend to submit a CR and follow the CMP process. Cindy Macy – Qwest agreed she would present this CR at the August CMP meeting and mark the CR as pending withdraw.

3.0 Confirm Areas & Products Impacted ADSL / Line Sharing

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation The CLECs question was answered and this CR will be marked as pending withdraw until the August CMP meeting.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) Cindy Macy – Qwest will present the CR and request to withdraw the CR at the August CMP meeting.


Open Product/Process CR PC073003-1 Detail

 
Title: Qwest to provide test plans and results prior to deployment of IMA
CR Number Current Status
Date
Area Impacted Products Impacted

PC073003-1 Crossover
7/27/2009
Preordering & Ordering
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Gallegos, John
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

CLECs currently have no insight to Qwest IMA test plans or results. MCI

requests review of the test plan and results prior to IMA deployment.

Expected Deliverable:

That Qwest provide in advance of deployment IMA test plans and results.


Status History

07/30/03 - CR Submitted

08/01/03 - CR Acknowledged

08/11/03 - Held Clarification Meeting

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/22/03 - CR crossed over to Systems SCR073003-01X


Project Meetings

12/17/03 December CMP Meeting Connie Winston with Qwest said that the LOE has been completed and would like to cross this over to Systems. MCI has requested more details factoring into the LOE. This CR will be crossed over to Systems.

Thu 12/11/03 4:50 PM From: Elizabeth Balvin [liz.balvin@mci.com] To: Sanchez Steinke, Linda Subject: FW: Draft Response PC073003-1

Linda,

Please provide the details of what Qwest anticipates providing that was factored into the LOE.

Thanks in advance,

Liz Balvin MCI Carrier Management - Qwest Region Internal Line - V625-7305 External Line - 303-217-7305 Pager (888) 900-7221

11/19/03 November CMP Meeting Kit Thomte with Qwest said that this CR was being discussed with the Global Action Item meeting 11/18/03 and Connie Winston had implied that it might not go forward. Qwest will update the response. Liz Balvin said there might be the ability for CLECs to request testing scenarios specific to the GUI. This CR will remain in Evaluation status.

10/15/03 October CMP Meeting This CR was discussed at the 10/14/03 meeting and it was agreed this CR would remain in Evaluation status. Liz Balvin expressed concern that this CR was lingering even though discussed in the ad-hoc process. Liz said Qwest had not even provided a response on this CR.

09/17/03 September CMP Meeting Connie Winston reviewed the response to this CR. Connie said that Qwest is evaluating how we can package all the suggestions for improvement and provide a joint benefit. Testing is one of the things that Qwest would like to discuss at the next systems Ad Hoc meeting that will take place in a couple of weeks. Liz Balvin said that she was happy that Qwest is looking at resolutions and taking in CLEC input and would like to know what Qwest will do with the input that is being tracked under the Global Action Item. Bonnie Johnson with Eschelon suggested that Qwest provide something to look at prior to the Ad Hoc meeting. This CR will be moved to Evaluation status.

08/20/03 August CMP Meeting Liz Balvin with MCI said this CR was submitted to request insight into Qwest test plans and results for IMA EDI and GUI. CLECs want the opportunity to provide test scenarios for Qwest to use in the testing schedule. Connie Winston said Qwest would need to evaluate this CR and asked if CLECs were interested in functionality testing. Liz said that CLECs are interested in how Qwest is testing the documentation they publish. CLECs see documentation as edits against the LSR and want to verify that Qwest is not testing on the field. CLECs want to know how Qwest is testing functionality. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

11:00 a.m. (MDT) / Monday, August 11, 2003

1-877-572-8687 3393947# PC073003-1 Qwest to provide test plans and results prior to deployment of IMA

Name/Company: Liz Balvin, MCI Donna Osborne-Miller, AT&T Bonnie Johnson, Eschelon Joel Anderson, Qwest John Gallegos, Qwest Pat Bratetic, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Linda read from MCI’s CR the description of the change: CLECs currently have no insight to Qwest IMA test plans or results. MCI requests review of the test plan and results prior to IMA deployment. Expected Deliverable: Qwest provide in advance of deployment IMA test plans and results.

Liz Balvin with MCI said that she has assumed there are two stages of implementation 1) test plans 2) test results coming out the testing. Currently CLECs have no insight into the test plans and the test planning process. This CR was initiated to bring forth what Qwest sees when testing and CLECs would like to provide input to test plans. Joel Anderson with Qwest asked what level of information CLECs would like to see. Liz said they would like to see test scenarios and test cases. John Gallegos with Qwest said that the system test level mapping it to what communicated in disclosure documents we would have to work on internally because some of the systems testing would be specific to our own systems. John said that IMA pulls data from other systems and test scenario documentation may go into that kind of detail. Liz gave an example from 12.0; in the disclosure documents CLECs don’t know what edits are in the backend systems and the edits may be cricital processes beyond IMA. Liz said CLECs do get the Disclosure Documents in advance. She would like to see Qwest development test cases to validate the business rules and what the results are from the actual testing. John asked for examples of what other ILECs provide. Bonnie Johnson with Eschelon will provide any examples after Kim returns on Tuesday. Joel asked iif CLEC would want to input to system test case. Liz said yes if have input would like to provide it if necessary and would be more confident the CRs are deployed correctly. Examples of CRs are Migrate as specified; Blocking, Hunting, DL. John asked if CLECs would be able to provide scenarios also to ensure they are tested. Bonnie said yes they would. Liz said if with migrate as specified tested every feature and understand documentation published by Qwest it is hard to provide test scenarios. John said that Qwest would work off-line to review documents sent to CLECs.

Confirm Areas & Products Impacted IMA test plans and results prior to deployment of IMA.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation MCI’s expectation is that Qwest provide in advance of deployment IMA test plans and results.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) MCI will present this CR at the August CMP meeting.


CenturyLink Response

December 11, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the December 2003 CMP Meeting

Liz Balvin MCI

SUBJECT: Qwest’s Revised Response Change Request - PC073003-1 "Qwest to provide test plans and results prior to deployment of IMA"

Qwest has reviewed the information submitted as part of Change Request PC073003-1. Based upon the scope of this CR as agreed to in several meetings, Qwest is able to provide an estimated Level of Effort (LOE) of 8500 to 9200 hours with an additional 4000 hours per release going forward for this IMA Change Request.

At the December Product/Process CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request being crossed over to a System CR. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

This Change Request is an eligible IMA 16.0 candidate.

Sincerely,

Connie Winston Qwest

September 9, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the September 2003 CMP Meeting

Liz Balvin MCI

SUBJECT: Qwest’s Change Request Response - PC073003-1 "Qwest to provide test plans and results prior to deployment of IMA"

This is a preliminary response regarding the MCI CR PC073003-1. This CR requests review of the Qwest test plans and results prior to IMA deployment

Qwest is currently evaluating this request and proposes moving this Change Request into Evaluation Status while we continue to investigate. Qwest will provide an updated response at the October CMP Meeting.

Sincerely,

Connie Winston Director, Information Technology Qwest


Open Product/Process CR PC111902-02X Detail

 
Title: Eliminate submission of service order completion notifications (SOCs) when provisioning of services have not yet occurred
CR Number Current Status
Date
Area Impacted Products Impacted

PC111902-02X Crossover
7/27/2009
All
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Winston, Connie
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest service order processors are designed today to automatically send a service order completion (SOC) notifications on the firm order confirmation (FOC) due date (auto completion process). Qwest admits that there are certain scenarios that exist that cause a SOC to be sent to the CLEC even when the provisioning of services have not yet completed (Qwest believes this occurs on 1% of the total orders when analyzing all products for both wholesale and retail orders combined). WCom is requesting enhancements to the auto completion process that exist today that would ensure that Qwest creates and sends a SOC to the CLEC only when the actual provisioning of the order has been fully completed by Qwest.


Status History

11/19/2002 - CR submitted

11/20/2002 - CR acknowledged

11/23/2002 - Clarification Meeting scheduled

12/3/2002 - Clarification Meeting held

12/10/2002 - Status changed to evaluation

12/11/2002 - Draft response issues

12/19/2002 - Discussed at Monthly CMP Meeting

7/17/03 - Discussed at July CMP Systems - See Attachment I of Distribution Package

7/17/03 - Connie Winston/Qwest stated that this Change Request was actually worked on the product/process side. Connie noted that the notification was issued on the Service Interval Guide (PROS.02.28.03.F.01018.ReNotice_SIG). She noted that this was an existing process and that we are reinforcing the process. Connie also noted that there is a no system change necessary for this request. She asked how this should be handled from a CMP perspective.

Judy Schultz/Qwest stated that if the work has already been completed, and we have already notified the CLECs, it should move to a CLEC Test status.

Liz Balvin/MCI said that she would like to find out what Qwest has done and thought that this request should be formally crossed-over to Product/Process.

Judy Schultz/Qwest stated that it will be handled as a cross-over request to Product/Process and will be reviewed in the August CMP Product/Process Meeting. The Product/Process CRPM will have an off-line discussion regarding the Level 2 notification.

8/20/03 - August CMP meeting - See project meeting section for meeting minutes

9/17/03 - Sep CMP meeting notes will be posted to the database. CR agreed to close.


Project Meetings

08/20/03 Meeting Minutes Connee Winston – Qwest advised this is a cross over from systems. Connie advised that Network changed the process to make sure we are not sending the service order completion notifications (SOCs) when provisioning has not yet occurred. Liz Balvin-MCI asked Connie to explain how the process was changed. Connie agreed to check with Network and get the details. .

7/17/03 Systems CMP Meeting Connie Winston/Qwest stated that this Change Request was actually worked on the product/process side. Connie noted that the notification was issued on the Service Interval Guide (PROS.02.28.03.F.01018.ReNoticeSIG). She noted that this was an existing process and that we are reinforcing the process. Connie also noted that there is a no system change necessary for this request. She asked how this should be handled from a CMP perspective. Judy Schultz/Qwest stated that if the work has already been completed, and we have already notified the CLECs, it should move to a CLEC Test status. Liz Balvin/MCI said that she would like to find out what Qwest has done and thought that this request should be formally crossed-over to Product/Process. Judy Schultz/Qwest stated that it will be handled as a cross-over request to Product/Process and will be reviewed in the August CMP Product/Process Meeting. The Product/Process CRPM will have an off-line discussion regarding the Level 2 notification.

12/19/02 December Systems CMP Meeting Liz Balvin/WorldCom is requesting that Qwest create and sends a SOC to the CLEC only when the actual provisioning of the order has been fully completed. She also stated that they have worked with the Account Teams and have provided examples of this scenario. Connie Winston/Qwest noted that what we have found this scenario to be very rare. Qwest is researching the SOC process to determine if there are instances where there the provisioning of the service has not been completed. Bonnie Johnson/Eschelon said that they are getting completions on LSRs when there isn’t even an order. Liz Balvin/WorldCom said that the studies show that Qwest believes that this occurs on 1% of the total orders. WorldCom believes that it is higher for UNE-P. Jonathan Spangler/AT&T said that AT&T has found that they are receiving the SOC and believe the customer is up and running. We begin billing the customer and receive a call a week later to find the outside technician is just beginning the work. Liz Balvin/WorldCom said that maybe the answer is a process change that a technician needs to call and say hold the order and stop the auto completion. Lynn Notarianni/Qwest stated that how we go about this needs to be carefully laid out due to close timing situations. You do not want a process that creates jeopardies that are really not.. The completion report is the result of all this and we need to look at the process before determining whether any completion report change is necessary. Sue Stott/Qwest asked if this is the LSR completion vs. the service order completion. Jonathan Spangler/AT&T said yes. Liz Balvin/WorldCom said that she didn’t understand the other’ interface noted on the CR. Connie Winston/Qwest said that this CR is still under evaluation. This CR is not IMA. Completions are handled behind IMA. Kit Thomte/Qwest asked if there were any other questions or comments. No questions or comments. Connie Winston/Qwest said that we will do more research and if there are other examples please send them to us. Jennifer Arnold/USLink asked whom the examples could be sent to. Lynn Stecklein/Qwest said that examples could be sent to Lynn Stecklein or CMPCR, whichever is easiest. Kit Thomte/Qwest noted that the status would remain in Evaluation.

12/3/02 Clarification Meeting

INTRODUCTION OF ATTENDEES Attendees: Liz Balvin - WorldCom, Chad Warner - WorldCom, Conrad Evans - Qwest, Denise Martinez - Qwest, Lynn Stecklein - Qwest

REVIEW REQUESTED (DESCRIPTION OF) CHANGE Lynn Stecklein reviewed the change request submitted by WorldCom. Qwest service order processors are designed today to automatically send a service order completion (SOC) notifications on the firm order confirmation (FOC) due date (auto completion process). Qwest admits that there are certain scenarios that exist that cause a SOC to be sent to the CLEC even when the provisioning of services have not yet completed (Qwest believes this occurs on 1% of the total orders when analyzing all products for both wholesale and retail orders combined). WCom is requesting enhancements to the auto completion process that exist today that would ensure that Qwest creates and sends a SOC to the CLEC only when the actual provisioning of the order has been fully completed by Qwest.

Conrad Evans asked who WorldCom has been working with at Qwest. Liz Balvin said that the Account Teams and the EDI implementation Team has been involved in the analysis. WorldCom sent examples to the Account Team.

CONFIRM AREAS & PRODUCTS IMPACTED Liz Balvin said that the process applies to all products. Liz Balvin also stated that the 1% could be higher if you look at UNE-P

CONFIRM RIGHT PERSONNEL INVOLVED All appropriate were involved in the clarification call. Lynn Stecklein will contact the account team for examples and additional information if available on analysis already completed.

IDENTIFY/CONFIRM CLEC'S EXPECTATION WorldCom wants Qwest to Eliminate submission of service order completion notifications (SOC)s when provisioning of services have not yet occurred.

IDENTIFY ANY DEPENDENT CHANGE REQUEST NA

ESTABLISH ACTION PLAN

WorldCom will present this change request in the December Systems CMP meeting.

Lynn Stecklein will get with the account team for the examples already provided by WorldCom.


CenturyLink Response

DRAFT RESPONSE

December 11, 2002

RE: SCR111902-02 (Eliminate submission of service order completion notifications (SOC)s when provisioning of services have not yet occurred)

Qwest is reviewing the information submitted as part of WorldCom’s Change Request SCR111902-02, which aims to eliminate submission of service completion notifications when provisioning of services have not yet occurred. Based upon research that has been conducted following the Clarification meeting (held December 3, 2002) it has been determined that additional research is needed. Qwest will provide an updated response at the January Systems CMP Meeting.

Qwest is working diligently to address this Change Request and to provide the most accurate LOE possible. At the December Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received at the next Monthly Systems CMP Meeting into further evaluation of this Change Request.

Sincerely, Qwest


Open Product/Process CR PC070103-1 Detail

 
Title: Provide "Lines In Service Report" to CLECs
CR Number Current Status
Date
Area Impacted Products Impacted

PC070103-1 Completed
10/20/2004
Resale, UNE P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: McGhghy, Laura
Director:
CR PM: Andreen, Doug

Description Of Change

MCI is requesting that Qwest implement a "Lines In Service Report". This report would result in what Qwest reflects as active UNE-P and Resale lines in service that belong to a given CLEC on the date the report is generated. MCI is requesting that the report be provided on a monthly basis via CD-ROM or equivalent media type. This report would provide needed insight to any discrepancies between CLEC customer data and Qwest data and assist with reconciliation efforts.

Information MCI requests on the report:

- CLEC Name

- ACNA - Access Customer Name Abbreviation

- BTN - Billing Telephone Number

- WTN - Working Telephone Number

- Service Delivery Method

- Original Migrate/Completion Date

- Date of snapshot extract

- Type of Service (Bus/Res)

- State

Expected Deliverable:

That Qwest provide a "lines in service report" for UNE-P and Resale lines on a monthly basis via CD-ROM or equivalent media type.


Status History

07/01/03 - CR Received

07/01/03 - CR Acknowledged

07/11/03 - Held Clarification Meeting

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/29/03 - Held Ad Hoc Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/27/04 - Qwest issued PROS.02.27.04.F.01409.LinesInServiceReport effective immediately

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

10/20/04 CMP Meeting Minutes Laura McGhghy, Qwest stated that testing is complete and the CR can be closed. MCI agreed and the CR will be moved to completed status.

-- 09/16/04 CMP Meeting Minutes Laura McGhghy reported that Qwest would like to leave this CR in Test for one more month. MCI is doing additional analysis and the intent is to have this ready to close next month and shift to the normal process involving the account manager. LeiLani Hines agreed and said that there was a conference call on Monday and due to some confusion when Liz Balvin left MCI we needed to get back on track. MCI will be submitting a new report and she is in agreement with leaving this in Test Status.

- 8/18/04 CMP Meeting Cindi Houston reported that Qwest had began an analysis of the items sent from MCI and requested clarification from MCI on some issues. She is currently awaiting MCI’s reply. Leilani Hines said she will check the status on the MCI side. The CR will remain in Test.

7/21/04 July CMP Meeting Liz Balvin, MCI said that MCI has been attempting to audit the report and have run into delays. She expected information from her MCI counterparts this week but has not received anything as yet. There are several issues and Liz is attempting to ascertain if the issues are MCI or Qwest. Liz will forward issues and examples to Doug Andreen when available. The CR will remain in Test.

6/28/04 9:00 a.m. To: 'liz.balvin@mci.com' From: Sanchez Steinke, Linda CR PC070103-1 Provide "Lines In Service Report" to CLECs

Hi Liz -

As a follow up to our discussion about this CR at the June CMP, has MCI been able to finish the audit and be able to close this CR mid-cycle?

Thank you

Linda Sanchez-Steinke Qwest CRPM 303-382-5768

06/16/04 June CMP Meeting Liz Balvin with MCI asked that the CR remain open for one more month until the audit is completed. If this is done before the next CMP, Liz will e-mail to close the CR. This CR will remain in CLEC Test status.

05/19/04 May CMP Meeting Laura McGhghy with Qwest said she had received additional requests for the reports and asked that the CR be closed. Liz Balvin asked that the CR remain open because they were supposed to have completed an audit but it has not been completed as of yet. This CR will remain in CLEC Test status.

04/21/04 April CMP Meeting Laura McGhghy with Qwest advised we are continuing to provide this report. Bonnie Johnson with Eschelon said she didn’t think Eschelon has the ability to get the report sooner than when the March data is available. Laura said that we are processing now for the March report. This CR will move to CLEC Test status.

03/17/04 March CMP Meeting Laura McGhghy with Qwest said she wanted to clear up any confusion regarding the lines in service report. The report is based on MR8 PID data and Qwest needs time to update tables and this report request follows the standard process for PID data reports. The CLEC should request the report prior to the first of the month and gave an example that if the request is received by the first of March, March results will be available at the end of April. Bonnie Johnson with Eschelon said that when the notice came out it said January data would be available at the end of February. Laura said that the notification was specific to MCI’s request, and, due to the timing of Eschelon’s report request, the Eschelon report will be ready at the end of April. This CR will remain in Development status.

- 02/18/04 February CMP Meeting Laura McGhghy with Qwest gave an update that 2/27/04 is targeted to provide the January data. In addition to the report, there will be a product code explanation file that provides a product code definition. Jennifer Arnold with U S Link asked how to get the report. Laura explained they should contact their service manager to request. This CR will remain in Development status.

01/21/04 January CMP Meeting Laura McGhghy with Qwest gave an update that January data will be provided at the end of February and that a notification will be sent. This CR will remain in Development status.

12/17/03 December CMP Meeting Laura McGhghy with Qwest gave an update on the CR. Laura said that during the ad hoc meeting she had an action item to determine if BTN would be available for non-design services. BTN will not be available for non-design services and will be available for design services. Laura added that the reports will be provided by state and each state will have one report for design services and one report for non-design services. Liz Balvin with MCI clarified that the reports will be state specific and will be broken down by design and non-design reports. This CR will remain in Development status.

11/19/03 November CMP Meeting Laura McGhghy with Qwest provided an update on this CR and said that Qwest is continuing development and expects to provide January results in the February timeframe. Liz Balvin with MCI asked how the CLECs would get the data. Laura said that the data will be available where the PID results are located. This CR will remain in Development Status.

Ad Hoc Meeting Minutes PC070103-1 Provide "Lines In Service Report" to CLECs CMP Product & Process October 29, 2003 1-877-572-8687, Conference ID 3393947# 9:00 a.m. - 10:00 a.m. Mountain Time

PURPOSE

At the October CMP Meeting, participants agreed to hold a conference call to review the format for the report. The following is the write-up of the discussion.

List of Attendees: Donna Osborne-Miller, AT&T Liz Balvin, MCI Kim Issaacs, Eschelon Kathy Stitcher, Eschelon Cedric Cox, MCI Ed Boehme, MCI Laura McGhghy, Qwest Dave Phillips, Qwest Jon Boisseau, Qwest Linda Sanchez-Steinke, Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to review the draft report format. Laura McGhghy with Qwest reviewed the draft reports. Resale design products and non-design products will be available in two files. Design Products report will include; CLEC ID, ACNA, BTN, Circuit ID, Product Code, Extract date, and State. Non-Design Products report will include; CLEC ID, WTN, Product Code, Extract Date and State.

Liz Balvin with MCI asked for further definition of the product code. Laura McGhghy said that the product name, i.e., DS1 would mean resale DS1. Liz asked if the CLEC ID would be the RSID. Laura said yes.

Laura continued explaining the report and said that the original migration date is not something that is in our system and is unavailable for the reports.

Cedric Cox with MCI asked if the BTN is available on non-design and added that most ILECs normally want the BTN with the WTN for disputes. Dave Phillips said that BTN is not available in the data that will be provided with the current report design. Cedric asked if the customer has multiple lines, will the WTNs show on the report as belonging to the CLEC. Dave answered yes. Laura took an action item to find out if BTN is available on the non-design data.

Liz Balvin asked if the report was derived from PREMIS or CRIS, as PREMIS only has WTN data. Dave said that the non-design data is coming from LMOS, and the design data is from TIRKS.

Cedric asked if there was a dispute on a WTN would the CLEC have to provide the BTN. Dave Phillips answered that we would have to work through disputes with the data available.

Liz asked if the extract date is the date the data is pulled from LMOS. Dave and Laura responded that it is the date the data is pulled from either LMOS or TIRKS.

Cedric asked if there will be indication of Residence or Business. Laura said that Res or Bus will be in the product code. Laura and Dave committed to provide a list of the prodcd’s and their English names to MCI.

Liz asked if they could get valid values populated and what date the reports would be available. Laura said that when the data is pulled the extract date is a snapshot of the date it occurs. Dave will find out when the data will be pulled and get back to MCI.

Cedrick asked what the dispute process is if they have 1000 ANI’s that they believe do not belong to them. Jon Boisseau said there is the informal reconciliation process, the formal process through the PAP and Service Management can also take the dispute to regulatory reporting.

Kathy Stitcher with Eschelon asked if unbundled loop would be in the design file. Laura said that resale and any other design type products would be in the design file.

Linda asked if there were any questions. No questions were asked.

10/15/03 October CMP Meeting Laura McGhghy with Qwest provided an update on this CR. Qwest plans to have January data available in the month of February. Laura would like to hold an ad hoc meeting to discuss the draft format of the report. Linda Sanchez-Steinke will e-mail Liz with possible dates for the meeting. This CR will remain in Development Status.

09/17/03 September CMP Meeting Laura McGhghy with Qwest provided the Qwest draft response. Qwest will provide the report requested and target January 2004 for the data to be available. Liz Balvin said would like to see the data in a draft form as soon as available. Other CLECs would like to get the report as well and Laura said they should request the report through their service manager. This CR will move to Development Status.

08/20/03 August CMP Meeting Laura McGhghy with Qwest reviewed the draft response and said Qwest is investigating possible solutions for this CR and will have an updated response at the September meeting. This CR will be moved to Evaluation status.

07/16/03 July CMP Meeting Liz Balvin with MCI presented this CR. MCI would like a monthly report of UNE-P and Resale lines in service. This report would give the ability to sync up the lines in service with the CLEC and Qwest. Sue Kriebel asked for the name of the report provided for access lines and Liz will provide the information to Linda Sanchez-Steinke. Dusti Bastian asked what additional data fields would be included in the monthly report vs. the daily loss and completion report. Liz said this report will be on a specific month timeframe and will include lines in service Qwest identifies and tie back to losses, helping to track and resolve issues. Sue Kriebel asked how the monthly report would be different from the CSR report that identifies lines in service. Liz said they have to access the CSR. Sue said the CSR is received along with the bill, and when the bill is received you can see the TN that is being billed. Liz said that billing isn’t what Qwest identifies as the lines in service and there would also be timing issues with the CSR report. Sue asked if the monthly report would be pulled on a different day than the bill and Liz said MCI wants the report pulled on the 1st or the 31st of the month. Bonnie Johnson with Eschelon said that the loss and completion report received daily only identifies service order activity and not total lines in service. Liz would like to understand why the CR was unilaterally changed to a Product / Process CR and Kit Thomte with Qwest apologized that the CR was acknowledged as Product and Process without an explanation when MCI had requested it be a Systems CR.

CLEC Change Request Clarification Meeting

3:00 p.m. (MDT) / Friday, July 11, 2003

1-877-572-8687 3393947# PC070103-1 Provide "Lines In Service Report" to CLECs

Name/Company: Liz Balvin, MCI Cedric Cox, MCI Donna Lucio, Qwest Fred Howard, Qwest Kerri Waldner, Qwest Luke Von Hagen, Qwest Don Kerschner, Qwest Laurel Nolan, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change MCI’s CR requests that Qwest implement a "Lines In Service Report". This report would result in what Qwest reflects as active UNE-P and Resale lines in service that belong to a given CLEC on the date the report is generated. MCI is requesting that the report be provided on a monthly basis via CD-ROM or equivalent media type. This report would provide needed insight to any discrepancies between CLEC customer data and Qwest data and assist with reconciliation efforts.

Information MCI requests on the report: - CLEC Name - ACNA - Access Customer Name Abbreviation - BTN - Billing Telephone Number - WTN - Working Telephone Number - Service Delivery Method - Original Migrate/Completion Date - Date of snapshot extract - Type of Service (Bus/Res) - State

Liz Balvin with MCI said that Qwest has a similar lines in service report on the Access side and this report allows a sync up with installed services and allows them to catch discrepancies sooner. Kerri Waldner with Qwest asked if the items requested are being provided in any other report. Liz said that she is not aware of any other report providing this information. Dusti Bastian asked for a definition of Service Delivery Method. Cedric said that is the product type, resale or UNE-P. Fred Howard asked if the report was requesting data for MCI only. Cedric answered yes, MCI only is what is requested. Dusti asked if this report would be for services billed or for services provisioned. Cedric said for those services provisioned.

Kerri asked if the report would be a snapshot in time with no accumulation. Cedric said that the report would be a snapshot in time. Donna Lucio asked about the timing of the report and if MCI would want the report at the first or the last of the month. Liz and Cedric said it didn’t matter what date the report is pulled and that they are looking for a monthly report. Cedric said that MCI would take the TN’s and bounce them against a database for telco billing and traffic data. This would give them line loses that they hadn’t been made aware of previously. Kerri asked if MCI wants to get this monthly, would it be a snap shot in time or a monthly compilation. Liz and Cedric answered they would like a snapshot in time and don’t need a cumulative report.

Liz said that she is concerned with the unilateral conversion process that this CR was moved to Product and process and would like an explanation why the CR was handled in this way.

Confirm Areas & Products Impacted Products impacted with this CR are UNE and Resale Lines.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation MCI’s expectation is a monthly report for active UNE-P and Resale lines in service.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) MCI will present this CR at the July CMP meeting.


CenturyLink Response

September 9, 2003

Liz Balvin MCI

SUBJECT: Qwest’s Change Request Response - CR PC070103-1 "Provide 'Lines in Service Report' to CLECs".

As a follow up to the August 20, 2003 CMP Meeting, Qwest is willing to provide a monthly report of all MCI lines in service for all products currently reported in 271 reporting.

This report will be available to MCI from the secure website where MCI obtains all other PID reporting data. Qwest is beginning investigation and coding work at this time and expects to have the data available to MCI in January 2004.

Sincerely,

Laura McGhghy Lead Process Analyst Qwest

August 13, 2003

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the August 20, 2003 CMP Meeting

Liz Balvin MCI

SUBJECT: Qwest’s Change Request Response - PC070103-1 Provide "Lines In Service Report" to CLECs

MCI’s CR requests that Qwest provide a report reflecting active UNE-P and Resale lines in service that belong to a given CLEC on the date the report is generated.

Qwest is investigating possible solutions to this change request and will provide an updated response at the September CMP meeting.

Sincerely,

Donna Lucio Sr. Process Analyst Qwest

Cc: Sue Burson, Qwest Sue Kriebel, Qwest


Open Product/Process CR PC093002-05X Detail

 
Title: Revised Title: EDI documentation guidelines Original Title: Single Source Document for Implementing (Crossover CR SCR093002 05)
CR Number Current Status
Date
Area Impacted Products Impacted

PC093002-05X Crossover
7/29/2009
Pre-Ordering, Ordering All
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Schultz, Judy
Director:
CR PM: Stecklein, Lynn

Description Of Change

4/18/03 Revised Description: That Qwest personnel utilize the following guidelines when updating documentation, on a going forward basis:

1) Interface differences not clear (EDI or GUI). Functional differences should not exist.

2) Field level of detail for both inquiry and response transactions lacking (what special characters apply?)

3) ALL valid entries be provided for each transaction type

4) Acronyms must be defined

5) Usage rules must be defined

6) References must defined or have links provided

7) Complete and accurate business rules must be provided

8) Restrictions must be clearly defined

9) Lack of business rules to support usage cannot occur

10) Process established to sync up EDI documentation (disclosure documents and appendices)

NOTE: As originally intended, MCI considers this CR to be a process change request. The CMP document is specific:

Section 5.1 states "A CLEC or Qwest seeking to change an existing OSS Interface, (CR to establish a new OSS Interface, or to retire an existing OSS Interface must submit a Change Request)."

Section 5.3 states "If a CLEC wants Qwest to change a product/process, the CLEC e-mails a Change Request (CR) Form to the Qwest CMP Manager, cmpcr@qwest.com."

MCI's CRs, as with Qwest internal documentation enhancements, should not be subject to IMA resources.


Status History

4/18/03P/P CR submitted by WorldCom - See Project Meeting Minutes 4/17/03

5/6/03 - P/P Crossover CR created (See SCR093002-05 System CR)


Project Meetings

4/17/03 An agreement was reached with the CLEC Community in the April CMP Systems Meeting on SCR093002-05 (Single Source Document for Implementing EDI). This change request will be 'crossed over' to product and process and closed. Qwest agreed to 'cross over' this CR with the caveat that Qwest does not agree that this is Process work and believes it to be a system request.

4/17/03 CMP Systems Meeting Kit Thomte/Qwest stated that there is one more walk on to discuss regarding, from Liz Balvin. Liz Balvin/MCI stated that she was expecting a follow up call from Qwest last month and never got one. Kit Thomte/Qwest stated that nothing has changed in regard to this issue. Liz Balvin/MCI stated that WorldCom submitted process CRs and Qwest unilaterally processed them as systems CRs. Liz stated that if Qwest objected to MCI’s issuing these CRs as Process CRs, then Qwest needs to take this to the oversight committee. Kit Thomte/Qwest stated that Judy Schultz needs to address this issue and that Judy will be returning to the meeting after lunch. Liz Balvin/MCI stated that WorldCom wanted the CRs reverted back to Product/Process and sees that it was not done. Liz stated that she does not know if Judy is aware of that. Lynn Notarianni/Qwest stated that Judy is aware of your position on that. Lynn stated that from a standpoint of resolution, Qwest’s position is that we would not be escalating on ourselves on an issue that we feel that the decision was made congruent with how we’ve treated these types of issues in the past. Lynn stated that these CRs do need and take systems resources in order to do the work. Kit Thomte/Qwest recommended that we break for lunch and reconvene at 1:00 p.m. MT. Liz Balvin/MCI stated that WorldCom submitted 3 CRs as document changes and Qwest unilaterally changed them to systems CRs. Liz stated that this conversation has gone round and round. Liz stated that she tried to change the language back in December because she did not want these to impact IMA resources. Liz stated that the Qwest EDI implementation team changes documentation if Qwest finds a problem. Liz stated that if Qwest believes that WorldCom inappropriately sent these as Product/Process, Qwest needs to do something. Liz noted that any time there has been a cross over we’ve agreed to it in this forum and stated that she sees Qwest as out of process and doesn’t know how to better address that. Judy Schultz/Qwest stated that it is important to have this discussion and feels that we are at an impasse. Judy apologized if in the past Qwest has made unilateral decisions without communicating those decisions to change the CRs from Product/Process to Systems. Judy stated that Qwest is in the unique position of knowing which it should be and when there will be an impact to the systems. Judy stated that you might think it is just a process change, but we do know our internal systems and can say when a request would really impact a system. Judy noted that on the other hand, some changes come in as systems and we can look at it and determine that it would not require systems restraints and so we suggest crossing those CRs over to Product/Process. Judy stated that an email is sent to state if processed as a Product/Process or a Systems CR. Judy stated that the one issue that we are a little bit apart on is what to do with these systems documentation changes. Judy stated that in Section 8, which describes systems changes, the deliverables do include the system’s documentation, which is Sue’s (Stott) team. Liz Balvin/MCI stated that she agrees that the initial documentation to documented system enhancements per release should be included, but this is after it is implemented and a CLEC identifies a flaw with the documentation. Liz stated that in December, she said that the change was not intended to change existing documentation or previously existing versions, we just want issues addressed going forward. Liz stated that resources are required for new release documents, but once the document is used and a defect is identified, they should be corrected. Liz noted that the CLECs work with the EDI documentation team and when an issue is identified, that team fixes the problem. Sue Stott/Qwest stated that her team handles those in the same manner as a production support bug. Liz Balvin/MCI stated that these CR’s are for the issues that the EDI team said Qwest would not do as a bug fix. Wendy Green/Qwest stated that those were ones that Qwest viewed as enhancements rather than a bug in the documentation. Sharon Van Meter/AT&T asked if after a release is implemented and a bug is identified in the documentation, WorldCom sends an email to someone? Judy Schultz/Qwest stated that should go through production support. Liz Balvin/MCI stated that the production support help desk would not know this stuff. Liz Balvin/MCI stated that they do work with the EDI team and were told to issue these CRs. Wendy Green/Qwest stated that they are not a bug because the information is already there, it is an enhancement. Wendy noted that a lot of the time Qwest fixes issues that a CLEC brings forwards through that team but in this case you were requesting something a bit bigger than simply a clarification or a bug fix. Liz Balvin/MCI stated that it is not an enhancement because the documentation is incorrect. Lynn Notarianni/Qwest stated that we are disagreeing about a gray area, one side views as an enhancement and one side views as a bug. Donna Osborne-Miller/AT&T stated that her consumer team is finding this a challenge, they are trying to work with a manual and are feeling the same frustration. Liz Balvin/MCI stated that she understands Qwest’s position to not look at every data field so agreed to change the CR. Liz stated that the guidelines are for Qwest to focus on documentation going forward. Judy Schultz/Qwest stated that there is a process for documentation issues when Qwest and the CLECs believe that it is a bug. Liz Balvin/MCI stated is for when Qwest believes it to be a bug. Judy Schultz/Qwest asked when it happens that something in the documentation that a CLEC sees as a defect and Qwest doesn’t, would it satisfy the CLECs if going forward as fields are impacted in the course of a release, the documentation would be changed going forward to adhere to those expectations. Sue Stott/Qwest stated that this is currently occurring. Liz Balvin/MCI stated that in reference to this CR, they were told to issue a CR., as well as for the other 2 CRs. Sue Stott/Qwest stated that where it gets gray is when further clarification is needed for a field. Liz Balvin/MCI stated that these items are not gray, they are adding valid values or formats. Sue Stott/Qwest stated that the bigger issue for IT documentation is Qwest has people working on the releases and when they get a request for a documentation update, the people have to be diverted from the release in order to do the documentation updates. Sue stated that maybe the answer is less capacity for a release. Judy Schultz/Qwest stated that she wants to make sure that we’re clear. Judy noted that if there were 200 different fields to update, that would be a big effort. Judy stated that she thought she heard that IT was going forward in trying to follow the proposed guidelines. Sue Stott/Qwest stated that IT does that today and noted that her concern is, if you are an EDI user you are not going to pay close attention to the new release right away and that Qwest will not be made aware of issues until much later. Randy Owen/Qwest stated that Qwest needs to be careful because you cannot update for some products and not all, that would create other problems. Randy stated that we need to look at updates across the board, maybe a legend should be developed. Liz Balvin/MCI stated that the EDI documentation is going to come along because you now have users. Liz noted that consistency is an excellent point, if you only do that on one field then it could create inconsistency. Liz stated that she liked the idea of a legend but would need to check with her coders to see if one would work for them. Liz stated that she could possibly only be looking at a specific field and would need a guide to tell her what to look at first. Judy Schultz/Qwest asked what if we do a running cheat sheet. Randy Owen/Qwest stated that we saw that this CR might take us there and started down that path. Then heard that is not what was wanted. Sue Stott/Qwest stated that we have to carefully scrutinize to ensure that a documentation change doesn’t also mean a system change. It is so tightly related, the difference can be as subtle as an and/or difference. Sue stated that is another reason why system resources are needed. Judy Schultz/Qwest stated that she understands that it is the same resources and is just trying to explore if IT can do a piece at-a-time. Judy asked if there are ever any times when it would be logical do to this kind of work. Is there ever a time in development when we could spend time doing this? Sue Stott/Qwest stated that it would still take systems resources to do that and stated that the issue is if it affects the voting capacity for a release. Sue stated that in many cases the same resources are used for coding and documentation. Liz Balvin/MCI asked if she could update the single source CR with a title change to ‘Guiding Principals to Qwest Documentation on Going Forward Basis, When Documentation Happens’, and will list the 10-items that you say you are using. Liz stated that the CR would then be moved back to Process and the documentation would be done when the regular document comes out. Liz stated that when new documentation comes out in future releases and sees that the guidelines are not being adhered to, and when it severely impacts her ability to do business then she would bring it forward. Liz stated that she would be willing to do that in order to get these off the table. Liz stated that she understands where Qwest is coming from and that believes that Qwest understands where she is coming from. Kit Thomte/Qwest asked how the guidelines would be updated. Liz Balvin/MCI stated that they would be closed with this CR and for other items that come up, new CRs would be issued. Donna Osborne-Miller/AT&T asked if they are to call the Help Desk if problems after in production. Randy Owen/Qwest stated that the documentation team is to be contacted if prior to 30 days after production, after the 30 days, you contact the Help Desk. Wendy Green/Qwest stated that we took the principles and looked at redesigning to be 1 document for both EDI and GUI. Wendy stated that she did not know if that is still on the table. Liz Balvin/MCI stated that that was not the intent of the CR. Lynn Notarianni/Qwest asked if the guiding principles are separate from SBCs document. Wendy Green/Qwest stated that within the current format, will use the 10 guiding principles. Judy Schultz/Qwest asked if we should have a ‘guiding principles’ standing agenda item to identify what can be removed from the list. Wendy Green/Qwest stated that things would never be crossed off the list because they are principles and are there forever. Liz Balvin/MCI shared Judy’s concern and stated that they just came across a situation where they reserved TNs in the GUI and submitted the order in EDI. The reps populated the PON manually, typing them in lower case, but went out the door in upper case. Liz stated that it is not documented that they have to be in upper case. Liz stated that it would be helpful to have a tab for Documentation Experiences/Discussion. Lynn Notarianni/Qwest stated that there is a tab for design walkthrough’s and we can have one for documentation. Lynn noted that it could have something in it, or not. Liz Balvin/MCI stated that she understands Qwests position and stated that she did not know that she could call the Help Desk for documentation issues, that is a value add from this discussion. Sue Stott/Qwest asked that instead of a standing agenda item or separate tab, maybe we could add documentation issues to the SATE portion of the meeting. Wendy Green/Qwest stated that that would be fine. Liz Balvin/MCI stated that it could be EDI/SATE. Liz Balvin/MCI stated that she would review her 3 CRs to see if they are guiding principles. Judy Schultz/Qwest stated that if Liz wants to close as a process CR, is ok with that as long as it is noted that Qwest does not agree that this is Process work. Judy stated that Qwest truly believes them to be systems requests. Liz Balvin/MCI stated that she was not clear on closing the CR as a Process CR. Judy Schultz/Qwest responded that that is what Liz wanted. Randy Owen/Qwest stated that the guiding principles can be closed, Qwest has adopted them. Judy Schultz/Qwest stated that when a CLEC submits a CR, Qwest looks at it and determines if it is an impact for Product/Process or Systems. Judy stated that Qwest would email the CLEC if the category is different. Judy asked if that was an acceptable way to communicate. Liz Balvin/MCI stated that she did receive emails and that she responded that she did not agree with the assigned category. Judy Schultz/Qwest asked that when the email is sent, what happens if we cannot reach agreement, how do we break that stalemate? Lynn Notarianni/Qwest stated that in that case, if a CLEC says it is a Product/Process CR and Qwest says that it is not, it could result in a denial based on infeaseability. Judy Schultz/Qwest stated that it could result in a denial. Liz Balvin/MCI stated that she would not be unreasonable. Lynn Notarianni/Qwest stated that she is just stating that it could be a risk. Liz Balvin/MCI stated that the stalemate is due to the category of product/process or systems, and stated that she thinks that we have flushed out why each of us believes the way we do. Liz asked if these CRs are going to remain as Process CRs as they were originally intended? Judy Schultz/Qwest stated that she is ok with the change back to Process and closing it out, with Judy adding a note that Qwest believes the CR to be a Systems change. Judy stated that she has an obligation to represent Qwest’s position. Judy stated that in the future, as CRs come in the door, my team will send out an email with the category, and if you don’t agree you need to let us know and we will call a meeting to discuss. Judy asked if that was acceptable to the CLECs. Liz Balvin/MCI said yes. Lynn Stecklein/Qwest asked how the CRs that are marked as both Product/Process are to be handled. Judy Schultz/Qwest stated that in some instances the CR may be both, could be a systems CR and an MN. Judy stated that if the CR is for both P/P and Systems, the CRPM would ask that separate CRs be issued. Lynn Stecklein/Qwest clarified that all 3 CRs will be crossed-over to Product/Process and will be closed. There were no additional questions or comments.

4/18/03 Revised Description: That Qwest personnel utilize the following guidelines when updating documentation, on a going forward basis: 1) Interface differences not clear (EDI or GUI). Functional differences should not exist. 2) Field level of detail for both inquiry and response transactions lacking (what special characters apply?) 3) ALL valid entries be provided for each transaction type 4) Acronyms must be defined 5) Usage rules must be defined 6) References must defined or have links provided 7) Complete and accurate business rules must be provided 8) Restrictions must be clearly defined 9) Lack of business rules to support usage cannot occur 10) Process established to sync up EDI documentation (disclosure documents and appendices) NOTE: As originally intended, MCI considers this CR to be a process change request. The CMP document is specific:

Section 5.1 states "A CLEC or Qwest seeking to change an existing OSS Interface, (CR to establish a new OSS Interface, or to retire an existing OSS Interface must submit a Change Request)."

Section 5.3 states "If a CLEC wants Qwest to change a product/process, the CLEC e-mails a Change Request (CR) Form to the Qwest CMP Manager, cmpcr@qwest.com."

MCI's CRs, as with Qwest internal documentation enhancements, should not be subject to IMA resources.

--Original Message-- From: Elizabeth Balvin [mailto:liz.balvin@wcom.com] Sent: Monday, January 27, 2003 5:09 PM To: 'lsteckl@qwest.com' Cc: 'Johnson, Bonnie J.'; 'amaus@mainstreetcom.com'; 'arlen@contactcom.net'; 'Bart Atkinson (E-mail)'; 'byron.dowding@alltel.com'; 'Carla D NCAM Pardee (E-mail)'; 'chris@contactcom.net'; 'Dan Rosedahl (E-mail)'; 'David Hennes (E-mail)'; 'dosborne@att.com'; 'freddi@microtech-tel.com'; 'John Berard (E-mail)'; 'Karen Clauson'; 'Kimberly Isaacs'; 'Lea Barron (E-mail)'; 'Leilani Hines (E-mail)'; 'Linda Fowlkes (E-mail)'; 'Littler Bill (E-mail)'; 'Lori Mendoza (E-mail)'; 'lrucks@blackfoot.com'; 'Mark R. Powell (E-mail)'; 'mzulevic@covad.com'; 'Nancy Conant (E-mail)'; 'Peder Gunderson (E-mail)'; 'Sharon K NCAM Van Meter (E-mail)'; 'Sherry Lichtenberg (E-mail)'; 'Stephanie Prull (E-mail)'; 'Tom Hyde (E-mail)'; 'vicky@consolidatedtelcom.com' Subject: EDI Documentation Lynn, The following is a high level list of issues WCom has identified regarding Qwest's EDI documentation. While this list is not inclusive, per Qwest recommendation, WCom provides as a start at developing "guidelines" for Qwest documentation updates going forward: 1) Interface differences not clear (EDI or GUI), CLECs expect functionality would NEVER differ, need to confirm 2) Field level of detail for both inquiry and response transactions lacking (what special characters apply?) 3) ALL valid entries be provided for each transaction type 4) Acronyms must be defined 5) Usage rules must be defined 6) References must defined or have links provided 7) Complete and accurate business rules must provided 8) Restrictions must be clearly defined 9) Lack of business rules to support usage cannot occur 10) Process established to sync up EDI documentation (disclosure documents and appendices)

12/18/02 Email w/ Revised Description: --Original Message-- From: Elizabeth Balvin [mailto:liz.balvin@wcom.com] Sent: Wednesday, December 18, 2002 2:19 PM To: 'cmpcr@qwest.com' Cc: 'lsteckl@qwest.com' Subject: FW: SCR093002-05 Single Source Document for Implementing EDI

WCom is willing to change the language in the attached CR to better reflect the intended change. NOTE: The original request was submitted as a "process" CR which is still the intended CMP WCom wishes to follow. As such, the CR would not compete for IMA resources and impact prioritization. The new language should read:

This change request is not intended to modify in any way the current or planned Qwest applications or code to support these systems. In addition, this change request is not intended to be retroactive to current or previous OSS interface requirements. It is intended to be implemented on a going forward basis. The request seeks to require CLEC input such that Qwest understands from a "users perspective" what changes are need to provide "efficacy" as required by the FCC. WCom recommends working sessions with interested Parties as a means to establish ground rules for documentation.

An exception would not be necessary if Qwest agrees with following the Process CMP.

9/27/02 Original Description: At a minimum, the following documents are provided by Qwest for EDI Implementation: Product Catalog (PCAT) Qwest Preparation Guides EDI Disclosure Documentation LSR Developer Worksheets Premis Guide for City List EDI/SATE Error List and IMA User's Guide Sources are not always in sync and cross referencing causes delays


Open Product/Process CR PC022703-25X Detail

 
Title: Documentation update (valid values on AVR and CSR response fields)
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-25X Crossover
7/27/2009
UNE-P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Schultz, Judy
Director:
CR PM: Stecklein, Lynn

Description Of Change

WCom request valid values be provided for the following:

1) Developer Worksheet CSRR9 PGRTIND.

2) Developer Worksheet CSRR10 CSRSIZE

3) Developer Worksheet CSRR77 and CSRR92 USOCQTY.

4) Developer Worksheet CSRR123 and CSRR127 ERRNUM.

5) Developers Worksheet, Appendix A field SWTYPNUM.

6) Developers Worksheet Appendix A, field NMNUM.

7) Developers Worksheet, Appendix A field MCNUM.


Status History

5/6/03 - P/P CR submitted by WorldCom

5/6/03 Crossover created. (See SCR022702-25)


Project Meetings

4/17/03 CMP Systems Meeting An agreement was reached with the CLEC Community in the April CMP Systems Meeting on SCR022703-25X Documentation update - valid values on AVR and CSR response fields). This change request will be 'crossed over' to product and process and closed. Qwest agreed to 'cross over' this CR with the caveat that Qwest does not agree that this is Process work and believes it to be a system request. 4/17/03 CMP Systems Meeting Kit Thomte/Qwest stated that there is one more walk on to discuss regarding, from Liz Balvin. Liz Balvin/MCI stated that she was expecting a follow up call from Qwest last month and never got one. Kit Thomte/Qwest stated that nothing has changed in regard to this issue. Liz Balvin/MCI stated that WorldCom submitted process CRs and Qwest unilaterally processed them as systems CRs. Liz stated that if Qwest objected to MCI’s issuing these CRs as Process CRs, then Qwest needs to take this to the oversight committee. Kit Thomte/Qwest stated that Judy Schultz needs to address this issue and that Judy will be returning to the meeting after lunch. Liz Balvin/MCI stated that WorldCom wanted the CRs reverted back to Product/Process and sees that it was not done. Liz stated that she does not know if Judy is aware of that. Lynn Notarianni/Qwest stated that Judy is aware of your position on that. Lynn stated that from a standpoint of resolution, Qwest’s position is that we would not be escalating on ourselves on an issue that we feel that the decision was made congruent with how we’ve treated these types of issues in the past. Lynn stated that these CRs do need and take systems resources in order to do the work. Kit Thomte/Qwest recommended that we break for lunch and reconvene at 1:00 p.m. MT. Liz Balvin/MCI stated that WorldCom submitted 3 CRs as document changes and Qwest unilaterally changed them to systems CRs. Liz stated that this conversation has gone round and round. Liz stated that she tried to change the language back in December because she did not want these to impact IMA resources. Liz stated that the Qwest EDI implementation team changes documentation if Qwest finds a problem. Liz stated that if Qwest believes that WorldCom inappropriately sent these as Product/Process, Qwest needs to do something. Liz noted that any time there has been a cross over we’ve agreed to it in this forum and stated that she sees Qwest as out of process and doesn’t know how to better address that. Judy Schultz/Qwest stated that it is important to have this discussion and feels that we are at an impasse. Judy apologized if in the past Qwest has made unilateral decisions without communicating those decisions to change the CRs from Product/Process to Systems. Judy stated that Qwest is in the unique position of knowing which it should be and when there will be an impact to the systems. Judy stated that you might think it is just a process change, but we do know our internal systems and can say when a request would really impact a system. Judy noted that on the other hand, some changes come in as systems and we can look at it and determine that it would not require systems restraints and so we suggest crossing those CRs over to Product/Process. Judy stated that an email is sent to state if processed as a Product/Process or a Systems CR. Judy stated that the one issue that we are a little bit apart on is what to do with these systems documentation changes. Judy stated that in Section 8, which describes systems changes, the deliverables do include the system’s documentation, which is Sue’s (Stott) team. Liz Balvin/MCI stated that she agrees that the initial documentation to documented system enhancements per release should be included, but this is after it is implemented and a CLEC identifies a flaw with the documentation. Liz stated that in December, she said that the change was not intended to change existing documentation or previously existing versions, we just want issues addressed going forward. Liz stated that resources are required for new release documents, but once the document is used and a defect is identified, they should be corrected. Liz noted that the CLECs work with the EDI documentation team and when an issue is identified, that team fixes the problem. Sue Stott/Qwest stated that her team handles those in the same manner as a production support bug. Liz Balvin/MCI stated that these CR’s are for the issues that the EDI team said Qwest would not do as a bug fix. Wendy Green/Qwest stated that those were ones that Qwest viewed as enhancements rather than a bug in the documentation. Sharon Van Meter/AT&T asked if after a release is implemented and a bug is identified in the documentation, WorldCom sends an email to someone? Judy Schultz/Qwest stated that should go through production support. Liz Balvin/MCI stated that the production support help desk would not know this stuff. Liz Balvin/MCI stated that they do work with the EDI team and were told to issue these CRs. Wendy Green/Qwest stated that they are not a bug because the information is already there, it is an enhancement. Wendy noted that a lot of the time Qwest fixes issues that a CLEC brings forwards through that team but in this case you were requesting something a bit bigger than simply a clarification or a bug fix. Liz Balvin/MCI stated that it is not an enhancement because the documentation is incorrect. Lynn Notarianni/Qwest stated that we are disagreeing about a gray area, one side views as an enhancement and one side views as a bug. Donna Osborne-Miller/AT&T stated that her consumer team is finding this a challenge, they are trying to work with a manual and are feeling the same frustration. Liz Balvin/MCI stated that she understands Qwest’s position to not look at every data field so agreed to change the CR. Liz stated that the guidelines are for Qwest to focus on documentation going forward. Judy Schultz/Qwest stated that there is a process for documentation issues when Qwest and the CLECs believe that it is a bug. Liz Balvin/MCI stated is for when Qwest believes it to be a bug. Judy Schultz/Qwest asked when it happens that something in the documentation that a CLEC sees as a defect and Qwest doesn’t, would it satisfy the CLECs if going forward as fields are impacted in the course of a release, the documentation would be changed going forward to adhere to those expectations. Sue Stott/Qwest stated that this is currently occurring. Liz Balvin/MCI stated that in reference to this CR, they were told to issue a CR., as well as for the other 2 CRs. Sue Stott/Qwest stated that where it gets gray is when further clarification is needed for a field. Liz Balvin/MCI stated that these items are not gray, they are adding valid values or formats. Sue Stott/Qwest stated that the bigger issue for IT documentation is Qwest has people working on the releases and when they get a request for a documentation update, the people have to be diverted from the release in order to do the documentation updates. Sue stated that maybe the answer is less capacity for a release. Judy Schultz/Qwest stated that she wants to make sure that we’re clear. Judy noted that if there were 200 different fields to update, that would be a big effort. Judy stated that she thought she heard that IT was going forward in trying to follow the proposed guidelines. Sue Stott/Qwest stated that IT does that today and noted that her concern is, if you are an EDI user you are not going to pay close attention to the new release right away and that Qwest will not be made aware of issues until much later. Randy Owen/Qwest stated that Qwest needs to be careful because you cannot update for some products and not all, that would create other problems. Randy stated that we need to look at updates across the board, maybe a legend should be developed. Liz Balvin/MCI stated that the EDI documentation is going to come along because you now have users. Liz noted that consistency is an excellent point, if you only do that on one field then it could create inconsistency. Liz stated that she liked the idea of a legend but would need to check with her coders to see if one would work for them. Liz stated that she could possibly only be looking at a specific field and would need a guide to tell her what to look at first. Judy Schultz/Qwest asked what if we do a running cheat sheet. Randy Owen/Qwest stated that we saw that this CR might take us there and started down that path. Then heard that is not what was wanted. Sue Stott/Qwest stated that we have to carefully scrutinize to ensure that a documentation change doesn’t also mean a system change. It is so tightly related, the difference can be as subtle as an and/or difference. Sue stated that is another reason why system resources are needed. Judy Schultz/Qwest stated that she understands that it is the same resources and is just trying to explore if IT can do a piece at-a-time. Judy asked if there are ever any times when it would be logical do to this kind of work. Is there ever a time in development when we could spend time doing this? Sue Stott/Qwest stated that it would still take systems resources to do that and stated that the issue is if it affects the voting capacity for a release. Sue stated that in many cases the same resources are used for coding and documentation. Liz Balvin/MCI asked if she could update the single source CR with a title change to ‘Guiding Principals to Qwest Documentation on Going Forward Basis, When Documentation Happens’, and will list the 10-items that you say you are using. Liz stated that the CR would then be moved back to Process and the documentation would be done when the regular document comes out. Liz stated that when new documentation comes out in future releases and sees that the guidelines are not being adhered to, and when it severely impacts her ability to do business then she would bring it forward. Liz stated that she would be willing to do that in order to get these off the table. Liz stated that she understands where Qwest is coming from and that believes that Qwest understands where she is coming from. Kit Thomte/Qwest asked how the guidelines would be updated. Liz Balvin/MCI stated that they would be closed with this CR and for other items that come up, new CRs would be issued. Donna Osborne-Miller/AT&T asked if they are to call the Help Desk if problems after in production. Randy Owen/Qwest stated that the documentation team is to be contacted if prior to 30 days after production, after the 30 days, you contact the Help Desk. Wendy Green/Qwest stated that we took the principles and looked at redesigning to be 1 document for both EDI and GUI. Wendy stated that she did not know if that is still on the table. Liz Balvin/MCI stated that that was not the intent of the CR. Lynn Notarianni/Qwest asked if the guiding principles are separate from SBCs document. Wendy Green/Qwest stated that within the current format, will use the 10 guiding principles. Judy Schultz/Qwest asked if we should have a ‘guiding principles’ standing agenda item to identify what can be removed from the list. Wendy Green/Qwest stated that things would never be crossed off the list because they are principles and are there forever. Liz Balvin/MCI shared Judy’s concern and stated that they just came across a situation where they reserved TNs in the GUI and submitted the order in EDI. The reps populated the PON manually, typing them in lower case, but went out the door in upper case. Liz stated that it is not documented that they have to be in upper case. Liz stated that it would be helpful to have a tab for Documentation Experiences/Discussion. Lynn Notarianni/Qwest stated that there is a tab for design walkthrough’s and we can have one for documentation. Lynn noted that it could have something in it, or not. Liz Balvin/MCI stated that she understands Qwests position and stated that she did not know that she could call the Help Desk for documentation issues, that is a value add from this discussion. Sue Stott/Qwest asked that instead of a standing agenda item or separate tab, maybe we could add documentation issues to the SATE portion of the meeting. Wendy Green/Qwest stated that that would be fine. Liz Balvin/MCI stated that it could be EDI/SATE. Liz Balvin/MCI stated that she would review her 3 CRs to see if they are guiding principles. Judy Schultz/Qwest stated that if Liz wants to close as a process CR, is ok with that as long as it is noted that Qwest does not agree that this is Process work. Judy stated that Qwest truly believes them to be systems requests. Liz Balvin/MCI stated that she was not clear on closing the CR as a Process CR. Judy Schultz/Qwest responded that that is what Liz wanted. Randy Owen/Qwest stated that the guiding principles can be closed, Qwest has adopted them. Judy Schultz/Qwest stated that when a CLEC submits a CR, Qwest looks at it and determines if it is an impact for Product/Process or Systems. Judy stated that Qwest would email the CLEC if the category is different. Judy asked if that was an acceptable way to communicate. Liz Balvin/MCI stated that she did receive emails and that she responded that she did not agree with the assigned category. Judy Schultz/Qwest asked that when the email is sent, what happens if we cannot reach agreement, how do we break that stalemate? Lynn Notarianni/Qwest stated that in that case, if a CLEC says it is a Product/Process CR and Qwest says that it is not, it could result in a denial based on infeaseability. Judy Schultz/Qwest stated that it could result in a denial. Liz Balvin/MCI stated that she would not be unreasonable. Lynn Notarianni/Qwest stated that she is just stating that it could be a risk. Liz Balvin/MCI stated that the stalemate is due to the category of product/process or systems, and stated that she thinks that we have flushed out why each of us believes the way we do. Liz asked if these CRs are going to remain as Process CRs as they were originally intended? Judy Schultz/Qwest stated that she is ok with the change back to Process and closing it out, with Judy adding a note that Qwest believes the CR to be a Systems change. Judy stated that she has an obligation to represent Qwest’s position. Judy stated that in the future, as CRs come in the door, my team will send out an email with the category, and if you don’t agree you need to let us know and we will call a meeting to discuss. Judy asked if that was acceptable to the CLECs. Liz Balvin/MCI said yes. Lynn Stecklein/Qwest asked how the CRs that are marked as both Product/Process are to be handled. Judy Schultz/Qwest stated that in some instances the CR may be both, could be a systems CR and an MN. Judy stated that if the CR is for both P/P and Systems, the CRPM would ask that separate CRs be issued. Lynn Stecklein/Qwest clarified that all 3 CRs will be crossed-over to Product/Process and will be closed. There were no additional questions or comments.


Open Product/Process CR PC022703-26X Detail

 
Title: Documentation update (valid date format)
CR Number Current Status
Date
Area Impacted Products Impacted

PC022703-26X Crossover
7/27/2009
UNE-P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Schultz, Judy
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest doesn't provide the valid date format in Developer Worksheet CSRR15 ORIGDATE.


Status History

4/18/03 CR submitted as P/P

5/6/03 Crossover CR created (See SCR022703-26


Project Meetings

4/17/03 CMP Systems Meeting An agreement was reached with the CLEC Community in the April CMP Systems Meeting on SCR0022703-26X (Documentation update - valid date format). This change request will be 'crossed over' to product and process and closed. Qwest agreed to 'cross over' this CR with the caveat that Qwest does not agree that this is Process work and believes it to be a system request.

4/17/03 CMP Systems Meeting Kit Thomte/Qwest stated that there is one more walk on to discuss regarding, from Liz Balvin. Liz Balvin/MCI stated that she was expecting a follow up call from Qwest last month and never got one. Kit Thomte/Qwest stated that nothing has changed in regard to this issue. Liz Balvin/MCI stated that WorldCom submitted process CRs and Qwest unilaterally processed them as systems CRs. Liz stated that if Qwest objected to MCI’s issuing these CRs as Process CRs, then Qwest needs to take this to the oversight committee. Kit Thomte/Qwest stated that Judy Schultz needs to address this issue and that Judy will be returning to the meeting after lunch. Liz Balvin/MCI stated that WorldCom wanted the CRs reverted back to Product/Process and sees that it was not done. Liz stated that she does not know if Judy is aware of that. Lynn Notarianni/Qwest stated that Judy is aware of your position on that. Lynn stated that from a standpoint of resolution, Qwest’s position is that we would not be escalating on ourselves on an issue that we feel that the decision was made congruent with how we’ve treated these types of issues in the past. Lynn stated that these CRs do need and take systems resources in order to do the work. Kit Thomte/Qwest recommended that we break for lunch and reconvene at 1:00 p.m. MT. Liz Balvin/MCI stated that WorldCom submitted 3 CRs as document changes and Qwest unilaterally changed them to systems CRs. Liz stated that this conversation has gone round and round. Liz stated that she tried to change the language back in December because she did not want these to impact IMA resources. Liz stated that the Qwest EDI implementation team changes documentation if Qwest finds a problem. Liz stated that if Qwest believes that WorldCom inappropriately sent these as Product/Process, Qwest needs to do something. Liz noted that any time there has been a cross over we’ve agreed to it in this forum and stated that she sees Qwest as out of process and doesn’t know how to better address that. Judy Schultz/Qwest stated that it is important to have this discussion and feels that we are at an impasse. Judy apologized if in the past Qwest has made unilateral decisions without communicating those decisions to change the CRs from Product/Process to Systems. Judy stated that Qwest is in the unique position of knowing which it should be and when there will be an impact to the systems. Judy stated that you might think it is just a process change, but we do know our internal systems and can say when a request would really impact a system. Judy noted that on the other hand, some changes come in as systems and we can look at it and determine that it would not require systems restraints and so we suggest crossing those CRs over to Product/Process. Judy stated that an email is sent to state if processed as a Product/Process or a Systems CR. Judy stated that the one issue that we are a little bit apart on is what to do with these systems documentation changes. Judy stated that in Section 8, which describes systems changes, the deliverables do include the system’s documentation, which is Sue’s (Stott) team. Liz Balvin/MCI stated that she agrees that the initial documentation to documented system enhancements per release should be included, but this is after it is implemented and a CLEC identifies a flaw with the documentation. Liz stated that in December, she said that the change was not intended to change existing documentation or previously existing versions, we just want issues addressed going forward. Liz stated that resources are required for new release documents, but once the document is used and a defect is identified, they should be corrected. Liz noted that the CLECs work with the EDI documentation team and when an issue is identified, that team fixes the problem. Sue Stott/Qwest stated that her team handles those in the same manner as a production support bug. Liz Balvin/MCI stated that these CR’s are for the issues that the EDI team said Qwest would not do as a bug fix. Wendy Green/Qwest stated that those were ones that Qwest viewed as enhancements rather than a bug in the documentation. Sharon Van Meter/AT&T asked if after a release is implemented and a bug is identified in the documentation, WorldCom sends an email to someone? Judy Schultz/Qwest stated that should go through production support. Liz Balvin/MCI stated that the production support help desk would not know this stuff. Liz Balvin/MCI stated that they do work with the EDI team and were told to issue these CRs. Wendy Green/Qwest stated that they are not a bug because the information is already there, it is an enhancement. Wendy noted that a lot of the time Qwest fixes issues that a CLEC brings forwards through that team but in this case you were requesting something a bit bigger than simply a clarification or a bug fix. Liz Balvin/MCI stated that it is not an enhancement because the documentation is incorrect. Lynn Notarianni/Qwest stated that we are disagreeing about a gray area, one side views as an enhancement and one side views as a bug. Donna Osborne-Miller/AT&T stated that her consumer team is finding this a challenge, they are trying to work with a manual and are feeling the same frustration. Liz Balvin/MCI stated that she understands Qwest’s position to not look at every data field so agreed to change the CR. Liz stated that the guidelines are for Qwest to focus on documentation going forward. Judy Schultz/Qwest stated that there is a process for documentation issues when Qwest and the CLECs believe that it is a bug. Liz Balvin/MCI stated is for when Qwest believes it to be a bug. Judy Schultz/Qwest asked when it happens that something in the documentation that a CLEC sees as a defect and Qwest doesn’t, would it satisfy the CLECs if going forward as fields are impacted in the course of a release, the documentation would be changed going forward to adhere to those expectations. Sue Stott/Qwest stated that this is currently occurring. Liz Balvin/MCI stated that in reference to this CR, they were told to issue a CR., as well as for the other 2 CRs. Sue Stott/Qwest stated that where it gets gray is when further clarification is needed for a field. Liz Balvin/MCI stated that these items are not gray, they are adding valid values or formats. Sue Stott/Qwest stated that the bigger issue for IT documentation is Qwest has people working on the releases and when they get a request for a documentation update, the people have to be diverted from the release in order to do the documentation updates. Sue stated that maybe the answer is less capacity for a release. Judy Schultz/Qwest stated that she wants to make sure that we’re clear. Judy noted that if there were 200 different fields to update, that would be a big effort. Judy stated that she thought she heard that IT was going forward in trying to follow the proposed guidelines. Sue Stott/Qwest stated that IT does that today and noted that her concern is, if you are an EDI user you are not going to pay close attention to the new release right away and that Qwest will not be made aware of issues until much later. Randy Owen/Qwest stated that Qwest needs to be careful because you cannot update for some products and not all, that would create other problems. Randy stated that we need to look at updates across the board, maybe a legend should be developed. Liz Balvin/MCI stated that the EDI documentation is going to come along because you now have users. Liz noted that consistency is an excellent point, if you only do that on one field then it could create inconsistency. Liz stated that she liked the idea of a legend but would need to check with her coders to see if one would work for them. Liz stated that she could possibly only be looking at a specific field and would need a guide to tell her what to look at first. Judy Schultz/Qwest asked what if we do a running cheat sheet. Randy Owen/Qwest stated that we saw that this CR might take us there and started down that path. Then heard that is not what was wanted. Sue Stott/Qwest stated that we have to carefully scrutinize to ensure that a documentation change doesn’t also mean a system change. It is so tightly related, the difference can be as subtle as an and/or difference. Sue stated that is another reason why system resources are needed. Judy Schultz/Qwest stated that she understands that it is the same resources and is just trying to explore if IT can do a piece at-a-time. Judy asked if there are ever any times when it would be logical do to this kind of work. Is there ever a time in development when we could spend time doing this? Sue Stott/Qwest stated that it would still take systems resources to do that and stated that the issue is if it affects the voting capacity for a release. Sue stated that in many cases the same resources are used for coding and documentation. Liz Balvin/MCI asked if she could update the single source CR with a title change to ‘Guiding Principals to Qwest Documentation on Going Forward Basis, When Documentation Happens’, and will list the 10-items that you say you are using. Liz stated that the CR would then be moved back to Process and the documentation would be done when the regular document comes out. Liz stated that when new documentation comes out in future releases and sees that the guidelines are not being adhered to, and when it severely impacts her ability to do business then she would bring it forward. Liz stated that she would be willing to do that in order to get these off the table. Liz stated that she understands where Qwest is coming from and that believes that Qwest understands where she is coming from. Kit Thomte/Qwest asked how the guidelines would be updated. Liz Balvin/MCI stated that they would be closed with this CR and for other items that come up, new CRs would be issued. Donna Osborne-Miller/AT&T asked if they are to call the Help Desk if problems after in production. Randy Owen/Qwest stated that the documentation team is to be contacted if prior to 30 days after production, after the 30 days, you contact the Help Desk. Wendy Green/Qwest stated that we took the principles and looked at redesigning to be 1 document for both EDI and GUI. Wendy stated that she did not know if that is still on the table. Liz Balvin/MCI stated that that was not the intent of the CR. Lynn Notarianni/Qwest asked if the guiding principles are separate from SBCs document. Wendy Green/Qwest stated that within the current format, will use the 10 guiding principles. Judy Schultz/Qwest asked if we should have a ‘guiding principles’ standing agenda item to identify what can be removed from the list. Wendy Green/Qwest stated that things would never be crossed off the list because they are principles and are there forever. Liz Balvin/MCI shared Judy’s concern and stated that they just came across a situation where they reserved TNs in the GUI and submitted the order in EDI. The reps populated the PON manually, typing them in lower case, but went out the door in upper case. Liz stated that it is not documented that they have to be in upper case. Liz stated that it would be helpful to have a tab for Documentation Experiences/Discussion. Lynn Notarianni/Qwest stated that there is a tab for design walkthrough’s and we can have one for documentation. Lynn noted that it could have something in it, or not. Liz Balvin/MCI stated that she understands Qwests position and stated that she did not know that she could call the Help Desk for documentation issues, that is a value add from this discussion. Sue Stott/Qwest asked that instead of a standing agenda item or separate tab, maybe we could add documentation issues to the SATE portion of the meeting. Wendy Green/Qwest stated that that would be fine. Liz Balvin/MCI stated that it could be EDI/SATE. Liz Balvin/MCI stated that she would review her 3 CRs to see if they are guiding principles. Judy Schultz/Qwest stated that if Liz wants to close as a process CR, is ok with that as long as it is noted that Qwest does not agree that this is Process work. Judy stated that Qwest truly believes them to be systems requests. Liz Balvin/MCI stated that she was not clear on closing the CR as a Process CR. Judy Schultz/Qwest responded that that is what Liz wanted. Randy Owen/Qwest stated that the guiding principles can be closed, Qwest has adopted them. Judy Schultz/Qwest stated that when a CLEC submits a CR, Qwest looks at it and determines if it is an impact for Product/Process or Systems. Judy stated that Qwest would email the CLEC if the category is different. Judy asked if that was an acceptable way to communicate. Liz Balvin/MCI stated that she did receive emails and that she responded that she did not agree with the assigned category. Judy Schultz/Qwest asked that when the email is sent, what happens if we cannot reach agreement, how do we break that stalemate? Lynn Notarianni/Qwest stated that in that case, if a CLEC says it is a Product/Process CR and Qwest says that it is not, it could result in a denial based on infeaseability. Judy Schultz/Qwest stated that it could result in a denial. Liz Balvin/MCI stated that she would not be unreasonable. Lynn Notarianni/Qwest stated that she is just stating that it could be a risk. Liz Balvin/MCI stated that the stalemate is due to the category of product/process or systems, and stated that she thinks that we have flushed out why each of us believes the way we do. Liz asked if these CRs are going to remain as Process CRs as they were originally intended? Judy Schultz/Qwest stated that she is ok with the change back to Process and closing it out, with Judy adding a note that Qwest believes the CR to be a Systems change. Judy stated that she has an obligation to represent Qwest’s position. Judy stated that in the future, as CRs come in the door, my team will send out an email with the category, and if you don’t agree you need to let us know and we will call a meeting to discuss. Judy asked if that was acceptable to the CLECs. Liz Balvin/MCI said yes. Lynn Stecklein/Qwest asked how the CRs that are marked as both Product/Process are to be handled. Judy Schultz/Qwest stated that in some instances the CR may be both, could be a systems CR and an MN. Judy stated that if the CR is for both P/P and Systems, the CRPM would ask that separate CRs be issued. Lynn Stecklein/Qwest clarified that all 3 CRs will be crossed-over to Product/Process and will be closed. There were no additional questions or comments.


