Wholesale: Products & Services

Archived System CR SCR060804-01 Detail

 
Title: Mechanize Post Completion Notices
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR060804-01 Withdrawn
6/24/2005
3200 - 4000   3/ All
Originator: Martinez, Denise
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Stecklein, Lynn
Description Of Change
This Enhancement will allow Post Completion Notices to be sent mechanically as opposed to the manual emailing or faxing of notices today.

Status History

Date Action Description
6/8/2004 CR Submitted  
6/10/2004 CR Acknowledged  
6/11/2004 Clarification Meeting Scheduled  
6/18/2004 Clarification Meeting Held  
7/22/2004 Discussed at Monthly CMP Meeting Discussed at the July CMP Systems Meeting - See attachment C of the July Distribution Package 
7/22/2004 Status Changed Status changed to presented 
8/18/2004 Discussed at Monthly CMP Meeting Discussed at the August CMP Systems Meeting - See attachment C of theAugust Distribution Package 
10/27/2004 Status Changed Status changed to pending prioritization 
5/27/2005 Status Changed Status Changed to Pending Withdrawal 
6/15/2005 Discussed at Monthly CMP Meeting Discussed at the June CMP Systems Meeting - See attachment G in the Systems Distribution Package 

Project Meetings

6/24/05 E-mail from Eschelon

In CMP last week, I told Qwest there were two CRs Eschelon could consider adopting. I just wanted to let you know, Eschelon has decided not to do so at this time.

Thanks,

Bonnie J. Johnson Director Carrier Relations Eschelon Telecom, Inc. Phone 612 436-6218 Fax 612 436-6318 Cell 612 743-6724 bjjohnson@eschelon.com

6/15/05 Systems CMP Meeting Jill Martain - Qwest stated that we did some analysis on this CR and determined that the volumes are low. She also said that the manual process is in place and is working well. Jill said that Qwest would like to withdraw this CR. Bonnie Johnson - Eschelon said that they may want to pick up this CR. Jill Martain - Qwest said that Eschelon should send an e-mail to CMPCR@qwest.com if they wanted to sponsor this CR.

2/16/05 Systems CMP Meeting - IMA 18.0 Candidate Discussion

Jill Martain-Qwest stated that Qwest rates this CR high.

8/18/04 Systems CMP Meeting

Jill Martain/Qwest stated that the LOE for this CR is 3200 to 4000 hours and that this action item will be closed.

7/22/04 CMP Systems Meeting

Denise Martinez/Qwest stated that this enhancement will allow Post Completion Notices to be sent mechanically as opposed to the manual emailing or faxing of notices today. Denise said that this change will be for IMA and IIS for faxing. Susie Bliss/Qwest said that this change is what MCI requested. Liz Balvin/MCI agreed and said that she also understood that the 16.0 IMA Release will accommodate the inappropriate use of the Post Completion Notice and that mechanization will help get us in synch. Denise Martinez/Qwest stated that 16.0 will reduce the number of Post Completion Notices. Denise said that this candidate will allow the Post Completion Notice to be sent mechanically and will improve the process of sending the notices. Liz Balvin/MCI asked if they still needed to certify. Connie Winston/Qwest said she thought so but that we are still defining. Denise Martinez/Qwest said that we will be introducing new fields on the notice and they will provide more information. Jill Martain/Qwest said that if this candidate is voted into a release, we could have additional discussion to walk through the definition. This CR will move to presented status.

6/18/04 Clarification Meeting

Attendees: Denise Martinez - Qwest, Tom Shuford - Qwest, Shonna Pasionek - Qwest, Bob Hercher - Qwest, Deb Roth - Qwest, Lynn Stecklein - Qwest

Review Description of Change

Denise Martinez - Qwest stated that this enhancement will allow Post Completion Notices to be sent mechanically as opposed to the manual emailing or faxing of notices today.

Discussion Denise Martinez - Qwest stated that she has been working the CLECs to determine when they want to receive a Post Completion Notices. Denise stated that several meetings have been held with the CLECs and have come to an agreement of when the CLECs want to see the Post Completion Notice. Denise stated that the CLECs want more detail on the Post Completion Notices and have asked for them to be mechanized. Deb Roth - Qwest asked if this notice would be a new or similar to what exists today. Denise Martinez - Qwest stated that this would be a new notice and that the notice will look more like a FOC. She stated that the notice would specifically point out what was changing (I.e. order number changing) Tom Shuford - Qwest asked how similar the Post Completion Notice would be to the FOC. Denise Martinez - Qwest stated that the notice would have similar elements. Confirm Areas and Products Impacted. Lynn Stecklein - Qwest asked what products would be impacted. (See Product List) Denise Martinez - Qwest stated that any product that receives a Post Completion Notice would be impacted.

Establish Action Plan

Denise Martinez - Qwest will present this CR in the July CMP Systems Meeting.

CenturyLink Response

DRAFT Response

August 12, 2004

RE: SCR0060804-01 Mechanize Post Completion Notices

Qwest has reviewed the information submitted as part of Change Request (SCR060804-01 Mechanize Post Completion Notices). Based upon the scope of this CR as agreed to in the Clarification Meeting (held June 18, 2004) Qwest is able to provide an estimated Level of Effort (LOE) of 3200 to 4000 hours for this IMA Change Request.

At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request.

This Change Request is an eligible candidate for the IMA 18.0 prioritization vote.

Sincerely, Qwest

Information Current as of 1/11/2021