Archived System CR SCR092402-01IG Detail

 
Title: Update EXACT for ASOG 26
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR092402-01IG Completed
4/17/2003
-   6/ All
Originator: Veik, Gary
Originator Company Name: Qwest Corporation
Owner: Thompson, Jeff
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
This industry standard change covers multiple products with numerous changes, and all of this information is currently available on the OBF website (http://www.atis.org) for use by all interested parties. Decisions as to when this release was established by OBF is also included (May 2002).

In order to comply with industry standards as directed by OBF, ASOG 26 is to be implemented on March 10, 2003. All telecommunication companies involved with the ASR process must convert to ASOG 26 at this time.

The anticipated timeline to be followed for this CR can be found on the Qwest OSS Release Calendar at:

http://www.qwest.com/wholesale/cmp/osscalendar.html

The key anticipated dates are:

March 10, 2003 Target Implementation

Status History

Date Action Description
9/24/2002 CR Submitted  
9/24/2002 CR Acknowledged  
9/26/2002 Communicator Issued CMPR.09.26.02.F.01330.ASOG26_CR_EXACT 
9/26/2002 Clarification Meeting Held  
10/17/2002 Discussed at Monthly CMP Meeting SCR092402-01IG discussed at October Systems CMP Monthly meeting; please see Systems CMP Distribution Package October CMP -- Attachment D 
12/20/2002 Communicator Issued SYST.12.20.02.F.04225.EXACT73DyDftTechSpec 
1/24/2003 Communicator Issued SYST.01.24.03.F.04242.EXACTFinalTechSpec 
3/13/2003 Status Changed Status changed to CLEC Test due to 3/10/03 deployment 
3/20/2003 Discussed at Monthly CMP Meeting SCR092402-01IG discussed at March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP. 
4/17/2003 Discussed at Monthly CMP Meeting SCR092402-01IG discussed at April Systems CMP Monthly meeting; please see April Systems CMP Distribution Package, Attachment G. 

Project Meetings

April 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest stated that this CR deployed on March 10, 2003, there are no issues and this CR is ok to close.

March 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR was implemented on March 10, 2003.

October 17, 2002 Systems CMP Meeting Discussion: Michael Buck/Qwest noted that the Industry Guidelines have been stricken from the Process document. Qwest will continue to identify as Industry Guideline but they will not receive special treatment, they will be treated and prioritized just like non Industry Guideline CRs. Michael Buck/Qwest stated that there were no objections received to proceed with this request as an Industry Guideline CR. Gary Veik/Qwest presented the CR and stated that OBF has agreed to ASOG 26. For EXACT, Qwest will follow the Industry Guidelines for that release. There will be nothing specific to Qwest. Targeted implementation is March 10, 2002. Gary asked if there were any question. None were brought forward. Michael Buck/Qwest stated that this CR would move to Presented status.

- Clarification Meeting 09/26/02 CR description was reviewed. There were no additional questions or comments.

CenturyLink Response

Draft Response

October 2, 2002

This is a Telcordia development effort. Qwest will implement this change on March 10, 2003 to support the Industry Standards through OBF. Information is available on the OBF website (http://www.atis.org) for use by all interested parties.

Sincerely, Qwest

Information Current as of 1/11/2021