Open Product/Process CR PC050503-3 Detail

 
Title: CEMR requests processed via the proper channels
CR Number Current Status
Date
Area Impacted Products Impacted

PC050503-3 Completed
1/21/2004
Repair
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: McBride, Kathy
Director:
CR PM: Harlan, Cindy

Description Of Change

If Qwest should receive a request for CEMR access that has not been processed through the designated CLEC representative, Qwest will reject the request and inform the requestor to go through their designated representative. As a result, the CLEC will have a complete update of all CEMR users and will be better equipped to maintain a current list and to notify Qwest of any changes or deletions. In addition, CLEC will be in a better position to notify users of any upcoming releases or changes to CEMR

Expected Deliverable:

That CEMR requests get processed via the proper channels


Status History

05/05/03 - CR Submitted

05/07/03 - Acknowledged CR

05/13/03 - Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/09/03 - Revised response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/5/03 - Held Ad Hoc meeting to review draft process

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/30/03 - Communicated with MCI and Vartech asking them for list of users for DC - sent spreadsheet for them to fill out to identify the users who need DC

11/17/03 - Sent user id list from MCI to IT to establish users

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/3/03 - Established partial list of users with Digital Certificates and user ids. Additional users in progress.

12/8/03 - Established list of users that were missed from the first list.

12/17/03 - Dec CMP notes will be posted to the database

12/29/03 - Provided list of existing users to account manager to validate and share with CLECs

1/21/03 - Jan CMP meeting minutes will be posted to the database


Project Meetings

January 21, 2004 CMP Meeting Liz Balvin – MCI advised this did get implemented in December. The forms are updated. They received the file to sync up their users. The list included users for all systems that have digital certificates. Liz asked how should they notify Qwest of users they want deleted from digital certificates, as the employee has left the business. Cindy Macy-Qwest asked Steve Kast-Qwest if he was aware of this process. Steve advised he is aware of how another CLEC has done this. There isn’t a place on the form to specifically identify deletions, but the CLEC just wrote it on the form and sent it to Qwest. Cindy Macy-Qwest advised she would double check this process and get back to Liz Balvin. Liz advised it is okay to change this CR to Completed Status.

December 17, 2003 CMP Meeting Liz Balvin – MCI advised Cindy Macy and I have been passing multiple emails working on getting users set up. Cindy Macy – Qwest confirmed that the notification went out and the process is effective December 22. Liz asked if it was okay to have multiple admin names as the point of contact for receipt of digital certificates. Cindy confirmed yes. Liz agreed to wait until the process is implemented on December 22 to submit additional users. Qwest was attempting to set up users manually prior to December 22. Cindy confirmed that this requires manual work to the user spreadsheet and that there is a possibility for error. The preferred method is to wait until the process is effective. This CR will move to CLEC test.

November 19, 2003 CMP Meeting Kathy McBride – Qwest advised the notification went out and the comment cycle closed today. Implementation is scheduled for December 3, 2003. Liz Balvin – MCI asked if this process includes allowing for a system admin as the common email address and a sync up of the database. Kathy McBride advised she would check on the ‘sync up of the database’ as she is not sure of that piece. Liz also asked about the list of user ids that she sent in and whether they were being set up. Cindy Macy – Qwest advised the list has been forwarded to our IT group to get the user ids set up. They have identified an ECOM server issue with accepting duplicate email ids. This issue is currently being investigated. Kathy McBride will follow up on these issues.

October 15, 2003 CMP Meeting Kathy McBride – Qwest advised we have concurrence from Security to issue the Digital Certificate to either a single point of contact designee for the CLEC or an individual user. Kathy advised she needs to check with the other systems that require a digital certificate to determine if there are additional system impacts. Kathy advised we are planning on issuing a Level 3 notification addressing the Digital Certificate form changes that are required. The form is used by the CLECs. The form will be updated to include the email address requirement for a designated single point of contact. Kathy explained if you have designated a single point of contact Qwest will verify it is the authorized person when a request for Digital Certificate is received. The requestor has to be either the designated person(s) or the end user that will be receiving the DC. Liz Balvin – MCI asked when this could be implemented. There is a substantial need for MCI to be able to get their end users access to CEMR. Monica Avila-Var Tech advised they have the same need. Kathy advised her target date is November 3 to have the Level 3 available for review. Bonnie Johnson – Eschelon asked is there was any way we could implement a workaround prior to the implementation date to address MCI and VarTech’s needs. Bonnie advised the CLECs should be able to work this with the Service Managers. Judy Schultz-Qwest advised we need to follow the CMP Process. Judy asked Dan Busetti – Qwest CEMR representative if CEMR could accommodate a faster implementation. Dan advised they could. Judy advised we would work this with Service Management and contact the help desk to have a trouble ticket issued. Pam DeLaittre advised Service Management will help get this resolved. Qwest will see what can be done to work this faster. Judy reviewed the Level 3 guidelines on Notification level change to determine what needed to be done. The team agreed if Qwest is able to handle this with a trouble ticket than we do not need to change the Notification level for the CR. This CR will remain in Development Status.

September 17, 2003 CMP Meeting Cindy Macy reported that a CLEC input meeting was held to review the process with the CLECs. A large number of CLECs attended the call. Kathy is currently working on the process and checking on the questions that were raised regarding whether Qwest can send the digital certificate to one email id in each company, opposed to a different email id per digital certificate. Liz Balvin-MCI explained their users are not able to use CEMR as they do not have their own email ids. Liz verified that her request is for Qwest to issue digital certificates to a single email id in their system administration group. Connie Winston and Dan Busetti said this is a security requirement that needs to be reviewed and not an application requirement. Cindy agreed she would schedule an internal meeting to discuss this further. Monica Avila – Var Tech advised her uses do not individual email ids either so they can’t use CEMR. This affects approximately 140 users in each company.

CLEC Ad Hoc Meeting September 5, 2003 PC050503-3 CEMR requests processed via the proper channels

In attendance: Jody Thompson – US Link Julie Pickar – US Link Jan Stys – MCI Steve Kast – Qwest Kim Issacs – Eschelon Jackie Debold – US Link Kathy McBride – Qwest Wayne Hart – Idaho PUC Cindy Macy – Qwest Brenda Davis – MCI Stephanie Prull – McLeod Liz Balvin – MCI Kim Webley – MCI

Cindy Macy – Qwest opened the meeting and reviewed the purpose of the call and agenda. The purpose of the call is to review the draft process for providing digital certificates to a designated contact in each company that chooses to participate.

Kathy McBride reviewed the draft process with the CLECs. Provide a list of all Digital Certificates that Qwest currently has to a designated person in each company (available tentatively in October). The CLECs would clean up the list and identify the designated contacts that would be able to request and receive digital certificate information on all systems (not just CEMR). If a request comes in from some one that is not designated or authorized, the request will be returned to the designate/authorized person.

Jody US Link advised they have received this already, it may have come from an individual request, not related to this effort.

Liz – MCI asked if the list would be in excel. Kathy – Qwest replied she believes so.

Liz – MCI advised they do not want to receive the list of digital certificates to ‘clean up’ until we have implemented the process. They do not want to ‘clean up’ their list more than once. Qwest agreed we would take that information into account in developing the process and timelines.

The suggestion was made that the 1st notification would ask the CLECs if they want to participate in this process, then the single point of contact would need to be identified.

Stephanie Prull – McLeod asked if this process would change the Company Profile. Kathy McBride advised this has not been determined yet.

Brenda – MCI asked if the Service Manager will be sent the single point of contact information. Kathy – Qwest replied they will have access to this information.

Liz – MCI explained that with IMA their own system administrators assign IMA passwords to their own employees. Liz wanted to know if this process would do that for CEMR digital certificates? Liz Balvin recapped that Stephanie Prull – McLeod said because CEMR currently doesn’t allow ‘administrative access’, McLeod doesn’t have the ability to administer user id and passwords (as is available via IMA today). Stephanie confirmed and said given the ability to do it for the systems that go by Digital Certificate we could support the system admin functions. But since the systems currently do not have the ability this is something we can not currently offer our internal users. Kathy – Qwest advised she would check but it doesn’t sound as if this is currently available. Cindy – Qwest advised if this is part of the request; to change CEMR to allow the CLEC to assign the user id and password, that would change the scope of the effort and we would have to relook at that. We will verify that CEMR does not allow the CLEC to assign their own user ids/passwords, but we will not change the scope at this time.

Liz-MCI explained the issue they are having is that they cannot use CEMR as the system requires the digital certificate user id/password to be emailed to the end user, not a single person, and the end users at MCI do not all have email ids. Liz would like Qwest to provide CEMR digital certificates to one designated email address and allow that email address to provide the user id/ password to the end user.

Kathy – Qwest advised she will provide status at the September CMP meeting.

** CMP Meeting 08-20-03

McBride-Qwest stated that Qwest is developing a process to implement the change and requested an ad hoc meeting with the CLECs to review the proposed process. She proposed September 4, from 1-2 PM MT. Balvin-MCI stated that she would contact White-Qwest if that time did not work for her.

=======================================================

CMP Meeting 07-16-03

White-Qwest presented the Qwest acceptance. Balvin-MCI stated that she wanted to be kept abreast of the development of the new process to request digital certificates. CR moved to Development.

========================================================== CMP Meeting 06-18-03

White-Qwest presented the Qwest response. He stated that because of the number of complex issues involved in developing a solution to this request, Qwest would like to move this CR into Evaluation status in order to provide a complete answer. He explained that Qwest will provide a status update at the July CMP meeting and will outline their response at that time. He asked that the CR be moved to Evaluation status.

========================================================== CMP Meeting 05-21-03

Balvin-MCI presented the CR. White-Qwest asked if other CLECs would like this request expanded to all systems that required digital certificates. Johnson-Eschelon and Van Meter-AT&T stated that they would. Mores-Electric Light Wave suggested Qwest sending digital certificates to only one group in each company. Johnson-Eschelon stated that this process would need to be different for each company. Isaacs-Eschelon stated that other ILECs (SBC) allowed the IT departments of the CLECs to have administrative privileges for the ILEC digital certificate system. This allowed the CLEC to control who in their company had digital certificates. Johnson-Eschelon and Zulevic-Covad suggested that Qwest service managers provide the CLECs with a list of digital certificate holders at some time interval. The other attendees agreed that this would be good because most digital certificate requests are provided to the service managers.

=========================================== Clarification Meeting 10:00 AM (Mountain Time) / Tuesday, May 13, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Kathy McBride – Qwest Jeanne Whisenant - Qwest Liz Balvin – MCI Jan Stys – MCI

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Stys-MCI reviewed the CR. She stated that in mid-April Qwest made change to the CEMR password and user-id process. She explained that MCI attempted to notify its internal employees of these changes and discovered that there were 300 MCI employees with digital certificates who the MCI IT group was not aware of. She stated that MCI employees were going directly to Qwest rather than going through the MCI IT group. She stated that MCI asked Qwest if their IT group could be copied on the e-mail that Qwest sent to the requestor when it issued the digital certificate. She stated that MCI needs a way to monitor and control the number of MCI employees who have digital certificates. She stated that MCI was trying to process all requests through their IT group. She stated that the internal MCI policy was for employees to go through the MCI IT group to get CEMR access and they were attempting to enforce the policy. White-Qwest asked how MCI employees are requesting digital certificates, if they are not going through the MCI IT group. Stys-MCI stated that she did not know. She stated that they may be using the wsst@qwest.com address. Balvin-MCI stated that she had requested CEMR access but was rejected, so there is some process for Qwest to control the access. White-Qwest asked how Balvin requested access. Balvin-MCI stated that she sent the form to wsst@qwest.com.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm MCI’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for MCI to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

Liz Balvin MCI

SUBJECT: Qwest’s Change Request Response - CR #PC050503-3

This is a revised response regarding MCI CR PC050503-3 (CEMR requests processed via the proper channels).

Qwest accepts this CR and proposes the following changes. Qwest will implement an internal process that will allow Service Managers to obtain a comprehensive list of all individuals within a CLEC company who currently possess a digital certificate. This list will also include the associated application access enjoyed by each certificate. This process will allow CLECs visibility of those individuals within each company who possess such access. Qwest proposes that this list be available beginning October 6, 2003.

In addition, Qwest will further define the process by which CLECs submit certificate requests. Qwest will develop a process wherein all CLECs may designate a single submission entity within each company.

Qwest will provide an update of the progress of this change at the August CMP Meeting.

Sincerely,

Kathy McBride Qwest

===================================================== June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, CMP Product/Process Meeting

Liz Balvin MCI

SUBJECT: Qwest’s Change Request Response - CR #PC050503-3

This is a preliminary response regarding MCI CR PC050503-3 (CEMR requests processed via the proper channels).

Because of the number of complex issues involved in developing a solution to this request, Qwest would like to move this CR into Evaluation Status in order to provide a complete answer. Qwest will provide a status update at the July CMP meeting and will outline their response at that time.

Sincerely,

Kathy McBride Qwest


Open Product/Process CR PC030503-2 Detail

 
Title: Enhance Qwest MDS/MDSI/MWI Document
CR Number Current Status
Date
Area Impacted Products Impacted

PC030503-2 Withdrawn
4/16/2003
Resale, UNE-P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Paxton, Mallory
Director:
CR PM: Harlan, Cindy

Description Of Change

WCom requests that Qwest enhance its document which identifies Qwest Central Offices equipped with Message Delivery Service Intraoffice (MDS) / Message Delivery Service Interoffice (MDSI) / Message Waiting Indicator (MWI) by adding the NPA values.

The document is currently available within Qwest’s SMDI Network Disclosure website (http://www.qwest.com/disclosures/netdisclosure366.html). The document does provide the NXX / Prefix value(s) associated with each listed Central Office and switch location, but does not include NPA data. This request is being submitted to have the NPA value(s) associated with the NXX / Prefix codes added.

Expected Deliverable:

None listed


Status History

03/05/03 - CR Submitted by World Com

03/06/03 - CR acknowledged by P/P CMP Manager

3/11/03 - Contacted World Comm to schedule Clarification Meeting

3/12/03 - Clarification Meeting scheduled for 3/17/03 11:00 - 12:00 am

3/17/03 - Clarification Meeting held

3/19/03 - March CMP Meeting minutes will be posted to the database

4/04/03 - Liz World Com advise she will withdraw this CR as they do not need NPA information on the report. They have determined they need CLLI code and that is already on the report. Changed status in database to pending withdraw.

4/16/03 - April CMP Meeting minutes will be posted to the database


Project Meetings

4/16/03 April CMP Meeting Minutes Liz Balvin agreed to withdraw this CR. Changed status to withdraw and closed 4/16/03.

3/19/03 March CMP Meeting Minutes Liz Balvin – World Comm reviewed and clarified the CR with the CLEC Community. Liz explained they would like NPA added to the document. ATT also supports this CR. This CR will move to Presented status.

Clarification Meeting March 17, 2003 11:30 –12:30 1-877-572-8687

CR PC030503-2 MDS/MDSI/MWI Update document with NPA Attendees Liz Balvin – World Com Becki Oliver – World Com Maureen Callan – Qwest Kelly Trachsel – Qwest Connee Moffatt – Qwest Mallory Paxton – Qwest Cindy Macy – Qwest Bill Woodworth – Qwest

Meeting Agenda 1.0 Introduction of Attendees Attendees Introduced

2.0 Review Requested (Description of) Change Becki Oliver and Liz Balvin reviewed and clarified the CR. World Comm explained they would like NPA added to the document. Having a column showing NPA would make the document more complete and helpful. WC uses this information to determine if MWI is a feature for their end user customers. WC is currently adding this information themselves by getting the data from the LERG and adding it to their own document.

Qwest asked if WC could determine this information as part of Pre-Order. WC advised this is a manual step before pre-order. Cindy Macy Qwest explained MWI feature is a CLEC feature. The MDS/MDSI is an ESP product offering, not a CLEC product offering. Liz Balvin advised they are also issuing a CR to ask for this document in Excel format, in addition to the PDF format.

3.0 Confirm Areas & Products Impacted MWI CLEC product offering

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation Add NPA to the document

6.0 Identify any Dependent Systems Change Requests Liz advised she has a systems CR SCR021403-01 that is asking for an update to IMA to have MWI reject up front and jep notification if order submitted but cannot provision MWI features. If MWI were not available the LSR would be rejected.

7.0 Establish Action Plan (Resolution Time Frame) Liz Balvin will present and clarify at the March 19 CMP Meeting Qwest will meet to determine our response


Open Product/Process CR PC031703-1 Detail

 
Title: Make MDS/MDSI/MWI Document Available in Excel Format
CR Number Current Status
Date
Area Impacted Products Impacted

PC031703-1 Completed
4/15/2009
Resale, UNE P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Paxton, Mallory
Director:
CR PM: Harlan, Cindy

Description Of Change

WCom requests that Qwest make its document which identifies Qwest Central Offices equipped with Message Delivery Service Intraoffice (MDS) / Message Delivery Service Interoffice (MDSI) / Message Waiting Indicator (MWI) available in Microsoft Excel format --in addition to the PDF format currently provided.

The document is currently provided within Qwest’s SMDI Network Disclosure website (http://www.qwest.com/disclosures/netdisclosure366.html) as a PDF download. The document in the PDF format permits a read-only use of the document, and therefore prohibits users from selecting and copying/pasting specific data elements for adding into another spreadsheet.

WCom needs the ability to select and copy/paste specific content of the document so that the data elements can be added to a WCom internal spreadsheet being created for determining MWI availability. Therefore receiving the Qwest document in an excel format will provide a copy of the document in a format that can be manipulated by CLECs for their own use.

This request asks Qwest to offer the document to CLECs in an excel format each time the document is updated; such that when notification is distributed that the PDF version on the website has been updated, an excel version (of the current document) could be provided to CLECs.


Status History

03/17/03 - CR Submitted by WorldCom

03/18/03 - CR acknowledged by P/P CMP Manager

03/21/03 - Contacted Customer to arrange for Clarification Meeting

03/25/03 - Clarification meeting scheduled for 3/28 Friday. OK per WorldComm.

03/28/03 - Held Clarification Meeting

04/03/03 - Sent Clarification Meeting notes to CLEC

4/16/03 - April CMP Meeting minutes will be posted to the database

5/9/03 - Notification will be send out 5-12 advising the document will be provided in excel format on the web site. Sent email to Liz Balvin to advise in advance.

5/13/03 - Document is available via web site

5/21/03 - May CMP Meeting Minutes will be posted to the database

6/18/03 - June CMP Meeting Minutes will be posted to the database. Agreed to close this CR at the June CMP Meeting.


Project Meetings

June 18, 2003 CMP Meeting Minutes - Liz Balvin agreed to close this CR. The report was provided in May.

May 21, 2003 CMP Meeting Minutes - Mallory Paxton – Qwest advised we have provided this document in Excel format and it is already available on the website. Notification was sent out and this CR was completed ahead of schedule. Liz Balvin thanked Mallory for her fast response. This CR will move to CLEC Test.

April 16, 2003 CMP Meeting - PC031703-1 Make MDS/MDSI/MWI Document available in Excel Format

Liz Balvin – MCI presented the CR to the CLEC Community. Liz advised they would like this report available in excel format. Liz advised she is hoping to get a response prior to the May CMP meeting. Qwest advised we will provide the response as soon as it is completed. This CR will move to presented status.

Clarification Meeting Friday March 28, 2003 1:00 – 2:00 p.m. MDT 1-877-572-8687 PC031703-1 MDS/MDSI/MWI Document in Excel format

Attendees Liz Balvin – World Com Lei Lani Heines – World Com Jeff Simons – World Com Mark Pollen – World Com Mallory Paxton – Qwest Connie Moffatt – Qwest Cindy Macy – Qwest

Meeting Agenda: 1.0 Introduction of Attendees Attendees Introduced

2.0 Review Requested (Description of) Change Liz and Lei Lani – World Com reviewed the CR. They advised the format is not very user friendly. They would like it available in Excel format also so they can manipulate and the use the data for their purposes.

Mark – World Com said the underlying document to the PDF file is an Excel spreadsheet. World Com would like to use the CLLI Code data on the spreadsheet. They thought they needed the NPA/NXX data but have determined they need the CLLI data. World Com will need to re-key all the data if they can’t get it in an excel spreadsheet. They are currently using the LERG to compare against this document and determine availability.

Qwest clarified there is another World Com CR that requests to have NPA data added to this document. Qwest asked if WC no longer needs the NPA data? Mark advised he is not aware if anyone else at World Com needs the NPA data. He can only speak to his part of this request and he does not need NPA data any longer. Liz agreed she would check to see if they could withdraw CR030503-2.

World Com advised they went to their Service Manager Pam O’Connell for this request and was advised to submit a CR.

Cindy Macy – Qwest asked if it is possible to provide this request where would World Com like the spreadsheet to be located? World Com advised their preference would be on the same web site location as the current PDF file.

3.0 Confirm Areas & Products Impacted Cindy Macy – Qwest explained that MDS/MDSI is an ESP product offering and MWI is a CLEC product offering.

4.0 Confirm Right Personnel Involved Yes

5.0 Identify/Confirm CLEC’s Expectation To have this document in an Excel and PDF format

6.0 Identify any Dependent Systems Change Requests CR PC030503-2

7.0 Establish Action Plan (Resolution Time Frame) Liz will present this CR to the CLEC Community at the April CMP Meeting Qwest will provide a response at the May CMP Meeting Liz said she would like us to provide our response at the April CMP Meeting. Cindy – Qwest advised the CMP Process does not support the response being required at the April Meeting. Liz asked if she requested an ad hoc meeting would Qwest be able to provide the response sooner? Cindy replied she was not sure the requirement of the ad hoc meeting, but she offered to check and see if Qwest can complete our response sooner, can we also provide the response before the May CMP meeting. Cindy did send Liz an email on 4-1-2003 advising her that if Qwest is able to complete the response sooner we will provide that to World Com, and not wait until the May meeting.


CenturyLink Response

May 14, 2003

For Review by CLEC Community and Discussion at the May 21, 2003, CMP Product/Process Meeting

Liz Balvin Carrier Management WorldCom

SUBJECT: Qwest’s Change Request Response - CR #PC031703-1

This is Qwest’s Response to WorldCom’s request to have Qwest provide its disclosure document Simplified Message Desk Interface (SMDI), located at http://www.qwest.com/disclosures/netdisclosure366.html, in Excel format.

This request is accepted. Effective the week of May 12, 2003, Qwest will provide this document on the web site referenced above in both PDF and Excel formats.

Because the Excel document can be updated by users, the PDF document will remain the primary source for Qwest data. Qwest respectively calls the attention of the CLEC community to the following disclaimer, which will be added to the web site:

“Please see the PDF download for switch detail in regards to this service. An Excel version containing the switch detail is also available, but Qwest will not be held responsible for any alteration of the Excel version and will refer to the PDF download as the primary source of data.”

Sincerely,

Mallory Paxton Senior Process Analyst Qwest Services Corporation


Open Product/Process CR PC041503-1CM Detail

 
Title: Add to section 4.0 TYPES OF CHANGE CLEC impacting defect
CR Number Current Status
Date
Area Impacted Products Impacted

PC041503-1CM Completed
8/29/2003
Pre Ordering, Ordering, Billing, Maintenance Rep
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: White, Matt
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Proposed language update to CMP document as follows:

Defect requests would be changes that correct problems discovered in production versions of an interface. These problems are where the interface is not working in accordance to the user requirements or the business rules published by Qwest. In addition, if functional requirements agreed upon by Qwest and the CLECs, results in inoperable functionality, even though software user requirements and business rules match; this will be addressed as a defect.

These problems typically affect the CLEC’s ability to exchange transactions with Qwest and may include documentation that is in error, has missing information or is unclear in nature. Defined severity levels and time frames for corrective action would be as follows:

o Severity 1 – Critical – Problem results in a complete system outage and/or is detrimental to the majority of the development and/or testing efforts. Correction of Severity 1 defects will occur within 3 days.

o Severity 2 – Serious – System functionality is degraded with serious adverse impact to the users and there is not an effective work-around. Correction of Severity 2 defects will occur within 10 business days following the date upon which Qwest’s defect validation process is scheduled to complete.

o Severity 3 – Moderate – System functionality is degraded with a moderate adverse impact to the users but there is an effective workaround. Correction of Severity 3 defects will occur within 30 business days following the date upon which Qwest’s defect validation process is scheduled to complete.

o Severity 4 – Cosmetic – There is no immediate adverse impact to the users. Correction of Severity 4 defects will occur within 45 business days following the date upon which BellSouth’s defect validation process is scheduled to complete. The CLEC and/or Qwest may initiate these types of changes affecting interfaces between the CLEC’s and Qwest’s operational support systems.

Detailed steps, accountable individuals, tasks, inputs/outputs and cycle times of each sub-process in the CLEC impacting defect type CR must be negotiated. This process will be used to validate defects, provide status notification(s), workarounds and final resolution to the CLEC community.

Expected Deliverable:

That the CMP document support language to address clec impacting defects (system and/or documentation) with corrective action timelines imposed.


Status History

04/15/03 - CR Received

04/17/03 - CR Acknowledged

05/21/03 - Presented at CMP Meeting

06/10/03 - Ad Hoc Meeting

07/08/03 - Held Ad Hoc Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

07/29/03 - Held Ad Hoc Meeting

08/01/03 - Qwest sent e-mail to John Berard, Phyllis Burt, Stephanie Prull, Jennifer Arnold, Bonnie Johnson

08/04/03 - Qwest sent notification CMPR.08.04.03.F.01540.RequestforResponse, written response to MCI proposed language

08/20/03 - CR discussed at August CMP Meeting

08/29/03 - Held Ad Hoc Meeting

09/04/03 - Qwest sent vote disposition, meeting minutes, and voting tally form, CMPR.09.04.03.F.01561.Vote_Disposition


Project Meetings

Ad Hoc Meeting Minutes PC041503-1CM Add to section 4.0 TYPES OF CHANGE CLEC impacting defect CMP Product & Process August 29, 2003 1-877-550-8686, Conference ID 2213337# 11:30 a.m. - 11:45 a.m. Mountain Time

PURPOSE

At the August CMP Meeting, participants agreed to hold a conference call to conduct voting on the proposed changes to Section 4.0 of the CMP. The following is the write-up of the discussion.

List of Attendees: Julie Pikar - U S Link Jen Arnold - U S Link Liz Balvin - MCI Bonnie Johnson - Eschelon Kim Issaacs - Eschelon Byron Dowding - Alltel Matt White - Qwest Steve Kast - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Matt White with Qwest explained that the purpose of the meeting was to vote on CMP CR PC041503-1CM. Matt explained that quorum is 6 and we have established quorum with 7 attendees. Matt asked if everyone was clear on what we were voting on and asked if anyone is uncomfortable voting out loud that they could e-mail their vote and he would arrange for cmpcr@qwest.com to be monitored to receive the vote.

The following votes were provided by meeting participants: MCI voted yes Eschelon voted yes U S Link voted yes Alltel voted yes

Matt read the e-mail votes: Allegiance voted yes McLeod voted yes Qwest voted no

Matt said the result of the vote is 6 - yes and 1 - no and said the standard for a vote on changing the CMP document is a unanimous vote, and because this vote was not unanimous, the changes will not be incorporated into the CMP. Matt said that he would provide notification of the vote disposition. Matt asked if there were any questions. No questions were asked.

CMP Meeting 08-20-03

White-Qwest provided an overview of the CR.

Notarianni-Qwest stated that the CLECs had provided redlining by inserting comments into the Qwest proposed language, rather than actually redlining the language. She stated that Qwest could adopt that style of inserting comments if the CLECs liked. She continued that the original MCI proposal contained four severity levels and associated timeframes for remedy. She stated that Qwest felt that the fixed timeframes were not workable and did not account for the fact that each different problem required a different level and length of effort to evaluate and solve. She stated that Qwest was committed to working expeditiously to meet the timeframes as much as is possible, but she could not commit Qwest to working too quickly in an effort to meet an arbitrary timeframe unrelated to the complexity of the issue. She explained that this course could too easily lead to errors. She continued by stating that the CLEC response contained no flexibility that would allow Qwest to adequately meet problems with varying scope and complexity. She stated that Qwest was willing to readdress the validation timeframe as long as the CLECs were willing to grant Qwest some flexibility and outline what that flexibility would look like. If this was the case, she recommended another ad hoc meeting. She explained that if the CLECs were unwilling to incorporate more flexibility into the language then Qwest was prepared to vote on the change as MCI had submitted it.

Balvin-MCI stated that the CLECs are 100% impacted by interface flaws. She stated that the CLECs worked hard to propose timeframes that attempted to accommodate Qwest’s needs but, without constraints, Qwest is not guaranteeing anything in its software.

Johnson-Eschelon discussed the LR form issue. She stated that this was a good illustration of why this defect language was needed. She stated that Qwest had done a very poor job of keeping her informed of the status of this fix. She stated that if Qwest was going to deny this request, she wanted it to deny it soon, so the CLECs could escalate.

Balvin-MCI stated that she was prepared to vote. She stated that the situation was at an impasse. She stated that Qwest wanted an out at every level. To illustrate her point, she read from the Qwest proposed language:

Severity Level 2 Production Defect

Qwest will either:

? Fix this trouble within 10 business days, or ? Issue an event notification, within 10 business days, announcing a date by which the trouble is scheduled to be fixed, or ? Issue an event notification, within 10 business days, announcing a date by which Qwest will announce a date by which the trouble is scheduled to be fixed.

Balvin-MCI stated that this language allows Qwest 30 business days, which is unacceptable.

Osborne-Miller-AT&T stated that she concurred.

Notarianni-Qwest stated that Qwest was prepared to vote. She stated that Qwest did not want an out at every level; instead, Qwest took severity levels seriously and scheduled fixes as expeditiously as possible. She stated that Qwest has provided updates to the LR form issue in the form of Event Notifications with patch dates. She stated that the current production support process is working as it was designed. She explained that Qwest had proposed language that afforded it an opportunity to address problems of various complexity and scope. She stated that Qwest does not want to be in a position to throw software out just to meet a date; instead, Qwest wants to fix problems the right way.

Balvin-MCI stated that she would like Qwest’s position in writing. She stated that the CLECs would seek arbitration.

Notarianni-Qwest stated that she had already provided her position both in writing and in the minutes of this call.

Johnson-Eschelon asked that the team just vote on a document so the CLECs could escalate.

Balvin-MCI suggested that the team vote on the original MCI proposal.

White-Qwest pointed out that the original proposal was missing discussion of the validation period, that was central to the Bellsouth process, and the proposed language still contained a reference to Bellsouth.

Balvin-MCI asked that White replace all occurrences of “Bellsouth” with “Qwest.”

White-Qwest stated that the vote would probably be on 8/29.

=========================================================

August 4, 2003

Announcement Date: August 4, 2003 Effective Date: Immediately Notification Number: CMPR.08.04.03.F.01540.RequestforResponse Notification Category: Change Management Notification Target Audience: CLECs, Resellers Subject: CMP - REQUEST FOR QWEST WRITTEN RESPONSE PC041503-1CM Associated CR # or System Name and Number: MCI CR# PC041503-1CM The purpose of this notification is to provide additional information on MCI CR# PC041503-1CM. A call was held July 29, 2003 to discuss the MCI originated request to add Defect Language to the CMP Document. Several participants at the July 29, 2003, ad hoc meeting requested that Qwest provide the written position on the proposed language. Per MCI's request during the meeting, below is Qwest written response indicating our concern with the CLEC request for 'Defect' language requiring resolution of all severity levels by certain timeframes. As was stated in the ad hoc meeting, Qwest does not believe that a fixed timeframe commitment for the severity levels, particularity the timeframes proposed by the joint CLEC community is practicable. Not all software issues are of the same magnitude and level of complexity. While a particular issue may involve a simple software fix, there are times when the production support team must go through an extensive development cycle to get a fix implemented, and/or may require that fixes be coordinated between multiple systems. In such cases and possibly for other reasons, Qwest would not necessarily be able to meet the fixed timeframe. Qwest's initial proposal back to the CLECs achieves not only flexibility to handle difficult issues in a responsible way, but also will make Qwest accountable to set forth timeframes. Qwest understands that some CLECs disagree with this language. Qwest would continue to ask that the joint CLEC community provide a red-line version of the language that they believe would accomplish their objectives and provide Qwest the flexibility necessary to adequately address problems when they arise. CR PC041503-1CM is contained in the Product Process Interactive Report posted to the Qwest Web site at http://www.qwest.com/wholesale/cmp/changerequest.html. If you have any questions or comments about this notification, please contact Linda Sanchez-Steinke, Qwest CRPM Manager, at linda.sanchez-steinke@qwest.com or 303-965-0972. Sincerely,

Qwest

Fri 8/1/03 5:02 PM From: Linda Sanchez-Steinke To: jberard@covad.com, phyllis.burt@att.com, stephanie.prull@mcleodusa.com,jennifer.arnold@uslink.com; bjjohnson@eschelon.com All,

The following is Qwest's response to MCI’s Defect Language:

A call was held July 29, 2003 to discuss the MCI originated request to add Defect Language to the CMP Document. Per MCI’s request during the meeting, below is Qwest written response indicating our concern with the CLEC request for ‘Defect’ language requiring resolution of all severity levels by certain timeframes.

As was stated in the ad hoc meeting, Qwest does not believe that a fixed timeframe commitment for the severity levels, particularity the timeframes proposed by the joint CLEC community is practicable.

Not all software issues are of the same magnitude and level of complexity. While a particular issue may involve a simple software fix, there are times when the production support team must go through an extensive development cycle to get a fix implemented, and/or may require that fixes be coordinated between multiple systems. In such cases and possibly for other reasons, Qwest would not necessarily be able to meet the fixed timeframe.

Qwest’s initial proposal back to the CLECs achieves not only flexibility to handle difficult issues in a responsible way, but also will make Qwest accountable to set forth timeframes.

Qwest understands that some CLECs disagree with this language. Qwest would continue to ask that the joint CLEC community provide a red-line version of the language that they believe would accomplish their objectives and provide Qwest the flexibility necessary to adequately address problems when they arise.

If you have any questions, please call me.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-965-0972

Ad Hoc Meeting Minutes PC041503-1CM July 29, 2003 1-877-550-8686, Conference ID 221337# 10:00 a.m. - 10:30 a.m. Mountain Time

PURPOSE

At the July 8, 2003 Ad Hoc CMP Meeting for PC041503-1CM, participants agreed to collectively red-line the Qwest proposed language to Section 12 Production Support and hold a subsequent ad hoc conference call to discuss MCI comments to the Qwest proposed language.

The following is the write-up of the discussions, action items, and decisions made in the working session.

List of Attendees: Liz Balvin - MCI John Berard - Covad Phyllis Burt - AT&T Stephanie Prull - McLeod Jen Arnold - U S Link Kim Isaacs - Eschelon Bonnie Johnson - Eschelon Lynn Notarianni - Qwest Connie Winston - Qwest Beth Foster - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

Lynn Notarianni with Qwest said that we have received comments back on the Qwest proposed language changes to Section 12 and have reviewed the comments the CLECs included. She noted that if there was no movement in some areas, then she proposes that we have language finalized and move to the vote. She indicated that the first CLEC Comment around addressing "inoperable functionality" was discussed on the first meeting to review this CR. Lynn read from the original language of the MCI proposal and recapped: even though software user requirements and business rules match; this will be addressed as a defect. Lynn said that Qwest’s original position on this is the same, that Qwest would not consider this a defect, as it would be functionality working as designed.

Liz Balvin with MCI said these types of inoperable functionality can happen and the CLECs need to have them addressed.

Lynn Notarianni with Qwest asked for further definition of "inoperable functionality". She asked the CLECs to provide proposed language to specify what the CLECs were talking about as the language provided in the original CR is too broad.

Liz Balvin with MCI said "inoperable functionality" means CLECs can’t submit an LSR and can’t pass orders.

Bonnie Johnson with Eschelon said it’s when the CLECs can’t submit an order because of an error on Qwest’s side. We are talking about Eschelon not being able to submit an electronic LSR, we are talking about others can’t submit electronic LSRs, and MCI can’t submit an electronic LSR.

Lynn Notarianni with Qwest said that maybe Qwest didn’t understand inoperable functionality as it was written in the Bell South Documentation. She reviewed the Bell South language that was originally submitted by MCI: "These problems are where the interface is not working in accordance to the user requirements or the business rules published by Qwest. In addition, if functional requirements agreed upon by Qwest and the CLECs, results in inoperable functionality, even though software user requirements and business rules match". Lynn Notarianni with Qwest noted that what she is hearing the CLECs talking about was when CLECs are unable to get an LSR into Qwest’s system.

Liz Balvin with MCI and Bonnie Johnson with Eschelon agreed with Lynn Notarianni’s statement.

Lynn Notarianni with Qwest said that Qwest will take a look at that.

Lynn Notarianni with Qwest noted that the second area that needs to be addressed is the timeframe for fixing ‘defects’ based on the severity levels. Qwest has proposed language to commit as best we could to the proposed timeframes the CLECs provided, and the proposed language also allowed for flexibility for fixing those trouble tickets that are larger in scope. The CLECs had agreed to review the language and come back with proposed changes of their own, and what the CLECs provided was their original language with no changes at all.

Liz Balvin with MCI said that the intent of the comment is that CLECs need specific timeframes for resolution and felt that Qwest didn’t provide any resolution timeframes at all.

Lynn Notarianni with Qwest said that we did come back with a proposal, for example, with a Severity 2 ticket where the issue is simply an edit change, then Qwest can fix within 10 days. However, often times a ticket may involve other downstream systems and could take more than 10 days. Lynn said that she is hearing the CLECs think Qwest did not come far enough, but asked if the CLECs can move off the timeframes for resolution in the Severity Levels; 3 business days Severity Level 1, 10 business days Severity Level 2, 30 business days Severity Level 3 and 45 business days. Lynn asked if the CLECs could provide back language indicating where they would be willing to budge on proposed timeframes.

Liz Balvin with MCI said that the CLECs want proposed timeframes for fixing defects and Qwest has proposed nothing, what Qwest has proposed is a way out of every situation. Liz asked what Qwest thinks ‘immediately’ means. By Qwest not giving a timeframe for a fix for a system outage, CLECs are out of the water if Qwest has done something wrong.

Lynn Notarianni with Qwest said that immediately means as soon as possible. Lynn said that Severity 1 issues are not where we should be focusing this discussion. She noted that Qwest is covered with the System availability PID and asked if it would be more appropriate to have the real focus on Severity Level 2 and Severity Level 3.

Liz Balvin with MCI asked if Qwest was agreeing to a timeframe for Severity Level 1.

Lynn Notatrianni with Qwest replied that she was not agreeing to a time frame, she said that Qwest is on top of Severity Level 1 and are meeting PIDS for availability of systems and it really seems like the Severity Level 2 is where impacts are.

Liz Balvin with MCI asked if Qwest will impose a time frame on Severity Level 1.

Lynn Notarianni with Qwest said that availability for systems makes Severity Level 1 a non-issue.

Liz Balvin with MCI said that if Qwest is meeting the PIDs, then it wouldn’t be an issue, but she would still like Qwest to impose timeframes on the other Severity Levels.

Lynn Notarianni with Qwest said that Qwest proposed what we thought we could do and now need to know how far the CLECs can go other than the 10 days they have proposed for Severity Level 2’s, allowing Qwest flexibility to determine the problem and negotiate the timeframe. Lynn noted that Qwest has provided what we truly believe can be done. She noted that Qwest is looking for language from the CLECs that proposes an alternative that they can live with.

Liz Balvin with MCI said that in situations where there is defect, it is not working as intended, Qwest built the interface and won’t guarantee anything as far as a fix time. Leaving the wording open-ended leaves the CLECs out of the water.

Lynn Notarianni with Qwest said that while she was not involved in the Re-Design process, it was her understanding that the current language was put together and all parties agreed to it at that time. Now you are saying that you want tighter language. If CLECs are able to move off the fixed timeframe of days currently proposed then Qwest would be interested in seeing their proposed language. If the CLECs are not willing to move away from their originally proposed language, then it is time to finalize the language and take a vote.

Bonnie Johnson from Eschelon asked if Qwest would vote no to the originally proposed language.

Lynn Notarianni with Qwest responded that a vote of no would likely be the result if there was no change to the original language proposed by MCI.

Bonnie Johnson from Eschelon said there are significant impacts and Qwest is saying they don’t care about the impact on the CLECs company.

Lynn Notarianni with Qwest stated that she would not try to dismiss Bonnie’s comment as she knows that Qwest can see our internal process and we know how hard the teams work to push through the changes to get fixed. She said that she knows the CLECs cannot see our internal process and have no way of knowing how hard Qwest works internally on issues to get them to resolution.

Liz Balvin with MCI re-read the Severity Level 2 wording "will occur within 10 business days following the date upon which Qwest’s defect validation process is scheduled to complete." She noted that this is talking about the time period after validation of a defect.

Lynn said that sometimes we have to go through the lifecycle and re-write and validate in the business rules and it is likely that the process will take more than 10 days. She noted that there are times when the production support team must go through an entire development cycle to get a fix implemented, impacting and coordinating multiple systems, and in cases like that there would be no way for Qwest to meet the timeframes put forth by the CLECs in their original proposal.

Connie Winston said that when problems impact the front end systems like IMA, it could be due to day to day impacts and be easy to quickly back out the problem and always focus on the front end. If the problem is in the billing systems sometimes we have to dig deeper and determine a good time to make changes and that is where we struggle with the 10 business days.

Bonnie Johnson with Eschelon said the CLECs need to discuss this further as a community.

Liz Balvin with MCI said that she doesn’t see Qwest making any movement toward the CLEC proposal.

Bonnie Johnson with Eschelon agreed with Liz Balvin and mentioned the problems with hunting, needing to submit another CR, and having to wait for 2 releases in order to get a fix for it.

Liz Balvin with MCI said Qwest is proposing no guarantees to CLECs on the software they provide to the CLECs but instead is providing themselves a way out.

Lynn Notarianni with Qwest said that Qwest did make a proposal back to CLECs and if there is a different way to meet the CLECs needs, Qwest would be happy to review it. If the CLECS could come with a proposal that you think you can live with, Qwest would review it. Lynn also said there are other areas in the proposed language that Qwest would like to discuss, but unless we can get past the larger issues then there seems to be no need to discuss those areas.

Liz Balvin with MCI asked that Qwest provide their written position to the CLEC comments as discussed on this call. She noted that the CLECs position is that Qwest needs to commit that they will guarantee the software they provide and right now Qwest is guaranteeing nothing.

Lynn Notarianni with Qwest said Qwest would provide their response to the CLEC comments by the end of the week.

Linda Sanchez-Steinke with Qwest asked if there were any additional comments. No comments were made.

July 8, 2003 - CMP Ad Hoc Meeting PC041503-1CM

Attendees Matt White - Qwest Lynn Notarianni - Qwest Beth Foster - Qwest Kit Thomte - Qwest Connie Winston - Qwest Liz Balvin - MCI Kim Isaacs - Eschelon Bonnie Johnson - Eschelon Donna Osborne-Miller - AT&T Sharon Van Meter - AT&T Carla Pardee - AT&T Mike Zulevic - Covad Lori Mendoza - Allegiance

Balvin-MCI asked Qwest to describe the proposed language. White-Qwest described the process Qwest used to create the proposed language. Notarianni-Qwest stated that Qwest tried to maintain the intent of the existing Production Support language while outlining these additional activities. She stated that this language also addresses the unpredictability of defects. She stated that Qwest focused on Severity 2 and Severity 3 troubles because Severity 1 troubles already have an effective process and Severity 4 troubles are essentially enhancements.

Balvin-MCI stated that the proposed warrantee period was too short for both GUI and EDI migrations. Notarianni-Qwest stated that the most efficient manner of conveying the CLEC’s issues might be to redline the Qwest proposed language. Balvin-MCI agreed.

Balvin-MCI stated that Qwest’s language did not address documentation flaws. She stated that these occur when Qwest changes language to more accurately reflect the way a system is really working. She also explained that she felt the proposed language was appropriately placed in Section 12.0, but that it placed too much burden on the CLECs to identify problems and validate that the trouble was a defect. She continued that she was not satisfied that the Qwest internal validation period was not bounded by a time constraint and that there is no discussion of how soon Qwest must request additional information from the CLECs.

Johnson-Eschelon stated that the warrantee period was too short for EDI and GUI users. She stated that the language also did not address issues like those faced in Hunting discussion. She explained that this was when the documentation agreed with the system, but that the system was not changed in such a manner that addressed the accepted CR. Notarianni-Qwest stated that there would be an edit for alpha and the system was working as written, but it broke the business. The issue is if it’s documented a certain way, and it’s acting the way it’s been documented, but it is not functional. Balvin-MCI added that it is also an issue if the change request was not implemented as requested, and provided Migrate as Specified as an example. Notarianni-Qwest asked if this was an issue for a defect discussion, or a question of how explicit CR descriptions and clarification calls must be. She asked if we need to get into more detail in clarification calls to make sure everyone is on the same page. She noted that there seems to be more of an issue of being more specific in the detail of the CRs. She stated that this are would be more difficult to get agreement on as far as getting the language written and agreed to. She indicated again that it would be most beneficial if the CLECs would take the language and provide their red-lines to provide their thoughts on how to make this work.

Balvin-MCI stated that each of the severity level descriptions in the proposed language gave Qwest an “out.” She stated that this language did not require an appropriate level of urgency. She stated that CLECs wanted immediate results and dates that Qwest would repair the defect. Notarianni-Qwest stated that this language was proposed because not all trouble tickets are similar; some require extensive checking through downstream systems, checking that cannot be done in such a short period of time. She added that Qwest would not want to agree to a timeline and then not be able to meet it. Osbourne-Miller-AT&T agreed with Balvin that the CELCs need definitive dates for fixing defects. Balvin-MCI stated that Bellsouth’s language did not include escape language like Qwest’s. She stated that this language needed to focus more on identifying the root cause of the trouble. She noted that longer timeframes for analysis could be looked at, but once the cause is identified, the CLECs should get an implementation date immediately. Notarianni-Qwest stated that she was not aware of how Bellsouth structured their efforts to comply with their obligations. Balvin-MCI stated that the language was too open-ended. She stated that the second to the last paragraph was also inappropriate because it inferred that Qwest would punish the CLECs for Qwest’s mistake. Notarianni-Qwest stated that Qwest added that paragraph because there could be situations where Qwest had to divert specialized resources to meet defect obligations. She added that this was also part of the reason that Qwest included the warrantee language, in order to assure that we don’t impact later cycle development efforts for the next version of the release

Balvin-MCI stated that she would like to provide redline comments. She stated that this language provided Qwest too many outs. She stated that she appreciated Qwest’s effort to prepare this language and that it was far more than she had expected. Notarianni-Qwest stated that she wanted to address Balvin’s point about the CLECs having to prove that the issue was a defect. She stated that Qwest’s intent was not to force the CLECs to prove defect status, but to ensure that Qwest had all possible information on what was being impacted to make the determination during the internal validation.

The group discussed how to proceed and agreed that the CLECs would collectively redline the proposed language and send it to White-Qwest. He would then issue a notification for a subsequent Ad Hoc Meeting. The meeting was adjourned.

================================================= CMP Meeting 06-18-03

White-Qwest gave a status of the CR. He stated that the Ad Hoc meeting would be held on 7/8. ================================================== Ad Hoc Meeting - 06-10-03

Attendees Matt White - Qwest Beth Foster - Qwest Lynn Notarianni - Qwest Sharon Van Meter - AT&T Donna Osborne Miller - AT&T Carla Pardee - AT&T Liz Balvin - MCI Lori Mendoza - Allegiance Kim Isaacs - Eschelon Bonnie Johnson - Eschelon

White-Qwest reviewed the purpose of the meeting and asked Balvin-MCI to review the purpose of the CR. Balvin-MCI reviewed the CR. She stated that it was an attempt to refine the process for what happens when something doesn’t work. She stated that if there is an identified problem, then Qwest should have to fix in a certain period of time. She stated that the Bellsouth process was more clearly defined that the Qwest CMP. White-Qwest asked how Bellsouth handled the “internal validation” process described in their CCP document and how they interpreted the “inoperable functionality” description. Balvin-MCI stated that this constitutes a system that is so flawed that there is no functionality. Notarianni-Qwest asked if that was similar to a Qwest CMP Production Support Level 1. Balvin-MCI stated that was correct. She continued that when a CLEC submits a CR to Bellsouth, Bellsouth validates that it is a defect. She stated that if Bellsouth does not agree that the CR is a defect, there is some give and take. She stated that there needs to be language in the Qwest CMP outlining a process to quickly fix defects.

Johnson-Eschelon stated that she had examples of what constituted defects. She described a situation involving hunting problems waiting to be fixed until the next release and a blocking work around that was a temporary fix to a system defect. She stated that there needs to be a clearer definition of when something is system defect vs. not. Notarianni-Qwest asked if these would be Level 2’s in Bellsouth’s language. Johnson-Eschelon stated that they would. Notarianni-Qwest asked how the CLECs would approach changes that occurred as a result of defects and that also caused development changes. She stated that these could constitute code impacting changes and that they could impact other CLECs as well as disrupt the development cycle. Balvin-MCI stated that there were really two kinds of defects. (1) When the system was not operating the way the business rules stated it should be and (2) when the system was operating in the way Qwest designed it, but the business rules were written in a way that caused the CLECs to code differently. She stated that the latter instance would be the one that caused CLECs development difficulty. Notarianni-Qwest asked if CLECs would want a short resolution timeframe for the former and a longer timeframe for the latter. Balvin-MCI agreed. Notarianni-Qwest asked if the CLECs could provide Qwest with examples of each defect severity from the other ILECs. She stated that Qwest’s attempts to get this information from Bellsouth had not been very successful. She stated that Qwest would like to understand how Bellsouth is implementing this and managing it without upending the current processes and lifecycles of development. Balvin-MCI agreed to look at providing some examples. Johnson-Eschelon stated that she would like Qwest to propose language that would work using the two examples she provided. Notarianni-Qwest stated that she was not familiar with the Hunting issue. She stated that the bottom line is that these types of changes will drain development resources and pull resources away from the development work required for major releases. She continued that the conclusion the team needed to arrive at was when these changes should impact other CLECs and when they should not. She asked if it was more important to the CLECs to establish a consistent timeframe for each problem, or that Qwest issue a negotiable commitment after uncovering the root of a problem. She stated that she was trying to avoid situations where there could be disagreements about an issue’s treatment. Balvin-MCI stated that she would be amenable to a range of days. She stated that the CLECs would want a ‘no later than’ date for fixes. She asked Qwest to propose language. Notarianni-Qwest stated that she would take that request back internally and discuss it further with the team. She reiterated that Qwest would like the CLECS to send some examples (of both Qwest issues and ILEC issues). She stated that Qwest must also consider a number of parts of the CMP document that such changes may impact. She stated that she would ask internally if Qwest was willing to commit to timeframes for fixing production issues and, if so, what timeframes Qwest could commit to. The team agreed that Qwest would issue proposed language with an Ad Hoc Meeting Notification on July 1, and that the Ad Hoc Meeting would occur on July 8. Balvin-MCI asked that if Qwest was ultimately going to deny this request, they indicate that intent as soon as possible. Notarianni-Qwest stated that would be her expectation, should that be the case.

=====================================================

05-21-03 CMP Meeting

Balvin-MCI presented the CR. White-Qwest stated that he would schedule an Ad Hoc Meeting. Balvin-MCI stated that the CLECs would like to see the Qwest proposed language before the meeting. She asked that the meeting be on 6/9 or 6/10.


Open Product/Process CR PC111303-1 Detail

 
Title: Allow multiple Billing Account Numbers Per Product Per State
CR Number Current Status
Date
Area Impacted Products Impacted

PC111303-1 Denied
1/21/2004
UNE - P
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Kriebel, Sue
Director:
CR PM: Andreen, Doug

Description Of Change

Qwest currently only supports a single BAN per product per state. MCI requests the ability to designate multiple BANs per product, per state. In doing so, the CLECs would have the ability to track orders submitted by different divisions of their company.

Expected Deliverable:

Determine whether a process change only is necessary whereby the CLECs would be required to populate differing BANs on each order. Otherwise, what system enhancements would need to be made to support.


Status History

11/13/03: CR Received

11/14/03: CR Acknowledged

11/25/03 - Held Clarification Meeting

11/25/03: Status Changed to Clarification

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Presented

01/14/04 - Response posted

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Development

2/2/04 - Qwest generated notice CMPR.02.02.04.F.01317.AdHocBillingMtg

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

03/17/04 March CMP Meeting Randy Owen, Qwest reported on the two open action items for this CR. First he reported that the edits will be removed from the alternate BAN field on March 19 and that CLECs could use this field as they see fit. On the second action item concerning providing more information on denial responses Randy reported that they are moving forward with examples and would provide an opportunity to discuss once the examples are available. The CR will remain in Denied status.

-- 2/18/04 CMP Meeting

Sue Kriebel reviewed the action item concerning the examples from Cbeyond that carried non-active BAN numbers. Sue clarified the issue by stating that not all orders are assigned BANs automatically but only those that go through flow through. It was uncovered that orders manually typed were having BANs assigned incorrectly in some cases. She is working with the centers to correct. Stephen Calhoun, Cbeyond asked about the issue of the CLECs being able to use the alternate BAN field as they wished. Doug Andreen, Qwest said that was still being researched. Connie Winston, Qwest is looking into dropping existing edits of a formatting nature that now exist in the system. The CR will remain in development.

Ad Hoc Meeting Minutes PC111303-1 Allow multiple Billing Account Numbers Per Product Per State CMP Product & Process February 12, 2004 1-877-521-8688, Conference ID 1456160 9 a.m. – 10a.m. Mountain Time

PURPOSE This meeting was to discuss action items from the January CMP Product and Process meeting, specifically: 1. Cbeyond examples were old BANs have been populated 2. Cost backup to the denial so CLECs can pursue other avenues 3. Can CLECs use optional BAN field as they wish

List of Attendees: Kathy Stichter, Eschelon T.J. Koller, Priority 1 Liz Balvin, MCI Bonnie Johnson, Eschelon Kim Isaacs, Eschelon Jan Arnold, U S Link Carla Pardee, AT&T Stephan Calhoun, Cbeyond John Gallegos, Qwest Connie Winston, Qwest Lydell Peterson, Qwest Sue Kriebel, Qwest

MEETING MINUTES The meeting began with Qwest making introductions and welcoming all attendees.

The meeting was called to discuss three outstanding items from the last CMP meeting: 1. Cbeyond examples where old BANs have been populated (Sue Kriebel) 2. Cost backup to the denial so CLEC can pursue other avenues (John Gallegos) 3. Can CLECs use optional BAN field as they wish (Connie Winston)

Issue 1.

Sue Kriebel, Qwest stated that on the list from Cbeyond that not all products go through the FTS (flow through system) and have BANs automatically assigned. On the Cbeyond list several orders had been marked for manual handling and it was found that the control point not in place was to ensure that the person manually handling the order assigned the correct – active BAN.

Stephan Calhoun, Cbeyond said that this more clearly explained why some orders were assigned BANs that were not expected. He feels that responses should initially carry this level of detail and thanked Qwest for the research

Liz Balvin, MCI asked what audits were in place to ensure manually handled orders carry the correct BAN. Sue said the process organization had sent a reminder to the order typists reminding them that they need to look up the correct BAN in CPS. She also said that Qwest is looking for other methods to tighten this up.

Issue 2:

John Gallegos, Qwest explained the impacts of the LOE. He stated that numerous systems (7) were affected downstream.

Connie Winston, Qwest added that CPS would have to be re-architect and then several changes to other impacted systems.

Liz asked how the functionality had existed before when the burden for entering BANs fell to the CLECs. Connie answered that even then only one active BAN per product per state was permitted. Liz asked for more detail since the CLECs need to truly understand what is impacted rather than just saying multiple systems. Bonnie Johnson, Eschelon agreed saying that CLECs did not necessarily have to know the system names but need the hours breakdown. Connie suggested this be taken off line and thought through to determine the format and structure this might take. She added specific to this CR that the min impact was to CPS and other highly impacted systems would be IMA and CRM. Bonnie stated that this was more information than the CLECs have had before and Stephan added that it truly helps to understand the reasons behind the denial. Connie said she would take an action item to see what kind of language can be appended to the denial.

Issue 3

Connie said she was still checking if the CLECs could use the optional BAN field. Qwest does some formatting validation but is looking at what it would take to remove these edits. Liz asked if the editing was limited to things like A/N characters and not if the BAN was a “good BAN”. Connie said yes that it is formatting only. Liz asked what the timeframe was and Connie answered hopefully by the CMP meeting.

1/21/04 CMP Meeting Sue Kriebel, Qwest reviewed the response denying the request based on it being economically not feasible. Sue stated to allow multiple BANs per product per state would remove some automation and would require several front and back end system changes. Liz Balvin, MCI stated she had sent Cbeyond examples where old BANs had been populated and would like these to be investigated. Sue agreed to do so and also stated that when BANs are closed orders in queue will flow to the old BAN. Bonnie Johnson, Eschelon stated that it was also possible that the Cbeyond orders were handled on a manual basis. Steven Calhoun, Cbeyond said that the examples were new orders so this should not have been the case. Liz also wanted some cost backup to the denial citing that if it was important enough to the CLEC that they can pursue other avenues. Judy Schultz, Qwest said that a meeting was held a week ago explaining that detail needs to be provided on an economically not feasible denial. Bonnie Johnson, Eschelon did verify that if an incorrect BAN is placed on an order that it will be corrected automatically by Qwest. Bonnie added that the denial is based on “we can’t do this” when that very thing is happening today. Liz stated that the main thrust of the three multiple BAN CRs is to give the CLECs the ability to control the billing of their customers. She stated she didn’t know the trigger for changing BANs. Connie Winston, Qwest said the process is managed by the CPS system and is handled by specific centers. Connie verified that a CLEC could be notified when a BAN is at 6,000 and potentially could not be exhausted until 9,000 because of orders during the interim and that Qwest is trying to keep the BANs at an acceptable level to avoid processing problems. Connie mentioned that the process is the same for all CLECs. Liz asked if the CLECs could use the optional BAN field as they wished. Connie said she would check. It was verified that the FOC would provide the same information as it does today but CLECs could track to the outbound order. Kathy Stichter, Eschelon asked about BAN consolidation. Sue explained the process and that this was done manually with the center. It was agreed that there are multiple action items to research and that a conference call would be held when new information is available. The CR will remain open in Development status. (Comment from Stephanie Prull) Stephanie Prull – Eschelon stated she is interested in the economic breakdown as well due to the economic price discrepancies quoted between her CR and the MCI CR. (end comment).

12/17/03 December CMP Meeting Liz Balvin of MCI presented the CR and stated that a clarification meeting had already been held. Doug said that per the clarification call that two BANs per product per state would solve the MCI specific situation since they are trying to separate divisions. Sue Kriebel, Qwest clarified that today there is one active BAN and possibly many inactive. This CR calls for multiple active BANs. Liz said they were willing to assign BANs from MCI’s end if this would help although at the present time both Liz and Bonnie Johnson of Eschelon were sure that any BAN assigned by the CLEC was overrode when passing through Qwest systems. Bonnie pointed out that Eschelon has well over 100 bills to look at for disputes and discrepancies and that this presents an administrative nightmare. The CR was changed to Presented status.

Clarification Meeting 11:00 a.m. (MDT) / Tuesday November 25, 2003 1-877-521-8688 1456160# PC111303-1 Allow multiple Billing Account Numbers Per Product Per State Attendees: Name/Company: Liz Balvin, MCI Sue Kriebel, Qwest John Gallegos, Qwest Doug Andreen, Qwest Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed. Review Requested (Description of) Change Doug Andreen -Qwest read the description of the CR: Qwest currently only supports a single BAN per product per state. MCI requests the ability to designate multiple BANs per product, per state. In doing so, the CLECs would have the ability to track orders submitted by different divisions of their company. Doug also covered the expected deliverables of the CR: Determine whether a process change only is necessary whereby the CLECs would be required to populate differing BANs on each order. Otherwise, what system enhancements would need to be made to support. Liz Balvin MCI stated that she has confirmed with her service manager that MCI is only allowed one BAN per product per state. She said that there is a field on the LSR to populate the BAN and she was hoping this would be able to be used to solve the request. Sue Kriebel Qwest said that there are numerous customers that do not populate this field and that it is populated when it hits Qwest. She also clarified that there may be multiple BANs per product per state but only one is live. Liz said what she is trying to do is enable segregation of the two divisions in MCI that handle the same products. Two BANs per state per product would be sufficient for MCI. She also thought there was another CR in existence that was similar. John agreed. John gave some historical perspective on population of the BAN field on the LSR. While it was done by the CLECs for some time this became a problem and now this field is populated by Qwest. John stated that implementing this CR would possibly put the responsibility back on the CLECs for ensuring the right BAN was on the order. Liz said MCI would be willing to do this and is open to any way to support implementation of the CR. Liz found the CR that is very similar. SCR100903-02. Sue questioned if this CR could still be worked as only a process change. John said no that there would have to be changes to internal systems to accommodate the change. Liz mentioned that she thought the customer profile drove BAN assignment. John answered yes, but only in part Liz expressed the concern that if this requires systems changes especially to IMA that a time line of presenting the CR at the December Product and Process meeting and having a response in January would conflict with the prioritization of 16.0 CRs in IMA for system changes. John responded that he would consider the expectations of her CR along with SCR100903-02 to ensure that the timeframes did not adversely impact prioritization. It was agreed to leave the CR in Product and Process for now. Doug agreed to relate to two CRs. Confirm Areas & Products Impacted Billing and Wholesale Billing Interface Confirm Right Personnel Involved Correct personnel were involved in the meeting. Identify/Confirm CLEC’s Expectation The following expectations were identified/confirmed: 1. Determine whether a process change only is necessary whereby the CLECs would be required to populate differing BANs on each order. 2. Otherwise, what system enhancements would need to be made to support 3. Relate this CR and SCR100903-02 in order to accelerate possible resolution of the CR. Identify any Dependent Systems Change Requests Related system change SCR100903-02 is related but not dependent Establish Action Plan (Resolution Time Frame) As it now stands, Liz will present the CR at the December 17 CMP Meeting. Response will be made during the January cycle.


