Wholesale: Products & Services

Archived System CR SCR060112-1 Detail

 
Title: Modify DL LNLN, LNFN and LTEXT fields – business rules for Terminal S
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR060112-1 Completed
3/20/2013
16 -   3/33 IMA User Profile
Originator: Gomez, Lee
Originator Company Name: CenturyLink
Owner: Gomez, Lee
Director:
CR PM: Lorence, Susan
Description Of Change
Modify DL.LNLN, DL.LNFN and DL.LTEXT business rules to not require reverse stylization for a terminal s when followed by a symbol. For example: Charlie’s-Road House

FROM:

• ‘ (apostrophe): will capitalize next letter unless it is a terminal s (e.g., Hardee’s).

Note: By definition, an S is only terminal when it is followed by a space. If the apostrophe S is followed by anything else, such as a hyphen, parenthesis,etc., it is not considered terminal.

An asterisk would be required for reverse stylization.

TO:

• ‘ (apostrophe): will capitalize next letter unless it is a terminal s (e.g., Hardee’s).

Note: By definition, an S is only terminal when it is followed by any symbol; space, hyphen, parenthesis, etc.

If the apostrophe S is followed by anything else, letter or number, it is not considered terminal. An asterisk would be required for reverse stylization.

Status History

Date Action Description
6/1/2012 CR Submitted CR Submitted 
6/5/2012 CR Acknowledged CR Acknowledged 
6/20/2012 Status Changed Status changed to Presented. 
6/20/2012 Discussed at Monthly CMP Meeting Presented at June Systems CMP Meeting – See Attachment C in the Distribution package 
6/20/2012 LOE Issued LOE issued of 16 hours 
7/13/2012 Status Changed Status changed to Packaged - IMA R33.0 
12/10/2012 Status Changed Status changed to CLEC Test 
1/16/2013 Discussed at Monthly CMP Meeting Discussed at the January Systems CMP Meeting - See Attachment G in the Distribution Package 
2/20/2013 Discussed at Monthly CMP Meeting Discussed at the February Systems CMP Meeting - See Attachment G in the Distribution Package 
3/20/2013 Status Changed Status changed to Completed. 
3/20/2013 Discussed at Monthly CMP Meeting Discussed at the March Systems CMP Meeting - See Attachment G in the Distribution Package. 

Project Meetings

3/20/13 System Monthly Meeting Mark Coyne - CenturyLink said these CRs are associated with IMA Release 33 which was implemented on December 10, 2012. Mark we discussed these in February and were OK to close then but asked if there were any questions. There were none.

2/20/13 System Monthly Meeting Mark Coyne - CenturyLink said we would like to close these six IMA CRs that are associated with IMA Release 33 which was implemented on December 10, 2012. Mark asked if there were any objections to moving them to Completed status.

Kim Isaacs – Integra asked if any XML companies had migrated to the release and if there were some customers migrated, were there any problems.

Carrie Bousfield – CenturyLink said there were two customers on the release as of January 19 and said there were quite a number migrating on March 23. Carrie said there were no problems.

Kim Isaacs – Integra said based on that, she did not have any concerns with closing the CRs.

01/16/13 Systems CMP Meeting Mark Coyne - CenturyLink said these six IMA CRs were associated with IMA Release 33 which was implemented on December 10, 2012. He said we would consider them in February for closure.

06/20/2012 Monthly CMP Systems Meeting Under Attachment D, Lee Gomez – CenturyLink presented the system CR. Lee asked if there were any questions on either CR. There were none.

Under Attachment I, Mark Coyne – CenturyLink stated that the LOE for the LSOG Phase 1 CR is 2200 hours. LOEs for SCR101111-4IG and SCR101111-5IG are still under evaluation. He stated that SCR060112-1 and SCR060112-2 that were presented on the call earlier had LOEs of 16 hours and 459 hours.

CenturyLink Response

Information Current as of 1/11/2021