Wholesale: Products & Services

Archived System CR SCR072505-1X Detail

 
Title: Cable Pair & Binding Post Identification (CR Crossed over from PC072505 1X)
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR072505-1X Completed
2/19/2014
2000 - 2248   3/35 Ordering
Originator: Lynn, Lisa
Originator Company Name: Granite Telecommunications
Owner: Martinez, Denise
Director:
CR PM: Lorence, Susan
Description Of Change
1/2/2013 UPDATE: Receive the identification of Cable Pair and Binding Post information upon Completion not when the order reaches Confirmed status.

Product types: We use the C/P/BP information for POTs; Centrex; Trunks and Resale. Please note this is not currently needed for T1s.

*****Original CR

Identification of cable pair and binding post information when the order reaches confirmed status (FOC). The cable pair and binding post information is currently provided via repair after the order is completed.

Status History

Date Action Description
1/22/2013 Discussed at Monthly CMP Meeting Info received from customer to move forward with CR. For additional history, see PC072505-1X 
2/20/2013 Discussed at Monthly CMP Meeting CR discussed in February monthly CMP meeting. Crossed over from Product Process CR PC072505-1 to Systems CR. See original Product Process CR for HISTORY. 
3/15/2013 Status Changed Status changed to Evaluation. 
3/20/2013 Discussed at Monthly CMP Meeting Discussed at the March Systems CMP Meeting - See Attachment E in the Distribution Package. 
3/20/2013 LOE Issued This CR has an LOE of 2248 hours. 
4/17/2013 Discussed at Monthly CMP Meeting Discussed at the April Systems CMP Meeting - See Attachment I in the Distribution Package. 
5/10/2013 Status Changed Status changed to Packaged in IMA Release 35. 
6/1/2013 Status Changed Status changed to Development 
10/28/2013 Status Changed Status changed to CLEC Test. 
11/19/2013 CLEC Requested Info Email from CLEC - Request for XML example of how CenturyLink will be sending data. 
11/20/2013 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See Attachment G in the Distribution Package. 
11/21/2013 Info Sent to CLEC Example of XML data sent to Granite as requested. 
12/11/2013 Discussed at Monthly CMP Meeting Discussed in the December System CMP Meeting - See Attachment G in the Distribution Package. 
1/15/2014 Discussed at Monthly CMP Meeting Discussed in the January System CMP Meeting - See Attachment G in the Distribution Package. 
2/19/2014 Status Changed Status changed to Completed. 
2/19/2014 Action Item Created Discussed at the February Systems CMP Meeting - See Attachment G in the Distribution Package. 

Project Meetings

2/19/2014 Monthly Systems CMP Meeting Mark Coyne – CenturyLink said this CR was implemented as part of IMA Release 35.0 which was effective October 28, 2013. The CR has remained open until Granite migrated to Release 35 which just recently occurred. Mark said we would like to move this CR to Completed status.

Lisa Lynn - Granite said it was OK to move the CR to Completed status.

1/15/2014 Monthly Systems CMP Meeting Mark Coyne – CenturyLink relayed this CR was implemented as part of IMA Release 35.0 which was effective October 28, 2013. Granite had requested this CR remain open until February after they migrate to Release 35. Mark asked if there was anyone from Granite on the call and there was no one. Mark said this CR would be revisited in February.

12/11/2013 Monthly Systems CMP Meeting Mark Coyne – CenturyLink said there are a large number of CRs on the list associated with the IMA release that went in late October. He said in the November monthly meeting, Granite had requested that we keep SCR072505-1X, Cable Pair & Binding Post Identification, open until they migrated at the end of January. Mark asked if there were any objections to closing the remaining CRs on the list that includes all of the IMA CRs as well as SCR030113-1IG associated with CABS BOS release in November and SCR062713-1SC associated with the MTG release in November. Mark asked if there were any objections. There were none.

11/20/2013 Monthly Systems CMP Meeting Mark Coyne – CenturyLink said there are a large number of CRs on the list associated with the IMA release that went in late last month. He asked if we needed to hold off until December to move them to Completed or was it was OK to move them to Completed.

Lisa Lynn – Granite said they are not scheduled to migrate to IMA Release 35 until January 25, 2014 and requested the Granite CR SCR072505-1X remain open until then. She requested an example of what the data would look like in XML.

Chuck Anderson – CenturyLink said he would send Lisa an example.

3/20/2013 Monthly Systems CMP Meeting

Mark Coyne – CenturyLink said this is the Granite Change Request that was crossed over last month. The CR will be considered for IMA Release 35.0 and has an LOE of 2248 hours. Mark asked if there were any questions. There were none.

CenturyLink Response

2/20/13 Product Process Monthly CMP Meeting

February 15, 2013 To: Lisa Lynn Cc: New Cr, Cmp Subject: CenturyLink Draft Response to Granite Change Request (CR) PC072505-1 Cable Pair & Binding Post Identification

Good morning, Lisa, With the February CMP Monthly meeting scheduled for February 20, 2013, we are proposing that your Change Request PC072505-1, Cable Pair & Binding Post Identification, be crossed over to a System CR. We are proceeding with the evaluation of the CR as a system change to IMA. As a crossover, the Product Process CR will be closed and CenturyLink will open CR SCR072505-1X on your behalf with a reference to the original Product Process CR. Please let me know if you have any questions. Here is the link to the calendar entry for this meeting http://wholesalecalendar.centurylinkapps.com/detail/385/2013-02-20. We hope you are able to attend. Thank you, Susan Lorence CenturyLink CR Project Manager **

Information Current as of 1/11/2021