CenturyLink Response

January 5, 2004

DRAFT RESPONSE For Review by the CLEC Community and Discussion at the January 2004 CMP Meeting

Liz Balvin MCI Carrier Management - Qwest Region MCI

SUBJECT: Qwest Change Request Response – CR PC111303-1 Allow Multiple Billing Account Numbers Per Product Per State

Qwest currently supports a single BAN per product per state. MCI requests the ability to designate multiple BANs per product, per state. In doing so, the CLECs would have the ability to track orders submitted by different divisions of their company.

A clarification meeting was held on November 25, 2003 with MCI and Qwest representation. At this meeting, Qwest clarified with MCI there may be multiple BANs per state but only one is ‘live/active.’ MCI explained they would like the ability to segregate the two divisions of MCI that handle the same products and therefore would only need two active BANs per state.

Qwest has completed an analysis for PC111303-1, Allow Multiple Billing Account Numbers, per Product, per State, and has determined that this change is economically not feasible. Qwest currently provides active BANs on a state by state basis. Qwest auto-populates these BANs to ensure ordering and billing accuracy. This change would require Qwest to remove this automation, which would require Qwest and CLEC manual intervention likely leading to additional errors or an increase in rejects. Additionally, several of Qwest’s front and back end systems would require changes in order to remove automation, modify existing accounts to allow the manipulation of BANs. Through Qwest’s analysis it was determined that the estimate for the initial implementation of this change would be at least $1 million. Qwest believes that to implement such a change to Qwest systems would be cost prohibitive.

Therefore, Qwest respectfully denies your request for PC111303-01, Allow Multiple Bans per Product, per State, due to economic infeasibility.

Sincerely,

Sue Kriebel Manager Process Management Qwest

CC: Connie Winston Lynn Notarianni Loretta Huff Beth Foster Kit Thomte Judy Schultz


Open Product/Process CR PC092503-1 Detail

 
Title: Provide PREMIS zip code extensions, delineate fields and exclude unnecessary information for the states of MT and WY as a means to obtain rate zone information.
CR Number Current Status
Date
Area Impacted Products Impacted

PC092503-1 Denied
12/17/2003
PREMIS Information
Originator: Balvin, Liz
Originator Company Name: MCI
Owner: Winston, Connie
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

MCI requests that Qwest populate the 4 digit zip codes extensions per address.

In addition that the PREMIS data dump, located at the following URLs, be provided in a loadable format (delineated):

ftp://199.168.32.150/incoming/ima/MTA.SAGA (Montana)

ftp://199.168.32.150/incoming/ima/CHY.SAGA (Cheyenne and SW WY)

ftp://199.168.32.150/incoming/ima/CPR.SAGA (Casper and Northern WY)

There is information currently in the files that doesn’t seem relevant. MCI provides the following as examples and if Qwest determines the information is not relevant, then strip from the files prior to providing to CLECs in a delineated format:

002D ***PO BOX REQ FOR DDA AND BL MLG ADDR ONLY***

0014 ***PO BOX REQ FOR DDA AND BL MLG ADDR ONLY**

THIS IS AN ALTERNATE. STREET NAME IS 1 STREET WEST

001D ***PO BOX REQ FOR DDA AND BL MLG ADDR ONLY**

002T THIS WIRE CENTER HS BEEN CONVERTED TO POSTAL STANDARDS

002T THIS WIRE CENTER HS BEEN CONVERTED TO POSTAL STANDARDS

@ I 3318 ASSIGN ONLY TO BIG SKY BEEPER


Status History

09/25/03 - CR Submitted

09/29/03 - CR Acknowledged

10/03/03 - Held Clarification Meeting

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

12/17/03 December CMP Meeting Liz Balvin with MCI said that the denial seemed based on the zip code extension only and MCI also asked for uploadable information as well. Connie Winston said that comma delimitated and stripping the file was denied also and felt that the file is readable the way it is and the zip code information is available to all of us. The mapping may not meet MCI’s the end goal of determining the rate zone and recognize that rate zones in Montana and Wyoming are difficult to breakdown. This CR will be moved to Denied status.

11/19/03 November CMP Meeting Linda Sanchez-Steinke with Qwest said that IT is working on a solution for the CR and will provide an update at the December CMP meeting. This CR will be moved to Evaluation status.

10/15/03 October CMP Meeting Liz Balvin with MCI presented this new CR. Liz said that at the Systems meeting the rate zone CR was closed and this CR was opened. A clarification meeting was held and Qwest did not want to delete any information and would like to let CLECs determine what is needed and not needed. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting

2:30 p.m. (MDT) / Friday October 3, 2003

1-877-572-8687 3393947# PC092503-1 Provide PREMIS zip code extensions delineate fields and exclude unnecessary information for the states of MT and WY as a means to obtain rate zone information

Name/Company: Liz Balvin, MCI Connie Winston, Qwest John Gallegos, Qwest Shon Higer, Qwest Jim Recker, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Linda read the description of change; MCI requests that Qwest populate the 4 digit zip codes extensions per address. In addition that the PREMIS data dump, located at the following URLs, be provided in a loadable format (delineated). The urls are listed in the body of the CR. There is information currently in the files that doesn’t seem relevant. MCI provides the following as examples and if Qwest determines the information is not relevant, then strip from the files prior to providing to CLECs in a delineated format. The examples are listed in the body of the CR.

Liz Balvin with MCI said that at Systems CMP meeting Connie Winston and she had discussed opening a systems change request. Connie explained that generally when putting information out on a URL that the CR would be considered Product/Process. Connie explained that the 4 digit zip code happens in the backend of the billing systems. Connie suggested that the postal zip code guide may have the information requested in this CR. Liz said that it had been determined there is no unique identification that would determine the rate zone. Connie said that the 4 digit zip code may not help determine the rate zone.

Connie said that it may be possible to delineate the PREMIS data. However, there is a risk for Qwest to determine if the information is or is not relevant because the CLECS may have a different perspective. The data in the SAG is simply a download of PREMIS. Liz said she was ok with that.

Shon Higer asked if what MCI is looking for is to drive or obtain the rate zone. Liz said yes, MCI has been told to do this through pre-order and they are actually trying to determine if they have a market entry in a particular area. Liz said that the 5 digit zip code wouldn’t give a breakdown as to rate zone, but hope that the 4 digit zip code would get to a higher summarization of data rather than getting to the unique addresses.

Connie said that the rate zone could cross the 9 digit zip code area. Shon said Rate zone information is loaded by individual address.

Confirm Areas & Products Impacted PREMIS, URLs : ftp://199.168.32.150/incoming/ima/MTA.SAGA (Montana) ftp://199.168.32.150/incoming/ima/CHY.SAGA (Cheyenne and SW WY) ftp://199.168.32.150/incoming/ima/CPR.SAGA (Casper and Northern WY)

Confirm Right Personnel Involved Correct personnel were involved in the meeting.

Identify/Confirm CLEC’s Expectation Qwest provide 4 digit zip code extensions and a downloadable format (delineated) for Montana SAGA, Cheyenne & SW WY SAGA, and Casper & Northern WY SAGA

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Liz will present this CR at the October CMP Meeting. Qwest will provide a response at the November CMP meeting.


CenturyLink Response

December 9, 2003

Liz Balvin MCI

CC: Connie Winston Lynn Notarianni Sue Stott Beth Foster Christy Turton Kit Thomte Judy Schultz

This letter is in response to CLEC Change Request number PC092503-1, dated 09/25/03, titled: Provide PREMIS zip code extensions, delineate fields and exclude unnecessary information for the states of MT and WY as a means to obtain rate zone.

CR Description: MCI requests that Qwest populate the 4 digit zip codes extensions per address. In addition that the PREMIS data dump, located at the following URLs, be provided in a loadable format (delineated): ftp://199.168.32.150/incoming/ima/MTA.SAGA (Montana) ftp://199.168.32.150/incoming/ima/CHY.SAGA (Cheyenne and SW WY) ftp://199.168.32.150/incoming/ima/CPR.SAGA (Casper and Northern WY)

There is information currently in the files that doesn’t seem relevant. MCI provides the following as examples and if Qwest determines the information is not relevant, then strip from the files prior to providing to CLECs in a delineated format: 002D PO BOX REQ FOR DDA AND BL MLG ADDR ONLY

0014 PO BOX REQ FOR DDA AND BL MLG ADDR ONLY**

THIS IS AN ALTERNATE. STREET NAME IS 1 STREET WEST 001D PO BOX REQ FOR DDA AND BL MLG ADDR ONLY**

002T THIS WIRE CENTER HS BEEN CONVERTED TO POSTAL STANDARDS

002T THIS WIRE CENTER HS BEEN CONVERTED TO POSTAL STANDARDS @ I 3318 ASSIGN ONLY TO BIG SKY BEEPER

Expected Deliverables/Proposed Implementation Date (if applicable): None

History: A clarification meeting was held on October 03, 2003 with MCI and Qwest representation. At this meeting, MCI stated that they would like to have the ability to determine if they have a market entry in a particular area. MCI went on to say that the 5 digit zip code doesn’t give a breakdown per rate zone, but feel that the 4 digit zip code would provide this type of data rather than receiving unique addresses. Qwest suggested that the postal zip code guide may have the information requested in this CR. MCI stated that it has been determined that there is no unique identification that would determine the rate zone. Qwest responded that the 4 digit zip code requested in this CR may not help either in determining the rate zone and that the rate zone information is loaded by individual addresses.

Qwest Response: Qwest has completed an analysis for PC092503-1, Provide PREMIS zip code extensions, delineate fields and exclude unnecessary information for the states of MT and WY as a means to obtain rate zone, and has determined that this change does not provide a reasonable demonstrable business benefit. As previously stated, Qwest does not believe that the 4 digit zip code extension requested in this CR will meet MCI’s business need for obtaining the rate zone because the rate zone is distance based for both Montana and Wyoming and has no relation to the five or nine digit zip extension.

Qwest is denying your request for PC092503-1, Provide PREMIS zip code extensions, delineate fields and exclude unnecessary information for the states of MT and WY as a means to obtain rate zone, due to no reasonable demonstrable business benefit.

Sincerely,

Connie Winston Qwest

November 11, 2003

For Review by the CLEC Community and Discussion at the November 19, 2003 CMP Meeting

Name: Liz Balvin Title: MCI Carrier Management Qwest Region Company: MCI

SUBJECT:CLEC Change Request Response - CR #PC092503-1 PREMIS Zip Code Extensions

This is a preliminary response regarding the MCI CR PC072203-1.

Qwest Information Technologies is currently working internally to identify if a solution or a different option to this request can be implemented. Because there are a number of complex issues associated with the CR, Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request in the December meeting.

Qwest will provide a status update at the December CMP meeting.

Sincerely,

Connie Winston Director Information Technologies Qwest


Open Product/Process CR PC121302-1 Detail

 
Title: Call Forwarding Simplification POTS resale and UNE P Pots
CR Number Current Status
Date
Area Impacted Products Impacted

PC121302-1 Denied
12/13/2002
Ordering, Billing, Maintenance/Repair, Billing UNE-P POTS, Resale POTS
Originator: Prull, Stephanie
Originator Company Name: McLeodUSA
Owner: Paxton, Mallory
Director:
CR PM: Harlan, Cindy

Description Of Change

McLeodUSA proposes the simplification of the Call Forward Busy and Don’t Answer USOC’s available for POTS resale and UNE-P Pots. McLeod would like to have one Call Forwarding USOC for Call Forward Busy, one for Call Forward Don’t Answer, and one for Call Forward Busy/Don’t Answer combo.

Currently there are multiple call forwarding USOC’s in each case. This causes confusion for order writers, line repair representatives, and causes end user pain if not ordered correctly as it can cause a loss of call forwarding service

Expected Deliverable:

McLeodUSA is expecting one call forwarding USOC in each instance labeled above that can work in any call forwarding situation (I.E intra-office, inter-office, overflow). This will eliminate training issues on both the CLEC and Qwest’s side by providing simplified training for order writing representatives for both companies. This will be more consistent with other products Qwest offers. And will allow for more accurate billing and data integrity.


Status History

12/13/02 - CR Submitted

12/13/02 - CR Acknowledged

01/06/03 - Conducted Clarification Meeting

01/15/03 - CR Presented at CMP Meeting

02/12/03 - Qwest response e-mailed to originator

02/19/03 - Qwest response presented at CMP Meeting

03/19/03 - Qwest update presented at CMP Meeting

04/09/03 - Qwest response sent

04/16/03 - Qwest response presented at CMP Meeting - CR Denied and Closed


Project Meetings

04-16-03 - CMP Meeting

Paxton-Qwest presented the denial response. Pardee-AT&T stated that AT&T was disappointed. She stated that the process was error prone and cumbersome. Powers-Tel West stated that Qwest is using “economically not feasible” as a reason for denial very frequently. She stated that CLECs submitted CRs because current Qwest processes were costing them money. She stated that she would begin submitting CRs with an estimate of how much the process was costing the CLEC. Johnson-Eschelon stated that Eschelon was disappointed by the denial of this CR. Balvin-WorldCom stated that the number of denials of economically infeasible also disappointed her. The CR was moved to Denied status.

======================================================

03-19-03 - CMP Meeting

Paxton-Qwest stated that Qwest was continuing to investigate this CR and would present a formal response at the April CMP Meeting. Pardee-AT&T stated that she supported this request as well. Johnson-Eschelon stated that Eschelon was also interested in this CR.

===================================================

02-19-03 - CMP Meeting

Paxton-Qwest presented the Qwest response. Prull-McLeod stated that she understood the response. White-Qwest stated that the CR would be moved to evaluation status.

==================================================

01-15-03 - CMP Meeting

Prull-McLeod presented the CR. Pardee-AT&T and Johnson-Eschelon stated that their companies were very interested in this change as well. The CR moves to Presented.

=================================================================

Clarification Meeting 2:00 PM (Mountain Time) / Monday, January 6, 2003

1-877-550-8686 2213337#

Attendees Matt White – CRPM Mallory Paxton – Qwest Stephanie Prull - McLeod

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Prull-McLeod reviewed the CR. Paxton-Qwest stated that Qwest should grandfather interoffice and intraoffice call forwarding since they are priced the same way. This is important for repair and process clarity. Qwest recommended that McLeod submit this CR. Prull-McLeod stated that several other CLECs support this CR. Paxton-Qwest stated that this request is for all CLECs.

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted. Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved. Paxton-Qwest stated that the retail (Catherine Thompson) and wholesale (Janean Van Dusen and Michael Whitt) Product Managers need to be involved. Paxton-Qwest stated that this would be a lengthy CR. Prull-McLeod stated that she did not expect it to be a quick CR.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm Allegiance’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for Allegiance to present the CR at the January Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

April 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the April 16th, 2003, CMP Product/Process Meeting Stephanie Prull OSS Manager McLeod Communications

SUBJECT: Qwest’s Change Request Response - CR #PC121302-1

This is Qwest’s Revised Response to McLeod’s request that Qwest reduce its number of call forwarding USOCs to three.

There are several applications for the many call forwarding USOCs Qwest uses today. These applications depend on the type of call forwarding requested, the product it will work with, and the state where the customer’s line is located.

This request is to make changes for POTS services. Since making these changes for POTS would impact other products, such as Voice Messaging and Centrex, which utilize call forwarding features and which use the same systems to provision them, Qwest’s evaluation of the request included the impact on those products.

Accommodating McLeod’s request would involve changes to Qwest’s ordering, provisioning, and billing processes and systems, including the Qwest Voice Messaging/Business Voice Messaging platform. These process changes would involve a very large financial commitment by Qwest. High level resource implications are outlined below:

- Addition of the following resources for a period of 12 months: - Five product management resources - Three process management resources (Centrex, Features and VMS/BVMS) - One Network Engineering resource - One Network Translations resource.

The economic magnitude of adding the indicated resources is too large for Qwest to implement this change. This request is denied because it is economically not feasible.

Qwest’s Product Management and Process Management, with our Network advisors, respectfully recommend that McLeod and other CLECs with questions concerning the use of these USOCs review the USOCs with their Qwest Service Management team to clarify the ordering process for these features. Ordering documentation, including the Resale and UNE-P feature PCATs and the USOC/FID Finder, is available on the Qwest Wholesale web site at http://www.qwest.com/wholesale/.

Sincerely,

Mallory Paxton Senior Process Analyst Qwest Services Corporation

Attachment 1 Call Forwarding USOCs

Call Forward Busy, Call Forward Don’t Answer, & Call Forward Busy/Don’t Answer are all features that utilize several USOCs and are ordered depending on the Call Forwarding Number (CFN) used on the order.

The options offered are:

Inter-office (Expanded): these USOCs are used to forward calls to a number outside of a customer’s Central Office switch in the various conditions described. FDJ – Call Forward Don’t Answer FBJ – Call Forward Busy Line FVJ – Call Forward Busy Line/Don’t Answer

Intra-office: These USOCs are used to forward calls to a number within the same Central Office switch in the various conditions described. For Residence customers: EVD – Call Forward Don’t Answer EVO – Call Forward Busy Line EVK – Call Forward Busy Line/Don’t Answer – All Qwest states except OR & WA EV2 – Call Forward Busy Line/Don’t Answer – OR & WA only

For Business customers: EVD - Call Forwarding Don't Answer EVB - Call Forwarding Busy Line External Intra-office - (Business Customers only USOC) EVO - Call Forwarding Busy Line Overflow - (Not available in NM to Bus Customers). EVF - Call Forwarding Busy Line External/Don'tAnswer - (Business Customers only USOC) EVK - Call Forwarding Busy Line Overflow/Don't Answer - ALL STATES EXCEPT OR, WA: (Not available in NM to Bus Customers) EV2 - Call Forwarding Busy Line Overflow/Don’t Answer Intraoffice - OR, WA ONLY.

Centrex 21 USOCs 69J – Call Forward Busy Line – Exceptions: In a DMS10 office the capability of forwarding outside the common block is not available. DMS-100 - Use 69J USOC followed by an 'HG' suffix, i.e. 69JHG 69H – Call Forward Don’t Answer – Exceptions: In a DMS-10 office the capability of forwarding outside the common block is not available. DMS-100 - Use 69H USOC followed by an 'HG' suffix, i.e. 69HHG. 69J & 69H – Call Forward Busy Line/Don’t Answer.

=====================================================

February 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the February 19, 2003, CMP Product/Process Meeting

Stephanie Prull OSS Manager McLeod Communications

SUBJECT: Qwest’s Change Request Response - CR #PC121302-1

This is Qwest’s Initial Response to McLeod’s request that Qwest reduce its many call forwarding USOCs to a total of three. Because of the complexity and effort necessary to appropriately evaluate this request, Qwest recommends moving this Change Request into Evaluation Status. Qwest will provide a status of Qwest’s research into a solution to the requested change in the March CMP meeting.

Sincerely,

Mallory Paxton Senior Process Analyst Qwest Services Corporation


Open Product/Process CR PC042103-1 Detail

 
Title: Tracking process for FBDL order issues.
CR Number Current Status
Date
Area Impacted Products Impacted

PC042103-1 Completed
8/18/2004
Escalations, Customer Service LNP, Unbundled Loop
Originator: Prull, Stephanie
Originator Company Name: McLeodUSA
Owner:
Director:
CR PM: Harlan, Cindy

Description Of Change

McLeod requests a process established for the listing operations center that is consistent with the CSIE center.

Expected Deliverable:

McLeod expects that a ticket be opened with the Directory Listing Operation center as is the process with the CSIE center today. Mcleod expects that these are tracked and available to any reporting that is available to the CSIE center tickets. Mcleod would accept a process where the ticket is initiated with the CSIE center then a warm transfer to the Directory Listing Operations Center is given. Again the ticket would need to be maintained and tracked as all other customer service tickets are today.


Status History

4/21/03 CR Received

4/22/03 CR Acknowledged

5/8/03 Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/09/03 - Revised response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

08/21/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/09/04 - Qwest sent CMPR.01.09.04.F.01241.Ad_Hoc_Mtg_SchldRESEND for ad hoc meeting scheduled 1/19/04

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/05/04 - Qwest sent PROD.03.05.04.F.01446.WPDL_V23_DL_UserGuide Level 4 proposed effective date 4/19/04

03/17/04 - March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/25/04 - Qwest sent PROD.03.25.04.F.01510.FNL_WPDL_V23_DL_UserGuide, effective date 4/19/04

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - Project meeting minutes will be posted to the database

8/16/04 - August CMP meeting mintues will be posted to the database


Project Meetings

8/16/04 CMP Meeting Mintues Cindy Macy – Qwest advised that she contacted Eschelon to verify if the report format was correct. Cindy advised that Qwest was reviewing the report internally to make sure it was accurate. Kim Isaacs – Eschelon advised that she did get a copy of the report and it looked accurate to her. It was sent as an attachment to the email. Kim advised the attachment was a much better way to deliver the report. Kim advised it was okay to close this CR. This CR will move to Completed Status.

07/21/04 July CMP Meeting Cindy Macy – Qwest provided status and advised that the format should be corrected with the July report that will be available August 5. This CR will remain in CLEC Test status.

06/16/04 June CMP Meeting Lee Gomez with Qwest said CLECs will continue to receive the report as originally formatted until formatting changes can be made. Stephanie Prull with Eschelon said they received the June report in the same format as the May report. Lee said that if anyone needs the report in the format that Lee views, they can request through their Listing Account Manager. This CR will remain in CLEC Test status.

Date: 5/24/04 12:08 p.m. From: Isaacs, Kimberly D. [kdisaacs@eschelon.com] To: Sanchez Steinke, Linda cc: Bonnie Johnson Subject: Report for PC042103-1

Linda, here is the FBDL Listing Help Ticket Report, Eschelon received on 5-5-04. Please let us know if you have any other questions. Thank you and have a wonderful day.

Kim Isaacs ILEC Relations Process Analyst kdisaacs@eschelon.com Eschelon Telcom Inc Ph: 612-436-6038 Fax: 612-436-1519

Date: 5/24/04 10:21 a.m. From: Sanchez Steinke, Linda To: 'bjjohnson@eschelon.com' Subject: Report for PC042103-1

Hi Bonnie -

Would you send me the e-mail report that you received for CMP CR PC042103-1 "Tracking process for FBDL order issues".

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

05/19/04 May CMP Meeting Linda Sanchez-Steinke with Qwest said that the reports were provided to the CLECs on 5/5/04. Bonnie Johnson with Eschelon said they received the report and expected it to provide additional details but was high level similar to the escalation ticket report. Stephanie Prull with Eschelon said there were issues with the report format and that it was just an e-mail with dates and the columns were shifted left and right. Stephanie suggested this be corrected by re-formatting the report and providing search capability. Bonnie also said the report should be in a table format with sorting capability. Lee Gomez with Qwest joined the call later and the formatting concerns were reiterated. Lee will check into these. Bonnie suggested putting the data into a table in a word document. This CR will move to CLEC Test status.

04/21/04 April CMP Meeting Lee Gomez with Qwest said that everything is ready and in place and any CLECs that would like to get the report should contact the Listing Account Manager to receive the report. Stephanie Prull with Eschelon said thank you for providing the report. This CR will move to CLEC Test status.

03/17/04 March CMP Meeting Linda Sanchez-Steinke gave an update the product notice for the White Page Directory Listings Version 23 User Guides was sent on 3/5 with a proposed effective date of 4/19. CLECs should contact the Listing Account Manager to receive the report. This CR will remain in Development status.

02/18/04 February CMP Meeting Lee Gomez with Qwest gave the update and advised that the CR is on track for implementation in April and will be sending a notification updating the listing document. The first report will be available in May and the CLECs should contact the Listing Account Manager to receive the report.

Stephanie Prull with Eschelon asked if multiple ACNAs will all be on the same report. Lee Gomez said there would be a separate report for each ACNA. This CR will remain Development status.

Fri 2/13/04 8:29 AM From; Sanchez Steinke, Linda To: bjjohnson@eschelon.com Subject: FW: Action Items Ad Hoc 1/19/04 PC042103-1 Tracking process for FBDL order issues

Bonnie - As a follow up to your request in the January CMP meeting minutes, attached are the take back items that Lee Gomez had for PC042103-1. I also posted to the body of the CR under Project Meetings.

Thank you Linda Sanchez-Steinke 303-382-5768

--Original Message-- From: Sanchez Steinke, Linda Sent: Monday, January 26, 2004 12:43 PM To: 'bjjohnson@eschelon.com' Subject: FW: Action Items Ad Hoc 1/19/04 PC042103-1 Tracking process for FBDL order issues

Bonnie - Forwarding to you -- I have your e-mail address incorrect in the first e-mail.

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

--Original Message-- From: Sanchez Steinke, Linda Sent: Monday, January 26, 2004 12:41 PM To: 'bjjohnson@escehlon.com'; 'kdisaacs@eschelon.com'; 'saprull@eschelon.com'; 'dosborne@att.com'; 'cdickinson@att.com' Subject: Action Items Ad Hoc 1/19/04 PC042103-1 Tracking process for FBDL order issues All,

As a follow up to the ad hoc meeting held 1/19/04, regarding PC042103-1, the following are answers to questions asked during the meeting that Lee Gomez took as action items:

Q) Bonnie said there are time when calls are referred to directory listings by CSIE and would like to know which report those would show on.

A) CSIE opens a ticket for every call received. If they determine that a call should be referred to the LOC, CSIE will close that ticket. With the implementation of this report, when a call is referred from the CSIE, the LOC will open a Help Ticket and follow the new process.

Q) Stephanie asked if tickets can be broken down by what tier closed.

A) FBDL does not have tiers. The LOC representative is the primary point of contact for listing related questions and they will be responsible for opening the Tickets. If the CLEC is not satisfied with the status of a ticket, they may chose to escalate the issue to their Listing Resource Services (LRS) Account Manager (AM). The LRS AM will investigate the situation and may work with the LOC regarding a Ticket, but the LOC representative is responsible for opening, updating and closing Tickets.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

Mon 1/26/04 12:41 PM From; Sanchez Steinke, Linda To: 'bjjohnson@escehlon.com', 'kdisaacs@eschelon.com' 'saprull@eschelon.com' 'dosborne@att.com' 'cdickinson@att.com' Subject: Action Items Ad Hoc 1/19/04 PC042103-1 Tracking process for FBDL order issues All,

As a follow up to the ad hoc meeting held 1/19/04, regarding PC042103-1, the following are answers to questions asked during the meeting that Lee Gomez took as action items:

Q) Bonnie said there are time when calls are referred to directory listings by CSIE and would like to know which report those would show on.

A) CSIE opens a ticket for every call received. If they determine that a call should be referred to the LOC, CSIE will close that ticket. With the implementation of this report, when a call is referred from the CSIE, the LOC will open a Help Ticket and follow the new process.

Q) Stephanie asked if tickets can be broken down by what tier closed.

A) FBDL does not have tiers. The LOC representative is the primary point of contact for listing related questions and they will be responsible for opening the Tickets. If the CLEC is not satisfied with the status of a ticket, they may chose to escalate the issue to their Listing Resource Services (LRS) Account Manager (AM). The LRS AM will investigate the situation and may work with the LOC regarding a Ticket, but the LOC representative is responsible for opening, updating and closing Tickets.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

01/21/04 January CMP Meeting Lee Gomez with Qwest gave an update that an ad hoc meeting was held to present the prototype report for FBDL tickets and that the targeted implementation is April. Stephanie Prull with Eschelon asked for the implementation date. Lee said it would be coincident with IMA 15.0. This CR will remain in Development status. (Begin comment from Bonnie Johnson - Eschelon) (Can you provide the answers to the take backs that Lee Gomez provided at the meeting?) (end comment).

Ad Hoc Meeting Minutes PC042103-1 January 19, 2004 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:30 a.m. Mountain Time

List of Attendees: Carla Pardee - AT&T Donna Osborne-Miller - AT&T Kim Isaacs - Eschelon Stephanie Prull - Eschelon Bonnie Johnson - Eschelon Lee Gomez - Qwest Linda Sanchez-Steinke - Qwest

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to gain input on the draft format of the report providing information on FBDL tickets opened by CLECs.

Lee Gomez with Qwest explained that the reports would be similar to the CSIE reports provided monthly. The data will be reported for the entire month and will include calls made to the Listing Operations Center (LOC) regarding FBDL. The report will give the total number of calls per month, broken down by day and 8 categories of the tickets opened. Lee explained how the categories are defined:

Account Ownership - account does not belong to Provider DLIS - question regarding information displayed in DLIS Ordering - question regarding how to complete an order. DSRED - question regarding data returned on a DSRED. Migration - question related to migration/conversion orders Missing Listing - question regarding listing not found Other - miscellaneous question.

These categories will be defined in the Facility-Based CLECs and Reseller/Unbundled Network CLECS Directory Listing User Document.

Stephanie Prull with Eschelon asked what category a ticket would go into when getting ready to do a conversion and DLIS is not correct. Lee said that it would fit into the account ownership if the order has already been issued.

Stephanie asked where a ticket would be categorized if Eschelon has a customer and the information on CSR doesn’t match DLIS. Lee said that would be under DLIS because of what is being displayed in DLIS, however, the Provider may request a specific reason code if necessary.

Stephanie asked if there is a trouble ticket opened with DLIS where would that be classified. Lee said that is would go under DLIS. The reason code can be negotiated between the CLEC and the Qwest LOC representative whenever the CLEC feels it is necessary.

Bonnie Johnson with Eschelon asked if the FBDL report would be separate from the CSIE report. Lee answered yes. Bonnie said there are time when calls are referred to directory listings by CSIE and would like to know which report those would show on. Lee will get back with Bonnie after checking. Bonnie stated that the preference would be that CSIE would close their ticket and it would appear on the FBDL report. Lee will verify.

Donna Osborne-Miller asked the if the number associated with the category is the total number. Lee said that was correct.

Stephanie asked if tickets can be broken down by what tier closed. Lee will find out the answer.

Linda will e-mail answers out to the group and will put the minutes in the body of this change request. There were no additional questions.

12/17/03 December CMP Meeting Linda Sanchez-Steinke gave status that this CR is targeted for the April timeframe and will arrange an ad hoc meeting to review draft format with Stephanie Prull. This CR will remain in Development status.

11/19/03 November CMP Meeting Lee Gomez with Qwest gave the update on this CR. Qwest is planning to provide a report prototype at the next meeting. There is a help ticket generated today and there will be updates made in the applicable PCAT. This CR will remain in Development Status.

10/15/03 October CMP Meeting Linda Sanchez-Steinke with Qwest gave the update on this CR. Qwest is planning to provide a report in the April 2004 timeframe. Linda will contact Stephanie Prull to arrange a meeting to discuss the report format. This CR will remain in Development Status.

09/17/03 September CMP Meeting Lee Gomez provided an update on this CR. Lee said that Qwest is actively working on providing a report in the April timeframe. This CR will remain in Development Status.

CMP Meeting 08-20-03

White-Qwest stated that the proposed implementation date for the change was April 2004. The CR was left in Development status.

=======================================

CMP Meeting 07-16-03

White-Qwest presented the Qwest acceptance and recommended the CR be moved in to Development.

==================================== CMP Meeting 06-18-03

White-Qwest presented the Qwest response. He stated that Qwest is currently working internally to identify a solution to this request. Because this request involves the creation of a complex and wide-reaching process, there are a large number of issues Qwest must analyze. He asked that the change move to Evaluation. ========================================================== CMP Meeting 05-21-03

Prull-McLeod presented the CR. Johnson-Eschelon stated that Eschelon was interested in this CR as well. ========================================== Clarification Meeting Wednesday, May 07, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Lee Gomez – Qwest Michelle Thacker – Qwest Stephanie Prull – McLeod Jennifer Arnold – USLink

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Prull-McLeod reviewed the CR. She stated that McLeod has a hard time keeping track of their FBDL issues because they go to a different center once the order has been processed. Gomez-Qwest stated that the CLECs are now calling into the CSIE center for system related issues. She explained that they should be able to take calls and open tickets for DLIS issues. She asked McLeod what the wanted to track. Prull-McLeod stated that McLeod wanted visibility on ordering issues. Gomez-Qwest asked if McLeod was currently experiencing problems with the center. Prull-McLeod stated that they weren’t but that McLeod is doing more internal reporting. She stated that this is a gap in this reporting because they don’t have a good way to track it. Gomez-Qwest asked if this CR was related to DLIS issues. Prull-McLeod stated that it was not. She stated that McLeod wanted to have a ticket number and tracking capabilities. Thacker-Qwest asked if USLink had the same concern. Arnold-USLink stated that USLink did not have the same issue and needed to submit a separate CR

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm McLeod’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for McLeod to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

Stephanie Prull McLeod USA

SUBJECT: Qwest’s Change Request Response - CR #PC042103-1

This is a revised response regarding McLeod CR PC042103-2. This CR requests a process be established for the listing operations center that is consistent with the CSIE center.

Qwest accepts this CR. Qwest will create a system to track each incoming CLEC call to the Listing Operations Center. Similarly, this system will allow Qwest to provide the CLEC with a ticket number and reports that identify all CLEC calls/help tickets/status. These systems and processes will be completely separate from those within the CSIE.

Qwest will provide a status update of the work to implement this CR at the August CMP meeting.

Sincerely,

Lee Gomez Lead Process Analyst Qwest Communications

=========================================== June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, CMP Product/Process Meeting

Stephanie Prull McLeod USA

SUBJECT: Qwest’s Change Request Response - CR #PC042103-1

This is a preliminary response regarding McLeod CR PC042103-2. This CR requests a process be established for the listing operations center that is consistent with the CSIE center.

Qwest is currently working internally to identify a solution to this request. Because this request involves the creation of a complex and wide-reaching process, there are a large number of issues Qwest must analyze. Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the July CMP meeting.

Sincerely,

Lee Gomez Lead Process Analyst Qwest Communications


Open Product/Process CR PC042103-2 Detail

 
Title: Escalation Ticket Reporting
CR Number Current Status
Date
Area Impacted Products Impacted

PC042103-2 Completed
3/2/2004
Originator: Prull, Stephanie
Originator Company Name: McLeodUSA
Owner: Thacker, Michelle
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

McleodUSA requests a process where CLECs can receive on a monthly basis statistics regarding the escalation tickets opened by the CLECs with Qwest.

Expected Deliverable:

McleodUSA expects to be able to be provided a process where we can receive a monthly report outlining the escalation ticket activity for that CLEC.

McleodUSA would like to see the following information available.

How many escalation tickets we opened.

How many were closed and by what tier. (By Tier 1, Tier 2, or Tier 3.)

What resolution the ticket was closed with.

How long the ticket was open for. (Or open date and time, close date and time.)

What platform the ticket was in regards to.

McleodUSA expects this process to be implemented as soon as possible.


Status History

4/21/03: CR Received

4/22/03: CR Acknowledged

5/8/03 Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/11/03 - Qwest response posted and distributed

06/18/03 - Discussed at CMP Meeting

07/09/03 - Revised response posted and distributed

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/07/03 - Held Ad Hoc meeting - minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/10/03 - Qwest issued PROS11.10.03.F.01013.OrderingV39 proposed effective date 12/19/03

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/01/03 - Qwest issued Final Notice PROS.12.01.03.F.01116.FNL_OrderingV39, effective date 12/16/03

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

02/18/04 - February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

03/02/04 - CR moved to completed status per e-mail from Tracey Koffran at McLeod USA


Project Meetings

Linda:

Thanks for checking. McLeodUSA also agrees that this can be closed.

Thanks! TSK

--Original Message-- From: Sanchez Steinke, Linda [mailto:Linda.SanchezSteinke@qwest.com] Sent: Monday, March 01, 2004 12:32 PM To: Kramer, Shawna L.; Koffron, Tracey S. Subject: FW: CMP CR PC042103-2 Escalation Ticket Reporting

Shawna & Tracey -

CR PC042103-2 can be viewed at http://www.qwest.com/wholesale/cmp/changerequest.html

We discussed the CR at CMP last Wednesday and it was ok to close from other CLECs standpoint, and I just want to verify that McLeod is ok to close. Please e-mail me back and if you have questions call me.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

From: Sanchez Steinke, Linda To: 'skramer@mcleodusa.com'; 'tkoffron@mcleodusa.com' cc: Subject: FW: CMP CR PC042103-2 Escalation Ticket Reporting

Shawna & Tracey -

CR PC042103-2 can be viewed at http://www.qwest.com/wholesale/cmp/changerequest.html

We discussed the CR at CMP last Wednesday and it was ok to close from other CLECs standpoint, and I just want to verify that McLeod is ok to close. Please e-mail me back and if you have questions call me.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

Thu 2/19/04 10:51 AM From; Sanchez Steinke, Linda To; 'msprague@mcleodusa.com' Subject: CMP CR PC042103-2 Escalation Ticket Reporting

Hi Michelle -

This CMP CR was discussed at the Product/Process meeting yesterday. It was agreed that the CR could be moved to Completed status, and that Qwest could e-mail McLeod and make sure it is ok to close it.

Would you please let me know.

Thank you

Linda Sanchez-Steinke CRPM Qwest 303-382-5768

02/18/04 February CMP Meeting Michelle Thacker with Qwest gave an update that the January reports were sent on 2/16/04 and asked if the CR could be closed. Stephanie Prull with Eschelon said that Eschelon agrees to close this CR and suggested that Qwest also contact Michelle Sprague at McLeod to close. Qwest will e-mail McLeod to confirm closing this CR. This CR will move to Completed status if McLeod agrees.

01/21/04 January CMP Meeting Michelle Thacker with Qwest gave an update that CLECs who requested the data received their November data in December and December data in January. This CR will move to CLEC Test status.

12/17/03 December CMP Meeting Michelle Thacker with Qwest gave an update that Qwest has received requests for reports and expect they will be delivered by 12/19. Bonnie Johnson with Eschelon provided her e-mail address to Michelle and asked if they would receive their report on 12/18. Michelle said that the report should be received 12/18. This CR will remain in Development status.

11/19/03 November CMP Meeting Michelle Thacker with Qwest provided an update on this CR. Michelle said that external documentation has been posted for review and comments. This CR will remain in Development status.

10/15/03 October CMP Meeting Michelle Thacker with Qwest provided an update on this CR. Michelle said that we held an ad hoc meeting on 10/7/03 and gained input from the CLECs on the report format. The outcome was two action items; request from CLECs for one e-mail and after research one e-mail is not possible. Each report will be e-mailed separately. Qwest can suppress pages from the report per CLEC request, for example CLECs can request to receive pages 1 and 5 and not to receive pages 2 and 4. Further information on how reports will be ordered will be included in a PCAT update. The other action item was to provide progress on documentation. Currently the external documentation is being worked on and will be deployed according to CMP guidelines. This CR will remain in Development status.

Ad Hoc Meeting Minutes PC042103-2 October 7, 2003 1-877-572-8687, Conference ID 3393947# 10:30 a.m. - 11:00 a.m. Mountain Time

List of Attendees: Carla Pardee - AT&T Stephanie Prull - McLeod Liz Balvin - MCI Kim Isaacs - Eschelon Bonnie Johnson - Eschelon Lydell Peterson - Qwest Jeff Tietz - Qwest Jen Arnold - U S Link Michelle Thacker - Qwest Dennis Van Der Vieren - Qwest Linda Sanchez-Steinke - Qwest

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to gain input on the draft format of the report providing statistics of call center tickets.

Michelle Thacker explained that Qwest has sent the reports individually to each CLEC and are looking for feedback on the format of the reports. Bonnie Johnson said that she received the e-mails and got pages 1, 3, 4, and 5 with no page 2. Michelle explained that the page numbers will be corrected.

Michelle explained that page 1 is the total call center tickets for the reporting timeframe and the total number of call center tickets for the call handling centers.

Page 2 are the call center tickets received and the tier that assisted with the ticket. Bonnie Johnson asked if this is the tier the ticket is closed at and Michelle said no this is the tier that assisted with the ticket.

Page 3 is the total number of tickets resolved by tier.

Page 4 is the total tickets resolved by reason code. Michelle explained that the CLEC facing documentation will provide further definition of the reason codes.

Account Ownership reason code would be requests to find out if the CLEC owns the account or to find out when the account was lost.

LSR reason code would be calls about rejects and jeopardy after FOC. Bonnie asked if there was more information about LSR reject definition. Michelle said that at any time the CLEC can ask how the ticket was closed. Bonnie explained Eschelon has been working on a project for LSR quality providing Qwest rejects in error and asked Qwest Service Management Team to identify rejects in error and the Service Management Team has said that they don’t have the data to pull a report.

Michelle explained that Listings are requests for assistance with listing, change listing on service orders, and complex listings. Stephanie Prull asked if the listing requests are from CSIE rather than the DL center. Michelle said yes the statistics are from CSIE.

Michelle explained that ordering tickets include resent FOC, resend PSON, supp’d LSRs, demarc, and expedites. Bonnie asked where a call about PSON id mistakes would fall. Michelle said that would be under pre-order.

Michelle explained that pre-order tickets would be addresses, loop qualification, CFA validation, facilities, IMA functionality.

Provisioning tickets are requests for assistance with out of service, complete service order in error, reschedule of tech visit.

Referral tickets would be making referrals to repair and warm transfers to repair and other Qwest departments..

Stephanie asked if there was a problem with address validation within Premis system, would the ticket be opened in pre-order. Michelle said yes those tickets would fall under pre-order.

Liz Balvin with MCI had not received the reports and Dennis Van Der Vieren will e-mail to her.

Carla Pardee with AT&T asked how they can get the reports and Michelle said that the reports would be ordered through the customer questionnaire as an interim process.

Stephanie Prull with McLeod asked if it would be possible to get all 4 pages of the report into one e-mail. Dennis will investigate if one e-mail can be sent.

Bonnie Johnson said that she was hoping to receive more data.

Stephanie Prull asked when the interface document will be available. Michelle said the external document is under development.

Jen Arnold with U S Link mentioned that on pages 3 and 4 the number of reports resolved in September must include carryovers from the prior month. Michelle said yes.

Linda asked if there were any additional questions. No questions were asked and Linda said that we would discuss this CR at the October CMP meeting.

09/17/03 September CMP Meeting Michelle Thacker with Qwest provided an update on this CR. Michelle would like to meet with Stephanie Prull with McLeod next week and provide the report in draft format. Eschelon, MCI, VarTec and AT&T would like to be included in the meeting. Qwest will arrange an ad hoc meeting on 9/25 and send notification. This CR will remain in Development status.

CMP Meeting 08-20-03

White-Qwest stated that Qwest would like to conduct a test of the new process with McLeod in September. Prull-McLeod stated that she should be the POC for that test. White-Qwest stated that Qwest estimated that the first report would come out in December with data collected in November.

==========================================

CMP Meeting 07-16-03

Thacker-Qwest presented the Qwest acceptance. Johnson-Eschelon asked if tickets escalated higher than Tier 2 will be included in the report. She stated that if it is escalated then it probably remains in the database as a Tier 2. Thacker-Qwest stated that in most cases this would be true. Johnson-Eschelon asked if the report will include notes. Thacker-Qwest stated that it would include only numbers; not notes. The CR was moved into Development.

========================================== CMP Meeting 06-18-03

Thacker-Qwest presented the Qwest response. She asked that the CR be moved to Evaluation status. Prull-McLeod asked that they be shown samples of the report format when Qwest developed them. Thacker-Qwest stated that if Qwest was able to accept this CR they would share samples with McLeod. Johnson-Eschelon stated that Eschelon’s Service Manager had provided them a report like this one requested in the CR. ========================================================== CMP Meeting 05-21-03

Prull-McLeod presented the CR. Johnson-Eschelon stated that Eschelon was interested in this CR as well. ========================================== Clarification Meeting Wednesday, May 07, 2003

1-877-550-8686 2213337#

Attendees Matt White – Qwest Michelle Thacker – Qwest Stephanie Prull – McLeod

Introduction of Attendees White-Qwest welcomed all attendees and reviewed the request.

Review Requested (Description of) Change Prull-McLeod reviewed the CR. Thacker-Qwest asked what the data would be used for. Prull-McLeod stated that it would be used primarily for reporting metrics and training issues. Thacker-Qwest asked if McLeod currently contacted their service manager thwne they want to know about their tickets. Prull-McLeod stated that they did contact their service manager. She stated that they used to receive a report from their service manager but that they haven’t received it recently. She explained that McLeod has made the same request of their service manager but was told that there was not a way to get the information. She stated that was why she submitted the CR. Thacker-Qwest stated that there is no current process, but that McLeod may be able to get this info from their service manager. Prull-McLeod stated that McLeod used to get the report, but had to ask for it. She stated that they would like to get it every month without requesting

Confirm Areas and Products Impacted White-Qwest confirmed that the attendees were comfortable that the request appropriately identified all areas and products impacted.

Confirm Right Personnel Involved White-Qwest confirmed with the attendees that the appropriate Qwest personnel were involved.

Identify/Confirm CLEC’s Expectation White-Qwest reviewed the request to confirm McLeod’s expectation.

Identify and Dependant Systems Change Requests White-Qwest asked the attendees if they knew of any related change requests.

Establish Action Plan White-Qwest asked attendees if there were any further questions. There were none. White-Qwest stated that the next step was for McLeod to present the CR at the May Monthly Product/Process Meeting and thanked all attendees for attending the meeting.


CenturyLink Response

July 9, 2003

REVISED RESPONSE For Review by CLEC Community and Discussion at the July 16, 2003, CMP Product/Process Meeting

Stephanie Prull McLeod

SUBJECT: Qwest’s Change Request Response - CR # PC042103-2 (Escalation Ticket Reporting)

This letter is in response to CLEC Change Request (CR) PC042103-2. This CR is a request by McLeod to establish a process where CLECs can receive, on a monthly basis, statistics regarding the escalation tickets opened by the CLECs with Qwest. During the clarification call, McLeod stated that it would use the data primarily for reporting metrics and training issues within McLeod.

In evaluating this request, Qwest accepts this CR to provide a monthly statistical report of all Call Center Database tickets opened and resolved in our Call Handling Centers. This report will be available upon request and contain such statistical ticket detail as:

- Product Type (Total number of tickets opened for each product) - Sub Product Type (Total number of tickets for sub product) - Reason Code/Sub Reason Code (Total number of tickets closed)

Ticket detail will be summarized including total number of tickets opened during the month, total number tickets closed at Tier 0, 1, 2, etc. External documentation will be available including instructions on how to order, where to call if questions about the report arise and if the report is not received.

Further details regarding implementation (dates, contact information, etc.) will be available at the August CMP meeting.

Sincerely,

Michelle Thacker Sr. Process Analyst Qwest Communications

=========================================== June 11, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the June 18, 2003, CMP Product/Process Meeting

Stephanie Prull McLeod USA

SUBJECT: Qwest’s Change Request Response - CR #PC042103-2

This is a preliminary response regarding McLeod CR PC042103-2. This CR requests a process where CLECs can receive on a monthly basis statistics regarding the escalation tickets opened by the CLECs with Qwest.

Qwest is currently working internally to identify a solution to this request. Because there are a large number of issues Qwest must analyze, Qwest proposes moving this Change Request into Evaluation Status while Qwest prepares a complete answer to this request.

Qwest will provide a status update at the July CMP meeting.

Sincerely,

Michelle Thacker Sr. Process Analyst Qwest Communications


Open Product/Process CR PC051203-1 Detail

 
Title: Versioning Process Change
CR Number Current Status
Date
Area Impacted Products Impacted

PC051203-1 Crossover
7/27/2009
Originator: Prull, Stephanie
Originator Company Name: McLeodUSA
Owner: Manning, Monica
Director:
CR PM: Harlan, Cindy

Description Of Change

Currently if the Service Center receives 2 versions of an order back to back they will respond to the newest version only. This is inconsistent with the way the system works today if an order goes auto-flow. Today by the service centers not responding to all versions this does not allow the CLECs to sync up their responses or makes it look like they are not receiving responses from Qwest for some of their orders.

Expected Deliverable:

McleodUSA expects that for every transaction we send we will receive some sort of response whether it’s via the system or the Service Centers. We expect this process to be changes acrossed all centers and all platforms. We expect this to be implemented ASAP.


Status History

5/12/03 CR Received

5/14/03 CR Acknowledged

5/16/03: Contacted customer

5/23/03: Held Clarification Call - agreed this CR should be crossed over to systems CR as CLEC is requesting change to EDI interface transaction set

5/28/03: Crossed over this CR to systems. We will get confirmation at the June CMP meeting that this is a cross over CR


Project Meetings

This CR was crossed over to SCR051203-01X. This CR will be closed.

Clarification Meeting

May 23, 2003 1-877-572-8687 3393947# PC051203-1 Versioning Process Change

Attendees Stephanie Prull – McLeod Monica Manning – Qwest Wendy Green – Qwest Woldey Assefa - Qwest Cindy Macy – Qwest

1.0 Introduction of Attendees Attendees introduced

2.0 Review Requested (Description of) Change Stephanie Prull – McLeod reviewed the CR. Stephanie explained that Qwest does not respond with an EDI transaction to the older version of an LSR when a newer version comes in when the LSR goes to manual. A response is sent when the LSRs are flowthrough. Cindy Macy – Qwest asked Stephanie why she didn’t identify the CR as a system CR with EDI impacts. Stephanie advised she wasn’t sure how to submit the CR as the process to have the SDC respond is a manual process but the response she needs is an EDI transaction. Monica – Qwest confirmed that Stephanie is looking for a mechanized EDI notification, but the generation of the notification does not have to be automated. Woldy, Wendy and Stephanie discussed possible EDI transaction sets that could be sent. The group discussed FOC or Rejct or Cancel but felt that these would impact the most current version of the LSR and that would not work. Possibly a new transaction set that makes that version of the LSR Inactive, but doesn’t affect measurements and the most current version of the LSR. Stephanie explained that not receiving a response on older versions causes problems with their tracking and complicates their trouble investigations. Monica confirmed that it is a documented process that Qwest does not respond to older versions when a new version is received. Stephanie agreed but is requesting it to be changed.

3.0 Confirm Areas & Products Impacted Ordering, Provisioning, EDI transactions

4.0 Confirm Right Personnel Involved The team discussed that this should be a systems CR and Cindy will discuss with the systems team and cross over. The systems team may want to have another clarification / adhoc meeting with the team.

5.0 Identify/Confirm CLEC’s Expectation McLeod advised they would like to receive an EDI transaction response of some kind on older versions of LSR when they submit a newer version and it is handled manually.

6.0 Identify any Dependent Systems Change Requests none

7.0 Establish Action Plan (Resolution Time Frame) McLeod will present the CR at the June CMP Meeting Qwest will cross over to systems


Open Product/Process CR PC112901-2 Detail

 
Title: TIC Charge Credit Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC112901-2 Denied
2/20/2002
Billing, Maintenance/Repair Centrex, Private Line, Resale, Unbundled Loop, UNE,
Originator: Bowers, Diane
Originator Company Name: McLeodUSA
Owner: Suellentrop, Craig
Director:
CR PM:

Description Of Change

Qwest has begun charging for trouble isolation charges. In numerous instances, the Qwest tech is dispatched and finds no trouble found when test to the dmarc. The trouble still exists and we will request the tech to be dispatched again. This time the tech finds the trouble on Qwest's network. The original trouble isolation charge should not be charged since the trouble was isolated to Qwest. Qwest is currently unable to stop the billing of the TIC charge or issue on the spot a credit to cover the charge issued the day before. It requires McLeod to research every TIC charge and determine if it was a valid charge. This is very time consuming and requires resources that we do not have. McLeod would like to request a process be developed to design services. They are calling the CLEC before closing a ticket if there is a charge generated from that ticket. Another suggestion is to provide the ability to the Qwest repair screeners to initiate the credit when McLeod communicates the event of a previous ticket being opened and closed with no trouble found. This would need to apply to resale and UNE trouble tickets.


Status History

11/28/01 - CR Received from McLeodUSA.

11/29/01 - E-Mail Acknowledgement issued to McLeodUSA.

11/30/01 - Contacted McLeodUSA via voice mail messages and confirmed availability any time between 12/4 - 12/7.

12/04/01 - Conducted Clarification Meeting with McLeodUSA.

12/06/01 - Issued Clarification Meeting Minutes to McLeodUSA.

12/12/01 - CMP Meeting - McLeod was not on the call to present its CR. Qwest reviewed what was discussed at the Clarification meeting. CR Status to change to Clarification.

12/27/01 - Christine Mohrfeld is out of the office through 1/2/02. Sent e-mail request for example.

01/03/02 - Telecon with Christine Mohrfeld - she is transitioning the responsibilities for this CR to Diane Bowers and she is working on providing the examples.

01/04/02 - Sent Dian Bowers e-mail for additional clarification meeting on Tuesday 1/8/02.

01/08/02 - Additional clarification meeting scheduled with McLeodUSA for 01/11/02.

01/11/02 - Conducted additional Clarification Meeting with McLeodUSA.

01/16/02 - CMP Meeting - the CR was discussed with the CLEC participants and Qwest provided various options. It was agreed that the CR could move to Evaluation.

01/18/02 - Issued Clarification Meeting Minutes to McLeodUSA.

02/12/02 - Issued Qwest's Draft Response dated 2/6/02 to McLeodUSA.

02/20/02 - CMP Meeting - Qwest presented its Draft Response. It was agreed that the status of the CR would be Denied. It was agreed that the aspects of this CR would be rolled into a Global Action Item on Test Charges. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02.

02/22/02 - Qwest's formal response dated 2/6/02 issued to CLEC Community.

03/20/02 - CR Open/Closed Status changed to Closed per agreement at 03/20/02 Monthly CMP Meeting that CRs having Denied status should also reflect Closed Status


Project Meetings

CLEC Change Request Clarification Meeting

Date: January 11, 2002, 2:00 p.m. (MT) Place: Conference Call 877-564-8688 Subject: PC112901-2, TIC Charge Credit Process

Attendees: Ric Martin, Qwest Alice Matthews, Qwest Craig Suellentrop, Qwest Cheryl McMahon, Qwest Dennis Pappas, Qwest Joann Garramone, Qwest Bud Witte, Qwest Don Tolman, Qwest Diane Bowers, McLeodUSA Rod Cox, McLeodUSA Sue Sedrow, McLeodUSA Carol Whitson, McLeodUSA Chad Sharp, McLeodUSA Todd McNally, McLeodUSA

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change Ric explained that the direction from the previous Clarification meeting with McLeodUSA was for Qwest to investigate a process for Qwest to initiate a credit on a TIC when it was determined that the TIC was applied in error. Ric further explained that internal discussions brought on additional questions that necessitated the additional clarification call. On the CR, several products were identified and Trouble Isolation Charge (TIC) applies to non-designed services and Maintenance & Service Charge (MSC) applies to Designed Services. Diane indicated that McLeod was not able to identify the end user of the TIC and MSC charges. She indicated that she was aware of a release in March that would put the ANI for MSC, but still couldn’t identify TIC end users. Sue asked how Qwest identifies the charge. Dennis indicated that a charge is applied when repair finds a trouble or when repairs are performed. Typically an E0135 is applied. Dennis indicated that he thought that the TIC was a flat charge and there was also a Dispatch charge. Bud clarified that for MSC, billing starts when tech is dispatched to the trouble, proves the trouble is not in Qwest network, gets customer approval to perform repair and the work is billed on a T&M basis and billed to the end user. Bud indicated that the Dispatch charge was for Designed Services. Ric advised that at the last Clarification meeting McLeodUSA wanted the ability to have the field tech or repair center issue a credit when it has been determined that the charge was in error. Ric explained that the system currently does not have the ability for either person to enter a credit. A system change would be required to add the coding. Ric further explained that once a TIC is issued and another Ticket is issued it is difficult to determine if the problems were the same. This was the reason Qwest requested an example of where they have determined that the TIC was applied and later determined that it was incorrect. Diane indicated that they were working on this. Craig confirmed that there were two items we should be trying to respond to. The first is the TIC and the second is McLeodUSA’s requirement to identify end user. Diane indicated that she thought that the determination of the incorrect TIC was identified before the ticket was closed. Craig advised that the charges were applied when the ticket was closed. He advised that, for Resale POTS tickets are closed by the Tech in the filed and POTS wouldn’t have the same ticket. Bud advised that for Designed Services there is a Dispatch Charge and the Tech’s travel time. McLeodUSA felt that this was a duplicate charge. Bud explained that the Dispatch charge is for the truck roll and the travel charge (30-min increments) is the Tech’s time. It was agreed that we could keep the TIC and MSC separate on focus on TIC. Qwest confirmed that the TIC only gets applied when the Tech uses a combination of Codes.

Establish Action Plan McLeodUSA will try to provide the examples. Qwest will identify options and suggestions at the 1/16/02 CMP.

-

Subject: CR PC112901-2 Date: Thu, 27 Dec 2001 14:23:30 -0700 From: Richard Martin Organization: Qwest Communications International, Inc. To: Christine Mohrfeld

Christine,

We have had a couple of internal meetings on the CR. A question has come up whether you have a specific instance when a TIC was applied incorrectly (i.e. the trouble was later determined to be in Qwest's Network). If you could provide an example, this would help us with isolating the issue and determining the appropriate resolution.

Thanks

Ric

CLEC Change Request Clarification Meeting

December 4, 2001, 2:00 p.m. (MT) Conference Call 877-564-8688 PC112901-2, TIC Charge Credit Process

Attendees: Ric Martin, Qwest Alice Matthews, Qwest Christine Mohrfeld, McLeodUSA

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change Christine advised that when Qwest’s screener gets a trouble ticket and if the technician didn’t find any trouble, the screener then initiate a Trouble Isolation Charge (TIC). The problem is when the trouble persists and it is subsequently determined that the trouble was Qwest related, there is no process for the screener or any other person to stop the TIC charge. McLeodUSA’s only avenue to reverse the TIC charge is at the back end in the billing cycle. They have to physically research, identify the incorrect TIC charge and call Qwest to get an adjustment. Qwest confirmed that this is the situation to date.

Confirm Areas & Products Impacted Christine confirmed that the products set forth in the CR are correct. She indicated that this issue was for all products. . Confirm Right Personnel Involved Alice Matthews confirmed she was the SME for this process. She advised that we would also need to get a network person involved in any solutions.

Identify/Confirm CLEC’s Expectation Christine confirmed that McLeodUSA is looking for a manual process that would allow the screener to initiate a credit for an incorrect TIC Charge. Ideally, once a manual process is developed, a mechanized solution would be required.

Identify any Dependent Systems Change Requests Christine indicated that they submitted a Systems CR that provides better definition on the billing charges. Qwest will look into the CR to see if there is any relation. Christine advised that they would like to have the TN identified. As a minimum they would like this for Resale and UBL would require the Circuit ID.

Establish Action Plan (Resolution Time Frame) Qwest advised that the path forward would be as follows: ? Since this CR was received after the 3 weeks prior to the CMP, McLeodUSA will present this CR at the December CMP Meeting. ? The CR will have the collective CLEC clarification at the January CMP Meeting. ? Qwest will begin to identify solutions that can be offered at the January CMP Meeting. ? Qwest will develop its response for the February’s CMP Meeting Qwest will identify a Network SME that will be involved in this CR.

Subject: Acknowledgement of Submitted Change Request Date: Thu, 29 Nov 2001 10:00:23 -0700 From: "Jim Beers" Organization: Qwest Communications International, Inc. To: cmohrfeld@mcleodusa.com CC: Richard Martin , Todd Mead , Michael Keegan , Peter Wirth

Dear Christine Mohrfeld:

Thank you for participating in the Qwest Change Management Process (CMP). We have received your Change Request (CR) submission titled "TIC Charge Credit Process". The information contained in the submitted CR appears to be complete and valid at this time.

Please note, we have applied a tracking number to this CR, #PC112901-2, for your use in following the progress of your submission through CMP. You may view your submitted CR via the Product & Process Interactive Report located on the Qwest web page at URL - http://www.qwest.com/wholesale/cmp/changerequest.html

We have assigned a CR Project Manager (CRPM) to facilitate the Qwest Response to your request. The assigned CRPM, Ric Martin, will be contacting you in the near future to schedule a Clarification Meeting.

Sincerely, Jim Beers Product & Process CMP Manager 303.965.2930

-


CenturyLink Response

February 6, 2002

Diane Bowers McLeod USA Cedar Rapids, IA 52404

SUBJECT: Qwest’s Change Request Response - CR PC112901-2 TIC Charge Credit Process

McLeod is requesting that Qwest issue a credit for incorrectly applied Trouble Isolation Charges (TIC) either at the time a trouble ticket is closed or when a new ticket at the same location is opened. The CR addressed both resale and UNE products. During clarification meetings with McLeod and other CLLEC’s it was agreed to focus on the TIC charge, which applies to POTS and CENTREX resale or UNE-P only.

The repair process for POTS requires the CLEC to submit a trouble report, either electronically through MEDIACC or CEMR, or by calling the Repair Call Handling Center (RCHC). During trouble reporting process the CLEC must either authorize the TIC or not authorize the TIC.

If the TIC is authorized, a Qwest technician may be dispatched to the end-user’s premise to isolate trouble. If a technician is dispatched and trouble is isolated to the end-user’s equipment or wiring (beyond the Network Interface Device (NID) the technician will attempt to contact the CLEC, and the ticket will be closed. The technician will enter disposition codes into Qwest’s system indicating trouble beyond the NID. These disposition codes are routed to billing and a TIC is applied.

If the TIC is not authorized, no dispatch will take place, although Qwest may perform a remote test. If the remote test indicates no trouble or trouble beyond the NID, the ticket will be closed Test OK (TOK) and no TIC will apply. A CLEC may also use CEMR to perform the remote test (MLT) itself.

Currently, billing disputes are handled through the CLEC’s Service Manager. The Service Manger will contact the appropriate Qwest employees to research the dispute and will work with the CLEC until resolution.

This Change Request would require resolution of billing disputes by Qwest’s network technicians or repair attendants. To determine if a TIC is inappropriately applied, investigation of each trouble ticket is necessary. Neither the repair attendant taking the trouble report nor the technician isolating the trouble at the end-user’s premise have the resources to adequately research the appropriateness of waiving a TIC charge in each situation. Such research, if assigned to network technicians or repair attendants, would result in slower repair intervals for the CLEC. This work function is appropriately assigned in Qwest to the Service Manager. Therefore, Qwest respectfully denies this Change request.

Sincerely,

Craig Suellentrop Interconnection Planner Qwest

Cc: Alice Matthews Cheryl McMahon Terrance Meehan Mary Retka Jamal Boudhaouia


Open Product/Process CR 5343715 Detail

 
Title: Legacy CR Suspending T1 (DSS) service for collection purposes.
CR Number Current Status
Date
Area Impacted Products Impacted

5343715 Withdrawn
4/16/2001
Billing Resale T1/DSS
Originator: Mohrfeld, Christine
Originator Company Name: McLeodUSA
Owner:
Director:
CR PM:

Description Of Change

McLeod would like the ability to suspend a T1 (DSS) line for collection purposes, either electronically or manually. Currently, we are required to disconnect the service and then reconnect the service following payment. The timeframe for disconnect and reconnect is extensive. Average 15 days for each process. Currently, Centrex suspension is realtime through CMS or 48 hours through IMA.


Status History

1/16/01 - CR Received from Christine Mohrfeld of McLeod

1/16/01 - Status changed to New-to be reviewed and sent to Christine

2/05/01 - Status changed to Reviewed - Under Consideration

2/06/01 - Updated CR sent to Christine Mohrfeld of McLeod

4/16/01 - Status changed to Cancelled - Co-Provider - Qwest

4/23/01 - Updated CR sent to Christine Mohrfeld of McLeod

3/28/02 - Posted this legacy CR to CMP Database. Completed CR Form had been posted to the Web as part of the "Change Request (CR) Archive - Change Requests statused as Inactive before August 1, 2001"


Project Meetings


Open Product/Process CR PC121101-1 Detail

 
Title: Add design contact's name to the CNR
CR Number Current Status
Date
Area Impacted Products Impacted

PC121101-1 Completed
2/20/2002
Provisioning Unbundled Loop, UNE
Originator: Whitson, Carol
Originator Company Name: McLeodUSA
Owner: Martain, Jill
Director:
CR PM:

Description Of Change

McLeod is requesting Qwest to make modification to the "customer not ready" spreadsheet and add the CLECs design contact's name as a column on the spreadsheet. When McLeod receives the spreadsheet, we have to manually look up every order to determine who the original order writer was. Once the order writer is identified, we forward the notification to them so they can follow up appropriately with Qwest.


Status History

12/11/01 - CR Submitted by Christine Mohrfeld, McLeod

12/11/01 - Acknowledgement of Submitted Change Request sent to McLeod

12/12/01 - CR posted to the web

12/18/01 - Held clarification call with McLeod, status changed to 'Clarification'

12/19/01 - Draft clarification meeting minutes issued to McLeod

12/19/01 - Qwest CR owner changed to Jill Martain

01/02/02 - Talked to Christine Mohrfeld about Mcleod's action from the clarification call, she will research.

01/04/02 - E-mail from Qwest asking Luanne to follow up on McLeod action

01/04/02 - E-mail from McLeod requesting jeopardy notifications via EDI

01/07/02 - The centers begin to send all McLeod jeopardy notices via EDI today

01/16/02 - January CMP meeting. Qwest presented a verbal response stating that McLeod is now receiving jeopardy notifications via EDI; therefore, this CR is no longer required. CLECs agreed to close if Qwest obtains an e-mail from Michelle Sprague (McLeod) concurring with Qwest.

01/17/02 - Qwest sent e-mail to McLeod requesting that they concur with closing CR

02/01/02 - Qwest sent response dated 02/01/02 to McLeod

02/20/02 - February CMP meeting: Qwest response dated 02/01/02 presented to CLECs. Qwest received voice mail from McLeod confirming request had been met. CLECs agreed to close CR. CR status changed to "Completed" Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package 03/20/02

02/21/02 - E-mail from McLeod confirming closure of this CR

02/22/02 - Formal response dated 02/01/02 issued to CLECs - Document Number: CMPR.02.22.02.F.01229.CR_Responses

03/20/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

2/21/02 - E-mail from McLeod confirming closure of this CR

Subject: Re: PC121101-1 "Add design contact's name to the CNR" Date: Thu, 21 Feb 2002 10:27:42 -0600 From: "Whitson, Carol" To: Todd Mead Todd, Please close out the CMP PC121101-1. We no longer need this change. Thanks Carol

2/21/02 - E-mail from Qwest asking for written confirmation of CR closure

From: Todd Mead on 02/21/2002 09:18 AM To: Carol Whitson/MCLEOD@MCLEOD cc: "Martain, Jill" Subject: PC121101-1 "Add design contact's name to the CNR" Carol, I received your voice mail yesterday confirming McLeod's request detailed in PC121101-1 has been met - thanks. I passed this message onto the general CLEC community at yesterday's CMP Product & Process meeting. They are happy to close this CR as long I receive written confirmation from you. So could you please reply to this e-mail confirming McLeod are happy to close this CR. Thanks

01/17/02 E-mail from Qwest asking for McLeod to concur with closing CR

Subject: PC121101-1 Add Design Contact's Name to the CNR Date: Thu, 17 Jan 2002 08:25:53 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: msprague@mcleodusa.com CC "Martain, Jill" , dmbowers@mcleodusa.com Michelle, At yesterday's P&P CMP meeting, Qwest presented their verbal response to PC121101-1. Qwest believes that now McLeod are receiving Jep notifications via EDI, you no longer need the extra column on the CNR spreadsheet displaying the order writer (as was requested in your CR). Diane was not familiar with this issue and asked that I get your concurrence before we close this CR. Can you please respond and let us know if we can close this CR. If you don't agree with this approach please let us know which direction this CR should take. If you have any questions, please don't hesitate to call me. I have attached the CR and relevant documentation for your information. Thanks Todd Mead

01/04/02 E-mail from McLeod requesting jeopardy notifications via EDI

Subject: Jeopardy Notices Date: Fri, 4 Jan 2002 12:07:35 -0600 From: "Mohrfeld, Christine A." To: jvilks@uswest.com CC: jmartai@uswest.com, tmead@uswest.com, "Sprague, Michelle L." , "Whitson, Carol" McLeod would like to make it a requirement of Qwest to provide all jeopardy notifications to McLeod via EDI. These jeopardy notices should include facility held orders, customer not ready issues, etc. I would also like to request the Customer not ready letters be faxed directly to the original order writer. McLeod would provide the fax number on our orders. Please let me know when this can be implemented. Thanks Christine

01/04/02 E-mail from Qwest asking Luanne to follow up on McLeod action

Subject: PC121101-1 Add Design Contact's Name to the CNR Date: Fri, 04 Jan 2002 07:56:31 -0700 From: Todd Mead Organization: Qwest Communications International, Inc. To: lhazen@mcleodusa.com CC: "Martain, Jill" Luanne Hazen, I understand you have taken over from Christine Mohrfeld as the McLeod representative for CRs? When we had the clarification call for this CR on the 18th of December, Christine accepted an action to investigate why McLeod are not requesting Jep Notifications via EDI? Could you please follow up on this action. Thanks Todd

Clarification Call 3:00 p.m. (MDT) / Tuesday 18th December 2001

Attendees: Jill Martain / Qwest Vivian Vigil / Qwest Todd Mead / Qwest Christine Mohrfeld / McLeod Lou-Ann Hazen / MeLeod

Review Description of Change: Qwest asked for clarification on the order writer, is this order writer the same as the LSR originator? McLeod confirmed that it was. Qwest asked why McLeod dos’nt request Jep notification via EDI which will solve this problem? McLeod is currently receiving FOC notifications via EDI. McLeod will investigate and report back to Qwest.

Products: Unbundled Loop, UNE Areas: Provisioning

Identify/Confirm CLEC’s Expectation: McLeod would like to replace the current manual process for identifying the LSR originator on the CNR spreadsheet.

Establish Action Plan: Christine will investigate why McLeod are not requesting Jep notification via EDI and will report back by this Friday (12/21/01).


CenturyLink Response

FORMAL RESPONSE

February 1, 2002

Carol Whitson ILEC Relation Account Manger McLeod USA

CC: Sue Burson

This letter is in response to your CLEC Change Request Form, number PC121101-1 - Add Design Contact's Name to the CNR.

REQUEST: McLeod is requesting Qwest to make modification to the "customer not ready" spreadsheet and add the CLECs design contact's name as a column on the spreadsheet. When McLeod receives the spreadsheet, we have to manually look up every order to determine who the original order writer was. Once the order writer is identified, we forward the notification to them so they can follow up appropriately with Qwest.

RESPONSE: Qwest held a clarification meeting with McLeod on the 18th December 2001. During this meeting, it was confirmed the ‘order writer’ McLeod was referring to is the same person as the ‘LSR Originator’. Qwest subsequently had discussions with McLeod questioning the reasons that they are not currently receiving jeopardy notices via EDI. As a result of the discussion, McLeod advised Qwest that they would prefer receiving their jeopardy notifications via EDI and submitted an e-mail requesting the change. Qwest believes that when McLeod receives this information via EDI they will no longer require an additional column on the CNR spreadsheet displaying the order writer.

McLeod began to receive jeopardy notifications via EDI on the 1st January 2002. Qwest believes the intent of this CR has now been met.

Sincerely,

Jill Martain Manager of Process Management


Open Product/Process CR PC030102-1 Detail

 
Title: Trouble tickets for resale worked liked unbundled trouble tickets
CR Number Current Status
Date
Area Impacted Products Impacted

PC030102-1 Completed
6/19/2002
Maintenance/Repair Resale
Originator: Whitson, Carol
Originator Company Name: McLeodUSA
Owner: Suellentrop, Craig
Director:
CR PM: Thomte, Kit

Description Of Change

Work the trouble tickets for resale with a screener so they can schedule the tech and the tech calls the screener. After the tech has called the screener, they would call McLeod with the resolution of what was done and then close out the ticket.


Status History

03/01/02 - CR Submitted by McLeodUSA (03/01/02 reflects the date notification was sent advising the receipt of this CR at cmpcr@qwest.com and not the 02/27/02 submitted date shown on the CR.)

03/01/02 - CR acknowledged by P/P CMP Manager

03/01/02 - CR posted to the web in the Product & Process Interactive Report (http://qwest.com/wholesale/cmp/changerequest.html)

03/04/02 - McLeod contacted (by e-mail) to organize clarification meeting

03/05/02 - Clarification meeting conducted with McLeodUSA

03/06/02 - Clarification minutes issued to McLeodUSA and posted to CMP database

03/20/02 - March CMP Meeting: CR Status changed to "Clarification." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

04/17/02 - April CMP Meeting: CLECs agreed to change CR status to "Evaluation". Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

05/08/02 - Issued Qwest's Draft Response dated April 29, 2002 to McLeodUSA.

05/15/02 - May CMP Meeting: Qwest presented its draft response dated April 29, 2002. McLeod identified examples where they were not getting call backs. Qwest agreed to open an action item. It was agreed that the CR would remain in a Presented status. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site.

06/19/02 - June CMP Product and Process meeting this CR was changed "Completed" Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site


Project Meetings

03/05/02 Clarification meeting conducted with McLeodUSA

Clarification Meeting 9:00 a.m. (MDT) / Tuesday 5th March 2002 1-877-564-8688 ID 626-5401 # PC030102-1 Trouble tickets for resale worked liked unbundled trouble tickets

Attendees: Carol Whitson / McLeod Mike Larson / McLeod Adam Schug / McLeod Scott Kendall / McLeod Jim Christner / McLeod Craig Suellentrop / Qwest Todd Mead / Qwest

Review Requested (Description of) Change: Carol read the Description of Change from the CR: "Work the trouble tickets for resale with a screener so they can schedule the tech and the tech calls the screener. After the tech has called the screener, they would call McLeod with the resolution of what was done and then close out the ticket." Craig asked for clarification that this request only covered resold POTs, not design services as design services already followed the same process as UBL. McLeod confirmed this request was for POTs. McLeod stated that with UBL there is a hold and then a call back to prevent multiple trouble tickets being opened. This is want they want with POTs. Craig reiterated that this request was clear. Currently Qwest Retail does not have this either, so this would be a completely new process. McLeod stated want they are really after here is to have a call back before the trouble ticket is closed. They have tried using 800 numbers etc to ensure this happens, but as yet they have not been successful in getting Qwest to call back prior to the ticket closing. This results in McLeod having to reopen multiple tickets for the same issue, which consequently results in escalation problems as the newly opened tickets do not qualify for the appropriate escalation. Qwest asked whether McLeod use CEMR or manual call in or both. McLeod replied they use a combination.

Confirm Areas & Products Impacted: Area: Maintenance/Repair Product: Resale Confirm Right Personnel Involved: Craig confirmed he is the right person within Qwest to take the lead on this CR. He will coordinate input from others within Qwest to develop the response to this CR.

Identify/Confirm CLEC’s Expectation: - Qwest would use screener to work trouble tickets and call McLeod instead of the tech. - McLeod want to have a process in place that will ensure they will receive a call from Qwest before the trouble ticket is closed

Identify any Dependent Systems Change Requests: None identified

Establish Action Plan: The General CLEC Clarification will be at the April CMP meeting (4/17/02). Qwest’s draft response to this will be presented at the May CMP meeting (5/15/02). The current CR status and respective documentation can be viewed in the Product & Process Interactive Report at: http://qwest.com/wholesale/cmp/changerequest.html


CenturyLink Response

“ April 29, 2002

Carol Whitson ILEC Relation Account Manager McLeod USA

SUBJECT: Qwest’s Change Request Response - CR PC030102-1 “Trouble tickets for resale worked like unbundled trouble tickets.”

This CR requests that Qwest “Work trouble tickets for resale with a screener so they can schedule the tech and the tech would call the screener when the trouble is resolved. After the tech has called the screener, they would call McLeod with the resolution and what was done and then close the ticket.” During the clarification call with McLeod and at the General Clarification at the April CMP meeting, McLeod indicated the primary concern is to receive a call before the ticket is closed.

As the title of this CR indicates, Qwest uses a Maintenance Control Organization (MCO) to manage all designed service trouble tickets (both wholesale and retail), including trouble tickets for unbundled network elements (excluding UNE-P POTS). The MCO technician manages the closure of these trouble tickets, including calling back the customer and waiting up to 24 hours to receive a call back to coordinate closure. The trouble ticket is placed in a “No Access” status while Qwest is waiting for a response from the customer. After 24 hours, the trouble ticket is closed if no response is received.

Because non-designed trouble tickets (both wholesale and retail) are generally less complex and have much larger volumes, Qwest doesn’t use an MCO technician to manage their closure. For non-designed trouble tickets (resale and UNE-P POTS) the technician that resolves the trouble closes the ticket. The technician attempts to contact the customer when closing the ticket. If the customer cannot be reached, the ticket is closed. In addition, for trouble tickets opened through the electronic interface (CEMR), notification is automatically sent (either through e-mail or fax) when the ticket is closed.

Qwest’s systems are unable to status non-designed trouble tickets as “No Access.” Waiting for a customer to clear voice mail and reply back to Qwest before closing a non-designed trouble ticket may result in increased trouble resolution time, missed appointments, and technician idle time. Therefore, Qwest respectfully denies this Change Request.

Sincerely,

Craig Suellentrop Staff Advocate, Policy & Law Qwest

Cc: Mary Retka, Director-Legal Issues, Qwest Catherine R. Garcia, Senior Process Analyst, Qwest Catherine Augustson, Senior Process Analyst, Qwest


Open Product/Process CR PC020602-1 Detail

 
Title: CLEC Trouble Ticket cross reference (Ref SCR030702 1)
CR Number Current Status
Date
Area Impacted Products Impacted

PC020602-1 Completed
3/20/2002
Maintenance/Repair Other: All products supported under the Repair platform.
Originator: Sprague, Michelle
Originator Company Name: McLeodUSA
Owner: McMahon, Cheryl
Director:
CR PM:

Description Of Change

McLeod would like to request that the CLEC repair trouble ticket number be added to the Qwest trouble ticket, each time a ticket is initiated with Qwest. This would allow for an efficient cross-reference for both McLeod and Qwest. The field chosen to house the CLEC trouble ticket number must be a searchable field, to allow for query capability. This change would save a great deal of time in locating tickets, assisting both McLeod and Qwest in efficiency.


Status History

02/06/02 - CR Submitted by McLeodUSA

02/06/02 - CR acknowledged by P/P CMP Manager.

02/12/02 - Submitting CLEC contacted to schedule clarificatiion meeting.

02/15/02 - Clarification Meeting conducted with McLeodUSA. Minutes transmitted to McLeodUSA and posted to CMP data base.

02/28/02 - Draft response dated 02/28/02 issued to McLeodUSA and posted to CMP database. CR status changed to "Presented"

03/01/02 - Draft response dated 02/28/02 posted to the web in the Product & Process Interactive report URL: http://qwest.com/wholesale/cmp/changerequest.html

03/01/02 - Notification issued to CLECs informing them draft response has been posted to the web

03/07/02 - Systems CR SCR030702-1 "CLEC Trouble Ticket Cross-Reference" opened to address this request

03/19/02 - E-mail from McLeod confirming closure of this CR - issue to be handled in Systems CMP

03/20/02 - March CMP Meeting: CLECs agreed to close CR. CR Status changed to "Completed." Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site

03/21/02 - Formal response dated 02/28/02 posted to CMP database

03/22/02 - Formal response dated 02/28/02 issued to CLECs. Notification CMPR.03.22.02.F.01240.CR_Responses

04/17/02 - CR Open/Closed status changed to closed and inactive and checked for Archive 2002


Project Meetings

03/19/02 E-mail from McLeod confirming closure of this CR - issue to be handled in Systems CMP

Subject: CR PC020602-1 Date: Tue, 19 Mar 2002 14:12:11 -0600 From: "Sprague, Michelle L." To: tmead@qwest.com, jxbeer2@qwest.com

I am OK with closing the CR McLeod has opened on the Product/Process side (PC020602-1) CLEC Trouble Ticket Cross-Reference and moving it to the system side. It defently has system impacts. I will be attending the Thursday meeting, to discuss the CR. Thanks for your help

--

9:30 a.m. (MDT) / Friday 15th February 2002 Conference Call TEL: 877.554.8688 CODE: 3269208 PC020602-1 "CLEC Trouble Ticket cross-reference"

Michelle Sprauge, McLeodUSA Cheryl McMahon, Qwest Craig Suellentrop, Qwest Dan Busetti, Qwest Catherine R. Garcia, Qwest Lynn Stecklein, Qwest Kerri L. Waldner, Qwest Peter Wirth, Qwest

1.0 Introduction of Attendees Attendees introduced.

2.0 Review Requested (Description of) Change {review long description from change request, confirm with all parties there is agreement on the change requested} Description: McLeod would like to request that the CLEC repair trouble ticket number be added to the Qwest trouble ticket, each time a ticket is initiated with Qwest. This would allow for an efficient cross-reference for both McLeod and Qwest. The field chosen to house the CLEC trouble ticket number must be a searchable field, to allow for query capability. This change would save a great deal of time in locating tickets, assisting both McLeod and Qwest in efficiency.

Expected Deliverables: For Qwest to communicate this new process to their service center and ensure that an applicable field for this new data to be stored, to allow for it to be searchable.

Michelle Sprauge discussed the CR. Additional clarification was provided regarding the following: 1) McLeodUSA format for trouble ticket number [McLeodUSA to provide] 2) Search capability for all Qwest trouble tickets requested by McLeodUSA 3) Electronic bonding may provide cross-referencing for electronic tickets. McLeodUSA to confirm. Manual ticketing will still require cross-referencing. 4) McLeodUSA ticket numbers are auto generated; thus preventing McLeodUSA from using the Qwest ticket number as their number.

3.0 Confirm Areas & Products Impacted {read from change request, modify if needed} Confirmed. Optional section: delete "SATE" reference.

4.0 Confirm Right Personnel Involved {ensure the Qwest SME can fully answer the CLEC request. Confirm whether anyone else within Qwest has been involved with this issue, or whether we need to bring anyone else in} Qwest & McLeodUSA confirmed appropriate personnel were in attendance.

5.0 Identify/Confirm CLEC’s Expectation {Identify specific deliverables from CLEC " what does Qwest have to do in order to close this CR? (in measureable terms ie provide a documented process, change a process to include training etc)"} Qwest to evaluate CR. During the March 2002 Monthly P&P CMP Meeting, Qwest will solicit input from CLEC community.


CenturyLink Response

February 28, 2002

Michelle Sprague OSS Manager McLeodUSA

SUBJECT: Change Request Response - CR # PC020602-1 "CLEC Trouble Ticket Cross-reference"

Qwest has reviewed the subject Change Request (CR) and has determined that the request should be re-classified as a 'Systems' CR. A process change would not satisfy the request for the trouble ticket cross-reference between Qwest and McLeodUSA. Qwest proposes to open a 'Systems' CR on behalf of McLeodUSA and process the request.

Sincerely,

Catherine Garcia Lead Process Analyst - Wholesale Repair Qwest Communications

Cc: Cheryl McMahon, Process Analyst Wholesale Repair, Qwest Sara Mendivil, Director Program/Project Management, Qwest


Open Product/Process CR PC063005-1 Detail

 
Title: Cease completion verification calls
CR Number Current Status
Date
Area Impacted Products Impacted

PC063005-1 Denied
10/11/2005
Provisioning Unbundled Loop
Originator: Sprague, Michelle
Originator Company Name: McLeodUSA
Owner: Rehm, Peggy
Director:
CR PM: Stecklein, Lynn

Description Of Change

McLeod would like Qwest to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. In today’s process, Qwest contacts the CLEC to notify them that the cut is complete, the CLEC then completes their testing and verification, the CLEC then contacts Qwest back to let them know that the cut is accepted. Future process, we would like Qwest to automatically assume the cut is accepted if the CLEC does not contact them back within 2 hours.


Status History

6/30/05 - CR submitted

6/30/05 - CR acknowledged

7/7/05 - Clarification Meeting Scheduled

7/12/05 - Clarification Meeting Held

7/20/05 - Discussed at the June Product/Process CMP Meeting

7/20/05 - Status changed to Presented Status

7/20/05 - Discussed in the July CMP Product/Process Meeting

8/17/05 - Status changed to Evaluation

8/17/05 - Discussed in the August CMP Product/Process Meeting

9/12/05 - Draft Response Issued

9/17/05 - Discussed in the September CMP Product/Process Meeting

10/11/05 - Final Response Issued

10/11/05 - Status changed to Denied

10/19/05 - Discussed at the October Product/Process CMP Meeting - See Attachment C in the Distribution Package


Project Meetings

E-mail from Covad 11/2/05

Thanks Lynn. Please note in the CR the following on behalf of Covad:

Qwest’s response does not provide sufficient information to question the dollars assessed that resulted in the denial of this CR. Qwest houses the information requested and it is not required to access the Inventory Systems to extract and send to the billing systems which contains this information.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Wednesday, October 26, 2005 9:55 AM To: Balvin, Elizabeth Cc: Hankins, Lynn Subject: RE: PC060105-01 Update Lines in Service Report

Liz,

I have attached a revision of the denial on PC060105-01 Update Lines in Service Report that includes a breakdown of the estimated costs. Let me know if you have further questions.

Thanks,

Lynn Stecklein Qwest Wholesale CRPM 303 382-5770

--Original Message-- From: Balvin, Elizabeth [mailto:ebalvin@covad.com] Sent: Monday, October 17, 2005 1:31 PM To: Stecklein, Lynn Subject: RE: PC060105-01 Update Lines in Service Report

Lynn,

Covad requests a breakdown of the estimated costs = $726, 730.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Monday, October 17, 2005 10:31 AM To: Balvin, Elizabeth Subject: RE: PC060105-01 Update Lines in Service Report

Hi Liz,

This is in response to your e-mail below regarding PC060105-1 Update Lines in Service Report. We did research your request asking Qwest to merge the data from two systems – 1 Billing and 1 Lines in Service. The second denial that was sent to you (attached) covers the cost for doing that merge. In order to do the merging correctly, Qwest would have to invest in hardware and development time to create the rules associated with the merge and which data is used, etc. As stated in the denial – ‘It is possible for Qwest to combine the two systems so that the billing information requested is included in the Lines In Service Report, however the cost to complete the systems work to do this merge and implement business rules for the merging process would be $726, 730. Therefore, Qwest denies this CR as being economically infeasible’

Let me know if you have additional questions or concerns.

Thanks,

Lynn Stecklein Qwest Wholesale CRPM

303 382-5770

--Original Message-- From: Balvin, Elizabeth [mailto:ebalvin@covad.com] Sent: Friday, October 07, 2005 4:22 PM To: Stecklein, Lynn Subject: RE: PC060105-01 Update Lines in Service Report

Lynn,

I believe Qwest mis-understood my “clarifying” request…as identified in the updated response:

Qwest’s Lines in Service report was built as a response to a CMP request and currently is created from data contained in Qwest’s Network back-end systems, which inventory the circuits and lines by the circuit ID/working telephone number. These systems are not used for billing or account maintenance; rather, they are used for inventory and trouble reporting only. For this reason, the source system does not contain the SBN or billing address, nor are the fields available to contain this information. The billing systems, which contain this information, don’t communicate with the inventory and trouble reporting systems.

I understood that the back-end systems used to generate the “lines in service” report did not house the SBN or billing address but the fact is that Qwest does “house” this information. Thus, I continue to request that the “existing” information be extracted “from whatever source” and provided for on the “Line In Service Report”. The original request did not ask that the back-end systems be expanded to house this information, thus I don’t believe an updated request is needed.

Thanks,

Liz

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Friday, September 30, 2005 11:54 AM To: Balvin, Elizabeth Subject: PC060105-01 Update Lines in Service Report

Hi Liz,

This is a follow up to the discussion we had in the August CMP Meeting regarding the denial on PC060105-01 Update Lines in Service Report. (See Meeting Minutes below) We have determined that the cost to combine the two systems so that the billing information you are requesting is included in the Lines in Service Report is economically not feasible. The denial attached has been revised to reflect the new project description and costs. Let me know if you have any questions.

Thanks,

Lynn Stecklein Qwest Wholesale CRPM 303 382-5770

8/17/05 CMP Meeting

PC060105-1 Update Lines In Service Report

Liz Balvin – Covad stated that she had questions regarding the denial. She said that Qwest refers to backend systems to generate the reports and wants to understand what the system has. Liz said that she wants the SBN at a minimum and would like a call to further discuss.

Laura McGhghy – Qwest stated that the data we are currently providing is existing data. {Comment received from Eschelon: from the MR-8 report]. She said that she was not sure what other systems would be needed for additional data and what that level of effort would be. [Comment received from Eschelon: Laura said they don’t have the fields in LMOS and TIRKS.]

Liz Balvin – Covad said that they would like to expand the report. She said that the report is an extract from LMOS and Tirks [Comment received from Eschelon: and she did not ask that Qwest get the data from those systems.] Liz said that she needs to expand the line and service report to create fields there and extract data elsewhere.

Laura McGhghy – Qwest said that she would take back to determine if possible.

Liz Balvin – Covad asked if the $500K to expand was because of LMOS and Tirks.

Laura McGhghy – Qwest said yes.

Liz Balvin – Covad said that Qwest already has the information and that they are just asking for the information on the report. [Comment received from Eschelon: Liz said wherever Qwest extracts the data from works for her.]

Laura McGhghy – Qwest said that we will look at that possibility.

Jill Martain – Qwest stated that we will talk offline with Covad.

10/19/05 Product/Process CMP Meeting

Jim Recker/Qwest stated that after multiple internal and external meetings, Qwest has determined that to implement this request would require a very manual intensive process. He said that this process would require that the status be checked multiple times and that we were unable to find a way to mechanize that process. Jim said that input was requested from other CLECs regarding this request. He said that Eschelon provided input on specific products. He said that based on the changes required for this request, Qwest is denying this CR because there is no demonstrable benefit to Qwest. Bonnie Johnson/Eschelon said that when Eschelon looked at this request they determined that they had no problem with the all or nothing regarding (Comments to minutes received from Eschelon 10/27/05) the specific products and request types McLeod listed in the CR. Bonnie also thanked Qwest for saying that there was no demonstrable benefit to only Qwest because Qwest cannot determine what business benefit a CR has for a CLEC.

9/21/05 Product/Process CMP Meeting

Jim Recker/Qwest stated that this CR is requesting that Qwest provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. Jim stated that Qwest did research the feasibility of making this optional. Jim said that we have determined that we would not be able to make this as an option due to the fact that we would not know who would call and who would not. He said that this would have to be done for all CLECs. He said that we continue to evaluate this CR to determine the feasibility of other options. Bonnie Johnson/Eschelon asked if this is applicable on basic installs only. Jim Recker/Qwest said yes, for basic cuts. Jim asked if the CLECs wanted Qwest to move forward with this request. Bonnie Johnson/Eschelon said that she would like to take this back and determine if (Comment to minutes received from Eschelon 9/30/05) moving forward with this request would have a negative impact to Eschelon since this would not be optional. Bonnie said Eschelon had not reviewed internally because they thought this could be optional. Bob Eggert/SBC asked if this was for basic services and not special access. Jim Recker/Qwest said that this was applicable if LX-- was on the order. Jill Martain/Qwest stated that this applied to 2 wire, 4 wire UBL. Jill Martain /Qwest asked if the CLECs had comments on whether they want to have Qwest pursue this request to send their comments to the CMP mailbox. Jim Recker/Qwest stated that we would provide a readout in the October meeting

8/17/05 Product/Process CMP Meeting

Jim Recker - Qwest stated that Qwest has been meeting internally to discuss this request and that we are in the evaluation stage. [Comment received from Eschelon: Jim said that Qwest has not identified all of the impacts.] Jim said that the status of this CR will move to be Evaluation.

8/3/05 E-mail from McLeod

Thanks for your help Lynn!!!

--Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Wednesday, August 03, 2005 1:22 PM To: Schug, Adam C. Subject: RE: CR = PC063005-1

Hi Adam,

I am including (see below) the meeting minutes from the July CMP Meeting where this CR was discussed. In that meeting, the CR moved to a presented status. Qwest is currently reviewing this request to determine options, feasibility, etc. and will provide a response either in the August or September CMP Meeting. Let me know if you have further questions.

Thanks,

Lynn Stecklein

Qwest Wholesale CRPM

303 382-5770

--Original Message-- From: Schug, Adam C. [mailto:Adam.Schug@mcleodusa.com] Sent: Wednesday, August 03, 2005 12:13 PM To: Stecklein, Lynn Subject: CR = PC063005-1

Lynn, I was wondering where we are at with the above change request and what happens next. Can you please provide me with an update.

Thanks

Adam C. Schug McLeodUSA Star Quality Certified Center of Excellence Customer Fulfillment Technical Team Lead Mountain & Central Region (319) 790-6332

7/20/05 Product/Process Meeting

Michelle Sprague - Mcleod reviewed the description of this CR. She said that McLeod would like Qwest to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. She said that in today’s process, Qwest contacts the CLEC to notify them that the cut is complete, the CLEC then completes their testing and verification, the CLEC then contacts Qwest back to let them know that the cut is accepted. Michelle said that in the future process, they would like Qwest to automatically assume the cut is accepted if the CLEC does not contact them back within 2 hours. Bonnie Johnson - Eschelon asked if this would include basic or coordinated cuts. Michelle Sprague - McLeod said that this request would not include new loops (Comments to minutes from Eschelon 7/27/05) and coordinated cuts because those are managed but does include basic conversions. She said that on the CR she requested a two hour time frame but was open to changing the timeframe if two hours wouldn’t work. Jeff Sonnier - Sprint asked if there was a possibility that Qwest could complete the circuit and then later find out the circuit didn’t complete and that there is a problem. Michelle Sprague - Mcleod said that if the CLECs are doing adequate testing this is unlikely. Jeff Sonnier - Sprint asked what the proposed suggested interval. Michelle Sprague - Mcleod said that they are suggesting 90 minutes because 2 hours may be too long. Bonnie Johnson - Eschelon said that there must be a standard interval now. She said that if Qwest doesn’t get a call it goes into a jeopardy status. Bonnie asked if Qwest has researched the optional aspect of this change. (Comments to minutes from Eschelon 7/27/05) Qwest said that they had not but did discuss it on the clarification call. Liz Balvin - Covad said that they may want McLeod to revise the CR to include specifications on these two items. Jill Martain - Qwest stated that this CR will move to a presented status.

7/12/05 Clarification Meeting

Attendees: Michelle Sprague - Mcleod, Steph Prull - Eschelon, Kim Isaacs - Eschelon, Ev Montez - Qwest, Kathy Ocken - Qwest, Deb Smith - Qwest, Lori Langston - Qwest, Lynn Stecklein - Qwest

Review Descripion of Change

Lynn Stecklein - Qwest reviewed the description of change. McLeod would like Qwest to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. In today’s process, Qwest contacts the CLEC to notify them that the cut is complete, the CLEC then completes their testing and verification, the CLEC then contacts Qwest back to let them know that the cut is accepted. Future process, we would like Qwest to automatically assume the cut is accepted if the CLEC does not contact them back within 2 hours.

Discussion: Michelle Sprague - Mcleod stated that they are open to any timeframe and said that they started with the 2 hour timeframe as an example. She said that Mcleod has been working with the Qwest Account Team and they suggested that Mcleod submit a CMP CR. She said that they are submitting a large volume of UNE-P to UNE-L orders and by eliminating the completion call they could save on resources. Lynn Stecklein - Qwest asked Mcleod what products would be impacted by this request. Michelle Sprague - Mcleod said that the request was submitted for the Unbundled Loop Product but she did not want to limit the scope. She said that other CLECs may have other recommendations. Michelle said that this would not impact coordinated hot cuts. Lori Langston - Qwest asked what Mcleod had in mind if the orders were completed late in the day. Michelle Sprague - Mcleod said that they would consider decreasing the timeframe to one hour to accommodate the 5:00 close. Kathy Ocken - Qwest stated that changing it to 60 minutes to could frame due time issues. Deb Smith - Qwest said that eliminating the call would pose a risk on brand new loop orders because of the testing and complexity involved. She said that we would need to limit to reuse situations. Steph Prull - Eschelon said that she would like to keep this process optional due to the impact this could have on smaller CLECs. Michelle Sprague - Mcleod said that she agreed and that the CLEC could request this option when they sign their Interconnection agreement. Lori Langston - Qwest asked what happens today when we don't receive a call from the customer to close. Kathy Ocken - Qwest stated that the order is place in a jeopardy status and follows the CNR process. The customer has to supp the order with a new due date. Ev Montez - Qwest said that she had a concern if this process included DS1 due to the testing and complexity involved. Kim Isaacs - Eschelon said that they agreed that DS1 should not be included because they wanted to test to make sure they have a good loop.

Confirm Products Impacted Michelle Sprague - Mcleod stated that this CR was requesting this process on Unbundled Loop but said that she wanted to keep the option open for products

Establish Action Plan Lynn Stecklein - Qwest stated that Mcleod requested that this CR be included as a Walkon in the July 20th Product/Process CMP Meeting.


CenturyLink Response

October 11, 2005

Final Response

For Review by the CLEC Community and Discussion at the October 19, 2005 CMP Meeting

TO: Chelsea Payne McLeodUSA

SUBJECT: CLEC CR PC063005-1 Cease completion verification calls

Description of Change: McLeod would like Qwest to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. In today’s process, Qwest contacts the CLEC to notify them that the cut is complete, the CLEC then completes their testing and verification, the CLEC then contacts Qwest back to let them know that the cut is accepted. Future process, we would like Qwest to automatically assume the cut is accepted if the CLEC does not contact them back within 2 hours.

Qwest Response:

During the ad hoc call, McLeod indicated that this request is for products associated with basic cuts (existing unbundled analog loops). In addition, during the CMP meeting McLeod stated that the 2 hour interval in the CR should be 90 minutes and to make this function optional.

Qwest has researched and analyzed how to meet the expected deliverable to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. Qwest has determined that it would require the following changes:

A new manual process for tracking and/or monitoring the interval of the order after completion of the lift and lay would be required, as well as reviewing the order multiple times to check status. Since this would involve only basic reuse (lift and lay) orders, it would require Qwest to sort the orders that need to be tracked which would include reassigning orders that would be completed late in the day. Making this process optional would be manually intensive since it would require CLEC by CLEC tracking. Qwest has previously implemented process changes that have removed manual intervention and monitoring and included steps to ensure quality, where the requested process change would be a regression of current processes and would reinstitute a manual process.

Qwest is denying this request because the requested change does not result in a demonstrable business benefit.

Sincerely, Qwest

For Review by the CLEC Community and Discussion at the September 21, 2005 CMP Meeting

September 21, 2005

Mcleod

SUBJECT: CR # PC063005- Cease completion verification calls

This letter is in response to Mcleod's Change Request (PC063005-1 Cease completion verification calls). This CR requests that Qwest McLeod would like Qwest to provide the option to CLECs to bypass the process of calling Qwest back following the completion of an all day basic cut. In today’s process, Qwest contacts the CLEC to notify them that the cut is complete, the CLEC then completes their testing and verification, the CLEC then contacts Qwest back to let them know that the cut is accepted. McLeod would like Qwest to automatically assume the cut is accepted if the CLEC does not contact them back within 2 hours.

Qwest would like to keep this CR in evaluation status in order to continue with analysis of the existing process and look at potential solutions for this change request. Qwest will provide an updated response at the October CMP meeting.

Sincerely,

Qwest Communications


Open Product/Process CR PC072009-1 Detail

 
Title: Deconsolidating Process for Resale, UNE P CSRs
CR Number Current Status
Date
Area Impacted Products Impacted

PC072009-1 Completed
11/18/2009
Ordering Resale, UNE-P
Originator: Bilow, Joyce
Originator Company Name: McLeodUSA
Owner: Wells, Susie
Director:
CR PM: Stecklein, Lynn

Description Of Change

McLeod d/b/a Pataec Business Services is requesting a Deconsolidating Matrix Process for submit LSRs. The qwest documentation (PCAT) matrix is based on consolidating CSRs versus deconsolidating CSRs.

Qwest (PCAT) documentation states:

The process to deconsolidate a single account into two accounts (the end result being the current account plus one new one) using one LSR is only available if the end result involves like products and services and the end-user address is not changing. If deconsolidation of an account involves splitting an existing account into more than two accounts, there must be a separate LSR issued for each additional new accoun

established. The LSRs should be related via a Related Purchase Order Number (RPON) and the Manual Indicator field must be populated with “Y”.

The One paragraph is not clear on the activity and the process for deconsolidating an already migrated account.

Qwest CSIE center has requested McLeod to follow the consolidated Matrix. ACT =C, LNA = C, Recap features = N and Directory Listing of ‘O’ and ‘I’.

The PCAT Process documentation needs to be updated to include a Deconsolidating Matrix to assist in the LSR ordering process.


Status History


Project Meetings

11/18/09 Product/Process CMP Meeting

Mark Coyne-Qwest said this change was effective on 10/1/09 and asked if there were any objections to closure. Julia Redman-Carter-PAETEC said this CR could be closed.

10/21/09 Product/Process CMP Meeting

Mark Coyne-Qwest said this change was effective on 10/1/09 and asked if there were any objections to closure. Joyce Bilow-PAETEC asked if this could be kept open until they can use the process. Mark Coyne-Qwest said that we will leave this open and revisit in the November CMP Meeting.

9/16/09 Product/Process CMP Meeting

Mark Coyne-Qwest said a clarification meeting was held on 7/28/09 and as a result Qwest will be making updates to the PCAT. He said the level 2 notice was sent out on 9/10/09 and is currently in review to become effective 10/1/09.

8/19/09 Product/Process CMP Meeting

Joyce Bilow-PAETEC said they were requesting a process for submitting orders when they try to deconsolidate CSRs. She said when the customer has migrated and they want to break up their CSR into separate CSRs, they are finding that when they submit the CSR, Qwest is requesting they submit as consolidated. She said they are having systems issues with fatals on the backend side and orders are in limbo. They are requesting that Qwest create a matrix for the deconsolidated so these orders can be processed in XML. Susan Lorence-Qwest said a clarification meeting was held on 7/28/09 and asked if there were any other questions. Susan said that we will be being doing further investigation on this CR.

PC072009-1 Deconsolidating Process for Resale, UNE-P CSRs Clarification Meeting – July 28, 2009

Attendees: Joyce Bilow-PAETEC, Kim Isaacs-Integra, Bonnie Johnson-Integra, Susie Wells-Qwest, Denise Martinez-Qwest, Sandie Tekavec-Qwest, Lynn Stecklein-Qwest

Lynn Stecklein-Qwest said the purpose of this meeting is to clarify the CR submitted by PAETEC (Deconsolidating Process for Resale, UNE-P CSRs). She reviewed the following description:

PAETEC is requesting a Deconsolidating Matrix Process for submit LSRs. The Qwest documentation (PCAT) matrix is based on consolidating CSRs versus deconsolidating CSRs. Qwest (PCAT) documentation states: The process to deconsolidate a single account into two accounts (the end result being the current account plus one new one) using one LSR is only available if the end result involves like products and services and the end-user address is not changing. If deconsolidation of an account involves splitting an existing account into more than two accounts, there must be a separate LSR issued for each additional new account established. The LSRs should be related via a Related Purchase Order Number (RPON) and the Manual Indicator field must be populated with “Y”. The One paragraph is not clear on the activity and the process for deconsolidating an already migrated account. Qwest CSIE center has requested McLeod to follow the consolidated Matrix. ACT =C, LNA = C, Recap features = N and Directory Listing of ‘O’ and ‘I’. The PCAT Process documentation needs to be updated to include a deconsolidating Matrix to assist in the LSR ordering process.

Joyce Bilow-PAETEC said they have been able to get one order through with the activity of ‘C’ and had to change the line level to a new with a listing of an In and Out. She said with the LNA of N, they have to include an appointment time. This is not a new line but is a change to the line. She said if they submit the order with the “C’activity, recapped the features (8/4/09 - Comments to minutes received from PAETEC in CAPS) IMA WILL RETURN A FATAL RESPONSE “FEATURES ARE ALREADY ON THE LINE A LSR ACTIVITY OF AN “C” REQUIRES AN In and Out listing AND ONLY ONE LML PER LOCATION IS ALLOWED. They recapped the current listing on the CSR as the Out and put the new listing for this customer on the CSR. She said in the past, they have done this as New. Joyce said their concern is the LNA of N is not really an N but a change. She said the users have contacted the CSIE and everyone they talk to tells them to do something different. She said it has been very frustrating to only get 1 order through. She said they have submitted as an N and documenting everything in the LSR notes and now they are being told they have to use the activity of a C. JOYCE STATED SHE WOULD LIKE A matrix TO ASSIST IN THE LSR ORDERING PROCESS. Bonnie Johnson-Integra said in the ordering overview there is a section called deconsolidating and consolidating but it says the N state has to be the same product.

Joyce Bilow-PAETEC said she referenced the same thing by product but everything is geared toward consolidating MATRIX vs. deconsolidating.

Susie Wells-Qwest asked if at one time PAETEC was doing the activity type of N.

Joyce Bilow-PAETEC said the (8/4/09 - Comments to minutes received from PAETEC in CAPS) LSR overall activity, the line activity and the listing was an N. They would note this was a deconsolidation with no dispatch AND IN THE LAST 3 MONTHS the orders HAVE BEEN were getting rejected saying they had to use a C activity.

Susie Wells-Qwest said with the ACT of C, we run into issues with IMA.

Joyce Bilow-PAETEC said yes, if you use the activity of a C. She said the Line level can’t be a C because it recaps the features for the line and it will say the features are at that location. She said that if you use a C you have to do the In & Out and if that line doesn’t have a listing, they have been utilizing the listing at that location. Joyce said they were successful in processing 1 LSR. She said used the activity of C with the LNA of N for an active line. They recapped the feature because there was an additional line level USOC that was changed to a main line level USOC but they still put in the listing of an In and Out

Denise Martinez-Qwest asked if PAETEC could provide the examples.

Joyce Bilow-PAETEC said the LSR ID is 28626085. She said that the order that has been in limbo for 6 weeks is 28709993. Joyce said the users want to make sure the out listing doesn’t get taken out.

Denise Martinez-Qwest asked if they were issuing these orders on specific types of products vs. others.

Joyce Bilow-PAETEC said mostly on the QPP Resale, UNE-P side.

Denise Martinez-Qwest asked if anyone else on the call was having these issues or had any other comments.

Kim Isaacs-Integra said it is always difficult to do these types of orders and the more documentation they have the better.

Denise Martinez-Qwest said she agreed and wanted to make sure there were no other issues they need to look at when they take this offline.

Joyce Bilow-PAETEC said they need to know exactly what is required on the LSR. She said that if they have to use an activity of N they are going to have to set an appointment time. They don’t want to take the customer down and if you dispatch, that could happen. (8/4/09 - Comments to minutes received from PAETEC in CAPS) JOYCE ALSO REQUESTED EXACTLY WHAT NEEDS TO BE NOTED IN THE LSR NOTES FOR A DECONSOLIDATION OF A CSR.

Lynn Stecklein-Qwest said that PAETEC will be presenting this CR in the August CMP Meeting


Open Product/Process CR PC013003-1 Detail

 
Title: Email FOC's to CLEC's
CR Number Current Status
Date
Area Impacted Products Impacted

PC013003-1 Withdrawn
2/19/2003
Provisioning Directory Listings
Originator: Listerud, Paula
Originator Company Name: North Star Access
Owner: To Be Determined
Director:
CR PM: Andreen, Doug

Description Of Change

Email the FOC's to CLEC's instead of faxing them.

Expected Deliverable:

Save paper and time.


Status History

01/30/03 - CR Submitted

02/03/03 - CR acknowledged by P/P CMP Manager.

02/04/03 - Contacted customer. Rec'd e-mail from Paula Listerud at NorthStar Access they have decided to withdraw change request as it is duplicate of SCR020602-1 submitted by AT&T and do not need to schedule a Clarification Meeting.

02/05/03 - CR Posted to Web. Status of CR changed to pending withdrawal.

02/19/03 - February CMP Meeting - Status of CR was discussed. Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

02/19/03 February CMP Meeting Linda Sanchez-Steinke with Qwest said that NorthStar Access submitted the change request and there was already a Systems Change Request, SCR020602-1, asking for Directory Listing FOCs to be e-mailed. NorthStar Access has decided to withdraw Product and Process CR PC013003-1. Qwest will update the project meetings section of this change request with the e-mail from Paula Listerud with NorthStar Access stating they wish to withdraw. The CLEC community agreed to change the status of this CR to Withdrawn.

2/4/03 2:24 p.m. From: Paula Listrud To: "'Linda Sanchez-Steinke'" cc:

Subject: RE: Change Request PC013003-1, Email FOC's to CLEC's

Linda:

NorthStar wants to withdraw this request as it is a duplicate request. Additionally, we do not need to schedule a Clarification meeting on PC013003-1.

Thank you,

Paula Listerud Process Analyst NorthStar Access

2/4/03 2:04 p.m. From: Linda Sanchez-Steinke To: paulal@nsatel.com cc:

Subject:Change Request PC013003-1, Email FOC's to CLEC's

Hi Paula -

As a follow up to our discussion this afternoon regarding the pending withdrawal status of Change Request PC013003-1, would you please send me an e-mail stating that NorthStar wants to withdraw the CR because it is a duplicate of the AT&T change request, SCR020602-1. Would you also confirm in your e-mail that NorthStar does not want to schedule a Clarification Meeting on PC013003-1.

Also, the Pending withdrawal change request, PC013003-1, will be on the agenda for the Product & Process CMP Meeting on 2/19/03.

Please call me if you have any questions.

Thank you

Linda Sanchez-Steinke Change Request Project Manager Qwest 303-965-0972


Open Product/Process CR PC022403-5 Detail

 
Title: Perform Line Moves for Line Shared orders at no charge to the CLEC/DLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-5 Completed
2/24/2003
Pre-Ordering, Ordering, Provisioning Line Sharing
Originator: Boudhaouia, Jamal
Originator Company Name: Qwest Corporation
Owner: Boudhaouia, Jamal
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC Community the opportunity to request Line Moves in certain circumstances for a voice customer whose existing line does not currently qualify for ADSL service. This Line Move will be provided to the CLEC/DLEC at no charge.

Line Move is defined as moving the existing customer loop that did not qualify for ADSL service to an existing available spare copper facility that qualifies for ADSL service.

This offering is being made for Line Sharing family of products (defined as Other below) only.

This CR may be subject to the Condition described under Change of Law provisions of the SGAT (Section 2.2).

Proposed Implementation Date: 4/15/03


Status History

02/24/03 - Ad Hoc Meeting Notification Distributed

02/24/03 - Clacrification Meeting

03/03/03 - Ad Hoc Meeting

03/11/03 - CLEC input meeting 1

03/14/03 - Initial Level 4 Notification distributed

03/19/03 - Discussed at CMP Meeting

03/14/03 - Final Level 4 Notification distributed

04/15/03 - Change Implemented

04/16/03 - Discussed at CMP Monthly Meeting

05/21/03 - Closed at CMP Monthly Meeting


Project Meetings

========================================================== CMP Meeting 05-21-03

Buckmaster-Qwest stated that the changes were implemented on 4/15 and Qwest would like to close the CRs. Zulevic-Covad stated that he would like to leave PC022403-3 open for another month. Johnson-Eschelon stated that she wanted to leave PC022403-2 open for another month. Zulevic-Covad stated that there was an issue that he had expected Buckmaster to contact him on. Buckmaster-Qwest stated that she would send Zulevic an e-mail after the meeting. ==========================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that the new process was implemented on 4/15. Zulevic-Covad asked if the change included line splitting. Buckmaster-Qwest stated that it did. Zulevic-Covad asked if Qwest would publish a process document outlining this process. Buckmaster-Qwest stated that the Assignments Process Document on the Web describes the process. She stated that she would check to see if it included a description of the conditioning process. Zulevic-Covad asked if a line move was a 5 day interval. Buckmaster-Qwest stated that it was. Zulevic-Covad asked what happened if a CLEC placed an ‘N’ in the SCA field. Buckmaster-Qwest stated that she did not know, but that she would find out. Johnson-Eschelon asked that Qwest document this in the process document. Zulevic-Covad asked if CLECs provided Qwest with conditioning standards. Boudhaouia-Qwest stated that Qwest would condition lines to the most current industry standards. Boudhaouia, Berard and Zulevic conducted a lengthy discussion about various conditioning standards. Zulevic-Covad asked if the Qwest conditioning standards for retail were the same as wholesale. Boudhaouia-Qwest stated that they were. Buckmaster-Qwest stated that the only change these CRs were implementing was a cessation of charges. Powers-Tel West asked if the conditioning interval was different for retail and wholesale. Buckmaster-Qwest stated that it was 5 days longer for retail.

===============================================

03-19-03 - CMP Meeting

Bucmaster-Qwest reviewed where the CRs were in the process. Zulevic-Covad asked if Qwest had analyzed the potential to allow CLECs to grant blanket approval. Buckmaster-Qwest stated that Qwest is still evaluating that option, but would not implement it until after the first set of changes were implemented on 4/15. Van Meter-AT&T asked that AT&T be added to the attendee list for the Ad Hoc Meeting.

================================================

CLEC Input Meetings March 11, 2003 March 12, 2003 March 13, 2003

Attendees – March 11, 2003 Sharon Van Meter – AT&T Liz Balvin – WorldCom John Berard – Covad Mike Zulevic – Covad Jennifer Arnold – US Link Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Dave Hahn – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Laurel Neher – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Deb Smith – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 12, 2003 Liz Balvin – WorldCom John Berard – Covad Donna Dix – US Link Bonnie Johnson – Eschelon Lori Mendoza – Allegiance Chris Connor - Qwest Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 13, 2003 Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Meeting Minutes March 11, 2003

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Buckmaster-Qwest to present the first three CRs (PC022403-2, -3, -4) for discussion. Buckmaster-Qwest presented CRs –2 and -4. Soderlund-Qwest described that process for requesting conditioning. She stated that process was unchanged from today. Zulevic-Covad asked if Qwest first checked for alternate facilities before it conditioned the line. Buckmaster-Qwest stated that was true. Zulevic-Covad asked what would happen if there was not a Y in the SCA field and the line had load coils on it. Buckmaster-Qwest stated that Qwest would reject the order and tell the CLEC to authorize conditioning. Zulevic-Covad asked if the CLECs could give Qwest a blanket authorization to condition, if necessary, on every order. Buckmaster-Qwest stated that she would check on that option, but believed that it was outside the scope of this CR. Zulevic-Covad stated that he was interested because Covad had orders previously delayed, unnecessarily, for this. Buckmaster-Qwest described –3. Schwartze-Qwest described the process to request conditioning. She stated that the process included noting that conditioning was authorized in the remarks field. Zulevic-Covad asked what the process was for Qwest retail requests. Buckmaster-Qwest stated that she was not aware of the process, but would find out.

Boudhaouia-Qwest briefed CRs –5 and -7. Soderlund-Qwest described the process to request line move and UDC removal. She stated that Qwest always looks to do a line move or UDC removal. If these options are not available, Qwest looks for a Y in the SCA field before it conditions a line. Zulevic-Covad asked how the intervals would work. Soderlund-Qwest stated that the line move was a 5-day interval, and that conditioning is a 15-day interval. Boudhaouia-Qwest stated that Qwest will always attempt to try a line move, then perform UDC removal, and finally to condition the line. Zulevic-Covad asked when he would get a notification that a line needed to be conditioned. Soderlund-Qwest stated that the notification would go out as soon as the assignments group knew the line needed to be conditioned. Berard-Covad asked if a CLEC should always check the RLDT before placing a request. Buckmaster-Qwest stated that the CLEC should check in the RLDT for spare copper facilities, but that Qwest would check automatically once the request came in. Berard-Covad asked if the CLECs needed to provide some proof that they had accessed the RLDT when they submitted their request. Boudhaouia-Qwest stated that they did not.

Boudhaouia-Qwest presented CR –6. Schwartze-Qwest stated that the process for UNE-P and resale would mirror the line move and UDC removal process.

Boudhaouia-Qwest presented CR –8. Berard-Covad asked if a CLEC, for planning purposes, could look up the presence of a single line UDC in the ICONN database. Boudhaouia-Qwest stated that when CLECs issue a line share request with a Y in the SCA field, Qwest will attempt to move the line first and them to remove the UDC. He stated that the lack of a Y in the SCA field would cause a FOC back requesting authorization for conditioning.

White-Qwest stated that Qwest had three “take-aways” that they would address at the next meeting. Zulevic-Covad stated that Covad appreciated Qwest initiating these CRs.

March 12, 2003 White-Qwest introduced the attendees and described the purpose of the meeting. Johnson-Eschelon stated that she had missed the previous day’s meeting and would like an overview of what was discussed.

Buckmaster-Qwest reviewed CRs –2 and –4. Johnson-Eschelon confirmed that there was no change to the existing process. Buckmaster-Qwest reviewed –3. Schwartze-Qwest reviewed the process. Johnson-Eschelon asked if the CLECs should mark for manual handling. Schwartze-Qwest stated that was not necessary. Johnson-Eschelon asked if this information would be posted to the Web site. Buckmaster-Qwest stated that this information would be included in the PCAT.

Boudhaouia-Qwest reviewed –5 and –7. Soderlund-Qwest briefed the process to request the conditioning. Johnson-Eschelon asked if there needed to be any special markings on the request. Buckmaster-Qwest stated that if the CLEC puts a Y in the SCA field in every instance, Qwest will have authorization to condition the line for each request. Johnson-Eschelon asked if this process removed the decision making responsibility from the CLEC. Boudhaouia-Qwest stated that Qwest would first try to do a line move, the UDC removal, then bridge tap/load coil removal. He summarized that it does remove the decision responsibility from the CLEC.

Boudhaouia-Qwest reviewed –6. Schwartze-Qwest stated that the only change from the line sharing was that for resale and UNE-P the remarks section must have “conditioning authorized.”

Boudhaouia-Qwest reviewed –8.

White-Qwest stated that Qwest had three action items from the last meeting. He asked Buckmaster to review the first. Buckmaster-Qwest stated that the first action item was to describe the retail process. Connor-Qwest described the retail request process. Berard-Covad asked if retail accessed the RLDT. Buckmaster-Qwest stated that retail did not use the RLDT.

White-Qwest stated that the next action item was an investigation of the possibility of CLECs granting blanket conditioning approval. Buckmaster-Qwest stated that she would like the CLECs to give Qwest an opportunity to get the process running and then to request the blanked authorization. Johnson-Eschelon stated that Eschelon would be interested in giving Qwest the same authorization.

White-Qwest stated that the final action item was related to putting a Y in the SCA field. Boudhaouia-Qwest stated that the CLEC must have a Y in the SCA field to give Qwest authorization to condition the line. Berard-Covad asked what the process was if there was not a Y in the SCA field and the line needed conditioning. Soderlund-Qwest stated that the process was to follow the IMA jeopardy-back process.

Johnson-Eschelon asked if the CLECs needed to put the conditioning authorized on the LSR with which they requested the add DSL. Soderlund-Qwest stated that Johnson was correct.

White-Qwest thanked the attendees and adjourned the meeting.

March 13, 2003 There were no CLEC attendees at the meeting. White-Qwest adjourned the meeting at 2:15 PM MT.

==================================================

Ad Hoc CMP Meeting March 3, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Denny Grahm – Qwest Barry Orrel – Qwest Laurel Neher – Qwest Joy McConnel-Couch – Qwest Joan Pfeffer – Qwest Craig Suellentrop - Qwest Ray Wilson – Qwest Cindy Schwartze – Qwest Deb Smith – Qwest Bob Mohr – Qwest Eric Yohe – Qwest Cindy Buckmaster – Qwest John Berard – Covad Julie Pickar – US Link Donna Dix – US Link Erica Beamus - WorldCom Chris Robish - Contact Monica Avila – Veritech Wayne Hart – Idaho PUC Kirk Hundertmark – Twin Rivers Valley Telecom Bonnie Johnson – Eschelon

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the Ad Hoc CMP Meeting.

Buckmaster-Qwest defined line conditioning and presented CRs PC022403-2, -3, and –4. She also proposed that the input cycle for the CRs consist of three 2-hour meetings on 3/11, 3/12, and 3/13. There were no objections to the proposed input cycle.

Zulevic-Covad asked if CLECs would be required to submit an LSR with a Y in the SCA field. Buckmaster-Qwest stated that they would.

Johnson-Eschelon stated that she was glad to see these CRs. She stated that currently when a CLEC orders Qwest DSL they must order it as a feature after a line install. She asked if these CRs would change that process. Buckmaster-Qwest stated that they did not. Johnson-Eschelon asked what these CRs did to loop qual. Buckmaster-Qwest stated that CLECs would continue to use the Raw Loop Data Tool to ascertain interval information.

Berard-Covad asked if putting a Y in the SCA field would automatically generate a 15 day interval. Buckmaster-Qwest stated that it would not. Zulevic-Covad asked if CLECs put a Y in the SCA field on all LSRs would the work be accomplished to industry specifications or would the work include a removal of all encumbrances. Buckmaster-Qwest stated that Qwest would condition to the CLEC’s DSL specifications but would not condition automatically to the tech pub standard. Zulevic-Covad asked if Qwest would provide a summary of the CR dependencies. Buckmaster-Qwest stated that she would. Robish-Contact stated that bridge taps do not affect his product. He asked if they would be required to remove bridge taps. Buckmaster-Qwest stated that they would not. Hundertmark-Twin Rivers asked if any of these CRs addressed CLEC DSL on a resold circuit because he had several issues with CRs of that variety. Buckmaster-Qwest stated that that issue was not addressed by any of these CRs. Schultz-Qwest stated that Qwest could set up another ad hoc meeting to discuss Twin River’s issues or add an item to the agenda of the next CMP Monthly Meeting. Hundertmark-Twin Rivers stated that he would prefer to discuss it at a monthly meeting.

Retka-Qwest presented CRs PC022403-5, -6, -7, and –8. Johnson-Eschelon stated that it sounded like there were several processes the CLECs would use for the various product varieties. Retka-Qwest stated that the CLECs should always consult the Raw Loop Data Tool first. Buckmaster-Qwest stated that this was an issue the team could work out during the input sessions on the 11th, 12th and 13th. Zulevic-Covad asked if there was a way to determine if the same customer has two lines on an UDC. Retka-Qwest stated that the only posting would be for customers with only one line on a UDC. Dix-US Link stated that there were errors in the RLDT. Schultz-Qwest asked Dix-US Link to contact her service manager. Dix-US Link stated that she did not know who that was. Schultz-Qwest stated that she would contact the US Link service manager and ask him/her to contact Dix. Zulevic-Covad asked if line moves were included in PC022403-5. Retka-Qwest stated that they were only included in situations where there was a spare copper loop. Buckmaster-Qwest stated that the intent was to giver the CLECs the facility to provision data on. She stated that a line move would be accomplished to accommodate data. Berard-Covad asked Retka to clarify what a UDC was. Retka-Qwest stated that a UDC was a two line pair gain at a customer premise or a cross box near a customer premise. Zulevic-Covad asked if CLECs were expected to use the RLDT before they place an order. Buckmaster-Qwest stated that was Qwest’s intent. Retka-Qwest recommended that the input process for the four latter CRs be conducted during the previously proposed meetings on the 11th, 12th, and 13th. There were no objections. There were no further questions.

The meeting was adjourned.


Open Product/Process CR PC022403-6 Detail

 
Title: Perform Line Moves and UDC Removal for Qwest DSL Resale and Qwest DSL on UNE P orders at no charge to the CLEC/DLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-6 Completed
2/24/2003
Pre-Ordering, Ordering, Provisioning Resale UNE-P
Originator: Boudhaouia, Jamal
Originator Company Name: Qwest Corporation
Owner: Boudhaouia, Jamal
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC Community the opportunity to request Line Moves and UDC Removal in certain circumstances for a voice customer whose existing line does not currently qualify for Qwest DSL service. This Line Move and UDC Removal will be provided to the CLEC/DLEC at no charge.

Line Move is defined as moving the existing customer loop that did not qualify for Qwest DSL service to an existing available spare copper facility that qualifies for Qwest DSL service.

UDC removal will performed under the following conditions:

- The UDC is serving the target customer

- The UDC is a two line system

- Only one channel is working on the UDC System

This offering is being made for Qwest DSL Resale and Qwest DSL on UNE-P only.

Proposed Implementation Date: 4/15/03

This CR may be subject to the Condition described under Change of Law provisions of the SGAT (Section 2.2).


Status History

02/24/03 - Ad Hoc Meeting Notification Distributed

02/24/03 - Clacrification Meeting

03/03/03 - Ad Hoc Meeting

03/11/03 - CLEC input meeting 1

03/14/03 - Initial Level 4 Notification distributed

03/19/03 - Discussed at CMP Meeting

03/14/03 - Final Level 4 Notification distributed

04/15/03 - Change Implemented

04/16/03 - Discussed at CMP Monthly Meeting

05/21/03 - Closed at CMP Monthly Meeting


Project Meetings

========================================================== CMP Meeting 05-21-03

Buckmaster-Qwest stated that the changes were implemented on 4/15 and Qwest would like to close the CRs. Zulevic-Covad stated that he would like to leave PC022403-3 open for another month. Johnson-Eschelon stated that she wanted to leave PC022403-2 open for another month. Zulevic-Covad stated that there was an issue that he had expected Buckmaster to contact him on. Buckmaster-Qwest stated that she would send Zulevic an e-mail after the meeting. ==========================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that the new process was implemented on 4/15. Zulevic-Covad asked if the change included line splitting. Buckmaster-Qwest stated that it did. Zulevic-Covad asked if Qwest would publish a process document outlining this process. Buckmaster-Qwest stated that the Assignments Process Document on the Web describes the process. She stated that she would check to see if it included a description of the conditioning process. Zulevic-Covad asked if a line move was a 5 day interval. Buckmaster-Qwest stated that it was. Zulevic-Covad asked what happened if a CLEC placed an ‘N’ in the SCA field. Buckmaster-Qwest stated that she did not know, but that she would find out. Johnson-Eschelon asked that Qwest document this in the process document. Zulevic-Covad asked if CLECs provided Qwest with conditioning standards. Boudhaouia-Qwest stated that Qwest would condition lines to the most current industry standards. Boudhaouia, Berard and Zulevic conducted a lengthy discussion about various conditioning standards. Zulevic-Covad asked if the Qwest conditioning standards for retail were the same as wholesale. Boudhaouia-Qwest stated that they were. Buckmaster-Qwest stated that the only change these CRs were implementing was a cessation of charges. Powers-Tel West asked if the conditioning interval was different for retail and wholesale. Buckmaster-Qwest stated that it was 5 days longer for retail.

===============================================

03-19-03 - CMP Meeting

Bucmaster-Qwest reviewed where the CRs were in the process. Zulevic-Covad asked if Qwest had analyzed the potential to allow CLECs to grant blanket approval. Buckmaster-Qwest stated that Qwest is still evaluating that option, but would not implement it until after the first set of changes were implemented on 4/15. Van Meter-AT&T asked that AT&T be added to the attendee list for the Ad Hoc Meeting.

================================================

CLEC Input Meetings March 11, 2003 March 12, 2003 March 13, 2003

Attendees – March 11, 2003 Sharon Van Meter – AT&T Liz Balvin – WorldCom John Berard – Covad Mike Zulevic – Covad Jennifer Arnold – US Link Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Dave Hahn – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Laurel Neher – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Deb Smith – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 12, 2003 Liz Balvin – WorldCom John Berard – Covad Donna Dix – US Link Bonnie Johnson – Eschelon Lori Mendoza – Allegiance Chris Connor - Qwest Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 13, 2003 Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Meeting Minutes March 11, 2003

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Buckmaster-Qwest to present the first three CRs (PC022403-2, -3, -4) for discussion. Buckmaster-Qwest presented CRs –2 and -4. Soderlund-Qwest described that process for requesting conditioning. She stated that process was unchanged from today. Zulevic-Covad asked if Qwest first checked for alternate facilities before it conditioned the line. Buckmaster-Qwest stated that was true. Zulevic-Covad asked what would happen if there was not a Y in the SCA field and the line had load coils on it. Buckmaster-Qwest stated that Qwest would reject the order and tell the CLEC to authorize conditioning. Zulevic-Covad asked if the CLECs could give Qwest a blanket authorization to condition, if necessary, on every order. Buckmaster-Qwest stated that she would check on that option, but believed that it was outside the scope of this CR. Zulevic-Covad stated that he was interested because Covad had orders previously delayed, unnecessarily, for this. Buckmaster-Qwest described –3. Schwartze-Qwest described the process to request conditioning. She stated that the process included noting that conditioning was authorized in the remarks field. Zulevic-Covad asked what the process was for Qwest retail requests. Buckmaster-Qwest stated that she was not aware of the process, but would find out.

Boudhaouia-Qwest briefed CRs –5 and -7. Soderlund-Qwest described the process to request line move and UDC removal. She stated that Qwest always looks to do a line move or UDC removal. If these options are not available, Qwest looks for a Y in the SCA field before it conditions a line. Zulevic-Covad asked how the intervals would work. Soderlund-Qwest stated that the line move was a 5-day interval, and that conditioning is a 15-day interval. Boudhaouia-Qwest stated that Qwest will always attempt to try a line move, then perform UDC removal, and finally to condition the line. Zulevic-Covad asked when he would get a notification that a line needed to be conditioned. Soderlund-Qwest stated that the notification would go out as soon as the assignments group knew the line needed to be conditioned. Berard-Covad asked if a CLEC should always check the RLDT before placing a request. Buckmaster-Qwest stated that the CLEC should check in the RLDT for spare copper facilities, but that Qwest would check automatically once the request came in. Berard-Covad asked if the CLECs needed to provide some proof that they had accessed the RLDT when they submitted their request. Boudhaouia-Qwest stated that they did not.

Boudhaouia-Qwest presented CR –6. Schwartze-Qwest stated that the process for UNE-P and resale would mirror the line move and UDC removal process.

Boudhaouia-Qwest presented CR –8. Berard-Covad asked if a CLEC, for planning purposes, could look up the presence of a single line UDC in the ICONN database. Boudhaouia-Qwest stated that when CLECs issue a line share request with a Y in the SCA field, Qwest will attempt to move the line first and them to remove the UDC. He stated that the lack of a Y in the SCA field would cause a FOC back requesting authorization for conditioning.

White-Qwest stated that Qwest had three “take-aways” that they would address at the next meeting. Zulevic-Covad stated that Covad appreciated Qwest initiating these CRs.

March 12, 2003 White-Qwest introduced the attendees and described the purpose of the meeting. Johnson-Eschelon stated that she had missed the previous day’s meeting and would like an overview of what was discussed.

Buckmaster-Qwest reviewed CRs –2 and –4. Johnson-Eschelon confirmed that there was no change to the existing process. Buckmaster-Qwest reviewed –3. Schwartze-Qwest reviewed the process. Johnson-Eschelon asked if the CLECs should mark for manual handling. Schwartze-Qwest stated that was not necessary. Johnson-Eschelon asked if this information would be posted to the Web site. Buckmaster-Qwest stated that this information would be included in the PCAT.

Boudhaouia-Qwest reviewed –5 and –7. Soderlund-Qwest briefed the process to request the conditioning. Johnson-Eschelon asked if there needed to be any special markings on the request. Buckmaster-Qwest stated that if the CLEC puts a Y in the SCA field in every instance, Qwest will have authorization to condition the line for each request. Johnson-Eschelon asked if this process removed the decision making responsibility from the CLEC. Boudhaouia-Qwest stated that Qwest would first try to do a line move, the UDC removal, then bridge tap/load coil removal. He summarized that it does remove the decision responsibility from the CLEC.

Boudhaouia-Qwest reviewed –6. Schwartze-Qwest stated that the only change from the line sharing was that for resale and UNE-P the remarks section must have “conditioning authorized.”

Boudhaouia-Qwest reviewed –8.

White-Qwest stated that Qwest had three action items from the last meeting. He asked Buckmaster to review the first. Buckmaster-Qwest stated that the first action item was to describe the retail process. Connor-Qwest described the retail request process. Berard-Covad asked if retail accessed the RLDT. Buckmaster-Qwest stated that retail did not use the RLDT.

White-Qwest stated that the next action item was an investigation of the possibility of CLECs granting blanket conditioning approval. Buckmaster-Qwest stated that she would like the CLECs to give Qwest an opportunity to get the process running and then to request the blanked authorization. Johnson-Eschelon stated that Eschelon would be interested in giving Qwest the same authorization.

White-Qwest stated that the final action item was related to putting a Y in the SCA field. Boudhaouia-Qwest stated that the CLEC must have a Y in the SCA field to give Qwest authorization to condition the line. Berard-Covad asked what the process was if there was not a Y in the SCA field and the line needed conditioning. Soderlund-Qwest stated that the process was to follow the IMA jeopardy-back process.

Johnson-Eschelon asked if the CLECs needed to put the conditioning authorized on the LSR with which they requested the add DSL. Soderlund-Qwest stated that Johnson was correct.

White-Qwest thanked the attendees and adjourned the meeting.

March 13, 2003 There were no CLEC attendees at the meeting. White-Qwest adjourned the meeting at 2:15 PM MT.

==================================================

Ad Hoc CMP Meeting March 3, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Denny Grahm – Qwest Barry Orrel – Qwest Laurel Neher – Qwest Joy McConnel-Couch – Qwest Joan Pfeffer – Qwest Craig Suellentrop - Qwest Ray Wilson – Qwest Cindy Schwartze – Qwest Deb Smith – Qwest Bob Mohr – Qwest Eric Yohe – Qwest Cindy Buckmaster – Qwest John Berard – Covad Julie Pickar – US Link Donna Dix – US Link Erica Beamus - WorldCom Chris Robish - Contact Monica Avila – Veritech Wayne Hart – Idaho PUC Kirk Hundertmark – Twin Rivers Valley Telecom Bonnie Johnson – Eschelon

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the Ad Hoc CMP Meeting.

Buckmaster-Qwest defined line conditioning and presented CRs PC022403-2, -3, and –4. She also proposed that the input cycle for the CRs consist of three 2-hour meetings on 3/11, 3/12, and 3/13. There were no objections to the proposed input cycle.

Zulevic-Covad asked if CLECs would be required to submit an LSR with a Y in the SCA field. Buckmaster-Qwest stated that they would.

Johnson-Eschelon stated that she was glad to see these CRs. She stated that currently when a CLEC orders Qwest DSL they must order it as a feature after a line install. She asked if these CRs would change that process. Buckmaster-Qwest stated that they did not. Johnson-Eschelon asked what these CRs did to loop qual. Buckmaster-Qwest stated that CLECs would continue to use the Raw Loop Data Tool to ascertain interval information.

Berard-Covad asked if putting a Y in the SCA field would automatically generate a 15 day interval. Buckmaster-Qwest stated that it would not. Zulevic-Covad asked if CLECs put a Y in the SCA field on all LSRs would the work be accomplished to industry specifications or would the work include a removal of all encumbrances. Buckmaster-Qwest stated that Qwest would condition to the CLEC’s DSL specifications but would not condition automatically to the tech pub standard. Zulevic-Covad asked if Qwest would provide a summary of the CR dependencies. Buckmaster-Qwest stated that she would. Robish-Contact stated that bridge taps do not affect his product. He asked if they would be required to remove bridge taps. Buckmaster-Qwest stated that they would not. Hundertmark-Twin Rivers asked if any of these CRs addressed CLEC DSL on a resold circuit because he had several issues with CRs of that variety. Buckmaster-Qwest stated that that issue was not addressed by any of these CRs. Schultz-Qwest stated that Qwest could set up another ad hoc meeting to discuss Twin River’s issues or add an item to the agenda of the next CMP Monthly Meeting. Hundertmark-Twin Rivers stated that he would prefer to discuss it at a monthly meeting.

Retka-Qwest presented CRs PC022403-5, -6, -7, and –8. Johnson-Eschelon stated that it sounded like there were several processes the CLECs would use for the various product varieties. Retka-Qwest stated that the CLECs should always consult the Raw Loop Data Tool first. Buckmaster-Qwest stated that this was an issue the team could work out during the input sessions on the 11th, 12th and 13th. Zulevic-Covad asked if there was a way to determine if the same customer has two lines on an UDC. Retka-Qwest stated that the only posting would be for customers with only one line on a UDC. Dix-US Link stated that there were errors in the RLDT. Schultz-Qwest asked Dix-US Link to contact her service manager. Dix-US Link stated that she did not know who that was. Schultz-Qwest stated that she would contact the US Link service manager and ask him/her to contact Dix. Zulevic-Covad asked if line moves were included in PC022403-5. Retka-Qwest stated that they were only included in situations where there was a spare copper loop. Buckmaster-Qwest stated that the intent was to giver the CLECs the facility to provision data on. She stated that a line move would be accomplished to accommodate data. Berard-Covad asked Retka to clarify what a UDC was. Retka-Qwest stated that a UDC was a two line pair gain at a customer premise or a cross box near a customer premise. Zulevic-Covad asked if CLECs were expected to use the RLDT before they place an order. Buckmaster-Qwest stated that was Qwest’s intent. Retka-Qwest recommended that the input process for the four latter CRs be conducted during the previously proposed meetings on the 11th, 12th, and 13th. There were no objections. There were no further questions.

The meeting was adjourned.


Open Product/Process CR PC022403-7 Detail

 
Title: Perform UDC Removal for Line Shared orders at no charge to the CLEC/DLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-7 Completed
2/24/2003
Pre-Ordering, Ordering, Provisioning Line Sharing
Originator: Boudhaouia, Jamal
Originator Company Name: Qwest Corporation
Owner: Boudhaouia, Jamal
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC Community the opportunity to request UDC Removal in certain circumstances for a voice customer whose existing line does not currently qualify for ADSL service. This UDC Removalwill be provided to the CLEC/DLEC at no charge.

UDC removal will performed under the following conditions:

- The UDC is serving the target customer

- The UDC is a two line system

- Only one channel is working on the UDC System

This offering is being made for Line Sharing family of products (defined as Other below) only.

This CR may be subject to the Condition described under Change of Law provisions of the SGAT (Section 2.2).

Proposed Implementation Date: 4/15/03


Status History

02/24/03 - Ad Hoc Meeting Notification Distributed

02/24/03 - Clacrification Meeting

03/03/03 - Ad Hoc Meeting

03/11/03 - CLEC input meeting 1

03/14/03 - Initial Level 4 Notification distributed

03/19/03 - Discussed at CMP Meeting

03/14/03 - Final Level 4 Notification distributed

04/15/03 - Change Implemented

04/16/03 - Discussed at CMP Monthly Meeting

05/21/03 - Closed at CMP Monthly Meeting


Project Meetings

========================================================== CMP Meeting 05-21-03

Buckmaster-Qwest stated that the changes were implemented on 4/15 and Qwest would like to close the CRs. Zulevic-Covad stated that he would like to leave PC022403-3 open for another month. Johnson-Eschelon stated that she wanted to leave PC022403-2 open for another month. Zulevic-Covad stated that there was an issue that he had expected Buckmaster to contact him on. Buckmaster-Qwest stated that she would send Zulevic an e-mail after the meeting. ==========================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that the new process was implemented on 4/15. Zulevic-Covad asked if the change included line splitting. Buckmaster-Qwest stated that it did. Zulevic-Covad asked if Qwest would publish a process document outlining this process. Buckmaster-Qwest stated that the Assignments Process Document on the Web describes the process. She stated that she would check to see if it included a description of the conditioning process. Zulevic-Covad asked if a line move was a 5 day interval. Buckmaster-Qwest stated that it was. Zulevic-Covad asked what happened if a CLEC placed an ‘N’ in the SCA field. Buckmaster-Qwest stated that she did not know, but that she would find out. Johnson-Eschelon asked that Qwest document this in the process document. Zulevic-Covad asked if CLECs provided Qwest with conditioning standards. Boudhaouia-Qwest stated that Qwest would condition lines to the most current industry standards. Boudhaouia, Berard and Zulevic conducted a lengthy discussion about various conditioning standards. Zulevic-Covad asked if the Qwest conditioning standards for retail were the same as wholesale. Boudhaouia-Qwest stated that they were. Buckmaster-Qwest stated that the only change these CRs were implementing was a cessation of charges. Powers-Tel West asked if the conditioning interval was different for retail and wholesale. Buckmaster-Qwest stated that it was 5 days longer for retail.

===============================================

03-19-03 - CMP Meeting

Bucmaster-Qwest reviewed where the CRs were in the process. Zulevic-Covad asked if Qwest had analyzed the potential to allow CLECs to grant blanket approval. Buckmaster-Qwest stated that Qwest is still evaluating that option, but would not implement it until after the first set of changes were implemented on 4/15. Van Meter-AT&T asked that AT&T be added to the attendee list for the Ad Hoc Meeting.

================================================

CLEC Input Meetings March 11, 2003 March 12, 2003 March 13, 2003

Attendees – March 11, 2003 Sharon Van Meter – AT&T Liz Balvin – WorldCom John Berard – Covad Mike Zulevic – Covad Jennifer Arnold – US Link Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Dave Hahn – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Laurel Neher – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Deb Smith – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 12, 2003 Liz Balvin – WorldCom John Berard – Covad Donna Dix – US Link Bonnie Johnson – Eschelon Lori Mendoza – Allegiance Chris Connor - Qwest Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 13, 2003 Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Meeting Minutes March 11, 2003

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Buckmaster-Qwest to present the first three CRs (PC022403-2, -3, -4) for discussion. Buckmaster-Qwest presented CRs –2 and -4. Soderlund-Qwest described that process for requesting conditioning. She stated that process was unchanged from today. Zulevic-Covad asked if Qwest first checked for alternate facilities before it conditioned the line. Buckmaster-Qwest stated that was true. Zulevic-Covad asked what would happen if there was not a Y in the SCA field and the line had load coils on it. Buckmaster-Qwest stated that Qwest would reject the order and tell the CLEC to authorize conditioning. Zulevic-Covad asked if the CLECs could give Qwest a blanket authorization to condition, if necessary, on every order. Buckmaster-Qwest stated that she would check on that option, but believed that it was outside the scope of this CR. Zulevic-Covad stated that he was interested because Covad had orders previously delayed, unnecessarily, for this. Buckmaster-Qwest described –3. Schwartze-Qwest described the process to request conditioning. She stated that the process included noting that conditioning was authorized in the remarks field. Zulevic-Covad asked what the process was for Qwest retail requests. Buckmaster-Qwest stated that she was not aware of the process, but would find out.

Boudhaouia-Qwest briefed CRs –5 and -7. Soderlund-Qwest described the process to request line move and UDC removal. She stated that Qwest always looks to do a line move or UDC removal. If these options are not available, Qwest looks for a Y in the SCA field before it conditions a line. Zulevic-Covad asked how the intervals would work. Soderlund-Qwest stated that the line move was a 5-day interval, and that conditioning is a 15-day interval. Boudhaouia-Qwest stated that Qwest will always attempt to try a line move, then perform UDC removal, and finally to condition the line. Zulevic-Covad asked when he would get a notification that a line needed to be conditioned. Soderlund-Qwest stated that the notification would go out as soon as the assignments group knew the line needed to be conditioned. Berard-Covad asked if a CLEC should always check the RLDT before placing a request. Buckmaster-Qwest stated that the CLEC should check in the RLDT for spare copper facilities, but that Qwest would check automatically once the request came in. Berard-Covad asked if the CLECs needed to provide some proof that they had accessed the RLDT when they submitted their request. Boudhaouia-Qwest stated that they did not.

Boudhaouia-Qwest presented CR –6. Schwartze-Qwest stated that the process for UNE-P and resale would mirror the line move and UDC removal process.

Boudhaouia-Qwest presented CR –8. Berard-Covad asked if a CLEC, for planning purposes, could look up the presence of a single line UDC in the ICONN database. Boudhaouia-Qwest stated that when CLECs issue a line share request with a Y in the SCA field, Qwest will attempt to move the line first and them to remove the UDC. He stated that the lack of a Y in the SCA field would cause a FOC back requesting authorization for conditioning.

White-Qwest stated that Qwest had three “take-aways” that they would address at the next meeting. Zulevic-Covad stated that Covad appreciated Qwest initiating these CRs.

March 12, 2003 White-Qwest introduced the attendees and described the purpose of the meeting. Johnson-Eschelon stated that she had missed the previous day’s meeting and would like an overview of what was discussed.

Buckmaster-Qwest reviewed CRs –2 and –4. Johnson-Eschelon confirmed that there was no change to the existing process. Buckmaster-Qwest reviewed –3. Schwartze-Qwest reviewed the process. Johnson-Eschelon asked if the CLECs should mark for manual handling. Schwartze-Qwest stated that was not necessary. Johnson-Eschelon asked if this information would be posted to the Web site. Buckmaster-Qwest stated that this information would be included in the PCAT.

Boudhaouia-Qwest reviewed –5 and –7. Soderlund-Qwest briefed the process to request the conditioning. Johnson-Eschelon asked if there needed to be any special markings on the request. Buckmaster-Qwest stated that if the CLEC puts a Y in the SCA field in every instance, Qwest will have authorization to condition the line for each request. Johnson-Eschelon asked if this process removed the decision making responsibility from the CLEC. Boudhaouia-Qwest stated that Qwest would first try to do a line move, the UDC removal, then bridge tap/load coil removal. He summarized that it does remove the decision responsibility from the CLEC.

Boudhaouia-Qwest reviewed –6. Schwartze-Qwest stated that the only change from the line sharing was that for resale and UNE-P the remarks section must have “conditioning authorized.”

Boudhaouia-Qwest reviewed –8.

White-Qwest stated that Qwest had three action items from the last meeting. He asked Buckmaster to review the first. Buckmaster-Qwest stated that the first action item was to describe the retail process. Connor-Qwest described the retail request process. Berard-Covad asked if retail accessed the RLDT. Buckmaster-Qwest stated that retail did not use the RLDT.

White-Qwest stated that the next action item was an investigation of the possibility of CLECs granting blanket conditioning approval. Buckmaster-Qwest stated that she would like the CLECs to give Qwest an opportunity to get the process running and then to request the blanked authorization. Johnson-Eschelon stated that Eschelon would be interested in giving Qwest the same authorization.

White-Qwest stated that the final action item was related to putting a Y in the SCA field. Boudhaouia-Qwest stated that the CLEC must have a Y in the SCA field to give Qwest authorization to condition the line. Berard-Covad asked what the process was if there was not a Y in the SCA field and the line needed conditioning. Soderlund-Qwest stated that the process was to follow the IMA jeopardy-back process.

Johnson-Eschelon asked if the CLECs needed to put the conditioning authorized on the LSR with which they requested the add DSL. Soderlund-Qwest stated that Johnson was correct.

White-Qwest thanked the attendees and adjourned the meeting.

March 13, 2003 There were no CLEC attendees at the meeting. White-Qwest adjourned the meeting at 2:15 PM MT.

==================================================

Ad Hoc CMP Meeting March 3, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Denny Grahm – Qwest Barry Orrel – Qwest Laurel Neher – Qwest Joy McConnel-Couch – Qwest Joan Pfeffer – Qwest Craig Suellentrop - Qwest Ray Wilson – Qwest Cindy Schwartze – Qwest Deb Smith – Qwest Bob Mohr – Qwest Eric Yohe – Qwest Cindy Buckmaster – Qwest John Berard – Covad Julie Pickar – US Link Donna Dix – US Link Erica Beamus - WorldCom Chris Robish - Contact Monica Avila – Veritech Wayne Hart – Idaho PUC Kirk Hundertmark – Twin Rivers Valley Telecom Bonnie Johnson – Eschelon

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the Ad Hoc CMP Meeting.

Buckmaster-Qwest defined line conditioning and presented CRs PC022403-2, -3, and –4. She also proposed that the input cycle for the CRs consist of three 2-hour meetings on 3/11, 3/12, and 3/13. There were no objections to the proposed input cycle.

Zulevic-Covad asked if CLECs would be required to submit an LSR with a Y in the SCA field. Buckmaster-Qwest stated that they would.

Johnson-Eschelon stated that she was glad to see these CRs. She stated that currently when a CLEC orders Qwest DSL they must order it as a feature after a line install. She asked if these CRs would change that process. Buckmaster-Qwest stated that they did not. Johnson-Eschelon asked what these CRs did to loop qual. Buckmaster-Qwest stated that CLECs would continue to use the Raw Loop Data Tool to ascertain interval information.

Berard-Covad asked if putting a Y in the SCA field would automatically generate a 15 day interval. Buckmaster-Qwest stated that it would not. Zulevic-Covad asked if CLECs put a Y in the SCA field on all LSRs would the work be accomplished to industry specifications or would the work include a removal of all encumbrances. Buckmaster-Qwest stated that Qwest would condition to the CLEC’s DSL specifications but would not condition automatically to the tech pub standard. Zulevic-Covad asked if Qwest would provide a summary of the CR dependencies. Buckmaster-Qwest stated that she would. Robish-Contact stated that bridge taps do not affect his product. He asked if they would be required to remove bridge taps. Buckmaster-Qwest stated that they would not. Hundertmark-Twin Rivers asked if any of these CRs addressed CLEC DSL on a resold circuit because he had several issues with CRs of that variety. Buckmaster-Qwest stated that that issue was not addressed by any of these CRs. Schultz-Qwest stated that Qwest could set up another ad hoc meeting to discuss Twin River’s issues or add an item to the agenda of the next CMP Monthly Meeting. Hundertmark-Twin Rivers stated that he would prefer to discuss it at a monthly meeting.

Retka-Qwest presented CRs PC022403-5, -6, -7, and –8. Johnson-Eschelon stated that it sounded like there were several processes the CLECs would use for the various product varieties. Retka-Qwest stated that the CLECs should always consult the Raw Loop Data Tool first. Buckmaster-Qwest stated that this was an issue the team could work out during the input sessions on the 11th, 12th and 13th. Zulevic-Covad asked if there was a way to determine if the same customer has two lines on an UDC. Retka-Qwest stated that the only posting would be for customers with only one line on a UDC. Dix-US Link stated that there were errors in the RLDT. Schultz-Qwest asked Dix-US Link to contact her service manager. Dix-US Link stated that she did not know who that was. Schultz-Qwest stated that she would contact the US Link service manager and ask him/her to contact Dix. Zulevic-Covad asked if line moves were included in PC022403-5. Retka-Qwest stated that they were only included in situations where there was a spare copper loop. Buckmaster-Qwest stated that the intent was to giver the CLECs the facility to provision data on. She stated that a line move would be accomplished to accommodate data. Berard-Covad asked Retka to clarify what a UDC was. Retka-Qwest stated that a UDC was a two line pair gain at a customer premise or a cross box near a customer premise. Zulevic-Covad asked if CLECs were expected to use the RLDT before they place an order. Buckmaster-Qwest stated that was Qwest’s intent. Retka-Qwest recommended that the input process for the four latter CRs be conducted during the previously proposed meetings on the 11th, 12th, and 13th. There were no objections. There were no further questions.

The meeting was adjourned.


Open Product/Process CR PC022403-8 Detail

 
Title: Perform UDC Removal for ADSL Capable Unbundled Loop orders at no charge to the CLEC/DLEC.
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-8 Completed
2/24/2003
Pre-Ordering, Ordering, Provisioning, Billing Unbundled Loop (ADSL Capable)
Originator: Boudhaouia, Jamal
Originator Company Name: Qwest Corporation
Owner: Boudhaouia, Jamal
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC Community the opportunity to request UDC Removal in certain circumstances for a voice customer whose existing line does not currently qualify for ADSL service. This UDC Removal will be provided to the CLEC/DLEC at no charge.

UDC removal will performed under the following conditions:

- The UDC is serving the target customer

- The UDC is a two line system

- Only one channel is working on the UDC System

This offering is being made for ADSL Capable unbundled Loops only.

This CR may be subject to the Condition described under Change of Law provisions of the SGAT (Section 2.2).

Proposed Implementation Date: 4/15/03


Status History

02/24/03 - Ad Hoc Meeting Notification Distributed

02/24/03 - Clacrification Meeting

03/03/03 - Ad Hoc Meeting

03/11/03 - CLEC input meeting 1

03/14/03 - Initial Level 4 Notification distributed

03/19/03 - Discussed at CMP Meeting

03/14/03 - Final Level 4 Notification distributed

04/15/03 - Change Implemented

04/16/03 - Discussed at CMP Monthly Meeting

05/21/03 - Closed at CMP Monthly Meeting


Project Meetings

========================================================== CMP Meeting 05-21-03

Buckmaster-Qwest stated that the changes were implemented on 4/15 and Qwest would like to close the CRs. Zulevic-Covad stated that he would like to leave PC022403-3 open for another month. Johnson-Eschelon stated that she wanted to leave PC022403-2 open for another month. Zulevic-Covad stated that there was an issue that he had expected Buckmaster to contact him on. Buckmaster-Qwest stated that she would send Zulevic an e-mail after the meeting. ==========================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that the new process was implemented on 4/15. Zulevic-Covad asked if the change included line splitting. Buckmaster-Qwest stated that it did. Zulevic-Covad asked if Qwest would publish a process document outlining this process. Buckmaster-Qwest stated that the Assignments Process Document on the Web describes the process. She stated that she would check to see if it included a description of the conditioning process. Zulevic-Covad asked if a line move was a 5 day interval. Buckmaster-Qwest stated that it was. Zulevic-Covad asked what happened if a CLEC placed an ‘N’ in the SCA field. Buckmaster-Qwest stated that she did not know, but that she would find out. Johnson-Eschelon asked that Qwest document this in the process document. Zulevic-Covad asked if CLECs provided Qwest with conditioning standards. Boudhaouia-Qwest stated that Qwest would condition lines to the most current industry standards. Boudhaouia, Berard and Zulevic conducted a lengthy discussion about various conditioning standards. Zulevic-Covad asked if the Qwest conditioning standards for retail were the same as wholesale. Boudhaouia-Qwest stated that they were. Buckmaster-Qwest stated that the only change these CRs were implementing was a cessation of charges. Powers-Tel West asked if the conditioning interval was different for retail and wholesale. Buckmaster-Qwest stated that it was 5 days longer for retail.

===============================================

03-19-03 - CMP Meeting

Bucmaster-Qwest reviewed where the CRs were in the process. Zulevic-Covad asked if Qwest had analyzed the potential to allow CLECs to grant blanket approval. Buckmaster-Qwest stated that Qwest is still evaluating that option, but would not implement it until after the first set of changes were implemented on 4/15. Van Meter-AT&T asked that AT&T be added to the attendee list for the Ad Hoc Meeting.

================================================

CLEC Input Meetings March 11, 2003 March 12, 2003 March 13, 2003

Attendees – March 11, 2003 Sharon Van Meter – AT&T Liz Balvin – WorldCom John Berard – Covad Mike Zulevic – Covad Jennifer Arnold – US Link Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Dave Hahn – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Laurel Neher – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Deb Smith – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 12, 2003 Liz Balvin – WorldCom John Berard – Covad Donna Dix – US Link Bonnie Johnson – Eschelon Lori Mendoza – Allegiance Chris Connor - Qwest Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 13, 2003 Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Meeting Minutes March 11, 2003

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Buckmaster-Qwest to present the first three CRs (PC022403-2, -3, -4) for discussion. Buckmaster-Qwest presented CRs –2 and -4. Soderlund-Qwest described that process for requesting conditioning. She stated that process was unchanged from today. Zulevic-Covad asked if Qwest first checked for alternate facilities before it conditioned the line. Buckmaster-Qwest stated that was true. Zulevic-Covad asked what would happen if there was not a Y in the SCA field and the line had load coils on it. Buckmaster-Qwest stated that Qwest would reject the order and tell the CLEC to authorize conditioning. Zulevic-Covad asked if the CLECs could give Qwest a blanket authorization to condition, if necessary, on every order. Buckmaster-Qwest stated that she would check on that option, but believed that it was outside the scope of this CR. Zulevic-Covad stated that he was interested because Covad had orders previously delayed, unnecessarily, for this. Buckmaster-Qwest described –3. Schwartze-Qwest described the process to request conditioning. She stated that the process included noting that conditioning was authorized in the remarks field. Zulevic-Covad asked what the process was for Qwest retail requests. Buckmaster-Qwest stated that she was not aware of the process, but would find out.

Boudhaouia-Qwest briefed CRs –5 and -7. Soderlund-Qwest described the process to request line move and UDC removal. She stated that Qwest always looks to do a line move or UDC removal. If these options are not available, Qwest looks for a Y in the SCA field before it conditions a line. Zulevic-Covad asked how the intervals would work. Soderlund-Qwest stated that the line move was a 5-day interval, and that conditioning is a 15-day interval. Boudhaouia-Qwest stated that Qwest will always attempt to try a line move, then perform UDC removal, and finally to condition the line. Zulevic-Covad asked when he would get a notification that a line needed to be conditioned. Soderlund-Qwest stated that the notification would go out as soon as the assignments group knew the line needed to be conditioned. Berard-Covad asked if a CLEC should always check the RLDT before placing a request. Buckmaster-Qwest stated that the CLEC should check in the RLDT for spare copper facilities, but that Qwest would check automatically once the request came in. Berard-Covad asked if the CLECs needed to provide some proof that they had accessed the RLDT when they submitted their request. Boudhaouia-Qwest stated that they did not.

Boudhaouia-Qwest presented CR –6. Schwartze-Qwest stated that the process for UNE-P and resale would mirror the line move and UDC removal process.

Boudhaouia-Qwest presented CR –8. Berard-Covad asked if a CLEC, for planning purposes, could look up the presence of a single line UDC in the ICONN database. Boudhaouia-Qwest stated that when CLECs issue a line share request with a Y in the SCA field, Qwest will attempt to move the line first and them to remove the UDC. He stated that the lack of a Y in the SCA field would cause a FOC back requesting authorization for conditioning.

White-Qwest stated that Qwest had three “take-aways” that they would address at the next meeting. Zulevic-Covad stated that Covad appreciated Qwest initiating these CRs.

March 12, 2003 White-Qwest introduced the attendees and described the purpose of the meeting. Johnson-Eschelon stated that she had missed the previous day’s meeting and would like an overview of what was discussed.

Buckmaster-Qwest reviewed CRs –2 and –4. Johnson-Eschelon confirmed that there was no change to the existing process. Buckmaster-Qwest reviewed –3. Schwartze-Qwest reviewed the process. Johnson-Eschelon asked if the CLECs should mark for manual handling. Schwartze-Qwest stated that was not necessary. Johnson-Eschelon asked if this information would be posted to the Web site. Buckmaster-Qwest stated that this information would be included in the PCAT.

Boudhaouia-Qwest reviewed –5 and –7. Soderlund-Qwest briefed the process to request the conditioning. Johnson-Eschelon asked if there needed to be any special markings on the request. Buckmaster-Qwest stated that if the CLEC puts a Y in the SCA field in every instance, Qwest will have authorization to condition the line for each request. Johnson-Eschelon asked if this process removed the decision making responsibility from the CLEC. Boudhaouia-Qwest stated that Qwest would first try to do a line move, the UDC removal, then bridge tap/load coil removal. He summarized that it does remove the decision responsibility from the CLEC.

Boudhaouia-Qwest reviewed –6. Schwartze-Qwest stated that the only change from the line sharing was that for resale and UNE-P the remarks section must have “conditioning authorized.”

Boudhaouia-Qwest reviewed –8.

White-Qwest stated that Qwest had three action items from the last meeting. He asked Buckmaster to review the first. Buckmaster-Qwest stated that the first action item was to describe the retail process. Connor-Qwest described the retail request process. Berard-Covad asked if retail accessed the RLDT. Buckmaster-Qwest stated that retail did not use the RLDT.

White-Qwest stated that the next action item was an investigation of the possibility of CLECs granting blanket conditioning approval. Buckmaster-Qwest stated that she would like the CLECs to give Qwest an opportunity to get the process running and then to request the blanked authorization. Johnson-Eschelon stated that Eschelon would be interested in giving Qwest the same authorization.

White-Qwest stated that the final action item was related to putting a Y in the SCA field. Boudhaouia-Qwest stated that the CLEC must have a Y in the SCA field to give Qwest authorization to condition the line. Berard-Covad asked what the process was if there was not a Y in the SCA field and the line needed conditioning. Soderlund-Qwest stated that the process was to follow the IMA jeopardy-back process.

Johnson-Eschelon asked if the CLECs needed to put the conditioning authorized on the LSR with which they requested the add DSL. Soderlund-Qwest stated that Johnson was correct.

White-Qwest thanked the attendees and adjourned the meeting.

March 13, 2003 There were no CLEC attendees at the meeting. White-Qwest adjourned the meeting at 2:15 PM MT.

==================================================

Ad Hoc CMP Meeting March 3, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Denny Grahm – Qwest Barry Orrel – Qwest Laurel Neher – Qwest Joy McConnel-Couch – Qwest Joan Pfeffer – Qwest Craig Suellentrop - Qwest Ray Wilson – Qwest Cindy Schwartze – Qwest Deb Smith – Qwest Bob Mohr – Qwest Eric Yohe – Qwest Cindy Buckmaster – Qwest John Berard – Covad Julie Pickar – US Link Donna Dix – US Link Erica Beamus - WorldCom Chris Robish - Contact Monica Avila – Veritech Wayne Hart – Idaho PUC Kirk Hundertmark – Twin Rivers Valley Telecom Bonnie Johnson – Eschelon

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the Ad Hoc CMP Meeting.

Buckmaster-Qwest defined line conditioning and presented CRs PC022403-2, -3, and –4. She also proposed that the input cycle for the CRs consist of three 2-hour meetings on 3/11, 3/12, and 3/13. There were no objections to the proposed input cycle.

Zulevic-Covad asked if CLECs would be required to submit an LSR with a Y in the SCA field. Buckmaster-Qwest stated that they would.

Johnson-Eschelon stated that she was glad to see these CRs. She stated that currently when a CLEC orders Qwest DSL they must order it as a feature after a line install. She asked if these CRs would change that process. Buckmaster-Qwest stated that they did not. Johnson-Eschelon asked what these CRs did to loop qual. Buckmaster-Qwest stated that CLECs would continue to use the Raw Loop Data Tool to ascertain interval information.

Berard-Covad asked if putting a Y in the SCA field would automatically generate a 15 day interval. Buckmaster-Qwest stated that it would not. Zulevic-Covad asked if CLECs put a Y in the SCA field on all LSRs would the work be accomplished to industry specifications or would the work include a removal of all encumbrances. Buckmaster-Qwest stated that Qwest would condition to the CLEC’s DSL specifications but would not condition automatically to the tech pub standard. Zulevic-Covad asked if Qwest would provide a summary of the CR dependencies. Buckmaster-Qwest stated that she would. Robish-Contact stated that bridge taps do not affect his product. He asked if they would be required to remove bridge taps. Buckmaster-Qwest stated that they would not. Hundertmark-Twin Rivers asked if any of these CRs addressed CLEC DSL on a resold circuit because he had several issues with CRs of that variety. Buckmaster-Qwest stated that that issue was not addressed by any of these CRs. Schultz-Qwest stated that Qwest could set up another ad hoc meeting to discuss Twin River’s issues or add an item to the agenda of the next CMP Monthly Meeting. Hundertmark-Twin Rivers stated that he would prefer to discuss it at a monthly meeting.

Retka-Qwest presented CRs PC022403-5, -6, -7, and –8. Johnson-Eschelon stated that it sounded like there were several processes the CLECs would use for the various product varieties. Retka-Qwest stated that the CLECs should always consult the Raw Loop Data Tool first. Buckmaster-Qwest stated that this was an issue the team could work out during the input sessions on the 11th, 12th and 13th. Zulevic-Covad asked if there was a way to determine if the same customer has two lines on an UDC. Retka-Qwest stated that the only posting would be for customers with only one line on a UDC. Dix-US Link stated that there were errors in the RLDT. Schultz-Qwest asked Dix-US Link to contact her service manager. Dix-US Link stated that she did not know who that was. Schultz-Qwest stated that she would contact the US Link service manager and ask him/her to contact Dix. Zulevic-Covad asked if line moves were included in PC022403-5. Retka-Qwest stated that they were only included in situations where there was a spare copper loop. Buckmaster-Qwest stated that the intent was to giver the CLECs the facility to provision data on. She stated that a line move would be accomplished to accommodate data. Berard-Covad asked Retka to clarify what a UDC was. Retka-Qwest stated that a UDC was a two line pair gain at a customer premise or a cross box near a customer premise. Zulevic-Covad asked if CLECs were expected to use the RLDT before they place an order. Buckmaster-Qwest stated that was Qwest’s intent. Retka-Qwest recommended that the input process for the four latter CRs be conducted during the previously proposed meetings on the 11th, 12th, and 13th. There were no objections. There were no further questions.

The meeting was adjourned.


Open Product/Process CR PC022403-4 Detail

 
Title: Conditioning for DSL Services in UBL Product at no charge to the CLEC/DLEC
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-4 Completed
2/24/2003
Pre-Ordering, Ordering, Provisioning, Billing Unbundled Loop, Loop
Originator: Buckmaster, Cindy
Originator Company Name: Qwest Corporation
Owner: Buckmaster, Cindy
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC/Reseller Community the opportunity to request Conditioning (Load Coil and Excessive Bridged Tap Removal) from any UBL copper facility for which the CLEC has ordered Data capability and has requested Conditioning according to the LSOG / ASOG requirements. This Conditioning will be provided to the CLEC/DLEC/Reseller at no charge. All Conditioning parameters will be defined by Qwest in applicable external documentation. Once CLEC/DLEC/Reseller Conditioning has been requested and performed, if the end-user’s Voice Grade service is degraded beyond Voice capability, the necessary Load Coils will be restored and the CLEC who requested the Conditioning will be billed for this restoral.

This offering is being made for the Non-Loaded, ADSL Compatible, ISDN and x-DSL-I Capable Unbundled Loop (defined as UBL or Loop below).

The effective date of this CR will be determined following the discussion a CMP adhoc meeting. Prior to an effective date, current processes remain in effect.

Proposed Implementation Date: 4/15/03


Status History

02/24/03 - Ad Hoc Meeting Notification Distributed

02/24/03 - Clacrification Meeting

03/03/03 - Ad Hoc Meeting

03/11/03 - CLEC input meeting 1

03/14/03 - Initial Level 4 Notification distributed

03/19/03 - Discussed at CMP Meeting

03/14/03 - Final Level 4 Notification distributed

04/15/03 - Change Implemented

04/16/03 - Discussed at CMP Monthly Meeting

05/21/03 - Closed at CMP Monthly Meeting


Project Meetings

========================================================== CMP Meeting 05-21-03

Buckmaster-Qwest stated that the changes were implemented on 4/15 and Qwest would like to close the CRs. Zulevic-Covad stated that he would like to leave PC022403-3 open for another month. Johnson-Eschelon stated that she wanted to leave PC022403-2 open for another month. Zulevic-Covad stated that there was an issue that he had expected Buckmaster to contact him on. Buckmaster-Qwest stated that she would send Zulevic an e-mail after the meeting. ==========================================

04-16-03 - CMP Meeting

Buckmaster-Qwest stated that the new process was implemented on 4/15. Zulevic-Covad asked if the change included line splitting. Buckmaster-Qwest stated that it did. Zulevic-Covad asked if Qwest would publish a process document outlining this process. Buckmaster-Qwest stated that the Assignments Process Document on the Web describes the process. She stated that she would check to see if it included a description of the conditioning process. Zulevic-Covad asked if a line move was a 5 day interval. Buckmaster-Qwest stated that it was. Zulevic-Covad asked what happened if a CLEC placed an ‘N’ in the SCA field. Buckmaster-Qwest stated that she did not know, but that she would find out. Johnson-Eschelon asked that Qwest document this in the process document. Zulevic-Covad asked if CLECs provided Qwest with conditioning standards. Boudhaouia-Qwest stated that Qwest would condition lines to the most current industry standards. Boudhaouia, Berard and Zulevic conducted a lengthy discussion about various conditioning standards. Zulevic-Covad asked if the Qwest conditioning standards for retail were the same as wholesale. Boudhaouia-Qwest stated that they were. Buckmaster-Qwest stated that the only change these CRs were implementing was a cessation of charges. Powers-Tel West asked if the conditioning interval was different for retail and wholesale. Buckmaster-Qwest stated that it was 5 days longer for retail.

===============================================

03-19-03 - CMP Meeting

Bucmaster-Qwest reviewed where the CRs were in the process. Zulevic-Covad asked if Qwest had analyzed the potential to allow CLECs to grant blanket approval. Buckmaster-Qwest stated that Qwest is still evaluating that option, but would not implement it until after the first set of changes were implemented on 4/15. Van Meter-AT&T asked that AT&T be added to the attendee list for the Ad Hoc Meeting.

================================================

CLEC Input Meetings March 11, 2003 March 12, 2003 March 13, 2003

Attendees – March 11, 2003 Sharon Van Meter – AT&T Liz Balvin – WorldCom John Berard – Covad Mike Zulevic – Covad Jennifer Arnold – US Link Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Dave Hahn – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Laurel Neher – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Deb Smith – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 12, 2003 Liz Balvin – WorldCom John Berard – Covad Donna Dix – US Link Bonnie Johnson – Eschelon Lori Mendoza – Allegiance Chris Connor - Qwest Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Kit Thomte – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Attendees – March 13, 2003 Jamal Boudhaouia – Qwest Cindy Schwartze – Qwest Crystal Soderlund – Qwest Linda Miles – Qwest Eric Yohe – Qwest Barry Orrel – Qwest Cindy Buckmaster – Qwest Denny Graham – Qwest Joy McConnel-Couch – Qwest Bob Mohr – Qwest Ray Wilson – Qwest Matt White - Qwest Heidi Moreland – Qwest

Meeting Minutes March 11, 2003

White-Qwest introduced the attendees and described the purpose of the meeting. He asked Buckmaster-Qwest to present the first three CRs (PC022403-2, -3, -4) for discussion. Buckmaster-Qwest presented CRs –2 and -4. Soderlund-Qwest described that process for requesting conditioning. She stated that process was unchanged from today. Zulevic-Covad asked if Qwest first checked for alternate facilities before it conditioned the line. Buckmaster-Qwest stated that was true. Zulevic-Covad asked what would happen if there was not a Y in the SCA field and the line had load coils on it. Buckmaster-Qwest stated that Qwest would reject the order and tell the CLEC to authorize conditioning. Zulevic-Covad asked if the CLECs could give Qwest a blanket authorization to condition, if necessary, on every order. Buckmaster-Qwest stated that she would check on that option, but believed that it was outside the scope of this CR. Zulevic-Covad stated that he was interested because Covad had orders previously delayed, unnecessarily, for this. Buckmaster-Qwest described –3. Schwartze-Qwest described the process to request conditioning. She stated that the process included noting that conditioning was authorized in the remarks field. Zulevic-Covad asked what the process was for Qwest retail requests. Buckmaster-Qwest stated that she was not aware of the process, but would find out.

Boudhaouia-Qwest briefed CRs –5 and -7. Soderlund-Qwest described the process to request line move and UDC removal. She stated that Qwest always looks to do a line move or UDC removal. If these options are not available, Qwest looks for a Y in the SCA field before it conditions a line. Zulevic-Covad asked how the intervals would work. Soderlund-Qwest stated that the line move was a 5-day interval, and that conditioning is a 15-day interval. Boudhaouia-Qwest stated that Qwest will always attempt to try a line move, then perform UDC removal, and finally to condition the line. Zulevic-Covad asked when he would get a notification that a line needed to be conditioned. Soderlund-Qwest stated that the notification would go out as soon as the assignments group knew the line needed to be conditioned. Berard-Covad asked if a CLEC should always check the RLDT before placing a request. Buckmaster-Qwest stated that the CLEC should check in the RLDT for spare copper facilities, but that Qwest would check automatically once the request came in. Berard-Covad asked if the CLECs needed to provide some proof that they had accessed the RLDT when they submitted their request. Boudhaouia-Qwest stated that they did not.

Boudhaouia-Qwest presented CR –6. Schwartze-Qwest stated that the process for UNE-P and resale would mirror the line move and UDC removal process.

Boudhaouia-Qwest presented CR –8. Berard-Covad asked if a CLEC, for planning purposes, could look up the presence of a single line UDC in the ICONN database. Boudhaouia-Qwest stated that when CLECs issue a line share request with a Y in the SCA field, Qwest will attempt to move the line first and them to remove the UDC. He stated that the lack of a Y in the SCA field would cause a FOC back requesting authorization for conditioning.

White-Qwest stated that Qwest had three “take-aways” that they would address at the next meeting. Zulevic-Covad stated that Covad appreciated Qwest initiating these CRs.

March 12, 2003 White-Qwest introduced the attendees and described the purpose of the meeting. Johnson-Eschelon stated that she had missed the previous day’s meeting and would like an overview of what was discussed.

Buckmaster-Qwest reviewed CRs –2 and –4. Johnson-Eschelon confirmed that there was no change to the existing process. Buckmaster-Qwest reviewed –3. Schwartze-Qwest reviewed the process. Johnson-Eschelon asked if the CLECs should mark for manual handling. Schwartze-Qwest stated that was not necessary. Johnson-Eschelon asked if this information would be posted to the Web site. Buckmaster-Qwest stated that this information would be included in the PCAT.

Boudhaouia-Qwest reviewed –5 and –7. Soderlund-Qwest briefed the process to request the conditioning. Johnson-Eschelon asked if there needed to be any special markings on the request. Buckmaster-Qwest stated that if the CLEC puts a Y in the SCA field in every instance, Qwest will have authorization to condition the line for each request. Johnson-Eschelon asked if this process removed the decision making responsibility from the CLEC. Boudhaouia-Qwest stated that Qwest would first try to do a line move, the UDC removal, then bridge tap/load coil removal. He summarized that it does remove the decision responsibility from the CLEC.

Boudhaouia-Qwest reviewed –6. Schwartze-Qwest stated that the only change from the line sharing was that for resale and UNE-P the remarks section must have “conditioning authorized.”

Boudhaouia-Qwest reviewed –8.

White-Qwest stated that Qwest had three action items from the last meeting. He asked Buckmaster to review the first. Buckmaster-Qwest stated that the first action item was to describe the retail process. Connor-Qwest described the retail request process. Berard-Covad asked if retail accessed the RLDT. Buckmaster-Qwest stated that retail did not use the RLDT.

White-Qwest stated that the next action item was an investigation of the possibility of CLECs granting blanket conditioning approval. Buckmaster-Qwest stated that she would like the CLECs to give Qwest an opportunity to get the process running and then to request the blanked authorization. Johnson-Eschelon stated that Eschelon would be interested in giving Qwest the same authorization.

White-Qwest stated that the final action item was related to putting a Y in the SCA field. Boudhaouia-Qwest stated that the CLEC must have a Y in the SCA field to give Qwest authorization to condition the line. Berard-Covad asked what the process was if there was not a Y in the SCA field and the line needed conditioning. Soderlund-Qwest stated that the process was to follow the IMA jeopardy-back process.

Johnson-Eschelon asked if the CLECs needed to put the conditioning authorized on the LSR with which they requested the add DSL. Soderlund-Qwest stated that Johnson was correct.

White-Qwest thanked the attendees and adjourned the meeting.

March 13, 2003 There were no CLEC attendees at the meeting. White-Qwest adjourned the meeting at 2:15 PM MT.

==================================================

Ad Hoc CMP Meeting March 3, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Denny Grahm – Qwest Barry Orrel – Qwest Laurel Neher – Qwest Joy McConnel-Couch – Qwest Joan Pfeffer – Qwest Craig Suellentrop - Qwest Ray Wilson – Qwest Cindy Schwartze – Qwest Deb Smith – Qwest Bob Mohr – Qwest Eric Yohe – Qwest Cindy Buckmaster – Qwest John Berard – Covad Julie Pickar – US Link Donna Dix – US Link Erica Beamus - WorldCom Chris Robish - Contact Monica Avila – Veritech Wayne Hart – Idaho PUC Kirk Hundertmark – Twin Rivers Valley Telecom Bonnie Johnson – Eschelon

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the Ad Hoc CMP Meeting.

Buckmaster-Qwest defined line conditioning and presented CRs PC022403-2, -3, and –4. She also proposed that the input cycle for the CRs consist of three 2-hour meetings on 3/11, 3/12, and 3/13. There were no objections to the proposed input cycle.

Zulevic-Covad asked if CLECs would be required to submit an LSR with a Y in the SCA field. Buckmaster-Qwest stated that they would.

Johnson-Eschelon stated that she was glad to see these CRs. She stated that currently when a CLEC orders Qwest DSL they must order it as a feature after a line install. She asked if these CRs would change that process. Buckmaster-Qwest stated that they did not. Johnson-Eschelon asked what these CRs did to loop qual. Buckmaster-Qwest stated that CLECs would continue to use the Raw Loop Data Tool to ascertain interval information.

Berard-Covad asked if putting a Y in the SCA field would automatically generate a 15 day interval. Buckmaster-Qwest stated that it would not. Zulevic-Covad asked if CLECs put a Y in the SCA field on all LSRs would the work be accomplished to industry specifications or would the work include a removal of all encumbrances. Buckmaster-Qwest stated that Qwest would condition to the CLEC’s DSL specifications but would not condition automatically to the tech pub standard. Zulevic-Covad asked if Qwest would provide a summary of the CR dependencies. Buckmaster-Qwest stated that she would. Robish-Contact stated that bridge taps do not affect his product. He asked if they would be required to remove bridge taps. Buckmaster-Qwest stated that they would not. Hundertmark-Twin Rivers asked if any of these CRs addressed CLEC DSL on a resold circuit because he had several issues with CRs of that variety. Buckmaster-Qwest stated that that issue was not addressed by any of these CRs. Schultz-Qwest stated that Qwest could set up another ad hoc meeting to discuss Twin River’s issues or add an item to the agenda of the next CMP Monthly Meeting. Hundertmark-Twin Rivers stated that he would prefer to discuss it at a monthly meeting.

Retka-Qwest presented CRs PC022403-5, -6, -7, and –8. Johnson-Eschelon stated that it sounded like there were several processes the CLECs would use for the various product varieties. Retka-Qwest stated that the CLECs should always consult the Raw Loop Data Tool first. Buckmaster-Qwest stated that this was an issue the team could work out during the input sessions on the 11th, 12th and 13th. Zulevic-Covad asked if there was a way to determine if the same customer has two lines on an UDC. Retka-Qwest stated that the only posting would be for customers with only one line on a UDC. Dix-US Link stated that there were errors in the RLDT. Schultz-Qwest asked Dix-US Link to contact her service manager. Dix-US Link stated that she did not know who that was. Schultz-Qwest stated that she would contact the US Link service manager and ask him/her to contact Dix. Zulevic-Covad asked if line moves were included in PC022403-5. Retka-Qwest stated that they were only included in situations where there was a spare copper loop. Buckmaster-Qwest stated that the intent was to giver the CLECs the facility to provision data on. She stated that a line move would be accomplished to accommodate data. Berard-Covad asked Retka to clarify what a UDC was. Retka-Qwest stated that a UDC was a two line pair gain at a customer premise or a cross box near a customer premise. Zulevic-Covad asked if CLECs were expected to use the RLDT before they place an order. Buckmaster-Qwest stated that was Qwest’s intent. Retka-Qwest recommended that the input process for the four latter CRs be conducted during the previously proposed meetings on the 11th, 12th, and 13th. There were no objections. There were no further questions.

The meeting was adjourned.


Open Product/Process CR PC022403-1EX Detail

 
Title: “Microsoft Network (MSN) Internet Access Powered by Qwest” narrowband (dial up) billing arrangements unavailable with UNE P, Resale, and UBS services
CR Number Current Status
Date
Area Impacted Products Impacted

PC022403-1EX Completed
2/24/2003
Provisioning, Billing Resale, UNE Switching, UNE-P
Originator: Whitt, Michael
Originator Company Name: Qwest Corporation
Owner: Whitt, Michael
Director:
CR PM: White, Matt

Description Of Change

This CR requests that Qwest implement the following change with a Level 1 Product/Process Notification instead of a Level 3 Product/Process Notification. The proposed documentation changes are associated with language to be added to UNE-P General, Resale General, and UBS PCATs regarding the following process change: “Microsoft Network (MSN) Internet Access Powered by Qwest.” As part of this change, Qwest will remove narrowband (dial-up) billing arrangements from Retail accounts converting to UNE-P, Resale, or UBS.

Qwest is requesting this exception to the Level 3 timeline to allow earlier implementation of a process which will enable retail accounts with “MSN Internet Access Powered by Qwest” narrowband billing arrangements to convert to UNE-P/Resale/UBS without requiring prior USOC/FID removal. This change will discontinue conversion LSR rejects based solely on the presence of the “MSN Internet Access Powered by Qwest” narrowband billing arrangement USOCs/FID.

Qwest requests that this change be implemented with a Level 1 Notification.


Status History

02-25-03 - Pre-Meeting Notification Distributed

02-27-03 - Pre-Meeting conducted

02-28-03 - Exception Notification distributed

03-06-03 - Exception Meeting conducted (No vote - quorum not established)

03-07-03 - Second Exception Meeting Notification distributed

03-11-03 - Second Exception Meeting conducted

03-12-03 - Level 1 Notification distributed


Project Meetings

Exception Meeting March 11, 2003 Meeting Start Time: 3:30 p.m.

Attendees

Michael Whitt – Qwest Janean Van Dusen - Qwest Matt White – Qwest Anthony Washington – Qwest Susan Lorence – Qwest Laurel Neher – Qwest Mike Zulevic – Covad Matt Myers – TelWest Communications Donna Osborne-Miller – AT&T Carla Pardee – AT&T

Meeting Minutes

White-Qwest described the Exception Process and the voting standard. He stated that because quorum was not met at the original Exception Meeting, quorum was not required at this meeting.

White-Qwest asked if there were any questions before he administered the vote.

White-Qwest asked the carriers present to cast their ballots aloud or by e-mail. He stated that there had been three e-mail votes prior to the meeting. He stated that these votes were Eschelon-Yes, US Link-Yes, and Qwest-Yes. The remainder of the votes are reflected on the voting tally. He stated that the exception was passed by a unanimous decision.

The meeting was adjourned.

===========================================================

Exception Meeting March 6, 2003

Attendees

Michael Whitt – Qwest Janean Van Dusen - Qwest Laurel Neher – Qwest Matt White - Qwest Bonnie Johnson – Eschelon Jennifer Arnold – US Link Doug Lacy (douglas.lacy@wcom.com) – WorldCom

Meeting Minutes

White-Qwest described the Exception Process and the voting standard. He stated that the required number of carriers to establish quorum at this meeting was six. He stated that there were not a sufficient number of carriers at this meeting to establish quorum. He stated that, in such circumstances, the CMP Document called for Qwest to hold a second Exception Meeting at which quorum was not required. He proposed that this meeting be help at 3:30 p.m. MT on Tuesday, March 11, 2003. There were no objections. White-Qwest stated that he would prepare and distribute a notification announcing the second Exception Meeting. The meeting was adjourned.

==========================================================

Exception Pre-Meeting February 27, 2003

Attendees: Matt White – Qwest Janean Van Dusen – Qwest Michael Whitt – Qwest Susan Lorence – Qwest Kim Isaacs – Eschelon Bonnie Johnson – Eschelon Kathy Murray – Eschelon Jen Arnold – US Link

White-Qwest began the meeting by welcoming all attendees and explaining the purpose of the pre-meeting.

Whitt-Qwest presented the exception CR and asked the attendees for questions. Jonhson-Eschelon asked if an account with only the DVDP FID will be rejected. Whitt-Qwest stated that currently it would. Johnson-Eschelon asked how Qwest could reject any orders. Whitt-Qwest stated that this call was not an appropriate forum to discuss that issue. He stated that this change was made to avoid as many rejects as possible. There were no further questions.

White-Qwest stated that the remainder of the meeting would be dedicated to determining the logistics for the vote, what ‘Yes’ and ‘No’ votes would mean, and what course of action the parties would follow if the request was granted.

White-Qwest proposed 1 PM MT on 3/6 for the vote. Johnson-Eschelon stated that 3 PM MT worked better for her. White-Qwest asked if there were any other conflicts. There were none. The meeting was set for 3 PM MT, 3/6.

White-Qwest proposed the following language for the meanings of ‘Yes’ and ‘No:’

A vote of ‘Yes’ will indicate a preference to allow Qwest to implement the change described in PC022403-1EX with a Level 1 Notification.

A vote of ‘No’ will indicate a preference that Qwest NOT implement the change described in PC022403-1EX with a Level 1 Notification.

There were no concerns or questions.

White-Qwest proposed the following language for the course of action the parties would follow if the request were granted:

If Exception Request PC022403-1EX is granted, Qwest will implement a process which will enable retail accounts with “MSN Internet Access Powered by Qwest” narrowband billing arrangements to convert to UNE-P/Resale/UBS without requiring prior USOC/FID removal with a Level 1 Notification. This change will discontinue conversion LSR rejects based solely on the presence of the “MSN Internet Access Powered by Qwest” narrowband billing arrangement USOCs/FID.

Johnson-Eschelon asked why there was a product limitation. Whitt-Qwest stated that he could not answer that question, but could research it and respond through White-Qwest. Arnold-Qwest stated that she was also interested in seeing the response to Johnson’s question. (On 3/3/03, White-Qwest sent Whitt’s response to Johnson-Eschelon and Arnold-USLink by e-mail.) White-Qwest asked if there were any concerns with the course of action language. There were none.

White-Qwest thanked the attendees and adjourned the meeting.


Open Product/Process CR PC031203-1 Detail

 
Title: CLEC access to MLT information in WFA
CR Number Current Status
Date
Area Impacted Products Impacted

PC031203-1 Completed
4/21/2009
PreOrdering Unbundled Loop
Originator: Suellentrop, Craig
Originator Company Name: Qwest Corporation
Owner: Suellentrop, Craig
Director:
CR PM: White, Matt

Description Of Change

Currently, Qwest performs a Mechanized Loop Test (MLT) when converting a voice grade service served by a Qwest switch to an unbundled loop (LX--, re-use only) and places the results of the MLT into the WFA notes screen. Qwest is proposing a manual process whereby it would provide the MLT results that were placed in the WFA notes screen, upon request by any CLEC, when available.

Expected Deliverable:

May 15, 2003


Status History

03/12/03 - Received CR from Qwest

03/12/03 - Received updated/revised CR from Qwest

03/13/03 - Acknowledged CR by CMP P/P Manager

03/27/03 - Distributed Input Cycle Notification - CMPR.03.27.03.F.01451.MtgToSolicitCLECInput

04/08/03 - Input Meeting held

04/16/03 - Discussed at CMP Meeting

04/21/03 - Input Meeting held

04/22/03 - Input Meeting held

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting


Project Meetings

CMP Meeting 08-20-03

Suellentrop-Qwest stated that the CR had been implemented in June and recommended a close. The group agreed and the CR was Closed.

===========================================

CMP Meeting 07-16-03

Suellentrop-Qwest stated that the change had been implemented on 6/30 and asked that the CR be moved to CLEC Test status. There were no objections.

================================================ CMP Meeting 06-18-03

Suellentrop-Qwest stated that implementation was scheduled for 6/30.

========================================================== CMP Meeting 05-21-03

Suellentrop-Qwest stated that the initial notification was distributed on 5/15. He stated that there had not been any comments and that he wanted to move the CR to development. ==========================================

04-16-03 - CMP Meeting

Suellentrop-Qwest presented the CR and described the input meetings that had already taken place. Van Meter-AT&T stated that at the earlier input meeting Qwest had resolved all CLEC questions, but that she had wanted to have another input meeting to ensure that all CLECs had an opportunity to ask questions. Suellentrop-Qwest stated that this CR was to implement a pre-order option. Berard-Covad asked how long the MLT results were stored in WFA. Suellentrop-Qwest stated that they were stored as long as the circuit was in use. He stated that and CLEC can request the MLT info. Johnson-Eschelon asked how long a Qwest employee would have to wait to get the MLT results. She asked if the employee would have to call the CSIE center and wait 48 hours. Suellentrop-Qwest stated that he would find out. Johnson-Eschelon stated that the team needed to meet again to discuss this CR.

================================================

Input meeting April 22, 2003

Matt White - Qwest Craig Suellentrop - Qwest Don McKay – ATG Communications Mary Roberts – ATG Communications

White–Qwest reviewed the purpose of the meeting.

McKay-ATG asked that Suellentrop-Qwest walk him through the tests Qwest performs before delivery of a loop. He stated that he was interested in qualifying DSL loops from an Unbundled xDSL-I and and Unbundled ADSL Compatible perspective. He asked how Qwest would know that a loop will work for DSL and clarified he was talking about ADSL and SDSL. Suellentrop-Qwest stated that the question is outside the scope of this CR. However, he explained that there is a set of core tests that Qwest performs when a loop is provisioned. Suellentrop-Qwest described the Core tests and stated that the technical parameters of unbundled loops are discussed in the interconnection unbundled loop tech pub - 77384. He concluded that the only additional test for ADSL compatible loops is a load coil test. McKay-ATG stated that he had no other questions. Roberts-ATG stated that she did not have any additional questions about this CR. There was no input regarding the manual process proposed in this CR. White-Qwest thanked the attendees and adjourned the meeting.

==================================================

Input Meeting April 21, 2003

Attendees Matt White – Qwest Craig Suellentrop – Qwest Michael Derleth – ATG Communications Sharon Van Meter – AT&T Liz Balvin – MCI Bonnie Johnson – Eschelon Mike Reith - ZTel

White-Qwest described the purpose of the meeting. Suellentrop-Qwest described the CR and the proposed process.

Johnson-Eschelon asked if Qwest internal personnel and retail have to follow this same process. Suellentrop-Qwest stated that all retail employees would have to follow the same process. He stated that Wholesale SDCs, who handle CLEC orders, have access to WFA. Johnson-Eschelon stated that she was not sure if retail sales would need this information. She asked if retail maintenance would have access to this information. Suellentrop-Qwest stated that network personnel have access to WFA. He stated that if retail wanted this information, they would need to go through this new process. He stated that retail hasn’t requested this information at this time. Johnson-Eschelon asked if there were any other methods that this information will be communicated. Suellentrop-Qwest stated that there was not.

Johnson-Eschelon asked why the CLECs would need this information. Suellentrop-Qwest stated that Qwest uses this information to validate that an unbundled loop is in good working condition when it is provisioned. He explained that CLECs could use this information if the CLEC is interested in marketing services to the end-user served by that loop. He continued that some CLECs have stated that this info is useful to them in qualifying loops for DSL service.

Johnson-Eschelon asked if the MLT testing process was documented in the PCAT. Suellentrop-Qwest stated that he did not think so. Johnson-Eschelon asked if it would be added to the PCAT. Suellentrop-Qwest stated that Qwest will document that the testing process is happening when it documents the new process in the Loop Qualification and Raw Loop Data Job Aid. White-Qwest asked if there were any additional questions. Van Meter-AT&T stated that all of her questions were answered in the 1st input call and in the CMP meeting. There were no additional questions. White-Qwest stated that there would be another input meeting on Tuesday at the same time, thanked the attendees and adjourned the call.

====================================================

=====================================================

Input Meeting Minutes Tuesday, April 8, 2003

Attendees Craig Suellentrop - Qwest Michelle Thacker – Qwest Deni Toye – Qwest Matt White - Qwest Sharon Van-Meter – AT&T Stephanie Prull - McLeod

White-Qwest described the purpose of the meeting and asked Suellentrop the present the CR. Van Meter-AT&T stated that she may need another input call to satisfy her internal users’ needs.

Suellentrop-Qwest presented the change and proposed implementation method and asked for questions. Van Meter-AT&T Asked when Qwest would respond if AT&T submitted a request. Thacker-Qwest stated the answer would be provided within 48 hours. Prull-Allegiance asked if Qwest would look into circuits without MLT. Suellentrop-Qwest stated that Qwest would not. He explained that if a CLEC gives Qwest a circuit ID, Qwest cannot determine what the circuit was before. Similarly, Qwest cannot perform an MLT test if a CLEC is provisioning a circuit that was not a voice grade circuit served by a Qwest switch before the request or if the circuit was provisioned before the MLT test process was in place. Prull-Allegiance asked if there was anywhere that denotes if an MLT test was done. Toye–Qwest stated that Qwest runs a test on all reuse circuits today and put results in WFA. She explained that if there is nothing in WFA, the circuit was not tested for MLT. Van Meter-AT&T asked if calling the center during business hours would ever result in being connected to a voice mailbox. Thacker-Qwest stated that it would not. Van Meter–AT&T asked if she cloud submit a request via e-mail. Thacker-Qwest stated that Qwest could not provide the same level of care for a request submitted by e-mail. She stated that the 48 hour timer for e-mail requests would start when the e-mail was read. She stated this could add several hours to the process. Van Meter-AT&T asked if she would be issued a ticket number when she called in. Thacker-Qwest stated that she would. Prull–McLeod asked if the 48 hour timeline was escalatable. Thacker-Qwest stated that it was. Van Meter-AT&T asked if this was the only format that Qwest could give the CLECs this information. Van Meter–AT&T stated that Mary Pat Cheshire made a declaration to the FCC that stated that Qwest created hard copies from the WFA. Toye–Qwest stated that the current process is not to print WFA information. White-Qwest asked if AT&T needed hard copies. Van Meter-AT&T stated that AT&T wanted all the info available. Toye–Qwest stated that if Qwest were to print the information, it would show the same information that Qwest was sending to the CLECs via e-mail. She stated that AT&T could print the e-mail for a hard copy identical to what Qwest would produce if Qwest’s process were to print hard copies. Prull–McLeod asked which test would WFA refelct if two MLT tests were run. Toye–Qwest stated that the system would display the most recent test results. Van Meter-AT&T asked that Qwest schedule an additional input call. She also requested a draft of the output from Qwest. Thacker-Qwest stated that the output would consist of a cut-and-paste from WFA. Suellentrop-Qwest stated that today CLECs perform MLT tests on their own circuits. He stated that this process would yield the same information. Prull-McLeod stated that she was familiar with this process and the McLeod was currently using it. Van Meter-AT&T asked what the subject line of the e-mail would contain. She asked that it contain the requester’s name. Prull-McLeod stated that having this sorting capability is important. She suggested including the first initial and last name of requester. Thacker-Qwest stated that Qwest would have to check to ensure there is adequate space in the subject line for the circuit number, requesting company, and name information. Van Meter-AT&T asked if the response e-mail from Qwest would be at or within 48 hours of the request. Thacker-Qwest stated that the response would be within 48 hours, if possible.

White-Qwest suggested that the next input meetings be scheduled for April 21 and 22. Van Meter-AT&T stated that Qwest should send the notification scheduling these meetings, but that the team should discuss this issue at the CMP Meeting. She stated that Qwest should cancel the input meetings if the CMP attendees agreed that they were not necessary. Prull-McLeod and Suellentrop-Qwest agreed. White-Qwest stated that he would issue the notification, thanked the attendees, and adjourned the call.

======================================== 03-19-03 CMP Meeting

Suellentrop-Qwest presented the CR as a walk-on. He proposed an input cycle. There were no questions. CR moved to presented.


Open Product/Process CR PC021103-1 Detail

 
Title: Conditioning for DSL level Data Services in all Products at no charge to the CLEC/DLEC
CR Number Current Status
Date
Area Impacted Products Impacted

PC021103-1 Withdrawn
2/11/2003
pre-ordering, ordering, provisioning, billing resale, unbundled loop, loop, UNE-P
Originator: Buckmaster, Cindy
Originator Company Name: Qwest Corporation
Owner: Buckmaster, Cindy
Director:
CR PM: White, Matt

Description Of Change

Qwest is offering the CLEC/DLEC/Reseller Community the opportunity to request Conditioning (Load Coil and Excessive Bridged Tap Removal) from any copper facility for which the CLEC has ordered Data capability and has requested Conditioning according to the LSOG / ASOG requirements. This Conditioning will be provided to the CLEC/DLEC/Reseller at no charge. All Conditioning parameters will be defined by Qwest in applicable external documentation. Once CLEC/DLEC/Reseller Conditioning has been requested and performed, if the end-user’s Voice Grade service is degraded beyond Voice capability, the necessary Load Coils will be restored and the CLEC who requested the Conditioning will be billed for this restoral. This offering is being made for the Non-Loaded, ADSL Compatible, ISDN and x-DSL-I Capable Unbundled Loop (defined as UBL or Loop below), the Line Sharing family of products (defined as Other below), and for UNE-P and Resale when the provisioning of Qwest DSL is requested.

The effective date of this CR will be determined following the discussion at the February CMP meeting. Prior to an effective date, current processes remain in effect.

This CR may be subject to the conditions described under Change in Law Provisions of the SGAT (Section 2.2).


Status History

02/11/03 - CR submitted

02/11/03 - Clarification meeting held

03/19/03 - Withdrawn at CMP Meeting


Project Meetings

03-19-03 - CMP Meeting

Buckmaster-Qwest presented the reason for withdrawal. There were no questions. The CR moved to Withdrawn.


CenturyLink Response

March 12, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the March 19, 2003, CMP Product/Process Meeting

CMP Community

SUBJECT: Qwest’s Change Request Withdrawal - CR #PC021103-1

Qwest wishes to withdraw CMP CR PC021103-1 CR because the changes it requests are more fully presented and detailed in CMP CRs PC022403-2, PC022403-3, PC022403-4, PC022403-5, PC022403-6, PC022403-7, and PC022403-8. Qwest presented these CRs at the Ad Hoc CMP Meeting on March 3, 2003.

Sincerely, Cindy Buckmaster Qwest Product Manager


Open Product/Process CR PC030503-1 Detail

 
Title: Grandfathering of Consumer Packages
CR Number Current Status
Date
Area Impacted Products Impacted

PC030503-1 Completed
6/18/2003
Ordering Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Consumer Packages to be grandparented on May 5, 2003:

Package Name: USOC:

PopularChoice w/ VMS PGOP7

PopularChoice w/o VMS PGOPX

2-Line PopularChoice w/ VMS PGOP8

2-Line PopularChoice w/o VMS PGOPY

CustomChoice PGOCC

2-Line CustomChoice PGOCG

CustomChoice ADL PGOCA

CustomChoice-Complete w/ VMS PGOC7

CustomChoice-Complete w/o VMS PGOCX

2-Line CustomChoice-Complete w/ VMS PGOC8

2-Line CustomChoice-Complete w/o VMS PGOCY

SelectPak with Call Waiting PGOVC

SelectPak grandparented PGOVA

SelectPak with Caller ID PGOVP


Status History

03/05/03 - CR Submitted by Qwest

03/06/03 - CR acknowledged by P/P CMP Manager

3/11/03 - Contacted Qwest - Janean and scheduled Clarification Meeting for 3/17/03 3:30 - 4:30

3/17/03 - Held Clarification Meeting with Qwest

3/19/03 - March CMP Meeting minutes will be posted to the database

4/16/03 - April CMP Meeting minutes will be posted to the database

5/21/03 - May CMP Meeting minutes will be posted to the database

6/18/03 - June CMP Meeting minutes will be posted to the database. The CLECs agreed to close this item as it was implemented May 5, 2003.


Project Meetings

06/21/03 June CMP Meeting Minutes Janean VanDusen –Qwest advised this CR implemented in May and the CLECs agreed ot is okay to close.

5/21/03 May CMP Meeting Minutes Janean VanDusen Qwest advised this CR was implemented May 5, 2003. The notification went out March 18, 2003 effective May 5, 2003. This CR will move to CLEC Test.

4/16/03 April CMP Meeting Minutes PC030503-1 Grandfathering of Consumer Packages

Janean VanDusen Qwest advised this CR is scheduled for implementation May 5, 2003. The notification went out March 18, 2003 effective May 5, 2003.

3/19/03 March CMP Meeting Minutes Janean VanDusen Qwest reviewed and clarified the CR. Janean explained Retail is Grandfathering the packages identified on May 5, 2003.


Open Product/Process CR PC032803-3 Detail

 
Title: Grandfather Centrex , Centrex Plus and Centron service in Colorado, New Mexico, North Dakota and South Dakota
CR Number Current Status
Date
Area Impacted Products Impacted

PC032803-3 Completed
1/21/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Grandfather Centrex, Centrex Plus and Centron service in Colorado, New Mexico, North Dakota and South Dakota on August 1, 2003 and sunset February 1, 2004.

Expected Deliverable:

August 1, 2003


Status History

03-28-03 - CR Received

03-31-03 - CR Acknowledged

04-03-03 - Clarification Meeting

04-16-03 - Presented at CMP Meeting

04-24-03 - Input Meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/17/03 - Notification distributed PROD.10.17.03.F.03587.ResaleCentrexPlusCentron_V16

11/3/03 - No comment notificaiton PROD.10.17.03.F.03587.ResaleCentrexPlusCentron_V16

11/14/03 - PROD.11.14.03.F.0103 8.FNL_RESCENTREXCENTRONV16

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP meeting minutes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database


Project Meetings

CMP Meeting 1/21/04 Janean VanDusen – Qwest advised that this CR was implemented December 1, 2003. The CLECs agreed to change this CR to Completed Status.

CMP Meeting 12/17/03 - Janean VanDusen – Qwest advised that this product is effective December 1, 2003. This CR will remain in CLEC Test status.

CMP Meeting 11/19/03 Janean VanDusen – Qwest advised that this product is effective December 1, 2003. This CR will remain in Development status, until December 1 and then the CLECs agreed that Qwest could change the status to CLEC Test.

CMP Meeting 10-15-03 Janean VanDusen – Qwest advised this project is on track for implementation 12-1-03. This CR will remain in Development Status.

CMP Meeting 9-17-03 Janean Vandusen-Qwest advised that in the last meeting notes the implementation date was captured incorrectly. The correct date is 12/01/03. We are currently still in development.

CMP Meeting 08-20-03

Van Dusen-Qwest stated that implementation had been delayed until 10/1.

============================================

CMP Meeting 07-16-03

White-Qwest stated that there was no change in status.

============================================ CMP Meeting 06-18-03

Van Dusen-Qwest stated that the implementation was scheduled for August 1. ========================================================== CMP Meeting 05-21-03

Van Dusen-Qwest presented the CRs. She suggested moving them to development. ========================================== Input Meeting - 04-24-03

Attendees Janean Van Dusen – Qwest Matt White – Qwest Susan Thompson – Qwest Susie Wells – Qwest Jim Hegarty – Qwest John Steagal – Qwest Lelani Hines - MCI Bonnie Johnson – Eschelon Lori Mendoza – Allegiance

White-Qwest described the purpose of the meeting that and asked Van Dusen-Qwest to present the CRs.

PC040103-1 Van Dusen-Qwest stated that she would be withdrawing PC040103-1 at the May CMP meeting. There were no questions.

PC040103-2 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if the flat rate would apply to retail. Steagal-Qwest stated that there would be one measured service plan available. He explained that Qwest is going from three measured service plans to one.

PC032803-3 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if this CR meant that Qwest would not offer Centrex service in the states indicated in the CR. Hegarty-Qwest stated that Johnson’s assumption was correct. He explained that Qwest will not offer Centrex plus in those stated but that Centrex prime will be available. Johnson-Eschelon asked if Eschelon would be able to order anything new that relates Centrex plus. Hegarty-Qwest stated that a CLEC could not add any new common blocks or systems. Johnson-Eschelon asked if this change only applied to new common blocks. Hegarty-Qwest stated that Qwest would file the tariff with the commission and ask for an August implementation date. He explained that, after the August effective date of tariff, month to month arrangements and contracts that expire during 6 month window must be migrated to another product. He stated that customers with contracts that expire after February 2004 will remain in service and will be able to add lines and feature functionality within existing common blocks and systems; however, no new common blocks and systems may be added. Johnson-Eschelon asked about UNE-P Centrex plus. Van Dusen-Qwest read a statement from Michael Whitt “Because the existing UNE-P Centrex product offering is functionally equivalent to the Retail/Resale Centrex Prime offering (which will continue to be available in Retail/Resale), the UNE-P Centrex offering is not being grandparented or changed in conjunction with the Retail/Resale grandparenting activity. This continuation of availability will minimize transition difficulties, while maintaining an equivalent UNE-P product.” Van Dusen-Qwest explained that what is currently offered for UNE-P Centrex is really Centrex Prime. Johnson-Eschelon stated that Eschelon has converted all resale Centrex plus to UNE-P Centrex plus. She asked if the changes would impact Eschelon in this respect. Van Dusen-Qwest explained that the current UNE-P Centrex plus offering is, in reality, Centrex prime. Hegarty-Qwest confirmed Van Dusen’s statement. Johnson-Eschelon stated that she had no further questions.

White-Qwest confirmed that there were no further questions or comments, thanked the attendees, and adjourned the meeting.

==========================================

04-16-03 - CMP Meeting

Van Dusen-Qwest presented the CR and suggested the input meeting be held for two hours on April 24. The CR was moved into Presented status.


Open Product/Process CR PC040103-1 Detail

 
Title: Grandfather of Integrated T 1 in Denver and Seattle.
CR Number Current Status
Date
Area Impacted Products Impacted

PC040103-1 Withdrawn
4/1/2003
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: White, Matt

Description Of Change

The Integrated T-1 offer in Denver and Seattle (state tariff section 15.4) will be grandfathered on 6/15/03.

Expected Deliverable:

not identified


Status History

04/01/03 - CR Received

04/02/03 - CR Acknowledged

04/02/03 - Clarification Meeting

04/16/03 - Presented at CMP Meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting


Project Meetings

05-21-03 - CMP Meeting

Van Dusen-Qwest presented the withdrawal.

========================================== Input Meeting - 04-24-03

Attendees Janean Van Dusen – Qwest Matt White – Qwest Susan Thompson – Qwest Susie Wells – Qwest Jim Hegarty – Qwest John Steagal – Qwest Lelani Hines - MCI Bonnie Johnson – Eschelon Lori Mendoza – Allegiance

White-Qwest described the purpose of the meeting that and asked Van Dusen-Qwest to present the CRs.

PC040103-1 Van Dusen-Qwest stated that she would be withdrawing PC040103-1 at the May CMP meeting. There were no questions.

PC040103-2 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if the flat rate would apply to retail. Steagal-Qwest stated that there would be one measured service plan available. He explained that Qwest is going from three measured service plans to one.

PC032803-3 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if this CR meant that Qwest would not offer Centrex service in the states indicated in the CR. Hegarty-Qwest stated that Johnson’s assumption was correct. He explained that Qwest will not offer Centrex plus in those stated but that Centrex prime will be available. Johnson-Eschelon asked if Eschelon would be able to order anything new that relates Centrex plus. Hegarty-Qwest stated that a CLEC could not add any new common blocks or systems. Johnson-Eschelon asked if this change only applied to new common blocks. Hegarty-Qwest stated that Qwest would file the tariff with the commission and ask for an August implementation date. He explained that, after the August effective date of tariff, month to month arrangements and contracts that expire during 6 month window must be migrated to another product. He stated that customers with contracts that expire after February 2004 will remain in service and will be able to add lines and feature functionality within existing common blocks and systems; however, no new common blocks and systems may be added. Johnson-Eschelon asked about UNE-P Centrex plus. Van Dusen-Qwest read a statement from Michael Whitt “Because the existing UNE-P Centrex product offering is functionally equivalent to the Retail/Resale Centrex Prime offering (which will continue to be available in Retail/Resale), the UNE-P Centrex offering is not being grandparented or changed in conjunction with the Retail/Resale grandparenting activity. This continuation of availability will minimize transition difficulties, while maintaining an equivalent UNE-P product.” Van Dusen-Qwest explained that what is currently offered for UNE-P Centrex is really Centrex Prime. Johnson-Eschelon stated that Eschelon has converted all resale Centrex plus to UNE-P Centrex plus. She asked if the changes would impact Eschelon in this respect. Van Dusen-Qwest explained that the current UNE-P Centrex plus offering is, in reality, Centrex prime. Hegarty-Qwest confirmed Van Dusen’s statement. Johnson-Eschelon stated that she had no further questions.

White-Qwest confirmed that there were no further questions or comments, thanked the attendees, and adjourned the meeting.

==========================================

04-16-03 - CMP Meeting

Van Dusen-Qwest presented the CR and suggested the input meeting be held for two hours on April 24. The CR was moved into Presented status.


Open Product/Process CR PC040103-2 Detail

 
Title: Grandfather Nebraska and Iowa Measured Service offerings.
CR Number Current Status
Date
Area Impacted Products Impacted

PC040103-2 Completed
4/15/2009
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: White, Matt

Description Of Change

Measured Service offerings in Iowa and Nebraska will be grandfathered June 15, 2003. The following are the USOCs/ descriptions involved:

IA:

RVM – basic Package $.02 per minute on calls placed

AQG – additional line for Basic Package

RWG – Main Line Value package – includes 6 hr. allowance period in the monthly rate.

AWJ – Additional line for Value Package

NE:

RVE – 1 hr. measured package

RWG – 6 hr. measured package

Expected Deliverable:

not identified


Status History

04/01/03 - CR Received

04/02/03 - CR Acknowledged

04/02/03 - Clarification Meeting

04/16/03 - Presented at CMP Meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

11/17/03 - PROD.11.17.03.F.01071.GrandparentMS_NE_IA

12/8/03 - Final Notice for CR PROD.12.08.F01129.FNL_grandparentMS_ne_IA


Project Meetings

CMP Meeting 08-20-03

Van Dusen-Qwest stated that the CR had been implemented in early July and asked to close it. The group agreed and the CR was Closed.

=============================================

CMP Meeting 07-16-03

Van Dusen-Qwest stated that the implementation was on 6/15. She stated that CR could move to CLEC test.

============================================ CMP Meeting 06-18-03

Van Dusen-Qwest stated that the implementation was scheduled for June 15 and recommended that that CR stay in Development. ========================================================== CMP Meeting 05-21-03

Van Dusen-Qwest presented the CRs. She suggested moving them to development. ========================================== Input Meeting - 04-24-03

Attendees Janean Van Dusen – Qwest Matt White – Qwest Susan Thompson – Qwest Susie Wells – Qwest Jim Hegarty – Qwest John Steagal – Qwest Lelani Hines - MCI Bonnie Johnson – Eschelon Lori Mendoza – Allegiance

White-Qwest described the purpose of the meeting that and asked Van Dusen-Qwest to present the CRs.

PC040103-1 Van Dusen-Qwest stated that she would be withdrawing PC040103-1 at the May CMP meeting. There were no questions.

PC040103-2 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if the flat rate would apply to retail. Steagal-Qwest stated that there would be one measured service plan available. He explained that Qwest is going from three measured service plans to one.

PC032803-3 Van Dusen-Qwest presented the CR. Johnson-Eschelon asked if this CR meant that Qwest would not offer Centrex service in the states indicated in the CR. Hegarty-Qwest stated that Johnson’s assumption was correct. He explained that Qwest will not offer Centrex plus in those stated but that Centrex prime will be available. Johnson-Eschelon asked if Eschelon would be able to order anything new that relates Centrex plus. Hegarty-Qwest stated that a CLEC could not add any new common blocks or systems. Johnson-Eschelon asked if this change only applied to new common blocks. Hegarty-Qwest stated that Qwest would file the tariff with the commission and ask for an August implementation date. He explained that, after the August effective date of tariff, month to month arrangements and contracts that expire during 6 month window must be migrated to another product. He stated that customers with contracts that expire after February 2004 will remain in service and will be able to add lines and feature functionality within existing common blocks and systems; however, no new common blocks and systems may be added. Johnson-Eschelon asked about UNE-P Centrex plus. Van Dusen-Qwest read a statement from Michael Whitt “Because the existing UNE-P Centrex product offering is functionally equivalent to the Retail/Resale Centrex Prime offering (which will continue to be available in Retail/Resale), the UNE-P Centrex offering is not being grandparented or changed in conjunction with the Retail/Resale grandparenting activity. This continuation of availability will minimize transition difficulties, while maintaining an equivalent UNE-P product.” Van Dusen-Qwest explained that what is currently offered for UNE-P Centrex is really Centrex Prime. Johnson-Eschelon stated that Eschelon has converted all resale Centrex plus to UNE-P Centrex plus. She asked if the changes would impact Eschelon in this respect. Van Dusen-Qwest explained that the current UNE-P Centrex plus offering is, in reality, Centrex prime. Hegarty-Qwest confirmed Van Dusen’s statement. Johnson-Eschelon stated that she had no further questions.

White-Qwest confirmed that there were no further questions or comments, thanked the attendees, and adjourned the meeting.

==========================================

04-16-03 - CMP Meeting

Van Dusen-Qwest presented the CR and suggested the input meeting be held for two hours on April 24. The CR was moved into Presented status.


Open Product/Process CR PC042303-4 Detail

 
Title: Implement New USOC PGO2N
CR Number Current Status
Date
Area Impacted Products Impacted

PC042303-4 Completed
6/5/2003
Preordering, Ordering, Billing Resale (PGOC-, PGOP-, PGOF-)
Originator: Paxton, Mallory
Originator Company Name: Qwest Corporation
Owner: Paxton, Mallory
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest is implementing a new USOC to identify the second line in a 2-line POTS package. The USOC will not be used for billing or provisioning the line; it will enable us to correctly identify and bill for the elements in the 2-line package account overall.. The impacted packages are identified in the table below.

Expected Deliverable:

Effective 8/9/2003 (or as otherwise determined as part of the Level 4 notification process), CLECs will be required to provide this USOC when ordering a 2-line package.

Fyi: Effective 6/12/03, CLECs will see this USOC on CSRs and Qwest will addd the USOC to orders issued in response to a request to add an impacted package. CLECs will be advised of this change in a Level 1 notification.


Status History

4/23/03: CR Received

4/24/03: CR Acknowledged

4/29/03: Contacted Mallory and scheduled Clarification Call for 5/2/03

5/02/03: Held Clarification Call

5/13/03: Agreed to change the CR# to match the systems SCR# for IMA BPL change and to cross this over after the May CMP meeting as a Manual CR related to a systems CR

5/21/03: May CMP Meeting minutes are posted to the database. This CR will cross over to systems to be handled as a manual workaround to a systems CR.

6/5/03: Changed CR to closed as this was crossed over to systems per May CMP meeting.


Project Meetings

May 21, 2003 CMP Meeting Minutes This CR is notifying the CLECs that effective August 9 this usoc will be required to be put on the LSR. Effective June 12 this usoc will be seen on the CSR, but not be required until August 9. This CR has a related Systems CR that is requesting an IMA BPL edit to require the CLECs to use this usoc. Because this CR is a manual process to the systems CR it will be crossed over to the system team.

CLEC Change Request Clarification Meeting 11:00 a.m. (MDT) / 5/2/03 1-877-561-8688 7385723 PC042303-4 Implement New USOC PGO2N

Mallory Paxton, Qwest Senior Process Analyst Shon Higer, Qwest Senior Process Analyst Janean Van Dusen, Qwest Product Manager Joy McConnell Couch, Qwest Staff Advocate Policy & Law Linda Sanchez-Steinke, Qwest Change Request Project Manager

Introduction of Attendees Introductions of the participants on the Conference Call were made and the purpose of the call discussed.

Review Requested (Description of) Change The description of change requested in the CR was reviewed. Mallory Paxton explained that the USOC is being introduced to identify the second line in a two-line package. The new USOC will be used with the package USOCs PGO2N, PGOCY, PGOC8, PGOPY, PGOP8, PGOFA, PGOFB, PGOVB. CLECs will see the new USOC on service orders, FOCs and CSRs starting in June and will need to provide the USOC when ordering 2 line packages in August. This USOC will not have a charge of its own.

Confirm Areas & Products Impacted Products impacted are Resale POTS, pre-ordering, provisioning and billing.

Confirm Right Personnel Involved Qwest confirmed that the right personnel were involved in the conference call.

Identify/Confirm CLEC’s Expectation CLECs will start seeing this USOC on service orders, FOCs and CSRs starting in June and will need to provide the USOC when ordering 2 line packages starting in August. Identify any Dependent Systems Change Requests

Establish Action Plan (Resolution Time Frame) CLECs will see this USOC on service orders, FOCs and CSRs starting in June and will need to provide the USOC when ordering 2 line packages starting in August.


Open Product/Process CR PC050503-1 Detail

 
Title: Grandparent Switchnet 56.
CR Number Current Status
Date
Area Impacted Products Impacted

PC050503-1 Completed
1/21/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Switchnet 56 will be grandfathered in all 14 Qwest in-region states on 15/2003 with a sunset date of 12/31/2004.

Expected Deliverable:

Grandfathered in all 14 Qwest in-region states on 8/15/2003 with a sunset date of 12/31/2004


Status History

05/05/03 - CR Received

05/05/03- CR Acknowledged

05/05/03 - Clarification Meeting

05/21/03 - Presented at CMP Meeting

06/03/03 - Input Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/10/03 - PROD.11.10.03.F.xxxxx.ResaleGeneral_V35

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/8/03 - PROD.12.08.03.F.01130.FNL_RESALEGENERALV35

12/17/03 - Dec CMP meeting minutes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database


Project Meetings

CMP Meeting 1/21/04 - Janean VanDusen – Qwest advised that this CR was implemented December 15, 2003. The CLECs agreed to change this CR to Completed Status.

CMP Meeting 12/17/03 - Janean VanDusen – Qwest advised Wyoming has been implemented. All other states have an implementation date of December 15, 2003. The CR will move to CLEC Test status.

CMP Meeting 11-19-03 Janean VanDusen – Qwest advised Wyoming has been implemented. All other states have an implementation date of December 15, 2003. The CR will remain in Development status.

CMP Meeting 10-15-03 Janean VanDusen – Qwest advised Wyoming was implemented 8-15-03. All other states are planned for 12-15-03. This CR will remain in Development Status.

CMP Meeting 9-17-03 Janean VanDusen advised this is applicable for all states. Wyoming was implemented 8-15-03 and all other states are targeted for 12/15/03.

CMP Meeting 08-20-03

Van Dusen-Qwest stated that Wyoming had implemented on 8/15 and the other states would implement in 10/15.

===========================================

CMP Meeting 07-16-03

Van Dusen-Qwest stated that Wyoming would implement on 8/15 and the other states would implement in October.

=========================================== CMP Meeting 06-18-03

Van Dusen-Qwest stated that the implementation for Wyoming was on schedule and the other states were on track for October. She recommended that that CR move to Development. ================================================ 05-21-03 - CMP Meeting

Van Dusen-Qwest presented the CR and stated that she was modifying the description of change to add all 14 Qwest in-region states. She suggested an input meeting on June 3 at 11 AM MT.

=================================================

Input Meeting – 06-03-03

Attendees Matt White – Qwest Janean Van Dusen – Qwest Skip Olson – Qwest Barb Newton – Qwest Richard Journey – Qwest Mallory Paxton – Qwest Dalene Fuqua – Qwest Bonnie Johnson – Eschelon

White-Qwest welcomed the attendees, described the purpose of the meeting and asked Van Dusen-Qwest to describe the CRs. Van Dusen-Qwest described the CRs.

050703-6

Johnson-Eschelon asked if this CR would follow the same format as the previous grandfathering CRs. Fuqua-Qwest and Newton-Qwest stated that it would.

050503-2

Johnson-Eschelon asked if grandfathering and grandparenting the same and if they were different from retiring. Van Dusen-Qwest stated that grandfathering and grandparenting were synonymous and that they did not mean the same thing as retiring. Johnson-Eschelon asked if only new customers would be impacted. Van Dusen-Qwest stated that was correct.

050503-1

Johnson-Eschelon asked what switchnet 56 was. Olson-Qwest stated that it was digital data just like ISDN. He explained that switchnet can only run at 58 kbps and that there is a lack of demand for this product.

========================================================== CMP Meeting 05-21-03


Open Product/Process CR PC050503-2 Detail

 
Title: Grandfather SVDS in all state tariffs including FCC tariff.
CR Number Current Status
Date
Area Impacted Products Impacted

PC050503-2 Withdrawn
11/14/2012
Provisioning Resale, UNE-P
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Brummett , Lee
Director:
CR PM: Lorence, Susan

Description Of Change

SVDS will be grandfathered in all states effective 8/15/03.

Expected Deliverable:

Grandfather SVDS effective 8/15/03


Status History

05/05/03 - CR Submitted

05/05/03 - Acknowledged CR

05/13/03 - Claification Meeting

05/21/03 - Presented at CMP Meeting

06/03/03 - Input Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

8/21/03 - Discussed at CMP Meeting

9/17/03 - Sep CMP meeting minutes will be posted to the database

10/17/03 - Oct CMP meeting minutes will be posted to the database

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP meeting minutes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section

7/21/04 - July CMP Meeting notes will be posted to the project meeting section

8/16/04 - August CMP meeting mintues will be posted to the database

9/15/04 - September CMP Meeting minutes will be posted to the database


Project Meetings

11/14/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said this CR was also on the Deferred list and was moved to Pending Withdrawal status. Mark said CenturyLink will like to move the CR to Withdrawn. There were no objections.

10/17/12 Product/Process CMP Meeting Mark Coyne - CenturyLink said this was also a CR that was on the Deferred list from several months ago and that CenturyLink will be moving this CR to Pending Withdrawal for November.

08/15/12 Product/Process CMP Meeting Mark Coyne – CenturyLink relayed that in the July meeting, CenturyLink had asked the owner of each Deferred CR to determine if it should remain in Deferred status, is it should be Withdrawn, or whether it should be re- evaluated. Mark then reviewed the status of each CR as listed on the Attachment:

PC050503-2 Grandfather SVDS in all state tariffs including FCC tariff - CenturyLink is checking to see if there are any current customers for this product and will determine if the CR can be withdrawn.

9/15/04 CMP Meeting Minutes Cindy Macy- Qwest advised that this CR has been pending FCC approval for quite some time. Qwest would like to move this CR to deferred status. Our SME will continue to monitor the CR and when the FCC approval occurs we will put this CR back on the agenda in Development Status. This CR will move to Deferred Status.

8/16/04 CMP Meeting Mintues Cindy Macy – Qwest advised this CR is pending FCC tariff approval. This CR will remain in Development Status.

July 21, 2004 Janean Van Dusen – Qwest advised that the effective date for this CR is still pending. This CR will remain in Development status.

June 16, 2004 Janean Van Dusen – Qwest reported that this CR is still pending. The FCC tariff is still waiting for an effective date. This CR will remain in Development Status.

May 19, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised that this CR remains on hold pending FCC approval. This CR will remain in Development Status.

April 21, 2004 CMP Meeting notes: Janean VanDusen – Qwest advised there is not an implementation date as of yet for this CR. This CR will remain in Development Status.

March 17, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised that the implementation date is still pending. This CR will remain in Development Status.

February 18, 2004 CMP Meeting Janean Van Dusen – Qwest provided status. This CR is still pending FCC approval. This CR will remain in Development Status.

CMP Meeting 1/21/04 Janean Van Dusen – Qwest advised this CR is still waiting for a date. It is in front of the FCC pending approval. This CR will remain in Development Status.

CMP Meeting 12/17/03 - Janean VanDusen – Qwest advised there is not an effective date for this CR as of yet. The CR will remain in Development status.

CMP Meeting 11/19/03 Janean VanDusen – Qwest advised there is not an effective date for this CR as of yet. The CR will remain in Development status.

CMP Meeting 10-15-03 Janean VanDusen – Qwest advised there is not an effective date for this project as of yet. This CR will remain in Development Status.

CMP Meeting 9-17-03 Janean advised the FCC tariff does not have an effective date as of yet. This CR will stay in Development status.

CMP Meeting 08-20-03

Van Dusen-Qwest stated that no precise implementation date was available.

============================================

CMP Meeting 07-16-03

Van Dusen-Qwest stated that the implementation date would be pushed back from 8/15.

=========================================== CMP Meeting 06-18-03

Van Dusen-Qwest stated that the implementation was scheduled for August although it may slip. She recommended that that CR move to Development. ========================================================== Input Meeting – 06-03-03

Attendees Matt White – Qwest Janean Van Dusen – Qwest Skip Olson – Qwest Barb Newton – Qwest Richard Journey – Qwest Mallory Paxton – Qwest Dalene Fuqua – Qwest Bonnie Johnson – Eschelon

White-Qwest welcomed the attendees, described the purpose of the meeting and asked Van Dusen-Qwest to describe the CRs. Van Dusen-Qwest described the CRs.

050703-6

Johnson-Eschelon asked if this CR would follow the same format as the previous grandfathering CRs. Fuqua-Qwest and Newton-Qwest stated that it would.

050503-2

Johnson-Eschelon asked if grandfathering and grandparenting the same and if they were different from retiring. Van Dusen-Qwest stated that grandfathering and grandparenting were synonymous and that they did not mean the same thing as retiring. Johnson-Eschelon asked if only new customers would be impacted. Van Dusen-Qwest stated that was correct.

050503-1

Johnson-Eschelon asked what switchnet 56 was. Olson-Qwest stated that it was digital data just like ISDN. He explained that switchnet can only run at 58 kbps and that there is a lack of demand for this product.

========================================================== CMP Meeting 05-21-03


Open Product/Process CR PC032703-2 Detail

 
Title: Modifications to existing requirement to have Voice Circuit in place before DSL can be added on Line Sharing Product Family
CR Number Current Status
Date
Area Impacted Products Impacted

PC032703-2 Completed
1/21/2004
Line Sharing
Originator: Buckmaster, Cindy
Originator Company Name: Qwest Corporation
Owner: Buckmaster, Cindy
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Qwest is offering a change to the existing process of delivering CLEC requested splitter capability only on an existing Voice service. Qwest is extending the opportunity for the CLEC/DLEC Community to request the provisioning of the splitter prior to completion of the Voice service order. This change will be provided to the CLEC/DLEC at no additional charge. All parameters will be defined by Qwest in applicable external documentation.

This offering is being made for requests that include Line Sharing, Line Splitting and Loop Splitting (identified as Other below).

The proposed effective date of this CR is 08-04-03. Prior to an effective date, current processes remain in effect.

This CR may be subject to the conditions described under Change in Law Provisions of the SGAT (Section 2.2).


Status History

03-27-03 - CR Recieved

03-27-03 - CR Acknowledged

03-28-03 - Clarification Meeting held

04-16-03 - Presented at CMP Meeting

04-25-03 - Input meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

08/07/03 - Qwest issued PROD.08.07.03.F.03493.Line_Sharing_V13 effective date 8/8/03

08/21/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

1/21/04 January CMP Meeting Linda Sanchez-Steinke with Qwest said this CR was opened last March on Product and Process and has remained open for system changes. When this CR was opened, there apparently was confusion with Qwest employees because there was a Systems CR, SCR030603-01EXSC, that was opened for the same reason, to enable CLECs to submit a single LSR for voice & data. PC032703-2 has stayed open because Line & Loop Splitting programming is scheduled for April 04. Qwest would like to close this CR and track the open system work on the Systems CR. Mike Zulevic with Covad said that since this CR has been open for so long, he is concerned that the changes be implemented and the open System CR be cross-referenced with the information in the Product Process CR. It was agree that this CR would be moved to Completed status.

12/17/03 December CMP Meeting Cindy Buckmaster with Qwest said the CR is in the same status; Line Sharing and Loop Splitting for N and T orders will be implemented in April 2004. This CR will remain in Development status.

11/19/03 November CMP Meeting Cindy Buckmaster with Qwest said that the CR status is the same as last month. The capability to place one request for voice and data was implemented in August. Line Splitting and Loop Splitting will be implemented in April 2004. Liz Balvin with MCI said she has a walk-on for the Systems meeting to discuss single LSR for Loop Splitting and has a question if they can submit a single LSR for conversion of non-digitally capable loop. Cindy said that Qwest is working on that process. By telling the voice customer, as you ask Qwest to relate the orders, then we will have the voice delayed and the orders will go in together. There is sometimes a problem making sure to get the orders related. Steve Kast with Qwest had questions about submitting 1 LSR for Loop Splitting on analog loops to convert to digital capable loop and submission of line splitting customers migrating to Loop Splitting. Cindy said that the purpose of this CR was to submit 1 order for new voice service with the ability to accommodate new data service. Because the discussion was not clearly related to this CR there will be a separate call scheduled. This CR will remain in Development Status.

10/15/03 October CMP Meeting Cindy Buckmaster with Qwest provided an update that Line sharing and Loop Splitting programming has not been completed and is scheduled for April 2004 and the CR should be left open until then. Cindy said this is also tied to the AI071603-1, Will Qwest offer CLECs a process to grant blanket approval for DSL Conditioning, which will addressed when the programming is completed. At that time we will arrange an ad hoc CLEC meeting. This CR will remain in Development Status.

09/17/03 September CMP Meeting Linda Sanchez-Steinke provided an update on this CR for Cindy Buckmaster who was unable to attend the CMP meeting. This CR has been delayed for an additional release, IMA 14.0 in December. John Berard with Covad had a question that he will e-mail to Linda.

CMP Meeting 08-20-03

White-Qwest stated that the implementation was still in progress and recommended that the CR remain in Development.

==========================================

CMP Meeting 07-16-03

Buckmaster-Qwest stated that this CR was scheduled for an August 4 implementation. She stated that training was ongoing and that CLECs should try to participate. She explained that CLECs could sign up on the Qwest web site.

============================================ CMP Meeting 06-18-03

Buckmaster-Qwest stated that Qwest was on track for an August 2003 implementation. Berard-Covad asked if he could submit a single resale LSR for voice and data. Buckmaster-Qwest stated that she was not sure and would get back to Berard. Berard-Coavd asked if this change had any impact on the Twin Rivers CR. Buckmaster-Qwest stated that Qwest was doing no additional work on that product line. Zulevic-Covad asked if Qwest was not doing this work because of the systems prioritization. Buckmaster-Qwest stated that the primary reason was because of line sharing program questions. She stated that she was not sure how Qwest will address these products; partly because of the order on the triennial review. Zulevic-Covad stated that he thought the product had already been developed. Buckmaster-Qwest stated that the software has not been developed. Zulevic-Covad stated that he had talked to Twin Rivers and thought that they would request a re-evaluation of the LOE on their CR. He stated that they would probably wait until the triennial review was released.

========================================================== CMP Meeting 05-21-03

Bockmaster-Qwest described the CRs and suggested the be put into development. Zulevic-Covad asked of Qwest had looked into line sharing. Buckmaster-Qwest stated that she would send Zulevic an e-mail. (On 5/22, White-Qwest forwarded Zulevic and e-mail from Buckmaster.) ========================================== Input Meeting 04-25-03

Attendees Matt White – Qwest Cindy Buckmaster – Qwest Sharon Van Meter – AT&T Caren Schaffner – MCI Chad Werner – WorldCom Kim Isaacs – Eschelon Bonnie Johnson - Eschelon Mike Zulavic – Covad Lisa McNabola – Multiband Communications

White-Qwest described the purpose of the meeting and asked Buckmaster to describe the CRs. Buckmaster-Qwest described the CRs. She stated that implementation was scheduled for August 2003. She explained that there were two CRs in order to distinguish between the line sharing product family from the resale and UNE-P product family. She went on to explain the current ordering process and stated that the capability of resale and UNE-P customers to identify whether their customer will qualify is limited to a search of working telephone numbers. She explained that currently, CLECs must have a working number to determine if DSL is available. She stated that recently, however, a Qwest initiated Systems CR that was introduced to give CLECs ability to search by address. She noted that this CR would be implemented on August 4.

Buckmaster-Qwest explained that currently the process in Resale is for CLECs to provide Resold Qwest Voice and DSL (in other words, one customer of record). She stated that the voice order must be completed before a CLEC can order data and the CLEC must search by the working telephone number to determine if there is DSL capability. In the future, CLECs will be able to request voice and data on the same order for the same customer. Qwest will tie those requests for the two types of services together and Qwest assignments will look for DSL capable facilities. She stated that this process would exist under the DSL interval. CLECs will be able to check for DSL capability ahead of time using the new tool that can now check for DSL capability based on address. There were no questions about resale.

Buckmaster-Qwest stated that for Line Sharing (Qwest provided Voice/CLEC provided Data) there are two customers of record. Today, the Qwest voice order must be complete before a CLEC data order can be processed. However, after august 4th, the process is different; the end user will place an order for voice, and once the telephone number is assigned, the CLEC can add the number to the DSL request to link it to the voice order. She explained that there is one complication that she wanted the CLECs to be aware of: When the end user places a voice order, they receive a voice interval, however, when the data order is placed, it receives a data interval. This situation creates the possibility of having analog facilities assigned to the voice order when digital facilities will be required to carry the data. That could result in a longer interval to install the data (i.e., if the assigned facility requires line conditioning).

Zulevic-Covad asked what the normal voice interval was. Buckmaster-Qwest stated that she though it was 2 days. Zulevic-Covad asked if the end user states that they will be ordering DSL from another provider, could Qwest look for DSL capable facilities. Buckmaster-Qwest stated that although Qwest is looking for a way to ensure data capable facilities could be assigned on the voice request in this situation, there is not currently a way to do that without unnecessarily assigning data capable facilities to all voice requests. Therefore, at this time, Qwest could not accommodate that request. Zulevic-Covad asked if Qwest had looked into ways of identifying it as a potential data order. Buckmaster-Qwest stated that Qwest was still trying to work through that issue. She explained that, thus far, Qwest had not found a solution but were still working on it. Zulevic-Covad stated that the line sharing products currently have a 3-day interval and Qwest is saying that could be pushed out to 5 (due to Line Move or UDC Removal) or 15 days (due to Conditioning – Load Coil and/or Bridged Tap Removal). Buckmaster-Qwest stated that Zulevic was correct. She stated that if the customer asked for the retail and line share order to be due at the same time, Qwest could link the orders and minimize the occurrences of delay to times when conditioning is required.

Buckmaster-Qwest stated that one Qwest concern is that CLECs will not check for data capability before placing linked orders. She stated that if CLECs do check for data capability, it would help Qwest avoid rejecting orders when facilities are not DSL capable. Zulevic-Covad asked if the voice service had to be in place for line shared services. Buckmaster-Qwest stated that the voice service must only be ordered.

Zulevic-Covad asked if Qwest has looked at migration of services. He stated that he had I submitted a CR for this. Buckmaster-Qwest stated that she was not familiar with the particular CR. White-Qwest stated that he would send Buckmaster the CR in question.

Buckmaster-Qwest stated that for Line Splitting, as there is one customer of record, Qwest and can accept simultaneous orders if data capable facilities are available. Zulevic-Covad asked if only one FOC will be returned. Buckmaster-Qwest stated that she thought that Line Splitting orders got a FOC at 24 hours. She explained that data capable facilities do not have FOC in 24 hours. She stated that she could not commit that the CLECs will receive only one. She stated that they will receive one in the first 24 hours and the Qwest will send another FOC if there is a need to modify the delivery date (ex. line conditioning).

Buckmaster-Qwest stated that Loop Splitting was handled just like Line Splitting.

Buckmaster-Qwest stated that Qwest did not want to force the end user into a longer interval for voice while they wait for data, so Qwest leaves that decision up to the CLEC.

Zulevic-Covad asked where the process was for resold Qwest voice with a second party DSL. He stated that there is currently an unprioritized systems CR for this product. Buckmaster-Qwest stated that the changes discussed on this call are only for existing products. Zulevic-Covad stated that the implementation of these changes requires OSS work. Buckmaster-Qwest stated that there was currently a Qwest originated systems CR, slated for implementation in 13.0, that is intended to provide the CLEC the ability to qualify a circuit at an address level. She stated that there are also other minor systems changes to allow CLECs to pass voice orders with a data requirement. There were no further questions. White and Buckmaster thanked the attendees and adjourned the meeting.

=============================

04-16-03 - CMP Meeting

Buckmaster-Qwest presented the CRs and suggested that the input meeting be held April 25th. Balvin-WorldCom asked if there was a systems CR associated with this. Buckmaster-Qwest stated that there was but that she did not know the number. (The CR number is SCR030603-01.) Zulevic-Covad asked if this would impact line sharing with resale voice. Buckmaster-Qwest stated that it would only impact existing products. Johnson-Eschelon asked if a CLEC could qualify by address under the new process. Buckmaster-Qwest stated that a CLEC could. CR moved to presented.


Open Product/Process CR PC032703-3 Detail

 
Title: Modifications to existing requirement to have Voice Circuit in place before Qwest DSL can be added on Resale and UNE P Services
CR Number Current Status
Date
Area Impacted Products Impacted

PC032703-3 Completed
10/15/2003
Resale, UNE-P
Originator: Buckmaster, Cindy
Originator Company Name: Qwest Corporation
Owner: Buckmaster, Cindy
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Qwest is offering a change to the existing process of delivering Qwest Data only on an existing Qwest POTS (Voice) service. Qwest is extending the opportunity for the CLEC/ Reseller Community to request both the Qwest Voice and Qwest Data services at the same time on one request. This change will be provided to the CLEC/ Reseller at no additional charge. All parameters will be defined by Qwest in applicable external documentation.

This offering is being made for requests that include Resale of both Qwest Voice and Qwest DSL Services. Products affected include UNE-P and Resale (identified as UNE-P and Resale below).

The proposed effective date of this CR is 08-04-03. Prior to an effective date, current processes remain in effect.


Status History

03-27-03 - CR Recieved

03-27-03 - CR Acknowledged

03-28-03 - Clarification Meeting held

04-16-03 - Presented at CMP Meeting

04-25-03 - Input meeting

05/21/03 - Discussed at CMP Meeting

06/18/03 - Discussed at CMP Meeting

07/16/03 - CR Discussed at CMP Monthly Meeting

08/01/03 - Qwest sent CMP notification PROD.08.01.03.F.03491.DSL_PreOrdering, effective 8/4/03

8/20/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

10/15/03 October CMP Meeting Cindy Buckmaster with Qwest gave an update on this CR. Resale and UNE-P with data and voice can be ordered at the same time. Bonnie Johnson with Eschelon said she submitted an external document request asking for further clarification to the PCAT because it did not tie the Loop Qualification and the PCAT clearly. Cindy said that she appreciates the feedback and encouraged request for clarification anytime documentation is unclear. It was agree this CR should be moved to Completed Status.

09/17/03 September CMP Meeting Linda Sanchez-Steinke provided an update on this CR for Cindy Buckmaster who was unable to attend the CMP meeting. This CR was implemented with IMA release 8/4. John Berard with Covad had a question that he will e-mail to Linda. This CR will remain in CLEC Test.

CMP Meeting 08-20-03

White-Qwest stated that change was implemented on 8/4 and recommended it move into CLEC Test. Zulevic-Covad asked if a process has been developed to ensure a voice service is provisioned on a DSL capable loop when the customer indicates they will be adding CLEC data (Line Sharing). White-Qwest stated that he would take the question back.

=============================================

CMP Meeting 07-16-03

Buckmaster-Qwest stated that this CR was scheduled for an August 4 implementation. She stated that training was ongoing and that CLECs should try to participate. She explained that CLECs could sign up on the Qwest web site.

============================================ CMP Meeting 06-18-03

Buckmaster-Qwest stated that Qwest was on track for an August 2003 implementation. Berard-Covad asked if he could submit a single resale LSR for voice and data. Buckmaster-Qwest stated that she was not sure and would get back to Berard. Berard-Coavd asked if this change had any impact on the Twin Rivers CR. Buckmaster-Qwest stated that Qwest was doing no additional work on that product line. Zulevic-Covad asked if Qwest was not doing this work because of the systems prioritization. Buckmaster-Qwest stated that the primary reason was because of line sharing program questions. She stated that she was not sure how Qwest will address these products; partly because of the order on the triennial review. Zulevic-Covad stated that he thought the product had already been developed. Buckmaster-Qwest stated that the software has not been developed. Zulevic-Covad stated that he had talked to Twin Rivers and thought that they would request a re-evaluation of the LOE on their CR. He stated that they would probably wait until the triennial review was released.

========================================================== CMP Meeting 05-21-03

Bockmaster-Qwest described the CRs and suggested the be put into development. Zulevic-Covad asked of Qwest had looked into line sharing. Buckmaster-Qwest stated that she would send Zulevic an e-mail. (On 5/22, White-Qwest forwarded Zulevic and e-mail from Buckmaster.) ========================================== Input Meeting 04-25-03

Attendees Matt White – Qwest Cindy Buckmaster – Qwest Sharon Van Meter – AT&T Caren Schaffner – MCI Chad Werner – WorldCom Kim Isaacs – Eschelon Bonnie Johnson - Eschelon Mike Zulavic – Covad Lisa McNabola – Multiband Communications

White-Qwest described the purpose of the meeting and asked Buckmaster to describe the CRs. Buckmaster-Qwest described the CRs. She stated that implementation was scheduled for August 2003. She explained that there were two CRs in order to distinguish between the line sharing product family from the resale and UNE-P product family. She went on to explain the current ordering process and stated that the capability of resale and UNE-P customers to identify whether their customer will qualify is limited to a search of working telephone numbers. She explained that currently, CLECs must have a working number to determine if DSL is available. She stated that recently, however, a Qwest initiated Systems CR that was introduced to give CLECs ability to search by address. She noted that this CR would be implemented on August 4.

Buckmaster-Qwest explained that currently the process in Resale is for CLECs to provide Resold Qwest Voice and DSL (in other words, one customer of record). She stated that the voice order must be completed before a CLEC can order data and the CLEC must search by the working telephone number to determine if there is DSL capability. In the future, CLECs will be able to request voice and data on the same order for the same customer. Qwest will tie those requests for the two types of services together and Qwest assignments will look for DSL capable facilities. She stated that this process would exist under the DSL interval. CLECs will be able to check for DSL capability ahead of time using the new tool that can now check for DSL capability based on address. There were no questions about resale.

Buckmaster-Qwest stated that for Line Sharing (Qwest provided Voice/CLEC provided Data) there are two customers of record. Today, the Qwest voice order must be complete before a CLEC data order can be processed. However, after august 4th, the process is different; the end user will place an order for voice, and once the telephone number is assigned, the CLEC can add the number to the DSL request to link it to the voice order. She explained that there is one complication that she wanted the CLECs to be aware of: When the end user places a voice order, they receive a voice interval, however, when the data order is placed, it receives a data interval. This situation creates the possibility of having analog facilities assigned to the voice order when digital facilities will be required to carry the data. That could result in a longer interval to install the data (i.e., if the assigned facility requires line conditioning).

Zulevic-Covad asked what the normal voice interval was. Buckmaster-Qwest stated that she though it was 2 days. Zulevic-Covad asked if the end user states that they will be ordering DSL from another provider, could Qwest look for DSL capable facilities. Buckmaster-Qwest stated that although Qwest is looking for a way to ensure data capable facilities could be assigned on the voice request in this situation, there is not currently a way to do that without unnecessarily assigning data capable facilities to all voice requests. Therefore, at this time, Qwest could not accommodate that request. Zulevic-Covad asked if Qwest had looked into ways of identifying it as a potential data order. Buckmaster-Qwest stated that Qwest was still trying to work through that issue. She explained that, thus far, Qwest had not found a solution but were still working on it. Zulevic-Covad stated that the line sharing products currently have a 3-day interval and Qwest is saying that could be pushed out to 5 (due to Line Move or UDC Removal) or 15 days (due to Conditioning – Load Coil and/or Bridged Tap Removal). Buckmaster-Qwest stated that Zulevic was correct. She stated that if the customer asked for the retail and line share order to be due at the same time, Qwest could link the orders and minimize the occurrences of delay to times when conditioning is required.

Buckmaster-Qwest stated that one Qwest concern is that CLECs will not check for data capability before placing linked orders. She stated that if CLECs do check for data capability, it would help Qwest avoid rejecting orders when facilities are not DSL capable. Zulevic-Covad asked if the voice service had to be in place for line shared services. Buckmaster-Qwest stated that the voice service must only be ordered.

Zulevic-Covad asked if Qwest has looked at migration of services. He stated that he had I submitted a CR for this. Buckmaster-Qwest stated that she was not familiar with the particular CR. White-Qwest stated that he would send Buckmaster the CR in question.

Buckmaster-Qwest stated that for Line Splitting, as there is one customer of record, Qwest and can accept simultaneous orders if data capable facilities are available. Zulevic-Covad asked if only one FOC will be returned. Buckmaster-Qwest stated that she thought that Line Splitting orders got a FOC at 24 hours. She explained that data capable facilities do not have FOC in 24 hours. She stated that she could not commit that the CLECs will receive only one. She stated that they will receive one in the first 24 hours and the Qwest will send another FOC if there is a need to modify the delivery date (ex. line conditioning).

Buckmaster-Qwest stated that Loop Splitting was handled just like Line Splitting.

Buckmaster-Qwest stated that Qwest did not want to force the end user into a longer interval for voice while they wait for data, so Qwest leaves that decision up to the CLEC.

Zulevic-Covad asked where the process was for resold Qwest voice with a second party DSL. He stated that there is currently an unprioritized systems CR for this product. Buckmaster-Qwest stated that the changes discussed on this call are only for existing products. Zulevic-Covad stated that the implementation of these changes requires OSS work. Buckmaster-Qwest stated that there was currently a Qwest originated systems CR, slated for implementation in 13.0, that is intended to provide the CLEC the ability to qualify a circuit at an address level. She stated that there are also other minor systems changes to allow CLECs to pass voice orders with a data requirement. There were no further questions. White and Buckmaster thanked the attendees and adjourned the meeting.

=============================

04-16-03 - CMP Meeting

Buckmaster-Qwest presented the CRs and suggested that the input meeting be held April 25th. Balvin-WorldCom asked if there was a systems CR associated with this. Buckmaster-Qwest stated that there was but that she did not know the number. (The CR number is SCR030603-01.) Zulevic-Covad asked if this would impact line sharing with resale voice. Buckmaster-Qwest stated that it would only impact existing products. Johnson-Eschelon asked if a CLEC could qualify by address under the new process. Buckmaster-Qwest stated that a CLEC could. CR moved to presented.


Open Product/Process CR PC061203-1 Detail

 
Title: Soft Coding of Value Choice Features
CR Number Current Status
Date
Area Impacted Products Impacted

PC061203-1 Completed
11/19/2003
Ordering, Provisioning Resale POTS
Originator: Paxton, Mallory
Originator Company Name: Qwest Corporation
Owner: Paxton, Mallory
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Level 4 Notification of Change in Value Choice Packages

Change Call Waiting (USOCs ESX or N2W), Long Distance Alert (USOC LWE), and Caller ID (USOC NNK) to optional features included in the Value Choice package prices but not automatically ordered as part of the packages. This means the package USOCs PCV6X (Value Choice) and PGOVB (2-Line Value Choice) will no longer automatically include these features. If desired, these features must be ordered separately by the CLEC. If not ordered, they will not be provisioned. If ordered, they will continue to be included in the package rate and will not incur additional charges.


Status History

06/12/03 - CR Received

06/12/03 - CR Acknowledged

06/23/03 - Held Clarification Meeting

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/20/03 - Qwest sent notification PROD.10.20.03.F.03589.ValueChoice_V11 effective 10/21/03

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

11/19/03 November CMP Meeting Linda Sanchez-Steinke with Qwest gave an update on this CR. The changes were effective on 10/21/03 and Mallory Paxton has received no questions and had suggested that the CR be moved to completed status. It was agreed this CR will move to Completed.

10/15/03 October CMP Meeting Mallory Paxton with Qwest gave an update on this CR. The changes are scheduled to go into release 13.01. Mallory suggested that the CR move to CLEC test. It was agreed this CR will move to CLEC test.

09/17/03 September CMP Meeting Mallory Paxton with Qwest gave an update on this CR. The PCAT will be updated and targeted implementation is 10/22/03. This CR will remain in Development status.

08/20/03 August CMP Meeting Mallory Paxton with Qwest provided an update. Changes will be effective 10/20/03 and a level 4 notification will be provided to CLECs. This CR will be moved to Development status.

07/16/03 July CMP Meeting Terri Kilker with Qwest presented this CR With the implementation of this CR, Call Waiting, Long Distance Alert and Caller ID will be soft coded in the Value Choice Features so the customer can chose the features if they want them. If the end user wants these features, the CLEC should identify them on the LSR. Bonnie Johnson asked if ordering the features would be a manual process and Terri answered no, that CLECs will need to order the three optional services by USOC separately. Targeted implementation is 10/20/03.

CLEC Change Request Clarification Meeting 2:30 p.m. (MT) / Monday, June 23, 2003

1-877-554-8688 PIN 1930099 # PC061203-1 Soft Coding of Value Choice Features Name/Company:

Janean Van Dusen, Qwest Mallory Paxton, Qwest Ellen Munz, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of the change requested in the CR was reviewed. Mallory Paxton said that Value Choice Packages, USOCs PCV6X, Value Choice and PGOVB, 2-Line Value Choice will no longer automatically include the following features: Call Waiting (USOCs ESX or N2W), Long Distance Alert (USOC LWE) and Caller ID (USOC NNK). Call Waiting, Long Distance Alert and Caller ID can be ordered separately as optional features but will not be automatically ordered as part of the Value Choice packages. This change will be effective on 10/20/03 (IMA/FTS/CRM Release 13.01)

Confirm Areas & Products Impacted Product impacted is Resale POTS

Confirm Right Personnel Involved Qwest confirmed that Mallory Paxton and Janean Van Dusen are correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation Qwest plans to make this change effective on 10/20/03 (IMA/FTS/CRM Release 13.01)

Identify any Dependent Systems Change Requests No dependent change requests were identified.

Establish Action Plan (Resolution Time Frame) Mallory Paxton will present this CR at the July CMP Meeting.


Open Product/Process CR PC070103-2 Detail

 
Title: Processing of EAS (Extended Area Service) Generated TGSRs (Trunk Group Service Requests)
CR Number Current Status
Date
Area Impacted Products Impacted

PC070103-2 Completed
7/21/2004
Ordering, Provisioning EAS - Extended area service Local Switching
Originator: LaBate, Michael
Originator Company Name: Qwest Corporation
Owner: Saunders, Craig
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Currently the Service Delivery Center (SDC) processes internal requests for new trunk groups for CLECs. Central office conversions represent an example where such requests arise. The TGSR issued from the SDC notifies the CLEC that they will be required to issue an Access Service Request (ASR) for provisioning new trunk groups for the implementation of office conversions. EAS expansions often generate the need for provisioning new local trunk groups for CLECs for successful implementation. Currently EAS expansions are not formally included in the SDC process for generating TGSRs. Instead, the EAS Team has relied on the Circuit Administration Center (CAC) to contact, explain, and convince CLECs (and the Qwest Service Managers) of the need for new local trunk groups for EAS implementation. Besides being less efficient, the team does not believe that this is the appropriate method of contact. CLECs are accustomed to the SDC process of TGSR notification for provisioning new trunk groups. Thus, Qwest wishes to have EAS expansions included in that process. Doing so will incorporate an established method and timeframe in the section of the EAS process requiring additional local trunk groups from CLECs for EAS implementations.

Examples of the need for inclusion in the existing SDC process include the two recent EAS expansions in Rogue River OR and Garfield county CO. There were 13 and 8 co-providers, respectively, that had to be contacted to provision additional local trunking for those EAS expansions. This could have been expedited if EAS had been a part of the existing SDC TGSR notification process.


Status History

07/01/03 - CR Received

07/01/03 - CR Acknowledged

07/16/03 - CR Discussed at CMP Monthly Meeting

08/21/03 - Discussed at CMP Meeting

09/08/03 - Qwest sent final notice PROS>09.08.03.F.01181.FNLL_ExtendedAreaService will be operational 9/23/03

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

07/21/04 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

07/21/04 July CMP Meeting Craig Saunders with Qwest gave an update that this CR had been in deferred status, then CLEC test. The process has worked well for the recent EAS conversion and Craig suggested that the CR be closed. This CR will move to Completed status.

06/16/04 June CMP Meeting Craig Saunders with Qwest gave an update that TGSR’s have been issued to Crystal Communications and Jaguar Communications and the process seems to be working well. The EAS change will be made in mid-July. This CR will remain in CLEC Test status.

05/19/04 May CMP Meeting Linda Sanchez-Steinke with Qwest said this CR was put into deferred status last year because we did not have an EAS expansion. This CR now has been brought out of deferred status because there will be an EAS expansion. Craig Saunders gave an update that the EAS in Northfield, MN will be effective on 7/14/04. TGSR’s have been provided to Crystal Communications and Jaguar Communications. This CR will move to CLEC Test status.

11/19/03 November CMP Meeting Mike LaBate gave an update that the PCAT changes became operational on 9/23/03 and that we have not had an EAS expansion and it may be sometime before there is an expansion. Kit Thomte with Qwest suggested that the CR be moved to Deferred status until there is an EAS expansion. This CR will be moved to Deferred status.

10/15/03 October CMP Meeting Mike LaBate gave an update that the PCAT changes became operational on 9/23/03. This CR will be moved to CLEC test.

09/17/03 September CMP Meeting Mike LaBate was not able to attend the CMP meeting and provided the following status for the meeting minutes. Qwest sent final notice of the Extended Area Service on 9/8/03 and will be operational 9/23/03.

CMP Meeting 08-20-03

White-Qwest stated that the change was currently in the comment cycle. CR was moved to Development status.

============================================= CLEC Input Meeting

Attendees Matt White - Qwest Michael LaBate – Qwest Kay Gruebel - Qwest Jan Dimmitt - Qwest Majorie Brown - Qwest Millie Amundson – US Link Kim Isaacs – Eschelon Paul Hanser – Eschelon Marcell - Eschelon Deanna Bean – Sprint Lori Mendoza - Allegiance

White-Qwest described the purpose of the meeting. LaBate-Qwest described the CR and the proposed process for notification of requirement of additional trunking for a local calling area expansion implementation. Qwest currently uses this process for office conversions, etc.

Millie-USLink asked if CLECs would be obligated to put in trunking if they had less than one span’s worth of traffic to the office. LaBate-Qwest stated that when Qwest gets a request, Qwest analyzes the scenario and attempts to utilize existing trunking. He explained that if there is no local tandem in the region and no direct local trunking, there would be a requirement to put in additional trunking. Marcell-Eschelon asked if CLECs can use the access tandem. LaBate-Qwest stated that if a CLEC uses Qwest’s SPOP product they can. Brown-Qwest stated that in Eschelon’s case, there is language in the ICA that allows functionality similar to the SPOP product. Marcell-Eschelon asked if his company would be covered if they already have trunks in place. Brown-Qwest stated that they would. White-Qwest asked if there were any additional questions. There were none.

=================================== CMP Meeting 07-16-03

LaBate-Qwest presented the CR and proposed a 7/24 input call. Van Meter-AT&T stated that the CLEC would contact White-Qwest if 9 AM would not work.


Open Product/Process CR PC080503-1CM Detail

 
Title: Change to the CMP Document Section 5.1.4 & Section 10.3.1
CR Number Current Status
Date
Area Impacted Products Impacted

PC080503-1CM Completed
9/17/2003
Change to CMP Document
Originator: Nolan, Laurel
Originator Company Name: Qwest Corporation
Owner: Sanchez-Steinke, Linda
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Proposed Change to Section 5.1.4: Systems Change Request Origination Process and to Section 10.3.1: Prioritization Review. See attached redline of the Change Management Process document.


Status History

08/05/03 - CR Submitted

08/06/03 - CR Acknowledged

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/04/03 - Held Ad Hoc Meeting

09/10/03 - Qwest issued CMPR.09.10.03.F.01564.CMPDocVote Notification of vote to be taken at September CMP

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/17/03 September CMP Meeting Linda Sanchez-Steinke with Qwest said there was an ad hoc meeting held on 9/4/03 to discuss this CR. Quorum is 7 carriers and we have established quorum with 9 carriers present today. E-mail ballots can be sent to cmpcr@qwest.com and Peggy Esquibel Reed is monitoring the mailbox. Per Section 2.1 the vote must be unanimous to change the language in the CMP. A vote of yes will incorporate the changes into the document and a vote of no will not incorporate the changes into the document.

The following votes were provided by meeting participants: Covad voted yes AT&T voted yes U S Link voted yes Eschelon voted yes Vartec voted yes MCI voted yes Qwest voted yes

The following votes were provided by e-mail votes: Allegiance voted yes McLeod voted yes

Linda said the result of the vote is 9 - yes and 0 - no and said the changes will be incorporated into the CMP. Linda said she would provide notification of the vote disposition.

Ad Hoc Meeting Minutes PC080503-1CM & 2CM Add to section 4.0 TYPES OF CHANGE CLEC impacting defect CMP Product & Process September 4, 2003 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:20 a.m. Mountain Time

PURPOSE

At the August CMP Meeting, participants agreed to hold a conference call to discuss Qwest initiated CR’s PC080503-1CM and PC080603-2CM changes to CMP document. The following is the write-up of the discussion.

List of Attendees: John Berard - Covad Julie Pikar - U S Link Jen Arnold - U S Link Sharon Van Meter - AT&T Stephanie Prull - McLeod Lori Mendoza - Allegiance Liz Balvin - MCI Bonnie Johnson - Eschelon Laurel Nolan - Qwest Jim Maher - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss Qwest initiated CRs PC080503-1CM and PC080503-2CM.

PC080503-1CM Laurel Nolan with Qwest said that at the August CMP we discussed the changes to the CMP document. These changes would make the systems CR process similar to the process followed for Product/Process change requests. Laurel explained the changes; Change Requests submitted 14 days prior to that month’s CMP meeting would be presented by the originator. This would allow discussion to take place, additional products to be added, prior to Qwest providing the LOE. Laurel explained that the CR would complete the review and LOE process prior to the prioritization review meeting with the CLEC community. With these changes, Qwest would not have to re-LOE the CRs right before prioritization and would provide a more effective management of the prioritization process. This change would allow for a full investigation of the CR, a solution created, and reviewed at the next month’s CMP meeting.

PC080503-2CM Jim Maher with Qwest explained that the purpose of the change to Section 10.4 was being proposed to allow any party the opportunity to submit SCRP requests as needed without the 5 calendar day after prioritization requirement. Jim pointed out that this would also include not having to follow the late adder process since any party willing to fund the development of the CR should not be required to have the CR go through the late adder prioritization if they are going to pay for the development of that CR.

Jim suggested that the vote be taken at the next CMP meeting. Linda asked if there were any questions. No questions were asked.

08/20/03 - August CMP Meeting Laurel Nolan with Qwest presented this CR to change Section 5.1.4 and 10.3.1 of the Wholesale Change Management Process Document. Laurel explained that currently the Systems CR process is such that CRs may be submitted up to 21 days prior to the meeting and with this proposed change the CR process would be structured similar to the product/process CR timeline. She continued that changing these sections allows the opportunity to expand the scope of the CR at the meeting the CR is presented. Then at the next month’s meeting, Qwest would provide the LOE and response. Sharon Van Meter with AT&T asked when the LOE is provided now. Laurel answered that the LOE is provided at the same meeting the CR is presented (as long as it’s submitted 21 days prior to the meeting) and that with the proposed changes the systems side would mirror the Product/Process side. Judy Schultz said that many times the first LOE is invalid because the scope is increased or decreased when the CR is presented. Laurel explained that the CR would complete the review and LOE process prior to the prioritization review meeting with the CLEC community. Qwest would not have to re-LOE the CRs days before prioritization. Liz Balvin asked if the LOE would be provided at the first meeting. Laurel answered that Qwest would provide LOE at the next month’s meeting if the scope based on the discussion from the first meeting when the CR was presented. Liz said she was concerned about the increase in Late Adders because CRs would need to be submitted one month prior to the prioritization review meeting. Laurel stated that CLECs and Qwest could use the Late Adder or SCRP processes if they needed to request CR implementation outside of the prioritization process . Linda Sanchez-Steinke stated that she would schedule an Ad Hoc meeting to gather input to this CR. Laurel suggested that any comments or suggested language be sent to cmpcr@qwest.com prior to the meeting.


Open Product/Process CR PC080503-2CM Detail

 
Title: Change to the CMP Document Section 10.4
CR Number Current Status
Date
Area Impacted Products Impacted

PC080503-2CM Completed
9/17/2003
Change to CMP Document
Originator: Nolan, Laurel
Originator Company Name: Qwest Corporation
Owner: Sanchez-Steinke, Linda
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Proposed change to SCRP language in Section 10.4: Special Change Request Process. Please see attached redline of the Change Management Process Document.


Status History

08/05/03 - CR Submitted

08/06/03 - CR Acknowledged

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/10/03 - Qwest issued CMPR.09.10.03.F.01564.CMPDocVote Notification of vote to be taken at September CMP

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/17/03 September CMP Meeting An ad hoc meeting to discuss this CR was held on 9/4/03. Linda Sanchez-Steinke with Qwest said there was an ad hoc meeting held on 9/4/03 to discuss this CR. Quorum is 7 carriers and we have established quorum with 9 carriers present today. E-mail ballots can be sent to cmpcr@qwest.com and Peggy Esquibel Reed is monitoring the mailbox. Per Section 2.1 the vote must be unanimous to change the language in the CMP. A vote of yes will incorporate the changes into the document and a vote of no will not incorporate the changes into the document.

Ad Hoc Meeting Minutes PC080503-1CM & 2CM Add to section 4.0 TYPES OF CHANGE CLEC impacting defect CMP Product & Process September 4, 2003 1-877-572-8687, Conference ID 3393947# 10:00 a.m. - 10:20 a.m. Mountain Time

PURPOSE

At the August CMP Meeting, participants agreed to hold a conference call to discuss Qwest initiated CR’s PC080503-1CM and PC080603-2CM changes to CMP document. The following is the write-up of the discussion.

List of Attendees: John Berard - Covad Julie Pikar - U S Link Jen Arnold - U S Link Sharon Van Meter - AT&T Stephanie Prull - McLeod Lori Mendoza - Allegiance Liz Balvin - MCI Bonnie Johnson - Eschelon Laurel Nolan - Qwest Jim Maher - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss Qwest initiated CRs PC080503-1CM and PC080503-2CM.

PC080503-1CM Laurel Nolan with Qwest said that at the August CMP we discussed the changes to the CMP document. These changes would make the systems CR process similar to the process followed for Product/Process change requests. Laurel explained the changes; Change Requests submitted 14 days prior to that month’s CMP meeting would be presented by the originator. This would allow discussion to take place, additional products to be added, prior to Qwest providing the LOE. Laurel explained that the CR would complete the review and LOE process prior to the prioritization review meeting with the CLEC community. With these changes, Qwest would not have to re-LOE the CRs right before prioritization and would provide a more effective management of the prioritization process. This change would allow for a full investigation of the CR, a solution created, and reviewed at the next month’s CMP meeting.

PC080503-2CM Jim Maher with Qwest explained that the purpose of the change to Section 10.4 was being proposed to allow any party the opportunity to submit SCRP requests as needed without the 5 calendar day after prioritization requirement. Jim pointed out that this would also include not having to follow the late adder process since any party willing to fund the development of the CR should not be required to have the CR go through the late adder prioritization if they are going to pay for the development of that CR.

Jim suggested that the vote be taken at the next CMP meeting. Linda asked if there were any questions. No questions were asked.

08/20/03 - August CMP Meeting Laurel Nolan with Qwest presented this CR to change Section 10.4, which currently implies that a CR would go through the prioritization process or Late Adder process prior to invoking the SCRP. Laurel stated that Qwest discovered these discrepancies when invoking the SCRP. She stated that the language needed to be clear that SCRP could be invoked at any time and that a CR did not have to go through the Prioritization or Late Adder processes. There will be an Ad Hoc meeting scheduled to gather input to this CR.


Open Product/Process CR PC080603-1 Detail

 
Title: Manual ordering process for Resale Metropolitan Optical Ethernet.
CR Number Current Status
Date
Area Impacted Products Impacted

PC080603-1 Completed
4/21/2009
Ordering, Billing Resale, Metropolitan Optical Ethernet
Originator: Wees, Jolene
Originator Company Name: Qwest Corporation
Owner: Wees, Jolene
Director:
CR PM: Harlan, Cindy

Description Of Change

This CR is to give CLECs notification of a process change for a new Retail product offering under development. On November 18, 2003, Qwest Retail will introduce Metropolitan Optical Ethernet (MOE) which will be available for resale. The product is currently in the final development stage. Upon rollout, the MOE Ordering Form will be available through your Account Team or Service Manager. Ordering will be manual and billing will be through IABS.

Expected Deliverable:

Proposed Implementation Date:

November 18, 2003


Status History

CR Received 8/6/03

CR Acknowledge 8/6/03

Customer contaced 8/11/02

Clarified CR and CMP process 8/12/03 - will offer CLEC input meeting on 9/2/03

8/20/03 - August CMP Meeting minutes posted to database

9/2/03 - Held CLEC Input Meeting

9/17/03 - Se p CMP meeting notes will be posted to the database

10/7/03 - Sent Bonnie email asking if she had any questions for Qwest to review prior to the Oct meeting.

10/8/03 - Bonnie requested additional ad hoc meeting to be scheduled to discuss product in more detail. Meeting will be scheduled first week in November

10/13/03 - Scheduled ad hoc meeting for November 3

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/3/03 - CMP Notification PROD.10.03.03.F.03571.ResaleMOE_V1

10/20/03 - Product notification PROD.10.17.03.A.000965.MetOpticalEther

11/3/03 - Held CLEC Ad Hoc meeting to discuss product in more detail

11/17/03: Notification PROD.11.17.03.F.01054.MOE_V1

11/19/03 - Nov CMP meeting minutes will be updated to the database

11/19/03 - PROD.11.19.03.F.01075MOE_V2

11/19/03 - PROD.11.19.03.F.010666.RESALE_INTERCONN_MOE_V2


Project Meetings

December 17, 2003 CMP Meeting Jo Wees – Qwest advised this product was effective November 18, 2003. No comments were received. This CR will move to Closed Status.

November 19, 2003 CMP Meeting Jo Wees – Qwest advised this product is available effective November 18, 2003. This CR will move to CLEC Test.

November 3, 2003 Ad Hoc Meeting CLEC Ad Hoc Meeting PC080603-1 Manual Ordering Process for Resale Metropolitan Optical Ethernet November 3, 2003 2:00 – 3:00 MT

In attendance: Bonnie Johnson – Eschelon Jo Wees – Qwest Barry Eastman – ViLata Communications Kim Isaacs – Eschelon Gloria Davy – Qwest Cindy Macy – Qwest

Cindy Macy – Qwest explained the purpose of the call is to review product and process details for ‘PC080603-1 Manual ordering process for Resale Metropolitan Optical Ethernet’. Jo Wees – Qwest explained she can talk about the ordering process and Gloria Davy – Qwest can talk about the product.

Gloria Davy advised the product is flexible and easy to use. The tariff will be filed today. This product allows end users to connect to multiple locations; point to point or multipoint. Users can order only as much as they need in varying increments; starting at 5-10 GB. Tech Pub 77411# has the details and information such as network interface, access link and connectivity. The initial ordering period is 1 years and 3-5 years. Non Recurring charges will be posted with the FCC this afternoon. The product is available November 18, 2003.

Bonnie Johnson – Eschelon asked about product availability. Gloria advised it is available in three states, inter and intrastate. Denver and Minneapolis, and then San Francisco and LA. Bonnie asked if Qwest would be expanding to other cities. Gloria advised that there are additions planned for 1st and 3rd Quarter next year. Bonnie asked what kind of customer would use this service? Gloria advised that currently we have large school districts interested. This would provide connectivity to the Internet for middle schools.

Barry Eastman – ViLata Communications asked if there is any distance limitations. Gloria advised yes and those are outlined in the tech pub. Barry asked how would Qwest qualify end users for this product? The CLLI code identifies wire center availability. Fiber needs to be available. If the customer wants the service the equipment needs to be on premise or placed on the premise. CISCO 3550 is the equipment used at the POP. Gloria agreed to check the web site for tariff access and contact Barry to advise the URL.

No further questions were asked. The CLECs thanked Qwest for holding the call.

October 15, 2003 CMP Meeting Jo Wees – Qwest advised implementation is scheduled for November 18, 2003. An additional ad hoc meeting is scheduled for November 3, 2003. Please send additional questions to cynthia.macy@qwest.com prior to the meeting. This CR will remain in Development Status.

September 17, 2003 CMP Meeting Jo Wees – Qwest advised this is a new retail product available for resale. We are on target for November 18, 2003. We would like to move this CR to Development status. Bonnie advised there were questions that were taken away from the meeting that were supposed to be answered. The CLECs felt they didn’t get enough information at the meeting. Jo Wees advised the product is under development and not all the information is known as of yet. Cindy Macy- Qwest advised the Clarification notes capture the questions that were asked and our replies. This was a review of a draft process and the completed product/process will be available via the Wholesale web site via a Level 4 PCAT with a comment cycle. Jo Wees asked Bonnie to send in the questions they had that did not get addressed and Qwest would be glad to review them. Susie Bliss-Qwest advised we will talk with our Retail product managers to help them understand how to communicate at the CLEC input meetings.

CLEC Input Meeting – PC080603-1 Manual Ordering Process for Resale Metropolitan Optical Ethernet

September 2, 2003 1:00 – 2:00 p.m. MST 1-877-572-8687 3393947#

In attendance: Jo Wees – Qwest Jean Novak – Qwest Sharon VanMeter – ATT Liz Balvin – MCI Mary Korthour – Eschelon Steve Kolar – Eschelon Joy McConnell Couch – Qwest Jeanne Buck – Qwest Dave Hahn – Qwest Ann Garlock – Eschelon Jeff Falk – Qwest Janean VanDusen – Qwest Barry Eastman – ViLata Communication

Cindy Macy – Qwest opened the call and reviewed the attendee list. The purpose of this meeting is to review CR PC080603-1 Manual Ordering Process for Resale Metropolitan Optical Ethernet.

Janean VanDusen – Qwest reviewed the product description with the CLECs. Janean advised Metropolitan Optical Ethernet (MOE) would be available to resellers. It is a new product not offered yet, but the planned implementation date is November 18, 2003.

The following questions were asked: ? When will pricing information be available? It will be available in the tariff when it is filed. ? Does this need to be added to our ICA before we can order it? No, as it is a resale product. ? Where will the product be offered / available? This information will be published in the Disclosure document. Expected to be a few wire centers in Colorado / Minnesota. ? What are the order intervals? These are not established as of yet but will match retail. ? Are Service Managers going to be covered on the process? Yes.

Jo Wees – Qwest reviewed the draft / high level process to order. Jo explained you would contact your sales or service manager to order the product. This would go through the AQCB system, a PCAT will be published covering ordering and product information, the CLEC will print or fax or email the order form to the center, the center will issue the order, and billing will be through IABS.

August 20, 2003 CMP Meeting Jolene Wees-Qwest advised on November 18 this product should be available for Resale. There is an order form (MOE) that will be available through your Service Manager. This product will be ordered manually and billing will be done in IABS. Cindy Macy-Qwest advised a CLEC Input meeting is planned for September 2 at 1:00 p.m. MST. This CR will move to Presented status.


Open Product/Process CR PC050703-6 Detail

 
Title: Grandfather Measured Service plans in CO, ID North, NM, ND
CR Number Current Status
Date
Area Impacted Products Impacted

PC050703-6 Completed
4/21/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

The following Measured Service Plans will be grandfathered effective 8/15/03:

Colorado:

LW1- Main line .05 first .02 additional

AKN- additional line

1MR- Main line .11 per call after 50 call allowance

AHR- additional line

1MB- Individual Message rate line 50 allowable .11 each additional

ALS- additional line

Idaho North:

LW1

1MR

New Mexico:

LW1

AKN

North Dakota:

RVJ- Main line .05 1st minute .01 each additional

AKN


Status History

05/07/03 - CR Submitted

05/08/03 - CR Acknowledged

5/13/03 - Scheduled Clarification Call for 5/15/03

5/15/03 - Held Clarification Call

5/21/03 - May CMP Meeting Minutes will be posted to the database

06/03/03 - Input Meeting

6/18/03 - June CMP P/P meeting mintues will be posted to the database

7/16/03 - July CMP monthly meeting will be posted to the database

8/20/03 - Aug CMP meeting minutes - see notes

9/17/03 - Sep meeting minutes will be posted to the database

10/13/03 - Ad Hoc meeting held to review changes to CR

10/15/03 - Oct CMP meeting minutes will be posted to the database

11/7/03 - Final Notice PROD.11.07.03.F0128.FNL_GrandparentMS

11/19/03 - Nov CMP meeting minutes will be posted to the databas

12/5/03 - Retraction of Grandparenting notification PROD.12.05.03.F.01141.RetractGrandparentMS_NM

12/17/03 - Dec CMP notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/5/04 - Prod.03.05.04.F.01439.FNL_GrandparentMS_USOCsNM

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/21/04 - April CMP meeting notes will be posted to the project meeting section


Project Meetings

April 21, 2004 CMP Meeting notes: Janean VanDusen – Qwest advised that Colorado was previously cancelled. Idaho North is also cancelled. ND was effective January 30 and the work was completed in the 15.0 release. NM Res has now been cancelled and NM Bus was completed March 23. This CR will move to Completed Status.

March 17, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised that Colorado has been cancelled, Idaho is on hold, North Dakota is in effect and will be completed with the IT work in 15.0, NM residence is on hold and will be implemented with a Level 1 when we have a date, NM business is effective March 23 and a revised final notice was sent out. This CR will remain in CLEC Test Status.

February 18, 2004 CMP Meeting Janean Van Dusen – Qwest provided status. New Mexico Residence is on hold and New Mexico Business is scheduled for implementation March 22. Idaho North is on hold, Colorado was cancelled and North Dakota was effective January 30 with the IT work complete with 15.0. This CR will remain in CLEC Test Status.

January 21, 2004 CMP Meeting Janean Van Dusen – Qwest recapped that Colorado was cancelled, Idaho was on hold, ND was effective January 30, 2004 but it won’t be implemented until 15.0 gets installed. New Mexico was retracted last month due to the commission not approving it yet. NM now has an effective date of January 30 so Qwest would like to implement this as a Level 1. The CLECs agreed. This CR will remain in CLEC Test Status.

December 17, 2003 CMP Meeting notes Janean VanDusen – Qwest advised this CR will be implemented December 1, 2003. NM was retracted by the state PUC and the retraction notice went out. This CR will remain in CLEC Test status.

November 19, 2003 CMP Meeting Janean VanDusen – Qwest advised this CR will be implemented December 1, 2003. This CR will remain in Development status, until December 1 and then the CLECs agreed that Qwest could change the status to CLEC Test.

October 15, 2003 Janean VanDusen – Qwest advised this project is scheduled for implementation 11-28-03. A CLEC ad hoc meeting was held as there were some changes made to New Mexico and South Dakota. These changes were reviewed during the ad hoc meeting. This CR will remain in Development Status.

September 17, 2003 Janean advised NM and ND are scheduled for 10/20/03. Idaho North is on hold and Colorado has been cancelled. This CR will remain in Development status.

August 20, 2003 Monthly Meeting minutes Janean VanDusen-Qwest advised this CR was delayed and is now scheduled for implementation on October 15, 2003.

July 16, 2003 Monthly Meeting minutes Janean VanDusen-Qwest advised this CR is scheduled and on track for implementation August 15, 2003.

June 18, 2003 Monthly Meeting minutes Janean VanDusen – Qwest advised there was a CLEC input meeting held and this CR is on track for deployment in August.

Input Meeting – 06-03-03

Attendees Matt White – Qwest Janean Van Dusen – Qwest Skip Olson – Qwest Barb Newton – Qwest Richard Journey – Qwest Mallory Paxton – Qwest Dalene Fuqua – Qwest Bonnie Johnson – Eschelon

White-Qwest welcomed the attendees, described the purpose of the meeting and asked Van Dusen-Qwest to describe the CRs. Van Dusen-Qwest described the CRs.

050703-6

Johnson-Eschelon asked if this CR would follow the same format as the previous grandfathering CRs. Fuqua-Qwest and Newton-Qwest stated that it would.

050503-2

Johnson-Eschelon asked if grandfathering and grandparenting the same and if they were different from retiring. Van Dusen-Qwest stated that grandfathering and grandparenting were synonymous and that they did not mean the same thing as retiring. Johnson-Eschelon asked if only new customers would be impacted. Van Dusen-Qwest stated that was correct.

050503-1

Johnson-Eschelon asked what switchnet 56 was. Olson-Qwest stated that it was digital data just like ISDN. He explained that switchnet can only run at 58 kbps and that there is a lack of demand for this product.

May 21, 2003 CMP Meeting Minutes

Van Dusen – Qwest presented the CR and suggested an input meeting on June 3 at 11 AM MT.


Open Product/Process CR PC060403-1 Detail

 
Title: Grandparent of CustomNet in MN for Public Access Lines (PAL) classes of service.
CR Number Current Status
Date
Area Impacted Products Impacted

PC060403-1 Completed
9/17/2003
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

CustomNet will be granparented in MN effective 8/15/2003 for Public Access Lines (PAL) customers. Fraud Protection will be available as the replacement product.

Expected Deliverable:

8/15/03


Status History

06/04/03 - CR Received

06/06/03 - CR Acknowledged

06/13/03 - Held Clarification Meeting

06/18/03 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/30/03 - Held CLEC input meeting

07/08/03 - Qwest issued product notice PROD.07.08.03.F.03460.CustomNet_V5.0

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/17/03 September CMP Meeting Janean Van Dusen with Qwest said that the changes were effective 8/15/03. This CR will be moved to Completed status.

08/20/03 August CMP Meeting Janean Van Dusen with Qwest gave an update on the CR and said that the PCAT was effective on 8/15. This CR will be moved to CLEC Test status.

07/16/03 July CMP Meeting Janean Van Dusen with Qwest gave an update on the CR and said that the PCAT was updated on 7/8 and will be effective on 8/15.

Meeting Minutes

Grandparent of CustomNet in MN for Public Access Lines (PAL) classes of service CMP Product & Process June 30, 2003 1-877-572-8687, Conference ID 3393947# 8:30 a.m. - 8:45 a.m. Mountain Time

List of Attendees Sharon Van Meter, AT&T Janean Van Dusen, Qwest Pat Finley, Qwest Linda Sanchez-Steinke, Qwest Marcia Ziegler, Qwest

PURPOSE At the June CMP Meeting, participants agreed to hold a conference call to obtain input from the CLEC Community on the proposed change request and a time for questions and answers to be addressed. The following is the write-up of the discussions, action items, and decisions made in the working session.

MEETING MINUTES The meeting began with Qwest making introductions and welcoming all attendees.

Overview of Change Request Janean Van Dusen with Qwest provided an overview of the change request, Grandparent of CustomNet in MN for Public Access Lines (PAL) classes of service, and said that on 8/15/03 the service will be grandparented and will no longer be available for new orders. For customers with the existing service, it will remain on the line and no new orders for CustomerNet in Minnesota will be accepted. Fraud Protection is the alternate product for CustomNet and the USOCS are PSESI, PSESO, PSESP. Qwest opened up the discussion for questions.

Questions and Answers Sharon Van Meter with AT&T asked for a definition of CustomNet. Pat Finley said CustomNet service provided screening and blocking restricting billing on long distance calls and alternate billing. Fraud Protection, the alternate product, prevents PAL lines from accepting incoming collect calls and prevents third number billing to coin.

Qwest asked if there were any additional questions. No questions were asked.

These minutes will be posted to CR PC060403-1 on the CMP Web site.

06/18/03 June CMP Meeting Janean Van Dusen with Qwest presented this CR. CustomNet will be grandparented in Minnesota effective 8/15/03 and Fraud Protection is the alternative product for CustomNet. Qwest would like to hold an input meeting on 6/30/03 at 8:30 Mountain time and will provide a notification with details of the call. This CR will be moved to Presented status.

CLEC Change Request Clarification Meeting 8:30 a.m. (MT) / Friday, June 13, 2003 1-877-554-8688 PIN 1930099 # PC060403-1 Grandparent of CustomNet in MN for Public Access Lines (PAL) classes of service. Name/Company: Janean Van Dusen, Qwest Pat Finley, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change The description of the change requested in the CR was reviewed. Janean Van Dusen said that CustomNet will be grandparented in MN for Public Access Lines classes of service on 8/15/03. If customers have CustomNet in MN they can keep the product and on 8/15/03 it will be grandfathered.

Confirm Areas & Products Impacted Products impacted are Resale PAL

Confirm Right Personnel Involved Qwest confirmed that Janean Van Dusen and Pat Finley are correct personnel to resolve the CR.

Identify/Confirm CLEC’s Expectation Qwest plans to hold an meeting to gain input from CLEC Community on 6/30/03.

Identify any Dependent Systems Change Requests No dependent change requests were identified.

Establish Action Plan (Resolution Time Frame) Janean Van Dusen will present this CR at the June CMP Meeting.


Open Product/Process CR PC050703-3 Detail

 
Title: Release of microduct technology.
CR Number Current Status
Date
Area Impacted Products Impacted

PC050703-3 Completed
9/17/2003
Pre-ordering, Ordering, Provisioning, Billing Poles, Ducts, Rights of Way
Originator: Lacy, Jane
Originator Company Name: Qwest Corporation
Owner: Campbell, Ben
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Where deployed within the Qwest network, microduct technology will be offered for lease. Microduct technology is an alternative solution to the current innerduct technology. Microduct is a smaller version of innerduct that must be placed inside an innerduct. Available duct capacity is increased since up to four microducts can be placed within a 1¼-inch innerduct.

Expected Deliverable

July, 2003


Status History

05/07/03 - CR Submitted

05/08/03 - CR Acknowledged

05/21/03 - Presented at CMP Meeting

06/02/03 - Input Meeting

06/03/03 - Qwest issued PROD.06.03.03.F.03418.Access_PDR_V15 proposed effective date is 7/18/03

06/18/03 - Discussed at CMP Meeting

07/03/03 - Qwest issued Final Notice PROD.07.03.03.F.03454.FNL_Access_PDR_V15 became operational 7/18/03

07/16/03 - CR Discussed at CMP Monthly Meeting

08/21/03 - Discussed at CMP Meeting

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/17/03 September CMP Meeting Ben Campbell with Qwest said that the PCAT became operational on 7/18/03. This CR will be moved to Completed status.

CMP Meeting 08-20-03

White-Qwest stated that the CR was implemented on 7/18 and asked that the CR be moved to CLEC Test.

=================================================

CMP Meeting 07-16-03

White-Qwest stated that the change would be implemented on 7/18. Van Meter-AT&T asked that the CR remain in Development.

================================================ CMP Meeting 06-18-03

White-Qwest stated that the change would be implemented July 18. He asked that the CR be moved into Development. ======================================================= Input Meeting 06-02-03

Attendees Matt White – Qwest Jane Lacy – Qwest Shirley Tallman - Qwest Liz Balvin – MCI Stephanie Prull – McLeod Kim Isaacs – Eschelon Carla Pardee – AT&T

White-Qwest welcomed attendees, described the purpose of the meeting and asked Lacy-Qwest to describe the CR. Lacy-Qwest described the proposed change and asked if there were any questions or comments. Balvin-MCI asked what the purpose of an innerduct was. Tallman-Qwest stated that microduct is a smaller pathway to place facilities within. She explained that there is no difference in the fiber structure but that the cladding/protection around the fiber is different to allow it to be pulled into a smaller duct. Balvin-MCI asked if microduct had the same capabilities. Tallman-Qwest stated that it did, but that it gives more network flexibility. Lacy-Qwest stated that Qwest was looking to implement this change on July 18. Balvin-MCI asked if a contract amendment would be required. Lacy-Qwest stated that it would because of the terms and conditions that relate to this product. Pardee-AT&T asked if Qwest has proposed amendment language. Balvin-MCI stated that the CLECs needed this language as soon as possible. Lacy-Qwest stated that she would see if Qwest could get that language out prior to the launch of the product. There were no more questions.

========================================================== CMP Meeting 05-21-03

Lacy-Qwest presented the CR and suggested an input meeting on June 2 at 10 AM MT.


Open Product/Process CR PC050703-4 Detail

 
Title: DC Power Changes
CR Number Current Status
Date
Area Impacted Products Impacted

PC050703-4 Completed
1/21/2004
Product Prerequisites Collocation DC Power
Originator: Campbell, Ben
Originator Company Name: Qwest Corporation
Owner: Campbell, Ben
Director:
CR PM: Harlan, Cindy

Description Of Change

Qwest will be implementing a DC Power Reading process , DC Power Restoration Process and adding clarifying information about DC Power rates and DC Power Reduction process.

Expected Deliverable

June 2003


Status History

05/07/03 - CR Submitted

05/08/03 - CR Acknowledged

5/13/03 - Scheduled Clarification Call for 5/15

5/15/03 - Held Clarification Call

5/21/03 - May CMP Meeting Minutes will be posted to the database

5/28/03 - Sent out notification to hold CLEC input meeting on June 5 at 1:00 mst

6/5/03 - Held CLEC input meeting

6/18/03 - June P/P CMP meeting mintues will be posted to the database

7/16/03 - July P/P CMP meeting minutes will be posted to the database

8/20/03 - August P/P CMP meeting minutes will be posted to the database

9/1703 - Sep CMP meeting minutes will be posted to the database

10/1/03 - Sent out Notification for CLEC ad hoc meeting to review DC Power questions from Eschelon - ad hoc meeting scheduled for 10/8/2003

10/8/03 - Held CLEC Ad Hoc meeting. Agreed to schedule another meeting to finish discussion. Meeting planned for 10-20-03.

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/20/03 - Held Ad Hoc Meeting to review DC Power questions

11/1803 - PROD.11.18.03.F.01069.ColloGeneralV17 notification update published

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/9/03 - PROD.12.09.03.F.01133.FNL_COLLOGENERALV17

12/17/03 - Dec CMP meeting minutes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database


Project Meetings

January 21, 2004 CMP Meeting Cindy Macy – Qwest reported that this CR was implemented December 24, 2003. The CLECs agreed to change this CR to Completed Status.

December 17, 2003 CMP Meeting notes Cindy Macy – Qwest reported that this CR has an implementation date of December 24 and no additional comments were received. This CR will stay in CLEC Test status.

November 19, 2003 CMP Meeting Ben Campbell – Qwest advised the PCAT was released on November 18, 2003. Implementation is scheduled for January 2, 2004. This is an optional offering that the CLEC can opt into. This CR will move to CLEC Test.

DC Power PC050703-6 Ad Hoc Meeting October 20, 2003 10:30 – 12:00 MT

In attendance: Lori Mendoza – Allegiance Mary Ann Wyborg – Qwest Liz Balvin – MCI Lydia Braze – ATT Paul Hanser – Eschelon Bill Fellman – Qwest Julie Skidmore – Qwest Steve Nelson – Qwest Sue Lamb – Digital Easy Chair Stacy Miesenhiemer – Sprint Curtis Ashton – Qwest Kim Issacs – Eschelon Ben Campbell – Qwest Bonnie Johnson – Eschelon Bill Markert – Eschelon Bob Alex – Qwest Cindy Macy - Qwest

Cindy Macy – Qwest explained the purpose of today’s call is to address any outstanding questions on DC Power and to have Steve Nelson – Qwest share the process for measuring power and Qwest’s intent regarding how to implement this CR.

Steve Nelson – Qwest advised that Qwest would offer this process as optional to the CLECs. An Amendment will be available for the CLECs to participate in, if they choose.

Curtis Ashton – Qwest discussed how power is measured. Paul Hanser-Eschelon shared their concern that the time of day when power is measured will impact the reading. Steve Nelson – Qwest explained the plan is to measure between normal business hours (8-5). This time depicts normal usage. Bonnie Johnson – Eschelon advised that there could be negative impacts depending if the CLECs have business or residence end users. Curtis Ashton – Qwest explained his experience shows that variance is 15-16% from peak to non-peak hours. Ben Campbell – Qwest recapped that this process will be an optional process and only applies to 61+ amps. Paul Hanser – Eschelon suggested that Qwest measure power at a CLEC suggested time. Lori Mendoza – Allegiance explained to Paul if you order two 40 amp feeds, it would not be measured. These are billed individually.

Steve Nelson – Qwest advised he checked with Cost Dockets and determined that this level of specificity was not discussed in State Hearings. Rates were filed and no questions came up.

Steve Nelson – Qwest recapped that an Amendment will be done, we will measure capacity 61+ amps. The process for 60 amps and below is 50% imputed rate. If you want changes to the 60 amp and below process a CR would need to be issued.

Cindy Macy – Qwest asked each CLEC if they had additional questions. Each CLEC confirmed they did not have additional questions. Eschelon advised they do not have additional questions, but they are not in agreement with this process.

Next Steps: Provide status at November CMP meeting Update the process based on the discussion from the Ad Hoc Meetings Build the Amendment Notify on the process

If the CLEC wants to participate in this process they would contact their Service Manager or negotiate to opt into the process or negotiate different terms.

October 15, 2003 CMP Meeting Ben Campbell – Qwest advised that Qwest held a meeting last week to review questions about the process. The team did not get through all of the questions and another meeting is scheduled for October 20 from 10:30 – 12:00 MT. Qwest will address the additional questions during that meeting. Qwest put the implementation on hold until we complete the ad hoc calls with the CLECs. Bonnie Johnson – Eshcelon thanked Qwest for delaying the implementation. This CR will remain in Development Status.

- CLEC Ad Hoc Meeting PC050703-4 DC Power October 8, 2003

In attendance; Bill Markert Eschelon Brent Debrock Cbeyond Lydia Braze ATT Michelle Brandt ATT Bill Fellman Qwest Liz Balvin MCI Lori Mendoza Allegiance Steve Nelson Qwest Bonnie Johnson Eschelon Julie Pickar US Link Pam Lehrke Hickory Tech Kim Issacs Eschelon Stacy Meisenheimer Sprint Celia Westfall Sprint Janet Leonard Qwest Sue Lamb Digital Easy Chair Curtis Ashton Qwest Lance 180 Communications

Cindy Macy Qwest opened the call and advised that the purpose of the call is to review questions that were sent in from the CLECs.

Bonnie Johnson-Eschelon advised the CR was not clear so it is difficult to comment on documentation when you do not understand what the CR is doing. Bonnie advised comments don’t impact whether Qwest will unilaterally impose the change, but how do we know what to comment on. Bonnie advised she sent in her comments the day of the September CMP meeting. She would have preferred to hold this meeting during the comment cycle or earlier than it was scheduled. Maybe next time the meeting could be held earlier.

Steve Nelson – Qwest assured the CLEC Community that Qwest is not about unilaterally imposing this process on the CLECs. Qwest has the CLEC’s interest in mind. Steve assured Bonnie that Qwest would update documentation if needed.

Bonnie said she didn’t want this to turn into the DS1 Capable Loop issue. If the CLECs are paying one rate on 10-22 and a new rate on 10-23 then it should go through a tariff change. Steve stated, that this is an existing process for measuring greater than 61 amps usage. This is an attempt to increase the percentage of reading taken in order that CLEC can pay for the DC Power they are using rather then ordered amps.

General discussion took place as follows:

Ben explained this process applies to 61+ amps and higher. Qwest is not measuring 60 amps or less. The process for 60 amps or less is not changing. The process for 61+ amps is what this update is addressing.

Paul Hansen-Eschelon asked why couldn’t Qwest charge for actual usage if under 60 amps. Ben Campbell-Qwest advised that Qwest does not have the meters available to measure the usage. Steve Nelson Qwest advised it would cost Qwest a considerable amount to add the meters. The cost models for less than 60 amps are based on ½ the rate. This was filed in Cost Dockets for each state.

Brent Cbeyond asked if they have ordered a 40 amp feed and they are using 40 amps, will they still be billed at 50% the rate? Steve Nelson Qwest advised yes, the current billing for 60 amps or less is not changing.

Discussion occurred regarding the combined rate element in ND/Oregon and SD. Bill Markert asked if the combined rate equals capacity. Steve Nelson advised yes, in these three states there is not a stand alone DC usage rate element.

Bill Markert asked if there was mention in cost dockets with how Qwest measures the rates? Steve Nelson Qwest advised he would check on cost docket and see if this was discussed. Bonnie clarified and Steve agreed that Qwest is going to implement a measuring plan that we have approved. This CR communicates the current measuring plan we have had in place for years and commits to an improved process to taking the measurements and updating the billing.

Questions were asked about if the non-recurring rate would be adjusted. Steve advised no, that the non-recurring rate is based on cost docket models. Lori Mendoza-Allegiance verified that Qwest agreed to disagree that we should not decrease our non recurring rates as these rates have been approved by cost dockets. This process change does not impact non-recurring rates.

Lance-180 Communications verified that Qwest is not changing rates or billing procedures. Steve confirmed we are not changing rates. This process improves our measurement process for actual DC power usage.

The group did not have enough time to answer all the questions. Agreement was reached to schedule another ad hoc call. Cindy Macy-Qwest agreed she would schedule the next call as soon as possible. There is a 5-day meeting notification timeline.

September 17, 2003 Benjamin Campbell – Qwest advised the document is available for review. Benjamin explained the high level process and changes made for power reading and reduction. Bonnie requested for Qwest to hold another CLEC Input meeting as she has some questions that she would like answered. Bonnie advised this appears to be a CR that is being used to change rates. Bonnie agreed she would send her questions to Qwest and Cindy Macy would schedule another CLEC meeting to provide answers to the questions.

August 20, 2003 Cindy Macy-Qwest advised the document is completed and the Documentation team is reviewing it. It should be available soon. Sharon VanMeter asked what level this will be. Cindy Macy-Qwest advised this is a Level 4 update.

July 16, 2003 CMP Monthly Meeting Cindy Macy-Qwest advised that Ben is in progress of updating the PCAT and anticipates it will be available for review in the next couple of weeks. This process will be available for review and comments cycle via the Notification process.

June 18, 2003 Monthly Meeting minutes Cindy Macy – Qwest advised there was a CLEC input meeting held on June 5 and attendance and participation was good. Ben Campbell is currently working on developing the updates to the process and will provide status next month. Sharon VanMeter asked if there would be other CLEC meetings and Qwest replied only if needed. Otherwise the documentation will go through the normal comment cycle. The CLECs agreed to move this CR to Development.

6/5/03 CLEC Input Meeting 1:00 - 2:00 mst

Ben Campbell - Qwest Cindy Macy - Qwest Bonnie Johnson - Eschelon Pam Zimmerman - US Link Liz Balvin - MCI Jen Arnold - US Link Brent Debrock - CBeyond Tom - US Link Mike Zulevic - Covad (we spoke with him later due to the delay in the call starting)

Ben Campbell reviewed the CR. Ben explained some of the changes include: Identifying the individual rate element and decscribe those in more detail. Update and add language in DC Power Restoration. Update DC Power Monitoring Creat 1 downloadable PCAT document, instead of one per function DC Power Rates - Difference between usage and power capacity DC Power reading, reductions, cancellations and restorations

Brent Cbeyond asked if we are considering charging on a per use basis. Ben advised yes, we would monitor and charge on a use basis. The monitoring can be done on the BDFB boards on 61 amps or above, except in MN where it is 60 amps or above.

Bonnie - Eschelon asked is this will have any impact on pricing. Ben advised no as this is cost docket driven.

Brent asked if this change would include existing power? Ben advised yes, accounts will be converted over automattically.

Ben advised he will provide status at the June CMP Meeting. There were no further questions.

5/21/03 May CMP Meeting Minutes Cindy Macy – Qwest reviewed this CR for Ben Campbell. The CLECs requested to have an input meeting to discuss this CR in more detail and provide input to the process. Cindy will schedule an input meeting targeting the 2nd week in June.


Open Product/Process CR PC100103-1 Detail

 
Title: Grandparenting of Single Number Service in AZ
CR Number Current Status
Date
Area Impacted Products Impacted

PC100103-1 Completed
2/18/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Single Number Service will be grandparented in AZ effective 12/31/03. This is the only state remaining that has not been grandparented.

Expected Deliverable:

12/31/03


Status History

10/01/03 - CR Submitted

10/02/03 - CR Acknowledged

10/3/03 - Contacted originator to discuss CR. I will schedule an internal meeting to review the CR in more detail.

10/7/03 - Clarified status of CR.

10/14/03 - Held internal call to discuss CR and sent out notification for CLEC Ad Hoc call scheduled on 10-21

10/15/03 - Oct CMP meeting minutes will be posted to the project meeting section

10/21/03 - Held CLEC Input Meeting

11/14/03 - PROD.11.14.03.F.01056.GRANDPARENTSNS

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/17/03 - Dec CMP meeting minutes will be posted to the database

12/12/03 - PROD.12.12.03.F.01150.FNL_GrandparentSNS

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section


Project Meetings

February 18, 2004 CMP Meeting Janean Van Dusen – Qwest provided status. This CR was implemented December 31, 2003. This CR will move to Completed Status.

January 21, 2004 CMP Meeting Janean Van Dusen – Qwest advised this CR was implemented December 31, 2003. This CR will move to CLEC Test Status.

December 17, 2003 CMP Meeting Janean VanDusen – Qwest advised this CR has an implementation date of December 31, 2003. This CR will remain in Development status.

November 19, 2003 CMP Meeting Janean VanDusen – Qwest advised this CR has an implementation date of December 31, 2003. This CR will move to Development status.

CLEC Input Meeting PC100103-1 Grandparent Single Number Service in Arizona October 21, 2003

In attendance: Liz Balvin MCI Janean Van Dusen Qwest Qiana Davis Qwest Cindy Macy Qwest

Cindy Macy Qwest explained that this is the CLEC Input Meeting for PC100103-1 Grandparent Single Number Service in Arizona.

Janean Van Dusen – Qwest reviewed the CR and explained Single Number Service is an AIN platform based product that provides a single number to call for multiple business locations. For example, a business that has multiple locations but takes all their calls through a single number. Arizona is the only state that is currently offering this service. This product will not be offered after 12/31/03. If you have the service it can be converted, but it can not be ordered new.

Liz Balvin – MCI asked if there is a new service replacing this product? Janean advised not specifically; an existing business line service would be offered.

Janean advised there would be PCAT updates that are published.

Liz asked what investigation does Qwest do prior to deciding to grandfather a service? Janean advised Retail makes these decisions and Wholesale is following the Retail lead, but a variety of factors are looked at. Factors include volume, technology reasons, and state differences.

There were no further questions. Cindy Macy thanked the participants and ended the call.

October CMP Meeting 10-15-03: Janean VanDusen – Qwest presented this CR. This CR is Grandparenting Single Number Service in Arizona. This is the last state that offers this service. Implementation date is currently 12-31-03. A CLEC Input Meeting is scheduled for October 21. This CR will move to Presented Status.


Open Product/Process CR PC090203-1 Detail

 
Title: Define criteria for use of CFLAG/PIA field
CR Number Current Status
Date
Area Impacted Products Impacted

PC090203-1 Completed
6/16/2004
Provisioning INP, Centrex, LNP, Private Line, Resale, Unbundled Loop, UNE, Products ordered on LSR
Originator: Martain, Jill
Originator Company Name: Qwest Corporation
Owner: Martain, Jill
Director:
CR PM: Harlan, Cindy

Description Of Change

Per discussions held with the CLEC Community, Qwest is submitting this CR as a Level 4 Process Change to define the criteria when the CFLAG/PIA fields are most commonly used. The following list can be used as a starting point for discussions with the CLECs:

Change Flags (CFLAG)

The CFLAG is used to communicate changes Qwest made on the service order that are different from what was requested on the original LSR. These changes are a result of two different conditions:

1. Changes that occurred as a result of a verbal directive from you.

1. Changes due to processing requirements within Qwest.

When the CFLAG is marked, the Remarks section of the FOC contains text indicating any deviations from the original request. Examples of some of the uses of CFLAG in each of the preceding areas are as follows:

- Changes that occurred as a result of a verbal directive from you when no supplement is sent:

- On the DD, you request a Connecting Facility Assignment (CFA) slot change when the assigned slot is unavailable.

- On the DD, you called and requested a verbal DD change.

- You called and requested a verbal supplement as a result of a non-fatal error.

- You called and requested a verbal supplement because a SUP 1 (Cancel) or SUP 2 (Desired Due Date (DDD) change) cannot be submitted due to a system (either yours or Qwest's) outage or limitation.

- Changes that occurred as a result of the processing requirements within Qwest include the following:

- If special characters (i.e., a virgule "/" appears in specific fields such as the PON) that are not allowed in Qwest’s Service Order Processors (SOP) are included on the service request, they will be changed to dashes to allow the request to process.

- Whenever Qwest cannot use the DDD on the LSR as the DD. Examples include a DDD that did not meet standard interval requirements or the LSR requested an invalid DD such as a Sunday or Holiday.

- The Summary Billing Account Number (BAN) is incorrect on the LSR and Qwest provides the correct BAN information on the FOC.

- For LSRs with Requisition Type and Status of CB (Local Number Portability (LNP)) and BB (Unbundled Local Loop/LNP) that have the ported TN in the Account Number (AN) field instead of the main AN, Qwest will process the order (porting the requested TN) using the main AN and will provide the correct AN of the FOC.

- When the LSR is requesting a feature and an additional USOC/feature is also required in order to provision the service correctly, Qwest adds the appropriate USOC/feature on the service order. This change is only made if Qwest has not provided the ordering rules externally. As trends are identified, Qwest will either make process changes and/or update the PCAT, as appropriate.

- When the Coordinated Hot Cut (CHC) field equal "N" (or blank) and the Appointment Time (APPTIME) and Desired Frame Due Time (DFDT) fields are populated, Qwest will ignore the information in the APPTIME and DFDT fields because they are not required.

- If the LSR requests a dispatch, but dispatch is not required for provisioning and you have not requested the service be "tagged", Qwest will not dispatch a technician because it was not necessary.

- If during processing of a LSR Qwest determines that the TN entered on the LSR is not available, Qwest will provide a new TN.

- If the address entry is a minor deviation from Qwest PREMIS address data (e.g., LSR uses "suite" and PREMIS uses "unit"), Qwest will use the information in PREMIS.

- If you set the Manual Indicator (IND) to "Y" and service order affecting information in the Remarks field causes a mismatch in field-to-field comparison, Qwest will use the information in the Remarks field to process the order.

Expected Deliverable:

To create a mutually agreed upon list of reasons when the CFLAG/PIA field would be checked on the LSR and document that criteria in the Ordering PCAT located on the Qwest external web site.


Status History

09/02/03 - CR Submitted

09/04/03 - CR Acknowledged

9/8/03 - Contacted Jill Martain and held clarification call

9/17/03 - Sep CMP meeting notes will be posted to the database

9/18/03 - Sent Notification offering 3 options for CLEC Input Meeting

9/23/03 - Selected Oct 1 9:00 - 11:00 meeting time for CLEC Input Meeting - notification distributed.

10/1/03 - Held CLEC Input Meeting and agreed to schedule another Ad Hoc call the last week in October

10/13/03 - Sent notification for CLEC Ad Hoc meeting scheduled on October 30 from 10:00 - 11:00

10/15/03 - Oct CMP meeting minutes will be posted to the database

10/30/03 - CLEC Ad Hoc meeting held to review CFLAG/PIA matrix

11/6/03 - Received input from Eschelon on matrix

11/7/03 - Received input from MCI on matrix

11/19/03 - Nov CMP meeting minutes will be posted to the database

12/5/03 - Schedule CLEC ad hoc meeting to review CFLAG/PIA codes and reasons (12/15)

12/8/03 - CMPR.12.08.03.F.01149.CFLAG_PIA_MTG

12/15/03 - Held CLEC ad hoc meeting to review PIA matrix

1/2/04 - Notification distributed for next CLEC meeting on 1/9/03

1/9/03 - Held CLEC ad hoc meeting to review PIA matrix

1/21/03 - Jan CMP meeting minutes will be posted to the database

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

2/26/04 - Held CLEC ad hoc meeting

3/17/04 - March CMP meeting notes will be posted to the project meeting section

4/21/04 - April CMP meeting notes will be posted to the project meeting section

5/19/04 - May CMP Meeting notes will be posted to the project meeting section

6/16/04 - June CMP Meeting notes will be posted to the project meeting section


Project Meetings

June 16, 2004 CMP Meeting notes: Jill Martain – Qwest advised the PCAT documentation is completed and is effective May 24. Qwest would like to close this CR. The CLEC community agreed it is okay to move this CR to Completed Status.

May 19, 2004 CMP Meeting notes: Jill Martain – Qwest advised that the documentation is available for CFLAG/PIA effective with the 15.0 release on April 19. The PIA 14 process update is effective May 24. This documentation closed without comment. Liz Balvin – MCI said that she thought this was a known concept and was already in effect. Jill advised that Qwest could not remove the PIA 14 value without proper notification. We are currently going through the notification time frame. It is possible that until May 24 the PIA value of 14 could be used incorrectly. It is very unlikely that PIA 14 will be used prior to May 24. We were not able to remove this value with the 15.0 release and it will require a new CR and CLEC vote to have removed in IMA. This CR will remain in CLEC Test Status.

April 21, 2004 CMP Meeting notes: Jill Martain – Qwest provided status on this CR. Jill advised that the documentation for this CR went out as part of the 15.0 release documentation. There also were notices issued related to the jep process and Line Sharing. Liz Balvin – MCI asked what the difference is between a LSR level PIA and an order level PIA. Jill advised that it depends on the circumstances as to whether you would use an order or LSR level PIA. If it was related to an order number or circuit ID it would be at the order level. If the CLEC submits an LSR and it has five TNs associated to it, Qwest may send a PIA response associated to the LSR, or it could be associated to one of the orders. It depends on the circumstances. Liz asked how does the PIA value come back and link back to the order. Jill advised that for EDI the information is in the Disclosure Document and Developer Worksheets. The field LR19 is used on LSRs. The field 40A is used at the service order level. This CR will remain in CLEC Test Status.

March 17, 2004 CMP Meeting notes: The PCAT has been updated with the PIA values that we agreed to for the 13.0 and 14.0 versions of IMA. Another update is coming effective in April with the new values that will be available with the 15.0 release. We had another ad-hoc meeting regarding the process where voice and DSL is requested on the same LSR, where the data cannot be provisioned and we mutually came to agreement to change the process to use a jeopardy notice instead of the PIA value of 14. The PCAT updates are being sent to the documentation team and should be available for comment within the next couple of weeks. In addition, Jill added after the meeting that although we won't be using the PIA value of 14 from a process perspective that the CLECs would still see it in the disclosure documentation as it will require a system change to remove it. We would like to move this CR into CLEC Test Status.

PC090203-1 CFLAG/PIA Ad Hoc Meeting PIA14 February 26, 2004

In attendance: Linda Miles – Qwest Kim Isaacs – Eschelon Cindy Schwartze – Qwest Bonnie Johnson – Eschelon Crystal Soderlund – Qwest Jill Martain – Qwest Cindy Macy – Qwest

Cindy Macy – Qwest opened the call and reviewed the agenda. During this call Qwest will review the current process, as Qwest understands it, and gather input and concerns from the CLECs.

Cindy Schwartze – Qwest explained the current process was effective August 2003 with the IMA release. This process is for N and T 1 LSR for voice and Qwest DSL. When you are ordering DSL with voice, the address has to pass Loop Qual for flow through. If the address qualifies, then we would accept the LSR, and issue the Service Order to provision the request. If the address does not qualify, then the LSR for voice and Qwest DSL would be rejected upfront by IMA.

In the event the DSL line can’t be provisioned and the order issued is for DSL and voice, we then follow the Retail provisioning process. We go ahead and provision the voice, send an FOC with a CFLAG saying that the data portion can not be provisioned. Cindy Schwartze – Qwest explained the volume is very low, and that we only have knowledge of this occurring once.

Crystal Soderlund – Qwest reviewed the Line and Loop Splitting process. This process was put in place in June 2001. The UNE P request is submitted, if the LSRs have the same due date and the DSL is available, Qwest will issue a pending order change to the UNE-P service to add the DSL. If the data portion cannot be provisioned, Qwest would allow the voice LSR to get provisioned. The Line Splitting LSR would follow the Held Order process. Crystal did not remember seeing this occur in production. With 15.0 IMA Qwest is offering the process to provision the 2 requests on 1 LSR. The CLEC may need to issue another LSR to condition the line. Loop Splitting will mirror Line Splitting.

Bonnie said we are not talking about a situation when you order line conditioning. We are talking about when you can’t provision DSL. In this case it should follow the standard process when you order a feature and it is not available. Qwest should reject the order, as that is what is done when a feature is not available. If we can’t have the DSL then we don’t want the voice. We have no use for just the voice line. This is in conflict with the Qwest reject process. Bonnie advised that the CLECs want to receive a Jeopardy notification and it should identify if DSL can’t be provisioned at all or if it needs to be conditioned. Qwest considers DSL a feature in other areas. It should be treated as a feature.

Crystal Soderlund – Qwest thanked Bonnie for helping us understand the issues. Crystal explained when the LSR is received the centers process the order. At that time we don’t know if the facility is DSL compatable. Crystal asked for clarification that the CLEC’s are really asking for Qwest to notify the CLECs with a Jeopardy notice and give 4 hours to respond? Bonnie asked if the SDC does not check to see if DSL is available? Crystal advised no, it is assumed the CLEC has done that up front, before the LSR is sent in. Bonnie asked what point in time is it determined when the DSL is not available? Crystal advised that the downstream organization contacts the SDC to remove the DSL. Bonnie said that Qwest should jeopardy the order at that time.

Crystal said the ILECs should check to make sure the line can handle DSL and IMA also does a check. For example, if CLEC doesn’t loop qualify, then IMA should do a check right away and reject the order. This is why we don’t think this happens very much. Bonnie said if the line doesn’t qualify then we do not order the line. If it required line conditioning we do a separate order after the line goes in. So, why do we have a PIA value to accommodate this, if it doesn’t happen very often? Bonnie said it should be rejected.

Crystal advised that the reject reason isn’t always clear to the SDC, so she requested a PIA value to provide more details. Bonnie advised that the CLECs would like to be able to have a choice on whether to accept, reject or jeopardy the order. Otherwise, if Qwest just removes the data and installs the voice, then the CLEC would be liable for Non Recurring charges and 30-day billing in situations where they may have chosen otherwise to cancel the request. Her preference was to receive the jeopardy notice and then make the appropriate decision. Bonnie understands if we do follow the jeopardy process a sup or new LSR may be required and the standard interval would be followed.

Bonnie advised the CLEC community would prefer to have an option. They would like for Qwest to jeopardy the LSR and follow the current jeopardy process. The CLEC would have 4 hours to respond or the LSR would be cancelled. In this case there would not be a need for PIA 14. Bonnie advised she would check with the other CLECs to make sure this represents their needs. If there are concerns, Bonnie will send an email to Cindy Macy.

Cindy Macy advised that the team will meet internally to review the request and determine the impacts to this process. Qwest will provide status or schedule another meeting to discuss the results.

February 18, 2004 CMP Meeting Jill Martain – Qwest advised the PCAT was published and comments were addressed. This closed January 28, 2004, effective March 3, 2004. Subsequent FOC was addressed. There will be a CLEC meeting to discuss PIA 14 on February 26, 2004. Stephanie Prull – Eschelon was in the 15.0 walkthrough meeting yesterday and realized that there would be an Order Level PIA and an LSR Level PIA. Stephanie advised this was never discussed in any of the PIA meetings. Qwest was able to page Denise Martinez-Qwest to join the call. Denise and Jill explained this is the way PIA is being implemented, opposed to the content or meaning of the PIA value. Denise and Jill advised this would allow Qwest to be specific with the correct level of PIA. Some PIA values are related to a BAN so that would be at an LSR level, and some PIA values are related to a Due Date or TN change so that would be at an Order level. Stephanie advised she understand the functionality and she agrees that it makes sense to implement it this way, but she was not aware of how she missed the way this was going to be implemented. Her understanding is that there would be multiple values, but not multiple fields or segments. Bonnie Johnson – Eschelon asked if the multiple PIA values are at different levels for the same PIA reason? This relates to PO20 impacts. Denise Martinez – Qwest advised it is a means for us to apply the value most accurately. It would not increase the amount of other PIAs. Jill Martain – Qwest advised that you might have LSR level PIA and then PIA values on the orders that are created from the LSR. Stephanie Prull – Eschelon advised our vendor does not support this so we will not be able to implement. Connie Winston – Qwest advised this is the CR in 15.0 for ‘Multiple PIA Values’. Bonnie Johnson – Eschelon said we never discussed order versus LSR level. We were under the impression that PIA was PIA – no different between order and LSR levels. Connie Winston – Qwest asked if we can provide a comment on the draft Tech Specs and then we will provide a response the to comment. Stephanie Prull – Eschelon advised she already submitted it as a comment and that this would be fine to handle it this way, instead of holding an ad hoc meeting. This CR will stay in Development Status.

January 21, 2004 CMP Meeting Jill Martain – Qwest advised that we had an ad hoc meeting with the CLEC and agreed to send the matrix documentation out. We agreed to omit PIA 14 from the matrix. The documentation will be distributed in two phases. The first phase will identify the PIA value definitions that are effective today. The second phase will be the additional PIA values added with 15.0 on April 19. Jill explained that we discussed PIA 14 and this was referred to the Product team. A CR should be issued this month to take care of this. Blocking will be discussed tomorrow in the systems meeting. Bonnie Johnson – Eschelon advised that the problem is that Qwest requires CLECs to send in the end state, opposed to adds and deletes. This causes a recap, and recaps don’t appear on the PSON. Bonnie advised it wasn’t disclosed that there were going to be exceptions to the PSON. It is good that it is on the service order. The CLECs wanted to discuss tomorrow in the systems meeting whether the recap on all the listing information will also fix this problem.

Ad Hoc Meeting PC090203-1

In Attendance: Bonnie Johnson – Eschelon Phyliss Burt – ATT Jill Martain – Qwest Kim Isaacs – Eschelon Linda Harmon – Qwest Donna Osborne Miller – ATT Carla Pardee – ATT Liz Balvin – MCI Nancy Sanders – Comcast Ray Smith – Eschelon Cindy Macy – Qwest

Cindy Macy – Qwest opened the call and advised the team will be reviewing the CFLAG/PIA matrix and the updates that were made based on previous meetings with the CLECs.

Jill Martain – Qwest explained that because we have reviewed the matrix before, she would ask the CLECs if they have comments or questions on each item, opposed to reading each item. This way we will discuss only the items that the CLECs have questions about.

Discussion occurred on the following items / topics: Adding a mini definition section to help clarify terms (subsequent FOC) PIA 5 – subsequent FOC PIA 8 – update to identify this will be used in 13/14.0. PIA 11 – Jill clarified #11 and Bonnie’s comments. Jill advised she agrees with Bonnie’s comment as both of them are saying the same thing. Phyllis Burt – ATT asked how would the customer get a PIA 11. Jill advised if the same reserved TN# was used mutiple times an we have to reassign a new TN. Work is going on to improve this process. Phyllis also clarified Bonnie’s comment. PIA 14 – Jill explained she understands Bonnie’s concern about needing to document the process. Jill explained this is Qwest’s existing process. Bonnie advised she is open to the process of sending a jep notice and to complete the voice part, but she would like to discuss how this process should work. Jill asked if she can explain the issue to the Product team and have them take care of this issue, as she is not the process person for this process. Bonnie agreed that would be okay. Bonnie explained her concern is that Qwest is trying to create a process with a PIA, opposed to creating the process first and using a PIA as part of the process. Jill agreed to omit PIA 14 from the matrix initially. Jill will issue the notice and matrix to publish this information and omit PIA 14. Jill discussed the blocking question. Jill explained that it is recapped on the service order but it is not visable to the CLECs. Jill advised a CR could be opened to change this. Bonnie advised that we can discuss this at CMP (systems meeting).

Bonnie advised she appreciates Jill’s analysis of the PIA values and data. Bonnie still would prefer to have a more expanded PIA value list. Bonnie hopes that the use of PIA 4 decreases with this CR. Eschelon will continue to monitor the use of PIA. Liz Balvin – MCI agreed that we need to continue to review the information in remarks and create a new PIA value if necessary.

Bonnie asked if the new PIA values will be effective with 15.0. Jill advised yes.

Next Steps Publish documentation / matrix

December 17, 2003 CMP Meeting Jill Martain – Qwest advised that the team met and reviewed the PIA Matrix on December 15. Qwest agreed to make additional updates to the matrix. Liz Balvin – MCI verified that Qwest will clearly distinguish between LSR and Service Order activity and FOC and subsequent FOC in the document. Jill agreed those updates / clarifications would be made. Jill asked the CLECs if they would like to have another meeting or if the matrix is okay to be published. Liz Balvin – MCI and Bonnie Johnson – Eschelon advised they would like to have another meeting as they did request additional unique PIA values around Blocking. Jill advised she is working on the two issues that were brought up at the Ad Hoc Meeting (Blocking and PIA14 Data Portion not provisioned). The team will discuss these at the next meeting. Cindy Macy – Qwest agreed to schedule a meeting for January 5 or 9. Bonnie expressed her concern that the CLECs did request additional specific PIA values that were not included in the matrix. Jill explained that she has tried to include all the scenarios that were discussed and the concern with having too many PIA values is that it becomes unmanageable and the centers would not use all of the values. This CR will remain in Development Status.

December 15, 2003 Ad hoc meeting PC090203-1 CFLAG/PIA Ad Hoc meeting

In Attendance: Julie Pickar – US Link Kim Isaacs – Eschelon Ray Smith – Eschelon Stephanie Prull – Eschelon Carla Pardee – ATT Jill Martain – Qwest Cindy Macy – Qwest Colleen Sponseller – MCI Liz Balvin – MCI Bonnie Johnson – Eschelon

Jill Martain – Qwest advised she has updated the matrix based on investigations and previous meetings. Jill advised there is a large list of PIA values and it is very hard for Qwest to manage so many different values. As an example, we have combined some PIA 4 reasons into one code.

Bonnie Johnson – Eschelon asked about 20% of training issues identified in the matrix? Was the PIA field used inaccurately? Jill Martain – Qwest advised some were unclear selections and training will help. This is an example of how too many PIA values become hard to manage.

Liz Balvin – MCI asked about subsequent FOCs as there is no such notifier. Jill Martain – Qwest advised if there is something missing Qwest will send a jep after the FOC. If Qwest makes an error and there is nothing to correct than Qwest will send another FOC with the correct PIA information. This is done on a Qwest typo error. Steph Prull – Eschelon advised their systems don’t look at the second FOC. So any updates on second FOC are not updated. Jill explained this is not new, it has always been the process. The CLECs asked if this is in the PCATs. Jill advised CFLAG was created to accommodate these situations so that is the purpose of CFLAG. Jill advised PIA is an industry standard. The industry only has four values.

Bonnie Johnson – Eschelon asked about due date change by Qwest. Bonnie asked why can’t there be a different PIA value for each of these due date changes. Jill advised this created the possibility of error and the ‘reason change’ is the same. Jill is very concerned about the number of different values.

The team agreed the next steps are to make changes to the document and then meet again to review. Liz wanted to make sure the changes would specify when Qwest felt it was appropriate to make changes. Specifically, Liz requested Qwest to identify if it was a change made from the CLEC LSR to Service Order or whether it was a change made to correct an error identified on the FOC notification . Jill agreed those changes would be included.

November 19, 2003 CMP Meeting Jill Martain – Qwest advised that she received comments from the CLECs regarding the last matrix that was distributed. Jill is in the process of providing a response to those issues. In addition, as a result of those comments and internal discussions the list is growing and there is concern about the number of values Qwest could be requiring our centers to manually review and accurately select. Jill will take another look at the most commonly used reasons and the CLEC feedback and provide a final proposal to the CLEC community hopefully, within the next week.

Lastly, there was discussion around retrofitting the multiple values and additional PIA values into the 13.0 and 14.0 releases. Since it has not been the practice to retrofit new changes into earlier EDI versions, Qwest does not plan to pursue retrofitting new PIA functionality into earlier EDI versions. However, Qwest is still looking into options of adding any new PIA values into the 15.0 release.

CLEC Ad Hoc Meeting PC090203-1 CFLAG / PIA October 30, 2003

In attendance: Julie Pickar – US Link Liz Balvin – MCI Kim Isaccs – Eschelon Ray Smith – Eschelon Jill Martain – Qwest Jenn Arnold – US Link Jackie Debold – US Link Denise Martinez – Qwest Cindy Macy – Qwest

Cindy Macy – Qwest opened the call and explained we will review the matrix, make updates and determine next steps. Cindy confirmed that the users had copies of the matrix.

Jill Martain – Qwest reviewed the PIA numbers and reasons. Discussion took place on several of the PIA values and reasons. See below.

PIA 4/15 – MCI requested that Qwest validate that this is in the disclosure document and this may create an out of sync condition. Liz advised she would like the business rules to be clear in the disclosure document. If the centers are using PIA 15 they would also notify the process specialist so we can be sure we review and correct the reason that we are using PIA 15.

Address Validation –MCI advised that different address systems are used to validate different forms or requests. Please be specific on PIA 4 as to which address system is being checked.

Remarks field can cause a mismatch. The request was that Qwest would monitor PIA 4 and Other to improve the reason that is causing us to use PIA 4.

The CLECs advised they will need to review this matrix with their coworkers to gather input. Jill asked the CLECs to get back to Cindy Macy at cynthia.macy@qwest.com to confirm that the PIA reasons are acceptable. After that, Jill would pursue obtaining new PIA values.

Jill explained that to implement these changes there are process and documentation changes, system changes are needed to assign new PIA values, and the request to retrofit the 15.0 changes into 13/14.0 releases require an exception meeting. -

October 15, 2003 CMP meeting minutes Cindy Macy – Qwest provided status for Jill as she is on vacation this week. Cindy advised the CLECs met October 1, 2003 to review the current use of CFLAG/PIA. During the Ad Hoc meeting Jill explained the reasons we use each CFLAG/PIA and the team began to further define acceptable reasons for ongoing use of CFLAG/PIA. Bonnie Johnson advised she made a request at the Long Term PID meeting that the CFLAG/PIA changes planned for Release 15.0 also be incorporated into 13, 14 and 15.0. Cindy advised she will discuss this with Jill when she returns from vacation. Stephanie Prull – McLeod advised they are on 13.0 and it seems like the use of CFLAG/PIA in the system is different with 13.0. Every time a conversion order that goes through autoflow, a PIA 12 (cus code change) is assigned. Stephanie advised McLeod is aware of the cus code changing so a PIA of 12 is not needed. This CR will move to Development Status.

CLEC Ad Hoc Meeting PC090203-1 CFLAG/PIA October 1, 2003

In attendance: Julie Pickar US Link James McClusky Accenture Liz Balvin MCI Steve Trana Launch Now Phyllis Burt ATT Mike Zulevic Covad Jill Martain Qwest Bonnie Johnson Eschelon Kim Issacs Eschelon Jennifer Arnold US Link Stephanie Prull McLeod

Cindy Macy – Qwest opened the call and advised the purpose of this call is to review the current use of CFLAG/PIA and to determine new uses for CFLAG/PIA. Bonnie Johnson-Eschelon advised her goal is to create a finite list for use of PIA. Liz Balvin-MCI advised at a minimum the CLECs have to know how the field is being used. Jill Martain-Qwest advised she has concerns over loosing the ability to use PIA in an interim process or work around. Liz Balvin-MCI asked why wouldn’t Qwest reject the LSR instead of use PIA. Jill advised sometimes the better option is to use PIA, opposed to missing a due date. Liz said she understands as long as the CLEC is contacted and advised about the use of PIA.

Jill explained CFLAG will be eliminated with 13.0 and PIA will be used 13.0 going forward. EDI 11 and 12 it is still valid. CFLAG and PIA terms are interchangeable.

Bonnie advised CFLAG/PIA has direct impacts to PO20. If CFLAG is used it excluded the order from PO20. The use of CFLAG/PIA has to be limited. Bonnie wants to have an exhaustive list. If something is broken, then Qwest needs to fix the problem opposed to using CFLAG.

Phyllis Burt ATT asked to explain the use of PIA 4 value of ‘other’. Bonnie explained this allows the CLEC to enter the LSR so it can be rejected. Qwest uses this field to notify CLECs of changes made to the order. It helps the order be processed.

Jill Martain – Qwest went through the CR and discussed the current uses for PIA. Bonnie requested that we go through the information and ask that the CLECs have time to go back to their organizations to gather input, before we make final decisions on the use of PIA. The team agreed this was okay and that we would have another meeting to discuss our findings. Jill agreed she would create a matrix that identifies the reason to use PIA and identify which PIA would be used in each situation. This matrix should be available to review at the next CLEC Ad Hoc Meeting.

The group discussed the PIA changes as a result of Verbal direction from CLECs, Changes due to processing requirements within Qwest, Changes for ‘other’ reasons and System limitations.

Jill agreed to look at creating multiple PIAs for system limitations such as: DD change per CLEC DD changes per Qwest Cancel per CLEC Cancel per Qwest Verbal DD changes Delayed order condition causing DD change The CLECs expressed their concerns over system limitation PIAs. If Qwest talks to the CLECs and gets their approval it is more acceptable.

Liz Balvin advised MCI does not subscribe to PSONs so the process can not be to notify via a PSON. Jill agreed to look at the Dispatch field and PIA 11 to make sure we understand how this is being used.

Bonnie Johnson advised the address field is another area where we may want multiple PIA. Qwest should identify minor deviations on address data. Jill explained we need to create a manageable list of PIAs. Bonnie and Liz advised they would like to know what specifically changed on the address so they can fix it next time. Jill offered to create a PIA for address and include the specifics in the remarks. Liz was okay with this.

Non fatal errors were discussed and agreed that these should be talked about further to identify situations when it would be used.

PIA 15 Requested USOC was discussed. Jill advised PIA 15 is only used when the feature PCAT does not tell us what to do.

Bonnie asked if PIA 3 could go away with 15.0. Jill agreed to check on.

PIA 13 BAN change – optional field. What happens is we don’t populate it? Jill advised if BAN is populated with the incorrect BAN Qwest uses PIA to fix it. If BAN is blank we don’t use PIA.

PIA 14 should be further defined. Jill will updated the matrix to further define PIA 14. PIA 8 goes away with Release 15.

The CLECs will take PIA and review with their organizations. Jill will update the PIA matrix and we will discuss it during our next meeting.

Bonnie sent in the following information as a result of CLEC discussions:

The CLECs committed to hold a meeting and review 3 issues on this CR. 1. Verbal sups on non fatal errors: * The CLECs collectively agree with Qwest (Char Mahs communicated Qwest will be sending a level 3 notice soon) that verbal sups should be allowed only when a sup is not possible due to a system or some other unique limitation. 2. PIA #15 value to be implemented in 14.0 * The CLEC community has a concern about this value. * How will the process for blocking and hunting impact this. Qwest process states that the USOC will no longer be required. Will every LSR with blocking requested (requiring a USOC) and hunting have a #15 value? * If so the CLECs would like a new value to apply to USOCs not required on the LSR and one for USOCs that are required. More discussion is needed on this. 3. Can we eliminate the #4 "other" field? * The CLECs would like to develop the detailed value list and discuss at that point, however, the general consensus is that if we can create a total list we may be able to accomplish that.

Some additional points: * CLECs want to ensure that the PIA field is not replacing any processes. The PIA field is merely Qwest defining the LSR/Service order mismatch and CLECs will not be required to use the PIA field will not communicate any data currently relayed to CLECs via other methods. For example, Qwest marks PIA value 12 because the customer code has changed. Qwest communicates the new customer code in remarks on the FOC. The CLEC will not need to now obtain the new customer code from the remarks field when they currently obtain the information through other means. * Will Qwest submit a special request to make all changes requested in this process in 15.0 and update 13.0 and 14.0 at that time?

September 17, 2003 CMP Meeting Jill Martain presented this CR and asked if Qwest could hold a CLEC Input meeting on 9-29-03 from 9 – 11:00 a.m. Liz Balvin-MCI advised Monday’s do not work for her. Cindy agreed to send a notification to offer 3 meeting options and then reschedule.

MEETING MINUTES

Request to change Level 2 Notification PROS.07.28.03.F.01137.ProvisioningV27 to a Level 4 Change Request

August 20, 2003 CLEC-Qwest Conference Call Meeting Time: 1:00 – 2:00 PM MDT

Purpose The purpose of the ad-hoc meeting was to determine how to move forward with implementing changes notified in PROS.07.28.03.F.01137.ProvisioningV27 and how to manage the CLEC requests that came in asking that this change be managed as a Level 4 CR.

Attendees Carla Pardee-ATT, Donna Osborne-Miller- ATT, Sharon Van Meter – AT&T, Mike Zulevic-Covad, Kim Isaacs-Eschelon, Bonnie Johnson-Eschelon, Bill Littler-Integra, Stephanie Prull-McLeod, Liz Balvin-MCI, Jennifer Arnold-US Link, Susan Lorence-Qwest, Jim Maher-Qwest, Jill Martain-Qwest, Judy Schultz-Qwest, Kit Thomte-Qwest

Meeting Minutes

Jim Maher-Qwest opened the meeting and explained that Qwest had issued a Level 2 notification PROS.07.28.03.F.01137.ProvisioningV27 updating information associated with CFLAG processes. The notification had been issued as Level 2 because it was an update that included documentation concerning existing processes/products not previously documented. Jim explained that comments had been received from Cbeyond, Covad, Eschelon and MCI requesting that the CLECs be involved in developing the procedures and that this could be accomplished by handling this as a Level 4 CR.

Jill Martain-Qwest proposed that the Level 2 change be implemented based on a request from the CLECs that this process should be more clearly documented. Martain stated that having the processes documented through the Level 2 notification might be more advantageous to all involved with this process, and that a Level 4 CMP CR could be opened to modify the process.

Bonnie Johnson-Eschelon stated that Eschelon had an issue with posting the information provided in the Level 2 notification because Eschelon did not think the information represented what was happening with CFLAG. She further explained that Eschelon had raised concerns regarding CFLAG for some time and that they had concerns with PID impacts. Mike Zulevic-Covad and Liz Balvin-MCI also stated they were uncomfortable with the Level 2 language being implemented and agreed that this should be managed as a CR. Jill Martain stated that the language provided in the Level 2 notification could be the starting point for the CR. Bonnie Johnson agreed with that approach. Martain agreed to proceed with th CR, and stated there may be a short term and longer term CR associated with this work.

The meeting adjourned.


Open Product/Process CR PC090303-1 Detail

 
Title: Grandparenting of specific LAN Switching Service (LSS) USOCs
CR Number Current Status
Date
Area Impacted Products Impacted

PC090303-1 Completed
12/17/2003
Provisioning Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

The following list of USOCs will be grandparented as of 11/10/2003 and relocated in the FCC tariff to section 8.10:

LAN Links

Ethernet, 10 Mbps, without protection, per LAN Link termination

- Monthly D5LCX

- 12 Months DLUC1

- 36 Months DLUC3

- 60 Months DLUC5

Ethernet, 10 Mbps, with protection, per LAN Link termination

- Monthly D5LCP

- 12 Months DPUC1

- 36 Months DPUC3

- 60 Months DPUC5

Fast Ethernet, 45 Mbps, without protection, per LAN Link termination

- Monthly D5L1X

- 12 Months DLU11

- 36 Months DLU13

- 60 Months DLU15

Fast Ethernet, 45 Mbps, with protection, per LAN Link termination

- Monthly D5L1P

- 12 Months DPU11

- 36 Months DPU13

- 60 Months DPU15

Fast Ethernet, 100 Mbps, without protection, per LAN Link termination

- Monthly D5L2X

- 12 Months DLU21

- 36 Months DLU23

- 60 Months DLU25

Fast Ethernet, 100 Mbps, with protection, per LAN Link termination

- Monthly D5L2P

- 12 Months DPU21

- 36 Months DPU23

- 60 Months DPU25

Expected Deliverable:

Grandparenting will be effective 11/10/2003


Status History

09/03/03 - CR Submitted

09/04/03 - CR Acknowledged

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/26/03 - Held Ad Hoc input meeting

10/08/03 - Qwest sent Product Notice, PROD.10.08.03.F.03576.GrandparentingLAN, proposed effective date 11/11/03

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/27/03 - Qwest sent final notification, PROD.10.27.03.F.03904.FNL_GrandparentingLAN, effective date 11/11/03

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

12/17/03 December CMP Meeting Janean Van Dusen said that the PCAT changes were effective 11/11/03 and suggested this CR be moved to Completed status. This CR will move to Completed status.

11/19/03 November CMP Meeting Janean Van Dusen with Qwest said that the changes were effective 11/11/03 and would like to move this CR to CLEC test. This CR will be moved to CLEC Test.

10/15/03 October CMP Meeting Janean Van Dusen with Qwest said there was an ad hoc meeting held on 9/26 for input to this CR. Qwest is on track for implementation 11/11/03. This CR will be moved to Development Status.

Ad Hoc Meeting Minutes PC090303-1 "Grandparenting of specific LAN Switching Service (LSS) USOCs" CMP Product & Process September 26, 2003 1-877-572-8687, Conference ID 3393947# 8:00 a.m. - 8:30 a.m. Mountain Time

PURPOSE

At the September CMP Meeting, participants agreed to hold a conference call to discuss Qwest submitted CR PC090303-1, Grandparenting of specific LAN Switching Service (LSS) USOCs. The following is the write-up of the discussion.

List of Attendees: Donna Osborne-Miller - AT&T Bonnie Johnson - Eschelon Kim Isaacs - Eschelon Janean Van Dusen - Qwest Connie Davidson - Qwest Linda Sanchez-Steinke - Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees. Linda Sanchez-Steinke with Qwest explained that the purpose of the meeting was to discuss CR PC090303-1.

Janean reviewed the CR and said that specific LAN Switching Service (LSS) USOCs will be grandparented on 11/10/03. These USOCs will not be available to order as new service but will be available for conversions. Connie Davidson with Qwest said the FCC filing will be effective on 11/11/03 because the FCC is unable to take the Filing on a Monday.

Qwest asked if there were any additional questions. No questions were asked.

09/17/03 September CMP Meeting Janean Van Dusen with Qwest presented this CR. There will be an ad hoc meeting on 9/26 for input to this CR. Liz Balvin with MCI asked if there tariffs will be filed with new rates. Janean answered yes. This CR will move to Presented Status.


Open Product/Process CR PC070203-1 Detail

 
Title: Process for Requesting Clarification to a Systems Document
CR Number Current Status
Date
Area Impacted Products Impacted

PC070203-1 Completed
10/15/2003
Systems Documentation
Originator: Winston, Connie
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

This CR would formalize the process for requesting clarification to existing systems documentation (for example, disclosure or Users Guides) outside of the documents documentation review cycle.

Expected Deliverable:

Process for requesting clarifications to the Diclosure Document:

1. During each CLEC's EDI Implementation or Migration to a new release, Qwest and each CLEC maintain a question log of all questions asked and the associated answers. If a CLEC feels that a documenation clarification is needed, that clarification should be requested on the Question Log.

2. Upon receipt of the requested clarification, the CLEC's EDI Implementation contact will evaluate the requested clarification against the criteria listed below.

3. Occasionally, Qwest will need to alter the wording of the documentation clarification requested by the CLEC. If this is necessary, the revised wording will be sent to the CLEC for review.

4. If the clarification meets the criteria, the change will be made in the next release's draft Technical Specification (Disclosure) publication.

5. If the clarification does not meet the criteria and the CLEC still wants to pursue the change, the CLEC will be instructed to use the Technical Escalation Process or the CMP Escalation/Dispute Resolution Process.

Criteria:

The documentation clarification can be made through this process if:

1. Does not require a systems change.

2. Documents an existing, undocumented, field-level requirement.

3. Clarifies an existing, field-level requirement.

4. Does not document the manner in in a which a legacy system functions.

5. Is not a system defect.

6. Is not a policy or process.

Process for updates to Other Systems Documentation:

All other updates to Systems Documentation should be submitted using the CLEC Documentation Change Request form.


Status History

07/02/03 - CR Submitted

07/02/03 - CR Acknowledged

07/15/03 - Held Clarification Meeting

07/16/03 - July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

08/08/03 - PROS.08.08.03.F.01153.ExDocReq

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/16/03 - Qwest sent PROS.09.16.03.F.01195.ExDocReqProc, CMP - External Documentation Request Process effective 9/17/03

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section

10/15/03 - October CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

10/15/03 October CMP Meeting Linda Sanchez-Steinke provided an update on this CR. Qwest issued the final notification and it was effective 9/17/03. Liz Balvin with MCI said that she had not used the system documentation clarification process and asked if it was the same as process. Linda said it was similar and has a different form for systems documentation. It was agree that this CR will be moved to Completed status.

09/17/03 September CMP Meeting Connie Winston provided an update on this CR. There is a systems form now available to request changes to system documentation. Notification was provided on 9/16/03 and is effective 9/17/03. The EDI teams will continue to handle requests as they have previously. This CR will be moved to CLEC Test status.

08/20/03 August CMP Meeting Connie Winston was not able to be present when this CR was discussed and provided the following update for the meeting minutes. The external url developed for the External Documentation Request Process will be used for systems documentation requests. Comments can also be provided via EDI through the EDI comment log. Currently we are looking at the external documentation form to determine if changes will needed to support systems documentation requests. This CR will be moved to Development status.

07/16/03 July CMP Meeting Connie Winston with Qwest presented this CR. Connie explained that this CR was opened because there is a need for CLECs to have a path to give feedback to Qwest on User Guide documentation. An external url will be implemented in mid-August and CLECs can request changes be made to systems documentation. When the requests are received, Qwest will determine if it meets the criteria listed in the CR. If the change to documentation requires a system change, then a systems CR would need to be opened.

Carla Pardee with AT&T said this CR is a good idea. Liz Balvin asked if there would still be EDI development teams and Connie answered yes the EDI development teams will continue.

CLEC Change Request Clarification Meeting

9:30 a.m. (MDT) / Tuesday, July 15, 2003

1-877-554-8688 1930099# PC070203-1 Process for Requesting Clarification to a Systems Document

Attendees Name/Company: Connie Winston, Qwest Kyle Kirves, Qwest Linda Sanchez-Steinke, Qwest

Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

Review Requested (Description of) Change Qwest’s CR formalizes the process to request clarification to existing systems documentation, when the document is outside the documentation review cycle. Clarification can be made through this process if the documentation fits in the following criteria: 1. Does not require a systems change. 2. Documents an existing, undocumented, field-level requirement. 3. Clarifies an existing, field-level requirement. 4. Does not document the manner in which a legacy system functions. 5. Is not a system defect 6. Is not a policy or process. Process for updates to Other Systems Documentation: All other updates to Systems Documentation should be submitted using the CLEC Documentation Change Request form.

Confirm Areas & Products Impacted The area of this Change Request impacts ability to provide feedback on systems documentation.

Confirm Right Personnel Involved Qwest confirmed the correct personnel were on the call to resolve the CR.

Identify/Confirm CLEC’s Expectation Provide formal process for clarification on systems documentation when document is outside documentation review cycle.

Identify any Dependent Systems Change Requests No systems change requests.

Establish Action Plan (Resolution Time Frame) Qwest will present this CR at the July CMP meeting with an update at the August CMP..


CenturyLink Response

September 9, 2003

DRAFT RESPONSE For Review by CLEC Community and Discussion at the September 2003 CMP Meeting

SUBJECT: Qwest’s Change Request - PC070203-1 "Process for Requesting Clarification to a Systems Document"

For EDI Documentation changes, CLECs should use the established process of identifying changes to the EDI Documentation and providing the suggested changes to their Qwest Project Manager during CLEC Implementation. The suggested changes will be captured on their Question and Answer log, will be reviewed and a response provided. The CLEC will be advised of the wording of the documentation change. This is the most effective way for CLECs to get their requested change made to their specifications. For process and non-EDI documentation changes, CLECs should use the following URL for submitting changes: http://www.qwest.com/wholesale/customerService/exdocreq.html). From this URL, CLECs can choose one of two forms: 1) For process documentation (e.g., LSOG, PCAT, et. al.), CLECs should select the process documentation form, 2) For non-EDI systems documentation (e.g., CEMR, DLIS, etc.), CLECs should use the systems documentation form. The process documentation form is currently available; the systems form is currently in design. When that form is available, Qwest will notify the CLECs of its availability.

Sincerely,

Connie Winston Director, Information Technology Qwest


Open Product/Process CR PC070203-2 Detail

 
Title: Introduce new form for MTE access.
CR Number Current Status
Date
Area Impacted Products Impacted

PC070203-2 Completed
11/19/2003
Ordering, Provisioning Loop - NID
Originator: Mohr, Bob
Originator Company Name: Qwest Corporation
Owner: Mohr, Bob
Director:
CR PM: Harlan, Cindy

Description Of Change

A new order form entitled “CLEC Access at Qwest Protector Field Application” is being introduced to allow CLECs to access the MTE NID’s protector field and have their cable spliced into the protector stub. A description of this activity is found in SGAT 9.5.2.5. This option is currently available; however, due to limited interest in this offering, no form was previously developed.

In addition, resulting from regulatory activity in the states of AZ, OR, and WA., CLECs may now directly access the protector field by removing Qwest’s cable pair from a pin on the protector field and placing a CLEC pair on that same pin instead of having their cable spliced into the protector stub. The “CLEC Access at Qwest Protector Field Application” has also been created to include this function.

Expected Deliverable:

New form linked to the NID PCAT


Status History

7/2/03: CR Received

7/2/03: CR Acknowledged

7/3/03: Left Bob Mohr message will discuss on 77/03

7/7/03: Discussed CR with Bob Mohr (clarification meeting)

7/16/03: July CMP meeting minutes will be posted to the database

7/22/03: CLEC Input meeting scheduled for 8/6/03 and notification distributed

8/6/03: Held CLEC input meeting

8/20/03 - August CMP meeting - see meeting notes

9/17/03 - Sep CMP meeting notes will be posted to the database

10/15/03- Oct CMP meeting minutes will beposted to the database

11/19/03 - Nov CMP meeting minutes will be posted to the database


Project Meetings

11/19/03 CMP Meeting Cindy Macy – Qwest reported for Bob Mohr that this process was implemented on October 9. Qwest asked to close this CR and the CLECs agreed. This status of this CR will change to Completed.

10/15/03 CMP Meeting Cindy Macy – Qwest advised the documentation was released on 9-25-03. No comments have been received and 10-9-03 was the implementation date. This CR will move to CLEC Test status.

9/17/03 CMP Meeting Bob Mohr – Qwest advised the PCAT is available on the review site. No comments were received. The document will be published as operational 10/9/03.

8/20/03 CMP Meeting Bob Mohr-Qwest reported the documentation is planned for release to the CLECs on August 25 with an effective date of October 9. This is a Level 4 update.

CLEC Input Meeting PC070203-2 Introduce new form for MTE (Multi tenant environment) access Wednesday August 6, 2003 10:00 – 11:00 a.m. MST 1-877-572-8687 3393947#

In attendance: Bob Mohr – Qwest Russ Urevig – Qwest Liz Balvin – MCI Shirley tallman – Qwest Bonnie Johnson – Eschelon Stephanie Prull - McLeod Dave Hahn – Qwest Cindy Macy – Qwest

Bob reviewed the CR and explained he is presenting an appliication form to allow a CLEC to access the Qwest protector equipment. This is a UNE. The protector field protects equipment from power surges.

Bonnie Johnson – Eschelon asked why would a CLEC access to this field? Bob replied there is no demand for this product currently. It is a UNE and Qwest is offering access to it. The CLEC would want access to our protector if there are space limitations or the CLEC does not provide their own protection. A CLEC can order access to the protector via this new form. Bob also explained you can access this protection at a pair by pair basis in certain states.

The CLECs asked how do we tell what kind of protection is in place? Qwest replied the technician has to check visually to determine. Shirley – Qwest advised being able to access the protector would also give access to the splice point. Protection is required and the CLEC can either provide it or use Qwest protection. This form would be used to access the protector.

Cindy Macy – Qwest reviewed the next steps. Bob Mohr will provide status on the release of the process / documentation at the August CMP meeting.

7/16/03 CMP Monthly Meeting minutes: Bob Mohr – Qwest reviewed the CR with the CLEC Community. Bob explained there is a new form that is being introduced to allow CLECs to access the MTE (multi tenant environment) NID’s protector field. Cindy Macy-Qwest advised we have planned a CLEC input meeting for August 6, 2003. A notification will be distributed providing the details for the call.


Open Product/Process CR PC081903-1 Detail

 
Title: Change in Resale, UNE and Interconnection Services Service Interval Guide (SIG)
CR Number Current Status
Date
Area Impacted Products Impacted

PC081903-1 Withdrawn
9/17/2003
LIS / Interconnect
Originator: Stulen, Sandy
Originator Company Name: Qwest Corporation
Owner: Stulen, Sandy
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Adding 21-30 NPA-NXXs with a 40 business day interval and adding 31-40 NPA-NXXs with a 45 business day interval. This is due to recent ASOG revisions which expanded quantities of NPA-NXXs and CICs on ASRs.

Expected Deliverable:

Proposed Implementation Date 10-31-03


Status History

08/19/03 - CR Submitted

08/19/03 - CR Acknowledged

08/19/03 - Clarification Meeting

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

09/17/03 - September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

09/17/03 - September CMP Meeting Sandy Stulen with Qwest gave an update on this CR. Qwest would like to withdraw this CR and doesn’t plan to change the SIG. Bonnie Johnson with Eschelon asked if Qwest can provide the intervals requested at last month’s meeting. Sandy Stulen answered she doesn’t have the data. This CR will be moved to Withdrawn Status.

08/20/03 - August CMP Meeting Sandy Stulen with Qwest presented changes to the LIS interconnection intervals to add additional quantities of NPA-NXXs to more nearly resemble feature group because of the increase in CIC codes shown on the TQ with the release of ASOG 27. The quantity of NPA-NXX codes had changed on a previous ASOG. Qwest is now proposing to make changes to the LIS, Wireless and Feature Group SIGs with the release of ASOG 27. The change is specifying an interval, which was previously ICB. Bonnie Johnson with Eschelon asked that Qwest analyze and provide to the CLECs the average number of business days orders with ICB due dates were completed, as this could have a negative impact on CLECs. There will be an Ad Hoc meeting scheduled to gather input to this CR.


Open Product/Process CR PC072103-1 Detail

 
Title: DLR Option Change
CR Number Current Status
Date
Area Impacted Products Impacted

PC072103-1 Withdrawn
8/20/2003
Provisioning LIS / Interconnect
Originator: Money, Bryan
Originator Company Name: Qwest Corporation
Owner: McBride, Kathy
Director:
CR PM: Sanchez-Steinke, Linda

Description Of Change

Plan Description:

Qwest will eliminate manual paper DLR’s

Customers will have 4 options for receiving DLRs from Qwest.

1. Customer printer equipped with a modem.

2. Customer PC

3. FAX

4. CEMR/DSOS

Note: Email is not an option due to security concerns.

Requirements:

1. Customer must have a DRC code. (A DRC can be obtained from Telcordia at a cost of approximately $400 or from Qwest at no charge).

2. A customer may have more than one DRC to accommodate multiple locations.

3. A DRC will be required on all orders. If a DRC is not provided a default of CTS will be populated (CTS is the DRC code for CEMR/DSOS).

Expected Deliverable:

Qwest will no longer mail paper DLRs. 4 options for DLRs are available see above. Will improve DLR receipt cycle time, eliminate manual processing and handling, reduce cost.


Status History

08/20/03 - August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

08/20/03 August CMP Meeting Kathy McBride with Qwest said that Qwest would like to withdraw the CR because, when implemented, will be a level 3 notification Bonnie Johnson with Eschelon asked for more information about the change request. Kathy said that the CR was initiated by Service Management and that today DLRs are sometimes manually handled in the ASR world. Mechanized options would include Fax, CEMR and customer printer equipped with a modem. Bonnie said that Gary Veik with Qwest had contacted Eschelon about getting DLRs from a Qwest system and wasn’t sure which system. Kathy said it might have been CEMR. This CR will be moved to Withdrawn status.


Open Product/Process CR PC112103-1EX Detail

 
Title: CMP December Meeting to be a combined one day Process and Product and Systems Meeting
CR Number Current Status
Date
Area Impacted Products Impacted

PC112103-1EX Completed
12/11/2003
CMP Meeting
Originator: Andreen, Doug
Originator Company Name: Qwest Corporation
Owner: Andreen, Doug
Director:
CR PM: Andreen, Doug

Description Of Change

Qwest will host a combined Product/Process and Systems CMP meeting for December on December 17. Product and Process will be held from 8 a.m. to 11:30 a.m. MST. The systems meeting will follow at 1:00 p.m. to 4:30 p.m. Meeting location will remain the same. All dates for distribution of materials for these meetings will remain the same: Distribution Package Posting dates of 12/12 for Product/Process and 12/15 for Systems. CR submission cut off dates will also remain the same at 12/3 for Product/Process and 11/27 for Systems.


Status History

11/21/03 - CR Submitted

11/21/03 - CR Acknowledged

11/24/03 - Qwest initiated notification CMPR.11.25.03.F.01099.ExceptionNoticeVoteReq

12/09-03 - Held vote on combined December meeting

12/10/03 - Qwest initiated Notification CMPR.12.10.03.F.01168.Dec_CMP_Mtg_Combined Vote disposition

12/11/03 - Status changed to closed.


Project Meetings

Meeting Minutes CR PC112103-1EX CMP Combined December Meeting December 9, 2003

Purpose The purpose of the vote is whether to allow an exception to the CMP document to allow a combined Product/Process and Systems CMP meeting to be held on December 17, 2003.

Attendees

Sue Lamb, Digital Easy Chair Liz Balvin, MCI John Berard, Covad

Meeting Minutes

Doug Andreen - Qwest reviewed the following:

A vote of ‘Yes’ will allow for a combined Product/Process and Systems CMP Meeting to be held on December 17,2003

A vote of ‘No’ will NOT allow for a combined Product/Process and Systems CMP Meeting to be held on December 17,2003

There were no questions associated with the Yes and No vote.

Doug Andreen - Qwest stated that Quorum of 6 Carriers was achieved.

Doug Andreen - Qwest stated that an emailed ‘Yes’ vote was received from Qwest, AT&T and Eschelon.

Doug Andreen - Qwest stated that based on the results of the vote, PC112103-1EX was granted an exception to hold a combined CMP meeting on the 17th of December.

There were no additional comments or questions.


Open Product/Process CR PC120303-1CM Detail

 
Title: CMP Document Language Changes to Section 12.4 and 12.5
CR Number Current Status
Date
Area Impacted Products Impacted

PC120303-1CM Completed
2/18/2004
Change to CMP Document
Originator: Winston, Connie
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Andreen, Doug

Description Of Change

Request CMP Document Language Change to Section 12.4 and Section 12.5. Please see attached redline of the Change Management Process Document.


Status History

12/03/03 - CR Submitted

12/04/03 - CR Acknowledged

12/18/03 - Qwest Initiated Notification CMPR.12.18.03.F.01200.CMP_Vote_on_Document

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Presented

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Development

1/27/04 - Qwest initiated notification CMPR.01.27.04.F.01298.CMP_Process_Vote_Disp

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

2/18/04 - Status changed to completed

3/4/04 - Qwest initiated Notification PROS.03.04.04.F.01435.CMP_Doc_Changes

4/5/04 - Qwest initiated Notification PROS.04.02.04.F.01530.FNL_CMP_Doc_Changes


Project Meetings

2/18/04 CMP Meeting This CR was approved at the January CMP meeting. It will carry an April 19 implementation. Status will move to complete.

- 1/21/04 CMP January Meeting The voting began with Doug Andreen advising that to achieve a Quorum 6 CLECs were needed to participate in this vote. Quorum was achieved. He also indicated that McLeod and Qwest had voted in advance of the meeting. Peggy Esquibel-Reed indicated no other email votes had been received. Doug Andreen, Qwest reviewed the CR allowing for a language change to Sections 12.4 and 12.5 of the CMP document Michelle Sprague, McLeod had voted yes via email Judy Schultz, Qwest had voted yes via email Liz Balvin stated that MCI votes yes Carla Pardee stated that AT&T votes yes Bonnie Johnson stated that Eschelon votes yes Mike Zulevic stated that Covad votes yes In this vote, conducted in accordance with Sections 16.4 and 17.0, the participants voted to approve a CMP language change to Sections 12.4 and 12.5 of the CMP document by a vote of 6 “Yes” votes, 0 "No" vote, and 0 "Abstain" votes. Voting was concluded.

-- 12/17/03 December CMP Meeting Kit Thomte, Qwest presented the language change to the CMP document. It was agreed that this CR would be voted on next month during the CMP Product Process Meeting.


Open Product/Process CR PC120303-2CM Detail

 
Title: Changes to the CMP Document Section 12.7
CR Number Current Status
Date
Area Impacted Products Impacted

PC120303-2CM Completed
2/18/2004
Change to CMP Document
Originator: Winston, Connie
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Andreen, Doug

Description Of Change

Proposed changes to Section 12.7 Notification Intervals in the CMP Document. Please see attached redline of the Change Management Process Document.


Status History

12/03/03 - CR Submitted

12/04/03 - CR Acknowledged

12/18/03 - Qwest Initiated Notification CMPR.12.18.03.F.01200.CMP_Vote_on_Document

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Presented

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Development

1/27/04 - Qwest initiated notice CMPR.01.27.04.F.01298.CMP_Process_Vote_Disp

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

2/18/04 - Status changed to completed

3/4/04 - Qwest initiated Notification PROS.03.04.04.F.01435.CMP_Doc_Changes

4/5/04 - Qwest initiated Notification PROS.04.02.04.F.01530.FNL_CMP_Doc_Changes


Project Meetings

2/18/04 CMP Meeting This CR was approved at the January CMP meeting. It will carry an April 19 implementation. Status will move to complete.

- 1/21/04 January CMP Meeting The voting began with Doug Andreen advising that to achieve Quorum 6 CLECs were needed to participate in this vote. Quorum was achieved. He also indicated that McLeod and Qwest had voted in advance of the meeting. Peggy Esquibel-Reed indicated no other email votes had been received. Doug Andreen, Qwest reviewed the CR allowing for a language change to Sections 12.7 of the CMP document Michelle Sprague, McLeod had voted yes via email Judy Schultz, Qwest had voted yes via email Liz Balvin stated that MCI votes yes Carla Pardee stated that AT&T votes yes Bonnie Johnson stated that Eschelon votes yes Mike Zulevic stated that Covad votes yes In this vote, conducted in accordance with Sections 16.4 and 17.0, the participants voted to approve a CMP language change to Sections 12.7 of the CMP document by a vote of 6 “Yes” votes, 0 "No" vote, and 0 "Abstain" votes. Voting was concluded.

- 12/17/03 December CMP Meeting Kit Thomte, Qwest presented the language change to the CMP document. It was agreed that this CR would be voted on next month during the CMP Product Process Meeting.


Open Product/Process CR PC120303-3 Detail

 
Title: Grandparent Interstate SHNS and SST USOCs
CR Number Current Status
Date
Area Impacted Products Impacted

PC120303-3 Completed
4/21/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Excel spreadsheet of 1302 Interstate and SHNS USOCs being grandparented on 3/1/04. There are three types of elements being grandparented; ports, shelves and port to port connecting agreements.

-Ports with month to month rates are not being affected. We are grandparenting 1,2,3 and 5 year rated ports.

-Shelves are being replaced by a fully loaded node. The currently tariffed nodes will become these fully loaded nodes once shelves are grandfathered.

-If a customer would have ordered a port to port connecting agreement, once that is grandparented, they will be able to order the currently tariffed COCC (central office connecting channel).

Expected Deliverable: 03/01/2004


Status History

12/03/03 CR Submitted

12/05/03 CR Acknowledged

12/8/03 Contacted Janean VanDusen

12/10/03 - Clarified CR

12/17/03 - Dec CMP meeting notes will be posted to the database

1/21/03 - Jan CMP meeting minutes will be posted to the database

1/16/04 - PROD.01.16.04.F.01240.ResaleSST_SHNS level 4 implementation date March 1, 2004

2/13/04 - PROD.02.12.04.F.01354.FNL_ResaleSST_SHNS

2/18/04 -Feb CMP Meeting notes will be posted to the project meeting section

3/5/04 - PROD.03.05.04.F.01451.Rev.FNL_Resale SST_SHNS

3/17/04 - March CMP meeting notes will be posted to the project meeting section

3/12/04 - PROD.03.12.04.F.01478.RevisedFNL_ResaleSST_SHNS Revised final notice

3/24/04 - Revised final notice changing dates to April 8, 2004. PROD.03.25.04.F.01515.RevFNL_ResaleSST_SHNS

4/21/04 - April CMP meeting notes will be posted to the project meeting section


Project Meetings

April 21, 2004 CMP Meeting notes: Janean VanDusen – Qwest advised this CR was effective April 8. This CR will move to Completed Status.

March 17, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised that this CR will be implemented April 6. There were delays in the tariff filing. This CR will remain in CLEC Test Status.

February 18, 2004 CMP Meeting notes: Janean Van Dusen – Qwest provided status. The final notification went out February 13. There are two effective dates with this CR. One is March 12 and the other is March 24. This CR will move to CLEC Test Status.

January 21, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised this CR is effective March 1, 2004. The USOC list is on the customer notification web site. It was noticed on January 16, 2004. This CR will move to Development Status.

December 17, 2003 CMP Meeting notes: Janean Van Dusen – Qwest reported that this is a new CR that is grandfathering USOCs related to these services. The intent is to streamline the number of USOCs associated to this product. There is a spreadsheet with 1302 USOCs on it. This spreadsheet is too large to include as part of the CR but it will be sent out with the Notification. This CR will move to Presented status.


Open Product/Process CR PC103103-1 Detail

 
Title: Buried service wire/placing/Conduit/Technician interface with end user
CR Number Current Status
Date
Area Impacted Products Impacted

PC103103-1 Completed
4/21/2004
Odering, Provisioning Unbundled Loop, UNE Loop, UNE-P, EEL (UNE-C)
Originator: Tallman, Shirley
Originator Company Name: Qwest Corporation
Owner: Tallman, Shirley
Director:
CR PM: Andreen, Doug

Description Of Change

Field Technician Process changes for Service drop wire and/or conduit Placement:

1. Field Tech is dispatched out to perform installation on a Wholesale order.

2. Field Tech determines that an initial or additional drop is required.

Residence premises: Placing is required for initial or additional drop.

Business premises: The property owner may be required to place conduit with pull-string for initial or additional drop placement.

3.

Non-design (ie, UNE-P)- Qwest Field Tech will contact CLEC to let them know about a jeopardy condition for placing of drop and/or conduit. The notification to CLEC is either direct to the CLEC contact or through a Voice Message. If the CLEC’s Voice Message is full, the Field Tech will make one more attempt to contact CLEC. The Field Tech will then place the order into jeopardy status.

Internal process Authorization of charges will need to be approved through a SUP on the LSR. Appropriate USOC's will be applied to the service order after SUP is received (Placement of conduit and the cost associated with it is the responsibility of the property owner.)

If conduit placement is required, Field Tech will advise property owner where the conduit should start and end.

Design (ie, Unbundled)- Qwest Field Tech makes a call to the QCCC or DSC and the QCCC or DSC will contact the CLEC for jeopardy condition for placing of drop and/or conduit and order will be placed into jeopardy status. Authorization of charges will need to be approved through a SUP on the LSR. Appropriate USOC will be applied to the service order after SUP is received (Placement of conduit and the cost associated with it is the responsibility of the property owner.)

If conduit placement is required, Field Tech will advise property owner where the conduit should start and end.

(If the QCCC or DSC cannot reach the CLEC, they will leave a VM.)

4. Property owner or end-user will contact CLEC to advise conduit placement is complete and order can be re-scheduled.

5. CLEC updates Qwest through LSR notification.

6. BSW group receives notification and schedules contractor to place Service Wire.

7. Field Technician is then dispatched out to complete installation.

Expected Deliverable:

January 1, 2004


Status History

10/31/03 - CR Submitted

10/31/03 - CR Acknowledged

11/11/03 Held Clarification Call

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status changed to Presented

11/19/03 - Qwest issued CLEC Input Meeting Notification CMPR.11.20.03.F.01085.CLECInputMeeting

12/04/03 - Held ad-hoc CLEC imput call

12/11/03 - Sent Minutes for CLEC input meeting

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Development

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status will remain in Devleopment

1/30/04: Qwest initiated notification PROS.01.30.04.F.01311.Mtce_&_Rpr_Overview V25.0

2/19/04: Qwest initiated notification PROS.02.19.04.F.01387.FNL_Prov_Overview_V34

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to Test

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

04/21/04 April CMP meeting Shirley Tallman, Qwest asked that this CR be moved to completed since all the work has been performed. The CR will be moved to Completed.

03/17/04 March CMP Meeting Shirley Tallman, Qwest reported that the PCAT was effective 3/5. The CR will move to CLEC Test status.

- 2/18/04 CMP Meeting Shirley Tallman, Qwest said the comment cycle completed with no comments being received. The PCAT will be published and operational on March 5. The CR will stay in Development status.

1/21/04 CMP Meeting Shirley Tallman, Qwest said the PCAT language has been developed and will be on line for CLEC comments by the end of the month. Lydell Peterson, Qwest asked if the escalation process would change. Shirley said no, that it would continue to flow through the delayed order desk. The CR will stay in Development.

12/17/03 December CMP Meeting Jamal Boudhaouia, Qwest provided an update to this CR that Qwest is moving forward on the PCAT language to establish the process for when initial or additional drops are needed to complete an order. This CR was moved to Development.

- Ad Hoc Meeting Minutes PC103103-1 Buried service wire/placing/Conduit/Technician interface with end user CMP Product & Process December 4, 2003 1-877-521-8688, Conference ID 1456160 10:00 a.m. 11:00 a.m. Mountain Time

PURPOSE

At the November CMP Meeting, participants agreed to hold a conference call to discuss Qwest initiated CR PC103103-1. The following is the write-up of the discussion.

List of Attendees: Bonnie Johnson, Eschelon Carla Pardee, AT&T Liz Balvin, MCI Patrick Hennesey, Eschelon Todd Miller, Eschelon Kim Isaacs, Eschelon Ann Atchison, AT&T Steve Kast, Qwest Cathy Augustson, Qwest Shirley Tallman, Qwest Allen Braeggar, Qwest Eric Yohe, Qwest Doug Andreen, Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Doug Andreen with Qwest explained that the purpose of the meeting was to discuss Qwest initiated CR PC103103-1.

Shirley Tallman, Qwest explained the purpose of the CR is to establish a process for the Qwest on site technician and the CLECs concerning a situation where the technician finds that either an additional drop wire or conduit needs to be run. Shirley than described the proposed process. She pointed out that while Qwest does not usually talk to the CLEC customer that in the case where the building owner/manager and the customer are one in the same that Qwest would talk to them in their capacity as the building owner/manager.

Bonnie Johnson, Echelon questioned if this was a new or existing process.

Shirley said it is a little of both. The purpose was to clarify the process for both the Qwest technician and the CLECs.

Todd Miller, Eschelon added that he felt some of this was existing but that this process clarifies some unknowns. Bonnie stated that her concerns is the benefit of supplying the building manager/customer with the information in the sense that they will want the CLEC to fix the problem. Therefore she wanted to make sure there was a method for the CLEC to get the information.

Shirley stated that at the same time the technician is giving the building manager/customer the information it would also be called to the QCCC for entry into the database. She suggested that we add a narrative of what the situation is after the notation that the order will be put in jeopardy status.

Bonnie asked if this could be built into process.

Shirley answered yes.

Bonnie further questioned if there could be information on how to contact the technician in case additional information was needed.

A discussion ensued on how this could best be done. Patrick Hennesey, Eschelon suggested the request go through the Service Manager. Steve Kast, Qwest suggested that there is an existing group in Cheyenne that handles jeopardy orders and that this might be the logical place to go for information.

Shirley agreed to investigate what would be the best way.

Doug asked if the intent is to have a CLEC contact that is a consistent place to go for additional information.

Bonnie agreed and added that there be a CLEC facing document that outlines the procedure.

Doug pointed out that a PCAT would be issued covering this process and that this document would be available for CLEC review.

Shirley mentioned that the PCAT might be delayed from the expected January 1 due date.

Bonnie pointed out that it is difficult for the CLECs to know what is going on if Qwest implements a process without the PCAT being issued.

Shirley asked if she wanted the process to not go into effect until the PCAT is finalized.

Bonnie said yes and Liz Balvin, MCI and Carla Pardee, AT&T concurred.

Doug said he would ensure that the CLECs were kept apprised of the PCAT status.

There were no further comments and the meeting was concluded.

-- 11/19/03 Nov. CMP Meeting Shirley Tallman Qwest presented the CR, which details the process for field technicians to follow when the technician finds that an initial or additional drop is required or that conduit is required. She stated that the intent is to document the process so that technicians are clear on what to do. Shirley also pointed out that she wanted the CLECs to be clear that this change involves the technician discussing with the property owner what the situation is and what needs to be done. The technician would also do this if the CLEC customer is the property owner. Anticipated effective date is January 1. Bonnie Johnson Eschelon asked if this was a new process or a modification to an existing process. Shirley replied that it is a bit of both and the intention is to get clarity around the process. Bonnie asked if there would be an input meeting or comment cycle. Kim Isaacs pointed out that this needs to be in the PCAT. It was agreed that both a comment cycle and input meeting will be utilized. Doug Andreen Qwest said the CLEC Input meeting is tentatively set for December 4. This CR will move to Presented status.


Open Product/Process CR PC103103-2 Detail

 
Title: Binding Post information
CR Number Current Status
Date
Area Impacted Products Impacted

PC103103-2 Completed
4/21/2004
Maintenance/Repair UNE Loop, EEL (UNE-C)
Originator: Tallman, Shirley
Originator Company Name: Qwest Corporation
Owner: Tallman, Shirley
Director:
CR PM: Andreen, Doug

Description Of Change

Qwest will provide dmarc Binding Post information for Unbundled Loop and EEL Products on CLEC orders through the Repair Department upon request, when information is available. If BP information is not available, the existing process for tagging the dmarc will apply.

Information on dmarc BP on non-design orders is not retained in any database and is not available.

Expected Deliverables:

January 1, 2004


Status History

10/31/03 - Submitted

10/31/03 - Acknowledged

11/18/03 - Held clarification call

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status changed to Presented

11/20/03 - Qwest issued Clec Input Meeting Notification CMPR.11.20.03.F.01086.CLECInputMtgBindingPost

11/24/03 - Qwest issued CLEC Input Meeting Time Change Notification CMPR.11.24.03.F.01095.TimeChangeCLECInputMtg

12/04/03 - Held ad-hoc CLEC input call

12/11/03 - Issued minutes from ad hoc call

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Development

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status will remain in Development

1/30/04: Qwest initiated notification PROS.01.30.04.F.01310.Prov_Overview_V34

2/19/04: Qwest initiated notification PROS.02.19.04.F.01388.FNL_Mtce_&_Rpr_Ver25

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 - Status changed to Test

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

04/21/04 CMP meeting Shirley Tallman, Qwest asked this CR to be moved to closed since all the work has been performed. Bonnie Johnson, Qwest asked about repair technicians being able to give out information on binding post for non-design orders. Shirley said that it was being covered through internal documentation that the technicians should provide this information. Kit Thomte, Qwest stated that Bonnie’s issue is if that documentation could be included in the PCAT. Bonnie added that she needed a CLEC facing document to support the policy. Kit said Mark Coyne’s team would be the appropriate team to check with to see how this can be handled. This CR will move to completed.

-- 03/17/04 March CMP Meeting Shirley Tallman, Qwest reported that the PCAT was effective 3/5. The CR will move to CLEC Test status.

- 2/18/04 CMP Meeting Shirley Tallman, Qwest said the comment cycle completed with no comments being received. The PCAT will be published and operational on March 5. The CR will stay in Development status.

- 1/21/04 CMP Meeting Shirley Tallman, Qwest stated that the PCAT language has been developed and will be on line for CLEC comments by the end of the month. Bonnie wanted to be sure that her comments about what an RSB representative had said about not giving out binding post information was about the situation and not about the employee. Kit Thomte, Qwest assured her that was understood. It was agreed that Doug Andreen will open a global action item concerning how CLECs will obtain Binding Post (demarc) information on non-design orders since this process only addresses design orders. The CR will stay in Development status.

- 12/17/03 December CMP Meeting Jamal Boudhaouia, Qwest stated that the Qwest is moving forward on PCAT language to provide information for Binding Post. Bonnie Johnson, Eschelon questioned the status on the question of CLECs seeing proprietary information in CEMR. She stated that two or three days after the Clarification call Eschelon called Qwest for Binding Post information and was told that the information could not be given out. Bonnie said she had stated on the Clarification call that she was afraid that Qwest would discontinue a process without proper notice to the CLECs. Judy Schultz, Qwest stated that a memo had been issued to the effect that proper notice must be given before process changes can be implemented. Jamal stated he would take on the issue of CEMR and what is proprietary. Bonnie stated that Qwest has a major compliance problem with tagging and the Qwest is obligated to provide last point of termination and that Qwest needs to correct the tagging problem or provide the information. She said the result is the Eschelon customer’s service is delayed and both companies have to dispatch to the premise. John Berard, Covad said there is a process being implemented at SBC for a CLEC tech to send tone on a line and determine the demarc. The CR was moved to Design.

-- Ad Hoc Meeting Minutes PC103103-2 Binding Post Information CMP Product & Process December 4, 2003 1-877-521-8688, Conference ID 1456160 3:00 p.m. 4:00 p.m. Mountain Time

PURPOSE

At the November CMP meeting, participants agreed to hold a conference call to discuss Qwest initiated CR PC103103-2. The following is the write-up of the discussion.

List of Attendees:

Jeff Bellin, Eschelon Bonnie Johnson, Eschelon Rhonda Knutson, Eschelon Allen Braeggar, Qwest Cathy Augustson, Qwest Shirley Tallman, Qwest Eric Yohe, Qwest Pat Finley, Qwest Don Deland, Qwest

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Doug Andreen with Qwest explained that the purpose of the meeting was to discuss Qwest initiated CR PC103103-2.

Shirley Tallman, Qwest explained the purpose of the CR: Qwest will provide dmarc Binding Post information for Unbundled Loop and EEL Products on CLEC orders through the Repair Department upon request, when information is available. If BP information is not available, the existing process for tagging the dmarc will apply. Information on dmarc BP on non-design orders is not retained in any database and is not available.

Bonnie Johnson, Eschelon asked if that meant Qwest would no longer tag.

Shirley responded no that normal processes for tagging still apply. This is primarily for when there is not a truck roll.

Bonnie said that on non-design orders she was surprised to hear that the information was not available.

Shirley responded that terminal information like at multi-tenant buildings is actual terminal information and not binding post at the dmarc.

Bonnie said Eschelon seems to be successful with data in CEMR and wondered on new orders if this process would prevent the CLECs from doing what they have done all along?

Shirley answered it would not as this is not designed to replace any existing process.

Bonnie asked if in the PCAT it would state that the information is not available?

Shirley said no, it would state that Qwest would provide the information it has if available.

Rhonda, Eschelon said that if an order is completed on non-design that Eschelon asks for binding post or F2 information. It may not be the last point but is close.

Shirley stated that Qwest should not be providing F2 information since this is in our network.

Rhonda stated that she was aware that cable and pair information should not be available but that F2 information was ok.

Jeff, Eschelon pointed out that on record 651-466-0492 in CEMR he could see binding post 272.

Shirley agreed to check out exactly what CLECs are seeing in CEMR.

Rhonda said that sometimes binding post and F2 are used interchangeably and she wondered if this could be causing the problem.

Bonnie stated that this information is critical especially when dealing with customer who has not paid their bill.

Shirley stated that Qwest should never be providing terminal binding post information but rather just binding post.

Bonnie stated that this would cause more dispatches for tagging.

Rhonda wondered how the information would show up. Will it say dmarc?

Shirley said at this point she was not sure.

Cathy Augustson, Qwest added when tech calls in an order complete that the tech provides the information at that time.

Rhonda asked if the last point of dmarc is where Qwest terminates the line.

Don Deland, Qwest said could be RJ11 or a 66 block.

Rhonda asked if F2 is where Qwest takes ownership.

Don said that it is jumpered from the F2 to a dmarc box or jack where the CLEC takes ownership.

Bonnie had two questions, first, is it called something else on a non-design and why doesn’t Qwest keep a record of it, and second isn’t Qwest obligated to provide information on where the dmarc is and where the CLEC takes ownership?

Shirley stated that the dmarc is not always our block that it can be the building owners.

Rhonda asked if beyond this point is the CLECs.

Don said usually the jumper is tagged to where the alternate provider takes over.

Bonnie asked if there would be a PCAT update and comment cycle.

Doug answered that there would be however the original date for the PCAT of January 1 would be delayed.

Doug asked Bonnie if her main concern is that these processes not supercede or replace anything in place today.

Bonnie said that was correct

Shirley added that this would not supercede or replace anything existing.

Bonnie said she would check if other CLECs were interested in this CR.

It was agreed there might be a need for another input meeting after the CMP meeting.

There was no disagreement with the design part of this CR, making the goal to not hold up design implementation while resolving issues on the non-design side.

- 11/19/03 Nov. CMP Meeting Shirley Tallman Qwest presented the CR for providing dmarc Binding Post information for Unbundled Loop and EEL Products on CLEC orders through the Qwest Repair Department upon request. She pointed out that this information on non-design orders is not available. Anticipated implementation is January 1. Bonnie Johnson Eschelon ask if the information was available through LMOS? Shirley responded that dmarc information is available but binding post is not. Bonnie questioned if the issue is a compliance issue since it is the existing process for the technician to tag at the dmarc. Shirley pointed out that there are times when a Qwest technician is not dispatched. Doug stated that a CLEC Input Meeting is tentatively set for December 4. This CR will move to Presented status.


Open Product/Process CR PC102703-1 Detail

 
Title: Grandparent usocs BAUTB, BAMTB and BAMHB in NE
CR Number Current Status
Date
Area Impacted Products Impacted

PC102703-1 Completed
2/18/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Andreen, Doug

Description Of Change

Grandparent usocs BAUTB, BAMTB and BAMHB measured/ message service in NE.

Expected Deliverable:

12/30/03


Status History

10/27/03 - CR Submitted

10/27/03 - CR Acknowledged

11/06/03 Held Clarification Call

11/14/03 - Qwest issued Process Notification PROS.11.14.03.F.01067.GrandparentMeasMessagRate, proposed effective date 12/30/03

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status changed to presented

12/8/03 - Qwest issued Process Notification PROS.12.08.03.F.01128.FNL_GrandpaMeasMessagRate

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Development

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Test

2/18/04 - Status changed to Completed

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

2/18/04 CMP Meeting Janean Van Dusen, Qwest stated that this CR was implemented December 30 and requested the CR be closed. The CR will move to Completed status.

-- 1/21/04 January CMP Meeting Janean Van Dusen, Qwest stated that this CR was implemented December 30. The CR will move to Test status.

- 12/17/03 December CMP Meeting Janean Van Dusen gave an update saying that on 11/15 the notification was issued for CLEC comments, none were received and that a final notification was issued on December 8 calling for an effective date of December 30. The CR was moved to development.

- 11/19/03 Nov. CMP Meeting Janean Van Dusen Qwest presented this CR to grandparent usocs BAUTB, BAMTB and BAMHB in Nebraska effective December 30. She also proposed using a comment cycle because of the holidays instead of a CLEC Input Meeting. Doug Andreen Qwest read the language in the CMP document section 5.4.5.1 that makes this an alternative. A comment cycle was approved. Liz Balvin MCI asked if grandparented USOCs are being replaced that this be noted on the CR. Janean said that could be done. Kit Thomte Qwest asked if a comment cycle could be used on all grandparent CRs. The CLECs agreed with this. Bonnie Johnson Eschelon asked if there could still be an option. Kit answered yes. This CR will move to Presented status.


Open Product/Process CR PC111003-1 Detail

 
Title: Reserved TN Procedure
CR Number Current Status
Date
Area Impacted Products Impacted

PC111003-1 Completed
5/19/2004
PreOrdering, Ordering, Provisioning, Billing Centrex, Resale POTS, UNE-P, any TN based product is impacted including resold ISDN, DID and Retail
Originator: Pent, Anne
Originator Company Name: Qwest Corporation
Owner: Dimmitt, Jan
Director:
CR PM: Andreen, Doug

Description Of Change

Implement procedure to either activate or cancel TNs reserved for 180 days or more to comply with December 2000 FCC Mandate.


Status History

11/10/03: CR Received

11/11/03: CR Acknowledged

11/18/03: Held Clarification meeting

11/18/03: Status changed to clarification

11/19/03: Qwest initiated notification CMPR.12.19.03.F.01201.Mtg_On_Reserve_TN_Process

12/17/03 -December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

12/17/03 - Status changed to Presented

01/12/04 - Held CLEC Input Call

01/15/04 - Sent CLEC Input Minutes

1/21/04 - January CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/21/04 - Status changed to Development

2/18/04 -February CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/17/04 -March CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

3/25/04 - Qwest generated notification PROS.03.29.04.F.01511.ResTelNumInvestigationV1

3/29/04 - Qwest generated notification PROS.03.29.04.F.01511.ResTelNumInvestigationV1

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

4/27/04 - Qwest generated final notice PROS.04.27.04.F.01598.FNL_TN_Invest_V1

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

5/19/04 CMP Meeting Jan Dimmitt, Qwest stated that the procedure is complete and published and requested that the CR be closed. The CR will be moved to Completed status.

- 4/21/04 April CMP Meeting Jan Dimmitt, Qwest stated that one comment was received during the comment cycle from MCI and the comment was included as a clarifying note in the front of the document. This CR will move to Test.

- 03/17/04 March CMP Meeting Jan Dimmitt, Qwest reported that the final draft for the PCAT has been completed. The comment cycle will begin on 3/25 and end on 4/13. Target for posting to the web is 5/13. The CR will remain in Development status.

- 2/18/04 CMP Meeting Jan Dimmitt said she is currently working on the PCAT. No line ranges have been encountered that require contacting the CLECs. The CR will remain in Development.

-- 1/21/04 CMP Meeting Jan Dimmitt said there was a CLEC Input meeting held January 12 and that the purpose of the CR is to establish a procedure where CLECs are notified when a line range has been reserved for over 180 days. She also said she is still looking into if a TN is part of a common block is it considered reserved or activated. Bonnie Johnson, Eschelon asked about the re-reserve policy. Jan said this is strictly a courtesy with no additional fees. A CLEC can continue to reserve, cancel the reservation, activate the line range, or re-reserve only a portion of the original. The CR will be moved to Development status.

CLEC Input Meeting 9:00 a.m. (MDT) / Monday January 12, 2004 1-877-521-8688 1456160 PC 111003-1-Reserve TN Procedure Attendees

Carla Pardee, AT&T Phyllis Burt, AT&T Liz Balvin, MCI Kim Isaacs, Eschelon Stephanie Prull, Eschelon James McCluskey, Accenture Cheryl Peterson, AT&T Anne Robberson, Qwest Jan Dimmitt, Qwest Doug Andreen, Qwest

Meeting Agenda: 1.0 Introduction of Attendees Introduction of participants on the conference call was made and the purpose of the call discussed.

2.0 Review Requested (Description of) Change

Doug Andreen, Qwest read the CR description: Implement a procedure to either activate or cancel TNs reserved for 180 days or more to comply with December 2000 FCC Mandate.

Jan Dimmitt, Qwest explained this process is not applicable to Resale Pre-Order TN Reservations through IMA and is applicable to numbers or number ranges that the CLEC has reserved and is paying a monthly fee to hold. This process is also not applicable to the 30 day reservations done through IMA. She said that Qwest gets a report of all reservations of over 150 days that have not been activated. They are compared with CNUM and the billing system for a match and to see if there are pending orders. The question is if the CLECs would like a courtesy call to inform them that they have a number or range of numbers that have been reserved for some time.

Kim Isaacs, Eschelon asked what happens after the courtesy call. Jan answered that the CLEC can either activate, continue to hold or cancel.

Kim then asked if the number is on the common block CSR is it activated or reserved. Jan said she would have to find out.

Liz Balvin, MCI wanted to verify that it is the CLECs choice of what to do with the reservation after the courtesy call.

Jan said yes and that some of these may take some research on the CLEC side. Qwest will continue to hold the number until advised by the CLEC what to do.

Anne Robberson, Qwest added that this is more of an effort to ensure the CLECs get what they want. The re-reserve policy still needs to be worked out.

Liz asked if Qwest was willing to hold another 180 days and Anne said yes. Anne then summarized that the process is to notify the CLECs of the choices they have.

Stephanie Prull, Eschelon asked if the non recurring charge would be applicable on re-reserves. Jan said she would have to check.

Cheryl Peterson, AT&T asked if only a portion of the original reservation could be re-reserved. Jan answered yes but it is now a verbal commitment. However, an email could verify the PON or service order. (The following was added after the meeting for further clarification: Qwest can initiate a service order without an LSR using PONS for specific order function. PON for cancel: CANRESRVTN180, PON for line range activation: ACTRESRVTN180, PON for cancel of portion of block and re-reserve portion of block: RERESRVTN180.)

Cheryl then said she needed more information on how the process works today and what now happens at the 150th day. Anne said the entire process is out in the LSOG and this is simply an addition.

Kim asked what the escalation process would look like iF something goes wrong. Jan said normal escalation procedures would apply.

Anne added that the preliminary investigation is a manual process.

Jan also added that the billing at the current time just continues on after 180 days without notifying the CLECs.

No other CLEC input was offered. There will be an update given in the January CMP meeting.

3.0 Confirm Areas & Products Impacted UNE-P, Centrex (not resale Centrex), any TN product is impacted including resold ISDN, DID, and Retail POTS

4.0 Confirm Right Personnel Involved Correct personnel were involved in the meeting.

- 12/17/03 December CMP Meeting Jan Dimmitt presented this CR which asks if the CLECs would like to be notified when a TN or range of TNs have been reserved for longer than 180 days. The CR was moved to Presented status.


Open Product/Process CR PC110303-2 Detail

 
Title: New Collocation Product Development Louvered Pedestal Collocation
CR Number Current Status
Date
Area Impacted Products Impacted

PC110303-2 Withdrawn
11/19/2003
Collocation, Remote Collocation
Originator: Campbell, Ben
Originator Company Name: Qwest Corporation
Owner: Campbell, Ben
Director:
CR PM: Andreen, Doug

Description Of Change

Qwest will be introducing a new type of remote collocation called Louvered Pedestal Collocation. This product will allow a CLEC to place equipment in a Qwest Louvered Pedestal for the purpose of connecting to unbundled network elements. This product will have an amendment specific to this product offering and rates specific to this product offering.

Expected Deliverable:

PCAT update, Product Pricing, Amendment Language, Technical Publication update. Proposed implementation is Jan. 2004.


Status History

11/03/03 - CR Submitted

11/04/03 - CR Acknowledged

11/05/03 - Status changed to pending withdrawal

11/19/03 - November CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

11/19/03 - Status Changed to Withdrawn


Project Meetings

11/19/03 Nov. CMP Meeting Ben Campbell Qwest asked that this CR be withdrawn because it is a modification to an existing product. He said that Louvered Pedestal Collocation had been discussed and a Network Notification had been issued in August. This is a follow up making modifications to the existing product. The intent is to make this a Level 3 change with continued CLEC joint planning. Steve Nelson Qwest pointed out that this modification will carry the same pricing, same procedures and same billing. He further pointed out that the Network disclosure meeting has been held. Liz Balvin MCI asked why proceed with a withdrawal and Steve answered that the intent is to reissue as a Level 3. Steve added that this is a change in architecture. It was agreed that the CR would move to Withdrawn status.


Open Product/Process CR PC072204-1 Detail

 
Title: Clarification of wording for CLEC to CLEC Connections
CR Number Current Status
Date
Area Impacted Products Impacted

PC072204-1 Withdrawn
2/15/2006
Provisioning Collocation, CLEC to CLEC Connection PCAT
Originator: Nelson, Steve
Originator Company Name: Qwest Corporation
Owner: Nelson, Steve
Director:
CR PM: Andreen, Doug

Description Of Change

Clarification of wording of documents relating to CLEC to CLEC Connections. Qwest believes CLEC to CLEC Cross Connect product is offered on a common ICDF frame only and CLEC has responsibility to design and regenerate. CLEC Community believes previous CR committed Qwest to design and regenerate.

Expected Deliverable:

CLEC facing meetings with Qwest will explore and hopefully reach agreement on this issue.


Status History

7-22-04: CR Received

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/27/04 - Qwest initiated notice CMPR.08.27.04.F.02007.Ad-hoc_Meetings

9/2/04 - Qwest initiated notice CMPR.09.02.04.F.02029.CLEC/CLEC_Connect_Agenda

9/16/04 - Qwest initiated notice CMPR.09.16.04.F.02056.Cancld_Ad-hoc_Meetings

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

1/31/06 - Status changed to Pending Withdrawal

2/15/06 - Discussed at the February Prod/Proc CMP Meeting

2/15/06 - Status changed to Withdrawn


Project Meetings

2/15/06 Product Process CMP Meeting

Jill Martain-Qwest stated that this CR had been in Deferred status for awhile and stated that Qwest would like to withdraw the CR. This CR moves to Withdrawal status.

9/16/04 CMP Meeting Minutes Mark Nickell reported that an ad-hoc call was held and it was mutually agreed to suspend CMP meetings until the current dispute resolution activities conclude in Colorado. Covad and Eschelon agreed. Bonnie Johnson added that the people involved in the call would not be able to do anything outside of the dispute resolution process and this is the reason to cease the calls. The CR will move to Deferred Status.

- Ad Hoc Meeting Minutes PC072204-1 Clarification of wording CLEC to CLEC Connections CMP Product & Process September 9, 2004 1-877-521-8688, Conference ID 1456160# 12:30 a.m. 2:00 a.m. Mountain Time

PURPOSE

The purpose of this ad-hoc call was to provide background on the CR and to set the stage for future meetings.

List of Attendees: John Berard Covad Jen Arnold U S Link Bonnie Johnson Eschelon Karen Clauson, Eschelon Paul Hansen, Eschelon Emily Baird, POP Telecom Mona Glover, DSET Paul Garneau, Sovereign Telecommunications Tommy Thompson, Qwest Communications Cindy Kalakis, Qwest Communications Evelyn Montez, Qwest Communications Jamal Boudhaouia, Qwest Communications Mike Norman, Qwest Communications Steve Nelson, Qwest Communications Doug Andreen, Qwest Communications

MEETING MINUTES

The meeting began with Qwest making introductions and welcoming all attendees.

Steve Nelson summarized meeting norms by saying please allow only one conversation at a time, turn off cell phones and pagers, speak to be understood, and if you have trouble being heard press the # key a couple of times to get his attention. Steve said this is the first of three meetings and is designed to provide background information on the CR that will be helpful in the meetings to follow. He also said comments are welcome and that Qwest would take action items as we proceed.

Steve went through the current level 4 CR (sent as an attachment to the agenda) reading the title and description. There were no questions. Steve further explained that this was originally submitted as a level 2 change, however the CLEC community thought it should be a level 4.

Jamal Boudhaouia gave the history of the Eschelon CR PC120301-4 (sent as an attachment to the agenda) dealing with this topic. This CR was submitted on November 3, 2001 and completed on April 17, 2002. Karen Clauson said Eschelon still maintains opinions expressed during the last series of meetings on this topic.

Tommy Thompson spoke on the current SGAT language. Since this was not sent as an attachment Tommy agreed he would forward to Doug Andreen who would distribute to all attendees. He said he would send the version that is applicable to all states except Washington and Arizona. He will send the specific wording for those two states also. There was conversation around the definition of “CLEC premises” in the document. It was agreed that the definition extends beyond COs to cover all buildings or similar structures that house Network facilities, owned, leased, or otherwise controlled by Qwest. It was also pointed out that one of the differences between the CLECs and Qwest is CLEC to CLEC direct connections. Karen Clauson stated that this is far from the only difference between Eschelon and Qwest concerning the CLEC-to-CLEC issue.

Karen asked the purpose of SGAT language in a CMP meeting and how the current discussion relates to negotiations that are going on between Qwest and Eschelon.

Steve said the SGAT is background since the current PCAT refers to the SGAT. He said nothing on the agenda today should affect negotiations. Karen asked how we are going to resolve in this forum since Eschelon is in negotiations and Covad is in arbitration on this issue. There was much discussion around this and Karen said that in reference to the PCAT, Eschelon’s position has not changed in that Eschelon submitted a CR (PC120301-4) and that Eschelon believes this is what we are operating under.

Steve answered that after this call Qwest would ask the CLECs to restate their position. Steve said after the meeting Qwest will gather comments and see if there is any movement in Qwest’s position. Steve said there may or may not be a change considering the position that arbitration has taken and how Qwest will respond.

Steve reviewed the current PCAT language. There were no questions. He said that in the redlined PCAT he tried to separate the CLEC to CLEC Direct connections from Cross Connections. He proceeded through the remainder of the redlined document. There were no questions.

Karen Clauson asked since we know there are major differences, how do you see us proceeding. Steve answered for the CLECs to send Qwest an annotated version of the PCAT and go from there. Karen added with the negotiations and arbitrations going forward if it would be a better use of time to let those finalize before continuing these meetings. It was agreed that these meetings would be suspended until arbitrations and negotiations have finalized. Tommy will not forward copies of the SGAT but Doug will publish minutes and cancel the other two meetings already scheduled.

The meeting was then adjourned.

8/18/04 CMP Meeting Steve Nelson presented the CR saying that the CR was previously communicated via a Level 2 notice but based on a CLEC facing call and CLEC comments it was withdrawn. Qwest believes that CLECs have the responsibility to design and regenerate CLEC to CLEC connections on a common ICDF frame. The CLECs believe it is a Qwest responsibility. Steve said that this CR will require a good amount of work since it will involve looking at FCC documents etc. He added that this is a sincere effort to move through this issue collaboratively to reach agreement. The CR will be moved to Presented status.


Open Product/Process CR PC062904-1 Detail

 
Title: Grandparent LADS in CO, UT and OR effective 9/7/04.
CR Number Current Status
Date
Area Impacted Products Impacted

PC062904-1 Withdrawn
7/21/2004
resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Andreen, Doug

Description Of Change

LADS (local area data services) will be grandfathered in Oregon, Colorado, and Utah effective September 7, 2004. Grandparenting the service means that existing customers will not be able to add new LADS circuits or move existing circuits. They will also not be able to renew their contract for existing LADS circuits. New customers will not be able to order LADS services at all for these 3 states. At this time, there is no sunset date set for the services.

Expected Deliverable: Implementation date 9/7/04


Status History

6/29/04 - CR submitted

6/29/04 - CR acknowledged

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.


Project Meetings

7/21/04 CMP Meeting Janean Van Dusen, Qwest moved to withdraw this CR. There were no objections. The CR will move to Withdrawn status.


Open Product/Process CR PC040504-1 Detail

 
Title: Grandparent Centrex Plus and Custom Centron
CR Number Current Status
Date
Area Impacted Products Impacted

PC040504-1 Completed
12/15/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Effective June 30, 2004 Centrex Plus will be grand parented in Arizona, Iowa, Oregon and Washington. Existing Centrex Plus month to month end users in Arizona and Washington must migrate on or before October 1, 2004 to another service. Effective June 30, 2006 Centrex Plus in Arizona and Washington will be sunset.

Effective June 30, 2004 Custom Centron will be grand parented in Arizona. Effective June 30, 2006 Centron Custom in Arizona will sunset.

Expected Deliverable:

June 30, 2004


Status History

04/05/04 - CR Submitted

04/06/04 - CR Acknowledged

04/13/04 - Held Clarification Meeting

04/21/04 - April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

05/14/04 - Qwest sent PROD.05.14.04.F.01672.ResaleCentPlus_CentronV17 proposed effective date 6/30/03

05/19/04 - May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

06/11/04 - Qwest generated notice PROD.06.11.04.F.01771.FNL_ReCentPlus_CentronV17

06/16/04 - June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

10/20/04 - October CMP Meeting minutes will be posted to the database

11/17/04 - November CMP Meeting minutes will be posted to the database

04/16/06 - PROD.04.14.06.F.03724.ResaleCentPlus_CentronV20


Project Meetings

April 14, 2006 Excerpt From PROD.04.14.06.F.03724.ResaleCentPlusCentronV20: " . . .the sunset date for Centrex Plus in WA has been changed to December 31, 2008, not June 30, 2006 . . ."

- December CMP Meeting Minutes Janean Van Dusen – Qwest advised the final state was completed on December 1. This CR will move to Completed Status.

11/17/04 November meeting minutes Cindy Macy – Qwest advised the remaining states are effective December 1. The CR will remain in CLEC Test Status.

10/20/04 CMP Meeting Minutes Janean Van Dusen said that this has been in CLEC Test but some of the states are not effective until December 1. The CR will remain in test status.

- 9/16/04 CMP Meeting Minutes Doug Andreen reported that the CR was effective September 1 and that the only customer affected is MCI with a minimal amount of customers. LeiLani Hines said that she was ok with working with Qwest to migrate those accounts. The CR will move to Test Status.

-- 8/18/04 CMP Meeting Doug Andreen reported there is no change to this CR. The final notice was sent July 30 and the CR will be affective September 1. Stephanie Prull said the first CR was scheduled to be affective much earlier and gave the CLECs until October 1 to have customers removed from these features. Bonnie Johnson remembered that Janean had stated that adjustments would be made to this date and that Qwest would work with the individual CLECs.

- 7/21/04 CMP Meeting Janean Van Dusen, Qwest said the final notice went out on 6/23. Grandparent effective date will be 9/1/04 for AZ, IA, and WA. The CR will stay in Development.

- 06/16/04 June CMP Meeting Janean Van Dusen with Qwest gave an update that dates have changed on this CR. Centrex Plus grandparenting will be effective 9/1/04 and a revised final notice will be sent on 6/23/04. Month to month USOC’s in AZ and WA will be effective 12/1/04, IA 3/1/05, OR has no date, and Sunset dates for AZ, IA, and WA are 6/30/06. OR has no date.

05/19/04 May CMP Meeting Janean Van Dusen with Qwest gave an update on this CR. Janean said this was going to be effective on 6/30/04 but there was a delay and currently have no new effective date. Janean said there was no effect on UNE-P Centrex Plus. Bonnie Johnson with Eschelon said that the notice contained a change in the USOC and we have not had to change USOCs. Janean said that AZ, IA, OR, WA, Centrex Plus will be grand parented on 6/30. In AZ and WA only month to month Centrex Plus will be eliminated and customers must be migrated to something else or term agreement. Janean will make sure to let service management know of CLECs that have any end users. Liz Balvin with MCI asked if there would be impact to end users or record change orders. Liz asked if the customer maintains existing service today or submits orders. Janean said the CLEC doesn’t have to do anything for the end user unless they are month to month. This should be invisible to the end user, except for anything that the CLECs decide to change. Bonnie Johnson would go through physical conversion if migrated and asked if service management would know soon. Janean said yes. This CR will move to Development Status.

04/21/04 April CMP Meeting Janean Van Dusen with Qwest presented this CR. Bonnie Johnson with Eschelon asked if UNE-P Centrex Plus was included. Janean did not believe the UNE-P product was included and will find out from Michael Whitt. This CR will move to Presented Status.


Open Product/Process CR PC040604-1 Detail

 
Title: Dispute (CLAIM) Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC040604-1 Completed
6/24/2005
Billing Claims dispute
Originator: Devine, Donna
Originator Company Name: Qwest Corporation
Owner: Devine, Donna
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

- Add Qwest’s Dispute ID number to acknowledgments, statuses and final resolution letters;

- Introduce required fields for submitting a claim on a standard form.

- Define pertinent terms, such as resolution, status, legal dispute;

- Standardize the escalation processes; and

- Finalize rules for submitting and processing claims involving multiple months

As a result Qwest will update the Product/Process Catalog (PCAT) describing the dispute process, including the process flow diagram discussed in LTPA

Expected Deliverable:

Date to be determined


Status History

04/06/04 - CR Submitted

04/07/04 - CR Acknowledged

4/21/04 -April CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

4/26/04 - Qwest Generated notice CMPR.04.26.04.F.01609.Ad_Hoc_Mtg

5/7/04 - Qwest generated notice CMPR.05.07.04.F.01657.Revised_Dispute_Document

5/14/04 - Qwest gererated notice CMPR.05.14.04.F.01684.Ad_Hoc_Mtg.

5/19/04 -May CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/16/04 -June CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

6/17/04 - Qwest generated notice GENL.06.17.04.F.01795.Claim_Process_Discussion

6/30/04 - Qwest generated notice General Notice: Mtgs: GN: Claim Process Docs:Effective 6-30-04

7/7/04 - Qwest generated notice General Notice: Mtgs: GN: Billing Claim Process: Effective 7/7/2004

7/12/04 - Qwest Generated notice General Notice: Mtgs: GN: Claim Process Documentation: Effective 7/12/04

7/21/04 -July CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

7/28/04 - Qwest generated notice CMPR.07.28.04.F.01927.Revised_Dispute_Documents

8/2/04 - Qwest Generated notice CMPR.08.02.04.F.01938.Dispute_Doc._Process_Flow

8/5/04 Qwest generated notice CMPR.08.05.04.F.01947.Ad_Hoc_Meeting

8/18/04 -August CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/14/04 - Qwest generated notice CMPR.09.14.04.F.02055.Ad_hoc_Meeting

9/16/04 -September CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

9/17/04 - Qwest generated notice CMPR.09.17.04.F.02071.Ad-Hoc_Meeting

9/22/04 - Held ad hoc meeting

11/10/04 -Qwest generated notice CMPR.11.10.04.F.02289.Ad_Hoc_Meeting

11/12/04 - Qwest generated notice CMPR.11.12.04.F.02299.Ad_Hoc_Meeting (rescheduled)

11/17/04 - Discussed at the November Product Process CMP Monthly Meeting.

11/22/04 - Qwest generated notice CMPR.11.19.04.F.02339.DocumentForAdHoc

12/9/04 - Ad Hoc Meeting Held. See Supplemental Information for Meeting Minutes.

12/15/04 - December CMP Meeting - Meeting minutes will be posted to this CR's Project Meetings section.

01/19/05 - Discussed in the January Product Process Monthly CMP Meeting

01/25/05 - PROS.01.25.05.F.02507.Dispute_Acknwlg_Res (Subject: MCC-Dispute Acknowledgement and Resolution Letters)

02/16/05 - Discussed in the February Product Process Monthly CMP Meeting

02/18/05 - PROS.02.18.05.F.02576.Dispute_Process_V1

03/16/2005 - Discussed in the Monthly Product/Process CMP Meeting

03/18/05 - PROS.03.18.05.F.02712.FNL_Dispute_Process_V1

04/01/05 - PROS.04.01.05.F.Billing_PCATs_Disputes (Level 1)

04/01/05 - PROD.04.01.05.F.PAL_PCATs_Disputes (Level 1)

04/20/2005 - Discussed in the Monthly Product/Process CMP Meeting

05/18/2005 - Discussed in the Monthly Product Process CMP Meeting

06/15/2005 - Discussed in the Monthly Product Process CMP Meeting

06/24/2005 - Email Received from Eschelon: In CMP last week, I committed to getting back to Qwest off line on whether Eschelon agrees to close the CR. Here is Eschelon's response. Please include our response in the CR status history. Eschelon's position has not changed on this CR Qwest implemented. Qwest implemented this CR over Eschelon's objection and Qwest can close the CR over our objection. Eschelon's ICA controls and this process does not apply to Eschelon or any CLEC that has billing dispute provisions in its contract. Thanks, Bonnie J. Johnson, Director Carrier Relations, Eschelon Telecom, Inc.


Project Meetings

- June 15, 2005 Monthly Product Process CMP Meeting discussion: Donna Devine-Qwest stated that this CR has been in CLEC Test over 60-days and asked for closure. Bonnie Johnson-Eschelon stated that she would like to check with her billing group and could close off-line. Jill Martain-Qwest stated that this CR would remain in CLEC Test and that Qwest would work with Eschelon off-line to close the CR.

- May 18, 2005 Monthly Product Process CMP Meeting discussion: Donna Devine-Qwest stated that this CR has been in CLEC Test for over a month and asked for CR closure. Bonnie Johnson-Eschelon asked that the CR not yet be closed and that we wait until they get through an entire cycle or 2. Bonnie stated that Eschelon just recently used the process and asked that it be kept open. Donna Devine-Qwest agreed to keep the CR open another month. This CR remains in CLEC Test.

-- April 20, 2005 Product Process CMP Meeting Discussion: Sue Kriebel-Qwest stated that this change was implemented on April 4th and would like to move the CR to CLEC Test. Liz Balvin-Covad stated (Change to minutes submitted by Covad 4/28/05) that this CR was discussed in the CLEC forum in the fact that this change impacted access claims and the fact the CLECs were not notified. Liz stated that when she was involved in the discussions that took nearly a year and the changes were specific to local wholesale. Sue Kriebel-Qwest stated that CMP discussions were for local but this process was implemented for other customers.Mark Coyne-Qwest stated that a Courtesy Notice was sent. Bonnie Johnson-Eschelon asked what a Courtesy Notice was. Mark Coyne-Qwest stated is a notice and go. Sue Kriebel-Qwest stated that the Courtesy Notice was for the non-CMP process. Liz Balvin-Covad stated that (Change to minutes submitted by Covad 4/28/05) the negotiated procedures for local/wholesale took nearly a year and couldn’t understand how Qwest believed IXCs would only need a 1-day notice and go. Liz stated that she understood MCI has numerous claims and noted that they all failed upon implementation by Qwest. Liz stated that the PCAT updates were specific to wholesale. Bonnie Johnson-Eschelon stated that in all Companies, they don’t do the same functions (Change to minutes submitted by Eschelon 4/29/05 and were not aware of these meetings, so a 1-day notice is not good. Sue Kriebel-Qwest asked to clarify that all Companies do not provide local and access services. Bonnie Johnson-Eschelon stated that was correct. Jill Martain-Qwest stated that Qwest did appreciate the feedback and that Qwest would continue to discuss internally, Jill advised this CR moves to CLEC Test.

March 16, 2005 Product Process CMP Meeting Discussion: Donna Devine-Qwest stated that the CLEC Comment cycle was through March 5th and that Qwest is reviewing the comments. Donna stated that this CR remains in Development status.

-- February 16, 2005 Product Process CMP Meeting Discussion: Donna Devine-Qwest stated that Qwest was on target to announce the process on February 18th.Jill Martain-Qwest stated that this CR remains in Development status and that the Level 4 notice would be sent.

- January 19, 2005 Product Process CMP Meeting Discussion Donna Devine/Qwest stated that she is targeting the Level 4 Notice to be sent the week of February 14th. Jill Martain/Qwest asked for questions. Bonnie Johnson/Eschelon thanked Donna for sending responses to their questions and stated that she does not believe that all were responded to. Bonnie stated that she would comment when the notice is sent. Bonnie then thanked Donna for her efforts. [1-28-05 Comment Received from Eschelon: Bonnie Johnson/Eschelon thanked Donna for sending responses to their questions and stated that she does not believe Qwest answered the comments. Bonnie s